NextDecade Provides Third Quarter 2025 Business Update
CEO Commentary
“The last few months have been transformative for NextDecade, as we completed financing and achieved positive Final Investment Decisions (FIDs) on Rio Grande LNG Train 4 and Train 5 without a material impact to NextDecade shares outstanding,” said Matt Schatzman, NextDecade’s Chairman and Chief Executive Officer. “We have shown that we can execute on expansion capacity at Rio Grande LNG in a way that is repeatable, delivers attractive expected returns, and maximizes projected cash flow on a per share basis.”
“Our expected 30 million tonnes per annum (MTPA) of liquefaction production capacity from Rio Grande LNG Trains 1 through 5 will place us at approximately
“We are dedicated to excellence in constructing and completing the first five trains at Rio Grande LNG safely and delivering on the projections we have provided to our shareholders and other stakeholders. Rio Grande LNG Phase 1 continues to progress safely and on budget, and is currently tracking ahead of schedule.”
Significant Recent Developments
Development and Construction
-
Under the engineering, procurement, and construction (EPC) contracts with Bechtel Energy Inc. (Bechtel), as of September 2025:
-
The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was
55.9% . Within this project completion percentage, engineering was95.0% complete, procurement was88.8% complete, and construction was29.8% complete. -
The overall project completion percentage for Train 3 of the Rio Grande LNG Facility was
33.4% . Within this project completion percentage, engineering was70.8% complete, procurement was67.2% complete, and construction was4.5% complete. - Progress for Train 4 included advancement on engineering drawings, issuance of purchase orders for a range of equipment and materials, and commencement of area clearing.
-
The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was
-
On September 9, 2025, the Company announced a positive FID on Train 4 and related infrastructure at the Rio Grande LNG Facility and issued a full notice to proceed (NTP) to Bechtel under the EPC contract for Train 4. Total project costs for Train 4 and related infrastructure are expected to total approximately
. Train 4 has an expected LNG production capacity of approximately 6 MTPA, and guaranteed substantial completion of Train 4 is in the second half of 2030.$6.7 billion -
On October 16, 2025, the Company announced a positive FID on Train 5 and related infrastructure at the Rio Grande LNG Facility and issued a full NTP to Bechtel under the EPC contract for Train 5. Total project costs for Train 5 and related infrastructure are expected to total approximately
. Train 5 has an expected LNG production capacity of approximately 6 MTPA, and guaranteed substantial completion of Train 5 is in the first half of 2031.$6.7 billion
Strategic and Commercial
- In September 2025, the Company announced a 20-year LNG Sale and Purchase Agreement (SPA) with EQT Corporation (EQT), pursuant to which EQT will purchase 1.5 MTPA of LNG from Train 5 at the Rio Grande LNG Facility for 20 years, on a free on board (FOB) basis at a price indexed to Henry Hub.
- In September 2025, the Company announced a 20-year LNG SPA with ConocoPhillips, pursuant to which ConocoPhillips will purchase 1.0 MTPA of LNG from Train 5 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub.
Financial
-
On September 9, 2025, in conjunction with the positive FID on Train 4 at the Rio Grande LNG Facility, the Company and certain of its subsidiaries closed an approximately
project financing for Train 4, which included the closing of:$6.7 billion -
A joint venture agreement which included approximately
of financial commitments from Global Infrastructure Partners, a part of BlackRock (“GIP”), GIC, Mubadala Investment Company, and TotalEnergies;$1.69 billion -
A commitment by the Company to invest approximately
in Train 4; and$1.13 billion -
A senior secured, non-recourse bank credit facility of
with a seven year maturity.$3.85 billion
-
A joint venture agreement which included approximately
-
On September 9, 2025, to fully fund the Company’s approximately
equity commitments for Train 4, certain of the Company’s wholly-owned subsidiaries entered into a delayed draw, senior secured term loan bank facility of$1.13 billion with a five year maturity (the “FinCo Loan”) and term loans of$734 million with a maturity date of the earlier of eight years or the 85th day prior to the maturity of the FinCo Loan (the “Super FinCo Loan”).$600 million -
On October 16, 2025, in conjunction with the positive FID on Train 5 at the Rio Grande LNG Facility, the Company and certain of its subsidiaries closed an approximately
project financing for Train 5, which included the closing of:$6.7 billion -
A joint venture agreement which included approximately
of financial commitments from GIP, GIC, and Mubadala Investment Company;$1.29 billion -
A commitment by the Company to invest approximately
in Train 5;$1.29 billion -
A senior secured, non-recourse bank credit facility of
with a seven year maturity; and$3.59 billion -
An offering of
senior secured, non-recourse private placement notes, which will bear interest at$500 million 6.56% , will be funded in multiple tranches from December 2025 through October 2026, and will amortize over a period of 20 years beginning in September 2031.
-
A joint venture agreement which included approximately
-
On October 16, 2025, to fully fund the Company’s approximately
equity commitments for Train 5, the Company contributed$1.29 billion cash to Rio Grande LNG Train 5, LLC, and certain of the Company’s wholly-owned subsidiaries increased the size of the FinCo Loan by$233 million , to a total of approximately$729 million , and increased the size of the SuperFinCo Loan by$1.46 billion , to a total of$600 million .$1.2 billion -
In October 2025, Rio Grande LNG Super Holdings, LLC, entered into a term sheet with the lender of its existing senior secured loan (the “Super Holdings Loan”) to refinance
of the existing loan amount and provide$50 million of incremental capital in the form of an exchangeable loan with total initial principal of$50 million (the “Exchangeable Loan”). Upon consummation of the transaction, the Exchangeable Loan would bear interest at$100 million 8% , payable in cash or in-kind at the Company’s election, and would mature in October 2030. The initial principal of the Exchangeable Loan, and any amounts of interest paid in-kind, would be exchangeable into shares of Company common stock at per share. Additionally, the interest rate on the remaining balance of the Super Holdings Loan would be amended to$9.50 13.5% .
Regulatory
- In July 2025, the Federal Energy Regulatory Commission (FERC) issued a final supplemental Environmental Impact Statement (SEIS) for the first five liquefaction trains at the Rio Grande LNG Facility, following a draft SEIS in March 2025.
- In August 2025, the FERC issued a final order on remand reaffirming its authorization for the siting, construction, and operation of the first five liquefaction trains at the Rio Grande LNG Facility, and as of October 30, 2025, the order is no longer appealable to FERC.
Rio Grande LNG Facility
NextDecade is constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south
Liquefaction Capacity Under Construction (Trains 1-5)
Construction commenced on Trains 1-3 (Phase 1) at the Rio Grande LNG Facility in July 2023, on Train 4 in September 2025, and on Train 5 in October 2025. The combined scope of Phase 1, Train 4, and Train 5 includes five liquefaction trains with a total expected LNG production capacity of approximately 30 MTPA, four 180,000 cubic meter full containment LNG storage tanks, two jetty berthing structures designed to load LNG carriers up to 216,000 cubic meters in capacity, and associated site infrastructure and common facilities including feed gas pretreatment facilities, electric and water utilities, ground flares, roads, levees surrounding the entire site, and warehouses, administrative, operations control room and maintenance buildings.
As of September 2025, progress on Phase 1 is ahead of schedule under the EPC contracts. During the third quarter of 2025, the construction team continued piping fabrication, rebar installation, equipment setting and concrete placement, and structural steel erection in the areas of Trains 1, 2, and 3. Roof raises were completed for the first two LNG storage tanks. Across the site, Bechtel also continued installing concrete foundations, instrument air receivers, floodgates, permanent fencing, temporary facilities, and other siteworks. In September 2025, the first compressor string and turbine for Train 1 arrived onsite.
During September 2025, progress on Train 4 included advancement on engineering drawings, issuance of purchase orders for a range of equipment and materials, and commencement of area clearing.
NextDecade holds equity interests in the Phase 1 joint venture that entitle it to receive up to
Development of Additional Liquefaction Capacity
The Company is developing and advancing the permitting process for additional liquefaction capacity at the Rio Grande LNG Facility site. Trains 6 through 8 are currently wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 MTPA once constructed and placed into operation.
Train 6 is being developed inside the existing levee at the Rio Grande LNG Facility site and adjacent to Trains 1 through 5. The Company expects to pre-file an application with FERC for Train 6 in 2025 and a full application with FERC in 2026. The Company is evaluating multiple areas on the site for the development of Trains 7 and 8.
There is sufficient space at the Rio Grande LNG Facility site for up to 10 liquefaction trains.
Investor Presentation
NextDecade has posted an updated investor presentation to its website concurrently with this release. A copy of this release and the investor presentation can be found on its website at www.investors.next-decade.com.
About NextDecade Corporation
NextDecade is committed to providing the world access to reliable, cleaner energy. We are focused on delivering secure and affordable energy through the safe and efficient development and operation of natural gas liquefaction capacity at Rio Grande LNG. Through our subsidiaries, we are constructing and developing the Rio Grande LNG natural gas liquefaction and export facility near
Forward-Looking Statements
This press release contains forward-looking statements within the meaning of
View source version on businesswire.com: https://www.businesswire.com/news/home/20251030202235/en/
NextDecade Contacts
Investors
Megan Light
mlight@next-decade.com
832-981-6583
Media
Susan Richardson
srichardson@next-decade.com
832-413-6400
Source: NextDecade Corporation