Allied Gold Advances Wet Commissioning at Kurmuk as Plant Nears First Gold
Allied expects Kurmuk to reach commercial production during November and December, with output increasing through the ramp-up.
Sentiment and the balance of points
Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.
Rhea-AI Summary
Allied Gold (AAUC) has begun wet commissioning at its Kurmuk Mine in Ethiopia as the processing plant approaches first gold production. The crushing circuit is operating, supporting infrastructure is complete, and mill testing is nearing completion. The company expects ore feed this week, with first gold targeted soon thereafter.
Allied expects 25,000 to 35,000 gold ounces during November and December, with commercial production expected in that period. Q1 2027 production is expected at 55,000 to 65,000 gold ounces; 2027 guidance remains 240,000 to 270,000 gold ounces. The 2028 outlook is approximately 300,000 gold ounces. An agreement with local stakeholders, including artisanal miners, enables cooperative exploration into new prospective areas.
How this balance works
Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.
It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.
Rhea-AI Sentiment measures something else, the tone of the wording.
Hollow bars mark forward-looking points. How the balance works
Positive
- Moderate pointKurmuk wet commissioning has begun, with mill drives energized and testing and commissioning nearing completion.
- Moderate point. Forward-looking: it has not happened yet and may not happen.Ore feed is expected this week, with first gold targeted soon thereafter.
- Moderate point. Forward-looking: it has not happened yet and may not happen.25,000 to 35,000 gold ounces expected during November and December, with commercial production expected during this period.
- Moderate point. Forward-looking: it has not happened yet and may not happen.Q1 2027 production of 55,000 to 65,000 gold ounces expected, increasing sequentially month over month.
- Moderate point. Forward-looking: it has not happened yet and may not happen.2027 production guidance remains 240,000 to 270,000 gold ounces.
- Moderate point. Forward-looking: it has not happened yet and may not happen.2028 production outlook is approximately 300,000 gold ounces.
5 minor points
- Minor pointCrushing circuit is operating; mine and plant infrastructure, including water and tailings storage facilities, is complete.
- Minor point. Forward-looking: it has not happened yet and may not happen.First four full years expected to average approximately 300,000 gold ounces annually.
- Minor pointOre stockpiles are close to the planned approximately three months of plant feed; mining grades match expectations.
- Minor point. Forward-looking: it has not happened yet and may not happen.Exploration at Ashashire, Dish Mountain and the Tsenge Trend advances the objective of sustaining production beyond four years.
- Minor pointLocal stakeholder agreement enables cooperative exploration into new prospective areas, supporting mineral inventory and mine-life objectives.
Negative
- None.
News Explained
Ahead of the
Key Figures
- Ramp-up production
- 25,000–35,000 gold ounces
- November and December
- Quarterly production
- 55,000–65,000 gold ounces
- Q1 2027
- Production guidance
- 240,000–270,000 gold ounces
- 2027; guidance remains in this range
- Production outlook
- Approximately 300,000 gold ounces
- 2028
Historical Context
-
Reported resource growth potential as Kurmuk commissioning advanced; first ore and first gold were expected.
-
Power line energized and first ore fed through crushing before grinding-circuit feed and first gold.
24h Move is the share-price change in the day after each event; other market factors may also have contributed.
Key Terms
wet commissioning technical
sag mill technical
tailings storage facility technical
national instrument 43-101 regulatory
AI-generated analysis. How Rhea-AI works. Not financial advice.
TORONTO, Oct. 29, 2026 (GLOBE NEWSWIRE) -- Allied Gold Corporation (TSX: AAUC; NYSE: AAUC) (“Allied” or the “Company”) is pleased to provide an update on its Kurmuk Mine in Ethiopia as it advances toward production startup. The Kurmuk Mine is a cornerstone of Allied’s production and cash flow growth, delivering a significant increase in production at attractive operating costs while enhancing the scale, quality and longevity of the Company’s portfolio.
- Mining and stockpiles on plan. Mining continues to progress well, with mining grades in line with expectations. Ore stockpiles are close to the planned level of approximately three months of plant feed ahead of the November ramp-up.
- Crushing and supporting infrastructure complete. The crushing circuit is operating well, and the crushed ore stockpile continues to build, providing operational flexibility for a smooth ramp-up. Process support systems and infrastructure are complete.
- Wet commissioning underway. Water transfer from the main water storage dam into the processing plant has commenced, allowing the processing circuits to be progressively wet-commissioned and tested ahead of ore feed. SAG mill and ball mill drives are energized, with testing and commissioning nearing completion.
- Ore feed and first gold. Ore is expected to be introduced into the circuit this week with first gold targeted soon thereafter. Mine and plant infrastructure is complete including the water storage facility, tailings storage facility, main access road and mining service areas, among others, supporting readiness for production ramp-up toward commercial production this year and strong first quarter and full year production next year.
- Ramp-up production outlook. Production is expected to increase through November and December, with total production of between 25,000 to 35,000 gold ounces and commercial production expected during this period. Production in Q1 2027 is expected to increase sequentially month over month, with quarterly production of 55,000 to 65,000 gold ounces and a monthly average production of approximately 20,000 gold ounces.
- Production outlook. Production guidance for 2027 remains in the range of 240,000 to 270,000 gold ounces, with the production outlook of approximately 300,000 gold ounces in 2028. For the first four full years of operations, average annual production is expected to be approximately 300,000 gold ounces.
- Exploration advancing toward a longer production profile. Recent exploration results at Ashashire, Dish Mountain and the Tsenge Trend, reported on October 6, 2026, continue to advance the objective of sustaining average annual production of approximately 300,000 gold ounces beyond the initial first four years of operations, as well as increasing mine life and overall mineral inventory.
- Agreement with local stakeholders. The Company has reached an agreement with local stakeholders, including artisanal miners active in certain parts of the exploration licences, to advance exploration cooperatively into new prospective areas while supporting local communities. This agreement is expected to drive the advancement of new targets across the broader Kurmuk property and contribute to the Company's longer-term objectives for mineral inventory growth and mine life extension. Together, the ongoing exploration program within the mining licence area and expanded access to prospective areas support Allied's objective of establishing Kurmuk as a long-life gold mining operation with strong, sustained annual production at attractive operating costs.
Photographs of the Kurmuk Mine
Click the links below to view photographs of the Kurmuk Mine.
Photo 1 — Crushed ore stockpile
Photo 2 — Main ROM pad
Photo 3 — Process plant commissioning
Photo 4 — Process plant commissioning
Third Quarter 2026 Financial Results
Allied expects to release its third quarter 2026 financial and operating results after market close on Wednesday, November 4, 2026. The Company will host a conference call and webcast to discuss the results on Thursday, November 5, 2026, at 9:00 a.m. ET.
Third Quarter 2026 Conference Call
| Toll-free dial-in number (Canada/US): | 1-800-715-9871 |
| Toll-free dial-in number (UK): | +44-800-260-6466 |
| Participant passcode: | 7077347 |
| Webcast: | https://alliedgold.com/investors/presentations/ |
The webcast replay will be available shortly after the call ends.
Qualified Person
Except as otherwise disclosed, all scientific and technical information contained in this press release has been reviewed and approved by Sébastien Bernier, P.Geo (Senior Vice President, Technical Services), a Qualified Person as defined by National Instrument 43-101. Exploration information referred to in this press release was previously reported on October 6, 2026, and was reviewed and approved by Don Dudek, P.Geo, Chief Exploration Officer, a Qualified Person as defined by National Instrument 43-101.
About Allied Gold Corporation
Allied Gold is a Canadian-based gold producer with a significant growth profile and mineral endowment which operates a portfolio of three producing assets and development projects located in Côte d’Ivoire, Mali, and Ethiopia. Led by a team of mining executives with operational and development experience and proven success in creating value, Allied Gold aspires to become a next-generation mid-tier gold producer in Africa and ultimately a leading senior global gold producer.
For further information, please contact:
Allied Gold Corporation
Royal Bank Plaza, North Tower
200 Bay Street, Suite 2200
Toronto, Ontario M5J 2J3 Canada
Email: ir@alliedgold.com
CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION AND STATEMENTS
This press release contains “forward-looking information” under applicable Canadian securities legislation. Forward-looking statements are characterized by words such as “plan”, “expect”, “target” and other similar words. Except for statements of historical fact, information contained herein constitutes forward-looking information, including, but not limited to, statements related to the sequence, timing and completion of wet commissioning and other remaining commissioning activities; the timing of ore feed and first gold; ore stockpile levels and mining performance; the ramp-up profile; Kurmuk’s production outlook and guidance for 2026, the first quarter of 2027, 2027 and 2028, and average annual production over the first four years and the life of the mine; the advancement of exploration, the agreement with local stakeholders, and the objectives of sustaining production and extending mine life; expected industry-leading cost performance; the generation of cash flow, profitability and shareholder returns; and the Company’s growth and shareholder-value objectives.
The material assumptions underlying these statements include timely completion of remaining commissioning activities; the availability of sufficient and reliable electrical power, water and other infrastructure to support commissioning and ramp-up; the availability of ore at planned grades and metallurgical characteristics; plant performance, availability and recovery consistent with the ramp-up plan and mine plan; continued cooperation with local stakeholders; the availability of personnel, contractors, equipment, consumables and funding; and no material adverse changes in commodity prices, exchange rates, costs, or the regulatory, security and operating environment. Actual results may differ materially if these assumptions are not met.
Forward-looking information is based on the opinions, assumptions and estimates of management considered reasonable at the date the statements are made, and is inherently subject to a variety of risks and uncertainties and other known and unknown factors that could cause actual events or results to differ materially from those projected in the forward-looking information. These factors include, without limitation, delays in completing remaining commissioning activities; delays or interruptions in power supply, including delays in the availability of sufficient grid power to support planned throughput during ramp-up; commissioning delays, equipment failures and an inability to sustain intended throughput or recovery; risks relating to artisanal mining and community relations; and risks and uncertainties related to the Company’s ability to meet its expansion and operational optimization goals, including production increases; risks relating to operating in emerging markets, particularly Africa, including risk of government expropriation or nationalization of mining operations; health, safety and environmental risks and hazards to which the Company’s operations are subject; counterparty, credit, liquidity and interest rate risks and access to financing; uncertainty in the estimation of Mineral Reserves and Mineral Resources; Allied’s ability to replace and expand Mineral Resources and Mineral Reserves; risks relating to partial ownerships and/or joint ventures at the Company’s operations; reliance on the Company’s existing infrastructure and supply chains at the Company’s operating mines; risks relating to the acquisition, holding and renewal of title to mining rights and permits, and changes to the mining legislative and regulatory regimes in the Company’s operating jurisdictions; the Company’s compliance with anti-corruption laws; title disputes or claims; risks relating to the termination of mining rights; risks relating to security and human rights; risks associated with processing and metallurgical recoveries; risks related to enforcing legal rights in foreign jurisdictions; risks related to the Company’s ability to service its debt obligations; fluctuating currency exchange rates (including the US Dollar, Euro, West African CFA Franc and Ethiopian Birr exchange rates); timing and possible outcome of pending and outstanding litigation and labour disputes; taxation risks; scrutiny from non-governmental organizations; labour and employment relations; repatriation of funds from foreign subsidiaries; the impact of global financial, economic and political conditions, global liquidity, interest rates, inflation and other factors on the Company’s results of operations and market price of the Company’s common shares; risks associated with financial projections; force majeure events; transactions that may result in dilution to common shares; future sales of common shares by existing shareholders; the Company’s dependence on key management personnel and executives; possible conflicts of interest of directors and officers of the Company; the reliability of the Company’s disclosure and internal controls; compliance with international ESG disclosure standards and best practices; vulnerability of information systems including cyber attacks; as well as those risk factors discussed or referred to in the Company’s current Annual Information Form and Form 40-F available under its profile on SEDAR+ at www.sedarplus.ca and www.sec.gov.
Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking information, there may be other factors that could cause actions, events or results to not be as anticipated, estimated or intended. There can be no assurance that forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. The Company undertakes no obligation to update forward-looking information if circumstances or management’s estimates, assumptions or opinions should change, except as required by applicable law. The reader is cautioned not to place undue reliance on forward-looking information. The forward-looking information contained herein is presented for the purpose of providing investors with information concerning the Company’s expectations and plans relating to its business and operations, and may not be appropriate for other purposes.
FAQ
AI-generated questions and answers. How Rhea-AI works. Not financial advice.
When does Allied Gold expect first gold and commercial production at Kurmuk?
Allied expects ore to enter the processing circuit this week, with first gold targeted soon thereafter and commercial production expected during November and December. Wet commissioning, which tests processing circuits with water before ore feed, is underway.
What is Allied Gold's Kurmuk production outlook for 2027 and 2028?
Kurmuk's 2027 production guidance remains 240,000 to 270,000 gold ounces, with approximately 300,000 gold ounces forecast for 2028. Allied expects Q1 2027 production of 55,000 to 65,000 gold ounces and average annual production of approximately 300,000 gold ounces over the first four full years of operations.
How much ore has Allied Gold stockpiled ahead of Kurmuk's ramp-up?
Ore stockpiles are close to the planned level of approximately three months of plant feed ahead of the November ramp-up. Mining grades are in line with expectations, and the crushed ore stockpile continues to build.