Osisko Gold approves C$990M Cariboo mine build

(Neutral)
(Neutral)
Form Type
6-K

Rhea-AI Filing Summary

Osisko Gold Group Inc. (OGG) approved full-scale construction of its 100%-owned Cariboo Gold Project in British Columbia, targeting first gold in early 2029 and commercial production in H2 2029 after an expected 30‑month construction period from August 1, 2026. The remaining go-forward capital obligation is estimated at C$990 million, after C$272 million spent to July 31, 2026 and assuming about C$117 million of equipment leasing.

At a spot gold price of US$4,350/oz, Cariboo shows an after-tax NPV5% of C$3.2 billion, after-tax IRR of 42.7%, payback of 1.8 years from commercial production, and average annual free cash flow of C$642 million in the first five years. Mine life is 10 years with average throughput of 4,900 tpd and total payable gold of 1,894 koz. Construction is expected to support 613 peak construction jobs and 525 permanent operating jobs.

To support funding, Urion agreed to invest about US$30 million for 9,554,141 common shares at US$3.14, alongside offtake agreements with Trafigura for 100% of gold concentrate and doré in the first four years and non-binding terms for a potential up to US$120 million subordinated gold prepay facility. From August 1, 2026 to commercial production, total capital sources are estimated at C$1,637 million versus uses of C$1,435 million, implying projected surplus liquidity of about C$201 million.

Positive

  • Formal construction decision on Cariboo moves OGG from development to execution on a fully permitted, 10‑year underground gold mine with 1,894 koz payable gold and a flagship asset in a mining-friendly jurisdiction.
  • At spot gold of US$4,350/oz, updated economics show after-tax NPV5% of C$3.2 billion, IRR of 42.7% and average first‑five‑year free cash flow of C$642 million, indicating strong leverage to gold price.
  • Estimated funding plan totals about C$1,637 million of sources versus C$1,435 million of uses from August 1, 2026 to commercial production, leaving projected surplus liquidity of C$201 million and supporting balance sheet strength during build-out.
  • Trafigura partnership brings a ~US$30 million equity investment, four‑year 100% gold concentrate and doré offtake, and non-binding terms for an up to US$120 million subordinated prepay facility, providing strategic support and potential non-dilutive capital.

Negative

  • The remaining C$990 million go-forward capital obligation and extended timeline to first gold in Q1 2029 and commercial production in H2 2029 concentrate execution, cost, and schedule risk during a 30‑month construction and ramp‑up period.
  • The company will review Cariboo-related non-financial assets for potential impairment as of September 30, 2026 under IFRS, and any resulting non-cash impairment charge, while not affecting cash flow, could impact reported earnings.
  • Key elements of the funding plan depend on successful closing of the Urion equity investment and execution of definitive documentation for the up to US$120 million gold prepay facility, which are not yet assured.

Filing Explained

The planned 9,554,141-share investment remains subject to exchange acceptance, so ownership dilution is conditional rather than completed.

As a Form 6-K interim report, this filing confirms the formal decision to proceed with full-scale construction, while reporting overall project completion at 22% as of July 31, 2026.

The planned equity investment is an agreement, not a completed issuance: Urion has agreed to acquire 9,554,141 common shares at US$3.14 per share, subject to final acceptance by the TSX Venture Exchange and the New York Stock Exchange.

If issued, the additional shares would increase the total share count and reduce existing holders' percentage ownership absent offsetting changes.

The update reports approximately 3.0 kilometres of underground development, procurement completion of approximately 44%, and approximately C$325 million committed to date, indicating that execution has begun but remains underway.

The company will review its Cariboo non-financial assets as of September 30, 2026 while preparing third-quarter results; any impairment charge would be non-cash and would not affect cash flows.

Go-forward capital obligation C$990 million Remaining capital from August 1, 2026 to commercial production for Cariboo
After-tax NPV5% (spot scenario) C$3.181 billion Cariboo economics at US$4,350/oz gold
After-tax IRR (spot scenario) 42.7% Cariboo Project internal rate of return at US$4,350/oz gold
Average free cash flow, first 5 years C$642 million per year Modeled Cariboo free cash flow 2029–2034 at spot scenario
Equity investment by Urion US$30 million 9,554,141 shares at US$3.14 each, subject to exchange approvals
Potential gold prepay facility Up to US$120 million Non-binding subordinated facility with SOFR + 6.00% interest rate
Total capital sources vs uses C$1,637 million sources; C$1,435 million uses From August 1, 2026 to commercial production, implying C$201 million surplus liquidity
Total payable gold (LOM) 1,894,000 ounces Cariboo life-of-mine payable gold from feasibility metrics
go-forward capital obligation financial
"The Project's remaining go-forward capital obligation is estimated at $990 million"
all-in sustaining costs financial
"All-in sustaining costs 2 | US$/oz | $1,157 | $1,163 | $1,202"
All-in sustaining costs (AISC) is a per-unit measure used mainly in the mining sector that captures the full ongoing cost to produce a unit of metal, including operating expenses, sustaining capital (maintenance of current operations), and a share of corporate overhead and site-level costs. Investors use AISC to judge whether production generates real profit and sustainable cash flow—think of it as the total monthly household cost to keep a home running, not just the utility bill.
Prepay Facility financial
"non-binding terms in respect of a potential Prepay Facility of up to US$120 million"
A prepay facility is a financing arrangement in which a lender advances cash up front to a company in exchange for rights to future revenues, sales receipts, or product deliveries; the loan is repaid out of those future cash flows. Think of it like getting paid early for money the business expects to receive later, often at a discount. It matters to investors because it changes a company’s liquidity, committed future cash streams, and balance-sheet leverage without issuing equity.
Net present value (NPV5%) financial
"Net present value (NPV5%) | $ mm | $943 | $2,323 | $3,181"
internal rate of return (IRR) financial
"Internal rate of return (IRR) | % | 22.1% | 34.7% | 42.7%"
The internal rate of return (IRR) is the annualized percentage return that makes the total value of a project's or investment's future cash flows equal the amount invested today — in other words, the break-even interest rate for that investment. Investors use IRR like a single-number speedometer to compare opportunities: a higher IRR means a project is expected to generate a stronger annual return, helping decide which investments are likely more attractive relative to required returns or alternatives.
Total Recordable Injury Frequency Rate other
"The Total Recordable Injury Frequency Rate for the Project sits at 1.21"
Total recordable injury frequency rate is a workplace-safety metric that counts the number of injuries requiring medical treatment, restricted work, or lost time, scaled to a standard amount of employee hours (commonly per million hours worked). Think of it like counting car accidents per miles driven: it lets investors compare how safely different operations run, signaling potential costs, production disruptions, regulatory risk, and reputational exposure tied to worker safety.

FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

What major decision did Osisko Gold Group (OGG) announce for the Cariboo Gold Project?

Osisko Gold’s board made a formal positive decision to proceed with full-scale construction of its 100%-owned Cariboo Gold Project, targeting first gold in early 2029 and commercial production in H2 2029 after an expected 30‑month construction period from August 1, 2026.

What is the remaining capital cost to build Osisko Gold’s (OGG) Cariboo mine?

The remaining go-forward capital obligation for Cariboo is estimated at C$990 million, net of about C$272 million already incurred to July 31, 2026. This figure includes a 16.5% contingency and assumes approximately C$117 million of major equipment is financed through leasing.

How strong are the updated Cariboo economics for OGG at current gold prices?

At a spot gold price of US$4,350/oz, Cariboo’s after-tax NPV5% is C$3.2 billion, after-tax IRR is 42.7%, payback is 1.8 years from commercial production, and average annual free cash flow in the first five years is modeled at C$642 million.

What financing did Osisko Gold (OGG) agree with Trafigura and Urion?

Urion agreed to subscribe for 9,554,141 common shares at US$3.14 each for gross proceeds of about US$30 million, plus Trafigura secured offtake for 100% of gold concentrate and doré for four years and non-binding terms for an up to US$120 million subordinated gold prepay facility.

What is Osisko Gold’s (OGG) projected funding and liquidity for Cariboo through commercial production?

From August 1, 2026 to forecast commercial production, total capital sources are estimated at about C$1,637 million versus C$1,435 million of uses, implying projected surplus liquidity of approximately C$201 million, assuming closing of the equity investment and execution of the prepay facility.

What production profile and costs are expected at Osisko Gold’s Cariboo Project?

Cariboo has a modeled 10‑year mine life, annual throughput of 4,900 tpd, total payable gold of 1,894 koz, and average production of 190 koz/year (202 koz in first five years). Total cash costs range around US$947–996/oz and AISC around US$1,157–1,202/oz under the scenarios presented.

How advanced is construction and development at the Cariboo Gold Project as of mid-2026?

As of July 31, 2026, overall project completion is estimated at 22%, with about 3.0 km of underground development, 40% detailed engineering, approximately 44% of 466 contract packages committed, and around C$325 million already committed to long-lead and major construction contracts.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google
Learn about SEC filing dates
 

UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549

Form 6-K

REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO RULE 13a-16 OR 15d-16 UNDER THE SECURITIES EXCHANGE ACT OF 1934

For the month of September 2026

Commission File Number: 001-41369

Osisko Gold Group Inc.
(Translation of registrant's name into English)

155 University Avenue, Suite 1450, Toronto, Ontario M5H 3B7
(Address of principal executive office)

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.
Form 20-F [   ]      Form 40-F [ X ]

 

 


EXHIBIT INDEX 

Exhibit Number Description
   
99.1 Press Release dated September 14, 2026

SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

      Osisko Gold Group Inc.    
  (Registrant)
   
  
Date: September 14, 2026     /s/ Alexander Dann    
  Alexander Dann
  Chief Financial Officer and VP Finance
  

EXHIBIT 99.1

Osisko Gold Announces Formal Construction Decision and Development Update for the Cariboo Gold Project

(All dollar amounts are expressed in Canadian dollars, unless stated otherwise)


HIGHLIGHTS
  • Positive formal construction decision on the Cariboo Gold Project made by the Board of Directors, with an expected first gold pour in Q1 2029 and commercial production in H2 2029
  • US$30 million strategic private placement from an affiliate of Trafigura, concentrate and doré off-take from Trafigura, and potential prepayment facility of up to US$120 million
  • Go-forward capital obligation update for the Cariboo Gold Project of $990 million, supported by total available and proposed estimated sources of capital of up to $1,637 million, including $837 million in cash & equivalents
  • Project completion estimated at 22% as of July 31, 2026; Detailed engineering is approximately 40% complete; Procurement and commitments for long-lead items is progressing with an overall completion of approximately 44%; $325 million has been committed to date
  •  


    TORONTO, Sept. 14, 2026 (GLOBE NEWSWIRE) -- Osisko Gold Group Inc. (NYSE: OGG, TSXV: OGG) ("Osisko Gold" or the "Company") is pleased to announce that its Board of Directors has made a formal positive decision to proceed with the construction of the Company's 100%-owned Cariboo Gold Project ("Cariboo" or the "Project"), located in central British Columbia, Canada.

    Sean Roosen, Chairman and CEO, commented: "The Board's formal positive decision to commence full-scale construction of our flagship Cariboo Gold Project represents a defining milestone for Osisko Gold and a pivotal inflection point toward our objective of becoming an intermediate gold producer. This decision is a culmination of more than a decade of de-risking work on the Project, from early exploration when the first drills hit the ground in 2015, through permitting and technical studies, and into project financing and pre-construction. It reflects our confidence in the significant long-term value Cariboo can deliver to our shareholders and other stakeholders, and in the transformational impact it can have on the future of Osisko Gold. I'd like to commend our talented team for their professionalism, dedication and extensive contributions over the years that have brought us to this important milestone."

    "With this step forward, supported by our strong balance sheet position and other sources of available and proposed funding, our focus is now firmly on disciplined project execution toward first gold in early 2029. Based on an estimated remaining go-forward capital obligation of C$990 million and spot gold prices of US$4,350/oz, the Project demonstrates robust economics with after-tax NPV5% of C$3.2 billion, after-tax IRR of 42.7%, and average annual free cash flow of C$642 million in the first 5 years, underscoring its significant leverage to the gold price. Construction is expected to support 613 direct jobs at its peak, followed by 525 permanent jobs during operations, while generating substantial direct and indirect economic benefits for local communities and the Province of British Columbia. Bringing Cariboo through construction and into production represents only the first step in establishing a strong platform for the Company's long-term growth strategy. In parallel, we continue to accelerate ongoing conversion drilling within the current deposit and advance exploration of the substantial potential at depth and along strike within the existing permit footprint, as well as across the broader Cariboo regional property. We look forward to providing further regular updates on our progress."

    Project Go-Forward Capital Obligation Estimate Update

    The Project's remaining go-forward capital obligation is estimated at $990 million, net of approximately $272 million in costs incurred up to and including July 31, 2026, inclusive of contingency of approximately 16.5%, and assuming the leasing of major mining equipment of approximately $117 million. Relative to the initial cost estimate outlined in the 2025 Optimized Feasibility Study (as defined herein), the go-forward update reflects costs incurred to date, progress achieved on detailed engineering and the procurement of major contracts, updates to certain cost assumptions to account for market inflation due to passage of time and broader industry and labour trends, inclusion of costs related to a PCM contract, and the reclassification of certain expenditures previously included in operating costs, principally those associated with the construction of the transmission line. The update also reflects certain modifications to the construction schedule, resulting in an anticipated 30-month construction period from August 1, 2026 (from 24 months in the 2025 FS) to first gold pour in Q1 2029 and 36 months (from 34 months in the 2025 FS) to commercial production in H2 2029.

    Table 1: Go-forward Capital Obligation Estimate Update – Summary1,6
    Items Go-forward Capital Obligation
    (C$ mm)
    Go-forward Capital Obligation
    (US$ mm)2
    Underground mine & development3 $390 $283
    Water and waste management $124 $90
    Power and electrical $98 $71
    Surface infrastructure $47 $34
    Process plant – Mine Site Complex $213 $154
    Construction indirects $215 $156
    Contingency (16.5%) $82 $59
    Capital Costs $1,169 $847
    Pre-production net revenue4 ($231) ($167)
    Pre-production capitalized operating costs4 $169 $122
    Equipment financing5 ($117) ($85)
    Go-forward Capital Obligation Update $990 $717
    1. From August 1, 2026.
    2. Assuming a USD:CAD exchange rate of C$1.38 per US$1.00.
    3. Underground mine and development costs already include an embedded contingency.
    4. The pre-production period is defined as the period prior to the achievement of a minimum of 30 consecutive days of operations during which the mill operates at an average of at least 60% of nameplate throughput of 4,900 tpd. During this ramp-up phase operating costs are capitalized and netted against revenues.
    5. Equipment lease financing includes certain assumptions on mining and other equipment contemplated under currently negotiated, non-binding term sheets, and remain subject to change as negotiations progress. The equipment leasing market remains robust, and the Company continues to evaluate opportunities that would enhance its financial flexibility throughout the construction period and thereafter.
    6. Totals may not add up due to rounding.
    7. In connection with the go-forward capital obligation update, the Company will undertake a normal course review of its non-financial assets relating to the Cariboo Gold Project in accordance with IFRS Accounting Standards as at September 30, 2026, as part of its third quarter 2026 financial results preparation. For the avoidance of doubt, any impairment charge, if any, would be non-cash in nature and would have no impact on the Company's cash flows.

    The estimated go-forward capital obligation is expected to be expended over the construction period set out below, based on an assumed USD:CAD exchange rate of C$1.38 per US$1.00. To mitigate financial exposures associated with the go-forward capital obligation, including currency and commodity risks, and to protect future operating cash flows, the Company may opportunistically contemplate entering into derivative contracts, such as put options.

    Table 2: Go-forward Capital Obligation – Estimated Timing of Spend (% of total)1,2
    20263 2027 2028 2029
    10% 40% 35% 15%
    1. Assuming a USD:CAD exchange rate of C$1.38 per US$1.00.
    2. Capital spend percentage breakdown associated with capital cost items only, and excludes capitalized revenue in year 2029.
    3. Partial year from August 1, 2026, onwards.

    The Project is designed as a conventional, decline-accessed underground mining operation employing mechanized long-hole stoping mining methods, with paste backfill, to extract ore from gold-bearing vein corridors. Underground access is currently provided through the Cow portal, with development extending into the Lowhee and Cow deposit Zones. At the mine site complex, earthworks have commenced on the second underground access at the Valley Portal. Once established, the Valley Portal will provide a second development front and support critical path primary development access to the Valley and Shaft Zones, which host the majority of the Cariboo Gold deposit's mineral reserves and mineral resources.

    Approximately 3.0 kilometres of underground development has been completed to date. Early works have already commenced during pre-construction, with preparatory activities advancing at the mine site complex, waste rock storage facility, sediment control pond and water treatment plant, among other areas. Major earthworks are scheduled to ramp-up in Q3 2026 and are expected to continue through Q4 2027, with the process plant foundations work commencing in the summer of 2027 and building enclosure targeted for Q2 2028. The expected timeline to commercial production, including key milestones and work areas, is outlined in Figure 1 below:

    FIGURE 1: Cariboo Gold Project Development Timeline to Commercial Production


    Trafigura Financing and Commercial Agreements

    As part of the Board’s decision to approve a final investment decision ("FID"), the Company is pleased to announce that it and its wholly-owned subsidiary, Barkerville Gold Mines Ltd. ("Barkerville"), have entered into agreements (the "Trafigura Financing and Commercial Agreements") with Trafigura Canada Limited ("Trafigura") and Urion Investments Holdings Limited ("Urion"), an affiliate of Trafigura, that support the development of the Project.

    The Trafigura Financing and Commercial Agreements comprises: (i) a subscription agreement between the Company and Urion pursuant to which Urion has agreed to acquire 9,554,141 common shares of the Company (each, a "Common Share") at a price of US$3.14 per Common Share (the "Issue Price"), representing a 10% premium to the five-day volume weighted average price of the Common Shares on the TSX Venture Exchange prior to signing, for gross proceeds of approximately US$30 million (the "Equity Investment"); (ii) offtake agreements between Barkerville and Trafigura for 100% of the (x) gold concentrate for the first four years of production at the Cariboo Gold Project (or until 80,000 dry metric tons of concentrate are delivered) and (y) gold doré for the first four years of production (together, the "Offtake Agreements"); and (iii) non-binding terms and an exclusivity period in respect of a potential subordinated gold prepayment facility and a further six-years of concentrate and doré offtake between Barkerville and Trafigura (the "Prepay Facility"). The proposed Prepay Facility, as currently contemplated, doesn't provide for any financial maintenance covenants, with final terms remaining subject to the execution of a definitive agreement.

    Sean Roosen further commented: “We are very pleased to welcome Trafigura, a global leader in the commodities industry, as a long-term strategic partner at Cariboo. Its strategic investment in the Company reflects confidence in both the Project and our team's ability to execute on its construction. We look forward to advancing towards a definitive agreement on the prepay financing, which would provide a significant additional non-dilutive source of capital for the construction of Cariboo.”

    The proceeds of the Equity Investment will be used for the development of the Cariboo Gold Project. The Common Shares to be issued under the Equity Investment will be subject to a statutory hold period of four months and one day from the date of issuance pursuant to applicable Canadian securities laws. Closing of the Equity Investment remains subject to final acceptance of the TSX Venture Exchange and the New York Stock Exchange.

    In connection with the Equity Investment, Urion has also agreed to enter into a voting support agreement with the Company (the "Voting Support Agreement"), pursuant to which Urion will agree to vote its Common Shares in accordance with the recommendations of the board of directors or management of the Company, subject to certain exceptions. The Voting Support Agreement also contains customary standstill and lock-up provisions restricting Urion's ability to acquire additional Common Shares or dispose of its Common Shares for specified periods.

    The Offtake Agreements provide for the purchase by Trafigura of 100% of the gold concentrate and doré bars produced by Barkerville from the Cariboo Gold Project at prices that incorporate prevailing London Bullion Market Association and deductions including standard treatment and refining charges. Deliveries under the Offtake Agreements are expected to commence upon the start of first gold pour at the Cariboo Gold Project.

    Barkerville and Trafigura have also agreed to non-binding terms in respect of a potential Prepay Facility of up to US$120 million and Trafigura has been granted an exclusivity period during which the parties will negotiate definitive documentation for such facility. There is no assurance that definitive documentation for the Prepay Facility will be entered into on the terms currently contemplated or at all. The non-binding terms contemplate that the Prepay Facility will be secured by a subordinated security interest against the assets of Barkerville. The facility is contemplated to be available to draw for three years from closing, with a maturity date that is at a minimum five years from closing at an interest rate of SOFR plus 6.00%.

    Double Zero Capital LP ("Double Zero"), an existing insider of the Company, has pre-emptive rights under the investor rights agreement dated August 15, 2025, between Double Zero and the Company (the "Double Zero IRA") to participate in the Equity Investment on the same terms as Urion, subject to the terms and conditions of the Double Zero IRA. Double Zero is entitled to participate in the Equity Investment on the same terms as Urion in order to maintain its existing ownership percentage in the Company. As of the date hereof, Double Zero has not waived its pre-emptive rights under the Double Zero IRA.

    Closing of the Equity Investment is expected to occur in September 2026, subject to the satisfaction of customary closing conditions, including final acceptance of the TSX Venture Exchange and the New York Stock Exchange. The Equity Investment is not subject to any minimum subscription amount.

    Sources and Uses of Capital

    The Company intends to maintain a disciplined approach to capital allocation over the ensuing construction period, focused on preserving sufficient liquidity and financial flexibility through the Project's construction, ramp-up and achievement of commercial production. The Company also intends to continue its infill and conversion drilling programs throughout the construction phase to further de-risk planned production areas by: (a) increasing geological confidence and definition of the existing measured and indicated mineral resources, and (b) supporting the upgrade of inferred mineral resources to higher confidence categories and, where appropriate, their potential conversion of such resources to mineral reserves after considering applicable modifying factors.

    Table 3 summarizes the estimated sources and uses of capital from August 1, 2026 through to forecasted commercial production in H2 2029. Total sources of capital are estimated at approximately $1,637 million (US$1,186 million) and comprise current cash and cash equivalents, marketable securities, and project debt, and are subject to the successful closing of the Equity Investment, the execution of the related definitive agreement in connection with the gold prepay facility, and certain assumptions in relation to equipment financing. Estimated uses of capital are estimated at approximately $1,435 million (US$1,040 million) and include the remaining go-forward capital obligation, working capital, exploration expenditures, debt service and financing costs, and other general corporate expenditures. This results in projected surplus liquidity of approximately $201 million (US$146 million).

    TABLE 3: Sources and Uses of Capital (from August 1, 2026 to commercial production)


    1. Adjusted working capital is as of June 30, 2026, and includes cash and cash equivalents of approximately $837 million, net of current liabilities.
    2. Exploration expenditures include remaining flow-through expenditure obligations of approximately $22 million, with the balance related to planned exploration activities across conversion, infill, and CGP deeps exploration surface and underground drilling.

    Additional potential sources not reflected in the estimated sources above include proceeds, if any, from the exercise of certain outstanding warrants of the Company. Full exercise of such warrants would generate potential proceeds of approximately US$120 million from the warrants expiring in August 2027 with an exercise price of US$2.56 per Common Share, which are subject to an acceleration provision beginning in mid-November 2026, and approximately US$150 million from warrants expiring in October 2029 with an exercise price of US$3.00 per Common Share. The Company continues to actively evaluate opportunities to optimize its project debt structure and reduce its overall cost of capital. The exercise of Company warrants is entirely at the discretion of the holders thereof, and there can be no assurance that any or all of the Company warrants will be exercised or that the Company will receive any proceeds therefrom.

    Summary of Project Metrics

    In connection with the Project's go-forward capital obligation update, the Company has adjusted, where applicable, certain financial inputs in the Cariboo Technical Report (as defined herein) to reflect the Project's current status and the prevailing commodity price environment, which have an impact on project economics. As noted above, the update also reflects certain modifications to the construction schedule, resulting in an anticipated 30-month construction period from August 1, 2026 (from 24 months in the 2025 FS) to first gold pour in Q1 2029 and 36 months (from 34 months in the 2025 FS) to commercial production in H2 2029.

    Except for these adjustments, the information contained in the Cariboo Technical Report (as defined herein) relating to geology and mineralization, mineral reserves and mineral resources, mining methods and mineral processing, together with all other material assumptions and qualifications, remains current and unchanged. A summary of Project metrics is presented in Table 4:

    Table 4: Cariboo Gold Project – Summary of Project Metrics1
    Metric units Feasibility Study
    (April 2025)
    Go-Forward Update
    (August 2026)
    Mine life years 10 10
    Annual throughput tpd 4,900 4,900
    Average gold head grade g/t Au 3.62 3.62
    Total payable gold, LOM koz Au 1,894 1,894
    Avg. gold production, LOM / First 5 years koz/yr 190 / 202 190 / 202
    Gold price US$/oz $2,400 $3,570 (LT consensus) $4,350 (spot)
    Exchange rate USDCAD 1.35 1.38 1.38
    Total cash costs2 US$/oz $947 $957 $996
    All-in sustaining costs2 US$/oz $1,157 $1,163 $1,202
    Project Go-Forward Capital Obligation3        
    Initial capital $ mm $881 $990 $9394
    Sustaining capital $ mm $426 $426 $426
    Economic Results (after-tax)        
    Total free cash flow, LOM $ mm $1,577 $3,610 $4,828
    Net present value (NPV5%) $ mm $943 $2,323 $3,181
    Internal rate of return (IRR) % 22.1% 34.7% 42.7%
    Payback, from commercial production years 2.8 2.2 1.8
    Average free cash flow2, LOM / first 5 years $ mm $158 / $296 $362 / $5215 $485 / $6425
    1. Totals may not add up due to rounding. Spot pricing scenario is based on the LBMA gold price as of the close of business on September 11, 2026, rounded to nearest US$50/oz.
    2. Non-IFRS Financial Measure. See Cautionary Statements – Non-IFRS Financial Measures.
    3. Go-forward capital obligation associated with the August 2026 update assumes remaining capital costs from August 1, 2026 to commercial production. Refer to Table 1 for a more detailed breakdown.
    4. Under the spot gold price scenario, higher pre-production revenues provide a greater offset to the go-forward capital obligation than under the long-term consensus pricing scenario.
    5. Average free cash flow for the first 5 years is calculated for the periods between 2029 and 2034, inclusive of the pre-production period.

    Cariboo Gold Project Update

    Project Activity Update
    Health and Safety
    • The Total Recordable Injury Frequency Rate for the Project sits at 1.21 year-to-date for 2026, with over 2.3 million total person-hours worked project-to-date.
    • Project Completion
      • Based on total costs incurred to date, including indirects and owners' costs, overall project completion is estimated at 22%, as of July 31, 2026.
      • Underground Development
        • Approximately 3.0 km of underground development has been completed to date. Underground development continues from the existing Cow Portal into the Lowhee Zone and along the main access ramp into the Cow Mountain Zone.
        • Development rates continue to improve as headings advance beyond the Lowhee fault, where enhanced ground support was required, and into more favourable ground conditions in the Cow Zone.
        • Development rates are expected to reach target monthly rates of up to approximately 500 metres by year-end.
        • At the mine site complex, earthworks have commenced on the second underground access at the Valley Portal, which is expected to be collared by mid-September 2026. Once established, it will provide a second development front and support critical path primary development access to the Valley and Shaft Zones, which host the majority of the Cariboo Gold deposit's mineral reserves and mineral resources.
        • A total of four (4) portal accesses are planned, with no shafts or hoisting systems. The existing Cow portal will serve as the primary access for mine equipment and waste haulage, while the three portals at the Valley Complex will provide secondary access, ventilation, and material conveyance, respectively.
        • Site Infrastructure
          • Water treatment plant – upgrades to the Bonanza Ledge water treatment plant are complete. Final commissioning continues, with full operation expected in Q3 2026. Excavation for the Mine Site Complex water treatment plant, which will serve as the primary facility during operations, has commenced, with the plant slated to be fully operational by the end of 2027.
          • Sediment control pond (Bonanza Ledge) – has been completed.
          • Waste rock storage facility – construction is progressing with Phase 1a cut and fill completed, underdrains installation complete, and placement of liner bedding approximately 50% complete. Completion of Phase 1 is anticipated in mid-2027.
          • Permanent camp – the site camp upgrade and expansion to 375 rooms is complete and, together with other Company-controlled accommodations, is expected to provide sufficient capacity aligned with peak construction and exploration manpower requirements.
          • Construction of other critical infrastructure is progressing.
          • Early Works
            • Early works at the mine site complex, which will host the primary processing facility, commenced in Q2 2026 and include tree clearing and geotechnical drilling.
            • Excavation of the Valley Portal and earthworks and foundation construction for the main water treatment plant at the Mine Site Complex have commenced in Q3 2026. Installation of the Willow River Bridge, which will provide the Project's primary access once completed, is expected to begin in Q3 2026.
            • Transmission Line
              • All long lead packages, transformer, conductor cabling and high voltage breakers have been procured and are expected to arrive at site in Q3 2027.
              • Engineering
                • Approximately 40% of detailed engineering has been completed.
                • Engineering progress status for key planned activities by category is as follows: process plant & site utilities (10%), water treatment plant (90%), MSC sediment control pond (10%), waste rock storage facility (100%), MSC civil works (75%), transmission line (100%), overland piping (75%), and other remaining areas (75%).
                • Procurement
                  • Procurement and commitments for long-lead items is progressing and includes a total of 466 work contract packages, with overall completion at approximately 44%. Approximately $325 million has been committed to date.
                  • Major construction contracts have been awarded, including those covering earthworks, structural steel erection, electrical and instrumentation, site services, the transmission line, overland piping, and others. Procurement activities for the remaining contract packages are actively progressing.
                  • Construction Management
                    • Project and Construction Management Services Agreement with JDS Energy & Mining Inc. in place.
                    • Permitting
                      • The Project obtained all permits necessary for construction, operation, and closure in Q4 2024 with the receipt of the Mines Act (British Columbia) and Environmental Management Act (British Columbia) permits.
                      • License of Occupation for the transmission line is expected to be obtained in Q4 2026.
                      • All remaining authorizations, permit amendments, and routine construction permits are expected to be obtained in the ordinary course as construction progresses.
                      • Labour and workforce
                        • Construction and exploration workforce at site currently exceeds 350 active personnel and is expected to ramp-up to up to 360-375 over the coming months.
                        • First Nations and Stakeholder Engagement
                          • The Company has entered into a Life of Project Agreement with Lhtako Dené Nation (2020) and entered into a Participation Agreement with Williams Lake First Nation (2022). Consultation and engagement with Xatśūll First Nation continues.
                          • The Company entered into a Support and Benefits Agreement with the District of Wells (2026) and continues to be an active participant in the local community.
                          • Exploration
                            • Underground development reached the first access point into the Cow Mountain Zone where a dedicated drill gallery is being advanced to enable infill drilling to support resource conversion, which is expected to commence at the end of September 2026.
                            • Up to 20 drill rigs are expected to be active at times throughout 2026 and beyond, as the various programs overlap and advance, representing up to approximately 160,000 metres of planned drilling across all targets. Thirteen drill rigs are currently operating across all programs, including three drills active underground.

                            • Project Development Photos

                              FIGURE 2: Mine Site Complex processing facility site earthworks underway.

                               

                               

                              FIGURE 3: Valley portal excavation with bedrock exposed at the Mine Site Complex.

                               

                               

                               

                              FIGURE 4: Cow portal entrance access to the underground Lowhee and Cow Zones.

                               

                               

                              FIGURE 5: Cariboo Gold Project underground – employees and equipment.

                               

                               

                              FIGURE 6: Underground haul truck in operation.

                               

                               

                              FIGURE 7: Underground development face drilling preparation.

                               

                               

                              FIGURE 8: Site camp upgrade and expansion to 375 rooms.

                               

                               

                              FIGURE 9: Site camp: individual rooms with dedicated washroom facilities, gym, cafeteria.

                               

                               

                              FIGURE 10: Overview of the waste rock storage facility (WRSF).

                               

                               

                              FIGURE 11: Construction of main trench in the WRSF and sediment control pond (SCP) (1).

                               

                               

                              FIGURE 12: Construction of main trench in the WRSF and SCP (2).

                               

                               

                              FIGURE 13: Bonanza Ledge overview – water treatment plant facilities, WRSF, SCP.

                               

                              ABOUT THE CARIBOO GOLD PROJECT

                              The Cariboo Gold Project is a permitted, 100%-owned feasibility-stage project located in the historic Wells-Barkerville mining camp of central British Columbia, Canada. Spanning approximately 186,740 hectares, the Company's land package includes 443 mineral titles and covers an area that extends approximately 77-kilometres from northwest to southeast. In late 2024, the Project was granted the Mines Act and Environmental Management Act (British Columbia) permits, marking the successful completion of the permitting process for key approvals, solidifying the Project's shovel-ready status.

                              Mineral Reserves Estimate – Cariboo Gold Project

                              The mineral reserves estimate for the Cariboo Gold Project included in the Cariboo Technical Report (as defined herein) has an effective date of April 10, 2025. Only mineral resources that were classified as measured and indicated were given economic attributes in the mine design, and when demonstrating economic viability were classified as mineral reserves.

                              Cariboo Gold Project – Mineral Reserves Statement (April 10, 2025)
                              Category / Zone   Tonnage   Gold Grade   Contained Gold
                                  (tonnes)   (g/t)   (oz)
                              Proven      
                              Probable            
                              Cow   3,999,971   3.35   430,548
                              Valley   3,238,636   3.59   374,058
                              Shaft   8,548,295   3.72   1,021,599
                              Mosquito   1,105,370   3.94   140,102
                              Lowhee   923,162   3.52   104,491
                              Total Proven & Probable   17,815,435   3.62   2,070,798


                              Notes:

                              1. Totals may not add up due to rounding.
                              2. The mineral reserve estimate follows the 2014 CIM Definition Standards on Mineral Resources and Reserves and the 2019 CIM Estimation of Mineral Resources and Mineral Reserves Best Practice Guidelines.
                              3. Mineral reserves used the following assumptions: US$1,915/oz gold price, USD:CAD exchange rate of 1.32, and variable cut-off value from 1.70 g/t to 2.0 g/t Au
                              4. Mineral reserves include both internal and external dilution along with mining recovery. The external dilution is estimated to be 10.1%. The average mining recovery factor was set at 91.3% to account for ore left in each block in the margins of the deposit.

                              Mineral Resources Estimate – Cariboo Gold Project

                              The mineral resources estimate for the Cariboo Gold Project included in the Cariboo Technical Report (as defined herein) has an effective date of April 22, 2025, and is reported exclusive of mineral reserves. Mineral resources that are not mineral reserves do not have demonstrated economic viability. The reader is cautioned that inferred mineral resources have a greater degree of uncertainty than indicated mineral resources and must not be converted to mineral reserves; it is reasonably expected, though not guaranteed, that the majority of inferred mineral resources could be upgraded to indicated mineral resources with continued exploration.

                              Table 6: Cariboo Gold Project – Mineral Resources Statement (April 22, 2025)
                              Category / Zone   Tonnage   Gold Grade   Contained Gold
                                  (000's tonnes)   (g/t)   (000's oz)
                              Measured            
                              Bonanza Ledge   47   5.06   8
                              Indicated            
                              Bonanza Ledge   32   4.02   4
                              BC Vein   1,057   3.00   102
                              KL   527   2.80   47
                              Lowhee   1,333   2.76   118
                              Mosquito   1,553   2.96   148
                              Shaft   6,121   2.92   575
                              Valley   2,718   2.70   236
                              Cow   3,991   2.91   374
                              Total Indicated Resources   17,332   2.88   1,604
                              Total Measured & Indicated   17,380   2.88   1,612
                              Inferred            
                              BC Vein   596   3.17   61
                              KL   2,514   2.53   205
                              Lowhee   486   3.01   47
                              Mosquito   1,883   3.08   186
                              Shaft   7,457   3.44   826
                              Valley   2,470   3.01   239
                              Cow   3,368   2.78   301
                              Total Inferred Resources   18,774   3.09   1,864


                              Notes:

                              1. The independent and qualified persons for the mineral resources estimates, as defined by NI 43-101, are Carl Pelletier, P.Geo., and Tessa Scott, P.Geo. (Norda Stelo). The effective date of the mineral resource estimate included in the Cariboo Technical Report is April 22, 2025.
                              2. These mineral resources, exclusive of the reserves, are not mineral reserves and do not have demonstrated economic viability.
                              3. The mineral resources estimate follows the 2014 CIM Definition Standards on Mineral Resources and Reserves and the 2019 CIM Estimation of Mineral Resources and Mineral Reserves Best Practice Guidelines.
                              4. A total of 481 vein zones were modelled for the Cow Mountain (Cow and Valley), Island Mountain (Shaft and Mosquito), Barkerville Mountain (BC Vein, KL, and Lowhee) deposits and one gold zone for Bonanza Ledge. A minimum true thickness of 2.0 m was applied, using the gold grade of the adjacent material when assayed or a value of zero when not assayed.
                              5. The estimate is reported for a potential underground scenario at a cut-off grade of 1.8 g/t Au, except for Bonanza Ledge at a cut-off grade of 3.5 g/t Au. The cut-off grade for the Cow, Valley, Shaft, Mosquito, BC Vein, KL, and Lowhee deposits was calculated using a gold price of US$2,400/oz; a USDCAD exchange rate of 1.35; an underground mining cost of $66.3/t; a processing and transport cost of $30.80/t; a G&A plus Environmental cost of $22.40/t; and a sustaining CAPEX cost of $45.6/t. No changes have been applied for the Bonanza Ledge. The cut-off grade for the Bonanza Ledge deposit was calculated using a gold price of US$1,700/oz; a USDCAD exchange rate of 1.27; an underground mining cost of $79.13/t; a processing and transport cost of $65.00/t; and a G&A plus Environmental cost of $51.65/t. The cut-off grades may be re-evaluated in light of future prevailing market conditions (metal prices, exchange rate, mining cost, etc.).
                              6. Density values for Cow, Shaft, Lowhee, and BC Vein were estimated using the ID2 interpolation method, with a value applied for the non-estimated blocks of 2.80 g/cm3 for Cow, 2.78 g/cm3 for Shaft, 2.74 g/cm3 for Lowhee, and 2.69 g/cm3 for BC Vein. Median densities were applied for Valley (2.81 g/cm3), Mosquito (2.79 g/cm3), and KL (2.81 g/cm3). A density of 3.20 g/cm3 was applied for Bonanza Ledge.
                              7. A four-step capping procedure was applied to composited data for Cow (3.0 m), Valley (1.5 m), Shaft (2.0 m), Mosquito (2.5 m), BC Vein (2.0 m), KL (1.75 m), and Lowhee (1.5 m). Restricted search ellipsoids ranged from 7 to 50 g/t Au at four different distances ranging from 25 m to 250 m for each deposit. High grades at Bonanza Ledge were capped at 70 g/t Au on 2.0 m composited data.
                              8. The gold mineral resources for the Cow, Valley, Shaft, Mosquito, BC Vein, KL, and Lowhee vein zones were estimated using Datamine StudioTM RM 1.9 software using hard boundaries on composited assays. The dilution halo gold mineralization was estimated using Datamine StudioTM RM Pro 1.11. The OK method was used to interpolate a sub-blocked model (parent block size = 5 m x 5 m x 5 m). Mineral resources for Bonanza Ledge were estimated using GEOVIA GEMSTM 6.7 software using hard boundaries on composited assays. The OK method was used to interpolate a block model (block size = 2 m x 2 m x 5 m).
                              9. Results are presented in situ. Ounce (troy) = metric tons x grade / 31.10348. Calculations used metric units (metres, tonnes, g/t). The number of tonnes were rounded to the nearest thousand. Any discrepancies in the totals are due to rounding effects. Rounding followed the recommendations as per NI 43-101.
                              10. The qualified persons responsible for this section of this news release are not aware of any environmental, permitting, legal, title, taxation, socio-economic, marketing, political, or other relevant factors that could materially affect the mineral resource estimate other than those disclosed in this news release and in the Cariboo Technical Report.

                              Technical Reports

                              Scientific and technical information relating to the Cariboo Gold Project and the 2025 feasibility study on the Cariboo Gold Project is supported by the technical report, titled "NI 43-101 Technical Report, Feasibility Study for the Cariboo Gold Project, District of Wells, British Columbia, Canada" dated June 11, 2025 (with an effective date of April 25, 2025) (the "Cariboo Technical Report").

                              For readers to fully understand the information in the Cariboo Technical Report, reference should be made to the full text of the Cariboo Technical Report in its entirety, including all assumptions, parameters, qualifications, limitations and methods therein. The Cariboo Technical Report is intended to be read as a whole, and sections should not be read or relied upon out of context. The Cariboo Technical Report was prepared in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects ("NI 43-101") and is available electronically on SEDAR+ (www.sedarplus.ca) and on EDGAR (www.sec.gov) under Osisko Gold's issuer profile and on the Company's website at www.osiskogold.ca.

                              Qualified Persons

                              The scientific and technical information contained in this news release has been reviewed, verified and approved by Scott Smith, P. Geo., Vice President, Exploration of Osisko Gold, a "qualified person" within the meaning of NI 43-101.

                              Advisors

                              GenCap Mining Advisory is acting as debt advisor to Osisko Gold with Calagus AG acting as the Company’s advisor for its concentrate and doré.

                              Currency of Presentation and Exchange Rate Data

                              Dollar amounts set out in this news release are stated in Canadian dollars except as otherwise indicated. All references to “US$” or “U.S. dollars” are to the lawful currency of the United States and all references to “$,” “C$” or “Canadian dollars” are to the lawful currency of Canada. Unless otherwise indicated, amounts are based on an assumed USD:CAD exchange rate of C$1.38 per US$1.00.


                              ABOUT OSISKO GOLD GROUP INC.


                              Osisko Gold Group Inc. is a continental North American gold development company focused on past producing mining camps with district-scale potential. The Company's objective is to become an intermediate gold producer through the development of its flagship, fully permitted, 100%-owned Cariboo Gold Project, located within the Company's broader Cariboo regional land package in central British Columbia, Canada, which hosts numerous prospective exploration targets and provides opportunities for future discoveries. Its Cariboo project pipeline is complemented by the Tintic Project, located in the historic East Tintic mining district in Utah, U.S.A., a brownfield property with significant exploration potential, extensive historical mining data, and access to established infrastructure. Osisko Gold is focused on developing long-life mining assets in mining-friendly jurisdictions while maintaining a disciplined approach to capital allocation, development risk management, and mineral inventory growth.

                              For further information, visit our website at www.osiskogold.ca or contact:

                               
                              Sean Roosen
                              Chairman and CEO
                              Email: sroosen@osiskogold.ca
                              Tel: +1 (514) 940-0685

                              Philip Rabenok
                              Vice President, Investor Relations
                              Email: prabenok@osiskogold.ca
                              Tel: +1 (437) 423-3644

                               


                              CAUTIONARY STATEMENTS

                              Non-IFRS Financial Measures

                              This news release contains certain non-IFRS (as defined herein) financial measures, including "all-in sustaining cost" (or "AISC"), "cash cost", "free cash flow" and "adjusted working capital". All-in sustaining cost per gold ounce is defined as production costs less silver sales plus general and administrative, exploration and other expenses, and sustaining capital expenditures divided by gold ounces sold. Cash costs are a non-IFRS financial measure reported by the Company on an ounces of gold sold basis. Cash costs include mining, processing, refining, general and administrative costs and royalties but exclude depreciation, reclamation, income taxes, capital costs and exploration costs. Free cash flow is calculated as cash flow from mine-site operating activities less capital expenditures. Adjusted working capital is calculated as current assets less current liabilities, excluding the current portion of derivative assets, and including the current portion of derivative liabilities and warrant liabilities. Management believes that such measures provide investors with an improved ability to evaluate the performance of the Company. Non-IFRS financial measures do not have any standardized meaning prescribed under IFRS and, therefore, they may not be comparable to similar measures employed by other companies. These measures are intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS, such as cost of sales. For non-IFRS financial measures related to the feasibility study for the Cariboo Gold Project refer to the Cariboo Technical Report (as defined herein).

                              Cautionary Note to U.S. Investors Regarding the Use of Mineral Reserve and Mineral Resource Estimates

                              The Company is subject to the reporting requirements of the applicable Canadian Securities Laws, and as a result reports information regarding mineral properties, mineralization and estimates of mineral reserves and mineral resources in accordance with Canadian reporting requirements, which are governed by NI 43-101. As such, the information contained in this news release concerning mineral properties, mineralization and estimates of mineral reserves and mineral resources is not comparable to similar information made public by U.S. companies subject to the reporting and disclosure requirements of the U.S. Securities and Exchange Commission.

                              Caution Regarding Forward-Looking Statements

                              This news release contains "forward-looking information" within the meaning of applicable Canadian securities laws and "forward-looking statements" within the meaning of the U.S. Private Securities Litigation Reform Act of 1995, as amended (collectively, "forward-looking statements"). All statements other than statements of historical fact contained in this news release are forward-looking statements. Such forward-looking statements relate to, among other things: the formal construction decision and anticipated development and construction of the Cariboo Gold Project; the expected timing of first gold pour and commercial production; the expected benefits of the Equity Investment and the gold prepay facility, including the anticipated use of proceeds; the anticipated satisfaction of remaining conditions precedent to, and the timing and successful closing of, the Equity Investment; the Company's ability to successfully negotiate and execute Prepay Facility on commercially acceptable terms ; the advancement of construction activities, detailed engineering, procurement, and project de-risking initiatives at the Cariboo Gold Project; the go-forward capital obligation estimate and anticipated timing of capital expenditures; estimates of mineral reserves and mineral resources; the anticipated mine life, production rates, gold grades, recoveries, and operating costs; estimated economic returns, including NPV, IRR, payback period, and free cash flow projections; the Company's sources and uses of capital and projected liquidity position; the Company's exploration programs and potential for resource conversion; the Company's objective of becoming an intermediate gold producer; employment and economic benefits to local communities; and the exploration potential and prospectivity of its properties.

                              Forward-looking statements are necessarily based upon estimates and assumptions that, while considered reasonable by the Company as of the date hereof, are inherently subject to significant business, economic, and competitive uncertainties and contingencies. Known and unknown factors could cause actual results to differ materially from those projected in the forward-looking statements. Forward-looking statements in this news release include statements that are not historical facts and are generally, but not always, identified by words or phrases such as "anticipate", "believe", "budget", "contemplate", "continue", "could", "estimate", "expect", "forecast", "foresee", "intend", "may", "objective", "ongoing", "outlook", "plan", "potential", "project", "propose", "scheduled", "seek", "should", "strategy", "target", "will", "would", or similar expressions, or statements that certain events or conditions "could", "may", "should", "will", or "would" occur, and the negative forms of any of these words.

                              The forward-looking statements in this news release are based upon certain material assumptions that were applied in drawing a conclusion or making a forecast or projection, including: risks relating to capital markets and the availability of future financing, including project financing, on terms acceptable to the Company (or at all); the ability of the Company to meet its financial obligations as they become due; actual operating cash flows, free cash flows, operating costs and other costs differing materially from those anticipated; changes in project parameters and assumptions; project infrastructure requirements and anticipated processing methods, whether or not the capital and operating costs outlined in the Cariboo Technical Report (as defined below) in respect of the feasibility study for the Cariboo Gold Project ("2025 Cariboo FS") can be achieved, exploration expenditures differing materially from those anticipated; actual results of current and planned exploration activities; whether additional mineral resources will be developed as a result of the deeper drilling below the Cariboo mineral resource estimate, within the Cariboo mine area, and/or on exploration targets beyond the mine area; whether infill drilling of inferred mineral resources, after considering other modifying factors, will be successful in converting mineral resources to measured or indicated mineral resources and any resulting increases in the mineral reserves; whether the results of the Company's 13,000m infill drill program will confirm or vary from those in the current mineral resource estimate; whether the development of the Cariboo Gold Project, if successfully completed, will provide the basis for the establishment of a broader mining district camp, including development of multiple deposits; whether all required authorizations for the implementation of the Mines Act (British Columbia) (the "Mines Act") permits for the Cariboo Gold Project, including the licence of occupation for the transmission line, will be received in a timely manner and not delay the project; whether an agreement will be completed, and on what terms, with Xatśūll First Nation; whether the Company's new water treatment plant and facilities will operate to expectations and meet permit conditions; whether current and planned test mining at Tintic will generate positive cash flow after deducting all costs; variations in mineral resources, mineral reserves, mineral production, grades or recovery rates or optimization efforts and sales; failure to obtain, or delays in obtaining, governmental approvals or financing or in the completion of development or construction activities; uninsured risks, including, but not limited to, pollution, cave-ins or hazards for which insurance cannot be obtained; regulatory changes; defects in title; availability or integration of personnel, materials and equipment; risks relating to foreign operations; inability to recruit or retain management and key personnel; performance of facilities, equipment and processes relative to specifications and expectations; unanticipated environmental impacts on operations; community, non-governmental and governmental actions and the impact of stakeholder actions; market prices; production, construction and technological risks or capital requirements and operating risks associated with the operations or an expansion of the operations; dilution due to future equity financings, fluctuations in gold, silver and other metal prices and currency exchange rates; the potential impact of tariffs and other trade restrictions; uncertainty relating to future production and cash resources; inability to successfully complete new development projects, planned expansions or other projects within the timelines anticipated; inability to achieve the business objectives and project milestones as anticipated; results of additional work programs and exploration; adverse changes to market, political and general economic conditions or laws, rules and regulations applicable to the Company; outbreak of diseases and public health crises; the possibility of project cost overruns or unanticipated costs and expenses; accidents, labour disputes, community and stakeholder protests and other risks of the mining industry; failure of plant, equipment or processes to operate as anticipated; risk of an undiscovered defect in title or other adverse claim; the Company's ability to satisfy the remaining conditions precedent to the closing of the Equity Investment and to execute definitive documentation in respect of the gold prepay facility on acceptable terms; the continued availability of financing under the gold prepay facility and other financing sources on the terms described herein; the Company's ability to advance the Cariboo Gold Project through construction and into commercial production on the anticipated timeline and within the estimated budget; the accuracy of the go-forward capital obligation estimate and the assumptions underlying such estimate, including with respect to inflation, labour costs, and foreign exchange rates; the accuracy of mineral reserve and mineral resource estimates and the assumptions underlying such estimates; the Company's ability to achieve anticipated production rates, grades, and recoveries; the absence of material adverse changes in the prices of gold and other commodities, foreign exchange rates, and interest rates; the absence of any material adverse change in general business and economic conditions; and the continued support of the Company's stakeholders, including First Nations communities; and any other information herein that is not a historical fact may be "forward looking information".

                              Material assumptions also include assumptions and qualifications underlying the 2025 Cariboo FS, management's perceptions of historical trends, management's understanding of the permitting process and status thereof, the ability of exploration (including drilling and chip sampling assays, and face sampling) to accurately predict mineralization; budget constraints and access to capital on terms acceptable to the Company, current conditions and expected future developments, regulatory framework remaining defined and understood, results of further exploration work to define or expand any mineral resources, gold prices, the costs required to advance the Cariboo Gold Project to construction, the results of the 2025 Cariboo FS as an indicator of quality and robustness of the Cariboo Gold Project, as well as other considerations that are believed to be appropriate in the circumstances. Forward-looking statements involve known and unknown risks, uncertainties and other factors that may cause actual results, performance, or achievements to differ materially from those expressed or implied by such forward-looking statements. Such risks and uncertainties include, but are not limited to: capital market conditions and the Company's ability to access capital on terms acceptable to the Company for the contemplated exploration and development at the Company's properties; regulatory framework and presence of laws and regulations that may impose restrictions on mining; the ability of exploration activities (including drill results and chip sampling, and face sampling results) to accurately predict mineralization; errors in management's geological modelling; the timing and ability of the Company to obtain and maintain required approvals and permits; the results of exploration activities; risks relating to exploration, development and mining activities; the global economic climate; metal and commodity prices; fluctuations in the currency markets; dilution; environmental risks; and community, non-governmental and governmental actions; the impact of stakeholder actions; failure to satisfy remaining conditions precedent to closing of the Equity Investment or to execute definitive documentation in respect of the gold prepay facility; changes in the terms of the gold Prepay Facility, not entering into the contemplate Prepay Facility or the occurrence of any event that would prevent the Company from accessing funds thereunder; the Company's ability to execute on the construction of the Cariboo Gold Project on the anticipated timeline and within the estimated budget, including risks related to cost overruns, construction delays, and supply chain disruptions; risks related to the accuracy of mineral reserve and mineral resource estimates and the geological, operational, and technical factors underlying such estimates; risks related to the exploration, development, and operation of the Cariboo Gold Project, including unexpected ground or geotechnical conditions, water management challenges, and other geological or mining challenges; risks related to processing capacity, gold recovery rates, and other technical and operational factors; fluctuations in gold prices and other commodity prices; fluctuations in foreign exchange rates, particularly between the Canadian and U.S. dollars; fluctuations in interest rates affecting the cost of borrowings; risks related to the Company's ability to attract and retain qualified personnel and contractors; labour shortages, disputes, or work stoppages; health, safety, and security incidents; risks related to relationships with Indigenous communities and other local stakeholders; risks related to environmental compliance, reclamation obligations, and changes in environmental laws and regulations; regulatory delays or changes in regulatory frameworks and applicable laws; risks related to title to the Company's properties and permits; risks related to competition in the mining industry; risks related to cybersecurity and information technology systems; general economic, political, and market conditions; and other risks and uncertainties provided under the heading "Risk Factors" in the Company's annual information form for the year ended December 31, 2025 as well as the financial statements and MD&A for the year ended December 31, 2025, the three months ended March 31, 2026 and the three and six months ended June 30, 2026, which have been filed on SEDAR+ (www.sedarplus.ca) under Osisko Gold's issuer profile and on the SEC's EDGAR website (www.sec.gov). Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated, or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Forward-looking statements are not guarantees of future performance, and the Company's actual results of operations, financial condition, and liquidity, and the development of the industry in which it operates, may differ materially from the forward-looking statements contained in this news release. Accordingly, readers should not place undue reliance on forward-looking statements or the information contained herein. The forward-looking statements contained in this news release are made as of the date hereof. Except as required under applicable securities legislation, the Company does not undertake any obligation to publicly update or revise any forward-looking statements, whether as a result of new information, future events, or otherwise.

                              Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release. No stock exchange, securities commission or other regulatory authority has approved or disapproved the information contained herein.

                              Photos accompanying this announcement are available at

                              https://www.globenewswire.com/NewsRoom/AttachmentNg/51a5d3df-2b86-47a7-9f26-0ceba6fd645e

                              https://www.globenewswire.com/NewsRoom/AttachmentNg/afb58f85-3251-48a5-89dd-6cf42ebd83a3

                              Filing Exhibits & Attachments

                              1 document

                              Keep reading