Work Underway to Strengthen Electric Grid in York County

(Neutral)
Tags

FirstEnergy PA (NYSE: FE) is upgrading its electric grid infrastructure in northwestern York County through its Met-Ed subsidiary. The project aims to enhance service reliability for approximately 300 customers in the Dillsburg area by replacing over a mile of older copper wire with larger-diameter aluminum wire.

The upgrade includes replacing 1.3 miles of wire, 32 wooden poles, 40 fuses, and 149 porcelain insulators along a 13.2-kilovolt power line. Additionally, 49 wildlife guards are being installed to prevent animal-related outages. The project, scheduled for completion in April 2025, is part of FirstEnergy's Long Term Infrastructure Improvement Plan (LTIIP III), a $382 million initiative for Met-Ed's distribution system.

This improvement is part of Energize365, FirstEnergy's broader $28 billion grid evolution program planned for 2025-2029, designed to create a smarter grid capable of accommodating electric vehicles, home electrification, and clean energy sources. The upgrade addresses York County's growing electrical needs, which has seen an 8% population increase since 2010.

Loading...
Loading translation...

Positive

  • None.

Negative

  • None.

News Market Reaction – FE

+2.79%
+2.79% Session move

In the trading session that priced this news, FE gained 2.79%, reflecting a moderate positive market reaction.

Data tracked by StockTitan Argus on the day of publication.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Replacing wires and poles should help prevent or minimize outages for nearly 300 Met-Ed customers

READING, Pa., April 9, 2025 /PRNewswire/ -- FirstEnergy Pennsylvania Electric Company (FE PA), a FirstEnergy Corp. (NYSE: FE) subsidiary doing business as Met-Ed in eastern Pennsylvania, is completing work to upgrade its energy delivery system in northwestern York County to help prevent or minimize the length of service disruptions, particularly during cold or hot weather when customers use more electricity to stay comfortable.

The project centers on replacing more than a mile of older copper wire on a neighborhood power line with larger-diameter aluminum wire capable of transporting more electricity, which should both enhance electric service reliability for about 300 Met-Ed customers in the Dillsburg area and meet the community's growing electrical needs.

John Hawkins, FirstEnergy President, Pennsylvania: "This proactive investment will help position our electric network to accommodate steady growth in York County, which has experienced an 8% increase in population since 2010."

Crews are replacing 1.3 miles of wire, 32 wooden poles, numerous crossarms, 40 fuses and 149 porcelain insulators along a portion of a 13.2-kilovolt (kV) power line that runs through the heart of Dillsburg. The line begins at a substation near Golf Course Road, travels east to Baltimore Street and then north along Baltimore Street to Welty Avenue.  

Crews are also installing 49 wildlife guards along the line to help prevent squirrels and other climbing animals from contacting transformers, fuses and switches, which can damage equipment and cause power outages. Animal guards are rubber boots or sleeves that cover transformer bushings, switches and other energized equipment.

The project is expected to be completed in April.

View and download a photo of line workers replacing a utility pole and crossarms and installing animal guards on the company's Flickr page.

The project is part of FirstEnergy Pennsylvania's Long Term Infrastructure Improvement Plan (LTIIP III), which includes a $382 million initiative to accelerate capital investments to the Met-Ed electric distribution system over five years to help ensure continued electric service reliability for customers.

LTIIP III is part of Energize365, a multi-year grid evolution program focused on transmission and distribution investments that will deliver the power FirstEnergy's customers depend on today while also meeting the challenges of tomorrow. With planned investments of $28 billion between 2025 and 2029, the program is creating a smarter, more secure grid that will meet and exceed reliability targets and accommodate electric vehicles, the electrification of homes and businesses and clean energy sources.

Met-Ed serves approximately 592,000 customers within 3,300 square miles of eastern and southeastern Pennsylvania. Follow Met-Ed on X @Met Ed and on Facebook at facebook.com/MetEdElectric.

FirstEnergy is dedicated to integrity, safety, reliability and operational excellence. Its electric distribution companies form one of the nation's largest investor-owned electric systems, serving more than six million customers in Ohio, Pennsylvania, New Jersey, West Virginia, Maryland and New York. The company's transmission subsidiaries operate approximately 24,000 miles of transmission lines that connect the Midwest and Mid-Atlantic regions. Follow FirstEnergy online at firstenergycorp.com and on X @FirstEnergyCorp.

 

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/work-underway-to-strengthen-electric-grid-in-york-county-302424558.html

SOURCE FirstEnergy Corp.

FAQ

What infrastructure improvements is FirstEnergy (FE) making in York County?

FirstEnergy is replacing 1.3 miles of copper wire with aluminum wire, 32 wooden poles, 40 fuses, and 149 insulators along a 13.2-kV power line in Dillsburg, benefiting 300 customers.

How much is FirstEnergy (FE) investing in Met-Ed's infrastructure through LTIIP III?

FirstEnergy is investing $382 million in Met-Ed's electric distribution system over five years through the Long Term Infrastructure Improvement Plan (LTIIP III).

What is the timeline for FirstEnergy's (FE) Energize365 program and its investment amount?

Energize365 runs from 2025 to 2029 with planned investments of $28 billion to create a smarter, more secure grid system.

How many customers will benefit from FirstEnergy's (FE) York County grid upgrade?

The grid upgrade will enhance electric service reliability for approximately 300 Met-Ed customers in the Dillsburg area.

What measures is FirstEnergy (FE) implementing to prevent power outages in York County?

FirstEnergy is installing 49 wildlife guards, replacing old copper wire with larger aluminum wire, and upgrading poles, fuses, and insulators to prevent outages.