STOCK TITAN

i-80 Gold Corp. (NYSE: IAUX) widens Q2 loss while ramping Nevada mines and Lone Tree plant

(Moderate)
(Neutral)
Form Type
8-K

Rhea-AI Filing Summary

i-80 Gold Corp. reported second-quarter 2026 results highlighted by rapid project advancement but wider losses. Revenue was $24.3 million, down from $27.8 million a year earlier, driven by lower gold ounces sold as third-party processing delays limited Granite Creek sales, partly offset by a higher average realized gold price of $4,522/oz.

Gold production rose sharply to 11,098 oz from 4,178 oz, supporting management’s view that 2026 production guidance remains on track. Gross profit increased to $8.6 million from $0.8 million, but net loss widened to $52.5 million from $30.2 million as pre-development, evaluation and exploration expenses climbed to support Granite Creek, Archimedes, Mineral Point and Cove.

Operating cash outflow increased to $49.6 million, while cash and cash equivalents totaled $464.6 million at June 30, 2026. The Lone Tree Plant refurbishment, envisioned as a regional autoclave hub for three underground mines, progressed on schedule and on budget, with $110.1 million in construction commitments and approximately 30–40% of project capital committed by mid-July. Management reaffirmed 2026 guidance and a growth capex range of $150–$175 million, with some mix shifts among Lone Tree, Archimedes and exploration.

Positive

  • Gold production increased to 11,098 oz from 4,178 oz year-over-year, indicating strong ramp-up at Granite Creek and supporting management’s confidence in meeting full-year production guidance.
  • Gross profit rose to $8.6 million from $0.8 million, driven largely by a higher average realized gold price of $4,522/oz, improving operating leverage despite lower revenue.
  • The Lone Tree autoclave refurbishment is advancing on schedule and on budget, with $110.1 million of construction commitments and about 40% of capital committed by mid-July, underpinning the planned hub-and-spoke processing model.
  • Cash and cash equivalents stood at $464.6 million as of June 30, 2026, providing substantial liquidity to fund the multi-asset development plan.

Negative

  • Net loss widened to $52.5 million from $30.2 million, reflecting significantly higher pre-development, evaluation and exploration expenses as multiple projects advance.
  • Cash used in operating activities increased to $49.6 million from $11.3 million, indicating a materially higher cash burn associated with project ramp-up and working capital needs.
  • Revenue declined to $24.3 million from $27.8 million, as gold ounces sold fell to 5,335 from 8,400 due to third-party processing delays at Granite Creek.
  • The Company reported a higher adjusted net loss of $41.2 million versus $26.5 million, even after excluding fair value and other non-core items, showing greater underlying operating and development costs.

Filing Explained

Project milestones remain conditional; June 30 cash equaled 843.2 days of that quarter’s operating cash use, while Lone Tree permits remain pending.

This Form 8-K reports the quarter ended June 30, 2026 and leaves the development plan in a pre-completion state: Archimedes first gold and Lone Tree major construction remain targeted for the fourth quarter, while permits for Lone Tree’s new design remain pending.

The Archimedes feasibility study is now anticipated around mid-2027 because drilling progressed slower than planned; Mineral Point drilling is expected to finish in the first quarter of 2027, with its pre-feasibility study around mid-2027.

For Lone Tree, the company reports $110.1 million of construction commitments as of June 30, 2026 and approximately 40% of capital committed by mid-July; these are committed project amounts, not completed construction.

At Granite Creek, the filing reports more than 5,300 recoverable ounces at a third-party processor and approximately 1,800 ounces in inventory at June 30, 2026, with the processed material expected to be handled during the third quarter.

The specified resolution points are approval of the remaining Lone Tree permits, the Archimedes feasibility study around mid-2027, and completion of the Mineral Point drilling program in the first quarter of 2027.

Sources and calculations
  • Cash and equivalents vs quarterly operating cash outflow, in days of cash use $464,555,000 / ($49,584,000 / 90) = [object Object]
Item 2.02 Results of Operations and Financial Condition Financial
Disclosure of earnings results, typically an earnings press release or preliminary financials.
Item 9.01 Financial Statements and Exhibits Exhibits
Financial statements, pro forma financial information, and exhibit attachments filed with this report.
Revenue Q2 2026 $24,348,000 Three months ended June 30, 2026
Gross profit Q2 2026 $8,618,000 Three months ended June 30, 2026
Net loss Q2 2026 $(52,527,000) Three months ended June 30, 2026
Cash used in operating activities Q2 2026 $(49,584,000) Three months ended June 30, 2026
Cash and cash equivalents $464,555,000 As of June 30, 2026
Gold produced Q2 2026 11,098 oz Three months ended June 30, 2026
Average realized gold price Q2 2026 $4,522/oz Consolidated, three months ended June 30, 2026
Lone Tree construction commitments $110,100,000 Total construction commitments as of June 30, 2026
toll milling agreement financial
"sulfide mineralized material is processed at a third-party processing facility and subject to a toll milling agreement"
A toll milling agreement is a contract where one company pays a processor to grind, mill or otherwise transform its raw materials into finished or semi‑finished products while the material owner keeps legal title and pays a fee for the service. For investors it matters because it lets a business avoid buying expensive production plants, affecting costs, margins, supply‑chain risk and operational flexibility—like renting a specialized workshop instead of owning it.
autoclave processing plant technical
"i-80 Gold is one of two gold companies in Nevada with an autoclave processing plant"
pre-feasibility study financial
"Mineral Point Open Pit) (Pre-Feasibility) — approximately mid-2027"
A pre-feasibility study is an initial assessment that evaluates whether a proposed project or investment idea is worth exploring further. It involves examining basic factors like costs, potential benefits, and possible challenges, similar to conducting a preliminary check before deciding to invest more time and resources. This helps investors determine if pursuing the project further is practical and likely to be successful.
Environmental Impact Statement regulatory
"the project may require preparation of an Environmental Impact Statement ("EIS") under the Bureau of Land Management"
An environmental impact statement is a formal report that evaluates the likely effects a proposed project or plan will have on air, water, land, wildlife and local communities; it lays out potential harms, proposed mitigation measures, and alternatives. Think of it as a project’s environmental report card and repair plan: regulators use it to decide permits, and investors use it to assess delays, extra costs, legal risks and reputation exposure tied to environmentally sensitive issues.
Net Smelter Return royalty financial
"Royalties exclude Net Smelter Return royalty payments"
A net smelter return (NSR) royalty is a contractual right to receive a percentage of the revenue from minerals sold after they are processed and refined, with common deductions for transportation and refining fees. Investors care because an NSR provides a predictable slice of mining project income without owning the mine, so it affects expected cash flow, risk exposure to commodity prices, and the valuation of both the royalty and the operating project—similar to collecting a portion of rent after paying building maintenance costs.
Adjusted net loss financial
"Adjusted net loss and adjusted net loss per share exclude a number of temporary or one-time items"
Adjusted net loss is the company’s reported net loss after removing one-time, non-cash, or unusual items that management says obscure underlying results, such as restructuring charges, asset write-downs, or stock-based pay. Investors use it to focus on the business’s core profitability — like smoothing out potholes to judge road quality — but should be cautious because choices about what to exclude can make performance look better than it really is.
Revenue Q2 2026 $24,348,000 Down from $27,836,000 in Q2 2025 due to lower gold sold.
Net loss Q2 2026 $(52,527,000) Increased from $(30,215,000) in Q2 2025 on higher development and exploration costs.
Adjusted net loss Q2 2026 $(41,164,000) Higher than $(26,509,000) in Q2 2025 after normalizing for fair value and other items.
Gold produced Q2 2026 11,098 oz Up from 4,178 oz in Q2 2025 as Granite Creek ramped up.
Average realized gold price Q2 2026 $4,522/oz Increased from $3,301/oz in Q2 2025.
Guidance

Company states it remains on track to meet its 2026 production and cost guidance, with growth capital expected largely in line with $150–$175 million.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google
Learn about SEC filing dates

FAQ

How did i-80 Gold (IAUX) perform financially in Q2 2026?

i-80 Gold reported Q2 2026 revenue of $24.3 million and a net loss of $52.5 million. Revenue fell year-over-year as fewer ounces were sold, while higher development and exploration spending widened the loss despite stronger gross profit.

What were i-80 Gold’s (IAUX) Q2 2026 gold production and sales?

In Q2 2026, i-80 Gold produced 11,098 ounces of gold and sold 5,335 ounces at an average realized price of $4,522 per ounce. Production increased significantly, but sales were constrained by third-party processing availability.

Is i-80 Gold (IAUX) still on track to meet its 2026 guidance?

Management stated the Company remains on track to meet 2026 guidance from its 2025 Annual Report. Growth capital is expected to be largely in line with the $150–$175 million range, with some mix shifts between Lone Tree, Archimedes and exploration.

What progress did i-80 Gold (IAUX) make on the Lone Tree Plant in Q2 2026?

The Lone Tree Plant refurbishment advanced on schedule and on budget, with $110.1 million in construction commitments and about 30% of project cost committed by June 30, 2026. Major construction is expected to begin in the fourth quarter of 2026.

How much cash does i-80 Gold (IAUX) have and what was Q2 2026 cash burn?

As of June 30, 2026, i-80 Gold held $464.6 million in cash and cash equivalents. During Q2 2026, cash used in operating activities was $49.6 million, reflecting higher working capital needs and increased project-related expenses.

What were i-80 Gold’s (IAUX) key non-GAAP results for Q2 2026?

i-80 Gold reported an adjusted net loss of $41.2 million, or $0.05 per share, for Q2 2026. Adjustments primarily removed fair value measurement impacts, loan-related items and other non-operating gains and losses from the reported net loss.

Which development milestones is i-80 Gold (IAUX) targeting over the next 18 months?

Key targets include first gold mined at Archimedes in Q4 2026, commencement of Lone Tree construction in Q4 2026, feasibility studies for Granite Creek and Cove in Q3 2026, and Archimedes and Mineral Point studies around mid-2027.
0001853962FALSE00018539622026-08-102026-08-10

UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
_______________________________
FORM 8-K
_______________________________
CURRENT REPORT
Pursuant to Section 13 or 15(d) of the
Securities Exchange Act of 1934
Date of Report (Date of earliest event reported): August 10, 2026
i-80 GOLD CORP.
(Exact name of registrant as specified in its charter)
British Columbia001-41382
98-1591259
(State or other jurisdiction of
incorporation)
(Commission
File Number)
(IRS Employer
Identification No.)
150 York Street, Suite 1802
Toronto, Ontario
Canada M5H 3S5
5190 Neil Road, Suite 460
Reno, Nevada
USA 89502
(Address of principal executive offices)
Registrant’s telephone number, including area code: (775) 525-6450
Not Applicable
(Former name or former address, if changed since last report)
_______________________________
Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions (see General Instruction A.2. below):
oWritten communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)
oSoliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)
oPre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))
oPre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))
Securities registered pursuant to Section 12(b) of the Act:
Title of each classTrading Symbol(s)Name of each exchange on which registered
Common SharesIAUXNYSE American LLC
Warrants to Purchase Common SharesIAUX.WSNYSE American LLC
Common SharesIAUThe Toronto Stock Exchange
Warrants to Purchase Common SharesIAU.WT.UThe Toronto Stock Exchange
Indicate by check mark whether the registrant is an emerging growth company as defined in Rule 405 of the Securities Act of 1933 (§230.405 of this chapter) or Rule 12b-2 of the Securities Exchange Act of 1934 (§240.12b-2 of this chapter).
Emerging growth company
If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act.



Item 2.02. Results of Operations and Financial Condition
On August 10, 2026, i-80 Gold Corp. issued a press release announcing its financial results for the quarter ended June 30, 2026. A copy of the press release is attached as Exhibit 99.1 to this Current Report on Form 8-K and is incorporated herein by reference. The press release shall be deemed furnished, not filed, for purposes of this Current Report on Form 8-K.
Item 9.01    Financial Statements and Exhibits.
(d) Exhibits
Exhibit No.Description
99.1
News Release, dated August 10, 2026, reporting second quarter 2026 results
104Cover Page Interactive Data File (embedded within the Inline XBRL document).



SIGNATURES
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned hereunto duly authorized.
Date: August 10, 2026
i-80 GOLD CORP.
By:/s/ Ryan Snow
Name:Ryan Snow
Title:Chief Financial Officer

imagea.jpg




i-80 Gold Reports Second Quarter 2026 Results;
On Track to Achieve Full-Year Guidance as Granite Creek Ramps Up and Development Plan Advances

TORONTO, ON, August 10, 2026 – i-80 GOLD CORP. (NYSE:IAUX) (TSX:IAU) (“i-80 Gold” or the “Company”) reports its financial and operating results, as well as development highlights, for the three and six months ended June 30, 2026.

“We delivered another solid quarter, with increased production from Granite Creek as the project continued to ramp up on plan, the advancement of Archimedes on schedule toward becoming our second underground mine, and the start of demolition at the Lone Tree Plant,” stated Richard Young, President & CEO. “Additionally, Archimedes drilling results released during the quarter demonstrated the vast exploration potential and the ability to extend its mine life. Our success year-to-date demonstrates the Company’s ability to advance multiple projects concurrently. We remain on track to commence gold mining at Archimedes and major construction at Lone Tree in the fourth quarter of this year, marking two important milestones by year-end as we execute our development plan to build a Nevada-focused mid-tier gold producer.”

SECOND QUARTER HIGHLIGHTS
Three months ended June 30, 2026 compared to three months ended June 30, 2025.
Unless otherwise stated, all amounts referred to herein are in U.S. dollars
.

Development
Granite Creek underground development continued ahead of plan increasing access to high-grade headings supporting the ongoing ramp up. The project remains on track to achieve its full-year production guidance, with a published feasibility study anticipated in the third quarter of 2026.

Archimedes underground advanced on schedule and largely on budget with the main decline development on track, advancement of the exploration drift, which has since been completed, and commencement of the ventilation raise in preparation for first gold mined by year-end.

Lone Tree Plant refurbishment advanced on schedule and on budget as early works and pre-construction readiness activities continued during the quarter, and the commencement of demolition mid-June ahead of major construction. Procurement activities remain on schedule, with approximately 50% of procurement packages, by value, awarded as of mid-July. Project capital remains on budget with minimal contingency drawdown and approximately 40% of capital committed as of mid-July.

Completed approximately 19,000 meters of drilling across three projects, including infill drilling at Archimedes underground and Mineral Point open pit in support of planned 2027 technical studies for both projects, as well as resource definition drilling at Granite Creek underground beyond the area covered by the upcoming feasibility study.

Permitting largely on track across the development plan as permitting actions continued to advance across the portfolio.
1 of 12

igc-logoxgolda.jpg
Financial and Operating

Revenues were $24.3 million, representing 5,335 ounces in gold sold(2) at an average realized gold price(1) of $4,522 per ounce, compared to $27.8 million represented by 8,400 ounces at an average realized gold price(1) of $3,301 per ounce in the prior year period. The decrease in revenues was primarily driven by lower gold sold at Granite Creek as a result of delays at the third-party processing facility, partially offset by a higher average realized gold price(1). Revenues in the prior year quarter were higher due to the finalization of the third-party toll processing agreement in March 2025 and the processing of a higher volume of stockpile material.

Gold production increased to 11,098 ounces from 4,178 ounces in the prior year period. The Company remains on track to achieve its full year production guidance range.
Gross profit increased to $8.6 million from $0.8 million in the prior year period due to a higher realized gold price.

Net loss increased to $52.5 million compared to $30.2 million in the prior year period, due primarily to higher pre-development, evaluation and exploration costs incurred as the Company advances multiple projects within its development plan. The higher costs were related to drilling programs at the Ruby Hill property. Upon declaration of mineral reserves, certain pre-development, evaluation and exploration expenditures that are currently expensed will be capitalized.

Net loss per share increased to $0.06 compared to a $0.05 loss in the prior year period, primarily due to a higher net loss, partially offset by an increase in the weighted average number of common shares outstanding following the equity financing in May 2025.

Adjusted net loss(1) increased to $41.2 million compared to $26.5 million in the prior year period due to increased spending on pre-development, evaluation and exploration expenses, partially offset by higher gross profit.

Cash used in operating activities increased to $49.6 million compared to $11.3 million in the prior year period as a result of comparative working capital changes of $20.9 million primarily as a result of increased inventory due to third-party processing availability and higher pre-development, evaluation and exploration expenses which was partially offset by higher gross profit.
Cash and cash equivalents were $464.6 million as of June 30, 2026, a decrease of $49.0 million compared to March 31, 2026, primarily due to cash used in operations of $49.6 million, capital expenditures of $21.5 million primarily driven by the start of the Lone Tree Plant refurbishment project partially offset by a release of restricted cash of $16.9 million and proceeds from warrant exercises.

Sustainability

Advanced community engagement across Northern Nevada by progressing community development, workforce development, and grant funding initiatives, including a joint $300,000 donation with Franco-Nevada Corporation to support development of the first licensed childcare facility in Eureka County, neighboring the Company's Ruby Hill property.
Strengthened Board with the appointment of Stephen Gottesfeld at the annual general meeting, bringing nearly 30 years of global mining experience in environmental, sustainability, legal and governance matters across the mine lifecycle.
2

igc-logoxgolda.jpg
UPCOMING CATALYSTS
Over the next 18 months, the Company is targeting the following key catalysts while continuing to identify opportunities to optimize the development schedule:

Archimedes Underground
First gold mined — Q4 2026
Lone Tree Plant
Commence construction — Q4 2026
Completion of detailed engineering — late Q1 2027
Filtration plant completion — early Q4 2027
First gold pour — Q4 2027

Technical Studies
Granite Creek underground (Feasibility) — Q3 2026
Cove underground (Feasibility) — Q3 2026
Archimedes Underground (Feasibility) — approximately mid-2027
Mineral Point Open Pit) (Pre-Feasibility) — approximately mid-2027
Granite Creek open pit (Pre-Feasibility) — timing under review

OUTLOOK

The Company remains on track to meet its 2026 guidance as originally published in its 2025 Year End Annual Report on Form 10-K on February 19, 2026 subject to the following:
Growth capital expenditures are expected to be largely in line with the $150 million to $175 million guidance.
Lone Tree plant refurbishment capital expenditures are expected to be lower in 2026 than guided, management was conservative in estimating expenditures for Lone Tree during the recapitalization planning process earlier in year to ensure that the Company raised sufficient capital.
Archimedes expenditures are expected to be higher reflecting a change in strategy for long-term surface infrastructure. Based on positive drill results, management is pivoting from refurbishment of certain existing facilities on site to construction of a new worker change facility and additional offices that are expected to improve operating effectiveness both for Archimedes and Mineral Point.
Exploration expenses are expected to be approximately $10 million lower in 2026 due to the personnel shortages at the Archimedes project and drill rig availability as well as contractor personnel shortages at Mineral Point project.
This outlook, including expected results and targets, is subject to various risks, uncertainties and assumptions, which may impact future performance and the Company’s ability to achieve the results and targets discussed in this section. Please refer to "Forward-Looking Information" section. The Company may, but is under no obligation to, update this outlook depending on changes in metal prices and other factors.
3

igc-logoxgolda.jpg

SUMMARY OF FINANCIAL AND OPERATING RESULTS
Three months ended
June 30,
Six months ended
June 30,
2026202520262025
Revenue$000s24,348 27,836 76,738 41,884 
Gross profit
$000s8,618 798 24,697 3,704 
Net loss
$000s(52,527)(30,215)(131,128)(71,420)
Net loss per share$/share(0.06)(0.05)(0.15)(0.14)
Adjusted net loss
$000s(41,164)(26,509)(69,889)(50,105)
Adjusted net loss per share1
$/share(0.05)(0.04)(0.08)(0.10)
Cash used in operating activities$000s(49,584)(11,335)(94,664)(34,036)
Cash and cash equivalents$000s464,555 133,691 464,555 133,691 
Gold producedoz11,098 4,178 21,964 14,326 
Gold ounces sold2
oz5,335 8,400 15,923 13,352 
Average realized gold price1
$/oz4,522 3,301 4,801 3,124 
Pre-development, evaluation and exploration expenses$000s29,264 9,045 54,962 18,590 
Notes to table above:
1This is a Non-GAAP Measure; please see “Non-GAAP and Supplementary Financial Performance Measures” section.
2Gold ounces sold include attributable gold from mineralized material sales at a payable factor of 56% in 2026 (2025 - 59%).

4

igc-logoxgolda.jpg
Granite Creek Property
The Granite Creek property includes the Granite Creek underground project, a fully permitted, constructed and operating mine, and the Granite Creek open pit oxide deposit adjacent to the underground project. Granite Creek underground is the Company's first brownfield project to be redeveloped and is currently ramping up towards steady-state gold output.
Granite Creek PropertyThree months ended
June 30,
Six months ended
June 30,
Operational Statistics2026202520262025
Mining
Oxide mineralized material minedtonnes12,039 24,074 23,752 39,397 
Sulfide mineralized material minedtonnes13,568 11,201 33,282 25,844 
Low-grade mineralized material minedtonnes9,338 16,173 22,375 39,019 
Waste minedtonnes37,405 31,947 77,762 59,409 
Total material minedtonnes72,350 83,395 157,171 163,669 
Oxide mineralized material gradeg/t7.44 11.38 8.14 11.74 
Sulfide mineralized material gradeg/t6.49 7.43 6.29 7.93 
Low-grade mineralized material gradeg/t3.13 3.03 2.97 2.88 
Processing
Processed mineralized material - sulfidetonnes9,055 7,014 35,460 7,014 
Processed mineralized material - heap leachtonnes 18,750 5,827 52,587 
Total processed mineralized material tonnes9,055 25,764 41,287 59,601 
Ore purchase agreement (high and low grade oxide)
Oxide mineralized material sold1
tonnes15,505 16,317 32,681 28,798 
Total gold producedoz8,634 1,941 17,532 9,392 
Total gold sold1
oz2,052 5,981 10,818 9,086 
Underground mine development (pre-development)meters360 211 747 365 
Drillingmeters1,211 586 3,135 586 
Financial Statistics2026202520262025
Mining cost (total mineralized material and waste)$/t178 175 169 173 
Processing cost (processed mineralized material)$/t325 133 293 74 
Site general and administrative (“G&A”) (total mineralized material mined)$/t57 34 50 32 
Operating costs2
$000s
7,106
22,067
37,835
30,386
Royalties2
$000s517 1,148 3,119 1,654 
Sustaining capital expenditures3
$000s1,672 778 4,268 201 
Growth capital expenditures3
$000s7,234 336 9,445 1,290 
Capital expenditures$000s8,906 1,114 13,713 1,491 
Pre-development, evaluation and exploration expenses
$000s7,882 5,949 19,278 9,719 
Notes to table above:
1Gold ounces sold include attributable gold from mineralized material sales at a payable factor of 56% in 2026 (2025 - 59%).
2Operating costs excluding depletion, depreciation, amortization, and royalties. Royalties exclude NSR royalty payments.
3This is a Non-GAAP and Supplementary Financial measure; please see “Non-GAAP and Supplementary Financial Performance Measures” section.
5

igc-logoxgolda.jpg

Granite Creek Underground
Mining & Processing
Mineralized material mined at Granite Creek underground is processed as follows: (i) sulfide mineralized material is processed at a third-party processing facility and subject to a toll milling agreement entered into in March 2025, (ii) high-grade and low-grade oxide mineralized material is subject to an ore sales agreement. Low-grade oxide mineralized material was sold under the ore purchase beginning in the first quarter of 2026, and (iii) residual leaching of low-grade oxide material previously placed on a segregated section of the Company’s Lone Tree heap leach facility continues with no additional mineralized material being placed after the first quarter of 2026.

During the quarter, mining activities at Granite Creek were impacted by ground conditions in two of the mine highest-grade headings, which temporarily restricted access to high-grade mineralized material and deferred a portion of planned high-grade tonnes during the quarter. Remediation of the affected headings was completed and access was re-established late in the quarter, allowing these areas to contribute to production beginning in the third quarter.

Throughout the quarter, advancement of the main decline as well as horizontal development continued to progress ahead of the mine plan, with year-to-date development footage exceeding plan. As a result, the number of available high grade mineralized material headings has increased significantly throughout the quarter. The Company remains on track to meet its full-year production guidance.

Water inflow volumes to the mine remained largely unchanged and continue to be managed well using the current underground pumping system, which presently operates near capacity. Work on an enhanced pumping system, that includes expanded sumps at lower levels and higher-capacity pumps, advanced during the quarter. Pumps were sized and ordered with installation continuing throughout the remainder of the year to increase overall water discharge capacity as the mine progresses at depth. Further, initial phases of commissioning a second water treatment plant began in late July, with mechanical completion having recently been completed. The second water treatment plant will increase surface water treatment capacity to approximately 3,500 gallons per minute to support the Company's long-term groundwater management objectives.

At June 30, 2026, the Company had in-process material containing over 5,300 recoverable ounces at its third-party processing facility. The Company expects the material to be processed during the third quarter of 2026. Approximately 1,800 ounces of gold was also held in inventory at June 30, 2026. Gold ounces sold were lower than the prior year periods due to availability at the third-party processing facility.

Processing cost per unit has increased compared to the prior year periods due to a higher proportion of sulfide material being processed at the third-party processing facility.

During the three months ended and six months ended June 30, 2026, growth capital expenditures were primarily related to the water treatment plant project. Sustaining capital expenditures were related primarily to the electrical substation replacement.

Pre-development, evaluation, and exploration expenses were $7.9 million for the three months ended June 30, 2026, which were related to underground mine development and infill drilling to upgrade mineral resources and step-out drilling.

6

igc-logoxgolda.jpg
Drill Program
During the quarter, the Company continued infill and step-out drilling at Granite Creek. The underground drill program remained focused on infill drilling to support resource conversion and mine planning. Drilling progressed slower than anticipated during the quarter due to water management, maintenance downtime, and rig relocation. The updated mineral resource estimate is near completion and under internal review. The feasibility study is now expected to be completed in the third quarter of 2026.

Granite Creek Open Pit
Preparation for a pre-feasibility trade-off study has commenced following the completion of the Granite Creek open pit preliminary economic assessment, prepared in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects (“NI 43-101”) and the corresponding Initial Assessment prepared under Subpart 1300 of Regulation S-K (“S-K 1300”), each filed on March 31, 2025 (“PEA”). Simultaneously, technical trade-off analyses are being conducted to optimize project economics. Based on preliminary assessments of potential environmental impacts, the project may require preparation of an Environmental Impact Statement ("EIS") under the Bureau of Land Management ("BLM") process. Early-stage pre-permitting activities and technical studies are currently underway, followed by planned baseline field studies commencing in 2027 to support the National Environmental Policy Act ("NEPA") permitting process.

Ruby Hill Property
The Ruby Hill property includes the Archimedes underground project, the Company's second planned underground mine for which construction began during 2025, and Mineral Point open pit, which is a large oxide gold and silver deposit with the potential to become the Company’s largest gold producing asset.

 Ruby Hill PropertyThree months ended
June 30,
Six months ended
June 30,
Operational Statistics2026202520262025
Heap Leach
Gold producedoz485 713 878 1,336 
Gold soldoz690 665 1,073 1,117 
Underground mine development (pre-development)
meters899 — 1,559 — 
Archimedes drillingmeters3,124 — 7,386 — 
Mineral Point drillingmeters14,836 1,749 15,586 1,749 
Financial Statistics2026202520262025
Processing cost (produced oz)
$/oz3,124 1,640 3,228 1,644 
Site G&A (produced oz)
$/oz658 1,174 755 1,191 
Operating costs$000s
2,639
1,726
3,552
2,808
Royalties1
$000s92 66 145 103 
Sustaining capital expenditures2
$000s152 719 469 911 
Growth capital expenditures2
$000s2,422  3,170  
Capital expenditures$000s2,574 719 3,639 911 
Pre-development, evaluation and exploration expenses
$000s20,083 1,898 32,466 5,089 
Notes to table above:
1 Royalties excludes Net Smelter Return royalty repayments
2This is a Non-GAAP and Supplementary Financial measure; please see “Non-GAAP and Supplementary Financial Performance Measures” section.

7

igc-logoxgolda.jpg
The Company continues to leach the historic leach pads on the Ruby Hill property, recovering gold. Year-to-date gold production from the historic leach pad remained below expectation as infiltration on the pad remained challenging. Higher processing cost per ounce compared to the prior year periods was due to lower produced ounces. For the residual leaching process, management continues to focus on managing ponding, maximizing the area under leach, and optimizing cyanide application rates.

Archimedes Underground
During the quarter, underground development at the Archimedes project continued to advance on schedule, with 899 meters of development completed during the quarter, supported by favorable ground conditions and high productivity rates from contractors. Pump testing was conducted on a recently completed dewatering well, and permitting activities for below the 5,100-foot level continued to advance as planned. The planned start of mining above the 5,100-foot level is fully supported by existing permits and is not dependent on the timing or outcome of permitting activities below the 5,100-foot level. The Company continues to expect to achieve first gold from Archimedes in the fourth quarter of 2026.

Growth capital expenditures for the three and six months ended June 30, 2026 were primarily related to heavy mobile equipment, infrastructure upgrades, power upgrades and mine load centers for the underground.

Pre-development, evaluation and exploration expenditures were $20.1 million and $32.5 million for the three and six months ended June 30, 2026. $20.1 million and $32.5 million for the three and six months ended June 30, 2026. Pre-development, evaluation and exploration expenditure were higher than the prior year periods primarily due to underground development at the Archimedes underground project which began in the third quarter of 2025. Development during the quarter focused on completion of the exploration drift to establish drilling platforms to access the ongoing definition drilling program for the Ruby Deeps zones at depth. Further development included commencement of the first ventilation raise.

Drilling activities during the quarter included the completion of the 2025-2026 program in the upper 426 zone and commencement of the 2026 infill drill program with 3,124 meters of infill drilling completed in the lower 426 and Ruby Deeps zones in support of a feasibility study. The latest assay results from the 2025-2026 drill program were published during the second quarter in a press release dated June 25, 2026. The results continued to confirm high-grade mineralization, demonstrate continuity within the planned mining areas, and extend mineralization beyond the boundaries of the current mineral resource estimate supporting the 2025 PEA. Drilling also continued to intersect significant intervals of oxide mineralization not included in the current mineral resource estimate.

An infill drilling program largely within the lower portion of the 426 zone and Ruby Deeps zone commenced in the second quarter of 2026, targeting approximately 55,000 meters planned across 140 drill holes in support of the planned Archimedes Feasibility Study. The drill program is encountering slower than planned progress due to contractor staffing availability. As a result, the Archimedes feasibility study is now anticipated to be completed approximately mid-year 2027.

Mineral Point Open Pit

At Mineral Point open pit, the Company advanced its surface drill program during the quarter as part of the largest 12-month drill program in the Company's history, completing approximately 14,836 meters of core drilling and reverse circulation drilling with a fleet of up to five drill rigs, primarily for infill drilling of the currently classified inferred resources. The drill program encountered slower than planned progress due to drill rig and contractor staffing availability, as well as slower penetration rates than expected in the sanded dolomite unit. Management expects to increase the overall drilling rate for the remainder of the year with mobilization of additional rigs, however, completion of the drill program is now expected in the first quarter of 2027. The results from this program will support a pre-feasibility study, which is expected at approximately mid-year 2027, pending timing of the drilling program. Early-stage pre-permitting activities continued to progress during the quarter.
8

igc-logoxgolda.jpg

Cove Underground

Cove is an advanced stage exploration project and is expected to be the Company's third underground mine. During the second quarter, the Company continued to advance technical and economic studies for the Cove Underground project. Various baseline studies and agency comment responses were submitted to the BLM. In addition, water pollution control permit renewal and modification applications were submitted to NDEP—BMRR for the underground mine and rapid infiltration basins. Additional federal and state permitting actions continue to progress. A feasibility study for Cove is expected to be completed in the third quarter of 2026.
Lone Tree Plant Refurbishment
The Lone Tree Plant (the "Plant") is currently undergoing refurbishment following a positive construction decision in the first quarter of 2026. i-80 Gold is one of two gold companies in Nevada with an autoclave processing plant (the other being owned by Nevada Gold Mines Inc., a joint venture between Barrick Mining Corporation and Newmont Corporation).

The Plant is envisioned to process material from the Company’s three underground mines, Granite Creek, Archimedes, and in the future Cove, to establish a regional hub-and-spoke mining and processing model. Upon refurbishment and commissioning, the Plant will allow the Company to transition from toll milling to owner-operated processing. This shift is expected to materially increase operating margins and enhance free cash flow generation.

During the quarter, detailed engineering and procurement advanced with the Company's contractor, with procurement package preparation and long-lead item ordering a key focus. Cleaning and environmental testing of the existing tanks, containment, and piping was completed, and demolition of existing infrastructure commenced during the quarter. The Company also progressed the tailings storage facility and new filtered tailings design work. The refurbishment timing remains on track with the engineering study timeline and scope of work. Early works and pre-construction readiness activities are well underway on site and continue to advance on schedule ahead of major construction, which is expected to commence in the fourth quarter of 2026. Second and third quarter pre-construction activities include mobilization of the EPCM contractor to site, commencement of demolition of the existing plant components requiring replacement as part of the refurbishment and advancement of detailed engineering, procurement packages, and the award of key contracts.

The Lone Tree Plant is permitted for the existing operational components in use. The approval of new and revised permit applications pertaining to air quality, mercury control, water pollution control, reclamation management, and other secondary programs for the new design remain outstanding. The Company submitted the necessary applications for air quality, mercury control and water quality environmental permits in the first quarter of 2026, as planned, with several permits received to date and further permits pending. Various construction activities are scheduled to commence in the second half of 2026 upon the anticipated approval of the associated permits, with major construction activities anticipated to commence in the fourth quarter of 2026.The permitting process is currently on track and aligns with the construction schedule.

Capital expenditures for the three months and six months ended June 30, 2026 were primarily related to the refurbishment of the Lone Tree Plant. The project spend is weighted in the second half of the year and the Company expects to meet full-year guidance.

As of June 30, 2026, total construction commitments were $110.1 million with approximately 30% of the project cost committed. Subsequent to the quarter, procurement activities remain on schedule, with approximately 50% of procurement packages, by value, awarded as of mid-July. Project capital remains on budget with minimal contingency drawdown and approximately 40% of capital committed as of mid-July.



9

igc-logoxgolda.jpg
FINANCIAL STATEMENTS
This press release should be read in conjunction with i-80 Gold’s Form 10-Q, including the unaudited consolidated financial statements and associated Management's Discussion and Analysis of Financial Condition and Results of Operation for the three and six months ended June 30, 2026 included therein, which is available on the Company’s website at www.i80gold.com, and under the Company's issuer profile on EDGAR at www.sec.gov and SEDAR+ at www.sedarplus.ca.

CONFERENCE CALL AND WEBCAST
Management will hold a conference call and audio webcast to discuss the second quarter highlights followed by a question-and-answer session with participants. The details are as follows:
Date:                Tuesday, August 11, 2026
Time:                10:00 a.m. ET
Webcast:             https://app.webinar.net/q0A61kDYpP2
Telephone:             1-416-945-7677
Toll-free (North America):     1-888-699-1199

TECHNICAL DISCLOSURE AND QUALIFIED PERSONS
All scientific and technical information contained in this press release has been reviewed, verified and compiled under the supervision of Paul Chawrun, P.Eng., member of the Professional Engineers of Ontario (PEO) and the Company’s Executive Vice President & Chief Operating Officer, and Tyler Hill, CPG., Vice President Geology for the Company, each of whom is a “Qualified Person” within the meaning of National Instrument 43-101 – Standards of Disclosure for Mineral Projects and S-K 1300 and Subpart 1300 of Regulation S-K under the U.S. Securities Act of 1933, as amended. Mr. Chawrun and Mr. Hill have verified the scientific and technical information disclosed in this press release.

ENDNOTES
(1)This is a Non-GAAP and Supplementary Financial measure; please see “Non-GAAP and Supplementary Financial Performance Measures” section.
(2) Gold ounces sold include attributable gold from mineralized material sales at a payable factor of 56% in 2026 (2025 - 59%).

ABOUT i-80 GOLD CORP.
i-80 Gold Corp. is a Nevada-focused mining company committed to building a mid-tier gold producer through a fully funded three-phase development plan to advance its high-quality asset portfolio. The Company is one of the largest mineral resource holders in the state with a pipeline of three high-grade underground and two open pit projects strategically located in some of Nevada’s most prolific gold-producing trends. Leveraging its central autoclave processing facility following an anticipated refurbishment, i-80 Gold is executing a hub-and-spoke regional mining and processing strategy to maximize efficiency and growth. i-80 Gold’s shares are listed on the NYSE (NYSE: IAUX) and Toronto Stock Exchange (TSX: IAU). Visit www.i80gold.com for more information.

For further information, please contact:
Leily Omoumi - SVP Corporate Development and Strategy
Caterina De Rosa - VP Investor Relations
1.866.525.6450
info@i80gold.com

10

igc-logoxgolda.jpg
CAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION
Certain information set forth in this press release, including but not limited to management's assessment of the Company's future plans and operations; the anticipated timing of the permitting, construction, refurbishment and commissioning of the Lone Tree Plant; the anticipated benefits of the refurbished Lone Tree Plant, including to cash margins, recoveries, operating margins and free cash flow generation, and the anticipated transition from toll milling to owner-operated processing; the perceived merit of projects or deposits; the impact, timing, and execution of the Company’s three-phase development plan, the anticipated timing of permitting, gold output, project development, or completion dates for feasibility studies, technical studies; execution and timing of all asset advancements in the development plan; the potential to utilize the autoclave infrastructure at the Lone Tree Plant to process mineralized material pending the outcome of the refurbishment; that Mineral Point will become the Company’s largest gold producing asset; the successful permitting of each project; the timing, completion and results of the Company’s drill programs; the inclusion of drill results in future feasibility studies and the expected conversion of mineral resources to higher confidence categories or to mineral reserves; that any of the projects will reach commercial production; the Company’s ability to achieve mid-tier producer status; outlook on gold output; the Company's 2026 production, operating, pre-development, evaluation and exploration cost guidance; the anticipated timing for water treatment plant completion at Granite Creek and the outcome of the dewatering program; the anticipated commissioning of the Lone Tree Plant by the end of 2027; the expected timing of first gold mined from Archimedes; the anticipated implementation of a hub-and-spoke regional mining and processing model; and the Company’s expectation that it has sufficient liquidity to meet its obligations as they become due, constitute forward-looking statements or forward-looking information (collectively, “forward-looking statements”) within the meaning of applicable Canadian and United States securities laws.

All statements other than statements of historical fact are forward-looking statements. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "continues", "forecasts", "projects", "predicts", "intends", "anticipates”, “targets" or "believes", or variations of, or the negatives of, such words and phrases, or state that certain actions, events or results "may", "could", "would", "should", "might" or "will" be taken, occur or be achieved. Forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable by management as at the date of this press release, are inherently subject to significant business, economic and competitive uncertainties and contingencies. Material assumptions used in preparing the forward-looking statements in this press release include, but are not limited to, assumptions regarding: the price of gold and silver; the accuracy of the Company’s mineral resource estimates and the underlying geological, technical and economic parameters; anticipated costs and expenditures; the timely receipt of all required regulatory and governmental approvals and permits on acceptable terms; the availability of financing on acceptable terms; the availability of equipment, labor and contractors; the absence of significant labor disruptions or material adverse changes in general economic conditions; and the Company’s ability to execute its three-phase development plan on the anticipated timeline and within budget. Readers are cautioned that the foregoing assumptions, although considered reasonable at the time of preparation, may prove to be inaccurate and, as such, undue reliance should not be placed on forward-looking statements.

The Company's actual results, performance or achievement could differ materially from those expressed in, or implied by, these forward-looking statements and, accordingly, no assurance can be given that any of the events anticipated by the forward-looking statements will transpire or occur, or if any of them do so, what benefits, if any, that the Company will derive therefrom. By their nature, forward looking statements are subject to numerous risks and uncertainties, some of which are beyond the Company’s control, including: general economic and industry conditions; volatility of commodity prices, including the prices of gold and silver; title risks and uncertainties; the Company’s ability to access sufficient capital from internal and external sources, including by selling assets, restructuring debt or obtaining additional equity capital, on terms that may be onerous or highly dilutive; uncertainties related to the refurbishment of the Lone Tree Plant, including cost overruns and construction delays; risks related to third-party toll milling arrangements and processing delays; uncertainties regarding water management and groundwater inflows at Granite Creek; risks related to the conversion of mineral resources and the results of feasibility and other technical studies; risks associated with mineral exploration, development and mining operations generally; risks related to obtaining and maintaining required governmental, environmental and other regulatory approvals and permits, including under NEPA and the BLM process, on a timely basis or at all; environmental, health and safety risks; risks relating to the reliance on key personnel and contractors (including Hatch); changes in applicable laws, regulations or government policies in Canada and the United States; foreign exchange and interest rate fluctuations; litigation risks; and the other risk factors discussed under the heading “Risk Factors” in the Company’s Form 10-K for the fiscal year ended December 31, 2025 and the Company’s Form 10-Q for the three months ended June 30, 2026, each of which is available on EDGAR at www.sec.gov/edgar and on SEDAR+ at www.sedarplus.ca. Readers are encouraged to carefully review these risk factors as well as the Company’s other filings with the U.S. Securities and Exchange Commission and the Canadian Securities Administrators. All forward-looking statements contained in this press release speak only as of the date of this press release or as of the dates specified in such statements. The Company disclaims any intention or obligation to update or revise any forward-looking statements, whether as a result of new information, future events or otherwise, except as required by applicable law.

Additional information relating to i-80 Gold can be found on i-80 Gold’s website at www.i80gold.com, SEDAR+ at www.sedarplus.ca, and on EDGAR at www.sec.gov/edgar.

NON-GAAP AND SUPPLEMENTARY FINANCIAL PERFORMANCE MEASURES

The Company has included certain non-GAAP performance measures commonly used in the mining industry that are not defined under US GAAP in this document. These include adjusted net loss, adjusted net loss per share, and average realized price per ounce. These measures are not defined under US GAAP, and therefore, they may not be comparable to similar measures employed by other companies. Management believes these measures in addition to measures determined in accordance with US GAAP provide investors with useful information to evaluate the Company's underlying operations and financial performance. Supplementary financial measures represents a component of a GAAP number. The measures presented are intended to provide additional information and should not be considered in isolation or as a substitute for measures prepared in accordance with US GAAP and should be read in conjunction with the Company's Financial Statements.

Definitions

"Average realized gold price” per ounce of gold sold is a supplementary financial measure and the calculation is shown below.

"Adjusted net loss” and “adjusted net loss per share” are non-GAAP financial performance measures that the Company considers to better reflect normalized earnings because it eliminates temporary or non-recurring items such as: gain and losses on fair value measurements, loss on loan extinguishment, gain (loss) on Convertible Loans and finance fee expense. Adjusted net loss per share is calculated using the weighted average number of shares outstanding under the basic calculation of earnings per share.

"Sustaining capital expenditures" and "Growth capital expenditures" are supplementary financial measures. Sustaining capital expenditures are investments that support current operational and production levels whereas Growth capital expenditures are associated with major projects and new mine development.

11

igc-logoxgolda.jpg
Average realized gold price per ounce of gold sold(2)
Three months ended
June 30,
Six months ended
June 30,
(in thousands of U.S. dollars, unless otherwise noted)2026202520262025
Consolidated
Revenues24,348 27,836 76,738 41,884 
Silver revenue(224)(108)(288)(169)
Gold revenue24,124 27,728 76,450 41,715 
Gold sold¹
ounce5,335 8,400 15,923 13,352 
Average realized gold price ($/oz)$/ounce4,522 3,301 4,801 3,124 
Granite Creek
Revenues9,355 19,727 53,194 28,422 
Gold ounces sold1
ounce2,052 5,981 10,818 9,086 
Average realized gold price ($/oz)$/ounce4,559 3,298 4,917 3,128 
Lone Tree
Revenues11,891 5,821 18,777 9,784 
Silver revenue
(173)(22)(233)(36)
Gold revenue11,718 5,799 18,544 9,748 
Gold soldounce2,593 1,754 4,032 3,149 
Average realized gold price ($/oz)$/ounce4,519 3,306 4,599 3,096 
Ruby Hill
Revenues3,102 2,288 4,767 3,678 
Silver revenue(51)(86)(55)(133)
Gold revenue3,051 2,202 4,712 3,545 
Gold soldounce690 665 1,073 1,117 
Average realized gold price ($/oz)$/ounce4,422 3,311 4,391 3,174 
Note to table above:
1 Gold ounces sold include attributable gold from mineralized material sales at a payable factor of 56% in 2026 (2025 - 59%)

Adjusted net loss(2)

Adjusted net loss and adjusted net loss per share exclude a number of temporary or one-time items detailed in the following table:

Three months ended
June 30,
Six months ended
June 30,
(in thousands of U.S. dollars, unless otherwise noted)2026202520262025
Net loss
$(52,527)$(30,215)$(131,128)$(71,420)
Adjust for:
Loss on fair value measurement of Silver Purchase Agreement derivative
(9,290)(1,986)(36,092)(9,461)
Loss on fair value measurement of NSR Royalty
(24,039)— (31,663)— 
Finance fee expense — (9,796)— 
Loss on loan extinguishment (782)(7,110)(782)
Gain (loss) on fair value measurement of Convertible Loans derivative
 765 (3,463)(673)
Loss on fair value measurement of Orion Gold Prepay Agreement derivative
 (2,412)(3,377)(10,674)
Gain / (loss) on Offtake liability(4,800)— (4,800)— 
Gain on fair value measurement of 2026 Gold Prepay derivative
22,000 — 29,893 — 
Gain on fair value measurement of warrant liabilities
4,766 709 5,169 275 
Total adjustments$(11,363)$(3,706)$(61,239)$(21,315)
Adjusted net loss
(41,164)(26,509)(69,889)(50,105)
Weighted average shares 861,071,221 608,167,841 849,153,360 520,243,077 
Adjusted net loss per share
$(0.05)$(0.04)$(0.08)$(0.10)

12

Filing Exhibits & Attachments

4 documents