Granite’s Grant Road Widening Project Aims to Improve Traffic Flow and Safety in Tucson
Sentiment and the balance of points
Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

“This multi-phase project will require continuous communication and outreach with the traveling public, local businesses and residents throughout the project,” said Todd Hill, Granite Vice President of Regional Operations. “In addition to serving as an anchor project to the
The project involves widening Grant Road to provide six through lanes and a median with left turn lane pockets. It also includes new curbs, sidewalks, landscaping, traffic signals, streetlights, detention pond, water main replacement, sewer main additions, cross roadway box culverts & storm drains, and a large 96" diameter culvert for storm runoff mitigation.
Granite will utilize its nearby Swan Plant facility to provide 36,000 tons of hot-mix asphalt (HMA), 40,000 tons of aggregate base course, and 32,500 tons of storm/water/sewer bedding and shading sand.
“This multi-phase project will require continuous communication and outreach with the traveling public, local businesses and residents throughout the project,” said Todd Hill, Granite Vice President of Regional Operations. “In addition to serving as an anchor project to the
The project is anticipated to begin in April 2024 and is expected to be completed by December 2026.
About Granite
Granite is America’s Infrastructure Company™. Incorporated since 1922, Granite (NYSE:GVA) is one of the largest diversified construction and construction materials companies in