T1 Energy Announces Preliminary Results for Third Quarter 2025
Rhea-AI Summary
T1 Energy (NYSE: TE) reported preliminary Q3 2025 results on Oct 22, 2025: total net sales $200–$210M on ~725 MW of module shipments and maintained full-year 2025 EBITDA guidance $25–$50M. At Sept 30, 2025 the company held $87M cash and restricted cash ($34M unrestricted) and has accrued $92M of Section 45X tax credits.
T1 confirmed a phased G2_Austin build: Phase 1 = 2.1 GW, capex $400–$425M, construction start planned Q4 2025, production start Q4 2026. Company recorded a $53M non-cash intangible impairment tied to an offtake dispute and expects deferred Q3 volumes to ship in Q4 2025.
Positive
- Q3 sales of $200–$210M on ~725 MW
- $92M accrued Section 45X tax credits
- G2 Phase 1 capacity 2.1 GW; capex $400–$425M
- Projected run-rate EBITDA $375–$450M at 5 GW + 2.1 GW
Negative
- Maintained 2025 EBITDA guidance skewed to low-end $25–$50M
- Recorded $53M non-cash intangible impairment
- $34M unrestricted cash at Sept 30, 2025
News Market Reaction
On the day this news was published, TE declined 8.26%, reflecting a notable negative market reaction. Argus tracked a trough of -27.5% from its starting point during tracking. Our momentum scanner triggered 43 alerts that day, indicating elevated trading interest and price volatility. This price movement removed approximately $68M from the company's valuation, bringing the market cap to $755M at that time. Trading volume was very high at 3.4x the daily average, suggesting heavy selling pressure.
Data tracked by StockTitan Argus on the day of publication.
AUSTIN, Texas and NEW YORK, Oct. 22, 2025 (GLOBE NEWSWIRE) -- T1 Energy Inc. (NYSE: TE) (“T1,” “T1 Energy,” or the “Company”) has announced preliminary financial and operating results for the third quarter 2025.
Preliminary Third Quarter 2025 Results Overview
- Total Net Sales/Modules Sales Volumes: T1 generated total net sales for the third quarter of
$200 -$210 million on modules sales of approximately 725 MW. - Maintaining 2025 EBITDA guidance range of
$25 -$50 million . In Q4 2025, T1 expects a significant increase in sales related to the highest expected production year-to-date at G1_Dallas, as well as policy driven inventory sales from modules produced in Q3 2025. - Cash, restricted cash and Section 45X tax credits. At September 30, 2025, T1 had cash, cash equivalents, and restricted cash of
$87 million , of which$34 million was unrestricted cash. In addition, T1 has accrued$92 million of Section 45X credits year-to-date that the Company expects to monetize.
Business Update and Guidance
- Updating G2_Austin phased development plan and initiating G2 Phase 1 EBITDA guidance. As mentioned in T1’s Q2 2025 earnings release, the company has decided to develop its planned G2_Austin U.S. PV solar cell manufacturing facility in two phases. Each phase is a standalone development with limited shared infrastructure; T1 is positioned to flex capacity to add up to three phases potentially totaling as many as 8 GW on T1’s existing Austin leasehold. The rationale behind the phased development approach is to match planned capacity with long-term offtake contracts; advance capital formation initiatives; and start production in Q4 2026 to address robust customer demand. Following the initial completion of detailed project engineering, the first phase of G2_Austin is now expected to total 2.1 GW of annual production capacity with an estimated capital expenditure of
$400 -$425 million . The estimated annual run-rate EBITDA from G1_Dallas operating at 5 GW capacity with the first 2.1 GW phase of G2_Austin fully online is$375 -$450 million . T1 expects to start G2 Phase 1 construction in Q4 2025 with planned start of production in Q4 2026. - Capital formation enables Q4 start of construction at G2. As previously disclosed, T1 entered a
$100 million commitment for the issuance of preferred stock to certain funds and accounts managed by Encompass Capital Advisors LLC in connection with T1’s acquisition of Trina Solar’s US manufacturing assets. T1 has elected to make the second and final draw of$50 million pursuant this$100 million commitment. With the expected proceeds from this preferred stock tranche and in conjunction with the progress T1 is making on parallel capital formation initiatives, the Company plans to start initial construction and to potentially order longer lead time items of its G2_Austin U.S. PV solar cell manufacturing facility in Q4 2025. - Section 232 and U.S. policy summary. T1 supports the recently announced investigation by the U.S. Secretary of Commerce into the use of foreign-sourced polysilicon and polysilicon derivatives under Section 232. T1 Energy’s contract to purchase hyper-pure polysilicon would likely be advantaged by any potential tariffs or import restrictions that result from this case. In addition, T1 continues to advance its near-term priority to ensure eligibility for section 45X tax credits in 2026 and beyond. The Company continues to make progress and expects to be compliant by year-end.
- Maintaining 2025 EBITDA guidance of
$25 -$50 million . T1’s 2025 full-year EBITDA guidance of$25 -$50 million is unchanged. The forecast, which continues to skew towards the low-end of the range, is based on a mix shift towards merchant sales agreements in H2 2025, the emergence of near-term uncertainties related to implementation of AD/CVDs, reciprocal tariffs, supply chain impacts, and customer safe harboring backlogs. In Q4 2025, T1 expects a significant increase in sales related to the highest expected production year-to-date at G1_Dallas, and policy driven inventory sales before year-end from modules produced in Q3 2025. T1’s guidance range assumes 2025 G1_Dallas production of 2.6 – 3.0 GW. There are no changes to T1’s projected$650 -$700 million annual run-rate EBITDA estimate based on 5 GW of annual optimized and integrated production at G1_Dallas and G2_Austin. - Offtake contract negotiation. T1 is involved in a potential dispute with one of its long-term supply offtake customers that reduced expected sales volumes in Q3 2025. The Company expects that the deferred third quarter sales volumes under this contract will be recognized in the fourth quarter of 2025. While T1 continues to negotiate with the counterparty to achieve a resolution, the Company believes it has a strong position under the contract and will evaluate all options. As a result of the potential dispute, T1 is recording a non-cash impairment to intangible assets of
$53 million .
“T1 Energy continued to make meaningful strides during the third quarter to build our American solar supply chain and provide scalable, reliable, low-cost energy,” commented Dan Barcelo, T1’s Chief Executive Officer and Chairman of the Board. “With our expanding U.S. partnership network, highlighted by recent agreements with companies like Hemlock, Corning, Talon and Nextracker, we are investing in domestic advanced manufacturing to power America.”
The financial and operational information in this press release is selected, preliminary, estimated unaudited financial information for the three months ended September 30, 2025. These estimates have been prepared by, and are the responsibility of, management and have not been reviewed by the Company’s independent registered accounting firm. The preliminary financial and operational information set forth above is based solely on information available to the management of the Company as of the date hereof and is subject to change. The actual financial results of the Company for the quarter ended September 30, 2025, may differ (and such differences may be material) from these preliminary estimates due to the completion of the Company’s quarterly financial closing procedures. The preliminary estimates presented above are subject to final adjustments and other developments that may arise between the date hereof and the time that the results for the quarter ended September 30, 2025 for the Company are finalized, and are not intended to be a comprehensive statement of our financial or operational results for the three months ended September 30, 2025. Accordingly, you should not place undue reliance on this preliminary estimated financial information, as it may differ materially from the actual results.
About T1 Energy
T1 Energy Inc. (NYSE: TE) is an energy solutions provider building an integrated U.S. supply chain for solar and batteries. In December 2024, T1 completed a transformative transaction, positioning the Company as one of the leading solar manufacturing companies in the U.S., with a complementary solar and battery storage strategy. Based in the U.S. with plans to expand its operations in America, the Company is also exploring value optimization opportunities across its portfolio of assets in Europe.
To learn more about T1, please visit www.T1energy.com and follow on social media.
Investor contact:
Jeffrey Spittel
EVP, Investor Relations and Corporate Development
jeffrey.spittel@T1energy.com
Tel: +1 409 599-5706
Media contact:
Russell Gold
EVP, Strategic Communications
russell.gold@T1energy.com
Tel: +1 214 616-9715
Cautionary Statement Concerning Forward-Looking Statements:
This press release contains forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. All statements contained in this press release that do not relate to matters of historical fact should be considered forward-looking statements, including without limitation with respect to the Company’s financial and operational performance and profitability, the G2_Austin phased development plan and associated G2 Phase 1 EBITDA guidance, the expected plans and benefits of such development plans, the expectation to bring the project online in Q4 2026 to address robust customer demand, the expected first phase of G2_Austin annual production capacity of 2.1GW total, with an estimated capital expenditure of
T1 intends to use its website as a channel of distribution to disclose information which may be of interest or material to investors and to communicate with investors and the public. Such disclosures will be included on T1’s website in the ‘Investor Relations’ section. T1 also intends to use certain social media channels, including, but not limited to, X and LinkedIn, as means of communicating with the public and investors about T1, its progress, products, and other matters. While not all the information that T1 posts to its digital platforms may be deemed to be of a material nature, some information may be. As a result, T1 encourages investors and others interested to review the information that it posts and to monitor such portions of T1’s website and social media channels on a regular basis, in addition to following T1’s press releases, SEC filings, and public conference calls and webcasts. The contents of T1’s website and other social media channels shall not be deemed incorporated by reference in any filing under the Securities Act of 1933, as amended.