Sigma Lithium Reports 3Q 26 Results: Resilient Profitability and Cash Flow: 32% Net Revenue Margin, Strengthened Balance Sheet

(Very High)

Sentiment and the balance of points

Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

Sigma Lithium (SGML) reported third-quarter 2026 gross revenue of US$22.3 million, reflecting lower sales volumes during a temporary partial operational suspension. Revenue compared with US$51.0 million in the second quarter. Operating cash flow rose to US$24.2 million from US$1.6 million a year earlier, while adjusted EBITDA was negative US$6.7 million and operating loss was US$16.8 million.

Nine-month gross revenue rose 20% to US$115.4 million. Sigma priced US$125 million of convertible bonds, expected to close around November 16, 2026, to refinance liabilities including the Synergy prepayment. Pro forma short-term debt falls 85% to US$19 million, while net debt rises to US$145 million from US$105 million. Operations fully resumed October 5. The company reaffirmed its 330,000-tonne 2027 production target and plans capacity of 830,000 tonnes annually by 2028.

Loading...
Loading translation...
26 points · 1 major

How this balance works

Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.

It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.

Rhea-AI Sentiment measures something else, the tone of the wording.

1 major · 10 points

Hollow bars mark forward-looking points. How the balance works

Positive

  • Major point. Forward-looking: it has not happened yet and may not happen.US$125 million convertible bond pricing provides planned refinancing, including full repayment of the Synergy export prepayment. 22% of market cap
  • Moderate pointOperating cash flow reached US$24.2 million in 3Q 26, versus US$1.6 million in 3Q 25.
  • Moderate pointNine-month gross revenue increased 20% year over year to US$115.4 million.
  • Moderate pointNine-month operating cash flow reached US$51.3 million, versus negative US$6.6 million in 9M 25.
  • Moderate pointNine-month net revenue margin reached 56.6%, compared with 5.6% in 9M 25.
  • Moderate pointNine-month adjusted EBITDA was US$35.7 million, with a 32% margin.
  • Moderate pointOperations fully resumed October 5, 2026; high-grade concentrate production reached 11,000 tonnes through November 10.
  • Moderate point. Forward-looking: it has not happened yet and may not happen.FY27 estimated cash generation is US$125 million–US$290 million at US$1,000/t–US$1,500/t realized prices, before specified deductions.
  • Moderate point. Forward-looking: it has not happened yet and may not happen.Plant 2 construction is planned to resume in 2027, adding 250,000 tonnes annually to reach 580,000 tonnes.
  • Moderate pointBRL 492 million committed BNDES funding fully covers Plant 2's BRL 492 million budget.
  • Moderate point. Forward-looking: it has not happened yet and may not happen.Plant 3 completion is planned by 2028, adding 250,000 tonnes annually to reach 830,000 tonnes.
15 minor points
  • Minor pointNine-month gross profit reached US$62.6 million; operating income was US$4.5 million.
  • Minor point3Q 26 cost of sales decreased 58% to US$9.3 million, producing US$4.3 million gross profit.
  • Minor point3Q 26 net revenue margin remained at 32%.
  • Minor pointPro forma 3Q 26 all-in sustaining cost fell 4% from 2Q 26 to US$642/t.
  • Minor point. Forward-looking: it has not happened yet and may not happen.Pro forma short-term debt decreases 85% to US$19 million following the bonds and Synergy repayment.
  • Minor point. Forward-looking: it has not happened yet and may not happen.Potential additional liquidity includes approximately US$10 million in high-grade sales and approximately US$20 million in unsold fines.
  • Minor point. Forward-looking: it has not happened yet and may not happen.Remaining offtake installments total US$32 million under the previously announced US$96 million agreement.
  • Minor point. Forward-looking: it has not happened yet and may not happen.4Q sale inventory includes 15,000 high-grade-equivalent tonnes of fines; 6,000 intermediate tonnes are expected to convert and sell.
  • Minor point. Forward-looking: it has not happened yet and may not happen.South Pit redesign provides access to approximately 200,000 tonnes of concentrate, versus approximately 100,800 tonnes previously.
  • Minor pointMining fleet upgrades increase excavators from 75 to 105 tonnes and trucks from 60 to 75 tonnes.
  • Minor pointSafety performance exceeded 1,190 consecutive days without lost-time injury; year-to-date recordable injury frequency was zero through November 10.
  • Minor point. Forward-looking: it has not happened yet and may not happen.2027 production guidance remains 330,000 tonnes, assuming only Plant 1 operates.
  • Minor point. Forward-looking: it has not happened yet and may not happen.Estimated 2027 quarterly production is 68,000 tonnes of high-grade concentrate plus 15,000 tonnes from tailings reprocessing.
  • Minor point. Forward-looking: it has not happened yet and may not happen.Cost guidance remains US$668/t for 2026 and US$620/t for FY27 estimated all-in sustaining costs.
  • Minor point. Forward-looking: it has not happened yet and may not happen.Mine 2 is planned to support expansion, with approximately 30 million tonnes of resources and no external infrastructure capex.

Negative

  • Major point. Forward-looking: it has not happened yet and may not happen.Convertible bonds add US$125 million of convertible debt, with potential shareholder dilution upon conversion. 22% of market cap
  • Moderate point3Q 26 gross revenue fell to US$22.3 million from US$51.0 million in 2Q 26 amid lower volumes.
  • Moderate point3Q 26 adjusted EBITDA was negative US$6.7 million; operating loss was US$16.8 million.
  • Moderate point. Forward-looking: it has not happened yet and may not happen.Bond closing remains expected on or about November 16, 2026; the refinancing is not yet completed.
  • Moderate point. Forward-looking: it has not happened yet and may not happen.Pro forma net debt rises to US$145 million from US$105 million at September 30, 2026.
5 minor points
  • Minor point. Forward-looking: it has not happened yet and may not happen.Bond repayment rights allow holders to require repayment around November 2029, before November 2031 maturity.
  • Minor pointPro forma short-term obligations include US$14.4 million of export prepayment finance and US$4.3 million of BDMG debt.
  • Minor pointPlant 2 expansion loan carries 7.53% BRL interest, a 16-year maturity and an 18-month amortization grace period.
  • Minor point. Forward-looking: it has not happened yet and may not happen.Plant 2 construction restart follows completion of the mining upgrade; expansion also depends on opening Mine 2.
  • Minor pointMining agency improvement notice requires reshaping a slope in the depleted North Pit; it does not stop operations.

News Explained

At September 30, the company reported US$10 million cash; additional listed liquidity sources remain potential, including sales, inventory and offtake installments.

The priced convertible bonds are awaiting expected closing around November 16, 2026; holders may require repayment around November 2029, before the bonds' stated November 2031 due date.

At September 30, 2026, cash was US$10 million, with another US$2 million in receivables from sold lithium materials expected to be collected after quarter-end. The company lists as potential post-period liquidity approximately US$10 million from high-grade sales, US$20 million in unsold lithium-fines inventory, and US$32 million in remaining installments under a previously announced offtake agreement.

Key Figures

3Q net revenue margin: 32% 3Q gross revenues: US$22.3 million 3Q operating cash flow: US$24.2 million +5 more
3Q net revenue margin
32%
Third quarter 2026
3Q gross revenues
US$22.3 million
Third quarter 2026; lower volumes sold
3Q operating cash flow
US$24.2 million
Third quarter 2026
3Q Adjusted EBITDA
negative US$6.7 million
Third quarter 2026
9M gross revenues
US$115.4 million
Nine months ended September 30, 2026; up 20% from 9M 25
9M Adjusted EBITDA
US$35.7 million
Nine months ended September 30, 2026
Convertible bonds
US$125 million
5-year bonds due November 2031; closing expected on or about November 16, 2026
Pro forma short-term debt
85% reduction to US$19 million
After the convertible bonds and full repayment of Synergy

Historical Context

1 past event · Latest: Nov 02
1 event
  1. Nov 02

    Convertible bond pricing

    24h Move
    +6.2%

    Priced the US$125 million convertible bond to refinance Synergy debt, with maturity in 2031.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

Key Terms

convertible bonds, aisc, cif, trifr
4 terms
convertible bonds financial
"priced US$125 million of 5-year convertible bonds due November 2031"
A convertible bond is a loan a company issues that pays regular interest and can be exchanged for a fixed number of the company’s shares under specified terms. It matters to investors because it combines the steady income and lower downside risk of a bond with the upside potential of owning stock—like holding a ticket that can be cashed for equity if the share price rises—affecting returns, risk, and shareholder dilution.
aisc financial
"Total Cash Costs: US$642/t (AISC - All-In Sustaining Cost)"
All-in Sustaining Cost (AISC) is a comprehensive measure of how much it costs a mining company to produce one unit of metal when ongoing operating expenses, long-term maintenance and sustaining capital, and share of corporate overhead are included. Investors use AISC to compare profitability and cash generation across producers—think of it as the full household cost to keep a business running divided by how many items it makes, which helps assess margins and resilience to price swings.
cif financial
"Plant gate costs at US$424/t and CIF costs at US$518/t"
CIF stands for “Cost, Insurance and Freight,” a common shipping term that says the seller pays the cost to move goods to a named port and buys insurance for the shipment while in transit. For investors, CIF matters because it affects who bears transport costs, insurance expense and some delivery risks — which changes a seller’s reported margins, cash flow and potential liability if goods are lost or delayed. Think of it like a seller paying for and insuring a courier to deliver a large package to a buyer’s local post office.
trifr technical
"a year-to-date Total Recordable Injury Frequency Rate (TRIFR) of zero"
TRIFR stands for Total Recordable Injury Frequency Rate, a safety metric that counts work-related injuries that need medical treatment, restricted duties, or lost time, scaled per a set number of hours worked (commonly per million hours). It matters to investors because it acts like a company’s safety scorecard—higher rates signal operational and regulatory risks, potential costs, and management quality, while lower rates suggest safer, more reliably run operations.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

FINANCIAL HIGHLIGHTS

  • Strengthened balance sheet through a pivotal 5-year, US$125M convertible bond, fully repaying the Synergy export prepayment and reducing pro forma short-term debt by 85% to US$19M.
    • Transformed its balance sheet lengthening its debt profile, lowering leverage ratios and additional deleveraging potential upon conversion of the debt.
  • Sigma Lithium delivered resilient profitability and strong cash generation in 3Q 26, building on growth for the nine months ended September 30, 2026 (9M 26):
    • 3Q 26 net revenue margin remained robust at 32%; 9M 26 net revenue margin of 57% and Adj. EBITDA margin of 32%.
    • 3Q 26 gross revenues of US$22M reflected lower volumes sold due to the temporary partial suspension of operations during the quarter; 9M 26 gross revenues of US$115M, up 20% from 9M 25.
    • Strong operating cash flow of US$24M in 3Q 26 (up from US$2M in 3Q 25) and US$51M in 9M 26 (up from negative US$7M in 9M 25).
  • Maintained cost leadership, with Low All-In Sustaining Costs:
    • Plant gate: US$424/t (9M 26: US$418/t)
    • CIF: US$518/t (9M 26: US$505/t), reflecting the move to CIF sales terms
    • AISC: US$642/t All-In Sustaining Costs

OPERATIONAL HIGHLIGHTS

  • Production growth strategy for 2027-2028 remains on track:
    • 330,000t production for FY27E from Cleantech Industrial Plant 1
  • Landmark victories for ESG credentials: TAC Agreement signed with the State of Minas Gerais and "too big to stop" classification awarded by the Federal Court of Appeals.
    • Operations fully resumed on October 5, 2026, with 11,000t of high-grade lithium oxide concentrate produced in early 4Q 26 through November 10, plus 21,000t of high-grade equivalent inventory available for sale in 4Q 26 and 7,000t of high-grade produced in 3Q 26.
  • Plans to increase installed industrial capacity by building two additional plants:
    • 580,000tpy with Cleantech Industrial Plant 2, construction resuming in 2027 (fully funded by BNDES)
    • 830,000tpy with Cleantech Industrial Plant 3 by 2028
  • 100% Circularity Achieved: Cleantech Industrial Plant 1's reprocessing circuit enables the recovery and commercialization of lithium fines and intermediate products, supporting cash generation during the mining ramp-up.

Conference Call Information

The Company will hold a conference call to discuss its financial results for the third quarter of 2026 at 7:00 a.m. EST on Friday, November 13, 2026. Register for the call at https://ir.sigmalithiumcorp.com/events.

Toronto, Ontario--(Newsfile Corp. - November 13, 2026) - Sigma Lithium Corporation (NASDAQ: SGML) (ASX: SAU) (TSXV: SGML) (BVMF: S2GM34) ("Sigma Lithium" or the "Company"), the largest industrial-mineral producer of lithium oxide concentrate in the Americas¹ and dedicated to industrializing lithium materials to supply global producers of batteries for energy security in a responsible manner, announces the Company's results for the three months ended September 30, 2026 and provides an update on recent developments.

ROBUST 3Q 26 MARGINS AND CASH GENERATION; 9M 26 REVENUES UP 20%

In 3Q 26, Sigma Lithium maintained a robust net revenue margin of 32% and generated operating cash flow of US$24.2 million, up from US$1.6 million in 3Q 25, demonstrating the resilience of its low-cost business model. Gross revenues were US$22.3 million, compared to US$51.0 million in 2Q 26, reflecting lower volumes sold during the quarter, and the average realized price was US$1,485/t. Cost of sales decreased by 58% to US$9.3 million, resulting in a gross profit of US$4.3 million. Adjusted EBITDA for the quarter was negative US$6.7 million and the operating loss was US$16.8 million.

Year to date, Sigma Lithium's results demonstrate the growth delivered across the first three quarters of 2026. For the nine months ended September 30, 2026 (9M 26), gross revenues reached US$115.4 million, up 20% from 9M 25, and net revenue margin was 56.6%, a tenfold improvement from 5.6% in 9M 25. Gross profit reached US$62.6 million, Adjusted EBITDA was US$35.7 million (a 32% margin) and operating income was US$4.5 million. Operating cash flow was US$51.3 million in 9M 26, a turnaround from negative US$6.6 million in 9M 25.

COST LEADERSHIP CREATES RESILIENCE TO LITHIUM PRICES

Sigma Lithium remained a cost leader in lithium oxide concentrate, while continuing the planned upgrade of its mining fleet. Unit costs in 3Q 26 were as follows:

  • Plant gate costs at US$424/t and CIF costs at US$518/t (9M 26: US$505/t), reflecting the move from FCA to CIF sales terms.
  • Total Cash Costs: US$642/t (AISC - All-In Sustaining Cost), down 4% from US$668/t in 2Q 26. The 3Q 26 AISC is presented on a pro forma basis, spreading 3Q 26 SG&A over a volume of 60,000 tonnes for the quarter, with all other components as reported.

STRENGTHENED BALANCE SHEET: PIVOTAL 5-YEAR, US$125 MILLION CONVERTIBLE BOND

On November 2, 2026, Sigma Lithium priced US$125 million of 5-year convertible bonds due November 2031, with closing expected on or about November 16, 2026. Holders may require repayment around November 2029. The convertible bonds extend the Company's debt maturity profile by refinancing its current liabilities, including the full repayment of the export prepayment agreement with Synergy (US$108.5 million, or US$97 million net of US$11 million cash held as collateral).

Pro forma for the convertible bonds and the full repayment of Synergy, short-term debt decreased by 85% to US$19 million, consisting of US$14.4 million of export prepayment trade finance and US$4.3 million of current BDMG (Development Bank of Minas Gerais) debt. As of September 30, 2026, net debt was US$105 million, representing 1.5x the 9M 26 annualized operating cash flow of US$68 million. Pro forma for the convertible bonds, net debt stands at US$145 million. In 4Q 26, Sigma Lithium had extended the maturity of its export prepayment agreement with Synergy, representing approximately 80% of total debt as of October 2026, to June 2027.

Sigma Lithium's cash position stood at US$10 million as of September 30, 2026, with a further US$2 million in receivables from lithium materials sold expected to be collected after quarter-end. Post period-end potential additional sources of liquidity include high-grade sales of approximately US$10 million, unsold inventory of lithium fines of approximately US$20 million and the remaining US$32 million of installments under the previously announced US$96 million offtake agreement.

STRONG OPERATIONAL MOMENTUM IN 4Q 26

During 3Q 26, Sigma Lithium successfully resumed operations twice, demonstrating its operational capacity to efficiently mobilize 1,700 people and equipment, with operations fully resuming on October 5, 2026.

In 4Q 26, Sigma Lithium has already produced 11,000 tonnes of high-grade lithium oxide concentrate as of November 10, 2026. In addition, the Company holds an inventory of 15,000 tonnes of high-purity lithium fines (in high-grade equivalent tonnes) available for sale in 4Q 26, as well as 6,000 tonnes of intermediate high-grade products expected to be converted into high-grade lithium oxide concentrate and sold in 4Q 26. Production in 3Q 26 totaled 7,300 tonnes, bringing 9M 26 production to 66,300 tonnes.

Sigma Lithium is focused on increasing volumes during 4Q 26. The new pit shell design for the South Pit of Mine 1 provides access to approximately 200,000 tonnes of lithium oxide concentrate (1.1 million tonnes of ore at 1.4% Li2O), compared to approximately 100,800 tonnes (0.6 million tonnes of ore) under the previous pit shell, an 83% increase in ore. The Company continues the second stage of deployment of larger mining equipment, upgrading excavators from 75 tonnes to 105 tonnes (+40%) and trucks from 60 tonnes to 75 tonnes (+25%), supported by its commercial partnership with SANY China, which decreased lead times for equipment availability.

Sigma Lithium continues to combine low costs with a top global safety record, with over 1,190 consecutive days without a lost time injury and a year-to-date Total Recordable Injury Frequency Rate (TRIFR) of zero, as of November 10, 2026.

LANDMARK VICTORIES FOR ESG CREDENTIALS: TAC AGREEMENT SIGNED AND "TOO BIG TO STOP" RULING

In August 2026, Sigma Lithium signed the TAC Agreement ("Termo de Ajuste de Conduta") with the State of Minas Gerais, a "no fault" resolution favorable to the Company of the matters raised by FEAM, the environmental regulator of Minas Gerais state. Under the TAC Agreement, the Company agreed to a settlement of US$1 million for the germination of mining rock piles and to fines of US$0.5 million.

In September 2026, the Federal Court of Appeals ruled favorably to Sigma Lithium in a lawsuit filed by the NGO Ngolo and awarded the Company the classification of "too big to stop", reflecting its significant economic impact in the state, supporting 19,000 jobs and 80,000 family members. A court-appointed expert will calculate distances and impacts; if an impact is quantified, the Company will execute mitigation actions mirroring those already delivered in other communities.

In addition, the National Mining Agency (ANM) issued an improvement notice requiring the reshaping of a slope in the depleted, non-operating North Pit. The notice does not represent a stoppage, and Sigma Lithium is complying with all requirements.

Brazil's rule of law, due legal process and dialogue with the State have upheld Sigma Lithium's licenses and operations. Sigma Lithium's expansion is estimated to benefit over 25,000 people in the Jequitinhonha Valley, including 585 direct jobs at its three main suppliers and approximately 6,435 indirect jobs created in the region.

ON TRACK FOR 330,000t PRODUCTION IN 2027; CAPACITY TO REACH 830,000t PER YEAR BY 2028

Sigma Lithium reaffirms its production guidance of 330,000 tonnes for the full year of 2027 assuming only Cleantech Industrial Plant 1 is operating.

Following the completion of the mining primarization ramp-up, the Company expects to resume its industrial production cadence in 2027, with estimated quarterly production of 68,000 tonnes of high-grade lithium oxide concentrate plus 15,000 tonnes from the reprocessing of tailings.

At current production capacity, Sigma Lithium is resilient to lithium price volatility. At realized lithium prices between US$1,000/t and US$1,500/t (SC6), Cleantech Industrial Plant 1 is expected to generate cash flow of US$125 million to US$290 million in FY27E (pre-tax, pre-interest, pre-growth capex and pre-working capital).

Sigma Lithium maintained its guidance for total cash costs (AISC) of US$668/t for 2026 and US$620/t for FY27E; year-to-date AISC of US$642/t demonstrates the Company is on track.

At the SC6 spot price of US$1,180/t as of November 11, 2026, the Company's CIF cash cost of US$518/t implies a margin of US$662/t, positioning Sigma Lithium as a cost leader in the hard-rock lithium CIF China cost curve.

Sigma Lithium remains committed to delivering strong growth. Following the finalization of its mining upgrade, the Company plans to resume construction of Cleantech Industrial Plant 2 in 2027, adding 250,000 tonnes of annual capacity to reach 580,000 tonnes per year (+76%). Cleantech Industrial Plant 2 is fully funded by a BRL 492 million long-term expansion loan committed by the Brazilian National Development Bank (BNDES), against a budgeted capex of BRL 492 million, with a 16-year maturity, an 18-month amortization grace period and an interest rate of 7.53% in BRL (an estimated 2.5% in USD-equivalent terms).

The Company also plans to complete a third industrial plant, Cleantech Industrial Plant 3, by 2028, adding another 250,000 tonnes of annual capacity and taking total capacity to 830,000 tonnes per year (+43%). The expansion will be supported by the opening of a second mine (Mine 2, with approximately 30 million tonnes of resources) and requires no external infrastructure capex, as the region already has the necessary roads, port access and power lines.

QUALIFIED PERSONS

The qualified person (QP) for the technical information contained herein is Mr. Alexandre Rodrigues Cabral, P. Eng., member of the Ordre des Ingénieurs du Québec (OIQ, membership number 105796), who is considered, by virtue of his education, experience and professional association, a Qualified Person under the terms of NI 43-101. Mr. Cabral is not considered an independent QP under NI 43-101 as he is a Sigma Lithium Director and Chair of the Company's Technical Committee. Mr. Alexandre Rodrigues Cabral has reviewed and approved the technical and scientific content of this release.

ABOUT SIGMA LITHIUM

Sigma Lithium Corporation (NASDAQ: SGML) (ASX: SAU) (TSXV: SGML) (BVMF: S2GM34) ("Sigma Lithium" or "the Company") is the largest industrial-mineral producer of lithium oxide concentrate in the Americas¹ and is dedicated to industrializing socially and environmentally sustainable lithium materials to supply global producers of batteries for energy security. The Company runs one of the world's largest lithium production sites—the fifth-largest industrial-mineral complex for lithium oxide concentrate—at its Grota do Cirilo operation in Brazil. Sigma Lithium currently has a nameplate capacity to industrialize 330,000 tonnes of lithium oxide concentrate on an annualized basis at its mine and state-of-the-art Cleantech Industrial Plant.

Sigma Lithium is at the forefront of environmental and social sustainability in the battery materials supply chain. Its Cleantech Industrial Plant combines nearly 100% water reuse, zero use of toxic chemicals, no tailings mud dams, and 100% renewable electricity. For more than three years, Sigma Lithium has recorded no lost-time accidents.

The Company plans to resume its Phase 2 expansion in 2027, which is designed to nearly double annual production capacity to 580,000 tonnes. It also plans a Phase 3 expansion to increase capacity further to 830,000 tonnes. For more information about Sigma Lithium, visit our website.

(1) USGS.

FOR INFORMATION PLEASE CONTACT

Mariana Bengtson, Investor Relations Manager
mariana.bengtson@sigmalithium.com.br
+55 11 9 2144 2750

Gabriel Chefaly, Investor Relations Manager
gabriel.chefaly@sigmalithium.com.br
+55 19 9 9848 2231

Jessica Fertig, Investor Relations Advisor and International Media Contact
jessica@taumedia.com.au
+61 408 855 855

Brazilian Media Contact
media@sigmalithium.com.br

PLEASE FOLLOW US ON SOCIAL MEDIA

LinkedIn: Sigma Lithium
Instagram: @sigmalithium
X: @SigmaLithium

ASX STATEMENT

This announcement has been authorized for release by Sigma Lithium's CEO.

FORWARD-LOOKING STATEMENTS

This news release includes certain "forward-looking information" under applicable Canadian and U.S. securities legislation, including but not limited to statements relating to timing and costs related to the general business and operational outlook of the Company, the environmental footprint of tailings and positive ecosystem impact relating thereto, donation and upcycling of tailings, timing and quantities relating to tailings and Green Lithium, achievements and projections relating to the Zero Tailings strategy, achievement of ramp-up volumes, production estimates and the operational status of the Grota do Cirilo Project, the completion, size, pricing and terms of the Offering and the use of proceeds therefrom, the expected Closing Date and the receipt of all required regulatory and stock exchange approvals, the Company's preliminary unaudited results for the third quarter ended September 30, 2026, expected sales of inventory in 4Q 26, the resumption and continuity of operations, including the status of the Company's operating and mining licenses and related court decisions, production guidance for the next 12 months and FY27E, AISC guidance, cash flow forecasts at various lithium prices, the second mine and the Phase 2 and Phase 3 expansion plans, lithium prices, and other forward-looking information. All statements that address future plans, activities, events, estimates, expectations, or developments that the Company believes, expects, or anticipates will or may occur are forward-looking information, including statements regarding the potential development of mineral resources and mineral reserves which may or may not occur. Forward-looking information contained herein is based on certain assumptions regarding, among other things: general economic and political conditions; the stable and supportive legislative, regulatory and community environment in Brazil; demand for lithium, including that such demand is supported by growth in the electric vehicle market; the Company's market position and future financial and operating performance; the Company's estimates of mineral resources and mineral reserves, including whether mineral resources will ever be developed into mineral reserves; and the Company's ability to operate its mineral projects including that the Company will not experience any materials or equipment shortages, any labor or service provider outages or delays or any technical issues. Although management believes that the assumptions and expectations reflected in the forward-looking information are reasonable, there can be no assurance that these assumptions and expectations will prove to be correct. Forward-looking information inherently involves and is subject to risks and uncertainties, including but not limited to that the market prices for lithium may not remain at current levels; and the market for electric vehicles and other large format batteries currently has limited market share and no assurances can be given for the rate at which this market will develop, if at all, which could affect the success of the Company and its ability to develop lithium operations. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking information. The Company disclaims any intention or obligation to update or revise any forward-looking information, whether because of new information, future events or otherwise, except as required by law. For more information on the risks, uncertainties and assumptions that could cause our actual results to differ from current expectations, please refer to the current annual information form of the Company and other public filings available under the Company's profile at www.sedarplus.com.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/323882

FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

How did Sigma Lithium perform in the third quarter of 2026?

Sigma Lithium reported US$22.3 million gross revenue, US$24.2 million operating cash flow and negative US$6.7 million adjusted EBITDA. Gross revenue compared with US$51.0 million in 2Q 26, reflecting lower sales volumes during a temporary partial suspension. The operating loss was US$16.8 million.

What are the terms and timing of Sigma Lithium's convertible bond refinancing?

Sigma Lithium priced US$125 million of five-year convertible bonds due November 2031, with closing expected on or about November 16, 2026. Holders may require repayment around November 2029. The planned refinancing includes full repayment of the Synergy export prepayment and reduces pro forma short-term debt by 85% to US$19 million.

How was Sigma Lithium's third-quarter 2026 all-in sustaining cost calculated?

The US$642/t all-in sustaining cost is presented on a pro forma basis, spreading third-quarter selling, general and administrative expenses over 60,000 tonnes. All other components are as reported. Plant-gate costs were US$424/t, while costs including insurance and freight were US$518/t.

What assumptions underpin Sigma Lithium's estimated 2027 cash generation?

Sigma Lithium expects Plant 1 to generate US$125 million to US$290 million in FY27 at realized lithium prices between US$1,000/t and US$1,500/t on an SC6 basis. The estimate is before taxes, interest, growth capital expenditure and working capital.

How much cash did Sigma Lithium have at September 30, 2026?

Sigma Lithium held US$10 million in cash at September 30, 2026. A further US$2 million in receivables from lithium materials already sold was expected to be collected after quarter-end.