AZIO AI Signs First Hosting Agreement at Atlas One with Power Champion; 10 MW Contracted, with Expansion Rights to 50 MW Representing Up to Approximately $450 Million in Capacity Reservation Charges
AZIO AI will fund site qualification, while Power Champion funds customer-specific improvements that remain AZIO AI property.
Sentiment and the balance of points
Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.
Rhea-AI Summary
AZIO AI (Nasdaq: AZIO) signed its first Atlas One hosting agreement with Power Champion, initially contracting 10 MW of capacity. AZIO AI expects approximately $90 million in capacity reservation charges over the 60-month initial term, before electricity sales and additional infrastructure services. Charges apply only to capacity delivered and made available; none has been energized and no revenue has been recognized under the agreement.
Expansion rights to 50 MW could yield approximately $450 million in reservation charges, conditional on full exercise, completed infrastructure and energization. No expansion right has been exercised. Site qualification remains incomplete, with no commencement date established. Performance requires Power Champion’s U.S. export approvals; further generation, equipment, permitting, financing and customer commitments are needed to deliver capacity.
How this balance works
Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.
It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.
Rhea-AI Sentiment measures something else, the tone of the wording.
Hollow bars mark forward-looking points. How the balance works
Positive
- Major pointInitial 10 MW agreement gives Atlas One its first contracted hosting customer, Power Champion.
- Moderate point. Forward-looking: it has not happened yet and may not happen.Expansion rights to 50 MW could yield approximately $450 million, conditional on full exercise, completed infrastructure and energization. 24× market cap
- Minor point. Forward-looking: it has not happened yet and may not happen.Initial capacity is expected to generate approximately $90 million in reservation charges over 60 months, excluding electricity and additional services.
- Minor pointExclusive power supply carries a fixed $0.13/kWh rate during the initial term, plus at-cost pass-through charges.
- Minor pointCustomer-specific build-out is Power Champion-funded and remains AZIO AI property after expiration or termination.
Negative
- Moderate pointAgreement has no energized capacity, commencement date or recognized revenue; reservation charges require delivered, available capacity.
- Moderate point. Forward-looking: it has not happened yet and may not happen.Campus has approximately 11 MW secured and approximately 6 MW activated; further capacity requires generation, equipment, permitting, financing and customer commitments.
- Moderate pointSite qualification remains incomplete; AZIO AI funds interconnection, substation, primary distribution and backbone fiber.
- Moderate point. Forward-looking: it has not happened yet and may not happen.Performance requires Power Champion’s U.S. export approvals; denial or revocation permits either party to terminate without liability.
- Moderate point. Forward-looking: it has not happened yet and may not happen.Power Champion has a 180-day conditional termination right if an engineering assessment finds initial delivery commercially infeasible.
- Moderate pointSeparate lease, build-out scope and budget, delivery milestones and final deposits await further written agreement.
2 minor points
- Minor point. Forward-looking: it has not happened yet and may not happen.Expansion requires available capacity, infrastructure improvements, an amendment and written support confirmation; no expansion right has been exercised.
- Minor pointPower delivery carries a 99.9% annualized availability commitment, subject to customary exclusions, with service credits as the exclusive remedy.
News Explained
AZIO funds and owns the infrastructure work, while Power Champion funds its build-out and retains a limited 180-day termination right.
Under the signed agreement, AZIO AI must fund site qualification and retain those improvements; Power Champion funds its customer-specific build-out, which will also remain AZIO AI property after expiration or termination.
Power Champion may terminate during the 180-day due-diligence period if a qualified third-party engineering assessment it obtains at its expense concludes the facility cannot support the initial 10 MW through commercially reasonable site work.
A separate lease, customer build-out scope and budget, delivery schedule, and final deposit amounts remain subject to further written agreement; the company says additional terms will be described in a future Form 8-K.
Key Figures
- Initial contracted capacity
- 10 MW
- Under the Atlas One agreement
- Maximum contracted capacity
- Up to 50 MW
- Expansion rights are conditional and had not been exercised as of the release
- Capacity reservation charge
- $150.00 per kW per month
- Applies to contracted capacity actually delivered and made available
- Fixed energy rate
- $0.13 per kWh
- For metered consumption during the Initial Term, plus pass-through charges
- Initial term
- 60 months
- Begins when the initial capacity is energized and available
- Initial-term capacity reservation charges
- Approximately $90 million
- Expected at the initial 10 MW capacity, before electricity sales and additional infrastructure services
- Conditional expanded-capacity charges
- Approximately $450 million
- Over the Initial Term only if expansion rights are fully exercised and required infrastructure is completed
- Power availability commitment
- 99.9% annualized
- Subject to customary exclusions; service credits are the exclusive remedy
Previous AI Reports
-
Power Champion hosting discussions at Atlas One remained unsigned; GPU pipeline was separate.
24h Move is the share-price change in the day after each event; other market factors may also have contributed.
Key Terms
behind-the-meter technical
export administration regulations regulatory
form 8-k regulatory
AI-generated analysis. How Rhea-AI works. Not financial advice.
Initial 10 MW deployment expected to generate approximately
HOUSTON, Oct. 09, 2026 (GLOBE NEWSWIRE) -- via IBN — AZIO AI Holdings, Inc. (Nasdaq: AZIO) (“AZIO AI” or the “Company”) today announced that it has entered into a Power Purchase and Hosting Agreement (the “Agreement”) with Power Champion Investment Limited (“Power Champion”) covering power delivery, leased facility space and interconnectivity services at Atlas One, the Company’s South Texas compute infrastructure campus. The Agreement establishes an initial contracted capacity of 10 megawatts (“MW” and such capacity, the “Initial Contracted Capacity”), with contractual expansion rights of up to a maximum contracted capacity of 50 MW (the “Maximum Contracted Capacity”), subject to the completion of required infrastructure improvements and other conditions described below.
The approximately
The Agreement is the first hosting agreement executed at Atlas One. In an Aug. 27, 2026, announcement, the Company disclosed that it was in discussions with Power Champion regarding potential hosting at the campus and that no agreement had been entered into. The Agreement concludes those discussions.
The Agreement does not amend, replace, or supersede the power purchase and hosting agreement with Power Champion announced on July 9, 2026. The Initial Contracted Capacity, Maximum Contracted Capacity, capacity reservation charges, and energy rates described in this release relate solely to the Agreement and to Atlas One.
Under the Agreement, AZIO AI will serve as Power Champion’s exclusive power supplier at the leased premises and will provide hosting, interconnectivity, and related infrastructure services supporting Power Champion’s deployment of AI GPU processors and associated advanced computing equipment.
Key Commercial Terms
- Contracted Capacity. Initial Contracted Capacity of 10 MW, with the right to request increases up to a Maximum Contracted Capacity of 50 MW — subject to available capacity at the facility, completion of required infrastructure improvements, execution of an amendment, and the Company’s written confirmation that site infrastructure can support the increase.
- Capacity Reservation Charge.
$150.00 per kilowatts (kW) per month of contracted capacity actually delivered and made available under the Agreement. Power Champion is not obligated to pay reservation charges on capacity that has not been energized. - Energy. Fixed energy rate of
$0.13 per kilowatt-hour (kWh) for metered consumption during the Initial Term (as defined below), plus pass-through utility, transmission, regulatory, and tax charges billed at cost without markup. Energy charges are additional to, and not included in, the capacity reservation figures described in this release. - Term. Initial term of sixty (60) months (the “Initial Term”) from the date on which the Company notifies Power Champion that the Initial Contracted Capacity is energized and available (the “Commencement Date”), with automatic successive twelve-month renewal terms absent notice of non-renewal 90 days prior to the expiration of the applicable renewal term.
- Phased delivery. Capacity will be energized in phases. Achievement of Phase 1 — delivery of at least the 10 Initial Contracted Capacity — establishes the Commencement Date.
- Cost allocation. AZIO AI will fund site qualification work — including interconnection, substation, primary distribution, and backbone fiber — at its own cost and will retain ownership of those improvements. Power Champion will fund the customer-specific build-out serving its load, which will be installed as property of AZIO AI and remain at the facility following expiration or termination.
- Availability.
99.9% annualized power availability commitment, subject to customary exclusions, with service credits as the exclusive remedy.
Contract Economics
At the Initial Contracted Capacity, the Company expects the Agreement to generate approximately
Capacity reservation charges are payable only on capacity actually delivered and made available. No assurance can be given that any expansion rights will be exercised, that any capacity beyond the initial phase will be energized, or that the Company will realize any portion of these amounts. Additional terms of the Agreement will be described in a Current Report on Form 8-K to be filed with the Securities and Exchange Commission.
Atlas One — Current Capacity Position
Announced on Aug. 20, 2026, Atlas One spans more than 548 acres in South Texas and is engineered for up to 500 MW of planned behind-the-meter power capacity, developed under the Company’s Project Atlas initiative.
Approximately 11 MW of that planned capacity has been secured to date, of which approximately 6 MW is activated. The balance of the campus’s planned capacity — including the capacity required to serve the full Initial Contracted Capacity under the Agreement and any expansion beyond it — is planned capacity that will require additional generation, equipment, permitting, financing, and customer commitments. The Company has not completed the site qualification work necessary to deliver the initial Contracted Capacity and has not established a Commencement Date.
Under Section 9.1 of the Agreement, the Company retains the right to deliver the contracted capacity at an alternative site of comparable size, capacity and energy rate, and the parties may relocate the facility by mutual written agreement.
Conditions, Approvals and Termination Rights
The Agreement is binding as of its effective date, but performance is subject to material conditions that investors should consider, including:
- U.S. export control approvals. The Company’s hosting and power obligations are expressly conditioned on Power Champion obtaining all required U.S. government approvals, licenses, and clearances — including from the Bureau of Industry and Security — for the purchase, import, deployment, and operation of AI GPU processors at the facility under the U.S. Export Administration Regulations and other applicable regulatory frameworks. The Company has no obligation to proceed with construction, energization, or service commencement until Power Champion provides written evidence of those approvals. If any required approval is denied or revoked, either party may terminate without liability.
- 180-day due diligence period. Power Champion may terminate during this period following the date of the Agreement only if a qualified third-party engineering assessment, obtained at its expense, concludes the facility cannot be made capable of delivering the Initial Contracted Capacity through commercially reasonable site qualification work.
- Documentation still to be completed. A separate lease agreement, the customer build-out scope and budget, the detailed delivery milestone schedule, and the final deposit amounts remain subject to further written agreement between the parties.
Relationship to the Previously Announced GPU Pipeline
Power Champion is also the counterparty to the Company’s previously announced agreement covering the purchase of up to 512 NVIDIA HGX B300 systems, which the Company has characterized as estimated sales pipeline value and not as backlog, contracted amounts, orders, or revenue. The Agreement does not obligate Power Champion to deploy any of those systems at Atlas One, and the deployment location for any systems purchased has not been determined. The capacity contracted under the Agreement and the GPU sales pipeline measure different things and are not additive.
Management Commentary
“On August 27 we told the market we were in discussions with Power Champion about hosting at Atlas One, and that we would announce an agreement if we reached one,” said Chris Young, Chief Executive Officer and Chairman of AZIO AI. “This is that agreement. Atlas One has a contracted customer.”
“Power is the constraint on AI. This is what converting power into contracted capacity looks like — sites, systems, hosting, and the electricity underneath it, under one roof.”
“Ten megawatts is what Power Champion has contracted for today. Fifty megawatts is the ceiling the agreement allows them to grow into, and getting there depends on generation, permitting, capital and their own export approvals — none of which we take for granted. We would rather show shareholders exactly where the work stands than announce a number and explain it later.”
About AZIO AI Holdings, Inc.
AZIO AI Holdings, Inc. (Nasdaq: AZIO), formerly Envirotech Vehicles, Inc. (Nasdaq: EVTV), is a technology infrastructure company focused on developing, owning, and operating artificial intelligence data centers, enterprise GPU compute infrastructure, digital power solutions, and other high compute operations. Through Project Atlas, the Company is developing behind-the-meter, power-backed campuses in Texas intended to support power-intensive compute workloads as additional generation, connectivity, customer commitments, and capital are secured.
For more information, please go to: www.azioai.ai and for potential global partnerships contact: Info@AiVenturesGP.com
Forward-Looking Statements
This press release contains forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995 and applicable federal securities laws. Forward-looking statements may be identified by words such as “may,” “will,” “could,” “expect,” “anticipate,” “believe,” “estimate,” “project,” “intend,” “plan,” “continue,” “potential,” “ongoing,” or the negative of these terms, although not all forward-looking statements contain such words.
Forward-looking statements in this release include, without limitation, statements regarding: the parties’ respective performance under the ; the delivery of the Initial Contracted Capacity and any expansion to the Maximum Contracted Capacity; expected capacity reservation charges, energy revenue, contract value and the timing of any such amounts; the achievement of the Commencement Date and any delivery milestone under the Agreement; the development, construction, energization, and expansion of Atlas One and future Project Atlas phases; the scope, cost, and completion of site qualification work and customer build-out; the Company’s ability to secure additional generation, equipment, permitting, financing, and customer commitments for Atlas One; the relationship between the Agreement and the Company’s previously announced GPU sales pipeline with Power Champion; and the Company’s broader business strategy and long-term growth objectives.
These statements are based on current expectations and assumptions that involve risks and uncertainties that could cause actual results to differ materially, and most of the relevant factors are outside the Company’s control. Such factors include, but are not limited to: the risk that the Agreement is terminated during the due diligence period or otherwise; the risk that Power Champion does not obtain, or loses, required U.S. government export control approvals, including from the Bureau of Industry and Security, without which the Company has no obligation to proceed; the risk that expansion rights are never exercised and that contracted capacity never exceeds the Initial Contracted Capacity; the risk that the Company is unable to complete site qualification work on the anticipated timeline or at all; the Company’s ability to secure the additional generation, interconnection, equipment, permitting, financing, and capital required to deliver capacity at Atlas One; the risk that capacity is delivered at an alternative site or that the facility is relocated; the risk that the separate lease agreement, customer build-out budget, and delivery milestone schedule are not agreed on terms acceptable to the Company or at all; counterparty credit and performance risk; the Company’s limited operating history in AI infrastructure and compute operations; supply chain constraints and equipment availability; energy price and grid volatility; the risk that GPU systems covered by the Company’s sales pipeline with Power Champion are never ordered or deployed; changes in digital asset markets; evolving compute demand and market conditions; and the additional risks described in the Company’s most recent Annual Report on Form 10-K and subsequent Quarterly Reports on Form 10-Q filed with the SEC, available at www.sec.gov. The Company undertakes no obligation to update forward-looking statements as a result of new information, future events, or otherwise, except as required by law.
Capacity Reservation Charges
Capacity reservation figures described in this release represent contractual charges payable only on capacity actually delivered and made available. They are not backlog, bookings, contracted revenue, or a revenue forecast, and are presented before electricity sales and additional infrastructure services. As of the date of this release, no capacity has been energized under the Agreement, no Commencement Date has been established, and no revenue has been recognized in respect of the Agreement.
Non-Additive Measures
The capacity reservation figures described in this release relate solely to the Agreement and to Atlas One. They do not include, and are not a restatement of, amounts previously disclosed in connection with the separate July 9, 2026 power purchase and hosting agreement with Power Champion, which is a distinct agreement covering a different site. Readers should not aggregate the figures in this release with the estimated GPU sales pipeline value announced on August 27, 2026, or with other previously disclosed capacity figures, agreement values or committed amounts. These measures address different things at different stages and are not cumulative.
Contacts
Corporate Communications:
IBN.Ai
Austin, Texas
www.IBN.Ai
512.354.7000 Office
Editor@IBN.Ai
FAQ
AI-generated questions and answers. How Rhea-AI works. Not financial advice.
How much could AZIO AI earn from the initial Atlas One hosting agreement?
AZIO AI expects approximately $1.5 million per month, or approximately $90 million in capacity reservation charges over the 60-month initial term. The charge is $150.00 per kW per month of capacity actually delivered and made available. Electricity sales and additional infrastructure services are excluded; these figures are not backlog, bookings, contracted revenue or a revenue forecast.
When does AZIO AI’s Atlas One hosting agreement start its initial term?
The 60-month initial term starts when AZIO AI notifies Power Champion that the initial 10 MW is energized and available. No commencement date has been established. Capacity will be energized in phases, and delivery of at least the initial contracted capacity establishes commencement.
Does AZIO AI’s Atlas One agreement replace its earlier Power Champion agreement or commit GPU deployments?
The Atlas One agreement does not replace the separate July 9, 2026 power purchase and hosting agreement, and it does not require deployment of the previously discussed GPU systems at Atlas One. The deployment location for any purchased systems remains undetermined. Capacity reservation figures and the estimated GPU sales pipeline measure different things and are not additive.
Can AZIO AI deliver Power Champion’s contracted capacity outside Atlas One?
AZIO AI retains the right to deliver the contracted capacity at an alternative site of comparable size, capacity and energy rate under Section 9.1. The parties may also relocate the facility by mutual written agreement.
When can Power Champion terminate AZIO AI’s agreement during due diligence?
Power Champion may terminate during the 180-day period following the agreement date only if a qualified third-party engineering assessment concludes the facility cannot deliver the initial contracted capacity through commercially reasonable site qualification work. Power Champion must obtain that assessment at its own expense.