Silvercorp reports a Mineral Reserve increase of 50% in tonnes and 20% in silver ounces for the Ying Mining District
Rhea-AI Summary
Silvercorp (TSX/NYSE American: SVM) released its 2026 Technical Report for the Ying Mining District, showing a 50% increase in Mineral Reserve tonnes and a 20% rise in contained silver ounces versus 2024.
The plan outlines a 17-year mine life to 2042 and projects 106 Moz silver production.
Positive
- Measured & Indicated Resources +90% in tonnes, contained Ag +37%, Au +62%, Pb +39%, Zn +48%
- Proven and Probable Reserves total 19 Mt, containing 106 Moz Ag and 107 koz Au
- Proven Reserve tonnes +45% and Probable Reserve tonnes +55% versus 2024
- Planned 17-year life of mine with total 109,119 koz AgEq production
- Projected pre-tax NPV of $1,275M and post-tax NPV of $1,030M at 5% discount rate
- Annual ore throughput projected to exceed 1.6 Mt from FY2029 to FY2031
Negative
- Measured & Indicated grades decreased: Ag -28%, Au -15%, Pb -27%, Zn -22% versus 2024
- Inferred grades lower for Ag, Au, Pb and Zn by 42%, 38% and 9% respectively
- Contained Inferred Ag -1%, Au -10%, Pb -4%, despite Zn +40%
- Life-of-mine production profile declines gradually after FY2031
- Lower cut-off grades rely on higher metal price assumptions than in 2024
News Market Reaction – SVM
In the Jun 12 session, SVM gained 7.52%, reflecting a notable positive market reaction. Argus tracked a peak move of +4.6% during that session. Our momentum scanner triggered 41 alerts that day, indicating elevated trading interest and price volatility.
Data tracked by StockTitan Argus on the day of publication.
Key Figures
Historical Context
| Date | Event | Sentiment | 24h Move | Catalyst |
|---|---|---|---|---|
| May 26 | Fiscal 2026 earnings | Positive | -4.3% | Strong revenue and cash flow with adjusted net income growth. |
| May 25 | HK listing plan | Positive | +5.6% | Application for Hong Kong listing and potential global offering. |
| May 22 | Dividend declaration | Positive | +5.6% | Announcement of semi-annual cash dividend to shareholders. |
| May 22 | Results timing update | Neutral | -3.3% | Rescheduled release date and call details for Fiscal 2026 results. |
| May 20 | Kyrgyz license extension | Positive | -2.6% | Extended Kyrgyz gold license and JV structure with Kyrgyzaltyn. |
24h Move is the share-price change in the day after each event; other market factors may also have contributed.
Recent history shows mixed reactions: strong operational or strategic updates sometimes met with selling, while capital markets and dividend announcements have seen buying.
Over the last few weeks, Silvercorp reported strong Fiscal 2026 results with revenue of $438.1M and adjusted net income of $150.8M, yet the stock fell after earnings on May 26. A proposed Hong Kong listing and a semi-annual dividend of US$0.0125 per share on May 25–22 both saw positive price reactions. The Kyrgyz Tulkubash/Kyzyltash license extension and joint venture announcement on May 20 were followed by a modest decline. Today’s substantial reserve and resource upgrades at Ying add another operational milestone to this sequence of growth-focused updates.
Key Terms
ni 43-101 regulatory
mineral reserve technical
mineral resource technical
life of mine technical
cut-off grades technical
silver equivalent technical
gold equivalent technical
payables financial
AI-generated analysis. How Rhea-AI works. Not financial advice.

Trading Symbol: TSX/NYSE American: SVM
Approximately 106 million ounces (Moz) of silver ("Ag") plus lead, zinc, and gold are projected to be mined at the Ying Property in the currently planned 17-year life of mine (LOM). There remains significant potential to extend the LOM beyond 2042 via further exploration and development, particularly in areas with identified Inferred Resources.
Silvercorp Main Observations to the Independent Ying 2026 Technical Report:
Lower cut-off grades were applied due to a higher silver price used (
The 2026 Mineral Reserves reflect the replenishment of metals mined-out between June 2024 (effective date of 2024 Technical Report) and December 2025, with approximately 9.8 million ounces of silver ("Moz Ag"), 12.6 thousand ounces of gold ("koz Au"), 38.6 thousand tonnes of lead ("kt Pb") and 5.1 thousand tonnes of zinc ("kt Zn") produced.
Ying Mining District LOM metal production AgEq values, which only consider silver plus conversion of gold ounces to equivalent silver ounces[1], are shown in Table 1.
Table 1. Ying LOM metal production AgEq values
Ying | FY | FY | FY | FY | FY | FY | FY | FY | FY | FY | FY | FY | FY | FY | FY | FY | FY | Total |
AgEq koz | 1,597 | 7,801 | 9,176 | 9,984 | 9,709 | 9,499 | 9,140 | 8,792 | 8,468 | 7,451 | 6,625 | 5,761 | 4,317 | 3,356 | 3,249 | 2,660 | 1,535 | 109,119 |
[1]AgEq (oz) = Ag (oz) + 83.279* Au (oz); Au and Ag prices at |
Note: Numbers may not compute exactly due to rounding. |
Summary of the Ying 2026 Technical Report
- Estimated Measured and Indicated Mineral Resources of 42.18 million tonnes (inclusive of Mineral Reserves) grading 146 grams per tonne ("g/t") Ag, 0.17 g/t Au,
2.24% Pb, and0.67% Zn, containing 198 Moz Ag, 231 koz Au, 944 kt Pb, and 284 kt Zn.- In comparison with the 2024 Technical Report, Measured and Indicated Resource tonnes have increased by
90% , and contained metal has increased by37% for Ag,62% for Au,39% for Pb and48% for Zn.
- In comparison with the 2024 Technical Report, Measured and Indicated Resource tonnes have increased by
- Estimated Proven and Probable Mineral Reserves of 19 million tonnes grading 174 g/t Ag, 0.17 g/t Au,
2.47% Pb,0.80% Zn, and0.04% Cu, containing 106 Moz Ag, 107 koz Au, 472 kt Pb, 150 kt Zn, and 6.7 kt Cu.- In comparison with the 2024 Technical Report there has been a
45% increase in total Proven Mineral Reserve tonnes and a55% increase in total Probable Mineral Reserve tonnes. Total contained metal has increased for silver, gold, lead, and zinc by20% for Ag,52% for Au,16% for Pb, and22% for Zn.
- In comparison with the 2024 Technical Report there has been a
- In comparison with the 2024 Technical Report, Inferred Resource tonnes have increased by
54% , and contained metal has decreased by1% for Ag,10% for Au, and4% for Pb, while Zn has increased by40% . - Annual ore production in the LOM plan is projected to rise from the projected full-year FY2026 level of about 1.2 Mt to: 1.3 Mt in FY2027; 1.5Mt in FY2028; and over 1.6 Mt in FY2029, with that level being maintained through to FY2031. From FY2032, production will decline gradually until the projected end of the mine life in 2042.
- Using the LOM production profile based on the 31 December 2025 Mineral Reserves, with long-term[2] metal prices of
/oz Ag,$28 /oz Au,$2,800 /lb Pb,$0.90 /lb Zn, and$1.20 /lb Cu, and a$4.40 5% discount rate, pre-tax and post-tax NPVs of and$1,275M , respectively, are projected[3] (other assumptions are outlined below).$1,030M
[2] Gold/oz: |
[3] As a conservative projection measure, |
Mineral Resources
The December 2025 Mineral Resources were estimated using a block modelling approach in Datamine or
The Mineral Resources are reported above cut‐offs after applying a minimum practical extraction width of 0.4 m. Diluted grades were estimated for blocks with mineralization widths less than 0.4 m by adding a waste envelope with zero grade. Cut‐off grades are based on either in situ values in silver equivalent (AgEq) or gold equivalent (AuEq) terms in grams per tonne and incorporate mining, trucking, and processing costs, with metallurgical recoveries and payable values provided by Silvercorp for each mine and reviewed by the QPs. Equivalency formulas by deposit are shown in the footnotes of the table below.
The estimated Mineral Resources and metal content for the Ying Mining District as of December 31, 2025 are detailed in Table 2 below.
Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. There is no certainty that all or any part of the Mineral Resources will be converted to Mineral Reserves.
Table 2. Ying Mining District – Mineral Resources and metal content for silver, lead, zinc, gold and copper as of December 31, 2025 (inclusive of Mineral Reserves)
Mine | Resource | Tonnes | Au | Ag | Pb | Zn | Cu | Au | Ag | Pb | Zn | Cu |
SGX | Measured | 6.98 | 0.06 | 205 | 3.99 | 2.08 | 0.03 | 13.85 | 45.95 | 278.43 | 145.13 | 2.11 |
Indicated | 5.63 | 0.05 | 157 | 2.95 | 1.66 | 0.05 | 9.57 | 28.49 | 165.77 | 93.27 | 2.54 | |
Meas + Ind | 12.61 | 0.06 | 184 | 3.52 | 1.89 | 0.04 | 23.43 | 74.44 | 444.20 | 238.40 | 4.65 | |
Inferred | 3.77 | 0.07 | 150 | 3.06 | 1.21 | 0.05 | 8.17 | 18.22 | 115.32 | 45.77 | 2.04 | |
HZG | Measured | 0.86 | - | 229 | 0.89 | - | 0.31 | - | 6.32 | 7.63 | - | 2.71 |
Indicated | 0.87 | - | 189 | 0.72 | - | 0.28 | - | 5.28 | 6.27 | - | 2.44 | |
Meas + Ind | 1.73 | - | 208 | 0.80 | - | 0.30 | - | 11.60 | 13.90 | - | 5.14 | |
Inferred | 0.63 | - | 266 | 0.69 | - | 0.29 | - | 5.39 | 4.38 | - | 1.85 | |
HPG | Measured | 1.81 | 0.82 | 57 | 2.42 | 0.75 | 0.06 | 47.57 | 3.32 | 43.61 | 13.53 | 1.00 |
Indicated | 2.27 | 0.78 | 47 | 1.92 | 0.66 | 0.05 | 57.01 | 3.44 | 43.78 | 15.11 | 1.11 | |
Meas + Ind | 4.08 | 0.80 | 51 | 2.14 | 0.70 | 0.05 | 104.57 | 6.75 | 87.39 | 28.64 | 2.11 | |
Inferred | 2.55 | 0.79 | 48 | 1.57 | 0.66 | 0.08 | 64.88 | 3.91 | 39.95 | 16.89 | 1.96 | |
TLP | Measured | 6.51 | 0.00 | 131 | 2.33 | - | 0.05 | 0.21 | 27.40 | 151.77 | - | 3.22 |
Indicated | 5.14 | 0.00 | 111 | 1.89 | - | 0.07 | 0.58 | 18.37 | 97.46 | - | 3.49 | |
Meas + Ind | 11.65 | 0.00 | 122 | 2.14 | - | 0.06 | 0.79 | 45.77 | 249.23 | - | 6.71 | |
Inferred | 2.06 | 0.14 | 113 | 2.02 | - | 0.09 | 9.07 | 7.53 | 41.64 | - | 1.93 | |
LME | Measured | 1.55 | 0.03 | 216 | 1.08 | 0.24 | 0.03 | 1.34 | 10.75 | 16.74 | 3.79 | 0.53 |
Indicated | 2.97 | 0.09 | 172 | 0.93 | 0.25 | 0.05 | 8.29 | 16.46 | 27.79 | 7.57 | 1.41 | |
Meas + Ind | 4.52 | 0.07 | 187 | 0.98 | 0.25 | 0.04 | 9.63 | 27.21 | 44.53 | 11.36 | 1.94 | |
Inferred | 1.54 | 0.16 | 145 | 1.06 | 0.31 | 0.05 | 8.09 | 7.19 | 16.36 | 4.79 | 0.79 | |
LMW | Measured | 2.71 | - | 178 | 1.64 | - | 0.11 | - | 15.46 | 44.47 | - | 3.01 |
Indicated | 2.83 | - | 131 | 1.42 | - | 0.07 | - | 11.95 | 40.05 | - | 2.04 | |
Meas + Ind | 5.54 | - | 154 | 1.53 | - | 0.09 | - | 27.41 | 84.52 | - | 5.06 | |
Inferred | 1.22 | - | 129 | 1.42 | - | 0.08 | - | 5.05 | 17.35 | - | 0.95 | |
LMW | Measured | 0.29 | 2.49 | 66 | 0.31 | - | 0.26 | 22.92 | 0.61 | 0.90 | - | 0.73 |
Indicated | 0.83 | 1.36 | 50 | 0.36 | - | 0.19 | 36.04 | 1.34 | 2.96 | - | 1.58 | |
Meas + Ind | 1.11 | 1.65 | 54 | 0.35 | - | 0.21 | 58.96 | 1.94 | 3.86 | - | 2.31 | |
Inferred | 0.81 | 1.19 | 25 | 0.22 | - | 0.12 | 31.12 | 0.66 | 1.81 | - | 0.99 | |
DCG | Measured | 0.25 | 1.62 | 54 | 1.68 | - | 0.04 | 12.97 | 0.43 | 4.17 | - | 0.09 |
Indicated | 0.44 | 1.01 | 35 | 2.01 | - | 0.02 | 14.27 | 0.50 | 8.84 | - | 0.08 | |
Meas + Ind | 0.69 | 1.23 | 42 | 1.89 | - | 0.03 | 27.24 | 0.93 | 13.01 | - | 0.17 | |
Inferred | 0.35 | 1.18 | 35 | 2.01 | - | 0.02 | 13.41 | 0.40 | 7.13 | - | 0.08 | |
KP | Measured | - | - | - | - | - | - | - | - | - | - | - |
Indicated | 0.25 | 0.75 | 197 | 1.29 | 2.34 | 0.00 | 5.99 | 1.57 | 3.20 | 5.82 | 0.00 | |
Meas + Ind | 0.25 | 0.75 | 197 | 1.29 | 2.34 | 0.00 | 5.99 | 1.57 | 3.20 | 5.82 | 0.00 | |
Inferred | 0.61 | 0.39 | 199 | 0.77 | 1.78 | 0.00 | 7.66 | 3.91 | 4.75 | 10.93 | 0.00 | |
All | Measured | 20.94 | 0.15 | 164 | 2.62 | 0.78 | 0.06 | 98.86 | 110.24 | 547.72 | 162.45 | 13.41 |
Indicated | 21.24 | 0.19 | 128 | 1.87 | 0.57 | 0.07 | 131.75 | 87.39 | 396.11 | 121.77 | 14.68 | |
Meas + Ind | 42.18 | 0.17 | 146 | 2.24 | 0.67 | 0.07 | 230.61 | 197.63 | 943.84 | 284.22 | 28.10 | |
Inferred | 13.55 | 0.33 | 120 | 1.84 | 0.58 | 0.08 | 142.40 | 52.26 | 248.70 | 78.38 | 10.60 |
Notes:
- CIM Definition Standards (2014) were used for reporting.
- Measured and Indicated Mineral Resources are inclusive of Mineral Reserves.
- Metal prices: gold
US /troy ounce (oz), silver$3,200 US /troy oz, lead$35.00 US per pound (lb), zinc$1.03 US /lb, copper$1.36 US /lb.$4.74 - Exchange rate:
RMB 7 .00:US .$1.00 - Mineral Resources exclude the first 5 m below surface.
- Veins diluted to minimum extraction width of 0.4 m after estimation except for HZG which was modelled to a minimum width of 0.4 m.
- COGs: SGX 75 g/t AgEq; HZG 75 g/t AgEq; HPG 0.95 g/t AuEq; TLP 65 g/t AgEq; LME 70 g/t AgEq; LMW silver rich veins 65 g/t AgEq; LMW gold rich veins 0.85 g/t AuEq; DCG 80 g/t AgEq, KP 90 g/t AgEq.
- AgEq equivalent formulas by mine for silver rich veins:
- SGX = Ag g/t + 21.3351 * Pb% + 15.7268 * Zn% + 37.3575 * Cu%.
- HZG = Ag g/t + 19.557 * Pb% + 39.5464 * Cu%.
- TLP = Ag g/t + 20.4155 * Pb% + 37.2718 * Cu%.
- LME = Ag g/t + 19.3704 * Pb% + 8.3614 * Zn% + 36.0026 * Cu%.
- LMW = Ag g/t + 20.6682 * Pb% + 38.6489 * Cu%.
- DCG = Ag g/t + 19.1772 * Pb% + 33.4296 * Cu%.
- AuEq equivalent formulas by mine:
- HPG (all veins) = Au g/t+0.0119*Ag g/t+0.2544*Pb%+0.1888*Zn%+0.4926*Cu%.
- LMW (gold rich veins: LM21, LM22, LM26, LM27, LM28, LM28a, LM50, LM50_3, LM51, LM52, LM53, LM54, LM54_1, LM54_2, LM55, LM58, LM58_1, LM59, LM59_2) = Au g/t + 0.0133 * Ag g/t + 0.2748 * Pb% + 0.5139 * Cu%.
- AgEq formulas used for significant gold bearing veins:
- SGX (Veins S16W, S18E, S21, S74) = Ag g/t + 52.7753 * Au g/t + 21.3351 * Pb% + 15.7268 * Zn% + 37.3575 * Cu%.
- TLP (T50, T51, T52, T53) = Ag g/t + 54.8113 * Au g/t + 20.4155 * Pb% + 37.2718 * Cu%.
- LME (Vein LM4E2) = Ag g/t + 46.0927 * Au g/t + 19.3704 * Pb% + 8.3614 * Zn% + 36.0026 * Cu%.
- DCG (C76, C9_1, C9_2, C9_3, C9_4, C9_5, C9_6, C9E1, C9E3, C9W1) = Ag g/t + 76.6609 * Au g/t + 19.1772 * Pb% + 33.4296 * Cu%.
- KP (all veins) = Ag g/t + 76.6609 * Au g/t + 19.1772 * Pb% + 17.9076 * Zn% + 33.4296 * Cu%.
- Processing recovery factors:
- SGX –
61.3% Au,95.6% Ag,96.4% Pb,70.1% Zn,90.8% Cu. - HZG –
62.2% Au,95.6% Ag,88.4% Pb,96.2% Cu. - HPG –
91.0% Au,88.8% Ag,90.1% Pb,66.0% Zn,93.8% Cu. - TLP –
61.8% Au,92.8% Ag,89.6% Pb,88.0% Cu. - LME –
53.3% Au,95.2% Ag,87.2% Pb,37.1% Zn,87.2% Cu. - LMW –
87.2% Au,95.4% Ag,93.3% Pb,93.8% Cu. - DCG –
75.9% Au,81.4% Ag,73.8% Pb,69.2% Cu. - KP -
75.9% Au,81.4% , Ag,73.8% , Pb, 68.0 % Zn,69.2% Cu.
- SGX –
- Payables: Au –
85% ; Ag –94.5% ; Pb –99.0% ; Zn –76.0% , Cu –40% . - Includes assay results up to and including 31 October 2025.
- Depleted for mine production to 31 December 2025. Non-recoverable Mineral Resources (sterile areas due to the proximity to stopes, unstable ground or where access to the vein is limited) defined as of 31 December 2025.
- Where gold grades show zero g/t, this reflects limited numbers of gold veins informing the Mineral Resource.
- Where copper grades show zero grade, this reflects the low tenor of the copper in the deposits.
- Numbers may not compute exactly due to rounding.
A comparison of Mineral Resource estimates between June 30, 2024 and December 31, 2025 indicates the following:
- Measured and Indicated tonnes have increased by
90% overall. The Inferred tonnes have increased by54% . - Measured and Indicated grades have decreased for Ag and Au by
28% and15% , respectively. Measured and Indicated grades have decreased for Pb by27% and Zn by22% . - Inferred grades decreased for Ag, Au, Pb, and Zn by
42% ,38% , and9% , respectively. - The net result in the Measured and Indicated categories has been an increase in the contained Ag and Au of
37% and62% respectively. Contained Measured and Indicated Pb and Zn have increased by39% and48% respectively. - The net result in the Inferred category has been a decrease in the contained Ag, Au, and Pb of
1% ,10% , and4% respectively. Inferred Zn has increased by40% .
The reasons for the differences in grade, tonnes, and contained metal include changes made to vein interpretations for the 2025 Q4 model, conversion to higher categories arising from drilling and level development, application of different COGs and depletion due to mining. The QPs note that metal prices have increased by
Mineral Reserves
The Mineral Reserve estimation assumes that current stoping practices will continue to be predominant at the Ying property, namely cut and fill resuing and shrinkage stoping for most veins, using hand-held drills (jacklegs) and hand-mucking within stopes, and loading to mine cars by rocker-shovel or by hand. The QP also recognizes the increased use of more mechanized mining techniques at the Ying operations. The typically sub-vertical veins, generally competent ground, reasonably regular vein width, and generally hand-mining techniques using short rounds, allow a significant degree of selectivity and control in the stoping process. Minimum mining widths of 0.5 m for resuing and 1.0 m for shrinkage are assumed. The QP has observed the resuing and shrinkage mining methods at the Ying property on several occasions and considers the minimum extraction and mining width assumptions to be reasonable. Minimum dilution assumptions are 0.10 m of total overbreak for a resuing cut and 0.2 m of total overbreak for a shrinkage stope. Average Ying dilution projections for resuing and shrinkage are
The QP notes that, for a small number of veins with relatively low-angle dip – generally veins with significant gold content – room and pillar stoping with slushers is now being used at the Property. Longhole stoping has also been recently employed in some areas of the LMW mine.
Recent initiatives at the Ying operations have resulted in a +
For the total tonnage estimated as Ying Mineral Reserves, approximately
The estimated Mineral Reserves and metal content for the Ying Mining District as of December 31, 2025 are detailed in Table 3 below.
Table 3. Ying Mining District Mineral Reserve estimates and metal content at December 31, 2025
Mine | Category | Mt | Au | Ag | Pb | Zn | Cu | Metal contained in Mineral Reserves | ||||
Au | Ag | Pb | Zn | Cu | ||||||||
SGX | Proven | 4.43 | 0.05 | 201 | 3.97 | 1.89 | 7.0 | 28.6 | 175.9 | 83.5 | ||
Probable | 2.81 | 0.03 | 198 | 3.70 | 1.70 | 2.6 | 17.9 | 104.3 | 47.8 | |||
Subtotal P&P | 7.24 | 0.04 | 200 | 3.87 | 1.81 | 9.6 | 46.5 | 280.2 | 131.4 | |||
HZG | Proven | 0.53 | 212 | 0.75 | 0.29 | 3.6 | 4.0 | 1.5 | ||||
Probable | 0.56 | 185 | 0.64 | 0.26 | 3.3 | 3.5 | 1.4 | |||||
Subtotal P&P | 1.09 | 198 | 0.69 | 0.28 | 6.9 | 7.5 | 3.0 | |||||
HPG | Proven | 0.68 | 1.01 | 62 | 2.60 | 0.61 | 0.07 | 22.3 | 1.4 | 17.8 | 4.1 | 0.5 |
Probable | 0.67 | 0.96 | 61 | 2.36 | 0.69 | 0.06 | 20.6 | 1.3 | 15.7 | 4.6 | 0.4 | |
Subtotal P&P | 1.35 | 0.99 | 62 | 2.48 | 0.65 | 0.07 | 42.8 | 2.7 | 33.5 | 8.7 | 0.9 | |
TLP | Proven | 2.48 | 150 | 2.28 | 12.0 | 56.5 | ||||||
Probable | 1.58 | 136 | 2.01 | 6.9 | 31.9 | |||||||
Subtotal P&P | 4.07 | 145 | 2.18 | 18.9 | 88.4 | |||||||
LME | Proven | 0.73 | 0.01 | 254 | 1.07 | 0.24 | 0.3 | 5.9 | 7.8 | 1.7 | ||
Probable | 1.56 | 0.04 | 214 | 1.03 | 0.25 | 2.2 | 10.7 | 16.0 | 3.8 | |||
Subtotal P&P | 2.28 | 0.03 | 227 | 1.04 | 0.24 | 2.5 | 16.7 | 23.8 | 5.6 | |||
LMW | Proven | 1.41 | 0.29 | 181 | 1.37 | 0.13 | 13.2 | 8.2 | 19.3 | 1.9 | ||
Probable | 1.06 | 0.50 | 152 | 1.23 | 0.09 | 17.0 | 5.2 | 13.1 | 0.9 | |||
Subtotal P&P | 2.48 | 0.38 | 168 | 1.31 | 0.11 | 30.2 | 13.4 | 32.4 | 2.8 | |||
DCG | Proven | 0.15 | 1.64 | 44 | 0.46 | 8.0 | 0.2 | 0.7 | ||||
Probable | 0.21 | 1.40 | 25 | 1.53 | 9.6 | 0.2 | 3.3 | |||||
Subtotal P&P | 0.36 | 1.50 | 33 | 1.08 | 17.6 | 0.4 | 3.9 | |||||
KP | Proven | |||||||||||
Probable | 0.21 | 0.66 | 158 | 1.12 | 2.20 | 4.4 | 1.1 | 2.3 | 4.5 | |||
Subtotal P&P | 0.21 | 0.66 | 158 | 1.12 | 2.20 | 4.4 | 1.1 | 2.3 | 4.5 | |||
Ying | Proven | 10.41 | 0.15 | 179 | 2.71 | 0.87 | 0.04 | 50.8 | 59.9 | 282.0 | 90.4 | 3.9 |
Probable | 8.66 | 0.20 | 167 | 2.19 | 0.71 | 0.03 | 56.3 | 46.6 | 190.1 | 61.7 | 2.7 | |
Total P&P | 19.08 | 0.17 | 174 | 2.47 | 0.80 | 0.04 | 107.1 | 106.5 | 472.1 | 150.2 | 6.7 | |
Notes to Mineral Reserve Statement:
- Cut‐off grades (AgEq g/t): SGX – 180 Resuing, 155 Shrinkage; HZG – 150 Resuing, 130 Shrinkage; HPG – 195 Resuing (2.10 AuEq), 175 Shrinkage (1.90 AuEq); TLP – 160 Resuing, 135 Shrinkage; LME – 170 Resuing, 145 Shrinkage, 145 Room & Pillar; LMW – 170 Resuing, 150 Shrinkage, 150 Longhole, 150 Room & Pillar (1.8 g/t AuEq); DCG – 220 Resuing, 195 Shrinkage; KP ‑ 225 Resuing, 205 Shrinkage.
- Stope Marginal cut‐off grades (AgEq g/t): SGX – 155 Resuing, 130 Shrinkage; HZG – 130 Resuing, 110 Shrinkage; HPG – 165 Resuing (1.80 AuEq), 145 Shrinkage (1.60 AuEq); TLP – 230 Resuing, 1.95 Shrinkage; LME – 135 Resuing, 105 Shrinkage, 105 Room & Pillar; LMW ‑ 135 Resuing, 110 Shrinkage, 110 Longhole, 110 Room & Pillar (1.35 AuEq); DCG – 145 Resuing, 125 Shrinkage.
- Development Ore cut-off grades (AgEq g/t): SGX – 100; HZG – 80; HPG – 115; TLP – 90; LME – 80; LMW – 90; DCG – 90; KP – 95.
- Unplanned dilution (zero grade) assumed as 0.05 m on each wall of a resuing stope and 0.10 m on each wall of a shrinkage stope.
20% unplanned dilution assumed for LMW longhole.27% ,31% , and62% average dilution assumed for Room & Pillar at LME, LMW, and KP, respectively. - Mining recovery factors assumed as
95% for resuing and92% for shrinkage, room and pillar, and longhole. - Metal prices: gold
US /troy oz, silver$2,800 US /troy oz, lead$28.00 US /lb, zinc$0.90 US /lb, copper$1.20 US /lb.$4.40 - Processing recovery factors: SGX –
61.3% Au,95.6% Ag,96.4% Pb,70.1% Zn,90.80% Cu; HZG –62.2% Au,95.6% Ag,88.4% Pb,96.2% Cu; HPG –91.0% Au,88.8% Ag,90.1% Pb,66.0% Zn,93.8% Cu; TLP –61.8% Au;92.8% Ag,89.6% Pb,88.0% Cu; LME –53.3% Au,95.2% Ag,87.2% Pb,37.1% Zn,87.2% Cu; LMW –87.2% Au,95.4% Ag,93.3% Pb,93.8% Cu; DCG –75.9% Au,81.4% Ag,73.8% Pb,69.2% Cu; KP –75.9% Au,81.4% Ag,73.8% Pb,68.0% Zn,69.2% Cu. - Payables: Au –
85% ; Ag –94.5% ; Pb –99.0% ; Zn –76.0% , Cu –40.0% . - Exchange rate assumed is
RMB 7 .00:US .$1.00 - Numbers may not compute exactly due to rounding.
The sensitivity of the Ying Mineral Reserves to variation in COG has been tested by applying a
Total Ying Mineral Reserve tonnes are approximately
Some significant aspects of a comparison of Mineral Reserve estimates between June 30, 2024 (previous Technical Report) and December 31, 2025 (Ying 2025 Technical Report) are the following:
50% increase in total (Proven + Probable) Ying Mineral Reserve tonnes:45% increase in Proven Mineral Reserves and55% increase in Probable Mineral Reserves.1% increase in Ying Mineral Reserve Au grade and reductions of20% ,23% , and17% in Ag, Pb, and Zn grades, respectively. Increase in Ag, Au, Pb, and Zn metal content of20% ,52% ,16% , and22% , respectively.- SGX continues to be the leading contributor to the total Ying Mineral Reserves, accounting for
38% of tonnes,44% of Ag,9% of Au,59% of Pb, and87% of Zn, compared to respective values of42% ,6% ,44% ,58% , and90% in the previous Technical Report. 34% increase in Mineral Reserve tonnes at SGX.77% increase in Au grade and11% ,12% and12% reductions in Ag, Pb, and Zn grades, respectively. Increases in Ag, Au, Pb, and Zn metal content of19% ,138% ,19% , and18% , respectively.- TLP remains the second largest contributor to total Ying Mineral Reserves, with
18% of tonnes,19% of Ag, and20% of Pb. 21% increase in Mineral Reserve tonnes at TLP.22% decrease in both Ag and Pb grades, with a6% reduction in both Ag and Pb metal content.- LMW remains the third largest contributor to total Ying Mineral Reserves, with
13% of tonnes,13% of Ag,28% of Ag,70% of Pb, and42% of Cu. 48% increase in Mineral Reserve tonnes at LMW.77% increase in Au grade, with32% and36% reductions in Ag and Pb grades, respectively. Increases in Ag and Au metal content of1% and162% , respectively; decrease in lead metal content of6% .40% of Ying total Mineral Reserves Au metal at HPG.- First Mineral Reserves of 0.21 Mt at KP.
- In terms of AgEq metal in total Ying Mineral Reserves, approximate respective contributions are Ag
67% , gold6% , lead22% , zinc5% , and copper1% . - In total Ying Mineral Reserves, SGX, TLP, LME, LMW, HPG, HZG, DCG, and KP contribute
47% ,16% ,12% ,12% ,6% ,1% , and1% of AgEq metal, respectively.
Table 4 summarizes projected LOM production for the Ying operations based on the 31 December 2025 Mineral Reserve estimates.
Table 4. Ying Mining District LOM production profile
Ying Mine | FY | FY | FY | FY | FY | FY | FY | FY | FY | FY | FY | FY | FY | FY | FY | FY | FY | Total |
Production | 278 | 1,308 | 1,503 | 1,644 | 1,616 | 1,600 | 1,584 | 1,552 | 1,516 | 1,374 | 1,261 | 1,166 | 830 | 559 | 550 | 474 | 302 | 19,119 |
Au (g/t) | 0.24 | 0.24 | 0.24 | 0.30 | 0.26 | 0.21 | 0.20 | 0.17 | 0.18 | 0.11 | 0.12 | 0.12 | 0.07 | 0.02 | 0.01 | 0.01 | 0.00 | 0.18 |
Ag (g/t) | 169 | 177 | 181 | 176 | 177 | 179 | 174 | 173 | 169 | 170 | 164 | 152 | 165 | 194 | 192 | 183 | 166 | 174 |
Pb (%) | 2.29 | 2.38 | 2.32 | 2.24 | 2.15 | 2.36 | 2.42 | 2.48 | 2.54 | 2.55 | 2.54 | 2.54 | 2.84 | 2.89 | 3.30 | 2.92 | 2.49 | 2.47 |
Zn (%) | 0.50 | 0.57 | 0.69 | 0.72 | 0.61 | 0.76 | 0.67 | 0.74 | 0.72 | 0.69 | 0.86 | 0.78 | 1.14 | 1.47 | 1.56 | 1.24 | 1.08 | 0.79 |
Cu (%) | 0.06 | 0.06 | 0.05 | 0.05 | 0.05 | 0.04 | 0.04 | 0.03 | 0.03 | 0.03 | 0.04 | 0.02 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.03 |
AgEq (g/t) | 252 | 264 | 270 | 268 | 261 | 266 | 260 | 258 | 256 | 250 | 247 | 235 | 254 | 287 | 296 | 271 | 241 | 260 |
Ag (t) | 47 | 232 | 272 | 290 | 285 | 286 | 276 | 268 | 257 | 234 | 207 | 178 | 137 | 109 | 106 | 87 | 50 | 3,320 |
Notes: | |
1. | Numbers may not compute exactly due to rounding. |
2. | Low zinc grades with minimal value not included for HZG, TLP, LME, LMW, and DCG. |
3. | DCG mine plan includes ~ 40kt of Inferred Resources – not material to Ying Mineral Reserves. |
4. | Other very minor and non-material differences between schedule and Mineral Reserves. |
Economic analysis
A high-level economic analysis shows the potential economic impact relative to the latest Mineral Reserve estimations and the associated production schedules. The following Ying realized selling metal prices (Ying averages over projected LOM except where stated), average costs, and exchange rate were used for the economic analysis (all values in $US):
• Gold price / troy ounce | |
• Silver price / troy ounce | |
• Lead price/lb | |
• Zinc price/lb | |
• Copper price/lb | |
• Mining cost/t | |
• Milling cost/t | |
• Shipping cost/t | |
• Mineral Resources tax & rights royalty/t | |
• G&A/t | |
• Government fees and other taxes/t | |
• Sustaining and growth capital/t | |
• Exchange rate |
The QP notes the following about the above economic parameters:
- Ying realized metal prices are as per Silvercorp advice and assume the following $US market prices:
Gold/oz: FY2026Q4,$4,000 FY2027,$3,500 remaining LOM$2,800
Silver/oz: FY2026Q4,$80 FY2027,$50 FY2028,$40 remaining LOM$28
Lead/lb:$0.90
Zinc/lb:$1.20
Copper/lb:$4.40 - Other than for FY2026Q4 / FY2027 for gold, and FY2026Q4 / FY2027 / FY2028 for silver, the above market prices are as per those used in the mining COG calculations.
The QP also notes that approximate spot metal prices at the time of writing of the Technical Report are: gold -
Based on the LOM production profile and the metal price and other assumptions shown above, pre‑tax and post-tax cashflow projections have been generated. At a
The Ying mine complex is seen to be a very viable operation with a projected LOM through to 2042 based on Proven and Probable Mineral Reserves. There remains significant potential to extend the LOM beyond 2042 via further exploration and development, particularly in areas with identified Inferred Resources.
Qualified Persons
The eleven authors of the Technical Report are independent Qualified Persons (QPs). Six of the authors have visited the Ying Property. The latest visit, by AMC QPs Mr HA Smith, Mr RJ Chesher, and Mr JE Glanvill, was in May 2026. The immediately preceding AMC visit, by Mr HA Smith, Mr S Robinson, Mr RJ Chesher, and Mr D Claffey, was in February 2024. The latest AMC visit by Dr GK Vartell was in July 2016. During the site visits, aspects of the project have been examined by the QPs, including drill core, exploration sites, underground workings, processing plant, laboratory, tailings management facilities, and other surface infrastructure.
The Ying 2025 Technical Report will be made available for review on the SEDAR+ system and on the Company's website at www.silvercorpmetals.com within 45 days of this news release.
HA Smith, P.Eng., GK Vartell, P.Geo., S Robinson, P.Geo., RC Stewart, P.Geo. of AMC Mining Consultants (
About Silvercorp
Silvercorp is a Canadian mining company producing silver, gold, lead, and zinc with a long history of profitability and growth potential. The Company's strategy is to create shareholder value by 1) focusing on generating free cashflow from long life mines; 2) organic growth through extensive drilling for discovery; 3) ongoing merger and acquisition efforts to unlock value; and 4) long term commitment to responsible mining and ESG. For more information, please visit our website at www.silvercorpmetals.com.
For further information:
Silvercorp Metals Inc.
Lon Shaver, President
Phone: (604) 669‐9397
Toll Free 1(888) 224‐1881
Email: investor@silvercorp.ca
Website: www.silvercorpmetals.com
CAUTIONARY DISCLAIMER ‐ FORWARD‐LOOKING STATEMENTS
Certain of the statements and information in this news release constitute "forward‐looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward‐looking information" within the meaning of applicable Canadian provincial securities laws (collectively, "forward‐looking statements"). Any statements or information that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, using words or phrases such as "expects", "is expected", "anticipates", "believes", "plans", "projects", "estimates", "assumes", "intends", "strategies", "targets", "goals", "forecasts", "objectives", "budgets", "schedules", "potential" or variations thereof or stating that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved, or the negative of any of these terms and similar expressions) are not statements of historical fact and may be forward‐ looking statements. Forward‐looking statements relate to, among other things: the price of silver and other metals; foreign exchange rates; the accuracy of mineral resource and mineral reserve estimates at the Company's material properties; projected amount of ounces of silver to be mined at the Ying Property; estimated mine life, potential to expand mine life and any anticipated changes related thereto; the sufficiency of the Company's capital to finance the Company's operations; estimates of revenues, operation costs, capital expenditures, mine plan, and estimated production from the Company's mines in the Ying Mining District; future mining methods and use of equipment; timing of receipt of permits and regulatory approvals; availability of funds from production to finance the Company's operations; and access to and availability of funding for future construction, use of proceeds from any financing and development of the Company's properties.
Forward‐looking statements are subject to a variety of known and unknown risks, uncertainties and other factors that could cause actual events or results to differ from those reflected in the forward‐looking statements, including, without limitation, risks relating to: fluctuating commodity prices; calculation of resources, reserves and mineralization and precious and base metal recovery; interpretations and assumptions of mineral resource and mineral reserve estimates; exploration and development programs; feasibility and engineering reports; all necessary permits, licenses and regulatory approvals for our operations are received in a timely manner;; title to properties; property interests; joint venture partners; acquisition of commercially mineable mineral rights; financing; recent market events and conditions; economic factors affecting the Company; timing, estimated amount, capital and operating expenditures and economic returns of future production; integration of acquisitions into the Company's existing operations; competition; operations and political conditions; regulatory environment in China, Canada, the United States, Ecuador and Kyrgyzstan; our ability to comply with environmental, health and safety laws; environmental risks; foreign exchange rate fluctuations; insurance; risks and hazards of mining operations; key personnel; conflicts of interest; dependence on management; internal control over financial reporting; and bringing actions and enforcing judgments under U.S. securities laws.
This list is not exhaustive of the factors that may affect any of the Company's forward‐looking statements. Forward‐ looking statements are statements about the future and are inherently uncertain, and actual achievements of the Company or other future events or conditions may differ materially from those reflected in the forward‐looking statements due to a variety of risks, uncertainties and other factors, including, without limitation, those referred to in the Company's Annual Information Form under the heading "Risk Factors". Although the Company has attempted to identify important factors that could cause actual results to differ materially, there may be other factors that cause results not to be as anticipated, estimated, described or intended. Accordingly, readers should not place undue reliance on forward‐looking statements.
The Company's forward‐looking statements are based on the assumptions, beliefs, expectations and opinions of management as of the date of this news release, and other than as required by applicable securities laws, the Company does not assume any obligation to update forward‐looking statements if circumstances or management's assumptions, beliefs, expectations or opinions should change, or changes in any other events affecting such statements. For the reasons set forth above, investors should not place undue reliance on forward‐looking statements.
CAUTIONARY NOTE TO US INVESTORS
The technical and scientific information contained herein has been prepared in accordance with NI 43‐101 and the Canadian Institute of Mining, Metallurgy and Petroleum classification system, which differs significantly from the standards adopted by the U.S. Securities and Exchange Commission (the "SEC"). Accordingly, the technical and scientific information contained herein, including any estimates of mineral reserves and mineral resources, may not be comparable to similar information disclosed by U.S. companies subject to the disclosure requirements of the SEC. In particular, and without limiting the generality of the foregoing, this news release uses the terms "measured resources," "indicated resources" and "inferred resources" as defined in accordance with NI 43-101 and the CIM Standards.
Further to recent amendments, mineral property disclosure requirements in the United States (the "U.S. Rules") are governed by subpart 1300 of Regulation S-K of the U.S. Securities Act of 1933, as amended (the "U.S. Securities Act") which differ from the CIM Standards. As a foreign private issuer that is eligible to file reports with the SEC pursuant to the multi-jurisdictional disclosure system (the "MJDS"), the Company is not required to provide disclosure on its mineral properties under the U.S. Rules and will continue to provide disclosure under NI 43-101 and the CIM Standards. If the Company ceases to be a foreign private issuer or loses its eligibility to file its annual report on Form 40-F pursuant to the MJDS, then the Company will be subject to the U.S. Rules, which differ from the requirements of NI 43-101 and the CIM Standards.
Pursuant to the new U.S. Rules, the SEC recognizes estimates of "measured mineral resources", "indicated mineral resources" and "inferred mineral resources." In addition, the definitions of "proven mineral reserves" and "probable mineral reserves" under the U.S. Rules are now "substantially similar" to the corresponding standards under NI 43-101. Mineralization described using these terms has a greater amount of uncertainty as to its existence and feasibility than mineralization that has been characterized as reserves. Accordingly, U.S. investors are cautioned not to assume that any measured mineral resources, indicated mineral resources, or inferred mineral resources that the Company reports are or will be economically or legally mineable. Further, "inferred mineral resources" have a greater amount of uncertainty as to their existence and as to whether they can be mined legally or economically. Under Canadian securities laws, estimates of "inferred mineral resources" may not form the basis of feasibility or pre-feasibility studies, except in rare cases. While the above terms under the U.S. Rules are "substantially similar" to the standards under NI 43-101 and CIM Standards, there are differences in the definitions under the U.S. Rules and CIM Standards. Accordingly, there is no assurance any mineral reserves or mineral resources that the Company may report as "proven mineral reserves", "probable mineral reserves", "measured mineral resources", "indicated mineral resources" and "inferred mineral resources" under NI 43-101 would be the same had the Company prepared the reserve or resource estimates under the standards adopted under the U.S. Rules.
Additional information relating to the Company, including Silvercorp's Annual Information Form, can be obtained under the Company's profile on SEDAR+ at www.sedarplus.ca on EDGAR at www.sec.gov, and on the Company's website at www.silvercorpmetals.com
View original content to download multimedia:https://www.prnewswire.com/news-releases/silvercorp-reports-a-mineral-reserve-increase-of-50-in-tonnes-and-20-in-silver-ounces-for-the-ying-mining-district-302798801.html
SOURCE Silvercorp Metals Inc.