Fermi and TensorWave Agree to Extend Closing Date to October 31, 2026
Fermi and TensorWave push back their large AI data center lease closing to late October while working to finalize financing-related conditions.
Rhea-AI Summary
Fermi (FRMI)/b) and TensorWave have amended their Data Center Lease and Services Agreement to extend the Lease closing date from September 30, 2026 to October 31, 2026, with all other terms unchanged.
The Lease covers 222 MW of total facility power at Fermi's Project Matador campus and represents approximately $6.5 billion in expected total revenue over its initial 15‑year term. The Lease remains subject to closing conditions, including related work letters and guaranties, final operations schedules and service-level agreement, Board approvals, and project-level financing sufficient to fund construction. Fermi is negotiating a guaranty of certain lease obligations with an investment-grade counterparty, and the closing date extension is intended to allow more time to finalize that guaranty and other remaining conditions.Positive
- 222 MW lease at Project Matador with ~$6.5 billion expected revenue over 15 years
- Closing date extended to October 31, 2026, preserving the existing lease terms
- $1.5 billion already invested in Project Matador buildout
- Project Matador expected to ramp to about 17 GW, with capital matched to commercial commitments
Negative
- Lease effectiveness delayed by one month, from September 30 to October 31, 2026
- Lease remains conditional on project-level financing and other closing conditions
- Guaranty of certain lease obligations with an investment-grade counterparty is not yet finalized
News Explained
The lease’s expected economics are unchanged, but closing moves to October 31 while the guaranty and other conditions remain unresolved.
Fermi and TensorWave have signed an amendment extending the lease closing date from
The amendment leaves the other lease terms in effect, so this disclosure changes the timing of the contemplated transaction rather than its stated scope or economics.
The latest supplied fundamentals show
That company-level liquidity measure does not establish the project-level financing condition required for closing.
The named resolution point is
Sources and calculations
- Fermi and TensorWave closing-date extension release (2026-09-22)
- Fermi second-quarter 2026 fundamentals (2026Q2)
- Available liquidity against the last reported quarterly operating outflow, in days at that rate $62,536,000 / ($48,671,000 / 91) = 116.9 days
Details
Market Reaction – FRMI
Following this news, FRMI has declined 1.56%, reflecting a mild negative market reaction. The stock is currently trading at $5.06.
Data tracked by StockTitan Argus (15 min delayed). Upgrade to Gold for real-time data.
Key Figures
- New closing date
- October 31, 2026
- Amended TensorWave lease deadline
- Previous closing date
- September 30, 2026
- Superseded lease deadline
- Expected total revenue
- $6.5 billion
- Initial 15-year lease term
- Facility power
- 222 megawatts (MW)
- TensorWave lease at Project Matador
- Initial lease term
- 15 years
- TensorWave lease
Historical Context
-
Signed 15-year TensorWave lease covering 222 MW and approximately $6.5 billion revenue.
24h Move is the share-price change in the day after each event; other market factors may also have contributed.
Key Terms
service-level agreement technical
investment-grade counterparty financial
behind-the-meter technical
combined-cycle natural gas technical
AI-generated analysis. How Rhea-AI works. Not financial advice.
DALLAS, TX / ACCESS Newswire / September 22, 2026 / Fermi Inc. (NASDAQ:FRMI)(LSE:FRMI), operating as Fermi America™ ("Fermi" or the "Company"), today announced that its wholly owned subsidiary, Fermi Campus 1 LLC, and TensorWave TEX1, LLC ("TensorWave") have signed a First Amendment to their Data Center Lease and Services Agreement (the "Lease"). The amendment extends the closing date under the Lease from September 30, 2026 to October 31, 2026. All other terms of the Lease remain unchanged and in effect. The Lease covers 222 megawatts (MW) of total facility power at Fermi's Project Matador campus and represents approximately
Parties Working Constructively Toward Closing
The Lease, signed in August 2026, provides that its effectiveness is subject to the satisfaction or waiver of specified closing conditions. Those conditions include executing and delivering related work letters and guaranties; finalizing operations schedules and a service-level agreement; obtaining Board approvals; and securing project-level financing sufficient to fund construction of the leased premises.
The Company continues to negotiate a guaranty of certain lease obligations with an investment-grade counterparty. Both parties extended the closing date to allow more time to finalize that guaranty and complete the remaining closing conditions.
The Company believes the extension reflects both parties' continued commitment to the transaction and the constructive posture of all parties in the guaranty discussions.
"Both Fermi and TensorWave remain fully committed to this lease, and our decision to formally extend the closing date together reflects that," said Lee McIntire, Chief Executive Officer of Fermi. "Our remaining work is to finalize the lease guaranty with our counterparty. Those discussions are active, constructive and progressing, and we look forward to closing and delivering Project Matador's first data center for TensorWave."
Project Matador
Fermi America is where AI gets power. The Company is developing one of the world's largest advanced energy and AI ecosystems, on an area in the Texas Panhandle. The site, called Project Matador, is secured or under long-term lease with more than
About Fermi America™
Fermi America™ (Nasdaq & LSE: FRMI) develops next-generation private electric grids that deliver highly redundant power at gigawatt scale to support next-generation intelligence and AI compute. Fermi America™ combines cutting-edge technology with a deep bench of proven world-class multi-disciplinary leaders with a combined 25 GW of experience, to create one of the world's largest, 17 GW next-gen private grid, helping ensure America's energy and AI dominance. The behind-the-meter Project Matador campus is expected to integrate the nation's biggest combined-cycle natural gas project, one of the largest clean, new nuclear power complexes in America, utility grid power, solar power, and battery energy storage, to support hyperscale AI and advanced computing. For additional information visit www.fermiamerica.com
About TensorWave
TensorWave is the AI cloud purpose-built for performance. Powered exclusively by AMD Instinct™ Series GPUs, TensorWave delivers high-bandwidth, memory-optimized infrastructure that scales with the most demanding training and inference workloads. Backed by funding from investors including Magnetar, AMD Ventures, Maverick Silicon, Nexus Venture Partners, and Western Frontier, TensorWave operates one of the world's largest all-AMD GPU clouds and is expanding rapidly to meet global demand. For more information, please visit tensorwave.com
Contacts
Investor Contacts
Barry Sievert | IR@fermiamerica.com
Media
Fermi Inc. Communications | media@fermiamerica.com
Forward-Looking Statements
This press release contains "forward-looking statements" within the meaning of the federal securities laws. These include statements regarding the expected closing of the Lease and the timing thereof; the satisfaction or waiver of the conditions to closing, including the negotiation, execution and delivery of the rent guaranty and other guaranties and the completion of project-level financing; the parties' commitment to the transaction and the status and outcome of ongoing negotiations; the anticipated revenue under the Lease; the expected construction, delivery and operation of the leased premises; the potential exercise of expansion options; and the expected timing, phasing, capacity and configuration of Project Matador. Such statements rest on current expectations and assumptions and are subject to risks and uncertainties, including the risk that the conditions to closing are not satisfied by October 31, 2026 or at all, that the parties are unable to agree on the terms of the rent guaranty, that either party exercises its right to terminate the Lease if the closing conditions are not satisfied, and those described in the Company's filings with the U.S. Securities and Exchange Commission. Actual results could differ materially. There can be no assurance that the closing conditions will be satisfied or that the transactions contemplated by the Lease will be consummated. Forward-looking statements speak only as of today. The Company undertakes no obligation to update them except as required by law.
SOURCE: Fermi Inc.
View the original press release on ACCESS Newswire
FAQ
AI-generated questions and answers. How Rhea-AI works. Not financial advice.
What key closing conditions must be satisfied before the Fermi–TensorWave lease becomes effective?
The Lease’s effectiveness is conditioned on several items: executing and delivering related work letters and guaranties, finalizing operations schedules and a service-level agreement, obtaining required Board approvals, and securing project-level financing sufficient to fund construction of the leased premises.
Why did Fermi and TensorWave agree to extend the closing date?
Both parties extended the closing date to October 31, 2026 to allow more time to finalize a lease guaranty with an investment-grade counterparty and to complete the remaining closing conditions. The company believes the extension reflects the parties’ continued commitment to the transaction.
What is Project Matador and how large could it become?
Project Matador is Fermi America’s behind-the-meter campus in the Texas Panhandle, designed as a large advanced energy and AI ecosystem. The site is secured or under long-term lease with more than $1.5 billion invested in buildout to date and, subject to entering into binding customer agreements, is expected to ramp to approximately 17 GW of next-generation private grid capacity.
What type of infrastructure will support Project Matador’s AI and compute workloads?
Project Matador is expected to integrate the nation’s biggest combined-cycle natural gas project, one of the largest clean, new nuclear power complexes in America, utility grid power, solar power, and battery energy storage to support hyperscale AI and advanced computing on a private grid.
Who is TensorWave and what kind of AI cloud will it run at Project Matador?
TensorWave is an AI cloud provider focused on performance, powered exclusively by AMD Instinct Series GPUs. It offers high-bandwidth, memory-optimized infrastructure for demanding training and inference workloads and operates one of the world’s largest all-AMD GPU clouds, which it is expanding to meet global demand.