NiSource battery deal payments expected at about $2.2B

GenCo’s expected $2.2 billion in payments is tied to an agreement conditioned on AGP Group executing construction and interconnection agreements by January 31, 2027.

(Neutral)

Sentiment and the balance of points

Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

Form Type
8-K

Rhea-AI Filing Summary

NiSource Inc., through subsidiary NiSource Generation Company LLC (GenCo), entered into a battery storage tolling agreement with Atlas Storage 1 LLC, an indirect subsidiary of AGP Capital Holdings Pte. Ltd. (AGP Group). AGP Group will develop, construct, own and operate a stand-alone battery system with 600 MWAC of capacity and 2,400 MWh of storage, interconnected to the Midcontinent Independent System Operator (MISO) transmission system.

GenCo will supply the electricity used to power the project and may direct its dispatch and receive the economic benefits of its available capacity, discharged energy and services. The delivery term is expected to be approximately twenty and a half years, beginning when the first phase reaches commercial operation, expected by December 1, 2027. GenCo’s aggregate storage payments to AGP Group are expected to be approximately $2.2 billion over the term, based on a fixed rate subject to adjustments and the project’s actual power capacity. The agreement is expected to be accounted for as a finance lease obligation. Its effectiveness is conditioned on AGP Group executing an engineering, procurement and construction contract and an interconnection agreement reasonably satisfactory to AGP Group by January 31, 2027. GenCo also has an exclusive and irrevocable option to purchase the project at specified intervals during and at the end of the delivery term.

Item 2.03 Creation of a Direct Financial Obligation or an Obligation under an Off-Balance Sheet Arrangement Financial
The company incurred a new significant debt or off-balance-sheet obligation.
Item 9.01 Financial Statements and Exhibits Exhibits
Financial statements, pro forma financial information, or exhibit attachments filed with this report.
Battery system capacity 600 MWAC Capacity of the stand-alone project
Energy storage 2,400 MWh Storage capacity of the stand-alone project
Aggregate storage payments Approximately $2.2 billion Expected over the delivery term
Delivery term Approximately twenty and a half years Expected term beginning on commercial operation of the first phase
Expected commercial operation December 1, 2027 Expected date for the first phase
Agreement condition deadline January 31, 2027 Deadline for AGP Group to execute the specified construction and interconnection agreements
Tolling Agreement technical
"Battery Storage System Tolling Agreement"
ancillary services technical
"energy storage services, ancillary services"
Ancillary services are the extra goods or services that support and complement a company’s main product or activity, like maintenance, testing, delivery, or billing. For investors they matter because these add-on offerings can create steady, often higher-margin revenue streams that diversify income and make a business less dependent on its core product — think of them like the accessories and service plans that keep a phone useful and also boost the seller’s profits.
finance lease obligation financial
"accounted for as a finance lease obligation"
commercial operation date technical
"commencing on the commercial operation date"
The commercial operation date (COD) is the day a facility, plant, or project begins regular, revenue-generating operations and is declared ready for routine use. For investors, COD is like a factory’s “opening day”: it signals when costs shift from construction to production, revenue and cash flow should start, and contractual triggers (loan repayments, warranties, tax treatment, and performance obligations) typically take effect, affecting valuation and risk.
interconnection agreement technical
"an interconnection agreement reasonably satisfactory to AGP Group"
A written contract that sets the technical, legal and financial rules for linking two networks or pieces of infrastructure so they can work together safely and reliably. Like a handshake plus a rulebook for plugging systems together, it spells out who pays for connection work, who is responsible for outages or upgrades, and how data or power will flow. Investors care because these agreements affect a company’s ability to sell services, meet regulations, control costs and avoid operational disruptions.

FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

How much will GenCo pay AGP Group under NiSource’s battery storage agreement?

GenCo’s aggregate storage payments are expected to be approximately $2.2 billion over the delivery term. Payments are based on a fixed rate, subject to certain adjustments, and the project’s actual power capacity.

Can NiSource buy the battery storage project?

GenCo has an exclusive and irrevocable option to purchase the project at specified intervals during and at the end of the delivery term.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google
Available on EDGAR Accepted by SEC EDGAR Learn about SEC filing dates
false 0001111711 0001111711 2026-10-15 2026-10-15
 
 

UNITED STATES

SECURITIES AND EXCHANGE COMMISSION

Washington, D.C. 20549

 

 

FORM 8-K

 

 

CURRENT REPORT

Pursuant To Section 13 OR 15(d)

of The Securities Exchange Act of 1934

Date of Report (Date of earliest event reported): October 15, 2026

 

 

NiSource Inc.

(Exact name of registrant as specified in its charter)

 

 

 

DE   001-16189   35-2108964

(State or other jurisdiction

of incorporation)

 

Commission

File Number

 

(I.R.S. Employer

Identification No.)

 

801 East 86th Avenue

Merrillville, IN

  46410
(Address of principal executive offices)   (Zip Code)

Registrant’s telephone number, including area code (614) 460-6000

 

 

Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions.

 

☐

Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)

 

☐

Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)

 

☐

Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2 (b))

 

☐

Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4 (c))

Securities registered pursuant to Section 12(b) of the Act:

 

Title of Each Class

 

Trading
Symbol(s)

 

Name of Each Exchange

on Which Registered

Common Stock, par value $0.01 per share   NI   NYSE

Indicate by check mark whether the registrant is an emerging growth company as defined in Rule 405 of the Securities Act of 1933 (§ 230.405 of this chapter) or Rule 12b-2 of the Securities Exchange Act of 1934 (§ 240.12b-2 of this chapter).

Emerging growth company ☐

If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act. ☐

 

 
 


Item 2.03.

Creation of a Direct Financial Obligation or an Obligation under an Off-Balance Sheet Arrangement of a Registrant

On October 15, 2026, NiSource Generation Company LLC (“GenCo”), a subsidiary of NiSource Inc. (the “Company”), entered into a Battery Storage System Tolling Agreement (the “Tolling Agreement”) with Atlas Storage 1 LLC, an indirect subsidiary of AGP Capital Holdings Pte. Ltd. (“AGP Group”), pursuant to which AGP Group will develop, construct, own, and operate a 600 MWAC / 2,400 MWh stand-alone battery energy storage system (the “Project”) interconnected to the electric transmission system operated by the Midcontinent Independent System Operator, Inc. (“MISO”). Under the Tolling Agreement, GenCo will supply, at its expense, the electricity used to power the Project and will have the right to instruct dispatch of the Project and receive the economic benefits of its available capacity, discharged energy, energy storage services, ancillary services and (if applicable) environmental attributes, including revenues generated from the sale of such products into the applicable MISO markets (the “Products”).

The delivery term under the Tolling Agreement is expected to be approximately twenty and a half years, commencing on the commercial operation date for the first phase of the Project (expected by December 1, 2027). In consideration for the Products, GenCo will pay AGP Group regular storage payments based on a fixed rate (subject to certain adjustments) and the Project’s actual power capacity. GenCo’s aggregate storage payments over the delivery term are expected to be approximately $2.2 billion. The Tolling Agreement is expected to be accounted for as a finance lease obligation under FASB ASC Topic 842. Effectiveness of the Tolling Agreement is conditioned upon AGP Group’s execution of a contract for the engineering, procurement, and construction of the Project and an interconnection agreement reasonably satisfactory to AGP Group, in each case by January 31, 2027. The Tolling Agreement also provides GenCo with an exclusive and irrevocable option to purchase the Project at specified intervals during and at the end of the delivery term.

Note regarding forward-looking statements

This Current Report on Form 8-K contains “forward-looking statements” within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended. These forward-looking statements include statements concerning AGP Group’s construction and operation of the Project, the anticipated capacity of the Project, interconnection of the Project to MISO’s transmission system, GenCo’s purchase of capacity, energy storage, discharging energy, ancillary services and environmental attributes available from the Project, the commencement of the delivery term of the Tolling Agreement and GenCo’s estimated aggregate storage payments over the delivery term. Investors and prospective investors should understand that many factors govern whether any forward-looking statement contained herein will be or can be realized. All forward-looking statements are based on assumptions that management believes to be reasonable; however, there can be no assurance that actual results will not differ materially. Factors that could cause actual results to differ materially from the projections, forecasts, estimates and expectations discussed in this Report include, but are not limited to, the receipt, timing and terms of required regulatory approval in connection with the Tolling Agreement and the ability to comply with any conditions associated with such regulatory approvals; the ability of key suppliers and contractors to timely satisfy their obligations to AGP Group under existing or future contracts and in compliance with the terms of such contracts; the impact of applicable tariffs, if any, and other economic factors; the impact of natural disasters or other severe weather events; AGP Group’s ability to perform its obligations under the Tolling Agreement, including construction of the Project on-time and effectively; the impact of public involvement, intervention or litigation with respect to these projects and other matters as set forth in Part I, Item 1A, “Risk Factors” and Part II, Item 7, “Management’s Discussion and Analysis of Financial Condition and Results of Operations” of our Annual Report on Form 10-K for the fiscal year ended December 31, 2025 and matters set forth in our subsequent Quarterly Reports on Form 10-Q, some of which are beyond our control.

All forward-looking statements are expressly qualified in their entirety by the foregoing cautionary statements. We undertake no obligation to, and expressly disclaim any such obligation to, update or revise any forward-looking statements to reflect changes in assumptions, the occurrence of anticipated or unanticipated events or changes to the future results over time or otherwise, except as required by law.

 


Item 9.01.

Financial Statements and Exhibits.

(d) Exhibits

 

Exhibit
Number
  

Description

104    Cover page Interactive Data File (embedded within the Inline XBRL document)

 


SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned hereunto duly authorized.

 

     

NiSource Inc.

      (Registrant)
Date: October 16, 2026     By:  

/s/ Shawn Anderson

      Shawn Anderson
      Executive Vice President and Chief Financial Officer