I&M, Google Filing to Support Reliability Through Demand Response Structure
Rhea-AI Summary
American Electric Power (NASDAQ: AEP) subsidiary Indiana Michigan Power (I&M) has filed a special joint contract with Google for a custom Demand Response structure to support capacity needs through clean generation. The agreement, filed with the Indiana Utilities Regulatory Commission on July 30, will enable Google to reduce or shift electricity demand during peak hours at its upcoming $2 billion Fort Wayne data center.
The partnership aims to manage electricity demand during peak times, potentially lowering overall energy costs for all I&M customers. Google's data center, announced in April 2024, represents one of Indiana's largest economic development projects. I&M currently serves over 600,000 customers with a diverse generation portfolio including 2,278 MW of nuclear, 450 MW of wind, and other renewable sources, with over 85% of energy delivered in 2023 being emission-free.
Positive
- None.
Negative
- Requires regulatory approval from IURC before implementation
- Additional strain on existing power infrastructure from new data center operations
News Market Reaction
On the day this news was published, AEP gained 1.25%, reflecting a mild positive market reaction.
Data tracked by StockTitan Argus on the day of publication.
The contract filed with the Indiana Utilities Regulatory Commission (IURC) on July 30 outlines a custom Demand Response structure, aligning with Google's operating capabilities. By participating in this program, Google will leverage new capabilities that allow it to reduce or shift electricity demand to carry out non-urgent tasks during hours when the electric grid is under less stress.
This offering will be used to reduce I&M's peak load in times of high energy demand, similar to programs currently available to residential and commercial/industrial customers. As a large load customer, Google's participation in this program boosts Indiana Michigan Power's ability to manage electricity demand during peak times. This helps lower overall energy costs, delivering savings to all I&M customers.
"I&M is excited to partner with Google to enable demand response capabilities at their new data center in
Weather serves as a primary contributor for changing energy demand throughout the year. As energy usage increases, so does the need to balance the demand on the power grid. Demand Response programs target the reduction or shift in energy used by customers out of the peak timeframe. Typically, peak hours, or the time of day when energy use is the highest, are most common on weekdays during the late afternoon and evening timeframe.
"As AI growth accelerates, we recognize the need to expand our demand response toolkit and develop capabilities specifically for machine learning workloads. Working closely with I&M to include load flexibility as part of the overall supply plan, we can support future power needs even where power generation and transmission are constrained. We want to be thoughtful about how we can continue to be a good grid citizen and see this as a vital tool for enabling responsible data center growth," said Amanda Peterson Corio, Global Head of Data Center Energy, Google.
The contract represents a significant commitment by Google to support sustainability and affordability of I&M's electric service, while reducing operational impacts it may have on peak energy needs. If approved by the IURC, this agreement will reduce I&M's long-term generation requirements and financial commitments to benefit all I&M customers.
Google announced plans to build a
Indiana Michigan Power (I&M) is headquartered in
About American Electric Power (AEP)
Our team at American Electric Power is committed to improving our customers' lives with reliable, affordable power. We are investing
News releases and other information about I&M are available at IndianaMichiganPower.com.
View original content to download multimedia:https://www.prnewswire.com/news-releases/im-google-filing-to-support-reliability-through-demand-response-structure-302520729.html
SOURCE American Electric Power