STOCK TITAN

Barrick (NYSE: B) Q1 profit jumps, adds $3B buyback and plans North American IPO

Filing Impact
(Neutral)
Filing Sentiment
(Neutral)
Form Type
6-K

Rhea-AI Filing Summary

Barrick Mining Corporation reported strong first-quarter 2026 results, with revenue of $5.22 billion and net earnings of $1.60 billion, driven mainly by higher gold prices and solid operations. Gold production was 719,000 ounces and copper production 49,000 tonnes.

Net earnings per share rose to $0.96, while adjusted EPS reached $0.98, up 256% and 180% from Q1 2025. Attributable EBITDA was $2.76 billion with a 66% margin, and free cash flow climbed to $1.58 billion. The company declared a quarterly dividend of $0.175 per share.

Barrick’s board authorized a new share repurchase program of up to $3.0 billion over 12 months and reiterated 2026 production and cost guidance for both gold and copper. Key growth projects, including Fourmile and the Lumwana Super Pit Expansion, advanced on time and on budget, while planning continued for a 2026 IPO of Barrick’s North American gold assets.

Positive

  • Strong earnings and cash flow growth: Q1 2026 revenue rose to $5.22 billion and net earnings to $1.60 billion, with free cash flow of $1.58 billion and a 66% attributable EBITDA margin, all sharply higher than Q1 2025.
  • Large capital return via buyback and dividend: The board approved a new authorization to repurchase up to $3.0 billion of common shares over 12 months and declared a $0.175 per share quarterly dividend aligned with a 50% free cash flow payout policy.
  • Reaffirmed 2026 production and cost guidance: Barrick maintained 2026 guidance for 2.90–3.25 million ounces of gold and 190,000–220,000 tonnes of copper, with detailed cost ranges, supporting visibility into planned volumes and unit costs.

Negative

  • None.

Insights

Q1 2026 shows sharp earnings and cash flow growth, plus a sizable buyback and reaffirmed guidance.

Barrick delivered revenue of $5.22 billion, up 67% year over year, and net earnings of $1.60 billion. Net EPS of $0.96 and adjusted EPS of $0.98 rose 256% and 180% versus Q1 2025, mainly from a much higher realized gold price and strong gold and copper contributions.

Cash generation was strong, with operating cash flow of $2.55 billion, attributable operating cash flow of $1.97 billion, and free cash flow of $1.58 billion. Attributable EBITDA reached $2.76 billion, giving a robust 66% margin, while net cash (cash exceeding debt) improved to $2.41 billion, supporting balance sheet strength.

The board authorized up to $3.0 billion of share repurchases over 12 months and kept 2026 gold production guidance at 2.90–3.25 million ounces and copper at 190,000–220,000 tonnes. Progress at Fourmile and the Lumwana Super Pit Expansion and the plan to IPO North American Barrick by year-end 2026 frame a multi-year growth and portfolio reshaping story, while the slowdown at Reko Diq adds some project-timing uncertainty.

Revenue $5,218 million For the three months ended March 31, 2026
Net earnings $1,602 million For the three months ended March 31, 2026
Net EPS $0.96 per share Basic and diluted, Q1 2026
Operating cash flow $2,554 million Net cash provided by operating activities, Q1 2026
Free cash flow $1,575 million Consolidated free cash flow, Q1 2026
Gold production 719,000 ounces Attributable gold production, Q1 2026
Copper production 49,000 tonnes Attributable copper production, Q1 2026
Share repurchase authorization $3.0 billion Maximum common shares buyback over next 12 months
All-in sustaining costs financial
"All-in sustaining costs (“AISC”)3 were $1,708 per ounce, down 4% compared to Q1 2025."
All-in sustaining costs (AISC) is a per-unit measure used mainly in the mining sector that captures the full ongoing cost to produce a unit of metal, including operating expenses, sustaining capital (maintenance of current operations), and a share of corporate overhead and site-level costs. Investors use AISC to judge whether production generates real profit and sustainable cash flow—think of it as the total monthly household cost to keep a home running, not just the utility bill.
Tier One Gold Asset financial
"The Fourmile project in Nevada continued to demonstrate its potential to become a standalone Tier One Gold Asset5."
A tier one gold asset is a top-quality gold mine or deposit that combines large size, long expected life and consistently low production cost, making it a reliable long-term source of gold. For investors it matters because these assets are like blue-chip properties in real estate: they tend to generate steady, predictable cash flow, resist price swings better than smaller projects, and form a safer foundation for company value and growth plans.
attributable free cash flow financial
"Attributable free cash flow3 in the first quarter were $1.21 billion—up 195% over Q1 2025."
Free cash flow attributable is the amount of cash a company generates from its operations after paying for necessary capital expenses, measured only for the portion that belongs to the company’s owners (excluding minority partners or outside investors). Investors care because it shows the real, reusable cash the owners can use to pay dividends, buy back shares, pay down debt, or reinvest — like the money left in your personal bank account after bills and shared household expenses are paid.
initial public offering financial
"Barrick is on track to complete the IPO by the end of 2026, subject to market and other conditions and necessary approvals."
An initial public offering (IPO) is when a private company first sells its shares to the public and becomes a stock-listed company. It matters because it allows the company to raise money from a wide range of investors, helping it grow, while giving early shareholders a way to sell some of their ownership.
non-GAAP financial measures financial
"The following table reconciles these non-GAAP financial measures to the most directly comparable IFRS measure."
Non-GAAP financial measures are numbers companies use to show their financial performance that exclude certain expenses or income. They help investors see how the company might perform without one-time costs or other unusual items, giving a different perspective from official reports. However, since they can be adjusted, they don’t always tell the full story and should be looked at alongside standard financial figures.
 
 

UNITED STATES

SECURITIES AND EXCHANGE COMMISSION

Washington, D.C. 20549

 

 

Form 6-K

 

 

REPORT OF FOREIGN PRIVATE ISSUER

PURSUANT TO RULE 13a-16 OR 15d-16

UNDER THE SECURITIES EXCHANGE ACT OF 1934

For the month of May 2026

Commission File Number: 1-9059

 

 

Barrick Mining Corporation

(Registrant’s name)

 

 

 

Brookfield Place, TD Canada Trust Tower,

Suite 3700

161 Bay Street, P.O. Box 212

Toronto, Ontario Canada M5J 2S1

(800) 720-7415

 

310 South Main Street

Suite 1150

Salt Lake City, Utah 84101

(801) 990-3745

(Address of principal executive offices)

 

 

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.

Form 20-F ☐   Form 40-F ☒

 

 
 


INCORPORATION BY REFERENCE

Exhibit 99.1 to this report on Form 6-K is furnished, not filed, and will not be incorporated by reference into any registration statement.

Exhibit 99.2 to this report on Form 6-K is hereby incorporated by reference into the Registration Statements on Form F-3 (File No. 333-206417), Form S-8 (File Nos. 333-121500, 333-131715, 333-135769, 333-224560) and Form F-10 (File No. 333-287021).


SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

 

Date: May 11, 2026     BARRICK MINING CORPORATION
    By:   /s/ Joseph Heckendorn
    Name:   Joseph Heckendorn
    Title:   Senior Vice-President, Corporate Secretary and Associate General Counsel


EXHIBIT INDEX

 

Exhibits

  

Description

99.1    2026 Q1 Report Press Release dated May 11, 2026
99.2    Barrick Mining Corporation’s Comparative Unaudited Financial Statements prepared in accordance with International Financial Reporting Standards and the notes thereto for the three months ended March 31, 2026 and Management’s Discussion and Analysis for the same periods

Exhibit 99.1

 

LOGO

Barrick Reports First Quarter 2026 Results

Disciplined execution drives strong operational and financial performance

 

Q1 gold production of 719,000 ounces1 beats guidance of 640,000–680,000 ounces1, driven by strong performances at NGM and Veladero, and the ramp-up at Loulo-Gounkoto; copper production of 49,000 tonnes1 in line with plan.

 

Gold costs per ounce were better than plan, driven by efficiencies in mining and processing: gold COS2 of $1,922 per ounce, TCC3 of $1,327 per ounce, and AISC3 of $1,708 per ounce.

 

Operating cash flow of $2.55 billion increased 111% year-on-year, attributable operating cash flow of $1.97 billion increased 89% year-on-year, and attributable free cash flow3 of $1.21 billion was up 195% year-on-year.

 

Strong earnings supported by a higher realized gold price3: net earnings per share of $0.96 rose 256% year-on-year, and adjusted net earnings per share3 of $0.98 rose 180% year-on-year.

 

Gold production expected to increase sequentially throughout the year with Q2 gold production of 730,000–770,000 ounces1; full year production and cost guidance remains unchanged.

 

North American Barrick IPO progressing as planned, targeting completion by year end.

 

$0.175 per share quarterly dividend declared and new $3.0 billion share buyback program announced.

All amounts expressed in U.S. dollars

Toronto, May 11, 2026 – Barrick Mining Corporation (NYSE:B)(TSX:ABX) (“Barrick” or the “Company”) today reported first quarter operating and financial results for the period ended March 31, 2026. Barrick produced 719,000 ounces1 of gold and 49,000 tonnes1 of copper in the quarter. The Company generated $5.22 billion in revenue, $2.55 billion in operating cash flow, $1.97 billion in attributable operating cash flow3, and $1.21 billion in attributable free cash flow3. Net earnings per share for the quarter were $0.96, and adjusted net earnings per share3 were $0.98—up 256% and 180%, respectively, from Q1 2025.

Mark Hill, President and Chief Executive Officer, said: “We started the year with another strong quarter. Building on momentum from Q4, we operated safely and outperformed our plan on both gold production and costs. Our performance allowed us to capture even more of the higher gold price, producing significantly higher earnings and cash flow compared to a year ago. Our growth pipeline advanced, with good progress at Lumwana and Fourmile. Most importantly, we continued to improve safety.”


Mark Hill continued: “Our focus for the year is clear: continue to improve safety performance, deliver on production and cost guidance, advance our growth projects on time and on budget, and execute the North American Barrick IPO to unlock further shareholder value.”

Operational Highlights

Firm in its belief that safe delivery and operational excellence are inseparable, Barrick continued to strengthen safety practices. Senior executives initiated a new practice of participating in on-site safety briefings every quarter.

Gold production in the first quarter totaled 719,000 ounces1, exceeding the guidance range of 640,000–680,000 ounces1. Three primary factors drove our performance: strong underground mining and processing at NGM, higher throughput and grades at Veladero, and a faster than expected ramp up at Loulo-Gounkoto. Gold costs per ounce increased year-on-year primarily due to higher royalties, less favorable production mix and inflationary pressure, but came in below our plan for the quarter. Gold cost of sales (“COS”)2 for Q1 were $1,922 per ounce, compared to COS2 of $1,629 in Q1 2025. Total cash costs (“TCC”)3 were $1,327 per ounce, compared to $1,220 in the prior-year quarter. All-in sustaining costs (“AISC”)3 were $1,708 per ounce, down 4% compared to Q1 2025.

Copper production rose 11% year-on-year to 49,000 tonnes1 in the first quarter. Copper COS4 of $3.41 per pound, C1 cash costs3 of $2.57 per pound and AISC3 of $3.67 per pound were up 17%, 14% and 20%, respectively, compared to the prior-year period. Royalties tied to the higher realized copper price3 and increased site operating costs drove the increases.

Financial Highlights

Higher gold production, lower costs, and a supportive gold price drove year-on-year growth in earnings and cash generation. Net earnings totaled $1.60 billion ($0.96 per share) and adjusted net earnings3 totaled $1.65 billion ($0.98 per share), compared to net earnings of $474 million ($0.27 per share) and adjusted net earnings3 of $603 million ($0.35 per share) in the prior-year quarter. Attributable EBITDA3 for the quarter totaled $2.76 billion, an increase of 103% over the prior-year quarter, with an attributable EBITDA margin3 of 66%.

Operating cash flow, attributable operating cash flow3 and attributable free cash flow3 in the first quarter were $2.55 billion, $1.97 billion and $1.21 billion—up 111%, 89% and 195% over Q1 2025, respectively. Revenues of $5.22 billion increased 67% from $3.13 billion in the prior-year quarter.

Key Growth Projects

The Fourmile project in Nevada continued to demonstrate its potential to become a standalone Tier One Gold Asset5. With the implementation of additional safety measures, drilling activity continued through winter, adding over three months of previously unavailable drilling time. The additional drilling time is helping accelerate progress on resource definition in the southern areas and extensional opportunities. Drilling is planned to be expanded throughout 2026. Ongoing PFS studies are expected to support the potential for significant resource growth, with a full PFS expected to be completed in 2028.

Construction at the Lumwana Super Pit Expansion continued to advance on time and on budget during the quarter. The initial lift of the mill building wall was completed in Q1, with mill shells delivered to site

 

BARRICK FIRST QUARTER 2026   2    PRESS RELEASE


and the first loads of structural steel expected in Q2. Capital expenditure for 2026 is expected to come in at the lower end of the $750–$850 million guidance range, with total project capital anticipated at $2 billion. First copper production from the expansion remains on track for the end of Q1 2028.

Returns to Shareholders

A quarterly dividend of $0.175 per share has been declared in respect of performance for the first quarter of 2026. The Q1 2026 dividend will be paid on June 15, 2026 to shareholders of record at the close of business on May 29, 2026.

Barrick’s dividend policy targets a total payout of 50% of attributable free cash flow on an annualized basis, comprised of a fixed base quarterly dividend of $0.175 per share and a performance top-up component at each year-end based on the attributable free cash flow during the year. The dividend paid in any given year may be higher or lower than the 50% target based on the strength of cash flow, capital needs, balance sheet considerations, and other factors.

In addition to the quarterly dividend, and following solid Q1 execution and strong free cash flow, Barrick’s Board of Directors has authorized the repurchase of up to $3.0 billion of the Company’s outstanding common shares at prevailing market prices. This authorization is intended to return cash to shareholders at a time when Barrick sees exceptional value in its own shares, particularly in anticipation of the planned IPO of North American Barrick. The repurchase authorization does not oblige the Company to acquire common shares.

2026 Guidance

Barrick is on track to meet 2026 guidance. Gold production guidance for 2026 continues to be 2.90–3.25 million ounces1, with 730,000–770,000 ounces1 expected in the second quarter, further increasing in Q3 and Q4, in line with typical seasonality. Gold cost guidance for 2026, including COS2 of $1,870–$2,070 per ounce, TCC of $1,330–$1,470 per ounce, and AISC3 of $1,760–$1,950 per ounce, is based on a gold price assumption of $4,500 per ounce.

Copper production guidance for 2026 remains unchanged at 190,000–220,000 tonnes1 at copper COS4 of $3.05–$3.35 per pound, C1 cash costs3 of $2.20–$2.45 per pound, and AISC3 of $3.45–$3.75 per pound. Copper cost guidance is based on a copper price assumption of $5.50 per pound.

2026 cost guidance is based on an oil price (WTI) assumption of $70 per barrel. For every $10 per barrel change in the oil price, the direct impact on costs associated with diesel consumption is $12 per ounce across our gold operations, and $0.04 per pound across our copper sites.

North American IPO

On April 28, 2026, Barrick provided an update regarding the planned initial public offering (“IPO”) of a minority stake of a company that will hold Barrick’s North American gold assets, being Barrick’s stakes and operatorship of Nevada Gold Mines and Pueblo Viejo, as well as the Fourmile project. Barrick is on track to complete the IPO by the end of 2026, subject to market and other conditions and necessary approvals. The anticipated IPO will abide by all applicable commitments in Barrick’s Joint Venture Agreements and, while Barrick is free to pursue the IPO unilaterally, it is working closely with its Joint Venture partner, so that value is created and maximized for all.

 

BARRICK FIRST QUARTER 2026   3    PRESS RELEASE


Presentation and Webcast

The management team will host a live webcast and presentation today at 11:00 AM ET followed by a question-and-answer session with analysts. To join the webcast, please register here. Presentation materials will be available on Barrick’s website prior to the event with a replay available soon after.

About Barrick Mining Corporation

Barrick is a leading global mining, exploration and development company. With one of the largest portfolios of world-class and long-life gold and copper assets in the industry, Barrick’s operations and projects span 17 countries and five continents. Barrick is also the largest gold producer in the United States. We create real, long-term value for all stakeholders through responsible mining, strong partnerships and a disciplined approach to growth. Barrick shares trade on the New York Stock Exchange under the symbol ‘B’ and on the Toronto Stock Exchange under the symbol ‘ABX’.

 

Investor Relations Contact

Barrick Mining Corporation

Cleve Rueckert, +1 775 397 5443

cleveland.rueckert@barrick.com

Media Contact

Brunswick Group

Carole Cable, +44 (0) 20 7404 5959

barrick@brunswickgroup.com

 

 

BARRICK FIRST QUARTER 2026   4    PRESS RELEASE


Financial and Operating Highlights

 

              For the three months ended  
           3/31/26        12/31/25        % Change        3/31/25        % Change  

Financial Results ($ millions)

                 

Revenues

        5,218        5,997        (13)%        3,130        67 %  

Cost of sales

        2,099        2,712        (23)%        1,785        18 %  

Net earningsa

        1,602        2,406        (33)%        474        238 %  

Adjusted net earningsb

        1,648        1,754        (6)%        603        173 %  

Attributable EBITDAb

        2,760        3,084        (11)%        1,361        103 %  

Attributable EBITDA marginb

        66 %        64 %        3 %        51 %        29 %  

Minesite sustaining capital expendituresb,c

        380        458        (17)%        564        (33)%  

Project capital expendituresb,c

        570        630        (10)%        269        112 %  

Total consolidated capital expendituresc,d

        979        1,107        (12)%        837        17 %  

Total attributable capital expenditurese

        755        906        (17)%        631        20 %  

Net cash provided by operating activities

        2,554        2,726        (6)%        1,212        111 %  

Net cash provided by operating activities marginf

        49 %        45 %        9 %        39 %        26 %  

Attributable operating cash flowb

        1,968        1,966        0 %        1,042        89 %  

Free cash flowb

        1,575        1,619        (3)%        375        320 %  

Net earnings per share (basic and diluted)

        0.96        1.43        (33)%        0.27        256 %  

Adjusted net earnings (basic)b per share

        0.98        1.04        (6)%        0.35        180 %  

Weighted average diluted common shares (millions of shares)

        1,675        1,684        (1)%        1,725        (3)%  

Debt (current and long-term)

        4,726        4,703        0 %        4,727        0 %  

Cash and equivalents

        7,131        6,706        6 %        4,104        74 %  

Debt, net of cash

              (2,405)        (2,003)        20 %        623        (486)%  

 

a.

Net earnings represents net earnings attributable to the equity holders of the Company.

 

b.

Further information on these non-GAAP financial measures, including detailed reconciliations, is included in the endnotes to this press release.

 

c.

Amounts presented on a consolidated cash basis. Project capital expenditures are not included in our calculation of all-in sustaining costs.

 

d.

Total consolidated capital expenditures also includes capitalized interest of $29 million for Q1 2026 (Q4 2025: $19 million; Q1 2025: $4 million).

 

e.

These amounts are presented on the same basis as our guidance.

 

f.

Represents net cash provided by operating activities divided by revenue.

 

              For the three months ended  
           3/31/26        12/31/25        % Change        3/31/25        % Change  

Operating Results

                 

Gold

                 

Gold production (thousands of ounces)a

        719        871        (17)%        758        (5)%  

Gold sold (thousands of ounces)a

        748        960        (22)%        751        0 %  

Market gold price ($/oz)

        4,873        4,135        18 %        2,860        70 %  

Realized gold pricea,b ($/oz)

        4,823        4,177        15 %        2,898        66 %  

Gold COS (Barrick’s share)a,c ($/oz)

        1,922        1,904        1 %        1,629        18 %  

Gold TCCa,b ($/oz)

        1,327        1,205        10 %        1,220        9 %  

Gold AISCa,b ($/oz)

        1,708        1,581        8 %        1,775        (4)%  

Revenue ($ millions)a

        3,682        4,111        (10)%        2,214        66 %  

Attributable EBITDA ($ millions)b

        2,480        2,708        (8)%        1,136        118 %  

Copper

                 

Copper production (thousands of tonnes)a

        49        62        (21)%        44        11 %  

Copper sold (thousands of tonnes)a

        45        67        (33)%        51        (12)%  

Market copper price ($/lb)

        5.83        5.03        16 %        4.24        38 %  

Realized copper pricea,b ($/lb)

        5.79        5.42        7 %        4.51        28 %  

Copper COS (Barrick’s share)a,d ($/lb)

        3.41        3.37        1 %        2.92        17 %  

Copper C1 cash costsa,b ($/lb)

        2.57        2.45        5 %        2.25        14 %  

Copper AISCa,b ($/lb)

        3.67        3.61        2 %        3.06        20 %  

Revenue ($ millions)a

        556        769        (28)%        474        17 %  

Attributable EBITDA ($ millions)b

              280        376        (26)%        199        41 %  

 

a.

On an attributable basis.

 

b.

Further information on these non-GAAP financial measures, including detailed reconciliations, is included in the endnotes to this press release.

 

c.

Gold COS/oz is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share).

 

d.

Copper COS/lb is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share).

 

BARRICK FIRST QUARTER 2026   5    PRESS RELEASE


Regional Summarya and 2026 Guidanceb

 

            For the three months ended     

  2026  

   Guidance   

 
           3/31/26         12/31/25         3/31/25  

Gold

              

North America

              

Gold produced (000s oz)

        457        595        454        1,770 - 1,980  

Gold sold (000s oz)

        462        608        460     

COS ($/oz)d

        1,783        1,663        1,687        1,820 - 2,010  

TCC ($/oz)c

        1,213        1,169        1,272        1,270 - 1,410  

AISC ($/oz)c

        1,612        1,460        1,843        1,690 - 1,870  

Revenue ($ millions)

        2,253        2,604        1,353     

Attributable EBITDA ($ millions)c

        1,552        1,730        668     

South America & Asia Pacific

              

Gold produced (000s oz)

        74        72        92        630 - 730  

Gold sold (000s oz)

        76        69        89     

COS ($/oz)d

        1,773        1,553        1,267        1,490 - 1,590  

TCC ($/oz)c

        1,126        983        890        940 - 1,020  

AISC ($/oz)c

        1,393        1,898        1,368        1,430 - 1,530  

Revenue ($ millions)

        376        289        264     

Attributable EBITDA ($ millions)c

        261        155        162     

Africa & Middle East

              

Gold produced (000s oz)

        188        204        212        820 - 910  

Gold sold (000s oz)

        210        283        202     

COS ($/oz)d

        2,281        2,527        1,639        1,420 - 1,520  

TCC ($/oz)c

        1,633        1,364        1,244        1,060 - 1,140  

AISC ($/oz)c

        1,836        1,575        1,602        1,360 - 1,460  

Revenue ($ millions)

        1,053        1218        597     

Attributable EBITDA ($ millions)c

              667        823        306           

Total Gold

              

Gold produced (000s oz)

        719        871        758        2,900 - 3,250  

Gold sold (000s oz)

        748        960        751     

COS ($/oz)d

        1,922        1,904        1,629        1,870 - 2,070  

TCC ($/oz)c

        1,327        1,205        1,220        1,330 - 1,470  

AISC ($/oz)c

        1,708        1,581        1,775        1,760 - 1,950  

Revenue ($ millions)

        3,682        4,111        2,214     

Attributable EBITDA ($ millions)c

              2,480        2,708        1,136           

Total Copper

              

Copper produced (kt)

        49        62        44        190 - 220  

Copper sold (kt)

        45        67        51     

COS ($/lb)e

        3.41        3.37        2.92        3.05 - 3.35  

C1 cash costs ($/lb)c

        2.57        2.45        2.25        2.20 - 2.45  

AISC ($/lb)c

        3.67        3.61        3.06        3.45 - 3.75  

Revenue ($ millions)

        556        769        474     

Attributable EBITDA ($ millions)c

              280        376        199           

 

a.

All figures in this table are on an attributable basis.

 

b.

See “Outlook Assumptions and Economic Sensitivity Analysis” in endnote 6 of this press release.

 

c.

Further information on these non-GAAP financial measures, including detailed reconciliations, is included in endnote 3 of this press release.

 

d.

Gold COS/oz is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share).

 

e.

Copper COS/lb is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share).

 

BARRICK FIRST QUARTER 2026   6    PRESS RELEASE


Technical Information

The scientific and technical information contained in this MD&A has been reviewed and approved by Jesse Clark, BSc (Hons), MSc, SMERM, Director, Geology; Richard Peattie, MPhil, FAusIMM, Chief Technical Officer; and Joel Holliday, FAusIMM, Executive Vice-President, Exploration – each a “Qualified Person” as defined in National Instrument 43-101Standards of Disclosure for Mineral Projects.

All mineral reserve and mineral resource estimates are estimated in accordance with National Instrument 43-101Standards of Disclosure for Mineral Projects. Unless otherwise noted, such mineral reserve and mineral resource estimates are as of December 31, 2025.

Endnotes

Endnote 1

On an attributable basis.

Endnote 2

On an attributable basis. Gold COS/oz is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share).

Endnote 3 – Non-GAAP Financial Measures

Total cash costs per ounce and All-in sustaining costs per ounce

“Total cash costs” per ounce (TCC/oz) and “All-in sustaining costs” per ounce (AISC/oz) are non-GAAP financial performance measures which are calculated based on the definition published by the World Gold Council (a market development organization for the gold industry comprised of and funded by gold mining companies from around the world, including Barrick, the “WGC”). The WGC is not a regulatory organization. Management uses these measures to monitor the performance of our gold mining operations and their ability to generate positive cash flow, both on an individual site basis and an overall company basis. TCC/oz start with our cost of sales related to gold production and removes depreciation, the non-controlling interest of cost of sales and costs allocated to by-products. AISC/oz start with TCC/oz and includes sustaining capital expenditures, sustaining leases, general and administrative costs, minesite exploration and evaluation costs related to the current mine plan and reclamation cost accretion and amortization. Barrick believes that the use of TCC/oz and AISC/oz will assist analysts, investors and other stakeholders of Barrick in understanding the costs associated with producing gold, understanding the economics of gold mining, assessing our operating performance and also our ability to generate free cash flow from the gold operations portion of our business. Due to the capital-intensive nature of the industry and the long useful lives over which these items are depreciated, there can be a significant timing difference between net earnings calculated in accordance with IFRS and the amount of free cash flow that is generated by a mine and therefore Barrick believes these measures are useful non-GAAP operating metrics and supplement our IFRS disclosures. These measures are not representative of all of Barrick’s cash expenditures as they do not include income tax payments, interest costs or dividend payments. These measures do not include depreciation or amortization. TCC/oz and AISC/oz are intended to provide additional information only and do not have standardized definitions under IFRS and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. These measures are not equivalent to net income or cash flow from operations as determined under IFRS. Although the WGC has published a standardized definition, other companies may calculate these measures differently. Further details on these non-GAAP financial performance measures are provided in the MD&A accompanying Barrick’s financial statements filed from time to time on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.gov. The following table reconciles these non-GAAP financial measures to the most directly comparable IFRS measure.

 

BARRICK FIRST QUARTER 2026   7    PRESS RELEASE


Reconciliation of Gold Cost of Sales to Total cash costs and All-in sustaining costs, including on a per ounce basis

 

 ($ millions, except per oz information in dollars)

              For the three months ended  
       Footnote        

  3/31/26

        12/31/25         3/31/25  

COS applicable to gold production

        1,874       2,423       1,568  

Depreciation

        (449     (503     (342

Total cash costs applicable to equity method investments

        128       111       109  

Costs allocated to by-products

        (119     (130     (60

Other

      a        (33     (258     5  

Non-controlling interests

      b        (409     (487     (364

Total cash costs

              992       1,156       916  

General & administrative costs

        39       64       42  

Minesite exploration and evaluation costs

      c        4       8       5  

Minesite sustaining capital expenditures

      d        380       458       564  

Sustaining leases

        6       4       8  

Rehabilitation - accretion and amortization (operating sites)

      e        16       16       17  

Non-controlling interest, copper operations and other

      f        (159     (191     (217

All-in sustaining costs

              1,278       1,515       1,335  

Ounces sold - attributable basis (koz)

      g        748       960       751  

COS/oz

     h,i        1,922       1,904       1,629  

TCC/oz

      i        1,327       1,205       1,220  

AISC/oz

      i        1,708       1,581       1,775  

 

a.

   Other - Other adjustments mainly relate to treatment and refining charges.

b.

   Non-controlling interests - Non-controlling interests include non-controlling interests related to gold production of $600 million for Q1 2026, (Q4 2025: $741 million; Q1 2025: $487 million). Non-controlling interests include NGM, Pueblo Viejo, Loulo-Gounkoto, Tongon, North Mara and Bulyanhulu. Refer to Note 5 to the Financial Statements for further information.

c.

   Exploration and evaluation costs - Exploration, evaluation and project expenses are included in AISC if they support current mine operations.

d.

   Capital expenditures - Capital expenditures are related to our gold sites only and are split between minesite sustaining and project capital expenditures.

e.

   Rehabilitation—accretion and amortization - Includes depreciation on the assets related to rehabilitation provisions of our gold operations and accretion on the rehabilitation provision of our gold operations, split between operating and non-operating sites.

f.

   Non-controlling interest and copper operations - Removes general and administrative costs related to non-controlling interests and copper based on a percentage allocation of revenue. Also removes exploration, evaluation and project expenses, rehabilitation costs and capital expenditures incurred by our copper sites and the non-controlling interest of NGM, Pueblo Viejo, Loulo-Gounkoto, Tongon, North Mara and Bulyanhulu operating segments. It also includes capital expenditures applicable to our equity method investment in Kibali. The impact is summarized as the following:

 

 ($ millions)

     For the three months ended  

 Non-controlling interest, copper operations and other

       3/31/26         12/31/25         3/31/25  

 General & administrative costs

     (6     (10     (6

 Minesite exploration and evaluation expenses

     (1     (3     0  

 Rehabilitation - accretion and amortization (operating sites)

     (5     (5     (5

 Minesite sustaining capital expenditures

     (147     (173     (206

 All-in sustaining costs total

     (159     (191     (217

 

   

g.

   Ounces sold - attributable basis - Excludes Long Canyon which is producing residual ounces from the leach pad while in care and maintenance.

h.

   COS/oz - Gold COS/oz is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share).

i.

   Per ounce figures - COS/oz, TCC/oz and AISC/oz may not calculate based on amounts presented in this table due to rounding.

Free Cash Flow, Attributable Free Cash Flow and Attributable Operating Cash Flow

“Free cash flow” is a non-GAAP financial measure that deducts capital expenditures from net cash provided by operating activities. “Attributable free cash flow” starts with free cash flow and adds our attributable share of free cash flow from our equity investees and subtracts the free cash flow attributable to the non-controlling interests. Management believes these to be useful indicators of our ability to operate without reliance on additional borrowing or usage of existing cash. Attributable operating cash flow starts with cash provided by operating activities and adds our attributable share of cash provided by operating activities from our equity investees and subtracts the cash provided by operating activities attributable to the non-controlling interests. Management believes this to be useful indicator of the amount of cash provided by operating activities to Barrick’s ownership share. Free cash flow, attributable free cash flow and attributable operating cash flow are intended to provide additional information only and do not have any standardized definition under IFRS, and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. These measures are not necessarily indicative of

 

BARRICK FIRST QUARTER 2026   8    PRESS RELEASE


operating profit or cash flow from operations as determined under IFRS. Other companies may calculate these measures differently. Further details on this non-GAAP financial performance measure are provided in the MD&A accompanying Barrick’s financial statements filed from time to time on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.gov. The following table reconciles these non-GAAP financial measures to the most directly comparable IFRS measure.

Reconciliation of Net Cash Provided by Operating Activities to Free Cash Flow, Attributable Free Cash Flow and Attributable Operating Cash Flow

 

 ($ millions)

     For the three months ended  
      

  3/31/26

        12/31/25         3/31/25  

 Net cash provided by operating activities

     2,554       2,726       1,212  

 Capital expenditures

     (979     (1,107     (837

 Free cash flow (consolidated)

     1,575       1,619       375  

 Free cash flow applicable to equity investees

     330       172       156  

 Non-controlling interests

     (692     (731     (120

 Attributable free cash flow

     1,213       1,060       411  

 Attributable capital expenditures

     755       906       631  

 Attributable operating cash flow

     1,968       1,966       1,042  

Adjusted Net Earnings and Adjusted Net Earnings per Share

“Adjusted net earnings” and “adjusted net earnings per share” are non-GAAP financial performance measures. Adjusted net earnings excludes the following from net earnings: impairment charges (reversals) related to intangibles, goodwill, property, plant and equipment, and investments; acquisition/disposition gains/losses; foreign currency translation gains/losses; significant tax adjustments; other items that are not indicative of the underlying operating performance of our core mining business; and tax effect and non-controlling interest of the above items. Management uses this measure internally to evaluate our underlying operating performance for the reporting periods presented and to assist with the planning and forecasting of future operating results. Management believes that adjusted net earnings is a useful measure of our performance because impairment charges, acquisition/disposition gains/losses and significant tax adjustments do not reflect the underlying operating performance of our core mining business and are not necessarily indicative of future operating results. Furthermore, foreign currency translation gains/losses are not necessarily reflective of the underlying operating results for the reporting periods presented. The tax effect and non-controlling interest of the adjusting items are also excluded to reconcile the amounts to Barrick’s shares on a post-tax basis, consistent with net earnings. Adjusted net earnings and adjusted net earnings per share are intended to provide additional information only and do not have standardized definitions under IFRS and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. The measures are not necessarily indicative of operating profit or cash flow from operations as determined under IFRS. Other companies may calculate these measures differently. The following table reconciles these non-GAAP financial measures to the most directly comparable IFRS measure. Further details on these non-GAAP financial performance measures are provided in the MD&A accompanying Barrick’s financial statements filed from time to time on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.gov.

Reconciliation of Net Earnings to Net Earnings per Share, Adjusted Net Earnings and Adjusted Net Earnings per Share

 

 ($ millions, except per share amounts in dollars)

     For the three months ended  
      

  3/31/26

        12/31/25         3/31/25  

 Net earnings attributable to equity holders of the Company

     1,602       2,406       474  

 Impairment charges related to intangibles, goodwill, property, plant and equipment, and investmentsa

     0       5       4  

 Acquisition/disposition (gains) lossesb

     1       (1,146     0  

 (Gain) loss on currency translation

     20       6       2  

 Significant tax adjustmentsc

     35       80       (15

 Other expense adjustmentsd

     18       559       173  

 Non-controlling interest

     (8     (101     (11

 Tax effecte

     (20     (55     (24

 Adjusted net earnings

     1,648       1,754       603  

 Net earnings per sharef

     0.96       1.43       0.27  

 Adjusted net earnings per sharef

     0.98       1.04       0.35  

 

a.

There were no significant impairment charges or reversals in the current period or prior periods.

 

BARRICK FIRST QUARTER 2026   9    PRESS RELEASE


b.

Acquisition/disposition gains for Q4 2025 relate to gain on sale of our Hemlo gold mine, our interest in the Tongon gold mine and the Alturas project. Q4 2025 was further impacted by the accounting impact of regaining control of the Loulo-Gounkoto complex on December 16, 2025.

c.

For Q1 2026, significant tax adjustments include the re-measurement of current and deferred tax balances and the impact of uncertain tax positions. For Q4 2025, significant tax adjustments include the resolution of uncertain tax positions, the impact of prior year adjustments and the recognition of deferred tax assets. Significant tax adjustments for Q1 2025 include the re-measurement of deferred tax balances.

d.

Other expense for Q1 2026 period mainly related to the fair value increment on inventory resulting from the purchase price allocation when we regained control of Loulo-Gounkoto, reduced operations costs at Mali, legal and consulting costs related to our North America IPO project and revaluation of contingent consideration for Hemlo. Other expense for 2025 periods mainly related to the reduced operations costs relating to Mali in Q1 2025, the settlement payment to the Government of Mali in November 2025, the fair value increment on inventory resulting from the purchase price allocation when we regained control of Loulo-Gounkoto and severance costs incurred

e.

Tax effect for Q1 2026 mainly relates to Mali other expense adjustments, Q4 2025 primarily relates to acquisition/disposition losses (gains) and Q1 2025 primarily relates to other expense adjustments

f.

Calculated using weighted average number of shares outstanding under the basic method of earnings per share.

C1 cash costs per pound and All-in sustaining costs per pound

“C1 cash costs” per pound (C1 cash costs/lb) and “All-in sustaining costs” per pound (AISC/lb) are non-GAAP financial performance measures related to our copper mine operations. We believe that C1 cash costs/lb enables investors to better understand the performance of our copper operations in comparison to other copper producers who present results on a similar basis. C1 cash costs/lb excludes royalties, production taxes and non-routine charges as they are not direct production costs. AISC/lb is similar to the gold AISC metric and management uses this to better evaluate the costs of copper production. We believe this measure enables investors to better understand the operating performance of our copper mines as this measure reflects all of the sustaining expenditures incurred in order to produce copper. AISC/lb includes C1 cash costs, sustaining capital expenditures, sustaining leases, general and administrative costs, minesite exploration and evaluation costs, royalties, production taxes, reclamation cost accretion and amortization and writedowns taken on inventory to net realizable value. Further details on these non-GAAP financial performance measures are provided in the MD&A accompanying Barrick’s financial statements filed from time to time on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.gov. The following table reconciles these non-GAAP financial measures to the most directly comparable IFRS measure.

Reconciliation of Copper Cost of Sales to C1 cash costs and All-in sustaining costs, including on a per pound basis

 

 ($ millions, except per lb information in dollars)

     For the three months ended  
      

  3/31/26

        12/31/25         3/31/25  

 Cost of sales

     217       281       208  

Depreciation/amortization

     (43     (88     (60

Treatment and refinement charges

     35       53       42  

C1 cash costs applicable to equity method investments

     95       174       90  

Less: royalties

     (30     (37     (21

Costs allocated to by-products

     (18     (22     (5

 C1 cash costs of sales

     256       361       254  

General & administrative costs

     6       11       8  

Rehabilitation - accretion and amortization

     1       1       1  

Royalties

     30       37       21  

Minesite exploration and evaluation costs

     2       3       2  

Minesite sustaining capital expenditures

     66       116       57  

Sustaining leases

     1       2       3  

 All-in sustaining costs

     362       531       346  

 Tonnes sold - attributable basis (thousands of tonnes)

     45       67       51  

 Pounds sold - attributable basis (millions pounds)

     99       147       112  

 COS/lba,b

     3.41       3.37       2.92  

 C1 cash costs per pounda

     2.57       2.45       2.25  

 AISC/lba

     3.67       3.61       3.06  

 

a.

COS/lb, C1 cash costs/lb and AISC/lb may not calculate based on amounts presented in this table due to rounding.

b.

Copper COS/lb is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share).

EBITDA, Adjusted EBITDA, Attributable EBITDA, Attributable EBITDA Margin and Net Leverage

EBITDA is a non-GAAP financial measure, which excludes the following from net earnings: income tax expense; finance costs; finance income; and depreciation. Management believes that EBITDA is a valuable indicator of our ability to generate liquidity by producing operating cash flow to fund working capital needs, service debt obligations, and fund capital expenditures. Management uses EBITDA for this purpose. Adjusted EBITDA removes the effect of impairment charges; acquisition/disposition gains/losses; foreign currency translation gains/losses; and other

 

BARRICK FIRST QUARTER 2026   10    PRESS RELEASE


expense adjustments. We also remove the impact of the income tax expense, finance costs, finance income and depreciation incurred in our equity method accounted investments. Attributable EBITDA further removes the non-controlling interest portion. Barrick believes these items provide a greater level of consistency with the adjusting items included in our adjusted net earnings reconciliation, with the exception that these amounts are adjusted to remove any impact on finance costs/income, income tax expense and/or depreciation as they do not affect EBITDA. Barrick believes this additional information will assist analysts, investors and other stakeholders of Barrick in better understanding our ability to generate liquidity from our attributable business, including equity method investments, by excluding these amounts from the calculation as they are not indicative of the performance of our core mining business and do not necessarily reflect the underlying operating results for the periods presented. Additionally, it is aligned with how we present our forward-looking guidance on gold ounces and copper pounds produced. Attributable EBITDA margin is calculated as attributable EBITDA divided by revenues - as adjusted. We believe this ratio will assist analysts, investors and other stakeholders of Barrick to better understand the relationship between revenues and EBITDA or operating profit. Net leverage is calculated as debt, net of cash divided by the sum of adjusted EBITDA of the last four consecutive quarters. We believe this ratio will assist analysts, investors and other stakeholders of Barrick in monitoring our leverage and evaluating our balance sheet. EBITDA, adjusted EBITDA, attributable EBITDA, EBITDA margin and net leverage are intended to provide additional information to investors and analysts and do not have any standardized definition under IFRS, and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. EBITDA, adjusted EBITDA and attributable EBITDA exclude the impact of cash costs of financing activities and taxes, and the effects of changes in operating working capital balances, and therefore are not necessarily indicative of operating profit or cash flow from operations as determined under IFRS. Other companies may calculate EBITDA, adjusted EBITDA, attributable EBITDA, EBITDA margin and net leverage differently. Further details on these non-GAAP financial performance measures are provided in the MD&A accompanying Barrick’s financial statements filed from time to time on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.gov. The following table reconciles these non-GAAP financial measures to the most directly comparable IFRS measure.

Reconciliation of Net Earnings to EBITDA, Adjusted EBITDA and Attributable EBITDA

 

 ($ millions)

              For the three months ended  

     3/31/26        12/31/25        3/31/25  

 Net earnings

     2,481           3,213           781     

 Income tax expense

     747           794           278     

 Finance costs, neta

     19           42           39     

 Depreciation

     499           599           411     

 EBITDA

     3,746           4,648           1,509     

 Impairment charges of non-current assetsb

     0           5           4     

 Acquisition/disposition losses (gains)c

     1           (1,146)         0     

 (Gain) loss on currency translation

     20           6           2     

 Other expense adjustmentsd

     18           559           173     

 Income tax expense, net finance costsa and depreciation from equity investees

     148           238           141     

 Adjusted EBITDA

     3,933           4,310           1,829     

 Non-controlling Interests

     (1,173)         (1,226)         (468)   

 Attributable EBITDA

     2,760           3,084           1,361     

 Revenues - as adjustede

     4,181           4,810           2,685     

 Attributable EBITDA marginf

     66 %        64 %        51 %  
       As at 3/31/26        As at 12/31/25        As at 3/31/25  

 Net leverageg

     -0.2:1        -0.2:1        0.1:1  

 

a.

Finance costs exclude accretion.

b.

There were no significant impairment charges or reversals in the current period or prior periods.

c.

Acquisition/disposition gains for Q4 2025 relate to gain on sale of our Hemlo gold mine, our interest in the Tongon gold mine and the Alturas project. Q4 2025 was further impacted by the accounting impact of regaining control of the Loulo-Gounkoto complex on December 16, 2025.

d.

Other expense for Q1 2026 period mainly related to the fair value increment on inventory resulting from the purchase price allocation when we regained control of Loulo-Gounkoto, reduced operations costs at Mali, legal and consulting costs related to our North America IPO project and revaluation of contingent consideration for Hemlo. Other expense for 2025 periods mainly related to the reduced operations costs relating to Mali in Q1 2025, the settlement payment to the Government of Mali in November 2025, the fair value increment on inventory resulting from the purchase price allocation when we regained control of Loulo-Gounkoto and severance costs incurred

e.

Refer to Reconciliation of Sales to Realized Price per oz/pound on the next page of this press release.

f.

Represents attributable EBITDA divided by revenues - as adjusted.

g.

Represents debt, net of cash divided by adjusted EBITDA of the last four consecutive quarters.

 

BARRICK FIRST QUARTER 2026   11    PRESS RELEASE


Capital Expenditures

These amounts are presented on the same basis as our guidance. Minesite sustaining capital expenditures and project capital expenditures are non-GAAP financial measures. Capital expenditures are classified into minesite sustaining capital expenditures or project capital expenditures depending on the nature of the expenditure. Minesite sustaining capital expenditures is the capital spending required to support current production levels. Project capital expenditures represent the capital spending at new projects and major, discrete projects at existing operations intended to increase net present value through higher production or longer mine life. Management believes this to be a useful indicator of the purpose of capital expenditures and this distinction is an input into the calculation of all-in sustaining costs per ounce/pound. Classifying capital expenditures is intended to provide additional information only and does not have any standardized definition under IFRS, and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. Other companies may calculate these measures differently. Further details on these non-GAAP financial performance measures are provided in the MD&A accompanying Barrick’s financial statements filed from time to time on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.gov. The following table reconciles these non-GAAP financial performance measures to the most directly comparable IFRS measure.

Reconciliation of the Classification of Capital Expenditures

 

 ($ millions)           For the three months ended  
       
          3/31/26        12/31/25        3/31/25  
 Minesite sustaining capital expenditures      380        458        564  
 Project capital expenditures      570        630        269  
 Capitalized interest      29        19        4  
 Total consolidated capital expenditures      979        1,107        837  

Realized Price

“Realized price” is a non-GAAP financial performance measure which excludes from sales: treatment and refining charges; and cumulative catch-up adjustment to revenue relating to our streaming arrangements. We believe this provides investors and analysts with a more accurate measure with which to compare to market gold and copper prices and to assess our gold and copper sales performance. For those reasons, management believes that this measure provides a more accurate reflection of our Company’s past performance and is a better indicator of its expected performance in future periods. The realized price measure is intended to provide additional information, and does not have any standardized definition under IFRS and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. The measure is not necessarily indicative of sales as determined under IFRS. Other companies may calculate this measure differently. Further details on these non-GAAP financial performance measures are provided in the MD&A accompanying Barrick’s financial statements filed from time to time on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.gov. The following table reconciles realized prices to the most directly comparable IFRS measure.

Reconciliation of Sales to Realized Price per ounce/pound

 

 ($ millions, except per oz/lb information in dollars)           Gold                    Copper          
                        For the three months ended  
      3/31/26     12/31/25     3/31/25     3/31/26      12/31/25      3/31/25  

 Sales

     4,756       5,353       2,766       343        514        304  

 Sales applicable to non-controlling interests

     (1,591     (1,756     (848     0        0        0  

 Sales applicable to equity method investmentsa,b

     446       418       252       196        233        164  

 Sales applicable to sites in closure or care and maintenancec

     (13     (5     (1     0        0        0  

 Treatment and refinement charges

     9       10       6       35        53        42  

 Otherd

     0       (10     0       0        0        0  

 Revenues – as adjusted

     3,607       4,010       2,175       574        800        510  

 Ounces/pounds sold (koz/Mlb)c

     748       960       751       99        147        113  

 Realized gold/copper price per oz/lbe

     4,823       4,177       2,898       5.79        5.42        4.51  

 

a.

Represents sales of $341 million for Q1 2026 (Q4 2025: $327 million; Q1 2025: $191 million) applicable to our 45% equity method investment in Kibali and $105 million (Q4 2025: $91 million; Q1 2025: $61 million) applicable to our 24.5% equity method investment in Porgera for gold. Represents sales of $110 million for Q1 2026 (Q4 2025: $151 million; Q1 2025: $95 million) applicable to our 50% equity method investment in Zaldívar and $86 million (Q4 2025: $83 million; Q1 2025: $72 million), applicable to our 50% equity method investment in Jabal Sayid for copper.

b.

Sales applicable to equity method investments are net of treatment and refinement charges.

c.

On an attributable basis. Excludes Long Canyon which is producing residual ounces from the leach pad while in care and maintenance.

 

BARRICK FIRST QUARTER 2026   12    PRESS RELEASE


d.

Represents cumulative catch-up adjustment to revenue relating to our streaming arrangements. Refer to note 2e of the 2025 Annual Financial Statements for more information.

e.

Realized price per oz/lb may not calculate based on amounts presented in this table due to rounding.

Endnote 4

On an attributable basis. Copper COS/lb is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share).

Endnote 5

A Tier One Gold Asset is an asset with a $1,500/oz reserve with potential to deliver a minimum 10-year life, annual production of at least 500,000 ounces of gold and with projected costs per ounce in the lower half of the industry cost curve. A Tier One Copper Asset/Project is an asset with a $3.25/lb reserve with potential for +5Mt contained copper in support at least 20 years life, annual production of at least 200ktpa, with costs per pound in the lower half of the industry cost curve. Tier One Assets must be located in a world-class geological district with potential for organic reserve growth and long-term geologically driven addition.

Endnote 6 – 2026 Outlook Assumptions and Economic Sensitivity Analysis

 

    

2026 guidance

assumption

   Hypothetical change   

Consolidated impact

on EBITDA (millions)

   Attributable impact on EBITDA3 (millions)    Attributable impact on TCC3 and AISC3
 Gold price sensitivity    $4,500/oz    +/- $100/oz    +/-$390    +/-$270    +/-$5/oz
 Copper price sensitivity    $5.50/lb    +/-$0.25/lb    +/- $110    +/- $110    +/-$0.01/lb
 Oil prices   

$70/bbl WTI

$75/bbl Brent

   +/- $10/bbl    +/- $61    +/- $56    +/- $12/oz

 

      
   
Key Outlook Assumptions     2026  
   
Gold price ($/oz)    4,500 
   
Copper price ($/lb)    5.50 
   
Oil price (WTI) ($/barrel)    70 
   
Oil price (Brent) ($/barrel)    75 
   
AUD exchange rate (AUD:USD)    0.75 
   
ARS exchange rate (USD:ARS)    1,513 
   
CAD exchange rate (USD:CAD)    1.30 
   
CLP exchange rate (USD:CLP)    900 
   
EUR exchange rate (EUR:USD)    1.10 

 

BARRICK FIRST QUARTER 2026   13    PRESS RELEASE


Cautionary Statement on Forward-Looking Information

Certain information contained or incorporated by reference in this press release, including any information as to our strategy, projects, plans or future financial or operating performance, constitutes “forward-looking statements”. All statements, other than statements of historical fact, are forward-looking statements. The words “believe”, “expect”, “plan”, “committed”, “guidance”, “project”, “progress”, “continue”, “progress”, “develop”, “on track”, “target”, “ongoing”, “estimate”, “growth”, “potential”, “future”, “extend”, “will”, “could”, “would”, “should”, “may” and similar expressions identify forward-looking statements. In particular, this press release contains forward-looking statements including, without limitation, with respect to: Barrick’s forward-looking production guidance; estimates of future cost of sales per ounce for gold and per pound for copper, total cash costs per ounce and C1 cash costs per pound, and all-in sustaining costs per ounce/pound; projected capital, operating and exploration expenditures; our ability to convert resources into reserves and replace reserves net of depletion from production; mine life and production rates, including anticipated production growth from Barrick’s organic project pipeline; the potential for Fourmile to become a standalone Tier One Gold Asset; Barrick’s global exploration strategy and planned exploration activities; Barrick’s copper strategy; our plans, and expected timing, completion and benefits of our growth projects, including the progress of the Lumwana Super Pit Expansion project; Barrick’s decision to slow development activity at Reko Diq; potential mineralization and metal or mineral recoveries; Barrick’s performance dividend policy; Barrick’s intention to pursue and the expected timing for and potential benefits of an initial public offering (“IPO”) of Barrick’s North American gold assets; the structure and the ability of the IPO to generate significant value for Barrick and Newmont; and expectations regarding future price assumptions, financial performance and other outlook or guidance.

Forward-looking statements are necessarily based upon a number of estimates and assumptions including material estimates and assumptions related to the factors set forth below that, while considered reasonable by the Company as at the date of this press release in light of management’s experience and perception of current conditions and expected developments, are inherently subject to significant business, economic and competitive uncertainties and contingencies. Known and unknown factors could cause actual results to differ materially from those projected in the forward-looking statements and undue reliance should not be placed on such statements and information. Such factors include, but are not limited to: fluctuations in the spot and forward price of gold, copper or certain other commodities (such as silver, diesel fuel, natural gas and electricity); risks associated with projects in the early stages of evaluation and for which additional engineering and other analysis is required; risks related to the possibility that future exploration results will not be consistent with the Company’s expectations, that quantities or grades of reserves will be diminished, and that resources may not be converted to reserves; risks associated with the fact that certain of the initiatives described in this press release are still in the early stages and may not materialize; changes in mineral production performance, exploitation and exploration successes; risks that exploration data may be incomplete and considerable additional work may be required to complete further evaluation, including but not limited to drilling, engineering and socioeconomic studies and investment; the speculative nature of mineral exploration and development; lack of certainty with respect to foreign legal systems, corruption and other factors that are inconsistent with the rule of law; changes in national and local government legislation, taxation, controls or regulations and/or changes in the administration of laws, policies and practices, including the status of value added tax refunds received in Chile in connection with the Pascua-Lama Project; expropriation or nationalization of property and political or economic developments in Canada, the United States, or other countries in which Barrick does or may carry on business in the future; risks relating to the proposed initial public offering of an entity that will hold Barrick’s North American assets; risks relating to political instability in certain of the jurisdictions in which Barrick operates; timing of receipt of, or failure to comply with, necessary permits and approvals; non-renewal of key licenses by governmental authorities; failure to comply with environmental and health and safety laws and regulations; increased costs and physical and transition risks related to climate change, including extreme weather events, resource shortages, emerging policies and increased regulations related to greenhouse gas (“GHG”) emission levels, energy efficiency and reporting of risks; the Company’s ability to achieve its sustainability goals, including its climate-related goals and GHG emissions reduction targets, in particular its ability to achieve its Scope 3 emissions targets which require reliance on entities within Barrick’s value chain, but outside of the Company’s direct control, to achieve such targets within the specified timeframes; contests over title to properties, particularly title to undeveloped properties, or over access to water, power and other required infrastructure; the liability associated with risks and hazards in the mining industry, and the ability to maintain insurance to cover such losses; damage to the Company’s reputation due to the actual or perceived occurrence of any number of events, including negative publicity with respect to the Company’s handling of environmental matters or dealings with community groups, whether true or not; risks related to operations near communities that may regard Barrick’s operations as being detrimental to them; litigation and legal and administrative proceedings; operating or technical difficulties in connection with mining or development activities, including geotechnical challenges, tailings dam and storage facilities failures, and disruptions in the maintenance or provision of required infrastructure and information technology systems; increased costs, delays, suspensions and technical challenges associated with the construction of capital projects; risks associated with working with partners in jointly controlled assets; risks related to disruption of supply routes which may cause delays in construction and mining activities, including disruptions in the supply of key mining inputs due to the invasion of Ukraine by Russia and conflicts in the Middle East; risk of loss due to acts of war, terrorism, sabotage and civil disturbances; risks associated with artisanal and illegal mining; risks associated with Barrick’s infrastructure, information technology systems and the implementation of Barrick’s technological initiatives, including risks related cybersecurity incidents, including those caused by computer viruses, malware, ransomware and other cyberattacks, or similar information technology system failures, delays and/or disruptions; the impact of global liquidity and credit availability on the timing of cash flows and the values of assets and liabilities based on projected future cash flows; the impact of inflation, including global inflationary pressures driven by ongoing global supply chain disruptions, global energy cost increases following the

 

BARRICK FIRST QUARTER 2026   14    PRESS RELEASE


invasion of Ukraine by Russia and country-specific political and economic factors in Argentina and uncertainty related to Venezuela; adverse changes in our credit ratings; fluctuations in the currency markets; changes in U.S. dollar interest rates; changes in U.S. trade, tariff and other controls on imports and exports, tax, immigration or other policies that may impact relations with foreign countries, result in retaliatory policies, lead to increased costs for raw materials and components, or impact Barrick’s existing operations and material growth projects; risks arising from holding derivative instruments (such as credit risk, market liquidity risk and mark-to-market risk); risks related to the demands placed on the Company’s management, the ability of management to implement its business strategy and enhanced political risk in certain jurisdictions; uncertainty whether some or all of Barrick’s targeted investments and projects will meet the Company’s capital allocation objectives and internal hurdle rate; whether benefits expected from recent transactions are realized; business opportunities that may be presented to, or pursued by, the Company; our ability to successfully integrate acquisitions or complete divestitures; risks related to competition in the mining industry; employee relations including loss of key employees; availability and increased costs associated with mining inputs and labor; risks associated with diseases, epidemics and pandemics; risks related to the failure of internal controls; and risks related to the impairment of the Company’s goodwill and assets.

In addition, there are risks and hazards associated with the business of mineral exploration, development and mining, including environmental hazards, industrial accidents, unusual or unexpected formations, pressures, cave-ins, flooding and gold bullion, copper cathode or gold or copper concentrate losses (and the risk of inadequate insurance, or inability to obtain insurance, to cover these risks).

Many of these uncertainties and contingencies can affect our actual results and could cause actual results to differ materially from those expressed or implied in any forward-looking statements made by, or on behalf of, us. Readers are cautioned that forward-looking statements are not guarantees of future performance. All of the forward-looking statements made in this press release are qualified by these cautionary statements. Specific reference is made to the most recent Form 40-F/ Annual Information Form on file with the SEC and Canadian provincial securities regulatory authorities for a more detailed discussion of some of the factors underlying forward-looking statements and the risks that may affect Barrick’s ability to achieve the expectations set forth in the forward-looking statements contained in this press release. We disclaim any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by applicable law.

 

BARRICK FIRST QUARTER 2026   15    PRESS RELEASE

Exhibit 99.2

 

LOGO

Management’s Discussion and Analysis (“MD&A”) Quarterly Report on the First Quarter of 2026

 

This portion of the Quarterly Report provides management’s discussion and analysis (“MD&A”) of the financial condition and results of operations, to enable a reader to assess material changes in financial condition and results of operations as at, and for the three month period ended March 31, 2026, in comparison to the corresponding prior-year periods. The MD&A is intended to help the reader understand Barrick Mining Corporation (“Barrick”, “we”, “our”, the “Company” or the “Group”), our operations, financial performance as well as our present and future business environment. This MD&A, which has been prepared as of May 8, 2026, is intended to supplement and complement the condensed unaudited interim consolidated financial statements and notes thereto, prepared in accordance with IFRS Accounting Standards as issued by the International Accounting Standards Board applicable to the preparation of interim financial statements, under International Accounting Standard 34, Interim Financial Reporting, for the three month period ended March 31, 2026 (collectively, the “Financial Statements”), which are included in this Quarterly Report on pages 48 to 52. You are encouraged to review the Financial Statements in conjunction with your review of this MD&A. This MD&A should be read in conjunction with both the annual audited 

consolidated financial statements for the two years ended December 31, 2025, the related annual MD&A included in the 2025 Annual Report, and the most recent Form 40–F/Annual Information Form on file with the U.S. Securities and Exchange Commission (“SEC”) and Canadian provincial securities regulatory authorities. These documents and additional information relating to the Company are available on SEDAR+ at www.sedarplus.ca and EDGAR at www.sec.gov. Certain notes to the Financial Statements are specifically referred to in this MD&A and such notes are incorporated by reference herein. All dollar amounts in this MD&A are in millions of United States dollars (“$” or “US$”), unless otherwise specified.

For the purposes of preparing our MD&A, we consider the materiality of information. Information is considered material if: (i) such information results in, or would reasonably be expected to result in, a significant change in the market price or value of our shares; (ii) there is a substantial likelihood that a reasonable investor would consider it important in making an investment decision; or (iii) it would significantly alter the total mix of information available to investors. We evaluate materiality with reference to all relevant circumstances, including potential market sensitivity.

 

 

Abbreviations

 

 
  
   
AISC    All-in Sustaining Costs
   
BNL    Barrick Niugini Limited
   
CCV    Critical Control Verifications
   
CEO    Chief Executive Officer
   
COS    Cost of Sales
   
DRC    Democratic Republic of Congo
   
G&A    General and administrative
   
GHG    Greenhouse Gas
   
GoT    Government of Tanzania
   
IASB    International Accounting Standards Board
   
ICMM    International Council on Mining and Metals
   
ICSID    International Centre for the Settlement of Investment Disputes
   
IFRS    IFRS Accounting Standards as issued by the International Accounting Standards Board
   
Ktpa    Thousand tonnes per annum
   
Lb    Pound
   
LME    London Metal Exchange
   
LTI    Lost Time Injury 
  
   
LTIFR    Lost Time Injury Frequency Rate
   
Mtpa    Million tonnes per annum
   
MW    Megawatt
   
NGM    Nevada Gold Mines
   
OECD    Organisation for Economic Co-operation and Development
   
Oz    Ounce
   
PJL    Porgera Jersey Limited
   
PNG    Papua New Guinea
   
Randgold    Randgold Resources Limited
   
SOKIMO    Société Minière de Kilo-Moto
   
TCC    Total Cash Costs
   
TRIFR    Total Recordable Injury Frequency Rate
   
TSF    Tailings Storage Facilities
   
TWMS    Temporary Water Management Structures
   
VAT    Value-Added Tax
   
WGC    World Gold Council
   
WTI    West Texas Intermediate
   
YTD    Year to date March 31
 

 

 

 

BARRICK FIRST QUARTER 2026   1    MANAGEMENT’S DISCUSSION AND ANALYSIS


Cautionary Statement on Forward-Looking Information

 

 

 

Certain information contained or incorporated by reference in this MD&A, including any information as to our strategy, projects, plans or future financial or operating performance, constitutes “forward-looking statements”. All statements, other than statements of historical fact, are forward-looking statements. The words “believe”, “expect”, “anticipated”, “aim”, “strategy”, “ramp up”, “target”, “plan”, “opportunities”, “guidance”, “forecast”, “outlook”, “project”, “intend”, “develop”, “progress”, “continue”, “temporary”, “estimate”, “potential”, “future”, “focus”, “ongoing”, “following”, “subject to”, “scheduled”, “may”, “will”, “can”, “could”, “would”, “should” and similar expressions identify forward-looking statements. In particular, this MD&A contains forward-looking statements including, without limitation, with respect to: Barrick’s forward-looking production and cost guidance, including our ability to meet our 2026 guidance; anticipated production growth from Barrick’s organic project pipeline and reserve replacement; estimates of future cost of sales per ounce for gold and per pound for copper, total cash costs per ounce and C1 cash costs per pound, and all-in sustaining costs per ounce/ pound; cash flow forecasts; projected capital, operating and exploration expenditures; the share buyback program and performance dividend policy; mine life and production rates; anticipated timing for development of the Goldrush Project; our plans, timelines, and expected completion and benefits of our growth projects, including the Goldrush Project, Fourmile, Ren, Pueblo Viejo plant expansion and mine life extension project, Veladero Phase 8 Leach Pad, Reko Diq, solar power project at Kibali, and the Lumwana Super Pit Expansion; anticipated production at Goldrush, Ren, Reko Diq and Lumwana; timing for first production from the Lumwana Super Pit Expansion; Barrick’s decision to slow development activity at Reko Diq capital expenditures related to upgrades and ongoing management initiatives; Barrick’s global exploration strategy and planned exploration activities; Barrick’s copper strategy; the resumption of operations at Loulo-Gounkoto following the resolution of disputes with the Government of Mali, including adoption of the 2023 Mining Code; our pipeline of high confidence projects at or near existing operations; our ability to identify new Tier One assets and the potential for existing assets to attain Tier One status, including Fourmile; the incorporation of Fourmile into the NGM joint venture at fair market value; potential mineralization and metal or mineral recoveries; Barrick’s intention to pursue and the expected timing for and potential benefits of an initial public offering (“IPO”) of Barrick’s North American gold assets; the structure and the ability of the IPO to generate significant value for Barrick and Newmont; our ability to convert resources into reserves and future reserve replacement; asset sales, joint ventures and partnerships; Barrick’s strategy, plans, targets and goals in respect of sustainability issues, including climate change, greenhouse gas (“GHG”) emissions reduction targets, human rights, safety performance, community development and resettlement, and responsible water use; and expectations regarding future price assumptions, financial performance and other outlook or guidance.

Forward-looking statements are necessarily based upon a number of estimates and assumptions including material estimates and assumptions related to the factors set forth below that, while considered reasonable by the

Company as at the date of this MD&A in light of management’s experience and perception of current conditions and expected developments, are inherently subject to significant business, economic and competitive uncertainties and contingencies. Known and unknown factors could cause actual results to differ materially from those projected in the forward-looking statements and undue reliance should not be placed on such statements and information. Such factors include, but are not limited to: fluctuations in the spot and forward price of gold, copper or certain other commodities (such as silver, diesel fuel, natural gas and electricity); risks associated with projects in the early stages of evaluation and for which additional engineering and other analysis is required; risks related to the possibility that future exploration results will not be consistent with the Company’s expectations, that quantities or grades of reserves will be diminished, and that resources may not be converted to reserves; risks associated with the fact that certain of the initiatives described in this MD&A are still in the early stages and may not materialize; changes in mineral production performance, exploitation and exploration successes; risks that exploration data may be incomplete and considerable additional work may be required to complete further evaluation, including but not limited to drilling, engineering and socioeconomic studies and investment; the speculative nature of mineral exploration and development; lack of certainty with respect to foreign legal systems, corruption and other factors that are inconsistent with the rule of law; changes in national and local government legislation, taxation, controls or regulations and/or changes in the administration of laws, policies and practices, including the expropriation or nationalization of property and political or economic developments in Canada, the United States, or other countries in which Barrick does or may carry on business in the future; risks relating to the proposed initial public offering of an entity that will hold Barrick’s North American assets; risks relating to political instability in certain of the jurisdictions in which Barrick operates; timing of receipt of, or failure to comply with, necessary permits and approvals; non-renewal of key licenses by governmental authorities; failure to comply with environmental and health and safety laws and regulations; increased costs and physical and transition risks related to climate change, including extreme weather events, resource shortages, emerging policies and increased regulations related to GHG emission levels, energy efficiency and reporting of risks; the Company’s ability to achieve its sustainability goals, including its climate-related goals and GHG emissions reduction targets, in particular its ability to achieve its Scope 3 emissions targets which require reliance on entities within Barrick’s value chain, but outside of the Company’s direct control, to achieve such targets within the specified time frames; contests over title to properties, particularly title to undeveloped properties, or over access to water, power and other required infrastructure; the liability associated with risks and hazards in the mining industry, and the ability to maintain insurance to cover such losses; damage to the Company’s reputation due to the actual or perceived occurrence of any number of events, including negative publicity with respect to the Company’s handling of environmental matters or dealings with community groups, whether true or not; risks related to operations near

 

 

 

 

BARRICK FIRST QUARTER 2026   2    MANAGEMENT’S DISCUSSION AND ANALYSIS


communities that may regard Barrick’s operations as being detrimental to them; litigation and legal and administrative proceedings; operating or technical difficulties in connection with mining or development activities, including geotechnical challenges, tailings dam and storage facilities failures, and disruptions in the maintenance or provision of required infrastructure and information technology systems; increased costs, delays, suspensions and technical challenges associated with the construction of capital projects; risks associated with working with partners in jointly controlled assets; risks related to disruption of supply routes which may cause delays in construction and mining activities, including disruptions in the supply of key mining inputs due to the invasion of Ukraine by Russia and conflicts in the Middle East; risk of loss due to acts of war, terrorism, sabotage and civil disturbances; risks associated with artisanal and illegal mining; risks associated with Barrick’s infrastructure, information technology systems and the implementation of Barrick’s technological initiatives, including risks related to cybersecurity incidents, including those caused by computer viruses, malware, ransomware and other cyberattacks, or similar information technology system failures, delays and/or disruptions; the impact of global liquidity and credit availability on the timing of cash flows and the values of assets and liabilities based on projected future cash flows; the impact of inflation, including global inflationary pressures driven by ongoing global supply chain disruptions, global energy cost increases following the invasion of Ukraine by Russia and country-specific political and economic factors in Argentina and uncertainty related to Venezuela; adverse changes in our credit ratings; fluctuations in the currency markets; changes in U.S. dollar interest rates; changes in U.S. trade, tariff and other controls on imports and exports, tax, immigration or other policies that may impact relations with foreign countries, result in retaliatory policies, lead to increased costs for raw materials and components, or impact Barrick’s existing operations and material growth projects; risks arising from holding derivative instruments (such as credit risk, market liquidity risk and mark-to-market risk); risks related to the demands placed on the Company’s

management, the ability of management to implement its business strategy and enhanced political risk in certain jurisdictions; uncertainty whether some or all of Barrick’s targeted investments and projects will meet the Company’s capital allocation objectives and internal hurdle rate; whether benefits expected from recent transactions are realized; business opportunities that may be presented to, or pursued by, the Company; our ability to successfully integrate acquisitions or complete divestitures; risks related to competition in the mining industry; employee relations including loss of key employees; availability and increased costs associated with mining inputs and labor; risks associated with diseases, epidemics and pandemics; risks related to the failure of internal controls; and risks related to the impairment of the Company’s goodwill and assets. In addition, there are risks and hazards associated with the business of mineral exploration, development and mining, including environmental hazards, industrial accidents, unusual or unexpected formations, pressures, cave-ins, flooding and gold bullion, copper cathode or gold or copper concentrate losses (and the risk of inadequate insurance, or inability to obtain insurance, to cover these risks).

Many of these uncertainties and contingencies can affect our actual results and could cause actual results to differ materially from those expressed or implied in any forward-looking statements made by, or on behalf of, us. Readers are cautioned that forward-looking statements are not guarantees of future performance. All of the forward-looking statements made in this MD&A are qualified by these cautionary statements. Specific reference is made to the most recent Form 40-F/Annual Information Form on file with the SEC and Canadian provincial securities regulatory authorities for a more detailed discussion of some of the factors underlying forward-looking statements and the risks that may affect Barrick’s ability to achieve the expectations set forth in the forward-looking statements contained in this MD&A. We disclaim any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by applicable law.

 

 

 

 

BARRICK FIRST QUARTER 2026   3    MANAGEMENT’S DISCUSSION AND ANALYSIS


Use of Non-GAAP Financial Measures

 

 

We use the following non-GAAP financial measures and ratios in our MD&A:

 

   

“adjusted net earnings”

 

   

“free cash flow”

 

   

“attributable free cash flow”

 

   

“attributable operating cash flow”

 

   

“EBITDA”

 

   

“adjusted EBITDA”

 

   

“attributable EBITDA”

 

   

“attributable EBITDA margin”

 

   

“net leverage”

 

   

“minesite sustaining capital expenditures”

 

   

“project capital expenditures”

 

   

“TCC/oz”

 

   

“C1 cash costs/lb”

 

   

“AISC per oz/lb” and

 

   

“realized price per oz/lb”

For a detailed description of each of the non-GAAP financial measures used in this MD&A and a detailed reconciliation to the most directly comparable measure under IFRS, please refer to the Non-GAAP Financial Measures section of this MD&A on pages 36 to 45. Each non-GAAP financial measure has been annotated with a reference to an endnote on page 46. The non-GAAP financial measures set out in this MD&A are intended to provide additional information to investors and do not have any standardized meaning under IFRS, and therefore may not be comparable to other issuers, and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS.

Changes in Presentation of Non-GAAP Financial Performance Measures

Attributable Operating Cash Flow

Starting with this MD&A, we are presenting attributable operating cash flow. Attributable operating cash flow starts with cash provided by operating activities and adds our attributable share of cash provided by operating activities from our equity investees and subtracts the cash provided by operating activities attributable to the non-controlling interests. Management believes this to be useful indicator of the amount of cash provided by operating activities to Barrick’s ownership share.

Index

 

 

   

5

  Overview
   
    5      Financial and Operating Highlights
   
    7      Key Business Developments
   
    8      Sustainability
   
    9      Outlook
   

11

  Operating Performance
   
    11      Nevada Gold Mines
   
    12       Carlin
   
    14       Cortez
   
    16       Turquoise Ridge
   
    17      Pueblo Viejo
   
    18      Loulo-Gounkoto
   
    19      Kibali
   
    20      North Mara
   
    21      Bulyanhulu
   
    22      Other Mines - Gold
   
    23      Lumwana
   
    24      Other Mines - Copper
   

25

  Future Growth
   

28

  Review of Financial Results
   
    28      Revenue
   
    29      Production Costs
   
    30      General and Administrative Expenses
   
    30      Exploration, Evaluation and Project Expenses
   
    30      Finance Costs, Net
   
    31      Additional Statement of Income Items
   
    31      Income Tax Expense
   

32

  Financial Condition Review
   
    32      Balance Sheet Review
   
    32      Financial Position and Liquidity
   
    33      Summary of Cash Inflow (Outflow)
   

34

  Commitments and Contingencies
   

35

  Review of Quarterly Results
   

35

  Internal Control over Financial Reporting and Disclosure Controls and Procedures
   

36

  IFRS Critical Accounting Policies and Accounting Estimates
   

36

  Non-GAAP Financial Measures
   

46

  Technical Information
   

46

  Endnotes
   

49

  Financial Statements
   

54

 

 

Notes to Consolidated Financial Statements

 

 

 

 

 

BARRICK FIRST QUARTER 2026   4    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Overview

 

 

Financial and Operating Highlights

 

     For the three months ended  
           
        3/31/26       12/31/25       % Change         3/31/25       % Change  

Financial Results ($ millions)

              

Revenues

     5,218        5,997        (13)%        3,130        67 %  

Cost of sales

     2,099        2,712        (23)%        1,785        18 %  

Net earningsa

     1,602        2,406        (33)%        474        238 %  

Adjusted net earningsb

     1,648        1,754        (6)%        603        173 %  

Attributable EBITDAb

     2,760        3,084        (11)%        1,361        103 %  

Attributable EBITDA marginb

     66 %        64 %        3 %        51 %        29 %  

Minesite sustaining capital expendituresb,c

     380        458        (17)%        564        (33)%  

Project capital expendituresb,c

     570        630        (10)%        269        112 %  

Total consolidated capital expendituresc,d

     979        1,107        (12)%        837        17 %  

Total attributable capital expenditurese

     755        906        (17)%        631        20 %  

Net cash provided by operating activities

     2,554        2,726        (6)%        1,212        111 %  

Net cash provided by operating activities marginf

     49 %        45 %        9 %        39 %        26 %  

Attributable operating cash flowb

     1,968        1,966        0 %        1,042        89 %  

Free cash flowb

     1,575        1,619        (3)%        375        320 %  

Attributable free cash flowb

     1,213        1,060        14 %        411        195 %  

Net earnings per share (basic and diluted)

     0.96        1.43        (33)%        0.27        256 %  

Adjusted net earnings (basic)b per share

     0.98        1.04        (6)%        0.35        180 %  

Weighted average diluted common shares (millions of shares)

     1,675        1,684        (1)%        1,725        (3)%  

Operating Results

              

Gold productiong(thousands of ounces)

     719        871        (17)%        758        (5)%  

Gold soldg (thousands of ounces)

     748        960        (22)%        751        0 %  

Market gold price ($/oz)

     4,873        4,135        18 %        2,860        70 %  

Realized gold priceb,g ($/oz)

     4,823        4,177        15 %        2,898        66 %  

Gold COSg,h ($/oz)

     1,922        1,904        1 %        1,629        18 %  

Gold TCCb,g ($/oz)

     1,327        1,205        10 %        1,220        9 %  

Gold AISCb,g ($/oz)

     1,708        1,581        8 %        1,775        (4)%  

Copper production (thousands of tonnes)g

     49        62        (21)%        44        11 %  

Copper sold (thousands of tonnes)g

     45        67        (33)%        51        (12)%  

Market copper price ($/lb)

     5.83        5.03        16 %        4.24        38 %  

Realized copper priceb,g ($/lb)

     5.79        5.42        7 %        4.51        28 %  

Copper COS (Barrick’s share)g,i ($/lb)

     3.41        3.37        1 %        2.92        17 %  

Copper C1 cash costsb,g ($/lb)

     2.57        2.45        5 %        2.25        14 %  

Copper AISCb,g ($/lb)

     3.67        3.61        2 %        3.06        20 %  
           
      As at
3/31/26
     As at
12/31/25
     % Change      As at 3/31/25      % Change  

Financial Position ($ millions)

              

Debt (current and long-term)

     4,726        4,703        0 %        4,727        0 %  

Cash and equivalents

     7,131        6,706        6 %        4,104        74 %  

Debt, net of cash

     (2,405)        (2,003)        20 %        623        (486)%  

 

a. 

Net earnings represents net earnings attributable to the equity holders of the Company.

b.

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

c. 

Amounts presented on a consolidated cash basis. Project capital expenditures are not included in our calculation of AISC.

d. 

Total consolidated capital expenditures also includes capitalized interest of $29 million for Q1 2026 (Q4 2025: $19 million; Q1 2025: $4 million).

e. 

These amounts are presented on the same basis as our guidance.

f. 

Represents net cash provided by operating activities divided by revenue.

g. 

On an attributable basis.

h. 

Gold COS/oz is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share).

i. 

Copper COS/lb is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share).

 

 

 

BARRICK FIRST QUARTER 2026   5    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

LOGO

 

a. 

On an attributable basis.

b. 

Gold COS/oz is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share). Copper COS/lb is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share). Refer to endnote 2 for further details.

c. 

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

d. 

Capital expenditures also includes capitalized interest.

e. 

Dividends declared are inclusive of performance dividends paid in 2025.

 

 

 

BARRICK FIRST QUARTER 2026   6    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Factors affecting net earnings and adjusted net earnings1 - Q1 2026 versus Q4 2025

Net earnings and adjusted net earnings1 attributable to equity holders of Barrick (“net earnings”) for Q1 2026 were $1,602 million and $1,648 million, respectively, compared to $2,406 million and $1,754 million, respectively in Q4 2025. The primary driver of the decrease were lower gold and copper sales volumes, partially offset by higher realized gold and copper prices1.

After adjusting for items that are not indicative of future operating earnings, adjusted net earnings1 of $1,648 million for Q1 2026 was $106 million lower than Q4 2025. Q1 2026 realized gold prices1 were 15% higher when compared to Q4 2025. The decrease in gold sales volumes was mainly as a result of lower grades mined and processed at Nevada Gold Mines and Pueblo Viejo combined with lower grades mined at North Mara and Kibali. These were partially offset by higher production at Loulo-Gounkoto as a result of ramping up of operations during Q1 2026 following resolution of the dispute with the Government of Mali late in Q4 2025. Lower copper sales was a result of lower grades and a planned shutdown at Lumwana.

Factors affecting net earnings and adjusted net earnings1 - Q1 2026 versus Q1 2025

Net earnings and adjusted net earnings1 for Q1 2026 were $1,602 million and $1,648 million, respectively, compared to $474 million and $603 million, respectively in Q1 2025. The primary drivers of the increase were higher realized gold prices1, partially offset by higher gold COS/oz2. Q1 2026 realized gold prices1 were 66% higher when compared to Q1 2025. The increase in gold COS/oz2 was mainly due to the impact of higher royalties, mining and production taxes (impact approximately $90/oz) associated with the higher realized gold price1. In addition, COS/oz2 was higher due to the inclusion of Loulo-Gounkoto sales at higher costs (as a result of the fair value increment on inventory resulting from the purchase price allocation when we regained control of Loulo-Gounkoto in Q4 2025) whereas in Q1 2025 there were no sales from Loulo-Gounkoto as shipments were restricted.

Factors affecting Operating Cash Flow and Free Cash Flow1 - Q1 2026 versus Q4 2025

In Q1 2026, we generated $2,554 million in operating cash flow, compared to $2,726 million in Q4 2025. The decrease of $172 million was primarily due to lower gold sales this quarter combined with higher gold TCC/oz1 partially offset by a higher realized gold price1. Operating cash flow was further impacted by an unfavorable movement in working capital, primarily in accounts payable which decreased as a result of the payment of supplier balances at Loulo-Gounkoto as operations ramped up in Q1 2026. These results were positively impacted by a decrease in cash taxes paid and lower interest paid as a result of the timing of semi-annual interest payments on our bonds, which primarily occur in the second and fourth quarters.

In Q1 2026, we recorded free cash flow1 of $1,575 million, compared to $1,619 million in Q4 2025, mainly reflecting lower operating cash flows as explained above, partially offset by lower capital expenditures than Q4 2025. In Q1 2026, capital expenditures on a cash basis

were $979 million compared to $1,107 million in Q4 2025, as discussed on page 33.

Factors affecting Operating Cash Flow and Free Cash Flow1 - Q1 2026 versus Q1 2025

In Q1 2026, we generated $2,554 million in operating cash flow, compared to $1,212 million in Q1 2025. The increase of $1,342 million was primarily due to higher realized gold prices1, partially offset by higher gold TCC/oz1. Operating cash flow was further impacted by an unfavorable movement in working capital, mainly in accounts payable which decreased as a result of the payment of supplier balances at Loulo-Gounkoto as operations ramped up in Q1 2026, as well as higher cash taxes paid this quarter.

In Q1 2026, we generated free cash flow1 of $1,575 million compared to $375 million in Q1 2025. The increase primarily reflects higher operating cash flows as explained above, partially offset by higher capital expenditures. In Q1 2026, capital expenditures on a cash basis were $979 million compared to $837 million in Q1 2025, as discussed on page 33.

Key Business Developments

North American Barrick IPO

In April 2026, Barrick announced several executive appointments, dedicated exclusively to our North American gold assets. These assets are comprised of four Tier One gold assets5 located in premier mining jurisdictions in North America: Carlin, Cortez, and Turquoise Ridge in the NGM complex, and the Pueblo Viejo mine in the Dominican Republic. North American Barrick will also include Barrick’s wholly-owned Fourmile gold project, located adjacent to NGM. Barrick believes Fourmile is one of the most significant gold discoveries of this century and will be a significant high-grade and low-cost growth opportunity in North American Barrick’s portfolio.

Barrick has identified what it believes to be the optimal structure for the IPO of its North American assets. North American Barrick is expected to have its primary listing in New York, with a secondary listing in Toronto, subject to customary SEC registration and Canadian prospectus qualification processes. Barrick is on track to complete the IPO by the end of 2026, subject to market and other conditions and necessary approvals.

New Share Buyback Program

At the May 8, 2026 meeting, the Board of Directors authorized a new share buyback program for the purchase of up to $3 billion of Barrick’s outstanding common shares over the next 12 months.

The actual number of common shares that may be purchased, and the timing of any such purchases, will be determined by Barrick based on a number of factors, including the Company’s financial performance, the availability of cash flows, and the consideration of other uses of cash, including capital investment opportunities, returns to shareholders, and debt reduction.

The repurchase program does not obligate the Company to acquire any particular number of common shares, and the repurchase program may be suspended or discontinued at any time at the Company’s discretion.

 
 

 Numerical annotations throughout the text of this document refer to the endnotes found starting on page 46.

 

 

 

BARRICK FIRST QUARTER 2026   7    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Executive Leadership Changes

On February 4, 2026, Mark Hill was appointed as President and Chief Executive Officer, following his appointment as Group Chief Operating Officer and Interim President and Chief Executive Officer on September 29, 2025.

Mr. Hill, who was previously responsible for Barrick’s LATAM and Asia Pacific region, is a seasoned mining executive with 30 years of experience. He joined Barrick in 2006 and has experience in strategy, corporate development and leading major projects across the world, and was also integral in the initial decision to undertake exploration at the Fourmile gold project in Nevada.

On March 1, 2026, Helen Cai was appointed as Senior Executive Vice President and Chief Financial Officer, following the departure of Graham Shuttleworth.

Ms. Cai has served on the Barrick Board of Directors since November 2021 and brings more than two decades of experience in equity research, corporate finance, strategic planning, capital markets, and M&A across the mining, industrial, and technology sectors, primarily with Goldman Sachs and China International Capital Corporation.

On February 24, 2026, we announced the appointments of James J. McGuire as Chief Legal and Policy Officer and Woo Lee as Chief Global Affairs Officer. Both will report to Barrick’s President and Chief Executive Officer, Mark Hill, and are now members of the Executive Committee.

Mr. McGuire brings over 30 years of legal (civil and criminal) experience representing leading corporations, financial institutions, and individuals on a wide range of complex legal and policy matters. As Chief Legal and Policy Officer, Mr. McGuire will oversee Barrick’s legal, compliance, regulatory, and public policy functions. Poupak Bahamin has become Barrick’s General Counsel and Chief Compliance Officer and will remain a member of Barrick’s Executive Committee.

Mr. Lee has worked at Barrick for over 11 years, most recently as Senior Vice President and Head of Government & Corporate Affairs, Asia Pacific, where he worked with government officials, business and community leaders to advance the Company’s strategic objectives. As Chief Global Affairs Officer, Mr. Lee will lead Barrick’s global government affairs strategy in all markets as well as manage government and sovereign relationships.

Board of Directors Changes

At the February 4, 2026 meeting, Robert Samek was appointed to the Board of Directors and has joined the Audit & Risk and Compensation Committees. In addition, Mark Hill, President and Chief Executive Officer, has joined the Company’s Board of Directors as a Non-Independent Director.

Reko Diq

Following the preliminary findings of the review initiated in February 2026 and the further escalation of security issues in the region, on April 2, 2026 the Company announced that it considers it necessary to slow development activity and extend the project review. The continued review will allow the Company to assess in a comprehensive manner the evolving security situation, capital requirements, project financing, project scope and timeline.

Sustainability

Sustainability, including our license to operate, is entrenched in our DNA: our sustainability strategy is our business plan. Please refer to page 17 of our 2025 Annual Report for a full description of governance, strategy, risk management and targets. Key updates for 2026 are summarized below:

Safety remains our priority. During Q1, injury severity continued to decline, with only two LTIs recorded over the past three months. Notably, AME, South America & Asia Pacific, and Reko Diq remained LTI-free during the period, and there were no fatalities across the group. The LTIFR3 improved quarter on quarter, reflecting positive progress in managing higher-severity outcomes. While the TRIFR3 increased from 0.79 to 0.92, the prevention of fatalities and serious harm requires sustained focus on critical risks and the effectiveness of critical controls, rather than minor injury counts alone.

As an organization, we are continuing to shift toward the use of leading indicators to better understand and manage fatal risk exposure. These indicators focus on whether:

 

  i.

Critical controls are in place and effective

  ii.

Controls are routinely verified in the field

  iii.

People feel safe to report near misses and control failures

  iv.

Actions arising from incident learnings are implemented and delivering the intended risk reduction

Leadership engagement in the field remains strong, with managers and superintendents actively completing quality CCVs. During Q1, approximately 11,000 CCVs were completed, with 24% identifying at-risk conditions. Importantly, 77% of these at-risk conditions were resolved in the field, demonstrating effective intervention at the point of risk and reinforcing the desired focus on eliminating hazards before they lead to serious incidents.

On April 2, 2026, Barrick published its standalone Human Rights Report, an update from the last publication in 2021. The Human Rights Report outlines the company’s policies, standards and procedures implemented to identify and manage potential human rights risks, along with generalized summaries of the independent human rights assessments that are undertaken as part of Barrick’s human rights program.

During Q1 2026, the Group’s total Scope 1 and 2 (location-based) GHG emissions were 1,721 kt CO2-e. Absolute emissions are trending 9% lower than 2025 due to the divestments of Hemlo and Tongon, and lower emissions from the Goldstrike Roaster and TS Power Plant, partially offset by the restart of Loulo-Gounkoto.

 

     For the three months ended  
      3/31/2026a      12/31/2025a      3/31/25  
LTIFR3      0.05        0.08        0.10  
TRIFR3      0.92        0.79        0.71  
Community Development Spend ($ millions)      13        15        15  
Class 14 Environmental Incidents      0        0        0  
GHG Scope 1 and 2 emissions (kt CO2-e) (location based)      1,721        1,928        1,874  
Water Recycling and Reuse Rate      81 %        82 %        82 %  

 

  a. 

Data presented is provisional data and is subject to change as a result of external assurance during annual reporting.

 

 

 

 

BARRICK FIRST QUARTER 2026   8    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Full Year 2026 Outlook

We continue to expect our 2026 gold production to be in the range of 2.90 to 3.25 million ounces. In addition to the higher contribution from Loulo-Gounkoto versus 2025, we also expect Pueblo Viejo to deliver a slightly higher year-over-year performance with offsetting decreases at Veladero and North Mara. At Carlin, we expect 2026 production to be slightly lower than 2025 driven by open pit mine sequencing although this is expected to be partially offset by higher deliveries of Cortez material processed through the Carlin roasters. At Turquoise Ridge, we expect lower underground grades as per the planned mining sequence. Relative to 2025, we continue to expect stable delivery for the other assets.

With production slightly ahead of plan in Q1, gold production in Q2 is now expected to be 730 - 770koz and to further increase in Q3 and Q4. This is driven by the ramp-up of Loulo-Gounkoto, the timing of shutdowns, the Goldrush ramp-up and mine sequencing across the NGM sites. We also expect production at Kibali to be higher in H2 2026.

Our 2026 gold cost guidance remains unchanged noting the ranges in the table to the right are based on a gold price assumption of $4,500/oz. We have previously disclosed that our cost sensitivity is $5/oz for every $100/oz change in the gold price.

We continue to expect 2026 copper production to be in the range of 190 to 220 thousand tonnes. Production is expected to step up over the remaining three quarters with Q1 being the lowest quarter of the year mainly driven by grade at Lumwana as per the mine plan. We are also on track to achieve our copper cost guidance metrics for 2026, which are based on a LME copper price assumption of $5.50/lb. We have previously disclosed that our cost sensitivity is $0.01/lb per $0.25/lb change in the copper price.

In terms of the sensitivity of our costs to the oil price assumptions, we have calculated that for every $10/barrel change in these oil prices, the direct impact on our costs associated with our diesel consumption is $12/oz across our gold operations and $0.04/lb across our copper sites.

We previously disclosed guidance for 2026 total attributable capital expenditure of $4.0 to $4.45 billion which was inclusive of $600-700 million for the Reko Diq project. The timing and quantum of capital expenditures for the Reko Diq project (including 2026) remains under review as part of the overall project review (refer to Key Business Developments).

Further detail on our 2026 company guidance is provided below and on the next page, inclusive of the key assumptions that were used as the basis for this guidance as released on February 5, 2026 and as qualified by the comments above.

Company Guidance

     2026  

($ millions, except per oz/lb data)

     Estimate  

  Gold production (millions of ounces)

     2.90 - 3.25  

  Gold cost metrics

  

COS - gold ($/oz)

     1,870 - 2,070  

TCC ($/oz)a

     1,330 - 1,470  

Depreciation ($/oz)

     470 - 520  

AISC ($/oz)a

     1,760 - 1,950  

Attributable minesite sustaininga

     1,100 - 1,250  

Attributable projecta

     900 - 1,000  

Total attributable capital expenditures

     2,000 - 2,250  

  Copper production (thousands of tonnes)

     190 - 220  

  Copper cost metrics

  

COS - copper ($/lb)

     3.05 - 3.35  

C1 cash costs ($/lb)a

     2.20 - 2.45  

Depreciation ($/lb)

     0.90 - 1.00  

AISC ($/lb)a

     3.45 - 3.75  

Attributable minesite sustaininga

     400 - 450  

Attributable projecta

     1,600 - 1,750  

Total attributable capital expenditures

     2,000 - 2,200  

  Exploration and project expenses

     450 - 500  

Exploration and evaluation

     320 - 350  

Project expenses

     130 - 150  

  General and administrative expenses

     ~180  

Corporate administration

     ~120  

Share-based compensationb

     ~60  

  Other expense

     70 - 90  

  Finance costs, net

     230 - 250  

 Effective income tax ratec

     24% - 28%  

  Key assumptions (used for guidance)

  

  Gold Price ($/oz)

     4,500  

  Copper Price ($/lb)

     5.50  

  Oil Price (WTI) ($/barrel)

     70  

  Oil Price (Brent) ($/barrel)

     75  

  AUD Exchange Rate (AUD:USD)

     0.75  

  ARS Exchange Rate (USD:ARS)

     1,513  

  CAD Exchange Rate (USD:CAD)

     1.30  

  CLP Exchange Rate (USD:CLP)

     900  

  EUR Exchange Rate (EUR:USD)

     1.10  

 

  a.

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

  b.

Based on a share price of US$45.76.

  c.

Based on key assumptions included in this table.

 

 

 

 

BARRICK FIRST QUARTER 2026   9    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Operating Division Guidance

Our 2026 forecast gold and copper production, COSa, TCCb, AISCb, and C1 cash costsb ranges by operating division were originally released on February 5, 2026 as follows:

 

 Operating Division    2026 forecast attributable
production (koz)
     2026 forecast COSa
($/oz)
     2026 forecast TCCb
($/oz)
    

2026 forecast AISCb  

($/oz)

 
 Gold            

Carlin (61.5%)

     600 - 670        1,770 - 1,960        1,340 - 1,490        1,900 - 2,100  

Cortez (61.5%)c

     430 - 480        1,980 - 2,190        1,390 - 1,540        1,690 - 1,870  

Turquoise Ridge (61.5%)

     300 - 330        1,610 - 1,790        1,220 - 1,360        1,490 - 1,650  

Phoenix (61.5%)

     80 - 100        2,440 - 2,710        900 - 1,000        1,180 - 1,310  

Nevada Gold Mines (61.5%)

     1,420 - 1,580        1,850 - 2,050        1,300 - 1,440        1,720 - 1,900  

Pueblo Viejo (60%)

     350 - 400        1,720 - 1,910        1,160 - 1,290        1,590 - 1,760  
 North America      1,770 - 1,980        1,820 - 2,010        1,270 - 1,410        1,690 - 1,870  
                 

Veladero (50%)

     180 - 200        2,000 - 2,210        1,160 - 1,280        1,460 - 1,620  

Porgera (24.5%)

     80 - 100        1,610 - 1,790        1,190 - 1,320        1,610 - 1,780  
 South America & Asia Pacific      260 - 300        1,870 - 2,070        1,170 - 1,300        1,500 - 1,660  
               

Loulo-Gounkoto (80%)d

     260 - 290        2,860 - 3,140        2,180 - 2,390        2,640 - 2,900  

Kibali (45%)

     270 - 310        1,520 - 1,680        1,130 - 1,250        1,330 - 1,470  

North Mara (84%)

     200 - 230        1,700 - 1,880        1,300 - 1,430        1,520 - 1,680  

Bulyanhulu (84%)

     140 - 160        1,750 - 1,940        1,230 - 1,360        1,870 - 2,070  
 Africa and Middle East      870 - 970        1,990 - 2,200        1,490 - 1,640        1,840 - 2,040  
         
 Total Attributable to Barricke,f,g      2,900 - 3,250        1,870 - 2,070        1,330 - 1,470        1,760 - 1,950  
               
      
2026 forecast attributable
production (kt)
 
 
    
2026 forecast COSa
($/lb)
 
 
    
2026 forecast C1 cash
costsb ($/lb)
 
 
    

2026 forecast AISCb  

($/lb)

 

 

Copper            

Lumwana

     130 - 150        2.85 - 3.15        2.05 - 2.30        3.40 - 3.75  

Zaldívar (50%)

     30 - 35        4.80 -5.10        3.70 - 3.90        5.40 - 5.70  

Jabal Sayid (50%)

     25 - 30        2.10 - 2.30        1.25 - 1.45        1.45 - 1.65  
 Total Copperg      190 - 220        3.05 - 3.35        2.20 - 2.45        3.45 - 3.75  

 

  a.

Gold COS/oz is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share). Copper COS/lb is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share).

  b.

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

  c.

Includes Goldrush.

  d.

2026 forecast cost of sales does not include the impact of the Loulo-Gounkoto purchase price allocation. Refer to note 4 to the Financial Statements for further information.

  e.

TCC/oz and AISC/oz include costs allocated to non-operating sites.

  f.

Operating division guidance ranges reflect expectations at each individual operating division and may not add up to the company-wide guidance range total.

  g.

Includes corporate administration costs.

 

 

 

BARRICK FIRST QUARTER 2026   10    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Operating Performance

 

 

 

Our presentation of reportable operating segments consists of eight gold mines (Carlin, Cortez, Turquoise Ridge, Pueblo Viejo, Loulo-Gounkoto, Kibali, North Mara and Bulyanhulu) and one copper mine (Lumwana). The remaining operating segments, including our remaining gold and copper mines, have been grouped into an “Other

 

  

 

Mines” category and will not be reported on individually. Segment performance is evaluated based on a number of measures including operating income before tax, production levels and unit production costs. Certain costs are managed on a consolidated basis and are therefore not reflected in segment income.

Nevada Gold Mines (61.5%)a, Nevada, USA

Summary of Operating and Financial Data

 

     For the three months ended   
           
        3/31/26         12/31/25      % Change          3/31/25      % Change   

Total tonnes mined (000s)

     29,947        33,330        (10)%        36,961        (19)%  

Open pit ore

     7,028        7,299        (4)%        3,974        77 %  

Open pit waste

     21,273        24,390        (13)%        31,534        (33)%  

Underground

     1,646        1,641        0 %        1,453        13 %  

Average grade (grams/tonne)

              

Open pit mined

     0.62        1.24        (50)%        0.98        (37)%  

Underground mined

     8.24        8.80        (6)%        7.62        8 %  

Processed

     1.86        2.79        (33)%        2.51        (26)%  

Ore tonnes processed (000s)

     8,920        7,535        18 %        6,143        45 %  

Oxide mill

     1,887        2,042        (8)%        1,880        0 %  

Roaster

     1,337        1,442        (7)%        1,126        19 %  

Autoclave

     1,161        1,087        7 %        1,098        6 %  

Heap leach

     4,535        2,964        53 %        2,039        122 %  

Recovery rate

     83 %        83 %        0 %        82 %        1 %  

Oxide Mill

     72 %        73 %        (1)%        77 %        (6)%  

Roaster

     85 %        85 %        0 %        85 %        0 %  

Autoclave

     83 %        83 %        0 %        81 %        2 %  

Gold produced (000s oz)

     376        466        (19)%        342        10 %  

Oxide mill

     52        67        (22)%        72        (28)%  

Roaster

     204        258        (21)%        172        19 %  

Autoclave

     107        131        (18)%        86        24 %  

Heap leach

     13        10        30 %        12        8 %  

Gold sold (000s oz)

     380        475        (20)%        345        10 %  

Revenue ($ millions)

     1,925        2,073        (7)%        1,030        87 %  

Cost of sales ($ millions)

     687        813        (15)%        570        21 %  

Income ($ millions)

     1,233        1,236        0 %        453        172 %  

EBITDA ($ millions)b,c

     1,398        1,439        (3)%        566        147 %  

EBITDA margind

     73 %        69 %        6 %        55 %        33 %  

Capital expenditures ($ millions)e

     207        183        13 %        257        (19)%  

Minesite sustainingb

     140        118        19 %        209        (33)%  

Projectb

     65        64        2 %        48        35 %  

COS ($/oz)

     1,800        1,695        6 %        1,643        10 %  

TCC ($/oz)b

     1,255        1,191        5 %        1,269        (1)%  

AISC ($/oz)b

     1,645        1,461        13 %        1,899        (13)%  

 

  a. 

Barrick is the operator of NGM and owns 61.5%, with Newmont Corporation owning the remaining 38.5%. NGM is accounted for as a subsidiary with a 38.5% non-controlling interest. These results represent our 61.5% interest in Carlin, Cortez, Turquoise Ridge and Phoenix and non-mine site related activity.

  b. 

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

  c. 

EBITDA represents income less depreciation. Depreciation expense is $165 million for Q1 2026 (Q4 2025: $203 million, Q1 2025: $113 million.

  d. 

Represents EBITDA divided by revenue.

  e. 

Includes capitalized interest.

Across the NGM sites, gold production for Q1 2026 was 10% higher than Q1 2025, primarily due to improved underground mining and processing performance. Highlights were:

 

Carlin achieved the highest underground tonnes mined since the formation of the joint venture

 

Cortez continued to benefit from the Goldrush ramp-up also delivering the highest underground tonnes mined

 

Turquoise Ridge underground had its best quarterly performance in terms of total tonnes mined since 2021

 

The two Carlin roasters had their highest Q1 gold production since 2022, and the Sage autoclave had its highest quarterly throughput since 2021

 

 

 

BARRICK FIRST QUARTER 2026   11    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Carlin (61.5%), Nevada, USA

Summary of Operating and Financial Data

 

     For the three months ended   
           
        3/31/26         12/31/25      % Change          3/31/25      % Change   

Total tonnes mined (000s)

     10,054        12,704        (21)%        16,710        (40)%  

Open pit ore

     954        1,822        (48)%        128        645 %  

Open pit waste

     8,234        10,018        (18)%        15,786        (48)%  

Underground

     866        864        0 %        796        9 %  

Average grade (grams/tonne)

              

Open pit mined

     2.13        2.45        (13)%        1.30        64 %  

Underground mined

     7.12        7.30        (2)%        7.27        (2)%  

Processed

     4.42        5.20        (15)%        3.97        11 %  

Ore tonnes processed (000s)

     1,501        1,554        (3)%        1,377        9 %  

Roasters

     960        963        0 %        860        12 %  

Autoclave

     541        569        (5)%        499        8 %  

Heap leach

     0        22        (100)%        18        (100)%  

Recovery rate

     82 %        82 %        0 %        81 %        1 %  

Roasters

     85 %        85 %        0 %        84 %        1 %  

Autoclave

     67 %        70 %        (4)%        67 %        0 %  

Gold produced (000s oz)

     173        207        (16)%        145        19 %  

Roasters

     151        173        (13)%        125        21 %  

Autoclave

     20        31        (35)%        16        25 %  

Heap leach

     2        3        (33)%        4        (50)%  

Gold sold (000s oz)

     173        211        (18)%        142        22 %  

Revenue ($ millions)

     860        904        (5)%        417        106 %  

Cost of sales ($ millions)

     311        395        (21)%        246        26 %  

Income ($ millions)

     547        504        9 %        168        226 %  

EBITDA ($ millions)a,b

     624        605        3 %        206        203 %  

EBITDA marginc

     73 %        67 %        9 %        49 %        49 %  

Capital expenditures ($ millions)d

     113        91        24 %        174        (35)%  

Minesite sustaininga

     87        70        24 %        156        (44)%  

Projecta

     25        20        25 %        18        39 %  

COS ($/oz)

     1,794        1,863        (4)%        1,720        4 %  

TCC ($/oz)a

     1,315        1,380        (5)%        1,459        (10)%  

AISC ($/oz)a

     1,838        1,732        6 %        2,570        (28)%  

 

  a. 

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

  b. 

EBITDA represents income less depreciation. Depreciation expense is $77 million for Q1 2026 (Q4 2025: $101 million, Q1 2025: $38 million).

  c. 

Represents EBITDA divided by revenue.

  d. 

Includes capitalized interest.

 

Safety and Environment  
For the three months ended  
      3/31/26      12/31/25  

LTI

     1        1  

LTIFR3

     0.43        0.42  

TRIFR3

     2.98        2.10  

Class 14 environmental incidents

     0        0  

Financial Results

Q1 2026 compared to Q4 2025

Gold production in Q1 2026 was 16% lower compared to Q4 2025 primarily due to lower grades mined and processed. This was driven by lower Leeville underground grades due to mine sequencing and a focus on development, as well as lower volumes and grades from the Arturo open pit as mining reached the floor of the pit.

COS/oz2 and TCC/oz1 in Q1 2026 were 4% and 5% lower, respectively, than Q4 2025, driven by higher capital development and lower autoclave costs from blend changes that resulted in lower acid and lime consumption, partially offset by lower fixed cost dilution due to lower sales volumes. In Q1 2026, AISC/oz1 was 6% higher than Q4 2025, due to higher sustaining capital expenditures1, partially offset by lower TCC/oz1.

Capital expenditures increased by 24% compared to Q4 2025 mainly due to higher underground development and open pit waste stripping at Gold Quarry and higher project capital expenditures from increased growth exploration drilling.

Q1 2026 compared to Q1 2025

Gold production for Q1 2026 was 19% higher than Q1 2025, primarily due to improved underground mining and processing performance, delivering the best underground

 

 

 

 

BARRICK FIRST QUARTER 2026   12    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

tonnage start since the formation of NGM in 2019 and the best Q1 roaster production since 2022. This was further supported by higher tonnes and grades mined from the Arturo open pit, as mining was completed in Q1 2026 whereas there was mainly waste stripping in Q1 2025.

COS/oz2 for Q1 2026 was 4% higher than Q1 2025, as higher depreciation expense associated with the Arturo open pit was partially offset by lower TCC/oz1. TCC/oz1 was 10% lower, primarily due to higher fixed cost dilution driven by higher sales volumes and lower roaster maintenance costs compared to Q1 2025 related to the timing of the planned shutdown, partially offset by higher royalties due to the higher average gold price. For Q1 2026, AISC/oz1 was 28% lower than Q1 2025 owing to lower TCC/oz1 combined with lower minesite sustaining capital expenditures1.

Capital expenditures were 35% lower than Q1 2025, mainly due to lower minesite sustaining capital expenditures1 following the purchase of the Komatsu-930 truck fleet in Q1 2025, partially offset by higher project capital expenditures from increased growth exploration drilling.

 

 

 

 

BARRICK FIRST QUARTER 2026   13    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Cortez (61.5%), Nevada, USA

Summary of Operating and Financial Data

 

     For the three months ended   
           
        3/31/26         12/31/25      % Change          3/31/25      % Change   

Total tonnes mined (000s)

     14,058        13,465        4 %        14,397        (2)%  

Open pit ore

     4,446        3,147        41 %        1,391        220 %  

Open pit waste

     9,079        9,770        (7)%        12,550        (28)%  

Underground

     533        548        (3)%        456        17 %  

Average grade (grams/tonne)

              

Open pit mined

     0.27        0.73        (63)%        1.14        (76)%  

Underground mined

     7.93        8.65        (8)%        6.37        24 %  

Processed

     0.87        1.82        (52)%        1.87        (53)%  

Ore tonnes processed (000s)

     4,426        2,963        49 %        1,782        148 %  

Oxide mill

     544        540        1 %        526        3 %  

Roasters

     372        475        (22)%        266        40 %  

Autoclave

     2        2        — %        13        (85)%  

Heap leach

     3,508        1,946        80 %        977        259 %  

Recovery rate

     81 %        83 %        (2)%        85 %        (5)%  

Oxide Mill

     70 %        78 %        (10)%        82 %        (15)%  

Roasters

     87 %        86 %        1 %        87 %        0 %  

Autoclave

     63 %        24 %        163 %        52 %        21 %  

Gold produced (000s oz)

     89        130        (32)%        92        (3)%  

Oxide Mill

     28        40        (30)%        37        (24)%  

Roasters

     52        84        (38)%        46        13 %  

Autoclave

     0        0        0 %        1        (100)%  

Heap leach

     9        6        50 %        8        13 %  

Gold sold (000s oz)

     89        136        (35)%        96        (7)%  

Revenue ($ millions)

     442        577        (23)%        281        57 %  

Cost of sales ($ millions)

     192        218        (12)%        148        30 %  

Income ($ millions)

     249        357        (30)%        131        90 %  

EBITDA ($ millions)a,b

     299        410        (27)%        166        80 %  

EBITDA marginc

     68 %        71 %        (4)%        59 %        15 %  

Capital expenditures ($ millions)

     68        64        6 %        60        13 %  

Minesite sustaininga

     32        22        45 %        32        0 %  

Projecta

     36        42        (14)%        28        29 %  

COS ($/oz)

     2,149        1,592        35 %        1,541        39 %  

TCC ($/oz)a

     1,569        1,196        31 %        1,172        34 %  

AISC ($/oz)a

     1,957        1,384        41 %        1,536        27 %  

 

  a. 

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

  b. 

EBITDA represents income less depreciation. Depreciation expense is $50 million for Q1 2026 (Q4 2025: $53 million, Q1 2025: $35 million).

  c. 

Represents EBITDA divided by revenue.

 

Safety and Environment  
For the three months ended  
      3/31/26      12/31/25  

LTI

     1        1  

LTIFR3

     0.92        0.88  

TRIFR3

     2.77        2.63  

Class 14 environmental incidents

     0        0  

Financial Results

Q1 2026 compared to Q4 2025

Gold production in Q1 2026 was 32% lower than Q4 2025, primarily driven by lower tonnes and grades mined from the Cortez Hills underground due to mine sequencing as well as lower open pit production following the completion of

mining of high grade ore from Cortez Pits phase 1 in Q4 2025.

COS/oz2 and TCC/oz1 in Q1 2026 were 35% and 31% higher, respectively, than Q4 2025, primarily reflecting lower fixed cost dilution driven by lower sales volume, higher royalties as production shifts to higher royalty regions, partially offset by an increase in capitalized stripping at Cortez Pits phase 2 and higher underground development. In Q1 2026, AISC/oz1 was 41% higher than Q4 2025, driven by higher TCC/oz1, combined with higher minesite sustaining capital expenditures1.

Capital expenditures in Q1 2026 were 6% higher than Q4 2025 due to higher minesite sustaining capital expenditures1 primarily related to the start of waste stripping at Cortez Pits phase 2 and the timing of equipment down payments and deliveries. This was partially offset by

 

 

 

 

BARRICK FIRST QUARTER 2026   14    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

lower project capital expenditures1 that decreased by 14% in Q1 2026 related to equipment down payments for Goldrush made in Q4 2025.

Q1 2026 compared to Q1 2025

Gold production for Q1 2026 was 3% lower than Q1 2025, primarily driven by lower oxide mill production due to the completion of Cortez Pits phase 1 in Q4 2025, partially offset by the ramp-up at Goldrush driving a Q1 record for underground deliveries. This was combined with a 220% increase in open pit ore mined, consistent with the planned mining sequence as stripping was completed at Crossroads.

COS/oz2 and TCC/oz1 for Q1 2026 were 39% and 34% higher, respectively, than Q1 2025, reflecting an increased proportion of higher cost refractory ounces processed at the Carlin roasters, lower fixed cost dilution driven by lower sales volumes, and higher royalties due to increased gold prices and increased production from higher royalty regions. For Q1 2026, AISC/oz1 was 27% higher than Q1 2025 driven by higher TCC/oz1.

Capital expenditures in Q1 2026 were 13% higher than Q1 2025, primarily due to higher project capital expenditures1 related to the autonomous haul truck project and continued ramp-up at Goldrush.

 

 

 

 

BARRICK FIRST QUARTER 2026   15    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Turquoise Ridge (61.5%), Nevada, USA

Summary of Operating and Financial Data

 

            For the three months ended   
           
        3/31/26        12/31/25      % Change          3/31/25      % Change   

Total tonnes mined (000s)

     887        327        171 %        201        341 %  

Open pit ore

     5        43        (88)%               — %  

Open pit waste

     635        55        1,055 %               — %  

Underground

     247        229        8 %        201        23 %  

Average grade (grams/tonne)

              

Open pit mined

     0.50        1.47        (66)%        n/a        n/a  

Underground mined

     12.40        14.06        (12)%        10.63        17 %  

Processed

     4.70        6.20        (24)%        4.08        15 %  

Ore tonnes processed (000s)

     713        599        19 %        655        9 %  

Oxide Mill

     90        79        14 %        69        30 %  

Autoclave

     618        516        20 %        586        5 %  

Roaster

     5        4        (100)%        n/a        n/a  

Recovery rate

     86 %        88 %        (2)%        85 %        1 %  

Oxide Mill

     81 %        83 %        (2)%        85 %        (5)%  

Autoclave

     87 %        88 %        (1)%        86 %        1 %  

Roaster

     89 %        85 %        5 %        n/a        n/a  

Gold produced (000s oz)

     90        105        (14)%        74        22 %  

Oxide Mill

     3        4        (25)%        5        (40)%  

Autoclave

     87        100        (13)%        69        26 %  

Heap leach

            1        (100)%               — %  

Gold sold (000s oz)

     96        104        (8)%        78        23 %  

Revenue ($ millions)

     475        443        7 %        224        112 %  

Cost of sales ($ millions)

     128        149        (14)%        125        2 %  

Income ($ millions)

     350        294        19 %        99        254 %  

EBITDA ($ millions)a,b

     379        333        14 %        128        196 %  

EBITDA marginc

     80 %        75 %        7 %        57 %        40 %  

Capital expenditures ($ millions)

     16        19        (16)%        14        14 %  

Minesite sustaininga

     13        17        (24)%        13        — %  

Projecta

     4        2        100 %        1        300 %  

COS ($/oz)

     1,327        1,422        (7)%        1,605        (17)%  

TCC ($/oz)a

     1,011        1,050        (4)%        1,227        (18)%  

AISC ($/oz)a

     1,153        1,225        (6)%        1,408        (18)%  

 

  a. 

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

  b. 

EBITDA represents income less depreciation. Depreciation expense is $29 million for Q1 2026 (Q4 2025: $39 million, Q1 2025: $29 million).

  c. 

Represents EBITDA divided by revenue.

 

Safety and Environment  
For the three months ended  
      3/31/26      12/31/25  

LTI

     0        0  

LTIFR3

     0.00        0.00  

TRIFR3

     6.21        0.00  

Class 14 environmental incidents

     0        0  

Financial Results

Q1 2026 compared to Q4 2025

Gold production in Q1 2026 was 14% lower than Q4 2025, mainly due to lower grades processed driven by mine sequencing at the Turquoise Ridge underground mine. This was partly offset by higher throughput at the Sage autoclave as a result of the planned shutdown that occurred in Q4 2025. Continued improvements in underground mining and process performance drove record quarterly underground tonnage and highest Sage Autoclave throughput since 2021.

COS/oz2 and TCC/oz1 in Q1 2026 were 7% and 4% lower, respectively, than Q4 2025, primarily due to lower maintenance costs given the planned autoclave shutdown in Q4 2025. AISC/oz1 was 6% lower than Q4 2025, primarily reflecting lower TCC/oz1, combined with decreased minesite sustaining capital expenditures1.

Q1 2026 compared to Q1 2025

Gold production for Q1 2026 was 22% higher than Q1 2025, primarily driven by improved underground performance, resulting in record tonnage mined and increased throughput at the Sage autoclave during Q1 2026, resulting in its best quarterly performance since 2021.

COS/oz2 and TCC/oz1 for Q1 2026 were 17% and 18% lower, respectively, than Q1 2025, primarily owing to higher grades processed and increased fixed cost dilution. AISC/oz1 was 18% lower than Q1 2025, reflecting lower TCC/oz1, while minesite sustaining capital expenditures1 were in line with the prior period.

 

 

 

 

BARRICK FIRST QUARTER 2026   16    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Pueblo Viejo (60%)a, Dominican Republic

Summary of Operating and Financial Data

 

            For the three months ended   
           
        3/31/26        12/31/25      % Change          3/31/25      % Change   

Open pit tonnes mined (000s)

     4,365        6,257        (30)%        1,382        216 %  

Open pit ore

     355        1,905        (81)%        89        299 %  

Open pit waste

     4,010        4,352        (8)%        1,293        210 %  

Average grade (grams/tonne)

              

Open pit mined

     2.10        2.29        (8)%        2.19        (4)%  

Processed

     2.29        2.59        (12)%        2.17        6 %  

Autoclave ore tonnes processed (000s)

     1,574        1,807        (13)%        1,294        22 %  

Recovery rate

     74 %        69 %        7 %        82 %        (10)%  

Gold produced (000s oz)

     81        103        (21)%        74        9 %  

Gold sold (000s oz)

     82        106        (23)%        76        8 %  

Revenue ($ millions)

     395        476        (17)%        228        73 %  

Cost of sales ($ millions)

     139        157        (11)%        141        (1)%  

Income ($ millions)

     253        313        (19)%        84        201 %  

EBITDA ($ millions)b,c

     293        361        (19)%        128        129 %  

EBITDA margind

     74 %        76 %        (3)%        56 %        32 %  

Capital expenditures ($ millions)e

     61        72        (15)%        46        33 %  

Minesite sustainingb

     35        41        (15)%        36        (3)%  

Projectb

     26        29        (10)%        8        225 %  

COS ($/oz)

     1,702        1,492        14 %        1,863        (9)%  

TCC ($/oz)b

     1,019        930        10 %        1,189        (14)%  

AISC ($/oz)b

     1,457        1,322        10 %        1,668        (13)%  

 

  a. 

Barrick is the operator of Pueblo Viejo and owns 60%, with Newmont Corporation owning the remaining 40%. Pueblo Viejo is accounted for as a subsidiary with a 40% non-controlling interest. The results in the table and the discussion that follows are based on our 60% share only.

  b. 

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

  c. 

EBITDA represents income less depreciation. Depreciation expense is $40 million for Q1 2026 (Q4 2025: $48 million, Q1 2025: $44 million).

  d. 

Represents EBITDA divided by revenue.

  e. 

Includes capitalized interest.

 

Safety and Environment  
For the three months ended   
      3/31/26      12/31/25   

LTI

     0        0  

LTIFR3

     0.00        0.00  

TRIFR3

     0.81        0.26  

Class 14 environmental incidents

     0        0  

Financial Results

Q1 2026 compared to Q4 2025

Q1 2026 was impacted by lower tonnes and grades processed compared to Q4 2025. Tonnes processed decreased by 13% due to the Q1 2026 scheduled plant shutdown. Lower grades processed were related to mine sequencing which included the opening of new faces in the Moore pit. This was partially offset by a 7% improvement in recovery rates, in particular the flotation sulphide recovery and mass pull.

COS/oz2 and TCC/oz1 for Q1 2026 were 14% and 10% higher respectively compared to Q4 2025, primarily reflecting lower fixed cost dilution and higher operating costs due to the scheduled plant shutdown in Q1 2026. For Q1 2026, AISC/oz1 was 10% higher than Q4 2025, driven by higher TCC/oz1 partially offset by lower minesite sustaining capital expenditures1.

Capital expenditures for Q1 2026 decreased by 15% compared to Q4 2025, due to lower sustaining capital

expenditures1 mainly related to the timing of major projects including mobile equipment and kiln refractory works.

Q1 2026 compared to Q1 2025

Gold production for Q1 2026 was 9% higher than Q1 2025, driven by higher tonnes processed as the prior year quarter was impacted by the extended shutdown for debottlenecking work whereas the Q1 2026 shutdown was shorter. In addition to this impact, grades processed were higher in Q1 2026, although this was partially offset by lower recoveries due to more tonnes processed through flotation.

COS/oz2 and TCC/oz1 for Q1 2026 were 9% and 14% lower, respectively, compared to Q1 2025, primarily reflecting higher fixed cost dilution and also aided by higher costs allocated to silver by-products. For Q1 2026, AISC/oz1 was 13% lower than Q1 2025, driven by lower TCC/oz1, and lower minesite sustaining capital expenditures1 on a per ounce basis.

Capital expenditures for Q1 2026 increased by 33% compared to Q1 2025, primarily due to increased project capital expenditures1 related to the Naranjo TSF.

 

 

 

 

BARRICK FIRST QUARTER 2026   17    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Loulo-Gounkoto (80%)a,b, Mali

Summary of Operating and Financial Data

 

            For the three months ended   
           
        3/31/26        12/31/25      % Change          3/31/25      % Change   

Total tonnes mined (000s)

     390        53        636 %        1,709        (77)%  

Open pit ore

                   —          57        (100)%  

Open pit waste

                   —          1,366        (100)%  

Underground

     390        53        636 %        286        36 %  

Average grade (grams/tonne)

              

Open pit mined

                   —          1.98        (100)%  

Underground mined

     4.57        7.71        (41)%        6.66        (31)%  

Processed

     3.13        3.84        (18)%        3.54        (12)%  

Ore tonnes processed (000s)

     689        97        610 %        169        308 %  

Recovery rate

     92 %        89 %        3 %        91 %        1 %  

Gold produced (000s oz)

     64        11        482 %        18        256 %  

Gold sold (000s oz)

     69        91        (24)%               100 %  

Revenue ($ millions)

     341        404        (16)%               100 %  

Cost of sales ($ millions)

     193        269        (28)%        5        3,760 %  

Income (loss) ($ millions)

     131        (70)        (287)%        (69)        (290)%  

EBITDA ($ millions)c,d

     161        (50)        (422)%        (64)        (352)%  

EBITDA margine

     47 %        (12)%        (492)%               100 %  

Capital expenditures ($ millions)c,f

                   —          14        (100)%  

Minesite sustainingc

                   —          10        (100)%  

Projectc,f

                   —          3        (100)%  

COS ($/oz)

     2,801        4,151        (33)%               100 %  

TCC ($/oz)c

     1,918        1,448        32 %               100 %  

AISC ($/oz)c

     1,933        1,448        33 %               100 %  

 

  a. 

Barrick owns 80% of Société des Mines de Loulo SA and Société des Mines de Gounkoto with the Republic of Mali owning 20%. Loulo-Gounkoto is accounted for as a subsidiary with a 20% non-controlling interest on the basis that Barrick controls the asset. The results in the table and the discussion that follows are based on our 80% share.

  b. 

As a result of temporary suspension of operations at Loulo-Gounkoto starting January 14, 2025, and subsequent loss of control on June 16, 2025, no operating data or per ounce data was provided for Q1 2025 to Q3 2025. On November 24, 2025, Barrick announced that an agreement had been entered into with the Government of the Republic of Mali to put an end to all disputes regarding the Loulo and Gounkoto mines. The provisional administration of the Loulo-Gounkoto complex was terminated on December 16, 2025, at which point operational control was handed back to Somilo and Gounkoto’s management.

  c. 

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

  d. 

EBITDA represents income less depreciation. Depreciation expense is $30 million for Q1 2026 (Q4 2025: $20 million, Q1 2025: $5 million).

  e. 

Represents EBITDA divided by revenue.

  f. 

Includes capitalized interest.

 

Safety and Environment  
For the three months ended  
      3/31/26      12/31/25  

LTI

     0        0  

LTIFR3

     0.00        0.00  

TRIFR3

     0.00        0.00  

Class 14 environmental incidents

     0        0  

Financial Results

Q1 2026 compared to Q4 2025

Gold production for Q1 2026 was substantially higher than Q4 2025 as a result of Barrick only regaining operational control midway through December 2025. The ramping up of operations during Q1 2026 has progressed ahead of schedule with both mining and processing outperforming compared to the restart plan.

COS/oz2 was 33% lower than Q4 2025, due to the fair value increment on inventory resulting from the purchase price allocation when we regained control of Loulo-Gounkoto and the large one-off shipment of gold inventory that occurred in Q4 2025 following the lifting of

the restrictions imposed by the Government of Mali on gold shipments. This is also the driver of the higher sales volumes in Q4 2025 relative to Q1 2026. TCC/oz1 for Q1 2026 was 32% higher reflecting the impact from ramping up of mining and processing activities during Q1 2026. For Q1 2026, AISC/oz1 was 33% higher than Q4 2025, mainly due to higher TCC/oz1.

There were no capital expenditures for Q1 2026 and Q4 2025, due to the impact of the restart procedures and rebasing of the mine plan to accommodate the ramp up to normal operations. Critical capital commitments have been prioritized for Q2 2026 and remain on track.

Q1 2026 compared to Q1 2025

Gold production for Q1 2026 was 256% higher than Q1 2025 due to the suspension of operations midway through January 2025 as a result of the dispute with the Government of Mali that was ultimately resolved in December 2025. This resulted in no gold sales in Q1 2025 and also explains zero TCC/oz1, AISC/oz1 and COS/oz2 for Q1 2025 given there were no sales.

 

 

 

 

BARRICK FIRST QUARTER 2026   18    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Kibali (45%)a, Democratic Republic of Congo

Summary of Operating and Financial Data

 

            For the three months ended   
           
        3/31/26      12/31/25      % Change          3/31/25      % Change   

Total tonnes mined (000s)

     6,834        6,840        0 %        5,246        30 %  

Open pit ore

     694        884        (21)%        392        77 %  

Open pit waste

     5,790        5,607        3 %        4,472        29 %  

Underground

     350        349        0 %        382        (8)%  

Average grade (grams/tonne)

              

Open pit mined

     1.42        1.59        (11)%        1.48        (4)%  

Underground mined

     4.74        5.38        (12)%        5.02        (6)%  

Processed

     2.24        2.91        (23)%        2.36        (5)%  

Ore tonnes processed (000s)

     910        933        (2)%        931        (2)%  

Recovery rate

     89 %        91 %        (2)%        90 %        (1)%  

Gold produced (000s oz)

     58        79        (27)%        63        (8)%  

Gold sold (000s oz)

     69        78        (12)%        67        3 %  

Revenue ($ millions)

     342        328        4 %        192        78 %  

Cost of sales ($ millions)

     132        123        7 %        113        17 %  

Income ($ millions)

     198        205        (3)%        72        175 %  

EBITDA ($ millions)b,c

     231        241        (4)%        104        122 %  

EBITDA margind

     68 %        73 %        (7)%        54 %        26 %  

Capital expenditures ($ millions)

     38        39        (3)%        32        19 %  

Minesite sustainingb

     11        19        (42)%        12        (8)%  

Projectb

     27        20        35 %        20        35 %  

COS ($/oz)

     1,906        1,557        22 %        1,691        13 %  

TCC ($/oz)b

     1,418        1,093        30 %        1,212        17 %  

AISC ($/oz)b

     1,614        1,374        17 %        1,426        13 %  

 

  a. 

Barrick owns 45% of Kibali Goldmines SA with the Government of DRC and our joint venture partner, AngloGold Ashanti, owning 10% and 45%, respectively. The figures presented in this table and the discussion that follows are based on our 45% effective interest in Kibali Goldmines SA held through our 50% interest in Kibali (Jersey) Limited and its other subsidiaries (collectively “Kibali”), inclusive of the impact of the purchase price allocation resulting from the merger with Randgold. Kibali is accounted for as an equity method investment on the basis that the joint venture partners that have joint control have rights to the net assets of the joint venture.

  b. 

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

  c. 

EBITDA represents income less depreciation. Depreciation expense is $33 million for Q1 2026 (Q4 2025: $36 million, Q1 2025: $32 million).

  d. 

Represents EBITDA divided by revenue.

 

Safety and Environment  
For the three months ended  
      3/31/26      12/31/25  

LTI

     2        0  

LTIFR3

     0.37        0.00  

TRIFR3

     0.75        0.35  

Class 14 environmental incidents

     0        0  

Financial Results

Q1 2026 compared to Q4 2025

Gold production for Q1 2026 was 27% lower than Q4 2025 mainly due to lower grades processed and lower tonnes mined. This was in line with plan as we shift focus to ramping up the underground development to ensure we are well placed to achieve our production targets and build operational flexibility. We continue to focus on improving equipment utilization and commissioning additional underground trucking capacity as we expect to deliver higher underground production in H2 2026.

COS/oz2 and TCC/oz1 for Q1 2026 were 22% and 30% higher, respectively, mainly due to the lower grades processed, further increased by higher royalties driven by a higher realized gold price1. For Q1 2026, AISC/oz1 was 17% higher than in Q4 2025, driven by a higher TCC/oz1

partially offset by lower minesite sustaining capital expenditures1 resulting from lower equipment purchases and rebuild costs compared to Q4 2025.

Q1 2026 compared to Q1 2025

Gold production for Q1 2026 was 8% lower than Q1 2025, mainly due to lower grades processed resulting from lower high grade underground tonnes mined. This was partially offset by a successful ramp-up in the open pits that delivered 77% more ore tonnes, providing critical operational flexibility.

COS/oz2 and TCC/oz1 for Q1 2026 were 13% and 17% higher, respectively, compared to Q1 2025 mainly resulting from increased labor and fuel costs driving higher unit costs coupled with higher royalties resulting from a higher realized gold price1. For Q1 2026, AISC/oz1 was 13% higher than Q1 2025, driven by higher TCC/oz1, partially offset by lower minesite sustaining capital expenditures1.

Capital expenditures for Q1 2026 were 19% higher than Q1 2025, predominantly driven by increased project capital expenditures1 driven by the Pamao TSF project.

 

 

 

 

BARRICK FIRST QUARTER 2026   19    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

North Mara (84%)a, Tanzania

Summary of Operating and Financial Data

 

            For the three months ended   
           
        3/31/26        12/31/25      % Change          3/31/25      % Change   

Total tonnes mined (000s)

     3,952        4,297        (8)%        3,843        3 %  

Open pit ore

     7        17        (59)%        1,057        (99)%  

Open pit waste

     3,599        3,845        (6)%        2,398        50 %  

Underground

     346        435        (20)%        388        (11)%  

Average grade (grams/tonne)

              

Open pit mined

     0.99        1.01        (2)%        2.04        (51)%  

Underground mined

     2.64        3.74        (29)%        3.72        (29)%  

Processed

     1.81        2.87        (37)%        3.56        (49)%  

Ore tonnes processed (000s)

     664        683        (3)%        672        (1)%  

Recovery rate

     85 %        90 %        (6)%        88 %        (3)%  

Gold produced (000s oz)

     33        56        (41)%        67        (51)%  

Gold sold (000s oz)

     36        56        (36)%        68        (47)%  

Revenue ($ millions)

     183        234        (22)%        198        (8)%  

Cost of sales ($ millions)

     83        91        (9)%        86        (3)%  

Income ($ millions)

     97        129        (25)%        109        (11)%  

EBITDA ($ millions)b,c

     115        150        (23)%        127        (9)%  

EBITDA margind

     63 %        64 %        (2)%        64 %        (2)%  

Capital expenditures ($ millions)

     45        56        (20)%        34        32 %  

Minesite sustainingb

     7        17        (59)%        17        (59)%  

Projectb

     37        39        (5)%        17        118 %  

COS ($/oz)

     2,287        1,640        39 %        1,257        82 %  

TCC ($/oz)b

     1,758        1,237        42 %        986        78 %  

AISC ($/oz)b

     1,990        1,546        29 %        1,258        58 %  

 

  a. 

Barrick owns 84% of North Mara, with the GoT owning 16%. North Mara is accounted for as a subsidiary with a 16% non-controlling interest on the basis that Barrick controls the asset. The results in the table and the discussion that follows are based on our 84% share.

  b. 

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

  c. 

EBITDA represents income less depreciation. Depreciation expense is $18 million for Q1 2026 (Q4 2025: $21 million, Q1 2025: $18 million).

  d. 

Represents EBITDA divided by revenue.

 

Safety and Environment  
For the three months ended  
      3/31/26      12/31/25  

LTI

     0        0  

LTIFR3

     0.00        0.00  

TRIFR3

     0.00        0.32  

Class 14 environmental incidents

     0        0  

Financial Results

Q1 2026 compared to Q4 2025

In Q1 2026, North Mara continued to rely on the underground operations with the open pit mining activity centered around waste material movement in the Gokona pit. In Q1 2026, gold production was 41% lower than Q4 2025 mainly driven by lower grades processed and lower throughput as we aim to build flexibility in the operation to support achieving our targets over the remainder of 2026.

COS/oz2 and TCC/oz1 for Q1 2026 were 39% and 42% higher, respectively, compared to Q4 2025 mainly due to the impact of the lower grades processed, higher energy costs driven by increased diesel powered generation to overcome Tanesco power fluctuations and higher royalties associated with the higher realized gold price1. AISC/oz1 in Q1 2026 was 29% higher than Q4 2025, mainly due to higher TCC/oz1, partially offset by lower minesite sustaining capital expenditures1.

Capital expenditures for Q1 2026 were 20% lower compared to Q4 2025 mainly driven by planned down payments in Q4 2025 to secure build slots for underground mobile equipment. Project capital expenditures1 were only slightly lower quarter on quarter with the Gokona open pit pre-stripping project on track to deliver as planned.

Q1 2026 compared to Q1 2025

Gold production for Q1 2026 was 51% lower compared to Q1 2025 mainly due to lower grades processed and lower recoveries.

COS/oz2 and TCC/oz1 for Q1 2026 were 82% and 78% higher, respectively, compared to Q1 2025, mainly due to the lower grades processed, combined with higher royalties associated with the higher realized gold price1. AISC/oz1 in Q1 2026 was 58% higher than Q1 2025, mainly due to the higher TCC/oz1, while minesite sustaining capital expenditures1 were lower than Q1 2025.

For Q1 2026, capital expenditures increased by 32% compared to Q1 2025, mainly due to higher project capital expenditures1 relating to the Gokona pre-stripping project.

 

 

 

 

BARRICK FIRST QUARTER 2026   20    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Bulyanhulu (84%)a, Tanzania

Summary of Operating and Financial Data

 

       

For the three months ended 

 

 
        3/31/26        12/31/25      % Change          3/31/25      % Change   

Underground tonnes mined (000s)

     349        356        (2)%        304        15 %  

Average grade (grams/tonne)

              

Underground mined

     5.47        5.44        1 %        5.27        4 %  

Processed

     5.15        5.71        (10)%        5.27        (2)%  

Ore tonnes processed (000s)

     204        224        (9)%        237        (14)%  

Recovery rate

     96 %        97 %        (1)%        93 %        3 %  

Gold produced (000s oz)

     33        40        (18)%        37        (11)%  

Gold sold (000s oz)

     36        39        (8)%        38        (5)%  

Revenue ($ millions)

     187        175        7 %        123        52 %  

Cost of sales ($ millions)

     73        74        (1)%        65        12 %  

Income ($ millions)

     112        98        14 %        56        100 %  

EBITDA ($ millions)b,c

     127        113        12 %        70        81 %  

EBITDA margind

     68 %        65 %        5 %        57 %        19 %  

Capital expenditures ($ millions)

     37        41        (10)%        35        6 %  

Minesite sustainingb

     19        17        12 %        23        (17)%  

Projectb

     17        24        (29)%        12        42 %  

COS ($/oz)

     2,008        1,885        7 %        1,714        17 %  

TCC ($/oz)b

     1,379        1,262        9 %        1,212        14 %  

AISC ($/oz)b

     1,922        1,694        13 %        1,831        5 %  

 

  a. 

Barrick owns 84% of Bulyanhulu, with the GoT owning 16%. Bulyanhulu is accounted for as a subsidiary with a 16% non-controlling interest on the basis that Barrick controls the asset. The results in the table and the discussion that follows are based on our 84% share.

  b. 

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

  c. 

EBITDA represents income less depreciation. Depreciation expense is $15 million for Q1 2026 (Q4 2025: $15 million, Q1 2025: $14 million).

  d. 

Represents EBITDA divided by revenue.

 

Safety and Environment  

For the three months ended

 
      3/31/26      12/31/25  

LTI

     0        1  

LTIFR3

     0.00        0.48  

TRIFR3

     0.48        2.88  

Class 14 environmental incidents

     0        0  

Financial Results

Q1 2026 compared to Q4 2025

Q1 2026 production was 18% below Q4 2025 driven by lower grades and tonnes processed. This was in line with the plan and a result of the focus on development activity in Q1 2026. The Upper West project continues to advance well and remains on track.

COS/oz2 and TCC/oz1 in Q1 2026 were 7% and 9% higher, respectively, due to the impact of the lower grades processed and higher royalties associated with the higher realized gold price1. AISC/oz1 in Q1 2026 was 13% higher than Q4 2025, due to higher TCC/oz1 and higher minesite sustaining capital expenditures1.

Capital expenditures in Q1 2026 were 10% lower compared to Q4 2025, reflecting lower project capital expenditures1 driven by the timing of spend on the Upper West decline.

Q1 2026 compared to Q1 2025

For Q1 2026, gold production was 11% lower than Q1 2025 mainly driven by lower tonnes and grades processed partially offset by higher recoveries.

COS/oz2 and TCC/oz1 for Q1 2026 were 17% and 14% higher compared to Q1 2025, due to the lower grades processed and higher royalties associated with the higher realized gold price1, slightly offset by improved underground unit cost rates associated with operational efficiency. AISC/oz1 in Q1 2026 was 5% higher than Q1 2025, mainly due to higher TCC/oz1, partially offset by lower sustaining capital expenditures1.

For Q1 2026, capital expenditures were 6% higher than Q1 2025, mainly due to higher project capital expenditures1 related to the development of Upper West project.

 

 

 

 

BARRICK FIRST QUARTER 2026   21    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Other Mines - Gold

Summary of Operating and Financial Data

 

                                                              For the three months ended  
      3/31/26      12/31/25  
     

Gold

produced

(000s oz)

    

COS

($/oz)

    

TCC

($/oz)a

    

AISC

($/oz)a

    

Capital

Expend-

ituresb

    

Gold

produced

(000s oz)

    

COS

($/oz)

    

TCC

($/oz)a

    

AISC

($/oz)a

    

Capital

Expend-

ituresb

 

Phoenix (61.5%)

     23        2,485        574        862        5        24        1,972        127        279        3  

Veladero (50%)

     55        1,816        1,037        1,253        25        48        1,526        886        1,915        56  

Porgera (24.5%)

     19        1,665        1,346        1,740        10        24        1,608        1,180        1,865        17  

Tongon (89.7%)c

                                        18        2,648        2,659        2,844        4  

Hemlod

                                        26        1,738        1,707        1,976        8  

 

  a. 

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

  b. 

Includes both minesite sustaining and project capital expenditures1.

  c. 

On October 6, 2025, we reached an agreement to sell our interest in the Tongon gold mine and certain of its exploration properties to the Atlantic Group for total consideration of up to $305 million. The transaction closed on December 1, 2025. Accordingly, operating and financial results provided are up to the closing date.

  d.

On September 10, 2025, we reached an agreement to sell the Hemlo gold mine to Carcetti Capital Corp. for gross proceeds of up to $1.09 billion. The transaction closed on November 26, 2025. Accordingly, operating and financial results provided are up to the closing date.

 

Phoenix (61.5%), Nevada, USA

Gold production for Phoenix in Q1 2026 was slightly below the prior quarter as lower grades mined and processed were partially offset by higher recoveries. COS/oz2 was 26% higher due to lower fixed cost dilution driven by lower sales volume compared to Q4 2025 while TCC/oz1 in Q1 2026 was 352% higher, mainly due to lower costs allocated to by-products. In Q1 2026, AISC/oz1 increased by 209% compared to Q4 2025 due to higher TCC/oz1 combined with higher minesite sustaining capital expenditures1.

Veladero (50%), Argentina

Gold production for Veladero in Q1 2026 was 15% higher compared to Q4 2025 driven by higher throughput and grades, partially offset by lower recovery. COS/oz2 and TCC/oz1 in Q1 2026 were 19% and 17% higher, respectively, mainly driven by lower capitalized stripping and higher royalties from the higher gold price. COS/oz2 was further impacted by higher depreciation as result of mine equipment that arrived in late Q4 2025. AISC/oz1 decreased by 35% due to lower minesite sustaining capital expenditures1 compared to Q4 2025, which included high sustaining capital expenditures1 from purchases of mine equipment referred to above, partially offset by higher TCC/oz1.

Porgera (24.5%), Papua New Guinea

Gold production in Q1 2026 was 21% lower than Q4 2025 driven by lower grades from mine sequencing and lower throughput due to planned maintenance. COS/oz2 and TCC/oz1 were 4% and 14% higher, respectively, driven by lower production and higher royalties from the higher gold price. AISC/oz1 decreased by 7% as result of lower minesite sustaining capital expenditures, partially offset by higher TCC/oz1.

 

 

 

 

BARRICK FIRST QUARTER 2026   22    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Lumwana (100%), Zambia

Summary of Operating and Financial Data

 

       

For the three months ended 

 

 
        3/31/26        12/31/25      % Change          3/31/25      % Change   

Open pit tonnes mined (000s)

     31,064        32,205        (4)%        30,310        2 %  

Open pit ore

     5,784        8,343        (31)%        6,004        (4)%  

Open pit waste

     25,280        23,862        6 %        24,306        4 %  

Average grade

              

Open pit mined

     0.58 %        0.56 %        4 %        0.59 %        (2)%  

Processed

     0.59 %        0.65 %        (9)%        0.57 %        4 %  

Tonnes processed (000s)

     5,911        7,029        (16)%        5,237        13 %  

Recovery rate

     91 %        91 %        0 %        91 %        0 %  

Copper produced (kt)

     32        42        (24)%        27        19 %  

Copper sold (kt)

     31        47        (34)%        34        (9)%  

Revenue ($ millions)

     347        520        (33)%        305        14 %  

Cost of sales ($ millions)

     217        282        (23)%        208        4 %  

Income ($ millions)

     124        233        (47)%        95        31 %  

EBITDA ($ millions)a,b

     167        322        (48)%        155        8 %  

EBITDA marginc

     48 %        62 %        (23)%        51 %        (6)%  

Capital expenditures ($ millions)d

     149        268        (44)%        70        113 %  

Minesite sustaininga

     45        92        (51)%        50        (10)%  

Projecta

     104        173        (40)%        20        420 %  

COS ($/lb)

     3.31        2.76        20 %        2.80        18 %  

C1 cash costs ($/lb)a

     2.67        1.97        36 %        2.22        20 %  

AISC ($/lb)a

     3.83        3.24        18 %        3.20        20 %  

 

  a.

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

  b. 

EBITDA represents income less depreciation. Depreciation expense is $43 million for Q1 2026 (Q4 2025: $89 million, Q1 2025: $60 million).

  c. 

Represents EBITDA divided by revenue.

  d. 

Includes capitalized interest.

 

Safety and Environment

For the three months ended

 

       3/31/26        12/31/25  
LTI      0        0  
LTIFR3      0.00        0.00  
TRIFR3      0.00        0.82  
Class 14 environmental incidents      0        0  

Financial Results

Q1 2026 compared to Q4 2025

Copper production in Q1 2026 was 24% lower than in Q4 2025 due to a planned plant shutdown for liner replacements which successfully took place in February 2026 leading to fewer tonnes processed. Q1 2026 feed grade was lower quarter on quarter, however this was as per the mine plan.

COS/lb2 and C1 cash costs/lb1 were 20% and 36% higher, respectively, than Q4 2025. Higher costs were driven by higher mining costs and higher processing costs. Mining costs were up due to higher maintenance costs from premature component failures which is being addressed with OEMs as well as due to the stronger local currency negatively impacting our cost base. Processing costs were up due to an unfavorable power split leading to increased higher cost generator power. In Q1 2026, AISC/lb1 increased by 18% compared to Q4 2025, primarily driven by the increase in C1 cash costs/lb1, partially offset by lower minesite sustaining capital expenditures1.

Capital expenditures for Q1 2026 were 44% lower than Q4 2025, as Q4 2025 had the highest quarterly spend in 2025, including several milestone fleet payments with the next set of fleet down payments due in April 2026 as part of the Lumwana Super Pit Expansion project. Refer to the Future Growth section on page 26 for more details. Minesite sustaining capital expenditures1 were lower in Q1 2026 due to lower capitalized waste stripping as well as a high rebuild spend in Q4 2025 in preparation for Q1 change outs.

Q1 2026 compared to Q1 2025

Copper production for Q1 2026 was 19% higher than Q1 2025, mainly due to higher throughput and higher grades processed. The higher throughput is due to the prolonged shutdown in Q1 2025 whereas the shutdown in Q1 2026 was shorter in duration.

COS/lb2 and C1 cash costs/lb1 for Q1 2026 increased by 18% and 20%, respectively, compared to Q1 2025, mainly due to the local currency appreciation driving higher payroll costs as well as higher power costs as mentioned above. For Q1 2026, AISC/lb1 was 20% higher than Q1 2025 mainly due to higher C1 cash cost/lb1, as well as higher royalties due to the higher realized copper price.

Capital expenditures for Q1 2026 were 113% higher than Q1 2025, mainly due to increased project capital expenditures1 on the Super Pit Expansion project, including earthworks, construction, mobile fleet, milestone payments on plant equipment, EPCM costs, and housing construction.

 

 

 

 

BARRICK FIRST QUARTER 2026   23    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Other Mines - Copper

Summary of Operating and Financial Data

 

                                                              For the three months ended  
      3/31/26      12/31/25  
      Copper
production
(kt)
    

 COS 

($/lb)

    

 C1 cash 

costs
($/lb)a

    

AISC

 ($/lb)a

     Capital
 Expend- 
ituresb
    

Copper
 production 

(kt)

    

 COS 

($/lb)

      C1 cash 
costs
($/lb)a
    

 AISC 

($/lb)a

      Capital 
Expend-
ituresb
 

Zaldívar (50%)

     8        4.87        3.70        5.02        30        12        6.33        5.17        6.03        25  

Jabal Sayid (50%)

     9        2.07        0.79        0.94        3        8        2.21        0.94        1.20        7  

 

  a. 

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

  b. 

Includes both minesite sustaining and project capital expenditures1.

 

Zaldívar (50%), Chile

Copper production for Zaldívar in Q1 2026 was 33% lower than Q4 2025 driven by lower throughput due to planned maintenance and lower grade from mine sequencing. COS/lb2 and C1 cash costs/lb1 were 23% and 28% lower, respectively, than Q4 2025, driven by an inventory write-down occurring in Q4 2025. AISC/lb1 in Q1 2026 was 17% lower compared to Q4 2025, due to lower C1 cash costs/lb1, partially offset by higher minesite sustaining capital expenditures1 on a per pound basis.

Our investment in this asset, of which we are not the operator, continues to be a non-core part of our portfolio.

Jabal Sayid (50%), Saudi Arabia

Jabal Sayid’s copper production in Q1 2026 was in line with Q4 2025. COS/lb2 for Q1 2026 was 6% lower than Q4 2025 due to the lower C1 cost combined with lower depreciation expense. C1 cash costs/lb1 decreased by 16% due to lower processing and general and administration costs. AISC/lb1 in Q1 2026 decreased by 22% compared to Q4 2025, mainly due to lower C1 cash costs/lb1 coupled with lower sustaining capital expenditures1 as projects closed in Q4 with new ones ramping up.

 

 

 

 

BARRICK FIRST QUARTER 2026   24    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Future Growth

 

 

 

Fourmile, Nevada, USA

Fourmile is a 100% owned Barrick asset in Nevada, located adjacent to Goldrush, that has the potential to be a standalone Tier One Gold Asset5. Barrick announced the summary results of a preliminary economic assessment (“PEA”) for Fourmile in September 2025, which outlined a conceptual underground mining operation with an indicative project capital estimate of approximately $1.5 to $1.7 billion, approximately 600,000 to 750,000 oz per annum of gold production, and life of mine COS2 of approximately $850-900 per ounce and AISC1 of approximately $650 to $750 per ounce at a long-term gold price assumption of $2,585 per ounce6. Estimated AISC1 figures are inclusive of a net profits interest royalty that will apply to production from certain portions of the Fourmile deposit and provide the royalty holder with a royalty equal to 10% of net profits from the property subject to the royalty until 6 million ounces of gold has been produced and increasing to 15% thereafter, as well as two gross smelter return royalties that will apply to the entire Fourmile deposit ranging from 1.2% to 1.3%. Ongoing PFS studies point to the potential for significant resource growth in support of a PFS expected to be completed in 2028.

With the implementation of additional safety measures, drilling activity continued through winter, adding over three months, accelerating progress towards the project’s key targets. Working in the lower elevation southern areas of Fourmile, the team was able to continue resource definition drilling while also being able to access extensional step out opportunities in the deeper Charlie zone. Drilling is planned to continue expanding throughout 2026 with lessons learned from the winter campaign being applied and having the benefit of safe and efficient drilling through the summer months.

The second year of the four year PFS project began with a focus on ventilation, mine design and paste backfill. Ventilation access trade offs were assessed to determine preferable opportunities for raise locations and design to facilitate ventilation throughout the life of mine. In addition, paste material testing and mix design also progressed, increasing confidence in the ability to satisfy the backfill requirements of the future operations.

In Q1 2026, execution planning for the dedicated decline access from twin portals to the north west of Fourmile continued. Contract negotiations are underway with key mining and construction contractors ahead of construction commencing in late 2026. These partners are also working with the team in refining the execution plan adding extra detail and working through risk assessments.

As previously disclosed, Barrick anticipates Fourmile will be incorporated into the NGM joint venture, at fair market value, if certain criteria are met following the completion of drilling and the requisite independent feasibility work.

Across drilling and studies activities, we spent $28 million in Q1 2026. Total spend for 2026 includes an anticipated drilling spend of $150 to $160 million together with $20 million of spend on studies work (both expensed) and $70 million on construction and decline commencement (capital). This phase of the project has been approved with an estimated total cost of $360 to $430 million extending through mid-2029.

Goldrush Project, Nevada, USA7,12

Goldrush, which is included within Cortez, is expected to be a long-life underground mine with anticipated annual production in excess of 400,000 ounces of gold per year (100% basis) once in full production by 2028.

In Q1 2026, execution planning continued for key infrastructure projects. The second surface ventilation shaft project kicked off with the contactor mobilized to site and excavation starting in Q2 2026. Ventilation modeling for the third surface ventilation shaft has started to define operational requirements and optimize the LOM plan. The paste plant Feasibility Design Report was completed and detailed engineering kicked off to define major equipment specifications. An Engineering, Procurement, and Construction Management contract for key projects was issued for bid with a final award targeted in Q2 2026.

The portal access road widening plan was developed in Q1 2026 and preliminary site work completed to allow access with open pit equipment. The road widening and portal pad construction is expected to be completed in Q3 2026. Goldrush’s underground water filtration system design progressed to 60%. Development started on the top level of the system and full excavation is planned to be completed and turned over to contractors in Q3 2026. Construction of a new shotcrete batch plant was completed in Q1 with full commissioning and handover in early April. The new plant and additional cement storage silo will improve production of shotcrete and cemented rockfill backfill for mining operations.

As of March 31, 2026, project spend was $500 million on a 100% basis (including $10 million in Q1 2026) inclusive of the exploration declines. This capital spent to date, together with the remaining expected pre-production capital, is still anticipated to be near the approximate $1 billion initial capital estimate for the Goldrush project (100% basis).

Along the northeastern edge of Goldrush, additional results were received from both surface and underground drilling in the southern KB area. Testing multiple target horizons and concepts, hole GUC-25147, drilled from the Goldrush underground, returned 29.3 meters at 12.05 g/t from 471.2 meters and 16.8 meters at 20.52 g/t from 538.3 meters, confirming mineral controls within the known KB zone. Further down hole, a deeper breccia target returned 11.1 meters at 57.76 g/t from 662.9 meters, supporting a high-grade, structurally controlled exploration model at depth. Lessons learned at Fourmile continue to be applied at Goldrush, with current drilling focused on extending mineralization to the north, targeting multiple ore-controlling features from KB toward North Crow. Drilling is expected to ramp up in Q2 2026 to further evaluate this opportunity.

Ren, Nevada, USA8

Ren is a new ore deposit at Goldstrike Underground and a key expansion project at Carlin. Located north of Goldstrike Underground’s Meikle and Banshee deposits, Ren is anticipated to produce an average of 140,000 ounces per

 

 

 

 

BARRICK FIRST QUARTER 2026   25    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

year (contained ounces, 100% basis) once in full production in 2027.

To develop the deposit, the existing exploration drift has been duplicated, allowing for increased ventilation and secondary egress into the working area. Additional exploration drilling platforms have been constructed from the duplicate drift to support further drilling for both existing resource conversion and further deposit growth.

To support production mining of the deposit, an additional set of twin declines will be driven from the Betze-Post West Barrel open pit layback, extending to the north with the intent to provide life of mine ventilation and a direct path for material to be hauled and hoisted out via the existing Meikle Headframe. To complete the project, a seven-meter finished diameter ventilation shaft will be sunk 550 meters to serve as an exhaust raise and utility conduit for mining the orebody.

During Q1 2026, exploration drift rehabilitation was completed for continued ventilation and utility service. Work at the West Barrel declines is continuing with commissioning of surface support infrastructure and beginning of routine decline development. The Ren ventilation shaft completed pre-sinking work scope and transitioned to production sinking infrastructure erection and commissioning. Production sinking commenced in early Q2 2026 with expected completion by year end.

As of March 31, 2026, project spend was $193 million (including $26 million in Q1 2026) out of an estimated capital cost of $410 to $470 million (100% basis).

Pueblo Viejo Expansion, Dominican Republic9

The Pueblo Viejo life of mine expansion continues to shift focus from housing and resettlement, to the Naranjo TSF and related facilities. The permits were received for the TWMS and construction is now underway, while the permitting package for the starter dam was submitted with a target receipt date of Q1 2027. Haul Road 19 continues to advance and a contract has been awarded for the second phase along with Haul Road 17 including all bridges, with mobilization ongoing. Construction of the new effluent treatment plant and the new diorite crusher are underway, while the proposal for the Reverse Osmosis Plant is expected in Q2 2026 along with advancement of engineering with the selected partner.

The housing project at Pueblo Viejo continues with over 600 homes constructed and more than 450 families now resettled. All focus is on completing the remaining 80 houses along with advancing the church and polytechnical school design. 90% of resettlement packages have now been accepted, with the public utility decree issued and full support from authorities to work with all individuals and avoid delays to the project.

As at March 31, 2026, total project spend was $1,265 million (including $36 million in Q1 2026) on a 100% basis. The estimated capital cost of the plant expansion and mine life extension project remains approximately $2.6 billion (100% basis).

Veladero Phase 8 Leach Pad, Argentina

The construction of the Phase 8 leach pad is being executed in three phases which are named 8A, 8B and 8C. Phase 8A has been completed. Phase 8B was approved in Q3 2025, with activities well advanced and completion expected in Q2 2026. The phased execution of the project provides flexibility to align future stages with economic

conditions and the applicable regulatory framework. Construction of the project includes cutting, filling, sub-drainage and monitoring, leak collection and recirculation, impermeabilization, as well as pregnant leaching solution collection.

Overall, the total Phase 8 leach pad project spend at March 31, 2026 was $119 million ($29 million in Q1 2026) out of an estimated capital cost of $250-$260 million (100% basis).

Reko Diq Project, Pakistan10

On February 5, 2026, the Company announced that it was reviewing all aspects of the project in light of the escalation of security risks and increased security incidents. On April 2, 2026, Barrick announced that following the preliminary findings of the review and further escalation of security issues in the region, the Company considers it necessary to slow the development activity and extend the project review.

Capital expenditures commenced in Q2 2024, with total capitalized spend to date of $1,083 million (including $234 million in Q1 2026) (100% basis). We previously disclosed a range for 2026 attributable capital expenditure of $600 to $700 million (50% basis) and work is continuing on estimating the timing and quantum of spend for the current year.

Kibali Solar Project, DRC

This project entails the design, supply and installation of a 16 MW photovoltaic solar farm with a 15 MW battery energy storage system to complement the existing hydroelectric power stations raising the renewable component of the mine’s energy mix from 81% to 85%. The completion of this project is projected to deliver a 53% reduction in fuel consumption in the power plant. During Q1 2026, we continued with the optimization of the power management system which enabled the solar photovoltaic field to inject 14,925MWh into the Kibali grid. As at March 31, 2026, project spend was $46 million and is substantially complete, coming in below the estimated capital cost of $55 million (100% basis).

Lumwana Super Pit Expansion, Zambia11

The Lumwana Super Pit Expansion is projected to deliver 240,000 tonnes of copper production per annum, from a 52Mtpa process plant expansion, with a mine life of more than 30 years.

The project is tracking slightly ahead of schedule with the target of first copper production at the end of Q1 2028. The main critical path for the process plant expansion is the mill building, where good progress was made during Q1 2026 with the completion of the first lift of the foundation walls and the second lift currently in progress. The primary crusher foundation has been poured, lift of the first walls is in progress and this was further complemented with the installation and commissioning of the tower crane. Long-lead equipment deliveries are tracking on schedule with the arrival of the mill shells on site during Q1 2026. The manufacturing of the structural steel commenced and the first loads of steel are currently en route to site. The building of the third phase of accommodation is ongoing and made steady progress during Q1 2026 with hand over of the first block of the third phase for occupancy. The TSF design and reviews have been completed and the construction of the first diversion channel for the expanded

 

 

 

 

BARRICK FIRST QUARTER 2026   26    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

facility is currently in progress. The contract for the construction of the Kamisengo inflow control dam has also been awarded. All orders for the 2026 mining fleet expansion have been completed and deliveries commenced during Q4 2025, with the PC7000 excavator now commissioned. The 930E haul trucks are currently in assembly.

With continued progress on the detailed engineering, procurement and construction, the total project remains on schedule and we are focused on delivery of critical milestones in line with the execution schedule. As at March 31, 2026, the total spend on the expansion project was $490 million (including $74 million in Q1 2026) with 2026 expenditure now expected to be at the lower end of the $750 to $850 million range. The total project capital cost (exclusive of capitalized stripping) is expected to be $2 billion based on the approved feasibility study.

Exploration13, 14

During Q1 2026, Barrick’s exploration teams have been active across all our operations, with strong results returned from drilling across NGM, and at Fourmile, Kibali in the DRC and Jabal Sayid in Saudi Arabia.

In North America, exploration activities remain focused within NGM, with programs across the Carlin, Cortez, Turquoise Ridge, and Battle Mountain districts. Results from the Cortez District are discussed in the Goldrush Project section. In the Carlin District, exploration at the Leeville Underground project continues to demonstrate continuity of high-grade mineralization beyond current resource boundaries. At Turquoise Ridge, drilling at the Dune target has validated an extension of the mineralized system near existing infrastructure, as represented by hole TUM-25236A, which returned 21.3 meters at 11.4g/t Au from 320.9 meters, with an estimated true width that is approximately 20-25% of the reported interval, based on the current geological interpretation.

Early-stage exploration continues in Canada, with framework drilling at the Norris property and additional programs initiated during the quarter, including framework drilling at Authier and a shallow geochemical drilling campaign at LaFlamme.

In South America, early-stage exploration activities continued in Peru and Jamaica. In Peru, work in the Yauri District has advanced several drill-ready targets, with additional geophysical anomalies under evaluation. In Jamaica, exploration is focused on three prioritized camp-scale areas targeting epithermal gold and porphyry copper–gold systems. In Argentina, within the Veladero District, drilling continues at the Porfiada target, where five of seven planned holes have been completed. Hole DDH-POR-07A returned 54.6 meters at 2.03 g/t Au from 163.4 meters, including 11.6 meters at 3.24 g/t Au and 18.0 meters at 3.39 g/t Au, all within oxidized material. The program will continue into Q2 2026, with the objective of defining the extent of mineralization.

In the Africa and Middle East region, the ARK target in Kibali continues to demonstrate strong growth potential through a combination of tighter infill drilling and wider-spaced drill holes stepping out down-plunge. The most recent drill holes intersected the system approximately 600 meters beyond any previous drilling, extending the known plunge extent of the mineralized system to over two kilometers from surface. ARK is emerging as a major discovery within the Kibali Camp, with extensive untested growth potential remaining. Continued delineation and expansion of the deposit will remain a primary focus in the quarters ahead. In the Kingdom of Saudi Arabia, a new, mineralized system has been discovered approximately ten kilometers south of the Jabal Sayid Mine. Drilling is currently underway to evaluate the scale and grade potential of the mineralization.

 

 

 

 

BARRICK FIRST QUARTER 2026   27    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Review of Financial Results

 

 

 

Revenue

 

 ($ millions, except per oz/lb

 data in dollars)

           For the three months
ended
 
      3/31/26      12/31/25      3/31/25  

 Gold

        

 000s oz solda

     748        960        751  

 000s oz produceda

     719        871        758  

 Market price ($/oz)

     4,873        4,135        2,860  

 Realized price ($/oz)b

     4,823        4,177        2,898  

 Revenue

     4,756        5,353        2,766  

 Copper

        

 000s tonnes solda

     45        67        51  

 000s tonnes produceda

     49        62        44  

 Market price ($/lb)

     5.83        5.03        4.24  

 Realized price ($/lb)b

     5.79        5.42        4.51  

 Revenue

     343        514        304  

 Other sales

     119        130        60  

 Total revenue

     5,218        5,997        3,130  

 

a.

On an attributable basis.

 
b.

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

 

Q1 2026 compared to Q4 2025

In Q1 2026, gold revenues on a consolidated basis decreased by 11% compared to Q4 2025, driven by lower sales volumes partially offset by a higher realized gold price1. The average market price for Q1 2026 was $4,873/ oz, representing an all-time high quarterly average and an 18% increase versus the $4,135/oz average in Q4 2025. The realized gold price1 in Q1 2026 was 1% lower than the market gold price due to the realized loss impact of the zero cost collars (refer to note 13 for further details). During Q1 2026, the gold price ranged from $4,099/oz to an all-time nominal high of $5,595/oz, and closed the quarter at $4,608/oz. Gold price volatility in Q1 2026 was driven primarily by economic and geopolitical concerns, in particular the conflict in the Middle East.

In Q1 2026, gold production on an attributable basis (excluding the divested mines) decreased by 13% compared to Q4 2025 mainly as a result of lower grades mined and processed at Nevada Gold Mines and Pueblo Viejo combined with lower grades mined at North Mara and Kibali. This was partially offset by higher production at Loulo-Gounkoto as a result of ramping up of operations during Q1 2026 following resolution of the dispute with the Government of Mali late in Q4 2025.

ATTRIBUTABLE GOLD PRODUCTION VARIANCE (000s oz)

Q1 2026 compared to Q4 2025

 

LOGO

 

  a.

Divested mines refer to the ounces produced by Hemlo and Tongon in Q4 2025.

 

In Q1 2026, copper revenues on a consolidated basis decreased by 33% compared to Q4 2025, primarily due to lower sales volumes compared to Q4 2025, partially offset by a higher realized copper price1. The average market price in Q1 2026 was $5.83/lb, representing an all-time high quarterly average and an increase of 16% from the $5.03/lb average in Q4 2025. The realized copper price1 in Q1 2026 was slightly lower than the market copper price due to the impact of negative provisional pricing adjustments, whereas the realized copper price1 was higher than the market copper price in Q4 2025 due to timing of sales and the impact of positive provisional pricing adjustments. During Q1 2026, the copper price traded in a range of $5.31/lb to an all-time nominal high of $6.59/lb, and closed the quarter at $5.52/lb. Copper prices in Q1 2026 were impacted by concerns about the global economy resulting from global trade disputes, supply disruptions, the conflict in the Middle East, and demand forecasts in China, which is the world’s largest consumer of copper.

Attributable copper production in Q1 2026 was 13 thousand tonnes lower compared to Q4 2025 mainly due to lower throughput at Lumwana resulting from a planned plant shutdown for liner replacements which was successfully completed in February 2026.

Q1 2026 compared to Q1 2025

For Q1 2026, gold revenues on a consolidated basis increased by 72% compared to Q1 2025, primarily due to a higher realized gold price1. The average market price for Q1 2026 was $4,873/oz versus $2,860/oz for Q1 2025.

 

 

 

 

BARRICK FIRST QUARTER 2026   28    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

ATTRIBUTABLE GOLD PRODUCTION VARIANCE (000s oz)

Q1 2026 compared to Q1 2025

 

LOGO

 

a.

Divested mines refer to the ounces produced by Hemlo and Tongon in Q1 2025.

 

For Q1 2026, attributable gold production (excluding the divested mines) was 4% higher than Q1 2025, primarily due to the ramp up of operations at Loulo-Gounkoto following the resolution of the dispute with the Government of Mali that was ultimately resolved in December 2025 and had shutdown the mine in January 2025. This was combined with higher production at Carlin due to improved underground mining and processing performance and Turquoise Ridge due to higher tonnes mined and increased throughput at the Sage autoclave. These impacts were partially offset by lower production from North Mara driven by lower grades processed.

For Q1 2026, copper revenues on a consolidated basis increased by 13% compared to Q1 2025, due to a higher realized copper price1 partially offset by lower sales volumes. In Q1 2026, the realized copper price1 was lower than the market copper price, as discussed above, whereas the realized copper price1 was higher than the market copper price in Q1 2025 due to the impact of positive provisional pricing adjustments.

Attributable copper production for Q1 2026 was 5 thousand tonnes higher than Q1 2025, mainly due to increased throughput and higher grades processed at Lumwana.

Production Costs

 

 ($ millions, except per oz/lb
 data in dollars)
           For the three months
ended
 
       3/31/26      12/31/25      3/31/25  

 Gold

        

Site operating costs

     1,179        1,623        1,097  

Depreciation

     449        503        342  

Royalty expense

     193        229        95  

Mining and production taxes

     46        55        23  

Community relations

     7        13        11  

Cost of sales

     1,874        2,423        1,568  

COS ($/oz)a

     1,922        1,904        1,629  

TCC ($/oz)b

     1,327        1,205        1,220  

AISC ($/oz)b

     1,708        1,581        1,775  

 Copper

        

Site operating costs

     143        154        126  

Depreciation

     43        88        60  

Royalty expense

     30        37        21  

Community relations

     1        2        1  

Cost of sales

     217        281        208  

COS ($/lb)a

     3.41        3.37        2.92  

C1 cash costs ($/lb)b

     2.57        2.45        2.25  

AISC ($/lb)b

     3.67        3.61        3.06  

 

  a.

Gold COS/oz is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share). Copper COS/lb is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share).

 
  b.

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

 

Q1 2026 compared to Q4 2025

In Q1 2026, gold cost of sales on a consolidated basis was 23% lower than Q4 2025, primarily due to lower sales volumes. Our 45% interest in Kibali and 24.5% interest in Porgera are equity accounted, and therefore each mine’s cost of sales is excluded from our consolidated gold cost of sales. Our per ounce metrics, gold COS/oz2 and TCC/oz1, includes our proportionate share of cost of sales at our equity method investees, and were 1% and 10% higher than Q4 2025, mainly due to lower fixed cost dilution driven by lower sales volume combined with higher royalties associated with the higher realized gold price1. The impact on COS/oz2 was partially offset by the fact that Q4 2025 included the impact of the fair value increment on inventory resulting from the purchase price allocation when we regained control of Loulo-Gounkoto and the large one-off shipment of gold inventory that occurred in Q4 2025 following the lifting of the restrictions imposed by the Government of Mali on gold shipments.

In Q1 2026, gold AISC/oz1, which also includes our proportionate share of equity method investees, increased by 8% compared to Q4 2025. This was primarily due to higher TCC/oz1, as explained above.

In Q1 2026, copper cost of sales on a consolidated basis was 23% lower than Q4 2025 primarily due to the impact of lower copper sales volumes. Our 50% interests in Zaldívar and Jabal Sayid are equity accounted and therefore, we do not include their cost of sales in our consolidated copper cost of sales. Our per pound metrics, copper COS/lb2 and C1 cash costs/lb1, include our proportionate share of cost of sales at our equity method

 

 

 

 

BARRICK FIRST QUARTER 2026   29    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

investees. Copper COS/lb2 and C1 cash costs/lb1 were 1% and 5% higher, respectively, compared to Q4 2025, primarily due to higher mining and processing costs at Lumwana.

In Q1 2026, copper AISC/lb1, which also includes our proportionate share of equity method investees, was 2% higher compared to Q4 2025, mainly due to an increase in C1 cash costs/lb1, partially offset by lower minesite sustaining capital expenditures1 .

Q1 2026 compared to Q1 2025

For Q1 2026, gold cost of sales on a consolidated basis was 20% higher than Q1 2025, mainly due to higher depreciation at Carlin, Loulo-Gounkoto and Cortez, combined with higher royalties associated with the higher realized gold price1. As described above, our per ounce metrics, gold COS/oz2 and TCC/oz1, include our proportionate share of cost of sales at our equity method investees, and were 18% and 9% higher, respectively, compared to Q1 2025. This was mainly due to the impact of higher royalties, mining and production taxes (impact approximately $90/oz) associated with the higher realized gold price1. In addition, COS/oz2 was higher due to the inclusion of Loulo-Gounkoto sales at higher costs (as a result of the fair value increment on inventory resulting from the purchase price allocation when we regained control of Loulo-Gounkoto in Q4 2025) whereas in Q1 2025 there were no sales from Loulo-Gounkoto as shipments were restricted.

For Q1 2026, gold AISC/oz1 was 4% lower than Q1 2025, primarily due to lower minesite sustaining capital expenditures1.

For Q1 2026, copper cost of sales on a consolidated basis was 4% higher than Q1 2025, primarily due to higher site operating costs as well as higher royalties associated with the higher realized copper price. As described above, our per pound metrics, copper COS/lb2 and C1 cash costs/lb1, include our proportionate share of cost of sales at our equity method investees. Copper COS/ lb2 and C1 cash costs/lb1 were 17% and 14% higher, respectively, compared to Q1 2025, mainly due to higher payroll costs as well as higher power costs at Lumwana in part due to the strengthening of the local currency.

For Q1 2026, copper AISC/lb1 was 20% higher than Q1 2025, mainly due to higher C1 cash cost/lb1, as well as higher royalties due to the higher realized copper prices1.

General and Administrative Expenses

 ($ millions)           For the three months
ended
 
      3/31/26      12/31/25      3/31/25  
 Corporate administration     24        25        27  
 Share-based compensationa     15        39        15  
 General & administrative expenses     39        64        42  

 

a.

Based on a US$38.16 share price as at March 31, 2026 (December 31, 2025: US$45.76 and March 31, 2025: US$19.04).

 

General and administrative expenses for Q1 2026 decreased compared to Q4 2025 as a result of lower share-based compensation expenses due to the decrease in our share price during the current quarter compared to a significant increase in Q4 2025.

Exploration, Evaluation and Project Expenses

 

 ($ millions)           For the three months
ended
 
      3/31/26      12/31/25      3/31/25  

Global exploration and evaluation

    60        82        27  

 Project costs:

       

Reko Diq

    1        4        3  

IPO costs

    31                

Other

    20        45        19  

Global exploration and evaluation and project expense

    112        131        49  

Minesite exploration and evaluation

    4        8        5  

Total exploration, evaluation and project expenses

    116        139        54  

Exploration, evaluation and project expenses for Q1 2026 decreased by $23 million compared to Q4 2025 driven by lower global exploration and evaluation costs, mainly due to reduced greenfields exploration activity around Reko Diq, and lower project costs as Q4 included legal and consulting costs related to the Hemlo and Tongon divestitures (included in “Other”). These were partially offset by legal and consulting costs related to our North America IPO project in Q1 2026.

Exploration, evaluation and project expenses for Q1 2026 were substantially higher compared to Q1 2025 driven by higher global exploration expense mainly related to the ramp-up of drilling activities at Fourmile as well as higher project costs related to our North American IPO project.

Finance Costs, Net

 

 ($ millions)          For the three months
ended
 
      3/31/26     12/31/25     3/31/25  

Interest expensea

    109       119       98  

Accretion

    20       22       23  

Interest capitalized

    (29     (19     (4

Other finance costs

    1             1  

Finance income

    (62     (58     (56
       

Finance costs, net

    39       64       62  

 

  a.

For Q1 2026, interest expense includes $7 million, of non-cash interest expense relating to the Pueblo Viejo streaming agreement with Royal Gold Inc. (Q4 2025: $nil; Q1 2025: $8 million). Interest expense also includes $8 million, relating to finance costs in Argentina (Q4 2025: $1 million; Q1 2025: $4 million).

In Q1 2026, finance costs, net decreased compared to Q4 2025 and Q1 2025 primarily due to higher interest capitalized in Q1 2026 and higher finance costs in Argentina associated with cash repatriation in Q4 2025 and Q1 2025 .

 

 

 

 

BARRICK FIRST QUARTER 2026   30    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Additional Statement of Income Items

 

 ($ millions)          For the three months
ended
 
      3/31/26     12/31/25     3/31/25  

Impairment charges

    0       5       4  

(Gain) loss on currency translation

    20       6       2  

Closed mine rehabilitation

    (3     (7     19  

Other (income) expense

    (4     (839     170  

Other (Income) Expense

Other income in Q1 2026 of $4 million was mainly related to the revaluation of the Hemlo contingent consideration, which was partially offset by a loss on the revaluation of our Kibali JV receivable. This compares to other income of $839 million in Q4 2025 which mainly related to the gain on the sale of non-current assets totaling $732 million, comprised of our Hemlo gold mine ($545 million), our interest in the Tongon gold mine ($134 million) and the Alturas project ($53 million). This was combined with the accounting impact of regaining control of the Loulo-Gounkoto complex on December 16, 2025, partially offset by the settlement payment of $253 million to the Government of Mali in November 2025. Other expense in Q1 2025 of $170 million was mainly related to the signing of agreements to settle legacy legal matters in the Philippines related to Placer Dome Inc., combined with reduced operations costs at Loulo-Gounkoto.

For a further breakdown of other expense, refer to note 9 to the Financial Statements.

Income Tax Expense

Income tax expense was $747 million in Q1 2026. The unadjusted effective income tax rate in Q1 2026 was 23% of income before income taxes.

The underlying effective income tax rate on ordinary income in Q1 2026 was 22% after adjusting for the impact of foreign currency translation losses on current and deferred tax balances; the impact of updates to the rehabilitation provision for our non-operating mines; the impact of non-deductible foreign exchange losses; the impact of the remeasurement of the Hemlo contingent consideration; the impact of Loulo-Gounkoto; and the impact of other expense adjustments.

We record deferred tax charges or credits if changes in facts or circumstances affect the estimated tax basis of assets and therefore, the expectations of our ability to realize deferred tax assets. The interpretation of tax regulations and legislation as well as their application to our business is complex and subject to change. We also have significant amounts of unrecognized deferred tax assets (e.g. for tax losses in Canada). Potential changes in any of these amounts, as well as our ability to realize deferred tax assets, could significantly affect net income or cash flow in future periods. For further details on income tax expense, refer to note 10 of the Financial Statements.

Withholding Taxes

In Q1 2026, we recorded $39 million of dividend withholding taxes related to the distributed earnings of our subsidiaries in Argentina, and undistributed earnings of our subsidiaries in Saudi Arabia and the United States.

OECD Pillar Two model rules

We have applied the exception available under the amendments to IAS 12 published by the IASB in May 2023 and are not recognizing or disclosing information about deferred tax assets and liabilities related to Pillar Two income taxes. Our review of Pillar Two for the current year, based on the OECD’s Transitional Safe Harbour rules as implemented in the Global Minimum Tax Act in Canada, has not identified any material amounts to be accrued for Q1 2026. As the law is evolving, both in Canada and elsewhere, we will continue to monitor the impact of this legislation.

 

 

 

 

BARRICK FIRST QUARTER 2026   31    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Financial Condition Review

 

 

Summary Balance Sheet and Key Financial Ratios

 

  ($ millions, except ratios and share amounts)        As at 3/31/26         As at 12/31/25  

Total cash and equivalents

     7,131       6,706  

Current assets

     3,482       3,511  

Non-current assets

     41,970       41,360  

Total Assets

     52,583       51,577  

Current liabilities excluding short-term debt

     3,403       3,441  

Non-current liabilities excluding long-term debta

     7,681       7,517  

Debt (current and long-term)

     4,726       4,703  

Total Liabilities

     15,810       15,661  

Total shareholders’ equity

     27,339       26,557  

Non-controlling interests

     9,434       9,359  

Total Equity

     36,773       35,916  

Total common shares outstanding (millions of shares)b

     1,676       1,675  

Debt, net of cash

     (2,405     (2,003

Key Financial Ratios:

                

   Current ratioc

     3.06:1       2.92:1  

   Debt-to-equityd

     0.13:1       0.13:1  

   Net leveragee

     -0.2:1       -0.2:1  

 

  a. 

Non-current financial liabilities as at March 31, 2026 were $5,761 million (December 31, 2025: $5,684 million).

  b. 

As of April 28, 2026, the number of common shares outstanding is 1,675,508,360.

  c.

Represents current assets divided by current liabilities (including short-term debt) as at March 31, 2026 and December 31, 2025.

  d. 

Represents debt divided by total shareholders’ equity (including minority interest) as at March 31, 2026 and December 31, 2025.

  e. 

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

 

Balance Sheet Review

Total assets were $52.6 billion as at March 31, 2026, slightly higher than total assets as at December 31, 2025.

Our asset base is primarily comprised of non-current assets such as property, plant and equipment and equity method investments, reflecting the capital-intensive nature of the mining business and our history of growing through acquisitions and creation of joint ventures with other mining companies. Other significant assets include production inventories, indirect taxes recoverable and receivable, concentrate sales receivable, other government and joint venture related receivables, as well as cash and equivalents.

Total liabilities as at March 31, 2026 were $15.8 billion, in line with total liabilities at December 31, 2025. Our liabilities are primarily comprised of debt, other non-current liabilities (such as provisions and deferred income tax liabilities), and accounts payable.

Financial Position and Liquidity

We believe we have sufficient financial resources to meet our business requirements for the foreseeable future, including capital expenditures, working capital requirements, interest payments, environmental rehabilitation, securities buybacks and dividends.

Total cash and cash equivalents as at March 31, 2026 were $7.1 billion. Our capital structure comprises a mix of debt, non-controlling interest (primarily at NGM) and shareholders’ equity. As at March 31, 2026, our total debt was $4.7 billion (cash and equivalents, net of debt was $2,405 million) and our debt-to-equity ratio was 0.13:1. This compares to total debt as at December 31, 2025 of $4.7 billion (debt, net of cash and equivalents was $2,003 million), and a debt-to-equity ratio of 0.13:1.

Uses of cash for the remainder of 2026 include capital commitments of $1,426 million, and we expect to

incur attributable minesite sustaining1 and project capital expenditures1 of approximately $3,250 to $3,700 million during the remainder of the year, based on our annual guidance range on page 9. Included in that remaining capital expenditure amount is approximately $480 to $580 million related to Reko Diq, which as noted on page 26, is currently under review. For the remainder of 2026, we have contractual obligations and commitments of $1,145 million for supplies and consumables. In addition, we have $265 million in interest payments and other amounts as detailed in the table on page 34. At the May 8, 2026 meeting, the Board of Directors authorized a new share buyback program, where we may purchase up to $3 billion of Barrick shares over the next 12 months. We expect to fund these commitments through operating cash flow, which is our primary source of liquidity, as well as our existing cash balances as necessary.

The Company’s dividend policy targets a total payout of 50% of attributable free cash flow on an annualized basis, comprised of a fixed base quarterly dividend of $0.175 per share and a performance top-up component at each year end based on the attributable free cash flow during the year. The dividend paid in any given year may be higher or lower than the 50% target based on the strength of cash flow, capital needs, balance sheet considerations, and other factors.

The declaration and payment of dividends is at the discretion of the Board of Directors, and will depend on the Company’s financial results, cash requirements, future prospects, the number of outstanding common shares, and other factors deemed relevant by the Board.

Our operating cash flow is dependent on the ability of our operations to deliver projected future cash flows. The sale of the gold and copper we produce and market price of gold and to a lesser extent, copper, are the primary drivers of our operating cash flow. Other options to enhance

 

 

 

 

BARRICK FIRST QUARTER 2026   32    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

liquidity include portfolio optimization; issuance of equity or long-term debt securities in the public markets or to private investors (Moody’s and S&P currently rate Barrick’s outstanding long-term debt as investment grade, with ratings of A3 and BBB+, respectively); and drawing on the $3.0 billion available under our undrawn Credit Facility (subject to compliance with covenants and the making of certain representations and warranties, this facility is available for drawdown as a source of financing). In May 2025, we completed an update to our undrawn $3.0 billion revolving credit facility, including an extension of the termination date by one year to May 2030. The revolving Credit Facility incorporates sustainability-linked metrics and are made up of annual environmental and social performance targets directly influenced by Barrick’s actions, rather than based on external ratings. The performance targets include Scope 1 and Scope 2 GHG emissions intensity, water use efficiency (reuse and recycling rates), and TRIFR3. Barrick may incur positive or negative pricing adjustments on drawn credit spreads and standby fees based on its sustainability performance versus the targets that have been set. The key financial covenant in our undrawn Credit Facility requires Barrick to maintain a net debt to total capitalization ratio of less than 0.60:1. Barrick’s net debt to total capitalization ratio was negative 0.07:1 as at March 31, 2026 (negative 0.06:1 as at December 31, 2025).

Summary of Cash Inflow (Outflow)

 

  ($ millions)   

For the three
months ended

 
      3/31/26     12/31/25     3/31/25  

Net cash provided by operating activities

     2,554       2,726       1,212  

Investing activities

      

Capital expenditures

     (979     (1,107     (837

Divestitures

     (4     1,163       0  

Income taxes paid on divestitures

     0       (44     0  

Funding of equity method investments

     0       0       0  

Dividends received from equity method investments

     110       100       38  

Shareholder loan repayments from equity method investments

     147       121       60  

Investment sales

     110       43       0  

Other

     2       2       0  

Total investing inflows/(outflows)

     (614     278       (739

Net change in debta

     (5     (4     (3

Dividendsb

     (697     (294     (172

Net disbursements to non-controlling interests

     (804     (570     (125

Share buyback program

     0       (500     (143

Other

     (9     0       4  

Total financing outflows

     (1,515     (1,368     (439

Effect of exchange rate

     0       1       0  

Increase in cash and equivalents

     425       1,637       34  

 

a. 

The difference between the net change in debt on a cash basis and the net change on the balance sheet is due to changes in non-cash charges, specifically the unwinding of discounts and amortization of debt issue costs.

 
b. 

For Q1 2026, we declared and paid dividends per share in US dollars totaling $0.42 (Q4 2025: declared and paid $0.175; Q1 2025: declared and paid $0.10).

 

Q1 2026 compared to Q4 2025

In Q1 2026, we generated $2,554 million in operating cash flow, compared to $2,726 million in Q4 2025. The decrease of $172 million was primarily due to lower gold sales this quarter combined with higher gold TCC/oz1 partially offset by a higher realized gold price1. Operating cash flow was further impacted by an unfavorable movement in working capital, primarily in accounts payable which decreased as a result of the payment of supplier balances at Loulo-Gounkoto as operations ramped up in Q1 2026. These results were positively impacted by a decrease in cash taxes paid and lower interest paid as a result of the timing of semi-annual interest payments on our bonds, which primarily occur in the second and fourth quarters.

Cash outflows from investing activities in Q1 2026 were $614 million, compared to cash inflows of $278 million in Q4 2025. The decreased outflow of $892 million was primarily due to proceeds from the sales of the Hemlo gold mine, our interest in the Tongon gold mine and the Alturas project which were received in Q4 2025. Capital expenditures in Q1 2026 were lower than Q4 2025, primarily at Lumwana which had a high Q4 outflow for mining fleet down payments and a large rebuild spend in preparation for Q1 change outs, combined with lower capitalized waste stripping in Q1 2026.

Net financing cash outflows for Q1 2026 amounted to $1,515 million, compared to $1,368 million in Q4 2025. The increase of $147 million is primarily due to higher net disbursements paid to non-controlling interests, primarily to Newmont in relation to their interest in NGM, and higher dividends paid in Q1 2026 as a result of our new dividend policy. These were partially offset by a lack of share repurchases in the current period as the Share Buyback Plan was not renewed in Q1 2026.

Q1 2026 compared to Q1 2025

In Q1 2026, we generated $2,554 million in operating cash flow, compared to $1,212 million in Q1 2025. The increase of $1,342 million was primarily due to higher realized gold prices1, partially offset by higher gold TCC/oz1. Operating cash flow was further impacted by an unfavorable movement in working capital, mainly in accounts payable which decreased as a result of the payment of supplier balances at Loulo-Gounkoto as operations ramped up in Q1 2026, as well as higher cash taxes paid this quarter.

Cash outflows from investing activities in Q1 2026 were $614 million compared to $739 million in Q1 2025. The decrease of $125 million was primarily due to higher dividends and shareholder loan repayments received from equity investees combined with investment sales proceeds this quarter. These were partially offset by higher capital expenditures driven by increased project capital expenditures1, mainly at Reko Diq and at Lumwana, partially offset by decreased minesite sustaining capital expenditures1 mainly at Carlin driven by purchases of the Komatsu-930 truck fleet occurring in Q1 2025.

Net financing cash outflows for Q1 2026 amounted to $1,515 million compared to $439 million in Q1 2025. The increase of $1,076 million is primarily due to higher net disbursements paid to non-controlling interests, primarily to Newmont in relation to their interest in NGM, and higher dividends paid in Q1 2026 as a result of our new dividend policy. These were partially offset by a lack of share repurchases in the current period as the Share Buyback Plan was not renewed in Q1 2026.

 

 

 

 

BARRICK FIRST QUARTER 2026   33    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Commitments and Contingencies

 

 

 

Litigation and Claims

We are currently subject to various litigation proceedings as disclosed in note 17 to the Financial Statements, and we may be involved in disputes with other parties in the future that may result in litigation. If we are unable to resolve these disputes favorably, it may have a material adverse impact on our financial condition, cash flow and results of operations.

Contractual Obligations and Commitments

In the normal course of business, we enter into contracts that give rise to commitments for future minimum payments. The following table summarizes the remaining contractual maturities of our financial liabilities and operating and capital commitments shown on an undiscounted basis:

 

 

  ($ millions)   

Payments due as at 3/31/26

 
   2026        2027        2028        2029        2030      2031 and
thereafter
       Total  

 Debta

                    

   Repayment of principal

     47        0        0        0        0        4,630        4,677  

   Capital leases

     9        14        8        5        4        29        69  

   Interest

     265        280        279        278        278        2,381        3,761  

 Provisions for environmental rehabilitationb

     140        121        86        82        68        1,912        2,409  

 Restricted share units

     26        32        4        0        0        0        62  

 Pension benefits and other post-retirement benefits

     4        5        5        4        4        72        94  

 Purchase obligations for supplies and consumablesc

     1,145        303        200        151        142        1,888        3,829  

 Capital commitmentsd

     1,426        351        208        45        0        0        2,030  

 Social development costse

     69        29        16        8        4        55        181  

 Other obligationsf

     294        107        61        67        64        496        1,089  

 Total

     3,425        1,242        867        640        564        11,463        18,201  

 

a. 

Debt and Interest: Our debt obligations do not include any subjective acceleration clauses or other clauses that enable the holder of the debt to call for early repayment, except in the event that we breach any of the terms and conditions of the debt or for other customary events of default. We are not required to post any collateral under any debt obligations. Projected interest payments on variable rate debt were based on interest rates in effect at March 31, 2026. Interest is calculated on our long-term debt obligations using both fixed and variable rates.

b. 

Provisions for environmental rehabilitation: Amounts presented in the table represent the undiscounted uninflated future payments for the expected cost of environmental rehabilitation.

c. 

Purchase obligations for supplies and consumables: Includes commitments related to new purchase obligations to secure a supply of acid, tires and cyanide for our production process.

d. 

Capital commitments: Purchase obligations for capital expenditures include only those items where binding commitments have been entered into.

e. 

Social development costs: Includes a commitment of $14 million in 2031 and thereafter, related to the funding of a power transmission line in Argentina.

f.

Other obligations includes the Pueblo Viejo joint venture partner shareholder loan, the deposit on the Pascua-Lama silver sale agreement with Wheaton Precious Metals Corp. due in 2039, the settlement of Writ of Kalikasan, and the royalties, penalties and applicable interest on the amounts payable to the Government of Mali for the application of the 2023 Mining Code.

 

 

 

BARRICK FIRST QUARTER 2026   34    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Review of Quarterly Results

 

 

Quarterly Informationa

 

  ($ millions, except where indicated)    2026        2025        2025        2025        2025        2024        2024        2024  
      Q1      Q4      Q3      Q2      Q1      Q4      Q3      Q2  

 Revenues

     5,218        5,997        4,148        3,681        3,130        3,645        3,368        3,162  

 Realized price/oz – goldb

     4,823        4,177        3,457        3,295        2,898        2,657        2,494        2,344  

 Realized price/lb – copperb

     5.79        5.42        4.39        4.36        4.51        3.96        4.27        4.53  

 Cost of sales

     2,099        2,712        1,890        1,878        1,785        1,995        2,051        1,979  

 Net earnings

     1,602        2,406        1,302        811        474        996        483        370  

  Per share (dollars)c

     0.96        1.43        0.76        0.47        0.27        0.57        0.28        0.21  

 Adjusted net earningsb

     1,648        1,754        982        800        603        794        529        557  

  Per share (dollars)b,c

     0.98        1.04        0.58        0.47        0.35        0.46        0.30        0.32  

 Operating cash flow

     2,554        2,726        2,422        1,329        1,212        1,392        1,180        1,159  

 Consolidated capital expendituresd

     979        1,107        943        934        837        891        736        819  

 Free cash flowb

     1,575        1,619        1,479        395        375        501        444        340  

 Attributable free cash flowb

     1,213        1,060        1,154        212        411        505        304        285  

 

a. 

Sum of all the quarters may not add up to the annual total due to rounding.

b. 

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

c.

Calculated using weighted average number of shares outstanding under the basic method of earnings per share.

d.

Amounts presented on a consolidated cash basis.

 

Our recent financial results reflect our emphasis on cost discipline, an agile management structure that empowers our site based leadership teams and a portfolio of Tier One Gold Assets5. This, combined with the significant increase in the gold price and ongoing strength in the copper price, has resulted in strong cash flows over the past several quarters delivering record high operating and free cash flow in Q4 2025. The positive operating cash flow generated has allowed us to continue to reinvest in our business including our key growth projects, maintain a strong balance sheet and increase returns to shareholders.

In addition to the strength in metal prices, net earnings has also been impacted by the following items in each quarter, which have been excluded from adjusted net earnings1. In 2025, we recorded a net loss of $625 million on the deconsolidation of Loulo-Gounkoto following the change of control after it was placed under a temporary provisional administration on June 16, 2025 and subsequent accounting impact of regaining control on

December 16, 2025, which impacted Q2, Q3 and Q4 of 2025. In addition, in Q4 2025, we recorded a gain on the sale of our Hemlo gold mine ($545 million), our interest in the Tongon gold mine ($134 million) and the Alturas project ($53 million). In Q2 2025, we recorded a net loss of $1,035 million on the deconsolidation of Loulo-Gounkoto following the change of control after it was placed under a temporary provisional administration on June 16, 2025 (refer to note 17 of the Financial Statements for further details), which was partially offset by the recognition of our 80% equity investment in Loulo-Gounkoto. In addition, we recorded a gain of $745 million on the sale of our 50% interest in the Donlin Gold project. In Q4 2024, we recorded non-current asset impairment reversals of $655 million at Lumwana and $437 million at Veladero. In addition, we recorded a goodwill impairment of $484 million related to Loulo-Gounkoto. In Q2 2024, we recorded a provision following the settlement of the Zaldívar Tax Assessments in Chile (refer to note 17 of the Financial Statements).

 

 

Internal Control Over Financial Reporting and Disclosure Controls and Procedures

 

 

Management is responsible for establishing and maintaining adequate internal control over financial reporting and disclosure controls and procedures as defined in our 2025 annual MD&A.

Together, the internal control frameworks provide internal control over financial reporting and disclosure. Due to its inherent limitations, internal control over financial reporting and disclosure may not prevent or detect all misstatements. Further, the effectiveness of internal control is subject to the risk that controls may become inadequate because of changes in conditions, or that the degree of compliance with policies or procedures may change.

There were no changes in our internal controls over financial reporting during the three months ended March 31, 2026 that have materially affected, or are reasonably likely to materially affect, our internal controls over financial reporting.

Under the supervision and with the participation of management, including the President and Chief Executive Officer, and Senior Executive Vice-President, Chief Financial Officer, management will continue to monitor and evaluate the design and effectiveness of its internal control over financial reporting and disclosure controls and procedures, and may make modifications from time to time as considered necessary.

 

 

 

 

BARRICK FIRST QUARTER 2026   35    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

IFRS Critical Accounting Policies and Accounting Estimates

 

 

 

Management has discussed the development and selection of our critical accounting estimates with the Audit & Risk Committee of the Board of Directors, and the Audit & Risk Committee has reviewed the disclosure relating to such estimates in conjunction with its review of this MD&A. The accounting policies and methods we utilize determine how we report our financial condition and results of operations, and they may require management to make estimates or rely on assumptions about matters that are inherently uncertain. The consolidated financial statements have been prepared in accordance with IFRS. Our material accounting policies are disclosed in note 2 of the Financial Statements, including a summary of current and future changes in accounting policies.

Critical Accounting Estimates and Judgments

Certain accounting estimates have been identified as being “critical” to the presentation of our financial condition and results of operations because they require us to make subjective and/or complex judgments about matters that are inherently uncertain; or there is a reasonable likelihood that materially different amounts could be reported under different conditions or using different assumptions and estimates. Our significant accounting judgments, estimates and assumptions, including our assessment of the impacts following the loss of control of our Loulo-Gounkoto mine, are disclosed in note 3 of the accompanying Financial Statements.

 

 

Non-GAAP Financial Measures

 

 

 

Adjusted Net Earnings and Adjusted Net Earnings per Share

Adjusted net earnings is a non-GAAP financial measure which excludes the following from net earnings:

   

Impairment charges (reversals) related to intangibles, goodwill, property, plant and equipment, and investments;

 
   

Acquisition/disposition gains/losses;

 
   

Foreign currency translation gains/losses;

 
   

Significant tax adjustments;

 
   

Other items that are not indicative of the underlying operating performance of our core mining business; and

 
   

Tax effect and non-controlling interest of the above items.

 

Management uses this measure internally to evaluate our underlying operating performance for the reporting periods presented and to assist with the planning and forecasting of future operating results. Management believes that adjusted net earnings is a useful measure of our performance because impairment charges, acquisition/disposition gains/losses and significant tax adjustments do not reflect the underlying operating performance of our core mining business and are not necessarily indicative of future operating results. Furthermore, foreign currency translation gains/losses are not necessarily reflective of the underlying operating results for the reporting periods presented. The tax effect and non-controlling interest of the adjusting items are also excluded to reconcile the amounts to Barrick’s share on a post-tax basis, consistent with net earnings.

As noted, we use this measure for internal purposes. Management’s internal budgets and forecasts and public guidance do not reflect the types of items we adjust for. Consequently, the presentation of adjusted net earnings enables investors and analysts to better understand the underlying operating performance of our core mining business through the eyes of management. Management periodically evaluates the components of adjusted net earnings based on an internal assessment of performance measures that are useful for evaluating the operating performance of our business segments and a review of the non-GAAP financial measures used by mining industry analysts and other mining companies.

Adjusted net earnings is intended to provide additional information only and does not have any standardized definition under IFRS and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. The measures are not necessarily indicative of operating profit or cash flow from operations as determined under IFRS. Other companies may calculate these measures differently. The following table reconciles these non-GAAP financial measures to the most directly comparable IFRS measure.

 

 

 

 

BARRICK FIRST QUARTER 2026   36    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Reconciliation of Net Earnings to Net Earnings per Share, Adjusted Net Earnings and Adjusted Net Earnings per Share

 

 ($ millions, except per share amounts in dollars)    For the three months ended  
         3/31/26        12/31/25        3/31/25  

Net earnings attributable to equity holders of the Company

     1,602        2,406        474  

Impairment charges related to intangibles, goodwill, property, plant and equipment, and investmentsa

     0        5        4  

Acquisition/disposition (gains) lossesb

     1        (1,146      0  

(Gain) loss on currency translation

     20        6        2  

Significant tax adjustmentsc

     35        80        (15

Other expense adjustmentsd

     18        559        173  

Non-controlling interest

     (8      (101      (11

Tax effecte

     (20      (55      (24

Adjusted net earnings

     1,648        1,754        603  

Net earnings per sharef

     0.96        1.43        0.27  

Adjusted net earnings per sharef

     0.98        1.04        0.35  

 

a.

There were no significant impairment charges or reversals in the current period or prior periods.

 

b. 

Acquisition/disposition gains for Q4 2025 relate to gain on sale of our Hemlo gold mine, our interest in the Tongon gold mine and the Alturas project. Q4 2025 was further impacted by the accounting impact of regaining control of the Loulo-Gounkoto complex on December 16, 2025.

 

c.

For Q1 2026, significant tax adjustments include the re-measurement of current and deferred tax balances and the impact of uncertain tax positions. For Q4 2025, significant tax adjustments include the resolution of uncertain tax positions, the impact of prior year adjustments and the recognition of deferred tax assets. Significant tax adjustments for Q1 2025 include the re-measurement of deferred tax balances.

 

d.

Other expense for Q1 2026 period mainly related to the fair value increment on inventory resulting from the purchase price allocation when we regained control of Loulo-Gounkoto, reduced operations costs at Mali, legal and consulting costs related to our North America IPO project and revaluation of contingent consideration for Hemlo. Other expense for 2025 periods mainly related to the reduced operations costs relating to Mali in Q1 2025, the settlement payment to the Government of Mali in November 2025, the fair value increment on inventory resulting from the purchase price allocation when we regained control of Loulo- Gounkoto and severance costs incurred

 

e. 

Tax effect for Q1 2026 mainly relates to other expense adjustments, Q4 2025 primarily relates to acquisition/disposition losses (gains) and Q1 2025 primarily relates to other expense adjustments

 

f.

Calculated using weighted average number of shares outstanding under the basic method of earnings per share.

Free Cash Flow, Attributable Free Cash Flow and Attributable Operating Cash Flow

Free cash flow is a non-GAAP financial measure that deducts capital expenditures from net cash provided by operating activities. Attributable free cash flow starts with free cash flow and adds our attributable share of free cash flow from our equity investees and subtracts the free cash flow attributable to the non-controlling interests. Management believes these to be useful indicators of our ability to operate without reliance on additional borrowing or usage of existing cash.

Starting with this MD&A, we are presenting attributable operating cash flow. Attributable operating cash flow starts with cash provided by operating activities and adds our attributable share of cash provided by operating activities from our equity investees and subtracts the cash provided by operating activities attributable to the non-

controlling interests. Management believes this to be useful indicator of the amount of cash provided by operating activities to Barrick’s ownership share.

Free cash flow, attributable free cash flow and attributable operating cash flow are intended to provide additional information only and do not have any standardized definition under IFRS and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. These measures are not necessarily indicative of operating profit or cash flow from operations as determined under IFRS. Other companies may calculate these measures differently. The following table reconciles these non-GAAP financial measures to the most directly comparable IFRS measure.

 

 

Reconciliation of Net Cash Provided by Operating Activities to Free Cash Flow, Attributable Free Cash Flow and Attributable Operating Cash Flow

 

 ($ millions)    For the three months ended  
        3/31/26     12/31/25     3/31/25  

Net cash provided by operating activities

     2,554       2,726       1,212  

Capital expenditures

     (979     (1,107     (837

Free cash flow (consolidated)

     1,575       1,619       375  

Free cash flow applicable to equity investees

     330       172       156  

Non-controlling interests

     (692     (731     (120

Attributable free cash flow

     1,213       1,060       411  

Attributable capital expenditures

     755       906       631  

Attributable operating cash flow

     1,968       1,966       1,042  

Capital Expenditures

Capital expenditures are classified into minesite sustaining capital expenditures or project capital expenditures depending on the nature of the expenditure. Minesite sustaining capital expenditures is the capital spending

required to support current production levels. Project capital expenditures represent the capital spending at new projects and major, discrete projects at existing operations intended to increase net present value through higher

 

 

 

 

BARRICK FIRST QUARTER 2026   37    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

production or longer mine life. Management believes this to be a useful indicator of the purpose of capital expenditures and this distinction is an input into the calculation of all-in sustaining costs per ounce/pound.

Classifying capital expenditures is intended to provide additional information only and does not have any

standardized definition under IFRS, and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. Other companies may calculate these measures differently. The following table reconciles these non-GAAP financial measures to the most directly comparable IFRS measure.

 

 

Reconciliation of the Classification of Capital Expenditures

 

 ($ millions)    For the three months ended  
        3/31/26      12/31/25      3/31/25  

Minesite sustaining capital expenditures

     380        458        564  

Project capital expenditures

     570        630        269  

Capitalized interest

     29        19        4  

Total consolidated capital expenditures

     979        1,107        837  

Total cash costs per ounce, All-in sustaining costs per ounce, C1 cash costs per pound and All-in sustaining costs per pound

TCC/oz and AISC/oz are non-GAAP financial measures which are calculated based on the definition published by the WGC (a market development organization for the gold industry comprised of and funded by gold mining companies from around the world, including Barrick). The WGC is not a regulatory organization. Management uses these measures to monitor the performance of our gold mining operations and their ability to generate positive cash flow, both on an individual site basis and an overall gold operations basis.

TCC/oz starts with our cost of sales related to gold production and removes depreciation, the non-controlling interest of cost of sales and costs allocated to by-products. AISC/oz starts with TCC/oz and includes sustaining capital expenditures, sustaining leases, general and administrative costs, minesite exploration and evaluation costs related to the current mine plan and reclamation cost accretion and amortization. These additional costs reflect the expenditures made to maintain current production levels.

We believe that our use of TCC/oz and AISC/oz will assist analysts, investors and other stakeholders of Barrick in understanding the costs associated with producing gold, understanding the economics of gold mining, assessing our operating performance and also our ability to generate free cash flow from the gold operations portion of our business. Due to the capital-intensive nature of the industry and the long useful lives over which these items are depreciated, there can be a significant timing difference between net earnings calculated in accordance with IFRS and the amount of free cash flow that is being generated by a mine and therefore we believe these measures are useful non-GAAP operating metrics and supplement our IFRS disclosures. These measures are not

representative of all of our cash expenditures as they do not include income tax payments, interest costs or dividend payments. These measures do not include depreciation or amortization.

TCC/oz and AISC/oz are intended to provide additional information only and do not have standardized definitions under IFRS and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. These measures are not equivalent to net income or cash flow from operations as determined under IFRS. Although the WGC has published a standardized definition, other companies may calculate these measures differently.

C1 cash costs/lb and AISC/lb are non-GAAP financial measures related to our copper mine operations. We believe that C1 cash costs/lb enables investors to better understand the performance of our copper operations in comparison to other copper producers who present results on a similar basis. C1 cash costs/lb excludes royalties and production taxes and non-routine charges as they are not direct production costs. AISC/lb is similar to the gold AISC metric and management uses this to better evaluate the costs of copper production. We believe this measure enables investors to better understand the operating performance of the copper portion of our business as this measure reflects all of the sustaining expenditures incurred in order to produce copper. AISC/lb includes C1 cash costs, sustaining capital expenditures, sustaining leases, general and administrative costs, minesite exploration and evaluation costs, royalties and production taxes, reclamation cost accretion and amortization and write-downs taken on inventory to net realizable value.

 

 

 

 

BARRICK FIRST QUARTER 2026   38    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Reconciliation of Gold Cost of Sales to Total cash costs and All-in sustaining costs, including on a per ounce basis

 

 ($ millions, except per oz information in dollars)         For the three months ended  
         
      Footnote      3/31/26     12/31/25     3/31/25  

COS applicable to gold production

        1,874       2,423       1,568  

Depreciation

        (449     (503     (342

Total cash costs applicable to equity method investments

        128       111       109  

Costs allocated to by-products

        (119     (130     (60

Other

   a      (33     (258     5  

Non-controlling interests

   b      (409     (487     (364
         

Total cash costs

          992       1,156       916  

General & administrative costs

        39       64       42  

Minesite exploration and evaluation costs

   c      4       8       5  

Minesite sustaining capital expenditures

   d      380       458       564  

Sustaining leases

        6       4       8  

Rehabilitation - accretion and amortization (operating sites)

   e      16       16       17  

Non-controlling interest, copper operations and other

   f      (159     (191     (217
 All-in sustaining costs           1,278       1,515       1,335  
 Ounces sold - attributable basis (koz)    g      748       960       751  
 COS/oz    h,i      1,922       1,904       1,629  
 TCC/oz    i      1,327       1,205       1,220  
 AISC/oz    i      1,708       1,581       1,775  

 

a. 

  Other - Other adjustments mainly relate to treatment and refining charges.

b.

  Non-controlling interests - Non-controlling interests include non-controlling interests related to gold production of $600 million for Q1 2026, (Q4 2025: $741 million; Q1 2025: $487 million). Non-controlling interests include NGM, Pueblo Viejo, Loulo-Gounkoto, Tongon, North Mara and Bulyanhulu. Refer to Note 5 to the Financial Statements for further information.

c.

  Exploration and evaluation costs - Exploration, evaluation and project expenses are included in AISC if they support current mine operations.

d.

  Capital expenditures - Capital expenditures are related to our gold sites only and are split between minesite sustaining and project capital expenditures.

e.

  Rehabilitation - accretion and amortization - Includes depreciation on the assets related to rehabilitation provisions of our gold operations and accretion on the rehabilitation provision of our gold operations, split between operating and non-operating sites.

f.

  Non-controlling interest and copper operations - Removes general and administrative costs related to non-controlling interests and copper based on a percentage allocation of revenue. Also removes exploration, evaluation and project expenses, rehabilitation costs and capital expenditures incurred by our copper sites and the non-controlling interest of NGM, Pueblo Viejo, Loulo-Gounkoto, Tongon, North Mara and Bulyanhulu operating segments. It also includes capital expenditures applicable to our equity method investment in Kibali. The impact is summarized as the following:

 

 ($ millions)            For the three months ended  

Non-controlling interest, copper operations and other

        3/31/26        12/31/25        3/31/25  

General & administrative costs

     (6      (10      (6

Minesite exploration and evaluation expenses

     (1      (3      0  

Rehabilitation - accretion and amortization (operating sites)

     (5      (5      (5

Minesite sustaining capital expenditures

     (147      (173      (206
       

All-in sustaining costs total

     (159      (191      (217

 

   

g. 

  Ounces sold - attributable basis - Excludes Long Canyon which is producing residual ounces from the leach pad while in care and maintenance.

h.

  COS/oz - Gold COS/oz is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share).

i.

  Per ounce figures - COS/oz, TCC/oz and AISC/oz may not calculate based on amounts presented in this table due to rounding.

 

 

 

BARRICK FIRST QUARTER 2026   39    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Reconciliation of Gold Cost of Sales to Total cash costs and All-in sustaining costs, including on a per ounce basis, by operating segment

 

 ($ millions, except per oz information in dollars)            For the three months ended 3/31/26  
      Footnote    Carlin     Cortez     Turquoise
Ridge
    Phoenix     Nevada Gold
Minesa
    Pueblo
Viejo
 

 COS applicable to gold production

        505       312       207       89       1,113       233  

Depreciation

        (125     (81     (46     (15     (267     (67

Costs allocated to by-products

        (10     (3     (3     (61     (77     (29

Other

   c      (1     0       0       8       7       0  

Non-controlling interests

        (142     (88     (61     (8     (299     (54
               

 Total cash costs

          227       140       97       13       477       83  

General & administrative costs

        0       0       0       0       0       0  

Minesite exploration and evaluation costs

   d      1       0       0       1       2       0  

Minesite sustaining capital expenditures

   e      142       52       21       8       228       58  

Sustaining capital leases

        0       0       0       0       0       0  

Rehabilitation - accretion and amortization (operating sites)

   f      3       4       1       1       9       2  

Non-controlling interests

        (56     (22     (8     (4     (92     (24
               

 All-in sustaining costs

          317       174       111       19       624       119  
               

 Ounces sold - attributable basis (000s ounces)

          173       89       96       22       380       82  

 COS/oz

   g,h      1,794       2,149       1,327       2,485       1,800       1,702  

 TCC/oz

   h      1,315       1,569       1,011       574       1,255       1,019  

 AISC/oz

   h      1,838       1,957       1,153       862       1,645       1,457  
 ($ millions, except per oz information in dollars)                               For the three months ended 3/31/26  
      Footnote    Veladero     Porgera     Loulo-
Gounkotoi
    Kibali    

North

Mara

    Bulyanhulu  

 COS applicable to gold production

        98       36       241       132       99       86  

Depreciation

        (36     (7     (38     (33     (21     (18

Costs allocated to by-products

        (6     0       0       (1     (2     (10

Other

   c      0       0       (38     0       0       1  

Non-controlling interests

          0       0       (33     0       (12     (9

 Total cash costs

        56       29       132       98       64       50  
               

General & administrative costs

        0       0       0       0       0       0  

Minesite exploration and evaluation costs

   d      0       1       0       0       0       0  

Minesite sustaining capital expenditures

   e      11       8       0       11       9       23  

Sustaining capital leases

        0       0       1       3       0       0  

Rehabilitation - accretion and amortization (operating sites)

   f      1       0       0       0       1       0  

Non-controlling interests

        0       0       0       0       (2     (3
               

 All-in sustaining costs

        68       38       133       112       72       70  
               

 Ounces sold - attributable basis (000s ounces)

        54       22       69       69       36       36  
               

 COS/oz

   g,h      1,816       1,665       2,801       1,906       2,287       2,008  

 TCC/oz

   h      1,037       1,346       1,918       1,418       1,758       1,379  

 AISC/oz

   h      1,253       1,740       1,933       1,614       1,990       1,922  

 

 

 

BARRICK FIRST QUARTER 2026   40    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

 ($ millions, except per oz information in dollars)                   For the three months ended 12/31/25  
      Footnote    Carlin     Cortez     Turquoise
Ridge
    Phoenix     Nevada
Gold Minesa
    Hemlob    

Pueblo

Viejo

 

 COS applicable to gold production

        642       355       241       79       1,318       44       264  

Depreciation

        (164     (86     (62     (15     (327     (1     (82

Costs allocated to by-products

        (2     (1     (1     (68     (72     0       (17

Other

   c      (2     (4     0       9       3       0       0  

Non-controlling interests

        (182     (103     (69     (2     (356     0       (67
                 

 Total cash costs

          292       161       109       3       566       43       98  

General & administrative costs

        0       0       0       0       0       0       0  

Minesite exploration and evaluation costs

   d      5       2       0       0       8       0       0  

Minesite sustaining capital expenditures

   e      113       36       28       4       190       7       67  

Sustaining capital leases

        0       0       0       1       1       1       (1

Rehabilitation - accretion and amortization (operating sites)

   f      3       5       1       1       10       0       2  

Non-controlling interests

        (47     (17     (11     (2     (81     0       (27
                 

 All-in sustaining costs

        366       187       127       7       694       51       139  
                 

 Ounces sold - attributable basis (000s ounces)

          211       136       104       24       475       27       106  

 COS/oz

   g,h      1,863       1,592       1,422       1,972       1,695       1,738       1,492  

 TCC/oz

   h      1,380       1,196       1,050       127       1,191       1,707       930  

 AISC/oz

   h      1,732       1,384       1,225       279       1,461       1,976       1,322  
 ($ millions, except per oz information in dollars)                   For the three months ended 12/31/25  
      Footnote    Veladero     Porgera     Loulo-
Gounkotoi
    Kibali     North Mara     Tongonj     Bulyanhulu  

 COS applicable to gold production

        67       35       472       123       108       56       86  

Depreciation

        (25     (9     (24     (36     (25     1       (17

Costs allocated to by-products

        (3     0       0       (2     (2     0       (12

Other

   c      0       0       (283     0       0       0       1  

Non-controlling interests

        0       0       (33     0       (12     (6     (9
                 

 Total cash costs

          39       26       132       85       69       51       49  

General & administrative costs

        0       0       0       0       0       0       0  

Minesite exploration and evaluation costs

   d      0       0       0       0       0       0       0  

Minesite sustaining capital expenditures

   e      43       15       0       19       20       3       20  

Sustaining capital leases

        1       0       0       3       1       1       0  

Rehabilitation - accretion and amortization (operating sites)

   f      1       0       0       0       (1     0       0  

Non-controlling interests

        0       0       0       0       (3     (1     (3
                 

 All-in sustaining costs

        84       41       132       107       86       54       66  
                 

 Ounces sold - attributable basis (000s ounces)

          47       22       91       78       56       19       39  

 COS/oz

   g,h      1,526       1,608       4,151       1,557       1,640       2,648       1,885  

 TCC/oz

   h      886       1,180       1,448       1,093       1,237       2,659       1,262  

 AISC/oz

   h      1,915       1,865       1,448       1,374       1,546       2,844       1,694  

 

 

 

BARRICK FIRST QUARTER 2026   41    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

 ($ millions, except per oz information in dollars)                   For the three months ended 3/31/2025  
      Footnote    Carlin     Cortez     Turquoise
Ridge
    Phoenix     Nevada
Gold Minesa
    Hemlob     Pueblo
Viejo
 

 COS applicable to gold production

        401       241       203       79       925       67       237  

Depreciation

        (62     (57     (47     (17     (183     (10     (75

Costs allocated to by-products

        (2     (1     (1     (33     (37     0       (12

Other

   c      0       0       0       6       6       0       0  

Non-controlling interests

        (130     (70     (60     (13     (273     0       (60
                 

 Total cash costs

          207       113       95       22       438       57       90  

General & administrative costs

        0       0       0       0       0       0       0  

Minesite exploration and evaluation costs

   d      1       1       0       0       3       0       0  

Minesite sustaining capital expenditures

   e      253       52       22       10       340       8       59  

Sustaining capital leases

        0       0       0       0       0       1       0  

Rehabilitation - accretion and amortization (operating sites)

   f      3       4       1       2       10       0       1  

Non-controlling interests

        (99     (22     (9     (5     (136     0       (23
                 

 All-in sustaining costs

        365       148       109       29       655       66       127  
                 

 Ounces sold - attributable basis (000s ounces)

          142       96       78       29       345       39       76  

 COS/oz

   g,h      1,720       1,541       1,605       1,686       1,643       1,730       1,863  

 TCC/oz

   h      1,459       1,172       1,227       747       1,269       1,458       1,189  

 AISC/oz

   h      2,570       1,536       1,408       1,012       1,899       1,692       1,668  
 ($ millions, except per oz information in dollars)                   For the three months ended 3/31/25  
      Footnote    Veladero     Porgera     Loulo-
Gounkotoi
    Kibali     North Mara     Tongonj     Bulyanhulu  

 COS applicable to gold production

        79       36             113       102       70       77  

Depreciation

        (25     (7           (32     (21     (6     (16

Costs allocated to by-products

        (1     0             0       (1     0       (7

Other

   c      0       0             0       0       0       1  

Non-controlling interests

        0       0             0       (13     (7     (9
                 

 Total cash costs

          53       29             81       67       57       46  

General & administrative costs

        0       0             0       0       0       0  

Minesite exploration and evaluation costs

   d      1       0             0       0       0       0  

Minesite sustaining capital expenditures

   e      33       6             12       21       3       28  

Sustaining capital leases

        0       0             2       0       0       0  

Rehabilitation - accretion and amortization (operating sites)

   f      1       0             0       1       2       0  

Non-controlling interests

        0       0             0       (3     0       (5
                 

 All-in sustaining costs

        88       35             95       86       62       69  
                 

 Ounces sold - attributable basis (000s ounces)

          68       21             67       68       29       38  

 COS/oz

   g,h      1,141       1,675             1,691       1,257       2,154       1,714  

 TCC/oz

   h      753       1,336             1,212       986       1,971       1,212  

 AISC/oz

   h      1,271       1,684             1,426       1,258       2,144       1,831  

 

a. 

 

These results represent our 61.5% interest in Carlin, Cortez, Turquoise Ridge and Phoenix and non-mine site related activity.

b.

 

On September 10, 2025, we reached an agreement to sell the Hemlo gold mine to Carcetti Capital Corp. for gross proceeds of up to $1.09 billion. The transaction closed on November 26, 2025. Accordingly, operating and financial results provided are up to the closing date.

c.

 

Other - Other adjustments at Carlin include the removal of TCC associated with Emigrant, which is producing incidental ounces.

d.

 

Exploration and evaluation costs - Exploration, evaluation and project expenses are included in AISC if they support current mine operations.

e.

 

Capital expenditures - Capital expenditures are related to our gold sites only and are split between minesite sustaining and project capital expenditures.

f.

 

Rehabilitation - accretion and amortization - Includes depreciation on the assets related to rehabilitation provisions of our gold operations and accretion on the rehabilitation provision of our gold operations, split between operating and non-operating sites.

g.

 

COS/oz - Gold COS/oz is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share).

h.

 

Per ounce figures - COS/oz, TCC/oz and AISC/oz may not calculate based on amounts presented in this table due to rounding.

i.

 

As a result of temporary suspension of operations at Loulo-Gounkoto starting January 14, 2025, and subsequent loss of control on June 16, 2025, no operating data or per ounce data was provided for Q1 2025 to Q3 2025. On November 24, 2025, Barrick announced that an agreement had been entered into with the

 

 

 

BARRICK FIRST QUARTER 2026   42    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Government of the Republic of Mali to put an end to all disputes regarding the Loulo and Gounkoto mines. The provisional administration of the Loulo-Gounkoto complex was terminated on December 16, 2025, at which point operational control was handed back to Somilo and Gounkoto’s management.

 

 

 

j.

On October 6, 2025, we reached an agreement to sell our interest in the Tongon gold mine and certain of its exploration properties to the Atlantic Group for total consideration of up to $305 million. The transaction closed on December 1, 2025. Accordingly, operating and financial results provided are up to the closing date.

 

 

Reconciliation of Copper Cost of Sales to C1 cash costs and All-in sustaining costs, including on a per pound basis

 

 ($ millions, except per lb information in dollars)           For the three months ended  
       
      3/31/26     12/31/25     3/31/25  

Cost of sales

     217       281       208  

Depreciation/amortization

     (43     (88     (60

Treatment and refinement charges

     35       53       42  

C1 cash costs applicable to equity method investments

     95       174       90  

Less: royalties

     (30     (37     (21

Costs allocated to by-products

     (18     (22     (5

C1 cash costs of sales

     256       361       254  

General & administrative costs

     6       11       8  

Rehabilitation - accretion and amortization

     1       1       1  

Royalties

     30       37       21  

Minesite exploration and evaluation costs

     2       3       2  

Minesite sustaining capital expenditures

     66       116       57  

Sustaining leases

     1       2       3  

All-in sustaining costs

     362       531       346  

Tonnes sold - attributable basis (thousands of tonnes)

     45       67       51  

Pounds sold - attributable basis (millions pounds)

     99       147       112  

COS/lba,b

     3.41       3.37       2.92  

C1 cash costs per pounda

     2.57       2.45       2.25  

AISC/lba

     3.67       3.61       3.06  

 

a.

COS/lb, C1 cash costs/lb and AISC/lb may not calculate based on amounts presented in this table due to rounding.

b.

Copper COS/lb is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share).

Reconciliation of Copper Cost of Sales to C1 cash costs and All-in sustaining costs, including on a per pound basis, by operating segment

 

 ($ millions, except per lb information in dollars)                                        For the three months ended  
       
      3/31/26     12/31/25     3/31/25  
                   
      Zaldívar     Lumwana     Jabal
Sayid
    Zaldívar     Lumwana     Jabal
Sayid
    Zaldívar     Lumwana     Jabal
Sayid
 

Cost of sales

     89       217       31       175       282       38       88       208       33  

Depreciation/amortization

     (20     (43     (6     (32     (89     (7     (24     (60     (7

Treatment and refinement charges

     0       35       0       0       53       0       0       39       3  

Less: royalties

     (1     (30     0       0       (37     0       0       (21     0  

Costs allocated to by-products

     0       (4     (13     0       (7     (15     0       0       (5

C1 cash costs of sales

     68       175       12       143       202       16       64       166       24  

Rehabilitation - accretion and amortization

     0       1       0       1       1       0       0       1       0  

Royalties

     1       30       0       0       37       0       0       21       0  

Minesite exploration and evaluation costs

     2       0       0       3       0       0       2       0       0  

Minesite sustaining capital expenditures

     20       45       2       20       92       4       5       50       2  

Sustaining leases

     1       0       0       1       0       1       2       1       0  

All-in sustaining costs

     92       251       14       168       332       21       73       239       26  

Tonnes sold - attributable basis (thousands of tonnes)

     8       30       7       12       47       8       10       34       7  

Pounds sold - attributable basis (millions of pounds)

     18       66       15       27       103       17       21       75       17  

COS/lba,b

     4.87       3.31       2.07       6.33       2.76       2.21       4.11       2.80       1.96  

C1 cash costs/lba

     3.70       2.67       0.79       5.17       1.97       0.94       2.99       2.22       1.44  

AISC/lba

     5.02       3.83       0.94       6.03       3.24       1.20       3.38       3.20       1.55  

 

a.

COS/lb, C1 cash costs/lb and AISC/lb may not calculate based on amounts presented in this table due to rounding.

b.

Copper COS/lb is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share).

 

 

 

BARRICK FIRST QUARTER 2026   43    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

EBITDA, Adjusted EBITDA, Attributable EBITDA, Attributable EBITDA Margin and Net Leverage

EBITDA is a non-GAAP financial measure, which excludes the following from net earnings:

   

Income tax expense;

 
   

Finance costs;

 
   

Finance income; and

 
   

Depreciation.

 

Management believes that EBITDA is a valuable indicator of our ability to generate liquidity by producing operating cash flow to fund working capital needs, service debt obligations, and fund capital expenditures. Management uses EBITDA for this purpose. EBITDA is also frequently used by investors and analysts for valuation purposes whereby EBITDA is multiplied by a factor or “EBITDA multiple” that is based on an observed or inferred relationship between EBITDA and market values to determine the approximate total enterprise value of a company.

Adjusted EBITDA removes the effect of impairment charges; acquisition/disposition gains/losses; foreign currency translation gains/losses; and other expense adjustments. We also remove the impact of income tax expense, finance costs, finance income and depreciation incurred in our equity method accounted investments. Attributable EBITDA further removes the non-controlling interest portion. We believe these items provide a greater level of consistency with the adjusting items included in our adjusted net earnings reconciliation, with the exception that these amounts are adjusted to remove any impact on finance costs/income, income tax expense and/or depreciation as they do not affect EBITDA. We believe this additional information will assist analysts, investors and other stakeholders of Barrick in better understanding our

ability to generate liquidity from our attributable business, including equity method investments, by excluding these amounts from the calculation as they are not indicative of the performance of our core mining business and do not necessarily reflect the underlying operating results for the periods presented. Additionally, it is aligned with how we present our forward-looking guidance on gold ounces and copper pounds produced.

Attributable EBITDA margin is calculated as attributable EBITDA divided by revenues - as adjusted. We believe this ratio will assist analysts, investors and other stakeholders of Barrick to better understand the relationship between revenues and EBITDA or operating profit.

Net leverage is calculated as debt, net of cash divided by the sum of adjusted EBITDA of the last four consecutive quarters. We believe this ratio will assist analysts, investors and other stakeholders of Barrick in monitoring our leverage and evaluating our balance sheet.

EBITDA, adjusted EBITDA, attributable EBITDA, attributable EBITDA margin and net leverage are intended to provide additional information to investors and analysts and do not have any standardized definition under IFRS, and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. EBITDA, adjusted EBITDA and attributable EBITDA exclude the impact of cash costs of financing activities and taxes, and the effects of changes in operating working capital balances, and therefore are not necessarily indicative of operating profit or cash flow from operations as determined under IFRS. Other companies may calculate EBITDA, adjusted EBITDA, attributable EBITDA, attributable EBITDA margin and net leverage differently.

 

 

Reconciliation of Net Earnings to EBITDA, Adjusted EBITDA and Attributable EBITDA

 

 ($ millions)           

For the three months ended 

 
     
      3/31/26       12/31/25       3/31/25   
 Net earnings      2,481           3,213           781     

Income tax expense

     747           794           278     

Finance costs, neta

     19           42           39     

Depreciation

     499           599           411     
 EBITDA      3,746           4,648           1,509     
 Impairment charges of non-current assetsb      0           5           4     
 Acquisition/disposition losses (gains)c      1           (1,146)          0     
 (Gain) loss on currency translation      20           6           2     
 Other expense adjustmentsd      18           559           173     
 Income tax expense, net finance costsa and depreciation from equity investees      148           238           141     
 Adjusted EBITDA      3,933           4,310           1,829     
 Non-controlling Interests      (1,173)          (1,226)          (468)    
 Attributable EBITDA      2,760           3,084           1,361     
 Revenues - as adjustede      4,181           4,810           2,685     
 Attributable EBITDA marginf      66 %        64 %        51 %  
     As at 3/31/26      As at 12/31/25        As at 3/31/25  
 Net leverageg      -0.2:1        -0.2:1        0.1:1  

 

a. 

Finance costs exclude accretion.

b. 

There were no significant impairment charges or reversals in the current period or prior periods.

c. 

Acquisition/disposition gains for Q4 2025 relate to gain on sale of our Hemlo gold mine, our interest in the Tongon gold mine and the Alturas project. Q4 2025 was further impacted by the accounting impact of regaining control of the Loulo-Gounkoto complex on December 16, 2025.

d. 

Other expense for Q1 2026 period mainly related to the fair value increment on inventory resulting from the purchase price allocation when we regained control of Loulo-Gounkoto, reduced operations costs at Mali, legal and consulting costs related to our North America IPO project and revaluation of contingent consideration for Hemlo. Other expense for 2025 periods mainly related to the reduced operations costs relating to Mali in Q1 2025, the settlement payment to the Government of Mali in November 2025, the fair value increment on inventory resulting from the purchase price allocation when we regained control of Loulo-Gounkoto and severance costs incurred

e. 

Refer to Reconciliation of Sales to Realized Price per oz/pound on page 45 of this MD&A.

f. 

Represents attributable EBITDA divided by revenues - as adjusted.

g. 

Represents debt, net of cash divided by adjusted EBITDA of the last four consecutive quarters.

 

 

 

BARRICK FIRST QUARTER 2026   44    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Realized Price

 

Realized price is a non-GAAP financial measure which excludes from sales:

Treatment and refining charges; and

Cumulative catch-up adjustment to revenue relating to our streaming arrangements.

 

We believe this provides investors and analysts with a more accurate measure with which to compare to market gold and copper prices and to assess our gold and copper sales performance. For those reasons, management believes that this measure provides a more accurate reflection of our

 

  

  

 

Company’s past performance and is a better indicator of its expected performance in future periods.

The realized price measure is intended to provide additional information, and does not have any standardized definition under IFRS and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. The measure is not necessarily indicative of sales as determined under IFRS. Other companies may calculate this measure differently. The following table reconciles realized prices to the most directly comparable IFRS measure.

Reconciliation of Sales to Realized Price per ounce/pound

 

 ($ millions, except per oz/lb information in dollars)

          Gold                    Copper          
          

For the three months ended

 
             
       3/31/26       12/31/25       3/31/25       3/31/26        12/31/25        3/31/25  

 Sales

     4,756       5,353       2,766       343        514        304  

 Sales applicable to non-controlling interests

     (1,591     (1,756     (848     0        0        0  

 Sales applicable to equity method investmentsa,b

     446       418       252       196        233        164  

 Sales applicable to sites in closure or care and maintenancec

     (13     (5     (1     0        0        0  

 Treatment and refinement charges

     9       10       6       35        53        42  

 Otherd

     0       (10     0       0        0        0  

 Revenues – as adjusted

     3,607       4,010       2,175       574        800        510  

 Ounces/pounds sold (koz/Mlb)c

     748       960       751       99        147        113  

 Realized gold/copper price per oz/lbe

     4,823       4,177       2,898       5.79        5.42        4.51  

 

a. 

Represents sales of $341 million for Q1 2026 (Q4 2025: $327 million; Q1 2025: $191 million) applicable to our 45% equity method investment in Kibali and $105 million (Q4 2025: $91 million; Q1 2025: $61 million) applicable to our 24.5% equity method investment in Porgera for gold. Represents sales of $110 million for Q1 2026 (Q4 2025: $151 million; Q1 2025: $95 million) applicable to our 50% equity method investment in Zaldívar and $86 million (Q4 2025: $83 million; Q1 2025: $72 million), applicable to our 50% equity method investment in Jabal Sayid for copper.

b. 

Sales applicable to equity method investments are net of treatment and refinement charges.

c. 

On an attributable basis. Excludes Long Canyon which is producing residual ounces from the leach pad while in care and maintenance.

d. 

Represents cumulative catch-up adjustment to revenue relating to our streaming arrangements. Refer to note 2e of the 2025 Annual Financial Statements for more information.

e. 

Realized price per oz/lb may not calculate based on amounts presented in this table due to rounding.

 

 

 

BARRICK FIRST QUARTER 2026   45    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Technical Information

 

 

The scientific and technical information contained in this MD&A has been reviewed and approved by Jesse Clark, BSc (Hons), MSc, SMERM, Director, Geology; Richard Peattie, MPhil, FAusIMM, Chief Technical Officer; and Joel Holliday, FAusIMM, Executive Vice-President, Exploration – each a “Qualified Person” as defined in National Instrument 43-101Standards of Disclosure for Mineral Projects.

All mineral reserve and mineral resource estimates are estimated in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects. Unless otherwise noted, such mineral reserve and mineral resource estimates are as of December 31, 2025.

Endnotes

 

 

 

1 

Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 36 to 45 of this MD&A.

 

2 

Gold COS/oz is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share). Copper COS/lb is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share). References to attributable basis means our 100% share of Hemlo and Lumwana, our 61.5% share of NGM, our 60% share of Pueblo Viejo, our 80% share of Loulo-Gounkoto, our 89.7% share of Tongon, our 84% share of North Mara, and Bulyanhulu, our 50% share of Veladero, Zaldívar and Jabal Sayid, our 24.5% share of Porgera and our 45% share of Kibali.

 

3 

Total reportable incident frequency rate (“TRIFR”) is a ratio calculated as follows: number of reportable injuries x 1,000,000 hours divided by the total number of hours worked. Reportable injuries include fatalities, lost time injuries, restricted duty injuries, and medically treated injuries. Lost time injury frequency rate (“LTIFR”) is a ratio calculated as follows: number of lost time injuries x 1,000,000 hours divided by the total number of hours worked.

 

4 

Class 1 - High Significance is defined as an incident that causes significant negative impacts on human health or the environment or an incident that extends onto publicly accessible land and has the potential to cause significant adverse impact to surrounding communities, livestock or wildlife.

 

5 

A Tier One Gold Asset is an asset with a $1,500/oz reserve with potential to deliver a minimum 10-year life, annual production of at least 500,000 ounces of gold and with projected costs per ounce in the lower half of the industry cost curve. A Tier One Copper Asset/Project is an asset with a $3.25/lb reserve with potential for +5Mt contained copper in support at least 20 years life, annual production of at least 200ktpa, with costs per pound in the lower half of the industry cost curve. Tier One Assets must be located in a world-class geological district with potential for organic reserve growth and long-term geologically driven addition.

 

6 

Fourmile production and economic metrics are based upon a preliminary economic assessment, using 2024 mineral resources only and August 2025 Long Term Consensus Gold Price of $2,585/oz. These metrics are conceptual in nature because they include inferred mineral resources that are considered too speculative to have the considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the preliminary economic assessment will be realized.

 

7 

Refer to the Technical Report on the Cortez Complex, Lander and Eureka Counties, State of Nevada, USA, dated December 31, 2021, and filed on SEDAR+ at www.sedarplus.ca and EDGAR at www.sec.gov on March 18, 2022.

 

8 

Refer to the Technical Report on the Carlin Complex, Eureka and Elko County, Nevada, USA, dated December 31, 2024, and filed on SEDAR+ at www.sedarplus.ca and EDGAR at www.sec.gov on March 14, 2025.

 

9 

Refer to the Technical Report on the Pueblo Viejo mine, Dominican Republic, dated December 31, 2025, and filed on SEDAR+ at www.sedarplus.ca and EDGAR at www.sec.gov on February 27, 2026.

 

10 

Refer to the Technical Report on the Reko Diq Project, Balochistan, Pakistan, dated December 31, 2024, and filed on SEDAR+ at www.sedarplus.ca and EDGAR at www.sec.gov on February 19, 2025.

 

11 

Refer to the Technical Report on the Lumwana Expansion Project, Republic of Zambia, dated December 31, 2024, and filed on SEDAR+ at www.sedarplus.ca and EDGAR at www.sec.gov on February 19, 2025.

 

 

 

BARRICK FIRST QUARTER 2026   46    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

12 

Q1 2026 Goldrush Underground (GRUG) Significant Interceptsac

 

Drill Results from Q1 2026          
                                   Includingd
Drill Holeb    Azimuth    Dip    Interval (m)     Estimated
True Width (m)c
  Au (g/t)    Interval (m)    Estimated
True Width (m)c
     Au (g/t)  

GUC-25147

   78    -33    265.5 - 268.5    3.0*   6.68         
               271.6 - 274.3    2.7*   4.53         
               442.0 - 445.0    3.0*   7.93         
               448.1 - 449.6    1.5*   4.16         
               463.0 - 464.1    1.1*   4.38         
               471.2 - 500.5    20.3   12.05    486.16 - 491.64    5.5    34.3
               538.3 - 555.0    16.8   20.52    544.37 - 551.99    7.6    35.2
               634.0 - 637.3    3.0   23.50    633.98 - 635.51    1.5    28.6
               662.9 - 674.0    11.1   57.76    662.94 - 672.08    9.1    67.2
               695.3 - 696.8    1.5   17.75         

 

  a.

All intercepts calculated using a 3.4 g/t Au cutoff and are uncapped; minimum intercept width is 1.0 meters; internal dilution is less than 20% total width.

  b.

Drill hole nomenclature: GUC Project area Goldrush Underground, the year (25 for 2025) followed by the hole number.

  c.

True width for drillhole intercepts has been estimated based on the latest geological interpretation and it is subject to refinement as additional data becomes available. *core length: true width of intercepts are uncertain at this stage.

  d.

Included intervals calculated using a 20.0 g/t Au cutoff and are uncapped; minimum intercept width is 1.0 meters; internal dilution is less than 20 % total width.

The drilling results for Goldrush contained in this presentation have been prepared in accordance with National Instrument 43-101Standards of Disclosure for Mineral Projects. All drill hole assay information has been manually reviewed and approved by staff geologists and re-checked by the project manager. Sample preparation and analyses are conducted by ALS Minerals, an independent laboratory. Procedures are employed to ensure security of samples during their delivery from the drill rig to the laboratory. The quality assurance procedures, data verification and assay protocols used in connection with drilling and sampling at Goldrush conform to industry accepted quality control methods.

 

13 

Q1 2026 Porfiada, Veladero District, Argentina Interceptsac

 

Drill Results from Q1 2026          
                                   Includingd
  Core Drill Holeb    Azimuth    Dip    Interval (m)    Estimated
True Width (m)c
  Au (g/t)    Interval (m)    Estimated
True Width (m)c
  Au (g/t)

DDH-POR-07A

   305    -60    125 - 129    4.0*   0.48        

DDH-POR-07A

   305    -60    132 - 136    4.0*   0.31        

DDH-POR-07A

   305    -60    142 - 144    2.0*   0.97        

DDH-POR-07A

   305    -60    163.4 - 216    54.6*   2.03    163.4 - 175    11.6*   3.24
                             183 - 199    18.0*   3.39
DDH-POR-07A    305    -60    242 - 244    2.0*   1.28        

 

  a.

All intercepts calculated using a 3.4 g/t Au cutoff and are uncapped; minimum intercept width is 1.0 meters; internal dilution is less than 20% total width.

  b.

Drill hole nomenclature: Drill system Diamond Drill Hole (DDH), Project Name (POR = Porfiada) followed by the hole number.

  c.

True width for drillhole intercepts has been estimated based on the latest geological interpretation and it is subject to refinement as additional data becomes available. *core length: true width of intercepts are uncertain at this stage.

  d.

Included intervals calculated using a 20.0 g/t Au cutoff and are uncapped; minimum intercept width is 1.0 meters; internal dilution is less than 20 % total width.

The drilling results for Porfiada contained in this MD&A have been prepared in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects. All drill hole assay information has been manually reviewed and approved by staff geologists and re-checked by the project manager. Sample preparation and analyses are conducted by the laboratory at our Veladero mine. Procedures are employed to ensure security of samples during their delivery from the drill rig to the laboratory. The quality assurance procedures, data verification and assay protocols used in connection with drilling and sampling at Argenta Block conform to industry accepted quality control methods.

 

 

 

BARRICK FIRST QUARTER 2026   47    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

14 

Q1 2026 Turquoise Ridge Significant Interceptsac

 

TRUG Dune Drill Results
                                   Including(d)
Core Drill Holeb    Azimuth    Dip    Interval (m)    Estimated
True Width (m)c
  Au (g/t)    Interval (m)    Estimated
True Width (m)c
   Au (g/t) 

 TUM-25236A

   79    -6    117-120    3.0*   8.3          — 
               144-146    1.5*   11.6          — 
               181-190    1.9*   6.6          — 
               321-342    5.04   11.4    328-329    1    94 

 

  a.

All intercepts calculated using a 3.4 g/t Au cutoff and are uncapped; minimum intercept width is 1.0 meters; internal dilution is less than 20% total width.

  b.

Drill hole nomenclature: TUM Project area Turquoise Ridge Underground, the year (25 for 2025) followed by the hole number.

  c.

True width for drillhole intercepts has been estimated based on the latest geological interpretation and it is subject to refinement as additional data becomes available. *core length: true width of intercepts are uncertain at this stage.

  d.

Included intervals calculated using a 20.0 g/t Au cutoff and are uncapped; minimum intercept width is 1.0 meters; internal dilution is less than 20 % total width.

The drilling results for Turquoise Ridge contained in this presentation have been prepared in accordance with National Instrument 43-101Standards of Disclosure for Mineral Projects. All drill hole assay information has been manually reviewed and approved by staff geologists and re-checked by the project manager. Sample preparation and analyses are conducted by ALS Minerals, an independent laboratory. Procedures are employed to ensure security of samples during their delivery from the drill rig to the laboratory. The quality assurance procedures, data verification and assay protocols used in connection with drilling and sampling at Turquoise Ridge conform to industry accepted quality control methods.

 

 

 

BARRICK FIRST QUARTER 2026   48    MANAGEMENT’S DISCUSSION AND ANALYSIS


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

 Consolidated Statements of Income

 

  Barrick Mining Corporation

  (in millions of United States dollars, except per share data) (Unaudited)

   Three months ended
March 31,
 
     
      2026     2025  
 

Revenue (notes 5 and 6)

     $5,218       $3,130  
 

Costs and expenses (income)

      
 

Cost of sales (notes 5 and 7)

     2,099       1,785  
 

General and administrative expenses

     39       42  
 

Exploration, evaluation and project expenses

     116       54  
 

Impairment charges

           4  
 

Loss on currency translation

     20       2  
 

Closed mine rehabilitation

     (3     19  
 

Income from equity investees (note 12)

     (316     (67
 

Other (income) expense (note 9)

     (4     170  
 

Income before finance costs and income taxes

     $3,267       $1,121  
 

Finance costs, net

     (39     (62
 

Income before income taxes

     $3,228       $1,059  
 

Income tax expense (note 10)

     (747     (278
 

Net income

     $2,481       $781  
 

Attributable to:

      
 

Equity holders of Barrick Mining Corporation

     $1,602       $474  
 

Non-controlling interests (note 16)

     $879       $307  
 
                  
 

Earnings per share attributable to the equity holders of Barrick Mining Corporation (note 8)

      
 

Net income

      
 

Basic

     $0.96       $0.27  
 

Diluted

     $0.96       $0.27  

The accompanying notes are an integral part of these condensed interim consolidated financial statements.

 

 

 

BARRICK FIRST QUARTER 2026   49    FINANCIAL STATEMENTS (UNAUDITED)


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

 Consolidated Statements

 of Comprehensive Income

 

  Barrick Mining Corporation

  (in millions of United States dollars) (Unaudited)

  

Three months

ended March 31,

 
     
      2026       2025  
 

Net income

     $2,481       $781  
 

Other comprehensive income (loss), net of taxes

      
 

Items that may be reclassified subsequently to profit or loss:

      
 

Unrealized losses on derivatives designated as cash flow hedges, net of tax $nil and $nil

     (184      
 

Realized losses on derivatives designated as cash flow hedges, net of tax $nil and $nil

     42        
 

Items that will not be reclassified to profit or loss:

      
 

Actuarial gain (loss) on post employment benefit obligations, net of tax $nil and $nil

           (1
 

Net unrealized change on equity investments, net of tax $nil and $nil

     (40     5  
 

Net realized change on equity investments, net of tax $(1) and $nil

     59        
 

Total other comprehensive (loss) income

     (123     4  
 

Total comprehensive income

     $2,358       $785  
 

Attributable to:

      
 

Equity holders of Barrick Mining Corporation

     $1,479       $478  
 

Non-controlling interests

     $879       $307  

The accompanying notes are an integral part of these condensed interim consolidated financial statements.

 

 

 

BARRICK FIRST QUARTER 2026   50    FINANCIAL STATEMENTS (UNAUDITED)


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

 Consolidated Statements of Cash Flow

 

Barrick Mining Corporation

(in millions of United States dollars) (Unaudited)

  

Three months

ended March 31,

 
     
          2026        2025  
 

OPERATING ACTIVITIES

      
 

Net income

     $2,481       $781  
 

Adjustments for the following items:

      
 

Depreciation

     500       411  
 

Finance costs, net

     39       62  
 

Impairment charges

           4  
 

Income tax expense (note 10)

     747       278  
 

Income from equity investees (note 12)

     (316     (67
 

Loss on sale of non-current assets (note 9)

     1        
 

Loss on currency translation

     20       2  
 

Change in working capital (note 11)

     (302     (105
 

Other operating activities (note 11)

     (256     (9
 

Operating cash flows before interest and income taxes

     2,914       1,357  
 

Interest paid

     (49     (25
 

Interest received

     55       46  
 

Income taxes paid1

     (366     (166
 

Net cash provided by operating activities

     2,554       1,212  
 

INVESTING ACTIVITIES

      
 

Property, plant and equipment

      
 

Capital expenditures (note 5)

     (979     (837
 

Sales proceeds

     2        
 

Divestitures2

     (4      
 

Investment sales

     110        
 

Dividends received from equity method investments (note 12)

     110       38  
 

Shareholder loan repayments from equity method investments

     147       60  
 

Net cash used in investing activities

     (614     (739
 

FINANCING ACTIVITIES

      
 

Lease repayments

     (5     (3
 

Dividends

     (697     (172
 

Share buyback program (note 15)

           (143
 

Funding from Reko Diq non-controlling interests (note 16)

     122       83  
 

Disbursements to non-controlling interests (note 16)

     (926     (208
 

Pueblo Viejo JV partner shareholder loan

     (9     4  
 

Net cash used in financing activities

     (1,515     (439
 

Effect of exchange rate changes on cash and equivalents

            
 

Net increase in cash and equivalents

     425       34  
 

Cash and equivalents at the beginning of period

     6,706       4,074  
 

Cash and equivalents at the end of period

     7,131       4,108  
 

Less: cash and equivalents classified as held for sale at the end of period

           4  
 

Cash and equivalents excluding assets classified as held for sale at the end of period

     $7,131       $4,104  

 

  1

Income taxes paid excludes $20 million (Q1 2025: $17 million) for Q1 2026 of income taxes payable that were settled against offsetting value added tax (“VAT”) receivables.

  2 

Relates to working capital adjustments from the sale of the Hemlo gold mine and our interest in the Tongon gold mine and certain of its exploration properties, of which both transactions closed in the fourth quarter of 2025.

The accompanying notes are an integral part of these condensed interim consolidated financial statements.

 

 

 

BARRICK FIRST QUARTER 2026   51    FINANCIAL STATEMENTS (UNAUDITED)


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

 Consolidated Balance Sheets

 

Barrick Mining Corporation

 

(in millions of United States dollars) (Unaudited)

 

    As at March 31,

 

2026

   

  As at December 31,

 

2025

 
 

ASSETS

     
 

Current assets

     
 

Cash and equivalents

    $7,131       $6,706  
 

Accounts receivable

    718       791  
 

Inventories

    2,148       2,068  
 

Other current assets

    616       652  
 

Total current assets

    $10,613       $10,217  
 

Non-current assets

     
 

Non-current portion of inventory

    2,789       2,792  
 

Equity in investees (note 12)

    4,325       4,216  
 

Property, plant and equipment

    29,857       29,354  
 

Intangible assets

    148       148  
 

Goodwill

    3,034       3,034  
 

Deferred income tax assets

    43       43  
 

Other assets

    1,774       1,773  
 

Total assets

    $52,583       $51,577  
 

LIABILITIES AND EQUITY

     
 

Current liabilities

     
 

Accounts payable

    $1,649       $1,859  
 

Debt

    61       56  
 

Current income tax liabilities

    1,072       866  
 

Other current liabilities

    682       716  
     

Total current liabilities

    $3,464       $3,497  
 

Non-current liabilities

     
 

Debt

    4,665       4,647  
 

Provisions

    1,791       1,846  
 

Deferred income tax liabilities

    4,147       3,984  
 

Other liabilities

    1,743       1,687  
     

Total liabilities

    $15,810       $15,661  
 

Equity

     
 

Capital stock (note 15)

    $26,841       $26,834  
 

Deficit

    (272     (1,170
 

Accumulated other comprehensive loss

    (396     (273
 

Other

    1,166       1,166  
     

Total equity attributable to Barrick Mining Corporation shareholders

    $27,339       $26,557  
 

Non-controlling interests (note 16)

    9,434       9,359  
     

Total equity

    $36,773       $35,916  
 

Contingencies and commitments (notes 5 and 17)

               
 

Total liabilities and equity

    $52,583       $51,577  

The accompanying notes are an integral part of these condensed interim consolidated financial statements.

 

 

 

BARRICK FIRST QUARTER 2026   52    FINANCIAL STATEMENTS (UNAUDITED)


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

 Consolidated Statements of Changes in Equity

 

 
  Barrick Mining Corporation              Attributable to equity holders of the company                  

  (in millions of United States dollars)

  (Unaudited)

    

Common
Shares (in
thousands)
 
 
 
   
Capital
stock
 
 
   

Retained
earnings
(deficit)
 
 
 
   


Accumulated
other
comprehensive
income (loss)1
 
 
 
 
    Other2      

Total equity
attributable to
shareholders
 
 
 
   

Non-
controlling
interests
 
 
 
   
Total
equity
 
 

At January 1, 2026

     1,675,360       $26,834       ($1,170     ($273     $1,166       $26,557       $9,359       $35,916  

Net income

                 1,602                   1,602       879       2,481  

Total other comprehensive loss

                       (123           (123           (123

Total comprehensive income (loss)

                 1,602       (123           1,479       879       2,358  

Transactions with owners

                

Dividends

                 (697                 (697           (697

Funding from non-controlling interests (note 16)

                                         122       122  

Disbursements to non-controlling interests (note 16)

                                         (926     (926

Dividend reinvestment plan (note 15)

     148       7       (7                              
                 

Total transactions with owners

     148       7       (704                 (697     (804     (1,501

At March 31, 2026

     1,675,508       $26,841       ($272     ($396     $1,166       $27,339       $9,434       $36,773  
                                                                  

At January 1, 2025

     1,727,100       $27,661       ($5,269     $33       $1,865       $24,290       $8,966       $33,256  

Net income

                 474                   474       307       781  

Total other comprehensive income

                       4             4             4  

Total comprehensive income

                 474       4             478       307       785  

Transactions with owners

                

Dividends

                 (172                 (172           (172

Funding from non-controlling interests

                                         83       83  

Disbursements to non-controlling interests

                                         (242     (242

Dividend reinvestment plan

     50       1       (1                              

Share buyback program

     (7,692     (124                 (22     (146           (146

Total transactions with owners

     (7,642     (123     (173           (22     (318     (159     (477

At March 31, 2025

     1,719,458       $27,538       ($4,968     $37       $1,843       $24,450       $9,114       $33,564  

 

1 

Includes cumulative translation losses at March 31, 2026: $95 million (December 31, 2025: $95 million; March 31, 2025: $95 million).

2 

Includes additional paid-in capital as at March 31, 2026: $1,128 million (December 31, 2025: $1,128 million; March 31, 2025: $1,805 million).

The accompanying notes are an integral part of these condensed interim consolidated financial statements.

 

 

 

BARRICK FIRST QUARTER 2026   53    FINANCIAL STATEMENTS (UNAUDITED)


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Notes to Consolidated Financial Statements

Barrick Mining Corporation. Tabular dollar amounts in millions of United States dollars, unless otherwise shown.

 

1  Corporate Information

 

 

Barrick Mining Corporation (“Barrick”, “we” or the “Company”) is a corporation governed by the Business Corporations Act (British Columbia). The Company’s corporate office is located at Brookfield Place, TD Canada Trust Tower, 161 Bay Street, Suite 3700, Toronto, Ontario, M5J 2S1. The Company’s registered office is 925 West Georgia Street, Suite 1600, Vancouver, British Columbia, V6C 3L2. Barrick shares trade on the New York Stock Exchange under the symbol B and the Toronto Stock Exchange under the symbol ABX. We are principally engaged in the production and sale of gold and copper, as well as related activities such as exploration and mine development. We sell our gold and copper into the world market.

We have ownership interests in producing gold mines that are located in Argentina, the Democratic Republic of the Congo, the Dominican Republic, Mali, Papua New Guinea, Tanzania and the United States. We have ownership interests in producing copper mines in Chile, Saudi Arabia and Zambia. We also have various projects located throughout the Americas, Asia and Africa.

2  Material Accounting Policy Information

 

 

a) Statement of Compliance

These condensed interim consolidated financial statements have been prepared in accordance with IFRS Accounting Standards as issued by the International Accounting Standards Board (“IASB”) applicable to the preparation of interim financial statements, under International Accounting Standard 34, Interim Financial Reporting. These interim financial statements should be read in conjunction with Barrick’s most recently issued Annual Report, which includes information necessary or useful to understanding the Company’s business and financial statement presentation. In particular, the Company’s material accounting policy information was presented in Note 2 of the Annual Consolidated Financial Statements for the year ended December 31, 2025 (“2025 Annual Financial Statements”), and have been consistently applied in the preparation of these interim financial statements. These condensed interim consolidated financial statements were authorized for issuance by the Board of Directors on May 8, 2026.

b) New Accounting Standards Issued

Certain new accounting standards and interpretations have been published that are either applicable in the current year or not mandatory for the current period. We have assessed these standards and determined they do not have a material impact on Barrick in the current reporting period. In particular, the following standards have been issued by the IASB.

 

Amendments to the Classification and Measurement of Financial Instruments (IFRS 9 and IFRS 7) with mandatory application of the standard in annual reporting periods beginning on or after January 1, 2026. The amendment clarifies the date of recognition and derecognition of some financial assets and liabilities, and updates the disclosures for equity instruments designated at fair value through other

   

comprehensive income. This did not have a material impact on the financial statements.

 

IFRS 18 Presentation and Disclosure in Financial Statements with mandatory application of the standard in annual reporting periods beginning on or after January 1, 2027. Even though IFRS 18 will not impact the recognition or measurement of items in the financial statements, it will impact presentation and disclosure of certain aspects of the financial statements including management-defined performance measures (MPM) within the financial statements. Based on our preliminary assessment, items of income and expenses in the statement of income will be grouped into new categories resulting in new subtotals and/or line items being presented and changes in how certain existing subtotals are calculated; operating profit will be the starting point for determining cash flows from operating activities instead of net income and interest paid will be presented as financing cash flows and interest received as investing cash flows; and new disclosures will be required for MPMs, of which we believe that the following will meet the MPM definition: Adjusted net earnings, EBITDA, Adjusted EBITDA and Attributable EBITDA.

No standards have been early adopted in the current period.

3  Critical Judgements, Estimates, Assumptions and Risks

 

 

The judgments, estimates, assumptions and risks discussed here reflect updates from the 2025 Annual Financial Statements. For judgments, estimates, assumptions and risks related to other areas not discussed in these interim consolidated financial statements, please refer to Notes 3 and 28 of the 2025 Annual Financial Statements.

a) Provision for Environmental Rehabilitation (“PER”)

Provisions are updated each reporting period for changes to expected cash flows and for the effect of changes in the discount rate and foreign exchange rates. The change in estimate is added or deducted from the related asset and depreciated over the expected economic life of the operation to which it relates. In the case of closed sites, changes in estimates and assumptions are recognized immediately in the consolidated statements of income. For Q1 2026, we recorded a net decrease of $44 million (Q1 2025: $26 million net increase) to the PER at our minesites primarily due to an increase in the discount rate and spending incurred during the quarter, partially offset by accretion.

Adjustments to the estimated amount and timing of future closure and rehabilitation cash flows are a normal occurrence in light of the significant judgments and estimates involved. Rehabilitation provisions are adjusted as a result of changes in estimates and assumptions and are accounted for prospectively. In Q4 of each year, our life of mine plans are updated and that typically results in an update to the rehabilitation provision.

 

 

 

 

BARRICK FIRST QUARTER 2026   54    NOTES TO FINANCIAL STATEMENTS (UNAUDITED)


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

b) Contingencies

Contingencies can be either possible assets or possible liabilities arising from past events which, by their nature, will be resolved only when one or more future events, not wholly within our control, occur or fail to occur. The assessment of such contingencies inherently involves the exercise of significant judgment and estimates of the outcome of future events. Refer to Note 17 for further details on contingencies.

4  Acquisitions and Divestitures

 

 

a) Loulo-Gounkoto

On June 16, 2025, the Bamako Commercial Tribunal placed Loulo-Gounkoto under temporary provisional administration. While Barrick retained its 80% legal ownership of the mining complex, control over operations transferred to an external administrator. Following this action by the Malian courts, management concluded that Barrick had lost control of the subsidiaries that hold our interest in Loulo-Gounkoto because we could not effectively exercise power over the relevant activities related to the mine, nor could we affect the returns of the mine through managerial involvement. As a result of the loss of control event in Q2 2025, we deconsolidated the subsidiaries, and derecognized the assets, liabilities and non-controlling interest of Loulo-Gounkoto at their carrying amounts at the date when control was lost.

On November 24, 2025, Barrick announced that an agreement had been entered into with the Government of the Republic of Mali to put an end to all disputes regarding the Loulo and Gounkoto mines. The provisional administration of the Loulo-Gounkoto complex was terminated on December 16, 2025, at which point operational control was handed back to the management of Société des Mines de Loulo SA (“Somilo”) and Société des Mines de Gounkoto SA (“Gounkoto”).

We have determined that this represents a business combination with Barrick identified as the acquirer. We have determined the acquisition price should be equal to the fair value of Barrick’s 80% investment in the equity of Somilo and Gounkoto.

We have determined the fair value of Barrick’s existing interest in Loulo-Gounkoto immediately before the acquisition of control, which represents the fair value of the consideration in the transaction. We have also determined the fair value of the non-controlling interest and performed a provisional allocation of the purchase price to identified assets and liabilities.

The tables below present the provisional allocation of the purchase price to the assets and liabilities acquired recorded in the fourth quarter of 2025. This allocation is provisional, primarily property, plant and equipment. As disclosed in note 17, in April 2026 we made a $200 million payment in respect of royalties, penalties and interest, which will have implications on the purchase price allocation. We expect to complete the purchase price allocation process in the second half of 2026.

 ($ millions)        

Fair value of Loulo-Gounkoto (100%)

   $ 3,220  

Fair value of Loulo-Gounkoto (80%)

     2,576  
          

Provisional fair value allocation at acquisition

  

Cash

   $ 71  

Other current assets

     154  

Inventory

     629  

Property, plant and equipment

     3,131  

Other long-term assets

     120  

Total assets

   $  4,105  

Current liabilities

   $ 347  

Deferred income tax liabilities

     474  

Lease liabilities

     17  

Provisions

     47  

Other liability to Loulo-Gounkoto NCI

     240  

Total liabilities

   $ 1,125  

Non-controlling interests

     404  

Net assets acquired

   $  2,576  

We primarily used a discounted cash flow model (being the net present value of expected future cash flows) to determine the fair value of the mining interests and used a depreciated replacement cost approach in determining the fair value of property, plant and equipment. Expected future cash flows are based on estimates of future gold prices inclusive of a $3,000/oz long-term gold price and projected future revenues, estimated quantities of ore reserves and mineral resources, including expected conversions of resources to reserves, expected future production costs and capital expenditures based on the life of mine plans for the mines as at the acquisition date. A WACC of 16% was applied in the discounted cash flow model.

Since it has been consolidated from December 16, 2025, Loulo-Gounkoto contributed revenue of $505 million and net income of $16 million for the year ended December 31, 2025. If the acquisition had occurred on January 1, 2025, consolidated revenue and consolidated net income for the year ended December 31, 2025, would have been $1,036 million and $484 million, respectively. For the three months ended March 31, 2026, revenue and net income were $426 million and $164 million, respectively. The fair value of accounts receivable was $92 million (included in other current assets) as at December 16, 2025, which was equivalent to the contractual amount.

 

 

 

 

BARRICK FIRST QUARTER 2026   55    NOTES TO FINANCIAL STATEMENTS (UNAUDITED)


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

5 Segment Information

 

 

Barrick’s business is organized into fourteen minesites. Barrick’s Chief Operating Decision Maker (“CODM”) (Mark Hill, President and Chief Executive Officer) reviews the operating results, assesses performance and makes capital allocation decisions at the minesite level. Our presentation of our reportable operating segments consists of eight gold mines (Carlin, Cortez, Turquoise Ridge, Pueblo Viejo, Loulo-Gounkoto, Kibali, North Mara and Bulyanhulu) and one copper mine (Lumwana). The remaining operating segments, including our remaining gold mines, have been grouped into an “Other Mines” category and will not be reported on individually. Segment performance is evaluated based on a number of measures including operating income before tax, production levels and unit production costs. Certain costs are managed on a consolidated basis and are therefore not reflected in segment income.

Consolidated Statement of Income Information

 

           Cost of Sales                     
   

  For the three months ended

  March 31, 2026

   Revenue    

Site operating
costs, royalties and

community relations

     Depreciation     Exploration,
evaluation and
project expenses
     Other expenses
(income)1
    Segment income  

Carlin2

     $1,399       $380       $125       $1        $1       $892  

Cortez2

     719       231       81              1       406  

Turquoise Ridge2

     772       160       47              (6     571  

Pueblo Viejo2

     669       166       67       1        3       432  

Loulo-Gounkoto2

     426       203       38              21       164  

Kibali

     342       99       33              12       198  

Lumwana

     347       174       43              6       124  

North Mara2

     218       78       21              3       116  

Bulyanhulu2

     222       68       18              2       134  

Reportable segment total

     $5,114       $1,559       $473       $2        $43       $3,037  

Other Mines2

     501       136       51       1              313  

Share of equity investees

     (342     (99     (33            (12     (198

Segment total

     $5,273       $1,596       $491       $3        $31       $3,152  

Consolidated Statement of Income Information

 

           Cost of Sales                     
   

  For the three months ended

  March 31, 2025

   Revenue    

Site operating

costs, royalties and

community relations

     Depreciation    

Exploration,

evaluation and

project expenses

    

Other expenses

(income)1

   

Segment income

(loss)

 

Carlin2

     $678       $339       $62       $1        $3       $273  

Cortez2

     456       184       57       2        2       211  

Turquoise Ridge2

     364       156       47              1       160  

Pueblo Viejo2

     377       162       75       1        3       136  

Loulo-Gounkoto2

                 6       1        79       (86

Kibali

     192       81       32              7       72  

Lumwana

     305       148       60              2       95  

North Mara2

     235       81       21              3       130  

Bulyanhulu2

     146       61       16              2       67  

Reportable segment total

     $2,753       $1,212       $376       $5        $102       $1,058  

Other Mines2

     583       237       58       2        3       283  

Share of equity investees

     (192     (81     (32            (7     (72

Segment total

     $3,144       $1,368       $402       $7        $98       $1,269  

 

1 

Includes accretion expense, which is included within finance costs in the consolidated statement of income. For Q1 2026, accretion expense was $12 million (Q1 2025: $14 million).

2 

Includes non-controlling interest portion of revenues, cost of sales and segment income for Q1 2026 for Nevada Gold Mines $1,202 million, $428 million, $773 million (Q1 2025: $644 million, $355 million, $284 million), Pueblo Viejo $275 million, $94 million, $180 million (Q1 2025: $149 million, $95 million, $54 million), Loulo-Gounkoto $85 million, $48 million, $33 million (Q1 2025: $nil, $1 million, $(17) million), North Mara and Bulyanhulu $70 million, $30 million, $40 million (Q1 2025: $61 million, $29 million, $31 million), and Tongon $nil, $nil, $nil (Q1 2025: $10 million, $7 million, $2 million), respectively.

 

 

 

BARRICK FIRST QUARTER 2026   56    NOTES TO FINANCIAL STATEMENTS (UNAUDITED)


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

Reconciliation of Segment Income to Income Before Income Taxes

 

     For the three months ended
March 31
 
     
      2026     2025  

Reportable segment income

     $3,037       $1,058  

Segment income from Other Mines

     313       283  

Share of equity investees in reportable segment income

     (198     (72

Other revenue

     (55     (14

Other cost of sales/amortization

     (12     (15

Exploration, evaluation and project expenses not attributable to segments

     (113     (47

General and administrative expenses

     (39     (42

Other income (expense) not attributable to segments

     23       (86

Impairment charges

           (4

Loss on currency translation

     (20     (2

Closed mine rehabilitation

     3       (19

Income from equity investees

     316       67  

Finance costs, net (includes non-segment accretion)

     (27     (48

Income before income taxes

     $3,228       $1,059  

 Capital Expenditures Information

   Segment capital
expenditures1
 
    

For the three months ended

March 31

 
     
          2026         2025  

Carlin

     $184       $204  

Cortez

     116       100  

Turquoise Ridge

     28       21  

Pueblo Viejo

     115       87  

Loulo-Gounkoto

           18  

Kibali

     40       34  

Lumwana

     164       70  

North Mara

     50       40  

Bulyanhulu

     41       38  

Other Mines

     47       71  

Segment total

     $785       $683  

Other items not allocated to segments

     316       124  

Total

     $1,101       $807  

Share of equity investees

     (40     (34

Total

     $1,061       $773  

 

1 

Segment capital expenditures are presented for internal management reporting purposes on an accrual basis. Capital expenditures in the Consolidated Statements of Cash Flow are presented on a cash basis. For Q1 2026, cash expenditures were $979 million (Q1 2025: $837 million) and the increase in accrued expenditures was $82 million (2025: $64 million decrease).

Purchase Commitments

At March 31, 2026, we had purchase obligations for supplies and consumables of $3,829 million (December 31, 2025: $3,837 million).

Capital Commitments

In addition to entering into various operational commitments in the normal course of business, we had capital commitments of $2,030 million at March 31, 2026 (December 31, 2025: $2,329 million).

 

 

 

BARRICK FIRST QUARTER 2026   57    NOTES TO FINANCIAL STATEMENTS (UNAUDITED)


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

6   Revenue

 

 

      For the three months  
ended March 31  
 
     
      2026      2025    

Gold sales

    

Spot market sales1

     $4,549       $2,601    

Concentrate sales

     196       149    

Provisional pricing adjustments

     11       16    
     $4,756       $2,766    

Copper sales

           

Concentrate sales

     $210       $275    

Cathode and anode sales

     174       —    

Provisional pricing adjustments

     (41     29    
     $343       $304    

Other sales2

     119       60    

Total

     $5,218       $3,130    

 

1 

Includes realized losses on gold contracts of $42 million for Q1 2026 (Q1 2025: $nil). Refer to note 13 for further details.

2

Revenues include the sale of by-products for our gold and copper mines.

7 Cost of Sales

 

 

 

    Gold     Copper     Other3     Total  

 

  For the three months ended March 31

 

 

  2026

   

 

  2025

   

 

  2026

   

 

  2025

   

 

  2026

   

 

  2025

   

 

  2026

   

 

  2025  

 

Site operating costs1,2

    $1,179       $1,097       $143       $126       $—       $—       $1,322       $1,223    

Depreciation1

    449       342       43       60       8       9       500       411    

Royalty expense

    193       95       30       21                   223       116    

Mining and production taxes

    46       23                               46       23    

Community relations

    7       11       1       1                   8       12    
      $1,874       $1,568       $217       $208       $8       $9       $2,099       $1,785    

 

1 

Site operating costs and depreciation include charges to reduce the cost of inventory to net realizable value as follows: $31 million for Q1 2026 (Q1 2025: $1 million).

2 

Site operating costs includes the costs of extracting by-products.

3 

Other includes corporate amortization.

8  Earnings Per Share

 

 

 

     For the three months ended March 31   
   
     2026    2025  
       Basic     Diluted       Basic       Diluted  

Net income

     $2,481     $2,481       $781       $781  

Net income attributable to non-controlling interests

     (879   (879)      (307     (307

Net income attributable to equity holders of Barrick Mining Corporation

     $1,602     $1,602       $474       $474  

Weighted average shares outstanding

     1,675     1,675       1,725       1,725  

Basic and diluted earnings per share attributable to the equity holders of Barrick Mining Corporation

     $0.96     $0.96       $0.27       $0.27  

 

 

 

BARRICK FIRST QUARTER 2026   58    NOTES TO FINANCIAL STATEMENTS (UNAUDITED)


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

9  Other (Income) Expense

 

 

 

     For the three
months ended
March 31
 
     
      2026     2025  

Other expense:

    

Bank charges

     $1       $1  

Litigation legal expenses

     5       4  

Loulo-Gounkoto reduced operations costs1

     12       67  

Loss on Kibali JV Receivable

     46        

Litigation settlement accruals

           91  

Other

     (4     18  

Total other expense

     $60       $181  

Other income:

    

Loss on sale of non-current assets

     $1       $—  

Remeasurement of contingent consideration

     (55      

Interest income on other assets

     (10     (11
     

Total other income

     ($64     ($11

Total other (income) expense

     ($4     $170  

 

1 

2026 expenses relate to remobilization costs. Refer to note 4 for further details.

 

10  Income Tax Expense

 

 

 

     For the three months
ended March 31
 
     
      2026      2025  

Current

     $580        $287  

Deferred

     167        (9

Total

     $747        $278  

Income tax expense was $747 million for Q1 2026 (Q1 2025: $278 million). The unadjusted effective income tax rate for Q1 2026 was 23% of income before income taxes.

The underlying effective income tax rate on ordinary income for Q1 2026 was 22% after adjusting for the impact of foreign currency translation losses on current and deferred tax balances; the impact of updates to the rehabilitation provision for our non-operating mines; the impact of non-deductible foreign exchange losses; the impact of the remeasurement of the Hemlo contingent consideration; the impact of Loulo-Gounkoto; and the impact of other expense adjustments.

Currency Translation

Current and deferred tax balances are subject to remeasurement for changes in foreign currency exchange rates each period. This is required in countries where tax is paid in local currency and the subsidiary has a different functional currency (typically US dollars). The most significant balances relate to Argentine, Malian and Zambian tax balances.

In Q1 2026, a tax expense of $36 million (Q1 2025: $15 million tax recovery) arose primarily from net translation losses on current and deferred tax balances in Zambia and Mali, respectively due to the strengthening of

the Zambian Kwacha and weakening of the West African CFA. These were partially offset by translation gains on deferred tax balances in Argentina due to the strengthening of the Argentine peso against the US dollar.

These net translation losses are included within income tax expense.

Withholding Taxes

For Q1 2026, we have recorded $39 million (Q1 2025: $20 million related to Tanzania and the United States) of dividend withholding taxes related to the distributed earnings of our subsidiaries in Argentina, and undistributed earnings of our subsidiaries in Saudi Arabia and the United States.

United States Tax Reform

Under the Inflation Reduction Act signed in August 2022, the United States implemented a 15% corporate alternative minimum tax (“CAMT”) on applicable financial statement income, effective for tax years beginning after December 31, 2022, with CAMT credit carryforwards having an indefinite life. Barrick is subject to CAMT as it meets the requisite income thresholds for a foreign-parented multinational group.

Since its introduction, we have recognized a deferred tax asset (DTA) from the CAMT credit carryforwards, anticipating recovery against future US Federal Income Tax liabilities. In Q1 2026, the IRS outlined additional interim guidance on the CAMT to allow several new adjustments to adjusted financial statement income (AFSI) and modify the scope of certain AFSI adjustments in prior interim guidance. Given potential future developments, the timing and amount of such CAMT recovery may be subject to change pending issuance of final regulations.

Organization for Economic Co-operation and Development (“OECD”) Pillar Two model rules

These rules apply to multi-national enterprises with annual consolidated revenues of at least 750 million in at least two of the prior four fiscal years immediately preceding the relevant fiscal year, which is reflective of our status.

Canada enacted Pillar Two legislation in Q2 2024, effective for fiscal years commencing on or after December 31, 2023. Other jurisdictions in which the group operates have either enacted or are in the process of enacting similar legislation. In accordance with the Global Minimum Tax Act enacted in Canada, the Group is required to file its first GloBE Information Return and the related Canadian tax returns for the 2024 fiscal year by June 30, 2026.

In terms of the income tax accounting, we have applied the exception available under the amendments to IAS 12 published by the IASB in May 2023 and are not recognizing or disclosing information about deferred tax assets and liabilities related to Pillar Two income taxes. Our review of Pillar Two for the current year, based on the OECD’s Transitional Safe Harbour rules as implemented in the Global Minimum Tax Act in Canada, has not identified any material amounts to be accrued for Q1 2026. As the law is evolving, both in Canada and elsewhere, we will continue to monitor the impact of this legislation.

 

 

 

 

BARRICK FIRST QUARTER 2026   59    NOTES TO FINANCIAL STATEMENTS (UNAUDITED)


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

11  Cash Flow - Other Items

 

 

Operating Cash Flows – Other Items    For the three months 
ended March 31 
 
     
      2026     2025   

Adjustments for non-cash income statement items:

    

Loss on Kibali JV receivable

     $46       $—  

Share-based compensation expense

     38       42  

Inventory impairment charges

     16       1  

Non-cash revenue recognized on Pueblo Viejo gold and silver streaming agreement

     (8     (7

Change in estimate of rehabilitation costs at closed mines

     (15     10  

Remeasurement of contingent consideration

     (55      

Litigation settlement accruals

           91  

Change in other assets and liabilities

     (103     (42

Settlement of share-based compensation

     (140     (53

Settlement of rehabilitation obligations

     (35     (51

Other operating activities

     ($256     ($9

Cash flow arising from changes in:

    

Accounts receivable

     $73       $12  

Inventory

     (52     (67

Value added taxes receivable1

     (54     (60

Other current assets

     (14     (2

Accounts payable

     (250     (24

Other current liabilities

     (5     36  
     

Change in working capital

     ($302     ($105

 

1 

Excludes $20 million (Q1 2025: $17 million) for Q1 2026 of VAT receivables that were settled against offsetting of income taxes payable and $10 million (Q1 2025: $44 million) for Q1 2026 of VAT receivables that were settled against offsetting of other duties and liabilities.

12  Equity Accounting Method Investment Continuity

 

 

      Kibali     Jabal Sayid       Zaldívar       Porgera       Other       Total  

At January 1, 2025

     $2,015       $401       $875       $780       $41       $4,112  

Equity pick-up (loss) from equity investees

     203       139       (26     121             437  

Funds invested

                             1       1  

Dividends received from equity investees

     (67     (130                 (2     (199

Equity earnings adjustment

                       7             7  

Shareholder loan repayment

                       (138     (4     (142
             

At December 31, 2025

     $2,151       $410       $849       $770       $36       $4,216  

Equity pick-up (loss) from equity investees

     204       53       14       44       (1     314  

Dividends received from equity investees

     (60     (50                       (110

Equity earnings adjustment

                       2             2  

Shareholder loan repayment

                       (97           (97
             

At March 31, 2026

     $2,295       $413       $863       $719       $35       $4,325  

 

 

 

BARRICK FIRST QUARTER 2026   60    NOTES TO FINANCIAL STATEMENTS (UNAUDITED)


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

13  Financial Instruments

 

Financial instruments include cash; evidence of ownership in an entity; or a contract that imposes an obligation on one party and conveys a right to a second party to deliver/ receive cash or another financial instrument.

Gold Contracts

In Q3 2025, we entered into 25,000 ounces of zero cost gold collars that mature every month between September 2025 and August 2028 for a total of 900,000 ounces. These contracts contain purchased put and sold call options with strike prices of $3,100/oz and $4,310/oz, respectively. These contracts are designated as cash flow hedges, with the effective portion of the hedge recognized in other comprehensive income and the ineffective portion recognized as loss (gain) on non-hedge derivatives. The realized loss related to these positions is $42 million for Q1 2026 (Q1 2025: $nil) and was recorded in revenue. As at March 31, 2026, the fair value of the remaining derivatives is a loss of $529 million (December 31, 2025: $386 million), with $165 million recorded as other current liabilities and $364 million recorded as other non-current liabilities (December 31, 2025: $89 million and $297 million, respectively). As at March 31, 2026, 725,000 ounces of gold collars remain outstanding.

14  Fair Value Measurements 

 

a) Assets and Liabilities Measured at Fair Value on a Recurring Basis

 

 As at March

 31, 2026

 

Quoted

prices in

active

markets
for
identical
assets

 

(Level 1)

   

Significant
other
observable
inputs

 

(Level 2)

   

Significant
unobservable
inputs

 

(Level 3)

   

Aggregate
fair value

 

 

Other investments1

    $47       $—       $—       $47  

Derivatives2

          (529           (529

Receivables from provisional copper and gold sales

          249             249  

Receivable from NOVAGOLD

                171       171  

Contingent consideration3

                296       296  
         
      $47       ($280     $467       $234  

 

1

Includes equity investments in other mining companies.

2

Refer to note 13 for further details.

3

Primarily includes contingent consideration relating to the Tongon mine, Norte Abierto project, Hemlo mine and Alturas project.

b) Fair Values of Financial Assets and Liabilities

 

      As at March 31, 2026      As at December 31,
2025
 
      Carrying
amount
     Estimated
fair value
     Carrying
amount
     Estimated
fair value
 

Financial assets

           

Other assets1

     $932        $932        $940        $940  

Other investments2

     47        47        131        131  

Contingent consideration3

     296        296        240        240  
       $1,275        $1,275        $1,311        $1,311  

Financial liabilities

           

Debt4

     $4,726        $4,889        $4,703        $4,970  

Derivative liabilities5

     529        529        386        386  

Other liabilities

     801        801        803        803  
       $6,056        $6,219        $5,892        $6,159  

 

  1 

Includes restricted cash and amounts due from our partners.

  2 

Includes equity investments in other mining companies. Recorded at fair value. Quoted market prices are used to determine fair value.

  3 

Primarily includes contingent consideration relating to the Tongon mine, Norte Abierto project, Hemlo mine and Alturas project.

  4 

Debt is generally recorded at amortized cost. The fair value of debt is primarily determined using quoted market prices. Balance includes both current and long-term portions of debt.

  5 

Refer to note 13 for further details.

The Company’s valuation techniques for our remaining financial assets and liabilities were presented in Note 26 of the 2025 Annual Financial Statements and have been consistently applied in these interim financial statements.

15  Capital Stock

 

a) Authorized Capital Stock

Our authorized capital stock is composed of an unlimited number of common shares (issued 1,675,508,360 common shares as at March 31, 2026). Our common shares have no par value.

b) Dividends

The Company’s practice has been to declare dividends after a quarter as part of the announcement of the results for the quarter. Dividends declared are paid in the same quarter.

The Company’s dividend reinvestment plan resulted in 147,965 common shares being issued to shareholders for YTD 2026.

At the May 8, 2026 meeting, the Board of Directors authorized a dividend of $0.175 per share (approximately $300 million dollars) to be paid on June 15, 2026 to shareholders of record at the close of business on May 29, 2026.

c) Share Buyback Program

At the May 8, 2026 meeting, the Board of Directors authorized a new share buyback program for the purchase of up to $3 billion of Barrick’s outstanding common shares over the next 12 months.

The actual number of common shares that may be purchased, and the timing of any such purchases, will be determined by Barrick based on a number of factors, including the Company’s financial performance, the availability of cash flows, and the consideration of other

 

 

 

 

BARRICK FIRST QUARTER 2026   61    NOTES TO FINANCIAL STATEMENTS (UNAUDITED)


OVERVIEW  

OPERATING

PERFORMANCE

 

  FUTURE GROWTH  

REVIEW OF FINANCIAL

RESULTS

 

  OTHER INFORMATION &
NON-GAAP
RECONCILIATIONS
 

FINANCIAL

STATEMENTS

 

uses of cash, including capital investment opportunities, returns to shareholders, and debt reduction.

The repurchase program does not obligate the Company to acquire any particular number of common shares, and the repurchase program may be suspended or discontinued at any time at the Company’s discretion.

 

 

16 Non-controlling Interests Continuity

 

 

      Nevada
Gold Mines
     Pueblo
Viejo
     Tanzania
Mines1
     Loulo-
Gounkoto
     Tongon2      Reko Diq      Other      Total  

NCI in subsidiary at March 31, 2026

     38.5 %        40 %        16 %        20 %        —         50 %        Various           

At January 1, 2025

     $6,379          $1,160          $375          $695          $16         $421          ($80)        $8,966   

Share of income (loss)

     1,851          272          95          (57)          10         (10)          —         2,161   

Cash contributed

     —          —          —          —          —         362          —         362   

Loss of control3

     —          —          —          (686)          —         —          —         (686)  

Acquisitions (divestitures)3

     —          —          —          404          (19)        —          —         385   

Disbursements

     (1,579)          (168)          (75)          —          (7)        —          —         (1,829)  

At December 31, 2025

     $6,651          $1,264          $395          $356          $—         $773          ($80)        $9,359   

Share of income (loss)

     736          97          26          21          —         (1)          —         879   

Cash contributed

     —          —          —          —          —         122          —         122   

Disbursements

     (814)          (112)          —          —          —         —          —         (926)  
                 

At March 31, 2026

     $6,573          $1,249          $421          $377          $—         $894          ($80)        $9,434   

 

1

Tanzania mines consist of the two operating mines, North Mara and Bulyanhulu.

2

On October 6, 2025, we reached an agreement to sell our interest in the Tongon gold mine and certain of its exploration properties to the Atlantic Group for total consideration of up to $305 million. The transaction closed on December 1, 2025.

3 

Refer to note 4 for further details.

17 Contingencies

 

Certain conditions may exist as of the date the financial statements are issued that may result in a loss to the Company, but which will only be resolved when one or more future events occur or fail to occur. The impact of any resulting loss from such matters affecting these financial statements and noted below may be material.

Except as noted below, no material changes have occurred with respect to the matters disclosed in Note 36 “Contingencies” to the 2025 Annual Financial Statements, and no new contingencies have occurred that are material to the Company since the issuance of the 2025 Annual Financial Statements.

The description set out below should be read in conjunction with Note 36 “Contingencies” to the 2025 Annual Financial Statements.

Litigation and Claims Update

Pascua-Lama — Proposed Canadian Securities Class Actions

In the Ontario proceeding, the Superior Court of Justice for Ontario issued its decision on the plaintiffs’ motion for class certification on March 4, 2026. The Court certified the plaintiffs’ statutory secondary market and common law misrepresentation claims but declined to certify the plaintiffs’ primary market claims.

In the Quebec proceeding, both parties have delivered expert reports. Trial is scheduled for April 18 to May 15, 2028.

North Mara - Ontario Litigation

On April 7, 2026, the Court of Appeal for Ontario dismissed the plaintiffs’ appeal, upholding Barrick’s motion to dismiss both actions on the grounds that Tanzania is a more appropriate forum in which to litigate this matter. The plaintiffs have 60 days from the date of the Court of Appeal judgment to file an application for leave to appeal to the Supreme Court of Canada.

Loulo-Gounkoto Mining Conventions Dispute

Further to the terms of the settlement agreement announced on November 24, 2025, the 10-year renewal of the Somilo Exploitation Permit was granted under the 2023 Mining Code on February 13, 2026. Also further to the settlement agreement, the senior judge at the Pôle National Économique et Financier issued a ruling dated March 25, 2026 dismissing the criminal proceedings previously issued against Somilo, Gounkoto and certain individuals. This matter is now closed.

In addition, pursuant to a tax reconciliation process contemplated by the settlement agreement, a total of $200 million was paid to the Government of Mali in April 2026 in respect of additional royalties, penalties and interest related to the application of the 2023 Mining Code to Loulo-Gounkoto for 2024 and 2025. 

 

 

 

 

BARRICK FIRST QUARTER 2026   62    NOTES TO FINANCIAL STATEMENTS (UNAUDITED)


 

 

Shares Listed

B    The New York Stock Exchange
ABX     The Toronto Stock Exchange

Transfer Agents and Registrars

TSX Trust Company

301 – 100 Adelaide Street West

Toronto, Ontario M5H 4H1

or

Equiniti Trust Company, LLC

48 Wall Street

New York, New York 10043

Telephone: 1 800 387 0825

Fax: 1 888 249 6189

Email: shareholderinquiries@tmx.com

Website: www.tsxtrust.com

 

 Barrick Mining Corporation

Telephone: +1 416 861 9911

Email: investor@barrick.com

Website: www.barrick.com

161 Bay Street, Suite 3700

Toronto, Ontario M5J 2S1

310 South Main Street, Suite 1150

Salt Lake City, Utah 84101

 Enquiries

Investor Relations Contact

Cleve Rueckert, +1 775 397 5443

Email: cleveland.rueckert@barrick.com

Media Contact

Brunswick Group

Carole Cable, +44 (0) 20 7404 5959

Email: barrick@brunswickgroup.com

 

 

Cautionary Statement on Forward-Looking Information

 

 

 

Certain information contained or incorporated by reference in this MD&A, including any information as to our strategy, projects, plans or future financial or operating performance, constitutes “forward-looking statements”. All statements, other than statements of historical fact, are forward-looking statements. The words “believe”, “expect”, “anticipated”, “aim”, “strategy”, “ramp up”, “target”, “plan”, “opportunities”, “guidance”, “forecast”, “outlook”, “project”, “intend”, “develop”, “progress”, “continue”, “temporary”, “estimate”, “potential”, “future”, “focus”, “ongoing”, “following”, “subject to”, “scheduled”, “may”, “will”, “can”, “could”, “would”, “should” and similar expressions identify forward-looking statements. In particular, this MD&A contains forward-looking statements including, without limitation, with respect to: Barrick’s forward-looking production and cost guidance, including our ability to meet our 2026 guidance; anticipated production growth from Barrick’s organic project pipeline and reserve replacement; estimates of future cost of sales per ounce for gold and per pound for copper, total cash costs per ounce and C1 cash costs per pound, and all-in sustaining costs per ounce/ pound; cash flow forecasts; projected capital, operating and exploration expenditures; the share buyback program and performance dividend policy; mine life and production rates; anticipated timing for development of the Goldrush Project; our plans, timelines, and expected completion and benefits of our growth projects, including the Goldrush Project, Fourmile, Ren, Pueblo Viejo plant expansion and mine life extension project, Veladero Phase 8 Leach Pad, Reko Diq, solar power project at Kibali, and the Lumwana Super Pit Expansion; anticipated production at Goldrush, Ren, Reko Diq and Lumwana; timing for first production from the Lumwana Super Pit Expansion; Barrick’s decision to slow development activity at Reko Diq capital expenditures related to upgrades and ongoing management initiatives;

Barrick’s global exploration strategy and planned exploration activities; Barrick’s copper strategy; the resumption of operations at Loulo-Gounkoto following the resolution of disputes with the Government of Mali, including adoption of the 2023 Mining Code; our pipeline of high confidence projects at or near existing operations; our ability to identify new Tier One assets and the potential for existing assets to attain Tier One status, including Fourmile; the incorporation of Fourmile into the NGM joint venture at fair market value; potential mineralization and metal or mineral recoveries; Barrick’s intention to pursue and the expected timing for and potential benefits of an initial public offering (“IPO”) of Barrick’s North American gold assets; the structure and the ability of the IPO to generate significant value for Barrick and Newmont; our ability to convert resources into reserves and future reserve replacement; asset sales, joint ventures and partnerships; Barrick’s strategy, plans, targets and goals in respect of sustainability issues, including climate change, greenhouse gas (“GHG”) emissions reduction targets, human rights, safety performance, community development and resettlement, and responsible water use; and expectations regarding future price assumptions, financial performance and other outlook or guidance.

Forward-looking statements are necessarily based upon a number of estimates and assumptions including material estimates and assumptions related to the factors set forth below that, while considered reasonable by the Company as at the date of this MD&A in light of management’s experience and perception of current conditions and expected developments, are inherently subject to significant business, economic and competitive uncertainties and contingencies. Known and unknown factors could cause actual results to differ materially from those projected in the forward-looking statements and

 

 

 


 

 

undue reliance should not be placed on such statements and information. Such factors include, but are not limited to: fluctuations in the spot and forward price of gold, copper or certain other commodities (such as silver, diesel fuel, natural gas and electricity); risks associated with projects in the early stages of evaluation and for which additional engineering and other analysis is required; risks related to the possibility that future exploration results will not be consistent with the Company’s expectations, that quantities or grades of reserves will be diminished, and that resources may not be converted to reserves; risks associated with the fact that certain of the initiatives described in this MD&A are still in the early stages and may not materialize; changes in mineral production performance, exploitation and exploration successes; risks that exploration data may be incomplete and considerable additional work may be required to complete further evaluation, including but not limited to drilling, engineering and socioeconomic studies and investment; the speculative nature of mineral exploration and development; lack of certainty with respect to foreign legal systems, corruption and other factors that are inconsistent with the rule of law; changes in national and local government legislation, taxation, controls or regulations and/or changes in the administration of laws, policies and practices, including the expropriation or nationalization of property and political or economic developments in Canada, the United States, or other countries in which Barrick does or may carry on business in the future; risks relating to the proposed initial public offering of an entity that will hold Barrick’s North American assets; risks relating to political instability in certain of the jurisdictions in which Barrick operates; timing of receipt of, or failure to comply with, necessary permits and approvals; non-renewal of key licenses by governmental authorities; failure to comply with environmental and health and safety laws and regulations; increased costs and physical and transition risks related to climate change, including extreme weather events, resource shortages, emerging policies and increased regulations related to GHG emission levels, energy efficiency and reporting of risks; the Company’s ability to achieve its sustainability goals, including its climate-related goals and GHG emissions reduction targets, in particular its ability to achieve its Scope 3 emissions targets which require reliance on entities within Barrick’s value chain, but outside of the Company’s direct control, to achieve such targets within the specified time frames; contests over title to properties, particularly title to undeveloped properties, or over access to water, power and other required infrastructure; the liability associated with risks and hazards in the mining industry, and the ability to maintain insurance to cover such losses; damage to the Company’s reputation due to the actual or perceived occurrence of any number of events, including negative publicity with respect to the Company’s handling of environmental matters or dealings with community groups, whether true or not; risks related to operations near communities that may regard Barrick’s operations as being detrimental to them; litigation and legal and administrative proceedings; operating or technical difficulties in connection with mining or development activities, including geotechnical challenges, tailings dam and storage facilities failures, and disruptions in the maintenance or provision of required infrastructure and information technology systems; increased costs, delays, suspensions and technical challenges associated with the construction of capital projects; risks associated with working with partners in jointly controlled assets; risks related to disruption of supply routes which may cause delays in construction and mining activities, including disruptions in the supply of key mining inputs due to the invasion of Ukraine by Russia and 

conflicts in the Middle East; risk of loss due to acts of war, terrorism, sabotage and civil disturbances; risks associated with artisanal and illegal mining; risks associated with Barrick’s infrastructure, information technology systems and the implementation of Barrick’s technological initiatives, including risks related to cybersecurity incidents, including those caused by computer viruses, malware, ransomware and other cyberattacks, or similar information technology system failures, delays and/or disruptions; the impact of global liquidity and credit availability on the timing of cash flows and the values of assets and liabilities based on projected future cash flows; the impact of inflation, including global inflationary pressures driven by ongoing global supply chain disruptions, global energy cost increases following the invasion of Ukraine by Russia and country-specific political and economic factors in Argentina and uncertainty related to Venezuela; adverse changes in our credit ratings; fluctuations in the currency markets; changes in U.S. dollar interest rates; changes in U.S. trade, tariff and other controls on imports and exports, tax, immigration or other policies that may impact relations with foreign countries, result in retaliatory policies, lead to increased costs for raw materials and components, or impact Barrick’s existing operations and material growth projects; risks arising from holding derivative instruments (such as credit risk, market liquidity risk and mark-to-market risk); risks related to the demands placed on the Company’s management, the ability of management to implement its business strategy and enhanced political risk in certain jurisdictions; uncertainty whether some or all of Barrick’s targeted investments and projects will meet the Company’s capital allocation objectives and internal hurdle rate; whether benefits expected from recent transactions are realized; business opportunities that may be presented to, or pursued by, the Company; our ability to successfully integrate acquisitions or complete divestitures; risks related to competition in the mining industry; employee relations including loss of key employees; availability and increased costs associated with mining inputs and labor; risks associated with diseases, epidemics and pandemics; risks related to the failure of internal controls; and risks related to the impairment of the Company’s goodwill and assets. In addition, there are risks and hazards associated with the business of mineral exploration, development and mining, including environmental hazards, industrial accidents, unusual or unexpected formations, pressures, cave-ins, flooding and gold bullion, copper cathode or gold or copper concentrate losses (and the risk of inadequate insurance, or inability to obtain insurance, to cover these risks).

Many of these uncertainties and contingencies can affect our actual results and could cause actual results to differ materially from those expressed or implied in any forward-looking statements made by, or on behalf of, us. Readers are cautioned that forward-looking statements are not guarantees of future performance. All of the forward-looking statements made in this MD&A are qualified by these cautionary statements. Specific reference is made to the most recent Form 40-F/Annual Information Form on file with the SEC and Canadian provincial securities regulatory authorities for a more detailed discussion of some of the factors underlying forward-looking statements and the risks that may affect Barrick’s ability to achieve the expectations set forth in the forward-looking statements contained in this MD&A. We disclaim any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by applicable law.

 

 

 

Filing Exhibits & Attachments

2 documents