STOCK TITAN

Yerington PFS outlines $694M post-tax NPV for Lion Copper and Gold (LCGMF)

Filing Impact
(High)
Filing Sentiment
(Neutral)
Form Type
8-K

Rhea-AI Filing Summary

Lion Copper and Gold Corp. has completed an S‑K 1300 Preliminary Feasibility Study and Technical Report for its wholly owned Yerington Copper Project in Nevada. The study defines Proven and Probable mineral reserves of 506.6 million tons grading 0.21% copper, supporting a 12‑year open‑pit, heap‑leach operation.

Total initial and sustaining capital is estimated at $1,731.7M, with life‑of‑mine operating costs of $1.92 per payable pound of copper and all‑in sustaining costs of $2.67 per pound. At a long‑term copper price of $4.30/lb, the project generates a pre‑tax NPV(7%) of $975M and IRR of 16.9%, and post‑tax NPV(7%) of $694M with IRR of 14.6%.

The mine plan contemplates 506.6 million tons of heap‑leach feed at 0.21% copper, with a low overall strip ratio of 0.32:1 and total payable copper production of 1,443 million pounds, or about 120 million pounds per year on average. Processing will use separate oxide and sulfide heap‑leach facilities, including Nuton™ technology for sulfide material, and twin solvent‑extraction circuits feeding a common electrowinning plant.

Positive

  • None.

Negative

  • None.

Insights

Yerington PFS delivers first reserve-based economics with solid NPV and moderate costs.

The study converts Measured and Indicated resources into 506.6 Mt of Proven and Probable reserves at 0.21% copper, underpinning a 12‑year open‑pit, heap‑leach operation. Life‑of‑mine payable production of 1,443 Mlbs of copper gives meaningful scale for a single-asset developer.

Economically, the project shows a pre‑tax NPV(7%) of $975M and IRR of 16.9%, and post‑tax NPV(7%) of $694M with IRR of 14.6%, against total capital of about $1.73B. Cash costs of $1.92/lb and AISC of $2.67/lb, using a long‑term copper price of $4.30/lb, position the project in a mid‑cost bracket.

The plan relies on large‑scale sulfide and oxide heap leaching, including Nuton™ technology for sulfides at a peak feed rate of 35 Mtpa, and assumes timely permitting over roughly 2.5–3.5 years and coordination with ongoing site remediation. Future disclosures in company filings may refine capital, operating assumptions, and permitting progress as the project advances toward a full feasibility study.


false 2026-02-13 0001339688 Lion Copper and Gold Corp. 0001339688 2026-02-13 2026-02-13

UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
___________________________

FORM 8-K

CURRENT REPORT
Pursuant to Section 13 or 15(d) of the Securities Exchange Act of 1934

Date of Report (Date of earliest event reported): February 13, 2026

LION COPPER AND GOLD CORP.
(Exact name of registrant as specified in its charter)

British Columbia 000-55139 98-1664106
(State or other jurisdiction (Commission (IRS Employer
of incorporation) File Number) Identification No.)

143 S Nevada St.
Yerington, Nevada, United States 89447
(Address of principal executive offices) (ZIP Code)

Registrant’s telephone number, including area code: (775) 463-9600

Not Applicable
(Former name or former address, if changed since last report)

Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions:

Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)

Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)

Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))

Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))

Securities registered pursuant to Section 12(b) of the Act:

Title of each class   Trading Symbols   Name of each exchange on which registered
N/A        

Indicate by check mark whether the registrant is an emerging growth company as defined in Rule 405 of the Securities Act of 1933 (§ 230.405 of this chapter) or Rule 12b-2 of the Securities Exchange Act of 1934 (§ 240.12b -2 of this chapter).

Emerging growth company

If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act.


Item 8.01. Other Events.

Lion Copper and Gold Corp. has completed a S-K 1300 Preliminary Feasibility Study & Technical Report Summary dated effective May 31, 2025 for its wholly-owned Yerington Copper Project, located in Lyon County, Nevada.

The Report was prepared in accordance with Subpart 1300 of Regulation S-K as promulgated by the U.S. Securities and Exchange Commission. A copy of the Report is attached hereto as Exhibit 99.1 to this Current Report on Form 8-K, and is incorporated herein by reference.

Item 9.01 Exhibits.

23.1 Consent of Samuel Engineering Inc.
23.2 Consent of AGP Mining Consultants, Inc.
23.3 Consent of NewFields Mining Design & Technical Services, LLC
23.4 Consent of T. Maunula & Associates
23.5 Consent of Independent Mining Consultants, Inc.
23.6 Consent of GSI Environmental Inc.
99.1 S-K 1300 Preliminary Feasibility Study & Technical Report Summary, Yerington Copper Project dated effective May 31, 2025
104 Cover Page Interactive Data File (embedded within the Inline XBRL document)

SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned hereunto duly authorized.

      Lion Copper and Gold Corp.
Date: February 13, 2026   (Registrant)
       
      /s/ Lei Wang
      Lei Wang, Chief Financial Officer



S-K 1300 PRELIMINARY FEASIBILITY STUDY &
TECHNICAL REPORT SUMMARY

YERINGTON COPPER PROJECT

FOR

LION COPPER AND GOLD

PREPARED BY

Lion Copper and Gold
143 South Nevada St.
Yerington, NV 89447
775.463.9600
   
Samuel Engineering, Inc.
8450 East Crescent Pkwy. Ste. 200
Greenwood Village, CO  80111-2816
303.714.4840
   
AGP Mining Consultants, Inc.
132 Commerce Park Dr., Unit K #246
Barrie, Canada L4N 0Z7
416.239.6777
   
NewFields
19540 Maroon Circle, Ste. 300
Englewood, CO 80112
720.508.3300

 

Qualified Persons:

Michael McGlynn, SME-RM, Samuel Engineering Marie-Hélène Paré, SME-RM, GSI Environmental Inc.
Steve Pozder, P.E., Samuel Engineering Tim Maunula, P.Geo., T. Maunula & Associates Consulting Inc.
Gordon Zurowski, P. Eng., AGP Mining Herb Welhener, MMSA-QPM, Independent Mining Consultants, Inc. (IMC)
Adrien Butler, P.E., NewFields  


Signature Page

This report titled "Preliminary Feasibility Study & Technical Report Summary - Yerington Copper Project" with an effective date of May 31, 2025, was prepared and signed by:

Samuel Engineering Inc.  
Dated December 1st, 2025 /s/ Samuel Engineering Inc.
   
AGP Mining Consultants, Inc.  
Dated December 1st, 2025 /s/AGP Mining Consultants, Inc.
   
NewFields  
Dated December 1st, 2025 /s/ Newfields
   
T. Maunula & Associates  
Consulting Inc.  
Dated December 1st, 2025 /s/ T. Maunula & Assocaites Consulting Inc.
   
Independent Mining  
Consultants, Inc.  
Dated December 1st, 2025 /s/ Independent Mining Consultants, Inc.
   
GSI Environmental Inc.  
Dated December 1st, 2025 /s/ GSI Environmental Inc.

 

 

This report was authored by the qualified persons (each a "QP" and collectively, the "QPs") listed in Table 2.2. Each QP and their respective Company only assumes responsibility for those sections or areas of the report that are referenced opposite their name in Table 2.1. None of such QPs, however, accept any responsibility or liability for the sections or areas of this report that were prepared by other QPs.


 

Table of Contents

1.0 EXECUTIVE SUMMARY 1
   
1.1 LOCATION AND PROPERTY DESCRIPTION 2
1.2 HISTORY 3
1.3 GEOLOGY 4
1.4 MINERALIZATION 5
1.5 EXPLORATION AND DIAMOND DRILLING 6
1.6 MINERAL PROCESSING AND METALLURGICAL TESTING 10
1.7 MINERAL RESERVES AND RESOURCE ESTIMATION 10
1.8 MINING METHODS 16
1.9 INFRASTRUCTURE 17
1.10 ENVIRONMENTAL 18
1.11 MARKETS 20
1.12 PROJECT ECONOMICS 20
1.13 QUALIFIED PERSONS RECOMMENDATIONS 22
   
2.0 INTRODUCTION 23
   
2.1 2025 PFS OVERVIEW 23
2.2 QUALIFIED PERSONS 23
2.3 SITE INSPECTION 24
2.4 EFFECTIVE DATES 26
   
3.0 PROPERTY DESCRIPTION 27
   
3.1 LOCATION 27
3.2 PROPERTY OWNERSHIP 28
3.3 MINERAL TENURE, TITLE AND ROYALTIES 29
3.4 PROJECT BACKGROUND 30
3.5 PROJECT CLAIMS AND PRIVATE LAND 30
3.6 PERMIT REQUIREMENTS 60
3.7 SIGNIFICANT FACTORS AND RISKS THAT MAY AFFECT ACCESS, TITLE OR WORK PROGRAMS 61
3.8 PERMITTING 61
   
4.0 ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE, AND PHYSIOGRAPHY 62
   
4.1 ACCESSIBILITY 62
4.2 CLIMATE AND LENGTH OF OPERATING SEASON 62
4.3 LOCAL RESOURCES AND INFRASTRUCTURE 62
   
5.0 HISTORY 64
   
5.1 PROPERTY HISTORY 64
5.2 HISTORICAL RESOURCES 67


 

6.0 GEOLOGICAL SETTING, MINERALIZATION, AND DEPOSIT 69
   
6.1 REGIONAL GEOLOGY 69
6.2 LOCAL GEOLOGY 73
6.3 PROPERTY GEOLOGY 73
6.4 PROPERTY ALTERATION 74
6.5 MINERALIZATION 76
6.6 DEPOSIT TYPES 78
   
7.0 EXPLORATION 80
   
7.1 EXPLORATION HISTORY 80
7.2 GEOPHYSICS 80
7.3 DRILLING 88
7.4 LION CG DRILLING 90
7.5 DRILLING PROCEDURES AND CONDITIONS 97
7.6 QP ADEQUACY STATEMENT 98
   
8.0 SAMPLE PREPARATION, ANALYSES, AND SECURITY 99
   
8.1 SAMPLE PREPARATION AND ANALYSES 99
8.2 DENSITY 103
8.3 SAMPLE SECURITY 104
8.4 QUALITY CONTROL 105
8.5 QP ADEQUACY STATEMENT 111
   
9.0 DATA VERIFICATION 112
   
9.1 YERINGTON DEPOSIT 112
9.2 MACARTHUR DEPOSIT 126
   
10.0 MINERAL PROCESSING AND METALLURGICAL TESTING 128
   
10.1 INTRODUCTION 128
10.2 COPPER RECOVERY PROJECTIONS 128
10.3 CURRENT METALLURGICAL TESTWORK PROGRAMS 129
10.4 YERINGTON OXIDE MATERIALS 150
10.5 MACARTHUR METALLURGICAL TESTING 155
10.6 HISTORIC HEAP LEACH PRODUCTION 172
10.7 DELETERIOUS ELEMENTS 173
10.8 CONCLUSIONS 173
10.9 RECOMMENDATIONS FOR FUTURE TESTING 174
10.10 QP ADEQUACY STATEMENT 174
   
11.0 MINERAL RESOURCE ESTIMATES 175
   
11.1 INTRODUCTION 175
11.2 YERINGTON DEPOSIT 175
11.3 YERINGTON RESIDUALS 188


 

11.4 MACARTHUR DEPOSIT 195
11.5 FACTORS THAT MAY AFFECT THE MINERAL RESOURCE ESTIMATE 219
11.6 QP ADEQUACY STATEMENT 219
   
12.0 MINERAL RESERVE ESTIMATES 220
   
12.1 SUMMARY 220
12.2 GEOTECHNICAL AND PIT SLOPES 221
12.3 ECONOMIC PIT SHELL DEVELOPMENT 221
12.4 CUT-OFF 223
12.5 DILUTION AND MINING LOSSES 223
12.6 MINE DESIGN 224
12.7 MINE SCHEDULE 224
12.8 MINERAL RESERVES STATEMENT 225
12.9 FACTORS THAT MAY AFFECT THE MINERAL RESERVE ESTIMATE 226
12.10 QP ADEQUACY STATEMENT 226
   
13.0 MINING METHODS 228
   
13.1 INTRODUCTION 228
13.2 MINING GEOTECHNICAL 228
13.3 OPEN PIT 235
13.4 PIT DESIGN 240
13.5 ROCK STORAGE FACILITIES 247
13.6 MINE SCHEDULE 249
13.7 MINE EQUIPMENT SELECTION 271
13.8 BLASTING AND EXPLOSIVES 271
13.9 GRADE CONTROL 271
13.10 PIT DEWATERING 272
13.11 PIT SLOPE MONITORING 272
13.12 HYDROGEOLOGY AND PIT DEWATERING 272
   
14.0 PROCESSING AND RECOVERY METHODS 273
   
14.1 INTRODUCTION 273
14.2 PROCESS PLANT LOCATION 273
14.3 QP ADEQUACY STATEMENT 283
   
15.0 INFRASTRUCTURE 284
   
15.1 INTRODUCTION 284
15.2 ACCESS 286
15.3 ACCOMMODATION 286
15.4 MACARTHUR SITE 287
15.5 YERINGTON SITE 289
15.6 SUPPORT BUILDINGS 295
15.7 MACARTHUR-YERINGTON PIPELINES 296


 

15.8 HAUL ROAD 296
15.9 SERVICE ROAD 297
15.10 FUEL 297
15.11 POWER SUPPLY AND ELECTRICAL DISTRIBUTION 297
15.12 STORMWATER MANAGEMENT 299
15.13 HEAP LEACH FACILITIES 300
   
16.0 MARKET STUDIES AND CONTRACTS 306
   
16.1 COPPER 306
16.2 HISTORIC 307
16.3 FORWARD 307
16.4 SULFUR 308
16.5 SULFURIC ACID 308
   
17.0 ENVIRONMENTAL STUDIES, PERMITTING AND PLANS, NEGOTIATIONS, OR AGREEMENTS WITH LOCAL INDIVIDUALS OR GROUPS 309
   
17.1 ENVIRONMENTAL BASELINE STUDIES 309
17.2 PROJECT PERMITTING 309
17.3 ENVIRONMENTAL STUDIES 316
17.4 ENVIRONMENTAL ISSUES 318
17.5 WASTE, WATER, AND PROCESS FLUID MANAGEMENT 319
17.6 SITE MONITORING 320
17.7 SOCIAL/COMMUNITY 321
17.8 CLOSURE PLANNING 322
   
18.0 CAPITAL AND OPERATING COSTS 325
   
18.1 CAPITAL COST 325
18.2 MINE CAPITAL COSTS 326
18.3 PROCESS PLANT CAPITAL COST 330
18.4 DEWATERING CAPITAL COST 335
18.5 ENVIRONMENTAL CAPITAL COST 335
18.6 INDIRECTS 336
18.7 CONTINGENCY 337
18.8 OPERATING COST ESTIMATION 338
18.9 PROCESS OPERATING COSTS 347
18.10 GENERAL AND ADMINISTRATIVE OPERATING COSTS 351
   
19.0 ECONOMIC ANALYSIS 352
   
19.1 CAUTIONARY STATEMENT 352
19.2 METHODOLOGY USED 353
19.3 FINANCIAL MODEL PARAMETERS 353
19.4 CAPITAL COSTS 354
19.5 OPERATING COSTS 355


 

19.6 ROYALTIES 357
19.7 TAXES, DEPRECIATION AND DEPLETION 357
19.8 ECONOMIC RESULTS 358
19.9 SENSITIVITY ANALYSIS 361
   
20.0 ADJACENT PROPERTIES 367
   
20.1 MASON PROJECT 367
20.2 PUMPKIN HOLLOW PROJECT 367
   
21.0 OTHER RELEVANT DATA AND INFORMATION 369
   
21.1 ENVIRONMENTAL FOOTPRINT AND BENCHMARKING 369
21.2 ENVIRONMENTAL OPTIMIZATIONS DUE TO NUTON TECHNOLOGY 369
21.3 STAKEHOLDER ENGAGEMENT 370
   
22.0 INTERPRETATION AND CONCLUSIONS 371
   
22.1 YERINGTON COPPER PROJECT 371
22.2 PROCESS, INFRASTRUCTURE 372
22.3 MINING 372
22.4 HLF 372
22.5 ENVIRONMENTAL STUDIES, PERMITTING AND SOCIAL OR COMMUNITY IMPACT 373
   
23.0 RECOMMENDATIONS 375
   
23.1 GEOLOGY 375
23.2 GEOTECHNICAL 375
23.3 MINING 376
23.4 METALLURGY AND MINERAL PROCESSING 377
23.5 INFRASTRUCTURE 377
23.6 HLF 377
23.7 ENVIRONMENTAL 378
23.8 FEASIBILITY STUDY 379
   
24.0 REFERENCES 380
   
24.1 PROCESS, INFRASTRUCTURE 380
24.2 GEOLOGY AND MINE 380
24.3 HLF 384
24.4 ENVIRONMENTAL 384
   
25.0 RELIANCE ON INFORMATION PROVIDED BY THE REGISTRANT 386
   
26.0 APPENDICES 387
   
26.1 APPENDIX A - UNITS OF MEASURE AND ABBREVIATIONS AND ACRONYMS 387


 

List of Tables

Table 1.1: 2024 Drilling Yerington Copper Project 7
   
Table 1.2: 2024 Drilling MacArthur Project 9
   
Table 1.3: Yerington Copper Project Projected Recoveries by Deposit/Ore Type/Process. 10
   
Table 1.4: Mineral Reserve Estimate 10
   
Table 1.5: Yerington Copper Project Measured and Indicated Resources 11
   
Table 1.6: Yerington Copper Project Inferred Mineral Resources 11
   
Table 1.7: Yerington Copper Project Capital Cost Estimate 20
   
Table 1.8: Yerington Copper Project Operating Costs - Life of Mine 21
   
Table 1.9: Financial Evaluation 21
   
Table 2.1: Summary of Qualified Persons 23
   
Table 2.2: Dates of Site Visits 26
   
Table 3.1: Patented Claims 30
   
Table 3.2: Private Ground 32
   
Table 3.3: Lode and Placer Claims 32
   
Table 3.4: Optioned Private Ground (Lyon County) 60
   
Table 3.5: Existing Project Permits 61
   
Table 5.1: Yerington Mine Production 65
   
Table 5.2: Yerington Copper Project Mineral Resource Statement 67
   
Table 5.3: MacArthur Project - Summary of Mineral Resource 68
   
Table 5.4: VLT Mineral Resource Statement 68
   
Table 6.1: Yerington District Geology Stratigraphic Column 72
   
Table 7.1: 2011 Drilling Yerington Copper Project 91
   
Table 7.2: 2017/2022 Drilling Yerington Copper Project 92
   
Table 7.3: 2024 Drilling Yerington Copper Project 92
   
Table 7.4: MacArthur Drilling Used for 2021 Mineral Resource Estimate 94
   
Table 7.5: 2024 Drilling MacArthur Project 95
   
Table 7.6: Yerington and MacArthur Drilling Contractors by Year 97
   
Table 8.1: Summary of Analytical Packages and Laboratories 101


 

Table 8.2: Geochemical Reference Standard 105
   
Table 8.3: Lion CG 2011 QAQC Program Results 105
   
Table 8.4: 2017-2022 QAQC Program Results 106
   
Table 8.5: Yerington 2024 QAQC Program Results 107
   
Table 8.6: Standards Used on Lion CG Drilling through 2012 108
   
Table 8.7: MacArthur 2024 QAQC Program Results 110
   
Table 8.8: MacArthur 2024 QAQC Program Details 110
   
Table 9.1: Boxplot Summary for XRF and Laboratory Data, Cu ppm 118
   
Table 9.2: Arimetco VLT Production Summary 118
   
Table 9.3: August 2012 Highwall Backhoe Sampling 123
   
Table 9.4: August 2012 Backhoe Sampling Comparison 124
   
Table 10.1: Yerington Copper Project Projected Recoveries by Deposit/Ore Type/Process(1). 128
   
Table 10.2: Phase 1 Test Conditions and Summary Results 129
   
Table 10.3: Phase 1 Composites - Gangue Mineralogy 131
   
Table 10.4: Phase 1 Composites - Copper Mineral Speciation 131
   
Table 10.5: Nuton Scoping Series - S-23 Sulfide Stockpile 132
   
Table 10.6: Nuton Scoping Series - Yerington Life of Asset Blend #1 134
   
Table 10.7: Nuton Scoping Series - Yerington Life of Asset Blend #2 135
   
Table 10.8: SAPCu Test Results for VLT Test Samples 141
   
Table 10.9: Phase 2 Optimization Composite Gangue Mineralogy 143
   
Table 10.10: Phase 2 Optimization Composite Copper Mineral Speciation 143
   
Table 10.11: Nuton Phase 2 Optimization KPIs (1) 144
   
Table 10.12: 2011 METCON Metallurgical Test Work Program Summary 156
   
Table 10.13: MacArthur 2022 Test Work Results Summary 161
   
Table 10.14: Average MacArthur Assay by Size Fraction Results from McClelland 2022 and 2024 Test Work Programs 167
   
Table 10.15: Average Yerington assay by size fraction results from McClelland 2024 test work program 168
   
Table 10.16: KUZ-RAM modeled ROM fragmentation size distribution 168
   
Table 10.17: MacArthur Oxide Extraction Model Extrapolation for ROM Fragmentation 171


 

Table 10.18: Yerington Oxide Extraction Model Extrapolation for ROM Fragmentation 172
   
Table 11.1: Composite Statistics Table (TCu%) 178
   
Table 11.2: Variogram Parameters 179
   
Table 11.3: Yerington Model Parameters 180
   
Table 11.4: Summary of Sample Selection 181
   
Table 11.5: Search Ellipse Specifications 182
   
Table 11.6: Special Models 183
   
Table 11.7: Comparison of Grades by Interpolation Method 184
   
Table 11.8: Yerington Deposit Cut-off Grade Assumptions 187
   
Table 11.9: Yerington Deposit Pit Slope Assumptions 187
   
Table 11.10: Yerington Deposit Mineral Resource Statement 188
   
Table 11.11: VLT Model Parameters 191
   
Table 11.12: Residuals Cut-off Grade Assumptions 194
   
Table 11.13: VLT Mineral Resource Statement 195
   
Table 11.14: Comparison of 2021 and 2025 Mineral Resources 196
   
Table 11.15: Summary of Assay Intervals for Total Copper by Company 196
   
Table 11.16: Assay Cap Levels by Oxidation Zone 202
   
Table 11.17: Tonnage Factors Assigned to Block Model 206
   
Table 11.18: MacArthur Model Size and Location, September 2024 206
   
Table 11.19: Inputs to Definition of Pit-Constrained Mineral Resource - Recoveries 214
   
Table 11.20: Inputs to Definition of Pit-Constrained Mineral Resource - Costs 215
   
Table 11.21: Summary of Mineral Resource 217
   
Table 11.22: Mineral Resource by Domain 218
   
Table 11.23: Mineral Resource by Domain and Oxidation Zone 218
   
Table 12.1: Yerington Copper Project - Proven and Probable Reserves - May 31, 2025 220
   
Table 12.2: Pit Slope Parameters (Overall Angles) 221
   
Table 12.3: Pit Design Parameters (Detailed) 221
   
Table 12.4: Open Pit Optimization Parameters 221
   
Table 12.5: Yerington Copper Project Cutoffs 223
   
Table 12.6: Proven and Probable Reserves - May 31, 2025 225


 

Table 13.1: LG Shell Slope Parameters (Overall Angles) 235
   
Table 13.2: Open Pit Model Framework 235
   
Table 13.3: Open Pit Model Item Descriptions for Yerington 236
   
Table 13.4: Open Pit Model Item Descriptions for VLT 236
   
Table 13.5: Open Pit Model Item Descriptions for MacArthur 237
   
Table 13.6: Economic Pit Shell Parameters by Area 238
   
Table 13.7: Pit Phase Tonnages and Grades 240
   
Table 13.8: Pit Slope Design Criteria 241
   
Table 13.9: Annual Mining and Heap Leach Feed Schedule Details 251
   
Table 14.1: MacArthur Heap Leach Info. 275
   
Table 14.2: MacArthur Site Reagent Consumption 276
   
Table 14.3: MacArthur Site Total LOM Reagent Consumption 277
   
Table 14.4: Yerington Heap Leach Information 279
   
Table 14.5: Yerington Site Reagent Consumption 280
   
Table 14.6: Yerington Site Total Reagent Consumption 281
   
Table 14.7: Total Copper LOM Production 282
   
Table 14.8: Energy Requirement for Major Areas 282
   
Table 15.1: Estimated Yerington Pit Lake Dewatering and Discharge Rates 292
   
Table 15.2: HLF Phasing 301
   
Table 16.1: Copper Price Forecasting 307
   
Table 17.1: Anticipated Permit Requirements 309
   
Table 17.2: Major Existing Project Permits 310
   
Table 17.3: Summary of Water Rights for Yerington and Macarthur 314
   
Table 17.4: Potential Baseline Surveys and Studies 316
   
Table 18.1: Yerington Copper Project Capital Cost Estimate 325
   
Table 18.2: Capital Cost Estimate Responsibilities 326
   
Table 18.3: Major Mine Equipment - Capital Cost ($USD) 327
   
Table 18.4: Equipment Purchases - Initial and Sustaining 329
   
Table 18.5: Equipment Fleet Size 329
   
Table 18.6: Mining Capital Cost Estimate ($USD) 330


 

Table 18.7: Process Capital Cost Estimate 330
   
Table 18.8: Yerington Copper Project Infrastructure Capital Costs 333
   
Table 18.9: Yerington Copper Project Environmental Cost Estimate 335
   
Table 18.10: Indirect Percentages and Cost Estimate 337
   
Table 18.11: Project Area Contingency Percentages 338
   
Table 18.12: Yerington Copper Project Operating Costs - Life of Mine 338
   
Table 18.13: Open Pit Mine Staffing Requirements and Annual Salaries (Year 5) 339
   
Table 18.14: Hourly Labor Requirements and Annual Salary (Year 5) 340
   
Table 18.15: Maintenance Labor Factors (Maintenance per Operator) 341
   
Table 18.16: Major Equipment Operating Costs - no labor ($/h) 342
   
Table 18.17: Drill Pattern Specification 343
   
Table 18.18: Drill Productivity Criteria 343
   
Table 18.19: Design Powder Factors 343
   
Table 18.20: Loading Parameters - Year 5 344
   
Table 18.21: Haulage Cycle Speeds 344
   
Table 18.22: Support Equipment Operating Factors 345
   
Table 18.23: Open Pit Mine Operating Cost ($/t Total Material) 347
   
Table 18.24: Open Pit Mine Operating Cost ($/t Heap Feed) 347
   
Table 18.25: Process Operating Cost (MacArthur) 348
   
Table 18.26: Consumables and Reagents (MacArthur) 348
   
Table 18.27: Process Operating Cost (Oxide) 348
   
Table 18.28: Consumables and Reagents (Oxide) 349
   
Table 18.29: Process Operating Cost (Nuton) 349
   
Table 18.30: Consumables and Reagents (Nuton) 349
   
Table 18.31: Process Labor 350
   
Table 19.1: Economic Model Parameters 353
   
Table 19.2: Initial Capital Cost Summary 354
   
Table 19.3: Sustaining and Working Capital Cost Summary 355
   
Table 19.4: Scenario 1 Excess Acid Sales Life of Mine Operating Cost Summary 355
   
Table 19.5: Scenario 2 No Acid Sales Life of Mine Operating Cost Summary 356


 

Table 19.6: Depreciation Methods 357
   
Table 19.7: LOM Taxes 358
   
Table 19.8: Economic Model Results 358
   
Table 19.9: Scenario 1 Excess Acid Sales Cash Flow Summary 359
   
Table 19.10: Scenario 2 No Acid Sales Cash Flow Summary 360
   
Table 19.11: Copper Price Sensitivity - Scenario 1 Excess Acid Sales 361
   
Table 19.12: CAPEX Sensitivity (Initial + Sustaining) - Scenario 1 Excess Acid Sales 363
   
Table 19.13: OPEX Sensitivity - Scenario 1 Excess Acid Sales 364
   
Table 20.1: Mason Project Mineral Resource (Hudbay, 2023) 367
   
Table 20.2: Pumpkin Hollow Project, Underground Mineral Resource (2019) 368
   
Table 20.3: Pumpkin Hollow Project, Open Pit Mineral Resource (2019) 368
   
Table 23.1: Recommended Definitive Feasibility Study Budgets 375
   
Table 26.1: Units of Measure 387
   
Table 26.2: Abbreviations and Acronyms 390


 

List of Figures

Figure 1.1: Yerington Copper Project Site Layout 2
   
Figure 1.2: Yerington Diamond Drilling by Lion CG, 2011 to 2024 8
   
Figure 1.3: MacArthur Drilling by Lion CG (in 2024) 9
   
Figure 1.4: Yerington Pit Long Section 13
   
Figure 1.5: Yerington Pit Mine Phases 14
   
Figure 1.6: MacArthur Pit North-South Sections 15
   
Figure 1.7: MacArthur Pit Mine Phases 16
   
Figure 3.1: Yerington Copper Project Location 27
   
Figure 3.2: Regional Layout Map 28
   
Figure 6.1: Structural Geology Map of Western United States 69
   
Figure 6.2: Regional Geology Map with Cross-Section Intersecting Yerington Mine 71
   
Figure 6.3: Yerington Geology Section 2451250 E (Looking West) 77
   
Figure 6.4: MacArthur Property Geology East-West Cross Section 78
   
Figure 7.1: MacArthur 3-D Fastmag Model Target Map 81
   
Figure 7.2: Calculated Total Horizontal Gradient (THG) of the Susceptibility Model 82
   
Figure 7.3: 2009 IP/Resistivity Survey Lines 84
   
Figure 7.4: 2011 IP/Resistivity Survey Lines 85
   
Figure 7.5: IP Response from 2D Inversion (Section 309980 E) 86
   
Figure 7.6: Stacked Magnetic Profile 87
   
Figure 7.7: Yerington Historic Drilling Collar Plot 89
   
Figure 7.8: MacArthur Historic Drilling Collar Plot in Nevada State Plane Coordinates 90
   
Figure 7.9: Yerington Diamond Drilling by Lion CG 93
   
Figure 7.10: MacArthur Drilling by Lion CG (as of 2021) 94
   
Figure 7.11: MacArthur Drilling by Lion CG (as of 2024) 95
   
Figure 7.12: VLT Collar Plot 96
   
Figure 8.1: Core Sampling Facility 99
   
Figure 8.2: Lion CG Check Assay Results 106
   
Figure 8.3: Comparison of Total Cu Check Assays 109
   
Figure 8.4: MacArthur 2024 Check Assays 111


 

Figure 9.1: Yerington Property 113
   
Figure 9.2: YM-047A and YM-049 Core Box Labelling 113
   
Figure 9.3: YM-047A and YM-049 Footage Blocks and Tags 114
   
Figure 9.4: Check Assays Comparison 115
   
Figure 9.5: Additional Historic Drill Holes (Planview) 116
   
Figure 9.6: Validation Cross Section for Additional Historic Drill Hole S-20-D-17 (Looking NW) 117
   
Figure 9.7: CT1 Backhoe Sampling in 2011 119
   
Figure 9.8: CT1 Sample Location in 2024 119
   
Figure 9.9: 2011 Bench Sampling Locations 120
   
Figure 9.10: Shows the highwall backhoe sampling evidence on Bench 4520 viewed on the site visit in 2024. 122
   
Figure 9.11: Bench 4520 Highwall Backhoe Sampling 123
   
Figure 9.12: XRF vs Lab Analytical Results for Three Wet Sonic Twin Holes 125
   
Figure 9.13: Twin Hole Comparison 127
   
Figure 10.1: Plan View of Yerington Phase 1 Samples 130
   
Figure 10.2: Section View of Yerington Phase 1 Samples 131
   
Figure 10.3: Nuton Scoping Series - Yerington S-23 Stockpile Extraction and NAC vs. Leach Days 133
   
Figure 10.4: Nuton Scoping Series - Yerington LoA Blend #1 Extraction and NAC vs. Leach Days 134
   
Figure 10.5: Nuton Scoping Series - Yerington East #2, Central #2, West #2, and LoA Blend #2 Cu Extraction and NAC vs. Leach Days 136
   
Figure 10.6: W-3 Stockpile Total Copper Assay 137
   
Figure 10.7: W-3 Stockpile Acid Soluble Copper Component 138
   
Figure 10.8: W-3 Stockpile Cyanide Soluble Copper Component 138
   
Figure 10.9: W-3 Stockpile Recoverable Copper Component 139
   
Figure 10.10: W-3 Stockpile Acid Consumption 139
   
Figure 10.11: VLT Stockpile Total Copper 140
   
Figure 10.12: VLT Acid Soluble Copper 140
   
Figure 10.13: VLT Acid Soluble Copper to Total Copper 141
   
Figure 10.14: VLT SAPCu to Total Copper 142


 

Figure 10.15: Plan View of Yerington Phase 2 Samples 145
   
Figure 10.16: Section View of Yerington Phase 2 Samples 145
   
Figure 10.17: Nuton Technology Copper Extraction and Net Acid Consumption Phase 2 Test 146
   
Figure 10.18: Yerington Central Nuton Composite Actual Column Results vs Predictive Extraction Model (LCG18) 147
   
Figure 10.19: Yerington East Nuton Composite Actual Column Results vs Predictive Extraction Model (LCG19) 147
   
Figure 10.20: Yerington West Nuton Composite Actual Column Results vs Predictive Extraction Model (LCG20) 148
   
Figure 10.21: Phase 1 Yerington LoA Blend Hydraulic and Air Conductivity 148
   
Figure 10.22: Phase 1 LoA Blend Dry Bulk Density and Total Porosity 149
   
Figure 10.23: Phase 2 LoA Blend Air Conductivity 149
   
Figure 10.24: Phase 2 LoA Blend Hydraulic Conductivity 149
   
Figure 10.25: Phase 2 LoA Blend Total Porosity 150
   
Figure 10.26: Phase 2 LoA Blend Dry Bulk Density 150
   
Figure 10.27: Yerington 2024 Composites Sequential Assay Results and Copper Distribution by Sequential Assays 151
   
Figure 10.28: Yerington 2024 Copper Extraction Summary 152
   
Figure 10.29: Yerington 2024 Copper Extraction Kinetic Leach Results 152
   
Figure 10.30: Yerington 2024 Calculated Copper Head Grade Summary 153
   
Figure 10.31: Yerington 2024 Gross Acid Consumption Summary 153
   
Figure 10.32: Yerington 2024 Net Acid Consumption Summary 154
   
Figure 10.33: Yerington 2024 Specific Acid Consumption Summary 154
   
Figure 10.34: METCON 2011 copper head grade summary statistics 157
   
Figure 10.35: METCON 2011 Head Grade, Recoverable Copper, Copper Extraction, and Median Copper Sequential Distribution Results for 31 METCON Columns 158
   
Figure 10.36: METCON 2011 Copper Extraction Summary 159
   
Figure 10.37: METCON 2011 Kinetic Copper Extraction Column Results 160
   
Figure 10.38: METCON 2011 gangue (net) acid consumption summary statistics 161
   
Figure 10.39: MacArthur 2022 Kinetic Column Leach Rate Data, McClelland 2022 162
   
Figure 10.40: MacArthur 2024 Composite Clustering Analysis Outputs 163


 

Figure 10.41: MacArthur 2024 Composites Sequential Assay Results and Copper Distribution by Sequential Assays, McClelland 2024 164
   
Figure 10.42: MacArthur 2024 Copper Extraction Summary, McClelland 2024 165
   
Figure 10.43: MacArthur 2024 Kinetic Column Copper Extraction Results, McClelland 2024 165
   
Figure 10.44: MacArthur 2024 Calculated Copper Head Grade Summary, McClelland 2024 166
   
Figure 10.45: MacArthur 2024 Gross Acid Consumption Summary, McClelland 2024 166
   
Figure 10.46: MacArthur 2024 Net Acid Consumption Summary, McClelland 2024 167
   
Figure 10.47: MacArthur Total Copper Grade Distribution for the Average Head Samples 169
   
Figure 10.48: Yerington Total Copper Grade Distribution for the average Head Samples 170
   
Figure 10.49: MacArthur Oxide Extraction by Particle Size for Sequential Copper Sizes 170
   
Figure 10.50: Yerington Oxide Extraction by Particle Size for Sequential Copper Sizes 171
   
Figure 10.51: Historic Yerington Heap Leach Ultimate Recovery. Curve is overall heap recovery after each operational year. 173
   
Figure 11.1: Contact Grade Analysis (TCu%) 176
   
Figure 11.2: Boxplot of Assays Reported by Recovery (TCu%) 177
   
Figure 11.3: Log Probability Plot by Domain (TCu%) 178
   
Figure 11.4: Yerington Copper Project Planview 5 ft. Contours 180
   
Figure 11.5: Rock Type Section 2451250 E (Looking West ±100 ft.) 181
   
Figure 11.6: Sulfide Material Search Ellipsoids 182
   
Figure 11.7: TCu% - 3800 ft. Plan (±25 ft.) 183
   
Figure 11.8: TCu% -- Section 2450000 E (Looking West ±50 ft.) 184
   
Figure 11.9: Plan Swath Plot Comparing CUNN1 (NN) and TCUK1 (OK) Grades 185
   
Figure 11.10: Plan Swath Plot Comparing CUID1 (ID2) and TCUK1 (OK) Grades 185
   
Figure 11.11: Resource Classification - Plan 3800 ft. Elevation 186
   
Figure 11.12: Yerington Residuals Collar Plot 189
   
Figure 11.13: VLT Assays, TCu% 190
   
Figure 11.14: VLT Assays, ASCu% 190
   
Figure 11.15: VLT 10 ft. Composites (TCu%) 191
   
Figure 11.16: VLT Section Block Model ID2 vs Drill Hole Composite TCu% Grade 192


 

Figure 11.17: VLT Swath Plot by Elevation 193
   
Figure 11.18: VLT Resource Classification (Planview) 194
   
Figure 11.19: Drill Holes with Logged Redox 198
   
Figure 11.20: Basic Statistics of Capped Total Copper Assays 199
   
Figure 11.21: Probability Plots of Capped Total Copper Assays 200
   
Figure 11.22: Probability Plots of Acid Soluble Copper Assays 201
   
Figure 11.23: Basic Statistics of 25-foot Irregular Composites 203
   
Figure 11.24: Oxide Zone Variogram 204
   
Figure 11.25: Mixed Zone Variogram 205
   
Figure 11.26: MacArthur Block Model Domains and Drillhole Collar Locations 207
   
Figure 11.27: East-West Cross-Section Looking North at 14,688,000 North 209
   
Figure 11.28: North-South Cross-Section Looking West at 2,439,000 East - Through MacArthur & North Ridge 210
   
Figure 11.29: North-South Cross-Section Total Copper Grade Looking West at 2,439,000 East - Through MacArthur & North Ridge 212
   
Figure 11.30: Cumulative Frequence of Copper Grades in Oxide Zone 213
   
Figure 11.31: MacArthur Mineral Resource Pit Shell 216
   
Figure 13.1: Structural Domains of the North Wall of the Yerington Pit 229
   
Figure 13.2: Observed Wedge Failures in South Wall 230
   
Figure 13.3: Yerington North Highwall Stereonet 230
   
Figure 13.4: Yerington South Highwall Stereonet 231
   
Figure 13.5: North Highwall Global Stability 231
   
Figure 13.6: South Highwall Global Stability 232
   
Figure 13.7: Aerial imagery showing configuration of MacArthur open pit as of December, 2020. 233
   
Figure 13.8: North Highwall Stereonet for MacArthur Open Pit 233
   
Figure 13.9: South Highwall Stereonet for MacArthur Open Pit 234
   
Figure 13.10: Global Stability Analysis for the North and South Highwalls of the MacArthur Open Pit 234
   
Figure 13.11: Yerington Profit vs. Price by Pit Shell 239
   
Figure 13.12: MacArthur Profit vs Price by Pit Shell 240


 

Figure 13.13: Yerington Phase 1 and 2 Designs 242
   
Figure 13.14: Yerington Phase 3 Design 243
   
Figure 13.15: Yerington Phase 4 Design 244
   
Figure 13.16: VLT Pit Design 245
   
Figure 13.17: MacArthur Pit 246
   
Figure 13.18: Gallagher Pit 246
   
Figure 13.19: North Ridge Pit Phase 1 247
   
Figure 13.20: North Ridge Pit Phase 2 247
   
Figure 13.21: Yerington Waste Rock Storage Facility and Heap Leach Facilities 248
   
Figure 13.22: MacArthur Waste Rock Storage Facility and Oxide ROM Heap Leach Facility 249
   
Figure 13.23: Annual Heap Leach Tonnages (Type and Area) 250
   
Figure 13.24: Annual Feed Grade by Type and Area 250
   
Figure 13.25: End of Year 1 - MacArthur Area 254
   
Figure 13.26: End of Year 2 - MacArthur Area 255
   
Figure 13.27: End of Year 2 - Yerington Area 256
   
Figure 13.28: End of Year 3 - MacArthur Area 257
   
Figure 13.29: End of Year 3 - Yerington Area 258
   
Figure 13.30: End of Year 4 - MacArthur Area 259
   
Figure 13.31: End of Year 4 - Yerington Area 260
   
Figure 13.32: End of Year 5 - MacArthur Area 261
   
Figure 13.33: End of Year 5 - Yerington Area 262
   
Figure 13.34: End of Year 6 - MacArthur Area 263
   
Figure 13.35: End of Year 6 - Yerington Area 264
   
Figure 13.36: End of Year 7 - Yerington Area 265
   
Figure 13.37: End of Year 8 - Yerington Area 266
   
Figure 13.38: End of Year 9 - Yerington Area 267
   
Figure 13.39: End of Year 10 - Yerington Area 268
   
Figure 13.40: End of Year 11 - Yerington Area 269
   
Figure 13.41: End of Year 12 - Yerington Area 270


 

Figure 14.1: Yerington Copper Project Process Flow Diagram 274
   
Figure 14.2: MacArthur Site Solvent Extraction Facility General Layout 276
   
Figure 14.3: Yerington Site Solvent Extraction Facility General Layout 278
   
Figure 15.1: Yerington Copper Project Site 285
   
Figure 15.2: MacArthur Site 287
   
Figure 15.3: Potential Location for MacArthur Pit Dewatering and Monitoring Wells 288
   
Figure 15.4: Yerington Site 290
   
Figure 15.5: Potential Location for Yerington Pit Dewatering Wells 294
   
Figure 15.6: Truck Shop General Layout 295
   
Figure 15.7: Administrative Trailer General Layout 296
   
Figure 15.8: Yerington Site Power Distribution 298
   
Figure 15.9: MacArthur Site Power Distribution 299
   
Figure 15.10: MacArthur Starter and Ultimate HLF 302
   
Figure 15.11: Yerington West Starter and Ultimate HLF 303
   
Figure 15.12: Yerington East Starter and Ultimate HLF 304
   
Figure 16.1: 1-Yr Trailing Historic LME Copper Price 307
   
Figure 16.2: 1-Yr Trailing West Cost Sulfuric Acid Market Price 308
   
Figure 19.1: Scenario 1 Excess Acid Sales OPEX Split 356
   
Figure 19.2: Scenario 2 No Acid Sales OPEX Split 356
   
Figure 19.3: Copper Price per Pound Sensitivity on NPV 7% (Pre-tax, Scenario 1 Excess Acid Sales) 362
   
Figure 19.4: Copper Price per Pound Sensitivity on IRR (Pre-tax, Scenario 1 Excess Acid Sales) 363
   
Figure 19.5: Multiple % Sensitivity on NPV @ 7% (Pre-tax, Scenario 1 Excess Acid Sales) 364
   
Figure 19.6: Multiple % Sensitivity on NPV @ 7% (Post-tax, Scenario 1 Excess Acid Sales) 365
   
Figure 19.7: Multiple % Sensitivity on IRR (Pre-tax, Scenario 1 Excess Acid Sales) 366
   
Figure 19.8: Multiple % Sensitivity on IRR (Post-tax, Scenario 1 Excess Acid Sales) 366


 

1.0 EXECUTIVE SUMMARY

Lion Copper and Gold Corp. (Lion CG) is a mine development company advancing the Yerington Copper Project in Lyon County, Nevada, defined as the Yerington deposit, VLT stockpile, North Ridge pit, Gallagher pit and MacArthur pit.

The Pre-feasibility Study (PFS) draws upon Measured and Indicated resources from the Yerington deposit, Vat Leach Tailings (VLT) stockpile, and MacArthur deposit areas, which have been converted to reserves. The mineral reserves are comprised of Proven 225.6 Mtons grading 0.23% copper and Probable 281.0 Mtons grading 0.20% copper for a total of 506.6 Mtons grading 0.21% copper.

The PFS indicates that the Yerington Copper Project holds potential for phased open-pit mining with heap leach extraction. The Yerington pit would feed oxide and sulfide material to two adjacent but separate Heap Leach Facilities (HLF). The sulfide material would go to a dedicated sulfide HLF equipped with a 35 Mtpa crushing and agglomerating system that employs mobile conveyors for stacking material. The sulfide HLF will utilize the Nuton™ process from Nuton Technology™. The Yerington oxide material would be placed on a separate oxide HLF as run-of-mine (ROM) from the Yerington pit and the residuals. Approximately 5 miles north of the Yerington pit, ROM oxide material from the North Ridge pit, the Gallagher pit, and the MacArthur pit will be stacked on an additional oxide HLF adjacent to the MacArthur deposit.

The total material stacked (sulfide and oxide) would amount to 506.6 Mtons with a grade of 0.21% total copper. Of this, the sulfide tonnage of 233.8 Mtons with a grade of 0.26% copper would undergo crushing and agglomeration before placement on the Nuton Technology™ HLF. The remaining oxide tonnage of 272.8 Mtons with a grade of 0.17% copper would be situated on the two separate oxide HLFs. The processing facilities would include two separate conventional solvent extraction (SX) circuits, one at MacArthur and one at Yerington, with a single combined electrowinning (EW) co-located with the Yerington SX. The proposed site layout illustrating the locations of proposed mining and processing facilities is depicted in Figure 1.1.


 

Figure 1.1: Yerington Copper Project Site Layout

1.1 LOCATION AND PROPERTY DESCRIPTION

The Yerington Copper Project ("Project") is located near the geographic center of Lyon County, Nevada, U.S.A., along the eastern flank of the Singatse Range. The Project includes both the historical Yerington Property, and the historic MacArthur open pit located 5 miles to the northwest. The Yerington Property is bordered on the east by the town of Yerington, Nevada, which provides access via a network of paved and gravel roads that were used during previous mining operations.


 

The Project consists of 5 fee simple parcels and 82 patented mining claims totaling 2,768 acres, and 1,155 unpatented lode and placer claims totaling 23,697 acres. The unpatented claims are located on lands administered by the U.S. Department of Interior, Bureau of Land Management (BLM).

1.2 HISTORY

1.2.1 Yerington

Recorded production in the Yerington mining district dates back to 1883 (Moore, 1969) as prospectors were attracted to and investigated colorful oxidized copper staining throughout the Singatse Range. Knopf (1918) reported that oxidized copper cropped out at the historic Nevada-Empire mine located above the south center of the present-day Yerington open pit. Knopf does not show or reference other mines or prospects underlain by the Yerington open pit footprint, as gravel and alluvial cover obscure bedrock over an approximate 0.75-mile radius around the Nevada-Empire Mine.

Information is sparse for the period from Knopf's reporting in 1918 until World War II, although it is likely that mineral leases were worked in the Nevada-Empire during spikes in the copper price. Private reports (Hart, 1915, and Sales, 1915) describe ore shipments and planned underground exploration from a northwest striking, southwest dipping structure at the historic Montana-Yerington Mine area located approximately one mile west of the present-day Yerington pit.

During the 1940s, Anaconda outlined a deposit in the current Yerington pit. During the early 1950s, the US government, citing the need for domestic copper production, offered "start-up" subsidies to Anaconda to open a copper mine in the Yerington district. Anaconda sank two approximately 400-foot-deep shafts in the present-day Yerington open pit area and drove crosscuts to obtain bulk samples of oxidized rock for metallurgical study. Anaconda began operating the Yerington Mine in 1952 and mined continually through 1979, producing approximately 1.744 billion pounds of copper from 162 million tons averaging 0.54% Cu. Approximately 104 million tons of this total was from oxidized copper mineralization that was "vat leached" with sulfuric acid in 13,000-ton cement vats on a seven-day leach cycle. Sulfide mineralization was concentrated on site in a facility that was dismantled and sold following termination of mining in 1979. The cement copper and sulfide concentrates were shipped to the Anaconda's smelter in Montana.

In 1976, all assets of Anaconda, including the Yerington Mine, were purchased by Atlantic Richfield Company (ARC), which shut down dewatering pumps in the pit and closed the Yerington Mine in 1979 due to low copper prices. 

The Yerington Mine site and adjacent Weed Heights mining camp were acquired by CopperTek, a private Yerington company owned by Mr. Don Tibbals, in 1982. In the mid-1980's CopperTek began reprocessing W-3 waste rock and Vat Leach Tailings (VLT) on Heap Leach Pads (HLPs) and a Solvent Extraction-Electro Winning (SX/EW) plant to produce cathode copper. In 1989, Arimetco purchased the mine property from CopperTek, commissioned a 50,000-pound-per-day SX/EW plant, and began heap leaching mineralized material at the Yerington site. Arimetco processed W-3 waste rock and VLTs on newly constructed HLPs as well as trucking oxide ore from the MacArthur Mine, located approximately five miles north of the Yerington Mine site. Arimetco produced some 95 million pounds of copper from 1989 to 1999 before declaring bankruptcy in 1997 due to low copper prices (Sawyer, 2011). Arimetco terminated mining operations in 1997 and abandoned the property in early 2000.


 

In early 2000 the Nevada Department of Environmental Protection (NDEP) assumed operation of the site on a care and maintenance basis, primarily to ensure that HLP drain down solutions would continue to be maintained.

Following four years of due-diligence studies and negotiations with State and federal agencies, the property was acquired by Lion CG from the Arimetco bankruptcy court in April 2011, after receiving bonafide prospective purchaser (BFPP) letters from the US Environmental Protection Agency (USEPA) and Nevada Division of Environmental Protection (NDEP). BLM to protect Lion CG from historic liabilities associated with the former mine owners and operations.

1.2.2 MacArthur

The most recent mining at MacArthur occurred between 1995 and 1997, when Arimetco mined a limited tonnage of surface oxide copper for heap leaching at the Yerington Mine Site. The historic metallurgical test work performed on material from the MacArthur deposit is dated and focused on leach performance of material typical of what was historically mined from the MacArthur pit. Anaconda, Bateman Engineering (Bateman), and Mountain States R&D International (Mountain States) have all performed various metallurgical test work for the MacArthur deposit.

1.3 GEOLOGY

The Project includes the Yerington Deposit, MacArthur Deposit and a portion of the Bear Property which represents three of four known porphyry copper deposits in the Yerington district. The other is the Mason copper-molybdenum property located 2.5 miles to the west. All the deposits are hosted in Middle Jurassic intrusive rocks of the Yerington Batholith.

Copper mineralization occurs in all three phases of the Yerington Batholith. Intrusive phases, from oldest to youngest, are known as the McLeod Hill Quartz Monzodiorite (field name granodiorite), the Bear Quartz Monzonite, and the Luhr Hill Granite, the source of quartz monzonitic (i.e. granite) porphyry dikes related to copper mineralization.

Following uplift and erosion, a thick Tertiary volcanic section was deposited, circa 18-17 Ma. This entire rock package was then extended along northerly striking, down-to-the-east normal faults that flatten at depth, creating an estimated 2.5 miles of west to east dilation-displacement (Proffett and Dilles, 1984). The extension rotated the section such that the near vertically emplaced batholiths were tilted 60° to 90° westerly. Pre-tilt, flat-lying Tertiary volcanics now crop out as steeply west dipping units in the Singatse Range west of the Property. The easterly extension thus created a present-day surface such that a plan map view represents a cross-section of the geology.


 

1.4 MINERALIZATION

1.4.1 Yerington

The Yerington Mine produced approximately 162 million tons of ore grading 0.54% Cu, of which oxide copper mineralization amenable to leaching accounted for approximately 104 million tons. A 1971 snapshot of head grades shows oxide mill head grade averaging 0.53% Cu and sulfide grades ranging from 0.45% to 0.75% Cu (D. Heatwole, personal communication).

The general geometry of copper mineralization below the Yerington pit is an elongate body extending 6,600 ft along a strike of S62ºE. The modeled mineralization has an average width of 2,000 ft and has been defined by drilling to an average depth of 400-500 ft below the pit bottom at the 3,500-foot elevation.

The copper mineralization and alteration throughout the Yerington district and at the Yerington Property are unusual for porphyry copper camps in that the mineralization occurs in WNW striking bands or stripes between materials of lesser grade. Much of this geometry is influenced by the strong district-wide WNW structural grain observed in fault, fracture and porphyry dike orientations. Altered mineralized bands range in width from tens of ft to 200-foot-wide mineralized porphyry dikes mined in the Yerington pit by Anaconda.

Oxide copper occurred throughout the extent of the Yerington pit; attracting the early prospectors who sank the Nevada-Empire shaft on copper showings located over the present-day south-central portion of the pit. To extract the copper oxides, Anaconda produced sulfuric acid on site, utilizing native sulfur mined and trucked from Anaconda's Leviathan Mine located approximately 50 miles southwest of Yerington.

Greenish-blue chrysocolla (CuSiO3.2H20) was the dominant copper oxide mineral occurring as fracture coatings and fillings, easily amenable to an acid leach solution. Historic Anaconda drill logs note lesser neotocite, aka black copper wad (Cu, Fe, Mn), SiO2 and rare tenorite (CuO) and cuprite (Cu2O). Oxide copper also occurs in iron oxide/limonite fracture coatings and selvages.

Chalcopyrite (CuFeS2) was the dominant copper sulfide mineral occurring with minor bornite (Cu5FeS4) primarily hosted in A-type quartz veins in the older porphyry dikes and in quartz monzonite and granodiorite, as well as disseminated between veins in host rock at lesser grade. The unmined mineralized material below the current pit bottom is primarily of chalcopyrite mineralization.

1.4.2 MacArthur

The MacArthur deposit is a large copper mineralized system containing near-surface acid soluble copper mineralization (IMC, 2022).

The MacArthur deposit consists of a 50 to 150-ft thick, tabular zone of secondary copper (oxides and/or chalcocite) covering an area of approximately two square miles. Limited drilling has also intersected underlying primary copper mineralization open to the north, but only partially tested to the west and east.

Oxide copper mineralization is most abundant and particularly well exposed in the walls of the legacy MacArthur pit. The most common copper mineral is chrysocolla (CuSiO32H2O). Also present is black copper wad, neotocite, ((Cu,Fe,Mn)SiO2)) and trace cuprite (Cu2O) and tenorite (CuO). The flat-lying zones of oxide copper mirror topography, exhibit strong fracture control and range in thickness from 50 to 100 ft. Secondary chalcocite mineralization forms a blanket up to 50 ft or more in thickness that is mixed with and underlies the oxide copper. Primary chalcopyrite mineralization has been intersected in several locations mixed with and below the chalcocite. The extent of the primary copper is unknown as many of the holes bottomed at 400 ft or less.


 

1.5 EXPLORATION AND DIAMOND DRILLING

During the 1952 to 1979 period of mine operation at the Yerington Mine, Anaconda completed a number of geophysical surveys, including an aeromagnetic survey, a ground magnetic survey, and multiple Induced Polarization (IP) surveys. Published gravity data were examined to estimate alluvial thicknesses in Mason Valley east of the Project. These surveys covered much more additional ground than current Project area.

1.5.1 Geophysics

2007 Helicopter Magnetometer Survey

In late 2007 and early 2008, Quaterra contracted a helicopter magnetometer survey conducted over the Yerington district (EDCON-PRJ, 2008). The survey was flown with a line spacing of 100 m separation with some areas in-filled to 50 m separation. A total of 2,685-line miles of new aeromagnetic data were acquired and 4,732-line miles of older data were digitized. This improved data set has been used extensively by Lion CG throughout the district to identify new targets as well as refine targets previously identified by Anaconda.

2009 Ground Geophysical Survey

Zonge Geosciences Inc. performed IP and Resistivity and Ground Magnetic surveys for Lion CG on the MacArthur Project, located in Lyon County, Nevada. The IP/Resistivity survey was conducted in 2009 from October to December. The Ground Magnetic survey was conducted during the period of 4-7 November 2009 (Zonge, 2009b).

Dipole-dipole IP/Resistivity data were acquired on three lines using a dipole length of 200 meters and 300 meters. Pole-dipole IP/Resistivity data were acquired on four lines using a dipole length of 150 meters and 200 meters. Line locations were established by Quaterra and Zonge personnel using handheld Garmin GPS receivers with real time differential corrections provided by Wide Area Augmentation System (WAAS). The surveys identified multiple targets for future exploration.

2009 Ground Magnetic Survey

Zonge Geosciences, Inc. performed GPS-based ground magnetic (Zonge, 2009a) and Induced Polarization and Resistivity surveys (Zonge, 2009b) for Lion CG on the MacArthur Project during November 2009. Ground Magnetic/GPS data were acquired on six lines-oriented north/south for a total distance of 31.8 line-kilometers of data acquisition.

Total field magnetic data were acquired with a GEM Systems GSM-19 Overhausereffect magnetometer. Positioning was determined with Trimble PRO-XRS GPS receivers that utilize the integrated real-time DGPS beacon for position corrections.


 

2011 Ground Geophysical Survey

Zonge International Inc. conducted a pole-dipole Complex Resistivity IP (CRIP) investigation for Lion CG on the MacArthur property during the period from 5 February through 7 March 2011. Pole-Dipole CRIP data were acquired on 7 lines for a total coverage of 37.0 line-km and 210 collected stations (Zonge, 2011). The surveys identified multiple targets for future exploration.

2012 Helicopter Magnetometer Survey

A more detailed helicopter magnetic survey was flown by Geosolutions Party Ltd., in April of 2012, north and northwest of the MacArthur pit area.  By design this system had a broader frequency bandwidth then previous systems and was ideal for modeling purposes. The line spacing was 50 meters and a terrain clearance of approximately 30 meters was flown. The near surface volcanic response is mapped and a weak, possible alteration low, was identified from the processed data. Subsequently this low was interpreted as a deep intrusive (Weis, 2012).

2016/2017 Ground Geophysical Survey

Zonge conducted an induced polarization-resistivity survey for Lion CG during November 2016, and February 2017 (Zonge International, 2017). Data were acquired along eight lines using Dipole-Dipole and Pole-Dipole arrays.

One line crossed over the Yerington pit. The total length of the line was 5.4 km of which approximately 600 m was in the pit itself. Data quality was good and four anomalous IP zones were detected. Two additional anomalies were detected north of the pit, one within the mine waste dumps and one in the area known as Groundhog Hills.

1.5.2 Yerington Site Drilling

Diamond drilling was completed at Yerington in 2024 totaling 3,458 ft of drilling in four core drill holes Table 1.1) which were targeted for expansion and resource upgrade.

Table 1.1: 2024 Drilling Yerington Copper Project
Drill Hole Year Drilled Azimuth Dip Total Depth (ft) Purpose Type
YM-047 2024 210 -45 1083.5 Expl Core
YM-047A 2024 210 -45 470.0 Expl Core
YM-048 2024 210 -45 1270.0 Expl Core
YM-049 2024 210 -45 634.0 Expl Core

Figure 1.2 illustrates all the drilling conducted by Lion CG relative to the current topography and Yerington Pit.


 

Source: AGP 2025

Notes: Drill holes projected on current topography

Figure 1.2: Yerington Diamond Drilling by Lion CG, 2011 to 2024

1.5.3 Macarthur Site Drilling

In 2024, drilling was focused on continuing upgrading the resource within and around the main portion of MacArthur. Drilling consisted of 18 reverse circulation (RC) drill holes, totaling 6,165 ft (Figure 1.3 and Table 1.2). RC drilling was conducted by Alford Drilling, LLC of Elko, NV. Downhole surveys were recorded every 5 ft working in continuous mode.


 

Source: IMC 2025

Figure 1.3: MacArthur Drilling by Lion CG (in 2024)

Table 1.2: 2024 Drilling MacArthur Project
Drill Hole Year Drilled Azimuth Dip Total Depth (ft) Purpose Type
QM-343 2024 180 -60 280 Expl RC
QM-344 2024 180 -60 330 Expl RC
QM-336 2024 0 -90 130 Expl RC
QM-337 2024 180 -60 310 Expl RC
QM-338 2024 180 -60 325 Expl RC
QM-339 2024 180 -60 350 Expl RC
QM-340 2024 180 -60 340 Expl RC
QM-341 2024 180 -50 600 Expl RC
QM-342 2024 180 -60 520 Expl RC
QM-342A 2024 180 -60 700 Expl RC
QM-345 2024 180 -60 200 Expl RC
QM-346 2024 180 -60 130 Expl RC
QM-347 2024 180 -60 200 Expl RC
QM-348 2024 0 -90 345 Expl RC
QM-349 2024 180 -70 495 Expl RC
QM-350 2024 180 -60 230 Expl RC
QM-351 2024 180 -60 290 Expl RC
QM-352 2024 0 -90 390 Expl RC


 

1.6 MINERAL PROCESSING AND METALLURGICAL TESTING

Metallurgical copper extraction estimates for the Project are summarized in Table 1.3 These projections are based on metallurgical test campaigns and data from historical operations at the Yerington project site.

Table 1.3: Yerington Copper Project Projected Recoveries by Deposit/Ore Type/Process.
Deposit Feed Type Crush Size TCu
Extraction
TCu Recovery w/
Operational
Scale-up Factor
Net Acid
Consumption
(lb./t)
MacArthur Oxide: MacArthur ROM 64% 59% 20
Oxide: Gallagher ROM 54% 46% 42
Oxide: North Ridge ROM 55% 46% 38
Yerington Oxide ROM 74% 68% 15
Residual: VLT As Received 75% 69% 15
Primary Sulfide 0.5-in. p80 77% 73% 30

1.7 MINERAL RESERVES AND RESOURCE ESTIMATION

The PFS includes the first Mineral Reserve estimate for the Project. The PFS is based on Mineral Reserves. The reserve estimate is based on pit designs using a copper price of $3.90/lb with cut-off grades ranging from 0.03 to 0.07% CuT for oxide material and 0.09% CuT for sulfide material.

1.7.1 Mineral Reserves

Table 1.4: Mineral Reserve Estimate
Pit Area Proven Probable Total
Ore Type Tons (kt) Grade
(Cu%)
Copper
Mlbs
Tons (kt) Grade
(Cu%)
Copper
Mlbs
Tons (kt) Grade
(Cu%)
Copper
Mlbs
Yerington Pit/VLT
Oxide 34,295 0.22 148.3 73,681 0.13 193.1 107,976 0.16 341.5
Sulfide 81,037 0.30 481.1 152,761 0.24 732.3 233,798 0.26 1,213.3
MacArthur Area
Oxide 110,224 0.19 411.7 54,553 0.16 173.5 164,777 0.18 585.2
Sulfide - - - - -        
Total Oxide 144,519 0.19 560.0 128,234 0.14 366.7 272,753 0.17 926.7
Total Sulfide 81,037 0.30 481.1 152,761 0.24 732.3 233,798 0.26 1,213.3
Total Reserve 225,556 0.23 1,041.1 280,995 0.20 1,099.0 506,551 0.21 2,140.0

Note: This Mineral Reserve estimate has an effective date of May 31, 2025, and is based on the mineral resource estimates for Yerington and VLT dated March 17, 2025 by T. Maunula & Associates Consulting Inc. and MacArthur Area Pits dated March 17, 2025 by Independent Mining Consultants Inc. The Mineral Reserve estimate was completed under the supervision of Gordon Zurowski, P.Eng. of AGP, who is a Qualified Person as defined under S-K 1300. Mineral Reserves are stated within the final pit designs based on a $3.90/lb copper price.

1. The copper cutoff grades used were:

Yerington Pit - 0.05% copper (oxide ROM), 0.09% copper (sulfide)

Vat Leach Tailings (VLT) Pit - 0.03% copper (oxide ROM)


 

MacArthur - 0.05% copper (oxide ROM)

Gallagher Pit - 0.07% copper (oxide ROM)

North Ridge Pit - 0.06% copper (oxide ROM)

2. Open pit mining costs varied by area and elevation with waste of $2.53/t, oxide material at $2.49/t and sulfide at $2.22/t.  Incremental costs of $0.027/25ft bench were applied below the 4225 foot elevation for waste and oxide and 0.024/t for sulfide material below the 4225 foot elevation.

3. Processing costs were based on the use of an acid plant at site with crushing for sulfide material.  The processing costs by pit area were:

Yerington Pit - $2.00/t ore (oxide ROM), $4.44/t (sulfide)

VLT Pit - $1.34/t ore (oxide ROM)

MacArthur - $1.67/t ore (oxide ROM)

Gallagher Pit - $2.14/t ore (oxide ROM)

North Ridge Pit - $1.73/t ore (oxide ROM)

G&A costs were $0.49/t ore.

4. Process copper recoveries varied by material and area and were as follows:

Yerington Pit - 70% (oxide ROM), 74% (sulfide)

VLT Pit - 75% (oxide ROM)

MacArthur - 55% (oxide ROM)

Gallagher Pit - 54% (oxide ROM)

North Ridge Pit - 55% (oxide ROM)

1.7.2 Mineral Resources (Inclusive of Mineral Reserves)

Table 1.5: Yerington Copper Project Measured and Indicated Resources
Pit Area Measured Indicated Measured + Indicated
Resource
Type
Tons (kt) Grade
(Cu%)
Copper
Mlbs
Tons
(kt)
Grade
(Cu%)
Copper
Mlbs
Tons (kt) Grade
(Cu%)
Copper
Mlbs
Yerington Pit/VLT
Oxide 37,531 0.21 157.6 96,556 0.13 257.9 134,087 0.16 417.0
Sulfide 84,163 0.30 505.0 263,230 0.22 1,158.2 347,393 0.24 1,663.2
MacArthur Area
Oxide 163,333 0.18 577.8 155,086 0.15 471.6 318,419 0.17 1,049.4
Sulfide - - - - - - - - -
Total
Oxide Total 200,864 0.19 735.4 251,642 0.15 729.4 452,506 0.16 1,464.9
Sulfide Total 84,163 0.30 505.0 263,230 0.22 1,158.2 347,393 0.24 1,663.2
Total 285,027 0.22 1,240.4 514,872 0.18 1,887.6 799,899 0.20 3,129.0

Table 1.6: Yerington Copper Project Inferred Mineral Resources
Pit Area Inferred
Resource Type Tons (kt) Grade (Cu %) Copper Mlbs
Yerington Pit/VLT
Oxide 67,338 0.11 145.8
Sulfide 67,576 0.17 229.8
MacArthur Area
Oxide 23,169 0.15 67.9
Sulfide - - -
Total


 

Table 1.6: Yerington Copper Project Inferred Mineral Resources
Oxide Total 90,507 0.12 213.6
Sulfide Total 67,576 0.17 229.8
Total 158,083 0.14 443.4

Notes:

1. Mineral Resources are reported in situ for Yerington and MacArthur and the effective date is March 17, 2025. The VLT Mineral Resources are not in situ and the effective date is March 17, 2025. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. There is no certainty that all or any part of the Mineral Resource estimate will be converted into Mineral Reserves.  The Mineral Resource Estimate of Yerington and the VLT was performed by Mr. Tim Maunula, P. Geo of T. Maunula & Associates Consulting and the MacArthur Area Pits by Mr. Herb Welhener, MMSA-QPM, Vice President of Independent Mining Consultants Inc. Both responsible parties are both Qualified Persons under S-K 1300 standards. All figures are rounded to reflect the relative accuracy of the estimates and totals may not add correctly.

2. Mineral Resources of the Yerington pit area are reported within a conceptual pit shell that used the following input parameters: a variable break-even economic cut-off grade of 0.04 % TCu and 0.08% TCu, for oxide and sulfide material respectively, based on assumptions of a net copper price of US$4.22 per pound (after transportation and royalty charges), 70% recovery in oxide material, 74% recovery in sulfide material, base mining costs of $2.49/st for oxide and $2.22/st for sulfide, and processing plus G&A costs of $2.00/st for oxide and $4.44/st for sulfide.

3. Mineral Resources of the VLT are reported within a conceptual pit shell that used the following input parameters: a break-even cut-off grade of 0.03 % TCu based on assumptions of a net copper price of US$4.22 per pound (after smelting, refining, transportation and royalty charges) and 75% recovery in oxide material.

4. Mineral Resources of the MacArthur pit area are reported within a conceptual pit shell that used the following input parameters: a break-even cut-off grade of 0.05 % for the MacArthur pit, 0.07 % TCu for the Gallagher pit, and 0.06 % TCu for the North Ridge pit. Metal price of $4.22 per pound (after smelting, refining, transportation, and royalty charges); process costs between $1.67 and $2.14/st; and base mining costs for heap tonnage of $2.49/st and $2.53/st for waste,

Recovery of Total Copper in redox zones of leach cap, overburden, oxide and mixed: MacArthur domain 55%, North Ridge domain 53%, Gallagher domain 54%.

Figure 1.4 through Figure 1.7 below show the mineral classification shells and the pit mining by phase for the Project.


 

Figure 1.4: Yerington Pit Long Section


 

 

Figure 1.5: Yerington Pit Mine Phases

Detailed information on the Pit Mine Phases is included in Section 16.4.


 

 

Figure 1.6: MacArthur Pit North-South Sections


 

Figure 1.7: MacArthur Pit Mine Phases

1.8 MINING METHODS

Open pit mining offers the best approach for development of the deposits based on the size of the resource, tenor of the grade, grade distribution and proximity to topography for the deposits.

The PFS mine schedule totals 506.6 Mt of heap leach feed grading 0.21% copper over a processing life of just under 12 years. Open pit waste tonnages from the various areas total 159.8 Mt and will be placed into waste storage areas adjacent to the open pits. The overall open pit strip ratio is 0.32:1 (waste: heap feed).

Three heap leach facilities will be used to provide copper solution to the processing (SX/EW) facilities.  The sulfide HLF located near the Yerington pit will utilize the Nuton process for the leaching of sulfide feed from the Yerington pit. The Nuton facility will have a peak feed rate of 35 Mtpa through a crushing plant.  The Yerington pit is the only supply of sulfide material for the PFS. The other process stream will employ conventional oxide copper leaching technology with ROM material. One oxide HLF will be located at Yerington for the Yerington oxide and VLT material while the other oxide HLF will be adjacent to the MacArthur pits.

The current mine plan includes minimal pre-stripping as the bottom of the existing pit still contains material suitable for placement on a HLF with conventional leaching and use of the Nuton process for the sulfide materials.

The open pit mining starts in Year 1 and continues uninterrupted until early in Year 12.


 

Conventional mining equipment was selected to meet the required production schedule, with additional support equipment for road, waste rock storage, and pit bench maintenance as is typical in an open pit mine.

Drilling will be completed with down-the-hole-hammer (DTH) electric drills with 6¾" bits. A smaller 5½" drill is used for tighter working areas. The primary loading units will be 21 yd³ electric hydraulic shovels. Additional loading will be completed by 15 yd³ loaders. It is expected that one of the loaders will be at the primary crusher for most of its operating time. The haulage trucks will be conventional 100-ton rigid body trucks.

1.9 INFRASTRUCTURE

The MacArthur and Yerington Sites have similar infrastructure, with Yerington as the main operating site. The major operating and administrative infrastructure will be located at the Yerington Site.

Both MacArthur and Yerington Sites will have the following:

  • Mine Pit(s)
  • HLFs
  • Waste Rock and Storage Facility (WRSF)
  • Raffinate pond
  • Pregnant Leach Solution (PLS) pond
  • PLS event pond
  • Solvent Extraction (SX) facility
  • Pit dewatering and deep well water pumps
  • Overhead power lines with connection to existing substations
  • Railroad spur and railroad offloading
  • Haul Roads
  • Service Roads

The shared infrastructure between the two Sites includes:

  • Railroad
  • Connecting Service Road
  • Intra-site pipelines

The Yerington Site will have the following additional infrastructure:

  • Yerington Stockpiles: coarse ore and fine ore
  • Truck shop
  • Administrative buildings
  • Crushing and Agglomeration circuit
  • Common Electrowinning (EW) facility
  • Water Treatment Plant
  • Acid Plants (2)
  • Cogeneration Plants (2)
  • Fuel storage

 

1.10 ENVIRONMENTAL

Permitting the Project will require authorizations from the Federal, State of Nevada, and local regulatory agencies supported by requisite studies and analyses and public involvement.

Lion CG intends to prepare a Mine Plan of Operations (MPO) in accordance with the Bureau of Land Management (BLM) 43 Code of Federal Regulations (CFR) 3809 Surface Management regulations and Nevada Guidance for Preparation of Operating Plans for Mining Facilities (Nevada Administrative Code [NAC] 445A.398). The BLM and the NDEP Bureau of Mining Regulation and Reclamation (BMRR) will concurrently review the Project MPO and Reclamation Plan Permit Application under a Memorandum of Understanding (MOU) between these two agencies.

Lion CG anticipates securing all required permits and authorizations needed to construct and operate the Project within reasonable and normal timeframes. Preliminary permitting schedule estimates the submittal of the MPO (and completeness determination) and the National Environmental Policy Act (NEPA) process (including all pre-NEPA tasks as outlined in BLM's Nevada Instruction Memorandum NV-IM-2024-019) requiring between 2.5 and 3.5 years. The Project's permitting schedule may benefit from the Executive Order 14241 titled Immediate Measures to Increase American Mineral Production issued in March 2025 to streamline permitting processes for mining projects, particularly those focused on critical minerals. In addition to this EO and BLM Nevada direction, Lion CG also recognizes recent changes made to NEPA and assumes BLM will comply with the Department of Interior's (DOI's) July 3, 2025 Interim Final Rule, including adherence to 516 DM 1 - US DOI Handbook of NEPA Implementing Procedures.

The State of Nevada requires permits for all mineral exploration and mining operations regardless of the land status. At the State level, the main permits will consist of the Reclamation Permit(s), Water Pollution Control Permits (WPCP) for mine operations and pit dewatering, and temporary discharge permits and the Air Quality Permit to construct and operate. Lion CG has secured consumptive use water rights for mining, milling, and dewatering and intends to acquire or offset existing groundwater rights for additional non-consumptive use during the initial 4 years of pit dewatering.

Preliminary permitting schedule estimates that Lion CG will require between 2.5 and 3.5 years to secure a WPCP for the Project and pit dewatering. Lion CG intends to proceed with preparation of the WPCP concurrently with the MPO and NEPA analysis.

Lion CG intends to ensure that the characterization of environmental resources at the Yerington and MacArthur Properties is complete and adequate to support the development of an MPO and satisfy other permitting requirements and environmental reviews, as determined in collaboration with Federal and State agencies.

Atlantic Richfield Company (ARC) is performing active remediation of the former Anaconda and Arimetco mining operations (brownfield site) at the Yerington Property. ARC, as successor in interest to the Anaconda Mining Company, is responsible for remediation of the Yerington Property. Lion CG will incorporate appropriate remedial design elements into the Project design for proposed facilities located within the remediation boundary, if necessary. Given the stringent engineering requirements for new mining facilities, it is highly likely that standard industry design features, such as placement of synthetic liners and installation of double-walled piping for conveyance of process solutions, will meet or exceed remedial action requirements. Lion CG has and will continue to work proactively with ARC to coordinate mine permitting and eventual construction and operation with the remediation requirements undertaken by ARC.


 

On September 11, 2019, Lion CG entered into an Environmental Covenant Agreement (2019 Covenant) with NDEP which describes use limitations, access agreements, and all other conditions associated with the historic Yerington Property. The 2019 Covenant allows for mineral exploration, development, mining, or mineral processing to the extent that such activities receive approval by the NDEP Bureau of Corrective Actions (BCA) before proceeding. The 2019 Covenant requires prior notification to and approval by NDEP BCA of any activities that alter, disturb, or modify any natural or manmade surface water features on or immediately adjacent to property where access, land, water, or other resource use restrictions are needed to implement investigations or cleanup.

Lion CG plans to ensure that all permits to construct and operate the Project facilities located within the Yerington Property boundary comply with the 2019 Covenant. Permitting proposed Project facilities located within the remediation boundary prior to completion of the remediation work will require coordination between NDEP BMRR and NDEP BCA to ensure compliance with applicable Nevada mine-related statutes and regulations and the 2019 Covenant.

Lion CG intends to manage waste and process-related fluids as required by the construction and operating permits and manage contact and non-contact water in accordance with applicable permits and regulations.

All Federal, State, and County agencies are expected to require environmental monitoring of the mine and processing operations and the fluid management system to ensure compliance with the Project permits. As part of both the WPCP and the MPO, Lion CG intends to submit a detailed monitoring plan to demonstrate compliance with the permits and other Federal or State environmental regulations, to provide early detection of potential problems, and to assist in directing potential corrective actions (if necessary).

Lion CG has developed a Stakeholder Outreach Strategy for engaging with the various stakeholder groups associated with the Project and establish measures and mechanisms to address stakeholders concerns on a timely basis. The framework includes a due diligence process, stakeholder mapping and analysis, engagement planning and communication protocols, grievance mechanism, record keeping, and follow-ups procedures.

The Project will provide substantial economic benefits and fiscal contributions to the community of Yerington, Lyon County, and the State of Nevada through increased employment and training opportunities, expanded economic activity (e.g., contractors, suppliers, support services), increased household incomes, and additional tax revenues.

Lion CG intends to reclaim disturbed areas resulting from activities associated with the Project in accordance with BLM Surface Management and the State of Nevada NDEP regulations and return mined land to productive post-mining land use.


 

1.11 MARKETS

Project production will consist of  LME Grade A copper cathode suitable for global markets. No long-term sales agreements have been put in place.

The Project long-term copper price used was $4.30/lb.

Acid pricing is based on an assumed price of $121/tonne sold to the regional market based upon spot market prices in May 2025. Sulfur pricing is based on an assumed price of $102/tonne delivered to the Wabuska rail spur based on an average 1-year trailing sulfur price from March 2025.

1.12 PROJECT ECONOMICS

1.12.1 Capital Costs

The capital cost estimate encompasses all direct and indirect expenditures, complete with appropriate contingencies for the various facilities required to commence production, as outlined in this study. It's important to note that all equipment and materials are assumed to be new, and the estimate does not incorporate allowances for potential scope changes, escalation, or fluctuations in exchange rates. The execution strategy is rooted in an engineering, procurement, and construction management (EPCM) implementation approach, with Lion CG overseeing construction management and the packaging of discipline-based construction contracts.

This capital cost estimate for the Project has been developed to align with the requirements of a PFS, encompassing the costs associated with designing, constructing, and commissioning the necessary facilities.

Table 1.7 outlines the total capital costs for the project, encompassing the mine, process facilities (including the 34 Mtpa crushing plant), heap leach facilities, on-site infrastructure, dewatering of the existing pit lake, and all associated project-related indirect expenditures and contingencies across major areas. The total capital cost estimate for the Project stands at approximately $1,732 million, with prices expressed in terms of Q1 2025 levels.

Table 1.7: Yerington Copper Project Capital Cost Estimate
Area Initial Capital
(M$)
Sustaining
Capital (M$)
Total Capital
(M$)
Open Pit Mining 22.8 40.7 63.5
Processing 143.4 318.5 461.9
Infrastructure 176.4 228.1 404.5
Acid Plant/CoGen 130.2 114 244.2
Dewatering 42.5 17.5 60
Indirects 74.0 125.7 199.7
Contingency 134.7 163.2 297.9
Total 724.0 1007.7 1731.7


 

1.12.2 Operating Costs

The estimated Project operating costs are shown in Table 1.8.

Table 1.8: Yerington Copper Project Operating Costs - Life of Mine
Area Life of Mine
($/t moved)
Life of Mine
($/t process feed)
Life of Mine
($/lb copper payable)
Open Pit Mining 2.55 3.35 1.18
Processing 1.42 1.87 0.66
G&A 0.19 0.24 0.09
Total Operating Cost 4.16 5.47 1.92

General data sources and assumptions used as the basis for estimating the process operating costs include:

  • Process design criteria in Section 17
  • Average production rate of 34 Mtpa for the Nuton circuit
  • Labor requirements as developed by AGP and Samuel Engineering
  • Unit cost of electrical energy of $0.065/kWhr
  • Unit cost of diesel fuel of $3.03/gal
  • Taxes are excluded from the G&A but are applied to the financial model

1.12.3 Financial Evaluation

Table 1.9: Financial Evaluation
Parameter Unit Pre-tax Post-tax
Net Revenue $USM 2,914 2,315
NPV (7%) (LOM) $USM $975 $694
IRR (LOM) % 16.9% 14.6%
Payback Years 6.4 6.7
Cash Costs1 $US/lb payable $1.92
AISC1 $US/lb payable $2.67
Copper - Payable Mlbs 1,443
Mine Life Years 12
Average Annual Production LOM Mlbs 120
LOM Production tons 721,352

Total cash cost and AISC are non-GAAP measures and include royalties payable. See reference below regarding non-IFRS measures.


 

1.13 QUALIFIED PERSONS RECOMMENDATIONS

Geology

  • Drilling to upgrade the Mineral Resource classification for VLT and W-3 and to support a Mineral Resource estimate for S-23.

Mine Geotechnical

  • Final slope analysis in the Yerington pit
  • Waste dump stability analysis of the Yerington Pit Waste Rock Storage Facility
  • MacArthur, Gallagher, and North Ridge final slope analysis
  • MacArthur waste rock storage facility stability analysis

Metallurgy

  • Expand the ore hardness and crusher work index database to confirm final crusher design parameters
  • Test additional material that has potential to convert from resource to reserves in the FS study

Heap Leach Pad

  • Perform geophysical testing in the footprint of the proposed HLFs to characterize shear wave velocity and refine seismic site classification for each location
  • Complete ore geotechnical characterization, to include laboratory testing such as strength and permeability testing

Environmental

  • Advance the geochemical characterization program, including sample collection and static testing. Conduct humidity cell tests and quarterly groundwater sampling
  • Schedule meetings with Federal (i.e., BLM) and State agencies (i.e., BMRR, BWPC, and BCA) to introduce the PFS-level Project and associated proposed development plans.

 

2.0 INTRODUCTION

2.1 2025 PFS OVERVIEW

Lion CG commissioned Samuel Engineering (SE) to prepare a S-K 1300 compliant PFS for its Yerington Copper Project, located approximately 80 miles southeast of Reno. SPS purchased the property, which has historical resources and water rights, in April 2011.

All capital and operating cost estimates meet the requirements of S-K 1300 and AACE Class 3, with an expected accuracy of -20% to +25%. An adequate contingency cost has been applied to capital cost estimates.  Contingency per area is broken down in Section 18.7.

This Technical Report (Report) was prepared on behalf of Lion CG by SE. The purpose of the Report is to present the results of the PFS on the Yerington Copper Project in Lyon County, Nevada. This Report was prepared in compliance with the Subpart 229.1300 - Disclosure by Registrants Engaged in Mining Operations in Regulation S-K 1300 (S-K1300). The mineral reserves used in the PFS were prepared on the Yerington Pit, VLT stockpile, and MacArthur deposits within the Project.

2.2 QUALIFIED PERSONS

The Qualified Persons (QPs), as that term is defined in S-K 1300, responsible for the preparation of the Report includes:

  • Tim Maunula, P.Geo.; Geology, Yerington and VLT Resource Estimate (TM&A)
  • Herb Welhener, MMSA-QPM; MacArthur Resource Estimate (IMC)
  • Michael McGlynn, RM-SME; Metallurgical, Process, Infrastructure (SE)
  • Adrien Butler, P.E.; Heap Leach Facilities, Stormwater Management (NewFields)
  • Gordon Zurowski, P.Eng.; Mineral Reserves, Mining (AGP)
  • Marie-Hélène Paré, SME-RM; Environmental (GSI Environmental Inc.)
  • Steven Pozder, P.E., MBA; Economic Analysis (SE)
Table 2.1: Summary of Qualified Persons
Name Professional
Designation
Title Responsible for Sections
Mr. Tim Maunula P.Geo. Principal Geologist
T. Maunula & Associates Consulting Inc.
Sections 1.2, 1.3, 1.4, 1.5, 1.7, 3, 5, 6, 7, 8, 9.1, 11.1-11.3, 11.5-11.6 20, 22.1.1, 23.1
Mr. Herb Welhener MMSA-QPM Vice President
Independent Mining Consultants, Inc.
Sections 1.2, 1.4, 1.5, 1.7, 3.7, 6.7, 8, 9.2, 11.4-11.6, 22.1.2
Mr. Michael McGlynn SME-RM Industry Manager - Metals & Minerals
Process Engineer
Samuel Engineering, Inc.
Sections 1.6, 1.9, 1.11, 3.7, 4, 10, 14, 15.1-15.11, 16, 18 (except 18.2, 18.8), 22.2, 23.4


 

Table 2.1: Summary of Qualified Persons
Name Professional
Designation
Title Responsible for Sections
Ms. Adrien Butler P.E. Senior Civil Engineer
NewFields
Sections 3.7, 15.12, 15.13, 22.4, 23.6.
Mr. Gordon Zurowski P.Eng. Principal Mine Engineer
AGP Mining Consultants Inc.
Sections 1.7, 1.8, 3.7, 12, 13, 18.2, 18.8, 23.2, 23.3.
Ms. Marie-Hélène Paré SME-RM Principal Mining Geologist
GSI Environmental, Inc.
Section 1.10, 15.5, 17, 22.5 23.7.
Mr. Steven Pozder P.E., MBA Senior Director - Engineering & Analysis
Mechanical Engineer
Samuel Engineering, Inc.
Sections 1.12, 19

2.3 SITE INSPECTION

Site visits were completed by Mr. Maunula, Mr. Welhener, Mr. McGlynn, Ms. Butler, Mr. Zurowski, and Ms. Paré.

2.3.1 Geology (Yerington and VLT)

Mr. Maunula conducted an initial site visit to the property for two days on February 13th and 14th, 2023. The Yerington and MacArthur sites were visited during the two-day trip.

A follow-up site visit was conducted for three days on August 26th to 28th, 2024 to visit the Yerington and VLT sites.

While on site for the 2024 site visit, Mr. Maunula reviewed drill core from Yerington and compared it with recorded drill logs, visited core sampling and storage facilities, and inspected drilling sites for Yerington and VLT. Also, bulk sample locations for VLT were located and reviewed.

Seven check samples were collected, under the QP's supervision, from drill holes YM-047A and YM-049, and submitted to ALS Laboratory in Reno, NV for analysis.

Meetings were held on-site with Lion personnel.

2.3.2 Geology (MacArthur)

Mr. Welhener (IMC) conducted a site visit to the Project for two days on February 14th and 15th 2022. The Yerington and MacArthur Deposits were visited during the two-day trip.

While on site, the drill core was reviewed from three drill holes and compared with recorded drill logs, visited core sampling and storage facilities, and inspected drilling sites.


 

The pit areas were also visited for Yerington and MacArthur Deposits, waste dump locations and proposed infrastructure locations including the waste storage areas, conveyor route, pit access roads, proposed plant and heap leach locations and nearby railway sidings.

Meetings were held on site with the various team members including Lion CG personnel responsible for geology, and environmental activities.

2.3.3 Metallurgy, Processing, and Infrastructure

Mr. McGlynn visited the property for two days on January 9th and 10th, 2024. The trip was intended for the PFS kick-off. During this trip, the Project area was visited.

Meetings were held on-site to review the Project areas. The visit included a site tour and review of drill core from both pit areas, visits to both pit areas, waste dump locations, proposed infrastructure locations, including the crusher and conveyor route, pit access roads, and proposed plant and heap leach locations.

2.3.4 Mining

Mr. Zurowski visited the property for two days on February 13th and 14th, 2023. The Yerington and MacArthur sites were visited during the two-day trip.

While on site, Mr. Zurowski reviewed drill core from the pit areas, visited both pit areas, waste dump locations, and proposed infrastructure locations, including the waste storage areas, conveyor route, pit access roads, proposed plant and heap leach locations, and nearby railway sidings.

Meetings were held on-site with the various team members, including Lion personnel responsible for geology and environmental activities.

2.3.5 Infrastructure

Ms. Butler visited the property for two days on September 13, 2022 (MacArthur and Yerington sites) and February 14, 2023 (Yerington site only).

While on site, Ms. Butler visited both pit areas, legacy mining infrastructure, and proposed infrastructure locations, including waste storage areas, a conveyor route, pit access roads, a proposed plant location, a proposed heap leach facility location, and nearby railway sidings.

2.3.6 Environment

Ms. Paré conducted a site visit at the MacArthur and Yerington sites on December 7, 2021.

While on site, Mrs. Paré visited both pit areas, waste dump locations, and proposed infrastructure locations, including the waste storage areas, conveyor route, pit access roads, proposed plant, and heap leach locations.


 

2.3.7 QP Site Visits

A summary of the site visits is shown in Table 2.2.

Table 2.2: Dates of Site Visits
Name Site Visit Dates
Mr. Tim Maunula, P.Geo. Yes February 13-14, 2023
August 26-28, 2024
Mr. Herb Welhener Yes February 14-15, 2022
Mr. Michael McGlynn, QP Yes January 9 and 10, 2024
Ms. Adrien Butler, P.E. Yes September 13, 2022, February 14, 2023
Mr. Gordon Zurowski, P.Eng. Yes February 13 - 14, 2023
Ms. Marie-Hélène Paré Yes December 7, 2021

2.4 EFFECTIVE DATES

The effective date for the Mineral Resource Statements for the Yerington Pit, VLT and MacArthur Area Pits is March 17, 2025.

The effective date for the Mineral Reserve Statement for the Yerington Pit and VLT is dated May 31, 2025.

The effective date for the Mineral Reserve Statement for the MacArthur Area Pits is dated March 17, 2025.

The effective date of the Yerington Copper Project PFS is May 31, 2025.


 

3.0 PROPERTY DESCRIPTION

3.1 LOCATION

The Project is located near the geographic center of Lyon County, Nevada, US, along the eastern flank of the Singatse Range (Figure 3.1 and Figure 3.2). The Project includes both the historical Yerington mine, flanked on the west by Weed Heights, Nevada (a small private community, the original company town of Anaconda) and the historic MacArthur open pit located approximately 4.5 miles to the northwest. The Project is bordered on the east by the town of Yerington, Nevada which provides access via a network of paved and gravel roads that were used during previous mining operations.

The coordinate of the Project centroid is 39°1'54.72° North latitude and 119°14'34.52° West longitude.

The Project is approximately 80 miles by road from Reno Nevada, 50 miles south of Tahoe-Reno Industrial Center, and 10 miles from the nearest rail spur of Wabuska. Topographic coverage is provided by the U.S. Geological Survey "Mason Butte", Lincoln Flat", and the "Yerington" 7.5' topographic quadrangles.

Source: Tetra Tech 2014

Figure 3.1: Yerington Copper Project Location


 

 

Source: Lion CG, 20

Figure 3.2: Regional Layout Map

3.2 PROPERTY OWNERSHIP

Five fee simple parcels (private land) (Table 3.2), 82 patented mining claims totaling 2,767.55 acres (Table 3.1), and 23 unpatented mining claims were acquired on April 27, 2011, when Lion CG closed a transaction under which assets of Arimetco, Inc. (Arimetco), a Nevada corporation, were acquired. The additional 1,132 unpatented claims were staked by Lion CG (Table 3.3). In total, Lion CG controls approximately 23,697 acres of unpatented claims. Table 3.4 summarizes five parcels of optioned private ground in Lyon County.


 

Private land is located in Township 13 North, Range 25 East in Sections 4, 5, 8, 9, 16, 17, and 21, and patented claims are located within Township 13 North, Range 25 East in Sections 16, 17, 19, 21, 31, and 32 and in Township 13 North, Range 24 East in Sections 22-25 and 36. Lion CG's unpatented claims are located in: Sections 1 and 2, Township 12 North, Range 24 East; Sections 1-3, 8, 9, 11-14, 22-27, 35, 36, Township 13 North, Range 24 East; Sections 4-9, 16-21, and 30-32, Township 13 North, Range 25 East; Sections 1-4, 9-16, 22-27, 34-36, Township 14 North, Range 24 East; Sections 17-20, 29-31 Township 14 North, Range 25 East; Sections 1, 13, 18, 24-25, 33-36 Township 15 North, Range 24 East, Mount Diablo Base & Meridian.

3.3 MINERAL TENURE, TITLE AND ROYALTIES

The purchase of the Arimetco assets was accomplished through a US$500,000 cash payment, 250,000 shares of Quaterra common stock, and a 2% net smelter return royalty capped at $7.5 million on production from any claims owned by its subsidiary Quaterra Alaska, Inc (including Quaterra's MacArthur Property) in the Yerington mining district.

A portion of the claims around the historic MacArthur mine were acquired by exercising a "Mining Lease with Option to Purchase". The original purchase option dated September 13, 2005, between North and the Company, as amended, was exercised on February 9, 2015. The Company's purchase is subject to a two percent Net Smelter Return (NSR) with a royalty buy down option of $1,000,000 to purchase one percent of the NSR, leaving a perpetual one percent NSR.

A portion of the MacArthur claim group is also included in the area referred to as the "Royalty Area" in the Company's purchase agreement for the acquisition of Arimetco's Yerington properties. Under this agreement, MacArthur claims within this area (as well as the Yerington properties) are subject to a two percent NSR production royalty derived from the sales of ores, minerals and materials mined and marketed from the Property up to $7,500,000.

Ownership of the patented claims and private land is maintained through payment of county assessed taxes, while unpatented lode claims staked on BLM ground in the United States require a federal annual maintenance fee of $200 each, due by 12:00 pm (noon) on September 1 of each year. Further, each unpatented claim staked in Nevada requires an Intent to Hold fee of $15.00, plus filing fees, due by November 1 of each year payable to the County Recorder of the Lyon county. All annual fees have been paid, and Lion CG claims are current.

Unpatented lode claims have been staked by placing a location monument (two- by two-in by four-foot-high wood post) along the center line of each claim and two- by two-inch by four-foot-high wood posts at all four corners, with all posts properly identified in accordance with the rules and regulations of the BLM and the State of Nevada. Maximum dimensions of unpatented lode claims are 600 ft × 1,500 ft.

Optioned land is maintained via annual payments to landowners.

A complete property listing is included in Table 3.1, Table 3.2, Table 3.3, and Table 3.4 below.


 

3.4 PROJECT BACKGROUND

Copper mining was first recorded at the Yerington Mine site from 1918-1920 at the Empire Mine, and later, beginning in 1953 by Anaconda. From that time forward, the Yerington mine operated under different companies until 1999 when Arimetco, the last operator, closed the operation. Soil and groundwater contamination from the former mining operations have been identified on the Yerington Property.

As a result, a portion of the Property acquired by Lion CG in 2011 is now being remediated under jurisdiction of NDEP. Liability for the contamination on site is the responsibility of a third party which is actively engaged in remedial investigation and remediation activities under the supervision of NDEP.

To establish Lion CG's position and rights, the acquisition by Lion CG of the Arimetco properties required a series of rigorous environmental, legal, and technical due diligence studies. In 2008, Chambers Group, Inc. and Golder Associates Inc. conducted a Phase I Environmental Site Assessment (Phase I ESA) for the Yerington Mine Site. A Phase I ESA is intended to serve as an appropriate, commercially prudent, and reasonable inquiry regarding the potential for recognized environmental conditions in connection with the subject property. The 2008 Phase 1 ESA was updated by SRK Consulting (U.S.) Inc. (SRK) in 2010 and again in 2011. These were completed to allow Lion CG to establish liability protection as a BFPP. Prior to closing on the Property, Lion CG received letters from the NDEP, BLM and the USEPA indicating the post-closing requirements then applicable to the Yerington Mine Site for Lion CG to maintain its defense to liability as a BFPP regarding the activities of the former mine owners and operators.

Technical due diligence included the review and compilation of a wealth of historical data in the Anaconda Collection, American Heritage Center, University of Wyoming, in Laramie. Numerous reports, maps, and historical drilling data have been scanned and entered into an internal data base, allowing an initial review of both past production and remaining mineralization throughout the Yerington District.

The company controls approximately 6,014-acre ft of primary groundwater rights permitted for mining and milling use at the site. The places of use for each of the water rights which make up this total are on the site, which also contains a pit lake now estimated to contain approximately 43,000-acre ft of water to be dewatered during mining activities. The company believes this water will have a variety of beneficial uses but will require some costs to make the water available for those beneficial uses.

If Lion CG elects to conduct exploration on unpatented lode mining claims on public lands administered by the BLM, a Notice of Intent is required if the proposed disturbance is less than five acres.

3.5 PROJECT CLAIMS AND PRIVATE LAND

Table 3.1: Patented Claims
Patented Claims Mineral Survey
Number
County Parcel
Number
Parcel Acreage
Know U Don'T 3144 012-111-21 98
January 3145    
Rossland 3367    
Eclipse 4080    


 

Table 2.1: Summary of Qualified Persons
Name Professional
Designation
Title Responsible for Sections
Edwin 1,2,5 4080    
Copper King, Kid 4081    
Copper Queen No. 1 4081    
Santa Cruse 1,3 3075 012-111-23 58
Santa Cruz 3075    
Copper Queen No. 1,3 3655 012-112-01 490
Minnie Edith 3655    
Nevada King 3655    
San Jacinto 3655    
Alcatraz 3656    
Black Horse 3656    
Boston 3656    
Cash Boy 3656    
Christina 3656    
Colorado 3656    
Colorado Springs 3656    
Copper Queen 2,6 3656    
Daisy 3656    
Fortuna 3656    
Iron Cap,Iron Cap 2 3656    
Jack Clubs 3656    
Juanita 3656    
Kathleen 3656    
Monte Cristo 3656    
Pocahontas 3656    
Sage Hen 3656    
Santa Inez 3656    
Santigo 3656    
Scorpion 3656    
Styx 3656    
No. 102 4850 012-113-01 64.48
No. 73 4850    
No. 74 4850    
Diamond,Diamond 1,2 3736 012-113-02 130
Diamond 3,4 3977    
Diamond Fr.,Diamond Fr. 1 3977    
Lone Star 3977    
Anaconda 3692 012-113-04 19
Copper Canyon 3157 012-113-05 20


 

Table 2.1: Summary of Qualified Persons
Name Professional
Designation
Title Responsible for Sections
A & L 4499 014-451-04 506.86
Wild Rose,Wild Rose 1-2 4499    
Black Horse 4531    
Blue Star 4531    
Canidate 4531    
Consolidated,Consolidated Fr. 4531    
Greenhorn 4531    
Hungry Bill 4531    
Katy Didn'T 4531    
New Blue Bird,New Blue Bird 1,2 4531    
New Royal Blue,New Royal Blue Ext. 4531    
North Star 4531    
Red Star 4531    
Sunlight 4531    
West Starlight 4531    
No. 38 4778    
No. Seven 4778    
No. Thirty-Five Fr. 4778    
No. Twenty-Five 4778    
No. Twenty-Four 4778    
No. Twenty-Six 4778    
No. Twenty-Three 4778    
Total Claims: 82 Total acreage: 1386.34

Table 3.2: Private Ground
Private Ground Count County Parcel
Number
Acreage
Private 1 014-401-06 182.77
Private 1 014-461-10 12.7
Private 1 014-461-11 31
Private 1 014-401-15 1074.74
Private 1 014-241-09 80
Total Parcels: 5 Total acreage: 1381.21

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
YERINGTON MINE LODE ADP 1 S4, 5-T13N-R25E
YERINGTON MINE LODE ADP 10 S16-T13N-R25E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range

YERINGTON MINE

LODE

ADP 11

S16-T13N-R25E

YERINGTON MINE

LODE

ADP 12

S16-T13N-R25E

YERINGTON MINE

LODE

ADP 13

S16-T13N-R25E

YERINGTON MINE

LODE

ADP 14

S16-T13N-R25E

YERINGTON MINE

LODE

ADP 15

S16-T13N-R25E

YERINGTON MINE

LODE

ADP 16

S16-T13N-R25E

YERINGTON MINE

LODE

ADP 17

S16-T13N-R25E

YERINGTON MINE

LODE

ADP 18

S16-T13N-R25E

YERINGTON MINE

LODE

ADP 19

S16-T13N-R25E

YERINGTON MINE

LODE

ADP 2

S5, 8-T13N-R25E

YERINGTON MINE

LODE

ADP 20

S16-T13N-R25E

YERINGTON MINE

LODE

ADP 21

S16-T13N-R25E

YERINGTON MINE

LODE

ADP 22

S17-T13N-R25E

YERINGTON MINE

LODE

ADP 23

S17-T13N-R25E

YERINGTON MINE

LODE

ADP 3

S5, 8-T13N-R25E

YERINGTON MINE

LODE

ADP 4

S7, 8-T13N-R25E

YERINGTON MINE

LODE

ADP 5

S7, 8-T13N-R25E

YERINGTON MINE

LODE

ADP 6

S17-T13N-R25E

YERINGTON MINE

LODE

ADP 7

S17-T13N-R25E

YERINGTON MINE

LODE

ADP 8

S8-T13N-R25E

YERINGTON MINE

LODE

ADP 9

S8-T13N-R25E

MACARTHUR CU

LODE

AT 1

Sec 9,10,15,16 T14N R24E

MACARTHUR CU

LODE

AT 10

Sec 15 T14N R24E

MACARTHUR CU

LODE

AT 100

Sec 22 T14N R24E

MACARTHUR CU

LODE

AT 101

Sec 22 T14N R24E

MACARTHUR CU

LODE

AT 102

Sec 22 T14N R24E

MACARTHUR CU

LODE

AT 103

Sec 22 T14N R24E

MACARTHUR CU

LODE

AT 104

Sec 22 T14N R24E

MACARTHUR CU

LODE

AT 105

Sec 22 T14N R24E

MACARTHUR CU

LODE

AT 106

Sec 22 T14N R24E

MACARTHUR CU

LODE

AT 107

Sec 15,22 T14N R24E

MACARTHUR CU

LODE

AT 108

Sec 22 T14N R24E

MACARTHUR CU

LODE

AT 109

Sec 15,22 T14N R24E

MACARTHUR CU

LODE

AT 11

Sec 10,15 T14N R24E

MACARTHUR CU

LODE

AT 110

Sec 22 T14N R24E

MACARTHUR CU

LODE

AT 111

Sec 15,22 T14N R24E

MACARTHUR CU

LODE

AT 112

Sec 22 T14N R24E

MACARTHUR CU

LODE

AT 113

Sec 15,22 T14N R24E

MACARTHUR CU

LODE

AT 114

Sec 22 T14N R24E

MACARTHUR CU

LODE

AT 115

S9, 10-T14N-R24E

MACARTHUR CU

LODE

AT 116

S9, 10-T14N-R24E

MACARTHUR CU LODE AT 117 S10-T14N-R24E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE AT 118 S10-T14N-R24E
MACARTHUR CU LODE AT 119 S10-T14N-R24E
MACARTHUR CU LODE AT 12 Sec 15 T14N R24E
MACARTHUR CU LODE AT 120 S10-T14N-R24E
MACARTHUR CU LODE AT 121 S10-T14N-R24E
MACARTHUR CU LODE AT 122 S10-T14N-R24E
MACARTHUR CU LODE AT 123 S10-T14N-R24E
MACARTHUR CU LODE AT 124 S10-T14N-R24E
MACARTHUR CU LODE AT 125 S10-T14N-R24E
MACARTHUR CU LODE AT 126 S10-T14N-R24E
MACARTHUR CU LODE AT 127 S10-T14N-R24E
MACARTHUR CU LODE AT 128 S10-T14N-R24E
MACARTHUR CU LODE AT 129 S10-T14N-R24E
MACARTHUR CU LODE AT 13 Sec 10,15 T14N R24E
MACARTHUR CU LODE AT 130 S10-T14N-R24E
MACARTHUR CU LODE AT 131 S10-T14N-R24E
MACARTHUR CU LODE AT 132 S10-T14N-R24E
MACARTHUR CU LODE AT 133 S10, 11-T14N-R24E
MACARTHUR CU LODE AT 134 S10, 11-T14N-R24E
MACARTHUR CU LODE AT 135 S11-T14N-R24E
MACARTHUR CU LODE AT 136 S11-T14N-R24E
MACARTHUR CU LODE AT 137 S11-T14N-R24E
MACARTHUR CU LODE AT 138 S11-T14N-R24E
MACARTHUR CU LODE AT 139 S11-T14N-R24E
MACARTHUR CU LODE AT 14 Sec 15 T14N R24E
MACARTHUR CU LODE AT 140 S11-T14N-R24E
MACARTHUR CU LODE AT 141 S11-T14N-R24E
MACARTHUR CU LODE AT 142 S11-T14N-R24E
MACARTHUR CU LODE AT 143 S11-T14N-R24E
MACARTHUR CU LODE AT 144 S11-T14N-R24E
MACARTHUR CU LODE AT 145 S11-T14N-R24E
MACARTHUR CU LODE AT 146 S11-T14N-R24E
MACARTHUR CU LODE AT 147 S11-T14N-R24E
MACARTHUR CU LODE AT 148 S11-T14N-R24E
MACARTHUR CU LODE AT 149 S11, 12-T14N-R24E
MACARTHUR CU LODE AT 15 Sec 10,15 T14N R24E
MACARTHUR CU LODE AT 150 S11, 12-T14N-R24E
MACARTHUR CU LODE AT 151 S12-T14N-R24E
MACARTHUR CU LODE AT 152 S12-T14N-R24E
MACARTHUR CU LODE AT 153 S12-T14N-R24E
MACARTHUR CU LODE AT 154 S12-T14N-R24E
MACARTHUR CU LODE AT 157 S9, 10-T14N-R24E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE AT 158 S10-T14N-R24E
MACARTHUR CU LODE AT 159 S10-T14N-R24E
MACARTHUR CU LODE AT 16 Sec 15 T14N R24E
MACARTHUR CU LODE AT 160 S10-T14N-R24E
MACARTHUR CU LODE AT 161 S10-T14N-R24E
MACARTHUR CU LODE AT 162 S10-T14N-R24E
MACARTHUR CU LODE AT 163 S10-T14N-R24E
MACARTHUR CU LODE AT 164 S10-T14N-R24E
MACARTHUR CU LODE AT 165 S10-T14N-R24E
MACARTHUR CU LODE AT 166 S10, 11-T14N-R24E
MACARTHUR CU LODE AT 167 S2, 11-T14N-R24E
MACARTHUR CU LODE AT 168 S2, 11-T14N-R24E
MACARTHUR CU LODE AT 169 S2, 11-T14N-R24E
MACARTHUR CU LODE AT 17 Sec 10,14,15 T14N R24E
MACARTHUR CU LODE AT 170 S2, 11-T14N-R24E
MACARTHUR CU LODE AT 171 S2, 11-T14N-R24E
MACARTHUR CU LODE AT 172 S2, 11-T14N-R24E
MACARTHUR CU LODE AT 173 S2, 11-T14N-R24E
MACARTHUR CU LODE AT 174 S2, 11, 12-T14N-R24E
MACARTHUR CU LODE AT 175 S1, 2, 11, 12-T14N-R24E
MACARTHUR CU LODE AT 176 S1, 12-T14N-R24E
MACARTHUR CU LODE AT 18 Sec 14,15 T14N R24E
MACARTHUR CU LODE AT 19 Sec 10,11,14 T14N R24E
MACARTHUR CU LODE AT 2 Sec 15,16 T14N R24E
MACARTHUR CU LODE AT 20 Sec 14 T14N R24E
MACARTHUR CU LODE AT 21 Sec 11,14 T14N R24E
MACARTHUR CU LODE AT 22 Sec 14 T14N R24E
MACARTHUR CU LODE AT 23 Sec 11,14 T14N R24E
MACARTHUR CU LODE AT 24 Sec 14 T14N R24E
MACARTHUR CU LODE AT 25 Sec 11,14 T14N R24E
MACARTHUR CU LODE AT 26 Sec 14 T14N R24E
MACARTHUR CU LODE AT 27 Sec 11,14 T14N R24E
MACARTHUR CU LODE AT 28 Sec 14 T14N R24E
MACARTHUR CU LODE AT 29 Sec 11,14 T14N R24E
MACARTHUR CU LODE AT 3 Sec 10,15 T14N R24E
MACARTHUR CU LODE AT 30 Sec 14 T14N R24E
MACARTHUR CU LODE AT 31 Sec 11,14 T14N R24E
MACARTHUR CU LODE AT 32 Sec 14 T14N R24E
MACARTHUR CU LODE AT 33 Sec 11,14 T14N R24E
MACARTHUR CU LODE AT 34 Sec 14 T14N R24E
MACARTHUR CU LODE AT 35 Sec 40131 T14N R24E
MACARTHUR CU LODE AT 36 Sec 13,14 T14N R24E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE AT 37 Sec 12,13 T14N R24E
MACARTHUR CU LODE AT 38 Sec 13 T14N R24E
MACARTHUR CU LODE AT 39 Sec 12,13 T14N R24E
MACARTHUR CU LODE AT 4 Sec 15 T14N R24E
MACARTHUR CU LODE AT 40 Sec 13 T14N R24E
MACARTHUR CU LODE AT 41 Sec 12,13 T14N R24E
MACARTHUR CU LODE AT 42 Sec 13 T14N R24E
MACARTHUR CU LODE AT 43 Sec 12,13 T14N R24E
MACARTHUR CU LODE AT 44 Sec 13 T14N R24E
MACARTHUR CU LODE AT 45 Sec 15,16 T14N R24E
MACARTHUR CU LODE AT 46 Sec 15,16,22 T14N R24E
MACARTHUR CU LODE AT 47 Sec 15 T14N R24E
MACARTHUR CU LODE AT 48 Sec 15,22 T14N R24E
MACARTHUR CU LODE AT 49 Sec 15 T14N R24E
MACARTHUR CU LODE AT 5 Sec 10,15 T14N R24E
MACARTHUR CU LODE AT 50 Sec 15,22 T14N R24E
MACARTHUR CU LODE AT 51 Sec 15 T14N R24E
MACARTHUR CU LODE AT 52 Sec 15,22 T14N R24E
MACARTHUR CU LODE AT 53 Sec 15 T14N R24E
MACARTHUR CU LODE AT 54 Sec 15,22 T14N R24E
MACARTHUR CU LODE AT 55 Sec 15 T14N R24E
MACARTHUR CU LODE AT 56 Sec 15,22 T14N R24E
MACARTHUR CU LODE AT 57 Sec 15 T14N R24E
MACARTHUR CU LODE AT 58 Sec 15 T14N R24E
MACARTHUR CU LODE AT 59 Sec 15 T14N R24E
MACARTHUR CU LODE AT 6 Sec 15 T14N R24E
MACARTHUR CU LODE AT 60 Sec 15 T14N R24E
MACARTHUR CU LODE AT 61 Sec 14,15 T14N R24E
MACARTHUR CU LODE AT 62 Sec 14,15 T14N R24E
MACARTHUR CU LODE AT 63 Sec 14 T14N R24E
MACARTHUR CU LODE AT 64 Sec 14 T14N R24E
MACARTHUR CU LODE AT 65 Sec 14 T14N R24E
MACARTHUR CU LODE AT 66 Sec 14 T14N R24E
MACARTHUR CU LODE AT 67 Sec 14 T14N R24E
MACARTHUR CU LODE AT 68 Sec 14 T14N R24E
MACARTHUR CU LODE AT 69 Sec 14 T14N R24E
MACARTHUR CU LODE AT 7 Sec 10,15 T14N R24E
MACARTHUR CU LODE AT 70 Sec 14 T14N R24E
MACARTHUR CU LODE AT 71 Sec 14 T14N R24E
MACARTHUR CU LODE AT 72 Sec 14 T14N R24E
MACARTHUR CU LODE AT 73 Sec 14 T14N R24E
MACARTHUR CU LODE AT 74 Sec 14 T14N R24E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE AT 75 Sec 14 T14N R24E
MACARTHUR CU LODE AT 76 Sec 14 T14N R24E
MACARTHUR CU LODE AT 77 Sec 14 T14N R24E
MACARTHUR CU LODE AT 78 Sec 14 T14N R24E
MACARTHUR CU LODE AT 79 Sec 13,14 T14N R24E
MACARTHUR CU LODE AT 8 Sec 15 T14N R24E
MACARTHUR CU LODE AT 80 Sec 13,14 T14N R24E
MACARTHUR CU LODE AT 81 Sec 13 T14N R24E
MACARTHUR CU LODE AT 82 Sec 13 T14N R24E
MACARTHUR CU LODE AT 83 Sec 13 T14N R24E
MACARTHUR CU LODE AT 84 Sec 13 T14N R24E
MACARTHUR CU LODE AT 85 Sec 13 T14N R24E
MACARTHUR CU LODE AT 86 Sec 13 T14N R24E
MACARTHUR CU LODE AT 87 Sec 13 T14N R24E
MACARTHUR CU LODE AT 88 Sec 13 T14N R24E
MACARTHUR CU LODE AT 89 Sec 13 T14N R24E
MACARTHUR CU LODE AT 9 Sec 10,15 T14N R24E
MACARTHUR CU LODE AT 90 Sec 13 T14N R24E
MACARTHUR CU LODE AT 91 Sec 13 T14N R24E
MACARTHUR CU LODE AT 92 Sec 13 T14N R24E
MACARTHUR CU LODE AT 93 Sec 13 T14N R24E
MACARTHUR CU LODE AT 94 Sec 13 T14N R24E
MACARTHUR CU LODE AT 95 Sec 13 T14N R24E
MACARTHUR CU LODE AT 96 Sec 13 T14N R24E
MACARTHUR CU LODE AT 97 Sec 13 T14N R24E
MACARTHUR CU LODE AT 98 Sec 13 T14N R24E
MACARTHUR CU LODE AT 99 Sec 22 T14N R24E
MACARTHUR CU LODE AT177 S33-T15N-R24E; S4, T14N-R24E
MACARTHUR CU LODE AT178 S4-T14N-R24E
MACARTHUR CU LODE AT179 S34-T15N-R24E; S3-T14N-R24E
MACARTHUR CU LODE AT180 S3-T14N-R24E
MACARTHUR CU LODE AT181 S34-T15N-R24E; S3-T14N-R24E
MACARTHUR CU LODE AT182 S3-T14N-R24E
MACARTHUR CU LODE AT183 S34-T15N-R24E; S3-T14N-R24E
MACARTHUR CU LODE AT184 S3-T14N-R24E
MACARTHUR CU LODE AT185 S34-T15N-R24E; S3-T14N-R24E
MACARTHUR CU LODE AT186 S3-T14N-R24E
MACARTHUR CU LODE AT187 S34-T15N-R24E; S3-T14N-R24E
MACARTHUR CU LODE AT188 S3-T14N-R24E
MACARTHUR CU LODE AT189 S34-T15N-R24E; S3-T14N-R24E
MACARTHUR CU LODE AT190 S3-T14N-R24E
MACARTHUR CU LODE AT191 S34-T15N-R24E; S3-T14N-R24E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE AT192 S3-T14N-R24E
MACARTHUR CU LODE AT193 S34-T15N-R24E; S3-T14N-R24E
MACARTHUR CU LODE AT194 S3-T14N-R24E
MACARTHUR CU LODE AT195 S34-T15N-R24E; S3-T14N-R24E
MACARTHUR CU LODE AT196 S3-T14N-R24E
MACARTHUR CU LODE AT197 S35-T15N-R24E; S2-T14N-R24E
MACARTHUR CU LODE AT198 S2-T14N-R24E
MACARTHUR CU LODE AT199 S35-T15N-R24E; S2-T14N-R24E
MACARTHUR CU LODE AT200 S2-T14N-R24E
MACARTHUR CU LODE AT201 S35-T15N-R24E; S2-T14N-R24E
MACARTHUR CU LODE AT202 S2-T14N-R24E
MACARTHUR CU LODE AT203 S35-T15N-R24E; S2-T14N-R24E
MACARTHUR CU LODE AT204 S2-T14N-R24E
MACARTHUR CU LODE AT205 S35-T15N-R24E; S2-T14N-R24E
MACARTHUR CU LODE AT206 S2-T14N-R24E
MACARTHUR CU LODE AT207 S35-T15N-R24E; S2-T14N-R24E
MACARTHUR CU LODE AT208 S2-T14N-R24E
MACARTHUR CU LODE AT209 S35-T15N-R24E; S2-T14N-R24E
MACARTHUR CU LODE AT210 S2-T14N-R24E
MACARTHUR CU LODE AT211 S35-T15N-R24E; S2-T14N-R24E
MACARTHUR CU LODE AT212 S2-T14N-R24E
MACARTHUR CU LODE AT213 S35, 36-T15N-R24E; S1, 2-T14N-R24E
MACARTHUR CU LODE AT214 S2-T14N-R24E
MACARTHUR CU LODE AT215 S36-T15N-R24E; S1-T14N-R24E
MACARTHUR CU LODE AT216 S2-T14N-R24E
MACARTHUR CU LODE AT217 S4-T14N-R24E
MACARTHUR CU LODE AT218 S3, 4, 9, 10-T14NR24E
MACARTHUR CU LODE AT219 S3-T14N-R24E
MACARTHUR CU LODE AT220 S3, 10-T14N-R24E
MACARTHUR CU LODE AT221 S3-T14N-R24E
MACARTHUR CU LODE AT222 S3, 10-T14N-R24E
MACARTHUR CU LODE AT223 S3-T14N-R24E
MACARTHUR CU LODE AT224 S3, 10-T14N-R24E
MACARTHUR CU LODE AT225 S3-T14N-R24E
MACARTHUR CU LODE AT226 S3, 10-T14N-R24E
MACARTHUR CU LODE AT227 S3-T14N-R24E
MACARTHUR CU LODE AT228 S3, 10-T14N-R24E
MACARTHUR CU LODE AT229 S3-T14N-R24E
MACARTHUR CU LODE AT230 S3, 10-T14N-R24E
MACARTHUR CU LODE AT231 S3-T14N-R24E
MACARTHUR CU LODE AT232 S3, 10-T14N-R24E
MACARTHUR CU LODE AT233 S3-T14N-R24E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE AT234 S3, 10-T14N-R24E
MACARTHUR CU LODE AT235 S2, 3-T14N-R24E
MACARTHUR CU LODE AT236 S2, 3, 10, 11-T14N-R24E
MACARTHUR CU LODE AT237 S2-T14N-R24E
MACARTHUR CU LODE AT238 S2, 11-T14N-R24E
MACARTHUR CU LODE AT239 S2-T14N-R24E
MACARTHUR CU LODE AT240 S2-T14N-R24E
MACARTHUR CU LODE AT241 S2-T14N-R24E
MACARTHUR CU LODE AT242 S2-T14N-R24E
MACARTHUR CU LODE AT243 S2-T14N-R24E
MACARTHUR CU LODE AT244 S2-T14N-R24E
MACARTHUR CU LODE AT245 S2-T14N-R24E
MACARTHUR CU LODE AT246 S2-T14N-R24E
MACARTHUR CU LODE AT247 S2-T14N-R24E
MACARTHUR CU LODE AT248 S2-T14N-R24E
MACARTHUR CU LODE AT249 S2-T14N-R24E
MACARTHUR CU LODE AT250 S2-T14N-R24E
MACARTHUR CU LODE AT251 S2-T14N-R24E
MACARTHUR CU LODE AT252 S2-T14N-R24E
MACARTHUR CU LODE AT253 S1, 2-T14N-R24E
MACARTHUR CU LODE AT254 S1, 2-T14N-R24E
MACARTHUR CU LODE AT255 S1-T14N-R24E
MACARTHUR CU LODE AT256 S1-T14N-R24E
YERINGTON MINE LODE BR 1 S32-T14N-R25E  S5-T13N-R25E
YERINGTON MINE LODE BR 10 S5-T13N-R25E
YERINGTON MINE LODE BR 11 S32, 33-T14N-R25E  S4, 5-T13N-R25E
YERINGTON MINE LODE BR 12 S4, 5-T13N-R25E
YERINGTON MINE LODE BR 13 S5-T13N-R25E
YERINGTON MINE LODE BR 14 S5, 8-T13N-R25E
YERINGTON MINE LODE BR 15 S5-T13N-R25E
YERINGTON MINE LODE BR 16 S4, 5-T13N-R25E
YERINGTON MINE LODE BR 17 S4-T13N-R25E
YERINGTON MINE LODE BR 18 S4, 9-T13N-R25E
YERINGTON MINE LODE BR 19 S4-T13N-R25E
YERINGTON MINE LODE BR 2 S32-T14N-R25E  S5-T13N-R25E
YERINGTON MINE LODE BR 20 S4, 9-T13N-R25E
YERINGTON MINE LODE BR 21 S5, 8-T13N-R25E
YERINGTON MINE LODE BR 22 S8-T13N-R25E
YERINGTON MINE LODE BR 23 S4,5,8,9-T13N-R25E
YERINGTON MINE LODE BR 24 S8, 9-T13N-R25E
YERINGTON MINE LODE BR 25 S9-T13N-R25E
YERINGTON MINE LODE BR 26 S9-T13N-R25E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
YERINGTON MINE LODE BR 27 S4, 9-T13N-R25E
YERINGTON MINE LODE BR 28 S9-T13N-R25E
YERINGTON MINE LODE BR 29 S4, 9-T13N-R25E
YERINGTON MINE LODE BR 3 S32-T14N-R25E  S5-T13N-R25E
YERINGTON MINE LODE BR 30 S9-T13N-R25E
YERINGTON MINE LODE BR 31 S4, 9-T13N-R25E
YERINGTON MINE LODE BR 32 S9-T13N-R25E
YERINGTON MINE LODE BR 33 S4, 9-T13N-R25E
YERINGTON MINE LODE BR 34 S9-T13N-R25E
YERINGTON MINE LODE BR 35 S4, 9-T13N-R25E
YERINGTON MINE LODE BR 36 S9-T13N-R25E
YERINGTON MINE LODE BR 37 S4, 9-T13N-R25E
YERINGTON MINE LODE BR 38 S9-T13N-R25E
YERINGTON MINE LODE BR 39 S3,4,9,10-T13N-R25E
YERINGTON MINE LODE BR 4 S5-T13N-R25E
YERINGTON MINE LODE BR 40 S3, 4-T13N-R25E
YERINGTON MINE LODE BR 41 S8-T13N-R25E
YERINGTON MINE LODE BR 42 S8, 17-T13N-R25E
YERINGTON MINE LODE BR 43 S8-T13N-R25E
YERINGTON MINE LODE BR 44 S8,9,16,17-T13N-R25E
YERINGTON MINE LODE BR 45 S9, 16-T13N-R25E
YERINGTON MINE LODE BR 46 S9, 16-T13N-R25E
YERINGTON MINE LODE BR 47 S9-T13N-R25E
YERINGTON MINE LODE BR 48 S9, 16-T13N-R25E
YERINGTON MINE LODE BR 49 S9-T13N-R25E
YERINGTON MINE LODE BR 5 S32-T14N-R25E  S5-T13N-R25E
YERINGTON MINE LODE BR 50 S9-T13N-R25E
YERINGTON MINE LODE BR 51 S9-T13N-R25E
YERINGTON MINE LODE BR 52 S9-T13N-R25E
YERINGTON MINE LODE BR 53 S9-T13N-R25E
YERINGTON MINE LODE BR 54 S9-T13N-R25E
YERINGTON MINE LODE BR 55 S9-T13N-R25E
YERINGTON MINE LODE BR 56 S9-T13N-R25E
YERINGTON MINE LODE BR 57 S9-T13N-R25E
YERINGTON MINE LODE BR 58 S9-T13N-R25E
YERINGTON MINE LODE BR 59 S9-T13N-R25E
YERINGTON MINE LODE BR 6 S5-T13N-R25E
MACARTHUR CU LODE BR 60 S9-T25E-13N
MACARTHUR CU LODE BR 61 S9-T25E-13N
YERINGTON MINE LODE BR 7 S32-T14N-R25E  S5-T13N-R25E
YERINGTON MINE LODE BR 8 S5-T13N-R25E
YERINGTON MINE LODE BR 9 S32-T14N-R25E  S5-T13N-R25E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE MP 1 S26-T14N-R24E
MACARTHUR CU LODE MP 10 S26,35-T14N-R24E
MACARTHUR CU LODE MP 11 S26-T14N-R24E
MACARTHUR CU LODE MP 12 S26,35-T14N-R24E
MACARTHUR CU LODE MP 13 S25,26-T14N-R24E
MACARTHUR CU LODE MP 14 S25,26,35,36-T14N-R24E
MACARTHUR CU LODE MP 15 S25-T14N-R24E
MACARTHUR CU LODE MP 16 S25,36-T14N-R24E
MACARTHUR CU LODE MP 17 S25-T14N-R24E
MACARTHUR CU LODE MP 18 S25,36-T14N-R24E
MACARTHUR CU LODE MP 19 S25-T14N-R24E
MACARTHUR CU LODE MP 2 S26,35-T14N-R24E
MACARTHUR CU LODE MP 20 S25,36-T14N-R24E
MACARTHUR CU LODE MP 21 S25-T14N-R24E
MACARTHUR CU LODE MP 22 S25,36-T14N-R24E
MACARTHUR CU LODE MP 23 S25-T14N-R24E
MACARTHUR CU LODE MP 24 S25-T14N-R24E
MACARTHUR CU LODE MP 25 S25-T14N-R24E
MACARTHUR CU LODE MP 26 S25-T14N-R24E
MACARTHUR CU LODE MP 27 S25-T14N-R24E  S30-T14N-R25E
MACARTHUR CU LODE MP 28 S30-T14N-R25E
MACARTHUR CU LODE MP 29 S30-T14N-R25E
MACARTHUR CU LODE MP 3 S26-T14N-R24E
MACARTHUR CU LODE MP 30 S26-T14N-R24E
MACARTHUR CU LODE MP 31 S26-T14N-R24E
MACARTHUR CU LODE MP 32 S26-T14N-R24E
MACARTHUR CU LODE MP 33 S26-T14N-R24E
MACARTHUR CU LODE MP 34 S26-T14N-R24E
MACARTHUR CU LODE MP 35 S26-T14N-R24E
MACARTHUR CU LODE MP 36 S26-T14N-R24E
MACARTHUR CU LODE MP 37 S26-T14N-R24E
MACARTHUR CU LODE MP 38 S26-T14N-R24E
MACARTHUR CU LODE MP 39 S26-T14N-R24E
MACARTHUR CU LODE MP 4 S26,35-T14N-R24E
MACARTHUR CU LODE MP 40 S26-T14N-R24E
MACARTHUR CU LODE MP 41 S25, 26-T14N-R24E
MACARTHUR CU LODE MP 42 S25, 26-T14N-R24E
MACARTHUR CU LODE MP 43 S25-T14N-R24E
MACARTHUR CU LODE MP 44 S25-T14N-R24E
MACARTHUR CU LODE MP 45 S25-T14N-R24E
MACARTHUR CU LODE MP 46 S25-T14N-R24E
MACARTHUR CU LODE MP 47 S25-T14N-R24E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE MP 48 S25-T14N-R24E
MACARTHUR CU LODE MP 49 S25-T14N-R24E
MACARTHUR CU LODE MP 5 S26-T14N-R24E
MACARTHUR CU LODE MP 50 S25-T14N-R24E
MACARTHUR CU LODE MP 51 S25-T14N-R24E
MACARTHUR CU LODE MP 52 S25-T14N-R24E
MACARTHUR CU LODE MP 53 S25-T14N-R24E
MACARTHUR CU LODE MP 54 S25-T14N-R24E
MACARTHUR CU LODE MP 55 S25-T14N-R24E
MACARTHUR CU LODE MP 56 S25-T14N-R24E
MACARTHUR CU LODE MP 57 S25-T14N-R24E
MACARTHUR CU LODE MP 58 S25-T14N-R24E
MACARTHUR CU LODE MP 59 S25-T14N-R24E  S30-T14N-R25E
MACARTHUR CU LODE MP 6 S26,35-T14N-R24E
MACARTHUR CU LODE MP 60 S25-T14N-R24E  S30-T14N-R25E
MACARTHUR CU LODE MP 61 S30-T14N-R25E
MACARTHUR CU LODE MP 62 S30-T14N-R25E
MACARTHUR CU LODE MP 63 S30-T14N-R25E
MACARTHUR CU LODE MP 64 S30-T14N-R25E
MACARTHUR CU LODE MP 65 S30-T14N-R25E
MACARTHUR CU LODE MP 66 S30-T14N-R25E
MACARTHUR CU LODE MP 67 S30-T14N-R25E
MACARTHUR CU LODE MP 68 S30-T14N-R25E
MACARTHUR CU LODE MP 69 S30-T14N-R25E
MACARTHUR CU LODE MP 7 S26-T14N-R24E
MACARTHUR CU LODE MP 70 S30-T14N-R25E
MACARTHUR CU LODE MP 71 S30-T14N-R25E
MACARTHUR CU LODE MP 72 S30-T14N-R25E
MACARTHUR CU LODE MP 73 S24, 25-T14N-R24E
MACARTHUR CU LODE MP 74 S24, 25-T14N-R24E
MACARTHUR CU LODE MP 75 S24, 25-T14N-R24E
MACARTHUR CU LODE MP 76 S24, 25-T14N-R24E
MACARTHUR CU LODE MP 77 S24, 25-T14N-R24E
MACARTHUR CU LODE MP 78 S24, 25-T14N-R24E
MACARTHUR CU LODE MP 79 S24, 25-T14N-R24E
MACARTHUR CU LODE MP 8 S26,35-T14N-R24E
MACARTHUR CU LODE MP 80 S24, 25-T14N-R24E  S19, 30-T14N-R25E
MACARTHUR CU LODE MP 81 S19, 30-T14N-R25E
MACARTHUR CU LODE MP 82 S19, 30-T14N-R25E
MACARTHUR CU LODE MP 83 S19, 30-T14N-R25E
MACARTHUR CU LODE MP 84 S19, 30-T14N-R25E
MACARTHUR CU LODE MP 85 S19, 30-T14N-R25E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE MP 9 S26-T14N-R24E
YERINGTON MINE PLACER PLOXI 1 S5-T13S-R25E
YERINGTON MINE PLACER PLOXI 11 S4-T13S-R25E
YERINGTON MINE PLACER PLOXI 13 S4-T13S-R25E
YERINGTON MINE PLACER PLOXI 14 S4-T13S-R25E
YERINGTON MINE PLACER PLOXI 15 S5-T13S-R25E
YERINGTON MINE PLACER PLOXI 16 S5-T13S-R25E
YERINGTON MINE PLACER PLOXI 19 S8-T13S-R25E
YERINGTON MINE PLACER PLOXI 2 S5-T13S-R25E
YERINGTON MINE PLACER PLOXI 20 S8-T13S-R25E
YERINGTON MINE PLACER PLOXI 21 S9-T13S-R25E
YERINGTON MINE PLACER PLOXI 22 S9-T13S-R25E
YERINGTON MINE PLACER PLOXI 23 S9-T13S-R25E
YERINGTON MINE PLACER PLOXI 24 S9-T13S-R25E
YERINGTON MINE PLACER PLOXI 25 S9-T13S-R25E
YERINGTON MINE PLACER PLOXI 26 S9-T13S-R25E
YERINGTON MINE PLACER PLOXI 27 S9-T13S-R25E
YERINGTON MINE PLACER PLOXI 28 S9-T13S-R25E
YERINGTON MINE PLACER PLOXI 29 S9-T13S-R25E
YERINGTON MINE PLACER PLOXI 3 S5-T13S-R25E
YERINGTON MINE PLACER PLOXI 30 S9-T13S-R25E
YERINGTON MINE PLACER PLOXI 31 S9-T13S-R25E
YERINGTON MINE PLACER PLOXI 32 S9-T13S-R25E
YERINGTON MINE PLACER PLOXI 33 S8-T13S-R25E
YERINGTON MINE PLACER PLOXI 34 S8-T13S-R25E
YERINGTON MINE PLACER PLOXI 35 S9-T13S-R25E
YERINGTON MINE PLACER PLOXI 36 S9-T13S-R25E
YERINGTON MINE PLACER PLOXI 37 S9-T13S-R25E
YERINGTON MINE PLACER PLOXI 38 S9-T13S-R25E
YERINGTON MINE PLACER PLOXI 39 S8-T13S-R25E
YERINGTON MINE PLACER PLOXI 40 S8-T13S-R25E
YERINGTON MINE PLACER PLOXI 41 S8-T13S-R25E
YERINGTON MINE PLACER PLOXI 42 S8-T13S-R25E
YERINGTON MINE PLACER PLOXI 43 S17-T13S-R25E
YERINGTON MINE PLACER PLOXI 44 S17-T13S-R25E
YERINGTON MINE PLACER PLOXI 45 S17-T13S-R25E
YERINGTON MINE PLACER PLOXI 46 S16-T13S-R25E
YERINGTON MINE PLACER PLOXI 47 S16-T13S-R25E
YERINGTON MINE PLACER PLOXI 48 S16-T13S-R25E
YERINGTON MINE PLACER PLOXI 49 S16-T13S-R25E
YERINGTON MINE PLACER PLOXI 5 S5-T13S-R25E
YERINGTON MINE PLACER PLOXI 50 S16-T13S-R25E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
YERINGTON MINE PLACER PLOXI 51 S16-T13S-R25E
YERINGTON MINE PLACER PLOXI 53 S16-T13S-R25E
YERINGTON MINE PLACER PLOXI 54 S16-T13S-R25E
YERINGTON MINE PLACER PLOXI 55 S16-T13S-R25E
YERINGTON MINE PLACER PLOXI 56 S16-T13S-R25E
YERINGTON MINE PLACER PLOXI 57 S17-T13S-R25E
YERINGTON MINE PLACER PLOXI 58 S16-T13S-R25E
YERINGTON MINE PLACER PLOXI 59 S16-T13S-R25E
YERINGTON MINE PLACER PLOXI 6 S5-T13S-R25E
YERINGTON MINE PLACER PLOXI 60 S16-T13S-R25E
YERINGTON MINE PLACER PLOXI 61 S16-T13S-R25E
YERINGTON MINE PLACER PLOXI 62 S20-T13S-R25E
YERINGTON MINE PLACER PLOXI 63 S20-T13S-R25E
YERINGTON MINE PLACER PLOXI 64 S20-T13S-R25E
YERINGTON MINE PLACER PLOXI 65 S20-T13S-R25E
YERINGTON MINE PLACER PLOXI 66 S20-T13S-R25E
YERINGTON MINE PLACER PLOXI 67 S21-T13S-R25E
YERINGTON MINE PLACER PLOXI 68 S21-T13S-R25E
YERINGTON MINE PLACER PLOXI 69 S21-T13S-R25E
YERINGTON MINE PLACER PLOXI 70 S21-T13S-R25E
YERINGTON MINE PLACER PLOXI 71 S21-T13S-R25E
YERINGTON MINE PLACER PLOXI 72 S21-T13S-R25E
YERINGTON MINE PLACER PLOXI 73 S21-T13S-R25E
YERINGTON MINE PLACER PLOXI 74 S21-T13S-R25E
YERINGTON MINE PLACER PLOXI 75 S21-T13S-R25E
YERINGTON MINE PLACER PLOXI 76 S21-T13S-R25E
YERINGTON MINE PLACER PLOXI 77 S21-T13S-R25E
YERINGTON MINE PLACER PLOXI 78 S21-T13S-R25E
YERINGTON MINE PLACER PLOXI 79 S21-T13S-R25E
YERINGTON MINE PLACER PLOXI 80 S21-T13S-R25E
YERINGTON MINE PLACER PLOXI 81 S21-T13S-R25E
YERINGTON MINE PLACER PLOXI 82 S20-T13S-R25E
YERINGTON MINE PLACER PLOXI 83 S21-T13S-R25E
YERINGTON MINE PLACER PLOXI 84 S21-T13S-R25E
YERINGTON MINE PLACER PLOXI 85 S21-T13S-R25E
MACARTHUR CU LODE QT 1 S14,15,22,23-T14N-R24E
MACARTHUR CU LODE QT 10 S23-T14N-R24E
MACARTHUR CU LODE QT 101 S19-T14N-R25E
MACARTHUR CU LODE QT 103 S19-T14N-R25E
MACARTHUR CU LODE QT 104 S19, 30-T14N-R25E
MACARTHUR CU LODE QT 105 S19-T14N-R25E
MACARTHUR CU LODE QT 106 S19, 30-T14N-R25E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE QT 107 S19, 20-T14N-R25E
MACARTHUR CU LODE QT 108 S19,20,29,30-T14N-R25E
MACARTHUR CU LODE QT 109 S20, 29-T14N-R25E
MACARTHUR CU LODE QT 11 S14, 23-T14N-R24E
MACARTHUR CU LODE QT 110 S20, 29-T14N-R25E
MACARTHUR CU LODE QT 111 S26, 27-T14N-R24E
MACARTHUR CU LODE QT 112 S26, 27-T14N-R24E
MACARTHUR CU LODE QT 113 S26-T14N-R24E
MACARTHUR CU LODE QT 114 S26-T14N-R24E
MACARTHUR CU LODE QT 115 S26-T14N-R24E
MACARTHUR CU LODE QT 116 S26-T14N-R24E
MACARTHUR CU LODE QT 117 S26-T14N-R24E
MACARTHUR CU LODE QT 12 S24-T14N-R24E
MACARTHUR CU LODE QT 13 S14, 23-T14N-R24E
MACARTHUR CU LODE QT 133 S30-T14N-R25E
MACARTHUR CU LODE QT 135 S29, 30-T14N-R25E
MACARTHUR CU LODE QT 136 S29, 30-T14N-R25E
MACARTHUR CU LODE QT 137 S29-T14N-R25E
MACARTHUR CU LODE QT 138 S29-T14N-R25E
MACARTHUR CU LODE QT 139 S29-T14N-R25E
MACARTHUR CU LODE QT 14 S23-T14N-R24E
MACARTHUR CU LODE QT 140 S29-T14N-R25E
MACARTHUR CU LODE QT 141 S26, 27-T14N-R24E
MACARTHUR CU LODE QT 142 S26, 27-T14N-R24E
MACARTHUR CU LODE QT 143 S26-T14N-R24E
MACARTHUR CU LODE QT 144 S26, 35-T14N-R24E
MACARTHUR CU LODE QT 145 S26-T14N-R24E
MACARTHUR CU LODE QT 146 S26, 35-T14N-R24E
MACARTHUR CU LODE QT 15 S14, 23-T14N-R24E
MACARTHUR CU LODE QT 152 S25, 36-T14N-R24E
MACARTHUR CU LODE QT 154 S25, 36-T14N-R24E
MACARTHUR CU LODE QT 156 S25, 36-T14N-R24E
MACARTHUR CU LODE QT 158 S25, 36-T14N-R24E
MACARTHUR CU LODE QT 16 S23-T14N-R24E
MACARTHUR CU LODE QT 160 S25, 36-T14N-R24E  S30, 31-T14N-R25E
MACARTHUR CU LODE QT 161 S30-T14N-R25E
MACARTHUR CU LODE QT 162 S30, 31-T14N-R25E
MACARTHUR CU LODE QT 163 S30-T14N-R25E
MACARTHUR CU LODE QT 164 S30, 31-T14N-R25E
MACARTHUR CU LODE QT 165 S30-T14N-R25E
MACARTHUR CU LODE QT 166 S30, 31-T14N-R25E
MACARTHUR CU LODE QT 167 S30-T14N-R25E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE QT 168 S30, 31-T14N-R25E
MACARTHUR CU LODE QT 17 S14, 23-T14N-R24E
MACARTHUR CU LODE QT 170 S30, 31-T14N-R25E
MACARTHUR CU LODE QT 171 S30-T14N-R25E
MACARTHUR CU LODE QT 173 S29, 30-T14N-R25E
MACARTHUR CU LODE QT 174 S29, 30-T14N-R25E
MACARTHUR CU LODE QT 175 S29-T14N-R25E
MACARTHUR CU LODE QT 176 S29-T14N-R25E
MACARTHUR CU LODE QT 177 S34, 35-T14N-R24E
MACARTHUR CU LODE QT 178 S35-T14N-R24E
MACARTHUR CU LODE QT 179 S35-T14N-R24E
MACARTHUR CU LODE QT 18 S23-T14N-R24E
MACARTHUR CU LODE QT 180 S35-T14N-R24E
MACARTHUR CU LODE QT 181 S35-T14N-R24E
MACARTHUR CU LODE QT 182 S35-T14N-R24E
MACARTHUR CU LODE QT 183 S35-T14N-R24E
MACARTHUR CU LODE QT 184 S35-T14N-R24E
MACARTHUR CU LODE QT 185 S35-T14N-R24E
MACARTHUR CU LODE QT 186 S35-T14N-R24E
MACARTHUR CU LODE QT 187 S35-T14N-R24E
MACARTHUR CU LODE QT 188 S35-T14N-R24E
MACARTHUR CU LODE QT 189 S35-T14N-R24E
MACARTHUR CU LODE QT 19 S13,14,23,24-T14N-R24E
MACARTHUR CU LODE QT 190 S35-T14N-R24E
MACARTHUR CU LODE QT 191 S35-T14N-R24E
MACARTHUR CU LODE QT 192 S35-T14N-R24E
MACARTHUR CU LODE QT 193 S35-T14N-R24E
MACARTHUR CU LODE QT 194 S35-T14N-R24E
MACARTHUR CU LODE QT 195 S35-T14N-R24E
MACARTHUR CU LODE QT 196 S35, 36-T14N-R24E
MACARTHUR CU LODE QT 197 S36-T14N-R24E
MACARTHUR CU LODE QT 198 S36-T14N-R24E
MACARTHUR CU LODE QT 199 S36-T14N-R24E
MACARTHUR CU LODE QT 2 S22, 23-T14N-R24E
MACARTHUR CU LODE QT 20 S23, 24-T14N-R24E
MACARTHUR CU LODE QT 200 S36-T14N-R24E
MACARTHUR CU LODE QT 201 S36-T14N-R24E
MACARTHUR CU LODE QT 202 S36-T14N-R24E
MACARTHUR CU LODE QT 203 S36-T14N-R24E
MACARTHUR CU LODE QT 204 S36-T14N-R24E
MACARTHUR CU LODE QT 205 S36-T14N-R24E
MACARTHUR CU LODE QT 206 S36-T14N-R24E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE QT 207 S36-T14N-R24E
MACARTHUR CU LODE QT 208 S36-T14N-R24E
MACARTHUR CU LODE QT 209 S36-T14N-R24E
MACARTHUR CU LODE QT 21 S13, 24-T14N-R24E
MACARTHUR CU LODE QT 210 S36-T14N-R24E
MACARTHUR CU LODE QT 211 S36-T14N-R24E  S31-T14N-R25E
MACARTHUR CU LODE QT 212 S36-T14N-R24E  S31-T14N-R25E
MACARTHUR CU LODE QT 213 S31-T14N-R25E
MACARTHUR CU LODE QT 214 S31-T14N-R25E
MACARTHUR CU LODE QT 215 S31-T14N-R25E
MACARTHUR CU LODE QT 216 S31-T14N-R25E
MACARTHUR CU LODE QT 217 S31-T14N-R25E
MACARTHUR CU LODE QT 218 S31-T14N-R25E
MACARTHUR CU LODE QT 219 S31-T14N-R25E
MACARTHUR CU LODE QT 22 S24-T14N-R24E
MACARTHUR CU LODE QT 220 S31-T14N-R25E
MACARTHUR CU LODE QT 221 S31-T14N-R25E
MACARTHUR CU LODE QT 222 S31-T14N-R25E
MACARTHUR CU LODE QT 223 S31-T14N-R25E
MACARTHUR CU LODE QT 224 S31-T14N-R25E
MACARTHUR CU LODE QT 23 S13, 24-T14N-R24E
MACARTHUR CU LODE QT 24 S24-T14N-R24E
MACARTHUR CU LODE QT 25 S13, 24-T14N-R24E
MACARTHUR CU LODE QT 251 S27-T14N-R24E  S34-T14N-R24E
MACARTHUR CU LODE QT 252 S27-T14N-R24E  S34-T14N-R24E
MACARTHUR CU LODE QT 253 S34-T14N-R24E
MACARTHUR CU LODE QT 254 S34-T14N-R24E
MACARTHUR CU LODE QT 255 S34-T14N-R24E
MACARTHUR CU LODE QT 256 S34-T14N-R24E
MACARTHUR CU LODE QT 257 S3-T13N-R24E  S34-T14N-R24E
MACARTHUR CU LODE QT 258 S3-T13N-R24E
MACARTHUR CU LODE QT 259 S3-T13N-R24E  S34-T14N-R24E
MACARTHUR CU LODE QT 26 S24-T14N-R24E
MACARTHUR CU LODE QT 260 S3-T13N-R24E
MACARTHUR CU LODE QT 261 S2, 3-T13N-R24E  S34, 35-T14N-R24E
MACARTHUR CU LODE QT 262 S2, 3-T13N-R24E
MACARTHUR CU LODE QT 263 S2-T13N-R24E  S35-T14N-R24E
MACARTHUR CU LODE QT 264 S2-T13N-R24E
MACARTHUR CU LODE QT 265 S2-T13N-R24E  S35-T14N-R24E
MACARTHUR CU LODE QT 266 S2-T13N-R24E
MACARTHUR CU LODE QT 267 S2-T13N-R24E  S35-T14N-R24E
MACARTHUR CU LODE QT 268 S2-T13N-R24E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE QT 269 S2-T13N-R24E  S35-T14N-R24E
MACARTHUR CU LODE QT 27 S13, 24-T14N-R24E
MACARTHUR CU LODE QT 270 S2-T13N-R24E
MACARTHUR CU LODE QT 271 S2-T13N-R24E  S35-T14N-R24E
MACARTHUR CU LODE QT 272 S2-T13N-R24E
MACARTHUR CU LODE QT 273 S2-T13N-R24E  S35-T14N-R24E
MACARTHUR CU LODE QT 274 S2-T13N-R24E
MACARTHUR CU LODE QT 275 S2-T13N-R24E  S35-T14N-R24E
MACARTHUR CU LODE QT 276 S2-T13N-R24E
MACARTHUR CU LODE QT 28 S24-T14N-R24E
MACARTHUR CU LODE QT 29 S13, 24-T14N-R24E
MACARTHUR CU LODE QT 3 S14, 23-T14N-R24E
MACARTHUR CU LODE QT 30 S24-T14N-R24E
MACARTHUR CU LODE QT 31 S13, 24-T14N-R24E
MACARTHUR CU LODE QT 32 S24-T14N-R24E
MACARTHUR CU LODE QT 33 S13, 24-T14N-R24E
MACARTHUR CU LODE QT 34 S24-T14N-R24E
MACARTHUR CU LODE QT 35 S13, 24-T14N-R24E
MACARTHUR CU LODE QT 36 S24-T14N-R24E
MACARTHUR CU LODE QT 37 S13, 24-T14N-R24E  S18, 19-T14N-R25E
MACARTHUR CU LODE QT 38 S24-T14N-R24E  S19-T14N-R25E
MACARTHUR CU LODE QT 39 S18, 19-T14N-R25E
MACARTHUR CU LODE QT 4 S23-T14N-R24E
MACARTHUR CU LODE QT 40 S19-T14N-R25E
MACARTHUR CU LODE QT 41 S18, 19-T14N-R25E
MACARTHUR CU LODE QT 42 S19-T14N-R25E
MACARTHUR CU LODE QT 43 S18, 19-T14N-R25E
MACARTHUR CU LODE QT 44 S19-T14N-R25E
MACARTHUR CU LODE QT 45 S18, 19-T14N-R25E
MACARTHUR CU LODE QT 46 S19-T14N-R25E
MACARTHUR CU LODE QT 47 S18, 19-T14N-R25E
MACARTHUR CU LODE QT 48 S19-T14N-R25E
MACARTHUR CU LODE QT 49 S18, 19-T14N-R25E
MACARTHUR CU LODE QT 5 S14, 23-T14N-R24E
MACARTHUR CU LODE QT 50 S19-T14N-R25E
MACARTHUR CU LODE QT 51 S18, 19-T14N-R25E
MACARTHUR CU LODE QT 52 S19-T14N-R25E
MACARTHUR CU LODE QT 53 S17,18,19,20-T14N-R25E
MACARTHUR CU LODE QT 54 S19, 20-T14N-R25E
MACARTHUR CU LODE QT 55 S22, 23-T14N-R24E
MACARTHUR CU LODE QT 56 S22,23,26,27-T14N-R24E
MACARTHUR CU LODE QT 57 S23-T14N-R24E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE QT 58 S23, 26-T14N-R24E
MACARTHUR CU LODE QT 59 S23-T14N-R24E
MACARTHUR CU LODE QT 6 S23-T14N-R24E
MACARTHUR CU LODE QT 60 S23, 26-T14N-R24E
MACARTHUR CU LODE QT 61 S23-T14N-R24E
MACARTHUR CU LODE QT 62 S23, 26-T14N-R24E
MACARTHUR CU LODE QT 63 S23-T14N-R24E
MACARTHUR CU LODE QT 64 S23, 26-T14N-R24E
MACARTHUR CU LODE QT 65 S23-T14N-R24E
MACARTHUR CU LODE QT 66 S23, 26-T14N-R24E
MACARTHUR CU LODE QT 67 S23-T14N-R24E
MACARTHUR CU LODE QT 68 S23, 26-T14N-R24E
MACARTHUR CU LODE QT 69 S23-T14N-R24E
MACARTHUR CU LODE QT 7 S14, 23-T14N-R24E
MACARTHUR CU LODE QT 70 S23, 26-T14N-R24E
MACARTHUR CU LODE QT 71 S23-T14N-R24E
MACARTHUR CU LODE QT 72 S23, 26-T14N-R24E
MACARTHUR CU LODE QT 73 S23, 24-T14N-R24E
MACARTHUR CU LODE QT 74 S23,24,25,26-T14N-R24E
MACARTHUR CU LODE QT 75 S24-T14N-R24E
MACARTHUR CU LODE QT 76 S24, 25-T14N-R24E
MACARTHUR CU LODE QT 77 S24-T14N-R24E
MACARTHUR CU LODE QT 79 S24-T14N-R24E
MACARTHUR CU LODE QT 8 S23-T14N-R24E
MACARTHUR CU LODE QT 81 S24-T14N-R24E
MACARTHUR CU LODE QT 83 S24-T14N-R24E
MACARTHUR CU LODE QT 85 S24-T14N-R24E
MACARTHUR CU LODE QT 87 S24-T14N-R24E
MACARTHUR CU LODE QT 89 S24-T14N-R24E
MACARTHUR CU LODE QT 9 S14, 23-T14N-R24E
MACARTHUR CU LODE QT 91 S24-T14N-R24E  S19-T14N-R25E
MACARTHUR CU LODE QT 93 S19-T14N-R25E
MACARTHUR CU LODE QT 95 S19-T14N-R25E
MACARTHUR CU LODE QT 97 S19-T14N-R25E
MACARTHUR CU LODE QT 99 S19-T14N-R25E
MACARTHUR CU LODE SC 1 S19,20-T13N-R25E
MACARTHUR CU LODE SC 10 S20,29-T13N-R25E
MACARTHUR CU LODE SC 100 S18-T13N-R25E
MACARTHUR CU LODE SC 101 S18-T13N-R25E
MACARTHUR CU LODE SC 102 S18-T13N-R25E
MACARTHUR CU LODE SC 103 S18-T13N-R25E
MACARTHUR CU LODE SC 104 S18-T13N-R25E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE SC 105 S18-T13N-R25E
MACARTHUR CU LODE SC 106 S18-T13N-R25E
MACARTHUR CU LODE SC 107 S18-T13N-R25E
MACARTHUR CU LODE SC 108 S18-T13N-R25E
MACARTHUR CU LODE SC 109 S17,18-T13N-R25E
MACARTHUR CU LODE SC 11 S20-T13N-R25E
MACARTHUR CU LODE SC 110 S17,18-T13N-R25E
MACARTHUR CU LODE SC 111 S17-T13N-R25E
MACARTHUR CU LODE SC 112 S17-T13N-R25E
MACARTHUR CU LODE SC 113 S17-T13N-R25E
MACARTHUR CU LODE SC 114 S17-T13N-R25E
MACARTHUR CU LODE SC 115 S12-T13N-R24E
MACARTHUR CU LODE SC 116 S12,13-T13N-R24E
MACARTHUR CU LODE SC 117 S12-T13N-R24E
MACARTHUR CU LODE SC 118 S12,13-T13N-R24E
MACARTHUR CU LODE SC 119 S12-T13N-R24E
MACARTHUR CU LODE SC 12 S20,29-T13N-R25E
MACARTHUR CU LODE SC 120 S12,13-T13N-R24E
MACARTHUR CU LODE SC 121 S12-T13N-R24E
MACARTHUR CU LODE SC 122 S12,13-T13N-R24E
MACARTHUR CU LODE SC 123 S12-T13N-R24E; S7-T13N-R25E
MACARTHUR CU LODE SC 124 S12,13-T13N-R24E; S7,18-T13N-R25E
MACARTHUR CU LODE SC 125 S7-T13N-R25E
MACARTHUR CU LODE SC 126 S7,18-T13N-R25E
MACARTHUR CU LODE SC 127 S7-T13N-R25E
MACARTHUR CU LODE SC 128 S7,18-T13N-R25E
MACARTHUR CU LODE SC 129 S7-T13N-R25E
YERINGTON MINE LODE SC 13 S20-T13N-R25E
MACARTHUR CU LODE SC 130 S7,18-T13N-R25E
MACARTHUR CU LODE SC 131 S7-T13N-R25E
MACARTHUR CU LODE SC 132 S7,18-T13N-R25E
MACARTHUR CU LODE SC 133 S7-T13N-R25E
MACARTHUR CU LODE SC 134 S7,18-T13N-R25E
MACARTHUR CU LODE SC 135 S7-T13N-R25E
MACARTHUR CU LODE SC 136 S7,18-T13N-R25E
MACARTHUR CU LODE SC 137 S7-T13N-R25E
MACARTHUR CU LODE SC 138 S7,18-T13N-R25E
MACARTHUR CU LODE SC 139 S7,8-T13N-R25E
MACARTHUR CU LODE SC 14 S20,29-T13N-R25E
MACARTHUR CU LODE SC 140 S7,8,17,18-T13N-R25E
MACARTHUR CU LODE SC 141 S1,2,11,12-T13N-R24E
MACARTHUR CU LODE SC 142 S11,12-T13N-R24E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE SC 143 S1,12-T13N-R24E
MACARTHUR CU LODE SC 144 S12-T13N-R24E
MACARTHUR CU LODE SC 145 S1,12-T13N-R24E
MACARTHUR CU LODE SC 146 S12-T13N-R24E
MACARTHUR CU LODE SC 147 S1,12-T13N-R24E
MACARTHUR CU LODE SC 148 S12-T13N-R24E
MACARTHUR CU LODE SC 149 S1,12-T13N-R24E
YERINGTON MINE LODE SC 15 S20-T13N-R25E
MACARTHUR CU LODE SC 150 S12-T13N-R24E
MACARTHUR CU LODE SC 151 S1,12-T13N-R24E
MACARTHUR CU LODE SC 152 S12-T13N-R24E
MACARTHUR CU LODE SC 153 S1,12-T13N-R24E
MACARTHUR CU LODE SC 154 S12-T13N-R24E
MACARTHUR CU LODE SC 155 S1,12-T13N-R24E
MACARTHUR CU LODE SC 156 S12-T13N-R24E
MACARTHUR CU LODE SC 157 S1,12-T13N-R24E
MACARTHUR CU LODE SC 158 S12-T13N-R24E
MACARTHUR CU LODE SC 159 S1,12-T13N-R24E; S6,7-T13N-R25E
YERINGTON MINE LODE SC 16 S20,29-T13N-R25E
MACARTHUR CU LODE SC 160 S12-T13N-R24E; S7-T13N-R25E
MACARTHUR CU LODE SC 161 S6,7-T13N-R25E
MACARTHUR CU LODE SC 162 S7-T13N-R25E
MACARTHUR CU LODE SC 163 S6,7-T13N-R25E
MACARTHUR CU LODE SC 164 S7-T13N-R25E
MACARTHUR CU LODE SC 165 S6,7-T13N-R25E
MACARTHUR CU LODE SC 166 S7-T13N-R25E
MACARTHUR CU LODE SC 167 S6,7-T13N-R25E
MACARTHUR CU LODE SC 168 S7-T13N-R25E
MACARTHUR CU LODE SC 169 S6,7-T13N-R25E
YERINGTON MINE LODE SC 17 S20-T13N-R25E
MACARTHUR CU LODE SC 170 S7-T13N-R25E
MACARTHUR CU LODE SC 171 S6,7-T13N-R25E
MACARTHUR CU LODE SC 172 S7-T13N-R25E
MACARTHUR CU LODE SC 173 S6,7-T13N-R25E
MACARTHUR CU LODE SC 174 S7-T13N-R25E
MACARTHUR CU LODE SC 175 S5,6,7,8-T13N-R25E
MACARTHUR CU LODE SC 176 S7,8-T13N-R25E
MACARTHUR CU LODE SC 177 S1,2-T13N-R24E
MACARTHUR CU LODE SC 178 S1,2-T13N-R24E
MACARTHUR CU LODE SC 179 S1-T13N-R24E
YERINGTON MINE LODE SC 18 S20,29-T13N-R25E
MACARTHUR CU LODE SC 180 S1-T13N-R24E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE SC 181 S1-T13N-R24E
MACARTHUR CU LODE SC 182 S1-T13N-R24E
MACARTHUR CU LODE SC 183 S1-T13N-R24E
MACARTHUR CU LODE SC 184 S1-T13N-R24E
MACARTHUR CU LODE SC 185 S1-T13N-R24E
MACARTHUR CU LODE SC 186 S1-T13N-R24E
MACARTHUR CU LODE SC 187 S1-T13N-R24E
MACARTHUR CU LODE SC 188 S1-T13N-R24E
MACARTHUR CU LODE SC 189 S1-T13N-R24E
MACARTHUR CU LODE SC 19 S19,20-T13N-R25E
MACARTHUR CU LODE SC 190 S1-T13N-R24E
MACARTHUR CU LODE SC 191 S1-T13N-R24E
MACARTHUR CU LODE SC 192 S1-T13N-R24E
MACARTHUR CU LODE SC 193 S1-T13N-R24E
MACARTHUR CU LODE SC 194 S1-T13N-R24E
MACARTHUR CU LODE SC 195 S1-T13N-R24E; S6-T13N-R25E
MACARTHUR CU LODE SC 196 S1-T13N-R24E; S6-T13N-R25E
MACARTHUR CU LODE SC 197 S6-T13N-R25E
MACARTHUR CU LODE SC 198 S6-T13N-R25E
MACARTHUR CU LODE SC 199 S6-T13N-R25E
MACARTHUR CU LODE SC 2 S19,20,29,30-T13N-R25E
MACARTHUR CU LODE SC 20 S20-T13N-R25E
MACARTHUR CU LODE SC 200 S6-T13N-R25E
MACARTHUR CU LODE SC 201 S6-T13N-R25E
MACARTHUR CU LODE SC 202 S6-T13N-R25E
MACARTHUR CU LODE SC 203 S6-T13N-R25E
MACARTHUR CU LODE SC 204 S6-T13N-R25E
MACARTHUR CU LODE SC 205 S6-T13N-R25E
MACARTHUR CU LODE SC 206 S6-T13N-R25E
MACARTHUR CU LODE SC 207 S1,2-T13N-R24E; S35-T14N-R24E
MACARTHUR CU LODE SC 208 S1,2-T13N-R24E
MACARTHUR CU LODE SC 209 S1-T13N-R24E; S35,36-T14N-R24E
MACARTHUR CU LODE SC 21 S20-T13N-R25E
MACARTHUR CU LODE SC 210 S1-T13N-R24E
MACARTHUR CU LODE SC 211 S1-T13N-R24E; S36-T14N-R24E
MACARTHUR CU LODE SC 212 S1-T13N-R24E
MACARTHUR CU LODE SC 213 S1-T13N-R24E; S36-T14N-R24E
MACARTHUR CU LODE SC 214 S1-T13N-R24E
MACARTHUR CU LODE SC 215 S1-T13N-R24E; S36-T14N-R24E
MACARTHUR CU LODE SC 216 S1-T13N-R24E
MACARTHUR CU LODE SC 217 S1-T13N-R24E; S36-T14N-R24E
MACARTHUR CU LODE SC 218 S1-T13N-R24E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE SC 219 S1-T13N-R24E; S36-T14N-R24E
MACARTHUR CU LODE SC 22 S20-T13N-R25E
MACARTHUR CU LODE SC 220 S1-T13N-R24E
MACARTHUR CU LODE SC 221 S1-T13N-R24E; S36-T14N-R24E
MACARTHUR CU LODE SC 222 S1-T13N-R24E
MACARTHUR CU LODE SC 223 S1-T13N-R24E; S36-T14N-R24E
MACARTHUR CU LODE SC 224 S1-T13N-R24E
MACARTHUR CU LODE SC 225 S1-T13N-R24E; S6-T13N-R25E; S36-T14N-R24E; S31-T14N-R25E
MACARTHUR CU LODE SC 226 S1-T13N-R24E; S6-T13N-R25E
MACARTHUR CU LODE SC 227 S6-T13N-R25E; S31-T14N-R25E
MACARTHUR CU LODE SC 229 S6-T13N-R25E; S31-T14N-R25E
MACARTHUR CU LODE SC 23 S20-T13N-R25E
MACARTHUR CU LODE SC 231 S6-T13N-R25E; S31-T14N-R25E
MACARTHUR CU LODE SC 232 S6-T13N-R25E
MACARTHUR CU LODE SC 233 S6-T13N-R25E; S31-T14N-R25E
MACARTHUR CU LODE SC 234 S6-T13N-R25E
MACARTHUR CU LODE SC 235 S11-T13N-R24E
MACARTHUR CU LODE SC 236 S11, 14-T13N-R24E
MACARTHUR CU LODE SC 237 S11-T13N-R24E
MACARTHUR CU LODE SC 238 S11, 14-T13N-R24E
MACARTHUR CU LODE SC 239 S11, 12-T13N-R24E
MACARTHUR CU LODE SC 24 S20-T13N-R25E
MACARTHUR CU LODE SC 240 S11, 12, 13, 14-T13N-R24E
MACARTHUR CU LODE SC 241 S12-T13N-R24E
MACARTHUR CU LODE SC 242 S12, 13-T13N-R24E
MACARTHUR CU LODE SC 243 S12-T13N-R24E
MACARTHUR CU LODE SC 244 S12, 13-T13N-R24E
MACARTHUR CU LODE SC 245 S12-T13N-R24E
MACARTHUR CU LODE SC 246 S12-T13N-R24E
MACARTHUR CU LODE SC 247 S12-T13N-R24E
MACARTHUR CU LODE SC 248 S12, 13-T13N-R24E
MACARTHUR CU LODE SC 249 S2, 11-T13N-R24E
YERINGTON MINE LODE SC 25 S20-T13N-R25E
MACARTHUR CU LODE SC 250 S11-T13N-R24E
MACARTHUR CU LODE SC 251 S2, 11-T13N-R24E
MACARTHUR CU LODE SC 252 S11-T13N-R24E
MACARTHUR CU LODE SC 253 S2-T13N-R24E
MACARTHUR CU LODE SC 254 S2-T13N-R24E
MACARTHUR CU LODE SC 255 S2-T13N-R24E
MACARTHUR CU LODE SC 256 S2-T13N-R24E
MACARTHUR CU LODE SC 257 S13-T13N-R24E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE SC 258 S13-T13N-R24E
MACARTHUR CU LODE SC 259 S13-T13N-R24E
YERINGTON MINE LODE SC 26 S20-T13N-R25E
MACARTHUR CU LODE SC 260 S13, 24-T13N-R24E
MACARTHUR CU LODE SC 261 S13, 24-T13N-R24E
MACARTHUR CU LODE SC 262 S24-T13N-R24E
MACARTHUR CU LODE SC 263 S24-T13N-R24E; S19-T13N-R25E
MACARTHUR CU LODE SC 264 S13-T13N-R24E
MACARTHUR CU LODE SC 265 S13-T13N-R24E
MACARTHUR CU LODE SC 266 S13-T13N-R24E
MACARTHUR CU LODE SC 267 S2-T13N-R24E
YERINGTON MINE LODE SC 27 S20-T13N-R25E
YERINGTON MINE LODE SC 28 S20,21-T13N-R25E
YERINGTON MINE LODE SC 29 S20,21-T13N-R25E
MACARTHUR CU LODE SC 294 S26-T13N-R24E
MACARTHUR CU LODE SC 295 S26-T13N-R24E
MACARTHUR CU LODE SC 296 S25,26-T13N-R24E
MACARTHUR CU LODE SC 297 S25,26-T13N-R24E
MACARTHUR CU LODE SC 298 S25-T13N-R24E
MACARTHUR CU LODE SC 299 S25-T13N-R24E
MACARTHUR CU LODE SC 3 S20-T13N-R25E
YERINGTON MINE LODE SC 30 S21-T13N-R25E
MACARTHUR CU LODE SC 300 S25-T13N-R24E
MACARTHUR CU LODE SC 301 S25-T13N-R24E
MACARTHUR CU LODE SC 302 S25-T13N-R24E
MACARTHUR CU LODE SC 303 S25-T13N-R24E
MACARTHUR CU LODE SC 304 S25-T13N-R24E
MACARTHUR CU LODE SC 305 S25-T13N-R24E
MACARTHUR CU LODE SC 306 S25-T13N-R24E
MACARTHUR CU LODE SC 307 S25-T13N-R24E
MACARTHUR CU LODE SC 308 S25-T13N-R24E
MACARTHUR CU LODE SC 309 S25-T13N-R24E
YERINGTON MINE LODE SC 31 S21-T13N-R25E
MACARTHUR CU LODE SC 310 S25-T13N-R24E
MACARTHUR CU LODE SC 311 S25-T13N-R24E
MACARTHUR CU LODE SC 312 S25-T13N-R24E
MACARTHUR CU LODE SC 313 S25-T13N-R24E
MACARTHUR CU LODE SC 314 S30-T13N-R25E
MACARTHUR CU LODE SC 315 S30-T13N-R25E
MACARTHUR CU LODE SC 316 S30-T13N-R25E
MACARTHUR CU LODE SC 317 S30-T13N-R25E
MACARTHUR CU LODE SC 318 S30-T13N-R25E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE SC 319 S30-T13N-R25E
YERINGTON MINE LODE SC 32 S21-T13N-R25E
MACARTHUR CU LODE SC 320 S30-T13N-R25E
MACARTHUR CU LODE SC 321 S30-T13N-R25E
MACARTHUR CU LODE SC 322 S25,36-T13N-R25E
MACARTHUR CU LODE SC 323 S25-T13N-R24E
MACARTHUR CU LODE SC 324 S25,36-T13N-R24E
MACARTHUR CU LODE SC 325 S25-T13N-R24E
MACARTHUR CU LODE SC 326 S25,36-T13N-R24E
MACARTHUR CU LODE SC 327 S25-T13N-R24E
MACARTHUR CU LODE SC 328 S25,36-T13N-R24E
MACARTHUR CU LODE SC 329 S25-T13N-R24E
YERINGTON MINE LODE SC 33 S21-T13N-R25E
MACARTHUR CU LODE SC 330 S25,36-T13N-R24E
MACARTHUR CU LODE SC 331 S25-T13N-R24E
MACARTHUR CU LODE SC 332 S25,36-T13N-R24E
MACARTHUR CU LODE SC 333 S25-T13N-R24E
MACARTHUR CU LODE SC 334 S25,36-T13N-R24E
MACARTHUR CU LODE SC 335 S25-T13N-R24E
MACARTHUR CU LODE SC 336 S35,36-T13N-R24E
MACARTHUR CU LODE SC 337 S36-T13N-R24E
MACARTHUR CU LODE SC 338 S36-T13N-R24E
MACARTHUR CU LODE SC 339 S36-T13N-R24E
YERINGTON MINE LODE SC 34 S21-T13N-R25E
MACARTHUR CU LODE SC 340 S36-T13N-R24E
MACARTHUR CU LODE SC 341 S36-T13N-R24E
MACARTHUR CU LODE SC 342 S36-T13N-R24E
MACARTHUR CU LODE SC 343 S36-T13N-R24E
MACARTHUR CU LODE SC 344 S36-T13N-R24E
MACARTHUR CU LODE SC 345 S36-T13N-R24E
MACARTHUR CU LODE SC 346 S36-T13N-R24E
MACARTHUR CU LODE SC 347 S36-T13N-R24E
MACARTHUR CU LODE SC 348 S36-T13N-R24E
MACARTHUR CU LODE SC 349 S36-T13N-R24E
YERINGTON MINE LODE SC 35 S20,21,28,29-T13N-R25E
MACARTHUR CU LODE SC 350 S36-T13N-R24E
MACARTHUR CU LODE SC 351 S36-T13N-R24E
MACARTHUR CU LODE SC 352 S36-T13N-R24E
MACARTHUR CU LODE SC 353 S35-T13N-R24E
MACARTHUR CU LODE SC 354 S2-T12N-R24E
MACARTHUR CU LODE SC 355 S35-T13N-R24E
MACARTHUR CU LODE SC 356 S2-T12N-R24E, S35-T13N-R24E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE SC 357 S35-T13N-R24E
MACARTHUR CU LODE SC 358 S2-T12N-R24E, S35-T13N-R24E
MACARTHUR CU LODE SC 359 S35-T13N-R24E
YERINGTON MINE LODE SC 36 S21,28-T13N-R25E
MACARTHUR CU LODE SC 360 S2-T12N-R24E, S35-T13N-R24E
MACARTHUR CU LODE SC 361 S35-T13N-R24E
MACARTHUR CU LODE SC 362 S2-T12N-R24E, S35-T13N-R24E
MACARTHUR CU LODE SC 363 S1,2-T12N-R24E, S35,36-T13N-R24E
MACARTHUR CU LODE SC 364 S1-T12N-R24E, S36-T13N-R24E
MACARTHUR CU LODE SC 365 S1-T12N-R24E, S36-T13N-R24E
MACARTHUR CU LODE SC 366 S1-T12N-R24E, S36-T13N-R24E
MACARTHUR CU LODE SC 367 S1-T12N-R24E, S36-T13N-R24E
MACARTHUR CU LODE SC 368 S1-T12N-R24E, S36-T13N-R24E
MACARTHUR CU LODE SC 369 S1-T12N-R24E, S36-T13N-R24E
YERINGTON MINE LODE SC 37 S21,28-T13N-R25E
MACARTHUR CU LODE SC 370 S35-T13N-R24E
MACARTHUR CU LODE SC 371 S25,36-T13N-R24E
YERINGTON MINE LODE SC 38 S21,28-T13N-R25E
YERINGTON MINE LODE SC 39 S21-T13N-R25E
MACARTHUR CU LODE SC 4 S20,29-T13N-R25E
YERINGTON MINE LODE SC 40 S21,28-T13N-R25E
YERINGTON MINE LODE SC 41 S21-T13N-R25E
YERINGTON MINE LODE SC 42 S21,28-T13N-R25E
YERINGTON MINE LODE SC 43 S21-T13N-R25E
MACARTHUR CU LODE SC 44 S19,30-T13N-R25E
MACARTHUR CU LODE SC 45 S19,30-T13N-R25E
MACARTHUR CU LODE SC 46 S19,30-T13N-R25E
MACARTHUR CU LODE SC 47 S19,30-T13N-R25E
MACARTHUR CU LODE SC 48 S19,30-T13N-R25E
MACARTHUR CU LODE SC 49 S19,30-T13N-R25E
MACARTHUR CU LODE SC 5 S20-T13N-R25E
MACARTHUR CU LODE SC 50 S19,30-T13N-R25E
YERINGTON MINE LODE SC 506 S28-T13N-R25E
YERINGTON MINE LODE SC 507 S28-T13N-R25E
YERINGTON MINE LODE SC 508 S28-T13N-R25E
YERINGTON MINE LODE SC 509 S28-T13N-R25E
MACARTHUR CU LODE SC 51 S19,30-T13N-R25E
YERINGTON MINE LODE SC 510 S28-T13N-R25E
YERINGTON MINE LODE SC 511 S28-T13N-R25E
YERINGTON MINE LODE SC 512 S28-T13N-R25E
MACARTHUR CU LODE SC 52 S19-T13N-R25E
MACARTHUR CU LODE SC 53 S24-T13N-R24E; S19-T13N-R25E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE SC 54 S19-T13N-R25E
MACARTHUR CU LODE SC 55 S19-T13N-R25E
MACARTHUR CU LODE SC 56 S19-T13N-R25E
MACARTHUR CU LODE SC 57 S19-T13N-R25E
MACARTHUR CU LODE SC 58 S19-T13N-R25E
MACARTHUR CU LODE SC 59 S19-T13N-R25E
MACARTHUR CU LODE SC 6 S20,29-T13N-R25E
MACARTHUR CU LODE SC 60 S19-T13N-R25E
MACARTHUR CU LODE SC 61 S19-T13N-R25E
MACARTHUR CU LODE SC 62 S19-T13N-R25E
MACARTHUR CU LODE SC 63 S19-T13N-R25E
MACARTHUR CU LODE SC 64 S19-T13N-R25E
MACARTHUR CU LODE SC 65 S19-T13N-R25E
MACARTHUR CU LODE SC 66 S19-T13N-R25E
MACARTHUR CU LODE SC 67 S19-T13N-R25E
MACARTHUR CU LODE SC 68 S13,24-T13N-R24E; S18,19-T13N-R25E
MACARTHUR CU LODE SC 69 S13-T13N-R24E; S18-T13N-R25E
MACARTHUR CU LODE SC 7 S20-T13N-R25E
MACARTHUR CU LODE SC 70 S18,19-T13N-R25E
MACARTHUR CU LODE SC 71 S18-T13N-R25E
MACARTHUR CU LODE SC 72 S18,19-T13N-R25E
MACARTHUR CU LODE SC 73 S18-T13N-R25E
MACARTHUR CU LODE SC 74 S18,19-T13N-R25E
MACARTHUR CU LODE SC 75 S18-T13N-R25E
MACARTHUR CU LODE SC 76 S18,19-T13N-R25E
MACARTHUR CU LODE SC 77 S18-T13N-R25E
MACARTHUR CU LODE SC 78 S18,19-T13N-R25E
MACARTHUR CU LODE SC 79 S18-T13N-R25E
MACARTHUR CU LODE SC 8 S20,29-T13N-R25E
MACARTHUR CU LODE SC 80 S18,19-T13N-R25E
MACARTHUR CU LODE SC 81 S18-T13N-R25E
MACARTHUR CU LODE SC 82 S18,19-T13N-R25E
MACARTHUR CU LODE SC 83 S18-T13N-R25E
MACARTHUR CU LODE SC 84 S17,18,19,20-T13N-R25E
MACARTHUR CU LODE SC 85 S17,18-T13N-R25E
MACARTHUR CU LODE SC 86 S17,20-T13N-R25E
MACARTHUR CU LODE SC 87 S17-T13N-R25E
MACARTHUR CU LODE SC 88 S17,20-T13N-R25E
MACARTHUR CU LODE SC 89 S17-T13N-R25E
MACARTHUR CU LODE SC 9 S20-T13N-R25E
MACARTHUR CU LODE SC 90 S17,20-T13N-R25E
MACARTHUR CU LODE SC 91 S19,20-T13N-R25E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU LODE SC 92 S20-T13N-R25E
MACARTHUR CU LODE SC 93 S13-T13N-R24E; S18-T13N-R25E
MACARTHUR CU LODE SC 94 S13-T13N-R24E; S18-T13N-R25E
MACARTHUR CU LODE SC 95 S18-T13N-R25E
MACARTHUR CU LODE SC 96 S18-T13N-R25E
MACARTHUR CU LODE SC 97 S18-T13N-R25E
MACARTHUR CU LODE SC 98 S18-T13N-R25E
MACARTHUR CU LODE SC 99 S18-T13N-R25E
MACARTHUR CU LODE SC268 S13-T13N-R24E
MACARTHUR CU LODE SC269 S23-T13N-R24E
MACARTHUR CU LODE SC270 S23, 26-T13N-R24E
MACARTHUR CU LODE SC271 S23-T13N-R24E
MACARTHUR CU LODE SC272 S23, 24, 25, 26-T13N-R24E
MACARTHUR CU LODE SC273 S24, 25-T13N-R24E
MACARTHUR CU LODE SC274 S23, 24, 25-T13N-R24E
MACARTHUR CU LODE SC275 S24-T13N-R24E
MACARTHUR CU LODE SC276 S24, 25-T13N-R24E
MACARTHUR CU LODE SC277 S24-T13N-R24E
MACARTHUR CU LODE SC278 S24, 25-T13N-R24E
MACARTHUR CU LODE SC279 S24-T13N-R24E
MACARTHUR CU LODE SC280 S24, 25-T13N-R24E
MACARTHUR CU LODE SC281 S24-T13N-R24E
MACARTHUR CU LODE SC282 S24, 25-T13N-R24E
MACARTHUR CU LODE SC283 S24-T13N-R24E
MACARTHUR CU LODE SC284 S24, 25-T13N-R24E
MACARTHUR CU LODE SC285 S24-T13N-R24E
MACARTHUR CU LODE SC286 S24, 25-T13N-R24E
MACARTHUR CU LODE SC287 S24-T13N-R24E
MACARTHUR CU LODE SC288 S24, 25-T13N-R24E
MACARTHUR CU LODE SC289 S24-T13N-R24E
MACARTHUR CU LODE SC290 S24, 25-T13N-R24E
MACARTHUR CU LODE SC291 S23-T13N-R24E
MACARTHUR CU LODE SC292 S23-T13N-R24E
MACARTHUR CU LODE SC293 S23-T13N-R24E
YERINGTON MINE LODE SC-500 S17,20-T13N-R25E
YERINGTON MINE LODE SC-501 S17,20-T13N-R25E
YERINGTON MINE LODE SC502 S9, 16-T13N-R24E
YERINGTON MINE LODE SC503 S9, 16-T13N-R24E
YERINGTON MINE LODE SC504 S21-T13N-R24E
YERINGTON MINE LODE SC505 S21-T13N-R24E
YERINGTON MINE LODE SCY-1 S8-T13N-R25E
YERINGTON MINE LODE SCY-10 S20-T13N-R25E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
YERINGTON MINE LODE SCY-11 S20, 21-T13N-R25E
YERINGTON MINE LODE SCY-12 AMENDED S16-T13N-R25E
YERINGTON MINE LODE SCY-13 AMENDED S16-T13N-R25E
YERINGTON MINE LODE SCY-2 S8, 17-T13N-R25E
YERINGTON MINE LODE SCY-3 S17-T13N-R25E
YERINGTON MINE LODE SCY-4 S17-T13N-R25E
YERINGTON MINE LODE SCY-5 S17-T13N-R25E
YERINGTON MINE LODE SCY-6 S17-T13N-R25E
YERINGTON MINE LODE SCY-7 S17-T13N-R25E
YERINGTON MINE LODE SCY-8 S17, 20-T13N-R25E
YERINGTON MINE LODE SCY-9 S20-T13N-R25E
MACARTHUR CU LODE TAUBERT HILLS S24-T14N-R24E
MACARTHUR CU LODE WEST SIDE 1 S8-T13N-R24E
MACARTHUR CU LODE WEST SIDE 2 S8,9-T13N-R24E
MACARTHUR CU LODE WEST SIDE 3 S8-T13N-R24E
MACARTHUR CU LODE WEST SIDE 4 S8,9-T13N-R24E
MACARTHUR CU LODE WEST SIDE 5 S8-T13N-R24E
MACARTHUR CU LODE WEST SIDE 6 S8,9-T13N-R24E
MACARTHUR CU LODE WEST SIDE 7 S8-T13N-R24E
MACARTHUR CU LODE WEST SIDE 8 S8,9-T13N-R24E
MACARTHUR CU Lode RR-1 S1-T14N-R24E; S36-T15N-R24E
MACARTHUR CU Lode RR-2 S36-T15N-R24E
MACARTHUR CU Lode RR-3 S36-T15N-R24E
MACARTHUR CU Lode RR-4 S25,36-T15N-R24E
MACARTHUR CU Lode RR-5 S25-T15N-R24E
MACARTHUR CU Lode RR-6 S25-T15N-R24E
MACARTHUR CU Lode RR-7 S25-T15N-R24E
MACARTHUR CU Lode RR-8 S24,25-T15N-R24E
MACARTHUR CU Lode RR-9 S24-T15N-R24E
MACARTHUR CU Lode RR-10 S24-T15N-R24E
MACARTHUR CU Lode RR-11 S24-T15N-R24E
MACARTHUR CU Lode RR-12 S13,24-T15N-R24E
MACARTHUR CU Lode RR-13 S13-T15N-R24E
MACARTHUR CU Lode RR-14 S13-T15N-R24E
MACARTHUR CU Lode RR-15 S13-T15N-R24E
MACARTHUR CU Lode RR-16 S13-T15N R24E; S18-T15N R25E
MACARTHUR CU Lode RR-17 S18-T15N-R25E
MACARTHUR CU Lode RR-18 S18-T15N-R25E
MACARTHUR CU Lode RR-19 S13-T15N R24E; S18-T15N-R25E
MACARTHUR CU Lode QT 282 S20,29-T14N-R25E
MACARTHUR CU Lode QT-283 S20,29-T14N-R25E


 

Table 3.3: Lode and Placer Claims
Program Type Claim Sec-Twp-Range
MACARTHUR CU Lode QT 284 S20,29-T14N-R25E
MACARTHUR CU Lode QT 285 S18-T14N-R25E
MACARTHUR CU Lode QT 286 S18-T14N-R25E
MACARTHUR CU Lode QT 287 S19,20-T14N-R25E
MACARTHUR CU Lode QT 288 S19,20-T14N-R25E
MACARTHUR CU Lode QT 289 S17,18,19,20-T14N-R25E
MACARTHUR CU Lode QT 290 S17,18-T14N-R25E
MACARTHUR CU Lode QT 291 S17,18-T14-R25E
MACARTHUR CU Lode QT 292 S17,18-T14N-R25E
MACARTHUR CU Lode QT 293 S17,18-T14N-R25E
MACARTHUR CU Lode QT 294 S17,18-T14N-R25E
MACARTHUR CU Lode QT 295 S17,18-T14N-R25E
MACARTHUR CU Lode QT 296 S17,18-T14N-R25E
MACARTHUR CU Lode QT 297 S17,18-T14N-R25E
MACARTHUR CU Lode QT 298 S31-T14N-R25E
MACARTHUR CU Lode QT 299 S31-T14N-R25E
MACARTHUR CU Lode QT 300 S30,31-T14N-R25E
MACARTHUR CU Lode QT 301 S29,30,31,32-T14N-R25E
YERINGTON MINE Lode BR-60 S9,16-T13N-R25E
YERINGTON MINE Lode SCY-14 S17-T13N-R25E
YERINGTON MINE Lode SCY-15 S17-T13N-R25E
Total Claims: 1155 Total acreage: 23,697

Table 3.4: Optioned Private Ground (Lyon County)
Landowner Term County Parcel
Number
Acreage
Desert Pearl Farms, LLC. March 20, 2013 to 2029 014-241-24
014-241-43
014-401-20
369.00
79.36
344.26
Yerington Mining, LLC. November 12, 2013, to 2027 01-531-02 392.87
Janet C. Taylor April 4, 2013, to March 2026 014-401-07 41.29
Chisum Properties, LLC. April 4, 2013, can continue indefinitely 014-401-08
014-401-09
40.00
40.00
Circle Bar N Ranch May 25, 2015, to June 15, 2029 001-551-01
001-561-06
331.64
688.20
Total Parcels: 5 Total acreage: 2326.62

3.6 PERMIT REQUIREMENTS

Lion CG has secured all necessary permits to proceed with site exploration and design activities. These permits encompass the Exploration Plan of Operations issued by the BLM and reclamation and temporary discharge permits issued by the State of Nevada. A comprehensive list of these permits is provided in Table 3.5.


 

Table 3.5: Existing Project Permits
Permit Name Permit Identifier
(if applicable)
Issuing Agency
Yerington Exploration Reclamation Permit #0321 NDEP-BMRR
MacArthur Exploration Reclamation Permit #0294 NDEP-BMRR
MacArthur Exploration Plan of Operations NVN-085212 U.S. BLM
Yerington Class II Air Quality Operating Permit AP1629-4669 NDEP-BAPC
MacArthur Class II Air Quality Operating Permit AP1629-4668 NDEP-BAPC
Yerington Temporary Authorization to Explore TNEV2024106 NDEP-BMRR
Yerington Stormwater Construction General Permit CSW-54058 NDEP-BWPC
MacArthur Stormwater Construction General Permit CSW-54053 NDEP-BWPC

3.7 SIGNIFICANT FACTORS AND RISKS THAT MAY AFFECT ACCESS, TITLE OR WORK PROGRAMS

Lion CG must comply with several conditions outlined in the above listed permits and provide reports to issuing agencies. Specific permit conditions, including monitoring and reporting requirements, are outlined in and specific to each permit. All required permits are current as of Report date. There are no other significant factors and risks known to Samuel Engineering, AGP or Newfields that may affect access, title, or the right or ability to perform work on the property that are not discussed in this Report.

3.8 PERMITTING

Permitting requirements and regulations are included in Section 17.


 

4.0 ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE, AND PHYSIOGRAPHY

4.1 ACCESSIBILITY

The Project is located adjacent to the town of Yerington, Nevada. The town is located about a 1.5-hour drive southeast of Reno (about 70 miles driving distance) via US Interstate I-80E and US-Highway 95 ALT.

Access to the Project from the town of Yerington follows US Highway ALT 95 north about one mile to the Burch Street turnoff, a paved road that leads west into the Property. Access into the mine area is fenced and restricted. Inside the fenced area a series of roads provide access to all the Project in Township 13 North, Range 25 East. Claims in Township 13 North, Range 24 East are accessed by several existing dirt roads leading west from US Highway ALT 95, from one to three miles south of the town of Yerington.

The Yerington Municipal Airport is a mile north of Yerington, in Lyon County, Nevada. Yerington Municipal Airport is a small airport, serving the town and surrounding areas. The airport is situated at the intersection of US-Highway ALT 95 and Nevada State Route 208. It provides facilities for Private and General Aviation operations. The airport offers basic services such as fueling, hangar rentals, and tie-down spaces for aircraft.

A cross-country railroad owned by Union Pacific Railroad is located about 12 miles north of Yerington. There is a rail load out station located along this line at Wabuska, also approximately 12 miles north of Yerington.

4.2 CLIMATE AND LENGTH OF OPERATING SEASON

The climate is temperate and is characterized by cool winters with temperatures between zero- and 50-degrees Fahrenheit and warm to hot summers with temperatures between 50- and 100-degrees Fahrenheit. Average annual precipitation is estimated at three to eight inches per year, with a significant part of this total precipitation falling as snow and increasing with elevation.

Work can be conducted throughout the year with only minor delays during winter months due to heavy snowfall or unsafe travel conditions when roads are particularly muddy. Future mining activities are expected to be conducted year-round.

There are no active streams or springs on the remainder of the Lion CG property. The terrain is moderately steep and sparsely covered by sagebrush and interspersed low profile desert shrubs. All gulches that traverse the Property are normally dry.

4.3 LOCAL RESOURCES AND INFRASTRUCTURE

The nearest population center is the agricultural community of Yerington, one mile east of the Yerington pit. Formerly an active mining center from 1953 to 1978 and from 1989 to 1997, Yerington now serves as a base for three active exploration groups: Lion CG; Hudbay Minerals Inc. (Mason Project copper-molybdenum property); and Southwest Critical Materials, LLC. (Pumpkin Hollow Copper Project). Yerington hosts a work force active in, qualified for, and familiar with mining operations within a one-hour drive of the Project area.


 

Yerington offers most necessities and amenities including police, hospital, groceries, fuel, regional airport, hardware, and other necessary infrastructure. Drilling supplies and assay laboratories can be found in Reno, a 1.5-hour drive. Reverse circulation drilling contractors are found in Silver Springs, Nevada, 33 miles north, as well as in the Winnemucca and Elko Nevada areas, within a three- to five-hour drive from the site.

4.3.1 Electrical Power

Power is available at the Project. NV Energy operates a 226 MW natural gas fueled power plant within ten miles of the Project site. The power infrastructure at the Project is expected to be readily available for a future mining operations.

4.3.2 Rail Spur

A cross-country railroad owned by Union Pacific Railroad is located about 12 miles north of Yerington. There is a rail load out station located along this line at Wabuska, also approximately 12 miles north of Yerington. Historical access by train to the Yerington Mine site has been removed but a tie-in point is available 3 miles west of the current load out station at Wabuska. A 12-mile-long rail spur alignment is planned to be established as part of the project for the supply of materials for processing and transport of final copper cathode.


 

5.0 HISTORY

5.1 PROPERTY HISTORY

Recorded production in the Yerington mining district dates back to 1883 (Moore, 1969) as prospectors were attracted to and investigated colorful oxidized copper staining throughout the Singatse Range. Knopf (1918) reported that oxidized copper cropped out at the historic Nevada-Empire mine located above the south center of the present-day Yerington open pit. Knopf does not show or reference other mines or prospects underlain by the Yerington open pit footprint, as gravel and alluvial cover obscure bedrock over an approximate 0.75-mile radius around the Nevada-Empire Mine.

Information is sparse for the period from Knopf's reporting in 1918 until World War II, although it is likely that mineral leases were worked in the Nevada-Empire during spikes in the copper price. Private reports (Hart, 1915, and Sales, 1915) describe ore shipments and planned underground exploration from a northwest striking, southwest dipping structure at the historic Montana-Yerington Mine area located approximately one mile west of the present-day Yerington pit.

During the 1940s, Anaconda outlined a deposit in the current Yerington pit. During the early 1950s, the US government, citing the need for domestic copper production, offered "start-up" subsidies to Anaconda to open a copper mine in the Yerington district. Anaconda sank two approximately 400-foot-deep shafts in the present-day Yerington open pit area and drove crosscuts to obtain bulk samples of oxidized rock for metallurgical study. Anaconda began operating the Yerington Mine in 1952 and mined continually through 1979, producing approximately 1.744 billion pounds of copper from 162 million tons averaging 0.54% Cu. Approximately 104 million tons of this total was from oxidized copper mineralization that was "vat leached" with sulfuric acid in 13,000-ton cement vats on a seven-day leach cycle. Sulfide mineralization was concentrated on site in a facility that was dismantled and sold following termination of mining in 1979. The cement copper and sulfide concentrates were shipped to the Anaconda's smelter in Montana.

In 1976, all assets of Anaconda, including the Yerington Mine, were purchased by ARC, which shut down dewatering pumps in the pit and closed the Yerington Mine in 1979 due to low copper prices. 

The Yerington Mine site and adjacent Weed Heights mining camp were acquired by CopperTek, a private Yerington company owned by Mr. Don Tibbals, in 1982. In the mid-1980's CopperTek began reprocessing W-3 waste rock and VLT on HLPs and a SX/EW plant to produce cathode copper. In 1989, Arimetco purchased the mine property from CopperTek, commissioned a 50,000-pound-per-day SXEW plant, and began heap leaching mineralized material at the Yerington site. Arimetco processed W-3 waste rock and VLTs on newly constructed HLPs as well as trucking oxide ore from the MacArthur Mine, located approximately five miles north of the Yerington Mine site. Arimetco produced some 95 million pounds of copper (Table 5.1) from 1989 to 1999 before declaring bankruptcy in 1997 due to low copper prices (Sawyer, 2011). Arimetco terminated mining operations in 1997 and abandoned the property in early 2000.


 

Table 5.1: Yerington Mine Production
Year Total Tons Mined Grade Pounds Contained Copper Total Pounds Copper Sold
1989 233,037 0.39 1,795,025 375,260
1990 1,489,452 0.24 7,181,516 2,659,738
1991 2,915,234 0.18 10,494,842 3,817,612
1992 4,405,469 0.18 16,112,430 9,190,619
1993 7,613,820 0.15 22,303,920 10,522,515
1994 7,617,264 0.21 32,706,247 14,301,007
1995 9,399,061 0.17 32,559,773 14,286,796
1996 5,000,906 0.26 25,788,439 14,838,074
1997 2,941,166 0.23 13,725,306 10,030,256
1998 9,360,826 0.11 20,182,155 12,379,969
1999 0 0.00 0 3,008,989

5.1.1 Yerington Site Remediation History

ARC, as successor in interest to the Anaconda Mining Company, is responsible for remediation of the Yerington Site under NDEP and EPA administrative orders that have been in place since the early 1980s. After ARC shut down mining operations, they continued to maintain the site under the jurisdiction of NDEP. EPA took over jurisdiction of the site under CERCLA in 2004, during which numerous remedial efforts took place to investigate ground water contamination, demolish mine infrastructure and manage drain down fluids from the Arimetco HLPs. ARC continued remedial activities under EPA Administrative Orders until 2018. At that time, the site was proposed for Superfund listing to fund remediation of the former Arimetco HLPs and associated mining infrastructure (OU-8, the orphan share which was previously operated by Arimetco). The listing proposal was withdrawn in 2018 and the site went back under jurisdiction of NDEP under the NPL Deferral Agreement, with ARC agreeing to remediate the entire site, including OU-8, under an Interim Administrative Order on Consent (IAOC),

The Site is divided into 8 Operable Units (OUs) and 10 Construction Management Units (CMUs). The OUs delineate the Site into areas according to legacy mining operations of Anaconda and Arimetco. The CMUs are logical groupings of the OUs to facilitate efficient remedial construction at the site. The regulatory, legal and technical requirements for remediation of the OUs and CMUs will be defined in three (3) Records of Decision (RODs). Remedial work is ongoing by ARC following a CERCLA-equivalent process under the Interim Administrative Order on Consent (IAOC) between NDEP and ARC. Remediation of the site is scheduled for completion in 2029.

5.1.2 MacArthur

The most recent mining at MacArthur occurred between 1995 and 1997, when Arimetco mined a limited tonnage of surface oxide copper for heap leaching at the Yerington Mine Site. The historic metallurgical test work performed on material from the MacArthur deposit is dated and focused on leach performance of material typical of what was historically mined from the MacArthur pit. Bateman and Mountain States have all performed various metallurgical test work for the MacArthur deposit.


 

5.1.3 SPS Ownership of the Yerington Property

Lion Copper was incorporated in British Columbia, Canada, on May 11, 1993, and its common shares are listed on the Canadian Securities Exchange ("CSE") under the symbol "LEO" and quoted for trading on the OTCQB Market under the symbol "LCGMF". The Company's Yerington Copper Project is located in Lyon County Nevada, which Lion CG holds through its wholly owned U.S. subsidiary, Singatse Peak Services LLC ("SPS"). Lion CG currently holds 100% interest in the Yerington Copper Project.

SPS acquired the Yerington Property from the Arimetco Bankruptcy Court in 2011. The acquisition included the private land, mineral rights, and water rights at the Yerington Property. During this period, SPS also acquired all the unpatented mining claims at the site from a 3rd Party.

Nuton Option Agreement

On March 18, 2022, Lion CG entered an option to earn-in agreement with Rio Tinto America Inc. ("Rio Tinto"), subsequently assigned to Nuton LLC (Nuton LLC), a Rio Tinto Venture to advance studies and exploration at the Company's copper projects in Mason Valley, Nevada. On April 27, 2022, the TSX Venture Exchange approved the Company's option agreement with Rio Tinto.

The Nuton agreement outlines a 3-stage investment to earn a 65% interest in the Yerington projects. The option agreement and subsequent modifications are summarized in the following Figure.

  • Stage 1: In June 2022, Nuton LLC provided $4,000,000 to the Lion to prepare a Scoping level evaluation of its Mason Valley Projects. Lion CG completed Stage 2a in January 2024
  • Stage 2: In January 2023, Nuton LLC provided $7,500,000 to Lion CG to prepare a Preliminary Economic Assessment (PEA) of the Yerington Copper Project and to perform exploration drilling at the Bear Deposit.

o In October 2023, an amendment was signed that separated Stage 2 into Stage 2a and Stage 2b. In January 2024, Nuton provided $11,500,000 for Stage2b to prepare a Prefeasibility Study (PFS) and perform additional exploration drilling at the Bear Deposit.

o Stage 2 was further modified to include Stage 2c in November 2024 whereby Nuton provided an additional $5,000,000 to complete the PFS. The PFS was completed in September 2025.

  • Stage 3: Nuton made a decision in Q4 2025 to invest in Stage 3 to progress completion of a Feasibility Study.

 

5.2 HISTORICAL RESOURCES

The Mineral Resource estimates for the Yerington Copper Project (effective date of March 17, 2025), MacArthur Copper Project (effective date of March 17, 2025) and VLT Project (effective date of March 17, 2025) discussed herein (11.0) supersedes historical and past Mineral Resource estimates presented within this section. The following historical information is relevant to provide context but is not current and should not be relied upon. The QPs responsible for the preparation of this Technical Report have not done sufficient work to classify the historical estimate as current Mineral Resources or Mineral Reserves, and Lion CG is not treating any historical estimates as Mineral Resource or Reserve estimates.

Yerington Copper Project

Historical mineral resource estimates were conducted by Tetra Tech in 2012 and 2014. The most recent mineral resource estimate, prior to the one reported within this technical report, was conducted by AGP in 2023.

Table 5.2: Yerington Copper Project Mineral Resource Statement
Material Cut-off Grade
(TCu%)
Tons TCu% TCu lbs
Measured Oxide 0.038 20,230,000 0.25 99,367,000
Measured Sulfide 0.126 42,671,000 0.32 274,578,000
Measured Total   62,901,000 0.30 373,945,000
Indicated Oxide 0.038 13,749,000 0.22 60,166,000
Indicated Sulfide 0.126 80,960,000 0.28 457,921,000
Indicated Total   94,709,000 0.27 518,087,000
Measured+Indicated Oxide 0.038 33,979,000 0.23 159,533,000
Measured+Indicated Sulfide 0.126 123,631,000 0.30 732,499,000
Measured+Indicated Total   157,610,000 0.28 892,032,000
Inferred Oxide 0.038 33,347,000 0.18 122,221,000
Inferred Sulfide 0.126 79,881,000 0.24 385,938,000
Inferred Total   113,229,000 0.22 508,159,000

Notes: Effective date for this Mineral Resource estimate was May 1, 2023.

The 2023 Mineral Resource estimate uses a variable break-even economic cut-off grade of 0.038 % TCu and 0.126% TCu based on assumptions of a net copper price of US$4.08 per pound (after smelting, refining, transportation and royalty charges), 70% recovery in oxide material, 75% recovery in sulfide material.

Mineral Resources are not Mineral Reserves and do not demonstrate economic viability.

Mineral Resource estimate reported from within resource pit shell.

There is no certainty that all or any part of the Mineral Resource estimate will be converted into Mineral Reserves.

All figures are rounded to reflect the relative accuracy of the estimates and totals may not add correctly.

MacArthur Copper Project

Two historic resource models were completed for the MacArthur deposit, one in 2009 and a second in 2014 (IMC, 2022). The most recent mineral resource estimate, prior to the one reported within this technical report, was conducted by IMC in 2022.


 

Table 5.3: MacArthur Project - Summary of Mineral Resource
Classification Ktons Total Cu, % Contained Cu
Pounds x 1000
Measured 116,666 0.180 420,929
Indicated 183,665 0.158 579,479
Sum Measured+Indicated 300,331 0.167 1,000,408
Inferred 156,450 0.151 471,714

Cutoff grade: 0.06% TCu for Leach Cap, Oxide & Transition; cutoff grade for Sulfide: 0.06% for MacArthur & North Ridge, 0.08% for Gallagher. Total resource shell tonnage = 628,831 ktons

Note: The effective date of the MacArthur Mineral Resource estimate was February 25, 2022.

VLT Project

AGP conducted the most recent mineral resource estimate, prior to the one reported within this technical report, in 2023. No compliant mineral resource estimates were reported before the 2023 mineral resource.

Table 5.4: VLT Mineral Resource Statement
Class Cut-off Grade
(TCu%)
Tons TCu% TCu lbs
Inferred >= 0.04 33,160,000 0.09 62,622,000

Notes: Mineral resources reported for the VLT were for surficial deposits and not in situ. The effective date for this VLT Mineral Resource estimate was July 31, 2023

The 2023 Mineral Resource estimate uses a variable break-even economic cut-off grade of 0.040 % TCu based on assumptions of a net copper price of US$4.08 per pound (after smelting, refining, transportation, and royalty charges), and 70% recovery in oxide material.

Mineral Resources are not Mineral Reserves and do not demonstrate economic viability.

Mineral Resource estimate reported from within the resource pit shell.

There is no certainty that all or any part of the Mineral Resource estimate will be converted into Mineral Reserves.

All figures are rounded to reflect the relative accuracy of the estimates, and totals may not add correctly.


 

6.0 GEOLOGICAL SETTING, MINERALIZATION, AND DEPOSIT

6.1 REGIONAL GEOLOGY

The Project is located in western Nevada near the western boundary of the Basin and Range Province, a land mass of internal drainage encompassing most of the state of Nevada. Basin and Range physiography consists of a series of nearly north-trending ranges separated by alluvial-filled, normal fault-bounded basins. The valley infill may range from tens to thousands of ft of alluvium.

In western Nevada, overprinted on the Basin and Range but not altering its physiographic character, is a major right lateral, northwest trending structural zone called the "Walker Lane" approximately 60 miles wide and generally parallel to the Nevada-California border, between Reno to the northwest and Las Vegas to the southeast (Figure 6.1). Major deposits, principally precious metals, occur in the Walker Lane as does the Yerington copper mining district.

Source: Modified Wesnousky 2005

Figure 6.1: Structural Geology Map of Western United States

Within Lyon County in the state of Nevada, the Project a\rea occupies the alluvial-covered eastern flank and bedrock uplands of the central Singatse Range, a modest sized, north trending mountain range.


 

Regional geology of the Singatse Range, including the Yerington mining district is displayed in Figure 6.2 (Proffett and Dilles, 1984) from which the following text has been adapted.

The oldest rocks of the Singatse Range are an approximate 4,000-foot section of Late Triassic, intermediate and felsic metavolcanics, and sedimentary rocks forming the McConnell Canyon Formation, associated with volcanic arc development along the North American Continent during the Mesozoic Period.

This sequence is disconformably overlain by a series of Upper Triassic carbonates, meta-sediments, and volcaniclastics that are, in turn, overlain by Upper Triassic limestone, siltstone, and tuffs, and by argillite thought to span the Triassic-Jurassic boundary. Jurassic limestone is succeeded by gypsum and sandstone, and by andesitic volcanics that may signal the beginning pulse of middle Jurassic plutonism.

Middle Jurassic plutonism, possibly related to the igneous activity that formed the Sierra Nevada Mountains to the west, resulted in emplacement of two batholiths comprising the Singatse Range, including the Yerington batholith extending across 40 miles from the Wassuk Range on the east to the Pine Nut Range on the west. East-west striking structural zones mark the contacts between igneous rock and older, outlying Mesozoic basement at the north and south ends of the Singatse Range; the structures can be projected through the adjoining basins.

The Yerington batholith comprises three intrusive phases emplaced between 169 Ma to 168 Ma (Figure 6.2), Proffett and Dilles, 1984): an early granodiorite pluton (McLeod Hill quartz monzodiorite); a second phase of medium-grained quartz monzonite (Bear quartz monzonite), creating a finer-grained ''border phase quartz monzonite" where in contact with granodiorite; and, finally, a medium-grained porphyritic quartz monzonite emplaced as a stock with cupolas developed over its top. Porphyry dike swarms sourced from the youngest phase, the porphyritic quartz monzonite, cut the cupolas. Copper mineralization formed contemporaneously with the dike swarms. Andesite and rhyolite dikes represent the final phase of Mesozoic igneous activity.

Mesozoic rocks were deeply eroded and then covered by Mid-Tertiary tuffs and lesser sedimentary rocks. The entire package was subsequently faulted along north-trending, downward and east dipping faults that resulted in extension and major westerly tilting.

The stratigraphic column for the Yerington District (Proffett and Dilles, 1984) is shown in Table 6.1.


 

 
Source: Modified Proffett and Dilles 1984
Notes: Property outlined in black.

Figure 6.2: Regional Geology Map with Cross-Section Intersecting Yerington Mine


 

Table 6.1: Yerington District Geology Stratigraphic Column
Era Period Rock Type
Cenozoic Quaternary Qal, Qls
    UNCONFORMITY
    Tba
    LOCAL UNCONFORMITY
    Ta, Tws, Twt
    UNCONFORMITY
    Tha, Thai
    Tb
    Td
    Tbs
    Tbm
    Ts
    Tsl
    Trt
    Twh
    Tru
    Tgm
    MINOR UNCONFORMITY
    Tei
    Teb
    Tcg
    MAJOR UNCONFORMITY
Mesozoic   Ja
    Jr
  Jurassic  Jqp
    Jsa
    Jqms
    Jgdp
    Jqmp
    Jpg
    Jpqm
    Jqm, Jbqm
    Jgd
    Jgb
    Jaf
    Jq
    Jgy
    Jl
    JTRcl
    JTRvc
  Triassic TRlb
    TRl


 

Table 6.1: Yerington District Geology Stratigraphic Column
Era Period Rock Type
    TRad
    TRvl
    TRla
    TRll
    DISCONFORMITY
    TRr, TRv
    TRa, TRv
    Mzqp
    Mzap
    Mzqm
    Mzdi

Source: Modified Proffett and Dilles, 1984

6.2 LOCAL GEOLOGY

The Project includes the Yerington Copper Deposit, MacArthur Copper Deposit and a portion of the Bear Property which represents three of four known porphyry copper deposits in the Yerington district. All of these deposits lie in Middle Jurassic intrusive rocks of the Yerington batholith.

Copper mineralization occurs in all three phases of the Yerington batholith. Intrusive phases, from oldest to youngest, are known as the McLeod Hill quartz monzodiorite (field name granodiorite), the Bear quartz monzonite, and the Luhr Hill granite, the source of quartz monzonitic (i.e. granite) porphyry dikes related to copper mineralization.

Following uplift and erosion, a thick Tertiary volcanic section was deposited, circa 18-17 Ma. This entire rock package was then extended along northerly striking, down-to-the-east normal faults that flatten at depth, creating an estimated 2.5 miles of west to east dilation-displacement (Proffett and Dilles, 1984). The extension rotated the section such that the near vertically emplaced batholiths were tilted 60° to 90° westerly. Pre-tilt, flat-lying Tertiary volcanics now crop out as steeply west dipping units in the Singatse Range west of the Project. The easterly extension thus created a present-day surface such that a plan map view represents a cross-section of the geology.

6.3 PROPERTY GEOLOGY

6.3.1 Yerington

Current knowledge of Yerington deposit geology benefits from detailed geologic mapping by Anaconda geologists on various pit benches during mining operations from the 1950s to the 1970s. Lion CG gained access to this data through membership in the Anaconda Collection - American Heritage Center housed on the campus of the University of Wyoming, Laramie, Wyoming. Further, of the approximately 840 exploration core holes drilled by Anaconda to define the Yerington deposit, one-half splits of approximately 20 percent of the core were stored in a recoverable manner on the mine site. Lion CG moved the core to a dry location for relogging and reassay to understand the geology as it relates to copper mineralization.


 

The three intrusive phases of the middle Jurassic Yerington batholith, exposed in the Yerington pit, have been intruded by at least six north dipping porphyry dikes originating from the youngest batholithic phase, the Luhr Hill Granite, also referred to as the Porphyritic quartz monzonite (PQM). Anaconda geologists identified petrographically similar porphyry dikes by number, e.g. QMP1, QMP1.5, QMP2, QMP2.5, QMP2.7, QMP3, with the lowest numbers representing the earliest and strongest copper mineralized dike activity. Younger unmineralized Jurassic rhyolite and andesite dikes followed, occurring with variable structural orientations. Cross-cutting relationships in pit walls allowed Anaconda geologists to determine age relationships of the dikes. A determination from core is more difficult. The oldest dikes are the best mineralized, especially QMP1 which averaged 0.80% to 2.0% TCu (J. Proffett, 2010, personal communication).

6.3.2 MacArthur

The MacArthur deposit is underlain by the rocks described in the Yerington batholith, including the granodiorite (McLeod Hill quartz monzodiorite) intruded by quartz monzonite, (Bear quartz monzonite) both of which are intruded by Middle Jurassic quartz porphyry hornblende and quartz porphyry biotite (hornblende) dikes. Presumably the dikes are derived from the Luhr Hill Granite described above, but this unit has not yet been identified at MacArthur. The north dipping porphyry dike swarms follow penetrative west-northwest and east-west structural fabrics. Age relationships of the dikes have not been fully determined, however, the quartz porphyry biotite dikes are older than the quartz porphyry hornblende dikes. Narrow (<10 ft) fine grained andesite and rhyolite dikes, post porphyry diking, also occur with variable structural orientations.

6.4 PROPERTY ALTERATION

Alteration types recognized in drill core and on surface at the Project are common to those found in many mineralized porphyry copper systems. Mid-Tertiary downward and eastward extensional faulting exposes a porphyry copper deposit in cross section lying on its side with its top toward the west. Limonite brownish sericite alteration (the pre-tilt upper, original pyrite-rich phyllic shell) is exposed at the west end of the Yerington pit and is exposed on surface at MacArthur. Potassically altered secondary biotite dominant alteration occurs in the center of the Yerington and MacArthur pits, which grades easterly into off-white sodic rich alteration that represents the pre-tilt base of the deposits. Tertiary volcanics occur to the west of both deposits.

6.4.1 Propylitic

Propylitic alteration is common throughout the Project in all rock types. This alteration type occurs as chlorite replacing hornblende, and especially epidotization as veining, coatings, and/or flooding on the granodiorite. Calcite veining is present but not commonly observed in core or drill cuttings. Feldspars are commonly unaltered. Propylitic alteration frequently overprints or occurs with the alteration types described in the following sub-sections. Pyrite and magnetite are common accessory minerals.

6.4.2 Phyllic/Quartz-Sericite-Pyrite (QSP)

Phyllic alteration is most frequently characterized by tan to light green sericite partially or completely replacing hornblende and/or biotite sites. When phyllic alteration becomes more intense, plagioclase and/or K-feldspar sites are also replaced by sericite. The altered mafics and feldspars are accompanied by a significant addition of pyrite, locally up to 10%. However, these minerals do not replace mafic or felsic sites. Sericitic altered zones are often quite siliceous; however, it is unclear if this is due to quartz addition or just the destruction of other primary minerals.


 

Phyllic alteration is most pervasive and intense in the west-central to west portion of the Yerington pit and western portion of MacArthur. The alteration type does not show preference with rock type and has been described in the granodiorite, quartz monzonite, and the porphyries.

6.4.3 Potassic Alteration

Potassic alteration occurs as shreddy, fine-grained biotite replacing hornblende. To a lesser extent, there is potassium feldspar replacing plagioclase within the rock as well as in vein halos. Potassic alteration occurs in the central part of the Yerington and MacArthur pits and typically coincides with the highest-grade copper mineralization. Quartz veining is most extensive in this alteration phase.

Potassic alteration is best observed in oldest (highest grade) porphyry dikes as well as the granodiorite and quartz monzonite hosts.

6.4.4 Sodic-Calcic Alteration

Pervasive sodic-calcic alteration, described by Anaconda geologists as sodic flooding, occurs at the east end (pre-tilt base) of the Yerington and MacArthur pits, creating off-white, hard altered rock. This type of alteration most frequently occurs as albite replacing K-feldspar and as chlorite, epidote, or actinolite replacing hornblende and/or biotite. In the most intense zones of sodic alteration, the mafics are completely destroyed.

6.4.5 Silicification

Silicification occurs as a wholesale replacement of the rock, occurring in an irregular nature.

6.4.6 Supergene

Supergene, or secondary enriched copper minerals, made only a minor contribution to Yerington Mine production due to insufficient pyrite available for oxidation and creation of sulfuric acid. Chalcocite, the primary result of secondary enrichment, occurs randomly toward the west end (pre-tilt top) of the Yerington pit. At the Gallagher area and north of the MacArthur pit, supergene alteration has formed leached capping which is underlain by chalcocite mineralization. Lion CG's drill holes collared on the west-northwest side of the pit intersected narrow, isolated chalcocite mineralization. The transition from oxide (green and / or black) copper to primary sulfide copper mineralization is sharp and consistently chalcocite-absent throughout the pit excepting the west pit area.

The oxide - sulfide surface across the Yerington pit generally occupies the 4,100-foot elevation as a rather smooth, undulating surface with local "divots" down to 3900 ft in places, ostensibly where oxidation followed fracturing downward. Base of oxidation in limited Lion CG drilling confirmed the general 4,100-foot elevation.


 

6.5 MINERALIZATION

6.5.1 Yerington Copper Deposit

The general geometry of copper mineralization below the Yerington pit is an elongate body extending 6,600 ft along a strike of S62ºE. The modeled mineralization has an average width of 2,000 ft and has been defined by drilling to an average depth of 400-500 ft below the pit bottom at the 3,500-foot elevation.

The copper mineralization and alteration throughout the Yerington district and at the Yerington deposit are unusual for porphyry copper camps in that the mineralization is "stripey", occurring in WNW striking bands or stripes between materials of lesser grade. Clearly, much of this geometry is influenced by the strong, district-wide WNW structural grain observed in fault, fracture and, especially, porphyry dike orientations. Porphyry dikes are associated with all copper occurrences in the district. Altered, mineralized bands range in width from tens of ft to 200-foot-wide mineralized porphyry dikes mined in the Yerington pit by Anaconda.

Greenish, greenish blue chrysocolla (CuSiO3.2H20) was the dominant copper oxide mineral, occurring as fracture coatings and fillings, easily amenable to an acid leach solution. Historic Anaconda drill logs note lesser neotocite, aka black copper wad (Cu, Fe, Mn)SiO2 and rare tenorite (CuO) and cuprite (Cu2O). Oxide copper also occurs in iron oxide/limonite fracture coatings and selvages.

Chalcopyrite (CuFeS2) was the dominant copper sulfide mineral occurring with minor bornite (Cu5FeS4) primarily hosted in A-type quartz veins in the older porphyry dikes and in quartz monzonite and granodiorite, as well as disseminated between veins in host rock at lesser grade. The unmined mineralized material below the current pit bottom consists primarily of chalcopyrite.

Surfaces were interpreted for alluvium (code 20), oxide (code 30) mineralization and sulfide (code 40) mineralization from the drill logs and soluble copper assays. Figure 6.3 compares the surfaces with the coding from drill holes and the block model.


 

Source: AGP 2023
Note: Brown=Alluvium (20), Green=Oxide (30), Red=Sulfide (40)

Figure 6.3: Yerington Geology Section 2451250 E (Looking West)

6.5.2 MacArthur Copper Deposit

The MacArthur deposit is a large copper mineralized system containing near-surface acid soluble copper mineralization (IMC, 2022).

The MacArthur deposit consists of a 50 to 150-ft thick, tabular zone of secondary copper (oxides and/or chalcocite) covering an area of approximately two square miles (Figure 6.4). Limited drilling has also intersected underlying primary copper mineralization open to the north, but only partially tested to the west and east.


 

Source: IMC 2022

Figure 6.4: MacArthur Property Geology East-West Cross Section

Oxide copper mineralization is most abundant and particularly well exposed in the walls of the legacy MacArthur pit. The most common copper mineral is chrysocolla (CuSiO32H2O). Also present is black copper wad, neotocite, ((Cu,Fe,Mn)SiO2)) and trace cuprite (Cu2O) and tenorite. (CuO) The flat-lying zones of oxide copper mirror topography, exhibit strong fracture control and range in thickness from 50 to 100 ft. Secondary chalcocite mineralization forms a blanket up to 50 ft or more in thickness that is mixed with and underlies the oxide copper. Primary chalcopyrite mineralization has been intersected in several locations mixed with and below the chalcocite. The extent of the primary copper is unknown as many of the holes bottomed at 400 ft or less.

6.6 DEPOSIT TYPES

Porphyry copper systems host some of the most widely distributed mineralization types at convergent plate boundaries, including porphyry deposits centered on intrusions; skarn, carbonate-replacement, and sediment-hosted Au deposits in increasingly peripheral locations; and adjacent to high- and intermediate-sulfidation epithermal deposits. The systems commonly define linear belts, some many hundreds of kilometers long. The systems are closely related to underlying composite plutons, at paleodepths of 5 to 15 km, which represent the supply chambers for the magmas and fluids that formed the vertically elongate (>3 km) stocks or dike swarms and associated mineralization (Sillitoe, 2010).

The alteration and mineralization in porphyry copper systems are zoned outward from the stocks or dike swarms, which typically comprise several generations of intermediate to felsic porphyry intrusions. At the regional and district scales, the occurrence of many deposits in belts within which clusters and alignments are prominent. At the deposit scale, particularly in the porphyry copper environment, early formed features commonly, but by no means always, give rise to higher grade deposits. Late-stage alteration overprints may cause partial depletion or complete removal of copper and gold, but metal concentration may also result.


 

The Yerington deposit represents a porphyry copper deposit hosted in porphyry dikes that formed in stocks of the upper Yerington batholith. The Yerington porphyry system has been tilted westerly so that the plan view of the deposit is a cross-sectional exposure.

Mining at the Yerington deposit has revealed an alteration geometry displaying the original pyrite-rich cap (present-day leached sericite-limonite on the west end of the Yerington pit) grading downward easterly to quartz-sericite-pyrite alteration and to potassic alteration in the central portion of the pit and then continuing to a soda-flooded root zone at the eastern end.

The MacArthur deposit is a supergene enriched, oxidized porphyry copper system. Within the MacArthur deposit, phyllic alteration from the upper portion of the porphyry system dominates to the west. The alteration grades to potassic in the central MacArthur pit area and pervasive sodic-calcic alteration dominates in the eastern portions of the MacArthur pit and in the far eastern portion of the property.


 

7.0 EXPLORATION

7.1 EXPLORATION HISTORY

During the 1952 to 1979 period of mine operation at the Yerington Mine, Anaconda completed a number of geophysical surveys, including an aeromagnetic survey, a ground magnetic survey, and multiple IP surveys. Published gravity data were examined to estimate alluvial thicknesses in Mason Valley east of the Project. These surveys covered much more additional ground than current Project area.

7.2 GEOPHYSICS

7.2.1 Helicopter Magnetometer Survey

2007 Survey

In late 2007 and early 2008, Quaterra contracted a helicopter magnetometer survey to be conducted over the Yerington district (EDCON-PRJ, 2008). The survey was flown with a line spacing of 100 m separation with some areas in-filled to 50 m separation. In addition, two helicopter surveys flown under contract to Anaconda were also digitized from contour maps and then merged with the larger district-wide survey. The objective of the survey was to create a magnetic data set for the entire district with significantly greater resolution than previous work by Anaconda. The survey began and was completed in December 2007, and the data was delivered in the first quarter of 2008. A total of 2,685-line miles of new aeromagnetic data were acquired and 4,732-line miles of older data were digitized. This improved data set has been used extensively by Lion CG throughout the district to identify new targets as well as refine targets previously identified by Anaconda.

2012 Survey

A more detailed helicopter magnetic survey was flown by Geosolutions Party Ltd., in April of 2012, north and northwest of the MacArthur pit area.  By design this system had a broader frequency bandwidth then previous systems and was ideal for modeling purposes. The line spacing was 50 meters and a terrain clearance of approximately 30 meters was flown. The near surface volcanic response is mapped and a weak, possible alteration low, was identified from the processed data. Subsequently this low was interpreted as a deep intrusive (Weis, 2012).

Interpretation

Modeling by Thomas Weis and Associates Inc. (Weis, 2012) of the detailed helicopter magnetic data set (2012, Geosolutions) merged with the 2007 EDCON survey identified two 'interpreted' intrusive centers at depth beneath post mineral volcanic cover. Each has a central magnetic low response with a magnetic high response occurring in a circular ring around the low. The relative low is interpreted to be a potential intrusive. Interpreted depth to the top of these intrusive systems is in excess of 500 meters.

IP/resistivity surveys run by Kennecott in the 1960's and Zonge in 2009 and 2011 show an IP high, interpreted to be a potential mineralized sulfide system running under volcanic cover to the northwest of the MacArthur pit. This would extend the sulfide system into the area of the NW-Target covered by the 2012 helicopter magnetic survey (Figure 7.1).


 

Follow up work by Weis in 2013 identified an additional three magnetic targets at depth beneath magnetic volcanic cover in the MacArthur area. The anomalies have a different strike than the overlying volcanic cover and are interpreted to be potential skarn targets in the Triassic sediments or primary mineralization associated with quartz monzonite porphyry intrusive dike systems (Figure 7.2).

Source: Weis 2012
Notes: Solid ellipses=Intrusives; Dashed ellipses=Skarn bodies

Figure 7.1: MacArthur 3-D Fastmag Model Target Map


 

Source: Weis 2013
Note: Targets outlined by solid black lines.

Figure 7.2: Calculated Total Horizontal Gradient (THG) of the Susceptibility Model


 

7.2.2 Ground Geophysical Surveys

2009 Surveys

Zonge Geosciences Inc. performed IP and Resistivity and Ground Magnetic surveys for Lion CG on the MacArthur Project, located in Lyon County, Nevada. The IP/Resistivity survey was conducted in 2009 from October to December. The Ground Magnetic survey was conducted during the period of 4-7 November 2009 (Zonge, 2009b).

Dipole-dipole IP/Resistivity data were acquired on three lines using a dipole length of 200 meters and 300 meters. Pole-dipole IP/Resistivity data were acquired on four lines using a dipole length of 150 meters and 200 meters. Line locations were established by Quaterra and Zonge personnel using handheld Garmin GPS receivers with real time differential corrections provided by Wide Area Augmentation System (WAAS) (Figure 7.3).

Measured IP/Resistivity data were presented as color pseudosections of 3-point decoupled phase and apparent resistivity plotted with the results of the two-dimensional inversions at a scale of 1:20,000. IP and resistivity inversion results and data are shown in separate plots. The surveys identified multiple targets for future exploration.


 

Source: Zonge 2009b

Figure 7.3: 2009 IP/Resistivity Survey Lines

2011 Survey

Zonge International Inc. conducted a pole-dipole Complex Resistivity IP (CRIP) investigation for Lion CG on the MacArthur property during the period from 5 February through 7 March 2011. Pole-Dipole CRIP data were acquired on 7 lines (Figure 7.4) for a total coverage of 37.0 line-km and 210 collected stations (Zonge, 2011).


 

Pole-dipole CRIP measurements acquired for each line were presented in colored pseudosections of apparent resistivity, raw phase response data, and 3-Pt decoupled phase response with posted values. The pole-dipole IP and resistivity cross-sections provided were 2-D smooth-model inversion results.

The surveys identified multiple targets for future exploration. A moderate intensity IP source (25 - 50 milliradian) is identified on the three northwestern Lines (5300, 4900 and 4300) near stations 24000-25800. On the Southern Lines (5300 extension to the South, 4500, 5600 and 6350), the 2-D smooth model inversions show uniform IP values as low as 2-10 milliradian. On Line 7500 (N-E line) the IP source shifts beneath station 24700-25300, with the 2-D smooth-model suggesting a narrower, deeper and less intense IP response (25-35 milliradian) than the lines to the northwest.

Source: Zonge 2011

 Figure 7.4: 2011 IP/Resistivity Survey Lines


 

2016/2017 Survey

Zonge conducted an induced polarization-resistivity survey for Lion CG during November 2016, and February 2017 (Zonge International, 2017).  Data were acquired along eight lines using Dipole-Dipole and Pole-Dipole arrays.

One line crossed over the Yerington pit. The line was surveyed using the dipole-dipole method with a dipole length of 300 m with readings taken from N=1 to 16, which senses response to an approximate depth of 900 m below surface. Because this line crossed the existing pit including pit lake it was necessary to place some receiver and transmitter stations on the pit bottom beneath the pit lake. The total length of the line was 5.4 km of which approximately 600 m was in the pit itself.

Data quality was good and four anomalous IP zones were detected. Figure 7.5 contains the IP response from 2D inversion of the observed data (lower panel). The location of the section and the IP line is shown in the upper panel (single red line) on the district geology map. One zone occurs south of the pit, coincident with an anomalous zone defined by past Anaconda surveys. This zone is referred to as the Native Copper zone. The zone extends over 500 m along the line with an intrinsic IP response of 25 milliradians which is equivalent to approximately 1-2 % by volume of metallic sulfides. The depth to the top of the zone is estimated at 400 m below surface.

A strong IP anomaly was detected directly below the Yerington pit and is 500 m wide along the line. The anomaly has an intrinsic value exceeding 40 milliradians which is equivalent to 3-5% by volume metallic sulfides.

Two additional anomalies were detected north of the pit, one within the mine waste dumps and one in the area known as Groundhog Hills. The anomaly in the waste dumps is shallow and weak on the order of 20-25 milliradians. The anomaly in the Groundhog Hills area is somewhat stronger, being 25-30 milliradians in magnitude. The top of this zone is at a depth of 200 m below ground-surface.

Source: Zonge International 2017

Figure 7.5: IP Response from 2D Inversion (Section 309980 E)


 

7.2.3 Ground Magnetic Survey

Zonge performed GPS-based ground magnetic (Zonge, 2009a) and Induced Polarization and Resistivity surveys (Zonge, 2009b) for Lion CG on the MacArthur Project during November 2009.

Ground Magnetic/GPS data were acquired on six lines-oriented north/south for a total distance of 31.8 line-kilometers of data acquisition.

Total field magnetic data were acquired with a GEM Systems GSM-19 Overhausereffect magnetometer. Positioning was determined with Trimble PRO-XRS GPS receivers that utilize the integrated real-time DGPS beacon for position corrections.

Figure 7.6 shows the stacked magnetic profile. The magnetic surveys along with the IP/resistivity surveys identified multiple targets for future exploration.

Source: Zonge 2023

Figure 7.6: Stacked Magnetic Profile


 

7.3 DRILLING

7.3.1 Historical Drilling

7.3.1.1 Yerington

Anaconda conducted considerable exploration and production drilling during the long tenancy of the Project, which resulted in the existing Yerington pit. Although the number of exploration drill holes and footage is unknown, historic records indicate that well over a thousand holes, including core and rotary, were drilled in exploration and development at the Yerington pit alone.

At the Anaconda Collection - American Heritage Center, University of Wyoming at Laramie, a large inventory of Anaconda data is available for review. Approximately 10,000 pages of scanned drill hole records from the library were reviewed to obtain drill hole information on the Project. While some holes contained only lithologic or assay summary information, after final verification 559 Anaconda holes totaling 236,536.9 ft contained adequately detailed assay, hole location and orientation information to be used in the mineral resource estimate. An additional 233 drill holes totaling 64,092.0 ft were digitized from sections, cross-validated and included in the drill hole database for use in the Yerington mineral resource estimate. In 2024, further review of the available Anaconda data was conducted by Lion CG, and an additional 17 drill holes (totaling 7,477.2 ft) were added to the drill hole database.  The data verification conducted by AGP for these holes is discussed in Section 9.1.2.

Of additional benefit to the Lion CG program, the core left on site by Anaconda was available for assay by Lion CG. As part of the validation of the Anaconda data (Bryan, 2014), selected intervals from 45 Anaconda core holes were submitted to Skyline Assayers and Laboratories for assay to compare with assays recorded from the historical documents. Although historic drilling included intervals subsequently mined by Anaconda, they remained in the database for statistical and interpolation purposes. Anaconda drill hole locations (based on drill logs and digitized sections) that were incorporated into the database are shown in Figure 7.7.


 

Source:  AGP 2025
Notes: Green-Original Historic drill holes, Red-Additional Historic drill holes
 Grid is 1000 x 1000 m
 Drill holes projected on the current topography

Figure 7.7: Yerington Historic Drilling Collar Plot

7.3.2 MacArthur

During MacArthur's exploration history (including North Ridge and Gallagher), several operators have contributed to the pre-Lion CG drill hole database of more than 300 holes. Figure 7.8 shows the historic collars for MacArthur conducted by the U.S. Bureau of Mines (USBM), Anaconda Company, Bear Creek Mining Company, Superior Oil Company, and Pangea Explorations, Inc.

Anaconda's drilling at MacArthur, supervised by Anaconda's Mining Research Department, was accomplished using Gardner-Denver PR123J percussion drills. The percussion drill was fitted with a sampling system designed by the Mining Research Department, which collected the entire sample discharged from the hole. It is uncertain what type of drilling equipment Anaconda used for core holes. The remainder of the drilling for MacArthur was done by Boyles Brothers Drilling Company using rotary and down-the-hole percussion equipment.


 

Source: IMC 2022

Figure 7.8: MacArthur Historic Drilling Collar Plot in Nevada State Plane Coordinates

7.4 LION CG DRILLING

7.4.1 Yerington

Lion CG's 2011 drilling program totaled 21,887 ft in 42 holes. That included 6,871 ft of core: 14 HQ core holes and one hole (SP-010) collared in PQ and reduced to HQ at 147 ft. Reverse circulation (RC) drilling totalled 15,016 ft in twenty-eight 4.5" RC holes (Table 7.1). Fourteen core holes and four RC holes were drilled to twin Anaconda core holes, while the remaining 24 RC holes were targeted for expansion of mineralization laterally and below historic Anaconda drill intercepts along the perimeter of the Yerington pit.

Drill hole siting was hampered by pit wall geometry and by the presence of the pit lake and was confined to selected benches within the Yerington pit to maintain safe access around the existing pit lake.

The total area covered by the drilling resembles an elliptical doughnut (the accessible ramps and roads along perimeter within the Yerington pit) measuring approximately 6,000 ft west-northwest by 2,500 ft. Drill hole spacing is irregular due to access and safety limitations within the pit. Table 7.1 provides basic collar information for 2011 drilling by Lion CG.


 

Table 7.1: 2011 Drilling Yerington Copper Project
Drill Hole Azimuth Dip Total Depth (ft) Purpose Type
SP-001 0 -90 207.5 Twin Core
SP-002 0 -90 259 Twin Core
SP-003 0 -90 405 Twin Core
SP-004 0 -90 803.5 Twin Core
SP-005 0 -90 390 Expl RC
SP-006 0 -90 791 Twin Core
SP-007 0 -90 340 Expl RC
SP-008 0 -90 435 Expl RC
SP-009 0 -90 355 Expl RC
SP-010 90 -70 741 Twin Core
SP-011 180 -60 500 Expl RC
SP-012 180 -60 1000 Expl RC
SP-013 180 -70 1000 Expl RC
SP-014 0 -90 341.5 Twin Core
SP-014A 180 -90 1000 Expl RC
SP-015 0 -90 438 Twin Core
SP-016 180 -70 780 Expl RC
SP-017 0 -90 216.5 Twin Core
SP-018 90 -70 530 Expl RC
SP-019 0 -90 300 Twin Core
SP-020 180 -80 265 Expl RC
SP-021 180 -60 720 Expl RC
SP-022 180 -60 940 Expl RC
SP-023 180 -60 596 Twin RC
SP-024 0 -90 780 Expl RC
SP-025 0 -90 610 Expl RC
SP-026 180 -60 655 Expl RC
SP-027 0 -90 797 Twin Core
SP-028 0 -90 300 Twin RC
SP-029 0 -90 560 Twin RC
SP-030 0 -90 460 Twin RC
SP-031 0 -90 162 Twin Core
SP-032 0 -90 506 Twin Core
SP-033 0 -90 190 Expl RC
SP-034 180 -60 903 Twin Core
SP-034A 0 -90 365 Expl RC
SP-035 0 -60 190 Expl RC
SP-036 0 -60 550 Expl RC
SP-037 180 -60 180 Expl RC
SP-038 90 -60 830 Expl RC
SP-039 0 -60 295 Expl RC
SP-040 0 -55 200 Expl RC

Notes:

Twin=Twin hole

Expl=Exploration


 

The 2017 and 2022 drilling focused on deeper drill holes to confirm the extent of mineralization. Lion CG completed an additional seven holes, totaling 15,636.7 ft. Four of the holes were pre-collared using RC and changed to HQ sized core (Table 7.2).

Table 7.2: 2017/2022 Drilling Yerington Copper Project
Drill Hole Year Drilled Azimuth Dip Total Depth (ft) Purpose Type
YM-041 2017 205.00 -55.00 714.0 Expl RC
YM-041A 2017 201.77 -53.83 2589.7 Expl RC/Core
YM-042 2017 202.27 -56.80 2770.6 Expl RC/Core
YM-043 2017 200.59 -52.38 2490.0 Expl RC/Core
YM-044 2017 189.09 -58.44 2746.7 Expl RC/Core
YM-045 2017 204.03 -54.34 2533.2 Expl Core
YM-046 2022 29.18 -47.20 1792.5 Expl Core

Notes:

Expl=Exploration

Diamond drilling was completed at Yerington in 2024 totaling 3,457.5 ft of drilling in four core drill holes (Table 7.3) which were targeted for expansion and resource upgrade.

Table 7.3: 2024 Drilling Yerington Copper Project
Drill Hole Year Drilled Azimuth Dip Total Depth (ft) Purpose Type
YM-047 2024 210 -45 1083.5 Expl Core
YM-047A 2024 210 -45 470.0 Expl Core
YM-048 2024 210 -45 1270.0 Expl Core
YM-049 2024 210 -45 634.0 Expl Core

Notes:

Expl=Exploration

Figure 7.9 illustrates the drilling conducted by Lion CG relative to the current topography and historic Anaconda open pit.


 

Source: AGP 2025
Notes: Drill holes projected on current topography

Figure 7.9: Yerington Diamond Drilling by Lion CG

7.4.2 MacArthur

From 2007 through to 2010, Lion CG completed an extensive drilling program of 123,005 ft in 375 holes, including 28,472 ft of core over 32 holes and 94,533 ft of reverse circulation drilling over 343 holes. Lion CG's initial objective was to verify and expand the MacArthur oxide resource, as defined by the 1972-1973 Anaconda drilling.

Considering minor secondary chalcocite intersected in the few Anaconda drill holes that reached depths greater than 300 ft, Lion CG successfully targeted a deeper chalcocite zone in step-out drill holes from the pit. The program expanded the oxide mineralization and encountered a large, underlying tabular blanket of mixed oxide-chalcocite mineralization. Lion CG's deeper drill holes, testing the western and northern margins of the chalcocite mineralization, encountered minor primary copper sulfide mineralization below the chalcocite blanket (Tetra Tech, 2009).

In 2011, drilling centered on approximately one-half square mile from the North Ridge area to the present-day MacArthur pit, and the Gallagher area located west of the existing MacArthur pit. Drill spacing was reduced to 250-foot centers on several drill fences. South-bearing angle holes tested the WNW, north-dipping structural or mineralized grain. In 2021, a focus was made to continue upgrading the resource calculation in the main MacArthur area and to step out to the east-southeast to test for additional acid-soluble copper mineralization. These drill holes were vertical or south bearing. (Table 7.4).

Also, during 2011, 3,275 ft of PQ-size diamond core was drilled at 26 sites for the purpose of metallurgical test work. The PQ holes twinned the existing Lion CG RC and core holes.


 

In 2021, 5,147 ft of HQ-size diamond core exploration drilling in ten holes was completed, and 4,445 ft of PQ-size diamond core was drilled in thirteen holes for metallurgical sampling.

In 2021, IMC developed a mineral resource estimate for the MacArthur, North Ridge, and Gallager areas using a drill hole database consisting of 747 drill holes containing 299,044 ft of drilling. Table 7.4 shows the number of holes and footage by the company. The drilling completed by Pangea Exploration was removed from the database.

Table 7.4: MacArthur Drilling Used for 2021 Mineral Resource Estimate
Company Program Date Number of Holes Ft Drilled
U. S. Bureau of Mines 1947 - 1950 8 3,414
Anaconda Company 1955 - 1973 291 59,327
Bear Creek Mining Co. 1963 - 19?? 8 2,934
Superior Oil 1967 - 1968 11 13,116
Lion CG 2007 - 2021 429 220,253
Total   747 299,044

Source: IMC 2022
Notes: 2021 Exploration drill holes are highlighted with a white circle.

Figure 7.10: MacArthur Drilling by Lion CG (as of 2021)

In 2024, drilling was focused on upgrading the resource within and around the main portion of MacArthur. Drilling consisted of 18 reverse circulation drill holes, totaling 6,165 ft (Figure 7.11 and Table 7.5). Alford Drilling, LLC of Elko, NV. conducted RC drilling. Downhole surveys were recorded every 5 ft, working in continuous mode.


 

Source: IMC 2025

Figure 7.11: MacArthur Drilling by Lion CG (as of 2024)

Table 7.5: 2024 Drilling MacArthur Project
Drill Hole Year Drilled Azimuth Dip Total Depth (ft) Purpose Type
QM-343 2024 180 -60 280 Expl RC
QM-344 2024 180 -60 330 Expl RC
QM-336 2024 0 -90 130 Expl RC
QM-337 2024 180 -60 310 Expl RC
QM-338 2024 180 -60 325 Expl RC
QM-339 2024 180 -60 350 Expl RC
QM-340 2024 180 -60 340 Expl RC
QM-341 2024 180 -50 600 Expl RC
QM-342 2024 180 -60 520 Expl RC
QM-342A 2024 180 -60 700 Expl RC
QM-345 2024 180 -60 200 Expl RC
QM-346 2024 180 -60 130 Expl RC
QM-347 2024 180 -60 200 Expl RC
QM-348 2024 0 -90 345 Expl RC
QM-349 2024 180 -70 495 Expl RC
QM-350 2024 180 -60 230 Expl RC
QM-351 2024 180 -60 290 Expl RC
QM-352 2024 0 -90 390 Expl RC


 

7.4.3 Vat Leach Tails

VLT are the leached products of Anaconda's vat leach copper extraction process (CH2M Hill, 2010). The oxide tailings dumps, located north of the process areas, contains the crushed rock that remained following the extraction of copper in the vat leaching process. The vat leach process involved crushing ore into a uniform minus 0.5-inch size and loading it into one of eight large concrete leach vats where weak sulfuric acid was circulated over an 8-day period. Following the 8-day cycle, the spent ore was removed from the vats and transferred to haul trucks for conveyance to the oxide tailings area (OU-6, Figure 7.12).

METCON Research (METCON) conducted a metallurgical study for Lion CG to support a scoping study for the Anaconda Vat Leach Tailings (Phase I) Project in Yerington, Nevada. The metallurgical study was conducted on drill hole samples obtained from a wet and dry sonic drilling campaign from the Anaconda Vat Leach Tailings.

The mineralization is expected to be primarily oxide forms of copper, chrysocolla, neotocite, others, and secondary sulfide (chalcocite) (SRK, 2012).

There were 22 drill holes, VLT-001 to VLT-022, completed by Major Drilling in May-June of 2012 using wet rotosonic drilling methods. In September 2012, nine dry rotosonic drill holes (Prosonic) by Boart Longyear twinned the wet sonic drill holes configured with an 8-inch-diameter drill pipe and a 7-inch core. "T" was added to the hole number to identify the twin holes: VLT-12-002, VLT-12-003T, VLT-12-005T, VLT-12-006T, VLT-12-011T, VLT-12-016T, VLT-12-017T, VLT-12-019T and VLT-12-021T (Figure 7.12).

Collars were surveyed by Lion CG using handheld Garmin eTrex 10 GPS. No downhole surveys were recorded. Summary drill logs collected information on lithology, grain size and copper mineralization.

Source: AGP 2025

Figure 7.12: VLT Collar Plot


 

7.5 DRILLING PROCEDURES AND CONDITIONS

Lion CG's drill holes through 2011 were surveyed by Lion CG consultants using a Trimble XHT unit with horizontal accuracy to within one-half meter and vertical accuracy from one-half to one meter. All other collars were surveyed using a handheld Garmin eTrex GPS by Lion CG geologists.

Drilling contractors and downhole surface information are summarized in Table 7.6. Some shorter holes may not be surveyed.

Table 7.6: Yerington and MacArthur Drilling Contractors by Year
Year Location Type Contractor Downhole
Survey
Interval
Downhole
Survey
Instrument
Downhole Survey
Contractor
2007 MacArthur Core
RC
Kirkness Diamond Drilling
Diversified Drilling LLC
50 ft Gyroscope International Directional Services LLC
2008 MacArthur Core
RC
KB Diamond Drilling
Diversified Drilling LLC
50 ft Gyroscope International Directional Services LLC
2009 MacArthur Core
RC
Major Drilling America Inc.
Diversified Drilling LLC
50 ft Gyroscope International Directional Services LLC
2010 MacArthur Core
RC
Major Drilling America Inc.
Diversified Drilling LLC
50 ft Gyroscope International Directional Services LLC
2011 MacArthur Core
RC
Ruen Drilling, Inc.
George DeLong Construction, Inc.
Diversified Drilling LLC
Leach Drilling, Inc.
50 ft Gyroscope International Directional Services LLC
2011 Yerington Core
RC
Ruen Drilling, Inc.
George DeLong Construction, Inc.
Diversified Drilling LLC
50 ft Gyroscope International Directional Services LLC
2017 Yerington RC
Core
Layne Christensen Drilling 50 ft Gyroscope International Directional Services LLC
2021 MacArthur Core National EWP 50 ft Gyroscope International Directional Services LLC
2022 MacArthur Core InterGeo Drilling 50 ft Gyroscope International Directional Services LLC
2022 Yerington Core InterGeo Drilling 50 ftj Gyroscope International Directional Services LLC
2023 MacArthur RC Alford Drilling, LLC 10 ft Gyro Master Alford Drilling, LLC


 

Table 7.6: Yerington and MacArthur Drilling Contractors by Year
Year Location Type Contractor Downhole
Survey
Interval
Downhole
Survey
Instrument
Downhole Survey
Contractor
2024 Yerington Core Alford Drilling, LLC 50 to 100 ft ChampGyro Alford Drilling, LLC
2024 MacArthur RC Alford Drilling, LLC 5 ft ChampGyro Alford Drilling, LLC

Core recovery was recorded for all core drill campaigns and averaged about 70%, but in general recovery exceeded 80%. Lion CG technicians measured core recovery per drill run as denoted by the core blocks inserted into the core boxes by the drilling contractor. For Yerington, drill intersections with less than 40% recovery were not used for the mineral resource estimate. No other factors were identified that could materially impact the accuracy and reliability of the drilling results.

Geologists logged information on the alteration, lithology, structures and sulfide descriptions. This information was captured on paper forms and loaded into a digital database combined with the collar and downhole survey information. Digital color core photographs are taken prior to the collection of samples.

7.6 QP ADEQUACY STATEMENT

It is the opinion of the QPs (TMMA & IMC) that the exploration and diamond drilling procedures and protocols used are consistent with generally accepted industry practices and, therefore, suitable for mineral resource and reserve estimation. 


 

8.0 SAMPLE PREPARATION, ANALYSES, AND SECURITY

8.1 SAMPLE PREPARATION AND ANALYSES

8.1.1 Anaconda - Yerington and MacArthur

Samples from MacArthur and Yerington were delivered to Anaconda's analytical laboratory in Yerington, NV. Samples were blended, pulverized, and a 2-gm sample was extracted for assay. According to standard wet chemistry procedures, samples were assayed for total copper and oxide copper.

Assay reports were handwritten and signed by Anaconda's Chief Chemist. One original was issued to management along with three carbon copies (Koehler, 2008).

8.1.2 Lion CG - Yerington Copper Project

Figure 8.1 shows the Lion CG core sampling facility at the Yerington Copper Project. The sampling area is connected to the logging area via a conveyor.

Source: AGP 2023

Figure 8.1: Core Sampling Facility

8.1.2.1 Reverse Circulation Sampling

Samples are collected in a conventional manner via a cyclone and standard wet splitter. Samples are collected in 17-in by 26-in cloth bags placed in five-gallon buckets to avoid material spillage. Sample bags are pre-marked by Lion CG personnel at five-foot intervals and include a numbered tag inserted into a plastic bag bearing the hole number and footage interval. Collected samples, weighing approximately 15 to 20 pounds each, are wire tied and then loaded onto a ten-foot trailer with a wood bed, allowing initial draining and drying. Each day, Lion CG personnel or the drillers at the end of their shift haul the sample trailer from the drill site to Lion CG's secure sample preparation warehouse in Yerington, Nevada.

Having been transported on a ten-foot trailer by drill crews or Lion CG personnel from the drill site to the secure sample warehouse, RC sample bags are unloaded onto suspended wire mesh frames for further drying. Diesel-charged space heaters assist in drying during the winter months. Once dry, four to five samples are combined in a 24-by-36-inch woven polypropylene transport ("rice") bag, wire tied and carefully loaded on plastic-lined pallets. Each pallet, holding approximately 13 to 15 rice bags, is shrink-wrapped and further secured with wire bands. Each pallet is weighed.


 

In the 2011 drill program, pallets were picked up and trucked by Skyline Assayers & Laboratories (Skyline) personnel who, at the time, operated a sample preparation facility in Battle Mountain, Nevada. Once Skyline prepared each sample in its Battle Mountain facility, approximately 50-gram sample pulps were air-freighted to Skyline's analytical laboratory in Tucson, Arizona for analyses and assay.

In 2017, Bureau Veritas' personnel picked up the samples, which were prepped in the Sparks, NV facility and then forwarded to their Vancouver laboratory for analysis.

In 2022 and 2024, Skyline personnel (from Tucson) picked up the samples which were prepped and analyzed in their Tucson laboratory.

Industry-standard chain of custody protocols were followed for all shipments.

8.1.2.2 Core Sampling

Drill core, having been transported at the end of each shift by the drill crew to Lion CG's secure sample warehouse, is logged by a Lion CG geologist who marks appropriate sample intervals (one to nominal five ft) with colored flagging tape and metal tags. Lines are marked along the length of the core with red wax crayons to indicate where the core piece should be sawed and sampled. After logging and marking the sample intervals, each core box is photographed, with a sample tag at the beginning of the core box indicating project name, drill hole number, box number, and footage. Core samples are then sawed or split in half on-site by Lion CG personnel. Sample tags and sample bags are labelled with the drill hole number, sample number, and footage. Half of the split was bagged in 11-by-17-inch cloth bags while the other half was returned to the appropriate core box for storage in the sample warehouse.

8.1.2.3 Sample Analyses

Samples were analyzed for total copper (TCu) and other analytes, as shown in Table 8.1 for core and RC drill samples. A selected core was used to provide bulk density measurements, as described in Section 11.2.

Samples processed by Lion CG between 2011 and 2024 were analyzed by:

  • Skyline Assayers and Laboratories: Tucson, Arizona. ISO/IEC 17025:2017 accredited.
  • Bureau Veritas Commodities Canada Ltd.: Reno, Nevada. ISO/IEC 17025:2017 accredited.
  • ALS Minerals Laboratory Reno, Nevada. ISO/IEC 17025:2017 accredited.

Sample preparation (crush, split, pulverize) was generally completed at local facilities in Nevada before shipment to the primary assay laboratories.

Skyline was used for the 2011 SP series of drilling and in 2022 and 2024 drilling. Bureau Veritas was used for the 2017 YM series drill holes.


 

ALS Minerals Laboratory was used for check samples.

All laboratories used by Lion CG are independent of them.

Table 8.1: Summary of Analytical Packages and Laboratories
Laboratory Procedure Code Procedure Description
Skyline Assayers MULTI-AAS
SEQ-AAS-AS
SEQ-AAS-CN
SEA-CuSAP
FA-1
TE-7
Multi-acid digestion AAS Copper
Sequential Analysis Copper AAS Acid Soluble
Sequential Analysis Copper AAS CN Soluble
Sequential Analysis Copper AAS Ferric Sulfate Soluble
Au Fire Assay - AA (Geochem) 30 g
Trace Elements by Multi Acid (with HF), ICP-MS
Bureau Veritas FA430
MA300
Au by 30 g fire assay, AAS finish
4 Acid digestion ICP-OES analysis 0.25 g
ALS Minerals CU-OG62
ME-OG62
Ore Grade Cu - Four Acid
Ore Grade Elements - Four Acid, ICP-AES analysis

8.1.3 Lion CG - Vat Leach Tails

Wet and dry sonic drilling was conducted on the Vat Leach Tails. The material that was drilled was collected directly in plastic sleeves (approximately 5 ft. each). For the wet sonic drilling, all the samples were sent to Metcon in Tucson, Arizona, for assay and subsequent metallurgical testing. The sample was split for the dry sonic drilling (twin holes). To split the material, Lion CG laid the sample between two half pipes (~12" split pipe) and then ran a box cutter down the middle of the plastic sleeve to cut it. Half of the sample went into one pipe and the other half into another. Lion CG placed the material from each half pipe into separate zip-tied plastic bags labelled with drill hole number, sample number, and footage. Half of the sample was submitted to Metcon for assaying, and the remaining half was placed in storage for potential additional testing. For all assay work, the Metcon assay code was MA-AA, which was a multi-acid digestion with AAS finish.

8.1.4 Lion CG - MacArthur

8.1.4.1 Reverse Circulation Sampling

Having been transported on a ten-foot trailer by Lion CG personnel from the drill site to the secure sample warehouse, RC sample bags are unloaded onto suspended wire mesh frames for further drying. Diesel-charged space heaters assist in drying during winter months. Once dry, sets of three samples are combined in a 24- by 36-inch woven polypropylene transport ("rice") bag, wire tied, and carefully loaded on plastic lined pallets. Each pallet, holding approximately 13 to 15 rice bags, is shrink-wrapped and further secured with wire bands. Lion CG samples were shipped via UPS Freight to Skyline Assayers & Laboratories (Skyline), Tucson, Arizona through 2008. During the 2009-2010 drill campaign, Skyline dispatched a transport truck from Tucson to collect samples. In 2011, Skyline established a sample preparation facility in Battle Mountain, Nevada, from which trucks were dispatched to pick up Lion CG's drill samples.Once Skyline prepared each sample in its Battle Mountain facility, approximately 50-gram sample pulps are air-freighted to Skyline's analytical laboratory in Tucson, Arizona for analyses and assay. In 2024, Skyline dispatched a truck from Tucson, Arizona that picked up the samples.


 

Lion CG weighs each shrink-wrapped pallet of samples prior to departure from Yerington. Rejects and pulps are returned to Lion CG and stored under cover in a secure location.

Industry standard chain of custody protocols were followed for all shipments.

8.1.4.2 Core Sampling

Drill core, having been transported at end of each shift by the drill crew to Lion CG's secure sample warehouse, is logged by a Lion CG geologist who marks appropriate sample intervals (approximately 5 ft) with colored flagging tape and marks the core with a wax pencil to indicate appropriate location for sawing or splitting. Each core box, bearing a label tag showing drill hole number, box number, and box footage interval, is then photographed.

Core preceding drill hole QMCC-20 was sawed in half by Lion CG personnel; core holes QM-026, QM-036, QM-041, QM-046, and QM-049 were split in half using a hydraulic powered blade at the warehouse by Lion CG personnel. From 2010-2011 core holes were sawed by ALS Minerals Laboratory, Reno, Nevada (ALS). In 2021, Lion CG personnel sawed and/or split the core samples. Samples with a large percentage of clay were split to preserve the fines.

When on-site sawing and or splitting was done, one half of the split was bagged in 11- by 17-inch cloth bags marked with drill hole number, footage interval, and sample number for assay while the other half was returned to the appropriate core box for storage in the sample warehouse.

Following geologic logging, magnetic susceptibility and RQD measurements, and photography, PQ core for metallurgical testing was shrink-wrapped in its cardboard core box, stacked on pallets, shrink-wrapped together, wire banded, and weighed. In 2011, pallets were shipped to METCON, Tucson, Arizona via UPS Freight. Chain of Custody was signed upon departure from Yerington and receipt in Tucson. In 2021, PQ samples were shipped to McClelland Laboratories, Sparks, Nevada via UPS Freight with the same sample chain of custody procedures.

8.1.4.3 Sample Analyses

During 2007, 12 core holes were analyzed at American Assay Laboratories (AAL) in Sparks, Nevada. AAL is ISO/UEC 17025 certified as well as a Certificate of Laboratory Proficiency PTP-MAL from the Standards Council of Canada.

Lion CG elected to use Skyline an ISO certified assay lab in Tucson, Arizona for all further analytical work. Samples submitted to AAL were re-assayed (pulps or rejects) by Skyline for consistency of the data set. Lion CG samples arrived at Skyline via UPS freight from 2007-2008.

Core from holes QM-099, QM-100, and QM-109 (2009-2010) and QM-163, QM-164, QM-165, QM-166, QM-177 and QM-185 (2011 program) were submitted to ALS Minerals, Sparks, Nevada. ALS Minerals is an ISO registered and accredited laboratory in North America. From 2009-2011 samples were picked up by a transport truck dispatched by Skyline from its temporary facility in Battle Mountain, Nevada and 2021 by a transport truck dispatched from Tucson by Skyline.

The Skyline assay procedures are as follows:


 
  • Total Copper: a 0.2000-to-0.2199-gram (g) sample is weighed into a 200-ml flask. A three-acid mix is added and heated to about 250°C for digestion. The sample is made to volume and read on an ICP/AAS using standards and blanks for calibration
  • Acid Soluble Copper: a 1.00 to 1.0199 g sample is weighed into a 200 ml flask. Sulfuric acid in water and sodium sulfite in water are mixed and added to the flask and allowed to leach for an hour. The sample is made to volume and read on an ICP/AAS using standards and blanks for calibration
  • Ferric Soluble Copper (QLT): a 0.500 to 0.5099 g sample is weighted into a 200 ml flask. Sulfuric acid ferric sulfate mixed with deionized water are mixed and added to the flask and allowed to leach for an hour. The filtrate is cooled, made up to a standard volume, and the copper determined by AA with appropriate standards and blanks for calibration
  • Sequential Copper Leach: consists of four analyses: Total Copper, Acid Soluble Copper, Cyanide Soluble Copper, and the difference, or Residual. Following analysis for Total Copper and Acid Soluble Copper, the residue from the acid soluble test is leached (shake test) in a sodium cyanide solution to determine percent cyanide soluble minerals. The Sequential Copper Leach is a different approach to the Ferric Soluble Copper (QLT) leach, with possible greater leaching of certain sulfides (e.g. chalcocite or bornite) during the cyanide leach step
  • Acid Consumption of Pulps: a 2.00 to 2.10 grams is weighted into a 50 ml screw cap centrifuge. Sulfuric acid is added to the sample and the shaken for an hour. The sample is decanted into a 50 ml screw cap centrifuge tube where titration is undergone and acid consumption calculated with the Tiamo software program

From 2009-2011, Lion CG requested 34-element trace element geochemistry from Skyline on selected samples which were analyzed by ICP.OES Aqua Regia Leach to determine presence the of other important elements.

During 2009-2010 Lion CG core samples were picked up at Lion CG's warehouse facility by ALS Minerals personnel and transported to ALS Minerals laboratory in Sparks, Nevada. ALS Minerals personnel sawed the core, saving one-half for return to Lion CG. ALS assayed core for trace element geochemistry with 48-element Four Acid "Near-Total" Digestion.

In 2020, to better understand acid consumption of the acid soluble mineralized zones, 111 pulps were analyzed by Skyline Laboratories.

8.2 DENSITY

8.2.1 Drill Samples-Yerington

Density tests were completed in November 2011, by Kappes, Cassiday & Associates, based in Reno, Nevada, on core samples from Lion CG drilling. Representative samples were collected from six rock types representing oxide and sulfide mineralization. No further details were provided regarding the methodology but prior work by Kappes, Cassiday & Associates for Lion CG was based on a water displacement method.


 

8.2.2 Drill Samples-MacArthur

Density determinations were from core samples collected by Lion CG personnel in 2008 for oxide, mixed and sulfide material. The samples were wax coated and density determination was based on a water displacement method. No further details regarding the methodology were available.

In 2024, samples were collected across the different redox zones: leach cap, oxide, mixed and sulfide but independent of rock type.  Primarily collected samples within or proximal to MacArthur pit but some samples were also collected from North Ridge and Gallagher. The 2024 density determinations by Paragon Geochemical Laboratories (Sparks, NV) were based on their water displacement method without wax coating (Bulk-DEN).

8.2.3 Residual Materials

Density for Anaconda residual materials (VLT, S-23 and W-3) were based on historic reports (SRK, 2023). Density for Arimetco (HLP) material was based on laboratory testing of remedial investigation drilling reported by CH2M Hill (USEPA, 2011). In general, the HLP materials tested ranged from well-graded sand to well-graded gravel. The amount of fines varied but typically did not exceed 15 percent. Moisture content was measured for field conditions on oven-dried samples, and the dry density was calculated (USEPA, 2011a).

8.3 SAMPLE SECURITY

All samples are delivered by the drillers twice a day (at end of driller's shift) or Lion CG personnel picks them up from the drill site. When core samples are delivered, they go directly into the logging facility and are under lock and key. The RC samples are dropped off on-site (behind a locked gate) and left in the trailer. Lion CG places the samples onto wire racks to finish drying and brings them into the logging facility at end of shift. If inclement weather or during the winter, Lion CG brings them directly into the warehouse where they dry on wire racks.

The only access to the core is to those who can get into the logging facility which is Lion CG employees and any consultants (geologist and/or sample splitter/sawyer) at the time of work being performed.  The RC samples are left outside within the Yerington Mine Site during daytime hours and can only be accessed by personnel who can get into the mine site locked gate which includes Lion CG personnel, the site manager, drillers, and mine site security personnel.

Chain of Custody forms are prepared by Lion CG for the samples with quality assurance/quality controls samples inserted. Primarily, the laboratory picks up the samples and sign-off on the Chain of Custody.  Rarely, Lion CG has dropped the samples off directly, and in that case the Chain of Custody is also signed off. Lion CG retains the Chain of Custody forms as documentation/confirmation.

Rejects and pulps are returned to Lion CG following a Chain of Custody protocol and are stored under cover in a secure location.


 

8.4 QUALITY CONTROL

No historic data on quality control at Anaconda's analytical laboratory in Yerington was found. The laboratory was not independent of Anaconda Company.

8.4.1 Yerington

Lion CG implemented a quality assurance and quality control assay protocol whereby either one blank or one standard is inserted with every ten samples into the assay stream. Additional check samples were submitted to ALS Minerals Laboratories in Sparks, Nevada. Core duplicates were not used.

Lot failure criteria were established as any standard assaying beyond two standard deviations of the expected value, or any blank assay greater than 0.015 percent TCu.

Geochemical reference standards are listed in Table 8.2. Blanks were also purchased from Moment Exploration Geoservices, two were used: Si.Blank.21.01 and Si.Blank.21.03. The accepted values were 0.005% total copper.

Table 8.2: Geochemical Reference Standard
Standard Source Accepted Value, % Cu
A106010X Moment Exploration GeoServices 0.215
A106009X 0.136
A106012X 0.388
A106013X 0.574
A106014X 1.428

8.4.1.1 Lion CG Drilling Prior to 2017

As part of the Lion CG quality control program, 220 standards and 222 blanks were submitted (Table 8.3) along with 5,557 individual drill hole samples to Skyline Laboratories. Additionally, 68 check assays plus seven quality control samples were submitted to ALS Mineral Labs, Reno, and 137 samples plus seven quality control samples were submitted for reassay to Skyline. No quality control failures were found during the reassaying (Table 8.3).

Table 8.3: Lion CG 2011 QAQC Program Results
  Skyline Labs ALS Mineral Labs
Total Drill Hole Samples 5694 68
Submitted Standards 220 3
Failed Standards 8 0
% Standards Failure 3.6% 0
Submitted Blanks 222 4
Failed Blanks 4 0
% Blank Failure 1.8% 0


 

Check assays from ALS Mineral Labs compared well with Skyline assays, providing additional confidence in the assay database, as shown in Figure 8.2.

Source: LionCG 2024

Figure 8.2: Lion CG Check Assay Results

8.4.1.2 Lion CG Drilling 2017-2022

Six drill holes were completed in 2017 by Lion CG and one additional hole in 2022. Table 8.4 summarizes the results of the QAQC program. No issues were noted.

Table 8.4: 2017-2022 QAQC Program Results
  Skyline Assays (2022) Bureau Veritas (2017)
Total Drill Hole Samples 325 2436
Submitted Standards 16 125
Failed Standards 1 2
% Standards Failure 1.6% 6.3%
Submitted Blanks 16 121
Failed Blanks 0 0
% Blank Failure 0.0% 0.0%

8.4.1.3 Lion CG Drilling 2024

Diamond drilling was completed at the Yerington Pit in 2024 totaling 3,457.5 ft of drilling in four core drill holes. Table 8.5 summarizes the results of the QAQC program. Certified Reference Material (CRM) failures were noted for CRM A106012X and A106013X. Samples bracketing the CRM failures were rerun with similar results produced by Skyline and ALS. If the CRM outliers are included for the determination of the standard deviation, the number of failures drops to 5. No other material issues were noted.


 

Table 8.5: Yerington 2024 QAQC Program Results
  Skyline Assays (2024)
Total Drill Hole Samples 609
Submitted Standards 29
Failed Standards 9
% Standards Failure 31.0%
Submitted Blanks 27
Failed Blanks 0
% Blank Failure 0.0%

8.4.2 Vat Leach Tails

Samples were processed by METCON (Tucson, AZ) to determine moisture content, particle size distribution, head assay analysis, and agitated leach testing (Guntumur, 2012a and 2012b). METCON Research was an international consulting group that delivered various services, including analytical testing, metallurgical research, and process engineering design for the global minerals and mining industry. No details were provided with respect to the assay methodology, but assay certificates were provided. METCON is independent of Lion CG. No accreditation information was available, but the assay certificates were signed and stamped by an Arizona Registered Assayer.

A total of 472 samples were submitted for analysis, including 53 duplicate samples (11.2%), 12 blank material samples (2.5%), and 18 standard reference materials (3.8%).

The standards were obtained from the Canadian Certified Reference Materials Project (CCRMP) operated by CANMET Mining and Mineral Sciences Laboratories in Ottawa, Ontario. The three standards used were HV-2, SU-1b, and MP-1b. The source of the blank material was not identified, but the accepted detection limit was <0.001% Cu.

No outliers or bias were noted in the review of the standards, blanks, and duplicates.

8.4.3 MacArthur

IMC completed a study of the duplicate samples, standards, and blank assays in the Lion CG drill hole database. The checks are limited to the holes and samples from the Lion CG holes. Core duplicates were not used. Beginning in 2009, Lion CG started a program to re-assay selected samples when blanks, standards, or repeat assays exceeded or were below the expected values by 15%, or blanks returned an assay of >.015% Cu. The QC program now re-assays standards outside +/- 2 standard deviations of the expected value, repeat assays +/- 15% of the original assay, and blanks greater than .015% Cu.


 

8.4.3.1 Standards

The data provided to IMC consisted of 1,965 assays run on 11 total copper standards, representing the insertion of a standard into the sample stream approximately every 20 samples. Table 8.6 summarizes the number of check assays run for each standard using the Lion CG drilling up through 2012.

The check on standards shows that a significant portion of the checks fall within two standard deviations of the standard assay value, which is within the acceptable range. The check on standards meets industry standard practices.

Table 8.6: Standards Used on Lion CG Drilling through 2012
Standard Name TCu Standard Value,
%
ASCu Standard Value,
%
Number of
TCu Checks
Number of
ASCu Checks
15000PPM 1.56   119  
4700PPM 0.45   100  
A106008X 0.075   68  
A106009X 0.136   64  
A106010X 0.215   74  
A106011X 0.291   69  
A106012X 0.388   245  
A106014X 1.428   82  
A107002X 0.468 0.440 447 402
A107004X 0.225 0.212 661 586
A108005X 0.414   36  

For the 2021 drilling, Lion CG inserted 46 standards for assay using three different standards (A106009X, A106010X, A106012X). Lion CG inserted these standards at a 1 in 20 interval (46 standards within 911 samples assayed). All standard checks were within two standard deviations.

8.4.3.2 Blanks

Blanks were inserted into the Lion CG drill hole samples approximately every 20 to 25 sample intervals for the drilling up through 2012. The results for 1,816 blanks assayed for total copper and 1,617 assayed for acid soluble copper were provided to IMC. Lion CG inserted 40 blanks into the 2021 drilling samples for an insertion rate of approximately every 23 samples. The results for the 2021 drilling were below the 0.005% TCu Skyline Laboratories detection limit.

8.4.3.3 Check Assays on MacArthur 2021 Drill Holes

As a check for the 2021 drilling, selected duplicate samples were sent to a second lab for assay. Check assays were done for 38 samples of the 2021 drilling assay intervals for total copper, acid soluble copper and cyanide soluble copper. The original lab for these assay intervals was Skyline Laboratories and the check lab was Paragon Geochemical Laboratories Inc. For total copper there were 911 Skyline assays and 38 Paragon assays which meant a check on 4.1% of the data intervals. For acid soluble copper and cyanide soluble copper there were 646 Skyline assays and 29 Paragon assays which meant a check on 4.5% of the data intervals. Figure 8.3 is an X-Y plot of the original Skyline total copper versus the results from Paragon.


 

Source: IMC 2022

Figure 8.3: Comparison of Total Cu Check Assays

8.4.3.4 MacArthur 2024 QAQC Program

Lion CG completed eight drill holes in 2024, and the QA/QC information was provided to IMC for review. Table 8.7 summarizes the results of the QAQC program. Table 8.8 shows the number of samples by drill hole for the blanks and standards. It should be noted that the majority (80%) of the failures (greater than +- 2 standard deviations) for the standards occurred in two standards (A106012X and A106013X), both of which are no longer used by Lion CG. The Skyline assays of standard A106012X cluster around 0.425% (with one very low result removed), ranging between 0.402% and 0.450% compared to the standard value of 0.364%. A similar result occurs for standard A106013X where the Skyline assays cluster around 0.611% (with one very low result removed), ranging between 0.552% and 0.665% compared to the standard value of 0.536%. Potential reasons for these discrepancies could include poor quality of the sample, settlement within the sample bag if the sample was not re-mixed occasionally, or the original value of the standard is not accurate.


 

Table 8.7: MacArthur 2024 QAQC Program Results
  Skyline Assays (2024)
Total Drill Hole Samples 1,230
Submitted Standards 81
Failed Standards 26
      % Standards Failure 32.1%
Submitted Blanks 31
Failed Blanks 2
      % Blank Failure 6.0%

Table 8.8: MacArthur 2024 QAQC Program Details
Hole ID Blanks Standards
A106009X A106010X A106011X A106012X A106013X Total
QM-336 1   1     2 3
QM-337 2   1 1 1   3
QM-338 3 1   1   1 3
QM-339 3 1 1   1   3
QM-340 2   1 1   1 3
QM-341 5 1 1 1 1 2 6
QM-342 3 2 1 1 2 1 7
QM-342A 7 2 3 1 2 1 9
QM-343   1 2 1   1 5
QM-344   1   1 1 2 5
QM-345   1 1     1 3
QM-346       1 1   2
QM-347   1     1 2 4
QM-348   1 1 1 1 1 5
QM-349   1 1 2 2 2 8
QM-350   1 1     1 3
QM-351 2 1 0 2   2 5
QM-352 3 1 1 1 1   4
Total 31 16 16 15 14 20 81
Failed 2 1 1 3 11 9 26
Failed High   1 1 3 10 8 24
Failed Low   0 0 0 1 1 2


 

8.4.3.5 MacArthur 2024 Check Assays

Thirty-three pulps from the 2024 drilling were sent to ALS as checks on the original Skyline assays.

Figure 8.4 compares the two data sets with the orange being the Skyline original assays and the blue being the ALS check assay. The two data sets are within +- 10% of each other for 67% of the data points.

Source: IMC 2025
Notes: Orange - Skyline Original Assays Blue - ALS Check Assays

Figure 8.4: MacArthur 2024 Check Assays

8.5 QP ADEQUACY STATEMENT

It is the QPs opinion that the sampling preparation, security, analytical procedures, and quality control protocols used are consistent with generally accepted industry practices and, therefore, suitable for mineral resource and reserve estimation.


 

9.0 DATA VERIFICATION

9.1 YERINGTON DEPOSIT

Lion CG has validated the historic data through data verification. AGP conducted independent data verification to support the updated mineral resource estimate.

9.1.1 Lion CG Data Verification Procedures

Lion CG carried out detailed data capturing and verification processes in 2011 from Anaconda archives available through the Anaconda Collection - American Heritage Center, University of Wyoming at Laramie. In order to verify and validate this data, three programs were completed:

  • cross sections with composites of captured data were generated to compare against Anaconda archived cross sections with posted composites for 560 historic drill holes
  • eighteen twin drill holes were drilled to confirm historic data
  • using Anaconda core remaining on site, selected intervals from 45 drill holes were sent for assay to compare against historic results
  • subsequent data for 232 additional drill holes was captured directly from historic cross sections after the 2011 validation program established that the sections were accurately reflecting data found in the historic records

The data verification confirmed that the historic data are suitable for use in the mineral resource estimate. Details of the verification are included in prior reports by Bryan (2012, 2014) and AGP (2024).

9.1.2 AGP Data Verification

AGP conducted data verification for the current Mineral Resource estimate (MRE). This included the built-in checks associated with importing data in MinePlan, random checks of database assays compared with assay certificates, and review of the QAQC performance (Section 8.0). This data verification was supported by a site visit conducted from August 26 to 28, 2024. Exploratory data analysis, as discussed in Chapter 11, was an additional component of the data verification process.

9.1.2.1 AGP Site Visit

AGP conducted a site visit on August 26-28, 2024. The Project site shown in Figure 9.1 identifies the Yerington Copper Project and VLT. No drilling or core logging was underway during the site visit.


 

Source: AGP 2025
Notes: A=Yerington Copper Project, B: VLT

Figure 9.1: Yerington Property

The site visit was completed to obtain a current view of the Project, to determine if there were any obvious concerns and to review current exploration work. Drill holes YM-047A and YM-049 (Figure 9.2 and Figure 9.3) were reviewed to compare core versus logging sheets. The comparison did not identify any material differences.

 
Source: AGP 2025

Figure 9.2: YM-047A and YM-049 Core Box Labelling


 

Source: AGP 2025  

Figure 9.3: YM-047A and YM-049 Footage Blocks and Tags 


 

9.1.2.2 Site Visit Check Samples

Seven samples were selected from YM-047A and YM-049 for check assay analysis. Half of the existing sample was collected for the check assay. The QAQC incorporated one blank sample (SiBlank21.01) and one standard reference material (A016009X), no issues were noted. AGP maintained custody of the samples until they were delivered to ALS Laboratory in Reno, NV.

The check assay samples for YM-049 were comparable to the original assays (Figure 9.4) but the results of the check assays for YM-047A were lower but still indicative of copper mineralization.

Source: AGP 2025

Figure 9.4: Check Assays Comparison

9.1.3 Additional Historic Drill Holes

Lion CG identified seventeen additional historic drill holes for inclusion in the drill hole database. Drill hole collars, assays, drill hole logs, and cross-sections were provided to AGP for review and validation. The solid red collars, shown in Figure 9.5, illustrate the drill hole locations relative to the existing database.


 

Source: AGP 2025

Figure 9.5: Additional Historic Drill Holes (Planview)

AGP created cross-sections (Figure 9.6) to compare the additional drill holes with the existing database and prior PEA block model. No material discrepancies were identified by this validation. The additional historic drill holes were accepted for use in the updated MRE.


 

Source: AGP 2025

Figure 9.6: Validation Cross Section for Additional Historic Drill Hole S-20-D-17 (Looking NW)

9.1.4 Vat Leach Tails

Lion CG conducted six sampling programs within VLT, as outlined below. VLT materials are believed to be generally homogeneous with localized differences in geotechnical and geochemical characteristics (USEPA, 2010a). Such differences likely resulted from different oxide types mined and leached by Anaconda and potential variations in the ore beneficiation steps.

The backhoe sampling may also be showing higher copper values due to the capillary action occurring with the VLT. Rainwater penetrating the VLT may turn slightly acidic, allowing for copper to be carried in solution with a travel preference to the outer portions of the VLT due to capillary action (Bonsall, 2012b).

A comparison between the block model grade and these sampling programs demonstrates the VLT block model homogeneity and supports the fact that the block model does not appear to overestimate the VLT grade.

9.1.4.1 2010 VLT XRF Samples (USEPA, 2010a)

Atlantic Richfield Company (ARC) prepared a Data Summary Report that described the field activities and laboratory analytical results under the Revised VLT Characterization Work Plan Using X-Ray Fluorescence (XRF).

ARC's perspective on their work was that based on the observed correlation between copper XRF measurements and laboratory results for the VLT materials samples included in this characterization effort, copper may be suitable for XRF based field screening of VLT materials. For copper, the only metal that indicated a potential correlation between XRF and lab data, the XRF measurements for the VLT materials are generally higher than the lab results and encompass a wider range of values relative to the lab results. However, the 0.84 correlation coefficient for copper was not considered to be a good correlation enough to replace the laboratory analytical results with XRF. Table 9.1 summarizes the XRF and comparable analytical results.


 

Table 9.1: Boxplot Summary for XRF and Laboratory Data, Cu ppm
Method Count Mean Minimum Q1 Median Q3 Maximum
XRF Measurements 49 1333.9 732.5 1052.1 1284.3 1560.9 2437.0
Lab Analytical Results 49 996.5 530.0 765.0 940.0 1100.0 1700.0

Source: USEPA, 2010a

Particle size distribution testing of VLT materials indicated they are composed of the following percentages of sand, gravel and fines:

  • sand (fine to coarse grained) - about 45 percent
  • gravel (fine [3/4-inch minus]) - approximately 40 percent
  • fines (silt and clay particles) - remaining 15 percent

9.1.4.2 2011 Arimetco Inc. VLT Historic Production (Sawyer, 2011)

Arimetco Inc. mined materials from the W-3 and VLT and leached them on five leach pads from 1989 to 1999. NDEP reviewed the available Arimetco mining production records and compiled those for the VLT as listed in Table 9.2. The QP was not able to independently verify the information provided by NDEP (Sawyer, 2011).

Table 9.2: Arimetco VLT Production Summary
Year Tons Head Grade, Cu% Cu lbs
1993 2,181,270 0.10 4,517,818
1994 284,328 0.06 448,380
1995 1,428,085 0.08 2,213,655
1996 284,920 0.08 478,584
1997 273,262 0.08 437,219
1998 7,770,640 0.10 15,541,280
Total 12,222,505 0.10 23,636,936

Source: Sawyer 2011

9.1.4.3 2011 Backhoe Sampling-Column Leach Study (METCON Research, 2011a)

Seven 500 lb. samples (CT1 to CT7) were collected using a backhoe in 2011 but one sample, CT5, was eliminated as a suspect sample as it was located at the top bench of the tailings. A historic photo (Figure 9.7) illustrates the sampling methodology for sample CT1, the location was verified on the site visit and shown in Figure 9.8.


 

Source: SPS 2011

Figure 9.7: CT1 Backhoe Sampling in 2011

Source: AGP 2024

Figure 9.8: CT1 Sample Location in 2024


 

The average grade of the six samples was 0.184% Cu which is significantly higher than the interpolated grade of the block model, 0.095% Cu, at the collocated points (Figure 9.9).

Source: AGP 2024.

 Figure 9.9: 2011 Bench Sampling Locations

9.1.4.4 July 2012 Highwall Backhoe Sampling

SPS collected 259 samples 10' apart on four pit wall benches as shown in Figure 9.10. The program design was developed at a meeting between Tetra Tech and SPS in 2012 (Bonsall, 2012b).


 

4454 Bench
4481 Bench


 

4520 Bench
4550 Bench

Source: SPS 2025

Figure 9.10: Shows the highwall backhoe sampling evidence on Bench 4520 viewed on the site visit in 2024.


 

Source: AGP 2024

Figure 9.11: Bench 4520 Highwall Backhoe Sampling

Metcon in Tucson completed the samples' assays using their method MA-ICP (Metcon, 2012). Duplicates, blanks, and standard reference material were included in the QAQC. The bench grade reported in Table 9.3 is from the AGP block model, and the backhoe sample grades are the average for the bench.

Table 9.3: August 2012 Highwall Backhoe Sampling
Compared with Block Model Bench Grade
Bench Backhoe Sample Cu% Bench Grade Cu %
4455 0.138 0.091
4480 0.172 0.090
4520 0.117 0.090
4545 0.117 0.092

Source: AGP 2024


 

9.1.4.5 2012 August, Deepcut Backhoe Highwall Sampling

Twenty-four sites were selected proximal to the July 2012 backhoe samples. Three types of samples were obtained to evaluate the grade correlation with distance to surface: a) 2 ft. into wall, b) 4 ft. into wall, and c) <6" into wall. The samples were shipped to Metcon in Tucson, AZ. The samples indicate higher grade mineralization at the surface (<6"). Overall, the grades are higher than the collocated block grades.

Table 9.4: August 2012 Backhoe Sampling Comparison
Bench Site ID %TCu 2' into
highwall
%TCu 4' into
highwall
%TCu Within
6"
%TCu Block
Model
4481 C2-1 0.105   0.165 0.100
4481 C4-1   0.122    
4481 C2-2 0.162     0.103
4481 C4-2   0.182    
4481 C2-3 0.138   0.161 0.099
4481 C4-3   0.160    
4454 C2-1 0.108   0.108 0.078
4454 C4-1   0.113    
4454 C2-2 0.098   0.11 0.071
4454 C4-2   0.118    
4454 C2-3 0.069   0.066 0.078
4454 C4-3   0.066    
4520 C2-1 0.097   0.187 0.092
4520 C4-1   0.110    
4520 C2-2 0.113   0.151 0.092
4520 C4-2   0.109    
4520 C2-3 0.073   0.179 0.095
4520 C4-3   0.095    
4550 C2-1 0.166   0.203 0.095
4550 C4-1   0.159    
4550 C2-2 0.113   0.146 0.091
4550 C4-2   0.106    
4550 C2-3 0.110   0.11 0.090
4550 C4-3   0.114    
Average   0.113 0.121 0.144 0.090

Source: AGP 2024

9.1.4.6 XRF of Wet Sonic Twin Holes

SPS conducted XRF copper analysis for 93 samples from three VLT sonic holes (VLT-12-002T, VLT-12-003T, and VLT-12-019T) in 2024. The results demonstrated a strong correlation (R2=0.9886) between XRF to lab analytical results. If three low-grade and two high-grade outliers (shown as solid red circles on Figure 9.12) are removed, the correlation slightly improves to R2=0.9946. XRF TCu% results averaged 5.5% greater than lab analytical results for the three holes tested.


 

Source: AGP 2025

Figure 9.12: XRF vs Lab Analytical Results for Three Wet Sonic Twin Holes

9.1.5 Adequacy of Data

On completion of the data verification process, it is the TMMA and IMC's opinion that the geological data collection, sampling, and QAQC procedures used by Lion CG at Yerington are consistent with accepted industry practices, and that the database is of suitable quality to support the mineral resource and reserve estimations.

It is TMMA's opinion that the data collection of historic data at Yerington by Lion CG is adequate for the use estimation for the following reasons:

  • sampling is representative of the deposit in both survey and geological context
  • twin holes and check assays have confirmed historical assays
  • drill hole cores have been archived and are available for further checking

 

9.2 MACARTHUR DEPOSIT

IMC conducted a site visit to the MacArthur Deposit and Lion CG's field office in Yerington, Nevada on February 14 and 15, 2022. During this visit Lion CG staff discussed the history of the Project, presented all requested data, answered questions posed by IMC, presented the current geologic interpretation of the MacArthur Deposit, and guided IMC on a field examination through the MacArthur Deposit. No drilling was in progress during IMC's site visit. The Lion CG staff reviewed all the Lion CG protocol related to drilling, sampling and sample chain of custody as part of IMC's site visit.

9.2.1 Historic Data Check

It is IMC's opinion that the previous owners of the MacArthur Deposit were competent, established companies that followed industry standard practices for drilling, sampling, and assaying according to the industry standards in place at the time of the work. IMC did not collect independent samples to corroborate historic data. Lion CG has completed verification work on the historic data by twin hole drilling.

IMC selected 17 Anaconda holes to compare the assays in the database with original assay certificates. IMC checked the total copper assays for each sample interval. There were no significant discrepancies noted between the database and certificates.

IMC selected 36 Lion CG holes which were drilled before 2012 and one hole drilled in 2021 to compare the assays in the database with original assay certificates. IMC checked the total copper assay and the acid soluble copper assay for each sample interval. For both the total copper assays and the acid soluble copper assays there were no significant discrepancies noted between the database and the certificates.

As a check on the historic Anaconda drilling within the confines of the current MacArthur pit, Lion CG twinned nineteen Anaconda holes using both RC and core drilling methods. Figure 9.13 confirms the correlation between the twin holes.


 

Source: IMC 2022

Figure 9.13: Twin Hole Comparison

9.2.2 2024 Drill Hole Collar Elevation Checks

The collar elevations were checked against the topography. Many of the holes drilled after QM-313 had a large difference (> 20 ft) between the topography elevation at the collar and the collar elevation assigned in the drill hole database. The collar elevation for these holes was based on a handheld GPS instrument versus a more precise measurement for earlier drilled holes. The topographic elevation was assigned as the collar elevation for holes drilled after QM-313.

9.2.3 Adequacy of Data

It is IMC's opinion that the data collection of both historic and modern data by Lion CG for the MacArthur Deposit is adequate for use in resource and reserve estimation for the following reasons:

  • The sampling is representative of the deposit in both survey and geological context
  • The drill hole cores, pulps, and coarse rejects have been archived and are available for further checking

 

10.0 MINERAL PROCESSING AND METALLURGICAL TESTING

10.1 INTRODUCTION

Copper mineralization at the Yerington Copper Project exhibits characteristics typical of deposits in the Western United States. The unique orientation of the mineralized zones and the existence of both the Yerington and MacArthur deposits allows for the potential to process oxide, transitional and sulfide copper ores simultaneously.

Recent advances in processing technology, particularly the NutonTM process, show improvements in recovering lower grade copper sulfide ores using bio-leaching technology without the need for flotation concentration and smelting. Modelling and associated test work confirm that copper recoveries up to 77% are achievable on primary Yerington sulfide ore using Nuton Technology.

Current test campaigns are optimizing Nuton Technology and evaluating synergies across flowsheets that incorporate heap leach processing of oxide, transitional and sulfide ore.

10.1.1 Nuton

In early 2022, Lion CG and Nuton LLC, a Rio Tinto venture, entered into an option to earn-in agreement that included the assessment of Nuton Technology on oxide, sulfide, and residual ore from Yerington and MacArthur.  Initial test work used historical drill core and fresh rock from both properties.

Results have demonstrated that Nuton Technology can effectively leach chalcopyrite-bearing ore from Yerington and achieve copper recoveries exceeding 70% in test work and modeling simulations.

10.2 COPPER RECOVERY PROJECTIONS

Metallurgical copper extraction and recovery estimates for the Yerington Copper Project are summarized in Table 10.1. These projections are based on metallurgical test campaigns and data from historical operations at the Yerington project site.

Table 10.1: Yerington Copper Project Projected Recoveries by Deposit/Ore Type/Process(1).
Deposit Feed Type Crush Size TCu
Extraction
TCu Recovery w/
Operational
Scale-up Factor
Net Acid
Consumption
(lb./t)
MacArthur Oxide: MacArthur ROM 64% 59% 20
Oxide: Gallagher ROM 54% 46% 42
Oxide: North Ridge ROM 55% 46% 38
Yerington Oxide ROM 74% 68% 15
Residual: VLT As Received 75% 69% 15
Primary Sulfide 0.4-in. p80 77% 73% 30

(1) Based on metallurgical test work campaigns


 

10.3 CURRENT METALLURGICAL TESTWORK PROGRAMS

10.3.1 YERINGTON METALLURGICAL TESTING

10.3.1.1 Yerington Sulfides - Nuton Phase 1

Initial mineralogy and geochemical analyses were conducted at the Rio Tinto's Bundoora Technology Development Centre in Australia. Results indicated a high probability of success in treating Yerington primary sulfide ore using Nuton Technology.

Collaboration between Lion CG and Nuton also revealed several opportunities for improving oxide and transitional ore recovery across both deposits through synergistic effects.  Nuton's process integrates column leaching using proprietary solutions involving bacteria and additives to optimize key performance attributes of the Yerington mineralization, including copper recovery, leach kinetics, and acid consumption.

The Nuton test work program for Yerington ore included the following six composites to demonstrate replicated metallurgical results:

1. Yerington Life of Asset Blend #1

 

4. Yerington East #2

2. S-23 Stockpile

 

5. Yerington West #2

3. Yerington Central #2

 

6. Yerington Life of Asset Blend #2


Table 10.2: Phase 1 Test Conditions and Summary Results
Samples Test Conditions Column Test KPI
Test ID Series pH Sulfur
Addition
Pyrite
Addition
Additives Days
Leaching
Cu Ext
(%)
NAC
(lb/ton)
LCG8 Yerington LoA Blend #1 1.5 No No 1, 4 & 5 228 41 47
LCG9 Yerington LoA Blend #1 1.5 No Yes 4 & 5 228 48 43
LCG10 Yerington LoA Blend #1 1.5 No Yes 1, 4 & 5 228 68 47
LCG11 Yerington LoA Blend #1 1.5 No Yes 2 452 77 88
LCG12 Yerington LoA Blend #1 1.5 No Yes 1 & 2 249 72 71
LCG13 Yerington LoA Blend #1 1.5/1.2 No Yes 1 & 2 452 79 167
LCG14 S-23 Stockpile 1.2 Yes No 1, & 2 249 78 121
LCG15 S-23 Stockpile 1.2/1.5 Yes No 1 & 2 186 57 101
LCG16 S-23 Stockpile 1.2 Yes No 1, 4 & 5 186 77 64
LCG17 S-23 Stockpile 1.2/1.5 No Yes 1 & 2 249 83 116
LCG21 S-23 Stockpile 1.2 No Yes 1 & 2 347 87 166
LCG18 Yerington Central #2 1.2 No Yes 1 & 2 179 79 118
LCG19 Yerington East #2 1.2 No Yes 1 & 2 179 76 116
LCG20 Yerington West #2 1.2 No Yes 1 & 2 179 82 116
LCG22 Yerington LoA Blend #2 1.2 No Yes 1 & 2 179 87 121
LCG23 Yerington LoA Blend #2 1.5 No No None 221 69 113
LCG24 Yerington LoA Blend #2 1.5 No Yes (A) None 221 73 36


 

Table 10.2: Phase 1 Test Conditions and Summary Results
Samples Test Conditions Column Test KPI
Test ID Series pH Sulfur
Addition
Pyrite
Addition
Additives Days
Leaching
Cu Ext
(%)
NAC
(lb/ton)

LCG25

Yerington LoA Blend #2

1.5

No

Yes (B)

None

221

69

48

10.3.2 Sample Selection and Preparation

Samples for Phase 1 test work composites were composed using historical drill core. Figure 10.1 below shows a plan view of the Yerington pit and all the sampled drill holes. Figure 10.2 below shows a section view of the drill holes with color coded sample points. The larger pink samples across the entire deposit were composited into the Life of Asset (LoA) Blend #1. The orange samples on the left side were composited into the West #2 composite. The blue samples in the center were composited into the Central #2 composite. The green samples on the right were composited into the East #2 composite.

Figure 10.1: Plan View of Yerington Phase 1 Samples


 

Figure 10.2: Section View of Yerington Phase 1 Samples

The mineralogical breakdown of the Phase 1 composites is shown in Table 10.3 and Table 10.4.

Table 10.3: Phase 1 Composites - Gangue Mineralogy
Gangue Minerals (%) Year 1 Yerington
LoA #1
S23
Blend
Yerington Central
#2
Yerington
East #2
Yerington
West #2
Pyrite 0.0 0.7 0.4 1.6 1.5 2.4
Biotite 1.4 0.9 0.9 0.8 1.5 1.2
Chlorite 3.4 3.6 4 3.4 3.7 2.7
Carbonates 0 0.6 0.5 0.8 0.9 0.6
Smectite 2.3 1.5 0.9 1.7 2.8 0.2
Kaolinite 0.1 0.1 0 0 0.1 0.1
Pyrophyllite 0 0.1 0 0.2 0.2 0
Quartz 25.5 34.2 33.2 30.9 26.2 36.8
Muscovite 5.4 12.7 12.6 12.4 5.2 17.7
Plagioclase Feldspar 45 30.3 32.8 35 40.9 23.4
K-Feldspar 2.8 6.7 6.4 3.8 6.2 9.7

Table 10.4: Phase 1 Composites - Copper Mineral Speciation
Gangue Minerals (%) Year 1 Yerington
LoA #1
S23
Blend
Yerington Central
#2
Yerington
East #2
Yerington
West #2
Chalcopyrite 0.1 92.8 82.6 86.8 85.2 96.6
Copper Arsenides 0.0 0.2 0.0 0.3 0.3 0.2
Bornite 0.0 4.7 7.1 9.8 11.1 0.6
Chalcocite 0.0 0.9 1.3 1.2 1.7 1.0
Covellite 0.0 0.0 0.6 0.0 0.0 0.0
Copper Oxides 33.6 0.1 0.4 0.2 0.1 0.1
Cu Clays 56.0 0.0 3.3 0.0 0.0 0.0
Other Cu Minerals 10.2 1.1 4.2 1.6 1.4 1.3
Total 100 100 100 100 100 100


 

10.3.3 S-23 Sulfide Stockpile

Testing of sulfide material from the S-23 stockpile using the Nuton Technology has been completed. Results based on a range of test conditions are summarized in Table 10.5, with corresponding leach rate and net acid consumption profile plots presented in Figure 10.3.

S-23 Sulfide stockpile is residual bulk material mined from the bottom of the Yerington pit and likely represents similar mineralization to material remaining in the Yerington pit.  There is currently no direct correlation of where S-23 material came from the pit.  S-23 material is not included in the resource or reserve estimate for The Project.

Data shows improved S-23 metallurgical performance by optimizing combinations of sulfur, pyrite, and proprietary Nuton additives. Phase 1results indicate that modeled copper extraction of 77% is achievable.

Results will inform optimization test work and provided design criteria for larger scale testing, process development and engineering design.

Table 10.5: Nuton Scoping Series - S-23 Sulfide Stockpile
S-23 Stockpile
Test ID
    Test Conditions   Column Test KPI
pH Sulfur
Addition
Pyrite
Addition
Additives Days
Leaching
Cu Ext (%) NAC
(lb/ton)
LCG14 1.2/1.5 Yes No 1, & 2 249 78 121
LCG15 1.2 Yes No 1 & 2 186 57 101
LCG16 1.2 Yes No 1, 4 & 5 186 77 64
LCG17 1.2/1.5 No Yes 1 & 2 249 83 116
LCG21 1.2 No Yes 1 & 2 347 87 166


 

Figure 10.3: Nuton Scoping Series - Yerington S-23 Stockpile Extraction and NAC vs. Leach Days

10.3.4 Life of Asset Blend #1

Drill core samples representing the Life of Asset production schedule were compiled into a composite called LoA Blend #1. Preliminary test data using this feed composite is shown in Table 10.6. The corresponding leach rate and net acid consumption profiles over time are displayed in Figure 10.4.

Test results on LoA Blend # 1 show copper extractions of up to 79% in a column test for the testing period. The column test results align with modeled heap extraction of 77%.  The results confirm projections and support further optimization of parameters such as pyrite addition and proprietary modifiers to incrementally improve kinetics and extraction.

The first phase testing on LoA Blend #1 was completed mid-2024. Test work results were used to model baseline criteria for prefeasibility assessments and design.


 

Table 10.6: Nuton Scoping Series - Yerington Life of Asset Blend #1
Yerington LoA Blend #1
Test ID
    Test Conditions   Column Test KPI
pH Sulfur
Addition
Pyrite
Addition
Additives Days
Leaching
Cu Ext
(%)
NAC
(lb/ton)
LCG8 1.5 No No 1, 4 & 5 228 41 47
LCG9 1.5 No Yes 4 & 5 228 48 43
LCG10 1.5 No Yes 1, 4 & 5 228 68 47
LCG11 1.5 No Yes 2 452 77 88
LCG12 1.5 No Yes 1 & 2 249 72 71
LCG13 1.5/1.2 No Yes 1 & 2 452 79 167

Figure 10.4: Nuton Scoping Series - Yerington LoA Blend #1 Extraction and NAC vs. Leach Days


 

10.3.5 Life of Asset Blend #2

A second Life of Asset blend was generated from additional drill core samples to provide confirmation and allow further optimization beyond the initial LoA test series. LoA Blend #2 along with the individual components (Yerington East #2, Central #2, and West #2) were tested using Nuton processing conditions and mass balanced results are summarized in Table 10.7 with copper extraction shown in Figure 10.5.

Data clearly shows enhanced performance in terms of copper recovery, leach kinetics, and acid consumption compared to previous testing. The results demonstrate continued opportunity for advancing operating parameters.

Table 10.7: Nuton Scoping Series - Yerington Life of Asset Blend #2
Yerington LoA
Blend #2
Test ID
    Test Conditions   Column Test KPI
pH Sulfur
Addition
Pyrite
Addition
Additives Days
Leaching
Cu Ext
(%)
NAC
(lb/ton)
LCG18 1.2 No Yes 1 & 2 179 79 118
LCG19 1.2 No Yes 1 & 2 179 76 116
LCG20 1.2 No Yes 1 & 2 179 82 116
LCG22 1.2 No Yes 1 & 2 179 87 121
LCG23 1.5 No No None 221 69 113
LCG24 1.5 No Yes None 221 73 36
LCG25 1.5 No Yes None 221 69 48


 

Figure 10.5: Nuton Scoping Series - Yerington East #2, Central #2, West #2, and LoA Blend #2 Cu Extraction and NAC vs. Leach Days

10.3.6 W-3 Stockpile

The W-3 stockpile consists of low-grade oxide and transition material below Anaconda's historical operating cut-off of 0.3% Cu, but above a 0.2% Cu lower limit. The copper oxide mineralization includes chrysocolla, neotocite and other secondary minerals along with some chalcocite.

Detailed modern geo-metallurgical analysis has not yet been conducted on W-3 material. Column testing is proposed to quantify potential performance. Until then, assumptions rely on 232 sonic drill samples analyzed for total copper (TCu), acid soluble copper (ASCu), sequential copper (SEQCu) and acid consumption.

Preliminary indications are that acid soluble copper assays (ASCu) combined with cyanide soluble copper assays (CNCu) provide reasonable estimates for copper recovery through conventional heap leaching. Recent analytical improvements provide more textural context to interpret release dynamics versus older empirical factors.


 

As shown in Figure 10.6, total copper assays (TCu) for W-3 range from 0.02% to 1.9%, averaging 0.15% with a median grade of 0.14% TCu. Targeted column work can validate copper recovery projections at relevant crush sizes and reagent conditions.

Figure 10.6: W-3 Stockpile Total Copper Assay

Figure 10.7 displays the acid soluble copper component from W-3 sequential analyses. The ASCu levels ranged from <0.01% to 0.34% across all samples. The dataset shows mean values of 0.07% (720 ppm) ASCu and a median of 0.05% (518ppm) ASCu.


 

Figure 10.7: W-3 Stockpile Acid Soluble Copper Component

Figure 10.8 shows the cyanide soluble copper component from W-3 sequential analyses. CNCuSeq levels ranged from below detection limit to 0.17% (1746 ppm) CNCu, reflecting the dominantly oxide nature of the material, with a mean value of 0.07% (720 ppm) CNCu. This indicates low levels of transition copper mineralization present in the W-3 oxide material.

Figure 10.8: W-3 Stockpile Cyanide Soluble Copper Component


 

Figure 10.9 shows estimated recoverable copper content as a percentage of total copper based on W-3 sequential analyses. The recoverable copper ranges between 3.1% and 92.8 % of the TCu content, with Mean and Median 44.9 % and 43.2 %, respectively.

Figure 10.9: W-3 Stockpile Recoverable Copper Component

A bench analytical method was utilized to estimate acid consumption of W-3 oxide material. Results were scaled to forecast consumption rates under commercial heap leach conditions.

Figure 10.10 presents statistical analysis of the projected acid addition requirements across all W-3 samples. Total net acid consumption levels ranged from 0 to 175 lb/ton, with an average of 23 lb/ton and a comparable median value of 20 lb/ton.

Figure 10.10: W-3 Stockpile Acid Consumption


 

 

10.3.7 Vat Leach Tailings Stockpile

Residual copper remains in the legacy VLT stockpile from inefficient copper extraction during the original Anaconda processing. The residual copper mineralization was identified across the 270 samples taken during recent sonic drilling.

Assay statistics indicate median VLT feed grades of 0.089% TCu and 0.051% ASCu based on global composite samples. The average ASCu:TCu ratio equals 51%.

Grade distribution plots for VLT samples are displayed in Figure 10.11 (TCu), Figure 10.12 (ASCu), and Figure 10.13 (ASCu:TCu ratio). These initial results suggest meaningful recoverable copper persists in unrealized portions of the stockpile.

Figure 10.11: VLT Stockpile Total Copper

Figure 10.12: VLT Acid Soluble Copper


 

Figure 10.13: VLT Acid Soluble Copper to Total Copper

To estimate overall recoverable copper, 48 VLT samples were randomly selected across grade distributions for expanded analysis using thresholds (0.06% TCu cut-off) matching prospective heap leach feed. These specimens underwent total copper (TCu) assays along with testing by a ferric sulfate acid leach method (SAPCu).

The SAPCu technique approximates recoverable copper levels under simulated heap conditions using a ferric lixiviant. Results are summarized in Table 10.8. Based on SAPCu/TCu ratios, average VLT copper recovery is projected at 65%.

Table 10.8: SAPCu Test Results for VLT Test Samples
Analytical
Method
Mean Std. Dev Min Max Median
TCu (%) 0.11 0.03 0.06 0.17 0.11
SAPCu (%) 0.007 0.02 0.03 0.14 0.07
SAPCu:TCu 65.04% 12.60% 40.87% 95.25% 62.32%

Figure 10.14 displays these data ratios providing a preliminary proxy for acid-based extraction performance. While useful for initial forecasting, demonstrating actual metallurgical response requires bench and column testing using the proposed comminution and leaching parameters.


 

Figure 10.14: VLT SAPCu to Total Copper

Initial bottle roll analysis to estimate VLT acid consumption suggests net acid demand averaging 15 lb./ton ore.

10.3.8 Yerington Sulfides - Nuton Phase 2

The Nuton Phase 2 two test work program was performed on a 2.2-ton master composite sample collected from across the deposit to simulate an additional life of asset composite. All Phase 2 column test work utilized the feed stock, with the program testing a range of operating parameters to determine the operating window.

Testwork is currently underway using a series of 1-meter-tall columns (LCG26-LCG42) for bench-scale evaluations, alongside a single 10-meter-tall column (LCGT1) designed to simulate full-scale heap leaching conditions.

The 10-meter-tall column test is used to simulate the heap leaching conditions at pilot scale.  The tall column replicates a vertical 10-meter profile.  It enables assessment of the leach kinetics, reagent consumption, permeability, and leach extraction estimation.

The mineralogical breakdown of the Phase 2 composite is shown in Table 10.9 and Table 10.10. Table 10.11 shows the test conditions for all Phase 2 test columns, including the status of the columns, and test results. Final results will inform the feasibility study design criteria and provide additional extraction parameters to refine the copper extraction model.


 

Table 10.9: Phase 2 Optimization Composite Gangue Mineralogy
Gangue Minerals (%) Phase 2 Optimization
Pyrite 0.5
Biotite 2.0
Chlorite 4.0
Carbonates 1.2
Smectite 1.5
Kaolinite 0.6
Pyrophyllite 0.0
Quartz 30.4
Muscovite 12.0
Plagioclase Feldspar 33.0
K-Feldspar 7.7

Table 10.10: Phase 2 Optimization Composite Copper Mineral Speciation
Cu Minerals (%) Phase 2 Optimization
Chalcopyrite 93.3
Copper Arsenides 0.0
Bornite 2.9
Chalcocite 1.4
Covellite 0.0
Copper Oxides 0.2
Cu Clays 1.3
Other Cu Minerals 1.0
Total 100.0


 

Table 10.11: Nuton Phase 2 Optimization KPIs (1)
Samples Test Conditions Column Test KPI
Test ID Status Temp
(°C)
pH Pyrite
Addition
Additives P100 (mm) Days
Leaching
Cu Ext
(%)
Fe Ext
(%)
NAC
(lb/ton)
LCG26 Complete / Sacrificial 60 1.5 Yes 1 + 2 12.5 60 35.4 1.9 45.7
LCG27 Complete / Sacrificial 60 1.5 Yes 1 + 2 19 60 36.5 4.3 57.9
LCG28 Complete / Sacrificial 60 1.5 Yes 1 + 2 19 60 46.6 6.8 52.9
LCG29 Complete 60 1.5 Yes 1 12.5 298 76.1 9.9 107.0
LCG30 Complete 70 1.5 Yes 1 + 2 12.5 298 74.0 -3.6 104.1
LCG31 Complete 60 1.8 Yes 1 + 2 12.5 298 80.9 -6.8 39.5
LCG32 On-going 60 1.5 Yes 1 + 2 12.5 357 70.4 0.8 104.1
LCG33 Complete 60 1.5 Yes 1 + 2 19 298 61.3 8.0 91.6
LCG34 Complete 60 1.5 Yes 1 + 2 19 298 69.3 10.4 76.8
LCG35 On-going 20 - 60 1.5 Yes 1 + 2 12.5 378 73.1 8.7 80.0
LCG36 Complete 60 1.5 Yes 2 12.5 297 75.3 4.9 94.8
LCG37 Complete 50 1.5 Yes 1 + 2 12.5 297 57.9 21.4 90.3
LCG38 Complete 60 1.5 Yes 1 + 2 12.5 298 78.4 14.9 108.5
LCG39 Complete 60 1.5 Yes 1 + 2 12.5 298 70.5 -6.2 107.4
LCG40 Complete 60 1.5 Yes 1 + 2 12.5 298 70.7 -1.6 102.6
LCG41 On-going 20 - 60 1.5 Yes 3 12.5 364 78.4 3.9 83.1
LCG42 On-going 60 1.5 Yes - 12.5 210 68.7 15.4 113.0
LCLLCT1 Eliminated Leach load test on coarse oxide for heap leach hydrodynamics
LCLLCT2 Complete 60 1.5 Yes 1 + 2 12.5 210 75.4 27.1 102.7
LCLLCT3 Complete 60 1.5 Yes 1 + 2 19 224 65.0 -2.5 93.1
LCGT1 On-going 20 - 60 1.5 Yes 1 + 2 12.5 372 75.5 2.4 48.0

(1) Column testing is underway and residue assay and mineralogy data will be used to complete final mass balances


 

10.3.9 Sample Selection and Preparation

Samples for creating the Phase 2 test work composites utilized samples from core drilled in 2017 and 2021. Figure 10.15 below shows the plan view of the Yerington pit identifying all the drill holes sampled. Figure 10.16 below is the section view of the drill holes with color coded sample points.

Figure 10.15: Plan View of Yerington Phase 2 Samples

Figure 10.16: Section View of Yerington Phase 2 Samples


 

10.3.10 Nuton Phase 2 Test Work Results

Copper extraction for Phase 2 tests average 72% with extractions to date ranging from 81% to 58%. The variance in results is expected given the variation in test conditions and operating parameters. Similar variation is observed in net acid consumption.

Copper extraction in the temperature ramped 10-meter-tall column (LCGT1) was calculated at 75.5% after 372 days of leaching.  The column leach test is on-going and will complete with final residue assays in Q4 2025.

Results from Phase 2 will be used to further calibrate the Nuton Technology copper extraction model in preparation for a future feasibility study.

Figure 10.17: Nuton Technology Copper Extraction and Net Acid Consumption Phase 2 Test


 

10.3.11 Nuton Technology Copper Extraction Modeling

The Nuton Technology copper extraction model utilizes copper mineral extractions rates from the mass balanced column data from Phase 1.  It uses mineral reaction extents to predict the overall copper extraction. The figures below for Yerington Central #2 (Figure 10.18), East #2 (Figure 10.19), and West #2 (Figure 10.20) composites show the actual column recoveries in red dots and the predicted model recovery represented with the thick blue line. The actual results of the columns align well with the predictive recovery model for the Central #2 and West #2 composites and the actual recovery for the Yerington east model was approximately five percent lower than the model predictions.

Figure 10.18: Yerington Central Nuton Composite Actual Column Results vs Predictive Extraction Model (LCG18)

Figure 10.19: Yerington East Nuton Composite Actual Column Results vs Predictive Extraction Model (LCG19)


 

Figure 10.20: Yerington West Nuton Composite Actual Column Results vs Predictive Extraction Model (LCG20)

The Nuton predictive copper extraction model will be used to determine a final copper extraction for Yerington sulfide ore. The model indicates an average copper extraction of 77% and scale-up factor of 95% is applied with a final copper recovery rate of 73%. The 95% scale-up factor is standard for sub one-inch crushed heap leach pads with minimal clay as referenced by Marsden and Botz, Heap leach modeling, a review of approaches to metal production forecasting.

10.3.12 Hydrodynamic Testing

Hydrodynamic testing was performed on Phase 1 and Phase 2 composites. Figure 10.21 through Figure 10.24 below indicates that air and hydraulic conductivity is adequate for copper extraction. Extraction occurs in three benches or between 0 and 30m of heap height. Figure 10.25 show the Phase 2 composite porosity results and Figure 10.26 contains the dry bulk density of the phase 2 composite at increasing heap height.

Figure 10.21: Phase 1 Yerington LoA Blend Hydraulic and Air Conductivity


 

Figure 10.22: Phase 1 LoA Blend Dry Bulk Density and Total Porosity

Figure 10.23: Phase 2 LoA Blend Air Conductivity

Figure 10.24: Phase 2 LoA Blend Hydraulic Conductivity


 

Figure 10.25: Phase 2 LoA Blend Total Porosity

Figure 10.26: Phase 2 LoA Blend Dry Bulk Density

10.4 YERINGTON OXIDE MATERIALS

A surface core drilling campaign was executed in 2024 to provide recent material for metallurgical testing to supplement the historic test work. The 2024 test included verifying recovery projections benchmarked from past production and quantifying potential synergies with Nuton processing.

Anaconda historically operated a vat leach plant at Yerington to process in-situ oxide ore , which has been well documented over the years.

10.4.1 YERINGTON BASELINE COLUMN TESTING: MCCLELLAND LABORATORIES 2024

The column test work program for oxide and transition ore contained in the Yerington pit was intended to verify historic recovery projections. Three oxide composites were constructed to align with the slight differences in geologic alterations observed between the pit's east, central, and west zones. Two transition composites were constructed for the central and west zones. The transition composites were leached using a traditional acid leach procedure, but in operation, the transition ore would be processed with the sulfide ore through the Nuton process.


 

The sequential copper distribution is detailed in Figure 10.27. Final copper recoveries are summarized in Figure 10.28. Kinetic column extractions are outlined in Figure 10.29. The calculated copper head grades are detailed in Figure 10.30. The average acid consumption results for the column test work program are summarized in Figure 10.31, Figure 10.32, and Figure 10.33.

The oxide composites leached well, with a final extraction range of 70-87%. The west and central oxide samples averaged 20 lb./ton gross acid consumption, but the east oxide was 90 lb./ton. Further mineralogical testing is ongoing to determine the root cause of high acid consumption.

Figure 10.27: Yerington 2024 Composites Sequential Assay Results and Copper Distribution by Sequential Assays


 

Figure 10.28: Yerington 2024 Copper Extraction Summary

Figure 10.29: Yerington 2024 Copper Extraction Kinetic Leach Results


 

Figure 10.30: Yerington 2024 Calculated Copper Head Grade Summary

Figure 10.31: Yerington 2024 Gross Acid Consumption Summary


 

Figure 10.32: Yerington 2024 Net Acid Consumption Summary

Figure 10.33: Yerington 2024 Specific Acid Consumption Summary


 

10.5 MACARTHUR METALLURGICAL TESTING

The MacArthur copper mineralization has an extensive metallurgical testing history spanning numerous operators over multiple decades:

  • Anaconda (1976): Bottle roll and column testing on surface trench material
  • Arimetco (1989-1995): Heap leached copper from newly mined oxide and transition material from the MacArthur pit
  • Arimetco (1992-1995): Various bottle and column leach tests using multiple external labs on surface samples
  • Quaterra (2010-2011): Bottle roll and column analysis performed at METCON in Arizona
  • Lion CG (2020-2023): Recent column testing programs on drill core at McClelland Laboratories in Nevada. Samples covered the MacArthur, North, Ridge, and Gallagher deposit areas

10.5.1 2011 METCON METALLURGICAL TEST WORK: MACARTHUR

METCON's 2011 analysis on MacArthur used drill core samples spanning deposit zones rather than analog surface trenches as in prior eras. Material representing 32 holes was compiled into column test charges. Results showed column extractions ranging from 42 to 87% and a straight test work campaign average of 60%. Acid consumption was variable, ranging from 29 to 113 lb/ton.

One composite failed mid-test due to high localized clay content, originally presumed to be caliche.  However, a review found the core intercepted a fault zone rather than caliche. This clay occurrence appears restricted, with minimal regional dissemination.

Excluding the failed column, 31 working columns provide a performance baseline. Generally, the existing MacArthur pit domains returned higher median recoveries of around 80% and lower acid consumptions than North MacArthur, Gallagher, or Northern zones.


 

Table 10.12 summarizes pertinent column feed data, including deposit location, source hole ID, test intervals, and critical output metrics for each specimen. The following figures present statistics across the combined global column dataset.

Table 10.12: 2011 METCON Metallurgical Test Work Program Summary
Column Test ID Deposit DHID From To Leach Days   Copper Grades     Gangue Acid Consumption
TCu (%) ASCu (%) CNCu (%) Residual Cu (%) Cu Extraction (%) (kg/tonne) (lb./ton)
CL-01 Gallagher PQ-11-QM-139 80 140 120 0.166 0.07 0.016 0.092 51.21 46.32 92.64
CL-02 Gallagher PQ-11-QM-106 0 30 120 0.335 0.208 0.015 0.096 72.69 56.64 113.28
CL-03 Gallagher PQ-11-QM-90 Part 1 0 70 120 0.125 0.037 0.005 0.078 41.97 43.22 86.44
CL-04 Gallagher PQ-11-QM-90 Part 2 80 130 120 0.363 0.108 0.203 0.051 56.43 22.78 45.56
CL-05 Gallagher PQ-11-QM-038 35 175 120 0.122 0.049 0.032 0.050 48.66 35.63 71.26
CL-06 Gallagher PQ-11-QM-035 15 90 120 0.168 0.054 0.01 0.095 48.01 34.38 68.76
CL-07 Gallagher PQ-11-QM-037 15 70 120 0.220 0.068 0.007 0.110 52.26 34.88 69.76
CL-08 Other PQ-11-QM-144 115 225 120 0.144 0.049 0.023 0.053 56.21 28.13 56.26
CL-09 MacArthur Pit Area PQ-11-QM-145 0 50 120 0.113 0.062 0.005 0.041 58.73 17.76 35.52
CL-10 MacArthur Pit Area PQ-11-QM-119 30 80 0 0.145 0.092 0.008 0.041 N/A  N/A N/A
CL-11 MacArthur Pit Area PQ-11-QMT-1 0 145 120 0.311 0.183 0.007 0.064 59.08 20.80 41.60
CL-12 MacArthur Pit Area PQ-11-QME-3 72.5 118 120 0.145 0.084 0.004 0.057 61.97 19.74 39.48
CL-13 MacArthur Pit Area PQ-11-QMT-9 13 91.1 120 0.575 0.453 0.012 0.046 80.86 22.01 44.02
CL-14 MacArthur Pit Area PQ-11-QM-083 100 170 120 0.170 0.105 0.008 0.045 69.57 24.75 49.50
CL-15 MacArthur Pit Area PQ-11-QMT-14 Part 1 5 17 120 0.207 0.14 0.004 0.035 87.15 14.38 28.76
CL-16 MacArthur Pit Area PQ-11-QMT-14 Part 2 36.2 118 120 0.376 0.32 0.012 0.052 87.16 25.15 50.30
CL-17 MacArthur Pit Area PQ-11-QMT-15 Part 1 12.5 118 120 0.271 0.207 0.005 0.049 84.44 27.40 54.80
CL-18 MacArthur Pit Area PQ-11-QMT-15 Part 2 118 180 120 0.089 0.068 0.003 0.023 80.29 20.70 41.40
CL-19 MacArthur Pit Area PQ-11-QMT-17 Part 1 52 94.7 120 0.093 0.03 0.007 0.056 47.56 32.30 64.60
CL-20 MacArthur Pit Area PQ-11-QMT-17 Part 2 99 154 120 0.264 0.19 0.008 0.020 79.90 31.31 62.62
CL-21 North Ridge PQ-11-QM-095 95 140 120 0.105 0.05 0.026 0.041 69.02 34.92 69.84
CL-22 North Ridge PQ-11-QMT-6 33 128 120 0.154 0.049 0.100 0.099 44.28 26.54 53.08
CL-23 North Ridge PQ-11-QM-020 40 180 120 0.092 0.044 0.006 0.052 61.38 27.49 54.98
CL-24 North Ridge PQ-11-QM-029 10 70 120 0.271 0.128 0.012 0.146 60.99 48.42 96.84
CL-25 North Ridge PQ-11-QMCC-1 Part 1 71.5 119 120 0.126 0.047 0.009 0.073 51.81 17.34 34.68
CL-26 North Ridge PQ-11-QMCC-1 Part 2 119 149 120 0.135 0.069 0.022 0.041 55.53 19.20 38.40
CL-27 North Ridge PQ-11-QMCC-11 94 194 120 0.146 0.087 0.012 0.051 57.12 22.80 45.60
CL-28 North Ridge PQ-11-QMCC-13 Part 1 7 62 120 0.186 0.113 0.011 0.066 62.53 22.01 44.02
CL-29 North Ridge PQ-11-QMCC-13 Part 2 63 114 120 0.142 0.029 0.002 0.085 49.31 23.64 47.28
CL-30 North Ridge PQ-11-QM-080 0 100 120 0.33 0.182 0.011 0.136 50.56 23.76 47.52
CL-31 North Ridge PQ-11-QMCC-14 21 88 120 0.06 0.017 0.006 0.031 30.89 22.41 44.82
CL-32 North Ridge PQ-11-QM-055 0 90 120 0.067 0.027 0.005 0.047 50.51 45.60 91.20


 

Figure 10.34 shows calculated total copper head grade statistics for the 31 successful METCON columns. Copper assays ranged from 0.086% TCu to 0.64% across all samples, with median grades of 0.155% TCu and a comparable mean of 0.191%.

Highlighted histogram regions indicate columns returning less than 60% copper recovery. The leftmost bar chart displays potential outliers, while the rightmost shows grade distribution quintiles.

Initial review suggests recovery shortfalls in lower grade ranges, pointing to opportunities for optimization.  However, applied testing is needed to systematically refine performance by geo-domain using fresh drill core intersects. Note that the two bar charts below represent the "Outlier" and "Quantile", from left to right.

Figure 10.34: METCON 2011 copper head grade summary statistics

Figure 10.35 presents copper recovery statistics for the 31 METCON columns using calculated head grades. Recoveries ranged from 30.9% to 87.2%, averaging 57.1% overall with a comparable median of 60.2%.

The chart also graphs recovery versus the ASCu+CNCu to TCu ratio. This shows strong correlation to TCu extraction by acid leaching, providing a useful predictive proxy. It is expected that using the Nuton raffinate would improve overall Cu recovery from the MacArthur oxide ore by 10% based on initial projections, pending confirmation through further studies.

Review of sequential copper analysis trends indicates transition zones and fresh sulfide bearing ore generally returned lower extractions. As expected, composites richer in acid soluble oxides and secondary copper minerals achieved higher and faster copper liberation.

Specimens from the existing MacArthur pit returned the best median recovery at 80%, reflecting a higher proportion of readily soluble mineralization. Geo-domain performance aligns with the oxidation and enrichment profile.


 

Figure 10.35: METCON 2011 Head Grade, Recoverable Copper, Copper Extraction, and Median Copper Sequential Distribution Results for 31 METCON Columns

Figure 10.36 shows overall copper extraction statistics across the 31 METCON columns.  Highlighted regions indicate tests returning less than 60% recovery.  After 120 days of leaching, copper extractions ranged from 30.9% to 87.2%, with median and average values of 57.1% and 57.2%, respectively.

It is important to note the METCON results reflect a simplified acid-only leach scheme on composite samples.  The presence of primary and secondary copper minerals clearly impacted extraction.

The scale-up factors applied to the Gallagher and North Ridge have been adjusted to 84% vs the 92% applied to MacArthur Pit Oxide and Yerington Oxide.  A lower scale-up factor has been applied due to higher occurrence of residual coppers with limited definition in the block model to apply copper extraction models that soluble copper (CuSOL) or residual copper (CuRES) factors.  Additionally, the standard deviation of column extractions for the Gallagher and North Ridge samples tested was ± 9%.


 

Figure 10.36: METCON 2011 Copper Extraction Summary

Figure 10.37 displays copper leach rate profiles over time for the 2011 METCON column tests. Recoveries use calculated head grades as bases.  Significantly, most columns still showed measurable copper extraction at the end of the 120-day primary leach cycle.

While PLS grades may not economically justify extended leaching in a single lift, results suggest high likelihood for additional recovery through secondary leach cycles in a multi-lift heap configuration.  Adjusting lixiviant application rates can also improve PLS quality and moderate acid consumption during initial and future lifts.


 

Figure 10.37: METCON 2011 Kinetic Copper Extraction Column Results

Figure 10.38 summarizes acid consumption statistics across the 31 METCON columns. Total consumption ranged from 14.8 to 56.6 kg/tonne acid per tonne of feed. The median acid demand equaled 25.5 kg/tonne, with a comparable average of 28.8 kg/tonne.

Notably, acid cure additions represented approximately 50% of overall acid volumes. The overdosing suggests opportunities to optimize initial cure rates for reduced acid costs.


 

Figure 10.38: METCON 2011 gangue (net) acid consumption summary statistics

10.5.2 McClelland Laboratories Test Work: MacArthur 2022

METCON's column test composites were compiled based on deposit zones rather than rock types, as detailed geo-metallurgical data were unavailable.  Discussion here focuses on critical leach performance factors for process design.

In 2022, McClelland Laboratories received core from 13 MacArthur holes to generate 6 column composites spatially representing Year 0 through Year 5 planned mining sequences. Grade continuity challenges prevented preparing distinct Year 2 and 3 specimens, so a combined composite for Years 2 and 3 was prepared.

This test work assumed standalone heap leach operations on ROM ore at MacArthur. Crushing aimed to replicate a nominal 6 in. top size for average ROM conditions. Results are summarized in Table 10.13 on the 5 columns. Leach cycles ranged from 139-164 days duration.  Calculated head grades spanned 0.133-0.331% TCu. Final copper extractions varied from 51.1% to 75.8%, with total net acid consumptions of 40.6 lb./ton and 60.1 lb/ton (20.3-30.0 kg/tonne).

Table 10.13: MacArthur 2022 Test Work Results Summary
MLI
Test #
Composite Leach/Rinse
Time, Days
Cu
Extraction,
%TCu
Assays % Cu H2SO4 Consumption
Extracted Tail Calc'd.
Head
Avg.
Head
Gross,
lb./ton ore
Net,
lb./ton ore
Specific (Net),
lb./lb. Cu
CL-1 Year 0 139 68.5 0.148 0.068 0.216 0.210 41.22 36.66 12.39
CL-2 Year 1 164 75.8 0.251 0.080 0.331 0.335 60.11 52.37 10.42
CL-3 Year 2/3 139 51.1 0.068 0.065 0.133 0.131 41.72 39.64 29.32
CL-4 Year 4 164 48.4 0.093 0.099 0.192 0.193 40.06 37.21 20.10
CL-5 Year 5 164 66.1 0.111 0.057 0.174 0.0993 43.22 39.81 17.99


 

Figure 10.39 displays MLI column leach rate curves over time. Copper continued extracting upon test conclusion, indicating additional recovery potential. Lower relative extractions for CL-3 (Years 2&3) and CL-4(Year 4) columns likely reflect higher proportions of transitional copper minerals.

As with prior datasets, results show copper leach sustaining beyond 120 days, suggesting an opportunity to enhance ultimate recovery through secondary leaching cycles.

Figure 10.39: MacArthur 2022 Kinetic Column Leach Rate Data, McClelland 2022

10.5.3 McClelland Laboratories Test Work: MacArthur 2024

The Macarthur 2024 test work program utilized a clustering analysis to generate bulk composites as opposed to previous test work programs where the composites were compiled based on deposit zones rather than rock types. The head grades, copper distribution, copper extraction, and acid consumption results from the METCON 2011 test work program were statistically analyzed with a clustering analysis. The clustering analysis coalesced on four main clusters primarily driven by the sequential copper in the head assays. Three clusters differed by low, medium, and high acid solubility and were all contained in the main MacArthur pit. A fourth cluster with large secondary copper component and clustered samples from the North Ridge pit. The clustering composites were created with untested material to match the clustering algorithms. The clustering analysis results are contained in Figure 10.40.


 

Figure 10.40: MacArthur 2024 Composite Clustering Analysis Outputs


 

The sequential copper distribution is detailed in Figure 10.41. Final copper recoveries are summarized in Figure 10.42. Kinetic column extractions are summarized in Figure 10.43. The calculated copper head grades are detailed in Figure 10.44. The average acid consumption results for the column test work program are summarized in Figure 10.45 and Figure 10.46.

Figure 10.41: MacArthur 2024 Composites Sequential Assay Results and Copper Distribution by Sequential Assays, McClelland 2024


 

Figure 10.42: MacArthur 2024 Copper Extraction Summary, McClelland 2024

Figure 10.43: MacArthur 2024 Kinetic Column Copper Extraction Results, McClelland 2024


 

Figure 10.44: MacArthur 2024 Calculated Copper Head Grade Summary, McClelland 2024

Figure 10.45: MacArthur 2024 Gross Acid Consumption Summary, McClelland 2024


 

Figure 10.46: MacArthur 2024 Net Acid Consumption Summary, McClelland 2024

10.5.4 Oxide Extraction Column vs ROM

All oxide column test work has been performed in columns with material P100 less than one and half inches. The column head sample and residue samples were assayed by size fraction to calculate copper extraction for each size fraction. The average extraction by size fraction for all MacArthur composites from McClelland test work in 2022 and 2024 is contained in Table 10.14. The average extraction by size fraction for all Yerington composites from McClelland 2024 test work program is contained in Table 10.15.

Table 10.14: Average MacArthur Assay by Size Fraction Results from
McClelland 2022 and 2024 Test Work Programs
  AVERAGE - MacARTHUR Composites  
Size CuT CuT CuAS CuSOL
Fraction Hd % Ext % Ext % Ext %
+1 1/2 - 3" 0.164 45% 61% 47%
-1 1/2 +1" 0.159 46% 71% 54%
-1 +3/4" 0.166 54% 81% 68%
-3/4+1/2" 0.173 61% 85% 75%
-1/2+1/4" 0.241 68% 91% 82%
-1/4"+6M 0.196 71% 92% 86%
-6+10M 0.214 72% 93% 87%
-10+20M 0.232 72% 93% 87%
-20+28M 0.256 72% 93% 87%
-28+65M 0.329 70% 94% 86%


 

Table 10.14: Average MacArthur Assay by Size Fraction Results from
McClelland 2022 and 2024 Test Work Programs
-65+100M 0.412 68% 94% 86%
-100+150M 0.430 68% 94% 86%
-150+200M 0.511 67% 94% 86%
-200M 0.749 63% 92% 84%
Overall Extraction 0.200 60% 85% 75%

Table 10.15: Average Yerington assay by size fraction results from
McClelland 2024 test work program
  AVERAGE - YERINGTON Composites  
Size CuT CuT CuAS CuSOL
Fraction Hd % Ext % Ext % Ext %
+3/4" 0.186 71% 78% 76%
-3/4+1/2" 0.220 77% 88% 86%
-1/2+1/4" 0.240 82% 93% 90%
-1/4"+6M 0.269 88% 97% 95%
-6+10M 0.307 88% 98% 96%
-10+20M 0.336 89% 98% 96%
-20+28M 0.397 89% 98% 96%
-28+65M 0.425 88% 98% 96%
-65+100M 0.471 88% 98% 96%
-100+150M 0.491 87% 97% 95%
-150+200M 0.484 86% 98% 96%
-200M 0.707 81% 97% 94%
Overall Extraction 0.245 76% 87% 84%

Scaling the ROM extraction requires least sum squared error (LSE) balancing of the modeled ROM blast fragmentation size distribution and the copper grade distribution showing in Table 10.14 and Table 10.15. The modeled ROM fragmentation is shown in Table 10.16.

Table 10.16: KUZ-RAM modeled
ROM fragmentation size distribution
KUZ-RAM ROM Fragmentation Curve
-24+18" 0.3%
-18+12" 1.2%
-12+8" 4.5%
-8+6" 6.0%
-6+4" 7.0%
-4+2" 9.0%
-2+1" 11.0%
-1+3/4" 10.5%


 

Table 10.16: KUZ-RAM modeled
ROM fragmentation size distribution
KUZ-RAM ROM Fragmentation Curve
-3/4+1/2" 9.0%
-1/2"+1/4" 8.0%
-1/4"+10M 6.5%
-10+35M 6.5%
-35+65M 6.5%
-65+100M 5.0%
-100+200M 4.0%
-200M 5.0%

The copper grade distribution of MacArthur and Yerington are shown in Figure 10.47 and Figure 10.48 respectively. The copper grade distribution is the ratio of the copper assay of the given size fraction divided by the total copper head grade. The copper grade distribution for both deposits indicated an increasing copper concentration with decreasing size.

Figure 10.47: MacArthur Total Copper Grade Distribution for the Average Head Samples


 

Figure 10.48: Yerington Total Copper Grade Distribution for the average Head Samples

The LSE balance is used to correct the fragmentation curve and the copper grade distribution curve to ensure the total copper distribution (sum product of each size fraction multiplied by the size fraction grade distribution) does not exceed 1. The ROM ore distribution and balanced copper grade distribution are multiplied against the extraction by particle size model contained in Figure 10.49 and Figure 10.50.

Figure 10.49: MacArthur Oxide Extraction by Particle Size for Sequential Copper Sizes


 

 

Figure 10.50: Yerington Oxide Extraction by Particle Size for Sequential Copper Sizes

Table 10.17: MacArthur Oxide Extraction Model Extrapolation for ROM Fragmentation
  % Size Dist Grade Dist % Ext Pred. ROM Ext
-24+18" 0.003 0.404 0.0% 0.0000
-18+12" 0.012 0.439 0.0% 0.0000
-12+8" 0.057 0.481 0.0% 0.0000
-8+6" 0.079 0.512 0.0% 0.0000
-6+4" 0.093 0.586 0.0% 0.0000
-4+2" 0.108 0.688 32.4% 0.0241
-2+1" 0.125 0.811 51.2% 0.0518
-1+3/4" 0.116 0.856 55.7% 0.0551
-3/4+1/2" 0.091 0.919 60.6% 0.0507
-1/2"+1/4" 0.071 1.051 65.3% 0.0488
-1/4"+10M 0.057 1.329 68.5% 0.0516
-10+35M 0.053 1.792 69.6% 0.0656
-35+65M 0.042 2.132 69.9% 0.0629
-65+100M 0.031 2.252 69.9% 0.0494
-100+200M 0.032 2.623 70.0% 0.0582
-200M 0.032 3.066 70.0% 0.0688
  Pred. ROM Extraction 0.587
  ROM Ext. + uplift from 160 to 360 days 0.640
  92% Scale-up Factor 0.589


 

Table 10.18: Yerington Oxide Extraction Model Extrapolation for ROM Fragmentation
  % Size Dist Grade Dist % Ext Pred. ROM Ext
-24+18" 0.003 0.355 0.0% 0.0000
-18+12" 0.011 0.389 0.0% 0.0000
-12+8" 0.048 0.452 0.0% 0.0000
-8+6" 0.060 0.493 0.0% 0.0000
-6+4" 0.088 0.561 4.4% 0.0022
-4+2" 0.106 0.668 46.0% 0.0326
-2+1" 0.128 0.806 66.8% 0.0691
-1+3/4" 0.119 0.842 71.8% 0.0722
-3/4+1/2" 0.094 0.874 77.2% 0.0633
-1/2"+1/4" 0.074 0.965 82.4% 0.0588
-1/4"+10M 0.060 1.185 86.0% 0.0613
-10+35M 0.058 1.586 87.2% 0.0804
-35+65M 0.047 1.829 87.5% 0.0748
-65+100M 0.034 1.864 87.5% 0.0555
-100+200M 0.035 2.171 87.6% 0.0667
-200M 0.036 2.547 87.6% 0.0811
  Pred. ROM Extraction 0.718
  ROM Ext. + uplift from 160 to 360 days 0.736
  92% Scale-up Factor 0.677

The copper extraction by particle size models in Figure 10.49 and Figure 10.50 both indicate a significant drop in copper extraction above one inch. Both models indicate copper extraction has gone to zero once particle size exceeds six inches (% Ext column in Table 10.17 and Table 10.18).

The copper extraction extrapolation for ROM MacArthur oxide material is 64% of total copper, Table 10.17. The QP utilizes a 92% scale-up factor for ROM copper heaps with low clay content. The MacArthur copper recovery is expected to be 59% after applying the 92% scale-up factor.

The copper extraction extrapolation for ROM Yerington oxide material is 74% of total copper, Table 10.18. Using the same 92% scale-up factor, the Yerington copper recovery is expected to be 68%.

10.6 HISTORIC HEAP LEACH PRODUCTION

Considerable metallurgical work has been completed on heap leaching at Yerington and MacArthur since the late 1970s. Yerington processing history includes flotation, vat leaching, cementation (Anaconda), and ROM heap leaching of oxides using W-3 material (Arimetco). However, detailed operational data from past heap operations is not available.

Heap leaching at Yerington restarted in 1989 on ROM "Slot Ore" from the W-3 stockpile, containing notable secondary/transitional minerals. This was supplemented by VLTs in 1993 and MacArthur oxide ore in 1994.

Approximately 51 million tons grading 0.18% TCu were leached on 5 HLFs, carrying 182.85 million lbs Cu. Copper recovery equaled 52.2%, with 94.41 million lbs sold over the campaign. The projected leach curve is shown in Figure 10.51. Shorter 60-day primary cycles and high solution rates reflected simpler ROM practices resulting in lower PLS grades and higher acid consumption compared to current industry standards.


 

The ongoing slope in Figure 10.51 indicates potential for ultimate copper recovery approaching 55% with extended leaching, which is considered reasonable given the mineralization blend. Modern geo-metallurgical methods now allow targeting zones matching historical analog performance.

Figure 10.51: Historic Yerington Heap Leach Ultimate Recovery. Curve is overall heap recovery after each operational year.

10.7 DELETERIOUS ELEMENTS

Test work programs to date have not identified any deleterious elements present in the Yerington or MacArthur mineralization expected to materially impact copper cathode quality or marketability. Produced LME Grade A copper cathode should readily meet standards for purity.

10.8 CONCLUSIONS

10.8.1 Nuton Sulfide Results

The two phases of Nuton test work have confirmed initial benchtop modeling results and demonstrated that Yerington sulfide ore can achieve copper recoveries exceeding 70% using Nuton leaching technologies. Optimization of leach additives and operational pH has improved leach kinetics and reduced acid consumption. Air and hydraulic conductivity of Yerington sulfide ore is suitable for the planned irrigation rates. Yerington sulfide is expected to achieve a total copper recovery of 73%.


 

10.8.2 Oxide Results

Historical production records and current tests to date support that Yerington and MacArthur oxide ore are well-suited for ROM heap leaching. Yerington oxide is expected to achieve a total copper recovery of 68%.  MacArthur oxide is expected to achieve a total copper recovery of 60%.

Portions of the MacArthur, North Ridge, and Gallagher "oxide" zones contain 20-30% transitional copper minerals which led to comparatively reduced empirical recovery historically.

10.9 RECOMMENDATIONS FOR FUTURE TESTING

Applied test work programs are recommended targeting enhanced copper recovery and reduced acid consumption across Yerington sulfide and MacArthur oxide materials. Feasibility work should focus on identifying the source of high acid consumption from the Yerington east oxide composite. Then test additional composites to confirm areas of focus to include solution management optimization and controlled acid dosage protocols.

All existing geological, mining, and metallurgical information should be compiled into an integrated geo-metallurgical model and incorporated into the feasibility level block model.

10.10 QP ADEQUACY STATEMENT

It is the QP and Samuel Engineer's opinion that the metallurgical test work and analysis support the metallurgical assumptions provided and used in the mineral reserve and resource estimation, the FS mine plans, and the economic analysis presented in this report.


 

11.0 MINERAL RESOURCE ESTIMATES

11.1 INTRODUCTION

AGP is responsible for the Yerington and VLT Mineral Resource estimates. IMC is responsible for all the MacArthur Deposit Mineral Resource estimate. Reported mineral resources were classified in accordance with S-K 1300 definitions, with material reported as in situ at Yerington and MacArthur Deposits.

11.2 YERINGTON DEPOSIT

This Project MRE used validated historic drill hole data generated by Anaconda and current drilling results by SPS in 2011, 2017, 2022, and 2024. All data received was based on the North American Datum (NAD) 83 Nevada State Plane.

The MRE has been generated from assay analyses and the interpretation of a geologic model that relates to the spatial distribution of copper in the Yerington deposit. Interpolation parameters have been defined based on geology, drill hole spacing, and geostatistical analysis of the data. The Yerington Copper Project Mineral Resources have been classified by their proximity to the sample locations and mining production.

The Mineral Resources were classified in accordance with S-K 1300 definitions.  Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. This estimate of Mineral Resources may be materially affected by environmental permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.

The Yerington Copper Project Mineral Resources are amenable to open-pit extraction, which was reported at a 0.04 % total copper (TCu) cut-off grade for oxide mineralization and a 0.08 % TCu cut-off grade for sulfide mineralization. The effective date of the Yerington Copper Project MRE is March 17, 2025. Mr. Tim Maunula, P.Geo., Principal Geologist, is the QP responsible for the completion of the Yerington Copper Project MRE.

The Mineral Resource estimate was prepared using HxGN MinePlan 3D 16.2.1 (MinePlan) resource software.

11.2.1 Database

The Mineral Resource estimate for the Yerington Copper Project is based on drill hole data consisting of total copper (TCu) assays, geological descriptions, recovery, and density measurements.

Limited sequential copper assays were available for acid-soluble copper (ASCu) from both Anaconda and SPS. Ferric sulfate copper (QLT) assays were available from SPS drilling. The datasets provided incomplete coverage for ASCu and QLT, so they were not used in the Mineral Resource estimation.

Data was provided to AGP by SPS in electronic formats Microsoft Excel and DXF files and imported into MinePlan. The database was additionally verified using the validation tool in MinePlan to determine errors and overlapping or out-of-sequence intervals. Minor errors were noted, and the database updated.


 

This mineral resource estimate used 862 drill hole collars totaling 346,368.8 ft. Although historical data includes material, some of which has been mined, that data was useful in establishing statistical parameters for grade interpolation into unmined blocks.

11.2.2 Geologic Model, Domains, and Coding

Lithology, as recovered from Anaconda archives or logged by SPS geologists, is included in the database. When lithology was not available, intervals were recorded as "UNK" or unknown.

The issue of metallurgical recovery is more a function of the mineralogical species of copper. The SPS geologists, incorporating their data and data from the Anaconda archives, interpreted two mineral zones, representing oxide and sulfide mineralization for grade interpolation. A third zone, alluvium, was modelled to represent the overburden material. The oxide contact with sulfide mineralization was updated using the data from the additional historic holes and recent drilling added to the database in 2024.

Historical data is a component of the database, and potential uncertainty arising from logging, assay, and survey errors is associated with the redox surfaces. Any future mineral processing could be affected by the misclassification of oxide or sulfide and their treatment. 

11.2.2.1 Contact Analysis

Contact grade analysis was conducted for oxide and sulfide assays (Figure 11.1). The average grade of each of the domains is within 10% of the contact with the oxide material, slightly higher. The oxide domain contains some TCu% higher grades and different mineralogy, so a hard boundary was used to control the extrapolation of these higher grades.

Source: AGP 2025

Figure 11.1: Contact Grade Analysis (TCu%)

11.2.3 Exploratory Data Analysis

11.2.3.1 Assays

Exploratory data analysis (EDA) was conducted based on the oxidation state of the mineralization: oxide and sulfide. Oxide material was coded as domain 30, sulfide material as 40, and alluvium as 20.


 

Core recovery was used as a factor to evaluate the assays. If the core recovery was greater than 40%, the assay was flagged (added 1 to the oxide or sulfide domain code, e.g., 31 or 41). Approximately 13% of the assays reported a core recovery of 40% or less. Figure 11.2 illustrates the differences between assays with recovery less than 40% (domains 30 or 40) versus those with recovery greater than 40% (domains 31 or 41). Within the oxide, there was no material difference in the mean grade. Within the sulfide, the mean grade of domain 41 was 15% lower.

Source: AGP 2025

Figure 11.2: Boxplot of Assays Reported by Recovery (TCu%)

11.2.3.2 Outlier Analysis

TCu% grades were reviewed for capping using log probability plots (Figure 11.3) and disintegration analysis. The log probability shows a linear trend for the final highest grades, without any observable "break" except for a few samples >10% TCu. This, along with low coefficient of variation (CV) supports using uncapped grades for grade interpolation.

The six highest assay grades (in drill holes B+100-4, I-3, M+100-17, N+100-17, Q+100-17 and Z-26) were reviewed on section, five of them were above the current open pit surface and had been mined out which was not reported in this MRE. The high grade in hole Z-26 was located within a cluster of five holes so the extrapolation was constrained. The assay grade of 9.64 % TCu, which was only 1.7 ft. downhole, was reduced to 1.22% TCu in the composite.


 

 

Source: AGP 2025

Figure 11.3: Log Probability Plot by Domain (TCu%)

11.2.3.3 Compositing

To normalize the assay data for further analysis, the raw assay values were composited to 25 ft. intervals within the mineralized domains oxide and sulfide. Composite values were then tagged by domain codes. Table 11.1 summarizes the descriptive statistics for the 25 ft. composites. Samples were coded based on core recovery to minimize potential bias. Only composites with >=40% core recovery were used for grade estimation.

Table 11.1: Composite Statistics Table (TCu%)
Domain Core
Recovery
Count Minimum Maximum Mean StDev CV
Oxide (30) <40% 1935 0.007 8.36 0.317 0.460 1.45
Oxide (31) >= 40% 4776 0.001 11.38 0.338 0.489 1.45
Sulfide (40) <40% 2875 0.003 3.478 0.311 0.315 1.01
Sulfide (41) >= 40% 8035 0.001 6.437 0.296 0.268 0.91

Notes: StDev = Standard Deviation; CV = Coefficient of Variation

No capping was applied as the coefficient of variation (CV) is within an acceptable range to confirm no material outliers were present in the grade population.


 

11.2.3.4 Spatial Analysis

The approach used to develop the variogram models employed Sage2001© software. Directional sample correlograms were calculated along horizontal azimuths of 0, 30, 60, 120, 150, 180, 210, 240, 270, 300, and 330 degrees. For each azimuth, sample correlograms were also calculated at dips of 30 and 60 degrees in addition to horizontally. Lastly, a correlogram was calculated in the vertical direction. Using the thirty-seven sample correlograms, an algorithm determined the best-fit model nugget effect and two-nested structure variance contributions. After fitting the variance parameters, the algorithm then fitted an ellipsoid to the thirty-seven ranges from the directional models for each structure. The anisotropy of the correlation was given by the range along the major, semi-major, and minor axes of the ellipsoids and the orientations of these axes for each structure. AGP reviewed the fitted variogram and adjusted, as required, to reflect the mineralization.

Table 11.2 presents the variogram parameters used for ordinary kriging.

Table 11.2: Variogram Parameters
Domain Structure Sill = 1.00 Z axis
Rotation
(°)
X' axis
Rotation
(°)
Y' axis
Rotation
(°)
X Range
(ft.)
Y Range
(ft.)
Z Range
(ft.)
Oxide (31) Nugget C0 = 0.20            
Spherical C1 = 0.52 -22 -13 -5 165 165 25
Spherical C2 = 0.28 -62 -2 -16 900 600 200
Sulfide (41) Nugget C0 = 0.20            
Spherical C1 = 0.52 -80 -1 60 150 300 75
Spherical C2 = 0.28 30 1 1 700 900 200

Note: MEDS or Vulcan Rotation Convention

 First rotation left-hand rule, Second rotation right-hand rule, Third rotation left-hand rule.

11.2.4 Bulk Density Data

Kappes, Cassiday & Associates, based in Reno, Nevada, completed twenty-three density tests on samples from the SPS drilling in November 2011. The tests resulted in an average tonnage factor of 12.62 cubic ft per short ton (cu.ft./ton) for oxide material and 12.61 for sulfide. A final value of 12.6 cu.ft./ton was used for the resource model, which compares with the 12.5 cu.ft./ton historically used by Anaconda.

11.2.5 Block Model and Resource Estimation

11.2.5.1 Model Framework

Block model parameters were defined to best reflect both the drill spacing and geometry of the deposit and the selective mining unit (SMU). Table 11.3 shows the block model parameters.


 

Table 11.3: Yerington Model Parameters
Model Parameters X (Columns) Y (Rows) Z (Levels)
Origin (ft): 2,446,400 14,661,000 2,900
Block size (ft) 25 25 25
Number of Blocks 360 320 100
Rotation No rotation

11.2.5.2 Topography

NewFields compiled 5 ft. contours and 3D faces for the topography in Nevada State Plane NAD83 coordinates (Figure 11.4) based on a LiDAR survey conducted by Olympus Aerial Surveys, Inc. in 2023 and Yerington Pit bathymetry by Resource Concepts Inc. and R.E.Y. Engineers, Inc. provided 20 February 2024.

Source: AGP 2023

Figure 11.4: Yerington Copper Project Planview 5 ft. Contours

11.2.5.3 Wireframes

SPS provided surfaces for the alluvium (20), oxide (30), and sulfide (40) contacts. AGP reviewed the surfaces. AGP updated the oxide-sulfide surface based on the new 2024 drilling, and additional historic drillholes added to the database. The block model rock type model was coded based on these surfaces as shown in the example Section 2451250E (Figure 11.5).


 

 

Source: AGP 2025
Note: Brown=Alluvium (20), Green=Oxide (30), Red=Sulfide (40)

Figure 11.5: Rock Type Section 2451250 E (Looking West ±100 ft.)

11.2.5.4 Grade Interpolation

Three methods of grade interpolation were used to estimate uncapped total copper (TCu%):

  • Nearest neighbor (NN)
  • Inverse distance interpolation to the second power (ID2)
  • Ordinary kriging (OK)

The block models were interpolated into two passes using 25 ft. composites. Table 11.4 summarizes the sample selection controls used with the various interpolation methods.

The software used for the Mineral Resource estimate was Leica Geosystems HxGN MinePlan 3D 16.2.1 (MinePlan).

Table 11.4: Summary of Sample Selection
Estimation Method Pass Minimum No. of
Samples
Maximum No. of
Samples
Maximum No. of
Samples/Drill Hole
Maximum No of
Samples/Sector
NN 1 1 1 1  
ID2 1 4 8 2 2
2 5 8 2 2
OK 1 4 8 2 2
2 5 8 2 2

Note: Pass 2 overwrites Pass 1


 

11.2.5.5 Search Ellipses

Table 11.5 summarizes the search ellipse parameters, which were based on the geological interpretation and spatial analysis. The same search ellipses were used for NN, ID2, and OK grade interpolation. Figure 11.6 shows the orientation of the sulfide material search ellipse.

Table 11.5: Search Ellipse Specifications
Domain Pass Search
Anisotropy
Z axis
Rotation

(°)
X' axis Rotation
(°)
Y' axis Rotation
(°)
X Range
(ft.)
Y Range
(ft.)
Z Range
(ft.)
Oxide (31) 1 MEDS -62 -2 -16 900 600 200
2 MEDS -22 -13 -5 165 165 25
Sulfide (41) 1 MEDS 30 1 1 700 900 200
2 MEDS -80 -1 60 150 300 75

Source: AGP 2025

Figure 11.6: Sulfide Material Search Ellipsoids

11.2.5.6 Special Model Attributes

Additional models were used to capture interpolation statistics to assist with the evaluation of confidence (Table 11.6).


 

Table 11.6: Special Models
Parameter NN OK
Local Error   KE1
Distance to Nearest Sample DSTN1 DSTK1
Number of Samples Used   NCMP1
Kriging Variance   KV1
Number of Sectors Used   NSEC1
Number of Drillholes Used   NDDH1
Average Distance to Samples Used   DSAV1
Pass Number   PASS1
Source: AGP 2025    

11.2.6 Model Verification and Validation

11.2.6.1 Visual Verification

The block model was validated by visually inspecting the block model TCu% grade estimation in the section and plan compared with the drill hole composite grade.

Figure 11.7 is a plan view comparing block model grades with composite grades. Figure 11.8 is a North-South section comparing the block model and composite grades. The grades of the blocks agreed well with the composite data used in the interpolation.

Source: AGP 2025
Note: 2025 Resource Pit: blue dash line

Figure 11.7: TCu% - 3800 ft. Plan (±25 ft.)


 

Source: AGP 2025
Note: 2025 Resource Pit: blue dash line

Figure 11.8: TCu% -- Section 2450000 E (Looking West ±50 ft.)

11.2.6.2 Statistical Validation

The block model statistics were reviewed, and no bias was found between the different interpolation methods (Table 11.7).

Table 11.7: Comparison of Grades by Interpolation Method
Rock Type NN Mean ID2 Mean OK Mean
CUNN% CUID% TCUK1%
Oxide (31) 0.109 0.123 0.126
Sulfide (41) 0.137 0.146 0.151

11.2.6.3 Swath Plots

A series of swath plots (grades accumulated by spatial coordinates) were generated to compare the composite grades with the NN, ID2 and OK interpolation methods. As shown in Figure 11.9, there appears to be agreement between the declustered composite grades (reflected by nearest neighbour interpolation) and interpolated OK grades. Figure 11.10 confirms the grade agreement between the ID2 and OK interpolation methods.


 

Source: AGP 2025

Figure 11.9: Plan Swath Plot Comparing CUNN1 (NN) and TCUK1 (OK) Grades

Source: AGP 2025

Figure 11.10: Plan Swath Plot Comparing CUID1 (ID2) and TCUK1 (OK) Grades


 

11.2.7 Mineral Resources Estimate

11.2.7.1 Mineral Resource Classification

The MREs were classified in accordance with S-K 1300 definitions.

The MREs were initially assigned based on data density in coordination with mineralization continuity. Mineral Resource classification was then refined based on the statistics collected during interpolation, primarily the distance to nearest composite used which reflected the spatial (derived from Variography) and geologic continuity. The nominal spacing for the Measured MREs, based on distance to nearest composite, was 100 ft. For the Indicated MREs, the spacing was 200 ft., and for Inferred MREs less than 400 ft. Grades beyond 400 ft. were unclassified.

Grooming was conducted on the initial resource classification to remove isolated pockets of different resource classifications by upgrading or downgrading to the surrounding resource classification. Figure 11.11 shows the Mineral Resource classification at the bottom of the existing pit. The blue outline is the conceptual resource pit shell used to constrain the Mineral Resources.

Source: AGP 2025
Note:  Red crosses are drillhole intersections
 1=Measured (Green), 2=Indicated (Yellow), 3=Inferred (Red)

Figure 11.11: Resource Classification - Plan 3800 ft. Elevation

11.2.7.2 Resource Classification Uncertainty

Following the statistical analysis in the preceding sub-section that classified MREs into the confidence categories, uncertainties regarding sampling and drilling methods, geological modelling and estimations were incorporated into the classifications assigned. The areas with fewer uncertainties were classified as Measured or Indicated.


 

The area of greatest uncertainty was assigned the Inferred category. These are areas corresponding to areas with >400-ft. drill spacing and generally along the margins of the deposit. Due to lack of drill density, there is a lower confidence in grade continuity. Additional drilling would resolve the uncertainty and contribute to upgrading the resource classification.

Uncertainty also lies in the historical drill data incorporated in the resource model, arising from logging, assaying and survey location uncertainty. Infill and/or twin hole drilling would reduce the potential errors arising from historical data. As multiple holes are used for grade interpolation and not single holes, that also reduces the potential uncertainty and allows for the classification of Measured or Indicated categories using historical data.

11.2.7.3 Cut-off Grade

A variable cut-off grade of 0.04% TCu for oxide material and 0.08% TCu for sulfide material was determined based on the assumptions listed in Table 11.8. Mineral Resources can be sensitive to the reporting cut-off grade.

The copper metal price of US$4.40/lb Cu was based on historic average price (determined October 2, 2024) of US$3.90/lb Cu escalated approximately 15%. The lower cut-off grades were influenced by using a proposed acid plant rather than purchasing acid at a higher unit cost which was the basis for the 2024 PEA (AGP, 2024).

Table 11.8: Yerington Deposit Cut-off Grade Assumptions
Description Parameter
Metal Price, US$/lb 4.40
Net Price after Smelting, Refining, Transportation and Royalty, US$/lb 4.22
Oxide Recovery 70%
Sulfide (Nuton) Recovery 74%
Oxide (ROM) Cut-off Grade, TCu% 0.04
Sulfide (Nuton) Cut-off Grade, TCu% 0.08

AGP generated a resource pit shell based on the economic parameters outlined in Table 11.8 and design criteria outlined in Table 11.9.

Table 11.9: Yerington Deposit Pit Slope Assumptions
Description Parameter
Overall pit slopes (°) 40
Alluvium Pit Slope (°) 40
Oxides (°) 40
Sulfides (°) 40

11.2.7.4 Mineral Resource Statement

Table 11.10 presents the Mineral Resources for the Yerington Deposit. The effective date of the Yerington Copper Project MRE is March 17, 2025. Mr. Tim Maunula, P.Geo., Principal Geologist is the QP responsible for the completion of the Yerington Copper Project MRE.


 

Table 11.10: Yerington Deposit Mineral Resource Statement
Material Cut-off Grade
(TCu%)
Tons TCu% TCu lbs
Measured Oxide 0.04 37,530,900 0.21 157,630,000
Measured Sulfide 0.08 84,163,100 0.30 504,979,000
Measured Total   121,694,000 0.27 662,609,000
Indicated Oxide 0.04 60,043,900 0.16 192,140,000
Indicated Sulfide 0.08 263,230,000 0.22 1,158,212,000
Indicated Total   323,273,900 0.21 1,350,352,000
Measured+Indicated Oxide 0.04 97,574,800 0.18 349,770,000
Measured+Indicated Sulfide 0.08 347,393,100 0.24 1,663,191,000
Measured+Indicated Total   444,967,900 0.23 2,012,961,000
Inferred Oxide 0.04 40,916,600 0.12 98,200,000
Inferred Sulfide 0.08 67,576,400 0.17 229,760,000
Inferred Total   108,493,000 0.15 327,960,000

Notes: Mineral resources are reported in situ and the effective date is March 17, 2025. Mineral resources are not mineral reserves and do not demonstrate economic viability.

Mineral resources are reported within a conceptual pit shell that used the following input parameters: a variable break-even economic cut-off grade of 0.04 % TCu and 0.08% TCu, for oxide and sulfide material respectively, based on assumptions of a net copper price of US$4.22 per pound (after smelting, refining, transportation, and royalty charges), 70% recovery in oxide material, 74% recovery in sulfide material, base mining costs of $2.49/st for oxide and $2.22/st for sulfide, and processing plus G&A costs of $2.00/st for oxide and $4.44/st for sulfide.

All figures are rounded to reflect the relative accuracy of the estimates and totals may not add correctly.

11.3 YERINGTON RESIDUALS

Numerous sites of low-grade mineralization and waste dumps are present at Yerington. Some of these have been sampled, post depositions, to determine an average grade and to conduct metallurgical testing. An MRE was conducted on one of these dumps, the VLT, that lies northwest of the Yerington Pit.

Oxide tailings, or VLT, are the residual leached products of Anaconda's vat leach copper extraction process (CH2M Hill, 2010). The oxide tailings dumps contain the crushed rock and the red sludge at the base of the leach vats that remained following the extraction of copper in the vat leaching process.

The Mineral Resources have been classified by their proximity to the sample locations and in accordance with S-K 1300 definitions. The VLT Mineral Resources amenable to open pit extraction were reported at 0.03 % TCu cut-off grade. The effective date of the VLT MRE is March 17, 2025. Mr. Tim Maunula, P.Geo., Principal Geologist is the QP responsible for the completion of the VLT Mineral Resources.

The Mineral Resource estimate was prepared using HxGN MinePlan 3D 16.2.1 resource software.

11.3.1 Database

There were 22 wet sonic drill holes, labelled VLT-001 to VLT-022, and 9 dry rotosonic drill holes (VLT-12-002, VLT-12-003T, VLT-12-005T, VLT-12-006T, VLT-12-011T, VLT-12-016T, VLT-12-017T, VLT-12-019T and VLT-12-021T) which twinned the wet sonic holes (Figure 11.12). The total footage of the 22 holes used for the 2024 Mineral Resources is 2621.5 ft.


 

Source: AGP 2025

Figure 11.12: Yerington Residuals Collar Plot

11.3.2 Geological Domains

No controls for mineralization were used as this is primarily low-grade oxide material in surface deposits and not in situ. The volume of the VLT was controlled by the current topography based on the 2023 LiDAR survey and the interpreted original topography.

11.3.3 Exploratory Data Analysis

Assay statistics for TCu% are illustrated in Figure 11.13, the mean assay grade is 0.093% TCu. Capping was evaluated using disintegration analysis for the VLT data but determined that capping was not required. The low CV of 0.39 (Figure 11.13) also supports the use of no capping.

Assays statistics for ASCu% are illustrated in Figure 11.14, the mean assay grade is 0.054% ASCu. No capping was applied.


 

Source: AGP 2025

Figure 11.13: VLT Assays, TCu%

Figure 11.14: VLT Assays, ASCu%


 

Ten-ft. composites were created. Figure 11.15 illustrates the composite statistics for TCu % using a log probability plot. A total of 247 composites were created from the 285 assays.

Source: AGP 2025

Figure 11.15: VLT 10 ft. Composites (TCu%)

No variography was conducted as there were insufficient samples and grade continuity in tailings was based on deposition and area of influence.

11.3.4 Bulk Density

The tonnage factor assigned was 16.67 cu.ft./ton which is appropriate for broken material present in the VLT as determined by CH2M Hill, Inc. (USEPA, 2010b).

11.3.5 Block Model and Resource Estimation

11.3.5.1 Model Framework

Block model parameters were defined to best reflect the drill spacing and geometry of the deposit, and SMU. Table 11.11 shows the block model parameters.

Table 11.11: VLT Model Parameters
Model Parameters X (Columns) Y (Rows) Z (Levels)
Origin (ft): 2,444,0500 14,669,000 2,900
Block size (ft) 25 25 25
Number of Blocks 180 280 48


 

Table 11.11: VLT Model Parameters
Model Parameters X (Columns) Y (Rows) Z (Levels)
Rotation No rotation

11.3.5.2 Grade Interpolation

The VLT block model TCu was interpolated using NN and ID2 methods. A horizontal one pass 750 ft. isotropic XY search with a 37.5 ft. Z search was used. No controls for mineralization were used.

Special models captured information for the NN model on distance to nearest composite and for the ID2 model: distance to nearest composite, average distance to composites used, maximum number of composites used and maximum number of drill holes used.

11.3.6 Model Verification and Validation

VLT grade interpolation was visually verified and validated using swath plots to compare the composite with the ID2 grades.

Figure 11.16 shows the correlation between the TCu% grade in the drill hole versus the interpolated ID2 grades. The visual verification supported the agreement between the drill hole grades and interpolated grades.

Source: AGP 2025
Notes: Resource Pit Shell=Orange
 Looking West ±50 ft.

Figure 11.16: VLT Section Block Model ID2 vs Drill Hole Composite TCu% Grade


 

Figure 11.17 illustrates the correlation (by elevation) between the TCu% drill hole grade with the interpolated ID2 grade.

Source: AGP 2025
Notes: Drill Hole Grade (red line)
 Block Model ID2 Grade (blue line)

Figure 11.17: VLT Swath Plot by Elevation

11.3.7 Mineral Resource Estimate

11.3.7.1 Mineral Resource Classification

The VLT resource classification was applied based on the distance to nearest composite reported for the ID2 interpolation. Blocks within 500 ft. were assigned as Indicated (2) and within 750 ft. as Inferred (3) Mineral Resource. All remaining interpolated blocks were uncategorized (4). No blocks were classified as Measured (4) Mineral Resource.

Figure 11.18 illustrates a plan view of the resource classification for VLT.


 

Source: AGP 2025
Notes: Measured=1, Indicated=2, Inferred=3, Not classified=4
 VLT Resource Shell shown in brown.

Figure 11.18: VLT Resource Classification (Planview)

11.3.7.2 Resource Classification Uncertainty

Following the statistical analysis in the preceding sub-section that classified Mineral Resources into the Indicated and Inferred confidence categories, uncertainties regarding sampling and drilling methods, geological modelling and estimation were incorporated into the classifications assigned. Twin hole drilling has added to the confidence categories. As multiple holes are used for grade interpolation and not single holes, that also reduces the potential uncertainty and allows for the classification of Inferred category. The areas of greatest uncertainty were not assigned a confidence category.

11.3.7.3 Cut-off Grade

A cut-off grade of 0.03% TCu was determined based on the assumptions listed in Table 11.12. Mineral Resources can be sensitive to the reporting cut-off grade.

The copper metal price of US$4.40/lb Cu was based on the historic average price of US$3.90/lb Cu escalated by approximately 15% for the Mineral Resource.

Table 11.12: Residuals Cut-off Grade Assumptions
Description Parameter
Metal Price, US$/lb 4.40
Net Price after Smelting, Refining, Transportation and Royalty, US$/lb 4.22
Oxide Recovery 75%


 

Table 11.12: Residuals Cut-off Grade Assumptions
Description Parameter
Oxide (ROM) Cut-off Grade, TCu% 0.03

11.3.7.4 Reasonable Prospects for Eventual Economic Extraction

To satisfy the requirements for reasonable prospects for eventual economic extraction, AGP generated a resource pit shell based on the economic parameters outlined in Table 11.12 and the design parameter of 40-degree overall pit slope.

11.3.7.5 Mineral Resource Statement

The marginal cut-off grade of 0.03% TCu was selected for reporting the VLT Mineral Resource in Table 11.13. The effective date for the VLT Mineral Resources is March 17, 2025. Mr. Tim Maunula, P.Geo., Principal Geologist, is the QP responsible for the 2025 VLT MRE.

Table 11.13: VLT Mineral Resource Statement
Class Cut-off Grade
(TCu%)
Tons TCu% TCu lbs ASCU% ASCU lbs
Indicated >= 0.03 36,512,000 0.09 65,722,000 0.05 36,512,000
Inferred >= 0.03 26,420,500 0.09 47,557,000 0.05 28,421,000

Notes: Mineral resources reported for the VLT are for surficial deposits and not in situ. Effective date for this Mineral Resource estimate is March 17, 2025.

The 2025 Mineral Resource estimate uses a break-even economic cut-off grade of 0.03 % TCu based on assumptions of a net copper price of US$4.22 per pound (after smelting, refining, transportation, and royalty charges) and 75% recovery in oxide material.

Mineral Resources are not Mineral Reserves and do not demonstrate economic viability.

The Mineral Resource estimate is reported from within the resource pit shell containing Indicated and Inferred Mineral Resources.

There is no certainty that all or any part of the Mineral Resource estimate will be converted into Mineral Reserves.

All figures are rounded to reflect the relative accuracy of the estimates and totals may not add correctly.

11.4 MACARTHUR DEPOSIT

The previous mineral resource estimate for MacArthur was completed in 2021 based on a drill hole data set of 747 drill holes totaling 299,044.8 ft.  Since then, the drill hole database has been updated to 802 holes totaling 317,696 ft. The additions include 26 historic holes (Anaconda - 20 holes and Bear Creek - 6 holes) and 29 new holes by Lion CG (18,652 ft).  In addition to the drill data updates, which reduced the average total copper grade in the database by 2.2%, the following inputs to the mineral resource have changed:

  • The 2021 block model was in a UTM ft coordinate system, and the 2024 block model is in the Nevada State Plane coordinate system
  • New resource block model with updates to the geologic domains and grade estimation
  • Changes to the resource classification, including distances and increasing the minimum composites for inferred from 1 to 2 composites
  • Changes to the density assignment and additional density samples
  • Changes to the copper recovery, costs, and copper price

 
  • Removing sulfide material from the mineral resource tabulation

Table 11.14 shows a comparison between the 2021 and 2025 mineral resource summaries.

Table 11.14: Comparison of 2021 and 2025 Mineral Resources
  2025 Estimate 2021 Estimate
Classification Ktons TCu, % Contained Cu,
Lbs x 1000
Ktons TCu, % Contained Cu,
Lbs x 1000
Measured 163,333 0.177 577,806 116,666 0.180 420,929
Indicated 155,086 0.152 471,570 183,665 0.158 579,479
Sum M & I 318,419 0.165 1,049,375 300,331 0.167 1,000,408
Inferred 23,169 0.146 67,868 156,450 0.151 471,714

Herb Welhener, Vice President of IMC, is the qualified person for the MacArthur Mineral Resource Estimate.

11.4.1 Database

The drill data for the MacArthur Deposit combines core, RC, air track, and churn drilling. Within the resource block model boundaries, 800 drill holes totaled 314,504 ft. A total of 58,987 intervals were assayed for total copper. Table 11.15 is a summary of the assaying for total copper by the company; only Lion CG drilling has been assayed for soluble copper (ASCu, 37,057 intervals; CNCu, 777 intervals; QLT, 18,592 intervals, and 1,235 intervals have sequential assays for ASCu and CNCu).

Table 11.15: Summary of Assay Intervals for Total Copper by Company
  Lion CG Anaconda Bear Creek Superior USBM Total
No. Holes 456 311 14 11 8 800
Total Length, ft 230,849 62,049 5,140 13,052 3,414 314,504
No. of Total Intervals 46,119 11,785 1,032 1,041 872 60,849
No. Assayed Intervals 44,963 11,629 851 740 804 58,987
TCu%, mean 0.093 0.219 0.115 0.125 0.140  
TCu%, minimum 0.000 0.000 0.002 0.001 0.010  
TCu%, maximum 13.800 5.380 3.362 2.336 1.94  

11.4.2 Geological Domains

The geological interpretation was completed by a collaboration between the Lion CG staff and IMC for application to the block model. The mineral zones were developed as surfaces based on polygons generated using the 25 ft bench composites from the drill holes that were logged for redox. Overall, 77.25% of the intervals in the assay database are logged for redox with 99% of the Lion CG intervals being logged. The assay intervals which were not logged received a redox code by back assigning the redox from the block model once the model codes were completed. The geological team interpreted the oxidation state (redox) of mineralization into five categories:

  • Overburden = 100
  • Leach Cap Code = 10

 
  • Oxide Code = 1
  • Mixed Code = 2
  • Sulfide Code = 3

Each of the zones represents a different mineralogy and amenability to the leach process. Figure 11.19 shows the holes which have logged redox values. This shows good coverage of the block model area where mineralization has high enough values to be considered part of the mineral resource.


 

 

Source: IMC 2024

Figure 11.19: Drill Holes with Logged Redox


 

11.4.3 Exploratory Data Analysis

11.4.3.1 Assays

IMC completed several basic statistical measures of the assay data sorted by the mineral zones. The basic statistical comparison of the capped total copper assays by the mineral zones is summarized below in Figure 11.20. Figure 11.21 shows probability plots of the capped assay data for total copper by the mineral zones and Figure 11.22 shows probability plots of the assay data for acid-soluble copper by mineral zones. The data is presented in log space.

Source: IMC 2024

Figure 11.20: Basic Statistics of Capped Total Copper Assays


 

Source: IMC 2024

Figure 11.21: Probability Plots of Capped Total Copper Assays


 

 

Source: IMC 2024

Figure 11.22: Probability Plots of Acid Soluble Copper Assays


 

11.4.3.2 Capping

Basic statistics and cumulative frequency plots were studied to determine the level at which outliner values should be capped. MacArthur Deposit assay grade capping was completed on total copper by oxidation zone. The oxidization zone was assigned to each assay interval from the zones within the resource block model. Capping was applied to assays prior to compositing. The capped assays were composited into irregular target length 25-foot length composites that respect the mineral zone (redox) boundaries.

The capping values were based on a review of cumulative frequency plots of each of the mineral zones to identify the few samples that were outliers. For completeness, the acid soluble grades (when present) were capped with the same percentage as total copper assay intervals that were capped. Table 11.16 summarizes the capping applied on the MacArthur Deposit.

Table 11.16: Assay Cap Levels by Oxidation Zone
Oxidation
Zone
Redox
Code
Number
of Assays
Original
Mean
TCu%
Cap
Grade
TCu%
Number
of
Capped
Intervals
Means
Capped
TCu%
Overburden 100 1,300 0.061 1.00 3 0.061
Leach Cap 10 6,597 .066 1.25 3 0.066
Oxide 1 28,498 0.142 2.50 6 0.142
Mixed 2 6,897 0.166 3.50 8 0.163
Sulfide 3 14,680 .070 3.00 5 0.069

11.4.3.3 Compositing

Prior to block grade estimation, the drill hole data was composited to 25-foot intervals that respected the mineral zone boundaries. The composite length was selected to match the mining bench height and provide samples of similar size and weight for block grade estimation. The purpose of compositing is to smooth the data somewhat to understand the grade distributions and domain boundaries prior to grade estimation.

Figure 11.23 summarizes the basic statistics of the 25-foot irregular composites respecting the mineralized zone boundaries. A minimum length of 10 ft was required for a composite to be calculated. The distribution of copper composites in Figure 11.23 represents the information that will be used for block grade estimation.


 

Source: IMC 2024

Figure 11.23: Basic Statistics of 25-foot Irregular Composites

11.4.3.4 Spatial Analysis

Variograms were run for total copper in each of the redox domains defined on the previous tables. The intent was to provide some guidance to the search orientation and search radii that should be combined during grade estimation. The 25-foot irregular composites bounded by redox were used as input for the copper variograms.

Those results were used as a guide to the selection of the grade estimation methods summarized in the next section. Figure 11.24 and Figure 11.25 are example horizontal variograms from the oxide and mixed domains respectively. Oxide and mixed are the two primary mineralization hosts for the deposit and overall have the higher grades across most of the grade range as shown in the probability plot of the capped total copper assays (Figure 11.23). Within the oxide and mixed zones of the deposit, the predominate orientations were horizontal variograms, azimuth of 0.0 with a horizontal window of 90.0 degrees.


 

Source: IMC 2024

Figure 11.24: Oxide Zone Variogram


 

Source: IMC 2024

Figure 11.25: Mixed Zone Variogram

The leach cap variogram shows multiple ranges of data which may be indicative of the grade break at 0.010 % Cu which was seen on the cumulative frequency plot. Again, indicating that portions of the leach cap need to be treated as a separate population during block grade estimation. If the plus 0.10% values were allowed to mix with the low background values of leach cap, the estimation methods would result in large areas of 0.06 to 0.10% copper that are not present. The true distribution is limited to a smaller area of plus 0.10% surrounded by a subgrade zone of 0.05% copper or less.

The sulfide variogram shows a long range in the horizontal direction. A review of the cross-sections indicates that there are several locations in the North Ridge area (North of 14,190,378) of the sulfide zone where there is an indication that the copper grades at depth dip to the north. Grade estimates were done both on a horizontal basis and a dipped search to the north; the dipped search connected like mineralized zones in the area of wide spaced drilling.


 

11.4.4 Bulk Density

Density was estimated based on the density data on samples collected by Lion CG personnel and measurements done by Paragon and KCA labs. In total, 51 density determinations were made (36 by Paragon and 15 by KCA). KCA ran two density measurements for each sample, and these were averaged to provide one value for the sample. Table 11.17 shows the results of the density test work in cubic ft per short ton by redox type and model domain. The average tonnage factors were assigned to the appropriate locations in the block model. No samples were collected for the overburden, and it was assigned a default value of 14.0 cubic ft per short ton.

Table 11.17: Tonnage Factors Assigned to Block Model
  MacArthur Domain North Ridge Domain Gallagher Domain Outside
Domains
  Number of
Samples
Average
Tonnage
Factor (cuft/st)
Number of
Samples
Average
Tonnage
Factor (cuft/st)
Number of
Samples
Average
Tonnage
Factor (cuft/st)
Average
Tonnage
Factor (cuft/st)
Leach Cap 3 12.94 4 12.96 2 12.64 12.92
Oxide 15 12.76 13 12.95 1 13.25 12.94
Mixed 3 12.94 3 13.40 3 13.68 13.30
Sulfide 1 13.01 1 13.33 2 12.48 12.96
Overburden 0 14.00 0 14.00 0 14.00 14.00

11.4.5 Block Model and Grade Interpolation

11.4.5.1 Model Framework

The resource model covers the areas of MacArthur Main (MacArthur pit area), North Ridge and Gallagher domains. Blocks were sized 25 ft x 25 ft x 25 ft in order to model the mineralization zones to provide a reasonable block size that could be used for open pit mine planning. The Project coordinate system is in Nevada State Plane NAD83 Nevada State Plane, West Zone, US Survey Foot system. Table 11.18 summarizes the size and location of the block model.

Table 11.18: MacArthur Model Size and Location, September 2024
MacArthur Model - Nevada State Plane Coordinate System
  Southwest Northwest Northeast Southeast
Easting 2,430,000 2,430,000 2,446,000 2,446,000
Northing 14,680,000 14,698,000 14,698,000 14,680,000
Elevation Range   2,650.00 5,775.00  
No Model Rotation, Primary Axis = 0.0 degrees  
Model 1   640 Blocks in Easting
Size     720 Blocks in Northing
Block Size 25 ft x 25 ft x 25 ft high   125 Levels  


 

Figure 11.26 illustrates the domain splits within the resource block model. The largest mineral resources are in the MacArthur pit and North Ridge domains, followed by the Gallagher area. The MacArthur pit domain is subdivided into two areas based on the density of drilling. The domain with the denser drilling contains the bulk of the historic drilling, which has a higher average total copper grade.

Source: IMC 2024

Colors: MacArthur Pit Area - Dark & Light Blue; North Ridge - Red; Gallagher - Green

Figure 11.26: MacArthur Block Model Domains and Drillhole Collar Locations

11.4.5.2 Mineralization Zones

The mineral resource model's main attribute is the mineralization's oxidation state (redox). The mineral zones were developed as surfaces using polygonal shapes on each 25 ft bench for the redox code of the 25 ft bench composite drill holes. The redox polygons used a 300 ft search to establish the zones that filled most blocks in the closer-spaced drill hole areas. In areas that were not assigned a redox code, the redox was assigned manually, bench by bench, using the trends from the assigned redox areas as guides. There are five major mineralization zones, which were assigned to the resource block model: leach cap (code 10), oxide (code 1), mixed (code 2), sulfide (code 3), and overburden (code 100). Each zone represents a different mineralogy and amenability to the leach process. The leach cap is generally quite low in copper grade, which has been removed from the rock mass and re-precipitated at the original water table in the mixed zone as secondary sulfides, typically chalcocite, covellite, or digenite.


 

The oxide zone reflects oxide minerals such as chrysocolla and neotocite. The mixed zone contains primary and secondary copper minerals, which are transported down from the leach cap and redeposited. The sulfide zone is predominantly unaltered chalcopyrite mineralization; the sulfide zone has been removed from the 2025 mineral resource. The mineralization in the overburden zone is somewhat random and represents more recent mobilization of copper mineralization. In addition to the changes in mineralogy within these zones, there is often a corresponding change in the grade of each zone as seen by the mean grades of the assay intervals (Figure 11.21). Figure 11.27 is an east-west cross-section through the block model in the Gallagher (west side) and MacArthur domains, showing the mineralization zones, and Figure 11.28 is a north-south cross-section through the MacArthur (south) and North Ridge domains. The drill holes on the example section show 25-foot composites of the oxidization zones.


 

Source: IMC 2024

Colors: Orange = Leach Cap, Yellow = Overburden, Blue = Oxide, Green=Mixed, Grey = Sulfide; Horizontal Grid is 1,000 ft


 

Figure 11.27: East-West Cross-Section Looking North at 14,688,000 North

Source: IMC 2024

Colors: Orange = Leach Cap, Yellow = Overburden, Blue = Oxide, Green=Mixed, Grey = Sulfide; Horizontal Grid is 1,000 ft

Figure 11.28: North-South Cross-Section Looking West at 2,439,000 East - Through MacArthur & North Ridge


 

11.4.5.3 Grade Interpolation

A boundary analysis was performed at the boundaries between each of the five mineralized domains and the results indicate that most domains should be estimated separately, thus boundaries between leach cap, oxide, mixed and sulfide were treated as 'hard' boundaries for the estimation of grades. The leach cap and overburden were treated as a combined domain. A study of the leach cap and overburden composites showed a population break at 0.10% total copper. The leach cap was separated into two zones using an indicator method with a 0.10% total copper discriminator. Of the 1,484 drill hole composites within the leach cap and overburden zones, 11% fall within the higher-grade pod and 89% fall outside.

Variograms were run for total copper in each of the mineralization domains. The intent was to provide guidance to the search orientation and search distance for the grade estimation. The 25-foot irregular composites bounded by rock type were used as input for the total copper variograms and ranges between 400 and 700 ft were obtained which support the search distances used to estimate the model grades.

Total copper grades were estimated using ID3 in the oxide, mixed, and sulfide mineral zone domains. Leach cap was segregated into two populations using an indicator method to address the plus 0.10% grade distribution separately from the sub 0.10% distribution in the leach cap with total copper grades estimated using ID3 in each population. Indicator procedures were tested for all the domains, but the ID3 results appear to follow the data better in the oxide, mixed and sulfide zones. All of the estimation runs used a minimum of two grade composites, a maximum of 10 composites with a maximum of three composites per hole. All of the search orientations were horizontal except for the deeper sulfide zone in the North Ridge domain where a dipped search of 30 degrees to the north connected up like mineralized zones in the area of wide spaced drilling. The search distances in each zone are:

  • Leach & Overburden: Indicator with 0.10% TCu discriminator, 450 x 450 x 40 ft

Grade inside higher grade zone, 450 x 450 x 40 ft

Grade outside higher grade zone , 450 x 450 x 40 ft

  • Oxide: MacArthur, 400 x 400 x 60; North Ridge, 380 x 380 x 60; Gallagher, 450 x 450 x 60 ft
  • Mixed: MacArthur, 500 x 500 x 60; North Ridge, 400 x 400 x 60; Gallagher, 400 x 400 x 60 ft
  • Sulfide: MacArthur, 400 x 500 x 200; Gallagher, 400 x 400 x 200 ft

North Ridge: 400 NS x 400 EW x 200 ft with dip 30 degrees to north

Figure 11.29 is a north-south cross section example looking west at 2,439,000 east showing the total copper grades in the block model and is at the same model location as Figure 11.28.


 

Source: IMC 2024

Colors:  Black = <0.05% TCu, Blue = 0.05 -0.10% TCu, Green = 0.10-0.25% TCu, Orange = 0.25 - 0.50% TCu, Red = >0.50% TCu

Figure 11.29: North-South Cross-Section Total Copper Grade Looking West at 2,439,000 East - Through MacArthur & North Ridge


 

11.4.6 Model Verification and Validation

Numerous tests were performed to confirm that the model is a reasonable representation of the data for the determination of mineral resources. Example sections and plans from the block model were reviewed with the supporting composite data during the model assembly process.

A nearest neighbor (polygon) estimate and a kriged estimate of copper were completed using the same domains and search radii that were applied to the inverse distance estimate. Figure 11.30 shows cumulative frequency plots of the three estimates in the oxide zone. Above a 0.05% total copper cutoff grade, the ID3 estimate tracks between the polygon estimate and the kriged estimate. The comparison of the nearest neighbor and the inverse distance estimates of number of blocks estimated times the average estimated grade at a zero-cut-off grade is a check designed to determine if the selected method has incorporated bias. In all redox zones, the difference is less than one percent.

Source: IMC 2024

Figure 11.30: Cumulative Frequence of Copper Grades in Oxide Zone


 

11.4.7 Mineral Resource Estimate

11.4.7.1 Mineral Resource Classification

The mineral resource classification is based on the number of composites used and the average distance of the block center to the composites being used to determine the classification of the block. The classification criteria used:

  • Measured: Number of composites = 10 (minimum 4 holes) within 175 ft
  • Indicated: Number of composites = 7 (minimum 3 holes) with 300 ft
  • Inferred: Any block with a total copper grade based on a minimum of two composites

11.4.7.2 Resource Classification Uncertainty

Following the statistical analysis in the preceding sub-section that classified mineral resource estimates into the confidence categories, uncertainties regarding sampling and drilling methods, geological modelling and estimation were incorporated into the classifications assigned. The areas with fewer uncertainties were classified as measured or indicated.

The area of greatest uncertainty assigned the inferred category. These are areas corresponding to areas with >225-foot drill spacing and generally outside of the MacArthur & North Ridge central areas along the margins of the deposits and at depth where fewer drillholes are present. Due to lack of drill density, there is a lower confidence in grade continuity.  Additional drilling would resolve the uncertainty and contribute to upgrading the resource classification.

Additional uncertainty lies in the historical drill data incorporated in the resource model, arising from logging, assaying and survey location uncertainty.  Infill and/or twin hole drilling would reduce the potential errors arising from historical data. As multiple holes are used for grade interpolation, that also reduces the potential uncertainty and allows for the classification of measured or indicated categories using historical data.

11.4.7.3 Cut-off Grade

The copper price used to define the mineral resource pit shell is $4.40 per pound., based on the December 2024 three year backward average of $3.90/lb plus approximately 15%. The $4.40 per pound price was agreed to by Lion CG, AGP and IMC. The copper price and all costs are in U.S. dollars. The recoveries and costs are based on recent reviews and adjustments to both the 2024 and historic evaluation work at Yerington and MacArthur (Table 11.19). Sulfuric acid cost assumes an onsite acid plant. The process and mining costs were provided by AGP and IMC feels the costs are valid as of December 2024. The cut-off grades are 0.05% TCu for all material types in the MacArthur pit area and 0.06% TCu in North Ridge, and 0.07% TCu in Gallagher. These cutoffs are rounded up compared to the calculated internal cutoff grades. No sulfide material is included in this mineral resource which is intended to be a run of mine heap leach.

Table 11.19: Inputs to Definition of Pit-Constrained Mineral Resource - Recoveries
Mineralization Recovery of Total Copper
  MacArthur North Ridge Gallagher
Leach Cap & Overburden 55.0% 53.0% 54.0%


 

Table 11.19: Inputs to Definition of Pit-Constrained Mineral Resource - Recoveries
Mineralization Recovery of Total Copper
Oxide 55.0% 53.0% 54.0%
Transition 55.0% 53.0% 55.0%
Sulfide 0.0% 0.0% 0.0%

Table 11.20: Inputs to Definition of Pit-Constrained Mineral Resource - Costs
Cost Center Unit Cost
Process Cost, ROM & Acid Plant Per heap short ton MacArthur $1.67
North Ridge $1.73
Gallagher $2.14
General & Administrative Per heap short ton $0.49
Cathode Refining & Transport Per Cu lb $0.05
Royalty Per Cu lb $0.108
Sulfuric Acid, cost Per short ton $128.00
Acid Consumption:
MacArthur Per short ton 20 lbs/st
North Ridge Per short ton 28 lbs/st
Gallagher Per short ton 42 lbs/st
Mining Cost:    
Mining Cost Per total st Heap tons $2.49
Waste tons $2.53

11.4.7.4 Reasonable Prospects for Eventual Economic Extraction

To satisfy the requirements for reasonable prospects for eventual economic extraction, the mineral resources for MacArthur are constrained within a pit shell defined by the current understanding of costs and recovery of copper based on the intended recovery method of heap leaching using sulfuric acid for run of mine material. The input parameters for the definition of the pit shell using a floating cone algorithm are given in Table 11.19 and Table 11.20.

An overall pit wall slope angle of 42 degrees was used to define the resource shell. An example plot of the pit shells is shown in Figure 11.31. The MacArthur Mineral Resources were classified in accordance S-K 1300 definitions.


 

Source: IMC 2025

Notes: The MacArthur pit area lies to the southeast, North Ridge to the north/northeast and Gallagher to the west.

Figure 11.31: MacArthur Mineral Resource Pit Shell


 

11.4.7.5 Mineral Resource Statement

The MacArthur Deposit mineral resource is summarized in Table 11.21 with the details given in Table 11.22 and Table 11.23. The MacArthur Deposit mineral resource estimate is current of March 17, 2025. IMC is responsible for the MacArthur Deposit mineral resource estimate.

Table 11.21: Summary of Mineral Resource
Classification Ktons Total Cu, % Contained Cu Pounds x 1000
Measured 163,333 0.177 577,806
Indicated 155,086 0.152 471,570
Sum Measured+Indicated 318,419 0.165 1,049,375
Inferred 23,169 0.147 67,868

Notes:

 Mineral resources are reported in situ and are current as of March 17, 2025.

 Mineral resources are not mineral reserves and do not have demonstrated economic viability.

 Herb Welhener, Vice president of IMC is qualified person for the MacArthur Mineral Resource estimate.

 Mineral resources are reported within a conceptual pit shell that uses the following input parameters:

 Metal price of $4.40/lb Cu; process costs between $1.67 and $2.14/st; and base mining costs for heap tonnage of $2.49/st and $2.53/st for waste,

 Recovery of Total Copper in redox zones of leach cap, overburden, oxide and mixed: MacArthur domain 55%, North Ridge domain 53%, Gallagher domain 54%, recovery in sulfide redox = 0%

 Cut-off grade: for leach cap, overburden, oxide and transition is 0.05% TCu in MacArthur, 0.06% Tcu in North Ridge and 0.07% Tcu in Gallagher

 Total resource shell tonnage = 438,601ktons


 

Table 11.22: Mineral Resource by Domain
Domain   MEASURED INDICATED MEASURED & INDICATED
Total Copper Cut-off, % Ktons & Grade Above Cut-off Ktons & Grade Above Cut-off Ktons & Grade Above Cut-off
Ktons TCu, % Contained Cu Pounds x 1000 Ktons TCu, % Contained Cu Pounds x 1000 Ktons TCu, % Contained Cu Pounds x 1000
MacArthur 0.05 111,983 0.176 393,150 53,434 0.146 156,154 165,417 0.166 549,304
North Ridge 0.06 38,779 0.182 141,457 63,537 0.152 192,984 102,316 0.163 334,441
Gallagher 0.07 12,571 0.172 43,199 38,115 0.161 122,431 50,686 0.164 165,631
Total 163,333 0.177 577,806 155,086 0.152 471,570 318,419 0.165 1,049,375

Domain   INFERRED
Total Copper Cut-off, % Ktons & Grade Above Cut-off
Ktons TCu, % Contained Cu Pounds x 1000
MacArthur 0.05 3,327 0.134 8,903
North Ridge 0.06 6,926 0.141 19,529
Gallagher 0.07 12,916 0.153 39,436
Total 23,169 0.146 67,868

Notes: Mineral resources are reported in situ and are current as at March 17, 2025.

 Mineral resources are not mineral reserves and do not have demonstrated economic viability.

 

Table 11.23: Mineral Resource by Domain and Oxidation Zone
    MEASURED INDICATED MEASURED & INDICATED INFERRED
Oxidation Zone Total Copper Cut-off, % Ktons & Grade Above Cut-off Ktons & Grade Above Cut-off Ktons & Grade Above Cut-off Ktons & Grade Above Cut-off
Ktons Total Cu, % Contained Pounds x 1000 Ktons Total Cu, % Contained Pounds x 1000 Ktons Total Cu, % Contained Pounds x 1000 Ktons Total Cu, % Contained Pounds x 1000
MacArthur
Leach Cap & Ovb 0.05 13,781 0.102 28,215 5,816 0.072 8,326 19,597 0.093 36,542 174 0.078 271
Oxide 0.05 90,132 0.184 331,686 40,012 0.145 116,035 130,144 0.172 447,721 2,568 0.120 6,163
Mixed 0.05 8,070 0.206 33,248 7,606 0.209 31,793 15,676 0.207 65,041 585 0.211 2,469
Sulfide                          
Total 111,983 0.176 393,150 53,434 0.146 156,154 165,417 0.166 549,304 3,327 0.134 8,903
North Ridge
Leach Cap & Ovb 0.06 4,704 0.096 9,060 10,710 0.094 20,031 15,414 0.094 29,091 2,970 0.077 4,574
Oxide 0.06 16,943 0.145 49,135 37,649 0.141 106,170 54,592 0.142 155,305 2,482 0.135 6,701
Mixed 0.06 17,132 0.243 83,262 15,178 0.220 66,783 32,310 0.232 150,045 1,474 0.280 8,254
Sulfide                          
Total 38,779 0.182 141,457 63,537 0.152 192,984 102,316 0.163 334,441 6,926 0.141 19,529
Gallagher
Leach Cap & Ovb 0.06 23 0.100 46 988 0.091 1,805 1,011 0.092 1,851 345 0.092 634
Oxide 0.06 10,301 0.163 33,581 28,130 0.153 86,078 38,431 0.156 119,659 10,728 0.147 31,540
Mixed 0.06 2,247 .0213 9,572 8,997 0.192 34,548 11,244 0.196 44,121 1,843 0.197 7,261
Sulfide                          
Total 12,571 0.172 43,199 38,115 0.161 122,431 50,686 0.163 165,631 12,916 0.153 39,436
Total
Leach Cap & Ovb 0.07 18,508 0.101 37,322 17,514 0.086 30,162 36,022 0.094 67,484 3,489 0.079 5,479
Oxide 0.07 117,376 0.177 414,402 105,791 0.145 308,283 223,167 0.162 722,685 15,778 0.141 44,405
Mixed 0.07 27,449 0.230 126,082 31,781 0.209 133,125 59,230 0.219 259,207 3,902 0.230 17,985
Sulfide                          
Total 163,333 0.177 577,806 155,086 0.152 471,570 318,419 0.165 1,049,375 23,169 0.146 67,868

Notes:  Mineral resources are reported in situ and are current as at March 17, 2025.

Mineral resources are not mineral reserves and do not have demonstrated economic viability.

IMC is the Firm responsible for the estimate.


 

11.5 FACTORS THAT MAY AFFECT THE MINERAL RESOURCE ESTIMATE

The deposits at Yerington and MacArthur are of a style of porphyry copper that is well known from past mining activity and completed drilling. Any issues arising in relation to relevant technical and economic factors likely to influence the process of economic extraction can be resolved with further study and test work. Factors that may affect the Mineral Resources include:

  • metal price and exchange rate assumptions
  • changes to the assumptions used to generate the copper grade cut-off grade
  • redefinition of Yerington Copper Project geological model to refine grade interpolation
  • changes in local interpretations of mineralization geometry and continuity of mineralized zones
  • changes to interpretation of the contact between the redox surfaces
  • density and domain assignments
  • changes to geotechnical, mining, and metallurgical recovery assumptions
  • change to the input and design parameter assumptions that pertain to the conceptual pit designs constraining the mineral resources
  • assumptions as to the continued ability to access the site, retain mineral and surface rights titles, maintain environment and other regulatory permits, and maintain the social license to operate

The Yerington Copper Project is to advance through additional stages of study that provide sufficient time before a final decision is made to address any shortfalls in information regarding the project. This could include additional drilling, test work and engineering studies to mitigate identified issues with the estimates.

There are no other environmental, legal, title, taxation, socioeconomic, marketing, political or other relevant factors known to the QPs that would materially affect the estimation of mineral resources that are not discussed in this report.

11.6 QP ADEQUACY STATEMENT

TMAC and IMC note that the deposits at Yerington and MacArthur are of a style of porphyry copper that is well known from past mining activity and completed drilling..


 

12.0 MINERAL RESERVE ESTIMATES

12.1 SUMMARY

The reserves for the Yerington Copper Project are based on the conversion of Measured and Indicated resources within the Yerington, VLT, MacArthur, Gallagher, and North Ridge open pits.

Table 12.1 shows the total reserves for the Yerington Copper Project. Some variation may exist due to rounding.

Table 12.1: Yerington Copper Project - Proven and Probable Reserves - May 31, 2025
  Proven Probable Total
Ore
Type
Tons
(kt)
Grade
(Cu%)
Copper
Mlbs
Tons
(kt)
Grade
(Cu%)
Copper
Mlbs
Tons
(kt)
Grade
(Cu%)
Copper
Mlbs
Oxide 144,519 0.19 560.0 128,234 0.14 366.7 272,753 0.17 926.7
Sulfide 81,037 0.30 481.1 152,761 0.24 732.3 233,798 0.26 1,213.3
Total 225,556 0.23 1,041.1 280,995 0.20 1,099.0 506,551 0.21 2,140.0

Note: This mineral reserve estimate has an effective date of May 31, 2025, and is based on the mineral resource estimates for Yerington and VLT dated March 17, 2025 by T. Maunula & Associates Consulting Inc. and MacArthur Area Pits dated March 17, 2025 by Independent Mining Consultants Inc. The Mineral Reserve estimate was completed under the supervision of Gordon Zurowski, P.Eng. of AGP, who is a Qualified Person as defined under S-K 1300. Mineral Reserves are stated within the final pit designs based on a $3.90/lb copper price.

1. The copper cutoff grades used were:

  • Yerington Pit - 0.05% copper (oxide ROM), 0.09% copper (sulfide)
  • VLT Pit - 0.03% copper (oxide ROM)
  • MacArthur - 0.05% copper (oxide ROM)
  • Gallagher Pit - 0.07% copper (oxide ROM)
  • North Ridge Pit - 0.06% copper (oxide ROM)

2. Open pit mining costs varied by area and elevation with waste of $2.53/t, oxide material at $2.49/t and sulfide at $2.22/t.  Incremental costs of $0.027/25ft bench were applied below the 4225 foot elevation for waste and oxide and 0.024/t for sulfide material below the 4225 foot elevation.

3. Processing costs were based on the use of an acid plant at site with crushing for sulfide material. The processing costs by pit area were:

  • Yerington Pit - $2.00/t ore (oxide ROM), $4.44/t (sulfide)
  • VLT Pit - $1.34/t ore (oxide ROM)
  • MacArthur - $1.67/t ore (oxide ROM)
  • Gallagher Pit - $2.14/t ore (oxide ROM)
  • North Ridge Pit - $1.73/t ore (oxide ROM)
  • G&A costs were $0.49/t ore.

4. Process copper recoveries varied by material and area and were as follows:

  • Yerington Pit - 70% (oxide ROM), 74% (sulfide)
  • VLT Pit - 75% (oxide ROM)
  • MacArthur - 55% (oxide ROM)
  • Gallagher Pit - 54% (oxide ROM)
  • North Ridge Pit - 55% (oxide ROM)

 

12.2 GEOTECHNICAL AND PIT SLOPES

Pre-feasibility level pit slope geotechnical recommendations were developed for the Yerington Copper Project following the collection of field data and the review of previous studies. The pit slope geotechnical field program that supported this work included oriented core drilling, soil sampling, test pits, and outcrop structure mapping.

Open pit highwall slope angle criteria vary by area and pit, as shown in Table 12.2.

Table 12.2: Pit Slope Parameters (Overall Angles)
Lithologic Zone Yerington MacArthur
Alluvium 40 40
North Wall 42 40
South Wall 45 40

The recommended pit shell slope parameters are based on the results of kinematic analysis. The MacArthur open pit does not vary lithologically or structurally in the same manner as the Yerington pit; thus, recommendations for all lithologic zones within it are equivalent.

For detailed pit designs, the parameters in Table 12.3 were used for bench height, bench face angle, berm width, and space between berms. Single benching was assumed.

Table 12.3: Pit Design Parameters (Detailed)
Pit Area Inter-ramp
Angle
Bench Face
Angle
Bench
Height
Berm
Spacing
Berm
Width
(degrees) (degrees) (ft) (ft) (ft)
Alluvium 36 65 25 25 20
Yerington - North Walls 37 70 25 25 20
Yerington - South Walls 39 75 25 25 20
VLT 27 40 25 25 20
MacArthur - North Walls 27 65 25 25 20
MacArthur - South Walls 45 65 25 25 20
Gallagher - All Walls 45 65 25 25 20
North Ridge - All Walls 45 65 25 25 20

12.3 ECONOMIC PIT SHELL DEVELOPMENT

The final pit designs are based on pit shells using the Lerch-Grossman procedure in Hexagon Mining's MinePlan software. The parameters for the pit shells are shown in Table 12.4.

Table 12.4: Open Pit Optimization Parameters
Description Units Yerington VLT MacArthur Gallagher North Ridge
Resource Model
Resource class   M+I M+I M+I M+I M+I


 

Table 12.4: Open Pit Optimization Parameters
Description Units Yerington VLT MacArthur Gallagher North Ridge
Block/Bench Height ft 25 25 25 25 25
Metal Prices
Cu US$/lb 3.90 3.90 3.90 3.90 3.90
Royalty % 2.5 2.5 2.5 2.5 2.5
Payable Metal and Deductions            
Cu Payable % 99.5 99.5 99.5 99.5 99.5
Cathode Rail Cost US$/ton 50 50 50 50 50
Cathode Port Cost US$/ton 20 20 20 20 20
Cathode Shipping Cost US$/ton 30 30 30 30 30
Net Metal Price Calculation
Cu Payable % 99.5 99.5 99.5 99.5 99.5
Cathode Rail Cost US$/lb 0.025 0.025 0.025 0.025 0.025
Cathode Port Cost US$/lb 0.010 0.010 0.010 0.010 0.010
Cathode Shipping Cost US$/lb 0.015 0.015 0.015 0.015 0.015
Total Transportation Cost US$/lb 0.050 0.050 0.050 0.050 0.050
Subtotal Copper Price US$/lb 3.83 3.83 3.83 3.83 3.83
Less Royalty US$/lb 0.10 0.10 0.10 0.10 0.10
Net Copper Price US$/lb 3.73 3.73 3.73 3.73 3.73
Process Recoveries
Oxide - ROM % 70 75 55 54 55
Sulfide - Nuton % 74 - - - -
Mining Costs
Base Elevation ft 4225 4225 4225 4225 4225
Waste Base Rate US/t moved 2.53 2.53 2.53 2.53 2.53
Oxide Feed US/t moved 2.49 2.49 2.49 2.49 2.49
Sulfide Feed US/t moved 2.22 2.22 2.22 2.22 2.22
Incremental Rate Below Base Elevation           
Waste Base Rate US/t moved 0.027 0.027 0.027 0.027 0.027
Oxide Feed US/t moved 0.027 0.027 0.027 0.027 0.027
Sulfide Feed US/t moved 0.024 0.024 0.024 0.024 0.024
Process and G&A Costs
Oxide Processing - ROM US$/t feed 2.00 1.34 1.67 2.14 2.02
Sulfides Processing - Nuton US$/t feed 4.44        
G&A Cost US$/t feed 0.49 0.49 0.49 0.49 0.49
Process + G&A
Oxide - ROM US$/t feed 2.49 1.83 2.16 2.63 2.51
Sulfides - Nuton US$/t feed 4.94        
Marginal Cutoff Grades
Oxide - ROM % Copper 0.05 0.03 0.05 0.07 0.06
Sulfides - Nuton % Copper 0.09        


 

Only Measured and Indicated resources were used in the pit shell generation. Pit optimization shells were completed for each area. These were plotted to determine the ultimate shell for pit design purposes and to help in the pit development phase determination.

A restriction was placed on the pit optimization runs for the Yerington pit so that pit shells were not expanded to the east past the highway into proximity with the Walker River. The existing pit crest was used as that limit. The shell chosen for the Yerington pit design was Revenue Factor (RF) = 0.9 or $3.51/lb copper. This is where 98% of the RF=1 pit revenue was achieved, with only 67% of the waste material needed to be moved.

For the VLT area, pits were generated, but the RF=1 pit was selected to fully remove the material where the sulfide heap leach facility (or HLF) would be placed. In later phased expansions, the sulfide facility will expand onto the current VLT location.

Pit optimization for the MacArthur area was completed in the same manner. Various pits were examined from a phasing perspective, but the RF=1.0 pit was selected as a single phase. This shell was used for the designs in all three areas (MacArthur, Gallagher, and North Ridge) of MacArthur.

12.4 CUT-OFF

The marginal cut-off was used for the statement of reserves for the Yerington Copper Project.  The cutoffs assume the use of an acid plant on site to reduce the cost of acid and thus the processing cost.

The various cutoffs employed are shown in Table 12.5. Only the Yerington pit has sulfide material for processing.

Table 12.5: Yerington Copper Project Cutoffs
Pit Area Oxide - ROM (% Cu) Sulfide (% Cu)
Yerington 0.05 0.09
VLT 0.03 -
MacArthur 0.05 -
Gallagher 0.07 -
North Ridge 0.06 -

12.5 DILUTION AND MINING LOSSES

The resource models are all whole block models. Some dilution is inherent within the blocks. Due to the nature of the deposit grade from the assays, it was interpolated over the full volume of the block to arrive at a diluted smooth block grade.

The contacts between feed and waste are transitional, typical of copper projects. For the PFS, dilution has been assumed to equal the feed loss from mining. Therefore, no additional dilution has been included in the tonnages in the mine designs.


 

12.6 MINE DESIGN

The pit designs vary by area. For Yerington, a multi-phase approach was developed to allow the mining of the first two phases within the current wall slopes. This provides initial feed material while the sides of the pit are pushed back, allowing the overall pit to go deeper than previously mined.

The VLT area is mined in its entirety. The sulfide heap facility will grow into the area currently occupied by the VLT.

MacArthur pit designs are single-phase but composed of different areas. The Gallagher pit is smaller and does not afford room for phasing. North Ridge could join with MacArthur, so it was mined in two phases, with the second phase connecting to MacArthur. The MacArthur area has already been opened due to previous development, and mining a larger area allows for efficient operations to occur, helping to keep the mining cost down.

Equipment sizing for ramps is based on the use of 100-ton rigid frame trucks. The ramp width is designed for a truck with an operating width of 23 ft. This means that single lane access is 70 ft (2x operating width plus berm and ditch), and double lane widths are 93 ft (3x operating width plus berm and ditch). Ramp uphill gradients are 10% in the pit and 8% uphill on the dump access roads. Working benches were designed for 115 ft 130 ft minimum on pushbacks, although some push-backs do work in a retreat manner to facilitate access and minimize waste stripping.

12.7 MINE SCHEDULE

The mining rate targets the crushing of a maximum of 34 Mtpa of Nuton feed (sulfide) from Year 3 onwards. There is an initial ramp-up period to allow the Nuton process to come online as the sulfide material is released from the Yerington pit. Recovered copper capacity peaks at 176.8 Mlbs in Year 7 but averages 129.0 Mlbs from Year 3 onwards after the sulfide leaching starts.

Oxide and sulfide material will be handled differently depending on their point of origin.  Yerington oxide materials which include the Yerington oxide, and VLT are assumed to be placed on the Oxide Heap Leach facility as run of mine (ROM).  MacArthur oxides are also ROM but placed in a separate facility adjacent to the MacArthur pits.

The sulfide material destined for the Nuton Heap Leach area is first sent to a crushing facility located northwest of Yerington pit. The material will be crushed, agglomerated, and then conveyed and stacked on the HLF.

Total life of mine heap leach production will be 506.6 million tons grading 0.21% copper.  The Yerington pit will deliver 233.8 million tons of sulfide material grading 0.26% copper to the Nuton Heap Leach.  Yerington oxides (pit and VLT) will total 108.0 million tons grading 0.16 % copper. MacArthur produces 164.8 million tons of oxide leach material with an average copper grade of 0.18%.

The overall mine strip ratio for the PFS is 0.31:1 (waste:feed). MacArthur has a strip ratio of 0.18:1 (waste:feed) and Yerington (pit + VLT) is 0.38:1 (waste:feed).


 

12.8 MINERAL RESERVES STATEMENT

The reserves for the Yerington Copper Project are based on the conversion of the Measured and Indicated Mineral Resources in the current mine plan within the Yerington, VLT, MacArthur, North Ridge and Gallagher open pits.  Measured Mineral Resources are converted directly to Proven Reserves. Indicated Mineral Resources are converted directly to Probable Reserves.

The total Mineral Reserves for the Yerington Copper project are shown in Table 12.6. Some variation may exist due to rounding.

Table 12.6: Proven and Probable Reserves - May 31, 2025
Pit
Area
  Proven Probable Total
Ore
Type
Cutoff
Grade
(Cu%)
Tons
(kt)
Grade
(Cu%)
Copper
Mlbs
Tons
(kt)
Grade
(Cu%)
Copper
Mlbs
Tons (kt) Grade
(Cu%)
Copper
Mlbs
Yerington Area
Yerington Pit                  
Oxide 0.05 34,295 0.22 148.3 41,785 0.16 137.6 76,080 0.19 285.9
Sulfide 0.09 81,037 0.30 481.1 152,761 0.24 732.3 233,798 0.26 1,213.3
VLT                  
Oxide 0.03 - - - 31,896 0.09 55.6 31,896 0.09 55.6
Sulfide - - - - - - - - - -
Yerington Subtotal                  
Oxide 0.05 34,295 0.22 148.3 73,681 0.13 193.1 107,976 0.16 341.5
Sulfide - 81,037 0.30 481.1 152,761 0.24 732.3 233,798 0.26 1,213.3
 
MacArthur Area
MacArthur                  
Oxide 0.05 89,425 0.19 330.9 27,185 0.16 87.3 116,610 0.18 418.3
Sulfide - - - - - - - - - -
Gallagher                  
Oxide 0.07 3,237 0.22 13.9 5,527 0.18 20.3 8,764 0.20 34.2
Sulfide - - - - - - - - - -
North Ridge                  
Oxide 0.06 17,563 0.19 66.8 21,840 0.15 65.9 39,403 0.17 132.7
Sulfide - - - - - - - - - -
MacArthur Area Subtotal                  
Oxide   110,224 0.19 411.7 54,553 0.16 173.5 164,777 0.18 585.2
Sulfide   - - - - -        
Reserves Total
Total                  
Oxide   144,519 0.19 560.0 128,234 0.14 366.7 272,753 0.17 926.7


 

Table 12.6: Proven and Probable Reserves - May 31, 2025
Pit
Area
  Proven Probable Total
Ore
Type
Cutoff
Grade
(Cu%)
Tons
(kt)
Grade
(Cu%)
Copper
Mlbs
Tons
(kt)
Grade
(Cu%)
Copper
Mlbs
Tons (kt) Grade
(Cu%)
Copper
Mlbs

Sulfide

 

81,037

0.30

481.1

152,761

0.24

732.3

233,798

0.26

1,213.3

Total

225,556

0.23

1,041.1

280,995

0.20

1,099.0

506,551

0.21

2,140.0

Note: This mineral reserve estimate has an effective date of May 31, 2025, and is based on the mineral resource estimates for Yerington and VLT dated March 17, 2025, by AGP Mining Consultants Inc. and MacArthur Area Pits dated March 17, 2025, by Independent Mining Consultants Inc. The Mineral Reserve estimate was completed under the supervision of Gordon Zurowski, P.Eng. of AGP, who is a Qualified Person as defined under S-K 1300. Mineral Reserves are stated within the final pit designs based on a $3.90/lb copper price.

1. The copper cutoff grades used were:

  • Yerington Pit - 0.05% copper (oxide ROM), 0.09% copper (sulfide)
  • VLT Pit - 0.03% copper (oxide ROM)
  • MacArthur - 0.05% copper (oxide ROM)
  • Gallagher Pit - 0.07% copper (oxide ROM)
  • North Ridge Pit - 0.06% copper (oxide ROM)

2. Open pit mining costs varied by area and elevation with waste of $2.53/t, oxide material at $2.49/t and sulfide at $2.22/t.  Incremental costs of $0.027/25ft bench were applied below the 4225-foot elevation for waste and oxide and 0.024/t for sulfide material below the 4225-foot elevation.

3. Processing costs were based on the use of an acid plant at site with crushing for sulfide material. The processing costs by pit area were:

  • Yerington Pit - $2.00/t ore (oxide ROM), $4.44/t (sulfide)
  • VLT Pit - $1.34/t ore (oxide ROM)
  • MacArthur - $1.67/t ore (oxide ROM)
  • Gallagher Pit - $2.14/t ore (oxide ROM)
  • North Ridge Pit - $1.73/t ore (oxide ROM)
  • G&A costs were $0.49/t ore.

4. Process copper recoveries varied by material and area and were as follows:

  • Yerington Pit - 70% (oxide ROM), 74% (sulfide)
  • VLT Pit - 75% (oxide ROM)
  • MacArthur - 55% (oxide ROM)
  • Gallagher Pit - 54% (oxide ROM)
  • North Ridge Pit - 55% (oxide ROM)

12.9 FACTORS THAT MAY AFFECT THE MINERAL RESERVE ESTIMATE

The QP has not identified any known legal, political, environmental, or other risks that would materially affect the potential development of the Mineral Reserves.

Risks that could materially affect the reserve include mining selectivity near the ore contacts, slope stability and assumed process recoveries for given rock types. These are considered manageable risks which will be mitigated as more test work and operating experience is obtained.


 

12.10 QP ADEQUACY STATEMENT

The QP and AGP believe the assumptions, parameters, and methods used to prepare the Mineral Reserves Statement is appropriate and consistent with other current operations and studies for similar facilities and is suitable for use in establishing reasonable prospects for economic extraction.  The Mineral Reserves are estimated and prepared in accordance with the U.S. Securities and Exchange Commission (US SEC) Regulation S-K subpart 1300 rules for Property Disclosures for Mining Registrants (S-K 1300).


 

13.0 MINING METHODS

13.1 INTRODUCTION

The Yerington Copper Project is located adjacent to the city of Yerington, Nevada. Historic open pit mining has occurred both at the Yerington and MacArthur pits. It has been established that there are still significant open pit mineral resources in the area which form the basis for this PFS.

Project Mineral Resources include the Yerington deposit, Vat Leach Tails (VLT) stockpile and the MacArthur deposits (MacArthur, Gallagher, and North Ridge). Open pit mining offers the most reasonable approach for development of the deposits in AGP's opinion considering current metal pricing levels, knowledge of the mineralization and previous mining activities. This is based on the size of the resource, tenor of the grade, grade distribution and proximity to topography for the deposits.

The PFS mine schedule totals 506.6 Mt of heap leach feed grading 0.21% copper over a processing life of just under 12 years. Open pit waste tonnages from the various areas total 159.8 Mt and will be placed into waste storage areas adjacent to the open pits. The overall open pit strip ratio is 0.32:1 (waste: heap feed).

Three heap leach facilities will be used to provide copper solution for the SXEW facility.  One process stream will utilize the Nuton process for the leaching of sulfide feed from the Yerington pit and be located near the Yerington pit. The other process stream will employ conventional oxide copper leaching technology with run of mine (ROM) material. One heap leach facility (HLF) will be located at Yerington for the Yerington oxide and VLT material. The other will be adjacent to the MacArthur pits and be for ROM sized material.  The Nuton facility will have a peak feed rate of 35 Mtpa through a crushing plant.  The Yerington pit is the only supply of sulfide material for the PFS.

The current mine plan includes minimal pre-stripping as the bottom of the existing pit still contains material suitable for placement on a HLF with conventional leaching and use of the Nuton process for the sulfide materials.

The open pit mining starts in Year 1 and continues uninterrupted until early in Year 12.

13.2 MINING GEOTECHNICAL

13.2.1 Yerington Pit Area

The Yerington open pit has not been actively mined since 1978. Pre-Feasibility level pit slope geotechnical recommendations were developed for the Yerington Copper Project following collection of field data and review of previous studies (Seegmiller, 1979; Golder, 2008). The pit slope geotechnical field program conducted in support of this work included oriented core drilling, soil sampling, test pits, and outcrop structure mapping. Data sources are inclusive of active operating periods and post-closure.

Development of PFS level pit slope geotechnical recommendations for the Yerington Copper Project included both a kinematic analysis (inter-ramp scale) and a global slope stability analysis (assuming failure through the intact rock mass). The kinematic analysis focuses on potential slope failure modes based on the structural fabric (faults, joints, etc.) of the rock mass, including planar, wedge, and toppling failure modes for a range of potential inter-ramp slopes and pit slope azimuths.

The global slope stability analysis uses a simplified limit-equilibrium approach to assess failure through the rock mass, independent of structural controls.

It is noted that the majority of failures in rock slopes are governed by structural features, therefore the results of the kinematic analyses are typically used to set the basic geotechnical recommendations for pit slopes.

The primary rock lithology within the pit consists of quartz monzonite units overlain by a thick, cemented Quaternary alluvial fan package consisting of sands and gravels. Rock mass exposures in the current Yerington pit are limited due to the thick alluvial package (tens to several tens of ft thick) and water present in the pit. In general, the existing alluvial high walls are cut very steeply (60° to 90°) with significant debris slopes due to long-term weathering and erosion. The majority of the mined pit benches in the alluvium and rock mass are full of debris that has accumulated over the years of inactivity. The exposed rock mass characteristics suggest that slope performance across the pit varies, depending on the dominant rock fabric in combination with wall orientation.


 

Specifically, there appears to be two structural domains in the North Wall of the Yerington Pit, as presented in Figure 13.1. 

Source: NewFields 2025

Figure 13.1: Structural Domains of the North Wall of the Yerington Pit

Domain 1 of the North wall is located west of the Sericite Fault identified by Seegmiller (1979). In this domain, the rock mass fabric dips steeply into the wall (toward the North) (as mapped by Seegmiller, 1979). The pit wall orientation is nearly parallel to the rock fabric in this location. The combination of steeply dipping fabric with parallel wall orientation has given rise to multi-bench toppling in the upper rock benches and tension cracks that have developed in the alluvium package.

The rock mass in Domain 1 also appears to be highly altered and low strength. The visual estimate of the rock mass's Geological Strength Index [GSI] is between 35 and 45 (poor to fair, very blocky rock mass quality).

Domain 2 of the North wall is generally located east of the Sericite Fault. This domain is characterized by an increase in wedge-forming rock fabric (alternating east-west joint planes). Several faults (continuous and discontinuous) were also noted in the exposed rock benches in Domain 2. The faults appear dipping into the wall (toward the North), but exposures were limited and could not be easily traced.

The rock mass in Domain 2 appears to be altered differently than in Domain 1 and has moderate strength and quality. The visual estimate of the GSI of the rock mass in Domain 2 is between 40 and 50 (poor to fair, very blocky rock mass quality). The rock mass adjacent to the observed faults appears to be of lower quality.

The South Wall of the Yerington pit appears to be dominated by mainly wedge-forming rock fabric (e.g., jointing). It is noted that this observation may be biased due to the limited rock mass exposure on the South Wall. There are two wedge failures exposed on the South Wall; the locations are shown in Figure 13.2. The first wedge failure appears to be a small single-bench failure (though it may extend further beneath the pit lake) on the access road on the east side of the South Wall. The second wedge failure is a multi-bench failure in the central portion of the South Wall. The visual estimate of the GSI of the rock mass exposed in the South Wall is between 35 to 45 (poor to fair, blocky rock mass quality).


 

Source: NewFields 2025

Figure 13.2: Observed Wedge Failures in South Wall

Structural data (faults and joints) for the Yerington Pit were collected from bench-scale mapping in July of 2024 by NewFields, and an oriented Core Hole was drilled in 2024 to augment the existing database on the site geology and ore-bearing zones. The orientation data collected in the field were digitized for evaluation using the DIPS graphical and statistical analysis software package. Part of this analysis involved the construction of representative stereonets for different areas of the pit. This allows for evaluation of the spatial distribution and persistence of structural trends and features. Stereonets of structural data for the Yerington pit were developed for the North and South Highwalls. While structural differences were observed within the North Highwall (e.g., Domain 1 and 2), there is insufficient data to conduct a separate kinematic analysis on the two domains. All the North Highwall data were combined into one dataset for this PFS work. The combined North Highwall stereonet is presented in Figure 13.3. As shown, the dominant rock fabric dips steeply into the high wall, which agrees with the pit wall observations and toppling features.

Source: NewFields 2025

Figure 13.3: Yerington North Highwall Stereonet

The kinematic analyses considered planar, wedge, and toppling modes of failure. The results of the North Wall kinematic analyses found acceptable percentages for planar and wedge features for a wide range of potential inter-ramp slope angles; however, toppling features were relatively high. An acceptable number of toppling features was found at inter-ramp slopes of 42° or lower using an average slope dip direction of 210°.

Figure 13.4 presents the stereonet for the South Wall of the Yerington pit. The stereonet exhibits three to four dominant structural groups, giving rise to potential wedge-type slope issues noted previously. Toppling and planar features were much less prevalent on the South Wall. The South Wall kinematic analyses found acceptable percentages for planar and toppling features for a wide range of potential inter-ramp slope angles; however, wedge features were higher than acceptable. An acceptable number of wedge features were found at inter-ramp slopes of 45° or lower using an average slope dip direction of 20°.


 

Source: NewFields 2025

Figure 13.4: Yerington South Highwall Stereonet

Global Stability analyses were also conducted for the North and South highwalls using a limit-equilibrium (LE) approach. Given the limited level of geotechnical data, the LE models were simplified using the following assumptions:

  • two lithologic units, alluvium and primary rock
  • shear strength of the alluvium of 40° friction and cohesion of 500 pounds per square foot (psf) based on back-analyses from Seegmiller (1979)
  • simplified shear strength of the rock mass of 34° friction and cohesion of 3,000 psf.; these values are similar to the values derived by Seegmiller (1979) and are consistent with the range of GSI values observed in the rock mass
  • groundwater elevation of 4360 ft. based on Seegmiller (1979) pre-mining level
  • nominal slope depressurization 500 ft. behind the mined pit slope
  • nominal maximum pit depth of 750 ft from pit rim

The results of the Global Stability analyses for the North and South Highwalls are presented in Figure 13.5 and Figure 13.6, respectively. As shown, the estimated Factor of Safety (FoS) for the North and South highwalls is 1.2, which is considered as an acceptable indicative value for this study.

Source: NewFields 2025

Figure 13.5: North Highwall Global Stability


 

Source: NewFields 2025

Figure 13.6: South Highwall Global Stability

Basic pit slope geotechnical recommendations were developed using the results of the kinematic analyses. Pit slope maximum bench heights were fixed at 25 ft to be consistent with the existing pit benches. It is assumed that all the pit slopes will be depressurized using a combination of pumping wells and horizontal drain holes (HDHs). This is consistent with previous mining operations. Conventional drill & blast practices should be adopted (i.e. trim and pre-shearing) to minimize rock damage. The cemented alluvium package appears to be competent and has been cut steeply (over 60°). It is recommended these slopes be flattened to a maximum inter-ramp angle of 40°, either by dozer trimming or benching. If the alluvium is to be benched, the minimum bench width should be 20 ft. A minimum 25-foot bench should be developed between the alluvium-rock contact. This bench is required to capture surface water run-off and debris from the alluvium during operations.

For the North Highwall:

  • A maximum inter-ramp slope angle in primary rock of 42° is recommended
  • inter-ramp slopes exceeding 300 ft. should be decoupled with a ramp or a minimum 25-foot geotechnical bench
  • minimum bench width of 20 ft. is recommended

For the South Highwall:

  • a maximum inter-ramp slope angle in primary rock of 45° is recommended
  • inter-ramp slopes exceeding 300 ft. should be decoupled with a ramp or a minimum 25 foot geotechnical bench
  • minimum bench width of 20 ft is recommended

13.2.2 MacArthur

The MacArthur open pit has not been actively mined since the late 1990's. The pit is shallow and dry, consisting of a few benches and no evidence of groundwater or seepage in its existing configuration. Heatwole (1978) reports that the MacArthur deposit is an outcropping oxidized porphyry occurrence located approximately five miles north of the Yerington open pit. The host rock is a Jurassic quartz monzonite intruded by northwest trending dikes which dip moderately to the north. Rock mass exposures within the MacArthur pit are limited to observation of pit benches. For the most part, the rock mass is blocky to very blocky. A visual estimate of the GSI of the rock mass in the pit is between 40 to 50 (poor to fair, very blocky rock mass quality). The rock mass adjacent to the observed faults and alteration zones appears to be of lower quality.


 

Source: AGP 2025

Figure 13.7: Aerial imagery showing configuration of MacArthur open pit as of December, 2020.

Structural data (faults and joints) for the MacArthur pit were collected from bench-scale mapping performed by NewFields in July of 2024. The configuration of the MacArthur pit along with section traces from the surface mapping are shown in Figure 13.7. The orientation data collected in the field were digitized for evaluation in the DIPS graphical and statistical analysis software for orientation data. The stereonet for North Wall exposures is presented in Figure 13.8, showing steeply dipping east-west features, with a secondary west-dipping structural set. The stereonet for South Wall exposures is presented in Figure 13.9. The South Wall stereonet shows a single dominant east-west oriented group dipping steeply toward the South. This suggests that toppling may be an issue for the South Wall as the mine is developed. It is noted that no toppling issues have been observed on the South Wall.

The kinematic analyses considered planar, wedge, and toppling modes. The results of the North Wall kinematic analyses found acceptable percentages for planar, wedge, and toppling features at inter-ramp slopes of 40° or lower using an average slope dip direction of 180°. The results of the South Wall kinematic analyses found acceptable percentages for planar, wedge, and toppling features at inter-ramp slopes of 40° or lower using an average slope dip direction of 0°.

Source: NewFields 2025

Figure 13.8: North Highwall Stereonet for MacArthur Open Pit


 

Source: NewFields 2025

Figure 13.9: South Highwall Stereonet for MacArthur Open Pit

Global Stability analyses were conducted for the North and South highwalls using a LE approach. Given the limited level of geotechnical data, the LE models were simplified using the following assumptions:

  • two lithologic units, alluvium and primary rock
  • shear strength of the alluvium of 40° friction and cohesion of 500 pounds per square foot (psf) based on back-analyses from Seegmiller (1979)
  • simplified shear strength of the rock mass of 34° friction and cohesion of 1,500 psf. These values are similar to the values derived for the Yerington pit by Seegmiller (1979) and are consistent with the range of GSI values observed in the rock mass; note a lower value of cohesion was used based on the block-nature of the observed rock mass
  • no groundwater encountered within the pit
  • nominal maximum pit depth of 150 ft

The results of the Global Stability analyses for the North and Highwall is presented in Figure 13.10. As shown, the estimated FoS for the North and South highwall is 1.7, which is considered an acceptable indicative value for this study.

Source: NewFields 2025

Figure 13.10: Global Stability Analysis for the North and South Highwalls of the MacArthur Open Pit


 

Basic pit slope geotechnical recommendations were developed using the results of the kinematic analyses. Pit slope maximum bench heights were fixed at 25 ft to be consistent with the existing pit benches. If needed, it is assumed that all the pit slopes will be depressurized using a combination of vertical pumping wells and HDHs. It is noted that at the time of these evaluations, groundwater is not expected to be encountered in the future pit development due to its shallow depth. Conventional drill & blast practices should be adopted (i.e. trim and pre-shearing) to minimize rock damage. It is recommended the slopes developed in the alluvium unit be flattened to a maximum inter-ramp angle of 40°, either by dozer trimming or benching. If the alluvium is to be benched, the minimum bench width should be 20 ft. A minimum 25-foot bench should be developed between the alluvium-rock contact. This bench is required to capture surface water run-off and debris from the alluvium during operations.

For the North and South Highwalls:

  • a maximum inter-ramp slope angle in primary rock of 40° is recommended
  • inter-ramp slopes exceeding 300 ft. should be decoupled with a ramp or a minimum 25 foot geotechnical bench
  • minimum bench width of 20 ft. is recommended

It is noted that the recommendations presented herein are based on the available data at the time of this report. It is further noted that this data was limited in nature due to the minimal exposure of rock in the pits and core hole data. The recommendations presented are considered to be suitable for a PFS-Level study.

13.2.3 Pit Slope Parameters

Table 13.1 shows the overall slope angles applied for the resource constraining pit shells and pit optimizations in the Yerington Copper Project PFS by area.

Table 13.1: LG Shell Slope Parameters (Overall Angles)
Lithologic Zone Yerington MacArthur
Alluvium 40 40
North Wall 42 40
South Wall 45 40

The recommended pit shell slope parameters are based on the results of kinematic analysis. The MacArthur open pit does not vary lithologically or structurally in the same manner as the Yerington pit, thus recommendations for all lithologic zones within it are equivalent.

13.3 OPEN PIT

13.3.1 Geologic Model Importation

The 2025 resource estimates for the Yerington and VLT deposits were created using Hexagon's MinePlan software for mineralization domains, estimation, and block modelling.  The block model was provided in the MinePlan format for open pit mine engineering purposes.

The 2025 MacArthur resource estimates were created in IMC resource modeling software, exported in CSV format and a mining model was then created for open pit planning.

Framework details of the open pit block models by area are provided in Table 13.2. The final mine planning model items are displayed in Table 13.3, Table 13.4, and Table 13.5. MinePlan® was used for the mining portion of the PFS, utilizing their Lerchs Grossman (LG) shell generation, pit and dump design and mine scheduling tools.

Measured and Indicated Mineral Resources were used in the PFS. Inferred mineral resources are treated as waste material.

Table 13.2: Open Pit Model Framework
Framework Description Yerington VLT MacArthur
MinePlan® file 10 (control file) YER10.dat vlt10.dat mcft10.dat
MinePlan® file 15 (model file) Yer15.in1 vlt15.24b Mcft24.15
X origin (m) 2446400 2446400 2430000


 

Table 13.2: Open Pit Model Framework
Framework Description Yerington VLT MacArthur
Y origin (m) 14661000 14670500 14680000
Z origin (m) (max) 2900 2900 2650
Rotation (degrees clockwise) 0 0 0
Number of blocks in X direction 360 180 640
Number of blocks in Y direction 320 280 720
Number of blocks in Z direction 100 48 125
X block size (ft) 25 25 25
Y block size (ft) 25 25 25
Z block size (ft) 25 25 25

Table 13.3: Open Pit Model Item Descriptions for Yerington
Field
Name
Min Max Precision Units Comments
TOPO 0 100 0.01 % Percent below topographic surface Base 2024 Lidar
TOP13 0 1 0.001 - Factor 0.01-1 below topographic surface Base 2024 Lidar
ROCK1 0 100 1 CODE Overburden 20, Oxide 31, Sulfide 41
TCUK1 0 10 0.0001 % Total Cu% OK Ordinary Kriging Grade Estimate
ASCU 0 10 0.0001 % Inverse Distance Grade Estimate (Not used)
RCLS 0 0 6 - Smoothed resource classification, 1,2,3 (4=undefined)
TF 0 100 0.01 cf/ton Tonnage factor, 12.62
CLASS 0 0 500 - Smoothed resource classification (RCLS * 100 + ROCK1), 131,141,231,241,331,341 (499=undefined)
RSCOD -1 1 1 - Hwy mining restriction (-1=no mining, 1=mining allowed)
RSCO2 -1 1 1 - West Wall and Hwy mining restriction and Pit Crest, (-1=no mining, 1=mining allowed)
RSCO3 -1 1 1 - West Wall and Hwy mining restriction, (-1=no mining, 1=mining allowed)
VLT1 0 0 999 US$/t Value per ton for pit shell run 9
VLB1 0 -9999 99999 US$ Value per block for pit shell run 9 
SLUMP 0 0 1 - Slump areas near north wall in oxide (0=no slumping, 1=slumping) Not used
SLP 0 9 1 - Slope code where 3=alluvium, 1= North Wall, 2=South Wall
SLP2 0 9 1 - Slope code where 3=alluvium, 1= North Wall, 2=South Wall ,4=West walls 38degree
MCWA 0 9 0.01 US$/t Mining Cost Waste by Rock type
MCOX 0 9 0.01 US$/t Mining Cost Ore Oxide Material
MSSU 0 9 0.01 US$/t Mining Cost Ore Sulfide Material
LBSCU 0 99999999 0.01 lbs Copper Pound calculation per block
ACCOS 0 100000 0.01 cf/ton Acid cost calculation per ton

Table 13.4: Open Pit Model Item Descriptions for VLT
Field
Name
Min Max Precision Units Comments
TOPO 0 100 0.01 % TOPO %
TF 0 20 0.01 cf/ton Tonnage Factor
ZONE 0 100 1 - 10=VLT, 20=QAL
TCU 0 100 0.0001 % % CU IDW2 Grade estimate
ASCU 0 100 0.0001 % IDW2 Grade estimate
RCLS 0 10 1 - 1 Measured, 2 Indicated, 3 Inferred
MINE 0 2 1 - Used for calculation - LG calculation 1 mine 0 air
VLT 0 0 999 US$/t Value per ton for pit shell
VLB 0 -9999 99999 US$ Value per block for pit shell


 

Table 13.4: Open Pit Model Item Descriptions for VLT
Field
Name
Min Max Precision Units Comments
RCODE -1 2 1 - Mining restriction, (-1=no mining, 1=mining allowed)
LBSCU 0 99999 0.1 lbs Copper Pound calculation per block
ACCOS 0 9999990 0.1 US$/t Acid cost calculation per ton

Table 13.5: Open Pit Model Item Descriptions for MacArthur
Field
Name
Min Max Precision Units Comments
TOPO 0 100 0.01 % TOPO %
KTONS 0 2 0.001 Ktons ktons per block based on avg density (not used)
OXIDE 0 100 1 - 100 =Alluvium 10=Leach Cap 1=Oxide 2=Mixed 3=Sulfide
CLASS 0 5 1 - 1 Measured 2 Indicated 3 Inferred
CUPDP 0 3 0.0001 - Capped total copper. Id3 estimate Final Grade
DOMIN 0 5 1 - 1,2 MacArthur Pit Area, 3 North Ridge 4 Gallagher 5 North Area
PSSHEL 0 3 0.001 - N/A
TF 0 20 0.01 TF Tonnage Factor
LBSCU 0 1000000 0.01 lbs Pound Copper calculation
ACCOS 0 10000 0.01 US$/t Acid Cost calculation
MCWA 0 100 0.01 US$/t Mining Cost Waste
MCOX 0 100 0.01 US$/t Mining Cost Waste Oxide
MSCU 0 100 0.01 US$/t Mining Cost Waste Sulfide
PCOX 0 100 0.01 US$/t Processing Cost Oxide
PCOPA 0 4 0.01 US$/t Processing Cost Oxide Purchased Acid Option
ZONE 0 100 0.01 % 1 North Area 2 McArthur 3 Gallagher
PCOAP 0 100 0.1 US$/t Processing Cost Oxide Purchased Acid Plan
SLP 0 10 1 - Slope angles
MREC 0 100 0.01 % Mining Recovery
APREX 0 100 0.01 % Acid Plant option Mining Recovery
PAREC 0 100 0.01 % Purchased aid option Mining Recovery
VLT1 0 300000 0.01 US$/t Value Per Tons
VLB1 -500000 300000 0.01 US$ Value Per Block

13.3.2 Economic Pit Shell Development

The open pit ultimate size and phasing were completed with various input parameters, including estimates of the expected mining, processing, and G&A costs, metallurgical recoveries, pit slopes, and reasonable long-term metal price assumptions. AGP worked with Lion CG and the study team personnel to select appropriate operating cost parameters for the open pits.

Wall slopes for pit optimization were based on the assessment discussed in Section 16.2.

The mining costs are estimates based on cost estimates for equipment from vendors specific to the Yerington Copper Project and previous studies completed by AGP. The costs represent a base cost from the pit edge and an incremental cost below this elevation for the Yerington pit, but a fixed average cost for the other pit areas due to their geometry being less influenced by the depth of the potential pit. Mill feed material is sent to separate destinations, and the costs reflect that. Process costs by feed type were developed jointly with the Lion CG and SE teams.

Table 13.6 shows the parameters used for pit shell generation. The mining cost estimates are based on using 100-ton trucks with an approximate waste dump configuration to determine incremental hauls for mill feed and waste.

Total copper grades are used in the revenue calculations, with the recoveries applied. The recovery assumptions are based on the process flow sheet, and the feed material will be subjected to the heap. Copper cathode is produced from all process flowsheets.


 

For block valuation, an NSR value ($/t) was determined for every block and used with the Lerchs-Grossman routine within the Mine Plan. The cutoffs used were based on the block value but equated to the copper cutoff shown in Table 13.6. These cutoffs were also used for the pit design process.

It should be noted that the processing cost for acid assumes acid generated on-site and not purchased on the open market. On-site acid generation has been assessed and is included in this PFS.

Table 13.6: Economic Pit Shell Parameters by Area
Description Units Yerington VLT MacArthur Gallagher North
Ridge
Resource Model
Resource class   M+I M+I M+I M+I M+I
Block/Bench Height ft 25 25 25 25 25
Metal Prices
Cu US$/lb 3.90 3.90 3.90 3.90 3.90
Royalty % 2.5 2.5 2.5 2.5 2.5
Payable Metal and Deductions
Cu Payable % 99.5 99.5 99.5 99.5 99.5
Cathode Rail Cost US$/ton 50 50 50 50 50
Cathode Port Cost US$/ton 20 20 20 20 20
Cathode Shipping Cost US$/ton 30 30 30 30 30
Net Metal Price Calculation
Cu Payable % 99.5 99.5 99.5 99.5 99.5
Cathode Rail Cost US$/lb 0.025 0.025 0.025 0.025 0.025
Cathode Port Cost US$/lb 0.010 0.010 0.010 0.010 0.010
Cathode Shipping Cost US$/lb 0.015 0.015 0.015 0.015 0.015
Total Transportation Cost US$/lb 0.050 0.050 0.050 0.050 0.050
Subtotal Copper Price US$/lb 3.83 3.83 3.83 3.83 3.83
Less Royalty US$/lb 0.10 0.10 0.10 0.10 0.10
Net Copper Price US$/lb 3.73 3.73 3.73 3.73 3.73
Process Recoveries
Oxide - ROM % 70 75 55 54 55
Sulfide - Nuton % 74 - - - -
Mining Costs
Base Elevation ft 4225 4225 4225 4225 4225
Waste Base Rate US/t moved 2.53 2.53 2.53 2.53 2.53
Oxide Feed US/t moved 2.49 2.49 2.49 2.49 2.49
Sulfide Feed US/t moved 2.22 2.22 2.22 2.22 2.22
Incremental Rate Below Base Elevation
Waste Base Rate US/t moved 0.027 0.027 0.027 0.027 0.027
Oxide Feed US/t moved 0.027 0.027 0.027 0.027 0.027
Sulfide Feed US/t moved 0.024 0.024 0.024 0.024 0.024
Process and G&A Costs
Oxide Processing - ROM US$/t feed 2.00 1.34 1.67 2.14 2.02
Sulfides Processing - Nuton US$/t feed 4.44        
G&A Cost US$/t feed 0.49 0.49 0.49 0.49 0.49
Process + G&A
Oxide - ROM US$/t feed 2.49 1.83 2.16 2.63 2.51
Sulfides - Nuton US$/t feed 4.94        
Marginal Cutoff Grades
Oxide - ROM % Copper 0.05 0.03 0.05 0.07 0.06
Sulfides - Nuton % Copper 0.09        

Note: processing assumes the cost of acid was from an acid plant at site and not purchased

Pit optimization shells were completed for each area. These were plotted to determine the best shell for pit design purposes and help in phase determination. The plot of pit profit versus copper price for the Yerington pit is displayed in Figure 13.11 and illustrates various break points in the pit shells.


 

A restriction was placed on the pit optimization run so that pit shells maintained a reasonable offset distance from the highway.

There is a steady increase in value and size of the pit shell as the copper price increases, while very little waste is mined in the lower copper price pits. A total of 24.9 million tons of waste is required to move with the revenue factor (RF) = 0.65 pit shell ($2.54/lb copper). This refers to the copper price being 65% of the base price of $3.90/lb. That pit shell mines 18% of the RF=1 pit waste tonnage but contains 76% of the full RF=1 pit value. This pit shell was used as a rough guide to split the final phase, but was practically designed due to access considerations. The space between existing topography and the RF=0.9 pit shell was, in many instances, only 200 ft wide, which is sufficient for a single phase.

The next breakpoint in the curve, at RF=0.9 ($3.51/lb copper), is where 98% of the RF=1 pit revenue is achieved, but only 67% of the waste material needs to be moved. For design purposes, this was selected as the ultimate pit shell.

Source: AGP 2025

Figure 13.11: Yerington Profit vs. Price by Pit Shell

For the VLT area, pits were generated but the RF=1 pit was selected to fully remove the material where the sulfide leach facility would be placed. The sulfide HLF will expand onto the current VLT location in later phased expansions.

Pit optimization for the MacArthur area was completed in the same manner. Various pits were examined from a phasing perspective but in the end the RF=1.0 pit was selected as a single phase (Figure 13.12). This shell was used for all three areas in MacArthur for the designs.


 

Source: AGP 2025

Figure 13.12: MacArthur Profit vs Price by Pit Shell

13.3.3 Dilution

The provided resource models are in whole block format. A whole block model means that any given block is routed as either mill feed or waste. The block size within each of the models was 25 ft by 25 ft in plan and 25 ft high. The resource grade model includes some internal dilution, where the grade from the assays was interpolated over the full volume of the block to arrive at a diluted smooth block grade.

The contacts between feed and waste are transitional, typical of copper projects. For the PFS, dilution has been assumed to be equal to the feed loss from mining. Therefore, no additional dilution has been included in the tonnages in the mine designs.

13.4 PIT DESIGN

The pit designs vary by area. For Yerington, a multi-phase approach was developed to allow the mining of the first two phases within the current wall slopes. This provides initial feed material while the sides of the pit are pushed back, allowing the overall pit to go deeper than previously mined.

The VLT area is mined in its entirety. The sulfide heap facility will grow into the area currently occupied by the VLT. Material that is shown to be economic is placed in the oxide heap leach facility. The waste material still contains copper, but is not currently economically viable at the copper price used. The waste material will also be placed on the oxide heap facility (Yerington East HLF) to store this material on a liner for the longer term. By doing this, there may be an opportunity to leach the waste material in the future, should the price of copper rise, possibly making this material economic.

MacArthur pit designs are single-phase but composed of different areas. The Gallagher pit is smaller and does not afford room for phasing. North Ridge can join with MacArthur, so it was mined in two phases, with the second phase connecting to MacArthur. The MacArthur Area has already been opened with previous mining, and mining a larger area allows for efficient mining to occur, enhancing mining cost efficiency.

Phase tonnages and grades are displayed in Table 13.7.

Table 13.7: Pit Phase Tonnages and Grades
Phase Oxide Cu Sulfide Cu Waste Total Strip Ratio
  (Mt) (%) (Mt) (%) (Mt) (Mt) (w:f)
Yerington              
Phase 1 2.7 0.30 2.8 0.26 0.0 5.4 0.00
Phase 2 - - 2.4 0.42 0.0 2.4 0.01


 

Table 13.7: Pit Phase Tonnages and Grades
Phase Oxide Cu Sulfide Cu Waste Total Strip Ratio
  (Mt) (%) (Mt) (%) (Mt) (Mt) (w:f)
Phase 3 48.0 0.19 58.2 0.24 48.2 154.5 0.45
Phase 4 25.4 0.17 170.4 0.26 45.3 241.1 0.23
Subtotal Yerington 76.1 0.19 233.8 0.26 93.6 403.4 0.30
VLT 31.9 0.09     37.2 69.1 1.17
MacArthur              
MacArthur 116.6 0.18     12.4 129.00 0.11
Gallagher 8.8 0.20     1.5 10.3 0.17
North Area Ph 1 20.1 0.16     3.4 23.5 0.17
North Area Ph 2 19.3 0.17     11.6 30.9 0.60
Subtotal MacArthur 164.8 0.18     28.9 193.7 0.18
Total Pits 272.8 0.17 233.8 0.26 159.7 666.3 0.32

Contained within the waste for MacArthur is 1.54 million tons of sulfide material grading 0.15 Cu%.  This is stored in a separate portion of the waste pile that may allow it to be processed with Nuton after metallurgical testing is completed in later stages of the study.

Geotechnical parameters discussed in Section 16.2 were applied to the pit designs developed. Ramp widths sufficient for 100-ton mining trucks have also been included where needed. The design criteria used is shown in Table 13.8.

Table 13.8: Pit Slope Design Criteria
Pit Area Inter-ramp
Angle

(degrees)
Bench Face
Angle

(degrees)
Bench
Height

(ft)
Height Between
Berms

(ft)
Berm
Width

(ft)
Alluvium 36 65 25 25 20
Yerington - North Walls 37 70 25 25 20
Yerington - South Walls 39 75 25 25 20
VLT 27 40 25 25 20
MacArthur - North Walls 27 65 25 25 20
MacArthur - South Walls 45 65 25 25 20
Gallagher - North Walls 45 65 25 25 20

13.4.1 Yerington Phase 1 and 2

The first phases in the Yerington pit are within the current pit footprint wall slopes and will provide feed material to ramp up the Nuton process and provide value from oxide.  The phases are designed to follow the water level down as the current pit lake is dewatered.

Phase 1 is predominantly oxide material and is located higher up in the pit on the eastern side, while Phase 2 is primarily sulfide and is located at depth. The previous ramp system will be rehabilitated and used for these phases while the side slopes are mined in Phase 3.

The designs for Phases 1 and 2 are shown in Figure 13.13.


 

Source: AGP 2025

Figure 13.13: Yerington Phase 1 and 2 Designs

13.4.2 Yerington Phase 3

Phase 3 is the second largest of the Yerington phases and a source of sulfide feed material for Nuton and significant oxide tonnage. This is also the phase where new access ramps are developed. The design provides leach feed access to the crusher on the northeast side and waste access on the western side. The design is shown in Figure 13.14.


 

Source: AGP 2025

Figure 13.14: Yerington Phase 3 Design

13.4.3 Yerington Phase 4

Phase 4 drives deeper in the center and western ends of the pit and also in the east.  To do this the pit wall is trimmed with the final push on the southeast side completed.  Doing this cuts the access road on the northeast side to allow the pit to go deeper in the eastern end.  Feed access to the crusher is along the western slope and waste access is on the southeastern side of the pit.

The design is shown in Figure 13.15.


 

Source: AGP 2025

Figure 13.15: Yerington Phase 4 Design

13.4.4 VLT Pit

The VLT pit is the selective material extraction within the VLT stockpile defined by a previous drilling program. Accesses are designed to exit to the east, and limited ramping is required. The remaining material will also be mined for the oxide HLF. The base of the pit design matches that of the sulfide HLF design to minimize additional earthworks.

The design is shown in Figure 13.16.


 

Source: AGP 2025

Figure 13.16: VLT Pit Design

13.4.5 MacArthur Pit

The MacArthur pit (Figure 13.17) is the main source of feed in the MacArthur area. This pit has been mined previously, and the design follows a similar development approach with access from the east on the various levels. A limited ramp system along the southern wall is required.


 

Source: AGP 2025

Figure 13.17: MacArthur Pit

13.4.6 Gallagher Pit

The Gallagher pit utilizes access from current topography for the initial levels. As the pit deepens, ramp access is required from the east to develop the undulating oxide levels.

The design is shown in Figure 13.18

Source: AGP 2025

Figure 13.18: Gallagher Pit


 

13.4.7 North Ridge Pit

The North Ridge Pit is primarily a slot extraction of the oxide within the narrow zone. A ramp is used to access the deep portions to the east within the deposit. The design is shown in Figure 13.19.

Source: AGP 2025

Figure 13.19: North Ridge Pit Phase 1

A second phase is developed from the east using MacArthur as an access point.  Access is along the north edge of MacArthur then follows the small valley. The mining is on retreat with access through MacArthur as shown in Figure 13.20.

Source: AGP 2025

Figure 13.20: North Ridge Pit Phase 2

13.5 ROCK STORAGE FACILITIES

The total amount of waste mined and stored within the mine plan is 159.8 Mtons. This is the total of the two main areas: Yerington and MacArthur. Yerington will have a total of 130.8 Mtons of waste generated from the Yerington pits (Yerington, VLT) while MacArthur will have 29.0 Mtons generated from the three mining areas (MacArthur, Gallagher, North Ridge).

A swell factor of 1.30 was applied to the waste rock storage facilities, which were designed with an overall 25° face slope angle to mimic a final reclamation slope. The Yerington waste rock storage facility will be placed atop the existing waste facility. The intention is to not extend beyond the current limits while also not burying the alluvial material at the north end of the existing waste rock storage facility, which is deemed useful for heap leach pad construction and capping of the heap leach facilities upon closure. The facility is shown in Figure 13.21.


 

Source: AGP 2025

Figure 13.21: Yerington Waste Rock Storage Facility and Heap Leach Facilities

The MacArthur waste rock storage facility is located in the southwest. The oxide ROM heap facility is located to the northeast. The locations of the facilities are shown in Figure 13.22.

There remains an opportunity to store a small amount of waste generated from Gallagher within the confines of the MacArthur pit. This aspect will be subject to further investigation in subsequent stages of study.


 

Source: AGP 2025

Figure 13.22: MacArthur Waste Rock Storage Facility and Oxide ROM Heap Leach Facility

13.6 MINE SCHEDULE

The mining rate targets the crushing of a maximum of 34 Mtpa of Nuton feed (sulfide) from Year 3 onwards. There is an initial ramp up period to allow the Nuton process to come online as the sulfide material is extracted from the Yerington pit.  Recovered copper capacity peaks at 179.3 Mlbs in Year 7 but averages 129.2 Mlbs from Year 3 onwards after the sulfide leaching starts.

Oxide and sulfide material will be handled differently depending on their point of origin.  Yerington oxide materials which include the Yerington oxide, and VLT will be placed on the Oxide Heap Leach facility as ROM. MacArthur oxides are also ROM but placed in a separate facility adjacent to the MacArthur pits.

The sulfide material destined for the Nuton Heap Leach area is first sent to a crushing facility to the northwest of the Yerington pit. The material will be crushed, agglomerated, and then conveyed to the HLF to be stacked on the facility.

Total life of mine heap leach production will be 506.6 million tons grading 0.21% copper. The Yerington pit will deliver 233.8 million tons of sulfide material grading 0.26% copper to the Nuton heap leach pad. Yerington oxides, including the VLT, will total 108.0 million tons grading 0.16 % copper. MacArthur produces 164.8 million tons of oxide leach material with an average copper grade of 0.18%.

The overall mine strip ratio for the PFS is 0.32:1 (waste:feed). MacArthur has a strip ratio of 0.18:1 (waste:feed) and Yerington's is 0.30:1 (waste:feed). The VLT pit is 1.17:1 (waste:feed).

The annual leach tonnages by area and type are shown in Figure 13.23. Annual feed grades by type and area are shown in Figure 13.24.

The detailed annual mining summary is shown in Table 13.9.


 

Source: AGP 2025

Figure 13.23: Annual Heap Leach Tonnages (Type and Area)

Source: AGP 2025

Figure 13.24: Annual Feed Grade by Type and Area


 

Table 13.9: Annual Mining and Heap Leach Feed Schedule Details

Table 13.9: Annual Mining and Heap Leach Feed Schedule Details
Description Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10 Y11 Y12 Total
Yerington Mining Summary Waste (Mt) - 19.2 15.4 22.4 19.6 27.0 23.9 0.8 0.3 0.6 1.1 0.6 130.8
Sulfide (Mt) - - 5.2 1.8 15.6 34.0 33.1 33.8 34.9 34.3 33.9 6.2 233.8
Cu (%) - - 0.34 0.13 0.19 0.26 0.25 0.26 0.29 0.28 0.26 0.24 0.26
Yerington Oxide (Mt) - - 3.9 24.2 20.6 11.2 16.0 0.2 - - - - 76.1
Cu (%) - - 0.25 0.18 0.20 0.16 0.19 0.24 - - - - 0.19
VLT Oxide (Mt) - - - 6.0 6.5 5.5 13.9 - - - - - 31.9
Cu (%) - - - 0.09 0.08 0.10 0.09 - - - - - 0.09
Total Feed (Mt) - - 9.0 31.9 42.7 51.7 63.0 34.0 35.0 34.3 33.9 6.2 341.8
Cu (%) - - 0.30 0.16 0.18 0.22 0.20 0.26 0.29 0.28 0.26 0.24 0.23
Total Yerington Mined (Mt) - 19.2 24.4 54.3 62.4 78.7 86.9 34.9 35.2 34.9 35.0 6.8 472.6
MacArthur Mining Summary Waste (Mt) 3.5 8.4 1.4 3.2 9.1 3.3 - - - - - - 29.0
MacArthur Oxide (Mt) 17.2 31.7 51.6 15.0 1.1 - - - - - - - 116.6
Cu (%) 0.20 0.18 0.17 0.18 0.18 - - - - - - - 0.18
Gallagher Oxide (Mt) 6.6 0.7 - - 1.5 - - - - - - - 8.8
Cu (%) 0.20 0.18 - - 0.17 - - - - - - - 0.20
North Ridge Oxide (Mt) 1.2 4.8 0.1 14.1 11.3 8.0 - - - - - - 39.4
Cu (%) 0.15 0.17 0.10 0.16 0.13 0.23 - - - - - - 0.17
Total Feed (Mt) 25.0 37.3 51.7 29.1 13.8 8.0 - - - - - - 164.8
Cu (%) 0.20 0.18 0.17 0.17 0.14 0.23 - - - - - - 0.18
Total MacArthur Mined (Mt) 28.5 45.0 53.1 32.9 22.9 11.3 - - - - - - 193.7
Total Total Waste Material (Mt) 3.5 27.6 16.8 25.6 28.7 30.3 23.9 0.8 0.3 0.6 1.1 0.6 159.8
Total Heap Material (Mt) 25.0 37.3 60.7 61.0 56.6 59.7 63.0 34.0 35.0 34.3 33.9 6.2 506.6
Total Material (Mt) 28.5 64.9 77.5 86.6 85.3 90.0 86.9 34.9 35.2 34.9 35.0 6.8 666.3
Processing Summary Sulfide - Nuton (Mt) - - 5.0 2.0 13.6 34.0 34.0 34.0 34.0 34.0 34.0 9.2 233.8
Cu (%) - - 0.34 0.13 0.20 0.27 0.24 0.26 0.29 0.28 0.26 0.20 0.26
Yerington Oxide (Mt) - - 3.9 24.2 20.6 11.2 16.0 0.2 - - - - 76.1
Cu (%) - - 0.25 0.18 0.20 0.16 0.19 0.24 - - - - 0.19
VLT Oxide (%) - - - 6.0 6.5 5.5 13.9 - - - - - 31.9
Cu (%) - - - 0.09 0.08 0.10 0.09 - - - - - 0.09
MacArthur Oxide (Mt) 17.2 31.7 51.6 15.0 1.1 - - - - - - - 116.6
Cu (%) 0.20 0.18 0.17 0.18 0.18 - - - - - - - 0.18
Gallagher Oxide (Mt) 6.6 0.7 - - 1.5 - - - - - - - 8.8
Cu (%) 0.20 0.18 - - 0.17 - - - - - - - 0.20
MacArthur North Oxide (Mt) 1.2 4.8 0.1 14.1 11.3 8.0 - - - - - - 39.4
Cu (%) 0.15 0.17 0.10 0.16 0.13 0.23 - - - - - - 0.17
Oxide - Total (Mt) 25.0 37.3 55.5 59.2 41.0 24.7 29.9 0.2 - - - - 272.8
Cu (%) 0.20 0.18 0.18 0.16 0.16 0.17 0.14 0.24 - - - - 0.17
Stockpile Sulfide Balance (Mt) - - 0.1 - 2.0 3.0 2.1 1.9 2.8 3.1 3.0 -  
Cu (%)) - - 0.14 - 0.13 0.13 0.11 0.11 0.12 0.12 0.12 -  
Reclaim (Mt) - - - 0.1 - - 3.0 0.2 - - 0.2 3.0 6.5
  Total Moved (Mt) 28.5 64.9 77.5 86.7 85.3 90.0 90.0 35.0 35.2 34.9 35.2 9.8 672.8


 

Before production begins, several critical infrastructure components must be fully prepared or nearing completion. This includes the development of the oxide heap leach facilities, start of the sulfide heap leach facilities, the setup of the crusher and conveyor systems for sulfide materials, and the readiness of the processing facility. While the heap leach facilities are a substantial portion of the work, they can and are developed in phases.

One of the key items for the Yerington pit is dewatering of the existing Yerington pit, which is essential to gaining access to the material at the current pit bottom. As the water level gradually recedes through the pumping process, the eastern section of the pit bottom where Yerington Phase 1 is situated will progressively become accessible.

In Year 1, mining activity will be restarted in the past producing MacArthur pit area.  This past activity has left ready access for equipment to start in MacArthur, but Gallagher and North Ridge will require new access development.  The terrain is not difficult, and access can be readily established.

No mining activities will occur in the Yerington area other than ongoing dewatering of the pit lake.

Year 2 will see ongoing mining activity in all three pit areas in MacArthur.  Gallagher will be almost complete.  MacArthur provides the bulk of the material to feed the heap leach facility in the MacArthur area.

Mining at Yerington will commence in Year 2 with the prestripping of waste material in Phase 3, focusing on the initial mining of slopes above Phases 1 and 2 while the water level drops.

Also in the Yerington area is the mining of VLT starting on the western edge of the VLT stockpile.  This will include waste mining to open the area for the initial phase of the sulfide leach pad and allow construction of the facility to be completed.

In Year 3 at Yerington, as the water level decreases, efforts will be directed towards the restoration of the old ramp system. This rehabilitation will occur concurrently with the mining activities focused on the oxide materials in Phase 1. Mining in Phase 2 at Yerington will also be started, which involves the restoration of the ramp leading to the lower phase location and the final phases of pit dewatering.

VLT mining is in the area of the sulfide leach pad second phase.  This is not required for two years but prepares the area for that construction.  VLT material is placed on the oxide heap leach facility at Yerington.

The MacArthur pit is the only pit to see any significant mining activity in Year 3 in the MacArthur area.  A small amount of material is mined in North Ridge.

Year 4 has the completion of VLT mining in the second phase area for the sulfide leach pad, both ore and waste.  Mining in the Yerington pit is only Phase 3 as Phases 1 and 2 were completed in Year 2.

MacArthur mining is both North Ridge and MacArthur pits with the split of tonnage to the heap leach almost equal from the two areas.


 

Mining in Year 5 sees the final remnants finished in the MacArthur pit.  North Ridge mines the connection between North Ridge and MacArthur.  North Ridge is the principal supplier of feed to the MacArthur heap leach pad this year.

The VLT mining is still within the future phase 2 sulfide pad area in Year 5.  The Yerington pit sees the initiation of Phase 4 mining in the west and deepening of Phase 3 in the east.  Oxide material from Yerington is still the dominant feed material as the sulfide leach ramps up with 19.9 million tons of oxide versus 15.7 million tons of sulfide coming from Yerington Phases 3 and 4.

Year 6 marks the end of mining in the MacArthur area with completion of the North Ridge pit.

VLT is still being mined in the sulfide heap leach second phase.  This mining releases the area for construction of the sulfide heap leach second phase to be completed.

The Yerington pit continues with Phases 3 and 4 advancing to depth.  Oxide production from the Yerington pit is less than the sulfide with 11.5 million tons of oxide versus 34 million tons of sulfide.

Year 7 has the VLT mining completed which opens up the third phase area of the sulfide leach pad for construction activities.  Mining in the Yerington pit is finishing Phase 3 with Phase 4 the main material supplier.  Sulfide tonnages are 34 million tons vs 15.6 million tons of oxide.

Year 8 and onwards is only mining in the Yerington pit and Phase 4.  Feed material is essentially all sulfide material except for 0.2 million tons of oxide.  No further oxide will come from the Yerington pit with the current understanding of the geology.

Year 9 until the end of mining in Year 12 is all Phase 4 in the Yerington pit.  Full production is maintained to keep the crusher full at 34 million tons per year.  The final year, Year 12 will only have 10 million tons of sulfide to the crusher as the pit is exhausted.

The end of period plans for the mine schedule are shown in Figure 13.25 to Figure 13.41 below.


 

Source: AGP 2025

Figure 13.25: End of Year 1 - MacArthur Area


 

Source: AGP 2025

Figure 13.26: End of Year 2 - MacArthur Area


 

Source: AGP 2025

Figure 13.27: End of Year 2 - Yerington Area


 

Source: AGP 2025

Figure 13.28: End of Year 3 - MacArthur Area


 

Source: AGP 2025

Figure 13.29: End of Year 3 - Yerington Area


 

Source: AGP 2025

Figure 13.30: End of Year 4 - MacArthur Area


 

Source: AGP 2025

Figure 13.31: End of Year 4 - Yerington Area


 

Source: AGP 2025

Figure 13.32: End of Year 5 - MacArthur Area


 

Source: AGP 2025

Figure 13.33: End of Year 5 - Yerington Area


 

Source: AGP 2025

Figure 13.34: End of Year 6 - MacArthur Area


 

Source: AGP 2025

Figure 13.35: End of Year 6 - Yerington Area


 

Source: AGP 2025

Figure 13.36: End of Year 7 - Yerington Area


 

Source: AGP 2025

Figure 13.37: End of Year 8 - Yerington Area


 

Source: AGP 2025

Figure 13.38: End of Year 9 - Yerington Area


 

Source: AGP 2025

Figure 13.39: End of Year 10 - Yerington Area


 

Source: AGP 2025

Figure 13.40: End of Year 11 - Yerington Area


 

Source: AGP 2025

Figure 13.41: End of Year 12 - Yerington Area


 

13.7 MINE EQUIPMENT SELECTION

Conventional mining equipment was selected to meet the required production schedule, with additional support equipment for road, dump, and bench maintenance as is typical in an open pit mine.

Drilling will be completed with DTH electric drills with 6 ¾" bits. This allows drilling 25-foot heights in a single pass. A smaller 5 1/2" drill is used for tighter working areas.

The primary loading units will be 21 yd³ electric hydraulic shovels.  Additional loading will be completed by 15 yd³ loaders.  It is expected that one of the loaders will be at the primary crusher for the majority of its operating time. The haulage trucks will be conventional 100-ton rigid-body trucks.

The support equipment fleet will be responsible for the usual road, pit, and dump maintenance requirements.  In addition, smaller road maintenance equipment is included to keep drainage ditches open and sedimentation ponds functional.

Additional fleet details are included in Section 21.

13.8 BLASTING AND EXPLOSIVES

The blast patterns for feed and waste material are the same. The blast patterns will be 17.7 ft x 15.4 ft (spacing x burden). Holes will be 25 ft plus an additional 4.3 ft of sub-drill, for a total of 29.3 ft.

The power factor with this pattern size will be 0.69 lb/t. ANFO will be used 80% of the time, with emulsion used only during wet conditions.

The blasting cost was estimated using quotations from a local vendor. The mine is responsible for guiding the loading process, including placement of boosters/Nonels, and stemming and firing the shot.

The total monthly cost of delivering the explosives to the hole is estimated to be $35,950/month for the vendor's pickup trucks, pumps, and labor. The explosives vendor will lease the explosives and accessories magazines as part of that cost. Further explosive details are included in Section 21.

13.9 GRADE CONTROL

Grade control will be completed with the blast hole drill cuttings. These cuttings will be collected at the drill hole and analyzed for the various copper grades (total, acid-soluble, and cyanide-soluble) to assist in recovery calculation and help make a short-range grade control model for the mine planners.

In areas of low-grade mineralization or waste, 25% of the blasthole cuttings will be sampled to confirm or identify undiscovered veinlets or pockets of mineralization.

These grade control holes will define the heap feed grade and mineralization contacts.

The samples collected will be sent to the assay laboratory and assayed for use in the short-range mining model.


 

13.10 PIT DEWATERING

Efficient and cost-effective dewatering will play a role in the project development. Dewatered slopes may allow a reduction in the strip ratio by permitting steeper inter-ramp angles while also being inherently safer.

The dewatering system includes the pumps, sumps, and pipelines responsible for moving water from the pit to the discharge points. Labor for this is already included in the General and Mine Engineering category of the mine operating cost. The mine is assumed to have a dedicated road/pump crew.

The dewatering operating cost also includes additional dewatering in the form of horizontal drain holes. Starting in Year 2, these holes will be drilled in annual campaigns. The design concept is a series of 150-foot holes angled up slightly and drilled into the high walls. They will allow the water behind the wall to drain freely and prevent pore water pressure build-up, particularly during freezing conditions.

Pit lake dewatering is discussed in Section 18.

13.11 PIT SLOPE MONITORING

Slope movement monitoring will be required during operations. Initial slope monitoring could be conducted with prisms read by manual or automated survey methods. Once operating slope measurement results for the first several years have been gathered and analyzed, a permanent, automated system may be necessary. Radar and satellite systems are two of the possible methods for gathering monitoring information. Detailed slope movement information will be useful for calibrating future numerical models to support detailed pit designs at depth.

A limited number of vibrating wire piezometers are envisioned to be installed around the pit to capture information about the drawdown cones/pore pressure distributions as the pit gets deeper, evaluating the effectiveness of installed drains. Horizontal passive drains at 150 ft spacing have been included in the costing to provide local depressurization to improve slope performance.

Pit wall mapping may be conducted using either digital or physical methods. The mapping results can then be reviewed and interpreted to verify the suitability of slope and blast designs.

Operating practices will need to be developed so that blast designs and vibrations are monitored for their impact on pit walls. Equipment operator training is also recommended to ensure that scaling and cleaning up near walls are completed adequately.

13.12 HYDROGEOLOGY AND PIT DEWATERING

See Section 15.5 for detailed hydrogeology and pit dewatering information.


 

14.0 PROCESSING AND RECOVERY METHODS

14.1 INTRODUCTION

The Yerington Copper Project consists of two sites: The MacArthur Site and the Yerington Site. The MacArthur Site will have three pits providing ore to its heap leach pad and solvent extraction facility. The Yerington Site will have the Yerington Pit providing sulfide ore to its crushing and agglomeration circuit and the heap leach pad. The rich electrolyte from both sites will be combined to feed into the electrowinning circuit to produce LME Grade A copper cathode.

A simplified flow sheet for the process is shown in Figure 14.1 below.

14.2 PROCESS PLANT LOCATION

14.2.1 MacArthur Site

The MacArthur Site is located 5.1 miles northwest of the main Yerington Site. The MacArthur Site consists of three pits for the ore source, primarily of oxide copper ore. MacArthur will have its own leach pad, raffinate, PLS pond, solvent extraction facility and event pond. The pregnant peach solution (PLS) will be processed through the MacArthur solvent extraction facility to produce rich electrolyte solution. The solution will be pumped to the Yerington Site's electrowinning circuit and combined with the Yerington Site's rich electrolyte solution. After the electrowinning process, part of Yerington Site's lean electrolyte solution will be returned to the MacArthur Site for reuse. The raffinate solution from the MacArthur raffinate pond can be pumped directly to Yerington raffinate pond for make-up and vice versa.


 

Figure 14.1: Yerington Copper Project Process Flow Diagram


 

14.2.1.1 MacArthur Site - Heap Leaching

The copper recovery is approximately 46 to 59% with leach cycle distribution over two years: 75% in the first year and 25% in the second year. Copper recoveries are based on test work from each of the Run-of-Mine (ROM) ores. The leach cycle is approximately 90 days. The irrigation rate is set at 0.0025 gpm/ft2.

Table 14.1 below summarizes the MacArthur heap leaching information.

Table 14.1: MacArthur Heap Leach Info.
Cu Recovery (ROM) Units  
Oxide MacArthur % 59%
Oxide North MacArthur % 46%
Oxide Gallagher % 46%
Leach Cycle Distribution
Irrigation Rate gpm/ft2 0.0025
Leach Cycle Days 90
Year 1   75%
Year 2   25%
Year 3   0%

14.2.1.2 MacArthur Site - Solvent Extraction Facility

The solvent extraction facility will receive PLS from the MacArthur's PLS pond.

The facility will consist of one train with a total of three solvent extraction mixer-settlers and one stripping mixer-settler. At nominal flow of 17,800 gpm, the extraction circuit will operate with two settlers in series and the third settler in parallel. All extraction mixer-settlers have been designed identically and will accommodate equal flowrates. Under high flow conditions, the second stage extraction mixer-settler will become the third parallel extraction mixer-settler to accommodate the additional flow. The organic handling equipment includes a crud treatment package. The solvent extraction area is serviced by a foam fire protection system. Figure 14.2 displays the general layout of the solvent extraction facility.


 

Figure 14.2: MacArthur Site Solvent Extraction Facility General Layout

After the solvent extraction process, the rich electrolyte is pumped through a 12-inch pipeline in a lined trench approximately five miles to the Yerington Site for electrowinning. After electrowinning, the lean electrolyte from the Yerington Site will be pumped back to the MacArthur Site for reuse in the solvent extraction stripping circuit. There will be a minor lean electrolyte bleed stream from the lean electrolyte to the raffinate stream.

14.2.1.3 MacArthur Site - Reagent Consumptions

As sulfuric acid is consumed through the process, it will be replaced with the raffinate solution mixed with sulfuric acid pumped from the Yerington Site. Ore sources will dictate the amount of acid consumption. Sulfuric acid will be produced at the Yerington Site's sulfuric acid plant and pumped to the MacArthur sulfuric acid storage tank in a two-inch line. The sulfuric acid tank can accept truck or rail delivery of concentrated sulfuric acid.

Diluent and extractant will be used in the solvent extraction circuit and will be delivered by rail or by truck. The overall reagent consumption per unit, and over the course of mine life, is summarized below in Table 14.2 and Table 14.3.

Table 14.2: MacArthur Site Reagent Consumption
MacArthur Pit Gross Sulfuric Acid Units  
MacArthur lb/ton feed 24
North Ridge lb/ton feed 44
Gallagher lb/ton feed 46
Solvent Extraction Units  
Diluent gal/ton CU 7.5
Extractant gal/ton CU 1.9
Sulfuric Acid ton Acid/ton CU 0.5


 

Table 14.3: MacArthur Site Total LOM Reagent Consumption
Gross Sulfuric Acid Consumption Units  
MacArthur ton 1,285,284
North Ridge ton 758,822
Gallagher ton 198,072
Total ton 2,467,756
Solvent Extraction Units  
Diluent gal 1,210,717
Extractant gal 302,359
Sulfuric Acid ton 1,239

14.2.1.4 MacArthur Site - Utilities

Two fresh water well pumps will supply the Site with potable and process water. Potable water will be treated as necessary to meet potable water standards. Two air compressors, with one of them as backup, will supply the plant air and instrumentation air.

14.2.2 Yerington Site

The Yerington Site is the main operating site. The Yerington Pit will be dewatered to access its oxide and sulfide copper ore. The sulfide ore will be directed to the crushing circuit, whereas the oxide ore will bypass crushing and be transferred directly to the Yerington oxide heap leach pad. A crushing circuit will crush the sulfide ore before agglomeration and stacking onto the Yerington sulfide heap leach pad. Two stockpiles are located between each crushing phase to maximize crushing and stacking equipment utilization. NutonTM Technology will be implemented to enhance copper extraction from the sulfide ore. Nuton Technology introduces proprietary bacteria and additives to the ore which, when coupled with heap leach operating parameters, facilitates the process of chalcopyrite oxidation and leaching.

The pumps located at the raffinate pond will pump the leach solution onto the HLF. The PLS pond will receive the copper-rich solution and pump it to the solvent extraction facility to extract the copper to an electrolyte solution while removing impurities. The Yerington Site will have two PLS ponds, one for sulfides and one for oxides. Additionally, the oxide PLS will recycle back to the sulfide PLS.

The Yerington copper rich electrolyte will combine with the MacArthur copper rich electrolyte and enter the electrowinning and cathode stripping facility to produce LME Grade A copper cathode. The copper cathodes will be transported to market via the rail service installed for the project.

There will be two 1,500 tpd sulfuric acid plants located adjacent to the Yerington SX/EW facility, each with a cogeneration steam power plant at the Yerington Site. They will receive raw sulfur via rail and produce the sulfuric acid needed for both the Yerington Site and the MacArthur Site. The steam generated from sulfuric acid production will be recovered as waste heat. It will be used to melt the sulfur feed stock, generate electricity, and to heat up the Yerington PLS raffinate through a heat exchanger before PLS enters the solvent extraction circuit.  Alternatively, the heat can be utilized to heat the raffinate with the same equipment/process proposed for heating the PLS stream. Figure 14.3 displays the Yerington Site SX facility layout.


 

Figure 14.3: Yerington Site Solvent Extraction Facility General Layout

14.2.2.1 Yerington Site - Primary Crushing and Coarse Ore Stockpile

The sulfide ore from the Yerington Pit will be brought by haul truck to two dump hoppers. From the dump hoppers, feeders supply the two dual shaft mineral sizers deployed as primary crushers. The mineral sizers will reduce the feed size of F80 at 6 inches to P80 at 3.5 inches. The crushed coarse ore will be transported to the coarse ore stockpile by two conveyors.

14.2.2.2 Yerington Site - Secondary, Tertiary Crushing & Fine Ore Stockpile

Coarse sulfide ore will enter the secondary crushing circuit through a series of three reclaim feeders, a conveyor, and into the secondary crushing circuit. The secondary crushing circuit is comprised of three parallel trains. Each train includes a feed bin, screen feeder, and a vibrating sizing screen and cone crusher. After the secondary crushers, the material is discharged onto the secondary crushing discharge conveyor. Each train is designed to process a nominal rate of 1,553 STPH or a design rate of 1,864 STPH. The secondary crusher feed bin has a residence time of 15 minutes with a total capacity of 750 ST.

A secondary discharge conveyor will transport the crushed ore to the tertiary crushing circuit. The tertiary crushing circuit is comprised of five parallel trains. Each train includes a feed bin, an apron feeder, and a vibrating sizing screen and cone crusher. After the tertiary crushers, the material is discharged onto the tertiary crushing discharge conveyor. The tertiary crusher feed bin will have a residence time of 15 minutes with a total capacity of 740 ST. Each cone crusher will have a nominal throughput capacity of 593 STPH. The discharge conveyer will transport the crushed ore to the fine ore stockpile.  Final crushed product will be P80 of 0.5 in. and a P50 of 0.28 in.


 

14.2.2.3 Yerington Site - Nuton Technology

The fine ore stockpile will be reclaimed through a series of reclaim feeders, conveyors, and bins, followed by agglomeration feeders and feed conveyors. There will be three agglomerators operating in parallel. They will process the ore with moisture from between 3% and 5% and increase it to 7% with raffinate solution. Pyrite and a process solution stream carrying bacteria inoculum from the Nuton Technology package and pyrite will be added to the agglomerators for sulfide ore.  Catalytic additives have not been included in the current design. Their potential value will be reassessed once all Phase 2 test columns have been mass-balanced and for future sample testing and studies.   

Pyrite is added to the ore to maintain elevated temperature inside the heap leach facility.  Biological oxidation of pyrite is exothermic, generating heat and warming the heap leach facility.  Nuton has developed a portfolio of patents directed to biological oxidation of pyrite and heap leach technologies and implementation of Nuton Technology will target pyrite addition to maintain active leaching areas between 50°C and 60°C to achieve the modeled 73% recovery.  Newmont successfully operated a high temperature bio-leach demonstration facility at their Yanacocha operation in Peru in 2013 to 2017.  The demonstration heap achieved 50°C successfully demonstrating the viability of elevated temperature heap leaching.  Additional information on the demonstration facility can be found in Biomining Technologies: Extracting and Recovering Metals From Ores and Wastes, pg 177-190.  Additionally, Freeport successfully achieved internal heap leach temperatures above 50°C during a chalcopyrite leaching trial between June 2007 and June 2009.  Results from that trial were published August 2013 by J. Ekenes and C. Caro, Improving Leaching Recovery of Copper from Low-Grade Chalcopyrite Ores.

A series of stacking and overland conveyors will transport the ore to the heap leach pad for stacking.

14.2.2.4 Yerington Site - Sulfide and Oxide Heap Leaching

The copper recovery for Yerington Sulfide is 73%, Yerington Oxide is 68%, and Yerington VLT is 69%. The leach cycle for Yerington Oxide is approximately 90 days with the irrigation rate set at 0.0025 gpm/ft2. The oxide PLS will then be utilized as a raffinate leaching solution to the Yerington West HLF.

The leach cycle for Yerington sulfide is 180 days with the irrigation rate set at 0.0025 gpm/ft2. The Oxide PLS will partially offset the raffinate solution to the Yerington West HLF when the Yerington East HLF is in operation.

Table 14.4 summarizes the Yerington heap leaching information.

Table 14.4: Yerington Heap Leach Information
Cu Recovery (5/8") Units Value
Yerington Sulfide (Nuton) % 73%
Cu Recovery (ROM) Units Value
Yerington Oxide % 68%
Yerington VLT % 69%
Leach Cycle Distribution
Irrigation Rate gpm/ft2 0.0025
Oxide Leach Irrigation Cycle Days 90


 

Table 14.4: Yerington Heap Leach Information
Year 1 % 75%
Year 2 % 25%
Year 3 % 0%
Sulfide Leach Irrigation Cycle Days 180
Year 1 % 65%
Year 2 % 30%
Year 3 % 5%

14.2.2.5 Yerington Site - Solvent Extraction Facility

The facility's layout will be the same as MacArthur's Solvent Extraction circuit and its configuration can be seen in Figure 14.2; however, the equipment sized for Yerington's circuit is larger due to higher PLS flowrates. It will consist of two trains with a total of three solvent extraction mixer-settlers and one stripping mixer-settler for each train. At nominal flow of 24,100 gpm, the extraction mixer-settlers have been designed identically and will accommodate equal flowrates. Each train can operate with one or two stage extraction depending on the volume of flow. Under high flow conditions, the second stage extraction mixer-settler will become the third parallel extraction mixer-settler to accommodate the additional flow. The organic handling equipment includes a crud treatment package. The solvent extraction area is serviced by a foam fire protection system.

After the solvent extraction process, the copper rich electrolyte will combine with the MacArthur copper rich electrolyte for electrowinning. The electrolyte will pass through filters to remove any organics then through a series of heat exchangers to increase the temperature before entering the electrowinning circuit.

After electrowinning, the lean electrolyte from Yerington will be pumped to a storage tank. From the storage tank a portion will return to the Yerington stripping circuit and the balance will be pumped back to MacArthur Site for reuse in the solvent extraction stripping circuit.

14.2.2.6 Yerington Site - Reagent Consumption

Sulfuric acid and pyrite will be used for the sulfide ore heap leaching. The Yerington sulfide ore has a gross acid consumption of 30 lbs sulfuric acid/t ore feed. Only sulfuric acid will be used for the oxide ore and VLT. The consumptions will be 20 and 15 lbs sulfuric acid/tore feed, respectively.

Diluent and extractant will be used in the solvent extraction circuit. All reagents will be delivered by rail or truck. Sulfuric acid will be produced by the sulfuric acid plant at site. The overall reagent consumption per unit and over the course of mine life is summarized below in Table 14.5 and Table 14.6.

Table 14.5: Yerington Site Reagent Consumption
Yerington Pit Gross Sulfuric Acid Units Value
Sulfide lb/ton feed 30
Oxide lb/ton feed 20
VLT lb/ton feed 15
Solvent Extraction Units Value


 

Table 14.5: Yerington Site Reagent Consumption
Diluent gal/ton CU 6.23
Extractant gal/ton CU 1.56
Sulfide Acid ton Acid/ton CU 0.52

Table 14.6: Yerington Site Total Reagent Consumption
Gross Sulfuric Acid Consumption Units Value
Yerington Sulfide ton 3,500,368
Yerington Oxide ton 760,796
Yerington VLT ton 239,223
Total ton 4,500,387
Solvent Extraction Units Value
Diluent gal 3,486,219
Extractant gal 872,932
Sulfide Acid ton 115,961

14.2.2.7 Yerington Site - Utilities

There will be two barge pumps used in dewatering the Yerington Pit Lake water before the pit's operation. A water treatment plant on site will begin with pretreatment filtration, two stage reverse osmosis and precipitation to remove all contaminants to meet the applicable discharge water quality standards. The discharge water will meet the requirements set forth by the NDEP for discharge into surface waters. After the Pit Lake has been dewatered, there will be up to 12 pit dewatering pumps to remove water from the pit during mining operations. The water will also be treated by the water treatment plant before being used as process water, potable water and any excess will be treated and discharged to the Walker River system via a combination of discharge to land for irrigation, directly into the Walker River, and/or the Walker River Irrigation District (WRID) system.

Plant and instrumentation air will be provided by two air compressors, with one as back up.

14.2.3 Electrowinning, Cathode Stripping and Handling

The copper rich electrolyte from MacArthur SX and Yerington SX will combine into one stream. It will pass through a set of parallel dual media filters and heat exchangers to remove any remaining organics and increase the electrolyte temperature.

Guar and cobalt will be added to the copper rich electrolyte before the electrolyte enters the electrowinning circuit. The dosage rates are 0.4 lbs/ST Cu for guar and 3.5 lbs/ST Cu for cobalt sulfate heptahydrate. They will be delivered to site via rail or truck. They will be mixed through a silo and screw feeder with process water.

The electrolyte will be processed in the electrowinning circuit to produce LME Grade A copper cathodes. The electrowinning circuit will consist of 128 cells with 85 lead anode and 84 cathodes. One rectifier will be used for the electrowinning. The nominal design production rate of 75,000 tpy and maximum of 90,000 tpy.


 

Table 14.7: Total Copper LOM Production
Total Copper Production Units  
MacArthur ton 161,610
Yerington ton 559,742
Total ton 721,352

14.2.4 Sulfuric Acid Plant and Cogeneration Plant

Two sulfuric acid plants with a capacity of 1,500 STPD will produce the sulfuric acid needed for both the Yerington and MacArthur Sites. Sulfur prill will be transported onto Site via rail as raw material for sulfuric acid production. Two cogeneration plants will also be in operation in conjunction with the sulfuric acid plants, where a turbine will produce electricity from the excess steam that is generated by the plant. Some of the steam will be used for liquifying sulfur and heating Yerington's PLS. Excess sulfuric acid generated by the acid plants will be sold and transported to the market by train.

14.2.5 Energy Requirements

Power sources assumed to be provide by Utility and on-site co-generation plants. The energy requirement for each major area of the Sites is summarized in Table 14.8.

Table 14.8: Energy Requirement for Major Areas
MacArthur Pit kWh
  Raffinate Pumping 3,408
  PLS Pumping 306
  SX 833
  Water Pumps 225
  Utility 86
  Reagents 66
Total           4,924
   
Yerington Pit kWh
  Crushing 13,200
  HLP Stacking & Agglo 16,202
Raffinate Pumping 3,578
PLS Pumping 1,774
  Nuton 7,005
  Solvent Extraction 1,724
  Process Water 105
  Barge pumps 1,090
  Pit Dewatering Pumps 1,877
  Water treatment 443
  Utility 86
  Reagent 9
Total         47,093
Water Treatment Plant               690
Electrowinning  
  Energy use (kW) 22,400


 

Table 14.8: Energy Requirement for Major Areas
  Power Use (kWh/ST Cu) 2,071
   
Acid Plant & COGEN  
  Acid Plant (kWh/ST Cu) 47
  COGEN (kW) 85
  Power Generation @100% cap. 286

 

14.3 QP ADEQUACY STATEMENT

The QP and Samuel Engineering believe the facilities and descriptions of the processing areas are appropriate and consistent with other current operations and studies for similar facilities.  Equipment selections are based on appropriate process modeling and include vendor consultations where required.  The information is suitable for use in establishing reasonable prospects for economic extraction for the mineral reserves, the mine plans, and financial analysis. 


 

15.0 INFRASTRUCTURE

15.1 INTRODUCTION

The MacArthur and Yerington Sites have similar infrastructure, with Yerington as the main operating site. The major operating and administrative infrastructure will be located at the Yerington Site.

Both MacArthur and Yerington Sites will have the following:

  • Mine Pit(s)
  • HLFs
  • Waste Rock and Storage Facility (WRSF)
  • Raffinate pond
  • Pregnant Leach Solution (PLS) pond
  • PLS event pond
  • Solvent Extraction (SX) facility
  • Pit dewatering and deep well water pumps
  • Overhead power lines with connection to existing substations
  • Railroad spur and railroad offloading
  • Haul Roads
  • Service Roads

The shared infrastructure between the two Sites includes:

  • Railroad
  • Connecting Service Road
  • Intra-site pipelines

The Yerington Site will have the following additional infrastructure:

  • Yerington Stockpiles: coarse ore and fine ore
  • Truck shop
  • Administrative buildings
  • Common Electrowinning (EW) facility
  • Water Treatment Plant
  • Acid Plants (2)
  • Cogeneration Plants (2)
  • Fuel storage

Figure 15.1 shows the site layout of the major infrastructure for the overall Yerington Copper Project Site.


 

Figure 15.1: Yerington Copper Project Site


 

 15.2 ACCESS

15.2.1 Airports

The closest major airport near the Yerington Copper Project site is the Reno-Tahoe International Airport (RNO). It is approximately 73 miles via I-80, NV-439, and US-95 ALT or 76 miles by road via I-580, US-50, and US-95 ALT. The Yerington Municipal Airport (EYR) is a general aviation airport located 1 mile north of the town of Yerington, adjacent to the project site. It is open to the public, but there are no commercial flights available.

15.2.2 Roads

The Yerington Copper Project site is connected to the US interstate road system by US-95 ALT North, approximately 46 miles to I-80 at Fernley, NV, and by US-95 ALT North and then US-50 East to I-580 at Carson City, NV (approximately 60 miles).

15.2.3 Railroad

An existing Union Pacific (UP) rail line is located approximately 11.5 miles north of the town of Yerington at Wabuska. A new rail spur will be constructed to connect with the existing UP rail line approximately 2.5 miles northwest of Wabuska. The rail spur will have a new turnout at the mainline connection point and then travel about 9 miles south to enter the MacArthur Site and then continue approximately 5 miles south to the Yerington Site. Additional spur lines with loading and unloading rail yards will be developed at both the MacArthur and Yerington Sites to facilitate the delivery of consumables and the transportation of the cathode product and excess sulfuric acid to the relevant markets.

Figure 15.1 shows the location of the railroad in pink.

15.2.4 Security

The Yerington Site's primary access is from the existing public, paved road, Luzier Lane. The MacArthur Site's primary access is a new service road off the existing public, paved road, Campbell Lane. Secondary access is being considered from the existing paved Burch Drive and Mason Pass Road. A part new, part existing service road on the project site will be the primary connection between the two Sites, particularly for mining equipment. A control gate and guard post will control access at both primary and secondary access points.

15.3 ACCOMMODATION

Accommodation is not provided on-site as there is residential accommodation for the expected number of site personnel available within 35 minutes of the site in the small towns of Yerington, Mason, and Silver Springs, as well as in the larger town of Fernley, approximately 50 minutes from the site. Reno and Carson City cities are approximately 1 hour and 15 minutes from the site. They could also provide accommodation for some personnel, as well as provide possible manufacturing and industrial services.


 

15.4 MACARTHUR SITE

The MacArthur Site is located five miles northwest of the town of Yerington. It has its own power distribution overhead lines, deep well water supply, and leaching and mining infrastructure.

Figure 15.2: MacArthur Site

15.4.1 MacArthur Site - Raffinate Pond

The raffinate pond will consist of four raffinate pumps, plus one backup pump, and they will pump leach solution onto the heap leach pad. It will also receive streams from process water, sulfuric acid make-up mixed with barren raffinate from MacArthur's solvent extraction circuit, and raffinate make-up from the Yerington raffinate pond.

The raffinate pond will have an operational storage capacity of 12 hours and a total storage capacity of 18 hours, for a design flow rate of 19,016 gpm. It will be 562 ft X 231 ft at the top and 431 ft X 100 ft at the bottom, and it will be 33 ft deep. It will have a volume of 2.75 million cubic ft.


 

15.4.2 MacArthur Site - Water Supply and Management

LCG will need to dewater in the vicinity of the MacArthur Pit area to ensure dry conditions for mining operations. The proposed pit floor is designed at 4,200 ft amsl. LCG anticipates encountering groundwater at the MacArthur Pit at approximately 4,365 ft amsl elevation. Based on the current plan and data available, dewatering will be required at MacArthur toward the end of mining, in Years 3, 4, and 5. Piteau (2025) estimates that dewatering will be required at a rate of approximately 411 gpm to lower the groundwater level elevation by approximately 160 ft (4,200-ft amsl elevation) below the pit floor.

Dewatering infrastructure at the MacArthur Pit will include the following (Figure 15.3):

  • Two 400-gpm capacity 600 to 800 ft deep dewatering wells with 14-inch diameter casing completed to approximately 300 ft below the proposed pit floor (i.e., 3,900 ft amsl)
  • Four 4-inch diameter wells for water quality monitoring
  • Four VWP strings equipped with three VWPs per borehole to confirm groundwater levels
  • Four HE pilot holes

The pit dewatering analysis (Piteau, 2025) assumed that pumping equipment at the MacArthur Pit will be capable of producing approximately 400 gpm or greater at total dynamic heads estimated to range between 270 and 480 ft of head (average head 375 ft).

Figure 15.3: Potential Location for MacArthur Pit Dewatering and Monitoring Wells


 

Based on the screening level evaluation for the MacArthur Pit (Piteau, 2025), the wall rocks are more reactive than the Yerington Pit. Further investigation at the feasibility study level, including humidity cell tests and quarterly groundwater sampling, are required to accurately estimate future pit lake water quality and groundwater chemistry. However, given the relatively small, predicted pit lake volume at MacArthur, pit lake water quality could possibly be managed with periodic amendments during closure, if additional geochemical modeling indicates the potential for any post-closure pit lake water quality to exceed State of Nevada Profile III NRVs (NDEP, 2020).

The pit dewatering wells will supply water to the MacArthur Site as process water. The process water will be used as firewater, make-up water for the raffinate pond, and make-up for the solvent extraction circuit. Some of the process water will also be used as potable water after potable water treatment.

15.5 YERINGTON SITE

The Yerington site is adjacent to and on the west side of the town of Yerington. Like MacArthur, the Yerington site has its own power supply overhead lines, deep well water supply, and leaching and mining infrastructure. Additionally, the Yerington site has a water treatment plant, two cogeneration plants, and two acid plants, as well as a truck shop and administrative buildings.


 

Figure 15.4: Yerington Site

15.5.1 Yerington Site - Stockpiles

There will be two stockpiles located by the primary and tertiary crushing circuit. These stockpiles create operational contingencies between the mine, the crushing circuit, and the heap leaching circuit.

The coarse ore stockpile will have an operational residence time of 12 hours and a live storage capacity of 55,900 tons. It will accommodate the secondary crushing circuit's throughput nominal rate of 4,659 STPH and design rate of 5,591 STPH, and be approximately 137 ft in height.


 

The fine ore stockpile will have an operational residence time of 12 hours and a live storage capacity of 55,9100 tons. It will be approximately 137 ft in height and accommodate the agglomeration and stacking circuits' throughput nominal rate of 4,659 STPH.

15.5.2 Yerington Site - Raffinate Pond

Four raffinate pumps, plus one backup pump, will be used in the raffinate pond to pump leach solution onto the three agglomerators as well as onto the Yerington sulfide and oxide heap leach pads. The pond also receives process water streams from the water treatment plant and returned barren SX raffinate solution. To maintain pH, sulfuric acid will be mixed with the barren raffinate solution before entering the pond.

The raffinate pond will have an operational storage capacity of 12 hours and a total storage capacity of 18 hours for a nominal flow rate of 24,343 gpm. It will be 650 ft X 250 ft at the top, 520 ft X 120 ft at the bottom, and 32 ft deep, with a volume of 3.5 million cubic ft.

15.5.3 Yerington Site - Pit Lake Dewatering

The intent is to dewater the existing Yerington pit lake before expanding the pit with pushbacks primarily to the north, south, and west. The pushbacks would deepen the existing pit from the current elevation of approximately 3,800 ft above mean sea level (amsl) to approximately 3,325 ft amsl. As of December 2024, the pit lake water elevation is at 4,257 ft amsl and is estimated to hold approximately 43,000 acre-ft of water.

Lion CG completed a hydrogeologic assessment to determine dewatering rates and anticipated pit water quality during operation and closure (Piteau, 2025).

The pit lake will be dewatered using a combination of a floating barge pumping system and pit adjacent dewatering wells over four years. During the initial dewatering period, pit dewatering water will be used for construction and other mine-related purposes, with excess water discharged to the Walker River system via a combination of discharge to land for irrigation, directly into the Walker River, and the WRID system. All water from the pit lake would be treated to meet the applicable discharge water quality standards.

During the operational phase of the Project, the pit will continue to be dewatered by using dewatering wells located adjacent to the pit and equipped with submersible pumps to dewater the local bedrock. Dewatering water will be used as an ongoing source of mine water and process water to support operations with the excess being discharged to irrigation or the Walker River.

It is expected that slope depressurization may require HDHs to locally manage pore pressures in selected areas of the pit for geotechnical stability. The timing and need for the HDH program will be further evaluated at the feasibility level, along with a more detailed geotechnical analysis.

Table 15.1 presents the estimated rates for dewatering and discharge of pit lake water. Piteau (2025) assumed an average of approximately 3,000 gallons per minute (4,840 acre-ft/year) for mine water makeup demand for processing, acid plant operation, dust control, and other miscellaneous needs during the Project life.


 

Table 15.1: Estimated Yerington Pit Lake Dewatering and Discharge Rates

Dewatering Sources

Dewatering Discharge Allocation

Time

(Year)

Stage

(ft amsl)

Floating Barge
Dewatering

(gpm)

Dewatering
Wells

(gpm)

Total
Dewatering

(gpm)

Mine Makeup
Water Use

(gpm)

Surplus for
Discharge

(gpm)

Discharge to
Walker River

(gpm)

Surplus for
Discharge

(gpm)

1

4202

7,500

0

7,500

0

7,500

5,150

2,350

2

4150

7,500

0

7,500

0

7,500

5,150

2,350

3

4081

7,500

0

7,500

2,500

5,000

2,650

2,350

4

3979

7,500

0

7,500

2,750

4,750

2,400

2,350

5

3785

2,642

2,860

5,502

2,870

2,632

132

2,500

6

3680

0

3,308

3,308

3,400

-92

0

0

7

3633

0

3,230

3,230

3,500

-270

0

0

8

3586

0

3,313

3,313

3,500

-187

0

0

9

3539

0

3,520

3,520

3,300

220

0

220

10

3492

0

3,701

3,701

3,100

601

0

601

11

3445

0

3,861

3,861

2,800

1,061

0

1,061

12

3398

0

4,003

4,003

2,500

1,503

0

1,503

13

3351

0

4,135

4,135

2,250

1,885

0

1,885

14

3304

0

4,254

4,254

2,250

2,004

0

2,004

Source: Piteau, 2025

Note: amsl= above mean sea level; gpm = gallon per minute


 

The Yerington Pit dewatering infrastructure will include the following (Piteau, 2025):

  • Floating barge pumping system and site distributions system (including discharge to mine process, water treatment plant, and irrigation systems) capable of pumping 8,000 gpm with total dynamic head ranging between 190 ft and 1,250 ft. The barge system is expected to pump at an average rate of 7,500 gpm
  • Eight to 12 perimeter ex-pit dewatering wells (potential locations shown in Figure 15.5), with a minimum production rate of 400 gpm. Each well will be completed with a minimum 14-inch diameter casing from land surface to 3,025 ft (approximately 1,400 and 1,600 ft deep), which is approximately 300 ft below the proposed 3,325 ft amsl pit floor, to enable the wells to maintain adequate freeboard beneath the pit
  • Submersible pumping equipment and column casing installed in each of the dewatering wells. Pumping equipment will need to be capable of producing 400 gpm or greater at total dynamic heads estimated to range between 600 to 1,400 ft of head (average head 970 ft)
  • Eight Vibrating Wire Piezometers (VWP) strings equipped with three VWPs per borehole to confirm groundwater levels meet the required dewatering targets and to monitor levels between the Yerington Pit and the Walker River

Additional groundwater monitoring wells are not expected to be required for the Project as existing monitoring wells used for site characterization likely provide sufficient groundwater monitoring capacity for mine operations.

Lion CG intends to drill pilot holes, also known as Hydrogeologic Exploration (HE) boreholes, to confirm the appropriate dewatering well locations. The HE boreholes also provide an opportunity to collect additional hydrogeologic data. These boreholes will be drilled with a conventional 6-inch diameter reverse circulation drill rig. Each HE hole will be equipped with VWPs and will serve as near well monitoring locations to track dewatering performance during operations.

At various stages of the mining process, in-pit wells or sumps may be required to capture groundwater that cannot be captured by the ex-pit dewatering system.


 

Figure 15.5: Potential Location for Yerington Pit Dewatering Wells

The water quality of the existing Yerington pit lake is well established through the extensive site characterization work completed by previous owner ARC in the late 1970s. Water chemistry in the pit lake has been circum-neutral (7.1 to 8.6) since monitoring began in 1991. The lake has met groundwater's Nevada Reference Values (NRVs, Profile I; NDEP, 2021) for all parameters except selenium (0.039-0.14 milligram per liter [mg/L]) and uranium (0.028-0.031 mg/L). Selenium concentrations have steadily decreased with time and are now approximately 70 percent lower than initial measurements in 1991 (Piteau, 2025). This is likely due to dilution from continued filling and the east wall alluvial seeps. Uranium data are sparse, therefore, temporal concentration trends are not established (Piteau, 2025).

The pit lake water is saturated with respect to several carbonate and oxide mineral phases (Piteau, 2025). Key mineral phases include barite, calcite, dolomite, ferrihydrite, fluorite, malachite, magnetite, and tenorite.

The pit lake water quality is expected to generally remain good during the initial 4-year dewatering period (i.e., neutral pH and meeting Profile I NRVs for all constituents but uranium) (Piteau, 2025). During the dewatering phase, some sulfide materials will be progressively exposed on the highwall which may oxidize and leach additional acidity, selenium, and uranium. However, the percentage of surface seepage from the highwall will be very low compared with the volume of water stored in the pit. (Piteau, 2025).


 

Future pit lake water quality (i.e., in the recovered Yerington Pit) is anticipated to resemble the present-day chemistry, since the contributing factors of groundwater seepage quality and pit wall geochemistry are not expected to materially differ from the current pit (Piteau, 2025).

15.5.4 Yerington Site - Water Supply and Water Treatment

The Yerington Pit will have two dewatering barge pumps in operation two years during initial construction and will continue into the first two years of operation. They will be capable of pumping at least 8,000 gpm for an average of 7,500 gpm for the first 4 years of pumping and will decrease to 2,650 gpm and cease pumping the following year to remove a total of 52,700 acre-ft of pit lake water. Additionally, eleven (11) 400-gpm capacity, 1,400 to 1,600 ft deep, perimeter dewatering wells will be installed and begin operation in Year 3 of the Project with dewatering rates ranging from 2,900 gpm to 4,300 gpm.

All the water supplied by the Yerington Pit barge pumps and dewatering wells will be pumped by underground pipe to a water treatment plant located in the Yerington process facilities area. The water treatment plant will consist of a microfiltration skid and an ion exchange system to remove major impurities, followed by reverse osmosis. All treated water from the water treatment plant will meet or exceed the discharge standards established by the NDEP. Water from the water treatment plant will be used for process, firewater, mining operations, and a small amount will be used for potable water after further treatment through a potable water treatment system. The remaining treated water will be discharged to the environment, specifically the Walker River surface water system.

15.6 SUPPORT BUILDINGS

15.6.1 Truck Shop and Administrative Buildings

There will be a truck shop building and three administrative trailers on site, located near the sulfuric acid plant and east of the secondary crushing circuit. See Figure 15.4 for Project location. The truck shop has 12 truck shop bays to service light to heavy-duty mobile equipment, ranging from site utility vehicles to haul trucks. The shop will be 300 ft by 120 ft. The general layout of the truck shop is shown in Figure 15.6.

Figure 15.6: Truck Shop General Layout


 

 

The three administrative trailers will be located adjacent to the truck shop. Each one consists of five closed-door offices with an open office area. It has two bathrooms and two open areas that can function as a kitchen and conference area. Each trailer will be 36 ft by 40 ft. The general layout of an administrative trailer is shown in Figure 15.7.

Figure 15.7: Administrative Trailer General Layout

15.7 MACARTHUR-YERINGTON PIPELINES

There will be four major pipelines that will transfer solutions between the Yerington Site and the MacArthur Site. At the MacArthur Site, a 10 ¾-inch pipeline will allow raffinate solution to be pumped between the MacArthur raffinate pond and the Yerington raffinate pond. Another 12 ¾ -inch pipeline will allow the MacArthur's rich electrolyte to be pumped and combined with the electrolyte at the Yerington copper-rich electrolyte tank located at the Yerington Site's SX facility.

At the Yerington Site, a 12 ¾-inch pipeline will allow the lean electrolyte from the Yerington site to be pumped back to the MacArthur site's solvent extraction circuit. Additionally, there will be a pipeline connecting the Yerington sulfuric acid storage tank to the MacArthur sulfuric acid tank. This pipeline supplies acid from the sulfuric acid plant to the MacArthur site with the needed acid for its leaching operation.

The dark blue line in Error! Reference source not found. indicates the location of the pipeline between the MacArthur Site and the Yerington Site.

15.8 HAUL ROAD

The new haul roads will be 65' wide with berms and side ditches for an approximate distance of 5.9 miles. One MacArthur segment will run from the northeast end of the MacArthur Pit heading northeast to the southeastern side of the MacArthur HLF. The other MacArthur segment runs east from the northeast corner of the Gallagher Pit to and along the south side of the MacArthur Pit and then continues to the southeast to the MacArthur WRSF (see Figure 15.2). The Yerington haul road runs from the northwestern end of the Yerington Pit to the southern end of the Yerington Oxide HLF (see Figure 18-3). Haul trucks will utilize the existing connecting service road that runs from the eastern side of the MacArthur Pit to the northwest side of the Yerington Pit for maintenance purposes. The brown lines in Figure 18.1 and all other site plans show the intended path of the new haul roads.


 

15.9 SERVICE ROAD

There will be two new plant entrances. The one for the Yerington site will be just west of Alternate 95 and north of the Yerington Oxide HLF near Scarsdale Drive. The other new plant entrance will be about two miles west of Alternate 95 near the intersection of Campbell Lane and Rosaschi Road.

Existing service roads will be used as much as practical. The new service roads will be 30' wide with berms and side ditches for an approximate distance of 6.2 miles. The new service roads are on both sides of the Yerington process facility and along the Yerington Crushing Circuit. At MacArthur, the new service road will run from the new plant entrance south to the MacArthur SX facility and then continue south-southeast connecting with the existing service road that leads to the Yerington site. The solid green lines in Figure 15.1 show the intended new service roads.

15.10 FUEL

Fuel will be delivered to Site by fuel skids on delivery trucks or by rail as determined by Operations. The fuel storage is located by the truck shop. Typical fuel storage will be approximately three days.

15.11 POWER SUPPLY AND ELECTRICAL DISTRIBUTION

Existing power infrastructure includes the Fort Churchill Power Plant approximately 7.5 miles northeast of MacArthur, a utility substation to the south of the Yerington Pit and overhead 69 kV Medium Voltage utility lines in the vicinity of both the Yerington and MacArthur sites. The existing electrical infrastructure appears adequate to support the Yerington Copper Project with expected minimal upgrades.

Figure 15.8 below displays the electrical layout for the Yerington Site. The teal color line indicates the 13.8 kV distribution overhead line, and the green line indicates the existing 69 kV utility overhead power line connection. The layout also indicates the location of the power distribution center (PDC) for the Yerington heap leach, SX/EW and the crushing circuit.


 

Figure 15.8: Yerington Site Power Distribution

The existing 69 kV Medium Voltage (MV) transmission line running through the Yerington Site from the utility grid originating from the nearby utility substation to the south of the Yerington Pit will be connected by a distribution overhead power line to a 69 kV/13.8 kV substation transformer to cover the electrical requirements needed for the Yerington Site. The 69 kV line runs close to the substation and does not require substantial material infrastructure for connection. The connection from the existing 69 kV line to the main substation transformer will be through a short section of overhead power line with a single circuit structure. The main substation consists of a 70 MVA, 69 kV/13.8 kV Step-down transformer and feed with medium voltage cables to a 13.8 kV, MV Switchgear. The transformer will feed roughly 90% of the plant loads under normal operation. The transformer is to be installed in the central area of the Yerington Site to facilitate the distribution of the 13.8 kV overhead power distribution lines feeding the other areas.

At the Yerington Site, the substation transformer and medium voltage switchgear will distribute 13.8 kV power via overhead distribution lines to all areas of the project, including the SX/EW process plant, administration building, sulfuric acid plant, transformer/rectifier, crushing/conveying facilities, PLS pumps, raffinate pumps, and the HLFs. Individual Power Distribution Center (PDC) buildings and MV to Low Voltage (LV) transformers are located strategically around the Site to provide power and controls to individual areas and processes, and to minimize distances of LV power circuit runs.

Figure 15.9 below displays the power distribution for the MacArthur Site. The teal line indicates the 4.16 kV distribution overhead line, and the green line indicates the existing 69 kV utility overhead power line. It also indicates the 69kV utility overhead power line connection, and the Macarthur SX PDC.


 

 

Figure 15.9: MacArthur Site Power Distribution

At the MacArthur Site, there is an overhead 69 kV power line running approximately one mile to the east of the SX Process Facility area that will be connected by a distribution overhead power line to a 69 kV/4.16 kV, 10 MVA Pad-mounted transformer to cover the electrical requirements for the MacArthur Site. The pad-mounted transformer will distribute 4.16 kV power via overhead distribution lines to all project areas, including the SX process plant and the Heap/Leach, PLS pumps, and Raffinate pumps areas. Individual PDC buildings and MV to LV transformers are located strategically around the Site to provide power and controls to individual areas and processes and minimize distances of LV power circuit runs.

15.12 STORMWATER MANAGEMENT

Stormwater will generally be managed by keeping contact water separate from non-contact water. Contact water can be considered stormwater, process-related solution, or effluent that may come in contact with the containment areas, such as HDPE lining systems, process plant components, or water/solution that has been in contact with ore or process solution.


 

The stormwater diversion system limits upgradient runoff reporting to the open pits, HLFs, WRSF, or the solution ponds. This ensures that stormwater management is sized for direct precipitation falling on the facility. Design considerations include the following criteria:

  • On-site and off-site drainage were evaluated for the 100-year, 24-hour duration event
  • As much of the off-site drainage as possible will be diverted around the facilities. In determining the area to be diverted, consideration was given to topographic conditions, layout of the facility, feasibility of, and costs associated with diversion channel construction
  • On-site drainage must be accommodated, collected, and retained so that precipitation from the design storm event that falls on the HLF will not exit the site as surface flow. Every reasonable effort shall be made to minimize the possibility of a leachate spill and discharge to the surface lands surrounding the site

Sediment ponds have been included at the base of the WRSFs to temporarily detain runoff from the WRSF before discharging downstream, preventing sediment-laden water from exiting the Project area. The proposed Yerington WRSF, currently sited on top of the existing South Waste Rock Area, was assumed not to need any additional control beyond what is already in place for the existing facility.

15.13 HEAP LEACH FACILITIES

15.13.1 HLF Designs

Leachable oxide ore (MacArthur and Yerington East) will be ROM and truck-stacked in nominal 30-foot lifts. Leachable sulfide ore (Yerington West) will be crushed, agglomerated, and conveyor-stacked in nominal 30-foot lifts. The assumed in-place dry density is 115 pounds per cubic foot (pcf) for both ore types. The heaps were designed with 3H:1V overall side slopes to accommodate the closure footprint. During operations, slopes will include benching and steeper inter-bench face slopes. The maximum heap height for all three facilities will be 330 ft, as measured from the top of the lining system to the top of the heap.

The MacArthur HLF was sited towards the northern extent of the Project, entirely on native ground, and designed as two phases to contain the estimated 166 million dry tons of leachable oxide ore coming from the MacArthur pits. The total MacArthur HLF footprint is approximately 390 acres.

The Yerington West HLF was designed with a total of three phases to accommodate the estimated 234 million dry tons of crushed and agglomerated sulfide ore from the Yerington Pit. Roughly half of its footprint is on native ground, and half is on disturbed ground currently occupied by VLT from legacy mine operations. The upgradient starter facility is sited on native ground. It can be constructed and operated while the VLT is being removed to accommodate the Phase 2 and Phase 3 expansions to the east. The total Yerington West HLF footprint is approximately 560 acres.

The Yerington East HLF was sited on the southern portion of the legacy sulfide tailings facility. The HLF was designed to contain 140 million dry tons of oxide ore coming from the VLT and Yerington pits. The total Yerington East HLF footprint is approximately 320 acres and will be constructed in two phases.

The HLFs were designed to meet the requirements outlined in the Nevada Administrative Code, including an 80-mil (2 mm) double-sided textured HDPE geomembrane liner underlain by 12 inches of compacted soil with a hydraulic conductivity less than 1x10-6 cm/s. The borrow source for this low permeability material, referred to as underliner, is currently envisaged as the northern end of the legacy sulfide tailings facility based on the PFS-level geotechnical investigations. However, additional geotechnical investigations, chemical testing, and permitting discussions are required at future stages to confirm that the fine-grained sulfide tailings can be used as underliner.


 

Each pad will have a solution collection system consisting of a network of perforated pipes placed on the HDPE liner and covered with a layer of drainage material, referred to as overliner. The pipes were sized based on the pad area reporting to each pipe and the proposed raffinate application flow rate. The design consists of secondary 4-inch perforated collection pipes reporting to primary 8-inch to 24-inch perforated header pipes arranged in a dendritic pattern across the geomembrane-lined areas. The spacing between pipes, in conjunction with an assumed overliner permeability of 2x10-1 cm/s, was designed to limit the hydraulic head on the liner system.

The perforated pipes will transition to solid-wall pipes to convey solutions to the PLS ponds. The PLS for each HLF were sized to provide enough storage for 12 hours of pregnant solution draindown as an operational inventory and an additional 24 hours of draindown for power loss events, with 3 ft of freeboard. The PLS ponds are intended to hold pregnant solution on a day-to-day basis. The adjacent event ponds, connected to the PLS ponds by a spillway, are intended to provide additional contact-water storage necessary during design storm events. The event ponds were sized to contain the volume of contact water runoff reporting from the HLF during the 100-year, 24-hour design storm event with 3 ft of freeboard. Each HLF has its own set of ponds, and the Yerington West Starter facility has a supplemental pond system because the Starter facility will be constructed upgradient from the pad expansion to allow for the VLT to be removed.

Consistent with the Nevada Administrative Code, the PLS pond is designed to be lined with two layers of geomembrane, separated by a layer of geonet with a leak detection and return system. The PFS design assumed the ponds are underlain by 12 inches of low permeability (<1x10-6 cm/s) underliner material. The liner selected for the ponds is 80-mil (2 mm) double-sided textured HDPE. The event ponds have been designed with the same liner system as the PLS ponds to allow for increased operational flexibility.

15.13.2 HLF Phasing

Phasing for each facility was determined based on constructability, mine plan, operational parameters, and minimizing the Starter configurations where possible to defer CAPEX. Table 15.2 summarizes the HLF phasing by facility.

Table 15.2: HLF Phasing
Facility Phase Estimated Construction Year Years of Operation Designed Capacity
(million tons)
MacArthur Starter Year 0 Year 1 to 2.5 87
Phase 2 Year 2 Year 2.5 through 6 79
TOTAL     166


 

Table 15.2: HLF Phasing
Facility Phase Estimated Construction Year Years of Operation Designed Capacity
(million tons)
Yerington West Starter Year 2 Year 3 to 6.5 65
Phase 2 Year 6 Year 6.5 to 9.5 104
Phase 3 Year 9 Year 9.5 through 12 65
TOTAL     234
Yerington East Starter Year 2 Year 3 to 5.5 91
Phase 2 Year 5 Year 5.5 through 8 49
TOTAL     140

Figure 15.10 shows the Starter and Ultimate configurations for the MacArthur HLF.

Figure 15.10: MacArthur Starter and Ultimate HLF


 

Figure 15.11: Yerington West Starter and Ultimate HLF


 

 

Figure 15.12: Yerington East Starter and Ultimate HLF

15.13.3 HLF Geotechnical Investigations

The primary goals of the PFS-level geotechnical investigations were to characterize the subsurface conditions at the Yerington and MacArthur properties, evaluate potential borrow sources for construction materials to inform the PFS-level CAPEX, and inform geotechnical evaluations. The investigations were completed in two phases. The first phase included excavating 14 test pits and drilling 11 geotechnical boreholes at the MacArthur Property and locations adjacent to the Yerington Property, on land controlled by the BLM. The second phase consisted of 12 Cone Penetration Tests (CPT) and 14 geotechnical boreholes at the Yerington legacy sulfide tailings facility.

NewFields supplemented the data collected through the PFS-level geotechnical investigations with information from several other drilling campaigns throughout the facility closure and maintenance.

Subsurface conditions at the Yerington East HLF generally consist of a layer of VLT between 2 to 15 ft in thickness, overlying sulfide tailings comprised of very loose to medium dense, poorly graded and clayey sands and very soft to medium stiff clays and silts. The sulfide tailings are underlain by alluvium consisting of medium dense to very dense sands. The thickness of the sulfide tailings varies across the facility, between 40 ft at the southern portion of the facility and up to 70 ft near the western and northern portions. Based on the pore pressure dissipation and laboratory testing results, the sulfide tailings are considered saturated.


 

The Yerington West HLF is sited over a native alluvial fan, and the VLT stockpiles. Prior to the construction of the ultimate facility, the VLT stockpiles located in the eastern portion of the proposed HLF footprint will be removed and reprocessed. Based on the proposed facility's location, subsurface conditions across the Yerington West HLF generally consist of VLT underlain by native alluvium and bedrock. The VLT stockpiles are typically coarse-grained soils and are up to a maximum of 150 ft thick. The native alluvial soil is generally dense to very dense coarse-grained interbedded sands and gravels with clay and silt lenses. The thickness of the alluvium increases towards the eastern footprint of the Yerington West HLF, on the order of 300 ft. Bedrock in the vicinity is characterized as quartz monzonite and weathered tuffs (Proffett and Dilles, 1984).

Subsurface conditions at the MacArthur HLF generally consist of a surficial layer of growth media approximately 0 to 1 foot in thickness, overlying alluvium consisting of medium dense to very dense, fine to coarse sands and gravels with a lens of fine-grained soil encountered in the northeast portion of the HLF study area. The thickness of the alluvium varies across the MacArthur HLF between 0 to 400 ft thick, generally increasing downslope of the alluvial fan, towards the eastern edge of the MacArthur Property.

At the conceptual MacArthur WRSF, subsurface conditions generally consist of shallow bedrock, locally mapped as quartz monzonite and tuffs (Proffett and Dilles, 1984). These materials excavate as clayey sands and gravels with increasing cobbles and boulders with depth to excavator refusal.

Several earthworks materials, including underliner, overliner, common fill, and structural fill, will be needed for the HLF construction. The borrow investigations were limited and were completed for PFS-level engineering only. Additional investigations and evaluations will be required during future studies to sufficiently evaluate construction material sources.

The sulfide tailings in the northern part of the facility, outside the HLF footprint, were assumed to be sufficient for use as an underliner borrow source based on limited geotechnical laboratory testing. The permeability of near-surface sulfide tailings samples met the minimum Nevada requirement for hydraulic conductivity of underliner materials (NAC, 2023); however, additional chemical testing and permitting discussions are required at future stages to confirm that the fine-grained sulfide tailings can be used as underliner.

Potential overliner feed rock sources were identified at the Yerington Property, including material from the legacy W-3 Waste Rock Area, legacy HLF material, EPA/North Pit Stockpile, and the South Waste Rock Area. Fresh rock from open-pit mining operations at either the MacArthur or Yerington Pits may also be suitable for use as overliner after crushing and screening.

Common fill and structural fill may be sourced from the more granular surficial native soils at both the Yerington and MacArthur Properties, or the coarse-grained material encountered at the legacy sulfide tailings.


 

15.13.4 Geotechnical Evaluations

Geotechnical evaluations such as liquefaction potential, slope stability, and settlement were completed at the different candidate HLF locations based on the subsurface conditions encountered during the geotechnical investigations. The soils underneath the MacArthur and Yerington West HLF are not anticipated to undergo static or cyclic liquefaction; however, the legacy sulfide tailings beneath the Yerington East HLF are susceptible to static and cyclic liquefaction. The Yerington West and MacArthur HLFs were designed to meet regulatory requirements and industry accepted stability standards for slope stability factor of safety (NDEP-BMRR, 2021). For the Yerington East HLF, a stability key and rockfill buttress are required along the northern portion to meet stability requirements and were incorporated into the PFS designs. Settlement of the Yerington West and MacArthur HLFs should not affect performance of the HLF geomembrane liner and drainage. Maximum settlement was estimated on the order of 6.5 ft for the Yerington East HLF due to the presence of a low-strength, saturated, fine-grained layer in the sulfide tailings and the grading plan was adjusted to account for potential for differential settlement.

15.13.5 Regulatory Requirements and Operational Safety

The HLFs and associated structures have been designed to meet regulatory requirements and industry-accepted standards and practices, and are suitable for a PFS-level design. Additional investigations, evaluations, and analyses will be required at subsequent design phases to confirm assumptions and reduce the risk of encountering unforeseen conditions during construction.

During construction, a rigorous Construction Quality Assurance (CQA) program will be implemented to ensure the construction materials meet or exceed specified values that are key to HLF performance. Materials not meeting the specifications will either not be used in construction or approved after confirming the deviations will not negatively impact facility performance through modeling or other analyses, evaluations, and calculations.

A robust Operations, Maintenance, and Safety (OMS) manual will be a key component to ensure operations and monitoring controls are in place for the structure's lifecycle. The OMS manual will include instrumentation and monitoring to provide early warning for potentially unstable conditions. These early warning systems will allow operators to monitor conditions at the HLF and provide recommendations if values trend toward thresholds for potentially unsuitable levels. The CAPEX includes preliminary instrumentation and monitoring systems.

16.0 MARKET STUDIES AND CONTRACTS

16.1 COPPER

The base-case copper price used in the economic analysis is US $4.30 per pound, stated in U.S. dollars and current as of July 31, 2025. This principal assumption is derived from a methodology that emphasizes historical pricing and is supplemented by an independent third-party outlook from S&P Global. Historical pricing is given greater weight, using a recent trailing average of actual traded prices through the end of July 2025. The forward-looking component draws on S&P Global's commodity briefing service issued in mid-June 2025 and reflects their near- to medium-term view for Copper.


 

16.2 HISTORIC

As of July 31, 2025. e = estimate; f = forecast; LME = London Metal Exchange; Moz = million ounces. Sources: S&P Global Commodity Insights; London Stock Exchange Group. The historic 12-month LME copper price averages $4.24/lb. with a 6-month trailing price of $4.34/lb.

Figure 16.1: 1-Yr Trailing Historic LME Copper Price

16.3 FORWARD

Table 16.1: Copper Price Forecasting
  2024e 2025f 2026f 2027f 2028f 2029f 2030f
Supply (tons) 24,637 25,290 26,403 27,136 27,465 28,249 28,860
Demand (tons) 24,363 25,035 25,936 26,788 27,559 28,123 28,599
Refined balance (tons) 274 255 467 348 -94 126 261
LME 3M price ($/ton) 8,407 8,522 8,351 8,313 8,555 9,019 9,242
LME 3M price ($/lb) 4.20 4.26 4.18 4.16 4.28 4.51 4.62

As of July 31, 2025. e = estimate; f = forecast; LME = London Metal Exchange; Moz = million ounces. Sources: S&P Global Commodity Insights; London Stock Exchange Group

Applying this historically dominant blend produces a reference level that is above US $4.30 per lb., while the third-party forward outlook aligning with the project execution timeline sits at or above the US $4.30 per lb. level. Selecting US $4.30 per lb. therefore represents a reasonable base-case input for a prefeasibility study analysis and is consistent with the requirement to justify principal assumptions using both historical information and an independent external view.

This section contains forward-looking information based on assumptions, including the copper price assumption stated above. Actual results may differ due to risks and uncertainties described elsewhere in this report and in the issuer's continuous disclosure


 

16.4 SULFUR

The sulfur supply price used for acid production in the economic analysis is US $102 per ton. The principal assumption is derived a trailing 12-month average sulfur price from Q1 2024 through Q1 2025. Sulfur prices are historically very volatile. Demand growth is outpacing supply growth driving current market conditions.

16.5 SULFURIC ACID

The sulfuric acid sale price used in the economic analysis is US $121 per ton. The principal assumption is a May 2025 spot price.

Sources: Intratec

Figure 16.2: 1-Yr Trailing West Cost Sulfuric Acid Market Price

It is recommended that Lion CG engage with potential buyers and sulfuric acid trading/distributors that supply sulfuric acid to the western United States to improve future selling costs during the feasibility study.


 

17.0 ENVIRONMENTAL STUDIES, PERMITTING AND PLANS, NEGOTIATIONS, OR AGREEMENTS WITH LOCAL INDIVIDUALS OR GROUPS

17.1 ENVIRONMENTAL BASELINE STUDIES

This section outlines the current permitting status, future anticipated requirements, and available information on environmental studies for the Yerington Copper Project, along with the general closure and reclamation plan and associated cost estimate. Potential social and community considerations and factors, including stakeholder engagements, are also presented in this section.

17.2 PROJECT PERMITTING

The Yerington and MacArthur Properties are on private and federal land administered by the BLM Sierra Front Field Office in the Carson City District. Proposed mining operations for the Project will require authorization from Federal, State, and local regulatory agencies, supported by requisite studies and analyses, along with public involvement.

Table 17.1 provides an overview of the anticipated Federal, State, and County permits and approvals that may be required to dewater the Yerington Pit and construct/operate the Yerington Copper Project. This preliminary list of permits/authorizations may require modifications as additional mine planning and engineering designs are completed and results of baseline characterization studies and analyses are available.

Table 17.1: Anticipated Permit Requirements
Permit Regulatory Agency
Federal Permitting
Mine Plan of Operations/Record of Decision U.S. Department of the Interior, Bureau of Land Management (BLM)
Incidental Take Permit (Golden Eagle) U.S. Fish and Wildlife Service (USFWS)
404 Permit U.S. Army Corps of Engineers (USACE)
Right of Way on Public Land (Railroad Spur) U.S. Bureau of Land Management (BLM)
Certificate to Construct, Acquire, or Operate Railroad Line U.S. Surface Transportation Board (STB)
Explosives Permit U.S. Department of Treasury, Bureau of Alcohol, Tobacco, Firearms, and Explosives
Hazardous Waste Identification Number Environmental Protection Agency (EPA)
Mine Identification Number Mine Safety and Health Administration (MSHA)
State Permitting
Water Pollution Control Permit (Project and pit dewatering) Nevada Division of Environmental Protection (NDEP)
Bureau of Mining Regulation and Reclamation (BMRR)
Reclamation Permit Nevada Division of Environmental Protection (NDEP)
Bureau of Mining Regulation and Reclamation (BMRR)
Air Quality Permit Nevada Division of Environmental Protection (NDEP)
Bureau of Air Pollution Control (BAPC)
Water Rights Appropriation Nevada Division of Water Resources (NDWR)


 

Table 17.1: Anticipated Permit Requirements
Permit Regulatory Agency
Stormwater National Pollutant Discharge Elimination System (NPDES) Multi-Sector General Permit (MSGP) for Stormwater/ Stormwater Pollution Prevention Plan (SWPPP) Nevada Division of Environmental Protection (NDEP)
Bureau of Water Pollution Control (BWPC)
Spill Prevention, Control, and Countermeasure Plan (SPCC) Nevada Division of Environmental Protection (NDEP)
Bureau of Water Pollution Control (BWPC)
Individual NPDES Permit for Discharge to Surface Waters Nevada Division of Environmental Protection (NDEP)
State Groundwater Permit Nevada Division of Environmental Protection (NDEP)
Bureau of Water Pollution Control (BWPC)
Section 401 Certification Nevada Division of Environmental Protection (NDEP)
Bureau of Water Pollution Control (BWPC)
Working in Waterways Permit Nevada Division of Environmental Protection (NDEP)
Bureau of Water Pollution Control (BWPC)
Notice of Dam Construction* Nevada Division of Water Resources (NDWR)
Water Rights Appropriation Nevada Division of Water Resources (NDWR)
Dam Safety Permit* Nevada Division of Water Resources (NDWR)
Public Water System Permit NDEP, Bureau of Safe Drinking Water
Hazardous Waste Management Permit NDEP, Bureau of Waste Management
Industrial Artificial Pond Permit Nevada Department of Wildlife, Habitat Division
Septic System Permit Nevada Division of Public Health
Hazardous Materials Permit State Fire Marshal
Hazardous Materials Storage Permit State Fire Marshal
Local (County)
Project Notification Lyon County
Special Use Permit Lyon County
Building Permit Lyon County
Business License Lyon County

Note:

*: Not anticipated at this time, but if the Heap Leach Facility (HLF) ponds are deemed jurisdictional dams, these permits may be required.

17.2.1 Existing Permits and Authorizations

The Project has obtained all permits required to conduct site exploration necessary to support mine planning and development of this PFS. These permits include Exploration Plan of Operations from BLM, Reclamation Permit from NDEP BMRR, and temporary discharge permits from NDEP BWPC. Table 17.2 lists the permits that Lion CG has secured at the time of this report.

Table 17.2: Major Existing Project Permits
Permit Name Permit Identifier Most Current
Issued Date
Issuing Agency
MacArthur Exploration Plan of Operations NVN-085212 Sept. 17, 2024 BLM


 

Table 17.2: Major Existing Project Permits
Permit Name Permit Identifier Most Current
Issued Date
Issuing Agency
Yerington Exploration Reclamation Permit #0321 Nov. 13, 2024 NDEP BMRR
MacArthur Exploration Reclamation Permit #0294 Aug. 12, 2024 NDEP BMRR
Yerington Class II Air Quality Operating Permit AP1629-4669 June 18, 2024 NDEP BAPC
MacArthur Class II Air Quality Operating Permit AP1629-4668 June 18, 2024 NDEP BAPC
Yerington Temporary Authorization to Explore TNEV2024106 Dec. 10, 2024 NDEP BMRR
Yerington Stormwater Construction General Permit CSW-54058 June 27, 2024 NDEP BWPC
MacArthur Stormwater Construction General Permit CSW-54053 June 27, 2024 NDEP BWPC

17.2.2 Federal Permitting Requirements

Lion CG intends to prepare an MPO in accordance with BLM 43 CFR 3809 Surface Management regulations and Nevada guidance for Preparation of Operating Plans for Mining Facilities (NAC 445A.398). The BLM, the lead agency, and NDEP BMRR will concurrently review the Project MPO, including the Reclamation Plan Permit Application, under a MOU between these two agencies (BLM Agreement No. BLM-MOU-NV21-3809-2019-014).

BLM's NV-IM 2024-019 provides the protocol all Nevada BLM offices must follow for processing and approving federal actions, including implementation and procedural guidance for project initiation and preplanning, NEPA compliance, and ensuring consistent compliance with applicable regulations when authorizing federal actions. NV-IM-2024-019 reduces permitting uncertainty by establishing specific reporting requirements and milestones and allowing for a robust NEPA process with shortened timelines.

NEPA requires BLM to assess the environmental effects of the proposed action prior to making decisions. Lion CG anticipates that the BLM will determine that an (EIS)-level review will be required for the Project. Under NV-IM-2024-019, the time limitation to complete the NEPA analysis and issue a Record of Decision (ROD) for an EIS is 1 year.

NV-IM-2024-019 describes the initial project review process (pre-NEPA) which includes submittal of a project proposal (Pre-MPO), multi-agency/stakeholder baseline kickoff meeting, and determination of baseline surveys requirements (Baseline Data Needs Assessment Form [BNAF]). Under this NV-IM, all baseline reports as determined by the BNAF, the MPO and Reclamation Plan Permit Application, Supplemental Information Report (SIR), and Supplemental Environmental Reports (SERs) need to be completed and approved by BLM prior to initiating the NEPA process. The SIR provides a detailed description of the proposed action, no action, and alternatives considered. An SER provides a summary of the proposed action and alternatives considered, a detailed description of the affected environment, and detailed effect analysis.


 

The Project's permitting schedule may benefit from implementation of the EO 14241 titled Immediate Measures to Increase American Mineral Production issued in March 2025 to streamline permitting processes for mining projects, particularly those focused on critical minerals. In addition to this EO and BLM Nevada direction, Lion CG also recognizes recent changes made to NEPA and assumes BLM will comply with the Department of Interior's (DOI's) July 3, 2025 Interim Final Rule, including adherence to 516 DM 1 - US DOI Handbook of NEPA Implementing Procedures. Depending on baseline data needs as determined by BLM and seasonality considerations for certain field surveys, the pre-NEPA tasks listed above could require 18 to 24 months to complete. Preliminary permitting schedule estimates the submittal of the MPO (and completeness determination) and NEPA process (including all pre-NEPA tasks as outline in NV-IM-2024-019) will require between 2.5 and 3.5 years.

Construction of the rail spur will require a Right of Way (ROW) permit from the BLM and a Certificate to Construct, Acquire, or Operate Railroad Line from the Surface Transportation Board (STB) under 49 CFR 1150. Lion CG may proceed with the ROW application in a separate process from the MPO. Lion CG must also comply with the Energy and Environmental Regulations at 49 CFR parts 1106 and 1105, including consulting with the Board's Office of Environmental Analysis at least 6 months prior to filing an application, to begin the scoping process to identify environmental issues and outline procedures for analysis of the proposal.

Any disturbance below the ordinary high-water mark of Walker River or an adjacent wetland (including installation of discharge infrastructure such as piping) would trigger involvement by the U.S. Army Corps of Engineers (USACE) under Section 404 of the Clean Water Act (CWA). The Walker River is jurisdictional Waters of the U.S. (WOTUS) given it is an interstate waterway (Nevada-California) and the primary tributary to Walker Lake. USACE issued a Navigable-in-Fact determination on Walker Lake in February 2022.

Raptor surveys were completed in 2022 (WRC, 2022), 2023 (WRC, 2023), and 2024 (WRC, 2024). Golden Eagle nests have been observed within or near the Project area during each survey event. Lion CG may need to apply for an Incidental Take Permit with the United States Fish and Wildlife Service (USFWS) under the Bald and Golden Eagle Protection Act (50 CFR 22). If an Incidental Take Permit is required, USFWS will also conduct some level of review under NEPA.

Other federal permits that may be required include explosives use permit from the Bureau of Alcohol, Tobacco, Firearms, and Explosives and a hazardous waste identification number from the EPA.

Lion CG anticipates securing all required Federal permits and authorizations needed to construct and operate the Project within reasonable and normal timeframes.

17.2.3 State Permitting Requirements

The State of Nevada requires permits for all mineral exploration and mining operations regardless of the land status. At the State level, the Project will require a Reclamation Permit, one or more WPCP(s) for mine operations and pit dewatering, and an Air Quality Permit to construct and operate.

The subsections below present additional information on key State permitting efforts.


 

17.2.3.1 Reclamation Permit

NDEP BMRR is the primary State agency regulating mining. NDEP BMRR issues Reclamation Permits prior to construction of exploration, mining, milling, or other beneficiation process activity that proposes to create disturbance over five acres. Reclamation is regulated in Nevada under the authority of the Nevada Revised Statutes (NRS) 519A.010 - NRS 519A.280 and NAC 519A.010 - NAC 519A.415. As previously stated, Lion CG will complete the Reclamation Plan Permit Application, including a reclamation cost estimate, as part of the MPO submittal.

17.2.3.2 Water Pollution Control Permit

NDEP BMRR administers the State of Nevada WPCP application process for the mine, material processing, and operation of the fluid management system in accordance with NAC 445A.350 through NAC 445A.447. A WPCP includes requirements for the management and monitoring of the mine and material processing operations, including the fluid management system and procedures for temporary, seasonal, and tentative permanent closure of mine and material processing operations.

Lion CG intends to prepare a WPCP application for proposed mine facilities and associated buildings and structures that have the potential to degrade the waters of the State. NDEP BMRR will also require a WPCP for pit lake dewatering, based on supporting analyses that predict future water quality within the pit lake to meet beneficial use standards and will not degrade groundwater. Lion CG would prepare one WPCP application for the Project or prepare the WPCP application for pit lake dewatering under a separate process from the overall mine WPCP. A WPCP is valid for 5 years, provided the operator remains in compliance with the regulations.

NDEP BCA Abandoned Mine Lands program may perform its own review of the pit lake dewatering plan to determine if dewatering may cause material changes to established baseline conditions established by ARC and BCA as part of human health and ecological risk assessments completed for the historic mine site remediation.  Approval of, or at a minimum, no objection to dewatering the pit lake may be required by the BCA, as outlined in the 2019 Environmental Covenant Agreement (further discussed in Section 15.5).

Preliminary permitting schedule estimates that Lion CG will require between 2.5 and 3.5 years to secure a WPCP for the Project and pit dewatering. Lion CG intends to proceed with preparation of the WPCP concurrently with the MPO and NEPA analysis.

17.2.3.3 Yerington Pit Lake Discharge Permitting Requirements

During pit dewatering, Lion CG intends to return all excess water to the Mason Valley basin, either via direct surface discharge to the Walker River or for irrigation use via a combination of discharge to land for irrigation and WRID system. During initial discussions with landowners, major irrigators in the area, and the WRID, Lion CG received expression of interest in the surface discharge options for agricultural crop irrigation since the basin is over-appropriated and over-pumped. Prior to discharge, Lion CG intends to treat pit lake water to meet the requirements of the water quality standard applicable for the particular discharge option. Water treatment is assumed to be via reverse osmosis thus providing flexibility in achieving various water quality standards depending upon a discharge streams final disposition.


 

Lion CG plans to secure a National Pollutant Discharge Elimination System (NPDES) permit from NDEP BWPC for the direct discharge of treated pit lake water to the Walker River. As part of its CWA delegation from the EPA, NDEP will provide the draft permit decision to EPA's Region 9 Water Management Division and address any EPA comments prior to public notice. Discharge to the Walker River will meet regulatory requirements associated with applicable water quality standards. A NPDES permit for discharge to the Walker River spans several beneficial use categories (drinking water, irrigation, recreation, etc.) in addition to standards for the protection of aquatic life.

A Section 401 Water Quality Certification from NDEP BWPC may also be required. Projects requiring water quality certification from the State of Nevada must comply with the CWA Section 401 Certification regulations that EPA promulgated in 2023, codified as 40 CFR 121. The State of Nevada defines Waters of the State (WOTS) in Nevada Revised Statute (NRS) 445A.415 to mean all waters situated wholly or partly within or bordering upon this State, including but not limited to:

  • All streams, lakes, ponds, impounding reservoirs, marshes, water courses, waterways, wells, springs, irrigation systems and drainage systems; and
  • All bodies or accumulations of water, surface and underground, natural or artificial.

Given this definition, some aquatic resources may not be a federally jurisdictional WOTUS but still be regulated by Nevada as a WOTS. In those cases, although no Federal permit may be required (Section 404 Permit), a Section 401 Water Quality Certification from NDEP BWPC occurring in, over, or near WOTS may still be required.

Discharge to land for irrigation and WRID will require a State Groundwater Permit for irrigation issued by BWPC. The treatment requirements for this permit will, at a minimum, meet the standards for irrigation water as prescribed in NAC 445A.1236 and the Sodium Adsorption Ratio (SAR) set in NAC 445A.1906. For discharge to the WRID system, Lion CG intends to enter into an agreement with the third-party irrigators and the WRID to demonstrate that the treated irrigated water will be applied in a manner consistent with the NDEP-approved irrigation management plan.

17.2.3.4 Water Rights

NDWR issues approvals to use groundwater for mining, milling, and domestic purposes. Lion CG currently owns the water rights for mining, milling, and domestic use presented in Table 17.3.

Table 17.3: Summary of Water Rights for Yerington and Macarthur
Permit
Number
Status Certificate
Number
Priority
Date
Source Manner of Use Annual
Volume
(AF)
Rate of
Diversion
(CFS/year)
15424 Certificate 4397 12/3/1953 Groundwater Mining, Milling 868.50 1.20
18411 Certificate 5485 11/2/1959 Groundwater Mining, Milling 970.11 1.34
23793 Certificate 7652 4/7/1967 Groundwater Mining, Milling 1,614.24 2.23
25399 Certificate 8428 12/17/1969 Groundwater Mining, Milling 1,628.67 2.25


 

Table 17.3: Summary of Water Rights for Yerington and Macarthur
Permit
Number
Status Certificate
Number
Priority
Date
Source Manner of Use Annual
Volume
(AF)
Rate of
Diversion
(CFS/year)

61449

Permit

n/a

3/12/1952

Groundwater

Mining, Milling

160.00

0.22

58527

Permit

n/a

11/2/1959

Groundwater

Mining, Milling

758.00

1.05

83843

Permit

n/a

11/2/1959

Groundwater

Mining, Milling

15.00

0.02

Total

6,014.52

8.31

Notes: CFS= cubic ft per second, AF = acre-ft

In Nevada, mine pit dewatering is considered a beneficial use of water, requiring water rights. Consumptive use, which is water that is withdrawn or diverted and not returned to the water source, is a key consideration in water rights and pit dewatering permitting.

Yerington Pit dewatering for the first 4 years of the Project are estimated at 12,075 acre-ft per year (Piteau, 2025). Dewatering of the MacArthur Pit in Years 3, 4, and 5 will total approximately 662 acre-ft per year. Lion CG owns 6,014.52 acre-ft of primary ground water rights that are permitted for mining, milling, and dewatering uses. The balance of the consumptive use will be achieved by discharging treated pit lake water back to the Mason Valley Basin as recharge via the Walker River and by irrigation of agricultural land. Irrigation using treated pit dewatering discharge will reduce the need for third-party irrigators and WRID to pump groundwater from the basin, therefore reducing the volume of groundwater currently pumped (consumptive use) by third-party irrigators and the WRID. This would offset the estimated consumptive use deficit for the Project considering the existing water rights held by Lion CG. Lion CG intends to meet the consumptive use requirements associated with the Yerington Pit dewatering by working with local water rights holders and NDWR.

17.2.3.5 Air Quality Permit

NDEP Bureau of Air Pollution Control (BAPC) works closely with NDEP BMRR on mining projects and issues permits to construct and operate facilities that emit gases or particulate matter to the atmosphere. Permits are issued in accordance with NAC 445B.001 through NAC 445B.3689. NDEP BAPC has primacy for air quality activities in Lyon County under the Federal Clean Air Act of 1970, as amended. The type of permit is dependent upon threshold exceedances (e.g., Class I, Class II). As part of the air permitting process, the Project's Potential to Emit (PTE) is reviewed to determine whether it constitutes a major stationary source.  Given the size of the Project, Lion CG assumes that a Class I Air Quality Operating Permit will be required. Lion CG estimates that it will take approximately 12 months to receive the required permit from when the application is submitted.  Permit acquisition will happen in parallel with other permitting processes. 

17.2.4 Local Permitting Requirements

Lion CG plans to apply for a Special Use Permit with Lyon County to receive authorization to conduct mining and processing at the Yerington and MacArthur Properties. The County Building Department will also issue various permits to construct and inhabit structures and facilities at the mine, including building, electrical, plumbing, and mechanical permits, and inspections.


 

17.3 ENVIRONMENTAL STUDIES

Lion CG plans to ensure that the characterization of environmental resources at the Yerington and MacArthur Properties is complete and adequate to support the development of an MPO and satisfy other permitting requirements, as determined in collaboration with Federal and State agencies.

The Yerington Property has been thoroughly characterized through previous permitting efforts, environmental studies and analyses, and as part of the regulatory compliance process under previous mining operations. The issuance of existing permits listed in Table 20-2 required additional environmental studies and site characterization. Nothing in either the historic characterization reports or recent environmental baseline studies indicates the presence of sensitive environmental receptors or other factors that could preclude the development of key Project resources or infrastructure or significantly delay preparation of a MPO for the Project.

Lion CG has previously completed cultural resources surveys (Johnson, 1989) on portions of the MacArthur Property to support the preparation of an Exploration Plan of Operations and 2009 Environmental Review (EA).

Golden eagles and other protected birds have been identified in the vicinity of the proposed MacArthur Pit (WRC 2022; 2023; 2024); however, these serve only to guide and focus future permitting efforts. The presence of eagles does not preclude Project development or operation.

The results of the ongoing regional numerical groundwater model and fate and transport model will support the permitting process and effect analysis under NEPA. The models will predict the extent of the groundwater cone of depression associated with the Yerington Pit dewatering, dewatering rates, and water quality that will be used to develop a water balance and refine water treatment plant design. Lion CG completed installation of piezometers and monitoring wells to further characterize the groundwater in the vicinity of both pits.

Lion CG intends to complete a baseline characterization program to support the permitting of the Project that will include, but not be limited to, the studies presented in Table 17.4. The complete list of baseline studies and analyses required to support permitting the project will be defined in consultation with State and Federal agencies with jurisdictional authority over resources that may be affected by the Project. As part of the State permitting, Lion CG intends to consult with regulatory agencies such as NDEP BMRR and NDWR to refine the baseline data needs that will support the preparation of a Reclamation Plan, WPCP including pit dewatering, pit lake discharge and NPDES/State Groundwater Permit, and Air Permit. To the extent feasible, Lion CG plans to initiate these studies concurrently at Yerington and MacArthur.

Table 17.4: Potential Baseline Surveys and Studies

Studies

Scope of Work

Wetlands, seeps and springs, and Waters of the US

  • Geomorphology survey
  • Hydrology (field measurements and water quality sampling)
  • Seeps and springs surveys
  • Soils and moisture observations
  • Proper functioning conditions
  • Aquatic resources (e.g., spring snails and macroinvertebrates)
  • Wetlands and Waters of the U.S.


 

Table 17.4: Potential Baseline Surveys and Studies

Studies

Scope of Work

Groundwater and surface water characterization

  • Stream delineation (flow rates and water quality sampling)
  • Groundwater baseline characterization (groundwater level and water quality sampling)
  • Aquifer testing
  • Pit lake and groundwater flow model (pit lake refill, water balance, dewatering rates, temporal water quality changes)
  • Groundwater contaminant transport model

Geochemical characterization

  • Ore, waste rock, heap leach/feed characterization testing:
  • Static testing (discrete and composite): Acid Base Accounting (ABA)and paste pH, Net Acid Generation (NAGpH) and Net Acidity Testing
  • Kinetic testing: Humidity Cell Testing (HCT) on waste rock, and Trickle Leach Column Testing on synthesized heap leach/feed composite(s).

Vegetation and wildlife

  • Biological inventory
  • Ecological risk assessment
  • Golden eagle consultations

Cultural resources

  • Class III (intensive) cultural resources inventory

Air quality

  • Baseline data collection
  • Dispersion air modeling
  • Green House Gas (GHGs) emissions inventory

Noise

  • Baseline data collection
  • Noise modeling

Soil and rangeland

  • Desktop review of publicly available information and previous studies/surveys

Geology and mineral resources

  • Desktop review to characterize the physiographic and topographic setting, regional geology, site geology, mineralization, historic mining, and geologic hazards and features of the Project area

Traffic and transportation study

  • Traffic study
  • Desktop review of public access, transportation, and traffic patterns in the Yerington area

Recreation

  • Review of federal, state, and local laws, regulations, and guidelines for recreation and wilderness resources management to describe recreational use

Socioeconomic

  • Study to describe the socioeconomic characteristics and conditions

Visual resources

  • Viewshed analysis
  • Digital photography survey and computer-generated visual simulations

Lion CG may expand these surveys and/or perform additional baseline characterization studies and analyses on other resources as deemed necessary by the agencies to support State and Federal permitting processes, including BLM's effect analysis under NEPA.


 

17.4 ENVIRONMENTAL ISSUES

As previously described in Section 5.1.1, ARC is actively remediating the former Anaconda and Arimetco mining operations (brownfield site) at the Yerington Property.

As discussed in Section 5.1.3, before acquiring the Yerington Property in 2011, Lion CG performed due diligence following the guidelines of a BFPP defense to shield Lion CG from legacy liabilities. In 2009, the State of Nevada, EPA, and BLM issued letters outlining the activities Lion CG needed to complete to maintain BFPP status under State and Federal law. Lion CG continues to perform the required activities to maintain the BFPP status.

Effective July 24, 2012, the EPA and Lion CG entered into an agreement that required Lion CG to perform a specific scope of work at the Yerington brownfield site in exchange for which EPA agreed to a sitewide covenant not to sue or take administrative actions against Lion CG for response costs, existing contamination, and other matters addressed in the agreement. This agreement constitutes an administrative settlement under CERCLA and states that Lion CG is entitled to protection from contribution claims or actions for existing contamination and for other matters as addressed in the agreement. The agreement also states that Lion CG has resolved its liability for all response actions at the brownfield site if Lion CG loses its status as a BFPP, and to release and waive any lien EPA may have at the time the agreement was signed or in the future for costs incurred by EPA. EPA issued a Notice of Completion for the work Lion CG was required to perform under the settlement on January 7, 2015.

Lion CG also entered into a Master Agreement with ARC effective June 1, 2015, that outlines the Parties' responsibilities concerning cooperation, access, property rights, liabilities, federal land acquisition, preservation of Lion CG's property and mineral rights and coordination of the use of the brownfield site by ARC to complete remedial actions and by Lion CG for exploration, mining, and mineral processing activities. This Master Agreement also contains covenants not to sue and indemnification provisions between the Parties.

These agreements reduce Lion CG's risks regarding environmental liabilities from past exploration, mining and mineral processing which took place at the Yerington brownfield site prior to Lion CG's acquisition in 2011. These agreements also enable Lion CG to advance with mine development and operations concurrently with ARC's ongoing remediation activities. The final ARC remediation schedule indicates issuance of the Final ROD by February 2027 with the remedial action completed during 2028-2030 followed by post-closure long-term monitoring and maintenance (NDEP BCA, 2025).

Lion CG will incorporate appropriate remedial design elements into the Project design for proposed facilities located within the remediation boundary, if necessary. Given the stringent engineering requirements for new mining facilities, it is highly likely that standard industry design features, such as placement of synthetic liners and installation of double-walled piping for conveyance of process solutions, will meet or exceed remedial action requirements. Lion CG has and will continue to work proactively with ARC and NDEP to coordinate mine permitting and eventual construction and operation with the remediation requirements undertaken by ARC. On September 11, 2019, SPS entered into an Environmental Covenant Agreement (2019 Covenant) with NDEP which describes use limitations, access agreements, and all other conditions associated with the historic Yerington Property. The 2019 Covenant allows mineral exploration, development, mining, or mineral processing to the extent that such activities receive approval by NDEP BCA or a No Further Action Determination before proceeding. The 2019 Covenant requires prior notification to and approval by NDEP of any activities that alter, disturb, or modify any natural or manmade surface water features on or immediately adjacent to property where access, land, water, or other resource use restrictions are needed to implement investigations or cleanup.


 

Lion CG plans to ensure that all permits to construct and operate the Project facilities located within the historic Yerington Property boundary comply with the 2019 Covenant, including proposed processing facilities located in areas under the jurisdiction of NDEP BCA Abandoned Mine Lands program. Permitting proposed Project facilities located within the remediation boundary prior to completion of the remediation work will require coordination between NDEP BMRR and NDEP BCA to ensure compliance with applicable Nevada mine-related statutes and regulations and the 2019 Covenant. The 2019 Covenant does not prohibit future mineral exploration, mineral development, mining, mineral processing, and all mining-related support activities to the extent that such uses and activities are approved by NDEP

17.5 WASTE, WATER, AND PROCESS FLUID MANAGEMENT

Lion CG intends to manage waste and process-related fluids as required by the construction and operating permits listed above. The Project will not generate tailings since Lion CG will extract copper from the mined material using heap leach and solvent extraction-electrowinning processes.

BLM Instruction Memorandum NV-2013-046 (BLM, 2013) outlines the rock and water resources data information that needs to be collected under 43 CFR 3809.401(b)(2) and 3809.401(c)(1) for plans of operation. NDEP BMRR issued additional guidance on material characterization (NDEP BMRR, 2025) pursuant to the WPCP program and associated NAC 445A regulations. Lion CG plans to initiate a geochemical characterization program to generate data that will allow prediction of the Acid Rock Drainage and Metal Leaching (ARDML) potential of the mined materials and prepare a Rock Characterization and Handling Plan based on the results of the study. The plan will describe how Lion CG will manage waste rock material and if special handling is required (i.e., segregation, encapsulation, etc.) based on the potential for material to neutralize or generate acid or leach metals under weathering conditions. As required by an operating permit, Lion CG will design and construct the Waste Rock Storage Facilities (WRSFs) including installation of liners or placement of other low permeability barriers within storage facility footprints prior to placement of waste rock.

Lion CG plans to design the Heap Leach Facilities (HLFs) to contain leach ore and solutions in accordance with NAC 445A.432 with 100 percent containment (zero discharge design) under both normal operating and emergency operating conditions. As required by federal and state regulations, Lion CG will line the HLFs with synthetic materials to ensure that neither process solution nor processed ore would enter the environment.

Both domestic and industrial solid waste will be generated during construction and operations of the Project. Lion CG plans to manage regulated waste material and comply with permits and/or applicable Federal and state standards for the disposal and treatment of solid waste, including regulations issued pursuant to the Solid Waste Disposal Act as amended by the Resource Conservation and Recovery Act (RCRA; 42 U.S.C. 6901 et seq.). If necessary, based on types of waste generated and quantities, Lion CG intends to obtain a Hazardous Waste Identification Number from EPA for both the mine and plant site. Hazardous waste will be managed and stored according to State, Federal (43 CFR 262) and local regulations. Lion CG will verify that all waste is properly labeled, stored, and disposed of pursuant to 43 CFR 8365.1-1(b). Lion CG will handle municipal type waste in accordance with regulatory requirements and local ordinances.


 

Lion CG plans to manage contact and non-contact water in accordance with applicable permits and regulations. Generally, non-contact water will consist of precipitation and runoff that does not come into contact with potentially contaminated areas such as processing facilities, WRSFs, and HLFs. This includes run-on from areas upgradient from the Project and run-off from certain non-process related facilities (i.e., access roads, office parking lots, etc.). Contact water generally includes water that has interacted with anything in the mining process, such as ore, tailings, waste rock, chemicals, or equipment.

Lion CG would design Project's stormwater management infrastructure to meet the following objectives:

  • Minimize run-on volumes by diverting water surface flows away from disturbed areas and mine facilities such as process solution sources, WRSFs, and HLFs
  • Capture runoff water downstream of mine infrastructure in diversion channels and ponds

Run-on and non-contact stormwater would be captured and diverted back to the environment, as much as practicable. Where possible, natural drainage patterns will be preserved for non-contact water management.

Contact water and process solution will be contained within the Project and either used in process operations or treated and discharged in compliance with applicable permits. All process solutions will be contained within lined facilities or other process components designed to prevent release to the environment.

The Project's proposed water treatment plant will generate brine as a by-product. During initial pit dewatering, Lion CG plans to recirculate the brine back to the pit or use ponds to naturally evaporate the brine, leaving behind a residue of salts and other dissolved solids. Lion CG would line the brine pond as required by Federal and State regulations. Once process makeup water is required for operations, Lion CG intends to incorporate the brine in the processing circuit.

17.6 SITE MONITORING

All Federal, State, and County agencies are expected to require monitoring of the mine, material processing operations, and the fluid management system to ensure compliance with the Project permits. As part of both the WPCP and the MPO, Lion CG would submit a detailed monitoring plan to demonstrate compliance with the permits and other Federal or State environmental regulations, to provide early detection of potential problems, and to assist in directing potential corrective actions (if necessary).

The site-wide monitoring plan would include a discussion of area water quality, monitoring locations, analytical profiles (NDEP Profiles I, II, or III), and sampling/reporting frequency. Typical monitoring programs include surface and groundwater quality and quantity, air quality, revegetation, stability, noise levels, and wildlife mortality.


 

BLM monitoring requirements will be included as part of the ROD. NDEP BMRR monitoring requirements will be included in applicable permits issued for the Project.

17.7 SOCIAL/COMMUNITY

17.7.1 Considerations of Social and Community Impacts

Lion CG is committed to securing and maintaining its social license to operate in the communities that may be affected by the Project. Lion CG recognizes that stakeholder support is important to the success of the Project and plans to deliver transparent and ongoing communication with all stakeholders, with the goal of advancing the Project inclusive of community and stakeholder input.

Lion CG will consider potential issues and concerns shared by the participants during these engagements and will consider input received (to the extent feasible) in the development of the MPO to avoid, minimize, mitigate, or offset/compensate potential negative effects on the communities and enhance Project benefits.

Stakeholder1 groups may include (but are not limited to) the following:

  • Agricultural industry
  • Area Schools & universities
  • City of Yerington
  • Elected officials
  • Local community organizations & businesses
  • Local residents
  • Lyon County
  • Media
  • Mining organizations
  • Native American Tribes
  • Non-Governmental Organizations (NGOs)
  • Regulatory agencies
  • Third-party irrigators
  • Utilities & infrastructure
  • Water authorities

Lion CG has developed a Stakeholder Outreach Strategy for engaging with the various stakeholder groups associated with the Project and establish measures and mechanisms to address stakeholders concerns on a timely basis. The framework includes a due diligence process, stakeholder mapping and analysis, engagement planning and communication protocols, grievance mechanism, record keeping, and follow-ups procedures. Lion CG's Stakeholder Outreach Strategy also allocates Company funding to conduct regular stakeholder engagements and work with parties to develop beneficial options to manage the potential negative effects of the Project.

From Project planning and throughout the life of mine, Lion CG intends to host town hall meetings, present Project information to individual groups of stakeholders, participate in community events, organize open house events, and offer guided tours of the Project area. Since the issuance of the PEA in March 2024, Lion CG has ongoing stakeholder engagements with city, county, and state elected officials, the Yerington Paiute Tribe, and the Walker River Paiute Tribe. Lion CG has also met with various regulatory agencies, irrigators, water authorities, elected officials, members of the public, and the Walker Basin Conservancy.


1 Stakeholders are listed in alphabetical order.

 


 

Lion CG is committed to understanding and communicating the potential positive and negative impacts of the mining operations on the local stakeholders. Should the construction of infrastructure and operation of the Project negatively affect some aspects of the local communities, Lion CG intends to evaluate and develop alternatives, where possible, to minimize these impacts, based on feedback received during ongoing stakeholder engagements. As part of its Stakeholder Outreach Strategy, Lion CG maintains a grievance mechanism available to all parties.

The Project will provide substantial economic benefits and fiscal contributions to the community of Yerington, Lyon County, and the State of Nevada through increased employment and training opportunities, expanded economic activity (e.g., contractors, suppliers, support services), increased household incomes, and additional tax revenues.

Lion CG anticipates that approximately 400 contracted and direct employees will be required for a period of approximately 2 years during the Project construction phase. Operation of the Project over the 12-year mine life will provide direct employment for approximately 550 workers with an average annual salary of $97,000. Lion CG will prioritize hiring the workforce locally, to the extent feasible. The Project will also create indirect employment opportunities associated with ancillary and support services to the Project such as transportation, maintenance, and supplies. Tax revenues generated by the Project are anticipated to be approximately $111,428,000 at the State level and $70,871,000 at the county level. Based on the projected mine life, the Project will have a positive long-term direct, indirect, and induced impact on both the local and regional economy.

Additionally, Lion CG plans to dewater the Yerington Pit lake and discharge treated water back to the watershed that will recharge the Mason Valley groundwater aquifer systems and provide important beneficial uses and enhance ecosystems in the area.

Reprocessing legacy mine residuals (i.e., VLTs) will generate additional overall economic benefits and make previously disturbed land available for new mine infrastructure, reducing the need for new land disturbance at the Yerington Property. Lion CG will design and construct any new HLF's in accordance with stringent modern industry standards and regulatory requirements. As part of the Project, Lion CG will reprocess legacy materials by moving the VLTs to the proposed Yerington HLF for recovery of copper while ensuring adequate closure and reclamation of these sites by reducing long-term potential impacts to the environment. The Project's mine closure plan and associated reclamation bond that will be in place prior to mining will enhance ongoing remediation efforts and ensure reclamation of the Yerington Property to the latest environmental and safety standards following completion of mining.

17.8 CLOSURE PLANNING

17.8.1 Closure and Reclamation Plan

Lion CG plans to reclaim disturbed areas resulting from activities associated with the Project in accordance with BLM Subpart 43 CFR 3809 - Surface Management and the State of Nevada NDEP regulations (NAC 519A and NAC 445A.350 through NAC 445A.447).


 

The State of Nevada requires the development of a Reclamation Plan for any new mining project meeting requirements to return mined land to productive post-mining land use. Lion CG will design and implement a strategy for mine closure and reclamation that will meet the following objectives:

  • Comply with applicable Federal and State environmental rules and regulations
  • Stabilize the disturbed areas to a safe condition
  • Reduce visual impacts
  • Limit and/or eliminate long-term maintenance following reclamation to the extent practical
  • Protect both disturbed and undisturbed areas from unnecessary and undue degradation

Lion CG plans to manage closure and reclamation in a similar manner for the Yerington and MacArthur Properties. Other legacy mining areas from previous operations exist at the brownfield site within the Yerington Property that are being managed by NDEP and are under the responsibility of third parties. Lion CG plans to assume responsibility for the closure activities.  Lion CG will not assume responsibility for legacy impacts of the facilities as outline in Section 3.4.

During construction activities, Lion CG plans to salvage and stockpile suitable and available growth media material for use in future reclamation activities. If possible, Lion CG will perform concurrent reclamation of areas no longer required for mining and processing operations.

Lion CG plans to close and reclaim the mine facilities as summarized below:

  • Mine pits: Once mining and dewatering activities cease; the pits will naturally re-fill with water forming pit lakes that will serve as local groundwater sinks (Piteau, 2025). Lion CG would place safety controls by the major access points to the pits to limit access. Lion CG would install/construct physical barriers (e.g., berms, fencing, or other appropriate barriers) along the pit areas, if needed
  • WRSFs: Regrade and recontour the exterior slopes of the facilities concurrently with operations to ensure an overall slope no steeper than 3H:1V. To the extent possible, ensure the slopes are stable and graded using dozers to blend with the surrounding topography. Lion CG would place stockpiled growth media on the facilities and revegetate with the approved reclamation seed mix
  • HLFs: Proceed with depletion of process fluids from the facilities (i.e., chemical stabilization and draindown), regrade and recontour the exterior slopes of the facilities to ensure an overall slope no steeper than 3H:1V, place a growth media cover on all slopes of the facilities, and revegetate with an approved reclamation seed mix
  • Process facilities: Decontaminate, decommission, demolish, and dispose of the crushing facility and conveyors, the processing plants, the acid plant, water treatment plant, and the fluid management system. Salvageable equipment may be sold

 
  • Pipeline: Remove the pipeline infrastructure between the Yerington and MacArthur Properties, regrade the area to match the surrounding topography, and revegetate with an approved native seed mix
  • Buildings (not identified as part of the post-mining use): Demolish and remove the building material from site, if appropriate; Remove above-ground concrete or bury on site and cover below-ground concrete in place. In those cases where the buildings may not be demolished, burial with inert material may be used as the method of site reclamation
  • Roads (not identified as part of the post-mining use and/or not needed for long-term monitoring access): Regrade the road surfaces to tie into existing ground contours, rip and scarify the area to alleviate compaction and allow for root penetration, and revegetate with an approved native seed mix
  • Post-closure monitoring: Continue monitoring activities at both Properties. Perform post-mining groundwater quality monitoring in accordance with NDEP requirements and the approved WPCP for at least 5 years; revegetation monitoring for a minimum of 3 years following implementation of revegetation activities or until revegetation success has been achieved; and monitor and control noxious weeds for 3 years following closure. Conduct slope stability monitoring, berm and sign maintenance, site inspections, and any other necessary monitoring for the period of reclamation responsibility following mine closure

The MPO submitted to BLM and NDEP BMRR will describe the closure and reclamation activities for the various Project facilities. A reclamation surety adequate for the reclamation of the entire Project, which includes development of the patented and unpatented claims, must be posted before Lion CG will be authorized to proceed with activities. Lion CG expects to provide a bond equivalent (using a phased approach) to the actual cost of performing the agreed upon reclamation measures. BLM and NDEP BMRR will approve the bond prior to approving the MPO and issuing the Reclamation Permit. The reclamation surety will be administered by NDEP. Estimated closure costs for the Yerington Copper Project are approximately $48,614,000.

Lion CG intends to submit a Final Plan for Permanent Closure (FPPC) to NDEP BMRR at least 2 years before the anticipated date of permanent closure. The FPPC will incorporate procedures, methods, and schedules for stabilizing spent process materials based on information and experience gathered throughout the active life of the facility.


 

18.0 CAPITAL AND OPERATING COSTS

18.1 CAPITAL COST

18.1.1 Summary - Capital Cost

This section provides an overview of the capital costs associated with the Yerington Copper Project, which has been designed to achieve a nominal annual copper production rate of approximately 120 million pounds.

The capital cost estimate encompasses all direct and indirect expenditures, complete with appropriate contingencies for the various facilities required to commence production, as outlined in this study. It's important to note that all equipment and materials are assumed to be new, and the estimate does not incorporate allowances for potential scope changes, escalation, or fluctuations in exchange rates. The execution strategy is rooted in an engineering, procurement, and construction management (EPCM) implementation approach, with Lion CG overseeing construction management and the packaging of discipline-based construction contracts.

This capital cost estimate for the Project has been developed to align with the requirements of a Pre-Feasibility Study (PFS), encompassing the costs associated with designing, constructing, and commissioning the necessary facilities.

Table 18.1 outlines the total capital costs for the project, encompassing the mine, process facilities (including the 34 Mtpa crushing plant), heap leach facilities, on-site infrastructure, dewatering of the existing pit lake, and all associated project-related indirect expenditures and contingencies across major areas. The total capital cost estimate for the Project stands at approximately $1,732 million, with prices expressed in terms of Q1 2025 levels.

Table 18.1: Yerington Copper Project Capital Cost Estimate
Area Initial Capital (M$) Sustaining Capital (M$) Total Capital (M$)
Open Pit Mining 22.8 40.7 63.5
Processing 143.4 318.5 461.9
Infrastructure 176.4 228.1 404.5
Acid Plant/CoGen 130.2 114 244.2
Dewatering 42.5 17.5 60
Indirects 74.0 125.7 199.7
Contingency 134.7 163.2 297.9
Total 724.0 1,008 1,732

Estimate Responsibility

This capital cost estimate reflects the joint efforts of SE, NewFields, and AGP. SE was responsible for compiling the submitted data into the overall estimate. Table 18.2 outlines the responsibilities of each company for the input of information into the capital cost estimate.


 

Table 18.2: Capital Cost Estimate Responsibilities
Company Responsibility
Samuel Engineering Process plant, crushing and overland conveying, heap leach stacking system, dewatering, water treatment, and on-site infrastructure, and taxes (included in the financial model).
AGP Mining.
NewFields Heap leach facilities and stormwater management.
Lion CG Owner's costs and closure costs.

Escalation

There is no allowance for escalation beyond May 31, 2025 in the estimate.

Exclusions

The following items are specifically excluded from the capital cost estimate:

  • permits and licenses
  • project sunk costs
  • escalation beyond the base date of the estimate
  • exchange rate variation

Capital Cost Risks

It is important to recognize that the costs of many items may currently be influenced by prevailing global market conditions. This estimate does not account for such uncertainties. The capital cost estimate provided is valid as of May 31, 2025.

In light of the challenges outlined above, a thorough examination of capital cost sensitivity is conducted as an integral part of the financial modeling process.

18.2 MINE CAPITAL COSTS

The capital costs associated with mining equipment were derived from the assumption of acquiring a mining fleet, with Lion CG serving as the mine operator.  Contract mining has not been considered for the PFS. Equipment pricing was predominantly sourced from quotations provided by local vendors, supplemented by data from AGP's database of recent projects for certain smaller equipment. The mining equipment capital costs reflect the use of financing of the major equipment and most support equipment.  A 20% down payment is included in the capital cost for those units financed. The remaining cost is included in the operating costs discussed later in 18.8.2.

The vendor's base cost estimates for each unit were incorporated into the calculation of unit costs, and additional options were factored to arrive at the final capital cost per unit, as detailed in Table 18.3. The capital cost represents the cost of the equipment if not financed. With financing the 20% downpayment amount is shown which is attributed to capital. The remainder is then expensed as an operating cost. The full cost of financing is also shown in Table 18.3.


 

Table 18.3: Major Mine Equipment - Capital Cost ($USD)
Equipment Unit Capacity Capital Cost Down Payment Full Financed Cost
Production Drill inch 5.5 1,342,000 268,000 1,517,000
Production Drill inch 6.75 3,085,000 617,000 3,487,000
Production Loader yd3 15 2,434,000 487,000 2,833,000
Electric Hydraulic Shovel yd3 21 6,579,000 1,316,000 7,659,000
Hydraulic Excavator yd3 8.8 2,349,000 470,000 2,655,000
Haulage Truck t 102 1,939,000 388,000 2,192,000
Crusher Loader m3 15 2,434,000 487,000 2,833,000
Track Dozer HP 636 1,656,000 331,000 1,928,000
Grader HP 218 439,000 89,000 496,000

Certain items, such as spare truck boxes and shovel buckets, were considered as capital expenses and procured concurrently with the mine equipment. For haulage trucks, the estimate assumes one spare box for every four trucks, while for hydraulic shovels and loaders, it anticipates one spare bucket for every two loading units.

The allocation of capital costs is determined based on the units required within a specific timeframe. If new or replacement units are necessary, their quantity, multiplied by the unit cost, defines the capital expenditure for that period. If the equipment is financed, this amount is the downpayment. Please note that no provision is made for potential cost escalation in these calculations. Major equipment purchases are anticipated one year in advance of their actual need. Consequently, if the equipment is required in Year 1, the cost is attributed to Year -1.

The quantity of units is contingent upon the mine schedule and the operating cost estimate, which is based on the required operating hours. These figures are balanced over time, ensuring that fluctuations in hours, whether from one period to another or from year to year, are evenly distributed across the entire equipment fleet to maintain equilibrium.

Replacement intervals for equipment are derived from average values gleaned from AGP's experience. Factors like equipment rebuilds and recertifications, as well as the consideration of used equipment, are not factored into these calculations. However, they should be contemplated during the procurement of the mine fleet.

The alignment of equipment units with operating hours is established for each major piece of mining equipment. Smaller equipment quantities are determined based on operational requirements, such as pickup trucks (dependent on field crews), lighting plants, mechanics trucks, and so forth.

The most substantial component of the major mine equipment is the haulage trucks. In Year 4, the demand for the truck fleet reaches its peak, with fifty units of 102-ton capacity required to sustain mine production. A maximum of 6,000 hours per truck per year is considered, even though there are periods where this maximum utilization is not reached. In such cases, the required hours are evenly distributed among the trucks within the fleet.


 

The calculation method remains consistent for other major mine equipment. Consequently, some smaller production loaders may have a longer lifespan (i.e., the same number of hours between replacements) due to the sharing of operational hours with other units in the fleet.

Support equipment is typically replaced on a periodic basis. For instance, pickup trucks are exchanged every four years, with older units potentially reallocated to other departments on the mine site. For the purposes of capital cost estimation, new units are taken into account for mine operations, engineering, and geology.

Table 18.4 shows the timing of equipment purchases, both initial and sustaining, and provides the projected operating life by unit. Meanwhile, Table 18.5 offers an overview of the total number of units on-site by year.


 

Table 18.4: Equipment Purchases - Initial and Sustaining
Equipment Unit Life
(hrs.)
Yr -1 Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr 12
Drill (5.5 inch) 25,000 1 1     1 1 1         1  
Electric Drill (6.75 inch) 45,000 4 3 2 1                  
Loader (15 yd3) 35,000 2 2 1                    
Electric Hydraulic Shovel 50,000 2 2     2                
Hydraulic Excavator 7 years 1   1                    
Truck (102t) 60,000 13 7 11 8 9   2            
Crusher Loader 35,000   1                      
Tracked Dozer 35,000 4 2               4 2    
Grader 20,000 2 1         1 1          

Table 18.5: Equipment Fleet Size
Equipment Unit Life (hrs.) Yr -1 Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr 12
Drill (5.5 inch) 25,000   2 2 2 2 3 3 3 3 2 2 2 1
Electric Drill (6.75 inch) 45,000   4 7 9 10 10 10 10 10 10 10 10 10
Loader (15 yd3) 35,000   2 4 5 5 5 5 5 5 5 5 5 5
Electric Hydraulic Shovel 50,000   2 4 4 6 6 6 6 6 6 6 6 6
Hydraulic Excavator 7 years   1 2 2 2 2 2 2 2 2 2 2 2
Truck (102t) 60,000   20 31 39 48 48 50 50 50 50 50 50 50
Crusher Loader 35,000   1 1 1 1 1 1 1 1 1 1 1 1
Tracked Dozer 35,000   6 6 6 6 6 6 6 6 6 6 6 6
Grader 20,000   3 3 3 3 3 3 3 3 3 3 3 3


 

The mining capital is tabulated in Table 18.6.

Table 18.6: Mining Capital Cost Estimate ($USD)
Mining Category Preproduction
($M)
Sustaining
($M)
Total
($M)
Mining Equipment
Major Equipment 13.0 33.2 46.2
Support Equipment 9.8 7.5 17.3
Total Mine Capital 22.8 40.7 63.5

Pre-Production Stripping

There is no need for pre-production stripping, as the material necessary for the heap leach facilities is readily accessible. Mining commences in MacArthur which has feed material currently available from previous mining activity. Consequently, no expenses have been allocated to this category.

Mining Equipment

In this analysis mining equipment considers of financing of the equipment. Only the downpayment component of the equipment purchase is shown for those units financed.  This category covers the downpayments, complete capital cost of the equipment if not financed, spare buckets for shovels and loaders, as well as spare boxes for truck rebuilds. Additionally, it incorporates various standard support equipment such as track dozers, graders, water trucks, and pump trucks. Furthermore, it encompasses specialized vehicles like the blaster's truck, along with essential emergency response assets such as ambulances, fire trucks, and associated rescue equipment.

The equipment roster also includes a 35-ton and 50-ton rough terrain crane, and a 100-ton lowboy and tractor specifically designated for transporting drills and dozers between different pit areas.

Mining Infrastructure

Power for the mine equipment is factored into the infrastructure capital and is not individually earmarked for the mine. Additionally, the main maintenance facilities are situated at the Yerington site and integrated into the Infrastructure category, rather than being accounted for within the mining capital expenditure.

18.3 PROCESS PLANT CAPITAL COST

The process capital cost encompasses various components, including those tailored to meet the specific requirements of Nuton technology, alongside the more traditional oxide heap leach facility. The detailed breakdown of costs for these facilities is provided in Table 18.7.

Table 18.7: Process Capital Cost Estimate
Area Initial Cost
($M)
Sustaining Cost
($M)
Total Cost
($M)
Crushing System 0.0 138.6 138.6
Overland Conveyor 0.0 13.0 13.0


 

Table 18.7: Process Capital Cost Estimate
Area Initial Cost
($M)
Sustaining Cost
($M)
Total Cost
($M)
Nuton TechnologyTM 0.0 65.2 65.2
Agglomeration System 0.0 21.2 21.2
Stacking System 0.0 41.4 41.4
Heap Leach 12.8 22.1 34.9
SX Circuit 63.2 27.1 90.2
Electrowinning 41.1 22.7 63.8
Reagents 2.5 0.1 2.6
Acid & CoGEN Plant 125.3 81.2 206.5
Utilities 9.8 0.0 9.8
Water Treatment 38.7 0.0 38.7
Laboratory 3.0 0.0 3.0
Total 296 433 729

The processing capital cost is composed of several distinct components, each contributing to the overall project cost:

Crushing System

The crushing circuit includes two primary sizer with secondary and tertiary cone crushing and conveying for the Nuton process stream, capable of processing 35 Mtpa.

Nuton TechnologyTM

This includes unit operations specific to generating and nurturing bacterial inoculum, pyrite, augmentation of the Yerington sulfide feed, agglomeration, and heap leach operational modifications to facilitate chalcopyrite leaching. The system will also maintain a biomass held in reserve if needed to augment the cultivation of the in-situ heap leach biomass.

Stacking System

Two independent stacking systems are included for the Yerington Nuton circuit designed for retreat stacking to improve mechanical utilization.

Heap Leach Facility (HLF)

Heap Leach Facility (HLF) costs are primarily included in infrastructure costs. Process capital costs for the HLF include mechanical equipment, piping, valves, controls, power systems, and installation costs.

Solvent Extraction (SX) Circuits

A modular design, allowing for expansion as needed when Yerington increases ore placement on the leach pads. Owing to the nature of the design, the downtime for an expansion to the system is minimized.


 

Electrowinning (EW) Circuit

Another modular design that adapts to increased copper cathode production rates, including an automatic cathode stripping unit.

Reagents

Capital for reagent handling and make-up, including mixing and day-tank storage, sized for high-consumption reagents like sulfuric acid.

Process Utilities

Encompassing plant and instrument air, freshwater make-up, and hot water.

Raw Water Treatment

Capital costs for a Reverse Osmosis (R/O) system to provide R/O quality water for boiler make-up, reagent mixing, and inoculum build-up.

Laboratory

Initially designed to support MacArthur sampling, with expansion planned when Yerington comes online in Year 4 to accommodate the larger sampling load and requirements associated with the blast hole cuttings.

Sustaining Maintenance Capital

Sustaining capital of 2% of initial capital is distributed over the project's lifespan for sustaining maintenance needs.

Estimating Methodology

Engineering lists, process flow diagrams, and other process deliverables have been produced with sufficient detail to determine capital costs at a PFS level of study. Engineering quantities for concrete, steelwork, mechanical, and electrical for the process plant and associated infrastructure have been factored based on accepted factors (Lang) and similar projects.

The unit rates and labor rates are based on historical rates and Nevada salary surveys.  Budgetary quotes for mechanical and electrical equipment were obtained from reputable international suppliers.

Pricing Basis

Costs are based on recent quotations for major process equipment, factored appropriately to accommodate specific project configurations.

Contractor Indirects

Based on historical cost information, it includes offsite management, onsite staff, and supervision above trade level, crane drivers, equipment, and labor mobilization and demobilization.

Construction indirect costs for all direct labor are included in the capital cost estimate, which also includes PPE, fuel, travel, and clothing.


 

18.3.1 Infrastructure Capital Cost

The Yerington Copper Project primarily centers its infrastructure capital requirements at the Yerington site, where the majority of essential facilities are located. The proximity of both Yerington heap leach facilities to the process plant streamlines operations. While some minor support facilities will be situated in the MacArthur area, the core infrastructure is strategically positioned at Yerington.

The construction of the heap leach facilities is a pivotal aspect of the project, and it has been carefully phased to distribute the necessary capital expenditure effectively, ensuring alignment with material placement and operational requirements.

Infrastructure costs are categorized into significant segments, each contributing to the overall project, as detailed in Table 18.8.

Table 18.8: Yerington Copper Project Infrastructure Capital Costs
Area Initial Cost
($M)
Sustaining Cost
($M)
Total Cost
($M)
Electrical System - site 5.2 0 5.2
Oxide Heap Leach Pad 48.1 100 148.1
Sulfide Heap Leach Pad 10.7 78 88.7
Rail Spur (12 miles) 35.5 0 35.5
Admin & Mine Maintenance Facilities 19.7 0 19.7
Site roads, equipment, dump preparation, etc 25.8 0 25.8
Total 144.9 178.0 322.9

18.3.2 Electrical System

The electrical system expenses encompass two key components: the connection to the existing 69 kV line and the extension of this line to accommodate the needs of the process plant and mine distribution.

The electrification of the pit area entails the installation of utility poles encircling the pit and extending along its walls. This electrification effort encompasses both MacArthur and Yerington, ensuring accessibility for shovels and drills, optimizing mining operations.

18.3.3 Sulfide Heap Leach Facility

The Sulfide heap leach facility will be strategically situated, encompassing the existing VLT stockpile. The facility construction will take place over a total of three phases, commencing in Year 2, with subsequent expansions in Years 6 and 9. Each phase of pad construction aligns with the mining schedule, ensuring that the targeted VLT areas for re-processing are fully extracted before pad expansions are initiated.

The cost estimate encompasses all aspects of pad development, spanning site preparation, earthwork, geosynthetic materials, collection ponds and solution collection pipework.


 

18.3.4 Oxide Heap Leach Facility

The Oxide Heap Leach Facility will be strategically situated atop the legacy sulfide tailings facility. This choice stems from the large surface area and proximity to the Yerington Pit and processing facilities offered by the existing tailings facility. Geotechnical investigations and evaluations completed for this study indicated this location is satisfactory; however, detailed geotechnical investigations and assessments will be conducted to confirm that the tailings can be adequately graded or otherwise prepared to serve as a suitable surface for the Heap Leach Facility.

The development of the initial pad will commence in Year 2, with a single expansion planned for Year 5. The comprehensive cost estimate encompasses all aspects of pad construction, covering site preparation, earthwork, geosynthetic materials, collection ponds, and solution collection pipework.

The MacArthur HLF is sited adjacent to the open pits, on the largest expanse of relatively flat ground within the MacArthur Property. The development of the initial pad will commence in Year 0, with an expansion planned for Year 2. The comprehensive cost estimate encompasses all aspects of pad construction, covering site preparation, earthwork, geosynthetic materials, collection ponds, and solution collection pipework.

18.3.5 Rail Spur

The rail spur is strategically located to connect the main rail line near Wabuska with the mine site. The spur traverses in a southerly direction from the main line around the ridge of hills, past MacArthur, and leads directly to the Yerington site.

This rail spur serves multiple purposes. It facilitates the delivery of essential supplies such as sulfur prill and other bulk materials while also establishing a reliable means for transporting the finished copper.

Precise details regarding the exact location of the rail spur will be subject to further engineering in subsequent stages of the study.

18.3.6 Mine Maintenance Shop

The construction of the mine maintenance shop will be phased to align with the growth of the equipment fleet. Initially, the shop will be sized to accommodate the requirements of the new equipment and the lower stripping demands associated with mining MacArthur and VLT. As Yerington operations commence, the facility will be expanded to effectively manage the growing number of units.

The cost estimate for the shop encompasses outfitting various areas within, including the tire bay, welding bay, and other essential sections.

18.3.7 Other Infrastructure

This category encompasses various elements of additional infrastructure, including site roads, fencing, waste dump preparation, mobile site equipment, truck weigh scales, and explosives storage. 


 

18.4 DEWATERING CAPITAL COST

Before commencing mining activities in the Yerington pit, it is essential to remove water from the existing pit lake. The destination of the water is being determined as part of the overall permitting effort, in coordination with local entities.

The dewatering cost covers the following components:

  • Pit Lake Dewatering: This includes the capital cost for pumps, pipes, discharge infrastructure, and related equipment.
  • Shallow Dewatering Wells: These wells are installed during pit lake dewatering to prevent potential pit slope instability during rapid pit lake drawdown
  • Deep Dewatering Wells: These wells are essential for long-term dewatering during pit operations
  • In-pit Dewatering Sumps/Pumps: These systems are responsible for capturing and removing direct precipitation within the Yerington Pit and MacArthur Pit during active operations
  • Water Treatment Plant: An allowance for a treatment facility is included should it be required after additional evaluations
  • Pond: A geomembrane-lined pond is provided for potential mixing, settling, and/or upset conditions, as needed
  • Pumping Cost: Capitalization of pit dewatering operating costs

The estimated costs associated with the dewatering of the Yerington pit and the establishment of infrastructure needed to maintain both the Yerington Pit and MacArthur Pit in dry conditions during active mining total $49.7 million. Of this, $45 million is allocated for initial capital needs, while the remaining $4.7 million represents sustaining capital for the establishment of longer-term dewatering wells and sumps for pit operations.

18.5 ENVIRONMENTAL CAPITAL COST

Closure costs are included for each area, encompassing the final reclamation of site facilities, heap leach facilities, and open pits. Additionally, it accounts for monitoring activities after mining operations have ceased.

The environmental costs of the mining area are provided in Table 18.9.

Table 18.9: Yerington Copper Project Environmental Cost Estimate
Area Initial Cost
($M)
Sustaining Cost
($M)
Total Cost
($M)
Yerington
Closure Costs 0 32.9 32.9
MacArthur
Closure Costs 0 15.7 15.7
Bond(1) 12.7 (-6.6) (6.1)
Total 12.7 56.7 69.4

(1) Bond Includes 6.1M in sustaining interest and (12.7M) repayment of the bond.


 

18.6 INDIRECTS

The Indirect costs have been applied as a percentage for each estimation area. The Owner's cost, which has been included in the Indirect category, is a calculated number based on the construction needs anticipated for the project construction.

The various items considered in determining the Indirects percentages include:

18.6.1 Engineering, Procurement and Construction Management (EPCM)

  • EPCM costs are factored based on historical ratios
  • Construction management (CM) costs are included in the owner's cost since Lion CG will oversee construction management
  • EPCM services for the project encompass detailed engineering, procurement, equipment and material purchases, contracting, project management, and controls

18.6.2 Construction Indirects

  • Construction indirect costs are factored and cover items not within the contractor or client scope, such as temporary facilities, warehousing, utilities, and infrastructure available on-site as directed by Lion CG
  • Costs for fuel, meals, accommodation, and vehicles have been estimated
  • Room and board costs during construction are estimated based on camp loading, construction duration, and recent pricing for Canadian camp maintenance

18.6.3 Spares

  • Commissioning spares for major equipment have been quoted by vendors
  • Costs for commissioning spares for other equipment have been factored
  • Capital and operating spares are included in the sustaining cost estimate

18.6.4 Vendor Representatives

  • Certain equipment will require vendor representation during construction and/or commissioning
  • The estimate includes a provision to cover vendor representatives' services based on major mechanical equipment packages

18.6.5 Freight

  • Freight costs are calculated as a percentage of the supply cost
  • Factors for freight costs were obtained from vendor quotations, and if unavailable, an approximation of 8% to 20% of equipment supply cost was used, based on historical rates and sourcing of materials and equipment

 

18.6.6 Owner's Costs/Royalty Buydown

  • Owner's costs, including the construction management team's salaries and other Lion CG-directed expenses, have been estimated and included in the estimate
  • An expense of $10.4 million is allocated for owner's costs in the initial capital expenses

To buy down the MacArthur royalty to 1%, $1 million is allocated in Year 3.

18.6.7 Indirect Percentages and Cost

Indirect percentages and costs for various areas, including estimate costs, are detailed in Table 18.10. Open Pit Mining was costed with a 5% indirect cost that is captured in operating costs as the project was costed based on equipment leasing terms.

Table 18.10: Indirect Percentages and Cost Estimate
Area Initial Cost ($M) Sustaining Cost ($M) Total Cost ($M)
Open Pit Mining 0 0 0
Heap Leach Facility 4.8 18.4 23.2
Infrastructure 18.8 0 18.8
Acid Plant & CoGEN 14.8 0.9 15.7
Process Facilities 19.5 52.1 71.5
Contracted Indirects 13 41.9 54.9
Other Indirects 22.1 26.9 49.0
Owners Cost/Royalty Buydown 9.9 0 9.9
Total 102.9 140.2 243.1

18.7 CONTINGENCY

The estimate incorporates a contingency fund to address unforeseen variances between the specific items considered in the estimate and the eventual total installed Project cost. The contingency does not cover scope changes or design expansions.

Contingency has been allocated to the estimate on an area basis, with varying percentages reflecting the level of confidence associated with each estimate area. It's worth noting that contingency is independent of the specified estimate accuracy and should be evaluated in the context of the Project's total cost, inclusive of contingency. In total, the contingency for the Capital Cost Estimate amounts to approximately 24.3% of the total Project cost, equating to $275.6 million over the mine's operational lifespan.  Open pit mining contingency is 5% but all contingency is captured in operating costs as project was costed based on equipment leasing terms.

Table 18.11 presents the contingency percentages and costs applied to each respective area for reference.


 

Table 18.11: Project Area Contingency Percentages
Area Contingency
(%)
Initial Cost
($M)
Sustaining Cost
($M)
Total Cost
($M)
Open Pit Mining 0 0 0 0
Heap Leach Facility 15 6.8 26.7 33.5
Infrastructure 24.4 15.3 0 15.3
Acid Plant & CoGEN 24.7 25.6 17.7 43.3
Process Facilities 26.0 61.1 79.8 140.9
Contracted Indirects 23.6 17.8 10.2 28
Other Indirects 27.5 6.1 6.5 12.6
Owner's Cost 20 2 0 2
Total 134.7 140.9 275.6

18.8 OPERATING COST ESTIMATION

18.8.1 Operating Cost Summary

The estimated Project operating costs are shown in Table 18.12.

Table 18.12: Yerington Copper Project Operating Costs - Life of Mine 
Area Life of Mine
($/t moved)
Life of Mine
($/t process feed)
Life of Mine
($/lb copper payable)
Open Pit Mining 2.55 3.35 1.18
Processing 1.42 1.87 0.66
G&A 0.19 0.24 0.09
Total Operating Cost 4.16 5.47 1.92

General data sources and assumptions used as the basis for estimating the process operating costs include:

  • process design criteria in Section 14.0
  • nominal production rate of 34 Mtpa for the Nuton circuit
  • labor requirements as developed by AGP and SE
  • unit cost of electrical energy of $0.065/kWhr
  • unit cost of diesel fuel of $3.03/gal
  • taxes are excluded from the G&A but are applied to the financial model

18.8.2 Mine Operating Costs

Mine operating costs are estimated from base principles. Key inputs to the mine costs are fuel, electricity, and labor. The fuel cost is estimated using local vendor quotations for fuel delivered to the site. A value of $3.03/gallon is used in this estimate. For electricity, a price of $0.065/kWhr has been used.


 

18.8.2.1 Open Pit Mine Operating Cost Estimate

Labor cost estimates were based on queries to other operations and recent salary surveys for Nevada.  Shift schedules are 12-hour shifts with a 4 days on/4 days off schedule.  Management will be on a 5x2 shift pattern. A burden rate of 30% was applied to all rates.  Mine positions and salaries are shown in Table 18.13.

Table 18.13: Open Pit Mine Staffing Requirements and Annual Salaries (Year 5)
Staff Position Employees Full Load Annual
Salary ($/a)
Mine Maintenance
Maintenance Shift Foremen 8 150,000
Maintenance Planner/Contract Admin 3 121,000
Clerk 1 74,000
Subtotal 12  
Mine Operations
Mine Operations General Foreman 1 162,000
Mine Shift Foreman - Senior 4 150,000
Mine Shift Foreman - Junior 4 130,000
Road Crew/Services Foreman 1 150,000
Clerk 1 74,000
Subtotal 11  
Mine Engineering
Chief Engineer 1 158,000
Senior Engineer 1 136,000
Open Pit Planning Engineer 2 113,000
Blasting Engineer 1 113,000
Blasting/Geotech Technician 1 83,000
Dispatch Technician 4 91,000
Surveyor/Mining Technician 1 98,000
Surveyor/Mine Technician Helper 2 83,000
Subtotal 13  
Geology
Chief Geologist 1 158,000
Senior Geologist 1 136,000
Grade Control Geologist/Modeler 2 113,000
Sampling/Geology Technician 4 98,000
Clerk 1 74,000
Subtotal 9  
Total Mine Staff 45  

Mine staff labor is lower during the initial two years, coinciding with MacArthur being the primary active pit with minor activity at Yerington in Year 2. As Year 3 marks the commencement of full-scale mining operations at Yerington, additional support in mine operations in the form of Junior Shift foremen, additional mine planning engineer and grade control geologists.  Additional maintenance supervision is added in Year 3 with one more maintenance planner.


 

From Year 7 through Year 12, the staff level remains steady at around thirty-one individuals before the mine is complete.

The hourly employee labor force in both the mine operations and maintenance departments fluctuates in response to production requirements. Table 18.14 provides a snapshot of the labor composition for Year 5.

Table 18.14: Hourly Labor Requirements and Annual Salary (Year 5)
Hourly Position Employees Full Load Annual Salary
($/a)
Mine General
General Equipment Operator 8 118,000
Road/Pump Crew 4 116,000
General Mine Laborer 8 116,000
Light Duty Mechanic 3 123,000
Tire Repair 4 135,000
Lube Truck Driver 8 123,000
Subtotal 35  
Mine Operations
Driller 48 130,000
Blaster 2 130,000
Blaster's Helper 4 116,000
Loader Operator 20 130,000
Hydraulic Shovel Operator 24 130,000
Haul Truck Driver 180 118,000
Dozer Operator 16 124,000
Grader Operator 9 124,000
Transfer Loader 3 130,000
Water Truck 14 116,000
Subtotal 320  
Mine Maintenance
Heavy Duty Mechanic 78 135,000
Welder 44 135,000
Electrician 4 135,000
Apprentice 11 123,000
Subtotal 137  
Total Hourly 492  

Labor costs are computed based on an owner-operated model, with Lion CG assuming responsibility for equipment maintenance through its in-house staff.


 

Supervising various mine departments, including operations, engineering, and geology, is the Mine General Foreman. Reporting to the Mine General Foreman are the Mine Maintenance Shift Foremen, Chief Engineer, and Chief Geologist.  Mine General Foreman reports to the Mine General Manager.

Directly under the purview of the Mine General Foreman are the shift foremen. The mine maintains four mine operations crews on rotation. Upon the initiation of full-scale operations at Yerington in Year 3, an additional shift foreman is added. A Road Crew/Services Foreman, responsible for roads, drainage, and pumping around the mine, also serves as a backup Mine Shift Foreman. The Mine Operations department features its own clerk.

In the engineering department, the Chief Engineer supervises one Senior Engineer and two open-pit engineers. These open-pit engineers handle blasting, short-range, and long-term planning tasks. The short-range planning group in engineering includes two surveyor/mine technicians and two surveyors/mine helpers who assist in field activities like staking, surveying, and sample collection, collaborating closely with the geology group and participating in blast pattern design.

Within the Geology department, the Chief Geologist leads one Senior Geologist. Additionally, two grade control geologists/modellers contribute-one in short-range and grade control drilling and the other in long-range/reserves. Four grade control geologists (one per mine operations crew) and one clerk/administrative assistant complete the team.

The Mine Maintenance Shift Foremen report directly to the Mine General Foreman. Three maintenance planners/contract administrators and a clerk support maintenance operations.

Hourly labor positions include light-duty mechanics, tire repair technicians, and lube truck drivers, each with one position per crew. Upon Yerington's commencement, an extra light-duty mechanic, two tire technicians, and four lube truck drivers join the team. General mine labor comprises two laborers per crew and trainees (one per crew until Year 4).

The drilling labor force is structured with one operator per drill, per crew, totaling an average of twelve drillers per crew. Shovel and loader operators peak at forty-eight in Year 6 before gradually decreasing. Haulage truck drivers reach two hundred in Year 6 and then taper off toward the end of the mine's life.

Maintenance staffing levels are determined using maintenance factors based on the number of drill operators. The calculation equates to 0.25 mechanics required for each drill operator, 0.25 welders per drill operator, and 0.05 electricians per drill operator. This approach for estimating maintenance requirements is consistently applied across each category of mine operating cost, as summarized in Table 18.15.

Table 18.15: Maintenance Labor Factors (Maintenance per Operator)
Maintenance Job Class Drilling Loading Hauling Mine Operations
Support
Heavy Duty Mechanic 0.25 0.25 0.25 0.25
Welder 0.250 0.25 0.25 0.25
Electrician 0.05 0.01 - -
Apprentice - - - 0.25


 

The estimation of loader, truck, and support equipment operators is based on projected equipment operating hours, with a maximum of four employees per unit to align with the mine crews.

The vendors provided repair and maintenance (R&M) costs for each piece of equipment as part of the cost quotations. Fuel consumption rates were also estimated for the anticipated conditions at Yerington and are factored into the detailed costs for the mine equipment. These R&M costs are represented in a $/h format.

The costs associated with different tire sizes, to be utilized during the project, were provided by various suppliers. Tire life estimates were derived from AGP's experience and discussions with mine operators. The operating cost of haulage truck tires is expressed in $/h. Haulage truck tires are expected to have a life of 5,500 hours per tire with proper rotation from front to back. Given that each tire for the haulage trucks costs $13,400, the tire cost per hour amounts to $14.62/h for trucks, factoring in the use of six tires in the calculation.

Ground Engaging Tool (GET) costs were estimated based on data from previous projects and conversations with personnel at other operations. This is an area of cost expected to undergo refinement during mine operations.

The estimation of drill consumables was conducted by considering a complete drill string, utilizing the parts list and component lifespans provided by the vendor. Drill productivity was projected to be 81.4 ft/h for the 5.5-inch drill and 79.4 ft/h for the 6.75-inch drill. Equipment costs used in the estimate can be found in Table 18.16.

Table 18.16: Major Equipment Operating Costs - no labor ($/h)
Equipment Fuel/
Power
Lube/Oil Tires Under-
Carriage
Repair &
Maintenance
GET/
Consumables
Total
Support Drill (5.5 inch) 48.03 4.80 - 3.00 70.00 111.49 237.32
Electric Drill (6.75 inch) 30.36 - - 6.00 70.00 184.47 290.83
Production Loader (15 yd3) 68.85 6.88 29.76 - 68.69 10.00 184.18
Electric Hydraulic Shovel (21 yd3) 46.22 - - 50.00 120.75 35.00 251.97
Haulage Truck - 102 t 48.03 4.80 14.62 - 66.09 3.00 136.54
Crusher Loader 68.85 6.88 29.76 - 68.69 10.00 184.18
Track Dozer 47.23 4.72 - 15.00 77.37 7.00 151.32
Grader 12.01 1.20 2.53 - 29.58 2.00 47.32

Open pit drilling operations will employ conventional down-the-hole (DTH) blasthole rigs equipped with 5.5 and 6.75-inch drill bits. The blast patterns for both heap feed and waste materials remain consistent, considering the rock's competence. A finer material size is chosen to enhance productivity and minimize maintenance costs within the crushing and sizing circuits. Details regarding the drill pattern parameters can be found in Table 18.17.


 

Table 18.17: Drill Pattern Specification
Specification Unit Heap Feed/Waste
(5.5 inch)
Heap Feed/Waste
(6.75 inch)
Bench Height ft 25 25
Sub-Drill ft 3.9 4.3
Blasthole Diameter inch 5.5 6.75
Pattern Spacing - Staggered ft 15.1 17.7
Pattern Burden - Staggered ft 13.1 15.4
Hole Depth ft 28.9 29.3

The inclusion of a sub-drill is essential to accommodate hole caving in weaker zones, preventing the need for hole re-drilling or short holes that could negatively impact bench floor conditions, ultimately leading to increased tire and overall maintenance costs.

For reference, the parameters utilized to estimate drill productivity are provided in Table 18.18. The electric drill is configured for single pass drilling of the blasthole, while the smaller drill requires steel breaking to complete the hole.

Table 18.18: Drill Productivity Criteria
Drill Activity Unit Heap Feed/Waste
(5.5 inch)
Heap Feed/Waste
(6.75 inch)
Pure Penetration Rate ft/min 1.8 1.6
Hole Depth ft 28.9 29.3
Drill Time min 16.73 21.09
Move, Spot, and Collar Blasthole min 3.00 3.00
Level Drill min 0.50 0.50
Add Steel min 0.50 0.00
Pull Drill Rods min 1.50 1.00
Total Setup/Breakdown Time min 5.50 4.50
Total Drill Time per Hole min 22.2 23.1
Drill Productivity ft/h 81.5 79.3

An emulsion product will be employed for blasting to ensure water protection when required, although the predominant explosive used will be ANFO, constituting 80% of the total explosive usage. The specific powder factors utilized for the explosive calculation are outlined in Table 18.19.

Table 18.19: Design Powder Factors
  Unit Heap Feed/Waste (5.5 inch) Heap Feed/Waste (6.75 inch)
Powder Factor lb/yd3 1.03 1.05
Powder Factor lb/t 0.48 0.49

The blasting cost estimation is derived from quotations obtained from a local vendor. The pricing for emulsion explosives stands at $820 per ton, while ANFO explosives are priced at $650 per ton. The mine assumes responsibility for overseeing the loading process, encompassing the placement of boosters/Nonels, stemming, and the firing of the shot.


 

Additionally, a monthly cost is incurred for the delivery of explosives to the hole, which includes expenses for the vendor's pickup trucks, pumps, and labor, covering the cost of the explosives plant. It's worth noting that the explosives vendor also leases the explosives and accessories magazines to Lion CG as part of this cost.

Regarding the loading of mill feed and waste, this is primarily carried out by front-end loaders and hydraulic shovels, with the shovels being the primary excavation equipment for mill feed and waste. Front-end loaders serve as a backup. Table 18.20 provides the average percentage breakdown of material types handled by these loading units, emphasizing the prominent role of the shovels over the loaders.

Table 18.20: Loading Parameters - Year 5
  Unit Front-End Loader Hydraulic Shovel
Bucket Capacity yd3 15 21
Waste Tonnage Loaded % 35 65
Heap Feed Tonnage Mined % 33 67
Bucket Fill Factor % 88 79
Cycle Time sec 40 35
Trucks Present at the Loading Unit % 80 80
Loading Time min 3.4 2.5

The shovel's standard bucket is not ideally matched to the 100-ton trucks, and future studies will explore optimizing bucket sizes to better accommodate different material densities. For the current estimate, fill factors were utilized to ensure that trucks reached their 102-ton capacity.

The term "trucks present at the loading unit" signifies the percentage of time a truck is available for loading. To enhance truck productivity and reduce operating costs, it is more efficient to slightly undersize the truck fleet compared to the loader or shovel capacity. This approach helps minimize the standby time that shovels often experience due to a shortage of available trucks. The choice of 80% value is informed by the typical standby time observed in shovels due to truck shortages.

Haulage profiles were developed for each pit phase, considering destinations such as the primary crusher or waste rock management facility. To estimate haulage costs, cycle times were calculated based on the tonnage, destination, and phase. It's important to note that trucks' maximum speed is limited to 30 mph, primarily to extend tire life and ensure safety. Table 18.21 provides details on the calculated speeds for various segments.

Table 18.21: Haulage Cycle Speeds
  Flat (0%)
on surface
Flat (0%)
Inpit, Crusher,
Dump
Slope Up
(8%)
Slope Up
(10%)
Slope Down
(8%)
Slope Down
(10%)
Acceleration or
Deceleration
Loaded (mph) 30 25 10 7.5 19 19 12.5
Empty (mph) 30 25 22 15.5 22 22 12.5


 

Support equipment hours and costs are determined using the percentages shown in Table 18.22.

Table 18.22: Support Equipment Operating Factors
Mine Equipment Factor Factor Units
Track Dozer 25% Of haulage hours to a maximum of 6 dozers
Grader 10% Of haulage hours to a maximum of 3 graders
Crusher Loader 35% Of loading hours to maximum of 1 loader
Support Backhoe 20% Of loading hours to maximum of 1 backhoe
Water Truck 20% Of haulage hours to a maximum of 4 trucks
Lube/Fuel Truck 6 h/d
Mechanic's Truck 12 h/d
Welding Truck 8 h/d
Blasting Loader 8 h/d
Blaster's Truck 8 h/d
Integrated Tool Carrier 4 h/d
Compactor 1 h/d
Lighting Plants 12 h/d
Pickup Trucks 10 h/d
Dump Truck - 20 ton 2 h/d

Based on these percentages, the operational requirements call for six track dozers, three graders, and one support backhoe. This allocation is partly influenced by the dispersed layout of the various pit areas, which can at times restrict equipment movement. The roles of these machines encompass tasks such as clearing loader faces, maintaining roads, managing dumps, and addressing blast patterns.

The graders will be responsible for the upkeep of routes used for heap feed and waste hauling. Additionally, water trucks will play a crucial role in monitoring haul roads and controlling fugitive dust, a measure taken for both safety and environmental considerations. The support backhoe will assist in dilution control during heap feed/waste separation. A smaller backhoe will handle maintenance and operational support for water management facilities, in conjunction with two small dump trucks.

These equipment hours are factored into the individual operating costs for each piece of equipment. It's worth noting that some of these units are categorized as support equipment, and as such, no direct labor force is allocated to them, given their specialized functions.

18.8.2.2 Grade Control

Grade control will be conducted using blasthole cuttings collected from the existing drill fleet. Given the deposit's characteristics, this approach should prove sufficient for segregating heap feed material from waste. There is no need for a separate fleet of reverse circulation (RC) drill rigs.

The anticipated cost for grade control is expected to average $1.3 million per year, with a peak of $1.79 million in Year 7. This translates to approximately $0.02 per ton moved over the mine's operational lifespan.


 

18.8.2.3 Dewatering

Efficient and cost-effective dewatering will be a pivotal aspect of the Yerington Copper Project's development, potentially allowing for a reduction in the strip ratio by enabling steeper inter-ramp angles, which inherently enhance safety.

The infrastructure capital already encompasses deep dewatering wells, strategically positioned at the eastern end of the Yerington pit. These wells will aid in managing seepage from the Walker River and groundwater sources, with pumped water being centralized for potential treatment and reuse in the processing circuit.

The dewatering system encompasses pumps, sumps, and pipelines responsible for transporting water from the pit to designated discharge points. Labor costs for this aspect are already incorporated into the General and Mine Engineering category of the mine operating cost, complete with a dedicated pump crew and pump crew foreman.

The cost estimate also includes an approximately $0.01 per ton moved allowance for operating the dewatering system after the pit lake has been fully drained.

18.8.2.4 Financing

Financing of the mine fleet is considered a viable option to reduce initial capital.  Various vendors offer this as an option to help select their equipment.

Indicative terms for leasing provided by the vendors are:

Down payment = 20% of equipment cost

Term Length = 3-5 years (depending on equipment)

Interest Rate = SOFR plus a percentage

Residual = $0

The proposed interest rate is used to calculate the required annual finance payment on the equipment.  The support equipment fleet is calculated in the same manner as the major mining equipment.

All major mine equipment, and most of the support equipment where it was considered reasonable, was financed. If the equipment has a life greater than the finance term length, then the following years onward of the term do not have a finance payment applied. In the case of the mine trucks, with an approximate 10-year working life, the financing would be complete, and the trucks would simply incur operating costs after that time. For this reason, the operating cost would vary annually depending on the equipment replacement schedule and timing of the financing.

Utilizing the leasing option adds $0.33/t moved to the mine operating cost over the life of the mine. On a cost per tonne of feed basis, it was $0.43/t of heap feed.

18.8.2.5 Total Open Pit Mine Costs

The total life of mine operating costs per ton of material moved and per ton of heap feed processed are shown in Table 18.23 and Table 18.24.


 

Table 18.23: Open Pit Mine Operating Cost ($/t Total Material)
Open Pit Operating Category Unit Year 1 Year 5 LOM
Average Cost
General Mine and Engineering $/t 0.29 0.14 0.17
Drilling $/t 0.34 0.30 0.30
Blasting $/t 0.26 0.23 0.23
Loading $/t 0.27 0.27 0.28
Hauling $/t 0.70 0.77 0.85
Support $/t 0.62 0.21 0.30
Grade Control $/t 0.02 0.02 0.02
Finance Cost $/t 0.93 0.28 0.33
Dewatering $/t 0.13 0.04 0.07
Total $/t 3.57 2.26 2.55

Table 18.24: Open Pit Mine Operating Cost ($/t Heap Feed)
Open Pit Operating Category Unit Year 1 Year 5 LOM
Average Cost
General Mine and Engineering $/t heap feed 0.33 0.22 0.23
Drilling $/t heap feed 0.39 0.47 0.40
Blasting $/t heap feed 0.30 0.36 0.31
Loading $/t heap feed 0.31 0.42 0.36
Hauling $/t heap feed 0.80 1.20 1.11
Support $/t heap feed 0.70 0.33 0.40
Grade Control $/t heap feed 0.03 0.03 0.03
Finance Cost $/t heap feed 1.06 0.44 0.43
Dewatering $/t heap feed 0.15 0.06 0.09
Total $/t heap feed 4.07 3.53 3.35

18.9 PROCESS OPERATING COSTS

The operating costs for the process plant have been established based on a designed processing rate of 95,900 tons per day for the Nuton Technology process and 141,500 tons per day for MacArthur Oxide heap leaching. This equates to 35 million tons per annum at Yerington and 51.7 million tons per annum at MacArthur for the feed material. All cost estimates are provided with an accuracy range of +25% to -25%.

Lion CG will pay a license fee to Nuton LLC, a Rio Tinto venture, to use the Nuton Technology, which will be negotiated at a later date. 

These process operating costs adhere to industry norms for a copper heap leach and SX-EW processing plant. Quantities and cost information have been compiled from diverse sources, encompassing:

  • metallurgical test work

 
  • consumable prices from suppliers
  • Woods internal data
  • first principal calculations

The estimation of process operating costs encompasses the following major categories:

  • operating consumables (reagents, steel, fuel, tools, and safety supplies)
  • plant maintenance costs
  • power
  • labor (operations and maintenance)
  • laboratory costs
Table 18.25: Process Operating Cost (MacArthur)
Operating Cost Summary    
Operations Labor $/t feed 0.45
Reagents/Supplies $/t feed 0.94
Maintenance $/t feed 0.10
Power $/t feed 0.08
TOTAL - Operating $/t feed 1.57

Table 18.26: Consumables and Reagents (MacArthur)
Supplies Units Usage Unit Cost
($/t)
Crusher Liners n/a n/a n/a
Sulfuric Acid lb/t 28  
Sulfur lb/t 9.3 0.47
Diluent gal/t Cu 7.49 0.04
Extractant gal/t Cu 1.87 0.08
Drip Line $/t 0.02 0.05
Additive Supplies (Nuton)   n/a n/a
Electrowinning Supplies     0.07
Total Reagents     0.94

Table 18.27: Process Operating Cost (Oxide)
Operating Cost Summary    
Operations Labor $/t feed 0.40
Reagents/Supplies $/t feed 0.71
Maintenance $/t feed 0.07
Power $/t feed 0.13
TOTAL - Operating $/t feed 1.31


 

Table 18.28: Consumables and Reagents (Oxide)
Supplies Units Usage Unit Cost
($/t)
Crusher Liners n/a n/a n/a
Sulfuric Acid lb/t 16.3  
Sulfur lb/t 5.4 0.28
Diluent gal/t Cu 6.23 0.04
Extractant gal/t Cu 1.56 0.07
Drip Line $/t 0.02 0.05
Additive Supplies (Nuton)     n/a
Electrowinning Supplies     0.07
Total Reagents     0.71

Table 18.29: Process Operating Cost (Nuton)
Operating Cost Summary    
Operations Labor $/t feed 0.73
Reagents/Supplies $/t feed 1.22
Maintenance $/t feed 0.47
Power $/t feed 0.70
TOTAL - Operating $/t feed 3.12

Table 18.30: Consumables and Reagents (Nuton)
Supplies Units Usage Unit Cost
($/t)
Crusher Liners lb/t 0.03 0.10
Sulfuric Acid lb/t 26.1  
Sulfur lb/t 8.7  0.44
Diluent gal/t Cu 6.23 0.07
Extractant gal/t Cu 1.56 0.13
Drip Line $/t 0.02 0.05
Additive Supplies (Nuton)     0.36
Electrowinning Supplies     0.07
Total Reagents     1.22

18.9.1 Operating Consumables

The consumables category encompasses a variety of items, including reagents, fuel, and operational consumables like wear iron, conveyor belting, screen panels, lubricants, solvent extraction reagents, and cathode production consumables. It's important to note that this category excludes general maintenance consumables such as greases, lubricants, equipment spare parts, and pump wear parts, which are accounted for in maintenance costs. The estimation of consumption rates and pricing for consumables and reagents was carried out as follows:

  • Consumption rates for comminution consumables, such as crusher wear iron, were projected based on factors like the material bond abrasion index and crusher power consumption

 
  • Reagent consumption figures were derived from metallurgical test work and established operational practices
  • Fuel consumption for mobile equipment was calculated using standard fuel consumption rates and equipment utilization data
  • Reagent prices were determined through supplier quotations or sourced from the Woods database, which includes recent project data and market studies

18.9.2 Maintenance

Maintenance costs, excluding labor and consumable expenses, were estimated as a percentage of capital equipment costs. Specifically, a 5% factor was applied.

18.9.3 Power

The power consumption of the process plant was calculated based on the installed motor size of individual equipment units, excluding standby equipment. This value was adjusted using efficiency, load, and utilization factors to obtain an annual average power draw. The result was then multiplied by the total annual operating hours and the electricity price to determine the overall power cost. The process plant is expected to consume an average of 64 MW, operating for 7,884 hours annually, with a total annual power cost estimated at $14 million.

18.9.4 Labor

Operating and maintenance labor costs for the process plant were determined from first principles, taking into account a typical organizational structure and labor rates sourced from the AGP project database. Labor for the process plant comprises a combination of day and shift work. A summary of the labor complement is provided below in Table 18.31.

Table 18.31: Process Labor
Location Number of Employees
Operations 66
Maintenance 49
Laboratory 13
Total 128

The following shift rotations are assumed:

  • professional employees and management - 5 days on/2 days off
  • operations and maintenance staff - 12-hour shifts, 4 days on, 4 days off rotation

18.9.5 Laboratory Costs

Laboratory costs cover necessary plant samples for monitoring metallurgical performance, including sample preparation, digestion, size analysis, and chemical analyses of production samples. Grade control costs are not included here and fall under mining expenses. The average laboratory cost is approximately $0.02 per ton of material processed.


 

18.10 GENERAL AND ADMINISTRATIVE OPERATING COSTS

General and administrative costs were estimated for each year of the project schedule. No camp facilities are required due to the proximity to the city of Yerington. G&A costs are $10.4 million per year and remain at that level until Year 12 then gradually decreasing until Year 13. Although mining ceases in Year 12, G&A costs are extended for an additional year to cover all closure-related activities. Wages for staff and hourly personnel in the G&A area total $5.1 million per year. The life-of-mine average G&A cost amounts to $0.30 per ton of feed or a total of $134.0 million over the entire mine life.


 

19.0 ECONOMIC ANALYSIS

19.1 CAUTIONARY STATEMENT

Certain information and statements contained in this section and in the Report are "forward looking" in nature. Forward-looking statements include, but are not limited to, statements with respect to the economic and study parameters of the Project; Mineral Resource estimates; the cost and timing of any development of the Project; the proposed mine plan and mining methods; dilution and extraction recoveries; processing method and rates and production rates; projected metallurgical recovery rates; infrastructure requirements; capital, operating and sustaining cost estimates; the projected life of mine and other expected attributes of the Project; the net present value (NPV) and internal rate of return (IRR after-tax) and payback period of capital; capital; future metal prices; the timing of the environmental assessment process; changes to the Project configuration that may be requested as a result of stakeholder or government input to the environmental assessment process; government regulations and permitting timelines; estimates of reclamation obligations; requirements for additional capital; environmental risks; and general business and economic conditions.

All forward-looking statements in this Report are necessarily based on opinions and estimates made as of the date such statements are made and are subject to important risk factors and uncertainties, many of which cannot be controlled or predicted. Material assumptions regarding forward-looking statements are discussed in this Report, where applicable. In addition to, and subject to, such specific assumptions discussed in more detail elsewhere in this Report, the forward-looking statements in this Report are subject to the following assumptions:

  • There being no significant disruptions affecting the development and operation of the Project
  • The availability of certain consumables and services and the prices for power and other key supplies being approximately consistent with assumptions in the Report
  • Labor and materials costs being approximately consistent with the assumptions in the Report
  • Permitting and arrangements with stakeholders being consistent with current expectations as outlined in the Report
  • All environmental approvals, required permits, licenses and authorizations will be obtained from the relevant governments and other relevant stakeholders
  • Certain tax rates, including the allocation of certain tax attributes, being applicable to the Project
  • The availability of financing for the planned development activities
  • The timelines for exploration and development activities on the Project
  • Assumptions made in Mineral Resource estimate and the financial analysis based on that estimate, including, but not limited to, geological interpretation, grades, commodity price assumptions, extraction and mining recovery rates, hydrological and hydrogeological assumptions, capital and operating cost estimates, and general marketing, political, business, and economic conditions

The production schedules and financial analysis annualized cash flow table are presented with conceptual years shown. Years shown in these tables are for illustrative purposes only. This Pre-Feasibility Study (PFS) supports a Mineral Reserve declaration, with the mine plan and financial analysis based on Proven and Probable Mineral Reserves as defined under S-K 1300 standards. The PFS provides a higher level of confidence than previous studies, but like all forward-looking information, there is no guarantee that results, estimates, or projections will be realized as anticipated. Methodology Used


 

19.2 METHODOLOGY USED

Samuel Engineering conducted a discount cash flow analysis for the Yerington Copper Project. The economic analysis of the Yerington Copper Project is reliant on the project schedule, mine schedule, capital, and operating costs discussed in the previous sections of this report. The technical and cost inputs were developed by Samuel Engineering, AGP Mining Consultants and Newfields with specific data provided by Lion CG. These inputs were reviewed in detail and deemed reasonable.

The analysis was performed on a stand-alone project basis, using annual cash flows discounted at 7% on an end-of-year basis. The economic evaluation was conducted as of the start of construction (Year -3), based on Q1 2025 US dollars.

Sunk costs (expenditures incurred before construction) are excluded from the economic analysis. The accuracy of this evaluation aligns with the capital cost estimate, with an expected range of -25% to +25%.

19.3 FINANCIAL MODEL PARAMETERS

Technical-economic parameters used in the model are summarized in the following sections. Table 19.1 presents the model input used in the economic analysis based on the first quarter, 2025 US dollars. Two scenarios are included in the economic analysis. The first scenario includes two acid plants, in which excess sulfuric acid not needed for the copper production is sold to the market for a duration of 20 years. The second scenario considers only the acid required for copper production with no excess sales. Scenario 2 includes only one sulfuric acid plant, with sulfuric acid being purchased from a third party in years 3 through 7 to meet the needs of the copper production.

Table 19.1: Economic Model Parameters
Description Values
Construction Period (years) 3
Mine Life (years) 12
Operating Life (years) 14
Discount Rate 7%
Closure Duration MacArthur, 2 years starting in Year 9
Yerington, 2 years beginning in Year 15
Acid Plants, 1 year beginning in Year 20
Copper Production
Tons Processed (ktons) 506,551
Tons Waste Mined (ktons) 159,783
Strip Ratio 0.32
Copper Production - LOM Cu Cathodes (klbs) 1,442,704
Sulfuric Acid Production
Excess 95% Sulfuric Acid Production (ktons) Scenario 1 14,239
Metal & Sulfuric Acid Pricing
Copper Price ($/lb) $4.30
Copper Premium ($/lb) $0.16
Sulfuric Acid Price ($/ton) $121


 

Table 19.1: Economic Model Parameters
Cost Criteria
Estimate Basis First Quarter 2025
Inflation None
Leverage 100% Equity
Royalties
Yerington Production Royalty 2%, capped at $7.5 million
MacArthur Production Royalty 1% with $1 million buydown
Taxes  
Lyon County Property Tax 1.86%
Nevada State Tax 5%
Federal Tax 21%

19.4 CAPITAL COSTS

The initial capital cost is estimated at $724 million and is the same for both Scenarios 1 and 2 as shown in Table 19.2. Sustaining and working capital for Scenario 1 is estimated at 1.09 billion and 884 million for Scenario 2 as shown in Table 19.3.

Table 19.2: Initial Capital Cost Summary
Description Cost ($000s)
DIRECT COSTS  
Site Prep and Access Roads 25,777
Truck Shop and Admin 15,475
Warehouse and Maintenance Facilities 4,200
Rail 35,514
MacArthur Heap Leach 54,782
Yerington Leach Pad 16,845
MacArthur SX 37,032
Yerington SX/EW 75,990
MacArthur Water 3,533
MacArthur Utilities 1,018
Yerington Water 35,178
Yerington Utilities 10,704
Acid Plant 130,240
INDIRECT COSTS  
Contractor Indirects & Equipment 24,276
Third Party Surveying, Testing & QA/QC 2,207
Construction Camp 7,500
EPCM 20,931
Pre-Operational Testing & Vendor Reps 5,879
Process Facilities Spare Parts 4,902
Initial Fills 519
Plant Mobile Equipment 2,053
Mine Equipment 22,823


 

Table 19.2: Initial Capital Cost Summary
Preproduction Dewatering 7,331
Freight 22,114
Owner's Cost 9,890
Bond Payment 12,669
Contingency 134,681
TOTAL INITIAL CAPITAL 724,063

Table 19.3: Sustaining and Working Capital Cost Summary
Description Scenario 1
Excess Acid Sales
Cost ($000s)
Scenario 2
No Acid Sales
Cost ($000s)
Mining 40,680 40,680
Dewatering 16,613 16,613
Acid Plant #1 23,070 15,380
Acid Plant #2 120,177 0
Process Plant 396,085 396,085
Infrastructure (Includes HLF) 285,431 285,431
Indirects 125,693 125,693
Total Sustaining Capital 1,007,749 879,882
Working Capital 1,563 3,618
Total Working & Sustaining Capital 1,009,312 883,500

19.5 OPERATING COSTS

Table 19.4 shows the total LOM operating cost is estimated at $3.5 billion for Scenario 1 and includes 20 years of operational costs for the portion of acid sold to the market. Table 19.5 shows the total LOM operating cost is estimated at $2.9 billion for Scenario 2. Figure 19.1 and Figure 19.2 shows the OPEX split for both Scenario 1 and 2.

Table 19.4: Scenario 1 Excess Acid Sales Life of Mine Operating Cost Summary
Description LOM Cost
($000s)
LOM Cost/ton
Mineralized Material
($)
LOM Cost/lb. Cu
($)
Mining 1,698,302 3.35 1.18
Processing 946,511 1.87 0.66
General & Administrative 124,026 0.24 0.09
Excess Sulfuric Acid 725,633 N/A N/A
LOM Operating Cost 3,494,471 5.47 1.92


 

Figure 19.1: Scenario 1 Excess Acid Sales OPEX Split

Table 19.5: Scenario 2 No Acid Sales Life of Mine Operating Cost Summary
Description LOM Cost
($000s)
LOM Cost/ton
Mineralized Material
($)
LOM Cost/lb. Cu
($)
Mining 1,698,302 3.35 1.18
Processing 1,129,136 2.23 0.78
General & Administrative 124,026 0.24 0.09
Excess Sulfuric Acid 0 N/A N/A
LOM Operating Cost 2,951,464 5.83 2.05

Figure 19.2: Scenario 2 No Acid Sales OPEX Split


 

19.6 ROYALTIES

The MacArthur royalty payments are based on a 2.0% royalty to North Exploration which can be reduced to 1% with a $1 million buydown. The $1 million buydown has been assumed to occur in Year 1.

Arimetco has a 2% royalty on the Yerington Property with a cap of $7.5 million on total cumulative payments. Payments begin in Year 3 with the $7.5 million cap met by Year 4.

The estimated royalty payments for life of mine total $23 million.

19.7 TAXES, DEPRECIATION AND DEPLETION

The Yerington Copper Project is subject to local Nevada and Federal Taxes. The relevant taxes and fiscal benefits by level of government are summarized below. Two types of depreciation are utilized in the tax calculations as shown in Table 19.6 below.

Table 19.6: Depreciation Methods
Depreciation Item Nevada Federal
Type Years Type Years
Mining Straight Line 7 MACRS 7
Process Straight Line 7 MACRS 7
Infrastructure Straight Line 39 MACRS 39
Dewatering Straight Line 5 MACRS 5
Acid Plant Straight Line 5 MACRS 5
Indirects Straight Line 10 MACRS 10

19.7.1 Property Tax - Lyon County

The Lyon County tax is calculated at 1.86% of the estimated assessed value, factoring in depreciation. To determine the tax levy, a rate of 35% is first applied to the assessed value.

19.7.2 Nevada State Tax

The Nevada State tax calculation considers revenue in relation to operating costs, Lyon County property tax, Federal depreciation, and Depletion, which is set at the standard rate of 15% for copper projects. A tax rate of 5% is used for the Nevada State Tax.

19.7.3 Federal Tax

Federal tax liability is determined by applying a rate of 21% to the net income before taxes, following deductions for the Nevada Net Proceeds tax.

19.7.4 Federal Tax Credits

The Advanced Manufacturing Tax Credit under the Inflation Reduction Act of 2022 allows for 10% credit of production costs to produce/sell copper as it relates to federal income taxes. Starting in 2030, the phase out percentages are 75 percent, 50 percent and 25 percent each year until 2032. Federal taxes for the Yerington Copper Project are not scheduled to be paid until conceptual year 5, which is beyond the phase out of 2032 if the project began today. Therefore, no credit has been applied. The One Big Beautiful Bill Act signed into law on July 4, 2025, has several tax benefits in relation to the Yerington Copper Project including bonus depreciation and an increase of the Advanced Manufacturing Tax Credit. Changes based on that law have not been included and further tax opportunities may exist.


 

Table 19.7 summarizes the total taxes paid for Scenario 1 and Scenario 2.

Table 19.7: LOM Taxes
Description Scenario 1
Excess Acid Sales Tax
($000s)
Scenario 2
No Acid Sales Tax
($000s)
Lyon County Property Tax 70,871 59,076
Nevada State Tax 111,428 77,417
Federal Tax 416,920 280,850
LOM Taxes Paid 599,219 417,343

19.8 ECONOMIC RESULTS

The results of the economic analysis are provided in Table 19.8 for both scenarios. Table 19.9 and Table 19.10 show the cash flow summary for each scenario.

Table 19.8: Economic Model Results
Description Scenario 1
Excess Acid Sales
Scenario 2
No Acid Sales
Pre Tax Economics    
IRR 16.9% 13.8%
Cashflow (Undiscounted) ($000's) 2,914,325 1,854,544
NPV 7% Discount Rate ($000's) 975,426 554,070
Payback (years) 6.4 6.9
After Tax Results    
IRR 14.6% 11.6%
Cashflow (Undiscounted) ($000's) 2,315,107 1,437,201
NPV 7% Discount Rate ($000's) 694,265 347,312
Payback (years) 6.7 7.2


 

Table 19.9: Scenario 1 Excess Acid Sales Cash Flow Summary
$ Values in Millions Total Year -3 Year -2 Year -1 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15-20
Copper Cathodes & Acid Sold                                      
Yerington Oxide (Million lbs) 231.9 0.0 0.0 0.0 0.0 0.0 10.0 51.9 64.3 39.3 51.2 15.0 0.2 0.0 0.0 0.0 0.0 0.0 0.0
Yerington Sulfide (Million lbs) 887.6 0.0 0.0 0.0 0.0 0.0 16.5 9.8 30.0 100.1 119.5 125.2 139.3 140.7 132.4 59.8 13.1 1.1 0.0
MacArthur Oxide (Million lbs) 323.2 0.0 0.0 0.0 40.9 70.6 97.6 65.7 27.0 17.2 4.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Excess Acid Production (ktons) 14238.5 0.0 0.0 0.0 258.7 669.3 479.5 357.9 383.2 363.5 424.7 602.0 648.1 650.4 663.0 899.3 1069.5 1132.2 5637.1
Revenue                                      
Yerington Oxide 1034.4 0.0 0.0 0.0 0.0 0.0 44.5 231.6 286.7 175.4 228.3 66.7 1.0 0.1 0.0 0.0 0.0 0.0 0.0
Yerington Sulfide 3958.5 0.0 0.0 0.0 0.0 0.0 73.5 43.8 133.7 446.5 533.1 558.6 621.3 627.5 590.5 266.8 58.2 4.9 0.0
MacArthur Oxide 1441.6 0.0 0.0 0.0 182.6 315.0 435.2 293.1 120.4 76.5 18.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Excess Acid Production 1722.9 0.0 0.0 0.0 31.3 81.0 58.0 43.3 46.4 44.0 51.4 72.8 78.4 78.7 80.2 108.8 129.4 137.0 136.7
Deductions                                      
Yerington Royalty 7.5 0.0 0.0 0.0 0.0 0.0 2.4 5.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
MacArthur Royalty 15.4 0.0 0.0 0.0 2.8 3.2 4.4 2.9 1.2 0.8 0.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Net Income 8134.4 0.0 0.0 0.0 211.1 392.8 604.5 603.8 586.0 741.6 831.3 698.1 700.8 706.3 670.8 375.6 187.6 141.9 682.1
                                       
Operating Costs                                      
Mining, Processing, G&A 2768.8 0.0 0.0 0.0 134.1 205.3 263.6 288.3 293.9 319.2 298.6 212.2 209.2 209.0 211.6 102.5 21.0 0.2 0.0
Acid Plants 725.6 0.0 0.0 0.0 12.8 33.2 25.1 18.8 20.1 19.0 22.3 31.6 34.0 34.1 34.8 44.4 52.8 57.4 285.1
                                       
EBITA 4639.9 0.0 0.0 0.0 64.1 154.4 315.7 296.8 272.0 403.4 510.4 454.2 457.6 463.2 424.4 228.7 113.8 84.3 79.6
Initial Capital 724.1 50.8 278.9 394.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Sustaining Capital 1007.7 0.0 0.0 0.0 255.3 445.7 7.6 61.1 141.1 43.1 4.6 0.2 23.1 5.1 0.3 5.0 3.8 0.0 11.5
Working Capital 1.6 0.0 0.0 0.0 0.8 3.7 11.4 (2.3) (2.4) 9.9 9.6 (1.5) 0.3 0.5 (3.4) (12.2) (6.5) (1.8) (4.6)
Closure Bond & Closure Costs (7.8) 0.0 0.0 0.0 0.4 0.4 0.4 0.4 0.4 0.4 3.1 0.4 6.7 6.6 0.4 0.4 3.9 0.4 (32.0)
                                       
Before Tax Cash Flow 2914.3 (50.8) (278.9) (394.3) (192.4) (295.4) 296.4 237.6 132.9 349.9 492.9 455.1 427.5 451.1 427.0 235.5 112.5 85.7 422.1
Cumlative Before Tax Cash Flow 2914.3 (50.8) (329.7) (724.1) (916.4) (1211.8) (915.5) (677.8) (544.9) (195.0) 297.9 753.0 1180.5 1631.6 2058.5 2294.0 2406.5 2492.2 2914.3
                                       
After Tax Cash Flow 2315.1 (50.8) (278.9) (394.3) (198.6) (303.9) 284.4 228.4 122.8 305.5 418.6 385.1 350.1 370.3 353.1 196.3 94.1 72.8 360.3
Cumulative After Tax Cash Flow 2315.1 (50.8) (329.7) (724.1) (922.7) (1226.6) (942.2) (713.8) (591.0) (285.5) 133.0 518.2 868.3 1238.6 1591.7 1788.0 1882.1 1954.8 2315.1


 

Table 19.10: Scenario 2 No Acid Sales Cash Flow Summary
$ Values in Millions Total Year -3 Year -2 Year -1 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15-20
(Each Year)
Copper Cathodes & Acid Sold                                      
Yerington Oxide (Million lbs) 231.9 0.0 0.0 0.0 0.0 0.0 10.0 51.9 64.3 39.3 51.2 15.0 0.2 0.0 0.0 0.0 0.0 0.0 0.0
Yerington Sulfide (Million lbs) 887.6 0.0 0.0 0.0 0.0 0.0 16.5 9.8 30.0 100.1 119.5 125.2 139.3 140.7 132.4 59.8 13.1 1.1 0.0
MacArthur Oxide (Million lbs) 323.2 0.0 0.0 0.0 40.9 70.6 97.6 65.7 27.0 17.2 4.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Excess Acid Production (ktons) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Revenue                                      
Yerington Oxide 1034.4 0.0 0.0 0.0 0.0 0.0 44.5 231.6 286.7 175.4 228.3 66.7 1.0 0.1 0.0 0.0 0.0 0.0 0.0
Yerington Sulfide 3958.5 0.0 0.0 0.0 0.0 0.0 73.5 43.8 133.7 446.5 533.1 558.6 621.3 627.5 590.5 266.8 58.2 4.9 0.0
MacArthur Oxide 1441.6 0.0 0.0 0.0 182.6 315.0 435.2 293.1 120.4 76.5 18.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Excess Acid Production 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Deductions                                      
Yerington Royalty 7.5 0.0 0.0 0.0 0.0 0.0 2.4 5.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
MacArthur Royalty 15.4 0.0 0.0 0.0 2.8 3.2 4.4 2.9 1.2 0.8 0.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Net Income 6411.5 0.0 0.0 0.0 179.8 311.9 546.5 560.5 539.6 697.6 779.9 625.3 622.4 627.6 590.5 266.8 58.2 4.9 0.0
                                       
Operating Costs                                      
Mining, Processing, G&A 2951.5 0.0 0.0 0.0 134.3 206.2 281.9 321.4 325.3 353.4 323.0 219.5 217.0 216.8 219.5 110.2 22.6 0.3 0.0
Acid Plants 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
                                       
EBITA 3460.1 0.0 0.0 0.0 45.5 105.7 264.6 239.1 214.4 344.2 456.9 405.8 405.4 410.8 371.0 156.6 35.6 4.6 0.0
Initial Capital 724.1 50.8 278.9 394.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Sustaining Capital 879.9 0.0 0.0 0.0 154.4 445.7 7.6 57.2 141.1 43.1 0.8 0.2 23.1 1.2 0.3 5.0 0.0 0.0 0.0
Working Capital 3.6 0.0 0.0 0.0 1.8 2.0 10.1 (3.8) (2.2) 9.6 10.7 0.1 0.1 0.5 (3.4) (13.3) (6.4) (1.7) (0.4)
Closure Bond & Closure Costs (2.0) 0.0 0.0 0.0 0.4 0.4 0.4 0.4 0.4 0.4 3.1 0.4 6.7 6.6 0.4 0.4 3.9 0.4 (26.3)
                                       
Before Tax Cash Flow 1854.5 (50.8) (278.9) (394.3) (111.1) (342.5) 246.5 185.2 75.1 291.0 442.3 405.1 375.5 402.5 373.7 164.5 38.1 5.8 26.7
Cumlative Before Tax Cash Flow 1854.5 (50.8) (329.7) (724.1) (835.2) (1177.6) (931.1) (745.9) (670.8) (379.7) 62.5 467.7 843.2 1245.7 1619.4 1783.9 1822.0 1827.9 1854.5
                                       
After Tax Cash Flow 1437.2 (50.8) (278.9) (394.3) (116.4) (349.8) 236.3 176.9 68.4 270.2 379.1 344.2 308.0 331.6 309.7 139.0 33.8 3.6 26.7
Cumulative After Tax Cash Flow 1437.2 (50.8) (329.7) (724.1) (840.4) (1190.3) (953.9) (777.1) (708.7) (438.5) (59.4) 284.7 592.7 924.3 1234.0 1373.1 1406.9 1410.5 1437.2


 

19.9 SENSITIVITY ANALYSIS

Table 19.11 through Table 19.13 and Figure 19.3 through Figure 19.8 show the relative sensitivity of NPV and IRR as capital and operating costs and copper price change in the Scenario 1 Excess Acid Sales economic model.

The sensitivity analysis shows that the Project is the most sensitive to copper price changes. Operating and capital cost changes have a lower impact on Project NPV than the former variable.

Table 19.11: Copper Price Sensitivity - Scenario 1 Excess Acid Sales
Sensitivity (%)/Item Copper
Price
Pre-Tax Post-Tax
  NPV IRR Payback NPV IRR Payback
$/lb $M % Years $M % Years
-50% $2.15 ($754) -1.2% N/A ($794) -1.6% N/A
-45% $2.37 ($581) 0.7% 17.78 ($621) 0.3% 18.69
-40% $2.58 ($408) 2.6% 13.94 ($459) 1.9% 14.67
-35% $2.80 ($235) 4.5% 10.96 ($309) 3.5% 11.49
-30% $3.01 ($62) 6.3% 9.82 ($164) 5.2% 10.19
-25% $3.23 $111 8.2% 8.96 ($21) 6.8% 9.34
-20% $3.44 $284 10.0% 8.20 $122 8.4% 8.60
-15% $3.66 $457 11.8% 7.61 $266 10.0% 7.95
-10% $3.87 $629 13.5% 7.12 $410 11.6% 7.45
-5% $4.09 $802 15.3% 6.73 $553 13.1% 7.02
0% $4.30 $975 16.9% 6.40 $694 14.6% 6.68
5% $4.52 $1,148 18.6% 6.11 $836 16.1% 6.39
10% $4.73 $1,321 20.2% 5.82 $976 17.5% 6.13
15% $4.95 $1,494 21.7% 5.53 $1,116 18.9% 5.87
20% $5.16 $1,667 23.3% 5.28 $1,254 20.3% 5.61
25% $5.38 $1,840 24.8% 5.06 $1,390 21.5% 5.39
30% $5.59 $2,013 26.3% 4.75 $1,525 22.8% 5.20
35% $5.81 $2,186 27.7% 4.45 $1,662 24.1% 5.02
40% $6.02 $2,359 29.1% 4.19 $1,800 25.3% 4.75
45% $6.24 $2,532 30.5% 3.98 $1,938 26.5% 4.49
50% $6.45 $2,705 31.9% 3.83 $2,077 27.8% 4.27


 

Figure 19.3: Copper Price per Pound Sensitivity on NPV 7% (Pre-tax, Scenario 1 Excess Acid Sales)


 

Figure 19.4: Copper Price per Pound Sensitivity on IRR (Pre-tax, Scenario 1 Excess Acid Sales)

Table 19.12: CAPEX Sensitivity (Initial + Sustaining) - Scenario 1 Excess Acid Sales
Sensitivity
(%)

/ Item
CAPEX
Value
Pre-Tax Post-Tax
NPV IRR Payback NPV IRR Payback
$M $M % Years $M % Years
-25% $1,299 $1,322 23% 5.38 $1,006 20% 5.69
-20% $1,385 $1,253 22% 5.61 $944 19% 5.94
-15% $1,472 $1,183 20% 5.84 $882 18% 6.14
-10% $1,559 $1,114 19% 6.06 $819 17% 6.32
-5% $1,645 $1,045 18% 6.23 $757 16% 6.50
0 $1,732 $975 17% 6.40 $694 15% 6.68
5% $1,818 $906 16% 6.57 $631 14% 6.86
10% $1,905 $837 15% 6.74 $569 13% 7.05
15% $1,992 $768 14% 6.91 $506 12% 7.24
20% $2,078 $698 13% 7.08 $443 11% 7.43
25% $2,165 $629 13% 7.27 $380 11% 7.63


 

Table 19.13: OPEX Sensitivity - Scenario 1 Excess Acid Sales
Sensitivity (%) Item OPEX Value Pre-Tax Post-Tax
NPV IRR Payback NPV IRR Payback
$M $M % Years $M % Years
-25% $2,077 $1,457 22% 5.51 $1,074 19% 5.89
-20% $2,215 $1,361 21% 5.69 $1,000 18% 6.05
-15% $2,354 $1,264 20% 5.88 $925 17% 6.19
-10% $2,492 $1,168 19% 6.06 $848 16% 6.34
-5% $2,630 $1,072 18% 6.22 $771 15% 6.51
0 $2,769 $975 17% 6.40 $694 15% 6.68
5% $2,907 $879 16% 6.58 $617 14% 6.87
10% $3,046 $783 15% 6.78 $539 13% 7.07
15% $3,184 $687 14% 6.99 $462 12% 7.29
20% $3,323 $590 13% 7.23 $382 11% 7.53
25% $3,461 $494 12% 7.48 $303 10% 7.79

Figure 19.5: Multiple % Sensitivity on NPV @ 7% (Pre-tax, Scenario 1 Excess Acid Sales)


 

Figure 19.6: Multiple % Sensitivity on NPV @ 7% (Post-tax, Scenario 1 Excess Acid Sales)


 

Figure 19.7: Multiple % Sensitivity on IRR (Pre-tax, Scenario 1 Excess Acid Sales)

Figure 19.8: Multiple % Sensitivity on IRR (Post-tax, Scenario 1 Excess Acid Sales)


 

20.0 ADJACENT PROPERTIES

20.1 MASON PROJECT

The Mason Project, which is held by Hudbay Minerals Inc. (Hudbay) is located approximately 3 miles (5 km) west of the Yerington pit. The Mason Project is a typical copper-molybdenum porphyry system hosted within a Jurassic quartz monzonite. The mineralization is described as being closely associated with the quartz monzonite porphyry dikes. The QP was not able to independently verify the information Hudbay (2023) provided. The mineralization for the Mason Project is not necessarily indicative of the mineralization present at the Yerington Copper project.

The current mineral resource estimate for the Mason Project is summarized in Table 20.1.

Table 20.1: Mason Project Mineral Resource (Hudbay, 2023)
Category Tonnes (000s) Cu (%) Mo (g/t) Au (g/t) Ag (g/t)
Measured 1,417,000 0.29 59 0.031 0.66
Indicated 801,000 0.30 80 0.025 0.57
Measured and Indicated 2,219,000 0.29 67 0.029 0.63
Inferred 237,000 0.24 78 0.033 0.73

Note: Totals may not add up correctly due to rounding.

1. Mineral resource estimates that are not mineral reserves do not have demonstrated economic viability.

2. Mineral resource estimates do not include factors for mining recovery or dilution.

3. Metal prices of $3.10 per pound copper, $11.00 per pound molybdenum, $1,500 per ounce gold, and $18.00 per ounce silver were used to estimate mineral resources.

4. Mineral resources are estimated using a minimum NSR cut-off of $6.25 per tonne.

5. Mineral resources are based on resource pit designs containing measured, indicated, and inferred mineral resources.

20.2 PUMPKIN HOLLOW PROJECT

The Pumpkin Hollow Project, which is held by Southwest Critical Minerals, previously permitted and operated by Nevada Copper, is located about 10 miles southeast of the Yerington pit. The Pumpkin Hollow Project is dominantly a copper and magnetite skarn, forming from Jurassic quartz monzonite and quartz monzonite porphyries intruding the limestones of the Triassic Mason Valley Formation and calcareous argillites and siliceous shales, siltstones, and limestones of the Trassic Gardnerville Formation. The QP was not able to independently verify the information Nevada Copper (2019) provided. The mineralization for the Pumpkin Hollow project does not necessarily indicate the mineralization present at the Yerington Copper project.

The current mineral resource estimate for the Pumpkin Hollow project is summarized in Table 20.2 and Table 20.3 for underground and open pit mineral resources, respectively.


 

Table 20.2: Pumpkin Hollow Project, Underground Mineral Resource (2019)
Category Cutoff
Grade Cu (%)
Tons
(millions)
Cu (%) Au (oz/t) Ag (oz/t)
Measured 0.75 12.1 1.60 0.006 0.127
Indicated 0.75 41.9 1.33 0.005 0.112
Measured and Indicated 0.75 54.1 1.39 0.005 0.116
Inferred 0.75 29.2 1.09 0.003 0.064

Notes: Totals may not add up correctly due to rounding.

1. Includes East and E2 deposits.

2. Measured and Indicated Resources are stated as inclusive of reserves.

3. Resources are constrained by a 0.5% Cu mineralized interpretation.

4. Effective date for the Underground Mineral Resource is April 15, 2015.

5. Mineral resource estimates that are not mineral reserves do not have demonstrated economic viability.

Table 20.3: Pumpkin Hollow Project, Open Pit Mineral Resource (2019)
Category Cutoff
Grade Cu (%)
Tons
(millions)
Cu (%) Au (oz/t) Ag (oz/t)
Measured 0.12 134.0 0.561 0.002 0.064
Indicated 0.12 419.0 0.417 0.001 0.051
Measured and Indicated 0.12 553.0 0.452 0.002 0.054
Inferred 0.12 28.0 0.358 0.001 0.040

Notes: Totals may not add up correctly due to rounding.

1. Cut-off grades are based on a price of US3.75/lb Cu, US$1,343/oz Au and US$19.86/oz Ag.

2. Metallurgical recoveries of 90% were used for the North Pit and 88% for the South Pit.

3. Measured and Indicated Resources are stated as inclusive of reserves.

4. Effective date for the Open Pit Mineral Resource is January 21, 2019.

5. Mineral resource estimates that are not mineral reserves do not have demonstrated economic viability.


 

21.0 OTHER RELEVANT DATA AND INFORMATION

This section discusses additional environmental and stakeholder engagement activities related to the Yerington Copper Project (the Project). These topics are often referred to using a variety of terms such as Environmental/Social/Governance (ESG), Sustainability, Social Responsibility, License to Operate and other similar terms. Simply put, a commitment to ESG means that the project development will take into account the environmental and social context in which it operates, striving to minimize its footprint and amplify the opportunities to achieve positive outcomes for the communities in the vicinity of the Project. This has been a central consideration for Lion CG since the project was envisioned, and it remains the foundation of the Company's operating principles. The current partnership with Nuton as a technology provider and an investor further supports the Project's ambition to be a force for good in the Mason Valley area.

21.1 ENVIRONMENTAL FOOTPRINT AND BENCHMARKING

Copper is designated as a critical material by the Department of Energy and as the world transitions to a low-carbon future to address global climate change and moves toward electrification and renewable energy sources. The Project aspires to produce copper to support this global transition, while creatively utilizing the latest technologies to minimize its own environmental footprint.

Guiding principles for setting Lion CG's environmental stewardship goals were developed to significantly reduce the environmental footprint of the mining operations, including lowering energy and water consumption, minimizing operational land disturbed, addressing greenhouse gas emissions and reducing waste. Lion CG has committed to achieving these goals by applying environmentally responsible technologies and processes during the entire lifecycle of the proposed mine and through mine closure. The Project is also seeking to have long-term positive impacts on the greater Mason Valley area and the people who live in nearby communities, while contributing positively to the local economy.

21.2 ENVIRONMENTAL OPTIMIZATIONS DUE TO NUTON TECHNOLOGY

One of the key considerations of any mining project is the selection of an appropriate processing technology for the ore under consideration. This decision is informed by the characteristics of the resource, the economics of the project and increasingly by the environmental impacts of the technology in question. In this case, the Yerington Copper Project consists of oxide, transition and primary sulfide copper resources. Primary sulfide copper resources are traditionally processed through a concentrator, smelter, and refinery in order to produce refined copper. This is a water, land, and power intensive process, often involving complex supply-chain logistics across borders and large capital expense. At the Project, processing of the primary sulfide resources takes advantage of Nuton Technology, a suite of proprietary catalytic bio-heap leaching technologies. Nuton is able to process sulfide copper ores with market-leading copper recoveries, unlocking primary copper resources more economically, with lower environmental impact and with the benefit of producing copper cathode on-site that will be available to domestic consumers. Application of the Nuton Technology also eliminates the need to permit, build and manage a tailing storage facility, and eliminates risks associated with it.

Given the host of environmental and economic benefits of Nuton Technology over the traditional route to process sulfides, this is the project's preferred path for the PFS. Nuton has successfully completed extensive laboratory-level and pilot scale testing and has developed proprietary modeling techniques to simulate results suitable for a PFS.


 

21.3 STAKEHOLDER ENGAGEMENT

Lion CG developed a Stakeholder Outreach Strategy (SOS) that identifies stakeholders that may have an interest in or will be affected by the Project. The SOS is used to guide Lion CG's engagement efforts with the local Communities, Lyon County, Indian Tribes, Regulatory Agencies and Elected Officials. Stakeholder engagement will continue to be an important element of the Company's ESG program going forward. Our goal is to advance this important project with full community and stakeholder input and build a project with the end in mind.

Lion CG is committed to transparent and ongoing communication with all stakeholders that will be affected by the Yerington Copper Project. Effectively communicating a clear narrative about the Project is essential. Lion CG will continue to provide details of the project as they are developed, so that key stakeholders can formulate fact-based perceptions about the Project. The following key messages are guiding ongoing public communications and stakeholder outreach regarding the Project.

21.3.1 Reclaiming 100 Years of Mining History

The long history of mining at the Yerington Copper Project location is well-known. The boom times of the active Anaconda mine brought jobs and growth to the region, but left legacy contamination and ongoing challenges for the communities near the mine. Lion CG is committed to operate the best of modern mining technologies to extract the unrealized value of the mine and, in doing so, fully reclaim the mine following the completion of operations.

21.3.2 Delivering a World-Class Mining Operation

Lion CG's goal is to deliver a world-class mining operation that leverages the most advanced modern technologies in the world and is designed with the highest environmental standards. By partnering with Nuton LLC, a Rio Tinto venture which is, a global company with some of the most advanced mining technologies in the world, as well as other experts and consultants, Lion CG is designing this project with the end in mind. Emphasis on a robust closure plan and an adequately funded reclamation bond will ensure safe closure of the mine at the end of operations. By utilizing technology that did not exist when the mine was previously active, LION CG will be able to enhance current remediation efforts.

21.3.3 Local Prosperity through Local Control

Lion CG believes this project has the potential to deliver economic benefits for the people of Yerington and northern Nevada in the form direct and indirect employment opportunities, wider economic benefits for the region, and support for local aquifers and water resources. While there have been previous attempts to restart mining operations at this mine, Lion CG believes that the changes in regulatory oversight of the project and advancements in mining technology and the global market will result in a viable, thriving project that will generate decades of domestic copper cathode production in Yerington, Nevada.


 

22.0 INTERPRETATION AND CONCLUSIONS

22.1 YERINGTON COPPER PROJECT

22.1.1 Yerington Property

AGP updated the Yerington Copper Project Mineral Resource estimate consisting of pit constrained Measured, Indicated, and Inferred Resources. This Yerington MRE used validated historic drill hole data generated by Anaconda and current drilling results by SPS in 2011, 2017, 2022 and 2024.

Historic and current drilling indicate that limits to the mineralization at the Yerington Mine have not yet been found, both horizontally and vertically, and additional exploration and in-fill drilling are warranted and are expected to both expand and upgrade the current S-K 1300 compliant copper resources.

Historic resources in the residuals which are part of the Yerington Copper Project reflect a potential to be evaluated to bring those resources into S-K 1300 standards. Mineral Resources were reported for the surficial deposit composed of Vat Leach Tails.

The updated Mineral Resources for the Yerington Deposit are: Measured Resources of 121.7 MTons at 0.27 TCu%; Indicated Resources of 323.3 MTons at 0.21 TCu%; and Inferred Resources of 108.5 MTons at 0.15 TCu%.  The cutoff grade used for Measured, Indicated and Inferred Oxide Resources is 0.04 TCu%.  The Sulfide Resource cutoff grade for Measured, Indicated and Inferred material is 0.08 TCu%.  The effective date of the Yerington Deposit Mineral Resources is March 17, 2025.

The VLT Mineral Resource amenable to open pit extraction was reported at 0.03 TCu% cut-off grade. The Indicated VLT Mineral Resource is 36.5 MTons at 0.09 TCu% and Inferred VLT Mineral Resource is 26.4 million tons at 0.09 TCu%.  The effective date of the VTL Mineral Resource estimate is March 17, 2025.

22.1.2 MacArthur Property

It is the opinion of IMC that the MacArthur Project Mineral Resource presented in this report has been completed in accordance with all requirements of S-K 1300 and has the potential to be expanded with additional drilling.

The Mineral Resource is updated with the drilling and geological interpretations current through the end of 2024. The reported Mineral Resource is pit shell constrained. A pit-constrained resource has a higher probability of converting a larger percentage of the mineral resource to a future mineral reserve when compared to an unconstrained mineral resource.

The cutoff grade for all material types is 0.05 TCu% in the MacArthur pit area, 0.06 TCu% in North Ridge, and 0.07 TCu% in Gallagher. The Mineral Resources for the MacArthur Project are: Measured Resources of 163.3 MTons at 0.177 TCu%; Indicated Resources of 155.1 MTons at 0.152 TCu%; and Inferred Resources of 23.2 MTons at 0.147 TCu%. The Mineral Resource at MacArthur includes overburden, leach cap, oxide and mixed materials and does not include any sulfide material.  The effective date of the Mineral Resource is March 17, 2025.


 

22.2 PROCESS, INFRASTRUCTURE

The two phases of Nuton test work have confirmed the initial benchtop modeling, which predicted that Yerington sulfide ore could achieve copper recoveries exceeding 70% with implementation of Nuton leaching technologies. Optimizing the combination of leach additives and operational pH targets enhances the leach kinetics and reduces acid consumption. Air and hydraulic conductivity of Yerington sulfide ore is suitable for the planned irrigation rates.

Preliminary indications are that Yerington and Macarthur oxide materials are well-suited for ROM heap leaching. Yerington oxide is expected to achieve a total copper extraction of 68%.  Macarthur oxide is expected to achieve a total copper extraction of 59%.

Portions of the MacArthur North Ridge and Gallagher "oxide" zones contain 20-30% transitional copper minerals which led to comparatively reduced empirical recovery historically.

22.3 MINING

Mineral resources were converted to reserves for use in the Yerington Copper Project. These include reserves from various areas of the Project, including the Yerington deposit, VLT stockpile, and the MacArthur deposits (MacArthur, Gallagher, and North Ridge). Open pit mining offers the most reasonable approach for development of the deposits based on the size of the resource, tenor of the grade, grade distribution and proximity to topography for the deposits.

The mine schedule for open pit mining totals 506.6 Mt of Proven and Probable heap leach feed grading 0.21% copper over a mine life of 12 years. Open pit waste tonnages from the various areas total 159.8 Mt and will be placed into waste storage areas adjacent to the open pits. The overall open pit strip ratio is 0.32:1 (waste: feed).

Three heap leach facilities will provide copper solution for the SX-EW facility. One process stream will utilize the Nuton Technology for the leaching of sulfide feed from the Yerington pit. The other process stream will employ conventional oxide copper leaching technology for the run-of-mine (ROM) feed from the MacArthur pits, Yerington oxide, and VLT stockpile. The Nuton facility will have a peak feed rate of 34 Mtpa through a crushing plant. The Yerington pit is the only supply of sulfide material for the PFS.

The current mine plan includes minimal prestripping as the bottom of the existing Yerington and MacArthur pits still contains material suitable for placement on an HLF with conventional leaching and using the Nuton process for the sulfide materials. Mining starts in the MacArthur pit, immediately providing ore for the heap facility. Mining starts in the Yerington pit in waste in Year 2 to advance mining, but as the water level in the Yerington pit recedes, ore is also immediately available. This is expected in Year 3.

22.4 HLF

For this study, the HLFs and associated structures have been designed to meet regulatory requirements and industry-accepted standards and practices, and are suitable for a PFS-level design.


 

Three HLFs are planned for the Project: Yerington West, Yerington East, and MacArthur. The 166 million dry tons of oxide ore generated from mining activities at the MacArthur pit will be stacked and leached on the MacArthur HLF. The sulfide ore generated from mining activities in the Yerington pit will be stacked and leached on the Yerington West HLF, capable of accommodating 234 million dry tons. The 140 million dry tons of oxide ore generated from mining activities at the Yerington pit and from reprocessing the legacy VLT will be stacked and leached on the Yerington East HLF.

For HLFs located on native soils, the geotechnical investigations showed that the native alluvium will form a suitable subgrade for HLF construction. The Yerington East HLF was sited toward the southern half of the existing sulfide tailings facility, where tailings are generally less than 40 ft thick based on the geotechnical investigations. Geotechnical evaluations completed for this PFS indicated additional foundation treatment is required in an isolated area on the north side of the HLF to meet the minimum recommended slope stability factor of safety values prescribed by the Nevada Division of Environmental Protection Bureau of Mining Regulation and Reclamation (NDEP-BMRR, 2021). The Yerington East HLF design includes a combination of a stability key and rock buttress along the northern portion of the facility.

HLF construction will consist of the following:

  • Bulk grading to achieve suitable drainage of the pads toward their respective process solution ponds
  • Limited foundation treatment
  • Constructing 12 inches of low-permeability compacted soil
  • Installing an 80-mil HDPE geomembrane liner
  • Installing a series of perforated pipes surrounded by free-draining gravel (overliner) over the geomembrane to convey process solution to the process ponds located at each HLF. The perforated pipes and overliner are incorporated into the design to meet regulatory requirements, minimize hydraulic head on the lining system, and to facilitate more rapid recovery of pregnant solution for processing

In compliance with the Nevada Administrative Code, each process pond will have an associated emergency or overflow pond to be used in conditions when the process pond capacity is exceeded. Ponds will be lined with a dual layer of 80-mil HDPE liner, separated by a layer of geonet with a leak detection and return system.

Additional investigations, evaluations, and analyses will be required at subsequent design phases to confirm assumptions and reduce the risk of encountering unforeseen conditions during construction.

22.5 ENVIRONMENTAL STUDIES, PERMITTING AND SOCIAL OR COMMUNITY IMPACT

The project will use NutonTM technology to process sulfide copper ores. NutonTM unlocks primary copper resources more economically and with lower environmental impact than a traditional mill/concentrator processing method. It also produces copper cathode on-site that will be available to domestic consumers. 


 

Water is a critical natural resource that is required to support the local agriculture, mining, municipal, commercial, and conservation needs in Mason Valley. Groundwater permits in Mason Valley are over-appropriated and could be subject to curtailment in the future; however, curtailment orders, if issued, based on previous Mason Valley curtailment orders, generally exclude mining water rights from such orders, given the continuous nature of pit dewatering and processing operations. Furthermore, pit dewatering will occur primarily within the bedrock groundwater system, which is poorly connected hydraulically to the alluvial groundwater system used by local irrigators (Piteau, 2025). Water conservation is a key metric for the success of the Project. NutonTM processes consume substantially less water per produced copper unit than a traditional mill/concentrator utilizing standard tailings storage facilities. Application of NutonTM technology eliminates the need to permit, build, and manage a tailing storage facility, eliminating the associated risks of tailings storage. The project's power needs are significantly reduced by utilizing the NutonTM bio-heap leach technology and eliminating the need for a mill/concentrator and smelter/refinery. On-site power will also be generated from the co-gen unit at the acid production facility.


 

23.0 RECOMMENDATIONS

The QPs recommend that Lion Copper and Gold Corp. advance to a Feasibility level of study (FS) as an integral component of the Yerington Copper Project's development strategy. In this regard, the QPs have presented recommendations and accompanying budgetary allocations to ensure the availability of adequate information for the Project's ongoing progression.

While certain costs associated with completing a Feasibility study are incorporated within the study's framework, additional expenses related to supporting studies or fieldwork are itemized in the relevant sections. For detailed cost estimates categorized by area, please refer to Table 23.1.

Table 23.1: Recommended Definitive Feasibility Study Budgets
Area of Study Approximate Cost ($USD)
Geology $2,800,000
Geotechnical $4,000,000
Mining $500,000
Metallurgy $1,500,000
Infrastructure $1,500,000
Environmental $1,000,000
Feasibility Study $8,500,000
TOTAL $19,800,000

23.1 GEOLOGY

To further advance the resource development for the Project, the following recommendations are made:

  • Drilling to upgrade the Mineral Resource classification for VLT and W-3 and to support a Mineral Resource estimate for S-23 - $2,000,000
  • Fresh core for metallurgical testing - $500,000
  • Sterilization drilling for HLP locations - $300,000

The cost of geology fieldwork is estimated to be $2.8 million during the FS.

23.2 GEOTECHNICAL

Additional geotechnical fieldwork and studies are required across the Yerington Copper Project to characterize subsurface conditions, provide parameters for geotechnical evaluations and analyses, and inform project designs (mine and infrastructure).

The following investigations are recommended to progress the mine designs to an FS level:

Mine Geotechnical

  • Yerington Pit Area

o Pit slope analysis, which includes:


 
  • Analysis of the wall slope configuration adjacent to Highway 339 and the Walker River
  • Final slope analysis in the Yerington pit
  • Waste dump stability analysis of the Yerington Pit Waste Rock Storage Facility
  • MacArthur Pit Area

o MacArthur, Gallagher, and North Ridge final slope analysis

o MacArthur waste rock storage facility stability analysis

To complete those tasks, the following fieldwork, subsequent geotechnical evaluations, and laboratory analyses will be conducted, encompassing:

  • Geotechnical Drilling - $3,000,000
  • Geotechnical Fieldwork - $300,000
  • Laboratory analysis of material and field samples - $500,000
  • Geotechnical evaluations/analyses - $200,000

The cost of the mine geotechnical investigations and analysis is estimated to be $4.0 million during the FS.

23.3 MINING

In addition to the standard analysis and design elements essential for a FS Mine design, the following mining activities are recommended:

  • Mine Equipment Selection:

o Conventional equipment selection

  • Detailed quotes from vendors
  • Continuous Miner Evaluation:

o Examination of the use of Wirtgen to

  • reduce blasting needs
  • size material to potentially reduce crushing capital for sulfide material
  • potential increase in recovery with smaller material for ROM heap leach facilities
  • Blasting Analysis:

o Detailed blasting analysis for areas adjacent to existing infrastructure

  • Waste Rock Storage Facility Optimization:

o Optimizing the design of waste storage facilities.

  • Contract Mining Comparison:

o Conducting a comprehensive assessment of contract mining options suitable for each pit area

The cost of mining analysis and optimization is estimated to be $0.50 million during the FS.


 

23.4 METALLURGY AND MINERAL PROCESSING

The QP recommended that Lion Copper and Gold Corp. perform an additional metallurgical test work program to further advance the process design criteria.  The test work program will incorporate the following:

  • All existing geological, mining, and metallurgical information should be compiled into an integrated geo-metallurgical model and incorporated into the feasibility level block model
  • Confirm acid consumption of Yerington oxide material to determine the root cause of the high acid consumption anomaly identified during PFS
  • Expand the ore hardness and crusher work index database to confirm final crusher design parameters
  • Test additional material that has potential to convert from resource to reserves in the FS study
  • The cost of the metallurgical test work is estimated to be $1.5 million for the FS

23.5 INFRASTRUCTURE

The following work is recommended to refine the cost estimate to FS level for site infrastructure:

  • Rail Spur design and costing for the proposed rail line and accompanying rail spurs at site.  Include all equipment or facilities needed for offloading sulfur and pyrite deliveries
  • Ancillary facilities design and costing. Further refine the cost estimate from PFS to include fit-for-purpose building options and assess current site buildings for remodel and upgrades for refinement to FS standard
  • Overland conveyor designs to refine costing based on designed conveyor profiles
  • Borrow material location sourcing: Identifying suitable sources for borrow materials

23.6 HLF

23.6.1 Geotechnical Investigations and Testing

  • Complete additional investigations such as geophysics, drilling, sampling, and test pitting within the footprint of the HLFs and associated ponds, surface water management infrastructure, and other process-related infrastructure. The investigations should be developed to further define foundation/subsurface conditions, determine if excavated soils will be a suitable fill source during cut-to-fill pad construction, and define the extent and characteristics of fine-grained sulfide tailings beneath the Yerington East HLF
  • Further define the quality and quantity of the potential construction material borrow sources, particularly the borrow sources for the low permeability soil liner (underliner) and for overliner. Laboratory testing to define the quality of the material would include geochemical sampling on potential construction material borrow sources and quantifying the potential processing required to generate materials that can meet the technical requirements
  • Perform geophysical testing in the footprint of the proposed HLFs to characterize shear wave velocity and refine seismic site classification for each location
  • Complete specialized laboratory testing on the legacy sulfide tailings to further evaluate liquefaction potential
  • Complete ore geotechnical characterization, to include laboratory testing such as strength and permeability testing

 
  • Complete liner interface testing and liner puncture testing with proposed design materials, including soil borrow materials (low permeability soil and overliner), geosynthetics, ore, and representative subsurface materials (as appropriate)

23.6.2 Geotechnical Evaluations

  • Perform a site-specific hazard response analysis to evaluate the seismic hazard and develop a surface response spectrum based on local ground motions at the Yerington Property. Site-specific ground motions will modify earthquake demands used in stability and liquefaction evaluations to reflect local subsurface conditions
  • Refine to revise liquefaction, slope stability, and settlement evaluations based on the results of additional investigations and laboratory testing
  • Complete a deformation evaluation to evaluate the effects of vibration-induced shaking on the HLF caused by a proposed rail line between Yerington West and Yerington East HLFs

The cost of geotechnical investigations and analyses during the FS is estimated to be $1.5 million.

23.6.3 Heap Leach Facilities and Surface Water Management Designs

  • Refine the earthwork grading and phasing of the HLFs
  • At the Yerington East HLF, explore additional design optimizations at the stability key/buttress on the north toe of the facility
  • Refine operational parameters for pond sizing and pond configurations
  • Site-specific evaluations should be completed to verify the design storm event determination and water balance model development
  • Confirm, through site reconnaissance, that conditions assumed in the hydrologic models are accurate to existing conditions
  • Refine the designs for stormwater diversions, sediment control structures, and other stormwater management features already in place.

The cost of HLF and stormwater management design work is estimated to be $0.5 million during the FS.

23.7 ENVIRONMENTAL

Further environmental investigations are recommended to advance the permitting process and provide essential data for design work. The scope of these environmental tasks is diverse, and the following activities are advised:

  • Refine numerical groundwater model incorporating the MacArthur Pit based on data from new groundwater monitoring boreholes and long-term pumping tests
  • Advance the geochemical characterization program, including sample collection and static testing. Conduct humidity cell tests and quarterly groundwater sampling to determine MacArthur Pit Lake water quality
  • Further assess existing Yerington Pit Lake water quality data against anticipated standards that would be included in an NPDES for discharge in the Walker River. In the feasibility stage, the need to actively manage the pit lake chemistry in recovery should also be evaluated

 
  • Schedule pre-application meetings with Federal (i.e., BLM) and State agencies (i.e., BMRR, BWPC, and BCA) to introduce the PFS-level Project and associated proposed development plans
  • Develop a stakeholder engagement strategy to discharge treated pit lake water on land for irrigation and/or in the WRID system with major irrigators and the WRID

23.8 FEASIBILITY STUDY

A consortium of qualified firms, each specialized in their respective fields, will be engaged to carry out the typical design activities for an FS. The typical expenses for the FS study encompass their fees, site visits, and collaborative design efforts. The management of these teams is also included in the customary costs of an FS.

The overall estimated expenditure, covering the various groups and associated expenses linked to the FS, is estimated to be $9.9M.


 

24.0 REFERENCES

24.1 PROCESS, INFRASTRUCTURE

Gantumur, Natska, 2012a: Metallurgical Study on Anaconda Vat Leach Tailings (Dry Sonic Drilling Samples). Prepared by Metcon Research, Tucson, Az. 144p.

Gantumur, Natska, 2012b: Metallurgical Study on Anaconda Vat Leach Tailings. Prepared by Metcon Research, Tucson, Az. 296p.

Johnson, David Barrie et al., 2023: Biomining Technologies, Extracting and Recovering Metals from Ore and Wastes. 177-190 p.

J. M. Ekenes C. A. Caro Improving Leaching Recovery of Copper from Low-Grade Chalcopyrite Ores. Society for Mining, Metallurgy & Exploration, 2015.

J. O. Marsden M. M. Botz Heap Leach Modeling - A Review of Approaches to Metal Production Forecasting. Society for Mining, Metallurgy & Exploration, 2017.

Nuton, 2024.  Lion CG Phase 1 Column Test Results Report & Presentation

Nuton, 2024.  Lion CG Phase 1 Hydrodynamic - Stacking Tests Summary.

Nuton, 2024.  Lion CG Phase 2 Hydrodynamic - Stacking Tests Summary.

Nuton, 2025.  Lion CG Phase 2 Column Test Results Interim Report & Presentation

Nuton, 2025.  Lion CG Phase 2 - Copper Model Prediction PFS Study

Water Tectonics, 2024. Lion CG Water Treatment 2024 Evaluation Report

Piteau Associates, 2025. Yerington Project Prefeasibility Hydrogeology Assessment.

24.2 GEOLOGY AND MINE

AGP Mining Consultants inc., 2024: Preliminary Economic Assessment of the Yerington Copper Project, Yerington, Nevada. NI 43-101 Technical Report prepared for Lion Copper and Gold Corp.

Anaconda Collection - American Heritage Center, University of Wyoming, Laramie, Wyoming.

Bonsall, T., 2012a: South Dump Report. Internal Memo. Prepared for Singatse Peak Services, LLC. 19 p.

Bonsall, T., 2012b: Tetratech - SPS Meeting Notes, August 1, 2012.

Bryan, Rex. C., 2012: NI 43-101 Technical Report, Mineral Resource. Yerington Copper Project, Lyon Count, Nevada. Prepared by Tetra Tech Inc. for Singatse Peak Services, LLC. 152 p.


 

Bryan, Rex C., 2014: NI 43-101 Technical Report, Mineral Resource Update. Yerington Copper Project, Lyon Count, Nevada. Prepared by Tetra Tech Inc. for Singatse Peak Services, LLC. 118 p.

Carten, Richard B., 1986: Sodium-Calcium Metasomatism: Chemical, Temporal, and Spatial Relationships at the Yerington Nevada Porphyry Copper Deposit: Economic Geology, Vol 81, pp. 1495-1519.

Dilles, J.H. and Proffett, J.M., 1995: Porphyry Copper Deposits of the American Cordillera: Arizona Geological Society Digest 20, p.306-315.

EDCON-PRJ, Inc., 2008: Acquisition and Processing of a Detailed Aeromagnetic Survey, Yerington Project. Prepared for Quaterra Alaska Inc. 12 p

Einaudi M.T, 1970: Final Report Deep Drilling Project Yerington Mine: unpublished private report for The Anaconda Company, 9p.

Gantumur, Natska, 2012a: Metallurgical Study on Anaconda Vat Leach Tailings (Dry Sonic Drilling Samples). Prepared by METCON Research, Tucson, Az. 144p.

Gantumur, Natska, 2012b: Metallurgical Study on Anaconda Vat Leach Tailings. Prepared by METCON Research, Tucson, Az. 296p.

Hart, V. A., 1915: Report Montana-Yerington Prospect and Adjoining Properties near Yerington, Nevada: unpublished private report for International Smelting Company: Anaconda Collection - American Heritage Center, University of Wyoming, 11p.

Howard, Jr., K. L., 1979: Geological Reserves - Yerington District: unpublished private report for The Anaconda Company: Anaconda Collection - American Heritage Center, University of Wyoming, 4p.

Hudbay Minerals Incl, 2023: Hudbay Provides Annual Reserve and Resource Update. News Release 2023 No. 3.

Independent Mining Consultants, Inc., 2022: MacArthur Copper Project, Mason Valley, Nevada, USA. NI 43-101 Technical Report, Mineral Resource Estimate.

Knopf, Adolph, 1918: Geology and ore deposits of the Yerington district, Nevada: U.S. Geol. Survey Professional Paper 114, 68p.

Koehler, Henry, 2008: Unpublished private letter from Anaconda Chief Chemist. Yerington, NV.

Lion Copper & Gold Corp., 2024: Lion Copper and Gold Announces Yerington Bear Deposit Diamond Drill Results. News Release, August 21, 2024. http://www.lioncg.com

MacLeod, I. N., Ellis, R. G., 2013: Magnetic Vector Inversion, a simple approach to the challenge of varying direction of rock magnetization; ASEG Forum on the Application of Remanent Magnetization, 2013 ASEG general meeting.


 

McClelland Laboratories: Column Leach Testing-MacArthur Project Drill Core Composites: August 31, 2023: McClelland Laboratories Inc.: Report on Column Leach Testing - MacArthur Drill Core Composites MLI Job No 4735, August 31, 2023.

METCON Research, Dec. 2011a: Column Leach Study on Anaconda Vat Leach Tailins. Prepared for Singatse Peak Services LLC. Prepared by METCON Research, Tucson, AZ. 127 p.

METCON Research, Dec. 2011b: MacArthur Project Preliminary Column Leach Study Report (Volumes I, II 7 III), Prepared by METCON Research, Tucson, AZ.

METCON Research, July 2012: Ceritificate of Analysis. Metcon Project Number M916-01A.

Moore, James G., 1969: Geology and Mineral Deposits of Lyon, Douglas, and Ormsby Counties, Nevada: Nevada Bureau of Mines and Geology, Bulletin 75, 45p.

Nelson, P.H. and Van Voorhis, G.D., 1983: Estimation of sulfide content from induced polarization data, GEOPHYSICS, V.48, No. 1, pp. 62-75.

Nesbitt, M., 1971: Unpublished private report, The Anaconda Company.

Nevada Administrative Code (NAC), 2022. Chapter 445A - Water Controls. Revised Date: 5-22.

Nevada Copper Corp., 2019: Pumpkin Hollow Project, Open Pit and Underground Mine Prefeasibility Study, Nevada U.S.A.

Nuton Update November 2023: Charles Abbey, internal email Nov. 27, 2023: 231121 Lion CG Columns Dashboard.xlsx Spread Sheet, Prepared by Nuton.

Proffett, Jr., J. M., and Dilles, J. H., 1984: Geologic Map of the Yerington District, Nevada: Nevada Bureau of Mines and Geology, Map 77.

Proffett, J.M. and Proffett, B.H., 1976: Stratigraphy of the Tertiary Ash-Flow Tuffs in the Yerington District, Nevada: Nevada Bureau of Mines and Geology, Report 27.

Sales, Reno H., 1915: Report on the Montana Yerington mine, Yerington, Nevada: unpublished private report for Anaconda Copper Mining Company: Anaconda Collection - American Heritage Center, University of Wyoming, 7p.

Sawyer, Joe, 2011: Arimetco Production history summary: private report. Prepared by Nevada Division of Environmental Production. 7p.

Schmidt, R., 1996: Copper Mineralogy of Four Samples: Hazen Research, Inc.: unpublished private report for Arimetco, Inc., 10p.

Souviron, Alavaro, 1976: Exploration Possibilities of the Yerington Mine, unpublished report, Anaconda Collection - American Heritage Center, University of Wyoming, 11p.


 

SRK Consulting (U.S.), Inc., 2005: Scoping Study to Evaluate the Processing of Leach Tailings & Low-Grade Ore Stockpile at the Yerington Mine, Lyon County, Nevada. Prepared for Atlantic Richfield Company. 48 p.

SRK Consulting (U.S.), Inc., 2012: Scoping Study for the Re-mining and Processing of Residual Ore Stockpiles and Tailings, Yerington Copper Mine, Lyon County, Nevada. Report prepared for Singatse Peak Services, LLC. 78 p.

Tingley, J.V., Horton, R.C., and Lincoln, F.C., 1993: Outline of Nevada Mining History: Nevada Bureau of Mines and Geology, Special Publication 15, 48p.

Turner, Tom, 2015:  McLeod Geology. Unpublished Memo - Word document.

USEPA, 2008: Public Review Draft, Remedial Investigation Report, Arimetco Facilities Operable Unit 8, Anaconda Copper Yerington Mine, pp. 170-172.

USEPA, 2010a: Data Summary Report for the Characterization of Vat Leach Tailings (VLT) Using X-Ray Fluorescence (XRF) - Yerington Mine Site. Prepared by Atlantic Richfield Company. 607 p.

USEPA, 2010b: Historical Summary Report - Anaconda-Yerington Mine Site - Yerington, NV. Prepared by CH2M Hill, Inc. 112 p.

USEPA, 2011a: Data Summary Report for the Characterization of Potential Cover Materials - Yerington Mine Site. Prepared by Atlantic Richfield Company. 48 p.

USEPA, 2011b: Supplemental Remedial Investigation Report, Arimetco Facilities Operable Unit 8, Anaconda Copper Yerington Mine, Yerington, NV.

USEPA, 2021: Final Combined Operable Units 4b, 5, and 6 Remedial Investigation Report - Anaconda PCopper Mine Site - Lyon County, Nevada. Prepared by Atlantic Richfield Company. 110 p.

Ware, G. H., 1979: In-situ induced-polarization and magnetic susceptibility measurements - Yerington mine, GEOPHYSICS, V. 44, No. 8, pp.1417-1428.

Wesnousky, S.G., 2005: The San Andreas and Walker Lane fault systems, western North America: transpression, transtension, cumulative slip and the structural evolution of a major transform plate boundary: Journal of Structural Geology, v. 27, no. 8, p. 1505-1512.

Wood Environmental & Infrastructure Solutions, Inc., 2020: Operable Unit 8 Peripheral Areas Remedial Investigation, Risk Characterization, and Feasibility Study. Anaconda Copper Mine Site, Lyon County, NV. Prepared for Atlantic Richfield Company. 108 p.

WSP, 2023: Heap Regrading and Capping Record of Construction Summary Report ROD 1/1A, Anaconda Copper Mine Site, Lyon County, Nevada. Prepared for Atlantic Richfield Company. May 10, 2023.

Zonge International Inc., 2017: Induced Polarization Survey, YMD IP Project. Lyon County, Nevada. Prepared for Singatse Peak Services, LLC. 55p


 

24.3 HLF

NDEP-BMRR (2021). Stability Requirements for Heap Leach Pads.

Bonnin, Geoffrey M., et. al. (2011). "NOAA Atlas 14 Precipitation-Frequency Atlas of the United States, Volume 1 Version 5.0: Semiarid Southwest (Arizona, Southeast California, Nevada, New Mexico, Utah)." Revised 2011. https://hdsc.nws.noaa.gov/pfds/pfds_map_cont.html?bkmrk=nv

NDEP-BMRR (2021). Stability Requirements for Heap Leach Pads.

Nevada Administrative Code (2023). Chapter 445A - Water Controls. https://www.leg.state.nv.us/NAC/nac-534.html, accessed June 9, 2025.

Proffett, J.M. and Dilles, J.H., (1984). Geologic Map of the Yerington District, Nevada Bureau of Mines and Geology, Map 77, Scale 1:24,000. 

United States Department of Commerce, National Oceanic and Atmospheric Administration (2011). "NOAA Atlas 14 Precipitation-Frequency Atlas of the United States Volume 1 Version 5.0" https://hdsc.nws.noaa.gov/pfds/pfds_map_cont.html?bkmrk=nv

24.4 ENVIRONMENTAL

Bureau of Land Management (BLM), 2013. Rock Characterization Resources and Water Analysis Guidance for Mining Activities.

Johnson, Frank W., 1989. A Cultural Resources Survey of Approximately 800 acres at the MacArthur Project in Lyon County, Nevada. April. To: Doug Stiles, VP, Sustainability & Environment, Lion Copper and Gold Corp. (Lion CG). November 25, 2024.

Nevada Division of Environmental Protection (NDEP) Bureau of Corrective Actions (BCA), 2025. Official Schedule Estimate, Anaconda Copper Mine Site, Atlantic Richfield Company Deliverables, and Nevada Division of Environmental Protection Responsibilities. January 2025

Nevada Division of Environmental Protection (NDEP) Bureau of Mining Regulation and Reclamation (BMRR), 2020. Guidance Document Pit Lake Water Quality Characterization Program NDEP Profile III. https://ndep.nv.gov/uploads/land-mining-regs-guidance-docs/20210824_GuidanceDoc_PitLakeSamplg_Profile3_ADA.pdf accessed on 05/20/2025.

____, 2021. Table of Profile I Constituents. https://ndep.nv.gov/uploads/land-mining-regs-guidance-docs/20210830_NDEP_Profile1_List_ADA.pdf.

____, 2025. Guidance Document Waste Rock, Overburden, and Ore Characterization and Evaluation. 6 January 2025.

Piteau Associates (Piteau), 2025. Yerington Prefeasibility Hydrogeology Assessment. May.


 

Wildlife Resource Consultants LLC (WRC), 2022. MacArthur Project 2022 Golden Eagle and Raptor Nesting Survey.

____, 2023. MacArthur Project 2023 Golden Eagle and Raptor Nesting Survey. October 17, 2023.

____, 2024. Yerington Copper Project 2024 Golden Eagle and Raptor Nesting Survey. July 2, 2024.


 

25.0 RELIANCE ON INFORMATION PROVIDED BY THE REGISTRANT

This report section has been prepared for Lion CG by the respective QPs referred to in Table 2.1. The information, conclusions, opinions, and estimates contained herein are based on:

  • Information available to the QPs at the time of preparation of this report.
  • Assumptions, conditions, and qualifications as set forth in this report.
  • Data, reports, and other information supplied by Lion CG.

For this report, the QPs have relied on property ownership information provided by Lion CG.  Samuel Engineering has not independently researched property title or mineral rights for the Yerington property and expresses no independent opinion as to the ownership status of the property.

Metal pricing assumptions are derived from information provided by S&P Global and Intratec.

Lion CG has provided the basis of the calculations for all associated royalties and taxes.

A draft copy of the Report has been reviewed for factual errors by Lion CG. Any representations, statements and opinions expressed in this document are given in good faith and in the belief that such statements and opinions are not false or misleading at the date of this Report.


 

26.0 APPENDICES

26.1 APPENDIX A - UNITS OF MEASURE AND ABBREVIATIONS AND ACRONYMS

26.1.1 Units of Measure

Table 26.1: Units of Measure
Above Mean Sea Level - amsl
Ampere - A
Amperes per Square Meter - ASM
Annum (Year) - a
Argentine Peso - AR$
Billion - B
British Thermal Unit - BTU
Centimeter - cm
Cubic Centimeter - cm3
Cubic Feet Per Minute - cfm
Cubic Feet Per Second - ft3/s
Cubic Foot - ft3
Cubic Inch - in3
Cubic Meter - m3
Cubic Yard - yd3
Coefficients Of Variation - CVs
Day - d
Days Per Week - d/wk
Days Per Year (Annum) - d/a
Dead Weight Tonnes - DWT
Decibel Adjusted - dBa
Decibel - dB
Degree - °
Degrees Celsius - °C
Diameter - ø
Dollar (American) - US$
Dollar (Canadian) - CDN$
Dry Metric Ton - dmt
Foot - ft
Gallon (US) - gal
Gallons Per Minute (US) - gpm
Gigajoule - GJ
Gigapascal - GPa
Gigawatt - GW
Gram - g
Grams Per Litre - g/L


 

Table 26.1: Units of Measure
Grams Per Tonne - g/t
Greater Than - >
Hectare (10,000 M2) - ha
Hertz - Hz
Horsepower - hp
Hour - h
Hours Per Day - h/d
Hours Per Week - h/wk
Hours Per Year - h/a
Inch - in
Kilo (Thousand) - k
Kilogram - kg
Kilograms Per Cubic Meter - kg/m3
Kilograms Per Hour - kg/h
Kilograms Per Square Meter - kg/m2
Kilometer - km
Kilometers Per Hour - km/h
Kilopascal - kPa
Kiloton (1,000 Tonnes) - kt
Kilovolt - kV
Kilovolt-Ampere - kVA
Kilovolts - kV
Kilowatt - kW
Kilowatt Hour - kWh
Kilowatt Hours Per Tonne - kWh/t
Kilowatt Hours Per Year - kWh/a
Less Than - <
Liter - L
Liters Per Minute - L/m
Liters Per Second - L/s
Megabytes Per Second - Mb/s
Megapascal - MPa
Megavolt-Ampere - MVA
Megawatt - MW
Meter - m
Meters Above Sea Level - masl
Meters Per Minute - m/min
Meters Per Second - m/s
Micron - μm
Milligram - mg
Milligrams Per Liter - mg/L
Milliliter - mL


 

Table 26.1: Units of Measure
Millimeter - mm
Million - M
Million Bank Cubic Meters - Mbm3
Million Bank Cubic Meters Per Annum - Mbm3/a
Million Tonnes - Mt
Minute (Plane Angle) - '
Minute (Time) - min
Month - mo
Ounce - oz
Pascal - Pa
Centipoise (MPa·S) - cP
Parts Per Million - ppm
Parts Per Billion - ppb
Percent - %
Pound(S) - lb
Pounds Per Square Inch - psi
Revolutions Per Minute - rpm
Second (Plane Angle) - "
Second (Time) - s
Short Ton (2,000 Lb) - st
Short Tons Per Day - st/d
Short Tons Per Year - st/y
Specific Gravity - SG
Square Centimetre - cm2
Square Foot - ft2
Square Inch - in2
Square Kilometre - km2
Square Metre - m2
Three-Dimensional - 3D
Tonne (1,000 Kg) (Metric Ton) - t
Tonnes Per Day - t/d
Tonnes Per Hour - t/h
Tonnes per annum - t/a
Tonnes Seconds Per Hour Metre Cubed - ts/hm3
United States Dollar - USD
Volt - V
Week - wk
Weight/Weight - w/w
Wet Metric Ton - wmt
Year - yr


 

26.1.2 Abbreviations and Acronyms

Table 26.2: Abbreviations and Acronyms
Acid Generating - AG
Acid Rock Drainage - ARD
Alternating Current - AC
Ammonium Nitrate Fuel Oil - ANFO
Association for the Advancement of Cost Engineering - AACE
Andes Corporación Minera S.A. - ACMSA
Autogenous/Ball Mill/Crushing - ABC
Battle Mountain Gold - BMG
Bond Ball Mill Work Index - BWi
Inductively Coupled Plasma - ICP
Canadian Institute of Mining, Metallurgy and Petroleum - CIM
Certificate Of Approval - CofA
Close-Circuit Fully Autogenous Grinding Milling - FAC
Conceptual Closure and Rehabilitation Plan - CRP
Construction Quality Assurance - CQA
Direct Current - DC
Diorite (Pre-Mineral Pluton) - DIO / PMP
Enrichment Ratio - ER
Environmental Impact Assessment - EIA
Environmental Impact Review - EIR
Environment, Social & Government - ESG
Exploratory Data Analysis - EDA
Early Mineral Porphyry - EMP
Ground Engaging Tools - GET
Hydrothermal Breccia - HBX
Hypogene (Primary Zone) - HYP
Induced Polarization - IP
Internal Rate of Return - IRR
International Organization for Standardization - ISO
In-The-Hole - ITH
Inverse Distance-Weighted - ID
Inter Mineral Porphyry - IMP
Leach Zone - LIX
Lerchs-Grossman - LG
Life-Of-Mine - LOM
Load-Haul-Dump - LHD


 

Table 26.2: Abbreviations and Acronyms
Magmatic Hydrothermal Breccia - MAG HYD BX
Magneto Telluric - MT
Million Years Ago - Mya
Mine Block Intrusion - MBI
Minera Andes S.A. - MASA
Minimum Environmental Protection Standard Laws - MEPSL
Mount Isa Mines - MIM
Canadian National Instrument 43-101 - S-K 1300
Nearest Neighbor - NN
Net Acid Generating/Generation - NAG
Net Present Value - NPV
Net Smelter Return - NSR
New York Stock Exchange - NYSE
Ordinary Kriging - OK
Overburden Zone - OVB
Portable Infrared Spectrometer - Pima
Preliminary Economic Assessment - PEA
Primary Zone - PR
Qualified Persons - QP's
Quality Assurance - QA
Quality Control - QC
Relative Bulk Strength - RBS
Reverse Circulation - RC
Rock Quality Designation - RQD
Run-Of-Mine - ROM
Selective Mining Unit - SMU
Semi-Autogenous - SAG
Semi-Autogenous/Ball Mill/Crushing - SABC
SGS Lakefield Research Ltd. - SGS
Solitario Argentina S.A. - SASA
Specific Gravity - SG
Standard Reference Material - SRM
Supergene Zone - SS
Tailings Storage Facility - TSF
Toronto Stock Exchange - TSX
Unidirectional Solidification Texture - UST
United Nations Development Program - UNDP
Volcanics - VOLCS


 

Table 26.2: Abbreviations and Acronyms
Waste Rock Storage Facility - WRSF
World Meteorological Organization - WMO


FAQ

What does Lion Copper and Gold (LCGMF) announce about the Yerington Copper Project?

Lion Copper and Gold announces completion of an S‑K 1300-compliant Preliminary Feasibility Study for its wholly owned Yerington Copper Project in Nevada. The study delivers first reserve-based mine planning, economics, permitting framework, and infrastructure concepts for a 12‑year open‑pit, heap‑leach copper operation.

What mineral reserves does Lion Copper and Gold (LCGMF) report for Yerington?

The project contains Proven reserves of 225.6 million tons at 0.23% copper and Probable reserves of 281.0 million tons at 0.20% copper. In total, Yerington hosts 506.6 million tons grading 0.21% copper, split between oxide and sulfide material for heap‑leach extraction.

What are the key economic results of the Yerington Copper Project PFS for LCGMF?

The PFS shows a pre‑tax NPV at 7% of $975 million and IRR of 16.9%, and post‑tax NPV at 7% of $694 million with IRR of 14.6%. These results use a long‑term copper price assumption of $4.30 per pound over a 12‑year mine life.

How much copper production is planned at Lion Copper and Gold’s Yerington project?

The plan targets 1,443 million pounds of payable copper over the mine life, averaging about 120 million pounds per year. This production comes from 506.6 million tons of heap‑leach feed grading 0.21% copper, processed through oxide and sulfide leach circuits.

What are the capital and operating costs in the Yerington PFS for LCGMF?

Total initial and sustaining capital is estimated at approximately $1,731.7 million in Q1 2025 dollars. Life‑of‑mine operating costs are $1.92 per payable pound of copper, with all‑in sustaining costs of $2.67 per pound, including royalties payable under project agreements.

What mining and processing methods will Lion Copper and Gold use at Yerington?

The project uses open‑pit mining with an overall strip ratio of 0.32:1, feeding three heap‑leach facilities. Oxide material is leached using conventional technology, while sulfide material from Yerington uses Nuton™ technology, with solvent‑extraction and electrowinning circuits producing LME Grade A copper cathode.

What is the permitting and environmental approach for Lion Copper and Gold’s Yerington project?

Lion Copper and Gold plans a Mine Plan of Operations under BLM 43 CFR 3809 and Nevada regulations, alongside Water Pollution Control and reclamation permits. The company coordinates with ongoing remediation by Atlantic Richfield and expects 2.5–3.5 years for key federal and state approvals.

Filing Exhibits & Attachments

12 documents
Lion Copper & Gold Corp

OTC:LCGMF

LCGMF Rankings

LCGMF Latest News

LCGMF Latest SEC Filings

LCGMF Stock Data

57.66M
247.63M
Other Industrial Metals & Mining
Basic Materials
Link
United States
Yerington