STOCK TITAN

GoldMining (NYSE: GLDG) outlines $532M NPV and 42% IRR in São Jorge PEA

Filing Impact
(Neutral)
Filing Sentiment
(Neutral)
Form Type
6-K

Rhea-AI Filing Summary

GoldMining Inc. released a preliminary economic assessment for its São Jorge gold project in Brazil, outlining an after-tax net present value (NPV 5%) of $532.5 million and a 42.4% after-tax internal rate of return at a gold price of $3,500/oz. The study contemplates a 10.6-year open-pit mine with total production of 543.2 thousand ounces of gold, averaging 53.4 thousand ounces annually in the first five years and life-of-mine average production of 51.2 thousand ounces, at all-in sustaining costs of $1,464 per ounce payable. Initial capital expenditure is estimated at $202.2 million, with total capital of $267.2 million including sustaining and closure costs, and an after-tax payback period of 2.83 years. GoldMining emphasizes that the PEA is preliminary in nature, relies in part on Inferred Mineral Resources, and there is no certainty the economic projections will be realized.

Positive

  • None.

Negative

  • None.

Insights

São Jorge PEA shows robust modeled returns but remains an early-stage, conceptual study.

The São Jorge assessment outlines after-tax NPV 5% of $532.5M and after-tax IRR of 42.4% at a base gold price of $3,500/oz, against initial capital of $202.2M. Modeled mine life is 10.6 years with total production of 543.2 koz and all-in sustaining costs of $1,464/oz.

Economics improve materially at a higher gold price, with spot-case after-tax NPV 5% of $836.8M and IRR of 58.6%. However, the study is a preliminary economic assessment that includes Inferred Mineral Resources, which are explicitly described as too speculative geologically to count as reserves or demonstrate economic viability.

Future technical reports, permitting and pre-feasibility work, as referenced for filing within 45 days, will be important to refine costs, recoveries, and resource confidence. Actual outcomes will depend on metal prices, financing availability, regulatory approvals and results from further drilling and metallurgical testing.

After-tax NPV 5% (base case) $532.5M Modeled at $3,500/oz gold price
After-tax IRR (base case) 42.4% São Jorge project economics at $3,500/oz Au
Initial capital expenditure $202.2M Includes pre-strip and 25% contingency
All-in sustaining costs (AISC) $1,464/oz payable Life-of-mine average for São Jorge
Total gold produced 543.2 koz Life-of-mine production over 10.6 years
Average annual production (Years 1–5) 53.4 koz Highest production period in PEA schedule
Spot-case after-tax NPV 5% $836.8M Modeled at $4,400/oz gold spot scenario
After-tax payback period 2.83 years Base case $3,500/oz Au scenario
preliminary economic assessment financial
"GoldMining announces the results of a preliminary economic assessment ("PEA") on its São Jorge Project"
A preliminary economic assessment is an initial analysis that estimates the potential profitability and feasibility of a project or resource, such as a new mineral deposit or development venture. It provides a rough idea of costs, benefits, and risks, helping investors decide whether to pursue more detailed studies. This early evaluation is important because it offers a snapshot of whether the project is worth further investment and development.
All-In Sustaining Costs (AISC) financial
"All-In Sustaining Costs (AISC) 3 | $/oz payable | 1,464"
All-in sustaining costs (AISC) is a per-unit measure that shows the total ongoing cost to keep a producing asset running, including operating expenses, routine maintenance, sustaining capital, and a share of corporate and administrative costs. For investors it provides a more complete picture than simple production cost numbers—think of it as the full monthly bill to maintain a business divided by its output—helping compare profitability and cash flow durability across producers.
Inferred Mineral Resources financial
"The PEA includes Inferred Mineral Resources, which are considered too speculative geologically"
An inferred mineral resource is an estimate of the quantity and grade of minerals in the ground based on limited sampling and geological information, where confidence is low and continuity is uncertain. For investors it signals potential value but also higher risk—like a rough sketch of a hidden treasure that requires much more exploration and testing before you can reliably judge its size or economic worth.
Net present value (NPV 5%) financial
"Net present value (NPV 5% ) – after-tax | $M | 532.5"
internal rate of return (IRR) financial
"Internal rate of return (IRR) – after-tax | % | 42.4"
The internal rate of return (IRR) is the annualized percentage return that makes the total value of a project's or investment's future cash flows equal the amount invested today — in other words, the break-even interest rate for that investment. Investors use IRR like a single-number speedometer to compare opportunities: a higher IRR means a project is expected to generate a stronger annual return, helping decide which investments are likely more attractive relative to required returns or alternatives.
NI 43-101 financial
"Disclosure regarding the Project, including the PEA and Mineral Resource Estimates included herein, has been prepared in accordance with NI 43-101"
A Canadian regulatory standard that sets the rules for how mining and exploration companies must report mineral resources and reserves, requiring technical reports prepared or signed off by an independent, certified expert. It matters to investors because it creates a consistent, transparent “inspection report” for mining projects, making it easier to compare prospects, judge the reliability of claims, and assess geological and financial risk before investing.
See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

 

U.S. SECURITIES AND EXCHANGE COMMISSION

Washington D.C. 20549

 

FORM 6-K

 

REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO RULE 13a-16 OR 15d-16 UNDER THE SECURITIES EXCHANGE ACT OF 1934

 

For the month of June 2026

 

Commission File Number: 001-39566

 

 

GoldMining Inc.

(Translation of registrant's name into English)

 

Suite 1830, 1188 West Georgia Street, Vancouver, British Columbia, Canada

(Address of principal executive office)

 

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.

 

☐ Form 20-F

 

☒ Form 40-F

 

 

 

 

EXHIBIT INDEX

 

 

Exhibit

Number

Description

   

99.1

News Release dated June 11, 2026

 

 

 

 

SIGNATURES

 

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

 

GOLDMINING INC.

 

 

By:

/s/ Pat Obara

 

Pat Obara

 

Chief Financial Officer

 

 

Date: June 11, 2026

 

 

Exhibit 99.1

 

 logomed.jpg

 

 

GoldMining Announces Positive PEA Highlighting $532 Million After-Tax NPV and 42% IRR at its São Jorge Project, Brazil

 

DESIGNATED NEWS RELEASE

 

Vancouver, British Columbia – June 11, 2026 – GoldMining Inc. (TSX: GOLD; NYSE American: GLDG) (the "Company" or "GoldMining") is pleased to announce the results of a preliminary economic assessment ("PEA") on its São Jorge Project (the "Project"), located in Pará State, Brazil.

 

All currency amounts herein are in US dollars unless otherwise indicated.

 

PEA Highlights

 

 

Strong Base Case Economics: The PEA sets out a base case scenario with an after-tax net present value at a 5% discount rate ("NPV5%") of $532 million and an after-tax internal rate of return ("IRR") of 42.4% utilizing base case gold price of $3,500 per ounce (“oz”) and an initial payback of 2.8 years.

 

 

Leverage to Gold Price: At spot gold prices ($4,400/oz), the after-tax NPV5% increases to $836.8 million, yielding an IRR of 58.6% and an initial payback of just 2.4 years.

 

 

High Capital Efficiency & Infrastructure Advantage: Initial capital is estimated at a highly manageable $202 million (including a 25% contingency), representing an attractive 2.6x base case NPV5% to initial capital ratio. This relatively low capital hurdle is directly supported by the Project’s ideal location, situated adjacent to existing power lines, paved highways, and an available skilled workforce.

 

 

Balance Sheet Backing: The Company’s strong balance sheet comprising approximately $183 million1 in cash and publicly traded securities positions it well to advance the Project through the next stages of development.

 

 

Cash Generator for the Company: The PEA envisages a robust internal free cash flow, supported by a stable gold production profile averaging an estimated 51,250 oz annually over a 10.6-year life of mine ("LOM"), with peak gold production of 57,200 oz per year in years 2 through 4.

 

 

Resilient Cost Profile: The PEA highlights relatively strong estimated margins, supported by an estimated life of mine All-In Sustaining Cost ("AISC") of $1,464/oz.

 

 

Conventional Operation: The PEA contemplates a conventional open-pit truck-and-shovel operation and a processing rate of 5,500 tonnes per day. A proven processing flowsheet utilizing standard gravity and leach circuits achieves high metallurgical recoveries of 90% Au.

 

 

Advancing Pre-Feasibility Studies: The Company plans to expeditiously commence pre-feasibility studies as the Project is further de-risked and moves forward with permitting towards a construction decision.

 

Alastair Still, CEO of GoldMining commented, “The São Jorge PEA marks a significant milestone in the advancement of our corporate strategy. By combining a manageable $202 million initial capital investment with a robust $532 million base case NPV5%, we have outlined a highly efficient, construction-track asset on a regional-scale property that retains significant exploration potential for additional resource growth. More than just a standalone project, the PEA highlights that São Jorge has the potential for resilient margins and rapid payback potential to become a cornerstone self-funding asset for us. With robust economics, we look forward to rapidly advancing and de-risking the Project with permitting and pre-feasibility studies to unlock further value across our gold-focused multi-million ounce Americas portfolio.”

 

1.

Cash holdings as at latest filings for the quarter ended February 28, 2026. The closing prices of shares underlying equity holdings as at close of June 10, 2026 and subject to a USD:CAD FX of $1.39.

 

 

 

logomed.jpg

 

The PEA is preliminary in nature, and there is no certainty that the reported results will be realized. The PEA includes Inferred Mineral Resources, which are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves. There is no certainty that this PEA, including the conceptual economics set out therein, will be realized.

 

 

Table 1: Summary of São Jorge PEA Selected Production Metrics

 

São Jorge PEA Key Metrics

   

Production

Result

Units

Mine life

10.6

Years

LOM Strip ratio (waste:processed material)

4.27

Ratio

Total mined material

109.1

Mt

Total processed material

20.7

Mt

Nominal process plant rate

5,500

tpd

Gold Production

   

Average gold feed grade

0.91

g/t

Average gold metallurgical recovery

90.0

%

Total gold produced

543.2

koz

Average annual gold production (Years 1-5)

53.4

koz

                                                             LOM

51.2

koz

 

Numbers may not add due to rounding.

 

 

 

Table 2: Summary of São Jorge PEA Selected Financial Metrics

 

São Jorge PEA Key Financial Metrics

   

Operating Costs (OPEX)

Units

Result

Mining unit cost

$/t mined

$/t milled

1.98

10.40

Process unit cost

$/t milled

10.44

General and Administrative (G&A) unit cost

$/t milled

1.29

Royalty (including government royalites)

$/t milled

4.21

Other (including maintenance and contingency)

$/t milled

8.55

Total OPEX

$/t milled

34.88

Transport & Refining Cost

$/t milled

0.16

Total Cash Cost2

$/t milled

$/oz payable

35.04

1,344

All-In Sustaining Costs (AISC)3

$/oz payable

1,464

Capital Expenditures (CAPEX)

Units

Result

Initial capital expenditure (includes pre-strip)

$M

202.2

Sustaining capital expenditure

$M

53.0

Closure costs

$M

12.0

Total Capital

$M

267.2

Base Case Economics ($3,500/oz Au)

Units

Result

Net present value (NPV5%) – pre-tax

$M

645.7

Internal rate of return (IRR) – pre-tax

%

48.9

Net present value (NPV5%) – after-tax

$M

532.5

Internal rate of return (IRR) – after-tax

%

42.4

Payback – after-tax

Years

2.83

Spot Price Economics ($4,400/oz Au) 3

Units

Result

Net present value (NPV5%) – pre-tax

$M

1,004.8

Internal rate of return (IRR) – pre-tax

%

67.3

NPV5% – after-tax

$M

836.8

IRR – after-tax

%

58.6

Payback – after-tax

Years

2.38

 

Numbers may not add due to rounding.

 

(1) Total Cash Cost consists of total operating costs plus transportation and refining costs.

 

(2) AISC includes Total Cash Cost plus sustaining capital and closure costs.

 

(3) Spot price determined on June 9, 2026 based on the 10-day trailing average rounded down to the nearest hundred.

 

 

 

logomed.jpg

 

São Jorge PEA Summary

 

The São Jorge Project is located in the southeastern portion of Pará State, Brazil, in the municipality of Novo Progresso, approximately 460 km southeast of the main regional city of Santarem and approximately 70 km north of the town of Novo Progresso. Regional highway BR-163, an all-weather paved road, passes through the Project area. The city of Itaituba is located approximately 250 km north of the Project.

 

The current mineral resource estimate for São Jorge was reported in the Company’s technical report titled "NI 43-101 Technical Report São Jorge Project, Para State, Brazil" dated effective January 28, 2025. The PEA is based on such estimate.

 

The PEA considers a conventional drill, blast, load, and haul open pit operation mining an average of 27,000 tpd (9.9 million tonnes per annum (Mtpa) over the 10.6 year life of mine. It contemplates that resources will be processed at a nominal rate of 5,500 tpd (1.9 Mtpa) at an average strip ratio of 4.27:1. Conventional gravity and leach circuit is planned to generate gold doré on site.

 

The PEA includes on-site development including mining, haul roads, access roads, process facilities, tailings and waste storage facilities, and related ancillary facilities. Construction is anticipated to take approximately two years with an initial capital expenditure of $202.2 million, including a healthy 25% contingency, with operations continuing for 10.6 years. Sustaining capital expenditures over the LOM are expected to be approximately $53 million, consisting of a mix of mining capital equipment and staged expansion of the tailings and waste facilities. Closure costs have been estimated at $12 million. LOM operating costs are expected to average $34.88/t of material processed.

 

Under the PEA, highest metal production occurs in the initial five years of production averaging 53.4 koz Au annual production. LOM average production is 51.2 koz Au.

 

 

 

 

logomed.jpg

 

Table 3: Estimated Capital Breakdown

 

Capital Area

Initial

($M)

Sustaining

 ($M)

Total

 ($M)

Site General & Pre-Construction

33.0

 

33.0

Power Distribution

16.8

 

16.8

Mining & Equipment

11.6

30.7

42.3

Process Plant

47.0

9.4

56.4

Tailing Storage & Water Management

4.5

 

4.5

Indirect Costs

13.9

 

13.9

Owner's Cost and General Services

40.5

 

40.5

Contingency (25%)

34.9

13.0

47.9

Sub-total Capital

202.2

53.0

255.2

Mine Closure

 

12.0

12.0

Total Capital

202.2

65.0

267.2

 

Numbers may not add due to rounding

 

 

 

Figure 1: Mined Material Schedule

 

a01.jpg

 

 

 

 

logomed.jpg

 

Figure 2: Process Schedule

 

a02.jpg

 

 

 

The São Jorge Deposit

 

The São Jorge Gold Project is located in the Tapajós gold district (see Figure 3) in the south-central portion of the Amazon Craton. The São Jorge gold deposit is a granite-hosted, intrusion-related gold mineral system which is a similar style to the Tocantinzinho gold mine owned and operated by G Mining located approximately 80 km northwest of São Jorge, that commenced commercial production in 2024 and produced 171,871 ounces of gold in 2025.

 

Exploration activities at the Project carried out by the Company over the past two years have successfully delineated several new exploration targets comprising gold ± copper ± molybdenum ± silver soil geochemical anomalies, which cumulatively outline a large mineral system (see news releases dated March 18, 2025 and April 14, 2025). The São Jorge mineral system is defined by a comprehensive exploration data set which the Company has developed over previous systematic exploration campaigns. Surrounding the currently delineated São Jorge deposit, which has a defined 1.4 km strike length, the broader mineral system comprises a zone of contiguous surface geochemical anomalies over an area of 12 km x 7 km, which the Company interprets to be the surface expression of a broad intrusion related gold system.

 

 

 

logomed.jpg

 

Figure 3: São Jorge Project location

 

a03.jpg

 

 

 

 

logomed.jpg

 

Mineral Resource Estimate

 

The PEA is based on the Company’s existing previously disclosed mineral resource estimate, which is summarized in the table below.

 

Table 4: Pit Constrained Mineral Resource Estimate

 

Category

Tonnage

(000 t)

Grade

(g/t Au)

Contained Metal

(000 oz Au)

Indicated

19,418

1.00

624

Inferred

5,557

0.72

129

 

Notes:

 

1.

See technical report titled "NI 43-101 Technical Report São Jorge Project, Para State, Brazil” dated effective January 28, 2025.

 

2.

CIM (2014) definitions were followed for Mineral Resources.

 

3.

Mineral Resource are estimated at a break-even cut-off grade of 0.27 g/t Au for classified blocks above a constraining pit shell.

 

4.

Mineral Resources are estimated using a long-term gold price of US$1,950 per ounce.

 

5.

A minimum mining width of five meters was used.

 

6.

There are no Mineral Reserves estimated at São Jorge Project. Mineral Resources that are not Mineral Reserves have not demonstrated economic viability.

 

7.

Numbers may not add due to rounding.

 

8.

The Qualified Person (QP) of the mineral resource estimate is not aware of any environmental, permitting, legal, title, taxation, socio-economic, marketing, political, or other relevant factors that could materially affect the mineral resource estimates.

 

For a description of the data verification, assay procedures and the quality assurance program and quality control measures applied by the Company, please see the Company’s Annual Information Form for the year ended November 30, 2025, filed under the Company’s profile on SEDAR+ at www.sedarplus.ca. Further information about the PEA referenced in this news release, including information in respect of data verification, key assumptions, parameters, risks and other factors, will be contained in a technical report, which will be filed by the Company in respect of the PEA within 45 days under its profile at SEDAR+ at www.sedarplus.ca.

 

Opportunities

 

This new PEA highlights strong potential for the advancement of the Project and sets out several opportunities for future study which may further enhance project value, including:

 

Opportunity

Potential Benefits

Metallurgical test work & Process design

Variability test work to optimize process flowsheet and improve gold recoveries.

 

Infill Drilling

Increase confidence in the geological models and controls on and interpolation of grade; may increase resource grade overall and convert mineral resources to higher categories.

 

Exploration Drilling

Expansion opportunities at the existing deposits to delineate additional resources.

 

Geotechnical test work

Optimize pit wall slopes and potentially reduce strip ratio and to assess potential waste rock and tailings storage sites.

 

Infrastructure design & Scheduling

Optimize site layout, material handling and pit backfill to reduce LOM operating costs.

 

Environmental & Sustainability Governance (ESG)

Environmental baseline & heritage studies, and community stakeholder engagement to inform the local community about the potential mining opportunity and economic benefits.

 

 

 

 

logomed.jpg

 

Qualified Persons

 

The PEA was prepared for the Company by Beck Nader,DSc, MSc.,FAIG, CBRR , who is independent of the Company and a Qualified Person, as such term is defined in NI 43-101.

The Mineral Resources were estimated by Reno Pressacco, M.Sc. (A), P.Geo., FGC, who is independent of the Company and a Qualified Person, as such term is defined in NI 43-101.

The specific sections of the technical report for which each such Qualified Person is responsible will be set out in the technical report relating to the PEA. Each such Qualified Person has reviewed and approved the scientific and technical information regarding the PEA as disclosed in this news release.

 

Imola Götz, M.Sc. P.Eng., F.E.C., Vice President, Project Development of the Company and a Qualified Person, as such term is defined in NI 43-101, has supervised the preparation of this news release and has reviewed and approved the scientific and technical information contained herein.

 

About GoldMining Inc.

 

GoldMining Inc. is a public mineral exploration company focused on acquiring and developing gold assets in the Americas. Through its disciplined acquisition strategy, GoldMining now controls a diversified portfolio of resource-stage gold and gold-copper projects in Canada, the U.S.A., Brazil, Colombia, and Peru.

 

For additional information, please contact:

 

Martin Dumont
VP, Corporate Development & Investor Relations

 

Telephone: (855) 630-1001

Email: info@goldmining.com

 

Notice to Readers

 

Disclosure regarding the Project, including the PEA and Mineral Resource Estimates included herein, has been prepared by the Company in accordance with NI 43-101. NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for public disclosure by issuer of scientific and technical information concerning mineral projects. NI 43-101 differs significantly from the disclosure requirements of the United States Securities and Exchange Commission ("SEC") generally applicable to U.S. companies subject to the SEC's disclosure requirements. For example, the terms "Indicated Mineral Resource" and "Inferred Mineral Resource" are defined in NI 43-101 by reference to the guidelines set out in the CIM Definition Standards on Mineral Resources and Mineral Reserves. Accordingly, information contained herein or in the Company's descriptions of its projects may not be comparable to similar information made public by U.S. companies reporting pursuant to SEC disclosure requirements.

 

Investors are cautioned not to assume that all or any part of "Measured" or "Indicated" Mineral Resource will ever be converted into "reserves". Investors should also understand that "Inferred Mineral Resources" have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. Under Canadian rules, estimated "Inferred Mineral Resources" may not form the basis of feasibility or pre-feasibility studies except in rare cases. 

 

For further information regarding the Company's projects and the resource estimates disclosed herein, please refer to the Company's most recent Annual Information Form and the technical reports filed under the Company's profile at www.sedarplus.ca and www.sec.gov.

 

 

 

 

logomed.jpg

 

Forward-Looking Statements

 

Certain of the information contained in this news release constitutes "forward-looking information" and "forward-looking statements" within the meaning of applicable Canadian and U.S. securities laws ("forward-looking statements"), which involve known and unknown risks, uncertainties and other factors that may cause the Companys actual results, performance and achievements to be materially different from the results, performance or achievements expressed or implied therein. Forward-looking statements, which are all statements other than statements of historical fact, include, but are not limited to the results of the PEA, the Companys plans and expectations regarding future opportunities and proposed work at the Project and the Companys other plans and expectations regarding the Project. Forward-looking statements are based on the then-current expectations, beliefs, assumptions, estimates and forecasts about the business and the markets in which GoldMining operates. Investors are cautioned that all forward-looking statements involve risks and uncertainties, including: the inherent risks involved in the exploration and development of mineral properties, fluctuating metal prices, unanticipated costs and expenses, risks related to government and environmental regulation, social, permitting and licensing matters, and uncertainties relating to the availability and costs of financing needed in the future. These risks, as well as others, including those set forth in GoldMinings Annual Information Form for the year ended November 30, 2025, and other filings with Canadian securities regulators and the SEC, could cause actual results and events to vary significantly. Accordingly, readers should not place undue reliance on forward-looking statements. There can be no assurance that forward-looking statements, or the material factors or assumptions used to develop such forward-looking statements, will prove to be accurate. The Company does not undertake to update any forward-looking statements, except in accordance with applicable securities law.

 

FAQ

What NPV and IRR did GoldMining Inc. (GLDG) report for the São Jorge PEA?

GoldMining reported an after-tax NPV 5% of $532.5 million and an after-tax IRR of 42.4% at a gold price of $3,500/oz. These figures summarize the modeled returns from the preliminary economic assessment for the São Jorge project.

What are the projected production and mine life for GoldMining’s São Jorge project?

The São Jorge PEA models a 10.6-year open-pit mine life with total gold production of 543.2 thousand ounces. Average annual production is 53.4 thousand ounces in years 1–5 and 51.2 thousand ounces over the life of mine.

What capital costs are estimated in GoldMining’s São Jorge PEA?

The São Jorge study estimates $202.2 million in initial capital expenditure, including pre-strip and a 25% contingency. Total capital, including $53.0 million sustaining and $12.0 million closure costs, is projected at $267.2 million over the project life.

What operating costs and AISC are modeled for the São Jorge project?

Life-of-mine operating costs are expected to average $34.88 per tonne of material processed. Total cash costs are modeled at $1,344 per ounce payable, with all-in sustaining costs (AISC) of $1,464 per ounce payable for the São Jorge project.

How sensitive is the São Jorge PEA to higher gold prices?

At a spot case gold price of $4,400/oz, the São Jorge PEA shows an after-tax NPV 5% of $836.8 million and an after-tax IRR of 58.6%. The modeled after-tax payback improves to 2.38 years under this higher price scenario.

Does the São Jorge PEA use Inferred Mineral Resources and what are the implications?

Yes, the PEA includes Inferred Mineral Resources, which the company notes are too speculative geologically to be classified as reserves. The disclosure emphasizes there is no certainty the PEA’s conceptual economics or resource figures will be realized in actual operations.

Filing Exhibits & Attachments

1 document