Lithium Americas Reports First Quarter 2025 Results
(All amounts in US$ unless otherwise indicated)
Jonathan Evans, President and Chief Executive Officer of Lithium Americas said, “Major construction has commenced at Thacker Pass and the first significant construction milestone was achieved the first week of May 2025 with the initial placement of permanent concrete in the processing plant area. The site has undergone transformational change over the past year and there is excitement amongst our stakeholders and partners as we build one of
OPERATING AND FINANCIAL HIGHLIGHTS
-
As of March 31, 2025, the Company had approximately
in cash and restricted cash.$446.9 million -
During the quarter ended March 31, 2025,
of construction capital costs and other project-related costs were capitalized.$78.2 million -
Subsequent to Q1 2025 on April 1, 2025, the Company closed the previously announced strategic investment of
from fund entities managed by Orion Resource Partners LP (collectively, “Orion”), for the development and construction of Phase 1 of Thacker Pass (“Orion Investment”). With the Orion Investment, Lithium Americas has achieved fully funded status for the development of Phase 1 of Thacker Pass at the project and corporate level for the duration of construction.$250 million -
Contemporaneously with closing the Orion Investment on April 1, 2025, the Company and General Motors Holdings LLC (“GM”) announced the final investment decision (“FID”) for construction of Phase 1 of Thacker Pass. On declaring FID, GM and Lithium Americas contributed
and$100 million in cash to the joint venture between GM and the Company (the “JV”), respectively.$191.6 million -
The Company currently expects to make the first draw on the previously announced
loan from the$2.26 billion U.S. Department of Energy (the “DOE Loan”) sometime in the third quarter of 2025 (“Q3 2025”).
PROJECT AND CONSTRUCTION UPDATE
- Completion of Phase 1 of Thacker Pass is targeted for late 2027. Project engineering and procurement continue in line with the project schedule to support construction.
-
Major construction has begun at Thacker Pass, with earthworks almost complete and permanent concrete placement in the processing plant area commenced in early May 2025.
-
As of March 31, 2025, detailed engineering was over
60% design complete and expected to increase to over90% design complete by year end 2025. The higher level of detailed engineering at the early stages of construction helps de-risks execution in terms of project schedule and cost. - In April 2025, fabrication of the structural steel to be used to build the facilities at Thacker Pass commenced. First steel installation is targeted to commence in September 2025.
- Manufacturing of all long-lead equipment awarded continues to advance with expected delivery in line with the project schedule.
-
As of March 31, 2025, detailed engineering was over
-
During Q1 2025, the first modular housing units were installed at the workforce hub, the Company’s all-inclusive housing facility for construction workers in
Winnemucca (the “Workforce Hub”). First occupancy of the Workforce Hub is targeted for the second half of 2025. - The Company recently submitted a Plan of Operations to the Bureau of Land Management to build a limestone quarry named Western Quarry, approximately one hour drive from Thacker Pass via national and state highways. Western Quarry is being planned as a source of local, lower cost limestone, a reagent used in the Thacker Pass processing flowsheet to produce battery-quality lithium carbonate.
Mr. Evans added, “The Company continues to review its potential exposure to the fluid tariff announcements. Our teams are working toward limiting the effect of any potential tariff or trade disputes on our construction supply chain. Approximately
TECHNICAL INFORMATION
The scientific and technical information in this news release has been reviewed and approved by Rene LeBlanc, PhD, SME, Vice President, Growth and Product Strategy of the Company, and a “qualified person” as defined under National Instrument 43-101 and Subpart 1300 of Regulation S-K under the United States Securities Act of 1933, as amended.
FINANCIALS
Selected consolidated financial information is presented as follows:
(in US$ million except per share information) |
|
Three months ended March 31, |
|
|||||
|
|
2025 |
|
|
2024 |
|
||
|
|
$ |
|
|
$ |
|
||
Operating expenses |
|
|
6.5 |
|
|
|
5.8 |
|
Net loss |
|
|
11.5 |
|
|
|
6.3 |
|
Loss per share - basic |
|
|
0.05 |
|
|
|
0.04 |
|
(in US$ millions) |
|
As at March 31, 2025 |
|
|
As at December 31, 2024 |
|
||
|
|
$ |
|
|
$ |
|
||
Cash and restricted cash |
|
|
446.9 |
|
|
|
594.2 |
|
Total assets |
|
|
1,018.5 |
|
|
|
1,044.9 |
|
Total long-term liabilities |
|
|
40.1 |
|
|
|
41.3 |
|
During Q1 2025, net loss increased due to higher general and administrative expenses reflecting continuing transition to domestic filer status, increased reporting obligations under the DOE Loan and higher transaction costs reflecting increased financing activities that concluded with the Orion Investment.
During Q1 2025, total assets decreased reflecting the use of cash for payment of transaction costs and other payables accrued at December 31, 2024.
This news release should be read in conjunction with the Company’s Quarterly Report on Form 10-Q for the three months ended March 31, 2025, available on the Company’s issuer profile on EDGAR at www.sec.gov, SEDAR+ at www.sedarplus.ca and on the Company's website at www.lithiumamericas.com.
ABOUT LITHIUM AMERICAS
Lithium Americas is committed to responsibly developing the Thacker Pass project located in
FORWARD-LOOKING STATEMENTS
This news release contains “forward-looking information” within the meaning of applicable Canadian securities legislation, and “forward-looking statements” within the meaning of the United States Private Securities Litigation Reform Act of 1995 (collectively referred to as “forward-looking statements” or “FLS”). All statements, other than statements of historical fact, are FLS and can be identified by the use of statements that include, but are not limited to, words, such as “anticipate,” “plan,” “continue,” “estimate,” “expect,” “may,” “will,” “project,” “predict,” “propose,” “potential,” “target,” “implement,” “schedule,” “forecast,” “intend,” “would,” “could,” “might,” “should,” “believe” and similar terminology, or statements that certain actions, events or results “may,” “could,” “would,” “might” or “will” be taken, occur or be achieved. FLS in this news release includes, but is not limited to: statements relating to the anticipated sources and uses of funds to complete project financing, statements relating to the JV, the DOE Loan and the Orion Investment, including statements regarding satisfaction of draw-down conditions on the DOE Loan and expected timing for first draw-down on the DOE Loan; expectations and timing on the commencement of major construction and first production; project de-risking initiatives and the extent to which work to date has de-risked project execution; the expected operations, financial results and condition of the Company; the Company’s future objectives and strategies to achieve those objectives, including the future prospects of the Company; the estimated cash flow, capitalization and adequacy thereof for the Company; the estimated costs of the development of Thacker Pass, including timing, progress, approach, continuity or change in plans, construction, commissioning, milestones, anticipated production and results thereof and expansion plans; cost and expected benefits of the transloading terminal; anticipated timing to resolve, and the expected outcome of, any complaints or claims made or that could be made concerning the permitting process in
FLS involves known and unknown risks, assumptions and other factors that may cause actual results or performance to differ materially. FLS reflects the Company’s current views about future events, and while considered reasonable by the Company as of the date of this news release, are inherently subject to significant uncertainties and contingencies. Accordingly, there can be no certainty that they will accurately reflect actual results. Assumptions and other factors upon which such FLS is based include, without limitation: expectations regarding Phase 2 of Thacker Pass, including financing; the ability of Lithium Nevada LLC (“LN”) to draw-down on the DOE Loan on the anticipated timeline, or at all, and the absence of material adverse events affecting the Company during the construction of the Project; the ability of LN to satisfy all draw-down conditions for the DOE Loan in a timely manner; the ability of the Company to perform conditions and meet expectations regarding the Company’s financial resources and future prospects; the ability to meet future objectives and priorities; a cordial business relationship between the Company and third party strategic and contractual partners; unforeseen technological and engineering problems; changes in general economic and geopolitical conditions, including as a result of regulatory changes by the current presidential administration and potential changes in
Readers are cautioned that the foregoing lists of factors are not exhaustive. There can be no assurance that FLS will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. As such, readers are cautioned not to place undue reliance on this information, and that this information may not be appropriate for any other purpose, including investment purposes. The Company’s actual results could differ materially from those anticipated in any FLS as a result of the risk factors set out herein, and in the Company’s other continuous disclosure documents available on SEDAR+ at www.sedarplus.ca and EDGAR at www.sec.gov. Readers are further cautioned to review the full description of risks, uncertainties and management’s assumptions in the aforementioned documents and other disclosure documents available on SEDAR+ and on EDGAR.
The Company expressly disclaims any obligation to update FLS as a result of new information, future events or otherwise, except as and to the extent required by applicable securities laws. Forward-looking financial information also constitutes FLS within the context of applicable securities laws and as such, is subject to the same risks, uncertainties and assumptions as are set out in the cautionary note above.
View source version on businesswire.com: https://www.businesswire.com/news/home/20250515497396/en/
INVESTOR CONTACT
Virginia Morgan, VP, IR and ESG
+1-778-726-4070
ir@lithiumamericas.com
Source: Lithium Americas Corp.