Applied Digital Achieves Initial 25 MW Ready for Service in Harwood, North Dakota, for Hyperscaler, Completes Base-Build Commissioning of First 75 MW

Sentiment and the balance of points

Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

Applied Digital (NASDAQ: APLD) achieved Ready for Service for its first 25 MW data hall at Polaris Forge 2 in Harwood, North Dakota. The company completed the hall’s fit-out and reached the milestone on schedule. It also completed testing and commissioning of the base infrastructure for the first 75 MW of the initial 150 MW building. The remaining 50 MW in that phase can now move into fit-out and customer delivery.

The building is fully leased under the customer’s 200 MW long-term lease at Polaris Forge 2. That lease contributes to Applied Digital’s portfolio of more than $41 billion in contracted base-term lease revenue. This is the first Ready for Service milestone at the company’s second campus, following delivery of 250 MW of operational critical IT load at Polaris Forge 1 in Ellendale, North Dakota.

Loading...
Loading translation...
4 points · 0 major

How this balance works

Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.

It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.

Rhea-AI Sentiment measures something else, the tone of the wording.

0 major · 1 point

Hollow bars mark forward-looking points. How the balance works

Positive

  • Moderate pointFirst 25 MW data hall at Polaris Forge 2 completed fit-out and reached Ready for Service on schedule
  • Moderate pointBase infrastructure for the first 75 MW of the initial 150 MW building was tested and commissioned
  • Moderate pointContracted base-term lease revenue exceeds $41 billion across the portfolio, including the Polaris Forge 2 lease
  • Minor pointInitial 150 MW building is fully leased under the customer’s 200 MW long-term lease at Polaris Forge 2

Negative

  • Minor point. Forward-looking: it has not happened yet and may not happen.Remaining 50 MW in the first phase still requires fit-out and customer delivery
Argus 15 min delay 184 alerts
-12.19% vs previous close $12.14 last price 1.8x rel. volume Open Argus
Details

Market Reaction – APLD

$11.67 – $13.45 Day Range
$3.67B Mkt Cap at Last Price

On Nov 24, the day this news came out, the latest delayed price for APLD is 12.19% below the previous close. Our momentum scanner has recorded 184 alerts for this stock so far that day. The latest delayed price is $12.14. Relative volume is above average at 1.8x what this stock usually trades by this time of day.

Data tracked by StockTitan Argus (15 min delayed). Upgrade to Gold for real-time data.

Key Figures

Ready for Service capacity: 25 MW Base-build commissioning: 75 MW Building capacity: 150 MW +3 more
Ready for Service capacity
25 MW
First data hall at Polaris Forge 2; achieved on schedule
Base-build commissioning
75 MW
First phase of the initial 150 MW building
Building capacity
150 MW
Initial Polaris Forge 2 data center building
Remaining phase capacity
50 MW
Can now advance through fit-out and customer delivery
Customer lease
200 MW
Long-term lease at Polaris Forge 2; building is fully leased
Contracted base-term lease revenue
More than $41 billion
Applied Digital portfolio

Historical Context

2 past events · Latest: Oct 02
2 events
  1. Oct 02

    AI capacity delivery

    24h Move
    +5.0%

    An additional 75 MW reached Ready for Service at Polaris Forge 1, bringing campus operational capacity to 250 MW.

  2. Oct 07

    Quarterly earnings

    24h Move
    +0.2%

    Reported approximately $36 billion in contracted base-term lease revenue alongside higher revenue and a wider net loss.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

On-schedule Polaris Forge 2 milestone establishes the foundation for the next 50 MW of customer deliveries, reinforcing repeatable execution against more than $41 billion in contracted base-term lease revenue

DALLAS, Nov. 24, 2026 (GLOBE NEWSWIRE) -- Applied Digital (NASDAQ: APLD), a U.S. based AI data center infrastructure company specializing in the design, development, ownership and operation of large-scale, purpose-built campuses serving hyperscale off-takers under long-term contracts, today announced it has completed base-build commissioning for the first 75 MW of its initial 150 MW data center building at Polaris Forge 2 in Harwood, North Dakota. Within this phase, the Company has completed the integrated fit-out of the first 25 MW data hall and achieved Ready for Service on schedule.

The milestone marks the first Ready for Service achievement at Applied Digital’s second AI Factory campus, following the delivery of 250 MW operational critical IT load at Polaris Forge 1 in Ellendale, North Dakota. With the base-build infrastructure for the full 75 MW phase successfully tested and commissioned, the remaining 50 MW can now advance through fit-out and customer delivery.

“AI infrastructure demand is not theoretical for us. It’s backed by long-term customer commitments, and our focus is on delivering against them,” said Wes Cummins, Chairman and Chief Executive Officer of Applied Digital. “With our second campus now reaching Ready for Service on schedule, we’re demonstrating that our execution model is repeatable. The ability to consistently turn contracted demand into delivered AI capacity is what will define the leaders in this industry, and that’s exactly what we’re doing at Applied Digital.”

The building is fully leased as part of the customer’s 200 MW long-term lease at Polaris Forge 2, contributing to Applied Digital’s portfolio of more than $41 billion in contracted base-term lease revenue. Each 150 MW building at the AI Factory Campus is commissioned in two 75 MW phases, with three 25 MW data halls tested and commissioned together during each phase.

This achievement underscores Applied Digital’s ability to execute against contracted hyperscaler demand, applying consistent engineering standards, construction processes and operational expertise to deliver purpose-built AI infrastructure across multiple campuses.

About Applied Digital

Applied Digital (Nasdaq: APLD) is a U.S. based AI infrastructure company specializing in the design, development, ownership and operation of large-scale, purpose-built AI data center campuses. 

Combining the fundamentals of technical real estate with the specialized requirements of digital infrastructure, the Company provides the mission-critical power, advanced liquid cooling and connectivity required to support artificial intelligence and high-performance computing workloads. Applied Digital’s AI Factory campuses are leased to hyperscale customers under long-term contracts, combining specialized infrastructure assets with predictable, long-term revenue streams.

Through its repeatable approach to design, development and operations, Applied Digital delivers highly engineered infrastructure designed to support the demanding requirements of AI computing at scale. 

Learn more at applieddigital.com or follow @APLDdigital on X and LinkedIn.

Forward-Looking Statements
This press release contains “forward-looking statements” as defined in the Private Securities Litigation Reform Act of 1995 regarding, among other things, future operating and financial performance, product development, market position, business strategy and objectives, and future financing plans. These statements use words, and variations of words, such as “will,” “continue,” “build,” “future,” “increase,” “drive,” “believe,” “look,” “ahead,” “confident,” “proven,” “deliver,” “outlook,” “expect,” “project” and “predict.” Other examples of forward-looking statements may include, but are not limited to, (i) statements that reflect perspectives and expectations regarding lease agreements and any current or prospective data center campus development; (ii) statements about the high-performance computing (HPC) industry; (iii) statements of company plans and objectives, including the company’s evolving business model, or estimates or predictions of actions by suppliers; (iv) statements of future economic performance; (v) statements of assumptions underlying other statements and statements about the company or its business; and (vi) the company’s plans to obtain future project financing. You are cautioned not to rely on these forward-looking statements. These statements are based on current expectations of future events and thus are inherently subject to uncertainty. If underlying assumptions prove inaccurate or known or unknown risks or uncertainties materialize, actual results could vary materially from the company’s expectations and projections. These risks, uncertainties, and other factors include, among others: our ability to complete construction of our data center campuses as planned; the satisfaction of conditions to effectiveness under our lease agreements, including the execution and regulatory approval of related power supply agreements; whether or not our customers exercise the renewal options under their leases with us; the lead time of customer acquisition and leasing decisions and related internal approval processes; changes to artificial intelligence and HPC infrastructure needs and their impact on future plans; costs related to the HPC operations and strategy; our ability to timely deliver any services required in connection with completion of installation under lease agreements; our ability to raise additional capital to fund the ongoing datacenter construction and operations; our ability to obtain financing of datacenter leases and more broadly for our development and general corporate activities; our dependence on principal customers, including our ability to execute and perform our obligations under our leases with key customers; our ability to timely and successfully build new hosting facilities with the appropriate contractual margins and efficiencies; power or other supply disruptions and equipment failures; the inability to comply with regulations, developments and changes in regulations; cash flow and access to capital; availability of financing to continue to grow our business; decline in demand for our products and services; maintenance of third party relationships; and conditions in the debt and equity capital markets. A further list and description of these risks, uncertainties, and other factors can be found in the company’s most recently filed Annual Report on Form 10-K and Quarterly Reports on Form 10-Q, including in the sections captioned “Forward-Looking Statements” and “Risk Factors,” and in the company’s subsequent filings with the Securities and Exchange Commission. Copies of these filings are available online at www.sec.gov, on the company’s website (www.applieddigital.com) under “Investors,” or on request from the company. Information in this press release is as of the dates and time periods indicated herein, and the company does not undertake to update any of the information contained in these materials, except as required by law.



Media Contact
JSA (Jaymie Scotto & Associates)
(856) 264-7827
jsa_applied@jsa.net

Investor Relations Contacts
Matt Glover or Ralf Esper
Gateway Group, Inc.
(949) 574-3860
APLD@gateway-grp.com

FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

How much of Applied Digital’s Polaris Forge 2 data center is ready for service?

The first 25 MW data hall reached Ready for Service on schedule. Applied Digital commissioned the base infrastructure for the first 75 MW, but the remaining 50 MW in that phase still needs fit-out and customer delivery.

How does Applied Digital commission each 150 MW building at Polaris Forge 2?

Applied Digital commissions each 150 MW building in two 75 MW phases. Three 25 MW data halls are tested and commissioned together in each phase.