STOCK TITAN

NeoVolta Announces Capacity Reservation Agreement with Infinite Grid Capital Ahead of Pendergrass Facility Grand Opening

A $53 million 2027 capacity reservation anchors NeoVolta's new Pendergrass BESS plant and validates demand from AI data centers.

(Very Positive)
Tags

NeoVolta (NEOV) announced a binding capacity reservation agreement with Infinite Grid Capital reserving approximately $53 million of Pendergrass manufacturing capacity for Northern Ontario Edge AI data center battery energy storage projects in calendar year 2027.

This is the first commercial capacity reservation under a previously announced utility-scale framework with IGC covering about 1.1 GWh of potential BESS deployments and roughly $200 million of potential supply. The agreement is described as an important commercial milestone that validates NeoVolta Power’s utility-scale product offering and domestic BESS manufacturing strategy. NeoVolta is also holding the grand opening of its 210,600-square-foot Pendergrass, Georgia facility, whose initial production line is in commissioning and whose production ramp remains on track for the fourth quarter of 2026.

Loading...
Loading translation...

Positive

  • Approximately $53 million binding 2027 capacity reservation with Infinite Grid Capital
  • First commercial commitment under ~$200 million, 1.1 GWh utility-scale framework
  • Pendergrass facility sized at 210,600 square feet for commercial, industrial and utility-scale BESS
  • Production ramp at Pendergrass remains on track for Q4 2026
  • Initial commitment targets AI data center projects, highlighting demand from energy-intensive customers

Negative

  • None.

Market Context

On Aug 10, 2026, NeoVolta filed an S-3 resale registration covering 4,500,000 shares held by IGC; th...
Analysis

On Aug 10, 2026, NeoVolta filed an S-3 resale registration covering 4,500,000 shares held by IGC; the filing states NeoVolta receives no resale proceeds, providing relevant shareholder-term context for this IGC agreement.

Key Figures

Binding commitment: Approximately $53 million Potential supply framework: Approximately $200 million Potential BESS deployments: Approximately 1.1 GWh +3 more
Binding commitment
Approximately $53 million
Pendergrass manufacturing capacity reservation for calendar year 2027
Potential supply framework
Approximately $200 million
Previously announced utility-scale framework with IGC
Potential BESS deployments
Approximately 1.1 GWh
Previously announced utility-scale framework
Reserved supply period
Calendar year 2027
Northern Ontario Edge AI data center projects
Facility size
210,600 square feet
NeoVolta Power facility in Pendergrass, Georgia
Production ramp
Fourth quarter of calendar 2026
Initial Pendergrass production line

Historical Context

2 past events · Latest: Aug 31
2 events
  1. Aug 31

    Partnership agreement

    24h Move
    +26.9%

    SK On collaboration secured 9 GWh of U.S.-manufactured LFP battery cells for Pendergrass expansion.

  2. Sep 10

    Credit facility

    24h Move
    -6.1%

    Horizon funded a $20 million senior credit facility to support NeoVolta growth.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

Key Terms

bess, site acceptance testing
2 terms
bess technical
"battery energy storage system (“BESS”) equipment"
BESS stands for Battery Energy Storage System, a technology that stores electricity for later use. Think of it as a large rechargeable battery that can hold excess power generated during times of low demand and release it when usage is high, helping balance supply and demand. This is important for investors because it supports the stability of energy grids, enables the integration of renewable sources, and can create new opportunities for profitability in the energy market.
site acceptance testing technical
"commissioning and Site Acceptance Testing"
Site acceptance testing is the final, on-location check that equipment, systems or installations perform as promised after they are delivered and set up at a facility. It matters to investors because passing this test is often required before a company can start operations, recognize revenue or meet regulatory conditions; a failed test can delay production, increase costs and push back cash flow—like taking a newly installed car for a test drive before signing off and driving it regularly.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Agreement Reserves Approximately $53 Million of Pendergrass Manufacturing Capacity for Northern Ontario Edge AI Data Center Projects

Represents First Commercial Capacity Reservation Under Previously Announced Approximately $200 Million Utility-Scale Framework

SAN DIEGO, Sept. 17, 2026 (GLOBE NEWSWIRE) -- NeoVolta Inc. (NASDAQ: NEOV) (“NeoVolta” or the “Company”), a U.S.-based energy technology company delivering scalable energy storage solutions, today announced that its majority-owned subsidiary, NeoVolta Power, LLC (“NeoVolta Power”), has entered into a binding capacity reservation agreement with Infinite Grid Capital (“IGC”) to provide battery energy storage system (“BESS”) equipment for North Ontario Edge artificial intelligence datacenter (“Edge AIDC”) projects for calendar year 2027.

Today’s announcement represents the first major commercial commitment under NeoVolta Power’s previously announced utility-scale framework with IGC, which contemplates approximately 1.1 GWh of potential BESS deployments and approximately $200 million of potential supply across multiple markets. The approximately $53M binding commitment advances the Company’s strategy of converting early utility-scale demand visibility into binding commercial relationships as its Pendergrass manufacturing platform progresses through commissioning and production-ramp activities.

“This is an important commercial milestone for NeoVolta Power and a meaningful validation of the platform we have built at Pendergrass,” said Ardes Johnson, Chief Executive Officer of NeoVolta. “The project demonstrates how our BESS manufacturing, a differentiated supply-chain strategy, and scalable energy-storage products can address the rapidly growing power-infrastructure needs of data centers and other energy-intensive customers. As we advance the production ramp at Pendergrass, our focus is on executing this initial commitment and converting additional qualified demand into binding customer orders.”

Utility-Scale Demand Validation

The capacity reservation agreement is intended to support the Northern Ontario Edge AIDC project and represents an initial commercial step within NeoVolta’s broader relationship with IGC. The relationship was previously announced as a non-binding framework spanning approximately 1.1 GWh of potential demand.

The Company believes the initial data-center-related commitment is strategically significant. Growth in artificial intelligence and data-center infrastructure is increasing the need for reliable, scalable power solutions, and BESS is expected to play an increasingly important role in supporting grid reliability, load management, and project-level energy resilience. The commitment provides commercial validation for NeoVolta Power’s utility-scale product offering and its domestic BESS manufacturing strategy.

Pendergrass Grand Opening

NeoVolta will host a grand-opening ceremony for its NeoVolta Power facility in Pendergrass, Georgia, later today. Members of NeoVolta management, key strategic partners, media, and local officials are expected to attend.

The event marks the official opening of the Company’s 210,600-square-foot facility, a purpose-built domestic BESS manufacturing platform designed to assemble commercial, industrial, and utility-scale energy-storage products. The Company’s initial Pendergrass production line is advancing through commissioning and Site Acceptance Testing, and the production ramp remains on track for the fourth quarter of calendar 2026.

NeoVolta expects to provide additional updates regarding the commissioning process, manufacturing milestones, and commercial activity as appropriate.

About Infinite Grid Capital

Infinite Grid Capital (“IGC”) is an energy infrastructure investment platform that develops and finances large-scale power projects, including battery energy storage systems, hybrid energy hubs, and dedicated power solutions for data centers across North America and selected global markets, including key U.S. power regions such as California, Texas, and the Southeastern United States. IGC focuses on building reliable and flexible energy assets that ensure continuous power for AI workloads, industrial operations, and other mission-critical facilities. Infinite Grid Capital is an existing strategic investor in NeoVolta and provides offtake origination and related advisory services in connection with NeoVolta Power’s BESS manufacturing operations.

For more information, visit www.infinitegridcapital.com.

About NeoVolta

NeoVolta is an innovator in energy storage solutions dedicated to advancing reliable, high-performance power infrastructure for residential, commercial, and utility applications. With a focus on scalable technology, domestic manufacturing, and strategic partnerships, NeoVolta is positioned to support the accelerating transition toward resilient energy systems.

For more information, visit www.neovolta.com.

Forward-Looking Statements

This press release contains forward-looking statements within the meaning of applicable federal securities laws. Forward-looking statements include statements regarding the Company’s business strategy, plans, objectives, expectations, and future operations; the anticipated timing and benefits of the Company’s manufacturing activities; the Company’s ability to execute its production ramp and achieve manufacturing and commercial milestones; anticipated customer demand, project opportunities, and order conversion; and the Company’s growth plans and future financial and operating performance.

Forward-looking statements are based on current expectations and assumptions and are subject to risks and uncertainties that could cause actual results to differ materially from those expressed or implied. These risks and uncertainties include, among others, risks related to market conditions; customer demand; the Company’s ability to execute its business strategy and manufacturing plans; supply-chain availability and costs; project development, permitting, construction, and deployment activities; the availability of financing; changes in laws, regulations, tax incentives, tariffs, or trade policies; competition; and other risks described in the Company’s filings with the U.S. Securities and Exchange Commission.

Forward-looking statements speak only as of the date made, and the Company undertakes no obligation to update or revise them, except as required by law.

Contacts

NEOV Investors
Bryan Baritot
Alliance Advisors IR
ir@neovolta.com  

NEOV Media
Email: press@neovolta.com
Phone: 800-364-5464


FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

What projects are covered by NeoVolta’s new capacity reservation with Infinite Grid Capital?

The binding capacity reservation agreement is intended to support Northern Ontario Edge artificial intelligence datacenter projects, where NeoVolta Power will provide battery energy storage system equipment in calendar year 2027.

How does this agreement relate to NeoVolta’s broader framework with Infinite Grid Capital?

The agreement represents the first major commercial step under a previously announced non-binding utility-scale framework with Infinite Grid Capital that spans approximately 1.1 GWh of potential battery energy storage demand and about $200 million of potential supply across multiple markets.

What is the role of the Pendergrass, Georgia facility in NeoVolta’s strategy?

The Pendergrass facility is a 210,600-square-foot domestic manufacturing platform designed to assemble commercial, industrial, and utility-scale energy storage products. The company said it is progressing through commissioning and Site Acceptance Testing, with the initial production ramp expected in the fourth quarter of calendar 2026.

Who is Infinite Grid Capital and how is it connected to NeoVolta?

Infinite Grid Capital is an energy infrastructure investment platform that develops and finances large-scale power projects, including BESS, hybrid energy hubs, and dedicated power solutions for data centers across North America and selected global markets. It is described as an existing strategic investor in NeoVolta and provides offtake origination and related advisory services for NeoVolta Power’s BESS manufacturing operations.

What future updates does NeoVolta plan to provide regarding Pendergrass and its utility-scale business?

NeoVolta expects to provide additional updates on the Pendergrass facility’s commissioning process, manufacturing milestones, and commercial activity as appropriate as it advances the production ramp and seeks to convert additional qualified demand into binding customer orders.

Keep reading