JAGUAR URANIUM ANNOUNCES MAIDEN MINERAL RESOURCE ESTIMATE AT THE BERLIN POLYMETALLIC PROJECT IN COLOMBIA
Sentiment and the balance of points
Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.
Rhea-AI Summary
Jaguar Uranium (JAGU) announced its first mineral resource estimate for the wholly owned Berlin Uranium-Polymetallic Project in Caldas, Colombia. The independent estimate, effective November 5, 2026, covers the initial 2.9 km of the 10.5 km mineralized trend. It reports 1.2 million lb of indicated U₃O₈ in 937,000 tonnes grading 561 ppm and 14.1 million lb of inferred U₃O₈ in 11.343 million tonnes grading 562 ppm.
The underground estimate uses a US$245/t net smelter return cut-off, a value threshold that accounts for assumed recoveries and off-site charges. It includes rare earths, vanadium, phosphate, nickel, zinc and molybdenum but excludes a near-surface layer extending to approximately 25 m depth. Jaguar is planning work to expand the resource and upgrade inferred material to indicated. The company has nearly US$18 million in cash and no debt.
How this balance works
Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.
It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.
Rhea-AI Sentiment measures something else, the tone of the wording.
Hollow bars mark forward-looking points. How the balance works
Positive
- Major pointInferred uranium resource totals 14.1 Mlb U₃O₈ in 11,343 kt grading 562 ppm.
- Major pointBalance sheet has nearly US$18 million in cash and no debt.
- Minor pointIndicated uranium resource totals 1.2 Mlb U₃O₈ in 937 kt grading 561 ppm.
- Minor pointCo-product credits bring some blocks grading 400–600 ppm U₃O₈ above the US$245/t cut-off.
- Minor pointNorthern extension remains open for an additional 7.6 km along the Berlin trend.
2 minor points
- Minor point. Forward-looking: it has not happened yet and may not happen.Infill drilling is a potential step in Jaguar’s planned program to upgrade inferred material to indicated.
- Minor point. Forward-looking: it has not happened yet and may not happen.Additional sampling is a potential step to refine processing methods and assess rock conditions.
Negative
- Minor point. Forward-looking: it has not happened yet and may not happen.Near-surface mineralization down to approximately 25 m was excluded; potential extraction would require open-pit methods.
- Minor pointSampling gaps remain in the current resource model.
- Minor pointHistorical assay records have documentation limitations, and individual test results showed variability.
News Explained
The Berlin estimate is a mineral resource, not a reserve: Jaguar says no reserves were estimated, and the resource does not demonstrate economic viability.
Key Figures
- Indicated contained U₃O₈
- 1.2 Mlb
- 937 kt at 561 ppm U₃O₈
- Inferred contained U₃O₈
- 14.1 Mlb
- 11,343 kt at 562 ppm U₃O₈
- NSR cut-off
- US$245/t
- Mineral Resource Estimate reporting threshold
- Long-term uranium price assumption
- US$105/lb U₃O₈
- Used in the Mineral Resource Estimate
Historical Context
-
Laguna Salada maiden estimate reported 4.2 million indicated and 10.1 million inferred uranium oxide pounds.
24h Move is the share-price change in the day after each event; other market factors may also have contributed.
Key Terms
net smelter return financial
indicated mineral resources technical
inferred mineral resources technical
ni 43-101 regulatory
AI-generated analysis. How Rhea-AI works. Not financial advice.
- Multi-commodity mineral resource:
- 1.2 Mlb Indicated at 561 ppm U₃O₈ and 14.1 Mlb Inferred at 562 ppm U₃O₈.
- Additional critical mineral and strategic metal co-products, including rare earth oxides (neodymium, dysprosium, terbium and yttrium), vanadium, nickel, zinc, molybdenum and phosphate, contribute substantially to the overall contained metal value of the polymetallic deposit.
- District-Scale, Stratabound Carbonate-Hosted Uranium-Polymetallic Mineral Resource encompassing the initial 2.9 km of the 10.5 km trend.
- Significant Expansion & Infill Potential: The mineralized horizon remains open along strike to the North along the 10.5 km
Berlin trend. - Strategic Western Supply of Critical Minerals: Potential to provide Western Hemisphere markets with a supply of uranium, critical and strategic metals.
- Well-Financed, Cash-Rich Balance Sheet: Company maintains nearly
US in cash and no debt$18 million - NSR Cut-Off Approach: Mineral Resources are reported above a Net Smelter Return (NSR) cut-off value of
US /t incorporating metallurgical recovery assumptions and off-site freight, smelting, and refining charges.$245
Mineral Resources are reported above a Net Smelter Return (NSR) cut-off of
"This MRE marks a significant milestone for Jaguar Uranium and supports our view of
Mineral Resource Statement
- SLR has prepared a MRE in accordance with Regulation S-K 1300 and CIM Definition Standards (2014). Constrained within conceptual underground stope optimization to demonstrate Reasonable Prospects for Eventual Economic Extraction (RPEE), the MRE is reported above a
US /t Net Smelter Return (NSR) cut-off.Classification Split: Mineral Resources are categorized into Indicated Mineral Resources of 937 kt grading 561 ppm U3O8 (1.2 Mlb contained U3O8) and Inferred Mineral Resources of 11,343 kt grading 562 ppm U3O8 (14.1 Mlb contained U3O8), applying a bulk density of 2.72 t/m3, a long-term uranium price of$245 US /lb U3O8, and$105 96.1% metallurgical recovery for uranium1 (Table 1). - Polymetallic NSR Credit Capture: Blocks with moderate U3O8 grades (400–600 ppm) that carry high concentrations of V2O5, P2O5, rare earths (Y2O3, Nd, Dy, Tb), Ni, Zn, and Mo exceed the
US /t NSR threshold and are captured in the resource inventory (Figure 1).$245
Note on Near-Surface Mineralization: The upper portion of the deposit, extending from surface to an approximate depth of 25 m and designated as the lateritized mineralized layer, was excluded from the current underground MRE, as its potential extraction would require open-pit mining methods and distinct technical and economic parameters. However, the surface expression of mineralization along both flanks represents a significant operational advantage that could facilitate future mine access and development.
|
_______________________________ |
|
1 Inferred Mineral Resources have a lower level of confidence than Indicated Mineral Resources and cannot be converted directly into Mineral Reserves. |
Table 1: Mineral Resource Statement for the Berlin Polymetallic Deposit (SLR, Effective November 5, 2026).
|
Classification |
NSR Cut-off Value |
Tonnage |
U3O8 Grade |
Contained Metal |
V2O5 |
P2O5 |
Y2O3 |
Dy |
Nd |
Tb |
Mo |
Ni |
Zn |
Jaguar Basis |
Recovery U3O8 |
|
($) |
(kt) |
(ppm) |
(Mlb U3O8) |
(ppm) |
(ppm) |
(ppm) |
(ppm) |
(ppm) |
(ppm) |
(ppm) |
(ppm) |
(ppm) |
( %) |
(%) |
|
|
Indicated |
245 |
937 |
561 |
1.2 |
3,170 |
50,474 |
262 |
18 |
73 |
3 |
303 |
1,094 |
1,830 |
100 |
96.1 |
|
Inferred |
11,343 |
562 |
14.1 |
3,081 |
53,405 |
309 |
19 |
79 |
3 |
319 |
1,368 |
1,916 |
Notes to Table 1 - Mineral Resource Statement:
|
1. |
SEC S-K 1300 and CIM Definition Standards (2014) were followed for all Mineral Resource categories. |
|
2. |
Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. No Mineral Reserves have been estimated. |
|
3. |
Reference metal prices used in the NSR formulation: |
|
4. |
A minimum mining width of 2 meters was used in determining Mineral Resources. |
|
5. |
Mineral Resources are based on a density factor of 2.72 t/m3. |
|
6. |
The MRE is supported by a Reasonable Prospects for Eventual Economic Extraction assessment incorporating underground stope optimization and an underground mining scenario consistent with longhole stoping. |
|
7. |
The NSR cut-off of |
|
8. |
Metallurgical Recoveries applied in the NSR calculation: |
|
9. |
The NSR cut-off value and conceptual underground mining shapes are intended solely to support the assessment of RPEE and do not demonstrate economic viability. |
|
10. |
NSR = ([NSR_Y2O3] + [NSR_Nd2O3] + [NSR_Tb2O3] + [NSR_Dy2O3] + [NSR_U3O8] + [NSR_ZnCO3] + [NSR_NiCO3] + [NSR_V2O5] + [NSR_P2O5]) - [SHARED_COSTS_USD_T] |
|
11. |
Mineral Resources are |
|
12. |
Totals may not add due to rounding. |
|
13. |
The Qualified Persons are not aware of any known environmental, permitting, legal, title, taxation, socio-economic, marketing, political or other relevant factors that could materially affect the MRE. |

Location, Geology and Mineralization
The Berlin Project is located in the Caldas Department, within the Central Cordillera of


Four successions were recognized in the study area (Figure 4):
Succession A: Basal conglomerates interbedded with sandstones.
Succession B: Fossiliferous calcareous mudstones containing well-preserved bivalves and gastropods, featuring a very fine-grained texture that acted as an impermeable barrier restricting fluid mobilization.
Succession C: Packstone containing reworked fossil fragments, displaying wavy lamination and high concentrations of authigenic apatite and uraninite, among other minerals of interest. This succession constitutes the mineralized horizon, which varies in thickness from 1 to 8 m in the southern sector where the MRE is delineated.
Succession D: An upper sequence of deformed black carbonaceous shales with bioclasts, locally reaching up to 600 m in thickness, interpreted as the potential source of the mineralizing fluids.

The geological continuity of the mineralized horizon is demonstrated over several kilometers along strike, occurring as a continuous, shallowly-to-steeply dipping sedimentary layer folded into the Syncline structure (Figure 3).
Upcoming Work Program: Extension Target & Infill Drilling
Jaguar is currently planning a focused work program aimed at expanding the resource base and upgrading Inferred material to Indicated classification, including potential steps such as:
- Northern Trend Extension: Exploration drilling, trenching and surface mapping indicate that the mineralized succession remains open along strike to the North for an additional 7.6 km along the 10.5 km Berlin Trend (Figure 3).
- Infill Drilling Program: A targeted infill diamond core drilling campaign to address spatial sampling gaps identified within the current block model, improving grade continuity confidence and upgrading Inferred volumes (Figure 1D).
- Geotechnical & Metallurgical Optimization: Step-out sampling for flotation, leach optimization, and geotechnical domain refinement.
Qualified Persons & Technical Reports
The MRE was prepared under the direction of Mark Mathisen, C.P.G., Senior Principal Geologist and Yenlai Chee, C.P.G. Consulting Geologist,independent Qualified Persons from SLR International Corporation, in accordance with Regulation S-K 1300 and NI 43-101. The Qualified Persons have reviewed the historical sampling, analytical, and QA/QC data underlying the Mineral Resource estimate (MRE), together with the results of Jaguar's 2026 verification program involving the independent re-analysis of 150 archived drill core and pulp samples by SGS del Perú S.A.C., and consider the data sufficiently reliable and adequate to support the current MRE, notwithstanding limitations in historical analytical documentation and observed variability in individual assay results
Additional scientific and technical content in this news release has been reviewed and approved by Andrés
A technical report prepared in accordance with NI 43-101 supporting the MRE will be filed on SEDAR+ within 45 days of this news release, and a Technical Report Summary (TRS) prepared in accordance with Regulation S-K 1300 supporting the MRE will be filed with the SEC as an exhibit to the Company's applicable SEC filing.
About Jaguar Uranium Corp.
Jaguar Uranium Corp. is a South America-focused uranium exploration company advancing a portfolio of prospective brownfield projects across Argentina and Colombia. In Argentina, Jaguar is advancing the Laguna Salada Project in Chubut Province and the historic Huemul uranium mine in Mendoza Province. Anchored by a former producing mine, a historic uranium district and exploration projects supported by historical drilling, the Company is focused on advancing and expanding uranium opportunities across the region. The Company's Berlin Project in Caldas Department, Colombia is a district-scale, sedimentary-hosted polymetallic system with a current MRE for uranium alongside rare earth elements, vanadium, nickel, phosphate, molybdenum and zinc. Jaguar completed a
Forward-Looking Statements
This news release contains "forward-looking statements" and/or "forward-looking information" (collectively, "forward-looking statements") within the meaning of applicable securities legislation. All statements, other than statements of historical fact, are forward-looking statements. Generally, forward-looking statements can be identified by the use of forward-looking terminology such as "plans", "expect", "is expected", "in order to", "is focused on" (a future event), "estimates", "intends", "anticipates", "believes" or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", or the negative connotation thereof. In particular, statements regarding the Company's future operations, future exploration and development activities or other development plans constitute forward-looking statements. By their nature, statements referring to mineral reserves or mineral resources constitute forward-looking statements. Forward-looking statements in this news release include, but are not limited to, statements with respect to Berlin's exploration and development potential, including any expansion or upgrade of mineral resources, the completion and timing for the filing of technical reports supporting the MRE, the Company's ability to ramp up exploration activity at the Berlin Project, the Company's ability to utilize its cash and the anticipated effects thereof, the Company's ability to advance its uranium and polymetallic opportunities, the planned work program at the Berlin Project, including exploration and infill drilling along the Berlin trend and metallurgical and geotechnical studies, the potential of the Berlin Project to supply uranium and critical and strategic metals, the potential for future mine access and development, and any other information herein that is not a historical fact. The Company considers its assumptions to be reasonable based on information currently available but cautions the reader that these assumptions regarding future events, many of which are beyond the control of the Company, may ultimately prove to be incorrect since they are subject to risks and uncertainties that affect the Company, its properties, and business. Material assumptions include, without limitation, that the assumptions underlying the MRE, including commodity prices, metallurgical recoveries and operating costs, are reasonable; that required permits, surface access and financing will be obtained on acceptable terms; and that planned work will be completed as expected. Risks and uncertainties include, but are not limited to, changes in demand for and price of uranium, vanadium, phosphates, rare earth elements, molybdenum, nickel, zinc, and other commodities and currencies; changes or disruptions in the securities markets; legislative, political, or economic developments in Colombia; changes in any of the assumptions underlying the MRE; the uncertainty inherent in Mineral Resource estimates, including the risk that Inferred Mineral Resources may not be upgraded to Indicated Mineral Resources; the need to obtain permits and comply with laws and regulations and other regulatory requirements; risks relating to title, community relations and security in Colombia; risks associated with the handling of radioactive materials; the risk that assumed metallurgical recoveries may not be achieved; the availability of financing; the possibility that actual results of work may differ from projections/expectations or may not realize the perceived potential of the Company's projects; risks of accidents, equipment breakdowns, and labor disputes or other unanticipated difficulties or interruptions; the possibility of cost overruns or unanticipated expenses in development programs; operating or technical difficulties in connection with exploration, mining, or development activities; the speculative nature of exploration and development, including the risks of diminishing quantities or grades of reserves and resources; and the risks involved in the exploration, development, and mining business and the additional risks discussed and identified in public filings made by the Company with the Securities and Exchange Commission and available on SEDAR+ at www.sedarplus.ca. The Company disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events, or otherwise, except as required by applicable securities laws.
View original content to download multimedia:https://www.prnewswire.com/news-releases/jaguar-uranium-announces-maiden-mineral-resource-estimate-at-the-berlin-polymetallic-project-in-colombia-302950016.html
SOURCE Jaguar Uranium
FAQ
AI-generated questions and answers. How Rhea-AI works. Not financial advice.