Boliden: Production capacity in Aitik and Tara restored

Boliden has restored full production capacity in its Aitik and Tara mines following disruptions caused by COVID-19 and equipment breakdowns.

(Neutral)

Sentiment and the balance of points

Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

Tags

Rhea-AI Summary

Boliden has restored full production capacity in its Aitik and Tara mines following disruptions caused by COVID-19 and equipment breakdowns. The impact on operating profit in the Business Area Mines for Q1 is now estimated at SEK -300 million, up from the previously forecasted SEK -200 million. In Aitik, a delay in repairs extended the outage of one primary mill by nearly three weeks, resulting in a throughput reduction of over 2 million tonnes. Production at the Tara mine resumed as planned after a brief interruption.

Loading...
Loading translation...

Positive

  • Full production capacity restored in Aitik and Tara mines.
  • Resumption of mine production at Tara occurred as scheduled.

Negative

  • Operating profit impact increased to SEK -300 million for Q1, up from SEK -200 million.
  • Production impact in Aitik due to delays and repairs estimated at over 2 million tonnes.
Argus Session date unavailable
+10.08% session move Open Argus
Details

News Market Reaction – BDNNY

The recorded move for BDNNY in the trading session of this news was +10.08%.

Data tracked by StockTitan Argus. Session date unavailable.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

BOLIDEN, Sweden, April 6, 2021 /PRNewswire/ --  Production capacity in Aitik and Tara is now fully restored after previously announced disruptions due to covid-19 and breakdowns. Impact on operating profit in Business Area Mines is estimated to amount to SEK -300 million in Q1, compared with SEK -200 million that was previously communicated.

In Aitik, production at the concentrator is now at full capacity. The stop in one of two primary mills lasted almost three weeks longer than first assessed due to additional repairs to the hydraulic system. The total production impact in Aitik is estimated at just over 2 million tonnes reduced throughput.

Mine production at Tara was resumed as planned about a week after the breakdown of the ore hoist occurred. 

For further information, please contact:

Klas Nilsson, Director Group Communications, tel: +46 (0)70-453 65 88    

Boliden is a metals company with a focus on sustainable development. Our roots are Nordic, our market global. Our core competence lies within the fields of exploration, mining, smelting and metal recycling. Boliden has around 6,000 employees and an annual turnover of SEK 50 billion. The share is listed in the Large Cap segment on NASDAQ OMX Stockholm.

www.boliden.com

This information was brought to you by Cision http://news.cision.com

https://news.cision.com/boliden/r/production-capacity-in-aitik-and-tara-restored,c3319908

The following files are available for download:

https://mb.cision.com/Main/997/3319908/1397364.pdf

Press release (PDF)

Cision View original content:http://www.prnewswire.com/news-releases/boliden-production-capacity-in-aitik-and-tara-restored-301262616.html

SOURCE Boliden

FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

What is the current production status of Boliden's Aitik and Tara mines?

Boliden has fully restored production capacity at both the Aitik and Tara mines after previous disruptions.

How much is the estimated impact on Boliden's operating profit for Q1?

The estimated impact on Boliden's operating profit for Q1 is SEK -300 million.

What caused the production disruptions at Boliden's Aitik mine?

The production disruptions at Aitik were due to COVID-19 and delays in repairs to the hydraulic system of one of the primary mills.

When did production at Tara mine resume?

Production at the Tara mine resumed as planned about a week after the breakdown of the ore hoist.

What was the throughput reduction estimated for Aitik?

The total production impact in Aitik is estimated at just over 2 million tonnes reduced throughput.