STOCK TITAN

Orion Spacecraft Completes Major Stacking Milestone Ahead of Artemis II Mission

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags

Lockheed Martin (NYSE: LMT) reported that the Orion spacecraft named Integrity was stacked atop the Space Launch System (SLS) rocket in High Bay 3 at Kennedy Space Center on Oct. 19, 2025, marking a major prelaunch milestone for Artemis II. Teams will complete electrical, data and umbilical hookups and EGS will run integrated tests before the stack rolls to Launch Pad 39B for a wet dress rehearsal next year. The first crewed Artemis flight is scheduled no earlier than February 2026, with launch windows extending through April 2026, and a planned mission duration of 10 days. Lockheed Martin is the prime contractor and built Orion's crew module, adapter and launch abort system.

Lockheed Martin (NYSE: LMT) ha riportato che la navicella spaziale Orion chiamata Integrity è stata impilata sopra il razzo Space Launch System (SLS) nel High Bay 3 al Kennedy Space Center il 19 ottobre 2025, segnando un importante traguardo pre-lancio per Artemis II. I team completeranno i collegamenti elettrici, di dati e di umbiliqui e l'EGS eseguirà test integrati prima che la pila venga spostata su Launch Pad 39B per una simulazione di lancio bagnata l'anno prossimo. La prima missione umana Artemis è prevista non prima di febbraio 2026, con finestre di lancio estese fino ad aprile 2026, e una durata della missione pianificata di 10 giorni. Lockheed Martin è l'appaltatore principale e ha costruito il modulo di equipaggio di Orion, l'adattatore e il sistema di abort di lancio.

Lockheed Martin (NYSE: LMT) informó que la nave espacial Orion llamada Integrity fue apilada sobre el cohete Space Launch System (SLS) en el High Bay 3 en el Kennedy Space Center el 19 de octubre de 2025, marcando un hito importante previo al lanzamiento para Artemis II. Los equipos completarán las conexiones eléctricas, de datos y umbilicales y EGS realizará pruebas integradas antes de que la pila se desplace a Launch Pad 39B para un ensayo húmedo (wet dress rehearsal) el próximo año. La primera misión tripulada de Artemis está programada no antes de febrero de 2026, con ventanas de lanzamiento que se extienden hasta abril de 2026, y una duración de la misión prevista de 10 días. Lockheed Martin es el contratista principal y construyó el módulo de tripulación de Orion, el adaptador y el sistema de aborto de lanzamiento.

Lockheed Martin (NYSE: LMT)는 Orion 우주선이 Integrity로 명명되었으며 Kennedy Space Center의 High Bay 3에서 Space Launch System(SLS) 로켓 위에 적재되었다고 발표했다. 이는 Artemis II의 주요 사전 발사 이정표를 나타낸다. 팀은 전력, 데이터 및 엄빌리컬 연결을 완료하고 EGS가 통합 테스트를 수행한 후 내년 Launch Pad 39B로 구성체를 옮겨 젖은 시연(wet dress rehearsal)을 진행한다. 첫 유인 Artemis 비행은 2026년 2월 이후로 예정되어 있으며, 발사 창은 2026년 4월까지 확장되며, 임무 기간은 10일로 계획되어 있다. Lockheed Martin은 주요 계약자로 Orion의 승무 모듈, 어댑터 및 발사 중단 시스템을 구축했다.

Lockheed Martin (NYSE: LMT) a annoncé que la navette Orion nommée Integrity a été empilée au sommet du Space Launch System (SLS) dans le High Bay 3 au Kennedy Space Center le 19 octobre 2025, marquant une étape préliminaire majeure pour Artemis II. Les équipes réaliseront les raccordements électriques, de données et umbiliques et l'EGS effectuera des tests intégrés avant que la pile ne soit déplacée vers le Launch Pad 39B pour une répétition de lancement humide l'année prochaine. Le premier vol habité d'Artemis est prévu pas avant février 2026, avec des fenêtres de lancement s'étendant jusqu'en avril 2026, et une durée de mission prévue de 10 jours. Lockheed Martin est l'entrepreneur principal et a construit le module d'équipage d'Orion, l'adaptateur et le système d'abort de lancement.

Lockheed Martin (NYSE: LMT) gab bekannt, dass das Orion-Raumfahrzeug mit dem Namen Integrity am 19. Oktober 2025 auf dem Space Launch System (SLS)-Raketenstapel im High Bay 3 am Kennedy Space Center gestapelt wurde, was einen wichtigen Vorstart-Meilenstein für Artemis II markiert. Teams werden elektrische, Daten- und Umbilical-Verbindungen abschließen und das EGS integrierte Tests durchführen, bevor der Stack auf die Launch Pad 39B für eine Wet Dress Rehearsal im nächsten Jahr rollt. Die erste bemannte Artemis-Mission ist nicht früher als Februar 2026 geplant, mit Launch-Fenstern, die sich bis April 2026 erstrecken, und einer geplanten Missionsdauer von 10 Tagen. Lockheed Martin ist der Hauptauftragnehmer und hat Orion's Crew-Modul, Adapter und Launch-Abort-System gebaut.

لوكهيد مارتن (NYSE: LMT) ذكرت أن مركبة أوريون الفضائية التي تحمل اسم Integrity تم تكديسها فوق صاروخ نظام الإطلاق الفضائي (SLS) في High Bay 3 بمركز كينيدي للفضاء في 19 أكتوبر 2025، مما يمثل علامة بارزة قبل الإطلاق لـ Artemis II. ستُكمل الفرق التوصيلات الكهربائية والبيانات والوصائل Umbilical، وستجري EGS اختبارات متكاملة قبل أن يتم نقل الحزمة إلى Launch Pad 39B لإجراء بروفة الإطلاق الرطب في العام القادم. من المقرر أن تتم الرحلة Artemis المأهولة الأولى ليس قبل فبراير 2026، مع نوافذ إطلاق تمتد حتى أبريل 2026، وبمدة مهمة مخطط لها 10 أيام. تعتبر Lockheed Martin المتعهد الرئيسي وبنت وحدةCrew لـ Orion، والمهايئ ونظام الإجهاض للإطلاق.

洛克希德马丁(NYSE: LMT) 报告称名为 Integrity 的 Orion 舱段已在肯尼迪航天中心的 High Bay 3 将 Space Launch System (SLS) 火箭叠放在一起,时间为 2025年10月19日,这是 Artemis II 的一次重要的发射前里程碑。团队将完成电气、数据和臍带连接,EGS 将进行综合测试,然后该组装体将移动到 Launch Pad 39B 进行明年湿练习(wet dress rehearsal)。首个载人阿耳忒弥斯任务预计最早 2026年2月 发射,发射窗口将延长至 2026 年 4 月,计划任务持续约 10 天。洛克希德马丁是总承包商,负责建造 Orion 的飞船舱模、适配器和发射中止系统。

Positive
  • Orion stacked onto SLS in High Bay 3 on Oct. 19, 2025
  • Artemis II crewed mission scheduled no earlier than Feb 2026 with defined windows
  • Mission length set at 10 days, advancing program milestones
  • Lockheed Martin serves as prime contractor and delivered key spacecraft hardware
Negative
  • Launch date remains tentative (NEoT Feb–Apr 2026), keeping schedule uncertainty
  • Integrated tests and wet dress rehearsal prior to rollout could introduce delays

Insights

Orion and SLS stacking completes a key hardware integration milestone ahead of the crewed Artemis II launch window.

The physical mating of the Orion spacecraft named Integrity to the SLS rocket on Oct. 19, 2025 moves the program from vertical assembly into integrated systems tests. Teams will now complete electrical, data and umbilical hookups and run joint integrated tests before rollout to Launch Pad 39B and a wet dress rehearsal in the lead-up to the planned crewed launch window starting February 2026 and extending through April 2026.

Dependencies and risks remain concrete and procedural: completion of the described electrical/data connections, successful integrated tests, and a successful wet dress rehearsal are all required prior to launch. Watch the outcomes and timings of the integrated test campaign and the wet dress rehearsal over the next few months; those discrete milestones will directly determine whether the program meets the early 2026 launch window.

Orion Integrity spacecraft connected with the SLS rocket, readying for historic crewed journey to the Moon

KENNEDY SPACE CENTER, Fla., Oct. 24, 2025 /PRNewswire/ -- In a move signifying mission readiness, NASA's Exploration Ground Systems (EGS) team recently joined and connected the Lockheed Martin (NYSE: LMT)-developed Orion spacecraft with the Space Launch System (SLS) rocket for the upcoming Artemis II mission. 

The Orion spacecraft, named Integrity by its astronaut crew, was transported to the Vehicle Assembly Building at the Kennedy Space Center where it was lifted atop the SLS rocket in High Bay 3 on Oct. 19. This marks a major milestone for the Artemis II mission as NASA and industry work toward a historic launch to the Moon with four astronauts early next year.

"Integration of SLS and Orion represents a major milestone in our progress on Artemis," said Acting NASA Administrator Sean Duffy. "Soon, we will be launching four astronauts around the Moon for the first time in over half a century on Artemis II — the latest demonstration of American dominance in space."

Following the mating, teams will make electrical and data connections between Orion and SLS, along with umbilical connections from the mobile launch platform to the spacecraft. EGS will conduct integrated tests of Orion and SLS before they are rolled out to Launch Pad 39B for a wet dress rehearsal next year.

"The full stack of Orion on the SLS is a truly spectacular sight," said Robert Lightfoot, president of Lockheed Martin Space. "Our teams have been working tirelessly to finalize these last steps and ensure Orion takes the crew to the Moon and brings them home safely."

The first crewed flight of the Artemis program is set to launch no earlier than February 2026, with potential launch windows extending through April 2026. The mission will be 10 days and is a key event to establishing a long-term presence at the Moon for exploration and science.

Orion is the most advanced, human-rated, deep space spacecraft ever developed. Lockheed Martin is the prime contractor to NASA for Orion and built the crew module, crew module adaptor and launch abort system.

About Lockheed Martin
Lockheed Martin is a global defense technology company driving innovation and advancing scientific discovery. Our all-domain mission solutions and 21st Century Security® vision accelerate the delivery of transformative technologies to ensure those we serve always stay ahead of ready. More information at Lockheedmartin.com

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/orion-spacecraft-completes-major-stacking-milestone-ahead-of-artemis-ii-mission-302594149.html

SOURCE Lockheed Martin

FAQ

What did Lockheed Martin (LMT) announce about Orion on Oct. 24, 2025?

Orion Integrity was stacked on the SLS rocket on Oct. 19, 2025, advancing Artemis II prelaunch work.

How does the Oct. 19, 2025 stacking affect Lockheed Martin (LMT) and Artemis II timing?

Stacking enables upcoming electrical and data hookups and integrated tests before a wet dress rehearsal ahead of a no earlier than Feb 2026 launch window.

When is the Artemis II crewed mission now planned to launch and how long will it last?

The mission is planned no earlier than February 2026 with windows through April 2026 and a 10-day duration.

What hardware did Lockheed Martin (LMT) provide for Orion for Artemis II?

Lockheed Martin built the crew module, crew module adapter and the launch abort system used on Orion.

What tests remain after Orion was stacked on SLS for Artemis II?

Teams will complete electrical, data and umbilical connections and EGS will run integrated tests before a wet dress rehearsal at Launch Pad 39B.
Lockheed Martin

NYSE:LMT

LMT Rankings

LMT Latest News

LMT Latest SEC Filings

LMT Stock Data

112.93B
233.28M
0.08%
75.59%
0.9%
Aerospace & Defense
Guided Missiles & Space Vehicles & Parts
Link
United States
BETHESDA