WASHINGTON, D.C. 20549
Indicate by check mark whether the registrant
files or will file annual reports under cover of Form 20-F or Form 40-F:
Pursuant to the requirements of the Securities
Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.
Suncor Energy Inc. Statement of Contingent Resources
dated March 30, 2026
Statement
of Contingent Resources
This
document contains information relating to estimates of contingent resources of Suncor Energy Inc. (Suncor) as at December 31, 2025.
This document is dated March 30, 2026.
The
contingent resources data included in this document is based on evaluations conducted by GLJ Ltd. (GLJ), contained in its report dated
March 27, 2026 with an effective date of December 31, 2025 (the GLJ Contingent Resources Report). GLJ is an independent qualified
reserves evaluator as defined in National Instrument 51-101 – Standards of Disclosure for Oil and Gas Activities (NI 51-101).
Suncor's contingent resources have been evaluated in accordance with NI 51-101 and the most recent publication of the Canadian Oil and
Gas Evaluation Handbook (COGE Handbook).
GLJ
has evaluated Suncor's contingent resources at its in situ and mining properties located within the Athabasca oil sands region in Alberta.
The in situ properties evaluated were Firebag, Lewis, MacKay River, Meadow Creek and Chard, and the mining properties evaluated were
Syncrude (Non-Producing Leases), Lease 23 and Audet.
All
of the properties evaluated by GLJ are anticipated to be developed using established technology, namely, for in situ properties, using
SAGD technology in sandstone reservoirs, and for mining properties, using open-pit mining operations, consistent with Suncor’s
current commercial developments within the Athabasca region. As such, there are no technical contingencies preventing the future classification
of these volumes as reserves.
Suncor
reports its contingent resources using the best estimate case, reflecting an equal likelihood that the actual remaining quantities recovered
would be greater than or less than the best estimate. Expressed probabilistically, there is a 50% probability that the actual quantities
recovered would equal or exceed the best estimate.
There
are numerous uncertainties inherent in estimating quantities of contingent resources, and such estimates involve additional risks compared
to estimates of reserves. There is uncertainty that it will be commercially viable to produce any portion of the contingent resources.
There is no guarantee that the estimates for synthetic crude oil (SCO) and bitumen contingent resources provided herein will be recovered.
Actual SCO and bitumen volumes recovered may be greater than or less than the estimates provided herein. Readers should review the heading
"Terminology" below and the definitions and information contained in the notes in the following tables.
Contingent
Resources Estimates
The
following tables provide the risked and unrisked contingent resources volumes (best estimate) attributable to Suncor’s in situ
properties and mining properties, as at December 31, 2025, contained in the GLJ Contingent Resources Report. The evaluations were
prepared using the price forecast derived from the average of forecasts developed by GLJ (dated January 1, 2026), Sproule Associates
Limited (dated December 31, 2025) and McDaniel & Associates Consultants Ltd. (dated January 1, 2026), all of whom
are independent qualified reserves evaluators. The following tables do not include the proved and probable reserves volumes and values
shown in the “Statement of Reserves Data and Other Oil and Gas Information” in Suncor’s Annual Information Form for
the year ended December 31, 2025.
Contingent
Reserves Tables and Notes
Summary
of Risked and Unrisked Oil and Gas Contingent Resources
As
at December 31, 2025
(forecast
prices and costs)
| | |
Contingent
Resources Best Estimate (mmbbl) | |
| | |
Risked | | |
Unrisked | |
| | |
Gross | | |
Net | | |
Gross | | |
Net | |
| Resources
Project Maturity Sub-Class | |
| | | |
| | | |
| | | |
| | |
| In
Situ – Bitumen(1) | |
| | | |
| | | |
| | | |
| | |
| Development
Pending | |
| 2,468 | | |
| 1,895 | | |
| 2,782 | | |
| 2,137 | |
| Development
Unclarified | |
| 15,204 | | |
| 12,180 | | |
| 19,675 | | |
| 15,759 | |
| Total
In Situ | |
| 17,672 | | |
| 14,075 | | |
| 22,457 | | |
| 17,896 | |
| Mining
- SCO(2) | |
| | | |
| | | |
| | | |
| | |
| Development
Pending | |
| 97 | | |
| 82 | | |
| 102 | | |
| 86 | |
| Development
Unclarified | |
| 5,527 | | |
| 4,912 | | |
| 7,807 | | |
| 6,945 | |
| Total
Mining | |
| 5,624 | | |
| 4,994 | | |
| 7,909 | | |
| 7,031 | |
| Total | |
| 23,296 | | |
| 19,069 | | |
| 30,366 | | |
| 24,927 | |
| | |
Project
Evaluation Status | |
Project
Chance of Commerciality (%) | |
Estimated
Risked Capital to Reach First Commercial Production ($ Millions) (3)(4) | | |
Estimated
Timing of First Commercial Production |
| Resources
Project Maturity Sub-Class | |
| |
| |
| | | |
|
| In
Situ – Bitumen(1) | |
| |
| |
| | | |
|
| Development
Pending | |
Development
Study | |
89% | |
| 2,929 | | |
2033 |
| Development
Unclarified | |
Pre-Development | |
77% | |
| 9,189 | | |
2034+ |
| Total
In Situ | |
| |
| |
| 12,118 | | |
|
| Mining
- SCO(2) | |
| |
| |
| | | |
|
| Development
Pending | |
Development
Study | |
95% | |
| 54 | | |
2038 |
| Development
Unclarified | |
Pre-Development | |
71% | |
| 15,522 | | |
2035+ |
| Total
Mining | |
| |
| |
| 15,576 | | |
|
| Total | |
| |
| |
| 27,694 | | |
|
| (1) | The
figures presented include Suncor’s 75% interest in Meadow Creek, 77.8% interest in
the OSLO portion of Lewis, and varying interests between 25% to 50% in Chard. See “Project
– Characterization – In Situ properties” below. |
| (2) | The
figures presented include Suncor's 58.74% interest in Syncrude, which directly owns the properties
underlying the Syncrude (Non-Producing Leases) and associated contingent resources. See "Project
Characterization – Mining properties" below. |
| (3) | The
estimates of capital and timing to reach first commercial production are prepared by GLJ
and are based on variable factors and assumptions. They are subject to numerous risks and
uncertainties associated with the recovery of such resources, including many factors beyond
Suncor's control. Actual results may vary significantly from these estimates and such variances
could be material. |
| (4) | Capital
presented is risked by chance of commerciality, uninflated and undiscounted. |
The
contingent resources have been risked for the chance of commerciality (CoC) in accordance with section 1.3.7.3 of the COGE Handbook,
which is equal to the 'chance of development' multiplied by the 'chance of discovery'. The 'chance of discovery' in respect of contingent
resources is equal to 1, and therefore the CoC for contingent resources is equal to the 'chance of development'.
The
contingent resources are evaluated based on the same fiscal conditions used in the assessment of reserves, and as such, are forecasted
to be economic. Development-related contingencies preventing the contingent resources from being classified as reserves include: (i) additional
delineation; (ii) regulatory application submissions and approvals; (iii) firm development plans and company commitment including
confirmation of corporate intent to proceed with the defined expansion plans; and (iv) final project design and sanctioning.
Project
Characterization
In
situ properties
The
in situ properties evaluated by GLJ were Firebag, Lewis, MacKay River, Meadow Creek and Chard. Suncor holds a 100% interest in each of
these properties, except for a 75% interest in Meadow Creek, 77.8% interest in the OSLO portion of Lewis, and interests in Chard varying
from 25%-50%. Each of these properties is anticipated to be developed using established SAGD technology to produce bitumen from sandstone
formations. Estimates do not include the use of Expanding Solvent SAGD (ES-SAGD) or Enhanced Bitumen Recovery Technology (EBRT) which
could potentially improve production rates, steam-to-oil ratio and GHG emissions intensity.
Mining
properties
The
mining properties evaluated by GLJ were Syncrude (Non-Producing Leases), Lease 23 and Audet. Suncor’s interest in the Syncrude
(Non-Producing Leases) is owned indirectly through Suncor’s 58.74% interest in Syncrude. Each of these properties is anticipated
to be developed using established open-pit mining processes to extract bitumen from oil sands.
Risks
and Significant Positive and Negative Factors Attributable to Contingent Resources Estimates
Significant
positive factors relevant to the contingent resources estimates include Suncor’s established history of developing oil sands resources
in the region, including leveraging learnings and technology developments from past and ongoing projects and the proximity of the contingent
resources to existing Suncor operations, enabling integration with current infrastructure. Additional positive factors include Suncor’s
strong balance sheet and investment grade credit ratings, which support its ability to access the capital required to develop the contingent
resources, and the proximity of the contingent resources to established logistics and marketing channels.
Significant
negative factors relevant to the contingent resources estimates and risks to Suncor’s ability to recover the contingent resources
include risks related to required regulatory approvals, potential changes to government and regulatory policies, availability of skilled
labour and material supply and prolonged periods of low commodity prices which could impact the economic viability of development of
such contingent resources.
Terminology
The
resources estimates presented herein are based on the definitions and guidelines contained in the COGE Handbook. A summary of these definitions
is set forth below.
Best
estimate is a classification of estimated resources described in the COGE Handbook as being considered to be the best estimate of
the quantity that will be recovered. It represents equal likelihood that the actual remaining quantities recovered will be greater or
less than the best estimate. If probabilistic methods are used, there should be a 50% probability that the quantities actually recovered
will equal or exceed the best estimate.
Contingent
resources are those quantities of petroleum estimated, as of a given date, to be potentially recoverable from known accumulations
using established technology or technology under development, but which are not currently considered to be commercially recoverable due
to one or more contingencies. Contingencies may include factors such as economic, legal, environmental, political, and regulatory matters,
or a lack of markets. It is also appropriate to classify as contingent resources the estimated discovered recoverable quantities associated
with a project in the early evaluation stage. Contingent resources are further classified in accordance with the level of certainty associated
with the estimates and may be sub-classified based on project maturity and/or characterized by their economic status. For a description
of the contingencies that must be met for Suncor's contingent resources to be classified as reserves, see the COGE Handbook "Resources
Classification".
Established
technology is a recovery method that has been proven to be successful in commercial applications in the subject reservoir and is
a prerequisite for assigning reserves. All of Suncor’s contingent resources are expected to be developed using established technology.
Risked
means that the applicable volumes or revenues have been adjusted for the probability of loss or failure in accordance with the COGE Handbook.
Unrisked
means that the applicable volumes or revenues have not been adjusted for the probability of loss or failure in accordance with the COGE
Handbook.
Suncor’s
contingent resources have been divided into the following project maturity sub-classes:
Development
pending resources sub-class is assigned to contingent resources for a particular project where resolution of the final conditions
for development is being actively pursued.
Development
unclarified resources sub-class is assigned to contingent resources for a particular project where the evaluation is incomplete and
there is ongoing activity to resolve remaining risks or uncertainties.