Montana-Dakota Utilities Announces Electric Service Agreement with Applied Digital for Proposed AI Factory
Rhea-AI Summary
Montana-Dakota Utilities, a subsidiary of MDU Resources (NYSE: MDU), signed an electric service agreement with Applied Digital (NASDAQ: APLD) to supply power to the proposed Polaris Forge 3 AI Factory near Center, North Dakota.
The campus could require 430 MW at full capacity, with Applied Digital paying energy purchase costs. Applied Digital targets initial operations in August 2027 and expects about 200 full-time jobs. Montana-Dakota Utilities already serves Applied Digital’s Polaris Forge 1 site, which has enabled $38.4 million in credits to North Dakota customers over three years. The agreement requires approval from the North Dakota Public Service Commission.
Positive
- ESA covers potential 430 MW load from Polaris Forge 3 AI campus
- Applied Digital responsible for purchasing energy costs under ESA
- Polaris Forge 3 expected to add about 200 full-time jobs regionally
- $38.4 million credited to North Dakota customers over past three years at Polaris Forge 1
Negative
- Electric service agreement requires approval by North Dakota Public Service Commission before power can be provided
News Market Reaction – APLD
In the Jun 23 session, APLD gained 0.15%, reflecting a mild positive market reaction. Argus tracked a trough of -3.0% from its starting point during tracking. Our momentum scanner triggered 12 alerts that day, indicating notable trading interest and price volatility.
Data tracked by StockTitan Argus on the day of publication.
Key Figures
Previous AI Reports
| Date | Event | Sentiment | 24h Move | Catalyst |
|---|---|---|---|---|
| Jun 08 | Delta Forge 2 lease | Positive | +3.4% | 210 MW, 15-year AI Factory lease adding multi‑billion base-term revenue. |
| Apr 23 | Delta Forge 1 tenant | Positive | +12.1% | 15-year, 300 MW hyperscaler lease lifting total contracted AI revenue. |
| Mar 04 | Base Electron power deal | Positive | +9.6% | 1.2 GW power project advancing generation to supply APLD AI campuses. |
| Jan 22 | Delta Forge 1 groundbreaking | Positive | -0.9% | Broke ground on 430 MW AI Factory campus with mid‑2027 launch goal. |
| Dec 18 | Macquarie dev loan | Positive | +8.6% | Development loan facility to fund early-stage AI Factory campuses. |
24h Move is the share-price change in the day after each event; other market factors may also have contributed.
APLD’s AI expansion announcements have typically led to positive share reactions, with only one prior AI event showing a mild divergence.
Key Terms
electric service agreement regulatory
ai factory technical
hyperscaler technical
colocation services technical
s&p smallcap 600 index financial
AI-generated analysis. How Rhea-AI works. Not financial advice.
At full capacity, the campus would require 430 megawatts of electricity. Under the ESA, Applied Digital would be responsible for the costs of purchasing the energy directly from the market or through other power supply arrangements. Applied Digital anticipates initial operations to commence in August 2027.
Polaris Forge 3 will expand Applied Digital's footprint in
"Polaris Forge 3 is another example of how Applied Digital is turning power into operational AI capacity through disciplined execution and long-term partnerships," said Wes Cummins, Chairman and CEO of Applied Digital. "This campus is expected to create approximately 200 full-time jobs, generate meaningful property tax revenue and support long-term growth across
Montana-Dakota Utilities currently serves Applied Digital at Polaris Forge 1, its AI Factory near
"This proposed project reflects the growing interest in
Approval of the ESA and other regulatory filings by the North Dakota Public Service Commission is required for the company to provide power under the agreement with Applied Digital.
About MDU Resources Group, Inc.
MDU Resources Group, Inc., a member of the S&P SmallCap 600 index, strives to deliver safe, reliable, cost-effective and environmentally responsible electric utility and natural gas distribution services to more than 1.2 million customers across the Pacific Northwest and Midwest. In addition to its utility operations, the company's pipeline business operates a more than 3,800-mile natural gas pipeline network and storage system, ensuring reliable energy delivery across the Northern Plains. With a legacy spanning over a century, MDU Resources remains focused on energizing lives for a better tomorrow. For more information about MDU Resources, visit www.mdu.com or contact the investor relations department at investor@mduresources.com.
About Applied Digital Corporation
Applied Digital (Nasdaq: APLD) named Best Data Center in the Americas 2025 by Datacloud — designs, builds, and operates high-performance, sustainably engineered data centers and colocation services for artificial intelligence, cloud, networking, and blockchain workloads. Headquartered in Dallas, TX, and founded in 2021, the company combines hyperscale expertise, proprietary waterless cooling, and rapid deployment capabilities to deliver secure, scalable compute at industry-leading speed and efficiency, while creating economic opportunities in underserved communities through its award-winning Polaris Forge AI Factory model. Learn more at applieddigital.com or follow @APLDdigital on X and LinkedIn.
Investor Contact: Brent Miller, treasurer, 701-530-1730 | ||
Media Contacts: | ||
MDU Resources: Byron Pfordte, director of integrated communications, 208-377-6050 | ||
Montana-Dakota Utilities: Jamie Tescher, senior public relations representative, 701-204-8274 | ||
Applied Digital: JSA (Jaymie Scotto & Associates), jsa_applied@jsa.net, 856-264-7827 | ||