GoGold Provides Update on Los Ricos South Construction

(Moderate)

Sentiment and the balance of points

Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

GoGold Resources (GLGDF) reported that construction at Los Ricos South remains on schedule, with first silver pour targeted for Q2 2028. At the Jalisco, Mexico, project, process plant site clearing and earthworks are approximately 48% complete and plant design is 95% complete. All equipment orders that require long lead times have been placed.

GoGold has spent US$21 million on the project and committed US$52 million to date. The company does not expect to need new equity or debt offerings to finish construction and, using a silver price of $45/oz, estimates that cash reserves will stay at or above US$100 million during construction.

Loading...
Loading translation...
16 points · 0 major

How this balance works

Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.

It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.

Rhea-AI Sentiment measures something else, the tone of the wording.

0 major · 1 point

Hollow bars mark forward-looking points. How the balance works

Positive

  • Moderate point. Forward-looking: it has not happened yet and may not happen.Los Ricos South construction and procurement remain on or ahead of plan, with first silver pour targeted for Q2 2028
  • Moderate point. Forward-looking: it has not happened yet and may not happen.Cash reserves are projected by GoGold to stay at or above US$100 million during construction, assuming $45/oz silver
  • Moderate point. Forward-looking: it has not happened yet and may not happen.Construction funding is not expected by GoGold to require new equity or debt offerings
  • Minor pointProcess plant site clearing and earthworks are approximately 48% complete, with 180 contractor personnel on site
  • Minor pointLong-lead equipment orders have all been placed
11 minor points
  • Minor pointProcess plant design by M3 and DENM Engineering is 95% complete
  • Minor point. Forward-looking: it has not happened yet and may not happen.Underground mining contractor Cominvi has been selected and is planned to mobilize in Q4 2026
  • Minor pointMine entrance designs are complete, and the related earthworks have begun
  • Minor pointUnderground mine plan refinement began in August 2026
  • Minor point. Forward-looking: it has not happened yet and may not happen.Powerline installation is scheduled to start in Q1 2027
  • Minor point. Forward-looking: it has not happened yet and may not happen.Concrete foundation pouring is scheduled for January 2027
  • Minor point. Forward-looking: it has not happened yet and may not happen.Mine entrance development and ramp blasting are scheduled for January 2027
  • Minor point. Forward-looking: it has not happened yet and may not happen.Paste plant construction is scheduled to begin in January 2027
  • Minor point. Forward-looking: it has not happened yet and may not happen.Hillslope stabilization and mining in the Main/Abra zone are scheduled for March 2027
  • Minor point. Forward-looking: it has not happened yet and may not happen.Grinding mill delivery to the site is scheduled for May 2027
  • Minor point. Forward-looking: it has not happened yet and may not happen.Plant testing and startup preparations are scheduled to begin in January 2028

Negative

  • Moderate pointProject spending and commitments total US$21 million spent and US$52 million committed to date 6.3% of market cap

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Halifax, Nova Scotia--(Newsfile Corp. - November 23, 2026) - GoGold Resources Inc. (TSX: GGD) (OTCQX: GLGDF) ("GoGold", "the Company") is pleased to provide an update on construction at its Los Ricos South project in Jalisco, Mexico. The project is progressing on schedule, and the Company reiterates first silver pour in the second quarter of 2028.

"Construction at Los Ricos South continues to progress according to plan with site clearing and earthworks about halfway complete," said Brad Langille, President and CEO. "Reflecting on recent volatility in the precious metals, it is good to note that our project is a very high margin project, which is less impacted by a decrease in metal price than most. Our very strong balance sheet and substantial cash flows generated at our operating mine in Parral further derisks the project and we do not foresee any need for future equity or debt offerings to complete the project. Based on internal estimates using $45/oz silver, we see our cash reserves maintaining a minimum of US$100 million over the course of the build."

Los Ricos South Construction Highlights

  • Active site works – Site clearing and earthworks at the process plant site are approximately 48% complete with 180 contractor personnel on site.

  • All long-lead orders placed – All long-lead equipment orders have been placed, with procurement continuing on schedule. The long-lead orders include the SAG mill, tailings filter, crusher, electrical switchgear, Merrill-Crowe plant, conveyors, slurry pumps, hydrocyclones, feeders and screens and paste plant pumps.

  • Plant design – the design by M3 and DENM Engineering is 95% complete. Vendor design specifications being inputted to the finals design.

  • Paste Plant design – the design is being carried out by RMS of Sudbury, Canada. The current progress will allow the start of construction in January 2027.

  • Underground mining contractor selected – Cominvi planned to mobilize to site in Q4 2026. Portal designs have been completed by WSP and associated earthworks have begun.

  • Schedule maintained – Construction and procurement remain on or ahead of plan, with first silver pour reiterated for Q2 2028.

To date, the Company has spent US$21 million on the project, with US$52 million committed to date. Following are the key schedule milestones:

Los Ricos South Key Schedule Milestones

  • Earthworks commenced – August 2026
  • Underground mine plan optimization commenced – August 2026
  • Start of powerline installation – Q1 2027
  • Concrete foundation pouring – January 2027
  • Portal development / ramp blasting – January 2027
  • Paste plant construction begins – January 2027
  • Hill-slope stabilization / mining – Main/Abra zone – March 2027
  • SAG mill delivery to site – May 2027
  • Plant commissioning begins – January 2028

Technical information contained in this news release with respect to GoGold has been reviewed and approved by Mr. Bob Harris, P.Eng., who is a non-independent qualified person for the purposes of NI 43-101.

About GoGold Resources
GoGold Resources (TSX: GGD) is a Canadian-based silver and gold producer focused on operating, developing, exploring and acquiring high quality projects in Mexico. The Company operates the Parral Tailings mine in the state of Chihuahua and has the Los Ricos South project, which is in development with a construction decision approved by the Board, and Los Ricos North exploration and development project, both in the state of Jalisco. Headquartered in Halifax, NS, GoGold is building a portfolio of low cost, high margin projects. For more information visit gogoldresources.com.

For further information please contact:

Steve Low
Corporate Development
GoGold Resources
T: 416 855 0435
E: steve@gogoldresources.com

CAUTIONARY STATEMENT:
The securities described herein have not been, and will not be, registered under the United States Securities Act of 1933, as amended (the "U.S. Securities Act"), or any state securities laws, and may not be offered or sold within the United States or to, or for the benefit of, U.S. persons (as defined in Regulation S under the U.S. Securities Act) except in compliance with the registration requirements of the U.S. Securities Act and applicable state securities laws or pursuant to exemptions therefrom. This release does not constitute an offer to sell or a solicitation of an offer to buy of any of GoGold's securities in the United States.

This news release may contain "forward-looking information" as defined in applicable Canadian securities legislation. All statements other than statements of historical fact, included in this release, including, without limitation, statements regarding the Parral tailings mine, the Los Ricos projects, future operating margins, future production and processing, construction timelines and future plans and objectives of GoGold, constitute forward looking information that involve various risks and uncertainties. Forward-looking information is based on a number of factors and assumptions which have been used to develop such information but which may prove to be incorrect, including, but not limited to, assumptions in connection with the continuance of GoGold and its subsidiaries as a going concern, general economic and market conditions, mineral prices, the accuracy of mineral resource estimates, and the performance of the Parral tailings mine. There can be no assurance that such information will prove to be accurate and actual results and future events could differ materially from those anticipated in such forward-looking information.

Important factors that could cause actual results to differ materially from GoGold's expectations include exploration and development risks associated with the GoGold's projects, the failure to establish estimated mineral resources or mineral reserves, volatility of commodity prices, variations of recovery rates, and global economic conditions. For additional information with respect to risk factors applicable to GoGold, reference should be made to GoGold's continuous disclosure materials filed from time to time with securities regulators, including, but not limited to, GoGold's Annual Information Form. The forward-looking information contained in this release is made as of the date of this release.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/325238

FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

When does GoGold expect the first silver pour at Los Ricos South?

GoGold is still targeting Q2 2028 for the first silver pour at Los Ricos South.

What work is scheduled at GoGold’s Los Ricos South project in early 2027?

GoGold’s schedule calls for foundation pouring, mine entrance development and ramp blasting, and the start of paste plant construction in January 2027. Powerline installation is scheduled to start in Q1 2027, and hillslope stabilization and mining in the Main/Abra zone are scheduled for March 2027.