Aris Mining starts bridge build for Toroparu

Aris Mining has started building a key 109‑metre bridge in Guyana to support Toroparu while advancing growth projects toward a potential 1 million ounce annual production profile.

(Neutral)
(Neutral)
Form Type
6-K

Rhea-AI Filing Summary

Aris Mining Corp (ARIS) reports that it has begun construction of a 109‑metre modular steel bridge across the Puruni River at Puruni Landing in Guyana, a permanent crossing that will complement the existing pontoon and strengthen logistics access to the Toroparu Gold Project.

The bridge is being advanced by Aris Mining’s Guyana project team while the Toroparu Prefeasibility Study continues, with completion of the study targeted for Q4 2026 and a Toroparu construction decision expected in early 2027. Construction of the bridge is being carried out in coordination with the Government of Guyana, with bridge completion targeted for December 2026.

Aris Mining operates the Segovia and Marmato underground gold mines in Colombia, which together produced approximately 257,000 ounces of gold in 2025, and is advancing expansion projects expected to increase annual production to approximately 500,000 ounces, with a longer-term objective of approximately 1 million ounces per year including potential contributions from Soto Norte and Toroparu.

Positive

  • None.

Negative

  • None.
Puruni Bridge length 109 metres Length of the modular steel bridge across the Puruni River at Puruni Landing
Gold production 2025 257,000 ounces Combined 2025 gold production from Segovia and Marmato underground mines
Target annual production after expansions 500,000 ounces Expected annual gold production from Segovia and Marmato following expansion projects
Longer-term annual production objective 1,000,000 ounces Company’s stated longer-term objective for annual gold production including potential from Soto Norte and Toroparu
Toroparu PEA throughput 7.0 million tonnes per annum Throughput rate contemplated in the Toroparu preliminary economic assessment effective October 21, 2025
Toroparu PEA mine life 21.3 years Mine life contemplated in the Toroparu preliminary economic assessment
Toroparu PEA average annual gold production 235,000 ounces Average annual gold production in the Toroparu preliminary economic assessment at US$3,000/oz
Toroparu PFS completion target Q4 2026 Targeted timing for completion of the Toroparu Prefeasibility Study
Prefeasibility Study technical
"while the Toroparu Pre-Feasibility Study (PFS) continues"
A prefeasibility study is an early, high-level assessment that tests whether a proposed project is likely to be technically workable and economically viable before committing large resources. Like a rough blueprint and budget for a construction project, it provides preliminary estimates of costs, potential returns, key risks and data gaps so investors can decide whether to proceed to more detailed studies or funding.
preliminary economic assessment technical
"includes potential production estimates from Toroparu, which is based on a preliminary economic assessment"
A preliminary economic assessment is an initial analysis that estimates the potential profitability and feasibility of a project or resource, such as a new mineral deposit or development venture. It provides a rough idea of costs, benefits, and risks, helping investors decide whether to pursue more detailed studies. This early evaluation is important because it offers a snapshot of whether the project is worth further investment and development.
inferred mineral resources technical
"includes inferred mineral resources that are considered too speculative geologically"
An inferred mineral resource is an estimate of the quantity and grade of minerals in the ground based on limited sampling and geological information, where confidence is low and continuity is uncertain. For investors it signals potential value but also higher risk—like a rough sketch of a hidden treasure that requires much more exploration and testing before you can reliably judge its size or economic worth.
National Instrument 43-101 regulatory
"is a Qualified Person as defined by National Instrument 43-101 (NI 43-101)"
National Instrument 43-101 is a set of rules and guidelines that govern how mineral exploration and mining companies must report information about their projects. It ensures that the details shared with investors are accurate, consistent, and reliable—similar to how a detailed, verified blueprint ensures a building’s safety. This helps investors make informed decisions based on trustworthy information about a company's mineral resources.
CIP plant technical
"construction of the new Marmato bulk mine and CIP plant, with first gold expected"
An CIP plant is an automated cleaning system that washes the inside of pipes, tanks and processing equipment without taking them apart — like an industrial dishwasher for a factory. For investors, a well-designed CIP setup matters because it helps ensure product safety and regulatory compliance, reduces production downtime and labor costs, and lowers the risk of contamination-related recalls that can hurt revenue and reputation.
forward-looking information regulatory
"This news release contains "forward-looking information" or “forward-looking statements""
Forward-looking information are predictions, plans, estimates or expectations about a company’s future performance, results or events, such as sales forecasts, project timelines, or anticipated costs. It matters to investors because these statements guide expectations but rely on assumptions and uncertain factors—like a weather forecast for a business—so investors should treat them as informed guesses rather than guarantees and consider the risks and possible changes behind the numbers.

FAQ

What project did Aris Mining (ARIS) advance with the new Puruni Bridge?

Aris Mining has commenced construction of a 109‑metre modular steel bridge across the Puruni River at Puruni Landing in Guyana. This permanent crossing is intended to strengthen logistics access to the Toroparu Gold Project while the Toroparu Prefeasibility Study continues.

When is the Puruni Bridge construction expected to be completed for ARIS?

Construction of the Puruni Bridge by Aris Mining is targeted for completion in December 2026. The bridge is being built in coordination with the Ministry of Natural Resources, the Ministry of Public Works and other relevant Guyanese government agencies.

How much gold did Aris Mining (ARIS) produce in 2025?

Aris Mining’s Segovia and Marmato underground gold mines in Colombia together produced approximately 257,000 ounces of gold in 2025. These operations form the company’s current production base in South America.

What is Aris Mining’s medium-term gold production objective?

Aris Mining states that expansion projects at Segovia and Marmato are expected to increase annual gold production to approximately 500,000 ounces, and that its portfolio supports a longer-term objective of approximately 1 million ounces of annual gold production, including potential contributions from Soto Norte and Toroparu.

What are the key timing milestones for Aris Mining’s Toroparu project?

For the Toroparu Gold Project, Aris Mining targets completion of a Prefeasibility Study in Q4 2026 and indicates that a construction decision is expected in early 2027, subject to necessary permits and formal approvals.

What production profile does the Toroparu preliminary economic assessment contemplate for ARIS?

The preliminary economic assessment for Toroparu, effective October 21, 2025, contemplates a 7.0 Mtpa operation over a 21.3‑year mine life with average annual gold production of approximately 235,000 ounces at a base case gold price of US$3,000/oz, while noting its preliminary nature and related uncertainties.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google
Learn about SEC filing dates

 

 

UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549

FORM 6-K

REPORT OF FOREIGN PRIVATE ISSUER
PURSUANT TO RULE 13a-16 OR 15d-16
UNDER THE SECURITIES EXCHANGE ACT OF 1934

For the month of September 2026

Commission File Number: 001-41794

Aris Mining Corporation
(Translation of registrant's name into English)

Suite 2400 - 1021 West Hastings St., Vancouver, BC, Canada V6E 0C3

(Address of principal executive offices)

 

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.


Form 20-F ☐      Form 40-F ☒

  

 

SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

  ARIS MINING CORPORATION
     
Date: September 8, 2026 By: (s) Ashley Baker
    Ashley Baker
    Chief Legal Officer

 

EXHIBIT INDEX    
     
Exhibit Number   Description
     
99.1   Press Release dated September 8, 2026

 

 

  

 

 

Exhibit 99.1

 

 

NEWS RELEASE

 

TSX & NYSE: ARIS

aris-mining.com

 

ARIS MINING BEGINS CONSTRUCTION OF THE PURUNI BRIDGE IN GUYANA

The permanent crossing will improve a key logistics link to the Toroparu Gold Project

Vancouver, Canada, September 8, 2026 – Aris Mining Corporation (Aris Mining or the Company) (TSX: ARIS; NYSE: ARIS) has commenced construction of a permanent bridge across the Puruni River at Puruni Landing in Guyana. The 109-metre modular steel bridge will provide a permanent crossing in addition to the existing pontoon crossing, strengthening an important access route to the Toroparu Gold Project while also improving access for other users of the Puruni corridor.

The bridge is an early infrastructure initiative being advanced by Aris Mining’s Guyana project team while the Toroparu Pre-Feasibility Study (PFS) continues. Toroparu’s planned route includes moving heavy equipment and cargo by barge to Itaballi and then by road to Toroparu, crossing the Puruni River at Puruni Landing.

Neil Woodyer, Chair and CEO of Aris Mining, commented: “With our Guyana project team in place, we are pleased to begin this early infrastructure work while we advance the Toroparu PFS toward completion in Q4 2026. Working in cooperation with the Government of Guyana, we are delivering practical infrastructure that supports Toroparu and provides broader benefits in the region.”

The bridge is expected to improve connectivity for communities, businesses and other users of the Puruni corridor. The permanent crossing will allow heavy industrial traffic to be diverted away from the main community road.

Construction of the bridge is being undertaken by Aris Mining in coordination with the Ministry of Natural Resources, the Ministry of Public Works and other relevant agencies, with completion targeted for December 2026.

About Aris Mining

Aris Mining is a Canadian gold mining company focused on South America. The Company operates the Segovia and Marmato underground gold mines in Colombia, which together produced approximately 257,000 ounces of gold in 2025. Aris Mining is listed on the Toronto Stock Exchange and the New York Stock Exchange under the symbol ARIS.

The Company is advancing expansion projects at Segovia and Marmato that are expected to increase annual gold production to approximately 500,000 ounces, driven by the ramp-up at Segovia following the installation of the second mill which was completed in June 2025, and construction of the new Marmato bulk mine and CIP plant, with first gold expected in Q4 2026.

Aris Mining’s portfolio supports a longer-term objective of approximately 1 million ounces of annual gold production. Key projects include the high-grade Soto Norte gold project in Colombia and the Toroparu gold project in Guyana, where a Prefeasibility Study is in progress and a construction decision is expected in early 2027.

 

     

1 Reflects expected steady-state annual gold production of approximately 300 thousand ounces (koz) at Segovia and 200 koz at Marmato following completion and ramp-up of the respective expansion projects. For more information, please refer to the Company’s news releases dated June 30, 2025 regarding the Segovia expansion and March 12, 2025 regarding the Marmato expansion.

 

2 Includes potential production estimates from Toroparu, which is based on a preliminary economic assessment effective October 21, 2025, which contemplates a 7.0 Mtpa operation over a 21.3-year mine life with average annual gold production of approximately 235 koz at a base case gold price of US$3,000/oz. The preliminary economic assessment is preliminary in nature and includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the preliminary economic assessment will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability. There can be no assurance that the projected production will be achieved. Such production also remains subject to obtaining all necessary permits and to formal construction decisions by the Company, in each case for both Soto Norte and Toroparu.

  

 

 

 

NEWS RELEASE

 

TSX & NYSE: ARIS

aris-mining.com

 

Additional information on Aris Mining can be found at www.aris-mining.com, www.sedarplus.ca, and on www.sec.gov.

 

Aris Mining Contact

Oliver Dachsel

Lillian Chow

Senior Vice President, Capital Markets Director, Investor Relations & Communications
+1.917.847.0063 info@aris-mining.com

 

Qualified Person and Technical Information

Pamela De Mark, P.Geo., Senior Vice President Geology and Exploration of Aris Mining, is a Qualified Person as defined by National Instrument 43-101 (NI 43-101), and has reviewed and approved the technical information contained in this news release.

Forward-Looking Information

This news release contains "forward-looking information" or “forward-looking statements" within the meaning of Canadian securities legislation. All statements included herein, other than statements of historical fact, including, without limitation, statements under the “About Aris Mining” heading relating to the Company’s ability to deliver on its 2026 objectives, updates and timing for completion, and first gold pour and ramp-up at the Marmato CIP plant, the timeline for a Prefeasibility Study and construction decision for the Toroparu Project, the objective of reaching 1 million ounces of gold production, and the timeline for completion and expected benefits derived from the Puruni Bridge, are forward-looking. Generally, the forward-looking information and forward looking statements can be identified by the use of forward looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", "will continue" or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved”. The material factors or assumptions used to develop forward looking information or statements are disclosed throughout this news release.

Forward looking information and forward looking statements, while based on management's best estimates and assumptions, are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Aris Mining to be materially different from those expressed or implied by such forward-looking information or forward looking statements, including but not limited to those factors discussed in the section entitled "Risk Factors" in Aris Mining's annual information form dated March 11, 2026 which is available on SEDAR+ at www.sedarplus.ca and included as part of the Company’s Annual report on Form 40-F, filed with the SEC at www.sec.gov.

Although Aris Mining has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information and forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such information or statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information or statements. The Company discloses in its Management's Discussion and Analysis and other publicly filed documents, changes to material factors or assumptions underlying the forward-looking information and forward-looking statements and to the validity of the information, in the period the changes occur. The forward-looking statements and forward-looking information are made as of the date hereof and Aris Mining disclaims any obligation to update any such factors or to publicly announce the result of any revisions to any of the forward-looking statements or forward-looking information contained herein to reflect future results. Accordingly, readers should not place undue reliance on forward-looking statements and information.

  

 

 

 

 

Filing Exhibits & Attachments

1 document

Keep reading