Galleon Gold Starts Underground Development at West Cache, Advancing the 86,500-Tonne Bulk Sample Program

Galleon Gold (GGOXF) has started underground development at its 100%-owned West Cache Gold Project in Timmins, Ontario, advancing its planned 86,500-tonne bulk sample program.

(Moderate)
(Neutral)
Tags

Galleon Gold (GGOXF) has started underground development at its 100%-owned West Cache Gold Project in Timmins, Ontario, advancing its planned 86,500-tonne bulk sample program.

The box cut and portal ground support are complete and ramp development is under way toward the first of four planned bulk sample stopes in Zone #9. Recent drilling in this zone has confirmed grade continuity below the planned extraction areas. The company plans to use the bulk sample to collect engineering, geological and operational data to support future mine development and will provide further updates as ramping, stope extraction and processing arrangements progress.

Loading...
Loading translation...

Positive

  • Underground development has commenced at the 100%-owned West Cache Gold Project
  • Planned bulk sample totals 86,500 tonnes to support future mine planning
  • Recent drilling in Zone #9 has confirmed grade continuity below planned extraction areas

Negative

  • None.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Toronto, Ontario--(Newsfile Corp. - September 21, 2026) - Galleon Gold Corp. (TSXV: GGO) (OTCQX: GGOXF) (FSE: 3H90) (the "Company" or "Galleon Gold") is pleased to announce that it has commenced underground development at its 100%-owned West Cache Gold Project (the "Project" or "West Cache") in Timmins, Ontario, a key milestone in the Company's disciplined, phased strategy to de-risk West Cache and advance its planned 86,500-tonne bulk sample.

The box cut and portal ground support are complete, and ramp development has commenced. Underground development is now advancing toward the first of four planned bulk sample stopes in Zone #9, where recent drilling has confirmed grade continuity below the planned extraction areas.

"West Cache has moved from permitting to surface construction to underground development inside a single year, and every step has been delivered on plan," said David Russell, Chairman and CEO of Galleon Gold. "Our objective remains clear: to develop the Project, extract the 86,500-tonne bulk sample, and gather the engineering, geological, and operational information required to support future mine development. Doing that safely, and with our community partners alongside us, is how we intend to build this mine."

Galleon Gold will provide further updates as development advances, including ramping, the start of stope extraction and the processing arrangements for the 86,500-tonne bulk sample. Safety, environmental stewardship and operational excellence remain the Company's first priorities on site.

Figures

Figure 1 shows the box cut face with the jumbo drill in position taken on September 19 while Figure 2 depicts the planned workings for the bulk sample.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/1014/315116_1fca1ae134d4f95b_001.jpg

Figure 1 – Photo of Box Cut Face and Jumbo

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1014/315116_1fca1ae134d4f95b_001full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/1014/315116_1fca1ae134d4f95b_002.jpg

Figure 2 – Planned Portal and Underground Workings for Bulk Sample

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1014/315116_1fca1ae134d4f95b_002full.jpg

Technical Content and Qualified Person

The technical content of this news release has been reviewed and approved by David Young, PE, an independent mining engineer and Qualified Person (QP) as defined in National Instrument 43-101 – Standards of Disclosure for Mineral Projects.

About the West Cache Gold Project

The West Cache Gold Project is an advanced-stage gold exploration project covering approximately 11,600 ha located 13 km west of Timmins, Ontario on Provincial Highway 101. It is situated in the Western Porcupine Gold Camp along the Destor-Porcupine Fault Zone within the Abitibi greenstone belt, approximately 7 km northeast of Pan American Silver's Timmins West Mine. The mining lease area hosts the current Mineral Resource Estimate near the center, with additional exploration targets to the north and south. The Mineral Resource Estimate is contained within the Porcupine Sedimentary Basin, a favourable litho-structural corridor with over 5 km of strike-length on the Property. Mineralization is open in all directions and at depth.

About Galleon Gold

Through a disciplined, phased development strategy, Galleon Gold is advancing the West Cache Gold Project by expanding the resource and progressing an 86,500-tonne bulk sample program designed to de-risk and systematically advance West Cache through the next stage of development.

For further information:
Galleon Gold
R. David Russell
Chairman and CEO
T. (416) 644-0066
info@galleongold.com

Graham Farrell
Investor Relations
T. (416) 842-9003
grahamfarrell@galleongold.com

Forward-Looking Statements

This news release contains certain "forward looking statements", as defined under applicable Canadian securities laws, that reflect the current views and/or expectations of Galleon Gold with respect to its long-term strategy, financing plans, proposed work, plans, bulk sample program and other reports including the PEA for its projects. Forward-looking statements are based on the then-current expectations, beliefs, assumptions, estimates and forecasts about the business and the markets in which Galleon Gold operates. Some of the statements contained herein may be forward-looking statements which involve known and unknown risks and uncertainties. Without limitation, statements regarding potential mineralization and resources, exploration results, expectations, plans, and objectives of Galleon Gold are forward-looking statements that involve various risks. The following are important factors that could cause Galleon Gold's actual results to differ materially from those expressed or implied by such forward-looking statements: changes in the world-wide price of mineral commodities, general market conditions and uncertainty of access to additional capital, risks inherent in mineral exploration, delays in the receipt of government approvals, risks associated with development, construction, mining operations and third party contractor activities, risks related to unanticipated events related to health, safety and environmental matters. There can be no assurance that forward-looking statements will prove to be accurate as actual results and future events may differ materially from those anticipated in such statements. Galleon Gold undertakes no obligation to update such forward-looking statements if circumstances or management's estimates or opinions should change. The reader is cautioned not to place undue reliance on such forward-looking statements.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/315116

FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

What is the purpose of the 86,500-tonne bulk sample at West Cache?

The company states that the bulk sample is designed to extract 86,500 tonnes of material to gather detailed engineering, geological and operational information. This data is intended to support decisions on future mine development and to help systematically de-risk and advance the West Cache Gold Project to its next stage.

What specific underground work has been completed and what is next?

The box cut and portal ground support are complete, and ramp development has started. Underground development is now advancing toward the first of four planned bulk sample stopes in Zone #9. Future updates are expected on ramp progress, the start of stope extraction, and the processing arrangements for the bulk sample.

Where is the West Cache Gold Project located and what is its scale?

The West Cache Gold Project covers approximately 11,600 hectares and is located about 13 km west of Timmins, Ontario, along Provincial Highway 101. It lies in the Western Porcupine Gold Camp along the Destor-Porcupine Fault Zone, within the Abitibi greenstone belt, with the current Mineral Resource Estimate near the center of the mining lease area and additional exploration targets to the north and south.