Hudbay Receives New Ingerbelle Expansion Permits for Copper Mountain

Hudbay (TSX, NYSE: HBM) received amended Mines Act and Environmental Management Act permits for the New Ingerbelle expansion at Copper Mountain, British Columbia, on Feb 20, 2026.

(Moderate)
(Positive)
Tags

Hudbay (TSX, NYSE: HBM) received amended Mines Act and Environmental Management Act permits for the New Ingerbelle expansion at Copper Mountain, British Columbia, on Feb 20, 2026. The permits enable access to higher-grade gold, a ~3x lower stripping ratio, projected production of 750,000 t Cu, 900,000 oz Au, and 5.5M oz Ag, preserve >800 direct jobs, and are forecast to generate over C$11.5 billion provincial GDP over the mine life. Participation agreements with Upper and Lower Similkameen Indian Bands were refreshed in Feb 2026.

Loading...
Loading translation...

Positive

  • Projected production: 750,000 tonnes copper; 900,000 ounces gold; 5.5M ounces silver
  • Stripping ratio approximately three times lower than current mining areas
  • Preserves more than 800 direct jobs
  • Forecast to generate C$11.5 billion provincial GDP

Negative

  • None.
Argus Feb 20 session
+0.97% close to close Open Argus
Details

News Market Reaction – HBM

On Feb 20, the day this news came out, HBM closed 0.97% above the previous close.

Data tracked by StockTitan Argus for the Feb 20 session.

Market Context

This announcement secures key permits for the New Ingerbelle expansion at Copper Mountain, enabling ...
Analysis

This announcement secures key permits for the New Ingerbelle expansion at Copper Mountain, enabling access to higher‑grade gold and a stripping ratio three times lower than current areas. The project is projected to add about 750,000 tonnes of copper and 900,000 oz of gold, plus 5.5 million oz of silver, and over C$11.5 billion in provincial GDP while preserving more than 800 jobs. In context of recent JV and production milestones, investors may watch how these permits translate into updated technical reports, capital plans, and long-term production guidance.

Key Figures

Copper production potential: 750,000 tonnes copper Gold production potential: 900,000 oz gold Silver production potential: 5.5 million oz silver +4 more
Copper production potential
750,000 tonnes copper
Projected output over extended mine life from New Ingerbelle expansion
Gold production potential
900,000 oz gold
Projected output over extended mine life from New Ingerbelle expansion
Silver production potential
5.5 million oz silver
Projected output over extended mine life from New Ingerbelle expansion
Provincial GDP impact
C$11.5 billion
Forecasted contribution to British Columbia Gross Domestic Product
Jobs preserved
more than 800 jobs
Direct jobs preserved by extending Copper Mountain mine life
Stripping ratio change
three times lower
New Ingerbelle stripping ratio vs current mining areas
Operating history
99 years
Hudbay’s operating history in Canada mentioned in release

Historical Context

5 past events · Latest: Jan 22
5 events
  1. Jan 22

    Exploration partnership

    24h Move
    +0.3%

    Expanded Flin Flon exploration partnership with JOGMEC and Marubeni earn-ins.

  2. Jan 16

    Production update

    24h Move
    -1.1%

    Preliminary 2025 results showing copper and gold production met guidance.

  3. Jan 12

    Strategic investment

    24h Move
    +4.5%

    $600M Mitsubishi investment for 30% Copper World JV interest.

  4. Nov 12

    Earnings update

    24h Move
    +2.4%

    Q3 2025 results with strong EBITDA and improved cash-cost guidance.

  5. Oct 09

    Earnings call notice

    24h Move
    -3.0%

    Announcement of Q3 2025 results conference call and webcast details.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

Key Terms

mines act, environmental management act, ni 43-101, p.geo.
4 terms
mines act regulatory
"The Company received the amended Mines Act and Environmental Management Act permits..."
A Mines Act is a law that sets safety, environmental, licensing and labor rules for mining operations in a country or region. For investors, it matters because the Act determines whether a mine can operate, what permits and inspections are required, what safety and cleanup costs companies must pay, and how disruptions or fines are handled—much like a rulebook that shapes a mine’s operating costs, timelines and legal risk.
environmental management act regulatory
"The Company received the amended Mines Act and Environmental Management Act permits..."
A legislative framework that sets rules for how companies and authorities must prevent pollution, manage natural resources, issue permits, and clean up environmental harm. It matters to investors because these rules determine compliance costs, project approval timelines, legal liabilities, and reputational risk—like building codes for a house, following them avoids fines and expensive repairs, while violations can halt operations or create large, unexpected costs.
ni 43-101 regulatory
"Mr. Brulotte is a qualified person pursuant to NI 43-101.For a description..."
A Canadian regulatory standard that sets the rules for how mining and exploration companies must report mineral resources and reserves, requiring technical reports prepared or signed off by an independent, certified expert. It matters to investors because it creates a consistent, transparent “inspection report” for mining projects, making it easier to compare prospects, judge the reliability of claims, and assess geological and financial risk before investing.
p.geo. technical
"approved by Marc-Andre Brulotte, P.Geo., Director, Global Exploration and Resource..."
P.Geo. is the professional designation for a licensed geoscientist who has met education, experience and ethical requirements to sign off on geological work. Think of it like a stamp of approval from a trained specialist — similar to a licensed engineer or doctor — that the rock, mineral or exploration data and interpretations were prepared by a qualified expert. For investors, seeing a P.Geo. attached to technical reports increases confidence that resource estimates and geological claims follow recognized standards and are less likely to be misleading.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

TORONTO, Feb. 20, 2026 (GLOBE NEWSWIRE) -- Hudbay Minerals Inc. (“Hudbay” or the “Company”) (TSX, NYSE: HBM) is pleased to announce that it has received key permit amendments for the New Ingerbelle expansion project at its Copper Mountain mine located in British Columbia, Canada. The Company received the amended Mines Act and Environmental Management Act permits through the coordinated authorizations process managed by the British Columbia Major Mines Office (“MMO”). This milestone enhances the copper and gold production profile at Copper Mountain, secures a longer mine life, protects more than 800 jobs and ensures continued economic benefits at the local, regional and federal levels.

“The New Ingerbelle permit ensures that we’ll be able to advance this major project while extending our partnership with local communities to facilitate additional growth investments at Copper Mountain and further adds to our 99 years of successful operations in Canada,” said Peter Kukielski, President and Chief Executive Officer at Hudbay. “Our efforts to optimize Copper Mountain, combined with the development of New Ingerbelle, will unlock significant long-term value for all of our stakeholders.”

“The Ingerbelle expansion will ensure hundreds of good jobs are retained for the Princeton community, providing economic benefits to the community and the province for years to come,” said the Honourable Jagrup Brar, Minister for Mining and Critical Minerals for British Columbia. “We are happy to see Hudbay continue its commitment to B.C. and to see this mine continue operating into the future.”

Commitment to Partnership and Engagement

Throughout the permitting process, Hudbay proactively engaged with the MMO, local communities, the Upper Similkameen Indian Band (“USIB”), and the Lower Similkameen Indian Band (“LSIB”) to ensure transparency and collaborative oversight.

“We want to thank the B.C. government, the USIB, the LSIB and our local communities for their open and efficient collaboration throughout the process,” said Robert Carter, Senior Vice President, Canada at Hudbay. “Through our strong commitment to responsible resource development and the expansion of copper production from Copper Mountain, we will be continuing to provide a metal that is vital for electrification and the global energy transition and supporting B.C.’s Critical Mineral Strategy.”

In addition, Hudbay finalized refreshed Participation Agreements with the USIB and LSIB in February 2026, reinforcing the Company’s commitment to strong Indigenous partnerships. Hudbay is committed to working collaboratively with the USIB and LSIB to continue to advance responsible mining practices and environmental stewardship.

Project Merit and Economic Impact

The New Ingerbelle expansion is a transformative development for Copper Mountain, strategically designed to unlock access to higher-grade gold mineralization while significantly improving operational efficiency with a stripping ratio approximately three times lower than current mining areas. Over the mine’s extended lifespan, it is projected to produce approximately 750,000 tonnes of copper, 900,000 ounces of gold, and 5.5 million ounces of silver based on current reserves only. This further positions Copper Mountain as a critical supplier for the global energy transition. Beyond its mineral output, the expansion serves as an economic engine for British Columbia, forecasted to generate over C$11.5 billion in provincial Gross Domestic Product. By securing the mine’s long-term viability, the project preserves more than 800 direct jobs, ensuring long-term financial stability and community investment for the region and the broader province.

Qualified Person and NI 43-101

The scientific and technical information contained in this news release has been approved by Marc-Andre Brulotte, P.Geo., Director, Global Exploration and Resource Evaluation. Mr. Brulotte is a qualified person pursuant to NI 43-101.

For a description of the key assumptions, parameters and methods used to estimate mineral reserves and resources, as well as data verification procedures and a general discussion of the extent to which the estimates may be affected by any known environmental, permitting, legal title, taxation, sociopolitical, marketing or other relevant factors, please see the most recent technical report for Copper Mountain titled "NI 43-101 Technical Report, Updated Mineral Resources and Mineral Reserves Estimate, Copper Mountain Mine”, effective as of December 1, 2023, a copy of which is available under Hudbay's profile on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.gov. 

Forward-Looking Information

This news release contains forward-looking information within the meaning of applicable Canadian and United States securities legislation. Forward-looking information is not, and cannot be, a guarantee of future results or events. Forward-looking information is based on, among other things, opinions, assumptions, estimates and analyses that, while considered reasonable by the company at the date the forward-looking information is provided, inherently are subject to significant risks, uncertainties, contingencies and other factors that may cause actual results and events to be materially different from those expressed or implied by the forward-looking information.

The risks, uncertainties, contingencies and other factors that may cause actual results to differ materially from those expressed or implied by the forward-looking information may include, but are not limited to, risks generally associated with the mining industry, such as economic factors (including future commodity prices, currency fluctuations, energy prices and general cost escalation), litigation, regulatory and landholding risks associated with Hudbay’s British Columbia business unit as well as the risks discussed under the heading “Risk Factors” in Hudbay’s most recent Annual Information Form.

Should one or more risk, uncertainty, contingency or other factor materialize or should any factor or assumption prove incorrect, actual results could vary materially from those expressed or implied in the forward-looking information. Accordingly, you should not place undue reliance on forward-looking information. Hudbay does not assume any obligation to update or revise any forward-looking information after the date of this news release or to explain any material difference between subsequent actual events and any forward-looking information, except as required by applicable law.

About Hudbay

Hudbay (TSX, NYSE: HBM) is a copper-focused critical minerals mining company with three long-life operations and a world-class pipeline of copper growth projects in tier-one mining jurisdictions of Canada, Peru and the United States.

Hudbay’s operating portfolio includes the Constancia mine in Cusco (Peru), the Snow Lake operations in Manitoba (Canada) and the Copper Mountain mine in British Columbia (Canada). Copper is the primary metal produced by the Company, which is complemented by meaningful gold production and by-product zinc, silver and molybdenum. Hudbay’s growth pipeline includes the Copper World project in Arizona (United States), the Mason project in Nevada (United States), the Llaguen project in La Libertad (Peru) and several expansion and exploration opportunities near its existing operations.

The value Hudbay creates and the impact it has is embodied in its purpose statement: “We care about our people, our communities and our planet. Hudbay provides the metals the world needs. We work sustainably, transform lives and create better futures for communities.” Hudbay’s mission is to create sustainable value and strong returns by leveraging its core strengths in community relations, focused exploration, mine development and efficient operations.

For further information, please contact:
Candace Brûlé
Senior Vice President, Capital Markets & Corporate Affairs
(416) 362-8181
investor.relations@hudbay.com


FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

What did Hudbay announce about New Ingerbelle permits on Feb 20, 2026 (HBM)?

Hudbay announced it received amended Mines Act and Environmental Management Act permits for New Ingerbelle. According to the company, the amendments were issued through the British Columbia Major Mines Office coordinated authorizations process and permit advancing the expansion at Copper Mountain.

How much metal is New Ingerbelle expected to produce and what did Hudbay report (HBM)?

New Ingerbelle is projected to produce 750,000 tonnes copper, 900,000 ounces gold, and 5.5 million ounces silver. According to the company, these figures are based on current reserves only and reflect the expansion's expected output.

What jobs and economic impact did Hudbay say New Ingerbelle will deliver in B.C. (HBM)?

Hudbay said the expansion secures more than 800 direct jobs and local economic benefits. According to the company, the project is forecast to generate over C$11.5 billion in provincial GDP during the mine's extended lifespan.

How does New Ingerbelle change mining efficiency at Copper Mountain according to Hudbay (HBM)?

Hudbay reported the expansion will access higher-grade gold and reduce the stripping ratio by about three times. According to the company, the lower stripping ratio significantly improves operational efficiency versus current mining areas.

Did Hudbay update agreements with Indigenous partners for New Ingerbelle (HBM)?

Yes. Hudbay finalized refreshed Participation Agreements with the Upper Similkameen and Lower Similkameen Indian Bands in February 2026. According to the company, the agreements reinforce commitments to Indigenous partnership and responsible development.

Keep reading