Nickel 28 Releases Ramu Q3 2026 Operating Performance
Sentiment and the balance of points
Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.
Rhea-AI Summary
Nickel 28 Capital (CONXF) reported third-quarter 2026 operating results for its Ramu nickel-cobalt joint venture in Papua New Guinea. Nickel 28 holds an 8.56% interest; volumes reflect the full operation.
Nickel production fell to 9,043 tonnes from 9,242 a year earlier, while cobalt production rose to 929 tonnes from 887. Sales of both metals fell year over year. Nickel inventory rose to 2,734 tonnes from 1,094 tonnes at June 30, 2026. Nickel 28 expects the shipment timing effect to reverse in the following quarter.
Net production cost rose to US$6.15/lb of nickel produced from US$3.07/lb a year earlier. Nickel 28 cited higher sulphur prices as the main cause. The quarter's average London Metal Exchange nickel price rose 10% year over year to US$7.52/lb, and the average cobalt price rose 58% to US$24.41/lb. Financial figures are preliminary and subject to audit and adjustment.
How this balance works
Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.
It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.
Rhea-AI Sentiment measures something else, the tone of the wording.
Hollow bars mark forward-looking points. How the balance works
Positive
- Moderate pointYear-to-date nickel production rose to 26,062 tonnes from 24,776 tonnes a year earlier
- Moderate pointYear-to-date nickel sales rose to 25,002 tonnes from 23,854 tonnes a year earlier
- Moderate pointQuarterly cobalt production rose to 929 tonnes from 887 tonnes a year earlier
- Moderate pointYear-to-date cobalt production rose to 2,595 tonnes from 2,322 tonnes a year earlier
- Moderate pointYear-to-date cobalt sales rose to 2,494 tonnes from 2,235 tonnes a year earlier
- Moderate pointQ3 average London Metal Exchange nickel price rose 10% year over year to US$7.52/lb
- Moderate pointQ3 average cobalt price rose 58% year over year to US$24.41/lb
6 minor points
- Minor point. Forward-looking: it has not happened yet and may not happen.Shipment timing effect is expected by Nickel 28 to reverse in the following quarter
- Minor pointYear-to-date nickel capacity utilization rose to 107% of design capacity from 101% a year earlier
- Minor pointYear-to-date mixed hydroxide precipitate output rose to 64,585 dry tonnes from 60,606 a year earlier
- Minor pointYear-to-date mixed hydroxide precipitate shipments rose to 61,961 dry tonnes from 58,423 a year earlier
- Minor pointQuarterly ore processed rose to 1,022 dry kilotonnes from 991 a year earlier
- Minor pointYear-to-date ore processed rose to 2,950 dry kilotonnes from 2,600 a year earlier
Negative
- Moderate pointQuarterly production cost net of by-product credits rose to US$6.15/lb of nickel produced from US$3.07/lb a year earlier
- Moderate pointQuarterly nickel sales fell to 7,403 tonnes from 9,880 tonnes a year earlier
- Moderate pointQuarterly cobalt sales fell to 775 tonnes from 948 tonnes a year earlier
- Moderate pointQuarterly nickel production fell to 9,043 tonnes from 9,242 tonnes a year earlier
- Moderate point. Forward-looking: it has not happened yet and may not happen.Near-term profitability and cash generation remain under pressure from costs and metal prices, Nickel 28 expects
- Moderate pointOperating margins narrowed as input costs rose and metal prices weakened during the quarter, Nickel 28 said
5 minor points
- Minor pointYear-to-date production cost net of by-product credits rose to US$4.25/lb of nickel produced from US$3.27/lb a year earlier
- Minor pointQuarterly nickel capacity utilization fell to 111% of design capacity from 113% a year earlier
- Minor pointQuarterly mixed hydroxide precipitate shipments fell to 18,407 dry tonnes from 24,615 a year earlier
- Minor pointQuarterly mixed hydroxide precipitate output fell to 22,501 dry tonnes from 22,844 a year earlier
- Minor point. Forward-looking: it has not happened yet and may not happen.Preliminary financial figures are unaudited and may change materially after audit and final adjustments
AI-generated analysis. How Rhea-AI works. Not financial advice.
Toronto, Ontario--(Newsfile Corp. - November 27, 2026) - Nickel 28 Capital Corp. (TSXV: NKL) (FSE: 3JC0) ("Nickel 28" or the "Company") is pleased to provide operational results for the calendar quarter ending September 30, 2026 for the Company's largest asset, the Ramu Nickel-Cobalt ("Ramu") integrated operation in Papua New Guinea. Production, shipment and inventory figures are reported on a
Q3 2026 Ramu Highlights:
- Production of 9,043 tonnes of contained nickel in Mixed Hydroxide Precipitate ("MHP"), compared to 9,242 tonnes in the same period last year.
- Production of 929 tonnes of contained cobalt in MHP, compared to 887 tonnes in the same period last year.
- Nickel sales of 7,403 tonnes of contained nickel, compared to 9,880 tonnes in the same period last year.
- Cobalt sales of 775 tonnes of contained cobalt, compared to 948 tonnes in the same period last year.
- Nickel inventory on hand at quarter-end was 2,734 tonnes of nickel in MHP, compared to 1,094 tonnes at June 30, 2026.
- London Metal Exchange average nickel price of US
$7.52 /lb in Q3 2026, an increase of10% from the same period last year (US$6.81 /lb). - Average cobalt price of US
$24.41 /lb in Q3 2026, an increase of58% from the same period last year (US$15.48 /lb). - Production costs, net of by-product credits were US
$6.15 /lb of nickel produced in MHP, compared to US$3.07 /lb in the same period last year, primarily reflecting higher sulphur prices. Year-to-date 2026 production costs, net of by-product credits, were US$4.25 /lb of nickel produced in MHP, compared to US$3.27 /lb in the same period last year.
Nickel 28's Chief Executive Officer, Craig Lennon stated: "Ramu continued to deliver strong operational performance during the third quarter of 2026, with nickel and cobalt production remaining robust and the project continuing to demonstrate its operational reliability. While reported sales volumes were lower than the previous quarter, this was principally attributable to the timing of a shipment that was not recognised within the quarter. As a result, inventory levels increased at quarter end, and we expect this timing difference to reverse in the following quarter. Importantly, the lower sales volumes do not reflect any deterioration in underlying production performance.
The operating environment has, however, become increasingly challenging, with a significant increase in production costs during the quarter, driven primarily by the continued escalation in sulphur prices. Sulphur is a major consumable in the high-pressure acid leach (HPAL) process, and the sustained increase in its price has had a material impact on operating costs and margins. These cost pressures have been compounded by lower average nickel and cobalt prices during the quarter, resulting in a more difficult financial environment than we experienced during the first half of 2026.
Nickel prices softened during the quarter, reflecting continued concerns regarding global oversupply, particularly from Indonesia. Cobalt prices also weakened as increased availability of material from the Democratic Republic of Congo and subdued downstream demand placed pressure on the market. The combination of lower commodity prices and higher input costs has resulted in a significant compression of operating margins, despite the continued strong production performance at Ramu.
Looking ahead, Indonesian governmental policy remains a critical factor in determining the direction of global nickel prices. In particular, the Indonesian government's management of nickel ore production quotas through its Work Plan and Budget (Rencana Kerja dan Anggaran Biaya, or RKAB) approval process will be closely watched by the industry. The RKAB is the mandatory annual operational and financial blueprint that mining license holders must get approved by the Indonesian Ministry of Energy and Mineral Resources or relevant local governor before carrying out exploration or production activities. Recent indications that Indonesia may adopt a more restrictive approach to production quotas in 2027 are encouraging and could help address the current global supply imbalance. However, the extent and timing of any resulting improvement in nickel prices remain uncertain.
While we remain confident in the underlying operational performance of Ramu, we expect the challenging cost and commodity price environment to continue to impact profitability and cash generation in the near term. The focus for the project remains on maintaining strong production performance, managing operating costs where possible and positioning the project to benefit from any improvement in market conditions."
Ramu operating results for the three and nine months ended September 30, 2026 and 2025:
| 2025 | 2026 | |||||||||||
| Q3 | YTD | Q3 | YTD | |||||||||
| Ore Processed (dry kt) MHP Produced (dry t) Contained Nickel (t) Contained Cobalt (t) Nickel Capacity Utilization (% of design1) | 991 22,844 9,242 887 | 2,600 60,606 24,776 2,322 | 1,022 22,501 9,043 929 | 2,950 64,585 26,062 2,595 | ||||||||
| MHP Shipped (dry t) Contained Nickel (t) Contained Cobalt (t) | 24,615 9,880 948 | 58,423 23,854 2,235 | 18,407 7,403 775 | 61,961 25,002 2,494 | ||||||||
| Production Cost Actual (2) | $ | 3.07 | $ | 3.27 | $ | 6.15 | $ | 4.25 | ||||
Note 1. Ramu's design capacity of 32,600 t Ni per year is an annualized benchmark. Quarterly utilization rates may exceed
Note 2. Actual production cost, net of by-product credits (US$/lb of contained Ni produced).
The figures in the table above have not been audited and are subject to change. As Ramu has not yet completed its local or corporate audit, nor completed the review of accounting procedures for the fiscal quarter, the financial information presented in this press release is preliminary, subject to audit, final adjustment and may change materially. The information presented above has not been reviewed or audited by the Company's auditor and should not be considered a substitute for reviewed or audited financial statements and should not be regarded as a representation by the Company as to the actual financial results.
About Nickel 28
Nickel 28 Capital Corp. is a nickel-cobalt producer through its
Scientific and Technical Information
Disclosures of a scientific or technical nature in this news release have been reviewed and approved on behalf of Nickel 28 by Alan Lambden, P.Geo., an independent consultant to Nickel 28 and a "qualified person" as defined by National Instrument 43-101 - Standards of Disclosure for Mineral Projects.
Cautionary Note Regarding Forward-Looking Statements
This news release contains certain information which constitutes 'forward-looking statements' and 'forward-looking information' within the meaning of applicable Canadian securities laws. Any statements that are contained in this news release that are not statements of historical fact may be deemed to be forward-looking statements. Forward-looking statements are often identified by terms such as "may", "should", "anticipate", "expect", "potential", "believe", "intend" or the negative of these terms and similar expressions. Forward-looking statements in this news release include, but are not limited to: statements and figures with respect to the operational and financial results; statements with respect to future commodities prices and other input costs; statements with respect to changes in Indonesian government policy and related impacts on the global nickel market and the global price of nickel; and statements with respect to the business and assets of the Company and its strategy going forward. Readers are cautioned not to place undue reliance on forward-looking statements. Forward-looking statements involve known and unknown risks and uncertainties, most of which are beyond the Company's control. Should one or more of the risks or uncertainties underlying these forward-looking statements materialize, or should assumptions underlying the forward-looking statements prove incorrect, actual results, performance or achievements, could vary materially from those expressed or implied by the forward-looking statements.
The forward-looking statements contained herein are made as of the date of this release and, other than as required by applicable securities laws, the Company does not assume any obligation to update or revise them to reflect new events or circumstances. The forward-looking statements contained in this release are expressly qualified by this cautionary statement.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. No securities regulatory authority has either approved or disapproved of the contents of this news release.
For more investor information - please contact:
Nickel 28 Investor Relations
Attn: Mr. Brett Richards
+1 905 449 1500
Email: info@nickel28.com

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/326118
FAQ
AI-generated questions and answers. How Rhea-AI works. Not financial advice.