Southern Company and its utility subsidiaries file an annual report describing their regulated electric and natural gas businesses across the Southeast and Midwest, including Alabama Power, Georgia Power, Mississippi Power, Southern Power, and Southern Company Gas.

Management outlines large capital plans, with a 2026 construction program of about $15.9 billion, including $12.6 billion for the Southern Company electric system, focused on new generation, transmission, distribution, and environmental compliance. Georgia Power alone plans roughly $3.6 billion for new generation and storage tied to prior IRP approvals.

The report highlights rapidly growing load from data centers and other large customers, leading regulators to certify about 13 GW of resources, mostly new generation and battery storage. Southern Company Gas serves about 4.4 million customers over 77,900 miles of pipe, while the traditional electric operating companies serve roughly 4.6 million retail power customers. The group employs about 29,800 people and emphasizes regulated cost recovery mechanisms, extensive environmental and nuclear oversight, and forward-looking risk factors affecting future earnings and capital needs.

Positive

  • None.

Negative

  • None.

Insights

Large regulated capex and data-center driven growth, with typical utility risk profile.

Southern Company describes a sizeable 2026 construction plan of about $15.9 billion, largely for regulated generation, transmission, and gas infrastructure. Georgia Power’s IRP-driven projects and Southern Power’s contracted renewables underpin most of the electric investment.

Load growth from data centers and other large customers is projected at roughly 9 GW under contract, while regulators have certified around 13 GW of resources with significant battery storage. This suggests continued rate-base expansion but also higher financing needs and execution risk on large projects.

Key variables for investors include state commission decisions on cost recovery, the effectiveness of fuel and environmental cost riders, and the outcome of federal proceedings affecting markets like SEEM. Long-dated nuclear licenses and ongoing environmental compliance spending will remain central to the company’s long-term capital and regulatory strategy.

000009212200000031530000041091000006690400011606610001004155FALSE2025FYthree years, six monthsP7Yhttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrenthttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrent18284111111111111111111111111111111P5YP5Y.000025.000025P3Yhttp://fasb.org/us-gaap/2025#OtherAssetsNoncurrenthttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrenthttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrenthttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrenthttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrenthttp://fasb.org/us-gaap/2025#OtherLiabilitiesNoncurrenthttp://southerncompany.com/20251231#PublicUtilitiesOtherDepreciablePropertyPlantAndEquipmentPlantInServicehttp://southerncompany.com/20251231#PublicUtilitiesOtherDepreciablePropertyPlantAndEquipmentPlantInServicehttp://southerncompany.com/20251231#PublicUtilitiesOtherDepreciablePropertyPlantAndEquipmentPlantInServicehttp://southerncompany.com/20251231#PublicUtilitiesOtherDepreciablePropertyPlantAndEquipmentPlantInServicehttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrenthttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrenthttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrenthttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrenthttp://fasb.org/us-gaap/2025#LongTermDebtAndCapitalLeaseObligationshttp://fasb.org/us-gaap/2025#LongTermDebtAndCapitalLeaseObligationshttp://fasb.org/us-gaap/2025#LongTermDebtAndCapitalLeaseObligationshttp://fasb.org/us-gaap/2025#LongTermDebtAndCapitalLeaseObligationshttp://fasb.org/us-gaap/2025#OtherAssetsNoncurrenthttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrenthttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrenthttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrenthttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrenthttp://fasb.org/us-gaap/2025#OtherLiabilitiesNoncurrenthttp://southerncompany.com/20251231#PublicUtilitiesOtherDepreciablePropertyPlantAndEquipmentPlantInServicehttp://southerncompany.com/20251231#PublicUtilitiesOtherDepreciablePropertyPlantAndEquipmentPlantInServicehttp://southerncompany.com/20251231#PublicUtilitiesOtherDepreciablePropertyPlantAndEquipmentPlantInServicehttp://southerncompany.com/20251231#PublicUtilitiesOtherDepreciablePropertyPlantAndEquipmentPlantInServicehttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrenthttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrenthttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrenthttp://fasb.org/us-gaap/2025#OtherLiabilitiesCurrenthttp://fasb.org/us-gaap/2025#LongTermDebtAndCapitalLeaseObligationshttp://fasb.org/us-gaap/2025#LongTermDebtAndCapitalLeaseObligationshttp://fasb.org/us-gaap/2025#LongTermDebtAndCapitalLeaseObligationshttp://fasb.org/us-gaap/2025#LongTermDebtAndCapitalLeaseObligationsP3YP1YP2Y11484476456645489iso4217:USDxbrli:sharesutr:MWiso4217:USDxbrli:sharesso:companyso:statexbrli:pureso:customeriso4217:USDso:KWH_Kilowatt_hourso:facilityso:projectso:unitso:scaleso:filingutr:miso:plantso:investorutr:Dso:agreementso:leveragedLeaseso:employeeso:typeutr:MMBTUiso4217:EURso:segment00000921222025-01-012025-12-310000092122so:AlabamaPowerMember2025-01-012025-12-310000092122so:GeorgiaPowerMember2025-01-012025-12-310000092122so:MississippiPowerMember2025-01-012025-12-310000092122so:SouthernPowerMember2025-01-012025-12-310000092122so:SouthernCompanyGasMember2025-01-012025-12-310000092122us-gaap:CommonStockMember2025-01-012025-12-310000092122so:Series2017B5.25JuniorSubordinatedNotesDue2077Member2025-01-012025-12-310000092122so:Series2020A4.95JuniorSubordinatedNotesDue2080Member2025-01-012025-12-310000092122so:Series2020C420JuniorSubordinatedNotesDue2060Member2025-01-012025-12-310000092122so:Series2021B1875FixedToFixedResetRateJuniorSubordinatedNotesDue2081Member2025-01-012025-12-310000092122so:Series2025A6.50JuniorSubordinatedNotesDue2085Member2025-01-012025-12-310000092122so:A2025SeriesACorporateUnitsMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberso:Series2017A5.00JuniorSubordinatedNotesDue2077Member2025-01-012025-12-310000092122so:SouthernPowerMemberso:Series2016B1.850SeniorNotesDue2026Member2025-01-012025-12-3100000921222025-06-3000000921222026-01-310000092122so:AlabamaPowerMember2026-01-310000092122so:GeorgiaPowerMember2026-01-310000092122so:MississippiPowerMember2026-01-310000092122so:SouthernPowerMember2026-01-310000092122so:SouthernCompanyGasMember2026-01-310000092122so:MillersBranchSolarDevelopmentPhase1Memberso:SouthernPowerMember2025-01-012025-12-310000092122so:MillersBranchSolarDevelopmentPhase2Memberso:SouthernPowerMember2025-01-012025-12-310000092122so:MillersBranchSolarDevelopmentPhase3Memberso:SouthernPowerMember2025-01-012025-12-310000092122so:SouthernCompanyGasMember2025-12-310000092122us-gaap:RetailMember2025-01-012025-12-310000092122us-gaap:RetailMember2024-01-012024-12-310000092122us-gaap:RetailMember2023-01-012023-12-310000092122so:WholesaleElectricMember2025-01-012025-12-310000092122so:WholesaleElectricMember2024-01-012024-12-310000092122so:WholesaleElectricMember2023-01-012023-12-310000092122so:OtherElectricRevenueMember2025-01-012025-12-310000092122so:OtherElectricRevenueMember2024-01-012024-12-310000092122so:OtherElectricRevenueMember2023-01-012023-12-310000092122so:NaturalGasMember2025-01-012025-12-310000092122so:NaturalGasMember2024-01-012024-12-310000092122so:NaturalGasMember2023-01-012023-12-310000092122us-gaap:ProductAndServiceOtherMember2025-01-012025-12-310000092122us-gaap:ProductAndServiceOtherMember2024-01-012024-12-310000092122us-gaap:ProductAndServiceOtherMember2023-01-012023-12-3100000921222024-01-012024-12-3100000921222023-01-012023-12-310000092122srt:FuelMember2025-01-012025-12-310000092122srt:FuelMember2024-01-012024-12-310000092122srt:FuelMember2023-01-012023-12-310000092122us-gaap:ElectricityPurchasedMember2025-01-012025-12-310000092122us-gaap:ElectricityPurchasedMember2024-01-012024-12-310000092122us-gaap:ElectricityPurchasedMember2023-01-012023-12-310000092122us-gaap:NaturalGasUsRegulatedMember2025-01-012025-12-310000092122us-gaap:NaturalGasUsRegulatedMember2024-01-012024-12-310000092122us-gaap:NaturalGasUsRegulatedMember2023-01-012023-12-3100000921222024-12-3100000921222023-12-3100000921222022-12-3100000921222025-12-310000092122us-gaap:CommonStockMember2022-12-310000092122us-gaap:TreasuryStockCommonMember2022-12-310000092122us-gaap:AdditionalPaidInCapitalMember2022-12-310000092122us-gaap:RetainedEarningsMember2022-12-310000092122us-gaap:AccumulatedOtherComprehensiveIncomeMember2022-12-310000092122us-gaap:NoncontrollingInterestMember2022-12-310000092122us-gaap:RetainedEarningsMember2023-01-012023-12-310000092122us-gaap:NoncontrollingInterestMember2023-01-012023-12-310000092122us-gaap:AccumulatedOtherComprehensiveIncomeMember2023-01-012023-12-310000092122us-gaap:CommonStockMember2023-01-012023-12-310000092122us-gaap:AdditionalPaidInCapitalMember2023-01-012023-12-310000092122us-gaap:TreasuryStockCommonMember2023-01-012023-12-310000092122us-gaap:CommonStockMember2023-12-310000092122us-gaap:TreasuryStockCommonMember2023-12-310000092122us-gaap:AdditionalPaidInCapitalMember2023-12-310000092122us-gaap:RetainedEarningsMember2023-12-310000092122us-gaap:AccumulatedOtherComprehensiveIncomeMember2023-12-310000092122us-gaap:NoncontrollingInterestMember2023-12-310000092122us-gaap:RetainedEarningsMember2024-01-012024-12-310000092122us-gaap:NoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:AccumulatedOtherComprehensiveIncomeMember2024-01-012024-12-310000092122us-gaap:CommonStockMember2024-01-012024-12-310000092122us-gaap:AdditionalPaidInCapitalMember2024-01-012024-12-310000092122us-gaap:CommonStockMember2024-12-310000092122us-gaap:TreasuryStockCommonMember2024-12-310000092122us-gaap:AdditionalPaidInCapitalMember2024-12-310000092122us-gaap:RetainedEarningsMember2024-12-310000092122us-gaap:AccumulatedOtherComprehensiveIncomeMember2024-12-310000092122us-gaap:NoncontrollingInterestMember2024-12-310000092122us-gaap:RetainedEarningsMember2025-01-012025-12-310000092122us-gaap:NoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:AccumulatedOtherComprehensiveIncomeMember2025-01-012025-12-310000092122us-gaap:AdditionalPaidInCapitalMember2025-01-012025-12-310000092122us-gaap:CommonStockMember2025-01-012025-12-310000092122us-gaap:CommonStockMember2025-12-310000092122us-gaap:TreasuryStockCommonMember2025-12-310000092122us-gaap:AdditionalPaidInCapitalMember2025-12-310000092122us-gaap:RetainedEarningsMember2025-12-310000092122us-gaap:AccumulatedOtherComprehensiveIncomeMember2025-12-310000092122us-gaap:NoncontrollingInterestMember2025-12-310000092122us-gaap:RetailMemberso:AlabamaPowerMember2025-01-012025-12-310000092122us-gaap:RetailMemberso:AlabamaPowerMember2024-01-012024-12-310000092122us-gaap:RetailMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:WholesaleNonAffiliatesMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:WholesaleNonAffiliatesMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:WholesaleNonAffiliatesMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:WholesaleAffiliatesMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:WholesaleAffiliatesMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:WholesaleAffiliatesMemberso:AlabamaPowerMember2023-01-012023-12-310000092122us-gaap:ProductAndServiceOtherMemberso:AlabamaPowerMember2025-01-012025-12-310000092122us-gaap:ProductAndServiceOtherMemberso:AlabamaPowerMember2024-01-012024-12-310000092122us-gaap:ProductAndServiceOtherMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:AlabamaPowerMember2024-01-012024-12-310000092122so:AlabamaPowerMember2023-01-012023-12-310000092122srt:FuelMemberso:AlabamaPowerMember2025-01-012025-12-310000092122srt:FuelMemberso:AlabamaPowerMember2024-01-012024-12-310000092122srt:FuelMemberso:AlabamaPowerMember2023-01-012023-12-310000092122us-gaap:ElectricityPurchasedMemberso:AlabamaPowerMember2025-01-012025-12-310000092122us-gaap:ElectricityPurchasedMemberso:AlabamaPowerMember2024-01-012024-12-310000092122us-gaap:ElectricityPurchasedMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:ElectricityPurchasedAffiliatesMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:ElectricityPurchasedAffiliatesMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:ElectricityPurchasedAffiliatesMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:AlabamaPowerMember2024-12-310000092122so:AlabamaPowerMember2023-12-310000092122so:AlabamaPowerMember2022-12-310000092122so:AlabamaPowerMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:RelatedPartyMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:RelatedPartyMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:CommonStockMember2022-12-310000092122so:AlabamaPowerMemberus-gaap:AdditionalPaidInCapitalMember2022-12-310000092122so:AlabamaPowerMemberus-gaap:RetainedEarningsMember2022-12-310000092122so:AlabamaPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2022-12-310000092122so:AlabamaPowerMemberus-gaap:RetainedEarningsMember2023-01-012023-12-310000092122so:AlabamaPowerMemberus-gaap:AdditionalPaidInCapitalMember2023-01-012023-12-310000092122so:AlabamaPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2023-01-012023-12-310000092122so:AlabamaPowerMemberus-gaap:CommonStockMember2023-12-310000092122so:AlabamaPowerMemberus-gaap:AdditionalPaidInCapitalMember2023-12-310000092122so:AlabamaPowerMemberus-gaap:RetainedEarningsMember2023-12-310000092122so:AlabamaPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2023-12-310000092122so:AlabamaPowerMemberus-gaap:RetainedEarningsMember2024-01-012024-12-310000092122so:AlabamaPowerMemberus-gaap:AdditionalPaidInCapitalMember2024-01-012024-12-310000092122so:AlabamaPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2024-01-012024-12-310000092122so:AlabamaPowerMemberus-gaap:CommonStockMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:AdditionalPaidInCapitalMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:RetainedEarningsMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:RetainedEarningsMember2025-01-012025-12-310000092122so:AlabamaPowerMemberus-gaap:AdditionalPaidInCapitalMember2025-01-012025-12-310000092122so:AlabamaPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2025-01-012025-12-310000092122so:AlabamaPowerMemberus-gaap:CommonStockMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:AdditionalPaidInCapitalMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:RetainedEarningsMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2025-12-310000092122us-gaap:RetailMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122us-gaap:RetailMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122us-gaap:RetailMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:WholesaleNonAffiliatesMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:WholesaleNonAffiliatesMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:WholesaleNonAffiliatesMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122us-gaap:ProductAndServiceOtherMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122us-gaap:ProductAndServiceOtherMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122us-gaap:ProductAndServiceOtherMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:GeorgiaPowerMember2024-01-012024-12-310000092122so:GeorgiaPowerMember2023-01-012023-12-310000092122srt:FuelMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122srt:FuelMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122srt:FuelMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122us-gaap:ElectricityPurchasedMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122us-gaap:ElectricityPurchasedMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122us-gaap:ElectricityPurchasedMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:ElectricityPurchasedAffiliatesMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:ElectricityPurchasedAffiliatesMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:ElectricityPurchasedAffiliatesMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:GeorgiaPowerMember2024-12-310000092122so:GeorgiaPowerMember2023-12-310000092122so:GeorgiaPowerMember2022-12-310000092122so:GeorgiaPowerMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:RelatedPartyMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:RelatedPartyMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:CommonStockMember2022-12-310000092122so:GeorgiaPowerMemberus-gaap:AdditionalPaidInCapitalMember2022-12-310000092122so:GeorgiaPowerMemberus-gaap:RetainedEarningsMember2022-12-310000092122so:GeorgiaPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2022-12-310000092122so:GeorgiaPowerMemberus-gaap:RetainedEarningsMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberus-gaap:AdditionalPaidInCapitalMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberus-gaap:CommonStockMember2023-12-310000092122so:GeorgiaPowerMemberus-gaap:AdditionalPaidInCapitalMember2023-12-310000092122so:GeorgiaPowerMemberus-gaap:RetainedEarningsMember2023-12-310000092122so:GeorgiaPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2023-12-310000092122so:GeorgiaPowerMemberus-gaap:RetainedEarningsMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberus-gaap:AdditionalPaidInCapitalMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberus-gaap:CommonStockMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:AdditionalPaidInCapitalMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:RetainedEarningsMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:RetainedEarningsMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberus-gaap:AdditionalPaidInCapitalMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberus-gaap:CommonStockMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:AdditionalPaidInCapitalMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:RetainedEarningsMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2025-12-310000092122us-gaap:RetailMemberso:MississippiPowerMember2025-01-012025-12-310000092122us-gaap:RetailMemberso:MississippiPowerMember2024-01-012024-12-310000092122us-gaap:RetailMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:WholesaleNonAffiliatesMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:WholesaleNonAffiliatesMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:WholesaleNonAffiliatesMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:WholesaleAffiliatesMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:WholesaleAffiliatesMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:WholesaleAffiliatesMemberso:MississippiPowerMember2023-01-012023-12-310000092122us-gaap:ProductAndServiceOtherMemberso:MississippiPowerMember2025-01-012025-12-310000092122us-gaap:ProductAndServiceOtherMemberso:MississippiPowerMember2024-01-012024-12-310000092122us-gaap:ProductAndServiceOtherMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:MississippiPowerMember2024-01-012024-12-310000092122so:MississippiPowerMember2023-01-012023-12-310000092122so:FuelAndPurchasedPowerMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:FuelAndPurchasedPowerMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:FuelAndPurchasedPowerMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:MississippiPowerMember2024-12-310000092122so:MississippiPowerMember2023-12-310000092122so:MississippiPowerMember2022-12-310000092122so:MississippiPowerMember2025-12-310000092122so:MississippiPowerMemberus-gaap:RelatedPartyMember2025-12-310000092122so:MississippiPowerMemberus-gaap:RelatedPartyMember2024-12-310000092122so:MississippiPowerMemberus-gaap:CommonStockMember2022-12-310000092122so:MississippiPowerMemberus-gaap:AdditionalPaidInCapitalMember2022-12-310000092122so:MississippiPowerMemberus-gaap:RetainedEarningsMember2022-12-310000092122so:MississippiPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2022-12-310000092122so:MississippiPowerMemberus-gaap:RetainedEarningsMember2023-01-012023-12-310000092122so:MississippiPowerMemberus-gaap:AdditionalPaidInCapitalMember2023-01-012023-12-310000092122so:MississippiPowerMemberus-gaap:CommonStockMember2023-12-310000092122so:MississippiPowerMemberus-gaap:AdditionalPaidInCapitalMember2023-12-310000092122so:MississippiPowerMemberus-gaap:RetainedEarningsMember2023-12-310000092122so:MississippiPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2023-12-310000092122so:MississippiPowerMemberus-gaap:RetainedEarningsMember2024-01-012024-12-310000092122so:MississippiPowerMemberus-gaap:AdditionalPaidInCapitalMember2024-01-012024-12-310000092122so:MississippiPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2024-01-012024-12-310000092122so:MississippiPowerMemberus-gaap:CommonStockMember2024-12-310000092122so:MississippiPowerMemberus-gaap:AdditionalPaidInCapitalMember2024-12-310000092122so:MississippiPowerMemberus-gaap:RetainedEarningsMember2024-12-310000092122so:MississippiPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2024-12-310000092122so:MississippiPowerMemberus-gaap:RetainedEarningsMember2025-01-012025-12-310000092122so:MississippiPowerMemberus-gaap:AdditionalPaidInCapitalMember2025-01-012025-12-310000092122so:MississippiPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2025-01-012025-12-310000092122so:MississippiPowerMemberus-gaap:CommonStockMember2025-12-310000092122so:MississippiPowerMemberus-gaap:AdditionalPaidInCapitalMember2025-12-310000092122so:MississippiPowerMemberus-gaap:RetainedEarningsMember2025-12-310000092122so:MississippiPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2025-12-310000092122so:WholesaleNonAffiliatesMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:WholesaleNonAffiliatesMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:WholesaleNonAffiliatesMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:WholesaleAffiliatesMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:WholesaleAffiliatesMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:WholesaleAffiliatesMemberso:SouthernPowerMember2023-01-012023-12-310000092122us-gaap:ProductAndServiceOtherMemberso:SouthernPowerMember2025-01-012025-12-310000092122us-gaap:ProductAndServiceOtherMemberso:SouthernPowerMember2024-01-012024-12-310000092122us-gaap:ProductAndServiceOtherMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:SouthernPowerMember2024-01-012024-12-310000092122so:SouthernPowerMember2023-01-012023-12-310000092122srt:FuelMemberso:SouthernPowerMember2025-01-012025-12-310000092122srt:FuelMemberso:SouthernPowerMember2024-01-012024-12-310000092122srt:FuelMemberso:SouthernPowerMember2023-01-012023-12-310000092122us-gaap:ElectricityPurchasedMemberso:SouthernPowerMember2025-01-012025-12-310000092122us-gaap:ElectricityPurchasedMemberso:SouthernPowerMember2024-01-012024-12-310000092122us-gaap:ElectricityPurchasedMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:SouthernPowerMember2024-12-310000092122so:SouthernPowerMember2023-12-310000092122so:SouthernPowerMember2022-12-310000092122so:SouthernPowerMember2025-12-310000092122so:SouthernPowerMemberus-gaap:RelatedPartyMember2025-12-310000092122so:SouthernPowerMemberus-gaap:RelatedPartyMember2024-12-310000092122so:SouthernPowerMemberus-gaap:AdditionalPaidInCapitalMember2022-12-310000092122so:SouthernPowerMemberus-gaap:RetainedEarningsMember2022-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2022-12-310000092122so:SouthernPowerMemberus-gaap:ParentMember2022-12-310000092122so:SouthernPowerMemberus-gaap:NoncontrollingInterestMember2022-12-310000092122so:SouthernPowerMemberus-gaap:RetainedEarningsMember2023-01-012023-12-310000092122so:SouthernPowerMemberus-gaap:ParentMember2023-01-012023-12-310000092122so:SouthernPowerMemberus-gaap:NoncontrollingInterestMember2023-01-012023-12-310000092122so:SouthernPowerMemberus-gaap:AdditionalPaidInCapitalMember2023-01-012023-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2023-01-012023-12-310000092122so:SouthernPowerMemberus-gaap:AdditionalPaidInCapitalMember2023-12-310000092122so:SouthernPowerMemberus-gaap:RetainedEarningsMember2023-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2023-12-310000092122so:SouthernPowerMemberus-gaap:ParentMember2023-12-310000092122so:SouthernPowerMemberus-gaap:NoncontrollingInterestMember2023-12-310000092122so:SouthernPowerMemberus-gaap:RetainedEarningsMember2024-01-012024-12-310000092122so:SouthernPowerMemberus-gaap:ParentMember2024-01-012024-12-310000092122so:SouthernPowerMemberus-gaap:NoncontrollingInterestMember2024-01-012024-12-310000092122so:SouthernPowerMemberus-gaap:AdditionalPaidInCapitalMember2024-01-012024-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2024-01-012024-12-310000092122so:SouthernPowerMemberus-gaap:AdditionalPaidInCapitalMember2024-12-310000092122so:SouthernPowerMemberus-gaap:RetainedEarningsMember2024-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2024-12-310000092122so:SouthernPowerMemberus-gaap:ParentMember2024-12-310000092122so:SouthernPowerMemberus-gaap:NoncontrollingInterestMember2024-12-310000092122so:SouthernPowerMemberus-gaap:RetainedEarningsMember2025-01-012025-12-310000092122so:SouthernPowerMemberus-gaap:ParentMember2025-01-012025-12-310000092122so:SouthernPowerMemberus-gaap:NoncontrollingInterestMember2025-01-012025-12-310000092122so:SouthernPowerMemberus-gaap:AdditionalPaidInCapitalMember2025-01-012025-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2025-01-012025-12-310000092122so:SouthernPowerMemberus-gaap:AdditionalPaidInCapitalMember2025-12-310000092122so:SouthernPowerMemberus-gaap:RetainedEarningsMember2025-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2025-12-310000092122so:SouthernPowerMemberus-gaap:ParentMember2025-12-310000092122so:SouthernPowerMemberus-gaap:NoncontrollingInterestMember2025-12-310000092122so:SouthernCompanyGasMember2024-01-012024-12-310000092122so:SouthernCompanyGasMember2023-01-012023-12-310000092122so:SouthernCompanyGasMember2024-12-310000092122so:SouthernCompanyGasMember2023-12-310000092122so:SouthernCompanyGasMember2022-12-310000092122so:SouthernCompanyGasMemberus-gaap:RelatedPartyMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:RelatedPartyMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:AdditionalPaidInCapitalMember2022-12-310000092122so:SouthernCompanyGasMemberus-gaap:RetainedEarningsMember2022-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2022-12-310000092122so:SouthernCompanyGasMemberus-gaap:RetainedEarningsMember2023-01-012023-12-310000092122so:SouthernCompanyGasMemberus-gaap:AdditionalPaidInCapitalMember2023-01-012023-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2023-01-012023-12-310000092122so:SouthernCompanyGasMemberus-gaap:AdditionalPaidInCapitalMember2023-12-310000092122so:SouthernCompanyGasMemberus-gaap:RetainedEarningsMember2023-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2023-12-310000092122so:SouthernCompanyGasMemberus-gaap:RetainedEarningsMember2024-01-012024-12-310000092122so:SouthernCompanyGasMemberus-gaap:AdditionalPaidInCapitalMember2024-01-012024-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2024-01-012024-12-310000092122so:SouthernCompanyGasMemberus-gaap:AdditionalPaidInCapitalMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:RetainedEarningsMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:RetainedEarningsMember2025-01-012025-12-310000092122so:SouthernCompanyGasMemberus-gaap:AdditionalPaidInCapitalMember2025-01-012025-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2025-01-012025-12-310000092122so:SouthernCompanyGasMemberus-gaap:AdditionalPaidInCapitalMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:RetainedEarningsMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedOtherComprehensiveIncomeMember2025-12-310000092122so:TraditionalOperatingCompaniesMember2025-12-310000092122so:AlabamaPowerMemberso:SouthernCompanyServicesIncMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberso:SouthernCompanyServicesIncMember2025-01-012025-12-310000092122so:MississippiPowerMemberso:SouthernCompanyServicesIncMember2025-01-012025-12-310000092122so:SouthernPowerMemberso:SouthernCompanyServicesIncMember2025-01-012025-12-310000092122so:SouthernCompanyGasMemberso:SouthernCompanyServicesIncMember2025-01-012025-12-310000092122so:AlabamaPowerMemberso:SouthernCompanyServicesIncMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberso:SouthernCompanyServicesIncMember2024-01-012024-12-310000092122so:MississippiPowerMemberso:SouthernCompanyServicesIncMember2024-01-012024-12-310000092122so:SouthernPowerMemberso:SouthernCompanyServicesIncMember2024-01-012024-12-310000092122so:SouthernCompanyGasMemberso:SouthernCompanyServicesIncMember2024-01-012024-12-310000092122so:AlabamaPowerMemberso:SouthernCompanyServicesIncMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberso:SouthernCompanyServicesIncMember2023-01-012023-12-310000092122so:MississippiPowerMemberso:SouthernCompanyServicesIncMember2023-01-012023-12-310000092122so:SouthernPowerMemberso:SouthernCompanyServicesIncMember2023-01-012023-12-310000092122so:SouthernCompanyGasMemberso:SouthernCompanyServicesIncMember2023-01-012023-12-310000092122so:AlabamaPowerMemberso:SouthernNuclearOperatingCompanyIncMember2025-01-012025-12-310000092122so:AlabamaPowerMemberso:SouthernNuclearOperatingCompanyIncMember2024-01-012024-12-310000092122so:AlabamaPowerMemberso:SouthernNuclearOperatingCompanyIncMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberso:SouthernNuclearOperatingCompanyIncMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberso:SouthernNuclearOperatingCompanyIncMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberso:SouthernNuclearOperatingCompanyIncMember2023-01-012023-12-310000092122so:PowerPoolMemberso:AlabamaPowerMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:PowerPoolMemberso:AlabamaPowerMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:PowerPoolMemberso:AlabamaPowerMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:PowerPoolMemberso:AlabamaPowerMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:PowerPoolMemberso:AlabamaPowerMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:PowerPoolMemberso:AlabamaPowerMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:AlabamaPowerMemberso:SouthernNaturalGasCompanyLLCMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberso:SouthernNaturalGasCompanyLLCMember2025-01-012025-12-310000092122so:SouthernPowerMemberso:SouthernNaturalGasCompanyLLCMember2025-01-012025-12-310000092122so:SouthernCompanyGasMemberso:SouthernNaturalGasCompanyLLCMember2025-01-012025-12-310000092122so:AlabamaPowerMemberso:SouthernNaturalGasCompanyLLCMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberso:SouthernNaturalGasCompanyLLCMember2024-01-012024-12-310000092122so:SouthernPowerMemberso:SouthernNaturalGasCompanyLLCMember2024-01-012024-12-310000092122so:SouthernCompanyGasMemberso:SouthernNaturalGasCompanyLLCMember2024-01-012024-12-310000092122so:AlabamaPowerMemberso:SouthernNaturalGasCompanyLLCMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberso:SouthernNaturalGasCompanyLLCMember2023-01-012023-12-310000092122so:SouthernPowerMemberso:SouthernNaturalGasCompanyLLCMember2023-01-012023-12-310000092122so:SouthernCompanyGasMemberso:SouthernNaturalGasCompanyLLCMember2023-01-012023-12-310000092122so:NonFuelExpenseMemberso:MississippiPowerMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:NonFuelExpenseMemberso:MississippiPowerMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:NonFuelExpenseMemberso:MississippiPowerMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:PowerSecureMemberso:GeorgiaPowerMemberso:EquipmentPurchaseAndServiceAgreementsMember2025-01-012025-12-310000092122so:PowerSecureMemberso:GeorgiaPowerMemberso:EquipmentPurchaseAndServiceAgreementsMember2024-01-012024-12-310000092122so:PowerSecureMemberso:GeorgiaPowerMemberso:EquipmentPurchaseAndServiceAgreementsMember2023-01-012023-12-310000092122so:PowerSecureMemberso:AlabamaPowerMemberso:EquipmentPurchaseAndServiceAgreementsMember2023-01-012023-12-310000092122so:PowerSecureMemberso:AlabamaPowerMemberso:EquipmentPurchaseAndServiceAgreementsMember2024-01-012024-12-310000092122so:PowerSecureMemberso:AlabamaPowerMemberso:EquipmentPurchaseAndServiceAgreementsMember2025-01-012025-12-310000092122so:PowerSecureMemberso:MississippiPowerMemberso:EquipmentPurchaseAndServiceAgreementsMember2023-01-012023-12-310000092122so:PowerSecureMemberso:MississippiPowerMemberso:EquipmentPurchaseAndServiceAgreementsMember2024-01-012024-12-310000092122so:PowerSecureMemberso:MississippiPowerMemberso:EquipmentPurchaseAndServiceAgreementsMember2025-01-012025-12-310000092122so:PowerSecureMemberso:USGeneralServicesAdministrationMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:PowerSecureMemberso:USGeneralServicesAdministrationMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:PowerSecureMemberso:USGeneralServicesAdministrationMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:SouthernCompanyServicesIncMemberus-gaap:ElectricTransmissionMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:SouthernCompanyServicesIncMemberus-gaap:ElectricTransmissionMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:SouthernCompanyServicesIncMemberus-gaap:ElectricTransmissionMemberso:SouthernPowerMember2023-01-012023-12-310000092122us-gaap:AlternativeEnergyMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122us-gaap:AlternativeEnergyMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122us-gaap:AlternativeEnergyMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:WholesaleCustomersMemberus-gaap:CustomerConcentrationRiskMemberso:SouthernPowerMemberus-gaap:SalesRevenueNetMember2025-01-012025-12-310000092122so:WholesaleCustomersMemberus-gaap:CustomerConcentrationRiskMemberso:MississippiPowerMemberso:LongTermContractMember2025-01-012025-12-310000092122so:IncludedInOperatingExpensesMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:IncludedInOperatingExpensesMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:IncludedInOperatingExpensesMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:AtlantaGasLightMember2025-12-310000092122so:AtlantaGasLightMember2024-12-310000092122so:AtlantaGasLightMember2023-12-310000092122so:ChattanoogaGasMember2025-12-310000092122so:ChattanoogaGasMember2024-12-310000092122so:ChattanoogaGasMember2023-12-310000092122so:NicorGasMember2025-12-310000092122so:NicorGasMember2024-12-310000092122so:NicorGasMember2023-12-310000092122so:AlabamaPowerMember2025-07-012025-09-300000092122so:SouthernCompanyGasMemberso:GasDistributionOperationsMember2025-12-310000092122so:SouthernCompanyGasMemberso:GasDistributionOperationsMember2024-12-310000092122so:SouthernCompanyGasMemberso:GasMarketingServicesMember2025-12-310000092122so:SouthernCompanyGasMemberso:GasMarketingServicesMember2024-12-310000092122us-gaap:CustomerRelationshipsMember2025-12-310000092122us-gaap:CustomerRelationshipsMember2024-12-310000092122us-gaap:TradeNamesMember2025-12-310000092122us-gaap:TradeNamesMember2024-12-310000092122so:PPAFairValueAdjustmentsMember2025-12-310000092122so:PPAFairValueAdjustmentsMember2024-12-310000092122us-gaap:OtherIntangibleAssetsMember2025-12-310000092122us-gaap:OtherIntangibleAssetsMember2024-12-310000092122so:FCCLicensesMember2025-12-310000092122so:FCCLicensesMember2024-12-310000092122so:PPAFairValueAdjustmentsMemberso:SouthernPowerMember2025-12-310000092122so:PPAFairValueAdjustmentsMemberso:SouthernPowerMember2024-12-310000092122us-gaap:CustomerRelationshipsMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:CustomerRelationshipsMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:TradeNamesMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:TradeNamesMemberso:SouthernCompanyGasMember2025-12-310000092122so:SouthernCompanyGasMemberso:GasMarketingServicesMember2025-01-012025-12-310000092122so:SouthernCompanyGasMemberso:GasMarketingServicesMember2024-01-012024-12-310000092122so:SouthernCompanyGasMemberso:GasMarketingServicesMember2023-01-012023-12-310000092122so:OperatingRevenuesMember2025-01-012025-12-310000092122so:SouthernCompanyGasMemberso:CollateralForLifeInsuranceAndLongTermDisabilityInsuranceMember2025-12-310000092122so:SouthernCompanyGasMemberso:CollateralForLifeInsuranceAndLongTermDisabilityInsuranceMember2024-12-310000092122us-gaap:AccumulatedGainLossCashFlowHedgeIncludingNoncontrollingInterestMember2022-12-310000092122us-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2022-12-310000092122us-gaap:AociIncludingPortionAttributableToNoncontrollingInterestMember2022-12-310000092122us-gaap:AccumulatedGainLossCashFlowHedgeIncludingNoncontrollingInterestMember2023-01-012023-12-310000092122us-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2023-01-012023-12-310000092122us-gaap:AociIncludingPortionAttributableToNoncontrollingInterestMember2023-01-012023-12-310000092122us-gaap:AccumulatedGainLossCashFlowHedgeIncludingNoncontrollingInterestMember2023-12-310000092122us-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2023-12-310000092122us-gaap:AociIncludingPortionAttributableToNoncontrollingInterestMember2023-12-310000092122us-gaap:AccumulatedGainLossCashFlowHedgeIncludingNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:AociIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:AccumulatedGainLossCashFlowHedgeIncludingNoncontrollingInterestMember2024-12-310000092122us-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2024-12-310000092122us-gaap:AociIncludingPortionAttributableToNoncontrollingInterestMember2024-12-310000092122us-gaap:AccumulatedGainLossCashFlowHedgeIncludingNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:AociIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:AccumulatedGainLossCashFlowHedgeIncludingNoncontrollingInterestMember2025-12-310000092122us-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2025-12-310000092122us-gaap:AociIncludingPortionAttributableToNoncontrollingInterestMember2025-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedGainLossCashFlowHedgeIncludingNoncontrollingInterestMember2022-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2022-12-310000092122so:SouthernPowerMemberus-gaap:AociIncludingPortionAttributableToNoncontrollingInterestMember2022-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedGainLossCashFlowHedgeIncludingNoncontrollingInterestMember2023-01-012023-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2023-01-012023-12-310000092122so:SouthernPowerMemberus-gaap:AociIncludingPortionAttributableToNoncontrollingInterestMember2023-01-012023-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedGainLossCashFlowHedgeIncludingNoncontrollingInterestMember2023-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2023-12-310000092122so:SouthernPowerMemberus-gaap:AociIncludingPortionAttributableToNoncontrollingInterestMember2023-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedGainLossCashFlowHedgeIncludingNoncontrollingInterestMember2024-01-012024-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122so:SouthernPowerMemberus-gaap:AociIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedGainLossCashFlowHedgeIncludingNoncontrollingInterestMember2024-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2024-12-310000092122so:SouthernPowerMemberus-gaap:AociIncludingPortionAttributableToNoncontrollingInterestMember2024-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedGainLossCashFlowHedgeIncludingNoncontrollingInterestMember2025-01-012025-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122so:SouthernPowerMemberus-gaap:AociIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedGainLossCashFlowHedgeIncludingNoncontrollingInterestMember2025-12-310000092122so:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2025-12-310000092122so:SouthernPowerMemberus-gaap:AociIncludingPortionAttributableToNoncontrollingInterestMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember2022-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember2022-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember2023-01-012023-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember2023-01-012023-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember2023-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember2023-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember2024-01-012024-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember2024-01-012024-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember2025-01-012025-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember2025-01-012025-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember2025-12-310000092122us-gaap:AssetRetirementObligationCostsMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:AssetRetirementObligationCostsMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:AssetRetirementObligationCostsMember2025-12-310000092122so:MississippiPowerMemberus-gaap:AssetRetirementObligationCostsMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:AssetRetirementObligationCostsMember2025-12-310000092122so:RetireeBenefitPlansMember2025-12-310000092122so:AlabamaPowerMemberso:RetireeBenefitPlansMember2025-12-310000092122so:GeorgiaPowerMemberso:RetireeBenefitPlansMember2025-12-310000092122so:MississippiPowerMemberso:RetireeBenefitPlansMember2025-12-310000092122so:SouthernCompanyGasMemberso:RetireeBenefitPlansMember2025-12-310000092122so:RemainingNetBookValueOfRetiredAssetsMember2025-12-310000092122so:AlabamaPowerMemberso:RemainingNetBookValueOfRetiredAssetsMember2025-12-310000092122so:GeorgiaPowerMemberso:RemainingNetBookValueOfRetiredAssetsMember2025-12-310000092122so:MississippiPowerMemberso:RemainingNetBookValueOfRetiredAssetsMember2025-12-310000092122so:SouthernCompanyGasMemberso:RemainingNetBookValueOfRetiredAssetsMember2025-12-310000092122us-gaap:DeferredIncomeTaxChargesMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:DeferredIncomeTaxChargesMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:DeferredIncomeTaxChargesMember2025-12-310000092122so:MississippiPowerMemberus-gaap:DeferredIncomeTaxChargesMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:DeferredIncomeTaxChargesMember2025-12-310000092122so:PropertyDamageReservesAssetMember2025-12-310000092122so:AlabamaPowerMemberso:PropertyDamageReservesAssetMember2025-12-310000092122so:GeorgiaPowerMemberso:PropertyDamageReservesAssetMember2025-12-310000092122so:MississippiPowerMemberso:PropertyDamageReservesAssetMember2025-12-310000092122so:SouthernCompanyGasMemberso:PropertyDamageReservesAssetMember2025-12-310000092122so:DeferredDepreciationMember2025-12-310000092122so:AlabamaPowerMemberso:DeferredDepreciationMember2025-12-310000092122so:GeorgiaPowerMemberso:DeferredDepreciationMember2025-12-310000092122so:MississippiPowerMemberso:DeferredDepreciationMember2025-12-310000092122so:SouthernCompanyGasMemberso:DeferredDepreciationMember2025-12-310000092122us-gaap:RegulatoryClauseRevenuesUnderRecoveredMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:RegulatoryClauseRevenuesUnderRecoveredMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:RegulatoryClauseRevenuesUnderRecoveredMember2025-12-310000092122so:MississippiPowerMemberus-gaap:RegulatoryClauseRevenuesUnderRecoveredMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:RegulatoryClauseRevenuesUnderRecoveredMember2025-12-310000092122so:SoftwareAndCloudComputingCostsMember2025-12-310000092122so:AlabamaPowerMemberso:SoftwareAndCloudComputingCostsMember2025-12-310000092122so:GeorgiaPowerMemberso:SoftwareAndCloudComputingCostsMember2025-12-310000092122so:MississippiPowerMemberso:SoftwareAndCloudComputingCostsMember2025-12-310000092122so:SouthernCompanyGasMemberso:SoftwareAndCloudComputingCostsMember2025-12-310000092122us-gaap:EnvironmentalRestorationCostsMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:EnvironmentalRestorationCostsMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:EnvironmentalRestorationCostsMember2025-12-310000092122so:MississippiPowerMemberus-gaap:EnvironmentalRestorationCostsMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:EnvironmentalRestorationCostsMember2025-12-310000092122us-gaap:RecoverableVacationPayMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:RecoverableVacationPayMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:RecoverableVacationPayMember2025-12-310000092122so:MississippiPowerMemberus-gaap:RecoverableVacationPayMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:RecoverableVacationPayMember2025-12-310000092122us-gaap:LossOnReacquiredDebtMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:LossOnReacquiredDebtMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:LossOnReacquiredDebtMember2025-12-310000092122so:MississippiPowerMemberus-gaap:LossOnReacquiredDebtMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:LossOnReacquiredDebtMember2025-12-310000092122so:NuclearOutageMember2025-12-310000092122so:AlabamaPowerMemberso:NuclearOutageMember2025-12-310000092122so:GeorgiaPowerMemberso:NuclearOutageMember2025-12-310000092122so:MississippiPowerMemberso:NuclearOutageMember2025-12-310000092122so:SouthernCompanyGasMemberso:NuclearOutageMember2025-12-310000092122so:RegulatoryClausesMember2025-12-310000092122so:AlabamaPowerMemberso:RegulatoryClausesMember2025-12-310000092122so:GeorgiaPowerMemberso:RegulatoryClausesMember2025-12-310000092122so:MississippiPowerMemberso:RegulatoryClausesMember2025-12-310000092122so:SouthernCompanyGasMemberso:RegulatoryClausesMember2025-12-310000092122so:QualifyingRepairsOfNaturalGasDistributionSystemsMember2025-12-310000092122so:AlabamaPowerMemberso:QualifyingRepairsOfNaturalGasDistributionSystemsMember2025-12-310000092122so:GeorgiaPowerMemberso:QualifyingRepairsOfNaturalGasDistributionSystemsMember2025-12-310000092122so:MississippiPowerMemberso:QualifyingRepairsOfNaturalGasDistributionSystemsMember2025-12-310000092122so:SouthernCompanyGasMemberso:QualifyingRepairsOfNaturalGasDistributionSystemsMember2025-12-310000092122so:FuelHedgingRealizedAndUnrealizedLossesMember2025-12-310000092122so:AlabamaPowerMemberso:FuelHedgingRealizedAndUnrealizedLossesMember2025-12-310000092122so:GeorgiaPowerMemberso:FuelHedgingRealizedAndUnrealizedLossesMember2025-12-310000092122so:MississippiPowerMemberso:FuelHedgingRealizedAndUnrealizedLossesMember2025-12-310000092122so:SouthernCompanyGasMemberso:FuelHedgingRealizedAndUnrealizedLossesMember2025-12-310000092122so:LongTermDebtFairValueAdjustmentMember2025-12-310000092122so:AlabamaPowerMemberso:LongTermDebtFairValueAdjustmentMember2025-12-310000092122so:GeorgiaPowerMemberso:LongTermDebtFairValueAdjustmentMember2025-12-310000092122so:MississippiPowerMemberso:LongTermDebtFairValueAdjustmentMember2025-12-310000092122so:SouthernCompanyGasMemberso:LongTermDebtFairValueAdjustmentMember2025-12-310000092122so:PlantDanielUnitsThreeAndFourMember2025-12-310000092122so:AlabamaPowerMemberso:PlantDanielUnitsThreeAndFourMember2025-12-310000092122so:GeorgiaPowerMemberso:PlantDanielUnitsThreeAndFourMember2025-12-310000092122so:MississippiPowerMemberso:PlantDanielUnitsThreeAndFourMember2025-12-310000092122so:SouthernCompanyGasMemberso:PlantDanielUnitsThreeAndFourMember2025-12-310000092122so:OtherRegulatoryAssetsMember2025-12-310000092122so:AlabamaPowerMemberso:OtherRegulatoryAssetsMember2025-12-310000092122so:GeorgiaPowerMemberso:OtherRegulatoryAssetsMember2025-12-310000092122so:MississippiPowerMemberso:OtherRegulatoryAssetsMember2025-12-310000092122so:SouthernCompanyGasMemberso:OtherRegulatoryAssetsMember2025-12-310000092122so:DeferredIncomeTaxCreditsMember2025-12-310000092122so:AlabamaPowerMemberso:DeferredIncomeTaxCreditsMember2025-12-310000092122so:GeorgiaPowerMemberso:DeferredIncomeTaxCreditsMember2025-12-310000092122so:MississippiPowerMemberso:DeferredIncomeTaxCreditsMember2025-12-310000092122so:SouthernCompanyGasMemberso:DeferredIncomeTaxCreditsMember2025-12-310000092122so:OtherCostOfRemovalObligationsMember2025-12-310000092122so:AlabamaPowerMemberso:OtherCostOfRemovalObligationsMember2025-12-310000092122so:GeorgiaPowerMemberso:OtherCostOfRemovalObligationsMember2025-12-310000092122so:MississippiPowerMemberso:OtherCostOfRemovalObligationsMember2025-12-310000092122so:SouthernCompanyGasMemberso:OtherCostOfRemovalObligationsMember2025-12-310000092122so:ReliabilityReserveLiabilityMember2025-12-310000092122so:AlabamaPowerMemberso:ReliabilityReserveLiabilityMember2025-12-310000092122so:GeorgiaPowerMemberso:ReliabilityReserveLiabilityMember2025-12-310000092122so:MississippiPowerMemberso:ReliabilityReserveLiabilityMember2025-12-310000092122so:SouthernCompanyGasMemberso:ReliabilityReserveLiabilityMember2025-12-310000092122so:OverRecoveredRegulatoryClauseRevenuesMember2025-12-310000092122so:AlabamaPowerMemberso:OverRecoveredRegulatoryClauseRevenuesMember2025-12-310000092122so:GeorgiaPowerMemberso:OverRecoveredRegulatoryClauseRevenuesMember2025-12-310000092122so:MississippiPowerMemberso:OverRecoveredRegulatoryClauseRevenuesMember2025-12-310000092122so:SouthernCompanyGasMemberso:OverRecoveredRegulatoryClauseRevenuesMember2025-12-310000092122so:StormAndPropertyDamageReservesLiabilityMember2025-12-310000092122so:AlabamaPowerMemberso:StormAndPropertyDamageReservesLiabilityMember2025-12-310000092122so:GeorgiaPowerMemberso:StormAndPropertyDamageReservesLiabilityMember2025-12-310000092122so:MississippiPowerMemberso:StormAndPropertyDamageReservesLiabilityMember2025-12-310000092122so:SouthernCompanyGasMemberso:StormAndPropertyDamageReservesLiabilityMember2025-12-310000092122so:PlantDanielsUnits1And2AcquisitionMember2025-12-310000092122so:AlabamaPowerMemberso:PlantDanielsUnits1And2AcquisitionMember2025-12-310000092122so:GeorgiaPowerMemberso:PlantDanielsUnits1And2AcquisitionMember2025-12-310000092122so:MississippiPowerMemberso:PlantDanielsUnits1And2AcquisitionMember2025-12-310000092122so:SouthernCompanyGasMemberso:PlantDanielsUnits1And2AcquisitionMember2025-12-310000092122so:OtherRegulatoryLiabilitiesMember2025-12-310000092122so:AlabamaPowerMemberso:OtherRegulatoryLiabilitiesMember2025-12-310000092122so:GeorgiaPowerMemberso:OtherRegulatoryLiabilitiesMember2025-12-310000092122so:MississippiPowerMemberso:OtherRegulatoryLiabilitiesMember2025-12-310000092122so:SouthernCompanyGasMemberso:OtherRegulatoryLiabilitiesMember2025-12-310000092122us-gaap:AssetRetirementObligationCostsMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:AssetRetirementObligationCostsMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:AssetRetirementObligationCostsMember2024-12-310000092122so:MississippiPowerMemberus-gaap:AssetRetirementObligationCostsMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:AssetRetirementObligationCostsMember2024-12-310000092122so:RetireeBenefitPlansMember2024-12-310000092122so:AlabamaPowerMemberso:RetireeBenefitPlansMember2024-12-310000092122so:GeorgiaPowerMemberso:RetireeBenefitPlansMember2024-12-310000092122so:MississippiPowerMemberso:RetireeBenefitPlansMember2024-12-310000092122so:SouthernCompanyGasMemberso:RetireeBenefitPlansMember2024-12-310000092122so:RemainingNetBookValueOfRetiredAssetsMember2024-12-310000092122so:AlabamaPowerMemberso:RemainingNetBookValueOfRetiredAssetsMember2024-12-310000092122so:GeorgiaPowerMemberso:RemainingNetBookValueOfRetiredAssetsMember2024-12-310000092122so:MississippiPowerMemberso:RemainingNetBookValueOfRetiredAssetsMember2024-12-310000092122so:SouthernCompanyGasMemberso:RemainingNetBookValueOfRetiredAssetsMember2024-12-310000092122us-gaap:DeferredIncomeTaxChargesMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:DeferredIncomeTaxChargesMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:DeferredIncomeTaxChargesMember2024-12-310000092122so:MississippiPowerMemberus-gaap:DeferredIncomeTaxChargesMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:DeferredIncomeTaxChargesMember2024-12-310000092122so:PropertyDamageReservesAssetMember2024-12-310000092122so:AlabamaPowerMemberso:PropertyDamageReservesAssetMember2024-12-310000092122so:GeorgiaPowerMemberso:PropertyDamageReservesAssetMember2024-12-310000092122so:MississippiPowerMemberso:PropertyDamageReservesAssetMember2024-12-310000092122so:SouthernCompanyGasMemberso:PropertyDamageReservesAssetMember2024-12-310000092122so:DeferredDepreciationMember2024-12-310000092122so:AlabamaPowerMemberso:DeferredDepreciationMember2024-12-310000092122so:GeorgiaPowerMemberso:DeferredDepreciationMember2024-12-310000092122so:MississippiPowerMemberso:DeferredDepreciationMember2024-12-310000092122so:SouthernCompanyGasMemberso:DeferredDepreciationMember2024-12-310000092122us-gaap:EnvironmentalRestorationCostsMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:EnvironmentalRestorationCostsMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:EnvironmentalRestorationCostsMember2024-12-310000092122so:MississippiPowerMemberus-gaap:EnvironmentalRestorationCostsMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:EnvironmentalRestorationCostsMember2024-12-310000092122us-gaap:RecoverableVacationPayMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:RecoverableVacationPayMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:RecoverableVacationPayMember2024-12-310000092122so:MississippiPowerMemberus-gaap:RecoverableVacationPayMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:RecoverableVacationPayMember2024-12-310000092122us-gaap:LossOnReacquiredDebtMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:LossOnReacquiredDebtMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:LossOnReacquiredDebtMember2024-12-310000092122so:MississippiPowerMemberus-gaap:LossOnReacquiredDebtMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:LossOnReacquiredDebtMember2024-12-310000092122so:SoftwareAndCloudComputingCostsMember2024-12-310000092122so:AlabamaPowerMemberso:SoftwareAndCloudComputingCostsMember2024-12-310000092122so:GeorgiaPowerMemberso:SoftwareAndCloudComputingCostsMember2024-12-310000092122so:MississippiPowerMemberso:SoftwareAndCloudComputingCostsMember2024-12-310000092122so:SouthernCompanyGasMemberso:SoftwareAndCloudComputingCostsMember2024-12-310000092122us-gaap:RegulatoryClauseRevenuesUnderRecoveredMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:RegulatoryClauseRevenuesUnderRecoveredMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:RegulatoryClauseRevenuesUnderRecoveredMember2024-12-310000092122so:MississippiPowerMemberus-gaap:RegulatoryClauseRevenuesUnderRecoveredMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:RegulatoryClauseRevenuesUnderRecoveredMember2024-12-310000092122so:RegulatoryClausesMember2024-12-310000092122so:AlabamaPowerMemberso:RegulatoryClausesMember2024-12-310000092122so:GeorgiaPowerMemberso:RegulatoryClausesMember2024-12-310000092122so:MississippiPowerMemberso:RegulatoryClausesMember2024-12-310000092122so:SouthernCompanyGasMemberso:RegulatoryClausesMember2024-12-310000092122so:NuclearOutageMember2024-12-310000092122so:AlabamaPowerMemberso:NuclearOutageMember2024-12-310000092122so:GeorgiaPowerMemberso:NuclearOutageMember2024-12-310000092122so:MississippiPowerMemberso:NuclearOutageMember2024-12-310000092122so:SouthernCompanyGasMemberso:NuclearOutageMember2024-12-310000092122so:FuelHedgingRealizedAndUnrealizedLossesMember2024-12-310000092122so:AlabamaPowerMemberso:FuelHedgingRealizedAndUnrealizedLossesMember2024-12-310000092122so:GeorgiaPowerMemberso:FuelHedgingRealizedAndUnrealizedLossesMember2024-12-310000092122so:MississippiPowerMemberso:FuelHedgingRealizedAndUnrealizedLossesMember2024-12-310000092122so:SouthernCompanyGasMemberso:FuelHedgingRealizedAndUnrealizedLossesMember2024-12-310000092122so:QualifyingRepairsOfNaturalGasDistributionSystemsMember2024-12-310000092122so:AlabamaPowerMemberso:QualifyingRepairsOfNaturalGasDistributionSystemsMember2024-12-310000092122so:GeorgiaPowerMemberso:QualifyingRepairsOfNaturalGasDistributionSystemsMember2024-12-310000092122so:MississippiPowerMemberso:QualifyingRepairsOfNaturalGasDistributionSystemsMember2024-12-310000092122so:SouthernCompanyGasMemberso:QualifyingRepairsOfNaturalGasDistributionSystemsMember2024-12-310000092122so:LongTermDebtFairValueAdjustmentMember2024-12-310000092122so:AlabamaPowerMemberso:LongTermDebtFairValueAdjustmentMember2024-12-310000092122so:GeorgiaPowerMemberso:LongTermDebtFairValueAdjustmentMember2024-12-310000092122so:MississippiPowerMemberso:LongTermDebtFairValueAdjustmentMember2024-12-310000092122so:SouthernCompanyGasMemberso:LongTermDebtFairValueAdjustmentMember2024-12-310000092122so:PlantDanielUnitsThreeAndFourMember2024-12-310000092122so:AlabamaPowerMemberso:PlantDanielUnitsThreeAndFourMember2024-12-310000092122so:GeorgiaPowerMemberso:PlantDanielUnitsThreeAndFourMember2024-12-310000092122so:MississippiPowerMemberso:PlantDanielUnitsThreeAndFourMember2024-12-310000092122so:SouthernCompanyGasMemberso:PlantDanielUnitsThreeAndFourMember2024-12-310000092122so:OtherRegulatoryAssetsMember2024-12-310000092122so:AlabamaPowerMemberso:OtherRegulatoryAssetsMember2024-12-310000092122so:GeorgiaPowerMemberso:OtherRegulatoryAssetsMember2024-12-310000092122so:MississippiPowerMemberso:OtherRegulatoryAssetsMember2024-12-310000092122so:SouthernCompanyGasMemberso:OtherRegulatoryAssetsMember2024-12-310000092122so:DeferredIncomeTaxCreditsMember2024-12-310000092122so:AlabamaPowerMemberso:DeferredIncomeTaxCreditsMember2024-12-310000092122so:GeorgiaPowerMemberso:DeferredIncomeTaxCreditsMember2024-12-310000092122so:MississippiPowerMemberso:DeferredIncomeTaxCreditsMember2024-12-310000092122so:SouthernCompanyGasMemberso:DeferredIncomeTaxCreditsMember2024-12-310000092122so:OtherCostOfRemovalObligationsMember2024-12-310000092122so:AlabamaPowerMemberso:OtherCostOfRemovalObligationsMember2024-12-310000092122so:GeorgiaPowerMemberso:OtherCostOfRemovalObligationsMember2024-12-310000092122so:MississippiPowerMemberso:OtherCostOfRemovalObligationsMember2024-12-310000092122so:SouthernCompanyGasMemberso:OtherCostOfRemovalObligationsMember2024-12-310000092122so:OverRecoveredRegulatoryClauseRevenuesMember2024-12-310000092122so:AlabamaPowerMemberso:OverRecoveredRegulatoryClauseRevenuesMember2024-12-310000092122so:GeorgiaPowerMemberso:OverRecoveredRegulatoryClauseRevenuesMember2024-12-310000092122so:MississippiPowerMemberso:OverRecoveredRegulatoryClauseRevenuesMember2024-12-310000092122so:SouthernCompanyGasMemberso:OverRecoveredRegulatoryClauseRevenuesMember2024-12-310000092122so:ReliabilityReserveLiabilityMember2024-12-310000092122so:AlabamaPowerMemberso:ReliabilityReserveLiabilityMember2024-12-310000092122so:GeorgiaPowerMemberso:ReliabilityReserveLiabilityMember2024-12-310000092122so:MississippiPowerMemberso:ReliabilityReserveLiabilityMember2024-12-310000092122so:SouthernCompanyGasMemberso:ReliabilityReserveLiabilityMember2024-12-310000092122so:StormAndPropertyDamageReservesLiabilityMember2024-12-310000092122so:AlabamaPowerMemberso:StormAndPropertyDamageReservesLiabilityMember2024-12-310000092122so:GeorgiaPowerMemberso:StormAndPropertyDamageReservesLiabilityMember2024-12-310000092122so:MississippiPowerMemberso:StormAndPropertyDamageReservesLiabilityMember2024-12-310000092122so:SouthernCompanyGasMemberso:StormAndPropertyDamageReservesLiabilityMember2024-12-310000092122so:NuclearFuelDisposalCostRecoveryMember2024-12-310000092122so:AlabamaPowerMemberso:NuclearFuelDisposalCostRecoveryMember2024-12-310000092122so:GeorgiaPowerMemberso:NuclearFuelDisposalCostRecoveryMember2024-12-310000092122so:MississippiPowerMemberso:NuclearFuelDisposalCostRecoveryMember2024-12-310000092122so:SouthernCompanyGasMemberso:NuclearFuelDisposalCostRecoveryMember2024-12-310000092122so:OtherRegulatoryLiabilitiesMember2024-12-310000092122so:AlabamaPowerMemberso:OtherRegulatoryLiabilitiesMember2024-12-310000092122so:GeorgiaPowerMemberso:OtherRegulatoryLiabilitiesMember2024-12-310000092122so:MississippiPowerMemberso:OtherRegulatoryLiabilitiesMember2024-12-310000092122so:SouthernCompanyGasMemberso:OtherRegulatoryLiabilitiesMember2024-12-310000092122srt:MaximumMemberso:AlabamaPowerMemberus-gaap:AssetRetirementObligationCostsMember2025-12-310000092122srt:MaximumMemberso:GeorgiaPowerMemberus-gaap:AssetRetirementObligationCostsMember2025-12-310000092122srt:MaximumMemberso:MississippiPowerMemberus-gaap:AssetRetirementObligationCostsMember2025-12-310000092122srt:MaximumMemberso:SouthernCompanyGasMemberus-gaap:AssetRetirementObligationCostsMember2025-12-310000092122so:AlabamaPowerMemberso:CCRAssetRetirementObligationsCostMember2025-12-310000092122so:GeorgiaPowerMemberso:CCRAssetRetirementObligationsCostMember2025-12-310000092122so:MississippiPowerMemberso:CCRAssetRetirementObligationsCostMember2025-12-310000092122srt:MaximumMemberso:GeorgiaPowerMemberso:RetireeBenefitPlansMember2025-12-310000092122srt:MaximumMemberso:AlabamaPowerMemberso:RetireeBenefitPlansMember2025-12-310000092122srt:MaximumMemberso:MississippiPowerMemberso:RetireeBenefitPlansMember2025-12-310000092122srt:MaximumMemberso:SouthernCompanyGasMemberso:RetireeBenefitPlansMember2025-12-310000092122so:PlantGorgasUnits89And10Memberso:AlabamaPowerMemberso:RemainingNetBookValueOfRetiredAssetsMember2025-12-310000092122so:PlantGorgasUnits89And10Membersrt:MaximumMemberso:AlabamaPowerMemberso:RemainingNetBookValueOfRetiredAssetsMember2025-12-310000092122so:PlantBarryUnit4Memberso:AlabamaPowerMemberso:RemainingNetBookValueOfRetiredAssetsMember2025-12-310000092122so:PlantWansleyUnits1And2Memberso:GeorgiaPowerMemberso:RemainingNetBookValueOfRetiredAssetsMember2025-12-310000092122so:PlantHammondUnits1Through4AndPlantBranchUnits2Through4Memberso:GeorgiaPowerMemberso:RemainingNetBookValueOfRetiredAssetsMember2025-12-310000092122so:PlantHammondUnits1Through4AndPlantBranchUnits2Through4Membersrt:MaximumMemberso:GeorgiaPowerMemberso:RemainingNetBookValueOfRetiredAssetsMember2025-12-310000092122so:RetailElectricMemberso:PlantWatsonAndPlantGreeneCountyMemberso:MississippiPowerMemberso:RemainingNetBookValueOfRetiredAssetsMember2025-12-310000092122so:WholesaleElectricRevenuesMemberso:PlantWatsonAndPlantGreeneCountyMemberso:MississippiPowerMemberso:RemainingNetBookValueOfRetiredAssetsMember2025-12-310000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMemberus-gaap:DeferredIncomeTaxChargesMember2025-12-310000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMemberso:DeferredIncomeTaxCreditsMember2025-12-310000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMemberso:StateDeferredIncomeTaxLiabilityMember2025-12-310000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMemberus-gaap:DeferredIncomeTaxChargesMember2025-12-310000092122so:MississippiPowerMemberus-gaap:DeferredIncomeTaxChargesMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:DeferredIncomeTaxChargesMember2025-12-310000092122so:PlantVogtleUnits3And4Memberso:MississippiPowerMemberso:StormAndPropertyDamageReservesLiabilityMember2025-12-310000092122so:PlantBarryUnit5Memberso:AlabamaPowerMemberso:DeferredDepreciationMember2025-12-310000092122so:PlantBarryMemberso:AlabamaPowerMemberso:DeferredDepreciationMember2025-12-310000092122so:PlantGastonUnit5Memberso:AlabamaPowerMemberso:DeferredDepreciationMember2025-12-310000092122so:PlantSchererUnits1Through3Memberso:GeorgiaPowerMemberso:DeferredDepreciationMember2025-12-310000092122so:PlantBowenUnits1And2Memberso:GeorgiaPowerMemberso:DeferredDepreciationMember2025-12-310000092122so:PlantVogtleUnit3AndCommonFacilitiesMemberso:GeorgiaPowerMemberso:DeferredDepreciationMember2025-12-310000092122srt:MaximumMemberso:AlabamaPowerMemberus-gaap:RegulatoryClauseRevenuesUnderRecoveredMember2025-12-310000092122so:MississippiPowerMemberso:RegulatoryClausesAmortizedThroughPerformanceEvaluationPlanMember2025-12-310000092122srt:MaximumMemberso:AlabamaPowerMemberus-gaap:LossOnReacquiredDebtMember2025-12-310000092122srt:MaximumMemberso:GeorgiaPowerMemberus-gaap:LossOnReacquiredDebtMember2025-12-310000092122srt:MaximumMemberso:MississippiPowerMemberus-gaap:LossOnReacquiredDebtMember2025-12-310000092122srt:MaximumMemberso:SouthernCompanyGasMemberus-gaap:LossOnReacquiredDebtMember2025-12-310000092122so:PlantFarleyMemberso:AlabamaPowerMemberso:NuclearOutageMember2025-12-310000092122so:PlantHatchNuclearMembersrt:MaximumMemberso:GeorgiaPowerMemberso:NuclearOutageMember2025-12-310000092122so:AlabamaPowerMemberso:FuelHedgingRealizedAndUnrealizedLossesMember2023-01-010000092122so:SouthernCompanyGasMemberso:FuelHedgingRealizedAndUnrealizedLossesMember2023-01-010000092122so:AtlantaGasLightMemberso:QualifyingRepairsOfNaturalGasDistributionSystemsMember2025-12-310000092122so:GeorgiaPowerMemberso:FuelHedgingRealizedAndUnrealizedLossesMember2025-12-310000092122so:MississippiPowerMemberso:FuelHedgingRealizedAndUnrealizedLossesMember2025-12-310000092122srt:MaximumMemberso:SouthernCompanyGasMemberso:LongTermDebtFairValueAdjustmentMember2025-12-310000092122so:RetailElectricMemberso:PlantDanielUnitsThreeAndFourMember2025-12-310000092122so:WholesaleElectricRevenuesMemberso:PlantDanielUnitsThreeAndFourMember2025-12-310000092122so:PlantDanielUnits1And2Memberso:MississippiPowerMember2025-07-300000092122so:NuclearFuelDisposalCostRecoveryReturnedToCustomerMember2024-12-310000092122so:AlabamaPowerMemberso:FuelHedgingRealizedAndUnrealizedLossesMember2025-12-310000092122so:AlabamaPowerMember2023-06-300000092122so:AlabamaPowerMember2023-06-140000092122so:AlabamaPowerMember2023-06-130000092122so:AlabamaPowerMember2023-04-040000092122srt:MinimumMemberso:AlabamaPowerMember2025-01-012025-12-310000092122srt:MaximumMemberso:AlabamaPowerMember2025-01-012025-12-310000092122srt:MinimumMemberso:AlabamaPowerMember2023-01-012023-12-310000092122srt:MinimumMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:AlabamaPowerMember2025-01-310000092122so:AlabamaPowerMemberso:JurisdictionalSeparationStudyOrderJSSMember2025-06-050000092122so:AlabamaPowerMember2023-10-030000092122srt:ScenarioForecastMemberso:AlabamaPowerMember2026-12-310000092122so:AlabamaPowerMember2023-06-012023-06-300000092122so:PlantBarryUnit8Memberso:AlabamaPowerMember2021-01-012021-12-310000092122so:AlabamaPowerMember2023-12-010000092122so:TenaskaAlabamaPartnersL.P.Memberso:AlabamaPowerMember2025-08-132025-08-130000092122so:AlabamaPowerMemberso:OtherRegulatoryAssetsCurrentMember2025-12-310000092122so:AlabamaPowerMemberso:OtherRegulatoryAssetsCurrentMember2024-12-310000092122so:AlabamaPowerMemberso:OtherRegulatoryAssetsDeferredMember2025-12-310000092122so:AlabamaPowerMemberso:OtherRegulatoryAssetsDeferredMember2024-12-310000092122so:AlabamaPowerMember2024-01-012024-01-310000092122so:AlabamaPowerMember2023-11-012023-11-300000092122so:AlabamaPowerMember2024-05-012024-05-310000092122so:AlabamaPowerMember2024-12-012024-12-310000092122srt:ScenarioForecastMemberso:AlabamaPowerMember2026-01-012027-12-310000092122srt:ScenarioForecastMemberso:AlabamaPowerMember2028-01-012028-01-310000092122so:PlantGreeneCountyUnits1And2Memberso:MississippiPowerMember2025-12-310000092122so:PlantGreeneCountyUnits1And2Memberso:AlabamaPowerMember2025-12-310000092122so:MajorStormMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:MajorStormMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:AlabamaPowerMemberso:ReliabilityReserveLiabilityMember2025-01-012025-12-310000092122so:AlabamaPowerMemberso:ReliabilityReserveLiabilityMember2023-01-012023-12-310000092122so:AlabamaPowerMemberso:ReliabilityReserveLiabilityMember2024-01-012024-12-310000092122srt:ScenarioForecastMemberso:AlabamaPowerMemberso:ReliabilityReserveLiabilityMember2026-01-012026-12-310000092122so:OtherRegulatoryLiabilitiesCurrentMemberso:AlabamaPowerMemberso:ReliabilityReserveLiabilityMember2025-12-310000092122so:OtherRegulatoryLiabilitiesDeferredMemberso:AlabamaPowerMemberso:ReliabilityReserveLiabilityMember2025-12-310000092122so:PlantBarryUnit5Memberso:AlabamaPowerMember2025-01-012025-12-310000092122so:PlantBarryUnit5Memberso:AlabamaPowerMember2025-12-310000092122so:PlantBarryUnit5Membersrt:ScenarioForecastMemberso:AlabamaPowerMember2026-03-310000092122so:PlantBarryUnit5Membersrt:ScenarioForecastMemberso:SouthernPowerMember2026-03-310000092122so:AlabamaPowerMember2025-10-072025-10-070000092122so:GeorgiaPowerMemberso:TraditionalBaseMember2025-12-310000092122so:GeorgiaPowerMemberso:EnvironmentalComplianceCostRecoveryTraditionalMember2025-12-310000092122so:GeorgiaPowerMemberso:DemandSideManagementMember2025-12-310000092122so:GeorgiaPowerMemberso:MunicipalFranchiseFeeMember2025-12-310000092122so:GeorgiaPowerMemberso:TraditionalBaseGeorgiaStateMember2025-12-310000092122so:GeorgiaPowerMemberso:InvestmentTaxCreditMember2025-12-310000092122so:GeorgiaPowerMemberso:EnvironmentalComplianceCostRecoveryTraditionalMember2025-01-012025-12-310000092122so:EnvironmentalComplianceCostRecoveryTraditionalMembersrt:ScenarioForecastMemberso:GeorgiaPowerMember2026-01-012026-12-310000092122so:GeorgiaPowerMemberso:EnvironmentalComplianceCostRecoveryTraditionalMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberso:EnvironmentalComplianceCostRecoveryTraditionalMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberso:A2022AlternateRatePlanMember2025-12-310000092122so:A2022AlternateRatePlanMembersrt:MinimumMemberso:GeorgiaPowerMember2025-12-310000092122so:A2022AlternateRatePlanMembersrt:MaximumMemberso:GeorgiaPowerMember2025-12-310000092122so:GeorgiaPowerMemberso:A2022AlternateRatePlanMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberso:PlantSchererUnitThreeMember2025-07-152025-07-150000092122so:GeorgiaPowerMemberso:PlantSchererUnitThreeMember2025-07-150000092122so:SegcoMemberso:GeorgiaPowerMember2025-07-152025-07-150000092122so:SegcoMemberso:GeorgiaPowerMember2025-07-150000092122so:SegcoMemberso:AlabamaPowerMember2025-07-150000092122so:GeorgiaPowerMemberso:PlantBowenUnits1Through4Member2025-07-152025-07-150000092122so:GeorgiaPowerMemberso:PlantSchererCoalUnitsOneAndTwoMember2025-07-152025-07-150000092122so:GeorgiaPowerMemberso:PlantSchererCoalUnitsOneAndTwoMember2025-07-150000092122so:GeorgiaPowerMemberso:PlantMcIntoshUnits10And11Member2025-07-152025-07-150000092122so:GeorgiaPowerMemberso:PlantMcIntoshUnits1Through8Member2025-07-152025-07-150000092122so:GeorgiaPowerMemberso:PlantVogtleNuclearUnitsOneAndTwoMember2025-07-152025-07-150000092122so:GeorgiaPowerMemberso:PlantVogtleNuclearUnitsOneAndTwoMember2025-07-150000092122so:GeorgiaPowerMemberso:HydroOperationsMember2025-07-152025-07-150000092122so:GeorgiaPowerMember2025-07-152025-07-150000092122so:GeorgiaPowerMemberso:PlantSchererUnit3Member2025-07-152025-07-150000092122so:GeorgiaPowerMember2025-09-042025-09-040000092122so:GeorgiaPowerMember2025-12-192025-12-190000092122srt:MaximumMemberso:GeorgiaPowerMember2025-12-192025-12-190000092122so:FirstProjectGroupMemberso:GeorgiaPowerMember2025-12-192025-12-190000092122so:SecondProjectGroupMemberso:GeorgiaPowerMember2025-12-192025-12-190000092122so:ThirdProjectGroupMemberso:GeorgiaPowerMember2025-12-192025-12-190000092122so:FourthProjectGroupMemberso:GeorgiaPowerMember2025-12-192025-12-190000092122so:AffiliatePPAMemberso:GeorgiaPowerMember2025-12-192025-12-190000092122so:FirstPPAMemberso:GeorgiaPowerMember2025-12-192025-12-190000092122so:SecondPPAMemberso:GeorgiaPowerMember2025-12-192025-12-190000092122srt:MinimumMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:GeorgiaPowerMember2025-09-012025-12-310000092122srt:MaximumMemberso:GeorgiaPowerMember2025-09-172025-09-170000092122so:BatteryEnergyStorageFacilitiesMemberso:GeorgiaPowerMemberus-gaap:SubsequentEventMember2026-02-112026-02-110000092122us-gaap:DisposalGroupHeldforsaleNotDiscontinuedOperationsMemberso:SouthernCompanyAndGeorgiaPowerMember2024-03-070000092122us-gaap:DisposalGroupHeldforsaleNotDiscontinuedOperationsMemberso:SouthernCompanyAndGeorgiaPowerMember2024-04-242024-04-240000092122us-gaap:DisposalGroupHeldforsaleNotDiscontinuedOperationsMemberso:SouthernCompanyAndGeorgiaPowerMember2025-04-012025-06-300000092122so:GeorgiaPowerMember2023-05-012023-05-3100000921222023-05-310000092122srt:MaximumMemberso:GeorgiaPowerMember2023-05-012023-05-310000092122so:GeorgiaPowerMemberus-gaap:SubsequentEventMember2026-02-172026-02-170000092122so:GeorgiaPowerMemberso:UnderRecoveredFuelClauseRevenuesMember2025-12-310000092122so:GeorgiaPowerMemberso:DeferredUnderRecoveredFuelClauseRevenuesMember2025-12-310000092122so:GeorgiaPowerMemberso:UnderRecoveredFuelClauseRevenuesMember2024-12-310000092122so:GeorgiaPowerMemberso:DeferredUnderRecoveredFuelClauseRevenuesMember2024-12-310000092122so:GeorgiaPowerMember2023-01-012023-01-010000092122so:MajorStormMemberso:GeorgiaPowerMember2024-09-012024-09-300000092122so:MajorStormMemberso:GeorgiaPowerMember2025-12-310000092122so:GeorgiaPowerMemberso:OtherRegulatoryAssetsCurrentMember2024-12-310000092122so:GeorgiaPowerMemberso:OtherRegulatoryAssetsMember2025-12-310000092122so:GeorgiaPowerMemberso:OtherRegulatoryAssetsMember2024-12-310000092122so:GeorgiaPSCMemberso:GeorgiaPowerMemberus-gaap:SubsequentEventMember2026-02-172026-02-170000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMember2025-12-310000092122so:GeorgiaPowerMember2025-07-012025-09-300000092122so:GeorgiaPowerMember2025-10-012025-12-310000092122so:MEAGPowerMemberso:PlantVogtleUnits3And4Memberso:GeorgiaPowerMember2022-01-012022-12-310000092122so:OglethorpePowerCorporationMemberso:PlantVogtleUnits3And4Memberso:GeorgiaPowerMember2023-10-012023-10-310000092122so:DaltonUtilitiesMemberso:PlantVogtleUnits3And4Memberso:GeorgiaPowerMember2023-10-012023-10-3100000921222022-01-012022-12-310000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMember2023-10-012023-10-310000092122so:PlantVogtleUnit3Memberso:GeorgiaPowerMember2022-01-012022-12-310000092122so:PlantVogtleUnit3Memberso:GeorgiaPowerMember2023-08-012023-08-010000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMember2009-01-012009-12-310000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMember2022-01-012022-12-310000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMember2024-05-012024-05-010000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMember2025-04-012025-06-300000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMember2024-04-012024-04-300000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMember2024-10-012024-12-310000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMember2023-12-310000092122so:McGrauFordMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:TwiggsCountyMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:WadleyMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:PlantBowenPhase1Memberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:PlantBowenPhase2Memberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:SouthHallMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:PlantWansleyMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:PlantYatesPhase1Memberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:PlantYatesPhase2Memberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:ThomsonMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:HammondPhase2Memberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:PlantMcIntoshMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:VariousFacilitiesMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:LaurensCountyMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:PlantMitchellMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:PlantBowenUnit7Memberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:PlantBowenUnit8Memberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:PlantMcIntoshUnit12Memberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:PlantWansleyUnit10Memberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:PlantWansleyUnit11Memberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:PlantYatesUnit8Memberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:PlantYatesUnit9Memberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:PlantYatesUnit10Memberso:GeorgiaPowerMember2025-01-012025-12-310000092122srt:WeightedAverageMemberso:MeasurementInputAverageCustomerPriceMemberso:MississippiPowerMember2025-12-310000092122srt:WeightedAverageMemberso:MeasurementInputServiceReliabilityMemberso:MississippiPowerMember2025-12-310000092122srt:WeightedAverageMemberso:MeasurementInputCustomerSatisfactionMemberso:MississippiPowerMember2025-12-310000092122so:MississippiPowerMemberso:MississippiPSCPEPFilingMember2025-06-172025-06-170000092122so:MississippiPowerMemberso:MississippiPSCPEPFilingMember2025-04-012025-04-300000092122so:MississippiPowerMemberso:MississippiPSCPEPFilingMember2025-07-012025-07-310000092122so:MississippiPowerMemberso:MississippiPSCPEPFilingMember2025-11-172025-11-170000092122so:MississippiPowerMember2023-10-012023-10-310000092122so:AffiliatePPAMemberso:MississippiPowerMember2025-07-082025-07-080000092122so:MississippiPowerMember2024-04-012024-04-300000092122so:PlantWatsonUnit4Memberso:MississippiPowerMember2024-04-300000092122so:PlantGreeneCountyUnits1And2Memberso:MississippiPowerMember2024-04-300000092122so:AlabamaPowerMemberso:PlantGreeneCountyUnits1And2Memberso:MississippiPowerMember2024-04-300000092122so:PlantDanielUnits1And2Memberso:MississippiPowerMember2024-04-300000092122so:MississippiPowerMember2025-01-092025-01-090000092122so:PlantDanielUnits1And2Memberso:MississippiPowerMember2025-12-310000092122so:PlantDanielUnits1And2Memberso:MississippiPowerMember2025-07-302025-07-300000092122so:MississippiPowerMemberso:EnvironmentalComplianceOverviewPlanMember2023-04-012023-04-300000092122so:MississippiPowerMemberso:EnvironmentalComplianceOverviewPlanMember2024-05-012024-05-310000092122so:MississippiPowerMemberso:EnvironmentalComplianceOverviewPlanMember2025-04-012025-04-300000092122so:EnvironmentalComplianceOverviewPlanMemberso:MississippiPowerMemberus-gaap:SubsequentEventMember2026-02-132026-02-130000092122us-gaap:RetailMemberso:MississippiPowerMember2024-02-062024-02-060000092122us-gaap:RetailMemberso:MississippiPowerMember2023-10-310000092122us-gaap:RetailMemberso:MississippiPowerMember2024-10-310000092122us-gaap:RetailMemberso:MississippiPowerMemberus-gaap:SubsequentEventMember2026-01-132026-01-130000092122us-gaap:RetailMemberso:MississippiPowerMember2025-10-310000092122us-gaap:RetailMemberso:MississippiPowerMember2025-12-310000092122us-gaap:RetailMemberso:MississippiPowerMember2024-12-310000092122so:RetailECMMemberso:MississippiPowerMember2024-12-310000092122so:MraRevenueMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:MraRevenueMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:MraRevenueMembersrt:ScenarioForecastMemberso:MississippiPowerMember2026-01-012026-12-310000092122so:MraRevenueMemberso:MississippiPowerMember2025-12-310000092122so:MraRevenueMemberso:MississippiPowerMember2024-12-310000092122so:WholesaleMBMemberso:MississippiPowerMember2024-12-310000092122so:WholesaleMBMemberso:MississippiPowerMember2025-12-310000092122so:MississippiPowerMember2023-06-012023-06-300000092122so:MississippiPowerMember2024-07-012024-07-310000092122so:MississippiPowerMember2025-09-012025-09-300000092122so:MajorStormMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:MajorStormMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:MajorStormMemberso:MississippiPowerMember2023-01-012023-12-310000092122us-gaap:RetailMemberso:MississippiPowerMember2025-12-310000092122us-gaap:RetailMemberso:MississippiPowerMember2024-12-310000092122so:MississippiPowerMember2023-01-010000092122so:MississippiPowerMember2024-04-300000092122so:MississippiPowerMember2025-06-170000092122us-gaap:RetailMemberso:MississippiPowerMember2025-06-160000092122us-gaap:RetailMemberso:MississippiPowerMember2025-06-170000092122so:MississippiPowerMemberso:ReliabilityReserveLiabilityMember2023-12-310000092122so:MississippiPowerMemberso:ReliabilityReserveLiabilityMember2025-01-012025-12-310000092122so:OtherRegulatoryLiabilitiesCurrentMemberso:MississippiPowerMemberso:ReliabilityReserveLiabilityMember2025-12-310000092122so:OtherRegulatoryLiabilitiesDeferredMemberso:MississippiPowerMemberso:ReliabilityReserveLiabilityMember2025-12-310000092122so:MississippiPowerMemberso:ReliabilityReserveLiabilityMemberus-gaap:SubsequentEventMember2026-01-132026-01-130000092122so:CooperativeEnergyMemberso:MississippiPowerMember2022-08-310000092122so:CooperativeEnergyMemberso:MississippiPowerMember2025-12-310000092122so:MississippiPowerMemberso:MunicipalAndRuralAssociationsTariffMember2024-05-282024-05-280000092122so:MississippiPowerMemberso:MunicipalAndRuralAssociationsTariffMember2024-12-232024-12-230000092122so:MississippiPowerMemberso:MunicipalAndRuralAssociationsTariffMember2024-12-230000092122so:NicorGasMember2025-11-192025-11-190000092122so:AtlantaGasLightMember2025-01-012025-12-310000092122so:VirginiaNaturalGasMember2025-12-172025-12-170000092122so:ChattanoogaGasMember2025-01-012025-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasDistributionOperationsMember2025-01-012025-12-310000092122so:SAVEMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:SAVEMemberso:SouthernCompanyGasMember2025-12-310000092122so:SystemReinforcementRiderMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:SystemReinforcementRiderMemberso:SouthernCompanyGasMember2025-12-310000092122so:PipelineReplacementProgramMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:PipelineReplacementProgramMemberso:SouthernCompanyGasMember2025-12-310000092122so:SAVEMemberso:VirginiaNaturalGasMemberso:Year2023Member2025-12-310000092122so:SAVEMemberso:VirginiaNaturalGasMemberso:Year2024Member2025-12-310000092122so:SAVEMemberso:VirginiaNaturalGasMember2025-12-310000092122so:SAVEMemberso:VirginiaNaturalGasMember2025-01-012025-12-310000092122so:SAVEMemberso:SouthernCompanyGasMemberso:A2025Member2024-06-010000092122so:SAVEMemberso:SouthernCompanyGasMemberso:A2026Member2024-06-010000092122so:SAVEMemberso:SouthernCompanyGasMemberso:A2029Member2024-06-010000092122so:SAVEMemberso:SouthernCompanyGasMemberso:A2028Member2024-06-010000092122so:SAVEMemberso:SouthernCompanyGasMemberso:A2027Member2024-06-010000092122so:SAVEMemberso:SouthernCompanyGasMember2024-06-010000092122so:SAVEMemberso:SouthernCompanyGasMember2024-06-012024-06-300000092122so:AtlantaGasLightMember2022-01-012024-12-310000092122so:ChattanoogaGasMember2021-01-012021-12-310000092122so:ChattanoogaGasMember2021-12-310000092122so:ChattanoogaGasMember2025-06-012025-06-300000092122srt:MaximumMemberso:NicorGasMember2014-01-012014-12-310000092122so:InvestingInIllinoisQualifyingInfrastructurePlantMemberso:NicorGasMember2019-01-012019-12-310000092122so:NicorGasMember2024-04-012024-06-300000092122so:InvestingInIllinoisQualifyingInfrastructurePlantMemberso:NicorGasMember2023-04-012023-06-300000092122so:InvestingInIllinoisQualifyingInfrastructurePlantMemberso:NicorGasMember2024-12-242024-12-240000092122so:CompleteMemberso:InvestingInIllinoisQualifyingInfrastructurePlantMemberso:NicorGasMember2025-01-012025-12-310000092122so:CompleteAppealedMemberso:InvestingInIllinoisQualifyingInfrastructurePlantMemberso:NicorGasMember2025-01-012025-12-310000092122so:FiledOnMarch192021Memberso:InvestingInIllinoisQualifyingInfrastructurePlantMemberso:NicorGasMember2025-01-012025-12-310000092122so:FiledOnMarch182022Memberso:InvestingInIllinoisQualifyingInfrastructurePlantMemberso:NicorGasMember2025-01-012025-12-310000092122so:FiledOnMarch202023Memberso:InvestingInIllinoisQualifyingInfrastructurePlantMemberso:NicorGasMember2025-01-012025-12-310000092122so:FilingOnOrBeforeMarch202024Memberso:InvestingInIllinoisQualifyingInfrastructurePlantMemberso:NicorGasMember2025-01-012025-12-310000092122so:InvestingInIllinoisQualifyingInfrastructurePlantMemberso:NicorGasMember2025-01-012025-12-310000092122so:SouthernCompanyGasMemberso:NaturalGasCostUnderRecoveryMember2025-12-310000092122so:SouthernCompanyGasMemberso:NaturalGasCostUnderRecoveryMember2024-12-310000092122so:NicorGasMember2023-01-012023-12-310000092122so:InvestingInIllinoisQualifyingInfrastructurePlantMemberso:NicorGasMember2023-01-012023-12-310000092122so:QIPRiderMemberso:NicorGasMember2023-11-012023-11-300000092122so:OtherTransmissionAndDistributionCapitalInvestmentsMemberso:NicorGasMember2023-11-012023-11-300000092122so:NicorGasMember2023-10-012023-12-310000092122so:NicorGasMember2025-12-222025-12-220000092122so:NicorGasMember2025-01-012025-12-310000092122so:NicorGasMemberus-gaap:SubsequentEventMember2026-01-092026-01-090000092122srt:MinimumMemberso:AtlantaGasLightMember2025-01-012025-12-310000092122srt:MaximumMemberso:AtlantaGasLightMember2025-01-012025-12-310000092122so:AtlantaGasLightMember2021-04-012021-04-300000092122srt:MinimumMemberso:AtlantaGasLightMember2021-04-300000092122srt:MaximumMemberso:AtlantaGasLightMember2021-04-300000092122so:AtlantaGasLightMember2021-11-012021-11-300000092122so:AtlantaGasLightMember2024-01-012024-12-310000092122so:AtlantaGasLightMember2021-11-300000092122so:SouthernCompanyGasMember2024-01-012024-01-010000092122so:SouthernCompanyGasMember2025-01-012025-01-010000092122srt:ScenarioForecastMemberso:SouthernCompanyGasMember2026-01-012026-01-010000092122srt:ScenarioForecastMemberso:SouthernCompanyGasMember2027-01-012027-01-010000092122so:AtlantaGasLightMember2024-07-022024-07-020000092122so:VirginiaNaturalGasMember2023-01-012023-12-310000092122so:VirginiaNaturalGasMember2023-01-012023-01-010000092122so:VirginiaNaturalGasMemberso:VirginiaCommissionMember2025-12-172025-12-170000092122so:AtlantaGasLightMemberso:RegulatoryAssetOffBalanceSheetMember2025-12-310000092122so:AtlantaGasLightMemberso:RegulatoryAssetOffBalanceSheetMember2024-12-310000092122so:VirginiaNaturalGasMemberso:RegulatoryAssetOffBalanceSheetMember2025-12-310000092122so:VirginiaNaturalGasMemberso:RegulatoryAssetOffBalanceSheetMember2024-12-310000092122so:ChattanoogaGasMemberso:RegulatoryAssetOffBalanceSheetMember2025-12-310000092122so:ChattanoogaGasMemberso:RegulatoryAssetOffBalanceSheetMember2024-12-310000092122so:SouthernCompanyGasMemberso:RegulatoryAssetOffBalanceSheetMember2025-12-310000092122so:SouthernCompanyGasMemberso:RegulatoryAssetOffBalanceSheetMember2024-12-310000092122so:KemperIgccMemberso:MississippiPowerMember2010-12-310000092122so:KemperIgccMemberso:MississippiPowerMember2016-12-310000092122so:KemperIgccMemberso:MississippiPowerMember2018-01-012018-12-310000092122so:SouthernCompanyMember2025-12-310000092122so:SouthernCompanyMember2024-12-310000092122us-gaap:PositiveOutcomeOfLitigationMemberso:AlabamaPowerMember2011-01-012019-12-310000092122so:CourtOfFederalClaimsMemberso:GeorgiaPowerMember2011-01-012019-12-310000092122so:AlabamaPowerAndGeorgiaPowerMember2025-12-310000092122so:AlabamaPowerAndGeorgiaPowerMember2025-01-012025-12-310000092122so:KemperIgccMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:KemperIgccMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:KemperIgccMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:MississippiPowerMember2025-03-312025-03-310000092122so:MississippiPowerMember2025-11-042025-11-040000092122so:MississippiPowerMember2025-03-312025-11-030000092122so:MississippiPowerMember2025-11-052025-11-050000092122so:MississippiPowerMemberus-gaap:SubsequentEventMember2026-01-130000092122so:GeorgiaPowerMemberso:MEAGPowerMember2025-12-310000092122so:GeorgiaPowerMemberso:PlantVogtleNuclearUnitsOneAndTwoMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberso:PlantVogtleNuclearUnitsOneAndTwoMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberso:PlantVogtleNuclearUnitsOneAndTwoMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberso:PlantVogtleNuclearUnitsOneAndTwoMember2025-12-310000092122so:AlabamaPowerMemberso:SouthernElectricGeneratingCompanyMember2025-12-310000092122so:RetailElectricResidentialMember2025-01-012025-12-310000092122so:RetailElectricResidentialMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:RetailElectricResidentialMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:RetailElectricResidentialMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:RetailElectricResidentialMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:RetailElectricResidentialMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:RetailElectricCommercialMember2025-01-012025-12-310000092122so:RetailElectricCommercialMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:RetailElectricCommercialMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:RetailElectricCommercialMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:RetailElectricCommercialMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:RetailElectricCommercialMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:RetailElectricIndustrialMember2025-01-012025-12-310000092122so:RetailElectricIndustrialMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:RetailElectricIndustrialMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:RetailElectricIndustrialMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:RetailElectricIndustrialMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:RetailElectricIndustrialMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:RetailElectricOtherMember2025-01-012025-12-310000092122so:RetailElectricOtherMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:RetailElectricOtherMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:RetailElectricOtherMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:RetailElectricOtherMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:RetailElectricOtherMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:RetailElectricMember2025-01-012025-12-310000092122so:RetailElectricMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:RetailElectricMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:RetailElectricMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:RetailElectricMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:RetailElectricMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:NaturalGasDistributionResidentialMember2025-01-012025-12-310000092122so:NaturalGasDistributionResidentialMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionResidentialMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionResidentialMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionResidentialMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionResidentialMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:NaturalGasDistributionCommercialMember2025-01-012025-12-310000092122so:NaturalGasDistributionCommercialMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionCommercialMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionCommercialMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionCommercialMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionCommercialMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:NaturalGasDistributionTransportationMember2025-01-012025-12-310000092122so:NaturalGasDistributionTransportationMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionTransportationMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionTransportationMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionTransportationMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionTransportationMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:NaturalGasDistributionIndustrialMember2025-01-012025-12-310000092122so:NaturalGasDistributionIndustrialMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionIndustrialMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionIndustrialMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionIndustrialMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionIndustrialMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:NaturalGasDistributionOtherMember2025-01-012025-12-310000092122so:NaturalGasDistributionOtherMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionOtherMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionOtherMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionOtherMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionOtherMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:NaturalGasDistributionMember2025-01-012025-12-310000092122so:NaturalGasDistributionMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:NaturalGasDistributionMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMember2025-01-012025-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:WholesaleElectricPPACapacityRevenuesMember2025-01-012025-12-310000092122so:WholesaleElectricPPACapacityRevenuesMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:WholesaleElectricPPACapacityRevenuesMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:WholesaleElectricPPACapacityRevenuesMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:WholesaleElectricPPACapacityRevenuesMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:WholesaleElectricPPACapacityRevenuesMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:WholesaleElectricNonPPARevenuesMember2025-01-012025-12-310000092122so:WholesaleElectricNonPPARevenuesMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:WholesaleElectricNonPPARevenuesMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:WholesaleElectricNonPPARevenuesMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:WholesaleElectricNonPPARevenuesMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:WholesaleElectricNonPPARevenuesMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:WholesaleElectricRevenuesMember2025-01-012025-12-310000092122so:WholesaleElectricRevenuesMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:WholesaleElectricRevenuesMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:WholesaleElectricRevenuesMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:WholesaleElectricRevenuesMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:WholesaleElectricRevenuesMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:OtherNaturalGasGasMarketingServicesMember2025-01-012025-12-310000092122so:OtherNaturalGasGasMarketingServicesMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:OtherNaturalGasGasMarketingServicesMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:OtherNaturalGasGasMarketingServicesMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:OtherNaturalGasGasMarketingServicesMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:OtherNaturalGasGasMarketingServicesMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMember2025-01-012025-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:OtherNaturalGasMember2025-01-012025-12-310000092122so:OtherNaturalGasMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:OtherNaturalGasMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:OtherNaturalGasMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:OtherNaturalGasMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:OtherNaturalGasMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:OtherRevenuesMember2025-01-012025-12-310000092122so:OtherRevenuesMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:OtherRevenuesMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:OtherRevenuesMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:OtherRevenuesMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:OtherRevenuesMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:OtherRevenueSourcesMember2025-01-012025-12-310000092122so:OtherRevenueSourcesMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:OtherRevenueSourcesMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:OtherRevenueSourcesMemberso:MississippiPowerMember2025-01-012025-12-310000092122so:OtherRevenueSourcesMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:OtherRevenueSourcesMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:RetailElectricResidentialMember2024-01-012024-12-310000092122so:RetailElectricResidentialMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:RetailElectricResidentialMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:RetailElectricResidentialMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:RetailElectricResidentialMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:RetailElectricResidentialMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:RetailElectricCommercialMember2024-01-012024-12-310000092122so:RetailElectricCommercialMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:RetailElectricCommercialMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:RetailElectricCommercialMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:RetailElectricCommercialMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:RetailElectricCommercialMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:RetailElectricIndustrialMember2024-01-012024-12-310000092122so:RetailElectricIndustrialMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:RetailElectricIndustrialMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:RetailElectricIndustrialMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:RetailElectricIndustrialMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:RetailElectricIndustrialMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:RetailElectricOtherMember2024-01-012024-12-310000092122so:RetailElectricOtherMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:RetailElectricOtherMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:RetailElectricOtherMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:RetailElectricOtherMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:RetailElectricOtherMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:RetailElectricMember2024-01-012024-12-310000092122so:RetailElectricMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:RetailElectricMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:RetailElectricMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:RetailElectricMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:RetailElectricMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:NaturalGasDistributionResidentialMember2024-01-012024-12-310000092122so:NaturalGasDistributionResidentialMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionResidentialMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionResidentialMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionResidentialMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionResidentialMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:NaturalGasDistributionCommercialMember2024-01-012024-12-310000092122so:NaturalGasDistributionCommercialMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionCommercialMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionCommercialMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionCommercialMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionCommercialMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:NaturalGasDistributionTransportationMember2024-01-012024-12-310000092122so:NaturalGasDistributionTransportationMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionTransportationMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionTransportationMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionTransportationMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionTransportationMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:NaturalGasDistributionIndustrialMember2024-01-012024-12-310000092122so:NaturalGasDistributionIndustrialMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionIndustrialMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionIndustrialMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionIndustrialMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionIndustrialMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:NaturalGasDistributionOtherMember2024-01-012024-12-310000092122so:NaturalGasDistributionOtherMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionOtherMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionOtherMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionOtherMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionOtherMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:NaturalGasDistributionMember2024-01-012024-12-310000092122so:NaturalGasDistributionMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:NaturalGasDistributionMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMember2024-01-012024-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:WholesaleElectricPPACapacityRevenuesMember2024-01-012024-12-310000092122so:WholesaleElectricPPACapacityRevenuesMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:WholesaleElectricPPACapacityRevenuesMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:WholesaleElectricPPACapacityRevenuesMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:WholesaleElectricPPACapacityRevenuesMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:WholesaleElectricPPACapacityRevenuesMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:WholesaleElectricNonPPARevenuesMember2024-01-012024-12-310000092122so:WholesaleElectricNonPPARevenuesMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:WholesaleElectricNonPPARevenuesMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:WholesaleElectricNonPPARevenuesMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:WholesaleElectricNonPPARevenuesMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:WholesaleElectricNonPPARevenuesMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:WholesaleElectricRevenuesMember2024-01-012024-12-310000092122so:WholesaleElectricRevenuesMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:WholesaleElectricRevenuesMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:WholesaleElectricRevenuesMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:WholesaleElectricRevenuesMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:WholesaleElectricRevenuesMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:OtherNaturalGasGasMarketingServicesMember2024-01-012024-12-310000092122so:OtherNaturalGasGasMarketingServicesMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:OtherNaturalGasGasMarketingServicesMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:OtherNaturalGasGasMarketingServicesMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:OtherNaturalGasGasMarketingServicesMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:OtherNaturalGasGasMarketingServicesMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMember2024-01-012024-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:OtherNaturalGasMember2024-01-012024-12-310000092122so:OtherNaturalGasMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:OtherNaturalGasMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:OtherNaturalGasMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:OtherNaturalGasMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:OtherNaturalGasMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:OtherRevenuesMember2024-01-012024-12-310000092122so:OtherRevenuesMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:OtherRevenuesMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:OtherRevenuesMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:OtherRevenuesMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:OtherRevenuesMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:OtherRevenueSourcesMember2024-01-012024-12-310000092122so:OtherRevenueSourcesMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:OtherRevenueSourcesMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:OtherRevenueSourcesMemberso:MississippiPowerMember2024-01-012024-12-310000092122so:OtherRevenueSourcesMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:OtherRevenueSourcesMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:RetailElectricResidentialMember2023-01-012023-12-310000092122so:RetailElectricResidentialMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:RetailElectricResidentialMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:RetailElectricResidentialMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:RetailElectricResidentialMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:RetailElectricResidentialMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:RetailElectricCommercialMember2023-01-012023-12-310000092122so:RetailElectricCommercialMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:RetailElectricCommercialMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:RetailElectricCommercialMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:RetailElectricCommercialMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:RetailElectricCommercialMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:RetailElectricIndustrialMember2023-01-012023-12-310000092122so:RetailElectricIndustrialMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:RetailElectricIndustrialMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:RetailElectricIndustrialMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:RetailElectricIndustrialMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:RetailElectricIndustrialMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:RetailElectricOtherMember2023-01-012023-12-310000092122so:RetailElectricOtherMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:RetailElectricOtherMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:RetailElectricOtherMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:RetailElectricOtherMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:RetailElectricOtherMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:RetailElectricMember2023-01-012023-12-310000092122so:RetailElectricMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:RetailElectricMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:RetailElectricMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:RetailElectricMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:RetailElectricMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:NaturalGasDistributionResidentialMember2023-01-012023-12-310000092122so:NaturalGasDistributionResidentialMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionResidentialMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionResidentialMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionResidentialMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionResidentialMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:NaturalGasDistributionCommercialMember2023-01-012023-12-310000092122so:NaturalGasDistributionCommercialMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionCommercialMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionCommercialMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionCommercialMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionCommercialMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:NaturalGasDistributionTransportationMember2023-01-012023-12-310000092122so:NaturalGasDistributionTransportationMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionTransportationMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionTransportationMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionTransportationMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionTransportationMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:NaturalGasDistributionIndustrialMember2023-01-012023-12-310000092122so:NaturalGasDistributionIndustrialMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionIndustrialMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionIndustrialMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionIndustrialMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionIndustrialMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:NaturalGasDistributionOtherMember2023-01-012023-12-310000092122so:NaturalGasDistributionOtherMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionOtherMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionOtherMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionOtherMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionOtherMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:NaturalGasDistributionMember2023-01-012023-12-310000092122so:NaturalGasDistributionMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:NaturalGasDistributionMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMember2023-01-012023-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:WholesaleElectricPPAEnergyRevenuesMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:WholesaleElectricPPACapacityRevenuesMember2023-01-012023-12-310000092122so:WholesaleElectricPPACapacityRevenuesMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:WholesaleElectricPPACapacityRevenuesMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:WholesaleElectricPPACapacityRevenuesMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:WholesaleElectricPPACapacityRevenuesMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:WholesaleElectricPPACapacityRevenuesMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:WholesaleElectricNonPPARevenuesMember2023-01-012023-12-310000092122so:WholesaleElectricNonPPARevenuesMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:WholesaleElectricNonPPARevenuesMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:WholesaleElectricNonPPARevenuesMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:WholesaleElectricNonPPARevenuesMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:WholesaleElectricNonPPARevenuesMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:WholesaleElectricRevenuesMember2023-01-012023-12-310000092122so:WholesaleElectricRevenuesMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:WholesaleElectricRevenuesMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:WholesaleElectricRevenuesMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:WholesaleElectricRevenuesMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:WholesaleElectricRevenuesMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:OtherNaturalGasGasMarketingServicesMember2023-01-012023-12-310000092122so:OtherNaturalGasGasMarketingServicesMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:OtherNaturalGasGasMarketingServicesMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:OtherNaturalGasGasMarketingServicesMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:OtherNaturalGasGasMarketingServicesMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:OtherNaturalGasGasMarketingServicesMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMember2023-01-012023-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:OtherNaturalGasOtherNaturalGasRevenuesMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:OtherNaturalGasMember2023-01-012023-12-310000092122so:OtherNaturalGasMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:OtherNaturalGasMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:OtherNaturalGasMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:OtherNaturalGasMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:OtherNaturalGasMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:OtherRevenuesMember2023-01-012023-12-310000092122so:OtherRevenuesMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:OtherRevenuesMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:OtherRevenuesMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:OtherRevenuesMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:OtherRevenuesMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:OtherRevenueSourcesMember2023-01-012023-12-310000092122so:OtherRevenueSourcesMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:OtherRevenueSourcesMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:OtherRevenueSourcesMemberso:MississippiPowerMember2023-01-012023-12-310000092122so:OtherRevenueSourcesMemberso:SouthernPowerMember2023-01-012023-12-310000092122so:OtherRevenueSourcesMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:EnergyEfficiencyEnhancementAndUpgradeMemberso:SouthernCompanyGasMember2025-12-310000092122so:UnregulatedDistributedGenerationMember2025-12-310000092122so:UnregulatedDistributedGenerationMember2024-12-3100000921222026-01-012025-12-3100000921222027-01-012025-12-3100000921222028-01-012025-12-3100000921222029-01-012025-12-3100000921222030-01-012025-12-3100000921222031-01-012025-12-310000092122so:AlabamaPowerMember2026-01-012025-12-310000092122so:AlabamaPowerMember2027-01-012025-12-310000092122so:AlabamaPowerMember2028-01-012025-12-310000092122so:AlabamaPowerMember2029-01-012025-12-310000092122so:AlabamaPowerMember2030-01-012025-12-310000092122so:AlabamaPowerMember2031-01-012025-12-310000092122so:GeorgiaPowerMember2026-01-012025-12-310000092122so:GeorgiaPowerMember2027-01-012025-12-310000092122so:GeorgiaPowerMember2028-01-012025-12-310000092122so:GeorgiaPowerMember2029-01-012025-12-310000092122so:GeorgiaPowerMember2030-01-012025-12-310000092122so:GeorgiaPowerMember2031-01-012025-12-310000092122so:MississippiPowerMember2026-01-012025-12-310000092122so:MississippiPowerMember2027-01-012025-12-310000092122so:MississippiPowerMember2028-01-012025-12-310000092122so:MississippiPowerMember2029-01-012025-12-310000092122so:MississippiPowerMember2030-01-012025-12-310000092122so:MississippiPowerMember2031-01-012025-12-310000092122so:SouthernPowerMember2026-01-012025-12-310000092122so:SouthernPowerMember2027-01-012025-12-310000092122so:SouthernPowerMember2028-01-012025-12-310000092122so:SouthernPowerMember2029-01-012025-12-310000092122so:SouthernPowerMember2030-01-012025-12-310000092122so:SouthernPowerMember2031-01-012025-12-310000092122so:SouthernCompanyGasMember2026-01-012025-12-310000092122so:SouthernCompanyGasMember2027-01-012025-12-310000092122so:SouthernCompanyGasMember2028-01-012025-12-310000092122so:SouthernCompanyGasMember2029-01-012025-12-310000092122so:SouthernCompanyGasMember2030-01-012025-12-310000092122so:SouthernCompanyGasMember2031-01-012025-12-310000092122so:PlantVogtleNuclearUnitsOneTwoAndThreeMemberso:GeorgiaPowerMemberso:NuclearOutageMember2025-12-310000092122so:DeferredCloudImplementationCostsMember2025-12-310000092122so:AlabamaPowerMemberso:DeferredCloudImplementationCostsMember2025-12-310000092122so:GeorgiaPowerMemberso:DeferredCloudImplementationCostsMember2025-12-310000092122so:MississippiPowerMemberso:DeferredCloudImplementationCostsMember2025-12-310000092122so:SouthernPowerMemberso:DeferredCloudImplementationCostsMember2025-12-310000092122so:SouthernCompanyGasMemberso:DeferredCloudImplementationCostsMember2025-12-310000092122so:DeferredCloudImplementationCostsMember2024-12-310000092122so:AlabamaPowerMemberso:DeferredCloudImplementationCostsMember2024-12-310000092122so:GeorgiaPowerMemberso:DeferredCloudImplementationCostsMember2024-12-310000092122so:MississippiPowerMemberso:DeferredCloudImplementationCostsMember2024-12-310000092122so:SouthernPowerMemberso:DeferredCloudImplementationCostsMember2024-12-310000092122so:SouthernCompanyGasMemberso:DeferredCloudImplementationCostsMember2024-12-310000092122so:SouthernCompanyGasMemberso:DeferredCloudImplementationCostsMember2023-01-012023-12-310000092122so:SouthernCompanyGasMemberso:DeferredCloudImplementationCostsMember2024-01-012024-12-310000092122so:SouthernCompanyGasMemberso:DeferredCloudImplementationCostsMember2025-01-012025-12-310000092122so:MississippiPowerMemberso:DeferredCloudImplementationCostsMember2023-01-012023-12-310000092122so:SouthernPowerMemberso:DeferredCloudImplementationCostsMember2023-01-012023-12-310000092122so:MississippiPowerMemberso:DeferredCloudImplementationCostsMember2025-01-012025-12-310000092122so:SouthernPowerMemberso:DeferredCloudImplementationCostsMember2024-01-012024-12-310000092122so:SouthernPowerMemberso:DeferredCloudImplementationCostsMember2025-01-012025-12-310000092122so:MississippiPowerMemberso:DeferredCloudImplementationCostsMember2024-01-012024-12-310000092122so:DeferredCloudImplementationCostsMember2025-01-012025-12-310000092122so:AlabamaPowerMemberso:DeferredCloudImplementationCostsMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberso:DeferredCloudImplementationCostsMember2025-01-012025-12-310000092122so:DeferredCloudImplementationCostsMember2024-01-012024-12-310000092122so:AlabamaPowerMemberso:DeferredCloudImplementationCostsMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberso:DeferredCloudImplementationCostsMember2024-01-012024-12-310000092122so:DeferredCloudImplementationCostsMember2023-01-012023-12-310000092122so:AlabamaPowerMemberso:DeferredCloudImplementationCostsMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberso:DeferredCloudImplementationCostsMember2023-01-012023-12-310000092122so:AlabamaPowerMemberso:UtilityPlantInServiceMember2025-01-012025-12-310000092122so:AlabamaPowerMemberso:UtilityPlantInServiceMember2024-01-012024-12-310000092122so:AlabamaPowerMemberso:UtilityPlantInServiceMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberso:UtilityPlantInServiceMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberso:UtilityPlantInServiceMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberso:UtilityPlantInServiceMember2023-01-012023-12-310000092122so:MississippiPowerMemberso:UtilityPlantInServiceMember2025-01-012025-12-310000092122so:MississippiPowerMemberso:UtilityPlantInServiceMember2024-01-012024-12-310000092122so:MississippiPowerMemberso:UtilityPlantInServiceMember2023-01-012023-12-310000092122so:SouthernCompanyGasMemberso:UtilityPlantInServiceMember2025-01-012025-12-310000092122so:SouthernCompanyGasMemberso:UtilityPlantInServiceMember2024-01-012024-12-310000092122so:SouthernCompanyGasMemberso:UtilityPlantInServiceMember2023-01-012023-12-310000092122so:MississippiPowerMember2025-04-012025-04-010000092122so:UtilityPlantInServiceMember2025-12-310000092122so:UtilityPlantInServiceMember2024-12-310000092122so:SouthernCompanyGasMemberso:UtilityPlantInServiceMember2025-12-310000092122so:SouthernCompanyGasMemberso:UtilityPlantInServiceMember2024-12-310000092122us-gaap:OtherPlantInServiceMember2025-12-310000092122us-gaap:OtherPlantInServiceMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:OtherPlantInServiceMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:OtherPlantInServiceMember2024-12-310000092122srt:MinimumMemberso:SouthernCompanyGasMemberus-gaap:TransportationEquipmentMember2025-01-012025-12-310000092122srt:MaximumMemberso:SouthernCompanyGasMemberus-gaap:TransportationEquipmentMember2025-01-012025-12-310000092122srt:MinimumMemberso:SouthernCompanyGasMemberso:StorageFacilitiesMember2025-01-012025-12-310000092122srt:MaximumMemberso:SouthernCompanyGasMemberso:StorageFacilitiesMember2025-01-012025-12-310000092122srt:MaximumMemberso:SouthernCompanyGasMemberus-gaap:OtherAssetsMember2025-01-012025-12-310000092122srt:MaximumMemberus-gaap:OtherPlantInServiceMember2025-01-012025-12-310000092122srt:MaximumMemberso:SouthernPowerMemberso:NaturalGasGeneratingFacilityMember2025-12-310000092122srt:MaximumMemberso:SouthernPowerMemberso:SolarGeneratingFacilityMember2025-12-310000092122srt:MaximumMemberso:SouthernPowerMemberso:WindGeneratingFacilityMember2025-12-310000092122so:KayWindFacilityMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:KayWindFacilityMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:AlabamaPowerMemberso:GreeneCountyMember2025-12-310000092122so:AlabamaPowerMemberso:PlantMillerCoalUnitsOneAndTwoMember2025-12-310000092122so:GeorgiaPowerMemberso:PlantHatchUnits1And2Member2025-12-310000092122so:GeorgiaPowerMemberso:PlantHatchNuclearMember2025-12-310000092122so:GeorgiaPowerMemberso:PlantVogtleNuclearUnitsOneAndTwoMember2025-12-310000092122so:GeorgiaPowerMemberso:PlantVogtleNuclearUnitsThreeAndFourMember2025-12-310000092122so:GeorgiaPowerMemberso:PlantSchererCoalUnitsOneAndTwoMember2025-12-310000092122so:GeorgiaPowerMemberso:PlantSchererUnitThreeMember2025-12-310000092122so:GeorgiaPowerMemberso:RockyMountainPumpedStorageMember2025-12-310000092122so:MississippiPowerMemberso:GreeneCountyMember2025-12-310000092122so:SouthernCompanyGasMemberso:DaltonPipelineNaturalGasPipelineMember2025-12-310000092122so:SouthernCompanyGasMemberso:DaltonPipelineNaturalGasPipelineMember2025-01-012025-12-310000092122so:ChevronProductsCompanyMemberso:MississippiPowerMember2025-12-310000092122so:PlantVogtleUnit4Member2024-02-140000092122so:GeorgiaPowerMember2024-09-012024-09-300000092122so:GeorgiaPowerMember2024-11-012024-11-300000092122so:AlabamaPowerMember2025-06-012025-06-300000092122so:MississippiPowerMember2025-06-012025-06-300000092122so:GeorgiaPowerMember2025-11-012025-11-300000092122us-gaap:EquitySecuritiesMember2025-12-310000092122us-gaap:EquitySecuritiesMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:EquitySecuritiesMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:DebtSecuritiesMember2025-12-310000092122us-gaap:DebtSecuritiesMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:DebtSecuritiesMemberso:GeorgiaPowerMember2025-12-310000092122so:OtherSecuritiesMember2025-12-310000092122so:OtherSecuritiesMemberso:AlabamaPowerMember2025-12-310000092122so:OtherSecuritiesMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:EquitySecuritiesMember2024-12-310000092122us-gaap:EquitySecuritiesMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:EquitySecuritiesMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:DebtSecuritiesMember2024-12-310000092122us-gaap:DebtSecuritiesMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:DebtSecuritiesMemberso:GeorgiaPowerMember2024-12-310000092122so:OtherSecuritiesMember2024-12-310000092122so:OtherSecuritiesMemberso:AlabamaPowerMember2024-12-310000092122so:OtherSecuritiesMemberso:GeorgiaPowerMember2024-12-310000092122so:FairValueIncreasesDecreasesMemberso:SecuritiesHeldInFundsMember2025-01-012025-12-310000092122so:FairValueIncreasesDecreasesMemberso:SecuritiesHeldInFundsMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:FairValueIncreasesDecreasesMemberso:SecuritiesHeldInFundsMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:FairValueIncreasesDecreasesMemberso:SecuritiesHeldInFundsMember2024-01-012024-12-310000092122so:FairValueIncreasesDecreasesMemberso:SecuritiesHeldInFundsMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:FairValueIncreasesDecreasesMemberso:SecuritiesHeldInFundsMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:FairValueIncreasesDecreasesMemberso:SecuritiesHeldInFundsMember2023-01-012023-12-310000092122so:FairValueIncreasesDecreasesMemberso:SecuritiesHeldInFundsMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:FairValueIncreasesDecreasesMemberso:SecuritiesHeldInFundsMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:UnrealizedGainLossOrWriteDownMemberso:SecuritiesHeldInFundsMember2025-01-012025-12-310000092122so:UnrealizedGainLossOrWriteDownMemberso:SecuritiesHeldInFundsMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:UnrealizedGainLossOrWriteDownMemberso:SecuritiesHeldInFundsMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:UnrealizedGainLossOrWriteDownMemberso:SecuritiesHeldInFundsMember2024-01-012024-12-310000092122so:UnrealizedGainLossOrWriteDownMemberso:SecuritiesHeldInFundsMemberso:AlabamaPowerMember2024-01-012024-12-310000092122so:UnrealizedGainLossOrWriteDownMemberso:SecuritiesHeldInFundsMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122so:UnrealizedGainLossOrWriteDownMemberso:SecuritiesHeldInFundsMember2023-01-012023-12-310000092122so:UnrealizedGainLossOrWriteDownMemberso:SecuritiesHeldInFundsMemberso:AlabamaPowerMember2023-01-012023-12-310000092122so:UnrealizedGainLossOrWriteDownMemberso:SecuritiesHeldInFundsMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122so:AccumulatedProvisionsForDecommissioningInternalReservesMemberso:AlabamaPowerMember2025-12-310000092122so:AccumulatedProvisionsForDecommissioningInternalReservesMemberso:AlabamaPowerMember2024-12-310000092122so:PlantFarleyMemberso:AccumulatedProvisionsForDecommissioningExternalTrustFundsMemberso:AlabamaPowerMember2025-12-310000092122so:PlantFarleyMemberso:AccumulatedProvisionsForDecommissioningExternalTrustFundsMemberso:AlabamaPowerMember2024-12-310000092122so:PlantHatchMemberso:AccumulatedProvisionsForDecommissioningExternalTrustFundsMemberso:GeorgiaPowerMember2025-12-310000092122so:PlantHatchMemberso:AccumulatedProvisionsForDecommissioningExternalTrustFundsMemberso:GeorgiaPowerMember2024-12-310000092122so:PlantVogtleNuclearUnitsOneAndTwoMemberso:AccumulatedProvisionsForDecommissioningExternalTrustFundsMemberso:GeorgiaPowerMember2025-12-310000092122so:PlantVogtleNuclearUnitsOneAndTwoMemberso:AccumulatedProvisionsForDecommissioningExternalTrustFundsMemberso:GeorgiaPowerMember2024-12-310000092122so:PlantVogtleUnit3Memberso:AccumulatedProvisionsForDecommissioningExternalTrustFundsMemberso:GeorgiaPowerMember2025-12-310000092122so:PlantVogtleUnit3Memberso:AccumulatedProvisionsForDecommissioningExternalTrustFundsMemberso:GeorgiaPowerMember2024-12-310000092122so:AccumulatedProvisionsForDecommissioningExternalTrustFundsMemberso:GeorgiaPowerMember2025-12-310000092122so:AccumulatedProvisionsForDecommissioningExternalTrustFundsMemberso:GeorgiaPowerMember2024-12-310000092122so:AlabamaPowerMemberso:PlantFarleyMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberso:PlantHatchMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberso:PlantVogtleNuclearUnitsOneAndTwoMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberso:PlantVogtleUnit3Member2025-01-012025-12-310000092122so:PlantFarleyMemberso:SiteStudyCostRadiatedStructuresMemberso:AlabamaPowerMember2025-12-310000092122so:PlantHatchMemberso:SiteStudyCostRadiatedStructuresMemberso:GeorgiaPowerMember2025-12-310000092122so:PlantVogtleNuclearUnitsOneAndTwoMemberso:SiteStudyCostRadiatedStructuresMemberso:GeorgiaPowerMember2025-12-310000092122so:PlantVogtleUnit3Memberso:SiteStudyCostRadiatedStructuresMemberso:GeorgiaPowerMember2025-12-310000092122so:PlantFarleyMemberso:SpentFuelManagementMemberso:AlabamaPowerMember2025-12-310000092122so:PlantHatchMemberso:SpentFuelManagementMemberso:GeorgiaPowerMember2025-12-310000092122so:PlantVogtleNuclearUnitsOneAndTwoMemberso:SpentFuelManagementMemberso:GeorgiaPowerMember2025-12-310000092122so:PlantVogtleUnit3Memberso:SpentFuelManagementMemberso:GeorgiaPowerMember2025-12-310000092122so:PlantFarleyMemberso:SiteStudyCostNonRadiatedStructuresMemberso:AlabamaPowerMember2025-12-310000092122so:PlantHatchMemberso:SiteStudyCostNonRadiatedStructuresMemberso:GeorgiaPowerMember2025-12-310000092122so:PlantVogtleNuclearUnitsOneAndTwoMemberso:SiteStudyCostNonRadiatedStructuresMemberso:GeorgiaPowerMember2025-12-310000092122so:PlantVogtleUnit3Memberso:SiteStudyCostNonRadiatedStructuresMemberso:GeorgiaPowerMember2025-12-310000092122so:AlabamaPowerMemberso:PlantFarleyMember2025-12-310000092122so:GeorgiaPowerMemberso:PlantHatchMember2025-12-310000092122so:GeorgiaPowerMemberso:PlantVogtleUnit3Member2025-12-310000092122so:PlantFarleyMemberso:AlabamaPowerMember2025-01-012025-12-310000092122so:PlantHatchMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberso:PlantHatchandPlantVogtleUnits1And2Member2023-01-012023-01-010000092122so:GeorgiaPowerMemberso:PlantVogtleUnit3Member2023-08-012023-08-010000092122so:GeorgiaPowerMemberso:PlantVogtleUnit4Member2024-05-012024-05-010000092122so:SouthernHoldingsCompanyMember2025-12-310000092122so:SouthernHoldingsCompanyMember2024-12-310000092122so:SouthernHoldingsCompanyMember2025-01-012025-12-310000092122so:SouthernHoldingsCompanyMember2024-01-012024-12-310000092122so:SouthernHoldingsCompanyMember2023-01-012023-12-310000092122so:AlabamaPowerMemberso:SouthernElectricGeneratingCompanyMember2025-01-012025-12-310000092122so:AlabamaPowerMemberso:SouthernElectricGeneratingCompanyMember2024-01-012024-12-310000092122so:AlabamaPowerMemberso:SouthernElectricGeneratingCompanyMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberso:SouthernElectricGeneratingCompanyMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberso:SouthernElectricGeneratingCompanyMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberso:SouthernElectricGeneratingCompanyMember2023-01-012023-12-310000092122so:AlabamaPowerMemberso:SouthernElectricGeneratingCompanyMember2025-12-310000092122so:SPSolarHoldingsILPMemberso:WhollyOwnedSubsidiaryOfSouthernPowerMemberus-gaap:GeneralPartnerMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:SPSolarHoldingsILPMemberso:WhollyOwnedSubsidiaryOfSouthernPowerMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:SPSolarHoldingsILPMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:SPSolarHoldingsILPMemberus-gaap:VariableInterestEntityPrimaryBeneficiaryMemberso:SouthernPowerMember2025-12-310000092122so:SPSolarHoldingsILPMemberus-gaap:VariableInterestEntityPrimaryBeneficiaryMemberso:SouthernPowerMember2024-12-310000092122so:SPSolarHoldingsILPMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:SPSolarHoldingsILPMemberso:GlobalAtlanticMember2025-01-012025-12-310000092122so:SPWindMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:SPWindMemberso:ClassBMembershipInterestsMemberso:SouthernPowerMember2025-12-310000092122so:SPWindMemberso:ClassAMembershipInterestsMemberso:SouthernPowerMember2025-12-310000092122so:SPWindMemberso:SouthernPowerMember2025-12-310000092122so:SPWindMemberso:SouthernPowerMember2025-12-312025-12-310000092122so:SPWindMemberus-gaap:VariableInterestEntityPrimaryBeneficiaryMemberso:SouthernPowerMember2024-12-310000092122so:OtherVariableInterestEntitiesMemberus-gaap:VariableInterestEntityPrimaryBeneficiaryMemberso:SouthernPowerMember2024-12-310000092122so:OtherVariableInterestEntitiesMemberus-gaap:VariableInterestEntityPrimaryBeneficiaryMemberso:SouthernPowerMember2025-12-310000092122so:SNGMemberso:SouthernCompanyGasMember2025-12-310000092122so:SNGMemberso:SouthernCompanyGasMember2024-12-310000092122so:OtherMemberso:SouthernCompanyGasMember2025-12-310000092122so:OtherMemberso:SouthernCompanyGasMember2024-12-310000092122so:SNGMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:SNGMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:SNGMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:OtherMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:OtherMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122us-gaap:SeniorNotesMember2025-12-310000092122us-gaap:SeniorNotesMember2024-12-310000092122us-gaap:JuniorSubordinatedDebtMember2025-12-310000092122us-gaap:JuniorSubordinatedDebtMember2024-12-310000092122so:FederalFinancingBankLoansMember2025-12-310000092122so:FederalFinancingBankLoansMember2024-12-310000092122so:PollutionControlRevenueBondsMember2025-12-310000092122so:PollutionControlRevenueBondsMember2024-12-310000092122so:FirstMortgageBondsMember2025-12-310000092122so:FirstMortgageBondsMember2024-12-310000092122us-gaap:MediumTermNotesMember2025-12-310000092122us-gaap:MediumTermNotesMember2024-12-310000092122so:OtherLongTermDebtMember2025-12-310000092122so:OtherLongTermDebtMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:SeniorNotesMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:SeniorNotesMember2024-12-310000092122so:AlabamaPowerMemberso:PollutionControlRevenueBondsMember2025-12-310000092122so:AlabamaPowerMemberso:PollutionControlRevenueBondsMember2024-12-310000092122so:AlabamaPowerMemberso:OtherLongTermDebtMember2025-12-310000092122so:AlabamaPowerMemberso:OtherLongTermDebtMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:SeniorNotesMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:SeniorNotesMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:JuniorSubordinatedDebtMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:JuniorSubordinatedDebtMember2024-12-310000092122so:GeorgiaPowerMemberso:FederalFinancingBankLoansMember2025-12-310000092122so:GeorgiaPowerMemberso:FederalFinancingBankLoansMember2024-12-310000092122so:GeorgiaPowerMemberso:PollutionControlRevenueBondsMember2025-12-310000092122so:GeorgiaPowerMemberso:PollutionControlRevenueBondsMember2024-12-310000092122so:GeorgiaPowerMemberso:OtherLongTermDebtMember2025-12-310000092122so:GeorgiaPowerMemberso:OtherLongTermDebtMember2024-12-310000092122so:MississippiPowerMemberus-gaap:SeniorNotesMember2025-12-310000092122so:MississippiPowerMemberus-gaap:SeniorNotesMember2024-12-310000092122so:MississippiPowerMemberso:PollutionControlRevenueBondsMember2025-12-310000092122so:MississippiPowerMemberso:PollutionControlRevenueBondsMember2024-12-310000092122so:SouthernPowerMemberus-gaap:SeniorNotesMember2025-12-310000092122so:SouthernPowerMemberus-gaap:SeniorNotesMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:SeniorNotesMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:SeniorNotesMember2024-12-310000092122so:SouthernCompanyGasMemberso:FirstMortgageBondsMember2025-12-310000092122so:SouthernCompanyGasMemberso:FirstMortgageBondsMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:MediumTermNotesMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:MediumTermNotesMember2024-12-310000092122so:SouthernCompanyGasMemberso:OtherLongTermDebtMember2025-12-310000092122so:SouthernCompanyGasMemberso:OtherLongTermDebtMember2024-12-310000092122so:Series2023AConvertibleSeniorNotesDue2025Memberso:AlabamaPowerMember2025-12-310000092122so:Series2025BFloatingRateSeniorNotesDue2075Memberso:AlabamaPowerMember2025-12-310000092122so:Series2023CConvertibleSeniorNotesDue2074Memberso:GeorgiaPowerMember2025-12-310000092122so:SouthernPowerMemberso:EuroDenominatedDebtMember2025-12-310000092122so:FFBCreditFacilityMemberso:GeorgiaPowerMember2019-01-012019-12-310000092122so:FFBCreditFacilityMemberso:GeorgiaPowerMember2022-12-310000092122so:FFBCreditFacilityMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122so:FFBCreditFacilityMemberso:GeorgiaPowerMember2025-12-310000092122so:FFBCreditFacilityMemberso:GeorgiaPowerMember2024-12-310000092122so:Series2019ARemarketableJuniorSubordinatedNotesMemberus-gaap:JuniorSubordinatedDebtMember2022-05-310000092122so:Series2019BRemarketableJuniorSubordinatedNotesMemberus-gaap:JuniorSubordinatedDebtMember2022-05-310000092122so:A2019SeriesAEquityUnitsMemberus-gaap:JuniorSubordinatedDebtMember2022-08-012022-08-310000092122so:A2019SeriesAEquityUnitsMemberus-gaap:JuniorSubordinatedDebtMember2022-08-012022-08-010000092122so:SeriesAEquityUnits2025Memberus-gaap:JuniorSubordinatedDebtMember2025-11-300000092122so:SeriesAEquityUnits2025Memberus-gaap:JuniorSubordinatedDebtMember2025-11-012025-11-300000092122so:Series2023AConvertibleSeniorNotesDue2025Memberus-gaap:ConvertibleDebtMember2025-11-300000092122so:Series2023AConvertibleSeniorNotesDue2025Memberus-gaap:ConvertibleDebtMember2023-02-280000092122so:Series2024AConvertibleSeniorNotesMemberus-gaap:ConvertibleDebtMember2025-11-300000092122so:Series2024AConvertibleSeniorNotesMemberus-gaap:ConvertibleDebtMember2024-05-310000092122so:AntiDilutionScenarioOneMemberso:Series2019AAndSeries2019BRemarketableJuniorSubordinatedNotesMembersrt:MinimumMemberus-gaap:JuniorSubordinatedDebtMember2025-11-300000092122so:AntiDilutionScenarioOneMemberso:Series2019AAndSeries2019BRemarketableJuniorSubordinatedNotesMemberus-gaap:JuniorSubordinatedDebtMember2025-11-300000092122so:AntiDilutionScenarioTwoMemberso:Series2019AAndSeries2019BRemarketableJuniorSubordinatedNotesMembersrt:MinimumMemberus-gaap:JuniorSubordinatedDebtMember2025-11-300000092122so:AntiDilutionScenarioThreeMemberso:Series2019AAndSeries2019BRemarketableJuniorSubordinatedNotesMemberus-gaap:JuniorSubordinatedDebtMember2025-11-300000092122so:Series2025RemarketableJuniorSubordinatedNotesMemberus-gaap:JuniorSubordinatedDebtMember2025-12-310000092122so:Series2025RemarketableJuniorSubordinatedNotesMemberus-gaap:JuniorSubordinatedDebtMember2025-01-012025-12-310000092122so:Series2023AConvertibleSeniorNotesDue2025Memberus-gaap:ConvertibleDebtMember2023-03-310000092122so:Series2025AConvertibleSeniorNotesMemberus-gaap:ConvertibleDebtMember2025-05-310000092122so:Series2023AConvertibleSeniorNotesMemberus-gaap:ConvertibleDebtMember2025-05-310000092122so:Series2024AConvertibleSeniorNotesMemberus-gaap:ConvertibleDebtMember2025-05-310000092122so:Series2023AConvertibleSeniorNotesDue2025Memberus-gaap:ConvertibleDebtMember2025-11-012025-11-300000092122so:Series2023AConvertibleSeniorNotesDue2025Memberus-gaap:ConvertibleDebtMember2025-12-152025-12-150000092122so:DebtConversionTermsOneMemberso:Series2024AConvertibleSeniorNotesMemberus-gaap:ConvertibleDebtMember2025-01-012025-12-310000092122so:DebtConversionTermsOneMemberso:Series2025AConvertibleSeniorNotesMemberus-gaap:ConvertibleDebtMember2025-01-012025-12-310000092122so:DebtConversionTermsTwoMemberso:Series2025AConvertibleSeniorNotesMemberus-gaap:ConvertibleDebtMember2025-01-012025-12-310000092122so:DebtConversionTermsTwoMemberso:Series2024AConvertibleSeniorNotesMemberus-gaap:ConvertibleDebtMember2025-01-012025-12-310000092122so:Series2024AConvertibleSeniorNotesMemberus-gaap:ConvertibleDebtMember2025-12-310000092122so:Series2025AConvertibleSeniorNotesMemberus-gaap:ConvertibleDebtMember2025-12-310000092122so:Series2025AConvertibleSeniorNotesMemberus-gaap:ConvertibleDebtMember2025-01-012025-12-310000092122so:Series2024AConvertibleSeniorNotesMemberus-gaap:ConvertibleDebtMember2025-01-012025-12-310000092122so:Series2025BRemarketableSeniorNotesDue2030Memberus-gaap:JuniorSubordinatedDebtMember2023-12-310000092122so:Series2025CRemarketableSeniorNotesDue2033Memberus-gaap:JuniorSubordinatedDebtMember2023-12-310000092122so:AtTheMarketMember2024-05-012024-05-310000092122so:ForwardSaleContract12024Member2024-01-012024-12-310000092122so:ForwardSaleContract12024Member2025-12-032025-12-030000092122so:ForwardSaleContract22024Member2024-01-012024-12-310000092122so:ForwardSaleContract22024Member2025-12-032025-12-030000092122so:ForwardSaleContract32024Member2024-01-012024-12-310000092122so:ForwardSaleContract32024Member2025-12-032025-12-030000092122so:ForwardSaleContract1Member2025-01-012025-01-310000092122so:ForwardSaleContract1Member2025-01-012025-12-310000092122so:ForwardSaleContract1Member2025-12-032025-12-030000092122so:ForwardSaleContract2Member2025-01-012025-12-310000092122so:ForwardSaleContract2Member2025-12-032025-12-030000092122so:ForwardSaleContract3Member2025-01-012025-12-310000092122so:ForwardSaleContract3Member2025-12-032025-12-030000092122so:ForwardSaleContract4Member2025-01-012025-12-310000092122so:ForwardSaleContract4Member2025-12-032025-12-030000092122so:ForwardSaleContract5Member2025-01-012025-12-310000092122so:ForwardSaleContract5Member2025-12-032025-12-030000092122so:ForwardSaleContract6Member2025-01-012025-12-310000092122so:ForwardSaleContract6Member2025-12-032025-12-030000092122so:ForwardSaleContract7Member2025-01-012025-12-310000092122so:ForwardSaleContract7Member2025-12-032025-12-030000092122so:ForwardSaleContract8Member2025-01-012025-12-310000092122so:ForwardSaleContract8Member2025-12-032025-12-030000092122so:ForwardSaleContract9Member2025-01-012025-12-310000092122so:ForwardSaleContract9Member2025-12-032025-12-030000092122so:ForwardSaleContract10Member2025-01-012025-12-310000092122so:ForwardSaleContract10Member2025-12-032025-12-030000092122so:ForwardSaleContract11Member2025-01-012025-12-310000092122so:ForwardSaleContract11Member2025-12-032025-12-030000092122so:ForwardSaleContract12Member2025-01-012025-12-310000092122so:ForwardSaleContract12Member2025-12-032025-12-030000092122so:ForwardSaleContract13Member2025-01-012025-12-310000092122so:ForwardSaleContract13Member2025-12-032025-12-030000092122so:ForwardSaleContract14Member2025-01-012025-12-310000092122so:ForwardSaleContract15Member2025-01-012025-12-310000092122so:ForwardSaleContract16Member2025-01-012025-12-310000092122so:ForwardSaleContract17Member2025-01-012025-12-310000092122so:ForwardSaleContract18Member2025-01-012025-12-310000092122so:ForwardSaleContract19Member2025-01-012025-12-310000092122so:ForwardSaleContract20Member2025-01-012025-12-310000092122so:ForwardSaleContract21Member2025-01-012025-12-310000092122so:ForwardSaleContract22Member2025-01-012025-12-310000092122so:ForwardSaleContract23Member2025-01-012025-12-310000092122us-gaap:PrivatePlacementMember2024-11-012025-12-3100000921222025-12-312025-12-310000092122so:OtherSubsidiariesMember2025-12-310000092122so:SouthernCompanyAndSouthernPowerMember2025-12-310000092122so:AlabamaPropertyCompanyMember2025-12-310000092122so:UncommitedLetterOfCreditFacilityMemberso:GeorgiaPowerMember2025-12-310000092122so:ContinuingLetterOfCreditFacilityAMemberso:SouthernPowerMember2025-12-310000092122so:ContinuingLetterOfCreditFacilityBMemberso:SouthernPowerMember2025-12-310000092122so:UncommitedLetterOfCreditFacilityMemberso:SouthernPowerMember2025-12-310000092122so:SouthernCompanyGasCapitalMember2025-12-310000092122so:PowerPurchaseAgreementMemberso:SouthernPowerMember2025-12-310000092122so:PowerPurchaseAgreementMemberso:SouthernPowerMember2024-12-310000092122us-gaap:CommercialPaperMember2025-12-310000092122us-gaap:CommercialPaperMember2024-12-310000092122so:ShortTermBankDebtMember2025-12-310000092122so:ShortTermBankDebtMember2024-12-310000092122us-gaap:CommercialPaperMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:CommercialPaperMemberso:GeorgiaPowerMember2024-12-310000092122so:ShortTermBankDebtMemberso:GeorgiaPowerMember2025-12-310000092122so:ShortTermBankDebtMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:CommercialPaperMemberso:MississippiPowerMember2025-12-310000092122us-gaap:CommercialPaperMemberso:MississippiPowerMember2024-12-310000092122us-gaap:CommercialPaperMemberso:SouthernPowerMember2025-12-310000092122us-gaap:CommercialPaperMemberso:SouthernPowerMember2024-12-310000092122us-gaap:CommercialPaperMemberso:SouthernCompanyGasCapitalMember2025-12-310000092122us-gaap:CommercialPaperMemberso:SouthernCompanyGasCapitalMember2024-12-310000092122us-gaap:CommercialPaperMemberso:NicorGasMember2025-12-310000092122us-gaap:CommercialPaperMemberso:NicorGasMember2024-12-310000092122us-gaap:CommercialPaperMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:CommercialPaperMemberso:SouthernCompanyGasMember2024-12-310000092122so:SouthernCompanyCommonStockMember2025-12-310000092122so:ElectricGeneratingUnitsMember2025-12-310000092122so:AlabamaPowerMemberso:ElectricGeneratingUnitsMember2025-12-310000092122so:GeorgiaPowerMemberso:ElectricGeneratingUnitsMember2025-12-310000092122so:MississippiPowerMemberso:ElectricGeneratingUnitsMember2025-12-310000092122so:SouthernPowerMemberso:ElectricGeneratingUnitsMember2025-12-310000092122so:SouthernCompanyGasMemberso:ElectricGeneratingUnitsMember2025-12-310000092122us-gaap:LandAndBuildingMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:LandAndBuildingMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:LandAndBuildingMember2025-12-310000092122so:MississippiPowerMemberus-gaap:LandAndBuildingMember2025-12-310000092122so:SouthernPowerMemberus-gaap:LandAndBuildingMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:LandAndBuildingMember2025-12-310000092122so:CommunicationTowersMember2025-12-310000092122so:AlabamaPowerMemberso:CommunicationTowersMember2025-12-310000092122so:GeorgiaPowerMemberso:CommunicationTowersMember2025-12-310000092122so:MississippiPowerMemberso:CommunicationTowersMember2025-12-310000092122so:SouthernPowerMemberso:CommunicationTowersMember2025-12-310000092122so:SouthernCompanyGasMemberso:CommunicationTowersMember2025-12-310000092122so:RailcarsMember2025-12-310000092122so:AlabamaPowerMemberso:RailcarsMember2025-12-310000092122so:GeorgiaPowerMemberso:RailcarsMember2025-12-310000092122so:MississippiPowerMemberso:RailcarsMember2025-12-310000092122so:SouthernPowerMemberso:RailcarsMember2025-12-310000092122so:SouthernCompanyGasMemberso:RailcarsMember2025-12-310000092122us-gaap:PropertyPlantAndEquipmentOtherTypesMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:PropertyPlantAndEquipmentOtherTypesMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:PropertyPlantAndEquipmentOtherTypesMember2025-12-310000092122so:MississippiPowerMemberus-gaap:PropertyPlantAndEquipmentOtherTypesMember2025-12-310000092122so:SouthernPowerMemberus-gaap:PropertyPlantAndEquipmentOtherTypesMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:PropertyPlantAndEquipmentOtherTypesMember2025-12-310000092122so:ElectricGeneratingUnitsMember2024-12-310000092122so:AlabamaPowerMemberso:ElectricGeneratingUnitsMember2024-12-310000092122so:GeorgiaPowerMemberso:ElectricGeneratingUnitsMember2024-12-310000092122so:MississippiPowerMemberso:ElectricGeneratingUnitsMember2024-12-310000092122so:SouthernPowerMemberso:ElectricGeneratingUnitsMember2024-12-310000092122so:SouthernCompanyGasMemberso:ElectricGeneratingUnitsMember2024-12-310000092122us-gaap:LandAndBuildingMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:LandAndBuildingMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:LandAndBuildingMember2024-12-310000092122so:MississippiPowerMemberus-gaap:LandAndBuildingMember2024-12-310000092122so:SouthernPowerMemberus-gaap:LandAndBuildingMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:LandAndBuildingMember2024-12-310000092122so:CommunicationTowersMember2024-12-310000092122so:AlabamaPowerMemberso:CommunicationTowersMember2024-12-310000092122so:GeorgiaPowerMemberso:CommunicationTowersMember2024-12-310000092122so:MississippiPowerMemberso:CommunicationTowersMember2024-12-310000092122so:SouthernPowerMemberso:CommunicationTowersMember2024-12-310000092122so:SouthernCompanyGasMemberso:CommunicationTowersMember2024-12-310000092122so:RailcarsMember2024-12-310000092122so:AlabamaPowerMemberso:RailcarsMember2024-12-310000092122so:GeorgiaPowerMemberso:RailcarsMember2024-12-310000092122so:MississippiPowerMemberso:RailcarsMember2024-12-310000092122so:SouthernPowerMemberso:RailcarsMember2024-12-310000092122so:SouthernCompanyGasMemberso:RailcarsMember2024-12-310000092122us-gaap:PropertyPlantAndEquipmentOtherTypesMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:PropertyPlantAndEquipmentOtherTypesMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:PropertyPlantAndEquipmentOtherTypesMember2024-12-310000092122so:MississippiPowerMemberus-gaap:PropertyPlantAndEquipmentOtherTypesMember2024-12-310000092122so:SouthernPowerMemberus-gaap:PropertyPlantAndEquipmentOtherTypesMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:PropertyPlantAndEquipmentOtherTypesMember2024-12-310000092122srt:MaximumMemberus-gaap:BuildingMember2025-01-012025-12-310000092122srt:MaximumMemberus-gaap:LandMember2025-01-012025-12-310000092122srt:MaximumMemberso:CommunicationTowersMember2025-01-012025-12-310000092122srt:MinimumMemberso:AlabamaPowerMemberso:ElectricGeneratingUnitsMember2025-12-310000092122srt:MaximumMemberso:AlabamaPowerMemberso:ElectricGeneratingUnitsMember2025-12-310000092122srt:AffiliatedEntityMemberso:GeorgiaPowerMemberso:ElectricGeneratingUnitsMember2025-12-310000092122srt:AffiliatedEntityMemberso:GeorgiaPowerMemberso:ElectricGeneratingUnitsMember2024-12-310000092122so:AssetsSubjectToPowerPurchaseAgreementMember2025-12-310000092122so:AlabamaPowerMemberso:AssetsSubjectToPowerPurchaseAgreementMember2025-12-310000092122so:GeorgiaPowerMemberso:AssetsSubjectToPowerPurchaseAgreementMember2025-12-310000092122so:AssetsSubjectToPowerPurchaseAgreementMember2024-12-310000092122so:AlabamaPowerMemberso:AssetsSubjectToPowerPurchaseAgreementMember2024-12-310000092122so:GeorgiaPowerMemberso:AssetsSubjectToPowerPurchaseAgreementMember2024-12-310000092122so:AssetsSubjectToPowerPurchaseAgreementMember2025-01-012025-12-310000092122so:AlabamaPowerMemberso:AssetsSubjectToPowerPurchaseAgreementMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberso:AssetsSubjectToPowerPurchaseAgreementMember2025-01-012025-12-310000092122so:AssetsSubjectToPowerPurchaseAgreementMember2024-01-012024-12-310000092122so:AlabamaPowerMemberso:AssetsSubjectToPowerPurchaseAgreementMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberso:AssetsSubjectToPowerPurchaseAgreementMember2024-01-012024-12-310000092122so:AssetsSubjectToPowerPurchaseAgreementMember2023-01-012023-12-310000092122so:AlabamaPowerMemberso:AssetsSubjectToPowerPurchaseAgreementMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberso:AssetsSubjectToPowerPurchaseAgreementMember2023-01-012023-12-310000092122so:GeorgiaPowerMember2024-12-312024-12-310000092122srt:MaximumMemberso:TraditionalElectricOperatingCompaniesMemberso:OutdoorLightingMember2025-12-310000092122srt:MaximumMemberso:GeorgiaPowerMemberso:OutdoorLightingMember2025-12-310000092122srt:MaximumMemberso:MississippiPowerMemberso:ElectricGeneratingUnitsMember2025-12-310000092122srt:MaximumMemberso:SouthernPowerMemberso:ElectricGeneratingUnitsMember2025-12-310000092122srt:MaximumMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122srt:MaximumMemberso:FuelCellsMember2025-12-310000092122so:MississippiPowerMemberus-gaap:OtherCurrentAssetsMember2025-12-310000092122so:MississippiPowerMemberus-gaap:OtherCurrentAssetsMember2024-12-310000092122so:MississippiPowerMemberso:OtherPropertyAndInvestmentsMember2025-12-310000092122so:MississippiPowerMemberso:OtherPropertyAndInvestmentsMember2024-12-310000092122so:SouthernPowerMemberus-gaap:OtherCurrentAssetsMember2025-12-310000092122so:SouthernPowerMemberus-gaap:OtherCurrentAssetsMember2024-12-310000092122so:SouthernPowerMemberso:SalesTypeLeaseNetInvestmentInLeaseAfterAllowanceForCreditLossNoncurrentMember2025-12-310000092122so:SouthernPowerMemberso:SalesTypeLeaseNetInvestmentInLeaseAfterAllowanceForCreditLossNoncurrentMember2024-12-310000092122so:TraditionalElectricOperatingCompaniesMember2025-01-012025-12-310000092122us-gaap:StateAndLocalJurisdictionMemberso:GeorgiaPowerMemberso:InvestmentTaxAndOtherCreditCarryforwardMember2025-01-012025-12-310000092122us-gaap:StateAndLocalJurisdictionMemberso:GeorgiaPowerMemberso:InvestmentTaxAndOtherCreditCarryforwardMember2024-01-012024-12-310000092122us-gaap:StateAndLocalJurisdictionMemberso:GeorgiaPowerMemberso:InvestmentTaxAndOtherCreditCarryforwardMember2023-01-012023-12-310000092122so:SouthernPowerMemberso:ProductionTaxCreditCarryforwardMember2025-01-012025-12-310000092122so:SouthernPowerMemberso:ProductionTaxCreditCarryforwardMember2024-01-012024-12-310000092122so:SouthernPowerMemberso:ProductionTaxCreditCarryforwardMember2023-01-012023-12-310000092122stpr:AL2025-01-012025-12-310000092122so:AlabamaPowerMemberstpr:AL2025-01-012025-12-310000092122so:GeorgiaPowerMemberstpr:GA2025-01-012025-12-310000092122so:SouthernPowerMemberstpr:GA2025-01-012025-12-310000092122so:SouthernPowerMemberstpr:OK2025-01-012025-12-310000092122stpr:IL2025-01-012025-12-310000092122so:SouthernCompanyGasMemberstpr:IL2024-01-012024-12-310000092122stpr:AL2024-01-012024-12-310000092122so:AlabamaPowerMemberstpr:AL2024-01-012024-12-310000092122stpr:GA2024-01-012024-12-310000092122so:GeorgiaPowerMemberstpr:GA2024-01-012024-12-310000092122so:SouthernPowerMemberstpr:GA2024-01-012024-12-310000092122so:SouthernCompanyGasMemberstpr:GA2024-01-012024-12-310000092122stpr:OK2024-01-012024-12-310000092122so:SouthernPowerMemberstpr:OK2024-01-012024-12-310000092122stpr:AL2023-01-012023-12-310000092122so:AlabamaPowerMemberstpr:AL2023-01-012023-12-310000092122stpr:GA2023-01-012023-12-310000092122so:GeorgiaPowerMemberstpr:GA2023-01-012023-12-310000092122so:SouthernCompanyGasMemberstpr:GA2023-01-012023-12-310000092122stpr:OK2023-01-012023-12-310000092122stpr:IL2023-01-012023-12-310000092122so:SouthernCompanyGasMemberstpr:IL2023-01-012023-12-310000092122so:SouthernPowerMemberso:InvestmentTaxAndOtherCreditCarryforwardMember2025-01-012025-12-310000092122so:SouthernPowerMemberso:InvestmentTaxAndOtherCreditCarryforwardMember2024-01-012024-12-310000092122so:SouthernPowerMemberso:InvestmentTaxAndOtherCreditCarryforwardMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberus-gaap:StateAndLocalJurisdictionMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberus-gaap:StateAndLocalJurisdictionMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberso:ProductionTaxCreditCarryforwardMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberso:ProductionTaxCreditCarryforwardMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberso:ProductionTaxCreditCarryforwardMember2023-01-012023-12-310000092122so:AcceleratedDepreciationMember2025-12-310000092122so:AlabamaPowerMemberso:AcceleratedDepreciationMember2025-12-310000092122so:GeorgiaPowerMemberso:AcceleratedDepreciationMember2025-12-310000092122so:MississippiPowerMemberso:AcceleratedDepreciationMember2025-12-310000092122so:SouthernPowerMemberso:AcceleratedDepreciationMember2025-12-310000092122so:SouthernCompanyGasMemberso:AcceleratedDepreciationMember2025-12-310000092122so:PropertyBasisDifferencesMember2025-12-310000092122so:AlabamaPowerMemberso:PropertyBasisDifferencesMember2025-12-310000092122so:GeorgiaPowerMemberso:PropertyBasisDifferencesMember2025-12-310000092122so:MississippiPowerMemberso:PropertyBasisDifferencesMember2025-12-310000092122so:SouthernPowerMemberso:PropertyBasisDifferencesMember2025-12-310000092122so:SouthernCompanyGasMemberso:PropertyBasisDifferencesMember2025-12-310000092122so:EmployeeBenefitObligationsMember2025-12-310000092122so:AlabamaPowerMemberso:EmployeeBenefitObligationsMember2025-12-310000092122so:GeorgiaPowerMemberso:EmployeeBenefitObligationsMember2025-12-310000092122so:MississippiPowerMemberso:EmployeeBenefitObligationsMember2025-12-310000092122so:SouthernPowerMemberso:EmployeeBenefitObligationsMember2025-12-310000092122so:SouthernCompanyGasMemberso:EmployeeBenefitObligationsMember2025-12-310000092122us-gaap:AssetRetirementObligationCostsMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:AssetRetirementObligationCostsMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:AssetRetirementObligationCostsMember2025-12-310000092122so:MississippiPowerMemberus-gaap:AssetRetirementObligationCostsMember2025-12-310000092122so:SouthernPowerMemberus-gaap:AssetRetirementObligationCostsMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:AssetRetirementObligationCostsMember2025-12-310000092122so:UnderRecoveredFuelClauseAndNaturalGasCostsMember2025-12-310000092122so:AlabamaPowerMemberso:UnderRecoveredFuelClauseAndNaturalGasCostsMember2025-12-310000092122so:GeorgiaPowerMemberso:UnderRecoveredFuelClauseAndNaturalGasCostsMember2025-12-310000092122so:MississippiPowerMemberso:UnderRecoveredFuelClauseAndNaturalGasCostsMember2025-12-310000092122so:SouthernPowerMemberso:UnderRecoveredFuelClauseAndNaturalGasCostsMember2025-12-310000092122so:SouthernCompanyGasMemberso:UnderRecoveredFuelClauseAndNaturalGasCostsMember2025-12-310000092122so:RegulatoryAssetsAssociatedWithAssetRetirementObligationsMember2025-12-310000092122so:AlabamaPowerMemberso:RegulatoryAssetsAssociatedWithAssetRetirementObligationsMember2025-12-310000092122so:GeorgiaPowerMemberso:RegulatoryAssetsAssociatedWithAssetRetirementObligationsMember2025-12-310000092122so:MississippiPowerMemberso:RegulatoryAssetsAssociatedWithAssetRetirementObligationsMember2025-12-310000092122so:SouthernPowerMemberso:RegulatoryAssetsAssociatedWithAssetRetirementObligationsMember2025-12-310000092122so:SouthernCompanyGasMemberso:RegulatoryAssetsAssociatedWithAssetRetirementObligationsMember2025-12-310000092122so:RegulatoryAssetsAssociatedWithEmployeeBenefitObligationsMember2025-12-310000092122so:AlabamaPowerMemberso:RegulatoryAssetsAssociatedWithEmployeeBenefitObligationsMember2025-12-310000092122so:GeorgiaPowerMemberso:RegulatoryAssetsAssociatedWithEmployeeBenefitObligationsMember2025-12-310000092122so:MississippiPowerMemberso:RegulatoryAssetsAssociatedWithEmployeeBenefitObligationsMember2025-12-310000092122so:SouthernPowerMemberso:RegulatoryAssetsAssociatedWithEmployeeBenefitObligationsMember2025-12-310000092122so:SouthernCompanyGasMemberso:RegulatoryAssetsAssociatedWithEmployeeBenefitObligationsMember2025-12-310000092122so:RegulatoryAssetsAssociatedWithRemainingBookValueOfRetiredAssetsMember2025-12-310000092122so:AlabamaPowerMemberso:RegulatoryAssetsAssociatedWithRemainingBookValueOfRetiredAssetsMember2025-12-310000092122so:GeorgiaPowerMemberso:RegulatoryAssetsAssociatedWithRemainingBookValueOfRetiredAssetsMember2025-12-310000092122so:MississippiPowerMemberso:RegulatoryAssetsAssociatedWithRemainingBookValueOfRetiredAssetsMember2025-12-310000092122so:SouthernPowerMemberso:RegulatoryAssetsAssociatedWithRemainingBookValueOfRetiredAssetsMember2025-12-310000092122so:SouthernCompanyGasMemberso:RegulatoryAssetsAssociatedWithRemainingBookValueOfRetiredAssetsMember2025-12-310000092122so:RegulatoryAssetsAssociatedWithStormDamageReservesMember2025-12-310000092122so:AlabamaPowerMemberso:RegulatoryAssetsAssociatedWithStormDamageReservesMember2025-12-310000092122so:GeorgiaPowerMemberso:RegulatoryAssetsAssociatedWithStormDamageReservesMember2025-12-310000092122so:MississippiPowerMemberso:RegulatoryAssetsAssociatedWithStormDamageReservesMember2025-12-310000092122so:SouthernPowerMemberso:RegulatoryAssetsAssociatedWithStormDamageReservesMember2025-12-310000092122so:SouthernCompanyGasMemberso:RegulatoryAssetsAssociatedWithStormDamageReservesMember2025-12-310000092122so:PremiumOnReacquiredDebtMember2025-12-310000092122so:AlabamaPowerMemberso:PremiumOnReacquiredDebtMember2025-12-310000092122so:GeorgiaPowerMemberso:PremiumOnReacquiredDebtMember2025-12-310000092122so:MississippiPowerMemberso:PremiumOnReacquiredDebtMember2025-12-310000092122so:SouthernPowerMemberso:PremiumOnReacquiredDebtMember2025-12-310000092122so:SouthernCompanyGasMemberso:PremiumOnReacquiredDebtMember2025-12-310000092122so:OtherDeferredTaxLiabilitiesMember2025-12-310000092122so:AlabamaPowerMemberso:OtherDeferredTaxLiabilitiesMember2025-12-310000092122so:GeorgiaPowerMemberso:OtherDeferredTaxLiabilitiesMember2025-12-310000092122so:MississippiPowerMemberso:OtherDeferredTaxLiabilitiesMember2025-12-310000092122so:SouthernPowerMemberso:OtherDeferredTaxLiabilitiesMember2025-12-310000092122so:SouthernCompanyGasMemberso:OtherDeferredTaxLiabilitiesMember2025-12-310000092122so:AssetRetirementObligationLiabilityMember2025-12-310000092122so:AlabamaPowerMemberso:AssetRetirementObligationLiabilityMember2025-12-310000092122so:GeorgiaPowerMemberso:AssetRetirementObligationLiabilityMember2025-12-310000092122so:MississippiPowerMemberso:AssetRetirementObligationLiabilityMember2025-12-310000092122so:SouthernPowerMemberso:AssetRetirementObligationLiabilityMember2025-12-310000092122so:SouthernCompanyGasMemberso:AssetRetirementObligationLiabilityMember2025-12-310000092122us-gaap:InvestmentCreditMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:InvestmentCreditMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:InvestmentCreditMember2025-12-310000092122so:MississippiPowerMemberus-gaap:InvestmentCreditMember2025-12-310000092122so:SouthernPowerMemberus-gaap:InvestmentCreditMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:InvestmentCreditMember2025-12-310000092122so:KemperIGCCLossMember2025-12-310000092122so:AlabamaPowerMemberso:KemperIGCCLossMember2025-12-310000092122so:GeorgiaPowerMemberso:KemperIGCCLossMember2025-12-310000092122so:MississippiPowerMemberso:KemperIGCCLossMember2025-12-310000092122so:SouthernPowerMemberso:KemperIGCCLossMember2025-12-310000092122so:SouthernCompanyGasMemberso:KemperIGCCLossMember2025-12-310000092122so:EstimatedLossOnRegulatoryDisallowanceMember2025-12-310000092122so:AlabamaPowerMemberso:EstimatedLossOnRegulatoryDisallowanceMember2025-12-310000092122so:GeorgiaPowerMemberso:EstimatedLossOnRegulatoryDisallowanceMember2025-12-310000092122so:MississippiPowerMemberso:EstimatedLossOnRegulatoryDisallowanceMember2025-12-310000092122so:SouthernPowerMemberso:EstimatedLossOnRegulatoryDisallowanceMember2025-12-310000092122so:SouthernCompanyGasMemberso:EstimatedLossOnRegulatoryDisallowanceMember2025-12-310000092122so:DeferredStateTaxAssetsMember2025-12-310000092122so:AlabamaPowerMemberso:DeferredStateTaxAssetsMember2025-12-310000092122so:GeorgiaPowerMemberso:DeferredStateTaxAssetsMember2025-12-310000092122so:MississippiPowerMemberso:DeferredStateTaxAssetsMember2025-12-310000092122so:SouthernPowerMemberso:DeferredStateTaxAssetsMember2025-12-310000092122so:SouthernCompanyGasMemberso:DeferredStateTaxAssetsMember2025-12-310000092122so:FederalEffectOfStateDeferredTaxesMember2025-12-310000092122so:AlabamaPowerMemberso:FederalEffectOfStateDeferredTaxesMember2025-12-310000092122so:GeorgiaPowerMemberso:FederalEffectOfStateDeferredTaxesMember2025-12-310000092122so:MississippiPowerMemberso:FederalEffectOfStateDeferredTaxesMember2025-12-310000092122so:SouthernPowerMemberso:FederalEffectOfStateDeferredTaxesMember2025-12-310000092122so:SouthernCompanyGasMemberso:FederalEffectOfStateDeferredTaxesMember2025-12-310000092122so:OtherPropertyBasisDifferencesMember2025-12-310000092122so:AlabamaPowerMemberso:OtherPropertyBasisDifferencesMember2025-12-310000092122so:GeorgiaPowerMemberso:OtherPropertyBasisDifferencesMember2025-12-310000092122so:MississippiPowerMemberso:OtherPropertyBasisDifferencesMember2025-12-310000092122so:SouthernPowerMemberso:OtherPropertyBasisDifferencesMember2025-12-310000092122so:SouthernCompanyGasMemberso:OtherPropertyBasisDifferencesMember2025-12-310000092122so:StateEffectOfFederalDeferredTaxesMember2025-12-310000092122so:AlabamaPowerMemberso:StateEffectOfFederalDeferredTaxesMember2025-12-310000092122so:GeorgiaPowerMemberso:StateEffectOfFederalDeferredTaxesMember2025-12-310000092122so:MississippiPowerMemberso:StateEffectOfFederalDeferredTaxesMember2025-12-310000092122so:SouthernPowerMemberso:StateEffectOfFederalDeferredTaxesMember2025-12-310000092122so:SouthernCompanyGasMemberso:StateEffectOfFederalDeferredTaxesMember2025-12-310000092122so:OtherPartnershipBasisDifferenceMember2025-12-310000092122so:AlabamaPowerMemberso:OtherPartnershipBasisDifferenceMember2025-12-310000092122so:GeorgiaPowerMemberso:OtherPartnershipBasisDifferenceMember2025-12-310000092122so:MississippiPowerMemberso:OtherPartnershipBasisDifferenceMember2025-12-310000092122so:SouthernPowerMemberso:OtherPartnershipBasisDifferenceMember2025-12-310000092122so:SouthernCompanyGasMemberso:OtherPartnershipBasisDifferenceMember2025-12-310000092122so:RegulatoryLiabilityAssociatedWithTaxReformMember2025-12-310000092122so:AlabamaPowerMemberso:RegulatoryLiabilityAssociatedWithTaxReformMember2025-12-310000092122so:GeorgiaPowerMemberso:RegulatoryLiabilityAssociatedWithTaxReformMember2025-12-310000092122so:MississippiPowerMemberso:RegulatoryLiabilityAssociatedWithTaxReformMember2025-12-310000092122so:SouthernPowerMemberso:RegulatoryLiabilityAssociatedWithTaxReformMember2025-12-310000092122so:SouthernCompanyGasMemberso:RegulatoryLiabilityAssociatedWithTaxReformMember2025-12-310000092122so:DeferredTaxAssetFairValueOfSeniorNotesMember2025-12-310000092122so:AlabamaPowerMemberso:DeferredTaxAssetFairValueOfSeniorNotesMember2025-12-310000092122so:GeorgiaPowerMemberso:DeferredTaxAssetFairValueOfSeniorNotesMember2025-12-310000092122so:MississippiPowerMemberso:DeferredTaxAssetFairValueOfSeniorNotesMember2025-12-310000092122so:SouthernPowerMemberso:DeferredTaxAssetFairValueOfSeniorNotesMember2025-12-310000092122so:SouthernCompanyGasMemberso:DeferredTaxAssetFairValueOfSeniorNotesMember2025-12-310000092122so:OtherComprehensiveIncomeLossesMember2025-12-310000092122so:AlabamaPowerMemberso:OtherComprehensiveIncomeLossesMember2025-12-310000092122so:GeorgiaPowerMemberso:OtherComprehensiveIncomeLossesMember2025-12-310000092122so:MississippiPowerMemberso:OtherComprehensiveIncomeLossesMember2025-12-310000092122so:SouthernPowerMemberso:OtherComprehensiveIncomeLossesMember2025-12-310000092122so:SouthernCompanyGasMemberso:OtherComprehensiveIncomeLossesMember2025-12-310000092122so:OtherDeferredTaxAssetsMember2025-12-310000092122so:AlabamaPowerMemberso:OtherDeferredTaxAssetsMember2025-12-310000092122so:GeorgiaPowerMemberso:OtherDeferredTaxAssetsMember2025-12-310000092122so:MississippiPowerMemberso:OtherDeferredTaxAssetsMember2025-12-310000092122so:SouthernPowerMemberso:OtherDeferredTaxAssetsMember2025-12-310000092122so:SouthernCompanyGasMemberso:OtherDeferredTaxAssetsMember2025-12-310000092122so:AcceleratedDepreciationMember2024-12-310000092122so:AlabamaPowerMemberso:AcceleratedDepreciationMember2024-12-310000092122so:GeorgiaPowerMemberso:AcceleratedDepreciationMember2024-12-310000092122so:MississippiPowerMemberso:AcceleratedDepreciationMember2024-12-310000092122so:SouthernPowerMemberso:AcceleratedDepreciationMember2024-12-310000092122so:SouthernCompanyGasMemberso:AcceleratedDepreciationMember2024-12-310000092122so:PropertyBasisDifferencesMember2024-12-310000092122so:AlabamaPowerMemberso:PropertyBasisDifferencesMember2024-12-310000092122so:GeorgiaPowerMemberso:PropertyBasisDifferencesMember2024-12-310000092122so:MississippiPowerMemberso:PropertyBasisDifferencesMember2024-12-310000092122so:SouthernPowerMemberso:PropertyBasisDifferencesMember2024-12-310000092122so:SouthernCompanyGasMemberso:PropertyBasisDifferencesMember2024-12-310000092122so:EmployeeBenefitObligationsMember2024-12-310000092122so:AlabamaPowerMemberso:EmployeeBenefitObligationsMember2024-12-310000092122so:GeorgiaPowerMemberso:EmployeeBenefitObligationsMember2024-12-310000092122so:MississippiPowerMemberso:EmployeeBenefitObligationsMember2024-12-310000092122so:SouthernPowerMemberso:EmployeeBenefitObligationsMember2024-12-310000092122so:SouthernCompanyGasMemberso:EmployeeBenefitObligationsMember2024-12-310000092122us-gaap:AssetRetirementObligationCostsMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:AssetRetirementObligationCostsMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:AssetRetirementObligationCostsMember2024-12-310000092122so:MississippiPowerMemberus-gaap:AssetRetirementObligationCostsMember2024-12-310000092122so:SouthernPowerMemberus-gaap:AssetRetirementObligationCostsMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:AssetRetirementObligationCostsMember2024-12-310000092122so:UnderRecoveredFuelClauseAndNaturalGasCostsMember2024-12-310000092122so:AlabamaPowerMemberso:UnderRecoveredFuelClauseAndNaturalGasCostsMember2024-12-310000092122so:GeorgiaPowerMemberso:UnderRecoveredFuelClauseAndNaturalGasCostsMember2024-12-310000092122so:MississippiPowerMemberso:UnderRecoveredFuelClauseAndNaturalGasCostsMember2024-12-310000092122so:SouthernPowerMemberso:UnderRecoveredFuelClauseAndNaturalGasCostsMember2024-12-310000092122so:SouthernCompanyGasMemberso:UnderRecoveredFuelClauseAndNaturalGasCostsMember2024-12-310000092122so:RegulatoryAssetsAssociatedWithAssetRetirementObligationsMember2024-12-310000092122so:AlabamaPowerMemberso:RegulatoryAssetsAssociatedWithAssetRetirementObligationsMember2024-12-310000092122so:GeorgiaPowerMemberso:RegulatoryAssetsAssociatedWithAssetRetirementObligationsMember2024-12-310000092122so:MississippiPowerMemberso:RegulatoryAssetsAssociatedWithAssetRetirementObligationsMember2024-12-310000092122so:SouthernPowerMemberso:RegulatoryAssetsAssociatedWithAssetRetirementObligationsMember2024-12-310000092122so:SouthernCompanyGasMemberso:RegulatoryAssetsAssociatedWithAssetRetirementObligationsMember2024-12-310000092122so:RegulatoryAssetsAssociatedWithEmployeeBenefitObligationsMember2024-12-310000092122so:AlabamaPowerMemberso:RegulatoryAssetsAssociatedWithEmployeeBenefitObligationsMember2024-12-310000092122so:GeorgiaPowerMemberso:RegulatoryAssetsAssociatedWithEmployeeBenefitObligationsMember2024-12-310000092122so:MississippiPowerMemberso:RegulatoryAssetsAssociatedWithEmployeeBenefitObligationsMember2024-12-310000092122so:SouthernPowerMemberso:RegulatoryAssetsAssociatedWithEmployeeBenefitObligationsMember2024-12-310000092122so:SouthernCompanyGasMemberso:RegulatoryAssetsAssociatedWithEmployeeBenefitObligationsMember2024-12-310000092122so:RegulatoryAssetsAssociatedWithRemainingBookValueOfRetiredAssetsMember2024-12-310000092122so:AlabamaPowerMemberso:RegulatoryAssetsAssociatedWithRemainingBookValueOfRetiredAssetsMember2024-12-310000092122so:GeorgiaPowerMemberso:RegulatoryAssetsAssociatedWithRemainingBookValueOfRetiredAssetsMember2024-12-310000092122so:MississippiPowerMemberso:RegulatoryAssetsAssociatedWithRemainingBookValueOfRetiredAssetsMember2024-12-310000092122so:SouthernPowerMemberso:RegulatoryAssetsAssociatedWithRemainingBookValueOfRetiredAssetsMember2024-12-310000092122so:SouthernCompanyGasMemberso:RegulatoryAssetsAssociatedWithRemainingBookValueOfRetiredAssetsMember2024-12-310000092122so:RegulatoryAssetsAssociatedWithStormDamageReservesMember2024-12-310000092122so:AlabamaPowerMemberso:RegulatoryAssetsAssociatedWithStormDamageReservesMember2024-12-310000092122so:GeorgiaPowerMemberso:RegulatoryAssetsAssociatedWithStormDamageReservesMember2024-12-310000092122so:MississippiPowerMemberso:RegulatoryAssetsAssociatedWithStormDamageReservesMember2024-12-310000092122so:SouthernPowerMemberso:RegulatoryAssetsAssociatedWithStormDamageReservesMember2024-12-310000092122so:SouthernCompanyGasMemberso:RegulatoryAssetsAssociatedWithStormDamageReservesMember2024-12-310000092122so:PremiumOnReacquiredDebtMember2024-12-310000092122so:AlabamaPowerMemberso:PremiumOnReacquiredDebtMember2024-12-310000092122so:GeorgiaPowerMemberso:PremiumOnReacquiredDebtMember2024-12-310000092122so:MississippiPowerMemberso:PremiumOnReacquiredDebtMember2024-12-310000092122so:SouthernPowerMemberso:PremiumOnReacquiredDebtMember2024-12-310000092122so:SouthernCompanyGasMemberso:PremiumOnReacquiredDebtMember2024-12-310000092122so:OtherDeferredTaxLiabilitiesMember2024-12-310000092122so:AlabamaPowerMemberso:OtherDeferredTaxLiabilitiesMember2024-12-310000092122so:GeorgiaPowerMemberso:OtherDeferredTaxLiabilitiesMember2024-12-310000092122so:MississippiPowerMemberso:OtherDeferredTaxLiabilitiesMember2024-12-310000092122so:SouthernPowerMemberso:OtherDeferredTaxLiabilitiesMember2024-12-310000092122so:SouthernCompanyGasMemberso:OtherDeferredTaxLiabilitiesMember2024-12-310000092122so:AssetRetirementObligationLiabilityMember2024-12-310000092122so:AlabamaPowerMemberso:AssetRetirementObligationLiabilityMember2024-12-310000092122so:GeorgiaPowerMemberso:AssetRetirementObligationLiabilityMember2024-12-310000092122so:MississippiPowerMemberso:AssetRetirementObligationLiabilityMember2024-12-310000092122so:SouthernPowerMemberso:AssetRetirementObligationLiabilityMember2024-12-310000092122so:SouthernCompanyGasMemberso:AssetRetirementObligationLiabilityMember2024-12-310000092122so:CAMTCarryforwardsMember2024-12-310000092122so:AlabamaPowerMemberso:CAMTCarryforwardsMember2024-12-310000092122so:GeorgiaPowerMemberso:CAMTCarryforwardsMember2024-12-310000092122so:MississippiPowerMemberso:CAMTCarryforwardsMember2024-12-310000092122so:SouthernPowerMemberso:CAMTCarryforwardsMember2024-12-310000092122so:SouthernCompanyGasMemberso:CAMTCarryforwardsMember2024-12-310000092122us-gaap:InvestmentCreditMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:InvestmentCreditMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:InvestmentCreditMember2024-12-310000092122so:MississippiPowerMemberus-gaap:InvestmentCreditMember2024-12-310000092122so:SouthernPowerMemberus-gaap:InvestmentCreditMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:InvestmentCreditMember2024-12-310000092122so:KemperIGCCLossMember2024-12-310000092122so:AlabamaPowerMemberso:KemperIGCCLossMember2024-12-310000092122so:GeorgiaPowerMemberso:KemperIGCCLossMember2024-12-310000092122so:MississippiPowerMemberso:KemperIGCCLossMember2024-12-310000092122so:SouthernPowerMemberso:KemperIGCCLossMember2024-12-310000092122so:SouthernCompanyGasMemberso:KemperIGCCLossMember2024-12-310000092122so:EstimatedLossOnRegulatoryDisallowanceMember2024-12-310000092122so:AlabamaPowerMemberso:EstimatedLossOnRegulatoryDisallowanceMember2024-12-310000092122so:GeorgiaPowerMemberso:EstimatedLossOnRegulatoryDisallowanceMember2024-12-310000092122so:MississippiPowerMemberso:EstimatedLossOnRegulatoryDisallowanceMember2024-12-310000092122so:SouthernPowerMemberso:EstimatedLossOnRegulatoryDisallowanceMember2024-12-310000092122so:SouthernCompanyGasMemberso:EstimatedLossOnRegulatoryDisallowanceMember2024-12-310000092122so:DeferredStateTaxAssetsMember2024-12-310000092122so:AlabamaPowerMemberso:DeferredStateTaxAssetsMember2024-12-310000092122so:GeorgiaPowerMemberso:DeferredStateTaxAssetsMember2024-12-310000092122so:MississippiPowerMemberso:DeferredStateTaxAssetsMember2024-12-310000092122so:SouthernPowerMemberso:DeferredStateTaxAssetsMember2024-12-310000092122so:SouthernCompanyGasMemberso:DeferredStateTaxAssetsMember2024-12-310000092122so:FederalEffectOfStateDeferredTaxesMember2024-12-310000092122so:AlabamaPowerMemberso:FederalEffectOfStateDeferredTaxesMember2024-12-310000092122so:GeorgiaPowerMemberso:FederalEffectOfStateDeferredTaxesMember2024-12-310000092122so:MississippiPowerMemberso:FederalEffectOfStateDeferredTaxesMember2024-12-310000092122so:SouthernPowerMemberso:FederalEffectOfStateDeferredTaxesMember2024-12-310000092122so:SouthernCompanyGasMemberso:FederalEffectOfStateDeferredTaxesMember2024-12-310000092122so:OtherPropertyBasisDifferencesMember2024-12-310000092122so:AlabamaPowerMemberso:OtherPropertyBasisDifferencesMember2024-12-310000092122so:GeorgiaPowerMemberso:OtherPropertyBasisDifferencesMember2024-12-310000092122so:MississippiPowerMemberso:OtherPropertyBasisDifferencesMember2024-12-310000092122so:SouthernPowerMemberso:OtherPropertyBasisDifferencesMember2024-12-310000092122so:SouthernCompanyGasMemberso:OtherPropertyBasisDifferencesMember2024-12-310000092122so:StateEffectOfFederalDeferredTaxesMember2024-12-310000092122so:AlabamaPowerMemberso:StateEffectOfFederalDeferredTaxesMember2024-12-310000092122so:GeorgiaPowerMemberso:StateEffectOfFederalDeferredTaxesMember2024-12-310000092122so:MississippiPowerMemberso:StateEffectOfFederalDeferredTaxesMember2024-12-310000092122so:SouthernPowerMemberso:StateEffectOfFederalDeferredTaxesMember2024-12-310000092122so:SouthernCompanyGasMemberso:StateEffectOfFederalDeferredTaxesMember2024-12-310000092122so:OtherPartnershipBasisDifferenceMember2024-12-310000092122so:AlabamaPowerMemberso:OtherPartnershipBasisDifferenceMember2024-12-310000092122so:GeorgiaPowerMemberso:OtherPartnershipBasisDifferenceMember2024-12-310000092122so:MississippiPowerMemberso:OtherPartnershipBasisDifferenceMember2024-12-310000092122so:SouthernPowerMemberso:OtherPartnershipBasisDifferenceMember2024-12-310000092122so:SouthernCompanyGasMemberso:OtherPartnershipBasisDifferenceMember2024-12-310000092122so:RegulatoryLiabilityAssociatedWithTaxReformMember2024-12-310000092122so:AlabamaPowerMemberso:RegulatoryLiabilityAssociatedWithTaxReformMember2024-12-310000092122so:GeorgiaPowerMemberso:RegulatoryLiabilityAssociatedWithTaxReformMember2024-12-310000092122so:MississippiPowerMemberso:RegulatoryLiabilityAssociatedWithTaxReformMember2024-12-310000092122so:SouthernPowerMemberso:RegulatoryLiabilityAssociatedWithTaxReformMember2024-12-310000092122so:SouthernCompanyGasMemberso:RegulatoryLiabilityAssociatedWithTaxReformMember2024-12-310000092122so:DeferredTaxAssetFairValueOfSeniorNotesMember2024-12-310000092122so:AlabamaPowerMemberso:DeferredTaxAssetFairValueOfSeniorNotesMember2024-12-310000092122so:GeorgiaPowerMemberso:DeferredTaxAssetFairValueOfSeniorNotesMember2024-12-310000092122so:MississippiPowerMemberso:DeferredTaxAssetFairValueOfSeniorNotesMember2024-12-310000092122so:SouthernPowerMemberso:DeferredTaxAssetFairValueOfSeniorNotesMember2024-12-310000092122so:SouthernCompanyGasMemberso:DeferredTaxAssetFairValueOfSeniorNotesMember2024-12-310000092122so:OtherComprehensiveIncomeLossesMember2024-12-310000092122so:AlabamaPowerMemberso:OtherComprehensiveIncomeLossesMember2024-12-310000092122so:GeorgiaPowerMemberso:OtherComprehensiveIncomeLossesMember2024-12-310000092122so:MississippiPowerMemberso:OtherComprehensiveIncomeLossesMember2024-12-310000092122so:SouthernPowerMemberso:OtherComprehensiveIncomeLossesMember2024-12-310000092122so:SouthernCompanyGasMemberso:OtherComprehensiveIncomeLossesMember2024-12-310000092122so:OtherDeferredTaxAssetsMember2024-12-310000092122so:AlabamaPowerMemberso:OtherDeferredTaxAssetsMember2024-12-310000092122so:GeorgiaPowerMemberso:OtherDeferredTaxAssetsMember2024-12-310000092122so:MississippiPowerMemberso:OtherDeferredTaxAssetsMember2024-12-310000092122so:SouthernPowerMemberso:OtherDeferredTaxAssetsMember2024-12-310000092122so:SouthernCompanyGasMemberso:OtherDeferredTaxAssetsMember2024-12-310000092122us-gaap:InvestmentCreditMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:InvestmentCreditMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:InvestmentCreditMember2025-12-310000092122so:SouthernPowerMemberus-gaap:InvestmentCreditMember2025-12-310000092122us-gaap:StateAndLocalJurisdictionMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:StateAndLocalJurisdictionMember2025-12-310000092122us-gaap:StateAndLocalJurisdictionMember2025-01-012025-12-310000092122stpr:MSso:MississippiPowerMember2025-12-310000092122stpr:OKso:SouthernPowerMember2025-12-310000092122stpr:FLso:SouthernPowerMember2025-12-310000092122so:OtherStatesMemberso:SouthernPowerMember2025-12-310000092122stpr:NYso:OtherSubsidiariesMember2025-12-310000092122so:NewYorkCityMemberso:OtherSubsidiariesMember2025-12-310000092122so:OtherStatesMemberso:OtherSubsidiariesMember2025-12-310000092122so:KemperIGCCLossMember2023-01-012023-12-310000092122so:AlabamaPowerMemberso:KemperIGCCLossMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberso:KemperIGCCLossMember2023-01-012023-12-310000092122so:SouthernCompanyGasMemberso:KemperIGCCLossMember2023-01-012023-12-310000092122us-gaap:QualifiedPlanMemberus-gaap:PensionPlansDefinedBenefitMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122so:MississippiPowerMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122so:SouthernPowerMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122so:MeasurementInputDiscountRateInterestCostsMemberus-gaap:PensionPlansDefinedBenefitMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:AlabamaPowerMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:MississippiPowerMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:SouthernPowerMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:MeasurementInputDiscountRateServiceCostsMemberus-gaap:PensionPlansDefinedBenefitMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:AlabamaPowerMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:MississippiPowerMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:SouthernPowerMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMember2025-01-012025-12-310000092122so:AlabamaPowerMemberus-gaap:PensionPlansDefinedBenefitMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberus-gaap:PensionPlansDefinedBenefitMember2025-01-012025-12-310000092122so:MississippiPowerMemberus-gaap:PensionPlansDefinedBenefitMember2025-01-012025-12-310000092122so:SouthernPowerMemberus-gaap:PensionPlansDefinedBenefitMember2025-01-012025-12-310000092122so:SouthernCompanyGasMemberus-gaap:PensionPlansDefinedBenefitMember2025-01-012025-12-310000092122so:AlabamaPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122so:MississippiPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122so:SouthernPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122so:MeasurementInputDiscountRateInterestCostsMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:AlabamaPowerMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:MississippiPowerMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:SouthernPowerMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:MeasurementInputDiscountRateServiceCostsMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:AlabamaPowerMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:MississippiPowerMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:SouthernPowerMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-01-012025-12-310000092122so:AlabamaPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-01-012025-12-310000092122so:MississippiPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-01-012025-12-310000092122so:SouthernPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-01-012025-12-310000092122so:SouthernCompanyGasMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122so:MississippiPowerMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122so:SouthernPowerMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122so:MeasurementInputDiscountRateInterestCostsMemberus-gaap:PensionPlansDefinedBenefitMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:AlabamaPowerMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:MississippiPowerMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:SouthernPowerMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:MeasurementInputDiscountRateServiceCostsMemberus-gaap:PensionPlansDefinedBenefitMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:AlabamaPowerMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:MississippiPowerMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:SouthernPowerMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMember2024-01-012024-12-310000092122so:AlabamaPowerMemberus-gaap:PensionPlansDefinedBenefitMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberus-gaap:PensionPlansDefinedBenefitMember2024-01-012024-12-310000092122so:MississippiPowerMemberus-gaap:PensionPlansDefinedBenefitMember2024-01-012024-12-310000092122so:SouthernPowerMemberus-gaap:PensionPlansDefinedBenefitMember2024-01-012024-12-310000092122so:SouthernCompanyGasMemberus-gaap:PensionPlansDefinedBenefitMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122so:MississippiPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122so:SouthernPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122so:MeasurementInputDiscountRateInterestCostsMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:AlabamaPowerMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:MississippiPowerMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:SouthernPowerMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:MeasurementInputDiscountRateServiceCostsMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:AlabamaPowerMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:MississippiPowerMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:SouthernPowerMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-01-012024-12-310000092122so:AlabamaPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-01-012024-12-310000092122so:MississippiPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-01-012024-12-310000092122so:SouthernPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-01-012024-12-310000092122so:SouthernCompanyGasMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMember2023-12-310000092122so:AlabamaPowerMemberus-gaap:PensionPlansDefinedBenefitMember2023-12-310000092122so:GeorgiaPowerMemberus-gaap:PensionPlansDefinedBenefitMember2023-12-310000092122so:MississippiPowerMemberus-gaap:PensionPlansDefinedBenefitMember2023-12-310000092122so:SouthernPowerMemberus-gaap:PensionPlansDefinedBenefitMember2023-12-310000092122so:SouthernCompanyGasMemberus-gaap:PensionPlansDefinedBenefitMember2023-12-310000092122so:MeasurementInputDiscountRateInterestCostsMemberus-gaap:PensionPlansDefinedBenefitMember2023-01-012023-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:AlabamaPowerMember2023-01-012023-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:MississippiPowerMember2023-01-012023-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:SouthernPowerMember2023-01-012023-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:MeasurementInputDiscountRateServiceCostsMemberus-gaap:PensionPlansDefinedBenefitMember2023-01-012023-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:AlabamaPowerMember2023-01-012023-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:MississippiPowerMember2023-01-012023-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:SouthernPowerMember2023-01-012023-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122us-gaap:PensionPlansDefinedBenefitMember2023-01-012023-12-310000092122so:AlabamaPowerMemberus-gaap:PensionPlansDefinedBenefitMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberus-gaap:PensionPlansDefinedBenefitMember2023-01-012023-12-310000092122so:MississippiPowerMemberus-gaap:PensionPlansDefinedBenefitMember2023-01-012023-12-310000092122so:SouthernPowerMemberus-gaap:PensionPlansDefinedBenefitMember2023-01-012023-12-310000092122so:SouthernCompanyGasMemberus-gaap:PensionPlansDefinedBenefitMember2023-01-012023-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2023-12-310000092122so:AlabamaPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2023-12-310000092122so:GeorgiaPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2023-12-310000092122so:MississippiPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2023-12-310000092122so:SouthernPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2023-12-310000092122so:SouthernCompanyGasMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2023-12-310000092122so:MeasurementInputDiscountRateInterestCostsMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2023-01-012023-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:AlabamaPowerMember2023-01-012023-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:MississippiPowerMember2023-01-012023-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:SouthernPowerMember2023-01-012023-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateInterestCostsMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:MeasurementInputDiscountRateServiceCostsMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2023-01-012023-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:AlabamaPowerMember2023-01-012023-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:MississippiPowerMember2023-01-012023-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:SouthernPowerMember2023-01-012023-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MeasurementInputDiscountRateServiceCostsMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2023-01-012023-12-310000092122so:AlabamaPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2023-01-012023-12-310000092122so:MississippiPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2023-01-012023-12-310000092122so:SouthernPowerMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2023-01-012023-12-310000092122so:SouthernCompanyGasMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2023-01-012023-12-310000092122so:EmployeeBenefitObligationsMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:MississippiPowerMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:SouthernPowerMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:SouthernCompanyGasMember2025-12-310000092122so:EmployeeBenefitObligationsMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:MississippiPowerMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:SouthernPowerMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:SouthernCompanyGasMember2025-12-310000092122so:EmployeeBenefitObligationsMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:MississippiPowerMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:SouthernPowerMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:SouthernCompanyGasMember2024-12-310000092122so:EmployeeBenefitObligationsMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:MississippiPowerMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:SouthernPowerMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:EmployeeBenefitObligationsMemberso:SouthernCompanyGasMember2024-12-310000092122so:MeasurementInputHealthcareCostTrendPre65Member2025-12-310000092122so:MeasurementInputHealthcareCostTrendPost65MedicalMember2025-12-310000092122so:MeasurementInputHealthcareCostTrendPost65PrescriptionMember2025-12-310000092122us-gaap:QualifiedPlanMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:QualifiedPlanMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:QualifiedPlanMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:QualifiedPlanMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMember2025-12-310000092122us-gaap:QualifiedPlanMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMember2025-12-310000092122us-gaap:QualifiedPlanMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:NonqualifiedPlanMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:NonqualifiedPlanMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:NonqualifiedPlanMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:NonqualifiedPlanMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMember2025-12-310000092122us-gaap:NonqualifiedPlanMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMember2025-12-310000092122us-gaap:NonqualifiedPlanMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMember2025-12-310000092122so:PriorServiceCostMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:PriorServiceCostMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:PriorServiceCostMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:PriorServiceCostMemberso:MississippiPowerMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:PriorServiceCostMemberso:SouthernCompanyGasMember2025-12-310000092122so:NetActuarialGainLossMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:NetActuarialGainLossMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:NetActuarialGainLossMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:NetActuarialGainLossMemberso:MississippiPowerMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:NetActuarialGainLossMemberso:SouthernCompanyGasMember2025-12-310000092122so:RegulatoryAmortizationMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:RegulatoryAmortizationMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:RegulatoryAmortizationMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:RegulatoryAmortizationMemberso:MississippiPowerMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:RegulatoryAmortizationMemberso:SouthernCompanyGasMember2025-12-310000092122so:PriorServiceCostMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:PriorServiceCostMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:PriorServiceCostMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:PriorServiceCostMemberso:MississippiPowerMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:PriorServiceCostMemberso:SouthernCompanyGasMember2024-12-310000092122so:NetActuarialGainLossMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:NetActuarialGainLossMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:NetActuarialGainLossMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:NetActuarialGainLossMemberso:MississippiPowerMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:NetActuarialGainLossMemberso:SouthernCompanyGasMember2024-12-310000092122so:RegulatoryAmortizationMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:RegulatoryAmortizationMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:RegulatoryAmortizationMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:RegulatoryAmortizationMemberso:MississippiPowerMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:RegulatoryAmortizationMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:RegulatoryAssetsMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:RegulatoryAssetsMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:RegulatoryAssetsMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:RegulatoryAssetsMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:RegulatoryAssetsMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentMemberso:RegulatoryAssetsMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentMemberso:RegulatoryAssetsMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentMemberso:RegulatoryAssetsMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentMemberso:RegulatoryAssetsMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentMemberso:RegulatoryAssetsMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:RegulatoryAssetsMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:RegulatoryAssetsMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:RegulatoryAssetsMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:RegulatoryAssetsMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:RegulatoryAssetsMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2023-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2023-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2023-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetPriorServiceIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetPriorServiceIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetPriorServiceIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AccumulatedDefinedBenefitPlansAdjustmentAmortizationOfNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:AccumulatedDefinedBenefitPlansAdjustmentAmortizationOfNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:AccumulatedDefinedBenefitPlansAdjustmentAmortizationOfNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetPriorServiceIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetPriorServiceIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetPriorServiceIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AccumulatedDefinedBenefitPlansAdjustmentAmortizationOfNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:AccumulatedDefinedBenefitPlansAdjustmentAmortizationOfNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:AccumulatedDefinedBenefitPlansAdjustmentAmortizationOfNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2025-12-310000092122so:PriorServiceCostMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PriorServiceCostMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PriorServiceCostMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PriorServiceCostMemberso:MississippiPowerMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PriorServiceCostMemberso:SouthernCompanyGasMember2025-12-310000092122so:NetActuarialGainLossMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:NetActuarialGainLossMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:NetActuarialGainLossMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:NetActuarialGainLossMemberso:MississippiPowerMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:NetActuarialGainLossMemberso:SouthernCompanyGasMember2025-12-310000092122so:RegulatoryAmortizationMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:RegulatoryAmortizationMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:RegulatoryAmortizationMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:RegulatoryAmortizationMemberso:MississippiPowerMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:RegulatoryAmortizationMemberso:SouthernCompanyGasMember2025-12-310000092122so:PriorServiceCostMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PriorServiceCostMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PriorServiceCostMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PriorServiceCostMemberso:MississippiPowerMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PriorServiceCostMemberso:SouthernCompanyGasMember2024-12-310000092122so:NetActuarialGainLossMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:NetActuarialGainLossMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:NetActuarialGainLossMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:NetActuarialGainLossMemberso:MississippiPowerMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:NetActuarialGainLossMemberso:SouthernCompanyGasMember2024-12-310000092122so:RegulatoryAmortizationMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:RegulatoryAmortizationMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:RegulatoryAmortizationMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:RegulatoryAmortizationMemberso:MississippiPowerMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:RegulatoryAmortizationMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:RegulatoryAssetsMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:RegulatoryAssetsMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:RegulatoryAssetsMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:RegulatoryAssetsMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:RegulatoryAssetsMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:RegulatoryAssetsMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:RegulatoryAssetsMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:RegulatoryAssetsMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:RegulatoryAssetsMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:RegulatoryAssetsMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2023-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2023-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2023-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AccumulatedDefinedBenefitPlansAdjustmentAmortizationOfNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernPowerMemberso:AccumulatedDefinedBenefitPlansAdjustmentAmortizationOfNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:AccumulatedDefinedBenefitPlansAdjustmentAmortizationOfNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2024-01-012024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AccumulatedDefinedBenefitPlansAdjustmentAmortizationOfNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernPowerMemberso:AccumulatedDefinedBenefitPlansAdjustmentAmortizationOfNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:AccumulatedDefinedBenefitPlansAdjustmentAmortizationOfNetGainLossIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2025-01-012025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AccumulatedDefinedBenefitPlansAdjustmentIncludingPortionAttributableToNoncontrollingInterestMember2025-12-310000092122us-gaap:DefinedBenefitPlanEquitySecuritiesMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:USStatesAndPoliticalSubdivisionsMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:ForeignGovernmentDebtSecuritiesMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:FixedIncomeSecuritiesMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:PooledFundsMember2025-12-310000092122so:PooledFundsMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:CashEquivalentsAndOtherMember2025-12-310000092122so:CashEquivalentsAndOtherMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:RealEstateInvestmentMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122so:SpecialSituationsInvestmentsMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:PrivateCreditMember2025-12-310000092122so:PrivateCreditMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:InfrastructureMember2025-12-310000092122so:InfrastructureMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:FixedIncomeSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:FixedIncomeSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:FixedIncomeSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:FixedIncomeSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:FixedIncomeSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PooledFundsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PrivateCreditMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:InfrastructureMember2025-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:DefinedBenefitPlanEquitySecuritiesMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:USStatesAndPoliticalSubdivisionsMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:ForeignGovernmentDebtSecuritiesMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:FixedIncomeSecuritiesMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:PooledFundsMember2024-12-310000092122so:PooledFundsMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:CashEquivalentsAndOtherMember2024-12-310000092122so:CashEquivalentsAndOtherMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:RealEstateInvestmentMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122so:SpecialSituationsInvestmentsMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:PrivateCreditMember2024-12-310000092122so:PrivateCreditMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122so:InfrastructureMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:FixedIncomeSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PrivateCreditMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PrivateCreditMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMemberso:InfrastructureMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:FixedIncomeSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PrivateCreditMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PrivateCreditMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PrivateCreditMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PrivateCreditMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:InfrastructureMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:InfrastructureMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:InfrastructureMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:InfrastructureMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:FixedIncomeSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:PrivateCreditMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:PrivateCreditMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:PrivateCreditMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:PrivateCreditMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:InfrastructureMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:InfrastructureMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:InfrastructureMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMemberso:InfrastructureMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:MississippiPowerMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:FixedIncomeSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:PrivateCreditMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:PrivateCreditMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:PrivateCreditMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:PrivateCreditMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:InfrastructureMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:InfrastructureMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:InfrastructureMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMemberso:InfrastructureMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernPowerMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:FixedIncomeSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PooledFundsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PrivateCreditMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PrivateCreditMember2024-12-310000092122us-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:InfrastructureMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:PensionPlansDefinedBenefitMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:DefinedBenefitPlanEquitySecuritiesMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:USStatesAndPoliticalSubdivisionsMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:ForeignGovernmentDebtSecuritiesMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:FixedIncomeSecuritiesMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PooledFundsMember2025-12-310000092122so:PooledFundsMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:CashEquivalentsAndOtherMember2025-12-310000092122so:CashEquivalentsAndOtherMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:TrustOwnedLifeInsuranceMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:TrustOwnedLifeInsuranceMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:TrustOwnedLifeInsuranceMember2025-12-310000092122so:TrustOwnedLifeInsuranceMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:RealEstateInvestmentMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122so:SpecialSituationsInvestmentsMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PrivateCreditMember2025-12-310000092122so:PrivateCreditMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:InfrastructureMember2025-12-310000092122so:InfrastructureMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:FixedIncomeSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:TrustOwnedLifeInsuranceMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:TrustOwnedLifeInsuranceMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:TrustOwnedLifeInsuranceMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:TrustOwnedLifeInsuranceMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:FixedIncomeSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:TrustOwnedLifeInsuranceMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:TrustOwnedLifeInsuranceMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:TrustOwnedLifeInsuranceMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:TrustOwnedLifeInsuranceMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:FixedIncomeSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:SpecialSituationsInvestmentsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:PrivateCreditMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:InfrastructureMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:FixedIncomeSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PooledFundsMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PooledFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:CashEquivalentsAndOtherMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:RealEstateInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:DefinedBenefitPlanEquitySecuritiesMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:USStatesAndPoliticalSubdivisionsMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:ForeignGovernmentDebtSecuritiesMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:FixedIncomeSecuritiesMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PooledFundsMember2024-12-310000092122so:PooledFundsMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:CashEquivalentsAndOtherMember2024-12-310000092122so:CashEquivalentsAndOtherMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:TrustOwnedLifeInsuranceMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:TrustOwnedLifeInsuranceMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:TrustOwnedLifeInsuranceMember2024-12-310000092122so:TrustOwnedLifeInsuranceMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:RealEstateInvestmentMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122so:SpecialSituationsInvestmentsMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:PrivateCreditMember2024-12-310000092122so:PrivateCreditMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122so:InfrastructureMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:FixedIncomeSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:TrustOwnedLifeInsuranceMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:TrustOwnedLifeInsuranceMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:TrustOwnedLifeInsuranceMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:TrustOwnedLifeInsuranceMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PrivateCreditMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:PrivateCreditMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMemberso:InfrastructureMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:FixedIncomeSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:TrustOwnedLifeInsuranceMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:TrustOwnedLifeInsuranceMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:TrustOwnedLifeInsuranceMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:TrustOwnedLifeInsuranceMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:FixedIncomeSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:SpecialSituationsInvestmentsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:PrivateCreditMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMemberso:InfrastructureMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:MississippiPowerMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:DefinedBenefitPlanEquitySecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USStatesAndPoliticalSubdivisionsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:ForeignGovernmentDebtSecuritiesMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:FixedIncomeSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PooledFundsMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:PooledFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberso:CashEquivalentsAndOtherMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:RealEstateInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMemberus-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:FairValueInputsLevel1Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:FairValueInputsLevel2Memberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberus-gaap:OtherPostretirementBenefitPlansDefinedBenefitMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:PerformanceSharesMember2025-01-012025-12-310000092122us-gaap:PerformanceSharesMember2025-12-310000092122us-gaap:PerformanceSharesMember2024-01-012024-12-310000092122us-gaap:PerformanceSharesMember2023-01-012023-12-310000092122so:EPSbasedandROEbasedPerformanceShareUnitsMember2025-01-012025-12-310000092122so:EPSbasedandROEbasedPerformanceShareUnitsMember2024-01-012024-12-310000092122so:EPSbasedandROEbasedPerformanceShareUnitsMember2023-01-012023-12-310000092122us-gaap:PerformanceSharesMember2024-12-310000092122us-gaap:PerformanceSharesMember2024-02-012024-02-290000092122us-gaap:PerformanceSharesMember2023-02-012023-02-280000092122us-gaap:PerformanceSharesMemberus-gaap:SubsequentEventMember2026-02-012026-02-280000092122us-gaap:RestrictedStockUnitsRSUMember2025-01-012025-12-310000092122us-gaap:RestrictedStockUnitsRSUMember2024-01-012024-12-310000092122us-gaap:RestrictedStockUnitsRSUMember2023-01-012023-12-310000092122us-gaap:RestrictedStockUnitsRSUMemberus-gaap:ShareBasedCompensationAwardTrancheOneMember2025-01-012025-12-310000092122us-gaap:RestrictedStockUnitsRSUMemberus-gaap:ShareBasedCompensationAwardTrancheTwoMember2025-01-012025-12-310000092122us-gaap:RestrictedStockUnitsRSUMemberus-gaap:ShareBasedCompensationAwardTrancheThreeMember2025-01-012025-12-310000092122us-gaap:RestrictedStockUnitsRSUMember2024-12-310000092122us-gaap:RestrictedStockUnitsRSUMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122us-gaap:EnergyRelatedDerivativeMember2025-12-310000092122us-gaap:InterestRateContractMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122us-gaap:InterestRateContractMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122us-gaap:InterestRateContractMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122us-gaap:InterestRateContractMember2025-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122us-gaap:ForeignExchangeContractMember2025-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122so:DomesticEquityMember2025-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122so:ForeignEquityMember2025-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122us-gaap:USTreasuryAndGovernmentMember2025-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122us-gaap:MunicipalBondsMember2025-12-310000092122us-gaap:FixedIncomeFundsMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122us-gaap:FixedIncomeFundsMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122us-gaap:FixedIncomeFundsMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122us-gaap:FixedIncomeFundsMember2025-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122us-gaap:CorporateDebtSecuritiesMember2025-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122us-gaap:AssetBackedSecuritiesMember2025-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:FairValueMeasuredAtNetAssetValuePerShareMember2025-12-310000092122us-gaap:PrivateEquityFundsMember2025-12-310000092122us-gaap:CashAndCashEquivalentsMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122us-gaap:CashAndCashEquivalentsMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122us-gaap:CashAndCashEquivalentsMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122us-gaap:CashAndCashEquivalentsMember2025-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueMeasuredAtNetAssetValuePerShareMember2025-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMember2025-12-310000092122us-gaap:FairValueInputsLevel1Member2025-12-310000092122us-gaap:FairValueInputsLevel2Member2025-12-310000092122us-gaap:FairValueInputsLevel3Member2025-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:AlabamaPowerMember2025-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2025-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2025-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2025-12-310000092122so:DomesticEquityMemberso:AlabamaPowerMember2025-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2025-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2025-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2025-12-310000092122so:ForeignEquityMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:USTreasuryAndGovernmentMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:MunicipalBondsMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:CorporateDebtSecuritiesMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:AssetBackedSecuritiesMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:PrivateEquityFundsMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2025-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberso:AlabamaPowerMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122so:AlabamaPowerMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122so:AlabamaPowerMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122so:AlabamaPowerMemberus-gaap:FairValueMeasuredAtNetAssetValuePerShareMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel1Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel2Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel3Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:GeorgiaPowerMember2025-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel1Memberso:GeorgiaPowerMember2025-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel2Memberso:GeorgiaPowerMember2025-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel3Memberso:GeorgiaPowerMember2025-12-310000092122so:DomesticEquityMemberso:GeorgiaPowerMember2025-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel1Memberso:GeorgiaPowerMember2025-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel2Memberso:GeorgiaPowerMember2025-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel3Memberso:GeorgiaPowerMember2025-12-310000092122so:ForeignEquityMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel1Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel2Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel3Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:USTreasuryAndGovernmentMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel1Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel2Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel3Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:MunicipalBondsMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel1Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel2Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel3Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:CorporateDebtSecuritiesMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel1Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel2Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel3Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:AssetBackedSecuritiesMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel1Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel2Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel3Memberso:GeorgiaPowerMember2025-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberso:GeorgiaPowerMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122so:GeorgiaPowerMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122so:GeorgiaPowerMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel1Memberso:MississippiPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel2Memberso:MississippiPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel3Memberso:MississippiPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:MississippiPowerMember2025-12-310000092122so:MississippiPowerMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122so:MississippiPowerMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122so:MississippiPowerMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel1Memberso:SouthernPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel2Memberso:SouthernPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel3Memberso:SouthernPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:SouthernPowerMember2025-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:FairValueInputsLevel1Memberso:SouthernPowerMember2025-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:FairValueInputsLevel2Memberso:SouthernPowerMember2025-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:FairValueInputsLevel3Memberso:SouthernPowerMember2025-12-310000092122us-gaap:ForeignExchangeContractMemberso:SouthernPowerMember2025-12-310000092122so:SouthernPowerMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122so:SouthernPowerMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122so:SouthernPowerMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel1Memberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel2Memberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel3Memberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:SouthernCompanyGasMember2025-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel1Memberso:SouthernCompanyGasMember2025-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel2Memberso:SouthernCompanyGasMember2025-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel3Memberso:SouthernCompanyGasMember2025-12-310000092122so:DomesticEquityMemberso:SouthernCompanyGasMember2025-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel1Memberso:SouthernCompanyGasMember2025-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel2Memberso:SouthernCompanyGasMember2025-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel3Memberso:SouthernCompanyGasMember2025-12-310000092122so:ForeignEquityMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:FixedIncomeFundsMemberus-gaap:FairValueInputsLevel1Memberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:FixedIncomeFundsMemberus-gaap:FairValueInputsLevel2Memberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:FixedIncomeFundsMemberus-gaap:FairValueInputsLevel3Memberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:FixedIncomeFundsMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:CashAndCashEquivalentsMemberus-gaap:FairValueInputsLevel1Memberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:CashAndCashEquivalentsMemberus-gaap:FairValueInputsLevel2Memberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:CashAndCashEquivalentsMemberus-gaap:FairValueInputsLevel3Memberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:CashAndCashEquivalentsMemberso:SouthernCompanyGasMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:FairValueInputsLevel1Member2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:FairValueInputsLevel2Member2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:FairValueInputsLevel3Member2025-12-310000092122us-gaap:InterestRateContractMemberus-gaap:FairValueInputsLevel1Memberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:InterestRateContractMemberus-gaap:FairValueInputsLevel2Memberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:InterestRateContractMemberus-gaap:FairValueInputsLevel3Memberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:InterestRateContractMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel1Member2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel2Member2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel3Member2024-12-310000092122us-gaap:EnergyRelatedDerivativeMember2024-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel1Member2024-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel2Member2024-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel3Member2024-12-310000092122so:DomesticEquityMember2024-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel1Member2024-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel2Member2024-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel3Member2024-12-310000092122so:ForeignEquityMember2024-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel1Member2024-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel2Member2024-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel3Member2024-12-310000092122us-gaap:USTreasuryAndGovernmentMember2024-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel1Member2024-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel2Member2024-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel3Member2024-12-310000092122us-gaap:MunicipalBondsMember2024-12-310000092122us-gaap:FixedIncomeFundsMemberus-gaap:FairValueInputsLevel1Member2024-12-310000092122us-gaap:FixedIncomeFundsMemberus-gaap:FairValueInputsLevel2Member2024-12-310000092122us-gaap:FixedIncomeFundsMemberus-gaap:FairValueInputsLevel3Member2024-12-310000092122us-gaap:FixedIncomeFundsMember2024-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel1Member2024-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel2Member2024-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel3Member2024-12-310000092122us-gaap:CorporateDebtSecuritiesMember2024-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel1Member2024-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel2Member2024-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel3Member2024-12-310000092122us-gaap:AssetBackedSecuritiesMember2024-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:FairValueInputsLevel1Member2024-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:FairValueInputsLevel2Member2024-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:FairValueInputsLevel3Member2024-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:FairValueMeasuredAtNetAssetValuePerShareMember2024-12-310000092122us-gaap:PrivateEquityFundsMember2024-12-310000092122us-gaap:CashAndCashEquivalentsMemberus-gaap:FairValueInputsLevel1Member2024-12-310000092122us-gaap:CashAndCashEquivalentsMemberus-gaap:FairValueInputsLevel2Member2024-12-310000092122us-gaap:CashAndCashEquivalentsMemberus-gaap:FairValueInputsLevel3Member2024-12-310000092122us-gaap:CashAndCashEquivalentsMember2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel1Member2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel2Member2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel3Member2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueMeasuredAtNetAssetValuePerShareMember2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMember2024-12-310000092122us-gaap:FairValueInputsLevel1Member2024-12-310000092122us-gaap:FairValueInputsLevel2Member2024-12-310000092122us-gaap:FairValueInputsLevel3Member2024-12-310000092122us-gaap:FairValueMeasuredAtNetAssetValuePerShareMember2024-12-310000092122us-gaap:InterestRateContractMemberus-gaap:FairValueInputsLevel1Member2024-12-310000092122us-gaap:InterestRateContractMemberus-gaap:FairValueInputsLevel2Member2024-12-310000092122us-gaap:InterestRateContractMemberus-gaap:FairValueInputsLevel3Member2024-12-310000092122us-gaap:InterestRateContractMember2024-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:FairValueInputsLevel1Member2024-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:FairValueInputsLevel2Member2024-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:FairValueInputsLevel3Member2024-12-310000092122us-gaap:ForeignExchangeContractMember2024-12-310000092122so:SouthernPowerMemberus-gaap:FairValueInputsLevel1Member2024-12-310000092122so:SouthernPowerMemberus-gaap:FairValueInputsLevel2Member2024-12-310000092122so:SouthernPowerMemberus-gaap:FairValueInputsLevel3Member2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:AlabamaPowerMember2024-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2024-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2024-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2024-12-310000092122so:DomesticEquityMemberso:AlabamaPowerMember2024-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2024-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2024-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2024-12-310000092122so:ForeignEquityMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:USTreasuryAndGovernmentMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:MunicipalBondsMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:CorporateDebtSecuritiesMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:AssetBackedSecuritiesMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:PrivateEquityFundsMemberus-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:PrivateEquityFundsMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel1Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel2Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel3Memberso:AlabamaPowerMember2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueMeasuredAtNetAssetValuePerShareMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberso:AlabamaPowerMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:FairValueInputsLevel1Member2024-12-310000092122so:AlabamaPowerMemberus-gaap:FairValueInputsLevel2Member2024-12-310000092122so:AlabamaPowerMemberus-gaap:FairValueInputsLevel3Member2024-12-310000092122so:AlabamaPowerMemberus-gaap:FairValueMeasuredAtNetAssetValuePerShareMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel1Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel2Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel3Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:GeorgiaPowerMember2024-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel1Memberso:GeorgiaPowerMember2024-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel2Memberso:GeorgiaPowerMember2024-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel3Memberso:GeorgiaPowerMember2024-12-310000092122so:DomesticEquityMemberso:GeorgiaPowerMember2024-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel1Memberso:GeorgiaPowerMember2024-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel2Memberso:GeorgiaPowerMember2024-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel3Memberso:GeorgiaPowerMember2024-12-310000092122so:ForeignEquityMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel1Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel2Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel3Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:USTreasuryAndGovernmentMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel1Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel2Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:MunicipalBondsMemberus-gaap:FairValueInputsLevel3Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:MunicipalBondsMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel1Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel2Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel3Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:CorporateDebtSecuritiesMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel1Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel2Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel3Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:AssetBackedSecuritiesMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel1Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel2Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel3Memberso:GeorgiaPowerMember2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberso:GeorgiaPowerMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:FairValueInputsLevel1Member2024-12-310000092122so:GeorgiaPowerMemberus-gaap:FairValueInputsLevel2Member2024-12-310000092122so:GeorgiaPowerMemberus-gaap:FairValueInputsLevel3Member2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel1Memberso:MississippiPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel2Memberso:MississippiPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel3Memberso:MississippiPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:MississippiPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel1Memberso:SouthernPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel2Memberso:SouthernPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel3Memberso:SouthernPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:SouthernPowerMember2024-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:FairValueInputsLevel1Memberso:SouthernPowerMember2024-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:FairValueInputsLevel2Memberso:SouthernPowerMember2024-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:FairValueInputsLevel3Memberso:SouthernPowerMember2024-12-310000092122us-gaap:ForeignExchangeContractMemberso:SouthernPowerMember2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel1Memberso:SouthernPowerMember2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel2Memberso:SouthernPowerMember2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberus-gaap:FairValueInputsLevel3Memberso:SouthernPowerMember2024-12-310000092122us-gaap:OtherThanSecuritiesInvestmentMemberso:SouthernPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel1Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel2Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:FairValueInputsLevel3Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:SouthernCompanyGasMember2024-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel1Memberso:SouthernCompanyGasMember2024-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel2Memberso:SouthernCompanyGasMember2024-12-310000092122so:DomesticEquityMemberus-gaap:FairValueInputsLevel3Memberso:SouthernCompanyGasMember2024-12-310000092122so:DomesticEquityMemberso:SouthernCompanyGasMember2024-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel1Memberso:SouthernCompanyGasMember2024-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel2Memberso:SouthernCompanyGasMember2024-12-310000092122so:ForeignEquityMemberus-gaap:FairValueInputsLevel3Memberso:SouthernCompanyGasMember2024-12-310000092122so:ForeignEquityMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:FixedIncomeFundsMemberus-gaap:FairValueInputsLevel1Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:FixedIncomeFundsMemberus-gaap:FairValueInputsLevel2Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:FixedIncomeFundsMemberus-gaap:FairValueInputsLevel3Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:FixedIncomeFundsMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:CashAndCashEquivalentsMemberus-gaap:FairValueInputsLevel1Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:CashAndCashEquivalentsMemberus-gaap:FairValueInputsLevel2Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:CashAndCashEquivalentsMemberus-gaap:FairValueInputsLevel3Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:CashAndCashEquivalentsMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel1Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel2Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:USTreasuryAndGovernmentMemberus-gaap:FairValueInputsLevel3Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:USTreasuryAndGovernmentMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel1Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel2Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:CorporateDebtSecuritiesMemberus-gaap:FairValueInputsLevel3Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:CorporateDebtSecuritiesMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel1Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel2Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:AssetBackedSecuritiesMemberus-gaap:FairValueInputsLevel3Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:AssetBackedSecuritiesMemberso:SouthernCompanyGasMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:FairValueInputsLevel1Member2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:FairValueInputsLevel2Member2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:FairValueInputsLevel3Member2024-12-310000092122us-gaap:InterestRateContractMemberus-gaap:FairValueInputsLevel2Memberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:InterestRateContractMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:CarryingReportedAmountFairValueDisclosureMember2025-12-310000092122us-gaap:CarryingReportedAmountFairValueDisclosureMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:CarryingReportedAmountFairValueDisclosureMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:CarryingReportedAmountFairValueDisclosureMemberso:MississippiPowerMember2025-12-310000092122us-gaap:CarryingReportedAmountFairValueDisclosureMemberso:SouthernPowerMember2025-12-310000092122us-gaap:CarryingReportedAmountFairValueDisclosureMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:EstimateOfFairValueFairValueDisclosureMember2025-12-310000092122us-gaap:EstimateOfFairValueFairValueDisclosureMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:EstimateOfFairValueFairValueDisclosureMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:EstimateOfFairValueFairValueDisclosureMemberso:MississippiPowerMember2025-12-310000092122us-gaap:EstimateOfFairValueFairValueDisclosureMemberso:SouthernPowerMember2025-12-310000092122us-gaap:EstimateOfFairValueFairValueDisclosureMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:CarryingReportedAmountFairValueDisclosureMember2024-12-310000092122us-gaap:CarryingReportedAmountFairValueDisclosureMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:CarryingReportedAmountFairValueDisclosureMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:CarryingReportedAmountFairValueDisclosureMemberso:MississippiPowerMember2024-12-310000092122us-gaap:CarryingReportedAmountFairValueDisclosureMemberso:SouthernPowerMember2024-12-310000092122us-gaap:CarryingReportedAmountFairValueDisclosureMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:EstimateOfFairValueFairValueDisclosureMember2024-12-310000092122us-gaap:EstimateOfFairValueFairValueDisclosureMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:EstimateOfFairValueFairValueDisclosureMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:EstimateOfFairValueFairValueDisclosureMemberso:MississippiPowerMember2024-12-310000092122us-gaap:EstimateOfFairValueFairValueDisclosureMemberso:SouthernPowerMember2024-12-310000092122us-gaap:EstimateOfFairValueFairValueDisclosureMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:PublicUtilitiesInventoryNaturalGasMember2025-12-310000092122us-gaap:PublicUtilitiesInventoryNaturalGasMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:PublicUtilitiesInventoryNaturalGasMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:PublicUtilitiesInventoryNaturalGasMemberso:MississippiPowerMember2025-12-310000092122us-gaap:PublicUtilitiesInventoryNaturalGasMemberso:SouthernPowerMember2025-12-310000092122us-gaap:PublicUtilitiesInventoryNaturalGasMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:PublicUtilitiesInventoryNaturalGasMemberus-gaap:NondesignatedMemberso:SouthernCompanyGasMemberus-gaap:LongMember2025-12-310000092122us-gaap:PublicUtilitiesInventoryNaturalGasMemberus-gaap:NondesignatedMemberso:SouthernCompanyGasMemberus-gaap:ShortMember2025-12-310000092122us-gaap:InterestRateContractMemberso:HedgingMaturityDateOneMemberso:FairValueHedgesOfExistingDebtMemberso:SouthernCompanyMember2025-12-310000092122us-gaap:InterestRateContractMemberso:HedgingMaturityDateOneMemberso:FairValueHedgesOfExistingDebtMemberso:SouthernCompanyMember2025-01-012025-12-310000092122us-gaap:InterestRateContractMemberso:HedgingMaturityDateTwoMemberso:FairValueHedgesOfExistingDebtMemberso:SouthernCompanyMember2025-12-310000092122us-gaap:InterestRateContractMemberso:HedgingMaturityDateTwoMemberso:FairValueHedgesOfExistingDebtMemberso:SouthernCompanyMember2025-01-012025-12-310000092122us-gaap:InterestRateContractMemberso:HedgingMaturityDateThreeMemberso:FairValueHedgesOfExistingDebtMemberso:SouthernCompanyMember2025-12-310000092122us-gaap:InterestRateContractMemberso:HedgingMaturityDateThreeMemberso:FairValueHedgesOfExistingDebtMemberso:SouthernCompanyMember2025-01-012025-12-310000092122us-gaap:InterestRateContractMemberso:FairValueHedgesOfExistingDebtMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:InterestRateContractMemberso:FairValueHedgesOfExistingDebtMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122us-gaap:InterestRateContractMember2025-12-310000092122so:TraditionalElectricOperatingCompaniesMember2025-12-310000092122us-gaap:ForeignExchangeContractMemberso:CashFlowHedgesOfExistingDebtMemberso:SouthernPowerMember2025-12-310000092122us-gaap:ForeignExchangeContractMemberso:CashFlowHedgesOfExistingDebtMemberso:SouthernPowerMember2025-01-012025-12-310000092122us-gaap:ForeignExchangeContractMemberso:HedgingMaturityDateTwoMemberso:CashFlowHedgesOfExistingDebtMemberso:SouthernPowerMember2025-12-310000092122us-gaap:ForeignExchangeContractMemberso:HedgingMaturityDateTwoMemberso:FairValueHedgesOfExistingDebtMemberso:SouthernCompanyMember2025-12-310000092122us-gaap:ForeignExchangeContractMemberso:HedgingMaturityDateTwoMemberso:FairValueHedgesOfExistingDebtMemberso:SouthernCompanyMember2025-01-012025-12-310000092122us-gaap:ForeignExchangeContractMemberso:CashFlowHedgesOfExistingDebtMemberso:SouthernCompanyMember2025-12-310000092122us-gaap:ForeignExchangeContractMemberso:CashFlowHedgesOfExistingDebtMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:AssetsFromRiskManagementActivitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:HedgingInstrumentsForRegulatoryPurposesMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:HedgingInstrumentsForRegulatoryPurposesMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:AssetsFromRiskManagementActivitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:HedgingInstrumentsForRegulatoryPurposesMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:HedgingInstrumentsForRegulatoryPurposesMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:HedgingInstrumentsForRegulatoryPurposesMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:HedgingInstrumentsForRegulatoryPurposesMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:HedgingInstrumentsForRegulatoryPurposesMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:HedgingInstrumentsForRegulatoryPurposesMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:HedgingInstrumentsForRegulatoryPurposesMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:HedgingInstrumentsForRegulatoryPurposesMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:AssetsFromRiskManagementActivitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:AssetsFromRiskManagementActivitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2024-12-310000092122us-gaap:InterestRateContractMemberso:AssetsFromRiskManagementActivitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2025-12-310000092122us-gaap:InterestRateContractMemberus-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2025-12-310000092122us-gaap:InterestRateContractMemberso:AssetsFromRiskManagementActivitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2024-12-310000092122us-gaap:InterestRateContractMemberus-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2024-12-310000092122us-gaap:InterestRateContractMemberso:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2025-12-310000092122us-gaap:InterestRateContractMemberso:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2025-12-310000092122us-gaap:InterestRateContractMemberso:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2024-12-310000092122us-gaap:InterestRateContractMemberso:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2024-12-310000092122us-gaap:ForeignExchangeContractMemberso:AssetsFromRiskManagementActivitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2025-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2025-12-310000092122us-gaap:ForeignExchangeContractMemberso:AssetsFromRiskManagementActivitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2024-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2024-12-310000092122us-gaap:ForeignExchangeContractMemberso:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2025-12-310000092122us-gaap:ForeignExchangeContractMemberso:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2025-12-310000092122us-gaap:ForeignExchangeContractMemberso:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2024-12-310000092122us-gaap:ForeignExchangeContractMemberso:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMember2024-12-310000092122so:CashFlowAndFairValueHedgingMemberus-gaap:DesignatedAsHedgingInstrumentMember2025-12-310000092122so:CashFlowAndFairValueHedgingMemberus-gaap:DesignatedAsHedgingInstrumentMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:AssetsFromRiskManagementActivitiesMemberus-gaap:NondesignatedMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:OtherCurrentLiabilitiesMemberus-gaap:NondesignatedMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:AssetsFromRiskManagementActivitiesMemberus-gaap:NondesignatedMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:OtherCurrentLiabilitiesMemberus-gaap:NondesignatedMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherDeferredChargesAndAssetsMemberus-gaap:NondesignatedMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:NondesignatedMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherDeferredChargesAndAssetsMemberus-gaap:NondesignatedMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:NondesignatedMember2024-12-310000092122us-gaap:NondesignatedMember2025-12-310000092122us-gaap:NondesignatedMember2024-12-310000092122us-gaap:OtherCurrentAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:OtherCurrentAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:AlabamaPowerMember2024-12-310000092122so:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:AlabamaPowerMember2025-12-310000092122so:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:AlabamaPowerMember2025-12-310000092122so:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:AlabamaPowerMember2024-12-310000092122so:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:DesignatedAsHedgingInstrumentMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:DesignatedAsHedgingInstrumentMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:OtherCurrentAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:OtherCurrentAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:GeorgiaPowerMember2024-12-310000092122so:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:GeorgiaPowerMember2025-12-310000092122so:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:GeorgiaPowerMember2025-12-310000092122so:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:GeorgiaPowerMember2024-12-310000092122so:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:DesignatedAsHedgingInstrumentMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:DesignatedAsHedgingInstrumentMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:OtherCurrentAssetsMemberus-gaap:NondesignatedMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:OtherCurrentLiabilitiesMemberus-gaap:NondesignatedMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:OtherCurrentAssetsMemberus-gaap:NondesignatedMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:OtherCurrentLiabilitiesMemberus-gaap:NondesignatedMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:OtherCurrentAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:MississippiPowerMember2025-12-310000092122us-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:MississippiPowerMember2025-12-310000092122us-gaap:OtherCurrentAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:MississippiPowerMember2024-12-310000092122us-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:MississippiPowerMember2024-12-310000092122so:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:MississippiPowerMember2025-12-310000092122so:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:MississippiPowerMember2025-12-310000092122so:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:MississippiPowerMember2024-12-310000092122so:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:MississippiPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:MississippiPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:MississippiPowerMember2024-12-310000092122us-gaap:OtherCurrentAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2025-12-310000092122us-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2025-12-310000092122us-gaap:OtherCurrentAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2024-12-310000092122us-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2024-12-310000092122so:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2025-12-310000092122so:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2025-12-310000092122so:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2024-12-310000092122so:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2024-12-310000092122us-gaap:OtherCurrentAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:ForeignExchangeContractMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2025-12-310000092122us-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:ForeignExchangeContractMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2025-12-310000092122us-gaap:OtherCurrentAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:ForeignExchangeContractMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2024-12-310000092122us-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:ForeignExchangeContractMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2024-12-310000092122so:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:ForeignExchangeContractMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2025-12-310000092122so:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:ForeignExchangeContractMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2025-12-310000092122so:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:ForeignExchangeContractMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2024-12-310000092122so:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:ForeignExchangeContractMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2024-12-310000092122us-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2025-12-310000092122us-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMemberso:SouthernPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:OtherCurrentAssetsMemberus-gaap:NondesignatedMemberso:SouthernPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:OtherCurrentLiabilitiesMemberus-gaap:NondesignatedMemberso:SouthernPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:OtherCurrentAssetsMemberus-gaap:NondesignatedMemberso:SouthernPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:OtherCurrentLiabilitiesMemberus-gaap:NondesignatedMemberso:SouthernPowerMember2024-12-310000092122so:AssetsFromRiskManagementActivitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:SouthernCompanyGasMember2025-12-310000092122so:AssetsFromRiskManagementActivitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:SouthernCompanyGasMember2024-12-310000092122so:AssetsFromRiskManagementActivitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:CashFlowAndFairValueHedgingMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:CashFlowAndFairValueHedgingMemberso:SouthernCompanyGasMember2025-12-310000092122so:AssetsFromRiskManagementActivitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:CashFlowAndFairValueHedgingMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:CashFlowAndFairValueHedgingMemberso:SouthernCompanyGasMember2024-12-310000092122so:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:SouthernCompanyGasMember2025-12-310000092122so:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:SouthernCompanyGasMember2025-12-310000092122so:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:SouthernCompanyGasMember2024-12-310000092122so:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:EnergyRelatedDerivativeMemberso:HedgingInstrumentsForRegulatoryPurposesMemberso:SouthernCompanyGasMember2024-12-310000092122so:AssetsFromRiskManagementActivitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:InterestRateContractMemberso:CashFlowAndFairValueHedgingMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:InterestRateContractMemberso:CashFlowAndFairValueHedgingMemberso:SouthernCompanyGasMember2025-12-310000092122so:AssetsFromRiskManagementActivitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:InterestRateContractMemberso:CashFlowAndFairValueHedgingMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:OtherCurrentLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:InterestRateContractMemberso:CashFlowAndFairValueHedgingMemberso:SouthernCompanyGasMember2024-12-310000092122so:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:InterestRateContractMemberso:CashFlowAndFairValueHedgingMemberso:SouthernCompanyGasMember2025-12-310000092122so:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:InterestRateContractMemberso:CashFlowAndFairValueHedgingMemberso:SouthernCompanyGasMember2025-12-310000092122so:OtherDeferredChargesAndAssetsMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:InterestRateContractMemberso:CashFlowAndFairValueHedgingMemberso:SouthernCompanyGasMember2024-12-310000092122so:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:DesignatedAsHedgingInstrumentMemberus-gaap:InterestRateContractMemberso:CashFlowAndFairValueHedgingMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:DesignatedAsHedgingInstrumentMemberso:CashFlowAndFairValueHedgingMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:AssetsFromRiskManagementActivitiesMemberus-gaap:NondesignatedMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:OtherCurrentLiabilitiesMemberus-gaap:NondesignatedMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:AssetsFromRiskManagementActivitiesMemberus-gaap:NondesignatedMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:OtherCurrentLiabilitiesMemberus-gaap:NondesignatedMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherDeferredChargesAndAssetsMemberus-gaap:NondesignatedMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:NondesignatedMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherDeferredChargesAndAssetsMemberus-gaap:NondesignatedMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherDeferredCreditsAndLiabilitiesMemberus-gaap:NondesignatedMemberso:SouthernCompanyGasMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:NondesignatedMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:NondesignatedMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsCurrentMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsCurrentMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsCurrentMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsCurrentMemberso:MississippiPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsCurrentMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsDeferredMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsDeferredMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsDeferredMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsDeferredMemberso:MississippiPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsDeferredMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesCurrentMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesCurrentMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesCurrentMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesCurrentMemberso:MississippiPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesCurrentMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesDeferredMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesDeferredMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesDeferredMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesDeferredMemberso:MississippiPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesDeferredMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:AlabamaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:GeorgiaPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:MississippiPowerMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsCurrentMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsCurrentMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsCurrentMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsCurrentMemberso:MississippiPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsCurrentMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsDeferredMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsDeferredMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsDeferredMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsDeferredMemberso:MississippiPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryAssetsDeferredMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesCurrentMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesCurrentMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesCurrentMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesCurrentMemberso:MississippiPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesCurrentMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesDeferredMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesDeferredMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesDeferredMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesDeferredMemberso:MississippiPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:OtherRegulatoryLiabilitiesDeferredMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:AlabamaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:GeorgiaPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:MississippiPowerMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMember2025-01-012025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMember2024-01-012024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMember2023-01-012023-12-310000092122us-gaap:InterestRateContractMemberus-gaap:CashFlowHedgingMember2025-01-012025-12-310000092122us-gaap:InterestRateContractMemberus-gaap:CashFlowHedgingMember2024-01-012024-12-310000092122us-gaap:InterestRateContractMemberus-gaap:CashFlowHedgingMember2023-01-012023-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMember2025-01-012025-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMember2024-01-012024-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMember2023-01-012023-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:FairValueHedgingMember2025-01-012025-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:FairValueHedgingMember2024-01-012024-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:FairValueHedgingMember2023-01-012023-12-310000092122us-gaap:CashFlowHedgingMemberso:GeorgiaPowerMember2025-01-012025-12-310000092122us-gaap:CashFlowHedgingMemberso:GeorgiaPowerMember2024-01-012024-12-310000092122us-gaap:CashFlowHedgingMemberso:GeorgiaPowerMember2023-01-012023-12-310000092122us-gaap:CashFlowHedgingMemberso:MississippiPowerMember2025-01-012025-12-310000092122us-gaap:CashFlowHedgingMemberso:MississippiPowerMember2024-01-012024-12-310000092122us-gaap:CashFlowHedgingMemberso:MississippiPowerMember2023-01-012023-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberso:SouthernPowerMember2025-01-012025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberso:SouthernPowerMember2024-01-012024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberso:SouthernPowerMember2023-01-012023-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberso:SouthernPowerMember2025-01-012025-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberso:SouthernPowerMember2024-01-012024-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberso:SouthernPowerMember2023-01-012023-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122us-gaap:InterestRateContractMemberus-gaap:CashFlowHedgingMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122us-gaap:InterestRateContractMemberus-gaap:CashFlowHedgingMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122us-gaap:InterestRateContractMemberus-gaap:CashFlowHedgingMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberso:DepreciationandAmortizationMember2025-01-012025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberso:DepreciationandAmortizationMember2024-01-012024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberso:DepreciationandAmortizationMember2023-01-012023-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberus-gaap:CostOfSalesMember2025-01-012025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberus-gaap:CostOfSalesMember2024-01-012024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberus-gaap:CostOfSalesMember2023-01-012023-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberus-gaap:OperatingExpenseMember2025-01-012025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberus-gaap:OperatingExpenseMember2024-01-012024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberus-gaap:OperatingExpenseMember2023-01-012023-12-310000092122us-gaap:InterestRateContractMemberus-gaap:CashFlowHedgingMemberus-gaap:InterestExpenseMember2025-01-012025-12-310000092122us-gaap:InterestRateContractMemberus-gaap:CashFlowHedgingMemberus-gaap:InterestExpenseMember2024-01-012024-12-310000092122us-gaap:InterestRateContractMemberus-gaap:CashFlowHedgingMemberus-gaap:InterestExpenseMember2023-01-012023-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberus-gaap:InterestExpenseMember2025-01-012025-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberus-gaap:InterestExpenseMember2024-01-012024-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberus-gaap:InterestExpenseMember2023-01-012023-12-310000092122us-gaap:InterestRateContractMemberus-gaap:FairValueHedgingMemberus-gaap:InterestExpenseMember2025-01-012025-12-310000092122us-gaap:InterestRateContractMemberus-gaap:FairValueHedgingMemberus-gaap:InterestExpenseMember2024-01-012024-12-310000092122us-gaap:InterestRateContractMemberus-gaap:FairValueHedgingMemberus-gaap:InterestExpenseMember2023-01-012023-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberus-gaap:OtherNonoperatingIncomeExpenseMember2025-01-012025-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberus-gaap:OtherNonoperatingIncomeExpenseMember2024-01-012024-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberus-gaap:OtherNonoperatingIncomeExpenseMember2023-01-012023-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberso:DepreciationandAmortizationMemberso:SouthernPowerMember2025-01-012025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberso:DepreciationandAmortizationMemberso:SouthernPowerMember2024-01-012024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberso:DepreciationandAmortizationMemberso:SouthernPowerMember2023-01-012023-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberus-gaap:InterestExpenseMemberso:SouthernPowerMember2025-01-012025-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberus-gaap:InterestExpenseMemberso:SouthernPowerMember2024-01-012024-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberus-gaap:InterestExpenseMemberso:SouthernPowerMember2023-01-012023-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberus-gaap:OtherNonoperatingIncomeExpenseMemberso:SouthernPowerMember2025-01-012025-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberus-gaap:OtherNonoperatingIncomeExpenseMemberso:SouthernPowerMember2024-01-012024-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberus-gaap:OtherNonoperatingIncomeExpenseMemberso:SouthernPowerMember2023-01-012023-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberus-gaap:OtherNonoperatingIncomeExpenseMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberus-gaap:OtherNonoperatingIncomeExpenseMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122us-gaap:ForeignExchangeContractMemberus-gaap:CashFlowHedgingMemberus-gaap:OtherNonoperatingIncomeExpenseMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberus-gaap:OperatingExpenseMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberus-gaap:OperatingExpenseMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:CashFlowHedgingMemberus-gaap:OperatingExpenseMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122us-gaap:InterestRateContractMemberus-gaap:CashFlowHedgingMemberus-gaap:InterestExpenseMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122us-gaap:InterestRateContractMemberus-gaap:CashFlowHedgingMemberus-gaap:InterestExpenseMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122us-gaap:InterestRateContractMemberus-gaap:CashFlowHedgingMemberus-gaap:InterestExpenseMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122us-gaap:InterestRateContractMemberus-gaap:FairValueHedgingMemberus-gaap:InterestExpenseMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122us-gaap:InterestRateContractMemberus-gaap:FairValueHedgingMemberus-gaap:InterestExpenseMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122us-gaap:InterestRateContractMemberus-gaap:FairValueHedgingMemberus-gaap:InterestExpenseMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122us-gaap:FairValueHedgingMemberus-gaap:LongTermDebtMember2025-12-310000092122us-gaap:FairValueHedgingMemberus-gaap:LongTermDebtMember2024-12-310000092122us-gaap:LongTermDebtMemberus-gaap:FairValueHedgingMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:LongTermDebtMemberus-gaap:FairValueHedgingMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:NondesignatedMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:NondesignatedMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122us-gaap:EnergyRelatedDerivativeMemberus-gaap:NondesignatedMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:RegistrantsMemberso:DerivativeCounterpartiesMember2025-12-310000092122us-gaap:InterestRateContractMemberso:SouthernPowerMember2025-12-310000092122so:TenaskaAlabamaPartnersL.P.Memberso:AlabamaPowerMember2025-09-302025-09-300000092122so:TenaskaAlabamaPartnersL.P.Memberso:AlabamaPowerMember2025-09-300000092122so:SouthCheyenneSolarFacilityAndMillersBranchSolarDevelopmentMemberso:SouthernPowerMember2024-01-012024-12-310000092122so:SouthCheyenneSolarFacilityMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:MillersBranchSolarDevelopmentMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:MillersBranchSolarDevelopmentMemberso:SouthernPowerMember2025-12-310000092122so:MillersBranchSolarDevelopmentPhase1Memberso:SouthernPowerMemberus-gaap:SubsequentEventMember2026-02-012026-02-180000092122so:WindFacilitiesMemberso:SouthernPowerMember2025-12-310000092122so:KayWindFacilityMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:GrantPlainsFacilityMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:GrantWindFacilityMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:WakeWindFacilityMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:BethelWindFacilityMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:KayWindFacilityMembersrt:MaximumMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:SouthernPowerMember2025-12-312025-12-310000092122us-gaap:OperatingSegmentsMemberso:TraditionalElectricOperatingCompaniesMember2025-01-012025-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernPowerMember2025-01-012025-12-310000092122us-gaap:IntersegmentEliminationMemberso:TraditionalElectricOperatingCompaniesAndSouthernPowerMember2025-01-012025-12-310000092122us-gaap:OperatingSegmentsMemberso:TraditionalElectricOperatingCompaniesAndSouthernPowerMember2025-01-012025-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122us-gaap:OperatingSegmentsMember2025-01-012025-12-310000092122us-gaap:CorporateNonSegmentMember2025-01-012025-12-310000092122us-gaap:IntersegmentEliminationMember2025-01-012025-12-310000092122us-gaap:OperatingSegmentsMemberso:TraditionalElectricOperatingCompaniesMember2025-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernPowerMember2025-12-310000092122us-gaap:IntersegmentEliminationMemberso:TraditionalElectricOperatingCompaniesAndSouthernPowerMember2025-12-310000092122us-gaap:OperatingSegmentsMemberso:TraditionalElectricOperatingCompaniesAndSouthernPowerMember2025-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:OperatingSegmentsMember2025-12-310000092122us-gaap:CorporateNonSegmentMember2025-12-310000092122us-gaap:IntersegmentEliminationMember2025-12-310000092122us-gaap:OperatingSegmentsMemberso:TraditionalElectricOperatingCompaniesMember2024-01-012024-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernPowerMember2024-01-012024-12-310000092122us-gaap:IntersegmentEliminationMemberso:TraditionalElectricOperatingCompaniesAndSouthernPowerMember2024-01-012024-12-310000092122us-gaap:OperatingSegmentsMemberso:TraditionalElectricOperatingCompaniesAndSouthernPowerMember2024-01-012024-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122us-gaap:OperatingSegmentsMember2024-01-012024-12-310000092122us-gaap:CorporateNonSegmentMember2024-01-012024-12-310000092122us-gaap:IntersegmentEliminationMember2024-01-012024-12-310000092122us-gaap:OperatingSegmentsMemberso:TraditionalElectricOperatingCompaniesMember2024-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernPowerMember2024-12-310000092122us-gaap:IntersegmentEliminationMemberso:TraditionalElectricOperatingCompaniesAndSouthernPowerMember2024-12-310000092122us-gaap:OperatingSegmentsMemberso:TraditionalElectricOperatingCompaniesAndSouthernPowerMember2024-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:OperatingSegmentsMember2024-12-310000092122us-gaap:CorporateNonSegmentMember2024-12-310000092122us-gaap:IntersegmentEliminationMember2024-12-310000092122us-gaap:OperatingSegmentsMemberso:TraditionalElectricOperatingCompaniesMember2023-01-012023-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernPowerMember2023-01-012023-12-310000092122us-gaap:IntersegmentEliminationMemberso:TraditionalElectricOperatingCompaniesAndSouthernPowerMember2023-01-012023-12-310000092122us-gaap:OperatingSegmentsMemberso:TraditionalElectricOperatingCompaniesAndSouthernPowerMember2023-01-012023-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122us-gaap:OperatingSegmentsMember2023-01-012023-12-310000092122us-gaap:CorporateNonSegmentMember2023-01-012023-12-310000092122us-gaap:IntersegmentEliminationMember2023-01-012023-12-310000092122us-gaap:OperatingSegmentsMemberso:TraditionalElectricOperatingCompaniesMember2023-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernPowerMember2023-12-310000092122us-gaap:IntersegmentEliminationMemberso:TraditionalElectricOperatingCompaniesAndSouthernPowerMember2023-12-310000092122us-gaap:OperatingSegmentsMemberso:TraditionalElectricOperatingCompaniesAndSouthernPowerMember2023-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMember2023-12-310000092122us-gaap:OperatingSegmentsMember2023-12-310000092122us-gaap:CorporateNonSegmentMember2023-12-310000092122us-gaap:IntersegmentEliminationMember2023-12-310000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMemberso:TraditionalElectricOperatingCompaniesMember2025-01-012025-12-310000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMemberso:TraditionalElectricOperatingCompaniesMember2024-01-012024-12-310000092122so:PlantVogtleUnits3And4Memberso:GeorgiaPowerMemberso:TraditionalElectricOperatingCompaniesMember2023-01-012023-12-310000092122us-gaap:DisposalGroupDisposedOfBySaleNotDiscontinuedOperationsMemberso:SparePartsMemberso:SouthernPowerMember2025-01-012025-12-310000092122so:RetailElectricMemberso:ElectricUtilitiesMember2025-01-012025-12-310000092122so:WholesaleElectricMemberso:ElectricUtilitiesMember2025-01-012025-12-310000092122so:OtherRevenueMemberso:ElectricUtilitiesMember2025-01-012025-12-310000092122so:ElectricUtilitiesMember2025-01-012025-12-310000092122so:RetailElectricMemberso:ElectricUtilitiesMember2024-01-012024-12-310000092122so:WholesaleElectricMemberso:ElectricUtilitiesMember2024-01-012024-12-310000092122so:OtherRevenueMemberso:ElectricUtilitiesMember2024-01-012024-12-310000092122so:ElectricUtilitiesMember2024-01-012024-12-310000092122so:RetailElectricMemberso:ElectricUtilitiesMember2023-01-012023-12-310000092122so:WholesaleElectricMemberso:ElectricUtilitiesMember2023-01-012023-12-310000092122so:OtherRevenueMemberso:ElectricUtilitiesMember2023-01-012023-12-310000092122so:ElectricUtilitiesMember2023-01-012023-12-310000092122so:GasDistributionOperationsMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:GasMarketingServicesMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:OtherGasRevenueMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122so:SouthernCompanyGasMember2025-01-012025-12-310000092122so:GasDistributionOperationsMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:GasMarketingServicesMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:OtherGasRevenueMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122so:SouthernCompanyGasMember2024-01-012024-12-310000092122so:GasDistributionOperationsMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:GasMarketingServicesMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:OtherGasRevenueMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122so:SouthernCompanyGasMember2023-01-012023-12-310000092122so:AlabamaPowerMemberso:ReportableSegmentMember2025-01-012025-12-310000092122so:AlabamaPowerMemberso:ReportableSegmentMember2024-01-012024-12-310000092122so:AlabamaPowerMemberso:ReportableSegmentMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberso:ReportableSegmentMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberso:ReportableSegmentMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberso:ReportableSegmentMember2023-01-012023-12-310000092122so:MississippiPowerMemberso:ReportableSegmentMember2025-01-012025-12-310000092122so:MississippiPowerMemberso:ReportableSegmentMember2024-01-012024-12-310000092122so:MississippiPowerMemberso:ReportableSegmentMember2023-01-012023-12-310000092122so:SouthernPowerMemberso:ReportableSegmentMember2025-01-012025-12-310000092122so:SouthernPowerMemberso:ReportableSegmentMember2024-01-012024-12-310000092122so:SouthernPowerMemberso:ReportableSegmentMember2023-01-012023-12-310000092122so:SouthernNaturalGasCompanyLLCMemberso:SouthernCompanyGasMember2025-12-310000092122so:DaltonPipelineMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasPipelineInvestmentsMember2025-01-012025-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasMarketingServicesMember2025-01-012025-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122us-gaap:CorporateNonSegmentMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122us-gaap:IntersegmentEliminationMemberso:SouthernCompanyGasMember2025-01-012025-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasDistributionOperationsMember2025-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasPipelineInvestmentsMember2025-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasMarketingServicesMember2025-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:CorporateNonSegmentMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:IntersegmentEliminationMemberso:SouthernCompanyGasMember2025-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasDistributionOperationsMember2024-01-012024-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasPipelineInvestmentsMember2024-01-012024-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasMarketingServicesMember2024-01-012024-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122us-gaap:CorporateNonSegmentMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122us-gaap:IntersegmentEliminationMemberso:SouthernCompanyGasMember2024-01-012024-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasDistributionOperationsMember2024-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasPipelineInvestmentsMember2024-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasMarketingServicesMember2024-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:CorporateNonSegmentMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:IntersegmentEliminationMemberso:SouthernCompanyGasMember2024-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasDistributionOperationsMember2023-01-012023-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasPipelineInvestmentsMember2023-01-012023-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasMarketingServicesMember2023-01-012023-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122us-gaap:CorporateNonSegmentMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122us-gaap:IntersegmentEliminationMemberso:SouthernCompanyGasMember2023-01-012023-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasDistributionOperationsMember2023-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasPipelineInvestmentsMember2023-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMemberso:GasMarketingServicesMember2023-12-310000092122us-gaap:OperatingSegmentsMemberso:SouthernCompanyGasMember2023-12-310000092122us-gaap:CorporateNonSegmentMemberso:SouthernCompanyGasMember2023-12-310000092122us-gaap:IntersegmentEliminationMemberso:SouthernCompanyGasMember2023-12-3100000921222025-10-012025-12-310000092122so:StanleyW.ConnallyJr.Member2025-10-012025-12-310000092122so:StanleyW.ConnallyJr.Member2025-12-310000092122so:ChristopherCummiskeyMember2025-10-012025-12-310000092122so:ChristopherCummiskeyMember2025-12-310000092122so:MatthewM.KimMember2025-10-012025-12-310000092122so:MatthewM.KimMember2025-12-310000092122so:SterlingA.SpainhourMember2025-10-012025-12-310000092122so:SterlingA.SpainhourMember2025-12-310000092122so:KimberlyS.GreeneMember2025-10-012025-12-310000092122so:KimberlyS.GreeneMember2025-12-310000092122so:SouthernNaturalGasCompanyLLCMember2025-01-012025-12-310000092122us-gaap:AllowanceForCreditLossMember2024-12-310000092122us-gaap:AllowanceForCreditLossMember2025-01-012025-12-310000092122us-gaap:AllowanceForCreditLossMember2025-12-310000092122us-gaap:AllowanceForCreditLossMember2023-12-310000092122us-gaap:AllowanceForCreditLossMember2024-01-012024-12-310000092122us-gaap:AllowanceForCreditLossMember2022-12-310000092122us-gaap:AllowanceForCreditLossMember2023-01-012023-12-310000092122so:AlabamaPowerMemberus-gaap:AllowanceForCreditLossMember2024-12-310000092122so:AlabamaPowerMemberus-gaap:AllowanceForCreditLossMember2025-01-012025-12-310000092122so:AlabamaPowerMemberus-gaap:AllowanceForCreditLossMember2025-12-310000092122so:AlabamaPowerMemberus-gaap:AllowanceForCreditLossMember2023-12-310000092122so:AlabamaPowerMemberus-gaap:AllowanceForCreditLossMember2024-01-012024-12-310000092122so:AlabamaPowerMemberus-gaap:AllowanceForCreditLossMember2022-12-310000092122so:AlabamaPowerMemberus-gaap:AllowanceForCreditLossMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberus-gaap:AllowanceForCreditLossMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:AllowanceForCreditLossMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberus-gaap:AllowanceForCreditLossMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:AllowanceForCreditLossMember2023-12-310000092122so:GeorgiaPowerMemberus-gaap:AllowanceForCreditLossMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberus-gaap:AllowanceForCreditLossMember2022-12-310000092122so:GeorgiaPowerMemberus-gaap:AllowanceForCreditLossMember2023-01-012023-12-310000092122so:MississippiPowerMemberus-gaap:AllowanceForCreditLossMember2024-12-310000092122so:MississippiPowerMemberus-gaap:AllowanceForCreditLossMember2025-01-012025-12-310000092122so:MississippiPowerMemberus-gaap:AllowanceForCreditLossMember2025-12-310000092122so:MississippiPowerMemberus-gaap:AllowanceForCreditLossMember2023-12-310000092122so:MississippiPowerMemberus-gaap:AllowanceForCreditLossMember2024-01-012024-12-310000092122so:MississippiPowerMemberus-gaap:AllowanceForCreditLossMember2022-12-310000092122so:MississippiPowerMemberus-gaap:AllowanceForCreditLossMember2023-01-012023-12-310000092122so:SouthernPowerMemberus-gaap:AllowanceForCreditLossMember2024-12-310000092122so:SouthernPowerMemberus-gaap:AllowanceForCreditLossMember2025-01-012025-12-310000092122so:SouthernPowerMemberus-gaap:AllowanceForCreditLossMember2025-12-310000092122so:SouthernPowerMemberus-gaap:AllowanceForCreditLossMember2023-12-310000092122so:SouthernPowerMemberus-gaap:AllowanceForCreditLossMember2024-01-012024-12-310000092122so:SouthernPowerMemberus-gaap:AllowanceForCreditLossMember2022-12-310000092122so:SouthernPowerMemberus-gaap:AllowanceForCreditLossMember2023-01-012023-12-310000092122so:SouthernCompanyGasMemberus-gaap:AllowanceForCreditLossMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:AllowanceForCreditLossMember2025-01-012025-12-310000092122so:SouthernCompanyGasMemberus-gaap:AllowanceForCreditLossMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:AllowanceForCreditLossMember2023-12-310000092122so:SouthernCompanyGasMemberus-gaap:AllowanceForCreditLossMember2024-01-012024-12-310000092122so:SouthernCompanyGasMemberus-gaap:AllowanceForCreditLossMember2022-12-310000092122so:SouthernCompanyGasMemberus-gaap:AllowanceForCreditLossMember2023-01-012023-12-310000092122us-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2024-12-310000092122us-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2025-01-012025-12-310000092122us-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2025-12-310000092122us-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2023-12-310000092122us-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2024-01-012024-12-310000092122us-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2022-12-310000092122us-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2023-01-012023-12-310000092122so:GeorgiaPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2024-12-310000092122so:GeorgiaPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2025-01-012025-12-310000092122so:GeorgiaPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2025-12-310000092122so:GeorgiaPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2023-12-310000092122so:GeorgiaPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2024-01-012024-12-310000092122so:GeorgiaPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2022-12-310000092122so:GeorgiaPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2023-01-012023-12-310000092122so:MississippiPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2024-12-310000092122so:MississippiPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2025-01-012025-12-310000092122so:MississippiPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2025-12-310000092122so:MississippiPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2023-12-310000092122so:MississippiPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2024-01-012024-12-310000092122so:MississippiPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2022-12-310000092122so:MississippiPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2023-01-012023-12-310000092122so:SouthernPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2024-12-310000092122so:SouthernPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2025-01-012025-12-310000092122so:SouthernPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2025-12-310000092122so:SouthernPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2023-12-310000092122so:SouthernPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2024-01-012024-12-310000092122so:SouthernPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2022-12-310000092122so:SouthernPowerMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2023-01-012023-12-310000092122so:SouthernCompanyGasMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2024-12-310000092122so:SouthernCompanyGasMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2025-01-012025-12-310000092122so:SouthernCompanyGasMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2025-12-310000092122so:SouthernCompanyGasMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2023-12-310000092122so:SouthernCompanyGasMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2024-01-012024-12-310000092122so:SouthernCompanyGasMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2022-12-310000092122so:SouthernCompanyGasMemberus-gaap:ValuationAllowanceOfDeferredTaxAssetsMember2023-01-012023-12-31
    Table of Contents                                Index to Financial Statements
UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
FORM 10-K
ANNUAL REPORT PURSUANT TO SECTION 13 OR 15(d)
OF THE SECURITIES EXCHANGE ACT OF 1934
For the Fiscal Year Ended December 31, 2025
OR
TRANSITION REPORT PURSUANT TO SECTION 13 OR 15(d)
OF THE SECURITIES EXCHANGE ACT OF 1934
For the Transition Period from            to           
Commission
File Number
Registrant,
State of Incorporation,
Address and Telephone Number
I.R.S. Employer
Identification No.
1-3526The Southern Company58-0690070
(A Delaware Corporation)
30 Ivan Allen Jr. Boulevard, N.W.
Atlanta, Georgia 30308
(404) 506-5000
1-3164Alabama Power Company63-0004250
(An Alabama Corporation)
600 North 18th Street
Birmingham, Alabama 35203
(205) 257-1000
1-6468Georgia Power Company58-0257110
(A Georgia Corporation)
241 Ralph McGill Boulevard, N.E.
Atlanta, Georgia 30308
(404) 506-6526
001-11229Mississippi Power Company64-0205820
(A Mississippi Corporation)
2992 West Beach Boulevard
Gulfport, Mississippi 39501
(228) 864-1211
001-37803Southern Power Company58-2598670
(A Delaware Corporation)
30 Ivan Allen Jr. Boulevard, N.W.
Atlanta, Georgia 30308
(404) 506-5000
1-14174Southern Company Gas58-2210952
(A Georgia Corporation)
Ten Peachtree Place, N.E.
Atlanta, Georgia 30309
(404) 584-4000


    Table of Contents                                Index to Financial Statements
Securities registered pursuant to Section 12(b) of the Act:
RegistrantTitle of Each ClassTrading
Symbol(s)
Name of Each Exchange
on Which Registered
The Southern CompanyCommon Stock, par value $5 per shareSONew York Stock Exchange
(NYSE)
The Southern CompanySeries 2017B 5.25% Junior Subordinated Notes due 2077SOJCNYSE
The Southern CompanySeries 2020A 4.95% Junior Subordinated Notes due 2080SOJDNYSE
The Southern CompanySeries 2020C 4.20% Junior Subordinated Notes due 2060SOJENYSE
The Southern CompanySeries 2021B 1.875% Fixed-to-Fixed Reset Rate Junior Subordinated Notes due 2081SO 81NYSE
The Southern Company
Series 2025A 6.50% Junior Subordinated Notes due 2085
SOJF
NYSE
The Southern Company
2025 Series A Corporate Units
SOMN
NYSE
Georgia Power CompanySeries 2017A 5.00% Junior Subordinated Notes due 2077GPJANYSE
Southern Power CompanySeries 2016B 1.850% Senior Notes due 2026SO/26ANYSE

Securities registered pursuant to Section 12(g) of the Act: None
Indicate by check mark if the registrant is a well-known seasoned issuer, as defined in Rule 405 of the Securities Act.
RegistrantYesNo
The Southern CompanyX
Alabama Power CompanyX
Georgia Power CompanyX
Mississippi Power CompanyX
Southern Power CompanyX
Southern Company GasX
Indicate by check mark if the registrant is not required to file reports pursuant to Section 13 or Section 15(d) of the Act. Yes ¨ No x (Response applicable to all registrants.)
Indicate by check mark whether the registrants (1) have filed all reports required to be filed by Section 13 or 15(d) of the Securities Exchange Act of 1934 during the preceding 12 months (or for such shorter period that the registrants were required to file such reports), and (2) have been subject to such filing requirements for the past 90 days. Yes x No ¨
Indicate by check mark whether the registrants have submitted electronically every Interactive Data File required to be submitted pursuant to Rule 405 of Regulation S-T during the preceding 12 months (or for such shorter period that the registrants were required to submit such files). Yes x No ¨
Indicate by check mark whether the registrant is a large accelerated filer, an accelerated filer, a non-accelerated filer, a smaller reporting company, or an emerging growth company. See the definitions of "large accelerated filer," "accelerated filer," "smaller reporting company," and "emerging growth company" in Rule 12b-2 of the Exchange Act.
RegistrantLarge Accelerated FilerAccelerated
Filer
Non-accelerated FilerSmaller
Reporting
Company
Emerging Growth Company
The Southern CompanyX
Alabama Power CompanyX
Georgia Power CompanyX
Mississippi Power CompanyX
Southern Power CompanyX
Southern Company GasX
If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act. 


    Table of Contents                                Index to Financial Statements
Indicate by check mark whether the registrant has filed a report on and attestation to its management's assessment of the effectiveness of its internal control over financial reporting under Section 404(b) of the Sarbanes-Oxley Act (15 U.S.C. 7262(b)) by the registered public accounting firm that prepared or issued its audit report.
RegistrantYesNo
The Southern CompanyX
Alabama Power CompanyX
Georgia Power CompanyX
Mississippi Power CompanyX
Southern Power CompanyX
Southern Company GasX
If securities are registered pursuant to Section 12(b) of the Act, indicate by check mark whether the financial statements of the registrant included in the filing reflect the correction of an error to previously issued financial statements.
Indicate by check mark whether any of those error corrections are restatements that required a recovery analysis of incentive-based compensation received by any of the registrant's executive officers during the relevant recovery period pursuant to § 240.10D-1(b). ☐
Indicate by check mark whether the registrant is a shell company (as defined in Rule 12b-2 of the Exchange Act). Yes No x (Response applicable to all registrants.)
Aggregate market value of The Southern Company's common stock held by non-affiliates of The Southern Company at June 30, 2025: $101.0 billion. All of the common stock of the other registrants is held by The Southern Company. A description of each registrant's common stock follows:
RegistrantDescription of
Common Stock
Shares Outstanding at January 31, 2026
The Southern CompanyPar Value $5 Per Share1,119,391,291 
Alabama Power CompanyPar Value $40 Per Share30,537,500 
Georgia Power CompanyWithout Par Value9,261,500 
Mississippi Power CompanyWithout Par Value1,121,000 
Southern Power CompanyPar Value $0.01 Per Share1,000 
Southern Company GasPar Value $0.01 Per Share100 
Documents incorporated by reference: specified portions of The Southern Company's Definitive Proxy Statement on Schedule 14A relating to the 2026 Annual Meeting of Stockholders are incorporated by reference into PART III.
Each of Alabama Power Company, Georgia Power Company, Mississippi Power Company, Southern Power Company, and Southern Company Gas meets the conditions set forth in General Instructions I(1)(a) and (b) of Form 10-K and is therefore filing this Form 10-K with the reduced disclosure format specified in General Instructions I(2)(b), (c), and (d) of Form 10-K.
This combined Form 10-K is separately filed by The Southern Company, Alabama Power Company, Georgia Power Company, Mississippi Power Company, Southern Power Company, and Southern Company Gas. Information contained herein relating to any individual registrant is filed by such registrant on its own behalf. Each registrant makes no representation as to information relating to the other registrants.


    Table of Contents                                Index to Financial Statements
Table of Contents
Page
Definitions
ii
Cautionary Statement Regarding Forward-Looking Information
vi
PART I
Item 1
Business
I-1
The Southern Company System
I-1
Construction Programs
I-4
Financing Programs
I-5
Fuel Supply
I-5
Territory and Customers Served by the Southern Company System
I-6
Competition
I-8
Seasonality
I-10
Regulation
I-10
Rate Matters
I-11
Human Capital
I-13
Item 1A
Risk Factors
I-15
Item 1B
Unresolved Staff Comments
I-28
Item 1C
Cybersecurity
I-28
Item 2
Properties
I-32
Item 3
Legal Proceedings
I-38
Item 4
Mine Safety Disclosures
I-39
Information about Our Executive Officers – Southern Company
I-40
PART II
Item 5
Market for Registrants' Common Equity, Related Stockholder Matters and Issuer Purchases of Equity Securities
II-1
Item 6
Reserved
II-1
Item 7
Management's Discussion and Analysis of Financial Condition and Results of Operations
II-2
Item 7A
Quantitative and Qualitative Disclosures about Market Risk
II-2
Item 8
Financial Statements and Supplementary Data
II-68
Item 9
Changes in and Disagreements with Accountants on Accounting and Financial Disclosure
II-253
Item 9A
Controls and Procedures
II-253
Item 9B
Other Information
II-253
Item 9C
Disclosure Regarding Foreign Jurisdictions that Prevent Inspections
II-254
PART III
Item 10
Directors, Executive Officers and Corporate Governance
III-1
Item 11
Executive Compensation
III-1
Item 12
Security Ownership of Certain Beneficial Owners and Management and Related Stockholder Matters
III-1
Item 13
Certain Relationships and Related Transactions, and Director Independence
III-1
Item 14
Principal Accountant Fees and Services
III-2
PART IV
Item 15
Exhibits and Financial Statement Schedules
IV-1
Item 16
Form 10-K Summary
IV-1
Signatures
i

    Table of Contents                                Index to Financial Statements
DEFINITIONS
When used in this Form 10-K, the following terms will have the meanings indicated.
TermMeaning
2022 ARP
Georgia Power's Alternate Rate Plan approved by the Georgia PSC in 2022 for the years 2023 through 2025
2023 IRP Update
Georgia Power's updated IRP filed in 2023 and approved by the Georgia PSC in April 2024 as modified by a stipulation among Georgia Power, the staff of the Georgia PSC, and certain intervenors
AFUDCAllowance for funds used during construction
AGL Services Company
AGL Services Company, Inc., the Southern Company Gas system service company and a wholly-owned subsidiary of Southern Company Gas
Alabama PowerAlabama Power Company
AMEAAlabama Municipal Electric Authority
Amended and Restated Loan Guarantee Agreement
Loan guarantee agreement entered into by Georgia Power with the DOE in 2014, as amended and restated in 2019, under which the proceeds of borrowings were used to reimburse Georgia Power for Eligible Project Costs incurred in connection with its construction of Plant Vogtle Units 3 and 4
AOCIAccumulated other comprehensive income
AROAsset retirement obligation
ASUAccounting Standards Update
Atlanta Gas LightAtlanta Gas Light Company, a wholly-owned subsidiary of Southern Company Gas
BcfBillion cubic feet
CAMT
Corporate alternative minimum tax
CCNCertificate of convenience and necessity
CCRCoal combustion residuals
CCR RuleDisposal of Coal Combustion Residuals from Electric Utilities final rule published by the EPA in 2015
Chattanooga GasChattanooga Gas Company, a wholly-owned subsidiary of Southern Company Gas
Clean Air ActClean Air Act Amendments of 1990
CO2
Carbon dioxide
CODCommercial operation date
CODM
Chief operating decision maker
Cooperative EnergyElectric generation and transmission cooperative in Mississippi
CPCNCertificate of public convenience and necessity
CWIPConstruction work in progress
Dalton
City of Dalton, Georgia, an incorporated municipality in the state of Georgia, acting by and through its Board of Water, Light, and Sinking Fund Commissioners
Dalton PipelineA pipeline facility in Georgia in which Southern Company Gas has a 50% undivided ownership interest
DOEU.S. Department of Energy
ECCRGeorgia Power's Environmental Compliance Cost Recovery tariff
ECO PlanMississippi Power's environmental compliance overview plan
ELGEffluent limitations guidelines
Eligible Project CostsCertain costs of construction relating to Plant Vogtle Units 3 and 4 that are eligible for financing under the loan guarantee program established under Title XVII of the Energy Policy Act of 2005
EMCElectric membership corporation
EPAU.S. Environmental Protection Agency
FASBFinancial Accounting Standards Board
FCCFederal Communications Commission
FERCFederal Energy Regulatory Commission
FFBFederal Financing Bank
FFB Credit FacilitiesNote purchase agreements among the DOE, Georgia Power, and the FFB and related promissory notes which provide for two multi-advance term loan facilities
ii

    Table of Contents                                Index to Financial Statements
DEFINITIONS
(continued)

TermMeaning
FitchFitch Ratings, Inc.
FP&LFlorida Power and Light Company
GAAPU.S. generally accepted accounting principles
Georgia PowerGeorgia Power Company
GHGGreenhouse gas
GRAMAtlanta Gas Light's Georgia Rate Adjustment Mechanism
GW
Gigawatt
Heating Degree DaysA measure of weather, calculated when the average daily temperatures are less than 65 degrees Fahrenheit
Heating SeasonThe period from November through March when Southern Company Gas' natural gas usage and operating revenues are generally higher
HLBVHypothetical liquidation at book value
IBEWInternational Brotherhood of Electrical Workers
IGCCIntegrated coal gasification combined cycle, the technology originally approved for Mississippi Power's Kemper County energy facility
IICIntercompany Interchange Contract
Illinois CommissionIllinois Commerce Commission
Internal Revenue CodeInternal Revenue Code of 1986, as amended
IPPIndependent power producer
IRA
Inflation Reduction Act of 2022
IRPIntegrated resource plan
IRSInternal Revenue Service
ITCInvestment tax credit
KWKilowatt
KWHKilowatt-hour
LIFOLast-in, first-out
LNGLiquefied natural gas
LTSALong-term service agreement
MarketersMarketers selling retail natural gas in Georgia and certificated by the Georgia PSC
MEAG PowerMunicipal Electric Authority of Georgia
Mississippi PowerMississippi Power Company
mmBtuMillion British thermal units
Moody'sMoody's Investors Service, Inc.
MPUSMississippi Public Utilities Staff
MRAMunicipal and Rural Associations
MWMegawatt
natural gas distribution utilitiesSouthern Company Gas' natural gas distribution utilities (Nicor Gas, Atlanta Gas Light, Virginia Natural Gas, and Chattanooga Gas)
NCCRGeorgia Power's Nuclear Construction Cost Recovery tariff
NDRAlabama Power's Natural Disaster Reserve
Nicor GasNorthern Illinois Gas Company, a wholly-owned subsidiary of Southern Company Gas
NRCU.S. Nuclear Regulatory Commission
NYMEXNew York Mercantile Exchange, Inc.
NYSENew York Stock Exchange
OBBB
One Big Beautiful Bill Act
OCIOther comprehensive income
OPCOglethorpe Power Corporation (an EMC)
OTCOver-the-counter
iii

    Table of Contents                                Index to Financial Statements
DEFINITIONS
(continued)

TermMeaning
PEPMississippi Power's Performance Evaluation Plan
PowerSecurePowerSecure, Inc., a wholly-owned subsidiary of Southern Company
PowerSouthPowerSouth Energy Cooperative
PPAPower purchase agreements, as well as, for Southern Power, contracts for differences that provide the owner of a renewable facility a certain fixed price for the electricity sold to the grid
PSCPublic Service Commission
PTCProduction tax credit
Rate CNPAlabama Power's Rate Certificated New Plant, consisting of Rate CNP New Plant, Rate CNP Compliance, Rate CNP PPA, and Rate CNP Depreciation
Rate ECRAlabama Power's Rate Energy Cost Recovery
Rate NDRAlabama Power's Rate Natural Disaster Reserve
Rate RSEAlabama Power's Rate Stabilization and Equalization
RegistrantsSouthern Company, Alabama Power, Georgia Power, Mississippi Power, Southern Power Company, and Southern Company Gas
RFP
Request for proposals
ROEReturn on equity
S&PS&P Global Ratings, a division of S&P Global Inc.
SAVESteps to Advance Virginia's Energy, an infrastructure replacement program at Virginia Natural Gas
SCSSouthern Company Services, Inc., the Southern Company system service company and a wholly-owned subsidiary of Southern Company
SECU.S. Securities and Exchange Commission
SEGCOSouthern Electric Generating Company, 50% owned by each of Alabama Power and Georgia Power
SEPASoutheastern Power Administration
SNGSouthern Natural Gas Company, L.L.C., a pipeline system in which Southern Company Gas has a 50% ownership interest
SOFRSecured Overnight Financing Rate
Southern CompanyThe Southern Company
Southern Company GasSouthern Company Gas and its subsidiaries
Southern Company Gas Capital
Southern Company Gas Capital Corporation, a wholly-owned subsidiary of Southern Company Gas
Southern Company power poolThe operating arrangement whereby the integrated generating resources of the traditional electric operating companies and Southern Power (excluding subsidiaries) are subject to joint commitment and dispatch in order to serve their combined load obligations
Southern Company systemSouthern Company, the traditional electric operating companies, Southern Power, Southern Company Gas, SEGCO, Southern Nuclear, SCS, Southern Linc, PowerSecure, and other subsidiaries
Southern HoldingsSouthern Company Holdings, Inc., a wholly-owned subsidiary of Southern Company
Southern LincSouthern Communications Services, Inc., a wholly-owned subsidiary of Southern Company, doing business as Southern Linc
Southern NuclearSouthern Nuclear Operating Company, Inc., a wholly-owned subsidiary of Southern Company
Southern PowerSouthern Power Company and its subsidiaries
SouthStarSouthStar Energy Services, LLC (a Marketer), a wholly-owned subsidiary of Southern Company Gas
SP SolarSP Solar Holdings I, LP, a limited partnership indirectly owning substantially all of Southern Power's solar and battery energy storage facilities, in which Southern Power has a 67% ownership interest
SP Wind
SP Wind Holdings II, LLC, a holding company owning a portfolio of eight operating wind facilities and wholly-owned by Southern Power as of December 31, 2025, was previously in a tax equity arrangement where Southern Power was the controlling partner through December 31, 2025
iv

    Table of Contents                                Index to Financial Statements
DEFINITIONS
(continued)

TermMeaning
SRRMississippi Power's System Restoration Rider, a tariff for retail property damage cost recovery and reserve
Subsidiary RegistrantsAlabama Power, Georgia Power, Mississippi Power, Southern Power, and Southern Company Gas
Tax Reform LegislationThe Tax Cuts and Jobs Act, which became effective on January 1, 2018
traditional electric operating companiesAlabama Power, Georgia Power, and Mississippi Power
U.S. Treasury
U.S. Department of the Treasury
VIEVariable interest entity
Virginia CommissionVirginia State Corporation Commission
Virginia Natural GasVirginia Natural Gas, Inc., a wholly-owned subsidiary of Southern Company Gas
Vogtle Owners
Georgia Power, OPC, MEAG Power, and Dalton
v

    Table of Contents                                Index to Financial Statements
CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION
This Annual Report on Form 10-K contains forward-looking statements. Forward-looking statements include, among other things, statements concerning regulated rates, the strategic goals for the business, customer and sales growth, economic conditions, including interest rates, tariffs, and inflation, cost recovery and other rate actions, projected equity ratios, current and proposed environmental regulations and related compliance plans and estimated expenditures, GHG emissions reduction goals, pending or potential litigation matters, access to sources of capital, projections for the qualified pension plans, postretirement benefit plans, and nuclear decommissioning trust fund contributions, financing activities, completion dates and costs of construction projects, filings with state and federal regulatory authorities, federal and state income tax benefits, estimated sales and purchases under power sale and purchase agreements, and estimated construction plans and expenditures. In some cases, forward-looking statements can be identified by terminology such as "may," "will," "could," "would," "should," "expects," "plans," "anticipates," "believes," "estimates," "projects," "predicts," "potential," or "continue" or the negative of these terms or other similar terminology. There are various factors that could cause actual results to differ materially from those suggested by the forward-looking statements; accordingly, there can be no assurance that such indicated results will be realized. These factors include:
the impact of recent and future federal and state legal and regulatory changes, including tax, environmental, and other laws and regulations to which Southern Company and its subsidiaries are subject, as well as changes in application of existing laws, regulations, and guidance;
the extent and timing of costs and legal requirements related to CCR;
current and future litigation or regulatory investigations, proceedings, or inquiries, including litigation related to the Kemper County energy facility;
the effects, extent, and timing of the entry of additional competition in the markets in which Southern Company's subsidiaries operate, including from the development and deployment of alternative energy sources;
variations in demand for electricity and natural gas, including uncertainties related to projected significant growth in electricity demand driven primarily by data centers and other large load customers, and the related requirement for substantial new generation and transmission investments, creating capital access and revenue recovery risks for the traditional electric operating companies;
customer affordability matters;
available sources and costs of natural gas and other fuels and commodities;
the ability to complete necessary or desirable pipeline expansion or infrastructure projects, limits on pipeline capacity, public and policymaker support for such projects, and operational interruptions to natural gas distribution and transmission activities;
transmission constraints;
the ability to control costs and avoid cost and schedule overruns during the development, construction, and operation of facilities or other projects due to challenges which include, but are not limited to, changes in labor costs, availability, and productivity; challenges with the management of contractors or vendors; subcontractor performance; adverse weather conditions; shortages, delays, increased costs, or inconsistent quality of equipment, materials, and labor; contractor or supplier delay; the impacts of inflation and trade policies (including tariffs and other trade measures) of the United States and other countries; delays due to judicial or regulatory action; nonperformance under construction, operating, or other agreements; operational readiness, including specialized operator training and required site safety programs; engineering or design problems or any remediation related thereto; design and other licensing-based compliance matters; challenges with start-up activities, including major equipment failure, or system integration, and/or operational performance; challenges related to future epidemic or pandemic health events; continued public and policymaker support for projects; environmental and geological conditions; delays or increased costs to interconnect facilities to transmission grids; and increased financing costs as a result of changes in interest rates or as a result of project delays;
legal proceedings and regulatory approvals and actions related to past, ongoing, and proposed construction projects, including state PSC or other applicable state regulatory agency approvals and FERC and NRC actions;
the ability to construct facilities in accordance with the requirements of permits and licenses, to satisfy any environmental performance standards and the requirements of tax credits and other incentives, and to integrate facilities into the Southern Company system upon completion of construction;
investment performance of the employee and retiree benefit plans and nuclear decommissioning trust funds and, with respect to retiree benefit plans, changes in actuarial assumptions and differences between the assumptions and actual values, any of the foregoing of which could cause additional funding requirements;
vi

    Table of Contents                                Index to Financial Statements
CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION
(continued)
advances in technology, including the pace and extent of development of low- to no-carbon energy and battery energy storage technologies and the impact of advancing technology on data center and other large load customer demand;
performance of counterparties under ongoing renewable energy partnerships and development agreements;
state and federal rate regulations and the impact of pending and future rate cases and negotiations, including rate actions relating to ROE, equity ratios, additional generating capacity and transmission facilities, extension of retirement dates for fossil fuel plants, and fuel and other cost recovery mechanisms;
the ability to successfully operate the traditional electric operating companies', SEGCO's, and Southern Power's generation, transmission, distribution, and battery energy storage facilities, as applicable, and Southern Company Gas' natural gas distribution and storage facilities and the successful performance of necessary corporate functions;
the inherent risks involved in operating nuclear generating facilities;
the inherent risks involved in generation, transmission, and distribution of electricity and transportation and storage of natural gas, including accidents, explosions, fires, mechanical problems, discharges or releases of toxic or hazardous substances or gases, and other environmental risks;
the performance of projects undertaken by the non-utility businesses and the success of efforts to invest in and develop new opportunities;
internal restructuring or other restructuring options that may be pursued;
potential business strategies, including acquisitions or dispositions of assets or businesses, or interests therein, which cannot be assured to be completed or beneficial to Southern Company or its subsidiaries;
the ability of counterparties of Southern Company and its subsidiaries to make payments as and when due and to perform as required;
the ability to obtain new short- and long-term contracts with wholesale customers;
the direct or indirect effect on the Southern Company system's business resulting from cyber intrusion or physical attack and the threat of cyber and physical attacks;
global and U.S. economic conditions, including impacts from geopolitical conflicts, recession, inflation, changes in trade policies (including tariffs and other trade measures) of the United States and other countries, interest rate fluctuations, and financial market conditions, and the results of financing efforts;
prolonged or recurring U.S. federal government shutdowns;
access to capital markets and other financing sources;
changes in Southern Company's and any of its subsidiaries' credit ratings;
the ability of the traditional electric operating companies to obtain additional generating capacity (or sell excess generating capacity) at competitive prices;
catastrophic events such as fires, including wildfires, land movement, earthquakes, explosions, floods, high winds, tornadoes, hurricanes and other storms, solar flares, droughts, future epidemic or pandemic health events, wars, political unrest, or other similar occurrences;
the direct or indirect effects on the Southern Company system's business resulting from incidents affecting the U.S. electric grid, natural gas pipeline infrastructure, or operation of generating or storage resources;
impairments of goodwill or long-lived assets;
the effect of accounting pronouncements issued periodically by standard-setting bodies; and
other factors discussed elsewhere herein and in other reports filed by the Registrants from time to time with the SEC.
The Registrants expressly disclaim any obligation to update any forward-looking statements.
vii

    Table of Contents                                Index to Financial Statements
PART I
Item 1. BUSINESS
Southern Company is a holding company that owns all of the outstanding common stock of three traditional electric operating companies, Southern Power Company, and Southern Company Gas.
The traditional electric operating companies – Alabama Power, Georgia Power, and Mississippi Power – are each vertically integrated utilities providing electric service to retail customers in three Southeastern states in addition to wholesale customers in the Southeast.
Southern Power Company is an operating public utility company. The term "Southern Power" when used herein refers to Southern Power Company and its subsidiaries, while the term "Southern Power Company" when used herein refers only to the Southern Power parent company. Southern Power develops, constructs, acquires, owns, operates, and manages power generation assets, including battery energy storage projects, and sells electricity at market-based rates in the wholesale market.
Southern Company Gas is an energy services holding company whose primary business is the distribution of natural gas in four states – Illinois, Georgia, Virginia, and Tennessee – through the natural gas distribution utilities. Southern Company Gas is also involved in several other businesses that are complementary to the distribution of natural gas.
Southern Company also owns SCS, Southern Linc, Southern Holdings, Southern Nuclear, PowerSecure, and other direct and indirect subsidiaries. SCS, the system service company, has contracted with Southern Company, each of the Subsidiary Registrants, Southern Nuclear, SEGCO, and other subsidiaries to furnish, at direct or allocated cost and upon request, the following services: general executive and advisory, general and design engineering, operations, purchasing, accounting, finance, treasury, legal, tax, information technology, marketing, auditing, insurance and pension administration, human resources, systems and procedures, digital wireless communications, cellular tower space, and other services with respect to business and operations, construction management, and Southern Company power pool transactions. Southern Linc provides digital wireless communications for use by Southern Company and its subsidiary companies and also markets these services to the public and provides fiber optics services through its subsidiary, Southern Telecom, Inc. Southern Linc's system covers approximately 122,000 square miles in the Southeast. Southern Holdings is an intermediate holding company subsidiary, which, through its subsidiaries, invests in various projects and insures various risk exposures of Southern Company and its subsidiaries. Southern Nuclear operates and provides services to the Southern Company system's nuclear power plants. PowerSecure develops distributed energy and resilience solutions and deploys microgrids for commercial, industrial, governmental, and utility customers.
See "The Southern Company System" herein for additional information. Also see Note 15 to the financial statements in Item 8 herein for information regarding recent acquisition and disposition activity. Segment information for the Registrants is included in Note 16 to the financial statements in Item 8 herein.
The Registrants' Annual Reports on Form 10-K, Quarterly Reports on Form 10-Q, Current Reports on Form 8-K, and any amendments to those reports are made available on Southern Company's website, free of charge, as soon as reasonably practicable after such material is electronically filed with or furnished to the SEC. Southern Company's internet address is www.southerncompany.com. The information contained on, or available through, Southern Company's internet website is not, and shall not be deemed to be, incorporated by reference into this report.
The Southern Company System
Traditional Electric Operating Companies
The traditional electric operating companies are vertically integrated utilities that own generation, transmission, and distribution facilities. See PROPERTIES – "Electric" in Item 2 herein for additional information on the traditional electric operating companies' generating facilities. Each company's transmission facilities are connected to the respective company's own generating plants and other sources of power (including certain generating plants owned by Southern Power) and are interconnected with the transmission facilities of the other traditional electric operating companies and SEGCO. For information on the state of Georgia's integrated transmission system, see "Territory and Customers Served by the Southern Company System – Traditional Electric Operating Companies and Southern Power" herein.
Agreements in effect with principal neighboring utility systems provide for capacity and energy transactions that may be entered into for reasons related to reliability or economics. Additionally, the traditional electric operating companies have entered into various reliability agreements with certain neighboring utilities, each of which provides for the establishment and periodic review of principles and procedures for planning and operation of generation and transmission facilities, maintenance schedules, load retention programs, emergency operations, and other matters affecting the reliability of bulk power supply. The
I-1

    Table of Contents                                Index to Financial Statements
traditional electric operating companies have joined with other utilities in the Southeast to form the SERC Reliability Corporation (SERC) to augment further the reliability and adequacy of bulk power supply. Through the SERC, the traditional electric operating companies are represented at the North American Electric Reliability Corporation. In 2022, the Southeast Energy Exchange Market (SEEM) began service. SEEM, whose members include the traditional electric operating companies and many of the other electric service providers in the Southeast, is an extension of the existing bilateral market where participants use an automated, intra-hour energy exchange to buy and sell power close to the time the energy is consumed, utilizing available unreserved transmission. Following a remand order issued by the U.S. Court of Appeals for the D.C. Circuit related to the FERC's initial approval of SEEM, on March 14, 2025, the FERC issued a further order affirming its initial approval of the SEEM market platform, subject to a later compliance filing. The FERC accepted the required compliance filing on June 26, 2025. New appeals were filed at the U.S. Court of Appeals for the D.C. Circuit while the FERC considered the court's earlier remand. On January 6, 2026, the FERC issued an order accepting a settlement agreement between SEEM members and petitioners in the ongoing appeal proceedings to resolve all pending appeals, subject to a compliance filing to modify the SEEM agreement in accordance with the settlement. The compliance filing was submitted on February 5, 2026. The pending appeals have been withdrawn in accordance with the settlement, which concludes all pending challenges to SEEM's approval. The ultimate outcome of this matter cannot be determined at this time.
The utility assets of the traditional electric operating companies and certain utility assets of Southern Power Company are operated as a single integrated electric system, or the Southern Company power pool, pursuant to the IIC. Activities under the IIC are administered by SCS, which acts as agent for the traditional electric operating companies and Southern Power Company. The fundamental purpose of the Southern Company power pool is to provide for the coordinated operation of the electric facilities in an effort to achieve the maximum possible economies consistent with the highest practicable reliability of service. Subject to service requirements and other operating limitations, system resources are committed and controlled through the application of centralized economic dispatch. Under the IIC, each traditional electric operating company and Southern Power Company retains its lowest cost energy resources for the benefit of its own customers and delivers any excess energy to the Southern Company power pool for use in serving customers of other traditional electric operating companies or Southern Power Company or for sale by the Southern Company power pool to third parties. The IIC provides for the recovery of specified costs associated with the affiliated operations thereunder, as well as the proportionate sharing of costs and revenues resulting from Southern Company power pool transactions with third parties.
The traditional electric operating companies are projecting a significant increase in demand for electricity sales, largely driven by data centers and other large load customers. Serving the projected increased load demand from these new customers while continuing to serve existing customers safely, reliably, and affordably requires investing in generation, transmission, and distribution systems and pricing sales to these new customers such that the related incremental costs are met with adequate incremental revenues from these new customers. Through the 2022 IRP and the 2023 IRP Update, the Georgia PSC has certified resources totaling approximately 13 GWs, approximately nine GWs of which are new generation and battery energy storage facilities that are being, or are expected to be, constructed by Georgia Power. The certified costs of these Georgia Power projects total $19.5 billion, and these projects are projected to be placed in service through 2030. Since 2023, the traditional electric operating companies have contracted with new data centers and other large load customers covering approximately nine GWs of electric load, with each contract individually representing a maximum annual electric load greater than 100 MWs, that have been signed by the parties and/or reviewed by the state regulatory commissions. These new contracts fully ramp up over several years after commencement of service. Some of these contracts are already in effect. Service under the contracts is expected to begin through 2028. The contracts contain various terms and conditions, such as minimum duration, minimum bill provisions, contribution by the customer to local construction costs, termination payment requirements, and financial security, designed to generate adequate incremental revenues associated with incremental costs to serve these customers.
Southern Power and Southern Linc have secured from the traditional electric operating companies certain services which are furnished in compliance with FERC regulations.
Alabama Power and Georgia Power each have agreements with Southern Nuclear to operate the Southern Company system's nuclear plants, Plants Farley, Hatch, and Vogtle. See "Regulation – Nuclear Regulation" herein for additional information.
Southern Power
Southern Power develops, constructs, acquires, owns, operates, and manages power generation assets, including battery energy storage projects, and sells electricity at market-based rates (under authority from the FERC) in the wholesale market. Southern Power seeks opportunities to execute its strategy to create value through various transactions including acquisitions, dispositions, sales and purchases of partnership interests, development and construction of new generating facilities, and entry into PPAs, primarily with investor-owned utilities, IPPs, municipalities, electric cooperatives, and other load-serving entities, as well as commercial and industrial customers. Southern Power's business activities are not subject to traditional state regulation like the traditional electric operating companies, but the majority of its business activities are subject to regulation by the FERC.
I-2

    Table of Contents                                Index to Financial Statements
For additional information on Southern Power's business activities, see MANAGEMENT'S DISCUSSION AND ANALYSIS – OVERVIEW – "Business Activities" in Item 7 herein.
Southern Power Company directly owns and manages generation assets primarily in the Southeast, which are included in the Southern Company power pool, and has various subsidiaries whose generation assets are not included in the Southern Company power pool. These subsidiaries were created to own, operate, and pursue power generation facilities, either wholly or in partnership with various third parties. At December 31, 2025, Southern Power's generation fleet, which is owned in part with various partners, totaled 12,648 MWs of nameplate capacity in commercial operation (including 5,268 MWs of nameplate capacity owned by its subsidiaries). See "Traditional Electric Operating Companies" herein for additional information on the Southern Company power pool.
A majority of Southern Power's partnerships in renewable facilities allow for the sharing of cash distributions and tax benefits at differing percentages, with Southern Power being the controlling partner and thus consolidating the assets and operations of the partnerships. At December 31, 2025, Southern Power had seven tax equity partnership arrangements where the tax equity investors receive substantially all of the tax benefits from the facilities, including ITCs and PTCs. In addition, Southern Power holds controlling interests in non-tax equity partnerships with its ownership interests primarily ranging from 51% to 66%.
See PROPERTIES – "Electric" in Item 2 herein for additional detail regarding Southern Power's generating facilities and partnership arrangements and Note 15 to the financial statements under "Southern Power" in Item 8 herein for additional information regarding Southern Power's acquisitions, dispositions, construction, and development projects.
Southern Power's electricity sales from natural gas generating facilities are primarily through long-term, fixed-price capacity PPAs with unaffiliated wholesale purchasers as well as with the traditional electric operating companies and consist of two types of agreements. The first type, referred to as a unit or block sale, is a customer purchase from a dedicated plant unit where all or a portion of the generation from that unit is reserved for that customer. Southern Power typically has the ability to serve the unit or block sale customer from an alternate resource. The second type, referred to as requirements service, provides that Southern Power serves the customer's capacity and energy requirements from a combination of the customer's own generating units and from Southern Power resources not dedicated to serve unit or block sales. Southern Power has rights to purchase power provided by the requirements customers' resources when economically viable. Capacity charges that form part of the PPA payments are designed to recover fixed and variable operations and maintenance costs based on dollars-per-kilowatt year and to provide a return on investment. Southern Power has attempted to insulate itself from significant fuel supply, fuel transportation, and electric transmission risks by generally making such risks the responsibility of the counterparties to its PPAs.
Southern Power's electricity sales from solar and wind generating facilities are also primarily through long-term PPAs; however, these solar and wind PPAs do not have a capacity charge and customers either purchase the energy output of a dedicated renewable facility through an energy charge or provide Southern Power a certain fixed price for the electricity sold to the grid. As a result, Southern Power's ability to recover fixed and variable operations and maintenance expenses is dependent upon the level of energy generated from these facilities, which can be impacted by weather conditions, equipment performance, transmission constraints, and other factors. Generally, under the renewable generation PPAs, the purchasing party retains the right to keep or resell the renewable energy credits.
Southern Power actively pursues replacement PPAs prior to the expiration of its current PPAs and anticipates that the revenues attributable to one customer may be replaced by revenues from a new customer; however, the expiration of any of Southern Power's current PPAs without the successful remarketing of a replacement PPA could have a material negative impact on Southern Power's earnings but is not expected to have a material impact on Southern Company's earnings.
Southern Power calculates an investment coverage ratio for its generating assets, including those owned with various partners, based on the ratio of investment under contract to total investment using the respective facilities' net book value (or expected in-service value for facilities under construction) as the investment amount. With the inclusion of investments associated with facilities under construction, as well as other capacity and energy contracts, Southern Power's average investment coverage ratio at December 31, 2025 was 97% through 2030 and 89% through 2035, with an average remaining contract duration of approximately 12 years. For the year ended December 31, 2025, approximately 63% of contracted MWs were with AAA to A- or equivalent rated counterparties, 31% were with BBB+ to BBB- or equivalent rated counterparties, and 4% were with unrated entities that either have ratemaking authority or have posted collateral to cover potential credit exposure.
Southern Power's future earnings will depend on the parameters of the wholesale market and the efficient operation of its wholesale generating assets; Southern Power's ability to execute its growth strategy through the development, construction, or acquisition of generating facilities and other energy projects while containing costs; regulatory matters; customer creditworthiness; total electric generating capacity available in Southern Power's market areas; Southern Power's ability to successfully remarket capacity as current contracts expire; renewable portfolio standards; continued availability of federal and
I-3

    Table of Contents                                Index to Financial Statements
state ITCs and PTCs under current and future tax legislation and U.S. Treasury guidance; transmission constraints; cost of generation from units within the Southern Company power pool; and operational limitations.
Southern Company Gas
Southern Company Gas is an energy services holding company whose primary business is the distribution of natural gas through the natural gas distribution utilities. Southern Company Gas is also involved in several other businesses that are complementary to the distribution of natural gas, including gas pipeline investments and gas marketing services. Southern Company Gas also has an "all other" non-reportable segment that includes segments below the quantitative threshold for separate disclosure.
Gas distribution operations, the largest segment of Southern Company Gas' business, operates, constructs, and maintains approximately 77,900 miles of natural gas pipelines and 14 storage facilities, with total capacity of 157 Bcf, to provide natural gas to residential, commercial, and industrial customers. Gas distribution operations serves approximately 4.4 million customers across Illinois, Georgia, Virginia, and Tennessee.
Gas pipeline investments primarily consists of joint ventures in natural gas pipeline investments including a 50% interest in SNG and a 50% joint ownership interest in the Dalton Pipeline. These natural gas pipelines enable the provision of diverse sources of natural gas supplies to the customers of Southern Company Gas. SNG, the largest natural gas pipeline investment, is the owner of a 7,000-mile pipeline connecting natural gas supply basins in Texas, Louisiana, Mississippi, and Alabama to markets in Louisiana, Mississippi, Alabama, Florida, Georgia, South Carolina, and Tennessee. SNG is developing a proposed pipeline project, designed to meet customer demand by increasing SNG's existing pipeline capacity by approximately 1.3 billion cubic feet per day, which the operator of the joint venture anticipates will be completed by 2029. The ultimate outcome of this matter cannot be determined at this time. See MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL – "Construction Programs" in Item 7 herein for additional information.
Gas marketing services is comprised of SouthStar, which serves approximately 677,000 natural gas commodity customers, markets gas to residential, commercial, and industrial customers and offers energy-related products that provide natural gas price stability and utility bill management in competitive markets or markets that provide for customer choice.
Construction Programs
The subsidiary companies of Southern Company are engaged in continuous construction programs, including capital expenditures to accommodate existing and estimated future loads on their respective systems and to comply with environmental laws and regulations, as applicable. In 2026, the Southern Company system's construction program is expected to be apportioned approximately as follows:
Southern Company
           system(a)(b)(c)(d)
Alabama
   Power(c)
Georgia
   Power(d)
Mississippi
   Power(a)
(in billions)
New generation$3.7 $0.1 $3.6 $— 
Environmental compliance(e)
0.2 0.1 0.1 — 
Generation maintenance1.4 0.3 1.0 0.1 
Transmission3.2 0.4 2.6 0.2 
Distribution2.0 0.5 1.4 0.1 
Nuclear fuel0.3 0.1 0.2 — 
General plant1.8 0.5 1.2 0.1 
12.6 2.0 10.1 0.4 
Southern Power(f)
0.9 
Southern Company Gas(g)
2.2 
Other subsidiaries0.2 
Total(a)
$15.9 $2.0 $10.1 $0.4 
(a)Totals may not add due to rounding.
(b)Includes the Subsidiary Registrants, as well as other subsidiaries.
(c)Excludes $38 million related to Alabama Power's decision to convert Plant Barry Unit 5 from coal to natural gas. See MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL – "Environmental Matters – Environmental Laws and Regulations – Water Quality" in Item 7 herein and Note 2 to the financial statements under "Alabama Power – Environmental Accounting Order" in Item 8 herein for additional information.
I-4

    Table of Contents                                Index to Financial Statements
(d)Includes expenditures of approximately $3.1 billion for construction projects and related transmission investments approved in conjunction with the 2022 IRP, the 2023 IRP Update, and the 2025 IRP. See Note 2 to the financial statements under "Georgia Power – Integrated Resource Plans" and " – Other Construction" in Item 8 herein for additional information.
(e)Reflects cost estimates for environmental laws and regulations. These estimated expenditures do not include compliance costs associated with the regulation of GHG emissions or costs associated with closure and monitoring of surface impoundments and landfills in accordance with the CCR Rule and the related state rules. See MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL – "Environmental Matters" and – FINANCIAL CONDITION AND LIQUIDITY – "Cash Requirements" in Item 7 herein for additional information. No material capital expenditures are expected for non-environmental government regulations.
(f)Includes $40 million and $0.7 billion related to the Millers Branch solar project and wind repowering projects, respectively. Does not include approximately $0.8 billion for planned acquisitions and placeholder growth, which may vary materially due to market opportunities and Southern Power's ability to execute its growth strategy. See Note 15 to the financial statements under "Southern Power" in Item 8 herein for additional information regarding the Millers Branch solar project and the wind repowering projects.
(g)Includes costs for ongoing capital projects associated with infrastructure improvement programs for certain natural gas distribution utilities that have been previously approved by their applicable state regulatory agencies. See Note 2 to the financial statements under "Southern Company Gas" in Item 8 herein for additional information. Also includes gas pipeline investment of approximately $0.3 billion. See MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL – "Construction Programs" in Item 7 herein for information regarding this project.
The construction programs are subject to periodic review and revision, and actual construction costs may vary from these estimates because of numerous factors.
The traditional electric operating companies also anticipate continued expenditures associated with closure and monitoring of surface impoundments and landfills in accordance with the CCR Rule and the related state rules, which are reflected in the applicable Registrants' ARO liabilities. Estimated costs for 2026 total $653 million for Southern Company, primarily consisting of $256 million for Alabama Power, $360 million for Georgia Power, and $18 million for Mississippi Power.
See MANAGEMENT'S DISCUSSION AND ANALYSIS – FINANCIAL CONDITION AND LIQUIDITY – "Cash Requirements" in Item 7 herein for additional information, including estimated expenditures for construction, environmental compliance, and closure and monitoring of surface impoundments and landfills for the years 2027 through 2030.
Also see MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL – "Environmental Matters" in Item 7 herein for additional information with respect to certain existing and proposed environmental requirements and PROPERTIES – "Electric – Jointly-Owned Facilities" and – "Natural Gas – Jointly-Owned Properties" in Item 2 herein and Note 5 to the financial statements under "Joint Ownership Agreements" in Item 8 herein for additional information concerning the Registrants' joint ownership of certain facilities.
Financing Programs
See MANAGEMENT'S DISCUSSION AND ANALYSIS – FINANCIAL CONDITION AND LIQUIDITY in Item 7 herein and Note 8 to the financial statements in Item 8 herein for information concerning financing programs.
Fuel Supply
Electric
The traditional electric operating companies' and SEGCO's supply of electricity is primarily fueled by natural gas and coal, as well as nuclear for Alabama Power and Georgia Power. Southern Power's supply of electricity is primarily fueled by natural gas. See MANAGEMENT'S DISCUSSION AND ANALYSIS – RESULTS OF OPERATIONS – "Southern Company – Electricity Business – Fuel and Purchased Power Expenses" and MANAGEMENT'S DISCUSSION AND ANALYSIS – RESULTS OF OPERATIONS under "Fuel and Purchased Power Expenses" for each of the traditional electric operating companies in Item 7 herein for information regarding the electricity generated and the average cost of fuel in cents per net KWH generated for the years 2024 and 2025.
SCS, acting on behalf of the traditional electric operating companies and Southern Power Company, has agreements in place for the natural gas burn requirements of the Southern Company system. For 2026, SCS has contracted for 644 Bcf of natural gas supply under agreements with remaining terms up to nine years. In addition to natural gas supply, SCS has contracts in place for both firm natural gas transportation and storage. Management believes these contracts provide sufficient natural gas supplies, transportation, and storage to ensure normal operations of the Southern Company system's natural gas generating units. See "Natural Gas" herein for information on the natural gas market.
The traditional electric operating companies have agreements in place from which they expect to receive substantially all of their 2026 coal burn requirements. These agreements have terms ranging between one and five years. Fuel procurement specifications, emission allowances, environmental control systems, and fuel changes have allowed the traditional electric operating companies to remain within limits set by applicable environmental regulations. As new environmental regulations are proposed that impact the utilization of coal, the traditional electric operating companies' fuel mix will be monitored to help ensure compliance with applicable laws and regulations. Southern Company and the traditional electric operating companies
I-5

    Table of Contents                                Index to Financial Statements
will continue to evaluate the need to purchase additional emissions allowances, the timing of capital expenditures for environmental control equipment, and potential unit retirements and replacements or extension of retirement dates of certain fossil fuel plants. While none of Southern Company's subsidiaries are currently subject to renewable portfolio standards or similar requirements, management of the traditional electric operating companies is working with applicable regulators through their IRP processes to continue the generating fleet transition in a manner responsible to customers, communities, employees, and other stakeholders. See MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL – "Environmental Matters" in Item 7 herein and Note 2 to the financial statements under "Alabama Power – Environmental Accounting Order," "Georgia Power – Integrated Resource Plans," and "Mississippi Power – Integrated Resource Plans" in Item 8 herein for additional information, including the Southern Company system's electric generating mix and plans to retire or convert to natural gas certain coal-fired generating capacity.
Alabama Power and Georgia Power have multiple contracts covering their nuclear fuel needs for uranium, conversion services, enrichment services, and fuel fabrication with remaining terms up to 10 years. Management believes suppliers have sufficient nuclear fuel production capability to permit normal operation of the Southern Company system's nuclear generating units. Alabama Power and Georgia Power also have contracts with the United States, acting through the DOE, that provide for the permanent disposal of spent nuclear fuel. The DOE failed to begin disposing of spent fuel in 1998, as required by the contracts, and Alabama Power and Georgia Power have pursued legal remedies against the government for breach of contract. See Note 3 to the financial statements under "Nuclear Fuel Disposal Costs" in Item 8 herein for additional information.
Changes in fuel prices to the traditional electric operating companies are generally reflected in fuel adjustment clauses contained in rate schedules. See "Rate Matters – Rate Structure and Cost Recovery Plans" herein for additional information. Southern Power's natural gas PPAs generally provide that the counterparty is responsible for substantially all of the cost of fuel.
Natural Gas
Natural gas remains a volatile commodity. Slight supply and demand imbalances can quickly result in significant price moves both up and down. These price movements may be short-lived, but the impacts can be pronounced. Natural gas supplies have continued to grow; however, this growth has been accompanied by LNG export growth. Forward curves project prices will remain in the mid- to high-$3 per mmBtu range through 2030; however, short-term price volatility is expected and future prices could be materially impacted by various factors, including unexpected geopolitical events as well as government policies related to natural gas and energy, including infrastructure development, production, and exports.
Southern Company Gas' procurement plans for natural gas supply and transportation to serve regulated utility customers are reviewed and approved by the regulatory agencies in the states where it operates. Southern Company Gas purchases natural gas supplies in the open market by contracting with producers and marketers and, for Atlanta Gas Light and Chattanooga Gas, under asset management agreements approved by the applicable state regulatory agency. Southern Company Gas also contracts for transportation and storage services from interstate pipelines that are regulated by the FERC. When firm pipeline services are temporarily not needed, Southern Company Gas may release the services in the secondary market under FERC-approved capacity release provisions or utilize asset management arrangements, thereby reducing the net cost of natural gas charged to customers for most of the natural gas distribution utilities. Peak-use requirements are met through utilization of company-owned storage facilities, pipeline transportation capacity, purchased storage services, peaking facilities, and other supply sources, arranged by either transportation customers or Southern Company Gas.
With the exception of Atlanta Gas Light, the natural gas distribution utilities are authorized by the relevant regulatory agencies in the states in which they serve to use natural gas cost recovery mechanisms that adjust rates to reflect changes in the wholesale cost of natural gas and ensure recovery of all costs prudently incurred in purchasing natural gas for customers. See Note 2 to the financial statements under "Southern Company Gas – Natural Gas Cost Recovery" in Item 8 herein for additional information.
Territory and Customers Served by the Southern Company System
Traditional Electric Operating Companies and Southern Power
The territory in which the traditional electric operating companies provide retail electric service comprises most of the states of Alabama and Georgia, together with southeastern Mississippi. In this territory there are non-affiliated electric distribution systems that obtain some or all of their power requirements either directly or indirectly from the traditional electric operating companies. As of December 31, 2025, the territory had an area of approximately 116,000 square miles and an estimated population of approximately 17 million. Southern Power sells wholesale electricity at market-based rates across various U.S. utility markets, primarily to investor-owned utilities, IPPs, municipalities, and other load-serving entities, as well as commercial and industrial customers.
I-6

    Table of Contents                                Index to Financial Statements
Alabama Power is engaged, within the state of Alabama, in the generation, transmission, distribution, and purchase of electricity and the sale of electric service, at retail in approximately 400 cities and towns (including Anniston, Birmingham, Gadsden, Mobile, Montgomery, and Tuscaloosa), as well as in rural areas, and at wholesale to three rural distributing municipal and cooperative associations. In addition, Alabama Power markets and sells outdoor lighting services and other customer-focused utility services. As of December 31, 2025, Alabama Power's sales contract with AMEA expired, thus eliminating wholesale sales to 11 municipally-owned electric distribution systems previously served indirectly through sales to AMEA.
Georgia Power is engaged in the generation, transmission, distribution, and purchase of electricity and the sale of electric service within the state of Georgia, at retail in over 530 cities and towns (including Athens, Atlanta, Augusta, Columbus, Macon, Rome, and Savannah), as well as in rural areas, and at wholesale to OPC, MEAG Power, Dalton, various EMCs, and non-affiliated utilities. Georgia Power also markets and sells outdoor lighting services and other customer-focused utility services.
Mississippi Power is engaged in the generation, transmission, distribution, and purchase of electricity and the sale of electric service within 23 counties in southeastern Mississippi, at retail in 123 communities (including Biloxi, Gulfport, Hattiesburg, Laurel, Meridian, and Pascagoula), as well as in rural areas, and at wholesale to one municipality, six rural electric distribution cooperative associations, and one generating and transmitting cooperative.
The following table provides the number of retail customers served by customer classification for the traditional electric operating companies at December 31, 2025:
Alabama PowerGeorgia Power
   Mississippi Power(a)
   Total(b)
(in thousands)
Residential1,347 2,480 158 3,986 
Commercial209 333 34 576 
Industrial11 — 17 
Other10 — 10 
Total(b)
1,563 2,834 193 4,590 
(a)Includes 421 industrial retail customers and 104 other retail customers.
(b)Totals may not add due to rounding.
For information relating to KWH sales by customer classification for the traditional electric operating companies, see MANAGEMENT'S DISCUSSION AND ANALYSIS – RESULTS OF OPERATIONS in Item 7 herein. Also, for information relating to the sources of revenues for Southern Company, each traditional electric operating company, and Southern Power, see Item 7 herein and Note 1 to the financial statements under "Revenues – Traditional Electric Operating Companies" and " – Southern Power" and Note 4 to the financial statements in Item 8 herein.
As of December 31, 2025, there were 62 electric cooperative distribution systems operating in the territories in which the traditional electric operating companies provide electric service at retail or wholesale.
PowerSouth is a generating and transmitting cooperative selling power to several distributing cooperatives, municipal systems, and other customers in south Alabama. As of December 31, 2025, PowerSouth owned generating units with more than 2,300 MWs of nameplate capacity, including an undivided 8.16% ownership interest in Alabama Power's Plant Miller Units 1 and 2. See PROPERTIES – "Electric – Jointly-Owned Facilities" in Item 2 herein and Note 5 to the financial statements under "Joint Ownership Agreements" in Item 8 herein for additional information.
In accordance with an agreement executed in 2021, Alabama Power began providing approximately 100 MWs of year-round capacity service to PowerSouth on February 1, 2024.
In 2021, Alabama Power and PowerSouth began operations under a coordinated planning and operations agreement, with a minimum term of 10 years. The agreement includes combined operations (including joint commitment and dispatch) and real-time energy sales and purchases and is expected to create energy cost savings and enhanced system reliability for both parties. Projected revenues are expected to offset any increased administrative costs incurred by Alabama Power. Under the agreement, Alabama Power has the right to participate in a portion of PowerSouth's future incremental load growth.
Alabama Power also has a separate agreement with PowerSouth involving interconnection between their systems. The delivery of capacity and energy from PowerSouth to certain distributing cooperatives in the service territory of Alabama Power is governed by the Southern Company/PowerSouth Network Transmission Service Agreement. The rates for this service to PowerSouth are on file with the FERC.
OPC is an EMC owned by its 38 retail electric distribution cooperatives, which provide retail electric service to customers in Georgia. OPC provides wholesale electric power to its members through its generation assets, some of which are jointly owned
I-7

    Table of Contents                                Index to Financial Statements
with Georgia Power, and power purchased from other suppliers. OPC and the 38 retail electric distribution cooperatives are members of Georgia Transmission Corporation, an EMC (GTC), which provides transmission services to its members and third parties. See PROPERTIES – "Electric – Jointly-Owned Facilities" in Item 2 herein and Note 5 to the financial statements under "Joint Ownership Agreements" in Item 8 herein for additional information regarding Georgia Power's jointly-owned facilities.
Mississippi Power has an interchange agreement with Cooperative Energy, a generating and transmitting cooperative, pursuant to which various services are provided. Cooperative Energy also has a 10-year network integration transmission service agreement with SCS for transmission service to certain delivery points on Mississippi Power's transmission system through March 31, 2031. See Note 2 to the financial statements under "Mississippi Power – Municipal and Rural Associations Tariff" in Item 8 herein for information on a separate shared service agreement between Mississippi Power and Cooperative Energy.
As of December 31, 2025, there were 72 municipally-owned electric distribution systems operating in the territory in which the traditional electric operating companies provide electric service at retail or wholesale.
As of December 31, 2025, 48 municipally-owned electric distribution systems and one county-owned system received their requirements through MEAG Power. MEAG Power serves these requirements from self-owned generation facilities, some of which are jointly-owned with Georgia Power, and purchases from other resources. MEAG Power also has a pseudo scheduling and services agreement with Georgia Power. Dalton serves its requirements from self-owned generation facilities, some of which are jointly-owned with Georgia Power, and through purchases from Southern Power through a service agreement. See PROPERTIES – "Electric – Jointly-Owned Facilities" in Item 2 herein and Note 5 to the financial statements under "Joint Ownership Agreements" in Item 8 herein for additional information.
Georgia Power has entered into substantially similar agreements with GTC, MEAG Power, and Dalton providing for the establishment of an integrated transmission system to carry the power and energy of all parties. The agreements require an investment by each party in the integrated transmission system in proportion to its respective share of the aggregate system load. See PROPERTIES – "Electric – Jointly-Owned Facilities" in Item 2 herein for additional information.
Southern Power has PPAs with Georgia Power, investor-owned utilities, IPPs, municipalities, electric cooperatives, and other load-serving entities, as well as commercial and industrial customers. See "The Southern Company System – Southern Power" herein and MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL – "Southern Power's Power Sales Agreements" in Item 7 herein for additional information.
SCS, acting on behalf of the traditional electric operating companies, also has a contract with SEPA providing for the use of the traditional electric operating companies' facilities at government expense to deliver to certain cooperatives and municipalities, entitled by federal statute to preference in the purchase of power from SEPA, quantities of power equivalent to the amounts of power allocated to them by SEPA from certain U.S. government hydroelectric projects.
Southern Company Gas
Southern Company Gas is engaged in the distribution of natural gas in four states through the natural gas distribution utilities. The natural gas distribution utilities construct, manage, and maintain intrastate natural gas pipelines and distribution facilities. Details of the natural gas distribution utilities at December 31, 2025 are as follows:
UtilityStateNumber of customersApproximate miles of pipe
(in thousands)
Nicor GasIllinois2,294 33.8 
Atlanta Gas LightGeorgia1,733 36.4 
Virginia Natural GasVirginia316 5.9 
Chattanooga GasTennessee73 1.8 
Total4,416 77.9 
For information relating to the sources of revenue for Southern Company Gas, see Item 7 herein and Note 1 to the financial statements under "Revenues – Southern Company Gas" and Note 4 to the financial statements in Item 8 herein.
Competition
Electric
The electric utility industry in the United States is continuing to evolve as a result of regulatory, projected demand requirements, and competitive factors. The competition for retail energy sales among competing suppliers of energy is influenced by various factors, including price, availability, technological advancements, service, and reliability. These factors are, in turn, affected by, among other influences, regulatory, political, and environmental considerations, taxation, and supply.
I-8

    Table of Contents                                Index to Financial Statements
The retail service rights of all electric suppliers in the state of Georgia are regulated by the Territorial Electric Service Act of 1973. Pursuant to standards set forth in this Act, the Georgia PSC has assigned substantially all of the land area in the state to a supplier. Notwithstanding such assignments, this Act provides that any new customer locating outside of 1973 municipal limits and having a connected load of at least 900 KWs may exercise a one-time choice for the life of the premises to receive electric service from the supplier of its choice.
Pursuant to the 1956 Utility Act, the Mississippi PSC issued "Grandfather Certificates" of public convenience and necessity to Mississippi Power and to six distribution rural cooperatives operating in southeastern Mississippi, then served in whole or in part by Mississippi Power, authorizing them to distribute electricity in certain specified geographically described areas of the state. The six cooperatives serve approximately 325,000 retail customers in a certificated area of approximately 10,300 square miles. In areas included in a "Grandfather Certificate," the utility holding such certificate may extend or maintain its electric system subject to certain regulatory approvals; extensions of facilities by such utility, or extensions of facilities into that area by other utilities, may not be made unless the Mississippi PSC grants a CPCN. Areas included in a CPCN that are subsequently annexed to municipalities may continue to be served by the holder of the CPCN, irrespective of whether it has a franchise in the annexing municipality. On the other hand, the holder of the municipal franchise may not extend service into such newly annexed area without authorization by the Mississippi PSC.
Generally, the traditional electric operating companies have experienced, and expect to continue to experience, competition in their respective retail service territories in varying degrees from the development and deployment of alternative energy sources such as self-generation (as described below) and distributed generation technologies, as well as other factors. Further technological advancements or the implementation of policies in support of alternative energy sources may result in further competition.
Southern Power competes with investor-owned utilities, IPPs, and others for wholesale energy sales across various U.S. utility markets. The needs of these markets are driven by the demands of end users and the generation available. Southern Power's success in wholesale energy sales is influenced by various factors including reliability and availability of Southern Power's plants, availability of transmission to serve the demand, price, and Southern Power's ability to contain costs.
As of December 31, 2025, Alabama Power had cogeneration contracts in effect with seven industrial customers. Under the terms of these contracts, Alabama Power purchases excess energy generated by such companies. During 2025, Alabama Power purchased approximately 83 million KWHs from such companies. The related costs were immaterial.
As of December 31, 2025, Georgia Power had contracts in effect to purchase alternative energy generation from 40 IPPs within the state of Georgia. During 2025, Georgia Power purchased 8.2 billion KWHs from such companies at a cost of $363 million. Georgia Power also has PPAs for electricity at cogeneration facilities with six industrial customers. Payments are subject to reductions for failure to meet minimum capacity output. During 2025, Georgia Power purchased 533 million KWHs at a cost of $50 million from these facilities.
As of December 31, 2025, Mississippi Power had a cogeneration agreement in effect with one of its industrial customers. Under the terms of this contract, Mississippi Power purchases any excess generation. During 2025, Mississippi Power did not make any such purchases.
Natural Gas
Southern Company Gas' natural gas distribution utilities do not compete with other distributors of natural gas in their exclusive franchise territories but face competition from other energy products. Their principal competitors are electric utilities and fuel oil and propane providers serving the residential, commercial, and industrial markets in their service areas for customers who are considering switching to or from a natural gas appliance.
Competition for heating as well as general household and small commercial energy needs generally occurs at the initial installation phase when the customer or builder makes decisions as to which types of equipment to install. Customers generally use the chosen energy source for the life of the equipment.
Customer demand for natural gas could be affected by numerous factors, including:
changes in the availability or price of natural gas and other forms of energy;
general economic conditions;
energy conservation, including state-supported energy efficiency programs;
legislation and regulations, including certain bans on the use of natural gas in new or existing construction and electrification initiatives;
the cost and capability to convert from natural gas to alternative energy products; and
technological or regulatory changes resulting in displacement or replacement of natural gas appliances.
I-9

    Table of Contents                                Index to Financial Statements
Southern Company Gas has natural gas-related programs that generally emphasize natural gas as the fuel of choice for customers and seek to expand the use of natural gas through a variety of promotional activities. In addition, Southern Company Gas partners with third-party entities to market the benefits of natural gas appliances.
Seasonality and Demand
The demand for electric power and natural gas supply is affected by seasonal differences in the weather. During normal weather conditions, the Southern Company system's electric power sales peak during both the summer and winter. In most of the areas Southern Company Gas serves, natural gas demand peaks during the winter. As a result, the overall operating results of the Registrants in the future may fluctuate substantially on a seasonal basis. In addition, the Subsidiary Registrants have historically sold less power and natural gas when weather conditions are milder.
See MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL – "General" and – RESULTS OF OPERATIONS – "Southern Company Gas" in Item 7 herein for information regarding trends in market demand for electricity and natural gas and the impact of seasonality on Southern Company Gas' business, respectively.
Regulation
States
The traditional electric operating companies and the natural gas distribution utilities are subject to the jurisdiction of their respective state PSCs or applicable state regulatory agencies. These regulatory bodies have broad powers of supervision and regulation over public utilities operating in the respective states, including their rates, service regulations, sales of securities (except for the Mississippi PSC), and, in the cases of the Georgia PSC and the Mississippi PSC, in part, retail service territories. See "Territory and Customers Served by the Southern Company System" and "Rate Matters" herein for additional information.
Federal Power Act
The traditional electric operating companies, Southern Power Company and certain of its generation subsidiaries, and SEGCO are all public utilities engaged in wholesale sales of energy in interstate commerce and, therefore, are subject to the rate jurisdiction of the FERC under the Federal Power Act. In addition, the traditional electric operating companies and SEGCO are subject to the financial and accounting jurisdiction of the FERC under the Federal Power Act. The FERC must approve certain financings and allows an "at cost standard" for services rendered by system service companies such as SCS and Southern Nuclear. The FERC is also authorized to establish regional reliability organizations which enforce reliability standards, address impediments to the construction of transmission, and prohibit manipulative energy trading practices.
Alabama Power and Georgia Power are also subject to the provisions of the Federal Power Act or the earlier Federal Water Power Act applicable to licensees with respect to their hydroelectric developments. As of December 31, 2025, among the hydroelectric projects subject to licensing by the FERC are 14 existing Alabama Power generating stations having an aggregate installed capacity of 1.7 million KWs and 15 existing Georgia Power generating stations and one generating station partially owned by Georgia Power, with a combined aggregate installed capacity of 1.1 million KWs.
In 2013, the FERC issued a new 30-year license to Alabama Power for Alabama Power's seven hydroelectric developments on the Coosa River (Weiss, Henry, Logan Martin, Lay, Mitchell, Jordan, and Bouldin). Alabama Power filed a petition requesting rehearing of the FERC order granting the relicense seeking revisions to several conditions of the license. In 2016, the FERC issued an order granting in part and denying in part Alabama Power's rehearing request. American Rivers and Alabama Rivers Alliance also filed multiple appeals of the FERC's 2013 order for the new 30-year license, and, in 2018, the U.S. Court of Appeals for the D.C. Circuit vacated the order and remanded the proceeding to the FERC. Alabama Power continues to operate the Coosa River developments under annual licenses issued by the FERC.
In 2021, Alabama Power filed an application with the FERC to relicense the Harris Dam project on the Tallapoosa River. The original Harris Dam project license expired on November 30, 2023, and, in December 2023, the FERC issued an annual license for the continued operation of the Harris Dam project. The Harris Dam project will operate under annual licenses until a new long-term license is issued, which is expected by the fourth quarter 2026.
In 2018, Georgia Power filed applications to surrender the Langdale and Riverview hydroelectric projects on the Chattahoochee River upon their license expirations on December 31, 2023, as they were inoperable by 2009. Georgia Power is currently awaiting the FERC surrender order, which is expected to include dam removal obligations and other post-dam removal activities such as monitoring and riverbank restoration activities.
In September 2024, Georgia Power received a new 40-year FERC license for the Lloyd Shoals project on the Ocmulgee River.
Georgia Power and OPC have a license, expiring on December 31, 2026, for the Rocky Mountain project, a pure pumped storage facility of 903,000 KW installed capacity. In December 2024, OPC, as an agent for co-licensees of the project, filed an
I-10

    Table of Contents                                Index to Financial Statements
application with the FERC to relicense the project. See PROPERTIES – "Electric – Jointly-Owned Facilities" in Item 2 herein for additional information.
Licenses for all projects, excluding those discussed above, expire in the years 2034-2066 for Alabama Power's projects and in the years 2034-2064 for Georgia Power's projects.
Upon or after the expiration of each license, the U.S. government, by act of Congress, may take over the project or the FERC may relicense the project either to the original licensee or to a new licensee. In the event of takeover or relicensing to another, the original licensee is to be compensated in accordance with the provisions of the Federal Power Act, such compensation to reflect the net investment of the licensee in the project, not in excess of the fair value of the property, plus reasonable damages to other property of the licensee resulting from the severance therefrom of the property. The FERC may grant relicenses subject to certain requirements that could result in additional costs.
The ultimate outcome of these matters cannot be determined at this time.
Nuclear Regulation
Alabama Power, Georgia Power, and Southern Nuclear are subject to regulation by the NRC. The NRC is responsible for licensing and regulating nuclear facilities and materials and for conducting research in support of the licensing and regulatory process, as mandated by the Atomic Energy Act of 1954, as amended; the Energy Reorganization Act of 1974, as amended; and the Nuclear Nonproliferation Act of 1978, as amended; and in accordance with the National Environmental Policy Act of 1969, as amended, and other applicable statutes. These responsibilities also include protecting public health and safety, protecting the environment, protecting and safeguarding nuclear materials and nuclear power plants in the interest of national security, and assuring conformity with antitrust laws.
The NRC licenses for Georgia Power's Plant Hatch Units 1 and 2 expire in 2034 and 2038, respectively. On May 15, 2025, Southern Nuclear submitted a subsequent license renewal application to the NRC seeking to renew both units' operating licenses for an additional 20 years (through 2054 and 2058 for Units 1 and 2, respectively). The NRC's decision on this application is anticipated by the end of the second quarter 2026.
The NRC licenses for Alabama Power's Plant Farley Units 1 and 2 expire in 2037 and 2041, respectively. Southern Nuclear has notified the NRC of its intent to seek to renew the plant's licenses for an additional 20 years (through 2057 and 2061 for Units 1 and 2, respectively). The subsequent license renewal application is projected to be submitted by the second quarter 2027.
The NRC licenses for Georgia Power's Plant Vogtle Units 1, 2, 3, and 4 expire in 2047, 2049, 2062, and 2063, respectively.
See Notes 3 and 6 to the financial statements under "Nuclear Insurance" and "Nuclear Decommissioning," respectively, in Item 8 herein for additional information.
Environmental Laws and Regulations
See "Construction Programs" herein, MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL – "Environmental Matters" in Item 7 herein, and Note 3 to the financial statements under "Environmental Remediation" and Note 6 to the financial statements in Item 8 herein for information concerning environmental laws and regulations impacting the Registrants.
Rate Matters
Rate Structure and Cost Recovery Plans
Electric
The rates and service regulations of the traditional electric operating companies are uniform for each class of service throughout their respective retail service territories. Rates for residential electric service are generally of the block type based upon KWHs used and include minimum charges. Residential and other rates contain separate customer charges. Rates for commercial service are also of the block type and, for large customers, the billing demand is generally used to determine capacity and minimum bill charges. These large customers' rates are generally based upon usage by the customer and include rates with special features to encourage off-peak usage. Additionally, Alabama Power and Mississippi Power are generally allowed by their respective state PSCs to negotiate the terms and cost of service to large customers, subject to final state PSC approval.
The traditional electric operating companies recover certain costs through a variety of forward-looking, cost-based rate mechanisms. Fuel and net purchased energy costs are recovered through specific fuel cost recovery provisions. These fuel cost recovery provisions are adjusted to reflect increases or decreases in such costs as needed or on schedules as required by the respective PSCs. Approved compliance, storm damage, and certain other costs are recovered at Alabama Power and Mississippi Power through specific cost recovery mechanisms approved by their respective PSCs. Certain similar costs at Georgia Power
I-11

    Table of Contents                                Index to Financial Statements
are recovered through various base rate tariffs as approved by the Georgia PSC. Costs not recovered through specific cost recovery mechanisms are recovered at Alabama Power and Mississippi Power through annual, formulaic cost recovery proceedings and at Georgia Power through periodic base rate proceedings.
See Note 2 to the financial statements in Item 8 herein for a discussion of rate matters and certain cost recovery mechanisms. Also see "Integrated Resource Planning" herein for additional information.
The traditional electric operating companies and Southern Power Company and certain of its generation subsidiaries are authorized by the FERC to sell power to non-affiliates, including short-term opportunity sales, at market-based prices. Specific FERC approval must be obtained with respect to a market-based contract with an affiliate.
Mississippi Power provides service under long-term contracts with rural electric cooperative associations and a municipality located in southeastern Mississippi which are subject to regulation by the FERC. The contracts with these wholesale customers represented 12.9% of Mississippi Power's total operating revenues in 2025.
Natural Gas
Southern Company Gas' natural gas distribution utilities are subject to regulation and oversight by their respective state regulatory agencies. Rates charged to customers vary according to customer class (residential, commercial, or industrial) and rate jurisdiction. These agencies approve rates designed to provide the opportunity to generate revenues to recover all prudently-incurred costs, including a return on rate base sufficient to pay interest on debt and provide a reasonable ROE.
With the exception of Atlanta Gas Light, the earnings of the natural gas distribution utilities can be affected by customer consumption patterns that are largely a function of price levels for natural gas and general economic conditions that may impact customers' ability to pay for natural gas consumed. The natural gas distribution utilities have weather or revenue normalization mechanisms that mitigate revenue fluctuations from customer consumption changes. Atlanta Gas Light operates in a deregulated environment in which Marketers rather than a traditional utility sell natural gas to end-use customers and earns revenue by charging rates to its customers based primarily on monthly fixed charges that are set by the Georgia PSC.
In addition to natural gas cost recovery mechanisms, other cost recovery mechanisms and regulatory riders, which vary by utility, allow recovery of certain costs, such as those related to infrastructure replacement programs as well as environmental remediation, energy efficiency plans, and bad debts.
See Note 2 to the financial statements under "Southern Company Gas" in Item 8 herein for a discussion of rate matters and certain cost recovery mechanisms.
Integrated Resource Planning
Each of the traditional electric operating companies continually evaluates its electric generating resources in order to ensure that it maintains a cost-effective and reliable mix of resources to meet the existing and future demand requirements of its customers. In addition, each year the Southern Company system engages in a scenario planning process, developing scenarios which look out over a 30-year horizon. For 2025, scenarios considered a range of views regarding pressure on CO2 emissions, load growth, supply options, and fuel prices. Views regarding future pressure on CO2 emissions include a fee beginning between $0 and $50 per metric ton rising above inflation over the 30-year planning period. See MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL – "Environmental Matters" in Item 7 herein for a discussion of existing and potential environmental regulations that may impact the future generating resource needs of the traditional electric operating companies, as well as a discussion of the Southern Company system's continued generating fleet transition.
Alabama Power
Triennially, Alabama Power provides an IRP report to the Alabama PSC. This report overviews Alabama Power's resource planning process and contains information that serves as the foundation for certain decisions affecting Alabama Power's portfolio of supply-side and demand-side resources. The IRP report facilitates Alabama Power's ability to provide reliable and cost-effective electric service to customers, while accounting for the risks and uncertainties inherent in planning for resources sufficient to meet expected customer demand. Under State of Alabama law, a CCN must be obtained from the Alabama PSC before Alabama Power constructs any new generating facility, unless such construction is an ordinary extension of an existing system in the usual course of business. Alabama Power provided its most recent IRP to the Alabama PSC during 2025. On August 13, 2025, the Alabama PSC approved a CCN authorizing Alabama Power to complete the acquisition of the Lindsay Hill Generating station. The transaction closed on September 30, 2025. See Note 2 to the financial statements under "Alabama Power – Rate CNP New Plant" in Item 8 herein for additional information.
I-12

    Table of Contents                                Index to Financial Statements
Georgia Power
Triennially, Georgia Power must file an IRP with the Georgia PSC that specifies how it intends to meet the future electric service needs of its customers through a combination of demand-side and supply-side resources. The Georgia PSC, under state law, must certify any new demand-side or supply-side resources serving retail customers. Once certified, the lesser of actual or certified construction costs and purchased power costs is recoverable through rates. Georgia Power may request cost recovery for costs greater than those approved by the Georgia PSC if proven to be prudent and reasonable. Certified costs may be excluded from recovery only on the basis of fraud, concealment, failure to disclose a material fact, imprudence, or criminal misconduct. In April 2024, the Georgia PSC approved Georgia Power's 2023 IRP Update as modified by a stipulation among Georgia Power, the staff of the Georgia PSC, and certain intervenors, which limited recovery of certain costs over the certified amount for Plant Yates Units 8, 9, and 10. On July 15, 2025, the Georgia PSC approved Georgia Power's 2025 IRP, as modified by a stipulation among Georgia Power, the staff of the Georgia PSC, and certain intervenors.
On September 4, 2025, the Georgia PSC approved Georgia Power's request to certify a Georgia Power-owned battery energy storage facility with a capacity of 200 MWs and a projected COD in 2027. On December 19, 2025, the Georgia PSC approved Georgia Power's request, as modified by a stipulation between Georgia Power and the staff of the Georgia PSC, to certify resources totaling 9,885 MWs with projected CODs or delivery commencement dates between 2027 and 2030. As included in the 2022 IRP final order, on February 11, 2026, Georgia Power initiated an RFP for up to 500 MWs of capacity for battery energy storage facilities with projected CODs or delivery commencement dates by 2031.
See Note 2 to the financial statements under "Georgia Power – Integrated Resource Plans" and " – Rate Plans" in Item 8 herein for additional information.
Mississippi Power
Triennially, Mississippi Power must file an IRP with the Mississippi PSC, as well as an update at approximately the mid-point of the three-year cycle. The IRP must include long-term plans to best meet the needs of electric utility customers through a combination of demand-side and supply-side resources and considering transmission needs. The IRP filing is not intended to supplant or replace the Mississippi PSC's existing regulatory processes for petition and approval of CPCNs for new generating resources. In April 2024, Mississippi Power filed its 2024 IRP with the Mississippi PSC. The Mississippi PSC did not note any deficiencies within the prescribed 120-day review period; therefore, the filing was concluded. On January 9, 2025, Mississippi Power notified the Mississippi PSC of its intent to extend the retirement date of Plant Daniel Unit 2 and potentially extend the retirement dates of other fossil steam units beyond their current 2028 retirement dates in order to serve recently signed economic development loads of approximately 600 MWs. Mississippi Power has since acquired FP&L's 50% ownership interest in Plant Daniel Units 1 and 2. In 2026, Mississippi Power is expected to file an update to its 2024 IRP with the Mississippi PSC. Mississippi Power must also file an annual report on energy delivery improvements, the latest of which was filed in November 2025. See Note 2 to the financial statements under "Mississippi Power – Integrated Resource Plans" and " – Plant Daniel" in Item 8 herein for additional information.
Human Capital
Southern Company system management is committed to attracting, developing, and retaining a sustainable workforce and aims to foster a culture of belonging where all employees feel valued. The Southern Company system's values – safety first, intentional inclusion, act with integrity, and superior performance – guide behavior. The Southern Company system had approximately 29,800 employees on its payroll at December 31, 2025 comprised of the following:
   At December 31, 2025(*)
Alabama Power6,100
Georgia Power7,700
Mississippi Power1,100
Southern Power500
Southern Company Gas5,000
SCS4,800
Southern Nuclear3,700
PowerSecure and other900
Total Southern Company system29,800
(*)Numbers are rounded to 100s.
I-13

    Table of Contents                                Index to Financial Statements
All Southern Company system employees are located within the United States. Part-time employees represent less than 1% of total employees.
Southern Company system management values an inclusive and innovative workforce. Southern Company's subsidiaries have policies, programs, and processes to help ensure that all employees are included and fairly treated across all job levels. The Southern Company system encourages different ideas and points of view, and its Code of Ethics affirms its expectation that employees treat each other with fairness, respect, and dignity. The Southern Company Board of Directors and management believe that diverse perspectives and experiences are important to help inform management of risk, business strategy, and innovation. Southern Company management leads the Southern Company system's intentional inclusion initiatives and employee recruitment, retention, and development efforts. The Board, principally through its Compensation and Talent Development Committee, oversees these efforts.
Southern Company system management supports various employee-led groups to provide formal and informal networks of colleagues that can help promote belonging, improve employee retention, and support development.
Southern Company system management recognizes the importance of attracting and retaining an appropriately qualified workforce. Southern Company system management uses a variety of strategies to attract and retain talent, including working with high schools, technical schools, universities, and military installations to fill many entry-level positions. The recruiting strategy also includes partnerships with professional associations and local communities to recruit mid-career talent. The addition of external hires augments the existing workforce to meet changing business needs, address any critical skill gaps, and supplement and enhance the Southern Company system's talent pipeline.
The Southern Company system supports the well-being of its employees through a comprehensive total rewards strategy with three measurable categories: physical, financial, and emotional well-being. The Southern Company system provides competitive salaries, annual incentive awards for nearly all employees, and health, welfare, and retirement benefits. The Southern Company system has a qualified defined benefit, trusteed pension plan and a qualified defined contribution, trusteed 401(k) plan which provides a competitive company-matching contribution. Substantially all Southern Company system employees are eligible to participate in these plans. There are differences between the pension plan benefit formulas based on when and by which subsidiary an employee is hired. See Note 11 to the financial statements in Item 8 herein for additional information. At December 31, 2025, the average age of the Southern Company system employees was 44 and the average tenure with the Southern Company system was 13 years. Turnover rate, calculated as the percent of employees that terminated employment with the Southern Company system, including voluntary and involuntary terminations and retirements, divided by total employees, was 6.3%.
Southern Company system management is committed to developing talent and helping employees succeed by providing development opportunities along with purposeful people moves as part of individual development plans and succession planning processes. The Southern Company system has multiple development programs, including programs targeted toward all employees, high potential employees, first-level managers, managers of managers, and executives. Additionally, Southern Company system management strives to deliver consistent needs-based training and solutions as workplace needs evolve.
Southern Company system management believes the safety of employees and customers is paramount. The Southern Company system seeks to meet or exceed applicable laws and regulations while continually improving its safety technologies and processes. The Southern Company System Safety and Health Council, which includes leaders from each Registrant, works collectively across the Southern Company system to provide safety leadership, share learning, work collaboratively to address safety-related issues, and govern the consistency of safety programs. The safety programs are focused on the prevention and elimination of life-altering events, serious injuries, and fatalities. These programs include continuous process improvements to put critical controls in place to prevent serious injuries, promote learning, and implement appropriate corrective actions. Southern Company's safety metrics include the serious injury rate and the number of fatalities. The serious injury rate represents the number of incidents per 100 employees and is calculated by taking the number of serious injuries multiplied by 200,000 workhours and dividing by the total employee workhours during the year. A serious injury is one that is life-threatening or life-changing (temporary or permanent) for the employee. Serious injury examples, as defined by applicable safety regulators, include fatalities, amputations, trauma to organs, certain bone fractures, certain soft tissue injuries, severe burns, and eye injuries. In 2025, the Southern Company system had a serious injury rate of 0.03 and no fatal injuries.
The Southern Company system also has longstanding relationships with labor unions. The traditional electric operating companies, Southern Nuclear, and the natural gas distribution utilities have separate agreements with local unions of the IBEW, which generally apply to operating, maintenance, and construction employees. These agreements cover wages, benefits, terms of the pension plans, working conditions, and procedures for handling grievances and arbitration. The Southern Company system also partners with the IBEW to provide training programs to develop technical skills and career opportunities.
At December 31, 2025, approximately 32% of Southern Company system employees were covered by agreements with unions, with agreements expiring between 2026 and 2030.
I-14

    Table of Contents                                Index to Financial Statements
Item 1A. RISK FACTORS
In addition to the other information in this Form 10-K, including MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL in Item 7, and other documents filed by Southern Company and/or its subsidiaries with the SEC, the following factors should be carefully considered in evaluating Southern Company and its subsidiaries. Such factors could affect actual results and cause results to differ materially from those expressed in any forward-looking statements made by, or on behalf of, Southern Company and/or its subsidiaries. The risk factors discussed below could adversely affect a Registrant's results of operations, financial condition, liquidity, and cash flow, as well as cause reputational damage.
UTILITY REGULATORY, LEGISLATIVE, AND LITIGATION RISKS
Southern Company and its subsidiaries are subject to substantial federal, state, and local governmental regulation, including with respect to rates. Compliance with current and future legal and regulatory requirements and procurement of necessary approvals, permits, and certificates may result in substantial costs to Southern Company and its subsidiaries. The reduction, elimination, or expiration of government incentives for, or regulations mandating or restricting the use of, renewable energy projects could reduce demand for renewable energy projects and harm the Registrants' businesses.
Laws and regulations govern the terms and conditions of the services the Southern Company system offers, protection of critical electric infrastructure assets, transmission planning, reliability, pipeline safety, interaction with wholesale markets and retail customers, and relationships with affiliates, among other matters. The Registrants' businesses are subject to regulatory regimes which could result in substantial monetary penalties if a Registrant is found to be noncompliant.
The traditional electric operating companies, and the power industry in general, have experienced a period of rising costs and projected capital expenditures, especially with respect to infrastructure investments, which is projected to continue for the foreseeable future. The profitability of the traditional electric operating companies' and the natural gas distribution utilities' businesses is largely dependent on their ability, through the rates that they are permitted to charge, to recover their costs and earn a reasonable rate of return on their invested capital. The traditional electric operating companies and the natural gas distribution utilities seek to recover their costs, including a reasonable return on invested capital, through their retail rates, which must be approved by the applicable state PSC or other applicable state regulatory agency. Such regulators, in a rate proceeding, may alter the timing or amount of certain costs for which recovery is allowed or modify the current authorized rate of return; rate refunds may also be required. The current period of rising costs and increased projected capital expenditures could result in increased resistance to authorizing cost recovery. Furthermore, the outcome of any rate proceeding could be impacted by a variety of factors, including the level of opposition from intervenors, potential impacts to customers, including affordability concerns, and past or future changes in the political, regulatory, economic, or legislative environment. See Note 2 to the financial statements under "Alabama Power" for additional information regarding the Alabama PSC's approval of a plan to keep retail rates stable through 2027, under "Georgia Power – Rate Plans" for additional information regarding the Georgia PSC's approval of a settlement agreement to extend the 2022 ARP through December 31, 2028, with no adjustments to base rates except for storm damage costs incurred through December 31, 2025, and under "Southern Company Gas – Infrastructure Replacement Programs and Capital Projects – Nicor Gas" and " – Rate Proceedings – Nicor Gas" in Item 8 herein for additional information regarding certain disallowances at Nicor Gas.
Additionally, the rates charged to wholesale customers by the traditional electric operating companies and Southern Power and the rates charged to natural gas transportation customers by Southern Company Gas' pipeline investments are subject to review by the FERC. Changes to Southern Power's and the traditional electric operating companies' ability to conduct business pursuant to FERC market-based rate authority could affect wholesale rates. Also, while a small percentage of transmission costs are recovered through wholesale electric tariffs, the majority are recovered through retail rates. Transmission planning and the resulting grid improvements could be impacted by FERC policy changes as well as North American Electric Reliability Corporation planning standard changes.
The IRA, among other items, imposes a 15% CAMT on adjusted financial statement income, as defined in the law, and is subject to the issuance of additional guidance by the U.S. Treasury and the IRS. Any rate recovery by the traditional electric operating companies or the natural gas distribution utilities subject to the CAMT will be determined pursuant to the regulatory processes of the FERC, state PSCs, or other applicable state regulatory agencies. There is no assurance, however, that such tax will be recoverable through the applicable regulatory process.
The OBBB was signed into law on July 4, 2025. The OBBB, among other things, materially changed the requirements for most of the federal renewable energy incentives. The Registrants are still assessing the impacts of the OBBB on tax incentives for renewable energy projects. Any loss of, reduction in, or impacts on tax incentives, including transferability of tax credits, due to the OBBB could have a material adverse effect on the Registrants. See MANAGEMENT'S DISCUSSION AND ANALYSIS –
I-15

    Table of Contents                                Index to Financial Statements
FUTURE EARNINGS POTENTIAL – "Income Tax Matters – Federal Tax Legislation" in Item 7 herein for additional information.
The Registrants are unable to predict changes in laws or regulations, regulatory guidance, legal interpretations, policy positions, and implementation actions that may occur in the future. The impact of any future revision or changes in interpretations or application of existing laws and regulations or the adoption of new laws and regulations applicable to Southern Company or any of its subsidiaries is uncertain. Changes in laws and regulations, the imposition of additional legal or regulatory requirements, changes in application of existing laws and regulations and in enforcement practices of regulators, as well as associated litigation, or penalties imposed for noncompliance with existing laws or regulations could influence the operating environment of the Southern Company system and may result in substantial costs.
The Southern Company system's costs of compliance with environmental laws and regulations and satisfying related AROs are significant.
The Southern Company system's operations are regulated by state and federal environmental agencies through a variety of laws and regulations governing air, GHGs, water, land, avian and other wildlife and habitat protection, and other natural resources. Compliance with existing environmental requirements involves significant capital and operating costs including the settlement of AROs, a major portion of which is expected to be recovered through retail and wholesale rates. There is no assurance, however, that all such costs will be recovered. The Registrants expect future compliance expenditures will continue to be significant.
The EPA has adopted and is implementing regulations governing air and GHG emissions under the Clean Air Act and water quality under the Clean Water Act. The EPA and certain states have also adopted and continue to propose regulations governing the disposal and management of CCR at power plant sites under the Resource Conservation and Recovery Act and applicable state laws. The cost estimates for AROs related to the disposal of CCR are based on information using various assumptions related to closure and post-closure costs, timing of future cash outlays, inflation and discount rates, and the potential compliance methods. The traditional electric operating companies will continue to periodically update their ARO cost estimates and those updates could be material.
Additionally, environmental laws and regulations covering the handling and disposal of waste and release of hazardous substances could require the Southern Company system to incur substantial costs to clean up affected sites, including certain current and former operating sites, and locations subject to contractual obligations.
Litigation over environmental issues and claims of various types, including property damage, personal injury, and citizen enforcement of environmental requirements, has occurred throughout the United States. This litigation has included, but is not limited to, claims for damages alleged to have been caused by CO2 and other emissions, CCR, releases of regulated substances, alleged exposure to regulated substances, and/or requests for injunctive relief in connection with such matters.
Compliance with any new or revised environmental laws or regulations could affect many areas of operations for the Southern Company system. The Southern Company system's ultimate environmental compliance strategy and future environmental expenditures will depend on various factors, such as state adoption and implementation of requirements, the availability and cost of any deployed control technology, fuel prices, and the outcome of pending and/or future legal challenges. Compliance costs may result from the installation of additional environmental controls, closure and monitoring of CCR facilities, unit retirements and replacements, operational changes, or changing fuel sources for certain existing units, as well as related upgrades to the Southern Company system's transmission and distribution (electric and natural gas) systems. Environmental compliance spending over the next several years may differ materially from the amounts estimated and could adversely affect the Registrants if such costs cannot continue to be recovered on a timely basis. Further, increased costs that are recovered through regulated rates could contribute to reduced demand for electricity and natural gas. Additionally, many commercial and industrial customers may also be affected by existing and future environmental requirements, which for some may have the potential to reduce their demand for electricity or natural gas.
The Southern Company system may be exposed to regulatory and financial risks related to the impact of GHG legislation, regulation, and emission reduction goals.
Concern and activism about climate change continue and, as a result, demand for energy conservation and sustainable assets could further increase. The public holds diverse and often conflicting views on the use of fossil fuels which may subject the Registrants to adverse publicity in connection with their use or supply of fossil fuels. Additionally, costs associated with GHG legislation, regulation, and emission reduction goals could be significant and there is no assurance such costs would be fully recovered through regulated rates or PPAs.
The Southern Company system has processes for identifying, assessing, and responding to climate-related risks, including a scenario planning process that is used to inform resource planning decisions in the states in which the traditional electric
I-16

    Table of Contents                                Index to Financial Statements
operating companies operate. This process relies on information and assumptions from internal and external sources, which may or may not be accurate in predicting future outcomes.
Additional GHG policies, including legislation, may emerge requiring the United States to accelerate its transition to a lower GHG emitting economy. The ultimate impact will depend on various factors, such as state adoption and implementation of requirements, natural gas prices, the development, deployment, and advancement of relevant energy technologies, the ability to recover costs through existing ratemaking provisions, and the outcome of pending and/or future legal challenges.
Because natural gas is a fossil fuel with lower carbon content relative to other fossil fuels, future carbon constraints, including, but not limited to, the imposition of a carbon tax, may create additional demand for natural gas, both for production of electricity and direct use in homes and businesses. However, such demand may be tempered by legislation limiting the use of natural gas in certain circumstances, including use in new construction and certain household appliances. Additionally, efforts to electrify the transportation, building, and other sectors may result in higher electric demand and negatively impact natural gas demand. For example, beginning in 2024, Nicor Gas' regulator, the Illinois Commission, has conducted "future of natural gas" proceedings to explore the recommendations involved with decarbonization of the gas distribution system in Illinois. The Illinois Commission's final report is expected by the end of 2026. In addition, future GHG constraints, including those related to methane emissions, designed to minimize emissions from natural gas could likewise result in increased costs to the Southern Company system and affect the demand for natural gas as well as the prices charged to customers and the competitive position of natural gas.
Since 2018, Southern Company system management established GHG emissions reductions goals including an intermediate goal of 50% from 2007 levels by 2030 and a long-term goal of net zero by 2050. Due primarily to the projected electric load growth, current projections indicate it will be extremely challenging to meet the 2030 goal. Achievement of these goals is dependent on various factors, many of which the Southern Company system does not control, including load growth across the Southern Company system's service territory, including projected load growth from large load customers, energy policy and regulations, natural gas prices, customer demand for carbon-free energy, and the development and deployment of low- to no-GHG energy technologies. The strategy to achieve these goals also relies on continuing to economically transition the Southern Company system's generating fleet through a diverse portfolio of resources including low-carbon and carbon-free resources; making the necessary related investments in transmission and distribution systems; continuing to implement effective energy efficiency and demand response programs; implementing initiatives to reduce natural gas distribution emissions; continuing research and development with a focus on technologies that lower GHG emissions; and constructively engaging with policymakers, regulators, investors, customers, and other stakeholders to support outcomes leading to a net zero future. There is no guarantee that the Southern Company system will achieve these goals.
See MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL – "Environmental Matters – Environmental Laws and Regulations – Greenhouse Gases" in Item 7 herein for additional information.
OPERATIONAL RISKS
The financial performance of Southern Company and its subsidiaries may be adversely affected if the subsidiaries are unable to successfully operate their facilities or perform certain corporate functions.
The financial performance of Southern Company and its subsidiaries depends on the successful operation of the electric generation, transmission, and distribution facilities, natural gas distribution facilities, and distributed generation storage technologies and the successful performance of necessary corporate functions. There are many risks that could affect these matters, including operator error or failure of equipment or processes, accidents, operating limitations that may be imposed by environmental or other regulatory requirements or in connection with joint owner or joint venture arrangements, failure of performance by counterparties, labor disputes, physical attacks, fuel or material supply interruptions and/or shortages, transmission disruption or capacity constraints, including with respect to the Southern Company system's and third parties' transmission, storage, and transportation facilities, inability to maintain reliability consistent with customer expectations as the traditional electric operating companies add generation, transmission, and related infrastructure to meet projected electric demand growth, compliance with mandatory reliability standards, including mandatory cyber security standards, implementation of new technologies, technology system failures, cyber intrusions, environmental events, such as spills or releases, supply chain disruptions, inflation, and catastrophic events such as fires, including wildfires, land movement, earthquakes, explosions, floods, high winds, tornadoes, hurricanes and other storms, solar flares, droughts, future pandemic health events, wars, political unrest, or other similar occurrences.
I-17

    Table of Contents                                Index to Financial Statements
Operation of nuclear facilities involves inherent risks, including environmental, safety, health, regulatory, natural disasters, cyber intrusions, physical attacks, and financial risks, that could result in fines or the closure of the nuclear units owned by Alabama Power or Georgia Power and which may present potential exposures in excess of insurance coverage.
Alabama Power owns, and contracts for the operation of, two nuclear units and Georgia Power holds undivided interests in, and contracts for the operation of, six nuclear units. The eight units are operated by Southern Nuclear and represented approximately 22% and 36% of the total KWHs generated by Alabama Power and Georgia Power, respectively, in the year ended December 31, 2025. Nuclear facilities are subject to environmental, safety, health, operational, and financial risks such as: the potential harmful effects on the environment and human health and safety resulting from a release of radioactive materials; uncertainties with respect to the ability to dispose of spent nuclear fuel and the need for longer term on-site storage; uncertainties with respect to the technological and financial aspects of decommissioning nuclear plants at the end of licensed lives or license extensions and the ability to maintain and anticipate adequate capital reserves for decommissioning; limitations on the amounts and types of insurance commercially available to cover losses that might arise in connection with nuclear operations; and significant capital expenditures relating to maintenance, operation, security, and repair of these facilities.
Damages, decommissioning, or other costs could exceed the amount of decommissioning trusts or insurance coverage, including statutorily required nuclear incident insurance.
The NRC has broad authority under federal law to impose licensing and safety-related requirements for the operation of nuclear facilities. In the event of non-compliance, the NRC has the authority to impose fines and/or shut down any unit, depending upon its assessment of the severity of the situation, until compliance is achieved. NRC orders or regulations related to increased security measures and any future NRC safety requirements could require Alabama Power and Georgia Power to make substantial operating and capital expenditures at their nuclear plants. In addition, if a major nuclear incident were to occur, it could result in substantial costs to Alabama Power or Georgia Power and Southern Company. A major incident at a nuclear facility anywhere in the world could cause the NRC to require additional safety measures. Moreover, a major incident at any nuclear facility in the United States, including facilities owned and operated by third parties, could require Alabama Power and Georgia Power to make material contributory payments.
In addition, actual or potential threats of cyber intrusions or physical attacks could result in increased nuclear licensing or compliance costs.
Generation, transmission, and distribution of electricity and transportation and storage of natural gas involve risks that may result in accidents and other operating risks and costs and that may present potential exposures in excess of insurance coverage.
The Southern Company system's electric generation, transmission, and distribution and natural gas distribution and storage activities involve a variety of inherent hazards and operating risks, such as accidents, explosions, fires, mechanical problems, discharges or releases of toxic or hazardous substances or gases, and other environmental risks. These incidents could result in serious injury, loss of life, significant damage to property, environmental pollution, and disruption of the Southern Company system's operations. The location of electric generation, transmission, and distribution infrastructure and natural gas pipelines and underground natural gas storage facilities near populated areas could increase the level of damage and liability resulting from any incidents. Additionally, electric generation, transmission, and distribution infrastructure and natural gas pipelines, storage facilities, and other infrastructure are subject to various state and other regulatory requirements. Failure to comply with these requirements could result in substantial monetary penalties, which could exceed the amount of insurance coverage.
Physical attacks, both threatened and actual, could impact the ability of the Subsidiary Registrants to operate.
The Subsidiary Registrants face the risk of physical attacks, both threatened and actual, against their respective generation and storage facilities and the transmission and distribution infrastructure used to transport energy, which could negatively impact their ability to generate, transport, and deliver power, or otherwise operate their respective facilities, or, with respect to Southern Company Gas, its ability to distribute or store natural gas, or otherwise operate its facilities, in the most efficient manner or at all. Transmission and distribution infrastructure can be vulnerable to physical attack because it is often unmanned, widely dispersed, and located in isolated areas. The risk of physical attack may escalate during periods of heightened geopolitical tensions. In addition, physical attacks against third-party providers could have a similar effect on the Southern Company system.
Despite the implementation of robust security measures, all assets are potentially vulnerable to disability, failure, or unauthorized access due to human error, natural disaster, technological failure, or internal or external physical attack. If assets were to fail, be physically damaged, or be breached and were not restored in a timely manner, the affected Subsidiary Registrant may be unable to fulfill critical business functions. Insurance may not be adequate to cover any associated losses.
I-18

    Table of Contents                                Index to Financial Statements
An information security incident, including a cybersecurity breach, or the failure of, or inability to remotely access, one or more key technology systems, networks, or processes could impact the ability of the Registrants to operate.
The Subsidiary Registrants operate in highly regulated industries that require the continued operation of sophisticated technology systems and network infrastructure, which are part of interconnected systems. Because of the critical nature of the infrastructure and the technology systems' inherent vulnerability to disability or failure due to hacking, virus, denial of service, ransomware, act of war or terrorism, or other type of data security breach, the Registrants face a heightened risk of cyberattack. In addition, the increased use of smartphones, tablets, and other wireless devices, as well as remote working arrangements, may also increase the Registrants' data security risks. Portions of the Registrants' system data, architecture, and other materials may also be disclosed, either intentionally or unintentionally, to third parties and the public by regulators, employees, contractors, and vendors. This system information may be used by malicious actors to understand the Registrants' systems to prepare for a cyberattack. In addition, unpatched software or network vulnerabilities, including those resulting from the use of end-of-life operating systems, could be leveraged by an attacker.
Cyber actors, including those associated with foreign governments, have attacked and threatened to attack energy infrastructure. Various regulators have increasingly stressed that these attacks, including ransomware attacks, and attacks targeting utility systems and other critical infrastructure, are growing in sophistication, magnitude, and frequency. Use of generative artificial intelligence has also increased the frequency, scale, and sophistication of cyber attacks and increased the capability of less sophisticated actors. As generative artificial intelligence continues to evolve, new technologies and increased computing power could cause these trends to continue or exacerbate. Moreover, certain actors, such as nation-state and state-sponsored actors, can deploy significant resources and employ sophisticated methods to plan and carry out attacks. Risk of these attacks may escalate during periods of heightened geopolitical tensions, such as those caused by the war in Ukraine and conflicts in the Middle East.
The Registrants and their third-party vendors have been subject, and will likely continue to be subject, to attempts to gain unauthorized access to their technology systems and confidential data or to attempts to disrupt utility and related business operations. While there have been immaterial incidents of phishing, unauthorized access to technology systems, financial fraud, and disruption of remote access across the Southern Company system, there has been no material impact on the Registrants or their operations from these attacks. However, the Registrants cannot guarantee that security efforts will have the maturity to detect or prevent breaches, operational incidents, or other breakdowns of technology systems and network infrastructure, especially in the event the Registrants are targeted by a sophisticated attacker with significant resources, such as a nation-state or state-sponsored actor. Further, the Registrants do not have security visibility into all operational technology communications and processes, do not maintain completely exhaustive inventories of assets and applications, and do not centrally manage or monitor all technologies, applications, and environments, which could negatively affect preparation for, investigation of, or response to an information security incident. Accordingly, the Registrants cannot provide any assurance that information security incidents will not have a material adverse effect in the future.
In addition, in the ordinary course of business, Southern Company and its subsidiaries collect and retain sensitive information, including personally identifiable information about customers, employees, and stockholders, and other confidential information. In some cases, administration of certain functions may be outsourced to third-party service providers. Malicious actors may target these providers, as well as other vendors, to disrupt or compromise services and products. Such third-party vendors have been increasingly used as attack vectors in efforts to target critical infrastructure, including that of the Registrants. The Registrants cannot fully assess the security maturity of all third-party vendors and such vendors could fail to establish adequate risk management and information security measures with respect to their systems and/or could fail to timely notify the Registrants of an information security incident.
Internal or external cyberattacks may have wide-reaching impacts due to incomplete segmentation among network assets and/or reliance of segmented networks on a disrupted network, inhibit the affected Registrant's ability to fulfill critical business functions, including energy delivery service failures, compromise sensitive and other data, violate privacy laws, and lead to customer dissatisfaction. Any cyber breach or theft, damage, or improper disclosure of sensitive electronic data may also subject the affected Registrant to penalties and claims from regulators or other third parties. Any violations of applicable laws and regulations could lead to material losses, both financial and reputational. Insurance may not be adequate to cover any associated losses, and there is no assurance that such losses would be recovered through customer rates. Additionally, the cost and operational consequences of implementing, maintaining, and enhancing system protection measures are significant, and they could materially increase to address ever changing intense, complex, and sophisticated cyber risks.
The Southern Company system may not be able to obtain adequate natural gas, fuel supplies, and other resources required to operate the traditional electric operating companies' and Southern Power's electric generating plants or serve Southern Company Gas' natural gas customers.
SCS, on behalf of the traditional electric operating companies and Southern Power, purchases fuel for the Southern Company system's generation fleet from a diverse set of suppliers. Southern Company Gas' primary business is the distribution of natural
I-19

    Table of Contents                                Index to Financial Statements
gas through the natural gas distribution utilities. Natural gas is delivered daily from different regions of the country. This daily supply is complemented by natural gas supplies stored in both company-owned and third-party storage locations. To deliver this daily supply and stored natural gas, the Southern Company system has firm transportation capacity contracted with third-party interstate pipelines and Southern Company Gas also utilizes its own pipeline network. Disruption in the supply and/or delivery of fuel as a result of matters such as transportation delays, weather, labor relations, natural disasters, cyber or physical attacks, other force majeure events, environmental regulations affecting fuel suppliers, constraints on existing natural gas pipeline capacity or on construction of new natural gas pipelines, or changing economic conditions could limit the ability of the traditional electric operating companies and Southern Power to operate certain facilities, which could impact reliability and result in higher fuel and operating costs, and the ability of Southern Company Gas to serve its natural gas customers.
The traditional electric operating companies are also dependent on coal, and related coal supply contracts, for a portion of their electric generating capacity. The counterparties to coal supply contracts may not fulfill their obligations to supply coal because of financial or technical problems. In addition, the suppliers and/or railroads may be delayed in supplying or delivering or may not be required to supply or deliver coal under certain circumstances, such as in the event of a natural disaster. If the traditional electric operating companies are unable to obtain their contracted coal requirements, they may be required to purchase additional coal at higher prices or limit coal generation, and these increased costs may not be recoverable through rates if deemed to be imprudently incurred. The pace of retirement of coal-fired generating facilities can affect the demand for coal. If these facilities are retired in the future, the demand for coal may decline. As a result, railroads may commit fewer resources to coal transportation, which could increase these risks.
Whereas fuel oil directly provides only a small portion of the Southern Company system's annual generation, its importance to the reliability of the Southern Company system's generation portfolio continues to grow. Over the last few years, related cost increases and supply chain challenges have become more common and may increase the risk of reliability challenges.
The traditional electric operating companies and Southern Power have been increasing their renewable resources and expect to continue to add renewable capacity in the future. The production of energy from wind and solar facilities depends heavily on suitable weather conditions, which are variable. Wind conditions or solar irradiance that are unfavorable or below the Southern Company system's estimates can cause electricity production to be substantially below expectations.
In addition to fuel supply and suitable weather conditions, the traditional electric operating companies and Southern Power also need adequate access to water, which is drawn from nearby sources, to aid in the production of electricity. Any impact to their water resources could also limit the ability of the traditional electric operating companies and Southern Power to operate certain facilities, which could result in higher fuel and operating costs.
The revenues of Southern Company, the traditional electric operating companies, and Southern Power depend in part on sales under PPAs, the success of which depend on PPA counterparties performing their obligations, Southern Company subsidiaries satisfying minimum requirements under the PPAs, and renewal or replacement of the PPAs for the related generating capacity.
Most of Southern Power's generating capacity has been sold to purchasers under PPAs with Southern Power's top three customers comprising approximately 25% of Southern Power's total revenues for the year ended December 31, 2025. In addition to Mississippi Power's PPA with Georgia Power, the traditional electric operating companies have entered into PPAs with non-affiliated parties for the sale of generating capacity.
The revenues related to PPAs are dependent on the continued performance by the purchasers of their obligations. Although the credit evaluations undertaken and contractual protections implemented by Southern Power and the traditional electric operating companies take into account the possibility of default by a purchaser, actual exposure to a default by a purchaser may be greater than predicted or specified in the applicable contract.
Additionally, neither Southern Power nor any traditional electric operating company can predict whether the PPAs will be renewed at the end of their respective terms or on what terms any renewals may be made. If a Registrant is unable to replace expiring PPAs with an acceptable new revenue contract, it may be required to sell the power produced by the facility at wholesale prices and be exposed to market fluctuations and risks, or the affected site may temporarily or permanently cease operations, which may result in impairment charges. The failure to satisfy minimum operational or availability requirements under these PPAs, including PPAs related to projects under construction, could result in payment of damages or termination of the PPAs.
Increased competition from other companies that supply energy or generation and storage technologies and changes in customer demand for energy could negatively impact Southern Company and its subsidiaries.
The traditional electric operating companies operate under a business model that invests capital to serve customers and recovers those investments and earns a return for investors through state regulation. Southern Power's business model is primarily focused on investing capital or building energy assets to serve creditworthy counterparties using a bilateral contract model. A
I-20

    Table of Contents                                Index to Financial Statements
key premise of these business models is that generating power at power plants achieves economies of scale and produces power at a competitive cost.
Customers and stakeholders are increasingly focused on the Registrants' ability to meet rapidly changing demands for new and varied products, services, and offerings. Additionally, the risk of global climate change continues to shape customers' and stakeholders' sustainability goals and energy needs.
New technologies such as distributed energy resources and microgrids and increased customer and stakeholder demand for sustainable assets could change the type of assets constructed and/or the methods for cost recovery. Advances in these technologies or changes in laws or regulations could reduce the cost of distributed generation storage technologies or other alternative methods of producing power to a level that is competitive with that of most power generation production or result in smaller-scale, more fuel efficient, and/or more cost effective distributed generation that allows for increased self-generation by customers. Broader use of distributed generation by energy customers may also result from customers' changing perceptions of the merits of utilizing existing generation technology or tax or other economic incentives. Additionally, state PSCs or legislatures may modify certain aspects of the traditional electric operating companies' businesses as a result of these advances in technology, which may provide for further competition from these alternative sources of generation.
It is also possible that rapid advances in power generation technology could reduce the value of the current electric generating facilities owned by the traditional electric operating companies and Southern Power. Changes in technology could also alter the channels through which electric customers buy or utilize power.
Southern Company Gas' business is dependent on natural gas prices remaining competitive as compared to other forms of energy. Southern Company Gas' gas marketing services segment also is affected by competition from other energy marketers providing similar services in Southern Company Gas' unregulated service territories, most notably in Illinois and Georgia.
If new technologies become cost competitive and achieve sufficient scale, the market share of the Subsidiary Registrants could be eroded, and the value of their respective electric generating facilities or natural gas distribution facilities could be reduced. Additionally, these technology- and customer-induced changes to the Subsidiary Registrants' business models could change the risk profile of the Southern Company system's historical capital investments. Southern Company Gas' market share could be reduced if Southern Company Gas cannot remain price competitive in its unregulated markets.
The Subsidiary Registrants are subject to workforce factors that could affect operations.
The Southern Company system must attract, train, and retain a workforce to meet current and future needs. Events such as an aging workforce without appropriate replacements, increased cost or reduced supply of labor, mismatch of skill sets to future needs, or unavailability of contract resources may lead to operating challenges such as lack of resources, loss of knowledge, and a lengthy time period associated with skill development, including workforce needs associated with construction projects and ongoing operations. The Southern Company system's costs, including costs for contractors to replace employees, productivity costs, and safety costs, may rise. The Southern Company system is also subject to risks associated with the failure to adequately manage contract resources. In addition, the failure to hire and adequately obtain replacement employees, including the ability to transfer significant internal historical knowledge and expertise to the new employees, or the future availability and cost of contract labor may adversely affect the Southern Company system's ability to manage and operate its business.
Supply chain disruptions, inflation, elevated interest rates, trade policies (including tariffs and other trade measures), and other economic factors could negatively impact operations.
The Southern Company system's operations and business plans depend on the global supply chain to procure equipment, materials, and other resources. The delivery of components, materials, equipment, and other resources that are critical to the Southern Company system's operations has been impacted by domestic and global supply chain disruptions. Future pandemic health events or continued international tensions, including the ramifications of regional or international conflicts, such as those in Ukraine and the Middle East, and any strained relationships between the United States and other countries related to such conflicts, and the impact of trade policies (including tariffs and other trade measures) of the United States and other countries, could further exacerbate global supply chain disruptions. These disruptions and shortages could adversely impact business operations. The constraints in the supply chain also could restrict availability and delay construction, maintenance, or repair of items needed to support normal operations or to continue planned capital investments.
Supply chain disruptions and trade policies have contributed to higher prices of components, materials, equipment, and other needed commodities, and these inflationary increases may continue. Further inflation, a continued elevated interest rate environment, further impacts of trade policies, or other economic factors may negatively affect operations and the timely recovery of costs.
I-21

    Table of Contents                                Index to Financial Statements
CONSTRUCTION RISKS
The Registrants have incurred and may incur additional costs or delays in the construction of new plants or other facilities and may not be able to recover their investments. Also, existing facilities of the Subsidiary Registrants require ongoing expenditures, including those to maintain reliability and meet AROs and other environmental standards and goals.
The businesses of the Registrants require substantial expenditures for investments in new facilities as well as capital improvements, including transmission, distribution, generation, and battery energy storage facilities for the traditional electric operating companies, generation and battery energy storage facilities for Southern Power, and capital improvements to natural gas distribution facilities for Southern Company Gas, to, among other things, maintain reliability and meet projected electric demand growth. These expenditures also include those to settle AROs and meet environmental standards and goals. The traditional electric operating companies and Southern Power are in the process of constructing new generating facilities and/or adding environmental and other modifications to certain existing generating facilities and Southern Company Gas is replacing certain pipe in its natural gas distribution system and is involved in new gas pipeline construction projects. Moreover, the pace and extent of the traditional electric operating companies' planned construction program have increased as a response to projected electric demand growth. The traditional electric operating companies also are in the process of closing surface impoundments to comply with the CCR Rule and, where applicable, state CCR rules. The Southern Company system intends to continue its strategy of developing and constructing new electric generating facilities, expanding and improving the electric transmission and electric and natural gas distribution systems, and undertaking projects to maintain reliability and to comply with environmental laws and regulations. These projects are long term in nature and in some cases may include the development and construction of facilities with designs that have not been finalized or previously constructed.
Completion of these types of projects without delays or significant cost overruns is subject to substantial risks that have occurred or may occur, including changes in labor costs, availability, and productivity; challenges with the management of contractors or vendors; subcontractor performance; adverse weather conditions; shortages, delays, increased costs, or inconsistent quality of equipment, materials, and labor; contractor or supplier delay; the impacts of inflation and trade policies (including tariffs and other trade measures) of the United States and other countries; delays due to judicial or regulatory action; nonperformance under construction, operating, or other agreements; operational readiness, including specialized operator training and required site safety programs; engineering or design problems or any remediation related thereto; design and other licensing-based compliance matters; challenges with start-up activities, including major equipment failure, or system integration; and/or operational performance; challenges related to future epidemic or pandemic health events; continued public and policymaker support for projects; environmental and geological conditions; delays or increased costs to interconnect facilities to transmission grids; and increased financing costs as a result of changes in interest rates or as a result of project delays.
If a Subsidiary Registrant is unable to complete the development or construction of a project or decides to delay or cancel construction of a project, it may not be able to recover its investment in that project and may incur substantial cancellation payments under equipment purchase orders or construction contracts, as well as other costs associated with the closure and/or abandonment of the project. Further, the traditional electric operating companies are incurring, and may in the future incur, significant engineering, design, and equipment costs in advance of receiving approval of generation, distribution, and transmission projects. If any of these projects are canceled for any reason, including if a traditional electric operating company is not selected through a PSC-approved RFP process or due to failure to receive other necessary regulatory approvals and/or siting or environmental permits, significant cancellation penalties under the equipment purchase orders and construction contracts could occur and such traditional electric operating company may not be able to recover through customer rates all such penalties or registration, prepayment, or other fees incurred in such process. See Note 2 to the financial statements under "Georgia Power – Integrated Resource Plans – 2025 IRP" and " – Certification Requests" in Item 8 herein for additional information.
In addition, partnership and joint ownership agreements may provide partners or co-owners with certain decision-making authority in connection with projects under construction. Any failure by a partner or co-owner to perform its obligations under the applicable agreements could have a material negative impact on the applicable project under construction. Southern Company Gas' current pipeline development project involves a joint owner that controls management of the project, and Southern Power participates in partnership agreements with respect to a majority of its renewable energy projects. See Note 5 to the financial statements under "Joint Ownership Agreements" in Item 8 herein for additional information regarding other jointly-owned facilities.
If construction projects are not completed according to specification, a Subsidiary Registrant may incur liabilities and suffer reduced plant efficiency, higher operating costs, and reduced net income. Furthermore, construction delays associated with renewable projects could result in the loss of otherwise available tax credits and incentives.
I-22

    Table of Contents                                Index to Financial Statements
Even if a construction project (including a joint venture construction project) is completed, the total costs may be higher than estimated or certified or may be deemed imprudent, disallowed, or otherwise not recoverable through regulated rates, if applicable. In addition, construction delays and contractor performance shortfalls can result in the loss of revenues. See MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL – "Construction Programs" in Item 7 herein for additional information.
Once facilities become operational, ongoing capital expenditures are required to maintain safe and reliable levels of operation. Significant portions of the traditional electric operating companies' existing facilities were constructed many years ago. Older equipment, even if maintained in accordance with good engineering practices, may require significant expenditures to maintain efficiency, to comply with environmental requirements, to provide safe and reliable operations, and/or to meet related retirement obligations.
Southern Company Gas' significant investment in pipeline development projects involves financial and execution risks.
Southern Company Gas, through SNG, has approved a significant investment in a pipeline development project. The pipeline development project will be constructed and operated by a third party. If the third party fails to perform in a proper manner, the book value of the investment could be impaired and Southern Company Gas could lose part or all of its investment. In addition, Southern Company Gas is required to fulfill capital obligations related to other pipelines in which Southern Company Gas has an ownership interest or, as necessary, guarantee the obligations related thereto, and Southern Company Gas may participate in other pipeline development projects in the future.
With respect to the pipeline development project, Southern Company Gas will rely on its joint venture partner for construction management and will not exercise direct control over the process. The project is dependent on contractors for successful and timely completion. Further, the development of the pipeline project involves numerous regulatory, environmental, construction, safety, political, and legal uncertainties and may require a significant investment. This project may not be completed on schedule, at the budgeted cost, or at all. There may be cost overruns and construction difficulties that cause Southern Company Gas' investment to exceed its initial expectations, which may impact the earnings of the joint venture partnership. Moreover, Southern Company Gas' net income will not materially increase immediately upon the expenditure of funds on this pipeline project. Pipeline construction occurs over an extended period of time, and Southern Company Gas' net income will not be materially impacted unless and until the project is placed in service.
See MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL – "Construction Programs" in Item 7 herein for information regarding this project.
FINANCIAL, ECONOMIC, AND MARKET RISKS
The electric generation and energy marketing operations of the traditional electric operating companies and Southern Power and the natural gas operations of Southern Company Gas are subject to changes in energy prices and fuel costs.
The generation, energy marketing, and natural gas operations of the Southern Company system are subject to changes in energy prices and fuel costs, which could increase the cost of producing power, decrease the amount received from the sale of energy, and/or make electric generating facilities and natural gas distribution systems less competitive. The market prices for these commodities may fluctuate significantly over relatively short periods of time as a result of changes in supply and/or demand, which could increase the expenses and/or reduce the revenues of the Registrants. For the traditional electric operating companies and Southern Company Gas' regulated gas distribution operations, such impacts may not be fully recoverable through rates.
Southern Power and the traditional electric operating companies purchase natural gas as a fuel source for their power generation needs and the natural gas distribution utilities purchase natural gas for sale to their customers. Accordingly, the price of natural gas affects, among other things, Southern Power's and the traditional electric operating companies' costs of generation and the natural gas distribution utilities' cost of natural gas. Natural gas remains a volatile commodity. Slight supply and demand imbalances can quickly result in significant price moves both up and down. These price movements may be short-lived, but the impacts can be pronounced. Natural gas supplies have continued to grow; however, this growth has been accompanied by LNG export growth. Forward curves project prices will remain in the mid- to high-$3 per mmBtu range through 2030; however, short-term price volatility is expected and future prices could be materially impacted by various factors, including unexpected geopolitical events, increased demand for natural gas, including to fuel electric generation to serve data centers and other large load customers, and government policies related to natural gas and energy, including infrastructure development, production, and exports.
The traditional electric operating companies and Southern Company Gas from time to time have experienced and may continue to experience under recovered fuel and purchased power and/or purchased gas cost balances. While the traditional electric operating companies and Southern Company Gas are generally authorized to recover fuel and purchased power and/or
I-23

    Table of Contents                                Index to Financial Statements
purchased gas costs through cost recovery clauses, recovery may be delayed or may be denied if costs are deemed to be imprudently incurred.
The Registrants are subject to risks associated with a changing economic environment, customer behaviors, including increased energy conservation, and adoption patterns of technologies by customers.
The consumption and use of energy are linked to economic activity. This relationship is affected over time by changes in the economy, customer behaviors, and technologies. An economic downturn could be caused by a variety of factors, including wars, geopolitical instability, acts of terrorism, political or financial crises or uncertainty, government shutdowns, trade policies (including tariffs and other trade measures) of the United States and other countries, government fiscal policy, future pandemic health events, or cyclical economic factors. Any economic downturn could negatively impact customer growth and usage per customer. Additionally, any economic downturn or disruption of financial markets, both nationally and internationally, could negatively affect the financial stability of customers and counterparties of the Subsidiary Registrants.
Outside of economic disruptions, changes in customer behaviors in response to energy efficiency programs, changing conditions and preferences, legislation, or changes in the adoption of technologies could affect the relationship of economic activity to the consumption of energy. For example, some jurisdictions in the United States have banned the use of natural gas in new construction.
Both federal and state programs exist to influence how customers use energy, and several of the traditional electric operating companies and the natural gas distribution utilities have state PSC or other applicable state regulatory agency mandates to promote energy efficiency.
Customers could also voluntarily reduce their consumption of energy in response to decreases in their disposable income, elimination of government energy assistance programs, government shutdowns, increases in energy prices, or individual conservation efforts.
In addition, the adoption of technology by customers can have both positive and negative impacts on sales. Many new technologies utilize less energy than in the past. However, electric and natural gas technologies such as data centers and electric and natural gas vehicles can create additional demand. Given that these technologies are rapidly evolving, the extent of any additional demand is uncertain. In particular, future incremental electric demand from data centers could be substantial or, on the other hand, future technological advances could offset or eliminate any such demand. Accordingly, future energy demand may vary widely from projections. The Southern Company system seeks to incorporate the effects of changes in customer behavior, state and federal programs, state PSC or other applicable state regulatory agency mandates, and technology, but the Southern Company system's planning processes may not accurately estimate and incorporate these effects.
The operating results of the Registrants are affected by weather conditions and may fluctuate on a seasonal basis. In addition, catastrophic events could result in substantial damage to or limit the operation of the properties of a Subsidiary Registrant.
Electric power and natural gas supply are generally seasonal businesses. The Subsidiary Registrants have historically sold less power and natural gas when weather conditions are milder.
Volatile or significant weather events could result in substantial damage to the transmission and distribution lines of the traditional electric operating companies, the generating facilities of the traditional electric operating companies and Southern Power, and the natural gas distribution and underground storage facilities of Southern Company Gas, which is likely to negatively impact revenue and/or earnings. The Subsidiary Registrants have significant investments in the Atlantic and Gulf Coast regions and Southern Power and Southern Company Gas have investments in various states that could be subject to severe weather and natural disasters, including hurricanes, wildfires, and extreme temperatures. Further, severe drought conditions can reduce the availability of water and restrict or prevent the operation of certain generating facilities. These volatile weather events may result in unexpected increases in customer load, requiring procurement of additional power at wholesale prices, or create other grid reliability issues.
In the event a traditional electric operating company or Southern Company Gas experiences any of these weather events or any natural disaster or other catastrophic event, recovery of costs in excess of reserves and insurance coverage is subject to the approval of its state PSC or other applicable state regulatory agency. The traditional electric operating companies from time to time have experienced and may continue to experience deficits in their storm cost recovery reserve balances. For example, in September 2024, Hurricane Helene caused significant damage to Georgia Power's transmission and distribution facilities. The incremental restoration costs related to this hurricane totaled approximately $880 million, of which approximately $780 million was deferred in the regulatory asset for storm damage, approximately $75 million was capitalized to property, plant, and equipment, and approximately $25 million was deferred as future billings to open access transmission tariff customers. See Note 2 to the financial statements in Item 8 herein for more information regarding storm damage balances. Additionally, the applicable state PSC or other applicable state regulatory agency may deny or delay recovery of any portion of such costs. Any
I-24

    Table of Contents                                Index to Financial Statements
such delay or failure in recovering costs by the Subsidiary Registrants could have a material adverse effect on the Registrants, including lower credit ratings and, thus, higher costs for future debt issuances, as well as limitations on their ability to fund capital expenditures and support economic development opportunities.
In addition, damages resulting from significant weather events occurring within a Subsidiary Registrant's service territory or otherwise affecting its customers may result in the loss of customers and reduced demand for energy for extended periods and may impact customers' ability to perform under existing PPAs.
Acquisitions, dispositions, or other strategic ventures or investments may not result in anticipated benefits and may present risks, including risks not originally contemplated.
Southern Company and its subsidiaries have made significant acquisitions, dispositions, and investments in the past and may continue to do so, including through SNG's pipeline development projects. Such actions cannot be assured to be completed or beneficial to Southern Company or its subsidiaries. Southern Company and its subsidiaries continually seek opportunities to create value through various transactions, including acquisitions or sales of assets or businesses (or interests therein). Specifically, Southern Power continually seeks opportunities to execute its strategy to create value through various transactions, including acquisitions, dispositions, and sales and purchases of partnership interests, development and construction of new generating facilities, and entry into PPAs primarily with investor-owned utilities, IPPs, municipalities, electric cooperatives, and other load-serving entities, as well as commercial and industrial customers. Additionally, Southern Company Gas continues to make significant investments in existing pipelines, most of which are operated by third parties. If one of these agents fails to perform in a proper manner, the value of the investment could decline and Southern Company Gas could lose part or all of its investment. In addition, Southern Company Gas is required to fulfill capital obligations to pipeline joint ventures.
Southern Company and its subsidiaries may face significant competition for transactional opportunities and anticipated transactions may not be completed on acceptable terms or at all. In addition, these transactions are intended to, but may not, result in the generation of cash or income, the realization of savings, the creation of efficiencies, or the reduction of risk.
These transactions also involve risks, including that they may not result in an increase in income or provide adequate or projected cash flows or return on capital or other anticipated benefits; they may result in Southern Company or its subsidiaries entering into new or additional lines of business, which may have new or different business or operational risks; they may not be successfully integrated into the acquiring company's operations, internal control processes, and/or accounting systems; the due diligence conducted prior to a transaction may not uncover situations that could result in financial or legal exposure or may not appropriately evaluate the likelihood or quantify the exposure from identified risks; they may result in impairment or decreased earnings, revenues, or cash flow; they may result in credit rating downgrades for Southern Company or its subsidiaries; they may involve retained obligations in connection with transitional agreements or deferred payments related to dispositions that subject Southern Company or its subsidiaries to additional risk; Southern Company or the applicable subsidiary may not be able to achieve the projected financial benefits from the use of funds generated by any dispositions; expected benefits of a transaction may be dependent on the cooperation, performance, or credit risk of a counterparty; minority investments in growth companies may not result in a positive return on investment; or, for the traditional electric operating companies and Southern Company Gas, costs associated with such investments that were expected to be recovered through regulated rates may not be recoverable.
Southern Company and Southern Company Gas are holding companies and Southern Power owns many of its assets indirectly through subsidiaries. Each of these companies is dependent on cash flows from their respective subsidiaries to meet their ongoing and future financial obligations.
Southern Company and Southern Company Gas are holding companies and, as such, they have no operations of their own. Substantially all of Southern Company's and Southern Company Gas' and many of Southern Power's respective consolidated assets are held by subsidiaries. Southern Company's, Southern Company Gas' and, to a certain extent, Southern Power's ability to meet their respective financial obligations, including making interest and principal payments on outstanding indebtedness, and, for Southern Company, to pay dividends on its common stock, is dependent on the net income and cash flows of their respective subsidiaries and the ability of those subsidiaries to pay upstream dividends or to repay borrowed funds. Prior to funding Southern Company, Southern Company Gas, or Southern Power, the respective subsidiaries have financial obligations and, with respect to Southern Company and Southern Company Gas, regulatory restrictions that must be satisfied, including among others, debt service. In addition, Southern Company, Southern Company Gas, and Southern Power may provide capital contributions or debt financing to subsidiaries under certain circumstances, which would reduce the funds available to meet their respective financial obligations, including making interest and principal payments on outstanding indebtedness, and to pay dividends on Southern Company's common stock.
I-25

    Table of Contents                                Index to Financial Statements
A downgrade in the credit ratings of any of the Registrants, Southern Company Gas Capital, or Nicor Gas could negatively affect their ability to access capital at reasonable costs and/or could require posting of collateral or replacing certain indebtedness.
There are numerous factors that rating agencies evaluate to determine credit ratings for the Registrants, Southern Company Gas Capital, and Nicor Gas, including capital structure, regulatory environment, business risk, the ability to cover liquidity requirements, other commitments for capital, and certain other controllable and uncontrollable events. The Registrants, Southern Company Gas Capital, and Nicor Gas could experience a downgrade in their ratings if any rating agency concludes that the level of business or financial risk of the industry or the applicable company has deteriorated. Changes in ratings methodologies by the agencies could also have a negative impact on credit ratings. If any rating agency downgrades any Registrant, Southern Company Gas Capital, or Nicor Gas, borrowing costs likely would increase, including potential automatic increases in interest rates or fees under applicable term loans and credit facilities, the pool of investors and funding sources would likely decrease, and, particularly for any downgrade to below investment grade, significant collateral requirements may be triggered in a number of contracts. Any credit rating downgrade could require altering the mix of debt financing currently used and could require the issuance of secured indebtedness (which would rank senior to unsecured indebtedness) and/or indebtedness with additional restrictive covenants binding the applicable company.
Uncertainty in demand for energy can result in lower earnings or higher costs.
The traditional electric operating companies and Southern Power each engage in a long-term planning process to estimate the optimal mix and timing of new generation assets required to serve future load obligations. Southern Company Gas engages in a long-term planning process to estimate the optimal mix and timing of building new pipelines, replacing existing pipelines, and entering new markets and/or expanding in existing markets. These planning processes must project many years into the future to accommodate the long lead times associated with the permitting and construction of new generation and associated transmission facilities and natural gas distribution facilities. Inherent risk exists in predicting demand as future loads are dependent on many uncertain factors, including economic conditions, customer usage patterns, efficiency programs, and customer technology adoption.
The traditional electric operating companies are experiencing projected demand that significantly exceeds recent experience, creating the need for new power generating resources and transmission facilities. The majority of this demand is driven by the power needs and projected power needs of data centers to serve an increasingly digital economy and to support artificial intelligence. Other demands are coming from new industrial facilities with advanced manufacturing processes for products such as electric vehicles and batteries. Extending service to these customers necessitates significant capital expenditures, which in turn requires sufficient access to sources of capital. These additional capital spending needs, the increased concentration of business within a single industry based on emerging technologies, and uncertainties on the actual capacity required to satisfy the projected new demands of these new industries creates risks for the traditional electric operating companies. Ensuring that incremental revenues from these projected new demands cover incremental costs and risks is critical to continuing the traditional electric operating companies' value proposition to customers. In particular, Georgia Power has agreed to file its next base rate case in a manner that will ensure the incremental revenue from large load customers has downward pressure, on a levelized basis, of at least $556 million per year for the years 2029, 2030, and 2031. See Note 2 to the financial statements under "Georgia Power – Integrated Resource Plans – Certification Requests" in Item 8 herein for additional information. While electric service agreements with new large load customers (including data centers) typically include provisions such as early termination payments, minimum bills, and financial security, these and other contractual provisions may not fully protect the traditional electric operating companies against all risks. Changes in industry practice or advances in the related technologies could reduce the demand for electricity to power data centers or other large load facilities. Additionally, these industries may experience a business downturn, which could cause the loss of current or potential customers or may weaken the financial condition and creditworthiness of existing customers. If anticipated demand growth does not materialize, the traditional electric operating companies could experience unrecovered capital investments made to serve expected load. Conversely, if demand grows more rapidly than projected, the traditional electric operating companies may face challenges in securing adequate generation and transmission capacity and maintaining service reliability.
Because regulators may not permit the traditional electric operating companies or the natural gas distribution utilities to adjust rates to recover the costs of new generation and associated transmission assets and/or new pipelines and related infrastructure in a timely manner or at all, these subsidiaries may not be able to fully recover these costs or may have exposure to regulatory lag associated with the time between the incurrence of costs and the recovery in regulated rates. In addition, under Southern Power's model of selling capacity and energy at negotiated market-based rates under long-term PPAs, Southern Power might not be able to fully execute its business plan if market prices drop below original forecasts. Southern Power and/or the traditional electric operating companies may not be able to extend or replace existing PPAs upon expiration, or they may be forced to market these assets at prices lower than originally expected.
I-26

    Table of Contents                                Index to Financial Statements
The traditional electric operating companies are currently obligated to supply power to retail customers, as well as wholesale customers under long-term PPAs. Southern Power is currently obligated to supply power to wholesale customers under long-term PPAs. At peak times, the demand for power required to meet obligations could exceed the Southern Company system's available generation capacity. Market or competitive forces may require that the traditional electric operating companies purchase capacity in the open market or build additional generation and transmission facilities and that Southern Power purchase energy or capacity in the open market. Because regulators may not permit the traditional electric operating companies to pass all of these purchase or construction costs on to their customers, the traditional electric operating companies may not be able to recover some or all of these costs or may have exposure to regulatory lag associated with the time between the incurrence of costs of purchased or constructed capacity and the traditional electric operating companies' recovery through regulated rates. Under Southern Power's long-term fixed price PPAs, Southern Power may not be able to recover all of these costs.
The businesses of the Registrants and Nicor Gas are dependent on their ability to successfully access capital through capital markets and financial institutions.
The Registrants and Nicor Gas rely on access to both short-term and longer-term capital markets as a significant source of liquidity to meet capital requirements not satisfied by the cash flow from their respective operations, including capital expenditures to meet projected electric demand growth. Access to capital markets may also be critical to finance unexpected material expenditures such as unusually volatile commodity costs or significant storm restoration activities for severe weather events. If any of the Registrants or Nicor Gas is not able to access capital at competitive rates or on favorable terms, its ability to implement its business plan will be limited due to weakened capacity to fund capital investments or acquisitions that it may otherwise rely on to achieve future earnings and cash flows and affordability concerns from increased borrowing costs could require the Registrants and Nicor Gas, unilaterally or at the direction of their regulators, to significantly scale back infrastructure investment, which could lead to additional risks related to safety and reliability. In addition, the Registrants and Nicor Gas rely on committed credit facilities as back-up liquidity for access to low cost money markets. Certain market disruptions, whether in the United States or globally, including an economic downturn or uncertainty, increases in interest rates, bankruptcy or financial distress at an unrelated utility company, financial institution, or sovereign entity, capital markets volatility and disruption, either nationally or internationally, changes in fiscal, monetary, trade, or tax policy, volatility in market prices for electricity and natural gas, actual or threatened cyber or physical attacks on facilities within the Southern Company system or owned by unrelated utility companies, impacts of any future pandemic health events, geopolitical instability, war or threat of war, or the overall health of the utility and financial institution industries, may increase the cost of borrowing or adversely affect the ability to raise capital through the issuance of securities or other borrowing arrangements or the ability to secure committed bank lending agreements used as back-up sources of capital. Furthermore, some financial institutions may be limited in their ability to provide capital to the Registrants as a result of such financial institution's investment criteria, including criteria related to GHG.
If sources of capital for the Registrants or Nicor Gas are reduced, capital costs could increase materially.
Failure to comply with debt covenants or conditions could adversely affect the ability of the Registrants, SEGCO, Southern Company Gas Capital, or Nicor Gas to execute future borrowings.
The debt and credit agreements of the Registrants, SEGCO, Southern Company Gas Capital, and Nicor Gas contain various financial and other covenants. Georgia Power's loan guarantee agreement with the DOE contains additional covenants, events of default, and mandatory prepayment events relating to the ongoing operation of Plant Vogtle Units 3 and 4. Future debt and credit agreements may contain additional or different covenants, events of default, and mandatory prepayment events. Failure to meet those covenants beyond applicable grace periods could result in accelerated due dates and/or termination of the agreements.
Volatility in the securities markets, interest rates, and other factors could substantially increase defined benefit pension and other postretirement plan costs and affect the funding available for nuclear decommissioning.
The costs of providing pension and other postretirement benefit plans are dependent on a number of factors, such as the rates of return on plan assets, discount rates, the level of interest rates used to measure the required minimum funding levels of the plans, changes in actuarial assumptions, government regulations, and/or life expectancy, and the frequency and amount of the Southern Company system's required or voluntary contributions made to the plans. Changes in actuarial assumptions and differences between the assumptions and actual values, as well as a significant decline in the value of investments that fund the pension and other postretirement plans, if not offset or mitigated by a decline in plan liabilities, could increase pension and other postretirement expense, and the Southern Company system could be required from time to time to fund the pension plans with significant amounts of cash. See MANAGEMENT'S DISCUSSION AND ANALYSIS – ACCOUNTING POLICIES – "Application of Critical Accounting Policies and Estimates – Pension and Other Postretirement Benefits" in Item 7 herein and Note 11 to the financial statements in Item 8 herein for additional information regarding the defined benefit pension and other
I-27

    Table of Contents                                Index to Financial Statements
postretirement plans. Additionally, Alabama Power and Georgia Power each hold significant assets in their nuclear decommissioning trusts to satisfy obligations to decommission their nuclear plants. The rate of return on assets held in those trusts can significantly impact both the funding available for decommissioning and the funding requirements for the trusts. See Note 6 to the financial statements under "Nuclear Decommissioning" in Item 8 herein for additional information.
Shareholder activism could cause Southern Company to incur significant expense, hinder execution of Southern Company's business strategy, and impact Southern Company's stock price.
Activist shareholders could seek to engage in proxy solicitations, advance shareholder proposals, or otherwise attempt to assert influence on Southern Company's board of directors and management. Should such activity arise, it could result in substantial costs and divert management's and Southern Company's board's attention and resources. Additionally, such shareholder activism could give rise to perceived uncertainties as to Southern Company's future, adversely affect the Southern Company system's relationships with its employees, customers, regulators, or service providers, and make it more difficult to attract and retain qualified personnel. Southern Company's stock price could be subject to significant fluctuation or otherwise be adversely affected by the events, risks, and uncertainties of any shareholder activism.
The Registrants are subject to risks associated with their ability to obtain adequate insurance at acceptable costs.
The financial condition of some insurance companies, actual or threatened physical or cyber attacks, natural disasters, and an increased focus on climate issues, among other things, could have disruptive effects on insurance markets. The availability of insurance may decrease, and the insurance that the Registrants are able to obtain may have higher deductibles, higher premiums, and more restrictive policy terms. Further, the insurance policies may not cover all of the potential exposures or the actual amount of loss incurred.
The use of derivative contracts by Southern Company and its subsidiaries in the normal course of business could result in financial losses that negatively impact the net income of the Registrants or in reported net income volatility.
Southern Company and its subsidiaries use derivative instruments, such as swaps, options, futures, and forwards, to manage their commodity and interest rate exposures and, to a lesser extent, manage weather and foreign currency exchange rate exposure and engage in limited trading activities. The Registrants could recognize financial losses as a result of volatility in the market values of these contracts or if a counterparty fails to perform. These risks are managed through risk management policies, limits, and procedures, which might not work as planned and cannot entirely eliminate the risks associated with these activities. In addition, derivative contracts entered into for hedging purposes might not offset the underlying exposure being hedged as expected, resulting in financial losses. In the absence of actively quoted market prices and pricing information from external sources, the valuation of these financial instruments can involve management's judgment or use of estimates. The factors used in the valuation of these instruments become more difficult to predict and the calculations become less reliable further into the future. As a result, changes in the underlying assumptions or use of alternative valuation methods could affect the reported fair value of these contracts.
See Notes 13 and 14 to the financial statements in Item 8 herein for additional information.
Future impairments of goodwill or long-lived assets could have a material adverse effect on the Registrants' results of operations.
Goodwill is evaluated for impairment annually or on an interim basis if changes in circumstances or the occurrence of events suggest impairment exists. If impairment testing indicates that the carrying amount of reporting units exceeds the respective fair value, an impairment charge would be recognized. If goodwill were to become impaired, the results of operations could be materially and adversely affected. At December 31, 2025, goodwill was $5.2 billion and $5.0 billion for Southern Company and Southern Company Gas, respectively.
In addition, Southern Company and its subsidiaries have long-lived assets recorded on their balance sheets. Long-lived assets are assessed for impairment whenever events or changes in circumstances indicate that the asset's carrying amount may not be recoverable. If impairment testing indicates that the carrying amount of the long-lived assets exceeds the respective fair value, an impairment charge would be recognized. See Notes 1 and 15 to the financial statements in Item 8 herein for information regarding certain impairment charges at Southern Company, Alabama Power, and Southern Company Gas.
Item 1B.UNRESOLVED STAFF COMMENTS.
None.
Item 1C.CYBERSECURITY.
Cybersecurity is a critical component of Southern Company's risk management program. The Southern Company system has implemented a cybersecurity program to assess, identify, and manage risks from cybersecurity threats that may result in material adverse effects on the Southern Company system's ability to fulfill critical business functions, including energy
I-28

    Table of Contents                                Index to Financial Statements
delivery service failures, and on the confidentiality, integrity, and availability of the Southern Company system's information systems.
Governance and Oversight of Cybersecurity Risk
Board of Directors
The Southern Company Board of Directors (Board), along with certain committees (primarily the Audit Committee of the Board), oversees the Southern Company system's enterprise risk management process. The Board devotes significant time and attention to overseeing cybersecurity risk, and the Southern Company system's approach to cybersecurity governance establishes oversight throughout the enterprise. The Board has delegated the primary responsibility to oversee cybersecurity matters to the Business Security and Resiliency Committee (BSRC) of the Board. Having a committee like the BSRC, focused on and dedicated to security, is a strong governance practice. Comprised solely of independent members of the Board, the BSRC is charged with oversight of risks related to cybersecurity, physical security, and operational resiliency. The BSRC includes directors with an understanding of cyber issues, including former federal officials with high levels of security clearances. The BSRC meets at every regular Board meeting and when needed in the event of a specific threat or emerging issue. The Chair of the BSRC regularly reports to the Board in connection with key matters the BSRC considered. The BSRC routinely receives presentations on a range of topics, including the threat environment and vulnerabilities and risks, policies, practices, technology trends, and regulatory developments, from the Chief Information Security Officer (CISO) and the legal organization and, as needed, the Chief Information Technology Officer (CITO). The CISO reports to the BSRC at each regular committee meeting. Protocols have been established by which certain cybersecurity incidents are escalated internally and, where appropriate, reported to the BSRC, and ongoing updates regarding any such incident are provided until it has been resolved. See "Incident Response" herein.
Management
The Southern Company system has implemented a cross-functional, risk-based, "defense-in-depth" approach to preventing, detecting, identifying, mitigating, responding to, and recovering from cybersecurity threats and incidents, while also implementing controls and procedures that provide for the prompt escalation of certain cybersecurity incidents so that decisions regarding the public disclosure and reporting of such incidents can be made by management in a timely manner. Overall network efforts are led by the CISO and the Cybersecurity Organization, the organization responsible for implementing, monitoring, and maintaining cybersecurity practices across the Southern Company system, and aided by the Executive Vice President of Operations and the Energy Management System and Generation organization. The CISO meets regularly with the CITO and the Chief Executive Officer and reports regularly to committees of the Board to discuss risk management measures implemented to identify and mitigate data protection and cybersecurity risks. Security and resiliency are emphasized through business assurance, enterprise risk management, and incident response plans designed to identify, evaluate, and remediate incidents when they occur. Among other things, the Cybersecurity Incident Response Plan (CIRP) establishes a team comprised of the CISO, the Deputy CISO, the Director of the Digital Defense Center, and members of the legal and compliance organizations to evaluate emerging cyber threats and escalate to executive management and business units as appropriate. Plans, policies, and technologies are regularly updated and training exercises and crisis management preparedness activities are conducted to test effectiveness.
The CISO works closely with the legal and compliance organizations, as well as the relevant business units, to help ensure broad oversight of and compliance with legal, regulatory, and contractual cybersecurity requirements. The CISO has extensive cybersecurity knowledge and skills gained from over 25 years of cybersecurity experience and over a decade securing critical infrastructure. The CISO receives reports on cybersecurity threats from a variety of sources both internally and externally on an ongoing basis and regularly reviews risk management measures implemented to identify and mitigate cybersecurity risks. Briefings to the Board on cybersecurity matters include annual briefings to the Audit Committee and the Operations, Environmental, and Safety Committee in addition to briefings to the BSRC at each of its regular meetings (at least five times annually).
Internal Cybersecurity Team
The Cybersecurity Organization, led by the CISO, is responsible for the implementation, monitoring, and maintenance of the cybersecurity and data protection practices across the Southern Company system. The Southern Company system also relies on a Data Privacy and Protection team in the compliance organization, as well as the internal audit organization, to work with the Cybersecurity Organization on data protection policies and practices. Multiple experienced information security leaders with internal and external security experience responsible for various parts of the business report to the CISO, each of whom is supported by a team of trained cybersecurity professionals. In addition to these internal cybersecurity capabilities, external
I-29

    Table of Contents                                Index to Financial Statements
auditors and security companies are regularly engaged to assist with assessing, testing, identifying, and managing cybersecurity, including through penetration testing, vulnerability testing, and other technical evaluations.
Risk Management and Strategy
Although many of the networks are segmented, overall network security is a centralized shared service across the Southern Company system, led by the Cybersecurity Organization and the CISO. Recognizing that no single technology, process, or business control can effectively prevent or mitigate all risks related to cyber threats, multiple technologies, processes, and controls, all working independently but as part of a cohesive strategy, are employed to reduce risk. Southern Company system exposure and defenses are regularly tested through auditing, penetration testing, vulnerability testing, and other exercises designed to assess effectiveness.
The Southern Company system emphasizes both security and resiliency through business assurance and incident response plans designed to identify, evaluate, and remediate incidents when they occur. A 24/7 security operations center is also utilized, which facilitates real-time situational awareness across the cyber-threat environment, and a robust insider threat protection program that leverages cross-function information sharing to assess insider threat activity is employed. The Southern Company system regularly reviews and updates its plans, policies, and technologies and conducts regular training exercises and crisis management preparedness activities to test their effectiveness. In addition, a security awareness program for the Southern Company system's employees has also been implemented, which is designed to educate and train employees at least annually, or more often as needed, about risks inherent to human interaction with information and operational technology.
The Southern Company system's cybersecurity program is increasingly leveraging intelligence-sharing capabilities about emerging threats within the energy industry, across other industries, with specialized vendors, and through public-private partnerships with U.S. government intelligence agencies. By engaging with both the Electricity Information Sharing and Analysis Center and the Downstream Natural Gas Information Sharing and Analysis Center, the Southern Company system benefits from quality analysis and rapid sharing of security information across the energy sector. Such intelligence helps to allow for better detection and prevention of emerging cyber threats before they materialize. Just as it tests its policies and plans internally, the Southern Company system also engages in external exercises such as the bi-annual GridEx Security Exercise to evaluate and address the preparedness of the industry as a whole.
Many cybersecurity policies and standards across the Southern Company system are governed by multiple regulatory requirements. Portions of these policies and standards are audited by the FERC, the Transportation Security Administration, and the NRC, as appropriate, and are periodically evaluated by third parties such as cybersecurity insurance carriers. Certain members of senior management have high-level security clearances to facilitate access to critical information, and the Southern Company system participates in pilot programs with industry and the U.S. government to share additional information and strengthen cybersecurity and business resiliency.
The Southern Company system also employs systems and processes designed to oversee, identify, and reduce the potential impact of a security incident at a third-party vendor, service provider, or customer or otherwise implicating the third-party technology and systems used. Among other things, the Southern Company system has established a Vendor Security Incident Working Group to address such third-party security incidents, including following up with the third party as appropriate and taking steps to mitigate any impact to systems. The Vendor Security Incident Working Group includes members of the internal cybersecurity teams to address any incidents that may invoke the CIRP. Additionally, the Southern Company system typically imposes contractual obligations on vendors and other third-party business partners related to privacy, confidentiality, and data security based on their access to the Southern Company system's data and systems. The Southern Company system also maintains insurance coverage for cyber incidents; the scope of coverage and fitness of coverage is evaluated each year.
Incident Response
The Southern Company system has adopted a CIRP that applies in the event of certain cybersecurity threats or incidents to provide a standardized guide for responding to security incidents. The CIRP sets out a coordinated approach to investigating, containing, documenting, and mitigating incidents, including reporting findings and keeping senior management and other key stakeholders informed and involved as appropriate. In general, the incident response process follows the National Institute of Standards and Technology guidance and focuses on four phases: preparation; detection and analysis; containment, eradication, and recovery; and post-incident remediation. The CIRP is reviewed periodically to help ensure its applicability to any changing needs or circumstances and to provide users a tactical tool to effectively respond to incidents. The CIRP applies to all Southern Company system personnel (including third-party contractors, vendors, and partners) that perform functions or services requiring access to secure Southern Company system information and to all devices and network services that are owned or managed by the Southern Company system. A full tabletop exercise is performed at least annually, including stakeholders from business units beyond technology security, such as power delivery, legal, compliance, risk management, and corporate communications. In addition, the Southern Company system participates in sector-level and cross-sector exercises led by
I-30

    Table of Contents                                Index to Financial Statements
industry or the U.S. government. In the event of an incident, the technology security organization, the legal organization, and other stakeholders frequently review lessons learned after an incident has been remediated.
Material Cybersecurity Risks, Threats, and Incidents
Due to evolving cybersecurity threats, it has and will continue to be difficult to prevent, detect, mitigate, and remediate cybersecurity incidents. Risks from cybersecurity threats, including as a result of any previous cybersecurity incidents, have not materially affected the Southern Company system, including its business strategy, results of operations, or financial condition. While the Southern Company system has not experienced any material cybersecurity incidents, there can be no guarantee that it will not be the subject of future successful attacks, threats, or incidents. Additional information on cybersecurity risks can be found in Item 1A "Risk Factors" of this Form 10-K which should be read in conjunction with the foregoing information.
I-31

    Table of Contents                                Index to Financial Statements
Item 2. PROPERTIES
Electric
At December 31, 2025, the traditional electric operating companies, Southern Power, and SEGCO owned and/or operated the generating and battery energy storage facilities listed in the table below. The traditional electric operating companies have certain jointly-owned generating stations. For these facilities, the nameplate capacity shown represents the Registrant's portion of total plant capacity, with ownership percentages provided if less than 100%. See "Jointly-Owned Facilities" and "Titles to Property" herein and Note 5 to the financial statements under "Joint Ownership Agreements" in Item 8 herein for additional information.
Company/Facility Type(a)/Facility Name/
Ownership Percentage
LocationNameplate
Capacity (KWs)
Alabama Power
Natural Gas
Combined Cycle:
Barry Units 6 through 8
Mobile, AL1,706,424 
Central Alabama Generating StationAutauga County, AL885,000 
Lindsay Hill Generating Station
Autauga County, AL879,700 
Combustion Turbine:
Calhoun Generating StationCalhoun County, AL748,000 
Greene CountyDemopolis, AL720,000 
Steam:
Barry Units 1, 2, and 4Mobile, AL600,000 
Greene County Units 1 and 2 (60%)Demopolis, AL300,000 
Total Natural Gas5,839,124 
Coal
Barry Unit 5Mobile, AL700,000 
Gaston Unit 5Wilsonville, AL880,000 
Miller (91.8% of Units 1 and 2 and 100% of Units 3 and 4)Birmingham, AL2,532,288 
Total Coal4,112,288 
Nuclear
FarleyDothan, AL1,720,000 
Solar
Anniston Army Depot
Calhoun County, AL
7,380 
Fort Rucker
Dale County, AL
10,560 
Total Solar17,940 
Hydro
BankheadHolt, AL53,985 
BouldinWetumpka, AL225,000 
HarrisWedowee, AL132,000 
HenryOhatchee, AL72,900 
HoltHolt, AL46,944 
JordanWetumpka, AL100,000 
LayClanton, AL177,000 
Lewis SmithJasper, AL157,500 
Logan MartinVincent, AL135,000 
MartinDadeville, AL182,000 
MitchellVerbena, AL170,000 
I-32

    Table of Contents                                Index to Financial Statements
Company/Facility Type(a)/Facility Name/
Ownership Percentage
LocationNameplate
Capacity (KWs)
ThurlowTallassee, AL81,000 
WeissLeesburg, AL87,750 
YatesTallassee, AL47,000 
Total Hydro1,668,079 
Cogeneration
Lowndes CountyBurkeville, AL104,800 
TheodoreTheodore, AL236,418 
Washington CountyWashington County, AL123,428 
Total Cogeneration464,646 
Total Alabama Power Generating Capacity13,822,077 
Georgia Power
Natural Gas
Combined Cycle:
McDonough-Atkinson Units 4 through 6Atlanta, GA2,520,000 
McIntosh Units 10 and 11Effingham County, GA1,318,920 
Combustion Turbine:
McDonough Unit 3Atlanta, GA78,800 
McIntosh Units 1 through 8Effingham County, GA640,000 
McManusBrunswick, GA481,700 
RobinsWarner Robins, GA158,400 
WilsonAugusta, GA354,100 
Steam:
YatesNewnan, GA700,000 
Total Natural Gas6,251,920 
Coal
BowenCartersville, GA3,160,000 
Scherer (8.4% of Units 1 and 2 and 75% of Unit 3)Macon, GA750,924 
Total Coal3,910,924 
Nuclear
Hatch (50.1%)Baxley, GA899,612 
Vogtle (45.7%)Augusta, GA2,167,094 
Total Nuclear3,066,706 
Solar
Fort BenningColumbus, GA30,005 
Fort GordonAugusta, GA30,000 
Fort StewartFort Stewart, GA30,000 
Fort ValleyFort Valley, GA10,800 
Kings BayCamden County, GA30,161 
Marine Corps Logistics BaseAlbany, GA31,161 
McIntosh
Effingham County, GA10,000 
Moody Air Force BaseValdosta, GA49,500 
Robins Air Force BaseWarner Robins, GA128,000 
8 Other PlantsVarious Georgia locations18,479 
Total Solar368,106 
I-33

    Table of Contents                                Index to Financial Statements
Company/Facility Type(a)/Facility Name/
Ownership Percentage
LocationNameplate
Capacity (KWs)
Hydro
Bartletts FerryColumbus, GA173,000 
BurtonClayton, GA8,100 
Flint RiverAlbany, GA5,400 
Goat RockColumbus, GA40,500 
Lloyd ShoalsJackson, GA18,000 
Morgan FallsAtlanta, GA16,800 
NacoocheeLakemont, GA4,800 
North HighlandsColumbus, GA29,600 
Oliver DamColumbus, GA60,000 
Rocky Mountain (25.4%)Rome, GA229,362 
(b)
Sinclair DamMilledgeville, GA45,000 
Tallulah FallsClayton, GA72,000 
TerroraClayton, GA20,800 
TugaloClayton, GA59,250 
Wallace DamEatonton, GA321,300 
YonahToccoa, GA22,500 
Total Hydro1,126,412 
Battery Energy Storage
Mossy Branch
Talbot County, GA
65,000 
Total Georgia Power Generating Capacity14,789,068 
Mississippi Power
Natural Gas
Combined Cycle:
DanielPascagoula, MS1,070,424 
RatcliffeKemper County, MS769,898 
Combustion Turbine:
SweattMeridian, MS39,400 
WatsonGulfport, MS39,360 
Steam:
Greene County Units 1 and 2 (40%)Demopolis, AL200,000 
WatsonGulfport, MS750,000 
Total Natural Gas2,869,082 
Coal
DanielPascagoula, MS1,000,000 
Solar
Walnut Grove
Walnut Grove, MS
1,500 
Cogeneration
Chevron Cogenerating StationPascagoula, MS147,292 
(c)
Total Mississippi Power Generating Capacity4,017,874 
I-34

    Table of Contents                                Index to Financial Statements
Company/Facility Type(a)/Facility Name/
Ownership Percentage
LocationNameplate
Capacity (KWs)
Southern Power
Natural Gas
Combined Cycle:
FranklinSmiths, AL1,857,820 
HarrisAutaugaville, AL1,318,920 
Rowan Unit 4Salisbury, NC530,550 
Wansley Units 6 and 7Carrollton, GA1,073,000 
Combustion Turbine:
Addison Thomaston, GA668,800 
ClevelandCleveland County, NC720,000 
DahlbergJackson County, GA756,000 
Rowan Units 1 through 3Salisbury, NC455,250 
Total Natural Gas7,380,340 
Solar
AdobeKern County, CA20,000 
ApexNorth Las Vegas, NV20,000 
Boulder IClark County, NV100,000 
ButlerTaylor County, GA104,000 
Butler Solar FarmTaylor County, GA22,000 
CalipatriaImperial County, CA 20,000 
Campo VerdeImperial County, CA147,420 
CimarronColfax County, NM30,640 
Decatur CountyDecatur County, GA20,000 
Decatur ParkwayDecatur County, GA84,000 
Desert StatelineSan Bernadino County, CA299,990 
East PecosPecos County, TX120,000 
GarlandKern County, CA205,290 
Gaskell West IKern County, CA20,000 
GranvilleGranville County, NC2,500 
HenriettaKings County, CA102,000 
Imperial ValleyImperial County, CA163,200 
LamesaDawson County, TX102,000 
Lost Hills-BlackwellKern County, CA32,000 
Macho SpringsLuna County, NM55,000 
Morelos del SolKern County, CA15,000 
North StarFresno County, CA61,600 
PawpawTaylor County, GA30,480 
RoserockPecos County, TX160,000 
RutherfordRutherford County, NC74,800 
SandhillsTaylor County, GA148,000 
South Cheyenne
Laramie County, WY
150,000 
SpectrumClark County, NV30,240 
TranquillityFresno County, CA205,300 
Total Solar2,545,460 
(d)
Wind
Beech Ridge IIGreenbrier County, WV56,200 
BethelCastro County, TX276,000 
Cactus FlatsConcho County, TX148,350 
Deuel HarvestDeuel County, SD301,100 
Glass SandsMurray County, OK118,300 
I-35

    Table of Contents                                Index to Financial Statements
Company/Facility Type(a)/Facility Name/
Ownership Percentage
LocationNameplate
Capacity (KWs)
Grant PlainsGrant County, OK147,200 
Grant
Grant County, OK151,800 
Kay
Kay County, OK299,000 
PassadumkeagPenobscot County, ME42,900 
ReadingOsage & Lyon Counties, KS200,100 
Salt ForkDonley & Gray Counties, TX174,000 
SkookumchuckLewis & Thurston Counties, WA136,800 
Tyler BluffCooke County, TX125,580 
Wake
Crosby & Floyd Counties, TX257,250 
Wildhorse
Pushmataha County, OK100,000 
Total Wind2,534,580 
(e)
Battery Energy Storage
GarlandKern County, CA88,000 
(f)
TranquillityFresno County, CA72,000 
(f)
Total Battery Energy Storage
160,000 
Fuel Cell
Red Lion and BrooksideNew Castle and Newark, DE27,500 
(g)
Total Southern Power Generating Capacity12,647,880 
SEGCO
Gaston Units 1 through 4 (Natural Gas-Steam)Wilsonville, AL1,000,000 
Gaston (Natural Gas-Combustion Turbine)Wilsonville, AL19,680 
Total SEGCO Generating Capacity1,019,680 
(h)
Southern Company System
Natural Gas23,360,146 
Coal9,023,212 
Nuclear4,786,706 
Solar2,933,006 
Hydro2,794,491 
Wind2,534,580 
Cogeneration611,938 
Battery Energy Storage
225,000 
Fuel Cell27,500 
Total Southern Company System Generating Capacity46,296,579 
(a)Represents the primary fuel source.
(b)Operated by OPC.
(c)Generation is dedicated to a single industrial customer. See MANAGEMENT'S DISCUSSION AND ANALYSIS – FINANCIAL CONDITION AND LIQUIDITY – "Credit Rating Risk" in Item 7 herein.
(d)Southern Power owns a 67% equity interest in SP Solar (a limited partnership indirectly owning all of Southern Power's solar facilities, except the Gaskell West I, Roserock, and South Cheyenne solar facilities). SP Solar is the 51% majority owner of Boulder I, Garland, Henrietta, Imperial Valley, Lost Hills Blackwell, North Star, and Tranquillity solar facilities; the 66% majority owner of Desert Stateline solar facility; and the sole owner of the remaining SP Solar solar facilities. Southern Power is the controlling partner in a tax equity partnership owning Gaskell West I and also owns 100% of Roserock and South Cheyenne. All of these entities are consolidated subsidiaries of Southern Power and the capacity shown in the table is 100% of the nameplate capacity for the respective facility. See Note 7 to the financial statements under "Southern PowerVariable Interest EntitiesSP Solar" in Item 8 herein for additional information.
I-36

    Table of Contents                                Index to Financial Statements
(e)Southern Power is the controlling partner in a non-tax equity partnership for Beech Ridge II and is the controlling partner in tax equity partnerships owning Cactus Flats, Deuel Harvest, Reading, Skookumchuck, and Wildhorse. For Deuel Harvest and Skookumchuck, another partner holds a noncontrolling interest in Southern Power's remaining equity. Southern Power also owns 100% of Glass Sands and 100% of SP Wind (a holding company which owns the remaining eight Southern Power wind facilities). All of these entities are consolidated subsidiaries of Southern Power and the capacity shown in the table is 100% of the nameplate capacity for the respective facility. See Note 7 to the financial statements under "Southern Power – Variable Interest EntitiesSP Wind" in Item 8 herein for additional information.
(f)Southern Power is the controlling partner in a tax equity partnership owning the Garland and Tranquillity battery energy storage facilities. Additionally, the noncontrolling interests in Southern Power's remaining equity are owned by two other partners and the facilities are indirect subsidiaries of SP Solar. These entities are consolidated subsidiaries of Southern Power and the capacity shown in the table is 100% of the nameplate capacity for the respective facility.
(g)Southern Power has two noncontrolling interest partners that own approximately 10 MWs of the facility. These entities are consolidated subsidiaries of Southern Power and the capacity shown in the table is 100% of the nameplate capacity for the respective facility.
(h)Alabama Power and Georgia Power each own 50% of the outstanding common stock of SEGCO, an operating public utility company. Alabama Power and Georgia Power are each entitled to one half of SEGCO's capacity and energy. Alabama Power acts as SEGCO's agent in the operation of SEGCO's units and furnishes fuel to SEGCO for its units. See Note 7 to the financial statements under "SEGCO" in Item 8 herein for additional information.
See MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL – "Environmental Matters" in Item 7 herein and Note 2 to the financial statements under "Alabama Power – Environmental Accounting Order," "Georgia Power – Integrated Resource Plans," and "Mississippi Power – Integrated Resource Plans" in Item 8 herein for information regarding plans to retire or convert to natural gas certain coal-fired generating capacity included in the table above.
Except as discussed below under "Titles to Property," the principal plants and other important units of the traditional electric operating companies, Southern Power, and SEGCO are owned in fee by the respective companies. It is the opinion of management of each such company that its operating properties are adequately maintained, substantially in good operating condition, and suitable for their intended purpose.
Mississippi Power owns a lignite mine that was intended to provide fuel for the Kemper IGCC. Liberty Fuels Company, LLC, the operator of the mine, has a legal obligation to perform mine reclamation and Mississippi Power has a contractual obligation to fund all reclamation activities. As a result of the abandonment of the Kemper IGCC, final mine reclamation began in 2018 and was substantially completed in 2020, with monitoring expected to continue through 2027.
On July 30, 2025, Mississippi Power completed its acquisition of FP&L's 50% ownership interest in Plant Daniel Units 1 and 2. See Note 2 to the financial statements under "Mississippi Power – Integrated Resource Plans" and " – Plant Daniel" and Note 15 to the financial statements under "Mississippi Power" in Item 8 herein for additional information on Plant Daniel.
In 2025, the maximum demand on the traditional electric operating companies, Southern Power Company, and SEGCO was 37,006,000 KWs and occurred on January 22, 2025. The all-time maximum demand of 38,194,000 KWs occurred on January 17, 2024. These amounts exclude demand served by capacity retained by MEAG Power, OPC, and SEPA. The reserve margin for the traditional electric operating companies, Southern Power Company, and SEGCO in 2025 was 20%.
Jointly-Owned Facilities
Alabama Power and Georgia Power at December 31, 2025 had undivided interests in certain generating plants and other related facilities with non-affiliated parties. The percentages of ownership of the total plant or facility are as follows:
Percentage Ownership
Facility
Total
Capacity
Alabama
Power
Power
South
Georgia
Power
OPCMEAG
Power
DaltonFP&L
(MWs)
Plant Miller Units 1 and 21,320 91.8 %8.2 %— %— %— %— %— %
Plant Hatch1,796 — — 50.1 30.0 17.7 2.2 — 
Plant Vogtle Units 1 through 4
4,742 — — 45.7 30.0 22.7 1.6 — 
Plant Scherer Units 1 and 21,636 — — 8.4 60.0 30.2 1.4 — 
Plant Scherer Unit 3818 — — 75.0 — — — 25.0 
Rocky Mountain903 — — 25.4 74.6 — — — 
Alabama Power and Georgia Power have contracted to operate and maintain the respective units in which each has an interest (other than Rocky Mountain) as agent for the joint owners. Southern Nuclear operates and provides services to Alabama Power's and Georgia Power's nuclear plants.
In addition, Georgia Power has commitments, in the form of capacity purchases totaling $34 million at December 31, 2025, regarding a portion of a 5% interest in the original cost of Plant Vogtle Units 1 and 2 owned by MEAG Power that are in effect until the later of the retirement of the plant or the latest stated maturity date of MEAG Power's bonds issued to finance such ownership interest. See Note 3 to the financial statements under "Commitments" in Item 8 herein for additional information.
I-37

    Table of Contents                                Index to Financial Statements
Titles to Property
The traditional electric operating companies', Southern Power's, and SEGCO's interests in the principal plants and other important units of the respective companies are owned in fee by such companies, subject to the following major encumbrances: (1) a leasehold interest granted by Mississippi Power's largest retail customer, Chevron Products Company (Chevron), at the Chevron refinery, where five combustion turbines owned by Mississippi Power are located and used for co-generation, as well as liens on these assets pursuant to the related co-generation agreements and (2) liens associated with Georgia Power's reimbursement obligations to the DOE under its loan guarantee relating to Plant Vogtle Units 3 and 4, which are secured by a first priority lien on (a) Georgia Power's undivided ownership interest in the units and (b) Georgia Power's rights and obligations under the principal contracts relating to the units. See Note 5 to the financial statements under "Assets Subject to Lien" and Note 8 to the financial statements under "Long-term Debt" in Item 8 herein for additional information. The traditional electric operating companies own the fee interests in certain of their principal plants as tenants in common. See "Jointly-Owned Facilities" herein and Note 5 to the financial statements under "Joint Ownership Agreements" in Item 8 herein for additional information. Properties such as electric transmission and distribution lines, steam heating mains, and gas pipelines are constructed principally on rights-of-way, which are maintained under franchise or are held by easement only. A substantial portion of lands submerged by reservoirs is held under flood right easements. In addition, certain of the renewable generating facilities occupy or use real property that is not owned, primarily through various leases, easements, rights-of-way, permits, or licenses from private landowners or governmental entities.
Natural Gas
Southern Company Gas considers its properties to be adequately maintained, substantially in good operating condition, and suitable for their intended purpose. The following sections provide the location and general character of the materially important properties that are used by the segments of Southern Company Gas. Substantially all of Nicor Gas' properties are subject to the lien of the indenture securing its first mortgage bonds. See Note 8 to the financial statements in Item 8 herein for additional information.
Distribution and Transmission Mains
Southern Company Gas' distribution systems transport natural gas from its pipeline suppliers to customers in its service areas. These systems consist primarily of distribution and transmission mains, compressor stations, peak shaving/storage plants, service lines, meters, and regulators. At December 31, 2025, Southern Company Gas' gas distribution operations segment owned approximately 77,900 miles of underground distribution and transmission mains, which are located on easements or rights-of-way that generally provide for perpetual use.
Storage Assets
Southern Company Gas owns and operates eight underground natural gas storage fields in Illinois with a total working capacity of approximately 150 Bcf, approximately 135 Bcf of which is usually cycled on an annual basis. This system is designed to meet about 50% of the estimated peak-day deliveries and approximately 40% of the normal winter deliveries in Illinois. This level of storage capability provides Nicor Gas with supply flexibility, improves the reliability of deliveries, and helps mitigate the risk associated with seasonal price movements.
Southern Company Gas also has four LNG plants located in Georgia and Tennessee with total LNG storage capacity of approximately 7.0 Bcf. In addition, Southern Company Gas owns two propane storage facilities in Virginia, each with storage capacity of approximately 0.3 Bcf. The LNG plants and propane storage facilities are used by Southern Company Gas' gas distribution operations segment to supplement natural gas supply during peak usage periods.
Jointly-Owned Properties
Southern Company Gas' gas pipeline investments segment has a 50% undivided ownership interest in a 115-mile pipeline facility in northwest Georgia. Southern Company Gas also has an agreement to lease its 50% undivided ownership in the pipeline facility. See Note 5 to the financial statements under "Joint Ownership Agreements" in Item 8 herein for additional information.
Item 3.LEGAL PROCEEDINGS
See Note 3 to the financial statements in Item 8 herein for descriptions of legal and administrative proceedings discussed therein. The Registrants' threshold for disclosing material environmental legal proceedings involving a governmental authority where potential monetary sanctions are involved is $1 million.
I-38

    Table of Contents                                Index to Financial Statements
Item 4.MINE SAFETY DISCLOSURES
Not applicable.
I-39

    Table of Contents                                Index to Financial Statements
INFORMATION ABOUT OUR EXECUTIVE OFFICERS – SOUTHERN COMPANY
(Identification of executive officers of Southern Company is inserted in Part I in accordance with Regulation S-K, Item 401) The ages of the officers set forth below are as of December 31, 2025.
Christopher C. Womack
Chairman, President, and Chief Executive Officer
Age 67
First elected in 2008. President since March 2023, Chief Executive Officer since May 2023, and Chairman since December 2023. Previously served as Chairman and Chief Executive Officer of Georgia Power from June 2021 to March 2023 and President of Georgia Power from November 2020 to March 2023.
David P. Poroch
Executive Vice President and Chief Financial Officer
Age 56
First elected in 2025. Executive Vice President and Chief Financial Officer since July 2025. Previously served as Comptroller from March 2023 to July 2025, Senior Vice President and Chief Accounting Officer of SCS from March 2023 to July 2025, and Executive Vice President, Chief Financial Officer, Chief Risk Officer, and Treasurer of Southern Company Gas from January 2021 to February 2023.
Bryan D. Anderson
Executive Vice President
Age 59
First elected in 2020. Executive Vice President and President of External Affairs since January 2021. Executive Vice President of SCS since November 2020.
Pedro P. Cherry
Chairman, President, and Chief Executive Officer of Mississippi Power
Age 54
First elected in 2025. Chairman and Chief Executive Officer of Mississippi Power since August 2025. President of Mississippi Power since March 2025. Previously served as Executive Vice President of Southern Company Gas and President and Chief Executive Officer of Atlanta Gas Light and Chattanooga Gas from August 2020 to March 2025.
Stanley W. Connally, Jr.
Executive Vice President and Chief Operating Officer
Age 56
First elected in 2012. Chief Operating Officer since January 2025. Executive Vice President since April 2021 and Executive Vice President of SCS since January 2025. Previously served as Chairman, President, and Chief Executive Officer of SCS from April 2021 to January 2025 and Executive Vice President for Operations of SCS from June 2018 to April 2021.
Christopher Cummiskey
Executive Vice President
Age 51
First elected in 2021. Executive Vice President since January 2021. Chairman of Southern Power since February 2021 and Executive Vice President of SCS, Chief Executive Officer of Southern Power, and President and Chief Executive Officer of Southern PowerSecure Holdings, Inc. and Southern Holdings since July 2020. Chairman, President, and Chief Executive Officer of SCS since January 2025.
Sloane N. Drake
Executive Vice President and Chief Human Resources Officer
Age 49
First elected in 2024. Executive Vice President and Chief Human Resources Officer of Southern Company and SCS since March 2023. Previously served as Senior Vice President of SCS from February 2019 to March 2023 and Senior Vice President of Georgia Power from August 2018 to March 2023.
Kimberly S. Greene
Chairman, President, and Chief Executive Officer of Georgia Power
Age 59
First elected in 2013. Chairman, President, and Chief Executive Officer of Georgia Power since April 2023. Previously served as Chairman, President, and Chief Executive Officer of Southern Company Gas from June 2018 to March 2023.
I-40

    Table of Contents                                Index to Financial Statements
James Y. Kerr II
Chairman, President, and Chief Executive Officer of Southern Company Gas
Age 61
First elected in 2014. Chairman, President, and Chief Executive Officer of Southern Company Gas since April 2023. Previously served as Executive Vice President, Chief Legal Officer, and Chief Compliance Officer of Southern Company from March 2014 to March 2023.
J. Jeffrey Peoples
Chairman, President, and Chief Executive Officer of Alabama Power
Age 66
First elected in 2023. Chairman, President, and Chief Executive Officer of Alabama Power since January 2023. Previously served as Executive Vice President of Customer and Employee Services of Alabama Power from June 2020 to January 2023.
Peter P. Sena III
Chairman, President, and Chief Executive Officer of Southern Nuclear
Age 62
First elected in 2024. Chairman and Chief Executive Officer of Southern Nuclear since June 2024. President of Southern Nuclear since March 2023. Previously served as Executive Vice President and Chief Nuclear Officer of Southern Nuclear from July 2019 to March 2023.
Sterling A. Spainhour
Executive Vice President and Chief Legal Officer
Age 57
First elected in 2023. Executive Vice President and Chief Legal Officer since April 2023. Previously served as Chief Compliance Officer of Southern Company from April 2023 to January 2024, Senior Vice President, General Counsel, Corporate Secretary, and Chief Compliance Officer of Georgia Power from June 2020 to March 2023, and Senior Vice President and General Counsel – East of SCS from July 2020 to March 2023.


Each officer listed above was initially elected at the time or times stated above by the board of directors of the applicable company and is currently serving until the next annual meeting (or written consent in lieu of the annual meeting) or until his or her successor is elected and qualified.
I-41

    Table of Contents                                Index to Financial Statements
PART II

Item 5.MARKET FOR REGISTRANTS' COMMON EQUITY, RELATED STOCKHOLDER MATTERS AND ISSUER PURCHASES OF EQUITY SECURITIES
(a)(1) The common stock of Southern Company is listed and traded on the NYSE under the ticker symbol SO. The common stock is also traded on regional exchanges across the United States.
There is no market for the other Registrants' common stock, all of which is owned by Southern Company.
(a)(2) Number of Southern Company's common stockholders of record at January 31, 2026: 87,056
Southern Company has paid dividends on its common stock since 1948. Dividends paid per share of common stock were $2.94 in 2025 and $2.86 in 2024. In January 2026, Southern Company declared a quarterly dividend of 74 cents per share. Dividends on Southern Company's common stock are payable at the discretion of Southern Company's Board of Directors and depend upon earnings, financial condition, and other factors. See Note 8 to the financial statements under "Dividend Restrictions" in Item 8 herein for additional information.
Each of the other Registrants have one common stockholder, Southern Company.
(a)(3) Securities authorized for issuance under equity compensation plans.
See Part III, Item 12. Security Ownership of Certain Beneficial Owners and Management and Related Stockholder Matters.
(b) Use of Proceeds
Not applicable.
(c) Issuer Purchases of Equity Securities
None.

Item 6.RESERVED
II-1

    Table of Contents                                Index to Financial Statements
Item 7.MANAGEMENT'S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS
Page
Combined Management's Discussion and Analysis of Financial Condition and Results of Operations
Overview
II-3
Results of Operations
II-8
Southern Company
II-8
Alabama Power
II-16
Georgia Power
II-20
Mississippi Power
II-24
Southern Power
II-28
Southern Company Gas
II-30
Future Earnings Potential
II-35
Accounting Policies
II-46
Financial Condition and Liquidity
II-51
This section generally discusses 2025 and 2024 items and year-to-year comparisons between 2025 and 2024. Discussions of 2023 items and year-to-year comparisons between 2024 and 2023 that are not included in this Annual Report on Form 10-K can be found in Item 7 of each Registrant's Annual Report on Form 10-K for the year ended December 31, 2024, which was filed with the SEC on February 19, 2025. The following Management's Discussion and Analysis of Financial Condition and Results of Operations is a combined presentation; however, information contained herein relating to any individual Registrant is filed by such Registrant on its own behalf and each Registrant makes no representation as to information related to the other Registrants.
Item 7A.QUANTITATIVE AND QUALITATIVE DISCLOSURES ABOUT MARKET RISK
See MANAGEMENT'S DISCUSSION AND ANALYSIS – FINANCIAL CONDITION AND LIQUIDITY – "Market Price Risk" in Item 7 herein and Note 1 to the financial statements under "Financial Instruments" in Item 8 herein. Also see Notes 13 and 14 to the financial statements in Item 8 herein.
II-2

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
OVERVIEW
Business Activities
Southern Company is a holding company that owns all of the common stock of three traditional electric operating companies, Southern Power, and Southern Company Gas and owns other direct and indirect subsidiaries. The primary businesses of the Southern Company system are electricity sales by the traditional electric operating companies and Southern Power and the distribution of natural gas by Southern Company Gas. Southern Company's reportable segments are the sale of electricity by the traditional electric operating companies, the sale of electricity in the competitive wholesale market by Southern Power, and the distribution of natural gas and other complementary products and services by Southern Company Gas. See Note 16 to the financial statements for additional information.
The traditional electric operating companies – Alabama Power, Georgia Power, and Mississippi Power – are vertically integrated utilities providing electric service to retail customers in three Southeastern states in addition to wholesale customers in the Southeast.
Southern Power develops, constructs, acquires, owns, operates, and manages power generation assets, including battery energy storage projects, and sells electricity at market-based rates in the wholesale market. Southern Power continually seeks opportunities to execute its strategy to create value through various transactions including acquisitions, dispositions, and sales and purchases of partnership interests, development and construction of new generating facilities, and entry into PPAs primarily with investor-owned utilities, IPPs, municipalities, electric cooperatives, and other load-serving entities, as well as commercial and industrial customers. In general, Southern Power commits to the construction or acquisition of new generating capacity only after entering into or assuming long-term PPAs for the new facilities.
Southern Company Gas is an energy services holding company whose primary business is the distribution of natural gas. Southern Company Gas owns natural gas distribution utilities in four states – Illinois, Georgia, Virginia, and Tennessee – and is also involved in several other complementary businesses. Southern Company Gas manages its business through three reportable segments – gas distribution operations, gas pipeline investments, and gas marketing services, which includes SouthStar, a Marketer and provider of energy-related products and services to natural gas choice markets – and one non-reportable segment, all other. See Notes 7, 15, and 16 to the financial statements for additional information.
Southern Company's other business activities include providing distributed energy and resilience solutions and deploying microgrids for commercial, industrial, governmental, and utility customers, as well as investments in telecommunications. Management continues to evaluate the contribution of each of these activities to total shareholder return and may pursue acquisitions, dispositions, and other strategic ventures or investments accordingly.
See FUTURE EARNINGS POTENTIAL herein for a discussion of many factors that could impact the Registrants' future results of operations, financial condition, and liquidity.
Recent Developments
Alabama Power
Jurisdictional Separation Study Order
On June 5, 2025, the Alabama PSC approved an order authorizing Alabama Power to implement changes related to the Jurisdictional Separation Study (JSS) under Rate RSE, which allocates costs between retail and other electric services. For 2026, a revised JSS allocation factor will account for Alabama Power system capacity previously allocated to wholesale electric services that is being used for retail electric service starting January 1, 2026. In addition, Alabama Power is authorized to establish a regulatory asset to defer certain costs associated with this capacity for 2026, and those costs are estimated to be approximately $100 million. Beginning in 2027, Alabama Power will amortize the regulatory asset on a levelized basis over a period not exceeding 10 years.
Reliability Reserve Accounting Order
In 2025, Alabama Power utilized $30 million of the reliability reserve for reliability-related transmission, distribution, and generation expenses and accrued $83 million to the reliability reserve in accordance with procedures established in the reliability reserve accounting order. In addition, Alabama Power notified the Alabama PSC through its annual RSE filing of its intent to utilize $60 million of its reliability reserve balance in 2026. See Note 2 to the financial statements under "Alabama Power – Reliability Reserve Accounting Order" for additional information.
II-3

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Rate CNP New Plant
On August 13, 2025, the Alabama PSC approved Alabama Power's petition for a CCN authorizing Alabama Power to complete the acquisition of the Lindsay Hill Generating Station (879.7 MWs), which had been approved by the FERC on June 6, 2025. The transaction closed on September 30, 2025. See Notes 2 and 15 to the financial statements under "Alabama Power – Rate CNP New Plant" and "Alabama Power," respectively, for additional information.
Nuclear Production Tax Credits Order
On October 7, 2025, the Alabama PSC issued an order authorizing Alabama Power to establish a regulatory liability for nuclear PTCs received through its nuclear generating facilities pursuant to Internal Revenue Code §45U for tax years 2024 through 2032. The §45U PTCs will be deferred as a regulatory liability until the Alabama PSC provides direction on how to apply them for the benefit of customers. For the 2024 tax year, Alabama Power received $180 million in §45U PTCs on Southern Company's consolidated federal income tax return. The ultimate outcome of this matter cannot be determined at this time.
December 5th Consent Order
On December 5, 2025, the Alabama PSC issued a consent order (December 5th Consent Order) approving a plan to keep retail rates stable through 2027. Alabama Power has agreed to:
a moratorium on any upward rate adjustments associated with Rate RSE for 2027;
maintain the current Rate CNP Compliance factors through December 2027;
delay the effective date of Rate CNP New Plant adjustment to recover costs associated with the Lindsay Hill Generating Station acquisition until January 2028 billings;
maintain the current Rate CNP PPA factor through March 2028; and
maintain the current Rate ECR interim factor through December 2027.
To implement the plan, the Alabama PSC authorized Alabama Power to apply any customer refund resulting from Alabama Power's 2025 Rate RSE actual result calculation to the NDR. The Alabama PSC also approved the use of Alabama Power's 2024 nuclear PTCs, when monetized, to offset retail cost of service in 2027. In addition, any future regulatory liabilities associated with monetized nuclear PTCs from 2025, 2026, and 2027 will be used to offset future retail cost of service, including any under recovered balances under Rate CNP and Rate ECR.
Furthermore, the Alabama PSC, as part of its routine oversight of Alabama Power's regulated activities, will monitor factors such as weather, natural disasters, changes in fuel markets, and other significant unforeseen events that may impact this plan. If such events occur, Alabama Power will work with the Alabama PSC to determine a reasonable and responsive course of action under the circumstances.
See Note 2 to the financial statements under "Alabama Power" for additional information.
Rate RSE
On December 1, 2025, Alabama Power made its required annual Rate RSE submission to the Alabama PSC of projected data for calendar year 2026. Projected earnings were within the specified range; therefore, retail rates under Rate RSE remain unchanged for 2026.
For the year ended December 31, 2025, Alabama Power's weighted common equity return exceeded 6.15%, resulting in Alabama Power establishing a current regulatory liability of $57 million for Rate RSE refunds, which was subsequently applied to the NDR pursuant to the December 5th Consent Order.
See Note 2 to the financial statements under "Alabama Power – Rate RSE" for additional information.
Georgia Power
2022 ARP
On July 1, 2025, the Georgia PSC approved a settlement agreement among Georgia Power, the staff of the Georgia PSC, and certain intervenors to extend the 2022 ARP for an additional three-year term through December 31, 2028 (ARP Extension). Under the ARP Extension, base rates will not be adjusted in 2026, 2027, or 2028 except for reasonable and prudent storm damage costs incurred through December 31, 2025.
In a separate regulatory proceeding, on February 17, 2026, Georgia Power filed a request with the Georgia PSC to recover the reasonable and prudent storm costs incurred through December 31, 2025, which is expected to increase annual recovery by approximately $300 million effective June 1, 2026. The proposed annual recovery included in the filing is expected to fully
II-4

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
recover the regulatory asset balance related to storm damage at December 31, 2025 over four years, and the remaining balance at December 31, 2028 will be included in the next rate case. Georgia Power expects the Georgia PSC to make a final decision on this matter on May 28, 2026. The ultimate outcome of this matter cannot be determined at this time.
Under the ARP Extension, Georgia Power's retail ROE set point will continue at 10.50% and its equity ratio will continue at 56%. Additionally, the retail ROE range approved by the Georgia PSC in the 2022 ARP, of 9.50% to 11.90%, will continue.
See Note 2 to the financial statements under "Georgia Power – Rate Plans" and " – Storm Damage Recovery" for additional information.
Integrated Resource Plans
2025 IRP
On July 15, 2025, the Georgia PSC approved Georgia Power's 2025 IRP, as modified by a stipulation among Georgia Power, the staff of the Georgia PSC, and certain intervenors. In the 2025 IRP decision, the Georgia PSC approved several requests, including the following:
Extended operation of Plant Scherer Unit 3 (614 MWs based on 75% ownership) through at least December 31, 2035 and Plant Gaston Units 1 through 4 (500 MWs based on 50% ownership through SEGCO) through December 31, 2034.
Installation of environmental controls and natural gas co-firing at Plant Bowen Units 1 through 4 (3,160 MWs), Plant Scherer Units 1 and 2 (137 MWs based on 8.4% ownership), and Plant Scherer Unit 3 for compliance with both ELG supplemental rules and GHG rules.
Upgrades to Plant McIntosh Units 10 and 11 (1,319 MWs) for a projected 194 MWs of incremental capacity by 2028 and Plant McIntosh Units 1 through 8 (640 MWs) for a projected 74 MWs of incremental capacity by 2033.
Upgrades to Plant Vogtle Units 1 and 2 (1,060 MWs based on 45.7% ownership) for a projected 54 MWs of incremental capacity, some of which could be available as early as 2028.
Investments related to the continued reliable operations of four hydro facilities, as well as the authority to spend up to $25 million to undertake engineering studies related to two additional hydro facilities.
RFP for at least 1,100 MWs of utility scale and distributed generation renewable resources.
See Note 2 to the financial statements under "Georgia Power – Integrated Resource Plans – 2025 IRP" for additional information.
Certification Requests
On September 4, 2025, the Georgia PSC approved Georgia Power's request to certify a Georgia Power-owned battery energy storage facility with a capacity of 200 MWs and a projected COD in 2027.
On December 19, 2025, the Georgia PSC approved Georgia Power's request, as modified by a stipulation between Georgia Power and the staff of the Georgia PSC (Certification Stipulation), to certify the following resources totaling 9,885 MWs:
18 resources selected from the RFP pursuant to the 2022 IRP final order, totaling 7,999 MWs (6,804 MWs of Georgia Power projects) with projected CODs or delivery commencement dates between 2028 and 2030.
Extension of 50 MWs of an existing 750-MW affiliate PPA with Mississippi Power for an additional year through December 31, 2029.
A 20-year non-affiliate PPA for 930 MWs commencing in 2030 and five 25-year non-affiliate PPAs totaling 646 MWs commencing in 2027.
Construction of a 260-MW Georgia Power-owned battery energy storage facility with a projected COD in 2027 to be paired with an existing non-affiliate solar PPA.
Pursuant to the Certification Stipulation, Georgia Power has agreed to file its next base rate case in a manner that will ensure the incremental revenue from large load customers has downward pressure, on a levelized basis, of at least $556 million per year for the years 2029, 2030, and 2031.
The approved certification requests in September and December 2025 associated with these Georgia Power-owned projects and related transmission investments total approximately $16.7 billion, excluding AFUDC.
See Note 2 to the financial statements under "Georgia Power – Integrated Resource Plans – Certification Requests" and FINANCIAL CONDITION AND LIQUIDITY – "Cash Requirements" herein for additional information.
II-5

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Fuel Cost Recovery
On February 17, 2026, Georgia Power filed a request with the Georgia PSC to decrease fuel rates by 12.6% effective June 1, 2026, which is expected to reduce annual billings by approximately $388 million. Georgia Power expects the Georgia PSC to make a final decision on this matter on May 28, 2026. The ultimate outcome of this matter cannot be determined at this time. See Note 2 to the financial statements under "Georgia Power – Fuel Cost Recovery" for additional information.
Mississippi Power
On April 3, 2025, the FERC approved a settlement agreement filed by Mississippi Power and Cooperative Energy in December 2024, as part of the MRA tariff.
On June 17, 2025, the Mississippi PSC approved Mississippi Power's annual retail PEP filing for 2025, resulting in an annual increase in revenues of approximately 4.0%, or $41 million. In accordance with the PEP rate schedule, an increase of 2.0% of total retail revenues, or approximately $22 million, became effective with the first billing cycle of April 2025, and the remaining approximately $19 million became effective with the first billing cycle of July 2025. Also in the PEP filing, the Mississippi PSC approved Mississippi Power's use of a portion of its retail reliability reserve balance during 2025. As a result, Mississippi Power utilized the retail reliability reserve in the amount of $10.9 million during 2025 for reliability-related generation, transmission, and distribution expenses.
On June 19, 2025, the Florida PSC issued a final order approving the transfer of FP&L's 50% ownership interest in Plant Daniel Units 1 and 2 to Mississippi Power. On July 30, 2025, Mississippi Power completed the acquisition of FP&L's 50% interest in Plant Daniel Units 1 and 2 and, as part of the acquisition, received approximately $36 million from FP&L, which was recorded as a regulatory liability and is being amortized to offset incremental costs as authorized by the Mississippi PSC.
On November 17, 2025, Mississippi Power submitted its annual preliminary retail PEP filing for 2026 to the Mississippi PSC, which requested a 1.8%, or $20 million, annual increase in revenues. In accordance with the PEP rate schedule, the rate increase became effective with the first billing cycle of January 2026, subject to refund. The Mississippi PSC is expected to render a final decision in the second quarter 2026. The ultimate outcome of this matter cannot be determined at this time.
On February 13, 2026, Mississippi Power submitted its annual ECO Plan filing to the Mississippi PSC, which requested a $2 million annual increase in revenues. The ultimate outcome of this matter cannot be determined at this time.
See Note 2 to the financial statements under "Mississippi Power" for additional information.
Southern Power
During 2025, Southern Power continued construction of the 200-MW first phase, the 180-MW second phase, and the 132-MW third phase of the Millers Branch solar facility. In addition, Southern Power continued the development project to repower 200 MWs of the 299-MW Kay wind facility and began development projects to repower the full capacity of the 147-MW Grant Plains, the 152-MW Grant, the 257-MW Wake, and the 276-MW Bethel wind facilities. The output of the development projects is contracted under new and amended PPAs, with commercial operations projected to occur between the third quarter 2026 and the third quarter 2027. The ultimate outcome of these matters cannot be determined at this time. Subsequent to December 31, 2025, Southern Power completed construction of the 200-MW first phase of the Millers Branch solar facility. See Note 15 to the financial statements under "Southern Power" for additional information.
On December 31, 2025, Southern Power purchased 100% of the noncontrolling Class A membership interests in the SP Wind tax equity partnership for approximately $282 million. See Note 7 to the financial statements under "Southern Power – Variable Interest Entities – SP Wind" for additional information.
Southern Power calculates an investment coverage ratio for its generating assets, including those owned with various partners, based on the ratio of investment under contract to total investment using the respective facilities' net book value (or expected in-service value for facilities under construction) as the investment amount. With the inclusion of investments associated with facilities under construction, as well as other capacity and energy contracts, Southern Power's average investment coverage ratio at December 31, 2025 was 97% through 2030 and 89% through 2035, with an average remaining contract duration of approximately 12 years.
Southern Company Gas
Nicor Gas
In connection with Nicor Gas' 2023 general base rate case proceeding, the Illinois Commission disallowed $127 million of capital investments that have been completed or were planned to be completed through December 31, 2024. This amount is comprised of $31 million for capital investments placed in service in 2022 and 2023 under a nine-year regulatory infrastructure program
II-6

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
(Investing in Illinois) and $96 million for other transmission and distribution capital investments. Nicor Gas recorded a pre-tax charge to income in the fourth quarter 2023 of $58 million ($44 million after tax) associated with the disallowances. The disallowances are reflected on the statements of income in estimated loss on regulatory disallowance. In January 2024, the Illinois Commission denied a request by Nicor Gas for rehearing on the base rate case disallowances associated with capital investment, as well as on other issues determined in the Illinois Commission's 2023 base rate case decision. In February 2024, Nicor Gas filed a notice of appeal with the Illinois Appellate Court related to the Illinois Commission's rate case ruling. On December 1, 2025, the Illinois Appellate Court upheld the Illinois Commission's decision regarding certain capital investment disallowances in Nicor Gas' 2023 general base rate case proceeding. On December 22, 2025, Nicor Gas filed a petition for rehearing with the Illinois Appellate Court specifically addressing $43 million of the base rate case disallowances.
Any further cost disallowances by the Illinois Commission in the 2020 through 2023 annual review proceedings of the Investing in Illinois program could be material to the financial statements of Southern Company Gas. See Note 2 to the financial statements under "Southern Company Gas – Infrastructure Replacement Programs and Capital Projects – Nicor Gas" for additional information.
On November 19, 2025, the Illinois Commission approved a $168 million annual base rate increase for Nicor Gas, which became effective December 2, 2025. The base rate increase was based on an ROE of 9.60% and an equity ratio of 50.00%.
Additionally, the Illinois Commission excluded $120 million of capital investments included in the base rate case filing that have been incurred or are expected to be incurred through December 31, 2026. Nicor Gas analyzed the Illinois Commission's order and recorded a pre-tax charge to income in the fourth quarter 2025 of $63 million ($47 million after tax) associated with excluded capital investments that have been incurred. The disallowances are reflected on the statements of income in estimated loss on regulatory disallowance.
On January 6, 2026, the Illinois Commission denied a request by Nicor Gas for rehearing on the base rate case disallowances associated with capital investment, as well as on other issues determined in the Illinois Commission's November 19, 2025 base rate case decision. On January 14, 2026, Nicor Gas filed a petition for review with the Illinois Appellate Court related to the Illinois Commission's rate case ruling. It remains Nicor Gas' position that it has met its evidentiary burden to demonstrate that the amount and the timing of such capital investments are prudent and reasonable and that such capital investments should be included in base rates.
On January 9, 2026, Nicor Gas filed a general base rate case with the Illinois Commission requesting a $221 million increase in annual base rate revenues. The requested increase is based on a projected test year for the 12-month period ending December 31, 2027, an ROE of 10.35%, and an equity ratio of 54.6%. The Illinois Commission is expected to rule on the requested increase within the 11-month statutory time limit, after which rate adjustments will be effective. See Note 2 to the financial statements under "Southern Company Gas – Rate Proceedings – Nicor Gas" for additional information.
The ultimate outcome of these matters cannot be determined at this time.
Virginia Natural Gas
On December 17, 2025, the Virginia Commission approved a stipulation related to Virginia Natural Gas' August 2024 general base rate case filing. The approved stipulation provides for a $40 million increase in annual base rate revenues, including the recovery of investments under the SAVE program, an ROE of 9.85%, and an equity ratio of 49.35%. Interim rates became effective January 1, 2025, subject to refund, based on Virginia Natural Gas' original requested increase of approximately $63 million. Refunds to customers related to the difference between the approved rates implemented December 31, 2025 and the interim rates will be administered during the first quarter 2026.
Key Performance Indicators
In striving to achieve attractive risk-adjusted returns while providing cost-effective energy to approximately 9.0 million electric and gas utility customers collectively, the traditional electric operating companies and Southern Company Gas continue to focus on several key performance indicators. These indicators include, but are not limited to, customer satisfaction, plant availability, electric and natural gas system reliability, and execution of major construction projects. In addition, Southern Company and the Subsidiary Registrants focus on earnings per share (EPS) and net income, respectively, as a key performance indicator. See RESULTS OF OPERATIONS herein for information on the Registrants' financial performance.
The financial success of the traditional electric operating companies and Southern Company Gas is directly tied to customer satisfaction. Key elements of ensuring customer satisfaction include outstanding service, high reliability, and competitive prices. The traditional electric operating companies use customer satisfaction surveys to evaluate their results and generally target the top quartile of these surveys in measuring performance. Reliability indicators are also used to evaluate results. See Note 2 to the financial statements under "Alabama Power – Rate RSE" and "Mississippi Power – Performance Evaluation Plan" for additional
II-7

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
information on Alabama Power's Rate RSE and Mississippi Power's PEP rate plan, respectively, both of which contain mechanisms that directly tie customer service indicators to the allowed equity return.
Southern Company Gas also continues to focus on several operating metrics, including customer count and volumes of natural gas sold. See RESULTS OF OPERATIONS – "Southern Company Gas" herein for additional information on Southern Company Gas' operating metrics.
Southern Power continues to focus on several key performance indicators, including, but not limited to, the equivalent forced outage rate and contract availability to evaluate operating results and help ensure its ability to meet its contractual commitments to customers.
RESULTS OF OPERATIONS
Southern Company
Consolidated net income attributable to Southern Company was $4.3 billion in 2025, a decrease of $60 million, or 1.4%, from 2024. The decrease was primarily due to increases in depreciation and amortization, other operations and maintenance expenses, and interest expense, largely offset by increases in retail electric revenues associated with rates and pricing and sales growth, other revenues, natural gas revenues associated with base rate increases, and allowance for equity funds used during construction.
Basic EPS was $3.94 in 2025 and $4.02 in 2024. Diluted EPS, which factors in additional shares primarily related to stock-based compensation, was $3.92 in 2025 and $3.99 in 2024. EPS for 2025 and 2024 was negatively impacted by $0.03 and $0.01 per share, respectively, as a result of increases in the average shares outstanding. See Note 8 to the financial statements under "Outstanding Classes of Capital Stock – Southern Company" for additional information.
Dividends paid per share of common stock were $2.94 in 2025 and $2.86 in 2024. In January 2026, Southern Company declared a quarterly dividend of 74 cents per share. For 2025, the dividend payout ratio was 75% compared to 71% for 2024.
Discussion of Southern Company's results of operations is divided into three parts – the Southern Company system's primary business of electricity sales, its gas business, and its other business activities.
20252024
(in millions)
Electricity business$4,707 $4,473 
Gas business732 740 
Other business activities(1,098)(812)
Net Income$4,341 $4,401 
II-8

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Electricity Business
Southern Company's electric utilities generate and sell electricity to retail and wholesale customers. A condensed statement of income for the electricity business follows:
 2025
Increase
(Decrease)
from 2024
 (in millions)
Retail electric revenues
$19,331 $1,541 
Wholesale electric revenues
2,941 510 
Other electric revenues
953 57 
Other revenues
552 66 
Total electric operating revenues
23,777 2,174 
Fuel4,897 801 
Purchased power980 97 
Cost of other sales274 37 
Other operations and maintenance5,454 364 
Depreciation and amortization4,725 691 
Taxes other than income taxes1,263 (25)
Total electric operating expenses17,593 1,965 
Operating income6,184 209 
Allowance for equity funds used during construction318 109 
Interest expense, net of amounts capitalized1,445 73 
Other income (expense), net519 (4)
Income taxes1,039 36 
Net income4,537 205 
Net loss attributable to noncontrolling interests(170)(29)
Net Income Attributable to Southern Company$4,707 $234 
Retail Electric Revenues
Retail electric revenues increased $1.5 billion, or 8.7%, in 2025 as compared to 2024. Details of the changes in retail electric revenues were as follows:
 
2025 vs. 2024
 (in millions)
(% change)
Estimated change in retail electric revenues resulting from —
Rates and pricing$885 5.0 %
Sales growth216 1.2 
Weather(45)(0.2)
Fuel and other cost recovery485 2.7 
Total change in retail electric revenues
$1,541 8.7 %
Changes in rates and pricing resulted in an increase in retail electric revenues in 2025 as compared to 2024 primarily due to increases at Georgia Power related to base tariff increases and increased ECCR tariff revenues in accordance with the 2022 ARP and the inclusion of Plant Vogtle Unit 4 in retail rates net of elimination of the NCCR tariff, as well as an increase in Rate RSE at Alabama Power. See Note 2 to the financial statements under "Alabama Power" and "Georgia Power" for additional information.
II-9

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Changes in sales resulted in an increase in retail electric revenues in 2025 as compared to 2024. Changes in retail electric revenues are influenced heavily by the change in the volume of energy sold from year to year, which generally results from changes in electricity usage by customers, weather, and the number of customers. Total retail KWH sales for 2025 and the percent changes from 2024 were as follows:
2025
Total
KWHs
Total KWH
Percent Change
Weather-Adjusted
   Percent Change(*)
(in billions)
Residential49.8 1.1 %0.8 %
Commercial51.4 2.5 2.8 
Industrial49.6 1.4 1.4 
Other0.5 (2.0)(2.0)
Total retail energy sales
151.3 1.6 %1.7 %
(*)Weather-adjusted KWH sales are estimated using statistical models of the historical relationship between temperatures and energy sales, and then removing the estimated effect of deviations from normal temperature conditions. Normal temperature conditions are defined as those experienced in the applicable service territory over a specified historical period. This metric is useful because it allows trends in historical operations to be evaluated apart from the influence of weather conditions. Management also considers this metric in developing long-term capital and financial plans.
Weather-adjusted retail energy sales increased by 2.5 billion KWHs in 2025 as compared to 2024. Weather-adjusted residential KWH sales increased 0.8% primarily due to customer growth. Weather-adjusted commercial KWH sales increased 2.8% primarily due to additional sales from new and existing data centers at Georgia Power. Industrial KWH sales increased 1.4% primarily due to increases in the electronics and primary metals sectors, partially offset by decreases in the pipeline and textiles sectors.
Changes in fuel and other cost recovery revenues resulted in an increase in retail electric revenues in 2025 as compared to 2024 primarily due to higher recoverable fuel costs, as discussed further under "Fuel and Purchased Power Expenses" herein. Electric rates for the traditional electric operating companies include provisions to adjust billings for fluctuations in fuel costs, including the energy component of purchased power costs. Under these provisions, fuel revenues generally equal fuel expenses, including the energy component of PPA costs, and do not affect net income. The traditional electric operating companies each have one or more regulatory mechanisms to recover other costs such as environmental and other compliance costs, storm damage, new plants, and PPA capacity costs. See Note 2 to the financial statements for additional information.
Wholesale Electric Revenues
Wholesale electric revenues increased $510 million, or 21.0%, in 2025 as compared to 2024. Details of wholesale electric revenues were as follows:
2025
Increase
(Decrease)
from 2024
 (in millions)
Capacity and other$657 $5 
Energy2,284 505 
Total$2,941 $510 
The change in wholesale electric revenues was largely driven by increases in energy revenues of $326 million at the traditional electric operating companies and $179 million at Southern Power. The increase in energy revenues was due to a $420 million increase related to the average cost per KWH sold primarily resulting from higher fuel and purchased power prices, as well as an $85 million increase related to the volume of KWHs sold resulting from higher demand. Wholesale energy sales totaled 52.5 billion KWHs in 2025, a 4.7% increase as compared to 2024.
Wholesale electric revenues consist of revenues from PPAs and short-term opportunity sales. Wholesale electric revenues from PPAs (other than solar and wind PPAs) have both capacity and energy components. Capacity revenues generally represent the greatest contribution to net income and are designed to provide recovery of fixed costs plus a return on investment. Energy revenues will vary depending on fuel prices, the market prices of wholesale energy compared to the Southern Company system's generation, demand for energy within the Southern Company system's electric service territory, and the availability of the Southern Company system's generation. Increases and decreases in energy revenues that are driven by fuel prices are accompanied by an increase or decrease in fuel costs and do not have a significant impact on net income. Energy sales from solar
II-10

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
and wind PPAs do not have a capacity charge and customers either purchase the energy output of a dedicated renewable facility through an energy charge or through a fixed price related to the energy. As a result, the ability to recover fixed and variable operations and maintenance expenses is dependent upon the level of energy generated from these facilities, which can be impacted by weather conditions, equipment performance, transmission constraints, and other factors. Wholesale electric revenues at Mississippi Power include FERC-regulated MRA sales and market-based sales. Short-term opportunity sales are made at market-based rates that generally provide a margin above the Southern Company system's variable cost to produce the energy.
Other Electric Revenues
Other electric revenues increased $57 million, or 6.4%, in 2025 as compared to 2024. The increase was primarily due to increases of $27 million in revenues from renewable energy programs at Georgia Power primarily associated with solar application fees, $24 million in regulated outdoor lighting sales at Georgia Power, $17 million in realized gains associated with price stability products for retail customers on variable demand-driven pricing tariffs at Georgia Power, $10 million in customer fees at Georgia Power, and $7 million related to undistributed customer bill credits at Alabama Power, partially offset by decreases of $19 million in pole attachment revenues at Alabama Power and Georgia Power and $16 million associated with transmission revenues at Southern Power.
Other Revenues
Other revenues increased $66 million, or 13.6%, in 2025 as compared to 2024. The increase was primarily due to increases of $80 million in unregulated sales primarily associated with power delivery construction and maintenance, renewables, and resiliency projects at Georgia Power, partially offset by decreases of $10 million in unregulated sales associated with energy conservation projects at Georgia Power and $8 million in unregulated sales of products and services at Alabama Power.
Fuel and Purchased Power Expenses
In 2025, total fuel and purchased power expenses were $5.9 billion, an increase of $898 million, or 18.0%, as compared to 2024. The increase was primarily the result of a $592 million net increase related to the average cost of fuel and purchased power and a $251 million increase related to the volume of KWHs generated and purchased. Also contributing to the increase was $55 million related to credits recorded at Georgia Power in 2024 resulting from litigation related to nuclear fuel disposal costs. See Note 3 to the financial statements under "Nuclear Fuel Disposal Costs" for additional information.
Fuel and purchased power energy transactions at the traditional electric operating companies are generally offset by fuel revenues and do not have a significant impact on net income. See Note 2 to the financial statements for additional information. Fuel expenses incurred under Southern Power's PPAs are generally the responsibility of the counterparties and do not significantly impact net income.
The mix of fuel sources for the generation of electricity is determined primarily by demand, the unit cost of fuel consumed, and the availability of generating units. Additionally, the electric utilities purchase a portion of their electricity needs from the wholesale market. Energy purchases will vary depending on demand for energy within the Southern Company system's electric service territory, the market prices of wholesale energy as compared to the cost of the Southern Company system's generation, and the availability of the Southern Company system's generation.
II-11

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Details of the Southern Company system's generation and purchased power and the related costs were as follows:
20252024
Total generation (in billions of KWHs)(a)
191 188 
Total purchased power (in billions of KWHs)
21 18 
Sources of generation (percent) —
Gas51 52 
Coal20 18 
Nuclear(a)
19 20 
Wind, Solar, and Other8 
Hydro2 
Cost of fuel, generated (in cents per net KWH) 
Gas
3.37 2.62 
Nuclear(a)(b)
0.83 0.86 
Coal3.75 3.94 
Average cost of fuel, generated (in cents per net KWH)(a)(b)
2.89 2.50 
Average cost of purchased power (in cents per net KWH)(c)
5.01 5.14 
(a)Excludes KWHs generated from test period energy at Plant Vogtle Unit 4 prior to being placed in service in April 2024. The related fuel costs were charged to CWIP in accordance with FERC guidance.
(b)Excludes $55 million of credits recorded to nuclear fuel expense in 2024 resulting from litigation related to nuclear fuel disposal costs. See Note 3 to the financial statements under "Nuclear Fuel Disposal Costs" for additional information.
(c)Average cost of purchased power includes fuel purchased by the Southern Company system for tolling agreements where power is generated by the provider.
Cost of Other Sales
Cost of other sales increased $37 million, or 15.6%, in 2025 as compared to 2024. The increase was primarily due to an increase in expenses associated with unregulated power delivery construction and maintenance contracts at Georgia Power.
Other Operations and Maintenance Expenses
Other operations and maintenance expenses increased $364 million, or 7.2%, in 2025 as compared to 2024. The increase was primarily due to a $132 million increase in generation expenses primarily due to non-outage maintenance expenses largely resulting from Plant Vogtle Unit 4 being placed in service in April 2024 at Georgia Power, as well as planned outages at Alabama Power and Mississippi Power, a $114 million gain in 2024 from the sale of integrated transmission system assets at Georgia Power, and increases of $65 million associated with reliability reserve accruals and reliability-related expenses at Alabama Power, $62 million associated with NDR accruals at Alabama Power, $60 million in certain employee compensation and benefit expenses, $57 million in certain technology infrastructure and application production costs, and $28 million related to injuries and damages primarily at Georgia Power, partially offset by a decrease of $98 million in transmission and distribution costs primarily associated with line maintenance and billings adjustments with integrated transmission system owners at Georgia Power, an increase of $39 million in credits to income related to the estimated probable loss on Plant Vogtle Units 3 and 4 at Georgia Power, and a $36 million impairment loss in 2024 associated with Alabama Power discontinuing the development of a multi-use commercial facility. See Note 1 to the financial statements under "Impairment of Long-Lived Assets" and Note 2 to the financial statements under "Alabama Power – Reliability Reserve Accounting Order" and – "Rate NDR" and "Georgia Power – Transmission Asset Sales" and " – Nuclear Construction" for additional information.
Depreciation and Amortization
Depreciation and amortization increased $691 million, or 17.1%, in 2025 as compared to 2024. The increase was primarily due to increases of $298 million in accelerated depreciation at Southern Power related to wind repowering projects, $226 million associated with additional plant in service, and $123 million in amortization of regulatory assets related to CCR AROs at Georgia Power as approved in the 2025 compliance filing under the terms of the 2022 ARP. See FUTURE EARNINGS POTENTIAL – "Construction Programs" herein and Notes 2 and 15 to the financial statements under "Georgia Power" and "Southern Power – Wind Repowering Projects," respectively, for additional information.
II-12

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Taxes Other Than Income Taxes
Taxes other than income taxes decreased $25 million, or 1.9%, in 2025 as compared to 2024. The decrease was primarily due to decreases of $78 million in property taxes primarily resulting from the actualization of prior-year tax assessments at Georgia Power, partially offset by increases of $21 million in municipal franchise fees resulting from higher retail revenues at Georgia Power, $18 million in utility license taxes at Alabama Power resulting from an increase in the tax base, and $9 million in payroll taxes.
Allowance for Equity Funds Used During Construction
Allowance for equity funds used during construction increased $109 million, or 52.2%, in 2025 as compared to 2024. The increase was primarily associated with increases in capital expenditures subject to AFUDC at Georgia Power and Alabama Power, partially offset by the impact of Plant Vogtle Unit 4 being placed in service in April 2024 at Georgia Power. See Notes 1 and 2 to the financial statements under "Allowance for Funds Used During Construction and Interest Capitalized" and "Georgia Power," respectively, for additional information.
Interest Expense, Net of Amounts Capitalized
Interest expense, net of amounts capitalized increased $73 million, or 5.3%, in 2025 as compared to 2024. The increase primarily reflects approximately $95 million related to higher average outstanding borrowings and a decrease of $12 million in net deferred financing costs related to Plant Vogtle Unit 3 at Georgia Power, partially offset by an increase of $41 million in capitalized interest and AFUDC debt associated with increased capital expenditures. See FINANCIAL CONDITION AND LIQUIDITY – "Sources of Capital" and – "Financing Activities" herein, Note 1 to the financial statements under "Allowance for Funds Used During Construction and Interest Capitalized," and Note 8 to the financial statements for additional information.
Other Income (Expense), Net
Other income (expense), net decreased $4 million, or 0.8%, in 2025 as compared to 2024 primarily due to a $40 million increase in charitable donations at the traditional electric operating companies, primarily at Georgia Power, largely offset by increases of $13 million in interest income, $13 million in customer charges related to contributions in aid of construction at the traditional electric operating companies, and $10 million related to the receipt of liquidated damages at Alabama Power associated with the termination of two solar projects.
Income Taxes
Income taxes increased $36 million, or 3.6%, in 2025 as compared to 2024. The increase was primarily due to higher pre-tax earnings and a $29 million increase in charges to a valuation allowance on certain state tax credit carryforwards at Georgia Power, partially offset by increases of $28 million in the flowback of certain excess deferred income taxes at the traditional electric operating companies and $21 million in the generation of advanced nuclear PTCs at Georgia Power. See Note 10 to the financial statements for additional information.
Net Loss Attributable to Noncontrolling Interests
Substantially all noncontrolling interests relate to renewable projects at Southern Power. Net loss attributable to noncontrolling interests increased $29 million, or 20.6%, in 2025 as compared to 2024. The increased loss was primarily due to $20 million in higher HLBV loss allocations to Southern Power's tax equity partners and $11 million in lower income allocations to Southern Power's equity partners.
Gas Business
Southern Company Gas distributes natural gas through utilities in four states and is involved in several other complementary businesses including gas pipeline investments and gas marketing services.
II-13

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
A condensed statement of income for the gas business follows:
 2025
Increase
(Decrease)
from 2024
 (in millions)
Natural gas revenues
$5,044 $588 
Cost of natural gas1,599 403 
Other operations and maintenance1,360 125 
Depreciation and amortization708 58 
Taxes other than income taxes272 24 
Total operating expenses3,939 610 
Operating income1,105 (22)
Earnings from equity method investments127 (19)
Interest expense, net of amounts capitalized377 36 
Other income (expense), net59 (7)
Income taxes182 (76)
Net income$732 $(8)
Southern Company Gas measures weather and the effect on its business using Heating Degree Days. Generally, increased Heating Degree Days result in higher demand for natural gas on Southern Company Gas' distribution system. During the Heating Season, more customers are connected to Southern Company Gas' distribution systems and natural gas usage is higher in periods of colder weather. As a result, operating results can vary significantly from quarter to quarter. For 2025, the percentage of operating revenues and net income generated during the Heating Season was 66% and 82%, respectively. For 2024, the percentage of operating revenues and net income generated during the Heating Season was 62% and 80%, respectively.
Natural Gas Revenues
Natural gas revenues in 2025 were $5.0 billion, reflecting a $588 million, or 13.2%, increase compared to 2024. Details of natural gas revenues were as follows:
2025 vs. 2024
(in millions)
(% change)
Estimated change in natural gas revenues resulting from –
Rate changes$146 3.3 %
Gas costs and other cost recovery372 8.3 
Gas marketing services61 1.4 
Other9 0.2 
Total change in natural gas revenues
$588 13.2 %
Changes in rates resulted in an increase in revenues in 2025 as compared to 2024 primarily due to base rate increases at Atlanta Gas Light and Virginia Natural Gas. See Note 2 to the financial statements under "Southern Company Gas – Rate Proceedings" for additional information.
Revenues associated with gas costs and other cost recovery increased in 2025 primarily due to higher cost of natural gas driven by higher natural gas prices and gas volumes, as well as increases in other expenses passed through to customers. Natural gas distribution rates include provisions to adjust billings for fluctuations in natural gas costs. Therefore, gas costs recovered through natural gas revenues generally equal the amount expensed in cost of natural gas and do not affect net income from the natural gas distribution utilities. See "Cost of Natural Gas" and "Other Operations and Maintenance Expenses" herein for additional information.
Revenues from gas marketing services increased in 2025 primarily due to higher commodity prices.
Southern Company Gas has various regulatory mechanisms, such as weather and revenue normalization and straight-fixed-variable rate design, which limits positive or negative impacts to income from exposure to weather changes within typical ranges in each of its utility's respective service territory. Southern Company Gas also utilizes weather hedges to limit the negative income
II-14

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
impacts in the event of warmer-than-normal weather in Illinois and Georgia for gas marketing services. Therefore, weather typically does not have a significant net income impact.
Cost of Natural Gas
Excluding Atlanta Gas Light, which does not sell natural gas to end-use customers, the natural gas distribution utilities' rates include provisions to adjust billings for fluctuations in natural gas costs. Therefore, gas costs recovered through natural gas revenues generally equal the amount expensed in cost of natural gas and do not affect net income from the natural gas distribution utilities. See Note 2 to the financial statements under "Southern Company Gas – Natural Gas Cost Recovery" for additional information. Cost of natural gas at the natural gas distribution utilities represented 81.7% of the total cost of natural gas for 2025.
Gas marketing services customers are charged for actual and estimated natural gas consumed. Cost of natural gas includes the cost of fuel and associated transportation costs, lost and unaccounted for gas, and gains and losses associated with certain derivatives.
Cost of natural gas was $1.6 billion, an increase of $403 million, or 33.7%, in 2025 as compared to 2024, which reflects higher gas cost recovery in 2025 as a result of a 51.0% increase in natural gas prices as compared to 2024.
Other Operations and Maintenance Expenses
Other operations and maintenance expenses increased $125 million, or 10.1%, in 2025 as compared to 2024. The increase was primarily due to $63 million in charges related to the disallowance of certain capital investments at Nicor Gas, as well as increases of $38 million in employee compensation and benefit expenses, $23 million in expenses passed through to customers at the natural gas distribution utilities, and $17 million in bad debt expense, partially offset by a decrease of $26 million related to certain deferred expenses. See Note 2 to the financial statements under "Southern Company Gas – Rate Proceedings – Nicor Gas" for additional information.
Depreciation and Amortization
Depreciation and amortization increased $58 million, or 8.9%, in 2025 as compared to 2024. The increase was primarily due to additional plant in service related to continued investments at the natural gas distribution utilities. See Note 2 to the financial statements under "Southern Company Gas – Infrastructure Replacement Programs and Capital Projects" for additional information.
Taxes Other Than Income Taxes
Taxes other than income taxes increased $24 million, or 9.7%, in 2025 as compared to 2024. The increase was primarily due to an increase in revenue taxes as a result of higher natural gas revenues at Nicor Gas. Revenue taxes imposed on Nicor Gas are recoverable from its customers.
Earnings from Equity Method Investments
Earnings from equity method investments decreased $19 million, or 13.0%, in 2025 as compared to 2024. The decrease was primarily due to legal settlements, increased spending on system integrity initiatives, and lower rates, all at SNG. See Note 7 to the financial statements under "Southern Company Gas" for additional information.
Interest Expense, Net of Amounts Capitalized
Interest expense, net of amounts capitalized increased $36 million, or 10.6%, in 2025 as compared to 2024. The increase was primarily associated with higher average outstanding borrowings. See FINANCIAL CONDITION AND LIQUIDITY – "Sources of Capital" and – "Financing Activities" herein and Note 8 to the financial statements for additional information.
Income Taxes
Income taxes decreased $76 million, or 29.5%, in 2025 as compared to 2024. The decrease was primarily due to lower pre-tax earnings, including the impact of the regulatory disallowance at Nicor Gas, an increase of $36 million in the flowback of excess federal and state deferred income taxes, and a decrease of $8 million related to uncertain state tax positions in 2024. See Note 2 to the financial statements under "Southern Company Gas – Rate Proceedings – Nicor Gas" and Note 10 to the financial statements for additional information.
Other Business Activities
Southern Company's other business activities primarily include the parent company (which does not allocate operating expenses to business units); PowerSecure, which provides distributed energy and resilience solutions and deploys microgrids for commercial, industrial, governmental, and utility customers; Southern Holdings, which, through its subsidiaries, invests in various projects and insures various risk exposures of Southern Company and its subsidiaries; and Southern Linc, which provides digital
II-15

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
wireless communications for use by the Southern Company system and also markets these services to the public and provides fiber optics services within the Southeast.
A condensed statement of operations for Southern Company's other business activities follows:
2025
Increase
(Decrease)
from 2024
(in millions)
Operating revenues$732 $67 
Cost of other sales408 (3)
Other operations and maintenance254 41 
Depreciation and amortization69 (2)
Taxes other than income taxes4  
Total operating expenses735 36 
Operating income (loss)(3)31 
Earnings (loss) from equity method investments
(21)(5)
Interest expense1,417 387 
Other income (expense), net(50)(26)
Income taxes (benefit)(393)(101)
Net loss$(1,098)$(286)
Operating Revenues
Operating revenues for these other business activities increased $67 million, or 10.1%, in 2025 as compared to 2024 primarily due to an increase in revenues at PowerSecure largely related to a higher volume of distributed infrastructure projects.
Other Operations and Maintenance
Other operations and maintenance expenses for these other business activities increased $41 million, or 19.2%, in 2025 as compared to 2024 primarily due to an increase of $43 million in expenses at PowerSecure primarily related to a higher volume of distributed infrastructure projects, partially offset by a decrease of $16 million in expenses at the parent company primarily related to lower director compensation expenses.
Interest Expense
Interest expense for these other business activities, which primarily results from parent company financing activities, increased $387 million, or 37.6%, in 2025 as compared to 2024 primarily due to increases of $252 million associated with the extinguishment of debt at the parent company, $117 million related to higher average outstanding borrowings, and $29 million related to higher interest rates. See Note 8 to the financial statements for additional information.
Other Income (Expense), Net
Other income (expense), net for these other business activities decreased $26 million, or 108.3%, in 2025 as compared to 2024 primarily due to an increase in charitable donations at the parent company.
Income Taxes (Benefit)
The income tax benefit for these other business activities increased $101 million, or 34.6%, in 2025 as compared to 2024 primarily due to higher pre-tax losses at the parent company.
Alabama Power
Alabama Power's net income was $1.5 billion in 2025, representing a $113 million, or 8.1%, increase from 2024. The increase was primarily due to higher retail electric revenues resulting from changes in rates and pricing, partially offset by increases in other operations and maintenance expenses and depreciation and amortization.
II-16

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
A condensed income statement for Alabama Power follows:
2025
Increase
(Decrease)
from 2024
(in millions)
Retail revenues
$7,136 $497 
Wholesale revenues, non-affiliates
449 112 
Wholesale revenues, affiliates
188 49 
Other revenues
462 23 
Total operating revenues
8,235 681 
Fuel1,524 166 
Purchased power508 134 
Other operations and maintenance2,026 131 
Depreciation and amortization1,510 51 
Taxes other than income taxes498 27 
Total operating expenses6,066 509 
Operating income2,169 172 
Allowance for equity funds used during construction69 12 
Interest expense, net of amounts capitalized465 17 
Other income (expense), net168 11 
Income taxes425 65 
Net income$1,516 $113 
Retail Revenues
Retail revenues increased $497 million, or 7.5%, in 2025 as compared to 2024. Details of the changes in retail revenues were as follows:
2025 vs. 2024
(in millions)
(% change)
Estimated change in retail revenues resulting from —
Rates and pricing$300 4.5 %
Sales growth13 0.2 
Weather(3) 
Fuel and other cost recovery187 2.8 
Total change in retail revenues
$497 7.5 %
Changes in rates and pricing resulted in an increase in revenues primarily due to an increase in Rate RSE. See Note 2 to the financial statements under "Alabama Power – Rate RSE" for additional information.
Changes in sales resulted in an increase in retail revenues in 2025 as compared to 2024. Changes in retail revenues are influenced heavily by the change in the volume of energy sold from year to year, which generally results from changes in electricity usage by
II-17

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
customers, weather, and the number of customers. Total retail KWH sales for 2025 and the percent change from 2024 were as follows:
2025
Total
KWHs
Total KWH
Percent Change
Weather-Adjusted
   Percent Change(*)
(in billions)
Residential18.2 0.7 %0.5 %
Commercial13.2 (0.5)0.2 
Industrial20.7 1.1 1.1 
Other0.1 (7.1)(7.1)
Total retail sales
52.2 0.5 %0.7 %
(*)Weather-adjusted KWH sales are estimated using statistical models of the historical relationship between temperatures and energy sales, and then removing the estimated effect of deviations from the normal temperature conditions. Normal temperature conditions are defined as those experienced in Alabama Power's service territory over a specified historical period. This metric is useful because it allows trends in historical operations to be evaluated apart from the influence of weather conditions. Management also considers this metric in developing long-term capital and financial plans.
Weather-adjusted retail energy sales increased by 0.3 billion KWHs in 2025 as compared to 2024. Weather-adjusted residential and commercial KWH sales increased 0.5% and 0.2%, respectively, primarily due to customer growth. Industrial KWH sales increased 1.1% primarily due to increases in the primary metals sector.
Changes in fuel and other cost recovery revenues resulted in an increase in retail revenues in 2025 as compared to 2024 primarily due to higher recoverable fuel costs, as discussed further under "Fuel and Purchased Power Expenses" herein. Electric rates include provisions to recognize the recovery of fuel costs, purchased power costs, PPAs certificated by the Alabama PSC, and costs associated with the NDR. Under these provisions, fuel and other cost recovery revenues generally equal fuel and other cost recovery expenses and do not affect net income. See Note 2 to the financial statements under "Alabama Power" for additional information.
Wholesale Revenues
Wholesale revenues from sales to non-affiliates increased $112 million, or 33.2%, in 2025 as compared to 2024. Details of wholesale revenues from sales to non-affiliated utilities were as follows:
2025
Increase
(Decrease)
from 2024
(in millions)
Capacity and other$134 $27 
Energy315 85 
Total non-affiliated$449 $112 
The increase in wholesale revenues from sales to non-affiliates was due to increases of $45 million related to the volume of KWH sales associated with higher demand, $40 million related to the average cost per KWH sold due to higher Southern Company system fuel and purchased power prices, and $27 million related to non-fuel revenues from wholesale capacity contracts. Wholesale energy sales to non-affiliates totaled 7.6 billion KWHs in 2025, an 18.4% increase as compared to 2024.
Wholesale revenues from sales to non-affiliates consist of PPAs and short-term opportunity sales. Wholesale revenues from PPAs have both capacity and energy components. Wholesale capacity revenues from PPAs are recognized in amounts billable under the contract terms and provide for recovery of fixed costs and a return on investment. Wholesale revenues from sales to non-affiliates will vary depending on fuel prices, the market prices of wholesale energy compared to the cost of Alabama Power's and the Southern Company system's generation, demand for energy within the Southern Company system's electric service territory, and the availability of the Southern Company system's generation. Increases and decreases in energy revenues that are driven by fuel prices are accompanied by an increase or decrease in fuel costs and do not affect net income. Short-term opportunity energy sales are made at market-based rates that generally provide a margin above Alabama Power's variable cost to produce the energy.
Wholesale revenues from sales to affiliates increased $49 million, or 35.3%, in 2025 as compared to 2024. The increase was primarily due to an increase of $48 million related to the average price of energy due to an increase in natural gas prices. Wholesale energy sales to affiliates totaled 5.7 billion KWHs in 2025, a 0.4% increase as compared to 2024.
II-18

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Wholesale revenues from sales to affiliated companies will vary depending on demand and the availability and cost of generating resources at each company. These affiliate sales are made in accordance with the IIC, as approved by the FERC. These transactions do not have a significant impact on earnings since this energy is generally sold at marginal cost.
Other Revenues
In 2025, other operating revenues increased $23 million, or 5.2%, as compared to 2024 primarily due to an $11 million increase in open access transmission tariff sales, a $10 million increase in regulated energy services revenues, $7 million related to undistributed customer bill credits associated with nuclear fuel disposal costs litigation, which was offset by an additional NDR accrual within other operations and maintenance expenses, and a $4 million increase in cogeneration revenues primarily related to higher fuel prices. These increases were partially offset by a $10 million decrease in pole attachment revenues and an $8 million decrease in sales of unregulated products and services. See Note 3 to the financial statements under "Nuclear Fuel Disposal Costs" for additional information.
Fuel and Purchased Power Expenses
Fuel and purchased power expenses were $2.0 billion in 2025, an increase of $300 million, or 17.3%, as compared to 2024. The increase was primarily due to a $159 million increase related to the volume of KWHs generated and purchased and a $141 million increase related to the average cost of fuel and purchased power.
Fuel and purchased power energy transactions do not have a significant impact on earnings since energy expenses are generally offset by energy revenues through Alabama Power's energy cost recovery clause. Alabama Power, along with the Alabama PSC, continuously monitors the under/over recovered balance to determine whether adjustments to billing rates are required. See Note 2 to the financial statements under "Alabama Power – Rate ECR" for additional information.
The mix of fuel sources for the generation of electricity is determined primarily by demand, the unit cost of fuel consumed, and the availability of generating units. Additionally, Alabama Power purchases a portion of its electricity needs from the wholesale market. Energy purchases from non-affiliates will vary depending on the market prices of wholesale energy as compared to the cost of the Southern Company system's generation, demand for energy within the Southern Company system's electric service territory, and the availability of the Southern Company system's generation. Energy purchases from affiliates will vary depending on demand for energy and the availability and cost of generating resources at each company within the Southern Company system. These purchases are made in accordance with the IIC or other contractual agreements, as approved by the FERC.
Details of Alabama Power's generation and purchased power and the related costs were as follows:
20252024
Total generation (in billions of KWHs)
59.4 60.0 
Total purchased power (in billions of KWHs)
9.2 6.9 
Sources of generation (percent)
Coal
36 34 
Gas
36 35 
Nuclear
22 25 
Hydro6 
Cost of fuel, generated (in cents per net KWH)
Coal
3.29 3.19 
Gas
3.20 2.73 
Nuclear
0.73 0.72 
Average cost of fuel, generated (in cents per net KWH)
2.66 2.36 
Average cost of purchased power (in cents per net KWH)(*)
5.92 5.72 
(*)Average cost of purchased power includes fuel, energy, and transmission purchased by Alabama Power for tolling agreements where power is generated by the provider.
Other Operations and Maintenance Expenses
Other operations and maintenance expenses increased $131 million, or 6.9%, in 2025 as compared to 2024. The increase was primarily due to increases of $65 million associated with reliability reserve accruals and reliability-related expenses, $62 million associated with NDR accruals, $27 million in certain employee compensation and benefit expenses, and $21 million in generation expenses primarily associated with planned outages, partially offset by a $36 million impairment loss in 2024 associated with
II-19

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Alabama Power discontinuing the development of a multi-use commercial facility. See Note 1 to the financial statements under "Impairment of Long-Lived Assets" and Note 2 to the financial statements under "Alabama Power – Reliability Reserve Accounting Order" and – "Rate NDR" for additional information.
Depreciation and Amortization
Depreciation and amortization increased $51 million, or 3.5%, in 2025 as compared to 2024 primarily due to additional plant in service related to transmission and distribution facilities.
Taxes Other Than Income Taxes
Taxes other than income taxes increased $27 million, or 5.7%, in 2025 as compared to 2024 primarily due to an increase in utility license taxes resulting from an increase in the tax base.
Allowance for Equity Funds Used During Construction
Allowance for equity funds used during construction increased $12 million, or 21.1%, in 2025 as compared to 2024 primarily due to an increase in capital expenditures subject to AFUDC. See Note 1 to the financial statements under "Allowance for Funds Used During Construction and Interest Capitalized" for additional information.
Interest Expense, Net of Amounts Capitalized
Interest expense, net of amounts capitalized increased $17 million, or 3.8%, in 2025 as compared to 2024. The increase was primarily associated with higher average outstanding borrowings. See FINANCIAL CONDITION AND LIQUIDITY – "Financing Activities" and – "Sources of Capital" herein and Note 8 to the financial statements for additional information.
Other Income (Expense), Net
Other income (expense), net increased $11 million, or 7.0%, in 2025 as compared to 2024 primarily due to the receipt of liquidated damages associated with the termination of two solar projects.
Income Taxes
Income taxes increased $65 million in 2025 as compared to 2024 primarily due to higher pre-tax earnings and a decrease of $39 million in the flowback of certain excess deferred income taxes. See Note 2 to the financial statements under "Alabama Power – Excess Accumulated Deferred Income Tax Accounting Order" and Note 10 to the financial statements for additional information.
Georgia Power
Georgia Power's net income was $2.9 billion in 2025, representing a $308 million, or 12.1%, increase from 2024. The increase was primarily due to higher retail revenues associated with rates and pricing and sales growth, as well as an increase in other revenues, partially offset by increases in depreciation and amortization and other operations and maintenance expenses.
II-20

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
A condensed income statement for Georgia Power follows:
2025
Increase
(Decrease)
from 2024
(in millions)
Retail revenues
$11,110 $923 
Wholesale revenues
525 260 
Other revenues
996 117 
Total operating revenues
12,631 1,300 
Fuel2,040 382 
Purchased power1,517 157 
Other operations and maintenance2,585 234 
Depreciation and amortization2,074 300 
Taxes other than income taxes576 (71)
Total operating expenses8,792 1,002 
Operating income3,839 298 
Allowance for equity funds used during construction248 96 
Interest expense, net of amounts capitalized793 68 
Other income (expense), net159 (19)
Income taxes (benefit)602 (1)
Net income$2,851 $308 
Retail Revenues
Retail revenues increased $923 million, or 9.1%, in 2025 as compared to 2024. Details of the changes in retail revenues were as follows:
2025 vs. 2024
(in millions)
(% change)
Estimated change in retail revenues resulting from —
Rates and pricing$539 5.3 %
Sales growth192 1.9 
Weather(40)(0.4)
Fuel cost recovery232 2.3 
Total change in retail revenues
$923 9.1 %
Changes in rates and pricing resulted in an increase in revenues primarily due to base tariff increases and increased ECCR tariff revenues in accordance with the 2022 ARP, the inclusion of Plant Vogtle Unit 4 in retail rates net of elimination of the NCCR tariff, and higher contributions from commercial and industrial customers with variable demand-driven pricing. See Note 2 to the financial statements under "Georgia Power" for additional information.
II-21

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Changes in sales resulted in an increase in retail revenues in 2025 as compared to 2024. Changes in retail revenues are influenced heavily by the change in the volume of energy sold from year to year, which generally results from changes in electricity usage by customers, weather, and the number of customers. Total retail KWH sales for 2025 and the percent change from 2024 were as follows:
2025
Total
KWHs
Total KWH
Percent Change
Weather-Adjusted
   Percent Change(*)
(in billions)
Residential29.5 1.2 %1.0 %
Commercial35.4 3.9 4.1 
Industrial24.0 1.7 2.1 
Other0.4 (0.2)(0.2)
Total retail sales
89.3 2.4 %2.5 %
(*)Weather-adjusted KWH sales are estimated using statistical models of the historical relationship between temperatures and energy sales, and then removing the estimated effect of deviations from normal temperature conditions. Normal temperature conditions are defined as those experienced in Georgia Power's service territory over a specified historical period. This metric is useful because it allows trends in historical operations to be evaluated apart from the influence of weather conditions. Management also considers this metric in developing long-term capital and financial plans.
Weather-adjusted retail energy sales increased by 2.1 billion KWHs in 2025 as compared to 2024. Weather-adjusted residential sales increased 1.0% primarily due to customer growth. Weather-adjusted commercial KWH sales increased 4.1% primarily due to additional sales from new and existing data centers. Weather-adjusted industrial KWH sales increased 2.1% primarily due to an increase in the electronics and transportation sectors, partially offset by decreases in the textiles and pipeline sectors.
Fuel revenues and costs are allocated between retail and wholesale jurisdictions. Changes in retail fuel cost recovery revenues resulted in an increase in retail revenues in 2025 as compared to 2024 primarily due to higher recoverable fuel costs, as discussed further under "Fuel and Purchased Power Expenses" herein. Electric rates include provisions to adjust billings for fluctuations in fuel costs, including the energy component of purchased power costs. Under these fuel cost recovery provisions, fuel revenues generally equal fuel expenses and do not affect net income. See Note 2 to the financial statements under "Georgia Power – Fuel Cost Recovery" for additional information.
Wholesale Revenues
Wholesale revenues from power sales increased $260 million, or 98.1%, in 2025 as compared to 2024. Details of wholesale revenues were as follows:
2025
Increase
(Decrease)
from 2024
(in millions)
Capacity and other$148 $21 
Energy377 239 
Total $525 $260 
The increase in wholesale revenues from power sales was due to a $239 million increase in energy revenues due to increases of $195 million in fuel-related revenues, of which $118 million related to the volume of KWH sales associated with higher demand and $77 million related to the average cost per KWH sold due to higher Southern Company system fuel and purchased power prices, and $44 million in non-fuel-related energy revenues from wholesale contracts, as well as a $21 million increase in capacity revenues from new and existing power sales agreements. Wholesale energy sales from power sales totaled 9.5 billion KWHs in 2025, a 106.4% increase as compared to 2024.
Wholesale revenues from sales to non-affiliates consist of PPAs and short-term opportunity sales. Wholesale revenues from PPAs have both capacity and energy components. Wholesale capacity revenues from PPAs are recognized in amounts billable under the contract terms and provide for recovery of fixed costs and a return on investment. Wholesale revenues from sales to non-affiliates will vary depending on fuel prices, the market prices of wholesale energy compared to the cost of Georgia Power's and the Southern Company system's generation, demand for energy within the Southern Company system's electric service territory, and the availability of the Southern Company system's generation. Increases and decreases in energy revenues that are driven by fuel prices are accompanied by an increase or decrease in fuel costs and do not have a significant impact on net income. Short-term opportunity sales are made at market-based rates that generally provide a margin above Georgia Power's variable cost of energy.
II-22

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Wholesale revenues from sales to affiliated companies will vary depending on demand and the availability and cost of generating resources at each company. These affiliate sales are made in accordance with the IIC, as approved by the FERC. These transactions do not have a significant impact on earnings since this energy is generally sold at marginal cost.
Other Revenues
In 2025, other operating revenues increased $117 million, or 13.3%, as compared to 2024 primarily due to increases of $80 million in unregulated sales primarily associated with power delivery construction and maintenance, renewables, and resiliency projects, $27 million in revenues from renewable energy programs primarily associated with solar application fees, $22 million in outdoor lighting sales, $17 million in realized gains associated with price stability products for retail customers on variable demand-driven pricing tariffs, and $10 million in customer fees, partially offset by decreases of $15 million in open access transmission tariff sales, $10 million in unregulated sales associated with energy conservation projects, $9 million in regulated sales associated with power delivery construction and maintenance projects, and $8 million in pole attachment revenues.
Fuel and Purchased Power Expenses
Fuel and purchased power expenses were $3.6 billion in 2025, an increase of $539 million, or 17.9%, as compared to 2024. The increase was due to a $288 million increase related to the volume of KWHs generated and purchased, an increase of $196 million related to the average cost of fuel and purchased power, and an increase of $55 million related to credits recorded in 2024 resulting from litigation related to nuclear fuel disposal costs. See Note 3 to the financial statements under "Nuclear Fuel Disposal Costs" for additional information.
Fuel and purchased power energy transactions do not have a significant impact on earnings since these fuel expenses are generally offset by fuel revenues through Georgia Power's fuel cost recovery mechanism. See Note 2 to the financial statements under "Georgia Power – Fuel Cost Recovery" for additional information.
The mix of fuel sources for the generation of electricity is determined primarily by demand, the unit cost of fuel consumed, and the availability of generating units. Additionally, Georgia Power purchases a portion of its electricity needs from the wholesale market. Energy purchases from non-affiliates will vary depending on the market prices of wholesale energy as compared to the cost of the Southern Company system's generation, demand for energy within the Southern Company system's electric service territory, and the availability of the Southern Company system's generation. Energy purchases from affiliates will vary depending on demand for energy and the availability and cost of generating resources at each company within the Southern Company system. These purchases are made in accordance with the IIC or other contractual agreements, all as approved by the FERC.
Details of Georgia Power's generation and purchased power and the related costs were as follows:
20252024
Total generation (in billions of KWHs)(a)
66.3 64.7 
Total purchased power (in billions of KWHs)
35.9 30.8 
Sources of generation (percent) —
Gas40 44 
Nuclear(a)
36 34 
Coal21 19 
Hydro and other3 
Cost of fuel, generated (in cents per net KWH)
Gas3.53 2.88 
Nuclear(a)(b)
0.89 0.96 
Coal4.31 4.94 
Average cost of fuel, generated (in cents per net KWH)(a)(b)
2.72 2.61 
Average cost of purchased power (in cents per net KWH)(c)
5.01 4.65 
(a)Excludes KWHs generated from test period energy at Plant Vogtle Unit 4 prior to being placed in service in April 2024. The related fuel costs were charged to CWIP in accordance with FERC guidance.
(b)Excludes $55 million of credits recorded to nuclear fuel expense in 2024 resulting from litigation related to nuclear fuel disposal costs. See Note 3 to the financial statements under "Nuclear Fuel Disposal Costs" for additional information.
(c)Average cost of purchased power includes fuel purchased by Georgia Power for tolling agreements where power is generated by the provider.
II-23

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Other Operations and Maintenance Expenses
Other operations and maintenance expenses increased $234 million, or 10.0%, in 2025 as compared to 2024. The increase was primarily due to a $114 million gain from the sale of integrated transmission system assets in 2024 and increases of $75 million in generation expenses primarily due to non-outage maintenance expenses largely resulting from Plant Vogtle Unit 4 being placed in service in April 2024, $42 million in certain technology infrastructure and application production costs, $38 million in expenses associated with unregulated power delivery construction and maintenance, energy conservation, and renewables projects, $33 million in certain employee compensation and benefit expenses, and $24 million related to injuries and damages, partially offset by a decrease of $80 million in transmission and distribution costs primarily associated with line maintenance and billings adjustments with integrated transmission system owners and an increase of $39 million in credits to income related to the estimated probable loss on Plant Vogtle Units 3 and 4. See Note 2 to the financial statements under "Georgia Power – Transmission Asset Sales" and " – Nuclear Construction" for additional information.
Depreciation and Amortization
Depreciation and amortization increased $300 million, or 16.9%, in 2025 as compared to 2024 primarily due to increases of $156 million associated with additional plant in service and $123 million in amortization of regulatory assets related to CCR AROs as approved in the 2025 compliance filing under the terms of the 2022 ARP. See Note 2 to the financial statements under "Georgia Power – Rate Plans" for additional information.
Taxes Other Than Income Taxes
Taxes other than income taxes decreased $71 million, or 11.0%, in 2025 as compared to 2024 primarily due to a decrease of $98 million in property taxes primarily resulting from the actualization of prior-year tax assessments, partially offset by an increase of $21 million in municipal franchise fees resulting from higher retail revenues.
Allowance for Equity Funds Used During Construction
Allowance for equity funds used during construction increased $96 million, or 63.2%, in 2025 as compared to 2024 primarily due to an increase in capital expenditures subject to AFUDC, partially offset by the impact of Plant Vogtle Unit 4 being placed in service in April 2024. See Notes 1 and 2 to the financial statements under "Allowance for Funds Used During Construction and Interest Capitalized" and "Georgia Power," respectively, for additional information.
Interest Expense, Net of Amounts Capitalized
Interest expense, net of amounts capitalized increased $68 million, or 9.4%, in 2025 as compared to 2024. The increase was primarily associated with an increase of approximately $71 million related to higher average outstanding borrowings and a decrease of $12 million in net deferred financing costs related to Plant Vogtle Unit 3, partially offset by an increase of $22 million in AFUDC debt related to increased capital expenditures. See FINANCIAL CONDITION AND LIQUIDITY – "Sources of Capital" and – "Financing Activities" herein, Note 1 to the financial statements under "Allowance for Funds Used During Construction and Interest Capitalized," and Note 8 to the financial statements for additional information.
Other Income (Expense), Net
Other income (expense), net decreased $19 million, or 10.7%, in 2025 as compared to 2024 primarily due to a $45 million increase in charitable donations, partially offset by a $15 million increase in customer charges related to contributions in aid of construction.
Income Taxes
Income taxes decreased $1 million, or 0.2%, in 2025 as compared to 2024 primarily due to increases of $77 million in the flowback of excess state deferred income taxes and $21 million in the generation of advanced nuclear PTCs, largely offset by higher pre-tax earnings and a $29 million increase in charges to a valuation allowance on certain state tax credit carryforwards. See Note 10 to the financial statements for additional information.
Mississippi Power
Mississippi Power's net income was $215 million in 2025, representing a $16 million, or 8.0%, increase from 2024. The increase was primarily due to higher retail revenues primarily resulting from changes in rates and pricing, partially offset by increases in depreciation and amortization and other operations and maintenance expenses.
II-24

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
A condensed income statement for Mississippi Power follows:
2025
Increase
(Decrease)
from 2024
(in millions)
Retail revenues
$1,085 $120 
Wholesale revenues, non-affiliates
275 47 
Wholesale revenues, affiliates
280 62 
Other revenues
55 3 
Total operating revenues
1,695 232 
Fuel and purchased power624 147 
Other operations and maintenance387 17 
Depreciation and amortization211 18 
Taxes other than income taxes139 12 
Total operating expenses1,361 194 
Operating income 334 38 
Interest expense, net of amounts capitalized79 2 
Other income (expense), net25 (2)
Income taxes65 18 
Net income $215 $16 
Retail Revenues
Retail revenues for 2025 increased $120 million, or 12.4%, as compared to 2024. Details of the changes in retail revenues were as follows:
2025 vs. 2024
(in millions)(% change)
Estimated change in retail revenues resulting from —
Rates and pricing$47 4.9 %
Sales growth10 1.0 
Weather(2)(0.2)
Fuel and other cost recovery65 6.7 
Total change in retail revenue
$120 12.4 %
Changes in rates and pricing resulted in an increase in revenues primarily due to new PEP rates that became effective for the first billing cycle of April 2025. See Note 2 to the financial statements under "Mississippi Power – Performance Evaluation Plan" for additional information.
Changes in sales resulted in an increase in retail revenues in 2025 as compared to 2024. Changes in retail revenues are influenced heavily by the change in the volume of energy sold from year to year, which generally results from changes in electricity usage by
II-25

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
customers, weather, and the number of customers. Total retail KWH sales for 2025 and the percent change from 2024 were as follows:
2025
Total
KWHs
Total KWH
Percent Change
Weather-Adjusted
   Percent Change(*)
(in millions)
Residential2,140 2.0 %2.1 %
Commercial2,902 (0.7)(0.5)
Industrial4,795 1.3 1.3 
Other21 (11.1)(11.1)
Total retail sales
9,858 0.8 %0.9 %
(*)Weather-adjusted KWH sales are estimated using statistical models of the historical relationship between temperatures and energy sales, and then removing the estimated effect of deviations from normal temperature conditions. Normal temperature conditions are defined as those experienced in Mississippi Power's service territory over a specified historical period. This metric is useful because it allows trends in historical operations to be evaluated apart from the influence of weather conditions. Management also considers this metric in developing long-term capital and financial plans.
Weather-adjusted retail energy sales increased by 86 million KWHs in 2025 as compared to 2024. Weather-adjusted residential KWH sales increased 2.1% primarily due to increased customer usage. Weather-adjusted commercial KWH sales decreased 0.5% primarily due to decreased customer usage. Industrial KWH sales increased 1.3% primarily due to increases in the petroleum and chemicals sectors.
Changes in fuel and other cost recovery revenues resulted in an increase in retail revenues in 2025 as compared to 2024 primarily due to higher recoverable fuel costs, as discussed further under "Fuel and Purchased Power Expenses" herein. Recoverable fuel costs include fuel and purchased power expenses reduced by the fuel and emissions portion of wholesale revenues from energy sold to customers outside Mississippi Power's service territory. Electric rates for Mississippi Power include provisions to adjust billings for fluctuations in fuel costs, including the energy component of purchased power costs. Under these provisions, fuel revenues generally equal fuel expenses, including the energy component of purchased power costs, and do not affect net income. Recoverable fuel costs include fuel and purchased power expenses reduced by the fuel and emissions portion of wholesale revenues from energy sold to customers outside Mississippi Power's service territory. See Note 2 to the financial statements under "Mississippi Power – Fuel Cost Recovery" for additional information.
Wholesale Revenues
Wholesale revenues from sales to non-affiliates increased $47 million, or 20.6%, in 2025 as compared to 2024. Details of wholesale revenues from power sales to non-affiliated utilities, including FERC-regulated MRA sales as well as market-based sales, were as follows:
2025
Increase
(Decrease)
from 2024
(in millions)
Capacity and other$8 $6 
Energy267 41 
Total non-affiliated$275 $47 
The increase in wholesale revenues from sales to non-affiliates was due to a $25 million increase associated with MRA customers largely due to higher recoverable fuel costs, a $15 million increase associated with changes in power supply agreements, and a $7 million increase in opportunity sales. Wholesale energy sales to non-affiliates totaled 3,397 million KWHs in 2025, an 8.5% increase as compared to 2024.
Wholesale revenues from sales to non-affiliates will vary depending on fuel prices, the market prices of wholesale energy compared to the cost of Mississippi Power's and the Southern Company system's generation, demand for energy within the Southern Company system's electric service territory, and the availability of the Southern Company system's generation. Increases and decreases in energy revenues that are driven by fuel prices are accompanied by an increase or decrease in fuel costs and do not have a significant impact on net income. In addition, Mississippi Power provides service under long-term contracts with rural electric cooperative associations and a municipality located in southeastern Mississippi which are subject to regulation by the FERC. The contracts with these wholesale customers represented 12.9% of Mississippi Power's total operating revenues in 2025. Short-term opportunity energy sales are also included in sales for resale to non-affiliates. These opportunity sales are made at
II-26

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
market-based rates that generally provide a margin above Mississippi Power's variable cost to produce the energy. See Note 2 under "Mississippi PowerMunicipal and Rural Associations Tariff" for additional information.
Wholesale revenues from sales to affiliates increased $62 million, or 28.4%, in 2025 as compared to 2024. The increase was primarily due to increases of $44 million related to the price of energy driven by natural gas prices and $16 million related to the volume of KWH sales. Wholesale energy sales to affiliates totaled 5,636 million KWHs in 2025, a 10.4% increase as compared to 2024. See Note 2 to the financial statements under "Mississippi Power – Integrated Resource Plans" for additional information.
Wholesale revenues from sales to affiliates will vary depending on demand and the availability and cost of generating resources at each company. These affiliate sales are made in accordance with the IIC or other contractual agreements, as approved by the FERC. The energy portion of these transactions does not have a significant impact on earnings since this energy is generally sold at marginal cost.
Other Revenues
In 2025, other operating revenues increased $3 million, or 5.8%, as compared to 2024 primarily due to an increase of $8 million in customer charges related to contributions in aid of construction included in rates, partially offset by a decrease of $4 million in transmission revenue primarily associated with open access transmission tariff revenues.
Fuel and Purchased Power Expenses
Fuel and purchased power expenses were $624 million in 2025, an increase of $147 million, or 30.8%, as compared to 2024. The increase was primarily due to a $111 million increase related to the average cost of fuel and a $36 million increase related to the volume of KWHs generated and purchased.
Fuel and purchased power energy transactions do not have a significant impact on earnings since energy expenses are generally offset by energy revenues through Mississippi Power's fuel cost recovery clauses. See Note 2 to the financial statements under "Mississippi Power – Fuel Cost Recovery" for additional information.
The mix of fuel sources for the generation of electricity is determined primarily by demand, the unit cost of fuel consumed, and the availability of generating units. Additionally, Mississippi Power purchases a portion of its electricity needs from the wholesale market. Energy purchases will vary depending on the market prices of wholesale energy as compared to the cost of the Southern Company system's generation, demand for energy within the Southern Company system's electric service territory, and the availability of the Southern Company system's generation. These purchases are made in accordance with the IIC or other contractual agreements, as approved by the FERC.
Details of Mississippi Power's generation and purchased power and the related costs were as follows:
20252024
Total generation (in millions of KWHs)
18,227 17,667 
Total purchased power (in millions of KWHs)
1,167 821 
Sources of generation (percent) —
Gas90 92 
Coal10 
Cost of fuel, generated (in cents per net KWH) —
Gas3.19 2.39 
Coal4.66 5.31 
Average cost of fuel, generated (in cents per net KWH)
3.34 2.65 
Average cost of purchased power (in cents per net KWH)
4.40 4.40 
Other Operations and Maintenance Expenses
Other operations and maintenance expenses increased $17 million, or 4.6%, in 2025 as compared to 2024. The increase was primarily due to increases of $20 million in generation expenses primarily associated with planned outages, $7 million in transmission and distribution expenses primarily associated with routine maintenance, and $3 million in customer service expenses, partially offset by a decrease of $10.9 million due to utilization of the retail reliability reserve to offset generation, transmission, and distribution expenses and a decrease of $8 million due to lower retail reliability reserve accruals. See Note 2 to the financial statements under "Mississippi Power – Reliability Reserve Accounting Order" for additional information.
II-27

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Depreciation and Amortization
Depreciation and amortization increased $18 million, or 9.3%, in 2025 as compared to 2024 primarily due to increases of $10 million resulting from higher depreciation rates and $9 million associated with additional plant in service. See Note 5 to the financial statements under "Depreciation and Amortization" for additional information.
Taxes Other Than Income Taxes
Taxes other than income taxes increased $12 million, or 9.4%, in 2025 as compared to 2024. The increase was primarily due to an increase in property taxes primarily resulting from an increase in the assessed value of property.
Income Taxes
Income taxes increased $18 million, or 38.3%, in 2025 as compared to 2024 primarily due to a decrease of $10 million in the flowback of certain excess deferred income taxes and higher pre-tax earnings. See Note 10 to the financial statements for additional information.
Southern Power
Net income attributable to Southern Power for 2025 was $125 million, a $203 million decrease from 2024. The decrease was primarily due to accelerated depreciation related to wind repowering projects, partially offset by higher revenues driven by higher market prices of energy. See FUTURE EARNINGS POTENTIAL – "Construction Programs" herein and Note 15 to the financial statements under "Southern Power – Wind Repowering Projects" for additional information.
A condensed statement of income for Southern Power follows:
2025
Increase
(Decrease)
from 2024
(in millions)
Operating revenues$2,198 $184 
Fuel676 97 
Purchased power122 44 
Other operations and maintenance528 12 
Depreciation and amortization843 321 
Taxes other than income taxes48 7 
Total operating expenses2,217 481 
Operating income(19)(297)
Interest expense, net of amounts capitalized104 (13)
Other income (expense), net17 4 
Income taxes (benefit)(61)(48)
Net income (loss)
(45)(232)
Net loss attributable to noncontrolling interests(170)(29)
Net income attributable to Southern Power$125 $(203)
Operating Revenues
Total operating revenues include PPA capacity revenues derived primarily from long-term contracts associated with natural gas facilities and PPA energy revenues derived from long-term contracts associated with Southern Power's generation facilities. To the extent Southern Power has capacity not contracted under a PPA, it may sell power into an accessible wholesale market, or, to the extent those generation assets are part of the FERC-approved IIC, it may sell power into the Southern Company power pool.
Natural Gas Capacity and Energy Revenue
Capacity revenues generally represent the greatest contribution to operating income and are designed to provide recovery of fixed costs plus a return on investment.
Energy is generally sold at variable cost or is indexed to published natural gas indices. Energy revenues will vary depending on the energy demand of Southern Power's customers and their generation capacity, as well as the market prices of wholesale energy
II-28

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
compared to the cost of Southern Power's energy. Energy revenues also include fees for support services, fuel storage, and unit start charges. Increases and decreases in energy revenues under PPAs that are driven by fuel or purchased power prices are generally accompanied by an increase or decrease in fuel and purchased power costs and do not have a significant impact on net income.
Solar and Wind Energy Revenue
Southern Power's energy sales from solar and wind generating facilities are predominantly through long-term PPAs that do not have capacity revenue. Customers either purchase the energy output of a dedicated renewable facility through an energy charge or pay a fixed price related to the energy generated from the respective facility and sold to the grid. As a result, Southern Power's ability to recover fixed and variable operations and maintenance expenses is dependent upon the level of energy generated from these facilities, which can be impacted by weather conditions, equipment performance, transmission constraints, and other factors.
See FUTURE EARNINGS POTENTIAL – "Southern Power's Power Sales Agreements" herein for additional information regarding Southern Power's PPAs.
Operating Revenues Details
Details of Southern Power's operating revenues were as follows:
20252024
(in millions)
PPA capacity revenues $513 $497 
PPA energy revenues 1,408 1,228 
Total PPA revenues1,921 1,725 
Non-PPA revenues 259 252 
Other revenues18 37 
Total operating revenues$2,198 $2,014 
Operating revenues for 2025 were $2.2 billion, a $184 million, or 9.1%, increase from 2024. The change in operating revenues was primarily due to the following:
PPA capacity revenues increased $16 million, or 3.2%, due to a net increase in MW capacity under contract from natural gas PPAs, partially offset by a decrease associated with a change in rates from natural gas PPAs.
PPA energy revenues increased $180 million, or 14.7%, primarily due to an increase of $96 million largely driven by fuel and purchased power prices and an increase of $87 million related to the volume of KWHs sold under natural gas PPAs.
Non-PPA revenues increased $7 million, or 2.8%, due to an increase of $72 million driven by the market price of energy, largely offset by a decrease of $67 million related to the volume of KWHs sold through short-term sales.
Other revenues decreased $19 million, or 51.4%, primarily due to a $16 million decrease associated with transmission revenues.
Fuel and Purchased Power Expenses
Details of Southern Power's generation and purchased power were as follows:
Total KWHs
2025 vs. 2024
20252024
Percent Change
(in billions of KWHs)
Generation45 44 
Purchased power3 
Total generation and purchased power48 46 4.3 %
Total generation and purchased power (excluding solar, wind, fuel cells, and tolling agreements)
22 28 (21.4)%
Southern Power's PPAs for natural gas generation generally provide that the purchasers are responsible for either procuring the fuel (tolling agreements) or reimbursing Southern Power for substantially all of the cost of fuel relating to the energy delivered under such PPAs. Consequently, changes in such fuel costs are generally accompanied by a corresponding change in related fuel revenues and do not have a significant impact on net income. Southern Power is responsible for the cost of fuel for generating
II-29

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
units that are not covered under PPAs. Power from these generating units is sold into the wholesale market or into the Southern Company power pool for capacity owned directly by Southern Power.
Purchased power expenses will vary depending on demand, availability, and the cost of generating resources throughout the Southern Company system and other contract resources. Load requirements are submitted to the Southern Company power pool on an hourly basis and are fulfilled with the lowest cost alternative, whether that is generation owned by Southern Power, an affiliate company, or external parties. Such purchased power costs are generally recovered through PPA revenues.
Details of Southern Power's fuel and purchased power expenses were as follows:
20252024
(in millions)
Fuel$676 $579 
Purchased power122 78 
Total fuel and purchased power expenses$798 $657 
Total fuel and purchased power expenses increased $141 million, or 21.5%, in 2025 as compared to 2024. Fuel expense increased $97 million, or 16.8%, due to an increase of $232 million associated with the average cost of fuel, largely offset by a decrease of $135 million related to the volume of KWHs generated. Purchased power expense increased $44 million, or 56.4%, due to an increase of $29 million associated with the average cost of purchased power and an increase of $15 million related to the volume of KWHs purchased.
Depreciation and Amortization
Depreciation and amortization increased $321 million, or 61.5%, in 2025 as compared to 2024 primarily due to a $298 million increase in accelerated depreciation related to wind repowering projects. See FUTURE EARNINGS POTENTIAL – "Construction Programs" herein and Note 15 to the financial statements under "Southern Power – Wind Repowering Projects" for additional information.
Interest Expense, Net of Amounts Capitalized
Interest expense, net of amounts capitalized decreased $13 million, or 11.1%, in 2025 as compared to 2024. The decrease was primarily due to an $18 million increase in capitalized interest associated with construction and wind repowering projects, partially offset by a $5 million increase in interest expense related to higher average outstanding borrowings. See FINANCIAL CONDITION AND LIQUIDITY – "Sources of Capital" and – "Financing Activities" herein and Note 8 to the financial statements for additional information.
Income Taxes (Benefit)
Income tax benefit increased $48 million in 2025 as compared to 2024 primarily due to a decrease in pre-tax earnings attributable to Southern Power. See Notes 1, 10, and 15 to the financial statements under "Income Taxes," "Effective Tax Rate," and "Southern Power – Wind Repowering Projects," respectively, for additional information.
Net Loss Attributable to Noncontrolling Interests
Net loss attributable to noncontrolling interests increased $29 million, or 20.6%, in 2025 as compared to 2024. The increased loss was primarily due to $20 million in higher HLBV loss allocations to tax equity partners and $11 million in lower income allocations to equity partners.
Southern Company Gas
Southern Company Gas uses Heating Degree Days to measure weather and the operational effects on its business. Generally, increased Heating Degree Days result in higher demand for natural gas on Southern Company Gas' distribution system. However, Southern Company Gas has various regulatory mechanisms, such as weather and revenue normalization and straight-fixed-variable rate design, which limit positive or negative impacts to income from exposure to weather changes within typical ranges in each of its utility's respective service territory. Southern Company Gas also utilizes weather hedges to limit the negative income impacts in the event of warmer-than-normal weather in Illinois and Georgia for gas marketing services. Therefore, weather typically does not have a significant net income impact.
During the Heating Season, more customers are connected to the gas distribution systems and natural gas usage is higher in periods of colder weather. Southern Company Gas' base operating expenses, excluding cost of natural gas and bad debt expense, are incurred relatively evenly throughout the year. Seasonality also affects the comparison of certain balance sheet items across
II-30

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
quarters, including receivables, unbilled revenues, natural gas for sale, and notes payable. Thus, Southern Company Gas' operating results can vary significantly from quarter to quarter as a result of seasonality. The impact of Heating Season on Southern Company Gas' annual results is illustrated in the table below.
Percent Generated During
Heating Season
Operating
Revenues
Net
Income
202566 %82 %
202462 %80 %
Net Income
Net income attributable to Southern Company Gas in 2025 was $732 million, a decrease of $8 million, or 1.1%, compared to 2024. The decrease was primarily due to a $16 million decrease in net income at gas pipeline investments and a $15 million decrease in net income at gas marketing services, partially offset by a $19 million increase in net income at gas distribution operations.
A condensed income statement for Southern Company Gas follows:
2025
Increase
(Decrease)
from 2024
(in millions)
Natural gas revenues
$5,044 $588 
Cost of natural gas1,599 403 
Other operations and maintenance1,297 62 
Depreciation and amortization708 58 
Taxes other than income taxes272 24 
Estimated loss on regulatory disallowance63 63 
Total operating expenses3,939 610 
Operating income1,105 (22)
Earnings from equity method investments127 (19)
Interest expense, net of amounts capitalized377 36 
Other income (expense), net59 (7)
Income taxes182 (76)
Net Income$732 $(8)
Natural Gas Revenues
Natural gas revenues in 2025 were $5.0 billion, reflecting a $588 million, or 13.2%, increase compared to 2024. Details of natural gas revenues were as follows:
2025 vs. 2024
(in millions)
(% change)
Estimated change in natural gas revenues resulting from —
Rate changes$146 3.3 %
Gas costs and other cost recovery372 8.3 
Gas marketing services61 1.4 
Other9 0.2 
Total change in natural gas revenues
$588 13.2 %
Changes in rates resulted in an increase in revenues in 2025 as compared to 2024 primarily due to base rate increases at Atlanta Gas Light and Virginia Natural Gas. See Note 2 to the financial statements under "Southern Company Gas – Rate Proceedings" for additional information.
II-31

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Revenues associated with gas costs and other cost recovery increased in 2025 as compared to 2024 primarily due to higher cost of natural gas driven by higher natural gas prices and volumes, as well as increases in other expenses passed through to customers. Natural gas distribution rates include provisions to adjust billings for fluctuations in natural gas costs. Therefore, gas costs recovered through natural gas revenues generally equal the amount expensed in cost of natural gas and do not affect net income from gas distribution operations. See "Cost of Natural Gas" and "Other Operations and Maintenance Expenses" herein for additional information.
Revenues from gas marketing services increased in 2025 as compared to 2024 primarily due to higher commodity prices.
Customer Count
The number of customers served by gas distribution operations and gas marketing services can be impacted by natural gas prices, economic conditions, and competition from alternative fuels. Gas distribution operations' and gas marketing services' customers are primarily located in Georgia and Illinois.
The following table provides the number of customers served by Southern Company Gas at December 31, 2025 and 2024:
20252024
(in thousands, except market share percent)
Gas distribution operations4,416 4,387 
Gas marketing services
Energy customers677 668 
Market share of energy customers in Georgia29.9 %29.8 %
Southern Company Gas anticipates customer growth and uses a variety of targeted marketing programs to attract new customers and to retain existing customers.
Cost of Natural Gas
Excluding Atlanta Gas Light, which does not sell natural gas to end-use customers, natural gas distribution rates include provisions to adjust billings for fluctuations in natural gas costs. Therefore, gas costs recovered through natural gas revenues generally equal the amount expensed in cost of natural gas and do not affect net income from gas distribution operations. See Note 2 to the financial statements under "Southern Company Gas – Natural Gas Cost Recovery" for additional information. Cost of natural gas at gas distribution operations represented 81.7% of the total cost of natural gas for 2025.
Gas marketing services customers are charged for actual and estimated natural gas consumed. Cost of natural gas includes the cost of fuel and associated transportation costs, lost and unaccounted for gas, and gains and losses associated with certain derivatives.
Cost of natural gas was $1.6 billion, an increase of $403 million, or 33.7%, in 2025 as compared to 2024, which reflects higher gas cost recovery in 2025 as a result of a 51.0% increase in natural gas prices as compared to 2024.
Volumes of Natural Gas Sold
Southern Company Gas' natural gas volume metrics for gas distribution operations and gas marketing services illustrate the effects of weather and customer demand for natural gas.
The following table details the volumes of natural gas sold during 2025 and 2024:
2025 vs. 2024
20252024
Percent Change
Gas distribution operations (mmBtu in millions)
Firm688 626 9.9 %
Interruptible87 92 (5.4)
Total775 718 7.9 %
Gas marketing services (mmBtu in millions)
Firm
61 56 8.9 
Interruptible large commercial and industrial13 15 (13.3)
Total74 71 4.2 %
II-32

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Other Operations and Maintenance Expenses
Other operations and maintenance expenses increased $62 million, or 5.0%, in 2025 as compared to 2024. The increase was primarily due to increases of $38 million in employee compensation and benefit expenses, $23 million in expenses passed through to customers at gas distribution operations, and $17 million in bad debt expense, partially offset by a decrease of $26 million related to certain deferred expenses.
Depreciation and Amortization
Depreciation and amortization increased $58 million, or 8.9%, in 2025 as compared to 2024. The increase was primarily due to additional plant in service related to continued investments at the natural gas distribution utilities. See Note 2 to the financial statements under "Southern Company Gas – Infrastructure Replacement Programs and Capital Projects" for additional information.
Taxes Other Than Income Taxes
Taxes other than income taxes increased $24 million, or 9.7%, in 2025 as compared to 2024. The increase was primarily due to an increase in revenue taxes as a result of higher natural gas revenues at Nicor Gas. Revenue taxes imposed on Nicor Gas are recoverable from its customers.
Estimated Loss on Regulatory Disallowance
In 2025, Southern Company Gas recorded $63 million in charges related to the disallowance of certain capital investments at Nicor Gas. See Note 2 to the financial statements under "Southern Company Gas – Rate Proceedings – Nicor Gas" for additional information.
Earnings from Equity Method Investments
Earnings from equity method investments decreased $19 million, or 13.0%, in 2025 as compared to 2024. The decrease was primarily due to legal settlements, increased spending on system integrity initiatives, and lower rates, all at SNG. See Note 7 to the financial statements under "Southern Company Gas" for additional information.
Interest Expense, Net of Amounts Capitalized
Interest expense, net of amounts capitalized increased $36 million, or 10.6%, in 2025 as compared to 2024. The increase was primarily associated with higher average outstanding borrowings. See FINANCIAL CONDITION AND LIQUIDITY – "Sources of Capital" and – "Financing Activities" herein and Note 8 to the financial statements for additional information.
Income Taxes
Income taxes decreased $76 million, or 29.5%, in 2025 as compared to 2024. The decrease was primarily due to lower pre-tax earnings, including the impact of the regulatory disallowance at Nicor Gas, an increase of $36 million in the flowback of excess federal and state deferred income taxes, and a decrease of $8 million related to uncertain state tax positions in 2024. See Note 2 to the financial statements under "Southern Company Gas – Rate Proceedings – Nicor Gas" and Note 10 to the financial statements for additional information.
Segment Information
20252024
Operating
Revenues
Operating
Expenses
Net Income
(Loss)
Operating
Revenues
Operating
Expenses
Net Income
(Loss)
(in millions)(in millions)
Gas distribution operations$4,428 $3,450 $569 $3,899 $2,911 $550 
Gas pipeline investments32 10 85 32 10 101 
Gas marketing services582 457 87 516 375 102 
All other12 17 (9)23 33 (13)
Intercompany eliminations(10)5  (14)— — 
Consolidated$5,044 $3,939 $732 $4,456 $3,329 $740 
II-33

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Gas Distribution Operations
The gas distribution operations segment is the largest component of Southern Company Gas' business and is subject to regulation and oversight by regulatory agencies in each of the states it serves. These agencies approve natural gas rates designed to provide Southern Company Gas with the opportunity to generate revenues to recover the cost of natural gas delivered to its customers and its fixed and variable costs, including depreciation, interest expense, operations and maintenance, taxes, and overhead costs, and to earn a reasonable return on its investments.
With the exception of Atlanta Gas Light, Southern Company Gas' second largest utility that operates in a deregulated natural gas market and has a straight-fixed-variable rate design that minimizes the variability of its revenues based on consumption, the earnings of the natural gas distribution utilities can be affected by customer consumption patterns that are a function of price levels for natural gas and general economic conditions that may impact customers' ability to pay for natural gas consumed. Southern Company Gas has various regulatory and other mechanisms, such as weather and revenue normalization mechanisms, that limit its exposure to changes in customer consumption, including weather changes within typical ranges in its natural gas distribution utilities' service territories. See Note 2 to the financial statements under "Southern Company Gas" for additional information.
In 2025, net income increased $19 million, or 3.5%, as compared to 2024 as described further below:
Operating revenues increased $529 million primarily due to higher gas cost recovery and base rate increases. Gas costs recovered through natural gas revenues generally equal the amount expensed in cost of natural gas.
Operating expenses increased $539 million primarily due to a $346 million increase in cost of natural gas as a result of higher gas prices and higher volumes sold compared to 2024, a $63 million charge related to the disallowance of certain capital investments at Nicor Gas, a $57 million increase in depreciation primarily due to additional plant in service related to continued investments at the natural gas distribution utilities, a $43 million increase related to expenses passed through to customers, a $25 million increase related to employee compensation and benefit expenses, and a $17 million increase in bad debt expense, partially offset by a decrease of $26 million related to certain deferred expenses.
Interest expense, net of amounts capitalized increased $31 million primarily due to higher average outstanding borrowings.
Income taxes decreased $63 million primarily due to lower pre-tax earnings, including the impact of the regulatory disallowance at Nicor Gas, and an increase in the flowback of excess federal and state deferred income taxes.
See Note 2 to the financial statements under "Southern Company Gas – Rate Proceedings – Nicor Gas" for additional information.
Gas Pipeline Investments
The gas pipeline investments segment consists primarily of joint ventures in natural gas pipeline investments including SNG and Dalton Pipeline. See Note 7 to the financial statements under "Southern Company Gas" for additional information. In 2025, net income decreased $16 million, or 15.8%, as compared to 2024 primarily due to legal settlements, increased spending on system integrity initiatives, and lower rates at SNG.
Gas Marketing Services
The gas marketing services segment provides energy-related products and services to natural gas markets and participants in customer choice programs that were approved in various states to increase competition. These programs allow customers to choose their natural gas supplier while the local distribution utility continues to provide distribution and transportation services. Gas marketing services is weather sensitive and uses a variety of hedging strategies, such as weather derivative instruments and other risk management tools, to partially mitigate potential weather impacts.
In 2025, net income decreased $15 million, or 14.7%, as compared to 2024. The decrease was due to an $82 million increase in operating expenses primarily related to an increase in cost of natural gas and an increase in charitable contributions, partially offset by a $66 million increase in operating revenues primarily due to higher commodity prices.
All Other
All other includes a renewable natural gas business, AGL Services Company, and Southern Company Gas Capital, as well as various corporate operating expenses that are not allocated to the reportable segments and interest income (expense) associated with affiliate financing arrangements.
II-34

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
FUTURE EARNINGS POTENTIAL
General
Prices for electric service provided by the traditional electric operating companies and natural gas distribution service provided by the natural gas distribution utilities to retail customers are set by state PSCs or other applicable state regulatory agencies under cost-based regulatory principles. Retail rates and earnings are reviewed through various regulatory mechanisms and/or processes and may be adjusted periodically within certain limitations. The ability of the traditional electric operating companies and the natural gas distribution companies to effectively operate pursuant to these regulatory mechanisms and/or processes and appropriately balance required costs and capital expenditures with customer prices will continue to be a challenge for the foreseeable future. Prices for wholesale electricity sales, interconnecting transmission lines, and the exchange of electric power are regulated by the FERC. Southern Power continues to focus on long-term PPAs. See ACCOUNTING POLICIES – "Application of Critical Accounting Policies and Estimates – Utility Regulation" herein and Note 2 to the financial statements for additional information about regulatory matters.
Each Registrant's results of operations are not necessarily indicative of its future earnings potential. The level of the Registrants' future earnings depends on numerous factors that affect the opportunities, challenges, and risks of the Registrants' primary businesses of selling electricity and/or distributing natural gas, as described further herein. The Registrants are unable to predict changes in law, regulations, regulatory guidance, legal interpretations, policy positions, and implementation actions that may occur in the future.
For the traditional electric operating companies, these factors include the ability to maintain constructive regulatory environments that allow for the timely recovery of prudently-incurred costs during a time of increasing costs, including those related to projected long-term demand growth, stringent environmental standards, including CCR rules, safety, system reliability and resiliency, fuel, restoration following major storms, and capital expenditures, including constructing new electric generating plants, extending the retirement dates of certain fossil fuel plants, and expanding and improving the transmission and distribution systems; continued customer growth; and the trends of an uncertain inflationary environment and reduced electricity usage per customer, especially in residential and commercial markets.
Earnings in the electricity business will also depend upon maintaining and growing sales and pricing of large load customers such that incremental costs are met with adequate incremental revenues, considering, among other things, recent trends driving projected growth in electricity consumption including the increasing digitization of the economy and growth in data centers, an increase in industrial activity in the Southern Company system's electric service territory, and continued electrification of transportation. Historically, the traditional electric operating companies have entered into large load contracts that support economic development and benefit existing customers; since 2023, the traditional electric operating companies have contracted with new data centers and other large load customers covering approximately nine GWs of electric load, with each contract individually representing a maximum annual electric load greater than 100 MWs, that have been signed by the parties and/or reviewed by the state regulatory commissions. These new contracts fully ramp up over several years after commencement of service. Some of these contracts are already in effect. Service under the contracts is expected to begin through 2028. The contracts contain various terms and conditions, such as minimum duration, minimum bill provisions, contribution by the customer to local construction costs, termination payment requirements, and financial security, designed to generate adequate incremental revenues associated with incremental costs to serve these customers. These projected growth opportunities may be affected by a variety of factors, such as energy efficiency, changes in technology, reliability and operational factors, customer demand, and government policies, which could increase or decrease the pace of growth associated with these opportunities. In addition, these opportunities present risks such as capital access and cost recovery risks. See Note 2 to the financial statements under "Georgia Power – Integrated Resource Plans" for additional information regarding Georgia Power's related regulatory proceedings.
The level of future earnings for Southern Power's competitive wholesale electric business depends on numerous factors including the parameters of the wholesale market and the efficient operation of its wholesale generating assets; Southern Power's ability to execute its growth strategy through the development, construction, or acquisition of generating facilities and other energy projects while containing costs; regulatory matters; customer creditworthiness; total electric generating capacity available in Southern Power's market areas; Southern Power's ability to successfully remarket capacity as current contracts expire; renewable portfolio standards; continued availability of federal and state ITCs and PTCs under current and future tax legislation and U.S. Treasury guidance; transmission constraints; cost of generation from units within the Southern Company power pool; and operational limitations. See "Income Tax Matters" herein for information regarding the IRA's expansion of the availability of federal ITCs and PTCs and the OBBB's restrictions on federal ITCs and PTCs. Also see Notes 10 and 15 to the financial statements for additional information.
The level of future earnings for Southern Company Gas' primary business of distributing natural gas and its complementary businesses in the gas pipeline investments and gas marketing services sectors depends on numerous factors. These factors include
II-35

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
the natural gas distribution utilities' ability to maintain constructive regulatory environments that allow for the timely recovery of prudently-incurred costs, including those related to projected long-term demand growth, safety, system reliability and resiliency, natural gas, and capital expenditures, including expanding and improving the natural gas distribution systems; the completion and subsequent operation of ongoing infrastructure and other construction projects; customer creditworthiness; and certain policies to limit the use of natural gas, such as the potential in Illinois and across certain other parts of the United States for state or municipal bans on the use of natural gas or policies designed to promote electrification. The volatility of natural gas prices has an impact on Southern Company Gas' customer rates, its long-term competitive position against other energy sources, and the ability of Southern Company Gas' gas marketing services business to capture value from locational and seasonal spreads. Additionally, changes in commodity prices, primarily driven by tight gas supplies, geopolitical events, and diminished gas production, subject a portion of Southern Company Gas' operations to earnings variability and may result in higher natural gas prices. Additional economic factors may contribute to this environment. The demand for natural gas may increase, including from large customers, which may cause natural gas prices to rise and drive higher volatility in the natural gas markets on a longer-term basis. Alternatively, a significant drop in oil and natural gas prices could lead to a consolidation of natural gas producers or reduced levels of natural gas production.
Earnings for both the electricity and natural gas businesses are subject to a variety of other factors. These factors include weather; competition; developing new and maintaining existing energy contracts and associated load requirements with wholesale customers; demand growth from data centers and other large load customers and associated load and operating requirements; customer energy conservation practices; the use of alternative energy sources by customers; government incentives to reduce overall energy usage; fuel, labor, and material prices in an environment of heightened inflation and material and labor supply chain disruptions; and the price elasticity of demand. Demand for electricity and natural gas in the Registrants' service territories is primarily driven by the pace of economic growth or decline that may be affected by changes in regional and global economic conditions and could be influenced by changes in technology, public policy, utility efficiency programs, and customer behavior. Significant changes in fiscal, monetary, or trade policies could affect actual economic activity and historical economic relationships in ways not anticipated in economic outlooks or Southern Company system plans. Additionally, changes in inflation, interest rates, and credit market conditions could affect the cost of doing business. All of these factors may impact future earnings. See RESULTS OF OPERATIONS herein for information on energy sales in the Southern Company system's service territory during 2025.
Mississippi Power provides service under long-term contracts with rural electric cooperative associations and a municipality located in southeastern Mississippi which are subject to regulation by the FERC. The contracts with these wholesale customers represented 12.9% of Mississippi Power's total operating revenues in 2025. See Note 2 to the financial statements under "Mississippi Power – Municipal and Rural Associations Tariff" for information on a rate settlement related to Mississippi Power's contract with Cooperative Energy through the end of 2035.
As part of its ongoing effort to adapt to changing market conditions, Southern Company continues to evaluate and consider a wide array of potential business strategies. These strategies may include business combinations, partnerships, joint ventures, and acquisitions involving other utility or non-utility businesses or properties, disposition of, or the sale of interests in, certain assets or businesses, internal restructuring, or some combination thereof. Furthermore, Southern Company may engage in new business ventures that arise from competitive and regulatory changes in the utility industry. Pursuit of any of the above strategies, or any combination thereof, may significantly affect the business operations, risks, and financial condition of Southern Company. In addition, Southern Power and Southern Company Gas regularly consider and evaluate joint development arrangements as well as acquisitions and/or dispositions of businesses and assets as part of their business strategies. See Note 15 to the financial statements and "Construction Programs" herein for additional information.
Environmental Matters
The Southern Company system's operations are regulated by state and federal environmental agencies through a variety of laws and regulations governing air, water, land, avian and other wildlife and habitat protection, and other natural resources. The Southern Company system maintains comprehensive environmental compliance and GHG strategies to assess both current and upcoming requirements and compliance costs associated with these environmental laws and regulations. New or revised environmental laws and regulations could further affect many areas of operations for the Subsidiary Registrants. The costs required to comply with environmental laws and regulations and to achieve stated goals, including capital expenditures, operations and maintenance costs, and costs reflected in ARO liabilities, may impact future electric generating unit retirement and replacement decisions (which are generally subject to approval from the traditional electric operating companies' respective state PSCs), results of operations, cash flows, and/or financial condition. Related costs may result from the installation of additional environmental controls, closure and monitoring of CCR facilities, unit extensions or retirements and replacements, or changing fuel sources for certain existing units, as well as related upgrades to the Southern Company system's transmission and distribution (electric and natural gas) systems. A major portion of these costs is expected to be recovered through retail and wholesale rates,
II-36

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
including existing ratemaking and billing provisions. The ultimate impact of environmental laws and regulations and the GHG goals discussed herein cannot be determined at this time and will depend on various factors, such as state adoption and implementation of requirements, the availability and cost of any deployed technology, fuel prices, the outcome of pending and/or future legal challenges and regulatory matters, and the ability to continue recovering the related costs, through rates for the traditional electric operating companies and the natural gas distribution utilities and/or through long-term wholesale agreements for the traditional electric operating companies and Southern Power.
Alabama Power and Mississippi Power recover environmental compliance costs through separate mechanisms, Rate CNP Compliance and the ECO Plan, respectively. Georgia Power's base rates include an ECCR tariff that allows for the recovery of environmental compliance costs. The natural gas distribution utilities generally recover environmental remediation expenditures through rate mechanisms approved by their applicable state regulatory agencies. See Notes 2 and 3 to the financial statements for additional information.
Southern Power's PPAs generally contain provisions that permit charging the counterparty for some of the new costs incurred as a result of changes in environmental laws and regulations. Since Southern Power's units are generally newer natural gas and renewable generating facilities, costs associated with environmental compliance for these facilities have been less significant than for similarly situated coal or older natural gas generating facilities. Environmental, natural resource, and land use concerns, including the applicability of air quality limitations, the potential presence of wetlands or threatened and endangered species, the availability of water withdrawal rights, uncertainties regarding impacts such as increased light or noise, and concerns about potential adverse health impacts can, however, increase the cost of siting and/or operating any type of existing or future facility. The impact of such laws, regulations, and other considerations on Southern Power and subsequent recovery through PPA provisions cannot be determined at this time.
Further, increased costs that are recovered through regulated rates could contribute to reduced demand for electricity and natural gas, which could negatively affect results of operations, cash flows, and/or financial condition. Additionally, many commercial and industrial customers may also be affected by existing and future environmental requirements, which may have the potential to affect their demand for electricity and natural gas.
Although the timing, requirements, and estimated costs could change materially as environmental laws and regulations are adopted or modified, as compliance plans are revised or updated, and as legal challenges to rules are initiated or completed, estimated capital expenditures through 2030 based on the current environmental compliance strategy for the Southern Company system and the traditional electric operating companies are as follows:
20262027202820292030Total
(in millions)
Southern Company$247 $231 $331 $187 $103 $1,099 
Alabama Power(a)
118 140 234 72 26 590 
Georgia Power117 68 60 65 69 379 
Mississippi Power(b)
11 23 38 51 132 
(a)Excludes amounts related to Alabama Power's decision to convert Plant Barry Unit 5 from coal to natural gas totaling $38 million in 2026, $15 million in 2027, and $54 million in 2028. See "Environmental Laws and Regulations – Water Quality" herein and Note 2 to the financial statements under "Alabama Power – Environmental Accounting Order" for additional information.
(b)Includes amounts contingent upon approval by the Mississippi PSC related to Mississippi Power's decision to convert Plant Daniel Unit 2 from coal to natural gas totaling $28 million in 2028 and $41 million in 2029. See Note 2 to the financial statements under "Mississippi Power – Integrated Resource Plans" for additional information.
These estimates do not include compliance costs associated with regulation of GHG emissions. See "Environmental Laws and Regulations – Greenhouse Gases" herein for additional information. The Southern Company system also anticipates substantial expenditures associated with surface impoundment closure and groundwater monitoring under the CCR Rule and related state rules, which are reflected in the applicable Registrants' ARO liabilities. See FINANCIAL CONDITION AND LIQUIDITY – "Cash Requirements" herein and Note 6 to the financial statements for additional information.
Environmental Laws and Regulations
Air Quality
In February 2023, the EPA published a final rule disapproving 19 state implementation plans (SIPs), including SIPs submitted by the States of Alabama and Mississippi, under the interstate transport (good neighbor) provisions of the Clean Air Act for the 2015 Ozone National Ambient Air Quality Standards (NAAQS). In March 2023, the State of Mississippi and Mississippi Power challenged the EPA's disapproval of the Mississippi SIP in the U.S. Court of Appeals for the Fifth Circuit. In June 2023, the U.S.
II-37

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Court of Appeals for the Fifth Circuit stayed the EPA's disapproval of the Mississippi SIP, and, on March 25, 2025, the court vacated and remanded the EPA's disapproval of the Mississippi SIP. On May 9, 2025, other parties to the case requested en banc review before the full U.S. Court of Appeals for the Fifth Circuit. The stay remains in effect, which protects the State of Mississippi from the requirements of the federal good neighbor plan. In April 2023, the State of Alabama, Alabama Power, and PowerSouth Energy Cooperative challenged the EPA's disapproval of the Alabama SIP in the U.S. Court of Appeals for the Eleventh Circuit. In August 2023, the U.S. Court of Appeals for the Eleventh Circuit stayed the EPA's disapproval of the Alabama SIP, pending appeal, which protects the State of Alabama from the requirements of a federal good neighbor plan pending resolution of the case. The case is currently being held in abeyance. On January 30, 2026, the EPA published the proposed Phase 1 rule reconsideration of the good neighbor plan which includes a reconsideration of the EPA's previous disapprovals of ozone interstate transport SIPs from multiple states, including Alabama and Mississippi.
In June 2023, the EPA published the 2015 Ozone NAAQS good neighbor federal implementation plan (FIP), which requires reductions in nitrogen oxides emissions from sources in 23 states, including Alabama and Mississippi for the 2015 Ozone NAAQS. Georgia and North Carolina have approved interstate transport SIPs addressing the 2015 Ozone NAAQS and are not subject to this rule. In June 2023, the State of Mississippi and Mississippi Power challenged the FIP for Mississippi in the U.S. Court of Appeals for the Fifth Circuit. In August 2023, the State of Alabama, Alabama Power, and PowerSouth Energy Cooperative challenged the FIP for Alabama in the U.S. Court of Appeals for the Eleventh Circuit. Both cases are being held in abeyance. In June 2024, the U.S. Supreme Court stayed the FIP pending the disposition of petitions for review of the FIP in the U.S. Court of Appeals for the D.C. Circuit and any petition for writ of certiorari to the U.S. Supreme Court. On March 12, 2025, the EPA announced its intent to reconsider the FIP.
The ultimate impact of the FIP and associated legal matters cannot be determined at this time; however, implementation of the stayed FIP and underlying SIPs would likely result in increased compliance costs for the traditional electric operating companies.
Water Quality
In May 2024, the EPA published the final rule revising the Steam Effluent Guidelines (2024 ELG Rule), which establishes more stringent limits for flue gas desulfurization wastewater, bottom ash transport water , and combustion residual leachate to be met no later than December 31, 2029. The 2024 ELG Rule maintains the 2020 ELG rule's permanent cessation of coal combustion (PCCC) subcategory and the existing rule's voluntary incentive program (VIP) compliance option. It also adds a new PCCC subcategory which allows units to cease coal combustion by December 31, 2034 as opposed to meeting the new more stringent requirements. The 2024 ELG Rule also establishes limitations for legacy wastewater. Numerous groups and states filed petitions for review challenging the rule in multiple federal circuit courts, and, in June 2024, the challenges were consolidated in the U.S. Court of Appeals for the Eighth Circuit. On February 28, 2025, the U.S. Court of Appeals for the Eighth Circuit placed the 2024 ELG Rule litigation in abeyance pending additional rulemaking. On December 31, 2025, the EPA published a final rule to extend certain 2024 ELG Rule compliance deadlines (ELG Deadline Extensions Rule), and, subsequently, multiple petitions for review were filed challenging the ELG Deadline Extensions Rule, which have been consolidated in the U.S. Court of Appeals for the Second Circuit. The EPA also indicated in this rulemaking that it will further evaluate whether to reconsider the 2024 ELG Rule technology requirements. The ultimate impacts of the 2024 ELG Rule, the ELG Deadline Extensions Rule, and associated legal matters cannot be determined at this time; however, they may result in significant compliance costs.
In 2021, Alabama Power submitted Notices of Planned Participation (NOPPs) to the Alabama Department of Environmental Management (ADEM) indicating plans to retire Plant Barry Unit 5 (700 MWs) and to cease using coal and begin operating solely on natural gas at Plant Gaston Unit 5 (880 MWs). However, subsequent to December 31, 2025, as a result of projected future generation needs, a decision was made to convert Plant Barry Unit 5 from coal to natural gas and to continue operating Plant Barry Unit 5 beyond December 31, 2028. As agent for SEGCO, Alabama Power indicated plans to retire Plant Gaston Units 1 through 4 (1,000 MWs) by December 31, 2028. However, upon further analysis, Alabama Power, in conjunction with Georgia Power, now expects to operate Plant Gaston Units 1 through 4 through December 31, 2034. As of December 31, 2025, Alabama Power is in compliance with the 2020 ELG rule generally applicable limits for bottom ash transport water for Plant Gaston Units 1 through 4. On December 30, 2025, pursuant to the 2024 ELG Rule, Alabama Power submitted additional NOPPs to the ADEM for Plant Barry Units 4 and 5, Plant Gaston Unit 5, and Plant Gorgas, opting in to the PCCC compliance subcategory for combustion residual leachate discharges by December 31, 2034. See Notes 2 and 7 to the financial statements under "Georgia Power – Integrated Resource Plans – 2025 IRP" and "SEGCO," respectively, for additional information.
The remaining assets for which Alabama Power has indicated retirement, due to repowering of the unit to natural gas, have net book values totaling approximately $464 million (excluding capitalized asset retirement costs which are recovered through Rate CNP Compliance) at December 31, 2025. Based on an Alabama PSC order, Alabama Power is authorized to establish a regulatory asset to record the unrecovered investment costs, including the plant asset balance and the site removal and closure costs, associated with unit retirements caused by environmental regulations (Environmental Accounting Order). Under the Environmental Accounting Order, the regulatory asset would be amortized and recovered over an affected unit's remaining useful
II-38

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
life, as established prior to the decision regarding early retirement, through Rate CNP Compliance. See Note 2 to the financial statements under "Alabama Power – Rate CNP Compliance" and " – Environmental Accounting Order" for additional information.
In 2021, Georgia Power submitted NOPPs to the Georgia Environmental Protection Division (EPD) indicating plans to retire Plant Bowen Units 1 and 2 (1,400 MWs) and Plant Scherer Unit 3 (614 MWs based on 75% ownership) on or before the compliance date of December 31, 2028. Georgia Power also submitted a NOPP indicating plans to pursue compliance with the 2020 ELG rule for Plant Scherer Units 1 and 2 (137 MWs based on 8.4% ownership) through the VIP by no later than December 31, 2028. As of December 31, 2025, Georgia Power is in compliance with the ELG rules for Plant Bowen Units 3 and 4 through the generally applicable requirements; therefore, no NOPP submission was required for these units. Through its 2025 IRP, Georgia Power received approval from the Georgia PSC to extend the operation of Plant Scherer Unit 3 through at least December 31, 2035, as well as Plant Gaston Units 1 through 4 (500 MWs based on 50% ownership through SEGCO) through December 31, 2034. In addition, the 2025 IRP assumes operation of Plant Bowen Units 1 and 2 through at least December 31, 2035 and does not impact the ELG compliance strategy for Plant Bowen as the flue gas desulfurization wastewater system is a common environmental control for all four generating units. On December 31, 2025, Georgia Power submitted a transfer NOPP indicating plans to pursue compliance with the 2020 ELG rule for Plant Scherer Unit 3 through the VIP by December 31, 2028. The NOPP submittals and generally applicable requirements are subject to the review of the Georgia EPD and decisions related to retirement or continued operation of units are subject to Georgia PSC approval. See Notes 2 and 7 to the financial statements under "Georgia Power – Integrated Resource Plans – 2025 IRP" and "SEGCO," respectively, for additional information.
Coal Combustion Residuals
In 2015, the EPA finalized non-hazardous solid waste regulations for the management and disposal of CCR, including coal ash and gypsum, in landfills and surface impoundments at active electric generating power plants. The CCR Rule requires landfills and surface impoundments to be evaluated against a set of performance criteria and potentially closed if certain criteria are not met. Closure of existing landfills and surface impoundments requires installation of equipment and infrastructure to manage CCR in accordance with the CCR Rule. In addition to the federal CCR Rule, the States of Alabama and Georgia finalized state regulations regarding the management and disposal of CCR within their respective states. In 2019, the State of Georgia received partial approval from the EPA for its state CCR permitting program, which has broader applicability than the federal rule. The State of Mississippi has not developed a state CCR permit program.
In June 2024, the EPA published a final determination to deny the ADEM's CCR permit program. Alabama Power's permits to close its CCR facilities remain valid under state law. In the absence of an EPA-approved state permit program, CCR facilities in Alabama will remain subject to both the federal and state CCR rules. The ultimate impact of the EPA's denial of ADEM's CCR permit program cannot be determined at this time; however, it may result in significant compliance costs.
Beginning in January 2022, the EPA issued numerous determinations that stated its positions on a variety of CCR Rule compliance requirements, such as criteria for groundwater corrective action and CCR unit closure. The traditional electric operating companies are working with state regulatory agencies to determine whether the EPA's determinations may impact closure and groundwater monitoring plans.
In May 2024, the EPA published the final legacy CCR surface impoundments rule (2024 Legacy Rule) which regulates two new categories of federally regulated CCR, legacy surface impoundments and CCR management units (CCRMUs). The 2024 Legacy Rule requires legacy surface impoundments and CCRMUs to meet certain existing regulatory requirements, including a requirement to initiate closure within 42 months after the effective date of the 2024 Legacy Rule for legacy surface impoundments and within 54 months after the effective date of the 2024 Legacy Rule for CCRMUs. Numerous industry groups, electric generators, and states filed petitions for review challenging the 2024 Legacy Rule in the U.S. Court of Appeals for the D.C. Circuit. On February 13, 2025, the U.S. Court of Appeals for the D.C. Circuit placed the 2024 Legacy Rule in abeyance pending additional rulemaking. On March 12, 2025, the EPA announced its intent to undertake several regulatory actions related to the CCR Rule. On February 10, 2026, the EPA published a final rule extending certain deadlines for compliance for owners and operators of CCRMUs. The ultimate impact of any final rule and associated legal matters cannot be determined at this time; however, it may result in significant compliance costs.
Based on compliance requirements for closure and monitoring of landfills and surface impoundments pursuant to state and federal CCR rules, the traditional electric operating companies have periodically updated, and expect to continue periodically updating, their related cost estimates and ARO liabilities for each CCR unit as additional information related to compliance monitoring, closure methodologies and strategies, schedules, and/or costs becomes available. Some of these updates have been, and future updates may be, material. The cost estimates for Alabama Power are based on closure-in-place for all surface impoundments. The cost estimates for Georgia Power and Mississippi Power are based on a combination of closure-in-place for some surface impoundments and closure by removal for others. Additionally, the closure designs and plans in the States of Alabama and
II-39

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Georgia are subject to approval by environmental regulatory agencies. Absent continued recovery of ARO costs through regulated rates, results of operations, cash flows, and financial condition for Southern Company and the traditional electric operating companies could be materially impacted. See FINANCIAL CONDITION AND LIQUIDITY – "Cash Requirements" herein, Notes 2 and 3 to the financial statements under "Georgia Power – Rate Plans" and "General Litigation Matters – Alabama Power," respectively, and Note 6 to the financial statements for additional information.
Greenhouse Gases
In May 2024, the EPA published the final GHG rules (2024 GHG Rules) to establish GHG emissions standards for existing fossil fuel-fired steam electric generating units and new fossil fuel-fired combustion turbines and combined cycle generation facilities. The 2024 GHG Rules do not include standards for existing fossil fuel-fired combustion turbines or combined cycle generation facilities. Under the 2024 GHG Rules, existing source compliance for steam generating units would begin as early as January 1, 2030, depending on the subcategory for the affected unit, and the standards for new combustion turbines and combined cycles include subcategories for low, intermediate, and base load operations. Compliance with new source standards begins when the unit comes online, with requirements for carbon capture and sequestration (CCS) beginning on January 1, 2032.
Numerous industry groups, electric generators, and states have filed petitions for review challenging the 2024 GHG Rules in the U.S. Court of Appeals for the D.C. Circuit. On April 25, 2025, the U.S. Court of Appeals for the D.C. Circuit placed the litigation over the 2024 GHG Rules in abeyance. On June 17, 2025, the EPA published a proposed rule that includes a primary proposal and an alternative proposal. Under the primary proposal, the EPA would repeal all GHG emissions standards for fossil fuel-fired power plants promulgated under Section 111 of the Clean Air Act based on a finding that GHG emissions from those plants do not meet the prerequisite for regulation under Section 111 that they contribute significantly to dangerous air pollution. Under the alternative proposal, the EPA would repeal all of the GHG emissions guidelines for existing fossil fuel-fired steam generating units as well as the carbon capture and storage requirement for new base load stationary combustion turbines, leaving the remaining emissions standards from the 2024 GHG Rules in place. The ultimate impact of any final rule and associated legal matters cannot be determined at this time; however, if the EPA selects the alternative proposal, it may result in increased compliance costs.
It is unclear what impact the EPA's February 12, 2026 repeal of its 2009 endangerment finding for GHG emissions from motor vehicles might have on the remaining Section 111 emissions standards if the EPA selects the alternative proposal. The EPA acknowledged in the repeal of the 2009 endangerment finding that other Clean Air Act rulemakings, including the Section 111 emissions standards for fossil fuel-fired power plants, have cited the 2009 endangerment finding, and the EPA said it would address any overlapping issues in separate rulemakings.
Internationally, the Paris Agreement establishes a non-binding universal framework for addressing GHG emissions based on nationally determined emissions reduction contributions and sets in place a process for tracking progress towards the goals every five years. The United States withdrew from the Paris Agreement effective January 27, 2026.
Additional GHG policies, including legislation, may emerge in the future requiring the United States to accelerate its transition to a lower GHG emitting economy; however, associated impacts are currently unknown. The Southern Company system has transitioned from an electric generating mix of 70% coal, 15% natural gas, and 14% nuclear in 2007 to a mix of 20% coal, 51% natural gas, and 19% nuclear in 2025. This transition has been supported in part by the Southern Company system retiring over 6,700 MWs of coal-fired generating capacity since 2010 and converting 3,700 MWs of generating capacity from coal to natural gas since 2015, as well as the addition of over 1,100 MWs of nuclear generating capacity (based on Georgia Power's ownership interest in Plant Vogtle Units 3 and 4) since 2023. In addition, the Southern Company system's capacity mix consists of over 12,700 MWs of renewable and storage facilities through ownership (including 100% of the nameplate capacity of Southern Power's facilities owned with partners) and long-term PPAs. See "Environmental Laws and Regulations – Water Quality" herein for information on plans to retire or convert to natural gas additional coal-fired generating capacity. In addition, Southern Company Gas has replaced over 6,000 miles of pipe material that was more prone to fugitive emissions (unprotected steel and cast-iron pipe), resulting in mitigation of more than 3.3 million metric tons of CO2 equivalents from its natural gas distribution system since 1998.
II-40

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
The following table provides the Registrants' 2024 and preliminary 2025 Scope 1 GHG emissions based on equity share of facilities:
2024
Preliminary 2025
(in million metric tons of CO2 equivalent)
Southern Company(*)
7983
Alabama Power(*)
3031
Georgia Power2424
Mississippi Power(*)
99
Southern Power1212
Southern Company Gas
22
(*)Includes GHG emissions attributable to acquired assets beginning with the date of the applicable acquisition. See Note 15 to the financial statements for additional information.
Since 2018, Southern Company system management established GHG emissions reductions goals including an intermediate goal of 50% from 2007 levels by 2030 and a long-term goal of net zero by 2050. Based on the preliminary 2025 emissions, the Southern Company system has achieved an estimated GHG emission reduction of 47% since 2007, compared to a 49% reduction in 2024. This increase in emissions is primarily attributed to increased electric generation and changes in fuel mix driven by economic dispatch, as discussed further under RESULTS OF OPERATIONS – "Southern Company – Electricity Business" herein. While none of Southern Company's subsidiaries are currently subject to renewable portfolio standards or similar requirements, management of the traditional electric operating companies is working with applicable regulators through their IRP processes to continue the generating fleet transition in a manner responsible to customers, communities, employees, and other stakeholders. The natural gas distribution utilities also engage in long-term planning processes in accordance with their state regulatory processes and are investing in programs and efforts to reduce GHG emissions associated with the delivery and use of natural gas, such as advanced leak detection and repair and renewable natural gas. Due primarily to the projected electric load growth, current projections indicate it will be extremely challenging to meet the 2030 goal. The Southern Company system continues to work toward its GHG goals while seeking to ensure reliable and affordable energy for its customers. Achievement of these goals is dependent on various factors, many of which the Southern Company system does not control, including load growth across the Southern Company system's service territory, including projected load growth from large load customers, energy policy and regulations, natural gas prices, customer demand for carbon-free energy, and the development and deployment of low- to no-GHG energy technologies. Southern Company system management expects to continue to economically transition the generating fleet through a diverse portfolio of resources including low-carbon and carbon-free resources; making the necessary related investments in transmission and distribution systems; continuing to implement effective energy efficiency and demand response programs; implementing initiatives to reduce natural gas distribution emissions; continuing research and development with a focus on technologies that lower GHG emissions; and constructively engaging with policymakers, regulators, investors, customers, and other stakeholders to support outcomes leading to a net zero future. There is no guarantee that the Southern Company system will achieve these goals.
Environmental Remediation
The Southern Company system must comply with environmental laws and regulations governing the handling and disposal of waste and releases of hazardous substances. Under these various laws and regulations, the Southern Company system could incur substantial costs to clean up affected sites. The traditional electric operating companies and Southern Company Gas conduct studies to determine the extent of any required cleanup and have recognized the estimated costs to clean up known impacted sites in their financial statements. Amounts for cleanup and ongoing monitoring costs were not material for any year presented. The traditional electric operating companies and the natural gas distribution utilities in Illinois and Georgia (which represent substantially all of Southern Company Gas' accrued remediation costs) have all received authority from their respective state PSCs or other applicable state regulatory agencies to recover approved environmental remediation costs through regulatory mechanisms. These regulatory mechanisms are adjusted annually or as necessary within limits approved by the state PSCs or other applicable state regulatory agencies. The traditional electric operating companies and Southern Company Gas may be liable for some or all required cleanup costs for additional sites that may require environmental remediation. See Note 3 to the financial statements under "Environmental Remediation" for additional information.
II-41

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Regulatory Matters
See OVERVIEW – "Recent Developments" herein and Note 2 to the financial statements for a discussion of regulatory matters related to Alabama Power, Georgia Power, Mississippi Power, and Southern Company Gas, including items that could impact the applicable Registrants' future earnings, cash flows, and/or financial condition.
Alabama Power
On November 14, 2025, Alabama Power issued an RFP seeking on-demand dispatchable capacity resources of 100 MWs or greater to meet future energy needs. Any purchases will depend upon the cost competitiveness of the respective offers, as well as other options available to Alabama Power, and would ultimately require approval by the Alabama PSC. The ultimate outcome of this matter cannot be determined at this time.
Construction Programs
The Southern Company system strategy continues to include developing and constructing new electric generating and battery energy storage facilities, expanding and improving the electric transmission and electric and natural gas distribution systems, and undertaking projects to comply with environmental laws and regulations.
The traditional electric operating companies are engaged in continuous construction programs to accommodate existing and estimated future loads on their respective systems. Major generation construction projects are subject to state PSC approval in order to be included in retail rates, through which the traditional electric operating companies recover their approved investment and a return on investment. Through the 2022 IRP and the 2023 IRP Update, the Georgia PSC has certified resources totaling approximately 13 GWs, approximately nine GWs of which are new generation and battery energy storage facilities that are being, or are expected to be, constructed by Georgia Power. These Georgia Power projects are projected to be placed in service through 2030. See Note 2 to the financial statements under "Georgia Power – Integrated Resource Plans" and " – Other Construction" for additional information.
Alabama Power executed an agreement to build a battery energy storage facility at the former Plant Gorgas site in Walker County, Alabama. The new Gorgas battery facility is designed to have the capacity to store up to 150 MWs of electricity generated by other Alabama Power resources. Construction began in the third quarter 2025, with projected completion by 2027.
Southern Power's construction program includes the Millers Branch solar project and the Kay, Grant Plains, Grant, Wake, and Bethel wind repowering projects. The repowering projects result in accelerated depreciation related to the equipment being replaced that will continue until the projects' CODs, which are projected to occur between the third quarter 2026 and the third quarter 2027. At December 31, 2025, the remaining pre-tax accelerated depreciation is projected to total approximately $490 million in 2026 and $100 million in 2027. The ultimate impact of these matters cannot be determined at this time. See Note 15 to the financial statements under "Southern Power" for information relating to Southern Power's construction of renewable energy facilities.
Southern Company Gas is engaged in various infrastructure improvement programs designed to update or expand the natural gas distribution systems of the natural gas distribution utilities to improve reliability and resiliency, reduce emissions, and meet operational flexibility and growth. The natural gas distribution utilities recover their approved investment and a return on investment associated with these infrastructure programs through their regulated rates, as approved by their applicable state regulatory agency. See Note 2 to the financial statements under "Southern Company Gas – Infrastructure Replacement Programs and Capital Projects" for additional information on Southern Company Gas' construction program.
SNG is developing an approximately $3 billion proposed pipeline project, designed to meet customer demand by increasing SNG's existing pipeline capacity by approximately 1.3 billion cubic feet per day. Subject to the satisfaction or waiver of various conditions, including the receipt of all required approvals by regulators, including the FERC, the operator of the joint venture anticipates the project will be completed in 2029. Southern Company Gas' share of the total project costs would be 50%. The ultimate outcome of this matter cannot be determined at this time. See Note 7 to the financial statements under "Southern Company Gas" for additional information on SNG.
See FINANCIAL CONDITION AND LIQUIDITY – "Cash Requirements – Capital Expenditures" herein for additional information regarding the Registrants' capital requirements for their construction programs, including estimated totals for each of the next five years.
II-42

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Southern Power's Power Sales Agreements
General
Southern Power has PPAs with certain of the traditional electric operating companies, other investor-owned utilities, IPPs, municipalities, electric cooperatives, and other load-serving entities, as well as commercial and industrial customers. The PPAs are expected to provide Southern Power with a stable source of revenue during their respective terms.
Many of Southern Power's PPAs have provisions that require Southern Power or the counterparty to post collateral or an acceptable substitute guarantee if (i) S&P, Fitch, or Moody's downgrades the credit ratings of the respective company to an unacceptable credit rating, (ii) the counterparty is not rated, or (iii) the counterparty fails to maintain a minimum coverage ratio. See FINANCIAL CONDITION AND LIQUIDITY – "Credit Rating Risk" herein for additional information.
Southern Power works to maintain and expand its share of the wholesale market. During 2025, Southern Power continued to be successful in remarketing up to 1,339 MWs of annual generation capacity to load-serving entities, as well as to commercial and industrial customers, through several PPAs extending over the next 20 years. Market demand is being driven by customers securing generation capacity to manage risk, support reliability and operational commitments, replace expiring PPAs and retiring generation, and plan for future growth.
Natural Gas
Southern Power's electricity sales from natural gas facilities are primarily through long-term PPAs that consist of two types of agreements. The first type, referred to as a unit or block sale, is a customer purchase from a dedicated generating unit where all or a portion of the generation from that unit is reserved for that customer. Southern Power typically has the ability to serve the unit or block sale customer from an alternate resource. The second type, referred to as requirements service, provides that Southern Power serve the customer's capacity and energy requirements from a combination of the customer's own generating units and from Southern Power resources not dedicated to serve unit or block sales. Southern Power has rights to purchase power provided by the requirements customers' resources when economically viable.
As a general matter, substantially all of the PPAs provide that the purchasers are responsible for either procuring the fuel (tolling agreements) or reimbursing Southern Power for substantially all of the cost of fuel or purchased power relating to the energy delivered under such PPAs. To the extent a particular generating facility does not meet the operational requirements contemplated in the PPAs, Southern Power may be responsible for excess fuel costs. With respect to fuel transportation risk, most of Southern Power's PPAs provide that the counterparties are responsible for the availability of fuel transportation to the particular generating facility.
Capacity charges that form part of the PPA payments are designed to recover fixed and variable operation and maintenance costs based on dollars-per-kilowatt year and to provide a return on investment. In general, to reduce Southern Power's exposure to certain operation and maintenance costs, Southern Power has LTSAs. See Note 1 to the financial statements under "Long-Term Service Agreements" for additional information.
Solar and Wind
Southern Power's electricity sales from solar and wind generating facilities are also primarily through long-term PPAs; however, these PPAs do not have a capacity charge and customers either purchase the energy output of a dedicated renewable facility through an energy charge or provide Southern Power a certain fixed price for the electricity sold to the grid. As a result, Southern Power's ability to recover fixed and variable operations and maintenance expenses is dependent upon the level of energy generated from these facilities, which can be impacted by weather conditions, equipment performance, transmission constraints, and other factors. Generally, under the renewable generation PPAs, the purchasing party retains the right to keep or resell the associated renewable energy credits.
Income Tax Matters
Consolidated Income Taxes
The impact of certain tax events at Southern Company and/or its other subsidiaries can, and does, affect each Registrant's ability to claim certain deductions and to utilize certain tax credits and net operating losses. See "Tax Credits" and ACCOUNTING POLICIES – "Application of Critical Accounting Policies and Estimates – Accounting for Income Taxes" herein and Note 10 to the financial statements for additional information.
II-43

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Federal Tax Legislation
In 2022, the IRA was signed into law. The IRA extends, expands, and increases ITCs and PTCs for clean energy projects, allows PTCs for solar projects, adds ITCs for stand-alone energy storage projects with an option to elect out of the tax normalization requirement, and allows for the transferability of the tax credits. The IRA extends and increases the tax credits for CCS projects and adds tax credits for clean hydrogen and nuclear projects. Additional ITC and PTC amounts are available if the projects meet domestic content requirements or are located in low-income or energy communities. The IRA also enacted a 15% CAMT on book income, with material adjustments for pension costs and tax depreciation. The 15% CAMT on book income can be reduced by tax credits.
The OBBB was signed into law on July 4, 2025. It extends many of the Tax Reform Legislation's provisions that were set to expire and makes some of them permanent. The OBBB includes major changes to tax incentives for renewable energy projects. The legislation restricts the ITCs and PTCs for solar and wind power projects, which were originally set to run through 2032 under the IRA. Such projects must now either begin construction by July 2026 or be fully operational by the end of 2027 in order to claim the applicable tax credits. Nuclear, hydropower, and geothermal energy projects maintain tax credits under the new law. Battery energy storage projects retain their full tax credit through 2033, with a gradual phase-out by 2036. The OBBB added new restrictions to tax credits for renewable facilities that are controlled or influenced by a prohibited foreign entity or that receive material assistance from a prohibited foreign entity. Pursuant to an executive order, the U.S. Treasury issued a notice on August 15, 2025, making changes to the start-of-construction guidance for wind and solar projects that begin construction after September 1, 2025. The Southern Company system is implementing the guidance in its plans for future renewable projects. Additionally, the IRS is expected to issue significant guidance on the tax provisions in the OBBB. The Southern Company system is still assessing and will continue to monitor the impacts of the OBBB. The ultimate outcome of this legislation cannot be determined at this time.
For solar projects placed in service in 2022 through 2027 or that begin construction by July 2026, the IRA and the OBBB provide for a 30% ITC and an option to claim a PTC instead of an ITC. Starting in 2023 and through 2033, with a gradual phase-out by 2036, the IRA and the OBBB provide for a 30% ITC for stand-alone battery energy storage projects. For wind projects placed in service in 2022 through 2027 or that have begun construction by July 2026, the IRA and the OBBB provide for a 100% PTC, adjusted for inflation annually. The 2025 PTC rate is 3 cents per KWH on solar and wind projects where PTCs have been elected. To realize the full value of ITCs and PTCs, the IRA requires satisfaction of prevailing wage and apprenticeship requirements.
In April 2024, the IRS issued final regulations related to the transfer of tax credits. Alabama Power, Georgia Power, and Southern Power have entered into purchase and sale agreements with non-affiliated parties to sell ITCs and PTCs at a discount to the generated credit value in 2024, 2025, and 2026. The discount will be recorded as a reduction in tax credits recognized in the financial statements. The Southern Company system continues to explore the ability to efficiently monetize tax credits through third-party transferability agreements. See Note 10 to the financial statements for additional information.
Tax Credits
Southern Company receives ITCs and PTCs in connection with investments in solar, wind, fuel cell, nuclear, hydroelectric, and battery energy storage facilities primarily at Southern Power, Georgia Power, and Alabama Power.
Southern Power's ITCs relate to its investment in new solar facilities and battery energy storage facilities (co-located with existing solar facilities) that are acquired or constructed and its PTCs relate to the first 10 years of energy production from its wind and solar facilities, which have had, and may continue to have, a material impact on Southern Power's cash flows and net income. At December 31, 2025, Southern Company and Southern Power had approximately $850 million and $481 million, respectively, of unutilized federal ITCs and PTCs, which are currently projected to be fully utilized by 2031 but could be further delayed. Since 2018, Southern Power has utilized tax equity partnerships for certain wind, solar, and battery energy storage projects, where the tax equity partner takes significantly all of the respective federal tax benefits. These tax equity partnerships are consolidated in Southern Company's and Southern Power's financial statements using the HLBV methodology to allocate partnership gains and losses. On December 31, 2025, Southern Power purchased 100% of the noncontrolling Class A membership interests in the SP Wind tax equity partnership and became the sole owner of SP Wind, and the partnership was dissolved. Beginning in 2026, Southern Power will recognize the full tax benefit, net of applicable transfer discounts, on credits generated by the eight underlying wind facilities as they are generated. See Note 15 under "Southern Power – Purchase of Renewable Facility Interests" for additional information.
See Note 1 to the financial statements under "General" for additional information on the HLBV methodology and Note 1 to the financial statements under "Income Taxes" and Note 10 to the financial statements under "Deferred Tax Assets and Liabilities – Tax Credit Carryforwards" and "Effective Tax Rate" for additional information regarding utilization and amortization of credits and the tax benefit related to associated basis differences.
In the third quarter 2023 and the second quarter 2024, Georgia Power started generating advanced nuclear PTCs for Plant Vogtle Units 3 and 4, respectively, beginning on each unit's respective in-service date. PTCs are recognized as an income tax benefit
II-44

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
based on KWH production. In addition, pursuant to the Vogtle Joint Ownership Agreements (as defined in Note 2 to the financial statements under "Georgia Power – Nuclear Construction – Cost and Schedule"), Georgia Power is purchasing advanced nuclear PTCs for Plant Vogtle Units 3 and 4 from the other Vogtle Owners. The gain recognized on the purchase of the joint owner PTCs is recognized as an income tax benefit. See Note 2 to the financial statements under "Georgia Power – Nuclear Construction" for additional information regarding Plant Vogtle Units 3 and 4.
Alabama Power and Georgia Power have nuclear generating facilities that qualify for Internal Revenue Code §45U PTCs under the IRA. The §45U PTC is available for tax years 2024 to 2032 and is subject to a phase-out. Southern Company, Alabama Power, and Georgia Power each evaluates annually whether it qualifies for the credit. For the 2024 tax year, Southern Company, Alabama Power, and Georgia Power claimed a credit of $373 million, $180 million, and $193 million, respectively, on the consolidated federal tax return, which included the prevailing wage multiplier. This credit, net of the transfer discount, was recorded as a regulatory liability. In November 2025, Southern Company received a full acceptance letter from the IRS for the consolidated 2024 federal income tax return. The estimated total credit amounts for the 2025 tax year are $122 million, $50 million, and $72 million for Southern Company, Alabama Power, and Georgia Power, respectively. Due to uncertainty regarding the acceptance of this credit by the IRS, the amounts for the 2025 tax year have been fully reserved. The ultimate outcome of this matter cannot be determined at this time.
See Note 2 to the financial statements under "Alabama Power – Nuclear Production Tax Credits Order" and "Georgia Power – Rate Plans" and Note 10 to the financial statements under "Unrecognized Tax Benefits" for additional information.
Implementation of the IRA and OBBB provisions related to existing nuclear generating facilities is subject to the issuance of additional guidance by the U.S. Treasury and the IRS. The applicable Registrants are still evaluating the impacts, and the ultimate outcome of this matter cannot be determined at this time.
Corporate Alternative Minimum Tax
On June 2, 2025 and September 30, 2025, the U.S. Treasury and the IRS issued guidance on the application of the CAMT. Southern Company has filed its consolidated 2024 federal income tax return and determined it was not subject to CAMT. Southern Company is still assessing the issued guidance and is not expecting to be subject to CAMT for the 2025 tax year.
Implementation of the IRA and OBBB provisions related to CAMT is subject to the issuance of additional guidance by the U.S. Treasury and the IRS. The Registrants are still evaluating the impacts, and the ultimate outcome of this matter cannot be determined at this time.
Natural Gas Safe Harbor Method
In 2023, the IRS issued Revenue Procedure 2023-15, which provides a safe harbor tax method of accounting that taxpayers may use to determine whether certain expenditures to maintain, repair, replace, or improve natural gas transmission and distribution property must be capitalized or allowed as repair deductions. The revenue procedure allows multiple alternatives for implementation. In April 2024, the IRS issued Revenue Procedure 2024-23, which gives additional implementation guidance on the natural gas safe harbor tax method of accounting for qualifying repair deductions. Southern Company and Southern Company Gas submitted a tax accounting method change for qualifying expenditures with the filing of its consolidated 2024 federal income tax return. The new tax method of accounting resulted in a material net positive cash flow for Southern Company Gas. This method change did not have an impact on the net income of Southern Company and Southern Company Gas. See Note 10 to the financial statements under "Deferred Tax Assets and Liabilities – Tax Credit Carryforwards" for additional information.
Georgia State Tax Legislation
On April 15, 2025, the State of Georgia enacted tax legislation that reduced the corporate income tax rate from 5.39% to 5.19% effective for the 2025 tax year. This legislation reduced the amount of Southern Company's and certain subsidiaries' income tax expense in the State of Georgia and existing state net accumulated deferred tax liabilities, increased regulatory liabilities at Georgia Power and Southern Company Gas, and reduces Georgia Power's ability to utilize certain state tax credits in the State of Georgia. The legislation did not have a material impact on the net income of the applicable Registrants in 2025.
General Litigation and Other Matters
The Registrants are involved in various matters being litigated and/or regulatory and other matters that could affect future earnings, cash flows, and/or financial condition. The ultimate outcome of such pending or potential litigation against each Registrant and any subsidiaries or regulatory and other matters cannot be determined at this time; however, for current proceedings and/or matters not specifically reported herein or in Notes 2 and 3 to the financial statements, management does not anticipate that the ultimate liabilities, if any, arising from such current proceedings and/or matters would have a material effect on
II-45

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
such Registrant's financial statements. See Notes 2 and 3 to the financial statements for a discussion of various contingencies, including matters being litigated, regulatory matters, and other matters which may affect future earnings potential.
ACCOUNTING POLICIES
Application of Critical Accounting Policies and Estimates
The Registrants prepare their financial statements in accordance with GAAP, which requires the use of estimates, judgments, and assumptions. Significant accounting policies are described in the notes to the financial statements. Detailed further herein are certain estimates made in the application of these policies that may have a material impact on the results of operations, financial condition, and related disclosures of the applicable Registrants (as indicated in the section descriptions herein). Different assumptions and measurements could produce estimates that are significantly different from those recorded in the financial statements. Senior management has reviewed and discussed these critical accounting policies and estimates with the Audit Committee of Southern Company's Board of Directors.
Utility Regulation (Southern Company, Alabama Power, Georgia Power, Mississippi Power, and Southern Company Gas)
The traditional electric operating companies and the natural gas distribution utilities are subject to retail regulation by their respective state PSCs or other applicable state regulatory agencies and wholesale regulation by the FERC. These regulatory agencies set the rates the traditional electric operating companies and the natural gas distribution utilities are permitted to charge customers based on allowable costs, including a reasonable ROE. As a result, the traditional electric operating companies and the natural gas distribution utilities apply accounting standards which require the financial statements to reflect the effects of rate regulation. Through the ratemaking process, the regulators may require the inclusion of costs or revenues in periods different than when they would be recognized by a non-regulated company. This treatment may result in the deferral of expenses and the recording of related regulatory assets based on anticipated future recovery through rates or the deferral of gains or creation of liabilities and the recording of related regulatory liabilities. The application of the accounting standards for rate regulated entities also impacts their financial statements as a result of the estimates of allowable costs used in the ratemaking process. These estimates may differ from those actually incurred by the traditional electric operating companies and the natural gas distribution utilities; therefore, the accounting estimates inherent in specific costs such as depreciation, AROs, and pension and other postretirement benefits have less of a direct impact on the results of operations and financial condition of the applicable Registrants than they would on a non-regulated company. Additionally, a regulatory agency may disallow recovery of all or a portion of certain assets. See Note 2 to the financial statements under "Southern Company Gas – Infrastructure Replacement Programs and Capital Projects – Nicor Gas" for information regarding the disallowance of certain capital investments at Nicor Gas.
Revenues related to regulated utility operations as a percentage of total operating revenues in 2025 for the applicable Registrants were as follows: 90% for Southern Company, 98% for Alabama Power, 95% for Georgia Power, 99% for Mississippi Power, and 88% for Southern Company Gas.
As reflected in Note 2 to the financial statements, significant regulatory assets and liabilities have been recorded. Management reviews the ultimate recoverability of these regulatory assets and any requirement to refund these regulatory liabilities based on applicable regulatory guidelines and GAAP. However, adverse legislative, judicial, or regulatory actions could materially impact the amounts of such regulatory assets and liabilities and could adversely impact the financial statements of the applicable Registrants.
Accounting for Income Taxes (Southern Company, Georgia Power, Mississippi Power, Southern Power, and Southern Company Gas)
The consolidated income tax provision and deferred income tax assets and liabilities, as well as any unrecognized tax benefits and valuation allowances, require significant judgment and estimates. These estimates are supported by historical tax return data, reasonable projections of taxable income, the ability and intent to implement tax planning strategies if necessary, and interpretations of applicable tax laws and regulations across multiple taxing jurisdictions. The effective tax rate reflects the statutory tax rates and calculated apportionments for the various states in which the Southern Company system operates.
Southern Company files a consolidated federal income tax return and the Registrants file various state income tax returns, some of which are combined or unitary. Under a joint consolidated income tax allocation agreement, each Southern Company subsidiary's current and deferred tax expense is computed on a stand-alone basis and each subsidiary is allocated an amount of tax similar to that which would be paid if it filed a separate income tax return except for certain credit utilization and state apportionment results. In accordance with IRS regulations, each company is jointly and severally liable for the federal tax liability. Certain deductions and credits can be limited or utilized at the consolidated or combined level resulting in tax credit and/or state net operating loss carryforwards that would not otherwise result on a stand-alone basis. Utilization of these carryforwards and the
II-46

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
assessment of valuation allowances are based on significant judgment and extensive analysis of Southern Company's and its subsidiaries' current financial position and results of operations, including currently available information about future years, to estimate when future taxable income will be realized. See Note 10 to the financial statements under "Deferred Tax Assets and Liabilities – Tax Credit Carryforwards" and " – Net Operating Loss Carryforwards" for additional information.
Current and deferred state income tax liabilities and assets are estimated based on laws of multiple states that determine the income to be apportioned to their jurisdictions. States have various filing methodologies and utilize specific formulas to calculate the apportionment of taxable income. The calculation of deferred state taxes considers apportionment factors and filing methodologies that are expected to apply in future years. Any apportionments and/or filing methodologies ultimately finalized in a manner inconsistent with expectations could have a material effect on the financial statements of the applicable Registrants.
Asset Retirement Obligations (Southern Company, Alabama Power, Georgia Power, Mississippi Power, and Southern Company Gas)
Estimating AROs requires significant judgment. AROs are computed as the present value of the estimated costs for an asset's future retirement and are recorded in the period in which the liability is incurred. The estimated costs are capitalized as part of the related long-lived asset and depreciated over the asset's useful life. In the absence of quoted market prices, AROs are estimated using present value techniques in which estimates of future cash outlays associated with the asset retirements are discounted using a credit-adjusted risk-free rate. Estimates of the timing and amounts of future cash outlays are based on projections of when and how the assets will be retired and the cost of future removal activities.
The ARO liabilities for the traditional electric operating companies primarily relate to facilities that are subject to the CCR Rule and the related state rules, principally surface impoundments. In addition, Alabama Power and Georgia Power have retirement obligations related to the decommissioning of nuclear facilities (Alabama Power's Plant Farley and Georgia Power's ownership interests in Plants Hatch and Vogtle). Other significant AROs include various landfill sites and asbestos removal for Alabama Power, Georgia Power, and Mississippi Power and gypsum cells and mine reclamation for Mississippi Power.
The traditional electric operating companies and Southern Company Gas also have identified other retirement obligations, such as obligations related to certain electric transmission and distribution facilities, certain asbestos-containing material within long-term assets not subject to ongoing repair and maintenance activities, certain wireless communication towers, the disposal of polychlorinated biphenyls in certain transformers, leasehold improvements, equipment on customer property, and property associated with the Southern Company system's rail lines and natural gas pipelines. However, liabilities for the removal of these assets have not been recorded because the settlement timing for certain retirement obligations related to these assets is indeterminable and, therefore, the fair value of the retirement obligations cannot be reasonably estimated. A liability for these retirement obligations will be recognized when sufficient information becomes available to support a reasonable estimation of the ARO.
The cost estimates for AROs related to the disposal of CCR are based on information using various assumptions related to closure and post-closure costs, timing of future cash outlays, inflation and discount rates, and the potential methods for complying with the CCR Rule and the related state rules. The traditional electric operating companies have periodically updated, and expect to continue periodically updating, their related cost estimates and ARO liabilities for each CCR unit as additional information related to these assumptions becomes available. Some of these updates have been, and future updates may be, material. The cost estimates for Alabama Power are based on closure-in-place for all surface impoundments. The cost estimates for Georgia Power and Mississippi Power are based on a combination of closure-in-place for some surface impoundments and closure by removal for others. Additionally, the closure designs and plans in the States of Alabama and Georgia are subject to approval by environmental regulatory agencies. See Note 6 to the financial statements and FUTURE EARNINGS POTENTIAL – "Environmental Matters – Environmental Laws and Regulations – Coal Combustion Residuals" herein for additional information, including updates to AROs related to surface impoundments recorded during 2025 by certain Registrants.
Pension and Other Postretirement Benefits (Southern Company, Alabama Power, Georgia Power, Mississippi Power, and Southern Company Gas)
The applicable Registrants' calculations of pension and other postretirement benefits expense are dependent on a number of assumptions. These assumptions include discount rates, healthcare cost trend rates, expected long-term rate of return (LRR) on plan assets, mortality rates, expected salary and wage increases, and other factors. Components of pension and other postretirement benefits expense include interest and service cost on the pension and other postretirement benefit plans, expected return on plan assets, and amortization of certain unrecognized costs and obligations. Actual results that differ from the assumptions utilized are accumulated and amortized over future periods and, therefore, generally affect recognized expense and the recorded obligation in future periods. While the applicable Registrants believe the assumptions used are appropriate, differences in actual experience or significant changes in assumptions would affect their pension and other postretirement benefit costs and obligations.
II-47

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Key elements in determining the applicable Registrants' pension and other postretirement benefit expense are the LRR and the discount rate used to measure the benefit plan obligations and the periodic benefit plan expense for future periods. For purposes of determining the applicable Registrants' liabilities related to the pension and other postretirement benefit plans, Southern Company discounts the future related cash flows using a single-point discount rate for each plan developed from the weighted average of market-observed yields for high quality fixed income securities with maturities that correspond to expected benefit payments. The discount rate assumption impacts both the service cost and non-service costs components of net periodic benefit costs as well as the projected benefit obligations.
The LRR on pension and other postretirement benefit plan assets is based on Southern Company's investment strategy, as described in Note 11 to the financial statements, historical experience, and expectations that consider external actuarial advice, and represents the average rate of earnings expected over the long term on the assets invested to provide for anticipated future benefit payments. Southern Company determines the amount of the expected return on plan assets component of non-service costs by applying the LRR of various asset classes to Southern Company's target asset allocation. The LRR only impacts the non-service costs component of net periodic benefit costs for the following year and is set annually at the beginning of the year.
The following table illustrates the sensitivity to changes in the applicable Registrants' long-term assumptions with respect to the discount rate, salary increases, and the long-term rate of return on plan assets:
Increase/(Decrease) in
25 Basis Point Change in:
Total Benefit Expense for 2026
Projected Obligation for Pension Plan at December 31, 2025
Projected Obligation for
Other Postretirement
Benefit Plans at December 31, 2025
(in millions)
Discount rate:
Southern Company
$28/$(27)
$380/$(362)
$31/$(30)
Alabama Power
$7/$(7)
$91/$(87)
$8/$(8)
Georgia Power
$7/$(7)
$108/$(103)
$11/$(10)
Mississippi Power
$1/$(1)
$17/$(16)
$1/$(1)
Southern Company Gas
$2/$(2)
$25/$(23)
$3/$(3)
Salaries:
Southern Company
$16/$(16)
$77/$(75)
$–/$–
Alabama Power
$4/$(4)
$21/$(21)
$–/$–
Georgia Power
$4/$(4)
$20/$(20)
$–/$–
Mississippi Power
$1/$(1)
$3/$(3)
$–/$–
Southern Company Gas
$1/$(1)
$3/$(3)
$–/$–
Long-term return on plan assets:
Southern Company
$42/$(42)
N/AN/A
Alabama Power
$11/$(11)
N/AN/A
Georgia Power
$13/$(13)
N/AN/A
Mississippi Power
$2/$(2)
N/AN/A
Southern Company Gas
$3/$(3)
N/AN/A
See Note 11 to the financial statements for additional information regarding pension and other postretirement benefits.
Impairment (Southern Company, Alabama Power, Southern Power, and Southern Company Gas)
Goodwill (Southern Company and Southern Company Gas)
The acquisition method of accounting for business combinations requires the assets acquired and liabilities assumed to be recorded at the date of acquisition at their respective estimated fair values. The applicable Registrants have recognized goodwill as of the date of their acquisitions, as a residual over the fair values of the identifiable net assets acquired. Goodwill is recorded at the reporting unit level, which is the operating segment or a business one level below the operating segment (a component), if discrete financial information is prepared and regularly reviewed by management. Components are aggregated if they have similar
II-48

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
economic characteristics. Goodwill is tested for impairment at the reporting unit level on an annual basis in the fourth quarter of the year and on an interim basis if events and circumstances occur that indicate goodwill may be impaired.
Goodwill is evaluated for impairment either under the qualitative assessment option or the quantitative option to determine the fair value of the reporting unit. If goodwill is determined to be impaired, an impairment loss measured at the amount by which the reporting unit's carrying amount exceeds its fair value, not to exceed the carrying amount of goodwill, is recorded.
Goodwill for Southern Company and Southern Company Gas was $5.2 billion and $5.0 billion, respectively, at December 31, 2025.
The judgments made in determining the estimated fair value assigned to each class of assets acquired and liabilities assumed, as well as asset lives, can significantly impact the applicable Registrant's results of operations. Fair values and useful lives are determined based on, among other factors, the expected future period of benefit of the asset, the various characteristics of the asset, and projected cash flows. As the determination of an asset's fair value and useful life involves management making certain estimates and because these estimates form the basis for the determination of whether or not an impairment charge should be recorded, the applicable Registrants consider these estimates to be critical accounting estimates.
See Note 1 to the financial statements under "Goodwill and Other Intangible Assets" for additional information regarding the applicable Registrants' goodwill.
Long-Lived Assets (Southern Company, Alabama Power, Southern Power, and Southern Company Gas)
The applicable Registrants assess their other long-lived assets for impairment whenever events or changes in circumstances indicate that an asset's carrying amount may not be recoverable. If an impairment indicator exists, the asset is tested for recoverability by comparing the asset carrying amount to the sum of the undiscounted expected future cash flows directly attributable to the asset's use and eventual disposition. If the estimate of undiscounted future cash flows is less than the carrying amount of the asset, the fair value of the asset is determined and a loss is recorded equal to the difference between the carrying amount and the fair value of the asset. In addition, when assets are identified as held for sale, an impairment loss is recognized to the extent the carrying amount of the assets or asset group exceeds their fair value less cost to sell. A high degree of judgment is required in developing estimates related to these evaluations, which are based on projections of various factors, some of which have been quite volatile in recent years. See Notes 1 and 15 to the financial statements for additional information, including any recent asset impairments.
As the determination of the expected future cash flows generated from an asset, an asset's fair value, and useful life involves management making certain estimates and because these estimates form the basis for the determination of whether or not an impairment charge should be recorded, the applicable Registrants consider these estimates to be critical accounting estimates.
Revenue Recognition (Southern Power)
Southern Power's power sale transactions, which include PPAs, are classified in one of four general categories: leases, normal sale derivatives or contracts with customers, derivatives designated as cash flow hedges, and derivatives not designated as hedges. Southern Power's revenues are dependent upon significant judgments used to determine the appropriate transaction classification, which must be documented upon the inception of each contract. The two categories with the most judgment required for Southern Power are described further below.
Lease Transactions
Southern Power considers the terms of a sales contract to determine whether it should be accounted for as a lease. A contract is or contains a lease if the contract conveys the right to control the use of identified property, plant, or equipment for a period of time in exchange for consideration. If the contract meets the criteria for a lease, Southern Power performs further analysis to determine whether the lease is classified as operating, financing, or sales-type. Generally, Southern Power's power sales contracts that are determined to be leases are accounted for as operating leases and the capacity revenue is recognized on a straight-line basis over the term of the contract and is included in Southern Power's operating revenues. Energy revenues and other contingent revenues are recognized in the period the energy is delivered or the service is rendered. For those contracts that are determined to be sales-type leases, capacity revenues are recognized by accounting for interest income on the net investment in the lease and are included in Southern Power's operating revenues. See Note 9 to the financial statements for additional information.
Normal Sale Derivative Transactions and Contracts with Customers
If the power sales contract is not classified as a lease, Southern Power further considers whether the contract meets the definition of a derivative. If the contract does meet the definition of a derivative, Southern Power will assess whether it can be designated as a normal sale contract. The determination of whether a contract can be designated as a normal sale contract requires judgment,
II-49

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
including whether the sale of electricity involves physical delivery in quantities within Southern Power's available generating capacity and that the purchaser will take quantities expected to be used or sold in the normal course of business.
Contracts that do not meet the definition of a derivative or are designated as normal sales are accounted for as revenue from contracts with customers. For contracts that have a capacity charge, the revenue is generally recognized in the period that it becomes billable. Revenues related to energy and ancillary services are recognized in the period the energy is delivered or the service is rendered. See Note 4 to the financial statements for additional information.
Acquisition Accounting (Southern Power)
Southern Power may acquire generation assets as part of its overall growth strategy. At the time of an acquisition, Southern Power will assess if these assets and activities meet the definition of a business. Acquisitions that meet the definition of a business are accounted for under the acquisition method, whereby the identifiable assets acquired, liabilities assumed, and any noncontrolling interests (including any intangible assets, primarily related to acquired PPAs) are recognized and measured at fair value and any goodwill is recognized as a residual over the fair values of the identifiable net assets acquired. Assets acquired that do not meet the definition of a business are accounted for as an asset acquisition. The purchase price of each asset acquisition is allocated based on the relative fair value of assets acquired.
Determining the fair value of assets acquired and liabilities assumed requires management judgment and Southern Power may engage independent valuation experts to assist in this process. Fair values are determined by using market participant assumptions and typically include the timing and amounts of future cash flows, incurred construction costs, the nature of acquired contracts, discount rates, power market prices, and expected asset lives. For potential or successful acquisitions that meet the definition of a business, any due diligence or transaction costs incurred are expensed as incurred. If the acquisition is an asset acquisition, direct and incremental transaction costs can be capitalized as a component of the cost of the assets acquired.
See Note 13 to the financial statements for additional fair value information and Note 15 to the financial statements for additional information on recent acquisitions.
Variable Interest Entities (Southern Power)
Southern Power has partnerships with varying ownership structures. Upon entering into these arrangements, membership interests and other variable interests are evaluated to determine if the legal entity is a VIE. If the legal entity is a VIE, Southern Power will assess if it has both the power to direct the activities of the VIE that most significantly impact the VIE's economic performance and the obligation to absorb losses or the right to receive benefits from the VIE that could potentially be significant to the VIE, making it the primary beneficiary. Making this determination may require significant management judgment.
If Southern Power is the primary beneficiary and is considered to have a controlling ownership, the assets, liabilities, and results of operations of the entity are consolidated. If Southern Power is not the primary beneficiary, the legal entity is generally accounted for under the equity method of accounting. Southern Power reconsiders its conclusions as to whether the legal entity is a VIE and whether it is the primary beneficiary for events that impact the rights of variable interests, such as ownership changes in membership interests. See Note 7 to the financial statements under "Southern Power – Variable Interest Entities" for additional information.
Southern Power has controlling ownership in certain legal entities for which the contractual provisions represent profit-sharing arrangements because the allocations of cash distributions and tax benefits are not based on fixed ownership percentages. For these arrangements, the noncontrolling interest is accounted for under a balance sheet approach utilizing the HLBV method. The HLBV method calculates each partner's share of income based on the change in net equity the partner can legally claim in an HLBV at the end of the period compared to the beginning of the period.
Contingent Obligations (All Registrants)
The Registrants are subject to a number of federal and state laws and regulations, as well as other factors and conditions that subject them to environmental, litigation, and other risks. See FUTURE EARNINGS POTENTIAL herein and Notes 2 and 3 to the financial statements for more information regarding certain of these contingencies. The Registrants periodically evaluate their exposure to such risks and record reserves for those matters where a non-tax-related loss is considered probable and reasonably estimable. The adequacy of reserves can be significantly affected by external events or conditions that can be unpredictable; thus, the ultimate outcome of such matters could materially affect the results of operations, cash flows, or financial condition of the Registrants.
Recently Issued Accounting Standards
See Note 1 to the financial statements under "Recently Adopted Accounting Standards" for additional information.
II-50

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
FINANCIAL CONDITION AND LIQUIDITY
Overview
The financial condition of each Registrant remained stable at December 31, 2025. The Registrants' cash requirements primarily consist of funding ongoing operations, including unconsolidated subsidiaries, as well as common stock dividends, capital expenditures, and debt maturities. Southern Power's cash requirements also include distributions to noncontrolling interests. Capital expenditures and other investing activities for the traditional electric operating companies include investments to build new generation facilities to meet projected long-term demand requirements and to replace units being retired as part of the generation fleet transition, to maintain existing generation facilities, to comply with environmental regulations including adding environmental modifications to certain existing generating units and closures of surface impoundments, to expand and improve transmission and distribution facilities, and for restoration following major storms. Southern Power's capital expenditures and other investing activities may include acquisitions or new construction associated with its overall growth strategy and to maintain its existing generation fleet's performance. Southern Company Gas' capital expenditures and other investing activities include investments to meet projected long-term demand requirements, to maintain existing natural gas transmission and distribution systems as well as to update and expand these systems, and to comply with environmental regulations. See "Cash Requirements" herein for additional information.
Operating cash flows provide a substantial portion of the Registrants' cash needs. For the three-year period from 2026 through 2028, each Registrant's projected stock dividends, capital expenditures, and debt maturities, as well as distributions to noncontrolling interests for Southern Power, are expected to exceed its operating cash flows. Southern Company plans to finance future cash needs in excess of its operating cash flows through one or more of the following: accessing borrowings from financial institutions, issuing debt, equity, and/or hybrid securities in the capital markets, and/or through its stock plans and its continuous equity offering program. Each Subsidiary Registrant plans to finance its future cash needs in excess of its operating cash flows primarily through external securities issuances, borrowings from financial institutions and other sources, and equity contributions from Southern Company. The Registrants plan to use commercial paper to manage seasonal variations in operating cash flows and for other working capital needs and continue to monitor their access to short-term and long-term capital markets as well as their bank credit arrangements to meet future capital and liquidity needs. See "Sources of Capital" and "Financing Activities" herein for additional information.
See Note 11 to the financial statements under "Pension Plans" for information on the Registrants' investments in their qualified pension plans. No mandatory contributions to the qualified pension plans are anticipated during 2026. See Note 6 to the financial statements under "Nuclear Decommissioning" for information on Alabama Power's and Georgia Power's investments in their respective nuclear decommissioning trust funds.
At the end of 2025, the market price of Southern Company's common stock was $87.20 per share (based on the closing price as reported on the NYSE) and the book value was $32.18 per share, representing a market-to-book value ratio of 271%, compared to $82.32, $30.28, and 272%, respectively, at the end of 2024.
II-51

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Cash Requirements
Capital Expenditures
Total estimated capital expenditures, including LTSA and nuclear fuel commitments, for the Registrants through 2030 based on their current construction programs are as follows:
20262027202820292030
(in billions)
Southern Company(a)(b)(c)(d)(e)
$15.9 $18.5 $17.1 $14.6 $12.0 
Alabama Power(a)
2.0 2.1 2.1 2.1 1.9 
Georgia Power(b)
10.1 12.7 12.1 9.8 7.7 
Mississippi Power(c)
0.4 0.4 0.4 0.3 0.3 
Southern Power(d)
0.9 0.5 0.1 0.2 0.1 
Southern Company Gas(e)
2.2 2.6 2.4 2.0 2.0 
(a)Excludes amounts related to Alabama Power's decision to convert Plant Barry Unit 5 from coal to natural gas totaling $38 million in 2026, $15 million in 2027, and $54 million in 2028. See FUTURE EARNINGS POTENTIAL – "Environmental Matters – Environmental Laws and Regulations – Water Quality" herein and Note 2 to the financial statements under "Alabama Power – Environmental Accounting Order" for additional information.
(b)Includes expenditures of approximately $3.1 billion, $5.5 billion, $5.1 billion, $3.2 billion, and $0.8 billion for 2026 through 2030, respectively, for construction projects and related transmission investments approved in conjunction with the 2022 IRP, the 2023 IRP Update, and the 2025 IRP. See Note 2 to the financial statements under "Georgia Power – Integrated Resource Plans" and " – Other Construction" for additional information.
(c)Includes amounts contingent upon approval by the Mississippi PSC related to Mississippi Power's decision to convert Plant Daniel Unit 2 from coal to natural gas totaling $28 million in 2028 and $41 million in 2029. See Note 2 to the financial statements under "Mississippi Power – Integrated Resource Plans" for additional information.
(d)Includes $40 million in 2026 related to the Millers Branch solar project and $0.7 billion and $0.4 billion in 2026 and 2027, respectively, related to wind repowering projects. Excludes approximately $0.8 billion per year for 2026 through 2029 and $0.7 billion for 2030 for Southern Power's planned acquisitions and placeholder growth, which may vary materially due to market opportunities and Southern Power's ability to execute its growth strategy. See Note 15 to the financial statements under "Southern Power" for additional information regarding the Millers Branch solar project and the wind repowering projects.
(e)Includes gas pipeline investment of approximately $0.3 billion, $0.8 billion, $0.5 billion, and $0.1 billion for 2026 through 2029, respectively. See FUTURE EARNINGS POTENTIAL – "Construction Programs" herein for information regarding this project.
Total estimated capital expenditures, primarily at the traditional electric operating companies, increased significantly since 2023, from $45.2 billion previously estimated for 2024 through 2028 to $78.1 billion currently estimated for 2026 through 2030. The traditional electric operating companies project a significant increase in demand for electricity sales, largely driven by data centers and other large load customers. Serving the projected increased load demand from these new customers while continuing to serve existing customers safely, reliably, and affordably requires investing in generation, transmission, and distribution systems and pricing sales to these new customers such that the related incremental costs are met with adequate incremental revenues from these new customers. Through the 2022 IRP and the 2023 IRP Update, the Georgia PSC has certified resources totaling approximately 13 GWs, approximately nine GWs of which are new generation and battery energy storage facilities that are being, or are expected to be, constructed by Georgia Power. The certified costs of these Georgia Power projects total $19.5 billion, and these projects are projected to be placed in service through 2030. See Note 2 to the financial statements under "Georgia Power – Integrated Resource Plans" and " – Other Construction" for additional information.
These capital expenditures include estimates to comply with environmental laws and regulations, but do not include compliance costs associated with regulation of GHG emissions. See FUTURE EARNINGS POTENTIAL – "Environmental Matters" herein for additional information. At December 31, 2025, significant purchase commitments were outstanding in connection with the Registrants' construction programs.
The traditional electric operating companies also anticipate continued expenditures associated with closure and monitoring of surface impoundments and landfills in accordance with state and federal CCR rules, which are reflected in the applicable Registrants' ARO liabilities. The cost estimates for Alabama Power are based on closure-in-place for all surface impoundments. The cost estimates for Georgia Power and Mississippi Power are based on a combination of closure-in-place for some surface impoundments and closure by removal for others. These estimated costs are likely to change, and could change materially, as assumptions and details pertaining to closure are refined and compliance activities continue. Current estimates of these costs through 2030 are provided in the table below. Material expenditures in future years for ARO settlements will also be required for surface impoundments, nuclear decommissioning (for Alabama Power and Georgia Power), and other liabilities reflected in the
II-52

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
applicable Registrants' AROs, as discussed further in Note 6 to the financial statements. Also see FUTURE EARNINGS POTENTIAL – "Environmental Matters – Environmental Laws and Regulations – Coal Combustion Residuals" herein.
20262027202820292030
(in millions)
Southern Company$653 $645 $520 $750 $730 
Alabama Power256 265 209 206 187 
Georgia Power360 341 297 541 540 
Mississippi Power18 14 13 
The construction programs are subject to periodic review and revision, and actual construction costs may vary from these estimates because of numerous factors. These factors include: changes in business conditions; changes in load projections; changes in environmental laws and regulations; changes in technology; the outcome of any legal challenges to environmental rules; changes in electric generating plants, including unit retirements and replacements and adding or changing fuel sources at existing electric generating units, to meet regulatory requirements; changes in FERC rules and regulations; state regulatory agency approvals; changes in the expected environmental compliance program; changes in legislation, regulation, and/or tariff policy; the cost, availability, and efficiency of construction labor, equipment, and materials; project scope and design changes; abnormal weather; delays in construction due to judicial or regulatory action; storm impacts; and the cost of capital. In addition, there can be no assurance that costs related to capital expenditures and AROs will be fully recovered. Additionally, expenditures associated with Southern Power's planned acquisitions may vary due to market opportunities and the execution of its growth strategy. See Note 15 to the financial statements under "Southern Power" for additional information regarding Southern Power's plant acquisitions and construction projects.
See FUTURE EARNINGS POTENTIAL – "Construction Programs" herein for additional information.
Other Significant Cash Requirements
Long-term debt maturities and the interest payable on long-term debt each represent a significant cash requirement for the Registrants. See Note 8 to the financial statements for information regarding the Registrants' long-term debt at December 31, 2025, the weighted average interest rate applicable to each long-term debt category, and a schedule of long-term debt maturities over the next five years. The Registrants plan to continue, when economically feasible, to retire higher-cost securities and replace these obligations with lower-cost capital if market conditions permit.
Fuel and purchased power costs represent a significant component of funding ongoing operations for the traditional electric operating companies and Southern Power. Total estimated costs for fuel and purchased power commitments at December 31, 2025 for the applicable Registrants are provided in the table below. Fuel costs include purchases of coal (for the traditional electric operating companies) and natural gas (for the traditional electric operating companies and Southern Power), as well as the related transportation and storage. In most cases, these contracts contain provisions for price escalation, minimum purchase levels, and other financial commitments. Natural gas purchase commitments are based on various indices at the time of delivery; the amounts reflected below have been estimated based on the NYMEX future prices at December 31, 2025. As discussed under "Capital Expenditures" herein, estimated expenditures for nuclear fuel are included in the applicable Registrants' construction programs for the years 2026 through 2030. Nuclear fuel commitments at December 31, 2025 that extend beyond 2030 are included in the table below. Purchased power costs represent estimated minimum obligations for various PPAs for the purchase of capacity and energy, except for those accounted for as leases, which are discussed in Note 9 to the financial statements.
20262027202820292030Thereafter
(in millions)
Southern Company(*)
$3,955 $3,097 $2,260 $1,500 $1,032 $3,517 
Alabama Power1,309 1,053 825 456 259 900 
Georgia Power(*)
1,494 1,234 918 670 462 1,509 
Mississippi Power520 364 255 194 161 692 
Southern Power698 515 335 192 150 416 
(*)Excludes capacity payments related to Plant Vogtle Units 1 and 2, which are discussed in Note 3 to the financial statements under "Commitments."
In connection with Georgia Power's 2022 IRP, the Georgia PSC certified two affiliate PPAs with Southern Power, which are expected to be accounted for as leases and are contingent upon approval by the FERC. The expected capacity payments associated
II-53

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
with the PPAs total $61 million in 2030 and $2.6 billion thereafter. See Note 2 to the financial statements under "Georgia Power – Integrated Resource Plans – Certification Requests" for additional information.
The traditional electric operating companies and Southern Power have entered into LTSAs for the purpose of securing maintenance support for certain of their generating facilities. See Note 1 to the financial statements under "Long-Term Service Agreements" for additional information. As discussed under "Capital Expenditures" herein, estimated expenditures related to LTSAs are included in the applicable Registrants' construction programs for the years 2026 through 2030. Total estimated payments for LTSA commitments at December 31, 2025 that extend beyond 2030 are provided in the following table and include price escalation based on inflation indices:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
(in millions)
LTSA commitments (after 2030)
$1,239 $345 $97 $50 $747 
In addition, Southern Power has certain other operations and maintenance agreements. Total estimated costs for these commitments at December 31, 2025 are provided in the table below.
20262027202820292030Thereafter
(in millions)
Southern Power's operations and maintenance agreements$68 $66 $67 $60 $61 $364 
Southern Company Gas has commitments for pipeline charges, storage capacity, and gas supply, including charges recoverable through natural gas cost recovery mechanisms or, alternatively, billed to marketers selling retail natural gas. Gas supply commitments include amounts for gas commodity purchases associated with Nicor Gas and SouthStar of 39 million mmBtu at floating gas prices calculated using forward natural gas prices at December 31, 2025 and valued at $151 million. Southern Company Gas' expected future contractual obligations for pipeline charges, storage capacity, and gas supply that are not recognized on the balance sheets at December 31, 2025 were as follows:
20262027202820292030Thereafter
(in millions)
Pipeline charges, storage capacity, and gas supply
$734 $549 $548 $458 $423 $4,522 
See Note 9 to the financial statements for information on the Registrants' operating lease obligations, including a maturity analysis of the lease liabilities over the next five years and thereafter.
Sources of Capital
Southern Company intends to meet its future capital needs through operating cash flows, borrowings from financial institutions, and debt, hybrid, and/or equity issuances. Equity capital can be provided from any combination of Southern Company's stock plans, private placements, or public offerings.
The Subsidiary Registrants plan to obtain the funds to meet their future capital needs from sources similar to those they used in the past, which were primarily from operating cash flows, external securities issuances, borrowings from financial institutions and other sources, and equity contributions from Southern Company. Operating cash flows provide a substantial portion of the Registrants' cash needs.
The amount, type, and timing of any financings in 2026, as well as in subsequent years, will be contingent on investment opportunities and the Registrants' capital requirements and will depend upon prevailing market conditions, regulatory approvals (for certain of the Subsidiary Registrants), and other factors. See "Cash Requirements" herein for additional information.
The issuance of securities by the traditional electric operating companies and Nicor Gas is generally subject to the approval of the applicable state PSC or other applicable state regulatory agency. The issuance of all securities by Mississippi Power and short-term securities by Georgia Power is generally subject to regulatory approval by the FERC. Additionally, with respect to the public offering of securities, Southern Company, the traditional electric operating companies, Southern Power (excluding its subsidiaries), Southern Company Gas Capital, and Southern Company Gas (excluding its other subsidiaries) file registration statements with the SEC under the Securities Act of 1933, as amended.
The Registrants generally obtain financing separately without credit support from any affiliate. See Note 8 to the financial statements under "Bank Credit Arrangements" for additional information. The Southern Company system does not maintain a
II-54

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
centralized cash or money pool. Therefore, funds of each company are not commingled with funds of any other company in the Southern Company system, except in the case of Southern Company Gas, as described below.
The traditional electric operating companies and SEGCO may utilize a Southern Company subsidiary organized to issue and sell commercial paper at their request and for their benefit. Proceeds from such issuances for the benefit of an individual company are loaned directly to that company. The obligations of each traditional electric operating company and SEGCO under these arrangements are several and there is no cross-affiliate credit support. Alabama Power also maintains its own separate commercial paper program.
Southern Company Gas Capital obtains external financing for Southern Company Gas and its subsidiaries, other than Nicor Gas, which obtains financing separately without credit support from any affiliates. Southern Company Gas maintains commercial paper programs at Southern Company Gas Capital and Nicor Gas. Nicor Gas' commercial paper program supports its working capital needs as Nicor Gas is not permitted to make money pool loans to affiliates. All of the other Southern Company Gas subsidiaries benefit from Southern Company Gas Capital's commercial paper program.
By regulation, Nicor Gas is restricted, up to its retained earnings balance, in the amount it can dividend or loan to affiliates and is not permitted to make money pool loans to affiliates. At December 31, 2025, the amount of subsidiary retained earnings restricted to dividend totaled $1.8 billion. This restriction did not impact Southern Company Gas' ability to meet its cash obligations, nor does management expect such restriction to materially impact Southern Company Gas' ability to meet its currently anticipated cash obligations.
Certain Registrants' current liabilities frequently exceed their current assets because of long-term debt maturities and the periodic use of short-term debt as a funding source, as well as significant seasonal fluctuations in cash needs. The Registrants generally plan to refinance long-term debt as it matures. See Note 8 to the financial statements for additional information. Also see "Financing Activities" herein for information on financing activities that occurred subsequent to December 31, 2025. The following table shows the amount by which current liabilities exceeded current assets at December 31, 2025 for the applicable Registrants:
At December 31, 2025Southern
Company
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
Current liabilities in excess of current assets$5,971 $2,412 $146 $548 $785 
The Registrants believe the need for working capital can be adequately met by utilizing operating cash flows, as well as commercial paper, lines of credit, and short-term bank notes, as market conditions permit. In addition, under certain circumstances, the Subsidiary Registrants may utilize equity contributions and/or loans from Southern Company.
Bank Credit Arrangements
At December 31, 2025, unused committed credit arrangements with banks were as follows:
At December 31, 2025Southern
Company
parent
Alabama
   Power(a)
Georgia
   Power(b)
Mississippi
Power
Southern
   Power(c)
Southern
Company
   Gas(d)
SEGCOSouthern
Company
(in millions)
Unused committed credit$2,999 $1,365 $2,042 $275 $600 $1,598 $30 $8,909 
(a)Includes $15 million at Alabama Property Company, a wholly-owned subsidiary of Alabama Power. Alabama Power is not party to this arrangement.
(b)Georgia Power had $26 million of letters of credit outstanding under an uncommitted letter of credit facility at December 31, 2025.
(c)At December 31, 2025, Southern Power also had two continuing letters of credit facilities for standby letters of credit, of which $21 million was unused. In addition, Southern Power Company has $23 million of letters of credit outstanding under an uncommitted letter of credit facility at December 31, 2025. Southern Power's subsidiaries are not parties to its bank credit arrangements or letter of credit facilities.
(d)Includes $798 million and $800 million at Southern Company Gas Capital and Nicor Gas, respectively.
Subject to applicable market conditions, the Registrants, Nicor Gas, and SEGCO expect to renew or replace their bank credit arrangements as needed, prior to expiration. In connection therewith, the Registrants, Nicor Gas, and SEGCO may extend the maturity dates and/or increase or decrease the lending commitments thereunder.
A portion of the unused credit with banks is allocated to provide liquidity support to certain revenue bonds of the traditional electric operating companies and the commercial paper programs of the Registrants, Nicor Gas, and SEGCO. At December 31, 2025, outstanding variable rate demand revenue bonds of the traditional electric operating companies with allocated liquidity support totaled approximately $1.5 billion (comprised of approximately $796 million at Alabama Power, $667 million at Georgia
II-55

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Power, and $58 million at Mississippi Power). In addition, at December 31, 2025, Alabama Power and Georgia Power had approximately $280 million and $384 million, respectively, of fixed rate revenue bonds outstanding that are required to be remarketed within the next 12 months. Alabama Power's $280 million of fixed rate revenue bonds are classified as securities due within one year on its balance sheet as they are not covered by long-term committed credit. All other variable rate demand revenue bonds and fixed rate revenue bonds required to be remarketed within the next 12 months are classified as long-term debt on the balance sheets as a result of available long-term committed credit.
See Note 8 to the financial statements under "Bank Credit Arrangements" for additional information.
Short-term Borrowings
The Registrants, Nicor Gas, and SEGCO make short-term borrowings primarily through commercial paper programs that have the liquidity support of the committed bank credit arrangements described above. Southern Power's subsidiaries are not issuers or obligors under its commercial paper program. Commercial paper and short-term bank term loans are included in notes payable in the balance sheets. Details of the Registrants' short-term borrowings were as follows:
Short-term Debt at the End of the Period
Amount
Outstanding
Weighted Average
Interest Rate
December 31,December 31,
202520242023202520242023
(in millions)
Southern Company$722 $1,338 $2,314 3.9 %4.8 %5.7 %
Alabama Power — 40  — 5.5 
Georgia Power160 200 1,329 3.9 5.3 5.9 
Mississippi Power 14 —  4.6 — 
Southern Power138 — 138 3.9 — 5.5 
Southern Company Gas:
Southern Company Gas Capital$209 $283 $23 3.9 %4.7 %5.5 %
Nicor Gas216 172 392 3.9 4.6 5.5 
Southern Company Gas Total$425 $455 $415 3.9 %4.7 %5.5 %
Short-term Debt During the Period(*)
Average Amount
Outstanding
Weighted Average
Interest Rate
Maximum Amount
Outstanding
202520242023202520242023202520242023
(in millions)(in millions)
Southern Company$891 $1,606 $2,191 4.6 %5.6 %5.6 %$2,291 $3,211 $3,270 
Alabama Power4 50 44 4.2 5.5 5.0 75 250 230 
Georgia Power305 560 1,440 4.8 6.0 5.8 1,025 1,422 2,260 
Mississippi Power25 40 56 4.6 5.4 5.5 144 154 169 
Southern Power43 125 158 4.6 5.4 5.6 285 256 359 
Southern Company Gas:
Southern Company Gas Capital$249 $95 $163 4.6 %5.3 %5.3 %$540 $405 $440 
Nicor Gas56 141 88 4.2 5.3 5.1 271 397 483 
Southern Company Gas Total$305 $236 $251 4.5 %5.3 %5.2 %
(*)Average and maximum amounts are based upon daily balances during the 12-month periods ended December 31, 2025, 2024, and 2023.
II-56

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Analysis of Cash Flows
Net cash flows provided from (used for) operating, investing, and financing activities in 2025 and 2024 are presented in the following table:
Net cash provided from (used for):
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
2025
Operating activities$9,802 $2,572 $4,808 $414 $670 $1,617 
Investing activities(13,959)(2,814)(7,933)(356)(934)(1,768)
Financing activities4,696 223 3,066 (45)201 122 
2024
Operating activities$9,788 $2,895 $4,793 $406 $708 $1,552 
Investing activities(9,400)(1,987)(4,896)(373)(330)(1,711)
Financing activities(208)(732)146 (58)(354)168 
Fluctuations in cash flows from financing activities vary from year to year based on capital needs and the maturity or redemption of securities.
Southern Company
Net cash provided from operating activities increased $14 million in 2025 as compared to 2024 primarily due to higher net income after non-cash adjustments and the timing of storm restoration cost recovery at Georgia Power and customer receivable collections, largely offset by the timing of vendor payments, decreased retail fuel cost recovery, and the timing of tax payments. See Note 2 to the financial statements under "Georgia Power – Storm Damage Recovery" for additional information.
The net cash used for investing activities in 2025 and 2024 was primarily related to the Subsidiary Registrants' construction programs.
The net cash provided from financing activities in 2025 was primarily related to net issuances of long-term debt and issuances of common stock through the settlement of forward sale contracts, partially offset by common stock dividend payments, a reduction in commercial paper borrowings, and Southern Power's purchase of membership interests in SP Wind. The net cash used for financing activities in 2024 was primarily related to common stock dividend payments, a reduction in commercial paper borrowings, and a net decrease in short-term borrowings, partially offset by net issuances of long-term debt. See Notes 8 and 15 to the financial statements under "Equity Distribution Agreement" and "Southern PowerPurchase of Renewable Facility Interests," respectively, for additional information.
Alabama Power
Net cash provided from operating activities decreased $323 million in 2025 as compared to 2024 primarily due to a decrease in fuel cost recovery and customer refunds associated with the nuclear fuel disposal cost award, partially offset by the monetization of §45U PTCs. See Notes 2 and 3 to the financial statements under "Alabama Power – Nuclear Production Tax Credits Order" and "Nuclear Fuel Disposal Costs," respectively, for additional information.
The net cash used for investing activities in 2025 and 2024 was primarily related to gross property additions and, for 2025, the acquisition of the Lindsay Hill Generating Station. See Note 15 to the financial statements under "Alabama Power" for additional information.
The net cash provided from financing activities in 2025 was primarily related to net issuances of senior notes and capital contributions from Southern Company, partially offset by common stock dividend payments. The net cash used for financing activities in 2024 was primarily related to common stock dividend payments, partially offset by capital contributions from Southern Company.
Georgia Power
Net cash provided from operating activities increased $15 million in 2025 as compared to 2024 primarily due to the timing of storm restoration cost recovery and customer receivable collections and an increase in retail revenues associated with base tariff increases, largely offset by the timing of vendor payments and higher income tax payments. See Note 2 to the financial statements under "Georgia Power – Storm Damage Recovery" for additional information relating to storm restoration costs.
II-57

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
The net cash used for investing activities in 2025 and 2024 was primarily related to gross property additions including costs associated with projects approved through the 2023 IRP Update and the certification requests in September and December 2025. See Note 2 to the financial statements under "Georgia Power – Integrated Resource Plans" and " – Other Construction" for information regarding Georgia Power's current construction projects.
The net cash provided from financing activities in 2025 was primarily related to capital contributions from Southern Company and net issuances of senior notes, partially offset by common stock dividend payments. The net cash provided from financing activities in 2024 was primarily related to capital contributions from Southern Company and net issuances of senior notes, partially offset by common stock dividend payments, a reduction in commercial paper borrowings, and a net decrease in short-term borrowings.
Mississippi Power
Net cash provided from operating activities increased $8 million in 2025 as compared to 2024 primarily due to funds received as part of the Plant Daniel acquisition, lower income tax payments, and the timing of fossil fuel stock purchases, largely offset by decreased fuel cost recovery. See Note 2 to the financial statements under "Mississippi Power – Plant Daniel" for additional information.
The net cash used for investing activities in 2025 and 2024 was primarily related to gross property additions.
The net cash used for financing activities in 2025 was primarily related to common stock dividend payments and a reduction in commercial paper borrowings, partially offset by issuances of senior notes and capital contributions from Southern Company. The net cash used for financing activities in 2024 was primarily related to common stock dividend payments, partially offset by capital contributions from Southern Company and net issuances of senior notes.
Southern Power
Net cash provided from operating activities decreased $38 million in 2025 as compared to 2024 primarily due to a change in the utilization of federal tax credit carryforwards, partially offset by the timing of customer receivable collections.
The net cash used for investing activities in 2025 and 2024 was primarily related to ongoing construction activities. See Note 15 to the financial statements under "Southern Power" for additional information.
The net cash provided from financing activities in 2025 was primarily related to capital contributions from Southern Company, net issuances of senior notes, and an increase in commercial paper borrowings, partially offset by the purchase of membership interests from noncontrolling interests, common stock dividend payments, and net distributions to noncontrolling interests. The net cash used for financing activities in 2024 was primarily related to common stock dividend payments, net distributions to noncontrolling interests, and a reduction in commercial paper borrowings, partially offset by capital contributions from Southern Company.
Southern Company Gas
Net cash provided from operating activities increased $65 million in 2025 as compared to 2024 primarily due to changes in recovery on certain regulatory clauses, due to weather impacts and timing, and timing of payments for natural gas as a result of higher volume and prices, as well as timing of other vendor payments, partially offset by timing of customer receivable collections as a result of weather impacts, higher natural gas prices, and increased base rates in 2025, as well as timing of income tax payments.
The net cash used for investing activities in 2025 and 2024 was primarily related to construction of transmission and distribution assets recovered through base rates.
The net cash provided from financing activities in 2025 was primarily related to net issuances of senior notes and first mortgage bonds, partially offset by common stock dividend payments. The net cash provided from financing activities in 2024 was primarily related to the issuance of senior notes and first mortgage bonds, partially offset by common stock dividend payments.
Significant Balance Sheet Changes
Southern Company
Significant balance sheet changes in 2025 for Southern Company included:
an increase of $9.7 billion in total property, plant, and equipment primarily related to the Subsidiary Registrants' construction programs;
an increase of $8.4 billion in long-term debt (including securities due within one year) related to issuances of senior notes and junior subordinated notes, partially offset by repayment of senior notes;
II-58

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
an increase of $2.8 billion in total common stockholders' equity primarily related to net income and issuances of common stock largely through the settlement of forward sale contracts, partially offset by common stock dividend payments;
a decrease of $630 million in under recovered fuel clause revenues primarily due to increased fuel cost recovery at Georgia Power;
a decrease of $616 million in notes payable due to a reduction in commercial paper borrowings and repayment of short-term bank debt;
a decrease of $615 million in noncontrolling interests primarily related to Southern Power's purchase of membership interests in SP Wind, net distributions to noncontrolling interests, and net loss attributable to noncontrolling interests;
an increase of $583 million in prepaid pension costs primarily related to actual returns on plan assets, partially offset by actuarial losses resulting from decreases in the assumed discount rates;
an increase of $569 million in cash and cash equivalents, as reflected in the statements of cash flows and discussed further under "Analysis of Cash Flow – Southern Company" herein; and
an increase of $403 million in accumulated deferred income taxes primarily related to an increase in property-related timing differences and federal tax credit carryforwards.
See "Financing Activities" herein and Notes 2, 5, 7, 8, 10, 11, and 15 to the financial statements for additional information.
Alabama Power
Significant balance sheet changes in 2025 for Alabama Power included:
an increase of $1.3 billion in total property, plant, and equipment primarily related to the construction of transmission and distribution facilities and the acquisition of the Lindsay Hill Generating Station;
an increase of $906 million in total common stockholder's equity primarily due to net income and capital contributions from Southern Company, partially offset by dividends paid to Southern Company;
an increase of $859 million in long-term debt (including securities due within one year) primarily due to net issuances of senior notes; and
decreases of $379 million and $262 million in AROs and regulatory assets associated with AROs, respectively, primarily related to settlements and cost estimate updates.
See "Financing Activities – Alabama Power" herein and Notes 5, 6, 8, and 15 to the financial statements for additional information.
Georgia Power
Significant balance sheet changes in 2025 for Georgia Power included:
an increase of $6.8 billion in total property, plant, and equipment primarily related to the construction of generation, transmission, and distribution facilities, including costs associated with projects approved through the 2023 IRP Update and the certification requests in September and December 2025;
an increase of $3.4 billion in common stockholder's equity primarily due to net income and capital contributions from Southern Company, partially offset by dividends paid to Southern Company;
an increase of $3.1 billion in long-term debt (including securities due within one year) primarily due to net issuances of senior notes;
a decrease of $644 million in under recovered retail fuel clause revenues primarily resulting from increased recovery of deferred fuel expense as ordered in Georgia Power's 2023 fuel cost recovery case; and
an increase of $426 million in accumulated deferred income taxes primarily related to an increase in property-related timing differences.
See "Financing Activities –Georgia Power" herein and Notes 2, 5, 8, and 10 to the financial statements for additional information.
Mississippi Power
Significant balance sheet changes in 2025 for Mississippi Power included:
an increase of $171 million in total property, plant, and equipment primarily related to the construction of transmission and distribution facilities;
an increase of $100 million in common stockholder's equity primarily related to net income and capital contributions from Southern Company, partially offset by dividends paid to Southern Company;
II-59

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
an increase of $93 million in long-term debt (including securities due within one year) primarily due to issuances of senior notes;
a decrease of $55 million in other cost of removal obligations primarily due to an increase in expenditures related to transmission and other production assets; and
an increase of $41 million in other deferred credits and liabilities primarily due to contributions in aid of construction.
See "Financing Activities – Mississippi Power" herein and Notes 5 and 8 to the financial statements for additional information.
Southern Power
Significant balance sheet changes in 2025 for Southern Power included:
an increase of $260 million in long-term debt (including securities due within one year) primarily due to net issuances of senior notes;
an increase of $162 million in total property, plant, and equipment in service primarily due to an increase in CWIP primarily related to the continued construction of the Millers Branch solar facility and the wind repowering projects, partially offset by the continued depreciation of assets;
a decrease of $161 million in total stockholders' equity primarily due to the purchase of membership interests from noncontrolling interests, dividends paid to Southern Company, net distributions to noncontrolling interests, and net loss, partially offset by capital contributions from Southern Company;
an increase of $138 million in notes payable due to an increase in commercial paper borrowings; and
a decrease of $133 million in accumulated deferred income taxes primarily related to a change in the utilization of ITCs.
See "Financing Activities – Southern Power" and Notes 5, 8, 10, and 15 to the financial statements for additional information.
Southern Company Gas
Significant balance sheet changes in 2025 for Southern Company Gas included:
an increase of $1.2 billion in total property, plant, and equipment primarily related to the construction of transmission and distribution assets;
an increase of $743 million in long-term debt (including securities due within one year) due to net issuances of senior notes and first mortgage bonds;
an increase of $200 million in total accounts receivable primarily related to higher customer billings driven by colder weather, higher natural gas prices, and increased base rates;
an increase of $175 million in accumulated deferred income taxes primarily due to reversal of CAMT and additional property-related timing differences;
an increase of $131 million in common stockholder's equity primarily related to net income, partially offset by dividends paid to Southern Company; and
an increase of $111 million in total accounts payable primarily related to higher natural gas volumes and prices and the timing of vendor payments.
See "Financing Activities – Southern Company Gas" and FUTURE EARNINGS POTENTIAL – "Income Tax Matters" herein and Notes 5, 8, and 10 to the financial statements for additional information.
II-60

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Financing Activities
The following table outlines long-term debt financing activities for the year ended December 31, 2025:
Issuances and Reofferings
Maturities and Redemptions
CompanySenior Notes
Other Long-
Term Debt
Senior Notes
Revenue
Bonds
Other Long-
   Term Debt(a)
(in millions)
Southern Company parent$3,650 $2,365 $2,895 $— $— 
Alabama Power1,100 250 — 
Georgia Power3,100 — 700 45 118 
Mississippi Power100 — — 11 
Southern Power1,100 — 900 — — 
Southern Company Gas850 200 250 — 50 
Other(b)
— — — — 13 
Elimination(c)
— — — — (18)
Southern Company$9,900 $2,570 $4,995 $56 $167 
(a)Includes reductions in finance lease obligations resulting from cash payments under finance leases and, for Georgia Power, principal amortization payments totaling $86 million for FFB borrowings. See Note 8 to the financial statements under "Long-term Debt – DOE Loan Guarantee Borrowings" for additional information.
(b)Includes repayment by SEGCO of $10 million of its $100 million principal amount long-term bank loan due November 15, 2026, which is guaranteed by Alabama Power. See Note 3 to the financial statements under "Guarantees" for additional information.
(c)Represents reductions in affiliate finance lease obligations at Georgia Power, which are eliminated in Southern Company's consolidated financial statements.
Except as otherwise described herein, the Registrants used the proceeds of debt issuances for their redemptions and maturities shown in the table above, to repay short-term indebtedness, and for general corporate purposes, including working capital. The Subsidiary Registrants also used the proceeds for their construction programs.
In addition to any financings that may be necessary to meet capital requirements and contractual obligations, the Registrants plan to continue, when economically feasible, a program to retire higher-cost securities and replace these obligations with lower-cost capital if market conditions permit.
Southern Company
During 2025, Southern Company issued approximately 22.5 million shares of common stock primarily through forward sale contract settlements and dividend reinvestment and employee equity compensation and savings plans. Proceeds from settlements of the forward sale contracts totaled approximately $1.5 billion. Also during 2025, Southern Company entered into additional forward sale contracts for the issuance of shares of common stock that may be settled through June 2027. See Note 8 to the financial statements under "Equity Distribution Agreement" for additional information.
In addition, in November 2025, Southern Company issued 40 million 2025 Series A Equity Units (2025 Equity Units), initially in the form of corporate units (Corporate Units), at a stated amount of $50 per Corporate Unit, for a total stated amount of $2 billion. Net proceeds from the issuance were $1.965 billion. Each Corporate Unit is comprised of (i) a stock purchase contract, which obligates the holder to purchase from Southern Company, no later than December 15, 2028, a certain number of shares of Southern Company's common stock for $50 in cash, (ii) a 1/40 undivided beneficial ownership interest in $1,000 principal amount of Southern Company's Series 2025B Remarketable Senior Notes due 2030, and (iii) a 1/40 undivided beneficial ownership interest in $1,000 principal amount of Southern Company's Series 2025C Remarketable Senior Notes due 2033. See Note 8 to the financial statements under "Equity Units" for additional information.
In January 2025, Southern Company issued $565 million aggregate principal amount of Series 2025A 6.50% Junior Subordinated Notes due March 15, 2085.
In February 2025, Southern Company issued $1.8 billion aggregate principal amount of Series 2025B 6.375% Fixed-to-Fixed Reset Rate Junior Subordinated Notes due March 15, 2055.
In May 2025, Southern Company issued $1.65 billion aggregate principal amount of Series 2025A 3.25% Convertible Senior Notes due June 15, 2028 in a private offering. Southern Company used a portion of the proceeds from this issuance to repurchase approximately $781.6 million of the $1.725 billion aggregate principal amount outstanding of its Series 2023A 3.875% Convertible Senior Notes due December 15, 2025 (Series 2023A Convertible Senior Notes) and approximately $328.1 million of the $1.5 billion aggregate principal amount outstanding of its Series 2024A 4.50% Convertible Senior Notes due June 15, 2027
II-61

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
(Series 2024A Convertible Senior Notes). See Note 8 to the financial statements under "Convertible Senior Notes" herein for additional information.
In October 2025, Southern Company repaid at maturity $500 million aggregate principal amount of its Series 2022A 5.15% Senior Notes.
In November 2025, Southern Company used a portion of the net proceeds from the 2025 Equity Units to repurchase (i) an additional approximately $674.4 million of the remaining approximately $943.4 million aggregate principal amount outstanding of its Series 2023A Convertible Senior Notes and (ii) an additional approximately $342.0 million of the remaining approximately $1.172 billion aggregate principal amount outstanding of its Series 2024A Convertible Senior Notes. See Note 8 to the financial statements under "Equity Units" for additional information.
In December 2025, Southern Company settled at maturity the remaining approximately $269.1 million outstanding of its Series 2023A Convertible Senior Notes. See Note 8 to the financial statements under "Convertible Senior Notes" for additional information.
Subsequent to December 31, 2025, Southern Company redeemed all $1.25 billion aggregate principal amount of its Series 2020B 4.00% Fixed-to-Fixed Reset Rate Junior Subordinated Notes due January 15, 2051.
Alabama Power
During 2025, a subsidiary of Alabama Power borrowed an additional approximately $5 million under a $20 million fixed rate bank loan entered into in December 2023 with a maturity date of December 31, 2030. The aggregate amount outstanding under this loan at December 31, 2025 was approximately $20 million.
In March 2025, Alabama Power issued $500 million aggregate principal amount of Series 2025A 5.10% Senior Notes due April 2, 2035.
In April 2025, Alabama Power repaid at maturity $250 million aggregate principal amount of its Series 2015B 2.80% Senior Notes.
In June 2025, Alabama Power issued $100 million aggregate principal amount of Series 2025B Floating Rate Senior Notes due August 15, 2075.
In July 2025, a subsidiary of Alabama Power repaid $1 million under a $15 million credit line entered into in December 2024 with a maturity date of December 11, 2026.
In September 2025, Alabama Power issued $500 million aggregate principal amount of Series 2025C 4.30% Senior Notes due March 15, 2031.
Georgia Power
In March 2025, Georgia Power issued $400 million aggregate principal amount of Series 2025A Floating Rate Senior Notes due September 15, 2026, $500 million aggregate principal amount of Series 2025B 4.85% Senior Notes due March 15, 2031, and $700 million aggregate principal amount of Series 2025C 5.20% Senior Notes due March 15, 2035.
In May 2025, Georgia Power repaid at maturity $700 million aggregate principal amount of its Series 2023C Floating Rate Senior Notes.
Also in May 2025, Georgia Power entered into a $200 million short-term floating rate bank loan bearing interest based on term SOFR.
In June 2025, Georgia Power extended both of its short-term floating rate bank loans totaling $400 million to long-term term loans, which mature in June 2026.
In July 2025, Georgia Power repaid at maturity its obligations with respect to $45 million aggregate principal amount of Development Authority of Monroe County (Georgia) Pollution Control Revenue Bonds (Georgia Power Company Plant Scherer Project), First Series 1995.
In September 2025, Georgia Power issued $250 million aggregate principal amount of additional Series 2025B 4.85% Senior Notes due March 15, 2031, $750 million aggregate principal amount of Series 2025D 4.00% Senior Notes due October 1, 2028, and $500 million aggregate principal amount of Series 2025E 5.50% Senior Notes due October 1, 2055.
Mississippi Power
In March 2025, Mississippi Power issued $50 million aggregate principal amount of Series 2025A 5.01% Senior Notes due March 15, 2030 and $50 million aggregate principal amount of Series 2025B 6.03% Senior Notes due March 15, 2055.
II-62

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
In July 2025, Mississippi Power repaid at maturity its obligations with respect to approximately $11 million aggregate principal amount of Mississippi Business Finance Corporation Solid Waste Disposal Facilities Revenue Bonds, Series 1995 (Mississippi Power Company Project).
Southern Power
In September 2025, Southern Power issued $550 million aggregate principal amount of Series 2025A 4.25% Senior Notes due October 1, 2030 and $550 million aggregate principal amount of Series 2025B 4.90% Senior Notes due October 1, 2035.
In October 2025, Southern Power redeemed all $500 million aggregate principal amount of its Series 2015C 4.15% Senior Notes due December 1, 2025.
In December 2025, Southern Power redeemed all $400 million aggregate principal amount of its Series 2021A 0.90% Senior Notes due January 15, 2026.
Southern Company Gas
In August 2025, Nicor Gas repaid at maturity $50 million aggregate principal amount of its 1.42% Series First Mortgage Bonds.
In September 2025, Southern Company Gas Capital issued $425 million aggregate principal amount of Series 2025A 4.05% Senior Notes due September 15, 2028 and $425 million aggregate principal amount of Series 2025B 5.10% Senior Notes due September 15, 2035, both guaranteed by Southern Company Gas.
In October 2025, Nicor Gas issued in a private placement $25 million aggregate principal amount of 4.17% Series First Mortgage Bonds due October 1, 2028 and $75 million aggregate principal amount of 4.92% Series First Mortgage Bonds due October 1, 2035. In December 2025, pursuant to the same agreement, Nicor Gas issued in a private placement $50 million aggregate principal amount of 5.59% Series First Mortgage Bonds due December 15, 2055 and $50 million aggregate principal amount of 5.69% Series First Mortgage Bonds due December 15, 2065.
In November 2025, Southern Company Gas Capital repaid at maturity $250 million aggregate principal amount of its 3.875% Senior Notes.
Credit Rating Risk
At December 31, 2025, the Registrants did not have any credit arrangements that would require material changes in payment schedules or terminations as a result of a credit rating downgrade.
There are certain contracts that could require collateral, but not accelerated payment, in the event of a credit rating change of certain Registrants to BBB and/or Baa2 or below. These contracts are primarily for physical electricity and natural gas purchases and sales, fuel purchases, fuel transportation and storage, energy price risk management, transmission, interest rate management, and equipment purchases related to construction of facilities.
The maximum potential collateral requirements under these contracts at December 31, 2025 were as follows:
Credit Ratings
Southern
   Company(*)
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
   Power(*)
Southern
Company
Gas
(in millions)
At BBB and/or Baa2$32 $$— $— $30 $— 
At BBB- and/or Baa3445 36 — 406 — 
At BB+ and/or Ba1 or below3,774 424 2,503 278 1,347 29 
(*)Southern Power has PPAs that could require collateral, but not accelerated payment, in the event of a downgrade of Southern Power's credit. The PPAs require credit assurances without stating a specific credit rating. The amount of collateral required would depend upon actual losses resulting from a credit downgrade. Southern Power had $106 million of cash collateral posted related to PPA requirements at December 31, 2025.
The amounts in the previous table for the traditional electric operating companies and Southern Power include certain agreements that could require collateral if either Alabama Power or Georgia Power has a credit rating change to below investment grade. Generally, collateral may be provided by a Southern Company guaranty, letter of credit, or cash. Additionally, a credit rating downgrade could impact the ability of the Registrants to access capital markets and would be likely to impact the cost at which they do so.
Mississippi Power and its largest retail customer, Chevron Products Company (Chevron), have agreements under which Mississippi Power provides retail service to the Chevron refinery in Pascagoula, Mississippi through at least 2038. The agreements grant Chevron a security interest in the co-generation assets owned by Mississippi Power located at the refinery that is
II-63

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
exercisable upon the occurrence of (i) certain bankruptcy events or (ii) other events of default coupled with specific reductions in steam output at the facility and a downgrade of Mississippi Power's credit rating to below investment grade by two of the three rating agencies.
On August 22, 2025, Fitch revised the ratings outlook of Georgia Power to stable from positive.
On September 23, 2025, Moody's revised the ratings outlook of Southern Company to negative from stable and the ratings outlook of Georgia Power to stable from positive.
Market Price Risk
The Registrants had no material change in market risk exposure for the year ended December 31, 2025 when compared to the year ended December 31, 2024. See Note 14 to the financial statements for an in-depth discussion of the Registrants' derivatives, as well as Note 1 to the financial statements under "Financial Instruments" for additional information.
Due to cost-based rate regulation and other various cost recovery mechanisms, the traditional electric operating companies and the natural gas distribution utilities that sell natural gas directly to end-use customers continue to have limited exposure to market volatility in interest rates, foreign currency exchange rates, commodity fuel prices, and prices of electricity. The traditional electric operating companies and certain of the natural gas distribution utilities manage fuel-hedging programs implemented per the guidelines of their respective state PSCs or other applicable state regulatory agencies to hedge the impact of market fluctuations in natural gas prices for customers. Mississippi Power also manages wholesale fuel-hedging programs under agreements with its wholesale customers. Because energy from Southern Power's facilities is primarily sold under long-term PPAs with tolling agreements and provisions shifting substantially all of the responsibility for fuel cost to the counterparties, Southern Power's exposure to market volatility in commodity fuel prices and prices of electricity is generally limited. However, Southern Power has been and may continue to be exposed to market volatility in energy-related commodity prices as a result of uncontracted generating capacity. To mitigate residual risks relative to movements in electricity prices, the traditional electric operating companies and Southern Power may enter into physical fixed-price contracts for the purchase and sale of electricity through the wholesale electricity market and, to a lesser extent, financial hedge contracts for natural gas purchases; however, a significant portion of contracts are priced at market.
Certain of Southern Company Gas' non-regulated operations routinely utilize various types of derivative instruments to economically hedge certain commodity price and weather risks inherent in the natural gas industry. These instruments include a variety of exchange-traded and OTC energy contracts, such as forward contracts, futures contracts, options contracts, and swap agreements. Southern Company Gas' gas marketing services business also actively manages storage positions through a variety of hedging transactions for the purpose of managing exposures arising from changing natural gas prices. These hedging instruments are used to substantially protect economic margins (as spreads between wholesale and retail natural gas prices widen between periods) and thereby minimize exposure to declining earnings. Some of these economic hedge activities may not qualify, or may not be designated, for hedge accounting treatment.
The following table provides information related to variable interest rate exposure on long-term debt (including amounts due within one year) at December 31, 2025 for the applicable Registrants:
At December 31, 2025
Southern
   Company(*)
Alabama
Power
Georgia
Power
Mississippi
Power
Southern Company
Gas
(in millions, except percentages)
Long-term variable interest rate exposure
$5,318 $1,141 $1,584 $58 $500 
Weighted average interest rate on long-term variable interest rate exposure4.31 %3.05 %3.60 %2.75 %4.28 %
Impact on annualized interest expense of 100 basis point change in interest rates$53 $11 $16 $$
(*)Includes $2.0 billion of long-term variable interest rate exposure at the Southern Company parent entity.
The Registrants may enter into interest rate derivatives designated as hedges, which are intended to mitigate interest rate volatility related to forecasted debt financings and existing fixed and floating rate obligations. See Note 14 to the financial statements under "Interest Rate Derivatives" for additional information.
Southern Company and Southern Power had foreign currency denominated debt at December 31, 2025 and have each mitigated exposure to foreign currency exchange rate risk through the use of foreign currency swaps. See Note 14 to the financial statements under "Foreign Currency Derivatives" for additional information.
II-64

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Changes in fair value of energy-related derivative contracts for Southern Company and Southern Company Gas for the years ended December 31, 2025 and 2024 are provided in the table below. At December 31, 2025 and 2024, substantially all of the traditional electric operating companies' and certain of the natural gas distribution utilities' energy-related derivative contracts were designated as regulatory hedges and were related to the applicable company's fuel-hedging program.
Southern
   Company(a)
Southern
   Company Gas(a)
(in millions)
Contracts outstanding at December 31, 2023, assets (liabilities), net
$(304)$(49)
Contracts realized or settled211 
Current period changes(b)
54 52 
Contracts outstanding at December 31, 2024, assets (liabilities), net
(39)10 
Contracts realized or settled9 (13)
Current period changes(b)
(18)(7)
Contracts outstanding at December 31, 2025, assets (liabilities), net
$(48)$(10)
(a)Excludes cash collateral held on deposit in broker margin accounts of $33 million, $17 million, and $62 million at December 31, 2025, 2024, and 2023, respectively, and immaterial premium and intrinsic value associated with weather derivatives for all periods presented.
(b)The changes in fair value of energy-related derivative contracts are substantially attributable to both the volume and the price of natural gas. Current period changes also include the changes in fair value of new contracts entered into during the period, if any.
The net hedge volumes of energy-related derivative contracts for natural gas purchased at December 31, 2025 and 2024 for Southern Company and Southern Company Gas were as follows:
Southern CompanySouthern Company Gas
mmBtu Volume (in millions)
At December 31, 2025:
Commodity – Natural gas swaps274  
Commodity – Natural gas options157 63 
Total hedge volume431 63 
At December 31, 2024:
Commodity – Natural gas swaps255 — 
Commodity – Natural gas options176 83 
Total hedge volume431 83 
Southern Company Gas' derivative contracts are comprised of both long and short natural gas positions. A long position is a contract to purchase natural gas, and a short position is a contract to sell natural gas. The volumes presented above for Southern Company Gas represent the net of long natural gas positions of 72 million mmBtu and short natural gas positions of 9 million mmBtu at December 31, 2025 and the net of long natural gas positions of 90 million mmBtu and short natural gas positions of 7 million mmBtu at December 31, 2024.
For the Southern Company system, the weighted average swap contract cost per mmBtu was approximately $0.11 per mmBtu below market prices at December 31, 2025 and was approximately $0.15 per mmBtu below market prices at December 31, 2024. The change in option fair value is primarily attributable to the volatility of the market and the underlying change in the natural gas price. Substantially all of the traditional electric operating companies' natural gas hedge gains and losses are recovered through their respective fuel cost recovery clauses.
The Registrants use OTC contracts that are not exchange traded but are fair valued using prices which are market observable, and thus fall into Level 2 of the fair value hierarchy. In addition, Southern Company Gas uses exchange-traded market-observable contracts, which are categorized as Level 1. See Note 13 to the financial statements for further discussion of fair value
II-65

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
measurements. The maturities of the energy-related derivative contracts for Southern Company and Southern Company Gas at December 31, 2025 were as follows:
Fair Value Measurements of Contracts at
December 31, 2025
Total
Fair Value
Maturity
2026
2027 – 2028
2029 – 2030
Thereafter
(in millions)
Southern Company
Level 1(a)
$(7)$(7)$— $— $— 
Level 2(b)
(41)(40)(3)— 
Southern Company total(c)
$(48)$(47)$(3)$$— 
Southern Company Gas
Level 1(a)
$(7)$(7)$— $— $— 
Level 2(b)
(3)(3)— — — 
Southern Company Gas total(c)
$(10)$(10)$— $— $— 
(a)Valued using NYMEX futures prices.
(b)Level 2 amounts for Southern Company Gas are valued using basis transactions that represent the cost to transport natural gas from a NYMEX delivery point to the contract delivery point. These transactions are based on quotes obtained either through electronic trading platforms or directly from brokers.
(c)Excludes cash collateral of $33 million as well as immaterial premium and associated intrinsic value associated with weather derivatives.
The Registrants are exposed to risk in the event of nonperformance by counterparties to energy-related and interest rate derivative contracts, as applicable. The Registrants generally enter into agreements and material transactions with counterparties that have investment grade credit ratings by Moody's, S&P, or Fitch or with counterparties who have posted collateral to cover potential credit exposure. Therefore, the Registrants do not anticipate market risk exposure from nonperformance by the counterparties. For additional information, see Note 1 to the financial statements under "Financial Instruments" and Note 14 to the financial statements.
Credit Risk
Southern Company (except as discussed herein), the traditional electric operating companies, and Southern Power are not exposed to any concentrations of credit risk. The traditional electric operating companies and Southern Power have received collateral or acceptable substitute guarantees as financial security from counterparties to contracts for certain data centers and other large load customers as described in FUTURE EARNINGS POTENTIAL – "General" herein and PPAs as described in FUTURE EARNINGS POTENTIAL – "Southern Power's Power Sales Agreements" herein. Southern Company Gas' exposure to concentrations of credit risk is discussed herein.
Southern Company Gas
Gas Distribution Operations
Concentration of credit risk occurs at Atlanta Gas Light for amounts billed for services and other costs to its customers, which consist of the 14 Marketers in Georgia. The credit risk exposure to the Marketers varies seasonally, with the lowest exposure in the non-peak summer months and the highest exposure in the peak winter months. Marketers are responsible for the retail sale of natural gas to end-use customers in Georgia. The provisions of Atlanta Gas Light's tariff allow Atlanta Gas Light to obtain credit security support in an amount equal to a minimum of two times a Marketer's highest month's estimated bill from Atlanta Gas Light. For 2025, the four largest Marketers based on customer count, which includes SouthStar, accounted for 19% of Southern Company Gas' operating revenues and 22% of operating revenues for Southern Company Gas' gas distribution operations segment.
Several factors are designed to mitigate Southern Company Gas' risks from the increased concentration of credit that has resulted from deregulation. In addition to the security support described above, Atlanta Gas Light bills intrastate delivery service to Marketers in advance rather than in arrears. Atlanta Gas Light accepts credit support in the form of cash deposits, letters of credit/surety bonds from acceptable issuers, and corporate guarantees from investment-grade entities. Southern Company Gas reviews the adequacy of credit support coverage, credit rating profiles of credit support providers, and payment status of each Marketer. Southern Company Gas believes that adequate policies and procedures are in place to properly quantify, manage, and report on Atlanta Gas Light's credit risk exposure to Marketers.
II-66

    Table of Contents                                Index to Financial Statements        

COMBINED MANAGEMENT'S DISCUSSION AND ANALYSIS
Atlanta Gas Light also faces potential credit risk in connection with assignments of interstate pipeline transportation and storage capacity to Marketers. Although Atlanta Gas Light assigns this capacity to Marketers, in the event that a Marketer fails to pay the interstate pipelines for the capacity, the interstate pipelines would likely seek repayment from Atlanta Gas Light.
Gas Marketing Services
Southern Company Gas obtains credit scores for its firm residential and small commercial customers using a national credit reporting agency, enrolling only those customers that meet or exceed Southern Company Gas' credit threshold. Southern Company Gas considers potential interruptible and large commercial customers based on reviews of publicly available financial statements and commercially available credit reports. Prior to entering into a physical transaction, Southern Company Gas also assigns physical wholesale counterparties an internal credit rating and credit limit based on the counterparties' Moody's, S&P, and Fitch ratings, commercially available credit reports, and audited financial statements.
II-67

    Table of Contents                                Index to Financial Statements
Item 8.FINANCIAL STATEMENTS AND SUPPLEMENTARY DATA
 Page
The Southern Company and Subsidiary Companies:
Report of Independent Registered Public Accounting Firm
II-69
Consolidated Statements of Income for the Years Ended December 31, 2025, 2024, and 2023
II-71
Consolidated Statements of Comprehensive Income for the Years Ended December 31, 2025, 2024, and 2023
II-72
Consolidated Statements of Cash Flows for the Years Ended December 31, 2025, 2024, and 2023
II-73
Consolidated Balance Sheets at December 31, 2025 and 2024
II-74
Consolidated Statements of Stockholders' Equity for the Years Ended December 31, 2025, 2024, and 2023
II-76
Alabama Power:
Report of Independent Registered Public Accounting Firm
II-77
Statements of Income for the Years Ended December 31, 2025, 2024, and 2023
II-79
Statements of Comprehensive Income for the Years Ended December 31, 2025, 2024, and 2023
II-79
Statements of Cash Flows for the Years Ended December 31, 2025, 2024, and 2023
II-80
Balance Sheets at December 31, 2025 and 2024
II-81
Statements of Common Stockholder's Equity for the Years Ended December 31, 2025, 2024, and 2023
II-83
Georgia Power:
Report of Independent Registered Public Accounting Firm
II-84
Statements of Income for the Years Ended December 31, 2025, 2024, and 2023
II-86
Statements of Comprehensive Income for the Years Ended December 31, 2025, 2024, and 2023
II-86
Statements of Cash Flows for the Years Ended December 31, 2025, 2024, and 2023
II-87
Balance Sheets at December 31, 2025 and 2024
II-88
Statements of Common Stockholder's Equity for the Years Ended December 31, 2025, 2024, and 2023
II-90
Mississippi Power:
Report of Independent Registered Public Accounting Firm
II-91
Statements of Income for the Years Ended December 31, 2025, 2024, and 2023
II-93
Statements of Comprehensive Income for the Years Ended December 31, 2025, 2024, and 2023
II-93
Statements of Cash Flows for the Years Ended December 31, 2025, 2024, and 2023
II-94
Balance Sheets at December 31, 2025 and 2024
II-95
Statements of Common Stockholder's Equity for the Years Ended December 31, 2025, 2024, and 2023
II-97
Southern Power and Subsidiary Companies:
Report of Independent Registered Public Accounting Firm
II-98
Consolidated Statements of Income for the Years Ended December 31, 2025, 2024, and 2023
II-100
Consolidated Statements of Comprehensive Income for the Years Ended December 31, 2025, 2024, and 2023
II-100
Consolidated Statements of Cash Flows for the Years Ended December 31, 2025, 2024, and 2023
II-101
Consolidated Balance Sheets at December 31, 2025 and 2024
II-102
Consolidated Statements of Stockholders' Equity for the Years Ended December 31, 2025, 2024, and 2023
II-104
Southern Company Gas and Subsidiary Companies:
Report of Independent Registered Public Accounting Firm
II-105
Consolidated Statements of Income for the Years Ended December 31, 2025, 2024, and 2023
II-109
Consolidated Statements of Comprehensive Income for the Years Ended December 31, 2025, 2024, and 2023
II-109
Consolidated Statements of Cash Flows for the Years Ended December 31, 2025, 2024, and 2023
II-110
Consolidated Balance Sheets at December 31, 2025 and 2024
II-111
Consolidated Statements of Common Stockholder's Equity for the Years Ended December 31, 2025, 2024, and 2023
II-113
Combined Notes to Financial Statements
II-114

II-68

    Table of Contents                                Index to Financial Statements

REPORT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM
To the stockholders and the Board of Directors of The Southern Company and Subsidiary Companies
Opinions on the Financial Statements and Internal Control over Financial Reporting
We have audited the accompanying consolidated balance sheets of The Southern Company and Subsidiary Companies (Southern Company) as of December 31, 2025 and 2024, the related consolidated statements of income, comprehensive income, stockholders' equity, and cash flows for each of the three years in the period ended December 31, 2025, the related notes, and the financial statement schedule listed in the Index at Item 15 (collectively referred to as the "financial statements"). We also have audited Southern Company's internal control over financial reporting as of December 31, 2025, based on criteria established in Internal Control – Integrated Framework (2013) issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO).
In our opinion, the financial statements referred to above present fairly, in all material respects, the financial position of Southern Company as of December 31, 2025 and 2024, and the results of its operations and its cash flows for each of the three years in the period ended December 31, 2025, in conformity with accounting principles generally accepted in the United States of America. Also, in our opinion, Southern Company maintained, in all material respects, effective internal control over financial reporting as of December 31, 2025, based on criteria established in Internal Control – Integrated Framework (2013) issued by COSO.
Basis for Opinions
Southern Company's management is responsible for these financial statements, for maintaining effective internal control over financial reporting, and for its assessment of the effectiveness of internal control over financial reporting, included in the accompanying Management's Report on Internal Control Over Financial Reporting. Our responsibility is to express an opinion on these financial statements and an opinion on Southern Company's internal control over financial reporting based on our audits. We are a public accounting firm registered with the Public Company Accounting Oversight Board (United States) (PCAOB) and are required to be independent with respect to Southern Company in accordance with the U.S. federal securities laws and the applicable rules and regulations of the Securities and Exchange Commission and the PCAOB.
We conducted our audits in accordance with the standards of the PCAOB. Those standards require that we plan and perform the audits to obtain reasonable assurance about whether the financial statements are free of material misstatement, whether due to error or fraud, and whether effective internal control over financial reporting was maintained in all material respects.
Our audits of the consolidated financial statements included performing procedures to assess the risks of material misstatement of the financial statements, whether due to error or fraud, and performing procedures to respond to those risks. Such procedures included examining, on a test basis, evidence regarding the amounts and disclosures in the financial statements. Our audits also included evaluating the accounting principles used and significant estimates made by management, as well as evaluating the overall presentation of the financial statements. Our audit of internal control over financial reporting included obtaining an understanding of internal control over financial reporting, assessing the risk that a material weakness exists, and testing and evaluating the design and operating effectiveness of internal control based on the assessed risk. Our audits also included performing such other procedures as we considered necessary in the circumstances. We believe that our audits provide a reasonable basis for our opinions.
Definition and Limitations of Internal Control over Financial Reporting
A company's internal control over financial reporting is a process designed to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with generally accepted accounting principles. A company's internal control over financial reporting includes those policies and procedures that (1) pertain to the maintenance of records that, in reasonable detail, accurately and fairly reflect the transactions and dispositions of the assets of the company; (2) provide reasonable assurance that transactions are recorded as necessary to permit preparation of financial statements in accordance with generally accepted accounting principles, and that receipts and expenditures of the company are being made only in accordance with authorizations of management and directors of the company; and (3) provide reasonable assurance regarding prevention or timely detection of unauthorized acquisition, use, or disposition of the company's assets that could have a material effect on the financial statements.
Because of its inherent limitations, internal control over financial reporting may not prevent or detect misstatements. Also, projections of any evaluation of effectiveness to future periods are subject to the risk that controls may become inadequate because of changes in conditions, or that the degree of compliance with the policies or procedures may deteriorate.
Critical Audit Matter
The critical audit matter communicated below is a matter arising from the current-period audit of the financial statements that was communicated or required to be communicated to the Audit Committee of Southern Company's Board of Directors and that (1) relates to accounts or disclosures that are material to the financial statements and (2) involved especially challenging, subjective,
II-69

    Table of Contents                                Index to Financial Statements
or complex judgments. The communication of critical audit matters does not alter in any way our opinion on the financial statements, taken as a whole, and we are not, by communicating the critical audit matter below, providing a separate opinion on the critical audit matter or on the accounts or disclosures to which it relates.
Impact of Rate Regulation on the Financial Statements – Refer to Note 1 (Summary of Significant Accounting Policies – Regulatory Assets and Liabilities) and Note 2 (Regulatory Matters) to the financial statements
Critical Audit Matter Description
Southern Company's traditional electric operating companies and natural gas distribution utilities (the "regulated utility subsidiaries") are subject to rate regulation by their respective state Public Service Commissions or other applicable state regulatory agencies and wholesale regulation by the Federal Energy Regulatory Commission (collectively, the "Commissions"). Management has determined that the regulated utility subsidiaries meet the requirements under accounting principles generally accepted in the United States of America to utilize specialized rules to account for the effects of rate regulation in the preparation of its financial statements. Accounting for the economics of rate regulation may impact multiple financial statement line items and disclosures.
The Commissions set the rates the regulated utility subsidiaries are permitted to charge customers. Rates are determined and approved in regulatory proceedings based on an analysis of the applicable regulated utility subsidiary's costs to provide utility service and a return on, and recovery of, its investment in the utility business. Current and future regulatory decisions can have an impact on the recovery of costs, the rate of return earned on investments, and the timing and amount of assets to be recovered through rates. The Commissions' regulation of rates is premised on the full recovery of prudently incurred costs and a reasonable rate of return on invested capital. While Southern Company's regulated utility subsidiaries expect to recover costs from customers through regulated rates, there is a risk that the Commissions will not approve: (1) full recovery of the costs of providing utility service, or (2) full recovery of all amounts invested in the utility business and a reasonable return on those investments.
We identified the impact of rate regulation related to certain assets and liabilities as a critical audit matter due to the significant judgments made by management to support its assertions about impacted account balances and disclosures and/or the high degree of subjectivity involved in assessing the potential impact of future regulatory orders on incurred costs. Management judgments include assessing the likelihood of (1) recovery in future rates of incurred costs, (2) a disallowance of part of the cost of recently completed plant or plant under construction, and/or (3) a refund to customers. Auditing these judgments, which include assumptions about the outcome of future decisions by the Commissions, required specialized knowledge of accounting for rate regulations and the rate setting process due to its inherent complexities.
How the Critical Audit Matter Was Addressed in the Audit
Our audit procedures related to the impact of rate regulation on certain assets and liabilities included the following, among others:
We tested the effectiveness of management's controls over the evaluation of the likelihood of (1) the recovery in future rates of certain incurred costs and (2) refunds or future reductions in rates that should be reported as regulatory liabilities; and the monitoring and evaluation of regulatory developments that may affect the likelihood of recovering certain costs in future rates or of a future reduction in rates. We also tested the effectiveness of management's controls over the initial recognition of certain regulatory assets or liabilities.
We read and evaluated relevant regulatory orders issued and/or other relevant publicly available information to assess the likelihood of recovery of certain incurred costs in future rates or of a future reduction in rates based on precedents of the treatment of similar costs under similar circumstances.
We tested certain incurred costs recorded as regulatory assets or liabilities during the period for completeness and accuracy.
We obtained representation from management regarding the likelihood of recoverability of incurred costs and potential refund or future reduction in rates to assess management's assertions about the likelihood of recovery, refund, or a future reduction in rates.
We evaluated Southern Company's disclosures related to the impacts of rate regulation, including the balances recorded and regulatory developments, including where there is a high degree of subjectivity involved in assessing the potential impact of future regulatory orders on incurred costs.
/s/ Deloitte & Touche LLP
Atlanta, Georgia
February 18, 2026
We have served as Southern Company's auditor since 2002.
II-70

    Table of Contents                                Index to Financial Statements
CONSOLIDATED STATEMENTS OF INCOME
For the Years Ended December 31, 2025, 2024, and 2023
Southern Company and Subsidiary Companies

202520242023
(in millions)
Operating Revenues:
Retail electric revenues$19,331 $17,790 $16,343 
Wholesale electric revenues2,941 2,431 2,467 
Other electric revenues953 896 792 
Natural gas revenues5,044 4,456 4,702 
Other revenues1,284 1,151 949 
Total operating revenues29,553 26,724 25,253 
Operating Expenses:
Fuel4,897 4,096 4,365 
Purchased power980 883 883 
Cost of natural gas1,599 1,196 1,644 
Cost of other sales687 668 560 
Other operations and maintenance7,066 6,518 6,025 
Depreciation and amortization5,501 4,755 4,525 
Taxes other than income taxes1,538 1,540 1,425 
Total operating expenses22,268 19,656 19,427 
Operating Income7,285 7,068 5,826 
Other Income and (Expense):
Allowance for equity funds used during construction340 235 268 
Earnings from equity method investments112 139 144 
Interest expense, net of amounts capitalized(3,238)(2,743)(2,446)
Other income (expense), net500 530 553 
Total other income and (expense)(2,286)(1,839)(1,481)
Earnings Before Income Taxes4,999 5,229 4,345 
Income taxes828 969 496 
Consolidated Net Income4,171 4,260 3,849 
Net loss attributable to noncontrolling interests(170)(141)(127)
Consolidated Net Income Attributable to Southern Company$4,341 $4,401 $3,976 
Common Stock Data:
Earnings per share —
Basic$3.94 $4.02 $3.64 
Diluted3.92 3.99 3.62 
Average number of shares of common stock outstanding — (in millions)
Basic1,103 1,096 1,092 
Diluted1,109 1,102 1,098 
The accompanying notes are an integral part of these consolidated financial statements.
 
II-71

    Table of Contents                                Index to Financial Statements
CONSOLIDATED STATEMENTS OF COMPREHENSIVE INCOME
For the Years Ended December 31, 2025, 2024, and 2023
Southern Company and Subsidiary Companies
 
202520242023
(in millions)
Consolidated Net Income$4,171 $4,260 $3,849 
Other comprehensive income (loss):
Qualifying hedges:
Changes in fair value, net of tax of
   $8, $(2), and $(17), respectively
26 (5)(41)
Reclassification adjustment for amounts included in net income,
   net of tax of $(10), $28, and $27, respectively
(33)80 69 
Pension and other postretirement benefit plans:
Benefit plan net gain (loss),
   net of tax of $4, $10, and $(14), respectively
10 23 (39)
Reclassification adjustment for amounts included in net income,
   net of tax of $, $, and $, respectively
 1 1 
Total other comprehensive income (loss)3 99 (10)
Comprehensive loss attributable to noncontrolling interests(170)(141)(127)
Consolidated Comprehensive Income Attributable to Southern Company$4,344 $4,500 $3,966 
The accompanying notes are an integral part of these consolidated financial statements.
 
II-72

    Table of Contents                                Index to Financial Statements
CONSOLIDATED STATEMENTS OF CASH FLOWS
For the Years Ended December 31, 2025, 2024, and 2023
Southern Company and Subsidiary Companies
 202520242023
 (in millions)
Operating Activities:
Consolidated net income$4,171 $4,260 $3,849 
Adjustments to reconcile consolidated net income
   to net cash provided from operating activities —
Depreciation and amortization, total6,030 5,266 4,986 
Deferred income taxes618 626 416 
Allowance for equity funds used during construction(340)(235)(268)
Pension, postretirement, and other employee benefits(579)(556)(527)
Settlement of asset retirement obligations(634)(566)(617)
Storm damage and reliability reserve accruals236 163 124 
Stock based compensation expense136 132 137 
Loss on extinguishment of debt
252   
Retail fuel cost under recovery – long-term(176)(32)(206)
Storm damage cost recovery – long-term(275)(631) 
Other, net(36)(60)(206)
Changes in certain current assets and liabilities —
-Receivables(124)(372)482 
-Retail fuel cost under recovery645 984 686 
-Fossil fuel for generation68 140 (368)
-Materials and supplies(24)(189)(345)
-Natural gas cost under recovery  108 
-Other current assets47 (47)(106)
-Accounts payable(290)492 (863)
-Accrued interest
125 30 42 
-Accrued taxes(36)206 23 
-Customer refunds(75)83 (157)
-Natural gas cost over recovery(36)(21)214 
-Other current liabilities99 115 149 
Net cash provided from operating activities9,802 9,788 7,553 
Investing Activities:
Property additions(12,737)(8,955)(9,095)
Business acquisition(635)  
Nuclear decommissioning trust fund purchases(1,702)(1,551)(1,142)
Nuclear decommissioning trust fund sales1,685 1,535 1,121 
Proceeds from dispositions1 369 164 
Cost of removal, net of salvage(655)(632)(592)
Change in construction payables, net301 106 18 
Payments pursuant to LTSAs(159)(108)(99)
Other investing activities(58)(164)(43)
Net cash used for investing activities(13,959)(9,400)(9,668)
Financing Activities:
Increase (decrease) in notes payable, net(414)(648)973 
Proceeds —
Long-term debt12,470 6,159 8,972 
Short-term borrowings200 700 350 
Common stock1,623 143 36 
Redemptions and repurchases —
Long-term debt(5,464)(2,222)(4,294)
Short-term borrowings (1,020)(1,630)
Distributions to noncontrolling interests(200)(185)(234)
Purchase of membership interests from noncontrolling interests(286)  
Payment of common stock dividends(3,015)(2,954)(3,035)
Other financing activities(218)(181)(139)
Net cash provided from (used for) financing activities4,696 (208)999 
Net Change in Cash, Cash Equivalents, and Restricted Cash539 180 (1,116)
Cash, Cash Equivalents, and Restricted Cash at Beginning of Year1,101 921 2,037 
Cash, Cash Equivalents, and Restricted Cash at End of Year$1,640 $1,101 $921 
Supplemental Cash Flow Information:
Cash paid during the period for —
Interest (net of $140, $103, and $132 capitalized, respectively)
$2,692 $2,538 $2,184 
Income taxes, net (excludes credit transfers)284 176 132 
Noncash transactions —
Accrued property additions at year-end1,473 1,199 1,027 
LTSA credits utilized from the sale of spare parts6 13 23 
Issuance of common stock under dividend reinvestment plan222 179  
The accompanying notes are an integral part of these consolidated financial statements.
II-73

    Table of Contents                                Index to Financial Statements
CONSOLIDATED BALANCE SHEETS
At December 31, 2025 and 2024
Southern Company and Subsidiary Companies
Assets20252024
(in millions)
Current Assets:
Cash and cash equivalents$1,639 $1,070 
Receivables —
Customer accounts2,251 2,228 
Unbilled revenues931 825 
Under recovered fuel clause revenues
316 713 
Other accounts and notes655 597 
Accumulated provision for uncollectible accounts(84)(74)
Materials and supplies2,202 2,178 
Fossil fuel for generation735 803 
Natural gas for sale396 388 
Prepaid expenses327 294 
Assets from risk management activities, net of collateral63 39 
Regulatory assets – asset retirement obligations353 353 
Other regulatory assets709 804 
Other current assets424 476 
Total current assets10,917 10,694 
Property, Plant, and Equipment:
In service146,114 137,143 
Less: Accumulated depreciation43,483 40,126 
Plant in service, net of depreciation102,631 97,017 
Other utility plant, net307 410 
Nuclear fuel, at amortized cost897 873 
Construction work in progress10,534 6,389 
Total property, plant, and equipment114,369 104,689 
Other Property and Investments:
Goodwill5,161 5,161 
Nuclear decommissioning trusts, at fair value2,947 2,621 
Equity investments in unconsolidated subsidiaries1,318 1,416 
Other intangible assets, net of amortization of $444 and $412, respectively
300 332 
Miscellaneous property and investments714 668 
Total other property and investments10,440 10,198 
Deferred Charges and Other Assets:
Operating lease right-of-use assets, net of amortization1,358 1,386 
Deferred charges related to income taxes948 889 
Prepaid pension costs3,257 2,674 
Unamortized loss on reacquired debt187 203 
Deferred under recovered retail fuel clause revenues
252 485 
Regulatory assets – asset retirement obligations, deferred5,129 5,458 
Other regulatory assets, deferred7,427 7,037 
Other deferred charges and assets1,436 1,467 
Total deferred charges and other assets19,994 19,599 
Total Assets$155,720 $145,180 
The accompanying notes are an integral part of these consolidated financial statements.
II-74

    Table of Contents                                Index to Financial Statements
CONSOLIDATED BALANCE SHEETS
At December 31, 2025 and 2024
Southern Company and Subsidiary Companies
Liabilities and Stockholders' Equity20252024
(in millions)
Current Liabilities:
Securities due within one year$6,220 $4,718 
Notes payable722 1,338 
Accounts payable3,710 3,701 
Customer deposits475 486 
Accrued taxes —
Accrued income taxes22 57 
Other accrued taxes982 997 
Accrued interest807 682 
Accrued compensation1,418 1,261 
Asset retirement obligations662 731 
Liabilities from risk management activities, net of collateral118 160 
Operating lease obligations197 200 
Natural gas cost over recovery158 193 
Other regulatory liabilities240 369 
Other current liabilities1,157 1,100 
Total current liabilities16,888 15,993 
Long-Term Debt65,649 58,768 
Deferred Credits and Other Liabilities:
Accumulated deferred income taxes12,133 11,730 
Deferred credits related to income taxes4,712 4,434 
Accumulated deferred ITCs2,002 2,056 
Employee benefit obligations980 1,011 
Operating lease obligations, deferred1,287 1,253 
Asset retirement obligations, deferred8,939 9,203 
Other cost of removal obligations2,036 2,016 
Other regulatory liabilities, deferred722 692 
Other deferred credits and liabilities1,505 1,350 
Total deferred credits and other liabilities34,316 33,745 
Total Liabilities116,853 108,506 
Common Stockholders' Equity:
Common stock, par value $5 per share (Authorized - 1.5 billion shares)
5,554 5,446 
    (Issued - 1.1 billion shares; Treasury - 1.0 million shares)
Paid-in capital15,740 14,149 
Treasury, at cost(59)(59)
Retained earnings14,856 13,750 
Accumulated other comprehensive loss(75)(78)
Total common stockholders' equity36,016 33,208 
Noncontrolling interests2,851 3,466 
Total Stockholders' Equity (See accompanying statements)
38,867 36,674 
Total Liabilities and Stockholders' Equity$155,720 $145,180 
Commitments and Contingent Matters (See notes)
The accompanying notes are an integral part of these consolidated financial statements.
II-75

    Table of Contents                                Index to Financial Statements
CONSOLIDATED STATEMENTS OF STOCKHOLDERS' EQUITY
For the Years Ended December 31, 2025, 2024, and 2023
Southern Company and Subsidiary Companies
Southern Company Common Stockholders' Equity
Number of Common SharesCommon StockAccumulated
Other
Comprehensive Income
(Loss)
Noncontrolling
Interests
 
IssuedTreasuryPar ValuePaid-In CapitalTreasuryRetained EarningsTotal
(in millions)
Balance at December 31, 20221,090 (1)$5,417 $13,673 $(53)$11,538 $(167)$4,124 $34,532 
Consolidated net income (loss)— — — — — 3,976 — (127)3,849 
Other comprehensive income (loss)— — — — — — (10)— (10)
Stock issued2 — 6 30 — — — — 36 
Stock-based compensation— — — 73 — — — — 73 
Cash dividends of $2.7800 per share
— — — — — (3,035)— — (3,035)
Capital contributions from
   noncontrolling interests
— — — — — — — 21 21 
Distributions to
   noncontrolling interests
— — — — — — — (236)(236)
Other— — — (1)(6)3 — (1)(5)
Balance at December 31, 20231,092 (1)5,423 13,775 (59)12,482 (177)3,781 35,225 
Consolidated net income (loss)— — — — — 4,401 — (141)4,260 
Other comprehensive income— — — — — — 99 — 99 
Stock issued6 — 23 299 — — — — 322 
Stock-based compensation— — — 56 — — — — 56 
Dividends of $2.8600 per share
— — — — — (3,133)— — (3,133)
Capital contributions from
   noncontrolling interests
— — — — — — — 11 11 
Distributions to
   noncontrolling interests
— — — — — — — (185)(185)
Other— — — 19 — — — — 19 
Balance at December 31, 20241,098 (1)5,446 14,149 (59)13,750 (78)3,466 36,674 
Consolidated net income (loss)     4,341  (170)4,171 
Other comprehensive income      3  3 
Issuance of equity units(*)
   (173)    (173)
Stock issued22  107 1,738     1,845 
Stock-based compensation   48     48 
Dividends of $2.9400 per share
     (3,237)  (3,237)
Capital contributions from
   noncontrolling interests
       23 23 
Distributions to
   noncontrolling interests
       (202)(202)
Purchase of membership interests
   from noncontrolling interests
   (16)   (267)(283)
Other  1 (6) 2  1 (2)
Balance at December 31, 20251,120 (1)$5,554 $15,740 $(59)$14,856 $(75)$2,851 $38,867 
(*) See Note 8 under "Equity Units" for additional information.
The accompanying notes are an integral part of these consolidated financial statements.
II-76

    Table of Contents                                Index to Financial Statements

REPORT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM
To the stockholder and the Board of Directors of Alabama Power Company
Opinion on the Financial Statements
We have audited the accompanying balance sheets of Alabama Power Company (Alabama Power) (a wholly-owned subsidiary of The Southern Company) as of December 31, 2025 and 2024, the related statements of income, comprehensive income, common stockholder's equity, and cash flows for each of the three years in the period ended December 31, 2025, the related notes, and the financial statement schedule listed in the Index at Item 15 (collectively referred to as the "financial statements"). In our opinion, the financial statements present fairly, in all material respects, the financial position of Alabama Power as of December 31, 2025 and 2024, and the results of its operations and its cash flows for each of the three years in the period ended December 31, 2025, in conformity with accounting principles generally accepted in the United States of America.
Basis for Opinion
These financial statements are the responsibility of Alabama Power's management. Our responsibility is to express an opinion on Alabama Power's financial statements based on our audits. We are a public accounting firm registered with the Public Company Accounting Oversight Board (United States) (PCAOB) and are required to be independent with respect to Alabama Power in accordance with the U.S. federal securities laws and the applicable rules and regulations of the Securities and Exchange Commission and the PCAOB.
We conducted our audits in accordance with the standards of the PCAOB. Those standards require that we plan and perform the audit to obtain reasonable assurance about whether the financial statements are free of material misstatement, whether due to error or fraud. Alabama Power is not required to have, nor were we engaged to perform, an audit of its internal control over financial reporting. As part of our audits, we are required to obtain an understanding of internal control over financial reporting but not for the purpose of expressing an opinion on the effectiveness of Alabama Power's internal control over financial reporting. Accordingly, we express no such opinion.
Our audits included performing procedures to assess the risks of material misstatement of the financial statements, whether due to error or fraud, and performing procedures that respond to those risks. Such procedures included examining, on a test basis, evidence regarding the amounts and disclosures in the financial statements. Our audits also included evaluating the accounting principles used and significant estimates made by management, as well as evaluating the overall presentation of the financial statements. We believe that our audits provide a reasonable basis for our opinion.
Critical Audit Matter
The critical audit matter communicated below is a matter arising from the current-period audit of the financial statements that was communicated or required to be communicated to the Audit Committee of Southern Company's Board of Directors and that (1) relates to accounts or disclosures that are material to the financial statements and (2) involved especially challenging, subjective, or complex judgments. The communication of critical audit matters does not alter in any way our opinion on the financial statements, taken as a whole, and we are not, by communicating the critical audit matter below, providing a separate opinion on the critical audit matter or on the accounts or disclosures to which it relates.
Impact of Rate Regulation on the Financial Statements – Refer to Note 1 (Summary of Significant Accounting Policies – Regulatory Assets and Liabilities) and Note 2 (Regulatory Matters – Alabama Power) to the financial statements
Critical Audit Matter Description
Alabama Power is subject to retail rate regulation by the Alabama Public Service Commission and wholesale regulation by the Federal Energy Regulatory Commission (collectively, the "Commissions"). Management has determined that it meets the requirements under accounting principles generally accepted in the United States of America to utilize specialized rules to account for the effects of rate regulation in the preparation of its financial statements. Accounting for the economics of rate regulation may impact multiple financial statement line items and disclosures.
The Commissions set the rates Alabama Power is permitted to charge customers. Rates are determined and approved in regulatory proceedings based on an analysis of Alabama Power's costs to provide utility service and a return on, and recovery of, its investment in the utility business. Current and future regulatory decisions can have an impact on the recovery of costs, the rate of return earned on investments, and the timing and amount of assets to be recovered through rates. The Commissions' regulation of rates is premised on the full recovery of prudently incurred costs and a reasonable rate of return on invested capital. While Alabama Power expects to recover costs from customers through regulated rates, there is a risk that the Commissions will not approve: (1) full recovery of the costs of providing utility service, or (2) full recovery of all amounts invested in the utility business and a reasonable return on those investments.
II-77

    Table of Contents                                Index to Financial Statements
We identified the impact of rate regulation related to certain assets and liabilities as a critical audit matter due to the significant judgments made by management to support its assertions about impacted account balances and disclosures and/or the high degree of subjectivity involved in assessing the potential impact of future regulatory orders on incurred costs. Management judgments include assessing the likelihood of (1) recovery in future rates of incurred costs, (2) a disallowance of part of the cost of recently completed plant or plant under construction, and/or (3) a refund to customers. Auditing these judgments, which include assumptions about the outcome of future decisions by the Commissions, required specialized knowledge of accounting for rate regulations and the rate setting process due to its inherent complexities.
How the Critical Audit Matter Was Addressed in the Audit
Our audit procedures related to the impact of rate regulation on certain assets and liabilities included the following, among others:
We tested the effectiveness of management's controls over the evaluation of the likelihood of (1) the recovery in future rates of certain incurred costs and (2) refunds or future reductions in rates that should be reported as regulatory liabilities; and the monitoring and evaluation of regulatory developments that may affect the likelihood of recovering certain costs in future rates or of a future reduction in rates. We also tested the effectiveness of management's controls over the initial recognition of certain regulatory assets or liabilities.
We read and evaluated relevant regulatory orders issued and/or other relevant publicly available information to assess the likelihood of recovery of certain incurred costs in future rates or of a future reduction in rates based on precedents of the treatment of similar costs under similar circumstances.
We tested certain incurred costs recorded as regulatory assets or liabilities during the period for completeness and accuracy.
We obtained representation from management regarding the likelihood of recoverability of incurred costs and potential refund or future reduction in rates to assess management's assertions about the likelihood of recovery, refund, or a future reduction in rates.
We evaluated Alabama Power's disclosures related to the impacts of rate regulation, including the balances recorded and regulatory developments, including where there is a high degree of subjectivity involved in assessing the potential impact of future regulatory orders on incurred costs.
/s/ Deloitte & Touche LLP
Birmingham, Alabama
February 18, 2026
We have served as Alabama Power's auditor since 2002.
II-78

    Table of Contents                                Index to Financial Statements
STATEMENTS OF INCOME
For the Years Ended December 31, 2025, 2024, and 2023
Alabama Power Company
 
202520242023
(in millions)
Operating Revenues:
Retail revenues$7,136 $6,639 $6,159 
Wholesale revenues, non-affiliates449 337 424 
Wholesale revenues, affiliates188 139 60 
Other revenues462 439 407 
Total operating revenues8,235 7,554 7,050 
Operating Expenses:
Fuel1,524 1,358 1,299 
Purchased power, non-affiliates235 199 253 
Purchased power, affiliates273 175 251 
Other operations and maintenance2,026 1,895 1,769 
Depreciation and amortization1,510 1,459 1,401 
Taxes other than income taxes498 471 442 
Total operating expenses6,066 5,557 5,415 
Operating Income2,169 1,997 1,635 
Other Income and (Expense):
Allowance for equity funds used during construction69 57 82 
Interest expense, net of amounts capitalized(465)(448)(425)
Other income (expense), net168 157 159 
Total other income and (expense)(228)(234)(184)
Earnings Before Income Taxes1,941 1,763 1,451 
Income taxes425 360 81 
Net Income$1,516 $1,403 $1,370 

STATEMENTS OF COMPREHENSIVE INCOME
For the Years Ended December 31, 2025, 2024, and 2023
Alabama Power Company

202520242023
(in millions)
Net Income$1,516 $1,403 $1,370 
Other comprehensive income:
Qualifying hedges:
Reclassification adjustment for amounts included in net income,
   net of tax of $1, $1, and $1, respectively
2 2 2 
Total other comprehensive income2 2 2 
Comprehensive Income$1,518 $1,405 $1,372 
The accompanying notes are an integral part of these financial statements.
 
II-79

    Table of Contents                                Index to Financial Statements
STATEMENTS OF CASH FLOWS
For the Years Ended December 31, 2025, 2024, and 2023
Alabama Power Company
 202520242023
 (in millions)
Operating Activities:
Net income$1,516 $1,403 $1,370 
Adjustments to reconcile net income
   to net cash provided from operating activities —
Depreciation and amortization, total1,654 1,608 1,554 
Deferred income taxes220 (55)(242)
Allowance for equity funds used during construction(69)(57)(82)
Pension, postretirement, and other employee benefits(211)(213)(204)
Settlement of asset retirement obligations(269)(254)(270)
Natural disaster reserve and reliability reserve accruals179 96 70 
Retail fuel cost under recovery – long-term(146)  
Other, net(55)103 4 
Changes in certain current assets and liabilities —
-Receivables(34)(32)(24)
-Fossil fuel stock36 55 (165)
-Materials and supplies(29)(57)(105)
-Retail fuel cost under recovery 246 376 
-Other current assets18 (32)(20)
-Accounts payable(99)(127)(162)
-Customer refunds(108)87 (39)
-Other current liabilities(31)124 18 
Net cash provided from operating activities2,572 2,895 2,079 
Investing Activities:
Property additions(1,935)(1,881)(2,022)
Business acquisition
(635)  
Nuclear decommissioning trust fund purchases(564)(593)(301)
Nuclear decommissioning trust fund sales564 592 300 
Cost of removal net of salvage(175)(166)(178)
Change in construction payables, net of joint owner portion
(48)10 (44)
Other investing activities(21)51 49 
Net cash used for investing activities(2,814)(1,987)(2,196)
Financing Activities:
Increase (decrease) in notes payable, net (40)40 
Proceeds —
Senior notes1,100  500 
Revenue bonds  326 
Short-term borrowings 50  
Other long-term debt5 8 29 
Redemptions and repurchases —
Senior notes(250) (300)
Revenue bonds (21) 
Short-term borrowings (50) 
Other long-term debt(1)(22) 
Capital contributions from parent company601 527 407 
Payment of common stock dividends(1,219)(1,182)(1,141)
Other financing activities(13)(2)(22)
Net cash provided from (used for) financing activities223 (732)(161)
Net Change in Cash, Cash Equivalents, and Restricted Cash(19)176 (278)
Cash, Cash Equivalents, and Restricted Cash at Beginning of Year585 409 687 
Cash, Cash Equivalents, and Restricted Cash at End of Year$566 $585 $409 
Supplemental Cash Flow Information:
Cash paid during the period for —
Interest (net of $20, $18, and $27 capitalized, respectively)
$431 $428 $397 
Income taxes, net243 387 315 
Noncash transactions — Accrued property additions at year-end100 148 138 
The accompanying notes are an integral part of these financial statements.
II-80

    Table of Contents                                Index to Financial Statements
BALANCE SHEETS
At December 31, 2025 and 2024
Alabama Power Company
Assets20252024
(in millions)
Current Assets:
Cash and cash equivalents$566 $585 
Receivables —
Customer accounts470 512 
Unbilled revenues189 187 
Affiliated126 91 
Other accounts and notes113 126 
Accumulated provision for uncollectible accounts(23)(22)
Fossil fuel stock303 339 
Materials and supplies732 699 
Prepaid expenses86 63 
Other regulatory assets344 332 
Other current assets80 79 
Total current assets2,986 2,991 
Property, Plant, and Equipment:
In service38,915 36,501 
Less: Accumulated provision for depreciation12,816 11,741 
Plant in service, net of depreciation26,099 24,760 
Other utility plant, net307 410 
Nuclear fuel, at amortized cost290 262 
Construction work in progress1,441 1,377 
Total property, plant, and equipment28,137 26,809 
Other Property and Investments:
Nuclear decommissioning trusts, at fair value1,542 1,386 
Equity investments in unconsolidated subsidiaries48 48 
Miscellaneous property and investments123 129 
Total other property and investments1,713 1,563 
Deferred Charges and Other Assets:
Operating lease right-of-use assets, net of amortization86 84 
Deferred charges related to income taxes261 264 
Prepaid pension and other postretirement benefit costs1,016 841 
Regulatory assets – asset retirement obligations1,518 1,780 
Other regulatory assets, deferred1,982 1,815 
Other deferred charges and assets425 391 
Total deferred charges and other assets5,288 5,175 
Total Assets$38,124 $36,538 
The accompanying notes are an integral part of these financial statements.
 

II-81

    Table of Contents                                Index to Financial Statements
BALANCE SHEETS
At December 31, 2025 and 2024
Alabama Power Company
Liabilities and Stockholder's Equity20252024
(in millions)
Current Liabilities:
Securities due within one year$625 $655 
Accounts payable —
Affiliated294 299 
Other576 625 
Customer deposits113 113 
Accrued taxes105 78 
Accrued interest134 120 
Accrued compensation275 240 
Asset retirement obligations256 364 
Other regulatory liabilities89 165 
Other current liabilities135 219 
Total current liabilities2,602 2,878 
Long-Term Debt11,388 10,499 
Deferred Credits and Other Liabilities:
Accumulated deferred income taxes4,209 4,178 
Deferred credits related to income taxes1,585 1,398 
Accumulated deferred ITCs115 113 
Employee benefit obligations152 148 
Operating lease obligations78 76 
Asset retirement obligations, deferred3,423 3,694 
Other regulatory liabilities, deferred252 271 
Other deferred credits and liabilities326 195 
Total deferred credits and other liabilities10,140 10,073 
Total Liabilities24,130 23,450 
Common Stockholder's Equity:
Common stock, par value $40 per share
    (Authorized - 40 million shares; Outstanding - 31 million shares)
1,222 1,222 
Paid-in capital8,263 7,657 
Retained earnings4,512 4,214 
Accumulated other comprehensive loss(3)(5)
Total common stockholder's equity (See accompanying statements)
13,994 13,088 
Total Liabilities and Stockholder's Equity$38,124 $36,538 
Commitments and Contingent Matters (See notes)
The accompanying notes are an integral part of these financial statements.
II-82

    Table of Contents                                Index to Financial Statements
STATEMENTS OF COMMON STOCKHOLDER'S EQUITY
For the Years Ended December 31, 2025, 2024, and 2023
Alabama Power Company

Number of
Common
Shares
Issued
Common
Stock
Paid-In
Capital
Retained
Earnings
Accumulated
Other
Comprehensive
Income (Loss)
Total
(in millions)
Balance at December 31, 202231 $1,222 $6,710 $3,764 $(9)$11,687 
Net income— — — 1,370 — 1,370 
Capital contributions from parent company— — 415 — — 415 
Other comprehensive income— — — — 2 2 
Cash dividends on common stock— — — (1,141)— (1,141)
Balance at December 31, 202331 1,222 7,125 3,993 (7)12,333 
Net income— — — 1,403 — 1,403 
Capital contributions from parent company— — 532 — — 532 
Other comprehensive income— — — — 2 2 
Cash dividends on common stock— — — (1,182)— (1,182)
Balance at December 31, 202431 1,222 7,657 4,214 (5)13,088 
Net income   1,516  1,516 
Capital contributions from parent company  606   606 
Other comprehensive income    2 2 
Cash dividends on common stock   (1,219) (1,219)
Other   1  1 
Balance at December 31, 202531 $1,222 $8,263 $4,512 $(3)$13,994 
The accompanying notes are an integral part of these financial statements.

II-83

    Table of Contents                                Index to Financial Statements

REPORT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM
To the stockholder and the Board of Directors of Georgia Power Company
Opinion on the Financial Statements
We have audited the accompanying balance sheets of Georgia Power Company (Georgia Power) (a wholly-owned subsidiary of The Southern Company) as of December 31, 2025 and 2024, the related statements of income, comprehensive income, common stockholder's equity, and cash flows for each of the three years in the period ended December 31, 2025, the related notes, and the financial statement schedule listed in the Index at Item 15 (collectively referred to as the "financial statements"). In our opinion, the financial statements present fairly, in all material respects, the financial position of Georgia Power as of December 31, 2025 and 2024, and the results of its operations and its cash flows for each of the three years in the period ended December 31, 2025, in conformity with accounting principles generally accepted in the United States of America.
Basis for Opinion
These financial statements are the responsibility of Georgia Power's management. Our responsibility is to express an opinion on Georgia Power's financial statements based on our audits. We are a public accounting firm registered with the Public Company Accounting Oversight Board (United States) (PCAOB) and are required to be independent with respect to Georgia Power in accordance with the U.S. federal securities laws and the applicable rules and regulations of the Securities and Exchange Commission and the PCAOB.
We conducted our audits in accordance with the standards of the PCAOB. Those standards require that we plan and perform the audit to obtain reasonable assurance about whether the financial statements are free of material misstatement, whether due to error or fraud. Georgia Power is not required to have, nor were we engaged to perform, an audit of its internal control over financial reporting. As part of our audits, we are required to obtain an understanding of internal control over financial reporting but not for the purpose of expressing an opinion on the effectiveness of Georgia Power's internal control over financial reporting. Accordingly, we express no such opinion.
Our audits included performing procedures to assess the risks of material misstatement of the financial statements, whether due to error or fraud, and performing procedures that respond to those risks. Such procedures included examining, on a test basis, evidence regarding the amounts and disclosures in the financial statements. Our audits also included evaluating the accounting principles used and significant estimates made by management, as well as evaluating the overall presentation of the financial statements. We believe that our audits provide a reasonable basis for our opinion.
Critical Audit Matter
The critical audit matter communicated below is a matter arising from the current-period audit of the financial statements that was communicated or required to be communicated to the Audit Committee of Southern Company's Board of Directors and that (1) relates to accounts or disclosures that are material to the financial statements and (2) involved especially challenging, subjective, or complex judgments. The communication of critical audit matters does not alter in any way our opinion on the financial statements, taken as a whole, and we are not, by communicating the critical audit matter below, providing a separate opinion on the critical audit matter or on the accounts or disclosures to which it relates.
Impact of Rate Regulation on the Financial Statements – Refer to Note 1 (Summary of Significant Accounting Policies – Regulatory Assets and Liabilities) and Note 2 (Regulatory Matters – Georgia Power) to the financial statements
Critical Audit Matter Description
Georgia Power is subject to retail rate regulation by the Georgia Public Service Commission and wholesale regulation by the Federal Energy Regulatory Commission (collectively, the "Commissions"). Management has determined that it meets the requirements under accounting principles generally accepted in the United States of America to utilize specialized rules to account for the effects of rate regulation in the preparation of its financial statements. Accounting for the economics of rate regulation may impact multiple financial statement line items and disclosures.
The Commissions set the rates Georgia Power is permitted to charge customers. Rates are determined and approved in regulatory proceedings based on an analysis of Georgia Power's costs to provide utility service and a return on, and recovery of, its investment in the utility business. Current and future regulatory decisions can have an impact on the recovery of costs, the rate of return earned on investments, and the timing and amount of assets to be recovered through rates. The Commissions' regulation of rates is premised on the full recovery of prudently incurred costs and a reasonable rate of return on invested capital. While Georgia Power expects to recover costs from customers through regulated rates, there is a risk that the Commissions will not approve: (1) full recovery of the costs of providing utility service, or (2) full recovery of all amounts invested in the utility business and a reasonable return on those investments.
II-84

    Table of Contents                                Index to Financial Statements
We identified the impact of rate regulation related to certain assets and liabilities as a critical audit matter due to the significant judgments made by management to support its assertions about impacted account balances and disclosures and/or the high degree of subjectivity involved in assessing the potential impact of future regulatory orders on incurred costs. Management judgments include assessing the likelihood of (1) recovery in future rates of incurred costs, (2) a disallowance of part of the cost of recently completed plant or plant under construction, and/or (3) a refund to customers. Auditing these judgments, which include assumptions about the outcome of future decisions by the Commissions, required specialized knowledge of accounting for rate regulations and the rate setting process due to its inherent complexities.
How the Critical Audit Matter Was Addressed in the Audit
Our audit procedures related to the impact of rate regulation on certain assets and liabilities included the following, among others:
We tested the effectiveness of management's controls over the evaluation of the likelihood of (1) the recovery in future rates of certain incurred costs and (2) refunds or future reductions in rates that should be reported as regulatory liabilities; and the monitoring and evaluation of regulatory developments that may affect the likelihood of recovering certain costs in future rates or of a future reduction in rates. We also tested the effectiveness of management's controls over the initial recognition of certain regulatory assets or liabilities.
We read and evaluated relevant regulatory orders issued and/or other relevant publicly available information to assess the likelihood of recovery of certain incurred costs in future rates or of a future reduction in rates based on precedents of the treatment of similar costs under similar circumstances.
We tested certain incurred costs recorded as regulatory assets or liabilities during the period for completeness and accuracy.
We obtained representation from management regarding the likelihood of recoverability of incurred costs and potential refund or future reduction in rates to assess management's assertions about the likelihood of recovery, refund, or a future reduction in rates.
We evaluated Georgia Power's disclosures related to the impacts of rate regulation, including the balances recorded and regulatory developments, including where there is a high degree of subjectivity involved in assessing the potential impact of future regulatory orders on incurred costs.
/s/ Deloitte & Touche LLP
Atlanta, Georgia
February 18, 2026
We have served as Georgia Power's auditor since 2002.
II-85

    Table of Contents                                Index to Financial Statements
STATEMENTS OF INCOME
For the Years Ended December 31, 2025, 2024, and 2023
Georgia Power Company
 
202520242023
(in millions)
Operating Revenues:
Retail revenues$11,110 $10,187 $9,222 
Wholesale revenues525 265 188 
Other revenues996 879 708 
Total operating revenues12,631 11,331 10,118 
Operating Expenses:
Fuel2,040 1,658 1,781 
Purchased power, non-affiliates659 615 517 
Purchased power, affiliates858 745 764 
Other operations and maintenance2,585 2,351 2,015 
Depreciation and amortization2,074 1,774 1,681 
Taxes other than income taxes576 647 541 
Total operating expenses8,792 7,790 7,299 
Operating Income3,839 3,541 2,819 
Other Income and (Expense):
Allowance for equity funds used during construction248 152 165 
Interest expense, net of amounts capitalized(793)(725)(626)
Other income (expense), net159 178 170 
Total other income and (expense)(386)(395)(291)
Earnings Before Income Taxes3,453 3,146 2,528 
Income taxes602 603 448 
Net Income$2,851 $2,543 $2,080 
STATEMENTS OF COMPREHENSIVE INCOME
For the Years Ended December 31, 2025, 2024, and 2023
Georgia Power Company
202520242023
(in millions)
Net Income$2,851 $2,543 $2,080 
Other comprehensive income:
Qualifying hedges:
Changes in fair value, net of tax of $1, $6, and $(1), respectively
3 18 (2)
Reclassification adjustment for amounts included in net income,
   net of tax of $, $1, and $2, respectively
1 4 5 
Total other comprehensive income4 22 3 
Comprehensive Income$2,855 $2,565 $2,083 
The accompanying notes are an integral part of these financial statements.
 
II-86

    Table of Contents                                Index to Financial Statements
STATEMENTS OF CASH FLOWS
For the Years Ended December 31, 2025, 2024, and 2023
Georgia Power Company
 202520242023
 (in millions)
Operating Activities:
Net income$2,851 $2,543 $2,080 
Adjustments to reconcile net income
   to net cash provided from operating activities —
Depreciation and amortization, total2,376 2,080 1,914 
Deferred income taxes493 380 206 
Allowance for equity funds used during construction(248)(152)(165)
Pension, postretirement, and other employee benefits(289)(288)(272)
Settlement of asset retirement obligations(321)(270)(304)
Retail fuel cost under recovery – long-term
  (157)
Storm damage cost recovery – long-term(275)(631) 
Other, net(95)(145)(141)
Changes in certain current assets and liabilities —
-Receivables33 (268)(57)
-Retail fuel cost under recovery645 738 308 
-Fossil fuel stock22 96 (189)
-Materials and supplies(32)(81)(154)
-Other current assets(58)(51)(63)
-Accounts payable(347)633 (206)
-Accrued taxes(125)212 74 
-Customer refunds33 (4)(117)
-Other current liabilities145 1 (5)
Net cash provided from operating activities4,808 4,793 2,752 
Investing Activities:
Property additions(7,792)(4,816)(4,786)
Nuclear decommissioning trust fund purchases(1,137)(958)(841)
Nuclear decommissioning trust fund sales1,122 942 821 
Cost of removal, net of salvage(324)(336)(279)
Change in construction payables, net of joint owner portion358 68 50 
Payments pursuant to LTSAs(62)(74)(49)
Proceeds from dispositions 357 59 
Other investing activities(98)(79)(54)
Net cash used for investing activities(7,933)(4,896)(5,079)
Financing Activities:
Increase (decrease) in notes payable, net160 (811)811 
Proceeds —
Senior notes3,100 2,117 2,450 
Short-term borrowings200 350 350 
Revenue bonds  229 
Redemptions and repurchases —
Senior notes(700)(400)(800)
Short-term borrowings (670)(1,430)
FFB loan(86)(86)(86)
Revenue bonds(45)  
Capital contributions from parent company2,700 1,780 2,291 
Payment of common stock dividends(2,209)(2,051)(1,855)
Other financing activities(54)(83)(38)
Net cash provided from financing activities3,066 146 1,922 
Net Change in Cash, Cash Equivalents, and Restricted Cash(59)43 (405)
Cash, Cash Equivalents, and Restricted Cash at Beginning of Year118 75 480 
Cash, Cash Equivalents, and Restricted Cash at End of Year$59 $118 $75 
Supplemental Cash Flow Information:
Cash paid (received) during the period for —
Interest (net of $78, $57, and $86 capitalized, respectively)
$717 $680 $592 
Income taxes, net (excludes credit transfers)129 (14)220 
Noncash transactions — Accrued property additions at year-end1,072 739 680 
The accompanying notes are an integral part of these financial statements.
II-87

    Table of Contents                                Index to Financial Statements
BALANCE SHEETS
At December 31, 2025 and 2024
Georgia Power Company
 
Assets20252024
(in millions)
Current Assets:
Cash and cash equivalents$59 $97 
Receivables —
Customer accounts, net993 985 
Unbilled revenues346 341 
Under recovered retail fuel clause revenues
310 713 
Joint owner accounts195 101 
Affiliated96 65 
Other accounts and notes61 92 
Fossil fuel stock362 385 
Materials and supplies994 968 
Regulatory assets – asset retirement obligations222 222 
Other regulatory assets335 373 
Other current assets285 262 
Total current assets4,258 4,604 
Property, Plant, and Equipment:
In service59,458 55,036 
Less: Accumulated provision for depreciation15,957 14,806 
Plant in service, net of depreciation43,501 40,230 
Nuclear fuel, at amortized cost606 611 
Construction work in progress6,764 3,197 
Total property, plant, and equipment50,871 44,038 
Other Property and Investments:
Nuclear decommissioning trusts, at fair value1,405 1,236 
Equity investments in unconsolidated subsidiaries40 43 
Miscellaneous property and investments231 192 
Total other property and investments1,676 1,471 
Deferred Charges and Other Assets:
Operating lease right-of-use assets, net of amortization1,120 1,331 
Deferred charges related to income taxes660 596 
Prepaid pension costs1,099 897 
Deferred under recovered retail fuel clause revenues
212 453 
Regulatory assets – asset retirement obligations, deferred3,382 3,436 
Other regulatory assets, deferred4,032 3,814 
Other deferred charges and assets767 615 
Total deferred charges and other assets11,272 11,142 
Total Assets$68,077 $61,255 
The accompanying notes are an integral part of these financial statements.

II-88

    Table of Contents                                Index to Financial Statements
BALANCE SHEETS
At December 31, 2025 and 2024
Georgia Power Company
 
Liabilities and Stockholder's Equity20252024
(in millions)
Current Liabilities:
Securities due within one year$1,370 $966 
Notes payable160 200 
Accounts payable —
Affiliated992 984 
Other1,728 1,837 
Customer deposits267 256 
Accrued taxes678 803 
Accrued interest234 190 
Accrued compensation327 276 
Operating lease obligations170 169 
Asset retirement obligations360 309 
Other regulatory liabilities52 150 
Other current liabilities332 296 
Total current liabilities6,670 6,436 
Long-Term Debt20,122 17,384 
Deferred Credits and Other Liabilities:
Accumulated deferred income taxes4,811 4,385 
Deferred credits related to income taxes2,225 2,047 
Accumulated deferred ITCs354 343 
Employee benefit obligations189 205 
Operating lease obligations, deferred960 1,159 
Asset retirement obligations, deferred5,167 5,106 
Other deferred credits and liabilities545 509 
Total deferred credits and other liabilities14,251 13,754 
Total Liabilities41,043 37,574 
Common Stockholder's Equity:
Common stock, without par value
    (Authorized - 20 million shares; Outstanding - 9 million shares)
398 398 
Paid-in capital22,416 19,708 
Retained earnings4,204 3,562 
Accumulated other comprehensive income16 13 
Total common stockholder's equity (See accompanying statements)
27,034 23,681 
Total Liabilities and Stockholder's Equity$68,077 $61,255 
Commitments and Contingent Matters (See notes)
The accompanying notes are an integral part of these financial statements.
 
II-89

    Table of Contents                                Index to Financial Statements
STATEMENTS OF COMMON STOCKHOLDER'S EQUITY
For the Years Ended December 31, 2025, 2024, and 2023
Georgia Power Company
 
Number of Common Shares IssuedCommon StockPaid-In CapitalRetained EarningsAccumulated Other Comprehensive Income (Loss)Total
(in millions)
Balance at December 31, 20229 $398 $15,626 $2,846 $(12)$18,858 
Net income— — — 2,080 — 2,080 
Capital contributions from parent company— — 2,297 — — 2,297 
Other comprehensive income— — — — 3 3 
Cash dividends on common stock— — — (1,855)— (1,855)
Balance at December 31, 20239 398 17,923 3,071 (9)21,383 
Net income— — — 2,543 — 2,543 
Capital contributions from parent company— — 1,785 — — 1,785 
Other comprehensive income— — — — 22 22 
Cash dividends on common stock— — — (2,051)— (2,051)
Other— — — (1) (1)
Balance at December 31, 20249 398 19,708 3,562 13 23,681 
Net income   2,851  2,851 
Capital contributions from parent company  2,708   2,708 
Other comprehensive income    4 4 
Cash dividends on common stock   (2,209) (2,209)
Other    (1)(1)
Balance at December 31, 20259 $398 $22,416 $4,204 $16 $27,034 
The accompanying notes are an integral part of these financial statements.
 
II-90

    Table of Contents                                Index to Financial Statements

REPORT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM
To the stockholder and the Board of Directors of Mississippi Power Company
Opinion on the Financial Statements
We have audited the accompanying balance sheets of Mississippi Power Company (Mississippi Power) (a wholly-owned subsidiary of The Southern Company) as of December 31, 2025 and 2024, the related statements of income, comprehensive income, common stockholder's equity, and cash flows for each of the three years in the period ended December 31, 2025, the related notes, and the financial statement schedule listed in the Index at Item 15 (collectively referred to as the "financial statements"). In our opinion, the financial statements present fairly, in all material respects, the financial position of Mississippi Power as of December 31, 2025 and 2024, and the results of its operations and its cash flows for each of the three years in the period ended December 31, 2025, in conformity with accounting principles generally accepted in the United States of America.
Basis for Opinion
These financial statements are the responsibility of Mississippi Power's management. Our responsibility is to express an opinion on Mississippi Power's financial statements based on our audits. We are a public accounting firm registered with the Public Company Accounting Oversight Board (United States) (PCAOB) and are required to be independent with respect to Mississippi Power in accordance with the U.S. federal securities laws and the applicable rules and regulations of the Securities and Exchange Commission and the PCAOB.
We conducted our audits in accordance with the standards of the PCAOB. Those standards require that we plan and perform the audit to obtain reasonable assurance about whether the financial statements are free of material misstatement, whether due to error or fraud. Mississippi Power is not required to have, nor were we engaged to perform, an audit of its internal control over financial reporting. As part of our audits, we are required to obtain an understanding of internal control over financial reporting but not for the purpose of expressing an opinion on the effectiveness of Mississippi Power's internal control over financial reporting. Accordingly, we express no such opinion.
Our audits included performing procedures to assess the risks of material misstatement of the financial statements, whether due to error or fraud, and performing procedures that respond to those risks. Such procedures included examining, on a test basis, evidence regarding the amounts and disclosures in the financial statements. Our audits also included evaluating the accounting principles used and significant estimates made by management, as well as evaluating the overall presentation of the financial statements. We believe that our audits provide a reasonable basis for our opinion.
Critical Audit Matter
The critical audit matter communicated below is a matter arising from the current-period audit of the financial statements that was communicated or required to be communicated to the Audit Committee of Southern Company's Board of Directors and that (1) relates to accounts or disclosures that are material to the financial statements and (2) involved especially challenging, subjective, or complex judgments. The communication of critical audit matters does not alter in any way our opinion on the financial statements, taken as a whole, and we are not, by communicating the critical audit matter below, providing a separate opinion on the critical audit matter or on the accounts or disclosures to which it relates.
Impact of Rate Regulation on the Financial Statements – Refer to Note 1 (Summary of Significant Accounting Policies – Regulatory Assets and Liabilities) and Note 2 (Regulatory Matters – Mississippi Power) to the financial statements
Critical Audit Matter Description
Mississippi Power is subject to retail rate regulation by the Mississippi Public Service Commission and wholesale regulation by the Federal Energy Regulatory Commission (collectively, the "Commissions"). Management has determined that it meets the requirements under accounting principles generally accepted in the United States of America to utilize specialized rules to account for the effects of rate regulation in the preparation of its financial statements. Accounting for the economics of rate regulation may impact multiple financial statement line items and disclosures.
The Commissions set the rates Mississippi Power is permitted to charge customers. Rates are determined and approved in regulatory proceedings based on an analysis of Mississippi Power's costs to provide utility service and a return on, and recovery of, its investment in the utility business. Current and future regulatory decisions can have an impact on the recovery of costs, the rate of return earned on investments, and the timing and amount of assets to be recovered through rates. The Commissions' regulation of rates is premised on the full recovery of prudently incurred costs and a reasonable rate of return on invested capital. While Mississippi Power expects to recover costs from customers through regulated rates, there is a risk that the Commissions will not approve: (1) full recovery of the costs of providing utility service, or (2) full recovery of all amounts invested in the utility business and a reasonable return on those investments.
II-91

    Table of Contents                                Index to Financial Statements
We identified the impact of rate regulation related to certain assets and liabilities as a critical audit matter due to the significant judgments made by management to support its assertions about impacted account balances and disclosures and/or the high degree of subjectivity involved in assessing the potential impact of future regulatory orders on incurred costs. Management judgments include assessing the likelihood of (1) recovery in future rates of incurred costs, (2) a disallowance of part of the cost of recently completed plant or plant under construction, and/or (3) a refund to customers. Auditing these judgments, which include assumptions about the outcome of future decisions by the Commissions, required specialized knowledge of accounting for rate regulations and the rate setting process due to its inherent complexities.
How the Critical Audit Matter Was Addressed in the Audit
Our audit procedures related to the impact of rate regulation on certain assets and liabilities included the following, among others:
We tested the effectiveness of management's controls over the evaluation of the likelihood of (1) the recovery in future rates of certain incurred costs and (2) refunds or future reductions in rates that should be reported as regulatory liabilities; and the monitoring and evaluation of regulatory developments that may affect the likelihood of recovering certain costs in future rates or of a future reduction in rates. We also tested the effectiveness of management's controls over the initial recognition of certain regulatory assets or liabilities.
We read and evaluated relevant regulatory orders issued and/or other relevant publicly available information to assess the likelihood of recovery of certain incurred costs in future rates or of a future reduction in rates based on precedents of the treatment of similar costs under similar circumstances.
We tested certain incurred costs recorded as regulatory assets or liabilities during the period for completeness and accuracy.
We obtained representation from management regarding the likelihood of recoverability of incurred costs and potential refund or future reduction in rates to assess management's assertions about the likelihood of recovery, refund, or a future reduction in rates.
We evaluated Mississippi Power's disclosures related to the impacts of rate regulation, including the balances recorded and regulatory developments, including where there is a high degree of subjectivity involved in assessing the potential impact of future regulatory orders on incurred costs.
/s/ Deloitte & Touche LLP
Atlanta, Georgia
February 18, 2026
We have served as Mississippi Power's auditor since 2002.
II-92

    Table of Contents                                Index to Financial Statements
STATEMENTS OF INCOME
For the Years Ended December 31, 2025, 2024, and 2023
Mississippi Power Company

202520242023
(in millions)
Operating Revenues:
Retail revenues$1,085 $965 $963 
Wholesale revenues, non-affiliates275 228 272 
Wholesale revenues, affiliates280 218 200 
Other revenues55 52 39 
Total operating revenues1,695 1,463 1,474 
Operating Expenses:
Fuel and purchased power624 477 538 
Other operations and maintenance387 370 362 
Depreciation and amortization211 193 190 
Taxes other than income taxes139 127 124 
Total operating expenses1,361 1,167 1,214 
Operating Income334 296 260 
Other Income and (Expense):
Interest expense, net of amounts capitalized(79)(77)(71)
Other income (expense), net25 27 35 
Total other income and (expense)(54)(50)(36)
Earnings Before Income Taxes280 246 224 
Income taxes65 47 36 
Net Income$215 $199 $188 
STATEMENTS OF COMPREHENSIVE INCOME
For the Years Ended December 31, 2025, 2024, and 2023
Mississippi Power Company

202520242023
(in millions)
Net Income$215 $199 $188 
Other comprehensive income (loss):
Qualifying hedges:
Changes in fair value, net of tax of $, $2, and $, respectively
(1)5  
Total other comprehensive income (loss)(1)5  
Comprehensive Income$214 $204 $188 
The accompanying notes are an integral part of these financial statements.

II-93

    Table of Contents                                Index to Financial Statements
STATEMENTS OF CASH FLOWS
For the Years Ended December 31, 2025, 2024, and 2023
Mississippi Power Company
 202520242023
 (in millions)
Operating Activities:
Net income$215 $199 $188 
Adjustments to reconcile net income
   to net cash provided from operating activities —
Depreciation and amortization, total230 209 232 
Deferred income taxes9 16 (13)
Pension, postretirement, and other employee benefits(20)(21)(20)
Settlement of asset retirement obligations(19)(17)(18)
Property damage reserve and reliability reserve accruals26 35 23 
Retail fuel cost under recovery – long-term(30)(32)(50)
Plant acquisition regulatory liability
36   
Other, net(12)5 (5)
Changes in certain current assets and liabilities —
-Receivables(3)(14)85 
-Fossil fuel stock10 (9)(3)
-Materials and supplies(2)(13)(9)
-Prepaid income taxes11 (11) 
-Other current assets(1)(1)10 
-Accounts payable(13)(10)(81)
-Retail fuel cost over recovery(10)55 27 
-Wholesale fuel cost over recovery
(20)15 5 
-Other current liabilities7  (2)
Net cash provided from operating activities414 406 369 
Investing Activities:
Property additions(328)(311)(319)
Contributions in aid of construction
58   
Cost of removal net of salvage(55)(41)(32)
Change in construction payables, net
(4) 9 
Payments pursuant to LTSAs(20)(19)(26)
Other investing activities(7)(2)(2)
Net cash used for investing activities(356)(373)(370)
Financing Activities:
Increase (decrease) in notes payable, net(14)14  
Proceeds — Senior notes
100 250 100 
Redemptions —
Senior notes
 (200) 
Revenue bonds(11)  
Capital contributions from parent company77 68 68 
Payment of common stock dividends(194)(188)(185)
Other financing activities(3)(2)(3)
Net cash used for financing activities(45)(58)(20)
Net Change in Cash, Cash Equivalents, and Restricted Cash13 (25)(21)
Cash, Cash Equivalents, and Restricted Cash at Beginning of Year13 38 59 
Cash, Cash Equivalents, and Restricted Cash at End of Year$26 $13 $38 
Supplemental Cash Flow Information:
Cash paid during the period for —
Interest$76 $74 $66 
Income taxes, net42 51 52 
Noncash transactions — Accrued property additions at year-end38 36 34 
The accompanying notes are an integral part of these financial statements. 
II-94

    Table of Contents                                Index to Financial Statements
BALANCE SHEETS
At December 31, 2025 and 2024
Mississippi Power Company

Assets20252024
(in millions)
Current Assets:
Cash and cash equivalents$26 $13 
Receivables —
Customer accounts, net50 45 
Unbilled revenues44 39 
Affiliated26 33 
Other accounts and notes22 24 
Fossil fuel stock46 56 
Materials and supplies101 103 
Other regulatory assets49 43 
Other current assets10 28 
Total current assets374 384 
Property, Plant, and Equipment:
In service5,972 5,697 
Less: Accumulated provision for depreciation1,922 1,833 
Plant in service, net of depreciation4,050 3,864 
Construction work in progress238 253 
Total property, plant, and equipment4,288 4,117 
Other Property and Investments143 152 
Deferred Charges and Other Assets:
Deferred charges related to income taxes25 27 
Prepaid pension costs151 124 
Deferred under recovered retail fuel clause revenues
40 32 
Regulatory assets – asset retirement obligations229 243 
Other regulatory assets, deferred255 259 
Accumulated deferred income taxes66 82 
Other deferred charges and assets66 74 
Total deferred charges and other assets832 841 
Total Assets$5,637 $5,494 
The accompanying notes are an integral part of these financial statements.

II-95

    Table of Contents                                Index to Financial Statements
BALANCE SHEETS
At December 31, 2025 and 2024
Mississippi Power Company

Liabilities and Stockholder's Equity20252024
(in millions)
Current Liabilities:
Securities due within one year$66 $12 
Notes payable 14 
Accounts payable —
Affiliated70 68 
Other77 83 
Accrued taxes125 115 
Accrued compensation49 46 
Asset retirement obligations21 32 
Over recovered retail fuel clause revenues
 32 
Other regulatory liabilities20 5 
Other current liabilities92 95 
Total current liabilities520 502 
Long-Term Debt1,720 1,681 
Deferred Credits and Other Liabilities:
Accumulated deferred income taxes491 492 
Deferred credits related to income taxes211 219 
Employee benefit obligations67 65 
Asset retirement obligations, deferred103 116 
Other cost of removal obligations115 170 
Other regulatory liabilities, deferred141 121 
Other deferred credits and liabilities80 39 
Total deferred credits and other liabilities1,208 1,222 
Total Liabilities3,448 3,405 
Common Stockholder's Equity:
Common stock, without par value
    (Authorized - 50 million shares; Outstanding - 1 million shares)
38 38 
Paid-in capital4,871 4,791 
Accumulated deficit(2,724)(2,745)
Accumulated other comprehensive income4 5 
Total common stockholder's equity (See accompanying statements)
2,189 2,089 
Total Liabilities and Stockholder's Equity$5,637 $5,494 
Commitments and Contingent Matters (See notes)
The accompanying notes are an integral part of these financial statements.
 
II-96

    Table of Contents                                Index to Financial Statements
STATEMENTS OF COMMON STOCKHOLDER'S EQUITY
For the Years Ended December 31, 2025, 2024, and 2023
Mississippi Power Company

Number of Common Shares IssuedCommon
Stock
Paid-In CapitalRetained Earnings (Accumulated Deficit)Accumulated Other Comprehensive Income (Loss)Total
(in millions)
Balance at December 31, 20221 $38 $4,652 $(2,759)$ $1,931 
Net income— — — 188 — 188 
Capital contributions from parent company— — 69 — — 69 
Cash dividends on common stock— — — (185)— (185)
Balance at December 31, 20231 38 4,721 (2,756) 2,003 
Net income— — — 199 — 199 
Capital contributions from parent company— — 70 — — 70 
Other comprehensive income— — — — 5 5 
Cash dividends on common stock— — — (188)— (188)
Balance at December 31, 20241 38 4,791 (2,745)5 2,089 
Net income   215  215 
Capital contributions from parent company  80   80 
Other comprehensive income (loss)    (1)(1)
Cash dividends on common stock   (194) (194)
Balance at December 31, 20251 $38 $4,871 $(2,724)$4 $2,189 
The accompanying notes are an integral part of these financial statements.
II-97

    Table of Contents                                Index to Financial Statements

REPORT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM
To the stockholder and the Board of Directors of Southern Power Company and Subsidiary Companies
Opinion on the Financial Statements
We have audited the accompanying consolidated balance sheets of Southern Power Company and subsidiary companies (Southern Power) (a wholly-owned subsidiary of The Southern Company) as of December 31, 2025 and 2024, the related consolidated statements of income, comprehensive income, stockholders' equity, and cash flows for each of the three years in the period ended December 31, 2025, the related notes, and the financial statement schedule listed in the Index at Item 15 (collectively referred to as the "financial statements"). In our opinion, the financial statements present fairly, in all material respects, the financial position of Southern Power as of December 31, 2025 and 2024, and the results of its operations and its cash flows for each of the three years in the period ended December 31, 2025, in conformity with accounting principles generally accepted in the United States of America.
Basis for Opinion
These financial statements are the responsibility of Southern Power's management. Our responsibility is to express an opinion on Southern Power's financial statements based on our audits. We are a public accounting firm registered with the Public Company Accounting Oversight Board (United States) (PCAOB) and are required to be independent with respect to Southern Power in accordance with the U.S. federal securities laws and the applicable rules and regulations of the Securities and Exchange Commission and the PCAOB.
We conducted our audits in accordance with the standards of the PCAOB. Those standards require that we plan and perform the audit to obtain reasonable assurance about whether the financial statements are free of material misstatement, whether due to error or fraud. Southern Power is not required to have, nor were we engaged to perform, an audit of its internal control over financial reporting. As part of our audits, we are required to obtain an understanding of internal control over financial reporting but not for the purpose of expressing an opinion on the effectiveness of Southern Power's internal control over financial reporting. Accordingly, we express no such opinion.
Our audits included performing procedures to assess the risks of material misstatement of the financial statements, whether due to error or fraud, and performing procedures that respond to those risks. Such procedures included examining, on a test basis, evidence regarding the amounts and disclosures in the financial statements. Our audits also included evaluating the accounting principles used and significant estimates made by management, as well as evaluating the overall presentation of the financial statements. We believe that our audits provide a reasonable basis for our opinion.
Critical Audit Matter
The critical audit matter communicated below is a matter arising from the current-period audit of the financial statements that was communicated or required to be communicated to the Audit Committee of Southern Company's Board of Directors and that (1) relates to accounts or disclosures that are material to the financial statements and (2) involved especially challenging, subjective, or complex judgments. The communication of critical audit matters does not alter in any way our opinion on the financial statements, taken as a whole, and we are not, by communicating the critical audit matter below, providing a separate opinion on the critical audit matter or on the accounts or disclosures to which it relates.
Income/Loss Allocation to Noncontrolling Interests – Refer to Note 1 (Summary of Significant Accounting Policies – Variable Interest Entities) and Note 7 (Consolidated Entities and Equity Method Investments – Southern Power – Variable Interest Entities) to the financial statements
Critical Audit Matter Description
Southern Power has entered into a number of tax equity partnership arrangements, wherein they agree to sell 100% of a class of membership interests (e.g. Class A) in an entity to a noncontrolling investor in exchange for cash contributions, while retaining control of the entity through a separate class of membership interests (e.g. Class B). The agreements for these partnerships give different rights and priorities to their owners in terms of cash distributions, tax attribute allocations, and partnership income or loss allocations. These provisions make the conventional equity method of accounting where an investor applies its "percentage ownership interest" to the investee's net income under generally accepted accounting principles to determine the investor's share of earnings or losses difficult to apply. Therefore, Southern Power uses the Hypothetical Liquidation at Book Value (HLBV) accounting method to account for these partnership arrangements. The HLBV accounting method calculates each partner's share of income or loss based on the change in net equity the partner can legally claim at the end of the reporting period compared to the beginning of the reporting period. The application of the HLBV accounting method by Southern Power required significant consideration of the allocations between Southern Power and the noncontrolling investors over the life of the agreement and the liquidation provisions of the agreement to determine the appropriate allocation of income or loss between the parties.
II-98

    Table of Contents                                Index to Financial Statements
The determination of the appropriate amount of allocated partnership income or loss to noncontrolling interests using the HLBV accounting method required increased audit effort and specialized skill and knowledge, including evaluation of the terms of the agreement and consideration of the appropriateness of the HLBV model based on the provisions of the agreement.
How the Critical Audit Matter Was Addressed in the Audit
Our audit procedures included the following, among others:
We read certain agreements to understand the liquidation provisions and the provisions governing the allocation of benefits.
We evaluated certain HLBV models utilized by management to determine whether the models accurately reflect the allocation of income or loss and tax attributes in accordance with the liquidation provisions and allocation terms defined in the agreements, as well as whether the inputs in the models are accurate and complete.
/s/ Deloitte & Touche LLP
Atlanta, Georgia
February 18, 2026
We have served as Southern Power's auditor since 2002.
II-99

    Table of Contents                                Index to Financial Statements
CONSOLIDATED STATEMENTS OF INCOME
For the Years Ended December 31, 2025, 2024, and 2023
Southern Power Company and Subsidiary Companies
 
202520242023
(in millions)
Operating Revenues:
Wholesale revenues, non-affiliates$1,743 $1,606 $1,597 
Wholesale revenues, affiliates437 371 537 
Other revenues18 37 55 
Total operating revenues2,198 2,014 2,189 
Operating Expenses:
Fuel676 579 706 
Purchased power122 78 116 
Other operations and maintenance528 516 473 
Depreciation and amortization843 522 504 
Taxes other than income taxes48 41 51 
Gain on dispositions, net  (20)
Total operating expenses2,217 1,736 1,830 
Operating Income (Loss)(19)278 359 
Other Income and (Expense):
Interest expense, net of amounts capitalized(104)(117)(129)
Other income (expense), net17 13 12 
Total other income and (expense)(87)(104)(117)
Earnings (Loss) Before Income Taxes(106)174 242 
Income taxes (benefit)(61)(13)12 
Net Income (Loss)(45)187 230 
Net loss attributable to noncontrolling interests(170)(141)(127)
Net Income Attributable to Southern Power$125 $328 $357 

CONSOLIDATED STATEMENTS OF COMPREHENSIVE INCOME
For the Years Ended December 31, 2025, 2024, and 2023
Southern Power Company and Subsidiary Companies
 
202520242023
(in millions)
Net Income (Loss)$(45)$187 $230 
Other comprehensive income:
Qualifying hedges:
Changes in fair value, net of tax of $14, $(10), and $(1), respectively
43 (31)(3)
Reclassification adjustment for amounts included in net income,
   net of tax of $(14), $12, and $4, respectively
(45)39 11 
Pension and other postretirement benefit plans:
Benefit plan net gain (loss),
   net of tax of $1, $2, and $(2), respectively
4 7 (7)
Total other comprehensive income2 15 1 
Comprehensive loss attributable to noncontrolling interests(170)(141)(127)
Comprehensive Income Attributable to Southern Power$127 $343 $358 
The accompanying notes are an integral part of these consolidated financial statements.
II-100

    Table of Contents                                Index to Financial Statements
CONSOLIDATED STATEMENTS OF CASH FLOWS
For the Years Ended December 31, 2025, 2024, and 2023
Southern Power Company and Subsidiary Companies
202520242023
 (in millions)
Operating Activities:
Net income (loss)$(45)$187 $230 
Adjustments to reconcile net income
   to net cash provided from operating activities —
Depreciation and amortization, total866 537 524 
Deferred income taxes(34)(7)16 
Utilization of federal tax credit carryforward(95)75 332 
Amortization of ITCs
(58)(58)(58)
Gain on dispositions, net  (20)
Other, net13 36 28 
Changes in certain current assets and liabilities —
-Receivables40 (39)121 
-Other current assets(19)(22)(22)
-Accounts payable7 (3)(60)
-Accrued taxes(8)16 (12)
-Other current liabilities3 (14)17 
Net cash provided from operating activities670 708 1,096 
Investing Activities:
Acquisitions, net of cash acquired  (181)
Property additions(878)(344)(118)
Change in construction payables(1)35 21 
Proceeds from dispositions  59 
Payments pursuant to LTSAs(56)(45)(50)
Other investing activities1 24 4 
Net cash used for investing activities(934)(330)(265)
Financing Activities:
Increase (decrease) in notes payable, net140 (129)(83)
Proceeds — Senior notes1,100   
Redemptions — Senior notes
(900) (290)
Capital contributions from parent company619 216 18 
Capital contributions from noncontrolling interests23 11 21 
Distributions to noncontrolling interests(200)(185)(234)
Purchase of membership interests from noncontrolling interests(286)  
Payment of common stock dividends(279)(262)(252)
Other financing activities(16)(5) 
Net cash provided from (used for) financing activities201 (354)(820)
Net Change in Cash, Cash Equivalents, and Restricted Cash(63)24 11 
Cash, Cash Equivalents, and Restricted Cash at Beginning of Year168 144 133 
Cash, Cash Equivalents, and Restricted Cash at End of Year$105 $168 $144 
Supplemental Cash Flow Information:
Cash paid (received) during the period for —
Interest (net of $25, $7, and $3 capitalized, respectively)
$88 $107 $122 
Income taxes, net (excludes credit transfers)148 (32)(254)
Noncash transactions —
Accrued property additions at year-end59 84 59 
LTSA credits utilized from the sale of spare parts6 13 23 
The accompanying notes are an integral part of these consolidated financial statements.
II-101

    Table of Contents                                Index to Financial Statements
CONSOLIDATED BALANCE SHEETS
At December 31, 2025 and 2024
Southern Power Company and Subsidiary Companies

Assets20252024
(in millions)
Current Assets:
Cash and cash equivalents$105 $159 
Receivables —
Customer accounts, net151 122 
Affiliated35 39 
Other16 90 
Materials and supplies132 107 
Other current assets89 82 
Total current assets528 599 
Property, Plant, and Equipment:
In service15,034 14,961 
Less: Accumulated provision for depreciation5,214 4,540 
Plant in service, net of depreciation9,820 10,421 
Construction work in progress1,080 317 
Total property, plant, and equipment10,900 10,738 
Other Property and Investments:
Intangible assets, net of amortization of $188 and $168, respectively
203 223 
Net investment in sales-type leases137 143 
Total other property and investments340 366 
Deferred Charges and Other Assets:
Operating lease right-of-use assets, net of amortization479 484 
Prepaid LTSAs170 234 
Other deferred charges and assets240 232 
Total deferred charges and other assets889 950 
Total Assets$12,657 $12,653 
The accompanying notes are an integral part of these consolidated financial statements.
II-102

    Table of Contents                                Index to Financial Statements
CONSOLIDATED BALANCE SHEETS
At December 31, 2025 and 2024
Southern Power Company and Subsidiary Companies

Liabilities and Stockholders' Equity20252024
(in millions)
Current Liabilities:
Securities due within one year$587 $500 
Notes payable138  
Accounts payable —
Affiliated88 80 
Other93 100 
Accrued taxes9 18 
Accrued interest38 26 
Operating lease obligations31 29 
Other current liabilities92 96 
Total current liabilities1,076 849 
Long-Term Debt2,353 2,180 
Deferred Credits and Other Liabilities:
Accumulated deferred income taxes579 712 
Accumulated deferred ITCs1,383 1,440 
Operating lease obligations, deferred
510 511 
Other deferred credits and liabilities235 279 
Total deferred credits and other liabilities2,707 2,942 
Total Liabilities6,136 5,971 
Common Stockholder's Equity:
Common stock, par value $0.01 per share
    (Authorized - 1 million shares; Outstanding - 1,000 shares)
  
Paid-in capital1,912 1,306 
Retained earnings1,758 1,912 
Accumulated other comprehensive income (loss) (2)
Total common stockholder's equity3,670 3,216 
Noncontrolling Interests2,851 3,466 
Total Stockholders' Equity (See accompanying statements)
6,521 6,682 
Total Liabilities and Stockholders' Equity$12,657 $12,653 
Commitments and Contingent Matters (See notes)
The accompanying notes are an integral part of these consolidated financial statements.
II-103

    Table of Contents                                Index to Financial Statements
CONSOLIDATED STATEMENTS OF STOCKHOLDERS' EQUITY
For the Years Ended December 31, 2025, 2024, and 2023
Southern Power Company and Subsidiary Companies
Number of Common Shares IssuedCommon StockPaid-In CapitalRetained EarningsAccumulated Other Comprehensive Income (Loss)
Total Common Stockholder's Equity
Noncontrolling InterestsTotal
(in millions)
Balance at December 31, 2022— $— $1,069 $1,741 $(18)$2,792 $4,124 $6,916 
Net income (loss)— — — 357 — 357 (127)230 
Capital contributions from parent
   company
— — 19 — — 19 — 19 
Other comprehensive income— — — — 1 1 — 1 
Cash dividends on common
   stock
— — — (252)— (252)— (252)
Capital contributions from
   noncontrolling interests
— — — — — — 21 21 
Distributions to noncontrolling
   interests
— — — — — — (236)(236)
Other— —     (1)(1)
Balance at December 31, 2023— — 1,088 1,846 (17)2,917 3,781 6,698 
Net income (loss)— — — 328 — 328 (141)187 
Capital contributions from parent
   company
— — 218 — — 218 — 218 
Other comprehensive income— — — — 15 15 — 15 
Cash dividends on common
   stock
— — — (262)— (262)— (262)
Capital contributions from
   noncontrolling interests
— — — — — — 11 11 
Distributions to noncontrolling
   interests
— — — — — — (185)(185)
Balance at December 31, 2024  1,306 1,912 (2)3,216 3,466 6,682 
Net income (loss)   125  125 (170)(45)
Capital contributions from parent
   company
  622   622  622 
Other comprehensive income    2 2  2 
Cash dividends on common
   stock
   (279) (279) (279)
Capital contributions from
   noncontrolling interests
      23 23 
Distributions to noncontrolling
   interests
      (202)(202)
Purchase of membership interests
   from noncontrolling interests(*)
  (16)  (16)(267)(283)
Other      1 1 
Balance at December 31, 2025 $ $1,912 $1,758 $ $3,670 $2,851 $6,521 
(*) See Note 15 under "Southern Power – Purchase of Renewable Facility Interests" for additional information.
The accompanying notes are an integral part of these consolidated financial statements.

II-104

    Table of Contents                                Index to Financial Statements

REPORT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM
To the stockholder and the Board of Directors of Southern Company Gas and Subsidiary Companies
Opinion on the Financial Statements
We have audited the accompanying consolidated balance sheets of Southern Company Gas and subsidiary companies (Southern Company Gas) (a wholly-owned subsidiary of The Southern Company) as of December 31, 2025 and 2024, the related consolidated statements of income, comprehensive income, common stockholder's equity, and cash flows for each of the three years in the period ended December 31, 2025, the related notes, and the financial statement schedule listed in the Index at Item 15 (collectively referred to as the "financial statements"). In our opinion, the financial statements present fairly, in all material respects, the financial position of Southern Company Gas as of December 31, 2025 and 2024, and the results of its operations and its cash flows for each of the three years in the period ended December 31, 2025, in conformity with accounting principles generally accepted in the United States of America.
We did not audit the financial statements of Southern Natural Gas Company, L.L.C. (SNG), Southern Company Gas' investment which is accounted for by the use of the equity method. The accompanying consolidated financial statements of Southern Company Gas include its equity investment in SNG of $1,148 million and $1,245 million as of December 31, 2025 and December 31, 2024, respectively, and its earnings from its equity method investment in SNG of $127 million, $146 million, and $139 million for the years ended December 31, 2025, 2024, and 2023, respectively. Those statements were audited by BDO USA, P.C., whose reports (which express unqualified opinions on SNG's financial statements and contain an emphasis of matter paragraph calling attention to SNG's significant transactions with related parties) have been furnished to us, and our opinion, insofar as it relates to the amounts included for SNG, is based solely on the reports of the other auditors.
Basis for Opinion
These financial statements are the responsibility of Southern Company Gas' management. Our responsibility is to express an opinion on Southern Company Gas' financial statements based on our audits. We are a public accounting firm registered with the Public Company Accounting Oversight Board (United States) (PCAOB) and are required to be independent with respect to Southern Company Gas in accordance with the U.S. federal securities laws and the applicable rules and regulations of the Securities and Exchange Commission and the PCAOB.
We conducted our audits in accordance with the standards of the PCAOB. Those standards require that we plan and perform the audit to obtain reasonable assurance about whether the financial statements are free of material misstatement, whether due to error or fraud. Southern Company Gas is not required to have, nor were we engaged to perform, an audit of its internal control over financial reporting. As part of our audits, we are required to obtain an understanding of internal control over financial reporting but not for the purpose of expressing an opinion on the effectiveness of Southern Company Gas' internal control over financial reporting. Accordingly, we express no such opinion.
Our audits included performing procedures to assess the risks of material misstatement of the financial statements, whether due to error or fraud, and performing procedures that respond to those risks. Such procedures included examining, on a test basis, evidence regarding the amounts and disclosures in the financial statements. Our audits also included evaluating the accounting principles used and significant estimates made by management, as well as evaluating the overall presentation of the financial statements. We believe that our audits and the reports of the other auditors provide a reasonable basis for our opinion.
Critical Audit Matter
The critical audit matter communicated below is a matter arising from the current-period audit of the financial statements that was communicated or required to be communicated to the Audit Committee of Southern Company's Board of Directors and that (1) relates to accounts or disclosures that are material to the financial statements and (2) involved especially challenging, subjective, or complex judgments. The communication of critical audit matters does not alter in any way our opinion on the financial statements, taken as a whole, and we are not, by communicating the critical audit matter below, providing a separate opinion on the critical audit matter or on the accounts or disclosures to which it relates.
Impact of Rate Regulation on the Financial Statements – Refer to Note 1 (Summary of Significant Accounting Policies – Regulatory Assets and Liabilities) and Note 2 (Regulatory Matters – Southern Company Gas) to the financial statements
Critical Audit Matter Description
Southern Company Gas' natural gas distribution utilities (the "regulated utility subsidiaries") are subject to rate regulation by their respective state Public Service Commission or other applicable state regulatory agencies (collectively, the "Commissions"). Management has determined that the regulated utility subsidiaries meet the requirements under accounting principles generally accepted in the United States of America to utilize specialized rules to account for the effects of rate regulation in the preparation
II-105

    Table of Contents                                Index to Financial Statements
of its financial statements. Accounting for the economics of rate regulation may impact multiple financial statement line items and disclosures.
The Commissions set the rates the regulated utility subsidiaries are permitted to charge customers. Rates are determined and approved in regulatory proceedings based on an analysis of the applicable regulated utility subsidiary's costs to provide utility service and a return on, and recovery of, its investment in the utility business. Current and future regulatory decisions can have an impact on the recovery of costs, the rate of return earned on investments, and the timing and amount of assets to be recovered through rates. The Commissions' regulation of rates is premised on the full recovery of prudently incurred costs and a reasonable rate of return on invested capital. While Southern Company Gas' regulated utility subsidiaries expect to recover costs from customers through regulated rates, there is a risk that the Commissions will not approve: (1) full recovery of the costs of providing utility service, or (2) full recovery of all amounts invested in the utility business and a reasonable return on those investments.
We identified the impact of rate regulation related to certain assets and liabilities as a critical audit matter due to the significant judgments made by management to support its assertions about impacted account balances and disclosures and/or the high degree of subjectivity involved in assessing the potential impact of future regulatory orders on incurred costs. Management judgments include assessing the likelihood of (1) recovery in future rates of incurred costs, (2) a disallowance of part of the cost of recently completed plant or plant under construction, and/or (3) a refund to customers. Auditing these judgments, which include assumptions about the outcome of future decisions by the Commissions, required specialized knowledge of accounting for rate regulations and the rate setting process due to its inherent complexities.
How the Critical Audit Matter Was Addressed in the Audit
Our audit procedures related to the impact of rate regulation on certain assets and liabilities included the following, among others:
We tested the effectiveness of management's controls over the evaluation of the likelihood of (1) the recovery in future rates of certain incurred costs and (2) refunds or future reductions in rates that should be reported as regulatory liabilities and the monitoring and evaluation of regulatory developments that may affect the likelihood of recovering certain costs in future rates or of a future reduction in rates, including previously incurred Qualifying Infrastructure Plant capital investments by Nicor Gas. We also tested the effectiveness of management's controls over the initial recognition of certain regulatory assets or liabilities.
We read and evaluated relevant regulatory orders issued and/or other relevant publicly available information to assess the likelihood of recovery of certain incurred costs in future rates or of a future reduction in rates based on precedents of the treatment of similar costs under similar circumstances.
We tested certain incurred costs recorded as regulatory assets or liabilities during the period for completeness and accuracy.
We obtained representation from management regarding the likelihood of recoverability of incurred costs and potential refund or future reduction in rates to assess management's assertions about the likelihood of recovery, refund, or a future reduction in rates.
We evaluated Southern Company Gas' disclosures related to the impacts of rate regulation, including the balances recorded and regulatory developments, including where there is a high degree of subjectivity involved in assessing the potential impact of future regulatory orders on incurred costs.
/s/ Deloitte & Touche LLP
Atlanta, Georgia
February 18, 2026
We have served as Southern Company Gas' auditor since 2016.
II-106

    Table of Contents                                Index to Financial Statements
Report of Independent Registered Public Accounting Firm

Board of Directors and Members
Southern Natural Gas Company, L.L.C.
Houston, Texas

Opinion on the Consolidated Financial Statements
We have audited the accompanying consolidated balance sheets of Southern Natural Gas Company, L.L.C. (the "Company") as of December 31, 2025 and 2024, the related consolidated statements of income, members' equity, and cash flows for each of the three years in the period ended December 31, 2025, and the related notes (collectively referred to as the "consolidated financial statements"). In our opinion, the consolidated financial statements present fairly, in all material respects, the financial position of the Company at December 31, 2025 and 2024, and the results of its operations and its cash flows for each of the three years in the period ended December 31, 2025, in conformity with accounting principles generally accepted in the United States of America.
Basis for Opinion
These consolidated financial statements are the responsibility of the Company's management. Our responsibility is to express an opinion on the Company's consolidated financial statements based on our audits. We are a public accounting firm registered with the Public Company Accounting Oversight Board (United States) ("PCAOB") and are required to be independent with respect to the Company in accordance with the U.S. federal securities laws and the applicable rules and regulations of the Securities and Exchange Commission and the PCAOB.
We conducted our audits in accordance with the standards of the PCAOB and in accordance with auditing standards generally accepted in the United States of America. Those standards require that we plan and perform the audit to obtain reasonable assurance about whether the consolidated financial statements are free of material misstatement, whether due to error or fraud. The Company is not required to have, nor were we engaged to perform, an audit of its internal control over financial reporting. As part of our audits, we are required to obtain an understanding of internal control over financial reporting but not for the purpose of expressing an opinion on the effectiveness of the Company's internal control over financial reporting. Accordingly, we express no such opinion.
Our audits included performing procedures to assess the risks of material misstatement of the consolidated financial statements, whether due to error or fraud, and performing procedures that respond to those risks. Such procedures included examining, on a test basis, evidence regarding the amounts and disclosures in the consolidated financial statements. Our audits also included evaluating the accounting principles used and significant estimates made by management, as well as evaluating the overall presentation of the consolidated financial statements. We believe that our audits provide a reasonable basis for our opinion.
Critical Audit Matter
The critical audit matter communicated below is a matter arising from the current period audit of the consolidated financial statements that was communicated or required to be communicated to the audit committee and that: (i) relates to accounts or disclosures that are material to the consolidated financial statements and (ii) involved our especially challenging, subjective, or complex judgments. The communication of the critical audit matter does not alter in any way our opinion on the consolidated financial statements, taken as a whole, and we are not, by communicating the critical audit matter below, providing a separate opinion on the critical audit matter or on the accounts or disclosures to which it relates.
II-107

    Table of Contents                                Index to Financial Statements
Postretirement Benefits Plan – Fair Value of Investments Measured at Net Asset Value
As discussed in Note 5 to the consolidated financial statements, the fair value of postretirement benefits plan assets on December 31, 2025, was $79 million. Of this amount, $78 million represents the fair value of investments measured at net asset value (NAV).
We identified the assessment of the postretirement benefits plan fair value of investments measured at NAV as a critical audit matter. Estimating the fair value requires management to make certain determination of unobservable inputs. Auditing these elements involved subjective auditor judgment due to the nature and extent of audit effort required, including the extent of specialized skills or knowledge needed to assess sufficiency of audit evidence.
The primary procedures we performed to address this critical audit matter included:
Comparing the fair values as recorded by the Company to external confirmations received directly from the third-party investment managers.
Utilizing specialists who performed a benchmark analysis to determine the correlation of the funds and the stated benchmark; the results were used to estimate the high and low fair value range of the investments to compare to the Company's fair value.
Emphasis of Matter – Significant Transactions with Related Parties
As discussed in Note 6 to the consolidated financial statements, the Company has entered into significant transactions with related parties.
/s/ BDO USA, P.C.
We have served as the Company's auditor since 2018.
Houston, Texas
February 5, 2026
II-108

    Table of Contents                                Index to Financial Statements
CONSOLIDATED STATEMENTS OF INCOME
For the Years Ended December 31, 2025, 2024, and 2023
Southern Company Gas and Subsidiary Companies

202520242023
(in millions)
Operating Revenues:
Natural gas revenues (includes revenue taxes of
   $136, $115, and $133, respectively)
$5,044 $4,456 $4,702 
Total operating revenues5,044 4,456 4,702 
Operating Expenses: 
Cost of natural gas1,599 1,196 1,644 
Other operations and maintenance1,297 1,235 1,187 
Depreciation and amortization708 650 582 
Taxes other than income taxes272 248 262 
Estimated loss on regulatory disallowance
63  88 
Total operating expenses3,939 3,329 3,763 
Operating Income1,105 1,127 939 
Other Income and (Expense):
Earnings from equity method investments127 146 140 
Interest expense, net of amounts capitalized(377)(341)(310)
Other income (expense), net59 66 57 
Total other income and (expense)(191)(129)(113)
Earnings Before Income Taxes914 998 826 
Income taxes182 258 211 
Net Income$732 $740 $615 

CONSOLIDATED STATEMENTS OF COMPREHENSIVE INCOME
For the Years Ended December 31, 2025, 2024, and 2023
Southern Company Gas and Subsidiary Companies
202520242023
(in millions)
Net Income$732 $740 $615 
Other comprehensive income (loss):
Qualifying hedges:
Changes in fair value, net of tax of $(1), $(3), and $(18), respectively
(3)(9)(45)
Reclassification adjustment for amounts included in net income,
   net of tax of $1, $12, and $19, respectively
3 30 46 
Pension and other postretirement benefit plans:
Benefit plan net gain (loss),
   net of tax of $2, $5, and $(7), respectively
4 11 (15)
Reclassification adjustment for amounts included in net income,
   net of tax of $(1), $(1), and $, respectively
(1) (1)
Total other comprehensive income (loss)3 32 (15)
Comprehensive Income$735 $772 $600 
The accompanying notes are an integral part of these consolidated financial statements.

II-109

    Table of Contents                                Index to Financial Statements
CONSOLIDATED STATEMENTS OF CASH FLOWS
For the Years Ended December 31, 2025, 2024, and 2023
Southern Company Gas and Subsidiary Companies
202520242023
(in millions)
Operating Activities:
Consolidated net income$732 $740 $615 
Adjustments to reconcile net income to net cash
   provided from operating activities —
Depreciation and amortization, total701 643 582 
Deferred income taxes122 132 126 
Estimated loss on regulatory disallowance
63  96 
Other, net41 3 (74)
Changes in certain current assets and liabilities —
-Receivables(189)28 431 
-Natural gas for sale, net of temporary LIFO liquidation(8)32 19 
-Prepaid income taxes12 63 (11)
-Natural gas cost under recovery  108 
-Other current assets41 (52)(17)
-Accounts payable75 (6)(276)
-Natural gas cost over recovery(36)(21)214 
-Other current liabilities63 (10)(51)
Net cash provided from operating activities1,617 1,552 1,762 
Investing Activities:
Property additions(1,741)(1,541)(1,561)
Cost of removal, net of salvage(99)(88)(104)
Change in construction payables, net(2)(19)(38)
Investments in unconsolidated subsidiaries(74)(82)(11)
Returned investment in unconsolidated subsidiaries148 15 14 
Proceeds from dispositions 3 42 
Other investing activities 1 2 
Net cash used for investing activities(1,768)(1,711)(1,656)
Financing Activities:
Increase (decrease) in notes payable, net(31)40 (153)
Proceeds —
Senior notes850 450 500 
First mortgage bonds200 275 275 
Other long-term debt 8 37 
Redemptions and repurchases —
Senior notes(250)  
First mortgage bonds(50) (50)
Short-term borrowings  (200)
Medium-term notes  (350)
Return of capital to parent company(23)  
Capital contributions from parent company39 16 373 
Payment of common stock dividends(594)(605)(585)
Other financing activities(19)(16)(1)
Net cash provided from (used for) financing activities122 168 (154)
Net Change in Cash, Cash Equivalents, and Restricted Cash(29)9 (48)
Cash, Cash Equivalents, and Restricted Cash at Beginning of Year44 35 83 
Cash, Cash Equivalents, and Restricted Cash at End of Year$15 $44 $35 
Supplemental Cash Flow Information:
Cash paid during the period for —
Interest (net of $16, $21, and $16 capitalized, respectively)
$372 $329 $291 
Income taxes, net29 59 91 
Noncash transactions —
Accrued property additions at year-end112 113 139 
Return of capital to parent company34   
The accompanying notes are an integral part of these consolidated financial statements.
II-110

    Table of Contents                                Index to Financial Statements
CONSOLIDATED BALANCE SHEETS
At December 31, 2025 and 2024
Southern Company Gas and Subsidiary Companies

Assets20252024
(in millions)
Current Assets:  
Cash and cash equivalents$15 $43 
Receivables —  
Customer accounts490 399 
Unbilled revenues341 244 
Other accounts and notes57 45 
Accumulated provision for uncollectible accounts(50)(33)
Materials and supplies62 66 
Natural gas for sale396 388 
Prepaid expenses26 45 
Other regulatory assets114 187 
Other current assets66 55 
Total current assets1,517 1,439 
Property, Plant, and Equipment:  
In service24,098 22,338 
Less: Accumulated depreciation6,273 5,887 
Plant in service, net of depreciation17,825 16,451 
Construction work in progress863 1,057 
Total property, plant, and equipment18,688 17,508 
Other Property and Investments:
Goodwill5,015 5,015 
Equity investments in unconsolidated subsidiaries1,182 1,279 
Other intangible assets, net of amortization of $179 and $173, respectively
3 9 
Miscellaneous property and investments24 25 
Total other property and investments6,224 6,328 
Deferred Charges and Other Assets:
Operating lease right-of-use assets, net of amortization85 38 
Prepaid pension and other postretirement benefit costs
229 191 
Other regulatory assets, deferred517 481 
Other deferred charges and assets127 192 
Total deferred charges and other assets958 902 
Total Assets$27,387 $26,177 
The accompanying notes are an integral part of these consolidated financial statements.
II-111

    Table of Contents                                Index to Financial Statements
CONSOLIDATED BALANCE SHEETS
At December 31, 2025 and 2024
Southern Company Gas and Subsidiary Companies

Liabilities and Stockholder's Equity20252024
(in millions)
Current Liabilities:
Securities due within one year$531 $302 
Notes payable425 455 
Accounts payable —
Affiliated70 75 
Other553 437 
Customer deposits75 98 
Accrued taxes107 85 
Accrued interest100 88 
Accrued compensation137 129 
Natural gas cost over recovery158 193 
Other regulatory liabilities36 7 
Other current liabilities110 149 
Total current liabilities2,302 2,018 
Long-term Debt8,743 8,229 
Deferred Credits and Other Liabilities:
Accumulated deferred income taxes1,971 1,796 
Deferred credits related to income taxes681 755 
Employee benefit obligations78 78 
Operating lease obligations123 30 
Other cost of removal obligations1,921 1,846 
Accrued environmental remediation207 198 
Other deferred credits and liabilities234 231 
Total deferred credits and other liabilities5,215 4,934 
Total Liabilities16,260 15,181 
Common Stockholder’s Equity:
Common stock, par value $0.01 per share
    (Authorized - 100 million shares; Outstanding - 100 shares)
  
Paid-in capital10,854 10,863 
Retained earnings222 85 
Accumulated other comprehensive income51 48 
Total common stockholder's equity (See accompanying statements)
11,127 10,996 
Total Liabilities and Stockholder's Equity$27,387 $26,177 
Commitments and Contingent Matters (See notes)
The accompanying notes are an integral part of these consolidated financial statements.

II-112

    Table of Contents                                Index to Financial Statements
CONSOLIDATED STATEMENTS OF COMMON STOCKHOLDER'S EQUITY
For the Years Ended December 31, 2025, 2024, and 2023
Southern Company Gas and Subsidiary Companies
 
Number of Common Shares
Issued
Common StockPaid-In CapitalRetained Earnings (Accumulated Deficit)Accumulated
Other
Comprehensive Income (Loss)
Total
(in millions)
Balance at December 31, 2022— $— $10,445 $(79)$31 $10,397 
Net income— — — 615 — 615 
Capital contributions from parent company— — 391 — — 391 
Other comprehensive income (loss)— — — — (15)(15)
Cash dividends on common stock— — — (585)— (585)
Balance at December 31, 2023— — 10,836 (49)16 10,803 
Net income— — — 740 — 740 
Capital contributions from parent company— — 27 — — 27 
Other comprehensive income— — — — 32 32 
Cash dividends on common stock— — — (605)— (605)
Other— — — (1)— (1)
Balance at December 31, 2024  10,863 85 48 10,996 
Net income   732  732 
Return of capital to parent company  (57)  (57)
Capital contributions from parent company  47   47 
Other comprehensive income    3 3 
Cash dividends on common stock   (594) (594)
Other  1 (1)  
Balance at December 31, 2025 $ $10,854 $222 $51 $11,127 
The accompanying notes are an integral part of these consolidated financial statements. 
II-113

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS



Notes to the Financial Statements
for
The Southern Company and Subsidiary Companies
Alabama Power Company
Georgia Power Company
Mississippi Power Company
Southern Power Company and Subsidiary Companies
Southern Company Gas and Subsidiary Companies



Index to the Combined Notes to Financial Statements
NotePage
1
Summary of Significant Accounting Policies
II-115
2
Regulatory Matters
II-129
3
Contingencies, Commitments, and Guarantees
II-150
4
Revenue from Contracts with Customers
II-155
5
Property, Plant, and Equipment
II-160
6
Asset Retirement Obligations
II-163
7
Consolidated Entities and Equity Method Investments
II-168
8
Financing
II-170
9
Leases
II-180
10
Income Taxes
II-188
11
Retirement Benefits
II-197
12
Stock Compensation
II-226
13
Fair Value Measurements
II-228
14
Derivatives
II-236
15
Acquisitions and Dispositions
II-245
16
Segment and Related Information
II-247
Index to Applicable Notes to Financial Statements by Registrant
The following notes to the financial statements are a combined presentation; however, information contained herein relating to any individual Registrant is filed by such Registrant on its own behalf and each Registrant makes no representation as to information related to the other Registrants. The table below indicates the Registrants to which each note applies.
Applicable Notes
Registrant
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Southern Companyl
l
llllllllllllll
Alabama Powerllllllllllllllll
Georgia Powerlllllllllllllll
Mississippi Powerlllllllllllllll
Southern Powerlllllllllllllll
Southern Company Gaslllllllllllllll

II-114

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

1. SUMMARY OF SIGNIFICANT ACCOUNTING POLICIES
General
Southern Company is the parent company of three traditional electric operating companies, as well as Southern Power, Southern Company Gas, SCS, Southern Linc, Southern Holdings, Southern Nuclear, PowerSecure, and other direct and indirect subsidiaries. The traditional electric operating companies – Alabama Power, Georgia Power, and Mississippi Power – are vertically integrated utilities providing electric service in three Southeastern states. Southern Power develops, constructs, acquires, owns, operates, and manages power generation assets, including battery energy storage projects, and sells electricity at market-based rates in the wholesale market. Southern Company Gas distributes natural gas through natural gas distribution utilities, including Nicor Gas (Illinois), Atlanta Gas Light (Georgia), Virginia Natural Gas, and Chattanooga Gas (Tennessee). Southern Company Gas is also involved in several other complementary businesses including gas pipeline investments and gas marketing services. SCS, the system service company, provides, at cost, specialized services to Southern Company and its subsidiary companies. Southern Linc provides digital wireless communications for use by Southern Company and its subsidiary companies and also markets these services to the public and provides fiber optics services within the Southeast. Southern Holdings is an intermediate holding company subsidiary, which, through its subsidiaries, invests in various projects and insures various risk exposures of Southern Company and its subsidiaries. Southern Nuclear operates and provides services to the Southern Company system's nuclear power plants, including Alabama Power's Plant Farley and Georgia Power's Plants Hatch and Vogtle. PowerSecure develops distributed energy and resilience solutions and deploys microgrids for commercial, industrial, governmental, and utility customers.
The Registrants' financial statements reflect investments in subsidiaries on a consolidated basis. Intercompany transactions have been eliminated in consolidation. The equity method is used for investments in entities in which a Registrant has significant influence but does not have control and for VIEs where a Registrant has an equity investment but is not the primary beneficiary. Southern Power has controlling ownership in certain legal entities for which the contractual provisions represent profit-sharing arrangements because the allocations of cash distributions and tax benefits are not based on fixed ownership percentages. For these arrangements, the noncontrolling interest is accounted for under a balance sheet approach utilizing the HLBV method. The HLBV method calculates each partner's share of income based on the change in net equity the partner can legally claim in an HLBV at the end of the period compared to the beginning of the period. See "Variable Interest Entities" herein and Note 7 for additional information.
The traditional electric operating companies, Southern Power, certain subsidiaries of Southern Company Gas, and certain other subsidiaries are subject to regulation by the FERC, and the traditional electric operating companies and the natural gas distribution utilities are also subject to regulation by their respective state PSCs or other applicable state regulatory agencies. As such, the respective financial statements of the applicable Registrants reflect the effects of rate regulation in accordance with GAAP and comply with the accounting policies and practices prescribed by relevant state PSCs or other applicable state regulatory agencies.
The preparation of financial statements in conformity with GAAP requires the use of estimates, and the actual results may differ from those estimates. Certain prior years' data presented in the financial statements have been reclassified to conform to the current year presentation. These reclassifications had no impact on the Registrants' results of operations, financial position, or cash flows.
Recently Adopted Accounting Standards
In November 2023, the FASB issued ASU 2023-07, Segment Reporting (Topic 280): Improvements to Reportable Segment Disclosures (ASU 2023-07), which requires entities to disclose significant segment expenses, other segment items, the title and position of the CODM, and information related to how the CODM assesses segment performance and allocates resources, among certain other required disclosures. Additionally, previous annual disclosures are required in interim periods. The Registrants adopted ASU 2023-07 and applied the guidance retrospectively effective for the fiscal year beginning January 1, 2024. ASU 2023-07 was applied retrospectively for the interim periods beginning January 1, 2025. See Note 16 for additional information and related disclosures.
In December 2023, the FASB issued ASU 2023-09, Income Taxes (Topic 740): Improvements to Income Tax Disclosures (ASU 2023-09), which requires entities to enhance consistency in income tax disclosures by improving transparency and comparability for stakeholders. Among other changes, ASU 2023-09 requires additional information in the effective tax rate reconciliation, including disaggregation of certain categories, and greater detail about income taxes paid, including disaggregation by jurisdiction. The Registrants adopted ASU 2023-09 and applied the guidance retrospectively effective for the fiscal year beginning January 1, 2025. See Note 10 under "Effective Tax Rate" and "Cash Paid for Income Taxes" for additional information and related disclosures.
II-115

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

In July 2025, the FASB issued ASU 2025-05, Financial Instruments – Credit Losses (Topic 326): Measurement of Credit Losses for Accounts Receivable and Contract Assets (ASU 2025-05), which allows an entity to elect a practical expedient for measuring expected credit losses on current accounts receivable and current contract assets arising from transactions accounted for as revenues from contracts customers. This expedient allows an entity to assume that current economic conditions as of the balance sheet date do not change for the remaining life of the asset. ASU 2025-05 is effective for fiscal years beginning after December 15, 2025 and interim periods within fiscal years beginning after December 15, 2026. As permitted, the Registrants have elected to early adopt the practical expedient as of December 31, 2025 and applied its provisions prospectively to the provision for uncollectable accounts. The adoption of ASU 2025‑05 did not have a material impact on the consolidated results of operations, cash flows or financial condition of the Registrants. See "Provision for Uncollectible Accounts" herein for additional information and disclosures impacted by ASU 2025-05.
Affiliate Transactions
The traditional electric operating companies, Southern Power, and Southern Company Gas have agreements with SCS under which certain of the following services are rendered to them at direct or allocated cost: general executive and advisory, general and design engineering, operations, purchasing, accounting, finance, treasury, legal, tax, information technology, marketing, auditing, insurance and pension administration, human resources, systems and procedures, digital wireless communications, cellular tower space, and other services with respect to business and operations, construction management, and Southern Company power pool transactions. These costs are primarily included in other operations and maintenance expenses or capitalized to property, plant, and equipment. Costs for these services from SCS in 2025, 2024, and 2023 were as follows:
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company Gas
(in millions)
2025$855 $1,364 $138 $101 $313 
2024813 1,197 130 93 290 
2023611 857 113 86 261 
Alabama Power and Georgia Power also have agreements with Southern Nuclear under which Southern Nuclear renders the following nuclear-related services at cost: general executive and advisory services; general operations, management, and technical services; administrative services including procurement, accounting, employee relations, systems, and procedures services; strategic planning and budgeting services; and other services with respect to business and operations. These costs are primarily included in other operations and maintenance expenses or capitalized to property, plant, and equipment. Costs for these services in 2025, 2024, and 2023 amounted to $275 million, $260 million, and $251 million, respectively, for Alabama Power and $832 million, $835 million, and $899 million, respectively, for Georgia Power.
Cost allocation methodologies used by SCS and Southern Nuclear prior to the repeal of the Public Utility Holding Company Act of 1935, as amended, were approved by the SEC. Subsequently, additional cost allocation methodologies have been reported to the FERC and management believes they are reasonable. The FERC permits services to be rendered at cost by system service companies.
Alabama Power's and Georgia Power's power purchases from affiliates through the Southern Company power pool are included in purchased power, affiliates on their respective statements of income. Mississippi Power's and Southern Power's power purchases from affiliates through the Southern Company power pool are included in purchased power on their respective statements of income and were as follows:
Mississippi
Power
Southern
Power
(in millions)
2025$19 $41 
20248 17 
20234 13 
Georgia Power has entered into a PPA with Mississippi Power, which commenced in 2024, and several PPAs with Southern Power for capacity and energy. Georgia Power's expenses associated with these PPAs are included in purchased power, affiliates on its statements of income. Mississippi Power's and Southern Power's revenues associated with these PPAs are included in wholesale revenues, affiliates on their respective statements of income. See Notes 2 and 9 for additional information.
II-116

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

SCS (as agent for Alabama Power, Georgia Power, and Southern Power) and certain subsidiaries of Southern Company Gas have long-term interstate natural gas transportation agreements with SNG that are governed by the terms and conditions of SNG's natural gas tariff and are subject to FERC regulation. See Note 7 under "Southern Company Gas" for additional information. Transportation costs under these agreements in 2025, 2024, and 2023 were as follows:
Alabama
Power
Georgia
Power
Southern
Power
Southern
Company Gas
(in millions)
2025$11 $105 $31 $29 
202413 103 35 28 
202312 101 34 28 
SCS, as agent for the traditional electric operating companies and Southern Power, has agreements with certain subsidiaries of Southern Company Gas to purchase natural gas. Natural gas purchases made under these agreements were immaterial for Alabama Power, Georgia Power, Mississippi Power, and Southern Power for all periods presented.
Alabama Power and Mississippi Power jointly own Plant Greene County. The companies have an agreement under which Alabama Power operates Plant Greene County and Mississippi Power reimburses Alabama Power for its proportionate share of non-fuel operations and maintenance expenses, which totaled $9 million, $7 million, and $5 million in 2025, 2024, and 2023, respectively. See Notes 2 and 5 under "Mississippi Power Integrated Resource Plans" and "Joint Ownership Agreements," respectively, for additional information.
Alabama Power, Georgia Power, and Mississippi Power each have agreements with PowerSecure for equipment purchases and/or services related to utility infrastructure construction, distributed energy, and energy efficiency projects. During 2025, 2024, and 2023, costs under these agreements were $51 million, $20 million, and $5 million, respectively, for Georgia Power and immaterial for Alabama Power and Mississippi Power.
Southern Company Gas had a $74 million contract with the U.S. General Services Administration to increase energy efficiency at certain federal buildings across Georgia, which was completed in 2025. Southern Company Gas engaged PowerSecure to provide the majority of the construction services under the contract. During 2025, 2024, and 2023, Southern Company Gas paid $1 million, $13 million, and $29 million, respectively, to PowerSecure related to this agreement.
See Note 7 under "SEGCO" for information regarding Alabama Power's and Georgia Power's equity method investment in SEGCO and related affiliate purchased power costs, as well as Alabama Power's gas pipeline ownership agreement with SEGCO.
Southern Power has several agreements with SCS for transmission services, which are billed to Southern Power based on the Southern Company Open Access Transmission Tariff as filed with the FERC. Transmission services purchased by Southern Power from SCS totaled $9 million, $25 million, and $33 million for 2025, 2024, and 2023, respectively, and were charged to other operations and maintenance expenses in Southern Power's consolidated statements of income.
The traditional electric operating companies and Southern Power may jointly enter into various types of wholesale energy, natural gas, and certain other contracts, either directly or through SCS as agent. Each participating company may be jointly and severally liable for the obligations incurred under these agreements. See Note 14 under "Contingent Features" for additional information. Southern Power and the traditional electric operating companies generally settle amounts related to the above transactions on a monthly basis in the month following the performance of such services or the purchase or sale of electricity. See "Revenues – Southern Power" herein for additional information.
The traditional electric operating companies, Southern Power, and Southern Company Gas provide incidental services to and receive such services from other Southern Company subsidiaries which are generally minor in duration and amount. Except as described herein, the traditional electric operating companies, Southern Power, and Southern Company Gas neither provided nor received any material services to or from affiliates in any year presented.
Regulatory Assets and Liabilities
The traditional electric operating companies and the natural gas distribution utilities are subject to accounting requirements for the effects of rate regulation. Regulatory assets represent probable future revenues associated with certain costs that are expected to be recovered from customers through the ratemaking process. Regulatory liabilities represent costs recovered that are expected to be incurred in the future or probable future reductions in revenues associated with amounts that are expected to be credited to customers through the ratemaking process.
In the event that a portion of a traditional electric operating company's or a natural gas distribution utility's operations is no longer subject to applicable accounting rules for rate regulation, such company would be required to write off to income or reclassify to
II-117

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

AOCI related regulatory assets and liabilities that are not specifically recoverable through regulated rates. In addition, the traditional electric operating company or the natural gas distribution utility would be required to determine if any impairment to other assets, including plant, exists and write down the assets, if impaired, to their fair values. All regulatory assets and liabilities are to be reflected in rates. See Note 2 for additional information including details of regulatory assets and liabilities reflected in the balance sheets for Southern Company, the traditional electric operating companies, and Southern Company Gas.
Revenues
The Registrants generate revenues from a variety of sources which are accounted for under various revenue accounting guidance, including revenue from contracts with customers, lease, derivative, and regulatory accounting. See Notes 4, 9, and 14 for additional information.
Traditional Electric Operating Companies
The majority of the revenues of the traditional electric operating companies are generated from contracts with retail electric customers. These revenues, generated from the integrated service to deliver electricity when and if called upon by the customer, are recognized as a single performance obligation satisfied over time, at a tariff rate, and as electricity is delivered to the customer during the month. Unbilled revenues related to retail sales are recognized for estimated deliveries of electricity not yet billed to these customers from the last bill date to the end of the accounting period. Retail rates may include provisions to adjust revenues for fluctuations in fuel costs, fuel hedging, the energy component of purchased power costs, and certain other costs. Revenues are adjusted for differences between these actual costs and amounts billed in current regulated rates. Under or over recovered regulatory clause revenues are recorded in the balance sheets and are recovered from or returned to customers, respectively, through adjustments to the billing factors. See Note 2 for additional information regarding regulatory matters of the traditional electric operating companies.
Wholesale capacity revenues from PPAs are recognized in amounts billable under the contract terms. Energy and other revenues are generally recognized as services are provided. The contracts for capacity and energy in a wholesale PPA have multiple performance obligations where the contract's total transaction price is allocated to each performance obligation based on the standalone selling price. The standalone selling price is primarily determined by the price charged to customers for the specific goods or services transferred with the performance obligations. Generally, the traditional electric operating companies recognize revenue as the performance obligations are satisfied over time as electricity is delivered to the customer or as generation capacity is available to the customer.
For both retail and wholesale revenues, the traditional electric operating companies have elected to recognize revenue for their sales of electricity and capacity using the invoice practical expedient as they generally have a right to consideration in an amount that corresponds directly with the value to the customer of the performance completed to date and that may be invoiced. Payment for goods and services rendered is typically due in the subsequent month following satisfaction of the Registrants' performance obligation.
Southern Power
Southern Power sells capacity and energy at rates specified under contractual terms in long-term PPAs. These PPAs are accounted for as leases, normal sale derivatives, or contracts with customers. Capacity revenues from PPAs classified as operating leases are recognized on a straight-line basis over the term of the agreement. Energy revenues are recognized in the period the energy is delivered. Capacity revenues from PPAs classified as sales-type leases are recognized by accounting for interest income on the net investment in the lease.
Southern Power's non-lease contracts commonly include capacity and energy which are considered separate performance obligations. In these contracts, the total transaction price is allocated to each performance obligation based on the standalone selling price. The standalone selling price is primarily determined by the price charged to customers for the specific goods or services transferred with the performance obligations. Generally, Southern Power recognizes revenue as the performance obligations are satisfied over time, as electricity is delivered to the customer or as generation capacity is made available to the customer.
Southern Power generally has a right to consideration in an amount that corresponds directly with the value to the customer of the performance completed to date and may recognize revenue in the amount to which the entity has a right to invoice. Payment for goods and services rendered is typically due in the subsequent month following satisfaction of Southern Power's performance obligation.
When multiple contracts exist with the same counterparty, the revenues from each contract are accounted for as separate arrangements.
II-118

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Southern Power may also enter into contracts to sell short-term capacity in the wholesale electricity markets. These sales are generally classified as mark-to-market derivatives and net unrealized gains and losses on such contracts are recorded in wholesale revenues. See Note 14 and "Financial Instruments" herein for additional information.
Southern Company Gas
Southern Company Gas records revenues when goods or services are provided to customers. Those revenues are based on rates approved by the state regulatory agencies of the natural gas distribution utilities. The majority of the revenues of Southern Company Gas are generated from contracts with natural gas distribution customers. Revenues from this integrated service to deliver gas when and if called upon by the customer are recognized as a single performance obligation satisfied over time and are recognized at a tariff rate as gas is delivered to the customer during the month.
Revenues from sales and transportation services are recognized in the same period in which the related volumes are delivered to customers. Revenues from residential and certain commercial and industrial customers are recognized on the basis of scheduled meter readings. Additionally, unbilled revenues are recognized for estimated deliveries of gas not yet billed to these customers, from the last bill date to the end of the accounting period. For other commercial and industrial customers, revenues are based on actual deliveries through the end of the period.
Southern Company Gas has elected to recognize revenue for sales of gas using the invoice practical expedient as it generally has a right to consideration in an amount that corresponds directly with the value to the customer of the performance completed to date and that may be invoiced. Payment for goods and services rendered is typically due in the subsequent month following satisfaction of Southern Company Gas' performance obligation.
Gas Distribution Operations
Atlanta Gas Light operates in a deregulated natural gas market whereby Marketers, rather than a traditional utility, sell natural gas to end-use customers in Georgia and handle customer billing functions. As required by the Georgia PSC, Atlanta Gas Light bills Marketers in equal monthly installments for each residential, commercial, and industrial end-use customer's distribution costs as well as for capacity costs utilizing a seasonal rate design for the calculation of each residential end-use customer's annual straight-fixed-variable charge, which reflects the historic volumetric usage pattern for the entire residential class. With the exception of Atlanta Gas Light, the natural gas distribution utilities have rate structures that include volumetric rate designs that allow the opportunity to recover certain costs based on gas usage.
The tariffs for the natural gas distribution utilities include provisions which allow for the recognition of certain revenues prior to the time such revenues are billed to customers. These provisions are referred to as alternative revenue programs and provide for the recognition of certain revenues prior to billing, as long as the amounts recognized will be collected from customers within 24 months of recognition. Revenue related to alternative revenue programs was $(53) million, $43 million, and $20 million in 2025, 2024, and 2023, respectively. These programs primarily consist of:
Weather normalization adjustments – reduce customer bills when winter weather is colder than normal and increase customer bills when weather is warmer than normal and are included in the tariffs for Virginia Natural Gas and Chattanooga Gas;
Revenue normalization mechanisms – mitigate the impact of conservation and declining customer usage and are contained in the tariffs for Virginia Natural Gas and Nicor Gas; and
Revenue true-up adjustment – included within the provisions of the GRAM program in which Atlanta Gas Light participates as a short-term alternative to formal rate case filings, the revenue true-up feature provides for a positive (or negative) adjustment to record revenue in the amount of any variance to budgeted revenues, which are submitted and approved annually as a requirement of GRAM. Such adjustments are reflected in customer billings in a subsequent program year.
Gas Marketing Services
Gas marketing services is comprised of several choice-based natural gas marketers operating in various deregulated jurisdictions. While gas marketing services follows the same general approach to revenue recognition described for Southern Company Gas above, it recognizes revenues on certain 12-month utility-bill management contracts as the lesser of cumulative earned or cumulative billed amounts.
Concentration of Revenue
Southern Company, Alabama Power, Georgia Power, Mississippi Power (with the exception of its long-term contracts described below), Southern Power, and Southern Company Gas each have a diversified base of customers. In 2025, Southern Power's
II-119

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

largest customer was Georgia Power, which accounted for approximately 10.5% of Southern Power's total revenues. For the other Registrants, no single customer comprises 10% or more of each company's revenues.
Mississippi Power provides service under long-term contracts with rural electric cooperative associations and a municipality located in southeastern Mississippi which are subject to regulation by the FERC. The contracts with these wholesale customers represented 12.9% of Mississippi Power's total operating revenues in 2025.
Fuel Costs
Fuel costs for the traditional electric operating companies and Southern Power are expensed as the fuel is used. Fuel expense generally includes fuel transportation costs and the cost of purchased emissions allowances as they are used. For Alabama Power and Georgia Power, fuel expense also includes the amortization of the cost of nuclear fuel. For the traditional electric operating companies, fuel costs also include gains and/or losses from fuel-hedging programs as approved by their respective state PSCs.
Cost of Natural Gas
Excluding Atlanta Gas Light, which does not sell natural gas to end-use customers, Southern Company Gas charges its utility customers for natural gas consumed using natural gas cost recovery mechanisms set by the applicable state regulatory agencies. Under these mechanisms, all prudently-incurred natural gas costs are passed through to customers without markup, subject to regulatory review. Southern Company Gas defers or accrues the difference between the actual cost of natural gas and the amount of commodity revenue earned in a given period such that no operating income is recognized related to these costs. The deferred or accrued amount is either billed or refunded to customers prospectively through adjustments to the commodity rate. Deferred and accrued natural gas costs are included in the balance sheets as regulatory assets and regulatory liabilities, respectively.
Southern Company Gas' gas marketing services' customers are charged for actual or estimated natural gas consumed. Within cost of natural gas, Southern Company Gas also includes costs of lost and unaccounted for gas and gains and losses associated with certain derivatives.
Income Taxes
The Registrants use the liability method of accounting for deferred income taxes and provide deferred income taxes for all significant income tax temporary differences. Under current tax law, certain projects are eligible for ITCs. The Registrants use the deferral method to account for federal and state ITCs, whereby the ITCs are recorded as a deferred credit and amortized to income tax expense over the useful life of the respective asset. In accordance with regulatory requirements, certain state ITCs at Georgia Power are recognized as an income tax benefit in the year the credit is generated through the establishment of a regulatory asset.
Furthermore, the federal tax basis of the asset is reduced by 50% of the federal ITCs received, which, together with the deferred credit, results in a net deferred tax asset. The Registrants have elected to recognize the tax benefit of these basis differences as a reduction to income tax expense in the year in which the asset reaches commercial operation. In accordance with regulatory requirements, the traditional electric operating companies and natural gas distribution utilities defer the income tax benefit resulting from these basis differences. In addition, certain projects are eligible for federal and state PTCs, which are recognized as an income tax benefit based on KWH production.
Federal ITCs and PTCs, as well as state ITCs and other state tax credits available to reduce income taxes payable, were not fully utilized in 2025 and will be carried forward and utilized in future years. In addition, Southern Company is expected to have various state net operating loss (NOL) carryforwards for certain of its subsidiaries, including Mississippi Power and Southern Power, which would result in income tax benefits in the future, if utilized. See Note 10 under "Deferred Tax Assets and Liabilities – Tax Credit Carryforwards" and " – Net Operating Loss Carryforwards" for additional information.
In April 2024, the IRS issued final regulations related to the transferability of certain tax credits under the IRA. Southern Company and certain subsidiaries have tax credits that are eligible to be transferred at a discount to the generated credit value. The discount will be recorded as a reduction in tax credits recognized in the financial statements. See Note 10 under "Current and Deferred Income Taxes" for additional information.
Under current tax law, Georgia Power is eligible to generate advanced nuclear PTCs for Plant Vogtle Units 3 and 4, which are recognized as an income tax benefit based on KWH production and are eligible to be transferred. Pursuant to the Vogtle Joint Ownership Agreements (as defined in Note 2 under "Georgia Power – Nuclear Construction – Cost and Schedule"), Georgia Power is purchasing advanced nuclear PTCs for Plant Vogtle Units 3 and 4 from the other Vogtle Owners. The gain recognized on the purchase of the joint owner PTCs is recognized as an income tax benefit.
The Registrants recognize tax positions that are "more likely than not" of being sustained upon examination by the appropriate taxing authorities. See Note 10 under "Unrecognized Tax Benefits" for additional information.
II-120

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Other Taxes
Taxes imposed on and collected from customers on behalf of governmental agencies are presented net on the Registrants' statements of income and are excluded from the transaction price in determining the revenue related to contracts with a customer.
Southern Company Gas is taxed on its gas revenues by various governmental authorities, but is allowed to recover these taxes from its customers. Revenue taxes imposed on the natural gas distribution utilities are recorded at the amount charged to customers, which may include a small administrative fee, as operating revenues, and the related taxes imposed on Southern Company Gas are recorded as operating expenses on the statements of income. Revenue taxes included in operating expenses were $132 million, $112 million, and $129 million in 2025, 2024, and 2023, respectively.
Allowance for Funds Used During Construction and Interest Capitalized
The traditional electric operating companies and the natural gas distribution utilities record AFUDC, which represents the estimated debt and equity costs of capital funds that are necessary to finance the construction of new regulated facilities. While cash is not realized currently, AFUDC increases the revenue requirement and is recovered over the service life of the asset through a higher rate base and higher depreciation. The equity component of AFUDC is not taxable.
Interest related to financing the construction of new facilities at Southern Power and new facilities not included in the traditional electric operating companies' and Southern Company Gas' regulated rates is capitalized in accordance with standard interest capitalization requirements.
Total AFUDC and interest capitalized in 2025, 2024, and 2023 was immaterial for Mississippi Power and was as follows for the other Registrants:
Southern
Company
Alabama
Power
Georgia
   Power(*)
Southern
Power
Southern
Company Gas
(in millions)
2025$480 $88 $327 $25 $38 
2024339 76 209 7 47 
2023400 109 251 3 37 
(*)See Note 2 under "Georgia Power – Nuclear Construction" for information on the inclusion of a portion of construction costs related to Plant Vogtle Units 3 and 4 in Georgia Power's rate base through each unit's respective in-service date.
The average AFUDC composite rates for 2025, 2024, and 2023 for the applicable traditional electric operating companies and the natural gas distribution utilities were as follows:
202520242023
Alabama Power7.9 %8.1 %8.1 %
Georgia Power(*)
7.7 %7.7 %7.6 %
Southern Company Gas:
Atlanta Gas Light7.9 %7.7 %7.4 %
Chattanooga Gas7.1 %7.1 %7.1 %
Nicor Gas4.2 %5.6 %4.6 %
(*)Excludes AFUDC related to the construction of Plant Vogtle Units 3 and 4 in 2023 and Plant Vogtle Unit 4 in 2024. See Note 2 under "Georgia Power – Nuclear Construction" for additional information.
Impairment of Long-Lived Assets
The Registrants evaluate long-lived assets for impairment when events or changes in circumstances indicate that the carrying amount of such assets may not be recoverable. The determination of whether an impairment indicator exists is based on either a specific regulatory disallowance, a sales transaction price that is less than the asset group's carrying amount, or an estimate of undiscounted future cash flows attributable to the asset group, as compared with the carrying amount of the assets. If an impairment has occurred, the amount of the impairment loss recognized is determined by either the amount of regulatory disallowance or by the amount the carrying amount exceeds the estimated fair value of the assets. For assets identified as held for sale, the carrying amount is compared to the estimated fair value less the cost to sell in order to determine if an impairment loss is required to be recorded. Until the assets are disposed of, their estimated fair value is re-evaluated when circumstances or events change.
II-121

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

In 2024, Alabama Power discontinued the development of a multi-use commercial facility. Given the decision to discontinue commercial development, Alabama Power performed an impairment test using a comparative market analysis and determined the carrying amount of the asset exceeded its fair value, net of selling costs. This resulted in a pre-tax impairment loss of $36 million ($27 million after tax) reflected in other operations and maintenance on the statements of income.
Goodwill and Other Intangible Assets
Goodwill and other intangible assets not subject to amortization are evaluated for impairment on an annual basis and when events or changes in circumstances necessitate an evaluation for impairment. Other intangible assets subject to amortization are evaluated for impairment when events or changes in circumstances indicate that the carrying amount of such assets may not be recoverable.
Southern Power's intangible assets consist primarily of certain PPAs acquired, which are amortized over the term of the respective PPA. Southern Company Gas' goodwill and other intangible assets primarily relate to its 2016 acquisition by Southern Company. In addition to these items, Southern Company's goodwill and other intangible assets also relate to its 2016 acquisition of PowerSecure.
For its 2025 and 2023 annual goodwill impairment tests, Southern Company Gas management performed the qualitative assessment and determined that it was more likely than not that the fair value of its reporting units with goodwill exceeded their carrying amounts, and therefore no quantitative assessment was required. For its 2024 annual goodwill impairment test, Southern Company Gas management performed the quantitative assessment, which indicated that the fair value of its reporting units with goodwill exceeded their carrying amounts.
For its 2025 and 2023 annual goodwill impairment tests, PowerSecure management performed the quantitative assessment, which indicated that the fair value of PowerSecure exceeded its carrying amount. For its 2024 annual goodwill impairment test, PowerSecure management performed the qualitative assessment and determined that it was more likely than not that the fair value of PowerSecure exceeded its carrying amount, and therefore no quantitative assessment was required.
At December 31, 2025 and 2024, goodwill was as follows:
At December 31, 2025At December 31, 2024
(in millions)
Southern Company$5,161 $5,161 
Southern Company Gas:
Gas distribution operations$4,034 $4,034 
Gas marketing services981 981 
Southern Company Gas total$5,015 $5,015 
II-122

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

At December 31, 2025 and 2024, other intangible assets were as follows:
At December 31, 2025At December 31, 2024
Gross
Carrying
Amount
Accumulated
Amortization
Other
Intangible
Assets, Net
Gross
Carrying
Amount
Accumulated
Amortization
Other
Intangible
Assets, Net
(in millions)(in millions)
Southern Company
Subject to amortization:
Customer relationships$212 $(189)$23 $212 $(182)$30 
Trade names64 (64) 64 (59)5 
PPA fair value adjustments390 (188)202 390 (168)222 
Other3 (3) 3 (3) 
Total subject to amortization$669 $(444)$225 $669 $(412)$257 
Not subject to amortization:
FCC licenses75  75 75  75 
Total other intangible assets$744 $(444)$300 $744 $(412)$332 
Southern Power(*)
PPA fair value adjustments$390 $(188)$202 $390 $(168)$222 
Southern Company Gas(*)
Gas marketing services
Customer relationships$156 $(153)$3 $156 $(150)$6 
Trade names26 (26) 26 (23)3 
Total other intangible assets$182 $(179)$3 $182 $(173)$9 
(*)All subject to amortization.
Amortization associated with other intangible assets in 2025, 2024, and 2023 was as follows:
202520242023
(in millions)
Southern Company(a)
$32 $35 $38 
Southern Power(b)
20 20 20 
Southern Company Gas
Gas marketing services6 7 10 
(a)Includes $20 million annually recorded as a reduction to operating revenues.
(b)Recorded as a reduction to operating revenues.
At December 31, 2025, the estimated amortization associated with other intangible assets for the next five years is as follows:
20262027202820292030
(in millions)
Southern Company$27 $24 $24 $23 $21 
Southern Power20 20 20 19 19 
Southern Company Gas
Gas marketing services3     
Acquisition Accounting
At the time of an acquisition, management will assess whether acquired assets and activities meet the definition of a business. Acquisitions that meet the definition of a business are accounted for under the acquisition method, and operating results from the date of acquisition are included in the acquiring entity's financial statements. Identifiable assets acquired, liabilities assumed, and
II-123

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

any noncontrolling interests (including any intangible assets) are recognized and measured at fair value, and goodwill is recognized as a residual over the fair values of the identifiable net assets acquired. Assets acquired that do not meet the definition of a business are accounted for as an asset acquisition. The purchase price of each asset acquisition is allocated based on the relative fair value of assets acquired. See Note 15 for additional information, including recent and proposed acquisitions.
Determining the fair value of assets acquired and liabilities assumed requires management judgment and management may engage independent valuation experts to assist in this process. Fair values are determined by using market participant assumptions and typically include the timing and amounts of future cash flows, incurred construction costs, the nature of acquired contracts, discount rates, power market prices, and expected asset lives. For potential or successful acquisitions that meet the definition of a business, any due diligence or transaction costs incurred are expensed as incurred. If the acquisition is accounted for as an asset acquisition, direct and incremental transaction costs can be capitalized as a component of the cost of the assets acquired.
Historically, any contingent consideration relates to fixed amounts due to the seller once an acquired construction project is placed in service. For contingent consideration with variable payments, management fair values the arrangement with any changes recorded in the statements of income. See Note 13 for additional fair value information.
Development Costs
For Southern Power, development costs are capitalized once a project is probable of completion, primarily based on a review of its economics and operational feasibility, as well as the status of power off-take agreements and regulatory approvals, if applicable. Southern Power's capitalized development costs are included in CWIP on the balance sheets. All of Southern Power's development costs incurred prior to the determination that a project is probable of completion are expensed as incurred and included in other operations and maintenance expense in the statements of income. If it is determined that a project is no longer probable of completion, any of Southern Power's capitalized development costs are expensed and included in other operations and maintenance expense in the consolidated statements of income. See Note 15 for additional information, including recent and proposed development projects.
Long-Term Service Agreements
The traditional electric operating companies and Southern Power have entered into LTSAs for the purpose of securing maintenance support for certain of their generating facilities. The LTSAs cover all planned inspections on the covered equipment, which generally includes the cost of all labor and materials. The LTSAs also obligate the counterparties to cover the costs of unplanned maintenance on the covered equipment subject to limits and scope specified in each contract.
Payments made under the LTSAs for the performance of any planned inspections or unplanned capital maintenance are recorded in the statements of cash flows as investing activities. Receipts of major parts into materials and supplies inventory prior to planned inspections covered under LTSAs are treated as noncash transactions in the statements of cash flows. Any payments made prior to the work being performed are recorded as prepayments in other current assets and non-current assets on the balance sheets or reduce existing payables for LTSA-related work already completed. At the time work is performed, an appropriate amount is accrued for future payments or transferred from the prepayment or inventory and recorded as property, plant, and equipment or expensed.
Transmission Receivables/Prepayments
As a result of Southern Power's acquisition and construction of generating facilities, Southern Power has transmission receivables and/or prepayments representing the portion of interconnection network and transmission upgrades that will be reimbursed to Southern Power. Upon completion of the related project, transmission costs are generally reimbursed by the interconnection provider and the receivable/prepayments are reduced as payments or services are received.
Cash, Cash Equivalents, and Restricted Cash
For purposes of the financial statements, temporary cash investments are considered cash equivalents. Temporary cash investments are securities with original maturities of 90 days or less.
II-124

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

The following table provides a reconciliation of cash, cash equivalents, and restricted cash reported within the balance sheets that total to the amount shown in the statements of cash flows for the applicable Registrants:
Southern
Company
Georgia
Power
Southern
Power
Southern
Company
Gas
(in millions)
At December 31, 2025
Cash and cash equivalents$1,639 $59 $105 $15 
Restricted cash(*):
Other current assets1    
Total cash, cash equivalents, and restricted cash
$1,640 $59 $105 $15 
At December 31, 2024
Cash and cash equivalents$1,070 $97 $159 $43 
Restricted cash(*):
Other current assets31 21 9 1 
Total cash, cash equivalents, and restricted cash
$1,101 $118 $168 $44 
(*)For Georgia Power, reflects remaining proceeds at December 31, 2024 from the issuance of solid waste disposal facility revenue bonds in 2022. For Southern Power, reflects remaining proceeds at December 31, 2024 from an arbitration award held to fund future equipment replacement costs. For Southern Company, also reflects collateral of $1 million for life insurance and long-term disability insurance, which was included at Southern Holdings and Southern Company Gas at December 31, 2025 and 2024, respectively.
Materials and Supplies
Materials and supplies for the traditional electric operating companies generally includes the average cost of transmission, distribution, and generating plant materials. Materials and supplies for Southern Company Gas generally includes the average cost of propane gas inventory, liquefied natural gas inventory, fleet fuel, and other materials and supplies. Materials and supplies for Southern Power generally includes the average cost of generating plant materials.
Materials are recorded to inventory when purchased and then expensed or capitalized to property, plant, and equipment, as appropriate, at weighted average cost when installed. In addition, certain major parts are recorded as inventory when acquired and then capitalized at cost when installed to property, plant, and equipment.
Fuel Inventory
Fuel inventory for the traditional electric operating companies includes the average cost of coal, natural gas, oil, transportation, and emissions allowances. Fuel inventory for Southern Power, which is included in other current assets, includes the average cost of oil, natural gas, and emissions allowances. Fuel is recorded to inventory when purchased and then expensed, at weighted average cost, as used. Emissions allowances granted by the EPA are included in inventory at zero cost. The traditional electric operating companies recover fuel expense through fuel cost recovery rates approved by each state PSC or, for wholesale rates, the FERC.
Natural Gas for Sale
With the exception of Nicor Gas, Southern Company Gas records natural gas inventories on a weighted average cost basis. In Georgia's deregulated, competitive environment, Marketers sell natural gas to firm end-use customers at market-based prices. On a monthly basis, Atlanta Gas Light assigns to Marketers the majority of the pipeline storage services that it has under contract, along with a corresponding amount of inventory. Atlanta Gas Light retains and manages a portion of its pipeline storage assets and related natural gas inventories for system balancing and to serve system demand.
Nicor Gas' natural gas inventory is carried at cost on a LIFO basis. Inventory decrements occurring during the year that are restored prior to year-end are charged to cost of natural gas at the estimated annual replacement cost. Inventory decrements that are not restored prior to year-end are charged to cost of natural gas at the actual LIFO cost of the inventory layers liquidated. The cost of natural gas, including inventory costs, is recovered from customers under a purchased gas recovery mechanism adjusted for differences between actual costs and amounts billed; therefore, LIFO liquidations have no impact on Southern Company's or Southern Company Gas' net income. At December 31, 2025, the Nicor Gas LIFO inventory balance was $194 million. Based on the average cost of gas purchased in December 2025, the estimated replacement cost of Nicor Gas' inventory at December 31, 2025 was $420 million.
II-125

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Provision for Uncollectible Accounts
See "Recently Adopted Accounting Standards" herein for additional information on the adoption of ASU 2025-05 and the practical expedient related to credit losses.
The customers of the traditional electric operating companies and the natural gas distribution utilities are billed monthly. For the majority of receivables, a provision for uncollectible accounts is established based on historical collection experience and other factors. For the remaining receivables, if the company is aware of a specific customer's inability to pay, a provision for uncollectible accounts is recorded to reduce the receivable balance to the amount reasonably expected to be collected. If circumstances change, the estimate of the recoverability of accounts receivable could change as well. Circumstances that could affect this estimate include, but are not limited to, customer credit issues, customer deposits, and general economic conditions. Customers' accounts are written off once they are deemed to be uncollectible. The Registrants have elected the practical expedient to assume that current conditions as of the balance sheet date will remain unchanged for the remaining life of the asset when estimating expected credit losses. For all periods presented, uncollectible accounts averaged less than 1% of revenues for each Registrant.
Credit risk exposure at Nicor Gas is mitigated by a bad debt rider approved by the Illinois Commission. The bad debt rider provides for the recovery from (or refund to) customers of the difference between Nicor Gas' actual bad debt experience on an annual basis and the benchmark bad debt expense used to establish its base rates for the respective year.
Concentration of Credit Risk
Concentration of credit risk occurs at Atlanta Gas Light for amounts billed for services and other costs to its customers, which consist of 14 Marketers in Georgia (including SouthStar). The credit risk exposure to the Marketers varies seasonally, with the lowest exposure in the non-peak summer months and the highest exposure in the peak winter months. Marketers are responsible for the retail sale of natural gas to end-use customers in Georgia. The functions of the retail sale of gas include the purchase and sale of natural gas, customer service, billings, and collections. The provisions of Atlanta Gas Light's tariff allow Atlanta Gas Light to obtain credit security support in an amount equal to a minimum of two times a Marketer's highest month's estimated bill from Atlanta Gas Light.
Financial Instruments
The traditional electric operating companies and Southern Power use derivative financial instruments to limit exposure to fluctuations in interest rates, the prices of certain fuel purchases, electricity purchases and sales, and occasionally foreign currency exchange rates. Southern Company Gas uses derivative financial instruments to limit exposure to fluctuations in natural gas prices, weather, and interest rates. All derivative financial instruments are recognized as either assets or liabilities on the balance sheets (included in "Other" or shown separately as "Risk Management Activities") and are measured at fair value. See Note 13 for additional information regarding fair value. Substantially all of the traditional electric operating companies', Southern Power's, and Southern Company Gas' bulk energy purchases and sales contracts that meet the definition of a derivative are excluded from fair value accounting requirements because they qualify for the "normal" scope exception and are accounted for under the accrual method. Derivative contracts that qualify as cash flow hedges of anticipated transactions or are recoverable through the traditional electric operating companies' and the natural gas distribution utilities' fuel-hedging programs result in the deferral of related gains and losses in AOCI or regulatory assets and liabilities, respectively, until the hedged transactions occur. Other derivative contracts that qualify as fair value hedges are marked to market through current period income and are recorded on a net basis in the statements of income. Cash flows from derivatives are classified on the statements of cash flows in the same category as the hedged item. See Note 14 for additional information regarding derivatives.
The Registrants offset fair value amounts recognized for multiple derivative instruments executed with the same counterparty under netting arrangements. The Registrants had no outstanding collateral repayment obligations or rights to reclaim collateral arising from derivative instruments recognized at December 31, 2025.
The Registrants are exposed to potential losses related to financial instruments in the event of counterparties' nonperformance. The Registrants have established risk management policies and controls to determine and monitor the creditworthiness of counterparties in order to mitigate their exposure to counterparty credit risk.
Southern Company Gas
Southern Company Gas enters into weather derivative contracts as economic hedges of natural gas revenues in the event of warmer-than-normal weather in the Heating Season. Exchange-traded options are carried at fair value, with changes reflected in natural gas revenues. Non-exchange-traded options are accounted for using the intrinsic value method. Changes in the intrinsic value for non-exchange-traded contracts are also reflected in natural gas revenues in the statements of income.
II-126

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Southern Company Gas enters into transactions to secure transportation capacity between delivery points in order to serve its customers and various markets. NYMEX futures and OTC contracts are used to capture the price differential or spread between the locations served by the capacity to substantially protect the natural gas revenues that will ultimately be realized when the physical flow of natural gas between delivery points occurs. These contracts generally meet the definition of derivatives and are carried at fair value on the balance sheets, with changes in fair value included in earnings in the period of change.
The purchase, transportation, storage, and sale of natural gas are accounted for on a weighted average cost, accrual, or LIFO basis, as appropriate, rather than on the fair value basis utilized for the derivatives used to mitigate the natural gas price risk associated with these transactions. Monthly demand charges are incurred for the contracted storage and transportation capacity and payments associated with asset management agreements, and these demand charges and payments are recognized on the statements of income in the period they are incurred. This difference in accounting methods can result in volatility in reported earnings, even though the economic margin is substantially unchanged from the dates the transactions were consummated.
Comprehensive Income
The objective of comprehensive income is to report a measure of all changes in common stock equity of an enterprise that result from transactions and other economic events of the period other than transactions with owners. Comprehensive income consists of net income attributable to the Registrant, changes in the fair value of qualifying cash flow hedges, and reclassifications for amounts included in net income. Comprehensive income also consists of certain changes in pension and other postretirement benefit plans for Southern Company, Southern Power, and Southern Company Gas.
AOCI (loss) balances, net of tax effects, for Southern Company, Southern Power, and Southern Company Gas were as follows:
Qualifying
Hedges
Pension and
Other
Postretirement
Benefit Plans
Accumulated
Other
Comprehensive
Income (Loss)(*)
(in millions)
Southern Company
Balance at December 31, 2022$(149)$(18)$(167)
Current period change28 (38)(10)
Balance at December 31, 2023(121)(56)(177)
Current period change75 24 99 
Balance at December 31, 2024(46)(32)(78)
Current period change(7)10 3 
Balance at December 31, 2025$(53)$(22)$(75)
Southern Power
Balance at December 31, 2022$(9)$(9)$(18)
Current period change8 (7)1 
Balance at December 31, 2023(1)(16)(17)
Current period change8 7 15 
Balance at December 31, 20247 (9)(2)
Current period change(2)4 2 
Balance at December 31, 2025$5 $(5)$ 
Southern Company Gas
Balance at December 31, 2022$(25)$56 $31 
Current period change1 (16)(15)
Balance at December 31, 2023(24)40 16 
Current period change21 11 32 
Balance at December 31, 2024(3)51 48 
Current period change 3 3 
Balance at December 31, 2025$(3)$54 $51 
(*)May not add due to rounding.
II-127

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Variable Interest Entities
The Registrants may hold ownership interests in a number of business ventures with varying ownership structures. Partnership interests and other variable interests are evaluated to determine if each entity is a VIE. The primary beneficiary of a VIE is required to consolidate the VIE when it has both the power to direct the activities of the VIE that most significantly impact the VIE's economic performance and the obligation to absorb losses or the right to receive benefits from the VIE that could potentially be significant to the VIE. See Note 7 for additional information regarding VIEs.
II-128

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

2. REGULATORY MATTERS
Regulatory Assets and Liabilities
Details of regulatory assets and (liabilities) reflected in the balance sheets at December 31, 2025 and 2024 are provided in the following tables:
Southern CompanyAlabama PowerGeorgia PowerMississippi PowerSouthern Company Gas
(in millions)
At December 31, 2025
AROs(*)
$5,482 $1,644 $3,604 $234 $ 
Retiree benefit plans(*)
2,442 630 836 128 31 
Remaining net book value of retired assets1,052 408 631 13  
Deferred income tax charges962 261 675 25  
Storm damage941  912 29  
Deferred depreciation784 428 356   
Under recovered regulatory clause revenues284 232  24 28 
Software and cloud computing costs248 92 146 7 3 
Environmental remediation(*)
242  13  229 
Vacation pay(*)
242 90 124 12 16 
Loss on reacquired debt203 30 169 4  
Nuclear outage106 59 47   
Regulatory clauses83 52   31 
Qualifying repairs of natural gas distribution systems65    65 
Fuel-hedging (realized and unrealized) losses50 18 18 14  
Long-term debt fair value adjustment44    44 
Plant Daniel Units 3 and 421   21  
Other regulatory assets225 65 30 40 90 
Deferred income tax credits(4,725)(1,585)(2,238)(211)(681)
Other cost of removal obligations(1,022)15 999 (115)(1,921)
Reliability reserves(243)(184) (59) 
Over recovered regulatory clause revenues(213) (31) (182)
Storm/property damage reserves(118)(60) (58) 
Plant Daniel Units 1 and 2 acquisition(34)  (34) 
Other regulatory liabilities(234)(17)(16)(3)(61)
Total regulatory assets (liabilities), net$6,887 $2,178 $6,275 $71 $(2,308)
II-129

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Company
Gas
(in millions)
At December 31, 2024
AROs(*)
$5,810 $1,906 $3,658 $248 $ 
Retiree benefit plans(*)
2,605 680 892 134 44 
Remaining net book value of retired assets1,198 454 729 15  
Deferred income tax charges927 264 634 27  
Storm damage859  827 32  
Deferred depreciation535 286 249   
Environmental remediation(*)
249  16  233 
Vacation pay(*)
224 85 112 12 15 
Loss on reacquired debt219 32 183 4  
Software and cloud computing costs200 76 116 4 4 
Under recovered regulatory clause revenues167 119  17 31 
Regulatory clauses162 82   80 
Nuclear outage92 39 53   
Fuel-hedging (realized and unrealized losses)69 23 29 17  
Qualifying repairs of natural gas distribution systems53    53 
Long-term debt fair value adjustment52    52 
Plant Daniel Units 3 and 423   23  
Other regulatory assets184 42 40 30 72 
Deferred income tax credits(4,536)(1,398)(2,149)(219)(755)
Other cost of removal obligations(1,176)24 816 (170)(1,846)
Over recovered regulatory clause revenues(285)(29)(52) (204)
Reliability reserves(188)(131) (57) 
Storm/property damage reserves(122)(70) (52) 
Nuclear fuel disposal cost recovery(100)(100)   
Other regulatory liabilities(180)(28)(14)(6)(31)
Total regulatory assets (liabilities), net$7,041 $2,356 $6,139 $59 $(2,252)
(*)Generally not earning a return as they are excluded from rate base or are offset in rate base by a corresponding asset or liability.
Unless otherwise noted, the following recovery and amortization periods for these regulatory assets and (liabilities) have been approved by the respective state PSC or regulatory agency:
AROs and other cost of removal obligations – Generally recorded over the related property lives, which may range up to 64 years for Alabama Power, 58 years for Georgia Power, 75 years for Mississippi Power, and 85 years for Southern Company Gas. AROs and other cost of removal obligations are settled and trued up following completion of the related activities. Alabama Power is recovering CCR ARO expenditures over a 38-year period ending in 2054 through Rate CNP Compliance. Georgia Power is recovering CCR ARO expenditures over four-year periods through its ECCR tariff. Mississippi Power is recovering CCR ARO expenditures over a 10-year period ending in 2034 through its ECO Plan. See "Georgia Power – Rate Plans" herein and Note 6 for additional information.
Retiree benefit plans – Recovered and amortized over the average remaining service period, which may range up to 14 years for Alabama Power, Georgia Power, and Mississippi Power and 15 years for Southern Company Gas. Southern Company's balances also include amounts at SCS and Southern Nuclear that are allocated to the applicable regulated utilities. See Note 11 for additional information.
Remaining net book value of retired assets
Alabama Power: Primarily represents the net book value of Plant Gorgas Unit 10 ($387 million at December 31, 2025) being amortized over a remaining period of 12 years (through 2037) and Plant Barry Unit 4 ($32 million at December 31, 2025) being amortized over a remaining period of nine years (through 2034). See "Alabama Power – Environmental Accounting Order" herein for additional information.
Georgia Power: Net book values of Plant Wansley Units 1 and 2 and Plant Hammond Unit 4 (totaling $348 million and $271 million, respectively, at December 31, 2025) are being amortized over a remaining period of 13 years (through 2038) pursuant to the extension of the 2022 ARP. Balance also includes unusable materials and supplies inventories, for which the Georgia PSC will determine a recovery period in a future base rate case. See "Georgia Power – Rate Plans" herein additional information.
Mississippi Power: Represents net book value of certain environmental compliance assets at Plant Watson and Plant Greene County. The retail portion is being amortized over a remaining period of eight years (through 2033), and the wholesale portion is being amortized over a remaining period of nine years (through 2034). See "Mississippi Power – Environmental Compliance Overview Plan" herein for additional information.
II-130

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Deferred income tax charges and credits – Charges are recovered and credits are primarily amortized over the related property lives, which may range up to 64 years for Alabama Power, 58 years for Georgia Power, 75 years for Mississippi Power, and 85 years for Southern Company Gas. See Note 10 for additional information. These accounts include certain deferred income tax assets and liabilities not subject to normalization, as described further below:
Alabama Power: Related amounts at December 31, 2025 include certain tax credits which will be returned to customers in a manner determined by the Alabama PSC, as discussed under "Alabama Power – Nuclear Production Tax Credits Order" herein. Related amounts at December 31, 2024 include excess federal deferred income tax liabilities that were returned for the benefit of customers in 2025, as discussed under "Alabama Power – Excess Accumulated Deferred Income Tax Accounting Order" herein.
Georgia Power: For deferred income tax charges, related amounts include deferred income tax assets related to construction costs for Plant Vogtle Units 3 and 4 ($120 million at December 31, 2025) being recovered over a remaining period of nine years (through 2034). For deferred income tax credits, related amounts at December 31, 2025 include $255 million of deferred income tax benefits for certain tax credits and $39 million of excess state deferred income tax liabilities, which are both expected to be amortized over a period of up to three years (through 2028), and related amounts at December 31, 2024 include $102 million of excess state deferred income tax liabilities that were returned to customers in 2025. See "Georgia Power – Rate Plans" and " – Nuclear Construction – Regulatory Matters" herein for additional information.
Mississippi Power: Related amounts at December 31, 2025 include retail excess federal deferred income tax liabilities of $21 million resulting from the Tax Reform Legislation, the flowback of which will be determined by the Mississippi PSC in a future rate proceeding. See "Mississippi Power – Excess Accumulated Deferred Income Tax Accounting Order" herein for additional information.
Southern Company Gas: Related amounts include deferred income tax liabilities ($26 million at December 31, 2025) being amortized over periods generally not exceeding five years, primarily related to excess state deferred income tax liabilities. See "Southern Company Gas – Rate Proceedings" herein for additional information.
Storm damage – See "Georgia Power – Storm Damage Recovery" herein for additional information. Mississippi Power's balance represents deferred storm costs associated with Hurricanes Ida and Zeta being recovered through PEP over a remaining period of nine years (through 2034).
Deferred depreciation
Alabama Power: Represents deferred depreciation for Plant Barry Unit 5 ($170 million at December 31, 2025) and Plant Barry common coal assets ($73 million at December 31, 2025) to be amortized until 2036 beginning when Alabama Power utilizes updated deprecation rates which is anticipated to be January 1, 2028 and Plant Gaston Unit 5 coal assets ($185 million at December 31, 2025) to be amortized until 2039 beginning when the assets are retired.
Georgia Power: Represents deferred depreciation for Plant Scherer Units 1 through 3 and Plant Bowen Units 1 and 2 (totaling $209 million and $121 million, respectively, at December 31, 2025) to be amortized over 13 years beginning January 1, 2026 (through 2038), both pursuant to the extension of the 2022 ARP, and Plant Vogtle Unit 3 and common facilities ($26 million at December 31, 2025) being amortized over a remaining period of nine years (through 2034). See "Georgia Power – Rate Plans" herein additional information.
Under and over recovered regulatory clause revenues
Alabama Power: Balances are recorded monthly and expected to be recovered over periods of up to five years. See "Alabama Power – Rate CNP PPA," " – Rate CNP Compliance," and " – Rate ECR" herein for additional information.
Georgia Power: Related to Demand-Side Management (DSM) tariffs. Balances are recorded monthly. Pursuant to the extension of the 2022 ARP, the Georgia PSC will determine a recovery period in a future base rate case. See "Georgia Power – Rate Plans" herein for additional information.
Mississippi Power: At December 31, 2025, $11 million is expected to be recovered through various rate recovery mechanisms over a period to be determined in future rate filings. See "Mississippi Power – Ad Valorem Tax Adjustment" herein for additional information.
Southern Company Gas: Balances are recorded and recovered or amortized over periods generally not exceeding five years. In addition to natural gas cost recovery mechanisms, the natural gas distribution utilities have various other cost recovery mechanisms for the recovery of costs, including those related to infrastructure replacement programs.
Software and cloud computing costs – Represents certain deferred operations and maintenance costs associated with software and cloud computing projects. For Alabama Power, costs are amortized ratably over the life of the related software, which ranges up to 10 years (through 2035). For Georgia Power, costs incurred through 2022 are being amortized over five years (through 2027), and the recovery period for costs incurred after 2022 will be determined in its next base rate case. For Mississippi Power, the recovery period will be determined in Mississippi Power's annual PEP filing process following the completion of the projects and is expected to begin no earlier than 2027. For Southern Company Gas, costs are being amortized ratably over the life of the related software, which ranges up to 10 years (through 2035).
Environmental remediation – Effective January 1, 2023, Georgia Power is recovering $5 million annually for environmental remediation under the 2022 ARP. Southern Company Gas' costs are recovered through environmental cost recovery mechanisms when the remediation work is performed. See Note 3 under "Environmental Remediation" for additional information.
Vacation pay – Recorded as earned by employees and recovered as paid, generally within one year. Includes both vacation and banked holiday pay, if applicable.
Loss on reacquired debt – Recovered over either the remaining life of the original issue or, if refinanced, over the remaining life of the new issue. At December 31, 2025, the remaining amortization periods do not exceed 22 years for Alabama Power, 27 years for Georgia Power, 16 years for Mississippi Power, and two years for Southern Company Gas.
Nuclear outage – Costs are deferred to a regulatory asset when incurred and amortized over a subsequent period of 18 months for Alabama Power and up to 24 months for Georgia Power. See Note 5 for additional information.
Regulatory clauses
Alabama Power: Effective January 1, 2023, balance is being amortized through Rate RSE over a five-year period ending in 2027.
Southern Company Gas: Represents amounts related to Nicor Gas' volume balancing adjustment rider expected to be recovered over a period of less than two years.
Qualifying repairs of natural gas distribution systems – Represents deferred costs of certain repairs at Atlanta Gas Light being amortized over 20 years.
Fuel-hedging (realized and unrealized) losses and gains – Assets and liabilities are recorded over the life of the underlying hedged purchase contracts. Upon final settlement, actual costs incurred are recovered through the applicable traditional electric operating company's fuel cost recovery mechanism. Purchase contracts generally do not exceed three and a half years for Alabama Power, three years for Georgia Power, and five years for Mississippi Power. Immaterial amounts for fuel-hedging gains at December 31, 2025 and 2024 are included in other regulatory liabilities. See Note 14 for additional information.
II-131

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Long-term debt fair value adjustment – Recovered over the remaining lives of the original debt issuances at acquisition, which range up to 13 years at December 31, 2025.
Plant Daniel Units 3 and 4 – Represents the difference between Mississippi Power's revenue requirement for Plant Daniel Units 3 and 4 under purchase accounting and operating lease accounting. At December 31, 2025, consists of the $15 million retail portion being amortized through 2046 over the remaining life of the related property and the $7 million wholesale portion being amortized over 10 years (through 2034).
Other regulatory assets – Comprised of numerous immaterial components with remaining amortization periods at December 31, 2025 generally not exceeding 18 years for Alabama Power, nine years for Georgia Power, 10 years for Mississippi Power, and 15 years for Southern Company Gas.
Reliability reserves and storm/property damage reserves – Utilized as related expenses are incurred. See "Alabama Power – Rate NDR" and " – Reliability Reserve Accounting Order," "Georgia Power – Storm Damage Recovery," and "Mississippi Power – System Restoration Rider" and " – Reliability Reserve Accounting Order" herein for additional information.
Plant Daniel Units 1 and 2 acquisition – Represents the incremental cost to Mississippi Power to acquire FP&L's 50% ownership interest in Plant Daniel Units 1 and 2. Utilized as related expenses are incurred. See "Mississippi Power – Plant Daniel" herein for additional information.
Nuclear fuel disposal cost recovery – At December 31, 2024, represents award resulting from litigation related to nuclear fuel disposal costs, of which $93 million was returned to customers through bill credits during the months of January, February, and March 2025 and the remaining $7 million was applied to the NDR balance. See "Alabama Power – Rate NDR" herein and Note 3 under "Nuclear Fuel Disposal Costs" for additional information.
Other regulatory liabilities – Comprised of numerous immaterial components with remaining amortization periods at December 31, 2025 generally not exceeding one year for Alabama Power, three years for Georgia Power, one year for Mississippi Power, and 20 years for Southern Company Gas.
Alabama Power
Alabama Power's revenues from regulated retail operations are collected through various rate mechanisms subject to the oversight of the Alabama PSC. Alabama Power currently recovers its costs from the regulated retail business primarily through Rate RSE, Rate CNP, Rate ECR, and Rate NDR. In addition, the Alabama PSC issues accounting orders to address current events impacting Alabama Power.
On December 5, 2025, the Alabama PSC issued a consent order (December 5th Consent Order) approving a plan to keep retail rates stable through 2027. The related impacts are described under "Rate RSE," "Rate CNP New Plant," "Rate CNP PPA," "Rate CNP Compliance," "Rate ECR," "Rate NDR," and "Nuclear Production Tax Credits Order" herein. Furthermore, the Alabama PSC, as part of its routine oversight of Alabama Power's regulated activities, will monitor factors such as weather, natural disasters, changes in fuel markets, and other significant unforeseen events that may impact this plan. If such events occur, Alabama Power will work with the Alabama PSC to determine a reasonable and responsive course of action under the circumstances.
Renewable Generation Certificate
Through the issuance of a Renewable Generation Certificate (RGC), Alabama Power is authorized by the Alabama PSC to procure renewable capacity and energy and to market the related energy and environmental attributes to customers and other third parties. Under the original RGC, Alabama was authorized to procure up to 500 MWs of renewable capacity and energy. In 2023, the Alabama PSC issued an order approving modifications to Alabama Power's RGC. The modifications authorized Alabama Power to procure an additional 2,400 MWs of renewable capacity and energy by June 14, 2029 and to market the related energy and environmental attributes to customers and other third parties. The modifications also increased the size of allowable renewable projects from 80 MWs to 200 MWs and increased the annual approval limit from 160 MWs to 400 MWs. Through December 31, 2025, Alabama Power has procured solar capacity totaling approximately 670 MWs under the RGC.
Rate RSE
The Alabama PSC has adopted Rate RSE that provides for periodic annual adjustments based upon Alabama Power's projected weighted common equity return (WCER) compared to an allowable range. Rate RSE adjustments are based on forward-looking information for the applicable upcoming calendar year. Rate RSE adjustments for any two-year period, when averaged together, cannot exceed 4.0% and any annual adjustment is limited to 5.0%. When the projected WCER is under the allowed range, there is an adjusting point of 5.98% and eligibility for a performance-based adder of seven basis points, or 0.07%, to the WCER adjusting point if Alabama Power (i) has an "A" credit rating equivalent with at least one of the recognized rating agencies or (ii) is in the top one-third of a designated customer value benchmark survey.
At December 31, 2025 and 2024, Alabama Power's equity ratio was approximately 53.7% and 53.9%, respectively.
Generally, during a year without a Rate RSE upward adjustment, if Alabama Power's actual WCER is between 6.15% and 7.65%, customers will receive 25% of the amount between 6.15% and 6.65%, 40% of the amount between 6.65% and 7.15%, and 75% of the amount between 7.15% and 7.65%. Customers will receive all amounts in excess of an actual WCER of 7.65%. During a year with a Rate RSE upward adjustment, if Alabama Power's actual WCER exceeds 6.15%, customers receive 50% of the amount between 6.15% and 6.90% and all amounts in excess of an actual WCER of 6.90%. Alabama Power's ability to retain a portion of the revenue that causes the actual WCER for a given year to exceed the allowed range positions Alabama Power to address the
II-132

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

pressure on its credit quality, without increasing retail rates under Rate RSE in the near term. There is no provision for additional customer billings should the actual retail return fall below the WCER range.
Retail rates under Rate RSE did not change for 2024 and increased by 4.87%, or $325 million annually, effective with the billing month of January 2025.
For the years ended December 31, 2023, 2024, and 2025, Alabama Power's WCER exceeded 6.15%, resulting in Alabama Power establishing a current regulatory liability of $15 million, $12 million, and $57 million, respectively, for Rate RSE refunds. The $15 million and $12 million regulatory liability at December 31, 2023 and 2024, respectively, was refunded to customers through bill credits in April 2024 and May 2025, respectively. The December 5th Consent Order required Alabama Power to subsequently apply the $57 million regulatory liability to the NDR on December 31, 2025.
On December 1, 2025, Alabama Power made its required annual Rate RSE submission to the Alabama PSC of projected data for calendar year 2026. Projected earnings were within the specified range; therefore, retail rates under Rate RSE remain unchanged for 2026. In addition, pursuant to the December 5th Consent Order, Alabama Power agreed to implement a moratorium on any upward rate adjustments under Rate RSE for 2027.
Jurisdictional Separation Study Order
On June 5, 2025, the Alabama PSC approved an order authorizing Alabama Power to implement changes related to the Jurisdictional Separation Study (JSS) under Rate RSE, which allocates costs between retail and other electric services. For 2026, a revised JSS allocation factor accounts for Alabama Power system capacity previously allocated to wholesale electric services that is being used for retail electric service starting January 1, 2026. In addition, Alabama Power was authorized to establish a regulatory asset to defer certain costs associated with this capacity for 2026, and those costs are estimated to be approximately $100 million. Beginning in 2027, Alabama Power will amortize the regulatory asset on a levelized basis over a period not exceeding 10 years.
Excess Accumulated Deferred Income Tax Accounting Order
In 2022, the Alabama PSC directed Alabama Power to accelerate the amortization of a regulatory liability associated with excess federal accumulated deferred income taxes. Under this order, in 2023, approximately $304 million was returned to customers through bill credits to offset the impact of a January 2023 rate increase under Rate CNP Depreciation.
In 2023, the Alabama PSC issued an order modifying its 2022 order and authorizing Alabama Power to (i) flow back in 2023 approximately $24 million of certain federal excess accumulated deferred income taxes resulting from the Tax Reform Legislation and (ii) make available any remaining balance of excess accumulated deferred income taxes at the end of 2023 for the benefit of customers in 2024 and/or 2025. At December 31, 2023, the remaining balance was $81 million, of which approximately $67 million and $14 million was flowed back in 2024 and 2025, respectively, for the benefit of customers.
Rate CNP New Plant
Rate CNP New Plant allows for recovery of Alabama Power's retail costs associated with newly developed or acquired certificated generating facilities placed into retail service.
In 2020, the Alabama PSC approved a CCN authorizing Alabama Power to complete the acquisition of the Central Alabama Generating Station, which occurred in August 2020. Through May 2023, Alabama Power recovered substantially all costs associated with the Central Alabama Generating Station through Rate RSE, offset by revenues from a power sales agreement. Beginning in July 2022, fuel costs associated with Central Alabama Generating Station are being recovered through Rate ECR. In March 2023, Alabama Power filed Rate CNP New Plant with the Alabama PSC to recover costs associated with the acquisition of the Central Alabama Generating Station. The filing reflected an annual increase in retail revenues of $78 million, or 1.1%, effective with June 2023 billings. On May 24, 2023, the Central Alabama Generating Station was placed into retail service.
The Alabama PSC's 2020 CCN also authorized Alabama Power to construct an approximately 720-MW combined cycle facility at Alabama Power's Plant Barry (Plant Barry Unit 8) and the recovery of estimated in-service costs. On November 1, 2023, the unit was placed in service. In December 2023, Alabama Power filed Rate CNP New Plant with the Alabama PSC to recover the related costs. The filing reflected an annual increase in retail revenues of $91 million, or 1.4%, effective with January 2024 billings.
On August 13, 2025, the Alabama PSC approved Alabama Power's petition for a CCN authorizing Alabama Power to complete the acquisition of the Lindsay Hill Generating Station (879.7 MWs), which had been approved by the FERC on June 6, 2025. The transaction closed on September 30, 2025. As part of the acquisition, Alabama Power assumed an existing power sales agreement under which the full output of the generating facility remains committed to a non-affiliated third party through April 2027. Upon expiration of that agreement, Alabama Power will recover costs associated with the Lindsay Hill Generating Station acquisition
II-133

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

through Rate CNP New Plant, Rate CNP Compliance, Rate ECR, and Rate RSE. The December 5th Consent Order authorized Alabama Power to delay the effective date of the Rate CNP New Plant cost recovery until January 2028 billings. See Note 15 under "Alabama Power" for additional information.
Rate CNP PPA
Rate CNP PPA allows for the recovery of Alabama Power's retail costs associated with certificated PPAs. Revenues for Rate CNP PPA, as recorded on the financial statements, are adjusted for differences in actual recoverable costs and amounts billed in current regulated rates. Accordingly, changes in the billing factors will have no significant effect on Southern Company's or Alabama Power's revenues or net income but will affect annual cash flow. No adjustments to Rate CNP PPA occurred during the period from 2023 through 2025, and, pursuant to the December 5th Consent Order, there will be no adjustments through March 2028 billings. At December 31, 2025 and 2024, Alabama Power had an under recovered Rate CNP PPA balance of $67 million and $84 million, respectively, of which $17 million and $17 million, respectively, is included in other regulatory assets, current and $50 million and $67 million, respectively, is included in other regulatory assets, deferred on Southern Company's and Alabama Power's balance sheets.
Rate CNP Compliance
Rate CNP Compliance allows for the recovery of Alabama Power's retail costs associated with laws, regulations, and other such mandates directed at the utility industry involving the environment, security, reliability, safety, sustainability, or similar considerations impacting Alabama Power's facilities or operations. Rate CNP Compliance is based on forward-looking information and provides for the recovery of these costs pursuant to factors that are calculated and submitted to the Alabama PSC by December 1 with rates effective for the following calendar year. Compliance costs to be recovered include operations and maintenance expenses, depreciation, and a return on certain invested capital. Revenues for Rate CNP Compliance, as recorded on the financial statements, are adjusted for differences in actual recoverable costs and amounts billed in current regulated rates. Accordingly, changes in the billing factors will have no significant effect on Southern Company's or Alabama Power's revenues or net income, but will affect annual cash flow. Changes in Rate CNP Compliance-related operations and maintenance expenses and depreciation generally will have no effect on net income.
In December 2023, November 2024, and November 2025, Alabama Power submitted calculations to the Alabama PSC associated with its cost of complying with governmental mandates for the following calendar year, as provided under Rate CNP Compliance. The 2023 filing reflected a $23 million, or 0.3%, annual decrease effective with January 2024 billings. The 2024 and 2025 filings reflected a projected under recovered retail revenue requirement of $50 million and $44 million, respectively. In December 2024, the Alabama PSC issued a consent order directing Alabama Power to maintain the 2024 Rate CNP Compliance factors in effect through 2025, and, pursuant to the December 5th Consent Order, Alabama Power will continue to maintain those same factors through the billing month of December 2027. Both consent orders specified that any prior year under collected amounts would be deemed recovered before any current year amounts are recovered and any remaining under recovered amounts would be reflected in the subsequent year's filing.
At December 31, 2025 and 2024, Alabama Power had an under recovered Rate CNP Compliance balance of $18 million and $35 million, respectively, which are included in other regulatory assets, deferred on Southern Company's and Alabama Power's balance sheets.
Rate CNP Depreciation
Rate CNP Depreciation allows Alabama Power to recover changes in depreciation resulting from updates to certain depreciation rates, excluding any depreciation recovered through Rate CNP New Plant, Rate CNP Compliance, or costs associated with the capitalization of asset retirement costs. No adjustments to Rate CNP Depreciation have occurred since its implementation effective with January 2023 billings, and no adjustments will occur in 2026.
Rate ECR
Rate ECR recovers Alabama Power's retail energy costs based on an estimate of future energy costs and the current over or under recovered balance. Revenues recognized under Rate ECR and recorded on the financial statements are adjusted for the difference in actual recoverable fuel costs and amounts billed in current regulated rates. The difference in the recoverable fuel costs and amounts billed gives rise to the over or under recovered amounts recorded as regulatory assets or liabilities. Alabama Power, along with the Alabama PSC, continually monitors the over or under recovered cost balance to determine whether an adjustment to billing rates is required. Changes in the Rate ECR factor have no significant effect on Southern Company's or Alabama Power's net income but will impact the related operating cash flows. The Alabama PSC may approve billing rates under Rate ECR of up to 5.910 cents per KWH.
II-134

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

In November 2023, the Alabama PSC approved a decrease to Rate ECR of approximately $126 million annually, effective with December 2023 billings. In May 2024, the Alabama PSC approved a decrease to Rate ECR of approximately $135 million annually, effective with July 2024 billings. In December 2024, the Alabama PSC approved an additional reduction to Rate ECR of $218 million annually, effective with January 2025 billings. Pursuant to the December 5th Consent Order, the currently effective energy cost recovery factor of 2.600 cents per KWH will remain in effect for the billing months of January 2026 through December 2027. Beginning with January 2028 billings, the rate will adjust to 5.910 cents per KWH absent a further order from the Alabama PSC.
At December 31, 2025, Alabama Power's under recovered fuel costs totaled $146 million and is included in other regulatory assets, deferred on Southern Company's and Alabama Power's balance sheets. At December 31, 2024, Alabama Power's over recovered fuel costs totaled $29 million and is included in other regulatory liabilities, current on Southern Company's and Alabama Power's balance sheets. These classifications are based on estimates, which include such factors as weather, generation availability, energy demand, and the price of energy. A change in any of these factors could have a significant impact on the timing of any recovery or return of fuel costs.
Plant Greene County
Alabama Power jointly owns Plant Greene County Units 1 and 2 with an affiliate, Mississippi Power. See Note 5 under "Joint Ownership Agreements" for additional information. Mississippi Power's 2024 IRP includes a schedule to retire Mississippi Power's 40% ownership interest in Plant Greene County Units 1 and 2 by the end of 2028. Alabama Power currently expects to retire Plant Greene County Units 1 and 2 (300 MWs based on 60% ownership) by the end of 2028. Alabama Power and Mississippi Power have continued to evaluate operating conditions and business needs relevant to the anticipated retirement of Plant Greene County Units 1 and 2. The ultimate outcome of this matter cannot be determined at this time. See "Mississippi Power – Integrated Resource Plans" herein for additional information.
Rate NDR
Based on an order from the Alabama PSC, Alabama Power maintains a reserve for operations and maintenance expenses to cover the cost of damages from major storms to its transmission and distribution facilities. The order approves a separate monthly Rate NDR charge to customers consisting of two components. The first component is intended to establish and maintain a reserve balance for future storms and is an on-going part of customer billing. When the reserve balance falls below $50 million, a reserve establishment charge will be activated (and the on-going reserve maintenance charge concurrently suspended) until the reserve balance reaches $75 million.
The second component of the Rate NDR charge is intended to allow recovery of any existing deferred storm-related operations and maintenance costs and any future reserve deficits over a 48-month period. The Alabama PSC order gives Alabama Power authority to record a deficit balance in the NDR when costs of storm damage exceed any established reserve balance. The maximum charge to recover a deficit is $5.00 per month per non-residential customer account and $2.50 per month per residential customer account. Alabama Power has the authority, based on an order from the Alabama PSC, to accrue certain additional amounts as circumstances warrant, which can be used to offset storm charges. Alabama Power made additional accruals of $7 million and $21 million in 2025 and 2024, respectively, and applied the 2025 Rate RSE refund of $57 million to the NDR in accordance with the December 5th Consent Order.
Under Rate NDR, Alabama Power collected approximately $23 million, $12 million, and $12 million in 2025, 2024, and 2023, respectively. Pursuant to orders of the Alabama PSC, Alabama Power applied $7 million of undistributed customer bill credits related to the nuclear fuel disposal costs litigation award to Rate NDR in 2025. Additionally, undistributed customer bill credits of $6 million and $1 million associated with Rate RSE refunds were applied in 2024 and 2023, respectively. Beginning with July 2025 billings, the reserve maintenance charge was suspended and the reserve establishment charge was activated as a result of the NDR balance falling below $50 million. Alabama Power expects to collect approximately $36 million annually under Rate NDR unless the NDR balance exceeds $75 million. At December 31, 2025 and 2024, the NDR balance was $60 million and $70 million, respectively, and is included in other regulatory liabilities, deferred on Southern Company's and Alabama Power's balance sheets. See Note 3 under "Nuclear Fuel Disposal Costs" for additional information regarding the nuclear fuel disposal costs litigation.
As revenue from the Rate NDR charge is recognized, an equal amount of operations and maintenance expenses related to the NDR will also be recognized. As a result, the Rate NDR charge will not have an effect on net income but will impact operating cash flows.
Reliability Reserve Accounting Order
Based on orders from the Alabama PSC, Alabama Power is authorized to maintain a reliability reserve separate from the NDR and to include certain reliability-related transmission and distribution expenses and generation-related expenses intended to
II-135

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

maintain reliability between scheduled generating unit maintenance outages. Alabama Power may make accruals to the reliability reserve if the NDR balance exceeds $35 million.
In 2025, Alabama Power utilized $30 million of the reliability reserve for reliability-related transmission, distribution, and generation expenses and accrued $83 million to the reliability reserve in accordance with procedures established in the reliability reserve accounting order. In 2023 and 2024, Alabama Power utilized a net $23 million and $12 million, respectively, from the reliability reserve for reliability-related transmission, distribution, and generation expenses.
Alabama Power notified the Alabama PSC through its annual RSE filing of its intent to utilize $60 million of its reliability reserve balance in 2026.
At December 31, 2025, Alabama Power's reliability reserve balance was $184 million, of which $60 million is included in other regulatory liabilities, current and $124 million is included in other regulatory liabilities, deferred on Southern Company's and Alabama Power's balance sheets. At December 31, 2024, Alabama Power's reliability reserve balance was $131 million and is included in other regulatory liabilities, deferred on Southern Company's and Alabama Power's balance sheets.
Environmental Accounting Order
Based on an order from the Alabama PSC, Alabama Power is authorized to establish a regulatory asset to record the unrecovered investment costs, including the unrecovered plant asset balance and the unrecovered costs associated with site removal and closure associated with future unit retirements, caused by environmental regulations. The regulatory asset is amortized and recovered over the affected unit's remaining useful life, as established prior to the decision regarding early retirement, through Rate CNP Compliance.
Alabama Power previously indicated plans to retire Plant Barry Unit 5 (700 MWs) by December 31, 2028. However, subsequent to December 31, 2025, as a result of projected future generation needs, a decision was made to convert Plant Barry Unit 5 from coal to natural gas and to continue operating Plant Barry Unit 5 beyond December 31, 2028. As a result, the unit's net book value of approximately $307 million no longer meets the criteria to be considered probable of abandonment. Accordingly, in the first quarter 2026, approximately $307 million will be reclassified from other utility plant, net to plant in service on Alabama Power's and Southern Company's balance sheets.
Nuclear Production Tax Credits Order
On October 7, 2025, the Alabama PSC issued an order authorizing Alabama Power to establish a regulatory liability for nuclear PTCs received through its nuclear generating facilities pursuant to Internal Revenue Code §45U for tax years 2024 through 2032. The §45U PTCs will be deferred as a regulatory liability until the Alabama PSC provides direction on how to apply them for the benefit of customers. For the 2024 tax year, Alabama Power received $180 million in §45U PTCs on Southern Company's consolidated federal income tax return. Pursuant to the December 5th Consent Order, Alabama Power will utilize the 2024 nuclear PTCs, when monetized, to offset retail cost of service in 2027. In addition, the nuclear PTCs generated in 2025, 2026, and 2027, when monetized, will be used to offset future retail cost of service, including any under recovered balances under Rate CNP and Rate ECR. The §45U PTC is subject to a phase-out. As such, Alabama Power will evaluate annually whether it qualifies for the credit. The ultimate outcome of this matter cannot be determined at this time. See Note 10 under "Unrecognized Tax Benefits" for additional information.
Georgia Power
Georgia Power's revenues from regulated retail operations are collected through various rate mechanisms subject to the oversight of the Georgia PSC. Georgia Power recovers its costs from the regulated retail business through traditional base tariffs, DSM tariffs, the ECCR tariff, and Municipal Franchise Fee (MFF) tariffs. These tariffs were set under the 2022 ARP for the years 2023 through 2025 and subsequently extended through 2028 as described herein. In addition, fuel costs are collected through a separate fuel cost recovery tariff.
See "Nuclear Construction – Regulatory Matters" herein for information regarding the approved recovery through retail base rates of certain costs related to Plant Vogtle Unit 3 and the common facilities shared between Plant Vogtle Units 3 and 4 (Common Facilities) that became effective August 1, 2023 based on the in-service date of July 31, 2023 for Unit 3, as well as base rate adjustments for the remaining costs related to Plant Vogtle Units 3 and 4 that became effective May 1, 2024 based on the in-service date of April 29, 2024 for Unit 4. Financing costs on certified construction costs of Plant Vogtle Units 3 and 4 were collected through Georgia Power's NCCR tariff until the inclusion of certified construction costs in rate base. When the base rate adjustments occurred following commercial operation of Unit 4, the NCCR tariff ceased to be collected and financing costs are now included in Georgia Power's general retail revenue requirements. See "Nuclear Construction" herein for additional information on Plant Vogtle Units 3 and 4.
II-136

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Rate Plans
In November 2023 and December 2024, the Georgia PSC approved the following tariff adjustments under the 2022 ARP effective January 1, 2024 and 2025, respectively:
Tariff20242025
(millions)
Traditional base(a)
$275 $194 
ECCR(99)126 
DSM10 (22)
MFF5 9 
Total(b)
$191 $306 
(a)For 2025, net of $122 million related to the Georgia state tax rate reduction.
(b)Totals may not add due to rounding.
On July 1, 2025, the Georgia PSC approved a settlement agreement among Georgia Power, the staff of the Georgia PSC, and certain intervenors to extend the 2022 ARP for an additional three-year term through December 31, 2028 (ARP Extension). Under the ARP Extension, base rates will not be adjusted in 2026, 2027, or 2028 (ARP Extension Period) except for reasonable and prudent storm damage costs incurred through December 31, 2025, which will be determined in a separate regulatory proceeding. The ARP Extension includes, among other things, the following modifications to the 2022 ARP:
Storm damage costs will be included in a separate regulatory proceeding to be filed no later than July 1, 2026 to recover the actual reasonable and prudent storm costs incurred through December 31, 2025. Subject to Georgia PSC approval, new rates would be effective approximately 90 days after the filing is made. The Georgia PSC will determine the period over which any such storm damage costs will be recovered.
Amortization of regulatory assets and liabilities in the 2022 ARP, which were subsequently included in current rates through annual compliance filings, will continue through the ARP Extension Period. This includes those regulatory asset and liability balances that were projected to be fully amortized through 2025 or during the ARP Extension Period.
The amounts previously deferred during the 2022 ARP for ITCs and PTCs will be amortized through the ARP Extension Period. The acceleration of amortization during the ARP Extension Period is subject to the Internal Revenue Code normalization rules and other guidance (if any) released by the IRS. Certain amounts of ITCs generated during the ARP Extension Period will be amortized over five years, and additional ITC amounts will be deferred to a regulatory liability during the ARP Extension Period. Sixty percent (60%) of PTC benefits generated (excluding PTCs generated under Internal Revenue Code §45J) during the ARP Extension Period will be credited to income tax expense as generated. The remaining forty percent (40%) will be deferred to a regulatory liability.
The period for depreciation and amortization related to certain generating plants and net book values of retired generating plants will be 13 years effective January 1, 2026.
In the 2022 ARP, the Georgia PSC approved recovery through the ECCR tariff of estimated CCR ARO compliance costs for 2024 and 2025 over four-year periods beginning January 1 of each respective year, with recovery of construction contingency beginning in the year following actual expenditures, resulting in a reduction of $60 million in the related amortization for 2024 and an increase of $123 million in the related amortization for 2025. Under the ARP Extension, the amortization will not change for 2026 through 2028. Compliance costs incurred were $300 million, $265 million, and $315 million in 2023, 2024, and 2025, respectively.
Further, under the 2022 ARP and the ARP Extension, Georgia Power's retail ROE is set at 10.50% and its equity ratio is set at 56%. Earnings are evaluated against a retail ROE range of 9.50% to 11.90%. Any earnings above 11.90% retail ROE will be subject to sharing whereby 40% of earnings above the band would be applied to regulatory assets, 40% would be directly refunded to customers, and the remaining 20% would be retained by Georgia Power. There will be no recovery of any earnings shortfall below 9.50% retail ROE on an actual basis. However, if at any time during the term of the 2022 ARP and the ARP Extension Period, Georgia Power projects that its retail earnings will be less than the lower end of the approved retail ROE range for any calendar year, it may petition the Georgia PSC for implementation of the Interim Cost Recovery (ICR) tariff to adjust Georgia Power's retail rates to achieve a retail ROE equal to the lower end of the approved retail ROE range. The Georgia PSC would have 90 days to rule on Georgia Power's request. Any ICR tariff would expire at the earlier of January 1, 2029 or the end of the calendar year in which the ICR tariff becomes effective. In lieu of requesting implementation of an ICR tariff, or if the Georgia PSC chooses not to implement an ICR tariff, Georgia Power may file a full base rate case. In 2023, 2024, and 2025, Georgia Power's retail ROE was within the allowed retail ROE range.
II-137

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Except as provided above, Georgia Power will not file a base rate increase while the ARP Extension is in effect. Georgia Power is required to file a general base rate case by July 1, 2028, in response to which the Georgia PSC would be expected to determine whether the 2022 ARP should be continued, modified, or discontinued.
Integrated Resource Plans
2025 IRP
On July 15, 2025, the Georgia PSC approved Georgia Power's triennial IRP (2025 IRP), as modified by a stipulation among Georgia Power, the staff of the Georgia PSC, and certain intervenors. In the 2025 IRP decision, the Georgia PSC approved the following requests:
Extended operation of Plant Scherer Unit 3 (614 MWs based on 75% ownership) through at least December 31, 2035 and Plant Gaston Units 1 through 4 (500 MWs based on 50% ownership through SEGCO) through December 31, 2034. See Note 7 under "SEGCO" for additional information.
Installation of environmental controls and natural gas co-firing at Plant Bowen Units 1 through 4 (3,160 MWs), Plant Scherer Units 1 and 2 (137 MWs based on 8.4% ownership), and Plant Scherer Unit 3 for compliance with both ELG supplemental rules and GHG rules.
Upgrades to Plant McIntosh Units 10 and 11 (1,319 MWs) for a projected 194 MWs of incremental capacity by 2028 and Plant McIntosh Units 1 through 8 (640 MWs) for a projected 74 MWs of incremental capacity by 2033.
Upgrades to Plant Vogtle Units 1 and 2 (1,060 MWs based on 45.7% ownership) for a projected 54 MWs of incremental capacity, some of which could be available as early as 2028.
Investments related to the continued reliable operations of four hydro facilities, as well as the authority to spend up to $25 million to undertake engineering studies related to two additional hydro facilities.
RFP for at least 1,100 MWs of utility scale and distributed generation renewable resources.
Issuance of a capacity RFP to procure resources to meet capacity needs in 2032 and 2033.
Strategic power delivery infrastructure plan necessary to help ensure adequate reliability and serve the projected future load growth projected in Georgia.
Certification of approximately 187 MWs of wholesale capacity associated with Plant Scherer Unit 3 to be placed in retail rate base, some of which will be available beginning in 2026.
In addition, the 2025 IRP assumes Plant Bowen Units 1 and 2 will operate through at least the end of 2035.
Certification Requests
On September 4, 2025, the Georgia PSC approved Georgia Power's request to certify a Georgia Power-owned battery energy storage facility with a capacity of 200 MWs and a projected COD in 2027.
On December 19, 2025, the Georgia PSC approved Georgia Power's request, as modified by a stipulation between Georgia Power and the staff of the Georgia PSC (Certification Stipulation), to certify the following resources totaling 9,885 MWs:
18 resources selected from the RFP pursuant to the 2022 IRP final order, totaling 7,999 MWs, which consist of four PPAs (including two affiliate PPAs with Southern Power that are subject to approval by the FERC) with capacity totaling 1,195 MWs commencing between 2028 and 2030, three project sites consisting of five Georgia Power-owned combined cycle units with capacity totaling 3,692 MWs and projected CODs commencing between 2029 and 2030, nine Georgia Power-owned battery energy storage facilities with capacity totaling 2,762 MWs and projected CODs commencing between 2028 and 2030, and two Georgia Power-owned battery energy storage facilities with solar with capacity totaling 350 MWs and projected CODs commencing in 2028.
Extension of 50 MWs of an existing 750-MW affiliate PPA with Mississippi Power for an additional year through December 31, 2029.
A 20-year non-affiliate PPA for 930 MWs commencing in 2030 and five 25-year non-affiliate PPAs totaling 646 MWs commencing in 2027.
Construction of a 260-MW Georgia Power-owned battery energy storage facility with a projected COD in 2027 to be paired with an existing non-affiliate solar PPA.
Pursuant to the Certification Stipulation, Georgia Power has agreed to file its next base rate case in a manner that will ensure the incremental revenue from large load customers has downward pressure, on a levelized basis, of at least $556 million per year for the years 2029, 2030, and 2031.
II-138

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

The approved certification requests in September and December 2025 associated with these Georgia Power-owned projects and related transmission investments total approximately $16.7 billion, excluding AFUDC.
As required by the 2025 IRP decision, Georgia Power filed with the Georgia PSC on September 17, 2025 an updated load forecast to support the certification requests from the RFP of up to 8,500 MWs.
As included in the 2022 IRP final order, on February 11, 2026, Georgia Power initiated an RFP for up to 500 MWs of capacity for battery energy storage facilities with projected CODs or delivery commencement dates by 2031.
See "2025 IRP" and "Other Construction" herein for additional information.
Transmission Asset Sales
In March 2024, the FERC approved the sale of transmission line assets under the integrated transmission system agreement, with a net book value of $236 million. In April 2024, the sale, with a purchase price of $351 million, was completed resulting in a pre-tax gain of approximately $114 million ($84 million after tax) recorded in 2024.
Fuel Cost Recovery
Georgia Power has established fuel cost recovery rates approved by the Georgia PSC. During 2022, Georgia Power's under recovered fuel balance increased significantly due to higher fuel and purchased power costs. In 2023, the Georgia PSC approved a stipulation between Georgia Power and the staff of the Georgia PSC to increase annual fuel billings by 54%, or approximately $1.1 billion, effective June 1, 2023. The increase includes a three-year recovery period for $2.2 billion of Georgia Power's under recovered fuel balance at May 31, 2023. Under the approved stipulation, Georgia Power is allowed to adjust its fuel cost recovery rates under an interim fuel rider (IFR) prior to the next fuel case, subject to a maximum 40% cumulative change, if its under or over recovered fuel balance accumulated since May 31, 2023 exceeds $200 million (IFR Threshold). On May 14, 2025, Georgia Power submitted an IFR notification and plan informing the Georgia PSC that Georgia Power's under recovered fuel balance exceeded the IFR Threshold. Georgia Power proposed no fuel cost recovery rate change and was required to monitor and report to the Georgia PSC monthly as long as the under recovered fuel balance was above the IFR Threshold. Georgia Power filed an IFR notification and plan monthly through September 2025, each of which also proposed no fuel cost recovery rate change. Between September 30, 2025 and November 30, 2025, Georgia Power's under recovered fuel balance did not exceed the IFR Threshold. On each of January 15, 2026 and February 13, 2026, Georgia Power filed an IFR notification and plan informing the Georgia PSC that Georgia Power's under recovered fuel balance exceeded the IFR Threshold as of December 31, 2025 and January 31, 2026, respectively, and proposed no fuel cost recovery rate change. On February 17, 2026, Georgia Power filed a request with the Georgia PSC to decrease fuel rates by 12.6% effective June 1, 2026, which is expected to reduce annual billings by approximately $388 million. Georgia Power expects the Georgia PSC to make a final decision on this matter on May 28, 2026. The ultimate outcome of this matter cannot be determined at this time.
Georgia Power's under recovered fuel balance totaled $522 million at December 31, 2025, of which $310 million is included in under recovered fuel clause revenues and under recovered retail fuel clause revenues on Southern Company's and Georgia Power's balance sheets, respectively, and $212 million is included in deferred under recovered retail fuel clause revenues on Southern Company's and Georgia Power's balance sheets. The under recovered fuel balance totaled $1.2 billion at December 31, 2024, of which $713 million is included in under recovered fuel clause revenues and under recovered retail fuel clause revenues on Southern Company's and Georgia Power's balance sheets, respectively, and $453 million is included in deferred under recovered retail fuel clause revenues on Southern Company's and Georgia Power's balance sheets.
Georgia Power's fuel cost recovery mechanism includes costs associated with a natural gas hedging program, as revised and approved by the Georgia PSC, allowing the use of an array of derivative instruments within a 36-month time horizon.
Fuel cost recovery revenues as recorded on the financial statements are adjusted for differences in actual recoverable fuel costs and amounts billed in current regulated rates. Accordingly, changes in the billing factor will not have a significant effect on Southern Company's or Georgia Power's revenues or net income but will affect operating cash flows.
Storm Damage Recovery
Georgia Power defers and recovers certain costs related to damages to its transmission and distribution facilities resulting from major storms as mandated by the Georgia PSC. Beginning January 1, 2023, Georgia Power is recovering $31 million annually under the 2022 ARP. During September 2024, Hurricane Helene caused significant damage to Georgia Power's transmission and distribution facilities. The incremental restoration costs related to this hurricane totaled approximately $880 million, of which approximately $780 million was deferred in the regulatory asset for storm damage, approximately $75 million was capitalized to property, plant, and equipment, and approximately $25 million was deferred and subsequently billed in 2025 to open access transmission tariff customers. At December 31, 2025 and 2024, Georgia Power's regulatory asset balance related to storm damage was $912 million and $827 million, respectively, of which $31 million for each year is included in other regulatory assets, current
II-139

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

and $880 million and $795 million, respectively, is included in other regulatory assets, deferred on Southern Company's and Georgia Power's balance sheets.
Pursuant to the ARP Extension, on February 17, 2026, Georgia Power filed a request with the Georgia PSC to recover the reasonable and prudent storm costs incurred through December 31, 2025, which is expected to increase annual recovery by approximately $300 million effective June 1, 2026. The proposed annual recovery included in the filing is expected to fully recover the regulatory asset balance related to storm damage at December 31, 2025 over four years, and the remaining balance at December 31, 2028 will be included in the next rate case. Georgia Power expects the Georgia PSC to make a final decision on this matter on May 28, 2026. The ultimate outcome of this matter cannot be determined at this time. See "Rate Plans" herein for additional information.
The rate of storm damage cost recovery is expected to be further adjusted in future regulatory proceedings as necessary. As a result of this regulatory treatment, costs related to storms are not expected to have a material impact on Southern Company's or Georgia Power's net income but do impact the related operating cash flows.
Nuclear Construction
See Note 8 under "Long-term Debt – DOE Loan Guarantee Borrowings" for information on the Amended and Restated Loan Guarantee Agreement, including applicable covenants, events of default, and mandatory prepayment events.
Cost and Schedule
Georgia Power placed Plant Vogtle Units 3 and 4 (553 MWs each based on 45.7% ownership) in service on July 31, 2023 and April 29, 2024, respectively. During the third quarter 2025, following the completion of site demobilization efforts, Southern Nuclear evaluated the remaining contractor obligations and reduced the remaining estimate to complete forecast by approximately $33 million. During the fourth quarter 2025, Southern Nuclear finalized the remaining contractor obligations and reduced the remaining estimate to complete forecast, including the impact of joint owner cost-sharing described below, by approximately $27 million. Accordingly, Georgia Power recorded pre-tax credits to income of approximately $33 million ($25 million after tax) and $27 million ($20 million after tax) in the third quarter 2025 and the fourth quarter 2025, respectively, to recognize capital costs previously charged to income. Georgia Power's final net investment in connection with Plant Vogtle Units 3 and 4 is $10.670 billion, which excludes capitalized AFUDC of approximately $440 million accrued through Unit 4's in-service date.
Georgia Power previously reached agreements with MEAG Power, OPC, and Dalton to resolve its respective dispute with each regarding the cost-sharing and tender provisions of the joint ownership agreements, as amended (Vogtle Joint Ownership Agreements). Under the terms of these agreements, among other items, Georgia Power reimbursed a portion of MEAG Power's, OPC's, and Dalton's costs of construction for Plant Vogtle Units 3 and 4 as such costs were incurred and with no further adjustment for force majeure costs, which payments (including amounts paid to date) totaled approximately $86 million, $82 million, and $4.4 million for MEAG Power, OPC, and Dalton, respectively, based on the final project capital cost. Georgia Power also reimbursed 20% of MEAG Power's costs of construction and 66% of each of OPC's and Dalton's costs of construction with respect to amounts over the final project capital cost, with no further adjustment for force majeure costs. Georgia Power recorded pre-tax charges to income through 2024 of $559 million ($418 million after tax) and a pre-tax credit to income in the fourth quarter 2025 of $22 million ($17 million after tax) associated with the cost-sharing provisions of the Vogtle Joint Ownership Agreements, including the settlements with the other Vogtle Owners described above. These charges are included in the total project capital cost and will not be recovered from retail customers.
Regulatory Matters
In 2021, the Georgia PSC approved an order under which Georgia Power would include in rate base an allocation of $2.1 billion to Plant Vogtle Unit 3 and the Common Facilities from the $3.6 billion of Plant Vogtle Units 3 and 4 costs previously deemed prudent by the Georgia PSC and would recover the related depreciation through retail base rates effective the month after Unit 3 is placed in service. In compliance with the Georgia PSC order, Georgia Power increased annual retail base rates by $318 million effective August 1, 2023 based on the in-service date of July 31, 2023 for Unit 3. The related increase in annual retail base rates included recovery of all projected operations and maintenance expenses for Unit 3 and the Common Facilities and other related costs of operation, partially offset by the related PTCs.
In 2023, the Georgia PSC approved Georgia Power's application to adjust rates to include reasonable and prudent Plant Vogtle Units 3 and 4 costs as modified by the related stipulation (Prudency Stipulation) among Georgia Power, the staff of the Georgia PSC, and certain intervenors.
Under the terms of the approved Prudency Stipulation, Georgia Power is recovering $7.562 billion in total construction and capital costs and associated retail rate base items of $1.02 billion, which includes AFUDC financing costs above $4.418 billion (the Georgia PSC-certified amount) up to $7.562 billion. Georgia Power is also recovering projected operations and maintenance
II-140

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

expenses, depreciation, nuclear decommissioning accruals, and property taxes, net of projected PTCs. After considering construction and capital costs already in retail base rates of $2.1 billion and $362 million of associated retail rate base items for Unit 3 and Common Facilities (approved by the Georgia PSC in 2021), Georgia Power included in retail rate base the remaining $5.462 billion of construction and capital costs as well as $647 million of associated retail rate base items effective with the April 29, 2024 in-service date for Unit 4. Annual retail base revenues increased approximately $730 million and the average retail base rates were adjusted by approximately 5% (net of the elimination of the NCCR tariff described below) effective May 1, 2024.
Reductions to the ROE used to calculate the NCCR tariff (pursuant to prior Georgia PSC orders) negatively impacted earnings by approximately $80 million through the second quarter 2024 and $310 million in 2023. Further, as included in the approved Prudency Stipulation, since commercial operation for Unit 4 was not achieved by March 31, 2024, Georgia Power's ROE used to determine the NCCR tariff and calculate AFUDC was reduced to zero effective April 1, 2024, which resulted in a negative impact to earnings of approximately $10 million (for one month) in the second quarter 2024 based on the April 29, 2024 in-service date. Effective May 1, 2024, following commercial operation of Unit 4, Georgia Power's NCCR tariff was eliminated and financing costs are included in Georgia Power's general retail revenue requirements.
As of each Unit's respective first refueling outage, if the respective Unit's performance has materially deviated from expected performance, the Georgia PSC may order Georgia Power to credit customers for operations and maintenance expenses or disallow costs associated with the repair or replacement of any system, structure, or component found to have caused the material deviation in performance if proven to be the result of imprudent engineering, construction, procurement, testing, or start-up. Unit 3 demonstrated high performance and reliability during the first 14 months of operation leading up to its first refueling outage, which took place in the fall of 2024. Unit 4 also demonstrated high performance and reliability during the first 16 months of operation leading up to its first refueling outage, which took place in the fall of 2025. No customer credits for operations and maintenance expenses or performance-related disallowances were recorded.
The approval of the Prudency Stipulation resolved all issues for determination by the Georgia PSC regarding the reasonableness, prudence, and cost recovery for the remaining Plant Vogtle Units 3 and 4 construction and capital costs not already in retail base rates.
As a result of the Georgia PSC's approval of the Prudency Stipulation, Georgia Power recorded a pre-tax credit to income of approximately $228 million ($170 million after tax) in the fourth quarter 2023 to recognize CWIP costs previously charged to income, which are now recoverable through retail rates. Associated AFUDC on these costs, which totaled approximately $14 million, was also recognized.
Other Construction
At December 31, 2025, Georgia Power had recorded approximately $3.1 billion of combined capital costs, excluding AFUDC, for the projects reflected in the table below approved through the 2023 IRP Update and the approved certification requests in September and December 2025. The total certified amounts related to these projects are approximately $19.5 billion, excluding
II-141

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

AFUDC. Georgia Power is required to file periodic construction monitoring reports with the Georgia PSC through commercial operation. The ultimate outcome of these matters cannot be determined at this time.
Resource/Project
Approximate Nameplate Capacity
(MW)
Projected COD
Projects Under Construction at December 31, 2025
Battery Energy Storage
McGrau Ford Phase 1
265Fourth quarter 2026
Twiggs County200Fourth quarter 2027
Wadley260Fourth quarter 2027
Plant Bowen Phase 1250Fourth quarter 2028
Plant Bowen Phase 2250Fourth quarter 2029
South Hall250Fourth quarter 2028
Plant Wansley500Fourth quarter 2028
Plant Yates Phase 1 320Fourth quarter 2028
Plant Yates Phase 2 250Fourth quarter 2028
Thomson500Fourth quarter 2029
Hammond Phase 2193Fourth quarter 2030
Plant McIntosh250Fourth quarter 2030
Various facilities500Second quarter 2026 through fourth quarter 2026
Solar with Battery Energy Storage
Laurens County 200Fourth quarter 2028
Plant Mitchell 150Fourth quarter 2028
Combined Cycle
Plant Bowen Unit 7741Fourth quarter 2029
Plant Bowen Unit 8741Second quarter 2030
Plant McIntosh Unit 12757Fourth quarter 2030
Plant Wansley Unit 10727Fourth quarter 2029
Plant Wansley Unit 11727Second quarter 2030
Combustion Turbine
Plant Yates Unit 8(*)
442Fourth quarter 2026
Plant Yates Unit 9(*)
442Second quarter 2027
Plant Yates Unit 10(*)
442Third quarter 2027
(*)Pursuant to the 2023 IRP Update, cost recovery over the certified amount is limited.
Mississippi Power
Mississippi Power's rates and charges for service to retail customers are subject to the regulatory oversight of the Mississippi PSC. Mississippi Power's rates are a combination of base rates and several separate cost recovery clauses for specific categories of costs. These separate cost recovery clauses address such items as fuel and purchased power, ad valorem taxes, property damage, and the costs of compliance with environmental laws and regulations. Recoverable costs not addressed through one of the specific cost recovery clauses are expected to be recovered through Mississippi Power's base rates.
Performance Evaluation Plan
Mississippi Power's retail base rates generally are set under the PEP, a rate plan approved by the Mississippi PSC. In recognition that Mississippi Power's long-term financial success is dependent upon how well it satisfies its customers' needs, PEP includes performance indicators that directly tie customer service indicators to Mississippi Power's allowed ROE. PEP measures Mississippi Power's performance on a 10-point scale as a weighted average of results in three areas: average customer price, as compared to prices of other regional utilities (weighted at 40%); service reliability, measured in percentage of time customers had electric service (40%); and customer satisfaction, measured in a survey of residential customers (20%). Typically, two PEP filings are made for each calendar year: the PEP preliminary report filing in November of the preceding year and the PEP Evaluation Report, which includes the current year PEP projected filing and the previous year PEP lookback filing, filed in March of the subsequent year. The annual PEP preliminary report filing is an informational report indicating whether a revenue adjustment is needed for the preceding year. The annual PEP projected filings utilize a historic test year adjusted for "known and measurable" changes and discounted cash flow and regression formulas to determine base ROE. The PEP lookback filing reflects the actual revenue requirement.
II-142

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

In June 2023 and June 2024, the Mississippi PSC approved Mississippi Power's annual retail PEP filings for 2023 and 2024, respectively, with no change in retail rates. On June 17, 2025, the Mississippi PSC approved Mississippi Power's annual retail PEP filing for 2025, resulting in an annual increase in revenues of approximately 4.0%, or $41 million, primarily due to increases in investment and depreciation. In accordance with the PEP rate schedule, an increase of 2.0% of total retail revenues, or approximately $22 million, became effective with the first billing cycle of April 2025, and the remaining approximately $19 million became effective with the first billing cycle of July 2025.
On November 17, 2025, Mississippi Power submitted its annual preliminary retail PEP filing for 2026 to the Mississippi PSC, which requested a 1.8%, or $20 million, annual increase in revenues. In accordance with the PEP rate schedule, the rate increase became effective with the first billing cycle of January 2026, subject to refund. The Mississippi PSC is expected to render a final decision in the second quarter 2026. The ultimate outcome of this matter cannot be determined at this time.
Integrated Resource Plans
In 2023, Mississippi Power signed an affiliate PPA with Georgia Power for 750 MWs of capacity, which began January 1, 2024 and will continue through December 31, 2028. On July 8, 2025, Mississippi Power extended 50 MWs of its affiliate PPA with Georgia Power for an additional year through December 31, 2029. See "Georgia Power – Integrated Resource Plans – Certification Requests" herein for additional information.
In April 2024, Mississippi Power filed its 2024 IRP with the Mississippi PSC. The Mississippi PSC did not note any deficiencies within the prescribed 120-day review period; therefore, the filing was concluded. The 2024 IRP included a schedule to retire Plant Watson Unit 4 (268 MWs) and Plant Greene County Units 1 and 2 (206 MWs based on 40% ownership) and to retire early Plant Daniel Units 1 and 2 (502 MWs based on 50% ownership), all by the end of 2028, which is consistent with the completion of the initial term of Mississippi Power's affiliate PPA with Georgia Power. On January 9, 2025, Mississippi Power notified the Mississippi PSC of its intent to extend the retirement date of Plant Daniel Unit 2 and potentially extend the retirement dates of other fossil steam units beyond their current 2028 retirement dates in order to serve recently signed economic development loads of approximately 600 MWs. Mississippi Power has since acquired FP&L's 50% ownership interest in Plant Daniel Units 1 and 2 as described under "Plant Daniel" herein. In 2026, in compliance with its IRP requirements, Mississippi Power is expected to file a mid-point update to its 2024 IRP with the Mississippi PSC.
On February 12, 2026, Mississippi Power filed a request with the Mississippi PSC to convert Plant Daniel Unit 2 from a coal-fired unit to a natural gas-fired unit. Conversion of the unit is projected to be completed in 2029.
The remaining net book value of Plant Daniel Units 1 and 2 was approximately $465 million at December 31, 2025, and Mississippi Power is continuing to depreciate these units using the current approved rates. Mississippi Power expects to reclassify the net book value remaining at retirement to a regulatory asset to be amortized over a period to be determined by the Mississippi PSC in future proceedings, consistent with a 2020 order. The Plant Watson and Plant Greene County units are expected to be fully depreciated upon retirement.
The ultimate outcome of these matters cannot be determined at this time.
Plant Daniel
In November 2024, Mississippi Power entered into an agreement with FP&L to acquire FP&L's 50% ownership interest in Plant Daniel Units 1 and 2. On January 7, 2025, the Mississippi PSC approved Mississippi Power's request for (i) the inclusion of the acquired assets and the associated costs at Plant Daniel in Mississippi Power's retail rate base, upon completion of the transaction, (ii) the establishment of a new regulatory liability account in which all of the proceeds to be paid by FP&L will be recorded, and (iii) Mississippi Power's ability to amortize that regulatory liability by charging certain expenditures against it. On June 19, 2025, the Florida PSC issued a final order approving the transfer of FP&L's 50% ownership interest in Plant Daniel Units 1 and 2 to Mississippi Power. On July 30, 2025, Mississippi Power completed the acquisition of FP&L's 50% ownership interest in Plant Daniel Units 1 and 2 and, as part of the acquisition, received approximately $36 million from FP&L, which was recorded as a regulatory liability being amortized to offset incremental costs as authorized by the Mississippi PSC. As part of the agreement, FP&L retained responsibility for environmental remediation and decommissioning liabilities related to its prior ownership interest.
Environmental Compliance Overview Plan
The Mississippi PSC has authorized Mississippi Power to defer in a regulatory asset for future recovery all plant retirement- or partial retirement-related costs resulting from environmental regulations.
In April 2023, May 2024, and April 2025, the Mississippi PSC approved Mississippi Power's annual ECO Plan filings, resulting in increases in revenues of approximately $3 million annually effective with the first billing cycle of May 2023, $9 million
II-143

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

annually effective with the first billing cycle of June 2024, and $6 million annually effective with the first billing cycle of May 2025, respectively.
On February 13, 2026, Mississippi Power submitted its annual ECO Plan filing to the Mississippi PSC, which requested a $2 million annual increase in revenues. The ultimate outcome of this matter cannot be determined at this time.
Fuel Cost Recovery
Mississippi Power annually establishes, and is required to file for an adjustment to, the retail fuel cost recovery factor that is approved by the Mississippi PSC. In February 2024, the Mississippi PSC approved Mississippi Power's request to increase retail fuel revenues by $18 million annually effective with the first billing cycle of March 2024. The approved filing included the deferral of approximately $61 million of under recovered fuel costs as of October 2023. On January 7, 2025, the Mississippi PSC approved Mississippi Power's request for no change in retail fuel revenues effective with the first billing cycle of February 2025. The approved filing included the deferral of approximately $25 million of under recovered fuel costs as of October 2024. On January 13, 2026, the Mississippi PSC approved Mississippi Power's request to increase retail fuel revenues by $40 million annually effective with the first billing cycle of February 2026. The approved filing included the deferral of approximately $31 million of under recovered fuel costs as of October 2025, which is expected to be included in Mississippi Power's next fuel filing. Mississippi Power will continue to accrue its weighted-average cost of capital on any under or over fuel recovery balance.
At December 31, 2025, Mississippi Power had $40 million of deferred under recovered retail fuel clause revenues related to higher recoverable fuel costs and its fuel-hedging program on its balance sheet. At December 31, 2024, Mississippi Power had $32 million of deferred under recovered retail fuel clause revenues primarily associated with its fuel-hedging program and $32 million of over recovered retail fuel clause revenues primarily related to lower recoverable fuel costs on its balance sheet. See Note 1 under "Fuel Costs" for additional information.
Mississippi Power has wholesale MRA and Market Based (MB) fuel cost recovery factors. Effective with the first billing cycles for January 2024, 2025, and 2026, annual revenues under the wholesale MRA fuel rate decreased $4 million, decreased $19 million, and increased $23 million, respectively. At December 31, 2025 and 2024, wholesale MRA fuel costs were under recovered $6 million and over recovered $19 million, respectively, and were included in other current assets and other current liabilities, respectively, on Mississippi Power's balance sheets. The wholesale MB fuel rate did not change materially in any period presented. The wholesale MB fuel cost recovery was immaterial for both periods presented.
Mississippi Power's operating revenues are adjusted for differences in actual recoverable fuel cost and amounts billed in accordance with the currently approved cost recovery rate. Accordingly, changes in the billing factor should have no significant effect on Mississippi Power's revenues or net income but will affect operating cash flows.
Ad Valorem Tax Adjustment
Mississippi Power annually establishes an ad valorem tax adjustment factor that is approved by the Mississippi PSC. Any changes are not expected to have a significant effect on Mississippi Power's net income but will affect operating cash flows. Effective with the first billing cycle of June 2023, July 2024, and September 2025, the Mississippi PSC approved changes in annual revenues collected through the ad valorem tax adjustment factor resulting in a $7 million decrease, a $5 million decrease, and a $7 million increase, respectively.
System Restoration Rider
Mississippi Power carries insurance for the cost of certain types of damage to generation plants and general property. However, Mississippi Power is self-insured for the cost of storm, fire, and other uninsured casualty damage to its property, including transmission and distribution facilities. As permitted by the Mississippi PSC and the FERC, Mississippi Power accrues for the cost of such damage through an annual expense accrual which is credited to regulatory liability accounts for the retail and wholesale jurisdictions. The cost of repairing actual damage resulting from such events that individually exceed $50,000 is charged to the reserve. Every year, the Mississippi PSC, the MPUS, and Mississippi Power agree on SRR revenue level(s). In the event the expected annual charges exceed the annual accrual or the target balance has been met, Mississippi Power and the Mississippi PSC will determine the appropriate change to the annual accrual. Additionally, if PEP earnings are above a certain threshold, Mississippi Power has the ability to apply any required PEP refund as an additional accrual to the property damage reserve in lieu of customer refunds.
Mississippi Power's net retail SRR accrual, which includes carrying costs and previously included amortization of related excess deferred income tax benefits, was $13.5 million in 2025, $12.6 million in 2024, and $11.7 million in 2023. At December 31, 2025 and 2024, the retail property damage reserve balance was $57 million and $52 million, respectively, and is included in other regulatory liabilities, deferred on Mississippi Power's balance sheets.
II-144

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

In 2023, the Mississippi PSC approved Mississippi Power's annual SRR filing, with no change in retail rates. Mississippi Power's minimum annual SRR accrual was increased from $8.3 million to $11.7 million. In April 2024, the Mississippi PSC approved Mississippi Power's annual SRR filing to the Mississippi PSC, with no change in retail rates. Mississippi Power's minimum annual SRR accrual was increased from $11.7 million to $12.6 million. On June 17, 2025, the Mississippi PSC approved Mississippi Power's annual SRR filing for 2025, with no change in retail rates. Mississippi Power's minimum annual SRR accrual increased from $12.6 million to $13.5 million and the target property damage reserve balance increased from $75 million to $125 million. Mississippi Power will continue to record the minimum annual accrual until the target property damage reserve balance of $125 million is met.
Reliability Reserve Accounting Order
Based on an order from the Mississippi PSC, Mississippi Power is authorized to maintain a retail reliability reserve to offset future generation, transmission, and distribution reliability-related expenditures for use in a future year. Mississippi Power may make accruals to the retail reliability reserve each year after meeting with the MPUS and Mississippi PSC staff. Mississippi Power will provide annually, through its capital plan, energy delivery plan, or PEP filing, any amounts to be charged against the retail reliability reserve during the current year.
During 2025, 2024, and 2023, Mississippi Power accrued $13 million, $21 million, and $11 million, respectively, to the retail reliability reserve. On June 17, 2025, the Mississippi PSC approved Mississippi Power's use of a portion of its retail reliability reserve balance during 2025, through its annual PEP filing. As a result, Mississippi Power utilized the retail reliability reserve in the amount of $10.9 million during 2025 for reliability-related generation, transmission, and distribution expenses. See "Performance Evaluation Plan" herein for information regarding approval of the annual PEP filing.
At December 31, 2025, Mississippi Power's retail reliability reserve balance was $59 million, of which $9 million is included in other regulatory liabilities, current and $50 million is included in other regulatory liabilities, deferred on Mississippi Power's balance sheets. At December 31, 2024, Mississippi Power's retail reliability reserve balance was $57 million and is included in other regulatory liabilities, deferred on Mississippi Power's balance sheets.
Excess Accumulated Deferred Income Tax Accounting Order
On January 13, 2026, the Mississippi PSC approved an accounting order authorizing Mississippi Power to accelerate the amortization of approximately $21 million of a regulatory liability associated with certain federal excess accumulated deferred income taxes resulting from the Tax Reform Legislation. The flowback will be determined in a future rate proceeding. The ultimate outcome of this matter cannot be determined at this time.
Municipal and Rural Associations Tariff
Mississippi Power provides wholesale electric service to Cooperative Energy, East Mississippi Electric Power Association, and the City of Collins, all located in southeastern Mississippi, under a long-term, FERC-regulated MRA tariff.
In 2017, Mississippi Power and Cooperative Energy executed, and the FERC accepted, a Shared Service Agreement (SSA), as part of the MRA tariff, under which Mississippi Power and Cooperative Energy share in providing electricity to the Cooperative Energy delivery points under the tariff. In 2022, the FERC accepted an amended SSA between Mississippi Power and Cooperative Energy, effective July 1, 2022, under which Cooperative Energy will continue to decrease its use of Mississippi Power's generation services under the MRA tariff up to 2.5% annually through 2035. At December 31, 2025, Mississippi Power is serving approximately 394 MWs of Cooperative Energy's annual demand. Beginning in 2036, Cooperative Energy will provide 100% of its electricity requirements at the MRA delivery points under the tariff. Neither party has the option to cancel the amended SSA.
In May 2024, the FERC issued an order accepting Mississippi Power's request for an $8 million increase in annual wholesale base revenues under the MRA tariff, effective May 29, 2024, subject to refund. On April 3, 2025, the FERC approved a settlement agreement filed by Mississippi Power and Cooperative Energy in December 2024. The settlement agreement provided for (i) a $1 million increase in annual wholesale base revenues and a refund to customers of approximately $4 million, (ii) a rate escalation of 2.5% on an annual basis in periods subsequent to December 31, 2024 and continuing through the end of the SSA on December 31, 2035, and (iii) a waiver of rights by Mississippi Power and Cooperative Energy to file for any changes in non-fuel rates through the end of the term of the SSA.
Southern Company Gas
Utility Regulation and Rate Design
The natural gas distribution utilities are subject to regulation and oversight by their respective state regulatory agencies. Rates charged to customers vary according to customer class (residential, commercial, or industrial) and rate jurisdiction. These
II-145

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

agencies approve rates designed to provide the opportunity to generate revenues to recover all prudently-incurred costs, including a return on rate base sufficient to pay interest on debt and provide a reasonable ROE.
As a result of operating in a deregulated environment, Atlanta Gas Light earns revenue by charging rates to its customers based primarily on monthly fixed charges that are set by the Georgia PSC and adjusted periodically. The Marketers add these fixed charges when billing their respective customers. This mechanism, called a straight-fixed-variable rate design, minimizes the seasonality of Atlanta Gas Light's revenues since the monthly fixed charge is not volumetric or directly weather dependent.
With the exception of Atlanta Gas Light, the earnings of the natural gas distribution utilities can be affected by customer consumption patterns that are largely a function of price levels for natural gas and general economic conditions that may impact customers' ability to pay for natural gas consumed. Specifically, customer demand substantially increases during the Heating Season when natural gas is used for heating purposes. Southern Company Gas has various mechanisms, such as weather and revenue normalization mechanisms, that limit exposure to weather changes within typical ranges in these utilities' respective service territories.
In addition to natural gas cost recovery mechanisms, other cost recovery mechanisms and regulatory riders, which vary by utility, allow recovery of certain costs, such as those related to infrastructure replacement programs as well as environmental remediation, energy efficiency plans, and bad debts. In traditional rate designs, utilities recover a significant portion of the fixed customer service and pipeline infrastructure costs based on assumed natural gas volumes used by customers. With the exception of Chattanooga Gas, the natural gas distribution utilities have decoupled regulatory mechanisms that Southern Company Gas believes encourage conservation by separating the recoverable amount of these fixed costs from the amounts of natural gas used by customers. See "Rate Proceedings" herein for additional information. Also see "Infrastructure Replacement Programs and Capital Projects" herein for additional information regarding infrastructure replacement programs at certain of the natural gas distribution utilities.
The following table provides regulatory information for Southern Company Gas' natural gas distribution utilities:
Nicor
Gas
Atlanta Gas
Light
Virginia
Natural Gas
Chattanooga
Gas
Authorized ROE at December 31, 2025
9.60%10.25%9.85%9.80%
Weather normalization mechanisms(a)
üü
Decoupled, including straight-fixed-variable rates(b)
üüü
Regulatory infrastructure program rate(c)
üüü
Bad debt rider(d)
üüü
Energy efficiency plan(e)
üü
Annual base rate adjustment mechanism(f)
üü
Year of last base rate case decision
2025
201920252018
(a)Designed to help stabilize operating results by allowing recovery of costs in the event of unseasonal weather, but are not direct offsets to the potential impacts on earnings of weather and customer consumption.
(b)Allows for recovery of fixed customer service costs separately from assumed natural gas volumes used by customers and provides a benchmark level of revenue for recovery.
(c)See "Infrastructure Replacement Programs and Capital Projects" herein for additional information. Chattanooga Gas' pipeline replacement program costs are recovered through its annual base rate review mechanism.
(d)The recovery (refund) of bad debt expense over (under) an established benchmark expense. The gas portion of bad debt expense is recovered through purchased gas adjustment mechanisms. Nicor Gas also has a rider to recover the non-gas portion of bad debt expense.
(e)Recovery of costs associated with plans to achieve specified energy savings goals.
(f)Regulatory mechanism allowing annual adjustments to base rates up or down based on authorized ROE and/or ROE range.
Infrastructure Replacement Programs and Capital Projects
In addition to capital expenditures recovered through base rates by each of the natural gas distribution utilities, Virginia Natural Gas has a separate rate rider that provides timely recovery of capital expenditures for specific infrastructure replacement programs, and Atlanta Gas Light has a separate rate rider that provides for the timely recovery of capital expenditures for a specific reinforcement capital program. Total capital expenditures incurred during 2025 for all gas distribution operations were $1.9 billion.
The following table and discussions provide updates on the infrastructure replacement programs and capital projects at the natural gas distribution utilities at December 31, 2025. These programs are risk-based and designed to update and replace cast iron, bare
II-146

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

steel, and mid-vintage plastic materials or expand Southern Company Gas' distribution systems to improve reliability and meet operational flexibility and growth.
UtilityProgramRecovery
Capital Expenditures in 2025
Capital Expenditures Since Project Inception
Pipe
Installed Since
Project Inception
Scope of
Program
Program DurationLast
Year of Program
(in millions)(miles)(miles)(years)
Virginia Natural Gas
SAVE
Rider$72 $633 620 938 182029
Atlanta Gas LightSystem Reinforcement RiderRider131 410 43 N/A62027
Chattanooga GasPipeline Replacement ProgramRate Base13 41 37 73 102031
$216 $1,084 700 1,011 
Virginia Natural Gas
The SAVE program, an accelerated infrastructure replacement program, allows Virginia Natural Gas to continue replacing aging pipeline infrastructure. The program included authorized annual investments of $70 million in each of 2023 and 2024, with a total potential variance of up to $5 million allowed for the program, for a maximum total investment over the previous six-year term (2019 through 2024) of $365 million.
In June 2024, the Virginia Commission approved the extension of the existing SAVE program through 2029. The extension of the program includes investments of $70 million in each year from 2025 through 2029, with a potential variance of up to $5 million allowed for the program, for a maximum total investment over the five-year extension (2025 through 2029) of $355 million.
The SAVE program is subject to annual review by the Virginia Commission. In accordance with the base rate case approved by the Virginia Commission in 2025, Virginia Natural Gas is recovering program costs incurred prior to January 1, 2025 through base rates. Program costs incurred subsequent to January 1, 2025 are currently being recovered through a separate rider and are subject to future base rate case proceedings. See "Rate Proceedings – Virginia Natural Gas" herein for additional information.
Atlanta Gas Light
In 2019, the Georgia PSC approved the continuation of GRAM as part of Atlanta Gas Light's 2019 rate case order. Various infrastructure programs previously authorized by the Georgia PSC, including the Integrated Vintage Plastic Replacement Program to replace aging plastic pipe and the Integrated System Reinforcement Program to upgrade Atlanta Gas Light's distribution system and LNG facilities in Georgia, continue under GRAM and the recovery of and return on the infrastructure program investments are included in annual base rate adjustments. The amounts recovered through rates related to allowed, but not incurred, costs were quantified as an unrecognized ratemaking amount that is not reflected on the balance sheets. These allowed costs are primarily the equity return on the capital investment under the infrastructure programs in place prior to GRAM and are expected to be fully recovered through GRAM and base rates by the end of 2027. The Georgia PSC reviewed Atlanta Gas Light's performance annually under GRAM. See "Unrecognized Ratemaking Amounts" herein for additional information.
Atlanta Gas Light and the staff of the Georgia PSC previously agreed to a variation of the Integrated Customer Growth Program to extend pipeline facilities to serve customers in areas without pipeline access and create new economic development opportunities in Georgia. A separate tariff provides recovery of up to $25 million annually for strategic economic development projects approved by the Georgia PSC.
The Georgia PSC also approved a new System Reinforcement Rider for authorized large pressure improvement and system reliability projects. Capital investments for the years 2022 through 2024 related to the System Reinforcement Rider totaled $279 million.
See "Rate Proceedings – Atlanta Gas Light" herein for additional information regarding the Georgia PSC's 2021 approval of Atlanta Gas Light's GRAM filing and Integrated Capacity and Delivery Plan (i-CDP).
Chattanooga Gas
In 2021, the Tennessee Public Utilities Commission approved Chattanooga Gas' pipeline replacement program to replace approximately 73 miles of distribution main over a seven-year period. The estimated total cost of the program is $118 million, which will be recovered through Chattanooga Gas' annual base rate review mechanism.
In June 2025, the Tennessee Public Utilities Commission approved an extension of Chattanooga Gas' pipeline replacement program from seven to 10 years.
II-147

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Nicor Gas
Illinois legislation allowed Nicor Gas to provide more widespread safety and reliability enhancements to its distribution system through 2023 and stipulated that rate increases to customers as a result of any infrastructure investments did not exceed a cumulative annual average of 4.0% or, in any given year, 5.5% of base rate revenues. In 2014, the Illinois Commission approved the nine-year regulatory infrastructure program, Investing in Illinois, which concluded in 2023 and is subject to annual review, as discussed further below. In accordance with orders from the Illinois Commission, Nicor Gas recovered program costs incurred through a separate rider and base rates. See "Rate Proceedings – Nicor Gas" herein for additional information.
In 2023, the Illinois Commission concluded its review of the Qualifying Infrastructure Plant (QIP) capital investments by Nicor Gas for calendar year 2019 under the QIP rider, also referred to as Investing in Illinois program. The Illinois Commission disallowed $32 million of the $415 million of capital investments commissioned in 2019, together with the related return on investment. Nicor Gas recorded a pre-tax charge to income in 2023 of $38 million ($28 million after tax) associated with the disallowance of capital investments placed in service in 2019. The disallowances are reflected on the statements of income as an $8 million reduction to revenues and $30 million in estimated loss on regulatory disallowance. Later in 2023, the Illinois Commission denied a rehearing request filed by Nicor Gas, and Nicor Gas filed a notice of appeal with the Illinois Appellate Court. In November 2024, the Illinois Appellate Court upheld the Illinois Commission's review of the QIP capital investments by Nicor Gas for calendar year 2019 under the QIP rider apart from one immaterial item. In December 2024, Nicor Gas filed a petition for leave to appeal $14 million of the 2019 QIP disallowances with the Illinois Supreme Court, which was denied on March 26, 2025. This matter is now concluded and had no impact on the financial statements for the period ended December 31, 2025.
The following table provides a summary of QIP capital investments during the nine-year program:
Year
Status of QIP Annual Review Proceeding
Capital Investments
DisallowedMonth of Disallowance
(in millions)
2015 – 2018Complete$1,246 $ 
2019
Complete
415 32 June 2023
2020
Filed March 2021
402 
(a)
2021
Filed March 2022
392 
(a)
2022
Filed March 2023
408 
(a)
6 
(b)
November 2023
2023
Filed March 2024
365 
(a)
25 
(b)
November 2023
$3,228 $63 
(a)Capital investments are subject to the required QIP annual review proceeding; years 2020 through 2023 are pending with the Illinois Commission.
(b)Disallowed in Nicor Gas' 2023 general base rate case proceeding. See "Rate Proceedings – Nicor Gas" herein for additional information regarding the Illinois Commission's disallowance of certain capital investments.
Any further cost disallowances by the Illinois Commission in the pending cases could be material to the financial statements of Southern Company Gas. The ultimate outcome of these matters cannot be determined at this time.
Natural Gas Cost Recovery
With the exception of Atlanta Gas Light, the natural gas distribution utilities are authorized by the relevant regulatory agencies in the states in which they serve to use natural gas cost recovery mechanisms that adjust rates to reflect changes in the wholesale cost of natural gas and ensure recovery of all costs prudently incurred in purchasing natural gas for customers. The natural gas distribution utilities defer or accrue the difference between the actual cost of natural gas and the amount of commodity revenue earned in a given period. The deferred or accrued amount is either billed or refunded to customers prospectively through adjustments to the commodity rate. Deferred natural gas costs are reflected as regulatory assets and accrued natural gas costs are reflected as regulatory liabilities. Natural gas costs generally do not have a significant effect on Southern Company's or Southern Company Gas' net income but could have a significant effect on cash flows. Since Atlanta Gas Light does not sell natural gas directly to its end-use customers, it does not utilize a traditional natural gas cost recovery mechanism. However, Atlanta Gas Light does maintain natural gas inventory for the Marketers in Georgia and recovers the cost through recovery mechanisms approved by the Georgia PSC. At December 31, 2025 and 2024, the over recovered balance was $158 million and $193 million, respectively, which is included in natural gas cost over recovery on Southern Company's and Southern Company Gas' balance sheets.
II-148

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Rate Proceedings
Nicor Gas
In 2023, the Illinois Commission approved a $223 million annual base rate increase for Nicor Gas, which became effective December 1, 2023. The base rate increase was based on an ROE of 9.51% and an equity ratio of 50.00%.
In connection with Nicor Gas' 2023 general base rate case proceeding, the Illinois Commission disallowed $127 million of capital investments that have been completed or were planned to be completed through December 31, 2024. This amount is comprised of $31 million for capital investments placed in service in 2022 and 2023 under the Investing in Illinois program and $96 million for other transmission and distribution capital investments. Nicor Gas recorded a pre-tax charge to income in 2023 of $58 million ($44 million after tax) associated with the disallowances. The disallowances are reflected on the statements of income in estimated loss on regulatory disallowance. See "Infrastructure Replacement Programs and Capital Projects – Nicor Gas" herein for additional information regarding the Illinois Commission's disallowance of certain capital investments. In January 2024, the Illinois Commission denied a request by Nicor Gas for rehearing on the base rate case disallowances associated with capital investment, as well as on other issues determined in the Illinois Commission's 2023 base rate case decision. In February 2024, Nicor Gas filed a notice of appeal with the Illinois Appellate Court related to the Illinois Commission's rate case ruling. On December 1, 2025, the Illinois Appellate Court upheld the Illinois Commission's decision regarding certain capital investment disallowances in Nicor Gas' 2023 general base rate case proceeding. On December 22, 2025, Nicor Gas filed a petition for rehearing with the Illinois Appellate Court specifically addressing $43 million of the base rate case disallowances.
On November 19, 2025, the Illinois Commission approved a $168 million annual base rate increase for Nicor Gas, which became effective December 2, 2025. The base rate increase was based on an ROE of 9.60% and an equity ratio of 50.00%.
Additionally, the Illinois Commission excluded $120 million of capital investments included in the base rate case filing that have been incurred or are expected to be incurred through December 31, 2026. Nicor Gas analyzed the Illinois Commission's order and recorded a pre-tax charge to income in the fourth quarter 2025 of $63 million ($47 million after tax) associated with excluded capital investments that have been incurred. The disallowances are reflected on the statements of income in estimated loss on regulatory disallowance.
On January 6, 2026, the Illinois Commission denied a request by Nicor Gas for rehearing on the base rate case disallowances associated with capital investment, as well as on other issues determined in the Illinois Commission's November 19, 2025 base rate case decision. On January 14, 2026, Nicor Gas filed a petition for review with the Illinois Appellate Court related to the Illinois Commission's rate case ruling. It remains Nicor Gas' position that it has met its evidentiary burden to demonstrate that the amount and the timing of such capital investments are prudent and reasonable and that such capital investments should be included in base rates.
On January 9, 2026, Nicor Gas filed a general base rate case with the Illinois Commission requesting a $221 million increase in annual base rate revenues. The requested increase is based on a projected test year for the 12-month period ending December 31, 2027, an ROE of 10.35%, and an equity ratio of 54.6%. The Illinois Commission is expected to rule on the requested increase within the 11-month statutory time limit, after which rate adjustments will be effective.
The ultimate outcome of these matters cannot be determined at this time.
Atlanta Gas Light
The Georgia PSC evaluates Atlanta Gas Light's earnings against an ROE range of 10.05% to 10.45%, with disposition of any earnings above 10.45% to be determined by the Georgia PSC. Additionally, the Georgia PSC allows inclusion in base rates of the recovery of and return on the infrastructure program investments, including, but not limited to, GRAM adjustments. GRAM filing rate adjustments are based on an authorized ROE of 10.25%.
In 2021, Atlanta Gas Light filed its i-CDP with the Georgia PSC, which included a series of ongoing and proposed pipeline safety, reliability, and growth programs for the next 10 years (2022 through 2031), as well as the required capital investments and related costs to implement the programs. The i-CDP reflected capital investments totaling approximately $0.5 billion to $0.6 billion annually.
Also in 2021, the Georgia PSC approved a stipulation between Atlanta Gas Light and the staff of the Georgia PSC, under which, for the years 2022 through 2024, Atlanta Gas Light would incrementally reduce its combined GRAM and System Reinforcement Rider request by 10% through Atlanta Gas Light's GRAM mechanism, which resulted in a reduction of $7 million for 2023 and $9 million for 2024. The stipulation also provided for $1.7 billion of total capital investment for the years 2022 through 2024.
In December 2023, the Georgia PSC approved Atlanta Gas Light's annual GRAM filing, which resulted in an annual base rate increase of $53 million effective January 1, 2024. In December 2024, the Georgia PSC approved Atlanta Gas Light's annual
II-149

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

GRAM filing, which included annual base rate increases of $72 million, $73 million, and $74 million effective January 1, 2025, 2026, and 2027, respectively.
In July 2024, the Georgia PSC approved a stipulation related to Atlanta Gas Light's 2024 i-CDP, which included a series of ongoing and proposed pipeline safety, reliability, and growth programs for the next 10 years (2025 through 2034), as well as the required capital investments and related cost to implement the programs. The i-CDP allows capital investments totaling approximately $0.6 billion annually for the years 2025 through 2027 with related revenue requirement recovery through either the annual GRAM filing or the System Reinforcement Rider surcharge adjustment. Additionally, the Georgia PSC approved a surcharge recovery mechanism for capital projects related to municipal, county, and Georgia Department of Transportation infrastructure work. Rate changes associated with the new surcharge will be based on requests filed annually on September 1. If approved, new rates will become effective January 1 of the following year.
Virginia Natural Gas
In 2023, the Virginia Commission approved a stipulation related to Virginia Natural Gas' 2022 general base rate case filing, which allowed for a $48 million increase in annual base rate revenues based on an ROE of 9.70% and an equity ratio of 49.06%. Interim rates became effective as of January 1, 2023, subject to refund, based on Virginia Natural Gas' original requested increase of approximately $69 million. Refunds to customers related to the difference between the approved rates implemented September 1, 2023 and the interim rates were completed during the fourth quarter 2023.
On December 17, 2025, the Virginia Commission approved a stipulation related to Virginia Natural Gas' August 2024 general base rate case filing. The approved stipulation provides for a $40 million increase in annual base rate revenues, including the recovery of investments under the SAVE program, an ROE of 9.85%, and an equity ratio of 49.35%. Interim rates became effective January 1, 2025, subject to refund, based on Virginia Natural Gas' original requested increase of approximately $63 million. Refunds to customers related to the difference between the approved rates implemented December 31, 2025 and the interim rates will be administered during the first quarter 2026.
Unrecognized Ratemaking Amounts
The following table illustrates Southern Company Gas' authorized ratemaking amounts that are not recognized on its balance sheets. These amounts are primarily comprised of an allowed equity rate of return on assets associated with certain regulatory infrastructure programs. These amounts will be recognized as revenues in Southern Company Gas' financial statements in the periods they are billable to customers, the majority of which will be recovered by 2027.
December 31, 2025December 31, 2024
(in millions)
Atlanta Gas Light$4 $11 
Virginia Natural Gas9 10 
Chattanooga Gas7 7 
Total$20 $28 
3. CONTINGENCIES, COMMITMENTS, AND GUARANTEES
General Litigation Matters
The Registrants are involved in various matters being litigated and regulatory matters. The ultimate outcome of such pending or potential litigation or regulatory matters against each Registrant and any subsidiaries cannot be determined at this time; however, for current proceedings not specifically reported herein, management does not anticipate that the ultimate liabilities, if any, arising from such current proceedings would have a material effect on such Registrant's financial statements.
The Registrants intend to dispute the allegations raised in and vigorously defend against the pending legal challenges discussed below; however, the ultimate outcome of each of these matters cannot be determined at this time.
Southern Company
On July 11, 2025, a purported class action complaint was filed in the U.S. District Court for the District of Maryland against two nuclear consulting companies and all U.S. commercial nuclear power operators, or affiliated entities, including Southern Company. The purported class of plaintiffs includes all persons employed in nuclear power generation by the defendants, including nuclear operators, nuclear engineers, and nuclear technicians, from May 1, 2003 to the present. The complaint alleges that, since at least May 2003, the nuclear power industry conspired to fix and suppress employee compensation for nuclear power generation employees in violation of federal antitrust law. Although not named as defendants, other entities are accused of having
II-150

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

participated in the plaintiffs' alleged conspiracy. The plaintiffs seek to recover, among other relief, unspecified monetary damages, including treble damages and attorneys' fees, and injunctive relief. On October 15, 2025, Southern Company moved to dismiss the complaint. On November 6, 2025, the plaintiffs filed an amended complaint naming Southern Nuclear, among others, as a defendant. On December 19, 2025, Southern Company and Southern Nuclear filed a motion to dismiss the amended complaint. An adverse outcome could have a material impact on Southern Company's financial statements.
Southern Company and Mississippi Power
In 2010, the DOE, through a cooperative agreement with SCS, agreed to fund $270 million of the Kemper County energy facility through the grants awarded to the project by the DOE under the Clean Coal Power Initiative Round 2. In 2016, additional DOE grants in the amount of $137 million were awarded to the Kemper County energy facility. In 2018, Mississippi Power filed with the DOE its request for property closeout certification under the contract related to the $387 million of total grants received. In 2020, Mississippi Power and Southern Company executed an agreement with the DOE completing Mississippi Power's request, which enabled Mississippi Power to proceed with full dismantlement of the abandoned gasifier-related assets and site restoration activities. In connection with the DOE closeout discussions, in 2019, the Civil Division of the Department of Justice informed Southern Company and Mississippi Power of a civil investigation related to the DOE grants. In 2023, the U.S. District Court for the Northern District of Georgia unsealed a civil action in which defendants Southern Company, SCS, and Mississippi Power were alleged to have violated certain provisions of the False Claims Act by fraudulently inducing the DOE to disburse funds pursuant to the grants. The federal government declined to intervene in the action. Later in 2023, the plaintiff, a former SCS employee, filed an amended complaint, again alleging certain violations of the False Claims Act. The plaintiff sought to recover all damages incurred personally and on behalf of the federal government caused by the defendants' alleged violations, as well as treble damages and attorneys' fees, among other relief. In February 2024, the defendants moved to dismiss the amended complaint. In August 2024, the court granted the defendants' motion in part and denied it in part, dismissing the plaintiff's False Claims Act count along with its accompanying treble damages and attorneys' fees but allowing the employment retaliation claim to proceed. In October 2024, the plaintiff requested interlocutory appeal of the court's decision, which was denied on February 25, 2025, and the defendants asserted counterclaims for conversion and misappropriation of trade secrets. In November 2024, the defendants filed a motion for judgment on the pleadings on the plaintiff's employment retaliation claim. In December 2024, the plaintiff filed a motion to dismiss the defendants' counterclaims. On July 15, 2025, the court denied the plaintiff's motion to dismiss the defendants' counterclaims and the defendants' motion for judgment on the pleadings. On August 6, 2025, the plaintiff asserted a counterclaim against the defendants. On September 8, 2025, the defendants renewed their motion for judgment on the pleadings. On November 12, 2025, the parties reached an agreement in principle to resolve the lawsuit. On January 20, 2026, the court entered an order dismissing the lawsuit. The resolution does not have a material impact on Southern Company's or Mississippi Power's financial statements.
Alabama Power
In 2022, Mobile Baykeeper filed a citizen suit in the U.S. District Court for the Southern District of Alabama alleging that Alabama Power's plan to close the Plant Barry surface impoundment utilizing a closure-in-place methodology violates the Resource Conservation and Recovery Act (RCRA) and regulations governing CCR. Among other relief requested, Mobile Baykeeper sought a declaratory judgment that the RCRA and regulations governing CCR were being violated, preliminary and injunctive relief to prevent implementation of Alabama Power's closure plan, and the development of a closure plan that satisfies regulations governing CCR requirements. Later in 2022, Alabama Power filed a motion to dismiss the case. In January 2024, the lawsuit was dismissed without prejudice by the U.S. District Court judge. In February 2024, the plaintiff filed a motion to reconsider, which was denied by the U.S. District Court judge in July 2024. In August 2024, the plaintiff filed a notice of appeal in the U.S. Court of Appeals for the Eleventh Circuit challenging the denial of the motion to reconsider the order of dismissal.
In 2023, the EPA issued a Notice of Potential Violations (NOPV) associated with Alabama Power's plan to close the Plant Barry surface impoundment. In September 2024, Alabama Power reached a settlement with the EPA resolving two of the three allegations in the NOPV related to the groundwater monitoring system and the emergency action plan at the Plant Barry surface impoundment. The settlement did not resolve the EPA's allegation relating to Alabama Power's plan to close the Plant Barry surface impoundment. Alabama Power has affirmed to the EPA its position that it is in compliance with CCR requirements.
On July 29, 2025, Coosa Riverkeeper filed a citizen suit in the U.S. District Court for the Northern District of Alabama alleging that Alabama Power's closure of the Plant Gadsden surface impoundment utilizing a closure-in-place methodology violates the RCRA and regulations governing CCR. Among other relief requested, Coosa Riverkeeper seeks declaratory judgment that Alabama Power is in violation of RCRA and regulations governing CCR, and preliminary and injunctive relief to require
II-151

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Alabama Power to close the CCR unit and operate a groundwater monitoring system in a different manner to satisfy RCRA and the regulations governing CCR requirements. On September 29, 2025, Alabama Power filed a motion to dismiss the citizen suit.
These matters could have a material impact on Alabama Power's and Southern Company's financial statements, including ARO estimates and cash flows. See Note 6 for a discussion of Alabama Power's ARO liabilities.
Environmental Remediation
The Southern Company system must comply with environmental laws and regulations governing the handling and disposal of waste and releases of hazardous substances. Under these various laws and regulations, the Southern Company system could incur substantial costs to clean up affected sites. The traditional electric operating companies and the natural gas distribution utilities conduct studies to determine the extent of any required cleanup and have recognized the estimated costs to clean up known impacted sites in the financial statements. A liability for environmental remediation costs is recognized only when a loss is determined to be probable and reasonably estimable and is reduced as expenditures are incurred. The traditional electric operating companies and the natural gas distribution utilities in Illinois and Georgia have each received authority from their respective state PSCs or other applicable state regulatory agencies to recover approved environmental remediation costs through regulatory mechanisms. Any difference between the liabilities accrued and costs recovered through rates is deferred as a regulatory asset or liability. These regulatory mechanisms are adjusted annually or as necessary within limits approved by the state PSCs or other applicable state regulatory agencies.
Georgia Power has been designated or identified as a potentially responsible party at sites governed by the Georgia Hazardous Site Response Act and/or by the federal Comprehensive Environmental Response, Compensation, and Liability Act, and assessment and potential cleanup of such sites is expected. For all periods presented, Georgia Power recovered approximately $5 million through the ECCR tariff for environmental remediation.
Southern Company Gas is subject to environmental remediation liabilities associated with former manufactured gas plant sites. Southern Company Gas' accrued environmental remediation liability at December 31, 2025 and 2024 was based on the estimated cost of environmental investigation and remediation associated with these sites.
At December 31, 2025 and 2024, the environmental remediation liability and the balance of under recovered environmental remediation costs were reflected in the balance sheets of Southern Company, Georgia Power, and Southern Company Gas as shown in the table below. Alabama Power and Mississippi Power did not have environmental remediation liabilities at December 31, 2025 or 2024.
Southern
Company
Georgia
Power
Southern
Company Gas
(in millions)
At December 31, 2025:
Environmental remediation liability:
Other current liabilities$34 $14 $20 
Accrued environmental remediation207  207 
Under recovered environmental remediation costs:
Other regulatory assets, current$28 $5 $23 
Other regulatory assets, deferred214 8 206 
At December 31, 2024:
Environmental remediation liability:
Other current liabilities$37 $13 $24 
Accrued environmental remediation198  198 
Under recovered environmental remediation costs:
Other regulatory assets, current$37 $5 $32 
Other regulatory assets, deferred212 11 201 
The ultimate outcome of these matters cannot be determined at this time; however, as a result of the regulatory treatment for environmental remediation expenses described above, the final disposition of these matters is not expected to have a material impact on the financial statements of the applicable Registrants.
II-152

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Nuclear Fuel Disposal Costs
Acting through the DOE and pursuant to the Nuclear Waste Policy Act of 1982, the U.S. government entered into contracts with Alabama Power and Georgia Power that required the DOE to take title to and dispose of spent nuclear fuel generated at Plants Farley, Hatch, and Vogtle Units 1 and 2 beginning no later than January 31, 1998. The DOE has yet to commence performance of its contractual and statutory obligation to dispose of spent nuclear fuel. Consequently, Alabama Power and Georgia Power pursued and continue to pursue legal remedies against the U.S. government for its partial breach of contract.
In June 2024 and August 2024, the Court of Federal Claims entered final judgments on damages in the third and fourth round of lawsuits against the U.S. government, respectively, awarding Alabama Power a total of approximately $100 million and Georgia Power a total of approximately $121 million (based on its ownership interests), which represent claims for the period from January 1, 2011 through December 31, 2019.
In December 2024, the Alabama PSC directed Alabama Power to return the award, which was reflected as a regulatory liability at December 31, 2024, to customers through bill credits during the months of January, February, and March 2025. During the third quarter 2024, Georgia Power credited the award to accounts where the original costs were charged, which reduced rate base, fuel, and cost of service for the benefit of customers, as previously authorized by the Georgia PSC. As a result of this regulatory treatment, there was no material impact on Southern Company's, Alabama Power's, or Georgia Power's net income.
On September 5, 2025, Alabama Power and Georgia Power filed their fifth round of lawsuits against the U.S. government in the Court of Federal Claims, seeking damages for the costs of continuing to store spent nuclear fuel at Plants Farley, Hatch, and Vogtle Units 1 and 2 for the period from January 1, 2020 through December 31, 2024. Damages will continue to accumulate until the issue is resolved, the U.S. government disposes of Alabama Power's and Georgia Power's spent nuclear fuel pursuant to its contractual obligations, or alternative storage is otherwise provided. No amounts have been recognized in the financial statements as of December 31, 2025 for any potential recoveries from the pending lawsuits.
The final outcome of this matter cannot be determined at this time. However, Alabama Power and Georgia Power expect to credit any recoveries for the benefit of customers in accordance with direction from their respective PSC; therefore, no material impact on Southern Company's, Alabama Power's, or Georgia Power's net income is expected.
On-site dry spent fuel storage facilities are operational at all three plants and can be expanded to accommodate spent fuel through the expected life of each plant.
Nuclear Insurance
Under the Price-Anderson Amendments Act (Act), Alabama Power and Georgia Power maintain agreements of indemnity with the NRC that, together with private insurance, cover third-party liability arising from any nuclear incident occurring at the companies' nuclear power plants. The Act provides funds up to $16.3 billion for public liability claims that could arise from a single nuclear incident. Each nuclear plant is insured against this liability to a maximum of $500 million by American Nuclear Insurers (ANI), with the remaining coverage provided by a mandatory program of deferred premiums that could be assessed, after a nuclear incident, against all owners of commercial nuclear reactors. A company could be assessed up to $166 million per incident for each licensed reactor it operates but not more than an aggregate of $25 million per incident to be paid in a calendar year for each reactor. Such maximum assessment, excluding any applicable state premium taxes, for Alabama Power and Georgia Power, based on its ownership and buyback interests in all licensed reactors, is $332 million and $473 million, respectively, per incident, but not more than an aggregate of $49 million and $71 million, respectively, to be paid for each incident in any one year. Both the maximum assessment per reactor and the maximum yearly assessment are adjusted for inflation at least every five years. The next scheduled adjustment is due no later than November 1, 2028. See Note 5 under "Joint Ownership Agreements" for additional information on joint ownership agreements.
Alabama Power and Georgia Power are members of Nuclear Electric Insurance Limited (NEIL), a mutual insurer established to provide property damage insurance in an amount up to $1.5 billion for members' operating nuclear generating facilities. Additionally, both companies have NEIL policies that currently provide decontamination, excess property insurance, and premature decommissioning coverage up to $1.25 billion for nuclear losses and policies providing coverage up to $750 million for non-nuclear losses in excess of the $1.5 billion primary coverage.
NEIL also covers the additional costs that would be incurred in obtaining replacement power during a prolonged accidental outage at a member's nuclear plant. Members can purchase this coverage, subject to a deductible waiting period of up to 26 weeks, with a maximum per occurrence per unit limit of $490 million. After the deductible period, weekly indemnity payments would be received until either the unit is operational or until the limit is exhausted. Alabama Power and Georgia Power each purchase limits based on the projected full cost of replacement power, subject to ownership limitations, and have each elected a 12-week deductible waiting period for each nuclear plant.
II-153

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Under each of the NEIL policies, members are subject to assessments each year if losses exceed the accumulated funds available to the insurer. The maximum annual assessments for Alabama Power and Georgia Power as of December 31, 2025 under the NEIL policies would be $61 million and $84 million, respectively.
Claims resulting from terrorist acts and cyber events are covered under both the ANI and NEIL policies (subject to normal policy limits). The maximum aggregate that NEIL will pay for all claims resulting from terrorist acts and cyber events in any 12-month period is $3.2 billion each, plus such additional amounts NEIL can recover through reinsurance, indemnity, or other sources.
For all on-site property damage insurance policies for commercial nuclear power plants, the NRC requires that the proceeds of such policies shall be dedicated first for the sole purpose of placing the reactor in a safe and stable condition after an accident. Any remaining proceeds are to be applied next toward the costs of decontamination and debris removal operations ordered by the NRC, and any further remaining proceeds are to be paid either to the applicable company or to its debt trustees as may be appropriate under the policies and applicable trust indentures. In the event of a loss, the amount of insurance available might not be adequate to cover property damage and other expenses incurred. Uninsured losses and other expenses, to the extent not recovered from customers, would be borne by Alabama Power or Georgia Power, as applicable, and could have a material effect on Southern Company's, Alabama Power's, and Georgia Power's financial condition, cash flows, and results of operations.
All retrospective assessments, whether generated for liability, property, or replacement power, may be subject to applicable state premium taxes.
Other Matters
Mississippi Power
Kemper County Energy Facility
In 2023, 2024, and 2025, Mississippi Power recorded charges to income associated with abandonment and related closure costs and ongoing period costs, net of salvage proceeds, for the mine and gasifier-related assets at the Kemper County energy facility. These charges, including related tax impacts, totaled $17 million pre-tax ($12 million after tax) in 2023, $12 million pre-tax ($9 million after tax) in 2024, and $13 million pre-tax ($10 million after tax) in 2025. The pre-tax charges are included in other operations and maintenance expenses on the statements of income. Dismantlement of the abandoned gasifier-related assets was completed at the end of 2025. Site restoration activities for the mine are substantially complete, and any additional costs are expected to be immaterial. See "General Litigation Matters – Southern Company and Mississippi Power" herein for information regarding litigation associated with the Kemper County energy facility.
Department of Revenue Audit
On March 31, 2025, the Mississippi Department of Revenue (Mississippi DOR) completed an audit of sales and use taxes paid by Mississippi Power from October 2019 to July 2024 and entered a final assessment, indicating a total amount due of $29 million, including associated penalties and interest. Mississippi Power did not agree with the audit findings and filed an administrative appeal with the Mississippi DOR on May 29, 2025. On November 4, 2025, Mississippi Power and the Mississippi DOR reached a settlement agreement on an assessment of approximately $13 million including associated penalties and interest, $11 million of which was previously paid by Mississippi Power. On November 5, 2025, Mississippi Power made a final $2 million payment. This matter is now concluded.
Pursuant to an accounting order approved by the Mississippi PSC on January 13, 2026, Mississippi Power deferred $9 million of the agreed-upon assessment related to taxes and associated interest to a regulatory asset for disposition in a future rate proceeding.
Commitments
To supply a portion of the fuel requirements of the Southern Company system's electric generating plants, the Southern Company system has entered into various long-term commitments not recognized on the balance sheets for the procurement and delivery of fossil fuel and, for Alabama Power and Georgia Power, nuclear fuel. The majority of the Registrants' fuel expense for the periods presented was purchased under long-term commitments. Each Registrant expects that a substantial amount of its future fuel needs will continue to be purchased under long-term commitments.
Georgia Power has commitments, in the form of capacity purchases, regarding a portion of a 5% interest in the original cost of Plant Vogtle Units 1 and 2 owned by MEAG Power that are in effect until the later of the retirement of the plant or the latest stated maturity date of MEAG Power's bonds issued to finance such ownership interest. The payments for capacity are required whether or not any capacity is available. Portions of the capacity payments made to MEAG Power for its Plant Vogtle Units 1 and 2 investment relate to costs in excess of Georgia Power's allowed investment for ratemaking purposes. The present value of these portions at the time of the disallowance was written off. Generally, the cost of such capacity is included in purchased power in Southern Company's consolidated statements of income and in purchased power, non-affiliates in Georgia Power's statements of
II-154

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

income. Georgia Power's capacity payments related to this commitment totaled $3 million, $4 million, and $3 million in 2025, 2024, and 2023, respectively. At December 31, 2025, Georgia Power's estimated long-term obligations related to this commitment totaled $34 million, consisting of $2 million annually for 2026 through 2030 and $24 million thereafter.
See Note 9 for information regarding PPAs accounted for as leases.
Guarantees
SCS may enter into various types of wholesale energy and natural gas contracts acting as an agent for the traditional electric operating companies and Southern Power. Under these agreements, each of the traditional electric operating companies and Southern Power may be jointly and severally liable. Accordingly, Southern Company has entered into keep-well agreements with each of the traditional electric operating companies to ensure they will not subsidize or be responsible for any costs, losses, liabilities, or damages resulting from the inclusion of Southern Power as a contracting party under these agreements.
Alabama Power has guaranteed a $100 million principal amount long-term bank loan SEGCO entered into in 2018 and subsequently extended and amended. Georgia Power has agreed to reimburse Alabama Power for the portion of such obligation corresponding to Georgia Power's proportionate ownership of SEGCO's stock if Alabama Power is called upon to make such payment under its guarantee. At December 31, 2025, the capitalization of SEGCO consisted of $49 million of equity and $70 million of long-term debt that matures in November 2026, on which the annual interest requirement is derived from a variable rate index. SEGCO had no short-term debt outstanding at December 31, 2025. See Note 7 under "SEGCO" for additional information.
As discussed in Note 9, Alabama Power and Georgia Power have entered into certain residual value guarantees related to railcar leases, with Georgia Power's railcar leases being terminated as of June 2024.
4. REVENUE FROM CONTRACTS WITH CUSTOMERS
The Registrants generate revenues from a variety of sources, some of which are not accounted for as revenue from contracts with customers, such as leases, derivatives, and certain cost recovery mechanisms. Included in the wholesale electric revenues of the traditional electric operating companies and Southern Power are revenues associated with affiliate transactions. These revenues are generated through long-term PPAs or short-term energy sales made in accordance with the IIC, as approved by the FERC. Amounts related to these affiliate revenues are eliminated in consolidation for Southern Company. See Note 1 under "Affiliate Transactions" and "Revenues" for additional information. See Notes 9 and 14 for additional information on revenue accounted for under lease and derivative accounting guidance, respectively.
II-155

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

The following table disaggregates revenue from contracts with customers for the periods presented:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
2025
Operating revenues
Retail electric revenues
Residential$8,601 $3,209 $5,064 $328 $ $ 
Commercial6,995 2,071 4,582 342   
Industrial4,045 1,704 1,984 357   
Other123 10 104 9   
Total retail electric revenues19,764 6,994 11,734 1,036   
Natural gas distribution revenues
Residential2,164     2,164 
Commercial527     527 
Transportation1,424     1,424 
Industrial 44     44 
Other295     295 
Total natural gas distribution revenues4,454     4,454 
Wholesale electric revenues
PPA energy revenues1,430 248 245 13 966  
PPA capacity revenues637 134 146 69 356  
Non-PPA revenues299 194 64 484 220  
Total wholesale electric revenues2,366 576 455 566 1,542  
Other natural gas revenues
Gas marketing services569     569 
Other
12     12 
Total other natural gas revenues
581     581 
Other revenues1,777 265 805 55 18  
Total revenue from contracts with customers28,942 7,835 12,994 1,657 1,560 5,035 
Other revenue sources(*)
611 400 (363)38 638 9 
Total operating revenues$29,553 $8,235 $12,631 $1,695 $2,198 $5,044 
II-156

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
2024
Operating revenues
Retail electric revenues
Residential$8,276 $3,133 $4,835 $308 $ $ 
Commercial6,585 2,042 4,219 324   
Industrial3,892 1,742 1,808 342   
Other124 13 102 9   
Total retail electric revenues18,877 6,930 10,964 983   
Natural gas distribution revenues
Residential1,753     1,753 
Commercial417     417 
Transportation1,295     1,295 
Industrial 34     34 
Other316     316 
Total natural gas distribution revenues3,815     3,815 
Wholesale electric revenues
PPA energy revenues1,059 206 94 4 778  
PPA capacity revenues641 108 136 63 400  
Non-PPA revenues226 139 5 375 230  
Total wholesale electric revenues1,926 453 235 442 1,408  
Other natural gas revenues
Gas marketing services507     507 
Other
18     18 
Total other natural gas revenues525     525 
Other revenues1,621 240 721 52 37  
Total revenue from contracts with customers26,764 7,623 11,920 1,477 1,445 4,340 
Other revenue sources(*)
(40)(69)(589)(14)569 116 
Total operating revenues$26,724 $7,554 $11,331 $1,463 $2,014 $4,456 
II-157

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
2023
Operating revenues
Retail electric revenues
Residential$7,309 $2,904 $4,105 $300 $ $ 
Commercial5,860 1,928 3,624 308   
Industrial3,613 1,721 1,558 334   
Other112 12 91 9   
Total retail electric revenues16,894 6,565 9,378 951   
Natural gas distribution revenues
Residential1,981     1,981 
Commercial505     505 
Transportation1,184     1,184 
Industrial45     45 
Other324     324 
Total natural gas distribution revenues4,039     4,039 
Wholesale electric revenues
PPA energy revenues1,107 234 87 20 790  
PPA capacity revenues624 156 51 45 376  
Non-PPA revenues250 65 35 407 409  
Total wholesale electric revenues1,981 455 173 472 1,575  
Other natural gas revenues
Gas marketing services528     528 
Other
31     31 
Total other natural gas revenues559     559 
Other revenues1,355 213 578 39 55  
Total revenue from contracts with customers24,828 7,233 10,129 1,462 1,630 4,598 
Other revenue sources(*)
425 (183)(11)12 559 104 
Total operating revenues$25,253 $7,050 $10,118 $1,474 $2,189 $4,702 
(*)Other revenue sources relate to revenues from customers accounted for as derivatives and leases, alternative revenue programs primarily at Southern Company Gas, and cost recovery mechanisms and revenues (including those related to fuel costs) that meet other scope exceptions for revenues from contracts with customers at the traditional electric operating companies.
II-158

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Contract Balances
The following table reflects the closing balances of receivables, contract assets, and contract liabilities related to revenues from contracts with customers at December 31, 2025 and 2024:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
Accounts Receivable
At December 31, 2025$3,139 $716 $1,278 $115 $132 $864 
At December 31, 20243,048 783 1,244 113 106 660 
Contract Assets
At December 31, 2025$294 $3 $160 $ $ $67 
At December 31, 2024323 3 184   72 
Contract Liabilities
At December 31, 2025$213 $6 $75 $ $2 $ 
At December 31, 2024140 11 34  2 3 
Contract assets for Georgia Power primarily relate to retail customer fixed bill programs, where the payment is contingent upon Georgia Power's continued performance and the customer's continued participation in the program over a one-year contract term, and unregulated service agreements, where payment is contingent on project completion. Contract liabilities for Georgia Power primarily relate to cash collections recognized in advance of revenue for unregulated service agreements. Southern Company Gas' contract assets relate to work performed on an energy efficiency enhancement and upgrade contract with the U.S. General Services Administration. Southern Company Gas received cash advances totaling $68 million from a third-party financial institution to fund work performed. These advances have been accounted for as long-term debt on the balance sheets. See Note 1 under "Affiliate Transactions" for additional information regarding the construction contract. At December 31, 2025 and 2024, Southern Company's unregulated distributed generation business had contract assets of $63 million and $67 million, respectively, and contract liabilities of $132 million and $95 million, respectively, for outstanding performance obligations, all of which are expected to be satisfied within one year.
Revenues recognized in 2025 and 2024, which were included in contract liabilities at December 31, 2024 and 2023, respectively, were $102 million and $98 million, respectively, for Southern Company, $24 million and immaterial, respectively, for Georgia Power, and immaterial for the other Registrants. Contract liabilities are primarily classified as current on the balance sheets as the corresponding revenues are generally expected to be recognized within one year.
Remaining Performance Obligations
Southern Company's subsidiaries may enter into long-term contracts with customers in which revenues are recognized as performance obligations are satisfied over the contract term. For the traditional electric operating companies and Southern Power, these contracts primarily relate to PPAs whereby electricity and generation capacity are provided to a customer. The revenue recognized for the delivery of electricity is variable; however, certain PPAs include a fixed payment for fixed generation capacity over the term of the contract. Southern Company's unregulated distributed generation business also has partially satisfied performance obligations related to certain fixed price contracts. Revenues from contracts with customers related to these performance obligations remaining at December 31, 2025 are expected to be recognized as follows:
20262027202820292030Thereafter
(in millions)
Southern Company$1,060 $583 $408 $385 $389 $2,685 
Alabama Power48 5 4 1 1 6 
Georgia Power65 45 35 21 21 76 
Mississippi Power(*)
66 69 73 12   
Southern Power(*)
350 348 358 368 367 2,603 
(*)Includes performance obligations related to affiliate PPAs with Georgia Power. See Note 1 under "Affiliate Transactions" for additional information.
II-159

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

5. PROPERTY, PLANT, AND EQUIPMENT
Property, plant, and equipment is stated at original cost or fair value at acquisition, as appropriate, less any regulatory disallowances and impairments. Original cost may include: materials; labor; minor items of property; appropriate administrative and general costs; payroll-related costs such as taxes, pensions, and other benefits; and the interest capitalized and/or cost of equity funds used during construction.
The Registrants' property, plant, and equipment in service consisted of the following at December 31, 2025 and 2024:
At December 31, 2025:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
Electric utilities:
Generation$63,533 $17,912 $27,192 $2,969 $14,986 $ 
Transmission17,814 7,057 9,651 1,064   
Distribution31,718 11,058 19,083 1,577   
General/other6,854 2,888 3,532 362 48  
Electric utilities' plant in service119,919 38,915 59,458 5,972 15,034  
Southern Company Gas:
Natural gas transportation and distribution
20,177     20,177 
Storage facilities1,954     1,954 
Other1,967     1,967 
Southern Company Gas plant in service24,098     24,098 
Other plant in service2,097      
Total plant in service$146,114 $38,915 $59,458 $5,972 $15,034 $24,098 
At December 31, 2024:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
Electric utilities:
Generation$61,292 $16,801 $26,089 $2,946 $14,920 $ 
Transmission16,280 6,449 8,800 989   
Distribution28,678 10,373 16,887 1,418   
General/other6,547 2,878 3,260 344 41  
Electric utilities' plant in service112,797 36,501 55,036 5,697 14,961  
Southern Company Gas:
Natural gas transportation and distribution
18,896     18,896 
Storage facilities1,748     1,748 
Other1,694     1,694 
Southern Company Gas plant in service22,338     22,338 
Other plant in service2,008      
Total plant in service$137,143 $36,501 $55,036 $5,697 $14,961 $22,338 
The cost of replacements of property, exclusive of minor items of property, is capitalized. The cost of maintenance, repairs, and replacement of minor items of property is charged to other operations and maintenance expenses as incurred or performed with the exception of nuclear refueling costs and certain maintenance costs including those described below.
In accordance with orders from their respective state PSCs, Alabama Power and Georgia Power defer nuclear refueling outage operations and maintenance expenses to a regulatory asset when the charges are incurred. Alabama Power amortizes the costs over a subsequent 18-month period with Plant Farley's fall outage cost amortization beginning in January of the following year and spring outage cost amortization beginning in July of the same year. Georgia Power amortizes its costs over each unit's
II-160

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

operating cycle, or 18 months for Plant Vogtle Units 1 through 4 and 24 months for Plant Hatch Units 1 and 2. Georgia Power's amortization period begins the month the refueling outage starts.
The portion of Southern Company Gas' non-working gas used to maintain the structural integrity of natural gas storage facilities that is considered to be non-recoverable is depreciated, while the recoverable or retained portion is not depreciated.
See Note 9 for information on finance lease right-of-use (ROU) assets, net, which are included in property, plant, and equipment.
The Registrants have deferred certain implementation costs related to cloud hosting arrangements. At December 31, 2025 and 2024, deferred cloud implementation costs, net of amortization, which are included in other current assets and other deferred charges and assets on the Registrants' balance sheets, were as follows:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
Deferred cloud implementation costs, net:
At December 31, 2025
$231 $73 $87 $10 $9 $21 
At December 31, 2024
321 92 111 13 12 35 
Once a hosted software is placed into service, the related deferred costs are amortized on a straight-line basis over the remaining expected hosting arrangement term, including any renewal options that are reasonably certain of exercise. The amortization is reflected with the associated cloud hosting fees, which are generally reflected in other operations and maintenance expenses on the Registrants' statements of income. Amortization of deferred cloud implementation costs recognized in 2025, 2024, and 2023 was immaterial for Mississippi Power, Southern Power, and Southern Company Gas and was as follows for the other Registrants:
Southern Company
Alabama Power
Georgia Power
(in millions)
2025$53 $17 $20 
202456 17 22 
202346 11 19 
See Note 2 under "Regulatory Assets and Liabilities" for information on deferrals of certain other operations and maintenance costs associated with software and cloud computing projects by the traditional electric operating companies and natural gas distribution utilities, as authorized by their respective state PSCs or applicable state regulatory agencies.
Depreciation and Amortization
The traditional electric operating companies' and Southern Company Gas' depreciation of the original cost of utility plant in service is provided primarily by using composite straight-line rates. The approximate rates for 2025, 2024, and 2023 were as follows:
202520242023
Alabama Power4.0 %4.2 %4.1 %
Georgia Power3.4 %3.4 %3.8 %
Mississippi Power3.6 %3.3 %3.4 %
Southern Company Gas3.0 %2.9 %2.7 %
Depreciation studies are conducted periodically to update the composite rates. These studies are filed with the respective state PSC and/or other applicable state and federal regulatory agencies for the traditional electric operating companies and the natural gas distribution utilities. On April 1, 2025, the Mississippi PSC approved a stipulation between Mississippi Power and the Mississippi Public Utilities Staff for an $8 million increase in total annual depreciation effective January 1, 2025. See Note 2 for additional information.
When property, plant, and equipment subject to composite depreciation is retired or otherwise disposed of in the normal course of business, its original cost, together with the cost of removal, less salvage, is charged to accumulated depreciation. For other property dispositions, the applicable cost and accumulated depreciation are removed from the balance sheet accounts, and a gain or loss is recognized. Minor items of property included in the original cost of the asset are retired when the related property unit is retired.
II-161

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

At December 31, 2025 and 2024, accumulated depreciation for Southern Company and Southern Company Gas consisted of utility plant in service totaling $42.3 billion and $38.9 billion, respectively, for Southern Company and $6.0 billion and $5.6 billion, respectively, for Southern Company Gas, as well as other plant in service totaling $1.2 billion and $1.2 billion, respectively, for Southern Company and $265 million and $252 million, respectively, for Southern Company Gas. Other plant in service includes the non-utility assets of Southern Company Gas, as well as, for Southern Company, certain other non-utility subsidiaries. Depreciation of the original cost of other plant in service is provided primarily on a straight-line basis over estimated useful lives. Useful lives for Southern Company Gas's non-utility assets range from five to 10 years for transportation equipment, five to 40 years for storage facilities, and up to 78 years for other assets. Useful lives for the assets of Southern Company's other non-utility subsidiaries range up to 40 years.
Southern Power
Southern Power applies component depreciation, where depreciation is computed principally by the straight-line method over the estimated useful life of the asset. Certain of Southern Power's generation assets related to natural gas-fired facilities are depreciated on a units-of-production basis, using hours or starts, to better match outage and maintenance costs to the usage of, and revenues from, these assets. The primary assets in Southern Power's property, plant, and equipment are generating facilities, which generally have estimated useful lives as follows:
Southern Power Generating FacilityUseful life
Natural gas
Up to 50 years
Solar
Up to 35 years
Wind
Up to 35 years
When Southern Power's depreciable property, plant, and equipment is retired, or otherwise disposed of in the normal course of business, the applicable cost and accumulated depreciation is removed and a gain or loss is recognized in the consolidated statements of income. Southern Power reviews its estimated useful lives and salvage values on an ongoing basis. The results of these reviews could result in changes which could have a material impact on Southern Power's net income. In 2025 and 2024, Southern Power recorded accelerated depreciation related to equipment being replaced associated with wind repowering projects of $307 million and $9 million, respectively. See Note 15 under "Southern Power – Wind Repowering Projects" for additional information.
II-162

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Joint Ownership Agreements
At December 31, 2025, the Registrants' percentage ownership and investment (exclusive of nuclear fuel) in jointly-owned facilities in commercial operation were as follows:
Facility (Type)Percent
Ownership
Plant in ServiceAccumulated
Depreciation
CWIP
(in millions)
Alabama Power
Plant Greene County (natural gas) Units 1 and 2
60.0 %
(a)
$190 $163 $2 
Plant Miller (coal) Units 1 and 291.8 
(b)
2,181 901 19 
Georgia Power
Plant Hatch (nuclear) Units 1 and 2
50.1 %
(c)
$1,477 $593 $137 
Plant Vogtle (nuclear) Units 1 and 245.7 
(c)
3,598 2,326 240 
Plant Vogtle (nuclear) Units 3 and 4
45.7 
(c)
7,979 250 86 
Plant Scherer (coal) Units 1 and 28.4 
(c)
286 152 11 
Plant Scherer (coal) Unit 375.0 
(c)
1,323 793 56 
Rocky Mountain (pumped storage)25.4 
(d)
186 166 18 
Mississippi Power
Plant Greene County (natural gas) Units 1 and 2
40.0 %
(a)
$119 $94 $1 
Southern Company Gas
Dalton Pipeline (natural gas pipeline)50.0 %
(e)
$273 $36 $1 
(a)Jointly owned by Alabama Power and Mississippi Power and operated and maintained by Alabama Power.
(b)Jointly owned with PowerSouth and operated and maintained by Alabama Power.
(c)Georgia Power owns undivided interests in Plants Hatch, Vogtle, and Scherer in varying amounts jointly with one or more of the following entities: OPC, MEAG Power, Dalton, FP&L, and Jacksonville Electric Authority. Georgia Power has been contracted to operate and maintain the plants as agent for the co-owners and is jointly and severally liable for third-party claims related to these plants.
(d)Jointly owned with OPC, which is the operator of the plant.
(e)Jointly owned with The Williams Companies, Inc., the Dalton Pipeline is a 115-mile natural gas pipeline that serves as an extension of the Transcontinental Gas Pipe Line Company, LLC pipeline system into northwest Georgia. Southern Company Gas leases its 50% undivided ownership for approximately $26 million annually through 2042. The lessee is responsible for maintaining the pipeline during the lease term and for providing service to transportation customers under its FERC-regulated tariff.
The Registrants' proportionate share of their jointly-owned facility operating expenses is included in the corresponding operating expenses in the statements of income and each Registrant is responsible for providing its own financing.
Assets Subject to Lien
Mississippi Power provides retail service to its largest retail customer, Chevron Products Company (Chevron), at its refinery in Pascagoula, Mississippi through at least 2038 in accordance with agreements approved by the Mississippi PSC. The agreements grant Chevron a security interest in the co-generation assets located at the refinery and owned by Mississippi Power, with a lease receivable balance of $130 million at December 31, 2025, that is exercisable upon the occurrence of (i) certain bankruptcy events or (ii) other events of default coupled with specific reductions in steam output at the facility and a downgrade of Mississippi Power's credit rating to below investment grade by two of the three rating agencies. See Note 9 under "Lessor" for additional information.
See Note 8 under "Long-term Debt" for information regarding debt secured by certain assets of Georgia Power and Southern Company Gas.
6. ASSET RETIREMENT OBLIGATIONS
AROs are computed as the present value of the estimated costs for an asset's future retirement and are recorded in the period in which the liability is incurred. The estimated costs are capitalized as part of the related long-lived asset and depreciated over the asset's useful life. In the absence of quoted market prices, AROs are estimated using present value techniques in which estimates of future cash outlays associated with the asset retirements are discounted using a credit-adjusted risk-free rate. Estimates of the timing and amounts of future cash outlays are based on projections of when and how the assets will be retired and the cost of
II-163

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

future removal activities. Each traditional electric operating company and natural gas distribution utility has received accounting guidance from its state PSC or applicable state regulatory agency allowing the continued accrual or recovery of other retirement costs for long-lived assets that it does not have a legal obligation to retire. Accordingly, the accumulated removal costs for these obligations are reflected in the balance sheets as regulatory liabilities and amounts to be recovered are reflected in the balance sheets as regulatory assets.
The ARO liabilities for the traditional electric operating companies primarily relate to facilities that are subject to state and federal CCR rules, principally surface impoundments. In addition, Alabama Power and Georgia Power have retirement obligations related to the decommissioning of nuclear facilities (Alabama Power's Plant Farley and Georgia Power's ownership interests in Plants Hatch and Vogtle). See "Nuclear Decommissioning" herein for additional information. Other significant AROs include various landfill sites and asbestos removal for Alabama Power, Georgia Power, and Mississippi Power and gypsum cells and mine reclamation for Mississippi Power. The ARO liability for Southern Power primarily relates to its solar and wind facilities, which are located on long-term land leases requiring the restoration of land at the end of the lease.
The traditional electric operating companies and Southern Company Gas also have identified other retirement obligations, such as obligations related to certain electric transmission and distribution facilities, certain asbestos-containing material within long-term assets not subject to ongoing repair and maintenance activities, certain wireless communication towers, the disposal of polychlorinated biphenyls in certain transformers, leasehold improvements, equipment on customer property, and property associated with the Southern Company system's rail lines and natural gas pipelines. However, liabilities for the removal of these assets have not been recorded because the settlement timing for certain retirement obligations related to these assets is indeterminable and, therefore, the fair value of the retirement obligations cannot be reasonably estimated. A liability for these retirement obligations will be recognized when sufficient information becomes available to support a reasonable estimation of the ARO.
Southern Company and the traditional electric operating companies will continue to recognize in their respective statements of income allowed removal costs in accordance with regulatory treatment. Any differences between costs recognized in accordance with accounting standards related to asset retirement and environmental obligations and those reflected in rates are recognized as either a regulatory asset or liability in the balance sheets as ordered by the various state PSCs.
Details of the AROs included in the balance sheets are as follows:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
   Power(*)
(in millions)
Balance at December 31, 2023$10,317 $4,158 $5,665 $168 $150 
Liabilities incurred130 8 120  2 
Liabilities settled(566)(254)(270)(17) 
Accretion expense
400 153 232 5 7 
Cash flow revisions(347)(7)(332)(8) 
Balance at December 31, 2024$9,934 $4,058 $5,415 $148 $159 
Liabilities incurred6  6   
Liabilities settled(634)(269)(321)(19) 
Accretion expense
393 154 223 6 7 
Cash flow revisions(98)(264)204 (11) 
Balance at December 31, 2025$9,601 $3,679 $5,527 $124 $166 
(*)Included in other deferred credits and liabilities on Southern Power's consolidated balance sheets.
Following initial criticality for Plant Vogtle Unit 4 on February 14, 2024, Georgia Power recorded AROs of approximately $118 million. See "Nuclear Decommissioning" herein and Note 2 under "Georgia Power – Nuclear Construction" for additional information.
In September 2024, Georgia Power completed updated decommissioning cost site studies for Plants Hatch and Vogtle Units 1 through 4. The estimated cost of decommissioning based on the studies resulted in a decrease in Georgia Power's ARO liability of $389 million. See "Nuclear Decommissioning" herein for additional information.
In November 2024, Georgia Power recorded a net increase of approximately $60 million to its AROs related to the CCR Rule and the related state rule resulting from changes in estimates, including higher future inflation rates and the timing of closure activities.
II-164

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

In June 2025, Alabama Power recorded a net decrease of approximately $257 million to its AROs related to the CCR Rule and the related state rule resulting from changes in estimates, including lower future inflation rates, higher discount rates, and timing of closure activities.
Also in June 2025, Mississippi Power, as a joint owner of Alabama Power's Plant Greene County Units 1 and 2, recorded a net decrease of approximately $13 million to its AROs related to the CCR Rule and the related Alabama state rule resulting from changes in estimates, including lower future inflation rates, higher discount rates, and timing of closure activities.
In November 2025, Georgia Power recorded a net increase of approximately $200 million to its AROs related to the CCR Rule and related state rule resulting from higher inflation rates, changes in estimates, and timing of closure activities.
The cost estimates for AROs related to the disposal of CCR are based on information at December 31, 2025 using various assumptions related to closure and post-closure costs, timing of future cash outlays, inflation and discount rates, and the potential methods for complying with the CCR Rule and the related state rules. The traditional electric operating companies have periodically updated, and expect to continue periodically updating, their related cost estimates and ARO liabilities for each CCR unit as additional information related to these assumptions becomes available. Some of these updates have been, and future updates may be, material. The cost estimates for Alabama Power are based on closure-in-place for all surface impoundments. The cost estimates for Georgia Power and Mississippi Power are based on a combination of closure-in-place for some surface impoundments and closure by removal for others. Additionally, the closure designs and plans in the States of Alabama and Georgia are subject to approval by environmental regulatory agencies. Absent continued recovery of ARO costs through regulated rates, results of operations, cash flows, and financial condition for Southern Company and the traditional electric operating companies could be materially impacted. The ultimate outcome of these matters cannot be determined at this time. See Note 3 under "General Litigation Matters – Alabama Power" for additional information.
Nuclear Decommissioning
The NRC requires licensees of commercial nuclear power reactors to establish a plan for providing reasonable assurance of funds for future decommissioning. Alabama Power and Georgia Power have external trust funds (Funds) to comply with the NRC's regulations. Use of the Funds is restricted to nuclear decommissioning activities. The Funds are managed and invested in accordance with applicable requirements of various regulatory bodies, including the NRC, the FERC, and state PSCs, as well as the IRS. While Alabama Power and Georgia Power are allowed to prescribe an overall investment policy to the Funds' managers, neither Southern Company nor its subsidiaries or affiliates are allowed to engage in the day-to-day management of the Funds or to mandate individual investment decisions. Day-to-day management of the investments in the Funds is delegated to unrelated third-party managers with oversight by the management of Alabama Power and Georgia Power. The Funds' managers are authorized, within certain investment guidelines, to actively buy and sell securities at their own discretion in order to maximize the return on the Funds' investments. The Funds are invested in a tax-efficient manner in a diversified mix of equity and fixed income securities and are reported as trading securities.
Alabama Power and Georgia Power record the investment securities held in the Funds at fair value, as disclosed in Note 13, as management believes that fair value best represents the nature of the Funds. Gains and losses, whether realized or unrealized, are recorded in the regulatory liability for AROs in the balance sheets and are not included in net income or OCI. Fair value adjustments and realized gains and losses are determined on a specific identification basis.
II-165

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Investment securities in the Funds at December 31, 2025 and 2024 were as follows:
Southern
Company
Alabama
Power
Georgia
Power
(in millions)
At December 31, 2025:
Equity securities$1,609 $963 $646 
Debt securities1,082 363 719 
Other securities254 214 40 
Total investment securities in the Funds$2,945 $1,540 $1,405 
At December 31, 2024:
Equity securities$1,413 $848 $565 
Debt securities976 335 641 
Other securities232 202 30 
Total investment securities in the Funds
$2,621 $1,385 $1,236 
These amounts exclude receivables related to investment income and pending investment sales and payables related to pending investment purchases.
The fair value increases (decreases) of the Funds, including unrealized gains (losses) and reinvested interest and dividends and excluding the Funds' expenses, for 2025, 2024, and 2023 are shown in the table below.
Southern
Company
Alabama
Power
Georgia
Power
(in millions)
Fair value increases
2025$348 $191 $157 
2024229 143 86 
2023281 157 124 
Unrealized gains
At December 31, 2025$216 $111 $105 
At December 31, 2024113 64 49 
At December 31, 2023241 119 122 
The investment securities held in the Funds continue to be managed with a long-term focus. Accordingly, all purchases and sales within the Funds are presented separately in the statements of cash flows as investing cash flows, consistent with the nature of the securities and purpose for which the securities were acquired.
For Alabama Power, approximately $11 million and $12 million at December 31, 2025 and 2024, respectively, previously recorded in internal reserves is being transferred into the Funds through 2040 as approved by the Alabama PSC.
The NRC's minimum external funding requirements are based on a generic estimate of the cost to decommission only the radioactive portions of a nuclear unit based on the size and type of reactor. Alabama Power and Georgia Power have filed plans with the NRC designed to ensure that, over time, the deposits and earnings of the Funds will provide the minimum funding amounts prescribed by the NRC.
II-166

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

At December 31, 2025 and 2024, the accumulated provisions for the external decommissioning trust funds were as follows:
20252024
(in millions)
Alabama Power
Plant Farley$1,540 $1,385 
Georgia Power
Plant Hatch$825 $735 
Plant Vogtle Units 1 and 2519 460 
Plant Vogtle Units 3 and 461 41 
Total$1,405 $1,236 
Site study cost is the estimate to decommission a specific facility as of the site study year. The decommissioning cost estimates are based on removal of the plant from service and prompt dismantlement. The actual decommissioning costs may vary from these estimates because of changes in the assumed date of decommissioning, changes in NRC requirements, or changes in the assumptions used in making these estimates. The estimated costs of decommissioning at December 31, 2025 based on the most current studies were as follows:
Alabama Power
   Georgia Power(*)
Plant
Farley
Plant
Hatch
Plant Vogtle
Units 1 and 2
Plant Vogtle
Unit 3 and 4
Most current study year
2023202420242024
Decommissioning periods:
Beginning year2037203420472062
Completion year2087208820922074
(in millions)
Site study costs:
Radiated structures$1,402 $795 $674 $599 
Spent fuel management513 306 255 88 
Non-radiated structures133 77 107 89 
Total site study costs$2,048 $1,178 $1,036 $776 
(*)Based on Georgia Power's ownership interests.
For ratemaking purposes, Alabama Power's decommissioning costs are based on the site study and Georgia Power's decommissioning costs are based on the NRC generic estimate to decommission the radioactive portion of the facilities and the site study estimate for spent fuel management. Significant assumptions used to determine these costs for ratemaking were an estimated inflation rate of 4.5% for Plant Farley, 2.5% for Plants Hatch and Vogtle Units 1 and 2, and 2.3% for Plant Vogtle Units 3 and 4 and an estimated trust earnings rate of 7.0% for Plant Farley, 4.5% for Plants Hatch and Vogtle Units 1 and 2, and 4.3% for Plant Vogtle Units 3 and 4.
Amounts previously contributed to the Funds for Plant Farley are currently projected to be adequate to meet the decommissioning obligations. Alabama Power's site-specific estimates of decommissioning costs for Plant Farley are updated every five years. The next site study for Alabama Power is expected to be completed in 2028. Projections of funds are reviewed with the Alabama PSC to ensure that, over time, the deposits and earnings of the Funds will provide adequate funding to cover the site-specific costs. If necessary, Alabama Power would seek the Alabama PSC's approval to address any changes in a manner consistent with NRC and other applicable requirements.
Effective January 1, 2023, as approved in the 2022 ARP, there is no annual decommissioning cost for ratemaking for Plant Hatch and Plant Vogtle Units 1 and 2. Any funding amount required by the NRC during the period covered by the 2022 ARP, including the ARP Extension Period, will be deferred to a regulatory asset and recovery is expected to be determined in Georgia Power's next base rate case. See Note 2 under "Georgia Power – Rate Plans – 2022 ARP" for additional information. Effective August 1, 2023, as approved under the Plant Vogtle Unit 3 and Common Facilities rate proceeding, Georgia Power's annual decommissioning cost for ratemaking is $8 million for Plant Vogtle Unit 3. Effective May 1, 2024, as approved under the
II-167

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Prudency Stipulation, Georgia Power's annual decommissioning cost for ratemaking is $8 million for Plant Vogtle Unit 4. See Note 2 under "Georgia Power – Nuclear Construction – Regulatory Matters" for additional information.
7. CONSOLIDATED ENTITIES AND EQUITY METHOD INVESTMENTS
The Registrants may hold ownership interests in a number of business ventures with varying ownership structures. Partnership interests and other variable interests are evaluated to determine if each entity is a VIE. If a venture is a VIE for which a Registrant is the primary beneficiary, the assets, liabilities, and results of operations of the entity are consolidated. The Registrants reassess the conclusion as to whether an entity is a VIE upon certain occurrences, which are deemed reconsideration events.
For entities that are not determined to be VIEs, the Registrants evaluate whether they have control or significant influence over the investee to determine the appropriate consolidation and presentation. Generally, entities under the control of a Registrant are consolidated, and entities over which a Registrant can exert significant influence, but which a Registrant does not control, are accounted for under the equity method of accounting.
Investments accounted for under the equity method are recorded within equity investments in unconsolidated subsidiaries in the balance sheets and, for Southern Company and Southern Company Gas, the equity income is recorded within earnings from equity method investments in the statements of income. See "SEGCO" and "Southern Company Gas" herein for additional information.
Southern Company
At December 31, 2025 and 2024, Southern Holdings had equity method investments totaling $124 million and $128 million, respectively, primarily related to investments in venture capital funds focused on energy and utility investments. The net loss from these investments totaled $18 million for the year ended December 31, 2025. Earnings/losses from these investments were immaterial for the years ended December 31, 2024 and 2023.
SEGCO
Alabama Power and Georgia Power own equally all of the outstanding capital stock of SEGCO, which owns electric generating units at Plant Gaston with a total rated capacity of 1,020 MWs, as well as associated transmission facilities. Retirement of SEGCO's generating units was previously expected to occur by December 31, 2028. However, upon further analysis, Alabama Power, in conjunction with Georgia Power, now expects to operate Plant Gaston Units 1 through 4 through December 31, 2034. See Note 2 under "Georgia Power – Integrated Resource Plans – 2025 IRP" for additional information. Alabama Power and Georgia Power account for SEGCO using the equity method; Southern Company consolidates SEGCO. The capacity of these units is sold equally to Alabama Power and Georgia Power. Alabama Power and Georgia Power make payments sufficient to provide for the operating expenses, taxes, interest expense, and an ROE. The share of purchased power included in purchased power, affiliates in the statements of income totaled $130 million in 2025, $115 million in 2024, and $112 million in 2023 for Alabama Power and $133 million in 2025, $118 million in 2024, and $115 million in 2023 for Georgia Power.
SEGCO paid dividends of $24 million in 2025, $20 million in 2024, and $25 million in 2023, one half of which were paid to each of Alabama Power and Georgia Power. In addition, Alabama Power and Georgia Power each recognize 50% of SEGCO's net income.
Alabama Power, which owns and operates a generating unit adjacent to the SEGCO generating units, has a joint ownership agreement with SEGCO for the ownership of an associated gas pipeline. Alabama Power owns 14% of the pipeline with the remaining 86% owned by SEGCO.
See Note 3 under "Guarantees" for additional information regarding guarantees of Alabama Power and Georgia Power related to SEGCO.
Southern Power
Variable Interest Entities
Southern Power has certain subsidiaries that are determined to be VIEs. Southern Power is considered the primary beneficiary of these VIEs because it controls the most significant activities of the VIEs, including operating and maintaining the respective assets, and has the obligation to absorb expected losses of these VIEs to the extent of its equity interests.
SP Solar
SP Solar is owned by Southern Power and a limited partner. A wholly-owned subsidiary of Southern Power is the general partner and holds a 1% ownership interest, and another wholly-owned subsidiary of Southern Power owns a 66% ownership interest. The
II-168

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

limited partner holds the remaining 33% noncontrolling interest. SP Solar qualifies as a VIE since the arrangement is structured as a limited partnership and the 33% limited partner does not have substantive kick-out rights against the general partner.
At December 31, 2025 and 2024, SP Solar had total assets of $5.2 billion and $5.4 billion, respectively, total liabilities of $360 million and $372 million, respectively, and noncontrolling interests of $0.9 billion and $1.0 billion, respectively. Cash distributions from SP Solar are allocated 67% to Southern Power and 33% to the limited partner in accordance with their partnership interest percentage. Under the terms of the limited partnership agreement, distributions without limited partner consent are limited to available cash and SP Solar is obligated to distribute all such available cash to its partners each quarter. Available cash includes all cash generated in the quarter subject to the maintenance of appropriate operating reserves.
Southern Power consolidates SP Solar, as the primary beneficiary, since it controls the most significant activities of the entity, including operating and maintaining its assets. Certain transfers and sales of the assets in the VIE are subject to partner consent and the liabilities are non-recourse to the general credit of Southern Power. Liabilities consist of customary working capital items and do not include any long-term debt.
SP Wind
SP Wind was owned by Southern Power and three financial investors through December 31, 2025. A wholly-owned subsidiary of Southern Power owned 100% of the Class B membership interests and the three financial investors owned 100% of the Class A membership interests. In July 2025, Southern Power notified the Class A members of its intent to exercise the option to purchase all Class A membership interests in the SP Wind tax equity partnership under the terms of the limited liability agreement. On December 31, 2025, Southern Power purchased 100% of the noncontrolling Class A membership interests for approximately $282 million. Subsequent to the transaction, Southern Power became the sole owner of SP Wind and its portfolio of eight operating wind facilities, and the partnership was dissolved. See Note 15 under "Southern Power – Purchase of Renewable Facility Interests" for additional information.
Prior to this transaction, SP Wind qualified as a VIE since the structure of the arrangement was similar to a limited partnership and the Class A members did not have substantive kick-out rights against Southern Power. At December 31, 2024, SP Wind had total assets of $2.0 billion, total liabilities of $177 million, and noncontrolling interests of $35 million.
Other Variable Interest Entities
Southern Power has other consolidated VIEs that relate to certain subsidiaries that have either sold noncontrolling interests to tax equity investors or acquired less than a 100% interest from facility developers. These entities are considered VIEs because the arrangements are structured similar to a limited partnership and the noncontrolling members do not have substantive kick-out rights.
At December 31, 2025 and 2024, the other VIEs had total assets of $1.6 billion, total liabilities of $236 million and $224 million, respectively, and noncontrolling interests of $617 million and $691 million, respectively. Under the terms of the partnership agreements, distributions of all available cash are required each month or quarter and additional distributions require partner consent.
Equity Method Investments
During 2023, Southern Power sold its remaining equity method investments in wind projects and received proceeds totaling $50 million. Earnings (loss) from these investments, including the gains associated with the sales, were immaterial for 2023.
Southern Company Gas
The carrying amounts of Southern Company Gas' equity method investments at December 31, 2025 and 2024 were as follows:
Investment BalanceAt December 31, 2025At December 31, 2024
(in millions)
SNG$1,148 $1,245 
Other
34 34 
Total$1,182 $1,279 
The earnings from Southern Company Gas' equity method investment related to SNG were $127 million in 2025, $146 million in 2024, and $139 million in 2023. The earnings from Southern Company Gas' other equity method investments were immaterial for all periods presented.
II-169

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

8. FINANCING
Long-term Debt
Details of long-term debt at December 31, 2025 and 2024 are provided in the following table:
At December 31, 2025
Balance Outstanding at
December 31,
MaturityWeighted Average
Interest Rate
20252024
(in millions)
Southern Company
Senior notes(a)
2026-20754.38%$49,922 $44,862 
Junior subordinated notes2027-20854.82%9,922 7,389 
FFB loans(b)
2026-20442.88%4,617 4,703 
Revenue bonds(c)
2026-20633.14%3,323 3,379 
First mortgage bonds(d)
2026-20653.93%2,925 2,775 
Medium-term notes2026-20277.03%84 84 
Other long-term debt2026-20454.56%603 209 
Finance lease obligations(e)
768 287 
Unamortized fair value adjustment249 275 
Unamortized debt premium (discount), net(56)(58)
Unamortized debt issuance expenses(488)(419)
Total long-term debt71,869 63,486 
Less: Amount due within one year(a)
6,220 4,718 
Total long-term debt excluding amount due within one year$65,649 $58,768 
Alabama Power
Senior notes2026-20754.02%$10,725 $9,875 
Revenue bonds(c)
2026-20633.11%1,300 1,300 
Other long-term debt2026-20305.32%65 61 
Finance lease obligations(e)
12 4 
Unamortized debt premium (discount), net(20)(19)
Unamortized debt issuance expenses(69)(67)
Total long-term debt12,013 11,154 
Less: Amount due within one year625 655 
Total long-term debt excluding amount due within one year$11,388 $10,499 
Georgia Power
Senior notes2026-20744.48%$13,692 $11,292 
Junior subordinated notes20775.00%270 270 
FFB loans(b)
2026-20442.88%4,617 4,703 
Revenue bonds(c)
2026-20623.16%1,923 1,968 
Other long-term debt20264.59%400  
Finance lease obligations(e)
734 261 
Unamortized debt premium (discount), net(17)(21)
Unamortized debt issuance expenses(127)(123)
Total long-term debt21,492 18,350 
Less: Amount due within one year1,370 966 
Total long-term debt excluding amount due within one year$20,122 $17,384 
II-170

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

At December 31, 2025
Balance Outstanding at
December 31,
MaturityWeighted Average
Interest Rate
20252024
(in millions)
Mississippi Power
Senior notes2026-20554.40%$1,675 $1,575 
Revenue bonds(c)
2027-20522.94%101 111 
Finance lease obligations(e)
19 14 
Unamortized debt premium (discount), net1 2 
Unamortized debt issuance expenses(10)(9)
Total long-term debt1,786 1,693 
Less: Amount due within one year66 12 
Total long-term debt excluding amount due within one year$1,720 $1,681 
Southern Power
Senior notes(a)
2026-20464.65%$2,963 $2,695 
Unamortized debt premium (discount), net(6)(4)
Unamortized debt issuance expenses(17)(11)
Total long-term debt2,940 2,680 
Less: Amount due within one year(a)
587 500 
Total long-term debt excluding amount due within one year$2,353 $2,180 
Southern Company Gas
Senior notes2026-20514.46%$5,999 $5,375 
First mortgage bonds(d)
2026-20653.93%2,925 2,775 
Medium-term notes2026-20277.03%84 84 
Other long-term debt2026-20453.81%68 68 
Unamortized fair value adjustment249 275 
Unamortized debt premium (discount), net(11)(9)
Unamortized debt issuance expenses(40)(37)
Total long-term debt9,274 8,531 
Less: Amount due within one year531 302 
Total long-term debt excluding amount due within one year$8,743 $8,229 
(a)Includes a fair value gain (loss) related to Southern Power's foreign currency hedge on its euro-denominated senior notes of $23 million at December 31, 2025, which is also included in amount due within one year, and $(45) million at December 31, 2024.
(b)Secured by a first priority lien on (i) Georgia Power's undivided ownership interest in Plant Vogtle Units 3 and 4 (primarily the units, the related real property, and any nuclear fuel loaded in the reactor core) and (ii) Georgia Power's rights and obligations under the principal contracts relating to Plant Vogtle Units 3 and 4. See "DOE Loan Guarantee Borrowings" herein for additional information.
(c)Revenue bond obligations represent loans to the traditional electric operating companies from public authorities of funds derived from sales by such authorities of revenue bonds issued to finance pollution control and solid waste disposal and wastewater facilities. In some cases, the revenue bond obligations represent obligations under installment sales agreements with respect to facilities constructed with the proceeds of revenue bonds issued by public authorities. The traditional electric operating companies are required to make payments sufficient for the authorities to meet principal and interest requirements of such bonds. Proceeds from certain issuances are restricted until qualifying expenditures are incurred.
(d)Secured by substantially all of Nicor Gas' properties.
(e)Secured by the underlying lease ROU asset. See Note 9 for additional information.
II-171

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Maturities of long-term debt for the next five years are as follows:
Southern
   Company(a)
Alabama
   Power(b)
Georgia
   Power(c)
Mississippi
Power
Southern
   Power(d)
Southern
Company
Gas
(in millions)
2026$6,211 $628 $1,371 $66 $564 $530 
20273,407 552 1,017 11  154 
20285,464 108 1,619 358  600 
20291,993 1 862 2  150 
20304,103 651 704 52 550 150 
(a)See notes (b), (c), and (d) below.
(b)Alabama Power's 2026 maturities include $200 million aggregate principal amount of Series 2023A Floating Rate Senior Notes due May 15, 2073 that are repayable at the option of the holders at certain dates that began in 2024 and $100 million aggregate principal amount of Series 2025B Floating Rate Senior Notes due August 15, 2075 that are repayable at the option of the holders at certain dates beginning in 2026. As a result, the senior notes are classified as securities due within one year on the balance sheets of Southern Company and Alabama Power at December 31, 2025.
(c)Amounts include principal amortization related to the FFB borrowings; however, the final maturity date is February 20, 2044. See "DOE Loan Guarantee Borrowings" herein for additional information. Georgia Power's 2026 maturities include approximately $117 million aggregate principal amount of Series 2024C Floating Rate Senior Notes due November 15, 2074 that are repayable at the option of the holders at certain dates that began in 2025. As a result, the senior notes are classified as securities due within one year on the balance sheets of Southern Company and Georgia Power at December 31, 2025.
(d)Southern Power's 2026 maturities include $564 million of euro-denominated debt at the U.S. dollar-denominated hedge settlement amount.
DOE Loan Guarantee Borrowings
Pursuant to the loan guarantee program established under Title XVII of the Energy Policy Act of 2005 (Title XVII Loan Guarantee Program), Georgia Power and the DOE entered into a loan guarantee agreement in 2014 and the Amended and Restated Loan Guarantee Agreement in 2019. Under the Amended and Restated Loan Guarantee Agreement, the DOE agreed to guarantee the obligations of Georgia Power under the FFB Credit Facilities. Under the FFB Credit Facilities, Georgia Power was authorized to make term loan borrowings through the FFB in an amount up to approximately $5.130 billion.
In 2021, Georgia Power made the final borrowings under the FFB Credit Facilities and no further borrowings are permitted. During 2025, Georgia Power made principal amortization payments of $86 million under the FFB Credit Facilities. At December 31, 2025 and 2024, Georgia Power had $4.6 billion and $4.7 billion of borrowings outstanding under the FFB Credit Facilities, respectively.
All borrowings under the FFB Credit Facilities are full recourse to Georgia Power, and Georgia Power is obligated to reimburse the DOE for any payments the DOE is required to make to the FFB under its guarantee. Georgia Power's reimbursement obligations to the DOE are secured by a first priority lien on (i) Georgia Power's undivided ownership interest in Plant Vogtle Units 3 and 4 (primarily the units, the related real property, and any nuclear fuel loaded in the reactor core) and (ii) Georgia Power's rights and obligations under the principal contracts relating to Plant Vogtle Units 3 and 4. There are no restrictions on Georgia Power's ability to grant liens on other property.
The final maturity date for each advance under the FFB Credit Facilities is February 20, 2044. Interest is payable quarterly and principal payments began in 2020. Each borrowing under the FFB Credit Facilities bears interest at a fixed rate equal to the applicable U.S. Treasury rate at the time of the borrowing plus a spread equal to 0.375%.
Under the Amended and Restated Loan Guarantee Agreement, Georgia Power is subject to customary borrower affirmative and negative covenants and events of default. In addition, Georgia Power is subject to project-related reporting requirements and other project-specific covenants and events of default.
In the event certain mandatory prepayment events occur, Georgia Power will be required to prepay the outstanding principal amount of all borrowings under the FFB Credit Facilities over a period of five years (with level principal amortization). Among other things, these mandatory prepayment events include (i) loss of necessary governmental approvals for operation of Plant Vogtle Units 3 and 4; (ii) loss of regulation by the Georgia PSC; (iii) cost disallowances by the Georgia PSC that could have a material adverse effect on Georgia Power's ability to repay the outstanding borrowings under the FFB Credit Facilities; (iv) certain material casualty losses or a governmental taking of Plant Vogtle Units 3 and 4; or (v) loss of access to the intellectual property rights necessary to operate Plant Vogtle Units 3 and 4. Under certain circumstances, insurance proceeds and any proceeds from an event of taking must be applied to immediately prepay outstanding borrowings under the FFB Credit Facilities.
II-172

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Georgia Power also may voluntarily prepay outstanding borrowings under the FFB Credit Facilities. Under the FFB Credit Facilities, any prepayment (whether mandatory or optional) will be made with a make-whole premium or discount, as applicable.
See Note 2 under "Georgia Power – Nuclear Construction" for additional information.
Secured Debt
Each of Southern Company's subsidiaries is organized as a legal entity, separate and apart from Southern Company and its other subsidiaries. There are no agreements or other arrangements among the Southern Company system companies under which the assets of one company have been pledged or otherwise made available to satisfy obligations of Southern Company or any of its other subsidiaries.
As discussed under "Long-term Debt" herein, the Registrants had secured debt outstanding at December 31, 2025 and 2024. Each Registrant's senior notes, junior subordinated notes, revenue bond obligations, bank term loans, credit facility borrowings, and notes payable are effectively subordinated to all secured debt of each respective Registrant.
Equity Units
In May 2022, Southern Company remarketed $862.5 million aggregate principal amount of its Series 2019A Remarketable Junior Subordinated Notes due August 1, 2024 (2019A RSNs) and $862.5 million aggregate principal amount of its Series 2019B Remarketable Junior Subordinated Notes due August 1, 2027 (2019B RSNs), pursuant to the terms of its 2019 Series A Equity Units (2019 Equity Units). In connection with the remarketing, the interest rates on the 2019A RSNs and the 2019B RSNs were reset to 4.475% and 5.113%, respectively, payable on a semi-annual basis. In August 2022, the proceeds were ultimately used to settle the purchase contracts entered into as part of the 2019 Equity Units and Southern Company issued approximately 25.2 million shares of common stock and received proceeds of $1.725 billion. In August 2024, Southern Company repaid at maturity the $862.5 million 2019A RSNs. At December 31, 2025 and 2024, the 2019B RSNs were included on Southern Company's consolidated balance sheets in long-term debt.
In November 2025, Southern Company issued 40 million 2025 Series A Equity Units (2025 Equity Units), initially in the form of corporate units (Corporate Units), at a stated amount of $50 per Corporate Unit, for a total of $2 billion. Net proceeds from the issuance were approximately $1.965 billion. Southern Company used a portion of the net proceeds to repurchase (i) approximately $674.4 million aggregate principal amount of the Series 2023A 3.875% Convertible Senior Notes due December 15, 2025 (Series 2023A Convertible Senior Notes) and (ii) approximately $342.0 million aggregate principal amount of the Series 2024A 4.50% Convertible Senior Notes due June 15, 2027 (Series 2024A Convertible Senior Notes). See "Convertible Senior Notes" herein for additional information regarding the repurchase of convertible senior notes.
Each Corporate Unit is comprised of (i) a stock purchase contract, which obligates the holder to purchase from Southern Company, no later than December 15, 2028, a certain number of shares of Southern Company's common stock for $50 in cash (Stock Purchase Contract), (ii) a 1/40 undivided beneficial ownership interest in $1,000 principal amount of Southern Company's Series 2025B Remarketable Senior Notes due 2030 (Series 2025B RSNs), and (iii) a 1/40 undivided beneficial ownership interest in $1,000 principal amount of Southern Company's Series 2025C Remarketable Senior Notes due 2033 (together with the Series 2025B RSNs, the 2025 RSNs). Southern Company has agreed to remarket the 2025 RSNs in 2028, at which time each interest rate on the 2025 RSNs will reset at the applicable market rate. Holders may choose to either remarket their 2025 RSNs, receive the proceeds, and use those funds to settle the related Stock Purchase Contract or retain the 2025 RSNs and use other funds to settle the related Stock Purchase Contract. If the remarketing is unsuccessful, holders will have the right to put their 2025 RSNs to Southern Company at a price equal to the principal amount. The Corporate Units carry an annual distribution rate of 7.125% of the stated amount, which is comprised of a quarterly interest payment on the 2025 RSNs of 4.15% per year and a quarterly contract adjustment payment of 2.975% per year.
Each Stock Purchase Contract obligates the holder to purchase, and Southern Company to sell, for $50 a number of shares of Southern Company common stock determined based on the applicable market value (as determined under the related Stock Purchase Contract) in accordance with the conversion ratios set forth below (subject to anti-dilution adjustments):
If the applicable market value equals or exceeds $116.44, 0.4294 shares.
If the applicable market value is less than $116.44 but greater than $93.15, a number of shares equal to $50 divided by the applicable market value.
If the applicable market value is less than or equal to $93.15, 0.5368 shares.
A holder's ownership interest in the 2025 RSNs is pledged to Southern Company to secure the holder's obligation under the related Stock Purchase Contract. If a holder of a Stock Purchase Contract chooses at any time to have its 2025 RSNs released from the pledge, such holder's obligation under such Stock Purchase Contract must be secured by a U.S. Treasury security equal to the aggregate principal amount of the 2025 RSNs. At the time of issuance, the 2025 RSNs were recorded on Southern
II-173

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Company's consolidated balance sheet as long-term debt and the present value of the contract adjustment payments of $173 million was recorded as a liability, representing the obligation to make contract adjustment payments, with an offsetting reduction to paid-in capital. The liability balance at December 31, 2025 was $173 million, of which $59 million was classified as current. The difference of $12 million between the face value and present value of the contract adjustment payments will be accreted to interest expense on the consolidated statements of income over the three-year period ending in 2028. The liability recorded for the contract adjustment payments is considered non-cash and excluded from the consolidated statements of cash flow. To settle the Stock Purchase Contracts, Southern Company will be required to issue a maximum of approximately 21.5 million shares of common stock (subject to anti-dilution adjustments and a make-whole adjustment if certain fundamental changes occur).
Convertible Senior Notes
In February 2023, Southern Company issued $1.5 billion aggregate principal amount of Series 2023A Convertible Senior Notes. In March 2023, Southern Company issued an additional $225 million aggregate principal amount of the Series 2023A Convertible Senior Notes upon the exercise by the initial purchasers of their over-allotment option.
In May 2024, Southern Company issued $1.5 billion aggregate principal amount of Series 2024A Convertible Senior Notes.
In May 2025, Southern Company issued $1.65 billion aggregate principal amount of Series 2025A 3.25% Convertible Senior Notes due June 15, 2028 (Series 2025A Convertible Senior Notes). Southern Company used a portion of the proceeds from the Series 2025A Convertible Senior Notes to repurchase approximately $781.6 million of the $1.725 billion aggregate principal amount then outstanding of the Series 2023A Convertible Senior Notes and approximately $328.1 million of the $1.5 billion aggregate principal amount then outstanding of the Series 2024A Convertible Senior Notes, in each case, through privately negotiated transactions with a limited number of holders thereof.
In November 2025, using a portion the net proceeds from the 2025 Equity Units, Southern Company repurchased approximately an additional $674.4 million of the remaining approximately $943.4 million aggregate principal amount outstanding of the Series 2023A Convertible Senior Notes and approximately an additional $342.0 million of the remaining approximately $1.172 billion aggregate principal amount outstanding of the Series 2024A Convertible Senior Notes, in each case, through privately negotiated transactions with a limited number of holders thereof. See "Equity Units" herein for additional information.
Southern Company evaluated these repurchases and determined that all of the repurchased notes were accounted for as extinguishment of debt. As a result of these transactions, Southern Company recognized a total loss on extinguishment of debt of $252 million during 2025 within interest expense in the consolidated statements of income.
On December 15, 2025, the Series 2023A Convertible Senior Notes matured and Southern Company settled its related conversion obligations to holders by (i) paying cash in respect of the approximately $269.1 million aggregate principal amount remaining outstanding and (ii) issuing approximately 255 thousand shares of common stock for the excess of its conversion obligation over such principal amount. These shares were recognized at par value in paid-in capital on Southern Company's balance sheets.
Interest on the Series 2024A Convertible Senior Notes and the Series 2025A Convertible Senior Notes is payable semiannually. The Series 2024A Convertible Senior Notes and the Series 2025A Convertible Senior Notes will mature on June 15, 2027 and 2028, respectively, unless earlier converted or repurchased, but are not redeemable at the option of Southern Company. Both the Series 2024A Convertible Senior Notes and the Series 2025A Convertible Senior Notes are direct, unsecured, and unsubordinated obligations of Southern Company, ranking equally with all of Southern Company's other unsecured and unsubordinated indebtedness from time to time outstanding, and are effectively subordinated to all secured indebtedness of Southern Company.
Under the following circumstances, holders may convert their Series 2024A Convertible Senior Notes and their Series 2025A Convertible Senior Notes at their option prior to the close of business on the business day preceding March 15, 2027 and 2028, respectively:
during any calendar quarter (and only during such calendar quarter), if the last reported sale price of Southern Company's common stock for at least 20 trading days (whether or not consecutive) during the period of 30 consecutive trading days ending on, and including, the last trading day of the immediately preceding calendar quarter is greater than or equal to 130% of the applicable conversion price of the Series 2024A Convertible Senior Notes or the Series 2025A Convertible Senior Notes, as the case may be, on each applicable trading day as determined by Southern Company;
during the five business day period after any 10 consecutive trading day period (Measurement Period) in which the applicable trading price per $1,000 principal amount of Series 2024A Convertible Senior Notes or Series 2025A Convertible Senior Notes, as the case may be, for each trading day of the Measurement Period was less than 98% of the product of the last reported sale price of the common stock and the applicable conversion rate on each such trading day; or
upon the occurrence of certain corporate events specified in the respective supplemental indentures governing the Series 2024A Convertible Senior Notes and the Series 2025A Convertible Senior Notes.
II-174

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

On or after March 15, 2027 and 2028, for the Series 2024A Convertible Senior Notes and the Series 2025A Convertible Senior Notes, respectively, a holder may convert all or any portion of its Series 2024A Convertible Senior Notes or its Series 2025A Convertible Senior Notes, as the case may be, at any time prior to the close of business on the second scheduled trading day immediately preceding the applicable maturity date regardless of the foregoing conditions.
Southern Company will settle conversions of the Series 2024A Convertible Senior Notes and the Series 2025A Convertible Senior Notes by paying cash up to the aggregate principal amount of the Series 2024A Convertible Senior Notes and the Series 2025A Convertible Senior Notes to be converted and paying or delivering, as the case may be, cash, shares of common stock, or a combination of cash and shares of common stock, at Southern Company's election, in respect of the remainder, if any, of Southern Company's conversion obligation in excess of the aggregate principal amount of the Series 2024A Convertible Senior Notes and the Series 2025A Convertible Senior Notes being converted. The Series 2024A Convertible Senior Notes are initially convertible at a rate of 10.8166 shares of common stock per $1,000 principal amount converted, which is approximately equal to $92.45 per share of common stock. The Series 2025A Convertible Senior Notes are initially convertible at a rate of 8.8077 shares of common stock per $1,000 principal amount converted, which is approximately equal to $113.54 per share of common stock. These conversion rates will be subject to adjustment upon the occurrence of certain specified events but will not be adjusted for accrued and unpaid interest. In addition, upon the occurrence of a make-whole fundamental change (as defined in the respective supplemental indentures governing the Series 2024A Convertible Senior Notes and the Series 2025A Convertible Senior Notes), Southern Company will, in certain circumstances, increase the applicable conversion rate by a number of additional shares of common stock for conversions in connection with the make-whole fundamental change.
Upon the occurrence of a fundamental change, other than an excluded fundamental change (each as defined in the respective supplemental indentures governing the Series 2024A Convertible Senior Notes and the Series 2025A Convertible Senior Notes), holders of the Series 2024A Convertible Senior Notes and the Series 2025A Convertible Senior Notes may require Southern Company to purchase all or a portion of their Series 2024A Convertible Senior Notes and their Series 2025A Convertible Senior Notes, in principal amounts equal to $1,000 or an integral multiple thereof, for cash at a price equal to 100% of the principal amount of the Series 2024A Convertible Senior Notes and the Series 2025A Convertible Senior Notes to be purchased plus any accrued and unpaid interest.
Equity Distribution Agreement
In May 2024, Southern Company established an at-the-market program by entering into an equity distribution agreement pursuant to which it may sell, from time to time, up to an aggregate of 50 million shares of its common stock, including through forward sale contracts.
II-175

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

The table below reflects shares of Southern Company common stock sold and settled under separate forward sale contracts with forward purchasers during the years ended December 31, 2025 and 2024.
Shares Sold
Initial Forward
Price Per Share
To be Settled On or
Before
Forward Price
Per Share Settled
Shares Issued to
Settle
Settlement Date
Sold during 2024
1,000,000$86.5645December 31, 2025$86.81511,000,000December 3, 2025
1,000,000$87.9658December 31, 2025$88.13481,000,000December 3, 2025
143,920$83.3293December 31, 2025$83.0276143,920December 3, 2025
Sold during 2025
292,694$83.3293December 31, 2025$83.0276292,694December 3, 2025
563,386$87.9027December 31, 2025$88.0621563,386December 3, 2025
1,000,000$88.7502June 30, 2026$88.86121,000,000December 3, 2025
1,000,000$88.7739June 30, 2026$88.83191,000,000December 3, 2025
1,000,000$91.2856June 30, 2026$91.39951,000,000December 3, 2025
1,000,000$89.1444June 30, 2026$89.14041,000,000December 3, 2025
1,000,000$88.8490June 30, 2026$88.81071,000,000December 3, 2025
1,000,000$88.8903June 30, 2026$88.79051,000,000December 3, 2025
1,000,000$90.9196June 30, 2026$90.82301,000,000December 3, 2025
1,255,000$91.0566June 30, 2026$90.94501,255,000December 3, 2025
1,324,942$88.7048December 31, 2026$88.76841,324,942December 3, 2025
2,277,113$88.3227December 31, 2026$88.29142,277,113December 3, 2025
    3,130,641(*)
$88.2823December 31, 2026$88.19762,060,000December 3, 2025
3,255,866$89.4692December 31, 2026N/AN/AN/A
3,850,000$90.6617December 31, 2026N/AN/AN/A
2,470,306$94.5394June 30, 2027N/AN/AN/A
2,314,487$92.7805June 30, 2027N/AN/AN/A
1,590,200$93.4524June 30, 2027N/AN/AN/A
4,000,000$90.8141June 30, 2027N/AN/AN/A
2,346,903$91.1610June 30, 2027N/AN/AN/A
2,876,034$92.2437June 30, 2027N/AN/AN/A
3,015,668$93.4521June 30, 2027N/AN/AN/A
911,448$94.2411June 30, 2027N/AN/AN/A
(*)The total number of shares sold under this forward sale contract is 3,130,641, of which 2,060,000 shares were settled in December 2025. The remaining 1,070,641 shares sold under this contract are subject to be settled at a future date.
As of December 31, 2025, Southern Company had entered into separate forward sale contracts with forward purchasers for a total of 44,618,608 shares of common stock, all of which had been sold by the forward sellers. Of these shares, 16,917,055 shares had been settled under the forward sale contracts in the form of shares at the initial forward price adjusted for interest earned and dividends paid from the forward sale date to the settlement date. The net proceeds from the settlement of these shares were approximately $1.5 billion.
The total number of shares sold remaining under the forward sale contracts subject to be settled at a future date is 27,701,553. Each initial forward price is subject to adjustment under certain specified circumstances as specified in the respective forward sale contracts. Southern Company may settle each of the forward transactions in shares, cash, or net shares.
II-176

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Bank Credit Arrangements
At December 31, 2025, committed credit arrangements with banks were as follows:
Expires
Company2026202720292030TotalUnused
Expires
within
One Year
(in millions)
Southern Company parent(a)
$ $500 $ $2,500 $3,000 $2,999 $ 
Alabama Power(b)
15  650 700 1,365 1,365 15 
Georgia Power(c)
   2,050 2,050 2,042  
Mississippi Power(a)
 125  150 275 275  
Southern Power(a)(d)
   600 600 600  
Southern Company Gas(e)
   1,600 1,600 1,598  
SEGCO30    30 30 30 
Southern Company$45 $625 $650 $7,600 $8,920 $8,909 $45 
(a)Arrangement expiring in 2030 represents a $3.25 billion combined arrangement for Southern Company, Mississippi Power, and Southern Power allowing for flexible sublimits. Pursuant to the combined facility, the allocations among Southern Company, Mississippi Power, and Southern Power may be adjusted.
(b)Includes $15 million expiring in 2026 at Alabama Property Company, a wholly-owned subsidiary of Alabama Power, of which $15 million was unused at December 31, 2025. Alabama Power is not party to this arrangement.
(c)Georgia Power had $26 million of letters of credit outstanding under an uncommitted letter of credit facility at December 31, 2025.
(d)Does not include Southern Power Company's $75 million and $100 million continuing letter of credit facilities for standby letters of credit, expiring in 2027 and 2028, respectively, of which $17 million and $4 million, respectively, was unused at December 31, 2025. In addition, Southern Power Company had $23 million of letters of credit outstanding under an uncommitted letter of credit facility at December 31, 2025. Southern Power's subsidiaries are not parties to its bank credit arrangements or letter of credit facilities.
(e)Southern Company Gas, as the parent entity, guarantees the obligations of Southern Company Gas Capital, which is the borrower of $800 million of the credit arrangement expiring in 2030. Southern Company Gas' committed credit arrangement expiring in 2030 also includes $800 million for which Nicor Gas is the borrower and which is restricted for working capital needs of Nicor Gas. Pursuant to the multi-year credit arrangement expiring in 2030, the allocations between Southern Company Gas Capital and Nicor Gas may be adjusted. See "Structural Considerations" herein for additional information.
The bank credit arrangements require payment of commitment fees based on the unused portion of the commitments. Commitment fees average less than 1/4 of 1% for the Registrants and Nicor Gas. Subject to applicable market conditions, Southern Company and its subsidiaries expect to renew or replace their bank credit arrangements as needed, prior to expiration. In connection therewith, Southern Company and its subsidiaries may extend the maturity dates and/or increase or decrease the lending commitments thereunder.
These bank credit arrangements, as well as the term loan arrangements of the Registrants, Nicor Gas, and SEGCO, contain covenants that limit debt levels and contain cross-acceleration provisions to other indebtedness (including guarantee obligations) that are restricted only to the indebtedness of the individual company. The cross-acceleration provisions to other indebtedness would trigger an event of default if the applicable borrower defaulted on indebtedness, the payment of which was then accelerated. Southern Company's, Mississippi Power's, Southern Company Gas', and Nicor Gas' credit arrangements contain covenants that limit debt levels to 70% of total capitalization, as defined in the agreements, and the other subsidiaries' bank credit arrangements contain covenants that limit debt levels to 65% of total capitalization, as defined in the agreements. For purposes of these definitions, debt excludes junior subordinated notes and, in certain arrangements, other hybrid securities. Additionally, for Southern Company and Southern Power, for purposes of these definitions, debt excludes any project debt incurred by certain subsidiaries of Southern Power to the extent such debt is non-recourse to Southern Power and capitalization excludes the capital stock or other equity attributable to such subsidiaries. At December 31, 2025, the Registrants, Nicor Gas, and SEGCO were in compliance with all such covenants. None of the bank credit arrangements contain material adverse change clauses at the time of borrowings.
A portion of the unused credit with banks is allocated to provide liquidity support to certain revenue bonds of the traditional electric operating companies and the commercial paper programs of the Registrants, Nicor Gas, and SEGCO. At December 31, 2025, outstanding variable rate demand revenue bonds of the traditional electric operating companies with allocated liquidity support totaled approximately $1.5 billion (comprised of approximately $796 million at Alabama Power, $667 million at Georgia Power, and $58 million at Mississippi Power). In addition, at December 31, 2025, Alabama Power and Georgia Power had approximately $280 million and $384 million, respectively, of fixed rate revenue bonds outstanding that are required to be remarketed within the next 12 months. Alabama Power's $280 million of fixed rate revenue bonds are classified as securities due
II-177

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

within one year on its balance sheets as they are not covered by long-term committed credit. All other variable rate demand revenue bonds and fixed rate revenue bonds required to be remarketed within the next 12 months are classified as long-term debt on the balance sheets as a result of available long-term committed credit.
At both December 31, 2025 and 2024, Southern Power had $106 million of cash collateral posted related to PPA requirements, which is included in other deferred charges and assets on Southern Power's consolidated balance sheets.
Notes Payable
The Registrants, Nicor Gas, and SEGCO make short-term borrowings primarily through commercial paper programs that have the liquidity support of the committed bank credit arrangements described above under "Bank Credit Arrangements." Southern Power's subsidiaries are not parties or obligors to its commercial paper program. Southern Company Gas maintains commercial paper programs at Southern Company Gas Capital and at Nicor Gas. Nicor Gas' commercial paper program supports working capital needs at Nicor Gas as Nicor Gas is not permitted to make money pool loans to affiliates. All of Southern Company Gas' other subsidiaries benefit from Southern Company Gas Capital's commercial paper program. See "Structural Considerations" herein for additional information.
In addition, Southern Company and certain of its subsidiaries have entered into various bank term loan agreements. Unless otherwise stated, the proceeds of these loans were used to repay existing indebtedness and for general corporate purposes, including working capital and, for the subsidiaries, their continuous construction programs.
Commercial paper and short-term bank term loans are included in notes payable in the balance sheets. Details of short-term borrowings for the applicable Registrants were as follows:
Notes Payable at December 31, 2025
Notes Payable at December 31, 2024
Amount
Outstanding
Weighted Average
Interest Rate
Amount
Outstanding
Weighted Average
Interest Rate
(in millions)(in millions)
Southern Company
Commercial paper$722 3.9 %$1,138 4.7 %
Short-term bank debt  200 5.3 
Total$722 3.9 %$1,338 4.8 %
Georgia Power
Commercial paper$160 3.9 %$  %
Short-term bank debt  200 5.3 
Total$160 3.9 %$200 5.3 %
Mississippi Power
Commercial paper$  %$14 4.6 %
Southern Power
Commercial paper$138 3.9 %$  %
Southern Company Gas
Commercial paper:
Southern Company Gas Capital$209 3.9 %$283 4.7 %
Nicor Gas216 3.9 172 4.6 
Total$425 3.9 %$455 4.7 %
See "Bank Credit Arrangements" herein for information on bank term loan covenants that limit debt levels and cross-acceleration or cross-default provisions.
II-178

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Outstanding Classes of Capital Stock
Southern Company
Common Stock
Stock Issued
During 2025, Southern Company issued approximately 22.5 million shares of common stock primarily through forward sale contract settlements and dividend reinvestment and employee equity compensation and savings plans.
See "Equity Units" and "Equity Distribution Agreement" herein for additional information.
Shares Reserved
At December 31, 2025, a total of 203 million shares were reserved for issuance pursuant to the Southern Investment Plan, employee savings plans, the Equity and Incentive Compensation Plan (which includes performance share units and restricted stock units as discussed in Note 12), an at-the-market program (including forward sale contracts), and the convertible senior notes (as discussed under "Convertible Senior Notes" herein). Of the shares reserved, 23 million shares are available for awards under the Equity and Incentive Compensation Plan at December 31, 2025.
Diluted Earnings Per Share
For Southern Company, the difference in computing basic and diluted earnings per share (EPS) is attributable to awards outstanding under stock-based compensation plans, forward sale contracts pursuant to the equity distribution agreement, convertible senior notes, and the 2025 Equity Units. EPS dilution resulting from stock-based compensation plans and the forward sale contracts is determined using the treasury stock method, and EPS dilution resulting from the convertible senior notes is determined using the net share settlement method. See Note 12 and "Convertible Senior Notes," "Equity Distribution Agreement," and "Equity Units" herein for additional information. Shares used to compute diluted EPS were as follows:
 Average Common Stock Shares
 202520242023
 (in millions)
As reported shares1,103 1,096 1,092 
Effect of stock-based compensation5 6 6 
Effect of forward sale contracts
1   
Diluted shares1,109 1,102 1,098 
For all periods presented, an immaterial number of stock-based compensation awards was excluded from the diluted EPS calculation because the awards were anti-dilutive.
For 2025 and 2024, the dilution resulting from convertible senior notes was immaterial.
Alabama Power
Alabama Power has preferred stock, Class A preferred stock, preference stock, and common stock authorized, but only common stock outstanding.
Georgia Power
Georgia Power has preferred stock, Class A preferred stock, preference stock, and common stock authorized, but only common stock outstanding.
Mississippi Power
Mississippi Power has preferred stock and common stock authorized, but only common stock outstanding.
Dividend Restrictions
The income of Southern Company is derived primarily from equity in earnings of its subsidiaries. At December 31, 2025, consolidated retained earnings included $7.5 billion of undistributed retained earnings of the subsidiaries.
The traditional electric operating companies and Southern Power can only pay dividends to Southern Company out of retained earnings or paid-in-capital.
II-179

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

See Note 7 under "Southern Power" for information regarding the distribution requirements for certain Southern Power subsidiaries.
By regulation, Nicor Gas is restricted, up to its retained earnings balance, in the amount it can dividend or loan to affiliates and is not permitted to make money pool loans to affiliates. At December 31, 2025, the amount of Southern Company Gas' subsidiary retained earnings available for dividend payment totaled $1.8 billion.
Structural Considerations
Since Southern Company and Southern Company Gas are holding companies, the right of Southern Company and Southern Company Gas and, hence, the right of creditors of Southern Company or Southern Company Gas to participate in any distribution of the assets of any respective subsidiary of Southern Company or Southern Company Gas, whether upon liquidation, reorganization, or otherwise, is subject to prior claims of creditors and preferred stockholders of such subsidiary.
Southern Company Gas Capital was established to provide for certain of Southern Company Gas' ongoing financing needs through a commercial paper program, the issuance of various debt, hybrid securities, and other financing arrangements. Southern Company Gas fully and unconditionally guarantees all debt issued by Southern Company Gas Capital. Nicor Gas is not permitted by regulation to make loans to affiliates or utilize Southern Company Gas Capital for its financing needs.
Southern Power Company's senior notes, commercial paper, and bank credit arrangement are unsecured senior indebtedness, which rank equally with all other unsecured and unsubordinated debt of Southern Power Company. Southern Power's subsidiaries are not issuers, borrowers, or obligors, as applicable, under any of these unsecured senior debt arrangements, which are effectively subordinated to any future secured debt of Southern Power Company and any potential claims of creditors of Southern Power's subsidiaries.
9. LEASES
Lessee
The Registrants recognize leases with a term of greater than 12 months on the balance sheet as lease obligations, representing the discounted future fixed payments due, along with ROU assets that will be amortized over the term of each lease.
As lessee, the Registrants lease certain electric generating units (including renewable energy facilities), real estate/land, communication towers, railcars, and other equipment and vehicles. The major categories of lease obligations are as follows:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
 (in millions)
At December 31, 2025
Electric generating units(*)
$1,064 $53 $1,793 $ $ $ 
Real estate/land931 3 37 1 541 111 
Communication towers134 3 5   20 
Railcars74 39 26 9   
Other49 6 3 19   
Total$2,252 $104 $1,864 $29 $541 $131 
At December 31, 2024
Electric generating units(*)
$672 $56 $1,509 $ $ $ 
Real estate/land834 3 45 2 540 20 
Communication towers118 2 4   21 
Railcars64 31 29 4   
Other52 2 2 16   
Total$1,740 $94 $1,589 $22 $540 $41 
(*)Amounts related to affiliate leases are eliminated in consolidation for Southern Company. See "Contracts that Contain a Lease" herein for additional information.
Real estate/land leases primarily consist of commercial real estate leases at Southern Company, Georgia Power, and Southern Company Gas and various land leases primarily associated with renewable energy facilities at Southern Power. The commercial
II-180

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

real estate leases have remaining terms of up to 18 years while the land leases have remaining terms of up to 41 years, including renewal periods.
Communication towers are leased for the installation of equipment to provide cellular phone service to customers and to support the automated meter infrastructure programs at the traditional electric operating companies and Nicor Gas. Communication tower leases have remaining terms of up to 15 years.
Renewal options exist in many of the leases. The expected term used in calculating the lease obligation generally reflects only the noncancelable period of the lease unless it is considered reasonably certain that the lease will be extended. Land leases associated with renewable energy facilities at Southern Power and communication tower leases for automated meter infrastructure at Nicor Gas include renewal periods reasonably certain of exercise resulting in an expected lease term at least equal to the expected life of the renewable energy facilities and the automated meter infrastructure, respectively.
Contracts that Contain a Lease
While not specifically structured as a lease, some of the PPAs at Alabama Power and Georgia Power are deemed to represent a lease of the underlying electric generating units when the terms of the PPA convey the right to control the use of the underlying assets. Amounts recorded for leases of electric generating units are generally based on the amount of scheduled capacity payments due over the remaining term of the PPA, which varies between three and 22 years. Georgia Power has several PPAs with Southern Power that Georgia Power accounts for as leases with a lease obligation of $782 million and $893 million at December 31, 2025 and 2024, respectively. The amount paid for energy under these affiliate PPAs reflects a price that would be paid in an arm's-length transaction as reviewed and approved by both the Georgia PSC and the FERC. Amounts related to the affiliate PPAs are eliminated in consolidation for Southern Company.
Short-term Leases
Leases with an initial term of 12 months or less are not recorded on the balance sheet; the Registrants generally recognize lease expense for these leases on a straight-line basis over the lease term.
Residual Value Guarantees
Residual value guarantees existed primarily in railcar leases at Alabama Power and Georgia Power. The remaining railcar leases containing residual value guarantees expired in 2023 for Alabama Power and in June 2024 for Georgia Power. The amounts probable of being paid under those guarantees were included in the lease payments, and all such amounts were immaterial at December 31, 2024.
Lease and Nonlease Components
For all asset categories, with the exception of electric generating units, gas pipelines, and real estate leases, the Registrants combine lease payments and any nonlease components, such as asset maintenance, for purposes of calculating the lease obligation and the ROU asset.
II-181

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Balance sheet amounts recorded for operating and finance leases were as follows:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
 (in millions)
At December 31, 2025
Operating Leases
Operating lease ROU assets, net$1,358 $86 $1,120 $9 $479 $85 
Operating lease obligations - current$197 $14 $170 $4 $31 $8 
Operating lease obligations - non-current1,287 78 960 6 510 123 
Total operating lease obligations(*)
$1,484 $92 $1,130 $10 $541 $131 
Finance Leases
Finance lease ROU assets, net$742 $12 $710 $18 $ $ 
Finance lease obligations - current$16 $3 $29 $1 $ $ 
Finance lease obligations - non-current752 9 705 18   
Total finance lease obligations $768 $12 $734 $19 $ $ 
At December 31, 2024
Operating Leases
Operating lease ROU assets, net$1,386 $84 $1,331 $8 $484 $38 
Operating lease obligations - current$200 $14 $169 $4 $29 $11 
Operating lease obligations - non-current1,253 76 1,159 4 511 30 
Total operating lease obligations(*)
$1,453 $90 $1,328 $8 $540 $41 
Finance Leases
Finance lease ROU assets, net$254 $4 $227 $14 $ $ 
Finance lease obligations - current$9 $1 $20 $1 $ $ 
Finance lease obligations - non-current278 3 241 13   
Total finance lease obligations$287 $4 $261 $14 $ $ 
(*)Includes operating lease obligations related to PPAs at Southern Company, Alabama Power, and Georgia Power totaling $486 million, $53 million, and $1.1 billion, respectively, at December 31, 2025 and $567 million, $55 million, and $1.3 billion, respectively, at December 31, 2024.
If not presented separately on the Registrants' balance sheets, amounts related to leases are presented as follows: operating lease ROU assets, net are included in "other deferred charges and assets"; operating lease obligations are included in "other current liabilities" and "other deferred credits and liabilities," as applicable; finance lease ROU assets, net are included in "plant in service"; and finance lease obligations are included in "securities due within one year" and "long-term debt," as applicable.
II-182

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Lease costs for 2025, 2024, and 2023, which includes both amounts recognized as operations and maintenance expense and amounts capitalized as part of the cost of another asset, were as follows:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
 (in millions)
2025
Lease cost
Operating lease cost(*)
$271 $19 $248 $5 $34 $21 
Finance lease cost:
Amortization of ROU assets13 1 22 1   
Interest on lease obligations11  12    
Total finance lease cost24 1 34 1   
Short-term lease costs 45 22 15    
Variable lease cost52  79  6  
Total lease cost $392 $42 $376 $6 $40 $21 
2024
Lease cost
Operating lease cost(*)
$248 $19 $190 $4 $27 $12 
Finance lease cost:
Amortization of ROU assets20 2 23 1   
Interest on lease obligations15  15 1   
Total finance lease cost35 2 38 2   
Short-term lease costs37 15 15    
Variable lease cost48 (1)77  4  
Total lease cost$368 $35 $320 $6 $31 $12 
2023
Lease cost
Operating lease cost(*)
$252 $16 $192 $5 $34 $12 
Finance lease cost:
Amortization of ROU assets24 2 19 1   
Interest on lease obligations14  17    
Total finance lease cost38 2 36 1   
Short-term lease costs40 16 16    
Variable lease cost47  74  4  
Total lease cost$377 $34 $318 $6 $38 $12 
(*)Includes operating lease costs related to PPAs at Southern Company, Alabama Power, and Georgia Power totaling $113 million, $5 million, and $222 million, respectively, in 2025, $108 million, $5 million, and $168 million, respectively, in 2024, and $112 million, $4 million, and $174 million, respectively, in 2023.
Georgia Power has variable lease payments that are based on the amount of energy produced by certain renewable generating facilities subject to PPAs, including $49 million, $45 million, and $42 million in 2025, 2024, and 2023, respectively, from finance leases which are included in purchased power on Georgia Power's statements of income, of which $23 million, $22 million, and $21 million was included in purchased power, affiliates in 2025, 2024, and 2023, respectively.
II-183

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Other information with respect to cash and noncash activities related to leases, as well as weighted-average lease terms and discount rates, is as follows:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
 (in millions)
2025
Other information
Cash paid for amounts included in the measurements of lease obligations:
Operating cash flows from operating leases$270 $19 $257 $4 $33 $13 
Operating cash flows from finance leases11  17    
Financing cash flows from finance leases21 2 32 1   
ROU assets obtained under operating leases168 16 18 6 2 61 
ROU assets obtained under finance leases509 10 513 6   
2024
Other information
Cash paid for amounts included in the measurements of lease obligations:
Operating cash flows from operating leases$243 $19 $186 $4 $33 $12 
Operating cash flows from finance leases15  21    
Financing cash flows from finance leases11 2 23 1   
ROU assets obtained under operating leases146 11 609  10 1 
Reassessment of ROU assets under operating leases(7)   (7) 
ROU assets obtained under finance leases1  44    
2023
Other information
Cash paid for amounts included in the measurements of lease obligations:
Operating cash flows from operating leases$253 $17 $199 $5 $33 $12 
Operating cash flows from finance leases15  22    
Financing cash flows from finance leases18 2 16 1   
ROU assets obtained under operating leases100 30 26 1 7 7 
ROU assets obtained under finance leases3 3 18    
II-184

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
At December 31, 2025
Weighted-average remaining lease term in years:
Operating leases16.09.77.04.631.410.9
Finance leases19.83.418.110.1N/AN/A
Weighted-average discount rate:
Operating leases 4.88 %5.07 %4.82 %4.58 %4.96 %5.30 %
Finance leases5.38 %4.38 %5.68 %3.78 %N/AN/A
At December 31, 2024
Weighted-average remaining lease term in years:
Operating leases16.410.27.94.332.36.8
Finance leases16.02.710.110.9N/AN/A
Weighted-average discount rate:
Operating leases4.73 %5.04 %4.73 %3.83 %4.88 %3.84 %
Finance leases4.86 %4.05 %5.8 %2.74 %N/AN/A
Maturities of lease liabilities are as follows:
At December 31, 2025
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
 (in millions)
Maturity Analysis
Operating leases:
2026$233 $18 $221 $4 $33 $9 
2027217 15 218 2 29 15 
2028202 11 216 2 30 16 
2029168 9 195 1 30 15 
2030118 9 111 1 30 16 
Thereafter1,294 56 378 1 954 110 
Total2,232 118 1,339 11 1,106 181 
Less: Present value discount 748 26 209 1 565 50 
Operating lease obligations $1,484 $92 $1,130 $10 $541 $131 
Finance leases:
2026$33 $3 $47 $2 $ $ 
202732 2 47 2   
202844 2 59 2   
202965 1 82 2   
203067 1 63 2   
Thereafter1,130 6 985 14   
Total1,371 15 1,283 24   
Less: Present value discount603 3 549 5   
Finance lease obligations$768 $12 $734 $19 $ $ 
Payments made under PPAs at Georgia Power for energy generated from certain renewable energy facilities accounted for as operating and finance leases are considered variable lease costs and are therefore not reflected in the above maturity analysis.
II-185

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

At December 31, 2025, Georgia Power has one affiliate PPA with Southern Power that has not yet commenced and will be accounted for as a lease. The PPA has a term of 10 years and is expected to commence in 2028. The estimated total obligation associated with this PPA is $63 million.
Lessor
The Registrants are each considered lessors in various arrangements that have been determined to contain a lease due to the customer's ability to control the use of the underlying asset owned by the applicable Registrant. For the traditional electric operating companies, these arrangements consist of outdoor lighting contracts accounted for as operating leases with initial terms of up to 10 years, after which the contracts renew on a month-to-month basis at the customer's option. For Alabama Power and Georgia Power, these arrangements also include PPAs related to electric generating units accounted for as operating leases with remaining terms of one year and up to 14 years, respectively. For Mississippi Power, these arrangements also include a tolling arrangement related to an electric generating unit accounted for as a sales-type lease with a remaining term of 13 years. For Southern Power, these arrangements consist of PPAs related to electric generating units accounted for as operating leases with remaining terms of up to 21 years and PPAs related to battery energy storage facilities accounted for as sales-type leases with remaining terms of up to 16 years. Southern Company Gas is the lessor in operating leases related to gas pipelines with remaining terms of up to 17 years. For Southern Company, these arrangements also include PPAs related to fuel cells accounted for as operating leases with remaining terms of up to eight years.
Lease income for 2025, 2024, and 2023 was as follows:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
 (in millions)
2025
Lease income - interest income on sales-type leases$23 $ $ $14 $9 $ 
Lease income - operating leases145 7 29 3 148 36 
Variable lease income408 1   442  
Total lease income$576 $8 $29 $17 $599 $36 
2024
Lease income - interest income on sales-type leases$24 $ $ $15 $9 $ 
Lease income - operating leases136 9 28 3 88 36 
Variable lease income417 1   450  
Total lease income$577 $10 $28 $18 $547 $36 
2023
Lease income - interest income on sales-type leases$24 $ $ $14 $10 $ 
Lease income - operating leases164 35 29 2 85 37 
Variable lease income406 1   437  
Total lease income$594 $36 $29 $16 $532 $37 
As part of its acquisition of the Lindsay Hill Generating Station, Alabama Power assumed an existing power sales agreement under which the full output of the generating facility remains committed to a non-affiliated third party through April 2027. These revenues are included above as lease income from operating leases. See Note 15 under "Alabama Power" for additional information.
Lease payments received under tolling arrangements and PPAs consist of either scheduled payments or variable payments based on the amount of energy produced by the underlying electric generating units. Lease income related to PPAs is included in wholesale revenues for Alabama Power, Georgia Power, and Southern Power. Scheduled payments to be received under outdoor lighting contracts' initial terms, tolling arrangements, and PPAs accounted for as leases are presented in the following maturity analyses.
II-186

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

The undiscounted cash flows expected to be received for in-service leased assets under the leases are as follows:
At December 31, 2025
Southern
Company
Mississippi
Power
Southern
Power
 (in millions)
2026$39 $23 $15 
202738 22 15 
202837 21 15 
202936 20 15 
203034 19 15 
Thereafter270 114 155 
Total undiscounted cash flows$454 $219 $230 
Net investment in sales-type lease(*)
286 130 152 
Difference between undiscounted cash flows and discounted cash flows$168 $89 $78 
(*)For Mississippi Power, included in other current assets ($10 million and $10 million at December 31, 2025 and 2024, respectively) and other property and investments ($120 million and $129 million at December 31, 2025 and 2024, respectively) on the balance sheets. For Southern Power, included in other current assets ($15 million and $15 million at December 31, 2025 and 2024, respectively) and net investment in sales-type leases ($137 million and $143 million at December 31, 2025 and 2024, respectively) on the balance sheets.
The undiscounted cash flows to be received under operating leases and contracts accounted for as operating leases are as follows:
At December 31, 2025
Southern
Company
Alabama
Power
Southern
Power
Southern
Company Gas
 (in millions)
2026$119 $6 $148 $35 
2027111 5 150 28 
2028111 4 161 28 
2029116 4 164 28 
2030115 3 103 28 
Thereafter554 34 400 299 
Total$1,126 $56 $1,126 $446 
Southern Power receives payments for renewable energy under PPAs accounted for as operating leases that are considered contingent rents and are therefore not reflected in the table above. Alabama Power and Southern Power allocate revenue to the nonlease components of PPAs based on the stand-alone selling price of capacity and energy. The undiscounted cash flows to be received under contracts accounted for as operating leases at Georgia Power and Mississippi Power are immaterial.
Southern Company Leveraged Lease
At December 31, 2025, a subsidiary of Southern Holdings had one leveraged lease agreement, which relates to energy generation, with an expected remaining term of six years. Southern Company receives federal income tax deductions for depreciation and amortization, as well as interest on long-term debt, related to this investment. Southern Company wrote off the related investment balance in 2020 following an evaluation of the recoverability of the lease receivable and the expected residual value of the generation assets at the end of the lease.
In June 2022, the Southern Holdings subsidiary operating the generating plant for the lessee provided notice to the lessee to terminate the related operating and maintenance agreement effective June 30, 2023. Subsequently, the lessee failed to make the semi-annual lease payment due in December 2022. As a result, the Southern Holdings subsidiary was unable to make its corresponding payment to the holders of the underlying non-recourse debt related to the generation assets. The parties to the lease entered into forbearance agreements which suspended the related contractual rights of the parties while they continued restructuring negotiations, during which the termination date for the operating and maintenance agreement was delayed until July 31, 2023. The negotiations were completed in July 2023, resulting in the Southern Holdings subsidiary agreeing to continue operating the plant for the lessee until the lessee's associated power off-take agreement ends in 2032, subject to certain terms and conditions. The restructuring had no material impact on Southern Company's financial statements. Southern Company will
II-187

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

continue to monitor the operational performance of the underlying assets and evaluate the ability of the lessee to continue to meet its obligations, including those associated with a future closure or retirement of the generation assets and associated properties, including the dry ash landfill.
10. INCOME TAXES
Southern Company files a consolidated federal income tax return, and the Registrants file various state income tax returns, some of which are combined or unitary. Under a joint consolidated income tax allocation agreement, each Southern Company subsidiary's current and deferred tax expense is computed on a stand-alone basis, and each subsidiary is allocated an amount of tax similar to that which would be paid if it filed a separate income tax return except for certain credit utilization and state apportionment results. In accordance with IRS regulations, each company is jointly and severally liable for the federal tax liability.
Current and Deferred Income Taxes
Details of income tax provisions are as follows:
2025
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company Gas
(in millions)
Federal —
Current$139 $110 $99 $57 $71 $28 
Deferred399 192 346 (6)(133)98 
Total federal
538 302 445 51 (62)126 
State —
Current94 95 32 (1)(3)32 
Deferred196 28 125 15 4 24 
Total state
290 123 157 14 1 56 
Total$828 $425 $602 $65 $(61)$182 
2024
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company Gas
(in millions)
Federal —
Current$221 $357 $200 $32 $(112)$84 
Deferred387 (111)211 2 106 86 
Total federal
608 246 411 34 (6)170 
State —
Current152 103 52 (1)6 42 
Deferred209 11 140 14 (13)46 
Total state
361 114 192 13 (7)88 
Total$969 $360 $603 $47 $(13)$258 
II-188

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

2023
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company Gas
(in millions)
Federal —
Current$54 $242 $205 $49 $(320)$62 
Deferred299 (257)195 (26)334 68 
Total federal
353 (15)400 23 14 130 
State —
Current41 82 37 1 (1)24 
Deferred102 14 11 12 (1)57 
Total state
143 96 48 13 (2)81 
Total$496 $81 $448 $36 $12 $211 
Southern Company's and Southern Power's ITCs and PTCs generated in the current tax year and carried forward from prior tax years that cannot be utilized or transferred in the current tax year are reclassified from current to deferred taxes in federal income tax expense in the tables above. Southern Power's ITCs and PTCs reclassified in this manner were $95 million for 2025 and were immaterial for 2024 and 2023. See "Cash Paid for Income Taxes" and "Deferred Tax Assets and Liabilities" herein for additional information.
Under current tax law, certain projects are eligible for ITCs. The Registrants use the deferral method to account for federal and state ITCs, whereby the ITCs are recorded as a deferred credit and amortized to income tax expense over the useful life of the respective asset. In accordance with regulatory requirements, certain state ITCs at Georgia Power are recognized as an income tax benefit in the year the credit is generated through the establishment of a regulatory asset. ITCs amortized in 2025, 2024, and 2023 were immaterial for the traditional electric operating companies and Southern Company Gas and were as follows for Southern Company and Southern Power:
Southern CompanySouthern Power
(in millions)
2025$84 $58 
2024109 58 
202384 58 
When Southern Company recognizes tax credits, the tax basis of the asset is reduced by 50% of the ITCs received, which, together with the deferred credit, results in a net deferred tax asset. Southern Power has elected to recognize the tax benefit of this basis difference as a reduction to income tax expense in the year in which the plant reaches commercial operation.
Georgia Power's state ITCs and other state credits, which are recognized in the period in which the credits are generated, reduced Georgia Power's income tax expense by $31 million in 2025, $44 million in 2024, and $49 million in 2023.
Southern Power's federal and state PTCs, which are recognized in the period in which the credits are generated, reduced Southern Power's income tax expense by $33 million in 2025, $32 million in 2024, and $26 million in 2023.
II-189

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Cash Paid for Income Taxes
The following table disaggregates income taxes paid, excluding credit transfers, (net of refunds) by federal, state, and foreign taxes for the periods presented:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company Gas
(in millions)
2025
Federal$170 $150 $53 $43 $162 $9 
State114 93 76 (1)(14)20 
Total cash taxes paid$284 $243 $129 $42 $148 $29 
2024
Federal$123 $289 $(21)$51 $(22)$53 
State53 98 7  (10)6 
Total cash taxes paid (received)$176 $387 $(14)$51 $(32)$59 
2023
Federal$78 $256 $178 $52 $(252)$71 
State51 59 42  (2)20 
Foreign3      
Total cash taxes paid (received)$132 $315 $220 $52 $(254)$91 
Income taxes paid (net of refunds) exceeded 5% of total income taxes paid (net of refunds) in the following jurisdictions for the periods presented:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company Gas
(in millions)
2025
State —
Alabama
$92 $91 
$ (*)
$ (*)
$ (*)
$ (*)
Georgia
(*)
(*)
74 
(*)
(11)
(*)
Oklahoma
(*)
(*)
(*)
(*)
(9)
(*)
Illinois
20 
(*)
(*)
(*)
(*)
20 
2024
State —
Alabama$99 $98 
$ (*)
$ (*)
$ (*)
$ (*)
Georgia(35)
(*)
7 
(*)
6 7
Oklahoma(18)
(*)
(*)
(*)
(18)
(*)
2023
State —
Alabama$60 $57 
$ (*)
$ (*)
$ (*)
$ (*)
Georgia(13)
(*)
42 
(*)
(*)
8 
Oklahoma(9)
(*)
(*)
(*)
(*)
(*)
Illinois
13 
(*)
(*)
(*)
(*)
13 
(*)Jurisdiction is either not applicable or below the threshold for the period presented.
II-190

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Southern Power, in 2025, paid back $95 million and, in 2024 and 2023, received $71 million and $332 million, respectively, of cash related to federal ITCs under renewable energy initiatives. See "Deferred Tax Assets and Liabilities" herein for additional information.
Alabama Power, Georgia Power, and Southern Power have entered into transferability agreements with non-affiliated parties to sell ITCs and PTCs at a discount to the generated credit value in 2024, 2025, and 2026. During 2025, Alabama Power, Georgia Power, and Southern Power received cash of $80 million, $64 million, and $24 million, respectively, from credits transferred. During 2024, Georgia Power and Southern Power received cash of $11 million and $24 million, respectively, from credits transferred. The discount is recorded as a reduction in tax credits recognized in the financial statements and does not have a material impact on results of operations. The Southern Company system continues to explore the ability to efficiently monetize its tax credits through third-party transfer agreements.
Pursuant to the Vogtle Joint Ownership Agreements, Georgia Power paid $156 million in 2025, $131 million in 2024, and $39 million in 2023 to the other Vogtle Owners for advanced nuclear PTCs for Plant Vogtle Unit 3 and 4, which were utilized and not reflected as a reduction to current income tax expense. The gains recognized in all periods were recorded in income tax benefit and were immaterial.
Effective Tax Rate
Southern Company's effective tax rate is typically lower than the statutory rate due to the flowback of excess deferred income taxes at the regulated utilities, federal income tax benefits from ITCs and PTCs primarily at Southern Power, Georgia Power, and Alabama Power, and non-taxable AFUDC equity at the traditional electric operating companies.
A reconciliation of the federal statutory income tax rate to the effective income tax (benefit) rate is as follows:
2025
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company Gas
(in millions, except percentages)
Federal statutory rate$1,050 21.0%$408 21.0%$725 21.0%$59 21.0%$(22)(21.0%)$192 21.0%
State and local income tax, net of federal income tax effect(*)
254 5.197 5.0149 4.311 4.01 1.044 4.8
Tax credits —
Amortization of ITCs(56)(1.1)(2)(0.1)(2)(0.1) (46)(43.7) 
Federal PTCs(166)(3.3) (137)(4.0) (28)(26.8) 
Other(2)(1)(1)   
Nontaxable or nondeductible items —
AFUDC equity(67)(1.3)(14)(0.7)(52)(1.5)   
Other19 0.412 0.621 0.62 0.6 (5)(0.5)
Changes in unrecognized tax benefits(26)(0.5) (26)(0.7)   
Other adjustments —
Noncontrolling interests36 0.7   36 33.9 
Federal flowback of excess deferreds(170)(3.4)(58)(3.0)(57)(1.7)(5)(1.9) (45)(4.9)
Other(44)(1.0)(17)(0.9)(18)(0.5)(2)(0.5)(2)(1.2)(4)(0.5)
Effective income tax (benefit) rate$828 16.6%$425 21.9%$602 17.4%$65 23.2%$(61)(57.8%)$182 19.9%
(*)The following states made up the majority (greater than 50%) of the tax effect in this category: for Southern Company and Georgia Power, Georgia; for Alabama Power, Alabama; for Mississippi Power, Mississippi; for Southern Power, Alabama, California, Delaware, Georgia, North Carolina, Oklahoma, and Tennessee; and for Southern Company Gas, Illinois.
II-191

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

2024
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company Gas
(in millions, except percentages)
Federal statutory rate$1,098 21.0%$370 21.0%$661 21.0%$52 21.0%$36 21.0%$209 21.0%
State and local income tax, net of federal income tax effect(*)
305 5.889 5.0184 5.911 4.4(4)(2.3)62 6.2
Foreign tax effects6 0.1     
Effect of cross-border tax laws(1)     
Tax credits —
Amortization of ITCs(61)(1.2)(1)(0.1)(7)(0.2) (46)(26.4) 
Federal PTCs(147)(2.8)(1)(0.1)(116)(3.7) (30)(17.2) 
Other(3)(0.1)(1)(1)   
Nontaxable or nondeductible items —
AFUDC equity(44)(0.8)(12)(0.7)(32)(1.0)   
Other30 0.612 0.726 0.81 0.61 0.21 0.1
Changes in unrecognized tax benefits —
State changes in unrecognized tax benefits from prior periods, net of federal income tax effect(25)(0.5) (33)(1.0)  8 0.8
Other adjustments —
Noncontrolling interests30 0.6   30 17.1 
Federal flowback of excess deferreds(206)(3.9)(94)(5.3)(70)(2.2)(16)(6.5) (22)(2.2)
Other(13)(0.3)(2)(0.1)(9)(0.4)(1)(0.3)  (0.1)
Effective income tax (benefit) rate$969 18.5%$360 20.4%$603 19.2%$47 19.2%$(13)(7.6%)$258 25.8%
(*)The following states made up the majority (greater than 50%) of the tax effect in this category: for Southern Company and Georgia Power, Georgia; for Alabama Power, Alabama; for Mississippi Power, Mississippi; for Southern Power, Georgia and Oklahoma; and for Southern Company Gas, Illinois.
2023
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company Gas
(in millions, except percentages)
Federal statutory rate$912 21.0%$305 21.0%$531 21.0%$47 21.0%$51 21.0%$174 21.0%
State and local income tax, net of federal income tax effect(*)
117 2.775 5.245 1.811 4.9(2)(0.7)62 7.6
Tax credits —
Amortization of ITCs(56)(1.3)(1)(0.1)(2)(0.1) (46)(19.0) 
Federal PTCs(52)(1.2) (35)(1.4) (18)(7.4) 
Other(4)(0.1)(2)(0.1)(2)(0.1)   
Nontaxable or nondeductible items —
AFUDC equity(48)(1.1)(17)(1.2)(31)(1.2)   
Other23 0.514 1.021 0.81 0.51 0.41 0.1
Changes in unrecognized tax benefits(5)(0.1) (6)(0.2)  2 0.2
Other adjustments —
Noncontrolling interests27 0.6   27 11.1 
Federal flowback of excess deferreds(401)(9.2)(287)(19.8)(64)(2.6)(23)(10.2) (22)(2.6)
Other(17)(0.4)(6)(0.4)(9)(0.2) (1)(0.3)(6)(0.7)
Effective income tax rate$496 11.4%$81 5.6%$448 17.8%$36 16.2%$12 5.1%$211 25.6%
(*)The following states made up the majority (greater than 50%) of the tax effect in this category: for Southern Company and Alabama Power, Alabama; for Georgia Power, Georgia; for Mississippi Power, Mississippi; for Southern Power, Georgia and Oklahoma; and for Southern Company Gas, Illinois.
II-192

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Deferred Tax Assets and Liabilities
The tax effects of temporary differences between the carrying amounts of assets and liabilities in the financial statements of the Registrants and their respective tax bases, which give rise to deferred tax assets and liabilities, are as follows:
At December 31, 2025
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
 (in millions)
Deferred tax liabilities —
Accelerated depreciation$10,234 $2,641 $4,035 $363 $1,345 $1,675 
Property basis differences3,090 1,394 1,099 177  418 
Employee benefit obligations1,223 434 501 66 15 64 
AROs710 422 242    
Under recovered fuel and natural gas costs195 45 135 15   
Regulatory assets —
AROs1,809 590 1,191 28   
Employee benefit obligations699 190 221 34  33 
Remaining book value of retired assets395 229 161 5   
Storm damage reserves236  236    
Premium on reacquired debt53 8 44 1   
Other644 141 211 32 26 175 
Total deferred income tax liabilities19,288 6,094 8,076 721 1,386 2,365 
Deferred tax assets —
AROs2,519 1,012 1,433 28   
ITC and PTC carryforwards1,427 31 683 2 481  
Employee benefit obligations837 188 261 47 17 77 
Estimated loss on plants under construction679  679    
Estimated loss on regulatory disallowance38     38 
Other state deferred tax attributes346  25 211 48 12 
Federal effect of net state deferred tax liabilities460 201 141  24 114 
Other property basis differences159  73  73  
State effect of federal deferred taxes136 136     
Other partnership basis differences149    149  
Regulatory liability associated with the Tax Reform Legislation (not subject to normalization)18 18     
Long-term debt fair value adjustment67     67 
Other comprehensive losses51 2     
Other780 297 237 49 44 92 
Total deferred income tax assets7,666 1,885 3,532 337 836 400 
Valuation allowance(445) (267)(41)(29)(6)
Net deferred income tax assets7,221 1,885 3,265 296 807 394 
Net deferred income taxes (assets)/liabilities$12,067 $4,209 $4,811 $425 $579 $1,971 
Recognized in the balance sheets:
Accumulated deferred income taxes – assets$(66)$ $ $(66)$ $ 
Accumulated deferred income taxes – liabilities$12,133 $4,209 $4,811 $491 $579 $1,971 
II-193

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

At December 31, 2024
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
Deferred tax liabilities —
Accelerated depreciation$9,828 $2,583 $3,810 $344 $1,309 $1,575 
Property basis differences3,025 1,497 918 192  412 
Employee benefit obligations1,067 362 470 54 13 60 
AROs727 458 221    
Under recovered fuel and natural gas costs318 13 305    
Regulatory assets —
AROs1,886 658 1,193 35   
Employee benefit obligations746 191 237 35  35 
Remaining book value of retired assets360 168 187 5   
Storm damage reserves216  216    
Premium on reacquired debt57 8 48 1   
Other678 171 187 61 1 201 
Total deferred income tax liabilities18,908 6,109 7,792 727 1,323 2,283 
Deferred tax assets —
AROs2,613 1,116 1,414 35   
CAMT carryforwards40  18   104 
ITC and PTC carryforwards1,380 48 719  384  
Employee benefit obligations897 196 279 49 16 87 
Estimated loss on plants under construction773  773    
Estimated loss on regulatory disallowance20     20 
Other state deferred tax attributes366  26 224 49 16 
Federal effect of net state deferred tax liabilities402 197 100  23 107 
Other property basis differences176  75  85  
State effect of federal deferred taxes126 126     
Other partnership basis differences60    60  
Regulatory liability associated with the Tax Reform Legislation (not subject to normalization)18 18     
Long-term debt fair value adjustment73     73 
Other comprehensive losses48 3   1  
Other601 227 160 50 20 86 
Total deferred income tax assets7,593 1,931 3,564 358 638 493 
Valuation allowance(333) (157)(41)(27)(6)
Net deferred income tax assets7,260 1,931 3,407 317 611 487 
Net deferred income taxes (assets)/liabilities$11,648 $4,178 $4,385 $410 $712 $1,796 
Recognized in the balance sheets:
Accumulated deferred income taxes – assets$(82)$ $ $(82)$ $ 
Accumulated deferred income taxes – liabilities$11,730 $4,178 $4,385 $492 $712 $1,796 
The traditional electric operating companies and the natural gas distribution utilities have tax-related regulatory assets (deferred income tax charges) and regulatory liabilities (deferred income tax credits). The regulatory assets are primarily attributable to tax benefits flowed through to customers in prior years, deferred taxes previously recognized at rates lower than the current enacted tax law, and taxes applicable to capitalized interest. The regulatory liabilities are primarily attributable to deferred taxes previously recognized at rates higher than the current enacted tax law, certain tax credits deferred for future customer benefit, and unamortized ITCs. See Note 2 for each Registrant's related balances at December 31, 2025 and 2024.
II-194

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Tax Credit Carryforwards
Federal ITC/PTC carryforwards at December 31, 2025 were as follows:
Southern
Company
Alabama
Power
Georgia
Power
Southern
Power
(in millions)
Federal ITC/PTC carryforwards$850 $31 $152 $481 
Tax year(s) in which federal ITC/PTC carryforwards expire(*)
2031-20452032-20452031-20452035-2045
Year by which federal ITC/PTC carryforwards are expected to be utilized2031203120312031
(*)The federal ITC/PTC carryforwards at Alabama Power and Georgia Power expiring in 2031-2034 are immaterial to their respective financial statements.
The estimated tax credit utilization reflects the various transactions described in Note 15 and could be impacted by numerous factors, including the acquisition or construction of additional renewable projects, changes in taxable income projections, transfer of eligible credits, potential income tax rate changes, and remaining final guidance on the IRA. In the third quarter 2023 and the second quarter 2024, Georgia Power started generating advanced nuclear PTCs for Plant Vogtle Units 3 and 4, respectively, beginning on each unit's respective in-service date. In addition, pursuant to the Vogtle Joint Ownership Agreements, Georgia Power is purchasing advanced nuclear PTCs for Plant Vogtle Unit 3 and 4 from the other Vogtle Owners. See Note 2 under "Georgia Power – Nuclear Construction" for additional information on Plant Vogtle Units 3 and 4.
At December 31, 2025, Southern Company and Georgia Power also had approximately $483 million and $438 million, respectively, in net state investment and other net state tax credit carryforwards for the State of Georgia that will expire between tax years 2025 and 2033 and are not expected to be fully utilized. Southern Company and Georgia Power have a net state valuation allowance of $248 million and $211 million, respectively, associated with these carryforwards, both of which increased during 2025 by $87 million.
The ultimate outcome of these matters cannot be determined at this time.
Net Operating Loss Carryforwards
At December 31, 2025, the net state income tax benefit of state and local NOL carryforwards and associated valuation allowances for Southern Company's subsidiaries were as follows:
Company/Jurisdiction
Approximate Net State
Income Tax Benefit of NOL
Carryforwards
Tax Year NOL
Begins Expiring
Net State Valuation
Allowance for NOL
Carryforwards
(in millions)(in millions)
Mississippi Power
Mississippi $167 2032$(32)
Southern Power
Oklahoma$25 2035$(13)
Florida10 2034(10)
Other states2 
2034
 
Southern Power total
$37 $(23)
Other(*)
New York$11 2036$(11)
New York City14 2036(14)
Other states21 
2026
(5)
Southern Company total
$250 $(85)
(*)Represents other non-registrant Southern Company subsidiaries. Alabama Power, Georgia Power, and Southern Company Gas did not have material state or local NOL carryforwards at December 31, 2025.
Certain state NOLs are not expected to be fully utilized prior to expiration. The ultimate outcome of these matters cannot be determined at this time.
II-195

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Unrecognized Tax Benefits
Changes in unrecognized tax benefits for the periods presented were as follows:
Southern
Company
Alabama
Power
Georgia
Power
Southern
Company Gas
(in millions)
Unrecognized tax benefits at December 31, 2022
$80 $ $ $32 
Tax positions changes —
Increase from prior periods88  86 2 
Statute of limitations expiration(52) (9) 
Unrecognized tax benefits at December 31, 2023
116  77 34 
Tax positions changes —
Increase from prior periods10   10 
Decrease from prior periods
(44) (43) 
Unrecognized tax benefits at December 31, 2024
82  34 44 
Tax positions changes —
Statute of limitations expiration(34) (34) 
Increase from current period
122 50 72  
Unrecognized tax benefits at December 31, 2025
$170 $50 $72 $44 
The unrecognized tax positions increase from prior periods for 2023 is primarily related to the amendment of certain 2019 through 2021 state tax filing positions related to tax credit utilization, a portion of which decreased in the fourth quarter 2023 due to a statute of limitations expiration. If effective settlement of the positions is favorable, these positions would decrease Southern Company's and Georgia Power's annual effective tax rates. The ultimate outcome of this unrecognized tax benefit, which is expected to be resolved within the next 12 months, is dependent on acceptance by the state or expiration of related statute of limitations.
The unrecognized tax positions reductions due to statute of limitations expiration for 2023 primarily relate to a 2019 state tax filing position to exclude certain gains from 2019 dispositions from taxation in a certain unitary state. This tax position and related interest was recognized in the fourth quarter 2023 and decreased Southern Company's annual effective tax rate.
The unrecognized tax positions increase from prior periods for 2024 is primarily related to a certain state tax filing position at Southern Company Gas. If effective settlement of this position is favorable, this position would decrease Southern Company's and Southern Company Gas' annual effective tax rates. The ultimate outcome is dependent on acceptance by the state.
The unrecognized tax positions decrease from prior periods and statute of limitations expiration for 2024 and 2025, respectively, are primarily related to the 2019 through 2021 amended state filing positions related to tax credit utilization at Georgia Power.
Alabama Power and Georgia Power recorded an unrecognized tax position in the second quarter 2025 for zero-emission nuclear power PTCs generated on the consolidated 2024 federal income tax return due to the uncertainty to meet the prevailing wage requirements. In the fourth quarter 2025, the unrecognized tax position at Alabama Power and Georgia Power was reversed as Southern Company received the acceptance letter from the IRS on these PTCs for the 2024 tax year. The reversal of the unrecognized tax position did not impact Southern Company's, Alabama Power's, and Georgia Power's effective tax rates.
The unrecognized tax positions increase from the current period is related to the Alabama Power and Georgia Power zero-emission nuclear power PTCs for the 2025 tax year of $50 million and $72 million, respectively.
All of the Registrants classify interest on tax uncertainties as interest expense. Accrued interest for all tax positions was immaterial for all periods presented. None of the Registrants accrued any penalties on uncertain tax positions.
The IRS has finalized its audits of Southern Company's consolidated federal income tax returns through 2024. Southern Company is a participant in the Compliance Assurance Process of the IRS. The IRS selected six Southern Power partnership returns for exam for the 2020 and 2021 tax years. One audit for 2020 is still under review, and the remaining audits have been closed with no change. The ultimate outcome of this matter cannot be determined at this time. The audits for the Registrants' state income tax returns have either been concluded, or the statute of limitations has expired, for years prior to 2018.
II-196

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

11. RETIREMENT BENEFITS
The Southern Company system has a qualified defined benefit, trusteed pension plan covering substantially all employees, with the exception of PowerSecure employees. The qualified pension plan is funded in accordance with requirements of the Employee Retirement Income Security Act of 1974, as amended (ERISA). No contributions to the qualified pension plan were made for the year ended December 31, 2025 and no mandatory contributions to the qualified pension plan are anticipated for the year ending December 31, 2026. The Southern Company system also provides certain non-qualified defined benefits for a select group of management and highly compensated employees, which are funded on a cash basis. In addition, the Southern Company system provides certain medical care and life insurance benefits for retired employees through other postretirement benefit plans. The traditional electric operating companies fund other postretirement trusts to the extent required by their respective regulatory commissions. For the year ending December 31, 2026, no contributions to any other postretirement trusts are expected.
Actuarial Assumptions
The weighted average rates assumed in the actuarial calculations used to determine both the net periodic costs for the pension and other postretirement benefit plans for the following year and the benefit obligations as of the measurement date are presented below.
2025
Assumptions used to determine net
periodic costs:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
Pension plans
Discount rate – benefit obligations5.76 %5.78 %5.75 %5.76 %5.84 %5.73 %
Discount rate – interest costs5.47 5.48 5.44 5.46 5.58 5.46 
Discount rate – service costs5.93 5.95 5.95 5.94 5.93 5.84 
Expected long-term return on plan assets8.50 8.50 8.50 8.50 8.50 8.50 
Annual salary increase4.60 4.60 4.60 4.60 4.60 4.60 
Other postretirement benefit plans
Discount rate – benefit obligations5.64 %5.67 %5.61 %5.63 %5.73 %5.62 %
Discount rate – interest costs5.35 5.38 5.34 5.34 5.45 5.30 
Discount rate – service costs5.90 5.92 5.91 5.89 5.86 5.89 
Expected long-term return on plan assets7.80 8.06 7.78 7.69 6.44 
Annual salary increase4.60 4.60 4.60 4.60 4.60 4.60 
2024
Assumptions used to determine net
periodic costs:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
Pension plans
Discount rate – benefit obligations5.07 %5.08 %5.06 %5.06 %5.14 %5.05 %
Discount rate – interest costs4.94 4.94 4.94 4.93 5.01 4.93 
Discount rate – service costs5.19 5.20 5.21 5.19 5.20 5.13 
Expected long-term return on plan assets8.30 8.30 8.30 8.30 8.30 8.30 
Annual salary increase4.60 4.60 4.60 4.60 4.60 4.60 
Other postretirement benefit plans
Discount rate – benefit obligations4.99 %5.01 %4.98 %4.98 %5.06 %4.98 %
Discount rate – interest costs4.90 4.90 4.89 4.90 4.94 4.89 
Discount rate – service costs5.16 5.17 5.16 5.16 5.14 5.16 
Expected long-term return on plan assets7.67 7.97 7.59 7.43 6.36 
Annual salary increase4.60 4.60 4.60 4.60 4.60 4.60 
II-197

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

2023
Assumptions used to determine net periodic costs:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
Pension plans
Discount rate – benefit obligations5.25 %5.26 %5.25 %5.25 %5.31 %5.24 %
Discount rate – interest costs5.13 5.14 5.12 5.12 5.19 5.12 
Discount rate – service costs5.36 5.38 5.38 5.37 5.37 5.31 
Expected long-term return on plan assets8.40 8.40 8.40 8.40 8.40 8.40 
Annual salary increase4.80 4.80 4.80 4.80 4.80 4.80 
Other postretirement benefit plans
Discount rate – benefit obligations5.18 %5.20 %5.17 %5.17 %5.24 %5.16 %
Discount rate – interest costs5.08 5.09 5.07 5.08 5.12 5.07 
Discount rate – service costs5.34 5.35 5.34 5.33 5.33 5.33 
Expected long-term return on plan assets7.67 7.95 7.49 7.43 6.59 
Annual salary increase4.80 4.80 4.80 4.80 4.80 4.80 
2025
Assumptions used to determine benefit obligations:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
Pension plans
Discount rate5.69 %5.72 %5.67 %5.66 %5.85 %5.61 %
Annual salary increase5.00 5.00 5.00 5.00 5.00 5.00 
Other postretirement benefit plans
Discount rate5.40 %5.45 %5.34 %5.38 %5.59 %5.38 %
Annual salary increase5.00 5.00 5.00 5.00 5.00 5.00 
2024
Assumptions used to determine benefit obligations:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
Pension plans
Discount rate5.76 %5.78 %5.75 %5.76 %5.84 %5.73 %
Annual salary increase4.60 4.60 4.60 4.60 4.60 4.60 
Other postretirement benefit plans
Discount rate5.64 %5.67 %5.61 %5.63 %5.73 %5.62 %
Annual salary increase4.60 4.60 4.60 4.60 4.60 4.60 
The Registrants estimate the expected rate of return on pension plan and other postretirement benefit plan assets using a financial model to project the expected return on each current investment portfolio. The analysis projects an expected rate of return on each of the different asset classes in order to arrive at the expected return on the entire portfolio relying on each trust's target asset allocation and reasonable capital market assumptions. The financial model is based on four key inputs: anticipated returns by asset class (based in part on historical returns), each trust's target asset allocation, an anticipated inflation rate, and the projected impact of a periodic rebalancing of each trust's portfolio. The Registrants set the expected rate of return assumption using an arithmetic mean which represents the expected simple average return to be earned by the pension plan assets over any one year. The Registrants believe the use of the arithmetic mean is more compatible with the expected rate of return's function of estimating a single year's investment return.
II-198

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

An additional assumption used in measuring the accumulated other postretirement benefit obligations (APBO) was a weighted average medical care cost trend rate. The weighted average medical care cost trend rates used in measuring the APBO for the Registrants at December 31, 2025 were as follows:
Initial Cost
Trend Rate
Ultimate Cost
Trend Rate
Year That
Ultimate Rate is
Reached
Pre-658.50 %4.50 %2034
Post-65 medical6.00 4.50 2034
Post-65 prescription11.00 4.50 2034
Pension Plans
The total accumulated benefit obligation for the pension plans at December 31, 2025 and 2024 was as follows:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
At December 31, 2025$11,952 $2,730 $3,549 $542 $147 $829 
At December 31, 202411,437 2,617 3,438 519 140 779 
An actuarial loss of $458 million and an actuarial gain of $887 million were recorded for the annual remeasurement of the Southern Company system pension plans at December 31, 2025 and 2024, respectively, primarily due to a decrease of 7 basis points and an increase of 69 basis points, respectively, in the overall discount rate used to calculate the benefit obligation as a result of a change in market interest rates.
Changes in the projected benefit obligations and the fair value of plan assets during the plan years ended December 31, 2025 and 2024 were as follows:
2025
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
Change in benefit obligation
Benefit obligation at beginning of year$12,564 $2,908 $3,733 $567 $167 $842 
Service cost264 60 63 11 6 27 
Interest cost664 154 196 30 9 45 
Benefits paid(761)(166)(247)(35)(6)(55)
Actuarial (gain) loss458 99 128 21 (1)36 
Balance at end of year13,189 3,055 3,873 594 175 895 
Change in plan assets
Fair value of plan assets at beginning of year14,559 3,539 4,519 664 188 978 
Actual return on plan assets1,886 452 576 86 22 130 
Employer contributions66 13 13 2 1 2 
Benefits paid(761)(166)(247)(35)(6)(55)
Fair value of plan assets at end of year15,750 3,838 4,861 717 205 1,055 
Accrued asset$2,561 $783 $988 $123 $30 $160 
II-199

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

2024
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
Change in benefit obligation
Benefit obligation at beginning of year$13,252 $3,076 $4,009 $599 $177 $882 
Service cost292 68 70 12 7 28 
Interest cost635 148 191 29 9 42 
Benefits paid(728)(162)(239)(33)(6)(46)
Actuarial gain(887)(222)(298)(40)(20)(64)
Balance at end of year12,564 2,908 3,733 567 167 842 
Change in plan assets
Fair value of plan assets at beginning of year14,618 3,544 4,571 669 185 980 
Actual return on plan assets604 148 152 23 7 39 
Employer contributions65 9 35 5 2 5 
Benefits paid(728)(162)(239)(33)(6)(46)
Fair value of plan assets at end of year14,559 3,539 4,519 664 188 978 
Accrued asset$1,995 $631 $786 $97 $21 $136 
The projected benefit obligations for the qualified and non-qualified pension plans at December 31, 2025 are shown in the following table. All pension plan assets are related to the qualified pension plan.
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
Projected benefit obligations:
Qualified pension plan$12,493 $2,939 $3,762 $566 $154 $837 
Non-qualified pension plan696 116 111 28 21 59 
II-200

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Amounts recognized in the balance sheets at December 31, 2025 and 2024 related to the Registrants' pension plans consist of the following:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
At December 31, 2025:
Prepaid pension costs(a)
$3,257 $899 $1,099 $151 $51 $219 
Other regulatory assets, deferred(b)
2,533 687 907 136  114 
Other current liabilities(68)(12)(13)(3)(2)(3)
Employee benefit obligations(c)
(628)(104)(98)(25)(19)(56)
Other regulatory liabilities, deferred(47)     
AOCI38    4 (56)
At December 31, 2024:
Prepaid pension costs(a)
$2,674 $746 $897 $124 $41 $191 
Other regulatory assets, deferred(b)
2,708 741 973 144  126 
Other current liabilities(68)(13)(13)(2)(2)(4)
Employee benefit obligations(c)
(611)(102)(98)(25)(18)(51)
Other regulatory liabilities, deferred(50)     
AOCI52    11 (54)
(a)Included in prepaid pension and other postretirement benefit costs on Alabama Power's and Southern Company Gas' balance sheets and other deferred charges and assets on Southern Power's consolidated balance sheets.
(b)Amounts for Southern Company exclude regulatory assets of $135 million and $155 million at December 31, 2025 and 2024, respectively, associated with unamortized amounts in Southern Company Gas' pension plans prior to its acquisition by Southern Company.
(c)Included in other deferred credits and liabilities on Southern Power's consolidated balance sheets.
Presented below are the amounts included in regulatory assets at December 31, 2025 and 2024 related to the portion of the defined benefit pension plan attributable to Southern Company, the traditional electric operating companies, and Southern Company Gas that had not yet been recognized in net periodic pension cost.
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Company
Gas
(in millions)
Balance at December 31, 2025
Regulatory assets:
Prior service cost$8 $3 $4 $1 $(2)
Net loss2,478 684 903 135 89 
Regulatory amortization    27 
Total regulatory assets(*)
$2,486 $687 $907 $136 $114 
Balance at December 31, 2024
Regulatory assets:
Prior service cost$8 $3 $5 $1 $(4)
Net loss2,650 738 968 143 91 
Regulatory amortization    39 
Total regulatory assets(*)
$2,658 $741 $973 $144 $126 
(*)Amounts for Southern Company exclude regulatory assets of $135 million and $155 million at December 31, 2025 and 2024, respectively, associated with unamortized amounts in Southern Company Gas' pension plans prior to its acquisition by Southern Company.
II-201

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

The changes in the balance of net regulatory assets (liabilities) related to the portion of the defined benefit pension plan attributable to Southern Company, the traditional electric operating companies, and Southern Company Gas for the years ended December 31, 2025 and 2024 are presented in the following table:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Company
Gas
(in millions)
Net regulatory assets (liabilities):(*)
Balance at December 31, 2023$2,913 $821 $1,051 $152 $143 
Net gain(199)(63)(58)(5)(7)
Reclassification adjustments:
Amortization of prior service costs(1)(1)(1) 2 
Amortization of net loss(55)(16)(19)(3)(1)
Amortization of regulatory assets(*)
    (11)
Total reclassification adjustments(56)(17)(20)(3)(10)
Total change(255)(80)(78)(8)(17)
Balance at December 31, 2024$2,658 $741 $973 $144 $126 
Net (gain) loss(127)(42)(50)(5)1 
Reclassification adjustments:
Amortization of prior service costs(1)(1)(1) 2 
Amortization of net loss(44)(11)(15)(3)(3)
Amortization of regulatory assets(*)
    (12)
Total reclassification adjustments(45)(12)(16)(3)(13)
Total change(172)(54)(66)(8)(12)
Balance at December 31, 2025$2,486 $687 $907 $136 $114 
(*)Amounts for Southern Company exclude regulatory assets of $135 million and $155 million at December 31, 2025 and 2024, respectively, associated with unamortized amounts in Southern Company Gas' pension plans prior to its acquisition by Southern Company.
Presented below are the amounts included in AOCI at December 31, 2025 and 2024 related to the portion of the defined benefit pension plan attributable to Southern Company, Southern Power, and Southern Company Gas that had not yet been recognized in net periodic pension cost.
Southern
Company
Southern
Power
Southern
Company
Gas
(in millions)
Balance at December 31, 2025
AOCI:
Net (gain) loss$38 $4 $(56)
Balance at December 31, 2024
AOCI:
Prior service cost$(1)$ $(1)
Net (gain) loss53 11 (53)
Total AOCI$52 $11 $(54)
II-202

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

The components of OCI related to the portion of the defined benefit pension plan attributable to Southern Company, Southern Power, and Southern Company Gas for the years ended December 31, 2025 and 2024 are presented in the following table:
Southern
Company
Southern
Power
Southern
Company
Gas
(in millions)
AOCI:
Balance at December 31, 2023$79 $20 $(45)
Net gain(29)(9)(11)
Reclassification adjustments:
Amortization of prior service costs1  2 
Amortization of net gain1   
Total reclassification adjustments2  2 
Total change(27)(9)(9)
Balance at December 31, 2024$52 $11 $(54)
Net gain(21)(7)(3)
Reclassification adjustments:
Amortization of prior service costs1  1 
Amortization of net gain6   
Total reclassification adjustments7  1 
Total change(14)(7)(2)
Balance at December 31, 2025$38 $4 $(56)
II-203

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Components of net periodic pension cost for the Registrants were as follows:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
2025
Service cost$264 $60 $63 $11 $6 $27 
Interest cost664 154 196 30 9 45 
Expected return on plan assets(1,281)(312)(397)(59)(17)(86)
Recognized net (gain) loss(*)
38 11 15 3  (1)
Net amortization(*)
 1 1   15 
Prior service cost(*)
     (3)
Net periodic pension income$(315)$(86)$(122)$(15)$(2)$(3)
2024
Service cost$292 $68 $70 $12 $7 $28 
Interest cost635 148 191 29 9 42 
Expected return on plan assets(1,263)(307)(393)(58)(17)(85)
Recognized net loss(*)
55 16 19 3   
Net amortization(*)
 1 1   15 
Prior service cost(*)
     (3)
Net periodic pension income$(281)$(74)$(112)$(14)$(1)$(3)
2023
Service cost$275 $64 $68 $11 $6 $24 
Interest cost626 145 191 28 8 42 
Expected return on plan assets(1,229)(297)(385)(56)(15)(85)
Recognized net (gain) loss(*)
32 9 13 2  (5)
Net amortization(*)
 1 1   15 
Prior service cost(*)
     (3)
Net periodic pension income$(296)$(78)$(112)$(15)$(1)$(12)
(*)For Southern Company, excludes amounts related to net periodic pension cost of $20 million, $20 million, and $17 million for the years ended December 31, 2025, 2024, and 2023, respectively, associated with unamortized amounts in Southern Company Gas' pension plans prior to its acquisition by Southern Company.
The service cost component of net periodic pension cost is included in operations and maintenance expenses and all other components of net periodic pension cost are included in other income (expense), net in the Registrants' statements of income.
Net periodic pension cost is the sum of service cost, interest cost, and other costs netted against the expected return on plan assets. The expected return on plan assets is determined by multiplying the expected rate of return on plan assets and the market-related value of plan assets. In determining the market-related value of plan assets, the Registrants have elected to amortize changes in the market value of return-seeking plan assets over five years and to recognize the changes in the market value of liability-hedging plan assets immediately. Given the significant concentration in return-seeking plan assets, the accounting value of plan assets that is used to calculate the expected return on plan assets differs from the current fair value of the plan assets.
II-204

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Future benefit payments reflect expected future service and are estimated based on assumptions used to measure the projected benefit obligation for the pension plans. At December 31, 2025, estimated benefit payments were as follows:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
Benefit Payments:
2026$803 $176 $252 $36 $7 $62 
2027827 182 255 37 8 63 
2028847 188 259 38 7 65 
2029868 193 264 38 8 66 
2030889 198 267 39 9 68 
2031 to 20354,638 1,041 1,353 209 55 360 
Other Postretirement Benefits
An actuarial loss of $71 million was recorded for the annual remeasurement of the Southern Company system other postretirement benefit plans at December 31, 2025 primarily due to a decrease of 24 basis points in the overall discount rate used to calculate the benefit obligation as a result of a change in market interest rates.
Changes in the APBO and the fair value of the Registrants' plan assets during the plan years ended December 31, 2025 and 2024 were as follows:
2025
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
Change in benefit obligation
Benefit obligation at beginning of year$1,359 $326 $488 $55 $9 $156 
Service cost13 4 4 1   
Interest cost70 17 25 3  7 
Benefits paid(113)(24)(40)(5)(1)(16)
Actuarial (gain) loss71 17 34 3 1 (1)
Balance at end of year1,400 340 511 57 9 146 
Change in plan assets
Fair value of plan assets at beginning of year1,141 421 420 24  141 
Actual return on plan assets158 56 61 4  19 
Employer contributions65 4 17 4 1 12 
Benefits paid(113)(24)(40)(5)(1)(16)
Fair value of plan assets at end of year1,251 457 458 27  156 
Accrued asset (liability)$(149)$117 $(53)$(30)$(9)$10 
II-205

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

2024
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
Change in benefit obligation
Benefit obligation at beginning of year$1,386 $329 $489 $57 $9 $172 
Service cost15 4 4 1  1 
Interest cost65 16 23 3  8 
Benefits paid(105)(25)(37)(4)(1)(12)
Actuarial (gain) loss(2)2 9 (2)1 (13)
Balance at end of year1,359 326 488 55 9 156 
Change in plan assets
Fair value of plan assets at beginning of year1,095 403 410 25  128 
Actual return on plan assets96 37 34   18 
Employer contributions55 6 13 3 1 7 
Benefits paid(105)(25)(37)(4)(1)(12)
Fair value of plan assets at end of year1,141 421 420 24  141 
Accrued asset (liability)$(218)$95 $(68)$(31)$(9)$(15)
Amounts recognized in the balance sheets at December 31, 2025 and 2024 related to the Registrants' other postretirement benefit plans consist of the following:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
At December 31, 2025:
Prepaid other postretirement benefit costs(a)
$ $117 $ $ $ $10 
Other regulatory assets, deferred(b)
25      
Other current liabilities(6)   (1) 
Employee benefit obligations(c)
(143) (53)(30)(8) 
Other regulatory liabilities, deferred(199)(47)(56)(6) (93)
AOCI(13)   1 (16)
At December 31, 2024:
Prepaid other postretirement benefit costs(a)
$ $95 $ $ $ $ 
Other regulatory assets, deferred(b)
24  3    
Other current liabilities(6)   (1) 
Employee benefit obligations(c)
(212) (68)(31)(8)(15)
Other regulatory liabilities, deferred(213)(45)(67)(9) (84)
AOCI(14)    (15)
(a)Included in prepaid pension and other postretirement benefit costs on Alabama Power's and Southern Company Gas' balance sheets.
(b)Amounts for Southern Company exclude regulatory assets of $4 million and $16 million at December 31, 2025 and 2024, respectively, associated with unamortized amounts in Southern Company Gas' other postretirement benefit plans prior to its acquisition by Southern Company.
(c)Included in other deferred credits and liabilities on Southern Power's consolidated balance sheets.
II-206

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Presented below are the amounts included in net regulatory assets (liabilities) at December 31, 2025 and 2024 related to the other postretirement benefit plans of Southern Company, the traditional electric operating companies, and Southern Company Gas that had not yet been recognized in net periodic other postretirement benefit cost.
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Company
Gas
(in millions)
Balance at December 31, 2025:
Regulatory assets (liabilities):
Prior service cost$8 $3 $3 $1 $ 
Net gain(182)(50)(59)(7)(75)
Regulatory amortization    (18)
Total regulatory assets (liabilities)(*)
$(174)$(47)$(56)$(6)$(93)
Balance at December 31, 2024:
Regulatory assets (liabilities):
Prior service cost$11 $3 $4 $1 $ 
Net gain(200)(48)(68)(10)(71)
Regulatory amortization    (13)
Total regulatory assets (liabilities)(*)
$(189)$(45)$(64)$(9)$(84)
(*)Amounts for Southern Company exclude regulatory assets of $4 million and $16 million at December 31, 2025 and 2024, respectively, associated with unamortized amounts in Southern Company Gas' other postretirement benefit plans prior to its acquisition by Southern Company.
The changes in the balance of net regulatory assets (liabilities) related to the other postretirement benefit plans for the plan years ended December 31, 2025 and 2024 are presented in the following table:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Company
Gas
(in millions)
Net regulatory assets (liabilities):(*)
Balance at December 31, 2023$(208)$(48)$(74)$(10)$(68)
Net (gain) loss8 1 6 1 (12)
Reclassification adjustments:
Amortization of prior service costs(2)(1)(1)  
Amortization of net gain13 3 5  5 
Amortization of regulatory assets(*)
    (9)
Total reclassification adjustments11 2 4  (4)
Total change19 3 10 1 (16)
Balance at December 31, 2024$(189)$(45)$(64)$(9)$(84)
Net (gain) loss5 (3)6 3 2 
Reclassification adjustments:
Amortization of prior service costs(2)(1)(1)  
Amortization of net gain (loss)12 2 3  (6)
Amortization of regulatory assets(*)
    (5)
Total reclassification adjustments10 1 2  (11)
Total change15 (2)8 3 (9)
Balance at December 31, 2025$(174)$(47)$(56)$(6)$(93)
(*)Amounts for Southern Company exclude regulatory assets of $4 million and $16 million at December 31, 2025 and 2024, respectively, associated with unamortized amounts in Southern Company Gas' other postretirement benefit plans prior to its acquisition by Southern Company.
II-207

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Presented below are the amounts included in AOCI at December 31, 2025 and 2024 related to the other postretirement benefit plans of Southern Company, Southern Power, and Southern Company Gas that had not yet been recognized in net periodic other postretirement benefit cost.
Southern
Company
Southern
Power
Southern
Company
Gas
(in millions)
Balance at December 31, 2025
AOCI:
Net (gain) loss$(13)$1 $(16)
Balance at December 31, 2024
AOCI:
Net gain$(14)$ $(15)
The components of OCI related to the other postretirement benefit plans for the plan years ended December 31, 2025 and 2024 are presented in the following table:
Southern
Company
Southern
Power
Southern
Company Gas
(in millions)
AOCI:
Balance at December 31, 2023$(9)$1 $(10)
Net gain(8)(1)(5)
Reclassification adjustments:
Amortization of net gain3   
Total change(5)(1)(5)
Balance at December 31, 2024$(14)$ $(15)
Net (gain) loss(1)1 (1)
Reclassification adjustments:
Amortization of net gain2   
Total change1 1 (1)
Balance at December 31, 2025$(13)$1 $(16)
II-208

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Components of the other postretirement benefit plans' net periodic cost for the Registrants were as follows:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
2025
Service cost$13 $4 $4 $1 $ $ 
Interest cost70 17 25 3  7 
Expected return on plan assets(91)(35)(33)(3)1 (15)
Net amortization(*)
(12)(2)(2)  5 
Net periodic other postretirement benefit cost (income)$(20)$(16)$(6)$1 $1 $(3)
2024
Service cost$15 $4 $4 $1 $ $1 
Interest cost65 16 23 3  8 
Expected return on plan assets(89)(35)(32)(3)1 (13)
Net amortization(*)
(13)(3)(4)  6 
Net periodic other postretirement benefit cost (income)$(22)$(18)$(9)$1 $1 $2 
2023
Service cost$15 $4 $4 $1 $ $1 
Interest cost70 17 25 3  9 
Expected return on plan assets(83)(33)(29)(3)1 (10)
Net amortization(*)
(11)(3)(3)  6 
Net periodic other postretirement benefit cost (income)$(9)$(15)$(3)$1 $1 $6 
(*)For Southern Company, excludes amounts related to net periodic other postretirement benefit cost of $12 million, $8 million, and $8 million for the years ended December 31, 2025, 2024, and 2023, respectively, associated with unamortized amounts in Southern Company Gas' other postretirement benefit plans prior to its acquisition by Southern Company.
The service cost component of net periodic other postretirement benefit cost is included in operations and maintenance expenses and all other components of net periodic other postretirement benefit cost are included in other income (expense), net in the Registrants' statements of income.
The Registrants' future benefit payments, including prescription drug benefits, are provided in the table below. These amounts reflect expected future service and are estimated based on assumptions used to measure the APBO for the other postretirement benefit plans.
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
Benefit payments:
2026$114 $26 $42 $5 $1 $15 
2027115 26 43 5 1 15 
2028116 27 43 5 1 14 
2029116 27 43 5 1 14 
2030116 27 43 5 1 13 
2031 to 2035566 136 211 23 1 56 
II-209

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Benefit Plan Assets
Pension plan and other postretirement benefit plan assets are managed and invested in accordance with all applicable requirements, including ERISA and the Internal Revenue Code. The Registrants' investment policies for both the pension plans and the other postretirement benefit plans cover a diversified mix of assets as described below. Derivative instruments may be used to gain efficient exposure to the various asset classes and as hedging tools. Additionally, the Registrants minimize the risk of large losses primarily through diversification but also monitor and manage other aspects of risk.
The investment strategy for plan assets related to the Southern Company system's qualified pension plan is to be broadly diversified across major asset classes. The asset allocation is established after consideration of various factors that affect the assets and liabilities of the pension plan including, but not limited to, historical and expected returns and interest rates, volatility, correlations of asset classes, the current level of assets and liabilities, and the assumed growth in assets and liabilities. Because a significant portion of the liability of the pension plan is long-term in nature, the assets are invested consistent with long-term investment expectations for return and risk. To manage the actual asset class exposures relative to the target asset allocation, the Southern Company system employs a formal rebalancing program. As additional risk management, external investment managers and service providers are subject to written guidelines to ensure appropriate and prudent investment practices. Management believes the portfolio is well-diversified with no significant concentrations of risk.
II-210

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Investment Strategies and Benefit Plan Asset Fair Values
A description of the major asset classes that the pension and other postretirement benefit plans are comprised of, along with the valuation methods used for fair value measurement, is provided below:
DescriptionValuation Methodology
Domestic equity: A mix of large and small capitalization stocks with generally an equal distribution of value and growth attributes, managed both actively and through passive index approaches.

International equity: A mix of large and small capitalization growth and value stocks with developed and emerging markets exposure, managed both actively and through fundamental indexing approaches.
Domestic and international equities such as common stocks, American depositary receipts, and real estate investment trusts that trade on public exchanges are classified as Level 1 investments and are valued at the closing price in the active market. Equity funds with unpublished prices that are comprised of publicly traded securities (such as commingled/pooled funds) are also valued at the closing price in the active market but are classified as Level 2.
Fixed income: A mix of domestic and international bonds.
Investments in fixed income securities, including fixed income pooled funds, are generally classified as Level 2 investments and are valued based on prices reported in the market place. Additionally, the value of fixed income securities takes into consideration certain items such as broker quotes, spreads, yield curves, interest rates, and discount rates that apply to the term of a specific instrument.
Trust-owned life insurance (TOLI): Investments of taxable trusts aimed at minimizing the impact of taxes on the portfolio.
Investments in TOLI policies are classified as Level 2 investments and are valued based on the underlying investments held in the policy's separate accounts. The underlying assets are equity and fixed income pooled funds that are comprised of Level 1 and Level 2 securities.
Real estate: Investments in equity or debt of real properties and in publicly traded real estate securities.

Special situations: Investments in opportunistic strategies with the objective of diversifying and enhancing returns and exploiting short-term inefficiencies, as well as investments in promising new strategies of a longer-term nature.

Private equity: Investments in private or public securities typically through privately-negotiated and/or structured transactions, including leveraged buyouts, venture capital, and distressed debt.

Private credit: Investments focused on debt instruments, of which returns are driven by income rather than capital appreciation.

Infrastructure: Investments in real assets, typically with long-term, predictable, and stable cash flows and a meaningful income component.
Investments in real estate, special situations, private equity, private credit, and infrastructure are typically invested in private partnerships and/or other pooled vehicles (Investment Funds) which are generally classified as Net Asset Value as a Practical Expedient, since the Investment Funds and underlying assets are not publicly traded and/or often have liquidity restrictions. The managers of the Investment Funds value the assets using various inputs and techniques depending on the nature of the underlying investments. Techniques may include purchase multiples for comparable transactions, comparable public company trading multiples, discounted cash flow analysis, prevailing market capitalization rates, recent sales of comparable investments, and independent third-party appraisals. The total market value of each of the Investment Funds is determined by aggregating the value of the underlying assets less liabilities.
For purposes of determining the fair value of the pension plan and other postretirement benefit plan assets and the appropriate level designation, management relies on information provided by the plan's trustee. This information is reviewed and evaluated by management with changes made to the trustee information as appropriate. The fair values presented herein exclude cash, receivables related to investment income and pending investment sales, and payables related to pending investment purchases.
II-211

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

The fair values, and actual allocations relative to the target allocations, of the Southern Company system's pension plans at December 31, 2025 and 2024 are presented below.
Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets
Significant
Other
Observable
Inputs
Net Asset
Value as a
Practical
Expedient
Target
Allocation
Actual
Allocation
At December 31, 2025:(Level 1)(Level 2)(NAV)Total
(in millions)
Southern Company
Assets:
Equity:41 %42 %
Domestic equity$2,216 $884 $ $3,100 
International equity2,219 1,184  3,403 
Fixed income:30 31 
U.S. Treasury, government, and agency bonds 1,994  1,994 
Mortgage- and asset-backed securities 75  75 
Corporate bonds 1,859  1,859 
Pooled funds 850  850 
Cash equivalents and other237 5  242 
Real estate investments350  1,541 1,891 12 12 
Special situations  258 258 3 2 
Private equity  1,829 1,829 9 11 
Private credit
  265 265 3 2 
Infrastructure
  60 60 2  
Total$5,022 $6,851 $3,953 $15,826 100 %100 %
Liabilities:
Derivatives$(1)$ $ $(1)
Total$5,021 $6,851 $3,953 $15,825 100 %100 %
Alabama Power
Assets:
Equity:41 %42 %
Domestic equity$538 $215 $ $753 
International equity541 289  830 
Fixed income:30 31 
U.S. Treasury, government, and agency bonds 486  486 
Mortgage- and asset-backed securities 18  18 
Corporate bonds 453  453 
Pooled funds 207  207 
Cash equivalents and other58 1  59 
Real estate investments85  376 461 12 12 
Special situations  63 63 3 2 
Private equity  446 446 9 11 
Private credit
  65 65 3 2 
Infrastructure
  15 15 2  
Total$1,222 $1,669 $965 $3,856 100 %100 %
II-212

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets
Significant
Other
Observable
Inputs
Net Asset
Value as a
Practical
Expedient
Target
Allocation
Actual
Allocation
At December 31, 2025:(Level 1)(Level 2)(NAV)Total
Target
Allocation
Actual
Allocation
(in millions)
Georgia Power
Assets:
Equity:41 %42 %
Domestic equity$683 $273 $ $956 
International equity685 365  1,050 
Fixed income:30 31 
U.S. Treasury, government, and agency bonds 615  615 
Mortgage- and asset-backed securities 23  23 
Corporate bonds 574  574 
Pooled funds 262  262 
Cash equivalents and other73 2  75 
Real estate investments108  476 584 12 12 
Special situations  80 80 3 2 
Private equity  564 564 9 11 
Private credit
  82 82 3 2 
Infrastructure
  19 19 2  
Total$1,549 $2,114 $1,221 $4,884 100 %100 %
Mississippi Power
Assets:
Equity:41 %42 %
Domestic equity$100 $40 $ $140 
International equity101 54  155 
Fixed income:30 31 
U.S. Treasury, government, and agency bonds 91  91 
Mortgage- and asset-backed securities 3  3 
Corporate bonds 85  85 
Pooled funds 39  39 
Cash equivalents and other11   11 
Real estate investments16  70 86 12 12 
Special situations  12 12 3 2 
Private equity  83 83 9 11 
Private credit
  12 12 3 2 
Infrastructure
  3 3 2  
Total$228 $312 $180 $720 100 %100 %
II-213

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets
Significant
Other
Observable
Inputs
Net Asset
Value as a
Practical
Expedient
Target
Allocation
Actual
Allocation
At December 31, 2025:(Level 1)(Level 2)(NAV)Total
Target
Allocation
Actual
Allocation
(in millions)
Southern Power
Assets:
Equity:41 %42 %
Domestic equity$29 $12 $ $41 
International equity29 15  44 
Fixed income:30 31 
U.S. Treasury, government, and agency bonds 26  26 
Mortgage- and asset-backed securities 1  1 
Corporate bonds 24  24 
Pooled funds 11  11 
Cash equivalents and other3   3 
Real estate investments5  20 25 12 12 
Special situations  3 3 3 2 
Private equity  24 24 9 11 
Private credit
  3 3 3 2 
Infrastructure
  1 1 2  
Total$66 $89 $51 $206 100%100 %
Southern Company Gas
Assets:
Equity:41 %42 %
Domestic equity$148 $59 $ $207 
International equity149 79  228 
Fixed income:30 31 
U.S. Treasury, government, and agency bonds 134  134 
Mortgage- and asset-backed securities 5  5 
Corporate bonds 125  125 
Pooled funds 57  57 
Cash equivalents and other16   16 
Real estate investments23  103 126 12 12 
Special situations  17 17 3 2 
Private equity  123 123 9 11 
Private credit
  18 18 3 2 
Infrastructure
  4 4 2  
Total$336 $459 $265 $1,060 100 %100 %
II-214

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets
Significant
Other
Observable
Inputs
Net Asset
Value as a
Practical
Expedient
Target
Allocation
Actual
Allocation
At December 31, 2024:(Level 1)(Level 2)(NAV)Total
(in millions)
Southern Company
Assets:
Equity:41 %41 %
Domestic equity$2,095 $835 $ $2,930 
International equity1,959 1,032  2,991 
Fixed income:30 31 
U.S. Treasury, government, and agency bonds 1,780  1,780 
Mortgage- and asset-backed securities 48  48 
Corporate bonds 1,715  1,715 
Pooled funds 792  792 
Cash equivalents and other255   255 
Real estate investments361  1,563 1,924 12 13 
Special situations  237 237 3 2 
Private equity  1,797 1,797 9 12 
Private Credit— — 152 152 3 
Infrastructure— — — — 2 — 
Total$4,670 $6,202 $3,749 $14,621 100 %100 %
Liabilities:
Derivatives$ $(33)$ $(33)
Total$4,670 $6,169 $3,749 $14,588 100 %100 %
II-215

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets
Significant
Other
Observable
Inputs
Net Asset
Value as a
Practical
Expedient
Target
Allocation
Actual
Allocation
At December 31, 2024:(Level 1)(Level 2)(NAV)Total
Target
Allocation
Actual
Allocation
(in millions)
Alabama Power
Assets:
Equity:41 %41 %
Domestic equity$509 $203 $ $712 
International equity476 251  727 
Fixed income:30 31 
U.S. Treasury, government, and agency bonds 433  433 
Mortgage- and asset-backed securities 12  12 
Corporate bonds 417  417 
Pooled funds 193  193 
Cash equivalents and other62   62 
Real estate investments88  380 468 12 13 
Special situations  57 57 3 2 
Private equity  437 437 9 12 
Private credit
— — 37 37 3 
Infrastructure
— — — — 2 — 
Total$1,135 $1,509 $911 $3,555 100 %100 %
Liabilities:
Derivatives$ $(8)$ $(8)
Total$1,135 $1,501 $911 $3,547 100 %100 %
II-216

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets
Significant
Other
Observable
Inputs
Net Asset
Value as a
Practical
Expedient
Target
Allocation
Actual
Allocation
At December 31, 2024:(Level 1)(Level 2)(NAV)Total
Target
Allocation
Actual
Allocation
(in millions)
Georgia Power
Assets:
Equity:41 %41 %
Domestic equity$652 $259 $ $911 
International equity608 320  928 
Fixed income:30 31 
U.S. Treasury, government, and agency bonds 552  552 
Mortgage- and asset-backed securities 15  15 
Corporate bonds 532  532 
Pooled funds 246  246 
Cash equivalents and other79   79 
Real estate investments112  485 597 12 13 
Special situations  73 73 3 2 
Private equity  558 558 9 12 
Private credit
  47 47 3 1 
Infrastructure
    2  
Total$1,451 $1,924 $1,163 $4,538 100 %100 %
Liabilities:
Derivatives$ $(10)$ $(10)
Total$1,451 $1,914 $1,163 $4,528 100 %100 %
II-217

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets
Significant
Other
Observable
Inputs
Net Asset
Value as a
Practical
Expedient
Target
Allocation
Actual
Allocation
At December 31, 2024:(Level 1)(Level 2)(NAV)Total
Target
Allocation
Actual
Allocation
(in millions)
Mississippi Power
Assets:
Equity:41 %41 %
Domestic equity$97 $38 $ $135 
International equity89 47  136 
Fixed income:30 31 
U.S. Treasury, government, and agency bonds 81  81 
Mortgage- and asset-backed securities 2  2 
Corporate bonds 78  78 
Pooled funds 36  36 
Cash equivalents and other12   12 
Real estate investments16  71 87 12 13 
Special situations  11 11 3 2 
Private equity  82 82 9 12 
Private credit
  7 7 3 1 
Infrastructure
    2  
Total$214 $282 $171 $667 100 %100 %
Liabilities:
Derivatives$ $(2)$ $(2)
Total$214 $280 $171 $665 100 %100 %
Southern Power
Assets:
Equity:41 %41 %
Domestic equity$27 $11 $ $38 
International equity25 13  38 
Fixed income:30 31 
U.S. Treasury, government, and agency bonds 23  23 
Mortgage- and asset-backed securities
 1  1 
Corporate bonds 22  22 
Pooled funds 10  10 
Cash equivalents and other3   3 
Real estate investments5  20 25 12 13 
Special situations  3 3 3 2 
Private equity  23 23 9 12 
Private credit
  2 2 3 1 
Infrastructure
    2  
Total$60 $80 $48 $188 100 %100 %
II-218

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets
Significant
Other
Observable
Inputs
Net Asset
Value as a
Practical
Expedient
Target
Allocation
Actual
Allocation
At December 31, 2024:(Level 1)(Level 2)(NAV)Total
Target
Allocation
Actual
Allocation
(in millions)
Southern Company Gas
Assets:
Equity:41 %41 %
Domestic equity$142 $56 $ $198 
International equity132 69  201 
Fixed income:30 31 
U.S. Treasury, government, and agency bonds 120  120 
Mortgage- and asset-backed securities 3  3 
Corporate bonds 115  115 
Pooled funds 53  53 
Cash equivalents and other17   17 
Real estate investments24  105 129 12 13 
Special situations  16 16 3 2 
Private equity  121 121 9 12 
Private credit
— — 10 10 3 
Infrastructure
— — — — 2 — 
Total$315 $416 $252 $983 100 %100 %
Liabilities:
Derivatives$ $(2)$ $(2)
Total$315 $414 $252 $981 100 %100 %
II-219

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

The fair values, and actual allocations relative to the target allocations, of the applicable Registrants' other postretirement benefit plan assets at December 31, 2025 and 2024 are presented below.
Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets
Significant
Other
Observable
Inputs
Net Asset
Value as a
Practical
Expedient
Total
Target
Allocation
Actual
Allocation
At December 31, 2025:
(Level 1)
(Level 2)
(NAV)
(in millions)
Southern Company
Assets:
Equity:60 %63 %
Domestic equity$98 $108 $ $206 
International equity63 102  165 
Fixed income:30 27 
U.S. Treasury, government, and agency bonds 61  61 
Mortgage- and asset-backed securities 2  2 
Corporate bonds 53  53 
Pooled funds 106  106 
Cash equivalents and other13   13 
Trust-owned life insurance 520  520 
Real estate investments11  44 55 4 4 
Special situations  7 7 1 1 
Private equity  52 52 3 4 
Private credit
  7 7 1 1 
Infrastructure
  2 2 1  
Total$185 $952 $112 $1,249 100 %100 %
II-220

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets
Significant
Other
Observable
Inputs
Net Asset
Value as a
Practical
Expedient
Total
Target
Allocation
Actual
Allocation
At December 31, 2025:
(Level 1)
(Level 2)
(NAV)Total
Target
Allocation
Actual
Allocation
(in millions)
Alabama Power
Assets:
Equity:68 %69 %
Domestic equity$18 $7 $ $25 
International equity18 10  28 
Fixed income:23 23 
U.S. Treasury, government, and agency bonds 17  17 
Mortgage- and asset-backed securities 1  1 
Corporate bonds 15  15 
Pooled funds 11  11 
Cash equivalents and other2   2 
Trust-owned life insurance 320  320 
Real estate investments3  13 16 3 3 
Special situations  2 2 1 1 
Private equity  15 15 3 3 
Private credit  2 2 1 1 
Infrastructure    1  
Total$41 $381 $32 $454 100 %100 %
Georgia Power
Assets:
Equity:59 %60 %
Domestic equity$54 $7 $ $61 
International equity18 50  68 
Fixed income:35 32 
U.S. Treasury, government, and agency bonds 17  17 
Mortgage- and asset-backed securities 1  1 
Corporate bonds 15  15 
Pooled funds 51  51 
Cash equivalents and other8   8 
Trust-owned life insurance 201  201 
Real estate investments4  13 17 3 3 
Special situations  2 2 1 1 
Private equity  15 15 2 3 
Private credit
  2 2  1 
Total$84 $342 $32 $458 100 %100 %
II-221

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets
Significant
Other
Observable
Inputs
Net Asset
Value as a
Practical
Expedient
Total
Target
Allocation
Actual
Allocation
At December 31, 2025:
(Level 1)
(Level 2)
(NAV)Total
Target
Allocation
Actual
Allocation
(in millions)
Mississippi Power
Assets:
Equity:34 %34 %
Domestic equity$3 $1 $ $4 
International equity3 2  5 
Fixed income:43 43 
U.S. Treasury, government, and agency bonds 7  7 
Corporate bonds 3  3 
Pooled funds 1  1 
Cash equivalents and other1   1 
Real estate investments  2 2 10 10 
Special situations    2 2 
Private equity  3 3 7 9 
Private credit
    3 2 
Infrastructure
    1  
Total$7 $14 $5 $26 100 %100 %
Southern Company Gas
Assets:
Equity:72 %74 %
Domestic equity$1 $83 $ $84 
International equity1 29  30 
Fixed income:26 24 
U.S. Treasury, government, and agency bonds 1  1 
Corporate bonds 1  1 
Pooled funds 34  34 
Cash equivalents and other1   1 
Real estate investments  1 1 1 1 
Private equity  1 1 1 1 
Total$3 $148 $2 $153 100 %100 %
II-222

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets
Significant
Other
Observable
Inputs
Net Asset
Value as a
Practical
Expedient
Target
Allocation
Actual
Allocation
At December 31, 2024:(Level 1)(Level 2)(NAV)Total
(in millions)
Southern Company
Assets:
Equity:61 %62 %
Domestic equity$94 $98 $ $192 
International equity54 83  137 
Fixed income:29 28 
U.S. Treasury, government, and agency bonds 54  54 
Mortgage- and asset-backed securities 1  1 
Corporate bonds 48  48 
Pooled funds 99  99 
Cash equivalents and other16   16 
Trust-owned life insurance 478  478 
Real estate investments11  43 54 4 5 
Special situations  6 6 1 1 
Private equity  50 50 3 4 
Private credit
— — 4 4 1 — 
Infrastructure
— — — — 1 — 
Total$175 $861 $103 $1,139 100 %100 %
Liabilities:
Derivatives$ $(1)$ $(1)
Total$175 $860 $103 $1,138 100 %100 %
II-223

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets
Significant
Other
Observable
Inputs
Net Asset
Value as a
Practical
Expedient
Target
Allocation
Actual
Allocation
At December 31, 2024:(Level 1)(Level 2)(NAV)Total
Target
Allocation
Actual
Allocation
(in millions)
Alabama Power
Assets:
Equity:68 %68 %
Domestic equity$17 $7 $ $24 
International equity16 9  25 
Fixed income:23 24 
U.S. Treasury, government, and agency bonds 14  14 
Corporate bonds 14  14 
Pooled funds 11  11 
Cash equivalents and other2   2 
Trust-owned life insurance 294  294 
Real estate investments3  13 16 3 4 
Special situations  2 2 1 1 
Private equity  15 15 3 3 
Private credit
— — 1 1 1  
Infrastructure
— — — — 1  
Total$38 $349 $31 $418 100 %100 %
Georgia Power
Assets:
Equity:59 %59 %
Domestic equity$52 $7 $ $59 
International equity16 41  57 
Fixed income:35 33 
U.S. Treasury, government, and agency bonds 14  14 
Corporate bonds 14  14 
Pooled funds 48  48 
Cash equivalents and other10   10 
Trust-owned life insurance 184  184 
Real estate investments4  13 17 3 4 
Special situations  2 2 1 1 
Private equity  15 15 2 3 
Total$82 $308 $30 $420 100 %100 %
II-224

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets
Significant
Other
Observable
Inputs
Net Asset
Value as a
Practical
Expedient
Target
Allocation
Actual
Allocation
At December 31, 2024:(Level 1)(Level 2)(NAV)Total
Target
Allocation
Actual
Allocation
(in millions)
Mississippi Power
Assets:
Equity:34 %32 %
Domestic equity$3 $1 $ $4 
International equity3 1  4 
Fixed income:43 44 
U.S. Treasury, government, and agency bonds 7  7 
Corporate bonds 2  2 
Pooled funds 1  1 
Cash equivalents and other1   1 
Real estate investments  2 2 10 11 
Special situations    2 2 
Private equity  2 2 7 10 
Private credit
— — — — 3 1 
Infrastructure
— — — — 1 — 
Total$7 $12 $4 $23 100 %100 %
Southern Company Gas
Assets:
Equity:72 %73 %
Domestic equity$1 $76 $ $77 
International equity1 23  24 
Fixed income:26 25 
U.S. Treasury, government, and agency bonds 1  1 
Corporate bonds 1  1 
Pooled funds 32  32 
Cash equivalents and other1   1 
Real estate investments  1 1 1 1 
Private equity  1 1 1 1 
Total$3 $133 $2 $138 100 %100 %
II-225

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Employee Savings Plan
Southern Company and its subsidiaries also sponsor 401(k) defined contribution plans covering substantially all employees and provide matching contributions up to specified percentages of an employee's eligible pay. Total matching contributions made to the plans for 2025, 2024, and 2023 were as follows:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
(in millions)
2025$148 $30 $36 $5 $3 $21 
2024137 29 31 5 3 20 
2023131 28 31 5 3 18 
12. STOCK COMPENSATION
Stock-based compensation in the form of Southern Company performance share units (PSU) and restricted stock units (RSU) may be granted through the Equity and Incentive Compensation Plan to eligible Southern Company system employees.
At December 31, 2025, the number of current and former employees participating in stock-based compensation programs for the Registrants was as follows:
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
Gas
Number of employees1,189 163 185 37 33 182 
The majority of PSUs and RSUs awarded contain terms where employees become immediately vested in PSUs and RSUs upon retirement. As a result, compensation expense for employees that are retirement eligible at the grant date is recognized immediately, while compensation expense for employees that are expected to become retirement eligible during the vesting period is recognized over the period from grant date to the date of retirement eligibility. In addition, the Registrants recognize forfeitures as they occur.
All unvested PSUs and RSUs vest immediately upon a change in control where Southern Company is not the surviving corporation. Stock-based compensation activity is immaterial for the Subsidiary Registrants.
In 2015, Southern Company discontinued granting stock options. As of December 31, 2017, all stock option awards were vested and compensation cost fully recognized, and the last exercise occurred in November 2024. Southern Company's cash receipts from issuances related to stock options exercised under the share-based payment arrangements, total intrinsic value of options exercised, and the related tax benefit were immaterial for the years ended December 31, 2024 and 2023.
Performance Share Units
PSUs granted to employees vest at the end of a three-year performance period. Shares of Southern Company common stock are delivered to employees at the end of the performance period with the number of shares issued ranging from 0% to 200% of the target number of PSUs granted, based on achievement of the performance goals established by the Compensation Committee of the Southern Company Board of Directors.
Southern Company has issued two types of PSUs, each with a unique performance goal. These types of PSUs include total shareholder return (TSR) awards based on the TSR for Southern Company common stock during the three-year performance period as compared to a group of industry peers and ROE awards based on Southern Company's equity-weighted return over the performance period.
The fair value of TSR awards is determined as of the grant date using a Monte Carlo simulation model. In determining the fair value of the TSR awards issued to employees, the expected volatility is based on the historical volatility of Southern Company's stock over a period equal to the performance period. The risk-free rate is based on the U.S. Treasury yield curve in effect at the
II-226

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

time of grant that covers the performance period of the awards. The following table shows the assumptions used in the pricing model and the weighted average grant-date fair value of TSR awards granted:
Year Ended December 31202520242023
Expected volatility19.7%19.1%30.0%
Interest rate4.1%4.0%3.8%
Weighted average grant-date fair value$91.26$80.99$76.83
The Registrants recognize TSR award compensation expense on a straight-line basis over the three-year performance period without remeasurement.
The fair values of ROE awards are based on the closing stock price of Southern Company common stock on the date of the grant. The weighted average grant-date fair value of the ROE awards granted during 2025, 2024, and 2023 was $84.06, $69.67, and $68.93, respectively. Compensation expense for ROE awards is generally recognized ratably over the three-year performance period adjusted for expected changes in ROE performance. Total compensation cost recognized for vested ROE awards reflects final performance metrics.
Southern Company had 2.3 million unvested PSUs outstanding at December 31, 2024. In February 2025, the PSUs that vested for the three-year performance period ended December 31, 2024 were converted into 2.0 million shares outstanding at a share price of $83.87. During 2025, Southern Company granted 1.0 million PSUs and 1.3 million PSUs were vested or forfeited, resulting in 2.0 million unvested PSUs outstanding at December 31, 2025. In February 2026, the PSUs that vested for the three-year performance period ended December 31, 2025 were converted into 2.4 million shares outstanding at a weighted average share price of $90.86.
Southern Company's total PSU compensation cost and the related tax benefit recognized in income for the years ended December 31, 2025, 2024, and 2023 were as follows:
202520242023
(in millions)
Compensation cost recognized in income$102 $102 $107 
Tax benefit of compensation cost recognized in income26 27 28 
The compensation cost related to the grant of Southern Company PSUs to the employees of each Subsidiary Registrant is recognized in each Subsidiary Registrant's financial statements with a corresponding credit to equity representing a capital contribution from Southern Company.
At December 31, 2025, Southern Company's total unrecognized compensation cost related to PSUs was $32 million and is expected to be recognized over a weighted-average period of approximately 18 months.
Restricted Stock Units
The fair value of RSUs is based on the closing stock price of Southern Company common stock on the date of the grant. The weighted average grant-date fair values of RSUs granted during 2025, 2024, and 2023 were $85.18, $70.49, and $68.95, respectively. For most RSU awards, one-third of the RSUs vest each year throughout a three-year service period and compensation cost for RSUs is generally recognized over the corresponding one-, two-, or three-year vesting period. Shares of Southern Company common stock are delivered to employees at the end of each vesting period.
Southern Company had 0.9 million RSUs outstanding at December 31, 2024. During 2025, Southern Company granted 0.5 million RSUs and 0.5 million RSUs were vested or forfeited, resulting in 0.9 million unvested RSUs outstanding at December 31, 2025, including RSUs related to employee retention agreements.
Southern Company's total RSU compensation cost and the related tax benefit recognized in income for the years ended December 31, 2025, 2024, and 2023 were as follows:
202520242023
(in millions)
Compensation cost recognized in income$33 $30 $30 
Tax benefit of compensation cost recognized in income9 8 8 
Total unrecognized compensation cost related to RSUs at December 31, 2025, which is being recognized over a weighted-average period of approximately 18 months, was immaterial for Southern Company.
II-227

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

The compensation cost related to the grant of Southern Company RSUs to the employees of each Subsidiary Registrant is recognized in such Subsidiary Registrant's financial statements with a corresponding credit to equity representing a capital contribution from Southern Company.
13. FAIR VALUE MEASUREMENTS
Fair value measurements are based on inputs of observable and unobservable market data that a market participant would use in pricing the asset or liability. The use of observable inputs is maximized where available and the use of unobservable inputs is minimized for fair value measurement and reflects a three-tier fair value hierarchy that prioritizes inputs to valuation techniques used for fair value measurement.
Level 1 consists of observable market data in an active market for identical assets or liabilities.
Level 2 consists of observable market data, other than that included in Level 1, that is either directly or indirectly observable.
Level 3 consists of unobservable market data. The input may reflect the assumptions of each Registrant of what a market participant would use in pricing an asset or liability. If there is little available market data, then each Registrant's own assumptions are the best available information.
In the case of multiple inputs being used in a fair value measurement, the lowest level input that is significant to the fair value measurement represents the level in the fair value hierarchy in which the fair value measurement is reported.
Net asset value as a practical expedient is the classification used for assets that do not have readily determined fair values. Fund managers value the assets using various inputs and techniques depending on the nature of the underlying investments.
II-228

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

At December 31, 2025, assets and liabilities measured at fair value on a recurring basis during the period, together with their associated level of the fair value hierarchy, were as follows:
Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets 
Significant
Other
Observable
Inputs
Significant
Unobservable
Inputs
Net Asset
Value as a
Practical
Expedient
At December 31, 2025:(Level 1)(Level 2)(Level 3)(NAV)Total
(in millions)
Southern Company
Assets:
Energy-related derivatives(a)
$4 $60 $ $ $64 
Interest rate derivatives 8   8 
Foreign currency derivatives 21   21 
Investments in trusts:(b)
Domestic equity935 278   1,213 
Foreign equity182 225   407 
U.S. Treasury and government agency securities 398   398 
Municipal bonds 50   50 
Pooled funds – fixed income 6   6 
Corporate bonds 520   520 
Mortgage- and asset-backed securities
 114   114 
Private equity   192 192 
Cash and cash equivalents1    1 
Other50 3  9 62 
Investments, available for sale:
U.S. Treasury and government agency securities3 12   15 
Corporate bonds1 2   3 
Mortgage- and asset-backed securities
 5   5 
Cash equivalents
1,080 19   1,099 
Other investments10 34 8  52 
Other
  11  11 
Total$2,266 $1,755 $19 $201 $4,241 
Liabilities:
Energy-related derivatives(a)
$12 $100 $ $ $112 
Interest rate derivatives 187   187 
Foreign currency derivatives 22   22 
Contingent consideration3  11  14 
Other 13 11  24 
Total$15 $322 $22 $ $359 
II-229

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets 
Significant
Other
Observable
Inputs
Significant
Unobservable
Inputs
Net Asset
Value as a
Practical
Expedient
At December 31, 2025:(Level 1)(Level 2)(Level 3)(NAV)Total
(in millions)
Alabama Power
Assets:
Energy-related derivatives
$ $19 $ $ $19 
Nuclear decommissioning trusts:(b)
Domestic equity514 267   781 
Foreign equity182    182 
U.S. Treasury and government agency securities 15   15 
Municipal bonds 1   1 
Corporate bonds 316   316 
Mortgage- and asset-backed securities
 31   31 
Private equity    192 192 
Other12 1  9 22 
Cash equivalents
273 19   292 
Other investments 34   34 
Total$981 $703 $ $201 $1,885 
Liabilities:
Energy-related derivatives$ $31 $ $ $31 
Georgia Power
Assets:
Energy-related derivatives$ $18 $ $ $18 
Nuclear decommissioning trusts:(b)
Domestic equity421 1   422 
Foreign equity 224   224 
U.S. Treasury and government agency securities 383   383 
Municipal bonds 49   49 
Corporate bonds 204   204 
Mortgage- and asset-backed securities
 83   83 
Other38 2   40 
Cash equivalents20    20 
Total$479 $964 $ $ $1,443 
Liabilities:
Energy-related derivatives$ $33 $ $ $33 
II-230

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets 
Significant
Other
Observable
Inputs
Significant
Unobservable
Inputs
Net Asset
Value as a
Practical
Expedient
At December 31, 2025:(Level 1)(Level 2)(Level 3)(NAV)Total
(in millions)
Mississippi Power
Assets:
Energy-related derivatives$ $14 $ $ $14 
Cash equivalents12    12 
Total$12 $14 $ $ $26 
Liabilities:
Energy-related derivatives$ $27 $ $ $27 
Southern Power
Assets:
Energy-related derivatives$ $4 $ $ $4 
Foreign currency derivatives 17   17 
Other
  11  11 
Total$ $21 $11 $ $32 
Liabilities:
Energy-related derivatives$ $1 $ $ $1 
Contingent consideration3  11  14 
Other 13 11  24 
Total$3 $14 $22 $ $39 
Southern Company Gas
Assets:
Energy-related derivatives(a)
$4 $5 $ $ $9 
Non-qualified deferred compensation trusts:
Domestic equity 10   10 
Foreign equity 1   1 
Pooled funds - fixed income 6   6 
Cash and cash equivalents1    1 
Total$5 $22 $ $ $27 
Liabilities:
Energy-related derivatives(a)
$12 $8 $ $ $20 
Interest rate derivatives 59   59 
Total$12 $67 $ $ $79 
(a)Excludes cash collateral of $33 million.
(b)Excludes receivables related to investment income, pending investment sales, payables related to pending investment purchases, and currencies. See Note 6 under "Nuclear Decommissioning" for additional information.
II-231

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

At December 31, 2024, assets and liabilities measured at fair value on a recurring basis during the period, together with their associated level of the fair value hierarchy, were as follows:
Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets
Significant
Other
Observable
Inputs
Significant
Unobservable
Inputs
Net Asset
Value as a
Practical
Expedient
At December 31, 2024:(Level 1)(Level 2)(Level 3)(NAV)Total
(in millions)
Southern Company
Assets:
Energy-related derivatives(a)
$12 $77 $ $— $89 
Investments in trusts:(b)
Domestic equity849 250  — 1,099 
Foreign equity148 175  — 323 
U.S. Treasury and government agency securities 371  — 371 
Municipal bonds 47  — 47 
Pooled funds – fixed income 7  — 7 
Corporate bonds 452  — 452 
Mortgage- and asset-backed securities
 106  — 106 
Private equity   181 181 
Cash and cash equivalents1   — 1 
Other39 3  9 51 
Investment, available for sale:
U.S. Treasury and government agency securities
2 7  — 9 
Corporate bonds
1 2  — 3 
Mortgage- and asset-backed securities
 10  — 10 
Cash equivalents and restricted cash
533 19  — 552 
Other investments9 31 8 — 48 
Total$1,594 $1,557 $8 $190 $3,349 
Liabilities:
Energy-related derivatives(a)
$5 $124 $ $— $129 
Interest rate derivatives 269  — 269 
Foreign currency derivatives 218  — 218 
Contingent consideration3  16 — 19 
Other 13 11 — 24 
Total$8 $624 $27 $— $659 
II-232

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets
Significant
Other
Observable
Inputs
Significant
Unobservable
Inputs
Net Asset
Value as a
Practical
Expedient
At December 31, 2024:(Level 1)(Level 2)(Level 3)(NAV)Total
(in millions)
Alabama Power
Assets:
Energy-related derivatives
$ $26 $ $— $26 
Nuclear decommissioning trusts:(b)
Domestic equity459 241  — 700 
Foreign equity148   — 148 
U.S. Treasury and government agency securities 16  — 16 
Municipal bonds 1  — 1 
Corporate bonds 287  — 287 
Mortgage- and asset-backed securities
 31  — 31 
Private equity    181 181 
Other11 1  9 21 
Cash equivalents and restricted cash
334 19  — 353 
Other investments 31  — 31 
Total$952 $653 $ $190 $1,795 
Liabilities:
Energy-related derivatives$ $42 $ $— $42 
Georgia Power
Assets:
Energy-related derivatives$ $19 $ $— $19 
Nuclear decommissioning trusts:(b)
Domestic equity390 1  — 391 
Foreign equity 174  — 174 
U.S. Treasury and government agency securities 355  — 355 
Municipal bonds 46  — 46 
Corporate bonds 165  — 165 
Mortgage- and asset-backed securities
 75  — 75 
Other28 2  — 30 
Cash equivalents35   — 35 
Total$453 $837 $ $— $1,290 
Liabilities:
Energy-related derivatives$ $42 $ $— $42 
Mississippi Power
Assets:
Energy-related derivatives$ $19 $ $— $19 
Liabilities:
Energy-related derivatives$ $34 $ $— $34 
II-233

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Fair Value Measurements Using
Quoted Prices
in Active
Markets for
Identical
Assets
Significant
Other
Observable
Inputs
Significant
Unobservable
Inputs
Net Asset
Value as a
Practical
Expedient
At December 31, 2024:(Level 1)(Level 2)(Level 3)(NAV)Total
(in millions)
Southern Power
Assets:
Energy-related derivatives$ $4 $ $— $4 
Cash equivalents51   — 51 
Total$51 $4 $ $— $55 
Liabilities:
Foreign currency derivatives 51  — 51 
Contingent consideration3  16 — 19 
Other 13 11 — 24 
Total$3 $64 $27 $— $94 
Southern Company Gas
Assets:
Energy-related derivatives(a)
$12 $9 $ $— $21 
Non-qualified deferred compensation trusts:
Domestic equity 8  — 8 
Foreign equity 1  — 1 
Pooled funds - fixed income 7  — 7 
Cash and cash equivalents
1   — 1 
Investments, available-for-sale:
U.S. Treasury and government agency securities
2 7  — 9 
Corporate bonds
1 2  — 3 
Mortgage- and asset-backed securities
 10  — 10 
Cash equivalents22   — 22 
Total$38 $44 $ $— $82 
Liabilities:
Energy-related derivatives(a)
$5 $6 $ $— $11 
Interest rate derivatives— 84 — — 84 
Total$5 $90 $ $— $95 
(a)Excludes cash collateral of $17 million.
(b)Excludes receivables related to investment income, pending investment sales, payables related to pending investment purchases, and currencies. See Note 6 under "Nuclear Decommissioning" for additional information.
Valuation Methodologies
The energy-related derivatives primarily consist of exchange-traded and OTC financial products for natural gas and physical power products, including, from time to time, basis swaps. These are standard products used within the energy industry and are valued using the market approach. The inputs used are mainly from observable market sources, such as forward natural gas prices, power prices, implied volatility, and overnight index swap interest rates. Interest rate derivatives are also standard OTC products that are valued using observable market data and assumptions commonly used by market participants. The fair value of interest rate derivatives reflects the net present value of expected payments and receipts under the swap agreement based on the market's expectation of future interest rates. Additional inputs to the net present value calculation may include the contract terms,
II-234

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

counterparty credit risk, and, occasionally, implied volatility of interest rate options. The fair value of cross-currency swaps reflects the net present value of expected payments and receipts under the swap agreement based on the market's expectation of future foreign currency exchange rates. Additional inputs to the net present value calculation may include the contract terms, counterparty credit risk, and discount rates. The interest rate derivatives and cross-currency swaps are categorized as Level 2 under Fair Value Measurements as these inputs are based on observable data and valuations of similar instruments. See Note 14 for additional information on how these derivatives are used.
For fair value measurements of the investments within the nuclear decommissioning trusts and the non-qualified deferred compensation trusts, external pricing vendors are designated for each asset class with each security specifically assigned a primary pricing source. For investments held within commingled funds, fair value is determined at the end of each business day through the net asset value, which is established by obtaining the underlying securities' individual prices from the primary pricing source. A market price secured from the primary source vendor is then evaluated by management in its valuation of the assets within the trusts. As a general approach, fixed income market pricing vendors gather market data (including indices and market research reports) and integrate relative credit information, observed market movements, and sector news into proprietary pricing models, pricing systems, and mathematical tools. Dealer quotes and other market information, including live trading levels and pricing analysts' judgments, are also obtained when available.
The NRC requires licensees of commissioned nuclear power reactors to establish a plan for providing reasonable assurance of funds for future decommissioning. See Note 6 under "Nuclear Decommissioning" for additional information.
Southern Company's investments, available for sale relate to a wholly-owned subsidiary that insures various risk exposures of Southern Company and its subsidiaries. Corporate and municipal bonds, government agency securities, and commercial paper are valued using pricing models maximizing the use of observable inputs for similar securities, including basing value on yields currently available on comparable securities of issues with similar credit ratings. Mortgage- and asset-backed securities are valued through an analysis of the underlying assets and a review of the documentation, including financials, the manager's valuation methodology in valuing their underlying assets, the types of assets and risks involved, and the investor's exit and termination parameters.
Southern Power has contingent payment obligations related to two of its acquisitions whereby it is primarily obligated to make generation-based payments to the seller, commencing at the commercial operation of each facility and continuing through 2026 and 2036, respectively. The obligations are primarily categorized as Level 3 under Fair Value Measurements as the fair value is determined using significant unobservable inputs for the forecasted facility's generation in MW-hours, as well as other inputs such as a fixed dollar amount per MW-hour, and a discount rate. The fair value of the obligations reflects the net present value of expected payments and any periodic change arising from forecasted generation is expected to be immaterial.
Southern Power also has payment obligations through 2040 whereby it must reimburse the transmission owners for interconnection facilities and network upgrades constructed to support connection of a Southern Power generating facility to the transmission system. The obligations are categorized as Level 2 under Fair Value Measurements as the fair value is determined using observable inputs for the contracted amounts and reimbursement period, as well as a discount rate. The fair value of the obligations reflects the net present value of expected payments.
"Other investments" primarily includes investments traded in the open market that have maturities greater than 90 days, which are categorized as Level 2 under Fair Value Measurements and are comprised of corporate bonds, bank certificates of deposit, treasury bonds, and/or agency bonds.
The fair value measurements of private market investments held in Alabama Power's nuclear decommissioning trusts that are calculated at net asset value per share (or its equivalent) as a practical expedient totaled $201 million and $190 million at December 31, 2025 and 2024, respectively. Unfunded commitments related to the private market investments totaled $83 million and $78 million at December 31, 2025 and 2024, respectively. Private market investments include high-quality private equity funds across several market sectors, funds that invest in real estate assets, and a private credit fund. Private market funds do not have redemption rights. Distributions from these funds will be received as the underlying investments in the funds are liquidated.
II-235

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

At December 31, 2025 and 2024, other financial instruments for which the carrying amount did not equal fair value were as follows:
Southern
   Company(*)
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Power
Southern
Company
   Gas(*)
(in billions)
At December 31, 2025:
Long-term debt, including securities due within one year:
Carrying amount$71.1 $12.0 $20.8 $1.8 $2.9 $9.3 
Fair value67.2 10.9 19.4 1.6 2.9 8.4 
At December 31, 2024:
Long-term debt, including securities due within one year:
Carrying amount$63.2 $11.2 $18.1 $1.7 $2.7 $8.5 
Fair value57.7 9.8 16.2 1.5 2.6 7.4 
(*)The carrying amount of Southern Company Gas' long-term debt includes fair value adjustments from the effective date of the 2016 merger with Southern Company. Southern Company Gas amortizes the fair value adjustments over the remaining lives of the respective bonds, the latest being through 2043.
The fair values are determined using Level 2 measurements and are based on quoted market prices for the same or similar issues or on the current rates available to the Registrants.
14. DERIVATIVES
The Registrants are exposed to market risks, including commodity price risk, interest rate risk, weather risk, and occasionally foreign currency exchange rate risk. To manage the volatility attributable to these exposures, each company nets its exposures, where possible, to take advantage of natural offsets and enters into various derivative transactions for the remaining exposures pursuant to each company's policies in areas such as counterparty exposure and risk management practices. Each company's policy is that derivatives are to be used primarily for hedging purposes and mandates strict adherence to all applicable risk management policies. Derivative positions are monitored using techniques including, but not limited to, market valuation, value at risk, stress testing, and sensitivity analysis. Derivative instruments are recognized at fair value in the balance sheets as either assets or liabilities and are presented on a net basis. See Note 13 for additional fair value information. In the statements of cash flows, any cash impacts of settled energy-related and interest rate derivatives are recorded as operating activities. Any cash impacts of settled foreign currency derivatives are classified as operating or financing activities to correspond with the classification of the hedged interest or principal, respectively. See Note 1 under "Financial Instruments" for additional information.
Energy-Related Derivatives
The Subsidiary Registrants enter into energy-related derivatives to hedge exposures to electricity, natural gas, and other fuel price changes. However, due to cost-based rate regulations and other various cost recovery mechanisms, the traditional electric operating companies and the natural gas distribution utilities have limited exposure to market volatility in energy-related commodity prices. Each of the traditional electric operating companies and certain of the natural gas distribution utilities manage fuel-hedging programs, implemented per the guidelines of their respective state PSCs or other applicable state regulatory agencies, through the use of financial derivative contracts, which are expected to continue to mitigate price volatility. The traditional electric operating companies (with respect to wholesale generating capacity) and Southern Power have limited exposure to market volatility in energy-related commodity prices because their long-term sales contracts shift substantially all fuel cost responsibility to the purchaser. However, the traditional electric operating companies and Southern Power may be exposed to market volatility in energy-related commodity prices to the extent any uncontracted capacity is used to sell electricity. Southern Company Gas retains exposure to price changes that can, in a volatile energy market, be material and can adversely affect its results of operations.
Southern Company Gas also enters into weather derivative contracts as economic hedges in the event of warmer-than-normal weather. Exchange-traded options are carried at fair value, with changes reflected in natural gas revenues. Non-exchange-traded options are accounted for using the intrinsic value method. Changes in the intrinsic value for non-exchange-traded contracts are reflected in natural gas revenues.
II-236

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Energy-related derivative contracts are accounted for under one of three methods:
Regulatory Hedges – Energy-related derivative contracts designated as regulatory hedges relate primarily to the traditional electric operating companies' and the natural gas distribution utilities' fuel-hedging programs, where gains and losses are initially recorded as regulatory liabilities and assets, respectively, and then are included in fuel expense as the underlying fuel is used in operations and ultimately recovered through an approved cost recovery mechanism.
Cash Flow Hedges – Gains and losses on energy-related derivatives designated as cash flow hedges (which are mainly used to hedge anticipated purchases and sales) are initially deferred in AOCI before being recognized in the statements of income in the same period and in the same income statement line item as the earnings effect of the hedged transactions.
Not Designated – Gains and losses on energy-related derivative contracts that are not designated or fail to qualify as hedges are recognized in the statements of income as incurred.
Some energy-related derivative contracts require physical delivery as opposed to financial settlement, and this type of derivative is both common and prevalent within the electric and natural gas industries. When an energy-related derivative contract is settled physically, any cumulative unrealized gain or loss is reversed and the contract price is recognized in the respective line item representing the actual price of the underlying goods being delivered.
At December 31, 2025, the net volume of energy-related derivative contracts for natural gas positions, together with the longest hedge date over which the respective entity is hedging its exposure to the variability in future cash flows for forecasted transactions and the longest non-hedge date for derivatives not designated as hedges, were as follows:
Net
Purchased
mmBtu
Longest
Hedge
Date
Longest
Non-Hedge
Date
(in millions)
Southern Company(*)
43120302029
Alabama Power1262028
Georgia Power1282028
Mississippi Power1062030
Southern Power820302026
Southern Company Gas(*)
6320282029
(*)Southern Company Gas' derivative instruments include both long and short natural gas positions. A long position is a contract to purchase natural gas and a short position is a contract to sell natural gas. Southern Company Gas' volume represents the net of long natural gas positions of 72 million mmBtu and short natural gas positions of 9 million mmBtu at December 31, 2025, which is also included in Southern Company's total volume.
In addition to the volumes discussed above, the traditional electric operating companies and Southern Power enter into physical natural gas supply contracts that provide the option to sell back excess natural gas due to operational constraints. The maximum expected volume of natural gas subject to such a feature is 15 million mmBtu for Southern Company, which includes 4 million mmBtu for Alabama Power, 6 million mmBtu for Georgia Power, 2 million mmBtu for Mississippi Power, and 3 million mmBtu for Southern Power.
For cash flow hedges of energy-related derivatives, the estimated pre-tax gains (losses) expected to be reclassified from AOCI to earnings for the year ending December 31, 2026 are immaterial for Southern Company, Southern Power, and Southern Company Gas.
Interest Rate Derivatives
Southern Company and certain subsidiaries may enter into interest rate derivatives to hedge exposure to changes in interest rates. Derivatives related to existing variable rate securities or forecasted transactions are accounted for as cash flow hedges where the derivatives' fair value gains or losses are recorded in OCI and are reclassified into earnings at the same time and presented on the same income statement line item as the earnings effect of the hedged transactions. Derivatives related to existing fixed rate securities are accounted for as fair value hedges, where the derivatives' fair value gains or losses and hedged items' fair value gains or losses are both recorded directly to earnings on the same income statement line item. Fair value gains or losses on derivatives that are not designated or fail to qualify as hedges are recognized in the statements of income as incurred.
II-237

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

At December 31, 2025, the following interest rate derivatives were outstanding:
Notional
Amount
Weighted Average
Interest Rate Paid
Interest
Rate
Received
Hedge
Maturity
Date
Fair Value
Gain (Loss) at
December 31, 2025
(in millions)(in millions)
Fair Value Hedges of Existing Debt
Southern Company parent$400 
1-day SOFR + 0.80%
1.75%March 2028$(24)
Southern Company parent1,000 
1-day SOFR + 2.48%
3.70%April 2030(95)
Southern Company parent565 
1-day SOFR + 1.56%
6.50%March 2045(1)
Southern Company Gas500 
1-day SOFR + 0.49%
1.75%January 2031(59)
Southern Company$2,465 $(179)
For cash flow hedges of interest rate derivatives, the estimated pre-tax gains (losses) expected to be reclassified from AOCI to interest expense for the year ending December 31, 2026 are immaterial for Southern Company, the traditional electric operating companies, and Southern Company Gas. Deferred gains and losses related to interest rate derivatives are expected to be amortized into earnings through 2054 for Southern Company, Georgia Power, and Mississippi Power, 2052 for Alabama Power, and 2046 for Southern Company Gas.
Foreign Currency Derivatives
Southern Company and certain subsidiaries, including Southern Power, may enter into foreign currency derivatives to hedge exposure to changes in foreign currency exchange rates, such as that arising from the issuance of debt denominated in a currency other than U.S. dollars. Derivatives related to forecasted transactions are accounted for as cash flow hedges where the derivatives' fair value gains or losses are recorded in OCI and are reclassified into earnings at the same time and on the same income statement line as the earnings effect of the hedged transactions, including foreign currency gains or losses arising from changes in the U.S. currency exchange rates. Derivatives related to existing fixed rate securities are accounted for as fair value hedges, where the derivatives' fair value gains or losses and hedged items' fair value gains or losses are both recorded directly to earnings on the same income statement line item, including foreign currency gains or losses arising from changes in the U.S. currency exchange rates. Southern Company has elected to exclude the cross-currency basis spread from the assessment of effectiveness in the fair value hedges of its foreign currency risk and record any difference between the change in the fair value of the excluded components and the amounts recognized in earnings as a component of OCI.
At December 31, 2025, the following foreign currency derivatives were outstanding:
Pay
Notional
Pay Rate
Receive
Notional
Receive
Rate
Hedge
Maturity Date
Fair Value
Gain (Loss) at
December 31, 2025
(in millions)(in millions)(in millions)
Cash Flow Hedges of Existing Debt
Southern Power$564 3.78%500 1.85%June 2026$17 
Fair Value Hedges of Existing Debt
Southern Company parent1,476 3.39%1,250 1.88%September 2027(18)
Southern Company$2,040 1,750 $(1)
For cash flow hedges of foreign currency derivatives, the estimated pre-tax gains expected to be reclassified from AOCI to earnings for the year ending December 31, 2026 are $17 million for Southern Power.
Derivative Financial Statement Presentation and Amounts
The Registrants enter into derivative contracts that may contain certain provisions that permit intra-contract netting of derivative receivables and payables for routine billing and offsets related to events of default and settlements. Southern Company and certain subsidiaries also utilize master netting agreements to mitigate exposure to counterparty credit risk. The fair value amounts of derivative assets and liabilities on the balance sheets are presented net to the extent that there are netting arrangements or similar agreements with the counterparties.
II-238

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

The fair value of energy-related derivatives, interest rate derivatives, and foreign currency derivatives was reflected as either assets or liabilities in the balance sheets (included in "Other" or shown separately as "Risk Management Activities") as follows:
At December 31, 2025At December 31, 2024
Derivative Category and Balance Sheet LocationAssetsLiabilitiesAssetsLiabilities
(in millions)
Southern Company
Energy-related derivatives designated as hedging instruments for regulatory purposes
Current
$24 $64 $33 $82 
Non-current
31 35 42 40 
Total derivatives designated as hedging instruments for regulatory purposes55 99 75 122 
Derivatives designated as hedging instruments in cash flow and fair value hedges
Energy-related derivatives:
Current
1 6 4 3 
Non-current
2 1 4  
Interest rate derivatives:
Current
8 48  61 
Non-current
 139  208 
Foreign currency derivatives:
Current
17 22  36 
Non-current
4   182 
Total derivatives designated as hedging instruments in cash flow and fair value hedges32 216 8 490 
Energy-related derivatives not designated as hedging instruments
Current
6 6 5 3 
Non-current
  1  
Total derivatives not designated as hedging instruments6 6 6 3 
Gross amounts recognized 93 321 89 615 
Gross amounts offset(a)
(21)(54)(44)(61)
Net amounts recognized in the Balance Sheets(b)
$72 $267 $45 $554 
Alabama Power
Energy-related derivatives designated as hedging instruments for regulatory purposes
Current
$9 $18 $11 $30 
Non-current
10 13 15 12 
Total derivatives designated as hedging instruments for regulatory purposes19 31 26 42 
Gross amounts offset(13)(13)(19)(19)
Net amounts recognized in the Balance Sheets$6 $18 $7 $23 
II-239

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

At December 31, 2025At December 31, 2024
Derivative Category and Balance Sheet LocationAssetsLiabilitiesAssetsLiabilities
(in millions)
Georgia Power
Energy-related derivatives designated as hedging instruments for regulatory purposes
Current
$7 $23 $6 $32 
Non-current
10 10 13 9 
Total derivatives designated as hedging instruments for regulatory purposes17 33 19 41 
Energy-related derivatives not designated as hedging instruments
Current
1   1 
Gross amounts recognized18 33 19 42 
Gross amounts offset(14)(14)(15)(15)
Net amounts recognized in the Balance Sheets$4 $19 $4 $27 
Mississippi Power
Energy-related derivatives designated as hedging instruments for regulatory purposes
Current
$3 $15 $5 $15 
Non-current
11 12 14 19 
Total derivatives designated as hedging instruments for regulatory purposes14 27 19 34 
Gross amounts offset(13)(13)(17)(17)
Net amounts recognized in the Balance Sheets$1 $14 $2 $17 
Southern Power
Derivatives designated as hedging instruments in cash flow hedges
Energy-related derivatives:
Current
$1 $1 $1 $ 
Non-current
2  3  
Foreign currency derivatives:
Current
17   11 
Non-current
   40 
Total derivatives designated as hedging instruments in cash flow hedges
20 1 4 51 
Energy-related derivatives not designated as hedging instruments
Current
1    
Net amounts recognized in the Balance Sheets$21 $1 $4 $51 
II-240

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

At December 31, 2025At December 31, 2024
Derivative Category and Balance Sheet LocationAssetsLiabilitiesAssetsLiabilities
(in millions)
Southern Company Gas
Energy-related derivatives designated as hedging instruments for regulatory purposes
Current
$5 $8 $11 $5 
Derivatives designated as hedging instruments in cash flow and fair value hedges
Energy-related derivatives:
Current
 5 3 3 
Non-current
 1 1  
Interest rate derivatives:
Current
 13  17 
Non-current
 46  67 
Total derivatives designated as hedging instruments in cash flow and fair value hedges 65 4 87 
Energy-related derivatives not designated as hedging instruments
Current
4 6 5 2 
Non-current
  1  
Total derivatives not designated as hedging instruments4 6 6 2 
Gross amounts recognized9 79 21 94 
Gross amounts offset(a)
19 (14)7 (10)
Net amounts recognized in the Balance Sheets(b)
$28 $65 $28 $84 
(a)Gross amounts offset includes cash collateral held on deposit in broker margin accounts of $33 million and $17 million at December 31, 2025 and 2024, respectively.
(b)Net amounts of derivative instruments outstanding exclude immaterial premium and intrinsic value associated with weather derivatives at December 31, 2025 and 2024.
II-241

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

At December 31, 2025 and 2024, the pre-tax effects of unrealized derivative gains (losses) arising from energy-related derivative instruments designated as regulatory hedging instruments and deferred were as follows:
Regulatory Hedge Unrealized Gain (Loss) Recognized in the Balance Sheets
Derivative Category and Balance Sheet
Location
Southern
Company
Alabama
Power
Georgia
Power
Mississippi
Power
Southern
Company
Gas
 (in millions)
At December 31, 2025:
Energy-related derivatives:
Other regulatory assets, current$(48)$(13)$(17)$(12)$(6)
Other regulatory assets, deferred(8)(5)(1)(2) 
Other regulatory liabilities, current7 4 1  2 
Other regulatory liabilities, deferred4 2 1 1  
Total energy-related derivative gains (losses)$(45)$(12)$(16)$(13)$(4)
At December 31, 2024:
Energy-related derivatives:
Other regulatory assets, current$(61)$(23)$(26)$(11)$(1)
Other regulatory assets, deferred(5)  (5) 
Other regulatory liabilities, current8 4   4 
Other regulatory liabilities, deferred8 3 4 1  
Total energy-related derivative gains (losses)$(50)$(16)$(22)$(15)$3 
II-242

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

For the years ended December 31, 2025, 2024, and 2023, the pre-tax effects of cash flow and fair value hedge accounting on AOCI for the applicable Registrants were as follows:
Gain (Loss) From Derivatives Recognized in OCI202520242023
(in millions)
Southern Company
Cash flow hedges:
Energy-related derivatives$(8)$(7)$(81)
Interest rate derivatives6 23 (12)
Foreign currency derivatives58 (40)14 
Fair value hedges(*):
Foreign currency derivatives(22)16 21 
Total$34 $(8)$(58)
Georgia Power
Cash flow hedges:
Interest rate derivatives$4 $24 $(2)
Mississippi Power
Cash flow hedges:
Interest rate derivatives$(1)$7 $ 
Southern Power
Cash flow hedges:
Energy-related derivatives$(1)$(1)$(18)
Foreign currency derivatives58 (40)14 
Total$57 $(41)$(4)
Southern Company Gas
Cash flow hedges:
Energy-related derivatives$(6)$(6)$(63)
Interest rate derivatives2 (5) 
Total$(4)$(11)$(63)
(*)Represents amounts excluded from the assessment of effectiveness for which the difference between changes in fair value and periodic amortization is recorded in OCI.
II-243

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

The pre-tax effects of cash flow and fair value hedge accounting on income for the years ended December 31, 2025, 2024, and 2023 were as follows:
Gain (Loss)
Statements of Income Location
Derivative Category
202520242023
(in millions)
Southern Company
Fuel
Energy-related cash flow hedges
$1 $(6)$(23)
Cost of natural gas
Energy-related cash flow hedges
(3)(40)(44)
Other operations and maintenance
Energy-related cash flow hedges
 (2)(2)
Interest expense, net of amounts capitalized
Interest rate cash flow hedges
(13)(16)(35)
Foreign currency cash flow hedges
(10)(12)(11)
Interest rate fair value hedges
90 (4)37 
Other income (expense), net
Foreign currency cash flow hedges
68 (33)19 
Foreign currency fair value hedges
149 2 69 
Amount excluded from effectiveness testing recognized in earnings
22 (16)(21)
Southern Power
Fuel
Energy-related cash flow hedges
$1 $(6)$(23)
Interest expense, net of amounts capitalized
Foreign currency cash flow hedges
(10)(12)(11)
Other income (expense), net
Foreign currency cash flow hedges
68 (33)19 
Southern Company Gas
Cost of natural gas
Energy-related cash flow hedges
$(3)$(40)$(44)
Other operations and maintenance
Energy-related cash flow hedges
 (2)(2)
Interest expense, net of amounts capitalized
Interest rate cash flow hedges
(1)(1)(19)
Interest rate fair value hedges
25 (5)6 
At December 31, 2025 and 2024, the following amounts were recorded on the balance sheets related to cumulative basis adjustments for fair value hedges:
Carrying Amount of
the Hedged Item
Cumulative Amount of Fair Value
Hedging Adjustment included in
Carrying Amount of the Hedged Item
Balance Sheet Location of Hedged ItemsAt December 31, 2025At December 31, 2024At December 31, 2025At December 31, 2024
(in millions)(in millions)
Southern Company
Long-term debt$(3,742)$(2,936)$156 $242 
Southern Company Gas
Long-term debt$(446)$(422)$51 $75 
Pre-tax gains (losses) on energy-related derivatives not designated as hedging instruments were $(11) million, $94 million, and $59 million for the years ended December 31, 2025, 2024, and 2023, respectively, and reflected in cost of natural gas on the statements of income of Southern Company and Southern Company Gas.
Contingent Features
The Registrants do not have any credit arrangements that would require material changes in payment schedules or terminations as a result of a credit rating downgrade. There are certain derivatives that could require collateral, but not accelerated payment, in the event of various credit rating changes of certain Southern Company subsidiaries. Generally, collateral may be provided by a Southern Company guaranty, letter of credit, or cash. At December 31, 2025, the Registrants had no collateral posted with derivative counterparties to satisfy these arrangements.
II-244

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

For Southern Company, the fair value of foreign currency derivative liabilities and interest rate derivative liabilities with contingent features, and the maximum potential collateral requirements arising from the credit-risk-related contingent features at a rating below BBB- and/or Baa3, was $20 million at December 31, 2025. For Southern Power, there were no foreign currency derivative liabilities with contingent features or associated collateral requirements arising from the credit-risk-related contingent features at a rating below BBB- and/or Baa3 at December 31, 2025. For the traditional electric operating companies and Southern Power, energy-related derivative liabilities with contingent features and the maximum potential collateral requirements arising from the credit-risk-related contingent features, at a rating below BBB- and/or Baa3, were immaterial at December 31, 2025. The maximum potential collateral requirements arising from the credit-risk-related contingent features for the traditional electric operating companies and Southern Power include certain agreements that could require collateral in the event that one or more Southern Company power pool participants has a credit rating change to below investment grade.
Alabama Power and Southern Power maintain accounts with certain regional transmission organizations to facilitate financial derivative transactions, and they may be required to post collateral based on the value of the positions in these accounts and the associated margin requirements. At December 31, 2025, cash collateral posted in these accounts was immaterial for Alabama Power and Southern Power. Southern Company Gas maintains accounts with brokers or the clearing houses of certain exchanges to facilitate financial derivative transactions. Based on the value of the positions in these accounts and the associated margin requirements, Southern Company Gas may be required to deposit cash into these accounts, which are netted with energy-related derivatives recognized in the balance sheets.
The Registrants are exposed to losses related to financial instruments in the event of counterparties' nonperformance. The Registrants generally enter into agreements and material transactions with counterparties that have investment grade credit ratings by Moody's, S&P, or Fitch or with counterparties who have posted collateral to cover potential credit exposure. The Registrants have also established risk management policies and controls to determine and monitor the creditworthiness of counterparties in order to mitigate their exposure to counterparty credit risk.
Southern Company Gas uses established credit policies to determine and monitor the creditworthiness of counterparties, including requirements to post collateral or other credit security, as well as the quality of pledged collateral. Collateral or credit security is most often in the form of cash or letters of credit from an investment-grade financial institution, but may also include cash or U.S. government securities held by a trustee. Prior to entering a physical transaction, Southern Company Gas assigns its counterparties an internal credit rating and credit limit based on the counterparties' Moody's, S&P, and Fitch ratings, commercially available credit reports, and audited financial statements. Southern Company Gas may require counterparties to pledge additional collateral when deemed necessary.
The Registrants do not anticipate a material adverse effect on their respective financial statements as a result of counterparty nonperformance.
15. ACQUISITIONS AND DISPOSITIONS
Alabama Power
On September 30, 2025, Alabama Power completed its acquisition of Tenaska Alabama Partners, L.P., which owned and operated the Lindsay Hill Generating Station, an approximately 879.7-MW combined cycle generation facility in Autauga County, Alabama. The transaction was accounted for as a business combination. The total purchase price was $635 million, of which $622 million was related to net assets recorded within property, plant, and equipment and the remainder was included in inventory, current receivables, and accounts payable on the balance sheet. The transaction was recorded as a business acquisition within the investing section of the statement of cash flows. Alabama Power assumed an existing power sales agreement under which the full output of the generating facility remains committed to a non-affiliated third party through April 2027. See Note 2 under "Alabama Power – Rate CNP New Plant" for additional information.
Mississippi Power
On July 30, 2025, Mississippi Power completed the acquisition of FP&L's 50% ownership interest in Plant Daniel Units 1 and 2 and, as part of the acquisition, received approximately $36 million from FP&L. See Note 2 under "Mississippi Power – Plant Daniel" for additional information.
Southern Power
Southern Power's acquisition-related costs for the projects discussed under "Asset Acquisitions" and "Construction Projects" were not material for any of the years presented.
II-245

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Asset Acquisitions
During 2023, Southern Power acquired the Millers Branch and South Cheyenne projects, as discussed further under "Construction Projects" below, with an aggregate purchase price of $193 million. There were no asset acquisitions during 2024 and 2025.
Construction Projects
During 2024, Southern Power completed construction of and placed in service the 150-MW South Cheyenne solar facility. During 2025, Southern Power continued construction of the three phases of the 512-MW Millers Branch solar facility. At December 31, 2025, the total cost of construction incurred for the Millers Branch project was $694 million, which is primarily included in CWIP. The ultimate outcome of these matters cannot be determined at this time.
Project
Facility
Resource
Approximate Nameplate Capacity (MW)
Location
Actual/Projected COD
PPA Contract Period
Projects Under Construction at December 31, 2025
Millers Branch
Phase ISolar200Haskell County, TX
   February 2026(*)
20 years
Phase II
Solar
180Haskell County, TX
Second quarter 2026
15 years
Phase III
Solar
132Haskell County, TX
Fourth quarter 2026
15 years
Projects Completed During 2024
South Cheyenne
Solar
150
Laramie County, WY
April 2024
20 years
(*)Subsequent to December 31, 2025, Southern Power completed construction of the 200-MW first phase of the Millers Branch solar facility.
Wind Repowering Projects
During 2025, Southern Power continued the development project to repower the Kay wind facility and began development projects to repower the Grant Plains, Grant, Wake, and Bethel wind facilities. At December 31, 2025, the total cost of construction incurred related to the projects was $358 million and is included in CWIP. The repowered output of the facilities is contracted under new and amended PPAs. The ultimate outcome of these matters cannot be determined at this time.
Project Facility
Resource
Approximate Nameplate Capacity
(MW)
Location
Projected COD
Projects Under Construction at December 31, 2025
Kay(*)
Wind
200
Kay County, OK
Third quarter 2026
Grant Plains
Wind
147
Grant County, OK
Fourth quarter 2026
Grant
Wind
152Grant County, OKFourth quarter 2026
Wake
Wind
257
Crosby & Floyd Counties, TX
Second quarter 2027
Bethel
Wind
276
Castro County, TX
Third quarter 2027
(*)The facility has a total capacity of 299 MWs, of which 200 MWs is projected to be repowered and is contracted under a PPA.
Purchase of Renewable Facility Interests
On December 31, 2025, Southern Power completed the purchase of 100% of the noncontrolling Class A membership interests in SP Wind from the three financial investors for approximately $282 million. Since Southern Power retains control of SP Wind, the purchase was accounted for as an equity transaction, and Southern Power will continue to consolidate SP Wind in its financial statements. On the date of the transaction, noncontrolling interest was reduced by $242 million. The difference in the purchase price and the carrying value of the noncontrolling interest resulted in a $36 million non-cash decrease to Southern Power's common stockholders' equity, net of deferred tax remeasurement. See Note 7 under "Southern Power – Variable Interest Entities – SP Wind" for additional information.
16. SEGMENT AND RELATED INFORMATION
The Registrants adopted ASU 2023-07 and applied the guidance retrospectively effective for the fiscal year beginning January 1, 2024. See Note 1 under "Recently Adopted Accounting Standards" for additional information.
The CODM at Southern Company, the traditional electric operating companies, and Southern Company Gas is the chairman, president, and chief executive officer of such Registrant. Southern Power's CODM consists of the chairman and chief executive officer and the president. The CODMs assess segment performance using net income that is reflected on the Registrants'
II-246

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

respective statements of income as net income attributable to the registrant or net income, as applicable. The CODMs use net income in the annual budget and forecasting process and consider budget versus actual results on a monthly basis when making decisions about the allocation of resources. Asset information by segment is not utilized by the CODMs for purposes of assessing performance or allocating resources.
Southern Company
Southern Company's reportable business segments are the sale of electricity by the traditional electric operating companies, the sale of electricity in the competitive wholesale market by Southern Power, and the distribution of natural gas and other complementary products and services by Southern Company Gas. While the traditional electric operating companies represent three separate operating segments, they are vertically integrated utilities providing electric service to retail customers, as well as wholesale customers, in the Southeast and have been aggregated into one reportable segment. The "All Other" presentation includes the Southern Company parent entity, which does not allocate operating expenses to business segments, and operating segments below the quantitative threshold for separate disclosure. These operating segments include providing distributed energy and resilience solutions and deploying microgrids for commercial, industrial, governmental, and utility customers, as well as investments in telecommunications. Revenues from sales by Southern Power to the traditional electric operating companies were $437 million, $371 million, and $537 million in 2025, 2024, and 2023, respectively. All other inter-segment revenues were immaterial for all periods presented.
Southern Company's CODM utilizes segment net income, including variances to budget and forecasts, to assess performance and is not provided with segment expense information. To achieve the consolidated net income goal, Southern Company's CODM sets net income expectations for each operating segment, which is expected to monitor its expenses in order to achieve its assigned net income target. Therefore, Southern Company has no reportable significant segment expenses.
Financial data for business segments and products and services for the years ended December 31, 2025, 2024, and 2023 was as follows:
Electric Utilities
Traditional
Electric
Operating
Companies
Southern
Power
EliminationsTotal
Southern
Company
Gas
Total
Reportable
Segments
All
Other
EliminationsConsolidated
(in millions)
2025
Operating revenues$22,056 $2,198 $(477)$23,777 $5,044 $28,821 $893 $(161)$29,553 
Other segment items(a)(b)(c)
11,157 1,187 (477)11,867 3,172 15,039 872 (154)15,757 
Depreciation and amortization(d)
3,882 843  4,725 708 5,433 68  5,501 
Earnings from equity method investments6   6 127 133 (21) 112 
Interest expense(e)
1,341 104  1,445 377 1,822 1,416  3,238 
Income taxes (benefit)1,100 (61) 1,039 182 1,221 (393) 828 
Segment net income (loss)(b)(c)(d)(e)(f)
$4,582 $125 $ $4,707 $732 $5,439 $(1,091)$(7)$4,341 
At December 31, 2025
Goodwill$ $2 $ $2 $5,015 $5,017 $144 $ $5,161 
Total assets114,287 12,657 (915)126,029 27,387 153,416 2,829 (525)155,720 
II-247

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Electric Utilities
Traditional
Electric
Operating
Companies
Southern
Power
EliminationsTotal
Southern
Company
Gas
Total
Reportable
Segments
All
Other
EliminationsConsolidated
(in millions)
2024
Operating revenues$19,977 $2,014 $(388)$21,603 $4,456 $26,059 $843 $(178)$26,724 
Other segment items(a)(b)(g)(h)
10,057 1,060 (388)10,729 2,613 13,342 802 (149)13,995 
Depreciation and amortization(d)
3,512 522  4,034 650 4,684 71  4,755 
Earnings from equity method investments8   8 146 154 (17)2 139 
Interest expense1,255 117  1,372 341 1,713 1,030  2,743 
Income taxes (benefit)1,016 (13) 1,003 258 1,261 (292) 969 
Segment net income (loss)(b)(d)(f)(g)(h)
$4,145 $328 $ $4,473 $740 $5,213 $(785)$(27)$4,401 
At December 31, 2024
Goodwill$ $2 $ $2 $5,015 $5,017 $144 $ $5,161 
Total assets105,577 12,653 (1,025)117,205 26,177 143,382 2,371 (573)145,180 
2023
Operating revenues$18,358 $2,189 $(549)$19,998 $4,702 $24,700 $718 $(165)$25,253 
Other segment items(a)(b)(c)(i)
9,643 1,187 (549)10,281 3,124 13,405 699 (150)13,954 
Depreciation and amortization3,361 504  3,865 582 4,447 78  4,525 
Earnings from equity method investments(1)  (1)140 139 5  144 
Interest expense1,145 129  1,274 310 1,584 879 (17)2,446 
Income taxes (benefit)571 12  583 211 794 (298) 496 
Segment net income (loss)(b)(c)(f)(i)
$3,637 $357 $ $3,994 $615 $4,609 $(635)$2 $3,976 
At December 31, 2023
Goodwill$ $2 $ $2 $5,015 $5,017 $144 $ $5,161 
Total assets100,429 12,761 (545)112,645 25,083 137,728 2,446 (843)139,331 
(a)Primarily consists of fuel, purchased power, cost of natural gas, cost of other sales, other operations and maintenance (including credits to income for estimated probable losses, regulatory disallowances, losses (gains) on asset dispositions, and impairment charges), taxes other than income taxes, AFUDC equity, non-service cost-related retirement benefits income, and net income (loss) attributable to noncontrolling interests.
(b)For the traditional electric operating companies, includes pre-tax credits to income at Georgia Power for the estimated probable loss associated with the construction and completion of Plant Vogtle Units 3 and 4 of $60 million ($45 million after tax) in 2025, $21 million ($16 million after tax) in 2024, and $68 million ($50 million after tax) in 2023. See Note 2 under "Georgia Power – Nuclear Construction" for additional information.
(c)For Southern Company Gas, includes pre-tax charges associated with the disallowance of certain capital investments at Nicor Gas totaling approximately $63 million ($47 million after tax) in 2025 and $96 million ($72 million after tax) in 2023. See Note 2 under "Southern Company Gas" for additional information.
(d)For Southern Power, includes accelerated depreciation related to the repowering of multiple wind facilities of $307 million ($221 million after tax, net of noncontrolling interest impacts) in 2025 and $9 million ($7 million after tax, net of noncontrolling interest impacts) in 2024. See Note 15 under "Southern Power –Wind Repowering Projects" for additional information.
(e)For All Other, includes a pre-tax loss of $252 million ($189 million after tax) associated with the extinguishment of debt at the parent company. See Note 8 under "Convertible Senior Notes" for additional information.
(f)Attributable to Southern Company.
(g)For the traditional electric operating companies, includes a pre-tax impairment loss at Alabama Power of $36 million ($27 million after tax) related to Alabama Power discontinuing the development of a multi-use commercial facility. See Note 1 under "Impairment of Long-Lived Assets" for additional information.
(h)For the traditional electric operating companies, includes a pre-tax gain at Georgia power of approximately $114 million ($84 million after tax) related to the sale of transmission line assets under the integrated transmission system agreement. See Note 2 under "Georgia Power – Transmission Asset Sales" for additional information.
(i)For Southern Power, includes an $18 million pre-tax loss recovery ($9 million after tax and partnership allocations) related to an arbitration award and a $16 million pre-tax gain ($12 million after tax) on the sale of spare parts.
II-248

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Products and Services
Electric Utilities' Revenues
YearRetailWholesaleOtherTotal
(in millions)
2025$19,331 $2,940 $1,506 $23,777 
202417,790 2,431 1,382 21,603 
202316,343 2,467 1,188 19,998 
Southern Company Gas' Revenues
YearGas
Distribution
Operations
Gas
Marketing
Services
Other
Total
(in millions)
2025$4,428 $582 $34 $5,044 
20243,899 516 41 4,456 
20234,090 548 64 4,702 
Traditional Electric Operating Companies
Each of the traditional electric operating companies' single reportable business segment is the sale of electricity. Revenues from products and services of the traditional electric operating companies are segregated into retail, wholesale, and other as reflected on their statements of income.
Alabama Power and Georgia Power have identified utility operations and maintenance expenses as significant segment expenses provided to their CODMs. Utility operations and maintenance expenses is calculated as other operations and maintenance, as reflected on the statements of income, less expenses from unregulated products and services, losses (gains) on asset dispositions, impairment charges, amortization of cloud software, and, for Georgia Power, charges (credits) for estimated loss on Plant Vogtle Units 3 and 4. Alabama Power's utility operations and maintenance expenses are disaggregated into expenses related to Rate RSE and Rate CNP Compliance. See Note 2 under "Alabama Power" for additional information.
During the third and fourth quarters of 2025, Mississippi Power updated the information provided to its CODM. As a result, Mississippi Power has identified certain operational and environmental compliance expenses as significant segment expenses and has recast prior period information to conform to the current period presentation.
Financial data for significant segment expenses and other segment information for the years ended December 31, 2025, 2024, and 2023 was as follows:
202520242023
(in millions)
Alabama Power
Operating revenues$8,235 $7,554 $7,050 
Utility operations and maintenance
Rate RSE expenses1,636 1,480 1,421 
Rate CNP Compliance expenses292 279 254 
Total utility operations and maintenance1,928 1,759 1,675 
Other segment items(a)(b)
2,391 2,125 2,098 
Depreciation and amortization1,510 1,459 1,401 
Interest expense465 448 425 
Income taxes425 360 81 
Segment net income(b)
$1,516 $1,403 $1,370 
Capital expenditures$2,508 $2,114 $2,159 
II-249

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

202520242023
(in millions)
Georgia Power
Operating revenues$12,631 $11,331 $10,118 
Utility operations and maintenance2,339 2,210 1,901 
Other segment items(a)(c)(d)
3,972 3,476 3,382 
Depreciation and amortization2,074 1,774 1,681 
Interest expense793 725 626 
Income taxes602 603 448 
Segment net income(c)(d)
$2,851 $2,543 $2,080 
Capital expenditures$8,140 $5,355 $5,394 
Mississippi Power
Operating revenues$1,695 $1,463 $1,474 
Operational expenses(e)
264 254 265 
Environmental compliance expenses(f)
16 12 10 
Other segment items(a)
845 681 714 
Depreciation and amortization211 193 190 
Interest expense79 77 71 
Income taxes65 47 36 
Segment net income
$215 $199 $188 
Capital expenditures$320 $357 $342 
(a)Primarily consists of fuel, purchased power, expenses from unregulated products and services, losses (gains) on asset dispositions, amortization of cloud software, taxes other than income taxes, AFUDC equity, and non-service cost-related retirement benefits income. For Alabama Power, includes impairment charges. For Georgia Power, includes credits for estimated loss on Plant Vogtle Units 3 and 4. For Mississippi Power, includes employee benefit expenses. Also includes earnings from equity method investments, which were immaterial for all periods presented.
(b)For 2024, includes a pre-tax impairment loss of $36 million ($27 million after tax) related to Alabama Power discontinuing the development of a multi-use commercial facility. See Note 1 under "Impairment of Long-Lived Assets" for additional information.
(c)Includes pre-tax credits to income for the estimated probable loss associated with the construction and completion of Plant Vogtle Units 3 and 4 of $60 million ($45 million after tax) in 2025, $21 million ($16 million after tax) in 2024, and $68 million ($50 million after tax) in 2023. See Note 2 under "Georgia Power – Nuclear Construction" for additional information.
(d)For 2024, includes a pre-tax gain of approximately $114 million ($84 million after tax) related to the sale of transmission line assets under the integrated transmission system agreement. See Note 2 under "Georgia Power – Transmission Asset Sales" for additional information.
(e)Consists of certain operations and maintenance expenses related to PEP and the MRA tariff, including labor costs, materials, contract services, and other normal operational costs. See Note 2 under "Mississippi Power" for additional information regarding PEP and the MRA tariff.
(f)Consists of environmental compliance expenses related to ECO Plan and the MRA tariff. See Note 2 under "Mississippi Power" for additional information regarding ECO Plan and the MRA tariff.
Southern Power
Southern Power's single reportable business segment is the sale of electricity in the competitive wholesale market. Substantially all of Southern Power's revenues from products and services are reflected as wholesale on its consolidated statements of income. Southern Power's CODM utilizes segment expense information in the form of variances to budget to assess performance; therefore, Southern Power has no reportable significant segment expenses.
II-250

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Financial data for segment information for the years ended December 31, 2025, 2024, and 2023 was as follows:
202520242023
(in millions)
Operating revenues
$2,198 $2,014 $2,189 
Other segment items(a)(b)
1,187 1,060 1,187 
Depreciation and amortization(c)
843 522 504 
Interest expense
104 117 129 
Income taxes (benefit)(61)(13)12 
Segment net income(b)(c)(d)
$125 $328 $357 
(a)Primarily consists of fuel, purchased power, other operations and maintenance, taxes other than income taxes, losses (gains) on asset dispositions, and net income (loss) attributable to noncontrolling interests.
(b)For 2023, includes an $18 million pre-tax loss recovery ($9 million after tax and partnership allocations) related to an arbitration award and a $16 million pre-tax gain ($12 million after tax) on the sale of spare parts.
(c)Includes accelerated depreciation of $307 million ($221 million after tax, net of noncontrolling interest impacts) in 2025 and $9 million ($7 million after tax, net of noncontrolling interest impacts) in 2024 related to the repowering of multiple wind facilities. See Note 15 under "Southern Power –Wind Repowering Projects" for additional information.
(d)Southern Power had no earnings from equity method investments for any period presented.
Southern Company Gas
Southern Company Gas manages its business through three reportable segments – gas distribution operations, gas pipeline investments, and gas marketing services. The non-reportable segments are combined and presented as "All Other."
The gas distribution operations segment is the largest component of Southern Company Gas' business and includes natural gas local distribution utilities that construct, manage, and maintain intrastate natural gas pipelines and gas distribution facilities in four states.
The gas pipeline investments segment consists of joint ventures in natural gas pipeline investments including a 50% interest in SNG and a 50% joint ownership interest in the Dalton Pipeline. These natural gas pipelines enable the provision of diverse sources of natural gas supplies to the customers of Southern Company Gas. See Notes 5 and 7 for additional information.
The gas marketing services segment provides natural gas marketing to end-use customers primarily in Georgia through SouthStar.
The "All Other" presentation includes operating segments and subsidiaries that fall below the quantitative threshold for separate disclosure.
Southern Company Gas' CODM utilizes segment expense information in the form of variances to budget to assess performance; therefore, Southern Company Gas has no reportable significant segment expenses.
Financial data for business segments for the years ended December 31, 2025, 2024, and 2023 was as follows:
Gas
Distribution
Operations
Gas
Pipeline
Investments
Gas
Marketing
Services
Total
Reportable
Segments
All
Other
EliminationsConsolidated
(in millions)
2025
Operating revenues$4,428 $32 $582 $5,042 $12 $(10)$5,044 
Other segment items(a)(b)
2,721 5 444 3,170 12 (10)3,172 
Depreciation and amortization687 5 14 706 2  708 
Earnings from equity method investments 127  127   127 
Interest expense342 36 3 381 (4) 377 
Income taxes109 28 34 171 11  182 
Segment net income (loss)(b)
$569 $85 $87 $741 $(9)$ $732 
Total assets at December 31, 2025
$25,391 $1,475 $1,749 $28,615 $10,643 $(11,871)$27,387 
II-251

    Table of Contents                                Index to Financial Statements

COMBINED NOTES TO FINANCIAL STATEMENTS

Gas
Distribution
Operations
Gas
Pipeline
Investments
Gas
Marketing
Services
Total
Reportable
Segments
All
Other
EliminationsConsolidated
(in millions)
2024
Operating revenues$3,899 $32 $516 $4,447 $23 $(14)$4,456 
Other segment items(a)
2,236 6 356 2,598 29 (14)2,613 
Depreciation and amortization630 5 14 649 1  650 
Earnings from equity method investments 146  146   146 
Interest expense311 35 3 349 (8) 341 
Income taxes172 31 41 244 14  258 
Segment net income (loss)
$550 $101 $102 $753 $(13)$ $740 
Total assets at December 31, 2024
$24,067 $1,573 $1,696 $27,336 $10,047 $(11,206)$26,177 
2023
Operating revenues$4,105 $32 $548 $4,685 $36 $(19)$4,702 
Other segment items(a)(b)
2,702 5 402 3,109 34 (19)3,124 
Depreciation and amortization561 5 15 581 1  582 
Earnings from equity method investments 140  140   140 
Interest expense275 32 3 310   310 
Income taxes126 32 37 195 16  211 
Segment net income (loss)(b)
$441 $98 $91 $630 $(15)$ $615 
Total assets at December 31, 2023
$22,906 $1,534 $1,615 $26,055 $9,675 $(10,647)$25,083 
(a)Primarily consists of cost of natural gas, other operations and maintenance, taxes other than income taxes, estimated loss on regulatory disallowance, AFUDC equity, and non-service cost-related retirement benefits income.
(b)For gas distribution operations, includes pre-tax charges associated with the disallowance of certain capital investments at Nicor Gas totaling approximately $63 million ($47 million after tax) in 2025 and $96 million ($72 million after tax) in 2023. See Note 2 under "Southern Company Gas" for additional information.
II-252

    Table of Contents                                Index to Financial Statements
Item 9.CHANGES IN AND DISAGREEMENTS WITH ACCOUNTANTS ON ACCOUNTING AND FINANCIAL DISCLOSURE
None.
Item 9A.CONTROLS AND PROCEDURES
Disclosure Controls and Procedures.
As of the end of the period covered by this Annual Report on Form 10-K, Southern Company, Alabama Power, Georgia Power, Mississippi Power, Southern Power, and Southern Company Gas conducted separate evaluations under the supervision and with the participation of each company's management, including the Chief Executive Officer and Chief Financial Officer, of the effectiveness of the design and operation of the disclosure controls and procedures (as defined in Rules 13a-15(e) and 15d-15(e) of the Securities Exchange Act of 1934, as amended). Based upon these evaluations, the Chief Executive Officer and the Chief Financial Officer, in each case, concluded that the disclosure controls and procedures are effective.
Internal Control Over Financial Reporting.
(a) Management's Annual Report on Internal Control Over Financial Reporting.
Page
Southern Company
II-255
Alabama Power
II-256
Georgia Power
II-257
Mississippi Power
II-258
Southern Power
II-259
Southern Company Gas
II-260
(b) Attestation Report of the Registered Public Accounting Firm.
The report of Deloitte & Touche LLP, Southern Company's independent registered public accounting firm, regarding Southern Company's Internal Control over Financial Reporting is included in Item 8 herein of this Form 10-K. This report is not applicable to Alabama Power, Georgia Power, Mississippi Power, Southern Power, and Southern Company Gas as these companies are not accelerated filers or large accelerated filers.
(c) Changes in internal control over financial reporting.
There have been no changes in Southern Company's, Alabama Power's, Georgia Power's, Mississippi Power's, Southern Power's, or Southern Company Gas' internal control over financial reporting (as such term is defined in Rules 13a-15(f) and 15d-15(f) under the Securities Exchange Act of 1934, as amended) during the fourth quarter 2025 that have materially affected or are reasonably likely to materially affect Southern Company's, Alabama Power's, Georgia Power's, Mississippi Power's, Southern Power's, or Southern Company Gas' internal control over financial reporting.
Item 9B.OTHER INFORMATION
The following table reports information regarding the adoption of "Rule 10b5-1 trading arrangements" or "non-Rule 10b5-1 trading arrangements," as defined in Item 408(a) of Regulation S-K, during the three months ended December 31, 2025 for Southern Company's directors and "officers," as defined in Rule 16a-1(f) under the Securities Exchange Act of 1934, as amended. There were no modifications or terminations of such trading arrangements during the three months ended December 31, 2025. Unless otherwise indicated, each trading arrangement listed below is a "Rule 10b5-1 trading arrangement," provides for the sale of shares of Southern Company's common stock, commences no earlier than the expiration of the cooling-off period required by Rule 10b5-1(c)(1)(ii)(B)(1) under the Securities Exchange Act of 1934, as amended, and terminates upon the earlier of the
II-253

    Table of Contents                                Index to Financial Statements
"Expiration Date" listed below or the completion of all sales. The Subsidiary Registrants had no reportable trading arrangements for the three months ended December 31, 2025.
Name
Title
Date of Adoption
Expiration Date
Aggregate Number of Shares Covered
Stanley W. Connally, Jr.Executive Vice President and Chief Operating OfficerNovember 17, 2025March 16, 202712,500
Christopher CummiskeyExecutive Vice PresidentNovember 18, 2025March 9, 2027
   8,954(1)
Matthew M. KimComptrollerNovember 25, 2025February 24, 2027
   6,353(1)
Sterling A. SpainhourExecutive Vice President and Chief Legal OfficerNovember 25, 2025September 1, 20279,443
Kimberly S. GreeneChairman, President, and Chief Executive Officer of Georgia PowerNovember 26, 2025March 30, 202765,000
(1)Includes shares underlying equity awards subject to performance conditions and accrual of dividend-equivalent rights. Accordingly, the total number of shares ultimately available for sale could be more or less than the amount shown. The amount shown is based on the target number of shares subject to equity awards and the dividend-equivalent rights accrued as of the date of adoption.
Item 9C.DISCLOSURE REGARDING FOREIGN JURISDICTIONS THAT PREVENT INSPECTIONS
Not applicable.
II-254

    Table of Contents                                Index to Financial Statements
MANAGEMENT'S REPORT ON INTERNAL CONTROL OVER FINANCIAL REPORTING
Southern Company and Subsidiary Companies
The management of Southern Company is responsible for establishing and maintaining an adequate system of internal control over financial reporting as required by the Sarbanes-Oxley Act of 2002 and as defined in Exchange Act Rule 13a-15(f). A control system can provide only reasonable, not absolute, assurance that the objectives of the control system are met.
Under management's supervision, an evaluation of the design and effectiveness of Southern Company's internal control over financial reporting was conducted based on the framework in Internal Control—Integrated Framework (2013) issued by the Committee of Sponsoring Organizations of the Treadway Commission. Based on this evaluation, management concluded that Southern Company's internal control over financial reporting was effective as of December 31, 2025.
Deloitte & Touche LLP, as auditors of Southern Company's financial statements, has issued an attestation report on the effectiveness of Southern Company's internal control over financial reporting as of December 31, 2025, which is included herein.

/s/ Christopher C. Womack
Christopher C. Womack
Chairman, President, and Chief Executive Officer

/s/ David P. Poroch
David P. Poroch
Executive Vice President, Chief Financial Officer, and Treasurer
February 18, 2026

II-255

    Table of Contents                                Index to Financial Statements
MANAGEMENT'S REPORT ON INTERNAL CONTROL OVER FINANCIAL REPORTING
Alabama Power Company
The management of Alabama Power is responsible for establishing and maintaining an adequate system of internal control over financial reporting as required by the Sarbanes-Oxley Act of 2002 and as defined in Exchange Act Rule 13a-15(f). A control system can provide only reasonable, not absolute, assurance that the objectives of the control system are met.
Under management's supervision, an evaluation of the design and effectiveness of Alabama Power's internal control over financial reporting was conducted based on the framework in Internal Control—Integrated Framework (2013) issued by the Committee of Sponsoring Organizations of the Treadway Commission. Based on this evaluation, management concluded that Alabama Power's internal control over financial reporting was effective as of December 31, 2025.

/s/ J. Jeffrey Peoples
J. Jeffrey Peoples
Chairman, President, and Chief Executive Officer

/s/ Moses H. Feagin
Moses H. Feagin
Executive Vice President, Chief Financial Officer, and Treasurer
February 18, 2026

II-256

    Table of Contents                                Index to Financial Statements
MANAGEMENT'S REPORT ON INTERNAL CONTROL OVER FINANCIAL REPORTING
Georgia Power Company
The management of Georgia Power is responsible for establishing and maintaining an adequate system of internal control over financial reporting as required by the Sarbanes-Oxley Act of 2002 and as defined in Exchange Act Rule 13a-15(f). A control system can provide only reasonable, not absolute, assurance that the objectives of the control system are met.
Under management's supervision, an evaluation of the design and effectiveness of Georgia Power's internal control over financial reporting was conducted based on the framework in Internal Control—Integrated Framework (2013) issued by the Committee of Sponsoring Organizations of the Treadway Commission. Based on this evaluation, management concluded that Georgia Power's internal control over financial reporting was effective as of December 31, 2025.

/s/ Kimberly S. Greene
Kimberly S. Greene
Chairman, President, and Chief Executive Officer

/s/ Tyler M. Cook
Tyler M. Cook
Senior Vice President, Chief Financial Officer, and Treasurer
February 18, 2026

II-257

    Table of Contents                                Index to Financial Statements
MANAGEMENT'S REPORT ON INTERNAL CONTROL OVER FINANCIAL REPORTING
Mississippi Power Company
The management of Mississippi Power is responsible for establishing and maintaining an adequate system of internal control over financial reporting as required by the Sarbanes-Oxley Act of 2002 and as defined in Exchange Act Rule 13a-15(f). A control system can provide only reasonable, not absolute, assurance that the objectives of the control system are met.
Under management's supervision, an evaluation of the design and effectiveness of Mississippi Power's internal control over financial reporting was conducted based on the framework in Internal Control—Integrated Framework (2013) issued by the Committee of Sponsoring Organizations of the Treadway Commission. Based on this evaluation, management concluded that Mississippi Power's internal control over financial reporting was effective as of December 31, 2025.

/s/ Pedro P. Cherry
Pedro P. Cherry
Chairman, President, and Chief Executive Officer

/s/ Matthew P. Grice
Matthew P. Grice
Vice President, Chief Financial Officer, and Treasurer
February 18, 2026

II-258

    Table of Contents                                Index to Financial Statements
MANAGEMENT'S REPORT ON INTERNAL CONTROL OVER FINANCIAL REPORTING
Southern Power Company and Subsidiary Companies
The management of Southern Power is responsible for establishing and maintaining an adequate system of internal control over financial reporting as required by the Sarbanes-Oxley Act of 2002 and as defined in Exchange Act Rule 13a-15(f). A control system can provide only reasonable, not absolute, assurance that the objectives of the control system are met.
Under management's supervision, an evaluation of the design and effectiveness of Southern Power's internal control over financial reporting was conducted based on the framework in Internal Control—Integrated Framework (2013) issued by the Committee of Sponsoring Organizations of the Treadway Commission. Based on this evaluation, management concluded that Southern Power's internal control over financial reporting was effective as of December 31, 2025.

/s/ Christopher Cummiskey
Christopher Cummiskey
Chairman and Chief Executive Officer

/s/ Gary Kerr
Gary Kerr
Senior Vice President, Chief Financial Officer, and Treasurer
February 18, 2026

II-259

    Table of Contents                                Index to Financial Statements
MANAGEMENT'S REPORT ON INTERNAL CONTROL OVER FINANCIAL REPORTING
Southern Company Gas and Subsidiary Companies
The management of Southern Company Gas is responsible for establishing and maintaining an adequate system of internal control over financial reporting as required by the Sarbanes-Oxley Act of 2002 and as defined in Exchange Act Rule 13a-15(f). A control system can provide only reasonable, not absolute, assurance that the objectives of the control system are met.
Under management's supervision, an evaluation of the design and effectiveness of Southern Company Gas' internal control over financial reporting was conducted based on the framework in Internal Control—Integrated Framework (2013) issued by the Committee of Sponsoring Organizations of the Treadway Commission. Based on this evaluation, management concluded that Southern Company Gas' internal control over financial reporting was effective as of December 31, 2025.

/s/ James Y. Kerr II
James Y. Kerr II
Chairman, President, and Chief Executive Officer

/s/ Grace A. Kolvereid
Grace A. Kolvereid
Executive Vice President, Chief Financial Officer, and Treasurer
February 18, 2026
II-260

    Table of Contents                                Index to Financial Statements
PART III
Items 10 (other than the information under "Code of Ethics" below), 11, 12, 13, and 14 for Southern Company are incorporated by reference to Southern Company's Definitive Proxy Statement relating to the 2026 Annual Meeting of Stockholders. Specifically, reference is made to "Corporate Governance at Southern Company" and "Biographical Information about our Nominees for Director," as well as "Delinquent Section 16(a) Reports," if required, for Item 10, "Compensation Discussion and Analysis," "Executive Compensation Tables," and "Director Compensation" for Item 11, "Stock Ownership Information," "Executive Compensation Tables," and "Equity Compensation Plan Information" for Item 12, "Biographical Information about our Nominees for Director" and "Corporate Governance at Southern Company" for Item 13, and "Principal Independent Registered Public Accounting Firm Fees" for Item 14.
Items 10, 11, 12, and 13 for each of the Subsidiary Registrants are omitted pursuant to General Instruction I(2)(c) of Form 10-K. Item 14 for each of the Subsidiary Registrants is contained herein.
Item 10.DIRECTORS, EXECUTIVE OFFICERS AND CORPORATE GOVERNANCE
Code of Ethics
The Registrants collectively have adopted a code of business conduct and ethics (Code of Ethics) that applies to each director, officer, and employee of the Registrants and their subsidiaries. The Code of Ethics can be found on Southern Company's website located at www.southerncompany.com. The Code of Ethics is also available free of charge in print to any shareholder by requesting a copy from Laura O. Hewett, Corporate Secretary, Southern Company, 30 Ivan Allen Jr. Boulevard NW, Atlanta, Georgia 30308. Any amendment to or waiver from the Code of Ethics that applies to executive officers and directors will be posted on the website.
Insider Trading Policies and Procedures
Each of the Registrants has adopted a Prohibition of Securities Trading Policy governing, among other items, the purchase, sale, and/or other dispositions of such Registrant's securities by directors, officers, and employees. Each Prohibition of Securities Trading Policy is reasonably designed to promote compliance with insider trading laws, rules, and regulations, and any listing standards applicable to such Registrant. The Prohibition of Securities Trading Policies do not address transactions in the Registrants' securities by the Registrants themselves; however, pursuant to the Code of Ethics, which, among other items, requires each Registrant to comply with all laws and regulations, it is the policy of each Registrant to comply with applicable securities laws and regulations with respect to any such transactions. Copies of the Prohibition of Securities Trading Policy for each Registrant are filed as Exhibits 19(a)-(f) to this Annual Report on Form 10-K.
III-1

    Table of Contents                                Index to Financial Statements
Item 14.PRINCIPAL ACCOUNTANT FEES AND SERVICES
The following represents fees billed to the Subsidiary Registrants in 2025 and 2024 by Deloitte & Touche LLP, each company's principal public accountant:
20252024
 (in thousands)
Alabama Power
Audit Fees (a)
$4,098 $3,663 
Audit-Related Fees (b)
92 128 
Tax Fees— — 
All Other Fees (c)
113 46 
Total$4,303 $3,837 
Georgia Power
Audit Fees (a)
$6,668 $6,216 
Audit-Related Fees (b)
154 196 
Tax Fees— — 
All Other Fees (c)
155 29 
Total$6,977 $6,441 
Mississippi Power
Audit Fees (a)
$681 $697 
Audit-Related Fees (b)
17 25 
Tax Fees— — 
All Other Fees (c)
25 
Total$723 $729 
Southern Power
Audit Fees (a)
$1,106 $1,028 
Audit-Related Fees (d)
2,130 2,478 
Tax Fees— — 
All Other Fees (c)
33 
Total$3,240 $3,539 
Southern Company Gas
Audit Fees (a)(e)
$2,626 $2,711 
Audit-Related Fees (b)
1,239 297 
Tax Fees— — 
All Other Fees (c)
12 11 
Total$3,877 $3,019 
(a)Includes services performed in connection with financing transactions.
(b)Represents fees for statutory and non-statutory audit services and other attest services.
(c)Represents registration fees for attendance at Deloitte & Touche LLP-sponsored education seminars and other non-audit advisory services.
(d)Represents fees in connection with audits of Southern Power partnerships, other statutory and non-statutory audit services, and other attest services.
(e)Includes fees in connection with statutory audits of several Southern Company Gas subsidiaries.
The Southern Company Audit Committee (on behalf of Southern Company and its subsidiaries) has a Policy of Engagement of the Independent Auditor for Audit and Non-Audit Services that includes pre-approval requirements for the audit and non-audit services provided by Deloitte & Touche LLP. All of the services provided by Deloitte & Touche LLP in fiscal years 2025 and 2024 and related fees were approved in advance by the Southern Company Audit Committee.
III-2

    Table of Contents                                Index to Financial Statements
PART IV
Item 15.EXHIBITS AND FINANCIAL STATEMENT SCHEDULES
(a)The following documents are filed as a part of this report on Form 10-K:
(1)Financial Statements and Financial Statement Schedules:
Management's Reports on Internal Control Over Financial Reporting for Southern Company and Subsidiary Companies, Alabama Power, Georgia Power, Mississippi Power, Southern Power and Subsidiary Companies, and Southern Company Gas and Subsidiary Companies are listed under Item 9A herein.
Reports of Independent Registered Public Accounting Firm (Deloitte & Touche LLP, PCAOB ID: 34) on the financial statements and financial statement schedules for Southern Company and Subsidiary Companies, Alabama Power Company, Georgia Power Company, Mississippi Power Company, Southern Power Company and Subsidiary Companies, and Southern Company Gas and Subsidiary Companies are listed under Item 8 herein. Also included in Item 8 herein is the Report of Independent Registered Public Accounting Firm (BDO USA, P.C.; Houston, Texas; PCAOB ID: 243) on the financial statements of Southern Natural Gas Company, L.L.C., Southern Company Gas' investment which is accounted for by the use of the equity method.
The financial statements filed as a part of this report for Southern Company and Subsidiary Companies, Alabama Power, Georgia Power, Mississippi Power, Southern Power and Subsidiary Companies, and Southern Company Gas and Subsidiary Companies are listed under Item 8 herein.
The financial statement schedules (Schedule II, Valuation and Qualifying Accounts and Reserves) for Southern Company and Subsidiary Companies, Alabama Power, Georgia Power, Mississippi Power, Southern Power and Subsidiary Companies, and Southern Company Gas and Subsidiary Companies are included on pages IV-2 and IV-3. Columns in Schedule II may be omitted if the information is not applicable or not required. All other schedules are omitted as not applicable or not required.
(2)Exhibits:
Exhibits for the Registrants are listed in the Exhibit Index at page E-1.

Item 16.FORM 10-K SUMMARY

None.
IV-1

    Table of Contents                                Index to Financial Statements
SCHEDULE II — VALUATION AND QUALIFYING ACCOUNTS
FOR THE YEARS ENDED DECEMBER 31, 2025, 2024, AND 2023

Additions
DescriptionBalance at Beginning of PeriodCharged to IncomeCharged to Other Accounts
Deductions(*)
Balance at End of Period
(in millions)
Provision for uncollectible accounts:
Southern Company
2025$74 $127 $7 $124 $84 
202468 119 (1)112 74 
202371 87 3 93 68 
Alabama Power
2025$22 $22 $ $21 $23 
202416 26  20 22 
202314 16  14 16 
Georgia Power
2025$15 $52 $ $60 $7 
20244 51  40 15 
20233 26  25 4 
Mississippi Power
2025$1 $2 $ $2 $1 
20241 2  2 1 
20231 2  2 1 
Southern Power
2025$ $ $ $ $ 
20241 (1)   
20231    1 
Southern Company Gas
2025$33 $50 $7 $40 $50 
202444 39 (1)49 33 
202350 43 3 52 44 
(*)Deductions represent write-offs of accounts considered to be uncollectible, less recoveries of amounts previously written off.
IV-2

    Table of Contents                                Index to Financial Statements
SCHEDULE II — VALUATION AND QUALIFYING ACCOUNTS (CONTINUED)
FOR THE YEARS ENDED DECEMBER 31, 2025, 2024, AND 2023

Additions
DescriptionBalance at Beginning of PeriodCharged to IncomeCharged to Other AccountsDeductionsBalance at End of Period
(in millions)
Tax valuation allowance (net state):
Southern Company(a)(b)(c)
2025$268 $128 $ $39 $357 
2024168 97 3  268 
2023207 (14)(25) 168 
Georgia Power(b)
2025$124 $126 $ $39 $211 
202460 97 (33) 124 
202398 (15)(23) 60 
Mississippi Power(c)
2025$32 $ $ $ $32 
202432    32 
202332    32 
Southern Power(c)
2025$21 $2 $ $ $23 
202421    21 
202321    21 
Southern Company Gas(c)
2025$4 $ $ $ $4 
20245  (1) 4 
20237  (2) 5 
(a)In 2024, Southern Company established a valuation allowance for certain Georgia state tax credits expected to expire prior to being fully utilized.
(b)In 2018, Georgia Power established a valuation allowance for certain Georgia state tax credits expected to expire prior to being fully utilized, which has been adjusted in subsequent years as a result of changes in projected state taxable income.
(c)Associated with a state net operating loss carryforward expected to expire prior to being fully utilized.
See Note 10 to the financial statements in Item 8 herein for additional information.
IV-3

    Table of Contents                                Index to Financial Statements
EXHIBIT INDEX
The exhibits below with an asterisk (*) preceding the exhibit number are filed herewith. The remaining exhibits have previously been filed with the SEC and are incorporated herein by reference. The exhibits marked with a pound sign (#) are management contracts or compensatory plans or arrangements required to be identified as such by Item 15 of Form 10-K.
(3)Articles of Incorporation and By-Laws
Southern Company
(a)1
Restated Certificate of Incorporation of Southern Company and amendments thereto through May 27, 2025. (Designated in Form 10-K for the year ended December 31, 2018, File No. 1-3526, as Exhibit 3(a)1 and in Form 8-K dated May 21, 2025. File No. 1-3526, as Exhibit 3.1.)
(a)2
Amended and Restated By-laws of Southern Company effective December 12, 2022, and as presently in effect. (Designated in Form 8-K dated December 12, 2022, File No. 1-3526, as Exhibit 3.1.)
Alabama Power
(b)1
Charter of Alabama Power and amendments thereto through September 7, 2017. (Designated in Registration Nos. 2-59634 as Exhibit 2(b), 2-60209 as Exhibit 2(c), 2-60484 as Exhibit 2(b), 2-70838 as Exhibit 4(a)-2, 2-85987 as Exhibit 4(a)-2, 33-25539 as Exhibit 4(a)-2, 33-43917 as Exhibit 4(a)-2, in Form 8-K dated February 5, 1992, File No. 1-3164, as Exhibit 4(b)-3, in Form 8-K dated July 8, 1992, File No. 1-3164, as Exhibit 4(b)-3, in Form 8-K dated October 27, 1993, File No. 1-3164, as Exhibits 4(a) and 4(b), in Form 8-K dated November 16, 1993, File No. 1-3164, as Exhibit 4(a), in Certificate of Notification, File No. 70-8191, as Exhibit A, in Form 10-K for the year ended December 31, 1997, File No. 1-3164, as Exhibit 3(b)2, in Form 8-K dated August 10, 1998, File No. 1-3164, as Exhibit 4.4, in Form 10-K for the year ended December 31, 2000, File No. 1-3164, as Exhibit 3(b)2, in Form 10-K for the year ended December 31, 2001, File No. 1-3164, as Exhibit 3(b)2, in Form 8-K dated February 5, 2003, File No. 1-3164, as Exhibit 4.4, in Form 10-Q for the quarter ended March 31, 2003, File No 1-3164, as Exhibit 3(b)1, in Form 8-K dated February 5, 2004, File No. 1-3164, as Exhibit 4.4, in Form 10-Q for the quarter ended March 31, 2006, File No. 1-3164, as Exhibit 3(b)(1), in Form 8-K dated December 5, 2006, File No. 1-3164, as Exhibit 4.5, in Form 8-K dated September 12, 2007, File No. 1-3164, as Exhibit 4.5, in Form 8-K dated October 17, 2007, File No. 1-3164, as Exhibit 4.5, in Form 10-Q for the quarter ended March 31, 2008, File No. 1-3164, as Exhibit 3(b)1, and in Form 8-K dated September 5, 2017, File No. 1-3164, as Exhibit 4.5.)
(b)2
Amended and Restated By-laws of Alabama Power effective October 16, 2023, and as presently in effect. (Designated in Form 10-Q for the quarter ended September 30, 2023, File No 1-3164, as Exhibit 3(b)1.)
Georgia Power
(c)1
Charter of Georgia Power and amendments thereto through October 9, 2007. (Designated in Registration Nos. 2-63392 as Exhibit 2(a)-2, 2-78913 as Exhibits 4(a)-(2) and 4(a)-(3), 2-93039 as Exhibit 4(a)-(2), 2-96810 as Exhibit 4(a)-2, 33-141 as Exhibit 4(a)-(2), 33-1359 as Exhibit 4(a)(2), 33-5405 as Exhibit 4(b)(2), 33-14367 as Exhibits 4(b)-(2) and 4(b)-(3), 33-22504 as Exhibits 4(b)-(2), 4(b)-(3) and 4(b)-(4), in Form 10-K for the year ended December 31, 1991, File No. 1-6468, as Exhibits 4(a)(2) and 4(a)(3), in Registration No. 33-48895 as Exhibits 4(b)-(2) and 4(b)-(3), in Form 8-K dated December 10, 1992, File No. 1-6468 as Exhibit 4(b), in Form 8-K dated June 17, 1993, File No. 1-6468, as Exhibit 4(b), in Form 8-K dated October 20, 1993, File No. 1-6468, as Exhibit 4(b), in Form 10-K for the year ended December 31, 1997, File No. 1-6468, as Exhibit 3(c)2, in Form 10-K for the year ended December 31, 2000, File No. 1-6468, as Exhibit 3(c)2, in Form 8-K dated June 27, 2006, File No. 1-6468, as Exhibit 3.1, and in Form 8-K dated October 3, 2007, File No. 1-6468, as Exhibit 4.5.)
(c)2
By-laws of Georgia Power as amended effective November 9, 2016, and as presently in effect. (Designated in Form 8-K dated November 9, 2016, File No. 1-6468, as Exhibit 3.1.)
Mississippi Power
(d)1
Amended and Restated Articles of Incorporation of Mississippi Power dated July 22, 2020. (Designated in Form 10-Q for the quarter ended June 30, 2020, File No. 001-11229, as Exhibit 3(d)1.)
(d)2
By-laws of Mississippi Power as amended effective July 22, 2020, and as presently in effect. (Designated in Form 10-Q for the quarter ended June 30, 2020, File No. 001-11229, as Exhibit 3(d)2.)
E-1

    Table of Contents                                Index to Financial Statements
Southern Power
(e)1
Certificate of Incorporation of Southern Power Company dated January 8, 2001. (Designated in Registration No. 333-98553 as Exhibit 3.1.)
(e)2
By-laws of Southern Power Company effective January 8, 2001. (Designated in Registration No. 333-98553 as Exhibit 3.2.)
Southern Company Gas
(f)1
Amended and Restated Articles of Incorporation of Southern Company Gas dated July 11, 2016. (Designated in Form 8-K dated July 8, 2016, File No. 1-14174, as Exhibit 3.1.)
(f)2
Amended and Restated By-laws of Southern Company Gas effective October 23, 2018. (Designated in Form 10-Q for the quarter ended June 30, 2019, File No. 1-14174, as Exhibit 3(e).)
(4)Instruments Describing Rights of Security Holders, Including Indentures
With respect to each of Southern Company, Alabama Power, Georgia Power, Mississippi Power, Southern Power Company, and Southern Company Gas, such Registrant has excluded certain instruments with respect to long-term debt that does not exceed 10% of the total assets of such Registrant and its subsidiaries. Each such Registrant agrees, upon request of the SEC, to furnish copies of any or all such instruments to the SEC.
Southern Company
(a)1
Senior Note Indenture dated as of January 1, 2007, between Southern Company and Computershare Trust Company, N.A., as successor Trustee, and certain indentures supplemental thereto through November 6, 2025. (Designated in Form 8-K dated January 11, 2007, File No. 1-3526, as Exhibit 4.1, in Form 8-K dated May 19, 2016, File No. 1-3526, as Exhibit 4.2(e), in Form 8-K dated May 19, 2016, File No. 1-3526, as Exhibit 4.2(f), in Form 8-K dated May 19, 2016, File No. 1-3526, as Exhibit 4.2(g), in Form 8-K dated April 1, 2020, File No. 1-3526, as Exhibit 4.2, in Form 8-K dated February 23, 2021, File No. 1-3526, as Exhibit 4.4(a), in Form 8-K dated February 23, 2021, File No. 1-3526, as Exhibit 4.4(b), in Form 8-K dated October 3, 2022, File No. 1-3526, as Exhibit 4.4(b), in Form 8-K dated May 15, 2023, File No. 1-3526, as Exhibit 4.4(a), in Form 8-K dated May 15, 2023, File No. 1-3526, as Exhibit 4.4(b), in Form 8-K dated September 5, 2023, File No. 1-3526, as Exhibit 4.4(a), in Form 8-K dated September 5, 2023, File No. 1-3526, as Exhibit 4.4(b), in Form 8-K dated May 9, 2024, File No. 1-3526, as Exhibit 4.2, in Form 8-K dated September 4, 2024, File No. 1-3526, as Exhibit 4.2, in Form 8-K dated May 20, 2025, File No. 1-3526, as Exhibit 4.2, in Form 8-K dated November 3, 2025, File No, 1-3526, as Exhibit 4.2(a), and in Form 8-K dated November 3, 2025, File No. 1-3526, as Exhibit 4.2(b).)
(a)2
Subordinated Note Indenture dated as of October 1, 2015, between Southern Company and Computershare Trust Company, N.A., as successor Trustee, and certain indentures supplemental thereto through February 28, 2025. (Designated in Form 8-K dated October 1, 2015, File No. 1-3526, as Exhibit 4.3, in Form 10-Q for the quarter ended June 30, 2017, File No. 1-3526 as Exhibit 4(a)1, in Form 8-K dated November 17, 2017, File No. 1-3526, as Exhibit 4.4, in Form 8-K dated August 13, 2019, File No. 1-3526, as Exhibit 4.4(b), in Form 8-K dated January 6, 2020, File No. 1-3526 as Exhibit 4.4, in Form 8-K dated September 15, 2020, File No. 1-3526, as Exhibit 4.4(b), in Form 8-K dated May 3, 2021, File No. 1-3526, as Exhibit 4.4, in Form 8-K dated September 13, 2021, File No. 1-3526, as Exhibit 4.4, in Form 8-K dated May 9, 2022, File No. 1-3526, as Exhibit 4.4(b), in Form 8-K dated January 8, 2025, File No. 1-3526, as Exhibit 4.4, and in Form 8-K dated February 25, 2025, File No. 1-3526, as Exhibit 4.4.)
(a)3
Purchase Contract and Pledge Agreement, dated as of November 6, 2025, between Southern Company and U.S. Bank Trust Company, National Association, as Purchase Contract Agent, Collateral Agent, Custodial Agent, and Securities Intermediary. (Designated in Form 8-K dated November 3, 2025, File No. 1-3526, as Exhibit 4.9.)
*
(a)4
Description of securities registered pursuant to Section 12 of the Securities Exchange Act of 1934, as amended.
E-2

    Table of Contents                                Index to Financial Statements
Alabama Power
(b)1
Senior Note Indenture dated as of December 1, 1997, between Alabama Power and Regions Bank, as Successor Trustee, and certain indentures supplemental thereto through September 5, 2025. (Designated in Form 8-K dated December 4, 1997, File No. 1-3164, as Exhibit 4.1, in Form 8-K dated February 11, 2003, File No. 1-3164, as Exhibit 4.2(a), in Form 8-K dated March 12, 2003, File No. 1-3164, as Exhibit 4.2, in Form 8-K dated May 8, 2008, File No. 1-3164, as Exhibit 4.2, in Form 8-K dated February 26, 2009, File No. 1-3164, as Exhibit 4.2, in Form 8-K dated March 3, 2011, File No. 1-3164, as Exhibit 4.2, in Form 8-K dated May 18, 2011, File No. 1-3164, as Exhibit 4.2(b), in Form 8-K dated January 10, 2012, File No. 1-3164, as Exhibit 4.2, in Form 8-K dated November 27, 2012, File No. 1-3164, as Exhibit 4.2, in Form 8-K dated August 20, 2014, File No. 1-3164, as Exhibit 4.6, in Form 8-K dated March 5, 2015, File No. 1-3164, as Exhibit 4.6, in Form 8-K dated January 8, 2016, File No. 1-3164, as Exhibit 4.6, in Form 8-K dated November 2, 2017, File No. 1-3164, as Exhibit 4.6, in Form 8-K dated June 21, 2018, File No. 1-3164, as Exhibit 4.6, in Form 8-K dated September 12, 2019, File No. 1-3164, as Exhibit 4.6, in Form 8-K dated August 24, 2020, File No. 1-3164, as Exhibit 4.6, in Form 8-K dated June 7, 2021, File No. 1-3164, as Exhibit 4.6, in Form 8-K dated November 15, 2021, File No. 1-3164, as Exhibit 4.6, in Form 8-K dated March 2, 2022, File No. 1-3164, as Exhibit 4.6, in Form 8-K dated August 9, 2022, File No. 1-3164, as Exhibit 4.6(a), in Form 8-K dated August 9, 2022, File No. 1-3164, as Exhibit 4.6(b), in Form 8-K dated May 3, 2023, File No. 1-3164, as Exhibit 4.6, in Form 8-K dated November 6, 2023, File No. 1-3164, as Exhibit 4.6, in Form 8-K dated March 20, 2025, File No. 1-3164, as Exhibit 4.6, in Form 8-K dated June 11, 2025, File No. 1-3164, as Exhibit 4.6, and in Form 8-K dated September 2, 2025, File No. 1-3164, as Exhibit 4.6.)
Georgia Power
(c)1
Senior Note Indenture dated as of January 1, 1998, between Georgia Power and Computershare Trust Company, N.A., as Successor Trustee, and certain indentures supplemental thereto through September 29, 2025. (Designated in Form 8-K dated January 21, 1998, File No. 1-6468, as Exhibits 4.1, in Form 8-K dated March 6, 2007, File No. 1-6468, as Exhibit 4.2, in Form 8-K dated February 4, 2009, File No. 1-6468, as Exhibit 4.2, in Form 8-K dated May 24, 2010, File No. 1-6468, as Exhibit 4.2, in Form 8-K dated August 26, 2010, File No. 1-6468, as Exhibit 4.2, in Form 8-K dated February 29, 2012, File No. 1-6468, as Exhibit 4.2, in Form 8-K dated March 12, 2013, File No. 1-6468, as Exhibit 4.2(a), in Form 8-K dated March 2, 2016, File No. 1-6468, as Exhibit 4.2(a), in Form 8-K dated February 28, 2017, File No. 1-6468, as Exhibit 4.2(b), in Form 8-K dated September 4, 2019, File No. 1-6468, as Exhibit 4.2(b), in Form 8-K dated January 8, 2020, File No. 1-6468, as Exhibit 4.2(c), in Form 8-K dated February 22, 2021, File No. 1-6468, as Exhibit 4.2 in Form 8-K dated May 2, 2022, File No. 1-6468, as Exhibit 4.2(a), in Form 8-K dated May 2, 2022, File No. 1-6468, as Exhibit 4.2(b), in Form 8-K dated May 1, 2023, File No. 1-6468, as Exhibit 4.2(a), in Form 8-K dated May 1, 2023, File No. 1-6468, as Exhibit 4.2(b), in Form 8-K dated February 20, 2024, File No. 1-6468, as Exhibit 4.2(a), in Form 8-K dated February 20, 2024, File No. 1-6468, as Exhibit 4.2(b), in Form 8-K dated November 8, 2024, File No. 1-6468, as Exhibit 4.2, in Form 8-K dated December 2, 2024, File No. 1-6468, as Exhibit 4.2, in Form 8-K dated February 24, 2025, File No. 1-6468, as Exhibit 4.3(a), in Form 8-K dated February 24, 2025, File No. 1-6468, as Exhibit 4.3(b), in Form 8-K dated February 24, 2025, File No. 1-6468, as Exhibit 4.3(c), in Form 8-K dated September 24, 2025, File No. 1-6468, as Exhibit 4.3(b), and in Form 8-K dated September 24, 2025, File No. 1-6468, as Exhibit 4.3(c).)
(c)2
Subordinated Note Indenture, dated as of September 1, 2017, between Georgia Power and Computershare Trust Company, N.A., as Successor Trustee, and First Supplemental Indenture thereto dated as of September 21, 2017. (Designated in Form 8-K dated September 18, 2017, File No. 1-6468, as Exhibit 4.3, and in Form 8-K dated September 18, 2017, File No. 1-6468, as Exhibit 4.4.)
(c)3
Amended and Restated Loan Guarantee Agreement, dated as of March 22, 2019, between Georgia Power and the DOE. (Designated in Form 8-K dated March 22, 2019, File No. 1-6468, as Exhibit 4.1.)
(c)4
Note Purchase Agreement among Georgia Power, the DOE, and the Federal Financing Bank dated as of February 20, 2014. (Designated in Form 8-K dated February 20, 2014, File No. 1-6468, as Exhibit 4.2.)
(c)5
Future Advance Promissory Note dated February 20, 2014 made by Georgia Power to the FFB. (Designated in Form 8-K dated February 20, 2014, File No. 1-6468, as Exhibit 4.3.)
(c)6
Amended and Restated Deed to Secure Debt, Security Agreement and Fixture Filing, dated as of March 22, 2019, by Georgia Power to PNC Bank, National Association, doing business as Midland Loan Services Inc., a division of PNC Bank, National Association. (Designated in Form 8-K dated March 22, 2019, File No. 1-6468, as Exhibit 4.4.)
E-3

    Table of Contents                                Index to Financial Statements
(c)7
Amended and Restated Owners Consent to Assignment and Direct Agreement and Amendment to Plant Alvin W. Vogtle Additional Units Ownership Participation Agreement, dated as of March 22, 2019, among Georgia Power, the other Vogtle Owners, the DOE, and PNC Bank, National Association, doing business as Midland Loan Services Inc., a division of PNC Bank, National Association. (Designated in Form 8-K dated March 22, 2019, File No. 1-6468, as Exhibit 4.5.)
(c)8
Note Purchase Agreement, dated as of March 22, 2019, between Georgia Power, the DOE, and the FFB. (Designated in Form 8-K dated March 22, 2019, File No. 1-6468, as Exhibit 4.2.)
(c)9
Promissory Note of Georgia Power, dated as of March 22, 2019. (Designated in Form 8-K dated March 22, 2019, File No. 1-6468, as Exhibit 4.3.)
(c)10
Description of securities registered pursuant to Section 12 of the Securities Exchange Act of 1934, as amended. (Designated in Form 10-K for the year ended December 31, 2019, File No. 1-6468, as Exhibit 4(c)10.)
Mississippi Power
(d)1
Senior Note Indenture dated as of May 1, 1998, between Mississippi Power and Computershare Trust Company, N.A., as Successor Trustee, and certain indentures supplemental thereto through June 29, 2021. (Designated in Form 8-K dated May 14, 1998, File No. 001-11229, as Exhibit 4.1, in Form 8-K dated October 11, 2011, File No. 001-11229, as Exhibit 4.2(b), in Form 8-K dated March 5, 2012, File No. 001-11229, as Exhibit 4.2(b), in Form 8-K dated March 22, 2018, File No. 001-11229, as Exhibit 4.2(b), in Form 8-K dated June 24, 2021, File No. 001-11229, as Exhibit 4.2(a), and in Form 8-K dated June 24, 2021, File No. 001-11229, as Exhibit 4.2(b).)
(d)
2
Senior Note Indenture dated as of June 1, 2023, between Mississippi Power and Regions Bank, as Trustee, and certain indentures supplemental thereto through March 28, 2025. (Designated in Form 10-Q for the quarter ended June 30, 2023, File No. 001-11229, as Exhibit 4(d)1, in Form 10-Q for the quarter ended June 30, 2023, File No. 001-11229, as Exhibit 4(d)2, in Form 10-Q for the quarter ended June 30, 2023, File No. 001-11229, as Exhibit 4(d)3, in Form 10-Q for the quarter ended March 31, 2024, File No. 001-11229, as Exhibit 4(d)1, in Form 10-Q for the quarter ended March 31, 2024, File No. 001-11229, as Exhibit 4(d)2, in Form 10-Q for the quarter ended June 30, 2024, File No. 001-11229, as Exhibit 4(d)1, in Form 10-Q for the quarter ended March 31, 2025, File No. 001-11229, as Exhibit 4(d)1, and in Form 10-Q for the quarter ended March 31, 2025, File No. 001-11229, as Exhibit 4(d)2.)
Southern Power
(e)1
Senior Note Indenture dated as of June 1, 2002, between Southern Power Company and Computershare Trust Company, N.A., as Successor Trustee, and certain indentures supplemental thereto through January 8, 2021. (Designated in Registration No. 333-98553 as Exhibit 4.1, in Form 8-K dated September 14, 2011, File No. 333-98553, as Exhibit 4.4, in Form 8-K dated July 10, 2013, File No. 333-98553, as Exhibit 4.4, in Form 8-K dated June 13, 2016, File No. 001-37803, as Exhibit 4.4(b), in Form 10-Q for the quarter ended September 30, 2016, File No. 001-37803, as Exhibit 4(f)1, and in Form 8-K dated November 10, 2016, File No. 001-37803, as Exhibit 4.4(c).)
(e)2
Senior Note Indenture dated as of August 1, 2025 between Southern Power Company and U.S. Bank Trust Company, National Association, as Trustee, and certain indentures supplemental thereto through September 19, 2025. (Designated in Registration No. 333-289172 as Exhibit 4.5, in Form 8-K dated September 16, 2025, File No.001-37803 as Exhibit 4.6(a), and in Form 8-K dated September 16, 2025, File No. 001-37803 as Exhibit 4.6(b).)
(e)3
Description of securities registered pursuant to Section 12 of the Securities Exchange Act of 1934, as amended. (Designated in Form 10-K for the year ended December 31, 2022, File No. 001-37803, as Exhibit 4(e)2.)
Southern Company Gas
(f)1
Indenture dated February 20, 2001 among AGL Capital Corporation, AGL Resources Inc., and Computershare Trust Company, N.A., as Successor Trustee and First Supplemental Indenture thereto dated as of September 9, 2021. (Designated in Form S-3, File No. 333-69500, as Exhibit 4.2, and in Form 8-K dated September 7, 2021, File No. 1-14174, as Exhibit 4.2.)
E-4

    Table of Contents                                Index to Financial Statements
(f)2
Southern Company Gas Capital Corporation's 6.00% Senior Notes due 2034, 5.875% Senior Notes due 2041, 4.40% Senior Notes due 2043, 3.250% Senior Notes due 2026, Form of 3.950% Senior Note due October 1, 2046, Form of Series 2017A 4.400% Senior Note due May 30, 2047, Form of 2020A 1.750% Senior Note due January 15, 2031, Form of Series 2021A 3.15% Senior Note due September 30, 2051, Form of Series 2022A 5.15% Senior Note due September 30, 2032, Form of Series 2023A 5.75% Senior Note due September 15, 2033, and Form of Series 2024A 4.95% Senior Note due September 15, 2034. (Designated in Form 8-K dated September 22, 2004, File No. 1-14174, as Exhibit 4.1, in Form 8-K dated March 16, 2011, File No. 1-14174, as Exhibit 4.1, in Form 8-K dated May 13, 2013, File No. 1-14174, as Exhibit 4.2, in Form 8-K dated May 13, 2016, File No. 1-14174, as Exhibit 4.2, in Form 8-K dated September 8, 2016, File No. 1-14174, as Exhibit 4.1(b), in Form 8-K dated May 5, 2017, File No. 1-14174, as Exhibit 4.1, in Form 8-K dated August 17, 2020, File No. 1-14174, as Exhibit 4.1, in Form 8-K dated September 9, 2021, File No. 1-14174, as Exhibit 4.1, in Form 8-K dated September 6, 2022, File No. 1-14174, as Exhibit 4.1, in Form 8-K dated September 11, 2023, File No. 1-14174, as Exhibit 4.1, and in Form 8-K dated September 3, 2024, File No. 1-14174, as Exhibit 4.1, respectively.)
(f)3
Southern Company Gas' Guarantee related to the 6.00% Senior Notes due 2034, Guarantee related to the 5.875% Senior Notes due 2041, Guarantee related to the 4.40% Senior Notes due 2043, Guarantee related to the 3.250% Senior Notes due 2026, Form of Guarantee related to the 3.950% Senior Notes due October 1, 2046, Form of Guarantee related to the Series 2017A 4.400% Senior Notes due May 30, 2047, Form of Guarantee related to the Series 2020A 1.750% Senior Notes due January 15, 2031, Form of Guarantee related to the Series 2021A 3.15% Senior Note due September 30, 2051, Form of Guarantee related to the Series 2022A 5.15% Senior Notes due September 30, 2032, Form of Guarantee related to the Series 2023A 5.75% Senior Notes Due September 15, 2033, and Form of Guarantee related to the Series 2024A 4.95% Senior Notes due September 15, 2034. (Designated in Form 8-K dated September 22, 2004, File No. 1-14174, as Exhibit 4.3, in Form 8-K dated March 16, 2011, File No. 1-14174, as Exhibit 4.1, in Form 8-K dated May 13, 2013, File No. 1-14174, as Exhibit 4.3, in Form 8-K dated May 13, 2016, File No. 1-14174, as Exhibit 4.3, in Form 8-K dated September 8, 2016, File No. 1-14174, as Exhibit 4.3(b), in Form 8-K dated May 5, 2017, File No. 1-14174, as Exhibit 4.3, in Form 8-K dated August 17, 2020, File No. 1-14174, as Exhibit 4.3, in Form 8-K dated September 9, 2021, File No. 1-14174, as Exhibit 4.3, in Form 8-K dated September 6, 2022, File No. 1-14174, as Exhibit 4.3, and in Form 8-K dated September 11, 2023, File No. 1-14174, as Exhibit 4.3, and in Form 8-K dated September 3, 2024, File No. 1-14174, as Exhibit 4.3, respectively.)
(f)4
Indenture dated as of February 1, 2025 among Southern Company Gas Capital Corporation, Southern Company Gas, and U.S. Bank Trust Company, National Association, as Trustee. (Designated in Registration No. 333-285115, as Exhibit 4.2.)
(f)5
Southern Company Gas Capital Corporation's Form of Series 2025A 4.05% Senior Notes due September 15, 2028 and Form of Series 2025B 5.10% Senior Notes due September 15, 2035. (Designated in Form 8-K dated September 3, 2025, File No. 1-14174, as Exhibit 4.1(a) and in Form 8-K dated September 3, 2025, File No. 1-14174, as Exhibit 4.1(b), respectively.)
(f)6
Southern Company Gas' Form of Guarantee related to the Series 2025A 4.05% Senior Notes due September 15, 2028 and Form of Guarantee related to the Series 2025B 5.10% Senior Notes due September 15, 2035. (Designated in Form 8-K dated September 3, 2025, File No. 1-14174, as Exhibit 4.3(a) and in Form 8-K dated September 3, 2025, File No. 1-14174, as Exhibit 4.3(b), respectively.)
(f)7Indenture dated December 1, 1989 of Atlanta Gas Light Company and First Supplemental Indenture thereto dated March 16, 1992. (Designated in Form S-3, File No. 33-32274, as Exhibit 4(a) and in Form S-3, File No. 33-46419, as Exhibit 4(a).)
E-5

    Table of Contents                                Index to Financial Statements
(f)8
Indenture of Commonwealth Edison Company to Continental Illinois National Bank and Trust Company of Chicago, Trustee, dated as of January 1, 1954, Indenture of Adoption of Northern Illinois Gas Company to Continental Illinois National Bank and Trust Company of Chicago, Trustee, dated February 9, 1954, and certain indentures supplemental thereto. (Designated in Form 10-K for the year ended December 31, 1995, File No. 1-7296, as Exhibit 4.01, in Form 10-K for the year ended December 31, 1995, File No. 1-7296, as Exhibit 4.02, in Registration No. 2-56578 as Exhibits 2.21 and 2.25, in Form 10-Q for the quarter ended June 30, 1996, File No. 1-7296, as Exhibit 4.01, in Form 10-K for the year ended December 31, 1997, File No. 1-7296, as Exhibit 4.19, in Form 10-K for the year ended December 31, 2003, File No. 1-7296, as Exhibit 4.10, in Form 10-K for the year ended December 31, 2006, File No. 1-7296, as Exhibit 4.11, in Form 10-Q for the quarter ended September 30, 2008, File No. 1-7296, as Exhibit 4.01, in Form 10-Q for the quarter ended September 30, 2012, File No. 1-7296, as Exhibit 4, in Form 10-K for the year ended December 31, 2016, File No. 1-14174, as Exhibit 4(g)6, in Form 10-K for the year ended December 31, 2017, File No. 1-14174, as Exhibit 4(g)6, in Form 10-Q for the quarter ended September 30, 2018, File No. 1-14174, as Exhibit 4(g)1, in Form 10-K for the year ended December 31, 2019, File No. 1-14174, as Exhibit 4(f)6, in Form 10-K for the year ended December 31, 2020, File No. 1-14174, as Exhibit 4(f)6, in Form 10-Q for the quarter ended September 30, 2021, File No. 1-4174, as Exhibit 4(f)4, in Form 10-Q for the quarter ended September 30, 2023, File No. 1-4174, as Exhibit 4(f)3, in Form 10-Q for the quarter ended September 30, 2024, File No. 1-4174, as Exhibit 4(f)3, and in Form 10-Q for the quarter ended September 30, 2025, File No. 1-4174, as Exhibit 4(f)6.)
(10)Material Contracts
Southern Company
#(a)1
Deferred Compensation Plan for Outside Directors of The Southern Company, Amended and Restated effective June 1, 2021 and First Amendment thereto effective as of June 1, 2021. (Designated in Form 10-Q for the quarter ended June 30, 2021, File No. 1-3526, as Exhibit 10(a)2, and in Form 10-K for the year ended December 31, 2021, File No. 1-3526, as Exhibit 10(a)25.)
 
#(a)2
Southern Company Deferred Compensation Plan, Amended and Restated as of January 1, 2025. (Designated in Form 10-K for the year ended December 31, 2024, File No. 1-3526 as Exhibit 10(a)2.)
#(a)3
The Southern Company Supplemental Executive Retirement Plan, Amended and Restated effective June 30, 2016, Amendment No. 1 thereto effective January 1, 2017, Amendment No. 2 thereto effective January 1, 2018, Amendment No. 3 thereto effective April 1, 2018, Amendment No. 4 thereto effective December 4, 2018, Amendment No. 5 thereto effective January 1, 2019 and Amendment No. 6 thereto effective January 1, 2019. (Designated in Form 10-Q for the quarter ended June 30, 2016, File No. 1-3526, as Exhibit 10(a)1, in Form 10-K for the year ended December 31, 2016, File No. 1-3526, as Exhibit 10(a)18, in Form 10-K for the year ended December 31, 2017, File No. 1-3526, as Exhibit 10(a)16, in Form 10-Q for the quarter ended March 31, 2018, File No. 1-3526, as Exhibit 10(a)1, in Form 10-K for the year ended December 31, 2018, File No. 1-3526, as Exhibit 10(a)23, in Form 10-K for the year ended December 31, 2018, File No. 1-3526, as Exhibit 10(a)24, and in Form 10-K for the year ended December 31, 2019, File No. 1-3526, as Exhibit 10(a)24.)
#(a)4
The Southern Company Supplemental Benefit Plan, Amended and Restated effective as of June 30, 2016, Amendment No. 1 thereto effective January 1, 2017, Amendment No. 2 thereto effective January 1, 2018, Amendment No. 3 thereto effective April 1, 2018, Amendment No. 4 thereto dated December 14, 2018, Amendment No. 5 thereto effective January 1, 2019, Amendment No. 6 thereto effective January 1, 2019, Amendment No. 7 thereto effective June 30, 2016, and Amendment No. 8 thereto effective July 1, 2021. (Designated in Form 10-Q for the quarter ended June 30, 2016, File No. 1-3526, as Exhibit 10(a)2, in Form 10-K for the year ended December 31, 2016, File No. 1-3526, as Exhibit 10(a)19, in Form 10-K for the year ended December 31, 2017, File No. 1-3526, as Exhibit 10(a)17, in Form 10-Q for the quarter ended March 31, 2018, File No. 1-3526, as Exhibit 10(a)2, in Form 10-K for the year ended December 31, 2018, File No. 1-3526, as Exhibit 10(a)25, in Form 10-K for the year ended December 31, 2018, File No. 1-3526, as Exhibit 10(a)26 in Form 10-K for the year ended December 31, 2019, File No. 1-3526, as Exhibit 10(a)23, in Form 10-K for the year ended December 31, 2020, File No. 1-3526, as Exhibit 10(a) 25, and in Form 10-Q for the quarter ended March 31, 2022, File No. 1-3526, as Exhibit 10(a)5.)
#(a)5
Amended and Restated Southern Company Change in Control Benefits Protection Plan effective August 15, 2022. (Designated in Form 8-K dated August 15, 2022, File No. 1-3526, as Exhibit 10.1.)
E-6

    Table of Contents                                Index to Financial Statements
#(a)6
Deferred Compensation Trust Agreement for Directors of Southern Company and its Subsidiaries, Amended and Restated effective January 1, 2001, between Delaware Charter Guarantee & Trust Company, Southern Company, SCS, Alabama Power, Georgia Power, Mississippi Power, Southern Linc, Southern Company Energy Solutions, LLC, and Southern Nuclear and First Amendment thereto effective January 1, 2009. (Designated in Form 10-K for the year ended December 31, 2000, File No. 1-3526, as Exhibit 10(a)103 and in Form 10-K for the year ended December 31, 2008, File No. 1-3526, as Exhibit 10(a)16.)
#(a)7
Amended and Restated Deferred Stock Trust Agreement for Directors of Southern Company and its Subsidiaries, Amended and Restated effective December 16, 2020, by and between Southern Company and Delaware Charter Guarantee & Trust Company. (Designated in Form 10-K for the year ended December 31, 2020, File No. 1-3526, as Exhibit 10(a)9.)
#(a)8
Amended and Restated Deferred Cash Compensation Trust Agreement for Directors of Southern Company and its Subsidiaries, Amended and Restated effective December 16, 2020, by and between Southern Company and Delaware Charter Guarantee & Trust Company. (Designated in Form 10-K for the year ended December 31, 2020, File No. 1-3526, as Exhibit 10(a)10.)
#(a)9
Southern Company Senior Executive Change in Control Severance Plan, Amended and Restated effective August 15, 2022. (Designated in Form 8-K dated August 15, 2022, File No. 1-3526, as Exhibit 10.2.)
#(a)10
Southern Company Executive Change in Control Severance Plan, Amended and Restated effective August 15, 2022. (Designated in Form 10-Q for the quarter ended September 30, 2022, File No. 1-3526, as Exhibit 10(a)3.)
#(a)11
Form of Terms for Named Executive Officer Equity Awards Granted under the Southern Company 2021 Equity and Incentive Compensation Plan. (Designated in Form 10-Q for the quarter ended March 31, 2022, File No. 1-3526, as Exhibit 10(a)1).
(a)12
The Southern Company Employee Savings Plan, Amended and Restated effective January 1, 2018, First Amendment thereto dated December 7, 2018, Second Amendment thereto dated January 29, 2019, Third Amendment thereto dated December 4, 2019, Fourth Amendment thereto dated November 27, 2020, Fifth Amendment thereto effective July 1, 2021, Sixth Amendment thereto effective July 1, 2021, Seventh Amendment thereto dated December 23, 2022, Eighth Amendment thereto dated December 13, 2023, and Ninth Amendment thereto dated December 16, 2024. (Designated in Post-Effective Amendment No. 1 to Form S-8, File No. 333-212783 as Exhibit 4.3, in Form 10-K for the year ended December 31, 2019, File No. 1-3526, as Exhibit 10(a)25, in Form 10-K for the year ended December 31, 2019, File No. 1-3526, as Exhibit 10(a)26, in Form 10-K for the year ended December 31, 2019, File No. 1-3526, as Exhibit 10(a)27, in Form 10-K for the year ended December 31, 2020, File No. 1-3526, as Exhibit 10(a)26, in Form 10-Q for the quarter ended March 31, 2022, File No. 1-3526, as Exhibit 10(a)2, in Form 10-Q for the quarter ended March 31, 2022, File No. 1-3526, as Exhibit 10(a)3, in Form 10-K for the year ended December 31, 2022, File No. 1-3526, as Exhibit 10(a)17, in Form 10-K for the year ended December 31, 2023, File No. 1-3526, as Exhibit 10(a)17, and in Form 10-K for the year ended December 31, 2024, File No. 1-3526, as Exhibit 10(a)13.)
*(a)13
Tenth amendment to the Southern Company Employee Savings Plan, dated December 12, 2025.
#(a)14
Deferred Compensation Agreement between Southern Company, SCS, Georgia Power, and Christopher C. Womack, effective December 10, 2008. (Designated in Form 10-Q for the quarter ended September 30, 2022, File No. 1-3526, as Exhibit 10(a)4.)
#(a)15
The Southern Company Equity and Incentive Compensation Plan, effective May 26, 2021. (Designated in Form 8-K dated May 26, 2021, File No. 1-3526, as Exhibit 10.1.)
*#(a)16
Consulting Agreement between SCS and Daniel S. Tucker dated August 11, 2025.
*#(a)17
Deferred Compensation Agreement among Southern Company, SCS, and David P. Poroch effective January 4, 2012.
Alabama Power
(b)1
Intercompany Interchange Contract as revised effective May 1, 2007, among Alabama Power, Georgia Power, Gulf Power Company, Mississippi Power, Southern Power Company, and SCS and Appendix A thereto dated as of January 1, 2019. (Designated in Form 10-Q for the quarter ended March 31, 2007, File No. 1-3164, as Exhibit 10(b)5 and in Form 10-K for the year ended December 31, 2018, File No. 1-3164, as Exhibit 10(b)2.)
E-7

    Table of Contents                                Index to Financial Statements
Georgia Power
(c)1
Intercompany Interchange Contract as revised effective May 1, 2007, among Alabama Power, Georgia Power, Gulf Power Company, Mississippi Power, Southern Power Company, and SCS and Appendix A thereto dated as of January 1, 2019. See Exhibit 10(b)1 herein.
(c)2
Revised and Restated Integrated Transmission System Agreement dated as of November 12, 1990, between Georgia Power and OPC. (Designated in Form 10-K for the year ended December 31, 1990, File No. 1-6468, as Exhibit 10(g).)
(c)3
Revised and Restated Integrated Transmission System Agreement between Georgia Power and Dalton dated as of December 7, 1990. (Designated in Form 10-K for the year ended December 31, 1990, File No. 1-6468, as Exhibit 10(gg).)
(c)4
Revised and Restated Integrated Transmission System Agreement between Georgia Power and MEAG Power dated as of December 7, 1990. (Designated in Form 10-K for the year ended December 31, 1990, File No. 1-6468, as Exhibit 10(hh).)
Mississippi Power
(d)1
Intercompany Interchange Contract as revised effective May 1, 2007, among Alabama Power, Georgia Power, Gulf Power Company, Mississippi Power, Southern Power Company, and SCS and Appendix A thereto dated as of January 1, 2019. See Exhibit 10(b)1 herein.
Southern Power
(e)1
Intercompany Interchange Contract as revised effective May 1, 2007, among Alabama Power, Georgia Power, Gulf Power Company, Mississippi Power, Southern Power Company, and SCS and Appendix A thereto dated as of January 1, 2019. See Exhibit 10(b)1 herein.
Southern Company Gas
(f)1
Final Allocation Agreement dated January 3, 2008. (Designated in Form 10-K for the year ended December 31, 2007, File No. 1-7296, as Exhibit 10.15.)
(19)
Insider Trading Policies and Procedures
Southern Company

(a)
Prohibition of Securities Trading Policy. (Designated in Form 10-K for the year ended December 31, 2024, File No. 1-3526, as Exhibit 19(a).)
Alabama Power

(b)
Prohibition of Securities Trading Policy. (Designated in Form 10-K for the year ended December 31, 2024, File No. 1-3526, as Exhibit 19(b).)
Georgia Power

(c)
Prohibition of Securities Trading Policy. (Designated in Form 10-K for the year ended December 31, 2024, File No. 1-3526, as Exhibit 19(c).)
Mississippi Power

(d)
Prohibition of Securities Trading Policy. (Designated in Form 10-K for the year ended December 31, 2024, File No. 1-3526, as Exhibit 19(d).)
Southern Power

(e)
Prohibition of Securities Trading Policy. (Designated in Form 10-K for the year ended December 31, 2024, File No. 1-3526, as Exhibit 19(e).)
Southern Company Gas

(f)
Prohibition of Securities Trading Policy. (Designated in Form 10-K for the year ended December 31, 2024, File No. 1-3526, as Exhibit 19(f).)
(21)Subsidiaries of Registrants
Southern Company
*(a)
Subsidiaries of Registrant.
Alabama Power
Omitted pursuant to General Instruction I(2)(b) of Form 10-K.
Georgia Power
Omitted pursuant to General Instruction I(2)(b) of Form 10-K.
E-8

    Table of Contents                                Index to Financial Statements
Mississippi Power
Omitted pursuant to General Instruction I(2)(b) of Form 10-K.
Southern Power
Omitted pursuant to General Instruction I(2)(b) of Form 10-K.
Southern Company Gas
Omitted pursuant to General Instruction I(2)(b) of Form 10-K.
(23)Consents of Experts and Counsel
Southern Company
*(a)
Consent of Deloitte & Touche LLP.
Alabama Power
*(b)
Consent of Deloitte & Touche LLP.
Georgia Power
*(c)
Consent of Deloitte & Touche LLP.
Mississippi Power
*(d)
Consent of Deloitte & Touche LLP.
Southern Power
*(e)
Consent of Deloitte & Touche LLP.
Southern Company Gas
*(f)
Consent of Deloitte & Touche LLP.
*(f)
Consent of BDO USA, P.C.
(24)Powers of Attorney and Resolutions
Southern Company
*(a)1
Power of Attorney and resolution.
Alabama Power
*(b)1
Power of Attorney and resolution.
Georgia Power
*(c)1
Power of Attorney and resolution.
Mississippi Power
*(d)1
Power of Attorney and resolution.
Southern Power
*(e)1
Power of Attorney and resolution.
Southern Company Gas
*(f)1
Power of Attorney and resolution.
(31)Section 302 Certifications
Southern Company
*(a)1
Certificate of Southern Company's Chief Executive Officer required by Section 302 of the Sarbanes-Oxley Act of 2002.
*(a)2
Certificate of Southern Company's Chief Financial Officer required by Section 302 of the Sarbanes-Oxley Act of 2002.
Alabama Power
*(b)1
Certificate of Alabama Power's Chief Executive Officer required by Section 302 of the Sarbanes-Oxley Act of 2002.
*(b)2
Certificate of Alabama Power's Chief Financial Officer required by Section 302 of the Sarbanes-Oxley Act of 2002.
E-9

    Table of Contents                                Index to Financial Statements
Georgia Power
*(c)1
Certificate of Georgia Power's Chief Executive Officer required by Section 302 of the Sarbanes-Oxley Act of 2002.
*(c)2
Certificate of Georgia Power's Chief Financial Officer required by Section 302 of the Sarbanes-Oxley Act of 2002.
Mississippi Power
*(d)1
Certificate of Mississippi Power's Chief Executive Officer required by Section 302 of the Sarbanes-Oxley Act of 2002.
*(d)2
Certificate of Mississippi Power's Chief Financial Officer required by Section 302 of the Sarbanes-Oxley Act of 2002.
Southern Power
*(e)1
Certificate of Southern Power Company's Chief Executive Officer required by Section 302 of the Sarbanes-Oxley Act of 2002.
*(e)2
Certificate of Southern Power Company's Chief Financial Officer required by Section 302 of the Sarbanes-Oxley Act of 2002.
Southern Company Gas
*(f)1
Certificate of Southern Company Gas' Chief Executive Officer required by Section 302 of the Sarbanes-Oxley Act of 2002.
*(f)2
Certificate of Southern Company Gas' Chief Financial Officer required by Section 302 of the Sarbanes-Oxley Act of 2002.
(32)Section 906 Certifications
Southern Company
*(a)
Certificate of Southern Company's Chief Executive Officer and Chief Financial Officer required by Section 906 of the Sarbanes-Oxley Act of 2002.
Alabama Power
*(b)
Certificate of Alabama Power's Chief Executive Officer and Chief Financial Officer required by Section 906 of the Sarbanes-Oxley Act of 2002.
Georgia Power
*(c)
Certificate of Georgia Power's Chief Executive Officer and Chief Financial Officer required by Section 906 of the Sarbanes-Oxley Act of 2002.
Mississippi Power
*(d)
Certificate of Mississippi Power's Chief Executive Officer and Chief Financial Officer required by Section 906 of the Sarbanes-Oxley Act of 2002.
Southern Power
*(e)
Certificate of Southern Power Company's Chief Executive Officer and Chief Financial Officer required by Section 906 of the Sarbanes-Oxley Act of 2002.
Southern Company Gas
*(f)
Certificate of Southern Company Gas' Chief Executive Officer and Chief Financial Officer required by Section 906 of the Sarbanes-Oxley Act of 2002.
(97)
Policy Relating to Recovery of Erroneously Awarded Compensation
Southern Company

(a)
The Southern Company and Covered Subsidiaries Compensation Recoupment Policy, effective December 1, 2023. (Designated in Form 10-K for the year ended December 31, 2023, File No. 1-3526, as Exhibit 97(a).)
Georgia Power
(c)
The Southern Company and Covered Subsidiaries Compensation Recoupment Policy, effective December 1, 2023. See Exhibit 97(a) herein.
Southern Power
(e)
The Southern Company and Covered Subsidiaries Compensation Recoupment Policy, effective December 1, 2023. See Exhibit 97(a) herein.
E-10

    Table of Contents                                Index to Financial Statements
(101)Interactive Data Files
*INSXBRL Instance Document – The instance document does not appear in the interactive data file because its XBRL tags are embedded within the inline XBRL document.
*SCHXBRL Taxonomy Extension Schema Document
*CALXBRL Taxonomy Calculation Linkbase Document
*DEFXBRL Definition Linkbase Document
*LABXBRL Taxonomy Label Linkbase Document
*PREXBRL Taxonomy Presentation Linkbase Document
(104)Cover Page Interactive Data File
*Formatted as inline XBRL with applicable taxonomy extension information contained in Exhibits 101.
E-11

    Table of Contents                                Index to Financial Statements
THE SOUTHERN COMPANY
SIGNATURES
Pursuant to the requirements of Section 13 or 15(d) of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized. The signature of the undersigned company shall be deemed to relate only to matters having reference to such company and any subsidiaries thereof.
THE SOUTHERN COMPANY
By:Christopher C. Womack
Chairman, President, and Chief Executive Officer
By:/s/ Melissa K. Caen
(Melissa K. Caen, Attorney-in-fact)
Date:February 18, 2026
Pursuant to the requirements of the Securities Exchange Act of 1934, this report has been signed below by the following persons on behalf of the registrant and in the capacities and on the dates indicated. The signature of each of the undersigned shall be deemed to relate only to matters having reference to the above-named company and any subsidiaries thereof.

Christopher C. Womack
Chairman, President, and Chief Executive Officer
(Principal Executive Officer)
David P. Poroch
Executive Vice President, Chief Financial Officer, and Treasurer
(Principal Financial Officer)
Matthew M. Kim
Comptroller and Chief Accounting Officer
(Principal Accounting Officer)
Directors:
Janaki Akella
Shantella E. Cooper
Anthony F. Earley, Jr.
James O. Etheredge
David J. Grain
Donald M. James
John D. Johns
Dale E. Klein
David E. Meador
William G. Smith, Jr.
Kristine L. Svinicki
Lizanne Thomas
John M. Turner, Jr.
By:/s/ Melissa K. Caen
(Melissa K. Caen, Attorney-in-fact)
Date: February 18, 2026



    Table of Contents                                Index to Financial Statements
ALABAMA POWER COMPANY
SIGNATURES
Pursuant to the requirements of Section 13 or 15(d) of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized. The signature of the undersigned company shall be deemed to relate only to matters having reference to such company and any subsidiaries thereof.
ALABAMA POWER COMPANY
By:J. Jeffrey Peoples
Chairman, President, and Chief Executive Officer
By:/s/ Melissa K. Caen
(Melissa K. Caen, Attorney-in-fact)
Date:February 18, 2026
Pursuant to the requirements of the Securities Exchange Act of 1934, this report has been signed below by the following persons on behalf of the registrant and in the capacities and on the dates indicated. The signature of each of the undersigned shall be deemed to relate only to matters having reference to the above-named company and any subsidiaries thereof.

J. Jeffrey Peoples
Chairman, President, and Chief Executive Officer
(Principal Executive Officer)
Moses H. Feagin
Executive Vice President, Chief Financial Officer, and Treasurer
(Principal Financial Officer)
Anita D. Allcorn
Senior Vice President and Comptroller
(Principal Accounting Officer)
Directors:
Angus R. Cooper, III
Lee C. Goodloe
O. B. Grayson Hall, Jr.
Larry R. Howell, Jr.
Anthony A. Joseph
Barbara J. Knight
Kevin B. Savoy
Charisse D. Stokes
Phillip M. Webb
William B. Wilson
By:/s/ Melissa K. Caen
(Melissa K. Caen, Attorney-in-fact)
Date: February 18, 2026


Supplemental Information to be Furnished with Reports Filed Pursuant to Section 15(d) of the Act by Registrants Which Have Not Registered Securities Pursuant to Section 12 of the Act:

Alabama Power is not required to send an annual report or proxy statement to its sole shareholder and parent company, The Southern Company, and will not prepare such a report after filing this Annual Report on Form 10-K for fiscal year 2025. Accordingly, Alabama Power will not file an annual report with the Securities and Exchange Commission.


    Table of Contents                                Index to Financial Statements
GEORGIA POWER COMPANY
SIGNATURES
Pursuant to the requirements of Section 13 or 15(d) of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized. The signature of the undersigned company shall be deemed to relate only to matters having reference to such company and any subsidiaries thereof.
GEORGIA POWER COMPANY
By:Kimberly S. Greene
Chairman, President, and Chief Executive Officer
By:/s/ Melissa K. Caen
(Melissa K. Caen, Attorney-in-fact)
Date:February 18, 2026
Pursuant to the requirements of the Securities Exchange Act of 1934, this report has been signed below by the following persons on behalf of the registrant and in the capacities and on the dates indicated. The signature of each of the undersigned shall be deemed to relate only to matters having reference to the above-named company and any subsidiaries thereof.

Kimberly S. Greene
Chairman, President, and Chief Executive Officer
(Principal Executive Officer)
Tyler M. Cook
Senior Vice President, Chief Financial Officer, and Treasurer
(Principal Financial and Accounting Officer)
Adam D. Houston
Vice President and Comptroller
(Principal Accounting Officer)
Directors:
Jill Bullock
Mark L. Burns
Andrew W. Evans
Steven R. Ewing
Thomas M. Holder
Virgil R. Miller
Valerie Montgomery Rice
Tonialo Smith
Kessel D. Stelling, Jr.
By:/s/ Melissa K. Caen
(Melissa K. Caen, Attorney-in-fact)
Date: February 18, 2026



    Table of Contents                                Index to Financial Statements
MISSISSIPPI POWER COMPANY
SIGNATURES
Pursuant to the requirements of Section 13 or 15(d) of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized. The signature of the undersigned company shall be deemed to relate only to matters having reference to such company and any subsidiaries thereof.
MISSISSIPPI POWER COMPANY
By:Pedro P. Cherry
Chairman, President, and Chief Executive Officer
By:/s/ Melissa K. Caen
(Melissa K. Caen, Attorney-in-fact)
Date:February 18, 2026
Pursuant to the requirements of the Securities Exchange Act of 1934, this report has been signed below by the following persons on behalf of the registrant and in the capacities and on the dates indicated. The signature of each of the undersigned shall be deemed to relate only to matters having reference to the above-named company and any subsidiaries thereof.

Pedro P. Cherry
Chairman, President, and Chief Executive Officer
(Principal Executive Officer)
Matthew P. Grice
Vice President, Treasurer, and Chief Financial Officer
(Principal Financial Officer)
Pascal B. Gill
Comptroller
(Principal Accounting Officer)
Directors:
Augustus Leon Collins
Thomas M. Duff
Mary S. Graham
David B. Hall
Mark E. Keenum
Kara R. Wilkinson
Camille Scales Young
By:/s/ Melissa K. Caen
(Melissa K. Caen, Attorney-in-fact)
Date: February 18, 2026


Supplemental Information to be Furnished with Reports Filed Pursuant to Section 15(d) of the Act by Registrants Which Have Not Registered Securities Pursuant to Section 12 of the Act:

Mississippi Power is not required to send an annual report or proxy statement to its sole shareholder and parent company, The Southern Company, and will not prepare such a report after filing this Annual Report on Form 10-K for fiscal year 2025. Accordingly, Mississippi Power will not file an annual report with the Securities and Exchange Commission.


    Table of Contents                                Index to Financial Statements
SOUTHERN POWER COMPANY
SIGNATURES
Pursuant to the requirements of Section 13 or 15(d) of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized. The signature of the undersigned company shall be deemed to relate only to matters having reference to such company and any subsidiaries thereof.
SOUTHERN POWER COMPANY
By:Christopher Cummiskey
Chairman and Chief Executive Officer
By:/s/ Melissa K. Caen
(Melissa K. Caen, Attorney-in-fact)
Date:February 18, 2026
Pursuant to the requirements of the Securities Exchange Act of 1934, this report has been signed below by the following persons on behalf of the registrant and in the capacities and on the dates indicated. The signature of each of the undersigned shall be deemed to relate only to matters having reference to the above-named company and any subsidiaries thereof.

Christopher Cummiskey
Chairman and Chief Executive Officer
(Principal Executive Officer)
Gary Kerr
Senior Vice President, Chief Financial Officer, and Treasurer
(Principal Financial Officer)
Jelena Andrin
Vice President and Comptroller
(Principal Accounting Officer)
Directors:
Bryan D. Anderson
Stanley W. Connally, Jr.
Sloane N. Drake
James Y. Kerr, II
David P. Poroch
Sterling A. Spainhour
Christopher C. Womack
By:/s/ Melissa K. Caen
(Melissa K. Caen, Attorney-in-fact)
Date: February 18, 2026



    Table of Contents                                Index to Financial Statements
SOUTHERN COMPANY GAS
SIGNATURES
Pursuant to the requirements of Section 13 or 15(d) of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized. The signature of the undersigned company shall be deemed to relate only to matters having reference to such company and any subsidiaries thereof.
SOUTHERN COMPANY GAS
By:James Y. Kerr II
Chairman, President, and Chief Executive Officer
By:/s/ Melissa K. Caen
(Melissa K. Caen, Attorney-in-fact)
Date:February 18, 2026
Pursuant to the requirements of the Securities Exchange Act of 1934, this report has been signed below by the following persons on behalf of the registrant and in the capacities and on the dates indicated. The signature of each of the undersigned shall be deemed to relate only to matters having reference to the above-named company and any subsidiaries thereof.

James Y. Kerr II
Chairman, President, and Chief Executive Officer
(Principal Executive Officer)
Grace A. Kolvereid
Executive Vice President, Chief Financial Officer, and Treasurer
(Principal Financial Officer)
Sarah P. Adams
Senior Vice President and Comptroller
(Principal Accounting Officer)
Directors:
Sandra N. Bane
Stephen A. Edwards
Vanessa C. Harrison
Bradley J. Henderson
Norman G. Holmes
J. Bret Lane
Eric S. Smith
A. Benjamin Spencer
By:/s/ Melissa K. Caen
(Melissa K. Caen, Attorney-in-fact)
Date: February 18, 2026


Supplemental Information to be Furnished with Reports Filed Pursuant to Section 15(d) of the Act by Registrants Which Have Not Registered Securities Pursuant to Section 12 of the Act:

Southern Company Gas is not required to send an annual report or proxy statement to its sole shareholder and parent company, The Southern Company, and will not prepare such a report after filing this Annual Report on Form 10-K for fiscal year 2025. Accordingly, Southern Company Gas will not file an annual report with the Securities and Exchange Commission.

FAQ

What is Southern Company (SO) planning to invest in 2026?

Southern Company plans about $15.9 billion of construction spending in 2026. Roughly $12.6 billion targets the electric system, including new generation, transmission, distribution, nuclear fuel, and environmental compliance, with the remainder at Southern Power, Southern Company Gas, and other subsidiaries.

How much new generation is Georgia Power planning according to the 10-K for SO?

Georgia Power’s certified projects from recent IRP orders total roughly 13 GW, including about 9 GW of new generation and battery storage. Certified construction and related transmission investments for 2026 include approximately $3.1 billion tied to these IRP-approved projects.

How many customers does Southern Company (SO) serve in its electric utilities?

The traditional electric operating companies serve about 4.6 million retail electric customers. At December 31, 2025, Alabama Power, Georgia Power, and Mississippi Power collectively supplied roughly 3,986 thousand residential, 576 thousand commercial, and 17 thousand industrial accounts, plus other classifications.

What is the scale of Southern Company Gas operations within SO?

Southern Company Gas serves around 4.4 million customers across Illinois, Georgia, Virginia, and Tennessee. It operates approximately 77,900 miles of pipelines and 14 storage facilities with about 157 Bcf of capacity, supplying residential, commercial, and industrial users.

How is data center growth affecting Southern Company (SO)?

Data centers and other large load customers are driving significant projected electricity demand growth. Since 2023, the traditional electric operating companies have signed contracts covering about 9 GW of new load, with service starting through 2028 and supporting large new generation and transmission investments.

What forward-looking risks does Southern Company (SO) highlight?

Southern Company cites risks from regulatory and environmental changes, cost overruns on major projects, data center-driven load uncertainty, fuel and commodity prices, cyber and physical security events, extreme weather, credit markets, and nuclear operations, all of which could materially affect future earnings and capital requirements.

Southern

NYSE:SO

SO Rankings

SO Latest News

SO Latest SEC Filings

SO Stock Data

100.24B
1.10B
Utilities - Regulated Electric
Electric Services
Link
United States
ATLANTA