STOCK TITAN

Silicon Metals Corp. Commences 2025 Field Work and Reports High Purity Results

Rhea-AI Impact
(Moderate)
Rhea-AI Sentiment
(Neutral)
Tags
Silicon Metals Corp has initiated 2025 fieldwork at its Ptarmigan Project near Prince George, BC, following successful Q4 2024 sampling results. The company completed a high-definition airborne LiDAR survey to create a 3D topographic model of the property's quartzite formations. Analysis of 225 samples by Bureau Veritas revealed impressive purity levels, with 48% of quartzite samples exceeding 99% SiO2 and 8% surpassing 99.9% SiO2. The average purity was 98.49% SiO2, with minimal impurities. The sampling program included rock grab, chip, and channel samples collected using rigorous procedures and analyzed at certified laboratories. The company aims to build on its 2024 success with an enhanced technical team and strategic plan for the Ptarmigan Project.
Loading...
Loading translation...

Positive

  • 48% of quartzite samples exceeded 99% SiO2 purity, demonstrating high-quality deposits
  • 8% of samples achieved exceptional purity levels above 99.9% SiO2
  • Average purity of 98.49% SiO2 indicates consistent quality across samples
  • Completion of high-definition LiDAR survey enables better modeling of quartzite formations

Negative

  • Grab samples may not represent true underlying mineralization
  • Some metal contamination from tools expected in sample analysis
  • Project still in early exploration phase with no resource estimates

News Market Reaction – SLCNF

-3.57%
1 alert
-3.57% News Effect

On the day this news was published, SLCNF declined 3.57%, reflecting a moderate negative market reaction.

Data tracked by StockTitan Argus on the day of publication.

Vancouver, British Columbia--(Newsfile Corp. - June 4, 2025) - SILICON METALS CORP. (CSE: SI) (FSE: X6U) (OTC Pink: SLCNF) ("Silicon Metals" or the "Company") is pleased to announce the start of fieldwork at its Ptarmigan Project (the "Project" or the "Property), located ~130 km from Prince George, BC, following promising Q4 2024 high-purity sampling results.

The Company recently completed a high-definition airborne LiDAR survey, conducted by McElhanney Ltd., to generate a 3D topographic model of the Property. This will support modeling of the high-purity quartzite formations, which appear as prominent northwest-southeast trending ridges.

In late 2024, 225 samples (184 quartzite and 41 country rock) were collected and analyzed by Bureau Veritas. Results showed:

  • 48% of quartzite samples exceeded 99% SiO₂

  • 8% exceeded 99.9% SiO₂

  • Average purity: 98.49% SiO₂

Main impurities included Al₂O₃ (0.84%), Fe₂O₃ (0.33%), K₂O (0.17%), and TiO₂ (0.10%). Samples were prepared using ceramic pulverisers and analyzed via XRF fusion to minimize contamination, though some metal traces from tools are expected. The reader is cautioned that grab samples are selected samples and may not represent true underlying mineralization.

COO Raymond Wladichuk, stated: "We're excited to build on 2024's success. With a stronger technical team and strategic plan, we're ready to advance the Ptarmigan Project."

Procedures

Rock grab, chip, and channel samples were collected from in-situ outcrops. Channel samples were cut using a handheld masonry saw with a diamond blade and were collected in 2 meter intervals for a total of 24 meters across two separate channel cuts. Chip samples were taken from an exposed bluff in a quarry and were collected in 5 meter intervals for a total of 30 contiguous meters. Samples were placed in poly ore bags with unique sample IDs and sealed with zip ties. Rock descriptions, sample location, and sample details were recorded for each sample. Samples were shipped to Bureau Veritas labs in Vancouver, BC, an independent certified laboratory, via Bandstra Transportation Systems; in-house chain of custody and sample security measures were implemented for all sample shipments. Samples were crushed until 70% passed through 10 mesh and a further 250 grams was pulverized (PRP70-250). Pulverized material was analyzed via X-ray fluorescence on a fused disc with Si02 detection limits of 0.01%

Qualified Persons

Jeremy Hanson, P. Geo., a Qualified Person as that term is defined under National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101"), has reviewed and approved the technical aspects of this news release. Mr. Hanson, P.Geo., is independent of Silicon Metals Corp.

Raymond Wladichuk, P.Geo., a Qualified Person as that term is defined under NI 43-101, has also reviewed and approved the technical aspects of this news release. Mr. Wladichuk, P. Geo., is the COO and Director of Silicon Metals Corp.

For further information on the Ptarmigan Silica project, please see the Company's technical report titled "Ptarmigan Silica Project Cariboo Mining Division NTS 093/H10 and 11 British Columbia, Canada NI 43-101 Technical Report" with an effective date of September 26, 2024 and filed on October 1, 2024 by Chris M. Healey, P. Geo Principal Geologist, Healex Consulting Ltd Engineers and Geoscientists British Columbia Member, which is available under the Company's profile on SEDAR+ at www.sedarplus.ca.

About Silicon Metals Corp.

Silicon Metals Corp. is currently focused on exploration in western Canada, namely British Columbia. The Company holds an undivided 100% right, title and interest in the Ptarmigan Silica Project located approximately 130km from Prince George, British Columbia. The Company has also acquired an option to purchase an undivided 100% right, title, and interest in both the Silica Ridge Silica Project located approximately 70kms southeast from the town of MacKenzie, British Columbia, as well as the Longworth Silica Project located approximately 85km East from Prince George, British Columbia.

ON BEHALF OF THE BOARD OF DIRECTORS OF

SILICON METALS CORP.

"Morgan Good"

Morgan Good
Chief Executive Officer and Director

For more information regarding this news release, please contact:

Morgan Good, CEO and Director

Neither the CSE nor its Regulation Services Provider (as that term is defined in the policies of the CSE accepts responsibility for the adequacy or accuracy of this release).

Cautionary Note Regarding Forward-Looking Statements

This release includes certain statements and information that may constitute forward-looking information within the meaning of applicable Canadian securities laws. Forward-looking statements relate to future events or future performance and reflect the expectations or beliefs of management of the Company regarding future events. Generally, forward-looking statements and information can be identified by the use of forward-looking terminology such as "intends" or "anticipates", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "should", "would" or "occur". This information and these statements, referred to herein as "forward‐looking statements", are not historical facts, are made as of the date of this news release and include without limitation, statements relating to: the Company's future exploration plans with respect to the Ptarmigan Silica Project. Accordingly, readers should not place undue reliance on the forward-looking statements and information contained in this news release. Readers are cautioned that the foregoing list of factors is not exhaustive.

In making the forward-looking statements in this news release, the Company has applied certain material assumptions, including without limitation, that the Company's future exploration plans with respect to the Ptarmigan Silica Project will remain unchanged; and that the Company's operations and ability to complete its exploration plans will not be adversely impacted by global events and changes in the global economy.

These forward‐looking statements involve numerous risks and uncertainties and actual results might differ materially from results suggested in any forward-looking statements. These risks and uncertainties include, among other things, that the Company may not be able to carry out its future exploration plans with respect to the Ptarmigan Silica Project.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/254397

FAQ

What were the key findings from Silicon Metals Corp's (SLCNF) 2024 sampling program?

The sampling program revealed that 48% of quartzite samples exceeded 99% SiO2 purity, with 8% exceeding 99.9% SiO2. The average purity was 98.49% SiO2, with minimal impurities.

Where is Silicon Metals' Ptarmigan Project located?

The Ptarmigan Project is located approximately 130 kilometers from Prince George, British Columbia, Canada.

What technology is Silicon Metals (SLCNF) using to map their quartzite formations?

The company completed a high-definition airborne LiDAR survey conducted by McElhanney Ltd. to generate a 3D topographic model of the property's quartzite formations.

What were the main impurities found in Silicon Metals' quartzite samples?

The main impurities included Al2O3 (0.84%), Fe2O3 (0.33%), K2O (0.17%), and TiO2 (0.10%).

How many samples were analyzed in Silicon Metals' 2024 sampling program?

A total of 225 samples were analyzed, consisting of 184 quartzite samples and 41 country rock samples.
Silicon Metals Corp