STOCK TITAN

TRX Gold Files NI 43-101 Preliminary Economic Assessment for the Buckreef Gold Project

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Positive)
Tags
TRX Gold has filed a NI 43-101 Technical Report detailing a Preliminary Economic Assessment (PEA) for its Buckreef Gold Project in Tanzania. The PEA outlines a significant expansion plan including: upgrading the process plant to 3,000 tonnes per day and transitioning from open pit to underground mining. The project shows a base case NPV5% of $701M pre-tax ($442M after-tax) at consensus gold prices, with potential to reach $1.18B pre-tax ($766M after-tax) at $3,000/oz gold. Over the 17.6-year mine life, average gold production is projected at 62,000 oz annually, increasing to 80,000 oz in the first five years of underground operations. The expansion requires $89M in growth capital over four years, with anticipated cash costs of $1,024/oz and AISC of $1,206/oz. The project benefits from existing infrastructure and could achieve underground production within 3 years.
TRX Gold ha presentato un Rapporto Tecnico NI 43-101 che dettaglia una Valutazione Economica Preliminare (PEA) per il suo progetto aurifero Buckreef in Tanzania. La PEA descrive un piano di espansione significativo che include: l'aggiornamento dell'impianto di processo a 3.000 tonnellate al giorno e la transizione dall'estrazione a cielo aperto a quella sotterranea. Il progetto mostra un NPV5% base di 701 milioni di dollari pre-tasse (442 milioni di dollari post-tasse) ai prezzi dell'oro concordati, con il potenziale di raggiungere 1,18 miliardi di dollari pre-tasse (766 milioni di dollari post-tasse) a 3.000 dollari/oz di oro. Nel corso della vita utile della miniera di 17,6 anni, la produzione media annua di oro è prevista a 62.000 oz, aumentando a 80.000 oz nei primi cinque anni di operazioni sotterranee. L'espansione richiede 89 milioni di dollari di capitale per la crescita in quattro anni, con costi in contanti previsti di 1.024 dollari/oz e AISC di 1.206 dollari/oz. Il progetto beneficia delle infrastrutture esistenti e potrebbe avviare la produzione sotterranea entro 3 anni.
TRX Gold ha presentado un Informe Técnico NI 43-101 que detalla una Evaluación Económica Preliminar (PEA) para su Proyecto de Oro Buckreef en Tanzania. La PEA describe un plan de expansión significativo que incluye: la mejora de la planta de procesamiento a 3,000 toneladas por día y la transición de minería a cielo abierto a minería subterránea. El proyecto muestra un VPN5% base de $701 millones antes de impuestos ($442 millones después de impuestos) a precios consensuados del oro, con potencial para alcanzar $1.18 mil millones antes de impuestos ($766 millones después de impuestos) a $3,000/oz de oro. Durante la vida útil de la mina de 17.6 años, se proyecta una producción promedio anual de oro de 62,000 oz, aumentando a 80,000 oz en los primeros cinco años de operaciones subterráneas. La expansión requiere $89 millones en capital de crecimiento durante cuatro años, con costos en efectivo anticipados de $1,024/oz y AISC de $1,206/oz. El proyecto se beneficia de la infraestructura existente y podría alcanzar producción subterránea en 3 años.
TRX Gold는 탄자니아 Buckreef 금 프로젝트에 대한 예비 경제성 평가(PEA)를 포함하는 NI 43-101 기술 보고서를 제출했습니다. PEA는 일일 처리량 3,000톤으로 공정 플랜트 업그레이드와 노천 채굴에서 지하 채굴로의 전환을 포함한 대규모 확장 계획을 제시합니다. 이 프로젝트는 합의된 금 가격 기준으로 세전 기준 5% 할인율 순현재가치(NPV)가 7억 1천만 달러(세후 4억 4,200만 달러)이며, 금 가격이 온스당 3,000달러일 경우 최대 11억 8천만 달러(세후 7억 6,600만 달러)까지 도달할 가능성이 있습니다. 17.6년의 광산 수명 동안 연평균 금 생산량은 62,000온스로 예상되며, 지하 채굴 초기 5년 동안은 80,000온스로 증가할 전망입니다. 확장에는 4년간 8,900만 달러의 성장 자본이 필요하며, 예상 현금 비용은 온스당 1,024달러, AISC는 온스당 1,206달러입니다. 이 프로젝트는 기존 인프라를 활용하며 3년 내에 지하 생산을 시작할 수 있을 것으로 보입니다.
TRX Gold a déposé un rapport technique NI 43-101 détaillant une évaluation économique préliminaire (PEA) pour son projet aurifère Buckreef en Tanzanie. La PEA présente un plan d'expansion significatif incluant : la mise à niveau de l'usine de traitement à 3 000 tonnes par jour et la transition de l'exploitation à ciel ouvert à l'exploitation souterraine. Le projet affiche une VAN à 5 % de 701 millions de dollars avant impôts (442 millions après impôts) aux prix consensuels de l'or, avec un potentiel d'atteindre 1,18 milliard de dollars avant impôts (766 millions après impôts) à 3 000 $/oz d'or. Sur la durée de vie de la mine de 17,6 ans, la production moyenne d'or est estimée à 62 000 oz par an, augmentant à 80 000 oz durant les cinq premières années d'exploitation souterraine. L'expansion nécessite 89 millions de dollars de capital de croissance sur quatre ans, avec des coûts en espèces anticipés de 1 024 $/oz et un AISC de 1 206 $/oz. Le projet bénéficie des infrastructures existantes et pourrait démarrer la production souterraine en 3 ans.
TRX Gold hat einen NI 43-101 Technischen Bericht eingereicht, der eine vorläufige wirtschaftliche Bewertung (PEA) für das Buckreef-Goldprojekt in Tansania enthält. Die PEA skizziert einen bedeutenden Expansionsplan, einschließlich: der Aufrüstung der Verarbeitungsanlage auf 3.000 Tonnen pro Tag und dem Übergang vom Tagebau zum Untertagebau. Das Projekt weist einen Basisfall NPV5% von 701 Mio. USD vor Steuern (442 Mio. USD nach Steuern) bei Konsens-Goldpreisen auf, mit Potenzial, bei einem Goldpreis von 3.000 USD/oz auf 1,18 Mrd. USD vor Steuern (766 Mio. USD nach Steuern) zu steigen. Über die 17,6-jährige Lebensdauer der Mine wird eine durchschnittliche Goldproduktion von 62.000 Unzen pro Jahr erwartet, die in den ersten fünf Jahren des Untertageabbaus auf 80.000 Unzen ansteigt. Die Expansion erfordert 89 Mio. USD Wachstumskapital über vier Jahre, mit erwarteten Cash-Kosten von 1.024 USD/oz und einem AISC von 1.206 USD/oz. Das Projekt profitiert von bestehender Infrastruktur und könnte innerhalb von 3 Jahren Untertageproduktion erreichen.
Positive
  • Strong NPV5% of $701M pre-tax ($442M after-tax) with upside potential to $1.18B pre-tax at higher gold prices
  • Significant 17.6-year mine life with average production of 62,000 oz Au annually
  • Higher production of 80,000 oz Au annually in first 5 years of underground operations
  • Expansion can be financed through internal cash flow without upfront capital requirement
  • Competitive AISC of $1,206/oz Au and cash costs of $1,024/oz Au
  • Existing infrastructure reduces time to production and capital requirements
Negative
  • Substantial capital requirements of $89M over next four years for expansion
  • Total LOM capital requirements of $359M including growth and sustaining capital
  • Transition risk from open pit to underground mining operations
  • Project dependent on gold price assumptions for profitability

Insights

TRX Gold's PEA shows strong economics with $442M after-tax NPV, 62,000 oz annual production, and manageable capital requirements.

TRX Gold's Preliminary Economic Assessment (PEA) for the Buckreef Gold Project in Tanzania presents a compelling economic case for the planned expansion. The study examines a two-pronged approach: upgrading the existing process plant to handle 3,000 tonnes per day and transitioning from open pit to underground mining over the next 2-3 years.

The financial metrics are particularly noteworthy. At consensus gold price forecasts, the project shows a pre-tax NPV5% of $701 million and after-tax NPV5% of $442 million. The upside case at $3,000/oz gold projects even stronger returns with pre-tax NPV5% of $1.18 billion and after-tax NPV5% of $766 million. Interestingly, there's no quoted Internal Rate of Return (IRR) since the company plans to finance the expansion from internally generated cash flow without requiring significant upfront capital.

Production metrics indicate a 17.6-year mine life processing 18.1 million tonnes of ore at an average grade of 2.14 g/t gold. Annual production is expected to average 62,000 ounces, with higher production of over 80,000 ounces during the first five years of underground operations. Cost structures appear competitive with industry standards, showing life-of-mine cash costs of $1,024/oz and all-in sustaining costs (AISC) of $1,206/oz.

The capital requirements are structured in phases, with $89 million in growth capital needed over the next four years, followed by additional investments throughout the mine life. The total life-of-mine capital expenditure is projected at $359 million, including both growth and sustaining capital.

What's particularly advantageous is the existing infrastructure. With an operating open-pit mine and processing facility already in place, the company expects to achieve underground production within three years, significantly reducing development time and initial capital needs. The resource base supporting this plan includes 10.8 million tonnes of Measured and Indicated resources at 2.57 g/t gold (893,000 oz) and 9.1 million tonnes of Inferred resources at 2.47 g/t gold (726,000 oz).

This PEA represents a significant milestone for TRX Gold, demonstrating a viable path toward expanded production with strong economics and a manageable capital profile.

TORONTO, May 27, 2025 (GLOBE NEWSWIRE) -- RX Gold Corporation (TSX: TRX) (NYSE American: TRX) (the “Company” or “TRX Gold”) has filed on SEDAR+ a Technical Report prepared in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) on the Buckreef Gold Project (“Buckreef Gold”), titled Preliminary Economic Assessment and Updated Mineral Resource Estimate of the Buckreef Gold Mine Project, Tanzania (“PEA”). The PEA supports disclosure made by the Company in its news release dated April 22nd, 2025, titled “TRX Gold Reports Robust PEA On Next Buckreef Gold Expansion”. There are no material differences in the PEA from those results disclosed in the April 22nd, 2025, news release.

Buckreef Gold PEA Highlights:

  • The PEA evaluated the following scenario: (i) an expansion and upgrade of the existing process plant at Buckreef Gold to 3,000 tonnes per day (“tpd”); and (ii) a transition from open pit mining to underground mining over the next 2-3 years.
  • Base case NPV5% of US$701 million pre-tax, or US$442 million after tax at consensus forecast case gold prices (US$2,707/oz year 1, US$2,646/oz year 2, US$2,495/oz year 3, US$2,400/oz year 4, US$2,245/oz thereafter) and NPV5% of US$1,181 million pre-tax, or US$766 million after tax at an upside US$3,000/oz gold price sensitivity;
  • The PEA demonstrates the Company’s ability to potentially finance the expansion from internally generated cash flow without an upfront capital requirement, thus there is no quoted Internal Rate of Return;
  • Over a 17.6-year period, the total process plant throughput is expected to be 18.1 million tonnes averaging 2.14 g/t Au with average recovered gold production of approximately 62,000 oz Au per annum. During the first five years of the underground operation, average recovered production is planned to be over 80,000 oz Au per annum;
  • Life of Mine (“LOM”) cash costs average US$1,024/oz Au and all-in sustaining costs (“AISC”) average of US$1,206/oz Au;
  • Growth capital of US$89 million will be deployed over the next four-year period comprised of: (i) US$55 million in capital for the underground expansion; (ii) US$30 million for process improvements, process plant throughput expansion, and camp upgrades; and (iii) US$3 million for tailings facility upgrades. LOM growth capital is estimated to be US$175 million and is primarily for underground development. LOM sustaining capital cost of US$87 million is estimated for site and process plant, and US$97 million for underground mining;
  • The PEA mine plan was developed from Measured and Indicated Mineral Resources of 10.8 million tonnes (“Mt”) grading 2.57 grams per tonne (“g/t”) gold containing 893,000 ounces of gold and Inferred Mineral Resources of 9.1 Mt grading 2.47 g/t gold containing 726,000 ounces of gold; and
  • With the existing open pit mine operating, the underground expansion plan benefits from the existing on-site process plant and mine infrastructure in place. The Company anticipates gold production from the underground expansion could be achieved within 3 years.

The Technical Report was prepared in accordance with NI 43-101 guidelines by P&E Mining Consultants Inc. (“P&E”). Input to this PEA was also provided by D.E.N.M. Engineering Ltd. (“D.E.N.M.”). This Technical Report has an effective date of April 15, 2025 and can be found on the Company’s website at www.TRXgold.com, on SEDAR+ at www.sedarplus.ca under the Company’s issuer profile, and on the SEC’s EDGAR system at sec.gov.

For readers to fully understand the information in this news release they should read the PEA in its entirety, including all qualifications, assumptions, exclusions and risks. The PEA is intended to be read as a whole, and sections should not be read or relied upon out of context.

Qualified Persons - PEA Authors

The PEA was prepared by consultants who are independent of TRX Gold, each of whom are Qualified Persons (“QP”) as defined by National Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101”). Each of the QPs have reviewed and confirmed that this news release fairly and accurately reflects, in the form and context in which it appears, the information contained in the respective sections of the PEA for which they are responsible.

The following acted as Qualified Persons under NI 43-101 as Authors of the PEA:

P&E Mining Consultants Inc.
Eugene Puritch, P.Eng., FEC, CET – Mineral Resources
Andrew Bradfield, P.Eng. – PEA leader and open pit mine design, scheduling and costs
D. Gregory Robinson, P.Eng. – Underground mine design, scheduling and costs
D. Grant Feasby, P.Eng. – Environmental
Fred H. Brown, P.Geo. – Mineral Resources
Yungang Wu, P.Geo. – Mineral Resources
William Stone, Ph.D., P.Geo. – Tenure, geology, drilling
Jarita Barry, P.Geo. – Data verification, QA/QC
D.E.N.M. Engineering Ltd.
David Salari, P.Eng. – Process plant expansion and process plant costing

Mr. Richard Boffey, BE Mining (Hons) F AusIMM, is the Company’s in-house Qualified Person under National Instrument 43-101 and Mr. Puritch have reviewed and assume responsibility for the scientific and technical content in this press release. Mr. Boffey is the Chief Operating Officer of TRX Gold and has 36 years of relevant industry experience. Mr. Puritch is the President and cofounder of P&E and has 45 years of relevant experience.

About TRX Gold Corporation

TRX Gold is a high margin and growing gold company advancing the Buckreef Gold Project in Tanzania. Buckreef Gold includes an established open pit operation and 2,000 tonnes per day process plant with upside potential demonstrated in the May 2025 Preliminary Economic Assessment (the “PEA”). The PEA outlines average gold production of 62,000 oz per annum over 17.6 years, and US$701 million pre-tax NPV5% at average life of mine gold price of US$2,296/oz. The Project hosts a Measured and Indicated Mineral Resource of 10.8 million tonnes (“MT”) at 2.57 grams per tonne (“g/t”) gold containing 893,000 ounces (“oz”) of gold and an Inferred Mineral Resource of 9.1 MT at 2.47 g/t gold for 726,000 oz of gold. The leadership team is focused on creating both near-term and long-term shareholder value by increasing gold production to generate positive cash flow to fund the expansion as outlined in the PEA and grow Mineral Resources through exploration. TRX Gold’s actions are led by the highest environmental, social and corporate governance (“ESG”) standards, evidenced by the relationships and programs that the Company has developed during its nearly two decades of presence in the Geita Region, Tanzania.

For investor or shareholder inquiries, please contact:

Investors:
Investor Relations
TRX Gold Corporation
+1 844 GOLD TRX (844-465-3879)
IR@TRXgold.com
www.TRXgold.com

Non-IFRS Performance Measures

The Company has included certain non-IFRS financial measures in this news release, such as LOM sustaining capital cost, total capital cost, Total or LOM cash cost, and AISC, which are not measures recognized under IFRS and do not have a standardized meaning prescribed by IFRS. As a result, these measures may not be comparable to similar measures reported by other corporations. Each of these measures used are intended to provide additional information to the user and should not be considered in isolation or as a substitute for measures prepared in accordance with IFRS. Non-IFRS financial measures used in this news release and common to the gold mining industry are defined below.

Total Cash Costs and Total Cash Costs per Ounce

Total cash costs are reflective of the cost of production. Total cash costs reported in the PEA include mining costs, processing and water treatment costs, general and administrative costs of the mine, off-site costs, refining costs, transportation costs and royalties. Total cash costs per ounce is calculated as total cash costs divided by payable gold ounces.

AISC and AISC per Ounce

AISC is reflective of all of the expenditures that are required to produce an ounce of gold from operations. AISC reported in the PEA includes total cash costs, sustaining capital, closure costs and salvage, but excludes corporate general and administrative costs. AISC per ounce is calculated as AISC divided by payable gold ounces.

Forward-Looking and Cautionary Statements

This press release contains certain forward-looking statements as defined in the applicable securities laws. All statements, other than statements of historical facts, are forward-looking statements. Forward-looking statements are frequently, but not always, identified by words such as “expects”, “anticipates”, “believes”, “hopes”, “intends”, “estimated”, “potential”, “possible” and similar expressions, or statements that events, conditions or results “will”, “may”, “could” or “should” occur or be achieved. Forward-looking statements relate to future events or future performance and reflect TRX Gold management’s expectations or beliefs regarding future events and include, but are not limited to, statements with respect to results set forth in the PEA, continued operating cash flow, expansion of its process plant under the terms of the PEA, exploration and conditions set forth in the PEA, expanding its open pit mining and initiating underground mining, current and anticipated price of gold, mine development plans, estimation of Mineral Resources, ability to develop value creating activities, recoveries, subsequent project testing, success, scope and viability of mining operations, the timing and amount of estimated future production, and capital expenditure.

Although TRX Gold believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance. The actual achievements of TRX Gold or other future events or conditions may differ materially from those reflected in the forward-looking statements due to a variety of risks, uncertainties and other factors. These risks, uncertainties and factors include general business, legal, economic, competitive, political, regulatory and social uncertainties; actual results of exploration activities and economic evaluations; fluctuations in currency exchange rates; changes in costs; future prices of gold and other minerals; mining method, production profile and mine plan; delays in exploration, development and construction activities; changes in government legislation and regulation; the ability to obtain financing on acceptable terms and in a timely manner or at all; contests over title to properties; employee relations and shortages of skilled personnel and contractors; the speculative nature of, and the risks involved in, the exploration, development and mining business.

These risks are set forth in reports that TRX Gold files with the SEC and the various Canadian securities authorities. You can review and obtain copies of these filings from the SEC's website at http://www.sec.gov/edgar.shtml and the Company’s profile on the System for Electronic Document Analysis and Retrieval (“SEDAR+”) at www.sedarplus.ca.

Technical information contained in this press release is as of the date of the press release and TRX Gold assumes no duty to update such information.


FAQ

What is the NPV of TRX Gold's Buckreef Gold Project according to the new PEA?

The base case NPV5% is $701M pre-tax ($442M after-tax) at consensus gold prices, with potential to reach $1.18B pre-tax ($766M after-tax) at $3,000/oz gold price.

How much gold will TRX's Buckreef Project produce annually?

The project is expected to produce an average of 62,000 oz gold annually over its 17.6-year life, with higher production of over 80,000 oz annually during the first five years of underground operations.

What are the estimated costs for TRX Gold's Buckreef expansion project?

The expansion requires $89M in growth capital over four years, with cash costs of $1,024/oz and AISC of $1,206/oz. Total LOM capital is estimated at $359M including growth and sustaining capital.

How long will TRX Gold's Buckreef mine operate according to the PEA?

The PEA indicates a 17.6-year mine life, processing 18.1 million tonnes averaging 2.14 g/t Au.

What are the mineral resources at TRX Gold's Buckreef Project?

The project has Measured and Indicated Resources of 10.8Mt at 2.57 g/t gold containing 893,000 ounces, and Inferred Resources of 9.1Mt at 2.47 g/t gold containing 726,000 ounces.
TRX Gold

NYSE:TRX

TRX Rankings

TRX Latest News

TRX Stock Data

85.84M
274.36M
2.07%
2.16%
0.08%
Gold
Basic Materials
Link
Canada
Oakville