STOCK TITAN

Anfield Energy (NASDAQ: AEC) touts 106% IRR PEA and near-term U.S. uranium output

Filing Impact
(Neutral)
Filing Sentiment
(Neutral)
Form Type
6-K

Rhea-AI Filing Summary

Anfield Energy reported strong first-half 2026 progress on its U.S. uranium-vanadium hub-and-spoke strategy centered on the fully permitted Shootaring Canyon Mill. An updated Preliminary Economic Assessment shows a pre-tax IRR of 106% and NPV of US$606 million (8% discount rate), and a post-tax IRR of 97% with NPV of US$533 million, with projected payback in 1.3 years on mine and mill capex and pre-production capex of about US$97 million.

The study outlines average annual production over a 15-year mine life of roughly 1.3 million pounds U₃O₈ and 6.4 million pounds V₂O₅, processed at Shootaring using ore from multiple Utah and Colorado mines and stockpiles. Phase One construction at Velvet-Wood is complete, with production targeted by the end of 2026 and mill production targeted for 2027. Anfield also completed the acquisition of BRS Engineering, advanced permitting on several projects, and highlighted increased ownership by major shareholder Uranium Energy Corp.

The company entered a three-month media services agreement with Goldwyn Media for US$200,000, subject to TSX Venture Exchange approval, to expand marketing and public awareness as it positions its U.S.-based assets within a supportive domestic critical minerals policy environment.

Positive

  • Exceptional PEA economics: Updated study for the Shootaring-centered hub-and-spoke model shows a pre-tax IRR of 106%, post-tax IRR of 97%, and NPVs of US$606m and US$533m with a 1.3-year payback.
  • Clear path toward production: Phase One construction at Velvet-Wood is complete with production targeted by end of 2026 and Shootaring mill production targeted for 2027, outlining a staged ramp-up plan.
  • Strategic backing and capabilities: Acquisition of BRS Engineering adds in-house technical expertise, while increased ownership by Uranium Energy Corp. signals strong industry support for Anfield’s development strategy.

Negative

  • None.

Insights

Anfield outlines very strong PEA economics and tangible steps toward U.S. uranium-vanadium production.

The updated PEA for the Shootaring-centered hub-and-spoke model shows a pre-tax IRR of 106% and NPV of US$606 million at an 8% discount rate, with post-tax IRR of 97% and NPV of US$533 million. A projected 1.3-year payback and pre-production capex of about US$97 million indicate relatively rapid capital recovery in the study’s base case.

Operationally, Phase One construction at Velvet-Wood is complete, production is targeted by the end of 2026, and the Shootaring license conversion aims for production in 2027. Integration of multiple mines and existing stockpiles, alongside the acquisition of BRS Engineering, supports execution of the hub-and-spoke plan. However, permitting challenges at SM-18, currently moving to a hearing, illustrate regulatory risk that could affect parts of the pipeline.

Average annual production over 15 years is estimated at about 1.3 million pounds U₃O₈ and 6.4 million pounds V₂O₅, with additional upside from DOE leases and processing improvements. Increased ownership by Uranium Energy Corp. and a US$200,000 media campaign show both strategic backing and an effort to raise visibility. Actual outcomes will depend on permitting decisions, financing, construction execution and future commodity prices beyond what is detailed in this update.

Pre-tax IRR 106% Updated PEA for hub-and-spoke model, 8% discount rate
Pre-tax NPV US$606 million Updated PEA, 8% discount rate
Post-tax NPV US$533 million Updated PEA, 8% discount rate
Payback period 1.3 years Mine and mill capex payback from PEA
Pre-production capex US$97 million Approximate capex over 12 months including contingency
Average annual U₃O₈ output 1.3 million pounds Projected average over 15-year mine life
Average annual V₂O₅ output 6.4 million pounds Projected average over 15-year mine life
Media services fee US$200,000 Three-month media services agreement with Goldwyn
Preliminary Economic Assessment financial
"The updated Preliminary Economic Assessment1 (“PEA”) demonstrates the compelling value of Anfield’s integrated hub-and-spoke model."
A preliminary economic assessment is an initial analysis that estimates the potential profitability and feasibility of a project or resource, such as a new mineral deposit or development venture. It provides a rough idea of costs, benefits, and risks, helping investors decide whether to pursue more detailed studies. This early evaluation is important because it offers a snapshot of whether the project is worth further investment and development.
internal rate of return financial
"Highlights include – Pre-tax IRR of 106% and NPV of US$606 million (8% discount rate); post-tax IRR of 97% and NPV of US$533 million."
A percentage that represents the annualized yield an investment would earn, taking into account the timing and amount of all cash inflows and outflows; mathematically it is the rate that makes the discounted sum of future cash flows equal the initial cost. Investors use it to compare different projects or deals the way they compare interest rates — a higher internal rate of return suggests a stronger potential payoff, but it does not by itself show risk, scale, or timing nuances.
NPV financial
"Pre-tax IRR of 106% and NPV of US$606 million (8% discount rate); post-tax IRR of 97% and NPV of US$533 million."
Net Present Value (NPV) is a way to measure how much a future stream of money is worth today. It helps investors decide whether an investment is worthwhile by comparing the current value of expected earnings to its initial cost. A positive NPV suggests the investment could generate profit, making it a key tool for evaluating financial decisions.
hub-and-spoke strategy financial
"The Company is executing on its hub-and-spoke uranium and vanadium strategy, with a clear line of sight to production."
National Instrument 43-101 regulatory
"a qualified person as defined by National Instrument 43-101 – Standards of Disclosure for Mineral Projects"
National Instrument 43-101 is a set of rules and guidelines that govern how mineral exploration and mining companies must report information about their projects. It ensures that the details shared with investors are accurate, consistent, and reliable—similar to how a detailed, verified blueprint ensures a building’s safety. This helps investors make informed decisions based on trustworthy information about a company's mineral resources.
Section 232 proclamation regulatory
"including the January 2026 Section 232 proclamation on processed critical minerals."
See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google
Learn about SEC filing dates
 

UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549

Form 6-K

REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO RULE 13a-16 OR 15d-16 UNDER THE SECURITIES EXCHANGE ACT OF 1934

For the month of June 2026

Commission File Number: 001-42808

Anfield Energy Inc.
(Translation of registrant's name into English)

2005-4390 Grange Street, Burnaby, British Columbia, Canada, V5H 1P6
(Address of principal executive office)

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.
Form 20-F [   ]      Form 40-F [ X ]

 

 


SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

      Anfield Energy Inc.    
  (Registrant)
   
  
Date: June 25, 2026     /s/ Corey Dias    
  Corey Dias
  Chief Executive Officer
  


EXHIBIT INDEX

Exhibit Number Description
   
99.1 Press Release dated June 25, 2026

EXHIBIT 99.1

Anfield Energy Delivers Strong First-Half 2026 Momentum with Exceptional PEA Economics and Clear Path to Near-Term Production

VANCOUVER, British Columbia, June 25, 2026 (GLOBE NEWSWIRE) -- Anfield Energy Inc. (NASDAQ: AEC; TSX.V: AEC; FRANKFURT: 0AD) (“Anfield” or the “Company”) is pleased to provide a corporate update highlighting significant operational, permitting, and economic advancements in the first half of 2026. The Company is executing on its hub-and-spoke uranium and vanadium strategy, with a clear line of sight to production and robust project economics that position it for potentially substantial value creation.

Shootaring Canyon Mill Advancement

  • Point-of-Compliance Wells Installed: Successfully completed drilling of 8 new monitoring wells in May 2026 near proposed process ponds and the tailings management facility. This key milestone delivers essential baseline groundwater data ahead of resuming full operations at the fully permitted Shootaring Canyon Mill (“Shootaring”).
  •  License Renewal & Refurbishment Progress: Ongoing engineering studies and refurbishment work at Shootaring are advancing well. The Company remains on track to convert the mill license from care-and-maintenance to operations, with production targeted for 2027.
  • Robust Economics Confirmed via Updated PEA (Filed June 2026): The updated Preliminary Economic Assessment1 (“PEA”) demonstrates the compelling value of Anfield’s integrated hub-and-spoke model. Highlights include:

– Pre-tax IRR of 106% and NPV of US$606 million (8% discount rate); post-tax IRR of 97% and NPV of US$533 million.
– Rapid payback period of just 1.3 years on mine and mill capex.
– Pre-production capex of approximately US$97 million (including contingency) over a 12-month period.
– Average annual production over 15-year mine life: ~1.3 million pounds U₃O₈ and 6.4 million pounds V₂O₅ (peak year: 1.9M lbs U₃O₈ + 7.8M lbs V₂O₅).
– Centralized processing at Shootaring (target capacity 1,000 tonnes per day) fed by Velvet-Wood, Slick Rock, and six West Slope mines (JD-6, JD-7, JD-8, JD-9, SR-11, SM-18).
– Includes ~250,000 pounds of uranium from existing stockpiles near Shootaring.
– Significant upside potential from the addition of 13 remaining U.S. Department of Energy (“DOE”) leases with minimal incremental capex, plus value-added processing technologies to improve grades and throughput.

Mining Project Advancement

  • Velvet-Wood Phase One Construction Completed (June 2026): Successfully finished Phase One, including topsoil stripping (set aside for reclamation), portal rehabilitation, temporary power installation, and road build-out. The project is now advancing to Phase Two, with production targeted by the end of 2026.
  • JD-8 Plan of Operations: Revised Plan of Operations submitted to DOE and Colorado Division of Reclamation, Mining and Safety (“DRMS”) in April 2026 following agency feedback.
  • SM-18 NOI & Drilling Program: In April 2026, the Company submitted the notice of intent to conduct a drilling program (“NOI”) at SM-18 designed to verify and potentially expand the existing mineral resources. Following an initial denial by DRMS and a subsequent denial of reconsideration, the Company has filed for a hearing with the relevant board. The Company is in discussions with DRMS and the Attorney General’s office to discuss a potential compromise. The Company continues to advance preparations for a comprehensive Plan of Operations.

Strategic Acquisitions & Operational Readiness

  • BRS Engineering Acquisition (May 2026): Completed acquisition of B.R.S. Inc. (“BRS Engineering”), providing dedicated in-house engineering expertise to accelerate Shootaring refurbishment and mining project development.
  • Underground Haul Truck Procurement (June 2026): Received underground haul truck from Young’s Machine (Utah manufacturer). This strengthens Anfield’s commitment to building a robust American supply chain for domestic uranium production.
  • Equipment Procurement Milestone (June 15, 2026): Additional key equipment procurement advances operational readiness for the hub-and-spoke production model.

U.S. Policy Support & Strategic Shareholder Backing

  • Supportive Federal Policy Environment: Anfield welcomes the U.S. government’s continued focus on domestic critical minerals and uranium supply chain security, including the January 2026 Section 232 proclamation on processed critical minerals. These measures reinforce the strategic importance of Anfield’s fully U.S.-based assets and near-term production capability.
  • Strategic Shareholder Alignment: Major shareholder, Uranium Energy Corp. (UEC) has increased its stake in Anfield, demonstrating strong confidence in the Company’s assets, team, and execution plan. This partnership provides valuable industry validation and potential synergies as Anfield advances toward production.

Management Commentary

“We are very proud of the substantial progress Anfield has delivered in the first half of 2026,” said Corey Dias, CEO of Anfield. “From completing critical mill infrastructure milestones and Phase One construction at Velvet-Wood, to securing in-house engineering capabilities and advancing our permitting pipeline, we are executing with precision. The updated PEA underscores the exceptional economics of our hub-and-spoke strategy—106% pre-tax IRR, US$606 million NPV, and a rapid 1.3-year payback—positioning Anfield for potentially significant value creation as we move toward production at Velvet-Wood by year-end 2026 and Shootaring in 2027. We are also encouraged by the supportive U.S. policy environment and the confidence shown by strategic shareholders. Anfield is well-positioned to contribute meaningfully to America’s domestic uranium and vanadium supply and the broader nuclear energy renaissance.”

Strategic Positioning

This progress aligns with Anfield’s hub-and-spoke strategy, leveraging the fully permitted Shootaring in Utah alongside its high-quality uranium-vanadium assets in Utah and Colorado. The Company remains focused on creating long-term shareholder value through efficient development, operational excellence, and contribution to U.S. energy security and the global transition to clean, carbon-free power.

Media Services Engagement

The Company has entered into a three-month media services agreement with Goldwyn Media LLC (“Goldwyn”), dated June 23, 2026 (the “Media Services Agreement”). Under the Media Services Agreement, Anfield will pay US$200,000 for comprehensive marketing and public awareness services aligned with TSX Venture Exchange (“TSXV”) policies and applicable securities laws, including developing and creating a range of informative and awareness content that aligns with the Company’s overall marketing and branding strategies. Goldwyn is at arm’s length to the Company with no other relationship or interest in Anfield securities.

Goldwyn is an independent limited liability company based in Sheridan, Wyoming, that provides services for shareholder information and public relations. None of Goldwyn nor its affiliates or associates have any interest directly or indirectly in the Company or its securities, or any right or intent to acquire such an interest. Goldwyn will not receive shares or other securities as compensation. The media services agreement is subject to the Company’s filing requirements with the TSXV and the approval of the TSXV.

Technical Disclosure

The scientific and technical information in this news release has been prepared under the supervision of and approved by Douglas L. Beahm, P.E., P.G., a qualified person as defined by National Instrument 43-101 – Standards of Disclosure for Mineral Projects, and Mr. Beahm has reviewed, verified and approved such scientific and technical information contained in this news release. No limitations or failures to verify were identified. Mr. Beahm is not independent of the Company, as he is the Company’s Chief Operating Officer.

About Anfield

Anfield is a uranium and vanadium development company that is committed to becoming a top-tier energy-related fuels supplier by creating value through sustainable, efficient growth in its assets. Anfield is a publicly traded corporation listed on the NASDAQ (AEC-Q), the TSXV (AEC-V) and the Frankfurt Stock Exchange (0AD).

On behalf of the Board of Directors
ANFIELD ENERGY INC.
Corey Dias, Chief Executive Officer

Contact:

Anfield Energy, Inc.
Corporate Communications
604-669-5762
contact@anfieldenergy.com
www.anfieldenergy.com

Neither the TSXV nor its Regulation Services Provider (as that term is defined in policies of the TSXV) accepts responsibility for the adequacy or accuracy of this release.

This news release contains forward-looking statements and forward-looking information (together, “forward-looking statements”) within the meaning of applicable Canadian securities laws. All statements, other than statements of historical facts, are forward-looking statements. Generally, forward-looking statements can be identified by the use of terminology such as “seek”, “expect”, “anticipate”, “budget”, “plan”, “estimate”, “continue”, “forecast”, “intend”, “believe”, “predict”, “potential”, “target”, “may”, “could”, “would”, “might”, “will” and similar words or phrases (including negative variations) suggesting future outcomes or statements regarding an outlook or statements that certain actions, events or results “may”, “could”, “would”, “might”, “occur” or “be achieved” (including negative variations). Forward-looking statements in this release include, but are not limited to, statements regarding the development, operational and economic results of the PEA, including capital expenditures, NPV projections and IRR projections; statements regarding the Company’s business plans, objectives and strategies of operations, including, without limitation, the advancement of construction at Velvet-Wood to Phase Two and production targeted for the end of 2026; and statements regarding the Media Services Agreement with Goldwyn and the transactions contemplated thereunder, including the necessary filings with and approval of the TSXV. Forward-looking statements involve risks, uncertainties and other factors that could cause actual results, performance and opportunities to differ materially from those implied by such forward looking statements. Factors that could cause actual results to differ materially from these forward-looking statements include, among other things: risks that the development, operational and economic results of the PEA may differ from projections; risks that construction and/or production Velvet-Wood may not progress as contemplated; risks that the transactions contemplated under the Media Services Agreement may not be completed as contemplated, or at all; the risks and uncertainties relating to exploration and development; the ability of the Company to obtain additional financing; the need to comply with environmental and governmental regulations in Canada and the United States; fluctuations in the prices of commodities; operating hazards and risks; competition and other risks and uncertainties and other such factors as are set forth in the annual information form for the Company’s most recently completed year end, as well as the management discussion and analysis and other disclosures of risk factors for the Company, filed on SEDAR+ at www.sedarplus.ca. Although the Company believes that the information and assumptions used in preparing the forward-looking statements are reasonable, undue reliance should not be placed on these statements, which only apply as of the date of this news release, and no assurance can be given that such events will occur in the disclosed time frames or at all. Except where required by applicable law, the Company disclaims any intention or obligation to update or revise any forward-looking statement, whether as a result of new information, future events or otherwise.

_____________________

1 Please see the technical report entitled “The Shootaring Canyon Mill and Tributary Mines, Utah and Colorado, USA, Preliminary Economic Assessment, National Instrument 43-101” dated effective May 4, 2026 available on the Company’s issuer profile on SEDAR+.

FAQ

What key economic results did Anfield Energy (AEC) report from its 2026 PEA?

The updated PEA shows very strong economics, with a pre-tax IRR of 106% and NPV of US$606 million, and post-tax IRR of 97% and NPV of US$533 million at an 8% discount rate, plus a projected 1.3-year payback.

What production levels does Anfield Energy (AEC) target in its hub-and-spoke model?

The PEA outlines average annual production over a 15-year mine life of about 1.3 million pounds U₃O₈ and 6.4 million pounds V₂O₅, processed at the Shootaring Canyon Mill using ore from multiple Utah and Colorado mines.

When does Anfield Energy expect production from Velvet-Wood and the Shootaring Mill?

Anfield targets production at the Velvet-Wood project by the end of 2026, following completion of Phase One construction, and aims to transition the fully permitted Shootaring Canyon Mill to operations with production targeted for 2027.

How much pre-production capital spending does Anfield Energy anticipate?

The updated PEA estimates pre-production capital expenditures of approximately US$97 million, including contingency, over a 12-month period for mine and mill development within Anfield’s integrated hub-and-spoke uranium-vanadium strategy.

What is the value of Anfield Energy’s media services agreement with Goldwyn?

Anfield entered a three-month media services agreement with Goldwyn Media LLC, under which it will pay US$200,000 for marketing and public awareness services, subject to TSX Venture Exchange filing requirements and approval, with no equity-based compensation involved.

How is Anfield Energy addressing permitting and regulatory matters at its U.S. projects?

Anfield advanced permitting by submitting a revised Plan of Operations for JD-8 and an NOI for SM-18. After SM-18’s NOI was denied and reconsideration refused, the company filed for a hearing and is discussing a potential compromise with regulators.

Filing Exhibits & Attachments

1 document