Heliostar Presents Stronger Economics at the La Colorada Mine in Updated Technical Report
Heliostar Metals (OTCQX: HSTXF) released an updated La Colorada technical report showing stronger economics and resource growth. Key base-case metrics include a US$66.2M after-tax NPV (5%), 24.4% IRR, and US$44.5M initial CAPEX at a US$2,300/oz gold price. The study forecasts a 6.1-year mine life, average AISC of US$1,626 per AuEq oz, and recovered gold of 286.3k oz. Indicated resources increased by 62k oz to 513k oz. Permits were received in Aug–Sep 2025 to expand the leach pad; further drilling in Q4 2025 targets converting up to 28k oz from Veta Madre Plus to reserves.
The report shows improved NPV/IRR versus January 2025, lower initial capital, and upside at higher gold prices (NPV US$243.3M at US$3,500/oz).
Heliostar Metals (OTCQX: HSTXF) ha pubblicato un aggiornamento del rapporto tecnico su La Colorada che mostra economie più solide e una crescita delle riserve. Le metriche di base principali includono un NPV post-tasse US$66,2 milioni (5%), IRR 24,4% e CAPEX iniziale US$44,5 milioni a un prezzo dell'oro di US$2.300/oz. Lo studio prevede una vita utile della miniera di 6,1 anni, una media di AISC di US$1.626 per oncia AuEq, e oro recuperato di 286,3k oz. Le riserve indicate sono aumentate di 62k oz a 513k oz. Nel periodo agosto-settembre 2025 sono stati rilasciati i permessi per espandere il pad di liscivia; ulteriori trivellazioni nel quarto trimestre 2025 mirano a convertire fino a 28k oz da Veta Madre Plus in riserve.
Il rapporto mostra un NPV/IRR migliorati rispetto a gennaio 2025, un capitale iniziale più basso e potenzialità a prezzi dell’oro più elevati (NPV US$243,3M a US$3.500/oz).
Heliostar Metals (OTCQX: HSTXF) publicó un informe técnico actualizado sobre La Colorada que muestra una economía más sólida y crecimiento de recursos. Las métricas base clave incluyen un NPV posterior a impuestos de US$66,2 millones (5%), IRR del 24,4% y CAPEX inicial de US$44,5 millones a un precio del oro de US$2.300/oz. El estudio prevé una vida útil de la mina de 6,1 años, un AISC promedio de US$1.626 por onza AuEq, y oro recuperado de 286,3k oz. Las reservas indicadas aumentaron en 62k oz a 513k oz. Se obtuvieron permisos en ago-sep de 2025 para ampliar la pila de lixiviación; nuevos barrenos en el Q4 2025 buscan convertir hasta 28k oz de Veta Madre Plus en reservas.
El informe muestra un NPV/IRR mejorado respecto a enero de 2025, menor CAPEX inicial y potencial en precios más altos del oro (NPV US$243,3 M a US$3.500/oz).
헬리오스타 메탈스(OTCQX: HSTXF)는 La Colorada에 대한 업데이트된 기술 보고서를 발표하여 경제성이 강화되고 자원 증가를 보여주었습니다. 주요 기본 매개변수로는 세후 NPV US$66.2M(5%), IRR 24.4%, 초기 CAPEX US$44.5M가 있으며 금 가격 US$2,300/oz에서 산정됩니다. 연구는 6.1년의 광산 수명, 평균 AuEq 온스당 AISC US$1,626, 회수된 금 286.3k oz를 예측합니다. 표시된 자원은 62k oz 증가하여 513k oz로 늘어났습니다. 2025년 8–9월에 재처리 패드를 확장하기 위한 허가를 받았으며, 2025년 4분기에는 Veta Madre Plus에서 최대 28k oz을 매장화로 전환하는 것을 목표로 추가 시추를 진행합니다.
보고서는 2025년 1월 대비 NPV/IRR이 개선되었고 초기 자본이 낮으며 금 가격이 높아질 때의 상승 여지가 있습니다(US$3,500/oz에서 NPV US$243.3M).
Heliostar Metals (OTCQX: HSTXF) a publié un rapport technique mis à jour sur La Colorada montrant une économie plus robuste et une croissance des ressources. Les métriques de base clés incluent une VAN après impôt US$66,2 millions (5%), TRI 24,4%, et CAPEX initial US$44,5 millions à un prix de l’or de US$2.300/oz. L’étude prévoit une durée minière de 6,1 ans, une AISC moyenne de US$1.626 par oz AuEq, et de l’or récupéré de 286,3k oz. Les ressources indiquées ont augmenté de 62k oz pour atteindre 513k oz. Des permis ont été délivrés en août-septembre 2025 pour élargir la plate-forme de lixiviation; d’autres forages au T4 2025 visent à convertir jusqu’à 28k oz de Veta Madre Plus en réserves.
Le rapport montre une NPV/IRR améliorée par rapport à janvier 2025, un capital initial plus faible et un potentiel à des prix de l’or plus élevés (NPV US$243,3M à US$3.500/oz).
Heliostar Metals (OTCQX: HSTXF) veröffentlichte einen aktualisierten technischen Bericht zu La Colorada, der eine stärkere Wirtschaftlichkeit und ein Wachstum der Ressourcen zeigt. Wichtige Grundkennzahlen umfassen einen nach Steuern NPV von US$66,2 Mio. (5%), IRR von 24,4% und initiales CAPEX von US$44,5 Mio. bei einem Goldpreis von US$2.300/oz. Die Studie prognostiziert eine Minenlebensdauer von 6,1 Jahren, einen durchschnittlichen AISC von US$1.626 pro AuEq-Unze und recyceltes Gold von 286,3k Unzen. Indizierte Ressourcen stiegen um 62k Unzen auf 513k Unzen. Genehmigungen wurden im Aug–Sep 2025 erteilt, um die Liesche-Pad zu erweitern; weitere Bohrungen im Q4 2025 zielen darauf ab, bis zu 28k Unzen von Veta Madre Plus in Reserven umzuwandeln.
Der Bericht zeigt eine verbesserte NPV/IRR im Vergleich zu Januar 2025, niedrigere anfängliche Kapitalkosten und Aufwärtspotenzial bei höheren Goldpreisen (NPV US$243,3 Mio. bei US$3.500/oz).
Heliostar Metals (OTCQX: HSTXF) أصدرت تقريراً فنياً محدثاً عن لا كولورادا يظهر اقتصاديات أقوى ونمو الموارد. المقاييس الأساسية تشمل صافي القيمة الحالية بعد الضرائب US$66.2 مليون (5%)، معدل العائد الداخلي 24.4%، و الإنفاق الرأسمالي الأولي US$44.5 مليون عند سعر ذهب US$2,300/أونصة. تتوقع الدراسة عمر المنجم 6.1 سنوات، ومتوسط AISCUS$1,626 لكل أونصة AuEq، وذهب مسترد مقداره 286.3 ألف أونصة. زادت الموارد المباشرة بمقدار 62 ألف أونصة لتصل إلى 513 ألف أونصة. تم الحصول على التراخيص في أغسطس–سبتمبر 2025 لتوسيع لوح الترشيح؛ وتستهدف حفر إضافية في الربع الرابع 2025 تحويل حتى 28 ألف أونصة من Veta Madre Plus إلى احتياطيات.
يظهر التقرير تحسناً في NPV/IRR مقارنةً بيناير 2025، وتكاليف رأس مال ابتدائية أقل وفرص صعود عند ارتفاع أسعار الذهب (NPV US$243.3 مليون عند US$3,500/أونصة).
Heliostar Metals (OTCQX: HSTXF) 发布了 La Colorada 的更新技术报告,显示出更强的经济性和资源增长。关键基本指标包括一个 税后净现值 US$66.2M(5%)、内部收益率 24.4%,以及 初始资本支出 US$44.5M,金价为 US$2,300/oz。研究预测矿山寿命为 6.1 年,平均 AuEq 每盎司的综合开采成本 AISC US$1,626,回收的金量为 286.3千盎司。示指资源增加了 62千盎司,达到513千盎司。已在 2025 年 8–9 月获得许可以扩展浸出垫;2025 年第四季度的进一步钻探目标是将 Veta Madre Plus 转换为储量的最多 28千盎司。
报告显示相对于 2025 年 1 月,NPV/IRR 提升,初始资本更低,金价走高时存在上行空间(在 US$3,500/oz 时 NPV 为 US$243.3M)。
- After-tax NPV5% of US$66.2M at US$2,300/oz
- Base-case IRR 24.4% (upside IRR 168.4% at US$3,500/oz)
- Initial capital cost reduced to US$44.5M (‑17% vs Jan 2025)
- Indicated resources increased by 62k oz to 513k oz
- Average AISC of US$1,626 per AuEq oz over a 6.1-year LOM
- Probable mineral reserves essentially unchanged at 376.2k oz (‑0.8k oz)
- Forecast mine life shortened to 6.1 years (‑6% vs prior study)
- Maximum projected negative cash flow of US$117.6M at base gold price due to pre-stripping
- Reserves constrained by recognition of faults requiring more conservative pit wall angles
Technical Report Highlights:
Base Case shows US
$66.2M post tax NPV5,24.4% IRR, with a payback multiple of 1.9 at a US$2,300 /oz gold priceUpside Case shows US
$243.3M post tax NPV5,168.4% IRR, with a payback multiple of 8.4 at a US$3,500 /oz gold price286k ounces of gold produced at an AISC of US
$1,626 per AuEq ounce over a 6.1-year mine life with US$45M initial CAPEXUS
$40M increase in base case post-tax NPV5 and US$9.4M reduction in initial capital expenditure from the previous technical reportLa Colorada Indicated Mineral Resources grow by 62k ounces to 513k ounces, grading 0.79 grams per tonne
Expansion potential with Veta Madre Plus. Potential to convert up to 28k Indicated Mineral Resource ounces to Mineral Reserves to support a larger pit with drilling to be completed in Q4, 2025
Permits received in August and September 2025 to expand the leach pad at La Colorada
Vancouver, British Columbia--(Newsfile Corp. - October 17, 2025) - Heliostar Metals Ltd. (TSXV: HSTR) (OTCQX: HSTXF) (FSE: RGG1) ("Heliostar" or the "Company") is pleased to announce the results of an updated study on the La Colorada Mine ("La Colorada"). This updated life of mine plan includes the results from the first two phases of drilling performed from November 2024 to March 2025 from the Company's ongoing ~20,000-metre drilling campaign.
Heliostar CEO, Charles Funk, commented, "Today's results show that the La Colorada mine can continue to be a high-margin, low CAPEX operation with a 6.1-year mine life. This updated study is focused on the open pits at La Colorada, demonstrating positive economics at conservative gold prices and a compelling opportunity at current gold prices. The Company aims to continue to maximize cash generation from stockpiles in the near term and internally fund capital requirements for open-pit production planned in 2027. Indicated gold resources grew significantly with higher or maintained resource grades at El Crestón and Veta Madre. Reserves remained almost unchanged with ounces defined by new drilling offset with more conservative pit wall angles at the El Crestón pit."
"Beyond this study, three clear growth opportunities exist - Veta Madre Plus, an expanded pit at El Crestón and the exploration potential of the larger land package. Veta Madre Plus will be tested with an infill drilling program this quarter that could quickly show the ability to expand the pit and add an additional 28k ounces of reserves. Should higher gold prices sustain, a larger pit at El Crestón may allow for steeper pit walls, increasing reserves. The exploration potential of La Colorada remains significant with open resources and compelling exploration targets across the property. These have been virtually untested over the last 10 years despite their proximity to permitted mine infrastructure - this will change in late 2025 and 2026."
The technical report supporting this news release will be available on SEDAR+ (www.sedarplus.ca) and on the Company's website (www.heliostarmetals.com) within the next 45 days. The La Colorada technical report that is the subject of this news release will be reported in United States dollars (USD or US$) unless otherwise noted.
La Colorada Mine Updated Technical Report
Mineral Resource and Mineral Reserve estimates, as well as a life-of-mine (LOM) plan, were updated for the
The study includes updated Mineral Resource and Mineral Reserve estimates for Veta Madre and El Crestón. The LOM plan indicates an overall Probable Mineral Reserve of 376.2k ounces of gold (a decrease of 0.8k ounces of gold compared to the previous technical report due to mining depletion), with Veta Madre having a forecast mine life of 1.3 years and El Crestón a forecast mine life of 4.6 years, respectively. The operation will have production rates up to the 13,000 t/d nameplate throughput capacity of the process plant at an estimated LOM average US
The La Colorada technical report is anticipated in November 2025.
Key Highlights
La Colorada - Mineral Reserve & Forecast Production Highlights | |
Probable Mineral Reserves (kt) 1 | 17,117 |
Gold Grade (g/t Au) | 0.68 |
Contained Gold (koz Au) | 376.2 |
Silver Grade (koz Ag) | 9.2 |
Contained Silver (koz Ag) | 5,055.9 |
Contained GEO (k GEO) 2 | 385.4 |
Processing Rate (t/d average) 3 | 8,200 |
Life of Mine (years) 4 | 6.1 |
Annual Production (oz GEO per year, average 2025-2031) 4 | 46,106 |
- Probable Mineral Reserve.
- GEO - Gold Equivalent Ounces.
- Processing throughput rates vary over the life of the mine, up to the nameplate capacity of the process plant, about 13,000 t/d.
- Includes production from the Junkyard Stockpile from May 2025 onwards.
La Colorada - Forecast Financial Highlights | |
Average Cash Operating Costs (US$ per payable oz GEO) 1 | 1,533 |
Average AISC (US$ per payable oz GEO) 1 | 1,626 |
Total Initial Capital Cost (US$M) 2 | 44.5 |
Total Sustaining Capital Cost (US$M) 2 | 12.5 |
Total Life of Mine Capital Cost (US$M) 3 | 63.8 |
- Non-International Financial Reporting Standards (IFRS) measures. All-in sustaining costs (AISC) were first issued by the World Gold Council (WGC) in 2013, with an updated Guidance note issued in 2018.
- The initial capital cost reflects capital and capitalized investment before the first metals production from Veta Madre. Total sustainable capital cost of US
$12.5 million is included for capitalized pre-strip before first metals production from El Crestón. - Includes US
$7.0 million reclamation expenditure at the end of the mine life.
La Colorada Forecast Return Estimates based on Gold Price 1, 2 | |||
US | US | ||
IRR (%) | 24.4 | 168.4 | |
NPV @ | 66.2 | 243.3 | |
Payback (years) | 3.4 | 2.0 |
- All other key parameters are set at base assumptions, including the
5% discount rate used. More detailed analysis will be presented in the full technical report. - After tax return estimates.
- Base gold price assumption used in the La Colorada technical report.
- Comparison of the gold price of US
$3,500 with reference to the US$4,110.82 London Bullion Market Association (LBMA) PM gold price on the trading day of October 15, 2025.
The study shows improved economics on the majority of the key metrics. The table below outlines the differences in the base case between the January 2025 technical report and the updated technical report. Drilling completed in 2024 and 2025 contributed additional indicated gold ounces (39k ounces at El Crestón and 30k ounces at Veta Madre). Reserves and LOM gold production have not materially changed due to recognition of faults in the El Crestón pit wall requiring more conservative pit wall designs. Resequencing production from the three deposit areas further improved the economics, increasing the NPV and the IRR in the updated technical report for La Colorada compared to the January 2025 technical report for the operation.
Changes in Key Metrics | |||
January 2025 Technical Report | Updated Technical Report | Change | |
Gold Price | US | US | |
After Tax NPV5% | US | US | |
After Tax IRR | |||
LOM Cash Flow | US | US | |
Payback multiple | 1.4x | 1.9x | |
Reserve gold ounces | 377 koz | 376.2 koz | - |
Reserve gold grade | 0.65 g/t | 0.68 g/t | |
GEOs produced | 297 koz | 293 koz | - |
Mine life | 6.5 years | 6.1 years | - |
Initial Capital Cost | US | US | - |
Total Cash Costs (per GEO) | US | US | |
AISC (per GEO) | US | US | - |
The LOM plan outlines sequential exploitation of the three deposits beginning with continued mining from the Junkyard Stockpile through 2025, followed by exploitation from Veta Madre, then El Crestón through the following six years.
Figure 1 - Site Overview
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/7729/270792_ff44e226847aeadb_001full.jpg
Note: Infrastructure in green, stockpiles in yellow and open pits in blue
Figure 2 - Ore Mined by Pit Phase
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/7729/270792_figure2.jpg
Note: Figure prepared by Hard Rock Consulting, 2025
La Colorada Forecast Operating Cost Estimates
The mining method and process circuit at the La Colorada Mine remains unchanged for the proposed LOM plan compared to the January 2025 technical study. The exploitation of the three deposits benefits from the existing infrastructure at the mine, including the installed crushing and stacking equipment with a capacity of 13,000 tonnes per day. The expected operating performance and operating cost forecasts were compiled with the benefit of benchmarking current and historical performance at La Colorada, the industry standard processes being used at the mine informing the expected consumption quantities of key supplies, and commercial pricing for goods and services in Mexico.
Total Operating Cost Summary
Operating Costs | Operating Cost (US$/oz AuEq) | Operating Cost (US$/t ore) | Operating Cost (US$/t mined) |
Total mining | 1,087 | 18.64 | 2.11 |
Total processing | 350 | 6.00 | |
Total site general and administrative | 68 | 1.17 | |
Refinery and transport | 28 | 0.48 | |
Cash operating costs | 1,533 | 26.28 | |
Production taxes | 46 | 0.78 | |
Royalties | 23 | 0.39 | |
Total cash costs | 1,602 | 27.46 | |
Sustaining capital costs | 23 | 0.40 | |
Total AISC | 1,626 | 27.86 |
La Colorada Forecast Capital Cost Estimates
The Junkyard Stockpile is currently in production and requires only working capital.
The initial capital cost for Veta Madre is estimated at US
The initial sustaining capital cost for El Crestón is estimated at US
The LOM plan includes US
Forecast Capital Cost Summary
Capital Costs | Initial (US$M) | Sustaining (US$M) | Total LOM (US$M) |
Mine pre-production development | 30.1 | 12.5 | 42.6 |
Contractor mobilization | 0.2 | 0.0 | 0.2 |
Slope radar system | 0.5 | 0.0 | 0.5 |
Leach pad expansion | 11.9 | 0.0 | 11.9 |
Total direct costs | 42.7 | 12.5 | 57.0 |
Owner costs and reclamation | 0.00 | 6.9 | 6.9 |
Indirects and contingency | 1.8 | 0.0 | 1.8 |
Total indirect costs | 1.8 | 6.9 | 8.7 |
Total | 44.5 | 19.3 | 63.9 |
La Colorada Economic Analysis
The economic analysis shows a base case after-tax net present value at a discount rate of
Summary Economic Results
Project Valuation Overview | Units | After Tax | Before Tax |
Total cashflow | US$ M | 105.5 | 162.6 |
NPV @ | US$ M | 66.2 | 108.5 |
Internal rate of return | % | 24.4 | 33.1 |
Payback period | Years | 3.4 | 3.3 |
Payback multiple | 1.9 | 2.4 | |
Total initial capital | US$ M | 44.5 | 44.5 |
Metal Prices
The gold market has experienced significant upward price movement in the past few years. The gold price is about
The sensitivity analysis presents gold price scenarios up to US
With ongoing exploitation of the Junkyard Stockpile during 2025, the project will generate revenues from sales based on current gold prices, which are expected to be significantly higher than the base case gold price used in the study.
The LOM plan and Mineral Reserves estimates are most sensitive to changes in the gold price and gold grade. Since silver is projected to contribute only about
Gold Price Sensitivity Analysis
Au Price (US$/oz Au) | Net Cash Flow (US$M) | After-Tax NPV @ (US$ M) | IRR (%) | Payback Period (years) | Payback Multiple |
500 | -444.25 | -364.85 | - | - | 0.0 |
800 | -335.58 | -280.57 | - | - | 0.0 |
1100 | -227.32 | -196.62 | - | - | 0.0 |
1400 | -120.04 | -113.37 | - | - | 0.0 |
1700 | -12.88 | -30.20 | - | 6.0 | 0.0 |
2000 | 50.44 | 21.07 | 3.8 | 1.3 | |
2300 | 105.45 | 66.21 | 3.4 | 1.9 | |
2600 | 160.45 | 111.05 | 3.0 | 2.8 | |
2900 | 215.46 | 155.36 | 2.6 | 4.5 | |
3200 | 270.46 | 199.36 | 2.3 | 6.6 | |
3500 | 325.47 | 243.35 | 2.0 | 8.4 | |
3800 | 380.47 | 287.35 | - | 0.7 | 10.4 |
4100 | 435.48 | 331.35 | - | 0.5 | 12.8 |
Note: Dash indicates values have exceeded the limits of parameters calculated using the economic model
Commentary by Company on Next Steps, Funding and Additional Opportunities
The mining of the Junkyard Stockpile will continue through the remainder of 2025. The Company expects to mine additional stockpile material already identified ahead of production from the Veta Madre Pit.
The total Mineral Reserve in the study is 374.9k ounces of gold, including the Junkyard Stockpile, Veta Madre and El Crestón.
The Veta Madre Mineral Reserve can be exploited subject to receiving a Change of Land Use (CUS) permit, which the Company expects to receive in late 2025. The El Crestón expansion is expected to be sequenced into the schedule in 2027.
In August and September 2025, the Company received approvals of modifications to two existing environmental permits; the modifications authorize the expansion of the current leach pad to include an additional 9.6Mt of capacity. This is forecast to be sufficient to mine and process material from stockpiles included in the mining sequence and the Veta Madre pit. An additional leach pad expansion is planned for the processing of material from the El Crestón expansion and will require an amendment of an existing environmental permit.
Since the development plan for La Colorada represents a continuation of the historical operations, minimal capital investment is required for new equipment and facilities; however, pre-stripping at Veta Madre and El Crestón will need to be funded. The Company expects this to come from a combination of cash generated from the operations and potentially additional non-dilutive project financing if required.
A number of opportunities at La Colorada will become a focus for the Company upon submission of the updated technical report
Stockpiles have the potential to fund stripping costs at Veta Madre. Drilling and analysis of their financial viability is ongoing and expected to be completed in Q4, 2025
28k Indicated Mineral Resource ounces at Veta Madre are not included in the mine plan. Infill drilling of these areas is planned for 2025, and the company is targeting converting these to reserves that would support a larger pit, known as the Veta Madre Plus pit
A larger pit at El Crestón may allow for steeper pit walls, increasing resource to reserve conversion at this deposit
Drilling beneath the current pit boundary at El Crestón revealed widths and grades of gold mineralized veins that maybe amenable to underground mining. The Company will further explore extensions of high-grade mineralization at depth at El Crestón and Gran Central in late 2025 and 2026
Outside the boundaries of the Mineral Resource estimate, several exploration targets remain largely unexplored. These include fault offsets from known mineralization, consistent gold-in-soil anomalies above 0.2 g/t, and areas with undrilled rock chip samples exceeding 1 g/t gold in zones of strong alteration. Further prospecting, geophysics, drill targeting and drilling are planned for the remainder of 2025 and 2026.
The La Colorada concession area covers 10,085ha and has seen very limited exploration beyond the immediate areas where Mineral Resources have been estimated.
Figure 3 - Veta Madre Plus Opportunity
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/7729/270792_ff44e226847aeadb_003full.jpg
Mineral Resource Estimates
Mineral Resources were estimated at La Colorada for three deposits: El Crestón, Veta Madre and the Junkyard Stockpile, and are summarized in the following table. Mineral Resources have an effective date of April 30, 2025 and are reported in situ, using the 2014 Canadian Institute of Mining, Metallurgy and Petroleum Definition Standards for Mineral Resources and Mineral Reserves (2014 CIM Definition Standards).
Mineral Resources Statement
Classification | Zone | Tonnes (kt) | Gold Grade (g/t) | Silver Grade (g/t) | Contained Gold Metal (koz) | Contained Silver Metal (koz) |
Indicated | El Creston | 13,678 | 0.91 | 13.0 | 402 | 5,721 |
Veta Madre | 3,915 | 0.74 | 3.6 | 94 | 452 | |
Junkyard | 2,620 | 0.21 | 7.2 | 18 | 602 | |
Total | 20,213 | 0.79 | 10.4 | 513 | 6,776 | |
Inferred | El Creston | 34 | 0.40 | 19.1 | 0 | 21 |
Veta Madre | 94 | 0.44 | 2.1 | 1 | 6 | |
Junkyard | 1,017 | 0.46 | 38.7 | 15 | 1,264 | |
Total | 1,144 | 0.45 | 35.1 | 17 | 1,291 |
Notes to accompany Mineral Resource table:
- Mineral Resources are reported insitu, using the 2014 CIM Definition Standards, and have an effective date of April 30, 2025. The Qualified Person for the estimate is Mr. David Thomas, P.Geo., of Mine Technical Services.
- Mineral Resources are reported inclusive of Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
- Mineral Resource estimates for El Crestón and Veta Madre use the end-of-month October 2024 topography. Mineral Resource estimates for the Junkyard use the end-of-month April 2025 topography.
- Mineral Resources at El Crestón and Veta Madre are constrained by a conceptual pit shell using the following assumptions: a gold price of US
$2,400 /oz Au; a silver price of US$29 /oz Ag; a rock mining cost of US$2.44 /t mined; a backfill mining cost of US$1.75 /t mined; a crushing and leaching cost of US$1.84 /t processed; at El Crestón a process cost of US$4.84 /t processed and at Veta Madre a process cost of US$3.72 $/t; a general and administrative cost of US$1.12 /t processed; a selling cost of US$0.88 /t processed; at El Crestón a gold metallurgical recovery of78% and a silver metallurgical recovery of19% were used. Pit slope angles varied from 22º (pad) to 35-42º (pit). At Veta Madre, a gold metallurgical recovery of67% and a silver metallurgical recovery of5.0% were used. Pit slope angles averaged 45°. - Junkyard Mineral Resources are reported using the following assumptions: a gold price of US
$2,400 /oz Au; a silver price of US$29 /oz Ag; a stockpile rehandle cost of US$1.30 /t mined; a crushing and leaching cost of US$1.72 /t processed; a process cost of US$3.10 /t processed; a general and administrative cost of US$1.15 /t processed; a selling cost of US$0.66 /t processed; a gold metallurgical recovery of66% ; and a silver metallurgical recovery of27% . - Mineral Resources are reported at gold equivalent cut-offs of 0.15 g/t AuEq at El Crestón and Junkyard and 0.13 g/t AuEq at Veta Madre. Gold equivalents are calculated using AuEq = (Au + Ag/equivalency factor), where equivalency factor = ((Au price in US$/g * Au recovery) / (Ag price in US$/g * Ag recovery)). This results in Au:Ag ratios of 1:339.75, 1:1,108.97 and 202.3 respectively.
- Totals may not sum due to rounding.
Mineral Reserve Estimates
Mineral Resources were converted to Mineral Reserves for El Crestón, Veta Madre and the Junkyard Stockpile. Mineral Reserves have an effective date of April 30, 2025, are presented at the point of delivery to the process plant, and are reported using the 2014 CIM Definition Standards.
The Mineral Reserve estimate is based on the operation of the existing crusher and conveyor system having a nameplate throughput capacity of about 13,000 t/d, and continued operation of the heap leach and carbon-in-circuit (CIC) process circuit and refinery to process ore from the three deposits. The Mineral Reserve estimate is presented in the following table.
Mineral Reserves Statement
Classification | Zone | AuEq Cut-off (g/t) | Tonnes (kt) | Gold Grade (g/t Au) | Silver Grade (g/t Ag) | Contained Gold (koz) | Contained Silver (koz) |
Probable | El Crestón | 0.165 | 12,596 | 0.77 | 10.61 | 312.2 | 4,295.3 |
Veta Madre | 0.167 | 2,072 | 0.71 | 3.1 | 47.9 | 207.4 | |
Junkyard Stockpile | 0.149 | 2,449 | 0.20 | 7.0 | 16.1 | 553.2 | |
Total | 17,117 | 0.68 | 9.19 | 376.2 | 5,055.9 |
Notes to accompany Mineral Reserves table:
- Mineral Reserves are reported using the 2014 CIM Definition Standards.
- Mineral Reserves have an effective date of April 30, 2025. The Qualified Person for the estimate is Mr. Jeffery Choquette, PE, of Hard Rock Consulting.
- A 0.165 g/t AuEq cut-off is used for reporting the Mineral Reserves at El Crestón, and a 0.167 g/t AuEq cut-off is used for reporting Mineral Reserves at Veta Madre. Cut-offs were calculated based on a gold price of US
$2,100 /oz Au, silver price of US$25 /oz Ag, processing costs of US$6.68 /t for El Crestón and US$5.56 /t for Veta Madre, general and administrative costs of US$1.12 /t, refining and selling costs of US$0.88 /t, gold recovery of78% for El Crestón and67% for Veta Madre and a silver recovery of19% for El Crestón and5% for Veta Madre. The AuEq cut-off for Junkyard is 0.149 g/t AuEq based on metal prices of US$2,100 /oz Au, and US$25 /oz Ag, processing costs of US$4.82 /t, general and administrative costs of US$1.15 /t, refining and selling costs of US$0.66 /t, gold recovery of66% and a silver recovery of27% . The AuEq calculation uses the formula AuEq = (Au + Ag/equivalency factor), where equivalency factor = ((Au price in US$/g * Au recovery) / (Ag price in US$/g * Ag recovery)). - Mineral Reserves are reported within the ultimate reserve pit design. An external dilution factor of
14% was factored into the Mineral Reserves estimates. - Tonnage and grade estimates are in metric units.
- Mineral Reserve tonnage and contained metal have been rounded to reflect the accuracy of the estimate, and numbers may not add due to rounding.
Qualified Persons
The technical report for the La Colorado Mine will be prepared for Heliostar Metals Inc. by Mr. Todd Wakefield, RM SME, Mr. David Thomas, P.Geo., Mr. Jeffrey Choquette, P.E., Mr. Carl Defilippi, RM SME, and Ms. Dawn Garcia, CPG. Each of these Qualified Persons has reviewed and approved the technical information contained in this news release in their area of expertise and is independent of the Company.
Qualified Persons with respect to this News Release
Gregg Bush, P.Eng. and Mike Gingles, the Company's Qualified Persons, as such term is defined by National Instrument 43-101 - Standards of Disclosure for Mineral Projects, have reviewed the scientific and technical information not derived from the updated technical reports and included in this news release in the Company Overview, Commentary by the Company on Relevant Matters and Commentary by the Company on Next Steps and Permitting sections for each property and have approved the disclosure herein.
Data Verification
In addition, the Qualified Persons for the updated technical report verified the data in the reports in their areas of expertise and concluded that the information supported Mineral Resource and Mineral Reserve estimation and could be used in mine planning and economic analysis. The verification completed by each Qualified Person is discussed in each technical report and included site visits, and could include data audits, suitability of data for use in estimation and mine planning, quality assurance and quality control checks, review of available technical and economic study data, review of data collection and evaluation methods, review of production data including reconciliation where available, review of actual cost data for operations, and review of third-party inputs to forecasts.
The Company's Qualified persons verified the information that was not derived from the technical reports. The data verification included site visits, data audits, review of available study data, review of data collection and evaluation methods, review of production data, including reconciliation where available, review of actual cost data for operations, and review of third-party inputs to forecasts, and consideration of the Company's plans for the projects.
About Heliostar Metals Ltd.
Heliostar aims to grow to become a mid-tier gold producer. The Company is focused on increasing production and developing new resources at the
FOR ADDITIONAL INFORMATION, PLEASE CONTACT:
Charles Funk President and Chief Executive Officer Heliostar Metals Limited Email: charles.funk@heliostarmetals.com Phone: +1 844-753-0045 | Rob Grey Investor Relations Manager Heliostar Metals Limited Email: rob.grey@heliostarmetals.com Phone: +1 844-753-0045 |
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Cautionary Statement Regarding Forward-Looking Information
This news release includes certain "Forward-Looking Statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information" under applicable Canadian securities laws. When used in this news release, the words "anticipate", "believe", "estimate", "expect", "target", "plan", "forecast", "may", "would", "could", "schedule" and similar words or expressions, identify forward-looking statements or information. These forward-looking statements or information relate to, among other things, timing and economics of mineral production, ability to expand production, resources, and exploration potential.
These statements reflect the Company's respective current views with respect to future events and are necessarily based upon a number of other assumptions and estimates that, while considered reasonable by management, are inherently subject to significant business, economic, competitive, political and social uncertainties and contingencies. Many factors, both known and unknown, could cause actual results, performance, or achievements to be materially different from the results, performance or achievements that are or may be expressed or implied by such forward-looking statements or forward-looking information and the Company has made assumptions and estimates based on or related to many of these factors. Such factors include, without limitation: precious metals price volatility; risks associated with the conduct of the Company's mining activities in foreign jurisdictions; regulatory, consent or permitting delays; risks relating to reliance on the Company's management team and outside contractors; risks regarding exploration and mining activities; the Company's inability to obtain insurance to cover all risks, on a commercially reasonable basis or at all; currency fluctuations; risks regarding the failure to generate sufficient cash flow from operations; risks relating to project financing and equity issuances; risks and unknowns inherent in all mining projects, including the inaccuracy of reserves and resources, metallurgical recoveries and capital and operating costs of such projects; contests over title to properties, particularly title to undeveloped properties; laws and regulations governing the environment, health and safety; the ability of the communities in which the Company operates to manage and cope with the implications of public health crises; the economic and financial implications of public health crises, ongoing military conflicts and general economic factors to the Company; operating or technical difficulties in connection with mining or development activities; employee relations, labour unrest or unavailability; the Company's interactions with surrounding communities; the Company's ability to successfully integrate acquired assets; the speculative nature of exploration and development, including the risks of diminishing quantities or grades of reserves; stock market volatility; conflicts of interest among certain directors and officers; lack of liquidity for shareholders of the Company; litigation risk; and the factors identified under the caption "Risk Factors" in the Company's public disclosure documents. Readers are cautioned against attributing undue certainty to forward-looking statements or forward-looking information. Although the Company has attempted to identify important factors that could cause actual results to differ materially, there may be other factors that cause results not to be anticipated, estimated or intended. The Company does not intend, and does not assume any obligation, to update these forward-looking statements or forward-looking information to reflect changes in assumptions or changes in circumstances or any other events affecting such statements or information, other than as required by applicable law.
This news release includes certain non-International Financial Reporting Standards (IFRS) measures. The Company has included these measures, in addition to conventional measures conforming with IFRS, to provide investors with an improved ability to evaluate the project and provide comparability between projects. The non-IFRS measures, which are generally considered standard measures within the mining industry albeit with non-standard definitions, are intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. Cash costs (Cash Costs) are a common financial performance measure in the gold mining industry but with no standard meaning under IFRS. The Company believes that, in addition to conventional measures prepared in accordance with IFRS, certain investors use this information to evaluate each project's economic results in the technical reports and each project's potential to generate operating earnings and cash flow. All-in Sustaining Costs (AISC) more fully defines the total costs associated with producing precious metals. The AISC is calculated based on guidelines published by the World Gold Council (WGC), which were first issued in 2013. In light of new accounting standards and to support further consistency of application, the WGC published an updated Guidance Note in 2018. Other companies may calculate this measure differently because of differences in underlying principles and policies applied. Differences may also arise due to a different definition of sustaining versus growth capital. Note that in respect of AISC metrics within the technical reports because such economics are disclosed at the project level, corporate general and administrative expenses were not included in the AISC calculations.
To view the source version of this press release, please visit https://www.newsfilecorp.com/release/270792