TC Energy commences collection of tolls on Southeast Gateway pipeline
TC Energy (NYSE:TRP) has announced the commencement of toll collection from the Comisión Federal de Electricidad (CFE) for its Southeast Gateway pipeline, with May payments received on schedule. The 1.3 Bcf/d, 715-kilometre natural gas pipeline was completed at US$3.9 billion, approximately 13% under the original cost estimate.
The project, completed in less than three years, represents the first major energy infrastructure project under TC Energy's public-private partnership with CFE. The pipeline is strategically positioned to support Mexico's plans to add 8.5 gigawatts of new natural gas power plant capacity, contributing to the country's energy security and economic development.
TC Energy (NYSE:TRP) ha annunciato l'inizio della riscossione dei pedaggi dalla Comisión Federal de Electricidad (CFE) per il suo gasdotto Southeast Gateway, con i pagamenti di maggio ricevuti puntualmente. Il gasdotto di 1,3 Bcf/giorno e 715 chilometri è stato completato con un costo di 3,9 miliardi di dollari USA, circa il 13% inferiore alla stima iniziale.
Il progetto, realizzato in meno di tre anni, rappresenta il primo grande intervento infrastrutturale energetico nell'ambito della partnership pubblico-privata tra TC Energy e CFE. Il gasdotto è posizionato strategicamente per supportare i piani del Messico di aggiungere 8,5 gigawatt di nuova capacità per centrali a gas naturale, contribuendo alla sicurezza energetica e allo sviluppo economico del Paese.
TC Energy (NYSE:TRP) ha anunciado el inicio de la cobranza de peajes a la Comisión Federal de Electricidad (CFE) por su gasoducto Southeast Gateway, con los pagos de mayo recibidos puntualmente. El gasoducto de gas natural de 1,3 Bcf/d y 715 kilómetros se completó con un costo de 3.900 millones de dólares, aproximadamente un 13% por debajo del presupuesto original.
El proyecto, finalizado en menos de tres años, representa la primera gran infraestructura energética bajo la asociación público-privada de TC Energy con CFE. El gasoducto está estratégicamente ubicado para apoyar los planes de México de añadir 8,5 gigavatios de nueva capacidad en plantas de energía a gas natural, contribuyendo a la seguridad energética y al desarrollo económico del país.
TC Energy (NYSE:TRP)는 Southeast Gateway 파이프라인에 대한 Comisión Federal de Electricidad (CFE)의 통행료 징수를 시작했다고 발표했으며, 5월 지불금도 예정대로 수령했습니다. 일일 1.3 Bcf, 길이 715킬로미터의 천연가스 파이프라인은 39억 달러의 비용으로 완공되었으며, 이는 원래 예상 비용보다 약 13% 낮은 금액입니다.
3년 미만의 기간에 완공된 이 프로젝트는 TC Energy와 CFE 간의 민관 협력 하에 진행된 첫 번째 주요 에너지 인프라 사업입니다. 이 파이프라인은 멕시코가 8.5기가와트의 신규 천연가스 발전소 용량을 추가하려는 계획을 지원하며, 국가의 에너지 안보와 경제 발전에 기여할 전략적 위치에 있습니다.
TC Energy (NYSE:TRP) a annoncé le début de la perception des péages auprès de la Comisión Federal de Electricidad (CFE) pour son pipeline Southeast Gateway, avec les paiements de mai reçus comme prévu. Le gazoduc de 1,3 Bcf/jour et de 715 kilomètres a été achevé pour 3,9 milliards de dollars US, soit environ 13 % de moins que l'estimation initiale des coûts.
Le projet, achevé en moins de trois ans, représente la première grande infrastructure énergétique dans le cadre du partenariat public-privé entre TC Energy et la CFE. Le pipeline est stratégiquement situé pour soutenir les plans du Mexique visant à ajouter 8,5 gigawatts de nouvelle capacité de centrales électriques au gaz naturel, contribuant ainsi à la sécurité énergétique et au développement économique du pays.
TC Energy (NYSE:TRP) hat den Beginn der Mauterhebung von der Comisión Federal de Electricidad (CFE) für seine Southeast Gateway-Pipeline bekannt gegeben, wobei die Zahlungen für Mai planmäßig eingegangen sind. Die 1,3 Bcf/d und 715 Kilometer lange Erdgasleitung wurde für 3,9 Milliarden US-Dollar fertiggestellt, was etwa 13 % unter der ursprünglichen Kostenschätzung liegt.
Das in weniger als drei Jahren abgeschlossene Projekt stellt das erste große Energieinfrastrukturprojekt im Rahmen der öffentlich-privaten Partnerschaft von TC Energy mit der CFE dar. Die Pipeline ist strategisch positioniert, um Mexikos Pläne zur Hinzufügung von 8,5 Gigawatt neuer Erdgas-Kraftwerkskapazität zu unterstützen und trägt zur Energiesicherheit und wirtschaftlichen Entwicklung des Landes bei.
- Project completed 13% under original cost estimate at US$3.9 billion
- Successfully commenced toll collection with timely payment received from CFE
- Pipeline capacity of 1.3 Bcf/d positions company for Mexico's planned 8.5 GW power expansion
- Completed ahead of schedule in less than 3 years from final investment decision
- Pending regulatory approval from CNE required for potential future interruptible service users
Insights
TC Energy's Southeast Gateway pipeline now collecting tolls, completed 13% under budget at $3.9B, supporting Mexico's energy growth plans.
TC Energy has hit a significant milestone with the commencement of toll collection from Mexico's Comisión Federal de Electricidad (CFE) for the Southeast Gateway pipeline, with the first payment for May already received. The 715-kilometer natural gas pipeline, with 1.3 Bcf/d capacity, was completed at approximately US$3.9 billion – an impressive
The cost efficiency demonstrates exceptional project management capabilities, especially considering the project's scale and complexity. The
This infrastructure asset positions TC Energy strategically in Mexico's energy market, where the government plans to add 8.5 gigawatts of natural gas power generation capacity. As the first major project under TC Energy's public-private partnership with CFE, the successful execution establishes a blueprint for future collaboration in a high-growth market.
The company is still working with the newly formed Comisión Nacional de Energía to obtain regulated rate approvals for potential future interruptible service users beyond CFE, which could create additional revenue streams. The pipeline's completion in less than three years from final investment decision further demonstrates TC Energy's execution capabilities in bringing complex projects online efficiently.
This operational milestone transforms a capital-intensive construction project into a revenue-generating asset with contracted cash flows, improving TC Energy's return on invested capital while supporting Mexico's transition to lower-emission energy sources.
- Final project cost is approximately US
$3.9 billion , 13 per cent under original cost estimate - Supplies affordable, reliable and sustainable natural gas to fuel Mexico’s economic growth
CALGARY, Alberta, June 27, 2025 (GLOBE NEWSWIRE) -- News Release – TC Energy Corporation (TSX, NYSE: TRP) (TC Energy or the Company) today announced that it has commenced the collection of tolls from the Comisión Federal de Electricidad (CFE) for the Southeast Gateway pipeline and has been paid by the CFE for the month of May, on time in accordance with our contract. We continue to work with the newly constituted Comisión Nacional de Energía (CNE) to obtain the approval of our regulated rates as soon as possible, which is required to provide service to potential future interruptible service users on Southeast Gateway other than the CFE.
The Southeast Gateway pipeline, a 1.3 Bcf/d, 715-kilometre natural gas pipeline, was constructed approximately 13 per cent under the original cost estimate in less than three years from the project's final investment decision. Southeast Gateway was the first significant energy infrastructure project constructed under our successful public-private partnership with the CFE.
“The successful completion of the Southeast Gateway pipeline reflects the unwavering commitment of our team, the CFE and the Ministry of Energy (SENER) to support Mexico’s expanding energy demand and future economic development,” said François Poirier, TC Energy’s President and Chief Executive Officer.
To advance Mexico’s economic growth and energy security, the Government of Mexico has announced plans to add approximately 8.5 gigawatts of newly installed capacity from natural gas power plants. The Southeast Gateway pipeline, along with the Company’s other assets in Mexico, is positioned to play a vital role in supporting this initiative and the transition to lower-emission, more reliable energy sources.
About TC Energy
We’re a team of 6,500+ energy problem solvers connecting the world to the energy it needs. Our extensive network of natural gas infrastructure assets is one-of-a-kind. We seamlessly move, generate and store energy and deliver it to where it is needed most, to homes and businesses in North America and across the globe through LNG exports. Our natural gas assets are complemented by our strategic ownership and low-risk investments in power generation.
TC Energy’s common shares trade on the Toronto (TSX) and New York (NYSE) stock exchanges under the symbol TRP. To learn more, visit us at TCEnergy.com.
FORWARD-LOOKING INFORMATION
This release contains certain information that is forward-looking and is subject to important risks and uncertainties (such statements are usually accompanied by words such as "anticipate", "expect", "believe", "may", "will", "should", "estimate", "intend" or other similar words). Forward-looking statements in this document are intended to provide TC Energy security holders and potential investors with information regarding TC Energy and its subsidiaries, including management's assessment of TC Energy's and its subsidiaries' future plans and financial outlook. All forward-looking statements reflect TC Energy's beliefs and assumptions based on information available at the time the statements were made, and as such are not guarantees of future performance. As actual results could vary significantly from the forward-looking information, you should not put undue reliance on forward-looking information and should not use future-oriented information or financial outlooks for anything other than their intended purpose. We do not update our forward-looking information due to new information or future events, unless we are required to by law. For additional information on the assumptions made, and the risks and uncertainties which could cause actual results to differ from the anticipated results, refer to the most recent Quarterly Report to Shareholders and Annual Report filed under TC Energy’s profile on SEDAR+ at www.sedarplus.ca and with the U.S. Securities and Exchange Commission at www.sec.gov.
-30-
Media Inquiries:
Media Relations
media@tcenergy.com
403-920-7859 or 800-608-7859
Investor & Analyst Inquiries:
Gavin Wylie / Hunter Mau
investor_relations@tcenergy.com
403-920-7911 or 800-361-6522
PDF available: http://ml.globenewswire.com/Resource/Download/71eecfb6-0f18-4356-a066-6de39df05b1f