i-80 Gold Announces the Start of Production Mining at Archimedes Underground
Sentiment and the balance of points
Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.
Rhea-AI Summary
i-80 Gold (IAUX) started production mining on schedule and mined its first gold at the Archimedes underground project in Nevada. It is the company's second underground mine to come online.
i-80 Gold expects first gold recovery from the Ruby Hill leach pad in Q1 2027 and expects oxide to make up most of the mineralized material mined at Archimedes in 2027. It plans to stockpile refractory material for processing at Lone Tree, where commissioning is planned for Q4 2027.
Once Lone Tree is commissioned, i-80 Gold targets 150,000 to 200,000 ounces of annual gold production from Archimedes and Granite Creek starting in 2028. With additional infrastructure due in 2027, expected project capital is approximately $10 million above the $47.3 million preliminary estimate. The Archimedes feasibility study is planned for the second half of 2027.
How this balance works
Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.
It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.
Rhea-AI Sentiment measures something else, the tone of the wording.
Hollow bars mark forward-looking points. How the balance works
Positive
- Moderate pointArchimedes production mining started on schedule, yielding first mined gold and bringing i-80 Gold's second underground mine online
- Moderate point. Forward-looking: it has not happened yet and may not happen.Annual gold production target of 150,000 to 200,000 ounces from Archimedes and Granite Creek starting in 2028 is not guidance
- Minor point. Forward-looking: it has not happened yet and may not happen.First gold recovery from the Ruby Hill leach pad is expected in the first quarter of 2027
- Minor pointRuby Hill heap leaching has lower overall oxide processing costs than using Lone Tree's oxide mill circuit, based on test work
- Minor point. Forward-looking: it has not happened yet and may not happen.2027 oxide mining is expected to account for most mineralized material mined at Archimedes, versus the preliminary assessment's sulfide majority assumption
7 minor points
- Minor point. Forward-looking: it has not happened yet and may not happen.Heap leach production outlook is expected to increase as the company anticipates mining mostly oxide at Archimedes in 2027
- Minor pointArchimedes mine development is progressing faster than the preliminary assessment outlined, with approximately 3,600 meters of lateral development completed
- Minor pointUpper 426 Zone contractor productivity continues to exceed planned rates
- Minor pointUpper 426 Zone drilling intersected oxide mineralization outside the preliminary assessment's mineral resource estimate
- Minor point. Forward-looking: it has not happened yet and may not happen.Additional mine infrastructure is planned through 2027 to support the ramp-up to planned mining rates
- Minor point. Forward-looking: it has not happened yet and may not happen.Archimedes feasibility study is planned for the second half of 2027
- Minor point. Forward-looking: it has not happened yet and may not happen.Resource definition and extension drilling targets approximately 55,000 meters across 140 holes, with completion expected in the second quarter of 2027
Negative
- Moderate point. Forward-looking: it has not happened yet and may not happen.Expected Archimedes project capital exceeds the $47.3 million preliminary estimate by approximately $10 million 1.1% of market cap
- Moderate point. Forward-looking: it has not happened yet and may not happen.Lone Tree commissioning, planned for Q4 2027, is needed for planned on-site stockpile processing and the 2028 production target
- Minor pointArchimedes extraction began without mineral reserves having been determined
- Minor point. Forward-looking: it has not happened yet and may not happen.Oxide outside the preliminary resource estimate is unclassified, and its contribution to heap leach production depends on mining and leaching results
News Explained
The oxide-heavy mining mix is expected to lift heap-leach production, but the size of that increase has not been quantified.
Production mining has commenced, and the company expects most Archimedes material mined in
The company expects this oxide mix to allow a higher heap-leach production outlook, but gives no quantity or grade for the oxide material that includes material outside the PEA resource estimate; its contribution depends on mining and leaching.
The release says extraction at Archimedes has started without determining mineral reserves.
The company says full guidance will be provided early in the new year.
Key Figures
- Expected project capital increase
- approximately $10 million
- Expected above the $47.3 million PEA estimate after additional infrastructure is completed in 2027
- Consolidated annual gold production target
- 150,000 to 200,000 ounces
- Company target beginning in 2028 from Archimedes and Granite Creek, pending Lone Tree Plant commissioning; not output guidance
- Expected oxide gold recovery
- First quarter of 2027
- Expected recovery of oxide material placed on the Ruby Hill heap leach pad
Historical Context
-
Q3 results widened net loss while Archimedes remained on schedule for year-end production mining.
-
Development update kept Archimedes on track for first gold mined in Q4 2026.
24h Move is the share-price change in the day after each event; other market factors may also have contributed.
Key Terms
preliminary economic assessment technical
heap leaching technical
mineral resource estimate technical
ni 43-101 regulatory
AI-generated analysis. How Rhea-AI works. Not financial advice.
All amounts are expressed in
"The start of production mining at Archimedes marks another significant step for i-80 Gold, further strengthening our track record of delivering on key development milestones," stated Paul Chawrun, Executive Vice President & Chief Operating Officer. "We are currently mining oxide and sulfide material at the Project. The oxide material is being placed on the active heap leach pad on the Ruby Hill property, while the sulfide material is being stockpiled for processing at our Lone Tree Plant next year. Our strong technical and operating teams and our underground mining contractor have enabled us to deliver on this milestone safely, on time and largely on budget."
Mr. Chawrun added, "Our focus for the Project now turns to ramping up mining rates through 2027 and stockpiling the refractory material mined in preparation for the commissioning of the Lone Tree Plant late in the year as Archimedes will be a key source of high-grade refractory material feed. Once the Lone Tree Plant is commissioned, we are targeting consolidated annual gold production of 150,000 to 200,000 ounces beginning in 2028 from the Archimedes and Granite Creek underground projects."(1)
Project Development
Production mining commenced following the scheduled completion of the surface and underground infrastructure required to begin production mining, including ventilation and escape raises. Lateral development to date totals approximately 3,600 meters. Ground conditions remain favorable, and the underground contractor continues to exceed planned productivity rates within the Project's upper 426 Zone. Construction of additional surface and underground infrastructure, such as additional ventilation raises, a permanent mine dry, and offices, will continue through 2027 to support the ramp up to planned mining rates.
Project construction commenced in September 2025 and has progressed largely in line with the capital development estimate in the March 2025 preliminary economic assessment (the "PEA"),(2) apart from the decision to expand and upgrade surface infrastructure to support the scale of future operations. Upon anticipated completion of the additional surface and underground infrastructure in 2027, total project capital is expected to be approximately
Processing and Stockpiling
Archimedes is a high-grade gold project consisting of sulfide (refractory) mineralized material as well as oxide mineralized material predominately in the upper 426 Zone. The recently completed 2025-2026 drilling program for the upper 426 Zone intersected significant intervals of oxide mineralization outside the mineral resource estimate contained in the PEA (refer to the Company's press release dated June 25, 2026). Metallurgical test work results have confirmed that the oxide material is amenable to heap leaching on the Ruby Hill property at lower overall processing costs compared to processing through the Company's oxide mill circuit at the Lone Tree Plant.
Beginning in mid-November, oxide material mined from the upper 426 Zone was placed on the existing heap leach pad on the Ruby Hill property, and the Company expects to begin recovering the associated gold in the first quarter of 2027.
Mining development rates at Archimedes are progressing faster than outlined in the PEA and moreover, the Company expects the majority of the mineralized material mined in 2027 to be oxide and to be placed on the existing heap leach pad. While the PEA assumed some tonnage being placed on the leach pad in 2027, the majority of the mineralized material mined was expected to be sulfide and toll milled at a
As previously disclosed, in 2027 the Company expects to stockpile all refractory material mined at Archimedes, along with a large portion of oxide and refractory material mined at Granite Creek underground. The stockpiled material is intended to be processed at the Company's wholly owned Lone Tree Plant upon its planned commissioning in the fourth quarter of 2027, rather than processed at a third-party facility. Additionally, over the next three years a significant portion of mineralized material mined at the Project is expected to be oxide and placed on the Ruby Hill leach pad.
2027 Planned Feasibility Study
Drilling in the upper 426 Zone was completed in April 2026. Drilling in the lower 426 and Ruby Deeps zones commenced in the second quarter of 2026. Seven underground drill rigs are currently active on site targeting approximately 55,000 meters planned across 140 drill holes. The drilling campaign is expected to be completed in the second quarter of 2027 and is designed to evaluate extensions to the mineralized system and enhance resource definition to support the Archimedes feasibility study, which is planned for completion in the second half of 2027.(2)
As of December 31, 2025, Archimedes hosts an Indicated Mineral Resource of 1.8 million tonnes containing 436,000 ounces of gold grading 7.6 grams per tonne and an Inferred Mineral Resource of 4.2 million tonnes containing 988,000 ounces of gold grading 7.3 grams per tonne.(4) The majority of the current Mineral Resource Estimate is hosted in the Ruby Deeps Zone, located below the 5,100-foot elevation of the deposit as demonstrated in the Figure below.

Technical Disclosure and Qualified Person
The technical information contained in this press release has been prepared under the supervision of, and has been reviewed and approved by Paul Chawrun P.Eng., Executive Vice President & Chief Operating Officer, for the Company, who is a qualified person within the meaning of National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") and Subpart 1300 of Regulation S-K under the United States Securities Act of 1933, as amended ("S-K 1300"). Mr. Chawrun has verified the scientific and technical information disclosed in this press release.
Endnotes
|
(1) |
Based on gold output estimates in the most recent life of mine gold output schedules disclosed in the latest technical studies filed for each respective project and related property: Granite Creek underground, Archimedes underground, Cove underground, and Mineral Point open pit. These anticipated output figures are preliminary in nature and are largely based on mineral resources, which do not have demonstrated economic viability and subject to successful project development. Only Granite Creek underground has declared mineral reserves. In addition, for all gold projects except Granite Creek underground, the foregoing technical reports are preliminary economic assessments/initial assessments that are preliminary in nature. The Granite Creek underground technical report was a feasibility study/technical report summary. Each include an economic analysis that is based, in part, on inferred mineral resources. Inferred mineral resources are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves. As such, there is no certainty that the output targets will be realized. Anticipated output targets are also pending the commissioning of the Lone Tree Plant and are Company goals and not a projection of results and should not be taken as output guidance. All of the Company's projects other than Granite Creek underground are considered exploration stage projects under S-K 1300, as the Company has not determined mineral reserves at such properties pursuant to S-K 1300. With respect to Archimedes underground, located on the Ruby Hill property, the Company has started extraction activities without determining mineral reserves. The following technical reports for each project and related property have been prepared in accordance with NI 43-101: Preliminary Economic Assessment Technical Report for the Cove Project, |
|
(2) |
See the discussion of the Archimedes Underground project in the Company's S-K 1300 Technical Report Summary, Initial Assessment for the Ruby Hill Complex, |
|
(3) |
The oxide mineralized material mined and expected to be mined at Archimedes includes material that, as previously disclosed, is outside the mineral resource estimate supporting the PEA and has not been classified as mineral resources or mineral reserves. The Company is not providing an estimate of the quantity or grade of this material at this time, and its contribution to heap leach production will depend on the results of mining and leaching. |
|
(4) |
Archimedes Underground Mineral Resource Estimate |
|
Deposit |
Tonnes (000) |
Au (g/t) |
Ag (g/t) |
Au oz (000) |
Ag oz (000) |
|
Indicated Mineral Resources |
|||||
|
426 |
899 |
6.9 |
0.8 |
199 |
22 |
|
Ruby Deeps |
892 |
8.3 |
2.4 |
237 |
69 |
|
Total Indicated |
1,791 |
7.6 |
1.6 |
436 |
92 |
|
Inferred Mineral Resources |
|||||
|
426 |
1,038 |
6.6 |
1.2 |
219 |
40 |
|
Ruby Deeps |
3,150 |
7.6 |
2.4 |
769 |
246 |
|
Total Inferred |
4,188 |
7.3 |
2.1 |
988 |
286 |
|
The Mineral Resource estimate is effective December 31, 2024, and was confirmed to remain current as of December 31, 2025. See the Project PEA for the full Mineral Resource statement, estimation assumptions and accompanying notes. |
About i-80 Gold Corp.
i-80 Gold Corp. is a Nevada-focused mining company committed to building a mid-tier gold producer through a funded development plan to advance its high-quality asset portfolio. The Company is one of the largest mineral resource holders in the state with a pipeline of high-grade multi-stage projects strategically located in Nevada's most prolific gold-producing trends. Leveraging its central processing facility following an anticipated refurbishment, i-80 Gold is executing a hub-and-spoke regional mining and processing strategy to maximize efficiency and growth. i-80 Gold's shares are listed on the NYSE (NYSE: IAUX) and the Toronto Stock Exchange (TSX: IAU). For more information, visit www.i80gold.com.
Cautionary Statement Regarding Forward-Looking Information
Certain information set forth in this press release, including but not limited to management's assessment of the Company's future plans and operations, expectations regarding the Project capital costs; commissioning at the Lone Tree Plant in the fourth quarter of 2027; the benefit of transitioning from toll milling to an owner-operator processing model, including reduced processing costs; the potential suitability of oxide material for heap leach processing; the potential upside to the existing mine plan with a lower cost processing option for oxide mineralization at Archimedes; timing of the feasibility study; expected ramp-up of mining rates and construction of additional surface and underground infrastructure through 2027; the expected proportion of oxide material mined and its processing on the Ruby Hill heap leach pad; the timing of 2027 production guidance; stockpiling of refractory material from Archimedes and Granite Creek ahead of Lone Tree Plant commissioning; the scope, timing and results of the Archimedes drilling program and potential resource expansion; the ability to achieve gold production targets such as the 150,000 – 200,000 ounces of annual gold production starting in 2028 constitute forward looking statements or forward-looking information within the meaning of applicable securities laws. All statements other than statements of historical fact are forward-looking statements. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "continues", "forecasts", "projects", "predicts", "intends", "anticipates" or "believes", or variations of, or the negatives of, such words and phrases, or state that certain actions, events or results "may", "could", "would", "should", "might" or "will" be taken, occur or be achieved. Readers are cautioned that the assumptions used in the preparation of information, although considered reasonable at the time of preparation, may prove to be inaccurate and, as such, reliance should not be placed on forward-looking statements. The Company's actual results, performance or achievement could differ materially from those expressed in, or implied by, these forward-looking statements and, accordingly, no assurance can be given that any of the events anticipated by the forward-looking statements will transpire or occur, or if any of them do so, what benefits, if any, that the Company will derive therefrom. By their nature, forward looking statements are subject to numerous risks and uncertainties, some of which are beyond the Company's control, including general economic and industry conditions, volatility of commodity prices, title risks and uncertainties, uncertainty in geological, metallurgical and geotechnical studies and opinions, and ability to access sufficient capital from internal and external sources such as selling assets, restructuring debt or obtaining additional equity capital on terms that may be onerous or highly dilutive. This release also contains references to estimates of mineral resources. The estimation of mineral resources is inherently uncertain and involves subjective judgments about many relevant factors. Mineral resources that are not mineral reserves do not have demonstrated economic viability. The accuracy of any such estimates is a function of the quantity and quality of available data, and of the assumptions made and judgments used in engineering and geological interpretation (including estimated future production from the Project, the anticipated tonnages and grades that will be mined and the estimated level of recovery that will be realized), which may prove to be unreliable and depend, to a certain extent, upon the analysis of drilling results and statistical inferences that may ultimately prove to be inaccurate. Mineral resource estimates may have to be re-estimated based on: (i) fluctuations in commodities prices; (ii) results of drilling, (iii) metallurgical testing and other studies; (iv) proposed mining operations, including dilution; (v) the evaluation of mine plans subsequent to the date of any estimates; and (vi) the possible failure to receive required permits, approvals and licenses or changes to existing mining licenses.
Cautionary Note to U.S. Investors
The Company prepares its disclosure in accordance with the requirements of securities laws in effect in Canada, including NI 43-101. NI 43-101 and the U.S. Securities and Exchange Commission's ("SEC") Regulation S-K 1300 have similar goals but at times embody different approaches and definitions. Accordingly, scientific and technical information contained in this press release, including any references to mineral resources, may not be comparable to similar information disclosed by U.S. companies subject to the SEC's disclosure requirements. Mineral resources that are not mineral reserves do not have demonstrated economic viability, and U.S. investors are cautioned not to assume that all or any part of the mineral resources referenced herein will be converted into mineral reserves.
Please see "Risks Factors" in the Form 10-K for the fiscal year ended December 31, 2025, as updated by the Company's quarterly reports on Form 10-Q and current reports on Form 8-K, for more information regarding risks pertaining to the Company, which is available on EDGAR at www.sec.gov/edgar and SEDAR+ at www.sedarplus.ca. Readers are encouraged to carefully review these risk factors as well as the Company's other filings with the SEC and the Canadian Securities Administrators. All forward-looking statements contained in this press release speak only as of the date of this press release or as of the dates specified in such statements. The Company disclaims any intention or obligation to update or revise any forward-looking statements, whether as a result of new information, future events or otherwise except as required by applicable law. Additional information relating to i-80 Gold can be found on i-80 Gold's website at www.i80gold.com, SEDAR+ at www.sedarplus.ca, and on EDGAR at www.sec.gov/edgar. The information included on, or accessible through, the Company's website is not incorporated by reference into this press release.
View original content to download multimedia:https://www.prnewswire.com/news-releases/i-80-gold-announces-the-start-of-production-mining-at-archimedes-underground-302948727.html
SOURCE i-80 Gold Corp