Idaho Copper estimates CuMo's after-tax NPV at $1.88B

Available on EDGAR Accepted by SEC EDGAR Learn about SEC filing dates
(High)

Sentiment and the balance of points

Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

Form Type
8-K

Rhea-AI Filing Summary

Idaho Copper Corp. (COPR) reported a preliminary S-K 1300 Initial Assessment for CuMo, estimating a Base Case after-tax NPV of US$1,878 million at an 8% discount rate and after-tax IRR of 18.50%. The M&I Case excludes Inferred Mineral Resources from processing and revenue and estimates after-tax NPV of US$1,482 million.

The Base Case lists US$2,521 million in total project capital and US$16,247 million in operating expenditure, with mill processing planned through Year 46. Inferred material is 156 million short tons, or 13.9% of 1,127 million short tons of evaluated mill feed; that is a feed-mass share, not a share of revenue or NPV. On the fixed production schedule, a 10% molybdenum-price decrease reduces pre-tax NPV at 8% to US$1,633 million; a separate 10% operating-cost increase reduces it to US$1,815 million.

Estimates are preliminary, with approximately ±50% accuracy for capital and operating costs, and do not establish Mineral Reserves; there is no certainty the assessment will be realized. The Mineral Resource estimate remains effective August 30, 2018, while new exploration drilling began October 4, 2026. Mineral sorting is not a mature technology at this mine scale, and its assumed performance may not prove accurate.

Positive

  • None.

Negative

  • Minor pointCapital and operating cost estimates have estimated accuracy of approximately ±50%.

Filing Explained

The report records September 9, 2026 approval of exploration work, but no applications for mine permits; active litigation challenges the March 14, 2025 exploration decision, so disclosed authorization remains exploration, not mine development.

Item 2.02 Results of Operations and Financial Condition Financial
Disclosure of earnings results, typically an earnings press release or preliminary financials.
Item 9.01 Financial Statements and Exhibits Exhibits
Financial statements, pro forma financial information, or exhibit attachments filed with this report.
Base Case after-tax NPV US$1,878 million At an 8% discount rate; includes Measured, Indicated and Inferred Mineral Resources.
M&I Case after-tax NPV US$1,482 million At an 8% discount rate; excludes Inferred Mineral Resources from processing and revenue.
Base Case after-tax IRR 18.50% Project economic analysis.
Total project capital US$2,521 million Base Case.
Operating expenditure US$16,247 million Base Case total over the project life; excludes preproduction expenditure included in capital.
Evaluated mill feed 1,127 million short tons Base Case including Inferred Mineral Resources.
Inferred share of evaluated mill feed 13.9% Feed-mass proportion; not a share of revenue or NPV.
Estimated cost accuracy Approximately ±50% Capital and operating cost estimates; the accuracy range is not a statistical confidence interval.
net present value (NPV) financial
"Net present value (NPV) is the sum of discounted project cash flows"
Net present value (NPV) measures the current worth of a series of future cash flows from an investment after subtracting the money put in today, using an interest rate to reflect time and risk. Investors use NPV to decide whether a project should go ahead: a positive NPV means the expected returns are worth more than the cost, like choosing between getting cash now or a bigger, but less valuable, pile of money later once you account for time and uncertainty.
internal rate of return (IRR) financial
"The internal rate of return (IRR) is the discount rate at which NPV is zero"
The internal rate of return (IRR) is the annualized percentage return that makes the total value of a project's or investment's future cash flows equal the amount invested today — in other words, the break-even interest rate for that investment. Investors use IRR like a single-number speedometer to compare opportunities: a higher IRR means a project is expected to generate a stronger annual return, helping decide which investments are likely more attractive relative to required returns or alternatives.
Inferred Mineral Resources technical
"The IA is preliminary in nature and includes Inferred Mineral Resources"
An inferred mineral resource is an estimate of the quantity and grade of minerals in the ground based on limited sampling and geological information, where confidence is low and continuity is uncertain. For investors it signals potential value but also higher risk—like a rough sketch of a hidden treasure that requires much more exploration and testing before you can reliably judge its size or economic worth.
Mineral Reserves technical
"Mineral Resources are not Mineral Reserves"
Mineral reserves are the amounts of a metal or mineral that a company has identified and can legally and economically extract with current technology. Think of it like the usable fuel in a car’s tank rather than all the oil in the ground; reserves determine how long a mine can produce, help estimate future revenue and costs, and shape a company’s value and investment risk.
recoverable value (RCV) technical
"recoverable value (RCV) was calculated for each block"
bulk ore sorting (BOS) technical
"bulk ore sorting (BOS) stage 1 system"

FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

What after-tax NPV did COPR estimate for the CuMo project?

The Base Case estimates after-tax NPV of US$1,878 million at an 8% discount rate. The M&I Case, which excludes Inferred Mineral Resources from processing and revenue, estimates US$1,482 million; both are preliminary project-evaluation figures.

How sensitive is COPR's CuMo assessment to lower molybdenum prices?

A 10% molybdenum-price decrease reduces pre-tax NPV at 8% to US$1,633 million. Separately, a 10% operating-cost increase reduces it to US$1,815 million; both sensitivities use the fixed production schedule.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google
false 0001263364 0001263364 2026-11-19 2026-11-19 0001263364 COPR:CommonStockParValue0.001PerShareMember 2026-11-19 2026-11-19 0001263364 COPR:CommonStockPurchaseWarrantMember 2026-11-19 2026-11-19 iso4217:USD xbrli:shares iso4217:USD xbrli:shares

 

 

 

UNITED STATES

SECURITIES AND EXCHANGE COMMISSION

Washington, D.C. 20549

 

FORM 8-K

 

CURRENT REPORT

Pursuant to Section 13 or 15(d) of the Securities Exchange Act of 1934

 

Date of Report: November 19, 2026

 

IDAHO COPPER CORPORATION

(Exact name of Registrant as specified in its Charter)

 

Nevada   001-43386   98-0221494

(State or Other Jurisdiction

of Incorporation)

 

(Commission

File Number)

 

(I.R.S. Employer

Identification No.)

 

800 W. Main Street, Suite 1460, Boise, Idaho 83702

(Address of Principal Executive Offices)

 

208-274-9220

(Registrant’s Telephone Number, including area code)

 

Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the Registrant under any of the following provisions (see general instruction A.2. below):

 

☐ Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)
   
☐ Soliciting material pursuant to Rule 14-a-12 under the Exchange Act (17 CFR 240.14a-12)
   
☐ Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))
   
☐ Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))

 

Securities registered pursuant to Section 12(b) of the Act:

 

Title of each class   Trading Symbols(s)   Name of each exchange on which registered
Common Stock, par value $0.001 per share   COPR   NYSE American LLC
Common Stock Purchase Warrant   COPR WS   NYSE American LLC

 

Indicate by check mark whether the registrant is an emerging growth company as defined in Rule 405 of the Securities Act of 1933 (§230.405 of this chapter) or Rule 12b-2 of the Securities Exchange Act of 1934 (§240.12b-2 of this chapter).

 

Emerging growth company ☐

 

If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act. ☐

 

 

 

 

 

 

Item 2.02. Results of Operations and Financial Condition.

 

On November 19, 2026, Idaho Copper Corporation (the “Company”) received an Initial Assessment and S-K 1300 Technical Report Summary (the “Report”). A copy of the Report and consents of the qualified persons in connection with the Report are filed as exhibits 99.1 and 23.1 and incorporated by reference herein.

 

Item 9.01. Financial Statements and Exhibits.

 

(d) Exhibits

 

Exhibit No.   Description
     
23.1   Consents of Qualified Persons in connection with Initial Assessment and S-K 1300 Technical Report Summary
     
99.1   Initial Assessment and S-K 1300 Technical Report Summary dated October 29, 2026
     
104   Cover Page Interactive Data File (embedded within the Inline XBRL Document)

 

 

 

 

SIGNATURES

 

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned thereunto duly authorized.

 

Date: November 23, 2026

 

  IDAHO COPPER CORPORATION
     
  By: /s/ Robert Scannell
  Name: Robert Scannell
  Title: Executive Chairman

 

 

 

 

Exhibit 99.1

 

 

 

 

 

 

Important Notice

 

This Report was prepared for Idaho Copper Corp. by the qualified persons (QPs) identified in the Report’s Date and Signature Page.

 

This Report contains estimates, projections, and conclusions that are forward-looking information within the meaning of applicable securities laws. Forward-looking statements are based upon the responsible QPs’ opinion at the time that they are made but, in most cases, involve significant risk and uncertainty.

 

Although each of the responsible QPs has attempted to identify factors that could cause actual events or results to differ materially from those described in this Report, there may be other factors that cause events or results to not be as anticipated, estimated or projected. None of the QPs undertake any obligation to update the forward-looking information.

 

This Report is intended to be used by Idaho Copper Corp. subject to the terms and conditions of its contracts with each of the QPs. Except for the purposes legislated under United States securities law, any use of, or reliance on, this Report by any third party is at that party’s sole risk.

 

barr.com

 

i

 

 

 

Date and Signature Page

 

This technical report summary and initial assessment is effective as of the 14th day of October, 2026. This report is complete as of October 29, 2026.
 
Original signed and sealed on file    

Daniel R. Palo, PE

On behalf of Barr Engineering Co.

Sections 1-5, Section 10, Section 13.2.3, Section 13.3, Section 14, Sections 15-17, Sections 18.1.2 – 18.1.7, Sections 18.2.2 – 18.2.4, Sections 20-25

  Date
     
Original signed and sealed on file    

Justin L. Smith, PE, SME-RM

On behalf of Northern Lights Mining, LLC

Section 13 (except 13.2.3 and 13.3), Section 18.1.1, Section 18.2.1, Section 18.1 and 18.2 (integrated cost summaries only), Section 19

  Date
     
Original signed and sealed on file    

Gareth Flitton, CPG, Pr.Sci.Nat.

On behalf of Dahrouge Geological Consulting USA LTD.

Sections 6-9

  Date
     
Original signed and sealed on file    

Jacob Anderson, CPG
On behalf of Dahrouge Geologic Consulting Ltd.

Sections 11-12

  Date

 

barr.com

 

ii

 

 

 

Consent of Qualified Person

 

I, Daniel R. Palo, PE, on behalf of Barr Engineering Co., hereby consent to:

 

1.The inclusion of Barr Engineering Co., and associated Qualified Persons in connection with Idaho Copper Corporations’ anticipated filing of the initial assessment titled “Idaho Copper CuMo Project S-K 1300 Initial Assessment” dated October 28, 2026, as an exhibit to and referenced in Form 10-K/Form 8-K/or other filing, prepared in accordance with Item 601(b)(96) of Regulation S-K (17 CFR §229.601 (b)(96)) and Subpart 1300 of Regulation S-K.
   
2.The incorporation, by reference, of the Report, in the above filing, or any other periodic reports filed by the company, and to the extent practicable in the Registration Statements on any of the associated forms prepared in relation to the filing mentioned above.
   
3.The information derived, summarized, quoted, or referenced from the Report, or portions thereof, that was prepared by use, that we supervised in the preparation of, and/or that was reviewed and approved by us, that is included or incorporated by reference in any of the forms associated with the above-mentioned filing, other periodic reports, or the Registration Statements.

 

Barr Engineering Co. is responsible for authoring, and this consent pertains to, the following Sections of the Initial Assessment: Sections 1-5, Section 10, Section 13.2.3, Section 13.3, Sections 14-17, Sections 18.1.2 – 18.1.7, Sections 18.2.2 – 18.2.4, Sections 20-25

 

Report Effective Date: October 14, 2026.

 

“ORIGINAL SIGNED AND SEALED BY AUTHOR AND ON FILE”

 

Name: Daniel R. Palo  
   
Title: Vice President  
   
Company: Barr Engineering Co.  

 

 

 

 

 

Consent of Qualified Person

 

I, Justin L. Smith , P.E., SME-RM on behalf of Northern Lights Mining, LLC., hereby consent to:

 

1.The inclusion of Northern Lights Mining, LLC., and associated Qualified Persons in connection with Idaho Copper Corporations’ anticipated filing of the initial assessment titled “Idaho Copper CuMo Project S-K 1300 Initial Assessment” dated October 28, 2026, as an exhibit to and referenced in Form 10-K/Form 8-K/or other filing, prepared in accordance with Item 601(b)(96) of Regulation S-K (17 CFR §229.601 (b)(96)) and Subpart 1300 of Regulation S-K.
   
2.The incorporation, by reference, of the Report, in the above filing, or any other periodic reports filed by the company, and to the extent practicable in the Registration Statements on any of the associated forms prepared in relation to the filing mentioned above.
   
3.The information derived, summarized, quoted, or referenced from the Report, or portions thereof, that was prepared by use, that we supervised in the preparation of, and/or that was reviewed and approved by us, that is included or incorporated by reference in any of the forms associated with the above mentioned filing, other periodic reports, or the Registration Statements.

 

Northern Lights Mining, LLC. is responsible for authoring, and this consent pertains to, the following Chapters of the initial assessment: Section 13 (except subsections 13.2.3 and 13.3), subsection 18.1.1, subsection 18.2.1, subsection 18.1 and 18.2 (integrated cost summaries only), Section 19.

 

Report Effective Date: October 14, 2026.

 

By: “ORIGINAL SIGNED AND SEALED BY AUTHOR AND ON FILE”
   
Name: Justin L. Smith  
     
Title: Principal  
     
Company: Northern Light Mining, LLC.  

  

 

 

 

 

Consent of Qualified Person

 

I, Gareth Flitton , CPG, Pr. Sci. Nat. on behalf of Dahrouge Geological Consulting, hereby consent to:

 

1.The inclusion of Dahrouge Geological Consulting, and associated Qualified Persons in connection with Idaho Copper Corporations’ anticipated filing of the initial assessment titled “Idaho Copper CuMo Project S-K 1300 Initial Assessment” dated October 28, 2026, as an exhibit to and referenced in Form 10-K/Form 8-K/or other filing, prepared in accordance with Item 601(b)(96) of Regulation S-K (17 CFR §229.601 (b)(96)) and Subpart 1300 of Regulation S-K.
2.The incorporation, by reference, of the Report, in the above filing, or any other periodic reports filed by the company, and to the extent practicable in the Registration Statements on any of the associated forms prepared in relation to the filing mentioned above.
3.The information derived, summarized, quoted, or referenced from the Report, or portions thereof, that was prepared by use, that we supervised in the preparation of, and/or that was reviewed and approved by us, that is included or incorporated by reference in any of the forms associated with the above mentioned filing, other periodic reports, or the Registration Statements.

 

Dahrouge Geological Consulting is responsible for authoring, and this consent pertains to, the following Chapters of the initial assessment: Chapters 6-9.

 

Report Effective Date: October 14, 2026.

 

By: “ORIGINAL SIGNED AND SEALED BY AUTHOR AND ON FILE”
   
Name: Gareth Flitton  
     
Title: Senior Geologist  
     
Company: Dahrouge Geological Consulting.  

 

 

 

 

 

Consent of Qualified Person

 

I, Jacob Anderson , CPG, MAusIMM on behalf of Dahrouge Geological Consulting, hereby consent to:

1.The inclusion of Dahrouge Geological Consulting, and associated Qualified Persons in connection with Idaho Copper Corporations’ anticipated filing of the initial assessment titled “Idaho Copper CuMo Project S-K 1300 Initial Assessment” dated October 28, 2026, as an exhibit to and referenced in Form 10-K/Form 8-K/or other filing, prepared in accordance with Item 601(b)(96) of Regulation S-K (17 CFR §229.601 (b)(96)) and Subpart 1300 of Regulation S-K.
2.The incorporation, by reference, of the Report, in the above filing, or any other periodic reports filed by the company, and to the extent practicable in the Registration Statements on any of the associated forms prepared in relation to the filing mentioned above.
3.The information derived, summarized, quoted, or referenced from the Report, or portions thereof, that was prepared by use, that we supervised in the preparation of, and/or that was reviewed and approved by us, that is included or incorporated by reference in any of the forms associated with the above mentioned filing, other periodic reports, or the Registration Statements.

 

Dahrouge Geological Consulting is responsible for authoring, and this consent pertains to, the following Chapters of the initial assessment: Chapters 11 - 12.

 

Report Effective Date: October 14, 2026.

 

By: “ORIGINAL SIGNED AND SEALED BY AUTHOR AND ON FILE”
   
Name: Jacob Anderson  
     
Title: Resource Geologist  
     
Company: Dahrouge Geological Consulting.  

  

 

 

 

 

Initial Assessment and

S-K 1300 Technical Report Summary

 

October 2026

 

Contents

 

1 Executive Summary 1
     
1.1 Introduction 1
1.2 Property Description, History, and Ownership 1
1.3 Exploration 2
1.4 Geology and Mineralization 2
1.5 Mineral Resource Estimate 2
1.6 Project Development and Operations 6
1.7 Social and Environmental 7
1.8 Project Costs 8
1.9 Project Economics 10
1.10 Project Risks 11
1.11 Project Opportunities 16
1.12 Conclusions and Recommendations 21
     
2 Introduction 29
     
2.1 Issuer 29
2.2 Terms of Reference 29
2.3 Responsibility 29
2.4 Work Program – Initial Assessment 30
2.5 Basis of Technical Report 30
2.6 Site Visit 31
     
3 Property Description 32
     
3.1 General 32
3.2 Mineral Tenure 32
3.3 Ownership Agreements 32
3.4 Environmental 39
3.5 Permits 40
     
4 Accessibility, Climate, Local Resources, Infrastructure, and Physiography 41

 

barr.com

 

iii

 

 

 

5 History 43
     
5.1 Exploration 43
5.2 Historical Resource Estimate 47
     
6 Geological Setting, Mineralization, and Deposit 48
     
6.1 Regional Geology 48
6.2 Local Geology 51
6.3 Property Geology 54
6.4 Mineralization 56
6.5 Deposit Types 63
     
7 Exploration 64
     
7.1 Historical Work 64
7.2 Overview 64
7.3 Drill Programs by Year 65
7.4 General Drilling Discussion 67
7.5 Drilling Procedures 70
     
8 Sample Preparation, Analyses, and Security 80
     
8.1 General Sampling 80
8.2 Density Determinations 81
8.3 Assay Techniques 82
8.4 Current Core Storage 83
8.5 QA/QC Programs 85
8.6 Survey Validation 104
8.7 Verification of Drilling Data 104
     
9 Data Verification 105
     
10 Mineral Processing and Metallurgical Testing 106
     
10.1 Metallurgical Testing (2025 and 2026) 106
10.2 Metallurgical Testing (2009, 2015) 108
10.3 Application of Ore Mineral Sorting 116
     
11 Mineral Resource Estimates 124
     
11.1 Introduction 124
11.2 Data Analysis 124
11.3 50-Foot Composites 129
11.4 Variography 130
11.5 Block Model and Grade Estimation 131
11.6 Bulk Density 135
11.7 Reasonable Prospects for Economic Extraction 135
11.8 Resource Classification 136
11.9 Recovered Value 137
11.10 Mineral Resource Estimate 139

 

barr.com

 

iv

 

 

 

12 Mineral Reserve Estimates 142
     
13 Mining Methods 143
     
13.1 Mining Overview and Method 143
13.2 Baseline Mine Planning Inputs 145
13.3 Geotechnical and Pit Water Basis 150
13.4 Pit Optimization and Design 153
13.5 Material Routing and Storage 160
13.6 Production Schedule and Mining Sequence 164
13.7 Mining Equipment and Operating Basis 171
13.8 Mining Operations and Services 173
     
14 Processing and Recovery Methods 175
     
14.1 General 175
14.2 Sorting Methods 177
14.3 Mill Design Criteria Summary 183
14.4 Mill Design Basis 184
14.5 Flow Sheet Development and Equipment Sizing 184
     
15 Infrastructure 187
     
15.1 General Layout 187
15.2 Road Access 187
15.3 Rail Access 188
15.4 Electrical Power 189
15.5 Fuel Supply 191
15.6 Water Supply 192
15.7 Waste Rock Facilities 192
15.8 Tailings Storage Facility 193
     
16 Market Studies 196
     
16.1 Summary for Copper 196
16.2 Summary for Molybdenum 200
16.3 Summary for Silver 202
16.4 Summary for Rhenium 203
16.5 Selected Metal Prices 204
     
17 Environmental Studies, Permitting, and Plans, Negotiations, or Agreements with Local Individuals or Groups 206
     
17.1 Environmental and Permitting 206
17.2 Permitting for Mining Operations 209
17.3 Monitoring 212

 

barr.com

 

v

 

 

 

17.4 Reclamation 213
17.5 Social and Community Impact 214
17.6 Potential Issues 215
17.7 Mine Closure – General Discussion 217
     
18 Capital and Operating Costs 218
     
18.1 Capital Cost Estimate 218
18.2 Operating Cost Estimate 225
     
19 Economic Analysis 231
     
19.1 Cautionary Statements 231
19.2 Analysis Basis 231
19.3 Comparison of Economic Results 232
19.4 Common Assumptions and Estimating Basis 233
19.5 Economic Analysis Including Inferred Mineral Resources 237
19.6 Economic Analysis Excluding Inferred Mineral Resources 246
     
20 Adjacent Properties 251
     
21 Other Relevant Data and Information 256
     
22 Interpretation and Conclusions 257
     
22.1 Conclusions 257
22.2 Project Risks 260
     
23 Recommendations 268
     
23.1 Mineral Resources 268
23.2 Pit Geotechnical 268
23.3 Mining 269
23.4 Mineral Sorting 270
23.5 Processing 270
23.6 Project Infrastructure 270
23.7 Tailings Management 271
23.8 Permitting 271
23.9 Economics 272
23.10 Additional Studies and Tradeoffs 272
23.11 Integrated Pre-Feasibility Study 273
23.12 Recommended Study Budget 274
     
24 References 275
     
25 Reliance on Information Provided by the Registrant 278
     
25.1 Title Opinion 278
25.2 Taxes and Depreciation 278

 

barr.com


 

vi

 

 

 

Tables

 

Table 1-1 Metal Prices for Resource Estimation 3
Table 1-2 CuMo Metal Recoveries by Zone 3
Table 1-3 Measured Resource Within Pit Shell 5
Table 1-4 Indicated Resources 5
Table 1-5 Measured and Indicated Resources 6
Table 1-6 Inferred Resources (Molybdenum, Copper, Silver, Rhenium, and Sulfur) 6
Table 1-7 Project Capital Cost Summary 9
Table 1-8 Base Case Operating Cost Summary 9
Table 1-9 Summary of Project Economics 11
Table 1-10 Recommended Study Program Budget 28
Table 2-1 QP Responsibilities 29
Table 3-1 Active Unpatented CuMo Project Claim List – June 2026 36
Table 3-2 Active Patented CuMo Project Claim List – June 2026 39
Table 5-1 Summary of Historical Drilling Completed through 1981 44
Table 5-2 List of Historic Drill Holes Completed through 1981 44
Table 5-3 Historical Resource Estimate 47
Table 6-1 Summary of Rock Units Present at the CuMo Property 55
Table 7-1 Summary of Diamond Drill Holes by Year 65
Table 7-2 Summary of Diamond Drill Holes Completed in 2006 65
Table 7-3 Summary of Diamond Drill Holes Completed in 2007 through 2011 66
Table 7-4 Summary of Diamond Drill Holes Completed in 2012 67
Table 7-5 Significant Drill Results 71
Table 7-6 Metal Prices Used to Calculate Copper and Molybdenum Equivalent 75
Table 7-7 Estimated Metallurgical Recoveries (%) by Mineral Zone Used to Calculate Copper and Molybdenite Equivalent 75
Table 7-8 Drill Holes Used in Resource Estimate 77
Table 8-1 Certified Standards Prepared for CuMo Project 81
Table 8-2 Density Data Example 82
Table 8-3 Density Measurement Results Summary 82
Table 10-1 Metallurgical Composite Samples Drillhole Sources 107
Table 10-2 Projected Recoveries 108
Table 10-3 Summary of Comminution Test Work Data 110
Table 10-4 Baseline Flotation Results for CuMo Composite Samples 111
Table 10-5 Cleaner Flotation Results for CuMo Composite Samples 112
Table 10-6 Locked Cycle Test Results 113
Table 10-7 Tungsten Recovery Test Results 114
Table 10-8 Grade/Recovery Predictions for CuMo 115
Table 10-9 Distribution of Sorted Data into RCV Bins 119
Table 10-10 Metal Distribution of Model 119
Table 10-11 First Stage Sort Distribution Table 120
Table 10-12 Second Stage Sort Distribution Table 121
Table 10-13 Third Stage Sort Distribution Table 122
Table 10-14 Summary of % Applied to Block Model 123
Table 11-1 Summary of MoS2 and Cu Contents 125
Table 11-2 Summary of Assay Statistics for Cu And MoS2 Sorted by Zone 125

 

barr.com

 

vii

 

 

 

Table 11-3 Summary of Assay Statistics for Ag and W Sorted by Zone 127
Table 11-4 Summary of Capping Levels by Mineralized Zone 127
Table 11-5 Summary of Capped Assay Statistics for Cu and MoS2 Sorted by Zone 128
Table 11-6 Summary of Capped Assay Statistics for Ag and W Sorted by Zone 128
Table 11-7 Summary of 50 Ft Composite Statistics 129
Table 11-8 Parameters for Semi-Variogram Models at CuMo 130
Table 11-9 Block Model Dimensions and Configuration 131
Table 11-10 Estimation Boundary Summary 132
Table 11-11 Summary of Kriging Search Parameters for Each Mineralized Zone 132
Table 11-12 Summary of Density Parameters for Each Mineralized Zone 135
Table 11-13 Metal Prices for Resources 138
Table 11-14 Metal Recoveries Sorted by Mineralized Zone 138
Table 11-15 Measured Resources 139
Table 11-16 Indicated Resources 140
Table 11-17 Measured and Indicated Resources 140
Table 11-18 Inferred Resources (Molybdenum, Copper, Silver, Rhenium, and Sulfur) 141
Table 13-1 Mine-Plan Overview 143
Table 13-2 Life-Of-Operation Material Balance at Defined Reference Points 145
Table 13-3 Scheduled Material Quantities 146
Table 13-4 Baseline Production-Scheduling Inputs 147
Table 13-5 Metallurgical Recoveries Used in Production Scheduling 147
Table 13-6 Mining and Mill Ramp-Up Schedule 148
Table 13-7 Internal and Operating Break-Even NSR Cutoffs 148
Table 13-8 Historical Resource-Pit-Shell Geometry from Snowden (2012) 151
Table 13-9 Pit-Design Bench Geometry 152
Table 13-10 IA Pit-Wall Angle Recommendations by Depth 152
Table 13-11 Inputs for the Pit-Optimization Validation 153
Table 13-12 Pit-Shell Response Near the Design Limits 156
Table 13-13 Whittle Pit Optimization Shell and Mine-Design Comparison 156
Table 13-14 Main Mining-Phase Quantities 157
Table 13-15 IA Mining-Access Criteria 160
Table 13-16 Life-of-Operation Crusher and Sorter Material Distribution 160
Table 13-17 Stockpile Movements and Inventories at Production Milestones 161
Table 13-18 Planned Material-Storage and Construction Quantities 162
Table 13-19 Annual Primary Excavation and Feed During Pit Mining 165
Table 13-20 Annual Mill-Feed Sources and Grades 166
Table 13-21 Maximum Annual Bench Advance by Scheduling Phase 169
Table 13-22 Bench Mining Sequence by Scheduling Phase 170
Table 13-23 Principal Mining Equipment Purchases 171
Table 13-24 Equipment Operating-Hour Criteria 172
Table 13-25 Mine Workforce by Function 172
Table 13-26 Peak Operating Fleet Estimate by Equipment Duty 173
Table 13-27 IA Drilling and Blasting Pattern Criteria 174
Table 14-1 Summary of the Ore Sorter Process Design Criteria 180
Table 14-2 Summary of the Process Plant Design Criteria (70 kstpd) 183
Table 16-1 Metal Prices for Economic Analysis 204
Table 17-1 List of Reports Related to the Supplemental Redline Environmental Assessment 207

 

barr.com

 

viii

 

 

 

Table 17-2 Major Permits and Authorizations That May be Required 209
Table 18-1 Project Capital Expenditure by Timing Group 219
Table 18-2 Mining Capital Expenditure Before Contingency 220
Table 18-3 Mining Equipment Purchase Cost Estimate 220
Table 18-4 Processing Capital Expenditure Before Contingency 221
Table 18-5 Dedicated Material Handling Equipment Purchase Costs 222
Table 18-6 Site Infrastructure Capital Expenditure Before Contingency 224
Table 18-7 Environmental and Closure Capital Before Contingency 224
Table 18-8 General Site Capital Expenditure Before Contingency 225
Table 18-9 Summary of Operating Costs 226
Table 18-10 Mining Costs by Activity 227
Table 18-11 Processing Operating Costs by Component 228
Table 18-12 General Site and Administrative Operating Costs 230
Table 19-1 Summary of Potential Project Economics 232
Table 19-2 Resource Classification and Production Comparison 233
Table 19-3 Pricing Assumptions for Economic Analysis 234
Table 19-4 Concentrate Sales and Off-Site Cost Assumptions 234
Table 19-5 Capital Cost Summary by Timing Group US$M 236
Table 19-6 Annual Recovered and Payable Metal Production Including Inferred Resources 237
Table 19-7 Annual Project Cash Flow Including Inferred Resources 239
Table 19-8 Operating Cost Summary Including Inferred Resources 241
Table 19-9 Contained Recovered and Payable Metal Including Inferred Resources 241
Table 19-10 Life of Project Taxes and Credits Including Inferred Resources 241
Table 19-11 Life of Mine Cash Costs and All-In Sustaining Costs Including Inferred Resources 242
Table 19-12 Capital Intensity Based on Average Scheduled Payable Production Including Inferred Resources 242
Table 19-13 One Variable Sensitivity with the Mine Plan Fixed Including Inferred Resources 243
Table 19-14 Pre-Tax NPV Sensitivity to Discount Rate Including Inferred Resources 245
Table 19-15 Annual Mill Feed and Metal Production Excluding Inferred Resources 247
Table 19-16 Annual Project Cash Flow Excluding Inferred Resources 248
Table 20-1 Summary of Adjacent Known Mining Properties [1] 252
Table 23-1 Estimated Budget for Additional PFS Study Work 274

 

barr.com

 

ix

 

 

 

Figures

 

Figure 3-1 CuMo Property Location Map 34
Figure 3-2 Claim Location Map for the CuMo Property 35
Figure 4-1 CuMo Project, Boise County, Location Map 42
Figure 5-1 Map Showing the Location of Completed and Proposed DDHs 46
Figure 6-1 Tectonic Map of the Western United States 49
Figure 6-2 Distribution of Idaho Montana Porphyry Deposits in Relation to the Great Falls Tectonic Zone 50
Figure 6-3 Geology of the Idaho City 30 × 60 Minute Quadrangle, Idaho 52
Figure 6-4 Geology of Boise County, Idaho, Showing Geological Setting of CuMo Deposit 53
Figure 6-5 Core Photographs of Felsic Porphyry Types Recognized in Drill Core 56
Figure 6-6 Photographs of Mineralized Core from the CuMo 2006 Program, Hole C06-28 58
Figure 6-7 Photographs of Molybdenite Mineralization in 2008 Drill Core 59
Figure 6-8 Surface Distribution of Quartz and Epidote Veinlets and Metal Zonation 60
Figure 6-9 Geochemical Distribution of Molybdenum in Surface Rock Chip Samples 61
Figure 6-10 Geochemical Distribution of Copper in Surface Rock Chip Samples 62
Figure 7-1 CuMo Deposit Q-Q’ Cross-Section (SRK, 2020) 68
Figure 7-2 CuMo Deposit H-H Cross-Section (SRK, 2020) 69
Figure 8-1 Location of Core Storage Facility and the CuMo Project 84
Figure 8-2 Core Boxes at Current Storage Facility 85
Figure 8-3 Skyline Original MoS2 Versus Skyline Duplicate MoS2 from Duplicate Drill Core 86
Figure 8-4 Skyline Original MoS2 Versus Skyline Duplicate MoS2 from Rejects 87
Figure 8-5 Skyline Original MoS2 Versus Skyline Duplicate MoS2 from Pulps 87
Figure 8-6 Skyline Original MoS2 Versus Amax Check MoS2 on Pulps from Drill Core 88
Figure 8-7 Skyline Original MoS2 Versus Amax Check MoS2 on RC Cuttings 88
Figure 8-8 Skyline Original MoS2 Versus Hazen Check MoS2 on Pulps 89
Figure 8-9 MoS2 in Blank Samples from Idaho Copper Drill Programs at CuMo 90
Figure 8-10 Cu in Blank Samples from 2008 Drill Program CuMo 91
Figure 8-11 Scatter Plot of Chemex Internal Duplicates for Mo ppm (Mo Metal) 93
Figure 8-12 Scatter Plot of Chemex Internal Duplicates for Cu ppm 94
Figure 8-13 Results for Standard S1 95
Figure 8-14 Results for Standard S2 96
Figure 8-15 Results for Standard S3 97
Figure 8-16 Results for Chemex Molybdenum Original versus ICP Check 99
Figure 8-17 Results for Chemex Copper Original Versus ICP Check 100
Figure 8-18 Results for Chemex Silver Original versus ICP Check 101
Figure 8-19 Results for Chemex Molybdenum Original Versus XRF Check 102
Figure 8-20 Results for Chemex Copper Original Versus XRF Check 103
Figure 10-1 Flowchart for Sorting Process 117
Figure 11-1 Contact Plots for Oxide-Cu-Ag Zone Contact 126
Figure 11-2 Scatter Plot Showing Re Versus MoS2 in the Cu-Mo Zone 134
Figure 11-3 Plan Views of the Measured, Indicated and Inferred Blocks at CuMo 137
Figure 13-1 Mine and Material-Storage Layout 144
Figure 13-2 Minimum Annual Crusher-Feed NSR Equivalent by Material Domain 149
Figure 13-3 Empirical Pit Wall Height and Slope Comparison 151
Figure 13-4 Discounted Pit Value and Material Quantities 155

 

barr.com

 

x

 

 

 

Figure 13-5 Discounted Pit Value and Incremental Stripping 155
Figure 13-6 Main Mining-Phase Designs in Plan View 158
Figure 13-7 Main Mining-Ultimate Pit Design in Plan View 159
Figure 13-8 Middlings Stockpile Inventory Profile 162
Figure 13-9 Initial Site Facility Layout 163
Figure 13-10 Final Site Facility Layout 164
Figure 13-11 Annual Mill-Feed Grades 168
Figure 13-12 Annual Excavation, Crushing and Mill-Feed Profile 169
Figure 14-1 Block Flow Process Schematic from ROM Ore through Products and Tailings 176
Figure 14-2 Ore Sorting Overall Flow Diagram 179
Figure 15-1 CuMo Project Possible Electrical Power Line Alignment 190
Figure 15-2 CuMo Project Possible Gas Pipeline Alignment 191
Figure 15-3 CuMo Project Site Layout with WRF 193
Figure 15-4 CuMo Project TSF Layout 194
Figure 15-5 Cross Section Profile Through CuMo Project TSF 194
Figure 16-1 Copper Demand Outlook 2015–2040 Shown in Millions of Metric Tons 197
Figure 16-2 Copper Production by Country, 2024 198
Figure 16-3 Copper Smelter Production by Country, 2024 198
Figure 16-4 Forecast Copper Concentrate Balance, Refined Copper Balance, and LME Three-Month Copper Price (2023–2035) 200
Figure 16-5 June 2024–June 2027 Copper Pricing Trend and Forecast 200
Figure 16-6 Silver Price Historical Trend and Forecast 203
Figure 16-7 Copper and Molybdenum Three-year Metal Price with Resource Metal Price 205
Figure 16-8 Silver Three-year Metal Price with Resource Metal Price 205
Figure 19-1 Pre-Tax NPV Sensitivity at an 8 Percent Discount Rate Including Inferred Resources 244
Figure 19-2 Pre-Tax IRR Sensitivity Including Inferred Resources 245
Figure 19-3 Pre-Tax NPV Sensitivity to Discount Rate Including Inferred Resources 246
Figure 20-1 Copper and Molybdenum Locations Near CuMo Property 254
Figure 20-2 Silver Locations Near CuMo Property 255

 

barr.com

 

xi

 

 

 

Abbreviations, Acronyms, and Units

 

$/lb dollar per pound
$/oz dollar per ounce
$M million US dollars
% percent
° degrees (of plane angle)
° C degrees Celsius
° F degrees Fahrenheit
µm micron (micrometer)
ABA acid-base accounting
ac acre
Ag silver
AISC all-in sustaining costs
ALS Chemex ALS-Chemistry
AMSL above mean sea level
AMT alternative maximum tax
ANFO ammonium nitrate/fuel oil
APS Announced Pledges Scenario
Au gold
Az azimuth
Barr Barr Engineering Co.
bcy bank cubic yards
bgs below ground surface
BLM Bureau of Land Management
BOR Bureau of Reclamation
BOS bulk ore sorting
C1 cash cost
CDN Labs CDN Resources Laboratories Ltd.
CFR Code of Federal Regulations
CIM Canadian Institute of Mining
cm centimeter
COG cut-off grade
Court United States District Court of the District of Idaho
Cu copper
Cu-Ag copper-silver
CuMo American CuMo Mining Corporation
Cu-Mo copper-molybdenum
CWA Clean Water Act
Dahrouge Dahrouge Geological Consulting USA LTD.
DCF uncapitalized discounted cash flow
DDH diamond drill hole
DEQ Department of Environmental Quality
Dl density of distilled water
dmt dry metric ton
DN Decision Notice

 

barr.com

 

xii

 

 

 

DRC Democratic Republic of Congo
Ds density of solid
EA environmental assessment
EIS environmental impact statement
elev elevation
ESA Endangered Species Act
Etc. et cetera
ETF exchange-trade fund
EV electric vehicle
FF/ft fracture frequency in feet
FF/m fracture frequency in meters
FONSI Finding of No Significant Impact
FoS factor of safety
FS feasibility study
ft foot
ft³ cubic foot
g gram
G&A General and Administrative
g/cm grams per centimeter
g/cm3 grams per cubic centimeter
g/t grams per metric ton
gal gallon
gpm gallons per minute
GSI Geological Strength Index
h hour
HARN high-accuracy reference network
Hazen Hazen Research
hp horsepower
HPGR high-pressure grinding rolls
HSTRCWTR Idaho Historical Waters
IA Initial Assessment
ICMC Idaho CuMo Corporation
ICP inductively couple plasma
ICP-AES inductively coupled plasma–atomic emission spectroscopy
ICP-ES inductively coupled plasma–emission spectroscopy
ICP-MS inductively coupled plasma mass spectrometry
ID identification
Idaho Copper Idaho Copper Corp.
IDAPA Idaho Administrative Procedure Act
IDL Idaho Department of Lands
IEA International Energy Agency
IGS Idaho Geological Survey
in. inch
INPR Idaho, Northern and Pacific Railroad
IP induced polarization
IPCC in-pit crushing and conveying
IRR internal rate of return

 

barr.com

 

xiii

 

 

 

JV joint venture
kg kilogram
kgd kilograms per day
Kirkness Kirkness Drilling
km kilometer
km² square kilometer
Kobex Kobex Resources Ltd.
koz thousand ounces
kst thousand short tons
kW kilowatt
kW/m³ kilowatts per cubic meter
kWh kilowatt-hour
kWh/mt kilowatt-hours per metric ton
lb pounds
lb/ft3 pounds per cubic foot
LNG liquified natural gas
LOM life-of-mine
Lycopodium Lycopodium Minerals Canada Ltd. (Americas)
m meter
M million or mega
m² square meter
m³ cubic meter
Ma million years ago
mg milligram
MI mass of sample in water
Midwest Midwest Oil Corp.
ML/ARD metal leaching / acid rock drainage
Mlb millions of pounds
mm millimeter
MMBtu million British thermal units
Mo molybdenum
MoS₂ molybdenite
MoS3 molybdenum trioxide
Moz million ounces
mph miles per hour
MRI magnetic resonance imaging
MSI potassic-silica alteration zone with lower-grade Cu-Mo mineralization
Mst million short tons
Mt million tons
mtpa or mstpa million short tons per annum
NaCN sodium cyanide
NAD83 North American Datum 1983
NAVD88 North American Vertical Datum 1988
NEPA National Environmental Policy Act
NF National Forest
NGO non-governmental organizations
NI National Instrument

 

barr.com

 

xiv

 

 

 

NLM Northern Lights Mining
non-PAG non-potentially acid generating
NP neutralization potential
NPV net present value
NSR net smelter return
NVP8 net present value at an 8% discount
NYSE New York Stock Exchange
OECD Organization for Economic Co-Operation and Development
OX oxide
oz troy ounce
PAG potentially acid generating
PAN potentially acid neutralizing
PEA preliminary economic assessment
PFS pre-feasibility study
PFTNA pulsed fast thermal neutron activation
PGNAA prompt gamma neutron activation analysis
ppm parts per million
QA/QC quality assurance / quality control
QP Qualified Person
RC reverse circulation
RCV recoverable value
Re rhenium
RL reduced level
RMR Rock Mass Rating
ROD Record of Decision
ROM run-of-mine
RQD rock quality designation
s second (unit of time)
S sulfur
s.g. or SG specific gravity
SAG semi-autogenous grinding
SCR solid core recovery
SGS SGS Testing Services
SIBX sodium isobutyl xanthate
SRK SRK Consulting (Canada) Inc.
STEPS Stated Policies Scenario
t or st short ton (US 2,000 pounds)
TCR total core recovery
tonne metric tonne
Tpd or stpd short tons per day
tph or stph short tons per hour
TRS Technical Report Summary
TSF tailings storage facility
TSXV or TSX-V TSX Venture Exchange
U.S. EPA U.S. Environmental Protection Agency
US$ U.S. Dollar
USACE U.S. Army Corps of Engineers
USFS United States Forest Service
USFWS U.S. Fish and Wildlife Service
USGS United States Geological Survey
UTM Universal Transverse Mercator
W tungsten
Whittle Whittle Consulting Pty Ltd
wmt wet metric ton
WO3 tungsten trioxide
WRF waste rock facility
Wt weight percent
XRF X-ray fluorescence
yd3 cubic yard

 

barr.com

 

xv

 

 

1 Executive Summary

 

1.1Introduction

 

Idaho Copper Corporation (f/k/a Idaho CuMo Mining Corporation), (Idaho Copper: NYSE/Amex: COPR), a Nevada corporation, retained Barr Engineering Co. (Barr) to update an Initial Assessment (IA) on the Idaho Copper Corporation (Idaho Copper) CuMo project in Boise County, Idaho, USA, and to present its outcomes in this independent S-K 1300 technical summary report (TRS). Other contributors to the IA report are Dahrouge Geological Consulting USA LTD. (Dahrouge), Northern Lights Mining, LLC (NLM), Lycopodium Minerals Canada Ltd. (Americas) (Lycopodium).

 

The IA is based on verification of the existing resource model previously reviewed and utilized for Idaho Copper’s PEA in 2020 (SRK, 2020), which itself was based on the resource model generated by qualified person (QP), Gary Giroux, and reported on in 2015 (Giroux et al., 2015). Barr reviewed aspects of the previous PEA to determine items that remain applicable to the current CuMo project evaluation. Original work by Barr includes the incorporation of the evaluation of bulk ore sorting developed by Lycopodium into the concept process design, generation of mine designs, based on optimization parameters developed by Whittle Consulting Pty Ltd. (Whittle), schedules and costing, selection and evaluation of a tailings management strategy, and updating the economic analysis. Recently, an updated National Instrument (NI) 43-101 and PEA was issued (Palo, D.R., et al., 2026) based on this same information that is the basis of this IA and TRS.

 

Dahrouge reviewed the previously developed mineral resource information for the current IA study and determined it to be appropriate for use. The current assessment maintained the previous study assumptions. The effective date for this Mineral Resource Estimate remains August 30, 2018.

 

Site visits for the purposes of personal inspections of the CuMo property have been undertaken by Mr. Gareth Flitton, geology QP (September 2025); Mr. Justin L. Smith, mining QP (June 2026); and Mr. Russell J. Sheets, geotechnical QP (June 2026). An additional site visit was completed by project team member Mr. Preetham Nayak (July 2024).

 

Note: Throughout this report, all currency is in 2026, non-escalated United States dollars and all units are US Customary, unless otherwise specifically noted.

 

1.2Property Description, History, and Ownership

 

The CuMo deposit is a molybdenum-copper deposit situated 37 miles (60 kilometers [km]) northeast of Boise, Idaho, USA. The project is situated in the southern section of the Boise Mountains which are characterized by north-northwest trending mountain ranges separated by alluvial filled valleys. Existing ground elevations within the mapped project area range from approximately 4,200 to 7,350 feet (ft) (1,280 to 2,240 meters [m]) above mean sea level.

 

Situated in a historic lode gold camp with a recorded production of 2.8 million ounces, molybdenite mineralization was not discovered in this area until 1963 by Amax Exploration (Amax). After conducting surface sampling in 1964, Amax relinquished rights to the property. It was subsequently explored by Curwood Mining Company, Midwest Oil Corporation (later Amoco Minerals Company), Amax (a second time), and then Climax Molybdenum Company (a subsidiary of Amax Inc.). The historic drilling was done between 1969 and 1982 for a total of 10,981 m (36,026 ft) in 23 diamond drill holes and three reverse circulation holes. Note: Reverse circulation holes are not used in the resource calculation.

 

1
 

 

The property was re-staked in 1998 by CuMo Molybdenum Mining Inc. and optioned to Mosquito Consolidated Gold Mines Ltd., (subsequently known as CuMoCo) in 2004. Presently, the CuMo project is held by Idaho Copper.

 

1.3Exploration

 

After CuMoCo had optioned the property in 2004, Kobex Resources Ltd. (Kobex) optioned it from CuMoCo in 2005 and commenced drilling in 2006. Kobex drilled one complete hole and 50% of a second hole (3,560 ft/1,085 m) in late 2006, CuMoCo resumed control and completed the 2007 to 2011 exploration drilling programs, including the incomplete hole started by Kobex. CuMoCo completed 66,235 feet (20,188 m) of drilling in 32 diamond drill holes in that program. During 2012, CuMoCo drilled nine additional holes totaling 15,463 ft (4,213 m), aimed at improving the resource categorization and gaining a better understanding of the extent of the deposit.

 

1.4Geology and Mineralization

 

The CuMo deposit is located at the southwestern end of the Idaho-Montana Porphyry Belt. Igneous complexes in this belt are interpreted to be related to an Eocene, intra-arc rift, and are characterized by alkalic rocks in the northeast, mixed alkalic and calc-alkalic rocks in the middle, and calc-alkaline rocks in the southwest. The CuMo deposit is typical of large, dispersed, low grade molybdenum ± copper porphyry deposits that are associated with hybrid magmas typified by fluorine-poor, differentiated monzogranite igneous complexes. Due to their large size, the total contained economic molybdenum in these types of deposits can be equivalent to or exceed that of high-grade molybdenum deposits.

 

Idaho Copper’s work has resulted in the interpretation and modelling of three distinct mineralized zones within the deposit. These zones were previously interpreted by Amax as distinct shells that were produced by separate intrusions. Previously completed re-interpretation of down-hole histograms for copper (Cu), silver (Ag) and molybdenite (MoS2) suggests the mineralized zones are part of a single, large, concentrically zoned system with an upper copper-silver zone (named Cu-Ag zone), underlain by a transitional copper-molybdenum zone (named Cu-Mo zone), in turn underlain by a lower molybdenum-rich zone (named Mo zone). Three-dimensional modeling of the above zonation indicates the current area being drilled is located on the north side of a large system extending 15,000 ft (4.5 km) in diameter, of which 3,000 ft (1.5 km) has been drilled.

 

1.5Mineral Resource Estimate

 

The mineral resource information was reviewed by the QP for the current IA study and determined to be appropriate for use. The current assessment maintained the previous study assumptions. The effective date for this Mineral Resource Estimate remains August 30, 2018.

 

A resource estimate update was originally completed in 2015, based on a total of 65 diamond drill holes totaling 118,654 ft (36,166 m). Note that the three reverse circulation holes were not used in the resource estimate. Nine of the 65 diamond drill holes were completed in 2012. As no additional drilling has been completed since the 2015 resource was estimated, it is considered current.

 

2
 

 

A geological model separating the CuMo deposit into four mineralized zones with an oxidized layer on top was developed by Idaho Copper geologists. In addition, major fault blocks were identified both by assay data and marker beds. Assays were tagged as one of four mineralized zones: a near surface Cu-Ag zone, a deeper Cu-Mo zone and a still deeper Mo zone and an underlying potassic-silica zone (MSI). Statistical analysis of each variable in each zone led to the capping of assays based on the grade distribution within each zone. Uniform down-hole 50 ft composites were produced for each zone. For variography, the major post mineral fault blocks were rotated back to their original position using marker beds. Semi-variograms were produced for each variable within each zone based on the samples’ original pre-fault locations. A block model with block dimensions of 50 ft x 50 ft x 50 ft was superimposed on the mineralized zones. Grade was interpolated into blocks by ordinary kriging. A tonnage factor was determined for each zone based on multiple specific gravity determinations. Individual blocks were classified as measured, indicated, or inferred resource based on their location relative to drill-hole composites.

 

To take into account the four primary potentially economic minerals estimated, a form of metal equivalent or recoverable value (RCV) was calculated for each block based on reasonable commodity prices and estimated recoveries in each of five zones; the oxide (OX) zone (a combination of altered Cu-Ag and Cu-Mo zones), Cu-Ag zone, Cu-Mo zone, Mo zone and potassic-silica alteration zone with lower-grade Cu-Mo mineralization (MSI) zone. The 2015 resource estimate is summarized below for RCV cut-offs.

 

The metal prices used for resource estimation are provided in Table 1-1.

 

Table 1-1 Metal Prices for Resource Estimation

 

Metal Price (US$)
Copper (Cu), $/lb 3.00
Molybdenum trioxide (MoO3), $/lb 10.00
Molybdenum (Mo) metal, $/lb 15.00
Silver (Ag), $/oz 12.50

 

Note. $ = US dollar, lb = pound, oz = ounce

 

The metal recoveries used were a function of mineralized zones as follows in Table 1-2.

 

Table 1-2 CuMo Metal Recoveries by Zone

 

Zone Cu Recovery (%) Mo Recovery (%) Ag Recovery (%)
OX 60 80 65
Cu-Ag 68 86 75
Cu-Mo 85 92 78
Mo 72 95 55
MSI 72 95 55

 

Note: The recoveries for all metals in the potassic-silica alteration zone with lower-grade Cu-Mo mineralization (MSI) zone were similar to the molybdenum (Mo) zone. Cu-Ag = copper-silver, Cu-Mo = copper-molybdenum, Mo = molybdenum, MSI = potassic-silica alteration zone with lower-grade Cu-Mo mineralization, OX = oxide

 

3
 

 

In 2025, Whittle used Geovia’s WhittleTM pit optimizer to determine a constraining open pit for the CuMo deposit. Optimization parameters were developed directly between Whittle and Idaho Copper. The open pit cone sequence and extents, the process throughput and recovery, and the schedule were provided to Barr. From the information, Barr developed initial and final open pit designs based on the pit cones, a mine production schedule and process schedule, and economic model based on applied metal prices, capital expenditures, and operational expenses over the life of the CuMo project.

 

The commodity prices used by Snowden (2012) for restraining the resource were Mo at $25 per pound (lb), Cu at $3/lb, Ag at $20 per troy ounce (oz), and tungsten (W) at $10/lb. Since the infill drill holes completed in 2012 were all within the conceptual pit, this resource update uses the Snowden (2012) optimum pit shell to constrain the estimate.

 

In the mineral resource estimate tables below (Table 1-3, Table 1-4, Table 1-5, and Table 1-6), the base case $5.00 per ton (t) RCV cut-off is highlighted and is selected based on operating costs and the results of grade improvement using a mineral sorting process. The $5.00 cut-off is suggested to separate waste from material that is fed into the sorters. From the sorters, only mill feed above an economic cut-off would be sent for immediate processing.

 

It should be noted that since the convention for the CuMo project has been to work with %MoS2, as calculated from measured %Mo, the %MoS2 values in the resource estimate tables are 1.6681 times the %Mo.

 

In August 2018, an estimate for rhenium (Re) and sulfur (S) associated with the MoS2 was completed using linear regression of MoS2 versus Re and MoS2 versus S to show the average grades of Re and S that would be contained with MoS2 within each block. The Re and S were not used to determine the RCV value of resources shown in Table 1-3, Table 1-4, Table 1-5, and Table 1-6 below. The effective date for this Mineral Resource Estimate remains August 30, 2018.

 

Although Re was not used in the block model as a basis for developing the production and process schedule upon which the IA is based, the Re recovery was considered within the project economics based metallurgical test work and average concentrate grades.

 

Note: Regression analysis is not an industry standard practice in calculating overall resources. However, the fact that rhenium is entirely, and almost all the sulfur are, contained within the material containing MoS2, (a minor amount of sulfur is contained in pyrite) which has been estimated by kriging, means that regression is a valid method of obtaining a reasonable estimate of the rhenium and sulfur contents at the level of precision of this study. Due to the large number of samples involved in the regression analysis, the confidence of this particular regression estimate is comparable to that obtained by the method of ordinary kriging.

 

Mineral Resources are not Mineral Reserves and have not demonstrated viable economic recovery. Therefore, it is not certain that Mineral Resources will be converted to Mineral Reserves. Any Mineral Reserve estimate may be affected by existing or future environmental, permitting, legal, land title, taxation, socio-political, metallurgical, or other relevant factors that may not be listed here. Inferred Mineral Resources inherently have a lower level of confidence compared to Indicated Mineral Resources and must not be converted to Mineral Reserves. It may be reasonable to expect that a portion of Inferred Mineral Resources could be upgraded to Indicated Mineral Resources with continued exploration and geometallurgical analysis. Mineral Resources, determined for this estimate are effective August 30, 2018, were previously prepared in accordance with National Instrument 43-101 (NI 43-101) and the CIM Definition Standards for Mineral Resources and Mineral Reserves. While the previous technical work provides a basis for the current assessment, the Mineral Resource disclosure presented here has been reviewed against the applicable definitions, classification requirements, and disclosure provisions of S-K 1300.

 

4
 

 

Table 1-3 Measured Resource Within Pit Shell

 

Cut-off RCV

 

($)

Grade > RCV Cut-off Contained Metal
Quantity (Mt) MoS2 (%)

Cu

 

(%)

Ag (ppm)

RCV

 

($)

Re (ppm)

S

 

(%)

Mo (Mlb)

Cu

 

(Mlb)

Ag (Moz)
2.5 308.4 0.079 0.074 2.09 17.32 0.029 0.233 292.1 456.5 18.8
5.0 297.2 0.081 0.076 2.09 17.83 0.03 0.229 288.6 451.7 18.1
7.5 282 0.085 0.076 2.06 18.48 0.031 0.223 287.4 428.7 16.9
12.5 227.9 0.097 0.075 2 20.50 0.036 0.217 265 341.8 13.3
15.0 195.4 0.105 0.072 1.9 21.71 0.039 0.212 246 281.3 10.8
17.5 159.7 0.115 0.067 1.8 23.04 0.043 0.207 220.1 213.9 8.4
20.0 122.9 0.125 0.063 1.7 24.50 0.047 0.202 184.1 154.8 6.1

 

Source: Giroux et al. (2015), modified 2019, reviewed 2026. The effective date for this Mineral Resource estimate remains August 30, 2018. Note: $ = US dollar, Ag = silver, Cu = copper, Mlb = millions of pounds, Mo = molybdenum, MoS2 = molybdenite, Moz = million ounces, Mt = million tons, ppm = parts per million, RCV = recoverable value, Re = rhenium, S = sulfur

 

Table 1-4 Indicated Resources

 

Cut-off RCV

 

($)

Grade > RCV Cut-off Contained Metal
Quantity (Mt) MoS2 (%)

Cu

 

(%)

Ag (ppm)

RCV

 

($)

Re (ppm)

S

 

(%)

Mo (Mlb)

Cu

 

(Mlb)

Ag (Moz)
2.5 2216.1 0.049 0.079 2.48 12.32 0.018 0.277 1301.9 3501.4 160.3
5.0 1972.3 0.053 0.085 2.57 13.40 0.019 0.269 1253.3 3352.9 147.8
7.5 1708.3 0.059 0.088 2.59 14.55 0.021 0.258 1208.4 3006.5 129
12.5 1050.6 0.076 0.09 2.55 17.67 0.027 0.235 957.4 1891.1 78.1
15.0 798.5 0.083 0.09 2.56 19.06 0.03 0.231 794.6 1437.2 59.6
17.5 541.6 0.093 0.088 2.49 20.60 0.034 0.226 603.9 953.2 39.3
20.0 301.3 0.106 0.082 2.36 22.49 0.039 0.219 383 494.2 20.7

 

Source: Giroux et al. (2015), modified 2019, reviewed 2026. The effective date for this Mineral Resource estimate remains August 30, 2018. Note: $ = US dollar, Ag = silver, Cu = copper, Mlb = millions of pounds, Mo = molybdenum, MoS2 = molybdenite, Moz = million ounces, Mt = million tons, ppm = parts per million, RCV = recoverable value, Re = rhenium, S = sulfur

 

5
 

 

Table 1-5 Measured and Indicated Resources

 

Cut-off RCV

 

($)

Grade > RCV Cut-off Contained Metal
Quantity (Mt) MoS2 (%)

Cu

 

(%)

Ag (ppm)

RCV

 

($)

Re (ppm)

S

 

(%)

Mo (Mlb)

Cu

 

(Mlb)

Ag (Moz)
2.5 2524.6 0.053 0.079 2.43 12.93 0.019 0.272 1604.3 3988.9 178.9
5.0 2269.6 0.057 0.084 2.5 13.98 0.021 0.264 1551.1 3812.9 165.5
7.5 1990.4 0.063 0.086 2.51 15.10 0.022 0.253 1503.5 3423.5 145.7
12.5 1278.6 0.079 0.087 2.46 18.17 0.029 0.232 1211.1 2224.8 91.7
15.0 993.9 0.088 0.087 2.43 19.58 0.032 0.227 1048.7 1729.5 70.4
17.5 701.4 0.098 0.083 2.33 21.16 0.036 0.221 824.1 1164.2 47.7
20.0 424.3 0.112 0.077 2.17 23.07 0.041 0.214 569.8 653.4 26.9

 

Source: Giroux et al. (2015), modified 2019, reviewed 2026. The effective date for this Mineral Resource estimate remains August 30, 2018. Note: $ = US dollar, Ag = silver, Cu = copper, Mlb = millions of pounds, Mo = molybdenum, MoS2 = molybdenite, Moz = million ounces, Mt = million tons, ppm = parts per million, RCV = recoverable value, Re = rhenium, S = sulfur

 

Table 1-6 Inferred Resources (Molybdenum, Copper, Silver, Rhenium, and Sulfur)

 

Cut-off RCV

 

($)

Grade > RCV Cut-off Contained Metal
Quantity (Mt) MoS2 (%) Cu (%) Ag (ppm)

RCV

 

($)

Re (ppm) S (%) Mo (Mlb)

Cu

 

(Mlb)

Ag (Moz)
2.5 3373.6 0.04 0.057 1.93 9.55 0.014 0.304 1617.9 3845.9 189.9
5.0 2556.6 0.048 0.067 2.13 11.48 0.017 0.282 1471.4 3425.9 158.8
7.5 1996 0.056 0.07 2.23 13.07 0.02 0.261 1340.1 2794.4 129.8
12.5 996.4 0.078 0.064 1.98 16.74 0.028 0.231 931.8 1275.4 57.5
15.0 637 0.086 0.074 2.16 18.63 0.03 0.244 656.8 942.7 40.1
17.5 384.8 0.094 0.084 2.34 20.49 0.032 0.259 433.7 646.4 26.3
20.0 190.2 0.109 0.078 2.37 22.80 0.037 0.262 248.6 296.8 13.1

 

Source: Giroux et al. (2015), modified 2019, reviewed 2026. The effective date for this Mineral Resource estimate remains August 30, 2018. Note: $ = US dollar, Ag = silver, Cu = copper, Mlb = millions of pounds, Mo = molybdenum, MoS2 = molybdenite, Moz = million ounces, Mt = million tons, ppm = parts per million, RCV = recoverable value, Re = rhenium, S = sulfur

 

1.6Project Development and Operations

 

1.6.1Mining

 

The CuMo project is planned as an owner-operated open pit using conventional drilling, blasting, loading and haulage. Large electric cable shovels load 360-short-ton haul trucks. The six-phase mine plan schedules 3,083 million US short tons (Mst) of material, comprising 1,401 Mst of processing feed and 1,682 Mst of waste and construction material. The waste-to-feed ratio is 1.20. Mining begins in Year -1, reaches 160 million short tons per year (Mstpa) in Year 4 and ends in Year 22.

 

The shovels are equipped with sensors that allow material selection at the loading face, referred to as shovel sorting. Material accepted for processing is hauled to the primary crusher or run-of-mine (ROM) stockpile. Shovel rejects and pit waste are hauled to the waste rock facility or, where suitable, used in the tailings embankment. After primary crushing, two belt-sorting stages make further separations. The first stage produces mill feed, rejects and middlings, which are intermediate material sent to the second stage. The second stage produces additional mill feed, middlings which are stored in a stockpile for later milling, and rejects which, along with first-stage rejects, are placed in the waste rock facility.

 

6
 

 

The mill treats 1,127 Mst over 46 production years, including 680 Mst reclaimed from middlings storage. Milling starts with 9.0 Mst in Year 1 and increases to 25.6 Mstpa in Year 5. Crushing and sorting continue through Year 24, and middlings supply all mill feed from Year 25.

 

The mine plan is based on a conceptual study completed by Whittle in 2025. That study evaluated pit limits, development sequences, sorting responses and operating configurations and established preferred pit limits and phased production targets. The QP responsible for the Mining Methods chapter subsequently carried out independent pit optimizations and mining and processing evaluations, then developed phase designs incorporating ramps, working widths and bench geometry. A comparison using the final economic assumptions supported similar pit limits. The mine plan is based on Mineral Resources, including Inferred Mineral Resources; their treatment in the economic analysis is described in Section 1.9.

 

1.6.2Processing

 

The processing facilities, and associated service facilities, will process run-of-mine (ROM) feed to produce separate copper and molybdenum concentrates, and tailings. The IA process encompasses crushing the ROM feed, sorting, grinding, bulk rougher flotation, regrinding, cleaner flotation, molybdenum separation, molybdenum purification, and dewatering of copper and molybdenum concentrates. The flotation tailings will be thickened before placement in the tailings storage facility (TSF).

 

The IA has assumed that two concentrates (copper and molybdenum) will be produced. The copper concentrate is assumed to be sold and shipped to a smelter. Silver is assumed to be a payable byproduct of the copper concentrate and will contribute to the value of the CuMo sales. It is assumed that the molybdenum concentrate will be shipped to a toll roaster within the United States where additional credits may be achieved through the production of rhenium. No penalty elements have been identified to date. At the current time, no contracts exist for delivery of final product so the report assumes that products will be sold on the open market.

 

1.6.3Tailings Management

 

The TSF will be located at the headwaters of the Clear Creek watershed, in a natural basin formed by the surrounding ridgeline. The TSF will have capacity to store the 24 billion cubic feet (ft3) of tailings produced over the mine and process plant’s total 46-year life. The TSF ultimate crest height will be 6,700 ft with 5 ft of freeboard above the top of tailings (6,695 ft). Tailings containment will be provided by the natural topography on the valley sides and an engineered dam that will be buttressed by additional waste rock, when available, constructed immediately downstream of the TSF. A starter dam will be constructed to a maximum initial elevation of 6,000 ft to facilitate early mine production, followed by additional raises spread out over the life of the active open pit operation.

 

1.7Social and Environmental

 

At this time, no issues were identified that would materially impact the ability to eventually extract Mineral Resources at the project.

 

7
 

 

The proposed mine will be located on public land administered by the United States Forest Service (USFS) and private land owned and controlled by Idaho Copper. The permitting path will involve multiple state and federal agencies. Permits likely to be required for the project are presented in Table 17-2. An environmental impact statement (EIS) will be required at the level of National Environmental Policy Act (NEPA) analysis for mine development, operations, and closure. Reclamation bonds will be required by both federal and state agencies. The reclamation liability for the proposed mine will have to be determined based on third-party costs, and the bond amount will have to be posted using an approved financial instrument. Idaho Copper has initiated consultation with various stakeholders namely: government officials at all levels and local communities in regard to the potential social and community impacts or improvements that may occur as the project progresses. All groups are provided regular updates as the project is proceeding. Local communities and officials have come out in strong support of the project and are actively working with the project on both the Grimes Creek project and future planning (Hilscher et al., 2018).

 

The mine will be located in an area used for weekend summer dispersed recreation and fall big-game hunting and is well-known in the Boise area. Organized environmental groups such as the Idaho Conservation League and Sierra Club are keeping their constituents informed to coordinate opposition to the project. As such, well-funded, organized opposition to mining activities should be anticipated.

 

The USFS has completed the Supplemental Environmental Assessment for the project and issued the signed Decision Notice and Finding of No Significant Impact (FONSI) on March 14, 2025, approving the 4-Year Exploration Plan of Operations that will allow the Company to proceed to the next round of drilling and road access construction on the property. This is the only current permitting activity.

 

1.8Project Costs

 

The IA presents the Base Case, which uses Measured, Indicated and Inferred Mineral Resources. The Measured and Indicated (M&I) Case excludes Inferred Mineral Resources from processing and revenue. Both cases use the same capital program. The capital and operating costs summarized below are for the Base Case. Section 1.9 describes the economic analysis and the qualifications associated with the use of Inferred Mineral Resources.

 

The cost estimate follows the mine plan presented in this report. Mining costs are based on scheduled material movements, haul cycles, and equipment requirements. Processing capital and operating costs use the discipline estimates presented in this report for the initial 35,000 short ton per day (stpd) plant and expansion to 70,000 stpd, together with the current crushing and sorting estimates. Stockpile placement, reclaim, and sorter-reject handling costs are based on the loading, haulage, and support duties. The estimate also includes site infrastructure, environmental and closure works, general site facilities, and owner’s costs.

 

Development requires US$1,169 million before production, including US$78 million of preproduction mining expenditure capitalized as prestripping. A further US$658 million is scheduled for mine and mill expansion during Years 1 to 4. The expanded plant begins operating in Year 4 and reaches full throughput in Year 5. Sustaining expenditure and closure allowances total US$693 million, bringing total project capital to US$2,521 million, as summarized in Table 1-7.

 

8
 

 

The capital and operating cost estimates are preliminary, with an estimated accuracy of approximately ±50%, reflecting the current level of engineering definition. The accuracy range is not a statistical confidence interval. Capital includes 25% contingency. No separate project operating-cost contingency has been added. Costs are expressed in 2026 US dollars, with no additional escalation for future inflation or exchange-rate movement.

 

Table 1-7 Project Capital Cost Summary

 

Component

Preproduction

 

US$M

Expansion

 

US$M

Sustaining and Closure

 

US$M

Total

 

US$M

Site Infrastructure 64 7 0 72
Mining 228 267 357 851
Processing and Material Handling 622 251 131 1,004
Environmental and Closure 0 0 60 60
General Site Facilities and Administration 14 2 7 23
Owner’s Costs 7 0 0 7
Subtotal Before Contingency 935 527 555 2,017
Contingency (25%) 234 132 139 504
Total Capital 1,169 658 693 2,521

 

Source: NLM (2026). Note. Base Case. Expansion covers Years 1-4; sustaining and closure expenditure is scheduled from Year 5 onward. Rounded values may not sum exactly. US$M = millions of US dollars

 

Base Case operating expenditure totals US$16,247 million, or US$14.42 per short ton milled. Primary mining ends in Year 22, while crushing and sorting continue through Year 24 and mill treatment of stored middlings continues through Year 46. Processing and material handling account for approximately two-thirds of operating expenditure over the project life. Table 1-8 summarizes the principal cost components.

 

Table 1-8 Base Case Operating Cost Summary

 

Cost Category Total Cost
US$M
Average Cost
US$ per st milled
Mining 5,428 4.82
Processing and Material Handling 10,377 9.21
Environmental Activities 42 0.04
General Site Administration 401 0.36
Total Operating Costs 16,247 14.42

 

Source: NLM (2026). Note. Operating costs exclude preproduction expenditure included in capital. Unit costs use 1,126.81 Mst of mill feed and are calculated before rounding. $M = million of US dollars, st = short ton

 

9
 

 

1.9Project Economics

 

1.9.1Cautionary Statements

 

1.9.1.1Certainty of Initial Assessment

 

The IA is preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to have the modifying factors applied to them that would enable them to be categorized as Mineral Reserves. There is no certainty that the IA will be realized.

 

1.9.1.2Mineral Resources are Not Reserves

 

Mineral Resources, unlike Mineral Reserves, do not have demonstrated economic viability. The IA does not establish Mineral Reserves or the level of technical and economic confidence of a pre-feasibility or feasibility study.

 

1.9.2Economic Summary

 

The economic analysis uses annual, unlevered cash flows in 2026 US dollars. Commodity prices are US$5.00/lb copper, US$25.00/lb molybdenum and US$50.00/troy oz silver. A rhenium credit uses 25-parts per million (ppm) in dry molybdenum concentrate, 25% payability and US$2,250/lb. The model includes capital, operating costs, property holding, concentrate deductions, working capital, and taxes. It excludes debt, interest, and financing costs.

 

Net present value (NPV) is the sum of discounted project cash flows and is calculated at an 8% discount rate from Year -3, the undiscounted starting period. Production Year 1 is discounted for three years. Development occupies Years -3 through -1, processing continues through Year 46, and closure and water-treatment capital extends through Year 55. Payback is measured from the start of production. The internal rate of return (IRR) is the discount rate at which NPV is zero. Table 1-9 compares the Base Case including Inferred Mineral Resources with the M&I Case excluding Inferred from processing and revenue.

 

In the Base Case, inferred material comprises 240 Mst, or 17.1% of the 1,401 Mst primary processing feed after shovel sorting and before crushing and belt sorting. Including stockpile reclaim, inferred material contributes 156 Mst, or 13.9% of the 1,127 Mst evaluated mill feed. These are feed-mass proportions and do not represent shares of revenue or NPV.

 

The model includes 21% federal income tax, 5.3% Idaho income tax, and 2% Idaho alternative minimum tax with subsequent credits, together with depreciation, depletion, and loss carryforwards. No royalty is modeled. Working capital is 20% of annual operating costs, with the remaining balance released after processing ends. The tax and royalty assumptions are stated in Section 19.4.5; the issuer-provided fiscal basis is described in Section 19.4.6, Fiscal Information Provided by the Registrant.

 

10
 

 

Table 1-9 Summary of Project Economics

 

Measure Unit Base Case Including Inferred M&I Case Excluding Inferred
Pre-Tax NPV @ 8% US$M 2,308 1,823
After-Tax NPV @ 8% US$M 1,878 1,482
Pre-Tax IRR % 19.84 18.26
After-Tax IRR % 18.50 17.04
Pre-Tax Payback from Production years 5.8 5.9
After-Tax Payback from Production years 5.9 6.0
Undiscounted Pre-Tax Cash Flow US$M 13,734 11,545
Undiscounted After-Tax Cash Flow US$M 11,372 9,591
Evaluated Mill Feed Mst 1,127 971
Payable Copper Mlb 1,748 1,509
Payable Molybdenum Mlb 906 819
Payable Silver Moz 59 50
Net Smelter Revenue US$M 32,513 28,907
Operating Expenditure US$M 16,247 14,830
Total Project Capital US$M 2,521 2,521

 

Source: NLM (2026) Note. Values are rounded. The Base Case includes Measured, Indicated and Inferred Mineral Resources. The M&I Case excludes Inferred material from processing and revenue, retains the pit, calendar and capital program. $M = million of US dollars, Mst = million short tons (US 2,000 lb), Mlb = million pounds, Moz = million troy ounces, IRR = internal rate of return, NPV = net present value

 

Cash cost (C1) includes site operating costs, operating-period property holding, and cash selling charges; all-in sustaining cost (AISC) adds sustaining and closure capital. Both exclude initial and expansion capital, income tax, financing, and working capital. Copper equivalent (CuEq) values payable copper, molybdenum, silver and rhenium at the analysis prices and divides their combined gross value by the copper price. Base Case C1 cash cost is US$2.63 per payable lb CuEq, and AISC is US$2.73 per payable lb CuEq. These are economic production equivalents, not resource grades.

 

Base Case sensitivities show material exposure to molybdenum price and operating expenditure. A 10% molybdenum-price decrease reduces pre-tax NPV at 8% to US$1,633 million; a separate 10% operating-cost increase reduces it to US$1,815 million. These sensitivities use the fixed production schedule.

 

1.10Project Risks

 

1.10.1Mineral Resource

 

The CuMo deposit is a large, zoned porphyry-style system, and the current Mineral Resource estimate is based on the available drill-hole database and geological interpretation. Additional drilling, particularly in areas of wider drill spacing or near the limits of the modeled mineralized zones, may result in changes to the interpretation of mineralized domains, grade distribution, and resource classification. Infill drilling is recommended to support conversion of Inferred Mineral Resources to higher-confidence categories, while step-out drilling may identify extensions to known mineralization or modify the interpreted limits of the deposit.

 

11
 

 

There is risk that future geotechnical, geometallurgical, density, structural, or metallurgical data could affect the Mineral Resource estimate or the classification of material considered to have reasonable prospects for eventual economic extraction. Changes in metal prices, operating cost assumptions, metallurgical recoveries, processing assumptions, or cut-off criteria could also affect the tons and grades reported as Mineral Resources.

 

These risks are considered typical for a project at the IA stage and can be reduced through additional drilling, data validation, geological modeling, density determinations, metallurgical test work, and updated resource estimation during future study phases.

 

1.10.2Mining

 

1.10.2.1Mining Selectivity and Sorting Response

 

Shovel sorting depends on grade discrimination at the scale of individual excavation parcels. The 50 ft resource blocks are larger than the nominal 85-metric-tonne sorting parcel, approximately 94 st. Fragmentation, blast movement, digging, and mixing could reduce separation performance. A smaller resource block size closer to the selective mining unit (SMU), the parcel that can be separately excavated and directed to processing or waste, should be considered in future studies. Change-of-support work, which relates grades estimated at the resource-block scale to grades at the SMU scale, is required to determine an appropriate smaller block size and the grade variability supported by the data. Given the large blocks relative to the SMU, the current mine plan assumes dilution and/or loss are incorporated in the model block grades and applies no additional mining dilution or separate mining-loss deduction.

 

A 0.8 sorting response factor has been included in this study to allow for imperfect mining selectivity. It reduces modeled grade discrimination relative to the sampled variability when estimating the mass and metal reporting to each sorting product. Mass yield is the fraction of feed mass retained in a product; metal retention is the fraction of contained metal retained. Both depend on material type, sensor performance, and physical sorter settings, and each upstream separation changes the feed presented to the next stage. Representative shovel and belt trials are required to establish achievable selectivity, sorting losses, throughput and loading productivity.

 

1.10.2.2Pit Slopes and Water Management

 

The preliminary slope assessment has limited spatial and depth coverage and did not include groundwater pressure effects. Different wall conditions or water pressures could change phase geometry, stripping and access, while greater inflows could increase pumping requirements and disrupt working areas. Geotechnical and hydrogeological investigations should establish sector criteria, dewatering, and depressurization requirements, and their effects on the mine sequence.

 

1.10.2.3Construction Rock and Placement Facilities

 

The mine must supply suitable rock at the time required for staged tailings embankment construction. Physical and geochemical suitability has to be demonstrated and linked to the rock available by phase and period. Changes in suitable rock supply could require different routing, additional handling, or a revised construction sequence.

 

12
 

 

1.10.2.4Long-Term Middlings Storage and Reclaim

 

Middlings storage begins in Year 1, reclaim starts in Year 9 and continues through Year 46, and inventory peaks at approximately 617 Mst in Year 21. The study assumes no storage-related reduction in metallurgical recovery. Aging, oxidation, degradation, and changing moisture or handling conditions may affect recovery, reclaim productivity, and costs. Tests on stored material should establish acceptable stockpile quantities and storage durations. The placement and reclaim plan should address drainage, blending, access, and equipment renewal over the full reclaim period.

 

1.10.2.5Workforce and Fuel Costs

 

Recruiting and retaining experienced operators, maintenance personnel, and technical staff is an operating risk for the remote site. Workforce availability, transport, and shift arrangements may affect costs and productivity. Diesel prices are also uncertain over the operating life and materially affect truck haulage and support-equipment costs. The next estimate should develop the staffing and transport plan, obtain current labor and fuel inputs, and test their effects on fleet productivity and project economics.

 

1.10.3Mineral Sorting

 

The open-pit-mined material will be processed by shovel sorting method in the bulk ore sorting (BOS) stage 1 system. The BOS stage 1 system will comprise a shovel equipped with a shovel-mounted sensor system. The sensor will use X-Ray Fluorescence (XRF) technology to scan the materials dynamically as the shovel bucket gets filled and estimate the grade and characteristics of the materials on a bucket-by-bucket basis.

 

The sensor data will be processed in real time to sort and classify the feed materials based on pre-defined Cu and Mo grades, enabling routing of the excavated materials to the appropriate destinations, such as the downstream crushing station, or the waste rock stockpile. The feed materials will be sorted and diverted into two product streams: Accept and Waste. The Accepted materials (Primary and Middlings) will be transferred to the crushing circuit using trucks. The Waste materials will be transferred to the waste rock stockpile using trucks.

 

The technology envisioned in this IA for BOS stage 2 and stage 3 sensors will utilize Prompt-Gamma-Neutron-Activation-Analysis (PGNAA or equivalent) to continuously measure the elemental composition and Cu and Mo grades of the material as it travels on the conveyors. Neutrons will interact with the ore and generate characteristic gamma rays, which will be detected and analyzed to determine elemental concentrations of Cu and Mo. The measured Cu and Mo grades will then be compared against the pre-defined sorting criteria to classify the material.

 

As with bulk and particle sorting technology, additional testing is required to better estimate the final results expected from particle sorting as additional exploration drilling is conducted and more core specimens are available for bench-scale testing.

 

1.10.4Processing

 

Metallurgical test results are based on composite samples of the three primary ore types. Variability sample testing and testing of blended ore types may yield different results. Ore hardness testing is limited due to the scope of an IA and subsequent testing may identify harder ore material. Dewatering testing of the tailings and concentrates has not been performed to date, and design parameters are based on industry standards. Additional metallurgical testing is recommended for the PFS.

 

13
 

 

The current processing plan will develop a large middlings stockpile which will be processed years after the ore is crushed and stockpiled. Sulfide mineral surface oxidation may reduce flotation recoveries on the stockpiled material. This potential has not been evaluated as there is no data on this ore to determine the degree of impact on recovery due to oxidation.

 

1.10.5Project Infrastructure

 

The planned mine will be a greenfield site and requires construction of mine and process related infrastructure, including the TSF which the embankment serves as a primary waste rock facility (WRF). Access roads in and around the project site will be required. Upgrades to existing gravel roads will likely be required to be made; however, some extents along the alignment may be found to require significant upgrades due to local landslides or avalanche chutes.

 

Several water supply sources have been identified at this stage: purchasing or leasing water in the Boise Basin, an appropriation from the Payette River which could be traded for a Boise Basin right, subsurface aquifers, and excess water from an adjacent drainage basin. All potential sources would be subject to water rights allocations and regulatory assessments.

 

There is a risk that the designs, costs, and implementation timelines for the provision of this infrastructure may not be as anticipated, increasing costs, and schedule.

 

1.10.6Permitting

 

At this time, no issues have been identified that would materially affect the potential to extract Mineral Resources from the CuMo project. However, the mining plan of operations may identify and characterize issues that could extend the permitting timeline or increase permitting-related costs. The IA described in this report does not quantify the schedule or costs associated with preconstruction and permitting activities.

 

Previous environmental analyses have identified the presence of the plant Sacajawea’s bitterroot, a plant listed (but not threatened or endangered) under the Endangered Species Act, and potential habitat for Endangered Species Act wildlife, and USFS sensitive species. These potential issues are known, and Idaho Copper is aware as these issues have been considered and cleared for past phases and the current phase of planned exploration drill programs. There is active litigation with the Idaho Conservation League and Audubon Society challenging the USFS Decision Notice issued in March 2025 approving the 4-year Exploration Plan of Operations (PoO). Idaho Copper’s required PoO for 2026 was approved by the USFS on September 9, 2026, and exploration and related approved activities commences on October 4, 2026.

 

Environmental studies will be conducted during pre-feasibility study (PFS) and feasibility study (FS) stages to further investigation site conditions for potential impacts. The findings will be included in NEPA documents with proposed measures to mitigate potential impacts.

 

The planned mine is located in an area that is used for dispersed summer recreation and fall big-game hunting and is well known to residents of the Boise area. Public interest in the project is expected to be elevated, and environmental organizations, including the Idaho Conservation League and Sierra Club, have communicated project-related information to their constituents. Accordingly, organized public opposition to mining activities should be anticipated and considered in future permitting and stakeholder-engagement planning.

 

14
 

 

Table 17-2 in Section 17.2, summarizes the federal, state, and local authorizations and permits that will be required for mining. No applications for mining authorizations and permits have been filed with federal, state, and local agencies. Reclamation bonds will have to be posted with the state of Idaho and the USFS.

 

1.10.7Economic Risks

 

1.10.7.1Project Strategy Risk

 

Overall, it is not expected that a major revision to the CuMo project strategy would be identified during the PFS (low to moderate risk level). The material movement approaches have the potential to be optimized at the PFS level; however, the current truck haulage strategy to conveyors for near plant material movement for the IA is consistent with general mining practices, but operating costs could be potentially improved via the implementation of in-pit crushing and conveying (IPCC).

 

Mineral sorting as contemplated in this study is not a mature technology at such a large-scale mine operation. There is a risk that the sorting assumptions used may not prove accurate at this scale. Elimination of the mineral sorting pre-process from the strategy has the potential to reduce the economic prospects of the project.

 

1.10.7.2Commodity Prices and Concentrate Terms

 

Molybdenum contributes 66% of modeled Base Case net product revenue, making project returns particularly sensitive to its price. Copper, silver, and rhenium prices, product payability, treatment charges, and transport terms also affect revenue. The long production period exposes the project to sustained changes in prices and sales terms. The next economic evaluation should test downside price and commercial scenarios for the selected development configuration.

 

1.10.7.3Capital Requirements and Operating Performance

 

The preliminary estimate leaves uncertainty in installed quantities, site preparation, equipment pricing, and construction productivity. Cost increases or slower ramp-up would increase funding requirements and defer returns. The operating estimate also depends on achievable haulage and reclaim productivity, fuel and power costs, labor availability, and maintenance. The long reclaim period makes equipment reuse, rebuilds, and replacement timing material assumptions. PFS engineering should obtain updated supplier and operating inputs and test the effects of higher costs and slower ramp-up on funding requirements and project returns.

 

1.10.7.4Permitting and Pre-Construction Schedule

 

The permitting and development schedule required to construct the project may vary from the schedule assumed in the current study. This risk is asymmetric, with a materially greater potential for downside impact than upside benefit. The risk is increased by the seasonal nature of site access and construction conditions, which may be more difficult during winter months. As a result, relatively minor delays could have a disproportionate effect if they shift critical-path activities into periods of limited access or reduced construction productivity, potentially compounding the overall schedule delay.

 

15
 

 

1.10.7.5Process Recovery

 

There is a risk that achieved recoveries could be lower than estimated, reducing the revenue and economic returns of the project. The process recovery estimates will be refined as part of the PFS as additional sampling and testing is completed.

 

1.11Project Opportunities

 

1.11.1Mineral Resource

 

If successful, additional drilling to the west could provide an opportunity to increase the Mineral Resource, both in terms of volume and higher-grade material, and add further process feed within the currently envisioned open pit or support future evaluation of an expanded pit configuration. Any such opportunity would require additional drilling, geological modeling, resource estimation, and mine planning studies to confirm its significance and potential impact on project economics.

 

The mineral deposit and a previous Mineral Resource estimate do include tungsten. The potential for recovery and an additional revenue stream has not been considered in the IA. However, a tungsten recovery and processing circuit is intended to be further investigated in the PFS stage.

 

Additional infill drilling may also provide an opportunity to improve confidence in the Mineral Resource estimate by supporting conversion of lower-confidence resource categories to higher-confidence categories, refining mineralized domain boundaries, and improving confidence in grade continuity, density assumptions, and local block model estimates.

 

This opportunity could provide either more process feed within the current envisioned open pit or increased size of the open pit to the west. This expansion can be done but may have some effect on the location of the mill, sorting plant, or crusher.

 

1.11.2Mining

 

1.11.2.1Material Handling and Development

 

Alternative starter pits and access arrangements may reduce initial stripping and excavation for roads, crusher platforms and conveyor routes. In-pit crushing and conveying (IPCC), in which a crusher in or near the pit feeds a conveyor system, would reduce truck requirements and exposure to diesel-price changes, while changing the capital requirements for the project. The PFS should compare conveying mineralized feed while trucking waste and assess a separate waste-crushing and conveying system where the waste quantities and destinations justify it. Starting with truck haulage and introducing IPCC later offers a further development sequence to evaluate.

 

The comparison should include practical crusher sites, conveyor routes and relocations, civil works, power, commissioning, availability, and fallback arrangements. Complete production schedules and economic models are needed to compare initial funding, operating costs, and equipment renewal.

 

16
 

 

1.11.2.2Sorting Response and Mine Planning

 

Developing response curves over variable physical sorter settings would improve the selection of material sent to each processing stage. These curves should reflect each material type and the effect of upstream sorting on downstream feed and should be compared with the fixed sorter response used in this study.

 

Future work should:

 

●Link the tested responses to a practical selective mining unit, grade control, and the mine schedule

 

●Compare shovel and belt combinations, fewer stages, bypass routes, targeted sensor installation, and staged deployment

 

●Assess the resulting metal retention, throughput, stockpile creation, productivity, and capital requirements together

 

1.11.3Mineral Sorting

 

The bulk sorting analysis was originally conducted on drill core that was sampled on a standard 10 ft interval. However, during 2023-2024, the Company employed an independent ore scanning firm which used XRF technology to scan 33,000 feet of drill core on 1.5-centimeter (cm) intervals. Thus, heterogeneity of the deposit was shown to be appropriate on a very small scale. With multiple stage sorting and splitting, smaller size packets of material can be measured; however, this needs to be balanced with practical mining practices and excavation selectivity. As heterogeneity increases with reduced scale, there is potential that better segregation of waste, mill primary feed, and middlings is possible. The opportunity would be for increased waste rejection, and ultimately reduced middlings fractions, to improve the economics of the project. Idaho Copper intends to use similar, small interval XRF scanning for future drill cores produced from the site.

 

However, the potential for mineral optimization from the heterogeneity of the deposit may not be adequately quantified from exploration-level data. Upon commencement of mine operations, Idaho Copper would obtain higher-resolution sampling and sorting across the continual exposure of the CuMo deposit. This has the potential to enhance project economics but cannot be quantified ahead of site development. Technology that is capable of penetrative scanning of ore within the mine face and crushed ore (e.g., MRI or atomic absorption methods) can augment the XRF scanning technology. This can refine the capability to classify and segregate ore as primary, middlings, and rejects, which in turn may increase head grade entering the plant and improve overall economics.

 

The field of mineral sorting is the subject of significant research and development. There exists an opportunity for this project to exploit improvements in this technology that have been observed and likely will be developed ahead of Project implementation.

 

1.11.4Processing

 

Additional metallurgical work should help to determine optimum grind size (the current assessment is based on the finest grind tested to date), analyze recoveries of the various metals, and analyze the effects of the higher grade coming from the mineral sorters on metal recoveries. Improvements in penetrative scanning technology can be considered and implemented to further improve the head grade feed to the plant. Optimization of reagents to reduce costs and improve metallurgical recoveries has the potential to improve project economics.

 

The ore sorting approach results in a large stockpile of middlings material that is intended for future processing through the mill after mining is completed. A sulfide ore leach pad and associated leaching circuit could provide a relatively low-cost approach to extract metals from this middling material shortly after crushing and ore sorting, rather than placed in long-term stockpile. This could provide additional revenue in the early years of the project rather than multiple decades in the future. There have been considerable advances in sulfide leaching techniques in recent years, and these will be evaluated in the PFS.

 

17
 

 

The current plan processes the middlings stockpile in the mill without further upgrading. There may be an opportunity to re-process the stockpile material through the ore sorting plant to upgrade the ore grade prior to milling. Utilizing the existing ore sorting plant in this capacity may improve cash flow and reduce operating costs in the later years of mine life.

 

Presently, the project assumes transportation of copper concentrates off-site for smelting and refining. Options to expand the on-site process capabilities may provide a more cost-effective use of capital expenditures and operating expenditures while increasing revenue. Options under consideration for the PFS include leaching sulfide concentrates, which can produce copper cathodes. This would allow Idaho Copper to produce marketable cathodes without shipment of concentrates to off-site and offshore smelters and refineries.

 

The trade-off studies for additional on-site or downstream process infrastructure includes consideration of a molybdenum roaster and/or a bolt-on iron-molybdenum plant using molybdenum-rhenium concentrates processed onsite. These facilities would further allow for an acid plant for sulfur recovery, with the potential for rhenium recovery. The molybdenum roaster would produce MoO3, a steel furnace feedstock, while a ferromolybdenum (FeMo) plant would provide FeMo, which is a feedstock for electric arc steel furnaces. These capabilities could augment the revenue stream, understood associated with further CAPEX, and increase the NPV.

 

As previously noted, tungsten mineralization is observed within the CuMo deposit and has previously been included in a Mineral Resource estimate. Tungsten recovery and processing will be assessed for inclusion in the process approach to provide an additional revenue stream for the project. Further testing is required to determine if there may be opportunity to economically recover tungsten from the mineralized material.

 

1.11.5Project Infrastructure

 

Further studies and site investigation may allow for optimization of infrastructure designs, costing, and schedule. The following are opportunities that could be optimized during trade-off studies to identify viable options that are worth pursuing.

 

A potential option that could improve concentrate transportation while minimizing impact and use of the road network, may be a gondola transport system from the concentrator downhill to a rail loadout area. Although this introduces a capital expenditure as well as operational maintenance, the benefit is reducing similar costs associated with overland truck transport. This approach also reduces the introduction of a portion of the large-scale traffic on the local roads, which otherwise might attract opposition from the local communities. In addition, a downhill run of a gondola-based concentrate transport can generate electricity for use in the project.

 

There is mutual benefit to Boise County, USFS, and Idaho Copper for improvements to the local county roads and USFS roads. The improved access roads will provide for wider travel surfaces for vehicles, shoulders and ditches, improved sight lines, and potential traffic passing zones. A shared approach for the capital expenditure for initial improvement and on-going maintenance costs can be part of a shared use agreement for the increased traffic.

 

18
 

 

As previously noted, Idaho Power has intention to install or upgrade transmission lines to the vicinity of Placerville to the southwest (10 miles) and the vicinity of Garden Valley to the northeast (9 miles) of the CuMo project. Depending on the timing of these construction projects, and the plans of Idaho Power in terms of power that would be available from expansions and upgrades, Idaho Copper’s project timing may incur an incremental cost to continue electrical power to the site. At the IA stage, there was limited evaluation of trade-offs for alternative electrical power sources. As power needs for the project are refined through future detailed development, such power options can more readily evaluated on a fit for purpose basis.

 

At the current understanding and expected fuel supply needs for the process plant, trucking of natural gas to an on-site storage facility is the likely scenario. However, the opportunity to extend an existing gas pipeline to the site may become viable.

 

Further investigation of subsurface conditions and evaluation of surface water availability will be necessary to determine opportunities to evaluate sources. However, further evaluation of the process plant makeup water needs, and overall water balance can include approaches to minimize water use as well as maximize recovery from the TSF pond. Currently, there are water appropriations on the Boise River available for purchase or rent, or potentially water appropriations from the Payette Basin which could be traded for Boise rights, which will be pursued during the pendency of the PFS.

 

Presently, there are strategic, near-pit and near-process facility external WRFs to allow for minimizing the waste and reject material haul. Further optimization of the mine plan and production schedule could lead to classification of additional waste material. This could be used to construct an additional toe buttress against the TSF embankment.

 

Geological and hydrological study of the TSF extents will be required; however, exploration drilling results by Idaho Copper suggest that groundwater is observed at depths exceeding 2,500 ft below ground surface. Detailed embankment design may be optimized when foundation conditions are verified. Furthermore, containment and seepage control aspects can be optimized, such as the extent of a liner system, where seepage is not an observed risk.

 

The timing of TSF construction is directly correlated to the production schedule. The PFS stage will include examining a heap leach facility to extract metals from the middlings material that would otherwise be stockpiled. A heap leach facility inherently will lead to less ore feed to the process plant and subsequently less tailings volume requiring storage. A reduced TSF size directly reduces costs to construct and operate the TSF.

 

1.11.6Economic Opportunities

 

1.11.6.1Real Option Value

 

In the case of a large, long-life, open-pit mine such as is contemplated for the CuMo project, there exists significant optionality that can be leveraged to improve project cashflows and values. The simple sensitivity analysis conducted in Section 19.5.7 assumes a constant operating strategy, even as assumptions are varied. In practice, management has the option to alter strategy in response to those variations. Downsides can be mitigated, and upsides can be leveraged for greater returns.

 

19
 

 

It is also expected that the mine would run using a dynamic ore binning approach where sorting strategies for recovered economic value of the separation of primary mill feed with middling stockpile material strategies, and mining rates will all be varied in real time to maximize returns as prices and costs vary. The benefits of this strategy are not reflected in the central estimate approach to valuation summarized in this report.

 

1.11.6.2Material Handling Costs and Capital Requirements

 

Changing the balance between truck haulage and IPCC could improve project economics through lower operating costs or a different capital expenditure sequence. The mining-method tradeoff should compare the full installed, operating and equipment-replacement costs of each configuration over the project life.

 

1.11.6.3Concentrate Transport and Roasting

 

A molybdenum roaster at a railhead, together with alternative concentrate transport and sales arrangements, may improve product value or reduce logistics costs. The project should compare the current concentrate-sales approach with the full capital, operating, transport, permitting and commercial requirements of the alternative. Rhenium recovery and product credits should be supported by representative test work and market terms.

 

1.11.6.4Project Strategy Opportunity

 

While the probability of a major revision to project strategy can be considered low to moderate, there are options to be evaluated during the PFS within trade-off studies that may allow for improvement to the strategy and economics. These are briefly summarized below as they were discussed in previous sections.

 

●IPCC infrastructure, as opposed to a conventional truck-shovel approach, applied with appropriate mine sequencing, to reduce material movement costs as the ore sorting process requires multiple rehandling cycles

 

●Inclusion of a heap leach process to recover revenue from middling material early in the life of mine rather than maintaining long term stockpiles with delayed value from the copper

 

●Onsite or downstream construction of a molybdenum roaster, and potentially an iron-molybdenum plant, to create value-added products, enhancing revenue, while capturing sulfur through an acid plant for sale

 

●Consideration and infrastructure to capture rhenium during the process stream in a molybdenum roaster

 

●Further study of tungsten mineralization within the CuMo deposit for processing and revenue stream

 

●Production of copper cathodes onsite through copper concentrate leaching

 

●Power trade-off studies to optimize the use of energy and reduce costs

 

●Gondola transport study

 

20
 

 

1.11.6.5Commodity Price Opportunity

 

There is a risk that all commodity prices may not be consistent with assumptions made in this study. Higher prices, both realized and forecasted, would lead to re-optimization of the mine and processing plans with a potential to create additional value beyond that shown by the sensitivity analysis summarized in Section 19.5.7.

 

1.11.6.6Capital Cost Opportunity

 

Opportunities to reduce or defer capital expenditure may be realized in future studies. Care should be taken when considering the relationship between lower capital opportunities and technical risk to the project.

 

Options noted above include trade-off studies to consider IPCC, gondola transport of concentrates, and several process plant options, all of which will require capital; however, there may be an optimal point in the production schedule to implement or expand after production is underway.

 

1.11.6.7Operating Cost Opportunity

 

Operating costs may be lower than forecast for this study. Lower costs should feed into both strategic and short-term mine planning, to allow optimization of stockpiling, sorting, and mill feed strategies.

 

1.11.6.8Schedule Opportunity

 

At this time, there is not a definable schedule opportunity. Further detailed open pit design, production schedule options, and process approaches will need to be advanced during PFS to identify potential schedule improvements.

 

1.11.6.9Process Recovery Opportunity

 

Further metallurgical test work will allow for optimization of the process flow sheet and plant design in the PFS and FS. Better than planned recoveries are possible.

 

1.11.6.10Pit Slope Angle Opportunity

 

This is not considered to be a significant opportunity from an economic perspective. Strip ratios are relatively low, and incremental change in waste-movement volumes do not impact the overall project economics significantly.

 

1.12Conclusions and Recommendations

 

1.12.1Mineral Resources

 

Mineral Resources, determined for this estimate are effective as of August 30, 2018. New exploration DDHs commenced on the CuMo project on October 4, 2026. The information, core samples, and subsequent metallurgical testing will provide new data necessary to develop an updated Mineral Resource Estimate for the CuMo project.

 

21
 

 

Exploration work consisting mainly of drilling and laboratory analysis is required to reach pre-feasibility. It is estimated that a total of approximately 16 additional core holes for 40,000 ft of combined geology and geotechnical drilling are required, including:

 

●In-fill drilling

 

●Delineation drilling

 

●Geotechnical drilling – requires oriented core recovery system and/or borehole televiewer surveys to obtain in-situ structural geology data

 

●Metallurgical Drilling sample – large diameter hole (PQ size) recommended

 

●Condemnation drilling waste dump, mill, and tailings site

 

Given the large scale and zoned nature of the CuMo mineralized system, future resource drilling should prioritize areas that have the greatest potential to improve project economics, support conversion of Inferred Mineral Resources, refine early mine phases, and improve confidence in higher-value mineralized domains.

 

It is also recommended that the geological model and Mineral Resource estimate be revisited and updated following completion of any material new drilling or technical work. This update should include reassessment of mineralized domain interpretations, grade continuity, density assumptions, variography, resource classification criteria, and reasonable prospects for eventual economic extraction.

 

These recommendations are intended to support advancement of the project toward a higher-confidence technical study and should be completed prior to any future PFS.

 

Further condemnation drilling of waste dump, mill site, and tailings pond areas, can be completed outside of the exploration program as those borings are a distance from the ore body and require limited depth below the surface.

 

1.12.2Pit Geotechnical

 

A geotechnical-focused investigation and assessment have not been initiated. The following summarizes the desktop and field activities that are recommended for the next steps of geotechnical assessment:

 

●Desktop evaluation from which the observations can be used to develop an optimized field geotechnical investigation and quantitative assessment. The following items can be completed on existing information.

 

○Geotechnical database QA/QC assessment, with respect to geology, to evaluate the possibly poor and variable geotechnical-related data observed in the existing data set

 

○Select a sub-set (~10-20%) of planned resource core drill holes that give good spatial coverage of the proposed pit walls, and from multiple drilling campaigns

 

○Undertake quantitative basic geotechnical logging using the full core photographs, if the photographs are available, of these drill holes to obtain total core recovery (TCR), solid core recovery (SCR), rock quality designation (RQD), and fracture frequency (FF/m or FF/ft)

 

○Log the core photographs to identify major structures and compare to the 3-D geology model

 

22
 

 

○FF/m vs RQD plots for both the existing and the photo-logged data-sets for quantitative comparison

 

○Assessment of differences to determine whether variance is systematic or random, and consequently decide on the respective approach to address (e.g., apply correction factor, re-logging more of the drill holes)

 

○Qualitative assessment of the rock susceptibility to deterioration by comparing core in the photos (fresh), to the current condition of the stored core (aged)

 

●Geotechnical-specific diamond-cored drill holes targeted to provide coverage of the proposed interim and ultimate pit walls, and compatible with the pit depth.

 

○Geotechnical logging to RMR89 system, or agreed upon system, for consistency

 

○Field (empirical and point load) and laboratory (uniaxial and triaxial compressive strength and direct shear) testing of fresh core to determine intact rock strength and structural zone material to determine shear zone strength

 

○Calculate Rock Mass Rating (RMR) and Geological Strength Index (GSI) values and conduct comparison with lithology, alteration and mineralogy zones of the 3-D geology model to establish broad geotechnical domains

 

○Establish pit sectors and domain-representative sections to conduct pit slope stability analyses and select pit design angles

 

1.12.3Mining

 

The IA provides a sufficient mining basis to advance the CuMo project toward a PFS, following the recommended additional studies and tradeoffs. The next work should assess shovel selectivity and sorting response, define the validation needed within the PFS and select the preferred development and material-handling configuration. The PFS investigations and engineering should address pit slopes and water management, construction-rock suitability, long-term middlings condition and reclaim, and fleet and workforce requirements. The study remains based on Mineral Resources and does not declare Mineral Reserves.

 

1.12.4Mineral Sorting

 

Idaho Copper should further engage and evaluate bulk and particle sorting technology providers to advance testing of penetrative technologies (e.g., MRI, PGNAA, or pulsed fast thermal neutron activation [PFTNA]) such that base assumptions can be developed to apply methodologies appropriate for a large-scale mine operation. These technologies, and other mineral sensing techniques, can support improved economics for the measurement of molybdenum in lower grade applications. This may include further testing, using samples collected from the CuMo project during future exploration campaigns, to assess the performance of bulk sorters at a bulk scale and an opportunity to compare different technologies.

 

Additionally, testing of the crushed product fines fraction mineralogy is recommended to determine if screening and direct feeding of this fraction to the mill would be beneficial to the project in an effort to reduce displacement of on-spec material.

 

23
 

 

1.12.5Processing

 

Additional metallurgical testing is recommended to confirm the design parameters for the mill. Variability samples consisting of at least 100 samples and representing all the ore zones at different elevations and pit locations should be tested. SAG mill, ball mill, crushing, and abrasion tests should be conducted on variability samples to confirm the mill sizing and maintenance requirements. Rougher kinetic flotation tests should also be conducted to quantify the flotation variability to be expected.

 

Composite samples representing specific periods of mill production should be developed and tested to determine the ore hardness and flotation recoveries. Solid-liquid separation tests should be conducted on the flotation test products to develop thickener and filtration design parameters. Mineralogy should be completed on the test feed and products to understand how recovery can be improved or processing costs reduced.

 

A large sample should be tested to further refine the copper-molybdenum flotation parameters. The separate copper and molybdenum concentrates produced in the test can be utilized for downstream testing. Downstream options that could be tested include chalcopyrite leaching to produce copper cathodes, molybdenum roasting to produce a higher value product, possible rhenium recovery, and sulfuric acid production.

 

High-pressure grinding rolls (HPGR) comminution and coarse particle flotation testing should be evaluated to determine the impact to site power consumption. Both technologies have the potential to reduce the required power.

 

Column leach testing of low-grade ore should be conducted to determine the copper recovery. The leaching will likely require biological oxidation of chalcopyrite to achieve economic recoveries. Leaching low-grade ore earlier in the project cycle has an opportunity to increase cash flow and NPV.

 

Testing to determine a viable recovery method for tungsten should be undertaken. Tungsten recovery could provide an additional revenue stream for the project.

 

1.12.6Project Infrastructure

 

Site access will be gravel roads from State Highways 21 and 55. Existing rail lines that parallel Highway 52 and Highway 55 can transport product from the CuMo project site if the product is trucked to a load-out facility in Horseshoe Bend. These will require discussion and agreements with both Boise Country and the rail line owner and operator such that they understand the increase and scale of traffic and steps to resume active use of the rail line. Alternatively, a trade-off study for gondola transport of concentrates, versus conventional truck haulage, should be a part of the PFS.

 

Electrical power transmission lines could be routed from the southwest (Placerville) and the northeast (Garden Valley) to provide sufficient power to Site. Discussion should be conducted with Idaho Power to understand the current long-term intent of infrastructure and options to extend power to the CuMo project site. A power trade-off study should be undertaken during the PFS to consider alternatives to extending lines to access the electrical grid.

 

Fuel for utilities and process equipment may be sourced as liquified natural gas (LNG) from the Intermountain Gas Company and shipped via truck from nearby Nampa, Idaho. LNG storage, vaporization, and regasification facilities will be required at the CuMo project site. Further studies for transportation needs and options are necessary as they may impact the plans for upgrading gravel roads and rail line needs.

 

24
 

 

Several water supply sources have been identified at this stage: purchasing or leasing water in the Boise Basin, an appropriation from the Payette River which could be traded for a Boise Basin right, subsurface aquifers, and excess water from an adjacent drainage basin. All potential sources would be subject to water rights allocations and regulatory assessments. Further study and investigation are needed into potential water supply sources through subsurface drilling to understand the current interpretation of deep regional aquifer. Additionally, Idaho Copper should commence discussion with appropriate regulatory agencies to develop viable surface water sources through appropriate permitting and rights allocations.

 

1.12.7Tailings Management

 

The TSF is effectively active as a WRF, based on unit quantities needed to construct the TSF embankment. A geotechnical site investigation including geotechnical sample collection and material characterization must be completed prior to engineering studies to inform the foundation parameters of the TSF.

 

Engineering studies should be conducted regarding TSF design and potential water management and treatment design, including:

 

●Updating the TSF and WRF designs based on field investigation results

 

●Developing tailings deposition plan and waste placement sequence to match pit development and mill output

 

●Detailed analysis of the water and load balance to predict the accumulation of mill reagents in the process water circuit from the tailings

 

1.12.8Environmental and Permitting

 

Idaho Copper should prepare a mining plan of operations and associated reclamation cost estimate that identify the locations of the mine, waste rock storage facilities, haul and access roads, power and water transmission corridors from source to point of use, the mill, tailings storage facility, and other supporting infrastructure. Operating plans should be developed concurrently with, and integrated into, the mining plan of operations. Idaho Copper should also develop comprehensive reclamation and closure plans for the proposed facilities and initiate the acquisition of any required water rights. Stakeholder engagement and outreach activities should continue throughout the permitting and project development process.

 

Following determination of the facility locations, Idaho Copper should coordinate with the appropriate state and federal agencies to identify the baseline studies required to support preparation of an environmental impact statement and should initiate those studies in a timely manner.

 

1.12.9Economic Conclusions

 

At an 8% discount rate, the Base Case including Measured, Indicated and Inferred Mineral Resources has an after-tax NPV of US$1,878 million and an after-tax IRR of 18.50%. The M&I Case, excluding Inferred Mineral Resources from processing and revenue, has an after-tax NPV of US$1,482 million and an after-tax IRR of 17.04%. These results indicate economic potential under the preliminary assumptions and support further technical and economic evaluation. Mineral Resources do not have demonstrated economic viability, and neither case establishes Mineral Reserves.

 

25
 

 

1.12.10Additional Studies and Tradeoffs

 

The recommended work is divided into two stages. Stage 1 comprises additional studies and tradeoffs to select the development configuration before PFS engineering. Stage 2 comprises the integrated PFS and its supporting investigations. The Stage 1 priorities are:

 

●Develop a geometallurgical model relating geology and material properties to sorting and metallurgical response, assess shovel and belt sorting, and define the validation program

 

●Compare mining methods, starter-pit development and material-handling arrangements

 

●Compare processing configurations and the sequence of capital expenditure

 

●Compare a railhead molybdenum roaster and concentrate transport arrangements

 

1.12.10.1Geometallurgical Model and Sorting Assessment

 

Develop an independently reviewed model relating geology, grade, mineralogy, and material properties to sorting and metallurgical response. Assess a smaller resource block size and change of support relative to the SMU. Review existing shovel and belt test data and use targeted supplier-supported assessments needed for the tradeoffs to develop preliminary material-specific response curves. Review the assumed block-grade treatment of dilution and loss, mixing and the 0.8 response factor. Define the representative sorting trials and validation required within the PFS program, including the effect of each separation on downstream feed.

 

1.12.10.2Mining Method and Development Tradeoff

 

Compare starter-pit, access and haulage configurations, including truck-and-shovel mining, IPCC, trucked waste, and separate waste conveying where justified. Evaluate truck and conveyor placement and reclaim of middlings, crusher and conveyor relocations and equipment renewal. Reconcile construction-rock requirements and available mine material by phase and period. Use complete schedules and economic comparisons to select the preferred mining and material-handling arrangement.

 

1.12.10.3Processing Configuration and Capital Staging

 

Compare initial and expanded plant capacities, fewer sorting stages or bypass routes, targeted sensor deployment, and staged installation. Integrate the available sorting responses with the mine schedule, direct feed, middlings storage, and reclaim. Include full installed and sustaining capital, construction timing, and operating costs, and assess the implications of extended storage for treatment and handling. Define storage-aging tests for the PFS program to establish acceptable stockpile quantities and storage durations. Select the configuration and capital sequence for PFS development.

 

1.12.10.4Railhead Roaster and Concentrate Transport Tradeoff

 

Compare concentrate transport modes and locations for a molybdenum roaster at a railhead against the current concentrate-sales approach. Include capital, operating and transport costs, product specifications, rhenium recovery, commercial terms and permitting requirements. Establish the preferred logistics and product strategy for the PFS.

 

Stage 1 should conclude with selection of the mining, sorting, processing, and concentrate-logistics configuration. Advancement to Stage 2 should depend on positive technical and economic results.

 

26
 

 

1.12.11Integrated Pre-Feasibility Study

 

Stage 2 comprises PFS engineering and the supporting drilling, site investigations and sorting or processing validation required for the selected configuration. The investigation scope should be developed from the Stage 1 findings and use the work already completed. The principal PFS tasks are:

 

●Complete resource drilling and representative geometallurgical, shovel- and belt-sorting, and metallurgical validation for the selected plan; include fragmentation, digging, and sensor trials and storage-aging tests to establish achievable selectivity, response, throughput, and the effects of extended middlings storage

 

●Complete geotechnical and hydrogeological investigations; develop slope criteria, dewatering and wall depressurization; test construction-rock suitability and integrate supply with staged embankment demand

 

●Develop pit and phase designs, access, production and final-wall blasting, grade control, material routing, stockpile placement and reclaim, and the production schedule

 

●Develop fleet and workforce estimates, staffing and transport arrangements, current labor and fuel inputs, and equipment reuse, rebuild, and replacement plans through the full reclaim period

 

●Coordinate processing, infrastructure and facility design with construction and permitting schedules; prepare capital, operating, and closure estimates and the integrated economic model, including updated commercial and tax inputs and downside scenarios

 

Stage 2 should conclude with a PFS assessment of technical and economic viability and a decision on further advancement.

 

1.12.12Recommended Study Budget

 

Table 1-10 summarizes the recommended program. The estimated budget considers a two-stage approach to a PFS study. The first stage, which commenced on October 4, 2026, with an exploration drilling program on the CuMo project, includes investigations, data collection and assessment, and tradeoff studies. This budget estimate allows US$13.5‒21.0 to complete these tasks. The PFS allowance includes US$8.5‒12.5 million for engineering and US$15‒25 million for supporting investigations and validation. These investigations remain within Stage 2.

 

The budget excludes land acquisition, the full environmental assessment and permitting program, and mine and facility construction. A purpose-built industrial sorting demonstration facility beyond vendor-supported trials requires a separate capital estimate within the PFS program.

 

27
 

 

Table 1-10 Recommended Study Program Budget

 

Recommended Work Estimated Cost US$M
Stage 1: Investigations and trade-offs evaluation  
Geology, metallurgical, and geotechnical drilling 10.0 ‒ 15.0
Metallurgical testing 0.2 ‒ 0.3
Geotechnical assessment 0.2 ‒ 0.3
Facility and infrastructure assessments 0.3 ‒ 0.6
Geology and resource model updates 0.5 ‒ 0.8
Geometallurgical model and sorting assessment 1.5 ‒ 2.5
Mining method and development tradeoff 0.2 ‒ 0.3
Processing configuration and capital staging 0.2 ‒ 0.3
Railhead roaster and concentrate transport tradeoff 0.4 ‒ 0.7
Stage 1 Subtotal: Additional studies and tradeoffs 13.5 ‒ 21.0
Stage 2: Integrated PFS program  
PFS engineering 8.5 ‒ 12.5
Supporting investigations and validation 15.0 ‒ 25.0
Stage 2 Subtotal: Integrated PFS program 23.5 ‒ 37.5
Total recommended study program 37.0 ‒ 58.5

 

Source: NLM (2026).Note. Preliminary budgeting allowances in 2026 US dollars. Stage 2 detail is included in its program total and is not additional expenditure. US$M = US dollar in millions

 

28
 

 

2 Introduction

 

2.1Issuer

 

The CuMo project is an advanced exploration project involving molybdenum (Mo), copper (Cu), silver (Ag), tungsten (W), and rhenium (Re); it is located approximately 37 miles (60 km) northeast of Boise, Idaho, USA, in the Boise National Forest. Idaho Copper Corporation (Idaho Copper), a Nevada corporation listed on the NYSE/Amex (COPR), holds its interest in the CuMo project through its direct subsidiary, Idaho CuMo Mining Corporation (ICMC), an Idaho corporation. For the purposes of this report, both Idaho Copper and ICMC are referred to as registrant of the CuMo project.

 

2.2Terms of Reference

 

Idaho Copper retained Barr Engineering Co. (Barr) to prepare this Technical Report Summary (TRS) and a Initial Assessment (IA) for the CuMo project and to issue an independent S-K 1300 report. The purpose of this TRS is to disclose the results of this IA for the Project. CuMo project is considered a material property under S-K 1300. This IA is based upon the information reported in Idaho Copper’s recent NI 43-101 and Preliminary Economic Assessment issued on October 23, 2026 (Palo, D.R., et al., 2026).

 

This technical report includes previous mineral resource information for the CuMo project from a statement prepared by Mr. Gary Giroux of Giroux Consultants Ltd. (Giroux) and reviewed by the current authors. That mineral resource statement was published as part of a technical report in October 2015. This technical report restates the mineral resource information for Idaho Copper and incorporates the results of the 2020 PEA (SRK, 2020), 2026 PEA (Palo, D.R., et al., 2026) and the IA study reported herein. The effective date for this Mineral Resource Estimate remains August 30, 2018.

 

2.3Responsibility

 

A summary of responsibilities for Qualified Persons (QPs) in the preparation of this report is shown in Table 2-1.

 

Table 2-1 QP Responsibilities

 

Name Company QP Responsibility
Daniel R. Palo, PhD, PE, P.Eng. Barr Engineering Co. Sec. 1; Sec. 2; Sec. 16; Sec. 22; Sec. 23
Russell J. Sheets, PE, SME-RM Barr Engineering Co. Sec. 3; Sec. 4; Sec. 5; Sec. 13.3 (including Sec. 13.3.1 and Sec. 13.3.2); Sec. 17; Sec. 18.1.5; Sec. 18.1.6; Sec. 18.2.4; Sec. 20; Sec. 21; Sec. 24; Sec. 25
Scott B. Sims, SME-RM Barr Engineering Co. Sec. 10; Sec. 13.2.3; Sec. 14; Sec. 18.1.2; Sec. 18.2.2; Sec. 18.2.3
Charlie Rehn, PE Barr Engineering Co. Sec. 15; Sec. 18.1.3; Sec. 18.1.4; Sec. 18.1.7
Justin L. Smith, PE, SME-RM Northern Lights Mining, LLC Sec. 13 (except 13.2.3 and except 13.3); Sec. 18.1 (integrated cost summary); Sec. 18.1.1; Sec. 18.2 (integrated cost summary); Sec. 18.2.1; Sec. 19
Gareth Flitton, CPG, Pr.Sci.Nat. Dahrouge Geological Consulting USA LTD. Sec. 6; Sec. 7; Sec. 8; Sec. 9
Jacob Anderson, CPG, MAusIMM Dahrouge Geological Consulting USA LTD. Sec. 11; Sec. 12

Note: QP = Qualified Person, Sec. = Section

 

29
 

 

2.4Work Program – Initial Assessment

 

The IA described in this technical report included evaluating the potential technical and economic merit of the CuMo project as an open-pit mining operation.

 

The IA described herein is preliminary in nature and relies in part on Inferred Mineral Resources, which are too geologically speculative to support the application of modifying factors necessary for classification as Mineral Reserves. Accordingly, there can be no assurance that the preliminary assessment based on these resources will be realized.

 

Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

 

2.5Basis of Technical Report

 

This report is based on information collected by the authors during site visits performed as set out in Section 2.6 and on additional information provided by Idaho Copper throughout the course of the IA study, and recently reported in the 2026 PEA (Barr, 2026).

 

Idaho Copper provided technical data and supporting information to Barr for evaluation and integration into the study. The datasets included electronic topography and aerial imagery covering the CuMo project area, as well as a geology and resource block model originally developed for the 2015 PEA (Giroux et al., 2015) and subsequently incorporated into the 2020 PEA (SRK, 2020). Dahrouge reviewed the outputs and interpretations from these previous studies and assessed their suitability for inclusion in the current IA.

 

Additional information supplied by Idaho Copper included metallurgical test work and associated results reported by SGS North America, Inc., ore sorting and binning classifications developed by Lycopodium Minerals Canada Ltd. (Americas), and strategic mine planning alternatives with optimized ore sorting and binning scenarios prepared by Whittle Consulting Pty Ltd. (Whittle). These datasets were provided in electronic format and served as key inputs for resource evaluation, processing strategy development, and mine planning analyses completed as part of the 2026 IA.

 

Idaho Copper retained Lycopodium to assist with the ore-sorting and recovery methodology based on the source geology model. The evaluation developed a sorting selection based on the material type plus the recovered value, with the outputs consisting of a primary feed, middlings, and reject material. Barr’s process QP reviewed the information and methodology provided by Lycopodium for the development of the ore-sorting response and inclusion in the crusher circuit and process plant concept for the current IA.

 

30
 

 

Idaho Copper retained Whittle to conduct a quantitative analysis of the provided information and develop mining schedules associated with different economic calculations for Idaho Copper’s option evaluation. Whittle’s approach modified the ore-sorting methodology using the same source geology model and data. The sorting selection is based on the material type plus CuMo grade, with the output being a stream of three materials: PMF (high-grade), MID (intermediate grade), and REJ (low or no-grade). This model was further analyzed using Whittle’s PROBER-E software, which adjusts timing and routing or classification of material types due to schedule optimization. These bin modifications are case specific based on applied conditions or factors.

 

The authors have no reason to doubt the reliability of the information provided by Idaho Copper or their project partners. The authors have not performed verification studies with respect to such information, other than as described explicitly in this report as required to confirm that the authors could produce the same output results when analyzing model inputs identical to those used by Lycopodium and Whittle.

 

Throughout this report, all currency is expressed in 2026 US dollars, non-escalated, unless otherwise noted.

 

2.6Site Visit

 

The following QPs have visited the CuMo project site.

 

●Gareth Flitton, from Dahrouge Geological Consulting USA LTD. (Dahrouge), visited the site on September 1, 2025. The purpose of the site visit was to view the temporary core storage facility and the previous drill sites for the project.

 

●Russell J. Sheets, from Barr Engineering Co., and Justin L. Smith, from Northern Lights Mining, LLC (NLM), visited the site on June 26, 2026. The purpose of the site visit was to view the following:

 

○Present site accessibility, including paved and unpaved roads and nearby rail lines

 

○The site location, including proposed open-pit, process plant, waste rock storage, and tailings storage facility locations

 

○Previous exploration dill sites

 

○General terrain and topography informing logistics for site development

 

○Potential utility connection points

 

○General local area and community

 

The following project team member also visited the CuMo project site.

 

●Preetham Nayak, from Lycopodium, visited the site on July 17, 2024. The purpose of the site visit was to view the project site and previous drill sites for the project.

  

31
 

 

3 Property Description

 

3.1General

 

The CuMo property is located approximately 37 air miles northeast of Boise, Idaho, USA (Figure 3-1). It is situated in the northern portion of the Grimes Pass area on the United States Geological Survey (USGS) 1:62,500 Placerville Quadrangle (15’ Series) within T7N and T8N, R5E and R6E, in Boise County, Idaho (Figure 3-2). The latitude at the approximate center of CuMo property is 44 degrees, 2’N, and the longitude is 115 degrees 47’ 30” W or Universal Transverse Mercator (UTM) coordinates of 597,500E, 4,876,000N (NAD 27 CONUS).

 

3.2Mineral Tenure

 

The property consists of 126 unpatented and un-surveyed contiguous mining lode claims covering an area of approximately 2,500 acres, as well as six fully patented claims covering an area of approximately 100 acres. Most of the claims consist of full-sized, 600-foot (ft) by 1,500 ft claims (20.66 acres each). However, the total includes 10 fractional claims where new claims were staked over existing claims. The claims are shown in Figure 3-2. The details for the active, unpatented claims are provided in Table 3-1, while the details for active patented claims are provided in Table 3-2. Unpatented claims have the mineral rights while the surface is owned by the federal government. Patented claims are private property and cover both surface and mineral rights.

 

In Idaho, staked claims expire annually on 1 September. An initial fee of $274 per claim is required, and an annual fee of $200 per claim must be paid to the Bureau of Land Management (BLM) prior to 31 August of each year, or all claims will expire on 1 September. The Company remitted this annual fee for the claims prior to 31 August, 2026. At $200 per claim, Idaho Copper must make annual payments of $25,200 to the BLM to keep all claims in good standing.

 

Since patented claims are owned outright, taxes are assessed by the county on a yearly basis. This varies, as it depends on assessed value and the county tax rate, which changes from year to year.

 

3.3Ownership Agreements

 

On October 13, 2004, CuMoCo (former parent company of ICMC) completed an “Option to Purchase Agreement” with CuMo Molybdenum Mining Inc. to purchase eight unpatented mineral claims located in Boise County, Idaho, USA, collectively known as “CuMo Molybdenum Property.” As part of the original CuMo and CuMoCo agreement, all claims acquired within 5 miles of the eight CuMo claims became part of the option deal. Therefore, all new claims referred to in this report as part of the CuMo Molybdenum Property are automatically subject to the terms outlined in that agreement. Terms of the agreement are:

 

1)Advance royalty payments:

 

a)$10,000 upon signing (completed)

 

b)$10,000 after 60 days (completed)

 

c)$5,000 after 6 months (completed)

 

d)$20,000 at 1-year anniversary (completed)

 

e)$20,000 at 2-year anniversary (completed)

 

f)$15,000 at 3-year anniversary (completed)

 

g)$15,000 every 6 months thereafter (up to date)

 

32
 

 

These payments are to be credited against a 1.5% net smelter return (NSR), which reduces to a 0.5% NSR after cumulative payments reach $3,000,000.

 

2)Work requirements:

 

a)$25,000 during the first year (completed)

 

b)At least $50,000 each year thereafter (up to date)

 

c)On January 21, 2005, CuMoCo entered into an option agreement with Kobex Resources Ltd. (Kobex), whereby Kobex could acquire a 100% interest in the CuMo Molybdenum Property and another property in Australia. Under the terms of the agreement, Kobex would earn a 100% undivided interest in these properties in consideration of cash payment of $5,000,000, 12,500,000 treasury shares, and $10,000,000 of work expenditure commitment.

 

On October 6, 2006, Kobex surrendered all rights and interests in the CuMo property to CuMoCo.

 

CuMoCo completed all required payments and work requirements under the 2004 Option to Purchase Agreement. The claims subject to this Option were included in the Mining Claims Agreement described below.

 

On February 14, 2017, CuMoCo announced it had purchased 20 claims in the area around the CuMo project from a group of local prospectors. The 20 unpatented mining claims cover an area of approximately 400 acres. The purchase price for 100% ownership of the claims was one $250,000 silver unit1 plus one million shares of CuMoCo.

 

On April 25, 2017, CuMoCo announced that its wholly owned subsidiary, ICMC, had completed an Option Agreement to purchase 36 patented mining claims covering an area of approximately 640 acres adjacent to the CuMo project. Patented claims include surface rights as well as mineral rights. However, it is understood that subsequently, ICMC determined to not execute and complete the Option Agreement through the stipulated payments, and said Option has expired.

 

On July 17, 2017, CuMoCo announced that it had signed a mining claims purchase agreement effective as of July 6, 2017 (the “Mining Claims Agreement” or “MCA”), with its wholly owned subsidiary, ICMC, and CuMo Molybdenum Mining Inc., Western Geoscience Inc., and Thomas Evans (collectively, the “Parties”). CuMoCo is to acquire from the Parties a 100% interest, including any NSR owned by the Parties, in the CuMo project, which is currently under option, pursuant to an option agreement between CuMoCo and CuMo Molybdenum Mining Inc. dated October 13, 2004, and amended on January 14, 2005 (the “Option Agreement”).

 

 

1 A silver unit is a seven-year exchange-approved debenture that can be converted to the right to buy silver for $5 per ounce from any future production at CuMo. The debenture pays 8.75% interest per annum.

 

On August 19, 2025, the Seller, and CuMoCo and ICMC (collectively, “Buyer”) entered into the First Amendment to the MCA. Pursuant to the Amendment the Seller agreed to transfer as part of the Property (as defined in the MCA) to be conveyed, the NSR and the claims subject to the Option Agreement. CuMoCo also agreed to assign and transfer all of its rights and obligations under the MCA to the Company.

 

The First Amendment to the MCA provided that Buyer shall have the right, but not the obligation, to purchase the Property. Upon purchase of the Property, the Buyer shall deliver Seller, $500,000 and $1,500,000 worth of shares of Common Stock of the Company, which number of shares shall be calculated by dividing $1,500,000 by the market closing price of the Company’s common stock on the closing date. Upon consummation of the purchase of the Property, the Seller will renounce any other claims or rights granted to it under the Option Agreement and the Option Agreement will be deemed terminated.

 

In July 2026, the Company completed the purchase of the Property under the MCA by delivering to the Seller the required consideration in cash and shares. The final executed title transfers are underway and will be recorded when received by Idaho Copper. All of the consideration (cash and shares) for the purchases of the claims was paid in July to the claim owners. These contracts when completed retired the royalty and transferred the claims to Idaho Copper.

 

33
 

 

 

 

Figure 3-1 CuMo Property Location Map

 

34
 

 

 

Figure 3-2 Claim Location Map for the CuMo Property

 

35
 

 

Table 3-1 Active Unpatented CuMo Project Claim List – June 2026

 

Item Claim Name & Number BLM Serial No. Idaho Serial No. Boise County Instrument No.
1 CUMO #1 188031 201255 ID101310593
2 CUMO #2 188032 201256 ID101310594
3 CUMO #3 188033 21257 ID101310595
4 CUMO #4 188034 201258 ID101310596
5 CUMO #5 188035 201259 ID101310597
6 CUMO #6 188036 201260 ID101310598
7 CUMO #7 188037 201261 ID101310599
8 CUMO #8 188038 201262 ID101311766
9 CUMO #62 188205 202147 ID101370505
10 CUMO #63 188206 202148 ID101370506
11 CUMO #65 FRACT. 188208 202150 ID101370508
12 CUMO #68 FRACT. 188211 202153 ID101370511
13 CUMO #70 FRACT. 188213 202155 ID101370513
14 CUMO #85 188228 202271 ID101371124
15 CUMO #87 188230 202273 ID101371125
16 CUMO #89 188232 202275 ID101371126
17 CUMO #91 188234 202277 ID101371127
18 CUMO #93 188236 202279 ID101371128
19 CUMO #94 188237 202281 ID101371129
20 CUMO #95 188238 202282 ID101371130
21 CUMO #99 188240 202367 ID101371132
22 CUMO #101 188242 202369 ID101371134
23 CUMO #121 188258 202283 ID101371136
24 CUMO #122 188259 202284 ID101371137
25 CUMO #123 188260 202285 ID101371138
26 CUMO #124 188283 202286 ID101371796
27 CUMO #125 188261 202287 ID101371139
28 CUMO #132 188268 202294 ID101371140
29 CUMO #133 188269 202295 ID101371141
30 CUMO #134 188270 202296 ID101371142
31 CUMO #135 188271 202297 ID101371143
32 CUMO #136 188272 202298 ID101371144
33 CUMO #137 188273 202299 ID101371794
34 CUMO #138 188274 202300 ID101371795
35 CUMO #148 188285 202310 ID101371797
36 CUMO #149 FRACT. 188286 202311 ID101371798

 

36
 

 

Item Claim Name & Number BLM Serial No. Idaho Serial No. Boise County Instrument No.
37 CUMO #150 188257 202312 ID101371135
38 CUMO #151 FRACT. 188287 202313 ID101371799
39 CUMO #152 188288 202314 ID101371864
40 CUMO #153 188289 202315 ID101371865
41 CUMO #154 188290 202316 ID101371866
42 CUMO #176 FRACT. 188306 202324 ID101371867
43 CUMO #177 FRACT. 188307 202325 ID101371868
44 CUMO #178 188308 202326 ID101371869
45 CUMO #179 188309 202327 ID101371870
46 CUMO #180 188310 202328 ID101371871
47 CUMO #181 188311 202329 ID101371872
48 CUMO #182 FRACT. 188312 202330 ID101371873
49 CUMO #183 FRACT. 188313 202331 ID101371874
50 CUMO #184 188314 202332 ID101371875
51 CUMO #185 188315 202333 ID101372523
52 CUMO #186 188316 202334 ID101372524
53 CUMO #187 188317 202335 ID101372525
54 CUMO #188 FRACT. 188318 202336 ID101372526
55 NEW CUMO #9 187938 199561 ID101312650
56 NEW CUMO #10 187939 199562 ID101312651
57 NEW CUMO #11 187940 199563 ID101312652
58 NEW CUMO #12 187941 199564 ID101312653
59 NEW CUMO #13 187942 199565 ID101313843
60 NEW CUMO #14 187943 199566 ID101313844
61 NEW CUMO #15 187944 199567 ID101314001
62 NEW CUMO #16 187945 199568 ID101314002
63 NEW CUMO #17 187946 199569 ID101314003
64 NEW CUMO #18 187947 199570 ID101314004
65 NEW CUMO #19 187948 199571 ID101314005
66 NEW CUMO #20 187949 199572 ID101314006
67 NEW CUMO #21 187950 199573 ID101314007
68 NEW CUMO #22 187951 199574 ID101314008
69 NEW CUMO #23 187952 199774 ID101314009
70 NEW CUMO #24 187953 199775 ID101314010
71 NEW CUMO #25 187954 199575 ID101314011
72 NEW CUMO #26 187955 199576 ID101314012

 

37
 

 

Item Claim Name & Number BLM Serial No. Idaho Serial No. Boise County Instrument No.
73 NEW CUMO #27 187956 19577 ID101314013
74 NEW CUMO #28 187957 199578 ID101314014
75 NEW CUMO #29 187958 199579 ID101314015
76 NEW CUMO #30 187959 199580 ID101314016
77 NEW CUMO #31 187960 199581 ID101314017
78 NEW CUMO #32 187961 199582 ID101314018
79 NEW CUMO #33 187962 199583 ID101314019
80 NEW CUMO #34 187963 199584 ID101315233
81 NEW CUMO #35 187964 199585 ID101315234
82 NEW CUMO #36 187965 199586 ID101315235
83 NEW CUMO #37 187966 199587 ID101315236
84 NEW CUMO #38 187967 199588 ID101315237
85 NEW CUMO #39 187968 199589 ID101315238
86 NEW CUMO #40 187969 199590 ID101315239
87 NEW CUMO #41 187970 199591 ID101315240
88 NEW CUMO #42 187971 199592 ID101315241
89 NEW CUMO #43 187972 199593 ID101315242
90 NEW CUMO #44 187973 199594 ID101315243
91 NEW CUMO #45 187974 199595 ID101315244
92 NEW CUMO #46 187975 199596 ID101315245
93 NEW CUMO #47 187976 199597 ID101315246
94 NEW CUMO #48 187977 199598 ID101315247
95 NEW CUMO #49 187978 199599 ID101315248
96 NEW CUMO #50 187979 199600 ID101315249
97 NEW CUMO #51 187980 199601 ID101315250
98 NEW CUMO #52 187981 199602 ID101315251
99 NEW CUMO #53 187982 199603 ID101315252
100 NEW CUMO #54 187983 199604 ID101315253
101 NEW CUMO #55 187984 199605 ID101316402
102 NEW CUMO #56 187985 199606 ID101316403
103 NEW CUMO #57 187986 199607 ID101316404
104 NEW CUMO #58 187987 199608 ID101316405
105 NEW CUMO #59 187988 199609 ID101316406
106 NEW CUMO #60 187989 199776 ID101316407
107 Sharon #1 177221 159054 ID101432157
108 Sharon #2 177222 159055 ID101432074
109 Sharon #3 177223 159056 ID101434598

 

38
 

 

Item Claim Name & Number BLM Serial No. Idaho Serial No. Boise County Instrument No.
110 Sharon #4 177224 159057 ID101482928
111 Sharon #5 177225 159058 ID101377222
112 Sharon #6 177226 159059 ID101433528
113 Sharon #7 177227 159060 ID101480529
114 Sharon #8 177228 159061 ID101300281
115 Sharon #9 177229 159062 ID101304180
116 Sharon #10 177230 159063 ID101497643
117 BlackJack #1 177236 159064 ID101433488
118 BlackJack #2 177237 159065 ID101483278
119 JRA No. 16 76851 106515 ID101481437
120 JRA No. 18 76853 106517 ID101433401
121 JRA No. 20 76855 106519 ID101431348
122 JRA No. 21 76856 106520 ID101483535
123 JRA No. 29 76864 16528 ID101434320
124 JRA No. 30 76865 106529 ID101433736
125 JRA No. 31 76866 106530 ID101430504
126 JRA No. 45 76880 106544 ID101484801

 

Note: BLM – Bureau of Land Management

 

Table 3-2 Active Patented CuMo Project Claim List – June 2026

 

Item Claim Name Patent Number Survey Number Year Granted
1 Blackbird 11830026 3636 1902 + 1983
2 Red Flag 11830026 3636 1902 + 1983
3 Enterprise 39183 1706 1902
4 Enterprise Fraction 39183 1706 1902
5 Commonwealth 39183 1706 1902
6 Baby Mine 38183 1706 1902

 

3.4Environmental

 

3.4.1Environmental Liabilities

 

There are currently no known environmental liabilities on the property. The company has a $300,000 reclamation bond on deposit for use once the permits are re-issued.

 

It is possible that with the development of a detailed mining PoO and the more detailed investigation of aspects of the property associated with that PoO, as-yet unknown environmental liabilities and/or issues may be identified.

 

39
 

 

3.4.2Other Significant Factors and Risks

 

At the time of this report, no specific issues have been identified that would materially impact the ability to eventually extract Mineral Resources at the project site. That is, any other significant factors and risks that may affect access, title, or the right or ability to perform work on the property are not known at present.

 

However, Idaho Copper should be prepared to address potential issues associated with, but not limited to, the following aspects:

 

●Water, including supply, water rights, and delivery system, and potential impacts

 

●Water management (stormwater, contact/non-contact water, water quality)

 

●Geochemistry of ore, waste rock, tailings solids and solution, and post-mining pit lake

 

●Threatened, endangered, and special-status plant and animal species

 

●Jurisdictional waters

 

●Transportation and access

 

●Reclamation and closure

 

3.5Permits

 

Exploration on federal lands requires authorization, except for the sampling of rocks and soils by hand and other activities that create no land disturbance.

 

Approval for a diamond-drilling program has been obtained from the USFS, to be carried out using the existing network of drill access roads; this program has been permitted under a Categorical Exclusion issued in 2008. An application for a Water Use Permit for diamond-drilling purposes was originally filed with the Idaho Department of Water Resources in 2008; that permit is renewed annually.

 

Idaho Copper was granted the approval of their yearly PoO for exploration activities, including drilling, on September 9, 2026. Exploration drilling activities commenced on October 4, 2026.

 

A more detailed discussion of the permitting history is included in Section 17.

 

40
 

 

4 Accessibility, Climate, Local Resources, Infrastructure, and Physiography

 

The property can be accessed by road from Boise, Idaho by taking State Highway 55 north for approximately 40 miles (65 kilometers [km]) to the town of Banks, Idaho, and then traveling east on the Banks Lowman Road for approximately 10 miles (16 km) toward the town of Garden Valley. A secondary road heading south across the Payette River exists 1 mile east of Garden Valley. Following this secondary road, the westernmost edge of the CuMo claim block is approximately 10 miles (16 km) from Garden Valley. Alternatively, access can be gained by 1) traveling northeast from Boise along Highway 21 past the towns of Idaho City and Centerville, along Grimes Creek, and then over the Grimes Creek Pass road to USFS roads, or 2) taking State Highway 55 north to Horseshoe Bend, and then traveling east on Harris Creek Road past New Centerville, Centerville, and Pioneerville to the Grimes Creek Pass road. From there, the USFS roads give access to the western portion of the claim block. The site location is shown on Figure 4-1.

 

International air travel is available through Boise, Idaho.

 

The project is situated in the southern part of the Salmon River Mountains, immediately west of the Rocky Mountains. The area is characterized by north-northwest-trending mountain ranges separated by alluvium-filled valleys. Existing ground elevations within the mapped project area range from approximately 4,200 to 7,350 ft (1,280 to 2,240 m) above mean sea level.

 

The climate at the project site is characterized by summer temperatures that can reach 100 °F (38 °C) and cold, windy winters with lows near -10 °F (-23 °C). Precipitation is moderately light, with an average annual rainfall of approximately 30 inches (in.) (less than 1 m) and an average annual snowfall of approximately 140 in. (3.6 m). Vegetation in the project area primarily consists of cedar, lodgepole pine, mountain mahogany, and juniper. Idaho Power Company supplies electricity to the residents of Garden Valley, Lowman, and Pioneerville. The nearest rail line is the Idaho Northern & Pacific line, formerly operated by Union Pacific, which passes through Banks approximately 20 road miles (32 km) west of the property.

 

Equipment, supplies, and services for exploration and mining development projects are available in Boise, which also has a trained mining-industrial workforce.

 

Exploration and mining at the property can be conducted year-round, due to the established road system and its proximity to other infrastructure. However, exploration activities are currently limited by Forest Service permits from April 15 to December 15 each calendar year. Boise County maintains the primary county road system, while the USFS maintains roads within Boise National Forest. However, Idaho Copper conducts limited road maintenance as permits allow for exploration activities. The property is large enough to accommodate the current CuMo deposit exploration and mining operations, including facilities. Potential waste rock storage and tailings storage areas will require permits from federal and state agencies, as discussed in Chapter 20 of this report (Environmental Studies, Permitting, and Social or Community Impact).

 

The project area comprises patented mining claims owned or optioned by Idaho Copper and public lands administered by the USFS. The extent of public land required for mining-related activities has not yet been finalized and would be defined in the mining PoO. Except for patented claims owned or optioned by Idaho Copper, surface rights within the current design area are administered by the USFS. These surface rights are not available for purchase and would require lease, authorization, or other approved acquisition and use under applicable federal requirements.

 

The NEPA process will disclose the potential environmental effects associated with construction, mining, closure, and reclamation activities and identify mitigation measures intended to avoid, minimize, or reduce such effects prior to authorization of the mining PoO. Surface-use authorization for commercial mine production will be granted, if approved, through the permitting process following issuance of a record of decision (ROD).

 

41
 

 

 

Figure 4-1 CuMo Project, Boise County, Location Map

 

42
 

 

5 History

 

5.1Exploration

 

The Boise Basin was first explored following the discovery of placer gold deposits in 1862. Several lode gold deposits were discovered and developed immediately following the initial alluvial gold rush, with significant production occurring in the late 1800s and early 1900s. There are several lode prospects within approximately 2 miles of the CuMo property, some of which have recorded minor past production of base and precious metals. These locations are discussed and shown in Chapter 20 (Adjacent Properties). No production has occurred on the CuMo property.

 

The first interest in the CuMo property was shown during aerial reconnaissance by Amax Exploration, Inc. (Amax) in 1963. Follow-up geochemical rock and soil sampling indicated anomalous molybdenum and copper values. Forty claims were then staked, and three previously existing claims were optioned. A 2.5-mile (4 km) rough access road was constructed in 1964 to facilitate collection of rock samples and geological mapping. The property was subsequently relinquished due to the combination of contemporary economic conditions and initial sample grades.

 

In 1968, Curwood Mining Company staked 12 claims and undertook detailed mapping and geochemical rock sampling. This work indicated roughly coincident anomalies in copper, molybdenum, and silver. Several trenches were excavated, and one line of dipole-dipole array induced polarization (IP) geophysical survey was conducted.

 

In 1969, Midwest Oil Corp. optioned the property and conducted exploration drilling through 1972 (four short rotary holes [less than 100 ft] initially, which were later deepened using diamond drilling, followed by six cored holes). Midwest also performed an IP survey in 1971 and an airborne magnetic survey in 1973. The IP survey indicated a pyrite halo on the north side of the deposit, although an alternative interpretation concluded “the combined IP data may indicate a halo effect but more probably shows an east-west trend to the rock types and mineralization” (Baker, 1983). The CuMo deposit did not have a strong magnetic signature, being something of a plateau with surrounding highs.

 

In 1973, Midwest formed a joint venture (JV) with Amax and subsequently merged with AMOCO, resulting in an Amax-AMOCO JV with AMOCO as operator. During the period of 1973 to 1981, the Amax-AMOCO JV completed 30,822 ft of drilling (summarized in Table 5-1), surface geological mapping, re-logging of the core, road construction, an aerial topographic survey, and age dating. In 1980, Amax Exploration Inc. transferred its interest to Climax Molybdenum Company (Climax), also a subsidiary of Amax Inc. In 1982, Climax collected more than 300 soil geochemical samples from three different grids.

 

43
 

 

Table 5-1 Summary of Historical Drilling Completed through 1981

 

Year Company Holes Footage Meters Comments
1969 Midwest 4 378 115 Rotary holes shallow due to water included in core
1970 Midwest 0 653 199 2 rotary holes deepened with core to 400-ft depth
1971 Midwest 1 2,251 686 1 core hole deepened further to 1,884 ft
1972 Midwest 3 1,892 577 1 core hole deepened from 810 to 1,416 ft
1974 Amax 1 805 245 Hole 9-9A
1975 Amax 1 2,382 726 Hole 10
1976 Amax 2 4,343 1,324 1 vertical, other 1,340 ft at -45
1977 Amax 3 5,861 1,786 3 vertical DDH 1,804–2,124 ft deep
1978 Amax 3 6,774 2,065 3 vertical DDH 2,132–2,361 ft deep
1979 Amax 2 4,823 1,470 Vertical DDH to 2,543-ft depth
1980 Amax 3 2,630 802 RC holes
1981 Amax 3 3,204 977 Vertical DDH 1,000- to 1,193-ft depths
Total   26 35,996 10,972  

 

Note: DDH = diamond drill hole; ft = feet; RC = reverse circulation

 

A total of 23 diamond holes and three RC holes were drilled on the property (Table 5-2). Most RC holes were pre-collars to diamond drill holes (DDHs), with only the diamond drill component of the holes being used for resource modeling and sampling. The historical holes were sampled mostly at a 20-ft sample interval. A map of all completed DDHs and proposed DDHs is shown in Figure 5-1.

 

A Skelton core representation of the historical drill holes (one 4-in. piece of core for each 10-ft interval) and all sample rejects were delivered directly from Climax’s secure facility in Colorado and are stored in the secure project warehouse facility for use by the project.

 

Table 5-2 List of Historic Drill Holes Completed through 1981

 

Hole Northing Easting Elevation Dip Azimuth Length (feet)
C71-01 120,990 219,904 6,026 -90 0 1,884 completed
C71-02 120,575 219,820 6,060 -70 0 405 completed
C71-03 120,250 219,905 6,165 -90 0 70 completed
C71-04 120,785 219,940 6,045 -90 0 113 completed
C72-05 120,525 220,570 6,202 -90 0 1,416 completed
C72-06 121,749 219,919 5,902 -90 0 663 completed
C72-07 121,491 219,823 5,962 -90 0 275 completed
C72-08 118,890 220,025 6,467 -90 0 379 completed
C74-09 121,438 220,687 5,890 -60 168 804.6 completed
C75-10 119,756 221,220 6,341 -90 0 2,381 completed
C76-11 120,456 221,250 5,996 -90 0 3,003 completed
C76-12 120,955 221,432 5,742 -43 190 1,340 completed

 

44
 

 

Hole Northing Easting Elevation Dip Azimuth Length (feet)
C77-13 119,472 219,903 6,426 -90 0 1,804 completed
C77-14 119,085 221,271 6,613 -90 0 2,123.8 completed
C77-15 119,772 221,951 6,339 -90 0 1,933.2 completed
C78-16 119,210 219,148 6,248 -90 0 2,131.7 completed
C78-17 118,712 219,887 6,544 -90 0 2,281.5 completed
C78-18 119,823 222,649 6,168 -90 0 2,361 completed
C79-19 120,178 219,887 6,170 -90 0 2,280 completed
C79-20 120,878 220,787 6,105 -90 0 2,543 completed
RC80-21 120,511 220,541 6,202 -90 0 1,000 completed
RC80-22 119,913 220,412 6,239 -90 0 670 completed
RC80-23 120,695 219,420 5,827 -90 0 960 completed
C81-24 120,671 222,009 6,070 -90 0 1,000 completed
C81-25 119,890 219,290 6,019 -90 0 1,011 completed
C81-26 121,338 221,433 5,768 -90 0 1,193 completed

 

Note: C holes are diamond and RC are reverse circulation. Holes listed in this table represent individual holes that may have been drilled across more than one year, and does differ from Table 5-1 shows the reported annual footage drilled in each year according to the records.

 

45
 

 

 

Source: Giroux et al. (2015), modified 2019, reviewed 2026

 

Figure 5-1 Map Showing the Location of Completed and Proposed DDHs

 

46
 

 

5.2Historical Resource Estimate

 

The estimate summarized herein was undertaken by Climax prior to the inception of NI 43-101 reporting and does not follow the standard or adhere to the categories outlined in NI 43-101. The Amax Resource is considered an historical estimate, not a Resource in accordance with NI 43-101. A technical report on the property was never filed. No QP has done sufficient work to classify the historical estimate as a current mineral resource. Idaho Copper is not treating the historical estimate as current Mineral Resources. It is included herein for historical completeness only (Table 5-3).

 

The resource for the property is only as defined in Section 11 of this report. The effective date for this Mineral Resource Estimate discussed in Section 11 remains August 30, 2018.

 

Based on the 26 drill holes, a resource block model was constructed in 1983, extending between local grid coordinates 17,000 to 25,000 east and 16,000 to 23,000 north. The individual blocks were 100 ft in both the north-south and east-west directions and were 50 ft in height. Blocks were located from 7,000 ft down to 3,050 ft AMSL. Grades were estimated using 50-ft drill hole assay composites and mineralized zone boundaries. Kriging was performed within a 1,500-ft horizontal search limited to 300 ft vertically.

 

Table 5-3 Historical Resource Estimate

 

Cut-off Grade (MoS2%) Million Tons Average Grade (MoS2%)
0.02 2,100 0.072
0.03 1,900 0.078
0.04 1,600 0.084
0.05 1,500 0.092
0.06 1,100 0.097
0.08 730 0.116
0.10 470 0.131
0.12 280 0.145
0.14 140 0.170

 

Source: Baker (1983) Note: MoS2 – molybdenite

 

In 1983, Climax transferred its interest in the property to Amax Exploration Inc., and no further work appears to have been done on the property between that event and the drilling campaigns of Idaho Copper (and its predecessors) that commenced in 2006 and ran through 2012.

 

47
 

 

6 Geological Setting, Mineralization, and Deposit

 

6.1Regional Geology

 

The tectonic setting in the region of the project site consists of a basement of amalgamated Archean and Paleoproterozoic crystalline terrains that were joined during the Paleoproterozoic Trans-Montana orogeny. These terrains are overlain discontinuously by sedimentary rocks of the Mesoproterozoic, Neoproterozoic, and Paleozoic ages, as well as volcanic and sedimentary rocks of the Eocene and Miocene ages. Voluminous tonalite to granite bodies of the Idaho batholith and later granitic plutons of Eocene age intrude into the older rocks. Major deformational episodes superimposed on the Precambrian basement, include:

 

●The Cretaceous Sevier orogeny, which mainly involved east-verging “thin-skinned” thrusting

 

●The Eocene extensional deformation, which resulted in development of metamorphic core complexes

 

●Basin and range-type faulting (Sims et al., 2005), as opposed to the Laramide orogeny’s “basement cored” uplifts, which partially overlapped the Sevier orogeny in time and space

 

Regional geology has been compiled at a scale of 1:1,000,000 to form the digital map of Idaho (Johnson and Raines, 1996). The CuMo deposit is situated within the Idaho batholith and is part of a regional-scale belt of porphyry and related deposits identified as the Idaho-Montana Porphyry Belt (Rostad, 1978). This belt is part of a magmatic arc that formed on the northeast margin of the North American Craton (Figure 6-1) during Laramide time (Late Cretaceous-Early Tertiary). The Idaho-Montana Porphyry Belt lies within the much longer (932-mile [1,500 km]) Great Falls tectonic zone (Figure 6-2), which can be distinguished by brittle structures and intrusions of Phanerozoic age that are interpreted to have been controlled by the reactivation of basement structures. (O’Neill and Lopez, 1985). Two sets of basement structures provided zones of weakness that were repeatedly rejuvenated (Sims et al., 2005):

 

1.Northeast-trending ductile shear zones developed on the northwest margin of the Archean Wyoming province during the Paleoproterozoic Trans-Montana orogeny

 

2.Northwest-trending, intra-continental faults of the Mesoproterozoic Trans-Rocky Mountain strike slip fault system.

 

The Trans-Montana orogeny comprises a deformed, north-facing, passive continental margin and subsequent fore-deep assemblages overlying an Archean basement that is juxtaposed with accreted conjoined terrains. The juncture is the linear deformed belt between the Great Falls and Dillon shear zones. The fold-and-thrust belt of the Trans-Montana orogeny coincides in part with the Great Falls tectonic zone.

 

The Trans-Rocky Mountain fault system is a major, deep-seated, northwest-trending, intracontinental strike-slip fault system of Mesoproterozoic age. It consists principally of west-northwest-striking strike-slip faults (principal displacement zones), branching and echelon northwest-trending faults, and widely spaced, more local north-trending faults.

 

48
 

 

 

 

Source: Hildenbrand et al. (2000)

 

Figure 6-1 Tectonic Map of the Western United States

 

49
 

 

 

 

Source: Lund et al. (2005)

 

Figure 6-2 Distribution of Idaho Montana Porphyry Deposits in Relation to the Great Falls Tectonic Zone

 

Mineral deposits in the Idaho-Montana Porphyry Belt (also called the Transverse Porphyry Belt of Idaho-Montana [Carten et al., 1993]) are related to Eocene granitic intrusions. The distribution of deposits along this belt from northeast to southwest reflects a progression from alkalic rocks (intra-arc rift-related), to mixed alkalic and calc-alkalic rocks, and finally calc-alkalic intrusive rocks. This pattern is similar to the distribution of igneous rocks from south to north along the proto-Rio Grande rift. The CuMo deposit is located at the southwestern end of this belt and is associated with a calc-alkalic monzogranite, reported as 45 to 52 Ma age2, that intrudes Cretaceous equigranular rocks of the Atlanta Lobe of the Idaho batholith.

 

The Idaho batholith is a composite mass of granitic plutons covering approximately 15,400 square miles. The northern part is called the Bitterroot lobe, and the southern part is the Atlanta lobe. Most of the southern lobe was emplaced 75 to 100 million years ago (Late Cretaceous), whereas the northern lobe was emplaced 70 to 80 million years ago. Older plutons of Jurassic age occur on the northwest side of the Bitterroot lobe, and many Eocene plutons have intruded into the eastern side of the Atlanta lobe. Although radiometric dates and field relationships restrict the Idaho Batholith to between 180 and 45 Ma age, the dominant interval of emplacement was early to Middle Cretaceous. There is a general west-to-east decrease in age among plutons of the batholith.

 

 

 2 “Ma age” denotes “million years of age.”

 

50
 

 

On the west side of the batholith the rocks are tonalites or quartz diorites, whereas on the east side they range from granodiorites to granites. The boundary between the two composition types also coincides with the 0.704 Sr 87/Sr 86 boundary and the boundary between the Mesozoic and Paleozoic eugeoclinal accreted rocks to the west with the continental Precambrian rocks to the east (Digital Atlas of Idaho, 2026).

 

The CuMo deposit is situated within the Atlanta Lobe of the Idaho batholith. The western margin of the Atlanta lobe is strongly folded and metamorphosed into gneissic rocks, which are well exposed near the town of McCall. The western side is composed of 95- to 85-million-year-old tonalite. The batholith core is biotite granodiorite, and the eastern side lobe is muscovite-biotite granite approximately 78 to 72 Ma age (Lewis et al., 1987).

 

6.2Local Geology

 

The geology of the area around the CuMo deposit was mapped and originally compiled at 1:24,000 scale by Anderson (1947). This mapping has been incorporated into the 1:100,000-scale Deadwood River 30 × 60 quadrangle map (Killsgaard et al., 2006) and adjoining Idaho City 30 x 60 quadrangle map (Killsgaard et al., 2001) as shown in Figure 6-3. It has also been compiled into the Boise County map of the digital Atlas of Idaho (Figure 6-4).

 

The CuMo area is underlain by biotite granodiorite, the most common rock type of the Atlanta lobe of the Idaho batholith (Unit Kgd) (Killsgaard et al., 1985). This unit was mapped by Anderson (1947) as quartz monzonite (Unit Kqm) that was in part porphyritic and included granodiorite. The rock is light grey, medium to coarse grained, and equigranular to porphyritic. Biotite averages about 5% and sericite alteration of feldspar is common. Killsgaard et al. (1985) reported his unit at 82 to 69 Ma age based on potassium-argon dating.

 

Tertiary plutonic rocks in the batholith in the vicinity of CuMo include Eocene diorite and hornblende-biotite granite, forming the Boise Basin and Long Gulch stocks and associated dikes (Unit Tgdd) (Killsgaard et al., 2005). Anderson (1947) identified these units as diorite and quartz monzonite porphyry, respectively. The Eocene granites are generally characterized by a pink color due to potassium feldspar as a major component; miarolitic cavities that may be lined with smoky quartz; high radioactivity relative to the Idaho batholith; perthitic feldspar; myrmekite; and a granophyric texture indicating high temperature crystallization complicated by quenching, and a high content of large cation elements including molybdenum, high-fluorine content, and high-iron biotite (Killsgaard et al., 1985).

 

51
 

 

 

 

Source: Killsgaard et al. (2001)

 

Figure 6-3 Geology of the Idaho City 30 × 60 Minute Quadrangle, Idaho

 

52
 

 

 

 

Source: This mapping has been incorporated into the 1:100,000-scale Deadwood River 30 × 60 quadrangle map (Killsgaard et al., 2006) and adjoining Idaho City 30 × 60 quadrangle map (Killsgaard et al., 2001).

 

Figure 6-4 Geology of Boise County, Idaho, Showing Geological Setting of CuMo Deposit

 

53
 

 

Hypabyssal equivalents of the granites include numerous rhyolite dikes concentrated along the trans-Challis fault system (Killsgaard et al., 1985). Rhyolite dikes are generally less than 25 ft thick and may exhibit flow banding, whereas rhyolite porphyry dikes can reach 200 ft in thickness and have prominent quartz phenocrysts (Anderson, 1947).

 

Extensive placer gold workings and lode deposits in the area are situated along the northeast-trending trans-Challis fault system (Killsgaard et al., 1989; Bennett, 1986). As shown in Figure 6-4, a north-trending basin and range fault, downthrown on the east, bounds the system of northeast-striking trans-Challis faults to the west of CuMo (Link, 2002).

 

6.3Property Geology

 

Amax completed detailed bedrock mapping on the CuMo property between 1964 and 1981. Earlier periods of mapping outlined five general rock types: quartz monzonite of the Idaho Batholith, rhyolite porphyry, lamprophyre, dacite, and diabase dykes. Subsequent mapping through 1982 resulted in subdivision of those 5 units into 17 (Table 6-1).

 

Baker (1983) noted that the “ranges of textures in the various dike types (TpA-TpF) overlap, but show a general trend from early, phenocryst-rich porphyries with large phenocrysts, to young, phenocryst-poor porphyries with small phenocrysts.”

 

Three main intrusive types—equigranular quartz monzonite, quartz monzonite porphyry, and intrusive breccia—were observed in the holes. Mafic dikes were also intersected. The equigranular quartz monzonite is considered to be the Idaho batholith (unit Kqm) and locally contains K-feldspar megacrysts. The intrusive breccia is composed of fragments of porphyry and equigranular quartz monzonite. All of the felsic intrusive phases have demonstrated molybdenite (MoS2) mineralization. Examples of the main rock types are shown in Figure 6-5. The quartz monzonite porphyry (unit Tbqmp) varies considerably in proportion and size of phenocrysts, with at least four varieties recognized (Figure 6-5). The first and possibly earliest phase (unit Tbqmp Type I) is dark to medium grey, with 10 to 15%, < 7 millimeters (mm) feldspar phenocrysts, 1 to 2% fine-grained biotite, and < 5% quartz set in a fine-grained groundmass. The second phase (unit Tbqmp Type II) is medium to light grey, with 30% feldspar phenocrysts and minor biotite set in a medium-grained groundmass. The third phase (Unit Tbqmp Type III) is similar to Type II but contains K-feldspar megacrysts. The fourth and possibly most recent phase is a crowded porphyry variant of Type III containing > 30% feldspar phenocrysts set in a medium-grained groundmass. Type I through IV phases may correlate with Amax units TpD, TpB, TpA and TpC, respectively, and appear to follow a general pattern of early, phenocryst-poor phases intruded by later, phenocryst-rich phases, which is opposite to the general progression observed by previous workers.

 

54
 

 

Table 6-1 Summary of Rock Units Present at the CuMo Property

 

Unit Age Rock Type Texture Grain Size
Tl Tertiary Lamprophyre Porphyritic Fine
Td Tertiary Diabase Massive, amygdaloidal Aphanitic
Tr Tertiary Rhyolite Massive to flow banded Aphanitic to fine
TpE Tertiary Biotite quartz monzonite porphyry Porphyritic Fine
Tbx Tertiary Intrusion to intrusive breccia Breccia Aphanitic to fine
Trp Tertiary Biotite quartz monzonite porphyry Porphyritic Aphanitic to fine
TpF Tertiary Biotite quartz latite to rhyolite porphyry Porphyritic Aphanitic
TpB Tertiary Biotite quartz latite to rhyolite porphyry Porphyritic Aphanitic
TpA Tertiary Biotite quartz latite to quartz monzonite porphyry Porphyritic Aphanitic to fine
TpD Tertiary Biotite quartz monzonite to quartz latite porphyry Porphyritic Aphanitic to fine
TpC Tertiary Biotite quartz latite to quartz monzonite porphyry Porphyritic Aphanitic to fine
Tbhqmp Tertiary Biotite hornblende quartz monzonite porphyry Porphyritic Fine
Tbdp Tertiary Biotite dacite porphyry Porphyritic Aphanitic
Tgd Tertiary Granodiorite Equigranular Fine-medium
Ta Tertiary Andesite Porphyritic Aphanitic
Kg Cretaceous Gabbro Equigranular – diabasic Fine
Kqm Cretaceous Biotite-quartz monzonite Equigranular to porphyritic Coarse-medium

 

Structure may be an important factor in the distribution of mineralization at the CuMo property. A strong northeast-to-east-northeast structural trend, characteristic of the trans-Challis fault system, is evident in the area of the property. The Tertiary dyke system trends in this same orientation, with steep to moderate dips to the south. Faults and mineralized structures identified to date dominantly trend to the northeast as well, including numerous small base and precious metal occurrences in the area and surrounding the CuMo deposit, with most of the major lodes striking east-northeast (N70E). Subordinate lodes are oriented in a northeasterly direction (N35E, N10-20E, and N30-60E). Several fault zones, marked by sections of broken core, were logged in the drilling and appear to offset the interpreted mineral zones. The full significance of these fault structures to the deposit geometry remains to be determined.

 

55
 

 

 

 

Note:All core pieces are 2.4 inches in width.Source: Giroux et al. (2015)

 

Figure 6-5 Core Photographs of Felsic Porphyry Types Recognized in Drill Core

 

6.4Mineralization

 

6.4.1Description of Mineralized Zones

 

The CuMo deposit is located in a historical gold mining camp. Gold was discovered in the Boise Basin in 1862, and lode mining began within a year. As of 1940, total gold production amounted to 2.8 million ounces, 74% of which was from placer operations (Anderson, 1947). More gold has been produced from the Boise Basin than from any other mining locality in Idaho (Killsgaard et al., 1989). Although these lodes are primarily gold deposits, considerable silver and minor copper, lead, and zinc have been produced as byproducts.

 

56
 

 

Anderson (1947) recognized two separate mineralizing events and termed them early Tertiary and early Miocene. The first event consists of gold-quartz veins containing minor sulfide minerals that occur within the Idaho batholith and are associated with weak wall rock alteration. Associated sulfide minerals include pyrite, arsenopyrite, sphalerite, tetrahedrite, chalcopyrite, galena, and stibnite. The second mineralizing event occurs within porphyry dikes and stocks as well as in the batholith, and it is characterized by relatively abundant sulfide mineralization, subordinate quartz, and widespread wall rock alteration. Base metal mineralization consists of pyrite, sphalerite, galena, tetrahedrite, chalcopyrite, minor quartz, and siderite, with local occurrences of pyrrhotite and enargite. The gold-quartz veins generally occur relatively distal to the CuMo deposit (within 4 to 6 miles [6 to 10 km]), whereas the base-metal-gold lodes occur in a belt that follows the “porphyry belt” from Quartzburg through Grimes Creek, proximal to and coincident with the CuMo deposit. This porphyry belt is what Idaho Copper refers to as the older copper-gold porphyry system, which is characterized by the chalcopyrite-silver-gold-bearing veins.

 

6.4.2Property Mineralization

 

Molybdenum mineralization was discovered at CuMo in 1963. The only other molybdenum showing in Boise County is the Little Falls molybdenum prospect, which is situated just to the northeast of CuMo.

 

Mineralization on the property occurs in veins and veinlets developed within various intrusive bodies. Molybdenite (MoS2) occurs within quartz veins, veinlets, and vein stockworks. Individual veinlets vary in size from tiny fractures to 5 cm in width, with an overall thickness averaging between 0.3 and 0.4 cm. Pyrite and/or chalcopyrite are commonly associated with molybdenite, although molybdenite can occur alone without other metallic mineralization.

 

Chalcopyrite occurs in quartz-pyrite + molybdenite veinlets, in magnetite + pyrite, and in pyrite-biotite + quartz + magnetite veins with secondary biotite halos. Scheelite is reportedly common on the property and closely parallels the distribution of molybdenite (Baker, 1983).

 

57
 

 

Figure 6-6 and Figure 6-7 show examples of mineralization at CuMo from the previous drill holes.

 

 

 

Note:In this older figure, “molybdenum” refers to molybdenite mineralization. Source: Giroux et al. (2015)

 

Figure 6-6 Photographs of Mineralized Core from the CuMo 2006 Program, Hole C06-28

 

58
 

 

 

 

Note:All core pieces are 2.4 inches in width.Source: Giroux et al. (2015)

 

Figure 6-7 Photographs of Molybdenite Mineralization in 2008 Drill Core

 

A compilation of Amax data on the frequency of veins mapped on the surface, as well as their mineral constituents, was presented by Giroux et al. (2005) and is shown graphically in Figure 6-8. A concentric pattern is clearly evident, which is also shown by the distribution of anomalous molybdenum and copper rock geochemical results (Figure 6-9 and Figure 6-10). The area drilled to date occupies only a portion of the central area; Amax had identified prospective target areas to the southeast and east of the area drilled.

 

59
 

 

 

 

Source: Giroux et al. (2015), modified 2019, reviewed 2026

 

Note: The “Amax Resource” indicated on the figure is considered an historical estimate, not a “Resource” in accordance with CIM Definition Standards or NI 43-101. A technical report on the property was never filed. No QP has done sufficient work to classify the historical estimate as a current mineral resource. Idaho Copper does not consider the Amax resource current.

 

Figure 6-8 Surface Distribution of Quartz and Epidote Veinlets and Metal Zonation

 

60
 

 

 

 

Source: Giroux et al. (2015), modified 2019, reviewed 2026

 

Figure 6-9 Geochemical Distribution of Molybdenum in Surface Rock Chip Samples

 

61
 

 

 

 

Source Giroux et al. (2015), modified 2019, reviewed 2026

 

Figure 6-10 Geochemical Distribution of Copper in Surface Rock Chip Samples

 

Amax interpreted two shells of molybdenite mineralization, with the upper shell being richer in copper and silver but of lower molybdenite grade, and the lower shell being molybdenite-rich but depleted in copper and silver (Baker, 1983). Amax interpreted this pattern of metal zoning to have formed above and peripheral to two or more source intrusions (only one of which was recognized physically).

 

No current Mineral Resources or Mineral Reserves are being reported based on this historical estimate.

 

62
 

 

6.5Deposit Types

 

The CuMo deposit is a porphyry-type deposit and has been classified as a porphyry copper-molybdenum deposit (Klein, 2004; Spanski, 2004) or a porphyry molybdenum-copper (low-fluorine-type) deposit (Mutschler et al., 2000).

 

Typical porphyry molybdenum-copper deposits are cylindrical, stock-like composite bodies with elongated outcrops with surface expressions on the order of 1.5 × 2 km, containing an outer shell of medium- to coarse-grained equigranular rock with a porphyritic core of similar composition. The most common hosts are quartz monzonite to granodiorite felsic plutonic rocks. In addition, a second population of deposits occurs in more mafic intrusive rocks of syenitic to dioritic composition.

 

The CuMo deposit is primarily of economic interest for its molybdenum content but contains significant values of copper and silver. Low-grade zones of copper enrichment typically form above and partially overlap with molybdenum shells in porphyry molybdenum deposits (Carten et al., 1993). The CuMo deposit is classified as a porphyry molybdenum-copper deposit (% molybdenum being > 0.04% and copper being potentially economically significant). The cutoff cited reflects the deposit-type literature and is not a statement of economic cutoff grade for the project.

 

The CuMo deposit is interpreted to be representative of large-tonnage, low-grade molybdenum and copper porphyry-style systems. Deposits of this class are typically associated with fluorine-poor, differentiated-monzogranite intrusive complexes formed in continental arc settings In some documented examples, their greater tonnage has been reported to offset lesser average grades relative to high-grade, Climax-type molybdenum deposits (Carten et al., 1993). This classification is provided for geological context only.

 

63
 

 

7 Exploration

 

7.1Historical Work

 

The information contained within this chapter is a review and reiteration of previous work completed by others. The assessment is warranted for due diligence and verification of past geology studies for application to this IA.

 

Since acquiring the property in 2005, Idaho Copper and its predecessors have focused its exploration work almost entirely on drilling at the CuMo project. Non-drilling exploration completed by Idaho Copper has been limited and has consisted primarily of reconnaissance-level field observations.

 

The only reportable non-drilling exploration activity completed by Idaho Copper was a dump sample collected during reconnaissance work undertaken by project geologists in 2017. The sample was collected from the Coon Dog dump (Figure 5-1).

 

The sample was collected by taking approximately 22 lb (10 kilograms [kg]) of randomly selected rock fragments from the dump area. Although the sample was intended to characterize material present at the dump, it is considered a grab sample and is not representative of the grade, size, width, or extent of mineralization in the area. The sample was submitted to ALS-Chemistry (ALS Chemex) for analysis using the inductively coupled plasma (ICP)-M61 analytical method and returned values of 3.12% copper, 783 parts per million (ppm) silver, and 0.986 ppm gold.

 

Grab sample results are selective in nature and may not be representative of the average grade, thickness, continuity, or extent of mineralization in the area in which they are collected. There is currently insufficient information regarding the size, geometry, and continuity of the mineralization represented by the Coon Dog dump sample to determine its significance.

 

The 2017 reconnaissance work involved two geologists examining surface exposures for additional indications of mineralization. Several prospective features were identified, including the Coon Dog dump. The results contributed to the broader interpretation of the mineralized extent of the CuMo system.

 

7.2Overview

 

Drilling completed on the CuMo project provided subsurface geological, analytical, and mineralization data for the current technical evaluation. Between 2006 and 2012, Idaho Copper completed 42 DDHs, totaling approximately 25,987 m. The drilling was conducted to test the extent, continuity, and grade distribution of molybdenum-copper-silver mineralization, and to support geological modeling and mineral resource estimation.

 

Drilling completed by Idaho Copper and its predecessors followed methods established by earlier historical drilling completed by previous operators. Sample preparation, analytical procedures, QA/QC, and data verification are discussed separately in Sections 8 and 9.

 

A map of all DDHs locations is shown in Figure 5-1.

 

64
 

 

7.3Drill Programs by Year

 

Idaho Copper and its predecessors reported as having drilled a total of 25,987 m among 42 DDHs between 2006 and 2012, as detailed in Table 7-1.

 

Table 7-1 Summary of Diamond Drill Holes by Year

 

Year Number of Holes Length (meters) Length (feet)
2006 1 1,085 3,560
2007 7 3,874 12,710
2008 11 8,157 26,762
2009 9 5,688 18,661
2010 3 1,313 4,307
2011 2 1,157 3,795
2012 9 4,714 15,464
Total 42 25,987 85,259

 

7.3.12006 Drilling

 

In 2006, diamond drilling was done by Kettle Drilling Inc. of Coeur d’ Alane on behalf of Kobex and Idaho Copper Resources Corp. Kobex commenced drilling in August 2006 and completed one hole. On October 6, 2006, Kobex delivered a notice of termination in respect to the CuMo property. The option on the project was terminated when the second hole was at a depth of 600 ft (183 m), and the action of the option termination was taken before any assays were received. Idaho Copper assumed control of the project on October 10, 2006, and completed this hole to a depth of 1,711 ft (521 m) before the program was halted due to the onset of winter conditions.

 

These core holes are summarized in Table 7-2.

 

Table 7-2 Summary of Diamond Drill Holes Completed in 2006

 

Hole (Name) Northing (feet)

Easting

 

(feet)

Elevation (feet) Dip Azimuth Length (feet) Comment
C06-27 120,031.9 220,207.9 6,351.4 -90 0 1,849.0 Completed
C06-28 119,539.8 220,816.8 6,321.1 -90 0 1,711.0 Completed

 

7.3.22007 to 2011 Drilling

 

Between 2007 and 2011, diamond drilling was done by Kirkness Drilling (Kirkness) of Carson City, Nevada. Kirkness drilled 32 DDHs, including the completion of a 2006 DDH. Table 7-3 provides details of the drilling undertaken from 2007 to 2011.

 

65
 

 

Table 7-3 Summary of Diamond Drill Holes Completed in 2007 through 2011

 

Hole (Name) Northing (feet)

Easting

 

(feet)

Elevation (feet) Dip Azimuth Length (feet) Comment
C07-29 119,778.9 221,246.7 6,343.7 -70 140 2,281.7 Completed
C07-30 119,732.2 219,616.8 6,213.1 -90 0 2,416.5 Completed
C07-31 119,792.5 221,243.3 6,342.3 -70 45 2,104.0 Completed
C07-32 119,558.4 220,822.6 6,323.6 -70 190 2,044.0 Completed
C07-33 118,476.7 221,227.0 6,796.8 -90 0 2,095.0 Stopped
C07-34 118,658.3 220,487.4 6,534.2 -70 95 1,769.0 Stopped
C08-35 118,655.2 220,480.4 6,533.2 -90 0 2,817.0 Completed
C08-36 119,335.3 219,448.7 6,274.6 -90 0 2,488.0 Completed
C08-37 119,780.4 221,246.8 6,341.5 -70 335 2,195.0 Completed
C08-38 118,655.2 220,480.4 6,533.2 -70 180 2,441.0 Completed
C08-39 118,917.9 220,813.2 6,575.1 -90 0 2,688.0 Completed
C08-40 119,530.1 220,791.4 6,321.4 -70 225 2,252.0 Completed
C08-41 119,630.2 218,962.5 6,219.9 -90 0 3,018.0 Completed
C08-42 118,748.9 219,911.0 6,549.2 -70 270 2,707.0 Stopped (winter)
C08-43 120,612.8 220,052.8 6,173.8 -80 40 1,313.0 Stopped (fault)
C08-44 118,085.1 221,515.9 6,739.4 -65 75 3,047.0 Completed
C08-45 119,802.3 218,821.4 6,183.7 -80 330 1,796.0 Stopped (winter)
C09-46 118,913.9 220,811.3 6,575.1 -75 110 959.0 Stopped
C09-47 120,686.7 219,421.7 5,832.6 -90 0 2,530.0 Completed
C09-48 120,690.0 219,425.0 5,825.5 -70 305 2,576.0 Completed
C09-49 119,094.6 221,745.7 6,645.3 -90 0 2,847.0 Completed
C09-50 121,548.0 219,843.5 5,832.6 -75 270 1,826.0 Completed
C09-51 121,534.9 219,859.8 5,828.5 -90 0 1,593.5 Completed
C09-52 118,499.5 221,251.3 6,791.2 -75 20 2,772.0 Completed
C09-53 119,803.9 218,830.5 6,183.4 -75 15 2,461.0 Completed
C09-54 119,534.9 219,005.1 6,195.9 -75 15 1,096.0 Completed
C10-55 117,559.6 218,422.5 6,724.2 -65 0 2,479.0 Completed
C10-56 117,559.9 218,421.9 6,724.2 -65 305 1,294.0 Completed
C10-57 117,559.3 218,422.2 6,724.2 -90 0 534.0 Stopped (winter)
C11-58 119,142.8 219,970.3 6,451.3 -90 0 1,885.0 Completed
C11-59 119,095.6 221,745.9 6,645.3 -75 0 1,910.0 Completed

 

66
 

 

7.3.32012 Drilling

 

For the 2012 diamond drilling program, 9 DDHs were drilled for, a total of 15,463 ft (Table 7-4). The DDHs were completed as part of the infill drilling strategy. The holes were located to infill gaps in the existing drilling coverage and were drilled along existing tracks and roads. All holes were surveyed down-the-hole at regular intervals using a Reflex survey instrument. Coordinates, elevations and lengths are in feet.

 

Table 7-4 Summary of Diamond Drill Holes Completed in 2012

 

Hole (Name) Northing (feet)

Easting

 

(feet)

Elevation (feet) Dip Azimuth Length (feet) Comment
C12-60 117,559.9 218,421.9 6,724.2 -50 180 1,455.0 Completed
C12-61 118,748.9 219,911.0 6,549.2 -75 335 1,318.0 Stopped
C12-62 116,866.1 218,040.5 6,628.7 -50 135 1,484.0 Completed
C12-63 116,866.8 218,041.5 6,628.7 -60 330 807.0 Completed
C12-64 118,913.9 220,811.3 6,575.1 -75 25 2,139.0 Completed
C12-65 118,148.8 221,117.5 6,785.7 -80 315 1,908.0 Completed
C12-66 118,674.0 221,687.8 6,689.7 -90 0 2,241.0 Completed
C12-67 118,913.9 220,811.3 6,575.1 -70 340 1,978.0 Completed
C12-68 119,095.6 221,745.9 6,645.3 -70 310 2,133.5 Completed

 

7.4General Drilling Discussion

 

CuMo project drilling programs were directly overseen by field geology staff based in Garden Valley, Idaho. The drilling programs consisted of both HQ and NQ diameter DDHs. The DDHs started with HQ diameter to then allow for reducing to NQ diameter at a major fault intersection, or at 1000 ft depth, which ever was encountered first. Core recoveries were monitored during drilling and were reported to be excellent (90%+). Additionally, all DDHs were surveyed down-the-hole at regular intervals (100 ft) using a Reflex survey instrument. All drill sites were surveyed using a total field station in order to accurately locate and georeferenced the DDHs.

 

All core was collected at the drill site by the diamond drillers under supervision of field geology staff and delivered to the secure warehouse facility in Garden Valley where they were logged, analyzed and samples collected.

 

Figure 7-1and Figure 7-2 show typical sections through the deposit that were developed during previous PEA and reported in 2020 (SRK, 2020). The conceptual pit boundary is based on the 2020 study and included for reference of limits and geometry necessary to mine the presented resource. The section locations are previously shown in Figure 5-1.

 

The QP has reviewed the information and these are shown for completeness with respect to the effective date for this Mineral Resource Estimate remaining August 30, 2018.

 

67
 

 

 

Source: Giroux et al. (2015), modified 2019, reviewed 2026

 

Figure 7-1 CuMo Deposit Q-Q’ Cross-Section (SRK, 2020)

 

68
 

 

 

 

Source: Giroux et al. (2015), modified 2019, reviewed 2026

 

Figure 7-2 CuMo Deposit H-H Cross-Section (SRK, 2020)

 

69
 

 

7.5

Drilling Procedures

 

All Idaho Copper drilling programs were directly supervised by on-site geology staff based in Garden Valley, Idaho. Drilling included both HQ- and NQ-diameter cores, with holes being started at HQ diameter and being reduced to NQ diameter at a major fault intersection or a depth of 1,000 ft, whichever was less. Core recoveries were monitored and were excellent (90%+).

 

All Idaho Copper holes were surveyed down-the-hole at regular intervals (100 ft) using a REFLEX survey instrument. Under the supervision of on-site geology staff, the diamond drillers collected the entirety of each core at the drill site. Cores were delivered to the secure warehouse facility in Garden Valley, where they were logged and analyzed and samples were collected. All drill sites were surveyed using a total field station to accurately locate the holes. Section 8 gives more details on the sampling procedures and core box handling methods employed.

 

7.5.1Sampling Intervals and True Thickness

 

All drill holes completed by Idaho Copper were sampled at 10-ft intervals along the entire hole. The deposit was a stockwork type. No preferred orientation of veins was identified. No systemic adjustment of sampling intervals or intercept lengths to reflect “true thickness” was applied, nor was it considered warranted.

 

7.5.2Significant Drill Results

 

Significant drill results are shown in Table 7-5.

 

70
 

 

Table 7-5 Significant Drill Results

 

Hole (Name)

From

(m)

To

(m)

Length (m) Zone Copper Equivalent % Molybdenite Equivalent % Molybdenite (%) Copper (%) Silver (ppm) Rhenium (ppm) Tungsten (ppm)
C71-01 70.4 574.2 503.8 Main 0.38 0.088 0.059 0.12 2.59 0.00 46
C71-01 118.9 143.3 24.4 Incl. 0.53 0.122 0.099 0.14 2.56 0.00 44
C71-01 518.2 574.2 56.1 Incl. 0.49 0.114 0.100 0.08 1.21 0.00 54
C72-05 137.2 431.6 294.4 Main 0.43 0.099 0.060 0.13 4.46 0.00 75
C74-09 140.2 245.2 105.0 Main 0.54 0.126 0.077 0.12 7.16 0.00 71
C75-10 67.1 658.4 591.3 Main 0.47 0.109 0.099 0.05 1.43 0.00 48
C76-11 42.7 740.1 697.5 Main 0.36 0.084 0.074 0.05 1.55 0.00 36
C76-11 396.2 597.4 201.2 Incl. 0.55 0.128 0.127 0.03 0.77 0.00 58
C76-12 29.9 435.9 405.9 Main 0.25 0.058 0.041 0.06 1.66 0.00 45
C77-13 207.3 549.9 342.6 Main 0.51 0.119 0.111 0.05 1.98 0.00 49
C77-14 237.7 647.3 409.6 Main 0.53 0.124 0.114 0.06 1.84 0.00 65
C77-14 365.8 597.4 231.6 Incl. 0.68 0.158 0.151 0.06 1.91 0.00 74
C77-15 182.9 589.2 406.4 Main 0.53 0.123 0.113 0.06 1.73 0.00 57
C77-15 384.0 573.0 189.0 Incl. 0.64 0.150 0.153 0.02 0.75 0.00 69
C78-16 304.8 649.7 344.9 Main 0.44 0.102 0.093 0.04 1.86 0.00 32
C78-17 353.6 695.4 341.8 Main 0.37 0.086 0.064 0.08 2.55 0.00 40
C78-18 426.7 719.6 292.9 Main 0.62 0.144 0.129 0.08 2.71 0.00 41
C79-19 36.6 694.9 658.4 Main 0.51 0.118 0.101 0.08 2.27 0.00 49
C79-20 50.3 548.6 498.3 Main 0.43 0.099 0.069 0.11 3.83 0.00 52
C81-25 57.9 308.2 250.2 Main 0.43 0.101 0.070 0.13 2.42 0.00 58
C81-25 225.6 308.2 82.6 Incl. 0.53 0.124 0.090 0.14 2.98 0.00 84
C81-26 9.1 228.6 219.5 Main 0.41 0.094 0.034 0.18 7.58 0.00 28
C06-27 36.6 563.6 527.0 Main 0.42 0.097 0.084 0.06 1.60 0.02 49
C06-27 329.2 563.6 234.4 Incl. 0.58 0.136 0.133 0.04 0.99 0.04 59
C06-28 15.2 515.1 499.9 Main 0.47 0.110 0.097 0.07 1.92 0.05 54

 

71
 

 

Hole (Name)

From

(m)

To

(m)

Length (m) Zone Copper Equivalent % Molybdenite Equivalent % Molybdenite (%) Copper (%) Silver (ppm) Rhenium (ppm) Tungsten (ppm)
C06-28 256.0 378.0 121.9 Incl. 0.70 0.162 0.162 0.03 0.98 0.09 68
C07-29 57.9 679.7 621.8 Main 0.52 0.121 0.103 0.08 2.13 0.05 53
C07-29 359.7 545.6 185.9 Incl. 0.74 0.171 0.169 0.04 1.20 0.08 37
C07-30 12.2 727.3 715.1 Main 0.52 0.122 0.108 0.06 2.05 0.04 41
C07-30 359.7 605.9 246.3 Incl. 0.80 0.187 0.185 0.04 1.46 0.07 37
C07-31 6.7 641.3 634.6 Main 0.34 0.079 0.064 0.07 1.76 0.02 43
C07-31 237.7 469.4 231.6 Incl. 0.40 0.092 0.081 0.05 1.45 0.03 45
C07-32 6.7 641.3 634.6 Main 0.55 0.129 0.109 0.09 2.26 0.04 61
C07-32 237.7 469.4 231.6 Incl. 0.65 0.151 0.129 0.10 2.62 0.05 77
C07-33 220.0 638.3 418.2 Main 0.20 0.048 0.026 0.07 2.01 0.01 48
C07-33 603.5 638.3 34.7 Incl. 0.48 0.111 0.084 0.10 2.68 0.03 67
C07-34 42.7 539.2 496.5 Main 0.25 0.058 0.034 0.08 2.30 0.01 53
C07-34 472.4 539.2 66.8 Incl. 0.41 0.096 0.074 0.09 2.36 0.02 67
C08-35 36.6 804.7 768.1 Main 0.31 0.072 0.057 0.06 1.73 0.02 37
C08-35 128.0 804.7 676.7 Incl. 0.33 0.077 0.062 0.07 1.69 0.02 39
C08-35 527.3 804.7 277.4 Incl. 0.43 0.100 0.089 0.05 1.37 0.03 35
C08-36 170.7 758.3 587.7 Main 0.43 0.100 0.088 0.05 1.42 0.03 34
C08-36 280.4 758.3 477.9 Incl. 0.39 0.090 0.103 0.04 1.04 0.03 33
C08-37 18.3 669.0 650.7 Main 0.43 0.100 0.084 0.05 1.67 0.03 42
C08-37 237.7 649.2 411.5 Incl. 0.40 0.094 0.104 0.02 1.17 0.04 41
C08-38 51.8 744.0 692.2 Main 0.46 0.106 0.029 0.06 4.40 0.00 32
C08-39 94.5 819.3 724.8 Main 0.24 0.056 0.099 0.06 1.38 0.03 52
C08-39 274.3 728.5 454.2 Incl. 0.47 0.109 0.122 0.04 1.09 0.04 57
C08-40 18.3 686.4 668.1 Main 0.54 0.127 0.115 0.06 3.79 0.04 46
C08-40 118.9 634.0 515.1 Incl. 0.57 0.133 0.129 0.06 4.27 0.05 45
C08-40 338.3 554.7 216.4 Incl. 0.64 0.150 0.142 0.04 7.78 0.06 45

 

72
 

 

Hole (Name)

From

(m)

To

(m)

Length (m) Zone Copper Equivalent % Molybdenite Equivalent % Molybdenite (%) Copper (%) Silver (ppm) Rhenium (ppm) Tungsten (ppm)
C08-41 259.1 862.6 603.5 Main 0.75 0.173 0.067 0.08 2.23 0.02 43
C08-41 454.2 618.7 164.6 Incl. 0.38 0.088 0.107 0.08 2.99 0.03 38
C08-41 759.0 862.6 103.6 Incl. 0.56 0.129 0.077 0.06 1.53 0.03 34
C08-42 167.6 825.1 657.5 Main 0.38 0.089 0.044 0.06 5.81 0.01 25
C08-42 289.6 825.1 535.5 Incl. 0.33 0.077 0.047 0.07 6.78 0.01 27
C08-42 600.5 825.1 224.6 Incl. 0.36 0.084 0.063 0.05 1.61 0.01 21
C08-43 50.3 397.2 346.9 Main 0.32 0.075 0.044 0.09 4.23 0.02 52
C08-43 201.2 249.9 48.8 Incl. 0.48 0.053 0.070 0.11 3.14 0.03 45
C08-44 342.9 865.6 522.7 Main 0.71 0.078 0.030 0.02 0.89 0.01 29
C08-44 780.3 819.9 39.6 Incl. 0.15 0.035 0.060 0.02 1.47 0.01 20
C08-45 51.8 547.4 495.6 Main 0.27 0.062 0.020 0.15 3.08 0.00 42
C08-45 307.8 547.4 239.6 Incl. 0.27 0.062 0.030 0.18 3.05 0.00 40
C09-46 91.4 292.3 200.9 Main 0.33 0.077 0.030 0.09 2.61 0.01 55
C09-47 88.4 529.3 440.9 Main 0.27 0.062 0.070 0.18 4.29 0.02 20
C09-47 292.6 865.6 573.0 Main 0.42 0.097 0.050 0.18 5.03 0.02 20
C09-48 463.3 737.6 274.3 Incl. 0.40 0.094 0.080 0.05 1.70 0.03 17
C09-49 246.9 464.7 217.8 Main 0.38 0.087 0.110 0.06 1.91 0.04 17
C09-49 158.5 478.5 320.0 Main 0.48 0.112 0.030 0.15 5.29 0.01 20
C09-50 271.3 823.0 551.7 Main 0.31 0.072 0.040 0.15 4.86 0.02 19
C09-51 545.6 804.7 259.1 Incl. 0.34 0.080 0.090 0.07 1.69 0.03 18
C09-52 243.8 753.2 509.3 Main 0.43 0.100 0.140 0.05 1.29 0.06 17
C09-52 460.2 753.2 292.9 Incl. 0.63 0.147 0.090 0.19 4.07 0.02 18
C09-53 179.5 334.1 154.5 Main 0.42 0.098 0.120 0.15 3.68 0.03 19
C09-53 70.1 128.0 57.9 Main 0.49 0.113 0.110 0.05 1.69 0.03 17
C09-54 362.7 365.8 3.0 Incl. 0.20 0.045 0.030 0.07 35.44 0.00 21
C10-55 67.1 152.4 85.3 Main 0.25 0.057 0.040 0.01 0.42 0.01 21

 

73
 

 

Hole (Name)

From

(m)

To

(m)

Length (m) Zone Copper Equivalent % Molybdenite Equivalent % Molybdenite (%) Copper (%) Silver (ppm) Rhenium (ppm) Tungsten (ppm)
C10-55 91.4 149.4 57.9 Main 0.49 0.071 0.070 0.02 3.80 0.02 21
C10-56 67.1 152.4 85.3 Main 0.15 0.035 0.030 0.01 0.01 0.01 25
C10-57 91.4 149.4 57.9 Main 0.35 0.082 0.070 0.02 0.02 0.02 18

 

Note: m = meter, ppm = parts per million

 

74
 

 

7.5.3

Metal Equivalent Calculations

 

Due to the multi-element nature of mineralization and mineral zoning, the equivalent intercept was calculated for both copper and molybdenum. The calculations in this section were used to determine the metal equivalents reported.

 

Metal equivalents for mineral equivalent calculations were based on metal prices outlined in Table 7-6.

 

Table 7-6 Metal Prices Used to Calculate Copper and Molybdenum Equivalent

 

Metal Price ($US) Unit
Copper 2.5 Pounds
Molybdenum Trioxide 10 Pounds
Silver 0.35 Grams

 

Note. $US = U.S. dollar

 

Metal prices used in the equivalency calculation are conservative assumptions from the time of the resource estimation. They do not represent spot or current market prices.

 

Estimated metallurgical recoveries used in the calculations are outlined in Table 7-7.

 

Table 7-7 Estimated Metallurgical Recoveries (%) by Mineral Zone Used to Calculate Copper and Molybdenite Equivalent

 

Mineral Zone Molybdenum % Copper % Silver %
Oxide 80 60 65
Copper-Silver 86 68 75
Copper-Molybdenum 92 85 78
Molybdenum 95 72 55
MSI 95 72 55

 

Note: MSI – potassic-silica alteration zone with lower-grade copper-molybdenum mineralization

 

Recovery (Rec) is taken from Table 7-7 for each assay in a particular mineral zone and applied in the following formulas to derive the equivalents:

 

%Cu Equiv. = (%Cu x 20 x $(Cu) x Rec(Cu) + %MoS2 x 20 x $(MoO3) x (1.5/1.6681) x Rec(Mo) + Ag x $(Ag) x Rec(Ag)) / ($(Cu) x Rec(Cu) x 20)

 

%MoS2 Equiv. = (%Cu x 20 x $(Cu) x Rec(Cu) + %MoS2 x 20 x $(MoO3) x (1.5/1.6681) x Rec(Mo) + Ag x $(Ag) x Rec(Ag)) / ($(MoO3) x Rec(Mo) x 20 x 1.5/1.6681)

 

Where:

 

Rec=Recovery

 

%Cu=Copper grade in %

 

$(Cu)=Copper price per pound

 

Rec(Cu)=Copper recovery

 

  %MoS2 =Molybdenum disulfide (molybdenite) grade in %

 

75
 

 

  $(MoO3) =Molybdenum Oxide price per pound

 

Rec(Mo)=Molybdenum recovery

 

Ag=Silver grade in ppm

 

$(Ag)=Silver price per gram

 

Rec(Ag)=Silver recovery

 

%Cu.=Equiv. Copper equivalent in-situ grade

 

  %MoS2 =Equiv. Molybdenum equivalent in-situ grade

 

Only molybdenum (as grade of MoS2 and conventional pricing of MoO3), copper and silver are used in the equivalent for these formulae.

 

Since the convention on the CuMo project has been to work with %MoS2 for resource estimation, in the foregoing equivalency formulae, %MoS2 is converted back to %Mo by dividing by 1.6681. The %Mo is then converted to %MoO3 by multiplying by 1.5. Also, the %MoS2 Equiv. values would be 1.6681 times greater than %Mo Equiv.

 

7.5.4Drilling Used in the 2012 Mineral Resource Estimate

 

The mineral resource estimate is based on 65 DDHs totaling 36,166 m (118,654 ft). The three RC drill holes historically completed on the property were not used in the mineral resource estimate. Nine of the 65 DDHs included in the estimate were completed during the 2012 drilling program. A list of drill holes used in the mineral resource estimate—including collar coordinates, elevation, dip, azimuth, and hole length—is provided in Table 7-8.

 

Drilling used in the mineral resource estimate includes both historical diamond drilling and Idaho Copper diamond drilling. The drill hole database forms the basis for geological interpretation, mineralized zone modeling, grade estimation, and resource classification.

 

7.5.5Comments

 

The QP considers the type, quantity, and distribution of drilling completed to be adequate to support geological interpretation and the mineral resource estimate. This approval is subject to data verification, sampling, analytical, and QA/QC considerations. Additional drilling may be required in future study phases to improve confidence in geological continuity, support conversion of inferred resources to higher-confidence categories, test potential extensions of mineralization, and provide additional geotechnical, metallurgical, and hydrogeological information.

 

76
 

 

Table 7-8 Drill Holes Used in Resource Estimate

 

Hole

 

(Name)

Northing (feet) Easting (feet) Elevation (feet) Dip Azimuth Length (feet)
C71-01 120,989.9 219,904.5 6,026.5 -90 0 1,884.0
C71-02 120,575.0 219,820.0 6,060.0 -70 0 405.0
C71-03 120,250.0 219,905.0 6,165.0 -90 0 70.0
C71-04 120,785.0 219,940.0 6,045.0 -90 0 113.0
C72-05 120,524.8 220,569.9 6,201.7 -90 0 1,416.0
C72-06 121,749.0 219,919.0 5,902.0 -90 0 663.0
C72-07 121,491.0 219,823.0 5,962.0 -90 0 275.0
C72-08 118,890.0 220,025.0 6,467.0 -90 0 379.0
C74-09 121,438.0 220,687.0 5,890.0 -60 168 804.6
C75-10 119,755.7 221,220.4 6,341.0 -90 0 2,381.0
C76-11 120,455.8 221,250.2 5,996.0 -90 0 3,003.0
C76-12 120,955.0 221,432.0 5,742.0 -43 190 1,340.0
C77-13 119,471.9 219,902.9 6,426.3 -90 0 1,804.0
C77-14 119,085.4 221,271.3 6,613.3 -90 0 2,123.8
C77-15 119,772.1 221,950.9 6,339.0 -90 0 1,933.2
C78-16 119,209.7 219,147.5 6,247.9 -90 0 2,131.7
C78-17 118,711.9 219,886.6 6,544.3 -90 0 2,281.5
C78-18 119,823.5 222,649.1 6,168.3 -90 0 2,361.0
C79-19 120,178.0 219,887.0 6,170.0 -90 0 2,280.0
C79-20 120,878.0 220,787.0 6,105.0 -90 0 2,543.0
C81-24 120,671.1 222,009.5 6,069.8 -90 0 1,000.0
C81-25 119,890.0 219,289.7 6,019.0 -90 0 1,011.0
C81-26 121,338.1 221,432.9 5,767.5 -90 0 1,193.0

 

77
 

 

Hole

 

(Name)

Northing (feet) Easting (feet) Elevation (feet) Dip Azimuth Length (feet)
C06-27 120,031.9 220,207.9 6,351.4 -90 0 1,849.0
C06-28 119,539.8 220,816.8 6,321.1 -90 0 1,711.0
C07-29 119,778.9 221,246.7 6,343.7 -70 140 2,281.7
C07-30 119,732.2 219,616.8 6,213.1 -90 0 2,416.5
C07-31 119,792.5 221,243.3 6,342.3 -70 45 2,104.0
C07-32 119,558.4 220,822.6 6,323.6 -70 190 2,044.0
C07-33 118,476.7 221,227.0 6,796.8 -90 0 2,095.0
C07-34 118,658.3 220,487.4 6,534.2 -70 95 1,769.0
C08-35 118,655.2 220,480.4 6,533.2 -90 0 2,817.0
C08-36 119,335.3 219,448.7 6,274.6 -90 0 2,488.0
C08-37 119,780.4 221,246.8 6,341.5 -70 335 2,195.0
C08-38 118,655.2 220,480.4 6,533.2 -70 180 2,441.0
C08-39 118,917.9 220,813.2 6,575.1 -90 0 2,688.0
C08-40 119,530.1 220,791.4 6,321.4 -70 225 2,252.0
C08-41 119,630.2 218,962.5 6,219.9 -90 0 3,018.0
C08-42 118,748.9 219,911.0 6,549.2 -70 270 2,707.0
C08-43 120,612.8 220,052.8 6,173.8 -80 40 1,313.0
C08-44 118,085.1 221,515.9 6,739.4 -65 75 3,047.0
C08-45 119,802.3 218,821.4 6,183.7 -80 330 1,796.0
C09-46 118,913.9 220,811.3 6,575.1 -75 110 959.0
C09-47 120,686.7 219,421.7 5,832.6 -90 0 2,530.0
C09-48 120,690.0 219,425.0 5,825.5 -70 305 2,576.0
C09-49 119,094.6 221,745.7 6,645.3 -90 0 2,847.0
C09-50 121,548.0 219,843.5 5,832.6 -75 270 1,826.0
C09-51 121,534.9 219,859.8 5,828.5 -90 0 1,593.5
C09-52 118,499.5 221,251.3 6,791.2 -75 20 2,772.0

 

78
 

 

Hole

 

(Name)

Northing (feet) Easting (feet) Elevation (feet) Dip Azimuth Length (feet)
C09-53 119,803.9 218,830.5 6,183.4 -75 15 2,461.0
C09-54 119,534.9 219,005.1 6,195.9 -75 15 1,096.0
C10-55 117,559.6 218,422.5 6,724.2 -65 0 2,479.0
C10-56 117,559.9 218,421.9 6,724.2 -65 305 1,294.0
C10-57 117,559.3 218,422.2 6,724.2 -90 0 534.0
C11-58 119,142.8 219,970.3 6,451.3 -90 0 1,885.0
C11-59 119,095.6 221,745.9 6,645.3 -75 0 1,910.0
C12-60 117,559.9 218,421.9 6,724.2 -50 180 1,455.0
C12-61 118,748.9 219,911.0 6,549.2 -75 335 1,318.0
C12-62 116,866.1 218,040.5 6,628.7 -50 135 1,484.0
C12-63 116,866.8 218,041.5 6,628.7 -60 330 807.0
C12-64 118,913.9 220,811.3 6,575.1 -75 25 2,139.0
C12-65 118,148.8 221,117.5 6,785.7 -80 315 1,908.0
C12-66 118,674.0 221,687.8 6,689.7 -90 0 2,241.0
C12-67 118,913.9 220,811.3 6,575.1 -70 340 1,978.0
C12-68 119,095.6 221,745.9 6,645.3 -70 310 2,133.5

 

79
 

 

8 Sample Preparation, Analyses, and Security

 

The QP has reviewed the procedures followed by Idaho Copper, as well as by third parties on behalf of Idaho Copper, and believes these procedures are consistent with industry best practices and acceptable for use in geological and resource modeling.

 

8.1General Sampling

 

Sampling was restricted from 2006 to 2012 to DDH core sampling and metallurgical sampling of previously drilled DDH core material. Standard core sampling methods were employed for both DDH core and metallurgical samples.

 

At the time of drilling, each core box was clearly labeled with the DDH hole number, core box number, and “to” and “from” drill core footages. Wooden core boxes were used at all times, and full core boxes were sealed with lids. The driller(s) and/or geologist(s) then delivered the core boxes to a secure core storage warehouse located in Garden Valley, Idaho. The core boxes were laid out in sequence on long tables specifically made for core-logging purposes, and geologists logged each core for lithology, structure, alteration, and mineralization. Geotechnical measurements for RQD were recorded. Additionally, each core box was labeled using a metal Dymo® labeling tool, for long-term preservation of identification. Each core was photographed, two boxes at a time, using a mounted Nikon® digital camera, before being delivered to the core-cutting technician. The photographs were downloaded onto computer files specific to each DDH.

 

Using a standard rock saw, the core-cutting technician sampled the cores using typical procedures. A half-core was collected at regular 10-ft intervals for analysis. Sample lengths were adjusted to lithological contacts in cases wherein barren dikes were intersected.

 

Half-core sample intervals were placed in sample bags, with the sample number on the outside of the bag in black permanent marker. Individual sample interval tags were included in each sample bag. The bag was then closed securely with a wire tie and placed in a plastic transport crate for shipping.

 

MoS2 loss from soft fracture fillings being washed away when a core is sawed in half has been noted at CuMo. Although there is no physical way to eliminate this problem at present—other than educating technicians on the extra care needed when sawing a soft fracture zone—geologists at CuMo have addressed possible inadvertent contamination of other cores by MoS2-enriched water from the rock saw’s water-recirculation tank. Their solution is to give the cut core a second clear-water bath prior to bagging or storing the core, and to void and refill the recirculation tank based upon clarity.

 

For each core, one bagged half-core sample was sent for analysis, and the other half-core sample was retained and stored at a core-storage warehouse. Each retained core was returned to its original core box, which was sealed with a plywood cover and stacked on a standard pallet. Each plywood cover was clearly labeled with the core’s information. The boxes were then strapped to the pallet with a metal banding tool, and the pallet was stored within the archive section of the core-storage warehouse.

 

Blanks and standards were inserted into the sample stream at a frequency of 1 every 20 samples. The core-cutting technician selected the exact intervals and noted them on the sample logs. While the technician inserted the blanks, the geologist-in-charge selected and inserted the standards.

 

80
 

 

Standards were selected from three bulk standards (low-, medium-, and high-grade) prepared from historical CuMo drill core samples. Standards were selected based on the grade that most closely matched the estimated grade of the core adjacent to each standard sample interval.

 

The standards were prepared and packaged by CDN Resource Laboratories Ltd. (CDN Labs) of Surrey, British Columbia. Each bulk sample was pulverized in a large rod mill, screened through 200 mesh (< 74 micrometer [μm]) using an electric sieve, and homogenized in a large, rotating mixer. Each standard was sealed in plastic to prevent gravity separation and oxidation. The standards were certified by Smee & Associates Consulting Ltd. of North Vancouver, British Columbia, based on round-robin analysis at five laboratories using a four-acid digestion and inductively coupled plasma-emission spectroscopy (ICP-ES) finish (Table 8-1). Note that the molybdenum parts per million values reflect measured molybdenum metal (i.e., not MoS2).

 

Table 8-1 Certified Standards Prepared for CuMo Project

 

Standard Element Certified Mean Standard Deviation
(among laboratories)
Standard 1 Total copper 1,138 ppm 65 ppm
Total molybdenum 367 ppm 19 ppm
Standard 2 Total copper 151 ppm 8 ppm
Total molybdenum 995 ppm 41 ppm
Standard 3 Total copper 840 ppm 35 ppm
Total molybdenum 54.0 ppm 3.7 ppm

 

Note: ppm = parts per million

 

The bagged core samples were string or wire tied and stored temporarily on holding pallets at the core-storage warehouse. When enough samples had been accumulated, Idaho Copper personnel delivered them to ALS-Chemistry (ALS Chemex) in Elko, Nevada, for preparation and analysis.

 

8.2Density Determinations

 

Specific historical (i.e., pre-2012) gravity determinations were made by Amax for CuMo for each mineralized zone. Skyline Laboratories of Colorado took measurements using the weight-in-air/weight-in-water procedure.

 

Prior to 2012, Idaho Copper had occasional density measurements recorded at ALS Chemex’s laboratory. Since 2012, Idaho Copper has maintained a regular density-measurement program, wherein 4- to 6-in. skeletons of half-cores from each sample interval representative of the 10-ft interval are analyzed. The following equipment and parameters are used in the analysis and have been added to the regular core-processing routine:

 

●4,000-gram (g) Sartorius Extend Series Digital Scale, with hook attachment

 

●Stand for scale

 

●Bucket of distilled water

 

●Bricks

 

●Computer with MS EXCEL®

 

●2,000-g calibration weight

 

81
 

 

The following equation was used to perform the density calculations:

 

Weight in air / (Weight in air – Weight in water)

 

The following data were recorded on the EXCEL® spreadsheet, in accordance with the example structure shown in Table 8-2.

 

Table 8-2 Density Data Example

 

Hole No. Sample Depth Dl mg Ml Ds Diameter

Scanner

Maximum

Scanner

Average

Zone Code
C08-41 95.5 1 396.53 240.82 2.55 16 0.101 0.048 Copper-Silver

Note. Zone code is included to identify the mineralized zone of the sample. Dl = density of distilled water, Ds = density of solid, mg = milligram, Ml – mass of sample in water

 

A total of 4,339 density measurements were completed on holes C08-41 through C12-68.

 

An additional density measurement of the bulk sample delivered to SGS was taken as part of the metallurgical study. The density obtained by SGS confirmed the earlier density measurements done by Amax.

 

Table 8-3 outlines the density values for each of the different mineralized zones, plus dykes.

 

Table 8-3 Density Measurement Results Summary

 

Grade Domain Code Density (tonnes per m3) Sample Count
Oxide 2.50 578
Copper-Silver 2.58 1,505
Copper-Molybdenum 2.58 1,524
Molybdenum 2.57 763
MSI 2.57 91
DYKE 2.52 78

Note: m³ = cubic meter; MSI = potassic-silica alteration zone with lower-grade copper-molybdenum mineralization

 

8.3Assay Techniques

 

Samples submitted by Kobex were routinely analyzed via the ALS Chemex ME-ICP61 procedure code for 39 elements, using a four-acid digestion with analysis by inductively coupled plasma emission-atomic emission spectroscopy (ICP-AES).

 

Samples submitted by Idaho Copper were routinely analyzed by ALS Chemex, an independent laboratory with ISO 9002 certification applicable at the time testing was conducted. The laboratory used ME-MS ICP61 procedure code for 47 elements using a four-acid digestion with analysis by inductively coupled plasma mass spectrometry (ICP-MS).

 

82
 

 

Samples submitted by Idaho Copper for inter-laboratory check analysis were analyzed by SGS, an independent laboratory with ISO 9002 and ISO 17025 accreditation applicable at the time testing was conducted. The laboratory used the SGS ICM40B method for 50 elements using a four-acid digestion/ICP-AES and ICP-MS.

 

The assay methods reported the main element results as follows:

 

●Molybdenum in ppm Mo, stored as both ppm Mo metal and molybdenum disulphide (MoS2%) in the database to reflect the actual natural material
   
●Copper in ppm Cu, stored as both ppm and percent copper (Cu%) in the database
   
●Silver in ppm Ag, stored as ppm, grams/tonne, and ounces/ton in the database
   
●Tungsten in ppm W, stored as ppm in the database
   
●Rhenium in ppm, stored as ppm in the database

 

8.4Current Core Storage

Currently, the core samples are stored 35 miles northwest of Boise, Idaho, and approximately 46 miles west of the CuMo project (Figure 8-1). The core, rejects, and exploration-related documentation were moved from the previous storage facility in Garden Valley to this secure area. The core boxes have been temporarily stored in this location while a more suitable storage facility is acquired. The core boxes are individually marked and labeled. During the site visit, the QP examined a representative selection of core boxes and confirmed that box labeling, sample intervals, and hole identifications were consistent with the project records reviewed. The core is stored on pallets stacked and bound by metal strapping (Figure 8-2) and is being covered by a tarp to prevent against rain and snow events. Historical samples are kept in high-walled pallets.

 

83
 

 

 

Figure 8-1 Location of Core Storage Facility and the CuMo Project

 

84
 

 

 

Figure 8-2 Core Boxes at Current Storage Facility

 

8.5QA/QC Programs

 

8.5.1Historical Checks

 

In a June 2005 report (Giroux et al., 2005), six datasets were available to verify the original Skyline MoS2 assay database (pre-Idaho Copper involvement in project). Skyline re-assayed its original assays at three stages of the sampling procedure: core duplicate samples, splits of rejects, and splits from pulps. Three inter-laboratory sets of duplicates were also available to compare with the Skyline original assays: a pulp sent to the Amax Laboratory (Amax) in Climax, Colorado, from DDH assays; a second split at the drill of RC drill cuttings; and a selected set of samples sent to Hazen Research’s (Hazen’s) laboratory. The results from all comparisons are discussed in this section.

 

It should be noted that the convention for the CuMo project has been to measure percent elemental molybdenum (%Mo) in assays, and to calculate %MoS2 by multiplying %Mo by 1.6681. Both %Mo and %MoS2 data are stored in the project’s database, and the latter are used in resource estimates and mine planning. Consequently, in the following descriptions comparing %MoS2 grades, they were the calculated MoS2 grades based on the underlying %Mo assays.

 

85
 

 

The first set compares 64 original MoS2 values with values from duplicate core samples, both run at Skyline. Figure 8-3 shows a very slight proportional bias, as indicated by the best-fit regression line below the equal value line; however, it is more than likely this is simply a function of the wide, random scatter of the data. The correlation coefficient is only 0.7061, indicating the amount of scatter about the best-fit regression line in Figure 8-3. The average precision (a measure of the reproducibility of a result by repeated attempts) of ±78% again points to high sampling variability among core samples.

 

 

 

Figure 8-3 Skyline Original MoS2 Versus Skyline Duplicate MoS2 from Duplicate Drill Core

 

The second set of checks consists of 25 original Skyline assays compared to re-splits of rejects also run by Skyline. This dataset shows a very slight fixed bias with the best-fit regression line (Figure 8-4), a constant 0.0011% MoS2 below the equal-value line. The coefficient of correlation is 0.9666. The average precision of this test is ±20%, indicating good reproducibility among samples after initial crushing.

 

86
 

 

 

Figure 8-4 Skyline Original MoS2 Versus Skyline Duplicate MoS2 from Rejects

 

The third set is a total of 408 samples reanalyzed by Skyline by taking a second assay from the pulp. This comparison is shown in Figure 8-5. The best-fit regression line through the data mirrors the equal-value line, indicating no bias. The correlation coefficient is 0.9891, and the precision on the estimate is ±23%.

 

 

Figure 8-5 Skyline Original MoS2 Versus Skyline Duplicate MoS2 from Pulps

 

The fourth set of historical data consists of a total of 303 sample pulps from DDHs analyzed for MoS2 by both Skyline and Amax. The results are shown in Figure 8-6. There is no bias indicated, with the best-fit regression line pulled slightly below the equal-value line by a single high-value outlier. There appears to be an equal number of samples falling on either side of the equal-value line. The correlation coefficient is 0.9671. The precision is ±56.5%.

 

87
 

 

 

Figure 8-6 Skyline Original MoS2 Versus Amax Check MoS2 on Pulps from Drill Core

 

A fifth set of duplicates compares original MoS2 results to an Amax second split of cuttings in a total of 57 samples from RC drill holes (see Figure 8-7). This subset shows no apparent bias, with the best-fit regression line and equal-value line being very close to each other. The correlation coefficient of 0.5989 is less than those of previous comparisons, and the data show much more scatter. The average precision of ±101% is much higher than those of previous comparisons. This is a very poor comparison between two laboratories; the large degree of random scatter is probably more the result of the two splits from the RC cuttings than of a comparison of the laboratories.

 

 

Figure 8-7 Skyline Original MoS2 Versus Amax Check MoS2 on RC Cuttings

 

88
 

 

A final set of Skyline original samples (10 samples) were sent to Hazen. While this set is hardly a representative sample, the results in Figure 8-8 show a pronounced proportional bias, with the best-fit regression line below the equal-value line. On average, the original Skyline assays for MoS2 are 0.70 of the value indicated by Hazen. A total of 8 out of 10 samples returned higher values at Hazen. The correlation coefficient is poor at 0.7281, and the average precision is ±55%.

 

 

 

Figure 8-8 Skyline Original MoS2 Versus Hazen Check MoS2 on Pulps

 

In general, the results from the first three tests at Skyline show increasing precision and lessening sampling variability from splits of core to splits from rejects to splits from pulps, as would be expected. The inter-laboratory test of diamond drill pulps between Skyline and Amax showed good agreement and no bias. A similar check between Skyline and Amax on two splits from RC cuttings again showed no bias but greater sampling variability. The final limited test of 10 samples comparing original Skyline results with Hazen checks showed a strong bias, with Hazen overestimating MoS2 relative to Skyline.

 

The historical sample preparations and analyses were done by a large, professional, international mining company, Amax, which presumably used professional sampling and assaying laboratories for its samples collected in the project area. There is no reason to suspect any irregularities or to question the results of the historical sampling.

 

8.5.2Blanks

 

During Idaho Copper’s diamond drill programs, blank samples were inserted into the sample stream at a frequency of or about 1 in 20. A total of 431 blanks were analyzed for molybdenum, copper, silver, rhenium, gallium, tungsten, iron, and sulfur. The results were very good, with no anomalies produced. The graphs for MoS2 (calculated) and copper are shown in Figure 8-9 and Figure 8-10, respectively.

 

89
 

 

 

Note: MoS2 grade is on the y-axis and sample number on x axis. Source: Giroux et al. (2015)

 

Figure 8-9 MoS2 in Blank Samples from Idaho Copper Drill Programs at CuMo

 

90
 

 

 

Note: Cu grade is on the y-axis and sample number on x axis. Source: Giroux et al. (2015)

 

Figure 8-10 Cu in Blank Samples from 2008 Drill Program CuMo

 

91
 

 

8.5.3Internal Laboratory Standards

 

The primary laboratory, ALS Chemex, inserted a blank and standard with every batch run during 2008. The policy was that unless the correlation results were excellent, the batch was redone. A total of 180 blanks and 346 standard results were provided with the analysis.

 

8.5.4Internal Pulp Checks

 

ALS Chemex also routinely ran duplicate checks on sample pulps. Over the 2007 to 2012 drill program, a total of 143 check samples were run for molybdenum. Figure 8-11 and Figure 8-12 show the results are excellent, with all but a few samples falling on an equal-value line. The best-fit regression line mirrors the equal-value line.

 

92
 

 

 

Source: Giroux et al. (2015)

Figure 8-11 Scatter Plot of Chemex Internal Duplicates for Mo ppm (Mo Metal)

 

93
 

 

 

Source: Giroux et al. (2015)

 

Figure 8-12 Scatter Plot of Chemex Internal Duplicates for Cu ppm

 

94
 

 

8.5.5Idaho Copper Standards

 

As explained in Section 8.1, CDN Labs prepared a set of standards using drill core from the CuMo property. Results for Standard 1 (see Figure 8-13)—the medium-grade standard for MoS2 (calculated) and highest-grade standard for Cu—are reasonable, with most falling between the mean ±2.5 standard deviations.

 

 

Source: Giroux et al. (2015)

 

Figure 8-13 Results for Standard S1

 

95
 

 

Standard S2, a higher-grade MoS2 and lower-grade Cu standard, shows reasonable results for Cu and MoS2 assays (see Figure 8-14), with all data falling between the mean ±2.5 standard deviations.

 

 

Source: Giroux et al. (2015)

Figure 8-14 Results for Standard S2

 

The results for Standard S3 are also reasonable, with more noise in the analysis due to the low-grade values encountered, but no large variations are observable (Figure 8-15).

 

96
 

 

 

Source: Giroux et al. (2015)

 

Figure 8-15 Results for Standard S3

 

8.5.6Coarse Reject Duplicates

 

At the ALS Chemex laboratory, the DDH core samples were crushed, and two duplicate samples were taken, every 20th sample being analyzed by splitting the crushed half core. Idaho Copper has been taking coarse reject duplicates since 2006.

 

97
 

 

Coarse reject duplicates were submitted to measure the precision of the sample preparation and the analysis process. The first duplicate underwent the same analytical procedure as the original sample (ICP-MS61). The results for molybdenum are shown in Figure 8-16, the results for copper in Figure 8-17, and results for silver in Figure 8-18.

 

The second duplicate was analyzed for molybdenum and copper using the X-ray fluorescence (XRF) technique. This process confirmed both sample and analytical technique variability. The results for molybdenum are shown in Figure 8-19, and the results for copper are shown in Figure 8-20.

 

98
 

 

 

Figure 8-16 Results for Chemex Molybdenum Original versus ICP Check

 

99
 

 

 

Figure 8-17 Results for Chemex Copper Original Versus ICP Check

 

100
 

 

 

Figure 8-18 Results for Chemex Silver Original versus ICP Check

 

101
 

 

 

Figure 8-19 Results for Chemex Molybdenum Original Versus XRF Check

 

102
 

 

 

Figure 8-20 Results for Chemex Copper Original Versus XRF Check

 

103
 

 

Between 2008 and 2012, 708 duplicate samples were submitted, resulting in a submission frequency rate of 1 in 20 samples. Overall, the results of the Idaho Copper coarse crushed duplicates from drill core samples show good precision and no evidence of sampling bias. Silver duplicate analyses results tend to show some scatter but are within acceptable tolerance limits. Precision plots yield good results, with an average of 80% of the data plotting within 20% of their respective duplicate samples, while an average of 55% of the data plot within 10%.

 

8.6Survey Validation

 

Idaho Copper established a survey control network completed by Geoterra Integrated Resource System Ltd. In 2007, 24 control points were surveyed by a licensed legal land surveyor, Shelby H. Griggs, of Boise, Idaho.

 

The survey was established using North American Datum 1983 (NAD83)(1999) (high-accuracy reference network [HARN]) UTM Zone 11 coordinates and North American Vertical Datum 1988 (NAVD88) elevations. Points included several drill holes completed before Hole 30. Monument control points were permanently marked with aluminum land survey pins. Future drill hole sites were surveyed using a total GPS station tying into the original survey points.

 

In 2012, Sacré-Davey conducted a re-survey of previous holes and surveyed 2012 holes and found no discernible difference among older hole locations. All Idaho Copper drill holes (i.e., 2008 and later) were surveyed down-the-hole using a REFLEX survey instrument. Holes dating prior to 2008 were surveyed by Troparia and/or single-shot Sperry Sun survey tools.

 

The QP visited and checked some of the drill sites during a site visit.

 

8.7Verification of Drilling Data

 

Drill hole data collected prior to 2008 were verified and validated by Ausenco Pty Ltd., which checked the header, survey, assay, geology, and geotechnical tables for missing, overlapping, or duplicated intervals and sample numbers, as well as for matching drill hole lengths across tables. Collars and traces were reviewed in plan and section as a visual check on collar and survey validity. In 2012, Snowden performed the same validation on all pre-2012 data.

 

104
 

 

9 Data Verification

 

The QP has reviewed the data collection and verification procedures followed by Idaho Copper and third parties on behalf of Idaho Copper and believes these procedures are consistent with industry best practices and acceptable for use in geological and resource modeling.

 

Previous public reports reviewed by the QP describe the previous validations; the QP has reviewed these reports and determined the processes and steps to be valid to demonstrate the validity of the data. In 2015, the survey validation steps were completed and described in relevant sections regarding the 2012 drilling data and assays.

 

The QP has no knowledge of any errors in the pre-2012 data and is aware that a few minor discrepancies were corrected within the datasets in the 2012 study.

 

105
 

 

10 Mineral Processing and Metallurgical Testing

 

Metallurgical test work was completed by SGS Lakefield on three composite samples in 2025 and 2026. The test program focused on flotation testing and did not include any additional ore hardness or dewatering testing. Test work completed in 2009 and 2015 is summarized in the report “Preliminary Economic Assessment & 43-101 Technical Report for the CuMo Project, USA” which was published May 2020. The text from the report is duplicated here in Section 10.2 for completeness.

 

The primary QP for this section, Mr. Scott Sims, has reviewed the underlying data, analytical work, and technical reports and takes responsibility for this summary.

 

10.1Metallurgical Testing (2025 and 2026)

 

10.1.1Introduction

 

Three composite samples were tested for rougher and cleaner flotation response. The work was built upon the previous test work and utilized the previously determined grind size conditions. Rougher and open circuit cleaner tests were conducted to determine flotation kinetics. Large scale flotation tests were completed for initial copper-molybdenum separation testing. Locked cycle flotation tests were completed and utilized to refine the recovery and grade projections for the project.

 

10.1.2Sample Origin

 

Three composite samples were compiled from drill core and shipped to the SGS Lakefield facility in 2024. Flotation testing commenced at SGS Lakefield in January 2025. The samples represented the following three primary ore zones of the Idaho Copper deposit:

 

●Copper silver (CuAg)
   
●Copper molybdenum (CuMo)
   
●Molybdenum (Mo)

 

Drill core utilized for the three samples was drilled in 2007, 2008, 2009, 2011, and 2012. The drill hole data that was used to composite the three metallurgical samples is shown in Table 10-1.

 

106
 

 

Table 10-1 Metallurgical Composite Samples Drillhole Sources

 

Year Borehole CuAg CuMo Mo
2007 C07-32 X X  
2008 C08-39   X X
2009 C09-47 X X  
2009 C09-49 X X X
2009 C09-52     X
2011 C11-59   X X
2012 C12-67 X X X
2012 C12-68   X  

Note. CuAg = copper-silver, CuMo = copper-molybdenum, Mo = molybdenum

 

10.1.3Rougher Kinetics Tests

 

Baseline rougher kinetics flotation tests were performed on each of the three composite samples. Six tests were conducted in total. The CuAg sample achieved higher copper when sodium isobutyl xanthate (SIBX) was used as the copper collector compared to 3418A. The CuMo sample copper grade was improved when the grind size was increased from 45 µm to 74 µm. The molybdenum flotation performance was relatively similar at the conditions tested.

 

10.1.4Cleaner Kinetics Test

 

Rougher and open circuit cleaning tests were performed on each composite sample to determine the flotation kinetics. Copper grade and recovery for the CuAg and Mo samples improved with higher copper collector dosages. The molybdenum grade and recovery improved in the Mo sample at a slightly coarser grind size.

 

10.1.5Large Scale Tests

 

The test charge size was increased from 2 kg to 4 kg and 12.5 kg to produce enough 3rd cleaner bulk concentrate to perform a copper/molybdenum separation flotation test. The CuAg and CuMo composite samples were tested twice, and the Mo composite sample was tested once. While the test conditions were not optimized, the test results showed an effective copper/molybdenum separation. Additional testing is required to determine the optimum conditions.

 

The additional testing should include large scale bulk roughing and cleaner flotation under optimized conditions to reject pyrite to produce bulk cleaner concentrate in sufficient quantity to support multiple copper/molybdenum separation flotation tests. The copper/molybdenum separation tests will consist of locked cycle flotation tests to determine the number of cleaning stages required, optimize reagent addition, and if an additional regrind stage is required.

 

10.1.6Locked Cycle Tests

 

The CuAg sample tests achieved higher flotation recoveries and grades compared to the sample tested in 2015. The 2015 sample was suspected to have oxidized minerals which would explain the lower recovery and grades. The CuMo sample and the Mo sample performed similarly to the 2015 samples.

 

107
 

 

The test results sulfur assays indicate that the primary diluent in the concentrate samples is likely pyrite. Future testing to determine an effective pyrite depression strategy will likely produce higher concentrate grades at similar recoveries. A mineralogy study should be conducted to determine the sulfide mineral liberation in the ore zones as well as the flotation circuit products. pH as well as collector selection may also improve pyrite flotation selectivity.

 

The copper concentrate grade produced in the tests of less than 20% by the Mo zone ore is lower than typically processed by smelters. Pyrite depression may need to be supplemented by additional flotation cleaning steps to produce a saleable copper concentrate grade. This impact may be mitigated by processing the Mo zone blended with the CuAg zone or the CuMo zone ores. Concentrate blending may also be used to ship higher copper grade concentrates.

 

10.1.7Recovery Projections

 

Based on the locked cycle tests conducted in 2026 along with the previous locked cycle test results, expected copper, molybdenum, and silver recoveries are projected for the Idaho Copper mill. The locked cycle test recoveries were reduced to account for molybdenum circuit cleaning recoveries and the targeted final concentrate grades. The recovery results are shown in Table 10-2.

 

Table 10-2 Projected Recoveries

 

Ore Zone Copper Molybdenum Silver
CuAg 87% 82% 77%
CuMo 87% 92% 75%
Mo 66% 90% 49%

Note. CuAg = copper-silver, CuMo = copper-molybdenum, Mo = molybdenum

 

The recoveries shown in Table 10-2 are interpreted from the test work based on producing a copper concentrate at 22% copper and a molybdenum concentrate at 52% molybdenum. For the economic analysis, concentrate grades of 28% copper and 55% molybdenum were used assuming that the pyrite rejection in the flotation circuit is successful.

 

10.2Metallurgical Testing (2009, 2015)

 

This sub-section 10.2 is reproduced from the 2020 PEA for completeness.

 

10.2.1Introduction

 

The test work undertaken to date is limited, with three composite samples tested for comminution characteristics and preliminary flotation testing to produce bulk copper/molybdenum concentrates. Despite limitations, the existing test work data are considered suitable for a conceptual study and the comminution data are considered adequate for a preliminary engineering assessment of the grinding circuit design. No copper/molybdenum separation or ferric chloride leaching of molybdenum concentrates has been undertaken to allow determination of final concentrate grades and recoveries achievable into saleable concentrates. Where no test work data are available, reasonable assumptions, based on typical industry values or data from other similar projects (e.g. Sierrita and Thompson Creek) have been used to develop the process design criteria used in plant design.

 

108
 

 

Thompson Creek is a primary molybdenum mine of similar mill feed grade to CuMo and, therefore, has similar recovery processes. Sierrita is a copper-molybdenum processing operation that produces separate copper and molybdenum concentrates from a bulk concentrate. Both are directly applicable to CuMo. These operations provide the basis for assumptions for copper/molybdenum separation by flotation, and production of saleable concentrates using additional flotation cleaning stages beyond those tested for CuMo. They also provide a basis for ferric chloride leaching of molybdenite (MoS2) flotation concentrate following flotation.

 

The CuMo mineralized material is of moderate hardness and is amenable to grinding in a conventional semi-autogenous grind (SAG) or ball milling circuit with or without pebble crushing. The mineralogy is fine grained and test work done indicates the requirement for a fine target grind size to achieve adequate liberation for flotation.

 

Acid-base accounting (ABA) testing indicates that the tailings are potentially acid neutralizing (PAN) due to the presence of carbonate and low pyrite content. SGS concludes that “the tailings tested were not acid generating”. Further studies are required, but if confirmed, this will lead to significant cost savings in the tailings handling circuit and a major reduction in the environmental impact of the project.

 

The three composite samples which were tested are labelled for the mineralized zones: CuAg, CuMo and Mo. The CuAg and CuMo labelled composites comprise both the oxide and sulfide parts of the system; oxide is not separated. The Mo composite consists of both Mo and MSI zones. To arrive at the recoveries for the oxide and MSI zone from the mixed samples, polished sections were examined, and factors were calculated to reduce the recoveries obtained for the CuAg sample. This is a conservative approach as the inclusion of the lower recovery oxide within the CuAg and CuMo zones effectively reduces the overall recovery below what could otherwise be expected.

 

10.2.2Sample Selection

 

Idaho Copper began collecting metallurgical samples for grinding and flotation testing in December 2007. One fourth of the core (quarter core) was used from continuous samples of the mineralized zones (an upper copper-silver zone, underlain by a transitional copper-molybdenum zone, in turn underlain by a lower molybdenum-rich zone) from drill holes CO6-27, CO6-28 and CO6-29 and collected as individual 10 ft samples of quarter core selected as representative of the three mineralized zones. Technicians supervised by geological staff collected the samples and prepared them for shipment. A bonded carrier took the samples from Garden Valley, Idaho to Vancouver, British Columbia. The samples were taken to SGS Canada, Kent Corporate Center, Kent Avenue N., Vancouver, British Columbia, for the metallurgical study. The test work results are detailed in an independent private report entitled “An Investigation into the recovery of molybdenum, copper and silver from CuMo samples prepared for Mosquito Consolidated Gold Mines Ltd. Project 50004-001.”

 

10.2.3Test Work Program

 

The flotation and grinding metallurgical test work program used as the basis for this report consisted of comminution and flotation test work on three separate metallurgical composites; copper/silver, copper/molybdenum and molybdenum, that were assembled to represent the three known mineralized types in the CuMo deposit at the time of testing. The test work results are reported in “An Investigation into the recovery of molybdenum, copper and silver from CuMo samples prepared for Mosquito Consolidated Gold Mines Ltd Project 50004-001” (SGS, 2009).

 

109
 

 

Two main phases of flotation and grinding metallurgical testing were undertaken on the CuMo samples:

 

●Bench scale comminution testing, consisting of SAG Performance Index (SPI®) and Bond ball mill work index testing
   
●Bench scale flotation testing consisting of rougher kinetic flotation, cleaner flotation and locked-cycle tests, supplemented with mineralogical examination

 

10.2.3.1Comminution Test Work Suite

 

The current comminution dataset consists of three SAG Power Index (SPI®) and Bond Ball Mill Work Index tests, one on each of the composites. Table 10-3 summarizes the outcomes of the comminution laboratory test work undertaken for this study, the table also shows the selected design case, which typically corresponds to copper/silver. To date, no samples have had SAGDesign Testing, Drop Weight Index (DWI) Testing (either by the JK Drop Weight Test or SAG Media Competency Test), Bond Crushing Index, Bond Rod Mill Index or Abrasion Index testing. Values for these metrics have been estimated from the available data or from typical values for similar mineralization.

 

Table 10-3 Summary of Comminution Test Work Data

 

Comminution Characteristics Unit CuAg CuMo Mo Design
Specific Gravity g/cm³ 2.64 2.60 2.60 2.64
SPI® min 84.5 73.0 70.8 84.5
SMC DWI kW/m³ n/a n/a n/a 7.4
Crushing Work Index kWh/mt n/a n/a n/a 15.8
Bond Rod Mill Work Index kWh/mt n/a n/a n/a 15.8
Bond Ball Mill Work Index (Closing Screen 106 pm) kWh/mt 15.8 15.7 12.6 15.8
Bond Abrasion Index   n/a n/a n/a 0.25

Note. CuAg = copper-silver, CuMo = copper-molybdenum, g/cm3 = grams per cubic centimeter, kW/m³ = kilowatts per cubic meter, kWh/mt = kilowatt-hours per metric ton, Mo = molybdenum

 

Due to the preliminary status of the test work and the composite nature of the samples tested, results from the most competent sample have been used as the basis for design. It has been assumed that this will provide a similar design point as the 80th percentile competency and ensure a robust design. This premise will need to be confirmed through additional testing using SPI tests on geometallurgical samples, and confirmed by SAGDesign testing of composite samples, in the next phase of study as more detailed mine schedule information and material comminution characteristics become available.

 

10.2.3.2Flotation Test Work Results

 

Flotation test work was completed prior to the commencement of the present study, beginning with rougher kinetic flotation testing and culminating with locked-cycle testing of the major material types. Only bulk sulfide flotation with multi-stage cleaning has been undertaken to produce a copper/molybdenum concentrate. No copper/molybdenum separation has been undertaken to date. (As noted in Section 10.1.5, copper/molybdenum separation testing was conducted by SGS in 2026.) Analysis of the test work has been used to develop the plant process design criteria and estimate concentrate grades and recovery for copper, molybdenum, and silver.

 

110
 

 

10.2.4Conceptual Study Flotation Test Work

 

The flotation test work program was divided into three phases: rougher flotation; open circuit cleaner flotation; and locked cycle flotation.

 

10.2.4.1Rougher Flotation

 

Initially, a series of rougher flotation tests were conducted to determine the sensitivity of the material types to grind size and reagent scheme. These tests were supplemented with mineralogical examination by QEM*SCAN (Quantitative Mineralogy by Scanning Electron Microscopy) to determine fundamental mineral liberation and speciation. These tests indicated the following:

 

●Copper mineralogy in the CuAg zone is fine grained and exhibited sensitivity to primary grind size, with highest recovery at a grind size of 80% passing 63 μm. Molybdenum and silver content exhibit little sensitivity to grind size.
   
●Target elements showed little sensitivity to grind size for the CuMo zone, with only a slight change in recovery between a grind size of 80% passing 106 and 63 μm for copper, molybdenum, and silver.
   
●The copper and silver minerals in the Mo zone exhibited significant sensitivity to grind size. Although the sensitivity of molybdenum was lower, the finer grind resulted in an increase in molybdenum recovery.

 

Sulfur assays on the concentrates from the CuAg zone and CuMo zone indicate the presence of a floatable sulfide gangue mineral; most likely pyrite (no sulfur assays were available for the Mo zone).

 

The results of these tests are summarized in Table 10-4.

 

Table 10-4 Baseline Flotation Results for CuMo Composite Samples

 

Mineral Zone Test No. Feed Concentrate Grade Concentrate Recovery
% Cu ppm Mo % Cu % Mo ppm Ag % Cu % Mo % Ag
CuAg VF1-1 0.16 213 1.22 0.18 39 76.5 87.7 78
VF1-2 0.16 179 1.71 0.27 53 58.7 81.6 70.3
CuMo VF2-1 0.12 435 2.11 0.79 42 89.7 92.4 74
VF2-2 0.11 398 1.54 0.61 36 89.3 92.9 74.5
Mo VF3-1 0.03 1135 0.47 1.99 13 77 94.4 64.4
VF3-2 0.03 1135 0.44 1.75 12 83.1 96.9 71.8

Note: The molybdenum grades are reported as elemental Mo, not MoS2. Ag = silver, Cu = copper, CuAg = copper-silver, CuMo = copper-molybdenum, ppm Ag = parts per million silver, ppm Mo = parts per million molybdenum

 

The test results indicate that the mineralization is amenable to flotation, resulting in good recovery of target mineral species into a low mass concentrate stream. The sensitivity of the mineralization to primary grind size indicates that a fine grind for all material types will be required to ensure effective recovery. Additional grind sensitivity test work should be included in subsequent testing to optimize the relationship between mineral recovery and grind size.

 

111
 

 

10.2.4.2Open Circuit Flotation

 

Cleaner flotation testing was conducted at the finer target primary grind size of 80% passing 63 μm and incorporated a rougher concentrate regrind stage to increase mineral liberation. Regrind times and reagent dosages were varied to determine optimum flotation conditions.

 

The cleaner flotation reagent scheme differed from that used in the rougher tests and included a molybdenum specific activator (moly oil) and a copper molybdenum specific collector (Aero 3302). Despite the presence of pyrite reporting to final concentrate, a non-specific sulfide collector (SIBX) was also used during the cleaner flotation testing.

 

The fine-grain nature of the mineralization identified by the QEM*SCAN testing, together with the improved rougher concentrate grade and recovery, indicated that regrinding of the rougher concentrates would be required to achieve adequate concentrate grades. Concentrate regrinding was therefore incorporated into all subsequent cleaner and locked cycle testing. The target regrind size was arbitrarily selected at 90-95% passing 20 μm and was achieved by grinding for a set period during each test. Multiple stages of cleaning were incorporated to target higher concentrate grades, typically with an elevated pH level during the final stage of cleaning. Results from selected optimization tests are summarized in Table 10-5.

 

Table 10-5 Cleaner Flotation Results for CuMo Composite Samples

 

Mineral Zone Test No. Feed Concentrate Grade Concentrate Recovery
% Cu ppm Mo % Cu % Mo ppm Ag % Cu % Mo % Ag
CuAg VF1-3 0.14 176 19.8 3.32 596 49.6 68.2 49
VF1-4 0.16 185 15.3 2.3 462 64 81.3 64.9
VF1-5 0.15 175 16.4 2.68 539 55.6 79 41.2
CuMo VF2-3 0.12 392 18 6.31 344 85.5 93.7 76.8
VF2-4 0.12 416 17.3 6.53 354 81.8 92.6 74.8
VF2-5 0.11 315 16.6 4.88 365 85.4 90.4 70.3
Mo VF3-3 0.03 1048 5.9 24.4 151 79.6 95.9 52.2
VF3-4 0.03 1025 6.1 24.8 150 79.8 95.8 50.7
VF3-5 0.03 958 5.7 21.3 168 79.8 95.3 56.2

Note: The molybdenum grades are reported as elemental Mo, not MoS2. Ag = silver, Cu = copper, CuAg = copper-silver, CuMo = copper-molybdenum, ppm Ag = parts per million silver, ppm Mo = parts per million molybdenum

 

The concentrate grades achieved in the majority of these tests indicate the presence of significant levels of diluents in the final concentrate. The absence of mineralogy or sulfur assays on the final concentrates makes it difficult to determine the nature of these diluents. However, the most likely explanation for this is the presence of floatable pyrite in the mineralization that has not been depressed during flotation and is reporting to the final concentrate. This issue will require further evaluation and testing during subsequent studies.

 

112
 

 

Following the completion of the open circuit cleaner flotation test work phase, a locked cycle test was conducted on each of the major material types. This phase was designed to evaluate the selected flowsheet conditions under locked cycle conditions and to determine the closed-circuit grade recovery performance of each material type for project evaluation.

 

10.2.4.3Locked Cycle Test Work at Design Conditions

 

Flotation results from the optimization test work highlighted the benefit of fine regrinding and multiple stages of concentrate cleaning on improving concentrate grade. A flowsheet incorporating rougher concentrate regrinding and multiple stages of cleaning, similar to that used in the open circuit cleaner testing was selected for the conceptual study. To evaluate the performance of the flow sheet across all material types, a series of locked cycle tests was conducted.

 

Locked cycle tests are used to determine the effects of recycling intermediate streams, such as scavenger concentrates, on the overall grade recovery performance of each material type. By retaining these streams and combining them with concentrates from a subsequent flotation test, the overall performance of a full-scale plant can be assessed.

 

Locked cycle tests were undertaken for the main mineralized zones, and the results are summarized in Table 10-6.

 

Table 10-6 Locked Cycle Test Results

 

Mineralized Zone Test No. Feed Concentrate Grade Concentrate Recovery
% Cu ppm Mo % Cu % Mo ppm Ag % Cu % Mo % Ag
CuAg VF1-LCT1 0.16 190 13 2 357 62.5 82 71.7
CuMo VF2-LCT1 0.12 401 16.4 5.66 324 90.7 93.8 80
Mo VF3-LCT1 0.04 1065 5.1 21.6 122 71.6 99.6 59.3

Note: The molybdenum grades are reported as elemental Mo, not MoS2. Ag = silver, Cu = copper, CuAg = copper-silver, CuMo = copper-molybdenum, ppm Ag = parts per million silver, ppm Mo = parts per million molybdenum

 

Analysis of these results indicates that recoveries of the target minerals are acceptable and are generally consistent with those achieved in the open circuit cleaner testing. However, the final concentrate grades remain lower than required to produce saleable concentrates after copper/molybdenum separation. Additional test work will be required to determine the nature of the concentrate diluents and identify methods to maximize their rejection while maintaining target recoveries.

 

10.2.4.4Tungsten Recovery

 

In 2009, SGS conducted a preliminary tungsten separation test on the rougher tailing of the lock cycle test of Composite 3. The test consisted of feeding the rougher tailings to a Falcon Concentrator whose concentrate was upgraded on a Mozley table. The test results are summarized in Table 10-7.

 

113
 

 

Table 10-7 Tungsten Recovery Test Results

 

Stream Wt% WO3%
Assay Distribution
Mozley Concentrate 0.04 4.61 26.34
Falcon Concentrate 2.85 0.093 40.55
Calculated Feed 100 0.003 100.00

Source: SGS (2009). Note. Wt% = weight percent, WO3 = tungsten trioxide

 

The sample used in the test, Composite 3, is from the Mo zone which has the lowest tungsten grade of the three zones. The average tungsten grade in the Mo zone is 21 ppm, compared with 34 ppm in the CuAg zone, and 41 ppm in the CuMo zone.

 

However, the SGS report states that, as before for the other two composites, the tungsten grades were too low to provide reliable assaying results.

 

Based on the SGS report, the possibility to recover tungsten in an economic process has not yet been established.

 

10.2.5Grade and Recovery Predictions

 

Analysis of the locked cycle tests has been undertaken to determine flotation performance predictions. The design recoveries of the target metals are generally in line with or slightly lower than those achieved in the locked cycle tests suggesting a degree of conservatism in the selected recoveries. The numbers were selected as generally being lower than the actual test work values with the exception of the CuAg zone, as this sample consisted of both oxidized and non-oxidized material.

 

A review of the specified recoveries indicates that they are reasonable for a bulk concentrate from the CuMo mineralized zones. However, the concentrate grades achieved directly from the current tests do not reflect those required to produce saleable concentrates and have been adjusted for the plant design and initial economic evaluation on the assumption that additional test work will confirm and further optimize flotation performance, allowing higher concentrate grades to be achieved with minimal impact on recovery.

 

The SGS (2009) report provides the following conclusions regarding the production of saleable concentrates:

 

●In the case of the CuAg zone sample: “However, the upgrading ratios indicate that a saleable grade of Cu concentrate can be made from this composite.” (page 6)
   
●In the case of the CuMo zone sample: “The upgrading ratios assured that saleable Cu and Mo concentrates can be made by added cleaning stages.” (page 7)
   
●And finally in the case of the Mo zone sample: “The upgrading ratios indicate that Cu and Mo concentrates of saleable grades can be made by added cleaning stages.” (page 8)

 

These assertions support the general assumptions with respect to concentrate grades and process design details and should be further evaluated during future advanced level studies are done on the project in the future.

 

114
 

 

To develop a process design and estimate capital and operating costs, it has been assumed that a selective molybdenum flotation phase with copper depression, followed by a ferric chloride leaching of the molybdenum concentrate to remove residual copper, will be required. The design and grade recovery performance of these process units have been estimated from operating and test work data from similar studies and operating plants. These include operating mines such as Las Pelambres, Andina, Collahuasi, Gibraltar, and Sierrita, as well as development projects evaluated in 2009 such as Pebble, Prosperity, and Mirador. All these have or have examined copper-molybdenum separation circuits.

 

The recoveries of target metals into their respective concentrates have been reduced to reflect metal misreporting during the separation stages. The final concentrator recoveries that have been assumed for the IA of CuMo are shown in Table 10-8. These figures include bulk concentrate recovery, copper/molybdenum flotation separation, and ferric chloride leach recovery.

 

Table 10-8 Grade/Recovery Predictions for CuMo

 

Material Type Concentrate Concentrate Grade Concentrate Recovery
% Cu % Mo % Cu % Mo % Ag
CuAg Molybdenum 0.1 52 0.02 83  
Copper 19 0.1 64 2.4 70
CuMo Molybdenum 0.1 51 0.04 92  
Copper 22 0.1 85 0.7 78
Mo Molybdenum 0.02 49 0.1 95  
Copper 20 0.8 72 1 55

Note. Ag = silver, Cu = copper, CuAg = copper-silver, CuMo = copper-molybdenum, Mo = molybdenum

 

Note that the recovery predictions shown in Table 10-8 for CuAg zone material were based on samples that also contained oxide material. Segregation of this oxide material results in the adjusted and slightly higher recovery predictions for non-oxide material referenced elsewhere in this report (Table 11-14).

 

In addition to the primary elements listed, the study also analyzed the final concentrate from the lock cycle tests for gallium, osmium and rhenium, while the rougher tails were analyzed for gallium. Rhenium was the only metal present in quantities above detection limit returning values of 0.9 ppm, 2.9 ppm, and 15 ppm respectively in the molybdenum concentrates from the three material types.

 

SGS’s 2008 locked-cycle tests measured rhenium contents of 0.9, 2.9 and 15.0 g/t in the cycle-C third-cleaner concentrates from the CuAg, CuMo and Mo composites, respectively. The corresponding molybdenum grades were 2.05%, 5.72% and 21.0%. These intermediate concentrates had not been upgraded to the assumed saleable molybdenum concentrate grade.

 

Extrapolating the paired assays to 55% Mo gives calculated rhenium grades of approximately 24.1, 27.9 and 39.3 ppm, assuming that the tested rhenium-to-molybdenum ratios are retained during subsequent separation and cleaning. These are calculated projections rather than measured final-product grades. Holmgren and Giroux (2009) previously interpreted the test results as supporting 30–40 ppm Re at 50% Mo and recommended 35 ppm for initial economic evaluation.

 

The current assessment adopts 25 ppm Re in molybdenum concentrate from the 25–30 ppm range recorded in the March 2025 initial mine-plan assumptions. This value is near the lower end of the historical test-based extrapolations. Further testwork is recommended to verify rhenium partitioning and the grade of the final molybdenum concentrate.

 

115
 

 

No test work was completed to determine the actual recovery of rhenium and sulfuric acid during the roasting process, though there are no indications that it cannot be achieved based on current technology and existing roasters. This test work is recommended for the next stage of development for this project.

 

10.3Application of Ore Mineral Sorting

 

The objective of ore sorting is to reject the below cut-off grade material entering the mill and reduce the mill throughput and increase the mill feed grade. Since the CuMo project is a high throughput low grade copper-molybdenum deposit, the ore sorting assessment considers bulk sorting methods such as shovel sorting at the mining face and two staged belt sorting after primary crushing.

 

This section will highlight the key findings of the analysis which includes the reclassification of the block model into three categories: mill feed, stockpile, and waste material. It also includes the metal recovery for each category (Lycopodium, 2025). Barr’s process QP reviewed the information and methodology provided by Lycopodium for the development of the ore-sorting response and inclusion in the crusher circuit and process plant concept for the current IA.

 

10.3.1Reference Data

 

The analysis considered two data sets:

 

●Drill core XRF Scanned data from Veracio
   
●Block model from SGS

 

The primary source of data that was utilized for the analysis was a dataset of XRF scans. The data set contained 410,163 rows of data excluding oxide and Dyke zones. There are 24 drillholes that were considered. Each data point in the dataset contains an XRF scan spanning 0.05 ft, collecting the copper and molybdenum grade, the position of the XRF scan, and the calculated recoverable value (RCV). For the purpose of the analysis, only the CuMo, Mo, and CuAg zones were considered, where data in the MSI zone were classified as Mo, and the oxide zone was classified as CuAg.

 

At each stage of sorting, the dataset is split into three categories of material. Material sent to the mill contained an RCV value of >$30, the stockpile containing >$5 and <$30, and lastly the waste containing <$5. Upon completion of this analysis, a distribution of the results was created and was applied to the block model file to gain an accurate representation of the accepts, stockpiles, and waste for each material.

 

10.3.2Methodology of Sorting

 

10.3.2.1Background

 

The analysis includes three stages of sorting. The first stage of sorting is done at the shovel, separating every bucket of material scooped. The accepted material from the first stage is sent to the primary crusher for size reduction before feeding the second stage sorter. The primary crushed product feeds the second stage sorter on the conveyor belt, separating the material into three groups: mill feed, stockpile, and waste. The stockpile from the second stage is sent to the third stage belt sorter for final separation. The product identified as mill feed from each stage is combined and sent to the mill. The reject from each stage is combined and sent to the waste rock stockpile. The stockpile from the third stage of sorting is stockpiled separately and assessed for further processing in the mill or rejected as waste. This decision in the current analysis is pending as the exact cut-off will be determined after whittle analysis. An overview of the flowsheet is shown Figure 10-1.

 

116
 

 

The XRF dataset is analyzed using various python scripts to handle the larger data sets. Three separate analyses were conducted. The analyses are as follows.

 

●Shovel bucket: 85 tonnes of material
   
●Second stage belt scan: 10 tonnes of material
   
●Third stage belt scan: 5 tonnes of material

 

The primary variable used for analysis is the RCV, which represents the monetary value of the copper and molybdenum concentration found in each data point. The RCV value can be calculated using the following equation.

 

RCV = (CuPerc * 20 * CuPrice * CuRecovery) + (MoPerc * 20 *MoPrice *MoRecovery)

 

Where CuPerc, MoPerc are percent grade of Cu and Mo, CuPrice and MoPrice representing the unit price of Cu and Mo, and CuRecovery and Mo Recovery representing recovery factors from metallurgical test work.

 

 

Source: Lycopodium (2024)

Figure 10-1 Flowchart for Sorting Process

 

117
 

 

10.3.2.2First Stage Sorting

 

For each stage, the RCV value is averaged based on the number of data points required to represent the given tonnage. For instance, the first stage of shovel buckets with 85 tonnes, the number of data points to represent 85 t was determined through utilizing the ratios of the weight of a 50 ft composite and a shovel bucket. A 50 ft composite represented by 50 ft of data within the XRF dataset is estimated to weigh 10,064 tonnes of material. The equation below identifies the number of data points required per shovel bucket.

 

10064 m𝑡/85 m𝑡 𝑏𝑢𝑐𝑘𝑒𝑡= 118.4 𝑏𝑢𝑐𝑘𝑒𝑡𝑠

 

This indicates that for every 50 ft of data, there are 118 buckets of material available. The data is split into 118 buckets for a full 50 ft set of data, where the RCV value is recalculated for a given bucket. It is important to note that there are instances within the XRF data set where the 50 ft of data did not contain 118 buckets worth of data. In these scenarios, “missing” buckets were disregarded. Another analysis was completed in a scenario where the missing buckets were counted as waste.

 

Upon recalculation of the RCV values per bucket size, the RCV values were categorized into bins for further analysis. The bins started at $0 to $2.50 and increased in increments of $2.50. Using the frequency of these bins, the proportion of material sent to the mill, stockpile, and waste was determined.

 

10.3.2.3Second Stage Sorting

 

The buckets containing an RCV value of $5 or higher were sent to the second stage sort. These buckets were reverted to the original XRF data that were contained within each bucket, identified by the position of the XRF scan. The data set was grouped into 10 tonnes of materials and analyzed similar to the first stage sorting. Ten tonnes of material is represented by two XRF scan points.

 

10.3.2.4Third Stage Sorting

 

The third stage of sorting represents belt scans of 5 tonnes of material. The data from the second sort that contained an RCV value in the stockpile range was used as the input for the third stage of sorting. Five tonnes of material is represented by a single XRF scan point.

 

10.3.2.5Alternative Analysis

 

An alternative to the 85-tonne shovel bucket analysis for the first stage was conducted where 255 tonnes of material representing a haul truck was used. The same logic and analysis from previous stages of sorting were applied. The analysis was repeated for the first and third stages of sorting using a $25 RCV cut off. This analysis has not been considered in the results presented however may be explored further.

 

10.3.2.6Distribution and Block Model Application

 

Upon completion of the analysis, a distribution of the sorted dataset was created. The distribution was separated by zone and RCV bin. RCV bins of 0-2.5, 2.5 - 7.5, 7.5-15, 15-22.5, 22.5-30, 30-50, and >50 was created to further categorize the available data. By sorting the results of each sort into these RCV bins, and categorizing by zone, the frequency of each combination of RCV and zone were calculated which was then used to calculate the proportion or % of mill, stockpile, and waste. These are shown in Table 10-9.

 

118
 

 

The distribution was adjusted to account for the three-step sorting process that includes total mill accounting for steps 2 and 3 mill, waste being the sum of all three steps, and stockpile from step 3. By applying these percentages to the block model, the results will be representative of the three-stage process.

 

Table 10-9 Distribution of Sorted Data into RCV Bins

 

Bin Start Bin End Zone Rejects W% Rejects Cu% Rejects Mo% Stockpile W% Stockpile Cu% Stockpile Mo% Accepts W% Accepts Cu% Accepts Mo%
0 2.5 CuAg 99 100 90 1 1 10 0 0 0
2.5 7.5 CuAg 85 57 51 14 40 32 1 3 17
7.5 15 CuAg 63 35 27 35 57 48 3 9 26
15 22.5 CuAg 33 14 9 61 69 57 6 18 35
22.5 30 CuAg 38 22 7 53 63 44 9 15 50

Note. Cu = copper, CuAg = copper-silver, Mo = molybdenum, W = tungsten

 

To apply the distribution to the blocks in the block model, each block would need to be categorized into the proper row of the distribution table to apply the appropriate percentage. The RCV of the specific block is used to identify the bin range, along with the zone. The Reject W, Stockpile W, and Accepts W% is applied to the ‘ZTons’, while the corresponding Cu%, Mo% are applied to Cu lb and Mo lb, Cu% were applied to the Ag gm.

 

10.3.3Results

 

Various tables and figures have been created to summarize the results of each step of the analysis. This includes the flow chart representing the steps of the sorting process, the distribution table for the sorting process, the % application table, and the results.

 

Based on SGS’s block model, the total material available is 3 billion tonnes which we have assessed for sorting application and produced the outcomes below in Table 10-10.

 

Table 10-10 Metal Distribution of Model

 

Metal Distribution
Metal Total Waste Stockpile Mill
Cu (lb) 4,342,406,352 964,398,141 22% 2,833,811,708 65% 544,196,504 13%
Mo (lb) 1,779,372,914 157,226,158 9% 785,884,312 44% 836,262,445 47%
Ag (g) 7,198,729,300 1,673,744,776 23% 4,619,801,148 64% 905,183,376 13%

Note. Ag = silver, Cu = copper, g = gram, lb = pound, Mo = molybdenum

 

The following three tables, Table 10-11, Table 10-12, and Table 10-13, are the distribution tables for sort 1, 2, and 3. Columns with W represent waste, S represents stockpile, and Mill representing the accept feed sent to the mill.

 

119
 

 

Table 10-11 First Stage Sort Distribution Table

 

 

Source: Lycopodium (2024)

 

Note. CuAg = copper-silver, CuMo = copper-molybdenum, Mill = the accept feed sent to the mill, Mo = molybdenum, MSI = potassic-silica alteration zone with lower-grade Cu-Mo mineralization, S = stockpile, W = waste

 

120
 

 

Table 10-12 Second Stage Sort Distribution Table

 

 

Source: Lycopodium (2024)

 

Note. CuAg = copper-silver, CuMo = copper-molybdenum, Mill = the accept feed sent to the mill, Mo = molybdenum, MSI = potassic-silica alteration zone with lower-grade Cu-Mo mineralization, S = stockpile, W = waste

 

121
 

 

Table 10-13 Third Stage Sort Distribution Table

 

 

Source: Lycopodium (2024)

 

Note. CuAg = copper-silver, CuMo = copper-molybdenum, Mill = the accept feed sent to the mill, Mo = molybdenum, MSI = potassic-silica alteration zone with lower-grade Cu-Mo mineralization, S = stockpile, W = waste

 

Table 10-14 summarizes the % applied to the block model. The % seen below have been recalibrated using the distribution table to account for the sorting process. For instance, the ‘Reject W %’ is a combination of the waste material from sorting stages 1, 2, and 3.

 

122
 

 

Table 10-14 Summary of % Applied to Block Model

 

 

Source: Lycopodium (2024)

 

Note. CuAg = copper-silver, CuMo = copper-molybdenum, Mill = the accept feed sent to the mill, Mo = molybdenum, MSI = potassic-silica alteration zone with lower-grade Cu-Mo mineralization, S = stockpile, W = waste

 

123
 

 

11 Mineral Resource Estimates

 

11.1Introduction

 

The mineral resource estimate for the CuMo project was previously prepared by Gary Giroux, P.Eng., and reported in the 2020 NI 43-101 Technical Report and Preliminary Economic Assessment for the CuMo Project. The current report does not include a re-estimation or material revision of the mineral resource estimate. The effective date for this Mineral Resource Estimate remains August 30, 2018.

 

The 2020 CuMo resource estimate represents an update of the 2012 estimate by Snowden Mining Industry Consultants (Jones, et al) and the 2009 resource estimate (Holmgren and Giroux), based on an additional 11 new diamond drill holes completed in 2011-2012.

 

The authors have reviewed the available mineral resource estimate, its supporting technical documentation, the drill-hole database used in the estimate, the associated geological and mineralization interpretations, and the resource classification methodology. Based on this review, and subject to the limitations discussed in this report, the mineral resource estimate is considered suitable for use as the basis for the updated IA-level assessment.

 

The QP responsible for this chapter has not re-estimated the mineral resource and has not made any significant revision to it. No material new drilling, sampling, geological information, or other technical information that would require revision of the mineral resource estimate has been identified. The Cu-Mo-Ag-W resource was estimated in April 2015, the effective date for this estimate is August 30, 2018, when estimates for Re and S were completed. Accordingly, the mineral resource estimate previously reported remains unchanged and is reproduced in this report for reference and as the basis for the current economic assessment.

 

The previous technical report that described in detail the data analysis, geological modelling, compositing, variography, block modelling, grade interpolation, density assignment, reasonable prospects for eventual economic extraction, resource classification, and reporting assumptions used in the mineral resource estimate is summarized in this report.

 

Relevant factors that could influence the resource estimate include future updates to the geological, geotechnical or geometallurgical models, infill drilling to convert Mineral Resources to a higher classification, drilling to test extensions to known resources, collection of additional bulk density data and significant changes to commodity prices. It should be noted that all these factors pose potential risk and opportunities to the current mineral resource.

 

11.2Data Analysis

 

A total of 65 DDHs and three RC drill holes, over a combined total of 121,280 ft, were provided with 1,001 downhole surveys and 10,456 assays for Mo and Cu. For this resource estimation, the three RC holes were not used leaving only the 65 DDHs as being used. For the 65 DDHs used, the total length was 36,166 m (118,654 ft)

 

The provided data was checked for sample overlaps, gaps in sample intervals and assays within allowable intervals. No errors were found

 

The basic assay statistics for DDHs are presented below in Table 11-1.

 

124
 

 

Table 11-1 Summary of MoS2 and Cu Contents

 

Statistic Parameter MoS2 (%) Cu (%)
Number 10,456 10,456
Mean 0.053 0.077
Standard Deviation 0.058 0.069
Minimum 0.0005 0.001
Maximum 1.09 0.920
Coefficient of Variation 1.09 0.89

Note: MoS2 here is calculated from the assays for Mo by multiplying by 1.6681. Cu = copper, MoS2 = molybdenite

 

The molybdenum and copper mineralization at CuMo lies in four distinct mineral zones with an oxidized layer on top. More or less from top to bottom there occurs in most drill holes an oxide zone, a Cu-Ag zone, a Cu-Mo zone and a Mo zone. Within one fault block, the Cu-Ag zone is missing, and the oxide sits on top of the Cu-Mo zone. These zones are underlain by a potassic-silica zone with lower grade copper and molybdenum material called the MSI zone. While the oxide zone has been modeled for metallurgical reasons, it has been combined with the Cu-Ag zone or in a few cases the Cu-Mo zone for estimation purposes. While no test-work has been completed on the oxide zone at this time, experience with other such deposits indicates that metal recoveries tend to be lower in oxidized zones as compared to primary zones and as a result it was modelled separately, and a lower recovery was applied. This is a conservative approach and will be useful for future work.

 

Contact plots for each variable in shown Figure 11-1 there is no difference in average grade across the oxide – Cu-Ag zone contact. There are also several post mineral dykes that are large enough and continuous enough to be modeled. The Cu and MoS2 grade statistics are shown in Table 11-2, sorted by zone. Silver and tungsten assays are shown in Table 11-3 for the same mineral zones. Values for MoS2 and Cu reported as 0.000 were assigned values of 0.0005% and 0.001%, respectively. Silver values reported as 0.000 were set to 0.01 ppm while tungsten values reported as 0.000 were set to 0.1 ppm.

 

Table 11-2 Summary of Assay Statistics for Cu And MoS2 Sorted by Zone

 

Statistical Parameter Cu–Ag Zone Cu-Mo Zone Mo Zone MSI Zone Dykes
MoS2 (%)

Cu

(%)

MoS2 (%)

Cu

(%)

MoS2 (%)

Cu

(%)

MoS2 (%)

Cu

(%)

MoS2 (%)

Cu

(%)

Number 3,813 3,813 3,509 3,509 2,677 2,677 330 330 128 128
Mean 0.017 0.076 0.049 0.103 0.113 0.053 0.057 0.028 0.005 0.016
Standard Deviation 0.019 0.074 0.045 0.072 0.066 0.042 0.029 0.038 0.014 0.038
Minimum 0.0005 0.001 0.0005 0.001 0.0005 0.001 0.0010 0.001 0.0005 0.001
Maximum 0.315 0.77 1.09 0.92 0.99 0.59 0.17 0.20 0.13 0.18
Coefficient of Variation 1.15 0.97 0.92 0.70 0.58 0.80 0.51 1.34 2.62 2.36

Note: MoS2 here is calculated from the assays for Mo by multiplying by 1.6681. Cu-Ag = copper-silver, Cu-Mo = copper-molybdenum, MoS2 = molybdenite

 

125
 

 

 

Source: CuMoCo (2015)

 

Figure 11-1 Contact Plots for Oxide-Cu-Ag Zone Contact

 

126
 

 

Table 11-3 Summary of Assay Statistics for Ag and W Sorted by Zone

 

Statistical Parameter Cu–Ag Zone Cu-Mo Zone Mo Zone MSI Zone Dykes
Ag (ppm)

W

(ppm)

Ag (ppm)

W

(ppm)

Ag (ppm)

W

(ppm)

Ag (ppm)

W

(ppm)

Ag (ppm)

W

(ppm)

Number 3,806 3,791 3,492 3,497 2,653 2,654 327 330 128 121
Mean 2.88 32.3 3.07 46.7 1.78 45.9 1.65 37.1 0.62 9.8
Standard Deviation 16.28 108.9 13.35 33.8 9.81 38.3 10.39 109.3 1.23 11.9
Minimum 0.01 0.1 0.01 0.1 0.01 0.1 0.01 3.3 0.01 0.1
Maximum 838.0 5400 744.0 470.0 494.0 890.0 182.0 1980 8.6 65.0
Coefficient of Variation 5.65 3.37 4.35 0.72 5.51 0.83 6.28 2.95 1.99 1.21

Note. Ag = silver, Cu-Ag = copper-silver, Cu-Mo = copper-molybdenum, ppm = parts per million, W = tungsten

 

Capping levels were set to minimize the effects of a small number of erratic outliers.

 

A similar strategy was applied to Cu, Ag, and W. The capping levels for each variable are shown in Table 11-4, Table 11-5, and Table 11-6.

 

Table 11-4 Summary of Capping Levels by Mineralized Zone

 

Domain Variable Cap Level Number Capped
Cu-Ag Zone MoS2 0.16 % 4
Cu-Mo Zone MoS2 0.40 % 2
Mo Zone MoS2 0.48 % 7
MSI Zone MoS2   0
Dykes MoS2 0.05 % 1
Cu-Ag Zone Cu 0.83 % 0
Cu-Mo Zone Cu 0.62 % 4
Mo Zone Cu 0.27 % 6
MSI Zone Cu   0
Dykes Cu 0.15 % 3
Cu-Ag Zone Ag 115 ppm 6
Cu-Mo Zone Ag 102 ppm 4
Mo Zone Ag 24 ppm 4
MSI Zone Ag 8 ppm 3
Dykes Ag 4.0 ppm 3
Cu-Ag Zone W 452 ppm 5
Cu-Mo Zone W 277 ppm 6

 

127
 

 

Domain Variable Cap Level Number Capped
Mo Zone W 275 ppm 6
MSI Zone W 118 ppm 3
Dykes W   0

Note. Cu-Ag = copper-silver, Cu-Mo = copper-molybdenum, ft = feet, Mo = molybdenum, MoS2 = molybdenite, MSI = potassic-silica alteration zone with lower-grade Cu-Mo mineralization, W = tungsten

 

The results from capping are tabulated below with some significant reductions in the coefficient of variation for some variables.

 

Table 11-5 Summary of Capped Assay Statistics for Cu and MoS2 Sorted by Zone

 

Statistical Parameter Cu–Ag Zone Cu-Mo Zone Mo Zone MSI Zone Dykes
MoS2 (%)

Cu

(%)

MoS2 (%)

Cu

(%)

MoS2 (%)

Cu

(%)

MoS2 (%)

Cu

(%)

MoS2 (%)

Cu

(%)

Number 3,813 3,813 3,509 3,509 2,677 2,677 330 330 128 128
Mean 0.017 0.076 0.049 0.103 0.112 0.053 0.057 0.028 0.005 0.016
Standard Deviation 0.018 0.074 0.040 0.070 0.063 0.041 0.029 0.038 0.009 0.036
Minimum 0.0005 0.001 0.0005 0.001 0.0005 0.001 0.0010 0.001 0.0005 0.001
Maximum 0.16 0.77 0.40 0.62 0.48 0.27 0.17 0.20 0.05 0.15
Coefficient of Variation 1.10 0.97 0.83 0.68 0.56 0.78 0.51 1.34 2.04 2.31

Note: MoS2 here is calculated from the assays for Mo by multiplying by 1.6681. Cu = copper, Cu-Ag = copper-silver, Cu-Mo = copper-molybdenum, MoS2 = molybdenite

 

Table 11-6 Summary of Capped Assay Statistics for Ag and W Sorted by Zone

 

Statistical Parameter Cu–Ag Zone Cu-Mo Zone Mo Zone MSI Zone Dykes
Ag (ppm)

W

(ppm)

Ag (ppm)

W

(ppm)

Ag (ppm)

W

(ppm)

Ag (ppm)

W

(ppm)

Ag (ppm)

W

(ppm)

Number 3,806 3,791 3,492 3,497 2,653 2,654 327 330 128 121
Mean 2.56 29.8 2.88 46.4 1.58 45.5 0.99 31.3 0.57 9.8
Standard Deviation 5.82 32.4 4.63 31.7 1.78 32.8 1.28 20.7 1.00 11.9
Minimum 0.01 0.1 0.01 0.1 0.01 0.1 0.01 3.3 0.01 0.1
Maximum 115.0 452.0 102.0 277.0 24.0 275.0 8.0 118.0 4.00 65.0
Coefficient of Variation 2.27 1.09 1.61 0.68 1.13 0.72 1.29 0.66 1.75 1.21

Note. Ag = silver, Cu = copper, Cu-Ag = copper-silver, Cu-Mo = copper-molybdenum, Mo = molybdenum, MoS2 = molybdenite, MSI = potassic-silica alteration zone with lower-grade Cu-Mo mineralization, ppm = parts per million, W = tungsten.

 

128
 

 

11.350-Foot Composites

 

The bulk of the historic drill holes (1969 to 1982) were assayed on 10 ft or 20 ft intervals while those assayed by CuMoCo (2006-2012) were assayed on 10 ft intervals. A 50 ft composite length was chosen to match a reasonable mining bench for this scale of deposit. This differs from the 2012 resource estimate where a 20 ft composite was used. The statistics for 50 ft composites are shown in Table 11-7. Samples coded as oxide were combined with Cu-Ag composites for estimation purposes.

 

Table 11-7 Summary of 50 Ft Composite Statistics

 

Statistical Parameters MoS2 (%) Cu (%) Ag (ppm) W (ppm)
Cu-Ag Zone
Number 810 810 810 807
Mean 0.016 0.076 2.68 29.8
Standard Deviation 0.013 0.062 4.77 28.1
Minimum 0.001 0.001 0.01 0.1
Maximum 0.101 0.432 92.39 365.1
Coefficient of Variation 0.80 0.82 1.78 0.94
Cu-Mo Zone
Number 813 813 808 810
Mean 0.048 0.103 2.88 45.8
Standard Deviation 0.027 0.057 2.81 23.4
Minimum 0.003 0.003 0.22 5.4
Maximum 0.226 0.366 42.50 190.6
Coefficient of Variation 0.56 0.55 0.98 0.51
Mo Zone
Number 639 639 631 631
Mean 0.112 0.053 1.64 46.7
Standard Deviation 0.046 0.037 1.27 24.1
Minimum 0.016 0.003 0.09 10.0
Maximum 0.302 0.218 10.68 160.0
Coefficient of Variation 0.41 0.69 0.77 0.52
MSI Zone
Number 81 81 80 81
Mean 0.056 0.027 1.04 31.8
Standard Deviation 0.023 0.037 1.08 16.7
Minimum 0.003 0.002 0.05 6.4
Maximum 0.104 0.150 5.00 101.7
Coefficient of Variation 0.42 1.35 1.04 0.53

 

129
 

 

Statistical Parameters MoS2 (%) Cu (%) Ag (ppm) W (ppm)
Dykes
Number 37 37 37 35
Mean 0.004 0.014 0.55 10.5
Standard Deviation 0.005 0.026 0.80 12.1
Minimum 0.001 0.001 0.01 1.5
Maximum 0.019 0.082 3.00 60.0
Coefficient of Variation 1.40 1.90 1.46 1.16

Note: %MoS2 statistics here are derived from assay grades calculated by multiplying %Mo by 1.6681. Ag = silver, Cu = copper, Cu-Ag = copper-silver, Cu-Mo = copper-molybdenum, Mo = molybdenum, MoS2 = molybdenite, MSI = potassic-silica alteration zone with lower-grade Cu-Mo mineralization, ppm = parts per million, W = tungsten

 

11.4Variography

 

For variogram analysis, the composite data was adjusted to accommodate post mineral faulting. Fault blocks were moved back to pre-fault locations based on marker beds displaced across fault boundaries. Semi-variograms were produced using these pre-fault locations. For estimation, the original locations of composites were used.

 

Pairwise, relative semi-variograms were used to determine grade continuity for MoS2, Cu, Ag, and W in 50 ft composites. Nested spherical models were fit to all directions with the model parameters tabulated below in Table 11-8.

 

Table 11-8 Parameters for Semi-Variogram Models at CuMo

 

Variable Domains Direction C0 C1 C2 Short Range (ft) Long Range (ft)
MoS2

Cu-Mo and

Mo Zone

Az 60 Dip 0 0.06 0.12 0.12 200 1800
Az 330 Dip -35 400 500
Az 150 Dip -55 300 1300
Cu-Ag Zone Az 0 Dip 0 0.16 0.16 0.20 200 1200
Az 270 Dip 0 200 400
Az 0 Dip -90 400 800
Cu

Cu-Ag and

Cu-Mo Zone

Az 60 Dip 0 0.08 0.08 0.10 250 1600
Az 330 Dip -35 500 700
Az 150 Dip -55 300 1600
Mo Zone Az 60 Dip 0 0.05 0.15 0.15 400 1200
Az 330 Dip 0 300 400
Az 0 Dip -90 300 500

 

130
 

 

Variable Domains Direction C0 C1 C2 Short Range (ft) Long Range (ft)
Ag

Cu-Ag and

Cu-Mo Zone

Az 70 Dip 0 0.12 0.05 0.09 200 1000
Az 340 Dip 0 50 200
Az 0 Dip -90 120 500
Mo Zone Az 60 Dip 0 0.06 0.15 0.14 300 1200
Az 330 Dip 0 300 500
Az 0 Dip -90 450 700
W

Cu-Mo and

Mo Zone

Az 0 Dip 0 .06 .02 0.15 150 1000
Az 270 Dip 0 50 500
Az 0 Dip -90 100 800
Cu-Ag Zone Az 30 Dip 0 0.08 0.11 0.17 160 1100
Az 300 Dip 0 200 1200
Az 0 Dip -90 300 400

Note. Ag = silver, Az = Azimuth, Cu = copper, Cu-Ag = copper-silver, Cu-Mo = copper-molybdenum, ft = feet, Mo = molybdenum, MoS2 = molybdenite, W = tungsten

 

There were insufficient composites within the MSI zone to model so the models for the Mo zone were applied to estimate this zone.

 

11.5Block Model and Grade Estimation

 

A block model with blocks of 50 ft x 50 ft x 50 ft in dimension was superimposed over the mineralized zones with the proportion of each block below surface topography and within the various mineralized solids recorded. The block model origin is as follows in Table 11-9:

 

Table 11-9 Block Model Dimensions and Configuration

 

Parameter Value
Left Lower Corner
Easting 214,600 E
Northing 114,250 N
Top of Model
Elevation 7075
Block Dimensions
Column Size 50 ft
Number of Columns 207
Row Size 50 ft
Number of Rows 179
Level Size 50 ft
Number of Levels 76

 

131
 

 

The grades for the four variables namely: MoS2, Cu, Ag, and W were interpolated into each block containing some proportion of mineralized solid by ordinary kriging. Kriging was completed for each variable separately within two mineralized zones. A combination of soft and hard boundaries was used to estimate MoS2, Cu, Ag, and W to reflect the metal zonation present at the CuMo deposit. The information used to boundary the estimation is summarized in Table 11-10.

 

Table 11-10 Estimation Boundary Summary

 

Mineral / Metal Estimation Boundary Information
MoS2 Estimated for Cu-Ag zone using only composites from Cu-Ag and oxide zones
Estimated for Cu-Mo and Mo zones using only composites from Cu-Mo and Mo zones
Cu Estimated for Mo Zone using only composites from Mo zone
Estimated for Cu-Ag and Cu-Mo Zones using only composites from Cu-Ag, CuMo and oxide zones
Ag Estimated for Mo zone using only composites from Mo zone
Estimated for Cu-Ag and Cu-Mo zone using only composites from Cu-Ag, CuMo and Oxide zone
W Estimated for Cu-Ag zone using only composites from Cu-Ag and Oxide zones
Estimated for Cu-Mo and Mo zones using only composites from Cu-Mo and Mo zones

Note. Ag = silver, Cu = copper, Cu-Ag = copper-silver, Cu-Mo = copper-molybdenum, Mo = molybdenum, MoS2 = molybdenite, W = tungsten.

 

Each kriging run was composed of four passes. The dimensions for the search ellipse, within each pass, were a function of the semi-variogram ranges.

 

Pass 1 required a minimum of four composites within a search ellipsoid with dimensions equal to one quarter of the semi-variogram range for each direction. For blocks not estimated, the search ellipse was expanded to half the semi-variogram range in Pass 2 and again a minimum of four composites were required to estimate the block. Pass 3 expanded the search ellipse to the entire range, and a final fourth pass used double the range. In all cases, the maximum number of composites from a single hole was set to three to ensure that a minimum of two drill holes were used in each estimate. The maximum number of composites used was set to 16, and if more than 16 composites were found, the closest 16 were used. The search parameters for each run are listed below in Table 11-11. Pass 4 for Ag and W used larger search ellipses to produce a value for all blocks estimated for MoS2 and Cu. This was due to the under-sampling of Ag and W relative to Mo and Cu.

 

A grade for each of the four variables was estimated in a total of 734,490 blocks.

 

Table 11-11 Summary of Kriging Search Parameters for Each Mineralized Zone

 

Domain Variable Pass Number of Blocks Estimated Az/Dip

Distance

(ft)

Az/Dip

Distance

(ft)

Az/Dip Distance (ft)
Cu-Ag MoS2 1 4,614 0 /0 300 270 / 0 100 0 / -90 200
2 26,207 600 200 400
3 83,342 1,200 400 800
4 252,646 2,400 800 1,600

 

132
 

 

Domain Variable Pass Number of Blocks Estimated Az/Dip

Distance

(ft)

Az/Dip

Distance

(ft)

Az/Dip Distance (ft)
Cu-Mo & Mo MoS2 1 35,447 60 / 0 450

150 / -

55

325

330 / -

35

125
2 110,887 900 650 250
3 121,147 1,800 1,300 500
4 59,784 3,600 2,600 1,000
Cu-Ag & Cu-Mo Cu 1 50,852 60 / 0 400

150 / -

55

175

330 / -

35

400
2 128,958 800 350 800
3 235,739 1,600 700 1,600
4 139,891 3,200 1,400 3,200
Mo Cu 1 1,789   300   100   125
2 22,307 60 / 0 600 330 / 0 200 0 / -90 250
3 58,857   1,200   400   500
4 80,068   2,400   800   1,000
Cu-Ag & Cu-Mo Ag 1 1,859   250   50   125
2 18,305 70 / 0 500 340 / 0 100 0 / -90 250
3 94,108   1,000   200   500
4 441,174   2000   400   1,000
Mo Ag 1 3,067   300   125   175
2 31,146   600   250   350
3 63,317 60 / 0 1,200 330 / 0 500 0 / -90 700
4 65,491   2,400   1,000   1,400
Cu-Ag W 1 14,288   275   300   100
2 51,953 30 / 0 550 300 / 0 600 0 / -90 200
3 122,565   1,100   1,200   400
4 179,224   2,200   2,400   800
Cu-Mo & Mo W 1 4,799   250   125   200
2 59,057 0 / 0 500 270 / 0 250 0 / -90 400
3 130,570   1,000   500   800
4 144,312   2000   1,000   1,600

 

Note: Distances shown in the table represent one quarter (Pass 1), one half (Pass 2), full (Pass 3) and twice (Pass 4) the semi variogram range in the three principal directions. Ag = silver, Az = Azimuth, Cu = copper, Cu-Ag = copper-silver, Cu-Mo = copper-molybdenum, ft = feet, Mo = molybdenum, MoS2 = molybdenite, W = tungsten

 

Rhenium and sulfuric acid are credits received by the project during the roasting process to be paid for at a third party roaster. Rhenium and sulfuric acid are contained solely within the molybdenite (MoS2) – rhenium as an impurity within the molybdenite (MoS2) structure, and sulfuric acid is produced from sulfur when the MoS2 is converted to MoO3. Due to the irregular nature of impurities and the sulfur content within the molybdenum, these cannot be estimated in blocks by kriging. Instead, statistical linear regressions were applied to 7,485 analyses related to rhenium content in the molybdenite (MoS2) within the various geological domains (mineralized zones) to determine the actual amount of these products produced. The results of statistical linear regression are lower and more conservative than the rhenium recovery reported by SGS (2009).

 

133
 

 

Scatter plots were produced for each mineralized zone, plotting Re and S against MoS2, and from these, a linear regression equation was used to estimate the amount of Re (ppm) and S (%) present on a block-by-block basis (see Figure 11-2 for an example plot showing Re versus MoS2 in Cu-Mo zone).

 

 

Source: Giroux et al. (2015)

 

Figure 11-2 Scatter Plot Showing Re Versus MoS2 in the Cu-Mo Zone

 

For blocks containing more than one mineralized zone, a weighted average was produced. The two commodities are considered not as by-products of a producing mine but as smelter/processing credits from the concentrates. Smelter credits and penalties are common within the mining industry and in many cases, the credit or penalty element is not contained in the current resources or reserves of a project. The author has included the commodities to provide full disclosure as circuits to recover and produce these products are built into capital and operating costs. Re and S values have not been used to determine the RCV of blocks. The contribution of these commodities to the overall economic analyses is small and well within the accuracy of the IA level of study, with rhenium contributing 0.37% of the overall revenue and sulfuric acid 0.49%.

 

Note: Regression analysis is not industry standard practice in calculating overall resources. However, the fact that rhenium and sulfur are contained within the material containing MoS2, which has been estimated by kriging, means that regression is a valid method of obtaining a reasonable estimate of the rhenium and sulfur contents at the level of precision of this study. Additional sulfur can be recovered from chalcopyrite. Due to the large number of samples involved in the regression analysis, the confidence of this particular regression estimate is comparable to that obtained by the method of ordinary kriging.

 

134
 

 

11.6Bulk Density

 

A total of 4,539 specific gravity determinations were made for CuMo in all mineralized zones. This total includes 4,339 determinations made during the 2011 drill program. The measurements were made using the weight in air/weight in water procedure. The results are summarized in Table 11-12.

 

Table 11-12 Summary of Density Parameters for Each Mineralized Zone

 

Zone Number of SG Determinations SG Minimum SG Maximum Average SG (g/cm3)

Average

TF (ft3/ton)

Ox 578 2.08 2.74 2.50 12.80
Cu-Ag 1,505 2.28 3.70 2.58 12.42
Cu-Mo 1,524 2.25 2.85 2.58 12.40
Mo 763 2.30 2.75 2.57 12.45
MSI 91 2.40 2.73 2.57 12.48
Dyke 78 2.19 2.75 2.52 12.71
Total 4,539 2.08 3.70 2.57  

 

Note. Cu-Ag = copper-silver, Cu-Mo = copper-molybdenum, ft3 = cubic feet, g/cm3 = grams per cubic centimeter, Mo = molybdenum, MoS2 = molybdenite, MSI = potassic-silica alteration zone with lower-grade Cu-Mo mineralization, OX = oxide, SG = specific gravity, W = tungsten

 

11.7Reasonable Prospects for Economic Extraction

 

Reasonable prospects for eventual economic extraction have been established by constraining the resource estimate to within a conceptual open pit design using reasonable parameters from an analogous nearby molybdenum deposit. An RCV in non-oxide material of $5.00/t has been highlighted as a possible open pit cut-off In the mineral resource tables at the end of this section, the $5.00 cut-off for the assumed price is highlighted and is selected based on operating costs. The $5.00 cut-off is suggested to separate waste from material that is fed to the sorters. From the sorters, only mill feed above an economic cut-off would be sent for immediate processing.

 

Since the infill drill holes completed in 2011-12 were all within this conceptual pit this resource update uses the Snowden (2012) optimum pit shell to both constrain the estimate and demonstrate reasonable prospects for eventual economic extraction.

 

In 2025, Whittle Consulting used Geovia’s WhittleTM pit optimizer to determine a constraining open pit for the CuMo deposit. Optimization parameters were developed directly between Whittle and Idaho Copper. The open pit cone sequence and extents, the process throughput and recovery, and the schedule were provided to Barr. From the information, Barr developed initial and final open pit designs based on the pit cones, a mine production schedule and process schedule, and economic model based on applied metal prices, capital expenditures, and operational expenses over the life of the CuMo project.

 

Based on the review of these assumptions, the Q P concludes that the reported Mineral Resources satisfy the requirement for reasonable prospects for economic extraction under S-K 1300, subject to the limitations and uncertainties discussed in this report.

 

135
 

 

11.8Resource Classification

 

At CuMo, geological continuity has been established through diamond drilling. The concentric zonation and faults have been used to constrain the mineralization in a series of mineralized zones. Grade continuity within the mineralized zones has been determined by semi-variograms for each variable.

 

Semi-variograms are an aspect of data analysis that assist in defining the correlation and range of influence of a grade variable in various directions in three dimensions. Semi-variograms are a graphical geostatistical tool used to determine the direction and range over which samples show continuity. The semi-variogram plots the mean squared difference between samples as an increasing function of distance between samples, and as the distance between samples increases, it reaches a point (the range) where samples are no longer correlated.

 

In this case, the semi-variogram analysis was completed after moving major fault blocks back to prefault positions. The kriging procedure was completed on fault blocks in their current positions; thus by using the range in each of the major directions, the grade continuity can be quantified. This in turn can be used to establish classification levels.

 

The resource is classified as follows in the following subsections.

 

11.8.1Measured

 

“Geological evidence is derived from detailed and reliable exploration, sampling and testing and is sufficient to confirm geological and grade or quality continuity between points of observation.”

 

Contiguous blocks within the Cu-Ag and Cu-Mo Zones estimated in Pass 1 (using one quarter of the semi-variogram range) for both MoS2 and Cu were classified as measured. For the Mo and MSI zones where Cu, Ag and W provide little of the economic benefit contiguous blocks estimated in Pass 1 for MoS2 were classified as measured.

 

11.8.2Indicated

 

“Geological evidence is derived from adequately detailed and reliable exploration, sampling and testing and is sufficient to assume geological and grade or quality continuity between points of observation.”

 

Indicated blocks were established from unclassified blocks estimated for Cu or MoS2 in Pass 1 or 2 using search ellipses up to a maximum of one half the semi-variogram range.

 

11.8.3Inferred

 

All other blocks were classified as inferred.

 

An Inferred Mineral Resource is that part of a mineral resource for which quantity and grade or quality are estimated on the basis of limited geological evidence and sampling. Geological evidence is sufficient to imply but not verify geological and grade or quality continuity. An Inferred Mineral Resource has a lower level of confidence than that applying to an Indicated Mineral Resource and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of Inferred Mineral Resources could be upgraded to Indicated Mineral Resources with continued exploration.

 

136
 

 

The previous authors have stated that the characteristics of the mineralization and associated reports and preliminary data and information concerning mining, metallurgy, economics, and social and environmental sensitivity was considered in determining that the classification meets the requirement of reasonable prospects for eventual economic extraction.

 

In 2026, SGS conducted copper/molybdenum separation flotation tests. While the conditions were not optimized, the test results showed an effective copper/molybdenum separation. Figure 11-3 shows indicative plan views of the measured, indicated and inferred blocks at CuMo.

 

 

Source: Giroux et al. (2015), modified 2019

 

Note: The above shows all blocks estimated. The outline of the 2012 Snowden constraining pit has been added. The blocks within this constraining pit are summarized in the various tables.

 

Figure 11-3 Plan Views of the Measured, Indicated and Inferred Blocks at CuMo

 

11.9Recovered Value

 

To properly evaluate the CuMo deposit with four metals occurring in different zones, A factor named recovered value, or RCV, was used. This calculation used metal prices in US dollars and metal recoveries.

 

The RCV calculations were based on the set of prices defined in Table 11-13.

 

137
 

 

Table 11-13 Metal Prices for Resources

 

Metal Price
Copper (Cu), $/lb 3.00
Molybdenum trioxide (MoO3), $/lb 10.00
Molybdenum Metal (Mo), $/lb 15.00
Silver (Ag), $/oz 12.50

Note. Ag = silver, Cu – copper, lb = pound, Mo = molybdenum, MoO3 = molybdenum trioxide, oz = ounce

 

Molybdenum is sold as molybdenum trioxide (MoO3) which has higher Mo content. The price used in this study for MoO3 is $10/lb. MoO3 is calculated from MoS2 by the following:

 

●Pounds Mo = MoS2 * 20 / 1.6681
   
●Pounds MoO3 = Pounds Mo * 1.5

 

The metal recoveries used to calculate RCV were a function of mineralized zones as follows in Table 11-14.

 

Table 11-14 Metal Recoveries Sorted by Mineralized Zone

 

Zone Cu Recovery (%) Mo Recovery (%) Ag Recovery (%)
OX 60 80 65
Cu-Ag 68 86 75
Cu-Mo 85 92 78
Mo 72 95 55
MSI 72 95 55

 

Note: The recoveries for all metals in the MSI zone were similar to the Mo zone. Cu-Ag = copper-silver, Cu-Mo =copper-molybdenum, Mo = molybdenum, MSI = potassic-silica alteration zone with lower-grade Cu-Mo mineralization, OX = oxide

 

Factors to use in RCV equation were as follows:

 

MoS2 Factor ($/ton) = MoS2 % * Mo Recovery % * 2000 lb/ton * $/lb MoO3 * 1.5/1.6681

Cu Factor ($/ton) = Cu % * Cu Recovery % * 2000 lb/ton * $/lb Cu

Ag Factor ($/ton) = Ag ppm * Ag Recovery % * $/oz Ag

31.1035 g/oz * 1.1023 tons/tonne

 

The equations to calculated RCV for each mineralized zone were as follows:

 

RCV (oxides) = (Cu% * 36.0) + (Ag(ppm) * 0.24) + (MoS2% * 143.88)

RCV (Cu-Ag) = (Cu% * 40.8) + (Ag(ppm) * 0.27) + (MoS2% * 154.67)

RCV (Cu-Mo) = (Cu% * 51.0) + (Ag(ppm) * 0.28) + (MoS2% * 165.46)

RCV (Mo) = (Cu% * 43.2) + (Ag(ppm) * 0.20) + (MoS2% * 170.85)

RCV (MSI) = (Cu% * 43.2) + (Ag(ppm) * 0.20) + (MoS2% * 170.85)

 

138
 

 

For blocks overlapping the mineralized zone boundaries, a weighted average RCV was produced.

 

A complete series of tables for each zone (5), each classification (4) and for each price regime (3) plus an overall set were produced (a total of 72 tables). For the purposes of this summary report, the mineral resource estimate described next was for all zones.

 

11.10Mineral Resource Estimate

 

Table 11-15. Table 11-16, Table 11-17, and Table 11-18 report the overall mineral resource estimated within the Snowden 2012 open pit shell at a variety of RCV cut-offs. The effective date for this Mineral Resource Estimate remains August 30, 2018. The $5.00/t cut-off is highlighted as an appropriate RCV cut-off based on grade improvements using mineral sorting processes. The base case $5.00 cut-off is suggested to separate waste from material that is fed to the sorters. The actual cut-off used in economic analysis and mine design will vary depending on numerous conditions at the time of the calculation: including metal prices, recoveries and operating costs.

 

It should be noted that since the convention for the CuMo project has been to work with %MoS2, as calculated from measured %Mo, the %MoS2 values in the resource estimate tables are 1.6681 times greater than %Mo.

 

Mineral Resources are not Mineral Reserves and have not demonstrated viable economic recovery. Therefore, it is not certain that Mineral Resources will be converted to Mineral Reserves. Any Mineral Reserve estimate may be affected by existing or future environmental, permitting, legal, land title, taxation, socio-political, metallurgical, or other relevant factors that may not be listed here. Inferred Mineral Resources inherently have a lower level of confidence compared to Indicated Mineral Resources and must not be converted to Mineral Reserves. It may be reasonable to expect that a portion of Inferred Mineral Resources could be upgraded to Indicated Mineral Resources with continued exploration and geometallurgical analysis. Mineral Resources, determined for this estimate effective August 30, 2018, were previously prepared in accordance with National Instrument 43-101 (NI 43-101) and the CIM Definition Standards for Mineral Resources and Mineral Reserves. While the previous technical work provides a basis for the current assessment, the Mineral Resource disclosure presented herein has been reviewed against the applicable definitions, classification requirements, and disclosure provisions of S-K 1300.

 

Table 11-15 Measured Resources

 

Cut-Off RCV ($) Grade > RCV Cut-Off

RCV

($)

Re (ppm)

S

(%)

Contained Metal

Ag

(Moz)

Quantity

(Mt)

MoS2

(%)

Cu

(%)

Ag

(ppm)

Mo

(Mlb)

Cu

(Mlb)

2.5 308.4 0.079 0.074 2.09 17.32 0.029 0.233 292.1 456.5 18.8
5.0 297.2 0.081 0.076 2.09 17.83 0.03 0.229 288.6 451.7 18.1
7.5 282 0.085 0.076 2.06 18.48 0.031 0.223 287.4 428.7 16.9
12.5 227.9 0.097 0.075 2 20.50 0.036 0.217 265 341.8 13.3
15.0 195.4 0.105 0.072 1.9 21.71 0.039 0.212 246 281.3 10.8
17.5 159.7 0.115 0.067 1.8 23.04 0.043 0.207 220.1 213.9 8.4
20.0 122.9 0.125 0.063 1.7 24.50 0.047 0.202 184.1 154.8 6.1

 

Source: Giroux et al. (2015), modified 2019, reviewed 2026. The effective date for this Mineral Resource estimate remains August 30, 2018. Note. Ag = silver, Cu-Ag = copper-silver, Mlb = millions of pounds, Mo = molybdenum, Moz = million ounces, Mt = million tons, ppm = parts per million, RCV = recoverable value

 

139
 

 

Table 11-16 Indicated Resources

 

Cut-Off RCV ($) Grade > RCV Cut-Off

RCV

($)

Re

(ppm)

S

(%)

Contained Metal

Ag

(Moz)

Quantity

(Mt)

MoS2

(%)

Cu

(%)

Ag

(ppm)

Mo

(Mlb)

Cu

(Mlb)

2.5 2216.1 0.049 0.079 2.48 12.32 0.018 0.277 1301.9 3501.4 160.3
5.0 1972.3 0.053 0.085 2.57 13.40 0.019 0.269 1253.3 3352.9 147.8
7.5 1708.3 0.059 0.088 2.59 14.55 0.021 0.258 1208.4 3006.5 129
12.5 1050.6 0.076 0.09 2.55 17.67 0.027 0.235 957.4 1891.1 78.1
15.0 798.5 0.083 0.09 2.56 19.06 0.03 0.231 794.6 1437.2 59.6
17.5 541.6 0.093 0.088 2.49 20.60 0.034 0.226 603.9 953.2 39.3
20.0 301.3 0.106 0.082 2.36 22.49 0.039 0.219 383 494.2 20.7

 

Source: Giroux et al. (2015), modified 2019, reviewed 2026. The effective date for this Mineral Resource estimate remains August 30, 2018. Note. Ag = silver, Cu-Ag = copper-silver, Mlb = millions of pounds, Mo = molybdenum, Moz = million ounces, Mt = million tons, ppm = parts per million, RCV = recoverable value

 

Table 11-17 Measured and Indicated Resources

 

Cut-Off RCV ($) Grade > RCV Cut-Off

RCV

($)

Re

(ppm)

S

(%)

Contained Metal

Ag

(Moz)

Quantity

(Mt)

MoS2

(%)

Cu

(%)

Ag

(ppm)

Mo

(Mlb)

Cu

(Mlb)

2.5 2524.6 0.053 0.079 2.43 12.93 0.019 0.272 1604.3 3988.9 178.9
5.0 2269.6 0.057 0.084 2.5 13.98 0.021 0.264 1551.1 3812.9 165.5
7.5 1990.4 0.063 0.086 2.51 15.10 0.022 0.253 1503.5 3423.5 145.7
12.5 1278.6 0.079 0.087 2.46 18.17 0.029 0.232 1211.1 2224.8 91.7
15.0 993.9 0.088 0.087 2.43 19.58 0.032 0.227 1048.7 1729.5 70.4
17.5 701.4 0.098 0.083 2.33 21.16 0.036 0.221 824.1 1164.2 47.7
20.0 424.3 0.112 0.077 2.17 23.07 0.041 0.214 569.8 653.4 26.9

 

Source: Giroux et al. (2015), modified 2019, reviewed 2026.The effective date for this Mineral Resource estimate remains August 30, 2018.Note. Ag = silver, Cu-Ag = copper-silver, Mlb = millions of pounds, Mo = molybdenum, Moz = million ounces, Mt = million tons, ppm = parts per million, RCV = recoverable value

 

140
 

 

Table 11-18 Inferred Resources (Molybdenum, Copper, Silver, Rhenium, and Sulfur)

 

Cut-Off RCV ($) Grade > RCV Cut-Off

RCV

($)

Re

(ppm)

S

(%)

Contained Metal

Ag

(Moz)

Quantity

(Mt)

MoS2

(%)

Cu

(%)

Ag

(ppm)

Mo

(Mlb)

Cu

(Mlb)

2.5 3373.6 0.04 0.057 1.93 9.55 0.014 0.304 1617.9 3845.9 189.9
5.0 2556.6 0.048 0.067 2.13 11.48 0.017 0.282 1471.4 3425.9 158.8
7.5 1996 0.056 0.07 2.23 13.07 0.02 0.261 1340.1 2794.4 129.8
12.5 996.4 0.078 0.064 1.98 16.74 0.028 0.231 931.8 1275.4 57.5
15.0 637 0.086 0.074 2.16 18.63 0.03 0.244 656.8 942.7 40.1
17.5 384.8 0.094 0.084 2.34 20.49 0.032 0.259 433.7 646.4 26.3
20.0 190.2 0.109 0.078 2.37 22.80 0.037 0.262 248.6 296.8 13.1

Source: Giroux et al., (2015), modified 2019, reviewed 2026. The effective date for this Mineral Resource estimate remains August 30, 2018. Note. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. There is no certainty that all or any part of the Mineral Resources will be converted into Mineral Reserves. Ag = silver, Cu-Ag = copper-silver, Mlb = millions of pounds, Mo = molybdenum, Moz = million ounces, Mt = million tons, ppm = parts per million, RCV = recoverable value

 

141
 

 

12 Mineral Reserve Estimates

 

No Mineral Reserve estimates, as defined by the SEC S-K 1300 New Mining Disclosure Rule, currently exist for the CuMo project.

 

142
 

 

13 Mining Methods

 

13.1Mining Overview and Method

 

The CuMo project is planned as an owner-operated open pit mine using electric cable shovels and electric-drive haul trucks. The mineralized inventory supports bulk mining by conventional drilling, blasting, loading and haulage. Grade control defines excavation boundaries and material destinations. Loading-face sorting separates mineralized feed from reject material at the dig face. Feed material is hauled to the primary crusher or run-of-mine (ROM) stockpile; waste and shovel rejects are hauled to Charlotte Gulch or, where suitable, used to construct the tailings embankment.

 

Primary crushing is followed by two belt-sorting stages. The first stage produces mill feed, middlings for further sorting and rejects. The second stage produces additional mill feed, middlings and rejects. Middlings are stored for later milling, while rejects are placed in the waste-rock storage facility. Sorting reduces the mass sent to the mill by rejecting lower-value material ahead of milling.

 

The pit is developed in six main mining phases, with the larger phases subdivided for production scheduling. Total excavation is approximately 3,083 million US short tons (Mst) including 1,401 Mst of mineralized material and 1,682 Mst of waste and construction rock. The waste-to-mineralized-material ratio is 1.20 st/st. Mill feed totals 1,127 Mst after sorting and stockpile reclaim. The final facilities layout is presented in Figure 13-1.

 

Primary open pit excavation begins in pre-production development Year −1 and continues through completion of the planned pit in Year 22. Processing continues from stockpiled material after pit mining ends. Mill operation starts in Year 1, expands to 25.55 million short tons per year (Mstpa) in Year 5 and continues through Year 46. Crushing and sorting extend through Year 24 as the remaining ROM stock is treated. From Year 25 onward, the mill is supplied entirely by middlings reclaim. The principal production measures are summarized in Table 13-1.

 

The IA is preliminary and includes Inferred Mineral Resources. These resources are geologically too speculative to support the economic assumptions required for Mineral Reserve classification. There is no certainty that the IA results will be realized.

 

Table 13-1 Mine-Plan Overview

 

Measure Unit Study Quantity
Primary Excavation Mst 3,083
Mineralized Material to Crushing or ROM Storage Mst 1,401
Primary Waste and Embankment Rock Mst 1,682
Waste/Mineralized-Material Ratio st/st 1.20
Mill Feed Mst 1,127
Maximum Annual Primary Excavation Mstpa 160
Maximum Annual Crusher Feed Mstpa 70
Full Annual Mill-Feed Rate Mstpa 25.55
Primary Excavation Relative years −1 and 1–22
Crushing and Sorting Relative years 1–24
Mill Operation Relative years 1–46

Source: NLM (2026). Note. Mst = million short tons, Mstpa = million short tons per year, st = short tons

 

143
 

 

 

Note. Grid coordinates and elevations are in feet. Source: NLM (2026)

 

Figure 13-1 Mine and Material-Storage Layout

 

13.1.1Mine Planning Development

 

Whittle Consulting completed a strategic option study in 2025 that evaluated pit limits, mining sequences, sorting responses and operating configurations (Whittle, 2025). The preferred pit limits and phased production targets provided the starting point for mine planning, including feed delivery, stockpile placement and reclaim.

 

144
 

 

NLM validated the Whittle pit limits through independent pit optimizations and evaluated alternative mining and processing configurations using preliminary engineering inputs. These evaluations examined phase development, mining rates, feed selection, stockpile use, process capacity and haulage. They confirmed similar pit limits and the principal development sequence. NLM then incorporated ramps, working widths and bench geometry into six main mining phases and developed the production schedule and mining cost estimate.

 

The production schedule and detailed mining costs were then incorporated in the Technical Economic Model presented in Section 19. The pit-limit comparison presented in Section 13.4 uses the stated pit-valuation assumptions to compare the ultimate Whittle pit, the independently generated pit optimization limits and the pit designs used in the production schedule.

 

13.2Baseline Mine Planning Inputs

 

The production schedule follows six main mining phases. Phases 3 to 6 are divided into smaller scheduling phases to control stripping and feed release. The resulting twelve scheduling phases are presented in the bench sequence in Section 13.6.1. Pit mining starts in Year −1 and ends in Year 22; stockpile treatment extends processing through Year 46.

 

The mine plan uses the Mineral Resource estimate described in Section 11, with an effective date of August 30, 2018. The estimate is unchanged from the 2020 technical report and was reviewed for this IA as described in Section 11. The planning model retains 50-ft cubic resource blocks containing tonnage, copper, molybdenum and silver grades, density, metallurgical-domain proportions and resource classification. Measured, Indicated, and Inferred Mineral Resources are included in the IA schedule. Copper–silver, copper–molybdenum and molybdenum/MSI domains are evaluated separately because their metal distributions and metallurgical responses differ.

 

Material quantities are stated in US short tons (st), equal to 2,000 lb; Mst denotes million short tons. Metal quantities are stated in million pounds (Mlb) or million troy ounces (Moz). Monetary values are in US dollars, with US$M denoting millions of dollars. Design dimensions and elevations are in feet. Copper and molybdenum grades are weight percentages; silver grade is in grams per metric tonne (g/t). Relative production years use a 365-day basis. Year −1 is the pre-production mining year and is followed by Year 1, with no Year 0. Displayed totals may differ from the sums due to rounding.

 

Primary excavation comprises mineralized material delivered to crushing or ROM storage and waste hauled to Charlotte Gulch or the tailings embankment. Crusher feed, sorter products, sorter rejects and mill feed are reported at their respective treatment stages. Stockpile placement and reclaim are separate handling duties and do not increase the pit inventory. Table 13-2 summarizes the life-of-operation material balance at these reference points.

 

Table 13-2 Life-Of-Operation Material Balance at Defined Reference Points

 

Reference Point / Stream Quantity (Mst)
Total Primary Excavation 3,083
Mineralized Material to Crusher or ROM Stock 1,401
Primary Waste and Construction Rock 1,682
Direct Pit-To-Crusher Delivery 1,384
Pit-To-ROM Stock Placement 17

 

145
 

 

Reference Point / Stream Quantity (Mst)
ROM Stock Reclaim to Crusher 17
Total Crusher and Sorter Feed 1,401
Sorter Products to Mill 447
Middlings Stockpile Receipts 685
Middlings Reclaim to Mill 680
Sorter Rejects To Waste 269
Total Mill Feed 1,127

Source: NLM (2026). Totals are calculated before rounding; displayed components may not sum to totals.

 

The ROM stockpile receives 16.6 Mst and later supplies that same quantity to the crusher. The mill receives 447 Mst of sorter products and 680 Mst of middlings reclaim. At the end of processing, 5.0 Mst remains in the middlings stockpile and is excluded from mill feed and metal production.

 

Scheduled feed by resource classification, waste and the strip ratio are summarized in Table 13-3. Inferred material accounts for 17.1% of feed tonnage. Feed quantities and grades are reported after loading-face selection and before belt sorting. Classification is based on resource classification as described in Section 11.8.

 

Table 13-3 Scheduled Material Quantities

 

Material or Classification Mass (Mst) Delivered Grade Contained Metal
Cu (%) Mo (%) Ag (g/t) Cu (Mlb) Mo (Mlb) Ag (Moz)
Measured 244 0.08 0.05 2.10 378 261 15
Indicated 917 0.10 0.04 2.76 1,773 706 74
Measured + Indicated 1,161 0.09 0.04 2.62 2,151 967 89
Inferred 240 0.09 0.02 2.69 430 116 19
Waste 1,682            
Strip ratio (st/st) 1.20            

Source: NLM (2026). Note. Scheduled feed does not constitute Mineral Reserves. Feed quantities are based on the schedule cutoffs described in Section 13.2.1. There is no certainty that further exploration will result in the Inferred Mineral Resources being upgraded to Indicated or Measured classification. Strip ratio is waste divided by scheduled feed, including Inferred Mineral Resources. Waste includes construction rock. Ag = silver, Cu = copper, g/t = grams per metric ton, Mlb = millions of pounds, Mo = molybdenum, Moz = million ounces, Mst = million short tons

 

Table 13-4 summarizes the initial economic assumptions used to develop the mine plan. Metal recoveries are listed in Table 13-5. Recovered copper, molybdenum and silver are valued at realized prices after selling deductions. Mining costs apply to excavated material, while treatment and handling costs apply to the material sent through each route. Scheduling maximizes discounted value subject to phase access, mining rates, treatment capacity and stockpile availability. Table 13-11 gives the inputs for the pit-limit comparison using the IA economic assumptions. The detailed cost estimate and economic results are presented in Sections 18 and 19.

 

146
 

 

Table 13-4 Baseline Production-Scheduling Inputs

 

Input Unit or Reference Point Value
Copper sales price US$/lb Cu 5.00
Molybdenum sales price US$/lb Mo 25.00
Silver sales price US$/troy oz Ag 50.00
Copper Realized Price US$/lb recovered Cu 4.20
Molybdenum Realized Price US$/lb recovered Mo 22.68
Silver Realized Price US$/troy oz recovered Ag 36.83
Variable Mining Cost US$/st mined 1.45
Fixed Mining Cost to Ordinary Destinations US$/st mined 0.20
Fixed Mining Cost to Embankment US$/st mined 0.90
Combined Mining Cost to Ordinary Destinations US$/st mined 1.65
Combined Mining Cost to Embankment US$/st mined 2.35
ROM Feed Processing and Reclaim Charge US$/st reclaimed 1.20
Belt-Sorting Route Charge US$/st treated 1.33
Mill Processing Cost US$/st mill feed 8.77
Middlings Placement Charge US$/st placed 0.82
Middlings Reclaim Charge US$/st reclaimed 0.82
Sorter Reject Placement Charge US$/st placed 0.82
Discount Rate % per year 8
Resource-Block Dimensions ft 50 × 50 × 50
Full Mining Rate Mstpa 160
Full Crusher Feed Rate Mstpa 70
Full Mill Feed Rate Mstpa 25.55
Operating Calendar days/year 365
Truck Payload st/load 360

Source: NLM (2026). Note. Ag = silver, Cu = copper, ft = feet, Mo = molybdenum, Mstpa = million short tons per year, st = short tons. Realized prices include downstream sales costs and payability.

 

Table 13-5 Metallurgical Recoveries Used in Production Scheduling

 

Material Domain Cu (%) Mo (%) Ag (%)
Copper–Silver 87 82 77
Copper–Molybdenum 87 92 75
Molybdenum 66 90 49

Source: Barr (2026). Note. Ag = silver, Cu = copper, Mo = molybdenum

 

The mining and mill ramp-up is summarized in Table 13-6. Mining reaches 160 Mstpa in Year 4, followed by full mill throughput of 25.55 Mstpa in Year 5.

 

147
 

 

Table 13-6 Mining and Mill Ramp-Up Schedule

 

Year Primary Excavation (Mst) Mill Feed (Mst)
−1 37.3 0.0
1 75.0 9.0
2 110.0 12.8
3 150.0 12.8
4 160.0 19.2
5 160.0 25.6

 

Source: NLM (2026).Note. Year −1 is pre-production; Year 1 is the first operating year. Mst = million short tons

 

13.2.1Economic Cutoff and Material Selection

 

Feed selection is based on net smelter return (NSR), expressed in dollars per short ton, because copper, molybdenum and silver all contribute to value. NSR is calculated by multiplying the contained quantity of each metal by its metallurgical recovery and realized sales price, summing the metal contributions and dividing by feed tonnage. Realized prices include selling deductions; on-site operating costs are applied separately. The prices and domain recoveries used in production scheduling are given in Table 13-4 and Table 13-5.

 

The preliminary cutoff calculation uses the primary mill-feed reference route in the mine-planning basis of design. Combined crushing, sorting, milling, tailings and site G&A cost is US$10.10/st. Mining costs are US$1.45/st for feed and US$1.65/st for waste. The internal cutoff compares processing with waste disposal for material that must be excavated; the operating break-even cutoff includes the full cost of mining the feed.

 

These costs give an internal NSR cutoff of US$9.90/st and an operating break-even NSR cutoff of US$11.55/st (Table 13-7). The reference costs are common to the three material domains. Equivalent metal grades differ with metal proportions and recovery.

 

Table 13-7 Internal and Operating Break-Even NSR Cutoffs

 

Cutoff Calculation (US$/st) NSR (US$/st)  
Internal

Downstream cost + feed mining − waste mining

10.10 + 1.45 − 1.65

9.90
Operating break-even

Downstream cost + feed mining

10.10 + 1.45

11.55

Source: NLM (2026). Calculations retain unrounded costs; displayed values are rounded to two decimals. Note. NSR = net smelter return, st = short ton, US$ = U.S. Dollar

 

Cutoffs are allowed to vary through the production schedule to account for the material exposed, available crusher and mill capacity, stockpile handling and the timing of revenue. Material is grouped into economic value classes for scheduling, and sorting determines the portions sent to the mill, stored as middlings or rejected. The schedule can therefore use more than one selection threshold in a year. Material routing is described in Section 13.5 and the production schedule in Section 13.6.

 

148
 

 

Figure 13-2 shows the resulting minimum crusher-feed NSR equivalent by material domain in each production year. Each value is the lowest average for a mining cut and material domain delivered to the crusher, including ROM reclaim. Years 23 and 24 contain ROM reclaim only. Gaps indicate years with no crusher feed from that domain.

 

 

Source: NLM (2026)

 

Figure 13-2 Minimum Annual Crusher-Feed NSR Equivalent by Material Domain

 

The plotted values describe feed selection at the crusher inlet, before belt sorting. Downstream rejection reduces the mass requiring milling, so the reference-route cutoffs do not act as fixed admission limits at the crusher. The curves represent cut averages rather than individual-block cutoffs. Sections 18 and 19 present the detailed operating costs and project economic results.

 

13.2.2Mining Dilution and Ore Loss

 

The mine plan uses 50 by 50 by 50 ft resource blocks. Dilution is assumed to be incorporated in the block grades, considering the block dimensions relative to the effective selection unit used in the sorting response. No additional mining dilution is applied. Mining recovery is assumed to be 100%, with no separate ore-loss deduction. Sorter rejects are accounted for in the processing balance, and metallurgical recoveries are applied to metal in the treatment streams.

 

13.2.3Selective Mining Unit and Sorter Efficiency

 

Lycopodium developed the response using Veracio drill-core X-ray fluorescence scans and the SGS block model. The dataset comprises 410,163 records from 24 drillholes at nominal 0.05-ft intervals after oxide and dyke records were excluded. Adjacent scans were composited into parcels representing successive material-handling stages, and copper and molybdenum grades were averaged within each parcel to calculate its value.

 

149
 

 

The loading-face selective mining unit is a nominal 85-metric-tonne parcel, equivalent to approximately 94 short tons. The two belt stages use 10- and 5-metric-tonne parcels. These parcel sizes define the scale of grade discrimination assumed in the sorting response. They do not reduce the 50-ft dimensions of the resource blocks used to calculate pit inventories.

 

For each material domain and value class, the parcel analysis estimates separate mass and metal distributions to accepted product, middlings and reject. These distributions are applied to the resource blocks to calculate the routed quantities and grades used in mine planning. Oxide material uses the copper–silver response, and MSI uses the molybdenum response. The mass response and metal response are carried separately through each stage so that rejection changes both feed quantity and grade.

 

A factor of 0.8 is applied to the sorter response to represent the modeled sorting efficiency. The parcel sizes were established before selection of the mining fleet. Performance at the loading face depends on fragmentation, blast movement, digging selectivity and mixing during loading and haulage. At the belt stages, sensor calibration, belt loading, material presentation and diverter response affect mass yield and metal retention.

 

The loading-face selection unit is small relative to the cable-shovel and 360-st truck operating arrangement. Representative trials and change-of-support analysis are included in the first stage of recommended work programs to establish the achievable response with this fleet and quantify mining dilution, mixing and sorter losses. These results will provide the sorting and selectivity basis for the PFS mine plan.

 

Barr’s process QP reviewed the information and methodology provided by Lycopodium for the development of the ore-sorting response and inclusion concept for the current IA.

 

13.3Geotechnical and Pit Water Basis
13.3.1Pit Wall Assessment

 

The pit geotechnical assessment comprised a review of existing investigations and a site visit on June 26, 2026. It considered rock-mass strength and planar, wedge and toppling failure along major structures. Three historical geotechnical holes are concentrated in the southwest part of the deposit; hole C10‒55 is approximately parallel to the proposed wall. Mean rock quality designation (RQD) was 18%. Rock mass rating (RMRL90) ranged from 25 to 70, averaging 46.

 

The geotechnical data referred to in the 2020 PEA update were not included with the information provided for this 2026 IA.

The core from drill hole C10‒55 showed a deep weathering profile and was generally highly fractured, largely due to medium to high micro-defect intensity. It included damage zones, gouge, breccia and rubble probably associated with large-scale brittle structures, such as faults and shear zones.

 

The color-coded plot of RMRL90 values showed no obvious zonation or increase in values with depth.

 

The QA/QC check found that sections of core had similar RMRL90 values but distinctly different rock qualities in the core photos. This pattern points to possible errors or inconsistencies in logging practices and the project geotechnical dataset.

 

Table 13-8 summarizes the wall heights, bench height, and calculated overall slope angles of the historical resource-constraining pit shell from Snowden (2012).

 

150
 

 

Table 13-8 Historical Resource-Pit-Shell Geometry from Snowden (2012)

 

Pit Sector Resource pit-shell depth, m (ft) Bench height, m (ft) Calculated Overall Slope Angle (degrees)
North Wall 670 (2,198) 15 (49.2) 42
East Wall 590 (1,936) 15 (49.2) 43
South Wall 850 (2,789) 15 (49.2) 42
West Wall 670 (2,198) 15 (49.2) 42

 

Source: Barr (2026), based on Snowden (2012). Feet are converted from the reported meter dimensions and rounded.

 

Figure 13-3 compares the historical resource-pit-shell wall heights and calculated overall slope angles with empirical slope experience. The historical drilling records extensive fracturing and deep weathering but provides limited coverage of the pit. Representative geotechnical investigation and stability analysis are recommended for the PFS in Section 23.

 

 

Source: SRK (2019), reproduced in Barr (2026)

 

Figure 13-3 Empirical Pit Wall Height and Slope Comparison

 

151
 

 

The pit design uses the 50-ft benches, 26-ft catch berms and 60° bench faces recommended by the qualified person responsible for the pit geotechnical assessment, as summarized in Table 13-9. Pit ramps are assumed to interrupt the bench stacks and contribute to decoupling the bench slopes. Separate 65-ft geotechnical berms included in the assessment recommendations were not incorporated in the pit design.

 

Table 13-9 Pit-Design Bench Geometry

 

Criterion Unit Value  
Maximum Bench Height feet 50
Catch-Berm Width feet 26
Bench Face Angle degrees 60

Source: Barr (2026) and NLM (2026)

 

A uniform stack of 50-ft benches, 26-ft catch berms and 60° bench faces has a calculated inter-ramp angle of approximately 42° before ramp interruptions. This geometric angle differs from the depth-based inter-ramp recommendations in Table 13-10. Stability of the designed walls, including the ramp-decoupling assumption and omission of separate major berms, requires assessment in the PFS as recommended in Section 23.

 

The recommended inter-ramp and overall slope angles flatten with increasing depth below ground surface (Table 13-10). The same depth-based slope criteria apply to all pit sectors. Inter-ramp angles apply between ramp interruptions; overall angles include the ramps. The geotechnical assessment used average angles of 38° inter-ramp and 35° overall for its pit-shell review, allowing for major berms and a spiral ramp. Assessment of the designed walls, including the ramp interruptions, is recommended in Section 23.

 

Table 13-10 IA Pit-Wall Angle Recommendations by Depth

 

Depth Below Ground Surface (ft) Inter-Ramp Angle (degrees) Overall Slope Angle (degrees)
<1,000 50 45
1,000–2,000 45 40
>2,000 40 35

Source: Barr (2026). Note. ft = feet

 

The geotechnical assessment did not include groundwater-pressure effects. Groundwater pressures and major low-angle faults may require flatter slopes or depressurization. The recommended investigations in Section 23 address these conditions.

 

13.3.2Pit Water Management

 

Pit water is collected and pumped to maintain trafficable working areas and haul roads. The mining estimate includes pumping and service equipment. Further hydrogeological testing and calibration of the groundwater model are recommended in Section 23 to estimate inflows and wall pressures as the pit deepens. Site water-management facilities are described in Section 15, and environmental requirements in Section 17.

 

152
 

 

13.4Pit Optimization and Design

 

13.4.1Pit Optimization

 

NLM carried out independent pit optimizations and mining-configuration evaluations to confirm the Whittle pit limits and development sequence before completing the pit and phase designs. The results presented here compare the preferred Whittle pit and those designs with an optimization using the IA project economic model. Localized differences in the pit outline do not materially change the overall mining extent.

 

The check used the Pseudoflow algorithm to determine pit limits from block revenues and mining and treatment costs, subject to slope and surface constraints. The 50-ft resource blocks were combined into 100-ft optimization blocks. Measured, Indicated and Inferred Mineral Resources were valued using the domain-specific sorting response and recoverable copper, molybdenum and silver; other resource classifications were treated as waste.

 

Table 13-11 summarizes the inputs used in pit optimization. Each block was evaluated for direct milling, middlings storage and later treatment, or rejection. Nested pit shells were generated by applying a range of revenue factors while holding operating costs, recoveries and slope criteria constant. A revenue factor scales the net metal revenue used to establish the pit limits; it is not a change to the metal prices assumed in the project economic analysis. The slope zones follow the depth intervals in the geotechnical assessment (Table 13-10). The wall geometry near surface was reduced to account for the greater effect of access roads on the overall slopes.

 

Table 13-11 Inputs for the Pit-Optimization Validation

 

Input Value or Basis
Optimization Method Pseudoflow
Optimization Block Dimensions 100 ft × 100 ft × 100 ft (reblocked 50 ft × 50 ft × 50 ft)
Resource Classifications Measured, Indicated and Inferred; other classes valued as waste
Copper / Molybdenum / Silver Price US$5.00/lb / US$25.00/lb / US$50.00/troy oz
Copper / Molybdenum / Silver Payability 96.5% / 99.0% / 92.5%
Copper / Molybdenum Concentrate Grade 28% Cu / 55% Mo, dry mass
Concentrate Moisture 8%, wet mass
Copper Treatment Charge US$40.00/dry st concentrate
Copper Refining Charge US$0.04/lb contained copper in concentrate
Copper Concentrate Freight US$115.00/wet st concentrate
Molybdenum Roasting Charge US$1.25/payable lb Mo
Molybdenum Concentrate Freight US$75.00/wet st concentrate
Rhenium In Molybdenum Concentrate 25 ppm; 25% payable; US$2,250.00/payable lb Re
Silver Refining Charge US$0.00/payable oz
Net Copper / Molybdenum / Silver Price US$4.49/lb / US$23.46/lb / US$46.25/oz recovered metal
Metallurgical Recovery Domain-specific recovery; see Table 10-2
Mining And Haulage US$1.80/st total pit material

 

153
 

 

Input Value or Basis
Crushing and Sorting US$1.35/st accepted crusher feed
Mill Processing US$6.32/st mill feed
Tailings US$0.18/st mill feed
General and Administrative US$0.35/st mill feed
Environmental US$0.04/st mill feed
Middlings Placement / Reclaim US$0.82/st placed / US$0.82/st reclaimed
Reject Placement US$0.82/st rejected
Total Direct-Mill Route Treatment US$8.23/st direct mill feed
Total Middlings Route Treatment US$9.87/st middlings treated
Total Reject Route Treatment US$2.17/st rejected material
Revenue Factors 0.20–1.08 in increments of 0.02
Overall Slope Assumptions 42° at 0–1,000 ft depth; 40° at 1,000–2,000 ft; 35° below 2,000 ft
Pit-Valuation Discount Rate 8% per year
Pit-Valuation Production Rates 70 Mstpa feed, 90 Mstpa waste, 160 Mstpa total

Source: NLM (2026). Note. Overall slope angles were assigned in three domains. The geotechnical recommendations are presented in Table 13-10. Note. ft = feet, lb = pound, Mst = million short tons, Mstpa = million short tons per year, oz = troy ounce, st = short ton

 

Pit valuation assumes eventual treatment of the modeled middlings at fixed annual feed and waste rates. Capital expenditure and taxes are excluded. The project cash flows in Section 19 use the production schedule, stockpile timing, and detailed cost estimate.

 

The optimization evaluated 45 revenue factors between 0.20 and 1.08. Each pit was scheduled and the resulting uncapitalized discounted cash flow (DCF) was tabulated at the study metal prices and an 8% discount rate, using best-case and worst-case mining sequences. The best-case mines successive nested pits, each from top down. The worst case completes each bench across the final pit before advancing to the next bench. These sequences indicate the effect of mining order on discounted value. The average is the arithmetic mean of the two cases. Figure 13-4 and Figure 13-5 show the value curves, material quantities and incremental stripping for the pit shells containing material.

 

Average discounted pit value peaks at a revenue factor of 0.52 and then declines gradually as the pit expands. The alternatives from 0.50 to 0.60 bracket the design tonnage and are summarized in Table 13-12. Material quantities for every shell are evaluated at the study economic assumptions, so they can be compared on a consistent basis.

 

154
 

 

 

Source: NLM (2026).

 

Note. Feed and waste are classified economically at the study base-price assumptions using the best-case sequence. These are full-block classifications, not crusher-feed quantities.

 

Figure 13-4 Discounted Pit Value and Material Quantities

 

 

Source: NLM (2026).

 

Note. Incremental stripping is the additional waste divided by additional economically classified feed between successive pit shells, using best-case inventories.

 

Figure 13-5 Discounted Pit Value and Incremental Stripping

 

155
 

 

Table 13-12 Pit-Shell Response Near the Design Limits

 

Revenue Factor Best-Case Total Material (Mst) Worst-Case DCF at 8% (US$M) Best-Case DCF at 8% (US$M)

Average DCF at 8%

(US$M)

0.50 2,309 5,998 7,640 6,819
0.52 2,607 5,817 7,847 6,832
0.54 2,949 5,480 8,005 6,743
0.56 3,165 5,271 8,082 6,677
0.58 3,336 4,894 8,093 6,494
0.60 3,550 4,939 8,168 6,553

Source: NLM (2026). Note. Discounted pit values exclude capital and taxes and are used to compare pit limits. Total material is from the best-case sequence. The valuation qualifications above apply. DCF = uncapitalized discounted cash flow, Mst = million short ton, US$M = U.S. dollars in millions

 

13.4.2Pit Designs Used in the Production Schedule

 

Whittle’s preferred pit contains 2,824 Mst. NLM incorporated ramps, working widths and bench geometry into the phase designs used in the production schedule, following the Whittle development sequence and NLM pit-optimization evaluations. Designed excavation totals 3,083 Mst, 9.17% above the Whittle inventory. Table 13-13 compares the Whittle pit, the independently generated reference shell and the mine design before sorting.

 

The shell generated at a revenue factor of 0.56 has a base-price valuation inventory of 3,165 Mst and provides the closest tonnage match to the design. It exceeds designed excavation by 81.7 Mst, or 2.65% of the design tonnage. Its average discounted pit value is US$6,677 million, equal to 97.7% of the maximum at a revenue factor of 0.52.

 

Expansion from the 0.52 shell to the 0.56 shell adds 558 Mst while average discounted pit value falls by US$155 million, or 2.27%. The broad value peak and similar mining extent provide a preliminary comparison with the pit designs used for this IA. Enlarging the pit beyond this range adds excavation with generally declining average value. The reference shell provides a comparison of scale and value sensitivity; the mine design incorporates the access and working geometry required for production.

 

The comparison is based on total pit material, including waste. The Whittle inventory uses full resource blocks, the optimization uses 100-ft blocks, and the design includes practical mining geometry. These differences affect the reported tonnages. Crusher and mill-feed quantities after sorting are reported separately in Sections 13.5 and 13.6.

 

Table 13-13 Whittle Pit Optimization Shell and Mine-Design Comparison

 

Inventory Unit Whittle Preferred Pit Optimization Reference Shell Mine Design
Total Pit Material Mst 2,824 3,165 3,083

Source: Whittle Consulting (2025) and NLM (2026). Note. Mst = million short ton

 

13.4.3Pit Design and Main Mining Phases

 

Six main phases develop the pit from the starter excavation to the ultimate limits. Phase 1 is approximately 3,000 by 2,400 ft in plan, with a pit bottom at 5,725 ft and a highwall height of 1,050 ft. Phase 6 forms the ultimate pit, approximately 7,200 by 7,000 ft in plan, with a pit-bottom elevation of approximately 3,975 ft. Table 13-14 gives the incremental quantities in the six main phases.

 

156
 

 

Phases 3 and 6 are each divided into three scheduling phases; Phases 4 and 5 are each divided into two. These smaller scheduling phases release mineralized material and distribute stripping within the larger designs. Their bench-by-year sequence is presented in Section 13.6.1. Figure 13-6 shows the six main phase designs in plan view. Figure 13-7 shows the ultimate pit in plan view.

 

Table 13-14 Main Mining-Phase Quantities

 

Main Phase

Total Mass

(Mst)

Crusher/ROM Feed (Mst) Waste and Construction Rock (Mst)

Waste/Feed

(st/st)

1 77 45 32 0.72
2 140 100 39 0.39
3 377 206 171 0.83
4 403 187 217 1.16
5 718 302 417 1.38
6 1,368 561 807 1.44
Total 3,083 1,401 1,682 1.20

Source: NLM (2026). Note. Quantities are incremental by main phase. Feed is material retained for crusher delivery or ROM stockpiling after loading-face selection and routing. The ratio is mining-stage waste and construction rock divided by retained feed.

Mst = million short ton, st = short ton

 

Phases 1 and 2 are opened during pre-production and supply the initial mining years. Phase 3 starts in Year 1 and is completed in Year 6. Phase 4 begins in Year 3 and continues through Year 9, maintaining feed supply as the earlier phases are completed.

 

Phase 5 is mined during Years 6–16. Phase 6 starts in Year 7 and continues through pit completion in Year 22. Several phases are mined concurrently to supply mineralized feed while stripping later mining areas. Table 13-21 and Table 13-22 show the timing and bench advance of the twelve scheduling phases.

 

Mining advances on 50-ft benches from the upper mining areas at 7,025 ft to the ultimate pit bottom at 3,975 ft. Maximum annual advance is six to ten benches, or 300 to 500 ft, depending on the scheduling phase. Section 13.6.1 presents the bench sequence and maximum advance by phase.

 

157
 

 

 

Note. Grid coordinates and elevations are in feet. Source: NLM (2026)

 

Figure 13-6 Main Mining-Phase Designs in Plan View

 

158
 

 

 

Note. Grid coordinates and elevations are in feet. Source: NLM (2026)

 

Figure 13-7 Main Mining-Ultimate Pit Design in Plan View

 

13.4.4Working Widths and Haul Roads

 

The main pit ramp exits on the southwest side of the pit (Figure 13-6). Surface haul roads connect the pit with the crusher area and ROM stockpile west of the pit and the Charlotte Gulch waste-rock storage facility to the south and southwest. The haul road continues south to the tailings embankment, as shown in Figure 13-1.

 

Pit access development is required to establish the haulage connections. Planned works include a cut-and-fill road to the tailings area, a ramp serving the lower elevations of the Charlotte Gulch waste-rock storage facility, and a ramp connecting the crusher and processing areas. A waste-rock platform is constructed for ROM storage.

 

The mine uses a minimum operating width of 400 ft to accommodate the large shovel-and-truck loading arrangement. Haul-roads were designed at a width of 130 ft for two-way ramps and 100 ft for one-way ramps. The road widths include allowances for a safety-berm and drainage. Table 13-15 summarizes the operating-width and haul-road criteria used in the mine design.

 

159
 

 

Table 13-15 IA Mining-Access Criteria

 

Criterion Unit Value
Minimum Mining Width ft 400
Two-Way Ramp Width ft 130
One-Way Ramp Width ft 100
Maximum Ramp Gradient % 10
Pit-Bottom Ramp Gradient % 12
Switchback Inside Radius ft 60

Source: NLM (2026).

 

Main ramps have a maximum gradient of 10%; pit-bottom access allows 12%. The inside switchback radius is 60 ft. Haulage cycle times account for loading and dumping, travel from the block mined to the ramp, along the ramps, and the route to each destination. As mining deepens, longer ramp travel increases truck hours for a given tonnage. Embankment construction and waste placement also change the haul routes.

 

13.5Material Routing and Storage

 

13.5.1Sorting and Mill Feed Selection

 

Loading-face sorting is followed by primary crushing and two belt-sorting stages. The first belt stage produces mill feed, middlings for further sorting and rejects. The second stage produces additional mill feed, middlings and rejects. Table 13-16 summarizes the resulting mass distribution.

 

Table 13-16 Life-of-Operation Crusher and Sorter Material Distribution

 

Stream After Crushing and Sorting

Quantity

(Mst)

Share of Crusher Feed (%)
Sorter Products to Mill 447 31.9
Middlings Stockpile Receipts 685 48.9
Rejects to Waste 269 19.2
Total Crusher Feed 1,401 100.0

Source: NLM (2026). Note. Shares describe mass distribution, not metal recovery. Subsequent middlings reclaim is excluded from this distribution because it is a withdrawal of material already counted in stockpile receipts.

 

The overall mine and storage layout is shown in Figure 13-1. Section 14.2 describes the sorting circuit and process material balance.

 

Approximately 32% of crusher feed reports as sorter products to the mill, 49% enters the middlings stockpile and 19% is rejected to waste. The material distribution is summarized in Table 13-16. Metallurgical recovery is applied to metal in mill feed. The scheduling recoveries are summarized in Table 13-5. Processing methods are described in Section 14.

 

160
 

 

13.5.2ROM and Middlings Stockpiles

 

The ROM stockpile has a storage capacity of 20 Mst and buffers mineralized-material delivery ahead of crushing. It contains 1.8 Mst at the end of pre-production, increases to 10 Mst by Year 3 and remains near that level through Year 19. Reclaim increases as pit production tapers, and the remaining ROM material supplies crushing in Years 23–24. The ROM stock is essentially exhausted by the end of Year 24.

 

The middlings stockpile receives sorter products during pit mining and supplies the mill when direct products or blend requirements call for reclaim. Reclaim begins in Year 9 at 6.1 Mst. Total receipts are 685 Mst, with peak storage of 617 Mst in Year 21. Figure 13-8 shows the inventory profile against the 645-Mst capacity, providing 28 Mst of unused capacity at peak inventory. The ROM stockpile is a separate facility. Table 13-17 summarizes stockpile movements and closing inventories at selected production milestones.

 

Table 13-17 Stockpile Movements and Inventories at Production Milestones

 

Year Middlings Receipts (Mst) Middlings Reclaim (Mst) Middlings Closing (Mst)

ROM Closing

(Mst)

-1 0.0 0.0 0.0 1.8
1 27.5 0.0 27.5 1.6
5 34.7 0.0 201.3 10.0
9 33.3 6.1 326.4 10.0
18 1.1 22.9 551.1 10.0
21 17.1 2.9 617.1 5.3
22 15.7 17.1 615.7 8.7
24 0.2 25.4 567.1 0.0
30 0.0 25.6 413.8 0.0
40 0.0 25.6 158.3 0.0
46 0.0 25.6 5.0 0.0

 

Source: NLM (2026). Note. Closing inventories are shown. Middlings receipts are sorter products; reclaim supplies the mill. The final 5.0 Mst remains unprocessed. Mst = million short ton, ROM = run-of-mine

 

At pit completion in Year 22, the middlings stockpile contains 616 Mst. It supplies 25.55 Mstpa of mill feed during Years 25–46. The final 5.0-Mst balance remains unprocessed in the IA.

 

161
 

 

 

Source: NLM (2026)

 

Figure 13-8 Middlings Stockpile Inventory Profile

 

Middlings remain in storage for an extended period before treatment. Aging, oxidation and degradation may affect recovery and reclaim conditions. Testing of these effects is recommended in Section 23. The IA assumes no storage-related reduction in metallurgical recovery.

 

13.5.3Waste Rock and Embankment Construction

 

Pit waste is hauled to the tailings embankment and the Charlotte Gulch waste-rock storage facility. The embankment receives 870 Mst. Charlotte Gulch receives approximately 812 Mst of pit waste and 269 Mst of sorter rejects, for total placement of approximately 1,081 Mst. Table 13-18 summarizes waste and tailings placement and peak stockpile inventories.

 

Table 13-18 Planned Material-Storage and Construction Quantities

 

Facility Planned Quantity (Mst) Total Capacity (Mst)

Capacity Used

(%)

Tailings Embankment 870 870 100
Tailings Storage 1,127 1,150 98
Charlotte Gulch Waste-Rock Storage 1,081 1,092 99
ROM Stockpile 10 20 50
Middlings Stockpile 617 645 96

 

Source: NLM (2026). Note. Quantities are cumulative placement for waste and tailings and peak inventory for the ROM and middlings stockpiles. Mst = million short ton

 

162
 

 

The initial facility layout in Figure 13-9 shows tailings and embankment elevations of 5,995 ft and 6,000 ft. Progressive raises increase these elevations to 6,695 ft and 6,700 ft at final buildout, shown in Figure 13-10. These layouts show the major mining-related facilities. Facility design, staged embankment construction, site preparation, water management, and site infrastructure, including the tailings pipeline, are described in Section 15.

 

 

Note. Grid coordinates and elevations are in feet. Source: NLM (2026)

 

Figure 13-9 Initial Site Facility Layout

 

163
 

 

 

Note. Grid coordinates and elevations are in feet. For facility identification, see Figure 13-1. Source: NLM (2026)

 

Figure 13-10 Final Site Facility Layout

 

13.6Production Schedule and Mining Sequence

 

Primary mining reaches 160 Mstpa, crushing and sorting up to 70 Mstpa, and milling 25.6 Mstpa. Middlings accumulate because sorter production exceeds mill capacity during pit mining. Their subsequent reclaim supplies the mill after pit completion.

 

164
 

 

The production schedule was developed using MinePlan™ Schedule Optimizer to maximize discounted value. Phase and bench precedences control the release of material. Limits on active mining areas and vertical advance govern the progression of the scheduling phases. Crusher and mill capacities constrain treatment, with ROM and middlings stockpiles carrying material between years.

 

Pre-production Year −1 excavates 37 Mst, including 36 Mst of primary waste and construction rock and 1.8 Mst placed in ROM stock. This establishes the initial mining areas and provides construction rock before mill operation. Primary excavation then increases to 75 Mst in Year 1, 110 Mst in Year 2 and 150 Mst in Year 3. The 160-Mstpa plateau begins in Year 4 and continues through Year 18.

 

Mill feed ramps from 9.0 Mst in Year 1 to 12.8 Mst in each of Years 2 and 3, 19.2 Mst in Year 4 and 25.6 Mst in Year 5. Sorter products supply the early mill feed while middlings inventory accumulates. Mining several phases concurrently maintains the range of material sources required by the mining and sorting plan. Annual primary excavation and downstream feed during the pit-mining years are presented in Table 13-19.

 

Table 13-19 Annual Primary Excavation and Feed During Pit Mining

 

Year Primary Excavation (Mst) Mineralized Material (Mst) Primary Waste (Mst) Crusher Feed (Mst)

Mill Feed

(Mst)

-1 37.3 1.8 35.5 0.0 0.0
1 75.0 45.0 30.0 45.1 9.0
2 110.0 76.1 33.9 68.3 12.8
3 150.0 70.5 79.5 70.0 12.8
4 160.0 70.0 90.0 70.0 19.2
5 160.0 70.0 90.0 70.0 25.6
6 160.0 70.0 90.0 70.0 25.6
7 160.0 70.0 90.0 70.0 25.6
8 160.0 70.0 90.0 70.0 25.6
9 160.0 63.9 96.1 63.9 25.6
10 160.0 70.0 90.0 70.0 25.6
11 160.0 70.0 90.0 70.0 25.6
12 160.0 70.0 90.0 70.0 25.6
13 160.0 70.0 90.0 70.0 25.6
14 160.0 64.8 95.2 64.8 25.6
15 160.0 67.1 92.9 67.1 25.6
16 160.0 66.0 94.0 66.0 25.6
17 160.0 70.0 90.0 70.0 25.6
18 160.0 42.1 117.9 42.1 25.6
19 145.0 68.9 76.1 68.9 25.6
20 63.8 53.1 10.7 59.1 25.6
21 59.1 48.4 10.7 47.1 25.6
22 42.9 33.0 9.9 29.6 25.6
Total¹ 3,083 1,401 1,682 1,392 514

 

¹ Totals in this table cover Year −1 and Years 1–22. Crushing and mill treatment continue afterward; their full-operation totals are reported separately. Source: NLM (2026). Note. Scheduled mineralized material includes Measured, Indicated and Inferred Mineral Resources and is not a Mineral Reserve estimate. Primary waste includes embankment construction rock. Crusher feed may include ROM reclaim; mill feed includes sorter products and middlings reclaim. Mst = million short ton

 

165
 

 

Middlings reclaim supplements sorter products when direct feed is insufficient to fill the mill. In Year 9, 6.1 Mst of reclaim is blended with 19.4 Mst of sorter products. In Year 18, the pit mines 160 Mst, but only 42 Mst is mineralized material. Sorter products supply 2.6 Mst of mill feed and reclaim supplies 22.9 Mst.

 

Primary excavation tapers to 145 Mst in Year 19, 64 Mst in Year 20, 59 Mst in Year 21 and 43 Mst in Year 22 as the final phases are completed. Mill feed remains at approximately 25.6 Mstpa. The final pit years require continued stockpile access and reclaim alongside the shrinking primary mining operation, and the mine fleet resources are reassigned to middlings reclaim after primary excavation ends.

 

Years 23 and 24 include final ROM Reclaim. They provide 4.7 Mst and 4.0 Mst of crusher feed, respectively, while middlings reclaim supplies most of the mill feed. From Year 25 through Year 46, the operation processes only the middlings stock. The post-pit period delivers 613 Mst of mill feed, of which approximately 612 Mst is middlings reclaim and 1.1 Mst is ROM-derived sorter product in Years 23–24. The annual mill-feed quantities and grades are given in Table 13-20.

 

Table 13-20 Annual Mill-Feed Sources and Grades

 

Year Sorter Products (Mst) Middlings Reclaim (Mst) Total Mill Feed (Mst) Cu (%) Mo (%) Ag (g/t)
-1 0.0 0.0 0.0 — — —
1 9.0 0.0 9.0 0.16 0.06 4.59
2 12.8 0.0 12.8 0.16 0.07 4.10
3 12.8 0.0 12.8 0.15 0.10 3.62
4 19.2 0.0 19.2 0.14 0.09 3.50
5 25.6 0.0 25.6 0.13 0.06 4.11
6 25.6 0.0 25.6 0.11 0.08 3.00
7 25.6 0.0 25.6 0.12 0.08 3.21
8 25.6 0.0 25.6 0.08 0.10 2.13
9 19.4 6.1 25.6 0.12 0.05 3.50
10 25.6 0.0 25.6 0.11 0.09 3.43
11 25.6 0.0 25.6 0.10 0.09 3.43
12 25.6 0.0 25.6 0.12 0.07 3.08
13 25.6 0.0 25.6 0.17 0.06 4.16
14 20.3 5.2 25.6 0.10 0.06 2.66

 

166
 

 

Year Sorter Products (Mst) Middlings Reclaim (Mst) Total Mill Feed (Mst) Cu (%) Mo (%) Ag (g/t)
15 22.6 2.9 25.6 0.07 0.06 2.27
16 21.5 4.0 25.6 0.05 0.08 1.75
17 25.6 0.0 25.6 0.07 0.10 1.80
18 2.6 22.9 25.6 0.10 0.03 2.39
19 24.4 1.1 25.6 0.17 0.06 4.50
20 19.7 5.9 25.6 0.11 0.07 3.23
21 22.7 2.9 25.6 0.11 0.07 2.94
22 8.4 17.1 25.6 0.09 0.06 2.56
23 0.9 24.6 25.6 0.08 0.03 2.54
24 0.2 25.4 25.6 0.06 0.03 1.72
25 0.0 25.6 25.6 0.10 0.02 2.36
26 0.0 25.6 25.6 0.06 0.02 1.70
27 0.0 25.6 25.6 0.06 0.01 2.07
28 0.0 25.6 25.6 0.03 0.01 2.08
29 0.0 25.6 25.6 0.06 0.02 2.04
30 0.0 25.6 25.6 0.11 0.02 3.24
31 0.0 25.6 25.6 0.08 0.03 2.37
32 0.0 25.6 25.6 0.07 0.03 2.13
33 0.0 25.6 25.6 0.08 0.03 2.30
34 0.0 25.6 25.6 0.09 0.02 2.52
35 0.0 25.6 25.6 0.09 0.02 2.46
36 0.0 25.6 25.6 0.07 0.03 2.07
37 0.0 25.6 25.6 0.11 0.02 3.02
38 0.0 25.6 25.6 0.09 0.02 2.53
39 0.0 25.6 25.6 0.09 0.02 2.60
40 0.0 25.6 25.6 0.10 0.02 2.71
41 0.0 25.6 25.6 0.11 0.02 2.80
42 0.0 25.6 25.6 0.09 0.03 2.47
43 0.0 25.6 25.6 0.11 0.02 2.76
44 0.0 25.6 25.6 0.10 0.02 2.61
45 0.0 25.6 25.6 0.09 0.02 2.58
46 0.0 25.6 25.6 0.10 0.02 3.04
Total 447 680 1,127 0.10 0.05 2.74

 

Source: NLM (2026). Note. Sorter products include products derived from ROM reclaim in Years 23–24. Total-row grades are mass-weighted over all mill feed; annual grades are not averaged arithmetically. Ag = silver, Cu = copper, g/t = grams per metric ton, Mo = molybdenum, Mst = million short tons

 

167
 

 

Life-of-operation mill-feed grades are 0.097% Cu, 0.045% Mo and 2.74 g/t Ag. Grade changes reflect phase contributions, sorter selection, and the reclaim blend. Mill recoveries are described in Section 14, and recovered and payable metal production in Section 19.5.2, Figure 13-11 shows the annual mill-feed grades through pit mining and subsequent stockpile processing.

 

 

Note. Grades are for total mill feed, including stockpile reclaim. Source: NLM ( 2026)

 

Figure 13-11 Annual Mill-Feed Grades

 

168
 

 

Figure 13-12 compares the annual excavation, crusher-feed, and mill-feed profiles.

 

 

Source: NLM (2026)

 

Figure 13-12 Annual Excavation, Crushing and Mill-Feed Profile

 

13.6.1Bench Advance and Phase Sequence

 

Table 13-22 gives the mining year for each bench in each scheduling phase. Multi-year entries indicate benches worked over more than one year. The matrix shows concurrent mining areas and interruptions in their advance. Annual vertical advance is measured from the lowest bench reached in consecutive years, using 50-ft bench intervals. Maximum advances range from six to ten benches, or 300 to 500 ft/year (Table 13-21).

 

Table 13-21 Maximum Annual Bench Advance by Scheduling Phase

 

Metric P1 P2 P3a P3b P3c P4a P4b P5a P5b P6a P6b P6c
Bench intervals/year 9 9 10 9 6 10 10 10 10 10 10 9
Vertical advance (ft/year) 450 450 500 450 300 500 500 500 500 500 500 450

 

Source: NLM (2026). Note. ft = feet

 

169
 

 

Table 13-22 Bench Mining Sequence by Scheduling Phase

 

Bench Elevation (ft) P1 P2 P3a P3b P3c P4a P4b P5a P5b P6a P6b P6c
7025           3   6     7  
6975           3   6     7  
6925           3   6     7  
6875     1     3   6     7  
6825     1     3   6     7, 8  
6775 −1 −1 1     3, 4   6     8  
6725 −1 −1 1     4   7     8, 12  
6675 −1 −1 1     4 4 7 10   12  
6625 −1 −1 2     4 4 7 10   12  
6575 −1 −1 2     4 4 7 10   13  
6525 −1 −1 2     4 5 7 10   13  
6475 −1 −1 2     4 5 7 10 8 13  
6425 −1 −1 2     4 5 7 10, 11 8 13  
6375 −1 −1 2     4 5 7 11 8 13, 14  
6325 −1, 1 1 2     4 5 7 11 8 14  
6275 1 1 3     5 5 7 11 8 14  
6225 1 1 3     5 5 8 11 8 14  
6175 1 1, 2 3 3   5 5 8 11 8 14 14
6125 1 2 3 3   5 5 8 11 8 14 14
6075 1 2 3 3   5 5 8 11 8 14, 15 16
6025 1 2 3 3, 4   5 6 8 11 8 15 16, 17
5975 1 2 3 4   5 6 8 11 9 15 17
5925 1 2 3 4   5 6 8 12 9 15 17
5875 1 2 3 4   6 6 8 12 9 15 17
5825 2 2 3 4   6 6 8 12 9 15 17
5775 2 2, 3 4 4   6 6 8 12 9 15 17
5725   3 4 4   6 6 9 12 9 15 17
5675   3 4 5   6 6 9 12 9 15 17
5625   3 4 5   6 7 9 12 9 15 17, 18
5575   3 4 5   6 7 9 12 9 16 18
5525   3 4 5   6 7 9 12 9 16 18
5475   3 4 5   6 7 9 12 10 16 18
5425   3 4 5   6, 7 7 9 13 10 16 18
5375   3 4 5   7 7 9 13 10 16 18
5325   3 4, 5 5   7 7 9, 10 13 10 16 18
5275   4 5 5, 6   7 8 10 13 10 16 18
5225       6 6 7 8 10 13 10, 11 16 18, 19
5175       6 6 7 8 10 13 11 16 19
5125       6 6 7 8 10 13 11 16 19
5075         6 7 8 10 13 11 17 19
5025         6 8 8 10 14 11 17 19
4975         6 8 8 10 14 11 17 19
4925         6 8 8 10 14 11 17 19
4875           8 8 10 14 11 17 19
4825           8 8 11 15 11, 12 17 19
4775           8 9 11 15 12 17 19
4725           8 9 11 15, 16 12 17 20
4675             9 11 16 12 17 20
4625             9 11 16 12 17, 19 20
4575               11 16 12 19 21
4525               11 16 12, 13 19, 20 21
4475               11 16 13 20 21
4425                 16 13 20 21
4375                 16 13, 14 20 21
4325                 16 16 20 21
4275                 16   20 22
4225                     20 22
4175                     21, 22 22
4125                       22
4075                       22
4025                       22
3975                       22

 

Source: NLM (2026). Note. Numbers identify the mine-plan years in which a scheduling-phase bench is mined. Color identifies the first mining year. Multiple years in a cell identify a bench mined in more than one year. A blank cell denotes no mining on that bench. ft = feet

 

170
 

 

Production year color legend for Table 13-22:

 

−1 1 2 3 4 5 6 7 8 9 10 11
12 13 14 15 16 17 18 19 20 21 22  

 

13.7Mining Equipment and Operating Basis

 

The mine is owner-operated. Primary loading uses 4100-class electric cable shovels paired with 360-short-ton electric-drive haul trucks. Production and perimeter drills support the 50-ft benches. Crawler and wheel dozers maintain loading and placement areas, graders maintain haul roads, and water trucks provide dust suppression.

 

The plan includes four cable shovels for primary mining. Equipment purchases include additions during ramp-up and subsequent replacements. After primary mining ends, existing primary and support equipment is reused for middlings reclaim where its remaining life permits. The reclaim operation uses two loading shovels drawn from the four units on site; these units are retained and rebuilt, and the estimate does not include late primary-shovel replacement capital. Haulage and support equipment renewals are included in the procurement schedule. Hourly equipment costs include rebuild allowances. Cumulative purchases are summarized in Table 13-23, and the purchase-cost estimate in Section 18.1.1.

 

Table 13-23 Principal Mining Equipment Purchases

 

Equipment Class Duty Year −1 Purchases (units) Operation-Total Purchases (units)
Production Drill: MD6310 / PV291–PV311 Class Production Blast Holes 2 8
D60 Drill Class Perimeter and Trim Drilling 1 3
4100 Cable-Shovel Class Primary Loading 2 4
D10 / D375 Crawler-Dozer Class Mining Support 1 3
900 Horsepower Wheel Dozer Loading-Area Support 1 10
Electric-Drive Haul Truck, 360 st/Load Primary Haulage and Embankment Delivery 10 88
D11 / D475 Crawler-Dozer Class Heavy Dozing and Placement 1 3
Cat 16 Grader Class Haul-Road Maintenance 2 4
20,000 Gallon Water Truck Dust Control 2 4

 

Source: NLM (2026). Note. Purchase quantities include additions and replacements. They are cumulative procurement quantities; the four cable shovels are the primary loading fleet. Equipment models denote estimating classes.

 

The fleet estimate uses the annual material movements and route-dependent haul cycles. Primary haulage includes waste delivery to the embankment and Charlotte Gulch. Separate loading and haulage requirements are calculated for middlings placement and reclaim and sorter-reject disposal.

 

After Year 22, two cable shovels and available primary trucks are assigned to middlings reclaim. Road maintenance, dust control and equipment service continue during this period to support delivery of 25.55 Mstpa to the mill.

 

171
 

 

The annual physical schedule uses 365 days. The operating estimate includes mine management and supervision, mining engineering, geology and grade control, sampling, survey, production operators and maintenance functions. Dispatch, lighting, pumping, fuel and lubrication service, field service and light vehicles support the production fleet. Labor cost assumptions cover employee paid hours separately from machine operating hours and equipment productivity. Table 13-24 gives the calendar hours, availability, utilization and effective operating hours used in the fleet estimate.

 

Table 13-24 Equipment Operating-Hour Criteria

 

Equipment Duty

Calendar

(hours per year)

Availability (%) Utilization (%)

Effective

(hours per year)

Primary Cable Shovel 8,760 92.0 80.0 6,447
Primary Haul Truck 8,760 85.0 75.0 5,585
Production Drill 8,760 90.0 85.0 6,701
Perimeter / Trim Drill 8,760 85.0 70.0 5,212
Rehandle Wheel Loader 8,760 88.0 80.0 6,167
Reused Cable Shovel For Reclaim 3,650 93.0 80.5 2,732
Dedicated Rehandle Haul Truck 8,760 85.0 75.0 5,585
Reused Primary Truck For Reclaim 3,650 85.0 75.0 2,327

 

Source: NLM (2026). Note. Effective hours equal scheduled calendar hours × mechanical availability × utilization of available hours. The 3,650-hour reclaim calendar corresponds to 10 hours per day for 365 days; the full-year calendar corresponds to 24 hours per day.

 

Mine personnel comprise management and administration, engineering and geology, survey and training, equipment operators, drilling and blasting crews, and maintenance personnel. Operating crews are organized into four crews in the labor estimate. Table 13-25 summarizes mine personnel by function at selected points in the mining schedule. Rehandle personnel are allocated to the associated loading and haulage duties in the processing cost estimate.

 

Table 13-25 Mine Workforce by Function

 

Function Year −1 Year 1 Year 4 Year 10 Year 22
Mine Management and Administration 10 11 14 18 10
Engineering, Geology, Survey and Training 28 28 36 36 28
Drilling and Blasting 16 20 36 36 8
Primary Loading 4 8 16 16 4
Primary Haulage 40 64 136 164 68
Mining Support 28 28 52 52 36
Maintenance 40 44 69 79 59
Total Salaried Personnel 44 44 57 65 44
Total Hourly Personnel 122 159 302 336 169
Total Mine Workforce 166 203 359 401 213

 

Source: NLM (2026). Note. Values are total employees across the four crews. Salaried and hourly totals classify the same personnel listed by function.

 

172
 

 

Table 13-26 presents the peak equipment requirements by duty.

 

Table 13-26 Peak Operating Fleet Estimate by Equipment Duty

 

Equipment Class Duty Calculated Peak (units) Whole-Unit Estimate
Production Drills Primary Mining 3.60 4
Perimeter / Trim Drills Primary Mining 1.02 2
4100 Cable Shovels Primary Mining 3.28 4
360-Short Tons Primary Haul Trucks Primary Mining and Embankment Delivery 47.27 48
Large Wheel Loaders Rehandle Loading 3.84 4
Reused Cable Shovels Middlings Reclaim 1.99 2
Dedicated Rehandle Haul Trucks Rehandle Haulage 14.00 14
Reused Primary Haul Trucks Middlings Reclaim 7.56 8

 

Source: NLM (2026). Note. Calculated peak requirements are rounded up to whole units for each duty. Peaks can occur in different years, and the rows are not additive. Reused units are drawn from the primary fleet. The primary loading fleet comprises four cable shovels; two of the four are assigned to reclaim after pit completion.

 

13.8Mining Operations and Services

 

13.8.1Drilling and Blasting

 

Production drilling uses rotary drills in the MD6310 / PV291–PV311 class. Perimeter and trim drilling uses down-the-hole drills. Both patterns are designed for 50-ft benches. Table 13-27 presents the drilling geometry, ammonium nitrate/fuel oil (ANFO) charge and powder-factor criteria used in the mining cost estimate.

 

The production pattern uses 12.25-in holes on a 28-ft burden and 32-ft spacing, with 8 ft of subdrill and 18.5 ft of stemming. The 39.5-ft explosive column contains approximately 1,716 lb of ANFO per hole, equivalent to 0.470 lb/st. The trim pattern uses 6.5-in holes on an 18-ft burden and 20-ft spacing, with 5 ft of subdrill and 10 ft of stemming. The 45-ft explosive column contains approximately 550 lb of ANFO per hole, equivalent to 0.375 lb/st.

 

The drilling calculation applies penetration rates of 200 ft per drilling hour for production holes and 125 ft per drilling hour for trim holes. Drilling time accounts for 50% and 45% of engine hours, respectively. Mechanical availability and utilization are applied separately to establish effective annual operating hours. Blasting and grade-control practices must preserve the material discrimination assumed in the sorting response and provide fragmentation compatible with loading and crushing.

 

173
 

 

Table 13-27 IA Drilling and Blasting Pattern Criteria

 

Parameter Unit Production Perimeter/Trim
Bench Height ft 50 50
Hole Diameter in 12.25 6.50
Burden ft 28 18
Spacing ft 32 20
Subdrill ft 8 5
Total Hole Depth ft 58 55
Stemming Length ft 18.5 10.0
Charge Length ft 39.5 45.0
Explosive Mass Per Hole lb/hole 1,716 550
Calculated Powder Factor lb/st 0.470 0.375
Target Powder-Factor Range lb/st 0.45–0.52 0.30–0.40
Explosive type ANFO ANFO
Rock Density st/bcy 2.20 2.20
Explosive Density lb/ft³ 53.06 53.06

 

Source: NLM (2026). Note. Powder factor is pounds of explosive per short ton of blasted rock. Charge mass is calculated from charge length, hole diameter and explosive density. ANFO = ammonium nitrate/fuel oil, bcy = bank cubic yards, ft = feet, ft3 = cubic foot, lb = pound, st = short ton

 

Detailed final-wall blast design is recommended for the PFS. The design should assess presplit or trim blasting, buffer patterns, charge concentration, initiation timing and vibration control against the rock-mass conditions and catch-berm requirements. The recommended PFS fragmentation, blast-movement and digging trials should establish their effects on loading-face selectivity and the sorting response before the PFS design is developed.

 

13.8.2Grade Control and Material Selection

 

Grade control uses geological interpretation, sampling and survey to define excavation boundaries and material destinations. Loading-face sorting provides additional discrimination before crushing, followed by the two belt-sorting stages. Dig instructions identify mineralized feed, suitable embankment rock and waste.

 

The mining dilution and ore-loss assumptions are described in Section 13.2.2. Blast movement and mixing during excavation must be controlled to achieve the sorting response described in Section 13.2.3.

 

13.8.3Mine Services and Operating Interfaces

 

Mine services maintain roads, loading areas, waste-placement areas and stockpile access throughout the operation. Road grading, dozing and dust suppression support loaded and empty travel, while pumping supports pit-floor conditions. Maintenance planning, field service, fuel and lubrication supply, lighting and dispatch are included in the mining support arrangement. These duties continue during the middlings-processing period where required by reclaim and mill-feed delivery.

 

The mine supplies rock for progressive tailings embankment construction and mineralized feed for crushing and sorting. Sorter products and middlings reclaim supply the mill. Construction-rock investigations should establish physical and geochemical suitability and identify the quantities available by mining phase and period. The PFS production schedule should route suitable mined rock to the tailings impoundment in accordance with the staged embankment construction requirements. Recovery methods are described in Section 14, facility design in Section 15, environmental and closure requirements in Section 17, and capital and operating costs in Section 18.

 

174
 

 

14 Processing and Recovery Methods

 

14.1General

 

The Idaho Copper processing facilities will process ROM (run-of-mine) feed to produce separate copper and molybdenum concentrates, waste rock, and tailings. The process includes crushing the ROM feed, sorting, grinding, bulk rougher flotation, regrinding, bulk cleaner flotation, molybdenum separation, molybdenum purification, and dewatering of copper and molybdenum concentrates. The copper concentrate (containing silver) will be trucked from site for downstream processing at another facility outside the scope of this report. Likewise, the molybdenum concentrate (containing rhenium) will be dried and packaged for shipment to molybdenum roasting processors. The flotation tailings will be thickened before pumping to the TSF.

 

The two-phase design includes an initial 35,000 stpd grinding line and flotation circuit that will later be expanded to a 70,000 stpd circuit in year 4. The process will consist of conventional grinding, flotation, and dewatering equipment. The equipment will be controlled by an industrial standard control system.

 

As shown in Figure 14-1, the primary gyratory crusher will process ROM ore and feed the stage 2 ore sorting plant. The stage 2 ore sorting plant will produce a waste stream which is hauled by mine trucks to the waste dump, a high-grade stream which feeds the grinding circuit, and a middlings stream which feeds the stage 3 ore sorting plant. The stage 3 ore sorting plant produces a waste stream which is also hauled to the waste dump, a high-grade stream which joins the stage 2 high-grade stream and feeds the grinding circuit, and a middlings stream which will be hauled by mine trucks to the middlings stockpile. The middlings stockpile will be reclaimed by mine equipment and fed to the coarse ore stockpile during times of low mine production and after the end of the mining operation.

 

The grinding circuit will consist of a SAG mill, two pebble crushers, two ball mills, and cyclones to produce a grind size of 63 microns. Conventional rougher flotation cells will produce a rougher concentrate which feeds the regrind circuit and tailings which will report to the tailings thickeners. The regrind cyclone overflow feeds conventional cleaner flotation cells which will produce a cleaner concentrate that feeds the molybdenum flotation circuit and tailings which will join the rougher flotation tailings and feed the tailings thickeners. The tailings thickener underflow is pumped to the tailings storage facility, and the tailings thickener overflow is recycled to the plant water dam. The copper minerals will be depressed in the molybdenum flotation circuit while the molybdenum minerals are floated into a concentrate. The molybdenum flotation tailings will become the copper concentrate which is filtered to produce a moisture content suitable for shipment. The molybdenum flotation concentrate is leached in a ferric chloride circuit to reduce the copper content prior to filtering, drying, and packaging for shipment. Copper recovered from the ferric chloride leach circuit will be recovered in the copper dewatering circuit.

 

175
 

 

 

Figure 14-1 Block Flow Process Schematic from ROM Ore through Products and Tailings

 

176
 

 

14.2Sorting Methods

 

Barr’s process QP reviewed the information and methodology provided by Lycopodium for the development of the ore-sorting response and inclusion in the crusher circuit and process plant concept for the current IA.

 

14.2.1Overview of Bulk Ore Sorting Application

 

A three-stage Bulk Ore Sorting (BOS) circuit is envisioned for the CuMo project, with the objective of rejecting waste and stockpiling low-grade material, reducing downstream process plant throughput, and upgrading the final mill feed. For the representative design case, approximately 467,500 stpd (19,482 short tons per hour [stph]) of ROM ore is the mining rate for the maximum tonnage processed through BOS Stage 1. The BOS Stage 1 sorting, supplemented by traditional ore control in known waste material, feeds a projected 191,000 stpd (7,958 stph) with a maximum capacity of 256,700 stpd (10,654 stph) to crushing and BOS stages 2 and 3, resulting in a final mill feed when the mill is expanded to a full process capacity of approximately 70,000 stpd (3,889 stph) at 0.115% copper (Cu) and 0.090% molybdenum (Mo).

 

This will represent an overall throughput reduction of approximately 84%, with 16% of the ROM mass reporting to the milling circuit. The head grades in mill feed are expected to be 0.110% Cu and 0.090% Mo, corresponding to upgrade ratios of 1.6 for Cu and 3.4 for Mo grades. The mill feed ore will have approximately 1.09% Cu-Equivalent and 0.10% Mo-Equivalent, on a price-only basis.

 

14.2.2Bulk Ore Sorting Process Design

 

The BOS plant / process design for the CuMo project is based on a 24-year mine plan and 46-year total production schedule, with particular focus on Period 11 of the production schedule as the representative design case. In this design basis, involves processing of nearly 467,500 stpd (19,482 stph) of run-of-mine (ROM) ore through the BOS stage 1 system and traditional ore control of known waste material. Accepted ore material is truck hauled to the crushing circuit at a projected feed of 191,000 stpd (7,958 stph) (maximum capacity of 256,700 stpd [10,654 stph]) for further processing through the BOS stage 2 and BOS stage 3 systems. The resulting material is then fed to the milling circuit at a rate of 70,000 stpd (3,889 stph), with sorter system calculated Cu grade of 0.110% and a Mo grade of 0.090%.

 

The proposed flowsheet for the ore sorting circuit consisting of the following:

 

●A BOS stage 1 system at the mine end.
   
●A primary crushing operation to provide crushed product with 80% passing (P80) of 120 mm.
   
●A BOS Stage 2 system to separate the crushed ore into three product streams: primary ore, middlings for stockpiling, and waste material.
   
●A BOS Stage 3 system to further process the stockpiled middlings from the BOS Stage 2 system and separate the material into three product streams: primary ore, middlings for stockpiling, and waste material.

 

The key criteria for equipment selection in this study were suitability for duty and reliability. The plant layout provides ease of access to all equipment for operating and maintenance requirements, while in turn maintaining a layout that will facilitate construction progress in multiple areas concurrently.

 

177
 

 

The key project design criteria for the plant were:

 

●ROM throughput at 160 Mtpa, with pit Cu and Mo feed grades of 0.071% and 0.026%, respectively.
   
●Primary crushing circuit operating at 75% utilization
   
●Milling circuit feeding rate of 25.6 Mtpa, at 0.110% Cu and 0.090% Mo feed grades.

 

An overall process flow diagram depicting the BOS and materials handling unit operations incorporated in the selected process flowsheet is presented in Figure 14-2.

 

178
 

 

 

Figure 14-2 Ore Sorting Overall Flow Diagram

 

179
 

 

14.2.2.1Ore Sorter Design Criteria

 

The key process design criteria are listed in Table 14-1.

 

Table 14-1 Summary of the Ore Sorter Process Design Criteria

 

Process Design Parameters Units Parameters
BOS Stage 1 Feeding Rate dry stph 19,482
Head Grade - Design % Cu 0.071
% Mo 0.026
BOS Stage 1 Recovery
Accept % 43.8
Rejects - Waste % 56.3
BOS Stage 2 Feeding Rate dry stph 10,654
BOS Stage 2 Recovery
Primary % 32.8
Middlings % 59.1
Rejects - Waste % 8.1
Crushed Product Size, P80 mm 120
BOS Stage 3 Feeding Rate dry stph 6,296
BOS Stage 3 Recovery
Primary % 6.3
Middlings % 85.1
Rejects - Waste % 8.6
Milling Circuit Feeding Rate dry stph 3,889
Product Grade - Copper % Cu 0.110
Product Grade - Molybdenum % Mo 0.090
Crushed Ore ‘Live’ Stockpile (Residence Time) h 12
Intermediate ‘Live” Stockpile (Residence Time) h 12
Low Grade Ore ‘Dead’ Stockpile (Residence Time) h 24
Waste Rock ‘Dead’ Stockpile (Residence Time) h 24

 

Note. Cu = copper, Mo = molybdenum, stph = short tons per hour

 

14.2.3Sorting Plant Description

 

The proposed sorting plant design includes the following unit operations:

 

●A BOS stage 1 system, comprising primary loading / excavating machines (shovels) and BOS sensors mounted in the shovel buckets.
   
●A crushing circuit to provide crushed product with 80% passing (P80) of 120 mm.

 

180
 

 

●A crushed ore stockpile, that serves as a buffer to control the feed rate to the downstream BOS stage 2 system and split the total flow into four streams to maintain feed within the BOS system requirements, in terms of maximum conveyor material bed depth.

 

●A BOS stage 2 system, comprising two sub-stages of analyzers, stage 2 (I) and stage 2 (II), to analyze and sort the reclaimed material from the crushed ore stockpiles. BOS stage 2 (I) analyzers will sort and divert the product stream into primary and reject material. The reject stream will be fed to the BOS stage 2 (II) analyzers to further sort and divert the material into two streams, stockpile / middlings and waste material.

 

●An intermediate stockpile to store stockpile / middling material coming from the BOS stage 2 (II) system, will serves as a buffer to control the feed rate to the downstream BOS stage 3 system and split the total flow into two streams to maintain the feed within the BOS system feed requirements, in terms of maximum conveyor material bed depth.

 

●A BOS stage 3 system, comprising two sub-stages of analyzers, stage 3 (I) and stage 3 (II), to analyze and sort reclaimed material from the intermediate stockpile. BOS stage 3 (I) analyzers will sort and divert the product stream into primary and reject material. The reject material stream will be fed to BOS stage 3 (II) analyzers to further sort and divert the material into two streams, stockpile / middlings and waste material.

 

●A low-grade ore stockpile to store stockpile/middling material coming from the BOS stage 3 (II) system.

 

●A waste rock facility to store Rejects and waste materials coming from all BOS systems.

 

14.2.3.1Bulk Ore Sorting – Stage 1

 

The open-pit mined material will be processed by shovel sorting method in the BOS stage 1 system.

 

The BOS stage 1 system will comprise a shovel equipped with a bucket-mounted sensor system. The sensor will use X-Ray Fluorescence (XRF) technology to scan the materials dynamically as the shovel bucket gets filled and estimate the grade and characteristics of the materials on a bucket-by-bucket basis.

 

The sensor data will be processed in real-time to sort and classify the feed materials based on pre-defined Cu and Mo grades, enabling routing of the excavated materials to the appropriate destinations, such as the downstream crushing station, or the waste rock stockpile.

 

The feed materials will be sorted and diverted into two product streams: Accept and Waste. The Accepted materials (primary and middlings) will be transferred to the crushing circuit using trucks. The Waste materials will be transferred to the waste rock stockpile using trucks.

 

14.2.3.2Particle Ore Sorting – Stage 2 and Stage 3

 

The Accept material from BOS stage 1 system will be further processed by two primary gyratory crushers, with dedicated rock breakers, bins, and primary crushing discharge conveyors. Both of these product discharge conveyors will feed (‘live’) crushed ore stockpile(s) that will serve as a buffer to control the feed rate to the downstream BOS stage 2 system.

 

181
 

 

BOS stage 2 and stage 3 sensors will utilize technology based on Prompt-Gamma-Neutron-Activation-Analysis (PGNAA or equivalent) to continuously measure the elemental composition and Cu and Mo grades of the material as it travels on the conveyors. Neutrons will interact with the ore and generate characteristic gamma rays, which will be detected and analyzed to determine elemental concentrations of Cu and Mo. The measured Cu and Mo grades will then be compared against the pre-defined sorting criteria to classify the material.

 

The primary-crushed material will first be transferred to the (‘live’) crushed ore stockpiles, which will provide an intermediate buffer between the crushing circuit and the downstream BOS stage 2 sorting systems and conveyors for a consistent and controlled feed and the reclaimed material will be split into four separate streams for the conveyor loading to fall within the BOS system capacity requirements. The material from the stockpile will be transferred to the downstream conveyors using apron feeders and sorted using BOS stage 2 system sensors / analyzers with flopper gates in the diverter chute to control the discharge direction of the sorted material.

 

The BOS stage 2 system will comprise of eight analyzers – four BOS stage 2 (I) analyzers installed on the four crushed ore transfer conveyors and the other four BOS stage 2 (II) analyzers installed on the four BOS stage 2 reject transfer conveyors.

 

The feed material will first be sorted using the BOS stage 2 (I) analyzers based on predefined Cu and Mo grades (criteria) and subsequently diverted into two product streams, Primary and Reject. The sorted Primary material of all four BOS stage 2 (I) systems will then be transferred to the BOS total mill quality transfer conveyor via the BOS stage 2 primary transfer conveyor. The Reject material will be further sorted using the BOS stage 2 (II) analyzers based on predefined Cu and Mo grades (criteria) and subsequently diverted into two streams, stockpile / middlings and waste.

 

The stockpile / middlings material will be transferred to the (‘live’) intermediate stockpile via two intermediate stockpile feed conveyors, while the Waste material will be transferred via one BOS stage 2 waste transfer conveyor onto the waste discharge conveyor that will ultimately feed the waste rock stockpile. The material from the intermediate stockpile feed conveyors will pass through the intermediate stockpile feed shuttle conveyors, prior to discharging on the intermediate stockpile.

 

The (‘live’) intermediate stockpile, containing the stockpile / middlings from the BOS stage 2 system, will act as an intermediate buffer between the BOS stage 2 system and the downstream BOS stage 3 system for a consistent and controlled feed. The reclaimed material will be split into two separate streams so that the loading on each conveyor falls within the BOS system capacity requirements. The material from the stockpile will be transferred to the downstream conveyors using apron feeders and sorted using BOS stage 3 system sensors / analyzers.

 

The BOS stage 3 system will comprise of four analyzers – two BOS stage 3 (I) analyzers installed on the two BOS stage 3 feed conveyors and the other two BOS stage 3 (II) analyzers installed on the two BOS Stage 3 reject transfer conveyors.

 

The feed material will first be sorted using the BOS stage 3 (I) analyzers based on predefined Cu and Mo grades (criteria) and subsequently diverted into two product streams, Primary and Reject. The sorted Primary material of the two BOS stage 3 (I) systems will then be transferred to the BOS total mill quality transfer conveyor via the BOS stage 3 primary transfer conveyor. The Reject material will be further sorted using the BOS stage 3 (II) Analyzers based on predefined Cu and Mo grades (criteria) and subsequently diverted into two streams, stockpile / middlings and waste. The stockpile / middlings material will be transferred to the low-grade ore stockpile via one low grade ore stockpile feed conveyor, while the waste material will be transferred via one BOS stage 3 waste transfer conveyor onto the waste discharge conveyor that will ultimately feed the waste rock stockpile. The material from the low-grade ore stockpile feed conveyor will pass through the low-grade ore stockpile feed shuttle conveyor, prior to discharging onto the low-grade ore stockpile.

 

182
 

 

Following classification, the classified material will continue along the conveyor to the material diversion point which will typically be located at least 30 seconds of conveyor travel time downstream from the analyzer. Based on the PGNAA analyzer output, the control system will actuate the flop gate at the appropriate time to direct the identified material into one of two product streams – Accept material and Reject material. The flop gate operation will be coordinated with the conveyor travel time between the analyzer, and the diversion point to ensure that each classified portion of material will be directed to the correct stream.

 

The BOS stage 3 stockpile / middlings will be transferred to a (‘dead’) low grade ore stockpile for storage which will serve as future mill feed or potential heap leaching. The waste material from the BOS stage 2 and BOS stage 3 systems will be transferred to a (‘dead’) waste rock stockpile using dedicated conveyors. The waste material will be rehandled and hauled to the waste rock storage facility.

 

14.2.3.3Feed to Milling Circuit

 

Feed to the milling circuit will combine the Primary materials from the crushed ore transfer conveyors (with BOS stage 2 (I) Analyzers) and the BOS stage 3 feed conveyors (with BOS stage 3 (I) analyzers). The combined materials will be the transferred to the milling circuit using one BOS total primary transfer conveyor.

 

14.3Mill Design Criteria Summary

 

The key project and specific criteria for the plant design and operating costs are provided in Table 14-2.

 

Table 14-2 Summary of the Process Plant Design Criteria (70 kstpd)

 

Criterion Units Value
Sort Feed Capacity kstpd 200
Mst/y 70
Primary Crusher Availability % 75
Primary Crusher Feed stph 5,555
Primary Crusher Selection Size (inch) 60 x 110
No. 2
Mill Feed (annual) Mst/y 25.55
Mill Grinding and Flotation Availability % 92
Mill Feed (hourly instantaneous) stph 3,170
Total Power requirement MW 92
Grind Size P80 (microns) 63
Head Grade %Cu 0.097
%MoS2 0.045
ppm Ag 2.87

 

183
 

 

Criterion Units Value
Cu Circuit Residence Time
Roughers Minutes 27.5
Cleaner 1 Minutes 10
Cleaner Scav. Minutes 2.5
Cleaner 2 Minutes 10
Cleaner 3 Minutes 5
Mo Circuit Residence Time
Roughers Minutes 35
Cleaner 1 Minutes 25
Cleaner Scav. Minutes 25
Cleaner 2 Minutes 25
Cleaner 3 Minutes 25

 

Note. Cu = copper, kstpd = kilo-short tons per day, Mo = molybdenum, MoS2 = molybdenite, Mst/y = million short tons per year, MW = megawatt, ppm Ag = parts per million silver, stph = short tons per hour

 

Detailed process design criteria incorporating the process mass balance, engineering design criteria, and key sizing criteria derived from the results of the metallurgical test-work program were determined and are summarized below.

 

14.4Mill Design Basis

 

A 35,000 stpd mill was designed to process upgraded ore from the CuMo deposit. This design is expanded to 70,000 stpd by adding an additional grinding line, flotation, and dewatering equipment in year 4. The mill will operate two shifts per day, 365 days per year, with an overall availability of 92%.

 

14.5Flow Sheet Development and Equipment Sizing

 

14.5.1Primary Crushing

 

Two 60” x 110” gyratory crushers will receive 200,000 stpd of ROM feed. The crushers will crush from a top size of 1,524 mm to a P80 of 120 mm. The crushers will be fed by direct tipping haul trucks, and rock breakers will be available to break oversized material. After the primary crushing the material will be conveyed into the sorting plant where it will be sorted into waste, middlings, and high-grade streams.

 

14.5.2Bulk Sorting and Preconcentration

 

The bulk sorting proposes XRF technology to sort the feed to the process. This is discussed in further detail in Section 14.2. Shovel sorting at the mine dig face will produce the following two streams: 1) waste that will be hauled directly to waste storage facility (or TSF embankment), and 2) sorter feed which will be hauled to the primary crushers.

 

184
 

 

The stage 2 sorting produces primary, middling, and reject (waste) streams. The primary are directed to the plant and rejects are fed to the appropriate stockpiles for haul to the waste storage facility, and the middling stream feeds the stage 3 sorting plant. The stage 3 sorting plant also produces primary, middling, and reject streams. The primary are directed to the plant and rejects join the appropriate stream from the stage 2 plant and are hauled to the waste rock facility. The stage 3 middling stream is conveyed to the middlings stockpile. Ore sorting produces three products:

 

1.Primary - Ore grade is significantly above economic viability (feed to mill)
2.Rejects - Ore grade is significantly below economic viability (send to waste pile)
3.Middlings – Ore grade acceptable for processing at a later date

 

14.5.3Stockpiling

 

The ore product from bulk sorting is conveyed to the coarse ore stockpile which feeds the SAG mills. Three apron feeders per line are used to feed material into the SAG mills.

 

Waste rock from the mine and sorting is used in the tailings storage facility (TSF) embankment and in the waste rock facility (WRF) located near the pit. The middling stockpile is reclaimed by mine equipment and hauled to a dump. The middling dump will be reclaimed by mining equipment and fed to the mill.

 

14.5.4SAG and Ball Mills

 

Each 35,000 stpd line will have a 15 MW SAG mill (34 ft diameter and 20 ft length) in closed circuit with vibrating screens and two 94-inch pebble crushers. The pebble crusher product will be conveyed to the mill feed conveyor.

 

The discharge from the SAG mill grinding circuit will feed two ball mills per line (24 ft diameter and 40 ft length) in closed circuit with hydrocyclones to produce a product grind size P80 of 63 µm.

 

14.5.5Bulk Flotation

 

Bulk flotation will recover a combination of copper, molybdenum, rhenium, and silver. The estimated equipment consists of:

 

●Bulk rougher flotation in ten 200 m3 forced air tank cells per phase that provide 28 minutes of flotation time

 

●Rougher concentrate is reground in three vertical stirred mills to a P80 of 10 µm

 

●Bulk cleaner 1 and the cleaner scavenger consist of 20 m3 forced air tank flotation cells that provide a total of 13 minutes of retention time

 

●Bulk cleaner 2 flotation cells consist of 8 m3 cells that provide ten minutes of retention time

 

●Bulk cleaner 3 flotation cells consist of 8 m3 flotation cells that provide five minutes of retention time

 

●Concentrate thickener to remove moisture from the bulk concentrate

 

185
 

 

14.5.6Molybdenum Flotation

 

The bulk concentrate is fed to the molybdenum flotation circuit where the molybdenum and rhenium is selectively floated from the copper and silver. Tailings from this circuit become the copper concentrate.

 

The flotation circuit consists of the following pieces of equipment:

 

●Molybdenum rougher flotation consisting of 8 m3 cells that provide a total of 35 minutes of retention time

 

●Molybdenum cleaner 1 flotation that provides a total of 25 minutes of retention time

 

●Molybdenum cleaner 2 flotation that provides a total of 25 minutes of retention time

 

●Molybdenum cleaner 3 flotation cells that provide a total of 25 minutes retention time

 

14.5.7Copper Concentrate

 

The copper-silver concentrate is the reject from the molybdenum concentration circuit. The concentrate will be thickened in a high-rate thickener and filtered in a vertical plate and frame pressure filter to ~10% moisture. The filtered concentrate will be stored in a stockpile before shipping to offtakers.

 

14.5.8Molybdenum Processing

 

The molybdenum-rhenium concentrate is thickened in a high-rate thickener and then leached using ferric chloride in 4,000-gallon, glass lined steel leach reactors followed by drying and storage in bulk one-ton bags. Copper removed from the ferric chloride leach circuit will be recovered in the copper concentrate filter. The concentrate bags are transported to a roaster to oxidize the molybdenum to a saleable molybdenum oxide product.

 

14.5.9Tailings

 

Tailings are thickened in a high-rate thickener to an underflow density of 50 wt% solids and sent to the TSF. The decant water from the tailings will be pumped to the mill process water dam.

 

14.5.10BOP

 

Fresh Water – There will initially need to be 190 acre-feet of fresh water to support operations, with an expected 10% replacement rate per year due to losses from evaporation and concentrate moisture.

 

Process Water – There will be a process water dam and distribution system for recirculation of process water throughout the plant as required. Process water is supplied from water reclaimed from the TSF, from process operations, and site run-off, with fresh water make-up as required.

 

Potable Water – Potable water is generated by treatment of fresh water in a reverse osmosis (RO) unit at the processing plant. Potable water is distributed to the plant, and for miscellaneous purposes around the site.

 

Plant Air – Air compressors with liquid collection systems will produce dry pressurized plant air for use in instruments and associated infrastructure. Flotation cells will receive air from high-volume blowers.

 

186
 

 

15 Infrastructure

 

15.1General Layout

 

Refer to the conceptual mine layout presented in Figure 15-1 and Figure 15-3.

 

15.2Road Access

 

Access road option number 1 is presently the preferred option for the IA-level study. This affords a more direct route to rail access, for industrial material and consumable transport (discussed in the following sections) from sidings to the CuMo project site. Access road option number 3 is a viable route as well which would require additional upgrades. Given the site location and potential for adverse winter weather, developing a dual access site in the mountains may be a consideration during future project studies.

 

15.2.1Road Access Option Number 1

 

Road access option number one is to upgrade the existing gravel roads that come from Highway 55 near Horseshoe Bend via Placerville, Centerville, and Pioneerville.3 The total route is approximately 40 miles. These paved and gravel roads are currently serviceable and suitable for light-duty travel. Their maintenance is conducted by either Boise County or the USFS. An upgrade to portions of the access road will be required for transportation of materials, consumables, and concentrate haulage. An extension to this route will be necessary to access the proposed plant site. This extension will need to rise in elevation from reduced level (RL) 4,900 ft to RL 6,100 ft. At a maximum grade of 10%, this road is approximately 4 miles of the total 40 miles. No specific access road route has been identified, although the terrain through which the road will travel is rugged, and switchbacks are likely to be required in areas.

 

Additionally, the existing route from Idaho City, Idaho, to Centerville (approximately 10 miles) can be improved to provide options for optimized transport. While the existing road from Idaho City to Centerville can be used, this option will not offer any significant benefits over the approach from Horseshoe Bend, where a rail line is also present.

 

15.2.2Road Access Option Number 2

 

Road access option number two is to travel 15 miles north of Horseshoe Bend via Highway 55 and turn onto Banks-Lowman Road, which runs east-to-west to the north of the project site; Garden Valley, Idaho, is reached via Banks-Lowman Road after approximately 10 miles. An existing bridge about 1.5 miles southeast of Garden Valley will be used to cross the Payette River and gain access to South Fork Road. This road follows the south bank of the river to the east for approximately 6 miles. It is relatively level, running along the valley while generally grading up, traveling to the east at 2% to 3%. Upgrades to South Fork Road will likely be straightforward and relatively low cost, based on the existing alignment and minimal dramatic change in topography. At Grimes Pass, the existing Grimes Pass Road leads south from South Fork Road for approximately 4 miles to a location near the CuMo project plant site. Grimes Pass Road continuously gains elevation at a grade of 10%. Therefore, improvements to widen this road to include safety berms and runaway truck ramps will be necessary to mitigate safety concerns associated with increased traffic and material transport. A new, similar, 4-mile extension of road would need to be constructed, as per access road option number 1.

 

 

3 Horseshoe Bend, Placerville, Centerville, and Pioneerville are all located in Idaho, USA.

 

187
 

 

This route has the advantage (over access road option number 1) of requiring much shorter haulage routes on non-sealed roads. However, the construction traffic and transportation on paved roads will be more likely to impact public and recreational traffic.

 

15.2.3Road Access Option Number 3

 

Road access option number three is to travel Highway 21 heading north from the east end of Boise for approximately 35 miles to Idaho City, Idaho. At Idaho City, go through town and take Centerville Road for 8 miles to New Centerville, Idaho. Then follow Grimes Pass Rd/NF-382 north for 9 miles, along the western side of Grimes Creek, and through Boston Gulch to the original Centerville town site and on to Pioneerville. Continue north 1.5 miles through Hall Gulch to Miller Gulch where turning east/northeast on Miller Gulch Road. The overall route has an average slope grade of 2.3% with an elevation gain of nearly 500 ft. The Miller Gulch Road intersects a network of Forest Service roads that can be followed through a distance of nearly 6 miles to the CuMo project site. The average grade is 10% with the majority of elevation gain occurring in the first 3 miles of nearly 2000 ft. There is a drop of approximately 700 ft in elevation over the subsequent 0.5 mile with a gradual 500 ft gain over the remaining 2.5 miles. Similar to the other access options, improvements to widen this road to include safety berms and runaway truck ramps will be necessary to mitigate safety concerns associated with increased traffic and material transport.

 

This route has an advantage for the purpose of developing a separate site access option whereas No. 1 and No. 2 include some overlap.

 

15.3Rail Access

 

The CuMo project is expected to produce separate copper and molybdenum concentrates that may require different handling and transportation methods. Molybdenum concentrate is anticipated to be packaged at the project site in approximately 1-ton bulk bags for transportation to a North American molybdenum roaster for processing. Copper concentrate is anticipated to be transported in bulk via trucks to a rail loadout and then using covered railcars to a suitable west coast US port facility for loading onto a bulk vessel. Rotainer® systems may provide an alternative handling method for copper concentrate; however, their viability will depend on the availability or development of suitable unloading and vessel-loading infrastructure at the selected port.

 

An existing rail line, parallel to Highways 52 and 55, is owned by the Idaho Northern and Pacific Railroad (INPR). This rail line could potentially be used to transport concentrate from the CuMo project site, provided the concentrate is first trucked from the project site to a suitable rail siding and loading facility. Idaho Copper is considering existing siding locations for this purpose, including one at Horseshoe Bend. From the loading facility, concentrate could be transported via INPR to Payette, Idaho, where the short line connects with the Union Pacific Railroad (UP).

 

INPR has operated freight services between Payette and Cascade, Idaho, since acquiring the short line. However, since 2023, INPR has focused its operations on the portion of the rail line between Payette and Emmett, Idaho, with Emmett located approximately 20 miles west of Horseshoe Bend and Highway 55. The portion of the INPR rail line north of Emmett is currently classified as out-of-service, although care and maintenance activities continue, including maintenance of rail crossings. At present, discussions have not been initiated with INPR regarding reactivation of the rail line north of Emmett or its capacity to accommodate the anticipated CuMo project rail traffic.

 

188
 

 

Assuming that the INPR rail line north of Emmett can be returned to service, the most suitable location for a concentrate loading facility may be in or around Horseshoe Bend. This location is also associated with Access Road Option Number 1. Development of the existing rail yard within Horseshoe Bend would require consideration of potential impacts to the surrounding residential community. If development at this location is not feasible, a new siding and loading facility could potentially be constructed outside of town.

 

For access road option number 2, it may be preferable to construct a concentrate loading facility near the junction of Highway 55 and Banks-Lowman Road. As with the Horseshoe Bend location, an existing siding may be available for use. However, potential conflicts with existing recreational and tourist uses in this area would need to be considered.

 

From the rail loading facility, the copper concentrate would be transported by rail using gondola cars equipped with hard EcoFab-type lids, or equivalent covered systems, to provide environmental containment and minimize precipitation contact and associated water-management requirements during transportation. The concentrate could then be transferred at the selected port for ocean shipment.

 

Rotainer® systems may provide an alternative method for handling copper concentrate by maintaining the concentrate within sealed containers during truck, rail, and port handling. However, the viability of this option would depend on the selected port having, or agreeing to install, suitable Rotainer unloading infrastructure capable of transferring concentrate directly into a bulk vessel. Rotainer capability is currently limited at West Coast port facilities; therefore, this option should not be assumed as the basis of the concentrate transportation strategy until a suitable port and handling arrangement are confirmed.

 

Given the status of the INPR rail line and the need to establish suitable rail loading, railcar, port handling, and ocean shipping arrangements, further investigation of the logistics associated with concentrate transport is recommended during the PFS. This assessment should include discussion with INPR and UP, evaluation of potential rail loading locations, confirmation of railcar requirements, and engagement with potential port facilities to establish feasible concentrate handling and vessel-loading alternatives.

 

15.4Electrical Power

 

The overall availability of sufficient power generation is unlikely to be an issue, as the project site is near existing infrastructure with significant power reticulation capacity. Idaho Power services the project area. No suitable power lines currently run near the project site, but Idaho Power has indicated an intention to install transmission lines to the vicinity of Placerville to the southwest (10 miles) and the vicinity of Garden Valley to the northeast (9 miles). These transmission line alignments are shown on Figure 15-1.

 

Consideration should be given to the provision of backup power for critical systems. For example, backup power generation may be warranted to allow pipelines, flotation cells, and thickeners and tailings management systems to be cleaned in the event of a power outage, thereby preventing costly blockages and delays. The PFS will evaluate a trade-off study between grid power, a hydrogen hub, and possibly mini-nuclear generators.

 

189
 

 

 

Figure 15-1 CuMo Project Possible Electrical Power Line Alignment

 

190
 

 

15.5Fuel Supply

 

Barr evaluated pipeline supplied natural gas, propane, diesel, and liquified natural gas (LNG), as potential fuel sources for the CuMo project site. Process fuel requirements are estimated to range from 60 to 200 million British thermal units (MMBtu) per day, excluding power generation.

 

Pipeline supplied natural gas was eliminated from further consideration due to a relatively low anticipated gas demand and the distance to the nearest natural gas pipeline system. The Williams Northwest Pipeline supplies natural gas to Intermountain Gas Company, the local gas-distribution company. A potential point of interconnect with Williams Northwest Pipeline is located 55 miles southwest of the CuMo project site, near Amsco, Idaho (Figure 15-2). If project gas demand increases significantly (i.e., to at least 10 times the current requirement), this option should be reconsidered.

 

 

Figure 15-2 CuMo Project Possible Gas Pipeline Alignment

 

Fuel delivery to the CuMo site could be reasonably accomplished via trucking. Options evaluated included LNG, propane, and diesel fuel.

 

LNG’s gross calorific value (higher heating value) is 0.084 MMBtu per gallon (gal) and would meet the site’s maximum daily demand with only 2,380 gal per day. Intermountain Gas Company has an LNG supply location in Nampa, Idaho. To use LNG, the CuMo project site would need to have the infrastructure in place to store and convert the fuel to its gaseous form prior to use. This equipment typically includes cryogenic storage tank(s), cryogenic pumps and insulated piping, vaporization module, a heat exchanger, pressure regulation and gas supply system, boil-off gas management equipment, and an odorization system (for domestic gas use). LNG storage, vaporization, and regasification systems of this size are typically sourced as turnkey packages, complete with electrical, instrumentation, and control systems for efficient integration into the plant.

 

191
 

 

Liquid propane at standard conditions (60 degrees F) has a heat content of 0.091 MMBtu/gal. The CuMo project site’s maximum demand would require almost 2,200 gal of propane per day. Standard U.S. diesel fuel has a heat content of 0.139 MMBtu/gal. The site’s maximum demand would require more than 430 gal per day of diesel fuel. Propane and diesel fuel were eliminated from consideration due to their relatively low heating values and associated onsite fuel storage requirements.

 

For purposes of this study, LNG is assumed to be the fuel source for plant process equipment and utilities. In the subsequent PFS, a number of different power alternatives to fuel should be examined.

 

15.6Water Supply

 

Idaho Copper has acquired water rights and sources sufficient to conduct exploration; however, additional water will be required to support development and mining and process activities. Based on discussions with Idaho Copper, additional water may be available from purchasing or leasing existing rights on the Boise River, and potentially for trade from appropriations secured from the Payette River, two miles north of the site, subject to applicable licensing and water rights.

 

Two other possible water supply sources require additional subsurface investigation and regulatory assessment. Based on previous exploratory drilling, the primary groundwater aquifer is located at depth. Production wells could potentially be developed if groundwater conditions are sufficient to support the CuMo project. Alternatively, excess water may be available for transfer from an adjacent drainage or basin. These possibilities will need to be discussed with the appropriate water authorities.

 

It is assumed that a water supply trade-off study will be undertaken as part of the PFS.

 

15.7Waste Rock Facilities

 

As noted in Section 13.3, a portion of the ROM waste material will be used to construct the TSF embankment (Section 15.8). Additionally, the CuMo project includes external WRF near the proposed pit exit to minimize ROM waste and sorter rejects haul costs (see Figure 15-3). However, it is plausible that through further optimization of the mine production and process plans that additional waste rock and rejects material will be identified that may require a larger WRF footprint near the open pit and facilities.

 

192
 

 

 

Figure 15-3 CuMo Project Site Layout with WRF

 

15.8Tailings Storage Facility

 

The TSF will be located at the headwaters of the Clear Creek watershed, in a natural basin formed by the surrounding ridgeline. The TSF will have the capacity to store approximately 24 billion ft3 of tailings to be produced over the mine and process plant’s total 46-year life. Approximately 870 Mst of ROM waste rock is required to construct the TSF embankment. The TSF ultimate crest height will be 6,700 ft with 5 ft of freeboard above the top of tailings (6,695 ft). A starter dam will be constructed to an elevation of 6,000 ft to facilitate early mine production.

 

Tailings will be piped to the TSF and deposited as conventional slurry from the dam crest. The settled tailings density is assumed to be approximately 100 pounds per cubic foot (lb/ft3), and beach slope angles are assumed to be 1% to 2% for sub-aerially deposited tailings. The water reclamation pond will form against the natural terrain upstream of the dam to mitigate potential for overtopping or embankment instability. The mine’s tailings have not tested positive for potential acid generation; however, there is potential for metal leaching.

 

15.8.1Tailings Embankment

 

The embankment is designed to be downstream construction for geotechnical stability, with the starter dam placed on bedrock. Slopes will be 2.5H:1V for both the upstream and downstream. The crest of the embankment will be 170 ft wide to accommodate vehicles and equipment. Sort waste and ROM waste will constitute the construction material, which will be transported by haul truck before being compacted in 3-ft lifts. The final embankment will contain approximately 15.0 billion ft3 waste material.

 

193
 

 

The starter dam is designed to a crest height of 6,000 ft to facilitate the first two years of tailings. The foundation for the starter dam will be cleared, and overburden will be stripped to bedrock. The overburden will be stockpiled for use in future reclamation of the waste facilities. Additional lifts will be constructed to an ultimate crest height of 6,700 ft. A freeboard of 5 ft will be maintained throughout the LOM.

 

Figure 15-4 and Figure 15-5 show the TSF concept.

 

 

Figure 15-4 CuMo Project TSF Layout

 

 

Figure 15-5 Cross Section Profile Through CuMo Project TSF

 

194
 

 

15.8.2Tailings Impoundment

 

The tailings impoundment will contain an ultimate capacity of 24 billion ft3 of tailings. Construction of the impoundment area will include the removal of topsoil and vegetation and compacting the exposed, fine-grained soils. Tailings will be discharged from the crest of the dam, limiting seepage through the dam. Due to the tailings deposition plan and overall configuration of the TSF, as well as the significant groundwater depth below ground surface and geology formations that typically exhibit low permeability, it is not expected that a synthetic geomembrane will be required to contain tailings for the entire basin. It may be expected a liner will be constructed on the upstream slope face of the tailings impoundment to reduce potential seepage risks.

 

The tailings pipeline is approximately 14,000 ft based on the concept alignment. The pipeline can be constructed concurrent with the mill and early embankment construction such that it is operational for production. The pipeline alignment considers the location of WRF and stockpile material; therefore, during the PFS where the project is being evaluated for further optimization of facility placement, this alignment will likely be adjusted.

 

195
 

 

16 Market Studies

 

The IA has assumed that two concentrates (copper and molybdenum) will be produced, and that the copper concentrate (grading >22% copper) will be sold and shipped to a smelter within the Pacific region (e.g., Japan, China, Korea, India). Silver is assumed to be a payable byproduct of the copper concentrate and will contribute to the value of the CuMo sales. It is assumed that molybdenum concentrate (grading >50% molybdenum) will be shipped to a toll roaster in the United States, where additional credits may be achieved through the production of rhenium. No penalty elements have been identified to date. At this time, no contracts exist for delivery of final product, so the IA assumes that products will be sold on the open market.

 

This chapter provides background information for copper, molybdenum, and silver as the current primary mineralization products of economic interest for the CuMo project. The information is provided as context for the ongoing development of the project, based on recent observations and expected trends. It is understood that factors beyond the control of the project proponent can result in positive or negative impacts.

 

The QP has reviewed the following studies and analyses, and the results support the assumptions made in other portions of this technical report.

 

16.1Summary for Copper

 

16.1.1Market Analysis: Copper

 

It is important to distinguish between refined copper, commonly traded as copper cathode, and copper concentrate. Copper cathode is a final metal product that generally requires no further refinement before sale into the market, whereas copper concentrate is an intermediate product that must be smelted and refined into cathode or other refined copper products before reaching end users. As the CuMo project is expected to produce copper concentrate rather than copper cathode, demand for the project’s copper product will be influenced not only by end-use refined copper demand, but also by available smelting and refining capacity for concentrate. China is a key driver of global copper concentrate demand because it has the world’s greatest smelting and refining capacity for copper concentrates.

 

Global refined copper demand is projected to increase materially, supported by electrification, renewable energy development, and infrastructure expansion. As shown in Figure 16-1, a recent International Energy Agency (IEA) analysis indicates that global copper demand is expected to increase from 27.4 million short tons (24.9 million metric tonnes) in 2021 to more than 34.3 million short tons (31.0 million metric tonnes) by 2030, representing growth of approximately 25% over the period (IEA, 2025). Figure 16-1 includes Stated Policies Scenario (STEPS) and Announced Pledges Scenario (APS) projections after 2024. Other industry forecasts indicate greater demand cases, with global copper consumption potentially exceeding 36.4 million short tons (33 million metric tonnes) by 2035 and continuing to increase through 2050. Although individual forecasts vary, published outlooks generally indicate continued copper demand growth through 2035 and beyond, supporting the need for additional mine supply and concentrate feed.

 

196
 

 

 

Source: IEA (2025)

 

Figure 16-1 Copper Demand Outlook 2015–2040 Shown in Millions of Metric Tons

 

Currently, global copper production is highly concentrated geographically, with annual total mine production estimated at approximately 25.3 Mst (23 million metric tonnes). The United States produces approximately 1.2 Mst (1.1 million metric tonnes) per year, representing roughly 4% to 5% of the global supply, and remains a net importer of refined copper. Major global producers are in Chile, the Democratic Republic of Congo (DRC), and Peru, which together account for nearly one-half of global copper output, highlighting the concentration of supply in a limited number of jurisdictions (World Population Review, 2026a), as shown in Figure 16-2.

 

The copper concentrate market is distinct from the refined copper market, because concentrate demand is driven primarily by smelter and refinery feed requirements rather than direct end-use consumption. Recent market analysis indicates that concentrate availability has tightened as mine supply growth has lagged, along with expanding smelting capacity, particularly in China (see Figure 16-3). This mismatch has contributed to historically low treatment and refining charges and increased competition among smelters for concentrate feed. This dynamic is directly relevant to the CuMo project, as it is expected to produce copper concentrate for sale to third-party smelters rather than refined copper cathode.

 

197
 

 

 

Source: International Copper Study Group (2025)

 

 

Figure 16-2 Copper Production by Country, 2024

 

 

Source: International Copper Study Group (2025)

 

Figure 16-3 Copper Smelter Production by Country, 2024

 

16.1.1.1Demand Drivers: Copper

 

The projected growth in global refined copper demand is underpinned by structural changes in end-use consumption associated with electrification and energy transition. Construction and electricity networks are expected to remain the largest sources of copper demand through 2050. However, electric vehicles (EVs) represent the fastest-growing end-use segment, with their share of global refined copper demand projected to increase from approximately 2% in 2024 to 10% by 2050, representing a sevenfold increase (IEA, 2025).

 

Demand from industrial machinery and equipment is also expected to grow significantly, nearly doubling and accounting for more than 15% of total refined copper demand by 2050; this growth will be supported by continued manufacturing expansion and electrification. Demand associated with solar, wind, and construction sectors is projected to increase by approximately 50% over the same period (IEA, 2025).

 

198
 

 

16.1.2Treatment and Refining: Copper

 

Copper concentrates are typically sold under long-term contracts that reference annual benchmark treatment charges and refining charges set among the industry’s largest smelters and concentrate producers. The treatment charges are assessed on a dry metric tonne (dmt) of concentrate basis and represent the cost of processing each tonne of material, while refining charges are assessed on a payable copper content basis.

 

Since 2019, benchmark treatment and refining charge terms have ranged from US$21.25 to $88.00 per dmt of payable copper, based on industry benchmark negotiations of global supply and refining capacity for copper concentrates (Brunelli and Moerenhout, 2026). However, in 2026, benchmark treatment and refining charges were set to US$0 per dmt, representing the lowest rates ever reached in annual negotiations. Constrained concentrate supply caused by mine disruptions, declining grades, and rapid smelter capacity growth—particularly in China—have driven spot treatment and refining charges to negative values in 2026.

 

For the CuMo project, these market conditions support the handling of copper treatment and refining charges as variable economic assumptions that should be confirmed through updated smelter quotations as the project advances.

 

16.1.3Metal Prices: Copper

 

Copper market fundamentals continue to be supported by long-term structural supply constraints and steady demand growth associated with electrification, renewable energy, transmission infrastructure, and digital technologies. However, copper prices also remain influenced by broader macroeconomic conditions, including global economic growth, interest rates, currency movements, and investor sentiment.

 

Recent industry forecasts indicate that global copper concentrate supply is expected to remain constrained as declining ore grades, increasing mining costs, permitting challenges, and long development timelines limit the rate at which new mine supply can be brought to market. At the same time, demand for copper concentrates continues to be supported by existing and expanding global smelting capacity, particularly in China.

 

S&P Global Market Intelligence forecasts that both the copper concentrate and refined copper markets will transition into sustained deficits during the early 2030s (Figure 16-4). While these structural deficits are expected to provide long-term support for copper prices, the projected price response is relatively modest, reflecting the influence of broader macroeconomic factors and the gradual market response to tightening supply conditions (Figure 16-5).

 

199
 

 

Accordingly, long-term copper price assumptions for the CuMo project should be based on independent market consensus forecasts, while recognizing that short-term price volatility may differ significantly from longer-term market fundamentals.

 

 

Source: S&P Global Market Intelligence (2026)

 

Figure 16-4 Forecast Copper Concentrate Balance, Refined Copper Balance, and LME Three-Month Copper Price (2023–2035)

 

 

Source: S&P Global Market Intelligence (n.d.)

 

Figure 16-5 June 2024–June 2027 Copper Pricing Trend and Forecast

 

16.2Summary for Molybdenum

 

16.2.1Market Analysis: Molybdenum

 

Global molybdenum demand continues to expand steadily, supported by its critical role as an alloying element in steel, superalloys, and high-performance industrial materials. Annual global molybdenum production has been approximately 275,000-350,000 short tons (250,000-320,000 metric tonnes) in recent years, as shown in Figure 16-5 (Mordor Intelligence, 2024; World Population Review, 2026b). Demand is projected to increase to nearly 437,000 short tons (397,000 metric tonnes) by 2030, representing growth of roughly 3 to 4% annually over the forecast period.

 

200
 

 

Supply is highly concentrated geographically. China accounts for more than 50% of global production, followed by the United States, Chile, and Peru. Together, the four countries with the greatest production account for approximately 85 to 90% of global output, highlighting a structurally concentrated supply base (Polyak, 2026).

 

The United States produces approximately 50,000 to 55,000 short tons (45,000 to 50,000 metric tonnes) annually (~15 to 20% of global supply) and remains one of the largest non-China producers. Unlike many base metals, however, molybdenum is produced predominantly as a byproduct of porphyry copper mining. As a result, global molybdenum supply is influenced primarily by copper mine production and processing decisions rather than molybdenum prices alone, creating a unique supply dynamic that can contribute to periods of market imbalance and price volatility (World Population Review, 2026b).

 

16.2.1.1Demand Drivers: Molybdenum

 

Molybdenum demand is predominantly industrial and is closely correlated with global manufacturing activity, particularly steel production. Approximately 70% to 80% of global molybdenum consumption is associated with alloy, stainless steel, and specialty steels, for which molybdenum enhances strength, corrosion resistance, temperature performance, and weldability. Consequently, demand is strongly influenced by trends in construction, infrastructure development, energy, transportation, and industrial manufacturing.

 

Key demand drivers include steel and infrastructure, fossil energy, renewables, nuclear, industrial machinery, and aerospace.

The Asia-Pacific region, led by China, accounts for the largest share of global molybdenum consumption, reflecting the region’s dominant steel industry and manufacturing base. Over the longer term, demand growth is expected to increasingly originate from emerging economies, particularly India and Southeast Asia, as industrialization and infrastructure investment continue. Although steel production is expected to remain the principal driver of molybdenum demand, continued investment in energy infrastructure and electrification is anticipated to provide additional long-term market support (Mordor Intelligence, 2024).

 

16.2.2Treatment and Refining: Molybdenum

 

Molybdenum concentrates are commonly processed at specialized roasting facilities that convert molybdenite (MoS₂) concentrate into technical-grade molybdenum oxide (MoO₃), the principal intermediate product used in the manufacture of ferromolybdenum, chemical products, and molybdenum metal. Unlike copper concentrates, molybdenum concentrates are not marketed using industry benchmark treatment and refining charges. Instead, commercial terms are negotiated privately between concentrate producers and roasting facilities.

 

Processing charges are generally structured as a conversion fee or a negotiated deduction from the contained molybdenum value and vary depending on concentrate grade, impurity levels, recovery, logistics, and prevailing market conditions. Consequently, commercial terms are typically confidential and not publicly reported. For the CuMo project, molybdenum processing costs should be developed using current commercial quotations from qualified roasting facilities and incorporated as variable economic assumptions within the project evaluation.

 

201
 

 

16.2.3Metal Prices: Molybdenum

 

Molybdenum prices have historically exhibited greater volatility than many other base metals due to the relatively small size of the global market and the predominance of byproduct production. Short-term price movements are influenced by changes in industrial activity, stainless and alloy steel demand, and fluctuations in copper production, which supplies a significant proportion of global molybdenum.

 

Although price volatility periods are expected to continue, long-term molybdenum prices are generally supported by sustained demand from the steel, energy, and industrial sectors. Accordingly, long-term price assumptions for the CuMo project should be based on independent market consensus forecasts and current market conditions.

 

16.3Summary for Silver

 

16.3.1Market Analysis: Silver

 

Silver plays a dual role as both a precious metal and a critical industrial commodity, resulting in a dynamic demand profile (Silver Institute, 2024). Total global silver demand reached approximately 1.16 billion ounces in 2024, while mine production totaled approximately 820 million ounces and recycling contributed an additional 194 million ounces. This resulted in a structural supply deficit of approximately 149 million ounces, continuing a multi-year trend of demand exceeding supply that began in 2021 (Silver Institute, 2024).

 

Silver mine production is geographically diversified but remains concentrated among a relatively small number of producing countries, with Mexico, China, and Peru among the leading producers (World Population Review, 2026c). Approximately 70% of global silver produced is recovered as a byproduct of lead, zinc, copper, and gold mining. Consequently, silver supply is driven primarily by production decisions for these primary commodities rather than silver prices alone, limiting the industry’s ability to respond rapidly to changes in silver demand (Silver Institute, 2025).

 

16.3.1.1Demand Drivers: Silver

 

Silver demand is increasingly driven by industrial applications, which now account for approximately 55% to 60% of total demand, surpassing traditional investment and jewelry segments.

 

Key drivers include solar photovoltaics, electronics and electrification, automotive applications, and investment.

 

Photovoltaic applications account for a significant and growing share of industrial consumption and are expected to remain a primary demand driver through 2030 as solar installations expand globally. Regionally, demand is strongest in China, India, North America, and Europe, reflecting both industrial manufacturing capacity and continued deployment of renewable energy (Silver Institute, 2024).

 

16.3.2Treatment and Refining: Silver

 

Silver-refining costs vary depending on the feed material, including doré, concentrates, recycled metal, and scrap silver. U.S. precious metal refiners typically charge a melt and assay fee in addition to a refining charge. Published schedules indicate refining charges of approximately US$0.50 per troy ounce of payable silver, with melt, assay, and treatment fees of approximately US$0.60 to $0.65 per troy ounce. These charges are often subject to minimum fee or minimum lot requirements.

 

202
 

 

16.3.3Metal Prices: Silver

 

The silver outlook is characterized by sustained structural demand growth and persistent supply constraints (Silver Institute, 2024). The projected price response is relatively modest, as shown in Figure 16-6.

 

Key market trends:

 

●Continued growth in industrial demand, led by solar power, electronics, and electrification
   
●Persistent supply deficits resulting from constrained mine production and strong consumption
   
●Continued price volatility arising from interaction between industrial demand and macroeconomic factors
   
●Potential price upside if solar and EV demand accelerates faster than anticipated

 

 

Source: S&P Global Market Intelligence (2026)

 

Figure 16-6 Silver Price Historical Trend and Forecast

 

16.4Summary for Rhenium

 

A rhenium credit is applied to the IA as it can be recovered from the molybdenum concentrate. The credit is applied on the basis of a 25-ppm content within the molybdenum concentrate assuming a 25% payability at a price of US$2,250/lb. According to the U.S. Geological Survey (USGS), the driving factor for rhenium metal price is demand from the aerospace sector, particularly for nickel-based superalloys, as well as in petroleum-reforming catalysts. Rhenium remains a supply-constrained critical mineral that is produced primarily as a by-product of molybdenum and copper operations, which is observed for the CuMo project as well; therefore, the limited supply availability in response to demand growth is directly related to the mining and processing capability of active molybdenum and copper operations.

 

203
 

 

16.5Selected Metal Prices

 

The metal prices selected and applied to this IA are based on historical average prices and a reasonable, conservative assessment of published, long-term price forecasts. The authors have reviewed economic assumptions and commodity prices reported in comparable IA, PFS, and FS reports and public disclosure documents prepared under NI 43-101 and S-K 1300, including active mining operations.

 

Copper and silver are actively traded on established terminal markets, providing transparent and frequently updated pricing data. Molybdenum pricing is less transparent and requires greater discernment in research and analysis, because it is primarily negotiated among producers, traders, and consumers rather than traded on a highly liquid, terminal market. Published molybdenum prices and forecasts may therefore be less current or consistent than those available for copper and silver. However, the availability and reliability of molybdenum market data have improved in recent years.

 

The metal prices used for mining technical economic model are presented in Table 16-1. The metal prices were selected based on the review of recent three-year price trends and benchmarking with the metal prices applied for comparable copper, molybdenum, and silver projects that published IA, PFS, and FS studies in 2026. The selected metal prices are compared with recent three-year price trends in Figure 16-7 for copper and molybdenum and Figure 16-8 for silver.

 

Table 16-1 Metal Prices for Economic Analysis

 

Metal Price
Copper (Cu) (per lb) $5.00
Molybdenum metal (Mo) (per lb) $25.00
Silver (Ag) (per troy oz) $50.00
Rhenium (Re) (per lb) $2,250.00

Note. lb = pound; oz = ounce

 

204
 

 

 

Source: YCharts (2026a); YCharts (2026b)

 

Figure 16-7 Copper and Molybdenum Three-year Metal Price with Resource Metal Price

 

 

Source: YCharts (2026c)

 

Figure 16-8 Silver Three-year Metal Price with Resource Metal Price

 

205
 

 

17 Environmental Studies, Permitting, and Plans, Negotiations, or Agreements with Local Individuals or Groups

 

17.1Environmental and Permitting

 

17.1.1Past and Present Permitting for Exploration Project

 

Idaho Copper’s predecessors submitted an exploration PoO in 2007 to the USFS for exploration activities to result in about 20 miles of drill road, 4.7 miles of which were existing unauthorized drill roads from previous operators and 13.3 miles of which were new, temporary roads. The USFS prepared an environmental assessment and initially issued the 2011 DN/FONSI to Idaho Copper in February 2011. The Idaho Conservation League filed a lawsuit against the project in July 2011. On August 29, 2012, the United States District Court of the District of Idaho (Court) ordered, “that the Defendant Forest Service’s decisions regarding groundwater made in the 2011 Environmental Assessment [be] vacated and the matter remanded to the Forest Service for further proceedings consistent with this opinion” (USFS, 2018). The USFS moved forward with preparing a Supplemental Environmental Assessment to undertake further analysis of groundwater and, as needed, address new information and changed circumstances since the 2011 DN/FONSI had been issued (e.g., change in status of the wolverine from a regional sensitive species to an Endangered Species Act (ESA) proposed listed species) (USFS, 2018).

 

The supplemental DN/FONSI (SDN/FONSI) addressing the 2011 Court order and other changes summarized in the preceding paragraph was signed on September 30, 2015. Plaintiffs from the 2011 lawsuit filed a new lawsuit challenging the 2015 supplemental decision in January 2016. The 2015 lawsuit challenged the analysis of potential effects of exploration activities on groundwater and Sacajawea’s bitterroot, a sensitive plant species. The Court issued the memorandum decision and order in this lawsuit on July 11, 2016. The Court upheld the SDN/FONSI as to the NEPA challenges related to groundwater, so no further analysis was required. The Court found the Forest Service’s analysis and conclusions concerning Sacajawea’s bitterroot to be arbitrary and capricious, because the analysis failed to re-examine the baseline Sacajawea’s bitterroot population.4

 

As occurred in response to the 2014 Grimes Fire, each resource area addressed in the 2015 CuMo Exploratory Project Supplemental Environmental Assessment was affected differently. Like updates made in response to the 2014 Grimes Fire, updates were made in the 2018 Supplemental Redline Environmental Assessment CuMo Exploration Project (Supplemental Redline Environmental Assessment) to address the changes in baseline conditions caused by the 2016 Pioneer Fire. The Supplemental Redline Environmental Assessment focused on the re-evaluation of the Sacajawea’s bitterroot baseline—as well as other resources addressed in the 2015 Supplemental Environmental Assessment that had been affected by the 2016 Pioneer Fire—to determine whether effect conclusions reached in the 2015 SEA that supported the 2015 SDN/FONSI were different or changed. The Supplemental Redline Environmental Assessment focused on only these topics, because the Court determined that other concerns raised during the 2012 and 2015 lawsuits had been properly addressed, and that the evidence and analysis in the 2015 Supplemental Environmental Assessment and supporting project record supported the determination that no significant impacts would occur among other resources as a result of proposed management activities (USFS, 2018).

 

 

4 The 2017 Sacajawea’s bitterroot survey was performed within a 10-mile radius and located previously unknown populations of the species following the 2014 Grimes Fire and subsequent 2016 Pioneer Fire (USFS, 2018). These populations totaled about 17,000 plants among six locations (USFS, 2018) in the project area.

 

206
 

 

In June of 2017, the Boise National Forest issued Idaho Copper a Road Use Permit to perform road maintenance on National Forest Service Roads 382C, 397, and 397B using best management practices. The road maintenance work was completed in June and July of 2017 (USFS, 2018).

 

A number of environmental studies were undertaken for the 2011 Environmental Assessment CuMo Exploration Project and subsequently revised in 2015 and 2018. The Supplemental Redline Environmental Assessment incorporated habitat changes and resulting impacts related to the 2014 Grimes Fire and 2016 Pioneer Fire. Public scoping for the project started in October 2023. The public comment period began on May 29, 2024, with the objection period starting on September 20, 2024. The USFS signed and issued the DN/FONSI in March 2025. In June 2025, NGOs again brought a lawsuit seeking to overturn the USFS’s decision. This litigation is ongoing, but Idaho Copper believes that the NGOs’ position is without merit.

 

With respect to the USFS’ decision issued in March 2025, Idaho Copper’s required yearly Plan of Operations for 2026 was approved by the USFS on September 9, 2026, and exploration and related approved activities commenced on October 4, 2026.

 

The following list of reports has been prepared by USFS specialists in support of the Supplemental Redline Environmental Assessment and can be accessed on https://www.fs.usda.gov/r04/boise/projects/64920.

 

Table 17-1 List of Reports Related to the Supplemental Redline Environmental Assessment

 

Report Title Date Prepared By Additional Information File Name
Minerals and Geology Technical Report January 2025 Travis Whitman, Geologist, Boise National Forest Updated Mar 24, 2025, by A Prior Collaborator 20250115_CuMo_MineralGeologyReport.pdf
Access and Safety Report January 2025

Doug Montini, Civil Engineer, Boise National Forest

Josh Newman, Idaho City District Ranger, Boise National Forest

Updated Mar 24, 2025, by A Prior Collaborator 20250117_CuMo_AccessAndSafetyReport.pdf
Air Quality Report January 2025 Terre Pearson-Ramirez, Forest Planner/ Environmental Coordinator, Boise National Forest Updated Mar 24, 2025, by A Prior Collaborator 20250117_CuMo_Air Quality Report.pdf
2024 Wildfire Season January 2025 Preparer Not Listed Updated Mar 24, 2025, by A Prior Collaborator 0250117_CuMo_2024WildfireSeason-ProjectReview.pdf
Forest Plan Consistency Documentation August 2024 Preparer Not Listed Updated Sep 27, 2025, by A Prior Collaborator 20240903_CuMO_ForestPlanConsistencyChecklist.pdf

 

207
 

 

Report Title Date Prepared By Additional Information File Name
Biological Assessment
Appendix A: Plan of Operations and Amendments
September 2024

Responsible Official: Brant Peterson, Forest Supervisor, Boise National Forest

For more information, contact: Joshua Newman, Idaho City District Ranger, Boise National Forest

Updated Sep 20, 2024, by A Prior Collaborator 20240915_CuMo_BA_Appendix A Plan of Operations and Amendments.pdf
2024 Biological Assessment September 2024

Scott Brandt, Forest Fish Biologist, Boise National Forest

Noel Copenhaver, District Wildlife Biologist, Boise National Forest

Jennifer Brickey, Forest Ecologist, Boise National Forest

Updated Sep 20, 2024, by A Prior Collaborator 20240909_CuMo_BA.pdf
Biological Assessment
Appendix B: Mitigation Measures and Best Management Practices
September 2024

Responsible Official: Brant Peterson, Forest Supervisor, Boise National Forest

For more information, contact: Joshua Newman, Idaho City District Ranger, Boise National Forest

Updated Sep 20, 2024, by A Prior Collaborator 20240915_CuMo_BA Appendix B Mitigation Measures.pdf
Wildlife Technical Report and Biological Evaluation September 2024 Noel Copenhaver, District Wildlife Biologist, Boise National Forest Updated Sep 19, 2024, by A Prior Collaborator 20240917_CuMo_WildlifeReport.pdf
Soil Resources Technical Report September 2024 Matthew Robinson, Forest Hydrologist, Boise National Forest Updated Sep 19, 2024, by A Prior Collaborator 20240917_CuMo_SoilsReport.pdf

Wildlife Technical Report and Biological Evaluation

Appendix A: Wildlife Survey Protocol

September 2024 Noel Copenhaver, District Wildlife Biologist, Boise National Forest Updated Sep 19, 2024, by A Prior Collaborator 20240917_CuMo_WildlifeReportAppendixA.pdf
Botanical Resources and Non-native Plants Biological Evaluation and Technical Report Appendices September 2024 Jennifer Brickey, Forest Ecologist, Boise National Forest Updated Sep 19, 2024, by A Prior Collaborator 20240917_CuMo_Botany-WeedsReportAppendices.pdf
Recreation, Visuals, and Special Management Areas Report September 2024 Everardo Santillan, Recreation Program Manager, Boise National Forest Updated Sep 19, 2024, by A Prior Collaborator 20240917_CuMo_RecreationReport .pdf
Range Technical Report September 2024 Matt Morehead, Forest Range Program Manager, Boise National Forest Updated Sep 19, 2024, by A Prior Collaborator 20240917_CuMo_RangeTechReport.pdf
Surface Water Hydrology Technical Report September 2024 Joshua Courter, South Zone Hydrologist, Boise National Forest Updated Sep 19, 2024, by A Prior Collaborator 0240917_CuMo_HydrologyReport.pdf
Groundwater Hydrology Technical Report September 2024 Rick Wells, Geologist, Boise National Forest Updated Sep 19, 2024, by A Prior Collaborator 20240917_CuMo_GroundwaterReport.pdf

 

208
 

 

Report Title Date Prepared By Additional Information File Name
Fisheries Technical Report September 2024 Scott Brandt, Forest Fish Program Manager, Boise National Forest Updated Sep 19, 2024, by A Prior Collaborator 20240917_CuMo_FisheriesReport.pdf
Botanical Resources and Non-native Plants Biological Evaluation and Technical Report September 2024 Jennifer Brickey, Forest Ecologist, Boise National Forest Updated Sep 19, 2024, by A Prior Collaborator 20240917_CuMo_Botany-WeedsReport.pdf
Evaluation and Update of Fuel Transport Memo May 2024 Doug Montini, Boise National Forest Engineer Updated Sep 19, 2024, by A Prior Collaborator 20240528_CuMo_FuelTransportMemo.pdf
Response to Comment Process June 2024 Not listed Updated Sep 23, 2024, by A Prior Collaborator 0240917_CuMo_CommentResponse.xlsx

 

Source: U.S. Forest Service (2026)

 

17.2Permitting for Mining Operations

 

Environmental permitting for mines in Idaho is predicated on land status. Because the mine will be located on public land administered by the U.S. Department of Agriculture – Forest Service, Boise National Forest, Idaho City Ranger District and patented claims (private land owned and controlled by Idaho Copper), the permitting path will involve multiple state and federal agencies, as shown in Table 17-2. A more complete list can only be prepared after the PoO is complete.

 

Table 17-2 Major Permits and Authorizations That May be Required

 

Name Authorizing Agency
Federal Permits and Authorizations
Mining Plan of Operations USFS
EIS Review and Approval USFS, U.S. EPA, and USACE
Approved Mining Plan of Operations/Record of Decision USFS
Rights-of-Way for Water/Power/Access Corridors Outside of Mining Plan of Operations boundary USFS and/or other federal and state agencies
CWA Section 404 Wetland Permit USACE
Threatened and Endangered Species Consultation and Compliance with the ESA USFWS
Compliance with the Bald Eagle Protection Act USFWS
Road Use and Special Use Permits USFS
U.S. EPA 402 NPDES U.S. EPA
Permit for Purchasing Explosives US DOJ - Bureau of Alcohol, Tobacco, Firearms & Explosives
Mine Safety Mine Safety and Health Administration

 

209
 

 

Name Authorizing Agency
Federal Permits and Authorizations
Idaho State Permits and Authorizations
Stream Channel Alteration Permit Idaho Department of Water Resources
Water Right Appropriation
Dam Safety Permit
Reclamation Plan Approval Idaho Department of Lands
Placer Permit
Idaho Mine Registration
Title V Operating Permit Idaho Department of Environmental Quality – Air Quality Division
Approval of Plans for a New Sewage Treatment Facility Idaho Department of Environmental Quality – Water Quality Division
Compliance with the Safe Drinking Water Act
Clean Water Act 401 Certification
Idaho Point Discharge Elimination Permit
Solid Waste Management Idaho Department of Environmental Quality – Waste Management & Remediation Division
Right-Of-Way Occupancy/Encroachment Permit Idaho Department of Transportation
Transportation and Storage of Hazardous Materials, Chemicals and Fuel Permits Idaho Department of Transportation
Consultation with State Historic Preservation Officer Idaho State Historic Preservation Office
Local
Building Permits Boise County
Road Maintenance Agreement
Conditional Use Permit

 

Note. No permit applications in relation to mining have been filed to date. CWA – Clean Water Act; EIS – Environmental Impact Statement; ESA – Endangered Species Act; NPDES – National Pollutant Discharge Elimination System; USACE – U.S. Army Corps of Engineers; U.S. EPA – U.S. Environmental Protection Agency; USFWS – U.S. Fish and Wildlife Service

 

17.2.1Federal Authorizations and Permits

 

Exploration and mining on lands administered by a federal agency—in this case, the USFS—requires authorization to conduct surface-disturbing activities. Mining for locatable minerals on lands administered by the USFS is guided by 36 CFR Part 228. These regulations require that a PoO be prepared for any operation likely to cause significant disturbance of surface resources. The PoO must provide a detailed description of construction, operations, closure, and reclamation of the proposed mining operation, as well as a reclamation cost estimate. Detailed technical documents to support the PoO can include, but not necessarily be limited to, engineering designs for the open pits, processing plants, waste rock dumps, tailings storage facilities, access roads, power supplies, and water supplies.

 

210
 

 

The “complete” PoO must provide sufficient detail to identify and disclose potential environmental impacts during the mandatory NEPA review process, under which the potential impacts associated with project development are analyzed. The most likely level of NEPA analysis for this project will be an EIS, which is a public disclosure document, not a permit or approval document. An EIS is intended to disclose any environmental impacts that could occur as a result of the project, and to guide the decisions of the public land managers. The USFS will most likely require that an EIS be prepared for the project for the following reasons or under the following circumstances:

 

●The size of the operation
   
●If the proposed project is expected to have significant impacts on critical elements or resources
   
●If significant potential for use of or impacts on surface water and/or groundwater exists
   
●If opposition from non-governmental organizations or the public is expected to be significant

 

An EIS must consider possible impacts on the following critical elements and resources:

 

●Critical elements – Air quality, aquatics, floodplains, cultural resources, environmental justice, migratory birds, Native American religious concerns, non-native invasive species, threatened and endangered species, solid and hazardous wastes, hydrology including geochemistry, wetlands, and wilderness.
   
●Resources – Soils, geohazards, roadless areas, vegetation, forestry, geology and mineralogy, paleontology, hazardous materials, lands and access, livestock and grazing, recreation, scenic values and noise, socioeconomics, and transportation.
   
●The USFS will require that baseline environmental surveys be conducted, and these surveys will likely be above and beyond those conducted for exploration activities. On-the-ground surveys will typically include: cultural resources; vegetation and animal biological resources, including threatened, endangered, and sensitive species and migratory birds; soils resources; noxious and invasive species; jurisdictional waters; and hydrology, including geochemistry. These surveys, prepared in accordance with federal and state protocols, will identify the presence or absence of a particular resource and be used as the baseline to assess potential impacts. The same level of study will be required for any rights-of-way for new or improved access roads and water or power line corridors outside of the Plan boundary.

 

Other resources that will likely have to be addressed via desktop studies and stakeholder consultation include, but are not limited to: Native American religious concerns, environmental justice, paleontology, livestock grazing, recreation, wilderness, and lands with wilderness characteristics.

 

The requirements of the PoO document are fairly well defined. However, virtually all of the baseline data necessary for the impact assessment phase of the project will need to be collected, analyzed, and interpreted in conjunction with the USFS, to ensure that the information collected meets the data quality objectives of the program. A list of the types of studies that should be undertaken during the mine planning phase, in advance of the NEPA process, and in support of the acquisition of various other permits could include:

 

●Biological resources
   
●Cultural resources of all areas proposed for disturbance, unless an area has been surveyed within the past 10 years
   
●Hydrogeological assessment (may include impact modeling including potential for pit lakes)
   
●Jurisdictional waters and wetlands

 

211
 

 

●Geochemical characterization of mill feed, waste rock, and spent mill feed
   
●Air quality and meteorological parameters
   
●Traffic study
   
●Environmental justice and socioeconomics

 

The time necessary to prepare an EIS varies with the complexity of the project. The USFS is in the process of revising its NEPA procedures to reduce the time and cost of project analysis and decision making, permitting increased the scale of analysis, more work accomplished on the ground, and creative new ways to care for the land. The project proponent is also expected to enter into a cost recovery agreement with the USFS for the development of the EIS for specialist time, as well as pay a third-party contractor to prepare the EIS.

 

Idaho Copper will have to provide adequate operational and baseline environmental information for the USFS to analyze potential environmental impacts, as required by the NEPA, and to determine if the mining PoO will prevent significant impacts on the environment. Insufficient baseline data will slow down the EIS process. The same types of baseline information and level of detail collected for the proposed mine will also be necessary for the alternatives analyzed in the EIS. Baseline information will also have to be developed for rights-of-way for power and water line corridors, as well as access roads where applicable.

 

During the EIS process, applicant-committed environmental protection measures and mitigation measures will be identified for the various resources and become part of the mining PoO and record of decision. These measures will be used to monitor and mitigate potential impacts.

 

Other federal agencies—namely the U.S. Army Corps of Engineers (USACE), U.S. Environmental Protection Agency (U.S. EPA), and the U. S. Fish and Wildlife Service (USFWS)—may be involved in the EIS process as cooperating agencies; state agencies can also be cooperating agencies. The USACE may require permitting under Section 404 of the Clean Water Act (CWA) if jurisdictional waterways are affected by the mine development. The USFWS will become involved if the mine has the potential to affect threatened and endangered species.

 

17.2.2Idaho State Authorizations and Permits

 

As shown in Table 17-2, a number of Idaho state authorizations and permits will also be required from at least six different Idaho state departments and divisions. Much of the information developed for the federal permitting process will also be applicable to state permits. Idaho agencies typically process complete applications within the EIS process time frame.

 

17.2.3Boise County Permits

 

The Boise County Zone and Development Ordinance is applicable, and a Conditional Use Permit is required for mining activities on federal land located in Boise County.

 

17.3Monitoring

 

Environmental resources within the project area will be monitored prior to mine construction to develop baseline conditions, as well as during mining operations, reclamation, closure, and post-closure. Resources typically monitored include: climate and air quality; surface and ground water quality and quantity; geochemistry and management of ore, waste rock, and tailings; fisheries, wildlife, noxious weeds, and invasive species; effectiveness of stormwater controls, and reclamation success.

 

212
 

 

During the federal and state permitting processes, Idaho Copper will develop specific monitoring plans that incorporate state and federal monitoring requirements. The monitoring plans must meet the following objectives:

 

●Demonstrate compliance with the approved PoO and other federal or state environmental laws and regulations.
   
●Provide early detection of potential problems, and supply information that will assist in directing corrective actions, should they become necessary.
   
●Provide details on types and locations of monitoring devices, sampling parameters and frequency, analytical methods, reporting procedures, and procedures to respond to adverse monitoring results.

 

The TSF will typically be monitored during construction, operation, closure, and post-closure to verify compliance with design specifications, operating conditions, water management, water quality, and reclamation success, as required by Idaho regulations and USFS authorizations. Geochemical characterization of waste rock, ore, and tailings will also be undertaken prior to and during mining to guide dump and stockpile designs, stormwater controls, and monitoring. Post-closure monitoring of the waste rock dumps and TSF will be performed in compliance with federal and state permits.

 

Mine tailings impoundment structure designs in Idaho are regulated under Idaho Administrative Procedure Act (IDAPA) 37.03.05 by the Idaho Department of Water Resources. Idaho Copper will have to post a bond to provide a means by which the TSF can be placed in a safe, maintenance-free condition if abandoned by the owner without conforming to the approved abandonment.

 

17.4Reclamation

 

17.4.1Federal Reclamation Performance Bond

 

The USFS will require a reclamation performance bond under 36 CFR 228A that calculates costs based on the assumption that the operator defaults, and that the USFS must complete reclamation activities. Idaho has a memorandum of understanding that allows the state to recognize a valid bond held by the USFS as long as the bonds is in an amount as great as or greater than the required state bond. The USFS will accept the following bond instruments:

 

●Negotiable Treasury bills and notes that are unconditionally guaranteed as to both principal and interest in an amount equal at their par value to the penal sum of the bond
   
●Certified or cashier’s check, bank draft, post office money order, cash, assigned certificate of deposit, assigned savings account, blanket bond, or an irrevocable letter of credit equal to the penal sum of the bond.

 

The bond must be posted prior to surface disturbance occurring.

 

213
 

 

17.4.2State Reclamation Performance Bond

 

A reclamation plan and reclamation cost estimate will also have to be prepared for the project in accordance with IDAPA 20.03.02. Prior to beginning any surface mining on a mine panel covered by a PoO, an operator must submit to the director, on a surface mining reclamation bond form, a performance bond meeting the requirements of this rule. The amount must be the amount necessary to pay the estimated reasonable costs of reclamation required under the reclamation plan or permanent closure plan, including indirect costs. The reclamation bond may be in the form of a corporate surety bond, collateral bond, or letter of credit. The bond must be posted prior to surface disturbance occurring.

 

If ponds or lakes are created during the mining process and will remain after reclamation is complete, the Idaho Department of Water Resources requires the operator or landowner to obtain a water right. If a water right cannot be obtained prior to a plan being submitted, then the reclamation plan must include backfilling to an elevation above the local ground water table. Bond calculations must include those backfilling costs.

 

17.5Social and Community Impact

 

Idaho Copper has initiated consultation with various stakeholders, namely: government officials at all levels and local communities in regard to the potential social and community impacts or improvements that may occur as the project progresses. All groups are provided regular updates as the project is proceeding (Hilscher et al., 2018).

 

The project is actively engaged with all local communities and, for example, has discussed and committed to the restoration and reclamation work of the contaminated placer gold dredge tailings currently present in the Grimes Creek, subject to proceeding to mine development. Local communities and officials have come out in strong support of the project and are actively working with Idaho Copper on both the Grimes Creek project and future planning (Hilscher et al., 2018). The contaminated dredge tailings are not located on the CuMo property that is the subject of this technical report. There are no negotiations or agreements with the local communities at this time.

 

Federal and state planning and permitting processes mandate that the public have an opportunity to provide input. Idaho Copper, in coordination with federal and state agencies, will engage with the public during mandated public scoping and comment periods. Furthermore, Idaho Copper will have the opportunity to engage with stakeholders and local communities outside of the permitting processes to define potential infrastructure and community support needs. Until Idaho Copper presents an actual mining PoO for community feedback, there is no additional, reasonably available information to disclose.

 

Typically, small communities have competing social concerns when a mine is planned in the vicinity (i.e., the need for jobs versus changes to the fabric of the community resulting from an influx of mining and contractor employees moving to the community). Potential social issues that could arise from the CuMo project generally include:

 

●A shortage of temporary and permanent housing
   
●Insufficient capacity of schools, health care, law enforcement, solid waste disposal, and municipal infrastructure
   
●Insufficient road network capacity, leading to traffic slowdowns and degradation of road surfaces
   
●Increases in crime, drug abuse, and alcoholism

 

214
 

 

The public will have multiple opportunities to provide comments during the federal and state scoping and comments periods. In the past, Idaho Copper engaged with nearby communities concerning the exploration project. This practice is expected to continue during mine development, allowing Idaho Copper and the communities to identify salient issues and work toward resolution.

 

17.6Potential Issues

 

The 2011 Environmental Assessment, 2015 Supplement Environmental Assessment, and 2018 Supplemental Redline Environmental Assessment all identified resource values that had occurred or had the potential to occur in the CuMo project area and could affect mine permitting by changing the habitat and/or affecting individuals. These resource values included:

 

●The presence of Sacajawea’s bitterroot, a sensitive plant species. Slightly more than two dozen populations of Sacajawea’s bitterroot are known to exist, roughly three-fourths of them within Boise National Forest (USFS, 2019).
   
●The potential existence of rare plant habitat for other sensitive and watch plant species.
   
●The potential existence of Canada lynx (Lynx canadensis) habitat in the project area; this species is listed under the ESA.
   
●The potential existence of wolverine (Gulo gulo) habitat in the project area; this species was proposed for listing as a threatened species under the ESA in 2016.
   
●Other USFS sensitive species with potential habitat within the project area are:

 

○Boreal owl (Aegolius funereus)
   
○Flammulated owl (Psiloscops flammeolus)
   
○Great gray owl (Strix nebulosi)
   
○Mountain quail (Oreortyx pictus)
   
○Northern goshawk (Accipiter gentilis)
   
○White-headed woodpecker (Picoides albolarvatus)
   
○Grey wolf (Canis lupus)
   
○Gull trout (Salvelinus confluentus)

 

Fresh water supply from surface or ground water will likely be one of the most difficult hurdles to overcome. An estimated 30,000 gallons per minute (gpm) of fresh water could be required. All water rights in Idaho exist for beneficial uses, and all water in Idaho is owned by the public. Holding a water right does not give the water user ownership of the water; rather, it simply gives the user the right to divert water. The project will be located in Basin 65, which includes the entire Boise River Drainage (IDWR, 2018).

 

215
 

 

At this time and based on the studies undertaken, no issues have been identified that would materially impact the ability to eventually extract Mineral Resources at the project site; however, Idaho Copper should be prepared to address potential issues associated with, but not limited to:

 

●Consultation with Native American tribes
   
●Water logistics, including supply, rights, delivery system, and potential impacts
   
●Water management (e.g., stormwater, contact/non-contact water, water quality)
   
●Geochemistry of ore, waste rock, tailings solids and solution, and post-mining pit lake
   
●Management of ore stockpiles, waste rock dumps, and tailings during operations, closure, and post-closure
   
●Threatened, endangered, and special status plant and animal species
   
●Jurisdictional waters
   
●Transportation and access
   
●Reclamation and closure

 

Any issues identified during the permitting process will have to be analyzed, disclosed, and potentially mitigated.

 

The mine would be located in an area used for summer weekend dispersed recreation and fall big game hunting, well-known in the Boise area. The majority of previous public scoping comments made on the environmental assessments were against mining activities (although the commenters had been directed to address the proposed action, which was the exploration project, rather than the mining activities). Organized environmental groups such as the Idaho Conservation League and Sierra Club are keeping their constituents informed, citing issues of potential pollution of the Boise River, which supplies drinking water to the City of Boise. As such, well-funded, organized opposition to mining activities should be anticipated.

 

In general, the 1872 Mining Law as amended offers mineral rights holders a legal ability to develop the Mineral Resources on their mining claims. With regards to the CuMo project, the USFS has lead regulatory oversight in managing Idaho Copper’s activities. This stewardship is in accordance with mining regulation 36 CFR 228A and necessitates compliance with the requirements of the NEPA.

 

Idaho Copper is responsible for developing a project PoO that demonstrates to the USFS that proposed activities are reasonably incident to mining, are not impacting areas unnecessary to mining, and comply with applicable federal, state, and local laws and regulations. The USFS is unable to apply additional requirements that would have the effect of denying a mineral rights holder the right to explore and develop a mineral resource if the mineral rights holder has identified a viable opportunity, provided the mining PoO otherwise meets the intent of applicable laws and regulations (USFS, 2018).

 

At this time, a detailed discussion on mine closure and reclamation cannot be completed. However, Idaho Copper will be required to post reclamation bonds to cover direct and indirect costs related to site stabilization, water treatment as needed, post-reclamation and -mining monitoring, and public safety.

 

216
 

 

17.7Mine Closure – General Discussion

 

The project proponent plan for closure and reclamation of mining disturbances on all affected land will need to address comprehensive Idaho and USFS closure and reclamation requirements. Regulatory authorities will require that a surety or bond in an amount sufficient to cover third-party costs to physically and chemically stabilize the site be posted prior to the onset of mining. A reclamation cost estimate will need to be prepared that will be approved by state and federal agencies prior to any mining surface disturbance; the bond amount must be posted using an approved financial instrument. The financing costs associated with such a surety have not been modeled. The initial submissions will require a detailed discussion on how the mining disturbance will be physically and chemically stabilized, and the duration of the closure process as reclamation and closure proceed will be analyzed in the EIS.

 

The plans for final closure must address the long-term potential for surface and ground water contamination from the closed facility, as well as the stabilization of slopes, soils, and vegetation on mining disturbances. Typically, the closure permitting process involves a decommissioning plan or a permanent capping plan along with a post-closure monitoring commitment. Permit applicants should consider methods of closing a facility that will eliminate the possibility of future surface and ground water contamination and thereby eliminate the need for long-term water treatment and monitoring.

 

At the current IA phase of the CuMo project, a site-specific closure cost estimate has not yet been developed. An approximate closure cost of $60M ($75M with 25% contingency), has been assumed for initial economic evaluation to include expected closure, reclamation, and water treatment. This estimate is not based on site-specific considerations and should be considered order-of-magnitude only within the accuracy of a IA-level study. During the PFS, a more detailed assessment of site conditions based on project infrastructure trade-off studies is warranted.

 

After mining operations cease, all buildings, infrastructure, and facilities associated with the CuMo Mine that have not been identified for a specific post-mining use must be removed from the site during the reclamation, salvage, and site demolition phase. These activities will generally include, but not be limited to the:

 

●Regrading to a stable configuration, placement of growth media, and seeding of disturbed surfaces without a post-mining use; it is not safe or practical to place growth media on open-pit highwalls.
   
●Removal of surface pipelines and power lines and the secure and stable abandonment of underground pipelines (including removal if required)
   
●Demolition of process facilities and salvage or removal of equipment and residual reagents for proper disposal
   
●Managing the drain-down solution to reduce the volume, which process may include the construction and operation of an evapotranspiration cell. Depending on site conditions, use of a water-treatment plant and discharge of treated water may be necessary to prevent unauthorized discharges of mine water that do not meet water quality standards.
   
●Ongoing monitoring of closure compliance for surface and ground water quality, soil stabilization, and revegetation success
   
●Maintaining public safety features such as warning signs, pit berms, and other barriers

 

To the extent practicable, reclamation and closure activities will be conducted concurrently with mining and disturbance activities to reduce the overall final reclamation and closure costs, minimize environmental liabilities, and limit the necessity of surety or bonding costs.

 

217
 

 

18 Capital and Operating Costs

 

This chapter presents capital and operating cost estimates for the initial assessment. The Base Case includes Measured, Indicated and Inferred Mineral Resources; the Measured and Indicated (M&I) Case excludes Inferred Mineral Resources from processing and revenue. Material selected at the shovel is delivered to the primary crusher or run-of-mine (ROM) stockpile. After primary crushing, material passes through two belt-sorting stages. The second stage produces middlings, an intermediate product stored for later milling. The capital estimate, facility scope and expenditure timing are common to both cases; operating costs reflect each case’s material movements and processing duties. The results are carried into the Economic Analysis chapter. Scheduled resource material is not a Mineral Reserve estimate.

 

The excluding-Inferred case retains the original pit excavation quantities and annual mining sequence. Inferred material previously assigned to processing is treated as waste, while retained Measured and Indicated material follows the original routing and calendar, including stockpile placement and reclaim. Unused processing capacity is not refilled. The case also exchanges 3.85 Mst between waste-dump and tailings-construction deliveries in Years 18 and 20. Its haulage costs include that routing adjustment; this is not an independently optimized M&I-only pit and schedule.

 

18.1Capital Cost Estimate

 

The project capital estimate totals US$2,521 million, including US$504 million contingency. It covers mining, processing and material handling, site infrastructure, environmental and closure works, general site facilities and owner’s costs. Preproduction capital is US$1,169 million, expansion capital is US$658.26 million, and sustaining capital is US$693 million. The estimate follows the production schedule and discipline estimates presented in this report.

 

No separate project-wide operating-cost contingency is identified in this economic analysis. Allowances already included in discipline unit rates remain within those costs and are not assumed to be zero.

 

The principal estimating risks are preliminary facility definition, equipment and construction quantities, unit prices, haulage productivity, and long-term maintenance and equipment reuse. These affect both the scale and timing of expenditure.

 

Project capital by discipline and expenditure timing is summarized in Table 18-1.

 

218
 

 

Table 18-1 Project Capital Expenditure by Timing Group

 

Component Preproduction
US$M
Expansion
US$M
Sustaining
US$M
Total
US$M
Site Infrastructure 64 7 0 72
Mining 228 267 357 851
Processing 622 251 131 1,004
Environmental and Closure 0 0 60 60
General and Administrative 14 2 7 23
Owner’s Costs 7 0 0 7
Subtotal Capital 935 527 555 2,017
Contingency (25.00%) 234 132 139 504
Total Capital 1,169 658 693 2,521

 

Source: NLM (2026). Note. Preproduction: Years -3 to -1; expansion: Years 1 to 4; sustaining: Year 5 onward, including closure after operations. Contingency is 25% of direct capital. Totals may differ from the sum of rounded components. US$M = million US dollars

 

18.1.1Mining Capital Costs

 

The capital and operating cost estimates are preliminary, with an estimated accuracy of approximately ±50%, reflecting the current level of engineering definition. The accuracy range is not a statistical confidence interval.

 

The QP responsible for the Mining Methods chapter developed the mining cost estimate from the production schedule and equipment requirements described in Section 13. Mining capital totals US$851 million before contingency, comprising US$78 million for prestripping, US$753 million for primary equipment and US$19 million for auxiliary equipment. The equipment purchase schedule includes additions and replacements during pit mining; purchase quantities are cumulative over the mine life.

 

The mining estimate is based on the scheduled material movements, route-dependent haul cycles, operating-hour criteria and equipment requirements described in Section 13. Equipment purchase prices use published InfoMine benchmarks dated 27 February 2024, increased by 6.0% in the estimate. Equipment operating costs include energy, lubricants, tires, maintenance and overhaul parts. Personnel costs and equipment purchases are estimated separately from these hourly operating costs.

 

Peak operating fleet requirements and workforce estimates are presented in Table 13-25 and Table 13-26 of the Mining Methods chapter.

 

Primary haulage is calculated at a 360-st payload. Four cable shovels are purchased for pit mining; two are retained for middlings reclaim after pit completion. The equipment program includes truck and support-equipment replacements and shovel rebuild allowances. No additional late-life primary-shovel purchase is included for the reclaim operation.

 

Capital contingency is 25.0% of the direct mining capital estimate. Preproduction expenditure occurs in Years -3 to -1, expansion expenditure in Years 1 to 4, and sustaining expenditure from Year 5 onward. These groups reflect the modeled expenditure timing.

 

Mining capital expenditure by timing group is summarized in Table 18-2.

 

219
 

 

Table 18-2 Mining Capital Expenditure Before Contingency

 

Component Preproduction
US$M
Expansion
US$M
Sustaining
US$M
Total
US$M
Prestripping 78 0 0 78
Primary Mining Equipment 143 265 345 753
Auxiliary Mining Equipment 6 1 12 19
Total Mining 228 267 357 851

 

Source: NLM (2026). Note. Totals may differ from the sum of rounded components. US$M = million US dollars

 

Equipment prices and cumulative procurement quantities are summarized in Table 18-3. Purchases include both ramp-up additions and replacement units; they are not simultaneous operating fleet counts.

 

Table 18-3 Mining Equipment Purchase Cost Estimate

 

Equipment Estimating Class Unit Cost
US$
LOM
Purchases
Capital
US$M
CAT: MD6310; Other: PV291-PV311 3,753,354 8 30
Other: D60 1,176,600 3 4
Komatsu: 4100 29,680,000 4 119
CAT: D10; Komatsu: D375 2,209,040 3 7
Wheel Dozer - 900 Horsepower 3,486,128 10 35
Mine Haul Truck - 360 Short Ton Operating Payload 6,137,930 88 540
CAT: D11; Komatsu: D475 3,377,478 3 10
CAT: 16 710,942 4 3
Water Truck – 20,000 Gal 1,600,388 4 6
Light Vehicle - 3/4 Ton 65,508 106 7
Light Tower – 20 kW 35,510 16 0.57
Explosives Loading Truck - ANFO 309,944 3 0.93
Skid-Steer Loader – 3,400 lb Lift 106,424 6 0.64
Light Vehicle - 1 Ton 68,688 7 0.48
Pump System - 5x3-12in 24,274 12 0.29
Fuel and Lube Truck - 350 Horsepower 455,906 8 4
Field Service Truck - 350 Horsepower 353,298 9 3
Forklift - 7 Ton Lift 78,758 12 0.95
Dispatch System - 90 Unit Fleet 1,794,686 1 2

 

Source: NLM (2026). Note. Equipment capital excludes contingency. LOM purchases are cumulative additions and replacements.

 

ANFO = Ammonium Nitrate/Fuel Oil , gal = gallon, in = inch, kW – kilowatt, lb = pound, US$ - United States dollar, US$M = million US dollars

 

220
 

 

18.1.2Processing Capital Costs

 

The capital and operating cost estimates are preliminary, with an estimated accuracy of approximately ±50%, reflecting the current level of engineering definition. The accuracy range is not a statistical confidence interval.

 

Processing capital totals US$1,004 million before contingency, as shown in Table 18-4. The estimate includes an initial mill capacity of 35,000 stpd, expansion to 70,000 stpd from Year 4, crushing and sorting facilities, and the equipment needed for stockpile placement, reclaim and sorter-reject disposal. Molybdenum concentrate is shipped to off-site processors for roasting; an on-site roaster is not included in the current project capital estimate.

 

Plant, crushing and sorting capital estimates are based on the initial 35,000-stpd plant and expansion to 70,000 stpd presented in this report. Crushing and milling costs use the processing estimates presented below; the separate sorting operating-cost basis is described in Section 18.2.2. The cost estimate was developed by Barr based on the IA design concept and InfoMine cost information. Detailed processing scope and the underlying supplier-estimate basis remain preliminary.

 

The capital summary applies a single 25% contingency to direct project capital. Initial plant and sorting expenditure is incurred before production, plant expansion is assigned to Years 1 to 4, and later equipment replacements are classified as sustaining capital.

 

Table 18-4 Processing Capital Expenditure Before Contingency

 

Component Preproduction
US$M
Expansion
US$M
Sustaining
US$M
Total
US$M
Material Placement and Rehandling Equipment 0 88 131 219
Initial 35,000 stpd Process Plant 268 0 0 268
Expansion To 70,000 stpd Process Plant 0 162 0 162
Crushing 73 0 0 73
Sorting 281 0 0 281
Total Processing 622 251 131 1,004

 

Source: Barr (2026). Note. Material handling includes stockpile placement and reclaim and sorter-reject disposal. Contingency is included in the project summary, not in these component amounts. stpd = short ton per day, US$M = million US dollars

 

Dedicated material-handling equipment comprises 210-st trucks, large wheel loaders, and support equipment. After pit mining ends, retained primary 360-st haul trucks and cable shovels undertake middlings reclaim. Their original purchases are included in mining capital; their reclaim operating and rebuild costs are included in the material-handling estimate.

 

Dedicated material-handling equipment prices and scheduled purchases use the mining and rehandling estimates presented in Table 18-5. They are separate from the plant, crushing and sorting capital estimates.

 

221
 

 

Table 18-5 Dedicated Material Handling Equipment Purchase Costs

 

Equipment Class Unit Price
US$
LOM
Purchases
Capital
US$M
Large Wheel Loader 10,070,000 11 111
D10 / D375 Crawler Dozer 2,209,040 3 7
900 Horsepower Wheel Dozer 3,486,128 2 7
Cat 16 Grader 710,942 3 2
Light Vehicle 65,508 7 0.46
Light Tower 35,510 20 0.71
210-st Dedicated Haul Truck 3,816,000 24 92
Total     219

 

Source: Barr (2026). Note. Equipment purchases total US$219.25 million before contingency. Quantities are cumulative additions and replacements over the operating schedule and do not represent one simultaneous fleet. st = short ton, US$ = United States dollar, US$M = million US dollars

 

18.1.2.1Assumptions

 

Geotechnical

 

A detailed geotechnical and drainage assessment of the proposed plant site is not yet available. The process estimate assumes conventional site preparation; special ground treatment is not separately identified. Site access, power and water allowances are summarized under site infrastructure.

 

Base Date and Exchange Rates

 

All costs are expressed in United States dollars. The mining estimate uses published equipment prices dated 27 February 2024 with a 6% purchase-price uplift, together with the fuel, power and labor assumptions described below. Processing and other discipline costs use the estimates presented in this report. No additional blanket foreign exchange adjustment is applied to those US-dollar inputs.

 

Electricity Supply

 

It is assumed that purchased grid power will be available to satisfy demand for the proposed plant. The site infrastructure estimate includes US$10 million for electrical supply before contingency. The process estimating basis includes high and medium voltage switchgear and distribution within the plant boundary; individual drive switchgear and cabling are included in estimating allowances for each plant area.

 

Water Supply

 

A water supply capable of meeting processing demand is assumed to be available. Site infrastructure includes US$3.0 million for water supply and US$2.5 million for wastewater treatment before contingency. Piping and distribution within the plant boundary form part of the process estimate.

 

18.1.2.2Contingency

 

Contingency is 25% of direct project capital, including mining, processing, site infrastructure, environmental and closure capital, general site facilities and owner’s costs. The allowance totals US$504 million and follows the timing of the underlying expenditures.

 

222
 

 

18.1.2.3Owner’s Costs

 

Owner’s costs of US$7.4 million are included before contingency in preproduction capital. They comprise US$0.66 million of preproduction environmental costs and US$6.7 million of preproduction general site and administrative costs.

 

18.1.2.4Construction Management

 

Construction management of US$3.50 million is included in general site capital before contingency. No separate 3% project fee is added to the current project capital summary.

 

18.1.2.5Escalation

 

The cash-flow forecast holds the capital and operating cost estimates constant through the modeled periods. No additional escalation for future inflation or exchange-rate movement is applied.

 

18.1.3Tailings Storage Facilities Capital Costs

 

The capital and operating cost estimates are preliminary, with an estimated accuracy of approximately ±50%, reflecting the current level of engineering definition. The accuracy range is not a statistical confidence interval.

 

The tailings capital allowance uses modeled initial tailings and crest elevations of 5,995 ft and 6,000 ft, increasing to final elevations of 6,695 ft and 6,700 ft. TSF capital is US$15 million before contingency, allocated between preproduction and Years 1 to 4 within site infrastructure.

 

The TSF embankment is developed by downstream construction using suitable mine waste placed in approximately 3-ft compacted lifts. The mine plan routes sorter rejects to the waste-rock disposal area at Charlotte Gulch. Primary mine-waste haulage is included in mining costs, while sorter-reject handling is included in processing costs. Waste-area dozers undertake spreading, and the TSF construction estimate allows for compaction. A full impoundment liner is not assumed; an upstream-slope liner may be required following further geotechnical and seepage assessment.

 

The estimate makes provision for general foundation clearing within the tailings footprint ahead of waste placement and stripping overburden beneath the embankment to expose bedrock. Stripped overburden is stockpiled for subsequent reclamation. Foundation preparation and embankment construction requirements will be refined through the site geotechnical investigation.

 

Subsequent TSF construction follows the tailings deposition schedule. The process operating estimate includes US$211 million for TSF expansion. This is separate from the US$15 million capital allowance and from the mine-waste and sorter-reject haulage costs; those haulage duties are not added again to the TSF allowance.

 

18.1.4Site Infrastructure Capital Costs

 

The capital and operating cost estimates are preliminary, with an estimated accuracy of approximately ±50%, reflecting the current level of engineering definition. The accuracy range is not a statistical confidence interval.

 

223
 

 

Site infrastructure capital totals US$72 million before contingency, as summarized in Table 18-6. The estimate includes access, electrical supply, water supply, TSF capital, wastewater treatment and fuel supply.

 

Access, power, water, fuel and TSF allowances follow the infrastructure estimates presented in this report. The costs reflect preliminary facility definition and require refinement against the selected design scope.

 

Table 18-6 Site Infrastructure Capital Expenditure Before Contingency

 

Component Preproduction
US$M
Expansion
US$M
Sustaining
US$M
Total
US$M
Access Roads 40 0 0 40
Electrical Power 10 0 0 10
Water Supply 3 0 0 3
Tailings Facilities 7 7 0 15
Wastewater Systems 3 0 0 3
Fuel Facilities 1 0 0 1
Total Infrastructure 64 7 0 72

 

Source: Barr (2026). Note. TSF expansion operating costs are reported under processing. US$M = million US dollars

 

18.1.5Environmental and Closure Capital Costs

 

The capital and operating cost estimates are preliminary, with an estimated accuracy of approximately ±50%, reflecting the current level of engineering definition. The accuracy range is not a statistical confidence interval.

 

Environmental and closure capital uses the allowances presented in this report. It totals US$60 million before contingency (see Table 18-7), comprising US$30 million for reclamation and US$30 million for water treatment. These expenditures are scheduled in Years 41 to 55, extending beyond processing in Year 46, and are included in sustaining capital. Operating environmental costs are reported separately below.

 

The US$60 million direct allowance is carried in modeled capital and totals US$75 million with 25% contingency. It is not a site-specific closure or reclamation liability estimate. The modeled allowance requires reconciliation with the closure plan, including the scope and duration of post-closure water treatment and monitoring.

 

Table 18-7 Environmental and Closure Capital Before Contingency

 

Component Preproduction
US$M
Expansion
US$M
Sustaining
US$M
Total
US$M
Reclamation 0 0 30 30
Water Treatment 0 0 30 30
Total Environmental And Closure 0 0 60 60

 

Source: Barr (2026). Note. Reclamation and water-treatment capital is scheduled at US $2.00 million per component per year in Years 41 to 55 and is included in sustaining expenditure. US$M = million US dollars

 

224
 

 

18.1.6General Site Capital and Owner Costs

 

The capital and operating cost estimates are preliminary, with an estimated accuracy of approximately ±50%, reflecting the current level of engineering definition. The accuracy range is not a statistical confidence interval.

 

General site capital totals US$23 million before contingency. It includes buildings, light vehicles, general mobile equipment and construction management (see Table 18-8). Owner’s preproduction environmental and site administration costs of US$7 million are carried separately in the project capital summary.

 

Table 18-8 General Site Capital Expenditure Before Contingency

 

Component Preproduction
US$M
Expansion
US$M
Sustaining
US$M
Total
US$M
Buildings 10 0 0 10
Light Vehicles 0.60 0.60 3 5
General Mobile Equipment 0 1 4 5
Construction Management 4 0 0 4
Total General Site Capital 14 2 7 23
Owner’s Costs 7 0 0 7

 

Source: Barr (2026). Note. Owner’s costs are separate from the general site capital total. US$M = million US dollars

 

18.1.7Capital Cost Estimate Exclusions

 

The capital estimate includes preproduction, expansion and sustaining expenditure, closure allowances and the owner’s costs stated above. Working capital, property holding costs, concentrate selling charges and income taxes are treated separately in the economic analysis. Financing costs and sunk expenditure are excluded from project capital. Further study costs and changes to the adopted scope are not added to the current estimate.

 

●On-site power generation; grid power is assumed to be purchased.

 

●Project and land acquisition and sunk costs incurred before the modeled development period.

 

●Future pre-feasibility and feasibility studies, additional exploration and test work beyond the adopted development scope.

 

●Financing interest and other project financing costs.

 

●Future inflation, exchange-rate movement and changes to the adopted project scope.

 

18.2Operating Cost Estimate

 

Life-of-mine operating expenditure (OPEX) totals US$16,247 million including Inferred Mineral Resources and US$14,830 million excluding Inferred. The respective mill-feed quantities are 1,127 Mst and 971 Mst, giving unit costs of US$14.42/st and US$15.28/st milled. Mining costs end with pit operations, while processing and stockpile reclaim continue through Year 46. Mine haulage, process material handling, TSF expansion and site administration are counted once.

 

225
 

 

Operating costs by discipline are summarized in Table 18-9.

 

Table 18-9 Summary of Operating Costs

 

Discipline

Including Inferred

US$M

Including Inferred

US$/st

Excluding Inferred

US$M

Excluding Inferred

US$/st

Mining 5,428 4.82 5,464 5.63
Processing 10,377 9.21 8,923 9.19
Environmental and Reclamation 42 0.04 42 0.04
Site G&A 401 0.36 401 0.41
Total Operating Costs 16,247 14.42 14,830 15.28

 

Source: NLM (2026). Note. Unit costs use each case’s own mill feed: 1,126.81 Mst including Inferred and 970.60 Mst excluding Inferred. Environmental and site G&A totals are the same in both cases. Capitalized prestripping, capital expenditure, property holding, concentrate selling charges, income taxes and working capital are excluded and treated separately in the economic analysis. Totals may differ from the sum of rounded components. G & A = General and Administrative, st = short ton, US$ = United States dollar, US$M = million US dollars

 

Capitalized preproduction mining costs of US$78 million are included in mining capital and excluded from the operating total. Environmental costs and general site administration are included as separate operating categories. Processing includes material handling and TSF expansion; concentrate realization charges are carried separately in the economic analysis.

 

18.2.1Mine Operating Costs

 

The capital and operating cost estimates are preliminary, with an estimated accuracy of approximately ±50%, reflecting the current level of engineering definition. The accuracy range is not a statistical confidence interval.

 

Mining operating costs total US$5,428 million including Inferred and US$5,464 million excluding Inferred. They include drilling, blasting, loading, haulage, support and mine administration. Preproduction mining costs of US$78 million are capitalized as prestripping in both cases and excluded from operating costs. The schedule-linked estimate applies the operating hours, fleet and labor basis in the Mining Methods chapter.

 

The estimate uses diesel at US$4.87/US gal and electricity at 8.62 US cents/kWh. Base hourly wages are US$35 for truck drivers, US$40 for drillers and loader operators, and US$45 for journeyman mechanics. A 40% burden is applied to regular pay; overtime is costed at 1.50 times the base hourly wage. Salaried positions carry a 40% burden. The workforce and paid-hour assumptions are distinct from effective equipment operating hours.

 

The haulage estimate uses route-dependent travel distances, gradients, loading and dumping time and the 360-st truck payload. Waste delivery to Charlotte Gulch and the tailings embankment is included in primary mining. Equipment fuel, electricity, maintenance, and rebuild costs and the workforce in Section 13.7 are applied to the scheduled equipment hours.

 

Mining unit costs are US$4.82/st milled including Inferred and US$5.63/st excluding Inferred. Each uses its own life-of-operation mill feed. These rates are distinct from cost per short ton of total primary material mined. Primary excavation remains 3,083 Mst in both cases; differences in waste destinations affect haulage cost.

 

226
 

 

Mining costs by activity, including the separate capitalized preproduction amounts, are presented in Table 18-10.

 

Table 18-10 Mining Costs by Activity

 

Activity

Shared Preproduction

Capital US$M

Including Inferred

OPEX US$M

Excluding Inferred

OPEX US$M

Drilling 3 211 211
Blasting 6 445 445
Loading 6 436 436
Haulage 42 3,724 3,760
Support 6 205 205
Mining G&A 15 407 407
Total Mining 78 5,428 5,464

 

Source: NLM (2026). Note. Capitalized prestripping is excluded from the operating total and included in mining capital. Totals may differ from the sum of rounded components. G & A = General and Administrative, US$M = million US dollars

 

ROM reclaim, sorter-reject disposal, middlings placement and middlings reclaim are allocated to processing costs and are excluded from the mining operating total. Reclaim uses retained cable shovels and primary haul trucks after their release from pit duty; their reclaim operating and rebuild costs are included in the separate material-handling estimate.

 

18.2.2Crushing and Sorting Operating Costs

 

The capital and operating cost estimates are preliminary, with an estimated accuracy of approximately ±50%, reflecting the current level of engineering definition. The accuracy range is not a statistical confidence interval.

 

Crushing operating costs total US$1,636 million including Inferred and US$1,354 million excluding Inferred. Sorting costs are US$128 million and US$106 million, respectively. Annual costs follow the quantities crushed and sorted and the retained operating periods.

 

Crushing costs use the processing estimates presented in this report. Sorting operating costs use annual all-in estimates. The underlying sorting rate and fixed-variable breakdown are not separately identified in that annual estimate. In the excluding-Inferred case, sorting costs are allocated by retained incoming fresh and ROM feed.

 

Sorter-reject disposal, middlings placement and middlings reclaim are included in the separate processing material-handling estimate. Loading, haulage and support total US$1,275 million including Inferred and US$1,110 million excluding Inferred. These costs are not added to mining operating costs.

 

18.2.3Processing and Material Handling Operating Costs

 

The capital and operating cost estimates are preliminary, with an estimated accuracy of approximately ±50%, reflecting the current level of engineering definition. The accuracy range is not a statistical confidence interval.

 

227
 

 

Processing and material-handling operating costs total US$10,377 million including Inferred and US$8,923 million excluding Inferred. These are summarized in Table 18-11. The milling cost basis is US$6.96/st milled for the initial 35,000-stpd plant in Years 1 to 3 and US$6.30/st for the expanded 70,000-stpd plant thereafter. The same adopted unit-cost basis applies to the retained feed in each case. Processing also includes crushing, sorting, TSF expansion and process vehicles and mobile equipment.

 

Table 18-11 Processing Operating Costs by Component

 

Component Including Inferred
Operating Cost US$M
Excluding Inferred
Operating Cost US$M
Rehandling Loading and Support 522 464
Rehandling Haulage 754 646
Sorting Operations 128 106
Tailings Facility Expansion 211 211
Process Vehicles and Mobile Equipment 5 5
Crushing 1,636 1,354
Initial Plant Milling (35,000 stpd) 240 239
Expanded Plant Milling (70,000 stpd) 6,881 5,898
Total Processing Operating Cost 10,377 8,923

 

Source: NLM (2026). Note. Initial-plant and expanded-plant milling costs apply to their respective periods. Material-handling costs are included in this total. stpd = short ton per day, US$M = million US dollars

 

Material handling includes ROM reclaim, sorter-reject disposal, middlings placement and reclaim. Loading and support costs total US$522 million including Inferred and US$467 million excluding Inferred; haulage costs total US$754 million and US$646 million. Dedicated loaders and 210-st trucks undertake early handling, and retained mining equipment undertakes later reclaim.

 

Material-handling costs use the annual loading, haulage and support estimates and the scheduled duties presented in this report. The excluding-Inferred case allocates retained classified quantities to the original handling calendar. Equipment and haulage criteria are described in the Mining Methods chapter.

 

18.2.3.1Labor

 

The original process estimating basis developed site labor costs from personnel numbers, positions, salaries and overheads for operations of comparable size and location, with on-cost factors applied to base salaries.

 

18.2.3.2Power

 

Power is assumed to be supplied from the local grid by Idaho Power. The current mining estimate uses US$0.0862/kWh. Processing power is included in the adopted annual milling costs; a separate processing electricity rate is not applied in the project summary.

 

18.2.3.3Maintenance Consumables and Services

 

Maintenance consumables and services in the original process estimating basis were estimated as a percentage of installed plant cost using comparable operations and an assumed Bond abrasion index of 0.25, a measure of material abrasiveness used to estimate equipment wear.

 

228
 

 

18.2.3.4Reagents and Consumables

 

The original process estimating basis used metallurgical test work and comparable operations to estimate reagent consumptions by mineralization type and production conditions.

 

Budget prices for major reagents in the original process estimate included delivery to site; duties, brokerage, handling charges and applicable taxes were excluded from those reagent prices.

 

18.2.3.5Environmental Operating Costs

 

The capital and operating cost estimates are preliminary, with an estimated accuracy of approximately ±50%, reflecting the current level of engineering definition. The accuracy range is not a statistical confidence interval.

 

Environmental operating costs total US$42 million in each resource case. The estimate includes environmental personnel, monitoring, permits and vehicles over the operating schedule. The separate closure and water-treatment allowances are carried in capital and are not added to operating costs. These operating allowances do not establish the adequacy of the full post-closure treatment and monitoring provision.

 

18.2.4General Site and Administrative Costs

 

The capital and operating cost estimates are preliminary, with an estimated accuracy of approximately ±50%, reflecting the current level of engineering definition. The accuracy range is not a statistical confidence interval.

 

General site and administrative operating costs total US$401 million in each case (see Table 18-12). They are equivalent to US$0.36/st milled including Inferred and US$0.41/st excluding Inferred because the feed quantities differ. The estimate includes personnel, safety, human resources, accounting and purchasing, supplies and software, training, light vehicles, transport, road maintenance, legal costs and overheads. Mining administration of US$407 million is already included in mining costs and is excluded from this site total.

 

229
 

 

Table 18-12 General Site and Administrative Operating Costs

 

Component Operating Cost
US$M
Personnel 45
Building Maintenance 0.99
Safety 27
HR 22
Accounting - Purchasing 43
Supply, Software, Training 77
Light Vehicles - Pickup, etc 43
Mobile Office Trailers 0.78
Miscellaneous Expenses 9
Busing / Transportations 86
Access Roads to Minesite 16
G&A Labor / Personnel: Other 8
General Mobile Equipment 5
Offsite Overhead Expenses 7
Legal, Audits, MSHA, etc 7
Donations, Public Relations 5
Total General and Administrative Operating Costs 401

 

Source: Barr (2026). Note. Values apply to both resource cases. Access-road maintenance of US$15.75 million is included in this total. US$M = million US dollars

 

230
 

 

19 Economic Analysis

 

19.1Cautionary Statements

 

19.1.1Certainty of Initial Assessment

 

The initial assessment is preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to have the modifying factors applied to them that would enable their classification as Mineral Reserves. There is no certainty that the initial assessment will be realized.

 

19.1.2Mineral Resources are Not Reserves

 

Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

 

19.2Analysis Basis

 

The economic analysis evaluates annual unlevered project cash flows from mine development, processing and concentrate sales. It includes capital expenditure, operating expenditure (OPEX) and property holding costs, concentrate deductions, working capital and taxes. Debt financing, interest and financing cash flows are excluded. The mine plan and metallurgical production form the physical basis of the analysis. Net smelter revenue is sales revenue after the assumed concentrate and selling deductions.

 

This chapter presents the economic analysis for the initial assessment under Subpart 229.1300 of Regulation S-K. The technical report summary presents the economic disclosure specified by Item 601(b)(96) of Regulation S-K. The analysis includes results with and without Inferred Mineral Resources. The Base Case includes Measured, Indicated and Inferred Mineral Resources. The Measured and Indicated (M&I) Case excludes Inferred Mineral Resources from processing and revenue. These cases are also identified as including Inferred and excluding Inferred, respectively.

 

The economic analysis is expressed in 2026 US dollars. Metal prices and unit-cost assumptions are held constant throughout the forecast. Project returns are measured by net present value (NPV), internal rate of return (IRR) and payback. NPV is the sum of discounted project cash flows; IRR is the discount rate at which NPV is zero. Payback measures the time required to recover project capital from cash flows after production commences. Discounted cash flow uses an 8.0% annual rate, with the first preproduction year, Year −3, undiscounted. Year 1 is the fourth annual cash-flow period and is discounted for three years to Year −3. Years −3 to −1 cover development and prestripping, followed by production Years 1 to 46. Closure and water-treatment capital payments extend through Year 55.

 

US$M denotes million US dollars. Mass quantities use US short tons (st), where 1 st equals 2,000 lb; Mst denotes million short tons. Mlb and Moz denote million pounds and million troy ounces, respectively. Capital intensity uses metric tonnes of annual payable metal. Cu, Mo, Ag, and Re denote copper, molybdenum, silver and rhenium, respectively.

 

Section 19.3 compares the two resource cases and presents their common assumptions and estimating basis. Sections 19.5 and 19.6 present the results, annual production, and annual cash flows including and excluding Inferred Mineral Resources, respectively. The detailed operating-cost, cash-cost, capital-intensity and sensitivity results in Section 19.5 apply to the case including Inferred.

 

231
 

 

19.3Comparison of Economic Results

 

At an 8.00% discount rate, pre-tax NPV is US$2,308 million including Inferred Mineral Resources and US$1,823 million excluding Inferred. After-tax NPV is US$1,878 million including Inferred and US$1,482 million excluding Inferred. The respective pre-tax IRRs are 19.84% and 18.26%, and after-tax IRRs are 18.50% and 17.04%. Payback from production commencement is 5.83 years before tax and 5.86 years after tax including Inferred, compared with 5.92 and 5.96 years excluding Inferred. Table 19-1 presents both cases on the same basis.

 

This initial assessment is preliminary and includes Inferred Mineral Resources that are too speculative geologically for the modifying-factor assessment needed to categorize them as Mineral Reserves. There is no certainty that the assessment will be realized. Mineral Resources, unlike Mineral Reserves, do not have demonstrated economic viability. Inferred material accounts for 17.13% of primary mineralized feed and 13.86% of evaluated mill feed, including stockpile reclaim, in the including-Inferred case. Both cases retain the stated assumptions and the excluding-Inferred case includes the construction-rock routing adjustment described in Section 19.6.2.

 

Table 19-1 Summary of Potential Project Economics

 

Measure Unit Including Inferred Excluding Inferred
Pre-Tax NPV at 8% US$M 2,308 1,823
After-Tax NPV at 8% US$M 1,878 1,482
Pre-Tax IRR % 19.84 18.26
After-Tax IRR % 18.50 17.04
Pre-Tax Payback years 5.8 5.9
After-Tax Payback years 5.9 6.0
Undiscounted Pre-Tax Cash Flow US$M 13,734 11,545
Undiscounted After-Tax Cash Flow US$M 11,372 9,591
Gross Recovered-Metal Revenue US$M 35,132 31,223
Non-Payable Metal And Off-Site Deductions US$M 2,620 2,316
Net Smelter Revenue US$M 32,513 28,907
Operating Cost US$M 16,247 14,830
Holding Cost US$M 11 11
Capital Expenditure US$M 2,521 2,521

 

Source: NLM (2026). Note. IRR = internal rate of return, NPV = net present value, US$M = U.S. dollars in millions. Totals are calculated before rounding; displayed components may not sum to totals.

 

Inferred Mineral Resources comprise 240 Mst, or 17.13%, of the 1,401 Mst of primary mineralized feed used in the including-Inferred economic analysis. This reference point is after loading-face selection and before crushing and sorting, including material placed in ROM storage. The Inferred contribution to evaluated mill feed, including stockpile reclaim, is 156 Mst, or 13.86% of 1,127 Mst. These mass percentages are not shares of revenue or NPV. The excluding-Inferred case contains no Inferred contribution to processing or revenue.

 

232
 

 

Table 19-2 Resource Classification and Production Comparison

 

Measure Unit Including Inferred Excluding Inferred
Total Primary Mining Mst 3,083 3,083
Inferred Primary Mineralized Feed Mst 240 0
Inferred Share of Primary Mineralized Feed % 17.13 0.00
Primary Mineralized Feed Mst 1,401 1,161
Primary Waste Mst 1,682 1,922
Evaluated Mill Feed Mst 1,127 971
Inferred Evaluated Mill Feed Mst 156 0
Inferred Share of Evaluated Mill Feed % 13.86 0.00
Payable Copper Mlb 1,748 1,509
Payable Molybdenum Mlb 906 819
Payable Silver Moz 59 50
Mining Operating Cost US$M 5,428 5,464
Processing Operating Cost US$M 10,377 8,923
Preproduction Capital US$M 1,169 1,169
Expansion Capital US$M 658 658
Sustaining and Closure Capital US$M 693 693
Processing Years years 46 46

 

Source: NLM (2026). Note. Primary mineralized feed is measured after loading-face selection and before crushing/sorting, including ROM receipts. Evaluated mill feed includes stockpile reclaim. These scheduled quantities are not Mineral Reserve estimates. Mlb = millions of pounds, Moz = million ounces, Mst – million short tons, US$M = U.S. dollars in millions

 

As shown in Table 19-2 excluding Inferred Resources reduces evaluated mill feed from 1,127 Mst to 971 Mst. Payable copper decreases from 1,748 Mlb to 1,509 Mlb, molybdenum from 906 Mlb to 819 Mlb, and silver from 58.75 Moz to 49.99 Moz. Net smelter revenue decreases from US$32,513 million to US$28,907 million, while operating expenditure decreases from US$16,247 million to US$14,830 million. Total capital remains unchanged.

 

Undiscounted cash flow totals US$13,734 million before tax and US$11,372 million after tax including Inferred, compared with US$11,545 million and US$9,591 million excluding Inferred. Both results indicate economic potential under the stated preliminary assumptions. Positive results do not establish Mineral Reserves or demonstrate economic viability at a PFS or FS level.

 

19.4Common Assumptions and Estimating Basis

 

Both cases retain the same metal prices, metallurgical recovery relationships for each material type, concentrate grades and payabilities, selling-charge basis, tax calculation methods and 8.00% discount rate. Weighted grades and overall recoveries reflect the retained material mix in each case. Prices and unit-cost assumptions remain constant. Capital expenditure totals US$2,521 million in each case, including US$1,169 million before production, US$658 million during expansion and US$693 million for sustaining and closure expenditure. Processing and material-handling costs respond to the retained quantities, and mining costs include the changes in waste handling. Working capital and taxes are calculated from each case’s own operating costs and cash flows.

 

233
 

 

19.4.1Pricing Assumptions

 

The common metal prices are US$5.00/lb copper, US$25.00/lb molybdenum and US$50.00/troy oz silver. Commodity-price assumptions, marketing terms and concentrate charges are addressed in the Market Studies chapter. The cash-flow analysis uses these sales prices and separate concentrate deductions. The mine-planning basis is presented in the Mining Methods chapter.

 

Table 19-3 Pricing Assumptions for Economic Analysis

 

Assumption Unit Value
Copper Price US$/payable lb Cu 5.00
Molybdenum Price US$/payable lb Mo 25.00
Silver Price US$/oz 50.00
Re Price US$/lb Re 2,250.00

 

Source: NLM (2026) Note. Cu = copper, lb = pound, Mo = molybdenum, Re = rhenium, US$ = U.S. dollar

 

19.4.2Metallurgical and Commercial Assumptions

 

Mill-feed grades and recoveries determine recovered copper, molybdenum, and silver. Payabilities of 96.5%, 99.0%, and 92.5%, respectively, then determine payable quantities. Concentrate grades are 28% Cu and 55% Mo; moisture is 8%. Copper treatment and refining, molybdenum roasting and freight charges are applied on the dry-concentrate, wet-concentrate or metal bases shown in Table 19-4.

 

The rhenium credit is treated as a commercial credit in molybdenum-concentrate sales. Historical support for rhenium recovery and marketing is described in SRK (2020), Sections19.1 and 22.7. The current economic model applies the adopted 25-ppm rhenium grade in dry molybdenum concentrate, 25% payable fraction and US$2,250/lb price presented in Table 19-3 and Table 19-4. The credit is calculated from dry molybdenum-concentrate tonnage and included in molybdenum net revenue. These current commercial assumptions are distinct from the numerical assumptions in the historical study.

 

Table 19-4 Concentrate Sales and Off-Site Cost Assumptions

 

Assumption Unit Value
Cu Concentrate Moisture % 8.00
Cu Concentrate Grade % 28.00
Cu Payable % 96.50
Cu Freight US$/wet st conc 115.00
Cu Treatment US$/dry st conc 40.00
Cu Refining US$/contained lb Cu 0.04
Mo Concentrate Moisture % 8.00
Mo Concentrate Grade % 55.00
Mo Payable % 99.00

 

234
 

 

Assumption Unit Value
Mo Freight US$/wet st conc 75.00
Mo Roasting/Refining US$/payable lb Mo 1.25
Re Grade in Mo Concentrate ppm Re 25.00
Re Payable % 25.00
Ag Payable % 92.50
Ag Refining/Other US$/payable oz Ag 0.50

 

Source: NLM (2026). Note. Concentrate grades are on a dry-mass basis. Moisture is used to calculate wet concentrate freight. Payabilities are applied to recovered metal. Ag = silver, Conc = concentrate, Cu = copper, Mo = molybdenum, oz = ounce, ppm = parts per million, Re = rhenium, st = short ton, US$ = U.S. dollar

 

19.4.3Capital and Estimating Basis

 

Total project capital is US$2,520.84 million, including 25.00% contingency. Preproduction capital is US$1,169 million, expansion capital is US$658 million and sustaining capital is US$693 million. Preproduction and expansion together total US$1,828 million.

 

The capital and operating estimates use the production schedule presented in this report and the discipline estimating bases described in Section 18, Capital and Operating Costs. The capital and operating cost estimates are preliminary, with an estimated accuracy of approximately ±50%, reflecting the current level of engineering definition. The accuracy range is not a statistical confidence interval. Capital contingency is 25% of direct capital.

 

The QP responsible for the Mining Methods chapter developed the mining estimate from scheduled material movements, route-dependent haulage, equipment requirements, operating hours and labor. Equipment purchase prices use InfoMine benchmarks dated 27 February 2024 with a 6% uplift. Plant, crushing and sorting capital, and annual crushing and milling costs use the processing estimates presented in this report. Sorting operating costs use the annual all-in amounts described in Section 18.2.2. Material-handling costs use the separate mining and rehandling estimates presented in this report. The process estimate was developed by the process QP based on the conceptual plant design discussed in Section 14 using similar InfoMine benchmarks for equipment and components and incorporated into this analysis. Infrastructure, environmental, closure and administration allowances are incorporated separately. Costs are expressed in 2026 US dollars and held constant through the forecast.

 

The principal estimating risks are preliminary facility definition, equipment and construction quantities, unit prices, haulage productivity, and long-term maintenance and equipment reuse. These affect both the scale and timing of expenditure. The adopted accuracy range and capital contingency reflect the preliminary assessment basis; the cost sensitivities in Section 19.5.7 show the effects of changes in the estimated expenditure.

 

Capital costs used in the evaluation are summarized in Table 19-5. The estimation basis and costs by discipline are presented in Chapter 18.

 

235
 

 

Table 19-5 Capital Cost Summary by Timing Group US$M

 

Category Preproduction Years - 3 to -1 Expansion Years - 1 to 4 Sustaining Year 5 onward

Total

US$M

Site Infrastructure 64 7 0 72
Mining 228 267 357 851
Processing 622 251 131 1,004
Environmental and Closure 0 0 60 60
General and Administrative 14 2 7 23
Owner’s Costs 7 0 0 7
Subtotal Capital 935 527 555 2,017
Contingency (25.00%) 234 132 139 504
Total Capital 1,169 658 693 2,521

 

Source: NLM (2026). Totals are calculated before rounding; displayed components may not sum to totals.

 

19.4.4Operating Cost Estimate Basis

 

Operating costs use the annual discipline estimates described in Section 18. Mining costs follow the scheduled mining and material-handling duties; processing costs include the separate material-handling duties and retained feed and adopted unit-cost basis. The approximately ±50% preliminary estimating accuracy assumption applies to these operating estimates. No separate project-wide operating-cost contingency is identified in this economic analysis. Allowances already included in discipline unit rates remain within those costs and are not assumed to be zero.

 

19.4.5Royalty Tax and Working Capital Assumptions

 

No royalty payments are included in the economic analysis.

 

The fiscal assumptions are 21.00% federal income tax, 5.30% Idaho income tax, and 2.00% alternative minimum tax (AMT), with subsequent credit. The analysis uses annual depreciation of 20.00%, tax-loss carryforwards and 15.00% percentage depletion subject to a 50.00% taxable-income limit. Idaho income tax is calculated after federal income tax.

 

Idaho Copper supplied the tax inputs and fiscal treatment described above. The basis for those inputs is described in Section 19.4.6, Fiscal Information Provided by the Registrant. The economic model applies those assumptions to the annual project cash flows.

 

Working capital is 20.00% of annual operating expenditure. Changes in the required balance are cash inflows or outflows, with the remaining balance released after processing ends. Reclamation and water treatment have direct capital allowances of US$30.00 million each, before contingency. Their payments extend through Year 55.

 

19.4.6Fiscal Information Provided by the Registrant

 

Idaho Copper, as the registrant, provided and reviewed the federal and Idaho income-tax assumptions, alternative minimum tax and related credits, depreciation, percentage depletion and tax-loss carryforwards and the royalty position applied in this IA. As described in Section 25.2, these inputs were communicated throughout the project and confirmed by Andrew Brodkey in his October 12, 2026, email, “CuMo Project Production Plan v83.2 TEM. Rev-06.” The tax parameters and royalty assumption used in the model are stated in Section 19.4.5. Proposed reliance covers the company-provided legal and governmental interpretations underlying these fiscal inputs, to the extent they are outside the responsible qualified person’s expertise.

 

236
 

 

These assumptions are applied consistently to both resource cases and form the basis for the after-tax annual cash flows in Table 19-7 and Table 19-16 and the after-tax NPV, IRR and payback results in Table 19-1. Table 19-10 presents taxes and credits for the case including Inferred Mineral Resources. The QP responsible for this chapter retains responsibility for the cash-flow calculations and interpretation of the results.

 

19.5Economic Analysis Including Inferred Mineral Resources

 

19.5.1Economic Results

 

At an 8.00% discount rate, the case including Inferred Mineral Resources has a pre-tax NPV of US$2,309 million and an after-tax NPV of US$1,878 million. Pre-tax IRR is 19.84% and after-tax IRR is 18.50%. Payback from production commencement is 5.83 years before tax and 5.86 years after tax. Table 19-1 compares these results with the case excluding Inferred. The preliminary nature of the assessment and the limitations of Mineral Resources described in Section 19.1 apply to these results.

 

19.5.2Annual Production

 

Table 19-6 presents annual recovered and payable metal production including Inferred Mineral Resources. Processing extends through Year 46. Recovered metal is distinct from payable product; Mlb and Moz denote million pounds and million troy ounces, respectively.

 

Table 19-6 Annual Recovered and Payable Metal Production Including Inferred Resources

 

Year Cu recovered (Mlb) Mo recovered (Mlb) Ag recovered (Moz) Cu payable (Mlb) Mo payable (Mlb) Ag payable (Moz)
1 24.8 9.7 0.91 23.9 9.6 0.84
2 35.5 15.4 1.15 34.3 15.3 1.07
3 31.9 23.9 0.99 30.8 23.6 0.91
4 45.2 31.8 1.40 43.7 31.5 1.29
5 57.2 29.9 2.22 55.2 29.6 2.05
6 44.6 35.3 1.49 43.1 35.0 1.38
7 50.4 39.0 1.60 48.7 38.6 1.48
8 31.8 48.2 0.96 30.7 47.7 0.89
9 49.9 23.1 1.88 48.1 22.9 1.74
10 45.0 41.4 1.70 43.5 41.0 1.57
11 42.8 40.7 1.83 41.3 40.3 1.69
12 51.3 32.9 1.61 49.5 32.6 1.49
13 76.5 27.8 2.30 73.8 27.5 2.13

 

237
 

 

Year Cu recovered (Mlb) Mo recovered (Mlb) Ag recovered (Moz) Cu payable (Mlb) Mo payable (Mlb) Ag payable (Moz)
14 38.8 29.1 1.29 37.5 28.8 1.19
15 26.2 25.4 1.11 25.3 25.1 1.03
16 20.6 38.7 0.83 19.9 38.3 0.77
17 25.6 44.0 0.81 24.7 43.6 0.75
18 40.4 13.8 1.25 39.0 13.6 1.15
19 75.6 29.5 2.47 73.0 29.2 2.28
20 46.8 34.6 1.67 45.2 34.2 1.54
21 44.7 33.8 1.42 43.2 33.4 1.31
22 33.3 28.3 1.18 32.1 28.0 1.09
23 29.7 16.0 1.14 28.6 15.9 1.06
24 22.5 15.1 0.81 21.7 15.0 0.75
25 41.5 8.8 1.28 40.0 8.8 1.18
26 27.7 9.7 0.90 26.8 9.6 0.83
27 25.1 6.5 1.17 24.2 6.4 1.08
28 13.2 5.9 1.19 12.7 5.9 1.10
29 26.0 8.9 1.11 25.1 8.8 1.02
30 49.7 6.8 1.85 48.0 6.8 1.71
31 32.5 12.4 1.19 31.4 12.3 1.10
32 29.4 13.3 1.10 28.3 13.1 1.02
33 33.2 12.0 1.12 32.0 11.9 1.04
34 41.0 7.3 1.41 39.6 7.2 1.30
35 36.3 9.2 1.28 35.1 9.1 1.18
36 28.7 12.3 1.04 27.7 12.2 0.97
37 46.3 9.2 1.64 44.7 9.1 1.51
38 38.4 9.6 1.34 37.0 9.5 1.24
39 39.0 10.3 1.35 37.7 10.2 1.25
40 42.5 10.3 1.46 41.0 10.2 1.35
41 49.4 10.7 1.55 47.6 10.6 1.43
42 40.7 12.0 1.33 39.3 11.9 1.23
43 49.1 9.2 1.55 47.4 9.1 1.44
44 45.1 8.5 1.47 43.6 8.4 1.36
45 38.5 7.1 1.47 37.1 7.0 1.36
46 46.4 7.5 1.73 44.7 7.4 1.60
Total 1,811 915 63.51 1,748 906 58.75

 

Source: NLM (2026). Note. Ag = silver, Cu = copper, Mlb = millions of pounds, Mo = molybdenum, Moz= million ounces

 

238
 

 

19.5.3Annual Cash Flows

 

Table 19-7 presents annual cash flows including Inferred Mineral Resources. The forecast covers development and prestripping in Years −3 to −1, production in Years 1 to 46, working-capital movements and closure and water-treatment payments through Year 55. Undiscounted cash flow totals US$13,734 million before tax and US$11,372 million after tax. Values are rounded for presentation; displayed annual values may not sum exactly to the reported life-of-project totals.

 

Table 19-7 Annual Project Cash Flow Including Inferred Resources

 

Year Net Revenue (US$M) OPEX (US$M) Holding (US$M) Capital (US$M) Working Capital (US$M) Pre-Tax Cash Flow (US$M) After-Tax Cash Flow (US$M)
-3 0 0 0.23 0 0 -0.23 -0.23
-2 0 0 0.23 443 0 -443 -443
-1 0 0 0.23 726 0 -726 -726
1 381 277 0.23 144 -55 -96 -96
2 574 398 0.23 226 -24 -74 -74
3 748 475 0.23 247 -15 11 11
4 1,014 526 0.23 42 -10 436 432
5 1,060 567 0.23 5 -8 479 472
6 1,097 591 0.23 0.65 -5 501 493
7 1,215 566 0.23 4 5 650 606
8 1,318 594 0.23 53 -6 666 538
9 852 592 0.23 0.04 0.24 259 228
10 1,252 605 0.23 56 -3 589 479
11 1,232 596 0.23 5 2 632 524
12 1,076 603 0.23 141 -1 331 265
13 1,101 600 0.23 79 0.63 423 352
14 916 570 0.23 108 6 244 210
15 764 596 0.23 9 -5 154 142
16 1,038 598 0.23 84 -0.41 355 305
17 1,185 609 0.23 0.90 -2 573 487
18 562 568 0.23 43 8 -41 -41
19 1,145 591 0.23 9 -5 540 465
20 1,098 440 0.23 4 30 683 566
21 1,058 403 0.23 0 7 662 540
22 867 364 0.23 0.20 8 510 419
23 561 206 0.23 0 32 387 320
24 493 204 0.23 0.89 0.31 288 234
25 452 190 0.23 0.75 3 264 215
26 392 189 0.23 0 0.24 204 167

 

239
 

 

Year Net Revenue (US$M) OPEX (US$M) Holding (US$M) Capital (US$M) Working Capital (US$M) Pre-Tax Cash Flow (US$M) After-Tax Cash Flow (US$M)
27 319 188 0.23 0 0.17 131 110
28 253 188 0.23 0 0 65 57
29 377 188 0.23 0.92 0 188 155
30 468 188 0.23 0 0 280 227
31 492 188 0.23 0 0 304 246
32 493 188 0.23 2 0 303 245
33 483 188 0.23 0 0.01 295 239
34 420 188 0.23 0 0 232 190
35 438 188 0.23 0.75 0 249 203
36 465 188 0.23 0.17 0 277 225
37 500 188 0.23 0 0.01 312 252
38 459 188 0.23 4 0.02 267 216
39 478 185 0.23 0 0.48 293 238
40 501 185 0.23 5 0.07 310 250
41 543 185 0.23 5 0.01 353 284
42 525 185 0.23 5 0 335 270
43 508 185 0.23 5 0 318 257
44 469 185 0.23 5 0 279 227
45 407 185 0.23 5 0.03 217 178
46 464 185 0.23 5 0 274 222
47 0 0 0 5 37 32 32
48 0 0 0 5 0 -5 -5
49 0 0 0 5 0 -5 -5
50 0 0 0 5 0 -5 -5
51 0 0 0 5 0 -5 -5
52 0 0 0 5 0 -5 -5
53 0 0 0 5 0 -5 -5
54 0 0 0 5 0 -5 -5
55 0 0 0 5 0 -5 -5
Total 32,513 16,247 11 2,521 0 13,734 11,372

 

Source: NLM (2026) Note. Costs are positive expenses. Working-capital movements and cash flows are signed inflows or outflows. Year −3 is the discounting origin. Closure and treatment capital payments continue through Year 55. US$M = U.S. dollars in millions

 

19.5.4Operating Sales and Tax Results

 

Gross metal revenue values recovered metal at the assumed sales prices. The deductions include the value of non-payable metal as well as freight, treatment, refining, and roasting. Gross recovered-metal revenue is US$35,132 million; deductions total US$2,620 million, giving net smelter revenue of US$32,513 million. The analysis includes a US $23.4 million rhenium credit in molybdenum revenue.

 

240
 

 

Life-of-mine operating costs total US$16,247 million, equivalent to US$14.42/st milled. Mining contributes US$4.82/st, processing US$9.21/st and site general and administrative costs US$0.36/st. Table 19-8 summarizes the totals by discipline; Table 19-7 presents the annual project cash flows.

 

Table 19-8 Operating Cost Summary Including Inferred Resources

 

Category Cost (US$M) US$/st Milled
Mining 5,428 4.82
Process 10,377 9.21
Environmental and Reclamation 42 0.04
G&A 401 0.36
Operating Costs 16,247 14.42

 

Source: NLM (2026) Note. G & A = General and Administrative, st = short ton, US$ = U.S. dollar, US$M = U.S. dollars in millions

 

Unit costs use the total mill feed of 1,127 Mst. The operating summary excludes capitalized prestripping, capital expenditure, property holding costs, concentrate selling charges, income taxes and working-capital movements; these items are included separately in Chapter 19.

 

Table 19-9 summarizes contained, recovered and payable metal for the case including Inferred. Table 19-10 presents the life-of-project taxes and credits calculated from this case’s annual cash flows.

 

Table 19-9 Contained Recovered and Payable Metal Including Inferred Resources

 

Metal Unit Contained in Mill Feed Recovered Mill Recovery (%) Payable
Copper Mlb 2,180 1,811 83.07 1,748
Molybdenum Mlb 1,016 915 90.04 906
Silver Moz 90 64 70.44 59

 

Source: NLM (2026) Note. Mill recovery is recovered metal divided by contained metal in mill feed. Mlb = millions of pounds, Moz = million ounces

 

Table 19-10 Life of Project Taxes and Credits Including Inferred Resources

 

Item Amount (US$M)
Federal Income Tax 1,969
AMT Payment 19
AMT Credit 19
Idaho Income Tax 393
Net Taxes 2,362

 

Source: NLM (2026) Note. AMT = alternative minimum tax, US$M = U.S. dollars in millions

 

19.5.5Cash Costs and All In Sustaining Costs

 

Cash cost (C1) and all-in sustaining cost (AISC) are reported on byproduct, coproduct and metal-equivalent bases because molybdenum contributes the largest share of project revenue. The measures use undiscounted life-of-mine costs and payable production. The costs for each calculation basis are summarized in Table 19-11.

 

241
 

 

C1 includes site operating costs, operating-period property holding costs and cash freight, treatment and refining charges. AISC also includes sustaining capital, production royalties and corporate overhead. The model assumes no production royalty or additional corporate overhead. Sustaining capital includes the scheduled reclamation and water-treatment expenditure. Initial and expansion capital, income taxes, financing and working capital are excluded from AISC.

 

The byproduct method deducts the other products’ net revenue from the primary metal’s costs. The co-product method allocates shared costs by each metal’s share of total net product revenue and adds directly attributable cash selling charges. Molybdenum contributes 65.97% of net product revenue and copper contributes 25.01%; silver and rhenium account for the remainder. The negative copper byproduct cost reflects the molybdenum credit.

 

Metal-equivalent production is calculated from the gross value of payable copper, molybdenum, silver and rhenium at the prices in the Market Studies chapter, divided by the reference-metal price. The copper-equivalent (CuEq) C1 cash cost is US$2.63/lb and AISC is US$2.73/lb. Equivalent output is a financial production measure and does not represent a resource grade or metallurgical recovery.

 

Table 19-11 Life of Mine Cash Costs and All-In Sustaining Costs Including Inferred Resources

 

Method

Cu C1

 

US$/Payable lb

Cu AISC

 

US$/Payable lb

Mo C1

 

US$/Payable lb

Mo AISC

 

US$/Payable lb

Byproduct -4.30 -3.91 7.06 7.82
Coproduct 2.67 2.77 13.16 13.67
Metal Equivalent 2.63 2.73 13.17 13.67

 

Source: NLM (2026) Note. For the metal-equivalent row, units are US$/payable lb copper equivalent (CuEq) and US$/payable lb molybdenum equivalent (MoEq). All amounts are undiscounted LOM ratios. These measures are not a substitute for project cash flow. AISC = all-in sustaining costs, C1 = cash costs, Cu = copper, lb = pound, Mo = molybdenum, US$ = U.S. dollar

 

19.5.6Capital Intensity

 

Capital intensity is capital divided by average annual payable production during Years 1 to 46. Average payable output is 17.2 ktpy of copper and 67.7 ktpy of copper equivalent, where kt denotes 1,000 metric tonnes. Preproduction and expansion capital of US$1,828 million gives an intensity of US$26,979 per annual payable copper-equivalent tonne. This denominator represents average scheduled production rather than nameplate capacity. The capital intensity is summarized in Table 19-12.

 

Table 19-12 Capital Intensity Based on Average Scheduled Payable Production Including Inferred Resources

 

Capital Scope Capital US$M

US$/Annual Payable

 

Cu Tonne

US$/Annual Payable

 

CuEq Tonne

Preproduction 1,169 67,857 17,262
Preproduction and Expansion 1,828 106,057 26,979
Life-of-Mine 2,521 146,287 37,213

 

Source: NLM (2026) Note. Cu = copper, CuEq = copper equivalent, US$ - U.S. dollar

 

242
 

 

19.5.7Sensitivity Analysis

 

Sensitivity analysis varies one economic assumption at a time while holding the mine plan and production schedule fixed. Results are pre-tax and relate to the case including Inferred Mineral Resources. Table 19-13 compares changes of ±10%, and Figure 19-1 and Figure 19-2 show NPV and IRR responses over ±25%. A 10% reduction in molybdenum price lowers NPV at 8.0% to US$1,633 million; a 10% increase in operating cost lowers it to US$1,815 million. Capital sensitivity scales project capital expenditure. The combined metal-price sensitivity changes copper, molybdenum, and silver prices together; rhenium price remains constant.

 

A comparison of pre-tax NPV with varying the discount rate between 0.0% and 15.0% is summarized in Table 19-14 and shown in Figure 19-3.

 

Table 19-13 One Variable Sensitivity with the Mine Plan Fixed Including Inferred Resources

 

Variable −10% NPV8 US$M Base NPV8 US$M +10% NPV8 US$M −10% IRR % +10% IRR %
Combined Metal Prices 1,363 2,308 3,253 15.22 24.15
Copper Price 2,106 2,308 2,511 18.89 20.79
Molybdenum Price 1,633 2,308 2,983 16.55 22.95
Silver Price 2,241 2,308 2,375 19.53 20.15
Mill Recovery 1,413 2,308 3,203 15.47 23.93
Capital Costs 2,479 2,308 2,138 21.73 18.22
Operating Costs 2,802 2,308 1,815 22.29 17.34

 

Source: NLM (2026). Note. Recovery changes are relative multipliers applied to the three recovered-metal quantities. These financial sensitivity tests do not define achievable metallurgical recovery limits. The upper multipliers can imply recovery above 100%; achievable domain recovery ranges require metallurgical testwork. IRR = internal rate of return, NPV8 = net present value at an 8% discount rate, US$M = U.S. dollars in millions

 

As shown in Table 19-1 there is an impact of a nearly US$500 million reduction to the base case pre-tax NPV and an approximately US$1,454 million reduction in process operating (Table 19-2) cost when Inferred Mineral Resources are removed. The summary in this section presents the impact to the base case when evaluating single variable sensitivity. The trends shown and discussed in this section would be similar for the case of where Inferred Mineral Resources are removed.

 

The sensitivity results apply to the production schedule used in the initial assessment. Changes in grade, sorting performance, throughput or stockpile-treatment timing would change production as well as cash flow and require a revised mine and processing plan.

 

243
 

 

 

Source: NLM (2026)

 

Figure 19-1 Pre-Tax NPV Sensitivity at an 8 Percent Discount Rate Including Inferred Resources

 

244
 

 

 

Source: NLM (2026)

 

Figure 19-2 Pre-Tax IRR Sensitivity Including Inferred Resources

 

Table 19-14 Pre-Tax NPV Sensitivity to Discount Rate Including Inferred Resources

 

Discount rate (%) NPV (US$M)
0 13,734
5 4,261
8 2,308
10 1,542
12 1,012
15 483

 

Source: NLM (2026). Note. NPV = net present value, US$M = U.S. dollars in millions

 

245
 

 

 

Source: NLM (2026)

 

Figure 19-3 Pre-Tax NPV Sensitivity to Discount Rate Including Inferred Resources

 

19.6Economic Analysis Excluding Inferred Mineral Resources

 

19.6.1Economic Results

 

At an 8.00% discount rate, the case excluding Inferred Mineral Resources has a pre-tax NPV of US$1,823.26 million and an after-tax NPV of US$1,482.42 million. Pre-tax IRR is 18.26% and after-tax IRR is 17.04%. Payback from production commencement is 5.92 years before tax and 5.96 years after tax. Table 19-1 compares these results with the case including Inferred. The preliminary nature of the assessment and the limitations of Mineral Resources described in Section 19.1 apply to these results.

 

19.6.2Resource Treatment and Routing Basis

 

The excluding-Inferred case retains the original pit excavation quantities and annual mining sequence. Inferred material previously assigned to processing is treated as waste. Its crushing, sorting, mill feed, recovered metal and associated cash flows are excluded. The retained M&I material follows the original routing and calendar, including stockpile placement and reclaim. Unused processing capacity is not refilled by resequencing the mine plan. This is a comparison within the existing mining plan, rather than an independently optimized M&I-only pit and schedule.

 

The excluding-Inferred case also includes the construction-rock routing variation that exchanges 3.85 Mst between the waste-dump and tailings-construction destinations in Years 18 and 20. The affected haulage costs are included in that case. The exchange changes the destinations and timing of those deliveries without changing total pit excavation. The two-case comparison therefore reflects both Inferred-resource exclusion and this stated routing adjustment.

 

246
 

 

19.6.3Annual Production

 

Table 19-15 presents annual mill feed and recovered and payable metal production excluding Inferred Mineral Resources, including the classification exclusions in stockpile reclaim. The annual forecasts preserve the same development, mining, processing and closure calendar as the including-Inferred case. Processing extends through Year 46.

 

Table 19-15 Annual Mill Feed and Metal Production Excluding Inferred Resources

 

Year Mill Feed Mst Cu Recovered Mlb Mo Recovered Mlb Ag Recovered Moz Cu Payable Mlb Mo Payable Mlb Ag Payable Moz
1 9.0 24.8 9.7 0.91 23.9 9.6 0.84
2 12.7 35.5 15.4 1.15 34.2 15.2 1.06
3 12.6 31.1 23.8 0.96 30.0 23.5 0.89
4 18.8 44.2 31.4 1.36 42.6 31.0 1.26
5 25.3 55.9 29.8 2.17 53.9 29.5 2.01
6 24.4 40.2 34.4 1.37 38.8 34.0 1.27
7 25.5 50.3 38.9 1.60 48.5 38.6 1.48
8 25.1 30.9 47.8 0.92 29.8 47.3 0.86
9 22.6 39.3 20.5 1.56 37.9 20.3 1.44
10 24.1 41.7 38.6 1.60 40.3 38.2 1.48
11 14.5 19.9 25.9 1.07 19.2 25.6 0.99
12 16.0 26.1 23.4 0.88 25.2 23.2 0.81
13 24.6 74.8 26.3 2.26 72.2 26.1 2.09
14 22.4 35.4 26.5 1.08 34.1 26.2 1.00
15 16.8 15.6 20.8 0.55 15.0 20.6 0.51
16 21.6 17.0 36.0 0.64 16.4 35.6 0.60
17 25.5 25.3 43.9 0.80 24.4 43.5 0.74
18 23.5 27.9 12.1 0.86 26.9 12.0 0.80
19 23.1 68.6 27.7 2.22 66.2 27.4 2.06
20 24.2 44.5 32.8 1.57 43.0 32.4 1.45
21 24.1 42.5 31.1 1.35 41.0 30.8 1.25
22 20.8 27.4 23.1 0.98 26.4 22.9 0.91
23 21.4 26.1 12.9 1.00 25.1 12.8 0.93
24 24.6 21.4 14.7 0.75 20.6 14.6 0.70
25 23.9 38.0 8.3 1.17 36.7 8.2 1.08
26 24.1 26.6 8.9 0.86 25.7 8.8 0.80

 

247
 

 

Year Mill Feed Mst Cu Recovered Mlb Mo Recovered Mlb Ag Recovered Moz Cu Payable Mlb Mo Payable Mlb Ag Payable Moz
27 14.0 15.6 3.6 0.59 15.1 3.6 0.55
28 4.2 1.0 1.4 0.25 1.0 1.4 0.23
29 18.2 22.7 7.1 0.84 21.9 7.1 0.77
30 24.9 47.9 6.6 1.80 46.2 6.6 1.66
31 14.7 15.1 7.6 0.63 14.6 7.5 0.58
32 14.8 11.3 8.8 0.49 10.9 8.7 0.45
33 21.3 26.5 10.3 0.92 25.6 10.2 0.85
34 16.9 23.3 4.9 0.78 22.5 4.9 0.72
35 20.1 25.2 8.0 0.90 24.3 7.9 0.83
36 21.8 24.8 11.4 0.87 23.9 11.2 0.81
37 25.5 46.2 9.2 1.63 44.6 9.1 1.51
38 24.4 35.2 9.4 1.24 34.0 9.3 1.15
39 23.7 34.0 9.9 1.18 32.8 9.8 1.09
40 24.0 39.2 10.2 1.34 37.8 10.1 1.24
41 24.8 47.9 10.4 1.51 46.2 10.3 1.39
42 25.5 40.6 12.0 1.33 39.2 11.9 1.23
43 24.5 46.5 9.0 1.47 44.9 8.9 1.36
44 25.6 45.1 8.5 1.47 43.6 8.4 1.36
45 25.0 38.2 7.0 1.45 36.9 6.9 1.34
46 25.5 46.3 7.5 1.73 44.6 7.4 1.60
Total 971 1,564 827 54.04 1,509 819 49.99

 

Source: NLM (2026) Note. Recovered metal is distinct from payable product. Classification exclusions include material reclaimed from stockpiles. Ag = silver, Cu = copper, Mlb – millions of pounds, Mo = molybdenum, Mst = million short tons

 

19.6.4Annual Cash Flows

 

Table 19-16 presents annual cash flows excluding Inferred Mineral Resources. The forecast covers development and prestripping in Years −3 to −1, production in Years 1 to 46, working-capital movements and closure and water-treatment payments through Year 55. The remaining working-capital balance is released in Year 47. Undiscounted cash flow totals US$11,545 million before tax and US$9,591 million after tax. Values are rounded for presentation; displayed annual values may not sum exactly to the reported life-of-project totals.

 

Table 19-16 Annual Project Cash Flow Excluding Inferred Resources

 

Year Net Revenue US$M OPEX US$M Holding US$M Capital US$M Working Capital US$M Pre-tax Cash Flow US$M After-tax Cash Flow US$M
-3 0.0 0.0 0.2 0.0 0.0 -0.2 -0.2
-2 0.0 0.0 0.2 443.2 0.0 -443.4 -443.4

 

248
 

 

Year Net Revenue US$M OPEX US$M Holding US$M Capital US$M Working Capital US$M Pre-tax Cash Flow US$M After-tax Cash Flow US$M
-1 0.0 0.0 0.2 726.1 0.0 -726.3 -726.3
1 380.3 276.9 0.2 143.6 -55.4 -95.8 -95.8
2 572.0 396.9 0.2 225.5 -24.0 -74.7 -74.7
3 741.6 471.1 0.2 247.4 -14.8 8.1 8.1
4 996.6 521.7 0.2 41.8 -10.1 422.8 418.9
5 1,049.3 560.7 0.2 5.3 -7.8 475.2 468.1
6 1,049.8 574.0 0.2 0.7 -2.7 472.2 464.8
7 1,212.7 565.1 0.2 4.1 1.8 645.1 609.6
8 1,303.1 580.6 0.2 52.8 -3.1 666.3 538.9
9 729.7 539.1 0.2 0.0 8.3 198.6 176.2
10 1,166.4 582.9 0.2 56.0 -8.8 518.5 421.4
11 745.2 484.7 0.2 5.3 19.6 274.7 243.2
12 706.5 508.4 0.2 141.2 -4.8 51.8 33.4
13 1,056.9 589.9 0.2 78.8 -16.3 371.7 308.2
14 830.1 493.2 0.2 108.4 19.3 247.6 213.8
15 582.1 469.6 0.2 8.8 4.7 108.1 102.6
16 950.7 564.1 0.2 83.9 -18.9 283.6 243.4
17 1,180.8 607.4 0.2 0.9 -8.7 563.7 478.1
18 447.9 497.3 0.2 42.8 22.0 -70.4 -70.4
19 1,058.8 568.1 0.2 9.1 -14.2 467.2 415.8
20 1,040.9 429.8 0.2 4.3 27.7 634.2 526.8
21 982.1 384.8 0.2 0.0 9.0 606.1 495.7
22 710.8 322.4 0.2 0.2 12.5 400.5 332.4
23 465.8 171.6 0.2 0.0 30.2 324.1 268.4
24 475.6 194.5 0.2 0.9 -4.6 275.4 222.9
25 417.9 178.6 0.2 0.8 3.2 241.5 197.2
26 368.3 178.9 0.2 0.0 -0.1 189.1 155.4
27 181.4 110.3 0.2 0.0 13.7 84.6 73.7
28 48.5 44.4 0.2 0.0 13.2 17.0 16.6
29 308.0 138.4 0.2 0.9 -18.8 149.6 118.7
30 453.3 183.1 0.2 0.0 -8.9 261.0 210.2
31 275.2 114.7 0.2 0.0 13.7 173.9 144.0
32 279.9 115.6 0.2 2.5 -0.2 161.4 130.8
33 403.4 159.0 0.2 0.0 -8.7 235.4 189.3
34 255.8 130.0 0.2 0.0 5.8 131.3 109.5
35 342.5 151.4 0.2 0.8 -4.3 185.9 150.9
36 417.6 162.9 0.2 0.2 -2.3 252.0 203.8

 

249
 

 

Year Net Revenue US$M OPEX US$M Holding US$M Capital US$M Working Capital US$M Pre-tax Cash Flow US$M After-tax Cash Flow US$M
37 498.3 187.3 0.2 0.0 -4.9 305.8 246.5
38 434.9 179.8 0.2 4.4 1.5 252.1 204.5
39 438.3 172.7 0.2 0.0 1.4 266.8 216.8
40 476.5 174.8 0.2 5.2 -0.4 295.8 238.4
41 527.0 180.0 0.2 5.0 -1.1 340.6 274.0
42 524.2 184.6 0.2 5.0 -0.9 333.4 268.8
43 487.4 178.0 0.2 5.2 1.3 305.3 246.9
44 469.1 184.7 0.2 5.0 -1.3 277.8 225.2
45 401.1 181.1 0.2 5.0 0.7 215.6 176.6
46 462.9 184.3 0.2 5.0 -0.7 272.7 221.3
47 0.0 0.0 0.0 5.0 36.9 31.9 31.9
48 0.0 0.0 0.0 5.0 0.0 -5.0 -5.0
49 0.0 0.0 0.0 5.0 0.0 -5.0 -5.0
50 0.0 0.0 0.0 5.0 0.0 -5.0 -5.0
51 0.0 0.0 0.0 5.0 0.0 -5.0 -5.0
52 0.0 0.0 0.0 5.0 0.0 -5.0 -5.0
53 0.0 0.0 0.0 5.0 0.0 -5.0 -5.0
54 0.0 0.0 0.0 5.0 0.0 -5.0 -5.0
55 0.0 0.0 0.0 5.0 0.0 -5.0 -5.0
Total 28,907 14,830 11 2,521 0 11,545 9,591

 

Source: NLM (2026) Note. Costs are positive expenses; working-capital movements and cash flows are signed inflows or outflows. Year −3 is the discounting origin. Closure and water-treatment capital payments continue through Year 55. US$M = U.S. dollars in millions

 

250
 

 

20 Adjacent Properties

 

At present, there are no adjacent active mines applicable to the CuMo project for disclosure purposes in this report. However, there are known historical mines in the area and within the Boise Basin. These historical occurrences provide regional geological context and are not necessarily indicative of mineralization or Mineral Resources at the CuMo project.

 

The historical mine properties near CuMo that have documented copper, molybdenum, and silver are compiled in Table 20-1 (IGS, 2026). The locations are shown on Figure 20-1 for copper and molybdenum and on Figure 20-2 for silver. The historical mines were undoubtedly on a smaller scale than the CuMo project. However, they indicate the presence of similar mineralization and geological conditions through the Boise Basin.

 

The information compiled in Table 20-1 and shown on Figure 20-1 and on Figure 20-2 were obtained from the Idaho Geological Survey (IGS) mines and prospects database as presented and downloaded from the web-based, interactive map on June 17, 2026.

 

251
 

 

Table 20-1 Summary of Adjacent Known Mining Properties [1]

 

IGS Property ID Property Name Commodities Land Ownership

Latitude[1]

(°)

Longitude[1]

(°)

CH0541 Gray Eagle Mine Gold, lead, silver, zinc USFS;IDL-Southwest 44.04233588 -115.7964047
CH0543 Grimes-Payette Mine Copper, lead, zinc USFS;Boise NF 44.03953573 -115.8205053
CH0544 Homestake Group Gold, silver, copper, lead, zinc PRIVATE;IDL-Southwest 44.03667584 -115.8082249
CH0545 Coon Dog Mine Gold, silver, lead, copper, zinc PRIVATE;IDL-Southwest 44.03735585 -115.8063649
CH0546 Morning Star Crossing Gold, silver USFS;IDL-Southwest 44.03173588 -115.8091049
CH0547 Independence Group Gold, silver, lead, zinc USFS;IDL-Southwest 44.03770581 -115.811795
CH0548 Silver Gem Gold, silver, copper, lead, zinc USFS;Boise NF 44.03403569 -115.8325056
CH0549 Slide Gulch Gold, silver USFS;Boise NF 44.02923569 -115.8380056
CH0550 Parker Gold, silver USFS;Boise NF 44.03123566 -115.8402057
CH0552 Ballinger Vein Silver, gold, zinc, copper USFS;Boise NF 44.0265357 -115.8402057
CH0553 Bruser Mine Silver, gold, lead, zinc, copper USFS;IDL-Southwest 44.02099577 -115.8375455
CH0555 Idaho Gold, silver, lead, zinc USFS;IDL-Southwest 44.01793573 -115.8469057
CH0556 Noble Placer Silver, gold USFS;IDL-Southwest 44.02084576 -115.8392456
CH0557 Grimes Pass Mine Copper, silver, lead PRIVATE;IDL-Southwest 44.01653584 -115.8327053
CH0558 Mountain Queen Gold, silver, lead, copper, zinc PRIVATE;IDL-Southwest 44.0109758 -115.8452456
CH0559 Oro Mine Gold, silver, copper, lead, zinc USFS;IDL-Southwest 44.00996584 -115.8411155
CH0560 J.S. Prospects Silver, gold, lead, copper PRIVATE;IDL-Southwest 44.01039577 -115.8496957
CH0562 Missouri Mine Gold, silver, copper, zinc, lead USFS;IDL-Southwest 44.00664578 -115.8524557
CH0563 Golden Age Mine Silver, gold, copper, lead, zinc PRIVATE;IDL-Southwest 44.02095581 -115.8310353
CH0564 Mohawk Mine Silver, gold, lead, copper, zinc USFS;IDL-Southwest 44.02419595 -115.8084248
CH0565 Windfall Group Gold, silver, lead PRIVATE;IDL-Southwest 44.01979596 -115.8116248
CH0566 Blackbird No. 5 Tunnel Gold, lead, copper, zinc, silver USFS;IDL-Southwest 44.01905591 -115.820225
CH0568 Ader Group Gold, silver, copper, zinc, lead USFS;IDL-Southwest 44.014236 -115.8122047
CH0569 Voltaire Gold, silver, zinc USFS;IDL-Southwest 44.01423604 -115.8069046
CH0570 Smuggler Mine Gold, silver, lead, copper, zinc PRIVATE;IDL-Southwest 44.01733587 -115.8274752

 

252
 

 

IGS Property ID Property Name Commodities Land Ownership

Latitude[1]

(°)

Longitude[1]

(°)

CH0571 Enterprise Group Mine Silver, gold, copper, zinc, lead USFS;IDL-Southwest 44.01932599 -115.8085147
CH0572 Overlook Mine Silver, gold, zinc, lead, copper USFS;IDL-Southwest 44.01873612 -115.7908042
CH0574 Comeback Mine Gold, silver, lead, zinc, copper PRIVATE;IDL-Southwest 44.00356604 -115.8203648
CH0576 Red Rose Silver, gold PRIVATE;IDL-Southwest 44.00123617 -115.8039043
CH0704 Sunnyside Placer Silver, gold BOR;Boise NF 44.05983492 -115.9111081
CH0705 Horse Shoe Placer Silver, gold BOR;Boise NF 44.05123504 -115.9041078
CH0714 Grandview Prospects Silver, gold, lead USFS;Boise NF 44.00464545 -115.9014471
CH0717 Abella Molybdenum HSTRCWTR;Boise NF 44.06873559 -115.8058053
CH0718 K.C. Mine Silver, gold, copper, zinc, lead, antimony USFS;Boise NF 44.05747571 -115.801765
CH0723 Little Fall Creek Molybdenum USFS;Boise NF 44.059836 -115.7583039
CH0727 Black Jack Prospect Silver, gold, zinc, lead, copper USFS;IDL-Southwest 44.02423627 -115.7622035
CH0730 Viking Silver, gold USFS;IDL-Southwest 44.01673636 -115.7580033
CH0731 Mammoth Mine Silver, gold, zinc, lead PRIVATE;IDL-Southwest 44.0032868 -115.7125818
CH1355 Payette River Molybdenum Molybdenum BOR;Boise NF 44.07433 -115.760922
HA0397 Applejack Placer Silver, gold USFS;IDL-Southwest 43.9943353 -115.8620456
HA0400 Almond Placer Silver, gold, black sand, monazite, titanium, rare-earths, zirconium PRIVATE;IDL-Southwest 43.99107872 -115.8366974
HA0402 Curry Ditch Placer Silver, gold, black sand, titanium, monazite, rare-earths, zirconium PRIVATE;IDL-Southwest 43.98269545 -115.8391258
HA0403 Poncia Placers Gold, silver, black sand, rare-earths, titanium, zirconium USFS;IDL-Southwest 43.9880754 -115.8587957
HA0404 Fountain Spring Gold, silver USFS;IDL-Southwest 43.99053537 -115.8656456
HA0423 Mineral Hill Mine Silver, gold, bismuth PRIVATE;Boise NF 43.98554413 -115.9112732
HA0424 Big Six Gold, silver USFS;Boise NF 43.98603553 -115.9148453
HA0425 Buckskin Mine Silver, lead, gold, zinc, copper, bismuth USFS;IDL-Southwest 43.97975768 -115.8867616
HA0507 King Mine Gold, silver, lead, copper, zinc USFS;IDL-Southwest 43.98819702 -115.6983012

 

Source: Idaho Geological Survey (n.d.). Note. [1] Latitude and Longitude based on WGS 84. BOR = Bureau of Reclamation; ID = identification; IDL = Idaho Department of Lands; HSTRCWTR = Idaho Historical Waters; IGS = Idaho Geological Survey; NF = National Forest; USFS = United States Forest Service

 

253
 

 

 

Source: Source: Idaho Geological Survey (n.d.)

 

Figure 20-1 Copper and Molybdenum Locations Near CuMo Property

 

254
 

 

 

Source: Idaho Geological Survey (n.d.)

 

Figure 20-2 Silver Locations Near CuMo Property

 

255
 

 

21 Other Relevant Data and Information

 

The author did not identify additional relevant data or information during this review of the CuMo project.

 

256
 

 

22 Interpretation and Conclusions

 

22.1Conclusions

 

22.1.1Mineral Resource

 

Based on the QP’s review of the available data and review of the previously developed geological model and information, the CuMo project hosts a measured mineral resource, at a $5.00/t RCV cut-off of 0.3 billion tons at grades of 0.081% MoS2, 0.076% Cu, 2.09 ppm Ag, and 0.030 ppm Re.

 

The CuMo project also hosts an indicated mineral resource, at a $5.00/t RCV cut-off of 1.97 billion tons at grades of 0.053% MoS2, 0.085% Cu, 2.57 ppm Ag, and 0.019 ppm Re.

 

There is a further inferred resource of 2.56 billion tons at grades of 0.048% MoS2, 0.067% Cu, 2.13 ppm Ag, 0.017 ppm Re.

 

22.1.2Mining

 

The IA evaluates an owner-operated open pit mine using electric cable shovels and 360-short-ton diesel-electric haul trucks. The pit is developed through six main phases, with shovel and belt sorting directing material to the mill, middlings storage or waste facilities. Pit mining continues through Year 22, while processing of stockpiled material extends through Year 46.

 

The mine plan provides a basis for further evaluation through a PFS. Its performance depends on achievable mining selectivity and sorting response, suitable pit slopes and water-management measures, timely delivery of construction rock, and reliable long-term stockpile reclaim. These matters should be addressed through the investigations and engineering recommended in Section 23.3. The scheduled material comprises Mineral Resources and does not constitute Mineral Reserves.

 

22.1.3Bulk and Particle Sorting

 

Previous studies, and ongoing evaluations by Idaho Copper have advanced the approach and application of bulk sorting technology. There is heterogeneity within the ore body, which will require a sorting sequence involving up to three stages. The approach is incorporated into the optimized pit shell development and mine production schedule, using scanning technology to distinguish three separate material streams: primary mill feed, middlings to stockpile, and rejects—which will be directed as waste material. The potential application of penetrative sensing and sorting technologies (e.g., MRI, PGNAA, PFTNA) may provide sorting optimization, enhance rejection rates, and reduce overall OPEX.

 

22.1.4Mineral Processing

 

The processing facility is designed with conventional grinding, flotation, and dewatering equipment at equipment sizes that are typically available from equipment suppliers. The flotation flow sheet is based on the locked cycle laboratory test work and typical of many copper-molybdenum flotation processing plants. HPGR comminution and coarse particle flotation testing carried out during the PFS could enhance recoveries and reduce costs. New equipment designs may be applied to the processing facility after studies and test work are completed during the PFS.

 

257
 

 

22.1.5Project Economics

 

At an 8% discount rate, the Base Case including Measured, Indicated and Inferred Mineral Resources has an after-tax NPV of US$1,878 million and an after-tax IRR of 18.50%. The M&I Case, excluding Inferred Mineral Resources from processing and revenue, has an after-tax NPV of US$1,482 million and an after-tax IRR of 17.04%. These results indicate economic potential under the preliminary assumptions and support further technical and economic evaluation. Mineral Resources do not have demonstrated economic viability, and neither case establishes Mineral Reserves.

 

This initial assessment is preliminary. The Inferred Mineral Resources included in the Base Case are too geologically speculative to have modifying factors applied to them that would enable reserve classification, and there is no certainty that the projected results will be realized.

 

22.2Project Risks

 

22.2.1Mineral Resource

 

The CuMo deposit is a large, zoned porphyry-style system, and the current Mineral Resource estimate is based on the available drill-hole database and geological interpretation. Additional drilling, particularly in areas of wider drill spacing or near the limits of the modelled mineralized zones, may result in changes to the interpretation of mineralized domains, grade distribution, and resource classification. Infill drilling is recommended to support conversion of Inferred Mineral Resources to higher-confidence categories, while step-out drilling may identify extensions to known mineralization or modify the interpreted limits of the deposit.

 

There is risk that future geotechnical, geometallurgical, density, structural, or metallurgical data could affect the Mineral Resource estimate or the classification of material considered to have reasonable prospects for eventual economic extraction. Changes in metal prices, operating cost assumptions, metallurgical recoveries, processing assumptions, or cut-off criteria could also affect the tons and grades reported as Mineral Resources.

 

These risks are considered typical for a project at the IA stage and can be reduced through additional drilling, data validation, geological modeling, density determinations, metallurgical test work, and updated resource estimation during future study phases.

 

22.2.2Mining

 

22.2.2.1Mining Selectivity and Sorting Response

 

Shovel sorting depends on grade discrimination at the scale of individual excavation parcels. The 50-ft resource blocks are larger than the nominal 94-short-ton (85-metric-tonne) sorting parcel. Fragmentation, blast movement, digging and mixing could reduce separation performance. A smaller resource block size closer to the selective mining unit (SMU), the parcel that can be separately excavated and directed to processing or waste, should be considered in future studies. Change-of-support work, which relates grades estimated at the resource-block scale to grades at the SMU scale, is required to determine an appropriate smaller block size and the grade variability supported by the data. Given the large blocks relative to the SMU, the current mine plan assumes dilution and loss are incorporated in the model block grades and applies no additional mining dilution or separate mining-loss deduction.

 

258
 

 

A 0.8 sorting-response factor has been included in this study to allow for imperfect mining selectivity. It reduces modeled grade discrimination relative to the sampled variability when estimating the mass and metal reporting to each sorting product. Mass yield is the fraction of feed mass retained in a product; metal retention is the fraction of contained metal retained. Both depend on material type, sensor performance and physical sorter settings, and each upstream separation changes the feed presented to the next stage. Representative shovel and belt trials are required to establish achievable selectivity, sorting losses, throughput and loading productivity.

 

22.2.2.2Pit Slopes and Water Management

 

The preliminary slope assessment has limited spatial and depth coverage and did not include groundwater-pressure effects. Different wall conditions or water pressures could change phase geometry, stripping and access, while greater inflows could increase pumping requirements and disrupt working areas. Geotechnical and hydrogeological investigations should establish sector criteria, dewatering and depressurization requirements and their effects on the mine sequence.

 

22.2.2.3Construction Rock and Placement Facilities

 

The mine must supply suitable rock at the time required for staged tailings embankment construction. Physical and geochemical suitability has to be demonstrated and linked to the rock available by phase and period. Changes in suitable rock supply could require different routing, additional handling or a revised construction sequence.

 

22.2.2.4Long-Term Middlings Storage and Reclaim

 

Middlings storage begins in Year 1, reclaim starts in Year 9 and continues through Year 46, and inventory peaks at approximately 617 Mst in Year 21. The study assumes no storage-related reduction in metallurgical recovery. Aging, oxidation, degradation and changing moisture or handling conditions may affect recovery, reclaim productivity and costs. Tests on stored material should establish acceptable stockpile quantities and storage durations. The placement and reclaim plan should address drainage, blending, access, and equipment renewal over the full reclaim period.

 

22.2.2.5Workforce and Fuel Costs

 

Recruiting and retaining experienced operators, maintenance personnel and technical staff is an operating risk for the remote site. Workforce availability, transport and shift arrangements may affect costs and productivity. Diesel prices are also uncertain over the operating life and materially affect truck haulage and support-equipment costs. The next estimate should develop the staffing and transport plan, obtain current labor and fuel inputs and test their effects on fleet productivity and project economics.

 

22.2.3Mineral Sorting

 

The XRF technology envisioned in this IA for bulk sorting, has application to molybdenum-copper deposits. While demonstrated for some low-grade copper-molybdenum deposits, further testing is required to verify that molybdenum is measurable at the specific grades envisioned for CuMo.

 

Additional testing is required to obtain the final results expected from both bulk and particle sorting.

 

259
 

 

22.2.4Processing

 

Metallurgical test results are based on composite samples of the three primary ore types. Variability sample testing and testing of blended ore types may yield different results. Ore hardness testing is limited due to the scope of a IA and subsequent testing may identify harder ore material. Dewatering testing of the tailings and concentrates has not been performed to date and design parameters are based on industry standards. Additional metallurgical testing is recommended for the PFS.

 

The current processing plan will develop a large middlings stockpile which will be processed years after the ore is crushed and stockpiled. Sulfide mineral surface oxidation may reduce flotation recoveries on the stockpiled material.

 

22.2.5Project Infrastructure

 

The planned mine will be a greenfield site and requires construction of mine and process related infrastructure, including the TSF which the embankment serves as a primary WRF. Access roads in and around the project site will be required. Upgrades to existing gravel roads will likely be required; however, some extents along the alignment may be found to require significant upgrades due to local landslides or avalanche chutes.

 

Several water supply sources have been identified at this stage: purchasing or leasing water in the Boise Basin, an appropriation from the Payette River which could be traded for a Boise Basin right, subsurface aquifers, and excess water from an adjacent drainage basin. All potential sources would be subject to water rights allocations and regulatory assessments.

 

There is a risk that the designs, costs and implementation timelines for the provision of this infrastructure may not be as anticipated, increasing costs and schedule.

 

22.2.6Permitting

 

At this time, no issues have been identified that would materially affect the potential to extract Mineral Resources from the CuMo project. However, the mining plan of operations may identify and characterize issues that could extend the permitting timeline or increase permitting-related costs. The IA described in this report does not quantify the schedule or costs associated with preconstruction and permitting activities.

 

Previous environmental analyses have identified the presence of the plant Sacajawea’s bitterroot, a plant listed (but not threatened or endangered) under the Endangered Species Act, and potential habitat for Endangered Species Act wildlife, and USFS sensitive species. These potential issues are known, and Idaho Copper is aware as these issues have been considered and cleared for past and the current phase of planned exploration drill programs. Environmental studies will be conducted during PFS and FS stages to further investigation site conditions for potential impacts. The findings will be included in NEPA documents with proposed measure to mitigate potential impacts.

 

The planned mine is in an area that is used for dispersed summer recreation and fall big-game hunting and is well known to residents of the Boise area. Public interest in the project is expected to be elevated, and environmental organizations, including the Idaho Conservation League and Sierra Club, have communicated project-related information to their constituents. Accordingly, organized public opposition to mining activities should be anticipated and considered in future permitting and stakeholder-engagement planning.

 

260
 

 

22.2.7Economic Risks

 

22.2.7.1Project Strategy Risk

 

Overall, it is not expected that a major revision to the CuMo project strategy would be identified during the PFS (low to moderate risk level). The material movement approaches have the potential to be optimized at the PFS level; however, the current haul truck haulage strategy to conveyors for near plant material movement for the IA is consistent with general mining practices, but operating costs could be potentially improved via the implementation of in-pit crush and convey (IPCC).

 

Mineral sorting as contemplated in this study is not a mature technology at such a large-scale mine operation. There is a risk that the sorting assumptions used may not prove accurate at this scale. Elimination of the mineral sorting pre-process from the strategy has the potential to reduce the economic prospects of the project.

 

22.2.7.2Commodity Prices and Concentrate Terms

 

Molybdenum contributes 66% of modeled Base Case net product revenue, making project returns particularly sensitive to its price. Copper, silver, and rhenium prices, product payability, treatment charges and transport terms also affect revenue. The long production period exposes the project to sustained changes in prices and sales terms. The next economic evaluation should test downside price and commercial scenarios for the selected development configuration.

 

22.2.7.3Capital Requirements and Operating Performance

 

The preliminary estimate leaves uncertainty in installed quantities, site preparation, equipment pricing, and construction productivity. Cost increases or slower ramp-up would increase funding requirements and defer returns. The operating estimate also depends on achievable haulage and reclaim productivity, fuel and power costs, labor availability and maintenance. The long reclaim period makes equipment reuse, rebuilds and replacement timing material assumptions. PFS engineering should obtain updated supplier and operating inputs and test the effects of higher costs and slower ramp-up on funding requirements and project returns. Closure and post-closure water-treatment requirements remain preliminary. Changes in their scope or duration could increase costs beyond the allowances included in the IA.

 

22.2.7.4Schedule Risk

 

The permitting and development schedule required to construct the project may vary from the schedule assumed in the current study. This risk is asymmetric, with a materially greater potential for downside impact than upside benefit. The risk is increased by the seasonal nature of site access and construction conditions, which may be more difficult during winter months. As a result, relatively minor delays could have a disproportionate effect if they shift critical-path activities into periods of limited access or reduced construction productivity, potentially compounding the overall schedule delay.

 

261
 

 

22.2.7.5Process Recovery Risk

 

There is a risk that achieved recoveries could be lower than estimated, reducing the revenue and economic returns of the project. The process recovery estimates will be refined as part of the feasibility study as additional sampling and testing is completed.

 

22.2.7.6Permitting and Pre-Construction Schedule Risk

 

The economic model discounts cash flows to Year −3, the first modeled year of development. It does not explicitly model the duration of permitting before development. Delays in obtaining approvals could defer project cash flows and introduce additional costs, reducing project value when assessed from the report date.

 

22.2.8Project Opportunities

 

22.2.8.1Mineral Resource

 

If successful, additional drilling to the west could provide an opportunity to increase the Mineral Resource, both in terms of volume and higher-grade material, and add further process feed within the currently envisioned open pit or support future evaluation of an expanded pit configuration. Any such opportunity would require additional drilling, geological modeling, resource estimation, and mine planning studies to confirm its significance and potential impact on project economics.

 

Tungsten is present in the mineral deposit, and a previous mineral Resource Estimate included it. The potential for recovery and an additional revenue stream has not been considered in the IA. However, a tungsten recovery and processing circuit is intended to be further investigated in the PFS stage.

 

Additional infill drilling may also provide an opportunity to improve confidence in the Mineral Resource estimate by supporting conversion of lower-confidence resource categories to higher-confidence categories, refining mineralized domain boundaries, and improving confidence in grade continuity, density assumptions, and local block model estimates.

 

This opportunity could provide either more process feed within the current envisioned open pit or increased size of the open pit to the west. This expansion can be done but may have some effect on the location of the mill, sorting plant, or crusher.

 

22.2.8.2Mining

 

With increased knowledge of the rock mass and structural geology, thorough geotechnical field investigations, and slope stability analysis, there is potential to steepen the wall angles for CuMo, potentially reducing and/or deferring some mining costs.

 

Mining equipment has been considered to be traditional diesel powered for the IA. Electric drive and powered equipment, and trolley assist for trucks, will be evaluated during the PFS to understand where benefits are present to reduce OPEX requirements to maintain and operate the equipment fleet. Autonomous or remote control equipment may also be appropriate for specific needs such as blasthole drilling.

 

262
 

 

Further consideration of high angle conveying solutions in combination with semi-mobile crushing and conveying (In-pit Crushing and Conveying, or IPCC) concepts could highlight opportunities for cost savings at CuMo. The greatest opportunity comes from applying IPCC to the sorting feed stream, which the ore sorted material needs to be crushed for analysis and is up to 50% of the mined material. This approach for material handling has the potential to improve CAPEX and OPEX costs given the scale of the CuMo project.

 

Additional sequencing considerations include an evaluation of waste material and reject low-grade ore that can be identified using conventional ore control methods. This will expedite waste material handling to focus more on the application of an IPCC coupled with sorting technology.

 

22.2.9Mineral Sorting

 

The bulk sorting analysis was originally conducted on drill core that was sampled on a standard 10 ft interval. However, during 2023-2024, the Company employed an independent ore scanning firm which used XRF technology to scan 33,000 feet of drill core on 1.5 cm intervals. Thus, heterogeneity of the deposit was proven on a very small scale. With multiple stage sorting and splitting, smaller size packets of material can be measured; however, this needs to be balanced with practical mining practices and excavation selectivity. As heterogeneity increases with reduced scale, there is potential that better segregation of waste, mill primary feed, and middlings is possible. The opportunity would be for increased waste rejection, and ultimately reduced middlings fractions, to improve the economics of the project. Idaho Copper intends to use similar, small interval XRF scanning for future drill cores produced from the site.

 

However, the potential for mineral optimization from the heterogeneity of the deposit may not be adequately quantified from exploration-level data. Upon commencement of mine operations, Idaho Copper would obtain higher-resolution sampling and sorting across the continual exposure of the CuMo deposit. This has the potential to enhance project economics but cannot be quantified ahead of site development. Technology that is capable of penetrative scanning of ore within the mine face and crushed ore (e.g., MRI or atomic absorption methods) can augment the XRF scanning technology. This can refine the capability to classify and segregate ore as primary, middlings, and rejects, which in turn may increase head grade entering the plant and improve overall economics.

 

The field of mineral-sorting is the subject of significant research and development. There exists an opportunity for this project to exploit improvements in this technology that have been observed and likely will be developed ahead of project implementation.

 

22.2.10Processing

 

Additional metallurgical work should help to determine optimum grind size (the current assessment is based on the finest grind tested to date), analyze recoveries of the various metals, and analyze the effects of the higher grade coming from the mineral sorters on metal recoveries. Improvements in penetrative scanning technology can be considered and implemented to further improve the head grade feed to the plant. Optimization of reagents to reduce costs and improve metallurgical recoveries has the potential to improve project economics.

 

The ore sorting approach results in a large stockpile of middlings material that is intended for future processing through the mill after mining is completed. A sulfide ore leach pad and associated leaching circuit could provide a relatively low-cost approach to extract metals from this middling material shortly after crushing and ore sorting, rather than placed in long-term stockpile. This could provide additional revenue in the early years of the project rather than multiple decades in the future. There have been considerable advances in sulfide leaching techniques in recent years, and these will be evaluated in the PFS.

 

263
 

 

The current plan processes the middlings stockpile in the mill without further upgrading. There may be an opportunity to re-process the stockpile material through the ore sorting plant to upgrade the ore grade prior to milling. Using the existing ore sorting plant in this capacity may improve cash flow and reduce operating costs in the later years of the mine life.

 

Presently, the project assumes transportation of copper concentrates off-site for smelting and refining. Options to expand the on-site process capabilities may provide a more cost-effective use of CAPEX/OPEX while increasing revenue. Options under consideration for the PFS include leaching of sulfide concentrates, which can produce copper cathodes. This would allow Idaho Copper to produce marketable cathodes without shipment of concentrates to off-site and offshore smelters and refineries.

 

The trade-off evaluation for additional on-site or downstream process infrastructure includes consideration of a molybdenum roaster and/or a bolt-on iron-molybdenum plant using molybdenum-rhenium concentrates processed on-site. These facilities would further allow for an acid plant for sulfur recovery, with the potential for rhenium recovery. The molybdenum roaster would produce MoO3, a steel furnace feedstock, while a FeMo plant would provide ferro-molybdenum which is a feedstock for electric arc steel furnaces. These capabilities could augment the revenue stream, understood associated with further CAPEX, and increase the NPV.

 

As previously noted, tungsten mineralization is observed within the CuMo deposit, and has previously been included in a mineral Resource Estimate. Tungsten recovery and processing will be assessed for inclusion in the process approach to provide an additional revenue stream for the project. Further testing is required to determine if there may be opportunity to economically recover tungsten from the mineralized material.

 

22.2.11Project Infrastructure

 

Further studies and site investigation may allow for optimization of infrastructure designs, costing, and schedule. The following is a list of opportunities that could be optimized during trade-off studies to identify viable options that are worth pursuing.

 

A potential option that could improve concentrate transportation while minimizing impact and use of the road network, may be a gondola transport system from the concentrator downhill to a rail loadout area. Although this introduces a capital expenditure as well as operational maintenance, the benefit is reducing similar costs associated with overland truck transport. The approach also reduces the introduction of a portion of the large-scale traffic on the local roads, which otherwise might attract opposition from the local communities. In addition, a downhill run of a gondola-based concentrate transport can generate electricity for use in the project.

 

22.2.11.1Road Access

 

There is mutual benefit to Boise County, USFS, and Idaho Copper for improvements to the local county roads and USFS roads. The improved access roads will provide for wider traveling surfaces for vehicles, shoulders and ditches, improved sight lines, and potential traffic passing zones. A shared approach for the capital expenditure for initial improvement and on-going maintenance costs can be part of a shared use agreement for the increased traffic.

 

264
 

 

22.2.11.2Electrical Power

 

As previously noted, Idaho Power has intention to install or upgrade transmission lines to the vicinity of Placerville to the southwest (10 miles) and the vicinity of Garden Valley to the northeast (9 miles) of the CuMo project. Depending on the timing of these construction projects, and the plans of Idaho Power in terms of power that would be available from expansions and upgrades, Idaho Copper’s project timing may incur and incremental cost to continue electrical power to the site.

 

At the IA stage, there was limited evaluation of trade-offs for alternative electrical power sources. As power needs for the project are refined through future detailed development, such power options can more readily evaluated on a fit for purpose basis.

 

22.2.11.3Fuel Supply

 

At the current understanding and expected fuel supply needs for the process plant, trucking of natural gas to an on-site storage facility is the likely scenario. However, if the opportunity to extend an existing gas pipeline to the site may become viable.

 

22.2.11.4Water Supply

 

Further investigation of subsurface conditions and evaluation of surface water availability will be necessary to determine opportunities to evaluate sources. However, further evaluation of the process plant makeup water needs, and overall water balance can include approaches to minimize water use as well as maximize recovery from the TSF pond. Currently, there are water appropriations on the Boise River available for purchase or rent, or potentially water appropriations from the Payette Basin which could be traded for Boise rights, which will be pursued during the pendency of the PFS.

 

22.2.11.5Waste Rock Facility

 

Presently, there are strategic near pit and process facility external WRFs to allow for minimizing the waste and reject material haul. Further optimization of the mine plan and production schedule could lead to classification of additional waste material. This could be used to construct an additional toe buttress against the TSF embankment.

 

22.2.11.6Tailings Storage Facility

 

Geotechnical and hydrogeological studies of the TSF area are required to confirm foundation conditions and assess seepage pathways. The PFS should use site-specific investigation results to refine the embankment design and determine liner and other seepage-control requirements.

 

The timing of TSF construction is directly correlated to the production schedule. The PFS stage will include examining a heap leach facility to extract metals from the middlings material that would otherwise be stockpiled. A heap leach facility inherently will lead to less ore feed to the process plant and subsequently less tailings volume requiring storage. A reduced TSF size directly reduces costs to construct and operate the TSF.

 

265
 

 

22.2.12Economic Opportunities

 

22.2.12.1Material Handling Costs and Capital Requirements

 

Changing the balance between truck haulage and IPCC could improve project economics through lower operating costs or a different capital expenditure sequence. The mining-method tradeoff should compare the full installed, operating and equipment-replacement costs of each configuration over the project life.

 

22.2.12.2Concentrate Transport and Roasting

 

A molybdenum roaster at a railhead, together with alternative concentrate transport and sales arrangements, may improve product value or reduce logistics costs. Compare the current concentrate-sales approach with the full capital, operating, transport, permitting, and commercial requirements of the alternative. Rhenium recovery and product credits should be supported by representative test work and market terms.

 

22.2.12.3Project Strategy Opportunity

 

While the probability of a major revision to project strategy can be considered low to moderate, there are options to be evaluated during the PFS within trade-off studies that may allow for improvement to the strategy and economics. These are briefly summarized below as they were discussed in previous sections.

 

●IPCC infrastructure, as opposed to a conventional truck-shovel approach, applied with appropriate mine sequencing, to reduce material movement costs as the ore sorting process requires multiple rehandling cycles

 

●Inclusion of a heap leach process to recover revenue from middling material early in the life of mine rather than maintaining long term stockpiles with delayed value from the copper

 

●On-site or downstream construction of a molybdenum roaster, and potentially an iron-molybdenum plant, to create value-added products, enhancing revenue, while capturing sulfur through an acid plant for sale

 

●Consideration and infrastructure to capture rhenium during the process stream in a molybdenum roaster

 

●Further study of tungsten mineralization within the CuMo deposit for processing and revenue stream

 

●Production of copper cathodes on-site through copper concentrate leaching

 

●Power trade-off studies to optimize the use of energy and reduced costs

 

●Gondola transport study

 

22.2.12.4Commodity Price Opportunity

 

There is a risk that all commodity prices may not be consistent with assumptions made in this study. Higher prices, both realized and forecasted, would lead to re-optimization of the mine and processing plans with a potential to create additional value beyond that shown by the sensitivity analysis summarized in Section 19.5.7.

 

266
 

 

22.2.12.5Capital Cost Opportunity

 

Opportunities to reduce or defer capital expenditure may be realized in future studies. Care should be taken when considering the relationship between lower capital opportunities and technical risk to the project.

 

Options noted above include trade-off studies to consider IPCC, gondola transport of concentrates as well as the process plant options will require capital; however, there may be an optimal point in the production schedule to implement or expand after production is underway.

 

22.2.12.6Operating Cost Opportunity

 

Operating costs may be lower than forecast for the purposes of this study. Lower costs should feed into both strategic and short-term mine planning, to allow optimization of stockpiling, sorting, and mill feed strategies.

 

22.2.12.7Process Recovery Opportunity

 

Further metallurgical test work will allow for optimization of the process flow sheet and plant design in the pre-feasibility and feasibility studies. Better than planned recoveries are possible.

 

22.2.12.8Pit Slope Angle Opportunity

 

This is not considered to be a significant opportunity from an economic perspective. Strip ratios are relatively low, and incremental change in waste-movement volumes do not impact the overall project economics significantly.

 

267
 

 

23 Recommendations

 

23.1Mineral Resources

 

Mineral Resources determined for this estimate are effective as of August 30, 2018. New exploration DDHs commenced on the CuMo project on October 4, 2026. The information, core samples, and subsequent metallurgical testing will provide new data necessary to develop an updated Mineral Resource Estimate for the CuMo project.

 

Exploration work consisting mainly of drilling and laboratory analysis is required to reach pre-feasibility. It is estimated that a total of approximately 16 additional core holes for 40,000 ft of combined geology and geotechnical drilling.

 

●In-fill drilling

 

●Delineation drilling

 

●Geotechnical drilling – requires oriented core recovery system and/or borehole televiewer surveys to obtain in-situ structural geology data

 

●Metallurgical Drilling sample – large diameter hole (PQ size) recommended

 

●Condemnation drilling waste dump, mill and tailings site

 

Given the large scale and zoned nature of the CuMo mineralized system, future resource drilling should definitely prioritize areas that have the greatest potential to improve project economics, support conversion of Inferred Mineral Resources, refine early mine phases, and improve confidence in higher-value mineralized domains.

 

It is also recommended that the geological model and Mineral Resource estimate also be revisited and updated following completion of any material new drilling or technical work. This update should include reassessment of mineralized domain interpretations, grade continuity, density assumptions, variography, resource classification criteria, and reasonable prospects for eventual economic extraction.

 

These recommendations are intended to support advancement of the project toward a higher-confidence technical study and should be completed prior to any future PFS.

 

Further condemnation drilling of waste dump, mill site, and tailings pond areas can be completed outside of the exploration program as those borings are a distance from the ore body and require limited depth below the surface.

 

23.2Pit Geotechnical

 

A geotechnical-focused investigation and assessment have not been initiated. The following summarizes the desktop and field activities that are recommended for the next steps of geotechnical assessment:

 

●For a desktop evaluation from which the observations can be used to develop an optimized field geotechnical investigation and quantitative assessment, the following items can be completed on existing information.

 

268
 

 

○Geotechnical database QA/QC assessment, with respect to geology, to evaluate the possibly poor and variable geotechnical-related data observed in the existing data set

 

○Select a sub-set (~10-20%) of planned resource core drill holes that give good spatial coverage of the proposed pit walls, and from multiple drilling campaigns

 

○Undertake quantitative basic geotechnical logging using the full core photographs, if the photographs are available, of these drill holes to obtain total core recovery (TCR), solid core recovery (SCR), rock quality designation (RQD), and fracture frequency (FF/m or FF/ft)

 

○Log the core photographs to identify major structures and compare them to the 3-D geology model

 

○FF/m vs RQD plots for both the existing and the photo-logged data-sets for quantitative comparison

 

○Assessment of differences to determine whether variance is systematic or random, and consequently decide on the respective approach to address e.g. apply correction factor, re-logging more of the drill holes

 

○Qualitative assessment of the rock susceptibility to deterioration by comparing core in the photos (fresh), to the current condition of the stored core (aged)

 

●Geotechnical-specific diamond-cored drill holes targeted to provide coverage of the proposed interim and ultimate pit walls, and compatible with the pit depth

 

○Geotechnical logging to RMR89 system, or agreed upon system for consistency

 

○Field (empirical and point load) and laboratory (uniaxial and triaxial compressive strength and direct shear) testing of fresh core to determine intact rock strength and structural zone material to determine shear zone strength

 

○Calculate RMR and GSI values and conduct comparison with lithology, alteration and mineralogy zones of the 3-D geology model to establish broad geotechnical domains

 

○Establish pit sectors and domain-representative sections to conduct pit slope stability analyses and select pit design angles

 

23.3Mining

 

The IA provides a sufficient mining basis to advance the CuMo project toward a PFS, following the recommended additional studies and tradeoffs. The next work should assess shovel selectivity and sorting response, define the validation needed within the PFS and select the preferred development and material-handling configuration. The PFS investigations and engineering should address pit slopes and water management, construction-rock suitability, long-term middlings condition and reclaim, and fleet and workforce requirements. The study remains based on Mineral Resources and does not declare Mineral Reserves.

 

269
 

 

23.4Mineral Sorting

 

Idaho Copper should further engage and evaluate bulk and particle sorting technology providers to advance testing of penetrative technologies (e.g., MRI, PGNAA, PFTNA) such that base assumptions can be developed to apply methodologies appropriate for a large-scale, mine operation. These technologies, and other mineral sensing techniques, can support improved economics for the measurement of molybdenum in lower grade applications. This may include further testing, using samples collected from the CuMo project during future exploration campaigns, to assess the performance of bulk sorters at a bulk scale and an opportunity to compare different technologies.

 

Additionally, testing of the crushed product fines fraction mineralogy is recommended to determine if screening and direct feeding of this fraction to the mill would be beneficial to the project to potentially reduce displacement of on spec material.

 

23.5Processing

 

Additional metallurgical testing is recommended to confirm the design parameters for the mill. Variability samples consisting of at least 100 samples and representing all the ore zones at different elevations and pit locations should be tested. SAG mill, ball mill, crushing, and abrasion tests should be conducted on variability samples to confirm the mill sizing and maintenance requirements. Rougher kinetic flotation tests should also be conducted to quantify the flotation variability to be expected.

 

Composite samples representing specific periods of mill production should be developed and tested to determine the ore hardness and flotation recoveries. Solid-liquid separation tests should be conducted on the flotation test products to develop thickener and filtration design parameters. Mineralogy should be completed on the test feed and products to understand how recovery can be improved or processing costs reduced.

 

A large sample should be tested to further refine the copper-molybdenum flotation parameters. The separate copper and molybdenum concentrates produced in the test can be utilized for downstream testing. Downstream options that could be tested include chalcopyrite leaching to produce copper cathodes and molybdenum roasting to produce a higher value product, possible rhenium recovery, and sulfuric acid.

 

HPGR comminution and coarse particle flotation testing should be evaluated to determine the impact to site power consumption. Both technologies have the potential to reduce the required power.

 

Column leach testing of low-grade ore should be conducted to determine the copper recovery. The leaching will likely require biological oxidation of chalcopyrite to achieve economic recoveries. Leaching low-grade ore earlier in the project cycle has an opportunity to increase cash flow and NPV.

 

Testing to determine a viable recovery method for tungsten should be undertaken. Tungsten recovery could provide an additional revenue stream for the project.

 

23.6Project Infrastructure

 

Site access will be gravel roads from State Highways 21 and 55. Existing rail lines that parallel Highway 52 and Highway 55 can transport product from the CuMo project site if the product is trucked to a load-out facility in Horseshoe Bend. These will require discussion and agreements with both Boise County and the rail line owner and operator such that they understand the increase and scale of traffic and steps to resume active use of the rail line. Alternatively, a trade-off study for gondola transport of concentrates, versus conventional truck haulage, should be a part of the PFS.

 

270
 

 

Electrical power transmission lines could be routed from the southwest (Placerville) and the northeast (Garden Valley) to provide sufficient power to Site. Discussion with Idaho Power to understand the current long-term intent of infrastructure and options to extend power to the CuMo project site. A power trade-off study should be undertaken during the PFS to consider alternatives to extending lines to access the electrical grid.

 

Fuel for utilities and process equipment/heaters may be sourced as LNG from the Intermountain Gas Company and shipped via truck from nearby Nampa, Idaho. LNG storage, vaporization, and regasification facilities will be required at the CuMo project site. Further studies for transportation needs and options are necessary as they may impact the plans for upgrading gravel roads and rail line needs.

 

Several water supply sources have been identified at this stage: purchasing or leasing water in the Boise Basin, an appropriation from the Payette River which could be traded for a Boise Basin right, subsurface aquifers, and excess water from an adjacent drainage basin. All potential sources would be subject to water rights allocations and regulatory assessments. Further study and investigation is needed into potential water supply sources through subsurface drilling to understand the current interpretation of deep regional aquifer. Additionally, commence discussion with appropriate regulatory agencies to develop viable surface water sources through appropriate permitting and rights allocations.

 

23.7Tailings Management

 

The TSF is effectively active as a WRF, based on unit quantities needed to construct the TSF embankment. A geotechnical site investigation including geotechnical sample collection and material characterization must be completed prior to engineering studies to inform the foundation parameters of the TSF.

 

Engineering studies, including TSF design and potential water management and treatment design, including:

 

●Updating the TSF and WRF designs based on field investigation results

 

●Developing tailings deposition plan and waste placement sequence to match pit development and mill output

 

●Detailed analysis of the water and load balance to predict the accumulation of mill reagents in the process water circuit from the tailings

 

23.8Permitting

 

Idaho Copper should prepare a mining plan of operations and associated reclamation cost estimate that identify the locations of the mine, waste rock storage facilities, haul and access roads, power and water transmission corridors from source to point of use, the mill, tailings storage facility, and other supporting infrastructure. Operating plans should be developed concurrently with, and integrated into, the mining plan of operations. Idaho Copper should also develop comprehensive reclamation and closure plans for the proposed facilities and initiate the acquisition of any required water rights. Stakeholder engagement and outreach activities should continue throughout the permitting and project development process.

 

271
 

 

Following determination of the facility locations, Idaho Copper should coordinate with the appropriate state and federal agencies to identify the baseline studies required to support preparation of an environmental impact statement and should initiate those studies in a timely manner.

 

23.9Economics

 

At an 8% discount rate, the Base Case including Measured, Indicated and Inferred Mineral Resources has an after-tax NPV of US$1,878 million and an after-tax IRR of 18.50%. The M&I Case, excluding Inferred Mineral Resources from processing and revenue, has an after-tax NPV of US$1,482 million and an after-tax IRR of 17.04%. These results indicate economic potential under the preliminary assumptions and support further technical and economic evaluation. Mineral Resources do not have demonstrated economic viability, and neither case establishes Mineral Reserves.

 

23.10Additional Studies and Tradeoffs

 

Table 23-1 sets out a summary of work expected to be completed as part of a PFS study. Potential for additional investigation and design basis needs, must be evaluated during the PFS, to develop an appropriate plan and budget if further evaluation is necessary.

 

The recommended work is divided into two stages. Stage 1 comprises additional studies and tradeoffs to select the development configuration before PFS engineering. Stage 2 comprises the integrated PFS and its supporting investigations. The Stage 1 priorities are:

 

●Develop a geometallurgical model relating geology and material properties to sorting and metallurgical response, assess shovel and belt sorting, and define the validation program

 

●Compare mining methods, starter-pit development and material-handling arrangements

 

●Compare processing configurations and the sequence of capital expenditure

 

●Compare a railhead molybdenum roaster and concentrate transport arrangements

 

23.10.1Geometallurgical Model and Sorting Assessment

 

Develop an independently reviewed model relating geology, grade, mineralogy, and material properties to sorting and metallurgical response. Assess a smaller resource block size and change of support relative to the SMU. Review existing shovel and belt test data and use targeted supplier-supported assessments needed for the tradeoffs to develop preliminary material-specific response curves. Review the assumed block-grade treatment of dilution and loss, mixing, and the 0.8 response factor. Define the representative sorting trials and validation required within the PFS program, including the effect of each separation on downstream feed.

 

23.10.2Mining Method and Development Tradeoff

 

Compare starter-pit, access and haulage configurations, including truck-and-shovel mining, IPCC, trucked waste and separate waste conveying, where justified. Evaluate truck and conveyor placement and reclaim of middlings, crusher and conveyor relocations, and equipment renewal. Reconcile construction-rock requirements and available mine material by phase and period. Use complete schedules and economic comparisons including capital estimates to select the preferred mining and material-handling arrangement.

 

272
 

 

23.10.3Processing Configuration and Capital Staging

 

Compare initial and expanded plant capacities, fewer sorting stages or bypass routes, targeted sensor deployment, and staged installation. Integrate the available sorting responses with the mine schedule, direct feed, middlings storage, and reclaim. Include full installed and sustaining capital, construction timing and operating costs, and assess the implications of extended storage for treatment and handling. Define storage-aging tests for the PFS program to establish acceptable stockpile quantities and storage durations. Select the configuration and capital sequence for PFS development.

 

23.10.4Railhead Roaster and Concentrate Transport Tradeoff

 

Compare concentrate transport modes and locations for a molybdenum roaster at a railhead against the current concentrate-sales approach. Include capital, operating and transport costs, product specifications, rhenium recovery, commercial terms, and permitting requirements. Establish the preferred logistics and product strategy for the PFS.

 

Stage 1 should conclude with selection of the mining, sorting, processing, and concentrate logistics configuration. Advancement to Stage 2 should depend on positive technical and economic results.

 

23.11Integrated Pre-Feasibility Study

 

Stage 2 comprises PFS engineering and the supporting drilling, site investigations and sorting or processing validation required for the selected configuration. The investigation scope should be developed from the Stage 1 findings and use the work already completed. The principal PFS tasks are:

 

●Complete resource drilling and representative geometallurgical, shovel- and belt-sorting, and metallurgical validation for the selected plan; include fragmentation, digging and sensor trials and storage-aging tests to establish achievable selectivity, response, throughput, and the effects of extended middlings storage

 

●Complete geotechnical and hydrogeological investigations; develop slope criteria, dewatering and wall depressurization; test construction-rock suitability; and integrate supply with staged embankment demand

 

●Develop pit and phase designs, access, production and final-wall blasting, grade control, material routing, stockpile placement and reclaim, and the production schedule

 

●Develop fleet and workforce estimates, staffing and transport arrangements, current labor and fuel inputs, and equipment reuse, rebuild and replacement plans through the full reclaim period

 

●Coordinate processing, infrastructure, and facility design with construction and permitting schedules; prepare capital, operating and closure estimates, and the integrated economic model, including updated commercial and tax inputs and downside scenarios

 

Stage 2 should conclude with a PFS assessment of technical and economic viability and a decision on further advancement.

 

273
 

 

23.12Recommended Study Budget

 

Table 23-1 summarizes the recommended program. The estimated budget considers a two-stage approach to a PFS study. The first stage, which commenced on October 4, 2026, with an exploration drilling program on the CuMo project, includes investigations, data collection and assessment, and tradeoff studies. This budget estimate allows US$13.5‒21.0 million to complete these tasks. The PFS allowance includes US$8.5‒12.5 million for engineering and US$15‒25 million for supporting investigations and validation. These investigations remain within Stage 2.

 

The budget excludes land acquisition, the full environmental assessment and permitting program, and mine and facility construction. A purpose-built industrial sorting demonstration facility beyond vendor-supported trials requires a separate capital estimate within the PFS program.

 

Table 23-1 Estimated Budget for Additional PFS Study Work

 

Recommended Work Estimated Cost (US$M)
Stage 1: Investigations and Trade-offs Evaluation  
Geology, metallurgical, and geotechnical drilling 10.0-15.0
Metallurgical testing 0.2-0.3
Geotechnical assessment 0.2-0.3
Facility and infrastructure assessments 0.3-0.6
Geology and resource model updates 0.5-0.8
Geometallurgical model and sorting assessment 1.5-2.5
Mining method and development tradeoff 0.2-0.3
Processing configuration and capital staging 0.2-0.3
Railhead roaster and concentrate transport tradeoff 0.4-0.7
Stage 1 Subtotal: Additional studies and tradeoffs 13.5-21.0
Stage 2: Integrated PFS program  
PFS engineering 8.5-12.5
Supporting investigations and validation 15.0-25.0
Stage 2 Subtotal: Integrated PFS program 23.5-37.5
Total recommended study program 37.0-58.5

 

Source: NLM (2026).Note. Preliminary budgeting allowances in 2026 US dollars. Stage 2 detail is included in its program total and is not additional expenditure.

 

274
 

 

24 References

 

Anderson, A.L. (1947). Geology and Ore Deposits of the Boise Basin, Idaho. USGS Bull 944C.

 

Armstrong, R.L., Taubeneck, W.H., & Hales, P.O. (1977). Rb–Sr and K–Ar geochronometry of Mesozoic granitic rocks and their Sr isotopic composition, Oregon, Washington, and Idaho. Geological Society of America Bulletin 88, 397–411.

 

Ashurst Perkins Coie US LLP. (2026). Mineral Title Review Letter for the CuMo Project. Prepared for Idaho Copper Corp. June 29, 2026.

 

Ausenco Canada Inc. (2009) CUMO Project – Throughput Scoping Study Report, November 27, 2009.

 

Baker, D.J. (1985). Geology of the CUMO Molybdenum-Copper System, Boise County, Idaho. Geological Society of America, Abstracts with Programs 1985, Rocky Mountain Section, No. 70043, p 205.

 

Baker, D.J. (1983). The CUMO Molybdenite System, Boise, Idaho, A Comprehensive Summary”, Climax Molybdenum Company, April 1983, unpublished.

 

Palo, D.R., Sheets, R.J., Sims, S.B., Rehn, C., Smith, J.L., Flitton, G., Nayak, P..(2026). Preliminary Economic Assessment and NI 43-101 Technical Report dated October 23, 2026. Barr Engineering Co.

 

Bennett, E.H. (1986) Relationship of the trans-Challis fault system in central Idaho to Eocene and Basin and Range extensions. Geology, v. 14, 481-484.

 

Braun, R.M., Holmgren, J.A., Giroux, G.H., Kehmeier, R., & Khoury, C. (2009). CUMO Property Preliminary Economic Assessment, Boise County, Idaho, for Mosquito Consolidated Gold Mines Ltd., an Ausenco National Instrument 43101 report dated November 18, 2009.

 

Brunelli, K., & Moerenhout, T. (2026). Protecting existing us and Allied copper smelting capacity - center on global energy policy at Columbia University Sipa: CGEP. Center on Global Energy Policy at Columbia University SIPA | CGEP. https://www.energypolicy.columbia.edu/publications/protecting-existing-us-and-allied-copper-smelting-capacity/

 

Carten, R.B., White, W.H., & Stein, H.J. (1993). High-Grade Granite-Related Molybdenite Systems: Classification and Origin, in Kirkham, R.V., Sinclair, W.D., Thorpe, R.I. and Duke, J.M., eds., Mineral Deposit Modeling; Geological Association of Canada, Special Paper 40, p. 521-544.

 

Giroux, G., Cavey, G., & Gunning, D. (2005). Summary Report on the CUMO Molybdenum Property, Boise County, Idaho, for Kobex Resources LTD., unpublished.

 

Giroux, G., Dykes, S., & Place, J.H. (2015) Summary Report on the CUMO Molybdenum Property, Boise County, Idaho. A national instrument 43-101 Report for American CuMo Mining Corp.

 

Hildenbrand, T.G., Berger, B., & Jachens, R.C. (2000). Regional Crustal Structures and Their Relationship to the Distribution of Ore Deposits in the Western United States, Based on Magnetic and Gravity Data. Econ. Geol. v.95. p. 15831603.

 

Holmgren, J. & Giroux, G. (2008). Summary Report on the CUMO Property, Boise County, Idaho. NI 43-101 Technical Report for Mosquito Consolidated Gold Mines Ltd., posted at www.sedar.com

 

Idaho Geological Survey. (n.d.). Introduction to mines and prospects database. https://www.idahogeology.org/geologic-resources/mines-minerals/introduction-to-mines-and-prospects-database

 

Idaho Department of Water Resources (2018). Water District Descriptions, https://idwr.idaho.gov/ExternalReports/WaterDistrictDescriptionReport.pdf , accessed November 20, 2018.

 

275
 

 

International Copper Study Group. (2025). Copper factbook. Accessed October 13, 2025. https://icsg.org/copper-factbook/

 

International Energy Agency [IEA]. (2025). Global Critical Minerals Outlook 2025. https://iea.blob.core.windows.net/assets/ef5e9b70-3374-4caa-ba9d-19c72253bfc4/GlobalCriticalMineralsOutlook2025.pdf

 

Johnson, B. R. & Raines G. L. (1996). Digital representation of the Idaho state geologic map: a contribution to the Interior Columbia River Basin Ecosystem Management Project; USGS Open File Report 95-690.

 

Killsgaard, T.H, Stanford, L.R., & Lewis, R.S. (2006). Geologic Map of the Deadwood River 30 x 60 Minute Quadrangle, Idaho. Idaho Geological Survey. Geologic Map 45.

 

Killsgaard, T.H, Stanford, L.R., & Lewis, R.S. (2001). Geologic Map of the Idaho City 30 x 60 Minute Quadrangle, Idaho. Idaho Geological Survey, Geologic Map GM-29, scale 1:100,000.

 

Killsgaard, T.H, Fisher, F.S., & Bennet, E.H. (1989). Gold-Silver Deposits Associated with the Trans-Challis Fault System, Idaho. USGS Bull 1857-B. p. B22-B44.

 

Killsgaard, T.H, & Lewis, R.S. (1985). Plutonic Rocks of Cretaceous Age and Faults in the Atlanta Lobe of the Idaho Batholith, Challis Quadrangle. USGS Bull 1658 A-S. p. 29-42.

 

Klein, T.L. (2004). Mineral deposit data for epigenetic base-and precious-metal and uranium-thorium deposits in south-central and southwestern Montana and southern and central Idaho. USGS Open File Report 2004-1005.

 

Lewis, R.S., Kiilsgaard, T.H., Bennett, E.H., & Hall, W.E. (1987). Lithologic and chemical characteristics of the central and southeastern part of the southern lobe of the Idaho batholith: in Vallier, T.L., and Brooks, H.C., eds., Geology of the Blue Mountains Region of Oregon, Idaho, and Washington: The Idaho Batholith and Its Border Zone. U.S. Geological Survey Professional Paper 1436, Chapter 9, p. 171–196.

 

Link, P.K. (2002). Geological Map of Boise County, Idaho. Digital Atlas of Idaho. website: http://imnh.isu.edu/digitalatlas/counties/geomaps/geomap.htm

 

Lipsett, J., & Simpson Jr. (1973). Analysis of the response by wheat to the application of molybdenum in relation to nitrogen status. Australian Journal of Experimental Agriculture and Animal Husbandry

 

Lowell, J.D., & Guilbert, J.M. (1970) Lateral and Vertical Alteration-Mineralization Zoning in Porphyry Ore Deposits. Economic Geology, 65, 373-408.

 

Lund, K., Klein, T.L, O’Neill J.M.,& Sims, P.K. (2005). Influence of structure and composition of basement on mineral deposits across Montana and Idaho; EarthScope in the Northern Rockies.

 

Lycopodium (Americas), Ltd. (2024). Nayak, P., Memorandum: Application of Ore Sorting at Idaho Copper’s CuMo Deposit

 

Mordor Intelligence. (2024). Molybdenum Market 2022-27 Industry Share, Size, Growth. https://www.mordorintelligence.com/industry-reports/molybdenum-market

 

Mutschler, F. E., Ludington, S., & Bookstrom, A. A. (2000). Giant porphyry-related metal camps of the world—A database (Open-File Report 99–556, Online Version 1.0). U.S. Geological Survey. https://doi.org/10.3133/ofr99556

 

O’Neill, J.M., & Lopez, D.A. (1985). Character and regional significance of the Great Falls tectonic zone, east-central Idaho and west-central Montana. American Association of Petroleum Geologists Bulletin, v. 69, p. 437–477.

 

Panteleyev, A. (1995). Porphyry Cu+/-Mo+/-Au, in “Selected British Columbia Mineral Deposit Profiles, Volume 1 - Metallics and Coal”, Lefebvre, D.V. and Ray, G.E., Editors, British Columbia Ministry of Energy of Employment and Investment, Open File 1995-20, pages 87-92.

 

276
 

 

Polyak, D. E. (2025). Mineral commodity summaries 2025: Molybdenum. U.S. Geological Survey. https://pubs.usgs.gov/periodicals/mcs2025/mcs2025-molybdenum.pdf

 

Rostad, O. H. (1978). K-Ar dates for mineralization in the White Cloud-Cannivan porphyry molybdenum belt of Idaho and Montana—A discussion. Economic Geology, 73(7), 1366–1368. https://doi.org/10.2113/gsecongeo.73.7.1366

 

S&P Global Market Intelligence. (2026). Copper and gold market outlook 2026: Prices, supply and mining costs. Accessed April 16, 2026. https://www.spglobal.com/market-intelligence/en/news-insights/research/2026/04/copper-gold-market-outlook-2026-prices-supply-mining-costs

 

S&P Global Market Intelligence. (n.d.). Commodities. S&P Capital IQ. Retrieved June 7, 2026, from https://www.capitaliq.spglobal.com/apisv3/spg-webplatform-core/markets/commoditiesDetail?NavFrom=0&PID=34&tabID=2

 

Seale, A. (2026). Solar silver thrifting not enough to curb demand. Accessed June 5, 2026. MINING.COM. https://www.mining.com/solar-thrifting-not-enough-to-curb-demand/

 

Silver Institute. (2024) World Silver Survey 2024. https://silverinstitute.org/wp-content/uploads/2024/07/World-Silver-Survey-2024.pdf

 

Sims, P.K., Lund, K., & Anderson, E.(2005). Precambrian Crystalline Basement Map of Idaho – An Interpretation of Aeromagnetic Anomalies. USGS, Scientific Investigations Map 2884.

 

Singer, D.A., Berger, V.I., & Moring, B.C. (2005). Porphyry Copper Deposits of the World: Database, Map, and Grade and Tonnage Models. USGS Open File Report 2005-1060.

 

Spanski, G.T. (2004). Inventory of Significant Mineral Deposit Occurrences in the Headwaters Project Area in Idaho, Western Montana, and Extreme Eastern Oregon and Washington. USGS Open File Report 2004-1038.

 

SGS. (2009). An Investigation into the Recovery of Molybdenum, Copper and Silver from CUMO samples prepared for Mosquito Consolidated Gold Mines Ltd Project 50004-001

 

SRK Consulting (Canada), Inc. (2020). Arseneau, G., McCarthy, B., Thomas, A., Boese, C., Winkelmann, N., Sawyer, V., Giroux, G., Starkey, J., Preliminary Economic Assessment & NI 43-101 Technical Report for the CuMo Project, USA

 

Snowden Mining Industry Consultants (2012). Jones, I., Scott K., Kehmeier, R., and Khoury, C., Resource Estimate Update June 2011, updated June 2012 posted at www.sedar.com

 

United States Department of Agriculture, Forest Service (2018). Supplemental Redline Environmental Assessment CuMo Exploration Project, December 2018.

 

United States Department of Agriculture, Forest Service (2019). Record of Decision Boise National Forest Invasive Species Project, March 2019.

 

United States Department of Agriculture, Forest Service (2015). CuMo Exploratory Project Supplemental Environmental Assessment, March 2015.

 

United States Department of Agriculture, Forest Service (2011).Environmental Assessment CuMo Project, February 2011.

 

U.S. Forest Service. (2026). Boise National Forest: NEPA project—2023 CUMO exploration project. https://www.fs.usda.gov/r04/boise/projects/64920

 

World Population Review. (2026a). Copper production by country 2026. Accessed June 16, 2026. https://worldpopulationreview.com/country-rankings/copper-production-by-country

 

World Population Review. (2026b). Molybdenum production by country 2026. Accessed June 16, 2026. https://worldpopulationreview.com/country-rankings/molybdenum-production-by-country

 

World Population Review. (2026c). Silver production by country 2026. Accessed June 16, 2026. https://worldpopulationreview.com/country-rankings/silver-production-by-country

 

YCharts Inc. (2026a). Copper Spot Price (I:CSPNM). Accessed June 22 and October 6, 2026. https://ycharts.com/indicators/copper_spot_price

 

YCharts Inc. (2026b). Molybdenum Spot Price (I:MSPNTS2D). Accessed May 28, June 22 and October 7, 2026. https://ycharts.com/indicators/molybdenum_spot_price

 

YCharts Inc. (2026c). Silver Price(I:NYSP). Accessed June 22 and October 6, 2026. https://ycharts.com/indicators/silver_price

 

277
 

 

25 Reliance on Information Provided by the Registrant

 

25.1Title Opinion

 

The Qualified Person responsible for the property description and mineral-tenure disclosure has relied on the Mineral Title Review Letter dated June 29, 2026, prepared by Ashurst Perkins Coie US LLP (Ashurst, 2026) for Idaho Copper Corp., including its referenced schedules and exhibits. The letter was provided to Barr Engineering Co. by Idaho Copper Corp.

 

The reliance applies to the legal conclusions concerning Idaho Copper Corp.’s ownership of, or interest in, the patented and unpatented mining claims comprising the CuMo project; the status and validity of those claims; and the material agreements, obligations, encumbrances, limitations, and other title matters addressed by counsel. These conclusions support the mineral-title, property-ownership, and tenure disclosures in Chapter 3, Property Description and Location, and corresponding disclosures elsewhere in this Report.

 

The Qualified Person compared the information in the letter with the claim schedules, property maps, Mineral Resource location, and conceptual project facilities presented in this Report. The Qualified Person did not independently examine title, verify the underlying public records or legal instruments, or provide a legal opinion regarding ownership, claim validity, encumbrances, access rights, or enforceability of agreements. The reliance concerns legal matters outside the Qualified Person’s expertise and is based on the project-specific letter prepared by identified legal counsel for Idaho Copper Corp. and the consistency checks described above. The legal conclusions are attributed to counsel; responsibility for the report’s use of third-party specialist information is not disclaimed.

 

25.2Taxes and Depreciation

 

The Qualified Person responsible for the economic analysis relied on Idaho Copper Corp.’s inputs and review of federal and Idaho income taxes, alternative minimum tax and related credits, depreciation, percentage depletion, and tax-loss carryforwards, as communicated throughout the project and confirmed by Andrew Brodkey in his October 12, 2026, email “CuMo Project Production Plan v83.2 TEM. Rev-06.” These assumptions were used in the after-tax economic analysis presented in Section 19. Reliance on the registrant concerns legal and governmental fiscal information outside the economic Qualified Person’s expertise. The basis is Idaho Copper’s provision and review of the project-specific fiscal inputs and its confirmation of them. The reliance applies to the fiscal assumptions in Sections 19.4.5 and 19.4.6 and their use in the after-tax results for both resource cases. The economic Qualified Person retains responsibility for applying the stated assumptions in the cash-flow calculations and interpreting the results.

 

278