NextDecade Provides First Quarter 2026 Business Update
Key Terms
engineering, procurement, and construction technical
epc technical
free-on-board financial
fob financial
front-end engineering and design technical
federal energy regulatory commission regulatory
ferc regulatory
final investment decision financial
Strong construction progress continues at Rio Grande LNG
CEO Commentary
“NextDecade is continuing to progress rapidly toward first LNG at the Rio Grande LNG Facility as we work with Bechtel to construct our trains safely, on budget, and ahead of schedule,” said Matt Schatzman, NextDecade Chairman and CEO. “Phase 1 continues to track ahead of the guaranteed substantial completion dates for each train, early electrical commissioning of Train 1 continues, and we expect first gas into the facility in the second half of this year and first LNG production in the first half of 2027.”
“We are also focused on the continued development of Trains 6 through 8, and we continue to expect to make a full filing with the Federal Energy Regulatory Commission for Train 6 before the end of the second quarter and also progress the development of Trains 7 and 8 this year. In parallel, we are working with Bechtel on front-end engineering and design for Train 6 and having commercial discussions with potential buyers for long-term sales of LNG from Train 6. We are excellently positioned to provide reliable, secure, and affordable energy to customers across the globe via long-term LNG sales from our expansion trains.”
Significant Recent Developments
Construction and Commissioning
-
Under the engineering, procurement, and construction (“EPC”) contracts with Bechtel Energy, Inc. (“Bechtel”), as of March 2026:
-
The overall project completion percentage for Trains 1 and 2 and the common facilities at the Rio Grande LNG Facility was
67.8% . Within this project completion percentage, engineering was98.4% complete, procurement was94.3% complete, and construction was49.4% complete. -
The overall project completion percentage for Train 3 at the Rio Grande LNG Facility was
44.2% . Within this project completion percentage, engineering was91.4% complete, procurement was82.6% complete, and construction was11.4% complete. -
The overall project completion percentage for Train 4 at the Rio Grande LNG Facility was
10.6% . Within this project completion percentage, engineering was43.6% complete, procurement was18.8% complete, and construction was0.5% complete. -
The overall project completion percentage for Train 5 at the Rio Grande LNG Facility was
6.8% . Within this project completion percentage, engineering was11.7% complete, procurement was15.3% complete, and construction was0.0% complete.
-
The overall project completion percentage for Trains 1 and 2 and the common facilities at the Rio Grande LNG Facility was
- Early electrical commissioning of Train 1 continues, and we expect first gas into the Rio Grande LNG Facility in the second half of 2026 and first LNG production from Train 1 in the first half of 2027.
Strategic and Commercial
-
In early 2026, we began the marketing of early cargoes that we expect to produce in 2027 and 2028 prior to the commencement of our long-term LNG Sale and Purchase Agreements ("SPAs"). In February 2026, we entered into LNG sales agreements for the sale of over 175 TBtu of LNG on a free-on-board ("FOB") basis, with fixed liquefaction fees that are expected to achieve a cargo margin, calculated as the FOB LNG sales price less our expected costs of natural gas feedstock and fuel, of over
per MMBtu. This volume represents$3.00 33% of our expected portfolio volumes from 2027 through early 2029.
Rio Grande LNG Facility
We are constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south
Liquefaction Capacity Under Construction (Trains 1-5)
Construction commenced on Phase 1 at the Rio Grande LNG Facility in July 2023, on Train 4 in September 2025, and on Train 5 in October 2025, in each case following a positive final investment decision ("FID") and the closing of project financing by the Company's subsidiaries. Construction will be completed by Bechtel under fully wrapped, lump-sum turnkey EPC contracts, and the liquefaction trains will utilize Honeywell AP-C3MR liquefaction technology, which is a predominant liquefaction technology utilized globally.
The combined scope of Phase 1, Train 4, and Train 5 includes five liquefaction trains with a total expected LNG production capacity of approximately 30 million tonnes per annum ("MTPA"), four 180,000 cubic meter full containment LNG storage tanks, two jetty berthing structures designed to load LNG carriers up to 216,000 cubic meters in capacity, and associated site infrastructure and common facilities including feed gas pretreatment facilities, electric and water utilities, ground flares, roads, levees surrounding the entire site, warehouses, and operations control room, maintenance, and administrative buildings.
Progress on Phase 1 as of March 2026 is ahead of the guaranteed completion schedule under the EPC contracts. Train 1 continues to progress across all areas, with focus on piping, equipment installation, cable pulling, testing, and system completions, and the main cryogenic heat exchanger ("MCHE") has been successfully installed in Train 1. Construction activities for Trains 2 and 3 are advancing, including civil works, piping, structural steel, and equipment installation, with placement of the Train 2 compressor packages underway. Welding of the inner tanks is progressing for Tanks 1 and 2, and concrete roof placement has been completed for both tanks.
Progress on Train 4 as of March 2026 is in line with the EPC contract. Early civil works are progressing on Train 4, and production piling has commenced for Tank 3. Progress on Train 5 as of March 2026 is in line with the EPC contract, and site preparation activities are underway for Train 5.
Across the site as of March 2026, construction of all permanent buildings is progressing, installation of perimeter security fencing is underway, construction activities at the gas inlet area are ongoing, dredging activities for the berths and turning basin are substantially complete, and channel deepening is nearing completion.
NextDecade holds equity interests in the Phase 1 joint venture that entitle it to receive up to
Development of Additional Liquefaction Capacity
We are developing and advancing the permitting process for Trains 6 through 8 at the Rio Grande LNG Facility site, which are currently wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 MTPA once constructed and placed into operation.
Train 6 is being developed inside the existing levee at the Rio Grande LNG Facility site and adjacent to Trains 1 through 5. In November 2025, we initiated the pre-filing process with the Federal Energy Regulatory Commission (“FERC”) for expansion at the Rio Grande LNG Facility that includes Train 6 and an additional marine berth, and we expect to file a formal application for this expansion with FERC before the end of the second quarter of 2026. We are evaluating multiple areas on the site for the development of Trains 7 and 8 and expect to advance the development of these trains throughout 2026.
There is sufficient space at the Rio Grande LNG Facility site for up to 10 liquefaction trains.
Investor Presentation and Webcast
NextDecade will host a conference call and webcast on Friday, May 1, 2026, at 11:00 a.m. Eastern Time (10:00 a.m. Central Time) to discuss developments from the first quarter of 2026. The webcast and accompanying presentation may be accessed through the Company’s website at https://investors.next-decade.com. A replay will also be available after the webcast concludes.
About NextDecade Corporation
NextDecade is committed to providing the world access to reliable, cleaner energy. We are focused on delivering secure and affordable energy through the safe and efficient development and operation of natural gas liquefaction capacity at Rio Grande LNG. Through our subsidiaries, we are constructing and developing the Rio Grande LNG natural gas liquefaction and export facility near
Forward-Looking Statements
This press release contains forward-looking statements within the meaning of
View source version on businesswire.com: https://www.businesswire.com/news/home/20260501318566/en/
NextDecade Contacts
Investors
Megan Light
mlight@next-decade.com
832-981-6583
Media
Susan Richardson
srichardson@next-decade.com
832-413-6400
Source: NextDecade Corporation