Integra Resources (ITRG) extends Florida Canyon mine life but lifts 2026 AISC guidance

Filing Impact
(Neutral)
Filing Sentiment
(Neutral)
Form Type
6-K

Rhea-AI Filing Summary

Integra Resources outlines an updated Technical Report for its Florida Canyon Mine in Nevada, extending active mining to 2033 with roughly eight years of mining and two years of residual leaching. The plan contemplates total ore mined of 116.9 Mt at an average grade of 0.31 g/t gold, containing 1,156 Koz.

Life-of-mine average gold recovery is 56.7%, yielding 656 Koz recoverable and 685 Koz sold, or about 81.8 Koz per year during mining years. Using gold price assumptions starting at $4,344/oz in 2026 and declining to $3,600/oz from 2030 to 2035, the project shows an after-tax NPV5% of $600.6M, average annual net free cash flow of $90.0M and total net free cash flow of $769.5M.

Life-of-mine site-level cash costs net of silver by-product are estimated at $1,940/oz, with site-level all-in sustaining costs excluding closure of $2,331/oz. Capital plans include sustaining capital and stripping of $267.4M and growth capital of $91.8M, largely for heap leach pad expansions and fleet modernization.

The company revises 2026 Florida Canyon site-level AISC guidance upward from $2,750–$2,950/oz to $3,300–$3,500/oz, citing higher tonnes mined and processed, lower Q1 2026 gold sales, increased royalties and excise taxes at stronger gold prices, and higher diesel and explosives costs, while maintaining 2026 production guidance of 70–75 Koz.

Positive

  • None.

Negative

  • 2026 cost guidance increased materially: Florida Canyon site-level AISC guidance rises from $2,750–$2,950/oz to $3,300–$3,500/oz, driven by higher tonnes mined and processed, lower Q1 2026 ounces sold, higher royalties and excise taxes from strong gold prices, and increased fuel and explosives costs.

Insights

Mine life and NPV rise, but cost guidance steps up notably.

The updated plan for Florida Canyon supports a longer operating life through 2033 and higher modeled cash flows. At assumed gold prices beginning at $4,344/oz in 2026, after-tax NPV5% is $600.6M with total net free cash flow of $769.5M.

However, life-of-mine site-level AISC of $2,331/oz and a revised 2026 AISC range of $3,300–$3,500/oz versus prior $2,750–$2,950/oz indicate a materially higher near-term cost structure. This reflects heavier stripping, more tonnes handled, higher royalties tied to strong gold prices, and inflation in diesel and explosives.

The plan foresees growth capital of $91.8M and sustaining capital and stripping of $267.4M, funded from mine cash flows, to expand heap leach capacity and modernize the fleet. Subsequent Technical Report filing and future operating results will show how closely realized performance tracks these assumptions.

After-tax NPV5% $600.6M Project economics for Florida Canyon at stated gold prices
Average annual net free cash flow $90.0M Mining years in Florida Canyon Technical Report
Total net free cash flow $769.5M Life-of-mine Florida Canyon project economics
LOM site-level AISC (excl. closure) $2,331/oz All-in sustaining costs net of silver by-product
2026 AISC guidance (new range) $3,300–$3,500/oz Updated 2026 site-level AISC for Florida Canyon
2026 AISC guidance (prior range) $2,750–$2,950/oz Previous 2026 site-level AISC guidance
2026 production guidance 70–75 Koz Au Florida Canyon gold production guidance for 2026
Growth capital $91.8M Florida Canyon heap leach expansion and fleet modernization
All-in Sustaining Costs financial
"Site-level All-in Sustaining Costs - Excluding Closure Costs | | $2,331 |"
All-in sustaining costs (AISC) is a per-unit measure used mainly in the mining sector that captures the full ongoing cost to produce a unit of metal, including operating expenses, sustaining capital (maintenance of current operations), and a share of corporate overhead and site-level costs. Investors use AISC to judge whether production generates real profit and sustainable cash flow—think of it as the total monthly household cost to keep a home running, not just the utility bill.
free cash flow financial
"Average Annual Net Free Cash Flow (Mining Yrs) | $90.0 Total Net Free Cash Flow | $769.5"
Free cash flow is the amount of money a company has left over after paying all its expenses and investing in its business, like buying equipment or updating facilities. It shows how much cash is available to reward shareholders, pay down debt, or save for future growth. This helps investors understand if a company is financially healthy and able to grow.
heap leach pad technical
"Crushed ore is then agglomerated with a polymer binding agent ... delivered to the heap leach pad"
A heap leach pad is a large, engineered outdoor area where crushed ore is stacked and soaked with a liquid that dissolves and carries out valuable metals, like gold or copper, for later recovery — imagine a giant soak-bed that extracts metal instead of color. Investors care because the pad’s size, design, chemical and water needs, recovery efficiency and environmental controls directly affect a mine’s production costs, output, permitting risks and potential cleanup liabilities.
Mineral Reserve Estimate financial
"Mineral Reserve Estimate The Mineral Reserves were estimated by applying detailed mine design"
A mineral reserve estimate is an expert calculation of how much economically recoverable mineral material exists at a site after accounting for costs, technology and legal permissions; think of it as the amount of usable, sellable product a mine is expected to produce. Investors care because it directly affects a project’s potential revenue, timeline and risk—larger, more certain reserves usually mean higher asset value and lower uncertainty about future cash flow.
NI 43-101 regulatory
"The scientific and technical information ... is a Qualified Person as defined by NI 43-101."
A Canadian regulatory standard that sets the rules for how mining and exploration companies must report mineral resources and reserves, requiring technical reports prepared or signed off by an independent, certified expert. It matters to investors because it creates a consistent, transparent “inspection report” for mining projects, making it easier to compare prospects, judge the reliability of claims, and assess geological and financial risk before investing.
cash cost financial
"Cash Costs Cash costs include site operating costs (mining, processing, site G&A), refinery costs and royalties"
Cash cost is the actual out-of-pocket money a business spends to produce a product or run its everyday operations, excluding accounting items that don't require immediate cash (for example, depreciation). Investors care because it shows the real, short-term cash burden per unit of output or service—like comparing the grocery bill for a meal versus the estimated long-term appliance wear—and helps judge whether a company can generate cash and cover expenses from its core activities.
See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google
Learn about SEC filing dates

UNITED STATES

SECURITIES AND EXCHANGE COMMISSION

Washington, D.C. 20549

Form 6-K

REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO RULE 13a-16 or 15d-16 UNDER THE
SECURITIES EXCHANGE ACT OF 1934

For the month of June 2026.

Commission File Number 001-39372

INTEGRA RESOURCES CORP.

(Exact Name of Registrant as Specified in Charter)


1050-400 Burrard Street

Vancouver, British Columbia V6C 3A6

Canada

(Address of principal executive office)

Indicate by check mark whether the registrant files or will file annual reports under cover Form 20-F or Form 40-F

Form 20-F  Form 40-F 

Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(1): ☐

Note:  Regulation S-T Rule 101(b)(1) only permits the submission in paper of a Form 6-K if submitted solely to provide an attached annual report to security holders.

Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(7):  ☐

Note: Regulation S-T Rule 101(b)(7) only permits the submission in paper of a Form 6-K if submitted to furnish a report or other document that the registrant foreign private issuer must furnish and make public under the laws of the jurisdiction in which the registrant is incorporated, domiciled or legally organized (the registrant's "home country"), or under the rules of the home country exchange on which the registrant's securities are traded, as long as the report or other document is not a press release, is not required to be and has not been distributed to the registrant's security holders, and, if discussing a material event, has already been the subject of a Form 6-K submission or other Commission filing on EDGAR.


SIGNATURE

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

  Integra Resources Corp.
   
Date:  June 25, 2026 /s/ Andree St-Germain      
Andree St-Germain
Chief Financial Officer


INDEX TO EXHIBITS

99.1 News Release dated June 25, 2026



1050 - 400 Burrard Street
Vancouver, British Columbia,
Canada, V6C 3A6
Email: ir@integraresources.com
   
FOR IMMEDIATE RELEASE TSXV: ITR; NYSE American: ITRG
June 25, 2026 www.integraresources.com

FLORIDA CANYON FEASIBILITY STUDY DELIVERS SUBSTANTIAL INCREASE IN MINERAL RESERVE, GOLD
PRODUCTION OVER AN 8-YEAR MINE LIFE AND US$0.8 BILLION IN AFTER-TAX FREE CASH FLOW;
PROVIDES OPERATIONAL UPDATE

Vancouver, British Columbia - Integra Resources Corp. ("Integra" or the "Company") (TSXV: ITR; NYSE American: ITRG) is pleased to announce the results of its updated Technical Report Feasibility Study and Life-of-Mine Plan (the "Technical Report") for the producing Florida Canyon Mine ("Florida Canyon" or the "Project"), located in Nevada. Less than two years after acquiring Florida Canyon for $68 million ("M")1, Integra has transformed the operation into a larger, longer-life asset with a 74% increase in Proven and Probable Mineral Reserves, a 17% increase in annual gold production and active mining extended through 2033. Florida Canyon is now expected to generate over $0.8 billion ("B") from gold production in after-tax free cash flow2 and total payable gold production of 685 thousand ounces ("Koz") over life-of-mine ("LOM"), including 2 years of gold production from residual leaching starting in 2033. 

(All amounts in United States ("U.S.") dollars and Metric Units unless otherwise stated)

2026 Florida Canyon Technical Report Highlights:

  • Robust gold project economics: After-tax net present value 5% ("NPV") of $601 M using base case metal prices3; After-tax NPV of ~$723 M using spot metal prices4.
  • Significant increase in Proven and Probable Mineral Reserve: Integra replaced gold ("Au") mined at Florida Canyon over the last two years and increased the Proven and Probable Mineral Reserve ("P&P") at Florida Canyon by 74%. The P&P increased from 685 Koz Au in the 2024 Mineral Reserve Statement5 to 1.19 million ounces ("Moz") Au in the 2026 Mineral Reserve Estimate, a 506 Koz Au increase in P&P6.
  • Substantial increase in oxide Mineral Resources: The Mineral Resource Estimate ("MRE") increased 128% in the oxide Measured and Indicated ("M&I") category and 57% in the oxide Inferred ("Inf.") category, including a MRE on the Standard Mine located south of Florida Canyon.
  • Enhanced gold production profile and extended mine life: The annual production profile in the Technical Report has increased from 70 Koz Au to an average of 82 Koz Au over an 8-year operating mine life (inclusive of 2026), a 12 Koz Au increase in average annual production with operating mine life extending from 2030 to 2033 (not including 2 years of gold production from residual leaching starting in 2033).
  • Strong free cash flow2 supports growth: Florida Canyon is expected to generate approximately $0.8 B in LOM after-tax free cash flow and average annual after-tax free cash flow of $90 M, supporting growth capital investments at Florida Canyon to increase mine life and annual production profile.
  • Lower LOM All-in Sustaining Costs2 and Revised 2026 Cost Guidance: Site-level all-in sustaining costs ("AISC") are expected to average approximately $2,331/oz over LOM. Due to the increase in tonnes mined, stacked and processed this year, along with inflationary pressures on diesel fuel and explosives, among others, the Company is revising its 2026 site-level AISC guidance from $2,750 to $2,950 to $3,300 to $3,500 while re-confirming and maintaining production guidance in 2026 of 70 Koz to 75 Koz Au. The updated mine plan in the Technical Report establishes a clear path toward lower long-term costs and higher annual gold production in future years. 

- 2 -

  • Optimized mine plan that unlocks value: Informed by two years of operating experience and a comprehensive review of historical performance and costs, the Technical Report delivers a more stable, predictable and executable mine plan for Florida Canyon. All production growth and planned heap leach pad expansion contemplated in the Technical Report can be supported within the existing Mine Plan of Operations.
  • Cash flow to support project pipeline: Cash flow from Florida Canyon will support the advancement of the DeLamar Project through permitting, with the Final Environmental Impact Statement and Record of Decision expected in H2 2027, and the Company's Nevada North project. Creating a path for the Company to become a multi-asset, mid-tier precious metals producer in the United States.
  • Multiple opportunities identified to increase LOM production and gold resource:  The Company is evaluating several opportunities to further increase gold recoveries, production and operating efficiency at Florida Canyon, including additional crushing capacity, haul road optimization, and improved truck routing. In addition, a 42,500 m exploration program is underway to identify potential mineral resource growth adjacent to the existing operation and across the Project. These opportunities are conceptual and not included in the current Mineral Reserve Estimate or economic analysis.

1) See news release dated July 29, 2024.

2) This is a non-GAAP financial measure, please refer to the "Cautionary Note Regarding Non-GAAP Measures" disclosure at the end of this news release for a description of this measure.

3) NPV discounted to January 1, 2026, and includes cash flows from January 1, 2026 to May 31, 2026. Base case gold prices: 2026 ($4,344/oz), 2027 ($4,414/oz), 2028 ($4,169/oz), 2029 ($3,824), 2030 to 2035 ($3,600/oz).

4) Assuming a gold price of $4,200/oz from mid-2026 to 2035.

5) Based on the technical report entitled, "NI 43-101 Technical Report, Florida Canyon Gold Mine, Pershing County, Nevada, USA" dated July 1, 2024, with an effective date of June 28, 2024 (the "2024 Technical Report") with additional production depletion through December 31, 2025. In the 2024 Technical Report, the P&P was 861 Koz.

6) Please see notes for Mineral Resource Estimate and notes for Mineral Reserve Estimate below.

George Salamis, President, CEO and Director of Integra commented: "Since acquiring Florida Canyon in late 2024, the team has developed a deep understanding of the operation and systematically addressed the opportunities identified during the acquisition. Through disciplined investment, exploration drilling, operational improvements and detailed mine planning, Florida Canyon has been transformed into a fundamentally stronger asset with higher gold production, lower future costs, a longer mine life and a substantially larger mineral reserve base. Florida Canyon is now expected to generate approximately $0.8 billion in after-tax free cash flow over an 8-year mine life, establishing Florida Canyon as the cash flow engine of Integra and providing the financial foundation to advance our development pipeline in Idaho and Nevada."

Mr. Salamis added: "Based on the updated mine plan, we are intentionally investing to drive future growth. The higher costs expected in 2026 are short-term in nature and are tied to increased mining rates at the mine this year. As Florida Canyon transitions to a more stable operation, we expect to benefit from lower costs and enhanced economics."


- 3 -

"The updated Mineral Resource Estimate demonstrates the significant value created at Florida Canyon since its acquisition. Despite two years of mining depletion, the Company has increased Proven and Probable Mineral Reserves by 74%, extended mine life by 3-years and increased annual gold production by 17%. Importantly, this growth has been achieved within a producing, self-funding mine and reinforces the Company's belief that Florida Canyon remains significantly underexplored with substantial upside. Combined with the advancement of DeLamar and Nevada North, Florida Canyon provides a strong foundation for Integra's long-term growth as a U.S.-focused precious metals producer."

Integra will host a conference call and webcast to discuss the Technical Report on June 26, 2026, at 8am Pacific Time / 11am Eastern Time, featuring a presentation from the senior management team and a live Q&A session. A recording will be available on Integra's corporate website at www.integraresources.com. To register for the webcast, please use the following link (call details are listed below):

https://events.q4inc.com/attendee/752689074

Technical Report Summary

The Technical Report reflects the evolution of Florida Canyon from a project with limited mine life and flat annual gold production into a project with an increased production profile and an extended mine life. The enhanced mine plan utilizes existing infrastructure and the current crushing circuit to support an 8-year operating mine life with a LOM site-level AISC of $2,331/oz. Annual gold production increases 17% from 70 Koz to 82 Koz, resulting in LOM gold sold of 685 Koz.

The mine plan outlined in the Technical Report represents a material transformation of Florida Canyon. To realize this growth, Integra plans to use its existing cash flow to invest approximately $92 M towards growth capital investments, including $55 M towards the expansion of heap leach capacity within the existing Mine Plan of Operations footprint and $37 M towards the modernization and replacement of the legacy fleet.  These investments allow the Company to execute on the updated mine plan outlined in the Technical Report. The Technical Report highlights a base case after-tax NPV of $601 M (see Table 1 for base case gold price assumptions and Table 2 for after-tax NPV and LOM cumulative cash flows at various gold prices).

The Company retained Global Resource Engineering ("GRE") as lead consultants, along with other engineering consultants, to complete the Technical Report and prepare the Technical Report in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101"). The Technical Report is derived from the updated mineral reserve estimate effective May 31, 2026. The effective date of the Technical Report is June 25, 2026, and the Technical Report prepared in accordance with NI 43-101 will be filed on the Corporation's website and under its SEDAR+ profile within 45 days of this news release.

Table 1: Florida Canyon Technical Report Highlights1

Mining  
Total Tonnage Mined (K tonnes ("Kt")) 211,199
Total Ore Mined (Kt) 116,935
Strip Ratio (Waste: Ore) 0.81
Mine Life (Mining Yrs) 8.0
Contained Gold (Koz Au) 1,156


- 4 -

Production  
LOM Average Gold Recovery (%) 56.7%
LOM Gold Recoverable Placed (Koz Au) 656
LOM Gold Sold (Koz Au) 685
Average Annual Gold Sold (Koz Au) - Mining Yrs 81.8
Costs per Tonne (Mining Years 2026 to 2033)  
Mining Costs ($/t mined) $3.04
Mining Costs ($/t placed) $5.50
Crushing & Processing Costs ($/t placed) $3.03
G&A Costs ($/t placed) $1.24
Total Site Operating Cost ($/t placed) $9.77
LOM Site-Level Cash Costs ($/oz Au)  
LOM Cash Cost, net-of-silver by-product $1,940
LOM Site-Level AISC, net-of-silver by-product 2 $2,331
LOM Capital Expenditure ($ M)  
Sustaining Capital $130.2
Capitalized Stripping  $86.5
Development Drilling $7.9
Financing Leases - Sustaining $42.8
Growth Capital $91.8
Financing Leases - Growth Capital $8.6
Salvage Value ($16.9)
Reclamation Cost $40.2
Bonding Cash Collateral Return ($11.4)
Gold Price Assumptions ($/oz)  
Gold Price 2026 $4,344
Gold Price 2027 $4,414
Gold Price 2028 $4,169
Gold Price 2029 $3,824
Gold Price 2030 to 2035 $3,600
Project Economics ($ M)  
After-Tax NPV5% $600.6
Average Annual Net Free Cash Flow (Mining Yrs) $90.0
Total Net Free Cash Flow $769.5

(1) Please refer to "Cautionary Note Regarding Non-GAAP Measures" for a description of non-GAAP financial measures included in this table.

(2) Excluding closure costs.


- 5 -

Figure 1: Florida Canyon Annual Production and Operating Cost Profile1

(1) Please refer to "Cautionary Note Regarding Non-GAAP Measures" for a description of non-GAAP financial measures included in this figure.

Figure 2: Florida Canyon LOM After-tax Free Cash Flow1

(1) Please refer to "Cautionary Note Regarding Non-GAAP Measures" for a description of non-GAAP financial measures included in this figure.


- 6 -

Table 2: Florida Canyon After-Tax NPV and LOM After-tax Net Cash Flow ("CF") Sensitivity to Gold Price1

        Gold Price Estimate ($/oz)
Change in
Gold Price
After-Tax
NPV (5%) $M
After-Tax
LOM CF $M
  2026 2027 2028 2029 2030 to
2035
(25%) $203.8 $275.3   $3,535 $3,311 $3,127 $2,868 $2,700
(20%) $283.5 $374.8   $3,697 $3,531 $3,335 $3,059 $2,880
(15%) $363.2 $474.1   $3,859 $3,752 $3,544 $3,250 $3,060
(10%) $443.1 $573.5   $4,021 $3,973 $3,752 $3,442 $3,240
(5%) $522.3 $672.1   $4,183 $4,193 $3,961 $3,633 $3,420
Base $600.6 $769.5   $4,344 $4,414 $4,169 $3,824 $3,600
5% $676.5 $864.2   $4,506 $4,635 $4,377 $4,015 $3,780
10% $752.3 $958.7   $4,668 $4,855 $4,586 $4,206 $3,960
15% $828.0 $1,053.2   $4,830 $5,076 $4,794 $4,398 $4,140
20% $903.6 $1,147.3   $4,992 $5,297 $5,003 $4,589 $4,320
25% $978.0 $1,239.4   $5,154 $5,518 $5,211 $4,780 $4,500

(1) Please refer to "Cautionary Note Regarding Non-GAAP Measures" for a description of non-GAAP financial measures included in this table.

Property Description, Location and Access

Florida Canyon is located 125 miles (~201 kilometers) east of Reno, Nevada, and immediately south of Interstate 80. The nearest towns are Winnemucca, 40 miles northeast (~64 kilometers) with a population of 8,388 (2022) and Lovelock, 33 miles southwest, with a population of 1,854 (2022). The highway exit for the Florida Canyon Mine from I-80 is at Imlay, Nevada. Access is reliable via the Interstate year-round.

Commercial mining operations at Florida Canyon began in 1986 using conventional open-pit mining and heap-leach processing methods. The mine operated continuously through 2011 before entering a period of intermittent production until 2015. Florida Canyon was subsequently restarted in mid-2016 following new investment and operational improvements and has remained in operation since. Since the restart, Florida Canyon has undergone modernization and expansion efforts, including upgrades to equipment, heap-leach infrastructure, permitting expansions, and long-term mine planning initiatives. 


- 7 -

Figure 3: Florida Canyon Location Map

Updated Mineral Resource Estimate

Mineral resources were re-estimated from the resource model released in 2024 and include historic waste rock stockpiles whose grade exceeds current cut-off grades for the Project. The updated Mineral Resource Estimate ("MRE") incorporates a revised geological interpretation that includes structural domains and shear controls. These changes improved grade continuity within mineralized zones and reduced dilution associated with previous estimation domains. The revised geological model includes infill, confirmatory and exploration drilling completed since 2024, together with historical drilling completed by previous operators. In total, the MRE is based on 5,454 drill holes totaling 665,423 meters ("m"). The updated MRE for Florida Canyon was modeled following industry-standard and Canadian Institute of Mining, Metallurgy & Petroleum ("CIM") compliant protocols.

Key steps included:

 Verification of the drill hole database;

 Generation of drill hole intercepts for each shear zone;

 Statistical analysis of assay data;

 Compositing of assay intervals;


- 8 -

 Capping of outlier composite values;
 Geostatistical analysis, including variography;
 Construction of the block model and grade interpolation;
 Classification of the Mineral Resources;
 Validation of the block model;
 Calculation of cut-off grades;
 Pit optimization;
 Confirmation that reported blocks meet the RPEEE criteria; and
 Preparation of the Mineral Resource statement.

The MRE is constrained within an optimized pit shell generated using updated metal prices, metallurgical recoveries, operating costs and slope assumptions consistent with reasonable prospects for eventual economic extraction.

Table 3: Florida Canyon and Standard Mine MRE

Notes for Florida Canyon Mineral Resource Estimate

(1) Mineral resources are reported, using the 2014 CIM Definition Standards, with an effective date of May 31, 2026. The qualified person as defined under NI 43-101 for the estimate is Ms. Terre Lane, MMSA QP, a Global Resource Engineering, Ltd. employee.​ Ms. Terre Lane is independent of the Company.

(2) Mineral resources are reported inclusive of those mineral resources converted to mineral reserves. Mineral resources that are not mineral reserves do not have demonstrated economic viability.​

(3) Mineral resources are constrained within a conceptual open pit shell that uses the following assumptions: gold price of $2,650/oz; gold recoveries ranging from 43% to 67% for oxides and 80% for sulfides; reference mining cost of $2.79/t mined in-situ and $2.47/t mined fill; processing cost of $6.51/t processed for oxide crushed material and $4.23/t processed for oxide ROM material; processing cost of $26.30/t processed for sulfide material; general and administrative costs of $1.14/t processed; treatment and refining costs of 38.73/oz Au recoverable; royalty of $132.00/oz Au recoverable, and pit slope overall angles ranging from 30-36°.​

(4) Mineral resources are reported at a cut-off grade ranging from 0.13 g/t to 0.14 g/t for oxides and is 0.46 g/t for sulfides.​

(5) Mineral Resources include a stockpile of 1,094 kt at an average grade of 0.21 g/t and total contain gold of 6.78 Koz.​

(6) Mineral Resources include Heap Leach Inventory of 6,648 kt at an average grade of 0.29 g/t and total contained gold of 56.5 Koz.​

(7) Numbers have been rounded and may not sum.

(8) The estimate of mineral resources may be materially affected by geology, environment, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.


- 9 -

Notes for Standard Mine Mineral Resource Estimate

(1) Mineral Resources are reported, using the 2014 CIM Definition Standards, with an effective date of May 31, 2026. The Qualified Person for the estimate is Mr. Antoine Teixeira de Carvalho, P.Geo., an employee of BT Africa Mining Services. Mr. Antoine Teixeira de Carvalho is independent of the Company.

(2) Mineral Resources are reported inclusive of those Mineral Resources converted to Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

(3) Mineral Resources are constrained within a conceptual open pit shell that uses the following assumptions: gold price of US$2,650/oz; gold recoveries ranging from 43% to 66.7% for oxides and 80% for sulfides; reference mining cost of $2.79/ton mined in-situ and $2.47/ton mined fill; processing cost of $5.37/ton processed for oxide crushed material and $3.09/ton processed for oxide ROM material; processing cost of $25.16/ton processed for sulfide material; general and administrative costs of $1.14/ton processed; treatment and refining costs of $38.73/oz Au recoverable; royalty of $145.75/oz Au recoverable, and pit slope overall angles ranging from 30-43°.

(4) Mineral Resources are reported at a cut-off grade ranging from 0.0038 oz/ton to 0.0071 oz/ton for oxides and is 0.0133 oz/ton for sulfides.

(5) Numbers have been rounded and may not sum.

(6) The estimate of mineral resources may be materially affected by geology, environment, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.

Mineral Reserve Estimate

The Mineral Reserves were estimated by applying detailed mine design, production schedules, operating costs, metallurgical recoveries and economic criteria to the Measured and Indicated Mineral Resources. The engineered open pits were constrained with cut-off grades that reflect updated metal prices, metallurgical recoveries and known operating costs. Based on updated geotechnical assessment and operating experience, inter-ramp slope angles in selected areas were increased from 38 degrees to 42 degrees, resulting in additional economic pit inventory available for resource conversion. Along with confirmatory and exploration drilling, refined engineering and the inclusion of historic waste rock stockpiles, the updated mineral reserve estimate fully replaces mining depletion since the acquisition of Florida Canyon and supports an extension of active mining through 2033.

Table 4: Florida Canyon Mineral Reserve

Notes to Mineral Reserves

(1) Mineral reserves are reported at the point of delivery to the process plant, using the 2014 CIM Definition Standards, with an effective date of May 31, 2026. The qualified person as defined under NI 43-101 for the estimate is Ms. Terre Lane, MMSA QP, a Global Resource Engineering, Ltd. employee.​ Ms. Terre Lane is independent of the Company.

(2) Mineral reserves are constrained within an open pit design that uses the following assumptions: gold price of $2,400/oz considering only oxide material; gold recoveries varied by deposit and ore type, ranging from 43% to 67%; reference mining cost of $3.24/t mined in-situ and $2.93/t mined fill; processing cost of $6.51/t processed for oxide crushed material and $4.23/t for oxide run-of-mine ("ROM") material; G&A costs of $1.14/t ore processed; treatment and refining costs of $38.73/oz gold recoverable; royalty costs of $132.00/oz gold recoverable; and pit slope inter-ramp angles ranged from 36-42° for rock and 36° for alluvium / fill.​


- 10 -

(3) Mineral reserves are reported at a cut-off grade ranging from 0.14 g/t to 0.15 g/t.​

(4) Mineral Reserves include a stockpile of 1,094 kt at an average grade of 0.21 g/t and total contained gold of 6.78 Koz.​

(5) Mineral Reserves include Heap Leach Inventory of 6,648 kt at an average grade of 0.29 g/t and total contained gold of 56.5 Koz.​

(6) Numbers have been rounded and may not sum.

(7) The estimate of mineral reserves may be materially affected by geology, environment, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.

Production Profile

The Technical Report outlines 8-years of active mining and ore placement, followed by approximately two years of residual gold recovery from heap leaching, extending the operating mine life from 2030 in the 2024 Technical Report to 2033 in the updated Technical Report. The 8-years of active mining at Florida Canyon are followed by 2-years of residual leaching. The updated mine plan shows an increase in annual production from 70 Koz Au in the 2024 Technical Report to 82 Koz in the updated Technical Report, which represents an annual increase of 12 Koz per year.

The Company anticipated 2026 would be a cost intensive transition year as it addressed a deferred stripping campaign in the Central pit and undertook fleet replacement and upgrades. The Technical Report reflects these investments and outlines a more stable and sustainable operating plan, reducing production variability and supporting a more consistent and predictable production profile over an increased LOM.

Mining

Mining is currently conducted as a conventional open-pit operation using truck-and-loader methods. The mine plan schedules 22.0 to 28.1 million tonnes ("Mt") of total material movement per year ("/yr"), which is consistent with historical mining performance and fleet capability, with an average of 14.6 Mt/yr of ore transferred to the heap leach pad. Approximately, 7.1 Mt/yr of ore is scheduled for crushing to 2.5 inches, consistent with capacity and historical operating performance of the existing crushing circuit. Crushed material will be blended with approximately 4.5 Mt to 9.3 Mt/yr of run-of-mine ("ROM") material during the 10-year LOM (8-years of active mining). The mine plan schedules 211.2 Mt of total material movement over the 8-year active mine life, including 116.9 Mt of ore with an average grade of 0.31 g/t Au, resulting in 656 Koz Au recoverable placed on the heap leach pad over LOM. The LOM average strip ratio of 0.81 waste tonnes per ore tonne is consistent with historical operating performance and supports the economic extraction of the reserve inventory.

The increased mine life and enhanced production profile are primarily driven by the expansion of the Central Pit and Radio Tower Pit. Mining is planned in the Central Pit from 2026 through 2028, followed by the Radio Tower Pit from 2028 through 2030. Mining from 2030 through 2033 will occur at the Jasperoid Pit and through the processing of historic waste rock stockpiles.

Mining assumptions were developed using recent operating performance, equipment productivity analyses, labour requirements, maintenance planning and detailed production scheduling. The Technical Report provides a mine plan that can be executed effectively and deliver consistent production. Through an improved geological model and detailed forward planning, the Company expects to improve operation reliability and preserve flexibility that supports multiple ore sources to unlock additional value from the Mineral Reserve base.


- 11 -

Figure 4: Florida Canyon Mining Profile

Processing and Recovery

Crushed ore at Florida Canyon passes through two stages of open circuit crushing to a final crush size of 80% minus 2.5 inches with processing capabilities of 21,000 tonnes per day ("tpd"). Crushed ore is then agglomerated with a polymer binding agent to improve solution percolation through the heap leach pad and is delivered via haul truck. The ore can also be delivered to the heap leach pad through a series of overland conveyors and mobile grasshopper conveyors, or a combination of both.

Crushed ore, representing 47% of all material transferred to the heap leach pad, is blended with ROM ore at the heap lead pad dump face. Barren solution (cyanide-bearing solution very low in gold grade) is applied selectively to different areas of the heap leach pad through drip irrigation tubing at an average application rate of 0.003 gallons per minute per square foot.

Heap leach pad expansions at Florida Canyon are planned within the existing Mine Plan of Operations at the Project. The heap leach pad expansion will take place over four total phases, with two phases completed between 2026 and 2028 and two phases completed in 2030 and 2031.

Figure 5: Florida Canyon Project Ounces Recoverable Placed Crushed vs. ROM


- 12 -

Table 5: Florida Canyon Project Mining & Processing Summary

  ROM Crushing Total
Mining
Total Ore Mined (Kt) 61,648 55,287 116,935
Total Waste (Kt)     94,264
Total Mined (Kt)     211,199
Strip Ratio (Waste: Ore)     0.81
Grade & Contained Metals
Average Gold Grade (g/t Au) 0.21 0.42 0.31
Contained Gold (Koz Au) 410 746 1,156
Production
LOM Average Gold Recovery (%) 44.8% 63.3% 56.7%
LOM Gold Recoverable Placed (Koz Au) 184 473 656
Ounces on the Heap Leach Pad as of Dec 31, 2025 (Koz Au)     29
LOM Gold Sold (Koz Au)     685

Operating Costs

The Technical Report provides a comprehensive assessment of Florida Canyon with a mine plan that reflects current and future operating realities. The Technical Report includes nearly two years of detailed review and analysis by Integra of operating costs, maintenance requirements, labour assumptions and long-term mine planning. The Company completed a bottom-up evaluation of all major cost categories at the Project, incorporating historical operating performance, budget variances and previously underrepresented costs to develop a more comprehensive and realistic cost structure. Assumptions have been updated to reflect current market conditions, including labour costs consistent with Nevada's competitive mining sector and expected turnover and vacancy rates.

The Technical Report also incorporates a fully integrated mine plan to support the expanded reserve base, including permitting costs and engineered plans for future heap leach pads. Equipment assumptions have been updated to reflect a more proactive maintenance strategy, integrating both planned component replacement programs and expected unplanned downtime based on historical operating performance. The Technical Report also includes investments in fleet modernization, including the transition to larger haul trucks and other equipment upgrades designed to improve productivity, increase reliability and reduce unit mining costs over time. Together, these investments support a more stable and predictable operating profile while providing the infrastructure and equipment capacity required to execute the mine plan.

Table 6: Florida Canyon Operating Cost Breakdown

Mining Years (2026 to 2033) $ Per Tonne  
Operating Costs 2026 to 2033 Mined   Placed  
Mining $3.04   $5.50  
Crushing and Conveying / Processing     $3.03  
G&A     $1.24  
Total Site Costs     $9.77  


- 13 -

Figure 6: Florida Canyon Annual Operating Cost ("Opex") per Tonne Placed

Table 7: Florida Canyon LOM Cash Costs and Site-Level AISC1

Life Of Mine   $/oz Au  
Site-Level Cash Costs, AISC Breakdown   By-Product  
Mining   $939  
Crushing and Conveying / Processing   $547  
G&A   $231  
Total Site Costs   $1,717  
Transport & Refining   $9  
Royalties   $246  
Total Cash Costs   $1,972  
Silver By-Product Credits   ($32 )
Total Cash Costs Net of Silver by-Product   $1,940  
Sustaining Capital   $391  
Site-Level All-in Sustaining Costs - Excluding Closure Costs   $2,331  
Closure Costs Net of Residual Value   $42  
Site-Level All-in Sustaining Costs - Including Closure Costs   $2,373  

(1) Please refer to "Cautionary Note Regarding Non-GAAP Measures" for a description of non-GAAP financial measures included in this table.

Capital Cost Estimates

The expanded production profile outlined in the Technical Report is expected to be funded from Florida Canyon's existing and future cash flow. The updated mine plan at Florida Canyon will be realized through growth capital investments of $92 M that will result in a materially enhanced Project. Expanding heap leach pad capacity is a key component of the updated mine plan, supporting both the longer mine life and increased production profile at Florida Canyon. The Company has allocated $55 M to construct two heap leach pad expansions within the existing Mine Plan of Operations footprint. In addition, the Company will invest approximately $37 M in fleet modernization, replacing aging loaders and legacy 777 haul trucks approaching their operating life with larger, more productive 785 haul trucks. These upgrades are expected to increase material movement capacity, improve operating efficiency and support the expanded production profile and longer mine life outlined in the Technical Report.


- 14 -

Sustaining capital of approximately $267 M includes ~$87 M for the completion of the extensive pre-stripping campaign in the Central Pit, which commenced in 2025 and is expected to conclude in 2026, providing access to higher-grade ore and supporting future production. In addition, ~$53 M in ongoing parts replacement and preventative maintenance designed to improve reliability and reduce unplanned downtime and ~$32 M for two additional heap leach pads are included in sustaining capital.

Table 8: Florida Canyon Capital Cost Breakdown

    Yr 2026 to 
Yr 2035
    Yr 2036 to  Yr
2038
    Combined
LOM
 
                   
Sustaining Capital Costs                  
Sustaining Capital   $130.2     $0.0     $130.2  
Capitalized Stripping   $86.5     $0.0     $86.5  
Development Drilling   $7.9     $0.0     $7.9  
Lease Payments (Financing) - Sustaining   $42.8     $0.0     $42.8  
Total Sustaining Capital & Stripping   $267.4     $0.0     $267.4  
                   
Other Capital                  
Lease Payments (Financing) - Growth   $8.6     $0.0     $8.6  
Growth Capital   $91.8     $0.0     $91.8  
Residual Value 1   ($16.9 )   $0.0     ($16.9 )
Reclamation 2   $19.9     $20.3     $40.2  
Cash collateral return 3   $0.0     ($11.4 )   ($11.4 )
Total Other Capital   $103.4     $8.9     $112.3  
                   
TOTAL SUSTAINING CAPITAL & OTHER   $370.8     $8.9     $379.7  

(1) The residual value represents estimated salvage value of mobile mining equipment and process / crushing / conveying equipment.

(2) Reclamation costs include ~$6M for reclamation of Standard Mine.

(3) Current cash collateral is assumed released in final year, once the reclamation is completed.

Next Steps and Opportunities

The Technical Report includes multiple opportunities for further additional Project optimization. These opportunities are conceptual in nature and not included in current Mineral Reserve Estimate or economic analysis. 


- 15 -

  • Near mine exploration: Exploration drilling completed in 2025 and 2026 contributed to a significant increase in mineral resources, demonstrating the potential for mineral resource growth next to existing infrastructure. In April 2026, Integra initiated a 42,500 m drill program at Florida Canyon to test underexplored extensions of known mineralization and evaluate targets along newly identified key structures that are known to control mineralization. Near mine drilling has the potential to increase mineral resources, mineral reserves, and production opportunities adjacent to Florida Canyon's existing mining and processing infrastructure.
  • Property wide exploration: Limited exploration has been completed by previous operators on the wider Florida Canyon property, which encompasses approximately 84 square miles (135 square kilometers). During the 2026 exploration program, Integra will drill at the Standard Mine south of Florida Canyon to evaluate historical backfill, waste material, and previously identified gold targets that have not seen significant exploration work in years. In addition, the Company will conduct first-pass drilling on several greenfield targets generated through geological work, geophysical surveys, geochemical sampling, and AI-assisted mineral targeting.
  • Crushing and recovery: The Company is evaluating the potential for additional crushing capacity at Florida Canyon to increase recovery and gold production in the future. As part of the assessment, detailed analysis will also focus on further optimizing crush size to accelerate gold recovery.
  • Enhanced mine productivity: The Company is implementing fleet management and dispatch systems to optimize haul road performance and planning, potentially lowering unit mining costs and increasing material movement reliability and efficiency.
  • Improved material routing: Refining cutoff grade strategies, stockpile management and ROM-to-crusher routing to maximize value capture from mined material and improve economic returns.

Guidance Update

The Company is revising its 2026 site-level AISC guidance at Florida Canyon. The adjustment to AISC is primarily attributed to an increase in the tonnes, mined, stacked and processed to support production, lower gold ounces sold during Q1 2026, increased royalties1 and excise taxes resulting from stronger-than-anticipated gold prices, and higher diesel fuel and explosive costs.  The Company now expects 2026 site-level AISC guidance to increase from $2,750 to $2,950 to $3,300 to $3,500 but confirms 2026 production guidance of 70 Koz to 75 Koz. The updated mine plan and costs presented in the Technical Report are grounded in historical and actual operation analysis and establish a realistic, executable mine plan moving forward that is expected to deliver more consistent production, lower long-term costs and sustainable value creation.

(1) Cost guidance calculated using average Au price of $4,200.

Florida Canyon Technical Report Conference Call & Webcast

Integra will host a conference call and webcast on Friday, June 26, 2026, at 11:00 AM Eastern Time / 8:00 AM Pacific Time, to discuss the Florida Canyon Technical Report. Details for the conference call and webcast are included below.

Dial-In Numbers / Webcast:

Conference ID: 5650865

Toll-Free: (800) 715-9871

Toll: +1 (646) 307-1963


- 16 -

Webcast: https://events.q4inc.com/attendee/752689074

About Integra

Integra is a growing precious metals producer in the Great Basin of the Western United States. Integra is focused on demonstrating profitability and operational excellence at its principal operating asset, the Florida Canyon Mine, located in Nevada. In addition, Integra is committed to advancing its flagship development-stage heap leach projects: the past producing DeLamar Project located in southwestern Idaho and the Nevada North Project located in western Nevada. Integra creates sustainable value for shareholders, stakeholders, and local communities through successful mining operations, efficient project development, disciplined capital allocation, and strategic M&A, while upholding the highest industry standards for environmental, social, and governance practices.

ON BEHALF OF THE BOARD OF DIRECTORS

George Salamis
President, CEO and Director

CONTACT INFORMATION

Corporate Inquiries: ir@integraresources.com
Company website: www.integraresources.com
Office phone: 1 (604) 416-0576

Qualified Persons

The scientific and technical information contained in this news release has been reviewed and approved by James Frost, P.Eng., Director, Technical Services of Integra Resources Corp., who is a Qualified Person as defined by NI 43-101.

The Company retained Global Resource Engineering as lead consultants, along with other engineering consultants, to complete the Technical Report. The following independent Qualified Persons with associated firms have reviewed and approved this news release as defined by NI 43-101:

Antoine Teixeira de Carvalho, P.Geo. - BT Africa Mining Services

Dave Swanton, MSc, P. Geo, - Equity Exploration Consultants Ltd.

Hamad Samari, Ph.D, MMSA QP - Global Resource Engineering, Ltd.

Larry Breckenridge, P.E. - Global Resource Engineering, Ltd.

Maxime Lamothe, P.E. - Alius Mine Consulting

Terre Lane, MMSA QP  - Global Resource Engineering, Ltd.

Todd Harvey, Ph.D., SME Register Member - Global Resource Engineering, Ltd.

Data Verification

The Qualified Persons responsible for the Technical Report have verified the data for which they are accountable, including the sampling, analytical, and test data underlying the information disclosed in this news release. Geological, mine engineering and metallurgical reviews included, among other things, reviewing drill data and core logs, review of geotechnical and hydrological studies, environmental and community factors, the development of the life-of-mine plan, capital and operating costs, transportation, taxation and royalties, and review of existing metallurgical test work. In the opinion of the Qualified Persons, the data, assumptions, and parameters used in the sections of the Technical Report that they are responsible for preparing are sufficiently reliable for those purposes. The Technical Report, when filed, will contain more detailed information concerning individual Qualified Persons responsibilities, associated quality assurance and quality control, and other data verification matters, and the key assumptions, parameters and methods used by the Company.


- 17 -

Sampling and QA/QC Procedure

Thorough QA/QC protocols are followed on the Project, including insertion of duplicate, blank and standard samples in the assay stream for all drill holes. The samples are submitted directly to American Assay Labs in Reno, Nevada for preparation and analysis. Analysis of gold is performed using fire assay method with atomic absorption ("AA") finish on a 1 assay ton aliquot. Gold results over 5 g/t are re-run using a gravimetric finish. Silver analysis is performed using ICP for results up to 100 g/t on a 5-acid digestion, with a fire assay, gravimetric finish for results over 100 g/t silver.

Additional supporting details regarding the information in this news release, will be provided in the Technical Report which will be available on SEDAR+ under the Company's profile within 45 days of this news release, including all qualifications, assumptions and exclusions that relate to the Technical Report. The Technical Report is intended to be read as a whole, and sections should not be read or relied upon out of context.

Forward Looking Statements

Certain information set forth in this news release contains "forward‐looking statements" and "forward‐looking information" within the meaning of applicable Canadian securities legislation and in applicable United States securities law (referred to herein as forward‐looking statements). Forward-looking statements are often identified by the use of words such as "may", "will", "could", "would", "anticipate", "believe", "expect", "intend", "potential", "estimate", "budget", "scheduled", "plans", "planned", "forecasts", "goals" and similar expressions. Except for statements of historical fact, certain information contained herein constitutes forward‐looking statements which includes, but is not limited to, statements with respect to: the future financial or operating performance of the Company, the Project and its mineral properties; the Company's updated 2026 guidance; the estimation of mineral resources and reserves; the realization of mineral resource and reserve estimates; the development, operational and economic results of the Technical Report for the Project, including cash flows, revenue potential, development, expenditures, and timing thereof, extraction rates, life-of-mine projections and cost estimates; timing of completion of the Technical Report and the filing thereof; magnitude or quality of mineral deposits; anticipated advancement of the Project mine plan, including, without limitation, the expansion of heap leach pad capacity and continued modernization of the Company's mining fleet; exploration expenditures, costs and timing of the development of new deposits; costs and timing of future exploration; permitting; construction and optimization planning, including, without limitation, timing of the Final Environmental Impact Statement and Record of Decision; estimates of metallurgical recovery rates; anticipated advancement and further exploration of the Project and surrounding areas, future prospects and prospective inclusion of Mineral Resources in future mining activities; requirements for additional capital; the future price of metals; government regulation of mining operations; environmental risks; the timing and possible outcome of pending regulatory matters; the realization of the expected economics of the Project; future growth potential of the Project; future development plans; and the date and timing of the conference call and webcast to discuss the Technical Report. Forward-looking statements are based on a number of factors and assumptions made by management and considered reasonable at the time such statement was made. Assumptions and factors include: the Company's ability to complete its planned exploration and development programs; the absence of adverse conditions at the Project and the Company's mineral properties; satisfying ongoing covenants under the Company's loan facilities; no unforeseen operational delays; no material delays in obtaining necessary permits; results of independent engineer technical reviews; the possibility of cost overruns and unanticipated costs and expenses; the price of gold remaining at levels that continue to render the Project and the Company's mineral properties economic; the Company's ability to continue raising necessary capital to finance operations; and the ability to realize on the mineral resource and reserve estimates. Forward‐looking statements necessarily involve known and unknown risks and uncertainties, which may cause actual performance and financial results in future periods to differ materially from any projections of future performance or result expressed or implied by such forward‐looking statements. These risks and uncertainties include, but are not limited to: general business, economic and competitive uncertainties; the actual results of current and future exploration activities; conclusions of economic evaluations; meeting various expected cost estimates; benefits of certain technology usage; changes in project parameters and/or economic assessments as plans continue to be refined; future prices of metals; possible variations of mineral grade or recovery rates; the risk that actual costs may exceed estimated costs; geological, mining and exploration technical problems; failure of plant, equipment or processes to operate as anticipated; accidents, labor disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing; risks related to local communities; the speculative nature of mineral exploration and development (including the risks of obtaining necessary licenses, permits and approvals from government authorities); title to properties; and other factors beyond the Company's control and as well as those factors included herein and elsewhere in the Company's public disclosure. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in the forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. Readers are advised to study and consider risk factors disclosed in Integra's Annual Information Form dated March 24, 2026 for the fiscal year ended December 31, 2025, which is available on the SEDAR+ issuer profile for the Company at www.sedarplus.ca and available as Exhibit 99.1 to Integra's Form 40-F, which is available on the EDGAR profile for the Company at www.sec.gov.


- 18 -

Investors are cautioned not to put undue reliance on forward-looking statements.  The forward-looking statements contained herein are made as of the date of this news release and, accordingly, are subject to change after such date.  The Company disclaims any intent or obligation to update publicly or otherwise revise any forward-looking statements or the foregoing list of assumptions or factors, whether as a result of new information, future events or otherwise, except in accordance with applicable securities laws.  Investors are urged to read the Company's filings with Canadian securities regulatory agencies, which can be viewed online under the Company's profile on SEDAR+ at www.sedarplus.ca.

Cautionary Note Regarding Non-GAAP Financial Measures

Alternative performance measures in this news release such as "cash cost", "AISC", "free cash flow" and "sustaining capital costs" are furnished to provide additional information. These non-GAAP performance measures are included in this news release because these statistics are used as key performance measures that management uses to monitor and assess performance of Florida Canyon, and to plan and assess the overall effectiveness and efficiency of mining operations. These performance measures do not have a standardized meaning within International Financial Reporting Standards ("IFRS") and, therefore, amounts presented may not be comparable to similar data presented by other mining companies. These performance measures should not be considered in isolation as a substitute for measures of performance in accordance with IFRS.


- 19 -

Cash Costs

Cash costs include site operating costs (mining, processing, site G&A), refinery costs and royalties, but excludes head office G&A and exploration expenses.  While there is no standardized meaning of the measure across the industry, the Company believes that this measure is useful to external users in assessing operating performance.

Site-Level All-In Sustaining Cost

Site-level AISC includes cash costs and sustaining and expansion capital, but excludes head office G&A and exploration expenses. The Company believes that this measure is useful to external users in assessing operating performance and the Company’s ability to generate free cash flow from potential operations.

Free Cash Flow

Free cash flows are revenues net of operating costs, royalties, capital expenditures and cash taxes. The Company believes that this measure is useful to the external users in assessing the Company's ability to generate cash flows from the Project.

Cautionary Note for U.S. Investors Concerning Mineral Resources and Reserves

NI 43-101 is a rule of the Canadian Securities Administrators which establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Technical disclosure contained in this news release has been prepared in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum Classification System. These standards differ from the requirements of the U.S. Securities and Exchange Commission ("SEC") and resource and reserve information contained in this news release may not be comparable to similar information disclosed by domestic United States companies subject to the SEC's reporting and disclosure requirements.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.


FAQ

What mine life and production does Integra Resources (ITRG) outline for Florida Canyon?

Integra outlines about eight years of active mining plus roughly two years of residual leaching at Florida Canyon, extending operations to 2033. Total ore mined is planned at 116.9 Mt, containing 1,156 Koz of gold, with life-of-mine gold sold estimated at 685 Koz.

What are the projected cash flows and NPV for Integra Resources (ITRG) Florida Canyon mine?

At stated gold price assumptions, the Florida Canyon plan shows after-tax NPV5% of $600.6M, average annual net free cash flow of $90.0M during mining years, and total net free cash flow of $769.5M. These economics rely on assumed gold prices from $4,344/oz in 2026 to $3,600/oz in 2030–2035.

How has Integra Resources (ITRG) changed 2026 AISC guidance for Florida Canyon?

Integra raises 2026 site-level AISC guidance for Florida Canyon from $2,750–$2,950/oz to $3,300–$3,500/oz. The company attributes the increase to higher tonnes mined and processed, lower gold ounces sold in Q1 2026, higher royalties and excise taxes, and increased diesel and explosives costs.

What are the life-of-mine operating costs at Integra Resources (ITRG) Florida Canyon?

Life-of-mine site-level cash costs net of silver by-product are estimated at $1,940/oz, while site-level all-in sustaining costs excluding closure costs are $2,331/oz. Including closure costs, site-level AISC is $2,373/oz, based on the Technical Report’s operating and capital assumptions.

How much capital investment is planned for Integra Resources (ITRG) Florida Canyon mine?

The plan includes sustaining capital and capitalized stripping totaling $267.4M and growth capital of $91.8M, plus lease payments and reclamation costs. Key uses are heap leach pad expansions and fleet modernization, including replacing older haul trucks with larger 785 trucks to support higher material movement.

What production guidance has Integra Resources (ITRG) issued for Florida Canyon in 2026?

For 2026, Integra maintains production guidance of 70–75 Koz of gold at Florida Canyon. This guidance is reaffirmed even as the company increases 2026 site-level AISC guidance, reflecting expectations for higher tonnes mined and processed and a cost-intensive transition year.