STOCK TITAN

TRX Gold Corporation (TRX) Stock Price, News & Analysis

TRX NYSE
Published by Stock Titan Data refreshed

Price Move History

Daily moves over 5%
76 252 sessions, October 21, 2025 to October 21, 2026
Largest daily move
+27% close of January 28, 2026
1-year change
+48.6% closing prices, October 21, 2025 to October 21, 2026
1-month change
-20.5% closing prices, September 21, 2026 to October 21, 2026

Company Description

TRX Gold Corporation (TRX) is a gold mining company focused on the exploration, development and production of mineral property interests in the United Republic of Tanzania. The company is advancing the Buckreef Gold Project, which is described as a high margin and growing gold operation anchored by a defined mineral resource base and an established open pit mine and processing plant. TRX Gold trades under the symbol TRX and reports as a foreign issuer under Form 40-F in the United States.

Core business and Buckreef Gold Project

According to company disclosures, TRX Gold is engaged in development and mining operations at Buckreef Gold and in exploring and evaluating its mineral properties. The project includes an open pit operation and a process plant with a nameplate capacity of approximately 2,000 tonnes per day. The company states that this plant has undergone several expansions since first gold pour, and that it is the platform from which further growth is being pursued.

The Buckreef Gold Project hosts a Measured and Indicated Mineral Resource of about 10.8 million tonnes at 2.57 grams per tonne gold containing approximately 893,000 ounces of gold and an Inferred Mineral Resource of about 9.1 million tonnes at 2.47 grams per tonne gold for roughly 726,000 ounces of gold, based on a Preliminary Economic Assessment (PEA) and related technical reporting. Earlier company descriptions also reference a larger mineral resource estimate published in 2020 for the broader project area.

Preliminary Economic Assessment and growth concept

TRX Gold has filed a Preliminary Economic Assessment for Buckreef Gold that evaluates an expansion and upgrade of the existing process plant and a transition from open pit to underground mining over time. The PEA scenario contemplates increasing process plant throughput to around 3,000 tonnes per day and outlines average recovered gold production of approximately 62,000 ounces per year over a 17.6-year period, based on processing 18.1 million tonnes at an average grade of 2.14 grams per tonne gold.

The PEA also presents life-of-mine cash costs and all-in sustaining costs, and a discounted cash flow analysis using various gold price assumptions. The mine plan in the PEA is developed from the Measured and Indicated and Inferred Mineral Resources at Buckreef Gold, including domains such as the Main, South, West and Eastern Porphyry zones, as well as the Stamford Bridge zone. The company notes that the PEA is preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to be categorized as Mineral Reserves, and that Mineral Resources which are not Mineral Reserves may not have demonstrated economic viability.

Processing plant expansion and technical focus

TRX Gold has announced plans and ongoing work to expand and upgrade the Buckreef Gold processing plant beyond the configuration contemplated in the PEA. The company describes a larger processing facility consisting of a 3,000+ tonnes per day processing circuit for sulphide material and a 1,000 tonnes per day circuit for oxide and transition material, with tailings retreatment and the ability for the smaller circuit to process sulphide material at reduced throughput and recovery. The expansion plan involves integrating new equipment and circuits into the existing 2,000 tonnes per day plant.

Technical elements highlighted by the company include installation of a semi-autogenous grinding (SAG) mill, flotation and fine-grind units to concentrate gold into a smaller mass fraction, ultra-fine grinding followed by intensive leaching, pre-leach thickeners feeding a carbon-in-leach (CIL) circuit, upgraded CIL agitators and interstage screens, an oxygen plant and Aachen reactor for high-purity oxygen injection, and a new adsorption, desorption and refining (ADR) plant with a new gold room. A cyanide destruction circuit is also planned for tailings management. The company indicates that these upgrades are intended to improve throughput, recovery, plant reliability and operating stability.

Mining operations and production profile

Company news releases describe Buckreef Gold as having an established open pit operation that has undergone a scheduled stripping campaign to access higher grade ore blocks. TRX Gold reports that, following this campaign, it began accessing higher grade ore, which has supported record quarterly gold pours and sales in recent reporting periods. The company has reported increasing daily production rates and a growing run-of-mine stockpile containing significant ounces of gold, which it views as supporting future production and cash flow.

TRX Gold has also disclosed that it has signed a gold sale service agreement with the Bank of Tanzania, under which a minimum portion of gold doré production is set aside for domestic sale as required by Tanzanian law. The company notes that domestic sales through the central bank and local refineries benefit from a lower royalty rate than exported sales, and that this arrangement aligns Buckreef Gold with Tanzania’s policies on local content, value addition and beneficiation.

Exploration and resource growth

Beyond the operating open pit, TRX Gold emphasizes exploration as a key part of its strategy at Buckreef Gold. The company has reported the discovery of a promising new gold mineralization shear zone known as the Stamford Bridge Zone, where drilling has returned some of its highest gram-times-metre results to date. This zone is described as potentially forming a bridge between the Buckreef Main Zone, the Eastern Porphyry zone and the Anfield zone.

TRX Gold has initiated a detailed ground magnetic survey over the Buckreef tenement area to map subsurface magnetic variations, structural features and lithological contacts, with the goal of generating new drilling targets. The company has also outlined plans for underground resource drilling on the Buckreef Main Zone and exploration drilling on high-priority zones such as Stamford Bridge and Eastern Porphyry. It has procured reverse circulation and diamond drilling rigs for on-site exploration work.

Financial and corporate reporting framework

TRX Gold prepares its financial statements in accordance with International Financial Reporting Standards (IFRS) and files them on SEDAR+ in Canada and with the U.S. Securities and Exchange Commission. The company uses non-IFRS performance measures such as EBITDA, Adjusted EBITDA, cash cost per ounce of gold sold and average realized gold price per ounce, and provides reconciliations to IFRS measures in its public filings and news releases.

The company has filed multiple Form 6-K reports with the SEC to furnish quarterly financial statements, management’s discussion and analysis, and news releases related to operating and financial results, plant expansion updates and preliminary economic assessment findings. TRX Gold also makes use of credit facilities, gold prepayment arrangements and an at-the-market equity offering program to supplement internally generated cash flow for capital spending and working capital management, as described in its disclosures.

ESG approach and regional presence

In its public statements, TRX Gold highlights that its actions are informed by environmental, social and corporate governance (ESG) standards. The company points to relationships and programs developed during nearly two decades of presence in the Geita Region of Tanzania as evidence of this focus. It also notes that agreements such as domestic gold sales to the Bank of Tanzania support national objectives related to foreign exchange reserves and local economic participation.

Risk profile and industry context

TRX Gold acknowledges that the business of exploring and mining for minerals involves a high degree of risk. The underlying value of its mineral properties depends on the existence and economic recovery of mineral resources and reserves, as well as the ability to raise long-term financing to continue development. The company’s technical disclosures are prepared under National Instrument 43-101 standards, with Qualified Persons responsible for scientific and technical content in its reports and news releases.

Stock Performance

$0.9808
-6.59%
0.07
Last updated: October 22, 2026 at 14:38
+48.6%
Performance 1 year
$321.2M

TRX Gold Corporation (TRX) closed at $1.05 on October 21, 2026. Over the past 12 months, the price has gained 48.6%.

See what a $1,000 investment in TRX would be worth today

Average down calculator for TRX

TRX Metrics & Rankings

Price returns through October 21, 2026. Month-to-date and YTD include the first trading day. Ranking links may use different dates.

Financial Highlights

TRX Gold Corporation generated $57.6M in revenue in FY2025, retaining a 41.5% gross margin, and net income was $687K, reflecting a 1.2% net profit margin. Diluted earnings per share stood at $0.00. The company generated $16.3M in operating cash flow. The current ratio was 1.05, measuring current assets divided by current liabilities.

$57.6M
Revenue (FY2025)
$687K
Net Income (FY2025)
$16.3M
Operating Cash Flow

Upcoming Events

OCT
29
October 29, 2026 Marketing

Red Cloud presentation

Stephen Mullowney presents at Omni King Edward Hotel, Toronto on 2026-10-29 at 12:00PM EST; Red Cloud Fall Mining Showcase.
JAN
01
January 1, 2027 - December 31, 2027 Operations

Full circuit commissioning

Full sulphide and oxide circuits commissioning at Buckreef in fiscal 2027
JUL
15
July 15, 2027 - January 15, 2028 Operations

3,500 tpd mill completion

Completion of new 3,500 tpd SAG/ball mill at Buckreef; expected within 12–18 months from 2026-07-15 (2027-07-15–2028-01-15).
SEP
14
September 14, 2027 - March 14, 2028 Operations

Plant upgrade completion

Completion window for upgrades to 2,000 tpd plant and new 3,500 tpd SAG/Ball mill; supports >62,000 oz annual production per PEA.

TRX Gold Corporation has 4 upcoming scheduled events. The next event, "Red Cloud presentation", is scheduled for October 29, 2026 (in 7 days). Investors can track these dates to stay informed about potential catalysts that may affect the TRX stock price.

Short Interest History

Last 12 Months

Short interest in TRX Gold Corporation (TRX) currently stands at 4.3 million shares, up 104.0% from the previous reporting period, representing 1.5% of the shares outstanding. Since October 2025, short interest has increased by 80.2%.

Days to Cover History

Last 12 Months

Days to cover for TRX Gold Corporation (TRX) currently stands at 1.0 days. The ratio is the reported short interest divided by the average daily trading volume. Since October 2025, the figure has decreased by 21.9%. Across the settlements charted above, it has ranged from 1.0 to 4.1 days.

TRX Company Profile & Sector Positioning

TRX Gold Corporation (TRX) operates in the Gold industry within the broader Basic Materials sector and is listed on the NYSE.

Investors comparing TRX often look at related companies in the same sector, including Goldgroup Mining Inc. (GORO), Vista Gold Corp. (VGZ), Hycroft Mining Holding Corporation (HYMC), U.S. Gold Corp. (USAU), and GoldMining Inc. (GLDG). Comparing financial metrics, valuation ratios, and stock performance across these peers can help investors evaluate TRX's relative position within its industry.

Frequently Asked Questions

What is the current stock price of TRX Gold Corporation (TRX)?

The current stock price of TRX Gold Corporation (TRX) is $0.9808 as of October 22, 2026.

What is the market cap of TRX Gold Corporation (TRX)?

The market cap of TRX Gold Corporation (TRX) is approximately $321.2M. Learn more about what market capitalization means .

What is the revenue of TRX Gold Corporation (TRX) stock?

The FY2025 revenue of TRX Gold Corporation (TRX) is $57.6M, from its most recent completed fiscal year.

What is the net income of TRX Gold Corporation (TRX)?

The FY2025 net income of TRX Gold Corporation (TRX) is $687K, from its most recent completed fiscal year.

What is the earnings per share (EPS) of TRX Gold Corporation (TRX)?

The diluted earnings per share (EPS) of TRX Gold Corporation (TRX) is $0.00 for FY2025, its most recent completed fiscal year. Learn more about EPS .

What is the operating cash flow of TRX Gold Corporation (TRX)?

The operating cash flow of TRX Gold Corporation (TRX) is $16.3M for FY2025, its most recent completed fiscal year. Learn about cash flow.

What is the profit margin of TRX Gold Corporation (TRX)?

The net profit margin of TRX Gold Corporation (TRX) is 1.2% for FY2025, its most recent completed fiscal year. Learn about profit margins.

What is the gross margin of TRX Gold Corporation (TRX)?

The gross profit margin of TRX Gold Corporation (TRX) is 41.5% for FY2025, its most recent completed fiscal year. Learn about gross margins.

What is the current ratio of TRX Gold Corporation (TRX)?

The current ratio of TRX Gold Corporation (TRX), current assets divided by current liabilities, was 1.05 at the end of FY2025, its most recent completed fiscal year. Learn about liquidity ratios.

What is the gross profit of TRX Gold Corporation (TRX)?

The gross profit of TRX Gold Corporation (TRX) is $23.9M for FY2025, its most recent completed fiscal year.

What does TRX Gold Corporation do?

TRX Gold Corporation is engaged in the exploration, development and production of mineral property interests in the United Republic of Tanzania. Its primary focus is advancing and operating the Buckreef Gold Project, which includes an established open pit mine and a processing plant supported by a defined mineral resource base.

Where is TRX Gold’s main project located?

TRX Gold’s main project, Buckreef Gold, is located in Tanzania. The company notes that it has had a presence in the Geita Region of Tanzania for nearly two decades and that Buckreef Gold is the core asset underpinning its operations and growth plans.

What is the Buckreef Gold Project?

The Buckreef Gold Project is TRX Gold’s flagship gold mining and development project. It comprises an operating open pit mine, a processing plant currently sized at about 2,000 tonnes per day, and a mineral resource base that includes Measured, Indicated and Inferred Mineral Resources as disclosed in technical reports and the company’s Preliminary Economic Assessment.

What mineral resources support Buckreef Gold?

According to TRX Gold’s PEA and related disclosures, Buckreef Gold hosts a Measured and Indicated Mineral Resource of approximately 10.8 million tonnes at 2.57 grams per tonne gold containing about 893,000 ounces of gold, and an Inferred Mineral Resource of about 9.1 million tonnes at 2.47 grams per tonne gold for roughly 726,000 ounces of gold.

What is the purpose of TRX Gold’s Preliminary Economic Assessment?

The Preliminary Economic Assessment evaluates an expansion and upgrade of the Buckreef Gold process plant and a transition from open pit to underground mining. It provides an economic analysis based on a 17.6-year mine life, average annual recovered gold production of around 62,000 ounces, and life-of-mine cost estimates, while noting that it is preliminary in nature and includes Inferred Mineral Resources.

How is TRX Gold expanding its processing capacity?

TRX Gold has outlined plans to expand and upgrade the Buckreef Gold processing plant by adding a 3,000+ tonnes per day sulphide circuit and a 1,000 tonnes per day circuit for oxide and transition material, integrated with the existing 2,000 tonnes per day plant. The expansion includes new crushing, grinding, flotation, fine-grind, CIL, oxygen injection and ADR infrastructure, as well as a cyanide destruction circuit for tailings management.

What exploration work is TRX Gold conducting at Buckreef?

The company is conducting exploration drilling and geophysical surveys across the Buckreef tenement area. It has reported the discovery of the Stamford Bridge Zone, a promising gold mineralization shear zone, and is planning further drilling on high-priority zones such as Stamford Bridge, Buckreef Main, Eastern Porphyry and Anfield, supported by newly procured reverse circulation and diamond drilling rigs.

How does TRX Gold describe its ESG approach?

TRX Gold states that its actions are led or informed by high environmental, social and corporate governance standards. It highlights long-standing relationships and programs in the Geita Region of Tanzania and points to initiatives such as domestic gold sales to the Bank of Tanzania and compliance with local mining legislation as part of its ESG and regional engagement.

What non-IFRS performance measures does TRX Gold report?

TRX Gold reports non-IFRS measures including EBITDA, Adjusted EBITDA, cash cost per ounce of gold sold, total cash costs, all-in sustaining costs and average realized price per ounce of gold sold. The company provides reconciliations to IFRS measures in its financial statements and explains that these metrics are used to assess operating performance and cost structure.

How are TRX Gold’s technical disclosures regulated?

Technical information for Buckreef Gold is prepared under National Instrument 43-101 standards. Qualified Persons, both internal and external, are identified in TRX Gold’s news releases and technical reports as responsible for mineral resource estimates, mine design, processing plant parameters and other scientific and technical content.