STOCK TITAN

VIZSLA SILVER AWARDS EPCM AND MINE DESIGN CONTRACTS FOR THE DEVELOPMENT OF THE PANUCO SILVER-GOLD PROJECT

(Positive)
Tags

Vizsla Silver (NYSE: VZLA) awarded an EPCM contract to M3 Engineering and a mine design contract to Mining Plus for the Panuco silver-gold project dated April 23, 2026. EPCM scope covers ~US$170 million (process plant and surface infrastructure); mining design covers ~US$50 million development capital and ~US$40 million ore development over two years.

Key schedule items: award mining contract in Q2 2026, begin mining after MIA permit, and conduct a two-year infill drilling program to support ramp-up and stockpiling ahead of plant commissioning.

Loading...
Loading translation...

Positive

  • EPCM contract valued at approximately US$170 million for process plant and surface infrastructure
  • Mining design scope covers approximately US$50 million in development capital
  • Planned ~US$40 million in ore development over next two years to support pre-production
  • Contracts with experienced firms M3 Engineering and Mining Plus with Mexico project history

Negative

  • Mining start contingent on receipt of the MIA permit (timing uncertain)
  • Definitive EPCM agreement terms still being finalized and may affect schedule or costs
  • Major near-term capital requirements (~US$260 million combined) ahead of production

News Market Reaction – VZLA

-4.62%
1 alert
-4.62% Session close to close
$1.17B Market Cap
5.43K Volume

In the Apr 23 session, VZLA declined 4.62%, reflecting a moderate negative market reaction.

Data tracked by StockTitan Argus on the day of publication.

Market Context

This announcement detailed a significant de‑risking step for Panuco, with an EPCM contract covering ...
Analysis

This announcement detailed a significant de‑risking step for Panuco, with an EPCM contract covering about US$170 million of plant and infrastructure and mine design work tied to roughly US$90 million in early capital and ore development. It followed prior months of security‑related disruptions at the project. Investors monitoring Vizsla may focus on execution of these contracts, progress toward permitting, and how the company manages long‑term security and ramp‑up plans as pre‑production spending advances.

Key Figures

EPCM scope value: US$170 million Mine design capex: US$50 million Ore development spend: US$40 million +2 more
5 metrics
EPCM scope value US$170 million Process plant and surface infrastructure at Panuco
Mine design capex US$50 million Development capital in mining design scope of work
Ore development spend US$40 million Ore development over next two years of pre-production
Mining contract timing Q2 2026 Target to award mining contract in project schedule
Pre-production period Two years Infill drilling and ore development ahead of plant commissioning

Historical Context

5 past events · Latest: Apr 06 (Negative)
Pattern 5 events
Date Event Sentiment 24h Move Catalyst
Apr 06 Security update Negative -2.1% Confirmed deaths and missing colleague in Concordia incident, operations impact.
Mar 11 Sector silver outlook Positive -1.2% Silver reserves and investment theme highlighting ongoing market deficit.
Mar 05 Security update Negative -2.2% Additional deaths confirmed and colleagues still missing at Panuco site.
Feb 26 Sector silver outlook Positive +6.9% Structural silver deficit and major producer metrics referencing Vizsla Silver.
Feb 12 Security/operations update Negative -6.4% Operations suspension at Panuco amid ongoing security and search efforts.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

Pattern Detected

News tied to security incidents around Panuco has consistently coincided with negative price moves, while silver‑market bullish pieces have generally aligned with positive reactions, with one recent divergence.

Recent Company History

Over recent months, VZLA’s news flow has centered on security incidents at the Panuco project and broader silver‑market commentary. Security updates on Jan 29, Feb 12, Mar 5, and Apr 6 all coincided with share price declines, reflecting market sensitivity to operational and safety risk. In contrast, silver‑deficit themed articles on Feb 26 and Mar 11 highlighted supportive sector fundamentals, with one notably strong positive reaction, framing today’s engineering and mine‑design contracts as part of a longer-term development narrative.

Key Terms

engineering, procurement and construction management, epcm, preliminary economic assessment, infill drilling program
4 terms
engineering, procurement and construction management technical
"it has awarded the Engineering, Procurement and Construction Management (the "EPCM") contract"
A project delivery approach where a firm handles detailed design, sources major equipment and materials, and oversees construction on behalf of the project owner, acting like the owner’s project manager. It matters to investors because the firm’s performance determines whether a project is built on time, on budget and to specification—similar to hiring a general contractor for a house, where delays or cost overruns directly affect returns, cash flow and project risk.
epcm technical
"the Engineering, Procurement and Construction Management (the "EPCM") contract to M3 Engineering"
EPCM stands for engineering, procurement and construction management, a contract model where a firm designs a project, buys major equipment and manages contractors rather than doing the actual building work itself. For investors, an EPCM arrangement matters because it usually keeps the project owner more directly responsible for contractor costs, schedules and on-site risks, which can affect budget certainty, timelines and the likelihood of delays or cost overruns. Think of it as hiring an architect and general manager who arranges and oversees the builders rather than having a single company deliver the whole job.
preliminary economic assessment technical
"have worked together since finalizing the Panuco Preliminary Economic Assessment (PEA)"
A preliminary economic assessment is an initial analysis that estimates the potential profitability and feasibility of a project or resource, such as a new mineral deposit or development venture. It provides a rough idea of costs, benefits, and risks, helping investors decide whether to pursue more detailed studies. This early evaluation is important because it offers a snapshot of whether the project is worth further investment and development.
infill drilling program technical
"Implement an infill drilling program over an initial two-year period"
An infill drilling program is a planned set of additional drill holes placed between earlier holes to create a tighter grid of samples and more detailed information about a mineral deposit. For investors, it matters because the denser data lowers uncertainty about how much ore exists and its quality—think of adding pixels to a blurry picture—helping turn speculative estimates into more reliable categories used for valuation, financing and mine planning.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

NYSE: VZLA     TSX: VZLA

VANCOUVER, BC, April 23, 2026 /PRNewswire/ - Vizsla Silver Corp. (TSX: VZLA) (NYSE: VZLA) (Frankfurt: 0G3) ("Vizsla Silver" or the "Company") today announced that it has awarded the Engineering, Procurement and Construction Management (the "EPCM") contract to M3 Engineering & Technology Corp. ("M3" or "M3 Engineering") and has entered into a Mine Design contract with Mining Plus. Both contractors will support the advancement of its flagship Panuco silver-gold project.

"The appointment of key engineering and mine design partners represents an important step in advancing our Panuco Project," said Michael Konnert, President and CEO. "We are pleased to partner with M3 and Mining Plus as we move towards mobilization."

With its partners, the Company will work off-site to advance detailed design, construction planning and equipment procurement, while continuing to advance go-forward, long-term security plans for the Panuco Project. Vizsla Silver advises that key development activities continue to progress in line with previously disclosed timelines.

EPCM Contract Selection

M3 Engineering is an experienced engineering firm specializing in mineral processing and infrastructure projects. The firm has participated in the design and construction of several mining projects in Mexico, including Mercedes, Los Gatos, Peñasquito, Camino Rojo and Terronera.

Since finalizing the Panuco Feasibility Study (published in November 2025), Vizsla Silver has worked with M3 Engineering to support the planning and development of the Project. The EPCM scope of work covers the process plant and surface infrastructure, valued at approximately US$170 million. The Company and M3 Engineering are currently finalizing the terms and conditions of the definitive EPCM agreement.

"M3 Engineering & Technology Corp. is proud to contribute our technical expertise to support Vizsla Silver in advancing the development of the Panuco Silver-Gold Project," said Alberto Bennett, President and CEO of M3 Engineering. "We look forward to continuing working closely with Vizsla Silver's team to deliver another successful project in Mexico, on time and on budget."

Mining Design Contract

Mining Plus, part of The Byrnecut Group, is a global mining services firm. Vizsla Silver and Mining Plus have worked together since finalizing the Panuco Preliminary Economic Assessment (PEA), published in July 2024.

Mining Plus has supported mine design, planning, scheduling and geotechnical work, including contributions to the development of the Company's Morgan Test Mine at Panuco. The mining design scope of work covers approximately US$50 million in development capital, and approximately US$40 million in ore development over the next two years of pre-production.

Key mining schedule items include:

  • Award mining contract in Q2 2026
  • Begin mining operations upon receipt of the MIA permit
  • Implement an infill drilling program over an initial two-year period to support ramp-up and stockpiling ahead of process plant commissioning

"Mining Plus is pleased to continue its partnership with Vizsla Silver as the Panuco Project advances toward production," said Vahid Haydari, Chief Executive Officer of Mining Plus. "Since our initial involvement following the Preliminary Economic Assessment, we have worked closely with the team on mine design and planning. This next phase focuses on detailed planning and disciplined execution as this high grade, technically compelling project advances toward commercial production."

About Vizsla Silver and the Panuco Project

Vizsla Silver is a Canadian mineral exploration and development company headquartered in Vancouver, BC, focused on advancing its flagship, 100%-owned Panuco silver-gold project located in Sinaloa, Mexico. The Company recently completed a Feasibility Study for Panuco in November 2025 which highlights 17.4 Moz AgEq of annual production over an initial 9.4-year mine life, an after-tax NPV (5%) of US$1.8B, 111% IRR and a 7-month payback at US$35.50/oz Ag and US$3,100/oz Au. Vizsla Silver aims to position itself as a leading silver company by implementing a dual track development approach at Panuco, advancing mine development while continuing district-scale exploration through low-cost means. 

Website: www.vizslasilvercorp.ca  

SPECIAL NOTE REGARDING FORWARD LOOKING STATEMENTS

Forward-looking statements in this release include, but are not limited to, statements regarding: the Company's objectives and milestones; the strategic vision for the Company following the proposed development of the Panuco Project and expectations regarding future financial or operating performance following such development; the timing and receipt of environmental and other regulatory permits, including but not limited to the MIA Permit; the timing and entry into the EPCM agreement as proposed or at all; the timing and execution of construction activities as proposed or at all, including the commencement of construction, advancement of detailed engineering, and selection of contractors and development partners; the Company's ability to advance the Panuco Project toward production; the results, timing and scope of planned drilling programs, including underground infill and expansion drilling, district-wide surface drilling, and follow-up drilling at Animas, Santa Fé, La Garra, Peñoles and other targets and their anticipated impact on project economics and mine design; the conversion of inferred mineral resources to indicated mineral resources, including targeted conversion of inferred mineralization within the Copala zone; the size, grade, continuity and potential expansion of mineral resources, including the potential to add mine life beyond the current Feasibility Study's mine plan; the completion and outcomes of bulk sampling, metallurgical testing, geotechnical work and optimization studies, and their anticipated impact on project economics and mine design; the economic results of the Panuco Project, including forecast production rates, mine life, capital costs, operating costs, free cash flow, net present value, internal rate of return, and payback period, as derived from the Feasibility Study; the assumptions underlying the Feasibility Study, including commodity prices, metallurgical recoveries, operating and capital cost estimates, permitting timelines, and development schedules; the Company's ability to fund construction and development, including expectations regarding the sufficiency of existing cash balances and access to financing; the anticipated benefits of property acquisitions and exploration programs, including the identification of new mineralized zones and discovery of additional deposits; and the Company's long-term growth strategy, including its ability to enhance shareholder value through continued exploration success, project development and operational execution.

Forward-looking statements are based on a number of assumptions believed to be reasonable by the Company as of the date of this release, including, without limitation: the accuracy of the Feasibility Study parameters; the availability of financing on acceptable terms; that required permits and approvals will be obtained in the expected timeframe; continued community and government support; stability in market, political and economic conditions; reasonable accuracy of operating and capital cost estimates; and continued favourable metal prices and exchange rates.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause actual results to differ materially. Such risks include, but are not limited to: exploration, development and operating risks; permitting, environmental and regulatory risks; community relations and social licence risks; commodity price and currency fluctuations; inflation and cost escalation; financing and liquidity risks; reliance on contractors and suppliers; title and surface rights risks; changes in project development and construction parameters; inaccuracies in technical or economic modelling; the risk that the Feasibility Study assumptions prove inaccurate; and other risks described in the Company's continuous disclosure filings available under its profile on SEDAR+ at www.sedarplus.ca.

There can be no assurance that the Panuco Project will be placed into production as proposed in this news release or at all, that the EPCM definitive agreement will be entered into and on what terms or that the results of the Feasibility Study will be realized. The purpose of the forward-looking statements is to provide information about management's current expectations and plans and may not be appropriate for other purposes. Readers are cautioned not to place undue reliance on forward-looking statements, which speak only as of the date of this release. Except as required by applicable law, the Company undertakes no obligation to update or revise any forward-looking statements contained herein.

No Production Decision: The Company has not made a production decision for the Panuco Project. A decision to proceed with construction will only be made following the completion and review of detailed engineering, financing arrangements, and receipt of all required permits and approvals.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/vizsla-silver-awards-epcm-and-mine-design-contracts-for-the-development-of-the-panuco-silver-gold-project-302750621.html

SOURCE Vizsla Silver Corp.

FAQ

What contracts did Vizsla Silver (VZLA) announce for the Panuco project on April 23, 2026?

They awarded an EPCM contract to M3 Engineering and a mine design contract to Mining Plus. According to the company, M3 will cover process plant and surface infrastructure (~US$170 million) while Mining Plus will cover ~US$50 million development capital and ~US$40 million ore development.

How much is the EPCM scope for Vizsla Silver's (VZLA) Panuco project worth?

The EPCM scope is valued at approximately US$170 million. According to the company, that covers the process plant and surface infrastructure as part of detailed design, construction planning and equipment procurement.

What are the near-term mining schedule milestones for VZLA's Panuco project?

Key milestones include awarding the mining contract in Q2 2026 and commencing mining after MIA permit approval. According to the company, an infill drilling program will run for two years to support ramp-up and stockpiling before plant commissioning.

Who are the contractors appointed by Vizsla Silver (VZLA) for mine design and engineering?

Vizsla Silver appointed M3 Engineering for EPCM and Mining Plus for mine design. According to the company, both firms have prior involvement in Panuco planning and experience on Mexican mining projects.

What capital and development work will Mining Plus perform for VZLA's Panuco project?

Mining Plus will support ~US$50 million in development capital and ~US$40 million of ore development over two years. According to the company, scope includes mine design, planning, scheduling, geotechnical work, and support for the Morgan Test Mine.