Hut 8 Commercializes First Phase of 1 GW Beacon Point AI Data Center Campus with 15-Year, 352 MW IT Lease with Base-Term Contract Value of $9.8 Billion

(Moderate)
(Neutral)
Tags
crypto AI

Hut 8 (Nasdaq: J) commercialized the first phase of its 1 GW Beacon Point AI data center campus with a 15-year, 352 MW IT lease worth a $9.8 billion base-term contract value and expected cumulative NOI of $9.8 billion over the base term.

Triple-net lease with a high-investment-grade tenant; three 5-year renewal options raise potential contract value to about $25.1 billion. Initial energization and project financing planned to support campus delivery beginning Q1 2027, with first data hall delivery expected Q3 2027.

Loading...
Loading translation...

Positive

  • Base-term contract value of $9.8 billion over 15 years
  • Average annual NOI contribution of approximately $655 million upon stabilization
  • Campus scale: 1,000 MW utility capacity with 352 MW contracted in Phase 1
  • Aggregate contracted AI capacity increased to 597 MW with ~$16.8 billion base-term value

Negative

  • Concentration risk: 352 MW lease represents a large single-tenant exposure
  • Long delivery horizon: initial energization expected Q1 2027 and first hall Q3 2027
  • Project finance dependency: development contingent on securing project-level financing

News Market Reaction – HUT

+35.31%
45 alerts
+35.31% Session close to close
+38.6% Peak in 1 hr 38 min
$12.26B Market Cap
0.4x Rel. Volume

In the May 6 session, HUT gained 35.31%, reflecting a significant positive market reaction. Argus tracked a peak move of +38.6% during that session. Our momentum scanner triggered 45 alerts that day, indicating elevated trading interest and price volatility.

Data tracked by StockTitan Argus on the day of publication.

Market Context

The stock surged +35.3% in the session following this news. A strong positive reaction aligns with m...
Analysis

The stock surged +35.3% in the session following this news. A strong positive reaction aligns with management’s ongoing pivot into large, contracted AI infrastructure. Earlier crypto,AI milestones produced average moves of about 0.79%, while today’s 3.11% gain came as HUT traded near its 52‑week high and well above its 200‑day MA. Investors may weigh sizable long‑term lease value against execution risk on multi‑year build‑outs and financing complexity.

Key Figures

Base-term contract value: $9.8 billion Annual base rent escalator: 3.0% Expected avg annual NOI: $655 million +5 more
8 metrics
Base-term contract value $9.8 billion 15-year Beacon Point IT lease
Annual base rent escalator 3.0% Beacon Point lease terms
Expected avg annual NOI $655 million Beacon Point upon stabilization
Total contracted AI base-term value approximately $16.8 billion All contracted AI data center capacity
Beacon Point IT capacity 352 MW Phase 1 AI factory design
Total contracted AI IT capacity 597 MW Company-wide AI data center contracts
Campus utility capacity 1,000 MW Beacon Point interconnection agreement
Total development pipeline 8,375 MW Energy Capacity across all stages

Previous Crypto,AI Reports

2 past events · Latest: Jan 08 (Positive)
Same Type Pattern 2 events
Date Event Sentiment 24h Move Catalyst
Jan 08 AI data center EPCM Positive +0.1% Jacobs named EPCM lead for River Bend AI data center under major lease.
Jun 24 Strategic AI financing Positive +1.5% $150M Coatue convertible note to fund expansion of AI infrastructure platform.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

Pattern Detected

Prior crypto,AI announcements produced modest positive price moves that aligned with generally positive strategic news flow.

Recent Company History

Over recent crypto,AI updates, HUT has steadily expanded its AI infrastructure strategy. In January 2026, Jacobs was appointed EPCM lead for the River Bend AI data center under a 15-year, $7.0 billion lease covering 245 MW of IT capacity. In June 2024, Hut 8 secured a $150 million strategic investment from Coatue via a convertible note to build a next‑generation AI infrastructure platform. Today’s Beacon Point lease extends this same AI build‑out theme.

Key Terms

triple-net lease, non-gaap financial measure, net operating income (noi), epcm, +1 more
5 terms
triple-net lease financial
"Triple-net lease with high-investment-grade tenant valued at up to $25.1 billion"
A triple-net lease is a rental agreement where the tenant pays the base rent plus the property's operating expenses—typically taxes, insurance, and maintenance—so the landlord receives mostly a steady, predictable cash payment. For investors, it matters because it can act like a low-maintenance, bond-like income stream with clearer expense exposure, but returns depend on the tenant’s financial strength and long-term ability to cover those extra costs.
non-gaap financial measure financial
"This press release includes a non-GAAP financial measure, expected net operating income (NOI)"
A non-GAAP financial measure is a way companies present their financial results that excludes certain expenses or income to show how they believe their core business is performing. It matters because it can give a clearer picture of how the company is really doing, but it can also be used to make results look better than they actually are.
net operating income (noi) financial
"non-GAAP financial measure, expected net operating income (NOI) contribution, which the Company defines"
Net operating income (NOI) is the money a property or business generates from its regular operations after paying direct operating costs (like maintenance, utilities, and staff) but before paying financing costs, taxes, or accounting write‑downs. Investors use NOI to judge how well an asset produces cash from its core activity—think of it as the profit from running a store before paying the mortgage and taxes—so it helps compare properties and value income-producing investments.
epcm technical
"Jacobs, a global scienced-based consulting and advisory firm, is retained as EPCM"
EPCM stands for engineering, procurement and construction management, a contract model where a firm designs a project, buys major equipment and manages contractors rather than doing the actual building work itself. For investors, an EPCM arrangement matters because it usually keeps the project owner more directly responsible for contractor costs, schedules and on-site risks, which can affect budget certainty, timelines and the likelihood of delays or cost overruns. Think of it as hiring an architect and general manager who arranges and oversees the builders rather than having a single company deliver the whole job.
engineering, procurement and construction management technical
"Jacobs ... is retained as EPCM (Engineering, Procurement and Construction Management) lead"
A project delivery approach where a firm handles detailed design, sources major equipment and materials, and oversees construction on behalf of the project owner, acting like the owner’s project manager. It matters to investors because the firm’s performance determines whether a project is built on time, on budget and to specification—similar to hiring a general contractor for a house, where delays or cost overruns directly affect returns, cash flow and project risk.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Triple-net lease with high-investment-grade tenant valued at up to $25.1 billion if all renewal options are exercised

Transaction expands Hut 8's total contracted AI data center capacity to 597 MW with aggregate base-term contract value of approximately $16.8 billion

Hut 8 to deliver a 352 MW AI factory designed to NVIDIA's DSX reference architecture for gigawatt-scale AI infrastructure

Executed under Hut 8's repeatable delivery model with Tier 1 counterparties: American Electric Power (Nasdaq: AEP), Vertiv Holdings Co (NYSE: VRT), and Jacobs (NYSE: J)

MIAMI, May 6, 2026 /PRNewswire/ -- Hut 8 Corp. (Nasdaq, TSX: HUT) ("Hut 8" or the "Company"), an energy infrastructure platform integrating power, digital infrastructure, and compute at scale to fuel next-generation, energy-intensive technologies, today announced the commercialization of the first phase of its Beacon Point data center campus in Nueces County, Texas through a 15-year, $9.8 billion lease (the "Agreement") for 352 megawatts (MW) of IT capacity (the "Transaction"). The tenant, a high-investment-grade company, will deploy dedicated compute infrastructure at the campus to support AI training and inference workloads at hyperscale.

Beacon Point is the second AI data center campus commercialized under the Company's power-first, greenfield development model following River Bend. Hut 8 has executed an interconnection agreement for 1,000 MW of utility capacity, with initial energization expected in Q1 2027. As with River Bend, Hut 8 identified and secured the site through its power-first approach and subsequently commercialized it through a hyperscale AI lease. The Beacon Point transaction brings Hut 8's total contracted AI data center capacity to 597 MW of IT capacity with aggregate base-term contract value of approximately $16.8 billion and aggregate average annual NOI to approximately $1.1 billion.

Transaction Highlights

  • Lease Structure: Triple net (NNN) lease.
  • Tenant Profile: Confidential, high-investment-grade company.
  • Compute Architecture: Hut 8 to deliver a 352 MW AI factory designed to NVIDIA's DSX reference architecture for gigawatt-scale AI infrastructure.
  • Base-Term Contract Value: Total contract value of $9.8 billion over a 15-year base lease term, inclusive of a 3.0% annual base rent escalator.
  • NOI Contribution: Expected cumulative NOI contribution of $9.8 billion over the base lease term, translating to an expected average annual NOI contribution of $655 million upon stabilization.
  • Upside Economics: Three 5-year renewal options increase potential contract value to approximately $25.1 billion assuming all three options are exercised.
  • Delivery Timeline: Initial data hall delivery expected in Q3 2027.
  • Project-level Financing: Hut 8 intends to support the development of Beacon Point with project-level financing that aims to optimize cost of capital at the asset level while maintaining disciplined long-term leverage metrics at the corporate level.
  • Campus Scalability: 1,000 MW of utility capacity with initial energization expected in Q1 2027.
  • Commercial Potential: The lease for 352 MW of IT capacity, requiring approximately 500 MW of utility capacity, represents the first phase of commercialization at a campus designed to support up to 1,000 MW of utility capacity, providing significant runway for potential campus expansion and revenue growth.

Power-First Underwriting and the First Phase of Value Creation

Beacon Point exemplifies Hut 8's power-first development model and the value creation it enables across the asset lifecycle. Originally underwritten on a speed-to-power thesis to serve Hut 8's affiliated customer, American Bitcoin Corp. ("ABTC"), the site was repositioned to AI infrastructure as power demand accelerated and customer requirements broadened. Hut 8 transitioned Beacon Point from its original commercialization pathway with ABTC to deliver an AI data center campus with contracted, investment-grade cash flows, marking the first phase of asset-level value creation at the campus.

Asher Genoot, CEO of Hut 8, said: "Beacon Point underscores why we start with power and maintain flexibility across end markets. Operating across multiple applications lets us underwrite assets that single-use-case developers cannot, then redirect them toward higher-value commercialization pathways as demand evolves. This flexibility is intentional, and it is embedded in how we underwrite, develop, and commercialize infrastructure."

First-Principles Engineering and the Second Phase of Value Creation

Beacon Point also exemplifies Hut 8's first-principles engineering approach and the value creation it enables as technology applications evolve. Following the repositioning of the campus to AI, the first data hall was scoped for 224 MW of IT capacity, sized to the chip architectures commercially deployed at the time. As NVIDIA's DSX reference architecture advanced toward commercial deployment with materially higher rack-level power densities, Hut 8 redesigned the data hall to support a 352 MW AI factory, a 57% increase over the initial design, within the same land and utility footprint.

Scalable, Partnership-Driven Execution Model

Hut 8 is developing Beacon Point through a partnership-driven execution model first implemented at its River Bend campus. The model is structured to mitigate risk across the project lifecycle by aligning Tier 1 partners to defined roles across technology, engineering and construction, and critical systems delivery.

Asher Genoot, CEO of Hut 8, said: "This transaction commercializes the first building of our newest gigawatt-scale campus and marks our second AI data center lease. More importantly, it demonstrates that our development model, which pairs power-first underwriting with disciplined commercialization and institutional execution, is repeatable and extendable across our broader pipeline."

NVIDIA is engaged as technology partner, with Phase 1 of the campus engineered to NVIDIA's DSX reference architecture for gigawatt-scale AI factories. Jacobs, a global scienced-based consulting and advisory firm, is retained as EPCM (Engineering, Procurement and Construction Management) lead, working alongside Vertiv in its role supporting critical digital infrastructure systems.

Bob Pragada, Chair and CEO of Jacobs, said: "Beacon Point underscores the strength of our partnership with Hut 8 and the discipline required to deliver AI infrastructure with speed, safety, and certainty. Building on our work together at River Bend, we are applying our EPCM leadership and advanced digital twin technology to set the benchmark for AI infrastructure deployment, optimization, and resiliency."

Giordano Albertazzi, CEO of Vertiv, said: "Next generation AI infrastructure will be defined by how quickly power can be converted into AI capacity. Partnering with Hut 8 aligns with Vertiv's systems-level approach to converged physical infrastructure —  bringing power, cooling, and deployment execution at scale. At Beacon Point, we are applying Vertiv's global manufacturing depth, supply chain discipline, engineering expertise, and critical digital infrastructure portfolio to help deliver AI capacity with speed, reliability, and long-term performance."

Utility and Regional Partnerships

Hut 8 is developing the Beacon Point campus in collaboration with key Texas stakeholders, including AEP Texas, a subsidiary of American Electric Power (AEP), and the Corpus Christi Regional Economic Development Corporation (CCREDC). Hut 8 and AEP Texas have executed an interconnection agreement for 1,000 MW of utility capacity for the campus, with initial energization expected in Q1 2027.

Hut 8 brings a long operating history in Texas and extensive experience working within ERCOT across large-load applications. This experience has enabled the Company to advance complex infrastructure projects by navigating market dynamics, interconnection processes, and transmission and system upgrade requirements while maintaining disciplined development and execution timelines.

Aaron Bowman, CEO of CCREDC, said: "Beacon Point reflects the type of long-term investment that supports durable growth in the Coastal Bend economy. Hut 8's focus on power infrastructure and disciplined execution aligns with the region's assets and workforce capabilities, and we are pleased to support the advancement of this campus in Nueces County."

Development Pipeline Update

The Transaction advances 500 MW of utility capacity from Energy Capacity Under Development to Energy Capacity Under Construction. An additional 500 MW of utility capacity from Beacon Point remains within Energy Capacity Under Development.  

Hut 8 continues to advance opportunities across a broader pipeline spanning 7,545 MW of Energy Capacity Under Diligence, Exclusivity, and Development, applying the same power-first underwriting framework and institutional execution model demonstrated at River Bend and Beacon Point.

Stage

Description

Utility Capacity   
As of May 6,
2026

Energy Capacity Under
Diligence

Sites identified for large-load use cases such as AI, HPC, ASIC compute, industrial applications such as
next generation manufacturing, and other energy-intensive technologies. At this stage, Hut 8 assesses site
potential by engaging with utilities, landowners, and other stakeholders to evaluate critical factors, including
power availability, infrastructure readiness, fiber connectivity, and overall commercial viability.

 

5,315 MW

Energy Capacity Under
Exclusivity

Sites where Hut 8 has secured a clear path to ownership through either: (i) an exclusivity agreement that prevents
the sale of designated land and power capacity to another party or (ii) a tendered interconnection agreement,
confirming a viable path to securing power and infrastructure for deployment.

1,680 MW1

Energy Capacity Under
Development

Sites where Hut 8 is actively investing in development and commercialization by executing definitive land and/or 
power agreements, advancing site design and infrastructure buildout, and engaging with prospective customers.

550 MW

Energy Capacity Under
Construction

 Sites where Hut 8 has executed a definitive offtake agreement and commenced construction activities.

830 MW

Total

All sites under diligence, exclusivity, development, commercialization, and construction.

8,375 MW1


Note: (1) Excludes 1,000 MW of potential IT expansion capacity at River Bend, for which Fluidstack holds a ROFO under the River Bend lease.

Non-GAAP Financial Measures

This press release includes a non-GAAP financial measure, expected net operating income (NOI) contribution, which the Company defines as expected lease revenue for a particular lease less any non-reimbursable operating expenses attributable to the leased property. The Company's management team uses expected NOI contribution to measure the expected operating performance of a particular lease. Operating income is the GAAP measure most directly comparable to expected NOI contribution. In evaluating expected NOI contribution, you should be aware that in the future the Company may incur non-reimbursable lease operating expenses that are not currently known. The Company's presentation of expected NOI contribution should not be construed as an inference that its future results will be unaffected by unusual or non-recurring items. Expected NOI contribution has important limitations as an analytical tool and you should not consider expected NOI contribution in isolation or as a substitute for analysis of results as reported under GAAP. For example, expected NOI contribution excludes the impact of selling, general and administrative expenses and depreciation and amortization, which have real economic effect and could materially impact the Company's consolidated financial results. Other companies, including Real Estate Investment Trusts, may calculate expected NOI contribution differently than the Company does and, accordingly, the Company's expected NOI contribution may not be comparable to similar measures published by such companies. No reconciliation of expected NOI contribution is included in this press release because the Company is unable to quantify certain amounts that would be required to be included in operating income without unreasonable efforts as such quantification would imply a degree of precision that would be confusing or misleading to investors.

Additional Transaction Information and Upcoming Communications

Hut 8 has made available on its website an investor presentation with further details regarding the Transaction.

For important news and information regarding the Company, including investor presentations and timing of future investor conferences, visit the Investor Relations section of the Company's website, hut8.com/investors, and its social media accounts, including on X and LinkedIn. The Company uses its website and social media accounts as primary channels for disclosing key information to its investors, some of which may contain material and previously non-public information.

About Hut 8

Hut 8 is an energy infrastructure platform integrating power, digital infrastructure, and compute at scale to fuel next-generation, energy-intensive technologies such as AI, high-performance computing, and ASIC compute. The Company develops, commercializes, and operates industrial-scale energy and data center infrastructure through a power-first, innovation-driven approach. For more information, visit hut8.com.

Cautionary Note Regarding Forward-Looking Information

This press release includes "forward-looking information" and "forward-looking statements" within the meaning of Canadian securities laws and United States securities laws, respectively (collectively, "forward-looking information"). All information, other than statements of historical facts, included in this press release that address activities, events, or developments that Hut 8 expects or anticipates will or may occur in the future, including statements relating to the terms, value, and expected benefits of the Transaction and the Agreement, including expected contract value, NOI contribution, and potential value from renewal options, the timing of development, construction, energization, and delivery of the Beacon Point campus, the Company's plans with respect to project-level financing, the expected capacity, scalability, and potential future expansion of the campus, the Company's development pipeline, and the Company's future business strategy, competitive strengths, expansion, and growth of the business and operations more generally, and other such matters is forward-looking information. Forward-looking information is often identified by the words "may", "would", "could", "should", "will", "intend", "plan", "anticipate", "allow", "believe", "estimate", "expect", "predict", "can", "might", "potential", "is designed to", "likely," or similar expressions.

Statements containing forward-looking information are not historical facts, but instead represent management's expectations, estimates, and projections regarding future events based on certain material factors and assumptions at the time the statement was made. While considered reasonable by Hut 8 as of the date of this press release, such statements are subject to known and unknown risks, uncertainties, assumptions and other factors that may cause the actual results, level of activity, performance, or achievements to be materially different from those expressed or implied by such forward-looking information, including, but not limited to, risks relating to the construction of new data centers, including cost overruns, delays, supply chain issues, permitting or regulatory hurdles, unexpected technical challenges, and dependency on contractors; risks relating to the financing of new data centers, including the potential dilutive impact of equity issuances (if any), access to capital markets, timing and cost of financing, and market conditions such as increases in interest rates, declining equity valuations, volatility in credit markets, or tightening lending standards; risks impacting our ability to expand the power capacity at the River Bend campus, such as limitations of transmission and/or generation resources; failure of critical systems; geopolitical, social, economic, and other events and circumstances; competition from current and future competitors; risks related to power requirements; cybersecurity threats and breaches; hazards and operational risks; changes in leasing arrangements; Internet-related disruptions; dependence on key personnel; having a limited operating history; attracting and retaining customers; entering into new offerings or lines of business; price fluctuations and rapidly changing technologies; predicting facility requirements; strategic alliances or joint ventures; operating and expanding internationally; failing to grow hashrate; purchasing miners; relying on third-party mining pool service providers; uncertainty in the development and acceptance of the Bitcoin network; Bitcoin halving events; competition from other methods of investing in Bitcoin; concentration of Bitcoin holdings; hedging transactions; potential liquidity constraints; legal, regulatory, governmental, and technological uncertainties; physical risks related to climate change; involvement in legal proceedings; trading volatility; and other risks described from time to time in Company's filings with the U.S. Securities and Exchange Commission. In particular, see the Company's recent and upcoming annual and quarterly reports and other continuous disclosure documents, which are available under the Company's EDGAR profile at sec.gov and SEDAR+ profile at sedarplus.ca.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/hut-8-commercializes-first-phase-of-1-gw-beacon-point-ai-data-center-campus-with-15-year-352-mw-it-lease-with-base-term-contract-value-of-9-8-billion-302763484.html

SOURCE Hut 8 Corp.

FAQ

What are the key terms of Hut 8's Beacon Point lease (Nasdaq: J) announced May 6, 2026?

The lease is a 15-year triple-net agreement for 352 MW IT capacity valued at $9.8 billion base-term. According to company, it includes a 3.0% annual rent escalator, three 5-year renewal options, and expected average annual NOI of $655 million upon stabilization.

How does the Beacon Point transaction change Hut 8's contracted AI capacity and contract value?

The transaction raises Hut 8's contracted AI capacity to 597 MW with aggregate base-term contract value of approximately $16.8 billion. According to company, Beacon Point's lease adds 352 MW and brings aggregate NOI contribution to about $1.1 billion annually across contracts.

When will Beacon Point become operational and what timelines did Hut 8 disclose for delivery?

Hut 8 expects initial energization in Q1 2027 with first data hall delivery around Q3 2027. According to company, project-level financing and partner-led execution will support phased delivery and campus scaling to 1,000 MW utility capacity.

What partners and technology architecture are involved in Beacon Point (J) Phase 1?

Phase 1 is engineered to NVIDIA's DSX reference architecture and delivered with partners including Jacobs, Vertiv, and AEP Texas. According to company, these Tier 1 partners support EPCM, critical systems, and the 1,000 MW interconnection agreement for the campus.