HIVE Digital Technologies Subsidiary, BUZZ High Performance Computing, Accelerates Canada's AI Industrial Revolution with Dell Technologies for its AI Cloud Expansion
HIVE (TSXV: HIVE, NASDAQ: HIVE) subsidiary BUZZ announced an agreement with Dell Technologies to deploy a 63-node liquid-cooled Dell PowerEdge XE9680L cluster (504 latest-generation GPUs) into the Bell AI Fabric data center and executed operating agreements to commence phase one.
BUZZ is procuring long-lead components for go-live in H2 2026 and plans Canadian and Swedish sites, each supporting 2,000 GPUs. BUZZ targets a fleet of over 6,000 latest-generation GPUs for its AI cloud by end-2026, projected to add $120 million ARR at an 80% operating margin (after electrical and data center costs), on top of the company’s current $20 million ARR. Combined with >5,000 GPUs already operating, BUZZ targets >11,000 GPUs by end-2026. HIVE also highlights a 70 MW Grand Falls site that can support >25,000 GPUs based on reference architecture.
HIVE (TSXV: HIVE, NASDAQ: HIVE) controllata BUZZ ha annunciato un accordo con Dell Technologies per distribuire un cluster Dell PowerEdge XE9680L raffreddato a liquido da 63 nodi (504 GPU di ultima generazione) nel data center Bell AI Fabric ed ha eseguito accordi operativi per avviare la fase uno.
BUZZ sta fornendo componenti a lungo lead per il go-live nell'H2 2026 e prevede siti in Canada e Svezia, ognuno in grado di supportare 2.000 GPU. BUZZ mira a una flotta di oltre 6.000 GPU di ultima generazione per il suo cloud IA entro la fine del 2026, con una proiezione di aggiungere $120 million ARR a una redditività operativa dell'80% (dopo costi elettrici e di data center), oltre all'attuale ARR di $20 million. Combinando con oltre 5.000 GPU già in funzione, BUZZ punta a oltre 11.000 GPU entro la fine del 2026. HIVE evidenzia anche un sito Grand Falls da 70 MW in grado di supportare oltre 25.000 GPU basato sull'architettura di riferimento.
HIVE (TSXV: HIVE, NASDAQ: HIVE) subsidiaria BUZZ anunció un acuerdo con Dell Technologies para implementar un clúster Dell PowerEdge XE9680L enfriado por líquido de 63 nodos (504 GPU de última generación) en el centro de datos Bell AI Fabric y ejecutó acuerdos operativos para iniciar la fase uno.
BUZZ está obteniendo componentes de larga duración para el go-live en la segunda mitad de 2026 y planea sitios en Canadá y Suecia, cada uno soportando 2.000 GPUs. BUZZ apunta a una flota de más de 6.000 GPUs de última generación para su nube de IA para finales de 2026, con la proyección de añadir $120 millones ARR con un margen operativo del 80% (después de costos eléctricos y de centro de datos), además del ARR actual de $20 millones. Combinado con más de 5.000 GPUs ya en operación, BUZZ apunta a más de 11.000 GPUs para finales de 2026. HIVE también destaca un sitio de 70 MW en Grand Falls que puede soportar más de 25.000 GPUs según la arquitectura de referencia.
HIVE (TSXV: HIVE, NASDAQ: HIVE)의 자회사 BUZZ는 Dell Technologies와 63 노드 액체 냉각 Dell PowerEdge XE9680L 클러스터(최신 세대 GPU 504개)를 Bell AI Fabric 데이터 센터에 배치하고 1단계 시작을 위한 운영 계약을 체결했다.
BUZZ는 가동 시작을 위한 장기 선행 부품을 조달 중이며 H2 2026에 예정되어 있고 캐나다와 스웨덴의 사이트를 계획하고 있으며 각 사이트는 2,000 GPU를 지원한다. BUZZ는 2026년 말까지 AI 클라우드를 위한 최신 세대 GPU 수를 6,000대 이상으로 목표로 하며 ARR를 $120 million로 추가하고 80%의 운영 마진을 기대한다(전력 및 데이터 센터 비용 반영 후), 현재 회사의 ARR $20 million에 더해진다. 이미 작동 중인 GPU가 5,000대 이상과 합쳐 2026년 말까지 11,000대 이상을 목표로 한다. HIVE는 또한 Grand Falls의 70 MW 사이트를 강조하며 참조 아키텍처에 따라 25,000대 GPU 이상을 지원할 수 있다.
HIVE (TSXV : HIVE, NASDAQ : HIVE) filiale BUZZ a annoncé un accord avec Dell Technologies pour déployer un cluster Dell PowerEdge XE9680L refroidi par liquide de 63 nœuds (504 GPU de dernière génération) dans le centre de données Bell AI Fabric et a conclu des accords opérationnels pour lancer la phase une.
BUZZ rachète des composants à long terme pour la mise en service au cours du 2e semestre 2026 et prévoit des sites au Canada et en Suède, chacun capable de prendre en charge 2 000 GPU. BUZZ vise une flotte de plus de 6 000 GPU de dernière génération pour son cloud IA d'ici fin 2026, avec une projection d'ajouter 120 millions de ARR à une marge opérationnelle de 80% (après coûts électriques et coûts du centre de données), en plus du ARR actuel de 20 millions. Combiné à plus de 5 000 GPU déjà en fonctionnement, BUZZ vise plus de 11 000 GPU d'ici fin 2026. HIVE met également en évidence un site Grand Falls de 70 MW qui peut prendre en charge plus de 25 000 GPU selon l'architecture de référence.
HIVE (TSXV: HIVE, NASDAQ: HIVE) Tochtergesellschaft BUZZ gab eine Vereinbarung mit Dell Technologies bekannt, um ein 63-Knoten-Dell PowerEdge XE9680L-Cluster (504 GPUs der neuesten Generation) gekühlt durch Flüssigkeit im Bell AI Fabric Rechenzentrum bereitzustellen und Betriebverträge abzuschließen, um Phase eins zu beginnen.
BUZZ beschafft langlebige Komponenten für den Live-Betrieb im 2. Halbjahr 2026 und plant Standorte in Kanada und Schweden, die jeweils 2.000 GPUs unterstützen. BUZZ zielt darauf ab, bis Ende 2026 eine Flotte von über 6.000 GPUs der neuesten Generation für seine KI-Cloud zu haben, mit der Prognose, 120 Millionen ARR bei einer 80%igen Betriebsrendite (nach Elektrik- und Rechenzentrumskosten) hinzuzufügen, zusätzlich zum aktuellen ARR von 20 Millionen. Kombiniert mit über 5.000 GPUs die bereits im Einsatz sind, zielt BUZZ bis Ende 2026 auf >11.000 GPUs. HIVE hebt auch einen 70-MW Grand Falls Standort hervor, der basierend auf der Referenzarchitektur mehr als 25.000 GPUs unterstützen kann.
هيف (TSXV: HIVE, NASDAQ: HIVE) الشركة التابعة BUZZ أعلنت اتفاقاً مع Dell Technologies لنشر عنقود Dell PowerEdge XE9680L المبرد بالسوائل من 63 عقدة (504 GPU من الجيل الأحدث) في مركز بيانات Bell AI Fabric، وأبرمت اتفاقات تشغيل لبدء المرحلة الأولى.
تقوم BUZZ بتوفير مكونات طويلة الأجل للتشغيل الفعلي في النصف الثاني من 2026 وتخطط لمواقع في كندا والسويد، كل منها يدعم 2,000 GPU. تستهدف BUZZ أسطولاً يتجاوز 6,000 GPU من أحدث أجيال GPUs لسحابة الذكاء الاصطناعي الخاصة بها بحلول نهاية 2026، مع توقع إضافة $120 million ARR عند هامش تشغيلي قدره 80% (بعد تكاليف الكهرباء ومركز البيانات)، بجانب ARR الحالي البالغ $20 مليون. وبالإضافة إلى أكثر من 5,000 GPU قيد التشغيل بالفعل، تستهدف BUZZ أكثر من 11,000 GPU بنهاية 2026. كما تبرز HIVE موقع Grand Falls بقدرة 70 MW يمكنه دعم أكثر من 25,000 GPU وفقاً للمعمارية المرجعية.
- 63-node Dell cluster with 504 latest-generation GPUs deployed to Bell AI Fabric
- Targeting > 6,000 additional GPUs by end-2026
- Projected $120M incremental ARR for BUZZ AI Cloud
- Projected 80% operating margin after electrical and data center costs
- Existing base of > 5,000 GPUs, targeting > 11,000 total by end-2026
- 70 MW Grand Falls site capable of supporting > 25,000 GPUs
- Projected $120M ARR and 80% operating margin are non-GAAP estimates and not guarantees
- All financial projections reflect market sentiment as of September 2025; actual outcomes may vary
Insights
HIVE's BUZZ secures Dell deployment and Bell facility deals to scale an AI cloud aiming for >11,000 GPUs and material ARR growth.
BUZZ advances by deploying a 63-node, liquid-cooled Dell PowerEdge XE9680L cluster with 504 latest-generation GPUs inside the Bell AI Fabric using Dell IR5000 racks, and plans proprietary Canadian and Swedish sites plus long-lead procurement for go-live in
Key dependencies and risks include timely delivery and installation of hardware, successful commissioning of liquid-cooling at scale, and the accuracy of the stated operating margin of
Watch the following concrete milestones: delivery and installation of the Dell IR5000 racks in the Bell AI Fabric, procurement progress and site readiness for Canadian and Swedish facilities toward a
San Antonio, Texas--(Newsfile Corp. - November 17, 2025) - HIVE Digital Technologies Ltd. (TSXV: HIVE) (NASDAQ: HIVE) (FSE: YO0) (the "Company" or "HIVE"), a diversified multinational digital infrastructure company, through its wholly owned subsidiary BUZZ High Performance Computing ("BUZZ"), today announced an agreement with Dell Technologies to deploy its next wave of AI Infrastructure (all amounts in US dollars, unless otherwise indicated). Additionally, BUZZ and HIVE are pleased to announce the operating agreements are executed for the commencement of the first phase of the BUZZ and Bell AI Fabric deployment.
BUZZ will be deploying a 63 node cluster of liquid-cooled Dell PowerEdge XE9680L servers operating 504 of the latest generation GPUs optimized for AI compute, delivered through Dell Integrated Rack Scalable Systems (IRSS). Delivery and installation of the fully-integrated Dell IR5000 racks will be in the Bell AI Fabric data center. This builds on BUZZ's existing partnership with Bell, enabling the expansion of its sovereign AI Cloud.
Scaling for the AI Future
BUZZ recently achieved Bronze status in the Semi-Analysis ClusterMax™ rankings—surpassing numerous publicly traded peers in the AI cloud sector and validating its technical leadership.
In addition to the Bell AI Fabric facility, BUZZ has proprietary high-efficiency liquid-cooled data center designs in Canada and Sweden, and BUZZ is procuring long-lead components for go-live in the second half of calendar 2026. Each Canadian and Swedish site, alongside the Bell AI Fabric facility, will support 2,000 additional latest generation GPUs to expand the BUZZ AI Cloud for 2026. In total, BUZZ targets a fleet of over 6,000 latest generation GPUs for AI cloud by the end of 2026. This is projected to generate an additional
Combined with over 5,000 GPUs already in operation, this would bring the BUZZ AI Cloud to a total of over 11,000 GPUs by the end of 2026.
Furthermore, the HIVE 70 megawatt ("MW") operation Tier I data center in Grand Falls, New Brunswick with 32.5 acres of land enables BUZZ to upgrade the facility for hyperscaler colocation in a Tier III+ (PUE <1.3) data center, which can provide capacity for over 25,000 latest generation GPUs, based on reference architecture. BUZZ's HPC capacity footprint is positioned to make major contributions to advancing Canada's position in the global AI race.
*As used herein, "Operating Margin" is calculated by dividing the HPC profit (revenue generated from HPC activities minus electrical and data center costs related to those activities) by the total revenue generated from HPC activities and expressed as a percentage. "ARR", as a metric, represents revenue only, and does not represent profitability. ARR is presented here as a measure of growth. These non-GAAP measures should be read in conjunction with and should not be viewed as alternatives to or replacements for measures of operating results and liquidity presented in accordance with GAAP in HIVE's quarterly and annual financial statements. All financial projections reflect current market sentiment and public disclosures as of September 2025; actual outcomes may vary. Investors should conduct their own due diligence.
About HIVE Digital Technologies Ltd.
Founded in 2017, HIVE Digital Technologies Ltd. is the first publicly listed company to mine digital assets powered exclusively by green energy. Today, HIVE builds and operates next-generation blockchain and AI data centers across Canada, Sweden, and Paraguay, serving both blockchain and high-performance computing (HPC) clients. HIVE's twin-turbo engine infrastructure—driven by blockchain and accelerated AI computing—delivers scalable, environmentally responsible solutions for the digital economy.
About BUZZ High Performance Computing
BUZZ, a wholly owned subsidiary of HIVE, specializes in AI Cloud and HPC data center services. With facilities in North America and Europe, BUZZ is engineered to support Canada's ambition in the global AI economy.
For more information, visit hivedigitaltech.com, or connect with us on:
X: https://x.com/HIVEDigitalTech
YouTube: https://www.youtube.com/@HIVEDigitalTech
Instagram: https://www.instagram.com/hivedigitaltechnologies/
LinkedIn: https://linkedin.com/company/hiveblockchain
On Behalf of HIVE Digital Technologies Ltd.,
"Frank Holmes"
Executive Chairman
For further information, please contact:
Nathan Fast, Director of Marketing and Branding
Frank Holmes, Executive Chairman
Aydin Kilic, President & CEO
Tel: (604) 664-1078
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.
Forward-Looking Information
Except for the statements of historical fact, this news release contains "forward-looking information" within the meaning of applicable Canadian securities laws, which may include but is not limited to statements regarding: the expected deployment, timing, capacity, and expansion of BUZZ HPC's GPU-accelerated infrastructure; the potential impact on Canadian AI innovation, competitiveness, and economic growth; compliance with privacy, cybersecurity, and data residency regulations; the use of renewable energy; and any other future-oriented statements. Forward-looking information is based on current expectations, estimates, forecasts, and projections, as well as management's beliefs and assumptions, including that the partnership will proceed as planned, infrastructure will be deployed on the expected timelines and within budget, demand for AI computing will continue to grow, and regulatory requirements will remain consistent with current expectations, and other related risks as more fully set out in the Company's disclosure documents under the Company's filings at www.sec.gov/EDGAR and www.sedarplus.ca.
Forward-looking information involves known and unknown risks, uncertainties, and other factors that may cause actual results, performance, or achievements to differ materially from those expressed or implied by such forward-looking information. Such factors include, but are not limited to: the risk that deployment timelines may change; that costs may exceed expectations; that demand for AI infrastructure may be lower than anticipated; that partnerships or regulatory approvals may not materialize as expected; and the risk factors described in the Company's continuous disclosure documents available on SEDAR+ at www.sedarplus.ca. Readers are cautioned not to place undue reliance on forward-looking information. The Company disclaims any obligation to update or revise any forward-looking information, whether as a result of new information, future events, or otherwise, except as required by law.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/274718