Denison Reports Financial and Operational Results for Q3 2026, Highlighted by 24% Total Completion after First Quarter of Full-Scale Construction at Phoenix ISR Uranium Mine
Direct equipment procurement front-loads Phoenix spending relative to onsite progress, while offsite fabrication supports winter work.
Sentiment and the balance of points
Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.
Rhea-AI Summary
Denison Mines (NYSE American: DNN) reported estimated 24% completion at its Phoenix uranium mine after its first quarter of full-scale construction. At September 30, 2026, engineering, project management and owner’s costs were 32% complete, construction was 20% complete, and equipment fabrication and delivery were 32% complete. Denison continues to target construction completion and first production in the second half of 2028.
Phoenix expenditures totaled C$161.1 million year to date, with 2026 spending forecast at C$278.6 million. Direct procurement requires fabrication progress payments, front-loading spending relative to onsite construction. By October’s end, nearly 50% of site civil work was complete. Phoenix North drilling intersected mineralization over 100 metres of strike length, including 0.67% equivalent uranium oxide over 2.5 metres in October; exploration continues into the fourth quarter.
How this balance works
Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.
It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.
Rhea-AI Sentiment measures something else, the tone of the wording.
Hollow bars mark forward-looking points. How the balance works
Positive
- Moderate pointPhoenix reached an estimated 24% total completion at September 30, 2026, after its first full-scale construction quarter.
- Moderate point. Forward-looking: it has not happened yet and may not happen.Denison continues to target construction completion and first production in the second half of 2028.
- Minor pointSite civil work was estimated nearly 50% complete by October’s end; the main access road is available.
- Minor pointConcrete needed to begin process plant building construction over winter was substantially completed by October’s end.
- Minor point. Forward-looking: it has not happened yet and may not happen.Offsite equipment fabrication supports continued winter productivity; fabrication has begun on most process plant equipment.
6 minor points
- Minor pointPhoenix North drilling intersected mineralization across 100 metres of strike length, remaining open in multiple directions.
- Minor pointThird-quarter hole WR-857D1 intersected 0.39% equivalent uranium oxide over 4.7 metres at Phoenix North.
- Minor pointOctober hole WR-868 intersected 0.67% equivalent uranium oxide over 2.5 metres at Phoenix North.
- Minor pointOctober hole WR-869A intersected 0.07% equivalent uranium oxide over 2.2 metres at Phoenix North.
- Minor pointSecond-quarter hole WR-857 intersected 0.20% equivalent uranium oxide over 1 metre and 0.07% over 0.5 metres.
- Minor point. Forward-looking: it has not happened yet and may not happen.Phoenix North exploration drilling continues into the fourth quarter within the Phoenix mine’s surface footprint.
Negative
- Moderate point. Forward-looking: it has not happened yet and may not happen.Phoenix spending totaled C$161.1 million year to date; forecast 2026 expenditures are C$278.6 million.
- Minor pointDirect procurement requires fabrication progress payments, front-loading project spending relative to onsite construction progress.
- Minor pointPhoenix North’s anticipated optimal target horizon remains untested.
Key Figures
- Phoenix total completion
- 24%
- As of September 30, 2026
- Year-to-date Phoenix expenditures
- C$161.1 million
- Year to date in 2026
- Forecast 2026 expenditures
- C$278.6 million
- Phoenix project
- Phoenix North intersection
- 0.39% eU3O8 over 4.7 metres
- Drill hole WR-857D1
- Phoenix North intersection
- 0.67% eU3O8 over 2.5 metres
- Drill hole WR-868
- Mineralized strike length
- Over 100 metres
- Phoenix North target area
- First production target
- Second half of 2028
- Phoenix
Previous Earnings Reports
-
Phoenix moved from early works into full-scale construction after Q2 civil-work progress.
-
Final approvals and site preparation set the stage for Phoenix construction.
24h Move is the share-price change in the day after each event; other market factors may also have contributed.
Key Terms
in-situ recovery technical
md&a financial
ni 43-101 regulatory
qualified person regulatory
AI-generated analysis. How Rhea-AI works. Not financial advice.
David Cates, President and CEO of Denison commented, "With a relatively short timeline for construction of the Phoenix In-Situ Recovery ("ISR") uranium mine, executing during the prime summer construction season is critical. We are very pleased with our ability to immediately mobilize to site after regulatory approvals and ramp up activity to achieve a full-scale rate of construction for the third quarter. Denison's results showcase significant construction progress at
During the quarter, we prioritized schedule-critical and seasonally sensitive activities to capitalize on the summer construction season, and we ended our first quarter of full-scale construction with the project's total percentage completion estimated at
By the end of October 2026, nearly
We are also pleased to report encouraging exploration results at the emerging Phoenix North target area, which is located within the surface footprint of the Phoenix ISR mine site. Drill hole WR-857D1 intersected
Highlights
Phoenix achieves24% total completion after first quarter of full-scale construction
Building on the successful completion of site preparation and early works construction in early July, Denison made significant progress executing on key construction work scopes during its first quarter of full-scale construction on site. The project's total percentage completion as at September 30, 2026 is estimated at approximately24% , which includes (i) engineering, PCM, and owner's costs at32% completion, (ii) construction and construction indirect costs at20% complete, and (iii) fabrication and delivery of equipment and materials at32% complete.
With full-scale construction commencing during the critical summer construction season, initial construction activities have focused on schedule and seasonally sensitive work. Civil work continued with the main site access road from Highway 914 currently available for use, the substation area substantially completed and the freeze plant area and airstrip significantly advanced (with100% of the final grade completed for the runway area). In addition, concrete work commenced in August and continues into the fourth quarter of 2026. By the end of October 2026, site civil work is estimated to be nearly50% complete and the concrete work required to enable the commencement of construction of the process plant building over the winter has been substantially completed.
Phoenix construction and procurement strategy allows continued productivity during winter months
With an approximately 2-year construction timeline targeted forPhoenix , Denison developed a procurement and execution strategy whereby key project components have been procured directly by Denison, rather than through its contractors, and modularization has been utilized wherever possible. As a result, Denison is responsible for making progress payments as equipment is fabricated and the total project spend curve is thus front-loaded relative to the rate of construction progress on site. This approach decouples fabrication of key equipment from onsite construction by utilizing offsite fabrication facilities which allows for continued productivity during the winter season. Fabrication has commenced on the majority of the process plant equipment and shipment release has occurred for the site transformer, substation e-house, high-voltage substation yard equipment, switchgear, generators, freeze plants, and certain process tanks and construction bulks.
Year to date totalPhoenix project expenditures totaled , including$161.1 million on construction and construction indirect costs and$105.0 million on procurement of equipment and materials. Life to date expenditures on procurement of equipment and materials is approximately$39.0 million .$56.8 million
Forecasted expenditures for 2026 are now estimated to be , with$278.6 million in procurement payments,$39.9 million in construction and construction indirect costs, and$68.5 million in engineering, PCM, and owner's costs estimated for the fourth quarter of 2026.$9.1 million
- Additional mineralization discovered at Phoenix North exploration target area, located within surface footprint of the Phoenix ISR mine site
During the third quarter of 2026, drill hole WR-857D1 intersected0.39% eU3O8 over 4.7 metres from 409.9 metres to 414.6 metres at the unconformity and represents the best mineralized hole drilled in this area of sparse historic drilling. WR-857D1 is located approximately 10 metres up-dip and along section of WR-857, which was completed during the second quarter and intersected mineralized intervals of0.20% eU3O8 over 1 metre from 417.6 metres, and0.07% eU3O8 over 0.5 metres from 415.8 metres. In October 2026, drill hole WR-868 encountered unconformity associated mineralization (0.67% eU3O8 over 2.5 metres from 413.1 metres to 415.6 metres) approximately 50 metres along strike to the northeast of WR-857, and drill hole WR-869A intersected additional mineralization (highlighted by0.07% eU3O8 over 2.2 metres from 421.5 metres to 423.7 metres) 50 metres along strike to the southwest of WR-857. See the MD&A for further details. Taken together, mineralization has now been intersected over 100-metres of strike length at the Phoenix North target area, which remains open in multiple directions with the anticipated optimal target horizon yet to be tested.
While in the early stages of exploration discovery, the results at Phoenix North are especially encouraging as the mineralization is situated in the immediate vicinity of the Phoenix ISR mine currently under construction.





About Denison
Denison Mines Corp. was formed under the laws of Ontario and is a reporting issuer in all Canadian provinces and territories. Denison's common shares are listed on the Toronto Stock Exchange (the "TSX") under the symbol 'DML' and on the NYSE American exchange under the symbol 'DNN'.
Denison is a uranium mining, exploration and development company with interests focused in the Athabasca Basin region of northern Saskatchewan, Canada. The Company has an effective
Full-scale construction commenced at Phoenix in July 2026, which followed receipt of Federal approval of the project's Environmental Assessment and issuance of the Construction Licence in February 2026, as well as completion of site preparation and early works programs initiated in March 2026. Construction is expected to take approximately 2 years with first production targeted for the second half of 2028.
Denison's interests in Saskatchewan also include a
Additionally, through its
In 2024, Denison celebrated its 70th year in uranium mining, exploration, and development, which began in 1954 with Denison's first acquisition of mining claims in the Elliot Lake region of northern Ontario.
Technical Disclosure and Qualified Person
The scientific and technical information contained in this press release has been reviewed and approved by Ricardo Afonso, P.Eng., Denison's Vice President Projects, or Chad Sorba, P.Geo., Denison's Vice President Technical Services & Project Evaluation, each of whom is a Qualified Person in accordance with NI 43-101.
CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING STATEMENTS
Certain information contained in this press release constitutes 'forward-looking information', within the meaning of the applicable United States and Canadian legislation concerning the business, operations, and financial performance and condition of Denison. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as 'plans', 'expects', 'budget', 'scheduled', 'estimates', 'forecasts', 'intends', 'anticipates', or 'believes', or the negatives and/or variations of such words and phrases, or state that certain actions, events or results 'may', 'could', 'would', 'might' or 'will be taken', 'occur', 'be achieved' or 'has the potential to'.
In particular, this press release contains forward-looking information pertaining to the following: Denison's estimated completion status, and other outlook, plans and objectives with respect to Phoenix construction; assumptions and estimates with respect to the Company's other exploration, development and expansion programs, plans and objectives; Denison's land position; and expectations regarding Denison's joint venture ownership interests and the continuity of its agreements with its partners. Statements relating to 'mineral reserves' or 'mineral resources' are deemed to be forward-looking information, as they involve the implied assessment, based on certain estimates and assumptions that the mineral reserves and mineral resources described can be profitably produced in the future.
Forward looking statements are based on the opinions and estimates of management as of the date such statements are made, and they are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Denison to be materially different from those expressed or implied by such forward-looking statements. For example, estimates of construction progress and related percentages are estimates subject to change, and may be impacted by many factors including contractor availability, labour availability, weather, and other events or circumstances. In addition, the results of the Denison's studies, including the Phoenix FS, and field work, may not be maintained after further testing or be representative of actual mining plans for the Phoenix deposit after further design and studies are completed. Denison could decide or otherwise be required to discontinue testing, evaluation and development work at Wheeler River or other projects, or its exploration plans if it is unable to maintain or otherwise secure the necessary resources (such as testing facilities, capital funding, regulatory approvals, etc.) or operations are otherwise affected by regulatory restrictions or requirements.
Denison believes that the expectations reflected in this forward-looking information are reasonable, but no assurance can be given that these expectations will prove to be accurate, and results may differ materially from those anticipated in this forward-looking information. For a discussion in respect of risks and other factors that could influence forward-looking events, please refer to the factors discussed under the heading 'Risk Factors' in this MD&A. These factors are not, and should not be construed as being, exhaustive. Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking information contained in this press release is expressly qualified by this cautionary statement. Any forward-looking information and the assumptions made with respect thereto speaks only as of the date of this press release. Denison does not undertake any obligation to publicly update or revise any forward-looking information after the date of this press release to conform such information to actual results or to changes in Denison's expectations except as otherwise required by applicable legislation.

View original content to download multimedia:https://www.prnewswire.com/news-releases/denison-reports-financial-and-operational-results-for-q3-2026-highlighted-by-24-total-completion-after-first-quarter-of-full-scale-construction-at-phoenix-isr-uranium-mine-302929901.html
SOURCE Denison Mines Corp.
FAQ
AI-generated questions and answers. How Rhea-AI works. Not financial advice.