MAYFAIR PROVIDES FENN-GIB PROJECT UPDATE
Rhea-AI Summary
Mayfair Gold (OTCQX: MFGCF) updated progress on the Fenn-Gib Project, reporting the PFS remains on track for Q4 2025, a high-density starter-pit drilling program underway, and geotechnical site investigations for the tailings storage facility.
Key facts: a 56-hole, 10m x 10m diamond drill program (~4,200 m) began 21 October 2025; conceptual open pit shown at a 0.7 g/t Au cut-off; TSF investigations included 25 test pits and 347 m of drilling; recent MRE has ~97% indicated confidence. Additional site work continues into 2026.
Positive
- PFS scheduled for completion in Q4 2025
- High-density drill program: 56 holes totaling ~4,200 m
- TSF site investigations: 25 test pits and 347 m drilled
- Mineral Resource Estimate at ~97% indicated confidence
Negative
- Suppliers/vendors face elevated demand, pressuring procurement and costs
- Additional site investigations will continue into 2026, extending field work
News Market Reaction 1 Alert
On the day this news was published, MFGCF gained 4.45%, reflecting a moderate positive market reaction.
Data tracked by StockTitan Argus on the day of publication.
- Pre-Feasibility Study on track for completion in Q4 2025
- Open pit mine plan to target near-surface high-grade mineralization
- Drill program underway to further delineate the high-grade starter zone at Fenn-Gib
- Tailing Storage Facility site investigation program – Phase 1 Complete
The Company's upcoming PFS will be based on the recently updated NI 43-101 Mineral Resource Estimate ("MRE") for the Fenn-Gib Project (see news release October 8, 2025, titled "Mayfair Gold Files Technical Report for Fenn-Gib Project"). The mine plan will prioritize near-surface high-grade zones within the open pit to maximize feed grade to the proposed on-site processing facility and optimize early-stage cash flow. The open pit operation is expected to incorporate conventional drill-and-blast methods, supported by a truck and shovel fleet.
By applying an elevated cut-off grade strategy focused on near-surface high-grade zones, the Company aims to enhance short-term project economics while preserving the integrity of the broader resource base. Figure 1 illustrates a conceptual open pit based on a 0.7 g/t Au cut-off grade, highlighting the potential configuration of a high-grade starter pit.
Nick Campbell, CEO of Mayfair Gold, stated, "The Fenn-Gib deposit is unique in that the highest-grade material occurs near the surface which allows for the potential to start operations with a smaller, targeted mining operation focused on low strip ratio, high-grade gold mineralization. Rather than pursue a larger scale operation, the grade distribution at Fenn-Gib provides Mayfair the optionality to fast-track the extraction of high margin material while at the same time mitigating construction risk and initial capital requirements. It also has the benefit of allowing us to follow the well-defined Ontario Provincial permitting process."
Nick further commented, "With the Canadian gold price currently above
High-Density Drilling Program Underway to Support PFS and Starter Pit Development
Although the deposit has been drilled to a
The drilling is designed to confirm and delineate near-surface high-grade mineralization expected to be mined and processed during the early years of operation. The results will enhance confidence in the geological model and contribute to de-risking the Project as it advances toward development.
Mayfair has engaged Black Diamond Drilling, a highly skilled contractor from the neighbouring Apitipi Anicinapek Nation, to execute the program. Drilling commenced on 21 October 2025 and is expected to continue through December 2025.
In addition to improved grade-control definition, the program will support further calibration of surficial geology and subsurface hydrogeological models within the open pit. Additional samples will also be used for ongoing metallurgical testing to further refine the geological-metallurgical recovery model.
Geotechnical Site Investigations for the Tailing Storage Facility
The Project has completed additional site investigations to support the design of the tailing storage facility ("TSF"). The site investigation program included 25 test pits and 347 meters of drilling over 10 holes around the perimeter of the proposed TSF footprint. Work was completed under the oversight of Knight Piesold who are the designers of the TSF. The geotechnical and hydrogeological information collected during the program will assist in better defining the design of the TSF. Additional site investigations will continue in 2026.
Drew Anwyll, P.Eng, Chief Operating Officer noted, "The tailings storage facility and broader site investigations are critical to de-risking the Fenn-Gib Project. A thorough understanding of the material properties of the overburden and underfoot conditions will lead to improved foundation and building designs and significantly enhances execution confidence. This phase is often undervalued and overlooked, yet it plays a significant role in setting projects up for success."
Pre-Feasibility Study on Track for Release in Q4 2025
The PFS for the Fenn-Gib Project continues to progress in line with the forecasted schedule, with completion anticipated in Q4 2025. Remaining work includes incorporating results from recent site investigations into the earthworks scope to optimize construction efficiency and cost estimates, as well as finalizing the integration of overall PFS costs into the broader economic analysis.
The Company notes that suppliers, vendors, and contractors are experiencing elevated demand due to the recent increase in gold prices, contributing to a highly active procurement environment.
With Canadian gold prices above
About Mayfair Gold
Mayfair Gold is a Canadian mineral exploration company focused on advancing the
Tim Maunula, P. Geo., of T. Maunula & Associates Consulting Inc., is a qualified person for the purposes of NI 43-101 and was responsible for the completion of the updated mineral resource estimate. Mr. Maunula has reviewed and approved the scientific and technical content with respect to the mineral resource estimate in this news release. Scientific and technical information with respect to diamond drilling in this news release has been reviewed and approved by Ali Gelinas-Dechene, P.Geo., Senior Geologist for Mayfair Gold, who oversaw the Mayfair Gold drill program, QA/QC and serves as a Qualified Person as defined under NI 43-101.
The scientific and technical content of this news release was reviewed, verified and approved by Drew Anwyll, P.Eng., M.Eng, Chief Operating Officer of the Company, and a Qualified Person as defined under NI 43-101.
Cautionary Notes to U.S. Investors Concerning Resource Estimates.
This news release has been prepared in accordance with the requirements of the securities laws in effect in
Cautionary Note Regarding Forward-Looking Information
This news release contains forward-looking information which reflects management's expectations regarding the Company's growth, results of operations, performance and business prospects and opportunities. Forward-looking statements in this news release include, but are not limited to, statements regarding the design, development and execution of the Fenn-Gib Gold Project, the timing for completion of the PFS, the advancement of the Fenn-Gib Gold Project to operation and the timing thereof, advancing Fenn-Gib to production and cash flow expected to help fund potential future growth opportunities, including the potential to permit and develop a larger operation at Fenn-Gib, and the potential uplisting in
Forward-looking information is subject to a variety of risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking information, including, without limitation, risks and uncertainties relating to foreign currency fluctuations; risks inherent in mining including environmental hazards, industrial accidents, unusual or unexpected geological formations, ground control problems and flooding; delays or the inability to obtain necessary governmental permits or financing; risks associated with the estimation of mineral resources and reserves and the geology, grade and continuity of mineral deposits; the possibility that future exploration, development or mining results will not be consistent with the Company's expectations; the potential for and effects of labor disputes or other unanticipated difficulties with or shortages of labor; failure of plant, equipment or processes to operate as anticipated; actual ore mined varying from estimates of grade, tonnage, dilution and metallurgical and other characteristics; the inherent uncertainty of production and cost estimates and the potential for unexpected costs and expenses, gold price fluctuations; uncertain political and economic environments; and changes in laws or policies.
The Company undertakes no obligation to publicly update or review the forward-looking statements whether as a result of new information, future events or otherwise, other than as required under applicable securities laws. The forward-looking statements reflect management's beliefs, opinions and projections as of the date of this news release.
Neither the TSX Venture Exchange ("TSXV") nor its Regulation Services Provider (as that term is defined in the policies of the TSXV) accepts responsibility for the adequacy or accuracy of this news release.
View original content to download multimedia:https://www.prnewswire.com/news-releases/mayfair-provides-fenn-gib-project-update-302609684.html
SOURCE Mayfair Gold Corp.