STOCK TITAN

Stronger, More Reliable Power Coming to Trumbull and Ashtabula Counties

Rhea-AI Impact
(Low)
Rhea-AI Sentiment
(Neutral)
Tags

FirstEnergy (NYSE: FE) said an 11.5-mile high-voltage transmission line in Trumbull and Ashtabula counties will be energized by the end of October 2025, after construction that began in 2023.

The $19 million rebuild installed nearly 140 new steel structures, thicker conductors and stronger foundations to reduce outages, speed restorations and allow easier rerouting during disruptions. The project affects nearly 10,000 residents and businesses and is part of the company’s $28 billion Energize365 grid-modernization program for 2025–2029.

FirstEnergy (NYSE: FE) ha dichiarato che una linea di trasmissione ad alta tensione di 11,5 miglia nei contee di Trumbull e Ashtabula sarà energizzata entro la fine di ottobre 2025, dopo la costruzione iniziata nel 2023.

La ricostruzione da $19 milioni ha installato quasi 140 nuove strutture in acciaio, conduttori più spessi e fondazioni più robuste per ridurre i blackout, accelerare le riparazioni e permettere un reindirizzamento più facile durante le interruzioni. Il progetto riguarda quasi 10.000 residenti e aziende ed è parte del programma di modernizzazione della rete $28 miliardi Energize365 dell'azienda per il 2025–2029.

FirstEnergy (NYSE: FE) dijo que una línea de transmisión de alta tensión de 11,5 millas en los condados de Trumbull y Ashtabula se energizará para finales de octubre de 2025, tras la construcción que comenzó en 2023.

La reconstrucción de $19 millones instaló casi 140 nuevas estructuras de acero, conductores más gruesos y cimientos más fuertes para reducir apagones, acelerar restauraciones y permitir un reencaminamiento más fácil durante interrupciones. El proyecto afecta a casi 10,000 residentes y negocios y es parte del programa de modernización de la red de la empresa $28 mil millones Energize365 para 2025–2029.

FirstEnergy (NYSE: FE)는 트럼불(Trumbull) 및 애스타배울라(Ashtabula) 카운티의 11.5마일 고전압 송전선이 2025년 10월 말까지 가동될 것이라고 밝혔다. 이는 2023년에 시작된 공사 이후의 일이다.

$19백만의 재건으로 거의 140개의 새로운 강구조물, 더 두꺼운 도체 및 더 강한 기초가 설치되어 정전을 줄이고, 복구를 가속하며 혼란 시 재배치를 더 쉽게 할 수 있다. 이 프로젝트는 거의 10,000명의 주민과 기업에 영향을 미치며 회사의 2025–2029년 그리드 현대화 프로그램인 $28조 Energize365의 일부이다.

FirstEnergy (NYSE : FE) a déclaré qu'une ligne de transmission haute tension de 11,5 miles dans les comtés de Trumbull et d'Ashtabula sera energisée d'ici la fin octobre 2025, après des travaux commencés en 2023.

La reconstruction évaluée à $19 millions a installé près de 140 nouvelles structures en acier, des conducteurs plus épais et des fondations plus solides pour réduire les pannes, accélérer les restaurations et permettre un réacheminement plus facile lors des perturbations. Le projet touche près de 10 000 résidents et entreprises et fait partie du programme de modernisation du réseau de l'entreprise $28 milliards Energize365 pour 2025–2029.

FirstEnergy (NYSE: FE) sagte, dass eine 11,5-Meilen lange Hochspannungs-Übertragungsleitung in den Landkreisen Trumbull und Ashtabula bis Ende Oktober 2025 energisiert sein wird, nach einer Bauphase, die 2023 begann.

Der 19 Mio. Dollar schwere Wiederaufbau installierte fast 140 neue Stahlelemente, dickere Leiter und stärkere Fundamente, um Ausfälle zu reduzieren, die Wiederherstellung zu beschleunigen und während Störungen eine leichtere Umleitung zu ermöglichen. Das Projekt betrifft fast 10.000 Einwohner und Unternehmen und ist Teil des 28 Milliarden Dollar Energize365-Netzmodernisierungsprogramms des Unternehmens für 2025–2029.

FirstEnergy (NYSE: FE) أعلنت أن خط نقل عالي الجهد بطول 11.5 ميل في مقاطعات ترومبِل وأشْتابولا سيُجهَّز بالطاقة بحلول نهاية أكتوبر 2025، بعد بدء البناء في عام 2023.

إعادة الإعمار التي بلغت قيمتها $19 مليون قامت بتركيب ما يقرب من 140 هيكلًا فولاذيًا جديدًا، وموصلات أسمك وأسُس أقوى لتقليل الانقطاعات وتسريع عمليات الاستعادة وتسهيل إعادة التوجيه أثناء الانقطاعات. يؤثر المشروع على ما يقرب من 10,000 مقيم ومؤسسة وهو جزء من البرنامج الذي تتبناه الشركة لتحديث الشبكة بقيمة $28 مليار Energize365 للفترة 2025–2029.

Positive
  • Rebuilt 11.5-mile high-voltage transmission line
  • Project cost: $19 million
  • Benefits nearly 10,000 residents and businesses
  • Installed nearly 140 new steel structures
Negative
  • Adds to capital deployment under the $28 billion Energize365 program

Insights

Upgraded 11.5-mile transmission line and $19 million capex enhance rural reliability; energization slated by end of this month.

The rebuild replaces aging structures with nearly 140 new steel poles, thicker conductors and deeper foundations, which increases mechanical strength and carrying capacity and enables easier rerouting by tying into adjacent lines. Those facts imply a direct operational mechanism: stronger assets reduce single-point failures and improve system topology flexibility during outages.

Key dependencies and risks include timely commissioning and successful integration with existing protection and switching schemes; energizing late this month and proper testing are required before reliability benefits materialize. The project is one discrete element within the broader $28 billion Energize365 program covering 20252029, so incremental benefits should be viewed in the context of a multi-year rollout.

Items to watch: completion and in-service confirmation by the end of the month, any post-energization outage metrics, and capital spending cadence under Energize365 over the next several years. Those milestones will provide observable signals about whether the upgrade delivers the intended reduction in outage frequency and restoration time.

Upgraded power line expected to be energized by the end of this month

AKRON, Ohio, Oct. 23, 2025 /PRNewswire/ -- Nearly 10,000 residents and businesses in rural Trumbull and Ashtabula counties will soon experience improved electric service as a major grid upgrade nears completion in northeast Ohio.

American Transmission Systems, Inc. (ATSI), a FirstEnergy (NYSE: FE) company, has rebuilt an 11.5-mile high-voltage transmission line to reduce outages and speed up restoration times when service is disrupted.

Built to Withstand the Elements
The project replaces aging infrastructure with stronger poles and thicker wires capable of carrying more electricity. Nearly 140 new steel structures were installed, many anchored in deep concrete foundations to better withstand severe weather and vehicle accidents. This is especially important in open fields, where one fallen pole can knock down others like dominos, causing bigger outages.

The upgraded line will also connect with existing lines, allowing power to be rerouted more easily during outages and minimizing service disruptions.

Mark Mroczynski, President of Transmission for FirstEnergy: "We know how frustrating power outages can be, especially in rural areas where repairs can take longer. This project is all about helping to keep the electricity flowing reliably during uncontrollable events like severe weather or car accidents and making life a little easier for our customers."

Construction began in 2023, and the line is expected to be energized by the end of this month.

View or download a video series on "Why a Modern Transmission System Matters to You" on FirstEnergy's YouTube channel.

Part of a Bigger Investment in Reliability
This nearly $19 million project is part of Energize365, FirstEnergy's $28 billion investment program to modernize the electric grid across the footprint between 2025 and 2029. The goal: a smarter, more secure grid that meets the needs of today's customers and tomorrow's growth.

FirstEnergy is dedicated to integrity, safety, reliability and operational excellence. Its electric distribution companies form one of the nation's largest investor-owned electric systems, serving more than six million customers in Ohio, Pennsylvania, New Jersey, West Virginia, Maryland and New York. The company's transmission subsidiaries operate approximately 24,000 miles of transmission lines that connect the Midwest and Mid-Atlantic regions. Follow FirstEnergy on X @FirstEnergyCorp or online at firstenergycorp.com

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/stronger-more-reliable-power-coming-to-trumbull-and-ashtabula-counties-302592891.html

SOURCE FirstEnergy Corp.

FAQ

When will FirstEnergy (FE) energize the upgraded Trumbull/Ashtabula line?

The company expects the line to be energized by the end of October 2025.

How many customers will benefit from FirstEnergy (FE) transmission upgrade in Trumbull and Ashtabula?

The project will affect nearly 10,000 residents and businesses in the two counties.

What is the size and cost of the transmission project announced by FirstEnergy (FE)?

The rebuild covers 11.5 miles and cost nearly $19 million.

How does the Trumbull/Ashtabula project fit into FirstEnergy's (FE) wider plans?

It is part of the $28 billion Energize365 grid-modernization program for 2025–2029.

What reliability features were added to the new FirstEnergy (FE) transmission line?

The upgrade added thicker conductors, stronger poles and deep concrete foundations and rerouting connections to reduce outages.

When did construction on the FirstEnergy (FE) transmission rebuild begin?

Construction began in 2023.
Firstenergy Corp

NYSE:FE

FE Rankings

FE Latest News

FE Latest SEC Filings

FE Stock Data

26.86B
547.61M
0.17%
92.8%
4.22%
Utilities - Regulated Electric
Electric Services
Link
United States
AKRON