STOCK TITAN

Sempra Infrastructure and EQT Announce Long-Term LNG Supply Agreement from Port Arthur LNG Phase 2

Rhea-AI Impact
(Low)
Rhea-AI Sentiment
(Neutral)

Sempra Infrastructure (NYSE: SRE) has signed a significant 20-year LNG supply agreement with EQT Corporation for 2 million tonnes per annum (Mtpa) from the Port Arthur LNG Phase 2 project in Texas. The agreement follows recent similar deals with JERA (1.5 Mtpa) and ConocoPhillips (4 Mtpa).

The Port Arthur LNG Phase 2 development has secured all major permits and selected Bechtel for engineering and construction. The project will add two liquefaction trains with 13 Mtpa capacity, potentially doubling the facility's total capacity to 26 Mtpa. Phase 1 is under construction with expected commercial operations in 2027-2028, while Phase 2's final investment decision is targeted for 2025.

Sempra Infrastructure (NYSE: SRE) ha firmato un importante contratto di fornitura di GNL della durata di 20 anni con EQT Corporation per 2 milioni di tonnellate all'anno (Mtpa) provenienti dal progetto Port Arthur LNG Fase 2 in Texas. L'accordo segue intese recenti simili con JERA (1,5 Mtpa) e ConocoPhillips (4 Mtpa).

Lo sviluppo della Fase 2 di Port Arthur LNG ha ottenuto tutte le autorizzazioni principali e ha scelto Bechtel per ingegneria e costruzione. Il progetto prevede l'aggiunta di due unità di liquefazione per una capacità di 13 Mtpa, potenzialmente raddoppiando la capacità complessiva dell'impianto a 26 Mtpa. La Fase 1 è in costruzione con entrata in servizio commerciale prevista per il 2027-2028, mentre la decisione finale sull'investimento per la Fase 2 è prevista per il 2025.

Sempra Infrastructure (NYSE: SRE) ha firmado un importante acuerdo de suministro de GNL a 20 años con EQT Corporation por 2 millones de toneladas anuales (Mtpa) procedentes del proyecto Port Arthur LNG Fase 2 en Texas. Este acuerdo se suma a pactos recientes similares con JERA (1,5 Mtpa) y ConocoPhillips (4 Mtpa).

El desarrollo de la Fase 2 de Port Arthur LNG ha obtenido todos los permisos principales y ha seleccionado a Bechtel para la ingeniería y la construcción. El proyecto añadirá dos trenes de licuefacción con 13 Mtpa de capacidad, lo que podría duplicar la capacidad total de la instalación hasta 26 Mtpa. La Fase 1 está en construcción y se espera que entre en operación comercial en 2027-2028, mientras que la decisión final de inversión para la Fase 2 está prevista para 2025.

Sempra Infrastructure (NYSE: SRE)는 텍사스의 Port Arthur LNG 2단계 프로젝트에서 연간 200만 톤(Mtpa)의 액화천연가스(LNG)를 공급받는 20년 장기 계약을 EQT Corporation과 체결했습니다. 이 계약은 JERA(1.5 Mtpa)ConocoPhillips(4 Mtpa)와의 최근 유사 계약에 이은 것입니다.

Port Arthur LNG 2단계 개발은 주요 인허가를 모두 확보했으며 엔지니어링 및 건설 파트너로 Bechtel을 선정했습니다. 이 프로젝트는 13 Mtpa 용량의 두 개 액화 트레인을 추가해 시설 전체 용량을 26 Mtpa로 잠재적으로 두 배로 늘릴 전망입니다. 1단계는 건설 중이며 2027–2028년에 상업운전을 시작할 예정이고, 2단계의 최종 투자 결정은 2025년을 목표로 하고 있습니다.

Sempra Infrastructure (NYSE: SRE) a signé un important contrat d'approvisionnement en GNL de 20 ans avec EQT Corporation pour 2 millions de tonnes par an (Mtpa) provenant du projet Port Arthur LNG Phase 2 au Texas. Cet accord fait suite à des contrats récents similaires avec JERA (1,5 Mtpa) et ConocoPhillips (4 Mtpa).

Le développement de la Phase 2 de Port Arthur LNG a obtenu toutes les autorisations majeures et a choisi Bechtel pour l'ingénierie et la construction. Le projet ajoutera deux trains de liquéfaction d'une capacité de 13 Mtpa, pouvant potentiellement porter la capacité totale de l'installation à 26 Mtpa. La Phase 1 est en construction avec une mise en service commerciale attendue en 2027-2028, tandis que la décision finale d'investissement pour la Phase 2 est prévue pour 2025.

Sempra Infrastructure (NYSE: SRE) hat einen bedeutenden 20-jährigen LNG-Liefervertrag mit EQT Corporation über 2 Millionen Tonnen pro Jahr (Mtpa) aus dem Port Arthur LNG Phase 2-Projekt in Texas abgeschlossen. Der Vertrag folgt auf ähnliche jüngste Abkommen mit JERA (1,5 Mtpa) und ConocoPhillips (4 Mtpa).

Die Entwicklung von Port Arthur LNG Phase 2 hat alle wichtigen Genehmigungen erhalten und Bechtel für Planung und Bau ausgewählt. Das Projekt sieht die Hinzufügung von zwei Verflüssigungszügen mit einer Kapazität von 13 Mtpa vor und könnte die Gesamtanlage damit potenziell auf 26 Mtpa verdoppeln. Phase 1 befindet sich im Bau und soll 2027–2028 kommerziell in Betrieb gehen, während die endgültige Investitionsentscheidung für Phase 2 für 2025 anvisiert ist.

Positive
  • Secured major 20-year LNG supply agreement with EQT for 2 Mtpa
  • All major regulatory permits obtained for Phase 2 development
  • Strong buyer interest demonstrated by recent agreements with JERA and ConocoPhillips
  • Project could double Port Arthur facility's total capacity to 26 Mtpa
Negative
  • Final investment decision still pending for Phase 2
  • Project faces various risks including need for additional commercial agreements and financing
  • Phase 1 operations won't begin until 2027-2028, indicating long development timeline

Insights

Sempra secures another major customer for Port Arthur LNG Phase 2, bringing total committed capacity to 7.5 Mtpa of the planned 13 Mtpa facility.

Sempra Infrastructure has secured EQT Corporation as the third major customer for its Port Arthur LNG Phase 2 project, with a 20-year agreement for 2 million tonnes per annum (Mtpa) of LNG. This deal follows recent agreements with JERA (1.5 Mtpa) and ConocoPhillips (4 Mtpa), bringing total committed capacity to 7.5 Mtpa, representing 58% of the planned 13 Mtpa Phase 2 capacity.

This agreement strengthens Sempra's position as it approaches a final investment decision (FID) on Phase 2 expected later in 2025. The project has already secured all major regulatory approvals, including FERC authorization and DOE export permits for non-free trade agreement countries. Engineering and procurement partner Bechtel is also in place, removing another key hurdle before FID.

The Henry Hub-indexed pricing structure ties the economics of this agreement to U.S. domestic natural gas prices rather than international oil benchmarks, potentially providing more stable revenue visibility for both parties. For EQT, America's largest natural gas producer, this represents significant progress in their strategy to expand into the LNG export market and secure long-term demand for their Appalachian production.

When combined with the 13 Mtpa Phase 1 facility currently under construction, the Port Arthur LNG complex would reach 26 Mtpa total capacity, positioning it among the largest LNG export facilities in North America. Phase 1 remains on schedule with expected commercial operations in 2027-2028, while securing these offtake agreements substantially de-risks the Phase 2 development.

HOUSTON and PITTSBURGH, Aug. 27, 2025 /PRNewswire/ -- Sempra Infrastructure, a subsidiary of Sempra (NYSE: SRE), and EQT Corporation (NYSE: EQT) today announced a 20-year definitive sales and purchase agreement (SPA) for the supply of 2 million tonnes per annum (Mtpa) of liquefied natural gas (LNG) offtake from the Port Arthur LNG Phase 2 development project in Jefferson County, Texas. Pursuant to the SPA, EQT will purchase the LNG on a free-on-board basis at a price indexed to Henry Hub.

"Advancing the Port Arthur LNG Phase 2 project with EQT reflects our mutual commitment to helping ensure U.S. natural gas projects continue to support local economic development and provide global markets with a stable, long-term supply of LNG," said Justin Bird, CEO of Sempra Infrastructure. "This development project can help fortify America's position as a leading energy exporter, which is a shared goal of EQT and Sempra Infrastructure."

"This agreement underscores EQT's role in unleashing U.S. LNG that enhance global energy security while driving progress toward lower-carbon solutions," said Toby Z. Rice, president and CEO of EQT. "We are proud to partner with Sempra Infrastructure on this critical project, helping further the quest to ensure American energy dominance."

The Port Arthur LNG Phase 2 development project is strategically positioned to help meet global energy demand and has attracted strong interest from prospective LNG buyers. In July 2025, Sempra Infrastructure signed a definitive 20-year SPA with JERA Co., Inc. for 1.5 Mtpa of LNG offtake. Earlier this month, Sempra Infrastructure expanded its strategic alliance with ConocoPhillips with a 20-year SPA for 4 Mtpa of LNG offtake from the proposed project. Future phases are also in the early development stage.

In September 2023, the Federal Energy Regulatory Commission granted project approval, followed by an export authorization from the U.S. Department of Energy in May 2025, allowing LNG exports to countries without a free-trade agreement with the United States. All major permits for the Port Arthur LNG Phase 2 development project have been secured.

Further advancing the project, Sempra Infrastructure also previously announced that Bechtel had been selected to deliver the engineering, procurement and construction of the Port Arthur LNG Phase 2 facility. With continued momentum in the project's development, Sempra Infrastructure continues to target making a final investment decision on the Port Arthur LNG Phase 2 project in 2025.

Port Arthur LNG Phase 2 is expected to include two liquefaction trains capable of producing approximately 13 Mtpa of LNG, which could increase the total liquefaction capacity of the Port Arthur LNG facility from approximately 13 Mtpa for Phase 1 to up to approximately 26 Mtpa. Port Arthur LNG Phase 1, which is currently under construction, is expected to achieve commercial operations in 2027 and 2028 for trains 1 and 2, respectively.

The development of the Port Arthur LNG Phase 2 project remains subject to various risks and uncertainties, including completing the required commercial agreements, securing and/or maintaining all necessary permits, obtaining financing and reaching a final investment decision, among other factors.

About Sempra Infrastructure
Sempra Infrastructure, headquartered in Houston, is focused on delivering energy for a better world by developing, building, operating and investing in modern energy infrastructure, such as LNG, energy networks and low-carbon solutions that are expected to play a crucial role in the energy systems of the future. Through the combined strength of its assets in North America, Sempra Infrastructure is connecting customers to safe and reliable energy and advancing energy security. Sempra Infrastructure is a subsidiary of Sempra (NYSE: SRE), a leading North American energy infrastructure company. For more information, visit semprainfrastructure.com or connect with Sempra Infrastructure on social media @SempraInfra.

About EQT Corporation
EQT Corporation is a premier, vertically integrated American natural gas company with production and midstream operations focused in the Appalachian Basin. We are dedicated to responsibly developing our world-class asset base and being the operator of choice for our stakeholders. By leveraging a culture that prioritizes operational efficiency, technology and sustainability, we seek to continuously improve the way we produce environmentally responsible, reliable and low-cost energy. We have a longstanding commitment to the safety of our employees, contractors and communities and to the reduction of our overall environmental footprint. Our values are evident in the way we operate and in how we interact each day — trust, teamwork, heart and evolution are at the center of all we do.

Cautionary Statements Regarding Forward-Looking Statements

Sempra Infrastructure Forward-Looking Statements

This press release contains forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. Forward-looking statements are based on assumptions about the future, involve risks and uncertainties, and are not guarantees. Future results may differ materially from those expressed or implied in any forward-looking statement. These forward-looking statements represent our estimates and assumptions only as of the date of this press release. We assume no obligation to update or revise any forward-looking statement as a result of new information, future events or otherwise.

In this press release, forward-looking statements can be identified by words such as "believe," "expect," "intend," "anticipate," "contemplate," "plan," "estimate," "project," "forecast," "envision," "should," "could," "would," "will," "confident," "may," "can," "potential," "possible," "proposed," "in process," "construct," "develop," "opportunity," "preliminary," "initiative," "target," "outlook," "optimistic," "poised," "positioned," "maintain," "continue," "progress," "advance," "goal," "aim," "commit," or similar expressions, or when we discuss our guidance, priorities, strategies, goals, vision, mission, projections, intentions or expectations.

Factors, among others, that could cause actual results and events to differ materially from those expressed or implied in any forward-looking statement include: decisions, audits, investigations, inquiries, regulations, denials or revocations of permits, consents, approvals or other authorizations, and other actions, including the failure to honor contracts and commitments, by the (i) U.S. Department of Energy, Comisión Nacional de Energía, U.S. Federal Energy Regulatory Commission, U.S. Internal Revenue Service and other regulatory bodies and (ii) U.S., Mexico and states, counties, cities and other jurisdictions therein and in other countries where we do business; the success of business development efforts, construction projects, acquisitions, divestitures and other significant transactions, including risks related to (i) being able to make a final investment decision, (ii) negotiating pricing and other terms in definitive contracts, (iii) completing construction projects or other transactions on schedule and budget, (iv) realizing anticipated benefits from any of these efforts if completed, (v) obtaining regulatory and other approvals and (vi) third parties honoring their contracts and commitments; changes to our capital expenditure plans and their potential impact on growth; changes, due to evolving economic, political and other factors, to (i) trade and other foreign policy, including the imposition of tariffs by the U.S. and foreign countries, and (ii) laws and regulations, including those related to tax and the energy industry in the U.S. and Mexico; litigation, arbitration, property disputes and other proceedings; cybersecurity threats, including by state and state-sponsored actors, of ransomware or other attacks on our systems or the systems of third parties with which we conduct business, including the energy grid or other energy infrastructure; the availability, uses, sufficiency, and cost of capital resources and our ability to borrow money or otherwise raise capital on favorable terms and meet our obligations, which can be affected by, among other things, (i) actions by credit rating agencies to downgrade our credit ratings or place those ratings on negative outlook, (ii) instability in the capital markets, and (iii) fluctuating interest rates and inflation; the impact on our ability to pass through higher costs to customers due to volatility in inflation, interest and foreign currency exchange rates and commodity prices and the imposition of tariffs; the impact of climate policies, laws, rules, regulations, trends and required disclosures, including actions to reduce or eliminate reliance on natural gas, the risk of nonrecovery for stranded assets, and uncertainty related to emerging technologies; weather, natural disasters, pandemics, accidents, equipment failures, explosions, terrorism, information system outages or other events, such as work stoppages, that disrupt our operations, damage our facilities or systems, cause the release of harmful materials or fires or subject us to liability for damages, fines and penalties, some of which may not be recoverable through insurance or may impact our ability to obtain satisfactory levels of affordable insurance; the availability of natural gas, including disruptions caused by failures in the pipeline and storage systems or limitations on the injection and withdrawal of natural gas from storage facilities; and other uncertainties, some of which are difficult to predict and beyond our control.

These risks and uncertainties are further discussed in the reports that Sempra has filed with the U.S. Securities and Exchange Commission (SEC). These reports are available through the EDGAR system free-of-charge on the SEC's website, www.sec.gov, and on Sempra's website, www.sempra.com. Investors should not rely unduly on any forward-looking statements.

Sempra Infrastructure and Sempra Infrastructure Partners are not the same company as San Diego Gas & Electric Company or Southern California Gas Company, and none of Sempra Infrastructure, Sempra Infrastructure Partners nor any of its subsidiaries is regulated by the California Public Utilities Commission.

EQT Forward-Looking Statements

This press release contains forward-looking statements within the meaning of Section 21E of the Securities Exchange Act of 1934, as amended, and Section 27A of the Securities Act of 1933, as amended. Statements that do not relate strictly to historical or current facts are forward-looking. Without limiting the generality of the foregoing, forward-looking statements contained in this press release specifically include the plans and expectations associated with EQT Corporation's (EQT) SPA with Sempra Infrastructure for the supply of LNG offtake from the Port Arthur LNG Phase 2 development project, including the proposed timing of in-service of the Port Arthur LNG Phase 2 facility, the final scope, infrastructure, and available liquefaction capacity at such facility, and whether the project will be completed at all – all of which could impact whether EQT will be able to purchase the volume of LNG offtake set forth in the SPA, if at all.

The forward-looking statements included in this press release involve risks and uncertainties that could cause actual results to differ materially from projected results. Accordingly, investors should not place undue reliance on forward-looking statements as a prediction of actual results. EQT has based these forward-looking statements on current expectations and assumptions about future events, taking into account all information currently known by EQT. While EQT considers these expectations and assumptions to be reasonable, they are inherently subject to significant business, economic, competitive, regulatory and other risks and uncertainties, many of which are difficult to predict and beyond EQT's control. These risks and uncertainties include, but are not limited to, volatility of commodity prices; the costs and results of drilling and operations; uncertainties about estimates of reserves, identification of drilling locations and the ability to add proved reserves in the future; the assumptions underlying production forecasts; the quality of technical data; EQT's ability to appropriately allocate capital and other resources among its strategic opportunities; access to and cost of capital; EQT's hedging and other financial contracts; inherent hazards and risks normally incidental to drilling for, producing, transporting, storing and processing natural gas, natural gas liquids and oil; operational risks and hazards incidental to the gathering, transmission and storage of natural gas as well as unforeseen interruptions; cyber security risks and acts of sabotage; availability and cost of drilling rigs, completion services, equipment, supplies, personnel, oilfield services and pipe, sand and water required to execute EQT's exploration and development plans, including as a result of inflationary pressures or tariffs; risks associated with operating primarily in the Appalachian Basin; the ability to obtain environmental and other permits and the timing thereof; construction, business, economic, competitive, regulatory, judicial, environmental, political and legal uncertainties related to the development and construction by EQT or its joint ventures of pipeline and storage facilities and transmission assets and the optimization of such assets; EQT's ability to renew or replace expiring gathering, transmission or storage contracts at favorable rates, on a long-term basis or at all; risks relating to EQT's joint venture arrangements; government regulation or action, including regulations pertaining to methane and other greenhouse gas emissions; negative public perception of the fossil fuels industry; increased consumer demand for alternatives to natural gas; environmental and weather risks, including the possible impacts of climate change; and disruptions to EQT's business due to recently completed or pending divestitures, acquisitions and other significant strategic transactions. These and other risks and uncertainties are described under the "Risk Factors" section and elsewhere in EQT's Annual Report on Form 10-K for the year ended December 31, 2024 and other documents EQT subsequently files from time to time with the Securities and Exchange Commission. In addition, EQT may be subject to currently unforeseen risks that may have a materially adverse impact on it.

Any forward-looking statement speaks only as of the date on which such statement is made, and, except as required by law, EQT does not intend to correct or update any forward-looking statement, whether as a result of new information, future events or otherwise.

Sempra Infrastructure (PRNewsfoto/Sempra Infrastructure)

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/sempra-infrastructure-and-eqt-announce-long-term-lng-supply-agreement-from-port-arthur-lng-phase-2-302539579.html

SOURCE Sempra North American Infrastructure

FAQ

What is the size of Sempra's LNG supply agreement with EQT for Port Arthur Phase 2?

Sempra Infrastructure signed a 20-year agreement with EQT to supply 2 million tonnes per annum (Mtpa) of LNG from Port Arthur Phase 2.

When will Sempra's Port Arthur LNG Phase 1 begin operations?

Port Arthur LNG Phase 1 is expected to begin commercial operations in 2027 for train 1 and 2028 for train 2.

What is the total capacity of Sempra's Port Arthur LNG facility after Phase 2?

After Phase 2 completion, the total liquefaction capacity could increase to approximately 26 Mtpa, up from Phase 1's 13 Mtpa.

How many LNG supply agreements has Sempra secured for Port Arthur Phase 2?

Sempra has secured three major agreements: 2 Mtpa with EQT, 1.5 Mtpa with JERA, and 4 Mtpa with ConocoPhillips.

When will Sempra make the final investment decision for Port Arthur LNG Phase 2?

Sempra Infrastructure is targeting to make the final investment decision in 2025.
Sempra Energy

NYSE:SRE

SRE Rankings

SRE Latest News

SRE Latest SEC Filings

SRE Stock Data

53.30B
651.26M
0.12%
91.83%
1.62%
Utilities - Diversified
Gas & Other Services Combined
Link
United States
SAN DIEGO