STOCK TITAN

Osisko Development Announces Resumption of Planned Site Activities at the Cariboo Gold Project

Rhea-AI Impact
(Moderate)
Rhea-AI Sentiment
(Neutral)
Tags

Osisko Development (NYSE: ODV) announced the resumption of planned site activities at the Cariboo Gold Project on March 2, 2026, following a temporary suspension after an isolated surface incident on January 22, 2026.

More than 250 personnel are onsite supporting pre-construction, early works and exploration. Key progress: 2.1 km of underground development completed, water treatment plant commissioning nearing completion, six surface drill rigs and three underground rigs operating, and the site camp expanded to 266 rooms.

Loading...
Loading translation...

Positive

  • 250+ personnel onsite supporting normal operating levels
  • 2.1 km of underground development completed from Cow Portal
  • Water treatment plant upgrades near full commissioning
  • Camp expanded to 266 rooms for peak construction manpower

Negative

  • Underground development below plan due to challenging ground conditions in the Lowhee fault
  • Enhanced ground support required, slowing ramp advance and increasing development risk
  • Approximately 5,000 meters of surface drilling complete with assays pending

Key Figures

Onsite personnel: over 250 personnel Underground development: 2.1 km completed Infill program length: 13 km program +5 more
8 metrics
Onsite personnel over 250 personnel Current operating level during Cariboo site activity resumption
Underground development 2.1 km completed Development from Cow Portal into Lowhee Zone and toward Cow Mountain Zone
Infill program length 13 km program Ongoing underground Lowhee infill drilling on 1260 level
Infill remaining 1.6 km remaining Final drill fan under the 13-km underground program
Underground drill rigs 3 drill rigs Current underground drilling at Cariboo
Surface drill rigs 6 drill rigs Two surface exploration programs at Cariboo and Proserpine
Deep exploration depth 1,000 meters Target depth below current extent of Cariboo Gold deposit
Camp capacity 266 rooms Upgraded site camp aligned with peak construction manpower

Market Reality Check

Price: $4.76 Vol: Volume 2,617,153 vs 20-da...
normal vol
$4.76 Last Close
Volume Volume 2,617,153 vs 20-day average 3,035,869 (about 14% below typical activity). normal
Technical Price $4.76 is trading above the 200-day MA at $3.01 and sits near the 52-week high of $4.795.

Peers on Argus

ODV gained 3.7%. Among key gold peers, IAUX rose 4% and GAU rose 2.92%, while CM...

ODV gained 3.7%. Among key gold peers, IAUX rose 4% and GAU rose 2.92%, while CMCL fell 2.37%, GROY slipped 0.43%, and DC was flat, indicating mixed sector action and a stock-specific tilt to ODV’s move.

Historical Context

5 past events · Latest: Feb 11 (Positive)
Pattern 5 events
Date Event Sentiment Move Catalyst
Feb 11 Drilling results update Positive -6.2% High-grade Lowhee infill drilling results and program timing update at Cariboo.
Feb 09 Project management deal Positive +8.0% Awarding project and construction management contract for Cariboo development.
Feb 03 Equity financing completion Negative +4.1% Completion of US$143.8M bought-deal share offering including over-allotment.
Feb 02 Executive appointment Positive +4.1% Appointment of VP, Permitting and Compliance to bolster regulatory capabilities.
Jan 27 Asset sale Neutral +1.3% Sale of San Antonio Gold Project for Axo shares and contingent payments.
Pattern Detected

Recent news often ties to Cariboo development; market reactions have been mixed, with some positive operational updates selling off while financing and project advancement news have sometimes attracted buying.

Recent Company History

Over the last few months, Osisko Development has focused on advancing the Cariboo Gold Project through financing, drilling, and project execution. A February 3 offering raised US$143.8M to fund infill and exploration. Earlier, the company sold the San Antonio project for 15,325,841 Axo shares and contingent payments, concentrating on Cariboo. Management strengthened permitting capabilities and awarded a project and construction management contract. The current announcement about resuming site activities and development progress at Cariboo follows this steady build-out of funding, personnel, and infrastructure.

Regulatory & Risk Context

Active S-3 Shelf · US$126.8 million
Shelf Active
Active S-3 Shelf Registration 2025-12-10
US$126.8 million registered capacity

An effective Form F-3 shelf allows resale of up to 104,751,318 common shares from an August 2025 private placement. Osisko would not receive proceeds from resales but could receive up to US$126.8 million if related warrants are exercised, which it expects to use for the Cariboo Gold Project. This structure may contribute to share supply overhang as registered holders gain liquidity.

Market Pulse Summary

This announcement describes the structured resumption of site activities at Cariboo following a temp...
Analysis

This announcement describes the structured resumption of site activities at Cariboo following a temporary suspension, with over 250 personnel onsite and 2.1 km of underground development completed. Infill and surface drilling are progressing, and a 266-room camp and key surface infrastructure are in place. In context of recent financings and project contracts, investors may focus on safety performance, development rates beyond the Lowhee fault, and future updates on drilling results and construction milestones at the Cariboo Gold Project.

Key Terms

infill drilling, exploration drilling, qualified person, national instrument 43-101
4 terms
infill drilling technical
"Lowhee infill program: Infill drilling has resumed and is underway, with approximately..."
Infill drilling is the targeted drilling of additional holes inside an area where mineral deposits have already been found, done to fill gaps in knowledge about how much rock or metal is really there and how continuous it is. For investors this matters because better, denser data reduces uncertainty about a project’s size and value, similar to taking more detailed photos of a landscape to judge how much land you actually own and how usable it is.
exploration drilling technical
"supporting the advancement of pre-construction, early works and exploration drilling..."
Exploration drilling is the process of drilling holes into the ground to find and sample underground resources such as minerals, oil or natural gas, much like taking test cores to see what’s below the surface. Investors care because the results reveal whether a deposit exists, how large and rich it might be, and therefore whether a project is worth developing — outcomes that directly affect a company’s future revenue potential, costs and share value.
qualified person regulatory
"Scott Smith, P. Geo., Vice President, Exploration of Osisko Development, a "qualified..."
A qualified person is someone with specialized knowledge, experience, and training in a particular field, allowing them to accurately assess and verify information or work. Their expertise helps ensure that reports, evaluations, or decisions are trustworthy and meet required standards. For investors, a qualified person provides confidence that the information they rely on is credible and properly validated.
national instrument 43-101 regulatory
"within the meaning of National Instrument 43-101 – Standards of Disclosure for..."
National Instrument 43-101 is a set of rules and guidelines that govern how mineral exploration and mining companies must report information about their projects. It ensures that the details shared with investors are accurate, consistent, and reliable—similar to how a detailed, verified blueprint ensures a building’s safety. This helps investors make informed decisions based on trustworthy information about a company's mineral resources.

AI-generated analysis. Not financial advice.

MONTREAL, March 02, 2026 (GLOBE NEWSWIRE) -- Osisko Development Corp. (NYSE: ODV, TSXV: ODV) ("Osisko Development" or the "Company") announces the resumption of planned site activities at its Cariboo Gold Project (the "Project") in British Columbia, following a temporary suspension related to an isolated tragic incident that occurred at surface on January 22, 2026. A phased gradual reopening plan of surface and underground activities was successfully implemented over the last several weeks, while ensuring the health and safety of all employees and contractors, in coordination with and approval from the relevant regulatory authorities.

"I want to thank the entire site team for their professionalism and unwavering commitment throughout this difficult period. As we move forward, the health, safety and wellbeing of everyone who works at Osisko Development remains our highest priority," said Sean Roosen, Chairman and CEO.

There are currently over 250 personnel onsite, reflecting normal operating levels for the current phase of work, supporting the advancement of pre-construction, early works and exploration drilling activities, including:

  • Water treatment plant: Upgrades to the Bonanza Ledge water treatment plant are in the final stages of commissioning and the facility is anticipated to be fully operational in the coming weeks.
  • Underground development: To date, approximately 2.1 kilometres ("km") of underground development has been completed from the existing Cow Portal into the Lowhee Zone, and along the main access ramp, through the Lowhee fault, towards the Cow Mountain Zone. Development progress has been below plan while encountering challenging ground conditions in and around the Lowhee fault, requiring enhanced ground support. Development rates are expected to improve as the ramp advances beyond this zone.
  • Lowhee infill program: Infill drilling has resumed and is underway, with approximately 1.6 km remaining in the final drill fan under the ongoing 13-km underground program on the 1260 level. Additional exploration and infill drilling is also ongoing on the 1290 level. A total of three drill rigs are currently operating underground.
  • Surface exploration: A total of six drill rigs are currently operating on two exploration programs. Three drill rigs are targeting exploration below the current extent of the Cariboo Gold deposit down to a depth of 1,000 meters. Approximately 5,000 meters of drilling have been completed to date, with assays pending. A second surface exploration program on the adjacent Proserpine regional target has also commenced with three drill rigs, and approximately 500 meters completed to date.
  • Surface infrastructure: Construction of the waste rock storage facility, the sediment control pond, early works in the mine site complex area and other critical infrastructure continues.
  • Camp upgrade: The upgrade and expansion of the site camp to 266 rooms is complete and is expected to provide accommodation capacity aligned with peak construction manpower requirements for the Project.

Qualified Persons

The scientific and technical information contained in this news release has been reviewed, verified and approved by Scott Smith, P. Geo., Vice President, Exploration of Osisko Development, a "qualified person" within the meaning of National Instrument 43-101 – Standards of Disclosure for Mineral Projects.

Figure 1: Waste rock storage facility excavation continues.

Waste rock storage facility excavation continues.

Figure 2: Sediment control pond spillway concrete work & dam raise.

Sediment control pond spillway concrete work & dam raise.

Figure 3: Water treatment plant commissioning underway.

Water treatment plant commissioning underway.

Figure 4: Project site camp expansion complete.

Project site camp expansion complete.

ABOUT OSISKO DEVELOPMENT CORP.

Osisko Development Corp. is a continental North American gold development company focused on past producing mining camps with district scale potential. The Company's objective is to become an intermediate gold producer through the development of its flagship, fully permitted, 100%-owned Cariboo Gold Project, located in central British Columbia, Canada. Its project pipeline is complemented by the Tintic Project located in the historic East Tintic mining district in Utah, U.S.A., a brownfield property with significant exploration potential, extensive historical mining data, and access to established infrastructure. Osisko Development is focused on developing long-life mining assets in mining-friendly jurisdictions while maintaining a disciplined approach to capital allocation, development risk management, and mineral inventory growth.

For further information, contact:

Sean RoosenPhilip Rabenok
Chairman and CEOVice President, Investor Relations
Email: sroosen@osiskodev.comEmail: prabenok@osiskodev.com
Tel: +1 (514) 940-0685Tel: +1 (437) 423-3644
  

CAUTION REGARDING FORWARD-LOOKING STATEMENTS

This news release contains "forward-looking information" (within the meaning of applicable Canadian securities laws) and "forward-looking statements" (within the meaning of the U.S. Private Securities Litigation Reform Act of 1995, as amended) (collectively, "forward-looking statements"). Such forward-looking statements are identified with words such as "may", "will", "would", "could", "anticipate", "believe", "expect", "plan", "intend", "potential", "estimate", "propose", "project", "outlook", "foresee", "objective", "strategy", variants of these words or the negative or comparable terminology, as well as terms usually used in the future and the conditional. Information contained in forward-looking statements is based upon certain material assumptions that were applied in drawing a conclusion or making a forecast or projection, including the assumptions, qualifications, limitations or statements pertaining to: the full resumption and continuation of planned site activities at the Cariboo Gold Project; the anticipated timing for the Bonanza Ledge water treatment plant to become fully operational; expectations regarding the improvement of underground development rates as the ramp advances beyond the Lowhee fault zone; the completion of the remaining infill drilling program on the 1260 level and ongoing exploration and infill drilling activities; the continuation of surface exploration drilling activities and receipt of assay results; the continuation of surface infrastructure construction, including the waste rock storage facility, sediment control pond, mine site complex early works and other critical infrastructure; expectations that the expanded camp will provide accommodation capacity aligned with peak construction manpower requirements; the ability to develop the Cariboo Gold Project; and the timing and ability to complete contemplated work. Such forward-looking statements are based on a number of risks, uncertainties and assumptions which may cause actual results or other expectations to differ materially from those anticipated and which may prove to be incorrect. These assumptions include, but are not limited to: the absence of further work stoppages or suspensions at the Project; favourable regulatory conditions and approvals; the ability to maintain adequate personnel and contractor levels; the absence of unforeseen ground conditions or other geological challenges; the availability of necessary equipment, supplies and infrastructure; and general economic and market conditions. Actual results could differ materially due to a number of factors, including, without limitation: risks related to the exploration, development and operation of the Cariboo Gold Project; health, safety and security incidents; unforeseen ground conditions, including in and around the Lowhee fault zone; delays in commissioning infrastructure, including the water treatment plant; regulatory delays or changes in regulatory framework and applicable laws; labour shortages or disputes; general economic and market conditions and business conditions in the mining industry; fluctuations in commodity and currency exchange rates; changes in regulatory framework and applicable laws, as well as those risks and factors disclosed in the Company's most recent annual information form, financial statements and management's discussion and analysis as well as other public filings on SEDAR+ (www.sedarplus.ca) and on EDGAR (www.sec.gov). Although the Company believes the expectations conveyed by the forward-looking statements are reasonable based on information available as of the date hereof, no assurances can be given as to future results, levels of activity and achievements. The Company disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results or otherwise, except as required by law. Forward-looking statements are not guarantees of performance and there can be no assurance that these forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release. No stock exchange, securities commission or other regulatory authority has approved or disapproved the information contained herein.

Photos accompanying this announcement are available at:

https://www.globenewswire.com/NewsRoom/AttachmentNg/8eff1504-09b1-40bc-8f72-9e0e78c13ea9

https://www.globenewswire.com/NewsRoom/AttachmentNg/4b9f965a-fcd2-4313-8564-a6e6bdb9a295

https://www.globenewswire.com/NewsRoom/AttachmentNg/299b8b71-1b27-4984-aac1-094605e4dd4b

https://www.globenewswire.com/NewsRoom/AttachmentNg/e6ce32c4-5082-448e-b930-100b25f7c2a7


FAQ

What did Osisko Development (ODV) announce about operations at Cariboo on March 2, 2026?

The company said it has resumed planned surface and underground activities at Cariboo, with phased reopening and regulatory approvals. According to the company, over 250 personnel are onsite supporting pre-construction, early works and exploration drilling programs.

How much underground development has ODV completed at the Cariboo Gold Project?

Osisko Development reported approximately 2.1 km of underground development completed from the Cow Portal into the Lowhee Zone. According to the company, progress slowed near the Lowhee fault and enhanced ground support was required.

What is the status of drilling and assays for ODV's Cariboo Project as of March 2026?

Surface drilling has completed roughly 5,000 meters with assays pending, while three underground rigs continue infill drilling. According to the company, a second surface program at Proserpine has completed about 500 meters to date.

When will the water treatment plant at Cariboo be operational for ODV?

Upgrades to the Bonanza Ledge water treatment plant are in final commissioning and are expected to be fully operational in the coming weeks. According to the company, commissioning is in its final stages.

What caused delays in ODV's underground development at Cariboo and what is the impact?

Development rates were below plan after encountering challenging ground conditions in and around the Lowhee fault, requiring enhanced ground support. According to the company, rates are expected to improve once ramp advances beyond this zone.

How has ODV adjusted site infrastructure and accommodation at Cariboo for construction?

The company completed a site camp upgrade to 266 rooms to align with peak construction manpower needs and continues waste rock facility and sediment pond construction. According to the company, infrastructure work remains ongoing.
Osisko Development Corp

NYSE:ODV

ODV Rankings

ODV Latest News

ODV Latest SEC Filings

ODV Stock Data

1.37B
173.64M
Gold
Basic Materials
Link
Canada
Montreal