Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

Form Type
8-K

Rhea-AI Filing Summary

Net Power Inc. said its indirect subsidiary, Net Power, LLC, and Saulsbury Industries amended the extension agreement for their engineering, procurement and construction (EPC) project. The deadline to execute a post-closing change order and limited notice to proceed, and make the required payments, moved from November 20 to December 4, 2026; the $3.5 million termination payment remains deferred. The prospective customer approved the amendment and form of change order on November 20, subject to changes that do not increase requested amounts or make the documents materially less favorable to it.

Net Power has no binding energy services or power offtake agreement for the Initial Project, and the prospective customer is not obligated to enter one. The company says failure to execute the change order or limited notice to proceed on acceptable terms by December 4, make the required payments, or deliver the full notice to proceed and fund the mobilization payment by March 31, 2027 could result in the termination payment or termination of the EPC Agreement. The company also cites the absence of committed equipment or project-level financing, customer funding or partner capital other than the conditional Cost Reimbursement Agreement, and the absence of a final investment decision.

0 points · 0 major

How this balance works

Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.

It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.

Rhea-AI Sentiment measures something else, the tone of the wording.

0 major · 1 point

Hollow bars mark forward-looking points. How the balance works

Positive

  • None.

Negative

  • Moderate point. Forward-looking: it has not happened yet and may not happen.Missing the December 4, 2026 EPC deadline could risk a $3.5 million termination payment or termination. 1.7% of market cap
Item 1.01 Entry into a Material Definitive Agreement Business
The company signed a significant contract such as a merger agreement, credit facility, or major partnership.
Item 9.01 Financial Statements and Exhibits Exhibits
Financial statements, pro forma financial information, or exhibit attachments filed with this report.
Termination payment $3.5 million Remains deferred under the amended extension agreement; potential payment if stated conditions are not met.
Deadline for Fourth Amendment, LNTP and required payments December 4, 2026 Extended from November 20, 2026.
FNTP and mobilization payment milestone March 31, 2027 Date by which the company identifies delivery of the FNTP and funding of the mobilization payment as risk conditions.
limited notice to proceed technical
"a limited notice to proceed under the EPC Agreement"
A limited notice to proceed is a short, partial green light from a client that lets a contractor begin specific early work—such as site preparation, ordering long‑lead materials, or hiring crews—before the full contract is signed. For investors it signals that a project is moving from planning toward execution, which can accelerate revenue timing but also exposes the company to early costs and schedule risk if the full contract terms change; think of it as starting the foundation before the final building permit paperwork is complete.
Cost Reimbursement Agreement financial
"under the Company’s Cost Reimbursement Agreement with that customer"
A cost reimbursement agreement is a contract where one party agrees to pay back another for actual costs incurred while carrying out a project, study, or service. It spells out which expenses are eligible, how they must be documented, and any limits or timing for repayment. For investors, these agreements matter because they shift which party bears project costs and cash-flow risk, affecting expected expenses, funding needs, and the timing of reported results.
power offtake agreement technical
"a binding energy services or power offtake agreement"
FNTP technical
"deliver the FNTP and fund the mobilization payment"

FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

What is NPWR's new deadline for the EPC change order and limited notice to proceed?

The deadline is December 4, 2026, extended from November 20 for execution of the Fourth Amendment and LNTP and payment of amounts required under the LNTP.

What could happen if Net Power misses the new EPC deadline?

Failure to execute the Fourth Amendment or LNTP on acceptable terms by December 4, 2026, make the required LNTP payments, or deliver the FNTP and fund the mobilization payment by March 31, 2027 could lead to the $3.5 million termination payment or termination of the EPC Agreement.

Is NPWR's prospective customer committed to buying power from the Initial Project?

No. The prospective customer is not obligated to enter a binding energy services or power offtake agreement for the Initial Project, and Net Power says no such binding agreement has been entered.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google
false 0001845437 0001845437 2026-11-22 2026-11-22 0001845437 NPWR:ClassACommonStockparvalueMember 2026-11-22 2026-11-22 0001845437 NPWR:WarrantseachexercisableMember 2026-11-22 2026-11-22 iso4217:USD xbrli:shares iso4217:USD xbrli:shares

 

 

 

UNITED STATES

SECURITIES AND EXCHANGE COMMISSION

Washington, D.C. 20549

 

 

 

FORM 8-K

 

CURRENT REPORT

Pursuant to Section 13 or 15(d) of the Securities Exchange Act of 1934

 

Date of report (Date of earliest event reported): November 22, 2026

 

 

 

NET POWER INC.

(Exact name of registrant as specified in its charter)

 

Delaware   001-40503   98-1580612
(State or other jurisdiction of
incorporation)
  (Commission File Number)   (IRS Employer Identification No.)

 

11700 Katy Freeway, Suite 700

Houston, Texas 77079

(Address of principal executive offices, including zip code)

 

(888) 323-6797

(Registrant’s telephone number, including area code)

 

Not Applicable

(Former name or former address, if changed since last report)

 

 

 

Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions:

 

¨ Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)

 

¨ Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)

 

¨ Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))

 

¨ Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))

 

Securities registered pursuant to Section 12(b) of the Act:

 

Title of each class Trading Symbol(s) Name of each exchange on which
registered
Class A Common Stock, par value $0.0001 per share NPWR The New York Stock Exchange
Warrants, each exercisable for one share of Class A Common Stock at a price of $11.50 per share NPWR-WT The New York Stock Exchange

 

Indicate by check mark whether the registrant is an emerging growth company as defined in Rule 405 of the Securities Act of 1933 (§ 230.405 of this chapter) or Rule 12b-2 of the Securities Exchange Act of 1934 (§ 240.12b-2 of this chapter).

 

Emerging growth company x

 

If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act. ¨

 

 

 

 

 

Item 1.01 Entry into a Material Definitive Agreement.

 

As previously disclosed, on August 31, 2026, Net Power, LLC (the “Purchaser”), an indirect subsidiary of NET Power Inc. (the “Company”), acquired the position of EMPower USA, LLC as “Owner” under the Engineering, Procurement and Construction Agreement dated December 15, 2025 with Saulsbury Industries, Inc. (“Saulsbury”) (as amended, the “EPC Agreement”). The Purchaser and Saulsbury are negotiating a post-closing change order to the EPC Agreement (the “Fourth Amendment”) and a limited notice to proceed under the EPC Agreement (the “LNTP”).

 

On November 20, 2026, the prospective customer under the Company’s cost reimbursement agreement with that customer (the “Cost Reimbursement Agreement”) approved Amendment No. 2 (as defined below) and the form of Fourth Amendment, subject to changes that do not increase the requested amounts or make the documents materially less favorable to the prospective customer.

 

On November 22, 2026, the Purchaser and Saulsbury entered into Amendment No. 2 to Agreement to Extend FNTP Date (“Amendment No. 2”), which amends the Agreement to Extend FNTP Date effective as of October 15, 2026, as previously amended (the “Extension Agreement”). Amendment No. 2 extends from November 20, 2026 to December 4, 2026 the date by which the Fourth Amendment and the LNTP must be executed, and the payments required under the LNTP made, for the $3.5 million termination payment under the Extension Agreement (the “Termination Payment”) to remain deferred.

 

In Amendment No. 2, Saulsbury confirmed that it has not demanded the Termination Payment, that the Termination Payment is not payable, and that it remains deferred under the Extension Agreement as amended by Amendment No. 2. Except for replacing the applicable November 20, 2026 references with December 4, 2026, the Extension Agreement is unchanged.

 

The Company has not entered into a binding energy services or power offtake agreement for the Initial Project, and the prospective customer is not obligated to enter into one.

 

Other than under the EPC Agreement, the Consent to Assignment and Acknowledgment dated as of August 27, 2026, the Extension Agreement, Amendment No. 2 and the other agreements described in the Company’s prior disclosure and the transactions contemplated by them, the foregoing description of Amendment No. 2 does not purport to be complete and is qualified in its entirety by reference to the full text of Amendment No. 2, which the Company intends to file as an exhibit to its Annual Report on Form 10-K.

 

Item 9.01 Financial Statements and Exhibits.

 

(d) Exhibits.

 

Exhibit No.   Description
104   Cover Page Interactive Data File (embedded within the Inline XBRL document).

 

Page 2 of 4

 

 

Cautionary Note Regarding Forward-Looking Statements

 

This Current Report on Form 8-K contains forward-looking statements within the meaning of the federal securities laws. Forward-looking statements include all statements that are not historical facts, including statements regarding the negotiation, execution and terms of the Fourth Amendment and the LNTP, the timing and amount of payments under the LNTP, the delivery of the FNTP and the funding of the mobilization payment, the payment or further deferral of the Termination Payment, the prospective customer’s approvals and other actions under the Cost Reimbursement Agreement, the execution of a binding energy services or power offtake agreement, and the development, financing, permitting and timing of the Company’s Initial Project.

 

Forward-looking statements are based on management’s current expectations and assumptions and are subject to risks, uncertainties and changes in circumstances that are difficult to predict and many of which are outside the Company’s control. These risks include the failure to execute the Fourth Amendment or the LNTP on acceptable terms by December 4, 2026 or at all, to make the payments required under the LNTP, or to deliver the FNTP and fund the mobilization payment by March 31, 2027; the resulting potential payment of the Termination Payment or termination of the EPC Agreement; the Company’s ability to fund its commitments and recover amounts paid toward the Wärtsilä equipment; the absence of any committed equipment or project-level financing, customer funding or partner capital other than the conditional Cost Reimbursement Agreement; the absence of a final investment decision; risks related to permitting, site control and large-load development in Texas; and the risks described in the Company’s filings with the Securities and Exchange Commission.

 

Forward-looking statements speak only as of the date of this report. The Company undertakes no obligation to update or revise any forward-looking statement, whether as a result of new information, future events or otherwise, except as required by law.

 

Page 3 of 4

 

 

SIGNATURE

 

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned hereunto duly authorized.

 

Dated: November 23, 2026 NET POWER INC.
     
  By: /s/ Daniel J. Rice IV
  Name: Daniel J. Rice IV
  Title: Chief Executive Officer

 