NOVAGOLD (NYSE American: NG) and Donlin Gold Holdings, owned by Paulson, selected Fluor Corporation to lead the Bankable Feasibility Study (BFS) for the Donlin Gold project in Alaska. Fluor has commenced work and will integrate Specialist Contractors while the BFS is expected to be completed in 2027.

A detailed BFS schedule and budget will be released after full-scope alignment; site activities, geotechnical drilling and owner team recruitment are ongoing as the project advances toward financing and development.

Loading...
Loading translation...

Positive

  • Fluor selected to lead the Bankable Feasibility Study
  • BFS expected to be completed in 2027

Negative

  • Detailed BFS budget and schedule remain pending
  • Project advancement requires successful financing before development

News Market Reaction – NG

+8.92%
44 alerts
+8.92% Session close to close
+20.0% Peak in 35 hr 14 min
$4.30B Market Cap
1.5x Rel. Volume

In the Feb 9 session, NG gained 8.92%, reflecting a notable positive market reaction. Argus tracked a peak move of +20.0% during that session. Our momentum scanner triggered 44 alerts that day, indicating elevated trading interest and price volatility.

Data tracked by StockTitan Argus on the day of publication.

Market Context

The stock moved +8.9% in the session following this news. A strong positive reaction aligns with a s...
Analysis

The stock moved +8.9% in the session following this news. A strong positive reaction aligns with a series of Donlin‑focused milestones, including prior drill successes and the $1.0 billion ownership transaction and $131.4M 2026 budget. Selecting Fluor to lead a Bankable Feasibility Study expected by 2027 further clarified execution plans and may have reinforced confidence after the recent $310.2M bought‑deal financing. However, past news shows at least one positive infrastructure update with limited impact, underscoring that enthusiasm can moderate as execution and timelines are digested.

Key Figures

BFS completion target: 2027
1 metrics
BFS completion target 2027 Bankable Feasibility Study expected completion year

Historical Context

5 past events · Latest: Jan 22 (Positive)
Pattern 5 events
Date Event Sentiment 24h Move Catalyst
Jan 22 Year-end report & financing Positive +5.0% Expanded Donlin ownership, major financing, and 2026 Donlin project budget.
Jan 13 Leadership appointment Positive +0.6% New Project Director to lead planning and execution of the BFS.
Jan 09 Infrastructure LOI update Positive +0.0% LOI for natural gas supply and 316‑mile pipeline planning for Donlin.
Jan 07 Earnings call notice Neutral -0.6% Announcement of 2025 year-end report webcast and BFS progress discussion.
Nov 25 Drill & permit update Positive +6.2% High‑grade drill results and favorable Alaska Supreme Court permit decision.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

Pattern Detected

Recent Donlin-related milestones and court/drill updates have generally seen positive price alignment, with only one notable instance of minimal reaction to positive infrastructure news.

Recent Company History

Over the last several months, NOVAGOLD has steadily advanced Donlin Gold toward development. On Nov 25, 2025, high‑grade drill results and a favorable Alaska Supreme Court decision supported the planned Bankable Feasibility Study and saw a 6.21% move. Subsequent updates in early 2026 highlighted a Glenfarne LNG letter of intent, appointment of a dedicated Project Director, and the Jan 22, 2026 year-end report detailing a $1.0 billion transaction and a $131.4M 2026 Donlin budget. Today’s selection of Fluor as BFS lead fits this progression toward a full, investment-grade study.

Key Terms

bankable feasibility study, pressure oxidation circuit, natural gas pipeline
3 terms
bankable feasibility study technical
"Fluor was selected to lead the Bankable Feasibility Study (BFS) as the engineering firm"
A bankable feasibility study is a comprehensive, independently reviewed analysis that shows whether a proposed project is technically sound, legally clear, environmentally acceptable and financially viable enough for banks or other lenders to provide long-term financing. Think of it as a detailed business plan plus an inspector’s report that quantifies costs, revenue forecasts and key risks; investors use it as evidence that the project can deliver returns and secure the funding needed to proceed.
pressure oxidation circuit technical
"key pieces of infrastructure and process unit operations. These include the power plant, the natural gas pipeline, and the pressure oxidation circuit and oxygen plant."
A pressure oxidation circuit is a high-pressure, high-temperature chemical processing step that 'cooks' certain hard-to-treat mineral ores inside sealed vessels so the valuable metals become extractable. Think of it like a pressure cooker that breaks down stubborn material so conventional extraction methods can work. Investors care because it is capital- and energy-intensive, strongly affects metal recovery rates, operating costs, and environmental controls, and therefore influences project economics and risk.
natural gas pipeline technical
"These include the power plant, the natural gas pipeline, and the pressure oxidation circuit and oxygen plant."
A natural gas pipeline is a long network of steel or plastic tubes and compressor stations that move natural gas from production sites to power plants, factories, and homes, like a highway system for fuel. For investors it matters because pipelines are physical assets that earn fees for transporting gas, so their revenue, value, and risk depend on gas demand, pipeline capacity and reliability, regulatory rules, and interruptions that can halt payments.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

VANCOUVER, British Columbia, Feb. 09, 2026 (GLOBE NEWSWIRE) -- NOVAGOLD RESOURCES INC. (“NOVAGOLD” or the “Company”) (NYSE American, TSX: NG) and Donlin Gold Holdings (DGH), 100% wholly-owned by Paulson Advisers LLC (“Paulson”) and its affiliates, are pleased to announce that Fluor Corporation (NYSE: FLR) (“Fluor”) was selected to lead the Bankable Feasibility Study (BFS) as the engineering firm for the Donlin Gold project in Alaska as it advances toward financing and development.

Donlin Gold is advancing the BFS using a disciplined, execution-focused approach informed by longstanding experience in delivering large, multi-disciplinary projects. The emphasis is on fully integrating scope, engineering, cost, and schedule to support a high-quality, investment-grade study, while continuing to make steady and deliberate progress toward development. The BFS is expected to be completed in 2027. A more detailed schedule and budget for the BFS are expected to be released in the coming months following full-scope alignment with other contractors selected to work on discreet portions of the overall project scope (“Specialist Contractors”).

Fluor is a global leader in engineering, mining, processing, and large-scale infrastructure delivery. The company portfolio includes extensive experience executing complex, large-scale gold and copper projects across North America and internationally in challenging environments including cold-weather and remote locations.

The bidding process for the Donlin Gold BFS was thorough and competitive, with participation from top-tier engineering firms. Fluor will integrate the other major work packages into the overall project and coordinate with other Specialist Contractors on key pieces of infrastructure and process unit operations. These include the power plant, the natural gas pipeline, and the pressure oxidation circuit and oxygen plant. Fluor will also bring substantial technical, engineering, and execution capabilities, supporting the design of what is anticipated to become the largest single operating gold mine in the United States. The BFS work will be primarily conducted at Fluor’s offices in Canada, utilize high value centers (HVC), with coordination from the Donlin Gold office and project site in Alaska.

“Fluor is pleased to be appointed as Donlin Gold’s partner to lead the BFS,” said Harish Jammula, Fluor’s President, Mining & Metals Business. “Our focus is on delivering an integrated, high-quality study, with an emphasis on safety, sustainability, quality, cost accuracy, constructability, and execution readiness as the project advances.”

“The selection of Fluor marks an important step in advancing the Donlin Gold project,” said Greg Lang, NOVAGOLD’s President and CEO. “They bring a proven track record of delivering complex projects on schedule and within budget, which is critical at this stage as we position Donlin Gold for development,” added John Paulson.

Scope of Work

Fluor has commenced work on the BFS and will be responsible for integrating workstreams from Specialist Contractors, advancing value and cost optimization, and delivering an integrated engineering, cost, and schedule framework.

Next Steps

Requests for proposals were issued in the fourth quarter of 2025 for Specialist Contractors to cover the power plant, pipeline, and pressure oxidation and oxygen plant scopes of work, which will be incorporated into the BFS.

In parallel, management has identified key project requirements and has begun recruiting critical roles to build the owner’s project team, while site activities continue to advance the next phase of development. This includes ongoing evaluation of geotechnical drilling as well as materials assessments along the planned upriver port and access road to support detailed design and the BFS.

The Company intends to advance these workstreams concurrently to support an integrated BFS and position the project for the next phase of development following completion of the study and project financing. The Company will continue to provide market updates as these activities progress.

About NOVAGOLD

NOVAGOLD is a well-financed precious metals company focused on the development of the Donlin Gold project in Alaska, one of the safest mining jurisdictions in the world. With approximately 40 million ounces of gold in the Measured and Indicated Mineral Resource categories (560 million tonnes at an average grade of approximately 2.22 grams per tonne, in the Measured and Indicated Mineral Resource categories on a 100% basis)1, inclusive of Proven and Probable Mineral Reserves, the Donlin Gold project is regarded to be one of the largest, highest-grade, and most prospective known open-pit gold deposits in the world. The Donlin Gold project is expected to produce an average of more than one million ounces per year over a 27-year mine life on a 100% basis once in production2.

About DGH

Donlin Gold Holdings (DGH), 100% wholly owned by Paulson Advisers LLC & its affiliates, is the 40% owner of the Donlin Gold project. DGH and NOVAGOLD together own 100% of Donlin Gold and share equal voting and operating control.

NOVAGOLD Contacts:

Mélanie Hennessey
Vice President, Corporate Communications

Frank Gagnon
Manager, Investor Relations

604-669-6227 or 1-866-669-6227
info@novagold.com
www.novagold.com

Cautionary Note Regarding Forward-Looking Statements

This media release includes certain “forward-looking information” and “forward-looking statements” (collectively “forward-looking statements”) within the meaning of applicable securities legislation, including the United States Private Securities Litigation Reform Act of 1995. Forward-looking statements are frequently, but not always, identified by words such as “expects”, “continue”, “ongoing”, “anticipates”, “believes”, “intends”, “estimates”, “potential”, “possible”, and similar expressions, or statements that events, conditions, or results “will”, “may”, “could”, “would” or “should” occur or be achieved. All statements, other than statements of historical fact, included herein are forward-looking statements. These forward-looking statements include statements regarding the anticipated timing of the release of the schedule and budget for the BFS and market updates relating to same; timing of the completion of the BFS; the preparation of the BFS; planned activities at the site relating to the preparation of the BFS; the mineral estimates at Donlin Gold and the anticipated production levels at Donlin Gold In addition, any statement that refers to expectations, intentions, projections or other characterizations of future events or circumstances are forward-looking statements. Forward-looking statements contained in this media release are based on a number of material assumptions, including but not limited to the following, which could prove to be significantly incorrect: our ability to achieve production at Donlin Gold; the cost estimates and assumptions contained in the 2025 Technical Report and the 2025 Technical Report Summary; estimated metal pricing, metallurgy, mineability, marketability and operating and capital costs, together with other assumptions underlying our resource and reserve estimates; our expected ability to develop adequate infrastructure and that the cost of doing so will be reasonable; assumptions that all necessary permits and governmental approvals will be obtained and the timing of such approvals; assumptions made in the interpretation of drill results, the geology, grade and continuity of our mineral deposits; our expectations regarding demand for equipment, skilled labor and services needed for exploration and development of mineral properties; operating or regulatory risks. Forward-looking statements are necessarily based on several opinions, estimates and assumptions that management of NOVAGOLD considered appropriate and reasonable as of the date such statements are made, are subject to known and unknown risks, uncertainties, assumptions, and other factors that may cause the actual results, activity, performance, or achievements to be materially different from those expressed or implied by such forward-looking statements. Forward-looking statements are not historical facts but instead represent the expectations of NOVAGOLD management’s estimates and projections regarding future events or circumstances on the date the statements are made. Important factors that could cause actual results to differ materially from expectations include the need to obtain additional permits and governmental approvals; the timing and likelihood of obtaining and maintaining permits necessary to construct and operate; availability of financing in the debt and capital markets; uncertainties involved in the interpretation of drill results and geological tests and the estimation of reserves and resources; changes in mineral production performance, exploitation and exploration successes; changes in national and local government legislation, taxation, controls or regulations and/or changes in the administration of laws, policies and practices, expropriation or nationalization of property and political or economic developments in the United States or Canada; the need for continued cooperation between the owners of Donlin Gold LLC, with government agencies and Native groups; risks of construction and mining projects such as accidents, equipment breakdowns, bad weather, disease pandemics, non-compliance with environmental and permit requirements, unanticipated variation in geological structures, ore grades or recovery rates; unexpected cost increases, which could include significant increases in estimated capital and operating costs; fluctuations in metal prices and currency exchange rates; whether or when a positive construction decision will be made regarding the Donlin Gold project; and other risks and uncertainties disclosed in NOVAGOLD’s most recent report on Forms 10-K, particularly the “Risk Factors” sections of those reports and other documents filed by NOVAGOLD with applicable securities regulatory authorities from time to time. Copies of these filings may be obtained by visiting NOVAGOLD’s website at www.novagold.com, or the SEC’s website at www.sec.gov, or on SEDAR+ at www.sedarplus.ca. The forward-looking statements contained herein reflect the beliefs, opinions and projections of NOVAGOLD on the date the statements are made. NOVAGOLD assumes no obligation to update the forward-looking statements of beliefs, opinions, projections, or other factors, should they change, except as required by law.

                                       

1 Donlin Gold data as per the report titled “NI 43-101 Technical Report on the Donlin Gold project, Alaska, USA” with an effective date of November 30, 2025 (the “2025 Technical Report”) and the report titled “S-K 1300 Technical Report Summary on the Donlin Gold project, Alaska, USA” (the “2025 Technical Report Summary”), dated November 30, 2025. Donlin Gold possesses Measured Resources of approximately 9 Mt grading 2.67 g/t and Indicated Resources of approximately 551 Mt grading 2.21 g/t, each on a 100% basis and inclusive of Mineral Reserves, of which approximately 6 Mt of Measured Resources and approximately 330 Mt of Indicated Resources inclusive of Reserves is currently attributable to NOVAGOLD through its 60% ownership interest in Donlin Gold LLC. Exclusive of Mineral Reserves, Donlin Gold possesses Measured Resources of approximately 1.4 Mt grading 1.18 g/t and Indicated Resources of approximately 175 Mt grading 1.32 g/t, of which approximately 0.9 Mt of Measured Resources and approximately 105 Mt of Indicated Resources exclusive of Mineral Reserves is currently attributable to NOVAGOLD. Donlin Gold possesses Proven Reserves of approximately 9 Mt grading 2.29 g/t and Probable Reserves of approximately 495 Mt grading 2.02 g/t, each on a 100% basis, of which approximately 6 Mt of Proven Reserves and approximately 297 Mt of Probable Reserves is attributable to NOVAGOLD. Mineral Reserve and Resources have been estimated in accordance with NI 43-101 and S-K 1300.
2 Anticipated average annual gold production during full life of mine if put into production as contemplated in the 2025 Technical Report and the 2025 Technical Report Summary.


FAQ

Who is leading the Donlin Gold Bankable Feasibility Study for NOVAGOLD (NG)?

Fluor Corporation is leading the Donlin Gold Bankable Feasibility Study as the engineering firm. According to the company, Fluor commenced work and will integrate Specialist Contractors, advance cost optimization, and deliver the integrated engineering, cost, and schedule framework.

When is the Donlin Gold BFS expected to be completed and what is the timeline for NG?

The Bankable Feasibility Study is expected to be completed in 2027. According to the company, a more detailed schedule and budget will be released in coming months after full-scope alignment with Specialist Contractors.

What scope will Fluor handle for the Donlin Gold project (NG)?

Fluor will integrate major work packages and coordinate Specialist Contractors on key infrastructure and process units. According to the company, this includes power plant, natural gas pipeline, pressure oxidation circuit, and oxygen plant integration.

How does Fluor’s selection affect Donlin Gold’s readiness for financing and development (NG)?

Selecting Fluor advances engineering and execution readiness to support financing and development. According to the company, Fluor will focus on cost accuracy, constructability, and an investment-grade integrated study to position the project for financing.

What project activities are ongoing while the Donlin Gold BFS progresses for NOVAGOLD (NG)?

Site activities continue, including geotechnical drilling and materials assessments along transport routes. According to the company, these workstreams support detailed design and the integrated BFS while owner team recruitment proceeds.

Has NOVAGOLD (NG) released the BFS budget and specialist contractor awards yet?